WATER QUALITY MANAGEMENT GUIDANCE
           WPD  11-75-01
DEMONSTRATION OF A PLANNING
PERSPECTIVE FOR WASTE WATER
      SLUDGE DISPOSITION
     Knoxville/Knox County
          NOVEMBER  1975
 ENVIRONMENTAL PROTECTION AGENCY
       WATER PLANNING DIVISION
      WASHINGTON, D.C.   20460

-------
   DEMONSTRATION OF A DEVELOPED METHODOLOGY

                   FOR THE

     ULTIMATE DISPOSAL OF RESIDUAL WASTES
            Contract No.  68-01-3225
          Project No. EPA-WA-75-R210
            Program Element 2BH149

           Knoxville/Knox County
                Project Officer
                 Dean Neptune
United States Environmental Protection Agency
         Planning Assistance Branch
           Washington, D.C.  20460
                 Prepared for

            WATER PLANNING DIVISION
 UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
            WASHINGTON, D.C.  20460

-------
                         TABLE OF CONTENTS

                                                            Page
Abstract                                                     vi
List of Tables                                              vii
List of Figures                                               x
Acknowledgements                                            xii
CHAPTER I      CONCLUSIONS AND RECOMMENDATIONS                1
     INTRODUCTION                                             1
     CONCLUSIONS                                              1
               Study Area                                     1
               Methodology                                    2
     RECOMMENDATIONS                                          3
               Study Area                                     3
               Methodology                                    4
CHAPTER II     INTRODUCTION                                   5
     BACKGROUND                                               5
     PURPOSE                                                  7
CHAPTER III    THE PLANNING PERSPECTIVE AND THE STUDY        10
               APPROACH
     THE METHODOLOGY PLANNING PERSPECTIVE                    10
     STUDY APPROACH                                          12
CHAPTER IV     CHARACTERIZATION OF THE KNOXVILLE-KNOX        17
               COUNTY AREA
     INTRODUCTION                                            17
     NATURAL SETTING                                         18
               Geology                                       18
               Climate and Air Quality                       20
               Topography                                    21
               Hydrology and Water Quality                   21
               Soils                                         26
               Flora-Fauna                                   27
               Mineral Resources                             27
     CULTURAL SETTING                                        27
               Evolution of the Knoxville-Knox County        30
                 Area
                                  ii

-------
                     TABLE OF CONTENTS  (CONT'D)
               The  1990  General  Plan  for  Knoxviiie-          31
                 Knox County
               Institutional  Characterization                34

     LEGAL SETTING                                           37

               The  Garbage  and Rubbish Collection  and        37
                 Disposal Services Act
               Solid  Waste  Disposal Act                      39
               The  Utility  District Act                      40
               The  Urban Type Public  Facilities Act          40
               The  Industrial Development Corporation        40
                 Act
               Corporations                                 41
               Additional Legal  Considerations               41

CHAPTER V      THE  SLUDGE DISPOSAL  PROBLEM                  48

     INTRODUCTION                                           48

     EXISTING FACILITIES                                    49

               Third  Creek  Drainage Area                    49
               Fourth Creek Drainage  Area                   52
               Loves  Creek  Drainage Area                    53
               Ten  Mile  Creek Drainage Area                 54
               East Knoxville Drainage Area                 54
               Knox-Chapman Drainage  Area                   55
         • '     Little Flat  Creek Drainage Area              55
               Bullrun Creek Drainage Area                  56
               Beaver Creek Drainage  Area                   56
               Hardin Valley Drainage Area                  57
               Turkey Creek Drainage  Area                   57

     EXISTING SLUDGE DISPOSAL PROCESSES                     58

     ANTICIPATED KNOXVILLE-KNOX COUNTY MUNICIPAL WASTE-     61
     WATER TREATMENT FACILITIES

               Knob Creek                                   61
               Powell                                       62
               Turkey Creek                                 62
               Karns                                        62
               Lyon Creek                                   63
               Loves Creek                                  63
               Forks-of-the-River                           63

     PROJECTED SLUDGE QUANTITIES                            64
                                    iii

-------
                      TABLE OF CONTENTS (CONT'D)
CHAPTER VI     SELECTION OF ALTERNATIVE SLUDGE DISPOSAL      73
               OPTIONS

     INTRODUCTION                                            73
     STUDY AREA CONSTRAINTS                                  74

     EVALUATION OF SLUDGE DISPOSAL OPTIONS                   76

               Elimination of Infeasible Alternatives        75
               Local Definition of General Disposal          73
                 Options
               Implications of Solid Waste Management        80
                 Planning
               Suitability of the Study Area for Land        81
                 Disposal Options
               Alternative Disposal Options Selected         83
                 for Further Review

CHAPTER VII    DEVELOPMENT AND EVALUATION OF ALTERNATIVE     90
               SLUDGE MANAGEMENT PLANS
     INTRODUCTION                                            90
     DEVELOPMENT OF ALTERNATIVE SLUDGE MANAGEMENT PLANS

               Alternative 1 - Sanitary Landfill             90
               Alternative 2 - Trenching                 .    93
               Alternative 3 - Incineration                  93
               Alternative 4 - Land Application:  Spray       96
                 Irrigation
               Alternative 5 - Land Application:              98
                 Composting
               Alternative 6 - Resource Recovery:  IRD        99
     EVALUATION OF ALTERNATIVE SLUDGE MANAGEMENT PLANS      99
               Economic  Analysis
               Environmental Factors

                    Alternative 1 - Sanitary Landfill
                    Alternative 2 - Trenching
                    Alternative 3 - Incineration           124
                    Alternative 4 - Land Application:      125
                      Spray Irrigation
                    Alternative 5 - Land Application:      125
                      Composting
                    Alternative 6 - Resource Recovery:     126
                      IRD
                                 iv

-------
                      TABLE OF  CONTENTS  (CONT'D)
APPENDIX A
APPENDIX B
APPENDIX C
                                             Page

Feasibility of Alternatives                  127
     Alternative 1 - Sanitary Landfill       128
     Alternative 2 - Trenching               128
     Alternative 3 - Incineration            128
     Alternative 4 - Land Application:       129
       Spray Irrigation
     Alternative 5 - Land Application:       129
       Composting
     Alternative 6 - Resource Recovery:      130
       IRD
Performance                                  130
     Alternative 1 - Sanitary Landfills      131
     Alternative 2 - Trenching               131
     Alternative 3 - Incineration            132
     Alternative 4 - Land Application:       132
       Spray Irrigation
     Alternative 5 - Land Application:       133
       Composting
     Alternative 6 - Resource Recovery:      133
       IRD

NATIONAL AND STATE/COUNTY AIR QUALITY        A-l
STANDARDS AND AIR QUALITY DATA FOR' KNOX-
VILLE, TENNESSEE
NATIONAL                                     A-l.
STATE AND KNOX COUNTY-            .           A-5

GENERAL WATER QUALITY CRITERIA FOR THE       B-l
DEFINITION AND CONTROL OF POLLUTION
IN THE WATERS OF TENNESSEE

FEDERAL WATER POLLUTION CONTROL DISCHARGE    C-l
STANDARDS
APPENDIX D
SOLID WASTE REGULATIONS-STATE OF  TENNESSEE   D-l

-------
                              ABSTRACT
     The existing and future sludge disposal problem in Knoxville,
Tennessee was investigated, and six major sludge management plans
were developed.  The plans were derived and evaluated by utilizing
a methodology previously developed for the U.S. Environmental
Protection Agency.

     The plans detail the processing, transportation, and ultimate
disposal sub-systems necessary to meet environmental, operational,
and institutional constraints found in the study area.  In addition,
costs of the various sub-systems and the overall costs of the plans
were determined.

     This report  was submitted in fulfillment of RFP No. WA75-R210,
Contract No. 68-01-3225, by Engineering-Science, Inc. under sponsor-
ship of the U.S.  Environmental Protection Agency.   Work was completed
as of 10 September 1975.
                                  vi

-------
                          LIST OF TABLES
Table No.                 Title                              Page

 III-l      Data Requirements and Sources for Knoxville-      14
               Knox County Case Study

   V-l      Present Sludge Quantities                        59

   V-2      Population Projection for the Anticipated        68
               Facilities

   V-3      Population Projections for the Anticipated       69
               Facilities-Industrial and Commercial
               Population Equivalents

   V-4      Population Projections for the Anticipated       70
               Facilities-Domestic,  Industrial,  and
               Commercial Population Equivalents

   V-5      Sludge Projections for the Anticipated           71
               Facilities-Raw Sludge

  VI-1      Summary Evaluation of Sludge Disposal            ?7
               Options

  VI-2      Factor Maps and Ranking Used for Site            82
               Suitability Analyses

  VI-3      Sludge Condition Required for Alternative        ^
               Disposal Options

 VII-1      Sludge Projections for the Anticipated           92
               Facilities - Alternative 1-Sanitary Land-
               fill and Alternative 2-Trenching

 VII-2      Sludge Projections for the Anticipated           95
               Facilities - Alternative 3-Incineration

 VII-3      Sludge Projections for the Anticipated           97
               Facilities -.Alternative A-Land
               Application:  Spray Irrigation

 VII-4      Sludge Projections for the Anticipated          10°
               Facilities - Alternative 5-Land
               Application:  Composting
                                  vii

-------
                       LIST OF TABLES (CONT'D)
Table No.             Title                                 Page

 VII-5      Sludge Projections for the Anticipated          101
               FacdHt-i^s - Alternative 6-Resource
               Recovery:  IRD

 VII-6A     Alternatives Evaluation Matrix-Economics and    102
               Environmental Factors

 VII-6B     Alternatives Evaluation Matrix-Feasibility      104
               and Performance

 VII-7a     Cost Estimate for Alternative 1-Sanitary        107
            Landfill

 VII-7b     Cost Estimate for Alternative 2-Trenching       108

 VII-7c     Cost Estimate for Alternative 3-Incineration    109

 VII-7d     Cost Estimate for Alternative 4-Land             110
               Application/Spray  Irrigation

 VII-7e     Cost Estimate for Alternative 5-Land             111
               Application/Composting

 VII-7f     Cost Estimate for Alternative 6-Resource        112
               Recovery

 VII-7g     Capital,  0 & M,  and Present  Worth  for  the       113
               Alternatives

 VII-8      Costs (Dollars)  Per Ton of Dry Sludge  Solids    H8
               Processed,  Transported, and Disposed  or
               Reclaimed Without  Federal Funding and with
               Federal Funding -  1995  Sludge Projection

 VII-9      Potential Significant Environmental Impacts     120
               of Alternative Sludge Management Plans

   A-l      Tennessee and Knox County  Ambient  Air  Quality   A-10
               Standards for Suspended Particulates
               Sulfur Dioxide, Carbon  Monoxide, Photo-
               chemical  Oxidants, Non-Methane  Hydro-
               carbons,  and  Nitrogen Dioxide

 A-2       Tennessee Ambient Air Quality Standards  for    A-ll
               Soil Index in COH  Units per 1000
               Linear Feet or Air
                                viii

-------
                       LIST OF TABLES (CONT'D)
Table No.             Title                                 Page

  A-3       Tennessee Ambient Air Quality Standards for    A-12
               Gaseous Fluorides Expressed as HF

  A-4       Maximum Allowable Particulate Emission         A-14
               Standards for Incinerators

  C-l       Second Treatment Standards                     C-l
                                  ix

-------
                         LIST OF FIGURES


Figure No.               Title
                                                            Page
  H-1      Study Area and  General Location Map-              8
               Knoxville  and  Knox County

 III-l      Operative  and Ultimate Disposal of  Residual      n
               Wastes:  A Planning Perspective

 HI-2      Study Approach  to Developing and Evaluating      13
               Alternative  Sludge Management Plans  for
               Knoxville-Knox County Case  Study

  IV-1      Carbonate Bedrock and Karst Areas-Knoxville      19
               and Knox County

  IV-2      Percent Slope Map-Knoxville and Knox County      22

  IV-3       Surface Hydrology-Knoxville and Knox County      23

  IV-4       Flood-Prone Areas-Knoxville and Knox County       25

  IV-5      Prime and Secondary Agricultural Soil Areas-      28
              Knoxville and Knox County

  IV-6      Mineral Resources-Knoxville and Knox County       29

  IV-7      Existing Land  Use-Knoxville and Knox County       32

  IV-8      1990 Land  Use  Plan-Knoxville and Knox County      33

  V-l      Drainage Basins  and  Public  Water Supply           50
              Locations-Knoxville and  Knox County

  V-2      Utility Districts  Located in Knox County         51

  V-3      Wastewater  Service Areas and Treatment            65
              Facilities-Knoxville and Knox County

  V-4       Existing and Projected Population Distribu-       66
              tion-Knoxville  and  Knox  County

VI-1       Strip-Mine Areas Near  Knox  County                 79

VI-2       Sanitary Landfill  Site Suitability Map-           84
             Knoxville and Knox  County

-------
                      LIST OF FIGURES  (CONT'D)
Figure No.           Title

  VI 2      Trenching Site Suitability Map-Knoxville         85
               and Knox County

  VI-A      Land Application Site Suitability Map            86
               Knoxville and Knox County

. VII-1      Capital Costs for Solids Processing Facilities  114

 VII-2      Operating Costs for Solids Processing           115
               Facilities

 VII-3      Trucking Transportation Costs  (1975)            H6
                                  xi

-------
                         ACKNOWLEDGEMENTS
     The assistance received from the Project Officer, Dr. Dean
Neptune, is recognized and appreciated.

     Specific mention must be made for the help received from the
following who provided time, information, and guidance to this
project:  Messrs. Donald Parnell and Richard Zelinski of the
Metropolitan Planning Commission of Knoxville-Knox County; Mr.
Frank Erickson of the East Tennessee Development District; and
Mr. Philip Lynn of the City of Knoxville Public Service Department.
The assistance of local consulting engineering firms, regulatory
agencies, and the Tenneseee Valley Authority is also acknowledged.

     Principal staff from Engineering-Science, Inc. were Mr.
Michael Wyatt, Project Manager, and Mr. Richard Heil, Project
Engineer.
                                   xii

-------
                           CHAPTER I
                CONCLUSIONS AND RECOMMENDATIONS
INTRODUCTION

     This report addresses the sludge disposal problem currently
experienced in Knoxville, Tennessee and the anticipated problem
expected upon expansion and upgrading of existing wastewater
treatment facilities and the construction of a regional facility.
The techniques employed in the projection of the present and
future sludge quantities and qualities; selection of feasible
sludge handling, transportation, and ultimate disposal or resource
recovery methods; and the evaluation of these methods compiled in-
to management plans were derived from a previously developed
methodology document discussed later in this report.  The following
sections present the conclusions and recommendations derived during
this study for both the Knoxville-Knox County Study Area as they
impact upon the on-going 208 planning process in this Area and
the evaluation of the utility and constraints of the methodology
document.

CONCLUSIONS

Study Area

        Six sludge management plans were found feasible for further
        in-depth consideration and final selection in the Study
        Area.  They are (not listed in any order of priority):
        (1)
truck transport and sanitary landfill disposal of a
digested, dewatered sludge to a County-owned and
operated site in the northeastern portion of the
County;
        (2)  truck transport and trench-incorporation of a
             digested, dewatered sludge to a City-owned and
             operated site in the northeastern portion of the
             County;

        (3)  truck transport and incineration of an undigested,
             dewatered sludge to a City-owned and operated
             incinerator located on the site of the proposed
             regional wastewater treatment facility with truck
             transport and sanitary landfill disposal of a digested,
             dewatered sludge from two outlying treatment plants,
             to the landfill identified in (1) above;
                               —1 —

-------
 (4)  tank truck transport and land application  (via
     spray irrigation) of a digested sludge to  a County-
     owned and City-operated site in the northeastern
     portion of the County with truck transport of a
     digested, dewatered sludge from one outlying facility
     to the landfill site identified in  (1) above;

 (5)  truck transport and land application  (via  composting
     and disking) of a digested, dewatered sludge to a
     County-owned and City-operated site [same  as in (4)
     above] with truck transport of a digested, dewatered
     sludge from one outlying facility to  the landfill
     site identified in (1) above; and

 (6)  tank truck and barge (from the regional facility)
     transport of a digested sludge to a privately-owned
     and operated sludge dewatering and fertilizer produc-
     tion facility on Pickel Island in the eastern portion
     of the County.

The six management plans identified above appear to present
no insurmountable problems in terms of meeting  environmental
constraints, performance criteria, or institutional and
legal feasibility.  However, the land application (via
spray irrigation) plan appears, at the level of cost
information available in this study, to be less cost-
effective than the other five plans.

Data constraints under which this study operated precluded
the development of the sludge management plans at any level
greater than a feasibility/representative system descrip-
tion.  It appears at this time that in order to develop
the data and its concomitant level of detail.for developing
site-specific alternatives for public review and selection
of a final plan, 208 planning agencies must be willing to
spend a larger portion of time and effort in residual waste
management plan development than perhaps is currently
alloted and/or allocated to them in the 208 grant monies
and planning time-frame.

ogy

Cost data presented in the Methodology document were, in
many instances during the conduct of this study, extra-
polated from curves.  Thus,  the utility of the cost data
for this study is limited to a first-order feasibility
analysis with an unknown variability when applied to a
specific area.   Site specific costs were either non-
existent or not made available to verify Methodology costs.
                         -2-

-------
        The Methodology document, as was intended, was used as
        both a source for information readily obtainable within
        the document and as a reference to other sources of
        information.  During future studies in which the
        Methodology document is utilized to develop alternative
        sludge management plans, the user (e.g. a 208 planning
        agency) should make every effort to supplement the
        Methodology document with the publications referenced
        in that document.  This is particularly true when local
        data are lacking or incomplete.

        Care must be exercised in the utilization of sludge
        quantity projections by 208 planning agencies.  Where
        local data indicate a different per capita wastewater
        flow, significant variations in raw sewage qualities
        due to industrial inputs or large infiltration and inflow
        contributions to the sewer system, the values presented
        in the Methodology document must be adjusted accordingly.
RECOMMENDATIONS
Study Area
        Additional local data, particularly with regard to the types
        and distribution of flora and fauna, site preparation and
        acquisition costs, probable users fees, and transportation
        costs are required as inputs before final selection of the
        preferred sludge management plan.

        Future long-term solutions for resource recovery appear
        promising and should be investigated as soon as possible.
        These solutions include strip-mine reclamation in areas
        outside the County and fuel supplementation in either a
        City-owned municipal solid waste incinerator or coal-
        fired power plants within Tennessee Valley Authority
        jurisdiction.

        The Knoxville-Knox County Metropolitan Planning Commission
        (the 208 planning agency) should, as soon as possible,
        obtain from local utility districts and their engineers
        verified or additional/corrected values for the sludge
        quantities present in this report.  A close review and
        substantiation of the data and assumptions made during
        both the 201 Facilities planning effort and this study
        should be made by the agency to insure a common base of
        facilities and sludge production.
                                    -3-

-------
Methodology
        The evaluation procedures provided in the Methodology
        document can be taken to any level of detail desired.
        It is recommended that,  in using the Methodology,
        such a feasibility level of analyses as represented
        by this case study, be done initially prior to detailed
        transportation routing and site evaluation.  Undesireable
        alternatives, as defined by the involved institutions
        and general public, could then be eliminated without
        undue time and monetary  constraints.  This feasibility
        evaluation, in addition  to identifying feasible alter-
        natives, also identifies critical data needs requiring
        further and more detailed resolution and/or quantifica-
        tion.

        The environmental,  feasibility, and performance evalua-
        tion factors in the Methodology document are rated in a
        subjective manner.   Prior to the site-specific evaluation
        of the feasible alternatives,  the 208 planning agency
        should review the factors and  use local, site-specific
        data to provide quantitative measures or descriptions of
        the ratings where possible.
                                -4-

-------
                           CHAPTER II
                          INTRODUCTION
BACKGROUND

    A review of the Federal Water Pollution Control Act Amendments
of 1972 (the Act)  and the associated legislative history clearly
indicates the Congressional intent to eliminate as much as possible
pollutant discharges to receiving components of the environment.
The basic waste treatment process consists of separating contaminants
in a way that is acceptable to local, State, and Federal regulatory
agencies.  Proper ultimate disposal or reuse of residual wastes is
essential so that usable environmental components such as surface
or ground waters will not be needlessly contaminated and that pollut-
ants are not continuously and directly recycled into water supplies,
food chains, and other cycles.

    At the present time, solids handling and other ultimate disposal
operations are probably the most troublesome problems in treatment
plant operations,  partly because they have had the least attention.
The problem is becoming more critical because residual waste volumes
are increasing with higher treatment efficiencies and because the
physical-chemical sludges and other residual wastes from tertiary
treatment operations are more difficult to handle than some of the
common biological sludges.

    The basic approaches embodied in the Act require pragmatic and
logical steps to identify and control pollution sources, including:

    (1)  regional planning and management of the Nation's waters
         which will eventually identify all point and non-point
         sources of pollution within a given region, and establish
         effluent limitations on these sources of pollution;

    (2)  delegation of the permit programs to approved State programs
         after guidelines have been prepared by the Federal Govern-
         ment ; and

    (3)  control programs to determine compliance with the effluent
         limitations and commencement of civil and criminal proceed-
         ings against violators.

    Regional planning and management processes to be undertaken by
the States must be as inclusive as physically possible, both with
respect to known types of pollution and the limitations of treatment
processes for removing various pollutants.  In addition, Sections
                                     -5-

-------
201(d), 201(e), 201(f) of the Act specifically encourage resource
utilization and resource recycling.  Within this encouragement lies
the intent that planning processes carried out in fulfillment of
Sections 201, 208, and 303 recognize and promote, where possible,
areawide implementation concepts of residual waste management.

    Under subsections (J) and (K) of Section 208(b)(2)  of the Act,
208 planning and management agencies must address "a process to
control the disposition of all residual waste generated in such area
which could affect water quality; and a process to control the dis-
posal of pollutants on land or in subsurface excavations within such
area to protect ground and surface water quality."  In addition,
Section 201 (d)(4)  of the Act requires in facilities planning con-
sideration of "the ultimate disposal of sludge in a manner that will
not result in environmental hazards."  It therefore is also the
concern of 208 planning agencies that facilities plans already made
and either presently under construction or proposed for construction
within the twenty-year 208 planning time framework be incorporated
into the overall 208 plan which is to include residual waste disposal
control.

    As the United States moves toward the goals and policies
described in Section 101 of the Act, publicly-owned treatment works
(POTU's) are required to meet by July 1, 1977, or July 1, 1978 (for
new construction), secondary treatment as defined in the Federal
Register (Ref. II-l).  In addition, by Sections 201(g) (2)(A)  and
30l(b) (2)(B)  of the Act, POTW's are to provide by July 1, 1983, the
application of best practicable waste treatment technology.

    The application of wastewater treatment technologies to meet
these requirements is anticipated to generate substantial amounts
of municipal wastewater treatment plant sludges which must be
handled yearly.  Realizing that sludge handling absorbs 35 percent
of the capital costs and 55 percent of the annual operation and
maintenance costs of a wastewater treatment plant, these projected
increases in sludge production will mean considerable expenditures
of money (Ref. II-2).  Every effort must be taken by 208 planning
and management agencies to see that the expenditures necessary for
sludge handling and disposal are made wisely.

     Recognizing that 208 agencies may require assistance in the
evaluation of residual waste management and disposal alternatives
for their areas, the Environmental Protection Agency (EPA) prepared
a Methodology document which considers the sources and characteristics
of municipal wastewater treatment plant residual wastes, processing
and transportation alternatives, and various methods of ultimate
disposal and resource recovery, hereinafter referred to as the
Methodology (Ref. II-2).  This Methodology also considered the
                                   -6-

-------
physical, chemical, and biological nature of the residual wastes
generated and various alternate disposal/recovery methods in light
of economic, environmental, social, and institutional implications
in the evaluation and formulation of alternative plans and the
selection of the preferred plan in the 208 planning process.

PURPOSE

    The purposes of this report are threefold, namely:

    (1)  to demonstrate the Methodology in a specific 208 planning
         area;

    (2)  to apply and verify the Methodology and suggest improve-
         ments; and

    (3)  to document the results as a planning tool for consider-
         ing alternatives.

    This demonstration study was conducted in Knoxville, Tennessee,
as a coordinated effort between the Knoxville-Knox County Metropolitan
Planning Agency (MPC); the Water Planning Division of EPA, Washington,
D.C.; and Engineering-Science, Inc. of McLean, Virginia.  The study
area is depicted in Figure II-l.

    Data sources were obtained from local sources established by MPC,
principally from previous local studies and 201 and 303 planning.
The MPC provided an understanding of timely cooperation with  local
sources for technical information on the location and size  of exist-
ing and proposed wastewater treatment plants, the magnitude and
character of the sludges either currently generated or to be
generated, pertinent land and water resource data, and socio-
political conditions.  During the course of this study, additional
outside data sources such as State and regional planning agencies;
State, county, and local agencies; and published reports were used
to augment data available through MPC.  Where data was unavailable,
reasonable assumptions were made utilizing as necessary the
information provided in the Methodology.
                                  -7-

-------
STUDY  AREA  AND  GENERAL  LOCATION MAP

     KNOXVILLE AND KNOX  COUNTY
                                  GENERAL LOCATION MAP

•
NMfcvilU

M9tj ALA.
1

KY.
TEH*.
^S^
TZ^"*"
-. ^^ . - .— -^^..- ^^M*
\ 8A. S
\
•

!7"
.•*
-------
                             CHAPTER II
                             REFERENCES
II-l       38 CFR 159 (17 August 1973).

I1-2       Sludge Processing,  Transportation,  and Disposal/Resource
           Recovery:   A Planning Perspective,  Wyatt, J. M.,  and
           White, P.  E., Jr.  Engineering-Science, Inc., EPA Contract
           No. 68-01-3104 (April 1975).
                                  -9-

-------
                            CHAPTER III

          THE PLANNING PERSPECTIVE AND THE STUDY  APPROACH
 THE METHODOLOGY  PLANNING  PERSPECTIVE

      The planning  perspective  for municipal wastewater  treatment
 and residual waste disposal  is depicted  in Figure  III-l.  Two major
 pathways of concern  in  the 208 planning  and management  process are:

      (1) Given an  existing wastewater  treatment  facility, what is
          the most  suitable ultimate disposal method  for the resid-
          ual wastes  produced?

      (2) Where a wastewater  treatment  facility is  needed and planned,
          and given existing  and anticipated physical, technological,
          environmental, social, and economic constraints of residual
          waste management and control, what is the most suitable type
          of wastewater  treatment facility for the  chosen residual
          waste disposal or use methodology?

      In  the first  situation  (pathway)  cited above, the  existing
 wastewater treatment facility is generating a known  quantity and
 quality  of residual wastes.  Federal,  State, and local  guidelines
 and regulations  help define  the ultimate residual  waste disposal
 options  available  to that facility.  These disposal  options,
 by  virtue of regulatory and  environmental, social, and  economic
 constraints, will  then have  restrictions as to the quantity and
 quality  of residual wastes they can accept.  By a  comparison of
 the disposal method's qualities and quantities of  residual wastes
 they can handle with the known values  from the wastewater treat-
 ment facility, the facility  can either utilize the disposal methods
 available or further treat and transform the residual wastes
 to  qualities and quantities  amenable to the available disposal
 methods.

