•'  --.. N ,

                        -    :V-'
      EVALUATION OF THE FEASIBILITY



   OF TOTAL CONVERSION TO COAL FIRING



           20-PLANT REPORT



              APPENDICES




                L - X
              PEDCo ENVIRONMENTAL

,-   v,      ',.   .
	)
               ?

     .•-/:-
'• 	  I .

-------
                                PEDCo  ENVIRONMENTAL-
                                                11-499 CHESTER ROAD
                                              CINCINNATI. OHIO 45246
                                                      (513) 782-4700
                   EVALUATION OF  THE FEASIBILITY

                OF TOTAL CONVERSION TO COAL FIRING

                         20-PLANT REPORT

                            APPENDICES


                              L -  X


                           Prepared by

                     PEDCo Environmental,  Inc.
                        11499 Chester Road
                      Cincinnati,  Ohio  45246

              EPA Project Officer:   Richard Atherton



                           Prepared for

               U.S. ENVIRONMENTAL PROTECTION AGENCY
             'Strategies and Air  Standards Division
                   Pollutant Strategies Branch
                     Research Triangle Park,
                      North Carolina  27711
                        September 24,  1978
       !,  :l ,1 'll,.
       -JMlSi.,.
CHeSTER TOWERS
                                BRANCH OFFICES
 Crown Center
Kannes City Mo.
                                        C(-.«ool Hill. N.C.

-------
                         APPENDIX L




                     LOVETT POWER PLANT
LOVETT POWER PLANT                                        L-l

-------
                            CONTENTS
Lovett Power Plant Survey Form

Lovett Power Plant Photographs
                                                   Page

                                                   L-4

                                                   L-17
Number
 L-l
 L-2
 L-3
                             FIGURES
Site Plan Showing Possible Location of Major
Components for the Sodium Solution Regenerable
System for Boilers 3, 4, and  5 at the Lovett
Power Plant

Site Plan showing the Possible Locations of
Major Components for the Limestone System  for
Boilers 3, 4, and 5 at the Lovett Power Plant

Site Plan Showing Possible Locations of New
ESP's for Boilers 3, 4, and 5 at the Lovett
Power Plant
                                                   Page
                                                            L-27
                                                            L-33
                                                            L-38
Number
 L-l
 L-2
 L-3
                             TABLES
Estimated Capital Cost of a Sodium Solution
Regenerable System for Boilers 3, 4, and 5 at
the Lovett Power Plant (1978)

Estimated Annual Operating Cost of a Sodium
Solution Regenerable System for Boilers 3, 4,
and 5 at the Lovett Power Plant (1978)

Retrofit Equipment and Facilities for the
Sodium Solution Regenerable System for Boilers
3, 4, and 5 at the Lovett Power Plant
                                                            Page
                                                            L-21
                                                            L-23
                                                            L-24
LOVETT POWER PLANT
                                                  L-2

-------
                        TABLES  (continued)

Number                                                       Page

  L-4       Retrofit Equipment Dimensions  Required  for  the
           Sodium  Solution  Regenerable  System  for  Boilers
           3,  4, and  5  at the Lovett  Power  Plant              L-25

  L-5       Estimated  Capital Cost of  a  Limestone Scrubbing
           System  for Boilers 3, 4, and 5 at the Lovett
           Power Plant  (1978)                                 L-27

  L-6       Estimated  Annual Operating Costs of a Limestone
           Scrubbing  System for Boilers 3,  4,  and  5  at the
           Lovett  Power Plant  (1978)                          L-29

  L-7       Retrofit Equipment and Facilities Required  for
           the Limestone Scrubbing System for  Boilers  3,
           4,  and  5 at  the Lovett Power Plant                 L-30

  L-8       Retrofit Equipment Dimensions Required  for  the
           Limestone  Scrubbing System for Boilers  3, 4, and
           5 at the Lovett Power Plant                        L-31

  L-9       Estimated  Capital Cost of  Electrostatic
           Precipitators for Boilers  3, 4,  and 5 at  the
           Lovett  Power  Plant (1978)                          L-33

  L-10      Estimated  Annual Operating Cost  of  Electrostatic
           Precipitators for Boilers  3, 4,  and 5 at  the
           Lovett  Power Plant (1978)                          L-34

  L-ll      Electrostatic Precipitator Design Values  for
           Boilers 3  and 4 at the Lovett Power Plan           L-35
LOVETT POWER PLANT                                          L-3

-------
                                                  OMB No. 158S 74023
                   POWER PLANT SURVEY FORM


A.  COMPANY INFORMATION:

    1. COMPANY NAME:  Orange & Rockland Utilities, Inc.

    2. MAIN OFFICE:  75 West Route 59, Spring Valley, New York 10977

    3. RESPONSIBLE OFFICER:  Kenneth B. Field

    4. POSITION:  Assistant Vice President

    5. PLANT NAME:  Lovett Generating Station

    6. PLANT LOCATION: Tomkins Cove, Town of Stony Point, Rockland
                        County, New York
    7. RESPONSIBLE OFFICER AT PLANT LOCATION:

    8. POSITION:

    9. POWER POOL
    DATE INFORMATION GATHERED:
    PARTICIPANTS IN MEETING:

    B. Baxter, Jr.
    K. B. Field
    Gerard J. Bogin
    C. F. Wilkinson
    Barry Tornich
    Thomas C. Ponder, Jr.
    Alan J. Sutherland
    Douglas A. Paul
Orange and Rockland Utilities, Inc.
Orange and Rockland Utilities, Inc.
Orange and Rockland Utilities, Inc.
Orange and Rockland Utilities, Inc.
U.S. Environmental Protection Agency
PEDCo Environmental, Inc.
PEDCo Environmental, Inc.
PEDCo Environmental, Inc.
 LOVETT  POWER  PLANT
                                 L-4

-------
     B.
M
13
o

w
to

13

£
z
ATMOSPHERIC EMISSIONS
1. PARTICULATE EMISSIONS3
LB/MM BTU
GRAINS/ACF
LB/HR (FULL LOAD)
TONS/YEAR ( )
2. APPLICABLE PARTICULATE EMISSION
REGULATION
a) CURRENT REQUIREMENT
AQCR PRIORITY CLASSIFICATION
REGULATION & SECTION NO.
LB/MM BTU

b) FUTURE REQUIREMENT (DATE: )
REGULATION & SECTION NO.
LB/MM BTU
3. SO2 EMISSIONS3
LB/MM BTU
LB/HR (FULL LOAD)
TONS/YEAR ( )
4. APPLICABLE SO EMISSION REGULATION
a) CURRENT REQUIREMENT
REGULATION & SECTION NO.
LB/M:-! BTU

b) FUTURE REQUIREMENT (DATE: )
REGULATION {, SECTION NO.
LB/Mi-1 BTU
Boiler number
1





NYSDEC












2


















3


















4
.041*




Part 227
.10






NA




5
.096*




Part 227
.10






NA




     a)  Identify v/hether results are from stack tests or  estimates

       NOTE: Analysis based  on  stack  tests  burning .3% Sulfur Oil

-------
C.  SITE DATA
    1. U.T.M. COORDINATES.
    2. ELEVATION ABOVE  MEAN  SEA LEVEL (FT)	
    3. SOIL DATA:   BEARING VALUE	
            PILING  NECESSARY	
    4. DRAWINGS REQUIRED
       PLOT PLAN OF SITE  (CONTOUR)
       EQUIPMENT LAYOUT AND  ELEVATION
       AERIAL PHOTOGRAPHS OF  SITE INCLUDING POWER PLANT,
       COAL STORAGE AND ASH  DISPOSAL AREA
    5. HEIGHT OF TALLEST BUILDING AT PLANT SITE OR
       IN CLOSE PROXIMITY TO  STACK (FT.  ABOVE GRADE)
    6. HEIGHT OF COOLING TOWERS (FT.  ABOVE GRADE):
 LOVETT POWER PLANT                                          L-6

-------
o
<
w
H
t-3

13
O
&
M
£
z
     D.
BOILER DATA
1. SERVICE: BASE LOAD
STANDBY, FLOATING, PEAK
2. TOTAL HOURS OPERATION (1975)
3. AVERAGE CAPACITY FACTOR (1975)
4 . SERVED BY STACK NO .
5 . BOILER MANUFACTURER
6. YEAR BOILER PLACED IN SERVICE
7. REMAINING LIFE OF UNIT
8. GENERATING CAPACITY (MW)
RATED
MAXIMUM CONTINUOUS
PEAK
9- FUEL CONSUMPTION: GAS 103 FT3/HR
COAL OR OIL RATED 100%OIL BBL/I
COAL TONS/HR
(TPH) OR (GPH) MAXIMUM CONTINUOUS
PEAK
10. ACTUAL FUEL CONSUMPTION GAS 10 J MCF
COAL (TPY) (1975) 103 TONS
OIL (GPY) (1975) 10 BBLS
11. HEAT RATE BTU/KWHR GAS
COAL
OIL
12. WET OR DRY BOTTOM
13. FLY ASH REINJECTION (YES OR NO)
14. STACK HGT ABOVE GRADE (FT.)
15. I.D. OF STACK AT TOP (INCHES)
Boiler number
1

119.86
0.72
1
B&W+
1949

19.1



R 41.6
9.6

11.8
1.490
-
_
?.-\t Qf!7
DRY-
NO
175
83
2

108.04
0.72
2
B&W+
1951

20



41.6
9.6

12.9
1.290
-
_
?4,?qi
DRY
NO
175
83
3

2845.31
17.24
3
CE°
1955

63



11Q.O
25.0

67.9
200.78
-
_
1 3, 215
DRY
NO
175
150
4

6,307.16
36.86
4
FW*
1966

202.1


1500
- 260
60.0

1402.6
810.09
-
9200
10,100
DRY
NO
212
156
5

8,116.51
47.68
5
B&W-+
1969

200.6


1528
275
- 65.0

1454.8
1360.5
-
9500
10,200
DRY
NO
245
192
              * FW - FOSTER WHEELER,  CORP.

      Notes:  + B&W -.BABCOCK  & WILCOX,  CO.

              ° CE - COMBUSTION ENGINEERING

-------
f
o
i
16. FLUE GAS CLEANING EQUIPMENT
a) MECHANICAL COLLECTORS
MANUFACTURER
TYPE
EFFICIENCY: DESIGN/ACTUAL (%)
MASS EMISSION RATE:
(GR/ACF)
(#/HR)
(#/MM BTU)
b) ELECTROSTATIC PRECIPITATOR
MANUFACTURER
TYPE
EFFICIENCY: DESIGN/ACTUAL (%}
MASS EMISSION RATE
(GR/ACF)
(#/HR)
(#/MM BTU)
NO. OF IND. BUS SECTIONS
TOTAL PLATE AREA (FT^)
FLUE GAS TEMPERATURE
@ INLET ESP @ 100% LOAD (°F)
17. EXCESS AIR: DESIGN/ACTUAL (%)

1
WEST+
MCTA
85/-



NA









25
Boiler number
f.
WEST*
MCTA
85/-



NA









25
3
PRATT0
MCTA
85/-



NA









20
4
NA





COTT*
E
95/-







20
5
NA





COTT*
E
95/-







20
tr1
 i
CD
     Notes: * COTT - RESEARCH-COTTRELL,  INC.

            + WESTERN PRECIPITATION DIVISION

            0 PRATT DANIEL  MECHANICAL PRECIPITATOR

-------
 o

 w
 O
 s
 M
 £
 z
18. FLUE GAS RATE (ACFM)
@ 100% LOAD
@ 75% LOAD
@ 50% LOAD
19. STACK GAS EXIT TEMPERATURE (°F)a
@ 100% LOAD
@ 75% LOAD
§ 50% LOAD
20. EXIT GAS STACK VELOCITY (FPS)a
§ 100% LOAD
@ 75% LOAD
@ 50% LOAD
21. FLY ASH: TOTAL COLLECTED (TONS/YEAR)
DISPOSAL METHOD
DISPOSAL COST ($/TON)
22. BOTTOM ASH: TOTAL COLLECTED (TONS/
DISPOSAL METHOD YEAR)
DISPOSAL COST ($/TON)
23. EXHAUST DUCT DIMENSIONS @ STACK
24. ELEVATION OF TIE IN POINT TO STACK
25. SCHEDULED MAINTENANCE SHUTDOWN
(ATTACH PROJECTED SCHEDULE)
Boiler number
1
110,000
61,600
27,500
335
300
280
49.0
27.4
12.2








2
125,000
70,000
31,200
335
300
280
55.7
31.2
13.9








3
252,000
141,800
63,000
310
300
225
34.1
19.1
8.0
i, "> i f\ o r\







4
648,000
362,880
162,000
300
285
250
85.5
38.21
17.0








5
785,000
440,980
196,280
288
286
267
68.5
38.3
17.3







f
I
VD
       a) Identify  source  of  values  (test or estimate)


       Notes:

-------
f
s
w
o
s
M
E . I . D . FAN DATA
1. MAXIMUM STATIC HEAD (IN. W.G.)
2. WORKING STATIC HEAD (IN. W.G.)
Boiler number
1
NA
NA
2
NA
NA
3
NA
NA
4
NA
NA
5
NA
NA
      Notes:
t*
i

-------
     FLY ASH DISPOSAL AREAS
     1.  AREAS AVAILABLE (ACRES)
     2.  YEARS STORAGE (ASH ONLY)
     3.   DISTANCE FROM STACK (FT.)
     4.   DOES THIS PLANT HAVE PONDING
         PROBLEMS?  DESCRIBE IN ATTACHMENT
     COAL DATA
     1.   COAL SEAM,  MINE, MINE LOCATION
         a.
         b.
         c.
         d.
     2.   QUANTITY USED BY SEAM AND/OR MINE
         a.
         b.
         c.
         d.
     3.   ANALYSIS
         HHV (BTU/LB)
                    13,500 - Design
         S  (%)
         ASH  (%)
        MOISTURE  (%)
     4.   PPT  PERFORMANCE EXPERIENCED WITH LOW
         S  FUELS  (DESCRIBE IN ATTACHMENT)
H.
FUEL OIL DATA  (1975)
1.  TYPE   #6  F.O.
    2.   S CONTENT  (%)  Q. 33
     3.  ASH CONTENT  (%)
    4.  SPECIFIC  GRAVITY
    5.  HHV  (BTU/GAL)  144,533
I.
J.
NATURAL GAS HHV  (BTU/FT3)
COST DATA
ELECTRICITY
1026
    FUEL:  COAL
                     GAS
      OIL
    WATER
    STEAM
    TAXES ON A.P.C. EQUIPMENT:   STATE SALES
       FEDERAL PROPERTY TAX
LOVETT POWER  PLANT
                                                             L-ll

-------
 K.  PLANT SUBSTATION CAPACITY

     APPROXIMATELY WHAT PERCENTAGE OF RATED
     STATION CAPACITY CAN PLANT  SUBSTATION
     PROVIDE?

     NORMAL LOAD ON  PLANT SUBSTATION?

     VOLTAGE AT WHICH POWER  IS AVAILABLE?

 L.  ADDITIONAL INFORMATION

         F.E.A. LETTER
  M,
OIL/GAS TO COAL CONVERSION DATA

1.  HAS THE BOILER EVER BURNED COAL?
      2.
Boiler No.
Yes or No.
1
YES
2
YES
3
YES
4
YES
5
YES
    SYSTEM AVAILABILITY

    2.1  COAL HANDLING
         a.  Is the system still installed?

         b.  Will it operate?
         c.  Of the following items which
             need to be replaced:
             Unloading equipment
             Stack. Reclaimer
             Bunkers
             Conveyors
             Scales
             Coal Storage Area

    2.2  FUEL FIRING
         a.  Is the system still installed?

         b.  Will it operate?
         c.  Of the following items which
             need to be replaced:
             Pulverizers or  Crushers
             Feed Ducts
             Fans
             Controls

     2 . 3  GAS CLEANING
         a.  Is  the system  still  installed?

         b.  Will  it  operate?
         c.  Of  the  following  items which
             need  to  be  replaced:
             Electrostatic  Precipitator
             Cyclones
             Fly Ash  Handling  Equipment
              Soot  Blowers  - Air Compressors
             Wall  deslaggers
                                                   Yes [3
                                                   YesS
                                                       0
                                                    YesD
                                                       D
                                                       D
                                                       D
                                                    Yes0
                                                    YesD
                                                       D
                                                       D
                                                       D
                                                       D
 No Q
   D
Yes D
a
a
a
a
a
NO D
a
a
a
•a
a
LOVETT POWER PLANT
 NO D
   a
 NO a
    a
    D
    a
 NO a
    a
 No D
    D
    a
    a
    D
L-12

-------
         2.4  ASH HANDLING
              a.  Is the system still installed?   YesH    NoD
              b.  Will it operate?                     0       Q
              c.  Of the following items which
                  need to be replaced:
                  Bottom Ash Handling              Yes Q    NoD
                  Ash Pond                             n       D
LOVETT POWER PLANT                                         L_13

-------
     N.   SUPPLEMENTARY  CONTROL  SYSTEM DATA
1.   DOES THE PLANT NOW HAVE A SUPPLEMENTAL  CONTROL
    SYSTEM (SCS)?                                      Yes
    If yes, attach a description  of the  system.

2.   IS THE PLANT CAPABLE OF SWITCHING  TO LOW
    SULFUR FUELS?
    2.1   Storage capacity for low sulfur fuels
         (tons,  bbls, days)
    2.2  Bunkers available for low sulfur coal
         storage?                                      Yes
    2.3  Handling facilities available for  low
         sulfur  fuels                                  Yes

         If yes, describe 	
                                                                          No
                                                                Yes  Q   No
                                                                          No


                                                                          No
         3.
    2.4  Time required  to  switch  fuels and  fire
         the low sulfur fuel  in the  boiler  (hrs)?_

    IS THE PLANT CAPABLE OF LOAD  SHEDDING?

    If yes, discuss  	
        4.   IS THE PLANT CAPABLE OF LOAD SHIFTING?

             If yes, discuss 	:	
         5.
    POWER PLANT  MONITORING  SYSTEM

    5.1   Existing  system

         a.   Air quality  instrumentation

             (1)  Sulfur  Oxides  - Continuous
                                - Intermittent
                                - Static

             (2)  Suspended  particulates
                                - Intermittent
                                - Static

             (3)  Other  (describe)	
                     Meteorological instrumentation
                     If yes, describe    NO	
                                                       Yes
                                                       Yes
                                                                          N°  n
                                                                          No
                                                                Yes  [x]   No
                                                             Number     Type
                                                                       Sulphur Pic ' 2
                                                                     Dust Colled
                 c.   Is the monitoring data available?
                 d.   Is the monitoring data reduced and
                      analyzed?
                  e.   Provide map of monitoring locations
Yes

Yes
                                                                 No

                                                                 No
LOVETT POWER PLANT
                                                                        L-14

-------
         5.2  Proposed system                                Yes  Q   No  \~\
              If yes, describe and provide map
              a.  Air monitoring  instrumentation           Number     Type
                  (1)  Sulfur oxides  -  Continuous          	     	
                                     -  Intermittent        	     ZZZ
                                     -  Static              	     ZZZ
                  (2)  Suspended  particulate
                                     -  Intermittent        	
                                     -  Static              ZHZ
                  (3)  Other  (describe) 	
              b.  Meteorological  instrumentation
                  If yes,  describe 	
LOVETT POWER PLANT                                                L_15

-------
      Photo No. 1.  View from the roof of the ESP serving
      Boiler 5 looking at the tie-in of Boiler 4's ESP to
      the stack.
       Photo No. 2.  View from ground level facing north
       showing the crusher house and the conveyors.  A
       view of the Lovett plant is in the background.
LOVETT POWER PLANT
L-16

-------
      1
   Photo No.  3.   View  from ground level facing southwest
   showing electrical  substation.
                                                  :•• BBft.
   Photo  No.  4.   View from ground level facing south showing
   the  car shaker and the thaw house.
LOVETT POWER PLANT
                                                           L-17

-------
  Photo  No.  5.   View from the  roof  of  the ESP serving Boiler
  5  facing  south showing  sludge  ponds  and stack 4.   The
  Hudson River,  the  rock  quarry,  and the  surrounding area
  are  shown in  the background.
  Photo No.  6.   View from the roof of the ESP serving Boiler
  5 facing north showing the parking lot and the warehouse.
LOVETT POWER PLANT
                                                            L-18

-------
 Photo No.  7.  View  from the  roof of  the  ESP  serving  Boiler
 5  facing northeast  showing the  Hudson  River,  Indian  Power
 Plant, and the  surrounding area.
 Photo No.  8.   View from the roof of the ESP serving Boiler
 5 facing southwest showing the residual fuel oil hold tank.
 The rock quarry and the surrounding area are in the back-
 ground.
LOVETT POWER PLANT
                                                           L-19

-------
  Photo No.  9.   View from the roof of the ESP serving Boiler
  5 facing north showing the Hudson River and the surrounding
  area.
  Photo  No.  10.   View from the  roof  of  the  ESP  serving Boiler
  5  facing west  showing  the surrounding area.
LOVETT POWER PLANT
L-20

-------
         TABLE L-l.  ESTIMATED CAPITAL COST OF A SODIUM
     SOLUTION REGENERABLE SYSTEM FOR BOILERS 3, 4, AND 5 AT
                  THE LOVETT POWER PLANT  (1978)
Direct Costs
A.   Soda Ash Preparation
     Storage silos
     Vibrating feeders
     Storage tanks
     Agitators
     Pumps and motors

B.   S02 Scrubbing
     Absorbers
     Fans and motors
     Pumps and motors
     Reheaters
     Soot blowers
     Ducting
     Valves

C.   Purge Treatment
     Refrigeration unit
     Heat exchangers
     Tanks
     Dryer
     Elevator
     Pumps and motors
     Centrifuge
     Crystallizer
     Storage silo
     Feeder
(continued)
LOVETT POWER PLANT
                                   Total A =
                                   Total B =
                                   Total C =
                                                        55,000
                                                         6,000
                                                        26,000
                                                        26,000
                                                         2,000
$    115,000

$ 10,728,000
   1,186,000
     314,000
   1,875,000
   1,630,000
   2,711,000
     376,000
$ 18,820,000

$    306,000
      46,000
      60,000
      27,000
      15,000
     252,000
     611,000
     733,000
      55,000
       6,000
$  2,111,000
        L-21

-------
TABLE L-l (continued)
     Regeneration
     Pumps and motors                             $    223,000
     Evaporators and reboilers                       2,867,000
     Keat exchangers                                   374,000
     Tanks                                              51,000
     Stripper                                          115,000
     Blower                                            122,000
                                   Total D =      $  3,752,000
     Particulate Removal
     Venturi scrubber                             $  4,710,000
     Tanks                                             140,000
     Pumps and motors                                  550,000
                                   Total E =      $  5,400,000
     Total direct costs = A + B + C + D + E = F=$ 30,198,000
Indirect Costs
     Interest during construction                 $  3,020,000
     Field labor and expenses                        3,020,000
     Contractor's fee and expenses                   1,510,000
     Engineering                                     3,020,000
     Freight                                           378,000
     Offsite                                           906,000
     Taxes                                                 000
     Spares                                            151,000
     Allowance for shakedown                         1,510,000
     Acid plant                                      1,476,000
               Total indirect costs G =           $ 14,991,000
               Contingency H =                       9,038,000
               Total =F+G+H=                $ 54,227,000
               Coal conversion costs                 3,424,000
               Grand total                        $ 57,651,000
               $/kW                                     123.79
 LOVETT POWER PLANT                                        L~22

-------
     TABLE L-2.  ESTIMATED ANNUAL OPERATING COST OF A SODIUM
      SOLUTION REGENERABLE SYSTEM FOR BOILERS 3, 4, AND 5
                AT THE LOVETT POWER PLANT (1978)
                    Quantity       Unit Cost      Annual Cost
Raw Materials
Soda ash
Utilities
0.45 ton/h $90.3/ton $ 139,000
Process water   2,068.3 gal/min    0.069 $/103 gal      29,000
Cooling water   8.8 x 103 gal/min  0.017 $/103 gal      31,000
Electricity     10,015 kW          55.7 mills/kWh    1,873,000
Reheat steam    71.2 106 Btu/h     2.835 $/106 Btu     679,000
Process steam   126.7 106 Btu/h    2.835 $/106 Btu   1,209,000

Operation Labor

Direct labor        4 men/day      $10.67/man-hour     374,000
Supervision         15% of direct labor                 56,000

Maintenance

Labor and materials  4% of fixed investment          2,169,000
Supplies            15% of labor and materials         325,000

Overhead

Plant             50% of operating and maintenance   1,462,000
Payroll           20% of operating labor                86,000

Fixed Costs

Depreciation        (5.00%)
Interim replacement (0.35%)
Insurance           (0.30%)
Taxes               (4.00%), Z = 20.85% of fixed
                                   investment
Capital cost       (11.20%)
Total fixed cost                                  $ 11,306,000

Total cost                                        $ 19,738,000

Credits (byproducts)

Sulfuric acid       6.30 tons/h    $65.24/ton       (1,382,000)
Na2SO4              0.45 ton/h     $79.34/ton         (122,000)

Total byproduct credits                           $ (1,504,000)
Fuel credit                                        (11,222,000)

Net annual cost                                   $  7,012,000
Mills/kWh                                                 4.44

LOVETT POWER PLANT                                        L-23

-------
 Table L-3.  RETROFIT EQUIPMENT AND FACILITIES FOR  THE

   SODIUM SOLUTION REGENERABLE SYSTEM FOR BOILERS 3,

      4, AND 5 AT THE LOVETT POWER PLANT
  Module
Description
 Number
Required
    Size/Capacity
Absorbers

Flue gas fans

Na-CO., storage

Na-CO, preparation

SO.., regeneration

Purge treatment

Sulfuric acid plant
   5

   5

   1

   1

   1

   1

   1
93.4 MW capacity unit

Scaled to train size

324 tons (30-day storage)

900 Ib/hr,  Na^CO.,

6746 Ib/hr,  S02

900 Ib/hr,  Na2S04

23.5 tons/day, H S04
LOVETT POWER PLANT
                                     L-24

-------
        Table  L-4.   RETROFIT  EQUIPMENT DIMENSIONS  REQUIRED

      FOR THE  SODIUM SOLUTION REGENERABLE  SYSTEM FOR BOILERS

           3,  4, AND 5  AT  THE LOVETT  POWER PLANT
      Item
 Number
required
     Dimensions, ft
 Na_CO_ storage

 Absorber feed surge
  tank

 Turbulent contact
  absorbers

 Regeneration plant

 Purge treatment plant

 Acid plant
   1

   1
   1

   1

   1
13 diam x 26 high

24 diam x 24 high


45 high x 15 wide x 39.4 long


34 wide x 130 long

41 wide x 170 long

57 wide x 124 long
LOVETT POWER PLANT
                                                          L-25

-------
f
s
w
13
i
M
I
                                                                A  PURGE TREATMENT AND
                                                                   S02  REGENERATION

                                                                B  ACID PLANT
                                                                C  SCRUBBERS
                                                                D  STORAGE SILO
                                                                E  SOLUTION TANK
i
ro
        Figure L-l.   Site plan showing possible location of major components for

              the  sodium solution  regenerable system  for Boilers 3, 4  and  5

                                at  the  Lovett power plant.

-------
        TABLE L-5.  ESTIMATED CAPITAL COST OF A LIMESTONE
         SCRUBBING SYSTEM FOR BOILERS 3,  4, AND 5 AT THE
                    LOVETT POWER PLANT (1978)

Direct Cost
A.   Limestone Preparation
     Conveyors                                    $   410,000
     Storage silo                                      76,000
     Ball mills                                       642,000
     Pumps and motors                                 128,000
     Storage tanks                                     93,000
                              Total A =           $ 1,349,000
B.   Scrubbing
     Absorbers                                    $ 9,950,000
     Fans and motors                                1,519,000
     Pumps and motors                                 786,000
     Tanks                                            611,000
     Reheaters                                      2,161,000
     Soot blowers                                     652,000
     Ducting and valves                             3,242,000
                              Total B =           $18,921,000
     Sludge Disposal
     Clarifiers                                   $   197,000
     Vacuum filters "                                  299,000
     Tanks and mixers                                    8,000
     Fixation chemical storage                         26,000
     Pumps and motors                                   54,000
     Sludge pond                                    1,347,000
     Mobile equipment                                   64,000
                              Total C =           $ 1,995,000

(continued)
 LOVETT POWER PLANT                                        L-27

-------
TABLE L-5 (continued)
D.    Particulate Removal
     Venturi scrubber                             $  5,428,000
     Tanks                                             165,000
     Pumps and motors                                  225,000
                                   Total D =      $  5,818,000
     Total direct costs = A + B + C + D = E =     $ 28,083,000
Indirect Costs
     Interest during construction                 $  2,808,000
     Field overhead                                  2,808,000
     Contractor's fee and expenses                   1,404,000
     Engineering                                     2,808,000
     Freight                                           351,000
     Offsite                                           842,000
     Taxes                                                 000
     Spares                                            140,000
     Allowance for shakedown                         1,404,000
               Total indirect costs F =           $ 12,565,000
               Contingency G =                       8,130,000
               Total =E+F+G=                $ 48,778,000
               Coal conversion costs                 3,424,000
               Grand total                        $ 52,202,000
               $/kW                                     112.09
LOVETT POWER PLANT                                        L-28

-------
   TABLE L-6.  ESTIMATED ANNUAL OPERATING COSTS OF A LIMESTONE
         SCRUBBING SYSTEM FOR BOILERS 3, 4, AND 5 AT THE
                    LOVETT POWER PLANT  (1978)

	Quantity	Unit Cost	Annual Cost
Raw Materials                                        ~~~

Limestone           8.8 tons/h     $16.81/ton     $    498,000
Fixation chemicals 21.8 tons/h     $ 2.20/ton          162,000

Utilities

Water            174.1 gal/min     0.068 $/103 gal       2,000
Electricity      9395 kW           55.6 mills/kWh    1,758,000
Fuel for reheat  82.0 x 10b Btu/h  2.835 $/10b Btu     782,000

Operating Labor

Direct labor        4 men/day      $10.67/man-hour     374,000
Supervision         15% of direct labor                 56,000

Maintenance

Labor and materials 4% of fixed investment           1,951,000
Supplies           15% of labor and material           293,000

Overhead

Plant              50% of operation and maintenance  1,337,000
Payroll            20% of operating labor               86,000

Trucking

Bottom/fly ash and                                   3,243,000
 sludge removal

Fixed Costs

Depreciation         (5.00%)
Interim replacement  (0.35%), E = 20.85% of fixed
                                   investment
Insurance            (0.30%)
Taxes                (4.00%)
Capital costs       (11.20%)
Total fixed charges                                 10,170,000

Total costs                                       $ 20,712,000
Fuel credit                                         (11,222,000)

Net annual cost                                   $  9,490,000
Mills/kWh                                                  6.01
LOVETT POWER PLANT                                        L-29

-------
          Table L-7.  RETROFIT EQUIPMENT AND FACILITIES

        REQUIRED FOR THE LIMESTONE SCRUBBING SYSTEM FOR

       BOILERS 3, 4, AND 5 AT THE LOVETT POWER PLANT
    Module Description
 Number
Required
    Size/Capacity
   Limestone storage

   Limestone slurry

   Turbulent contact

     absorbers

   Flue gas fans
   1

   1

   5
6336 tons (30 day storage)

8.8 ton/hr limestone

93.4 MW capacity units



Scaled to train size
LOVETT POWER PLANT
                                                           L-30

-------
           Table  L-8.   RETROFIT  EQUIPMENT DIMENSIONS  REQUIRED

        FOR THE LIMESTONE  SCRUBBING  SYSTEM FOR BOILERS  3,  4,  AND

                   5 AT THE  LOVETT POWER  PLANT
        Item
  Limestone storage pile

  Limestone silos

  Limestone slurry tanks

  Ball mill building

  Turbulent contact

    absorbers

  Clarifiers

  Vacuum filter building
 Number
Required
   1

   3

   1

   1

   5



   2

   1
     Dimensions, ft
115 W x 117 L

14 diam x 31 height

45 diam x 20 height

30 W x 30 L

45 height x 15 width x 29 length



49 diam x 20 height

30 W x 30 L
LOVETT POWER PLANT
                              L-31

-------
K


TJ
                                                                 A  SCRUBBER
                                                                 B  SLURRY TANK
                                                                 C  LIMESTONE  SILOS
                                                                 D  BALL MILL  BUILDING
                                                                 E  CLARIFIER
                                                                 F  VACUUM FILTER BUILDING
NJ
   Figure  L-2.   Site plan  showing the possible locations  of  major
components for  the limestone  system for Boilers 3, 4, and  5  at the
                         Lovett power plant.

-------
       TABLE L-9.  ESTIMATED CAPITAL COST OF ELECTROSTATIC
           PRECIPITATORS FOR BOILERS 3, 4, AND 5 AT THE
                    LOVETT POWER PLANT (1978)
Direct Costs

ESP                                               $  9,701,000

Ash handling                                         1,563,000

Ducting                                              1,171,000
                              Total direct costs  $ 12,435,000

Indirect Costs

Interest during construction  8% of direct costs  $    995,000

Contractor fee               10% of direct costs     1,244,000

Engineering                   6% of direct costs       746,000

Freight                    1.25% of direct costs       155,000

Offsite                       3% of direct costs       373,000

Taxes         '                0% of direct costs           000

Spares                        1% of direct costs       124,000

Allowance for shakedown       3% of direct costs       373,000
               Total indirect costs               $  4,010,000

               Contingency                           3,289,000
               Total                              $ 19,734,000

               Coal conversion costs                 3,424,000
               Grand total                        $  23,158,000

               $/kW                                      49,73
 LOVETT POWER PLANT                                        L-33

-------
  TABLE L-10.  ESTIMATED ANNUAL OPERATING COST OF ELECTROSTATIC
          PRECIPITATORS FOR BOILERS 3, 4, AND 5 AT THE
                    LOVETT POWER PLANT (1978)
Utilities
Electricity
Water
Quantity Unit Cost
1851 kW 55.7 mills/kWh
9784 x 103/gal $0.01/103 gal
Annual Costs
$ 346,000
1,000
Operating Labor

Direct labor     0.5 man/shift  $10.67/man-hour        139,000
Supervision      15% of direct labor                    21,000

Maintenance

Labor and materials  2% of fixed investment            395,000
Supplies            15% of labor and materials          59,000

Overhead

Plant               50% of operating and maintenance   307,000
Payroll             20% of operating labor              32,000

Trucking

Bottom/fly ash                                       1,856,000
 removal

Fixed costs

Depreciation        (4.00%)
Interim replacement (0.35%), I = 19.85% of fixed
                                    investment
Insurance           (0.30%)
Taxes               (4.00%)
Capital cost        (11.20%)
Total fixed cost                                     3,917,000
Total cost                                        $  7,073,000
Fuel credit                                         (11,222,000)
Net annual credit                                 $  (4,149,000)
Mills/kWh                                                 (2.63)
LOVETT POWER PLANT                                        L-34

-------
         Table L-ll.   ELECTROSTATIC PRECIPITATOR DESIGN
                   VALUES FOR BOILERS 3 AND 4
                AT THE LOVETT POWER PLANT
Design Parameter
Collection efficiency, %
(Overall)
Specific collecting area,
ft2/1000 acfm
Total collecting area, ft2
Superficial velocity, fps
Overall ESP dimensions
(height x width x depth) , ft
excluding hopper dimensions
Value
3
98.66
449
113,200
4.0
30 x 35 x 43
4
98.66
399
258,700
4.0
27 x 100 x 37
LOVETT POWER PLANT
                                                           L-35

-------
       Table  L-ll(Continued).   ELECTROSTATIC  PRECIPITATOR

                   DESIGN  VALUES  FOR  BOILER  5

                AT  THE  LOVETT  POWER PLANT  (1976)
      Design Parameter
                                            Value
 Collection efficiency, %
    (Overall)

 Specific collecting area,
    ft2/1000 acfm
 Total collecting area,

 Superficial velocity, fps

 Overall ESP dimensions
 (height x width x depth) , ft
 excluding hopper dimensions
    98.66


     312


   245,300

     4.0

21 x 156 x 28
LOVETT POWER PLANT
                                                            L-36

-------
I
w
13
o
Si
w
f

OJ
              Figure L-3.  Site plan showing possible  locations of new ESP's for


                        Boilers 3, 4, and  5 at  the  Lovett power plant.

-------
                         APPENDIX M




                     MUSTANG POWER PLANT
MUSTANG POWER PLANT                                      M-l

-------
                            CONTENTS
Mustang Power Plant Survey Form

Mustang Power Plant Photographs
                                                  Page

                                                  M-4

                                                  M-16
Number
 M-l
                             FIGURES
Site Plan Showing Possible Locations of New
ESP's for Boilers 1 and 2 at the Mustang Power
Plant
                                                  Page
                                                            M-29
Number
 M-l
 M-2
 M-3
 M-4
 M-5
 M-6
                             TABLES
Estimated Capital Cost of Electrostatic Pre-
cipitators for Boilers 1 and 2 at the Mustang
Power Plant on High-Sulfur Coal  (1978)

Estimated Annual Operating Costs of Electro-
static Precipitator for Boilers 1 and 2 at the
Mustang Power Plant on High-Sulfur Coal (1978)

Electrostatic Precipitator Design Values for
Boiler 1 at the Mustang Power Plant on High-
Sulfur Coal Burning

Electrostatic Precipitator Design Values for
Boiler 2 at the Mustang Power Plant on High-
Sulfur Coal Burning

Estimated Capital Cost of Electrostatic Pre-
cipitators for Boilers 1 and 2 at the Mustang
Power Plant on Low-Sulfur Coal (1978)

Estimated Annual Operating Costs of Electro-
static Precipitators for Boilers 1 and 2 at the
Mustang Power Plant on Low-Sulfur Coal (1978)
                                                  Page
                                                            M-21
                                                            M-22
                                                            M-23
                                                            M-24
                                                            M-25
                                                            M-26
MUSTANG POWER PLANT
                                                  M-2

-------
                        TABLES  (continued)

Number                                                       Page

 M-7       Electrostatic Precipitator  Design  Values  for
           Boiler  1  at  the Mustang  Power  Plant  on
           Low-Sulfur Coal Burning                            M-27

 M-8       Electrostatic Precipitator  Design  Values  for
           Boiler  2  at  the Mustang  Power  Plant  on
           Low-Sulfur Coal Burning                            M-28
MUSTANG POWER PLANT                                         M-3

-------
                                                  OMB No. 158S 74023
                   POWER PLANT SURVEY FORM


A.  COMPANY INFORMATION;

    1. COMPANY NAME: Oklahoma  Gas  and Electric  Company

    2. MAIN OFFICE:  P.O.  Box  321,  Oklahoma  City,  Oklahoma   73101

    3. RESPONSIBLE OFFICER:   G. L.  Gibbons

    4. POSITION:  Vice  President

    5. PLANT NAME:  Mustang

    6. PLANT LOCATION:   Oklahoma,  Canadian Oklahoma  City  73127

    7. RESPONSIBLE OFFICER AT PLANT LOCATION:   K.A. Ketchersid

    8. POSITION:  Plant Superintendant

    9. POWER POOL   Southwest  Power Pool
    DATE INFORMATION GATHERED:    April 26, 1976
    PARTICIPANTS IN MEETING:
   George L. Gibbons  Oklahoma Gas & Electric Co.
   John D. Graham  Oklahoma Gas & Electric Co.
   V. T. Huckleberry  Oklahoma Gas & Electric Co.
   0. Wayne Beasley  Oklahoma Gas & Electric Co.
   Jerry Gouett  Oklahoma Gas & Electric Co.
   Jim Pollard  Oklahoma Gas & Electric Co.
   Pat Ryan  Oklahoma Gas & Electric Go.
   Cris Caenepeel  EPA - OAQPS
   Thomas C. Ponder, Jr.  PEDCo Environmental, Inc
   N. David Noe PEDCo Environmental, Inc.
   Richard T. Price  PEDCo Environmental, Inc.
 MUSTANG POWER PLANT                                       M_4

-------
          B
      z
      o
      O
      S
      w
ATMOSPHERIC EMISSIONS
1. PARTICULATE EMISSIONS3 (A . P . 42)
LB/MM BTU Gas-Firing Calc.
GRAINS/ACF
LB/HR (FULL LOAD)
TONS/YEAR (1975) Calc.
2. APPLICABLE PARTICULATE EMISSION
REGULATION
a) CURRENT REQUIREMENT
AQCR PRIORITY CLASSIFICATION
REGULATION & SECTION NO.
LB/MM BTU

b) FUTURE REQUIREMENT (DATE: )
REGULATION & SECTION NO.
LB/MM BTU
3. SO2 EMISSIONS3 (A. P. 42)
LB/MM BTU Gas-Firing Calc.
LB/HR (FULL LOAD)
TONS/YEAR (1975) Calc.
4. APPLICABLE SO2 EMISSION REGULATION
a) CURRENT REQUIREMENT
REGULATION & SECTION NO.
LB /:•"•! BTU

b) FUTURE REQUIREMENT (DATE: )
REGULATION & SECTION NO. *
LB/MM BTU
Boiler number
1
.014


19
AQCR
Section 6
0.25



.0006

< 1
Section 1
Ambient S


*
2
.014


19
184
. 2 , Figure
0.25



.0006

< 1
6.21
02 Standar


*





-
I








a









































_,         a)  Identify v.-hether results are from stack tests or estimates *Accordin9 to th« State of Oklahom

The Mustang plant must comply with Federal NSPS (i.e.  1.2 Ibs/mmBtu S02)  if converted to coal-firing.