      The  second situation (pathway) is essentially the  reverse
 process.  A planning area will have acceptable ultimate disposal
 methods, again constrained in quantities and qualities which they
 can  handle by virtue of regulations and environmental,  social, and
 economic  factors, acceptable for use in the area.  The  choice of
 the  type of wastewater facility will then be influenced by comparing
 predicted quantities and qualities of  residual wastes from a
 variety of treatment processes to those of the acceptable and
 available ultimate disposal methods.   In this case,  the quantities
 and  qualities of residual wastes from various wastewater treat-
ment processes can be modified by both raw wastewater modification,
                                 -10-

-------
                                                             FIGURE HI-I
            OPERATIVE  AND  ULTIMATE  DISPOSAL
                     OF  RESIDUAL  WASTES'
                   A  PLANNING   PERSPECTIVE
   (MVEN A RAM WASTEWATER ANO NEE0
FOR ULTIMATE DISPOSAL OF RESIDUAL WASTE

                    REJECT FACILITY
                                                      ACCEPT FACILITY
RAW WASTEWATER F" —
                            MASTEVftTER TREATMBff
                                 FACILITY
          mm
         tUANSFORM
                                                     .J
                                                 INSTITUTION At
                                                  CONSTRAINT*
                              MtlDUAL «A»TE
                     ULTIMATE
                                         MCTNW
                                 L_E
                               ENVIRONMENTAL,
                               SOCI AC,
                               ECONOMIC,
                               CONVTftAMTV
                  REJECT

                                            I
                                               OIVCN CONSTRAWTS
                                             - AND NEED FOR A
                                                         TREATMENT
                                  ACCErt.
                                 DISPOSAL
                                  METHOO
              . MTNMMV POII A PLANNED PUTURf «AtE* OR WMTCWffEft
              TREATMENT PAOUTV WlTHM «IVEN CONfTftAWTS.

              PATMMT POR All EXISTINS MATE* Oft VASTEWkTI*
              TRIATMENT PAC&.ITV fNTMM SIVCN CONSTRANftlb
SOURCE: RtfsrtnotDl-l Modified to Reflect situation in I&ioxvilleA^vox County
                                    -11-

-------
such as industrial pretreatment and sewer infiltration and inflow
controls, and by residual waste treatment and transformation proces-
ses.

     The evaluative proceso J^cribed above would be the same,
although more complex, where more than one wastewater treatment
facility either exists or is planned.  However, the potential for
economies of scale will require that combined treatment processes,
both for wastewater and residual wastes, be investigated to insure
a cost-effective plan as well as a plan that could provide for the
resource recovery, recycling, and utilization .encouraged in the
Act.

STUDY APPROACH

     The Methodology pathway (approach) used in the Knoxville-Knox
County case study is not constrained by existing/proposed quantities
and qualities of sludge.  This approach corresponds to the second
situation described in the previous section.  The study approach
and report organization derived from following the pathway in
Figure III-l are shown in Figure III-2.

     As shown in Figure III-2, the study initially has three
independent processes occurring concurrently:  1) generation of
the raw-sludge forecast; 2) characterization of the study area;
and 3) delineation of the ultimate disposal options.  The first
intersection of processes occurs in the feasibility analysis of
ultimate disposal options in which the study area constraints
(derived from the study area characterization)  and the general
siting/suitability criteria for the ultimate disposal options are
compared and evaluated.  Subsequently, the feasible disposal options
and the required sludge conditions (i.e., digested, de-watered, etc.)
are identified.  A sludge management plan for the study area is
then developed for each feasible disposal option incorporating
the raw-sludge forecast and the required sludge condition (i.e.,
solids handling system).  In the last step of the approach, each
alternative sludge management plan is evaluated according to the
criteria delineated in Chapter VII of the Methodology  (i.e.,
economic, environmental, performance, and feasibility parameters),
The general data requirements and the data sources utilized to
meet them are presented in Table III-l.

     The approach taken during this study and as depicted in Figure
IH-2 is a possible approach that may be taken by the 208
planning agencies.  Existing ana/or proposed wastewater treat-
ment plants generally have either poor records of existing
quantities and qualities of sludge or insufficient and unavailable
                                 -12-

-------
  STUDY   APROACH  TO  DEVELOPING  AND   EVALUATING  ALTERNATIVE  SLUDGE
        MANAGEMENT  PLANS   FOR  KNOXVILLE-KNOX   COUNTY  CASE  STUDY
    EXISTING/PROPOSED
    STP'S (locations)
  WASTEWATER  TREATMENT
  REQUIREMENTS
POPULATION
PROJECTIONS
            RAW-SLUDGE FORECAST
            (quantitiM, distribution)
 CHAPTER V  *
             DEVELOPMENT OF
             ALTERNATIVE SLUDGE
             MANAGEMENT PLANS
                    I
             EVALUATION  OF
             ALTERNATIVE SLUDGE
             MANAGEMENT PLANS
          CHAPTER VII
* Report chapter  in which enclosed
   steps are  presented.
I
  CHARACTERIZATION OF
  STUDY AREA NATURAL
  AND CULTURAL  SETTINGS
  (onvironnwntal a socioseonomicol
  voluss)
                                         CHAPTER IV
                                        F
           l|
I
  DELINEATION OF ULTIMATE
  SLUDGE  DISPOSAL  OPTIONS
                                              SITING/SUITABILITY
                                              CRITERIA
                                                   STUDY AREA
                                                   CONSTRAINTS
                                  FEASIBILITY ANALYSIS OF
                                  ULTIMATE DISPOSAL
                                  OPTIONS
                             ALTERNATIVE  FEASIBLE
                             DISPOSAL OPTIONS
               	I   FEDERAL/STATE REGULATIONS
                     (sluoos conditions)
                                         CHAPTER VI
                                                                        5
                                                                                                    l
                                                                                                   ro

-------
                            TABLE III-l

            DATA REQUIREMENTS AND SOURCES FOR KNOXVILLE-
                      KNOX COUNTY CASE STUDY
     DATA REQUIRED                          DATA SOURCE

Existing/Proposed STP's            201 facilities plan (draft), MFC,
                                   utility districts, Wastewater
                                   Control System (City of Knoxville)

Population Projections             201 facilities plan (draft), MFC

Wastewater Treatment Requirements  201 facilities plan (draft),
                                   utility districts, EPA Regional
                                   Office

Study Area Characteristics         303(e) planning reports, 201
(e.g., geology, land use, etc.)    facilities plan (draft), MFC and
                                   TVA reports, Tennessee Department
                                   of Conservation, miscellaneous
                                   maps and reports from Federal,
                                   regional, and educational
                                   institutions

Ultimate Sludge Disposal Options/  Methodology (Chapter VI), MFC,
Siting Criteria/Costs              TVA

Federal, State Sludge Disposal     Methodology (Chapter VI),
Regulations                        Tennessee State Agencies (Air,
                                   Water, Public Health);.

Alternative Solids Handling        Methodology (Chapter IV and VIII)
Systems/Costs

Transportation Costs               Methodology (Chapter V)

Evaluation Criteria                Methodology (Chapter VII)
information in 201 Facilities Plans for proposed plants.  Many 208
agencies will be faced, as was the case in this study, with in-
complete or on-going facilities planning programs and, thus, will
be required to generate sludge quantities and qualities utilizing
initially local information, if available, and secondly the
                                   -14-

-------
Methodology.  The data sources utilized during this study (see
Table III-l) would therefore also be the same types of sources
other 208 planning agencies would use in the development of
sludge management plans.
                                    -15-

-------
                            CHAPTER III
                            REFERENCES
III-l      Sludge Processing,  Transportation,  and Disposal/
           Resource Recovery:   A Planning Perspective,  Wyatt,  J.M. ,
           and White,  P.E.,  Jr., Engineering-Science,  Inc., EPA
           Contract No.  68-01-3104 (April 1975).
                                  -16-

-------
                            CHAPTER  IV

       CHARACTERIZATION OF THE KNOXVILLE-KNOX COUNTY AREA
INTRODUCTION

     The primary purpose of this chapter is to provide background
data on the Knoxville-Knox County Study Area used in developing
and evaluating municipal wastewater sludge disposal alternatives.
Because this is a case study which will be read by persons unfamiliar
with the Study Area, it is deemed necessary to include such a pre-
sentation of general background information as an aid in understand-
ing the tailoring of the Methodology to the Knoxville-Knox County
area.

     The following sections are intended to provide brief but com-
prehensive pictures of the Study Area.  The pictures to be described
are the natural and cultural systems or settings.  An understanding
of these systems should guarantee both protection of existing and
future environmental and cultural values in the region and a minimum
cost for a sludge management system.  Ignoring any or all of these
systems might result in sludge disposal methods that impair existing
and/or future uses of air, land, and water resources and lead to
costly corrective or containment actions.

     The natural setting includes discussions of the physiography,
the geology, climatology, hydrology, soils, and other physical
characteristics which provide a basis for evaluating the environmental
suitability of the Study Area for various types of sludge management
options and the probable environmental impact.  The cultural setting
describes the evolution of socioeconomic development in the Study
Area and the projected level, type, and distribution of future
development.  This is important in delineating future sludge
quantities and in locating possible sludge management facilities,
particularly those having large land requirements.  Included in  the
cultural setting is a discussion of the institutional framework
(as related to wastewater sludge management) which attempts to
evaluate the legal, administrative, and technical capabilities of
existing agencies.  Such knowledge is important for assigning
agency responsibility when developing sludge management alternatives
for consideration.  Finally,a discussion of the legal setting high-
lights the existing laws under which a residual waste management
agency might finance, administer, implement, and enforce a
recommended management plan.
                                   -17-

-------
 NATURAL SETTING

      The natural processes dominant in the Study Area are perhaps
 most easily described within the context of the physiographic
 region.  Physiographic regions are generally defined as contiguous
 areas having similar geologic structure and climate that have
 evolved the same general land  forms.   Inherent in this definition
 is the understanding that  it is the interaction between geology and
 climate which defines the  drainage pattern of streams and rivers;
 the topography, types and  locations of soils, vegetation, and wild-
 life; and the distribution of ground  water.   These latter character-
 istics are directly related to the inherent environmental suitability
 of the region for the various sludge  disposal methods.

      The Study Area physiography is also dependent in certain areas
 on the reaction  of  the underlying  carbonate  rocks  (i.e.,  limestone
 and dolomite)  with  the existing humid temperate climate.   Carbonate
 and calcareous rocks are susceptible  to solvation,  particularly
 along fractures and bedding planes.   Over -long periods  of time,
 the subsurface solution  features begin to greatly affect landforms,
 surface drainage, and groundwater availability.   Regions in which
 large-scale  solution occurs are known as "karst" regions.  Within
 the Study Area there are many areas in which karst features (Figure
 IV-1)  are  abundant  along with  the  unique problems  associated with
 such areas (e.g., flooding,  subsidence,  etc.).

      The Study Area lies entirely  within the Valley and Ridge
 physiographic  province.  The Valley and  Ridge province  is a narrow
 belt of faulted  and folded  rocks of Paleozoic age,  extending 1200
 miles (1931  kilometers)  from central  Alabama to  the St.  Lawrence
 Valley.   The region is characterized  by  parallel  ridges and valleys
 which are  only occasionally broken by wind  and water gaps.   The
 Valley and Ridge province in Tennessee is bounded  on the west by
 the Appalachian  Plateau  province,  a low  chain of  folded mountains,
 and on the east  by  the Blue Ridge  province,  a belt of mountains
 composed primarily  of metamorphic  rocks.

 Geology

      The rocks of the Valley and Ridge province  were originally
 deposited  on the margins of  the  interior Paleozoic  sea,  the sediment
 originating  from the erosion of  highlands to the  southeast  and
 northwest.  During  or after  their  deposition, the  Appalachian revolu-
 tion  (i.e., mountain-building  period)  occurred which folded and
 faulted  the 30,000  to 40,000 feet  (9100  to 12,000 meters) of  strati-
 fied rock  and  sediment causing a substantial decrease in  the basin
width.   The compression  of  these rocks resulted  in parallel bands
of rock  extending in a southwest-to-northeast direction.
                                  -18-

-------
                           KNOXVILLE  AND  KNOX  COUNTY

                      CARBONATE  BEDROCK  AND KARST  AREAS
                                                                    Carbonate Rock

                                                                    Sinkhole Area
                                                                                   o
                                                                                   c
                                                                                   ;o
                                                                                   m
SOURCE: Reference IV-16

-------
     The geologic formations present in the Study Area are primarily
limestones, dolomites, calcareous and sandy shales, and sandstones
of early Paleozoic age.  Carbonate rocks underlie approximately 55
percent of  the  land surface with shales and sandstones underlying
40 and five percent, respectively.   These formations are generally
covered by  a mantle of residual soil, mostly clay, which varies
in thickness up to 150 feet (46 meters) (Ref.  IV-1).   The residual
soil or regolith is a product of the weathering of the underlying
bedrock and is  of a much more recent age.  Alluvial deposits of
gravel, sand, and clay of very recent origin have been deposited
along floodplains and terraces.

Climate and Air Quality

     The climate of the Study Area is apparently moderated to a
great extent by the adjacent Cumberland Plateau (a division of the
Appalachian Plateau) and the Blue Ridge provinces.  The Cumberland
Plateau to  the  west has a rain-shadow effect on the Valley and Ridge
province causing annual precipitation to be 10 inches (25.4 cm) less
in the Study Area than that of the plateau region.  The Cumberland
Plateau also acts to reduce the impacts of winter and cold fronts.
The Blue Ridge  province to the east tends to divert hot summer
winds from high-pressure systems off the South Atlantic Coast.

     Precipitation in the Study Area averages about 48 inches
(122 cm) annually including about 12 inches (30 cm) of snow.
Rainfall is fairly evenly distributed throughout the year with the
least rainfall  occurring in September and October.  The frost-free
period for the  area is 215 to 220 days.

     January through March is considered the winter season with
winds predominately from the west and southwest, these wind
directions also occurring during the spring season.  The wind
speeds during these months (January-June) rarely fall below five
miles per hour  [.224 centimeters per second (cms)].  In summer
months the wind speeds are at their lowest, with speeds below five
miles per hour  (224 cms) occurring thirty percent of the time.
During the fall (October through December), the winds are more
directional than any other season,  with speeds lower than five
miles per hour  (224 cms) from the northwest occurring 33 percent
of the time (Ref.  IV-2).

     "In addition to seasonal fluctuations in wind speed and
direction,  there exists pronounced diurnal fluctuations in the
wind.   Daytime winds generally have a southwesterly component,
while nightime winds tend to be from the northeast" (Ref. IV-2).

     In accordance with 40 CFR 51.12(e) published in the Federal
Register of June 18, 1973, states are to identify those areas which
                                   -20-

-------
have the potential for exceeding any National Ambient Air Quality
Standards between 1975 and 1985.  The identified areas are to be
known as Air Quality Maintenance Areas (AQMA's).  Rnoxville-Knox
County was not designated as an AQMA.  Within the Knoxville Standard
Metropolitan Statistical Area (SMSA), the projected particulate
emissions (including Anderson, Blount, Union, and Knox County) for
1975 are 21,541 tons per year (19,542 metric tons per year) and
for 1985, they are projected to be 28,788 tons per year  (26,166
metric tons per year)  (Ref. IV-3).   Pertinent Federal, State, and
local air pollution standards and air quality data for Knoxville
(1974) may be found in Appendix A.

Topography

     The Study Area topography is classified as Open Hills surface
type in the Appalachian Rough Lands  Subdivision  (Ref. IV-4).  This
type of topography is characterized  by 20-50 percent of  the land
being in gentle slopes with over 75  percent of the gentle slopes
being in lowland areas (Figure IV-2).  Local relief ranges from
300-500 feet (91-152 meters).

     The land surface comprises a series of narrow subparallel
valleys and ridges oriented approximately N 55°E.  These are a
result of the folded and faulted nature of the underlying geologic
formations which vary in their ability to resist weathering erosion.
In general, the ridges are comprised of resistant cherty limestones
and dolomites and sandstones, while  the valleys are underlain by
soluble carbonate rocks or shales which are easily weathered and
eroded.  Relief between valley floors and ridge crests is between
180-400 feet (55-122 meters), decreasing slightly from northeast to
southwest.

Hydrology and Water Quality

     The principle rivers draining the Study Area are the Clinch,
French Broad,  and the Holston Rivers.  The latter two join at
Knoxville to form the Tennessee.  The northwestern third of the
area is drained to the Clinch River  (Melton Hill Lake) by Bullrun
and Beaver Creeks.   The remainder of the area is drained to the
Holston and French Broad Rivers  and, from Knoxville downstream,  to
the Tennessee River (Fort Loudoun Lake)  by many small streams
(Figure IV-3.).

     The mean flow of the Tennessee  River at Knoxville is 12,850 cfs
(21,845 cu m/min) of which the Holston and French Broad  contribute
35 and 65 percent, respectively.  The flow of the Holston River
is controlled by Cherokee Dam, 52 miles (84 kilometers)   upstream of
Knoxville,  and that of the French Broad by Douglas Dam,   32 miles
(51 kilometers) upstream.
                                   -21-

-------
K)
fO
I
               036
               I  .  . I  .  .  I
               SCALE IN MILES
                                   KNOXVILLE AND  KNOX  COUNTY
                                        PERCENT  SLOPE  MAP
                                                                               0-3% Slope
                                                                               3-9% Slope
                                                                               > 9% Slope
                                                                                              o
                                                                                              v
                                                                                              m
       SOURCE: U.S.G.S. Topographic Maps

-------
                                  KNOXVILLE AND  KNOX  COUNTY
                                       SURFACE HYDROLOGY
S3
u>
                                                                     HOUSTON
                                                                      RIVER
                                                                     FRENCH BROAD
                                                                            Drainage Basins
                                                                                           i
                                                                                           m
                                                                                           01

-------
      Major flooding of  the Tennessee,  Holston,  and French Broad
 Rivers in the Study Area  has  not  occurred  since the construction
 of Tennessee Valley Authority (TVA)  impoundments upstream and  down-
 stream.   However,  studies conducted  by TVA indicate that such  flood-
 ing is possible in the  future under  certain storm conditions (Ref.
 IV-5) .  Flooding is possible  on many of the sinaj.j.er tributary  streams
 under many winter  storm and thunderstorm conditions.   Figure IV-4
 shows those areas  most  prone  to flooding and includes sinkhole
 areas (karst features)  which,  because  of their  importance in local
 drainage, could under certain circumstances contribute to flooding.

      Annual runoff in Knox County averages about 19 inches (48 cm)
 with 7-9  inches (18-23  cm) passing through the  groundwater system
 before discharging to streams.  Evapotranspiration processes return
 the  remaining  29 inches  (74 cm) of annual  precipitation  to the
 atmosphere  (Ref. IV-6).

      The  occurrence  of ground water  in the Study Area is  controlled
 by fractures in the  underlying  rocks.   These rocks have  little pri-
 mary  porosity  and  permeability, but  fracturing  due to folding and
 faulting  and solvation along bedding planes have  created a secondary
 porosity  and permeability.  In  carbonate and  calcareous  rocks the
 fractures are  enlarged by  percolating  ground  water which  dissolves
 calcium carbonate  from the  rock.  The  area of active  solvation with-
 in carbonate rocks is generally within 300 feet (91 meters)  of the
 land  surface.  Below this  depth fractures  are small and precipita-
 tion  of dissolved  calcium  carbonate  occurs which decreases the
 secondary porosity and permeability  (Ref.  IV-1).

      There  is  no area-wide aquifer underlying the Study Area which
 will  yield  predictable, large supplies  of  ground  water to  wells.
 In general, areas underlain by carbonate rocks  have the most ground-
 water storage  and areas underlain by shale  and  sandstone  the least.
 Much  of the groundwater storage in carbonate  rock areas is  in the
 residual  soil  overlying the bedrock,  which  can  be  as  much  as 150
 feet  (46 meters) thick.  However,  the permeability  of  this material
 is low causing it  to act as a recharge  reservoir  for  the bedrock
 system.   The bedrock system has limited  storage but high  transmission
 capacities along fractures and bedding  planes.  The yield  of springs
 or wells  in these areas is dependent on  the number  and extent of
 fracture  systems intercepted.

     Domestic  supplies of ground water  [5-10  gallons  per minute
 (gpra)] [0.32-0.63 liters per second  (I/sec)]  are  available to
wells in virtually all parts of the  Study Area.   Well yields sub-
 stantially greater than that required  for  domestic  purposes occur
much  less frequently for the reasons stated above.
                                   -24-

-------
i
ts)
Ui
                                     KNOXVILLE  AND  KNOX  COUNTY
                                           FLOOD-PRONE  AREAS

                                                                        Area Of Maximum Probable Flooding
                                                                        Area Flood-Prone Because It
                                                                        Contains Abundant Sinkholes
       SOURCE. Reference IV-5

-------
      A  review  of  the  303(e)  plans  developed  for  the  Study Area
 indicates  that  the majority  of  municipal  and  industrial  dischargers
 of  concern in  this study  are located  on water-quality-limiting
 stream  segments (Ref.  IV-6,  IV-7,  IV-8, and  IV-9).   In addition
 the 303(e)  plans  all  assumed that  "by 1980 all persons living with-
 in  an urbanized area  will be served by a  waste treatment facility"
 (Refs.  IV-7, IV-8, and  IV-9).   Knoxville-Knox County SMSA and, in
 particular,  the Study Area for  this report being essentially in
 urban character (Ref.  IV-10), it was  assumed  (see  also Chapter V)
 that  the population within the  Study  Area will be  sewered and the
 wastewater  treatment  facilities will  meet, at the  minimum,  discharge
 standards  promulgated to  ensure compliance with  stream standards for
 water-quality-limiting  segments.

      In accordance with the  Water  Quality Control Act of 1971,
 Chapter 164 Public Acts of 1971 as Amended, Sections  70-324 through
 70-342, Tennessee Code Annotated,  the  Tennessee  Water Quality Control
 Board and  the Division of Water Quality Control  are  seeking the
 achievement of water quality conditions necessary  to meet all the
 reasonable and necessary water needs  of the people of the basin and
 to  provide the greatest possible net  benefit  to  the  region.

     As a part of the overall water quality goal, specific water
 quality criteria have been established for all streams within the
 State of Tennessee.  The  "General  Water Quality  Criteria for the
 Definition and Control of Pollution in the Waters of Tennessee"
 were  adopted on May 26, 1967 by the Tennessee Stream Pollution
 Control Board and were amended and readopted  on  October  26, 1971
 by  the Tennessee Water Quality Control Board with subsequent
 amendments on December 14, 1971, and  October  30,  1973.   This Board
 succeeded and replaced the Tennessee  Stream Pollution Control
 Board as required by the Water Quality Control Act of 1971.

     The Water Quality Criteria vary  according to each of seven
 recognized reasonable and necessary water uses:   domestic raw water
 supply, industrial water supply, fish and aquatic life,  recreation,
 irrigation, livestock watering and wildlife,   and navigation.  The
Water Quality Criteria are given in Appendix  B.   Tennessee's
Water Quality Standards have been  approved by the Water Quality
Office of EPA (Refs.  IV-7, IV-8, and  IV-9).

Soils

     There are  60 kinds of soil represented in the Study Area
 (Ref. IV-11).  These soils vary greatly in their  characteristics
which are dependent to a great extent on parent  material, relief,
and time, and to a lesser extent,   on  climate  and living organisms.
In general, the most developed and thickest soils occur in the
                                   -26-

-------
valleys where the rate of erosion is least and,  consequently,  the
time for soil development the greatest.   The parent material in
the valley areas is chiefly residuum (the clay and silt remaining
after solution of the underlying carbonate rocks) with some over-
lying alluvial (stream) and colluvial (gravity slope) deposits.
The soils formed in the residuum are generally poorly-drained with
low to moderate fertility.   Those soils  formed in the alluvium
and colluvium are well-drained and highly fertile.   The alluvial
and colluvial soils are the prime agricultural soils in the Study
Area; the residuum soils being more suited for hay and pasture.
The locations of these soils in the Study Area are shown in Figure
IV-5.
      The  soils  formed  near  and along the  ridges  are  generally  thin,
poorly  developed,  and  infertile.   This  is primarily  due  to  the
higher  rate  of  erosion in  these  steep-sloped  regions which  removes
the  soil  almost  as fast as  it  is  produced.

Flora/Fauna

      Information characterizing  the flora and fauna of the  Study
Area was  not found during  the course of this  study in detail
sufficient  for  use in the  Methodology.  The existing floral and
faunal  systems  generally found in the Valley  and Ridge province
today are primarily those  of oak forest (Ref. IV-11).  In uncut
areas,  red and white oak predominate on intermediate slopes and
chestnut  oak on higher rocky slopes and crests.   The valley areas
are predominately white and red oak with hickories and tulip
poplars.   Some of the valley areas might have been natural prairie
at one time.  The wildlife associated with  such vegetated areas
would include numerous varieties of birds and small mammals,
 including deer, fox, raccoon, and oppossum.

Mineral Resources

      The  mineral resources  of the Study Area  are related primarily
to the  carbonate rocks. Carbonate rocks  are  important as sources
of crushed  stoae, agricultural limestone, lime,  cement,  and dimen-
sion stone.   Carbonate rocks near the town  of Mascot are the host
for  zinc  deposits which are mined primarily as  sphalerite concentrates.
Shale is  also quarried for brick and lightweight aggregate manu-
facture.   The locations of  active quarries  and mines are shown in
Figure  IV-6.  On a regional basis, the  Study  Area  is located  only
several tens of miles east of extensive coal  strip-mining operations
which could  provide feasible reclamation alternatives for sludge
disposal.

CULTURAL  SETTING

    .  Just as it is unwise to plan sludge disposal management
ignorant  of  the natural setting, so is  it equally unwise to develop
                                    -27-

-------
i
ro
co
                               KNOXVILLE  AND  KNOX  COUNTY

                     PRIME AND  SECONDARY  AGRICULTURAL  SOIL  AREAS
      V

  ?. . f.  .1
  SCALE IN MILES

      J±.^
  C I ,
»


i
             *r
                                                                   Prime Agricultural


                                                                   Secondary Agricultural
                                                                                   3
                                                                                   CD
      SOURCE: Reference IV-II

-------
o
                                       KNOXVILLE  AND  KNOX  COUNTY
                                              MINERAL  RESOURCES
    LEGEND
  x Active Quarry Or Mine
  • Prospect
 © Mill Or Plant
 Zn Zinc
  L Lime
 LS Limestone
  M Marble
  C Cement
CSS Crushed Sandstone
  sh Shale
  B Brick
 Pb Lead
 SG Sand And Grovel
 LA Light Aggregate
         SOURCE: Reference IV-17

-------
and evaluate disposal alternatives without considering the exist-
ing and projected cultural setting and values.  Sludge disposal
alternatives compete with other public and private interests
for economic and environmental resources, whether it be for space
in a sanitary landfill or the money for building and operating an
incinerator.  The following sections are intended to present in
brief form the cultural setting as it exists now and, possibly
more important, what it is desired/projected to be.

Evolution of the Knoxvi^l_le-Knox County Area

     The primary driving force in the socioeconimic development of
the Study Area has been its location at  the navigable headwaters
of the Tennessee River.  This natural access to cheap bulk trans-
portation has led to a concentration of wholesale, retail, banking,
transportation, and manufacturing services, (primarily located in
and adjacent to Knoxville) which serve eastern Tennessee and parts
of Virginia, Kentucky, and North Carolina.  With its evolution
from an area primarily devoted to developing local agricultural,
forest, and mineral resources to one of  providing regional services
(not dependent, to any great extent, upon local natural resources),
a different set of environmental needs and values related to urban-
ization developed within the Study Area.

     Initially, the urbanization process occurred north of and
adjacent to the upper Tennessee River in what is now the central
core of Knoxville.   Urban development through the 1950's occurred in
areas adjacent to past development with  the steep ridge areas left
undeveloped.  Post-1960 development occurred  in rural areas several
miles from the city limits primarily as  medium and low density
residential developments.  This recent development has led  Lo
environmental quality problems related to the use of septic tank
disposal in clay and/or thin soil areas  (i.e., groundwater pollution,
drainfield seepage, etc.).  In addition, suburban development has
resulted in competition for prime agricultural land which  in many
cases  is susceptible to flooding (Figures 1V-4 and IV-5).

     Critical to its function as a regional center,  transportation
networks of all types are available within the Knoxville-Knox County
area.  Highway accessibility has been increased with the  completion
of Interstate Highways 40, 75, and 81.   Local and surrounding
area traffic is handled by several additional Federal and  State
highways.   The Louisville and Nashville  Railroad and the  Southern
Railroad operate rail  freight facilities in Knoxville providing
rail service in virtually all directions.  The Tennessee  River  is
presently navigable  from Knoxville  to its confluence with  the
Ohio River.