-------
    SITE DATA
    1. U.T.M. COORDINATES  N  25°  33'  19"  W 97° 40'  2?"
    2. ELEVATION ABOVE MEAN SEA LEVEL (FT)   1237.5'
    3. SOIL DATA:  BEARING VALUE
            PILING NECESSARY    Had  to  pile  65'	
    4. DRAWINGS REQUIRED
       PLOT PLAN OF SITE  (CONTOUR)
       EQUIPMENT LAYOUT AND ELEVATION
       AERIAL PHOTOGRAPHS OF  SITE  INCLUDING POWER PLANT,
       COAL STORAGE AND ASH DISPOSAL AREA
    5. HEIGHT OF TALLEST BUILDING AT PLANT  SITE OR
       IN CLOSE PROXIMITY TO  STACK  (FT.  ABOVE GRADE)
    6. HEIGHT OF COOLING TOWERS (FT. ABOVE  GRADE):  39' 11"
MUSTANG POWER PLANT
                                                           M-6

-------
S
Z
o
O
5
W
*o
£
z
>. BOILER DATA
1. SERVICE: BASE LOAD
STANDBY, FLOATING, PEAK
2. TOTAL HOURS OPERATION (1975)
3. AVERAGE CAPACITY FACTOR (19 73
4. SERVED BY STACK NO.
5. BOILER MANUFACTURER
6 . YEAR BOILER PLACED IN SERVICE
7. REMAINING LIFE OF UNIT
8. GENERATING CAPACITY (MW)
RATED
MAXIMUM CONTINUOUS Gas
PEAK
9. FUEL CONSUMPTION:
COAL 9R-QJ£ RATED tons/hour
(T-PH) OR (GPH) MAXIMUM CONTINUOUS
PEAK
10. ACTUAL FUEL CONSUMPTION Gas (lOOOMG
COAL (TPY) (19 75}
OIL (GPY) (19 73
11. WET OR DRY BOTTOM
12. FLY ASH REINJECTION (YES OR NO)
13. STACK HGT ABOVE GRADE (FT.)
14. I.D. OF STACK AT TOP (INCHES)
Boiler number
1

7132.7
38.6
1
B & W*
1950


60


27

•)2,575
None
Non<=»
Dry
No
250
126
2

7868.1
44.2
»
2
B & W*
1951


58


27

2,710
None
N<^n°
Dry
Mr,
7Rn
126




























































•2.
I
     Notes:
                * B & W  -  The  Babcock & Wilcox Co.

-------
 G
 cn
 Z
 O
 o
 s
 w
 »

 T3
 tr1
 >
 Z
 •-3
15. FLUE GAS CLEANING EQUIPMENT
a) MECHANICAL COLLECTORS
MANUFACTURER
TYPE
EFFICIENCY: DESIGN/ACTUAL (%)
MASS EMISSION RATE:
(GR/ACF)
(#/HR)
(#/MM BTU)
b) ELECTROSTATIC PRECIPITATOR
MANUFACTURER
TYPE
EFFICIENCY: DESIGN/ACTUAL (%)
MASS EMISSION RATE
(GR/ACF)
(tf/HR)
(#/MM BTU)
NO. OF IND. BUS SECTIONS
TOTAL PLATE AREA (FT^)
FLUE GAS TEMPERATURE
@ INLET ESP @ 100% LOAD (°F)
16. EXCESS AIR: DESIGN/ACTUAL (%)
Boiler number
1
NA





NA









16/
2
NA





NA









16/






















































       Notes
 I
CO

-------
3
C
cn
1-3
CD
O
s:
ra
z
•-3
17. FLUE GAS RATE (ACFM)
@ 100% LOAD
@ 75% LOAD
@ 50% LOAD
18. STACK GAS EXIT TEMPERATURE (°F)a
@ 100% LOAD
@ 75% LOAD
@ 50% LOAD
19. EXIT GAS STACK VELOCITY (FPS)a
@ 100% LOAD
@ 75% LOAD
@ 50% LOAD
20. FLY ASH: TOTAL COLLECTED (TONS/YEAR)
DISPOSAL METHOD
DISPOSAL COST ($/TON)
21. BOTTOM ASH: TOTAL COLLECTED (TONS/
DISPOSAL METHOD YEAR)
DISPOSAL COST ($/TON)
22. EXHAUST DUCT DIMENSIONS @ STACK
23. ELEVATION OF TIE IN POINT TO STACK
24. SCHEDULED MAINTENANCE SHUTDOWN
(ATTACH PROJECTED SCHEDULE)
Boiler number
1
134,115
115,000
89,000
290
273
247
25.8
22.2
17.1







2
134,115
115,000
89,000
290
273
247
25.8
22.2
17.1


























































2
I
a) Identify  source of values  (test  or estimate)


Notes:

-------
 S
 G
 C/5
O
w
JO
£
z
E. I .D. FAN DATA
1. MAXIMUM STATIC HEAD (IN. W.C.)
2. WORKING STATIC HEAD (IN. W.C.)
Boiler number
1
14
8.2
2
14
8.2









      Notes :     No  Controls Presently

                Would Need Extra Capacity if ESP Added
3
I

-------
F.   FLY ASH DISPOSAL AREAS
     1.   AREAS AVAILABLE (ACRES)
     2.   YEARS STORAGE (ASH ONLY)
     3.   DISTANCE FROM STACK (FT.)
     4.   DOES THIS PLANT HAVE PONDING
         PROBLEMS?  DESCRIBE IN ATTACHMENT
     COAL DATA
     1.   COAL SEAM,  MINE, MINE LOCATION
         a.
         b.
         c.
         d.
     2.   QUANTITY USED BY SEAM AND/OR MINE
         a .
         b.
         c.
         d.
     3.   ANALYSIS
         GHV (BTU/LB)     12,971
         S  (%)            1.3
         ASH (%)          10.0
         MOISTURE (%)     10.5
     4.   PPT  PERFORMANCE EXPERIENCED WITH LOW
         S  FUELS  (DESCRIBE IN ATTACHMENT)
H.   FUEL  OIL  DATA
     1.  TYPE
     2.   S  CONTENT (%}
     3.   ASH  CONTENT (%)
     4.   SPECIFIC  GRAVITY
     5.  GHV  (BTU/GAL)	126.353  Natural  Gas  -  1037 Btu/ft3
     COST  DATA
     ELECTRICITY
     WATER
     STEAM
     PLANT  SUBSTATION CAPACITY
     APPROXIMATELY WHAT PERCENTAGE OF RATED
     STATION  CAPACITY CAN PLANT SUBSTATION
     PROVIDE?
    NORMAL  LOAD  ON PLANT SUBSTATION?
    VOLTAGE AT WHICH POWER IS AVAILABLE?
MUSTANG POWER PLANT                                         M-ll

-------
   K.   OIL/GAS TO COAL CONVERSION DATA

       1.   HAS THE BOILER EVER BURNED COAL?    Not Full Time-only for El  r<
Boiler No.
Yes or No.
1
Yes
2
Yes






       2.   SYSTEM AVAILABILITY
           2.1
           2.2
           2.3
COAL HANDLING

a.  Is the system still installed?

b.  Will it operate?
                                                    Yes
   D
   a
    Of the following items which
    need to be replaced:

    Unloading equipment
    Stack Reclaimer
    Bunkers
    Conveyors
    Scales
    Coal Storage Area
FUEL FIRING
a.  Is the system still installed?

b.  Will it operate?

c.  Of the following items which
    need to be replaced:

    Pulverizers or Crushers
    Feed Ducts
    Fans
    Controls
Yes D
   D



   D


YesD

   D
                                                    YesQ
                                                        D
                                                        D
                                                        Q
No D

  D
                                                             NO n
                                                                a
                                                                a
                                                                D
                                                                a
                                                                D
NoD
   a


NO a
GAS CLEANING

a.

b.

c.
                              - No equipment is currently installed
                    is the system still installed?   Yes Q    No Q

                    Will it operate?                    D       D

                    Of the following items which
                    need to be replaced:

                    Electrostatic Precipitator       YesQ    No D
                    Cyclones                            D       D
                    Fly Ash Handling Equipment          D       D
                    Soot Blowers - Air Compressors      Q       D
                    Wall deslaggers                     D       D
MUSTANG POWER PLANT
                                                           M-12

-------
          2.4  ASH HANDLING
              a.  Is  the  system  still  installed?    Yes B     No Q
              b.  Will  it operate?                     Q       0
              c.  Of  the  following  items  which
                  need  to be  replaced:
                  Bottom  Ash  Handling               Yes®     No [j
                  Ash Pond                             $       D
MUSTANG POWER PLANT                                       M-13

-------
     L.   SUPPLEMENTARY  CONTROL SYSTEM DATA
         1.   DHLS THE PLANT NOW HAVE A SUPPLEMENTAL CONTROL
             SYSTEM  (SCS)?                                       Yes  Q   No
             If yes, attach a description of the system.
         2.   IS THE  PLANT CAPABLE OF SWITCHING TO LOW
             SULEUR  FUELS?                                       Yes  Q   No
             2.1  Storage capacity for low sulfur fuels
                 (tons, bbls, days)
             2.2  Bunkers available for low sulfur coal
                 storage?                                       Yes  [|   No
             2.3  Handling facilities available for low
                 sulfur fuels                                   Yes       No
                 If yes, describe 	
            2.4  Time required to switch fuels and fire
                 the low sulfur fuel in the boiler (hrs)?
        3.   IS THE PLANT CAPABLE OF LOAD SHEDDING?
             If yes, discuss _
                                                                Yes       No
        4.   IS THE PLANT CAPABLE OF LOAD SHIFTING?
             If yes, discuss __
            __         Yes  [Jx]   No
        5.  POWER PLANT MONITORING SYSTEM
            5.1  Existing system                                Yes  [  |   No |   |
                 a.  Air quality instrumentation             Number     Type
                     (1)  Sulfur Oxides - Continuous         __     _
                                        - Intermittent       __     _
                                        - Static             _     _
                     (2)  Suspended participates
                                        - Intermittent       _     _
                                        - Static
                     (3)  Other (describe)	
                     Meteorological instrumentation
                     If yes, describe 	
                 c.  Is the monitoring data available?          Yes  jj   No  [~|
                 d.  Is the monitoring data reduced and
                     analyzed?                                  Yes  Q]   No  [j
MUSTANG POWER PLANT                                              M-14

-------
            b.2  Proposed system                                Yes  fj   No
                 If yes, describe	'_
                 a.  Air monitoring instrumentation           Number     Type
                     (1)  Sulfur oxides  -  Continuous          	     	
                                        -  Intermittent        	
                                        -  Static              	     	
                     (2)  Suspended particulate
                                        -  Intermittent        	      	
                                        -  Static              	     ~	
                     (3)  Other (describe) 	
                 b.  Meteorological  instrumentation
                     If yes,  describe  	 •
MUSTANG POWER PLANT                                             M~15

-------
       Photo No. 1  View from ground level facing west
       showing the induced fan house, duct work,
       and stack serving Boiler 1.
         Photo No. 2  View from the boiler house looking
         northwest.  Stacks 1 and 2 and their lead-in
         ducts are shown in the foreground of the photo.
         Cooling towers and oil storage tanks are shown
         in the background.
MUSTANG POWER PLANT
M-16

-------
          Photo No. 3  View from the boiler house facing
          northeast.  Cooling towers and the waste water
          pit are shown.
        Photo No.  4  View from boiler house roof looking
        west showing the coal pile and a portion of the
        coal conveying system.
MUSTANG POWER PLANT
M-17

-------
        Photo No. 5  View from ground level facing south-
        west showing the coal conveyors and the transport
        house.
       Photo No. 6  View from the boiler house roof looking
       southeast.  A portion of a switchyard is shown in the
       foreground of the photo.  The ash pond is shown in the
       left-center and the surrounding terrain is shown in
       the background of the photograph.
MUSTANG POWER PLANT
M-18

-------
       Photo No. 7  View from the boiler house roof facing
       north showing oil storage tanks, natural gas meter and
       regulator stations, and cooling towers.
       Photo No. 8  View from the boiler house roof looking
       south.  The 138 KV substation is shown in the center
       of the photograph.  The surrounding farmland is shown
       in the background.
MUSTANG POWER PLANT
M-19

-------
          Photo No.  9  View  from  the boiler house roof  facing
          southwest.   The  top of  the transfer house  is  shown
          in  the  lower left  of  the photo.  The  surrounding
          terrain and  railroad  lines are also shown.
             Photo  No.  10   View from the  boiler house roof
             looking northwest.   Gas turbines  are shown in
             the lower  right and an oil storage tank is
             shown  in the  center of the photograph.   A plant
             storage area  is shown in the background.
MUSTANG POWER PLANT
                                                           M-20

-------
        TABLE M-l.  ESTIMATED CAPITAL COST OF ELECTROSTATIC
         PRECIPITATORS FOR BOILERS 1 AND 2 AT THE MUSTANG
             POWER PLANT ON HIGH-SULFUR COAL (1978)
Direct Costs

ESP                                               $  1,617,000

Ash handling                                           134 QOO

Ducting                                                421,000

                              Total direct costs  $2,172,000

Indirect Costs

Interest during construction  8% of direct costs  $    174,000

Contractor's fee             10% of direct costs       217,000

Engineering                   6% of direct costs       130,000

Freight                    1.25% of direct costs        27,000

Offsite                       3% of direct costs        65,000

Taxes                         0% of direct costs           000

Spares                        1% Of direct costs        22,000

Allowance for shakedown       3% of direct costs        65,000

               Total indirect costs               $700,000

               Contingency                             574,000

               Total                              $3,446,000

               Coal conversion costs                10,703,000

               Grand total                        $  14,149,000

               5/kW                                     119.91
MUSTANG POWER PLANT                                    M-21

-------
  TABLE M-2.  ESTIMATED ANNUAL OPERATING COSTS OF ELECTROSATIC
         PRECIPITATOR FOR BOILERS 1 AND 2 AT THE MUSTANG
             POWER PLANT ON HIGH-SULFUR COAL (1978)
Utilities                                         Annual Costs

Electricity    335 kW at 27.5 mills/kWh           $     33,000
Water          4794 x 103 gal/yr at $0.01/103 gal        1,000

Operating Labor

Direct labor     0.5 man/shift at $7.52/h               66,000
Supervision      15% of direct labor                    10,000

Maintenance

Labor and materials  2% of fixed investment             69,000
Supplies            15% of labor and materials          10,000

Overhead

Plant               50% of operating and maintenance    78,000
Payroll             20% of operating labor              15,000

Additional Operating and Maintenance

Coal conversion                                        866,000

Fixed costs

Depreciation        (8.33%)
Interim replacement (0.35%),  £ = 20.18% of fixed
                                   investment
Insurance           (0.30%)
Taxes               (0.00%)
Capital cost       (11.20%)
Total fixed cost
Total cost
Fuel credit
Net annual credit
Mills/kWh
$
$
$
695,000
1,843,000
(2,145,000)
(302,000)
0.71
 MUSTANG POWER PLANT                                     M-22

-------
     Table M-3 .   ELECTROSTATIC PRECIPITATOR DESIGN VALUES

           FOR BOILER 1 AT THE MUSTANG POWER PLANT

                ON HIGH- SULFUR COAL BURNING
      Design Parameter
Value
 Collection efficiency,  %
   (Overall)

 Specific collecting area,
   ft2/1000 acfm
                          2
 Total collecting area,  ft

 Superficial velocity,  fps

 Overall ESP dimensions
   (height x width x depth),  ft
   excluding hopper dimensions
97.65


197


26,400

4


15 x 37 x 19
MUSTANG POWER PLANT
             M-23

-------
    Table  M-4  .   ELECTROSTATIC  PRECIPITATOR DESIGN  VALUES

           FOR  BOILER  2 AT  THE MUSTANG  POWER PLANT

                 ON HIGH-SULFUR  COAL  BURNING
      Design  Parameter
Value
 Collection  efficiency,  %
   (Overall)

 Specific  collecting  area,
   ft2/1000  acfm
                          2
 Total  collecting  area,  ft

 Superficial velocity,  fps

 Overall ESP dimensions
   (height x width x  depth),  ft
   excluding hopper dimensions
97.65


197


26,400

4


15 x 37 x 19
MUSTANG POWER PLANT
            M-24

-------
        TABLE M-5.  ESTIMATED CAPITAL COST OF ELECTROSTATIC
      PRECIPITATORS FOR BOILERS 1 AND 2 AT THE MUSTANG POWER
                 PLANT ON LOW-SULFUR COAL (1978)
Direct Costs

ESP                                               $  1,951,000

Ash handling                                           283,000

Ducting                                                388,000

                              Total direct costs  $2,622,000

Indirect Costs

Interest during construction  8% of direct costs  $    210,000

Contractor's fee             10% of direct costs       262,000

Engineering                   6% of direct costs       157,000

Freight                    1.25% of direct costs        33,000

Offsite                       3% of direct costs        79,000

Taxes                         0% of direct costs           000

Spares                        1% of direct costs        26,000

Allowance for shakedown       3% of direct costs        79,000

               Total indirect costs               $846,000

               Contingency                             694,000

               Total                              $4,162,000

               Coal conversion costs                10,703,000

               Grand total                        $ 14,865,000

               SAW                                     125.97
MUSTANG POWER PLANT                                     M-25

-------
  TABLE M-6.  ESTIMATED ANNUAL OPERATING COSTS OF ELECTROSTATIC
        PRECIPITATORS FOR BOILERS 1 AND 2 AT THE MUSTANG
              POWER PLANT ON LOW-SULFUR COAL (1978)
Utilities                                         Annual Costs

Electricity    158 kW at 27.5 mills/kWh           $     15,000
Water          4794 103 gal/yr at $0.01/103 gal          1,000

Operating Labor

Direct labor     0.5 man/shift   $7.52/h                66,000
Supervision      15% of direct labor                    10,000

Maintenance

Labor and materials  2% of fixed investment             83,000
Supplies            15% of labor and materials          13,000

Overhead

Plant               50% of operating and maintenance    86,000
Payroll             20% of operating labor              15,000

Additional Operating and Maintenance

Coal conversion                                        866,000

Fixed costs

Depreciation        (8.33%)
Interim replacement (0.35%), E = 20.18% of fixed
                                   investment
Insurance           (0.30%)
Taxes               (0.00%)
Capital cost        (11.20%)
Total fixed cost
Total cost
Fuel cost
Net annual cost
Mills/kWh
$
$
$
840,000
1,995,000
4,725,000
6,720,000
15.72
 MUSTANG POWER PLANT                                    M-26

-------
     Table M-7 .   ELECTROSTATIC PRECIPITATOR DESIGN VALUES

           FOR BOILER 1 AT THE MUSTANG POWER PLANT

                  ON LOW-SULFUR COAL BURNING
      Design Parameter
Value
 Collection efficiency, %
   (Overall)

 Specific collecting area,
   ft2/1000 acfm

 Total collecting area, ft

 Superficial velocity, fps

 Overall ESP dimensions
   (height x width x depth), ft
   excluding hopper dimensions
97.65


417


55,900

4


30 x 19 x 42
MUSTANG POWER PLANT
             M-27

-------
   Table M-8  .  ELECTROSTATIC PRECIPITATOR DESIGN VALUES

          FOR BOILER 2 AT THE MUSTANG POWER PLANT

                  ON LOW-SULFUR COAL BURNING
     Design Parameter
Value
Collection efficiency, %
   (Overall)

Specific collecting area,
   ft2/1000 acfm
                         2
Total collecting area, ft

Superficial velocity,  fps

Overall ESP dimensions
   (height x width x depth),  ft
   excluding hopper dimensions
97.65


417


55,900

4


30 x 19 x 42
MUSTANG POWER PLANT
            M-28

-------
o
o
o
o
COOLING

TOWERS
                                      0
                                      o
                                     WASTE

                        COOLING TOWER  WATER
                                      PIT
O
o
o
                                                          PRECIPITA-
                                               TANKS
                                                 O/S

                                                 V-X
                                                                     o
                                                                     o
                                                                     o
                                                                     0
                                           -i	1	»-
                                  DGAS REGULATOR &

                                 METERING STATIONS
                                t   i	1	1	1	1	
                                          S     STACKS   ~~ESP~
             TRANSPORTf)
                HOUSE UJ
                                       POWER PLANT
                                                            PARKING LOT
                               _X	y	x—. j—x—x	x—.

                               •    66 KV    I I             I

                               J  SWITCHYARD   fj   SWITCHYARD  J

                               I—X	X	X—J I—X	X^—X—J
                    138  KV

                  SUBSTATION
Figure M-l.   Site  plan  showing possible  locations of  new  ESP's

         for Boilers 1 and 2  at the Mustang  power  plant.
 MUSTANG POWER  PLANT
                                               M-29

-------
                         APPENDIX N




                  POSSUM POINT POWER  PLANT
POSSUM POINT POWER PLANT                               N-l

-------
                            CONTENTS



Possum Point Power Plant Survey Form

Possum Point Power Plant Photographs
                                                  Page

                                                  N-4

                                                  N-16
Number
 N-l
                             FIGURES
Site Plan Showing Possible Locations of New
ESP's for Boilers 2, 3, and 4 at the Possum
Point Power Plant
                                                  Page
                                                            N-30
Number
 N-l
 N-2
 N-3
 N-4
 N-5
 N-6
                             TABLES
Estimated Capital Cost for an Electrostatic
Precipitator for Boiler 2 at the Possum Point
Power Plant (1978)

Estimated Annual Operating Cost of an Electro-
static Precipitator for Boiler 2 at the Possum
Point Power Plant (1978)

Electrostatic Precipitator Design Values for
Boiler 2 at the Possum Point Power Plant

Estimated Capital Cost of an Electrostatic
Precipitator for Boiler 3 at the Possum Point
Power Plant (1978)

Estimated Annual Operating Cost of an Electro-
static Precipitator for Boiler 3 at the Possum
Point Power Plant (1978)

Electrostatic Precipitator Design Values for
Boiler 3 at the Possum Point Power Plant
                                                  Page
                                                            N-21
                                                            N-22
                                                            N-23
                                                            N-24
                                                            N-25
                                                            N-26
POSSUM POINT POWER PLANT
                                                  N-2

-------
                        TABLES  (continued)

 Number                                                       Page

 N-7       Estimated  Capital  Cost  of  an  Electrostatic
           Precipitator  for Boiler 4  at  the  Possum Point
           Power  Plant  (1978)                                 N-27

 N-8       Estimated  Annual Operating Cost of  an  Electro-
           static Precipitator  for Boiler 4  at the Possum
           Point  Power Plant  (1978)                           N-28

 N-9       Electrostatic Precipitator Design Values for
           Boiler 4 at the Possum  Point  Power  Plant          N-29
POSSUM POINT POWER PLANT                                    N-3

-------
                                                    OMB No.  158S 74023
                    POWER  PLANT SURVEY FORM
 A.  COMPANY INFORMATION:
     1. COMPANY NAME:
                  Virginia Electric  &  Power  Co.

2. MAIN OFFICE:  P-0. Box 26666, Richmond,  Virginia  23261

3. RESPONSIBLE OFFICER:  C' M' Callings
4. POSITION:  vice President

5. PLANT NAME: Possuit^ Point  Power  Station
6. PLANT LOCATION:  Prince William County,  Dumfries Va.   22026

   RESPONSIBLE OFFICER AT PLANT  LOCATION:
   POSITION:  Plant Superintendent
     7

     8
                                                 Holland Simmons
     9. POWER POOL
     DATE INFORMATION GATHERED:
                            April  21,  1976
     PARTICIPANTS IN MEETING:

     Ned Kirby - VEPCO  -  Richmond
     Ken Newsome - VEPCO  -  Richmond
     Jim Cassada VEPCO  -  Richmond
     Joe O'Rear - VEPCO -Richmond
     Bob Combs - VEPCO  -  Richmond
     R. H. Milliard - VEPCO-Possum  Point
     Rolland Simmons -  VEPCO- Possum Point
     Bernie Turlinski - U.S.  Environmental Protection Agency
     Daniel J. Gaston - Virginia  Air Pollution Control Board
     Frank Lalley - Federal  Energy  Administration
     Thomas C.- Ponder,  Jr.  -  PEDCo  Environmental, Inc.
     N. David Noe - PEDCo Environmental,  Inc.
     David M. Augenstein  -  PEDCo  Environmental,  Inc.
POSSUM POINT POWER PLANT
                                                        N-4

-------
O
to
to
C
S

13
O
w
JO
B.
Z
I
ui
*
ATMOSPHERIC EMISSIONS
1. PARTICIPATE EMISSIONS3
LB/MM BTU
GRAINS/A CF
LB/HR (FULL LOAD)
TONS/YEAR ( )
2. APPLICABLE PARTICULATE EMISSION
REGULATION
a) CURRENT REQUIREMENT
AQCR PRIORITY CLASSIFICATION
REGULATION & SECTION NO.
LB/MM BTU

b) FUTURE REQUIREMENT (DATE: )
REGULATION & SECTION NO.
LB/MM BTU
3. S02 EMISSIONS3
LB/MM BTU
LB/HR (FULL LOAD)
TONS/YEAR ( )
4. APPLICABLE S02 EMISSION REGULATION
a) CURRENT REQUIREMENT
REGULATION & SECTION NO.
LB/MM BTU

b) FUTURE REQUIREMENT (DATE: )
REGULATION & SECTION NO.
LB/MM BTU
Boiler number






Part IV
0.1 Ib/i
less than





Part IV
1.06 Ib









ule Ex -
im B tu
20% opari t





ule Ex - '
mm Btu !









4.30

y ( Rn 1 p • ]





4.51 ( i
02









(a) 11

v 7 )





»
) 1























       a)  Identify whether results are from stack tests  or  estimates

-------
  C.   SITE DATA
      1.  U.T.M. COORDINATES
      2.  ELEVATION ABOVE MEAN SEA LEVEL  (FT)	
      3.  SOIL DATA:  BEARING VALUE	
              PILING NECESSARY_	
      4.  DRAWINGS REQUIRED
         PLOT PLAN OF SITE (CONTOUR)
         EQUIPMENT LAYOUT AND ELEVATION
         AERIAL PHOTOGRAPHS OF SITE INCLUDING POWER PLANT,
         COAL STORAGE AND ASH DISPOSAL AREA
      5.  HEIGHT OF TALLEST BUILDING AT PLANT SITE OR
         IN CLOSE PROXIMITY TO STACK  (FT. ABOVE GRADE)
      6.  HEIGHT OF COOLING TOWERS (FT. ABOVE GRADE):
POSSUM POINT POWER PLANT                                   N_g

-------
 G
 3
 Z
 t-3
 i
 w
 13

 £
 z
Z
I
-j
•^
D. BOILER DATA
1. SERVICE: BASE LOAD
STANDBY, FLOATING, PEAK
2. TOTAL HOURS OPERATION (1975)
3. AVERAGE CAPACITY FACTOR (19? 5 )
4. SERVED BY STACK NO.
5. BOILER MANUFACTURER
6. YEAR BOILER PLACED IN SERVICE
7. REMAINING LIFE OF UNIT
8. GENERATING CAPACITY (MW)
RATED
MAXIMUM CONTINUOUS - Summer
PEAK
9. FUEL CONSUMPTION:
COAL . -, ': , - TPH coal -
(TPH) OR (GPH) MAXIMUM CONTINUOUS
BBL/Hr. oil
10. ACTUAL FUEL CONSUMPTION
COAL (TPY) (1975)
OIL '^") BBI./yr
11. WET OR DRY BOTTOM
12. FLY ASH REINJECTION (YES OR NO)
13. STACK HGT ABOVE GRADE (FT.)
14. I.D. OF STACK AT TOP (INCHES)
Boiler number
1
Float
6,572.50
39.0
1
TF.
1948

69
74


31.5
132

525,050
Dry
Yes
175
156
2
Float
7,243.75
48.0
2
CE
1951

69
69.2


29.6
140

577,950
Dry
Yes
175
156
3
Float
5,057.60
34.0
3
PE
1955

113.64
101


38.5
162

551,950
Dry
Yes
177
156
4
Float
7,043.36
57.0
4
rv
1962 *•

239. 36
232.9


78. 3
338

1,970,600
Dry
f
Yes
175
168
5
rioating
3,585.38
23.3
5
CE
1975

882
805


0
1.220

3,212.690
NA
.Yes
358.5
276
     Notes:

-------
O
Cfi
W
G
s
O
H
2
O
S
M
Z
-3
15. FLUE GAS CLEANING EQUIPMENT
a) MECHANICAL COLLECTORS
MANUFACTURER
TYPE
EFFICIENCY: DESIGN/ACTUAL (%)
MASS EMISSION RATE:
(GR/ACF)
(#/HR)
(#/MM BTU)
b) ELECTROSTATIC PRECIPITATOR
MANUFACTURER
TYPE
EFFICIENCY: DESIGN/ (%)
MASS EMISSION RATE
(GR/ACF)
(#/HR)
(#/MM BTU)
NO. OF IND. BUS SECTIONS
TOTAL PLATE AREA (FT^)
FLUE GAS TEMPERATURE
@ INLET ESP @ 100% LOAD (°F)
16. EXCESS AIR: DESIGN/ACTUAL (%)
Boiler number
1
N/A





COTT
E
95


249 . 7





2
N/A





COTT
E
96


170





3
N/A





COTT
E
96


210. 7





4
N/A





COTT
E
96


428 .5



t

5
UOP
MCAX
9112

206

N/A










2

00
Notes :

-------
 O
 cn
 en
 c
 2
 O
 M
 z
 13
 i
 w
£
z
^
17. FLUE GAS RATE (ACFM)
@ 100% LOAD
@ 75% LOAD
@ 50% LOAD
18. STACK GAS EXIT TEMPERATURE (°F)a
@ 100% LOAD
@ 75% LOAD
@ 50% LOAD
19. EXIT GAS STACK VELOCITY (FPS)a
@ 100% LOAD
@ 75% LOAD
@ 50% LOAD
20. FLY ASH: TOTAL COLLECTED (TONS/YEAR)
DISPOSAL METHOD
DISPOSAL COST ($/Yr.)
21. BOTTOM ASH: TOTAL COLLECTED (J.IGNS/
DISPOSAL METHOD YEAR)
DISPOSAL COST ($/-T2QN)
22. EXHAUST DUCT DIMENSIONS @ STACK
23. ELEVATION OF TIE IN POINT TO STACK
24. SCHEDULED MAINTENANCE SHUTDOWN
(ATTACH PROJECTED SCHEDULE)
Boiler number
1
322r321
247,217
172,556
364
330
311
40.5
31 .0
21.7
0 .6 cal
Land fill
30, 700
0.1 ca]
Land fill
7,000



2
271r 776
210,945
144 ,692
303
275
255
34.4
26.5
18. 2







3
338 ,nqq
259,259
186 ,502
277
265
246
42.5
32.6
23.4







4
6Sn, 3RS
492,435
334,125
265
2'46
219
70.4
53.3
36. 2







5
?,ORO inn
1,583,500
1,103,500
260
255
249
83.4
63.5
44.3







z
I
a) Identify source of values  (test or estimate)


Notes:

-------
o
to
to
c
2

13
O
E .    I .D.  FAN  DATA
       1.  MAXIMUM  STATIC  HEAD  (IN.  W.C-)
       2.  WORKING  STATIC HEAD  (IN.  W.C.)
                                                                               Boiler nunxber
O
s
w
13
tr1
>
Z
•-3
        Notes :
z,
I

-------
  F.   FLY  ASH DISPOSAL AREAS
       1.   AREAS AVAILABLE (ACRES)
       2_.	YEARS STORAGE (ASH ONLY)
       3.   DISTANCE FROM STACK  (FT.)
       4.   DOES THIS PLANT HAVE PONDING
           PROBLEMS?  DESCRIBE IN ATTACHMENT
       COAL  DATA
       1.  COAL SEAM,  MINE, MINE LOCATION
          a.
          b.
           c.
          d.
          QUANTITY USED BY SEAM AND/OR MINE
          a.
          b.
          c.
          d.
          ANALYSIS
          GHV  (BTU/LB)
          S  (%)
          ASH  (%)
          MOISTURE  (%)
      4.  PPT PERFORMANCE EXPERIENCED WITH LOW
          S FUELS  (DESCRIBE IN ATTACHMENT)
  H.   FUEL OIL DATA
      1.  TYPE    //2
      2.  S CONTENT  (%)
      3.  ASH CONTENT  (%)
          SPECIFIC GRAVITY
      5.	GHV  (BTU/GAL)    146,680
      COST DATA
      ELECTRICITY
      WATER
      STEAM
      PLANT SUBSTATION CAPACITY
      APPROXIMATELY WHAT  PERCENTAGE OF RATED
      STATION CAPACITY CAN  PLANT SUBSTATION
      PROVIDE?
      NORMAL LOAD ON PLANT  SUBSTATION?
      VOLTAGE AT WHICH  POWER  IS  AVAILABLE?
POSSUM POINT POWER  PLANT                                    N-ll

-------
    K.  OIL/GAS TO COAL CONVERSION DATA
        1.  HAS THE BOILER EVER BURNED COAL?
Boiler
Yes
or
SYSTEM
2.1



NO.
No.
1
Yes
AVAILABILITY
234 5
Yes YP« Yog - ifo

COAL HANDLING
a
b
c
. Is
the system still installed? Yes S No D Runn: {
OK
. Will it operate? D D
. Of
the following items which
need to be replaced:
Unloading equipment Repair Yes H No D
Stack Reclaimer S D
Bunkers
Conveyors
Scales
Coal Storage
2.2


B D
a D
D m
Area H D
FUEL FIRING
a
b
. Is
the system still installed? YesQ No Q
. Will it operate? D [3
  Some replaced by
                     Of the following items which
                     need to be replaced:
                     Pulverizers or Crushers
fly ash reinject 	Feed Ducts
                     Fans
                     Controls
            2.3  GAS CLEANING
                 a.  Is the system still installed?

                 b.  Will it operate?
                 c.  Of the following items which
                     need to be replaced:
                     Electrostatic Precipitator
                     Cyclones
                     Fly Ash Handling Equipment
                     Soot Blowers - Air Compressors
                     Wall deslaggers
Yes [x|
   D
   m
   B


Yesgg
   E
Yes
No D
  D
  D
  D
No n
   D
NoQ
   Bon A
   E
   D    x
   Q
   n
   a
   a
   D
 POSSUM POINT POWER PLANT
     N-12

-------
         2.4  ASH HANDLING
              a.   Is the system still installed?   Yes 0    Non
              b.   Will it operate?                     0      Q
              c.   Of the following items which
                  need to be replaced:
                  Bottom Ash Handling              Yes 0    NoD
                  Ash Pond                             D x    Q
POSSUM POINT POWER PLANT                                  N_13

-------
 L.   SUPPLEMENTARY  CONTROL  SYSTEM DATA

     1.   DOES THE PLANT  NOW HAVE A  SUPPLEMENTAL CONTROL
         SYSTEM  (SCS)?                                       Yes  D  -No  D
         If yes, attach  a description of the system.

     2.   IS THE  PLANT CAPABLE OF SWITCHING TO LOW
         SULFUR  FUELS?                                       Yes  Q   No  Q

         2.1   Storage capacity for  low sulfur fuels
              (tons, bbls,  days)

         2.2   Bunkers available for low sulfur coal
              storage?                                       Yes  [~]   No  r~)

         2.3   Handling facilities available for low
              sulfur fuels                        '           Yes       No

              If yes, describe
         2.4   Time  required to switch fuels and fire
              the  low  sulfur fuel in the boiler (hrs)?
     3.   IS  THE  PLANT CAPABLE OF LOAD SHEDDING?