     The economy of  the  Study Area  is diversified with manufacturing
the largest  single  employment category.  Trades, government, and
                                   -30-

-------
services are also significant economic factors.   The agricultural
economy is characterized by numerous small farms [about 1800 farms
with an average size of 73 acres (30 hectares) in 1969] with a
long-term decreasing trend in the number of farms and the acreage
fanned (Refs.  IV-7,  IV-8,  and IV-9).

      The population of the Study Area has grown from 74,000 in 1900
 to 276,000 in 1970.   The  growth rate per decade has been fairly
 constant.   A  current population estimate made by the Metropolitan
 Planning Commission (MFC) in July,  1974 is 303,379 of which 59
 percent live  within the city limits of Knoxville.   Figure V-4
 shows the distribution of the estimated 1975 and 1995 populations
 per drainage  area.   Primary population centers  outside Knoxville
 are to the north, west, and southwest of the city  limits.

      The existing  land use (Figure  IV-7) for the Study Area outside
 Knoxville has major residential developments west  and north of the
 city limits adjacent to major highways.   Industrial areas are located
 primarily within Knoxville and adjacent to railroad lines.  Pre-1960
 development,  particularly residential, occurred in a ring-like
 pattern centered around the central core-area of Knoxville.  Post-
 1960 residential and industrial development has occurred in a much
 more dispersed manner. Many medium and low density residential
 projects and  large  commerical and office parks  have been built in
 formerly rural areas,  particularly  in west Knox County.  The
 northern portion of Knox  County has had additional suburban
 residential development on a smaller scale.  East  Knox County has
 not experienced much development since 1960 with the exception of
 the Forks-of-the-River industrial area.   Recent development in
 southern Knox County has  been limited to some low density residential
 developments.

 The 1990 General Plan for Knoxville-Knox County

      The primary goal of  the 1990 General Plan  for the Study Area
 as delineated by the MFC  is to provide the greatest number of people
 with public services and  facilities on a cost-effective basis.  This
 is most easily accomplished by filling in currently sparsely populated
 areas with future  new development.  Figure IV-8  snows the 1990
 land use plan which, when compared  to the existing land use map
 (Figure IV-7), reveals several assumptions/desires of the MPC in
 regard to the future development of the area:

      "Most of the  urbanized areas will remain in their present
      uses and character,  except where urban renewal or other
      similar  programs can change the economic equation suffi-
      ciently  to allow redevelopment.

      The major elements of the transportation system will
      remain essentially intact.

      Location of additional development will be greatly
      influenced by  topography and transportation corridors.


                                    -31-

-------
                                KNOXVILLE  AND  KNOX  COUNTY
                                      EXISTING  LAND  USE
                                                                             Recreotionol

                                                                            ] Urban/Suburtxin Residential
                                                                      F"^ •-- -- •- •~~^~
                                                                             Industrial
                                                                                                    5

                                                                                                    I
SOURCE: Knoxvilie-Knox County Metropolitan Planning Commission

-------
i
u>
UJ
I
                                      KNOXVILLE  AND KNOX  COUNTY

                                           1990  LAND USE PLAN
                                                                                Recreational

                                                                                Urban/Suburban Residential


                                                                                Industrial
                                                                                                       33
                                                                                                       rn
                                                                                                       i
                                                                                                       ao
       SOURCE: Knoxville-Knox County Metropolitan Planning Commission

-------
     Some manufacturing uses will be located outside of the
     city with regional services and distribution facilities
     concentrated within the city."  (Ref.  IV-13).

 In addition to allowing for more extensive and cost-effective
 public services, increasing the density of development would
 preserve land for other uses such as agriculture and recreation.

     Population projections (Figure V-4)  indicate  three general
 areas within the Study Area which are expected to absorb most of
 the new development through 1990.  West Knox County is expected
 to accommodate the greatest amount of development.  North and
 south Knox County are expected to absorb the bulk of the remaining
 development potential with new development in north Knox County
 being a greater certainty.

 Institutional Characterization

     Another important parameter to be considered in the general
 feasibility of a sludge management alternative is the number of
 implementation alternatives practically available in the Study
 Area.  It would show poor foresight to develop disposal alternatives
 which are compatible with the environment and the projected land
 uses of an area but infeasible to implement for political or
 financial reasons.  And, although there are a large number of
 possible financial, operational, and political alternatives, only
 a limited number would apply to any given area.  The following
 discussion is intended to delineate the existing wastewater
 agencies operating in the Study Area and their financial, legal,
 and administrative capabilities, and assess the institutional
 possibilities for various types of disposal alternatives.

     Currently several wastewater management agencies are operating
within the Study Area.  The largest such agency is the Public
 Service Department of the City of Knoxville which services about
 70 percent of the city population.  Three utility districts
 (autonomous service areas created within the county) provide sewer
and treatment services to certain developing communities in Knox
 County.  In addition, Knox County owns and operates an industrial
park wastewater treatment facility at Forks-of-the-River.

     The Public Service Department (PSD)  has been responsible for
 the sanitary sewer system and treatment facilities in the City of
Knoxville since 1923.  The division of the Department currently
responsible for the day-to-day operation of these facilities is
 the Wastewater Control System, established in 1953.   Policy
decisions for the sanitary system are made at the Department level.
The Department has all the legal powers necessary to perform its
                                  -34-

-------
functions (which would include sludge disposal)  as provided in the
Tennessee Annotated Code and Knoxville city charter (Ref.  IV-10).
Among its legal prerogatives are the ability to  enter into contracts
with other municipalities or private corporations outside  its juris-
diction in order to provide adequate service and the power of eminent
domain, which under certain circumstances can extend beyond the
corporate limits of the city.  The Department has the power to issue
general obligation bonds and can determine sewer rates (subject to
City Council approval).  It has received Federal and State funds  in
the past and, owing to inadequate and malfunctioning treatment plants,
is ranked high on the priority list for Federal funding.   Revenues to
repay bonded indebtedness and system operating costs are generated
through user charges, improvement fees, and industrial surcharges.
If these revenues are not enough to meet expenses, funds can be
obtained from the general tax fund of the city,  although this has
never been required in the past.  Because city taxes guarantee the
bonds, the Department has an "A" bond rating.  The Department has
an established record for providing diverse public services and
would have some of the technical expertise in-house required to
design and operate a sludge management program.

     The three utility districts providing sewer  service and treat-
ment to areas of Knox County are West Knox, Hallsdale-Powell, and
First Utility  (Figure V-2) .  The sewered populations served by
these districts are small although they are expected to increase
substantially in the future  (see previous section Hydrology and
Water Quality).  In the past, the utility districts have operated
relatively autonomously, although they are participating in  recent
"201" and "208" planning.  Two of the utility districts are  currently
coordinating with the PSD in order to sewer parts of their districts
to the city  system.  Utility districts do not have  the power  to
levy taxes and must rely on revenue bonds, short-term loans,  and
Federal assistance for financing capital  improvements.  Because of
their snuill  size and inability to tax, utility  district bond  ratings
are  low  (BBB or less) which means high interest  rates.  Utility
districts do have most of  the other  legal powers  given to municipali-
ties, such as  eminent  domain and entering  into  contracts as  stated
in the Utility District Act  of 1937  of the  State  of  Tennessee
(Ref. IV-10). The technical and administrative capabilities of
the  districts  are  limited,  such  services  being  normally provided
by outside consultants.

     Knox County has only  recently  (1967)  provided  sewer  service
and  treatment  with the Forks-of-the-River industrial park  facility.
Traditionally, most  counties  in  Tennessee have  avoided providing
such services, hence  the  creation of the  utility districts.   This
has  been  in  accordance with legislative  and constitutional limita-
tions upon  the power  and  nature  of  county government.   In 1961,
however,  a public  act  of  the legislature  specifically  gave the
                                   -35-

-------
counties the right to provide certain urban services including
sanitary sewer service (Tennessee Code Annotated, Sec. 3-1612).
There are tentative indications that the County is evolving a more
responsible County-wide awareness which could lead to greater
County participation in services and planning in the future.  For
example, the Knox County Court, in 1971, created the Knox County
Environmental Commission with a goal of bringing County-wide
water services, sewage disposal, and solid waste disposal under a
single agency (presumably the County).   Currently the county is
limited in its ability to administer any of these functions.
Although it has MFC to perform technical planning duties, the
County does not have a large technical staff available.

     From an institutional perspective, then, the Study Area can
be described as a large municipal agency (PSD) surrounded by
several small utility districts within a county matrix.  Tradi-
tionally, these agencies have operated independently with little or
no interaction.  In recent years, however, the PSD (City of Knox-
ville) and the First Utility and West Knox utility districts have
cooperated in providing sewer service to portions of west Knox
County, thus establishing a precedent for interagency cooperation.
At the same time, a metropolitan attitude has been evolving within
the Study Area via various civic groups, planning agencies, and
City and County officials.  An initial step in this perspective
change is the growing awareness within Knox County of the need
for the County to participate more extensively in the provision
of public services and in the planning and direction of future
development.  These functions could, however, be usurped by
individual developers and the utility districts which do not and
could not have an area-wide perspective or concern for their impacts
on County development.  As a result two desirable but conflicting
institutional processes are evolving within the Study Area:
(1) greater interagency cooperation among existing agencies; and
(2) growing pressure for the County to enlarge its responsibilities
and participation in the future development of the area.  The
latter increase in power by the County would be at the expense of
the utility districts.

     From a sludge management perspective, the institutional setting
is currently limiting in regards to metropolitan-level solutions.
The utility districts can not be required to participate in a metro-
politan solution.  The financial instability and inherent limited
financial capabilities of the utility districts  (i.e., small size,
no taxation power) would almost certainly deter  their participation
in an expensive^ but environmentally-and socially-sound alternative.
Moreover, it is conceivable that a utility district would become a
principal adversary in the implementation of a large land applica-
tion system within its jurisdiction, not necessarily for environ-
mental or cost reasons, but based on its need/desire to encourage
                                 -36-

-------
residential development within its area in order to finance the
existing system and future improvements.   As a result,  a sludge
management alternative incorporating a metropolitan solution would
need to be both economically advantageous to a utility  district
and noninterfering with regard to its development needs in order
to expect the utility districts cooperation.

LEGAL SETTING

     The setting in which residual waste management [including both
solid waste and municipal wastewater treatment plant sludges, which
are considered a "special" solid waste (see  following discussion
under The Solid Waste Disposal Act, TCA 53-4302 et seq.)] could be
addresses from a legal standpoint is also a concern in the planning
and management of any disposal or resource recovery plan.  The
following information has been provided by the East Tennessee
Development District (ETDD) which covers 26 counties of east
Tennessee and 3 counties of north Georgia (Ref. IV-14).

     In order to determine the available options for regional
waste management it is necessary to examine the laws of Tennessee
pertaining to solid waste, intergovernmental cooperation, and  the
formation of other corporate and municipal type entities capable
of waste management.  Solid waste collection and disposal is
covered under a number of different sections of the Tennessee
Code Annotated (TCA).  The two most significant Acts which relate
to the institutional arrangements for a resource and energy
recovery system are the Garbage and Rubbish  Collection and
Disposal S ervice_s__Act_, TCA 5-1901 et seq., which authorizes
governmental bodies and joint efforts of the same  to collect
and dispose of solid wastes; and the Tennessee Solid Waste
Disposal Act, TCA 53-4302 et seq., which provides  for grants  to
governmental bodies to aid in the proper disposal  of solid waste
and loans for the construction of resource and energy recovery
systems.

     In addition to these Acts, the Utility  District Act, TCA
6-2601 et seq.; the IndustrialJJevelopment Corporation Act,
TCA 6-2501 et seq.; and the Corporations laws at TCA 48  have
potential use in the development of management  possibilities
for a resource and  energy  recovery  system and related  industrial
development.  A brief  discussion of each of  these  laws  follows.

The Garbage and Rubbish Collection  and Disposal  Services  Act
(TCA 5-1901 et seq.)

     Under  this Act,  the  counties  of  the State  of  Tennessee
are authorized to  provide  garbage  and  rubbish  collection services
                                   -37-

-------
and  to provide disposal services to the entire county or to
special districts within the county.  The Act contains an inter-
local agreement section which gives counties the option of enter-
ing  into cooperative agreements for either the collection or the
disposal of solid waste.   (TCA 5-1901).  This section of the Act
is broad in that it allows counties to enter into such agreements
with other counties or with any other governmental unit or
agency, Federal, State, or local.  It includes municipalities,
towns, utility districts, and improvement districts within the
County , and also allows contracting with private contractors
for  collection and/or disposal, or any other entity which provides
either or both services.

     The interlocal agreement section of the Garbage and Rubbish
Collection and Disposal Services Act specifically gives the
cooperative management entity the power to raise revenues in any
and  all ways that the county can raise revenues, such as by
revenue bonds, by taxes levied in specific districts, by
combinations of revenue bonds and income from facilities operated
by the several jurisdictions, etc.  For the purposes of the
institutional arrangements of a resource recovery facility in the
Study area, this section could be used to form either one entity
to oversee the entire operation or groups of cooperative entities
to construct and manage transfer stations, to operate regional
sanitary landfills,  and  to  coordinate  collection.

     The interlocal agreement section of the Act would give a
stronger basis for such cooperative efforts than would the
Interlocal Cooperation Act. TCA 12-801 et seq.  The Interlocal
Cooperation Act is vague about power to raise revenues for the
operation of a cooperative effort.  This vagueness could result
in delays while an agency formed under it is tested in court action.
The Des Moines Solid Waste Agency was  formed under an Interlocal
Agreement Act very similar to that of  the Tennessee Code Annotated,
and  the Supreme Court of Iowa found that additional legislation
would be required to give that agency  the power to raise revenues
(Goreham V. Des Moines,  188 NW 2nd 860).

     At least two possible arrangements exist and would be work-
able under TCA 5-1901 et seq. (1)  The  local  government  could
contract with the provider of the recovery facility on an individual
basis for disposal of solid waste.  Where the amount of waste
generated by a specific local government is insufficient to make
the transportation from that county alone economically feasible,
a cooperative unit of several local governments could be formed.
That unit could contract in turn with  TVA,  the  City of Knoxville,
or any other provider of a resource/energy recovery facility
for disposal of solid waste.   (2)  Another possibility would be
for the entire Study Area to form an agency for the construction
                                 -38-

-------
and management of transfer stations necessary to store and prepare
waste for transportation to a resource/energy recovery facility,
and for the acquisition and management of regional sanitary land-
fills for waste unsuitable for recovery and as alternative
disposal sites in the event of facility shutdown.  (A private
corportation could also participate at any of the stages of the
operation; that is, it could do the collection, construct and
manage the transfer facilities, handle the transportation, or
construct and operate the recovery facility.)

Solid Waste Disposal Act, (TCA 53-4302 et seq.)

     This Act as amended in 1974 will also be very beneficial
in developing the institutional arrangements for a solid waste
system with resource/energy recovery.  Grants of up to one
dollar ($1.00) per capita are available from the State for each
incorporated city or town or for each county to be used in
operating and maintaining state approved disposal facilities.
Cooperative efforts are encouraged as part of the specific
legislative intent of the grant section of TCA 53-4302 et seq.
"It is the further intent of this section to reduce the number
of these optimum feasible solid waste disposal facilities or
systems to the absolute minimum by vesting in the department
(of Health) the authority to insist upon maximum cooperation
among local instrumentalities as a prerequisite to receiving
these special minimum-level grants" (TCA 53-4318).

     The grant funds are available for the purposes of "Acquiring,
establishing, constructing, altering or operating solid waste
disposal facilities or systems or for the purpose of purchasing
equipment therefor, or for the service of debt incurred therefor"
(TCA 53-4317).  These funds may be provided either directly to the
cities,  towns, and counties involved  or  they  may  be  provided  by
contract with one or more other political subdivisions of the
State as authorized by the Interlocal Agreement Act.  They
may also go to an approved private solid waste disposal system
or facility that is certified as eligible by the Department
of Health.

     The Solid Waste Disposal Act also gives the Tennessee
Department of Public Health authority to approve grants and loans
from the Federal government or other sources to local governments
(TCA 53-4309).
                                    -39-

-------
      The  1974  amendment  to  the  Act  provides  for  resource/energy
 recovery  facility  loans  from the  State.   (TCA 53-4322 et seq.).
 This  section provides  that  the  "State  of  Tennessee  is hereby
 authorized to  make loans to any municipal corporation or county
 for the construction of  energy  recovery facilities  and/or  solid
 waste resource recovery  facilities.  Such loans  shall be made
 from  the  proceeds  of State  bond sales  authorized pursuant  to
 implementing acts  of the State  of Tennessee" (TCA 53-4323).
 Limits of indebtedness imposed  by other laws of  the State  are
 not applicable to  loans  under this  Act (TCA 53-4336).

      Loans under this  section of  the Act  can be  supplementary
 to grants made under the other  provisions of the Act.   Loans are
 available to special districts  of the  State empowered to provide
 solid  waste  disposal service  as well as to municipal corporations
 and countiesi

     Pertinent  sections  of  the  regulations governing solid waste
 processing and  disposal  in  Tennessee may  be found in Appendix D.

 The Utility District Act. (TCA 6-2601 et seq.)

     Solid waste collection and disposal  are among  the  services
 that can be performed by utility  districts in Tennessee (TCA
 6-2603).  The potential for using  utility  districts  for  the
 purpose of coordinating  local governments in solid waste collec-
 tion and  disposal has not been  adequately explored  in Tennessee.
 A factor  that supports utility  districts  in waste management
 is their ability to  charge customers for  actual  services.  This
 would  allow local governments to  remove solid waste collection
 and/or disposal from their ordinary expenses and  actual costs
 could be billed to the customer-user in the same  manner as other
 utilities are now billed.

 The Urban Type Public Facilities Act,  (TCA 5-1601 et seq.)

     This Act used with  the Interlocal Cooperation Act, supra,
 created the Tellico Area Service  System in Monroe and Loudon
 Counties  for development of the Tellico Area and  the Timberlake
 Community.  It  gives the system utility functions including the
 incineration or other disposal  of solid waste.    However special
 authorization is necessary for  the addition of each new service.
 It is  limited to the two counties but  could be expanded or
 other  counties  could form similar service systems if necessary.

T-he Industrial  Development Corporation Act. (TCA 6-2801 et  seq.)

     This  Act provides  for the issuance of bonds to raise revenue
                                -40-

-------
for industrial development.  The revenues can fund nonprofit
corporations established to increase industry.   Its purpose is
to develop job potential through industrialization.  It also
seems to provide for loans to existing industry for acquisition
of pollution control devices necessary to meet  State standards.
It might prove useful in developing resource recovery related
industry and in ultimately financing pollution  control equipment
for a resource/energy recovery facility.   Its use for the latter
appears somewhat dubious because of the lack of clarity of those
provisions of the Act.

Corporations,  (TCA 48-102 et seq.)

     The Corporation Act of the State of Tennessee has been
used at all  stages of solid waste collection and  disposal,
and corporations chartered by this  State and others  are  engaged
in each area of activity at this time.  Two landfills  in the ETDD
area are owned and operated by private for-profit corporations.
Transfer stations are operated in conjunction  with one of the
landfills.   Collection  is  carried on by large  numbers  of
corporations in the grant  area, ranging from the  largest cor-
poration in  the Nation  involved in  the solid waste  industry,
Browning Ferris Industries, Inc., to small  family corporations
operating one or two  trucks for collection.

     In Nashville, Tennessee, the Nashville Thermal  Transfer
Corporation  is chartered by the State  of  Tennessee as  a  not-for-
profit corporation whose purpose is to provide low-cost  district
cooling and  heating services  for downtown Nashville.  The Nashville
Electric  Service and  the Nashville  Gas Company were  initially
approached with the idea of providing a central heating  and
cooling plant for  the area, but because  a referendum would have
been required to give them the authority  to do this, the not-
for-profit  corporation  was formed  so that the  work on the system
could be  begun within a necessary  time frame.

     The  system proposed  by I.C. Thomasson  and Associates for
Knoxville (see also Chapter V) is similar in design  to the
Nashville Thermal  Transfer Facility.  While it could be establish-
ed as  a not-for-profit  corporation, the  proposal calls for it  to
be owned  by the city and financed  through either revenue or
general  obligation bonds.

Additional Legal Considerations

      In  additional to the laws  discussed above and earlier sections
of this chapter (see Climate and Air Quality and Hydrology and
Water  Quality),  there are two legal considerations  that impact
on sludge management for Knoxville-Knox County.  Ordinance No.
 5819 of the City of Knoxville,  effective 8 November, 1974,
                                -41-

-------
established rules and regulations governing the wastewater control
system of the city.  Normal domestic wastewater, as defined in
Article III of the ordinance is as follows:

     "Normal Domestic Wastewater" shall be regarded as
     "normal" for Knoxville.  Normal domestic wastewater
     shall contain a daily average of not more than 2,500
     pounds (300 Milligrams per liter) of suspended
     solids; not more than 2,000 pounds (240 Milligrams
     per liter) of B.O.D.; and not more than 471 pounds
     (50 Milligrams per liter) of grease and oil, each,
     per million gallons.

Industrial discharges to the City sewer system must either pretreat
their wastes to domestic wastewater quality levels prior to
discharge or pay an extra strength surcharge (Articles IV, Section
8, Paragraph G-l and Article IV,  Section 6, Paragraph C).   In
addition,  Article IV,  Section 8,  Paragraph H establishes waste-
water discharge criteria which include heavy metals such as
cadmium,  iron,  chromium, copper,  zinc,  and nickel.

     As also noted in Chapter V of this study,  it was assumed, due
to a lack of data, that future industrial discharges to the City
sewer system would be comparable,  in terms of strength, to domestic
sewage.  It should be pointed out that the present extra strength
surcharge rates appear both low in terms of dollars charged for
pounds in excess and lacking in ability to consider excess heavy
metals in the surcharge.  Thus, the industries may not presently
have a sufficient economic  incentive to provide pretreatment
facilities capable of heavy metal removal.  If sludge disposal
options are selected which  are sensitive to heavy metal inputs
(e.g.,  land application systems),  the City may be required, for
operational concerns in these options,  to provide stricter heavy
metals discharge standards  and extra strength surcharges based
also upon heavy metals.  This can be done by Article IV, Section
8, Paragraph H as cited below;

     "No statement xn this  ordinance is intended or may
     be construed to prohibit the Director from establish-
     ing specific wastewater discharge criteria more
     restrictive where wastes are determined to be harmful
     or destructive to the facilities of the Waste Water
     Control System, or to create a public nuisance, or
     to cause the discharge of any treatment facility
     operated by the Waste Water Control System to violate
     effluent or stream quality standards imposed or as
     may be imposed by the Tennessee Department of Public
     Health and/or the United States Environmental
                                -42-

-------
      Protection Agency, or  to exceed industrial effluent
      standards for  discharge to minicipal wastewater
      treatment systems as imposed or as may be imposed
      by  the  Tennessee Department of Public Health and/or
      the United States Environmental Protection Agency."

      Zoning  ordinances for 'both the City of Knoxville and Knox
 County provide restrictions as to the uses of various types of
 lands within their  respective boundaries.  The existing and
 proposed land maps  for the  Study Area as noted earlier in
 this chapter were developed by MFC and considered the various
 applicable zoning ordinances.  The evaluation of potential
 disposal options utilized these maps and thus, indirectly,
 zoning ordinances  (see Chapter VI, Table VI-2 of this report).

     The  issue of eminent domain  (see under Institutional
Characterization)  has been addressed  in a recent  publication
(Ref. IV-15). As noted in this  publication,  Article  1,  Section
21 of the Tennessee Constitution  allows the taking  of private
property  for  public use only upon payment of just compensation
to the owner thereof.  Just  compensation is satisfied by the
payment of the fair market value  of the property  actually
taken. To determine the  fair market  value,  the Circuit  Courts
(under which jurisdiction over  eminent domain proceedings  is
vested by statute unless  the Chancery Courts acquire jurisdiction
over a matter pecurlarly  cognizable such as to assess damages
in a suit originally brought to avoid a contract  or to reform
a deed) must  assess all available uses and capacities to which
the property is adaptable and all the available uses to which
it might  be applied given its size,  zoning, location, and
condition.

     If only partial taking of  a  landowner's tract is involved,
the landowner is entitled to recover the fair market value of
the property actually taken, to which will be added by statute
(TCA, Title 23, Sections 1414 and 1537), damages incidentally
done to the residue by reason of the taking, less the value of
any benefits accruing thereto by reasons of the proposed improve-
ment.  By definition, incidental damages to the residue are
allowable only to a property owner some part of whose land
was actually  taken, and do not cover compensation for ajoining
or abutting owners no part of whose land is actually taken for
the  improvement.  The following have been held compensable as
incidental damage to the residue of property taken: noise, soot,
and  inconvenience created by the operation of a railroad;
obstruction of view by a highway embankment within the right-
of-way;  change of grade in a municipal street, reasonable
apprehension of danger from inherent and unavoidable defects  in
                                 -43-

-------
 the improvement;  and  loss  of  access  to  abutting  street.   In
 addition,  reasonable  expenses of  removing  and  reinstalling
 fixtures,  moving  expenses  for a distance not  to  exceed  ten
 miles,  cost  of  amortizing  the remaining principal  of a  mortgage
 or  deed of trust  at a rate not to exceed nine  percent are also
 included as  incidental damages that  may be recovered.

      The condemnor is entitled to off-set  against incidental
 damages the  value of  any benefits accruing to  the  residue
 by  reason  of the  improvement,  but is not entitled  to offset
 any general  increase  or advance in the  value of  the residue
 occasioned by the construction of the improvement.

      Following  proper procedure (i.e.,  determination of juris-
 diction, petition, filing  of  notice, and deposit of amount
 of  damages the  condemnor determines  as  due the owner for which
 he  can  seek  legal remedy under equity), the City of Knoxville
 of  Knox County  can proceed under  its powers of eminent  domain
 (specifically, water works and sewers TCA  6-1701,  et seq.) to
 obtain  lands  necessary  for ultimate disposal of  sludges derived
 from  such  works.  As discussed above, it would appear that the
 least costly  means of  acquiring such property would be  the
 acquisition  of whole property and not leaving in an owner's
 possession residue property which  is part  of a disposal site.

     The City of  Knoxville/Knox County might also wish  to consider
 leasing  rather  than purchasing the land.   The City currently is
 under a  lease agreement for the sanitary landfill located near
 Rutledge Pike and therefore has prior experience and legal
 capabilities  in such arrangements  (Ref.  IV-18).

     The disadvantage of utilizing a lease arrangement  for land
 application systems is that, unlike purchase and outright land
 ownership where the purchase price can be  shared 75 percent by
 Federal funding with State and local share of only 25 percent,
 the lease payments would be considered an  operating expense to be
borne totally by  the local area.   Thus,  prior to evaluation of a
 land-oriented sludge management plan, the  true costs of leasing
versus amortization of the 25 percent capital expense of purchase
must be compared  to determine the  most cost-effective financial
arrangement.

     In addition,  care must be excerised in drawing up the lease
arrangement to protect the legal  interests of the lessor from
possible suits brought against the lessee  for improner operation
of the land site leading to off-site environmental degradation.

     Land application programs require site preparation and design
 features (contouring,  dikes,  berms, underground collection systems)
                                -44-

-------
to prevent run-off from entering nearby water courses.  The
design and construction costs of these features are quite high,
generally greater than the purchase costs of the land itself.
In the development of sludge management plans for Greater Chicago,
the Metropolitan Sanitation District looked at purchase versus
leasing of suburban lands south of the city.  It was noted that
"since the investment in site preparation is large relative to the
purchase price of the land, it is generally preferable to purchase,
rather than lease, land in order to be able to recover development
costs in the event of a later sale of the property" (Ref. IV-19).
                                -45-

-------
                            CHAPTER  IV
                           REFERENCES
IV-1      "Ground-Water Resources of East Tennessee,"  DeBuchananne,
          G. D., and Richardson, R. M.,  Tennessee Div. Geol.,
          Bull. 58 (1956).