         If  yes, discuss _
         ___ ; _         Yes  Q   No  [J
     4.   IS  THE  PLANT CAPABLE OF LOAD SHIFTING?
         If  yes,  discuss _
                                                            Yes       No
     5.   POWER  PLANT MONITORING SYSTEM
         5.1  Existing  system      '                          Yes  [~1   No  [~|
             a.  Air quality instrumentation             Number     Type

                 (1)   Sulfur Oxides - Continuous         _     _
                                    - Intermittent       __     _
                                    - Static             _     _
                 (2)   Suspended particulars
                                    - Intermittent       _     _
                                    - Static
                  (3)   Other  (describe)
              b.   Meteorological instrumentation
                  If yes, describe 	
              c.   Is  the monitoring data available?          Yes  f~j   No  (|

              cl.   Is  the monitoring data reduced and
                  analyzed?                                  Yes  Q]   No  [j


POSSUM POINT POWER PLANT                                        N-14

-------
             !i.2  Proposed system                                Yes  P]   No
                  If yes,  describe	
                  a.   Air monitoring  instrumentation           Number     Type
                      (1)  Sulfur  oxides  - Continuous          	     	
                                         - Intermittent        	
                                         - Static                ~
                      (2)  Suspended  particulato
                                         - Intermittent        	     	
                                         - Static              	
                      (3)  Other (describe) 	
                  b.   Meteorological  instrumentation
                      If  yes, describe
POSSUM POINT POWER PLANT                                         N-15

-------
    Photo  No.  1.   View from the  roof of Boiler 5 facing south
    showing  stacks 1,  2,  3,  and  4.   Cooling towers and Potomac
    River  are  in  the  background.
   Pholc No. 2.  View from the roof of Boiler 5 facing north-
   east: showing oil tanker unloading facilities on the Potomac.
POSSUM POINT POWER PLANT
                                                              N-16

-------
    Photo No. 3.  View from the roof of Boiler 5 facing north
    showing Boiler 5 duct tie-ins to the stack.  Oil storage
    tanks are shown in the background.
    Photo  No.  4.   View from the roof of Boiler 5 facing north-
    west showing  oil  storage facilities and electrical sub-
    station.
POSSUM POINT POWER PLANT
N-17

-------
Photo No. 5.  View from the roof of Boiler 5 facing south-
west showing an electrical substation, coal storage area and
the Potomac River.
   Photo No.  6.   View from ground level showing electrostatic
   pi:ecipitator  serving Boiler 4 located on the northeast end
   of the plant.
POSSUM POINT POWER PLANT
                                                             N-18

-------
 Photo No. 7.  View from ground level showing electrostatic
 precipitator and tie-in to stack serving Boiler 3 located on
 the east end of the plant.
 Photo No.  8.   View from ground level facing south showing
 available  space behind Stacks 1,  2, 3, and 4 on the east end
 of the plant.
POSSUM POINT POWER PLANT
                                                          N-19

-------

          I
  Photo No.  9.  View from ground level facing north showing
  electrostatic precipitator and tie-in duct serving Boiler 1
   Photo No. 10.  View from ground level facing south showing
   coal handling facilities.  A portion of the coal storage
   area is also shown.
POSSUM POINT POWER PLANT
                                                           N-20

-------
      TABLE N-l.  ESTIMATED CAPITAL COST FOR AN ELECTROSTATIC
                 PRECIPITATOR FOR BOILER 2 AT THE
                  POSSUM POINT POWER PLANT (1978)

     Direct  Costs


     ESP                                                    $2,356,000

     Ash  handling                                              850,000

     Ducting                                                   356,000

                             Total direct costs            $3,562,000

     Indirect Costs

     Interest during construction  10% of direct costs      $  356,000

     Contractor's fee              10% of direct costs         356,000

     Engineering                   10% of direct costs         356,000

     Freight                     1.25% of direct costs          45,000

     Offsite                        3% Of direct costs         107,000

     Taxes                          0% of direct costs             000

     SPares                         1% of direct costs          36,000

     Allowance for shakedown        3% of direct costs         107,000

              Total indirect costs                         $1,363,~000~

              Contingency                                     985,000

              To ta l                                        $ 5,9 ToTo o o~

              Coal conversion costs                            137,000

              Grand total                                  $6,047,000

                                                              87.38
POSSUM POINT POWER PLANT                                  N-21

-------
         TABLE N-2.  ESTIMATED ANNUAL OPERATING COST OF AN
           ELECTROSTATIC PRECIPITATOR FOR BOILER 2 AT THE
                  POSSUM POINT POWER PLANT  (1978)
    Utilities           Quantity            Unit Cost      Annual Cost

    Electricity         466 kW          27.50 mills/kWh    $   53,000
    Water               1 x 103 gal/h   $0.01/103 gal           i,'000

    Operating Labor

    Direct labor        0.5 man/shift   $8.50/man-hour         37 000
    Supervision         15% of direct labor                     6,'oOQ

    Maintenance

    Labor and materials 21 of fixed investment                118 000
    Supplies            i5-6 of labor and materials             18,'oOO

    Overhead

    Plant               50°o of operation and maintenace        90,000
    Payroll             20-S of operating labor                  9,000

    Trucking

    Bottom/fly ash                                                000
       removal

    Fixed Costs

    Depreciation        (7.69%)
    Interim replacement (0.35C<;),  I  = 19.54%  of fixed
                                     investment

    Insurance            (0.30-c)
    Taxes               (0.00%)
    Capital cost       (11.20%)
    Total fixed  cost                                        $1,155,000
    Total cost                                              $1,487,000
    Fuel credit
    Net  annual cost                                         $   836,000
    Mills/kWh                                                     2 87
POSSUM POINT POWER PLANT                                 N-22

-------
    TABLE N-3.  ELECTROSTATIC PRECIPITATOR DESIGN VALUES FOR
            BOILER 2 AT THE POSSUM POINT POWER PLANT
       Design Parameter
   Values
  Collection efficiency, %
     (Overall)

  Specific collecting area,
     ft2/1000 acfm

  Total collecting area, ft2

  Superficial velocity, ft/s

  Overall ESP dimensions
  (height x width x depth), ft
  excluding hopper dimensions
    97.40


     568


   155,400

     4.0

42 x 29 x 50
POSSUM POINT POWER PLANT
                                                            N-23

-------
            TABLE N-4.   ESTIMATED CAPITAL COST OF  AN
         ELECTROSTATIC  PRECIPITATOR FOR BOILER 3 AT  THE
                 POSSUM POINT POWER PLANT (1978)
   Direct Costs

   ESP                                                    $2,430,000

   Ash handling                                              945,000

   Ducting                                                   387,000

                            Total direct costs            $ 3,762,000

   Indirect Costs

   Interest during construction  1.0% of. direct costs      $  376,000

   Contractor's fee              10% of direct costs         376,000

   Engineering                   10% of direct costs         376,000

   Freight                     1.25% of direct costs          47,000

   Offsite                        3% of direct costs         113,000

   Taxes                          0% of direct costs             000

   Spares                         1% of direct costs          38,000

   Allowance for shakedown        3% of direct costs         113,000

             Total indirect costs                         $1,439,000

             Contingency                                   1,040,000

             Total                                        $6,241,000

             Coal conversion costs                            213  000

             Grand total                                  $6,454,000

             $/kW                                              63>90
POSSUM POINT POWER PLANT                                 N-24

-------
          TABLE N-5.   ESTIMATED ANNUAL  OPERATING  COST  OF  AN
               ELECTROSTATIC  PRECIPITATOR  FOR BOILER 3
               AT  THE  POSSUM  POINT  POWER PLANT  (1978)
ULilUieS           Quantity            unit Cost

                                   27.50 mills/kW            ,
                            gal/h  $0.01/103 gal            i/000
     lUectricity          538  kW         27.50  mills/kWh      $    43,000
     WaLcr                !      J
     Operating  Labor

     Direct  labor-        0.5 man/shift   $8 . 50/man-hour
     Supervision          i5% of direct  labor

     Maintenance

     Labor and materials  2", of fixed investment                125 QOO
     Supplles             15"6 of labor and materials             19,000

     Overhead


     Payroll              ™? °P opcration and nmintenace        94,000
     layroli              20° of operating labor                  9,000

     Trucking

     Bottom/fly ash                                                nnn
       removal                                                    °°°

    Fixed Costs

    Depreciation         (5.88%)
    Interim replacement  (0.35%),  L = 17.73% of  fixed
                                     investment

    Insurance             (0.305)
    Taxes                (0.00%)
    Capital  cost       (11.20%)
    Total fixed  cost                                        C1  , n_  nnn
                                                           $1,107,000
    Total cost                                             ei

                                                           $1
POSSUM POINT POWER PLANT                                  N-25

-------
    TABLE  N-6.   ELECTROSTATIC PRECIPITATOR DESIGN VALUES FOR
            BOILER 3  AT THE POSSUM POINT POWER PLANT
       Design Parameter
   Values
  Collection efficiency, %
    (Overall)

  Specific collecting area,
    ft2/1000 acfm

  Total collecting area, ft2

  Superficial velocity, ft/s

  Overall ESP dimensions
  (height x width x depth), ft
  excluding hopper dimensions
    97.40


     531


   179,634

     4.0

39 x 38 x 47
POSSUM POINT POWER PLANT
                                                         N-26

-------
     TABLE N-7.   ESTIMATED  CAPITAL  COST  OF AN  ELECTROSTATIC
                PRECIPITATOR  FOR  BOILER  4 AT THE
                 POSSUM POINT POWER PLANT  (1978)


   Direct Costs

   ESP                                                    $3,463,000

   Ash handling                                            1,455,000

   Ducting                                                   523,000

                            Total direct costs            $ 5,441,000

   Indirect Costs

   Interest during construction  10% of. direct costs      $  544,000

   Contractor's fee              10% of direct costs         544,000

   Engineering                   10% of direct costs         544,000

   Freight                     1.25% of direct costs          68,000

   offsite                        3% of direct costs         163,000

   Taxes                          0% of direct costs             000

   SPares                         1% of direct costs          54,000

   Allowance for shakedown         3% of direct costs         163,000

             Total indirect costs                         $2f080"f"000"

             Contingency                                   1,504,000

             Total                                        $9,025,000

             Coal conversion  costs                            341,000

             Grand total                                  $9,366,000

             SAW                                              40.21
POSSUM POINT POWER PLANT                                    N-27

-------
         TABLE N-8.   ESTIMATED ANNUAL OPERATING COST OF AN
          ELECTROSTATIC PRECIPITATOR FOR BOILER 4 AT THE
                  POSSUM POINT POWER PLANT (1978)
Quantity            unit Cost
                                                           Annual Cost

    Electricity         863 kW          27.50 mills/kWh    $   118,000
    Water               3 x 103 gal/h   $0.01/103 gal            1,000

    Ope rat ing Laboi:

    Direct labor        0.5 man/shift   $8 . 50/man-hour          37 QOO
    Supervision         15°, o£ direct labor                       6,000
    Maintenance

    Labor  and materials  2:,  of  fixed  investment                 181,000
    supplies             is-j Of  labor and  materials              . 27,000

    Overhead

                        50°6 of  operation  and  maintenace         126,000
          1              20o of  operating  labor                   9,000

    Trucking

    Bottom/fly ash                                                  000
      removal

   Fixed Costs

   Depreciation         (4.17%)
   Interim replacement  (0.353), JJ = 16.02% of fixed
                                    investment

   Insurance            (0.30°0)
   Taxes                (0.00°0)
   Capital cost       (11.20%)
   Total fixed  cost                                       $ 1/446/000
   Total cost                                             s ,  95,
   Fuel rrprtil-                                            ^ l,ybl,000
      1 credlt                                             (3,696,000)
   Net annual credit                                      S(1 74,--
   Mills/kWh                                              >U,/4b_,
POSSUM POINT POWER PLANT                                  N_28

-------
      TABLE N-9.  ELECTROSTATIC PRECIPITATOR DESIGN VALUES
          FOR BOILER 4 AT THE POSSUM POINT POWER PLANT
        Design Parameter
    Values
   Collection efficiency,  %
     (Overall)

   Specific  collecting area,
     ft2/1000 acfm

   Total  collecting  area,  ft2

   Superficial  velocity,  ft/s

   Overall ESP  dimensions
   (height x width x depth), ft
   excluding hopper  dimensions
    97.40


     442


   287,760

     4.0

33 x 83 x 40
POSSUM POINT POWER PLANT
                  N-29

-------
o
en
w
c
s
o
H
T)
O
s;
M
i
I
u>
o
                                 ;ESP.I IESP.! I ESP.;
               Figure N-l.   Site plan showing  possible locations  of new ESP's  for

                     Boilers 2,  j,  ana 4 at  tne Possum Point  power plant.

-------
                         APPENDIX  0




                   RAVENSWOOD  POWER  PLANT
RAVENSWOOD POWER PLANT                                    0-1

-------
                            CONTENTS



Ravenswood Power Plant Survey Form

Ravenswood Power Plant Photographs
                                                  Page

                                                  0-4

                                                  0-16
Number
 0-1
 0-2
                             FIGURES
Site Plan Showing Possible Locations of Major
Components for the Sodium Solution Regenerable
System for Boiler 30 at the Ravenswood Power
Plant

Site Plan Showing Possible Locations of Major
Components for the Limestone System for Boiler
30 at the Ravenswood Power Plant
                                                  Paqe
                                                            0-27
                                                            0-33
Number
 0-1
 0-2
 0-3
 0-4
                             TABLES
Estimated Capital Cost of a Sodium Solution
Regenerable System for Boiler 30 at the
Ravenswood Power Plant (1978)

Estimated Annual Operating Cost of a Sodium
Solution Regenerable System for Boiler 30 at
the Ravenswood Power Plant (1978)

Retrofit Equipment and Facilities for the
Sodium Solution Regenerable System for Boiler
30 at the Ravenswood Power Plant

Retrofit Equipment Dimensions Required for the
Sodium Solution Regenerable System for Boiler
30 at the Ravenswood Power Plant
                                                  Page
                                                            0-22
                                                            0-24
                                                            0-25
                                                            0-26
 RAVENSWOOD  POWER  PLANT
                                                   0-2

-------
                        TABLES (continued)

 Number                                                       Page

  0-5       Estimated  Capital  Cost of a Limestone Scrubbing
           System for Boiler  30  at the Ravenswood Power
           Plant  (1978)                                       0-28

  0-6       Estimated  Annual Operating Cost  of a Limestone
           Scrubbing  System for  Boiler 30 at the Ravenswood
           Power  Plant (1978)                                 0-30

  0-7       Retrofit Equipment and Facilities Required for
           the  Limestone  Scrubbing System for Boiler 30
           at the Ravenswood  Power Plant                      0-31

  0-8       Retrofit Equipment Dimensions Required for the
           Limestone  Scrubbing System for Boiler 30  at the
           Ravenswood Power Plant                            0-32
RAVENSWOOD POWER PLANT                                      0-3

-------
                                         OMB No.  158S 74023
                  POWER PLANT SURVEY  FORM


 A.    COMPANY INFORMATION;

      1.   COMPANY NAME:  Consolidated  Edison Company

      2.   MAIN OFFICE:  4 Irving Place,  New York,  New York  10003

      3.   RESPONSIBLE OFFICER:  John J.  Grob,  Jr.

      4.   POSITION:  Chief Nuclear and Emission Control Engineer

      5.   PLANT NAME:  Ravenswood

      6.   PLANT LOCATION:    Queens, New York

      7.   RESPONSIBLE OFFICER AT PLANT  LOCATION:  Gene McGrath

      8.   POSITION:   Plant Superintendent

      9.   POWER POOL N.Y.  P.P.
      DATE INFORMATION GATHERED:   June 30,  1976
      PARTICIPANTS IN MEETING:
      Bertrum D.  Moll
      Demarest Romaine
      Peter  C. Freudenthal
      John J.  Grob
      Ralph  Morgan
      Ray Werner
      Robert N. Ogg
      Richard T.  Price
      N. David Noe
      Thomas C. Ponder
Consolidated Edison Company
Consolidated Edison Company
Consolidated Edison Company
Consolidated Edison Company
Consolidated Edison Company
USEPA - II - Air Branch
USEPA - II - Air Facilities Branch
PEDCo Environmental, Inc.
PEDCo Environmental, Inc.
PEDCo Environmental, Inc.
RAVENSWOOD POWER PLANT
                               0-4

-------
      B.
M
Z
Cfi
S
o
o
D
O
s:
M
tr1
>
Z
O
 I
ATMOSPHERIC EMISSIONS
1. PARTICULATE EMISSIONS3 Oil
LB/MM BTU
GRAINS/ACF
LB/HR (FULL LOAD)
TONS/YEAR (1975)
2. APPLICABLE PARTICULATE EMISSION
REGULATION
a) CURRENT REQUIREMENT
AQCR PRIORITY CLASSIFICATION
REGULATION & SECTION NO..
LB/MM BTU
OPACITY, PERCENT
b) FUTURE REQUIREMENT (DATE: )
REGULATION & SECTION NO.
LB/MM BTU
3. S02 EMISSIONS3 Oil
LB/MM BTU
LB/HR (FULL LOAD)
TONS/YEAR ( )
4. APPLICABLE S02 EMISSION REGULATION
a) CURRENT REQUIREMENT
REGULATION & SECTION NO.
LB/MM BTU

b) FUTURE REQUIREMENT (DATE: )
REGULATION & SECTION NO.
LB/MM BTU
Boiler number
i n




I
._— — — — — C^

0.10






"Da

0.33



?n




I
:t 227.3 (<
0.10






rt 225 Tab:
0. 33



^n
0.06


1284
I
, \ _ 	 	
. ) — — 	
0.10



0.29

6805
ST _

0.33









































      a)  Identify whether results are  from stack tests or estimates

-------
 C.   SITE DATA
     1.  U.T.M.  COORDINATES.
     2.  ELEVATION ABOVE MEAN SEA LEVEL (FT)	
     3.  SOIL DATA:  BEARING VALUE	
             PILING NECESSARY	
     4.  DRAWINGS REQUIRED
        PLOT PLAN OF SITE (CONTOUR)
        EQUIPMENT LAYOUT AND ELEVATION
        AERIAL PHOTOGRAPHS OF SITE INCLUDING POWER PLANT,
        COAL STORAGE AND ASH DISPOSAL AREA
     5.  HEIGHT OF TALLEST BUILDING AT PLANT SITE OR
        IN CLOSE PROXIMITY TO STACK (FT.  ABOVE GRADE)
     6.  HEIGHT OF COOLING TOWERS (FT.  ABOVE GRADE):
RAVENSWOOD POWER PLANT                                    0-6

-------
1
w
z
en
S
o
o
D
i
w
      D.
O
I
BOILER DATA
1. SERVICE: BASE LOAD
STANDBY, FLOATING, PEAK
2. TOTAL HOURS OPERATION (1975)
3. AVERAGE CAPACITY FACTOR ' (1975 )
4 . SERVED BY STACK NO .
5. BOILER MANUFACTURER
6. YEAR BOILER PLACED IN SERVICE
7. REMAINING LIFE OF UNIT
8. GENERATING CAPACITY (MW)
RATED
MAXIMUM CONTINUOUS
PEAK
9. FUEL CONSUMPTION:
RATED "^ ~*>
MAXIMUM CONTINUOUS
m ted Gas
10. ACTUAL FUEL CONSUMPTION
GAS (1975) 106 FT3
OIL (1975) 103 BBL
11. HEAT RATE BTU/KWHR GAS
COAL (1968)
OIL (1974)
12. WET OR DRY BOTTOM
13. FLY ASH REINJECTION (YES OR NO)
14. STACK HGT ABOVE GRADE (FT.)
15. I.D. OF STACK AT TOP (INCHES)
Boiler number
10

7862
67.8
1
CE
1963

400



568.1
None
3580
250.1
3110.7




No
515
170
?n

6228
55.7
2
CE
1963

400



568.1
None
3580
32.7
2487.8




No
515
170
in N

7552
63.6
3
CE
1965


TO Q

7333
62.5
3
CE
1965






	 1 0
— T>

	 No
"7 O

__ _ _"7 £
	 	 /O'

	 97,
— — — — QAi

Dry
No
	 51
	 28


	

ie 	

9___ _ _
"3 Q__ _ _
o . y — - -

19 	 --

4_ 	
Dry
No

, 	























        Notes:

-------
w
z
en

g
O
o

13
O
16. FLUE GAS CLEANING EQUIPMENT
a) MECHANICAL COLLECTORS
MANUFACTURER
TYPE
EFFICIENCY: DESIGN/ACTUAL (%)
MASS EMISSION RATE:
(GR/ACF)
(#/HR)
(#/MM BTU)
b) ELECTROSTATIC PRECIPITATOR
MANUFACTURER
TYPE
EFFICIENCY: DESIGN/ACTUAL (%)
MASS EMISSION RATE
(GR/ACF)
(#/HR)
(#/MM BTU)
NO. OF IND. BUS SECTIONS
TOTAL PLATE AREA (FT^)
FLUE GAS TEMPERATURE
@ INLET ESP @ 100% LOAD (°F)
17. EXCESS AIR: DESIGN /ACTUAL (%)
Boiler number
10
















10
20
















10
10






Pntt *

qq/


4qdd


1,008,000
700
25




































o
I
oo
Notes
Cott - Research  Cottrell,  Inc.

-------
M
O
O
o
o
s:
M
18. FLUE GAS RATE (ACFM)
@ 100% LOAD
@ 75% LOAD
§ 50% LOAD
19. STACK GAS EXIT TEMPERATURE (°F)a
8 100% LOAD
§ 75% LOAD
@ 50% LOAD
20. EXIT GAS STACK VELOCITY (FPS)a
@ 100% LOAD
@ 75% LOAD
@ 50% LOAD
21. FLY ASH: TOTAL COLLECTED (TONS/YEAR)
DISPOSAL METHOD
DISPOSAL COST ($/TON)
22. BOTTOM ASH: TOTAL COLLECTED (TONS/
DISPOSAL METHOD YEAR)
DISPOSAL COST ($/TON)
23. EXHAUST DUCT DIMENSIONS @ STACK
24. ELEVATION OF TIE IN POINT TO STACK
25. SCHEDULED MAINTENANCE SHUTDOWN
(ATTACH PROJECTED SCHEDULE)
Boiler number
10
656.000


335


119









20
656.000


335


119









30
4 ,300, 000


700


105











































o
I
a) Identify source of values  (test or estimate)


Notes:

-------
o
o
D
      E.   I.D. FAN DATA
            1.  MAXIMUM  STATIC HEAD (IN. W.G.)
2.  WORKING STATIC HEAD  (IN.  W.G.)
                                                                      Boiler number
O
5
W
JO
      Notes:
O
I

-------
F.   FLY ASH DISPOSAL AREAS
     1.   AREAS AVAILABLE (ACRES)
     2.   YEARS STORAGE (ASH ONLY)
     3.   DISTANCE FROM STACK (FT.)
     4.   DOES THIS PLANT HAVE PONDING
         PROBLEMS?  DESCRIBE IN ATTACHMENT
     COAL DATA
     1.   COAL SEAM,  MINE, MINE LOCATION
         a.
         b.
         c.
         d.
     2.   QUANTITY USED BY SEAM AND/OR MINE
         a.
         b.
         c.
         d.
     3.   ANALYSIS  (19
         HHV  (BTU/LB)
         S  (%)
        ASH  (%)
        MOISTURE  (%)
     4.   PPT  PERFORMANCE EXPERIENCED WITH LOW
         S  FUELS  (DESCRIBE.IN ATTACHMENT)
H.  FUEL OIL  DATA (1975)
    1.  TYPE
     2.   S  CONTENT (%)     0.27
     3.  ASH  CONTENT (%)
    4.  SPECIFIC  GRAVITY
     5.  HHV  (BTU/GAL)     144,241
I.  NATURAL GAS  HHV (BTU/FT3)   1025
J.  COST DATA
    ELECTRICITY
    FUEL:  COAL           GAS          OIL
    WATER
    STEAM
    TAXES ON A.P.C.  EQUIPMENT:   STATE SALES   (No Sales Tax)
         STATE  PROPERTY  TAX
 RAVENSWOOD POWER PLANT

-------
  K,
PLANT SUBSTATION CAPACITY
  M.
APPROXIMATELY WHAT PERCENTAGE OF RATED
STATION CAPACITY CAN PLANT SUBSTATION
PROVIDE?

NORMAL LOAD ON PLANT SUBSTATION?

VOLTAGE AT WHICH POWER IS AVAILABLE?

ADDITIONAL INFORMATION

   F.E.A. LETTER

OIL/GAS TO COAL CONVERSION DATA

1.  HAS THE BOILER EVER BURNED COAL?
Boiler No.
Yes or No.










      2.  SYSTEM AVAILABILITY

          2.1  COAL HANDLING
               a.  Is the system still installed?

               b.  Will it operate?

               c.  Of the following  items which
                   need to be replaced:

                   Unloading equipment
                   Stack Reclaimer  (Barge)
                   Bunkers
                   Conveyors
                   Scales
                   Coal Storage Area

          2.2  FUEL FIRING
               a.  Is the system still installed?

               b.  Will it operate?
               c.  Of the following  items which
                   need to be replaced:
                   Pulverizer^ or Crushers
                   Feed Ducts
                   Fans
                   Controls

          2.3  GAS CLEANING
               a.  Is the system still installed?

               b.  Will it operate?

               c.  Of the following  items which
                   need to be replaced:

                   Electrostatic Precipitator
                   Cyclones
                   Fly Ash Handling  Equipment
                   Soot Blowers  - Air Compressors
                   Wall deslaggers
Boiler
YesES
                                                     30
                                              YesB
                                              Yes
                                                 m
                                                 B
                                              YesQ
                                                 a
                                                      NoD
                                                         D
YesH
D
B
H
H
D
No D
S
D
D
D
H
         NoD
            D
         NoD
            a
            a
            a
         NO a
            a
YesQ
a
0
a
s
NoD
n
n
n
D
RAVENSWOOD POWER PLANT
                                                    0-12

-------
       2.4  ASH HANDLING
            a.  Is the system still installed?   Yes B    No Q
            b.  Will it operate?                     H       D
            c.  Of the following items which
                need to be replaced:
                Bottom Ash Handling              YesB    NoD
                Ash Pond                             £]       Q
RAVENSWOOD POWER PLANT                                    O-13

-------
        SUPPLEMENTARY CONTROL SYSTEM DATA
        1 .   DOES THE PLANT NOW HAVE A SUPPLEMENTAL  CONTROL
            SYSTEM (SCS)?
            If yes,  attach a  description  of the  system.
        2.   IS THE PLANT CAPABLE  OF SWITCHING TO  LOW
            SULFUR FUELS?
            2.1   Storage capacity for low sulfur  fuels
                 (tons ,  bbls >  days)
            2.2   Bunkers available  for low  sulfur coal
                 storage?
            2.3   Handling  facilities  available for  low
                 sulfur  fuels
                 If  yes, describe _
        3.
       5.
2.4  Time required to switch fuels and fire
     the low sulfur fuel  in the boiler (hrs)?
IS THE PLANT CAPABLE OF LOAD SHEDDING?
If yes, discuss
       4.   IS THE PLANT CAPABLE OF LOAD SHIFTING?
            If yes, discuss 	
POWER PLANT MONITORING SYSTEM
5.1   Existing system
     a.   Air quality instrumentation
         (1)  Sulfur Oxides  - Continuous
                            - Intermittent
                            - Static
         (2)  Suspended  particulates
                            - Intermittent
                            - Static
         (3)  Other  (describe)	___
     b.   Meteorological  instrumentation
         If yes,  describe
     c.
                    Is the monitoring data available?
                d.  Is the monitoring data reduced and
                    analyzed?
                e.  Provide map of monitoring  locations
RAVENSWOOD POWER PLANT
                                                    Yes
             No  G
                                                    Yes  Q   No
                                                    Yes  G   No  G

                                                    Yes       No  O
                                                    Yes
   Yes

   Yes
Number
Yes

Yes
                                                                         No  G
                                                                         N°  o
                                                                         No
                                                                       Type
             No D

             No D
                                                         0-14

-------
         5.2  Proposed system                                 Yes  f"D   No
              If yes, describe and  provide map	
                  Air monitoring instrumentation           Number     Type

                  (1)  Sulfur oxides - Continuous           	     	
                                     - Intermittent         	
                                     - Static              	
                  (2)  Suspended particulate
                                     - Intermittent         	     	
                                     - Static
                  (3)  Other (describe)  	

                  Meteorological  instrumentation
                  If yes, describe 	
RAVENSWOOD  POWER  PLANT                                           0_15

-------
 Photo No.  1  View from the roof  of  Boiler 30  facing  northeast.
 The surrounding urbanized Queens area  is shown across  the center
 of the photograph.
   Photo No.  2  View  from  the  roof of Boiler  30  looking east.
   A  portion  of the ESP house  is  shown across  the bottom of  the
   photo.   Part of Stack 30  is shown on  the right side of  the
   photograph.
RAVENSWOOD POWER PLANT
0-16

-------
 Photo No.  3  View  from  the boiler  house  roof  facing  northwest.
 Turbines  4 through  11 are shown  in the center of  the photo.
 To  their  right are  shown a fuel  oil  tank and  two  gas turbines.
 The Welfare  Island  Bridge is  shown just  left  of center.
  Photo  No.  4   View  from the  roof  of  Boiler 30  looking south-
  southeast.   Stacks 10  and 20  are shown in the center of the
  photo  from right to left,  respectively.
RAVENSWOOD POWER PLANT
0-17


-------
 Photo  No.  5  View from the boiler house roof facing  south-
 southwest.  The coal crusher house is shown in the center
 of the photo.  To its right and left, respectively,  are  shown
 coal conveyors A and B.  The top half of the photo shows the
 59th Street Bridge crossing the East River.
      £
      i*
      •'/£.'
<£•*
Photo No.  6   View  from  the roof of Boiler 20 facing east.   Oil
transfer pumps  for Boilers 10 and 20 are shown just left of
center.   The natural  gas meter and regulation station are shown
left of  the  pumps.
RAVENSWOOD POWER PLANT
                                                        0-18

-------
Photo No. 7  View from the boiler house roof looking southwest,
The Vernon switch station is shown in the bottom left portion
of the photo.  The ash silo is shown just right of center.
  Photo No. 8  View from the roof of Boiler 10 facing south.
  Queensboro Park is shown in the center of the photograph.
  The switchyard and 59th Street Bridge are shown at the
  bottom and top of the photo, respectively.
RAVENSWOOD POWER PLANT
0-19

-------
 Photo No.  9  View from ground level facing north.   The coal
 unloading tower is shown in the center of the photo.   Conveyor
 A is shown rising upward at left.
 Photo  No.  10   View  from  ground  level  looking  south-southeast
 Cooling water  circulating  pumps are shown  in  the  center  of
 the photo.
RAVENSWOOD POWER PLANT
0-20

-------
 Photo  No.  11   View from the parking lot facing west.   The
 Ravenswood power  plant is  at left and its  steam plant is shown
 right  of  center.   The steam plant's two stacks are a,lso shown.
 Photo  No.  12   View from ground level  looking southwest.   The
 I.D.  fan installations for Boilers 10 and 20 are shown respec-
 tively,  from  left to  right across the center of the photograph
RAVENSWOOD POWER PLANT
0-21

-------
         TABLE 0-1.   ESTIMATED CAPITAL COST OF A SODIUM
        SOLUTION REGENERABLE SYSTEM FOR BOILER 30 AT THE
                  RAVENSWOOD POWER PLANT (1978)
Direct Costs
A.   Soda Ash Preparation
     Storage silos
     Vibrating feeders
     Storage tanks
     Agitators
     Pumps and motors

B.   SO2 Scrubbing
     Absorbers
     Fans and motors
     Pumps and motors
     Reheaters
     Soot blowers
     Ducting
     Valves

C.   Purge Treatment
     Refrigeration unit
     Heat exchangers
     Tanks
     Dryer
     Elevator
     Pumps and motors
     Centrifuge
     Crystallizer
     Storage silo
     Feeder
                                                       89,000
                                                        6,000
                                                       32,000
                                                       26,000
                                                        2,000
                                        Total A = $   155,000

                                                  $20,570,000
                                                    2,275,000
                                                      602,000
                                                    3,595,000
                                                    2,608,000
                                                   10,690,000
                                                    1,674,000
                                        Total B = $42,014,000

                                                  $   585,000
                                                       87,000
                                                      101,000
                                                       32,000
                                                       15,000
                                                      493,000
                                                    1,171,000
                                                    1,405,000
                                                       89,000
                                                        6,000
                                        Total C = $ 3,984,000
 (continued)
RAVENSWOOD POWER PLANT
                                                          0-22

-------
 TABLE O-l (continued)
 D.   Regeneration
      Pumps and motors                             $    317,000
      Evaporators and reboilers                       5,268,000
      Heat exchangers                                   690,000
      Tanks                                              77,000
      Stripper                                          154,000
      Blower                                            225,000
                                    Total D =      $  6,731,000

      Particulate Removal
      Venturi scrubber                             $  9,030,000
      Tanks                                             262,000
      Pumps and motors                                2,642,000
                                    Total E =      $ 11,934,000
      Total direct costs = A + B + C + D + E = F=$ 64,818,000
 Indirect Costs
      Interest during construction                 $  6,482,000
      Field labor and expenses                        6,482,000
      Contractor's fee and expenses                   3,241,000
      Engineering                                     6,482,000
      Freight                                           810,000
      Offsite                                         1,944,000
      Taxes                                                 000
      Spares                                            324,000
      Allowance for shakedown                         3,241,000
      Acid plant                                      2,498,000
                     Total  indirect costs  G =       $  31,504,000
                     Contingency  H =                 19,264,000
                     Total  =  F  +  G  +  H  =            $115,586,000
                     Coal conversion  cost                863,000
                     Grand  total                    $116,449,000
                     $/kW                                 145.56

RAVENSWOOD POWER PLANT                                    0-23

-------
      TABLE  0-2.   ESTIMATED  ANNUAL OPERATING  COST OF  A SODIUM
         SOLUTION  REGENERABLE  SYSTEM FOR  BOILER  30 AT THE
                   RAVENSWOOD  POWER PLANT (1978)
                     Quantity
                                      Unit Cost   Annual Cost
Raw Materials
Soda Ash 0.84 tons/h
Utilities
$90.36/ton $ 421,000
 Process water
 Cooling water
 Electricity
 Reheat steam
 Process steam

 Operation  Labor

 Direct labor
 Supervision

 Maintenance
                  4168 gal/min       $0.66/10^ gal     912,000
                  16.5 x 103 gal/min $0.01/10  gal      56,000
                  19078 kW           33.3 mills/kWh  3,504,000
                  137 x 106 Btu/h    $1.696/106 Btu  1,278,000
                  234 x 106 Btu/h    $1.699/106 Btu  2,193,000
                  4 men/day
                  15% of direct labor
$10.67/man-hour
 Labor  and materials   4%  of  fixed  investment
 Supplies             15%  of  labor  and materials

 Overhead
374,000
 56,000
                                                     4,623,000
                                                       694,000
 Plant
 Payroll

 Fixed  Costs
                    50% of operating and maintenance 2,874,000
                    20% of operating labor
                   86,000
 Depreciation
                    (3.70%)
Interim replacement (0.35%)
Insurance           (0.30%)
Taxes               (4.00%)
                              E =  19.55% of  fixed
                                    investment
Capital cost        (11.20%)
Total  fixed cost

Total  cost

Credits  (byproducts)
                                                    22,597,000

                                                  $ 39,668,000
Sulfuric acid 11.64 tons/h
Na2S04 0.84 tons/h
Total byproduct credits
Fuel credit
Net annual cost
Mills/kWh
$58.41/ton (3,754,000)
$71.63/ton (334,000)
$ (4,088,000)
(26,149,000)
$ 9,431,000
2.13
RAVENSWOOD POWER PLANT
                                                          0-24

-------
          Table  0-3.   RETROFIT  EQUIPMENT AND FACILITIES

          FOR THE  SODIUM  SOLUTION  REGENERABLE  SYSTEM

          FOR BOILER  30 AT THE RAVENSWOOD POWER PLANT
   Module
 Description
 Number
Required
    Size/Capacity
 Absorbers

 Flue gas fans

 Na-CO., storage

 Na-CO., preparation

 $©2 regeneration

 Purge treatment

 Sulfuric acid plant
   8

   8

   1

   1

   1

   1

   1
100 MW capacity unit

Scaled to train size

605 tons (30-day storage

1680 Ib/hr,  Na2CO3

12,850 Ib/hr, SO2

1680 Ib/hr,  Na2SO.

146 tons/day, HSO.
RAVENSWOOD POWER PLANT
                                 0-25

-------
       Table 0-4.  RETROFIT EQUIPMENT DIMENSIONS REQUIRED

           FOR THE SODIUM SOLUTION REGENERABLE SYSTEM

           FOR BOILER 30 AT THE RAVENSWOOD POWER PLANT
      Item
 Number
required
     Dimensions, ft
 Na-CO, storage

 Absorber feed surge
  tank
 Turbulent contact
  absorbers

 Regeneration plant

 Purge treatment plant

 Acid plant
   1

   1
   1

   1

   1
20 diam x 45 high

40 diam x 40 high


45 high x 15 wide x 40 long


65 x 180

65 x 190

75 x 155
RAVENSWOOD POWER PLANT
                                0-26

-------
.
1
1
o
•z.
1
13
«x
_J
0.
EAST RIVER
gj^^j^^<^-"*^~^^===^^^ 	 	 — *-- — ^^=^^~r-
FLY ASHQO
SILOS ^Y^
FUTURE
VERNON SUBSTATION

L-J DOCK COAL CONVEYORS U
T|NNSFER STATIONARY ST
T°WEP COAL TOWER
RAVENSWOOD POWER PLANT
BOILER BOILER BOILER
NO. 10 NO. 20 NO. 30
STACK STACK
ONO. 1 DNO. 2 STACK
(Pb (Hi (fli (ft* 1 v_x
,f~j, jtfSk *^» j/^i
°°r (QJ | Esp J| Esp |

X
G WHARF_____^ BULKHEAD LINE
r"^ ln'7Tflrii' ... .—
ACK^l \o5TACK
L 1 _J TURBINE HOUSE
L- L— r
BOILER
'USE A 2,000,000 GAL^
OIL TANK \J _ OIL
UTANK !
AB . — — — i i
UNIT 2 UNIT 3


V GAS TURBINES
                                                                                        cs:
                                                                                        CO
                                      VERNON BOULEVARD
o
(o
            A  PURGE TREATMENT AND
               S02 REGENERATION

            B  ACID
            C  SCRUBBERS
            D  STORAGE SILO
            E  SOLUTION TANK

   Figure  O-l.  Site plan showing possible locations of major  components

for the  sodium solution  regenerable  system for Boiler 30 at the  Ravenswood
                                 power plant.

-------
        TABLE 0-5.  ESTIMATED CAPITAL COST OF A LIMESTONE
  SCRUBBING SYSTEM FOR BOILER 30 AT THE RAVENSWOOD POWER PLANT
                             (1978)

Direct Cost
A.   Limestone Preparation
     Conveyors                                    $   453,000
     Storage silo                                     100,000
     Ball mills                                       724,000
     Pumps and motors                                 206,000
     Storage tanks                                    171,000
                                   Total A =      $ 1,654,000
B.   Scrubbing
     Absorbers                                    $16,557,000
     Fans and motors                                2,527,000
     Pumps and motors                               1,254,000
     Tanks                                            992,000
     Reheaters                                      3,595,000
     Soot blowers                                     978,000
     Ducting and valves                            10,930,000
                                   Total B =      $36,833,000
     Sludge Disposal
     Clarifiers                                   $   346,000
     Vacumm filters                                   484,000
     Tanks and mixers                                  12,000
     Fixation chemical storage                         33,000
     Pumps and motors                                 108,000
     Sludge pond                                    2,103,000
     Mobile equipment                                  64,000
                                   Total C =      $ 3,150,000
(continued)
RAVENSWOOD POWER PLANT                                    O-28

-------
TABLE 0-5  (continued)
D.   Particulate Removal
     Venturi scrubber                             $   9,030,000
     Tanks                                              265,000
     Pumps and motors                                   348,000
                                        Total D = $   9,643,000
     Total direct costs =A+B+C+D=E=     $  51,280,000
Indirect Costs
     Interest during construction                 $   5,128,000
     Field overhead                                   5,128,000
     Contractor's fee and expenses                    2,564,000
     Engineering                                      5,128,000
     Freight                                            641,000
     Offsite                                          1,538,000
     Taxes                                                  000
     Spares                                             256,000
     Allowance for shakedown                          2,564,000
               Total indirect costs F =           $  22,947,000
               Contingency G =                       14,845,000
               Total =E+F+G=                $  89,072,000
               Coal conversion costs                    863,000
               Grand total                        $  89,935,000
               $/kW                                      112.42
RAVENSWOOD POWER PLANT                                    0-29

-------
        TABLE 0-6.  ESTIMATED ANNUAL OPERATING COST OF A
         LIMESTONE SCRUBBING SYSTEM FOR BOILER 30 AT THE
                  RAVENSWOOD POWER PLANT (1978)
                     Quantity
                  Unit Cost
                Annual Cost
Raw Materials

Limestone
Fixation chemicals

Utilities

Water
Electricity
Fuel for reheat

Operating Labor

Direct labor
Supervision

Maintenance

Labor and materials
Supplies

Overhead

Plant
Payroll

Trucking

Bottom/fly ash and
  sludge removal

Fixed Costs
16.2 tons/h
67.0 tons/h
$16.81/ton
$2.20/ton
290 gal/min       $0.66/10  gal
15,633 kW         33.3 mills/kWh
136.5 x 106 Btu/h $1.696/106 Btu
3 men/day
$10.67/man-hour
15% of direct labor
4% of fixed investment
15% of labor and material
50% of operation and maintenance
20% of operating labor
$ 1,510,000
    817,000
                     64,000
                  2,872,000
                  1,278,000
    281,000
     42,000
                  3,563,000
                    534,000
                  2,210,000
                     65,000
                                   12,242,000
Depreciation        (3.70%)
Interim replacement (0.35%),

Insurance           (0.30%)
Taxes               (4.00%)
Capital cost       (11.20%)
Total fixed charges

Total cost
Fuel credit

Net annual cost
Mills/kWh
        £ = 19.55% of fixed
              investment
                                   17,414,000

                                  $42,892,000
                                  (26,149,000)

                                  $16,743,000
                                         3.79
 RAVENSWOOD POWER PLANT
                                      O-30

-------
       Table 0-7.   RETROFIT EQUIPMENT AND FACILITIES REQUIRED

          FOR THE  LIMESTONE SCRUBBING SYSTEM FOR BOILER 30

                AT THE RAVENSWOOD POWER PLANT
   Module  Description
  Limestone  storage

  Limestone  slurry

  Turbulent  contact

   absorbers

  Flue gas fans
 Number
Required
   1

   1

   8
    Size/Capacity
11,700 tons  (30 day storage)

16.2 ton/hr limestone

100 MW unit/s



Scaled to train size
RAVENSWOOD POWER PLANT
                                                          0-31

-------
       Table 0-8.   RETROFIT EQUIPMENT DIMENSIONS REQUIRED
        FOR THE LIMESTONE SCRUBBING SYSTEM FOR BOILER 30
              AT THE RAVENSWOOD POWER PLANT
       Item
 Number
Required
      Dimensions, ft
 Limestone storage pile
 Limestone silos•
 Limestone slurry  tanks
 Ball mill building
 Turbulent contact
   absorbers
 Clarifiers
 Vacuum filter building
   1
   3
   1
   1
   8

   2
   1
115 wide x 170 long
17 diam x 38 high
60 diam x 20 high
40 x 40
45 high x 15 wide x 30 long

75 diam x 20 high
40 x 40
RAVENSWOOD POWER PLANT
                              0-32.

-------
s
EAST RIVER S
1
o
1
o
>-
CL
FLY ASH/7\O
SILOS yW
FUTURE
VERNON SUBSTATION
I— > DOCK COAL CONVEYORS U
TRANSFER STATIONARY ST
TOWER COAL TOWER
RAVENSWOOD POWER PLANT
BOILER BOILER BOILER
NO. 10 NO. 20 NO. 30
STACK STACK
QNO. 1 ONO. 2 STACK
©,<=•.,<=»,,«=>, f^NO 3
O' O O \^/
0^*. *•*. ^a.
^^ I ESP II ESP I

G WHARF______^ BULKHEAD LINE
loCTflrii' .— —
' L_j-^ TURBINE HOUSE
BU1LLK
HOUSE A x^=^
?,nnn,nnn GAI f^i
OIL TANK \J ^ OIL
LIMESTONE STORAGE UTANK '

® OOOLlJ UNIT 2 UNIT 3
C
©/~*\
(^} GAS TURBINES
                                                                                                   UJ
                                                                                                   CD
                                                                                                   cn
                                                                                                   5
                                                                                                   m
                                                                                                   o
                                                                                                   2
                                                VERNON BOULEVARD
O
w
u>
              A  SCRUBBERS
              B  SLURRY TANK
              C  LIMESTONE SILOS
              D  BALL MILL BUILDING
              E  CLARIFIER
              F  VACUUM FILTER BUILDING

Figure  O-2.   Site plan showing  possible locations of major components for
    the limestone system for Boiler 30 at  the Ravenswood power plant.

-------
                          APPENDIX P




                     RIDGELAND  POWER PLANT
RIDGELAND POWER PLANT                                     P-l

-------
                            CONTENTS



Ridgeland Power Plant Survey Form

Ridgeland Power Plant Photographs
                                                  Page

                                                  P-4

                                                  P-21
Number
 P-l
 P-2
 P-3
                             FIGURES
Site Plan Showing Possible Location of Major
Components for the Sodium Solution Regenerable
System for Boilers 1,2,3,4,5, and 6 at the
Ridgeland Power Plant

Site Plan Showing Possible Location of Major
Components for the Limestone System for Boilers
1,2,3,4,5, and 6 at the Ridgeland Power Plant

Site Plan Showing Possible Locations of New
ESP's for Boilers 1,2,3,4,5 and 6 at the
Ridgeland Power Plant
                                                  Paqe
                                                            P-31
                                                            P-37
                                                            P-41
Number
 P-l
 P-2
 P-3
                             TABLES
Estimated Capital Cost of a Sodium Solution
Regenerable System for Boilers 1 through 6
at the Ridgeland Power Plant (1978)
                                                  Page
                                                            P-26
Estimated Annual Operating Costs of a Sodium
Solution Regenerable System for Boilers 1 through
6 at the Ridgeland Power Plant (1978)             P-28

Retrofit Equipment Dimensions Required for the
Sodium Solution Regenerable System for Boilers
1,2,3,4,5, and 6 at the Ridgeland Power Plant     P-29
RIDGELAND POWER PLANT
                                                  P-2

-------
                       TABLES  (continued)

Number                                                       Page

 P-4      Retrofit Equipment Dimensions  Required  for  the
          Sodium Solution Regenerable System  for  Boilers
          1,2,3,4,5, and 6 at  the  Ridgeland Power Plant      P-30

 P-5      Estimated Capital Cost of a Limestone Scrubbing
          System for Boilers 1 through 6 at the Ridgeland
          Power Plant  (1978)                                 P-32

 P-6      Estimated Annual Operating Costs of a Limestone
          Scrubbing System for Boilers 1 through  6 at the
          Ridgeland Power Plant  (1978)                       P-34

 P-7      Retrofit Equipment and Facilities Required  for
          the Limestone Scrubbing  System for Boilers
          1,2,3,4,5, and 6 at  the  Ridgeland Power Plant      P-35

 P-8      Retrofit Equipment Dimensions  Required  for  the
          Limestone Scrubbing  System for Boiler 1,2,3,4,5,
          and 6 at the Ridgeland Power Plant                 P-36

 P-9      Estimated Capital Cost of Electrostatic
          Precipitators for Boilers 1 through 6 at the
          Ridgeland Power Plant  (1978)                       P-38

 P-10     Estimated Annual Operating Costs of Electro-
          static Precipitator  for  Boilers 1 through 6
          at the Ridgeland Power Plant (1978)                P-39

 P-ll     Electrostatic Precipitator Design Values for
          Boilers 1,2,3,4,5, and 6 at the Ridgeland
          Power Plant                                        P-40
RIDGELAND POWER PLANT                                       P-3

-------
                                         OMB No.  158S  74023
                  POWER PLANT SURVEY FORM


 A.   COMPANY INFORMATION:

      1.  COMPANY NAME:   Commonwealth Edison

      2.  MAIN OFFICE:    P.O.  Box 767

      3.  RESPONSIBLE OFFICER:    J-  P.  McCluskey

      4.  POSITION:   Director  of Environmental Affairs

      5.  PLANT NAME:  Ridgeland Station

      6.  PLANT LOCATION:  4300 South Ridgeland Avenue

      7.  RESPONSIBLE OFFICER AT PLANT LOCATION:  T.  F. McKeon

      8.  POSITION:  Station Superintendent

      9.  POWER POOL     MAIN
      DATE INFORMATION GATHERED:  July 27,  1976
      PARTICIPANTS IN MEETING:
       J.  P.  McClusky
       W.  L.  Ramsey
       Mike Trykoski
       Walter N.  Kozlowski
       Lee Hermansen
       Ron Cook
       A.  0.  Courtney
       Eugene H.  Reinstein
       Thomas C.  Ponder,  Jr.
       N.  David Noe
       Richard T.  Price
Commonwealth Edison Company
Commonwealth Edison Company
Commonwealth Edison Company
Commonwealth Edison Company
Commonwealth Edison Company
Commonwealth Edison Company
Commonwealth Edison Company
Ishan, Lincoln, and Beale
PEDCo Environmental, Inc.
PEDCo Environmental, Inc.
PEDCo Environmental, Inc.
RIDGELAND POWER PLANT
                           P- 4

-------
       B.
£
z
D

13
O
13

£
z
•-3
13
I
en
ATMOSPHERIC EMISSIONS
1. PARTICULATE EMISSIONS3
LB/MM BTU
GRAINS/ACF
LB/HR (FULL LOAD)
TONS/YEAR (1975)
2 . APPLICABLE PARTICULATE EMISSION
REGULATION
a) CURRENT REQUIREMENT
AQCR PRIORITY CLASSIFICATION
REGULATION & SECTION NO..
LB/MM BTU
OPACITY, PERCENT
b) FUTURE REQUIREMENT (DATE: )
REGULATION S, SECTION NO.
LB/MM BTU
3. S02 EMISSIONS3 (Oil)
LB/MM BTU
LB/HR (FULL LOAD)
TONS/YEAR ( )
4. APPLICABLE S02 EMISSION REGULATION
a) CURRENT REQUIREMENT
REGULATION & SECTION NO.
LB/MM BTU (liquid fuel)
LB/MM BTU (solid fuel)
b) FUTURE REQUIREMENT (DATE: )
REGULATION & SECTION NO.
LB/MM BTU
Boiler number
1
.06
-





























2
.06
—





Cook Count













Cook Counl
In

-1.8 	




3
.06
_





y Ordinanc
-0.1 Ib/Ml
-30% (6.1-




n Q r\

— A RQ f>— —

— 1 ? 7c;n-
J-^/JDU —
y Ordinanc



_ XT A _ _



Jl
.06
_





:e 6.2-2(b)


1 (t>) ) 	










:e 6.31(d)







t;
.06
_




















2\ i •; ^ ___ .
) ( i j 	










      a)  Identify whether results  are  from stack tests or  estimates

-------
       B.
M
D
n
w
o
=3
 I
CTi
ATMOSPHERIC EMISSIONS
1. PARTICULATE EMISSIONS3
LB/MM BTU
GRAINS/ACF
LB/HR (FULL LOAD)
TONS/YEAR ( )
2. APPLICABLE PARTICULATE EMISSION
REGULATION
a) CURRENT REQUIREMENT
AQCR PRIORITY CLASSIFICATION
REGULATION & SECTION NO..
LB/MM BTU
OPACITY, PERCENT
b) FUTURE REQUIREMENT (DATE: )
REGULATION & SECTION NO.
LB/MM BTU
3. SO- EMISSIONS3
LB/MM BTU
LB/HR (FULL LOAD)
TONS/YEAR ( )
4. APPLICABLE S0_ EMISSION REGULATION
a) CURRENT REQUIREMENT
REGULATION & SECTION NO.
LB/MM BTU
LB/MM BTU
b) FUTURE REQUIREMENT (DATE: )
REGULATION & SECTION NO.
LB/MM BTU
Boiler number
6
.06
-


__ 	






































































































               nt
wl-
                                    .ul
                                           ire
                                                  om
icfc
st:
                                                                       •  e
aa1

-------
C.  SITE DATA
    1. U.T.M. COORDINATES
    2. ELEVATION ABOVE MEAN  SEA  LEVEL (FT)
    3. SOIL DATA:  BEARING VALUE
            PILING NECESSARY   yes	
    4. DRAWINGS REQUIRED
       PLOT PLAN OF SITE  (CONTOUR)
       EQUIPMENT LAYOUT AND ELEVATION
       AERIAL PHOTOGRAPHS OF SITE  INCLUDING POWER PLANT,
       COAL STORAGE AND ASH DISPOSAL AREA
    5. HEIGHT OF TALLEST BUILDING  AT PLANT SITE OR    128.0 ft.*
       IN CLOSE PROXIMITY TO STACK (FT.  ABOVE GRADE)
    6. HEIGHT OF COOLING TOWERS  (FT. ABOVE GRADE) ;  N/A	

       * Height of  stack:  213  ft.
RIDGELAND POWER PLANT                                     p_7

-------
D
O
W
f

I
O
1
I
oo
      D.
BOILER DATA
1. SERVICE: BASE LOAD
STANDBY, FLOATING, PEAK
2. TOTAL HOURS OPERATION (19 75)
3. AVERAGE CAPACITY FACTOR (1975 )
4. SERVED BY STACK NO.
5. BOILER MANUFACTURER a
6. YEAR BOILER PLACED IN SERVICE
7 . REMAINING LIFE OF UNIT b
8. GENERATING CAPACITY (MW)
-RATED Summer Gross
Summer Net
PEAK
9. FUEL CONSUMPTION :CGas 1Q3 ft3/hr
COAL OR OIL RATED g°f (^f
MAXIMUM CONTINUOUS
PEAK
10. ACTUAL: FUEL CONSUMPTION
Gas (10* fWyr) (1975) -
COAL (TPY) (19 79
OIL (eW) (19 73
11. HEAT RATE BTU/KWHR GAS
COALd
OIL
12. WET OR DRY BOTTOM
13. FLY ASH REINJECTION (YES OR NO)
14. STACK HGT ABOVE GRADE (FT.)
15. I.D. OF STACK AT TOP (INCHES)
Boiler number
1

6302
52.7
1
B&W
1951
N/A
Unit 1
166
152

821.1
42.7
136.3

B?Wgr
None
1219.3

10.861
11,376 E
- Wet
No
213
96
2
	 	 Flc
5129
47.8
2
B&W
1951
N/A
—
—

821,1
42.7
136.3

1 and 2


11,216
TU/NKWH -
Wet
No
213
96
1
atinq 	
7134
56.1
3
B&W
1950
N/A
Unit 2
166
152

821 1
42.7
136.3

Boiler
20.3
None
1488.6

9,859
Station Tc
Wet
No
213
96
4

6666
51.8
4
B&W
1950
N/A
^_
—

R71 1
42,7
136.3

3 and 4


9.737
tal
Wet
No
213
96
q

3925
31 .2
5
B&W
1 95T
N/A
Unit 3
151
137

1423
74
.236.2

548.8
None
599.2



Wet -
No
213
118
        Notes:
                     The Babcock & Wilcox Company
                     Plant - 1986.

                     L^.0^ it. va
data at
                                                  ra<_j.ng
                             Station avg.  - 10,623 BTUAWn(net) on
                                                    Lno   Coa

-------
      D.
50"
M
a
o
w
z
D
o
s
ra
JO
£
25
 I

vo
BOILER DATA
1. SERVICE: BASE LOAD
STANDBY, FLOATING, PEAK
2. TOTAL HOURS OPERATION (19 75)
3. AVERAGE CAPACITY FACTOR (1975)
4 . SERVED BY STACK NO .
5. BOILER MANUFACTURER **
6. YEAR BOILER PLACED IN SERVICE
7. REMAINING LIFE OF UNIT b
8. GENERATING CAPACITY (MW)
)
PEAK
9. FUEL CONSUMPTION:0
COAL OR OIL RATED £°f ( 
-------
D
O
W
O
s;
w
£
z
16. FLUE GAS CLEANING EQUIPMENT
a) MECHANICAL COLLECTORS
MANUFACTURER
TYPE
EFFICIENCY: DESIGN/ACTUAL (%)
MASS EMISSION RATE:
(GR/ACF)
(#/HR)
(#/MM BTU)
b) ELECTROSTATIC PRECIPITATOR
MANUFACTURER
TYPE
EFFICIENCY: DESIGN/ACTUAL (%)
MASS EMISSION RATE
(GR/ACF)
(#/HR)
(#/MM BTU)
NO. OF IND. BUS SECTIONS
TOTAL PLATE AREA (FT^)
FLUE GAS TEMPERATURE
@ INLET ESP @ 100% LOAD (°F)
17. EXCESS AIR: DESIGN /ACTUAL (%)
Boiler number
1
None





(1)
Res. Cott
(2) E
98%




4
25,200
?«S
18
•)
None





(1)
Res. Cott
(2)E
98%




4
25,200
385
18
T
None





(1)
Res. Cott
(2)E
98%




4
25,200
385
18
A
None





(1)
Res. Cott
(2) E
98%




4
25,200
385
18
5
Nonp





(1)
Res. Cott
(2) E
90%




4
60,500
334
10
13
I
      Notes
(1)  Res.  Cott - Research Cottrell, Inc.

(2)  E - Electrostatic Precipitator

-------
z

D
o
s;
w
1.6. FLUE GAS CLEANING EQUIPMENT
a) MECHANICAL COLLECTORS
MANUFACTURER
TYPE
EFFICIENCY: DESIGN/ACTUAL (%)
MASS EMISSION RATE:
(GR/ACF)
(#/HR)
(#/MM BTU)
b) ELECTROSTATIC PRECIPITATOR
MANUFACTURER
TYPE
EFFICIENCY: DESIGN/ACTUAL (%)
MASS EMISSION RATE
(GR/ACF)
(#/HR)
(#/MM BTU)
NO. OF IND. BUS SECTIONS
TOTAL PLATE AREA (FT^)
FLUE GAS TEMPERATURE
@ INLET ESP @ 100% LOAD (°F)
17- EXCESS AIR: DESIGN/ACTUAL (%)
Boiler number
6
None





(1)
Res . Cott
(2) E !
90%




8
600,500
334
10








































































   Notes:
(1)  Res.  Cott -  Research Cottrell


(2)  E -  Electrostatic Precipitator

-------
D
O
W
f
>
z
a

13
o
s
w
£
z
18. FLUE GAS RATE (ACFM)
@ 100% LOAD (Design)
6 75% LOAD
@ 50% LOAD
19. STACK GAS EXIT TEMPERATURE (°F)a
@ 100% LOAD (High)
@ 75% LOAD
@ 50% LOAD
20. EXIT GAS STACK VELOCITY (FPS)a
@ 100% LOAD
@ 75% LOAD
@ 50% LOAD
21. FLY ASH: TOTAL COLLECTED (TONS/YEAR)
DISPOSAL METHOD
DISPOSAL COST ($/TON)
22. BOTTOM ASH: TOTAL COLLECTED (TONS/
DISPOSAL METHOD b YEAR)
DISPOSAL COST ($/TON)
23. EXHAUST DUCT DIMENSIONS @ STACK
24. ELEVATION OF TIE IN POINT TO STACK
25. SCHEDULED MAINTENANCE SHUTDOWN
(ATTACH PROJECTED SCHEDULE)
Boiler number
1
384,000
288,000
192,000
335 <2)
310 ">
285 (2)
(2)
127.4
95.6(2)
63.7(2)


None

(See at-


2
384,000
288,000
192,000
335 (2)
310 (2)
285 (2)
(2)
127.4
95.6(2)
63.7(2)




ached drav


3
384,000
288,000
192,000
335(2>
3!0(2'
285(2)
(2)
127.4
95.6(2)
63.7(2)
500 tons
$66,000 tc


ings)


4
384,000
288,000
192,000
335{2)
310(2)
285(2)
(2)
127.4
95.6(2)
63.7(2)

tal 	





5
546,000
409,300
273,000
350 (2>
310 (2)
275 (2)
(2)
119.9
89. 9m
60.0 (2)







     a)  Identify  source  of  values  (test  or Estimate)



     Notes:  bwaste Water Treatment.

-------
 D
 n
 w
 z
 D
 O
 5
 w
 50
18. FLUE GAS RATE (ACFM)
@ 100% LOAD
@ 75% LOAD
@ 50% LOAD
19. STACK GAS EXIT TEMPERATURE (°F)a
@ 100% LOAD
6 75% LOAD
@ 50% LOAD
20. EXIT GAS STACK VELOCITY (FPS)a
e 100% LOAD
@ 75% LOAD
@ 50% LOAD
21. FLY ASH: TOTAL COLLECTED (TONS/YEAR)
DISPOSAL METHOD
DISPOSAL COST ($/TON)
22. BOTTOM ASH: TOTAL COLLECTED (TONS/
DISPOSAL METHOD YEAR)
DISPOSAL COST ($/TON)
23- EXHAUST DUCT DIMENSIONS @ STACK
24. ELEVATION OF TIE IN POINT TO STACK
25. SCHEDULED MAINTENANCE SHUTDOWN
(ATTACH PROJECTED SCHEDULE)
Boiler number
6
54 fi, nno
409.500
273.000
(2) 350
310 (2)
275 (2)
119.9(2)
39.9m
60.0 (2)


None

(See attac
















hed drawir
















gs)




































I
t->
U)
a) Identify source  of  values (test or estimate)


Notes:

-------
o
en
n

|

a


o

w

E . I . D . FAN DATA
1. MAXIMUM STATIC HEAD (IN. W.G.)
2. WORKING STATIC HEAD (IN. W.G.)

1
(1)16
14.5
Bo
2
(1)16
14.5
iler numbe
1
(1)16
14.5
r
4
(1)16
14.5

*
(2)18.4
12.9
Notes:
                  ' Based on 700,000  Ib/hr .  steam
                (2)
                   Based on 1,100,000  Ib/hr.  steam
i

M
*».

-------
K
f
E . I . D . FAN DATA
1. MAXIMUM STATIC HEAD (IN. W.G.)
2. WORKING STATIC HEAD (IN. W.G.)
Boiler number
6
(2)
18.4
12.9












o
s
w
Notes:
13

£
Z

-------
     FLY ASH DISPOSAL AREAS
     1.   AREAS AVAILABLE (ACRES)  None
     2.   YEARS STORAGE (ASH ONLY)
     3.   DISTANCE FROM STACK (FT.)
H.
I.
J.
     4.   DOES THIS PLANT HAVE PONDING
         PROBLEMS?  DESCRIBE IN ATTACHMENT
     COAL DATA

     Coal Analysis  (1955):
         Ash  -  10.8%  by  wt (as  received);  12.2% (dry)
         Moisture  - 14.0%  by  wt
         Sulfur -  4.4% by  wt  (as  received)
         BTU/lb -  10,500  as  received);  12,400 (dry);  14,000
                   (moisture and ash free)
     (1) per our latest survey of  January 1976...  The disposal
        area  is 56.6% filled. Assuming  present fuel, 86 years
        storage remain.
     (2) Distance from Stack #1:   500  ft.
        Distance from Stack #6:   950  ft.
FUEL OIL DATA (19 73
1.
2.
3.
4.
5.
TYPE Residual
S CONTENT (%)
ASH CONTENT (%)
0.8
0.1
SPECIFIC GRAVITY N/A
HHV (BTU/GAL)
147,886
NATURAL GAS HHV  (BTU/FT3)   1034
COST DATA
ELECTRICITY
FUEL : COAL
GAS
OIL

WATER
STEAM
TAXES ON A.
STATE
P.C. EQUIPMENT:
PROPERTY TAX
STATE SALES
Not Exempt.
Yes , Exempt

RIDGELAND  POWER PLANT
                                                          P-16

-------
K.  PLANT SUBSTATION CAPACITY
M.
      APPROXIMATELY WHAT PERCENTAGE  OF  RATED
      STATION CAPACITY CAN  PLANT SUBSTATION
      PROVIDE?
      NORMAL LOAD ON PLANT  SUBSTATION?     Will have to add additional
                                          buses.
      VOLTAGE AT WHICH POWER IS  AVAILABLE?

      ADDITIONAL INFORMATION

         F.E.A.  LETTER

      OIL/GAS TO COAL CONVERSION DATA

      1.  HAS THE BOILER EVER BURNED COAL?
    2.
Boiler No.
Yes or No.
1,2,3,4,5
Yes
,6,







          SYSTEM AVAILABILITY
          2.1  COAL HANDLING
               a.  Is the system still installed?
               b.  Will it operate?
               c.  Of the following items which
                                                     D
Yes Q
m
D
0
a
El
No D
D
E
D
D
n
                   need to be replaced:
                   Unloading equipment
                   Stack Reclaimer
                   Bunkers
                   Conveyors
                   Scales
                   Coal Storage Area

          2.2  FUEL FIRING
               a.  Is the system still installed?

               b.  Will it operate?
               c.  Of the following items which
                   need to be replaced:
                   Pulverizers or Crushers
                   Feed Ducts
                   Fans
                   Controls

          2.3  GAS CLEANING
               a.  Is the system still installed?
               b.  Will it operate?
               c.  Of the following items which
                   need to be replaced:
                   Electrostatic Precipitator
                   Cyclones
                   Fly Ash Handling Equipment
                   Soot Blowers - Air  Compressors
                   Wall deslaggers
                Not Adequate For Coal Firing Under Current
                   Environmental Standards
RIDGELAND POWER PLANT
                                                  Yes0
                                                     D
                                                  Yes£]
                                                     a
                                                     n
                                                     S
                                                          NoD
NoD
No D
   D
   a
   D
NOD
   D
YesH
n
S
H
D
No D
a
n
n
a
                                                       P-17

-------
       2.4  ASH HANDLING
            a.  Is the system still installed?   Yes 0    No Q
            b.  Will it operate?                     D       S
            c.  Of the following items which
                need to be replaced:
                Bottom Ash Handling              Yes 0    NoQ
                Ash Pond                             0       D
RIDGELAND POWER PLANT                                    P-18

-------
   N-  SUPPLEMENTARY CONTROL SYSTEM DATA
       1 .   DOES THE PLANT NOW HAVE A SUPPLEMENTAL  CONTROL
           SYSTEM (SCS)?                                        Yes  Q   No  [x]
           If yes,  attach a  description  of  the  system.
       2.   IS THE PLANT CAPABLE  OF SWITCHING  TO LOW
           SULFUR FUELS?                                        Yes  Q   No
           2.1   Storage capacity for low sulfur fuels
                (tons, bbls, days)
           2.2  Bunkers available for low sulfur coal
                storage?                                        Yes        No
           2.3   Handling  facilities  available  for  low
                sulfur  fuels                                   Yes       No
                If yes , describe
           2.4  Time  required  to  switch fuels and fire
               the low  sulfur  fuel  in the boiler (hrs)?
       3.   IS THE  PLANT CAPABLE OF LOAD SHEDDING?
           If yes, discuss 	
           	i	         Yes  D   No  [xl
       4.   IS THE  PLANT CAPABLE OF LOAD SHIFTING?
           If yes, discuss 	
           	Yes  0   No  [J
       5.   POWER PLANT MONITORING SYSTEM
           5.1  Existing system                                Yes  Q   No
               a.  Air quality instrumentation             Number     Type
                   (1)  Sulfur Oxides - Continuous
                                      - Intermittent
                                      - Static
                   (2)  Suspended particulates
                                      - Intermittent
                                      - Static
                   (3)  Other (describe)	
               b.  Meteorological instrumentation
                   If yes, describe
               c.  Is the monitoring data available?          Yes  [~~j   No  |~)
               d.  Is the monitoring data reduced and
                   analyzed?                                  Yes  Q]   No
              . e.  Provide map of monitoring  locations
RIDGELAND  POWER  PLANT       -              •                     P-19

-------
       5.2  Proposed system                                Yes  F]   No

            If yes, describe and provide map	
            a.  Air monitoring  instrumentation           Number     Type

                (1)  Sulfur oxides  - Continuous          	     	
                                   - Intermittent        	     	
                                   - Static              	     	

                (2)  Suspended  particulate
                                   - Intermittent        	     	
                                   - Static
                (3)  Other (describe)
            b.  Meteorological  instrumentation

                If yes, describe  	
RIDGELAND POWER PLANT                                          P-20

-------
                                                      \
                                                       \
   Photo No. 1  View from ground level facing southwest.
   The northern portion of the plant is shown.  Two of the
   69 kV transformers are in clear view in the center of the
   photograph.
    Photo No. 2  View from the roof of Boiler 1 looking east.
    The top left of the photo shows the industrialized surround-
    ing area, the center shows an ash pond,  and the bottom of the
    photo shows rail lines.
RIDGELAND POWER PLANT
                                                         P-21

-------
                                                   '. -v.
  Photo No.  3  View  from  the  boiler  house  roof facing north.
  The gate house  and road leading  into  the plant are shown in
  the bottom left portion of  the photo.
   Photo  No.  4   View from the roof of Boiler 6 looking west.  A
   portion  of the plant's oil storage tank area is shown.  The
   densely  wooded surrounding area is shown in the background.
RIDGELAND POWER PLANT
P-22

-------
                        	       _
Photo No.  5  View  from  the  roof  of Boiler  6  facing  southwest.
Part of the coal storage area  is shown  in  the bottom left
portion of the photograph.  A  rail spur line is  shown leading
toward the plant.
     .
>tacks
,6   View  from the  roof  of  Boiler  6  looking  southeast
 through 6  are shown  from left  to  right.
RIDGELAND POWER PLANT
                                                 P-23

-------
Photo No. 7  View from the roof of Boiler 5 facing southeast.
The coal junction house is shown in the center of the photo.
The gantry crane is shown in the upper left hand corner.  The
coal car dumper is shown in the right center of the photograph.
                                  	
 Photo No.  8  View from ground level near the Boiler 1 area
 looking northwest.   Some of the plant's  4 kV transformers are
 shown in the right  center of the photograph.
RIDGELAND POWER PLANT
P-24

-------
   Photo No. 9  View from ground level facing east.  Slag
   tanks for Boilers 5 and 6 are shown in the foreground.
   The coal junction house (upper right corner)  is partially
   blocking the breaker house shown in the upper center of the
   photo.
  Photo No.  10  View from the boiler house roof  looking north.
  The warehouse is shown in the bottom center of the photo.   A
  portion of the wooded residential area is shown across the
  photograph,  just below center.
RIDGELAND POWER PLANT
                                                         P-25

-------
         TABLE P-l.  ESTIMATED CAPITAL COST OF A SODIUM
       SOLUTION REGENERABLE SYSTEM FOR BOILERS 1 THROUGH 6
               AT THE RIDGELAND POWER PLANT (1978)
Direct Costs
A.
B.
Soda Ash Preparation
Storage silos
Vibrating feeders
Storage tanks
Agitators
Pumps and motors
SO0 Scrubbing
$ 191,000
6,000
57,000
26,000
2,000
Total A = $ 272,000
     Absorbers
     Fans and motors
     Pumps and motors
     Reheaters
     Soot blowers
     Ducting
     Valves

C.   Purge Treatment
     Refrigeration unit
     Heat exchangers
     Tanks
     Dryer
     Elevator
     Pumps and motors
     Centrifuge
     Crystallizer
     Storage silo
     Feeder
Total B =
                                   Total C =
$ 17,718,000
   1,960,000
     518,000
   3^096,000
   1,956,000
   7,211,000
     824,000
$ 33,283,000

$    504,000.
      76,000
     104,000
      48,000
      15,000
     827,000
   1,008,000
   1,210,000
     191,000
       6,000
$  3,989,000
(continued)
 RIDGELAND POWER PLANT
                        P-26

-------
TABLE P-l (continued)
D.   Regeneration
     Pumps and motors                             $    603,000
     Evaporators and reboilers                      12,525,000
     Heat exchangers                                 1,652,000
     Tanks                                             138,000
     Stripper                                          235,000
     Blower                                            537,000
                                   Total D =      $ 15,690,000
     Particulate Removal
     Venturi scrubber                             $  7,779,000
     Tanks                                             212,000
     Pumps and motors                                  571,000
                                   Total E =      $  8,562,000
     Total direct costs = A + B + C + D + E = F = $ 61,796,000
Indirect Costs
     Interest during construction                 $  6,180,000
     Field labor and expenses                        6,180,000
     Contractor's fee and expenses                   3,090,000
     Engineering                                     6,180,000
     Freight                                           772,000
     Offsite                                         1,854,000
     Taxes                                                 000
     Spares                                            309,000
     Allowance for shakedown                         3,090,000
     Acid plant                                      3,659,000
               Total  indirect  costs  G  =            $  31,314,000
               Contingency  H =                      18,622,000
               Total  =  F  +  G  +  H =                 $111,732,000
               Coal conversion  costs                 17,795,000
               Grand  total                         $129,527,000
               $AW                                     215.52

 RIDGELAND POWER PLANT                                     P-27

-------
TABLE P-2.  ESTIMATED ANNUAL OPERATING COSTS OF A SODIUM SOLUTION
        REGENERABLE SYSTEM FOR BOILERS 1 THROUGH 6 AT THE
                  RIDGELAND POWER PLANT (1978)

Raw Materials
Soda ash
Utilities
Quantity

2.01 tons/h

Unit Cost

$77.02/ton

Annual

$

Cost

636,000

Process water       8375 gal/min       $0.66/10  gal       1,358,000
Cooling water       35.5 x 103 gal/min $0.01/103 gal          89,000
Electricity         19,004 kW          33.1 mills/kWh      2,568,000
Reheat steam        117.6 x 106 Btu/h  $1.685/106 Btu        810,000
Process steam       560.6 x 106 Btu/h  $1.685/106 Btu      3,861,000

Operation Labor

Direct labor        3 men/day          $9.55/man-hour        250,000
Supervision         15% of direct labor                       38,000

Maintenance

Labor and materials  4% of fixed investment                4,469,000
Supplies            15% of labor and materials               670,000

Overhead

Plant               50% of operating and maintenance       2,714,000
Payroll             20% of operating labor                    58,000

Fixed Costs

Depreciation        (7.69%)
Interim replacement (0.35%)
Insurance           (0.30%)
Taxes               (4.00%), E = 23.54% of fixed
                                   investment
Capital cost       (11.20%)

Total fixed costs                                         26,302,000

Total cost                                             $  43,823,000

Credits (byproducts)

Sulfuric acid       27.9 tons/h        $51.90/ton         (5,916,000)
Na2S04              2.01 tons/h        $42.65/ton           (352,000)

Total byproduct credits                                $  (6,268,000)
Fuel credit                                              (18,516,000)

Net annual cost                                        $  19,039,000
Mills/kWh                                                       7.73

  RIDGELAND POWER PLANT                                     p~28

-------
   Table  P-3.   RETROFIT  EQUIPMENT  DIMENSIONS  REQUIRED FOR THE

         SODIUM SOLUTION REGENERABLE  SYSTEM FOR BOILERS

    1,  2,  3,  4,  5, AND 6 AT THE RIDGELAND  POWER PLANT
   Module
 Description
 Number
Required
Size/Capacity
 Absorber



 Flue  gas  fans

 Na-CO.,  storage

 Na2C03  preparation

 SO- regeneration

 Purge treatment

 Sulfuric  acid plant
   4
   1
   1

   6

   1

   1

   1

   1

   1
80 MW unit
139 MW unit
144 MW unit

Scaled to train size

1450 tons (30-day storage)

4020 Ib/hr,  Na2C03

36,500 Ib/hr, S02

4020 Ib/hr,  Na2S04

305 ton/day, HS0
RIDGELAND POWER PLANT
                                                         P-29

-------
  Table P-4.  RETROFIT EQUIPMENT DIMENSIONS REQUIRED FOR THE

        SODIUM SOLUTION REGENERABLE SYSTEM FOR BOILERS

    1,  2,  3,  4, 5, AND 6 AT THE  RIDGELAND  POWER PLANT
       Item
 Number
Required
Dimensions, ft
 Na^CO,  storage

 Absorber  feed surge
  tank
 Turbulent contact
  absorbers

 Regeneration plant

 Purge treatment plant

 Acid plant
   4
   2

   1

   1

   1
30 diam x 60 high

44 diam x 55 high


45 high x 15 wide x 37 long
45 high x 15 wide x 56 long

100 x 250

90 x 220

105 x 220
RIDGELAND POWER PLANT
                                P-30

-------
M
§
ra
TJ


I-1
           r
            i	
                                              RIDGELAND   fRJ~!«
                                              POWER PLANT   \ '
                                                     L
            A  PURGE TREATMENT AND
              S02 REGENERATION

            B  ACID
            C  SCRUBBERS
            D  STORAGE SILO
            E  SOLUTION TANK

       Figure P-l.  Site plan showing possible  location  of  major components for  the

           sodium solution regenerable systen  for Boilers 1,2,3,4,5,  and 6 at the

                                     Ridgeland power plant.

-------
        TABLE P-5.   ESTIMATED CAPITAL COST OF A LIMESTONE
         SCRUBBING SYSTEM FOR BOILERS 1 THROUGH 6 AT THE
                  RIDGELAND POWER PLANT (1978)
Direct Cost
A.   Limestone Preparation
     Conveyors                                    $   586,000
     Storage silo                                     175,000
     Ball mills                                       971,000
     Pumps and motors                                 379,000
     Storage tanks                                    531'000
                              Total A =           $ 2,642,000
B.   Scrubbing
     Absorbers                                    $14,261,000
     Fans and motors                                2,176,000
     Pumps and motors                               1,148,000
     Tanks                                            894,000
     Reheaters                                      3,096,000
     Soot blowers                                     978,000
     Ducting and valves                             8,035,000
                              Total B =           $30,588,000
C.   Sludge Disposal
     Clarifiers                                   $   423,000
     Vacuum filters                                   619,000
     Tanks and mixers                                   14,000
     Fixation chemical storage                          58,000
     Pumps and motors                                 137,000
     Sludge pond                                    1,618,000
     Mobile equipment                                   64,000
                              Total C =            $ 2,933,000
 (continued)
  RIDGELAND POWER PLANT                                     p~32

-------
TABLE P-5 (continued)
D.   Particulate Removal
     Venturi scrubber                             $  7,778,000
     Tanks                                             243,000
     Pumps and motors                                  333,000
                                   Total D =      $  8,354,000
     Total direct costs = A + B + C + D = E =     $ 44,517,000
Indirect Costs
     Interest during construction                 $  4,452,000
     Field overhead                                  4,452,000
     Contractor's fee and expenses                   2,226,000
     Engineering                                     4,452,000
     Freight                                           556,000
     Offsite                                         1,336,000
     Taxes                                                 000
     Spares                                            223,000
     Allowance for shakedown                         2,226,000
               Total  indirect  costs  F  =            $  19,923,000
               Contingency  G =                      12,888,000
               Total  =E+F+G=                 $  77,328,000
               Coal conversion costs                 17,795,000
               Grand  total                         $  95,123,000
               $/kW                                     158.27
 RIDGELAND POWER PLANT                                     P-33

-------
   TABLE P-6.  ESTIMATED ANNUAL OPERATING COSTS OF A LIMESTONE
    SCRUBBING SYSTEM FOR BOILERS 1 THROUGH 6 AT THE RIDGELAND
                       POWER PLANT  (1978)

Raw Materials
Limestone
Fixation chemicals
Quantity
38.9 tons/h
100 tons/h
Unit Cost
$13.06/ton
$2.20/ton
Annual Cost
$
2,079,000
903,000
Utilities

Water               250 gal/min       $0.66/103 gal     41,000
Electricity         14,205 kW         33 mills/kWh   1,920,000
Fuel for reheat     117.6 x 106 Btu/h $1.685/106 Btu   810,000

Operating Labor

Direct labor        3 men/day         $9.55/man-hour   251,000
Supervision         15% of direct labor                 38,000

Maintenance

Labor and materials 4% of fixed investment           3,093,000
Supplies           15% of labor and material           464,000

Overhead

Plant              50% of operation and maintenance  1,923,000
Payroll            20% of operating labor               58,000

Trucking

Bottom/fly ash and                                   6,766,000
 sludge removal

Fixed Costs

Depreciation        (7.69%)
Interim replacement (0.35%),  Z = 23.54% of fixed
                                   investment
Insurance           (0.30%)
Taxes               (4.00%)
Capital costs      (11.20%)

Total fixed costs                                   18,203,000

Total costs                                       $ 36,549,000

Fuel credit                                        (18,516,000)
Net annual cost                                   $ 18,033,000
Mills/kWh                                                 7.32
  RIDGELAND  POWER PLANT                                     P-34

-------
   Table P-7.   RETROFIT EQUIPMENT AND  FACILITIES  REQUIRED FOR

           THE  LIMESTONE SCRUBBING SYSTEM FOR BOILERS

    1,  2,  3,  4,  5,  AND  6 AT  THE  RIDGELAND POWER PLANT
   Module Description
 Number
Required
Size/Capacity
  Limestone  storage

  Limestone  slurry

  Turbulent  contact

     absorbers
   1

   1

   4

   1
   1
28,000 tons (30-day storage)

38.9 ton/hr limestone

80 MW unit

139 MW unit
144 MW unit
RIDGELAND POWER PLANT
                                P-35

-------
  Table P-8.   RETROFIT EQUIPMENT DIMENSIONS  REQUIRED FOR THE

  LIMESTONE SCRUBBING SYSTEM FOR BOILER  1, 2,  3,  4, 5, AND  6

               AT THE RIDGELAND POWER PLANT
       Item
 Number
Required
Dimensions, ft
  Limestone  storage  pile

  Limestone  silos

  Limestone  slurry tanks

  Ball  mill  building

  Turbulent  contact

     absorbers

  Clarifiers

  Vacuum filter  building
   1

   3

   1

   1

   4

   2

   2

   1
115 wide x 325 long

23 diam x 50 high

95 diam x 20 high

40 x 40

45 high x 15 wide x 30 long

45 high x 15 wide x 45 long

165 diam x 20 high

40 x 40
RIDGELAND POWER PLANT
                                                         P-36

-------
I
U>
             r
             A
             B
             C
             D
             E
             F
SCRUBBERS
SLURRY TANK
LIMESTONE SILOS
BALL MILL BUILDING
CLARIFIER
VACUUM FILTER BUILDING
                                          \
         Figure P-2.   Site plan showing  possible location of major components for  the

          limestone system for Boilers 1,2,3,4,5, and  6  at the Ridgeland power plant.

-------
       TABLE P-9.   ESTIMATED CAPITAL COST OF ELECTROSTATIC
          PRECIPITATORS FOR BOILERS 1 THROUGH 6  AT THE
                  RIDGELAND POWER PLANT (1978)
Direct Costs

ESP                                               $  10,518,000

Ash handling                                         1,701,000

Ducting                                              1,660,000

                              Total direct costs  $  13,879,000

Indirect Costs

Interest during construction  8% of direct costs  $   1,110,000

Contractor's fee             10% of direct costs     1,388,000

Engineering                   6% of direct costs       833,000

Freight                    1.25% of direct costs       173,000

Offsite                       3% of direct costs       416,000

Taxes                         0% of direct costs           000

Spares                        1% of direct costs       139,000

Allowance for shakedown       3% of direct costs       416,000
               Total indirect costs               $  4,475,000

               Contingency                           3,671,000
               Total                              $ 22,025,000

               Coal conversion costs                17,795,000
               Grand total                        $ 39,820,000

               $/kW                                      66.26
  RIDGELAND  POWER  PLANT                                     P-38

-------
 TABLE P-10.  ESTIMATED ANNUAL OPERATING COSTS OF ELECTROSTATIC
           PRECIPITATOR FOR BOILERS 1 THROUGH 6 AT THE
                  RIDGELAND POWER PLANT  (1978)

Utilities           Quantity       Unit Cost      Annual Costs

Electricity         2016 kW        33.1 mills/kWh $     274,000
Water            1705 x 10"3 gal/yr $0.01/103 gal         1,000

Operating Labor

Direct labor     0.5 man/shift     $9.55/man-hour       250,000
Supervision      15% of direct labor                    38,000

Maintenance

Labor and materials  2% of fixed investment             441,000
Supplies            15% of labor and materials          66,000

Overhead

Plant               50% of operating and maintenance    398,000
Payroll             20% of operating labor              58,000

Trucking

Bottom/fly ash                                       1,774,000
 removal

Fixed costs

Depreciation        (7.69%)
Interim replacement (0.35%), Z = 23.54% of fixed
                                   investment
Insurance           (0.30%)
Taxes               (4.00%)
Capital cost       (11.20%)
Total fixed cost                                     5,185,000

Total cost                                        $  8,485,000

Fuel credit                                        (32,240,000)

Net annual credit                                 $(23,755,000)
Mills/kWh                                                (9.64)
 RIDGELAND POWER PLANT                                     P-39

-------
H
D
Q
M
2
O
M
JO

t)
f
     Table  P-ll.   ELECTROSTATIC PRECIPITATOR DESIGN  VALUES


FOR BOILERS 1,2,3,4,5, AND  6 AT THE RIDGELAND POWER  PLANT
Design Parameter
Collection efficiency, %
(Overall)
Specific collecting area,
ft2/1000 acfm
2
Total collecting area, ft
Superficial velocity, fps
Overall ESP dimensions
(height x width x depth) , ft
excluding hopper dimensions
Value
1
86.4
256
98,220
4
18x89x24
2
86.4
256
98,220
4
18x89x24
3
86.4
256
98,220
4
18x89x24
4
86.4
256
98,220
4
18x89x24
5
86.4
256
139,660
4
18x126x24
6
86.4
256
139, 660
4
18x126x24
 I
£>
O

-------
r
                           \
    Figure P-3.  Site plan showing possible locations of new  ESP's  for
        Boilers 1, 2, 3, 4, 5, and 6 at the Ridgeland power plant.