IV-2      Air Resource Management in Knox County, Technical  Report
          No. 3, Duncan, J. R., and Miller,  T.,  Knox County  Depart-
          ment of Air Pollution Control (April 1972).

IV-3      Data supplied by Knox County Department of Air  Pollution
          Control.

IV-4      "Some Geomorphic Aspects and Problems  Related to the Knox
          County Area,  Tennessee,  "Clark,  G.M.,  in Geology of Knox
          County,  Tennessee Div. Geol, Bull.  70  (1973).

IV-5      "Areas of  Possible Flooding in Knox County,  Tennessee",
          Harns, L.D.,  U.S.  Geol.  Survey Misc. Geol, Inv. Map I-767M
          (1973).

IV-6      "Water Resources of Knox County, Tennessee," McMaster,
          W. M., in Geology of Knox County,  Tennessee  Div. Geol.,
          Bull. 70 (1973).

IV-7      Water Quality Management Plan for  the  Upper  Tennessee
          River Basin.  Preliminary Draft, Division of  Water  Quality
          Control, Tennessee Department  of Public Health  (undated).

IV-S      Water Quality Management Plan for  the  Holston River Basin.
          Preliminary Draft, Division of Water Quality Control,
          Tennessee Department of Public Health  (undated).

IV-9      Water Quality Management Plan for the  French Broad River
          Basin. Division of Water Quality Control, Tennessee Depart-
          ment of Public Health (undated).

IV-10     Institutional Alternatives for Providing Programmed Water
          and Sever Services in Urban Growth Areas; A Case  Study  of
          Knoxville-Ktiox County Tennessee. Hayes, G. G.,  Report
          No. 18, Water Resources Research Center, University of
          Tennessee (June 1972).

IV-11     "Soils of Knox County Tennessee," Moneymaker, R. H.,  in
          geology of Knox County, Tennessee Div. Geol., Bull.  70
          (1973).
                                    -46-

-------
                           CHAPTER IV
                           REFERENCES
                           (Continued)
IV-12     Design with Nature,  McHarg,  I.L., Doubleday/Natural
          History Press,  Garden City,  New York (1969).

IV-13     "Land Use and Capital Improvements  in 201 Facilities Plan
          (Draft)," Knoxville-Knox County Metropolitan  Planning
          Commission (March 1975).

IV-14     Letter from Frank Erickson,  ETDD,  20 August,  1975.

IV-15     Eminent Domain in Tennessee, Institute for Public Service,
          University of Tennessee (May 1972).

IV-16     "Areas with Abundant Sinkholes  in Knox County,  Tennessee,"
          Harris, L.D.,  U.S. Geol. Survey Misc. Geol.  Inv.  Map
          I-767F (1973).

IV-17     "Mineral Resources of Knox County,  Tennessee,"  Maher, S.W.,
          in Geology of Knox County. Tennessee Div. Geol.,  Bull. 70
          (1973).

IV-18     Telephone conversation with  Mr. Frank Erickson, East
          Tennessee Development District  (October 3, 1974).

IV-19     "Institutional Options for Recycling Urban Sludges and
          Effluents on Land,"  Barbolini,  R.R., in Recycling
          Municipal Sludges and Effluents on  Land,  Proceedings of
          a conference held July 9-13, 1973 in Champaign, Illinois,
          available from the National  Association of State Universities
          and Land-Grant Colleges, One DuPont Circle,  N.W., Washington,
          D. C.  20036.
                                  -47-

-------
                             CHAPTER V
                   THE SLUDGE DISPOSAL PROBLEM
INTRODUCTION

     Evaluation of the planning perspective figure in Chapter III
indicates that one of the investigations necessary in the develop-
ment of residual waste management options is the review of existing
and proposed wastewater treatment facilities in the 208 Study Area
and the projection of sludge quantities from these facilities.  This
review and projection would be facilitated by having completed 201
Facilities Plans available such that the actual quantities could be
ascertained and utilized.  However, the 201 Facilities Plan for Knox-
ville-Knox County was not completed during the course of this investi-
gation, thus making it necessary to utilize the Methodology to develop
sludge projections.  It should be recognized that in a great many cases
this lack of completed 201 Facilities Plans for use in a 208 planning
study would likely be the rule.  Therefore, the following portions of
this chapter are intended to: 1) characterize the existing situation
in terms of wastewater treatment facilities and current disposal
practices; and 2) describe the future anticipated facilities and
project for these facilities raw sludge production.

     Due to the lack of sufficient or complete data within the 201
Facilities Plan as noted above, the following procedure was utilized
such that the characterization of the Study Area in terms of existing
municipal wastewater treatment facilities (and the drainage areas
served by them) and their respective sludge quantities and existing
disposal practices could be described.  The goals of the procedure
were to: 1) identify the extent of the present service area served
by each existing facility; 2) identify the responsible agencies
providing the sewerage and treatment facilities; and 3) the existing
treatment facilities (their present average dry weather flows and
operational difficulties which impact upon current and/or proposed
sludge handling and disposal).

     The procedure was as follows:

     (1) review the 201 Facilities Plan and, to the extent possible,
         abstract and synthesize data from the Plan;

     (2) describe in some manner common to the Plan the existing
         situation (thus providing some commonality between 201 and
         208 planning);
                                   -48-

-------
     (3) contact local agencies,  utility districts,  and consulting
         engineering firms such that missing or incomplete data
         could be filled in; and

     (4) from »-'ho first three steps above summarize the existing
         facilities, their current sludge quantities produced and
         the current disposal practices.

     The same procedural format was also utilized in the development
of information necessary to describe the anticipated facilities.
During the course of this phase (i.e., description of the anticipated
facilities), it became necessary to make reasonable assumptions as to
the extent of future service areas and population served such that
projected future raw sludge quantities could be made.  These
assumptions, required because of a lack of data supplied in the 201
Facilities Plan regarding future sludge quantities,  were made in
order to facilitate the use of the per capita sludge generation
numbers found in the Methodology.  The method and the necessary
assumptions used to describe future sludge quantities are described
in a latter portion of this chapter.

EXISTING FACILITIES

     As shown on Figure y-1, there are thirty-one distinct and
separate drainage basins within the Study Area.  These thirty-one
drainage basins were combined during the preparation of the 201
Facilities Plan into the eleven major drainage areas described below
and utilized during this study (Ref. V-l).  The major wastewater
facilities are presented and industrial discharges to the system
discussed.  Figure V-2 indicates the boundaries of the utility
districts and the City of Knoxville discussed in the following text.

Third Creek Drainage Area

     The Third Creek Drainage Area encompasses approximately 64
square miles (166 square kilometers) of which 50 square miles (129
square kilometers) are in the City of Knoxville.  It consists of the
central, northern, and southern portions of the City of Knoxville and
includes eight drainage basins.  These drainage basins are First Creek;
Second Creek; Goose Creek; Toll Creek; and portions of Third Creek,
Knob Creek, Williams Creek and Loves Creek.  Sewerage service within
the basins is provided by the City of Knoxville.
                                  -49-

-------
             KNQXVILLE  AND  KNOX  COUNTY

DRAINAGE BASINS AND PUBLIC WATER  SUPP1Y  LOCATIONS
                                                       Oroinogt Botint

                                                       Row-wottr Intok*

                                                       Spring Supply
                                                       Wtll R«ld
o
c
20
n

-------
             UTILITY DISTRICTS LOCATED IN KNOX COUNTY
036
t  .  .  I .  .
SCALE  IN MILES
                                                               Utility Districts
                                                                               Tl
                                                                               c
                                                                               m
                                                                               <
                                                                               ix>

-------
      The largest existing waste treatment facility located in this
drainage area, as well as in the Study Area, is the Third Creek Treat-
ment Plant. It is owned and operated by the City of Knoxville.  The
plant provides primary treatment for the entire wastewater flow
entering the plant, secondary activated sludge treatment for a portion
of the flow, and effluent chlorination for the entire flow.  Its sewage
collection system serves the entire area within the City limits of this
drainage area and serves approximately 132,400 people (1970 figure).

      The existing effective capacity of the Third Creek Treatment
Plant is 18.0 million gallons per day (mgd) (6.81 x 10^ cu m/day).
However, the average dry weather flow received at the plant is 26.8
mgd (10.14 x 10^ cu m/day).  As indicated, the plant is severely over-
loaded.   The effluent, which presently does not meet the requirements
of the regulatory agencies, is discharged to the Tennessee River (Fort
Loudoun  Lake)  at River Mile 646.3 (Ref.  V-l).

     Thirty-seven industries discharge to the Third Creek sewerage
system 6.52 mgd (2.47 x 10^ cu m/day).  Of these thirty-seven
industries,  nine operate on a seven day a week, twenty-four hour a
day basis and  discharge 2.98 mgd (1.13 x 10^ cu m/day).   The other
twenty-eight industries operate on a five day a week,  eight hour a
day basis.   Thus,  on weekends the Third  Creek plant receives only
46 percent  of  the total industrial input experienced during the
earlier  five day work week;  an operational problem which may
adversely impact upon wastewater treatment efficiency and sludge
handling.  Only four of the thirty-seven industries provide pre-
treatment prior to  sewer  discharge at the present time (Ref.  V-l).

Fourth Creek Drainage Area

      The Fourth Creek Drainage Area occupies approximately 43 square
miles (111 square kilometers) in the western part of the City of Knox-
ville and part of west-central Knox County.  It consists of four
drainage basins, including Fourth Creek, Bluegrass, Duncan Branch,
and the  portion of Third Creek previously discussed.

      Sewerage service for approximately 65 percent of the Fourth
Creek Drainage Area is provided by the City of Knoxville.  However,
due to the land use pattern and topography, much of the area is
unsewered.  These unsewered areas are treating their wastewaters
through the use of individual septic tanks and leaching fields.  The
Fourth Creek Drainage Area also receives wastewater from the Ten Mile
Creek Drainage Area via the Ten Mile Creek Pump Station.
                                    -52-

-------
     The sewered area is served by Fourth Creek Treatment Plant, the
City's second largest wastewater treatment facility.  It is an acti-
vated sludge plant with an effective capacity of 5 ragd (1.89 x 10^ cu
m/day).  It is presently receiving an average dry weather flow of 5.7
mgd  (2.16 x 10^ cu m/day) (Ref. V-l).

     Five industries discharge to the Fourth Creek sewerage system
1.08 mgd (0.41 x 10^ cu m/day).  Of these five industries, two
operate on a seven day a week, twenty-four hour a day basis and
discharge 0.43 mgd (0.16 x 10^ cu m/day).  The other three industries
operate on a five day a week, eight hour a day basis.  Thus on
weekends the Fourth Creek plant receives only 40 percent of the total
industrial input experienced during the earlier five day work week;
again with operational problems as noted for Third Creek above.  Only
one  of the five industries currently provides pretreatment prior to
sewer discharge (Ref V-l).

Loves Creek Drainage Area

      The Loves Creek Drainage Area is located in the eastern pa-t of
the City of Knoxville.  It occupies an area of approximately 14 square
miles (36 square kilometers) and encompasses the Woods Creek Drainage
Basin, as well as portions of Loves Creek and Williams Creek Drainage
Basins.   Portions of the Loves Creek Drainage Area lie within the area
served by the Northeast Knox Utility District and portions lie within
the county and are not served by any utility district.  The portions
not served by any utility district were considered a part of the City
of Knoxville for planning purposes.

      Sewerage services in the Loves Creek Drainage Area are provided
only by the City of Knoxville.  The area within the City limits and
the majority of the area within the county are presently sewered.
The wastewater is collected and treated at the City's Loves Creek
Wastewater Treatment Plant which employs trickling filters, designed
to treat an average dry weather flow of 3.0 mgd (1.14 x 10^ cu m/day).
It is presently receiving an average dry weather flow of 1.2 mgd
(0.45 x 104 cu.m/day).  The effluent is discharged at River Mile 5.0
of the Holston River.  The sludge generated at this treatment plant
is pumped to the gravity collection system for the Third Creek Treatment
Plant and becomes a part of the raw wastewater flow to this treatment
facility (Ref V-l).
area.
      No industries contribute to the sewer system in this drainage
                                  -53-

-------
Ten Mile Creek Drainage Area

      The Ten Mile Creek Drainage Area is in the west-central portion
of Knox County.  It encompasses an area of approximately 19 square
miles (49 square kilometers) and contains only the Ten Mile Creek
Drainage Basin.

      West Knox Utility District serves approximately 49 percent of
the area, First Utility District serves 31 percent, the City of Knox-
ville serves 3 percent, and approximately 17 percent of the drainage
area is not served by any utility district.  For planning purposes
this latter portion was considered a part of the City.  Approximately
62 miles (100 kilometers) of sanitary sewer serve 3,600 customers in
the West Knox and First Utility Districts.  Wastewater service to the
Ten Mile Creek Drainage Basin is jointly contracted by West Knox
Utility^District, First Utility District,  and the City of Knoxville.
Each utility district maintains its sewerage collection system and
the City of Knoxville owns and operates the pump stations that
transmit the waste to the City of Knoxville's Fourth Creek Treatment
Plant (Ref.  V-l).

      No industrial discharges in this drainage area were identified.


East Knoxville Drainage Area

      The East Knoxville Drainage Area is located in  the eastern
portion of Knox County.  It is bounded on the north and west by the
Holston River, on the east by the Knox County limits, and on the
south by the French Broad River.  It encompasses an area of approxi-
mately 67 square miles (174 square kilometers) and includes five
drainage basins.  These drainage basins are Lyon Creek, Sinking Creek,
Swanpond Creek, Frazier Branchj and Tuckahoe Creek.

      Most of the domestic residential wastewaters are treated by
individual septic tanks and leaching fields.  The Eastwood Sub-
division is served by a prefabricated wastewater treatment plant
which is operated by the City of Knoxville.

      In the Forks-of-the-River Industrial Park, an existing sewer-
age system treats the domestic waste from eighteen industries in  the
area.  The wastewater  is  treated  in  a  1 mgd  (0.38 x  10**  cu m/day)
design capacity  secondary  activated  sludge  treatment  plant operated
by Knox  County and  the effluent  is discharged  to the  French Broad
River at  River Mile  1.9.   The plant  also  receives  process wastewater
estimated at  0.21 mgd  (0.08 x  10^  cu m/day)  all  on a  five day a week,
approximately  eight hour  a day basis  from five  industries located
                                 -54-

-------
in the Forks-of-the-River Industrial Park.   The plant is receiving
0.26 mgd (0.10 x 10^ cu m/day)  average flow and is discharging an
unsatisfactory effluent, due to heavy metals discharge by one of
the industries (Ref. V-l).

Knox-Chapman Drainage Area

     The Knox-Chapman Drainage Area is located in the southern
portion of Knox County.  It includes six drainage basins and  occupies
approximately 61 square miles (158 square kilometers).  These drain-
age basins are Spring Creek, Knob Creek, Burnett-Hines, Cement Mill,
Stock Creek, and Roddy Branch.   A portion of this area within Knox
County is not served by a utility district.  For purposes of  planning,
it was considered a part of the City of Knoxville.  The remainder of
the area is served by the Knox-Chapman Utility District.

     At present, no sewage collection and treatment system is serving
this area.  All residential wastewater generated in the area  is treated
by individual systems.  The University of Tennessee Hospital, located
near the City limits, discharges approximately 0.26 mgd (1.10 x 10^
cu m/day) on a seven day a week basis to the City sewer system.  No
industrial discharges were noted (Ref. V-l).

Little Flat Creek Drainage Area

     The little Flat Creek Drainage Area is situated in the north-
eastern portion of Knox County and occupies an approximate area of
64 square miles (166 square kilometers).  It consists of two drain-
age basins, Strong Creek and Little Flat Creek Drainage Basins,
both tributary to the Holston River.

     At present,, two utility districts are serving this drainage
area.  These are the Luttrell-Blaine-Corryton Utility District and
the Northeast Knox Utility District.  The former serves three com-
munities in three counties.  These are Luttrell in Union County,
Elaine in Grainger County, and Corryton in Knox County.  Only the
Corryton area, which occupies approximately 17.5 square miles
(45 square kilometers) is included in this study.  The Northeast
Knox Utility District serves the remainder of this drainage area.

     The area is sparsely populated due to topography.  There are
no existing sewage collection and treatment systems in  the area
(Ref. V-l).  Small package treatment plants are currently used to
serve some commercial establishments while septic tanks are employed
by individual residences.  No industrial discharges were noted.
                                  -55-

-------
Bullrun Creek Drainage Area

      This drainage area is located in the northern part of Knox
County.  It occupies approximately 41 square miles (106 square kilo-
meters) and consists of one drainage basin, Bullrun Creek.  This
area is separated from the remainder of Knox County by three parallel
ridges forming Brushy, Bullrun, and Raccoon Valley.

      This area is -presently served by the Hallsdale-Powell Utility
District.   However, no sewage collection and treatment system is   ,
existing in this area, although a 150,000 gallon per day  (0.06 x 10
cu m/day)  extended aeration type process is being proposed for com-
pletion in 1975.  The proposed location is at Interstate 75 and
Raccoon Valley Drive (Ref.  V-l).

Beaver Creek Drainage Area

      The  Beaver Creek Drainage Area encompasses approximately 92
square miles (238 square kilometers).  It lies in the north-central
part of Knox County parallel to and south of Bullrun Creek Drainage
Area.  It  contains only one drainage basin, Beaver Creek, which is
tributary  to the Clinch River.

      Of the total area enclosed by Beaver Creek Drainage Area,
approximately 32.3 percent [30 square miles (78 square kilometers)]
in the southwestern portion of the drainage area is presently served
by the West Knox Utility District.  This includes the communities of
Karnes, Solway, and Ball Camp, and the 550-acre (223 hectare)
Byington Industrial Park.

      A sewage treatment and collection system is in operation
 near Byington and has a total design 'capacity of ]00,000 gallons
 per day (0.04 x 10^ cu m/day).  It is -a prefabricated extended aera-
 tion type process (Ref. V-l).  This plant will be known as the Karns
 facility  and referred to as such in the remainder of this report.

      Another utility district that serves the Beaver Creek Drainage
 Area is the Hallsdale-Powell Utility District.  It serves approxi-
 mately 54.7 percent [50 square miles (129 square kilometers)] of
 the total area.  Two major communities are in this utility district,
 each being served by a separate sewage and collection system.  The
 Hallsdale Community Treatment Plant, an extended aeration facility
 owned and operated by the District, has a design capacity of 400,000
 gallons per day (0.2 x 10^ cu m/day) (Ref. V-l).  After chlorination,
 the effluent is discharged to Beaver Creek.
                                      -56-

-------
      The other treatment facility owned and operated by the Halls-
dale-Powell Utility District serves the Powell Community.  This
wastewater is treated by a contact stabilization treatment plant
with a design capacity of 400,000 gallons per day (0.2 x 10  cu
m/day).  At present, this treatment facility is receiving approxi-
mately 200,000 gallons per day (0.1 x 10  cu m/day).  The effluent
from the treatment plant is discharged to an aerated lagoon,
chlorinated, and then discharged to Beaver Creek (Ref. V-l).

      The northeastern portion of this drainage area is served by
the Northeast Knox Utility District.  It occupies about 10.2 percent
[9.4 square miles (24 square kilometers)] of the total drainage
area.  No existing sewage collection and treatment system is
presently serving this part of the drainage area  (Ref. V-l).

      The remainder of the drainage area, which occupies 2.8 percent
[2.7 square miles (7 square kilometers)], lies within a portion of
the county not served by any utility district.  For purposes of
planning, this portion was considered part of the City of Knoxville.

      Industrial discharges to the sewer systems of the Hallsdale-
Powell Utility District are approximately 50,890 gallons per day
(0.02 x 10  cu m/day) on a five day a week basis (Ref. V-l).

Hardin Valley Drainage Area

      This drainage area is located in the west-northwest part of
Knox County adjacent to the Clinch River.  It occupies approximately
21 square miles (54 square kilometers) and is served by the West
Knox and First Utility Districts.  Only one drainage basin, Hardin
Valley Drainage Basin, lies within this area.

      There are no wastewater collection or treatment  facilities in
the drainage area; domestic wastes being treated by individual septic
tanks.  No industrial discharges were noted (Ref. V-l).

Turkey Creek Drainage Area

     The Turkey Creek Drainage Area lies in the southwestern section
of Knox County,  It contains three drainage basins, Turkey Creek,
Little Turkey Creek and Choto Basin, and occupies approximately 42
square miles  (109 square kilometers).  It is served by the First
Utility District, with the exception of  the extreme northeast  tip
which  is within the jurisdiction of the West Knox Utility District.
There  are four existing wastewater  collection systems  owned and
operated by the First Utility District.  Three  of these  are  located
in the Turkey Creek Drainage Basin  and the  fourth is  in  the Ten Mile
Creek  Drainage Basin which was discussed previously.
                                    -57-

-------
     The three collection systems are Stonecrest, Village Green, and
Fox Den.  The Stonecrest system collects the wastewater which is
then hauled by tank truck to the Ten Mile Creek collection system.
The Village Green collection system discharges into a small contact
stabilization and tertiary nitrification plant,  currently operating
at a flow of 75,000 gallons per day (0.03 x 10^  cu in/day).   The
Fox Den collection system discharges into a small contact stabili-
zation and filtration plant.  The plant is operating at less than
10,000 gallons per day (0.004 x 10  cu m/day).  A new wastewater
treatment facility (Turkey Creek), at 1 mgd (0.38 x 10  cu m/day)
is designed to treat the wastewater collected at all three of the
above collection systems as well as a large segment of the Turkey
Creek Drainage Area.  The wastes from all three  collection systems
are strictly domestic with no industrial discharges noted (Ref. V-l).

EXISTING SLUDGE DISPOSAL PROCESSES

     Data in the 201 Facilities Plan, at least those portions of
the plan available during the course of this study, were lacking
with regard to current sludge disposal processes or quantities -and
qualities.  It therefore became necessary to contact the utility
districts, local consulting engineering firms, and City/County per-
sonnel to obtain such information if available.   Table V-l is the
best available information that could be developed during this
specific contact investigation phase.  The estimation for Turkey
Creek was based upon a scaling up from information provided on the
Powell plant facility.  It should be recognized  that the accuracy
of the sludge quantity numbers may be questionable, however the
overall relative quantities between plants is felt to be a reasonable
approximation of the current picture.  It should also be noted that
the low values for the Third Creek facility are  due to operational
problems at the overloaded facility which during 1974 had removal
efficiences of 32 percent for biochemical oxygen demand  (BOD) and 43
percent for suspended solids (SS) (Ref. V-2).

     The existing sludge disposal practices for  Knoxville-Knox
County involve (1) allowing private individuals  to pick up a de-
watered sludge, (2)  on-site disposal of a dewatered sludge or,
(3) trucking to a landfill either all of the dewatered sludge or
the remaining portion from (1) above.

     There appears to be, at least noted by personnel at the Third
Creek facility, a decline in the amount of dewatered sludge taken by
private individuals, possibly due to a saturation of the area within
an economical and convenient distance to the plant.  Whether a
decline could be anticipated in the long run for this disposal option
for such outlying facilities as Powell, where access to larger
agricultural interests may be found, is unknown  at this time.  How-
ever, due to the urbanization process within the County and the
                                   -58-

-------
                                             TABLE V-l
                                      PRESENT SLUDGE QUANTITIES
Plant
Third Creek
Fourth Creek
Loves Creek
Forks- of-
the- River
Raccoon
Valley
Karns
Hallsdale
Powell
Turkey
Creek
Type
Activated
Sludge
Activated
Sludge
Trickling
Filter
Activated
Sludge
Extended
Aeration
Extended
Aeration
Extended
Aeration
Contact
Stabili-
zation
Contact
Stabili-
zation
Size
mgd
26.80
5.70
1.20
0.26
0.15
0.10
0.40
0.20
1.00
Status
Existing
Existing
Existing
Existing
Under Con-
struction
Existing. To
be expanded
To be aban-
doned in 1977
Existing. To
be expanded
Under con-
struction and
to be expanded
Sludge Handling
Anaerobic Digestion,
Vacuum Filter to
Private individuals
or landfill
Anaerobic & Aerobic
Digestion, Vacuum
Filter, Landfill
Raw, Pumped to
Third Creek
Aerobic Digestion,
Sand Bed Dewatering
On-site disposal
None, hauled to
Powell when needed
monthly - 2000
gallons at 3% solids

Sand Drying Beds
Applied once a week
Sand Drying Beds
Aerobic Digestion,
Sand Drying Beds,
On-site Disposal
Sludge Quantities
6721 Ibs/day dry solids
(this low value is due
to operational problems
of the Third Creek plant)
7988 Ibs/day dry solids
Included in Third Creek

100 Ibs/day dry solids
Negligible
374 Ibs/day dry solids
286 Ibs/day dry solids
Estimated
1430 Ibs/day dry solids
Ln
VO

-------
 decline  in  both  size  and  numbers of  farms  in  the County, as noted
 in  Chapter  IV, it is  unlikely  that either  partial or total reliance
 upon  private  individuals  to  truck away sludge would be a feasible
 means of  sludge  disposal  in  the short or long run.

      On-site  disposal, again for the processes of urbanization occur-
 ring  within the  county and the expansion plans for several of the
 existing  facilities which would require site  acreage, is unlikely
 to  provide  either a short-or long-range disposal option.  Although
 this  is an  existing practice at the Forks-of-the-River and Turkey
 Creek plants, these plants are located in  areas subject to expansion
 of  surrounding industrial activities, such as at Forks-of-the-River,
 or  urbanization  such  as at Turkey Creek.   Avoidance of potential
 problems  such as complaints  from neighbors and restrictions in usable
 on-site land, particularly at  Turkey Creek, would thus render on-site
 disposal  less likely  to occur  in the relatively near future.

      Utilization of sanitary landfills for disposal of a dewatered
 sludge thus appears to be both the current and possible near-term
 disposal program and  as such was considered to represent the "base
 case"  in this study.  However, the future  of  sanitary landfills in
 Knoxville-Knox County is  open  to question.  Studies currently in
 progress by the Tennessee Valley Authority (TVA) are investigating
 the possibility of collecting  and transporting municipal solid
 waste  to regional processing centers for separation of metals, glass,
 and combustible fractions (Ref. V-3).   The metals and glass frac-
 tion would be sold and the combustible fraction remaining would
 then be transported to TVA steam power plants to augment coal
 supplies.  One of the regional processing  centers under investigation
 would be located in Knoxville-Knox County.  Concurrently, the City
 of Knoxville is conducting an  investigation of the feasibility of
 solid waste collection and burning in a municipal incinerator which
 would also generate power and  steam for use in the downtown area.

     It thus appears that solid waste disposal and hence sanitary
 landfilling, is a problem recognized in the Knoxville-Knox County
 area as being  sufficiently serious  to warrant consideration of other
alternatives.   In addition,  all open dumps have been closed in the
County, and only one sanitary landfill in  the northeast portion
 of the County  (Rutledge Pike) is presently in operation.

     Thus, the long-term viability  of the  "base case",  i.e. sludge
disposal into  a sanitary landfill,  is questionable,  recognizing
however the probable lag time of implementation of the solid waste
alternatives mentioned above.

     As existing wastewater  treatment facilities are expanded,
wastewater treatment levels are increased  to meet more stringent
 discharge standards, and proposed facilities come on-line, the
                                  -60-

-------
increased amounts of sludge generated that must be disposed will
increase substantially.  Disposal to sanitary landfills, which may
be of questionable viability in the near future, is therefore a
problem of significant concern to Knoxville-Knox County.  As stated
earlier in this report, it is one of the intended purposes of this
study, by utilizing the Methodology, to develop alternative residual
waste (in this case municipal wastewater treatment plant sludges)
handling and ultimate disposal alternatives for Knoxville-Knox County.
The following sections of this chapter discuss the wastewater treatment
facilities anticipated in Knoxville-Knox County for inclusion in this
study and the projected raw sludge productions at these facilities.