-------
                         APPENDIX Q




                    RIVERTON POWER PLANT
RIVERTON POWER PLANT                                     Q-l

-------
                            CONTENTS
Riverton Power Plant Survey Form

Riverton Power Plant Photographs
                                                  Page

                                                  Q-3

                                                  Q-15
Number
 Q-l
                             FIGURES
Site Plan Showing Possible Location of a New
ESP for Boiler 1 at the Riverton Power Plant
                                                  Page
                                                            Q-23
Number
 Q-l
 Q-2
 Q-3
                             TABLES
Estimated Capital Cost of an Electrostatic
Precipitator for Boiler 1 at the Riverton
Power Plant (1978)

Estimated Annual Operating Costs of an Electro-
static Precipitator for Boiler 1 at the
Riverton Power Plant  (1978)

Electrostatic Precipitator Design Values for
Boiler 1 at the Riverton Power Plant
Page



Q-20



Q-21


Q-22
RIVERTON POWER PLANT
                                                  Q-2

-------
                                                  OMB No. 158S 74023
                   POWER PLANT SURVEY FORM

    COMPANY INFORMATION:
                      Potomac Edison Company
    1.  COMPANY NAME:  Allegheny Power Sejvi^e  Corp.
    2.  MAIN OFFICE:  800 Cabin Hill Drive Greensburg,  PA   15601
    3.  RESPONSIBLE OFFICER:  C. G. McVay
    4.  POSITION:  V.P. System Power Supply
    5.  PLANT NAME:   River ton
    6.  PLANT LOCATION:   Front Royal, P.O. Box  243, Warren  County,  Virginia
    7.  RESPONSIBLE OFFICER AT PLANT LOCATION:  John Coulter    2263°
    8.  POSITION:     Plant Superintendent
    9.  POWER POOL   - ECAR
    DATE  INFORMATION GATHERED:  April 22,1976
    PARTICIPANTS  IN MEETING:

    Robert L.  Ballentine - Allegheny Power Service Corporation
    John W.  Coulter - Station Superintendent
    Bernie Turlinski - U.S.  Environmental Protection Agency
    D.  J.  Gaston  -  Virginia  Air Pollution Control "Board
    Wayne  E.  Peters  - Federal Energy Administration
    N.  David  Noe  -  PEDCo Environmental, Inc.
    David  M.  Augenstein - PEDCo Environmental, Inc.
RIVERTON POWER PLANT                                      Q-3

-------
        B.
H
<
w
i
tn
O
* "- ' .
ATMOSPHERIC EMISSIONS
1. PARTICULATE EMISSIONS3 uncontrolled
LB/MM BTU Full load
GRAIK'S/ACF
LB/HR (FULL LOAD)
TONS/YEAR ( )
2. APPLICABLE • PARTICULATE EMISSION
REGULATION
a) CURRENT REQUIREMENT
AQCR PRIORITY CLASSIFICATION
REGULATION 5, SECTION NO.
LB/MM BTU

b) FUTURE REQUIREMENT (DATE: )
REGULATION & SECTION NO.
LB/MM BTU
3. SO2 EMISSIONS3
LB/MM BTU
LB/HR (FULL' LOAD)
TONS/YEAR ( )
4. APPLICABLE SO EMISSION REGULATION
a) CURRENT REQUIREMENT
REGULATION & SECTION NO.
LB/MM BTU
Ib/hr (s = ?-64lO
b) FUTURE REQUIREMENT (DATE: )
REGULATION & SECTION NO.
LB/MM BTU
Boiler numoer
1
G.06 (oi
NA
38 (oil
3.15 (c)
1
Part IV
0.1899

Same

0.253 (c
158 (c)
13 (c]
Part IV I
2. 64

1) 0.19 (c

)


ruld •. ^.x -




,
sal)




3 4 .30




il) 2.64 (coal)


ule Ex ~-

1782 Ib/hr
Same





4 .5]










(a) 11







?
i
'(a) 1























                                        *re .
                                                              s or-  e

-------
    SITE DATA
    1.  U.T.M. COORDINATES Lat.  38°  57'  50"    ;    Long.  78°  10'  40"
    2.  ELEVATION ABOVE MEAN SEA LEVEL  (FT)   APP  530      	
    3.  SOIL DATA:  BEARING VALUE	
            PILING NECESSARY	
    4.  DRAWINGS REQUIRED
       PLOT PLAN OF SITE  (CONTOUR)   REVD
       EQUIPMENT LAYOUT AND ELEVATION
       AERIAL PHOTOGRAPHS OF SITE INCLUDING  POWER PLANT,
       COAL.STORAGE AND ASH DISPOSAL AREA
    5.  HEIGHT OF TALLEST BUILDING AT PLANT SITE  OR
       IN CLOSE PROXIMITY TO STACK  (FT. ABOVE GRADE)
    6.  HEIGHT OF COOLING TOWERS  (FT. ABOVE GRADE):  ApRA  	
RIVERTON POWER PLANT                                      Q-5

-------
 w
 X)
 >-3
 O
 z
 O
 s
 M
O
•*
BOILER DATA
1. SERVICE: BASE LOAD
STANDBY, FLOATING, PEAK
2. TOTAL HOURS OPERATION (19 75)
3. AVERAGE CAPACITY FACTOR (19 75)
4. SERVED BY STACK NO.
5. BOILER MANUFACTURER
6. YEAR BOILER PLACED IN SERVICE
7. REMAINING LIFE OF UNIT
8. GENERATING CAPACITY (MW)
RATED
MAXIMUM CONTINUOUS
PEAK
9. FUEL CONSUMPTION :
. OIL RATED
(GPH) MAXIMUM CONTINUOUS
PEAK
10. ACTUAL FUEL CONSUMPTION
COAL (TPY) (19 75)
OIL (GPY) (19 75)
11. WET OR DRY BOTTOM
12. FLY ASH REINJECTION (YES OR NO)
13. STACK HGT ABOVE GRADE (FT.)
14. l.D. OF STACK AT TOP (INCHES)
Boiler number
1
Peak
504
2. 2%
1
Riley
1949

40
40


114 Bar/

0
787,576
Dry
No
130
108












Hr .



































































        Notes:

-------
 o
 2
o
w
I
•-3
           15.
O
 I
       Notes:
FLUE GAS  CLEANING EQUIPMENT
a) MECHANICAL COLLECTORS
    MANUFACTURER
                    TYPE
                    EFFICIENCY:  DESIGN/ACTUAL  (%)
                    MASS EMISSION  RATE:
                               (GR/ACF)
                               (#/HR)
                               (S/MM BTU)
               b)  ELECTROSTATIC  PRECIPITATOR
                    MANUFACTURER
                    TYPE
                    EFFICIENCY:  DESIGN/ACTUAL  (%)
                    MASS EMISSION  RATE
                               (GR/ACF)
                               (#/HR)
                                     BTU)
                   NO.  OF IND. BUS  SECTIONS
                   TOTAL PLATE AREA  (FT2")
                   FLUE GAS TEMPERATURE
                    @  INLET ESP  @  100% LOAD  (°F)
          16-  EXCESS  AIR: DESIGN/ACTUAL  (%)
                                                                          Boiler number
                                          UOP
                                                         MCAX
                                         85/79
                                                          38 (oi]
                                                         None
                                                          20

-------
M
»
i-3
O
O
s:
M
•<
17. FLUE GAS RATE (ACFM)
@ 100% LOAD
@ 75% LOAD
@ 50% LOAD
18. STACK GAS EXIT TEMPERATURE (°F)a
@ 100% LOAD
@ 75% LOAD
@ 50% LOAD
19. EXIT GAS STACK VELOCITY (FPS)a
@ 100% LOAD
@ 75% LOAD
@ 50% LOAD
20. FLY ASH: TOTAL COLLECTED (TONS/YEAR)
DISPOSAL METHOD 1973
DISPOSAL COST ($/TOH)
21. BOTTOM ASH: TOTAL COLLECTED (TONS/
1973 VFAR 1
DISPOSAL METHOD I£-rtK'
DISPOSAL COST ($/5'OW-)
22. EXHAUST DUCT DIMENSIONS @ STACK
23. ELEVATION OF TIE IN POINT TO STACK
24. SCHEDULED MAINTENANCE SHUTDOWN
(ATTACH PROJECTED SCHEDULE)
One week
Boiler number
1
212,000
180,000
120,000
360
340
300
S6
46
36
2,204
Land fill
$ 400.
1 ,Ub /
Land fil!
$1,400


4/18/77
5/8/78


















































, 	

















Q
 I
oo
a) Identify  source  of  values (test or estimate)



Notes:

-------
w
»
^
O
O
5
w
JO
•^
E . I . D . FAN DATA
1. MAXIMUM STATIC HEAD (IN. W.C.)
2. WORKING STATIC HEAD (IN. W.C.)
Boiler number















Notes:
O
 I

-------
F.   FLY  ASH  DISPOSAL AREAS    Deteriorated 15 acre  pond
     1.   AREAS  AVAILABLE (ACRES)  2Q-3Q  Acres	
     2.   YEARS  STORAGE (ASH ONLY)   pOnd not in use
     3.   DISTANCE  FROM STACK (FT.)   800
     4.   DOES  THIS  PLANT HAVE PONDING
         PROBLEMS?   DESCRIBE IN ATTACHMENT   Po"d n°t in
G.   COAL DATA
     1.   COAL  SEAM,  MINE,  MINE LOCATION
         a.
         c .
         d.
     2.   QUANTITY USED BY SEAM AND/OR MINE.
         a.
         b.
         c .
         d.
     3.   ANALYSIS
         GHV (BTU/LB)    U.62A
                  3.2
         ASH (%)  21.4
         MOISTURE (%)    2.6	
     4.   PPT PERFORMANCE EXPERIENCED WITH LOW
         S FUELS (DESCRIBE IN ATTACHMENT)
H.   FUEL OIL DATA
     1.  TYPE   No.  2
     2.  S CONTENT  (%)   u-20
     3.  ASH CONTENT  (%) Q.QQ5
     4.  SPECIFIC GRAVITY
     5.   GHV (BTU/GAL)   138.695
     COST DATA
     ELECTRICITY  X
     WATER    N/A
     STEAM    N/A
 J.   PLANT SUBSTATION CAPACITY
     APPROXIMATELY WHAT PERCENTAGE  OF  RATED   Transformer required?
     STATION CAPACITY CAN  PLANT  SUBSTATION
     PROVIDE?	U^)-KW breaker	
     NORMAL LOAD ON  PLANT  SUBSTATION?	
     VOLTAGE AT WHICH  POWER IS AVAILABLE?   230 V  A40V	

  RIVERTON POWER PLANT                                      Q~10

-------
  K.   OIL/GAS TO COAL CONVERSION DATA
      1.   HAS THE BOILER EVER BURNED COAL?
Boiler No.
Yes or No.
1
Yes







*
      2.   SYSTEM AVAILABILITY
          2.1
          2.2
          2.3
        YesS
            m
COAL HANDLING

a.  Is the system still installed?

b.  Will it operate?

c.  Of the following items which do not
    need to be replaced:  Maintenance

    Unloading equipment    parts    Yes 53
    Stack Reclaimer        belts        D
    Bunkers         9 month - lead time H
    Conveyors
    Scales
    Coal Storage Area     Maintenance   H

FUEL FIRING                Need a Bulldozer

a.  Is the system still installed?  YesQ

b.  Will it operate?                    D   x

c.  Of the following items which  do not
                                                       H
                                                            No D

                                                               D
                  No D
                    0
                    a
                    B
                    D
                    a
                                                                 No
                   need to be replaced:
                   Pulverizers or Crushers
                   Feed Ducts
                   Fans
                   Controls
         Yes
Rebuilding
                                                            NoD
                                                        par tially
                                                               0
                                              NoQ
                                                D
                                                D
                                                D
GAS CLEANING

a.  Is the system still installed?   Yes£]     No Q

b.  Will it operate?                    D       D

c.  Of the following items which  do  not
    need to be replaced:

    Electrostatic Precipitator  N/A  YesD     No D
    Cyclones                            H       D
    Fly Ash Handling Equipment          S       D
    Soot Blowers - Air Compressors      E       D
    Wall deslaggers                     £3       D
RIVERTON POWER PLANT
                                          Q-ll

-------
        2.4   ASH  HANDLING
             a.   Is  the  system still  installed?   Yes (*]    No Q
             b.   Will  it operate?                     &      Q
             c.   Of  the  following  items which
                 need  to be  replaced:
                 Bottom  Ash  Handling               Yes D    NoQ
                 Ash Pond           Maintenance       Q      Q
RIVERTON POWER PLANT                                     Q-12

-------
   L.  SyPPLff-lENTMY CONTROL SYSTEM DATA
1 .   DOES THE PLANT NOW HAVE A SUPPLEMENTAL  CONTROL
    SYSTEM (SCS)?

    If yes, attach a description  of the  system.

2.   IS THE PLANT CAPABLE  OF SWITCHING  TO LOW
    SULFUR FUELS?                            '

    2.1   Storage capacity for low sulfur fuels
         (tons ,  bbls ,  days)

    2.2   Bunkers available for low sulfur coal
         storage?

    2.3   Handling facilities  available for  low
         sulfur  fuels                        '

         If yes, describe  _ -
       3.
5.
    2.4  Time required to switch fuels and fire
         the low sulfur fuel  in the boiler (hrs)?

    IS THE PLANT CAPABLE OF LOAD SHEDDING?

    If yes,  discuss   	
       4.   IS  THE  PLANT CAPABLE OF LOAD SHIFTING?

           If  yes, discuss
    POWER  PLANT MONITORING  SYSTEM

    5.1  Existing  system

        a.  Air quality  instrumentation

            (1)   Sulfur  Oxides - Continuous
                               - Intcrmittent
                               - Static
            (2)   Suspended participates
                               - Intermittent
                               - Static
            (3)   Other (describe)	
                   Meteorological instrumentation
                   If yes, describe 	
         c.   Is  the  monitor ing  data  available?
         cl.   Is  the  monitoring  data  reduced  and
             analyzed?
                                                        Yes
                                                                   Fl
                                                                   1   '
                                                               Yes   x    No
                                                              Yes  [~K|   No

                                                              Yes  [~X]   No  |  ]
                                                              YCS  rj   NO  rj
                                                              Yes  [j   No  rj


                                                              Yes  [~]   No  [  |
                                                           Number     Type
                                                              Yes  |  j   No  |  |

                                                              Yes  HJ   No  [H
RIVERTON  POWER  PLANT
                                                                   Q-13

-------
        5.2  Proposed system                                 Yes   Q   No
             If yes, describe	
                  (2)  Suspended particulate
                                    - Intermittent
                                    - Static
                  (3)  Other  (describe) 	
             b.  Meteorological instrumentation
                 If yes, describe	
RIVERTON POWER  PLANT
             a.  Air monitoring instrumentation           Number     Type
                 (1)  Sulfur oxides - Continuous          	     	
                                    - Intermittent        	     	
                                    - Static              	     	
                                                                   Q-14

-------
                     -
      Photo No. 1.  View from the boiler roof facing southeast
      showing the Shenandoah River and Blue Ridge Mountains.
      Photo No. 2.  View from ground level facing east
      showing boiler stack and the west end of the plant.
RIVERTON POWER PLANT
                                                         Q-15

-------
 Photo No. 3.  View from ground level facing southeast
 showing a portion of the oil storage facilities, boiler duct
 tie-in to the stack, and the coal conveyor.
   Photo  No.  4.   View from the  roof  facing  southwest showing
   the  Shenandoah River  and surrounding  terrain including the
   golf course which  adjoins the  plant.
RIVERTON POWER PLANT
Q-16

-------
    Photo No. 5.  View from the roof facing northwest showing
    the surrounding terrain.
 Photo No. 6.  View from  the roof  facing north  showing  the
 coal storage area transfer station, and a portion of the
 electrical switchyard.
RIVERTON POWER PLANT
                                                         Q-17

-------
Photo No. 7.  View from ground level facing north showing
coal transfer house and conveyors.  The coal storage area is
in the background.
  Photo No. 8.  View from ground level facing northwest
  showing coal handling facilities located at the north end of
  the plant.
RIVERTON POWER PLANT
Q-18

-------
 Photo No.  9.   View from ground level facing southwest
 showing inactive ash settling basin located approximately
 500 feet west of the plant.   Plans are being initiated to
 pipe the plant effluent to this retired ash settling basin,
   Photo No. 10.  View from rooftop facing northeast showing
   electrical substation serving the plant.
RIVERTON POWER PLANT
Q-19

-------
   TABLE Q-l.  ESTIMATED CAPITAL COST OF AN ELECTROSTATIC
PRECIPITATOR FOR BOILER 1 AT THE RIVERTON POWER PLANT  (1978)
Direct Costs
ESP
Ash handling
Ducting
Total direct costs
Indirect Costs
Interest during construction 8% of direct costs
Contractor's fee 10% of direct costs
Engineering 6% of direct costs
Freight 1.25% of direct costs
Offsite 3% of direct costs
Taxes 0% of direct costs
Spares 1% of direct costs
Allowance for shakedown 3% of direct costs
Total indirect costs
Contingency
Total
Coal conversion costs
Grand total
SAW

$ 1,514,000
220,000
87,000
$ 1,821,000

$ 146,000
182,000
109,000
23,000
55,000
000
18,000
55,000
$ 588,000
482,000
$ 2,891,000
2,269,000
$ 5,160,000
129.00
RIVERTON POWER PLANT
Q-20

-------
TABLE Q-2.  ESTIMATED ANNUAL OPERATING COSTS OF AN ELECTROSTATIC
  PRECIPITATOR FOR BOILER 1 AT THE RIVERTON POWER PLANT (1978)
Utilities       Quantity        Unit Cost          Annual Cost

Electricity    260 kW          27.55 mills/kWh  $       11,000
Water          3003 103 gal/yr $0.33/103 gal             1,000

Operating Labor

Direct labor   1.5 men/shift  $8.50/man-hour            37,000
Supervision    15% of direct labor                       6,000

Maintenance

Labor and materials 2% of fixed investment              58,000
Supplies           15% of labor and materials            9,000

Overhead

Plant              50% of operation and maintenance     55,000
Payroll            20% of operating labor                9,000

Trucking

Bottom/fly ash
 removal                                                   000

Fixed Costs

Depreciation        (7.69%)
Interim replacement (0.35%), E = 19.54% of fixed
                                     investment

Insurance           (0.30%)
Taxes               (0.00%)
Capital cost       (11.20%)
Total fixed cost
Total cost
Fuel credit
Net annual cost
Mills/kWh
$
$
$
565,000
751,000
(142,000)
609,000
64.37
RIVERTON POWER PLANT                                      Q-21

-------
    Table Q-3.  ELECTROSTATIC PRECIPITATOR  DESIGN VALUES

       FOR BOILER 1 AT THE  RIVERTON POWER PLANT
     Design Parameter
                                      Value
Collection efficiency, %
   (Overall)

Specific collecting area,
   ft2/1000 acfm
                         *2
Total collecting area, ftz

Superficial velocity, fps

Overall ESP dimensions
 (height x width x depth), ft
excluding hopper dimensions
97.48


409


87,000

4

30 x 29 x 39
RIVERTON POWER PLANT
                   Q-22

-------
                                      N
      A.  CRUSHER  HOUSE

      B.  TRUCK HOPPER
                                                     COAL STORAGE
           WASTEWATER
       TREATMENT LAGOON
     Figure  Q-l.   Site plan  showing possible location of

     a new ESP for Boiler  1  at the Riverton power plant.
RIVERTON  POWER PLANT
Q-23

-------
                         APPENDIX R




                     VIENNA POWER PLANT
VIENNA POWER PLANT                                       R-l

-------
                            CONTENTS
Vienna Power Plant Survey Form

Vienna Power Plant Photographs
                                                  Page

                                                  R-3

                                                  R-15
Number
 R-l
                             FIGURES
Site Plan Showing Possible Location of a New
ESP for Boiler 7 at the Vienna Power Plant
                                                  Page
                                                             R-23
Number
 R-l
 R-2
 R-3
                             TABLES
Estimated Capital Cost of an Electrostatic
Precipitator for Boiler 7 at the Vienna Power
Plant (1978)

Estimated Annual Operating Costs of an Electro-
static Precipitator for Boiler 7 at the Vienna
Power Plant (1978)

Electrostatic Precipitator Design Values for
Boiler 7 at the Vienna Power Plant
                                                  Page
                                                             R-20
                                                            R-21
                                                            R-22
VIENNA POWER PLANT
                                                  R-2

-------
                                                 OMB No. 158S 74023
                  POWER PLANT SURVEY FORM


   COMPANY INFORMATION;

   1. COMPANY NAME:  Delmarve Power &  Light Co.

   2. MAIN OFFICE:   Wilmington, Delaware

   3. RESPONSIBLE OFFICER:  Hudson Hoen

   4. POSITION:   Director, Environmental Affairs

   5. PLANT NAME: Vienna

   6. PLANT LOCATION:  Vienna, Maryland

   7. RESPONSIBLE OFFICER AT PLANT LOCATION:  David Windslow

   8. POSITION:  Superintendent

   9. POWER POOL   PJM
   DATE  INFORMATION GATHERED:
    PARTICIPANTS  IN MEETING:
   Tom Evans - Delmarva Power & Light
   Dick Parcels  - Delmarva Power & Light
   Bob Matthews  - Delmarva Power & Light
   D. Bruce McClenathan - Delmarva Power & Light
   Clark I. Simms, Jr. - Delmarva Power & Light
   Ralph Schumacher - Maryland Health Department
   Bernie Turlinski - U.S. Environmental Protection Agency
   N. David Noe  - PEDCo Environmental, Inc.
   Michael F. Szabo - PEDCo Environmental,. Inc.
   David M. Augenstein - PEDCo Environmental, Inc.
VIENNA POWER PLANT                                         R_3

-------
B.
ATMOSPHERIC EMISSIONS
1. PARTICULATE EMISSIONS3
LB/MM BTU
GRAINS/ACF
LB/HR (FULL LOAD)
TONS/YEAR ( )
2. APPLICABLE PARTICULATE EMISSION
REGULATION
a) CURRENT REQUIREMENT
AQCR PRIORITY CLASSIFICATION
REGULATION & SECTION NO..
LB/MM BTU
OPACITY, PERCENT
b) FUTURE REQUIREMENT (DATE: )
REGULATION & SECTION NO.
LB/MM BTU
3. SO- EMISSIONS3
LB/MM BTU
LB/HR (FULL LOAD)
TONS/YEAR ( )
4. APPLICABLE SO2 EMISSION REGULATION
a) CURRENT REQUIREMENT
REGULATION & SECTION NO.
i-e/MH-BTO Coal
Residual Oil
b) FUTURE REQUIREMENT (DATE: )
REGULATION & SECTION NO.
LB/MM BTU
Boiler number
5


7

«,
Area I\
Reg. 1(
0.35







1.0% Si
0.5% Si


6


I


.03.41.03.
0.30







ilfur
ilfur


7


17


B. (3).
0.35











fl


1140


Stack-Stac
0.30

















k basis












        ltd
re
      >m
             ck
;ts
                           e:
at

-------
C.  SITE DATA
    1. U.T.M. COORDINATES
    2. ELEVATION ABOVE MEAN SEA LEVEL  (FT) 8' above  mean  low
    3. SOIL DATA:  BEARING VALUE
            PILING NECESSARY  Yes
    4. DRAWINGS REQUIRED
       PLOT PLAN OF SITE  (CONTOUR)
       EQUIPMENT LAYOUT AND ELEVATION
       AERIAL PHOTOGRAPHS OF SITE  INCLUDING  POWER PLANT,
       COAL STORAGE AND ASH DISPOSAL AREA
    5. HEIGHT OF TALLEST BUILDING  AT PLANT SITE OR
       IN CLOSE PROXIMITY TO STACK (FT.  ABOVE GRADE)
    6. HEIGHT OF COOLING TOWERS  (FT. ABOVE GRADE):
 VIENNA POWER PLANT                                          R-5

-------
     D.
M
w
2
Z
13
O
a
w
50


CTl
BOILER DATA
1. SERVICE: BASE LOAD
STANDBY, FLOATING, PEAK
2. TOTAL HOURS OPERATION (1975)
3. AVERAGE CAPACITY FACTOR (1975)
4. SERVED BY STACK NO.
5. BOILER MANUFACTURER
6. YEAR BOILER PLACED IN SERVICE
7. REMAINING LIFE OF UNIT 28 yr. bookli
8. GENERATING CAPACITY (MW)
RATED
MAXIMUM CONTINUOUS
PEAK
9. FUEL CONSUMPTTON:
GO-A-fc OR OIL RATED
f'FRtr-e-R-firPH-)- MAXIMUM CONTINUOUS
PEAK
10. ACTUAL FUEL CONSUMPTION
COAL (TPY) (1971)
OIL (G23O- (1975) BBl/y
11. HEAT RATE BTU/KWHR GAS
COAL
OIL
12. WET OR DRY BOTTOM
13. FLY ASH REINJECTION (YES OR NO)
14. STACK HGT ABOVE GRADE (FT.)
15. I.D. OF STACK AT TOP (INCHES)
Boiler number
5

3,165
17.8
3&4
B&W
1947
fe
17



42

44,000
75,000



dry
No
133

6

6,447
37.4
4&5
B&W
1949
1
17



42

45,000
154,000



dry
No
133

7

2,490
15. 3
6
B&W
1951
3
40



104

97,000
1.38,000



dry
No
133

3

4,848
28.0
7
CE
1971
23
162



,_ 276

N.A.
736,000



dry
Yes
160
























       Notes:

-------
<
M

M


z
i
M
13

£
z
16. FLUE GAS CLEANING EQUIPMENT
a) MECHANICAL COLLECTORS
MANUFACTURER
TYPE
EFFICIENCY: DESIGN/ACTUAL (%)
MASS EMISSION RATE:
(GR/ACF)
(#/HR)
(#/MM BTU)
b) ELECTROSTATIC PRECIPITATOR
MANUFACTURER
TYPE
EFFICIENCY: DESIGN/ACTUAL (%)
MASS EMISSION RATE
(GR/ACF)
(#/HR)
(#/MM BTU)
NO. OF IND. BUS SECTIONS
TOTAL PLATE AREA (FTZ)
FLUE GAS TEMPERATURE
@ INLET ESP @ 100% LOAD (°F)
17. EXCESS AIR: DESIGN /ACTUAL (%)
Boiler number
5
BUEL
MCTA
85/60














6
UOP
MCAX
85/0














7
UOP
MCAX
85/0














8
UOP
MCTA
87.5/87.5
































   Notes

-------
tn
z
z
O
33
W
50
18. FLUE GAS RATE (ACFM)
@ 100% LOAD
@ 75% LOAD
@ 50% LOAD
19. STACK GAS EXIT TEMPERATURE (°F)a
@ 100% LOAD
@ 75% LOAD
@ 50% LOAD
20. EXIT GAS STACK VELOCITY (FPS)a
@ 100% LOAD
@ 75% LOAD
@ 50% LOAD
21. FLY ASH: TOTAL COLLECTED (TONS/YEAR)
DISPOSAL METHOD
DISPOSAL COST ($/TON)
22. BOTTOM ASH: TOTAL COLLECTED (TONS/
DISPOSAL METHOD YEAR)
DISPOSAL COST ($/TON)
23. EXHAUST DUCT DIMENSIONS @ STACK
24. ELEVATION OF TIE IN POINT TO STACK
25. SCHEDULED MAINTENANCE SHUTDOWN
(ATTACH PROJECTED SCHEDULE)
Stack number
3
52,000
40,700
28,000
350
325
300
27.5
20
14




76"


4
104,000
81,000
56,000
375
350
325
55
42
30




76"


5
52,000
40,700
28,000
350
325
300
27.5
20
14




76"


fi
242,000
185,900
127,000
380
360
340
95
65
44




88"


7
672,000
504,000
336,000
625
570
540
92
69
46




150"


oo
    a)  Identify source of values  (test or estimate)
    Notes:
Boiler 5
Boiler 6
Boiler 7
Boiler 8
Stacks 3&4
Stacks 4&5
Stack 6
Stack 7

-------
z
z
E . I . D . FAN DATA
1. MAXIMUM STATIC HEAD (IN. W.G.)
2. WORKING STATIC HEAD (IN. W.G.)
Boiler number















33

13

£
z
     Notes:

-------
F.   FLY  ASH DISPOSAL AREAS
     1.   AREAS AVAILABLE (ACRES)   1QO
     2.   YEARS STORAGE (ASH ONLY) soon to be discontinued.
     3.   DISTANCE FROM STACK (FT.)  12 miles
     4.   DOES THIS PLANT HAVE PONDING
         PROBLEMS?  DESCRIBE IN ATTACHMENT
G-   COAL DATA
     1.   COAL SEAM,  MINE, MINE LOCATION
         a.
         b.
         c.
         d.	
     2.   QUANTITY USED BY SEAM AND/OR MINE
         a .
         b.
         c.
         d.
     3.   ANALYSIS (19   )
         HHV  (BTU/LB)	
         S (%)	
         ASH  (%)
         MOISTURE (%)	
     4.   PPT  PERFORMANCE EXPERIENCED WITH LOW
         S FUELS  (DESCRIBE. IN ATTACHMENT)
H .   FUEL OIL DATA (197 5 )
     1.   TYPE     #6 residual	
     2.   S CONTENT (%)    j_3
     3.   ASH  CONTENT (%)
     4.   SPECIFIC GRAVITY   i
     5.  HHV  (BTU/GAL)    145.628
I.  NATURAL GAS  HHV  (BTU/FT3)
J.  COST DATA
    ELECTRICITY
    FUEL:  COAL           GAS          OIL
    WATER
    STEAM
    TAXES ON A.P.C.  EQUIPMENT:   STATE SALES
       FEDERAL  PROPERTY  TAX
 VIENNA POWER  PLANT                                          R-10

-------
  K.
PLANT SUBSTATION CAPACITY
  M.
APPROXIMATELY WHAT PERCENTAGE OF RATED
STATION CAPACITY CAN PLANT SUBSTATION
PROVIDE?

NORMAL LOAD ON PLANT SUBSTATION?

VOLTAGE AT WHICH POWER IS AVAILABLE?

ADDITIONAL INFORMATION

   F.E.A. LETTER

OIL/GAS TO COAL CONVERSION DATA

1.  HAS THE BOILER EVER BURNED COAL?
Boiler No.
Yes or No.
5
Yes
6
Yes
7
Yes
8
No


                                                    Yes@

                                                       Q
YesB
H
H
H -
B
m D
No D
D
a
	 m
n
H
2.  SYSTEM AVAILABILITY
    2.1  COAL HANDLING
         a.  Is the system still installed?

         b.  Will it operate?

         c.  Of the following items which
             need to be replaced:
             Unloading equipment
             Stack Reclaimer No  rail service
             Bunkers
             Conveyors need extensive work
             Scales  corrosion
             Coal Storage Area not enough room

    2 .2  FUEL FIRING
         a.  Is the system still installed?   YesD

         b.  Will it operate?                    D
         c.  Of the following items which
             need to be replaced:
             Pulverizers or Crushers Rebuilding g
             Feed Ducts                          S
             Fans  modify                        S
             Controls                            S

    2.3  GAS CLEANING
         a.  Is the system still installed?   Yes H 5

         b.  Will it operate?                    13 5
         c.  Of the following items which
             need to be replaced:
             Electrostatic Precipitator       YesD
             Cyclones                            H
             Fly Ash Handling Equipment          D
             Soot Blowers - Air  Compressors      Q
             Wall deslaggers                     D
No D
  a
                                                             NO a
                                                               a
                                                             NO a
                                                               a
                                                               D
                                                               a
                                                             No 0 6,7
                                                                06,7
                                                             NO a
                                                                a
                                                                a
                                                                a
                                                                a
VIENNA POWER PLANT
                                                           R-ll

-------
      2.4  ASH HANDLING
           a.  Is the system still installed?   Yes B    NoQ
           b.  Will it operate?                     B       D
           c.  Of the following  items which
               need to be replaced:
               Bottom Ash Handling              Yes S    NoD
               Ash Pond                             H       D
VIENNA POWER PLANT                                         R~12

-------
  N .   SUPPLEMENTARY CONTROL SYSTEM DATA
       1 .   DOES THE PLANT NOW HAVE A SUPPLEMENTAL CONTROL
           SYSTEM  (SCS)?                                       Yes  Q   No
           If yes, attach a description of the system.
       2.   IS THE  PLANT CAPABLE OF SWITCHING TO LOW
           SULFUR  FUELS?                                       Yes  Q   No  [J
           2.1  Storage capacity for Tow sulfur fuels
               (tons , bbls , days)
           2.2  Bunkers available for low sulfur coal
               storage?                                       Yes        No
           2.3  Handling facilities available for low
               sulfur fuels                                   Yes   Q   No
               If yes, describe _
           2.4  Time required to switch fuels and fire
               the low sulfur fuel in the boiler (hrs)?
       3.   IS THE PLANT CAPABLE OF LOAD SHEDDING?
           If yes, discuss _
                                                              Yes   T   No
       4.   IS THE PLANT CAPABLE OF LOAD SHIFTING?
           If yes, discuss __
           __         Yes  0   No  Q
       5.   POWER PLANT MONITORING SYSTEM
           5.1  Existing system No S02 monitoring           Yes  [  [   No  [  |
               a.  Air quality instrumenftfttiBnavailable   Number     Type
                   (1)  Sulfur Oxides - Continuous         __     _
                                      - Intermittent       __     _
                                      - Static                         _
                    (2)  Suspended participates
                                      - Intermittent
                                      - Static
                    (3)  Other (describe)	
                b.  Meteorological instrumentation
                   If yes, describe 	
                c.   Is the monitoring data available?          Yes  Pj   No
                d.   Is the monitoring data reduced and
                    analyzed?                                  Yes  Q]   No
                e.   Provide map of monitoring locations
VIENNA POWER PLANT                                                R-13

-------
         b.2  Proposed system          :                       Yes  P]  No
              If yes, describe and provide map	
                                     - Intermittent
                                     - Static

                  (2)  Suspended particulato
                                     - Intermittent
                                     - Static  •

                  (3)  Other (describe) 	
              b.  Meteorological  instrumentation

                  If yes, describe 	
              a.  Air monitoring instrumentation           Number     Type

                  (1)  Sulfur oxides - Continuous           	     	
VIENNA POWER PLANT                                                R-14

-------
  Photo No. 1.  View from ground level at the entrance gate
  facing east showing the entire plant.  Boiler No. 8 is on
  the left.  The brick building houses Boilers 5, 6, and 7.
   Photo No. 2.  View from the roof of Boiler 8 facing south
   showing Stacks 3, 4, 5, and 6.  Nanticoke River and the
   surrounding area are shown in background.
VIENNA POWER PLANT
R-15

-------
  Photo No.  3.   View from the roof of Boiler 8 facing north
  showing plant surroundings and cooling tower which serves
  Boiler 8.
  Photo No. 4.  View from the roof of Boiler 8  facing north
  showing the coal storage area and coal handling facilities.
VIENNA POWER PLANT
                                                           R-16

-------
       Photo No. 5.  View from the roof of Boiler 8 facing south
       showing electrical substation and the oil storage tanks.
   Photo No.  6.   View from the roof of Boiler 8 facing south-
   west showing  the electrical substation and the oil storage
   facilities.
VIENNA POWER PLANT
R-17

-------
   Photo No. 7.  View from the roof of Boiler 8 facing east
   across Nanticoke River.  The existing ash disposal facil-
   ities are located across the river.
    Photo No.  8.   View from the roof of Boiler 8 facing west
    showing the plant surroundings.   The equipment storage
    buildings  and areas are pictured in the foreground.
VIENNA POWER PLANT
R-18

-------
    Photo  No.  9.   View from ground level facing south showing
    the  space  between the boiler house and the Nanticoke River
 Photo No.  10.  View  from ground  level  facing  north showing
 coal storage area, handling  facilities,  and the  cooling
 tower serving Boiler  8.
VIENNA POWER PLANT
R-19

-------
     TABLE R-l.  ESTIMATED CAPITAL COST OF AN ELECTROSTATIC
   PRECIPITATOR FOR BOILER 7 AT THE VIENNA POWER PLANT (1978)
Direct Costs

ESP                                               $ 1,495,000

Ash handling                                          124,000

Ducting                                               347,000
                              Total direct costs  $ 1,966,000

Indirect Costs

Interest during construction  8% of direct costs  $   157,000

Contractor's fee             10% of direct costs      197,000

Engineering                   6% of direct costs      118,000

Freight                    1.25% of direct costs       25,000

Offsite                       3% of direct costs       59,000

Taxes                       1.5% of direct costs       29,000

Spares                        1% of direct costs       20,000

Allowance for shakedown       3% of direct costs       59,000
          Total indirect costs                    $   664,000

          Contingency                                 526,000
          Total                                   $ 3,156,000

          Coal conversion costs                       446,000
          Grand total                             $  3,602,000

          $/kW                                          90.05
VIENNA POWER PLANT                                        R-2Q

-------
       TABLE R-2.  ESTIMATED ANNUAL OPERATING COSTS OF AN
         ELECTROSTATIC PRECIPITATOR FOR BOILER 7 AT THE
                    VIENNA POWER PLANT (1978)
Utilities

Electricity
Water

Operating Labor

Direct labor
Supervision

Maintenance

Labor and materials
Supplies

Overhead
 Quantity

 146 kW
 2660 103 gal/yr
            Unit Cost

          27.55 mills/kWh
          $0.01/103 gal
 0.5 man/shift      $8.50/man-hour
 15% of direct labor
 2% of fixed investment
 15% of direct labor
Annual Cost

$    6,000
     1,000
                                36,000
                                 5,000
                                63,000
                                 5,000
Plant
Payroll

Trucking

Bottom/fly ash
  removal
 50% of operation and maintenance
 20% of operating labor
                                57,000
                                 8,000
                                       1,932,000
Fixed Costs
Depreciation
Interim replacement

Insurance
Taxes
Capital cost
Total fixed cost

Total cost
Fuel credit

Net annual cost
Mills/kWh
 (7.69%)
 (0.35%)

 (0.30%)
 (0.00%)
(11.20%)
Z = 19.54% of fixed
     investment
                                      $   617,000

                                      $2,734,000
                                        (997,000)

                                      $1,737,000
                                           32.40
 VIENNA POWER PLANT
                                      R-21

-------
          Table  R-3  .  ELECTROSTATIC PRECIPITATOR DESIGN

          VALUES FOR BOILER 7 AT THE VIENNA POWER PLANT
          Design Parameter
Value
     Collection efficiency, %
       (Overall)

     Specific collecting area,
       ft2/1000 acfm

     Total collecting area, ft2

     Superficial velocity, fps

     Overall ESP dimensions
     (height x width x depth), ft
     excluding hopper dimensions
96.2


202


48,900.

4

15x67x19
VIENNA POWER PLANT
                                                           R-22

-------
                                                                                                                           It'  SLKVE
TJ
          WASTE WATER
          DISPOSAL MT
                                                                      VATHI
                                                                      TREATMENT
                                                                                                                            CONDERSATE
                                                                                                                            STORAGE  TANK
                                                                                   MAIN POWER Urn
                                                                                   TRANSFORMER ["[I  |
                                                                                                                             HELL WATER STORAGE TAKI
                                                                                  —I  KW  >~n
                                                                                           STAIRWAY
                                                                                                                     VNEUTRALIZIHS TAN(
                                                                                                           OUST
                                                                                                         COUECTOI
                                                                                                        I P.O.  FANS.
                                                                                     ACID STORAGE TANK

                                                                                   CAUSTIC STORAGE TANK
                                                                                                                                     EIISTING
                                                                                                                                     SlINGER
                                                EXISTINC POWER NOUSI
                                                                                EXISTING—
                                                                               20.000 GAL
                                                                              COHO. 'STORAGE
                                                                                 TANK
UISTIM
STOCIt-OUi
CONVEYOR
                                                                                                                   EXISTING
                                                                                                                   CONVENOR TO BUNKERS
                                                                                                 36' DISCHARGE FROM
                                                                                                 SEAL CHAMBER
  MAKE UP-WATER
  INTAKE PIT
                                                                                             DISCHARGE CANAL EUSTINC
                                            Oil IOOM ENCLOSURE
                                                         fLOW
                                                                                   MRTICOKE RIVER
                           Figure  R-l.    Site  plan  showing  possible  location of  a  new ESP

                                            for   Boiler  7  at  the  Vienna  power  plant.
 U)

-------
                         APPENDIX S




                     WISDOM POWER PLANT
WISDOM POWER PLANT                                      S-l

-------
                            CONTENTS



                                                            Page




Wisdom Power Plant Survey Form                              S-3




Wisdom Power Plant Photographs                              S-15
WISDOM POWER PLANT                                       .   S-2

-------
                                                 OMB No. 158S 74023
                  POWER PLANT SURVEY FORM

   COMPANY INFORMATION;
   1. COMPANY NAME: CORN  BELT POWER COOPERATIVE
   2. MAIN OFFICE: 1300 North 13th St., Humbolt,  Iowa  50548
   3. RESPONSIBLE OFFICER:  Dan C. Adams
   4. POSITION:  Supt. of Plants
   5. PLANT NAME:  Wisdom
   6. PLANT LOCATION:  Clay County, Iowa - Spencer, Iowa  5130
   7. RESPONSIBLE OFFICER AT PLANT LOCATION:  P.  J. Rath
   8. POSITION: Plant Superintendent
   9. POWER POOL
   DATE INFORMATION GATHERED:  December 31,  1975
   PARTICIPANTS IN MEETING:
  Dan C. Adams - Corn Belt Power Cooperative
  •Philip J. Rath - Corn Belt Power Cooperative
  John Metcalfe - Iowa Department of Environmental Quality
  David A. Kirchgessner - U.S. Environmental Protection Agency
  Thomas C. Ponder, Jr. - PEDCo Environmental, Inc.
  N. David Noe - PEDCo Environmental, Inc.
  Alan J. Sutherland - PEDCo Environmental, Inc.
WISDOM POWER PLANT                                       S-3

-------
     B
CO
o

i
ATMOSPHERIC EMISSIONS
1. PARTICULATE EMISSIONS*
* LB/MM BTU
GRAINS/ACF
LB/HR (FULL LOAD)
TONS/YEAR ( )
2. APPLICABLE PARTICULATE EMISSION
REGULATION
a) CURRENT REQUIREMENT
AQCR PRIORITY CLASSIFICATION
REGULATION & SECTION NO. Sect.
LB/MM BTU

b) FUTURE REQUIREMENT (DATE: )
REGULATION & SECTION NO.
LB/MM BTU
3. S02 EMISSIONS3
LB/MM BTU
LB/HR (FULL LOAD)
TONS/YEAR ( )
4. APPLICABLE SO2 EMISSION REGULATION
a) CURRENT REQUIREMENT
REGULATION S SECTION NO. Sect.
LB/MM BTU

b) FUTURE REQUIREMENT (DATE : 7/31/78)
REGULATION & SECTION NO.
LB/MM BTU
Boiler number
1
.0109



-
4.3 (2B)
= 8






4.3 (3a)
6.0

4.3 (3B)
5.0












































































CO
     a)  T
    .*" wh~4-ver -~3ul*"- are from. -"-ack '--str ~T e-^

* STW Testing  Inc.,  Denver, Colorado (7/17/75)  at  38 MW

-------
M
C/3
a
o
s
i
W
13
2S
•-3
15. FLUE GAS CLEANING EQUIPMENT
a) MECHANICAL COLLECTORS
MANUFACTURER
TYPE
EFFICIENCY: DESIGN/ACTUAL (%)
MASS EMISSION RATE:
(GR/ACF)
(#/HR)
(#/MM BTU)
b) ELECTROSTATIC PRECIPITATOR
MANUFACTURER
TYPE
EFFICIENCY: DESIGN/ACTUAL (%)
MASS EMISSION RATE'
(GR/ACF)
(#/HR)
(#/MM BTU)
NO. OF IND. BUS SECTIONS
TOTAL PLATE AREA (FT/)
FLUE GAS TEMPERATURE
@ INLET ESP @ 100% LOAD (°F)
16- EXCESS AIR: DESIGN/ACTUAL (%)
Boiler number

Hagen
multiple




American

99 +





32,400
360°
20%


cyclones




Standard
































































^    Notes:

-------
M
to
D
•XI
O
a
w
£
25
17. FLUE GAS RATE (ACFM)
@ 100% LOAD
@ 75% LOAD
@ 50% LOAD
18. STACK GAS EXIT TEMPERATURE (°F)a
@ 100% LOAD
@ 75% LOAD
@ 50% LOAD
19. EXIT GAS STACK VELOCITY (FPS)a
@ 100% LOAD
@ 75% LOAD
@ 50% LOAD
20. FLY ASH: TOTAL COLLECTED. (TONS/YEAR)
DISPOSAL METHOD
DISPOSAL COST ($/TON)
21. BOTTOM ASH: TOTAL COLLECTED (TONS/
1975 data DISPOSAL METHOD YEAR)
DISPOSAL COST ($/TON)
22. EXHAUST DUCT DIMENSIONS @ STACK
23. ELEVATION OF TIE IN POINT TO STACK
24. SCHEDULED MAINTENANCE SHUTDOWN
(ATTACH PROJECTED SCHEDULE)
Boiler number

180,900


350°


59.78


500
Silo -*• tr





Oct. 1976
Turbine -










ucked





Boiler fo
















r 3 weeks


































en
I
oo
a) Identify source of values  (test or estimate)


Notes:  Breakdown cost  (#21-22)

        $540 - truck               1/2 mile  (1 way)  to dump site
       $1875 - labor

       $1375 - tractor             $11,235  (cost  for top & bottom)

       $5100 - labor

-------
 en
 D
 O


 13
 O
 s
 M
     E.   I.D.  FAN DATA
1.  MAXIMUM STATIC HEAD  (IN.  W.C-)
2.  WORKING STATIC HEAD  (IN.  W.C.)
                                                                     Boiler number
     Notes:
to
I
10

-------
 F.   FLY ASH DISPOSAL AREAS
     1.  AREAS AVAILABLE  (ACRES)  Unlimited
     2.  YEARS STORAGE  (ASH ONLY)   20 years
     3.  DISTANCE FROM STACK  (FT.)   1/2 mile
     4 .  DOES THIS PLANT HAVE PONDING         M
                                              NO
         PROBLEMS?  DESCRIBE IN ATTACHMENT
 G.   COAL DATA
     1.  COAL SEAM, MINE, MINE LOCATION
         a. 5 sources - districts  15,  22,
  Mines  b> oist.  15  - Welch Mine,  Craig  County,  Okl.	
Location c. Dist.  22  - Colstrip,  Montana;  Dist.  10  - Eagle Mine,  Utah
         d. Dist.  9 - Margareta,  Hopkins  County,  Kentucky	
     2.  QUANTITY  USED BY  SEAM AND/OR MINE
Total _*, a.  42.87 consumption/1000 tons  of coal	
Coal     b>
Total  ^c.  660.678 consumption/1000 mcf  of  gas
Gas	~~~
Analysis^'  1,000 Btu/cf  for gas	
     3.  ANALYSIS   (Avg) from 1975
         GHV  (BTU/LB)  12,015
         S  (%)   3%
         ASH  (%)  11.6
         MOISTURE  (%)  8.6
      4.   PPT  PERFORMANCE  EXPERIENCED WITH LOW
          S FUELS  (DESCRIBE  IN  ATTACHMENT)
 H.  FUEL OIL  DATA
     1.  TYPE
      2.   S CONTENT  (%)
      3.  ASH  CONTENT  (%)
      4.   SPECIFIC  GRAVITY
      5.   GHV  (BTU/GAL)
      COST  DATA
      ELECTRICITY
      WATER
      STEAM
      PLANT SUBSTATION CAPACITY
      APPROXIMATELY WHAT PERCENTAGE OF RATED
      STATION CAPACITY CAN PLANT SUBSTATION
      PROVIDE?
      NORMAL LOAD ON PLANT SUBSTATION?
      VOLTAGE AT WHICH POWER IS AVAILABLE?
 WISDOM POWER PLANT                                        S-10

-------
   K.  OIL/GAS TO COAL CONVERSION DATA

       1.   HAS THE BOILER EVER BURNED COAL?
Boiler No.
Yes or No.
1
Yes








       2.
SYSTEM AVAILABILITY

2 .1  COAL HANDLING

     a.  Is the system still installed?

         Will it operate?
                b,
                c,
         Of the following items which
         need to be replaced:

         Unloading equipment
         Stack Reclaimer
         Bunkers
         Conveyors
         Scales
         Coal Storage Area
           2.2  FUEL FIRING
                a.   Is the system still installed?

                b.   Will it operate?
                c.   Of the following items which
                    need to be replaced:

                    Pulverizers or Crushers
                    Feed Ducts
                    Fans
                    Controls

           2.3  GAS CLEANING
                a.   Is the system still installed?

                b.   Will it operate?

                c.   Of the following items which
                    need to be replaced:

                    Electrostatic Precipitator
                    Cyclones
                    Fly Ash Handling Equipment
                    Soot Blowers - Air Compressors
                    Wall deslaggers
                                                    Yes
                                                    YesD
                                                       D
                                                       D
                                                       D
                                                       D
                                                       D
                                         YesD

                                             D
                                         YesQ
                                             D
                                             D
                                            'D
                                         Yesn
                                             D
                                         YesQ
                                             D
                                             D
                                             D
                                             P
NoD

   D
No K)
   K)
   S
   B
   0
NoD

   D
NoD
   D
   D
   D
NOQ
   D
NoQ
   D
   D
   D
   D
WISDOM POWER PLANT
                                                          S-ll

-------
        2.4  ASH HANDLING
             a.  Is the system still installed?   Yes Q    NoD
             b.  Will it operate?                     D       D
             c.  Of the following items which
                 need to be replaced:
                 Bottom Ash Handling              Yes Q    NoD
                 Ash Pond                             D       D
        Milwaukee  R.R.  Line

        Coal  costs =  $1.05 -  $1.10/MW
WISDOM POWER PLANT                                        S-12

-------
      L.  SUPPLEMENTARY CONTROL  SYSTEM DATA
1.  DOES THE PLANT  NOW  HAVE A SUPPLEMENTAL CONTROL
    SYSTEM (SCS)?                                       Yes

    If yes,  attach  a  description of the system.

2.  IS THE PLANT CAPABLE OF SWITCHING TO LOW
    SULFUR FUELS?                                       Yes

    2.1   Storage capacity for low sulfur fuels
         (tons, bbls, days)

    2.2   Bunkers available for low sulfur coal
         storage?   Derate                              Yes
    2.3   Handling facilities available for low
         sulfur fuels                                   Yes

         If  yes, describe _
                                                                           No
                                                                           No
                                                                           No


                                                                           No
          3.
          5.
    2.4   Time  required to switch fuels and fire
         the low  sulfur fuel in the boiler (hrs)?

    IS THE  PLANT  CAPABLE OF LOAD SHEDDING?
    If yes, discuss 	
          4.   IS THE PLANT CAPABLE OF LOAD SHIFTING?

              If yes, discuss
    POWER PLANT MONITORING SYSTEM

    5.1  Existing system

        a.  Air quality instrumentation

            (1)  Sulfur Oxides - Continuous
                               - Intermittent
                               - Static
            (2)  Suspended particulates
                               - Intermittent
                               - Static
            (3)  Other (describe)	

        b.  Meteorological instrumentation
            If yes, describe
                                                       Yes
                                                                          No
                                                                 Yes  Q]  No  j~]

                                                              Number     Type
        c.  Is the monitoring -data  available?

        d.  Is the monitoring data  reduced and
            analyzed?            .
               No  env. complaints
               ESP costs  - $1.25 million
WISDOM POWER PLANT
                                                                Yes  |  j   No


                                                                Yes  Q   No
                                                                    S_13

-------
                                     - Intermittent
                                     - Static
                   (2)  Suspended particulate
                                     - Intermittent
                                     - Static
                   (3)  Other  (describe) 	
               b.  Meteorological instrumentation
                  If yes, describe 	
          5.2  Proposed  system                                 Yes  Q   No
               If yes, describe	
               a.   Air monitoring instrumentation           Number    Type
                   (1)   Sulfur oxides - Continuous          	
WISDOM POWER PLANT                                              3-14

-------
  Photo  No.  1.   View from ground  level  facing  northwest.   The
  electrostatic  precipitator  and  its  tie-in  ducts  are  shown in
  the  center of  the  photograph.
WISDOM POWER PLANT
                                                          S-15

-------
   Photo  No.  2.  View  from  ground  level  facing  southwest.   The
   coal crusher, conveyor,  coal pile, and coal  car  shaker  are
   shown  in  the center of the photograph.
     Photo No. 3.  View from ground level looking southwest
     showing the ash silo and the coal pile.
WISDOM POWER PLANT
                                                          S-16

-------

    Photo No. 4.  View from ground level looking northeast.  The
    railroad spur is shown in the center of the photograph.  A
    portion of the boiler house is located in the foreground and
    the electrical switchyard is shown in the background of the
    photograph.
      Photo No. 5.  View from boiler house roof facing south
      showing the cooling tower and the surrounding area.
WISDOM POWER PLANT
S-17

-------

    Photo No.  6.   View from the boiler house foof looking east,
    The plant's access road and Stony Creek are shown in the
    center of  the photograph.
    Photo No. 7.  View  from the boiler house roof  facing west
    showing the main railroad  spur and a natural gas meter and
    regulator station.  The area surrounding the plant is shown
    in the background of the photograph.
WISDOM POWER PLANT
S-18

-------
   Photo No.  8.   View from ground level looking north showing
   the plant's nearest neighbor.
   Photo No.  9.   View from the boiler house roof facing west
   showing the coal pile and the surrounding area.
WISDOM POWER PLANT
                                                          S-19

-------
    Photo No. 10.  View from the boiler house roof  facing
    southwest.  The plant's switchyard and the  surrounding  area
    are shown in the background.
WISDOM POWER PLANT
                                                          S-20

-------
                         APPENDIX T




                   L.D. WRIGHT POWER PLANT
L.D. WRIGHT POWER PLANT                                  T-l

-------
                            CONTENTS



L. D. Wright Power Plant Survey Form

L. D. Wright Power Plant Photographs
                                                  Page

                                                  T-3

                                                  T-14
Number
 T-l
                             FIGURES
Site Plan Showing Possible Locations of New
ESP's for Boilers 6 and 7 at the L. D. Wright
Power Plant
                                                  Page
                                                            T-23
Number

 T-l



 T-2



 T-3


 T-4
                             TABLES
Estimated Capital Cost of Electrostatic
Precipitators for Boilers 6 and 7 at the L. D.
Wright Power Plant (1978)

Estimated Annual Operating Costs of Electro-
static Precipitators for Boilers 6 and 7 at the
L. D. Wright Power Plant (1978)

Electrostatic Precipitator Design Values for
Boiler 6 at the L. D. Wright Power Plant

Electrostatic Precipitator Design Values for
Boiler 7 at the L. D. Wright Power Plant
Page



T-20



T-21


T-22


T-23
L. D. WRIGHT POWER PLANT
                                                  T-2

-------
                                                   OMB No. 158S 74023
                    POWER PLANT SURVEY FORM


 A.  COMPANY INFORMATION:

     1. COMPANY NAME:   Department of Utilities

     2. MAIN OFFICE:   725 N.  Park;  Fremont,  Nebraska

     3. RESPONSIBLE OFFICER:   Win. J. Sommers
     4. POSITION:   General Manager

     5. PLANT NAME:   Lon D. Wright Memorial
     6. PLANT LOCATION:  Fremont,  Nebraska

     7. RESPONSIBLE OFFICER AT PLANT LOCATION:   Jess Williams
     8. POSITION:  Superintendent
     9. POWER POOL   Omaha Public  Power District
     DATE INFORMATION GATHERED:   April 28,  1976
     PARTICIPANTS IN MEETING

      Wm.  J.  Sommers
      Forrest McGrew
      Lyle Gill
      Daniel  Wheeler

      N.  David Noe
      Robert  Smolin
Department of Utilities
Department of Utilities
City Attorney; Fremont, Nebraska
U.S. Environmental Protection Agency -
  Region VII
PEDCo Environmental, Inc.
PEDCo Environmental, Inc.
L.D. WRIGHT POWER PLANT
                                                         T-3

-------
jr1


a
B.
§
M
^

£
z

ATMOSPHERIC EMISSIONS
1. PARTICULATE EMISSIONS3 Coal
LB/MM BTU EST Gas
GRAINS/ACF
LB/HR (FULL LOAD)
TONS/YEAR (1975) EST
2. APPLICABLE PARTICULATE EMISSION
REGULATION
a) CURRENT REQUIREMENT
AQCR PRIORITY CLASSIFICATION
REGULATION & SECTION NO.
LB/MM BTU

b) FUTURE REQUIREMENT (DATE: }
REGULATION & SECTION NO.
LB/MM BTU
3. SO_ EMISSIONS3
2 Coal
LB/MM BTU EST Gas
LB/HR (FULL LOAD)
TONS/YEAR (1975) EST
4. APPLICABLE SO EMISSION REGULATION
a) CURRENT REQUIREMENT
REGULATION & SECTION NO.
LB/I-IM BTU

b) FUTURE REQUIREMENT (DATE: )
REGULATION & SECTION NO.
LB/MM BTU
Boiler number
6
1.33
.005


213.8


0.23


.18
1.29
0.0006

207.6

2.5



7
1.33
.005


285.6


0.23


.18
1.29
0.0006

276. 8

2.5













With new
operat

















Boiler No.
ion.

















8 in








             de
                   •y
                  th
res
                                             fr
                                                  te
                                                                 01
                                       tii

-------
 C.  SITE DATA
     1. U.T.M. COORDINATES  Lat.  41°-26'-13",  Long.  96°-27'-17"
     2. ELEVATION ABOVE MEAN SEA LEVEL  (FT)    1,176.74	
     3. SOIL DATA:  BEARING VALUE
             PILING NECESSARY	No  -  On  slab	
     4. DRAWINGS REQUIRED
        PLOT PLAN OF SITE (CONTOUR)
        EQUIPMENT LAYOUT AND ELEVATION
        AERIAL PHOTOGRAPHS OF SITE INCLUDING POWER PLANT,
        COAL STORAGE AND ASH DISPOSAL AREA
     5. HEIGHT OF TALLEST BUILDING AT PLANT SITE OR
        IN CLOSE PROXIMITY TO STACK (FT. ABOVE GRADE)
     6. HEIGHT OF COOLING TOWERS  (FT.  ABOVE GRADE):
L.D. WRIGHT POWER PLANT                                  T_5

-------
      D.
33
50
M
O
EC
1-3
O
33
W
50

BOILER DATA
1. SERVICE: BASE LOAD
STANDBY, FLOATING, PEAK
2 TOTAL HOURS OPERATION (1975)
3 AVERAGE CAPACITY FACTOR (1975)
4. SERVED BY STACK NO.
5. BOILER MANUFACTURER
6 YEAR BOILER PLACED IN SERVICE
7. REMAINING LIFE OF UNIT (years)
8. GENERATING CAPACITY (MW)
RATED
MAXIMUM CONTINUOUS (Coal)
PEAK
9. FUEL CONSUMPTION:
COAL ' RATED
(TPH) '~ " MAXIMUM CONTINUOUS
PEAK
10. ACTUAL FUEL CONSUMPTION
COAL (TPY) (19 75)
GAS (19 75) MCF
11. WET OR DRY BOTTOM
12. FLY ASH REINJECTION (YES OR NO)
13. STACK HGT ABOVE GRADE (FT.)
14. I.D. OF STACK AT TOP (INCHES)

6
Floating
6,456
46%
6
B&W*
1957
21
18.5
15


8.3

15,600
388,400
Wet
No
176
96
Bo:
7
Floating
6,709
45%
7
ERIG+
1963
27
28.5
20


13.2

20,800
771,129
Wet
No
176
120
tier numbei




















>•









































       Notes:   *  B&W  -  Babcock & Wilcox
                +  ERIG - Erie City Iron Works

-------
f
•

D
CD
3C
13
O
s
M
15. FLUE GAS CLEANING EQUIPMENT
a) MECHANICAL COLLECTORS
MANUFACTURER
TYPE
EFFICIENCY: DESIGN/ACTUAL (%)
MASS EMISSION RATE:
(GR/ACF)
(#/HR)
(#/MM BTU)
b) ELECTROSTATIC PRECIPITATOR
MANUFACTURER
TYPE
EFFICIENCY: DESIGN/ACTUAL (%)
MASS EMISSION RATE
(GR/ACF)
(#/HR)
(#/MM BTU)
NO. OF IND. BUS SECTIONS
TOTAL PLATE AREA (FT^)
FLUE GAS TEMPERATURE
@ INLET ESP @ 100% LOAD (°F)
16. EXCESS AIR: DESIGN/ACTUAL (%)
Boiler number
6
West
SCTA
81/70



N.A.









20
7
West
SCTA
81/70



N.A.









20






















































         Notes:

-------
tr1
•

o
s:
SO
£
z
17. FLUE GAS RATE (ACFM)
@ 100% LOAD
@ 75% LOAD
@ 50% LOAD
18. STACK GAS EXIT TEMPERATURE (°F)a
@ 100% LOAD
@ 75% LOAD
@ 50% LOAD
19. EXIT GAS STACK VELOCITY (FPS)a
@ 100% LOAD
@ 75% LOAD
@ 50% LOAD
20. FLY ASH: TOTAL COLLECTED (TONS/YEAR)
DISPOSAL METHOD
DISPOSAL COST ($/TON)
21. BOTTOM ASH: TOTAL COLLECTED (TONS/
YEAR}
DISPOSAL METHOD '
DISPOSAL COST ($/TON)
22. EXHAUST DUCT DIMENSIONS @ STACK
23. ELEVATION OF TIE IN POINT TO STACK
24. SCHEDULED MAINTENANCE SHUTDOWN
(ATTACH PROJECTED SCHEDULE)
Boiler number
6
66.100


335


275
295
300
770
Land Fill

200
Land Fill

8'-0"x
3'-8 1/2"
91'
1978
7
101.500


338


330
300
290




7'-0" x
5 '-6"
91'
1978



















































I

oo
a) Identify  source of values  (test or  estimate)



Notes:

-------
D
•


S
o
ac
t-3
O

w


t)

5
z
E . I . D . FAN DATA
1. MAXIMUM STATIC HEAD (IN. W.C.)
2. WORKING STATIC HEAD (IN. W.C.)
Boiler number















          Notes:
1-3
I
vo

-------
F.   FLY ASH DISPOSAL AREAS
     1.   AREAS AVAILABLE  (ACRES)
     2.   YEARS STORAGE  (ASH ONLY)  Yearly maintenance
     3.   DISTANCE FROM STACK  (FT.)
     4 .   DOES THIS PLANT HAVE PONDING
         PROBLEMS?  DESCRIBE IN ATTACHMENT
     COAL DATA
     1.   COAL SEAM, MINE, MINE LOCATION
         a.
         b.
         c .
         d.
     2.   QUANTITY USED BY SEAM AND/OR MINE
         a.
         b.
         c.
         d.
     3.  ANALYSIS
         GHV (BTU/LB)        10,300
                              0.7
         ASH (%) 	7.0
         MOISTURE  (%)        12.5
     4.   PPT PERFORMANCE EXPERIENCED WITH  LOW
         S FUELS  (DESCRIBE IN ATTACHMENT)
 H.   FUEL OIL DATA
     1.  TYPE
     2 .   S CONTENT  (%)
     3.   ASH CONTENT  (%)
     4.  SPECIFIC GRAVITY
     5.  GHV  (BTU/GAL)
     COST DATA
     ELECTRICITY
     WATER
     STEAM
     PLANT SUBSTATION CAPACITY
     APPROXIMATELY WHAT PERCENTAGE  OF  RATED
     STATION CAPACITY CAN  PLANT  SUBSTATION
     PROVIDE?	Would need enlargement
     NORMAL LOAD ON PLANT  SUBSTATION?
     VOLTAGE AT WHICH  POWER  IS  AVAILABLE?
L.D. WRIGHT POWER PLANT                                   T-10

-------
   K.   OIL/GAS  TO COAL CONVERSION  DATA

       1.   HAS  THE BOILER EVER BURNED COAL?
Boiler No.
Yes or No.
6
Yes
7
Yes






       2.
SYSTEM AVAILABILITY

2 .1  COAL HANDLING
     a.  Is the system still installed?

     b.  Will it operate?

     c.  Of the following items which
         need to be replaced:
         Unloading equipment
         Stack Reclaimer
         Bunkers
         Conveyors
         Scales
         Coal Storage Area
2.2  FUEL FIRING
         Is the system still installed?
         Will it operate?
                                         Yes El
                                                    YesD
                                                    NA D
                                                       D
                                                       D
                                                       D
                                                       D
                                                    Yes
                    Of  the  following items  which
                    need to be replaced:
                    Pulverizers or Crushers
                    Feed Ducts
                    Fans
                    Controls
2 .3  GAS CLEANING
     a.  Is the system still installed?

     b.  Will it operate?
     c.  Of the following items which
         need to be replaced:
         Electrostatic Precipitator   NA
         Cyclones
         Fly Ash Handling Equipment
         Soot Blowers - Air Compressors
         Wall deslaggers
                                          YesQ
                                             D
                                             D
                                             D
                                                       0
                                          YesQ
                                             E
                                                             No D

                                                               D
                                                  No K! Frozen
                                                     n  Coal
                                                     0 Problem
                                                     El


                                                  NoD

                                                     D



                                                  No H
                                                             No
                                                     D
                                                             NoQ
                                                                D
                                                        E ModifyD
                                                        D       53 May be
                                                        P       K requir-
                                                                  ed.  •
L.D. WRIGHT POWER PLANT
                                               T-ll

-------
       2 .4  ASH HANDLING
            a.  Is the system still installed?    Yes53     No Q

            b.  Will it operate?                     £)       D
            c.  Of the following  items which
                need to be replaced:
                Bottom Ash Handling               Yes S     NoQ
                Ash Pond                             53       D
L.D. WRIGHT POWER PLANT                                  T-12

-------
  L.   SUPPLEMENTARY  CONTROL  SYSTEM DATA
      1.   DOES THE  PLANT NOW HAVE A SUPPLEMENTAL CONTROL
          SYSTEM  (SCS)?
          If yes, attach a description of the system.
      2.   IS THE  PLANT CAPABLE OF SWITCHING TO LOW
          SULFUR  FUELS?
          2.1  Storage capacity for low sulfur fuels
              (tons, bbls, days)
          2.2  Bunkers available for low sulfur coal
              storage?
          2.3  Handling facilities available for low
              sulfur fuels
              If yes, describe 	
      3.
      4.
      5.
Yes
                                                   Yes
                                                             No
          No
Yes  £

Yes
                                                             No

                                                             No
2.4  Time required  to  switch  fuels  and  fire
     the low sulfur fuel  in the  boiler  (hrs)?  N.A.
IS THE PLANT CAPABLE OF LOAD  SHEDDING?
If yes, discuss 	
IS THE PLANT CAPABLE OF LOAD  SHIFTING?
If yes, discuss  	
POWER PLANT MONITORING  SYSTEM
5.1   Existing system
     a.   Air quality instrumentation
         (1)  Sulfur Oxides  -  Continuous
                            -  Intermittent
                            -  Static
         (2)  Suspended participates
                            -  Intermittent
                            -  Static
         (3)  Other (describe)	
     b.   Meteorological instrumentation
         If yes, describe 	
               c.   Is  the  monitoring  data available?
               d.   Is  the  monitoring  data reduced and
                   analyzed?
                                                   Yes
                                                                       No  fj[)
                                                             Yes
                                                             No
                                                             Yes  Q   No  Q]
                                                          Number     Type
Yes
Yes
                                                              No  D
                                                              No
L.D.  WRIGHT POWER PLANT
                                                                   T-13

-------
          ii.2  Proposed system                                 Yes  P[]   No

               If yes,  describe	
                                      -  Intermittent
                                      -  Static
                   (2)   Suspended  particulate
                                      -  Intermittent
                                      -  Static
                   (3)   Other  (describe) 	
               b.   Meteorological  instrumentation
                   If yes,  describe 	
               a.   Air monitoring  instrumentation           Number     Type

                   (1)  Sulfur  oxides  - Continuous          	
L.D.  WRIGHT POWER PLANT                                        T_14

-------
    Photo No.  1.   View from ground level facing west showing
    the Lon D.  Wriqht Power Plant.
  Photo No. 2.  View from the boiler house roof  facing  north-
  east showing the cooling tower and the surrounding  area.
L.D. WRIGHT POWER PLANT
T-15

-------
  Photo  No.  3.   View from the boiler house roof facing east
  showing the warehouse and the surrounding area.
 Photo No.  4.   View from the boiler house roof facing south-
 east showing  the ash pond and part of the coal storage area
 In the background,  the surrounding area is shown.
L.D. WRIGHT POWER PLANT
T-16

-------
 Photo No. 5.  View from the boiler house roof  facing  south-
 east showing the crusher house and part of  the coal storage
 area.
 Photo No. 6.  View from the boiler house roof facing north-
 west showing the surrounding residential area.
L.D. WRIGHT POWER PLANT
T-17

-------
  Photo No. 7.  View from the boiler house roof facing south-
  east showing stacks 6 and 7 and the ash ponds.
 Photo No. 8.  View from ground level facing southeast showing
 the propane tank farm.
L.D. WRIGHT POWER PLANT
T-18

-------
   Photo No. 9.  View from ground level facing west showing the
   ESP for Boiler 8.
   Photo No. 10.  View  from the boiler house roof facing  south
   showing the top of the ESP for Boiler 8.
L.D. WRIGHT POWER PLANT
T-19

-------
       TABLE T-l.   ESTIMATED CAPITAL COST OF  ELECTROSTATIC
      PRECIPITATORS FOR BOILERS 6  AND 7  AT THE  L.  D.  WRIGHT
                       POWER PLANT (1978)
Direct Costs

ESP                                               $  2,208,000

Ash handling                                          183,000

Ducting                                               259,000

                              Total direct costs  $  2,650,000

Indirect Costs

Interest during construction  8% of direct costs  $    212,000

Contractor's fee             10% of direct costs      265,000

Engineering                   6% of direct costs      159,000

Freight                    1.25% of direct costs       33,000

Offsite                       3% of direct costs       80,000

Taxes                       1.5% of direct costs       40,000

Spares                        1% of direct costs       27,000

Allowance for shakedown       3% of direct costs       80,000
          Total indirect costs                    $   896,000

          Contingency                                 709,000

          Total                                   $ 4,255,000

          Coal conversion costs                       475,000
          Grand total       >                      $ 4,730,000

          $/kW                                         135.14
 L.D. WRIGHT POWER PLANT                                   T 20

-------
  TABLE T-2.  ESTIMATED ANNUAL OPERATING COSTS OF ELECTROSTATIC
PRECIPITATORS FOR BOILERS 6 AND 7 AT THE L. D. WRIGHT POWER PLANT
                              (1978)
Utilities

Electricity
Water

Operating Labor

Direct labor
Supervision

Maintenance

Labor and materials
Supplies

Overhead

Plant
Payroll
Quantity

216 kW
2911 103 gal/yr
Unit Cost

27.5 mills/kWh
SO.01/103 gal
0.5 man/shift      $8.50/man-hour
15% of direct labor
 2% of fixed investment
15% of labor and materials
50% of operation and maintenance
20% of operating labor
Coal Cost Differentials

Operating and maintenance

Fixed Costs

Depreciation        (4.55%)
Interim replacement (0.35%), Z = 16.40% of fixed
                                   investment
Insurance           (0.30%)
Taxes               (0.00%)
Capital cost       (11.20%)
Total fixed cost

Total cost
Fuel cost

Net annual cost
Mills/kWh
Annual Cost

$    24,000
      1,000
                      73,000
                      11,000
                      85,000
                      13,000
                      91,000
                      17,000
                                         83,000
                                    $   698,000

                                    $ 1,096,000
                                        118,000

                                    $ 1,214,000
                                           8.70
  L.D. WRIGHT  POWER PLANT
                                      T-21

-------
         Table  T-3.   ELECTROSTATIC PRECIPITATOR DESIGN

      VALUES  FOR BOILER 6  AT THE L.D.  WRIGHT POWER PLANT
          Design Parameter
Value
      Collection efficiency,  %
       (Overall)

      Specific collecting area,
       ft2/1000 acfm
                               2
      Total collecting area,  ft

      Superficial velocity,  fps

      Overall ESP dimensions
       (height x width x depth), ft
        excluding hopper dimensions
96.9


431


28,500

4

30 x 9 x 47
L.D. WRIGHT POWER PLANT
            T-2.2

-------
          Table T-4.   ELECTROSTATIC PRECIPITATOR DESIGN

       VALUES FOR BOILER 7 AT THE L.D.  WRIGHT POWER PLANT
           Design Parameter
Value
       Collection efficiency,  %
        (Overall)

       Specific collecting area,
        ft2/1000 acfm
                                2
       Total collecting area,  ft

       Superficial velocity,  fps

       Overall ESP dimensions
        (height x width x depth), ft
         excluding hopper dimensions
96.9


431


44,000

4

30 x 14 x 46
L.D. WRIGHT POWER PLANT
           T-23

-------
                           NEW
;  NEW i
!  ESP !
                                                      WAREHOUSE
                                         WATER
                                       TREATMENT
                                        BUILDING
    Figure T-l.  Site  plan showing  possible locations of

new ESP's  for Boilers  6  and 7 at  the L.D. Wright power plant.
L.D. WRIGHT POWER PLANT
                               T-2 4

-------
                    APPENDIX U




BASIS OF SODIUM SOLUTION REGENERABLE PROCESS DESIGN
                        U-l

-------
                         APPENDIX U

     BASIS OF SODIUM SOLUTION REGENERABLE PROCESS DESIGN


     A.    DESIGN VALUES

     The design basis for the sodium solution regenerable

system was determined after review of process designs now in

use or proposed for use, and discussions with Davy Power

Gas.  A process flow sheet is presented in Figure U-l.  A

list of equipment required for the sodium solution regen-

erable process is shown in Table U-l.

     Values of the major design parameters are tabulated

below:

     0    Variable design parameters:  Table U-2

     0    Constant design parameters:  Tables U-3 and U-4

     0    Flue gas pressure:  atmospheric

     0    Reheat:  50°F above dew point  (from 125 to 175°F)

     0    Soda ash consumption:  5% stoichiometric

Soda Ash System

     Size:   (unloading hoppers for the twenty plants):
     200  tons

     Feeders:  capacity = 3.0 x maximum soda ash flow

     Na~CO,  slurry storage tank:  4 hours

     Na^CO.,  slurry feed pump:  1 pump

     Raw water pumps:  two
                             U-2

-------
c
i
         FROM TRAINS
*-*  YEKTURI CIW. TWKSji





TO DISPOSAL
                               Figure  U-l.   Sodium solution regenerable system.

-------
COMPANY

LOCATION
    EQUIPMENT LIST
•  PEDCo-ENVIRONMENTAL
                                    Cincinnati,  Ohio
P.N. 	
CHECKED
BY
           Sodium Solution Regenerate
COMPUTED
                                        DATE
                                                                          DATE
Tflhl^ "-I . FnuTPMFMT f-TST FOR THE SODIUM SOLUTION REGENERABLE SYSTEM
NO.

Wl-Pl
VIL-P2
Ml -PI
UL-P5

WL-S1
WL-S2
WL-S3
WL-S4
WL-S5
WL-S6
WL-S7
WL-S8
WL-S9
WL-S10
WL-S11

WL-PT1
WL-PT2
Ul -PT"?
WL-PT4
WL-PT5
WLdPJ.6
WL-PT7



DESCRIPTION
NaCO, Preparation System
Storage Silo
Vibratinq Feeder

C «J
Ma TO Anitatrir*
Na^CO-, Make-up Pump

"2 ~
<;n Ahcnrhrr
Absorber Circulation Pumps
I.D. Fan
Hc-at Exchanger
Soot Blower
Butterfly Valving
Absorber Feed Surge Tank
Absorber Feed Surge Tank Agitator
Ducting
Absorber Product Surqe Tank
Absorber Product Surqe Tank Agitator
Purge Treatment
Purae Stream Heat Exchanger
Refriqeration Unit
Refrigeration Heat Exchanqer
Glycol Storage Tank
n wml Pnmn*;

Ccntri fune



NO . OF
ITEMS








.




















H.P/
ITEM





























TOTAL
H.P.





























COST/
ITEM





























TOTAL
COST





























                                            U-4

-------
COMPANY

LOCATION
  EQUIPMENT LIST

PEDCo-ENVIRONMENTAL
 Cincinnati, Ohio
P.N. 	
CHECKED
BY
       Sodium Solution Regenerable
                                                         COMPUTED
                                                         BY
DATE
                                      DATE
     Table U-l.  (Cont.) EQUIPMENT LIST FOR THE SODIUM SOLUTION REGENERABLE SYSTEM
ITEM
NO.
WL-PT8
WL-PT9
WL-PT10
WL-PT11
WL-PT12
WL-PT13
WL-R1
Jl -P?
WL-R3
WL-R4
JL-R5
'.•IL-R6
UL-R7
UL-R8
UL-R9
ML- RIO
UL-R11
WL-R12
WU£RL_
ULdEB2_
'•JUP_R3_
'.^IL-PR4





DESCRIPTION
Centrate Tank
Dryer
Elevator
Na-,50, Storage Tank
c 
-------
Table U-2. VARIABLE DESIGN  PARAMETERS FOR SODIUM SOLUTION




                 REGENERABLE SYSTEMS
1 Plant
Arthur Kill

Astoria




E.F. Barrett
Bergen

Cromby
Hudson
Lovett


Ravenswood
Ridge land





Boiler
No.
20
30
10
20
30
40
50
10
1
2
2
1
3
4
5
30
1
2
3
4
5
6
Flue gas
temp. , °F
300
293
300
300
300
300
300
281
269
269
240
291
310
300
288
700
385
385
385
385
334
334
Inlet S02 cone. ,
Ib/MM BtU
2.38
2.38
2.38
2.38
2.38
2.38
2.38
2.38
2.38
2.38
4.29
3.04
2.38
2.38
2.38
2.38
7.24
7.24
7.24
7.24
7.24
7.24
Outlet S02 cone.,
Ib/MM Btu
0.40
0.40
0.40
0.40
0.40
0.40
0.40
0.40
0.30
0.30
1.80
0.30
0.40
0.40
0.40
0.40
1.80
1.80
1.80
1.80
1.80
1.80
                          U-6

-------
Scrubbing System (Each Train)


     Fan:  double inlet centrifugal type (1-100% unit)


           AP:  16.0" H20


     Absorber:  sieve tray type with two stages

           AP:  8.0" H20


           L/G:  3 gpm/MAcfin/stage (inlet gas to absorber
           scrubber)


           Slurry concentration:  25% (wt.)


           S02 removal:  see Table U-3

           Gas velocity:  8 fps
   Table U-3.   S02 REMOVAL EFFICIENCY FOR SODIUM SOLUTION


                     REGENERABLE SYSTEMS
Plant
Arthur Kill
Astoria
E.F. Barrett
Bergen
Cromby
Hudson
Lovett
Ravenswood
Ridgeland
SO removal efficiency, %
83.2
83.2
83.2
87.4
58.0
90.1
83.2
83.2
75.2
         Solution  storage  tanks:   24-hour  storage

         Pumps:  two/stage plus one  spare  pump  for  every
         unit
                             U-7

-------
Table U-4.  SIZES OF TURBULENT CONTACT ABSORBERS FOR THE




           SODIUM SOLUTION REGENERABLE PROCESS
Plant
Arthur Kill
Astoria
E.F. Barrett
Bergen
Cromby
Hudson
Lovett
Ravenswood
Ridgeland
No. of
absorbers
8
16
1
5
2
4
5
8
4
2
Dimensions (h
45 x 15
45 x 15
45 x 15
45 x 15
45 x 15
45 x 15
45 x 15
45 x 15
45 x 15
45 x 15
X W X 1) , ft
x 40
x 37
x 60
x 42
x 35
x 35
x 39
x 40
x 37
x 56
                             U-8

-------
Entrainment separator:  Chevron vane type (two/absorber)

     Number passes:  two

     AP:  2.0" H20

     Gas velocity:  7 fps

Purge treatment:

     Refrigeration:  temperature =  40°F; flow = 5% of
     recirculation rate

     Centrifuge:  solids = 5% of stoichiometric Na-CO^
                                                  ^  *5
Acid Plant:  125% of average SO- flow

SO- regeneration:

     Evaporators:  30% slurry of NaHSO-j based on SO2
     absorbed.  Evaporators are sized for 1 hour retention
     and 50% free space.

     Reboilers:  7.5°F temperature rise; 8 Ib of steam per
     Ib of S02

     Stripper:  overhead is 1 Ib SO- and 1 Ib H-0 for every
     1 Ib S02                      ^           ^

Reheater:  indirect tubular type

     AT:  50°F  (inlet temperature = 125°F;
               outlet temperature = 175°F)

     Heating medium:  low-pressure steam

     B.   DESIGN RATIONALE

     0    The soda ash storage silo is sized for 30 days
          storage to allow the plant to continue operating
          in the event of an interruption in the supply of
          soda ash.

     0    The feeders are sized at 3.0 times the maximum
          soda ash flow.

     0    The soda ash slurry storage is sized for 4 hours
          storage.
                             U-9

-------
All critical pumps in the process are provided
with spares.

A sieve tray unit selected for removal of the bulk
of the SC>2 has 2 stages of sieve trays to provide
the contact area necessary for mass transfer to
S02 from the gas to the liquid phase.  The absorber
is designed for an L/G of 3 GPM/MACFM/stage  (inlet
gas to the absorber) and a pressure drop of  8 in.
H20.  Slurry concentration will be 25%; gas  velo-
city in the unit will be 8 FPS; and SOj removal is
specified to be about 90%.  Standard sizes for
absorbers and Venturis for the sodium solution
regenerable process are showning Tables U-5  and
LJ-6, respectively.  Standard scrubber modules are
presented in Figures U-2a through U-2d.

The absorbers have common solution storage tanks
sized to provide 24-hour storage of the slurry.
This storage time allows the absorbers to operate
for approximately 24 hours in the event the  acid
plant should breakdown.

A Chevron vane-type entrainment separator removes
mist thatis carried over in the gas from the
absorber.  This unit contains two stages of
Chevron vanes, which are washed continuously with
water.  Superficial gas velocity through the unit
is 7 FPS and the pressure drop is expected to be
about 2 in. H20.

The gas leaving the entrainment separator must be
reheated to desaturate it and provide buoyancy for
adequate atmospheric dispersion.  The number of
degrees of reheat necessary is variable and
dependent on a number of factors such as stack
height, local weather conditions, population
density, terrain, and maximum allowable S02
ground-level concentration.  For this study, a
reheat AT of 50°F is used; this value is believed
to be about the minimum acceptable.  Obviously,
the lowest acceptable reheat AT should be chosen,
since each increase of 50°F of the flue gas
temperature requires about 1.5% of the gross heat
input to the plant.
                     U-10

-------
         Table U-5.  TABLE OF ABSORBER  STANDARD SIZES FOR THE SODIUM SOLUTION REGENERABLE PROCESS
G
i
Description
Flow rate @125°F, acfm
Flow rate @300°F, acfm
Nominal MW
Absorber
Length (A) , ft
Width (B) , ft
Height (C) , ft
Absorber tank
Diameter (D) , ft
Height (E) , ft
Entrainment Separator
Height (F) , ft
Hot duct
Dimension (G) , ft
Reheater to Separator
Overall
dimensions (H) , ft
Stack duct
Dimensions (J) , ft
I
300,000
398,000
150

39.0
15.0
45.0

44.0
20.0

15.0

12 x 11

30.0

14 x 13
II
250,000
325,000
110

28.0
15.0
'45.0

37.0
20.0

15.0

10 x 9

25.0

12 x 10
III
150,000
195,000
65

17.0
15.0
45.0

29.0
20.0

15.0

7x8

20.0

10 x 8
IV
100,000
130,000
45

11.0
15.0
45.0

23.5
20.0

15.0

6x6

20.0

7x7
V
50,000
60,000
20

6.0
15.0
45.0

17.0
20.0

15.0

4x5

20.0

5x5

-------
           Table U-6.  TABLE OF  VENTURI STANDARD  SIZES FOR THE  SODIUM SOLUTION  REGENERABLE  PROCESS
c
i
i—1
NJ
Description
Flow rate @ 125°, acfm
Flow rate @ 300°, acfm
Nominal MW
Venturi
Length (K) , ft
Width (L) , ft
Height (M) , ft
Venturi tank
Diameter (N) , ft
Height (O) , ft
I
300,000
390,000
150

29.0
6.5
20.0

15.5
15.0
II
250,000
325,000
110

22.5
6.0
20.0

13.0
15.0
III
150,000
195,000
65

15.0
5.5
20.0

10.0
15.0 .
IV
100,000
130,000
45

10.0
5.5
20.0

8.25
15.0
V
50,000
65,000
20

5.6
5.0
20.0

6.0
15.0

-------
            Y
             \
  FROM BOILER. TO  STACK
x"l



xTd;:

•v
i
i

-

	 1
i
i
\
	 Y.