ANTICIPATED KNOXVILLE-KNOX COUNTY MUNICIPAL WASTEWATER TREATMENT
FACILITIES

     As noted in the contract for this study, the alternatives
evaluated were to meet disposal requirements for a 20-year period
(Ref. V-4).  This also corresponds  to the planning timeframe re-
quired under 208 planning  (Ref. V-5).  The facilities described
below are those anticipated to be operable in Knoxville-Knox County
during this 20-year period  (Ref. V-l).  It is assumed in  this study
that these facilities as designed or proposed meet applicable dis-
charge standards required under the 1983 goals of the Federal Water
Pollution Control Act Amendments of 1972.  The solids handling
systems are as proposed currently and do not necessarily reflect the
alternatives discussed in Chapter VII of this report.

Knob Creek

     Because of current operational problems at the Third Creek
facility, the City of Knoxville has been in the process of com-
pleting a 201 Facilities Plan which investigated for the Study Area
the facilities needed to meet applicable standards and  to serve the
present and anticipated growth in the Area (Ref. V-l).  One
major finding of this Plan has been  to abandon  the Third and
Fourth Creek facilities and construct a biological (activated
sludge) regional facility  in the southern portion of the  area
serving the majority of the urban portion of the Area.  A tenta-
tive site location  (Cox Sky Ranch) has been selected.   This  site,
although meeting some local opposition, has been evaluated by MPC
in conjunction with other  alternative sites and tentatively  approved
(Ref. V-6).

     The Knox Creek facility will be an air activated sludge pro-
cess employing mechanical  screening, grit removal, primary  settling,
activated sludge, nitrification  (if needed), multi-media  filtration,
chlorination, and post aeration prior to discharge to the Tennessee
River.
                                    -61-

-------
      Proposed sludge handling includes  sludge thickening,  two-stage
 anaerobic digestion, and filter press dewataring with the  filter
 cake trucked to a sanitary landfill.

 Powell

      The present Powell plant,  located  in the northwest  portion of
 the Study Area,  is currently under  expansion proceedings (construc-
 tion bids).   The Hallsdale plant is to  be abandoned  following  the
 completion of the Powell construction program (sometime  in 1977)
 and for  the  purposes of this study  will not  be considered  as a
 separate facility but as having contributed  its flow to  Powell.

      The Powell  plant after expansion will include bar screens,
 grit removal,  contact stabilization, aerated lagoons, air  flotation
 (for removal and return of algae to the lagoons), multi-media
 filtration,  chlorination,  and post  aeration  prior to discharge to
 Beaver Creek.

      Sludge  handling includes,  for  the  contact stabilization
 process  sludge,  aerobic digestion,  thickening,  and vacuum  press
 dewatering.   The filter cake would  then be trucked to a  sanitary
 landfill.  Excess algae from the aerobic lagoons recycle would be
 dried on sand drying beds  for on-site disposal.  Sludge  from the
 Raccoon  Valley plant will  be trucked to Powell for handling in the
 thickening and vacuum press  processes.

 Turkey Creek

      The Turkey  Creek facility,  located in the southwestern portion
 of  the Study Area,  is currently finishing a  construction and start-
 up  phase as  a contact stabilization facility.   Before 1995 flows
 come  on  line,  the plant would be modified as an oxygen activated
 sludge plant with nitrification  facilities.  The exact flow process
was not made available  for this  study.

      Proposed  sludge handling processes include aerobic  digestion
followed by sand drying beds with on-site disposal.

Karns

     The Karns facility will be  expanded as a contact stabiliza-
tion facility followed by sand filtration until 1990.  At that
time the plant will be modified and expanded to provide air activated
sludge treatment.

     The modified plant will provide primary clarification, air
activated sludge with carbon addition for nitrification,  secondary
                                    -62-

-------
clarification, rapid sand filtration, chlorination and dechlorina-
tion, prior to effluent discharge to Beaver Creek.

     Primary sludge would be mechanically dewatered and disposed
into a sanitary landfill.  Secondary sludge containing carbon
would be reprocessed for carbon recovery and reused with the sludge
ash going to sanitary landfill.  It is unclear at this time the
rational used by the local consulting firm as to its suggested
disposition of primary dewatered sludge into a sanitary landfill.
This sludge handling process would not come on-line until 1990.

     Up to 1990 the solids handling includes aerobic digestion of
the waste activated sludge, vacuum filtration, and trucking to
sanitary landfill.

Lyon Creek

     A proposed modified extended aeration plant at Lyon Creek in
the eastern portion of the County would serve the Little Flat Creek
drainage basin in the Luttrell-Blaine-Corryton and Northeast Knox
Utility Districts and Lyon Creek drainage basin in the East Rnox-
ville Utility District.

     This plant would provide grit removal, primary settling,
extended aeration, secondary-clarification, chlorination, and post
aeration prior to effluent discharge to the Holston River.

     Proposed sludge handling includes sludge thickening, two-stage
anaerobic digestion, sand bed dewatering, and trucking the cake  to
a sanitary landfill.

Loves Creek

     Serving the Loves Creek drainage basin in the eastern portion
of the County, the existing Loves Creek facility, a trickling
filter plant, has a design capacity expected to be sufficient for
projected 1995 flows.  The facility is anticipated to undergo
expansion after 1995.

     Sludge generated at Loves Creek is currently pumped to the
gravity collection system for the Third Creek treatment plant.
Upon abandonment of Third Creek and flow diversion to the regional
Knob Creek plant, the sludge from Loves Creek then becomes part of
the raw wastewater flow to Knob Creek.

Forks-of-the-River

     This facility presently serves the domestic wastes from  the
industries located in the Forks-of-the-River Industrial Park  as
                                   -63-

-------
well as some process wastewater from five industries located in
the park.  The current hydraulic capacity is expected to serve as
the ultimate capacity expected in the year 2005.

     The plant is an activated sludge facility utilizing trickling
filters prior to the aeration basins.  Primary and secondary
sludge is aerobically digested, dewatered on drying beds, and dis-
posed on-site.

PROJECTED SLUDGE QUANTITIES

     With the exception of the Forks-of-the-River Plant, all other
anticipated plants will be discharging to water quality limited
stream segments (Refs.  V-7, 8, and 9).  Thus, the wastewater treat-
ment efficiencies required will translate directly to large
quantities of sludge to be processed and disposed.

     Information made available during the course of this study was
incomplete with regards to both the anticipated wastewater flows in
the year 1995 and the resultant projected sludge quantities for
these anticipated facilities.  Therefore, the Methodology was
utilized to develop these quantities.  The technique utilized is
described below.

     The anticipated facilities and their service areas are shown
on Figure V-3.   The eleven drainage areas discussed earlier for
the existing facilities and their respective 1975 and 1995 popu-
lation estimates  are shown in Figure V-4.  A comparison was made
of these two figures and assuming the total population to be
sewered as anticipated  by the various river basin plans in the area
(Refs.  V-7,  8,  and 9) (see also Chapter IV of this report), the
following breakdown of  population served by the anticipated
facilities by drainage  areas was utilized for this study:

     (1)   Knob Creek -  serves all of the Third Creek, Fourth Creek,
          and Ten Mile  Creek drainage and two-thirds of the
          Knox Chapman  drainage area;

     (2)  Loves Creek -  serves  all of  the  Loves  Creek drainage
         area and one-half of  the East Knoxville  drainage  area;

     (3)  Powell - serves all  of  Bullrun  Creek drainage  area  and
         four-fifths of the  Beaver  Creek  drainage area;

     (4)  Turkey Creek - serves all  of  the Turkey  Creek  and
         Hardin Valley  drainage  areas;
                                   -64-

-------
$
i
                          WASTEWATER  SERVICE AREAS AND  TREATMENT FACILITIES
                                           KNOXVILLE AND KNOX  COUNTY
                   PLANTS

              I. Knob  Creek
              2 Love* Creek
              3. Powell
              4. Turkey Creek
              5. Korr*
              6.Lyon Creek
              7. Fork*-Of-The-River
              S.Hallsdale
              9. Eastwood
              10. Third Creek
              11. Fourth Creek
              12. Raccoon Valley
                                                                           EXISTING  PROPOSED
SCALE  IN MILES
                                                                                             Treatment Plant
                                                                                             Major Trunk Lines
                                                                                             Forced Mains
                                                                                             Service Area*
                                                                                             To Be Abandoned
                                                                                             To Be Expanded
                                                                                             Sludge Pumped Or
                                                                                             Trucked Elsewhere
          SOURCE:  Knaxville-Knox  County Metropolitan Planning Commtsson

-------
                             KNOXVILLE AND  KNOX  COUNTY

                  EXISTING  AND PROJECTED POPULATION DISTRIBUTION
       036
       I .  .  I
                                                                     Droinoge Basin

                                                                     1975 Population (Estimated)

                                                                     1995 Projected Population
                                                                                           c
                                                                                           JO
SOURCE: Knoxville-Knox County Metropolitan Planning Commission

-------
     (5)   Karns - serves one-fifth of the Beaver Creek drainage
          area;

     (6)   Lyon Creek - serves all of the Little Flat Creek drainage
          area and one-fourth of the East Knoxville drainage dii_ci;
          and

     (7)   Forks-of-the-River - serves one-third of the Knox Chapman
          drainage area and one-fourth of the East Knoxville
          drainage area.

     Population forecasts provided by MFC (Ref. V-l) were
aggregated according to the above breakdowns, and the projected
domestic  populations served by the anticipated facilities shown in
Table V-2.

     The  industrial and commercial discharges within the drainage
areas noted earlier were converted first to a seven day a week
basis and then to population equivalents and are shown in Table V-3.
The combined domestic, industrial, and commercial populations used
during this study are shown in Table V-4.

     Utilizing the Methodology (Ref. V-10), the projections of
raw sludge quantities were determined and are given in Table V-5.
The applicable factors used in projecting the sludge quantities
are noted in this table.

     Implicit in the utilization of the per capita sludge projec-
tion values in the Methodology is the fact that these values are
those to  be used when the per capita wastewater flows are 100 gallons
per day.   A report prepared in 1972 projected for the Knoxville
area a per capita value of approximately 100 gallons per day based
upon projected water requirements and usage  (Ref. V-ll).  Therefore,
the values in the Methodology were used directly.  However, it
should be noted that if local situations (e.g. heavy industrial
input or  specific flow and quality of sewage on a per capita basis)
warrant in other study areas, the values in  the Methodology should
be adjusted accordingly.
                                  -67-

-------
                                                     TABLE V-2
                                  POPULATION PROJECTION FOR THE ANTICIPATED FACILITIES
00
I
Facility
1, Knob Creek
2. Loves Creek
Sub Total
3. Powell
4. Turkey Creek
5. Karns
Sub Total
6. Lyon Creek
7, Forks-of-the-River
GRAND TOTAL
(noxville-Knox County
1975
205,729
18,019
223,748
36,720
13,707
5,856
56,283
14,955
8,394
303,380
1980
224,523
18,300
242,823
43,581
15,901
6,951
66,433
15,597
10,426
335,279
1985
238,422
18,582
257,004
49,790
17,014
7,938
74,742
15,996
12,356
360,098
1990
245,927
18,792
264,719
55,018
18,127
8,776
81,921
16,136
12,656
375,432
1995
252,457
19,719
272,176
57,030
18,384
9,048
84,462
16,510
13,281
386,429

-------
                                                 TABLE V-3
                               POPULATION PROJECTIONS FCH THE ANTICIPATED  FACILITIES
                                INDUSTRIAL AND COMMERCIAL POPULATION  EQUIVALENTS
VD
 I
Facility
1. Knob Creek
2. Loves Creek
Sub Total
3. Powell
4. Turkey Creek
5. Karns
Sub Total
6. Lyon Creek
7. Forks-of-the-River
GRANT) TOTAL

-------
                                                          TABLE V-4



                                     POPULATION PROJECTION'S FOR THE ANTICIPATED FACILITIES-

                                 DOMESTIC,  INDUSTRIAL,  AND COMMERCIAL POPULATION EQUIVALENTS
I
—i
o
I
Facility
1. Knob Creek
2. Loves Creek
Sub Total
3. Powell
4. Turkey Creek
5. .Cams
Sub Total
6. Lyon CreeV
7. Forks-of-the-River
I GRAND TOTAL
knoxville-Knox County
1975
261,195
18,019
279,214
37,011
13,707
5,929
56,647
14,955
10,501
361,317
1980
280.921
18,300
299,221
43,877
15,901
7,025
66,803
15,597
12,568
394,189
1985
295,768
18,582
314,350
50,091
17,014
8,013
75,118
15,996
14,534
419,998
1990
304,236
18,792
323,028
55,324
18,127
8,853
82,304
16,136
14,871
436,339
1995
311,746
19,719
331,465
57,341
18,384
9,126
84,851
16,510
15,533
448,359

-------
                                                   TABLE V-5
                                SLUDGE PROJECTIONS FOR THE ANTICIPATED  FACILITIES
                                                   RAW SLUDGE
                                                    Un tons)6
Facility
4
1. Knob Creek
2. Loves Creek
Sub Total
3. Powell
4. Turkey Creek
5. Karns
Sub Total

4
7. Forks--of~the-River
GRAND TOTAL











1975
764. 00/30. 561
21. 50/ 0.43
785.50/30.99
176. 67/ 2.65
65. 33/ 0.98
2o.uOj U. 4^
270. OO/ 4.05
30. OO/ 0.60
30. 75/ 1.23
1116.25/36.87
1980
821.75/32.87
22. OO/ 0.44
843.75/33.31
209. 33/ 3.14
76. OO/ 1.14

318. 66/ 4 78
31. OO/ 0.62
36. 75/ 1,47
1230.16/40.18
1985
865.00/34.60
22. OO/ 0.44
887.00/35.04
238. 67/ 3.58
81. 33/ 1.22
TO no/ n s?

358. OO/ 5.37
32. OO/ 0.64
42. 50/ 1.70
1319.50/42.75
1990
890.00/35.60
22. 50/ 0.45
912.50/36.05
264. OO/ 3.96
53. OO/ 2.12
7fi flO/ 1 04

343. OO/ 7.12
32. 50/ 0.65
43. 50/ 1.74
1331.50/45.56
1995
911.75/36.47
23. 50/ 0.47
935.25/36.94
273. 33/ 4.10
53. 75/ 2.15
26 75/ 1 07

353. 83/ 7.32
33. OO/ 0.66
45. 50/ 1.82
1367.58/46.74
Process
Description
Primary Sedimen-
tation & Activa-
ted Sludge
Trickling Filter
to Knob Creek^
At Knob Creek
Contract Stabi-
lization2
<1990 contact
sta.>1990 prim.
& act. sludce
Same as Turkey
Creek

Extended Aera-
tion Modified3
Primary & Acti-
vated Sludge
Knoxville-
Knox County
Note: 1. Values given in wet ton3 per day and dry tons per day.
      2. For contact stabilization,  used 143 Ibs. dry solids per day per 1000 people at 1.5Z solids.
      3. For modified extended aeration, used 80 Ibs. dry solids per day per 1000 people at 2.0% solids.
      4. Knob Creek and Forks-of-the-River uet tons are for a thickened sludge at 42 solids and 234 Ibs.  dry
         solids per day per 1000 people.
      5. Trickling filter dry tons based upon 48 Ibs. dry solids per day per 1000 people and 22 solids for
         discharge into sewers to Knob Creek.
      6. tons x 0.91 - metric tons.

-------
                          CHAPTER V
                          REFERENCES
V-l      Knox County Facilities 201 Plan, in progress by Ryckman,
         Edgerley, Tomlinson and Associates, Inc., Knoxville,
         Tennessee (May 7, 1975).

V-2      Information supplied by Mr. Jim Clark of the Wastewater
         Control Department, City of Knoxville to MFC, (6 May 1975).

V-3      Newsletter. TVA  (1 May 1975).

V-4      "Demonstration of a Developed Scheme for the Ultimate
         Disposal of Residual Wastes", Engineering-Science, Inc.,
         EPA Contract 68-01-3225 (A June 1975)

V-5      Guidelines for Areawide Waste Treatment Management
         Planning, Section 208, Federal Water_P_ollut_i_o_n Control
         Act Amendments of 1J7_2, Environmental Protection Agency
         (August 1975).

V-6      Wastewater Treatment Plant Site Evaluation, Knoxville-
         Knox County Metropolitan Planning Commission (8 July 1975).

V-7      Water Quality Management Plan for the French Broad River
         Basin, Division  of Water Quality Control, Tennessee
         Department of Public Health  (undated).

V-8      Water Quality Management Plan for the Hols ton River Basin,
         Division of Water Quality Control, Tennessee Department
         of Public Health (undated).

V-9      Water Quality Management Plan for the Upper Tennessee
         River Basin, Division of Water Quality Control, Tennessee
         Department of Public Health  (undated).

V-10     Sludge Processing, Transportation, and Disposal/Resource
         Recovery; A Planning Perspective, Wyatt, J.M. and White,
         P.E. Jr., Engineering-Science, Inc.,  EPA Contract No.
         68-01-3104  (April 1975).

V-ll     Water and Wastewater Plan; Anderson,  Blount, and Knox
         Counties, Tennessee, Volumes I and II, Allen & Hoshall,
         Consulting Engineers (July 1972) .
                                  -72-

-------
                               CHAPTER VI
            SELECTION OF ALTERNATIVE SLUDGE DISPOSAL OPTIONS
INTRODUCTION

     The Methodology allows for the selection of alternative sludge
disposal options in one of two ways: 1) evaluation of ultimate
disposal options per specific types and quantities of sludge or
2) evaluation of the suitability of an area relative to the known
disposal options.  The primary difference in the selection approaches
is the former initially eliminates disposal options by the types of
sludges to be disposed, while the latter does not.  As a result,
more disposal options are considered in the latter approach.  As
discussed in Chapter III, the study is to utilize the latter selec-
tion approach which does not consider existing or proposed solids
handling processes and resultant sludges as a selection criterion.

     The general sludge disposal options available, as defined in
the Methodology, are: 1) sanitary landfill; 2) ocean disposal;
3) waste disposal ponds; 4) sludge recycling (i.e., land application);
5} land reclamation; and 6) resource recovery.  Resource recovery
includes such alternatives as incineration, pyrolysis, recalcination,
composting, and sludge reuse (e.g., as a fuel or a fertilizer base).
The first three options are traditional methods which have been
utilized within the context of sludge as being a waste to be dis-
posed of as cheaply as possible.  The latter options reflect a
different attitude, one of sludge as a resource, which is currently
being encouraged by Federal and State agencies and environmental
groups.

     In order to define the more feasible or suitable disposal
options to be considered for incorporation into a set of alternative
sludge management plans, a selection procedure was developed.  The
basic steps involved in the procedure were:

     (1)  characterization of the natural and cultural settings of
          the Study Area (Chapter IV);

     (2)  characterization of the sludge disposal problem in the
          Study Area (Chapter V);

     (3)  delineation of the Study Area constraints as derived
          from Chapters IV and V;
                                    -73-

-------
     (A)  evaluation of the sludge disposal options relative to
          the Study Area constraints; and

     (5)  selection of the sludge disposal options for incorpora-
               into alternative sludge management plans.
The critical step in this selection procedure is the delineation
of the Study Area constraints (Step 3).  Based on these environ-
mental, socioeconomic, and institutional conditions and values
assumed to exist in the Study Area, infeasible and inapplicable
disposal options are defined and eliminated from further considera-
tion.  Characterization of the Study Area's natural and cultural sys-
tems was perceived to be a necessary inclusion to this casevstudy to
provide background for readers unfamiliar with the Knoxville-
Knox County area.  This type of knowledge would or should be
resident in a 208 agency and would not necessarily be presented
in a real-life study in the detail or format used in this report.

STUDY AREA CONSTRAINTS

     The environmental, socioeconomic, and institutional constraints
listed below evolved from general comparisons of the desired
characteristics for the siting and institutional arrangements of the
disposal options, as delineated in the Methodology, and the actual
or assumed characteristics presented in Chapters IV and V.  The
environmental constraints defined in this study are primarily site
limiting and do not exclude alternative disposal options per se.
However, these constraints are used in defining suitable site areas,
if any, for the various disposal options considered in the evalua-
tion process.  The socioeconomic and institutional constraints are
of a nature which could exclude entire disposal options (e.g., owing
to the complexity of the implementation required and/or the lack of
appropriate existing institutional mechanisms) .

     Environmental Constraints/Considerations:

             Valley and ridge topography limits the area of
             developable land to valleys and the lower slopes of
             ridges.

             A large proportion of the undeveloped land is forested.

             There are large areas where the depths to bedrock are
             very shallow (less than six feet) .
                                    -74-

-------
     •  The  groundwater hydrology  is primarily carbonate-
       rock type  (i.e.,  fracture  porosity) which is parti-
       cularly  susceptible  to  pollution  from infiltration.

     •  There are  numerous sinkhole areas present which adversely
       affect local  topography and groundwater  quality.

       There are  many  areas susceptible  to  flooding.

Socioeconomic Constraints/Considerations:

     •  The area is rapidly  urbanizing with  major  development
        concentrated in western and north central  Knox County.

     •   Prime agricultural soil areas  are limited  and decreas-
        ing with suburban expansion.

     •   There has been only a limited  demand for sludge product
        by the Study Area public in  the past and current demand
        is declining.

 Institutional Constraints/Considerations:

     •  The  current  "201" and  "208" planning studies require
        immediate  solutions  (i.e., the disposal option must be
        technically, financially, and  institutionally implement-
        able in the  near future).

     •  The sludge disposal option must  guarantee  disposal
         (e.g.,  if public demand is required for disposal, such
        demand  must  exist or be a virtual certainty  at  the  time
        it would  be required).

      -  The area  is institutionally  fragmented  making regional
        or metropolitan solutions uncertain.

         Although regional agencies  exist (e.g., Eastern
         Tennessee Development  District), no regional sludge-
         disposal projects have ever  been implemented.

         The Study Area is just beginning to have problems
         requiring metropolitan or regional solutions.  As a
         result, long-term planning  in related  areas, such as
         solid waste management, is  only starting with no
         commitments being made to a  particular future policy.

         Physical-chemical sludges are not considered in this
         study because of institutional decisions previously made
         excluding the consideration  of a physical-chemical STP
         as a viable treatment  alternative.


                               -75-

-------
EVALUATION OF SLUDGE DISPOSAL OPTIONS

     The principle function of this section was to apply the Study
Area constraints,  as defined above, to the specific disposal options
available in order to evaluate their applicability to the Study Area.
In this study,  this was done by comparing possible impacts,  dis-
advantages, and/or problems for each disposal option, as stated in
the Methodology,  with the Study Area constraints and noting  those
areas where adverse relationships exist.   it was assumed that dur-
ing the course of this process certain disposal options could be
eliminated as infeasible or inapplicable to the needs of the Study
Area, thereby reducing the number of disposal options to be  con-
sidered .

     Before certain disposal options could be analyzed, in particular
land reclamation and sludge reuse, it was necessary to define the
local options available.  In the case of sludge reuse, two alter-
natives were defined.  In addition, during the analysis of the
sanitary landfill option, it became obvious that an alternative type
of landfilling incorporating only sludge (i.e., trenching) would
need to be considered.  As a result, 12 disposal options were
initially defined and evaluated against the Study Area constraints.
A summary evaluation of the sludge disposal options is presented  in
Table VI-1.

Elimination of Infeasible Alternatives

     The sludge disposal options which immediately  fell  out as being
infeasible or inapplicable were ocean disposal, waste disposal ponds,
pyrolysis, and recalcination.  Ocean disposal  is  inappropriate for
geographic and institutional  reasons.  Waste disposal ponds, although
a viable local disposal  method,  require  large  land  areas and are
incompatible with most land uses  for health and aesthetic reasons.
Generally, waste disposal ponds are  utilized by small,  rural waste-
water treatment plants where  land  is  abundant,  cheap,  and relatively
free of people to complain  of  odors.  It  is doubtful  if  waste  dis-
posal ponds could ever be considered  a real disposal  option  for a
treatment plant of any large  size, because of  the  large  land require-
ments and the proximity  to  residential land uses.   Pyrolysis is a
new process which has had only limited field testing.   Primarily
developed to utilize solid waste  refuse, pyrolysis  has  only recently
been considered as a method  to utilize sewage  sludge.   Although a
pyrolysis unit is being  incorporated  into  a large  wastewater treat-
ment plant in Minneapolis/St.  Paul  (as noted in the Methodology),
only 15 to 40 percent of the  sludge  solids are to  be  treated by the
unit.  As a result,  pyrolysis  is  neither a proven  nor  a total  solu-
tion at this time.   Recalcination  is  not  a  feasible alternative
without lime being used  in  the wastewater  treatment process.   As
stated  in Chapter V, no  such  wastewater  processes  currently  exist
                                     -76-

-------
                                                  T/BLE VI-1




                                SUMMARY EVALUATION CF SLUDGE PISPOSAL OPTIONS
SLUDGE DISPOSAL
OPTION
Sanitary Landfill
Trenching
] STUDY AKEA CONSTRAINTS
Environmental
Potential groundwater pollution.
i
Potential groundwater pollution;
substantial land requirements.
Ocean Disposal Unknown impact on ocean ecology.
j
Waste Disposal Ponds Substantial land requiremerts.
, Resource Recovery j
Land Application
Land Reclamation
Inc i nr'r.-it i on
J'yro ] yni a
Reca Ic tnat 1 on
Com posting
Substant1.il land requiremei ts;
potential nurface and grour d-
water pollution.
Potential surface and groui ri-
veter pol lu t ion .
Seme air quality degradation.
None
Socioeconomlc ! Institutional
Requires rural location;
restricts future land use
op c ioTis .
Requires rural location.
Uneconomic distance.
Incompatible with other
land uses.

Requires rural location.
None
None
No market for product.
None None
None
Sludge Reuse: IRD* 1 None
S liid^o Reuse: ' None
TVA Boiler Feed
No market for all of
product .
None
None
Future of solid waste
management uncertain.
Experimental; requires
strict operation and
monitoring.

prohibit new permits.
None

Requires strict opera-
tion and monitoring.
Requires complex insti-
t u t Lonal ar rang erne tit s ,
strict operation snd
monitoring.
None
L.ir^ely experimental;
never bn-n used to
h.^nd le all solids pro-
dured ,
Physical-chemical plant
eliminated frora study.
None

from private company.
Currently only being
considered by TVA
*IRD-Independent Research and  Development Company

-------
or are proposed for future wastewater treatment plants.

Local Definition of General Disposal Options

     Two general disposal options requiring local definition are
land reclamation and sludge reuse.  During this study land re-
clamation feasibility was derived from a general analysis of the
mining operations occurring within the eastern Tennessee region.
Two sludge reuse proposals were identified after discussions with
local planning agencies.  One sludge reuse option is a recent
business proposal made to the City of Knoxville by the Independent
Research and Development Company (IRD) involving the processing of
sewage sludge to a high-nitrogen fertilizer.  The other sludge
reuse option is tied to an on-going study being conducted by TVA.
The study is evaluating the feasibility of regional solid waste
recovery including firing TVA power plant boilers with the organic
fraction of solid waste.  It has been suggested that organic sewage
sludges could be mixed with the solid waste and used as a fuel.

     Within the Study Area, no feasible mining reclamation projects
or possibilities were identified.  Subsequent investigation involved
the use of a regional mineral resource map (Ref. VI-1) and a TVA
study of strip-mined areas in eastern Tennessee (Ref. VI-2).
Synthesis of these sources led to the identification of numerous
potential strip-mine reclamation areas within 20 to 50 miles (40 to
80 kilometers) of Knoxville (Figure VI-1).  Access to these areas
via rail or highway is adequate and over one-third of the haul roads
to abandoned or orphan strip-mine areas are in good condition.   Most
of the orphan strip-mines are of the contour type and are less than
40 acres (16 hectares) in extent; the total bare strip-mine acreage
requiring reclamation being estimated to be 6000 acres (2430 hectares)
(Ref. VI-2).  However, these areas are scattered and a reclamation
project incorporating Study Area sludge would have to be well-
coordinated to minimize transportation costs-

     The IRD sludge reuse option is part of an overall effort  to
develop Pickel Island in Knox County into a "Resource Recovery and
Research Center."  IRD plans to:

     "1.  Construct a wood waste  processing plant that will pro-
         duce marketable steam and commercial grade charcoal.

     2.  Construct a municipal refuse processing plant that will
         provide a fuel product  and recover metals and glass.

     3.  Construct a  rubber tire recycling plant which would pro-
         duce carbon  black and a fuel product.

     A.  Construct a  sewage sludge processing plant  that would
         produce a high-nitrogen fertilizer.
                                     -78-

-------
e
i
                                STRIP-MINE  AREAS  NEAR   KNOX   COUNTY
                                                                    KENTUCKY


                                                                  / TENNESSEE
            \  -
                                                                                    LEGEND
                                                                              .••.•.•;;.-'I Active  Strip-Mine Area


                                                                                    Orphan Strip-Mine Area

                                                                                    Railroad
                                                                                        0    5    10
                                                                                        iii

                                                                                        SCALE IN MILES
                                                                                                          CD


                                                                                                          aj

                                                                                                          m
         SOURCE: References VI-1 and VI-2

-------
     5.  Develop a river terminal and related transportation net-
         work to bring raw wastes to the island from outlying areas.
         Since Knoxville has no public use river terminal, the
         terminal planned for Pickel Island will be used to tranship
         steel and other vital commodities."  (Ref. VI-3)

The IRD sludge processing plant  [100 dry tons/day  (91 metric  tons/
day)] would convert all the sludge from the cities of Knoxville and
Chattanooga into a granular fertilizer which will have,  following
supplemental nutrient (urea)  addition,  a nitrogen content of  15  to
20 percent by weight.  The product is claimed to be in demand in
the professional turf grass and the home and garden market.  The
process used was developed by Organics, Inc. and is discussed in
the Methodology.

Implications of Solid Waste Management  Planning

     Solid waste management in the Study Area is a growing problem,
particularly in regards to the siting  and  operation of  sanitary
landfills.  Currently there is only one  sanitary landfill  operating
in  the Study Area with an expected useful  life of  three years
(Ref.  V-3).  Because of  the increasing  expense  of solid waste
collection and disposal and the  increasing difficulty of locating
both environmentally and  socially acceptable sites, the long-term
objective of solid waste management is  anticipated to be toward
resource recovery  (Ref. VI-4).   Resource recovery  would provide  a
means  for recovering part of the  cost  of solid waste management  in
addition to eliminating the need  to locate an acceptable landfill
site every  few years.  The TVA study mentioned previously  is  currently
dominating  the  local and  regional planning efforts by the  City  of
Knoxville and ETDD.  A TVA-sponsored regional solid waste  recovery
program  is  the  first cnoice  of most  of the Study Area and regional
planning agencies.   As  a  result,  all  solid waste studies are in
 abeyance until  the TVA  study  is  completed, causing the  future of
 solid  waste management  and  the sanitary landfill in  the Study Area
 to be  uncertain.

     When considering  the sanitary  landfill as  an ultimate dis-
 posal  option,  it  should be  recognized  that the  sanitary landfill
 is a solid waste  repository  first and  foremost.   It is  perceived
 that a need for a sanitary  landfill  would  exist, regardless of the
 implementation  of a  solid waste  resource recovery scheme, to dis-
pose of  a small fraction  of  inert residual material.  However,  the
 projected sludge  quantities  to be disposed compared  to  the quantity
 of residual solid waste to be disposed would be so great that normal
 sanitary landfill operation would be impossible.  As  a  result of
 the uncertain future of solid waste  management  in the Study Area,  a
method which approximates the operation and purpose of  a sanitary
 landfill and has  the same sludge condition requirements was introduced-
                                      -80-

-------
trenching.   Trenching  is  a  recent  disposal technique  which  is utilized
exclusively for sludge disposal.   At  this time,  no municipality  is
using this method although  large-scale field studies  have proved its
feasibility (Ref. VI-5) •

 Suitability of  the Study Area for Land Disposal Options

      In  order  to evaluate  the feasibility of  long-term land disposal
 (i.e., sanitary landfill,  trenching,  and  land application), it  was
 perceived  necessary to locate possible site areas within the Study
 Area.  The approach used in  locating  possible site areas was a
 graphical  technique involving factor  maps,  a  factor  map being the
 presentation of a siting criterion such  as existing  land use or sink-
 hole locations.  Many of the factor maps  used were generated during
 the compilation of Chapter IV and are presented as figures in that
 chapter.

      An  important assumption made in  this analysis was  that it  was
 desirable to  locate site areas which  required minimum engineering
 and, as  a result, a minimum cost  to  protect the environment or  to
 prepare  a site for operation.  Consequently,  the  suitable  site  areas
 identified in  the following figures  represent those  areas  which,
 based on the  available data, would  require a minimum engineering cost
 and/or maximum resource utility  of  the  sludge.  This analytical
 technique does not preclude the  existence of reasonable site areas out-
 side those identified as suitable,  but  merely attempts to  locate,  in
 a general fashion, cost-effective site  areas.

      The suitability  analysis began with the listing of siting/
 suitability criteria (i.e., factors) discussed in the Methodology.
 Subsequently,   if they did not already exist, relevant factor maps
 were compiled  from available data.   The  information presented on
 each map was ranked  subjectively on a negative scale where zero =
 no  impact, -L =  some impact, -2 = significant impact, and unsuitable =
 major impact.   Each  factor  map was then  coded per the ranking system.
 The applicable factor maps  were then overlaid and, by visual analysis,
 a  composite map  was  derived which showed the sum of the factor  rank-
 ings for  areas within the Study Area.   The composite map  was then
 further refined  by assuming that all areas with  a summed  factor rat-
 ing greater than -2  were  unsuitable.  Unsuitable in this  case meant
 that significant engineering (and cost)  was  required to improve the
 site characteristics or provide environmental  protection. In  addition,
 only those suitable  site  areas having  sufficient areal extent  to
 incorporate the anticipated sludge volume to be  generated in the
 Knoxville-Knox County County between 1975 and  1995  are presented.

      The  factor maps used and their  ranking for  each disposal  or
 management option are  presented  in  Table VI-2.   Some of  the factors
 utilized (e.g., sinkhole  areas,  flood-prone areas,  etc.)  were  declared
                                   -81-

-------
              TABLE VI-2
FACTOR MAPS  AND RANKING USED FOR SITE
         SUITABILITY ANALYSES
FACTOR MAPS
Carbonate-rock Area
Sinkhole Area
Percent Land Slope
i 32
3%-9%
> 92
Depth to Bedrock
< 6 feet (carbonate rock)
< 6 feet (non-carbonate rock)
i. 6 feet
Flood-prone Areas
Soil Utility
Prime agricultural soil
Secondary agricultural soil
Other soils
Forested Areas
Existing Land Use
Proposed Land Use
Residential
Industrial
Distance from Knoxville
6-8 miles
> 8 miles
FACTOR RANKING
Sanitary
Landfill
-1
Unsuitable

-1
0
0

Unsuitable
-2
0
Unsuitable

Unsuitable
0
0
Unsuitable
Unsuitable

-1
-1

-1
-2
Trenching
0
Unsuitable

0
0
0

Unsuitable
-2
0
Unsuitable

Unsuitable
0
-1
Unsuitable
Unsuitable

-2
-2

0
0
Land
Application
0
Unsuitable

0
-1
Unsuitable

-2
-2
0
Unsuitable

Unsuitable
0
-1
Unsuitable
Unsuitable

-2
-2

0
0
                    -82-

-------
unsuitable initially and deserve some further explanation.   Sinkhole
areas were undesirable locations because of their direct connection
with the underlying groundwater system and disruptive topographic
expression (i.e., deep depressions).  Flood-prone areas were unsuit-
able for obvious reasons related to site safety, operability, and
environmental protection.  Prime agricultural soils were considered
a valuable local resource which should be preserved where
possible.  Forested areas were considered unsuitable for
ecological purposes, particularly wildlife habitat alteration, and
the cost of clearing.  Existing land use areas (i.e., residential,
industrial, and recreational) were excluded from consideration
because of their already existing utility which would be disrupted
and/or degraded by the incorporation of sanitary landfill,  trenching
or land application systems.

     For the purposes of this study, identification of suitable
land disposal sites ended with this process.  Ideally, if a similar
analysis were performed in the future, actual site visits would be
desirable in order to field-check and refine the ""imits of possible
site areas.  Suitable site areas within the Study Area were identi-
fied for sanitary landfills, trenching, and land application and
are shown in Figures VI-2, VI-3, and VI-4.  As a result, all the
land disposal options remained as feasible disposal options to be
considered further.

Alternative Disposal Options Selected  for  Further Review

     Of  the  12  alternative  sludge disposal options  originally
considered in  this  study, four have been  previously defined  as
infeasible or  inapplicable:  1)  ocean  disposal;  2)  waste disposal
ponds;  3)  pyrolysis; and  4)  recalcination.   The  remaining  eight
alternatives appear  to  be environmentally  and  socioeconomically
feasible.  However,  some do  not  meet the  institutional constraints
defined  earlier in  this Chapter.  The  particular constraints violated
are:   1)  an  immediate  solution;  and 2)  guaranteed  disposal.

     Land  (i.e.,  strip-mine)  reclamation,  although  a desirable  sludge
use, would require  extensive investigation into  the institutional
responsibilities involved.   During  the course  of this study,  no
 institution  was identified  as  having or taking responsibility for
the unreclaimed strip-mine  areas and no studies  had been conducted
considering  such a  reclamation approach.   It was considered  to be
beyond the scope of  this study to initiate or  formulate institutional
arrangements to increase the feasibility  of this alternative.  As
a result,  although  it  is an attractive future  possibility,  strip-
mine reclamation does  not meet the  immediate needs of the  study.

     For essentially the same  reason,  the sludge reuse option that
would  burn sewage sludge with  solid waste refuse in TVA power plant
                                   -83-

-------
                               KNOXVILLE AND KNOX COUNTY
                         SANITARY LANDFILL SITE SUITABILITY MAP
00
r
                                                                         Possible Site Areas
                                                                                       o
                                                                                       a
                                                                                       i
                                                                                       ro

-------
                               KNOXVILLE  AND  KNOX COUNTY
                             TRENCHING  SITE  SUITABILITY  MAP
00

Y1
                                                                        Possible Site Areas
                                                                                      c
                                                                                      TO
                                                                                      m

-------
                               KNOXVILLE AND  KNOX  COUNTY
                         LAND  APPLICATION SITE SUITABILITY MAP
00
                                                                        Suitable Site Arta
                                                                                    o
                                                                                    c
                                                                                    m
                                                                                    <
                                                                                     i

-------
boilers is also put off as a possible near terir. alternative.   The
initial results of the TVA study, which will probably not be avail-
able until late in 1975, will be looking at solid waste only.  If
TVA decides that using solid waste refuse to fire boilers is both
feasible and desirable, then the addition of sewage sludge should
be investigated.  Consequently, the TVA nnsition on burning sewage
sludge will not be known for some time.

     Composting of sewage has only rarely been economically success-
ful in this country.   This has been primarily due to a lack of a
market for the product.  Although there is a history of the local
public hauling substantial quantities of sludge from existing
treatment plants in the area, this practice appears to be declin-
ing (see Chapter V of this report).   Moreover, the sludge was
supplied at no cost.   One can assume that if there were to be a
charge for compost, it would only decrease the demand of the
compost product.

     The remaining sludge disposal options to be considered, then,
which will be incorporated into alternative sludge management plans
are:

     (1)  sanitary  landfilling;

     (2)  trenching;

     (3)  incineration;

     (A)  land application-spray  irrigation;

     (5)  land application-composting; and

     (6)  sludge reuse-IRD.

Descriptions and evaluations of  these alternative disposal options
occur  in the subsequent Chapter.  The sludge  conditions required
for the disposal options are presented  in Table VI-3.
                                     -87-

-------
                           TABLE VI-3

                 SLUDGE CONDITION REQUIRED FOR
                 ALTERNATIVE DISPOSAL OPTIONS
  ULTIMATE DISPOSAL
       OPTION
 SLUDGE CONDITION*
 1.   Sanitary Landfilling

 2.   Trenching
 3.   Incineration

 4.   Land Application:
       Spray Irrigation

 5.   Land Application
       Composting

 6.   IRD (fertilizer base)
Digested, Dewatered

Digested, Dewatered
    (Ref. VI-5)

     Dewatered
     Digested


Digested, Dewatered

Digested(Ref. VI-3)
*Note:   Unless noted otherwise, the reference for the sludge
        condition requirement is the Methodology.
                                 -88-

-------
                             CHAPTER VI
                             REFERENCES
VI-1     "Mineral Resources of the Tennessee Valley Region (Map),"
         Tennessee Valley Authority,  Div.  Water Control Planning,
         Geologic Branch (1970).

VI-2     Information supplied by Allen Curry of Tennessee Valley
         Authority, Knoxville, Tenn.  (July 1975).

VI-3     "Pickel Island-A Regional Resource Recovery and Research
         Center," Independent Research and Development Company,
         Knoxville, Tennessee (April 1975).

VI-4     "Solid Waste Management Plan for Anderson, Blount, and
         Knox Counties, Tennessee," prepared by Allen & Hoshall
         Engineers, for East Tennessee Development District,
         Knoxville, Tenn. (Oct. 1971).

VI-5     "Trench Incorporation of Sewage Sludge," Walter, J. M. in
         Municipal Sludge Management, proceedings of National
         Conference on Municipal Sludge Management (June 1974).
                                    -89-

-------
                             CHAPTER VII
               DEVELOPMENT AND EVALUATION OF ALTERNATIVE
                        SLUDGE MANAGEMENT PLANS
INTRODUCTION

     Having defined the quantity and distribution of raw sludge to
be disposed (Chapter V) and the feasible disposal options (Chapter
VI), the next step was to synthesize these data into alternative
sludge management plans.  The development of a sludge management
plan includes the definition of a solids handling system for each
sewage treatment plant considered, the transportation scheme for
solids handling and/or disposal, and the ultimate disposal method.
Subsequently, these plan aspects  (i.e., solids handling, trans-
portation, and disposal) were evaluated according to the criteria
and procedures presented in Chapter VII of the Methodology.

DEVELOPMENT OF ALTERNATIVE SLUDGE MANAGEMENT PLANS

     Although only six ultimate disposal options were defined as
feasible within the Study Area, the number of possible solids
handling and transportation schemes that could be combined with
each disposal option is quite large.  As a result, the several
alternative sludge management plans developed are largely represen-
tative.  For the purposes of this study, only one management plan
was developed for each disposal option with each management plan
incorporating a regional solution where possible.  The latter con-
dition (regionalization) was imposed at the request of the MPC, the
current 208 planning agency, and is in keeping with its planning
perspective and objectives.

Alternative 1 - Sanitary Landfill

     This alternative represents the base case as most existing and
proposed STP's in the Study Area currently use or intend to use
sanitary landfilling as their ultimate disposal method.  Based on
the suitability analysis performed earlier in the study, it was
assumed that sanitary landfill sites would be available for the
design period (i.e., 1975 to 1995).  However, current local and
regional solid waste management plans are recommending alternative
disposal schemes for solid waste which would eliminate the sanitary
landfill as a disposal method  (see Chapter VI).  As a result,
although the existence of sanitary landfills is assured for the next
several years, the longer-term is far less certain.

     The solids handling processes vary from plant to plant and
were based on existing or proposed processes.  This is a deviation
                                  -90-

-------
in concept from the Methodology approach but it is justified some-
what in its truer representation of the base case situation.  In
the development of all the alternatives, the solids handling sys-
tems for existing and proposed STP's were used in part or in total
if they met the required sludge condition for the various disposal
options.  The Methodology was used to define any additional or
substitutive solids handling processes required.

     The sludge condition required for sanitary landfill disposal
is digested and dewatered.  Aerobic digestion would be utilized by
Powell, Turkey Creek, Karns, and Forks-of-the-River STP's.
Anaerobic digestion preceded by gravity thickening would occur in
Knob Creek and Lyon Creek STP's.  Dewatering would be accomplished
by pressure filtration in Knob Creek and Powell STP's, sand beds
in Turkey Creek, Lyon Creek, and Forks-of-the-River STP's, and
vacuum  filtration in Karns STP.

     The raw-sludge quantities presented in Chapter V of  this
report  and the  following  assumptions  (from information presented  in
Chapter IV of  the Methodology) were used to project sludge  quantities

     (1)  A 40 percent reduction in the dry solids input during
          both anaerobic  and aerobic digestion;

     (2)  for anaerobic digestion a three percent solids output
          and  for aerobic digestion a  four percent solids output;

     (3)  pressure filtration  and sand bed dewatering produces a
          cake  dry solids content by weight of  40 percent, while
          vacuum  filtration produces  a cake dry solids content by
          weight  of  20 percent  and  the specific gravities of both
          types of cake are  equal;  and

      (4) a specific  gravity  of  the digested,  dewatered  sludge  of
          0.95  which  is used  to  convert from  wet tons per day  to
          cubic yards per day  as follows:


          yd3   _  wet  tons  (2000  Ib.      ft3       yd3      JL
           day        day    \wet  ton    62.4 Ib.    27 ft^   0.95J

                           3             /        3\
                         yd  _ wet tons  [ 1.25 yd  1
                         day     day     \ wet ton f

 Table VII-1 presents the estimated sludge production for various
 design years.
                                                                »
      The dewatered sludges would then be transported via a trucking
 operation to a landfill site near the currently operating sanitary
                                   -91-

-------
                                                                     TABLE VII-1
                                                  SLUDGE  PROJECTION'S  FOR_T] 1 K_ANTICIPATED FACILITIES

                                           ALTERNATIVE 1 - SANITARY  LANDFILL  A.ND  ALTERNATIVE 2 - TRENCHING
to
 I
Facility
1. Knob Creek
2. Loves Creek
Sub Total
3. Powell
4. Turkey Creek
5. Karns
Sub Total
t
6. Lyon Creek
!7. Forks of the River
1
GRAND TOTAL
1
1975
45. 85/57. 311
0.65/0.81
46.50/58.12
3.98/4.98
1,48/1.85
1.25/1.56
6.71/8.39
0.90/1.13
! 1.85/2.31
55.96/69.95
1980
49.30/61.63
0.65/0.81
49.95/62.44
4. 70/5.88
1.70/2.13
1.50/1.88
7.90/9.89
0.93/1.16
2.20/2.75
60,98/76.24
1985
51.90/64.88
0.65/0.81
52.55/65.69
5.38/6.73
1.83/2.29
1.70/2.13
8.91/11.15
0.95/1.19
2.55/3.19
64.96/81.22
1990
53.40/66.75
0.68/0.85
54.08/67.60
5.95/7.44
3.18/3.98
3.10/3.88
12.23/15.30
0.98/1.23
2.60/3.25
69.89/87.38
1995
54.70/68. 38
0.70/0.88
55.40/69.26
6.15/7.69
3.23/4.04
3.20/4.00
12.58/15.73
1.00/1.25
2.73/3.41
71.71/89.65



watered sludge
to either
sanitary land-
fill or trench-
ing


Knoxville-
Knox County
              Note:  1. Values given in wet  tons  per  day  and  wet  cubic yards per day.

-------
landfill site near Rutledge Pike in northeastern Knox County.
Trucking distances would vary from 12 to 31 miles (19.3 to 49.9
km) depending on the location of the treatment facility.   There
the sludge would be mixed and buried with the daily collections of
municipal refuse.  No significant increase in landfill volume
required is expected from this practice due to the Z-rgely liquid
nature of the sludge (i.e., the sludge would merely fill in the
spaces within the solid waste).

     Each treatment facility would operate independently in this
alternative.  It is assumed that the County would continue to
operate the sanitary landfill, charging a user's fee of $6.00  per
wet short ton ($6.60 per wet metric ton).

Alternative 2 - Trenching

     As discussed in Chapter VI, trenching (i.e., the burial of
sludge in trenches) was introduced into this study as an alterna-
tive to sanitary landfills.  The solids handling systems (and the
estimated sludge production) and transportation plans are the same
as those for Alternative 1.

     Using  the site suitability map developed for Chapter VI,  a
trenching   site was located in the same general area as the sani-
tary landfill in Alternative 1.  The area required to dispose the
sludge estimated to be generated in the Study Area from 1975 to
1995 (1,110,000 yd3 or 839,160 cu m) is 500 acres (202.5 ha).   This
is based on a trench width of two feet  (0.61 m), trench depth of
three feet  (0.91 m), and trench spacing of two  feet  (0.61 m).
An additional 200 acres to be used for buffer, buildings, and
equipment storage would also be required.

          It was assumed that the City of Knoxvllle would own  and
operate the trenching facility.   The City was selected for this
function over the County and utility districts because it has  the
largest financial, administrative, and technical base in addition
to being the largest user of the facility.  Although the suitable
site areas  for trenching are outside its corporate limits, the City
does have the legal powers (i.e., eminent domain) and precedent
(e.g., Knoxville Municipal Airport) to condemn  land and operate
facilities outside its jurisdiction.  The City would charge a
user's fee  to the County and each participating utility district
utilizing the facility.

Alternative 3 - Incineration

     Incineration of sewage sludges is a common disposal method  in
many areas  of the country.  In this alternative, one  regional  in-
cinerator located at Knob Creek would incinerate undigested dewatered
sludge from the  Knob Creek, Powell, Turkey Creek,  and Karns STP's.
                                 -93-

-------
Lyon Creek and Forks-of-the-River STP's would dispose their digested
and dewatered sludge to a sanitary landfill per Alternative 1 because
of their proximity to probable landfill sites and small sludge
contributions.

     "ndigested primary and secondary sludges would be conditioned
with lime and ferric chloride prior to dewatering by pressure fil-
tration.  In addition to conditioning the sludge for dewatering,
lime addition would also stabilize the raw sludge and minimize the
possible public health risk of transporting raw sludge from the out-
lying treatment plants to Knob Creek.

      The  following assumptions based upon information provided  in
 the  Methodology were utilized  to estimate sludge and ash  production.

      (1)   Pressure filtration and  sand  bed  dewatering produces  a
           cake dry solids  content  by weight  of  40 percent;

      (2)   a  specific gravity of  the  undigested,  dewatered  sludge  of
           0.95 used  in  the  same  manner  as indicated  earlier;

      (3)   lime and ferric  chloride addition  prior to pressure
           filtration increases dry weight by  25  percent;

      (4)   incineration  provides  a  volume  reduction of 80  percent
           and a weight  reduction of  75  percent;  and

      (5)   Lyon Creek and Forks-of-the-River  solids handling  is
           the sarae as  for Alternative 1.

 Table VII-2  indicates  the amount of  incinerator  ash  to be  disposed
 into  a  sanitary landfill for Knob  Creek,  Loves  Creek  Powell
 Turkey  Creek,  and  Karns, and the digested,  dewatered sludge  to  the
 landfill  for  Lyon  Creek and Forks-of-the-River.

      A  multiple-hearth  incinerator was  assumed  for treatment be-
 cause it  is  simple,  durable, and has lower  capital and operating
 c^sts than other types  of incinerators.   At  30  to 40 percent solids
 content,  the  undigested, dewatered sludge should  have sufficient
 energy  for self-sustaining  combustion in  the  incinerator,  thereby
 eliminating  supplemental fuel costs.  Air pollution  control  equip-
 ment, such as  scrubbers and cyclone  separators,  has  been  included
 in the  capital and operating costs.   The  incinerator ash would  be
 trucked to a  local  landfill for  disposal.

      Ic --.-as  assumed  that each participating utility  would  be charged
 a^user  s  fee  by the  City for use of  the incinerator  and transporta-
 tion  and  disposal  costs of  the ash to a landfill.
                                   -94-

-------
                                                                        TAJ8LE  VII-2
                                                    SLUDGE PROJECTION::_ FOR  THE ANTICIPATED FACILITIES
                                                               ALTERN.VIVE  3 - INCINERATION
 I
\D
Facility
1
1. Knob Creek
2. Loves CreelT
Sub Total
1
3. Powell1
4. Turkey Creek
5. Karns
Sub Iota I
2
6. Lyon CrepV'
7. Forks-of-che-River
1 GRAND TOTAL
!
1975
7.64/38.16
0.11/0.54
7.75/38.70
0.66/1.66
0. 25/0.61
0.11/0,52
1.02/2.79
0.36/1. 13
0.74/2.31
9.87/44.93
1980
8. 22/41.07
0. 11/0.55
8.33/41.62
'0.79/1,96
0.29/0.71
0. 13/0.62
1.21/3.29
\
', 0.37/1.. 16
I 0.88/2.75
!
! 10.79/48.82
1985
8. 65/43. 2*.
0.11/0.55
8.76/43. 79
0.90/2.24
0.31/0.76
0.14/0.71
1.35/3.71
0.38/1.19
1.02/3.19
11.51/51.88
1990
8.90/44.48 '
0.11/0.56
9.01/45.04
0.99/2.47
0. 53/1.32
0.26/1.30
1.78/5.09
0. 39/1.23
1.04/3.25
12.22/54.61
1995
9.12/45. 58
0.12/0.59
9.24/46.17
1.03/2.56
0.54/1.34
0. 27/1.34
1.84/5,24
0.40/1.25
1.09/3.41
12.57/56.07 I


Incinerator ash
to landfill

Digested, De-
watered, truck
to landfill

-------
Alternative 4 - Land Application: Spray Irrigation

     Spray irrigation of liquid sludge on agricultural land has
received considerable attention in recent years because of its
beneficial effect on crop p inactivity .  This alternative sludge
management plan would utilize digested sludge from all the waste-
water treatment plans except Forks-of-the-River STP, which would
continue to dispose its sludge- to a sanitary landfill.  It was
assumed that, because of the substantial industrial contribution to
Forks-of-the-River STP, as noted in Chapter V of this report, the
heavy metal content of the sludge would be too high for safe long-
term application to agricultural land.

     The remaining wastewater treatment plants would end their
solids handling processes with either aerobic or anaerobic
digestion.  The liquid sludge would then be transported by tank
truck to the land application site and pumped into a storage lagoon
for later application.  The transportation distances to the site
vary from 14 to 40 miles (22.5 to 64.4 km).

     The following assumptions based upon information provided in
the Methodology were utilized to project sludge production.

     (1)  A 40 percent reduction in the dry solids input during
          both anaerobic and aerobic digestion;

     (2)  for anaerobic digestion a three percent solids output
          and for aerobic digestion a four percent solids output;

     (3)  a specific gravity of the digested sludge of 1.03
          which is used to convert from wet tons per day to cubic
          yards per day as follows:


          yd3  =  wet tons  / 2000 lb .       ft3        yd3      _J. _
          day       day     ^wet ton   X  62.4  lb . X  27 ft3  X  l.Q3j


                    3               /           3  \
                  yd      wet tons  I,  nror   yd    \
                   —     — - - —          — — • — —
                  .                    .
                  day       day     \        wet ton/

     (4)   Forks-of-the-River solids handling the same as for
          Alternative 1.