,'



« _
\
*"



-^
^
                                 PLAN VIEW
             TO STACK
                           /
                     REHEATER
                                      ENTRAINMENT
                                       SEPARATOR
LOCATION OF V
(IF APPLICABLE
SEE FIGURE
ENTURI


\
~*~7\ "G" (FAN

FROM BOILER





1



Af
1


JSORBE
R
ABSORBER
TANK
•^ 	
ii n ii ^^

*
"E"
-, t

                             ELEVATION
Figure  U-2a.  Plan  view and  elevation  of an absorber,
                             U-13

-------
                     •r •
                     i
       •C"
                 I	1 !	•
                SIDE VIEW
Figure U-2b.   Side  view of an absorber.
                    U-14

-------
 FROM BOILER-




\ :





1
1



II







*
1
i
.






^ " N "_^.
~D33
y> *\_
' i i '
i i
i i
• i i •
"V t/~



r
\

                                                    •TO SCRUBBER
                             PLAN VIEW
FROM  BOILER
                                                     TO SCRUBBER
                            ELEVATION
Figure  U-2c.  Plan  view and elevation of  a  venturi scrubber,
                                 U-15

-------
                 SIDE VIEW
Figure U-2d.  Side view of a venturi  scrubber,
                        U-16

-------
In the indirect finned tubular heat exchanger
selected for the reheater, the first 33% of the
rows of tubes are constructed of Alloy 20 for
corrosion resistance to the gas, which enters at
its dew point.  The remaining 67% of the rows are
constructed of carbon steel.  Heating medium for
the unit is low-pressure saturated steam.  Pres-
sure drop through the reheater is calculated to be
about 4.0" H20.

Based on experience at Will County, a retractable
B&W type soot blower is used for each 25 ft2 of
scrubber exit duct cross-section for the heat
exchanger.  Half of the soot blowers are on the
entry side, the remainder on the exit side of the
heat exchanger.

Cost of reheat is based purely on an oil con-
version cost in Btu's.

Purge treatment equipment is based mostly on TVA
cost estimates.

The acid plant costs are based on data furnished
by Wellman-Lord.
                   U-17

-------
           APPENDIX V




BASIS OF LIMESTONE PROCESS DESIGN
              V-l

-------
                         APPENDIX V

              BASIS OF LIMESTONE PROCESS DESIGN

     A.    DESIGN VALUES

     The process design basis for the wet limestone system

used in this study was determined after review of process

design used or proposed for use at various installations and

discussions with control system manufacturers.  A flowsheet

of the limestone system is shown in Figure V-l.  Table V-l

presents a complete list of equipment required for the

limestone process.  Typical installation times for the

various stages of the limestone process are presented in

Figure V-2, the Critical Path Schedule.

     Values of the major design parameters are tabulated

below:

     0    Variable design parameters:  Table V-2.

     0    Constant design parameters:  Tables V-3 and V-4.

     0    Flue gas pressure:  atmospheric

     0    Reheat:  50°F above dew  point  (from  125 to 175°F)

     0    Limestone consumption:   130% stoichiometric

Limestone System

     Size:   (unloading hoppers  for the twenty  plants):   200
     tons
                             V-2

-------
                                                                                                          (1IUCT

                                                                                                    • tfPIl   i» i.t.l
I

u>
                                                                                       —-L  V W
                                                                                       c7cTFm*Vj    t     4     S
                                                                                    uueci riiinei in*
                                                                 ruio ituccc 10 iiiroiu-
                                  Figure  V-l.    Limestone scrubbing  system.

-------
COMPANY _

LOCATION
   Table  V-l.
  EQUIPMENT LIST
PEDCo-ENVIRONMENTAL
 Cincinnati, Ohio
P.N. 	
CHECKED
BY
                                                       COMPUTED
                                                       BY
DATE
                                     DATE
ITEM
NO.

LL-L1
LL-L2
LL-L3
LL-L<*
LL-L5
LL-L6
LL-L7
LL-L8
LL-L9
LL-L10
LL-L11
LL-L12
LL-LI3
LL-LH
LL-L15
LL-S1
LL-S2
LL-S3
LL-S1*
LL-S5

. U-A1
U-A2
LL-A3
LL-A^

LL-CI
LL-C2
DESCRIPTION
Limestone Handling System
Hopper
Unloading Feeder
Tunnel Conveyor
Flop Gate
Stacker
Plant Conveyor
Tr iooer Bel t
Storage Si los
Vibrating Feeders
Weigh Feeders
Dust Col lector
Bal 1 Mills
Bal 1 Mill Tanks
Bal 1 Mill Tank Sump Pump
Limestone Classifier
Slurry Storage Tank
Slurry Mixer
Slurry Pumps
Slurry Surge Tank 	
Surge Pump
SO-) Scrubbing System
Absorber
Absorber Tank
Absorber Agi tator
Absorber Circulation Pump
Sludqe System
Clarifier Tank
Overflow Pump
NO. OF
• ITEMS





























H.P/
ITEM





























TOTAL
H.P.





























COST/
ITEM





























TOTAL
COST





























                                           V-4

-------
COMPANY
Table V-l (Continued).
    EQUIPMENT LIST     P.N.
LOCATION
  PEDCo-ENVIRONMENTAL
   Cincinnati,  Ohio
CHECKED
BY
                                                       COMPUTED
                                                       BY
                                                                       DATE
                                       DATE
ITEM
NO.
LL-C3
LL-C^
LL-C5
LL-C6
LL-C7
LL-C8
LL-C9
LL-C10
LL-CI1
LL-SR1

LL-H1
LL-H2

LL-AP1
LL-AP2
LL-AP3

LL-V1
LL-V2
LL-V3








DESCRIPTION
Underflow Pump
Vacuum F i 1 ter
Vacuum Pump
Return Filtrate Pump
Mix Tank
Mixer
Sludge Pump
Add i t i ve Hopper
Water Make-Up Pump
Mobi le Equipment
Heat t'xchanqer System
Heat Exr.hanqer
Soot Blowers
Air Pipi ng System
Induced Draft Fans
Ducting
Butterfly Valves w/Operator
Particulate Removal System
Venturi System
Venturi Circulation Tank
Venturi Circulation Tank








NO. OF
ITEMS





























H.P/
ITEM





























TOTAL
H.P.





























COST/
ITEM





























TOTAL.
COST





























                                         V-5

-------
                                                                                         SECUT »IH«e
                                                                    DESIGN PIPING. WE CV.S.
                                                                    t P5tr«i BILL or E.-.H.;
                                                                             '
                  riNALIIE
                  LAt CUTS/
 IkDIUIU CRITICAL ACTIlin


• INDICATES OU«n ACTIVITY
u/ .QOJ -y:*
'[PARC PREUMIMN-
IVIL D»»JIM;S «x
till OF MATERIAL
FINALIZE 1C
CONTVC1 ro< I
AM) CPEMI
y m pV«ti
^\ ^,'1?;
[IZj \368J/ L
bccu>c
l.C't'-TSI
[1
CLt« i
cr«L
LEVEI
11
OBTAI
PAOCUR
DUCtIN
DESIGN 1 SPECIF
I.D. FAN
111
ursici i spccirr s
ILECiaiCAL EQUIP. I
LU \i
DESIGN SLUDGE S~*
STSIEH / l!
QO) li»|l
DESIGN fK>
i:r[siONC /*T7\
srsi'.i .( H A
llSJ \»ijj/
!•• TflW JL
IHIIIONI XT*N
c«i$ r \\\
                                                                                                   (_ INSTALL t tRtCT
                                                                                                          t«ui?»cirr
                                 Figure  V-2.    Critical  path  schedule.

-------
Table V-2.   VARIABLE DESIGN PARAMETERS FOR




            LIMESTONE SYSTEMS
Plant
Arthur Kill

Astoria




E.F. Barrett
Bergen

Cromby
Hudson
Lovett


Raven swood
Ridgeland





Boiler
No.
20
30
10
20
30
40
50
10
1
2
2
1
3
4
5
30
1
2
3
4
5
6
Flue gas
temp. ,°F
300
293
300
300
300
300
300
281
269
269
240
291
310
300
288
700
385
385
385
385
334
334
Inlet SO2 cone. ,
Ib/MM Btu
2.38
2.38
2.38
2.38
2.38
2.38
2.38
2.38
2.38
2.38
4.29
3.04
2.38
2.38
2.38
2.38
7.24
7.24
7.24
7.24
7.24
7.24
Outlet S02 cone. ,
Ib/MM Btu
0.40
0.40
0.40
0.40
0.40
0.40
0.40
0.40
0.30
0.30
1.80
0.30
0.40
C.40
0.40
0.40
1.80
1.80
1.80
1.80
1.80
1.80
                    V-7

-------
 Feeders,  Conveyors:   capacity = 5.8 x maximum limestone
 flow

 Lime storage silos:   3 days storage

 Limestone slurry storage tank;  24  hours storage

 Limestone slurry feed pumps:  two pumps/train with one
 spare for each two operating pumps

 Raw water pumps:  two

 Clarifier and sludge pond dimension:  see Table V-3

 Clarifiers:  two per plant
Table V-3.
CLARIFIER AMD SLUDGE POND DIMENSIONS FOR

      LIMESTONE SYSTEMS
Plant
Arthur Kill
Astoria
E.F« Barrett
Bergen
Cromby
Hudson
Lovett
Ravenswood
Ridgeland
Clarifier, ft _.
Diameter
75
100
49
65
60
56
49
75
165
Height
20
20
20
20
20
20
20
20
20
Sludge pond,
acre-ft/yr
44
73
26
64
45
49
17
43
115
                          V-8

-------
Scrubbing System (each train)

     Fan:  double inlet centrifugal (1-100% unit)

           AP:  24.0" H20

     Absorber:  TCA type with two beds

     L/G:  65 gpm/MAcfm  (inlet gas to absorber scrubber)

     Slurry concentration:  8% (wt.)

     SO- removal:  see Table V-4

           Table V-4.  S02 REMOVAL EFFICIENCY FOR

                     THE LIMESTONE SYSTEMS
Plant
Arthur Kill
Astoria
E.F. Barrett
Bergen
Cromby
Hudson
Lovett
Ravenswood
Ridgeland
SO- removal, %
83.2
83.2
83.2
87.4
58.0
90.1
83.2
83.2
75.2
     Gas velocity:  10 fps, absorber

     Circulating tank:  10 minutes retention, absorber

     Pumps:  four/train plus one spare pump for each train,
     absorber
                              V-9

-------
Entrainment separator:  Chevron vane type

     Number passes:  two

     AP:  2.0" H20

     Gas velocity:  7 fps

Reheater:  indirect tubular type

     AT:  50°F (inlet temperature + 125°F; outlet
          temperature = 175°F)

     Heating medium:  low pressure steam

       B.  DESIGN RATIONALE

     0    The unloading hoppers are sized to hold 200 tons
          to accomodate unloading of trains as well as
          trucks.

     0    The live storage silo is sized for 3 days storage.

     0    The feeders and conveyors are sized at 5.8 times
          the maximum limestone flow to allow the unloading
          of limestone during a 40-hour week while the plant
          operates continuously.

     0    The limestone slurry storage tank is sized for 24
          hours storage to allow the scrubbing trains to
          continue operating this limestone for 24 hours if
          supply  is interrupted.

     0    All critical pumps in the process are provided
          with spares.

     0    The thickeners and new pond are used with diking
          to provide sufficient pond space for the life of
          the plant.  The thickener concentrates the ef-
          fluent  slurry from 15% solids to 30% solids and
          then discharges the 30% effluent slurry to the
          vacuum  filtration units.  The effluent leaves the
          filtration unit with a slurry 60% by weight and
          then enters a mixing tank where the fixation
          additives are stirred in with the 60% slurry,
          which is then pumped to the sludge pond.  Figure
          V-3 illustrates how sludge pond dimensions are
          calculated.
                              V-10

-------
<
I
     o
     o

     x:
     o
     Lul
O
C£.
O.
         40--
         20--
            0    20   40  60   80  100   120  140   160  100   200  220  240  260  200  300  320  340  360  330
                                    LENGTH L AND WIDTH W OF SLUDGE POND (FEET)


                              Figure  V-3.   Sludge  pond  size sheet.

-------
         A UOP* Turbulent Contact Absorber  (TCA) was selected
         for removal of the bulk of the S02.  This unit has
         two beds of hollow plastic spheres, which move
         randomly between support grids and provide the
         contact area necessary for mass  transfer of S02  from
         the gas to the liquid phase.  The absorber is
         designed for an L/G of 65 gpm/MAcfm  (inlet gas to
         the absorber) and a pressure drop of 7  in. H20.
         Slurry concentration will be 8%; gas velocity in
         the unit will be 10 fps; and S02 removal is
         specified to be about 85% plus.  The size of the
         turbulent contact absorbers is shown in Table V-5.
         Standard sizes for absorbers and Venturis for the
         limestone process are shown in Tables V-6 and V-7,
         respectively.  Standard scrubber modules are
         presented in Figures V-4a through V-4d.

         Each  absorber has a circulating  tank sized to
         provide a 10-minute retention time based on the
         slurry circulation rate.  This retention time is
         essentially the same as that reported by others
         and  should provide sufficient time for  desuper-
         saturation and thus reduce scaling potential.   If
         long  retention time are required,  the incremental
         cost  would be small since the circulating tanks  do
         not  represent large cost  items;  space limitations
         may  require locating a secondary tank some dis-
         tance away and providing  additonal piping.

         The  Chevron vane-type entrainment  separator  is
         incorporated  to remove mist carried  over  in  the
         gas  from the  absorber.  This unit  contains two
         stages of Chevron vanes,  which are washed con-
         tinuously with water.  Superficial gas  velocity
         through  the unit  is  7  fps and the  pressure drop  is
         expected to be about  2.0" H20.   Design  of  the unit
         is  based on information from C-E,  Chemico, and  UOP.

         The  gas  leaving  the  entrainment  separator must  be
         reheated to desaturate it and provide buoyancy  for
         adequate atmospheric dispersion.   The number of
         degrees  of reheat necessary  is variable and
         dependent on  a number of  factors such as  stack
         height,  local weather conditions,  population
         density, terrain, and maximum allowable SO2
         ground  level  concentration.  For this  study, a
*
  Universal Oil Products Company (Air Correlation Division).
                              V-12

-------
Table V-5.  SIZES OF TURBULENT CONTACT ABSORBERS FOR




                THE LIMESTONE SYSTEMS
Plant
Arthur Kill
Astoria
E.F. Barrett
Bergen
Cromby
* Hudson
Lovett
Ravenswood
Ridgeland
No. of
absorbers
8
16
1
5
2
4
5
8
4
2
Dimensions (h x w x 1) , ft
45 x 15 x 32
45 x 15 x 30
45 x 15 x 45
45 x 15 x 31
45 x 15 x 28
45 x 15 x 35
45 x 15 x 29
45 x 15 x 30
45 x 15 x 30
45 x 15 x 45
                           V-13

-------
         Table V-6.  TABLE OF ABSORBER STANDARD SIZES FOR  THE  LIMESTONE PROCESS
Description
Flow rate @125°F, acfm
Flow rate @300°F, acfm
Nominal MW
Absorber
Length (A) , ft
Width (B) , ft
Height (C), ft
Absorber tank
Diameter (D), ft
Height (E), ft
Entrainment Separator
Height (F), ft
Hot duct
Dimension (G), ft
Reheater to Separator
Overall
dimensions (H), ft
Stack duct
Dimensions (J), ft
I .
300,000
455,000
150

39.0
15.0
45.0 '

44.0
20.0

15.0

12 x 11

30.0

14 x 13
II
250,000
325,000
110

28.0
15.0
45.0

37.0
20.0

15.0

10 x 9

25.0

12 x 10
III
150,000
195,000
65

17.0
15.0
45.0

29.0
20.0

15.0

7x8

20.0

10 x 8
IV
100,000
130,000
45

11.0
15.0
45.0

23.5
20.0

15.0

6x6

20.0

7x7
V
50,000
65,000
20

6.0
15.0
45.0

17.0
20.0

15.0

4x5

20.0

5x5
<
I

-------
Table V-7.  TABLE OF  VENTURI STANDARD SIZES FOR  THE  LIMESTONE PROCESS
Description
Flow rate @125°F, acfm
Flow rate @300°F, acfm
Nominal MW
Venturi
Length (K) , ft
Width (L) , ft
Height (M) , ft
Venturi tank
Diameter (N) , ft
Height (O) , ft
I
350,000
455,000
150

29.0
6. 5
20.0

15.5
15.0
II
250,000
325,000
110

22.5
6.0
20.0

13.0
15.0
III
150,000
195,000
65

15.0
5.5
20.0

10.0
15.0
IV
100,000
130,000
45

10.0
5.5
20.0

8.25
15.0
V
50,000
65,000
20

5.6
5.0
20.0

6.0
15.0

-------
                         II .
                        •fr"
FROM BOILER. TO STACK
—/•
 ;

 l
—\-
                                 PLAN VIEW
             TO  STACK

                     REHEATER
                                       ENTRAPMENT

                                        SEPARATOR
                                      ABSORBER
LOCATION OF VE
(IF APPLICABLE
SEE FIGURE
-*-A "G" (
1NTURI
)


\
FAN





1



FROM BOILER



<»B">

ABSORBER
TANK
«* —
" D " -rm
u *^
A
II r it
L, t

                               ELEVATION




       Figure  V-4a.   Plan  view  and  elevation of  an  absorber,



                                 V-16

-------
FROM BOILER




t
a





i
• i
•




II







i
I
i







i

^ " N "— ^
-rrn
/i "\
i i i
' , i : /
'AL, Jf




0 teu


                                                        TO SCRUBBER
                              PLAN VIEW
FROM BOILER
                                                         TO SCRUBBER
                               ELEVATION
     Figure V-4b.  Plan view and elevation of a venturi scrubber,
                                   V-17

-------
    •C"
I	

I
I
                    r'

              SIDE  VIEW
Figure V-4c.  Side view of an absorber,
                                                             I—~-~\
                                                             I    I
                                                        !K"
                                                           SIDE  VIEW
                                Figure V-4d.  Side view of a venturi

                                              scrubber.

-------
reheat AT of 50°F is used; this value is believed
to be about the minimum acceptable.  Obviously,
the lowest acceptable reheat AT should be chosen,
since each increase of 50°F of the flue gas
temperature requires about 1.5% of the gross heat
input to the plant.

In the indirect finned tubular heat exchanger
selected for the reheater, the first 33% of the
rows of tubes are constructed of Alloy 20 for
corrosion resistance to the gas, which enters at
its dew point.   The remaining 67% of the rows are
constructed of carbon steel.  Heating medium for
the unit is low-pressure saturated steam.  Pres-
sure drop through the reheater is calculated to be
about 4.0" H20.

Based on experience at Will County, a retractable
B&W type soot blower is used for each 25 ft2 of
scrubber exit duct cross-section for the heat
exchanger.  Half of the soot blowers are on the
entry side, the remainder on the exit side of the
heat exchanger.

Cost of reheat is based purely on an oil con-
version cost in Btu's.
                    V-19

-------
       APPENDIX W




ESP SUPPORT INFORMATION
          W-l

-------
                         APPENDIX W



                   ESP SUPPORT INFORMATION






     The design basis for the cost and installation of ESP's




was determined after review of process designs now in use



or proposed, and discussions with control system manufac-



turers.  A list of equipment required for installation of



an ESP is presented in Table W-l.  The critical path sched-



ule, Figure W-l, illustrates the time required for installa-



tion of various stages of an ESP.  Standard layouts for an




ESP are shown in Figure W-2.
                           W-2

-------
COMPANY
LOCATION  Electrostatic
          Precioitator
    Table W-l
  EQUIPMENT LIST

PEDCo-ENVIRONMENTAL
 Cincinnati,  Ohio
P.M. 	
CHECKED
BY
                     COMPUTED
                     BY
DATE
                                                                       DATE
ITEM
NO.





























DESCRIPTION
ESP
ESP and Vaninq
Transformer and Rectifier Sets
Rappers (wires and plates)

ASH HANDLING SYSTEM
Ash Hoppers
Flv Ash Pipe and Fittinqs
Fly Ash Valves
Seqreqatinq Valves
Ash Silo
Primary Collector
Secondary Collector
Vent Filter
Dustless Unloader
Exhauster
Vacuum Breaker

TRANSITION DUCTING
Ductinq
Valves








NO. OF
• ITEMS





























H.P/
ITEM





























TOTAL
H.P.


.


























COST/
ITEM





























TOTAL
COST





























                                          W-3

-------
                                                                                                PIOCURE  i EVALUATE Duenna
                                                                                                    {ASRICATIOII «IOS/'T7>
                                                                                                                                                                                 INSTAll ClCailCAI.
                                                                                                                                                                                   EOUIPMENT AW
                                                                                                                                                                                  COMPLETE UIRINC
•s,
 I
                                                                                                                              FIWlllE
                                                                                                                          DUCT INC CONTRACT
                                                                                                                                m
                                                                           PROCME | EVALUAT
                                                                                   D
                                                                           to   tuit\n
                                                  DCSIH I SPECIFY
                                                      I.D. FIN
                        FINAI.IK
                     1.0.  FAN OBOE
                                                                                                                              FABRICATt 1 OCUVEB 1.0. TABS
     PREPAJ1I
          COOBX
  f>LJU AM) COVI.I-
.  -	SCMDUl
I  > FQ« AGENCT
                                                FINAIIH
                                               ANS AHDSPC
                                                                                                FABRICATE « OEUVEI
                                                                                                                                                           PIPING COH.1iCTIOHS tSP-l
                                                                                                                                                                           INSTALL 1.0.
                                                                                                                                                                           FAN I CONNECT
                                                                                                                                                                              TS: ESP.J
                                                                                     FABRICATE I DELIVER
                                                                                       tSP-l m SITE
SECURE CIVIL
 CONTRACTOR
                                                                                                                       I RELATED iOUlPMEKT
                                                                                            EICAVATE 1 PREPARE
                                                                                             FOUNDATIONS FOR
                                                                                                  ESP-l
   PROCURE
 CONSTRUCT 1011
   MATERIAL
INSTALL I.D.
FAN I CONNECT               |
DUCTING ESP-2               i
                           PRCPAJU PUllMlllUT COIL
                          DRAMlies I Bill or MATERIAL
                                                                                                                                      4
                                                                                                                                      I

                                                                                                                                      IERECI CSP-Z
                                                                                                                                  1 RELATED EQUIPMENT
                                                                                    flCAVME » PREPARE <
                                                                                     FOUnOAT IONS FOR
                                                                                       EOUIFMEKT
                                                                                        «T       V«6I80
     WIE
  FOUNDATION
     DUGS. .

     0
                                DEBUG I
                               COKI SSI OH
                               fSP SYSTEM
SWITCH (M I
 EST SYSTE
                     ACTIVITY DESCRIPTION
                                                                                                                                                         HAKE ELECTRICAL
                                                                                                                                                            t PIPING
                                                                                                                                                          CONNECTIONS
                                                                                                                                                           FOR ESP-2  .
                                                                               EICAVATE I (RETIRE
                                                                              FOUNDATIONS FOR csr-t
                      IKOICATES OLM1T ACTI»ITT

                      INDICATtS dlTICM.
                                                              Figure   W-l.     ESP  Critical  Path   Schedule.

-------
s
ui
                             Figure W-2.   ESP  standard layout.

-------
                     APPENDIX X




COMPANY LETTERS TO THE FEDERAL ENERGY ADMINISTRATION
                           X-l

-------
              APPENDIX X-l ARTHUR KILL POWER PLANT


      Given for the purpose of completeness, the following

 information relative to the fuel conversion was supplied to

 the Federal Energy Administration by the Consolidated Edison

 Company:

      "The questions (on the FEA information request) were
      answered on the basis that any order to convert to coal
      firing would be on a non-emergency basis, and would be
      for the long term.  No allowance or consideration was
      made for an AQCS further than adequate precipitators.
      The cost figures used are estimates and should be used
      as order of magnitude numbers."

      Original Coal specifications for Boilers 20 and 30 are

 shown below:

                                    Boiler 20      Boiler 30

      HHV, Btu/lb                    13,600         13,600
      Ash, %                          7.2            7.2
      Volatite, %                    36.5           36.5
      Ash fusion temp.,°F          1900-2300        2100
      Moisture, %                     3.4            3.4
      Free carbon, %                 52.9           52.9
      Grindability                    63             63

      The anticipated acquistion or refurbishing of coal

 handling and firing equipment that would be required to

 reinstitute coal burning capability, and information rel-

 evant to the adequacy of storage facilities for coal are

 listed  below.  Costs and outage time are also provided.
ARTHUR KILL POWER PLANT                                    X-2

-------
SC
C
f
f
i
w
13
£
z
                 Item
       Arthur Kill
           Unit 20
1)    Install new precipitators
2)    Install new bottom ash
      system
3)    Install new fly ash system
      & storage facility
4)    Overhaul raw coal system
5)    Overhaul pulverizer system
6)    Overhaul burner equipment
7)    Check controls & checkout
      system
       Arthur Kill
           Unit 30
            1)   Install new precipitators
            2)   Convert bottom to coal
                  firing
            3)   Install new fly ash system
            4)   Overhaul raw coal system
            5)   Complete pulverizer over-
                  haul
            6)   Change boiler orifices to
                  coal firing
            7)   Change combustion & burner
                  control to coal firing
            8)   Checkout coal firing system
Estimated lead
imated
$
6,000,
750,
1,500,
300,
100,
100,
cost, time & construction
time, yr
000
000
000
000
000
000
2 -
1 -
2 -
1/6
1/2
1/2
2 1/2
1 1/2
2 1/2
- 1/2
- 1
- 1
Estimated
plant out
time , wk
2-3
2
None
None
None
2
                                                   25,000
                                    7,000,000

                                       75,000
                                  Incl. in Un.20
                                  Incl. in Un.20

                                       75,000

                                       20,000

                                       20,000
                                       10,000
    1/2
2-21/2

  2 Wks
2-2 1/2
1/6 - 1/2

  3 Wks

  2 Wks

  3 Wks
  1 Wk
                                                                                    1/2 -  1 yr

                                                                                       2
                                                                                     None
                                                                                     None

                                                                                     None

                                                                                       2

                                                                                       2
                                                                                       1/2
             "Coal  storage  (on ground) available, deliveries by  rail  only  no  river  edge
              loading or unloading available.
x
 i
U)

-------
     The differential operation and maintenance cost es-
timates are as follows:
                    Operation    Maintenance     Total
     Unit  20        $ 79,557     $ 61,084       $140,641
     Unit  30        $441,386     $294,465       $735,851
ARTHUR KILL POWER PLANT                                     X-4

-------
                 APPENDIX X-2 ASTORIA POWER PLANT


       Given for the purpose of  completeness,  the  following

  information relative to the fuel  conversion  was  supplied to

  the Federal energy Administration by  the  Consolidated Edison

  Company:

       "The questions (on the FEA information  request)  were
       answered on  the basis that any order to convert  to coal
       firing would be on a  non-emergency basis, and would be
       for  the long term.  No allowance or  consideration was
       made for an  AQCS further  than adequate  precipitators.
       The  cost figures used are estimates  and should be used
       as order of  magnitude numbers."

       Original coal specifications for Boilers 10  and  20, and

  for Boilers 30, 40, and 50 are shown  below:

                                Boilers 10-20   Boilers  30-50

       HHV,  Btu/lb                 13,253        13,600
       Ash,%                        8.0            7.2
       Volatile, %                  37.8           36.5
       Ash  fusion temp.,°F      1900-2300      1900-2300
       Moisture, %                   4.1            3.4
       Free carbon, %              50.1           52.9
       Grindability                64             63

       The  anticipated acquisition  or refurbishing  of coal

  handling  and firing equipment  that would  be  required  to

  reinstitute coal  burning capability,  and  information  rel-

  evant to  the adequacy of storage  facilities  for  coal  are

  listed below.  Costs and outage time  are  also provided.
ASTORIA POWER PLANT                                         X-5

-------
       The differential operation and maintenance cost estimates

  are as follows:

                      Operation      Maintenance    Total

       Units 10&20,$    231,578         293,230      524,808
       Units 30&40,$    154,334         195,487      349,821
       Unit 50,$       231,540         293,947      525,487
ASTORIA POWER PLANT                                         X-6

-------
en
i-3
O
po
O
3S
w
X
I
Astoria  Units 10 & 20

     1)   Install new precipitator
     2)   Install new bottom ash
           system
     3)   Restore fly ash system &
           silo
     4)   Overhaul raw coal system
     5)   Overhaul pulverizer system
     6)   Overhaul burner equipment
     7)   Overhaul/Checkout coal
           controls

         Unit 30

     1)   Install new precipitator
     2)   Install new bottom ash
           system
     3)   Restore fly ash system &
           silo
     4)   Overhaul raw coal system
     5)   Overhaul pulverizer
           system
     6)   Overhaul burner equipment
     7)   Overhaul/checkout coal
           controls

         Unit 40

     1)   Install new precipitator
     2)   Overhaul bottom ash
           system
     3)   Overhaul fly ash system
     4)   Overhaul raw coal system
     5)   Overhaul pulverizer
           system
     6)   Overhaul burners
     7)   Overhaul controls
4,






6,

Incl.
Incl.



6,

Incl.
Incl.



000,
750,
800,
500,
150,
100,
25,
000,
750,
in
in
150,
60,
50,
000,
50,
in
in
100,
100,
25,
000
000
000
000
000
000
000
000
000
Un. 10&20
Un. 10&20
000
000
000
000
000
Un. 10&20
Un. 10&20
000
000
000
2 -
1 -
1
1
1/2
1/2

2 -
1 -


1/2
1/2
1/2
2 -
1/3


1/2
1/2

2
1


-
—
1/2
2
1
1
1
_
—
-
2
—
1
1
—
-
1/2
1/2
1/2


1
1

1/2
1/2


1
1
1
1/2
1/2


1
1

                                                                                       2-3

                                                                                         2

                                                                                         2
                                                                                       None

                                                                                       None
                                                                                         4
2-3

  2
  2
None

None
3-5
  2
                 Unit 50 - Same as Unit  40

-------
          APPENDIX X-3   E.  F.  BARRETT POWER PLANT






     Given for the purpose of completeness,  the following



information relative to the fuel conversion was supplied to



the Federal Energy Administration by the Long Island Light-




ing Company:



1.  Maximum and Minimum Values



     These data reflect the range of each fuel character-



istic satisfactorily and reliably experienced in operation,



although it must be recognized not extremes of each char-



acteristic necessarily simultaneously.  The coal and ash



handling systems were designed for 13,000 Btu/lb. coal.  A



decrease in that level (usually as a function of increased



ash content) overloads both the coal unloading and coal



pulverizing systems reducing boiler capacity and/or re-



liability.  Increased ash content overloads the ash handling



systems, decreases precipitator efficiency, produces plume



opacity problems and  frequently requires load curtailment  to



empty ash  hoppers and associated transport piping.  As  an



additional consideration, ash disposal  areas on Long Island



are extremely  limited in  availability.  At the Barrett



Station resolution of environmental  (water) problems must  be
 E. F. BARRETT POWER PLANT                                  X-8

-------
accomplished before existing areas of limited capacity may

be used.

     Btu/lb.                                 - 13,000
     Ash, %, maximum                         - 10%
     Moisture, %, maximum                    - 5%
     Volatile matter, %                      - 26-39
     Grindability, Hardgrove, minimum        - 60
     Ash Characteristics

          Initial deformation, °F            - 1900°
          Ash softening, temp., °F           - 2100° min.
          Ash fusion, temp. °F               - 2250° min.

2.  Coal Transportation

     LILCO has great concern regarding the availability of

coal on a continuing reliable basis  ....  It is our

evaluation that significant revisions to our coal and ash

handling and dust collection equipment is required to place

this plant back on coal.

     We are concerned over the capacity of the coal piers in

the New York harbor to accommodate additional tonnage for

unloading into barges.  Of the three previous coal unloading

piers  (Penn-Central, Central Railroad of New Jersey, and the

Reading R.R.), only the Reading Pier is in operation.  The

financial condition of the other two railroads makes ques-

tionable their ability to restore their piers to an op-

erating status.

     Historic coal deliveries to the E. F. Barrett plant

have been by rail to the Jersey side of the Hudson River, at

which point, they were floated on barges to a terminal of
E. F. BARRETT POWER PLANT                                   X-9

-------
the Long Island Railroad (LIRR).   The LIRR will no longer




accept coal on car floats and will not use passenger rail-



road tunnels under the Hudson and Fast Rivers for transit to



Long Island proper.  Thus,  an all-rail route north to



Selkirk, New York, thence south over the Hell Gate Bridge to



Long Island, is necessitated.



3.  Acquisition and Refurbishment



     Phase I - Revisions and additional equipment required



               to provide reliable operating conditions,



               exclusive of plume opacity considerations.



           (1)  Conversion of boiler ash pit, burners and ash



               system from oil to coal firing.



               Lead time 2 weeks



           (2)  Dredge ash pond for required additional




               bottom ash capacity.



               Lead time 2 months



           (3)  Rebuild existing coal pile storage area,



               install impervious liner to prevent ground



               water contamination, and provide drainage to



               capture and treat runoff.



               Lead time 6 months



           (4)  Install dust control system at coal pile and



               railroad car unloading facility.



               Lead time 9 months



           (5)  Alter railroad track egress to LILCO property
 E. F.  BARRETT  POWER PLANT                                    X-10

-------
                from the Long Island Railroad (L.I.R.R.).



                The LIRR (Metropolitan Transportation Au-



                thority)  notified LILCO in 1974  that it will



                not deliver  coal  under existing  railroad



                track layouts,  except in limited delivery



                increments,  to  avoid blocking of Long Beach



                Road for passenger and commercial traffic  and



                emergency vehicles of the Village of Island



                Park.



                Lead time 9-12  months



           (6)   Rotary railroad car dumper complete  with pit,



                building,  tracks,  positioner,  etc.



                Lead time 2  years



           (7)   Installation of waste water treatment system



                for coal  firing.   This is necessary  for



                treatment of bottom ash waste water.



                Lead time 2  years



           (8)   Hydrobin  capacity  is required to handle high



                ash coal.  The  hydrobin is used  for  inter-



                mediate  storage of bottom ash and to decant



                out hydraulic ash  transfer medium.   The



                installation of a  hydrobin is anticipated  due



                to  environmental restrictions which  would



                prohibit  the hydraulic deposit of ash in



                previous  fields draining  into waterways.
E. F. BARRETT POWER PLANT                                   X-ll

-------
               Lead  time  2  years
          (9)   Installation of  dry  fly  ash  system,  ash silo
               and building,  equipment,  etc.
               Lead  time  2  years
                                   Phase I   Total
     Phase II  - Precipitators required  to meet efficiency
                of 98% or higher.
          (1)   New precipitator parallel to existing unit.
               Lead  time  3  years
     Phase III - S02 removal equipment  if required by EPA or
                 State.  (Present fuel  requirement is 0.37%
                 sulfur.)
          (1)   SO-  removal system.
               Lead  time  3 years (minimum)
4.   Power Plant Outage Time
     Upon receipt of notification,  conversion from oil to
coal firing with existing equipment can be accomplished with
a two week outage for each unit.   Such estimate is based on
converting to coal firing with original design conditions
and is exclusive of present day environmental standards.
5.   Lead Time
     The coal handling and stacking out equipment  is over-
hauled and capable of  stock-piling coal whenever it  is
received.  The ash system has been checked out and can be
operated.  However, a  minimum amount of ash can be removed
 E.  F.  BARRETT POWER PLANT                                   X~12

-------
before the ash field has to be dredged.  The boiler is in a



state of readiness such that it requires a two week shutdown



for actual boiler conversion work.  This would also be



sufficient time to develop the necessary coal inventory with



existing equipment.



     However, a lead time of up to two years to acquire or



refurbish the equipment discussed in Response Nos. 4 and 5



would be necessary.



6.   Local Laws



     State laws that have an effect on coal utilization are



Parts 700-703, Title 6, New York State Water Quality Stan-



dards and Part 201.9 of 6 NYCRR, air pollution control.



     In addition, Barrett is located in the Town of Hempstead



which has a noise code in Chapter 144.
E. F. BARRETT POWER PLANT                                   X-13

-------
             APPENDIX X-4  BERGEN POWER PLANT




      Given for the purpose  of completeness,  the following

 information relative to the fuel  conversion  was supplied to

 the Federal Energy Administration by the  Public Service

 Electric and Gas Company:

      1.    Original design  coal specifications:

      Bergen Nos. 1 & 2  Units

           Heating value       - 13,000 Btu/lb as received
           % Sulfur            -  3.0          as received
           % Ash               - 10.0          as received
           % Volatile matter   - 36.0          as received
           Grindability         - 60 Hardgrove
           Ash fusion temp.     - 2100 F

      Some variations in the original specifications could be

 tolerated if these variations are not too great.  Maximum

 and minimum limits for  the boilers are:

 Heating value       - 12,800 Btu/lb Mininum as received
 % Ash               - 11%            Maximum as received
 Volatile matter     - 22%            Minimum as received
 Grindability        - 55 Hardgrove  Minimum
 Ash fusion temp.    - 2300 F        Maximum
BERGEN POWER PLANT                                         X-14

-------
 2.   Coal Conversion Costs Are:

                COAL CONVERSION DATA AND
COSTS
 Data
      Capacity  (MW)
      Initial service  (year)
      Last burned coal  (year)
      Maximum lead time-material
        (weeks)
      Maximum lead time-conversion
        (weeks)
      Boiler outage required
        (week)

 Costs

      Coal handling equipment
      Pulverizers, burners, boilers
      Ash and dust disposal
      Pipeline penalty
      Outage replacement energy

      Total conversion costs

 Additional Annual Operating Costs

      Labor
      Material
      Ash and dust disposal

      Total additional annual
      operating costs
                                              Bergen
                                            Nos. 1 & 2
    280   283
   1959  1960
   1971  1971
       40

       52

     9     9
   $  588,500
      372,000
    2,298,500
    4,450,000
   $7,709,000
   $  407,000
      200,000
      652,000

   $1,259,000
BERGEN POWER PLANT
                   X-15

-------
                         COAL CONVERSION
                  EQUIPMENT COSTS AND LEAD TIME
                       NOS. 1 AND 2 UNITS
                    BERGEN GENERATING STATION
             PUBLIC SERVICE ELECTRIC AND GAS COMPANY
                              (1975)
       Equipment

  Coal Handling Equipment

    Redlers
    Coal  silos & vibrators
    Car thawing shed
    Car dumper
    Conveyors
    Bradford breaker
    Crushers
    Swing Boom & swing
      boom rest
    Transfer tower
    Miscellaneous
    Bulldozer
      Total
  Cost
$  200,000
    18,500
     8,500
    10,500
   124,500
    18,500
    20,500
     7,500

    14,000
    16,000
   150,000
$  588,000
   Pulverizers,  Burners,  Boilers

     Combustion  control         $     2,000
     Feeder  tables  &  assoc.         36,000
      equipment
     Pulverizer  mills              64,500
     Coal burning air syst.         20,500
     Boiler  tubing                 110,000
     Sootblowers                  125,500
     Air heaters                    8,500
     Boiler  penthouse'              5,000
      pressurizing  fans            	
       Total
$  372,000
   Ash and Dust Disposal

     Dust transport
      system
     Ash sluice system
     Slag system
     Rebuild ash pond and
      Water treatment
       Total
$   29,500

    27,000
    42,000
 2,200,000

$2,298,000
Conversion
lead time
 (weeks)
    45
    21
     7
    28
    42
    34
    12
    28

    16
     6
    10
                     27
                     33

                     44
                     11
                     24
                     32
                     16
                     10
    30

    30
    48
    52
BERGEN POWER PLANT
                                                            X-16

-------
                  APPENDIX  X-5  CROMBY  POWER PLANT


       Given  for  the  purpose of  completeness,  the  following

  information relative  to  the fuel  conversion was  supplied to

  the  Federal Energy  Administration by  the  Philadelphia  Elec-

  tric Company:


       "1.  Original  specification  coal characteristics,  as
           fired, for  Cromby Unit  No.  2.

           Btu/lb                              13,700
           Sulfur, %                           1.5
           Ash,  %                               7.0
           Volatile, %                          26.0
           Ash fusion  temp.  - Softening        2590°F
                              Liquid            2670°F

       2.  Range of  characteristics compatible  with design
           tolerance.

                                         Maximum    Minimum

           Btu/lb                            -        13,100
           Sulfur, %                          3          1.5
           Ash,  %                            10           -
           Volatile, %                       40           24
           Ash fusion temp.  - Softening     -         2,500
                              Liquid         -         2,600

       3.  Coal and  Transportation Information

           (a)  Availability of coal and transportation

           Based on  the quality of coal received  in 1974,  the
           additional coal required for Cromby  No. 2 would be
           difficult to obtain and meet the specifications of
           the equipment.  New mines would have to be opened
CROMBY POWER PLANT                                        X-17

-------
           with cleaning equipment to produce the quality
           required.  Locomotive power and roadbed  should be
           adequate; car availability could be  inadequate.