Table VII- 3 indicates the amount of digested, undewatered sludge
from Knob Creek and  Loves Creek, Powell, Turkey Creek, Karns , and
Lyon Creek to be applied to the land and the digested, dewatered
sludge from Forks-of-the-River to the landfill.
                                   -96-

-------
                                                     TABLE VII-3
                                    SLUDGE  PROJECTIONS FOR THE ANTICIPATED FACILITIES
                                    ALTERNATIVE  4  -  LAND  APPLICATION: SPRAY  IRRIGATION
Facility
1. Knob Creek
1
2. Loves Creek
Sub Total
3. Powell1
4. Turkey Creek
5. Karns
Sub Total
6. Lyon Creek
Sub Total
2
7, Forks-of-the-River
GRAND TOTAL
in cubic yards per day
1975
18.34/704.56
0.26/ 9.99
18.60/714.55
1.59/ 45.81
0.59/ 17.00
0.25/ 7.20
2.43/ 70.01
0.36/ 13.83
21.39/798.39
1.85/ 2.31
800 . 70
1980
19.72/757.58
0.26/ 9.99
19.98/767.57
1.88/ 54.17
0.68/ 19.59
0.30/ 8.64
2.86/ 82.40
0.37/ 14.21
23.21/864.18
2.20/ 2.75
866.93
1985
20.76/797.54
0.26/ 9.99
21.02/807.53
2.15/ 61.95
0.73/ 21.03
0.34/ 9.80
3.22/ 92.78
0.38/ 14.60
24.62/914.91
2.55/ 3.19
918.10
1990
21.36/820.59
0.27/ 10.37
21.63/830.96
2.38/ 68.57
1.211 36.59
0.62/ 17.86
4.27/123.02
0.39/ 14.98
26.29/968.96
2.60/ 3.25
972.21
1995
21.88/840.56
0.28/ 10.75
22.16/851.31
2.46/ 70.88
1.29/ 37.17
0.64/ 18.44
4.39/126.49
0.40/ 15.36
26.95/993.16
2.73/ 3.41
996.57
To Land
Application
Site

To Sanitary
Landfill
Knoxville-
RJIOX County
Note: 1. Values given in dry tons per day and dry cubic yards per day for Knob Creek, Loves Creek, Powell,  Turkey Creek,
         Karns, and Lyon Creek and the resultant subtotal to land application site.
      2. Values given in wet tons per day and cubic yards per day for Forks-of-the-River to sanitary landfill or
         on-site disposal.

-------
      The land application site assumed for this study was located
 using the land application suitability map developed in Chapter VI
 and would occupy that area adjacent to and west of House Mountain
 in northeastern Rnox County.   The land requirements for the land
 application area are estimated to be 670 acres (271 ha).  This is
 based on an application rate  of 15 dry short  tons of sludge/acre/
 year (34 dry metric tons/ha/year) and the estimated 1995 sludge
 production for the Study Area (see Table VII-3).   The application
 rate is  an average rate for humid climatic regions and was obtained
 from the Methodology.  Because of the high water  content of the
 sludge,  a subsurface collection system would  need to be installed
 to collect leachate for water quality analysis and possible treat-
 ment before discharge to surface water courses.   An additional 330
 acres (134 ha)  would be acquired for buffer land  and a storage
 lagoon.   The storage lagoon would be capable  of holding liquid
 sludge for the  several month  period between growing seasons and
 would be 15 to  20  acres (6 to 8 ha) in area (six-month storage
 capacity).

      Because of the  large  and  long-term  land  requirements  of the
 spray irrigation system, a joint  City/County  ownership  of  the  sys-
 tem was  assumed to be  the most viable  institutional  arrangement.
 For  the  purposes of  this study,  the  County would  own the land while
 the City would own and  operate the  storage, application, and
 collection  facilities.  Acreage would  be  leased to local farmers
 for  crop production with the  crops  grown  monitored by  the  state
 public health department which is operated at  the County level.
 User  charges would be  levied  on  the  participating utility  districts.
 No leasing revenues were included in the  economic analysis.

 Alternative 5 - Land Application; Composting

     This is a unique  alternative developed for this study.  In
 concept,  it is similar  to Alternative  4  in that the  sludge would be
 applied  to agricultural land  to benefit  crop  production.   Instead
 of liquid sludge, however, digested, dewatered sludge and  compost
would be applied to  the land  during  the  period between  growing
 seasons.   During the growing  season, the  digested, dewatered sludge
would be composted and  stored.  Depending on  the  demand, a
 quantity of compost  could be  packaged  for public  sale.   If public
demand were substantial, a significant reduction in  land require-
ments at  the land application site could be realized in addition
 to increased revenue.

     As  in Alternative 4, all the wastewater  treatment plants would
participate except for Forks-of-the-River STP  which would dispose
 to a landfill.  The solids handling processes  and the pertinent
 assumptions for the wastewater treatment plants would be the same
                                   -98-

-------
as those for Alternative 1, the required sludge conditions being
the same.  Table VII-4 presents the anticipated sludge production
from these processes for various years.  The dewatered sludges
would be transported via container truck to the land application
si te.

     The composting and land application site location and area re-
quirements are identical to those of Alternative 4.  However,
owing to the low water  content of the  dewatered sludge and compost,
site development would  not require subsurface collection  or spray
application systems.  The  composting area would require a five
acre (2 ha) concrete pad for sludge processing  (i.e., bulking and
 windrowing) and storage.

     The institutional  arrangements and rationale  for Alternative
4 were assumed to apply to this alternative, also.  No leasing  or
composting revenues were considered in the  economic analysis.

Alternative 6 - Resource Recovery; IRQ

     As  discussed in Chapter VI,  Independent Research  and Develop-
ment Company  (IRD) has  proposed to develop  a resource  recovery
center on Pickel Island, located  near  the mouth of the French
Broad in eastern Knox County.  Among its planned  operations  is  a
sludge processing plant that would convert  wastewater  sludges from
the  Chattanooga and  Knoxville  metropolitan  areas  into a  high nitro-
gen  fertilizer.  For  this  alternative, all  the  wastewater treatment
plants  (including  Forks-of-the-River STP) would deliver  a digested
liquid sludge  to IRD.

     The solids handling processes would end with digestion, either
aerobic  or  anaerobic depending upon the facility  producing the
sludge  quantities  presented  in Table VII-5. The  liquid  sludge would
be transported  via tank truck  to  Pickel Island  except for that of
Knob d-eek  STP  which would be  barged.   It  was  assumed that each
 treatment  facility would make  its own  transportation  arrangements
 and  that IRD would provide a vacuum filter dewatering process and
 charge  a dewatering fee for  liquid sludge  received.

EVALUATION OF ALTERNATIVE  SLUDGE  MANAGEMENT PLANS

     The six sludge management alternatives were  evaluated with
respect  to economics, environmental factors, feasibility,  and per-
formance according to the  guidelines presented  in Chapter VII of
the Methodology.  Table VII-6  shows the completed  sludge  management
evaluation matrix.  The bases  of  the quantifiable  (i.e.,  economics)
and  qualitative  (i.e.,  environmental,  feasibility, and performance)
factors  are presented in the following sections.
                                   -99-

-------
                                                                 TABLE VII-4
                                               SLUDGE  PROJECTIONS  FOH  THE ANTICIPATED_FACILITIES

                                                  ALTERNATIVE  5  -  LAN3 APPLICATION: COMPOSTING
Facility
1. Knob Creek
2. Loves Creek.
Sub Total
3. Powell
4. Turkey Creek
5. Kama
Sub Total
6. Lyon Creek
Sub Total
7. Forks-of-the-River
GRAKD TOTAL
1975
45.857 57. 311
0.65/ 0.81
46. 50/ 58.12
3.98/ 4.98
1.48/ 1.85
1.25/ 1.56
6.71/ 8.39
0.90/ 1.13
54. ll/ 67.64
1.857 2.31
55.967 69.95
1980
49.307 61.63
0.657 0.81
49.95/ 62.44
4.707 5.88
1.70/ 2.13
1.507 1.88
7.907 9.89
0.937 1.16
58.787 73.49
2.20/ 2.75
60.987 76.24
1985
51.907 64.88
0.65/ 0.81
52.557 65.69
5.387 6.73
1.837 2.29
1.707 2.13
8.91/ 11.15
0.957 1.19
62. 41/ 78.03
2.55/ 3.19
64.96/ 81.22
1990
53.407 66.75
0.687 0.85
54.087 67.60
5.957 7.44
3.18/ 3.98
3.10/ 3.88
12.237 15.30
0.987 1.23
67.297 84.13
2.607 3.25
69.897 87.38
1995
54.707 68.38
0.70/ 0.88
55.407 69.26
6.157 7.69
3.237 4,04
3.207 4.00
12.587 15.73
l.OO/ 1.25
68.987 86.24
2.737 3.41
71.717 89.65
To Compost
Site

To Sanitary
Landfill
Knoxville-
Knox County
o
o
I
             Note;  1.  Values given in wet tons per day and wet cubic yards per day.

-------
                                                    TABLE VII-5
                                SLUDGE PROJECTIONS  FOR THE ANTICIPATED FACILITIES

                                      ALTERNATIVE 6  -  RESOURCE RECOVERY: IRQ
i
t—'
o
t—'
i
Facility
1. Knob Creek
2. Loves Creek
Sub Total
3. Powell
4. Turkey Creek
5. Karns
Sub Total
6. Lyon Creek
7. Forks of the River
GRAND TOTAL
1975
611. 33/704. 56 1
8.67/9.99
620.00/714.55
39.75/45.31
14.75/17.00
6.25/7.20
60.75/70.01
12.00/13.83
18.50/21.32
711.25/819.71
1980
657.33/757.58
8.67/9.99
666.00/767.57
.47.00/54.17
17.00/19.59
7. 50/8.64
71.50/82.40
12.33/14.21
22.00/25.36
771. 83/889. 5i
1985
692.00/797.54
8.67/9.99
700.67/807.53
53.75/61.95
18.25/21.03
8. 50/9.80
80.50/92.78
12.67/14.60
25.50/29.39
819.34/944.30
1990
712.00/820.59
9.00/10.37
721.00/830.96
59.50/68.57
31.75/36.59
15.50/17.86
106.75/123.02
13.00/14.98
26.00/29.97
866.75/998.93
1995
729.33/840.56
9.33/10/75
738.66/851.31
61.50/70.88
32.25/37.17
16.00/18.44
109. 75/126.49
13.33/15.36
27.25/31.41
888.99/1024.57
Digested sludge
to Pickel Island
Knoxville-
Knox County
             Note
                 : 1. Values in wet tons per day and wet cubic yard: per day.

-------
                                                           TABLE VII-6A
                                                 ALTERNATIVES  EVALUATION  MATRIX
                                              Economics and  Environmental Factors
PARAMETERS
ECONOMICS

ENVIRONMENTAL
FACTORS
CAPITAL COST
ANNfAL CAPITAL
AMORTIZATION
0. AND H. COST
RECLAMATION*
RL'.'ENIT
PRESENT WORTH

WATER QUALITY
AIR QUALITY
LAND QUALITY
FLORA AND FAUNA
AESTHETICS
PUBLIC HEALTH
COMMUNITY IMPACT
RESOURCE
CONSERVATION
ALTERNATIVE 1
$ 4,836,000
S , 456,000-
$ 484,000
S 13,000
S 9,828,000
RATING
it
No change In any water quality
Produces sight increases in odors
and truck emissions
Ultimately limits soil produc-
tivity and use options
ALTERNATIVE 2
S 6,876,000
$ 649,000
$ 496,000
S 13,000
511,994,000
RATING
*«
No change in any water quality
Produces slight increases in odors,
dust, and truck emissions
Increase soil productivity;
limits use options
Severely disrupts local ecology j Severely disrupts local ecology
Degradation of aesthetic qualities
In some local areas
No change in public health

No change in social or physical
elements of the community
Maintains present level of energy
and materials resource usage
Some loss of areas with desirable
aesthetic qualities
Some Increase in public health
involvement
Involves displacement of resi-
dents from community
Increase primary resource con-
sumption and decreases secondary
resource production
ALTERNATIVE 3
$ 5,099,000
$ 481,000
$ 357,000
$ 0
$ 8,879,000
RATING
No change in any water quality
Produces slight increases in odors,
dust, and truck emissions
No change In land quality
Has only Minor Impact on ecology
N- changes in present aesthetic
qua I i ty
No change in public health
invo Ivement
Increases noise or odor levels In
community
sumption and decreases secondary
resource production
o
Ni
I
            * Methane recovery from anaerobic digestion
            ** Lf site is properly managed
            Note:  1. See also Table VII-7

-------
                                                  TABLE  VII-6A  (Continued)



                                              ALTERNATIVES EVALUATION MATRIX

                                            Economics and Environmental Factors
PARAMETERS
ECONOMICS
CAPITAL COST
AN-NUAL CAPITAL
AMORTIZATION
0. AND M. COST
RECLAMATION*
RKVENUE
PR£SENT WORTH

ENVIRONMENTAL
FACTORS
WATKR QUALITY
AIR QUALITY
LA.ND QUALITY
ALTERNATIVE 4
5 9.060,000
$ 855,000
$ 938,000
$ 13,000
5 18,965.000
RATING
**
No changes In any w.iter quality
Produces slight increases In odors
and truck emissions
Increuses soil productivity
FLORA AND FAUNA Severely disrupts sone local ecology
AESTHETICS
Df|;r:ii!.it Ion of aesthetic qualities
in some local areas
PUBLIC HEALTH Increases potential of harm to
public health
COMMUNITY IMPACT
RESOURCE
CONSERVATION
Involves displacement of residents
from community
Promotes beneficial use of sludge
and reduces usage of natural
resources
ALTERNATIVE S
5 6,536,000
$ 617,000
$ 561.000
$ 13,000
12,342,000
RATING
**
N.I ch.infjCH In any uatc-r quality
dust, and truck emissions
Increases soil productivity
Si-verely disrupts some local ecology
IVKr.id.it ion of aesthetic qualities
in iome local areas
Increases potential of harm to
public health
Involves displacement of residents
from community
Proaotes beneficial use of sludge
a. id reduces usage of natural
resources
ALTERNATIVE 6
$ 4,304,000
$ 406,000
$ 565,000
$ 13,000
$10,147,000
RATING
*»
No cli.m|;c8 In any u.-itcr quality
and tug and truck emissions.
No change In land quality
No impacts on ecology
No ch.inge In present aesthetic
quality
No change In public health Involve-
ment
No change in social or physical
elements of the community
Promotes beneficial use of sludge
and reduces usage of natural
resources
o
u>
I
           *  Methane recovery from anaerobic digestion

           ** If site is properly managed


           Note:  1.  See also Table VII-7

-------
                                                    TABLE VII-6B


                                          ALTERNATIVES EVALUATION MATRIX

                                            Feasibility and Performance
PARAMETERS
FEASIBILITY
PERFORMANCE
FINANCIAL
FEASIBILITY
PUBLIC
ACCEPTABILITY
LAND USE
COMPATIBILITY
EASE OF
IMPLEMENTATION
SYSTEM
EFFtCTIVRNESS
RELIABILITY
ADAPTABILITY
CALAMITY
RESISTANCE
PERMANENCE
ALTERNATIVE 4
Readily falls within funding
capabilities of responsible agency
Opposed by some local groups
Compatible with existing land use
plans
Will require minor reorganization
of agencies
Will meet performance criteria
Complex system with little
mechanical downtime
Will not adapt to neu processes
or performance criteria
Will cease function for more than
several days
System adequate for immediate
planning horizon
ALTERNATIVE 5
Readily falls within funding
capabilities of responsible agency
Opposed by some local groups
Compatible with existing land use
plans
Will require minor reorganization
of agencies
Will meet performance criteria
Simple system with little mechanical
downtime
Will adapt to some new processes
Will cease functions for a very
short period of time
System adequate for Immediate
planning horizon
ALTERNATIVE 6
Readily falls within funding
capabilities of responsible agency
Supported by some local groups
Compatible with existing land use
plans
Readily implementable by existing
agencies within current legislative
limits
Will meet performance criteria
Complex system unproven In full-
scale operation
Will adapt to some new processes
In event of calamity, will cease
function and require major repairs
System adequate for Immediate
planning horizon
I
r-1
O

I

-------
                                             TABLE VII-6B (Continued)


                                          ALTERNATIVES EVALUATION MATRIX
                                            Feasibility and Performance
PARAMETERS
FEASIBILITY
PERFORMANCE
FINANCIAL
FEASIBILITY
PUBLIC
ACCEPTABILITY
LAND USE
COMPATIBILITY
EASE OF
IMPLEMENTATION
SYSTEM
EFFECTIVENESS
RELIABILITY
ADAPTABILITY
CALAMITY
RESISTANCE
PF.R.MANENCE
ALTERNATIVE 1
Readily falls within funding
capabilities of responsible agency
Public ambivalent coward this
syscem
Compatible with existing land use
plans
Readily Implementable by existing
agencies within current legislative
limits
Will meet performance criteria
Simple system with little mechanical
downtime
Will adapt to aome new processes
Will remain fully functional and
require only minor repairs
Interim measure, usable for several
years only
ALTERNATIVE 2
Readily falls within funding
capabilities of responsible agency
Opposed by some local groups
Compatible with existing land use
plans
Readily Implementable by existing
agencies within current legislative
limits

Simple system unproven in full-scale
operat Ion
Will adapt to some new processes
Will remain fully functional and
require only minor repairs
Systen adequate for Imnedlate
planning horizon
ALTERNATIVE 3
Readily falls within funding
capabilities of responsible agency
Strongly opposed by local groups
Compatible with existing land use
plans
Readily Implementable by existing
agencies within current legislative
limits
Will meet performance criteria
Simple system with little mechanical
downtime
Will adapt to some new performance
criteria
Will cease function for more than
several days
System adequate for Immediate
planning horizon
I
h->
O

I

-------
     It should be noted at this time that the level of analysis is
at a general feasibility level.  Only representative transportation
distances and routes were used in this study.  In addition, dis-
posal site areas were only generally located.  However, the
evaluation procedures which follow can be taken to any level of
detail desired.   It is recommended that,  in the actual use of the
Methodology,  such a feasibility level of  analysis, as represented
by this case study, be done initially prior to detailed transpor-
tation routing and site evaluation.   Undesirable alternatives,  as
defined by the involved institutions and  public,  could then be
eliminated without undue time and money commitments.

Economic Analysis

     Included in Tables VII-7a through 7f and summary Table VII-7g
are the cost worksheets and figures used  for the six alternatives.
Figures VII-1, VII-2, and VII-3 show the  capital, operation and
maintenance,  and truck transportation costs, respectively, used
and extrapolated from the Methodology cost curves.  The following
assumptions were made in the preparation  of these costs:

      (1)   sludge processing  equipment  (thickeners, digesters,
           pressure  or  vacuum filters,  incinerators,  etc.)  were
           assumed  to have  a  service  life  of  20 years;

      (2)   the interest  rate  used was seven  percent;

      (3)   transportation modes  (trucks or barge)  would  not entail
           a  capital cost because either  existing  trucks would be
           utilized  or  future  truck and barge  capacity would be
           leased;

      (4)   landfills would  not  entail a capital expenditure because
           a  landfill will  be  required  and operated for  either
           solid  wastes  or  the  residuals  remaining from  solid waste
           processing and the  landfill  user  charge would include
           the user's share of  the amortized  capital  (the  local
           land  fee  by  1995 was assumed at $6/wet  ton);
     (5)  land costs were included as a necessary capital  expen-
          diture and ammortized over the 20-year  planning  period
          at seven  percent;

     (6)  assuming  that one-half of the total anaerobic digestion
          methane gas production per day to be excess suitable for
          reclamation revenue, it was estimated (using 0.4  cubic
          feet  (0.01 cu m) per capita, 600 BTU/ft  (5350 kg-cal./
          cu m) , and !?0 ,085/therm) that the contribution would be
                                  -106-

-------
                                                      TABLE VII-7a
                                            COST  ESTIMATE FOR ALTERNATIVE  1

                                                     SANITARY LANDFILL

                                                         (Base Case)
I
M
O

I
PROCESSING

No. Pltnc


3 Powell
4 Turkey Creek
5 K*rn»
6 Lyon Cr«ek
7 Forks- of -th*-Iiv*r
TRANSPORTATION


3 Powell
4 Turkey Cr.ek
3 Kerne
6 Lyoo Cr**k
7 Torki of ch« Klvor
ULTIMATE &ISPOSAL

All Plant* to Sanitary Landfill
TOTAL COSTS (Capital. Annual OtH, T


Processes

Digestion (Anaerobl-;)
Digestion (Aerobic)
Dig esc l^n (Aerobic)
Dewaler (Sar.d Bed»)
Digestion (Aerobic)
Dcuatfcr (Vacuum Filura)
Thickening (Cavity)
Digestion (Anaerobic)
Dewater (Sand &ed«)
fiigeatlon (Aerobic)
Cewacer (Sand fiede)

Trdiitportatloa

Truck 16.6
Truck 30.1
Truck 24.4
Truck 14.1
Truck 11.7

UeC Tcm*/I *y
72
o»l Aanu.l)




36.94
4.10
2.46
2.15
1.29
1.07
0.64
0.66
0.66
0.40
1.82
1.09

1995
Dry Term/Day
22 16
2.46
1.29
0.64
0.40
1.09

£/y«c Ton
6
94


S100C

2600
155
42
120
90
96
30
26
1J
100
28
76
80

Z
SolUi
40
40
40
20
40
40



.434,000


S1003

264.29
14.63
3.96
11.33
8.50
9.06
4.72
2.45
1.23
9.44
2.64
7.17
7.55

(/Dry Toa
6 00
5.70
6.90
9.60
5.10
4.50






$1000

39
29
7
16
20
13
14
4
4
1
4
It
11

*/0.y
132 96
14.02
11.35
6.14
2.04
4.91



$414.240


si ooo

303.29
43.63
10.96
27.33
28.50
22.06
IS. 72
6.45
5.23
10.44
25.17
18.55

Annual
S10CO
48 33
5.12
4.14
2.24
0.74
1.79
Totll
Annual
51000
157. 68
(940.700
                                         >ludg* production /or 197>-1995»

-------
                                                               TABLE VII-7b



                                                    COST ESTIMATE  FOR ALTERNATIVE 2

                                                              TRENCHING
o
oo
i
PROCESSING
No.
112
3
4
5
t
7
Plant
Knob Cr««k 'i Lovaa Craak
Powell
Turkiy Cr«ak
Karna
Lyon Cr«*k
Forka-of- tha-Rivar
Unit
Processes
Thlckenlne (Cravlt •}
Digestion (An«erob -c)
Deuatcr (Presbuie i'ilt«t«)
DiRCfrtlcn (Aerobic
Thickening (Cravlt 0
Dewater (Pressure .'ilc«r«)
Digestion (Aerobic
Dewater (SanJ Biidb
Digestion (Aerobic
Deuaier (Vacuu= l"l t«n)
Thlckenlnz (Grivll 0
Dewater (Sand Bed£^
Blgistlon (Aerobic!
Dewacer (Sand Beda^
1995
Dry Tona/Day
Processed
36.94
36.94
22.16
4.10
2.46
2.46
2.15
1.29
1.07
0.64
0.66
0.66
0.40
1.82
1.09
TTO.VSPORTATION

1 I 2
3
4
5
6
7
LTTIXA



AII ri






TOTAL

Knob Creek 1 Lynn Crt«k
Powell
Turkey Crctk
fUrnl
Ly&n Creek
Fork«-of-t>.e-Rlv«r
TE DISPC:AL



anil CO Trenching Sic*

Land Cose (700 acrea
t 5700/jcrt)
Sice Developcenc

Equlpaent
COSTS (Capital. Mnu«l OI.H.
Tranfiportacioa
Kode, Kllia
Truck 18.4
Truck 16.6
Truck 30.8
Truck !'.«
Truck 14.1
Truck 11.7

Wet Tone /Day !/>•'' t Ton

72 6.45






Total Annual)
1995
Dry Tons/Day
22.16
2.46
1.29
0.64
0.40
1.C9












Capital
$1000
uo
2800
720
155
42
120
90
96
50
26
13
100
28
76
80

Solid!
40
iu
40
20
40
40
Capital
S1000


490


1440
250

$6.676.000
Annual
Capital
51000
41.53
204.29
67.96
14.63
3.96
11.33
8.50
9.06
4.72
2.45
1.23
9.44
2.64
7.17
7.55

S/Dry Too
6.03
5.70
8.80
S.60
5.10
4.50
Annual
Capl Lai
sicoo


46 . 25


135.92
13.60



$1000
21
39
62
29
7
16
20
13
14
4
4
1
4
18
11

S/2ay
132. S6
14.02
11.35
6.14
2.04
4.91










$,94,070
Total
51000
63.53
303.29
129.96
43.63
10.96
27.33
2B.iO
22. C6
18.72
6.45
5.23
10.44
6.&H
25. 17
16.55
Total
51000
48.53
5.12
2.24
0.74
1.79
Total
Anr.ual

169.51

46.25


135. 92
23.60

$1.158.100
                               *l**«d upon *v*r»g« elude* pcaducciaft for 1975-1993.

-------
                                                           TABLE  VII-7c


                                                COST  ESTIMATE FOR ALTERNATIVE 3

                                                           INCINERATION
I
r—'
o

I
PROCISSIXC
NO.
112
3
4
5
6
7
Plant

Powell
Turkey Creek
Karns
Lyon Creek
Forks -of -the -River
Unit



Incineration
Deuater (Pressure Ftltura)
Dewater (Pressure Flltirt)
Thickening (Gravity)
Deuacer (Sar.d geds)
Digestion (Aerobic)
Dewater (Sand Be^s)
1995
Dry Tone/Day Capital
Processed $1000
36.94 440
36.94 1100
44.26 2SOO
4.10 190
2.15 110
1.07 62
0.66 13
0.66 100
0.40 28
1.82 76
1.09 80
Arr.uj 1
Capital
S1COO
41.53
103.83
273.73
17.93
10.38
5.85
1.23
9.44
2.64
7.17
7.55
Annual
04M
$1000
22
66
90
21
15
9
4
1
4
IS
11
TRAXS'OSTATIO:;

1 1 2
3
5
6
7
ULTIVATt

1-3
6 1 7
TOTAL COS

Knob Creek fc Loves Cra«k
(Ash to Landfill)
Crrek
Powell
Kama
Slui.'c to Ur.rtflll
Lyon Cr^.k
Forks -of -Che -Biver
DISPOSAL

Incinerator Ash
SluJ;e
TS (Capital, nr.r.uai jiM.
Koi. , Ml lea
Truck 18.4
Truck 19
Truck 26.6
Truck 26.6
Truck 14.1
Truck 11.7
Wet Tor.£./3iy S.'^l Ton
14.77 (,
3.73 6
Total Annual)
1995 t
Dry Tons/Day Solid.
11.08 Ath
4.10 40
2.15 40
1.07 40
0.40 40
1.09 40


55.099.000
$/Dry Ton
3.45
6.30
8.00
8.00
5.10
4.50



5/Day
38.23
25.83
17.20
8.56
2.04
4.91


$356.630
" Tc-.il
annual
51000

139,83
363.73
25.38
K.S5
5.23
6.64
25.17
13.55
Total
Annual
$1000
13.94
9.43
6.28
3.12
0.74
1.79
Total
Ar.r.ujl
S100C
32.35
8.17
$838.110
                                 *Baa*d upon average »ludg« production for 1975-15^5.