            (b)  Transportation Companies

           Penn Central Railroad and lateral lines
           Baltimore and Ohio Railroad and lateral  lines
           Western Maryland  Railroad
           Reading Company

            (c)  Estimated Increased Coal Consumption

           Approximately 540,000 tons/year for  next five
           years.

           Equipment refurbishing required and  estimated
           labor  and material cost.

            (a)  Inspect coal burners and repair as  required.
                Inspect and  repair mills as required.   Labor
                and material estimate is $10,000.

            (b)  Clean and inspect the ash handling  system.
                Inspect electrostatic precipitator  and re-
                place wiring as  required.  Install  hopper
                unloading rotary valves.  Labor and material
                estimate is  $15,000.

            (c)  Replace tube shields on  superheater tubes.
                Labor and material estimate is  $20,000.

            (d)  Clean and inspect combustion control  for
                coal-firing. Repair as  required and  adjust.
                Labor and material estimate is  $5,000.

            (e)  The increased operations and maintenance cost
                for coal firing  is estimated to be  O.OSC/kWh.

            Estimated Outage  Time Required

            Two weeks

            Estimated Lead Time  Required

            Approximately one month to obtain material, plan
            outage,  and  schedule  manpower.  Coal inventory  is
            already  on hand  for  coal  firing of  Unit  No. 1.
CROMBY POWER PLANT                                         X-18

-------
            Cromby  Unit No.  2  is  expected  to  retire  in  the
            early 1990's.   However,  this date will be subject
            to  review  as  the date approaches.   Final retire-
            ment date  will  be  determined by the in-service
            dates of new  capacity additions and the  system
            capacity requirements at the time.

        7.   State or Local  Laws or Policies

            Excluding  air pollution controls, no other  limi-
            tations are known."
CROMBY POWER PLANT                                          X-19

-------
           APPENDIX X-6  HOWARD  M.  DOWN  POWER PLANT


      Given for the purpose  of completeness,  the  following

 information relative to the fuel  conversion  was  supplied to

 the Federal Energy Administration by the City of Vineland

 Electric Utility:

      "Original Coal Specifications

      Last contract - 1972:

           % Moisture                         3-5 maximum
           % Volatile                    22 to 37 maximum
           % Asn                              8.5 maximum
           % Sulfur                           1-° maximum
           BTU/lb                          14,000 minimum
           Ash Fusion - Temp. °F            2,550 minimum
           % Fe2 03 in Ash                     15 maximum
           Grindability  (Hardgrove Index)      85 maximum
           Burning characteristics  Light to medium caking


      "Maximum and Minimum Values of Coal

      Unit No. 10  (Pulverizers)

           % Moisture                    2.5 - 10
           % Volatile                     20 - 40
           % Fixed Carbon                 40 - 70
           % Sulfur                        1-3.5
           % Hydrogen
           % Oxygen
           % Ash                         6.5 - 15
           Heat Value -  as  fired -
            BTU/lb                    12,000 - 14,000
           Ash Softening Temp.  °F       2,000 - 2,500
           Grindability, Hardgrove        45-80
HOWARD M. DOWN POWER PLANT                                  X-20

-------
            "The most recent purchases of coal were  from the
       Island  Creek Coal  Sales Company of West Virginia and
       the  Crown Coal and Coke Company of Pennsylvania.

            "Coal must be available under contract consistent
       with the public bidding laws of the  State  of  New Jersey.
       The  Central Railroad  (CRR) of  New Jersey branch, to
       Bridgeton, must be maintained  in good  condition to
       provide a reliable supply  route.

            "Coal is delivered to the Down  Station by the CRR
       of New  Jersey.  They would receive the cars from var-
       ious connecting railroads  according  to the point of
       origin.

            "Estimated Annual Coal Consumption Unit  10:
       80,000  tons.

            "The Down Station coal-handling and ash-handling
       systems are operable and in satisfactory condition.
       The  firing equipment on the No. 10 unit is operable.
       Storage facilities will accommodate  approximately ten
       (10)  days supply of coal.

            "Actual conversion of Unit No.  10 involves very
       minimal cost.  It  will be  necessary  to stock  replace-
       ment parts for pulverizers and associated  equipment.
       This may require a ten thousand dollar ($10,000) in-
       vestment.

            "Unit No. 10  can be converted to  coal-firing with
       a few hours of partial outage.

            "Coal handling facilities can be  changed from
       standby to operational status  in about one (1) week.
       If coal were obtained initially on a spot  purchase
       basis,  it would probably require two (2) months or more
       to build an adequate coal  inventory.

            "No laws or policies  other than the Air  Pollution
       Control limit the  utilization  of coal  in the  Down
       Station."
HOWARD M. DOWN POWER PLANT                                  X-21

-------
               APPENDIX  X-7   FOX  LAKE POWER PLANT


       Given  for  the  purpose  of  completeness, the  following

  information relative  to the fuel  conversion was  supplied

  to  the  Federal  Energy Administration by  the Interstate

  Power Company:

      Coal  Specifications Compatible with  Design Tolerances

Btu/lb
Sultur
Ash
Volatile Matter
Ash Fusion Temp.
Maximum
12,000
-
12.0%
40.0%
2200°F
Minimum
8,000
0.5%
-
25.0%
1900°F
       "The main coal supplier is Westmoreland Resources,
  Sarpy Creek,  Montana.   No coal or transportation difficulties
  are encountered.   BN and CMSTP & P railroads are the prin-
  cipal transportation companies.

       "Based on 100% maximum capacity coal burning,  coal
  consumption would average 140,000 tons/yr based on 8,450 Btu/lb
  coal.

       "Additional  equipment  (i.e. bunkers, feeders,  pulveri-
  vers, burners, piping, soot blower, and controls) would  have
  to be purchased to attain 100% capacity on coal at a cost
  of $1,500,000.

       "Existing coal storage will handle 75,000 tons which
  should be adequate.

       "An estimated outage time of one month and a lead time
  of eighteen months is needed to attain 100% coal burning
  capacity.

       "No existing state or local laws other than air pollu-
  tion control laws would limit utilization of coal.
FOX LAKE POWER PLANT                                      X-22

-------
              APPENDIX X-9   HUDSON POWER PLANT
       Given for the purpose of completeness,  the following

  information relative to the fuel conversion was supplied to the

  Federal Energy Administration by the Public Service Electric and

  Gas Company:

  1.  Original Design Coal Specifications:

  Hudson No. 1 Unit:
       Heating value
       % Sulfur
       % Ash
       % Volatile matter
       Grindability
       Ash fusion temp.
- 13,000 Btu/lb as received
-3.0          as received
- 10.0          as received
- 36.0          as received
- 55 Hardgrove
- 2100 F
       Some variations in the original specifications could be

  tolerated if these variations are not too great.  Maximum and

  minimum limits for the boiler is:
       Heating value
       % Ash
       % Volatile matter
       Grindability
       Ash fusion temp.
- 12,800 Btu/lb Minimum as received
- 11%           Maximum as received
- 22%           Minimum as received
- 55 Hardgrove  Minimum
- 2300 F        Maximum
HUDSON POWER PLANT
                                 X-23

-------
2.   Coal Conversion Costs Are:

               COAL CONVERSION DATA AND COSTS
Data
     Capacity (MW)
     Initial service (year)
     Last burned coal (year)
     Maximum lead time-material (weeks)
     Maximum lead time-conversion (weeks)
     Boiler outage required (weeks)

Costs

     Coal handling equipment
     Pulverizers, burners, boilers
     Ash and dust disposal
     Pipeline penalty
     Outage replacement energy

     Total conversion costs

Additional Annual Operating Costs

     Labor
     Material
     Ash and dust disposal
                                                  Hudson
                                                  No. 1
     383
    1964
    1970
      40
      52
       8
$ 3,833,500
    451,000
  4,868,000
  3,350,000
$12,532,500
    721,500
    360,000
    452,000
     Total additional annual operating costs    $ 1,533,500
HUDSON POWER PLANT
                                                            X-24

-------
                         COAL  CONVERSION
                  EQUIPMENT  COSTS  AND  LEAD  TIME
                          NO.  1 UNIT
                   HUDSON GENERATING STATION
             PUBLIC SERVICE  ELECTRIC AND  GAS  COMPANY
                             (1975)
       Equipment

  Coal Handling  Equipment

    Modify coal  handling
     system
    Silo level controls
    Crushers
    Bulldozer
      Total

  Feeders, Burners,  Boiler

    Combustion control
    Fuel detectors
    Gravimetric  feeder
    Coal conduits
    Coal inlet gates
    Cyclone wear blocks
    Auxiliary cooling
    Water jacket
    Sandblast cyclones
    Restud cyclones
    Cyclone slag tags
    Gunnite cyclones
    Air dampers
    Reheater shields
    Deslag furnace
    Floor
    Slag tap
    Cinder trap
    Sootblowers
    Combustion control
      Total

  Ash and Dust Disposal

    Dust transport system
    Ash sluice system
    Slag system
    Rebuild ash pond & water
     treatment
      Total
  Cost
$3,640,000

    21,500
    22,000
   150,000
$3,833,500
     5,500
     3,000
    26,500
    33,000
     8,500
    24,000
     5,000
     8,500
     6,500
   126,000
    17,000
     9,000
    12,500
    22,500
     1,000
    78,500
     1,500
     2,000
    60,500
     5,500
$  451,000
$  100,000
    69,000
    99,000
 4,868,000

$4,868,000
Conversion
lead time
  (weeks)
    52

    12
    12
     3
    41
    31
    29
     4
    17
     2
     4
     2
    18
     4
     2
     3
     7
     2
    18
     1
     1
    24
     3
     32
     29
     32
     52
HUDSON POWER PLANT
                              X-25

-------
          APPENDIX X-9    JONES STREET POWER PLANT


     Given for the purpose of completeness, the following

information relative to the fuel conversion was supplied to

the Federal Energy Administration by the Omaha Public Power

District Company:

     Boiler #27 at the Jones Street Power Station was con-
verted from coal to oil/gas in 1972.  This was done because
the station could not meet air quality standards and the
cost to install air quality control equipment was prohibi-
tive vis-a-vis the age, available space, and worth of the
plant.  Furthermore, it was agreed that no additional vari-
ances would be requested beyond June 1, 1973.

     In connection with this conversion, two 1,000,000-
gallon oil tanks were installed in 1972, and two more
 (1,600,000-gallon and 1,300,000-gallon) were installed in
1973.  These tanks were all placed in the old coal handling
area, and also serve the two gas turbines installed on the
Station.  Since that time, much of the coal conveying and
other coal handling equipment has been removed and disposed
of.

     The Omaha Public Power District is presently an "inter-
ruptible customer" of Northern Natural Gas Company and has
been for several years.  The District has been informed by
Northern Natural Gas that 1976 will be the last year that
gas will be available to fire boilers.

     The Jones Street Power Station now consists of two old
boilers and turbines and is used for peaking operations only
as  is evidenced by the following 1974 data:
JONES STREET POWER PLANT                                   X-26

-------
                               BOILER #26          BOILER #27

 Year Built                       1949                1951
 Net Capacity                     36 MW               47 MW
 Hours of Operation               856                 920
      % of Year                   9.8%                10.5%
 Capacity Factor                  7.9%                7.4%

 Total Oil Consumed            109,986 gallons (both boilers)
 Total Gas Consumed            696,000 MCF (both boilers)

 1977 Projections:
      Total Oil                760,000 gallons #2 oil (18,095 bbls)
      Total Gas                          NONE

      To convert one of these two boilers, or both, back to
 coal at this stage of plant life is not only economically
 infeasible, it borders on the impossible due to the considera-
 tions enumerated below.

 1.    Because of the age and efficiency of the boilers,  air
      quality standards, including particulate limits, could
      not be met without the addition of air quality control
      equipment.  This equipment would have to be installed
      in the former coal storage area, now occupied by fuel
      storage tanks.  This would necessitate the relocation
      of the fuel storage tanks and the establishment of a
      new coal storage area.

 2.    There are no ash settling ponds or similar facilities
      at the site.  With no means of handling coal pile
      runoff or sluicing water used in the ash handling
      system, water quality standards could not be met.

 3.    The Jones Street Power Station is located on the
      Missouri River in downtown Omaha and is surrounded by
      other commercial facilities.  The size of the site is
      approximately 16 acres.  With no room to expand, the
      addition of any major facility, such as a new fuel oil
      storage area, coal storage area, or ash settling pond
      £B not possible.

 4.    The deteriorated condition of the remaining coal and
      ash handling equipment, and the need to rebuild large
      segments of major coal handling systems already removed
      would be costly and uneconomical.
JONES STREET POWER PLANT                                    X-27

-------
     In conclusion,  should the Omaha Public Power District
be directed to convert the Jones Street Station to coal,
serious consideration would have to be given to decommission-
ing the plant rather than embarking on a costly, uneconomical
conversion.

     Boiler No. 27 was designed to burn Kansas Bituminous
coal from the mines near Pittsburg, Kansas.  The character-
istics are as listed below.

     Kind - Kansas Coal, Bituminous
     Grindability - 55
     Surface Moisture, % - 6
     BTU/LB - 11,380
     Sulphur, % - 5.24
     Ash, % - 16.70
     Volatile Matter, % - 33.70
     Ash Temperature, °F
          Init. Def. - 1894
          Liquid - 1955
     Slagging Index, R_ - 2.96 (Severe slagging coal)
     Fouling Index,  Rp - 0.74  (High fouling coal)

     The sintering characteristics of the coal have not been
determined as such.

     Boiler No. 27 has not burned other types of coal to any
extent.  However, it is felt that Hanna, Wyoming coal could
be burned with some reduction in capacity.  Kansas coal is
no longer available and to determine the feasibility of
burning other types of coal would require a detailed engi-
neering study which has not been done.  Hanna, Wyoming coal
is available at the present time and the characteristics are
listed below.

Kind - Wyoming, Sub-bituminous

                         Max.                Min.

Grindability             N.A.                N.A.
Moisture, %              13.8                12.0
BTU/LB                   10,800              10,000
Sulphur, %               0.95                0.75
Ash, %                   13.8                5.3
Volatile Matter, %       N.A.                N.A.
Ash Temperature, °F
     Init. Def.          N.A.                N.A.
     Liquid              N.A.                N.A.
N.A. - Not Available
JONES STREET POWER PLANT                                    X-28

-------
     In order for the Omaha Public Power District to be
capable of burning coal in their Jones Street Station Boiler
#27, it would be necessary to purchase and install,  modify,
or repair the following items:

1.   Coal Handling System
     	2—*	                              Cost

     A.   Purchase Locomotive to move coal           $100,000
     B.   Purchase coal handling scraper              125,000
     C.   Install R.R. trackage over coal              75,000
          scale, track hopper, repair remainder
          of RR track
     D.   Purchase and install track scale            100,000
          and scale house
     E.   Purchase and install shaker house            60,000
          and shaker car
     F.   Purchase and install coal pit,              100,000
          vibrating screens, coal conveyor
          or vert, lift
     G.   Purchase and install stocking-out           200,000
          conveyor system
     H.   Purchase and install vertical coal           20,000
          lift basement to transfer belt
           (w/some salvage material)
     I.   Purchase and install transfer belt,          30,000
          coal sampling and weighing system
     J.   Purchase and install horizontal              20,000
          drag conveyor above bunker
     K.   Purchase and install 480 volt motor          25,000
          control center and wiring for coal
          handling
     L.   Rework offices because of interference        3,000
          with coal conveyor
                                             Cost    $858,000

 2.   Storage Facilities for Coal
     	                                            Cost

     A.    Purchase land and provide diking           $125,000
           for control of surface water run-off
     B.    Process system for run-off water             10,OOP

                                             Cost    $135,000
JONES STREET POWER PLANT                                     X-29

-------
 3.   Ash and Dust Handling System
                                                       Cost

     A.   Purchase and install ash hydrobin,        $701,000
          recir. system, ash piping, and
          ash unloading equipment
     B.   Purchase and install dry fly ash           105,000
          silo, dustless unloader, and dry
          unloader
     C.   Purchase and install dry fly ash           114,000
          pneumatic conveyor system
     D.   Purchase dump truck                         10,000

                                             Cost   $930,000

 4.   Additions and Modification to Boiler No. 27 to Burn
     Coal
                                                       COst

     A.   Purchase and install 480 volt motor       $ 20,000
          control center for equipment motors
     B.   Purchase and install new coal burners       30,000
          and coal burner piping
     C.   Purchase and install new controls           60,000
          for coal burning on boiler gauge
          board and field installed panels
     D.   Modify burner deck oil burning              15,000
          management control system
     E.   Relocate oil piping, controls, etc.,         5,000
          on burner front to accommodate new
          coal burners                              	i

                                             Cost   $130,000

 5.   Maintenance of Existing Coal Burning Related Equipment

                                                       Cost

     A.   Repair sluice water pumps and replace     $ 12,000
          piping
     B.   Repair ash removal pumps, etc.               5,000
     C.   Repair boiler ash hopper                     5,000
     D.   Repair clinker grinder                       3,000
     E.   Overhaul coal pulverizers,  etc.               5,000
     F.   Repair soot blowers,  soot blower             2,000
          steam piping and valves
                                             COSt   $ 32,000
JONES STREET POWER PLANT                                  X-30

-------
 6.   Storage Facilities  for Coal

     Since  the  District  has used  its  former  coal  storage
 area for  the installation of  two  (2)  oil  fired  gas  turbines,
 and four  (4) large  (2  -  1,000,000,  1  -  1,600,000, and  1 -
 1,300,000 gal.  each) oil storage  tanks  that  area  is no
 longer  available.   In  order to  store  coal at the  Jones
 Street  Power Station,  additional  land would  have  to be
 purchased,  cleared  and necessary  diking constructed to
 contain surface water  run-off from  the  coal  pile.

     The  costs  associated to  restore  coal firing  capability
 are as  follows:

     1.   Coal  Handling  System                     $  858,000
     2.   Storage Facilities  for  Coal                135,000
     3.   Ash and Dust Handling System                930,000
     4.   Additions and  Modifications                130,000
          to Boiler #27  to  Burn Coal
     5.   Maintenance  of Existing Coal                 32,000
          Burning related equipment               	

          Subtotal                                 $2,085,000

     6.  Engineering  Costs  (15%  of #l-#5)           312,750
     7.  Overhead  and Interest (15%  of #l-#6)        359,660

          TOTAL RESTORATION COSTS                 $2,757,410

     The  estimate of operating  and  maintenance cost differential
 per  year  associated with the  necessary  changes are as follows:

      1.  Maintenance  cost  differential/year      $25,000
      2.  Operational  cost  differential/year      $60,000
JONES STREET POWER PLANT                                     X-31

-------
               APPENDIX X-10  LOVETT POWER PLANT
     Given for the purpose of completeness, the following

information relative to the fuel conversion was supplied to

the Federal Energy Administration  (FEA) by the Orange and

Rockland Utilities:

     1)   Maximum and Minimum values for types of coal
          compatible with boilers' design tolerances.
          Btu/lb.

          % Sulfur

          % Ash

          % Volatile matter

          Ash  softening  temp.
           Btu/lb

           %  Sulfur

           %  Ash

           %  Volatile  matter

           Ash softening temp.
                                        Lovett  #4
 Min.

12,000

  0

  0

 30.0

2,150°F
 Max.



 4.0

15.0
                                         Lovett  #5
 Min.

12,000

  0

  0

 30.0

2,335°F
 Max.



 4.0

15.0
LOVETT POWER PLANT
                        X-32

-------
      2)    Anticipated acquisition or refurbishing of ash
           handling facilities and costs in 1975 dollars.

           Water Quality

           Ash settling pond refurbish and waste treatment
           facilities                            $1,900,000

           Environmental Noise

           Sound-proof coal car Shaker Building  $  120,000
      3)    Lead time to restore coal firing capability:

           Settling pond and waste treatment - 1 1/2 years
           Sound proof coal car shaker building - 1 year

           a.    Lead time is not necessary for initial oper-
                ation if variance is granted for noise and
                water quality standards.
      4)    Projected capacity factors:

      Capacity factors -        Unit No.  4      Unit No.  5

      1974  actual          909,252  MWH output 1,125,871  MWH output
                            187 MW x 8,760      202 MW x 8.760
                              = 0.56             = 0.64

      1975                       0.46               0.37

      1976                       0.43               0.30

      1977                       0.47               0.35

      1978                       0.50               0.39

      1979                       0.55               0.45
LOVETT POWER PLANT                                          X-33

-------
                APPENDIX X-1T    MUSTANG  POWER PLANT


       Given for the purpose of completeness, the  following

  information relative to the fuel conversion was  supplied

  to the Federal Energy Administration by the Oklahoma Gas

  and Electric Company:

       "We have not purchased coal for the plant since 1963
  when we bought 100 tons.  The last purchase prior to that
  Was in 1954.  Past supplier's were Beribow Coal Company
  (1963) and Leavell Coal Company  (1954).

       "This plant can be supplied only by rail.   The only
  carriers possible are the Chicago, Rock Island arid Pacific:
  railroads.

       "We had in 1973 only 1100 tons of coal in stdrage
  (1.7 burn days) and the maximum amount of coal we have
  ever had is 5900 tons or 3.9 burn days.  The maximum
  storage capacity is 7800 tons for 5.3 burn days  at present
  capacity factor of 33%.

       "In short, the plant was designed and built to burn
  coal on an emergency  stahd-by basis and has been operated
  in that manner.

                  Original Coal Specifications

               Btu/lb                 11,020
               % Sulfur               1.1
               % Ash                  16.4
               % Volatile Matter      30.2
               % Moisture             5.5
               Ash Fusion Temp.       1900-2000°F

       "At present rates, the fuel cost will double on this
  unit if coal is burned.  The estimated cost for  equipment
  is $7,900,055, for operations and maintenance $731,000
  per year, excluding the fuel.
MUSTANG POWER PLANT                                        X-34

-------
          APPENDIX X-12  POSSUM POINT POWER PLANT



     Given for the purpose of completeness,  the following

information relative to the fuel conversion was supplied to

the Federal Energy Administration by Virginia Electric and

Power Company:

     The minimum and maximum values of coal compatible with
     Vepco power plants design tolerances are as follows:

               Btu/lb              11,300* - 14,000
               Percent Sulfur          0.5 - 4.0
               Percent Ash             2.5 - 20
               Percent Volatile         15 - 34
                matter
               Ash Fusion Tempera-   2,300 - 2,900
                ture (F)

     * If Btu/lb is below 11,800 and Hardgrove Grindability
       is less than 75, there is a possibility of reduction
       in capability because of mill capacity.

     Below are listed the work required, on Boilers 2 through

4 at Possum Point power plant, to convert to coal firing.

These are estimates and after inspection of the boilers and

associated coal auxiliaries additional work may be required

at additional cost, time, and effort.

Boiler

     Burner corner repair  (buckets, dampers)
     Relocation of side igniters and oil guns
     Replace cold end elements on air preheaters
     Repair IR-soot blowers
     Remove refractory from furnace walls
POSSUM POINT POWER PLANT                                    X-35

-------
     Change-out orifices in lower drums
     Recalibration of boiler controls
     Repairs to electrostatic precipitators

Coal Handling System

     Inspection and repair of coal feeders and mills

Ash Handling System

     Reinstall dry fly ash handling system
     Bottom ash pond is no longer available due to construc-
      tion of Unit 5.  A small retention pond will have to
      be constructed to handle bottom ash until a permanent
      pumping system to the fly ash ponds can be constructed.

Coal Storage Equipment

     Repair railroad tracks and install 1,500 feet of new
      track
     Repair coal  unloading equipment  (car shaker, feeders,
      crusher, conveyors and scales)
     Obtain locomotive and tractor

     The estimated cost to restore coal firing capability

 for Possum Point  is as follows:

          Possum  Point 2                $  35,000

          Possum  Point 3                $  55,000

          Possum  Point 4                $  88,000

          Coal  Handling Equipment       $179,000

          Temporary Bottom Ash Pond     $220,000

          Total  - Possum  Point 2-4      $577,000

      The estimated annual  increase due  to  conversion to

 coal  firing  using 1975  Estimated  Annual Expenses  would  be:
POSSUM POINT POWER PLANT                                    X-36

-------
 Possum Point
      Operation                     $  45,000

      Coal Handling                 $150,000

      Maintenance                   $190,000
      Total - Possum Point 2-4       $405,000

      "The estimated outage time required to  make necessary
      changes and convert the units  to  coal firing,  if  no
      major problems are encountered or if work beyond  that
      envisioned has to be done because of inspection findings."

           Possum Point 2           3 weeks

           Possum Point 3           3 weeks

           Possum Point 4           4 weeks
      Total time required for Possum Point -  10  weeks
POSSUM POINT POWER PLANT                                    X-37

-------
              APPENDIX X-13  RAVENSWOOD POWER PLANT

      Given for the purpose of completeness, the following

 information relative to the fuel conversion was supplied to

 the Federal Energy Administration by the Consolidated Edison

 Company:

      "The questions  (on the FEA information request) were
      answered on the basis that any order to convert to coal
      firing would be on a non-emergency basis, and would be
      for the long term.  No allowance or consideration was
      made for an AQCS further than adequate precipitators.
      The cost figures used are estimates and should be used
      as order of magnitude numbers."

      Original coal specifications for Boiler 30 is shown

 below:

                                         Boiler 30

      HHV, Btu/lb                         14,080
      Ash,%                                 7-2
      Volatile,  %                         36-5
      Ash fusion temp.,°F                1900-2300
      Moisture,  %                           3-4
      Free Carbon,%                       52.9
      Grindability                          63
RAVENSWOOD POWER PLANT                                     X-38

-------
 I
 M
 o
 a
o
s:
M
Ravenswood Unit 30 North

  1) Overhaul & remove precipitator
      blanks
  2) Overhaul bottom ash system
  3) Restore fly ash system & silo
  4) Overhaul raw coal system
  5) Overhaul pulverizers & burners
  6) Overhaul controls

Unit 30 South

  1) Repair precipitator
  2) Same as Unit 30 N
  3) Same as Unit 30 N
  4) Same as Unit 30 N
  5) Same as Unit 30 N &
      repair damaged ductwork
  6) Same as Unit 30 N
                                      Estimated cost,
                                           $
 20,000

 25,000
300,000
100,000
100,000
 20,000
                                              2,200,000
                                             Incl.  in Un. 30 N
                                             Incl.  in Un. 30 N
                                             Incl.  in Un. 30 N
                                                175,000

                                             Incl.  in Un. 30 N
                   Estimated
                   lead time
                 & construction
                     time
   3 wk.

  4-6 mo.
  4-6 mo.
  4-6 mo.
1/2 - 1 yr,
   1 mo.
                      4 mo.
                   1/2 - 1 yr
                 Estimated
                 Plant out
                   time
1 wk.

1 wk.
1 wk.
None
3 wk.
1 wk.
                    1 wk.
                    None
x
i
u>
VO

-------
       "No coal  storage  (on ground).  All coal deliveries by



 barge, direct  to bunkers.  No bottom ash or fly ash disposal




 on  site.



       The differential  operation and maintenance cost es-




 timates are as follows:



                     Operation      Maintenance      Total



 Unit  30, $           299,059         277,863       576,922
RAVENSWOOD POWER PLANT                                      X-40

-------
            APPENDIX X-14   RIDGELAND POWER PLANT




      Given for the purpose of completeness, the following

 information relative to the fuel conversion was supplied to

 the Federal Energy Administration  by the Commonwealth

 Edison Company:

       (1)  Original specification coal for Ridgeland based on
           Illinois Seam 6 coal is  analyzed as  follows:

                Moisture,  %          15.00
                Ash, %               15.00
                Carbon, %            52.00
                Hydrogen,  %          3.85
                Sulfur, %            4.65
                Oxygen, %            8.70
                Nitrogen,  %          0.80
                Btu/lb               10,000
                Ash fusion temp.     2,000

           "Performance estimates and criteria  shall be based
           on the coal specified above.  The entire steam
           generating and  coal burning equipment, however,
           shall be able to develop the maximum capacity and
           operating efficiency with other Illinois, Indiana,
           and Kentucky coals having heating values between
           10,000 and 12,500 Btu/lb; ash fusion temperatures
           varying between 1950°F and 2300°F and moisture up
           to 15%."

       (2)  Range of characteristics compatible  with design
           tolerance:

                                     Maximum   Minimum

           Btu/lb                               10,000
           Ash, %                     15         -
           Sulfur,  %                   4.5       -
           Ash sintering strength,   5,000
            psi
           Ash fusion temperature    2,250
RIDGELAND POWER PLANT                                       X-41

-------
       (3)  Identification of facilities to be acquired or
           refurbished:

                Equipment/facilities               Cost, $

           Coal unloading equipment - west dock    456,000
                                    - east dock    100,300

           Coal moving equipment                    10,000

           Conveyor belt junction hoppers,          81,000
            gates, and belt system

           Breaker house                            49,000

           Ash and slag handling                    45,000

           Boilers 1 through 6 - refitting         149,200
            required for coal firing

           Boiler instrument and controls             6,000

           Ash handling systems                    7,000,000

           Coal and ash pile water runoff          3,300,000
            control

           Air heater and boiler fire side wash    2,500,000
            water control facilities

           Misc. drain collection, discharge,      1,700,000
            and control facilities

           Total cost of anticipated acquisi-     15,396,500
            tion refurbishing of facilities

       (4)  Total increase in annual operating and maintenance
           construction is  estimated at  $2,900,000.

          - Other Considerations

           Increased boiler maintenance  can  be expected  with
           coal-firing due  to more rapid cyclone  tube wear
           and due to increased  superheater  wastage and
           failure because  of higher furnace temperatures.
           This will result in more frequent Scheduled and
           Emergency outages.  Availability  would be  expected
           to drop about 6%.
RIDGELAND POWER PLANT                                       X-42

-------
            Superheater tube replacement is an unkown factor.
            We can expect that the more frequent failures will
            require replacement of sections of tube banks
            within a couple of years of conversion.

              Boilers 1-4 might spend up to $150,000 each.
              Boilers 5 and 6 might spend up to $300,000 each.

            Manpower problems will include, in addition to
            hiring of the 24 men for coal plant and operating:

            a)   Training of these new men for skilled and
                 unskilled positions.  Former coal plant
                 people have left Ridgeland.  Most of those
                 remaining at the Station are in other classi-
                 fications and will not desire returning to
                 coal plant work even (as some have indicated)
                 if a promotion is involved.

            b)   Selecting two men as supervisors for the coal
                 plant.  We may have to go outside the station
                 and train them to handle our equipment.

            c)   Possible loss to retirement of operating
                 people due to the harder work which can be
                 encountered in handling wet coal, slag and
                 ash problems, both at the furnace tap or slag
                 tank and dust hoppers, and control problems
                 due to tripouts and difficulty of lighting
                 off the cyclone burners particularly on a
                 cold boiler.  For maintenance and more
                 frequent outages resulting in harder, dirtier
                 work, callouts and longer hours.

                 We have two Shift Engineers who have requested
                 retirement at age 58 in 1975.

                 The number and ages of supervisors and
                 employees of concern are:

                 Supervisors

                 Total                         33
                 No. at age 58 or 59            3
                 No. at age 60 to 64            4
RIDGELAND POWER PLANT                                         X-43

-------
                Employees

                Total                        179

                  Skilled
                    No. at age 58 or 59       13
                    No. at age 60 to 64       16
                  Semi-Skilled
                    No. at age 58 or 59        4
                    No. at age 60 to 64        2

           In arriving at repair costs no consideration was
           given to repair of car dumper.  This can handle
           only the lower height cars up to 100 tons.  It
           cannot handle tall railroad cars.

       (5)  A one month outage would be required for each
           boiler.  An outage of either Boiler 1 or Boiler 2
           will decrease the capacity of Unit 1 by approxi-
           mately one-half.  A similar relationship exists
           with respect to Boilers 3 and 4, and Unit 2.  The
           outage of Boiler 5 will mean the total loss of
           capacity of Unit 3.  The outage of Boiler 6 will
           mean the total loss of capacity of Unit 4.  As
           discussed on page 3 of cover letter reference no.
           2, Units 1 and 2 cannot be out of service at the
           same time, and there are substantial constraints
           against Units 3 and 4 being out of service simul-
           taneously for periods 'as long as a month.

           Because of the nature of the boiler rehabilitation
           work, the boilers should not be returned to oil
           firing after being refitted for coal.  Therefore,
           the refit work would be scheduled to coincide with
           the stockpiling of adequate amounts of coal for
           start-up.  Such a stockpile cannot be established
           until a system for collecting and treating the
           coalpile rainfall runoff is installed and made
           ready to operate.

       (6)  The restoration of coal firing capability at
           Ridgeland Station is contingent upon two major
           construction and reconstruction activities.  These
           are:  1) the construction of water quality systems
           and 2) the restoration of existing coal associated
           equipment.  The critical path activities are
           illustrated in Figure 1.  You will note that the
           most severe time constraint is imposed by the
RIDGELAND POWER PLANT                                       X-44

-------
            construction of  the  system  to  handle  the  coal  and
            ash  pile  runoff.   The  end date for  this activity
            is 45 months after start of design.   The  boiler
            conversion  activities  proceed  at  the  rate of a
            boiler per  month and the entire conversion is
            completed approximately 51  months after initiation.

            The  estimated  time to  build an adequate coal
            inventory is 100 days.  This is based on  starting
            to build  the storage pile before  actual coal
            burning starts.   A coal supply for  ninety days is
            considered  adequate  at Ridgeland.   The estimated
            buildup is  accomplished at  2500 tons  per  day.
            This is not a  critical path activity.

       (7)   Identify  any state or  local laws  or policies,
            other than  air pollution control  laws or  policies,
            that might  limit the utilization  of coal  by the
            power plant.

            In summary, we cannot  verify at this  time whether
            compliance  with  all  of the  regulations cited is
            technically feasible (and indeed, such a  determina-
            tion cannot be finally made until a specific air
            pollution control mode is chosen) .  What  d^s_
            certain is  that  any  program of attempted  compliance
            will strongly  impact both the  cost  and the scheduling
            of any coal conversion.  These impacts are treated
            in sections (4)  and  (6), above.
RIDGELAND POWER PLANT                                         x_45

-------
             APPENDIX X-l5   RIVERTON POWER PLANT


      Given for the purpose of completeness, the following

 information relative to  the fuel conversion was supplied to

 the Federal Energy Administration by the Potomac Edison

 Company.

      Riverton power plant's original specification for coal

 and the maximum and minimum values for other types of coal

 are presented below:

      Unit's original specification coal as outlined in

 Boiler Proposal:
      Btu/lb.
      Moisture
      Volatile Matter
      Fixed Carbon
      Ash
      Grindability

      Btu/lb.
      %  Sulfur
       %  Ash
12,000 Ultimate Analysis
8.0% Proximate Analysis
29.0% Proximate Analysis
51.0% Proximate Analysis
12.0% Proximate Analysis
55 Hardgrove Minimum

10,800 minimum.
There is no coal with the 0.2%
sulfur required to meet ambient
requirements.

25% maximum for handling and main-
tenance considerations.  There is
no coal with the less than 1% ash
that would be required to meet
emission requirements.  This unit
does not have an electrostatic
precipitator,  and one would have to
be installed.
RIVERTON POWER PLANT
                                                            X-46

-------
      % Volatile and  Ash Slagging/Sintering  -  We  have  never
           encountered difficulty with  either  of  these items
           with bituminous  coal  on this boiler.

      Provided below  are listed  the coal conversion  costs  and
 coal  handling equipment requiring maintenance.

                                                           Outage
      Item                    Comment             Cost      Time

 Install coal  burners,    Equipment available.     $50,000    6  wks,
 etc.                     Some 2 weeks  would be
                         necessary to  plan  for
                         the outage work.

 In  addition to the above item:

 (a)   Differential plant manpower cost  increase to use coal
      instead  of oil  - $64,000/year.

 (b)   Some coal firing items were not maintained  and will
      require  additional maintenance after returning to coal.
      These include conveyor belting, pulverizers, coal
      feeders,  etc.   They should not provide deterrents to
      returning to coal firing.

 (c)   Water quality regulations  may require  expenditures,  the
      amount of which cannot now be determined if the  unit is
      reconverted to  coal firing.
RIDGELAND POWER PLANT                                       X-47

-------
             APPENDIX X-16   VIENNA POWER PLANT


     Given  for  the purpose of  completeness,  the  following

 information relative to  the  fuel  conversion  was  supplied to

 the  Federal Energy Administration by  Delmarva  Power  and

 Light  Company:

     Unit 8 was designed and constructed to  use  heavy  oil  as
 the  only fuel.   No space is  available for the  installation
 of coal bunkers,  pulverizers,  coal pipes and conveyors.  Ex-
 tensive boiler  modifications would be required and even
 then,  the effective capacity of  the unit would be greatly
 reduced because of furnace design limitations.  Therefore,
 this unit has not been considered as  a candidate for conver-
 sion to coal.

     Tabulated  below are the capacities and  ages of  the
 remaining units at the station:

 Unit           Capacity  - MW       Installation  Date/Age-yrs.

  5                   17                        1947/27
  6                   17                        1948/26
  7                   40                        1951/23

      In view of the  age  of  these units, the  extensive  capi-
 tal  requirements for coal conversion, their  probably future
 use  for cycling service  and  considering their  small  size  and
 the  resultant minimal  savings  in oil  consumption, we do  not
 believe the expense  of conversion to  coal  is justifiable.
 Further,  a  cooling  tower serving Unit 8 has  been installed
 in  the former location of the  coal storage pile.  It would
 be  possible to  create  a  new coal pile of  reduced size but
 this would  make the  reliability of the station more  vulner-
 able to  interruptions  in coal  supply  caused  by strikes,
 transport problems,  etc.  In addition, a  coal  pile  in close
 proximity to the Unit  8  cooling tower would  have a  deleteri-
 ous  affect  on the cooling tower and the water in the tower
 with an  adverse affect on the  reliability of this unit.
VIENNA POWER PLANT                                          X-48

-------
      We believe that these units could be converted to coal
 and possibly would not violate the primary air standards.
 Improved particulate collection and SC>2 removal would be
 required by 1978 to meet the SIP standards.  However, there
 does not appear to be space available for the installation
 of scrubbers.

 Conversion Costs

      A.   Convert to coal and possibly comply with primary
           air standards - no SC>2 scrubbing or new particulate
           removal equipment.

           Conversion of Units 5, 6 & 7 to coal         $300,000

      B.   Differential Annual Operating Costs (50% capacity
           factor)

           Operating & maintenance  (excluding fuel)     $ 35,000

 Timing of Conversion - no S02 scrubbing, no new precipitators

      Unit 5-1 month
      Unit 6-6 months
      Unit 7-8 months
RIDGELAND POWER PLANT                                       X-49

-------
       APPENDIX  X-17    L.  D. WRIGHT  POWER PLANT


     Given  for the  purpose of  completeness,  the  following

 information relative  to the  fuel  conversion  was  supplied to

 the  Federal Energy  Administration by the Department  of

 Utilities:

     The  original coal  specifications for the  two  units were
     as  follows:

     Crawford County, Kansas
     Carbon - 49.0%
     Ash  -  10.0%
     Volatie Matter - 34.1%
     Sulfur - 3.5%
     Moisture -  10.0%
     Btu  -  12,500/lb
     Ash  fusing  temperature  -  1900°F

     Presently the  coal being  fired  is from  Carbon County,
     Wyoming with the following  analysis:

     Moisture -  14  to 16%
     Ash  -  6 to  10%
     Sulfur - 0.6 to  0.9%
     Btu  -  9,900 to 10,100/lb
     Ash  fusion  - 2,100° to  2,200°F

     Present coal storage  area is 65,000 tons.   There are  no
     facilities  for unloading  coal during winter weather.
     L.D. Wright is in  the midst of  construction a new 91.5
     MW  addition to the present  plant and until  this is
     completed,  an  increase  in the area available  for coal
     storage is  limited.

     In  order to handle the  increase discharge of  ash,  a new
     ash  line will  have to be  installed, along with  additional
     ponding to  contain the  ash.   Also, an enlarged  coal
     crusher will be  needed  and  conveyor modifications.
L. D. WRIGHT POWER PLANT                                    X-50

-------
      With  the  slagging  characteristics  of  the  fuel,  addi-
      tional  soot blowers  will  have  to be installed.  A  new
      loader  will need to  be  purchased to handle  additional
      coal.

      The estimated  cost for  additional  equipment and refur-
      bishing is  as  follows:

      Coal  crusher and conveyor modifications    $ 18,000.00
      Increase  size  of railroad siding             50,000.00
      New ash line                                20,000.00
      Coal  loader                                 70,000.00
      Ash pond                                     15,000.00
      Upgrading pulverizers - unknown
                                                $173,000.00

      The additional fuel  cost at the
        present price would be                   263,925.00
      Extra coal  handling  cost                    25,218.00
      Increased operating  and maintenance cost     44,306.62
                                                $333,449.62

      Starting  in April  of 1976, the L.D. Wright plant  has
      a long term contract with the  Stansbury Coal Co.,
      Denver, Colorado,  to purchase  its  future  coal needs.
      This  amount of coal  to  be purchased takes into account
      that  the  plant will  be  100% coal  fired by the end of
      1976.
L. D. WRIGHT POWER PLANT                                      X-51

-------