-------
                                                         TABLE VII-7d
o
i
                                              COST  ESTIMATE FOR ALTERNATIVE 4

                                              LAND  APPLICATION/SPRAY IRRIGATION
PROCESS I NC
No. Mant


4 Turkey Creek

6 Lyon Creek
7 Forki-ol-the-River
TRANSPORTATION

To Land AoMUatlon Site
142 Knob Creek 4 Lovea Creak
) fowell
4 Turkey Creek
S Kama
6 Lyon Creek
To landfill
7 Forka-of-the-Hlvar
UlTIM/.TE DISPOSAL




Unit
Proceasec


Dlge«tlon (Aerobic I
Digestion (Aerobic >
Thickening (Cravlt/)
Digestion (Anaerobic)
Digestion (Aerobic)
Dewater (Sand Sadat

Transportation
Mode Kllel
Truck 28.0
Truck 20.9
Truck 40.4
Truck 29.0
Truck 13. •

Truck 11.7


A.creag.
1000
Site Development - tncludea screening and
1995

Dry Tone/Day Capital
rroceteed $1000
36.94
36.94
4.10
2.13
1.07
0.66
0.66
1.82
1.09

1995
Dry ToneYDay
22.16
2.46
1.29
0.64
0.40

1.09


Cost
f 700/ecre
$68£0/aere
440
2800
155
90
50
13
100
76
80

Z
Sollua
3
4
4
4
)

40

Capital
tiooo
700
4SS6
A.nnua 1
Capital
$1000
41.53
14.6}
8.50
4.72
1.23
9.44
7.17
7.55

S/Dry Ton
80.00
44.00
75.00
56.50
46.00

4.50
Annua 1
Capital
$1000
66
430
OtM - Includee puaplng aanpowex.
Mterlala

Landfill
TOTAL COSTS (Capital. Annual 04X,

W«t Toi » '^ay
2.73
Total Annual)

$yuct Ton
6




$9.060.000

$/Day
16.38

Annual*
OiM
$1000
22
29
20
14
4
1
18
11

»/».y
1772.80
108.24
96.75
36.16
18.40


Annual
OU1
$1000


40


6
$941.000
Total
Annual
$1000
63.53
43.63
28.50
18.72
5.23
10.44
25.17
18.55
Total
$1000
647
40
35
13
7


Total
Anr.ua 1
$1000
66
430
40


6
J1.803. 060
                               *Iaa*4 upon average aludge production for 1975-199$.

-------
                             TABLE VII-7e
                 COST ESTIMATE  FOR ALTERNATIVE 3
                   LAND APPLICATION/COMPOSTING
PROCESS

Ho.
lit


)


4

>

6


7




141
1
4
)
6
7
IXC

Plant
Knob Creek t Love* Creak


Powll


Turkey Creek

Kerne

Lyon Creek


Forka-nf-th*~Rlvur

STATION



Unit
Praceeaa i
Thickening (Gravity)
Plge.tlon (Aiuer iblc)
Dawatcr (Preueur i Flltare)
Plgcatlon (Aerobic)
Thickening (Gravity)
Dcwater (Preaaurt Filter*)
Dlfiottlon (Aerobic)
Dewatcr (Sand Be le)
Dlgeatlon (Aerotlc)
Dcwater (Vacuua. filter*)
Thickening (Gravity)
Dtgaatlon (Aneerjblc)
Dewater (Sand 1*4*)
Oljeitlcm (Aerobic)
Deuater (Sand l«de)

Tranaportetlcm
Hod* Mllta
Knob Creek 4 Lovee Creak Truck 11.0
Pow«Il
Turkey Cre*k
Kama
Lyon Creek
Porka-of-cne-Rlv*r
Truck 20.9
Truck 40.4
Truck 19.0
Truck 11. 1
Truck 11.7
199)
Dry Tone/Day
Froceaaad
36.94
36.94
11.16
4.10
1.46
1.46
1.1J
1.29
1.07
0.64
0.46
0.66
0.40
1.12
1.09

199)
Dry Tone/Day
11.16
1.46
1.29
0.64
0.40
1.09

Capltel
11000
440
ieoo
720
1)>
41
110
90
96
SO
26
1)
100
it
76
ao

t
tolld*
40
40
40
10
40
40
Annual
Capital
91000
41.))
164,29
67.96
14.63
1.96
11.1)
.SO
.06
.71
.t)
.11
.44
.64
.17
'"


I/Pry Tu '
a.io
6.10
10.7)
11.11
5.00
4.50
Annual* Total
04X
11000
11
39
61
if
7
16
10
1)
It
4
4
1
4
IB
11


l/Oay
It). 91
16.46
1).6>
7.10
1.00
4.91
Annual
11000
63.))
103.19
119.96
43.6)
10.96
27.1)
21.50
22.06
18.71
t.t)
5.21
10.44
6.64
2). 17
18.))
Total
Annual
«1003
67
6
) .
3
1
- 2
U1.TTMJ.TE DISPOSAL







Uac
Acraag* Coat Toa*7Day I/Vac
1 - t







7
COPPO.^.
Land
Pad, Storage
Runoff Pond.
Coapoitare. Truck*.
Loader*. Sc4le»,
Control Uouae
Din
UadMll
Forka of the River
TOTAL COSTS (Capitol. Annual UM.

1000 l)00/*cr*







Total Annual)








1.7) «
1

Annual
Capital Capital
Ton* S1000

700
600

400




i. 534. 000
11000

46
41. M

17.76





Annual
out
11000






107

6
J61.000
Toral
Annual
11000

66
41.30

11.76

107

6
• l.LM.UC
•*aa*d upon av*ra(* *lwd|* production (or 1*71-1991.

-------
                                                                    TABLE VI1-7f

                                                       COST  ESTIMATE  FOR ALTERNATIVE 6
                                                              RESOURCE  RECOVERY
                                                                     (IRD)
N5
 I
PROCESSING
No.
1 & 2
3
4
5
6
7
Plant
Knob Creek 4 Loves Creek
Powell
Turkey
Karns
Lyon Creek
Forks -of -che -River
Unit
Processes
Thickening (Gravity)
Digestion (Anaerobic)
Digestion (Aerobic)
Digestion (Aerobic)
Digestion (Aerobic)
Thickening (Gravity)
Digestion (Anaerobic)
Digestion (Aerobic)
1995
Dry Tons/Day
Processed
36.94
36. 94
it. 10
2.15
1.07
0.66
0.66
1.82

Capital
S1000
440
2800
155
90
50
13
100
76
Annual
Capital
51000
41,53
264.29
14.63
8.50
4.72
1.23
9.44
7.17
Annual*
OiM
$1000
22
39
29
20
14
4
1
18
TRANSPORTATION

1 t 2
3
4
5
6
7
To Pickel Island
Knob Creek. I Lovee Creek
Powell
Turkey Creek
Karns
tyon Creek
Forks-of- the- River
Transportation
Mode Klles
Barge 16
Truck 15.8
Truck 23.1
Truck 21.1
Truck 14-7
Truck 1.0
1995
Dry Tons/Day

2.46
1.29
0.64
0.40
1.09
I
Solids
3
4
4
4
3
3.5
RESOURCE RECOVERY


TOTAL
Plant
IRD
COSTS (Capital. Aanual OiM,
Unit
Processes
Devater (Vacuum Fill ers)
Total Annua" x
1995
Dry Tons/Day
28.04

Capital
$1000
580
$4.304.000
S/Dry Ton

30.00
47.00
44.00
48.25
4.60
Annual
Capital
S1000
54.75

5/Day

73.80
60.63
28.16
19.30
5.01
Annual
0«.M
$1000
30
$564,500
Total
Annual
$1000
63.73
303.29
43.63
2H.50
18.72
5.23
10.44
25.17
Total
Annual
$1000
319. 50«*
27
22
10
7
2
Total
Annual
SI 000
84.75
$970.760
                          "Annual Capital - SRfl.lfW (nayahle to harpe owners)
                            Annual Oik - $239,000t
                          t $14-66 to-ing cost/trip mile x J2 miles x 32 mile. - $i29.12/trip x 365 crips/year - $229,628.80/ye.r
                            + $9660 (maintenance)  - 5239.000

-------
                                                   TABLE VII-7g


                                          CAPITAL. 0 & M, AND PRESENT WORTH

                                                FOR THE ALTERNATIVES

1.
2.
3.
4.
5.
6.
Alternative
Sanitary Landfill
Trenching
Incineration
Land Application:
Spray Irrigation
Land Application:
Composting
Resource Recovery:
IRD
Total Capital
$ 4,836,000
$ 6,876,000
$ 5,099,000
$ 9,060,000
$ 6,536,000
$ 4,304,000
Total Annual 0 & M
$ 471,000**
$ 483,000**
$ 357,000
$ 935,000**
$ 548,000**
$ 552,000**
Present Worth*
$ 9,828,000
$ 11,994,000
$ 8,879,000
$ 18,965,000
$ 12,342,000
$ 10,147,000
I
H-
M
LO
       *  Amortized Capital at 7 percent for 20 years (factor = 0.09439).

       ** Includes $13,000/year debited against annual 0 & M for reclaimed resource of methane off-gas

-------
            CAPITAL  COSTS TOR SOLIDS PROCESSING FACILITIES
UJ
Q-
o
o
o
CO
OO
UJ
l_>
o
ct:
o_

i/o
o
o
oo

a:
a
    1000
LEGEND
Gravity Thickening
Vacuum Filtration
Aerobic Digestion
Anaerobic Digestion
Pressure Filtration
Incineration
Sand  Bed Dewatering
                                                                                           CD
                     .01           0.1            1
                    CONSTRUCTION COSTS,  MILLIONS OF  DOLLARS

-------
           OPERATING  COSTS  FOR SOLIDS PROCESSING FACILITIES
    1000
     100
 Q

 o:
 LLj
 Q.
o
o
o
      10  :
LU
O
a:
a.
o
on

a:
a
     0.1
        0.1
                                     LEGEND
                                GT - Gravity Thickening
                                VF - Vacuum Filtration
                               Dae - Aerobic Digestion
                               Dan - Anaerobic Digestion
                                PF - Pressure Filtration
                                 I - Incineration
                                SB - Sand Bed Dewatering
                                                         J	L
                                                                          i i i i l
 1             10            100           1000

OPERATING COSTS,  THOUSAND DOLLARS PER YEAR
10,000
                                                                                          £75
                                                                                          I
                                                                                          ro

-------
                                                   FIGURE VII-3
O

cc.
UJ
D-
O
CJ
               TRUCK TRANSPORTATION COSTS
                           (1975)
                  DISTANCE TO DISPOSAL POINT, MILES
                               -116-

-------
          lor  both  Knob  Creek/Loves Creek  and  Lyon  Creek  approxi-
          mately  $13,000 per year, of which  95 percent  ($12,350 per
          year) is  attributed  to Knob Creek/Loves Creek and  five
          percent  ($650  per year)  is attributed to  Lyon Creek;

     (7)   no other  reclamation resource  revenues were developed due
          to lack  of  specific  cost data  in the Study Area (i.e.,  the
          revenue  numbers  presented in the Methodology  were  felt  to
          be unrepresentative  of the Study Area);

     (8)   other  transportation modes such  as rail or pipeline were
          not  investigated due to  the  substantial amount  of  rail-
          car  switching  necessary  in the Study Area and the  rela-
          tively  short distances  involved  from the  plants to the
          ultimate disposal areas;

     (9)   the  annual  0 & M costs were  based  on the  average sludge
          quantities  handled  over  the  20-year planning  period; and

    (10)   the  cost curves  in the  Methodology were  utilized due to
          lack of  local  data and  extrapolated when  necessary,
          recognizing however  the  possible degree  of error intro-
          duced  by such  a  technique.

     Table VIl-7g shows, for each of  the six alternatives, the total
capital cost,  the total  annual operation and maintenance costs
(0 & M),  and  the  calculated present worth.

     Where local  costs were unavailable  (e.g., site development or
composting and trenching costs),  the -following references cited in
the Methodology  were  utilized:

     (1)   for  trenching-site development and equipment  costs,
          Ref. VII-1;

     (2)   for  land application/spray  irrigation site development
          and  operating  costs, Ref.  VII-2; and

     (3)   for  land application/composting site development,  equip-
          ment,  and operating costs,  Ref.  VII-3.

     Table VII-8 shows for each alternative the costs  by alternative
and by each plant without  Federal funding and with  75  percent
Federal funding.   Thus,  the lower case numbers would reflect  the
cost per  ton borne by State and local  funding.
                                   -117-

-------
                                                    TABLE VII-8

                      CQSTS  (DOLLARS)  PER TON OF DRY SLUDGE  SOLIDS  PROCESSED.  TRANSPORTED.  AND
                          DISPOSED OR  RECLAIMED WITHOUT FEDERAL  FUNDING  AND  WITH  FEDERAL
                                         FUNDING -  1995 SLUDGE PROJECTION
oo
I
         Sewage  Treatment
             Plant
        Forks-of-the-River
        Alternative Cost
        1 Cost  ($/ton of dry solids) without Federal Funding.
        2 Cost  ($/ton of dry solids) 75 percent Federal funding of capital costs.

-------
 Environmental Factors

     The summary listing of potential environmental impacts presen-
 ted  in Table VII-9 shows the categories of concern investigated for
 each alternative.  The following discussion^ nresent the rationale
 for  the evaluations found in Table VII-6.

     Alternative 1 - Sanitary Landfill

     No unacceptable changes in any water quality are expected  from
 this alternative because of strict state guidelines and regulations
 for  the location, design, and operation of the  sanitary landfill,
 precluding degradation of surface and ground waters.  Whether non-
 degradation of water quality occurs in fact is  the responsibility
 of the operating agency and the concerned state regulatory agencies.

     A very minor increase in pollutant emissions could be expected
 from the operation of the trucks transporting the sludge (on the
 average, 3-4 truck trips/day would be required).  Disposal of the
 sludge would be expected to contribute additional odors at the  land-
 fill site prior to the daily covering operations.

     Although abandoned sanitary landfill sites often are used  to
 provide new recreational facilities (e.g., parks, baseball diamonds,
 etc.), this is done not so much out of choice as by limitation.
 Methane gas generation, subsidence, corrosive leachate, and un-
 developed soil profiles severely limit the possible uses of such a
 site for many years after landfilling ceases.

     Sanitary landfills by their very nature damage the existing
 aesthetic value of an area and disrupt the existing ecologic sys-
 tems.  However, the sanitary landfill (and the  open dump which
 preceded it) has been in existence in the Study Area for many
 years and  most likely will continue to exist in the future.
 As a result, no changes are expected in community impact, public
 health involvement or resources consumed because of the implemen-
 tation of this alternative.

     Alternative 2 - Trenching

     No unacceptable changes in any water quality are expected  from
 this alternative for much the same reason as given in Alternative  1.
 A trenching operation would undoubtedly come under strict supervision
and regulation by the state environmental and public health agencies
and would necessarily be located in the best natural location with
water quality protection devices provided if necessary.
                                  -119-

-------
                            TABLE VII-9
           POTENTIAL SIGNIFICANT ENVIRONMENTAL IMPACTS  OF
                ALTERNATIVE SLUDGE MANAGEMENT  PLANS
Alternative
1. Sanitary
   Landfill
      Process

•Truck transport of
 digested, dewatered
 sludge to landfill

•Disposal  of sludge at
 sanitary landfill site
2. Trenching
•Truck transport of
 digested, dewatered
 sludge to trenching
 site

•Disposal of sludge
 at trenching site
3. Incineration "Truck transport of
                 dewatered sludge to
                 Knob Creek STP
                •Truck transport of
                 digested, dewatered
                 sludge (Lyon Creek &
                 Forks-of-the-River
                 STP's) to sanitary
                 landfill site

                • Incineration
Potential Significant
Environmental Impact

•Air pollutant emissions
•Noise
•Traffic

•Destruction of wildlife
 habitat
•Groundwater degradation
•Damage to aesthetics
'Development of new
 recreation lands
'Odors
'Public health hazard
•incompatibility with
 other land uses

*Same as Alternative 1
                                             Same as Alternative 1
                            "Air pollutant emissions
                            •Noise
                            •Traffic
                            •Vector propagation

                            •Same as Alternative 1
                            *Air pollutant emissions
                            •Public health hazard
                            •Damage to aesthetics
                            •Construction dust
                            •Construction noise
                                  -120-

-------
                        TABLE VII-9 (Continued)
            POTENTIAL SIGNIFICANT ENVIRONMENTAL IMPACTS  OF
                 ALTERNATIVE SLUDGE MANAGEMENT  PLANS
Alternative
      Process
3.  Incineration •Truck transport  of
                 incinerator ash  to
                 sanitary landfill site
4. Land
   Application:
   Spray
   Irrigation
Potential Significant
Environmental Impact

•Air Pollutant emissions
•Noise
•Traffic
•Dust
                <»Disposal of  sludge          »Same  as  Alternative  1
                 at sanitary  landfill  site
                •Disposal of incinerator
                 ash at sanitary  landfill
                 site
*Truck transport of
 digested sludge
 to land application
 site

•Truck transport of
 digested, dewatered
 sludge (Forks-of-the-
 River STP) to sanitary
 landfill site

•Spray irrigation of
 digested sludge at
 land application site
•Destruction of wildlife
 habitat
•Groundwater degradation
•Damage to aesthetics
•Dust
'Development of new
 recreation land
'Incompatibility with
 other land uses

*Air pollutant emissions
*Noise
'Traffic
                                            'Same  as  Alternative  1
                                             Odors
                                            •Construction dust
                                             Construction noise
                                             Destruction of  natural
                                             vegetation
                                            'Destruction of  wildlife
                                             habitat
                                             Damage to aesthetics
                                             Vector propagation
                                            •Displacement of local
                                             residents
                                   -121-

-------
                        TABLE VII-9  (Continued)

            POTENTIAL SIGNIFICANT ENVIRONMENTAL IMPACTS OF
                 ALTERNATIVE SLUDGE MANAGEMENT PLANS
Alternative
      Process
4.  Land
   Application:
   Spray
   Irrigation
5. Land
   Application:
   Composting
•Disposal of sludge
 at sanitary landfill
 site

'Truck transport of
 digested, dewatered
 sludge to land applica-
 tion site or sanitary
 landfill (Forks-of-the-
 River STP)

•Disposal of sludge at
 sanitary landfill site

•Composting at land
 application site
                *Land application of
                 compost and/or digested,
                 dewatered sludge
Potential Significant
Environmental Impact

•Groundwater degradation
• Surface water pollution
• Incompatibility with
 other land uses
• Enhance soil producti-
 vity
•Toxic elements to food
 chain

•Same as Alternative 1
•Same as Alternative 1
                                             'Same as Alternative 1
•Odors
•Dust
•Noise
•Vector propagation
•Groundwater degradation
•incompatibility with
 other land uses
•Surface water pollution
•Damage to aesthetics
"Construction noise
•Construction dust

•Odors
*Dust
*Noise
•Vector propagation
•Groundwater degradation
 Incompatibility with
 other land uses	
                                   -122-

-------
                     TABLE  VII-9  (Continued)

         POTENTIAL SIGKIFICANT  ENVIRONMENTAL  IMPACTS OF
              ALTERNATIVE SLUDGE  MANAGEMENT PLANS
 Iternative
                      Process
5.  Land Application:
   Composting
6. Resource
   Recovery:
   IRD
•Tn.-ck transport of
 digested sludge
 to IRD facility

•Barge transport of
 digested sludge to IRD
 facility
                «Use of product
Potential Significant
Environmental Impact

•Displacement of local
 residents
•Surface water pollution
•Destruction of natural
 vegetation
•Destruction of wildlife
 habitat
"Damage to aesthetics
•Enhance soil producti-
 vity
•Toxic element to food
 chain

•Same as Alternative 4
•Surface water pollution
•Vector propagation
*Air pollutant emissions
°Traffic              _ .
0Damage to  aesthetics

•Enhance soil prodycti-
 vity
*Groundwater degradation
•Toxic elements  to  food
  chain
      Air quality considerations are the same as those for Alter-
 native 1.  In addition, noise and dust would be generated during
 the operation of the trenching system.

      Assuming the location of the trenching site would be on land
 of only marginal productivity, a slight increase in soil pro-
 ductivity would be realized after the incorporation of sludge.
                                   -123-

-------
This benefit, however, would only be realized if cropping of the
trenching site were the subsequent land use.  As a result, this is
a conditional benefit.  In addition, trenching could be viewed as
development limiting in that residential and industrial development
would probably not be allowed on the site until the buried sludge
degraded anaerobically to an inert hunus, a slow process requiring
many years to occur.
     Considerable disruption of existing ecosystems and damage to
aesthetics would occur during the operation of the trenching
facility.  In addition, it is likely that sorce local residents
would be displaced by the acquisition of site and buffer lands,
owing to the large acreage and type of land (i.e., cleared) re-
quired .

     Depending on one's point of view, resource conservation might
or might not be occurring in this alternative.  If one assumes
that the land utilized would have been upgraded in productivity
with or without trenching (viz. fertilizer or compost), then
resources would be conserved.  However, the decline in the
agricultural economy of Knox County (at least in terms of acreage
and number of farms) and increase in population and residential
land use requirements seem to indicate that the development-
potential loss would be greater than the potential agricultural
benefits that would occur.

     Alternative  3 -  Incineration

     No  unacceptable  changes  in water  quality,  land quality,  public
health,  ecology  or  aesthetics  are  expected  to  occur with  the  incinera-
tion of  the  dewatcred sludges  or  disposal  of  the  incinerator  ash to  a
sanitary landfill.  Air  quality would  be  somewhat  impacted  by truck
emissions,  incinerator  stack  emissions,  and  incinerator dust  leak-
age during  transit  and  disposal.

     The possible air  quality  impacts  from  the  operation  of  the
regional incinerator  at  Knob  Creek  were  investigated  by utilizing
in-house air quality  models.   Air  quality  data,  specifically  wind
rose data  from  sources  noted  in Chapter  IV  of  this  report  and the
following  typical incinerator  stack parameters  were used:  stack
height  of  75 feet (22.86  meters),  stack  diameter  of 4 feet  (1.22
meters), exit  gas temperature  of  350  F (177C),  and  exit gas  velocity
of  30  feet  per  second (9.14  meters  per second).

     The average  annual  particulate concentrations within  approxi-
mately  a two-mile (1.61  kilometer)  radius  of  the  incineiator  were
never above  0.03  yg/m  and  the distribution was  in a  northeasterly
and southwesterly direction.
                                 -124-

-------
     The maximum 24-hour concentration would  occur  under an A
stability classification with  the wind from the  north  and would
result in a concentration of 0.33 ug/m ;  an insignificant addition
to  the existing levels  (see Appendix A).

     Thus   the operation of a  regional sludge incinerator located
at  Knob Creek utilizing proper emission  control  devices  to meet
Federal  State, and  locnl regulations  is  anticipated  to  create no
significant impact to the existing  levels of  particulates within
the Study Area.
     Al t e rnativ^JLjiJiand_j^lication: Spray  Irrigation

     Vith the incorporation of the surface and underground collection
and storage svstems required for a liquid sludge spray irrigation
svstera and the expected nutrient uptake by crops, no unacceptable
chances in any water quality are anticipated by  the implementation
of  this alternative.  As in Alternative 2, considerable State par-
ticipation in the design, operation, and nonatoring of the system
by  environmental protection and public health  agenc.es would be
expected to guarantee proper system performance.

                        =,ir nnllutant emissions and traffic from
     Minor increases in air  ^^averaging  40  truck trips/day)
truck transportation of the sludge       *          lan
and some increase in odors woul        -
an  some                                          ^
tion site.  ThV°SSrieatIonwou?d be .incized by proper
aerosols from the spray irrigation wouia             d
operational considerations and surrounding buffer l..nd.

                                ,™,1H hp located en already existing
     The land application site wou Jd Je ^"  ible with existing
or potential farmland and would not be ^^^   j      required
land uses, aesthetics  or ecosystems   hou-e.er, tne   g
area
      and surface runoff control.
                                       .
and would reduce the n« d for ot ,er fe^  ^^^^ ^ t(j tbe net
crop production.  Tlierc is ^o --4                 restrictions on
benefit to nsrlcMlt,,ral production because o  ^ J^     Uc health
th. types of crops to be             / ^. ^L of'slud.e at
                                 -125-

-------
figure)  and the exclusion of Forks-of-the-River sludge assumed ior
this alternative are based largely or solely on this consideration.
However, sludge, soil, and crop monitoring for toxic element con-
centrations would be required to verify this application rate
locally.

     Alternative 5 - Land Application: Composting

     No unacceptable water quality changes are expected with the
implementation of this alternative.  As with Alternatives 2 and 4,
State regulation and monitoring could be expected to be rigorous.
Some runoff, collection, and storage facilities might be necessary,
particularly around the composting pad, although subsurface drainage
collection (at the land application site) should not be required, owing
to the low water content of the dewatered sludge and/or compost.

     Minor increases in air pollutant emissions from trucks trans-
porting the sludge to the composting facility would be expected to
occur.  The composting operation and the land application of the
sludge/compost (viz. disking) would be expected to generate some
dust, although the former would be mitigated by utilizing a con-
crete compost pad.  The rural location and the use of buffer areas
would tend to minimize the impact of dust generated during disking.

     The construction and operation of the composting facility
could be expected to disrupt existing ecosystems and degrade the
aesthetics (viz. noise, odors, etc.) of the area local to it.
These aesthetic impacts could be alleviated by the use of buffer
lands.  The land application site and operation would be compatible
with existing land uses and praciices.  However, the displacement
of some local residents would be required to obtain the necessary
land.

     The use of the sludge and/or compost on the land would in-
crease the soil productivity and represents a beneficial use of
the sludge.  It is anticipated that fewer restrictions would be
placed on the types of crops grown making this alternative a
greater potential contribution to the local agricultural economy.
Considerations of long-term sludge/compost application to the
soil, particularly in regards to heavy metal build-up and soil
toxicity, are the same as those discussed in Alternative 4.

     Alternative 6 - Resource Recovery: IRD

     No unacceptable changes in water quality, land quality, ecology,
aesthetics, public health involvement, or community impact are expected to
                                -126-

-------
occur with the implementation of this alternative.   Some minor in-
creases in pollutant emissions could be expected from barge and
truck transportation operations.  Because it would  be used to
product a high-nitrogen fertilizer,  the sludge would become a.
resource.

Feasibility of Alternatives

     The feasibility of implementing the alternative sludge manage-
ment plans was evaluated in this section by preliminary analyses of
four parameters:  (1) financial feasibility; (2) public acceptability;
(3) land use compatibility; and (4)  ease of implementation.  The
procedures and rationale used in these analyses are particular
both to  the general feasibility level of the Study and  the nature
of  the Knoxville-Knox County Study Area and should be viewed as an
example  only.  It would be the  responsibility of the individual
planning agency using the Methodology to identify the evaluating
criteria  (e.g., bonding capability, public  opinion surveys,  etc.)
and detail most relevant to discerning the  feasibility  of  alter-
natives .

     For the financial feasibility analysis, it was assumed  that
the City of Knoxville (viz. Knob Creek SIT) could readily  finance
on  an individual basis or as a  regional administrator,  any of  the
alternatives considered.  As noted earlier, the PSD (City  of Knox-
ville) has the capability to issue A-rated  bonds of any  type and
adjust user charges, is currently on a pay-as-you-go basis,  and is
high on  the state priority list for Federal funding.  The  utility
districts are not nearly as capable financially and are  already
charging high user's fees.  As  a result, alternative sludge manage-
ment costs considerably higher  than those  currently incurred would
be  undesirable although not necessarily infeasible.  A  percent
increase in sewer charges was estimated for the utility  districts
for comoarative purposes based  on the assumptions that:  (1)  30
percent  of the total annual cost (i.e., O&M and amortized  capital
costs) of the sewer system is attributable  to solids handling and
disposal; and (2) Alternative 1 (sanitary  landfilling)  represents
the base case to which all alternative costs are referenced.  The
costs per dry ton of solids (without Federal funding) presented
in Table VII-8 were used as a basis for this analysis..

     Public acceptability was gauged by project and MFC  staff
familiar with the feelings of local interest groups in  the Study
Area.  This method is acceptable only at the preliminary feasibi-
lity stage.  Subsequent evaluations and investigations  should
include  public participation via public meetings, mass-media
presentations, and/or public opinion surveys.

     Land use compatibility with future land use plans was a
siting criterion for all the alternatives  considered.   As  a
                                  -127-

-------
result, all the alternatives are compatible with existing land use
plans.

     Alternative 1 - Sanitary Landfill

     This alternative,  as noted above, is the base case anJ »I11
occur barring the implementation of another sludge management plan
developed in this or subsequent studies.   As a result, it is
assumed to be both financially feasible and easily implementable in
that no changes in the  institutional relationships or responsibili-
ties from those currently existing are recommended.

     Landfilling  of  sewage  sludge  shares  common public  acceptabi-
 lity problems with  landfilling of  municipal  refuse.   The majority
 of  the public  is  ambivalent toward landfilling, but  residents  in
 the immediate  vicinity  of a disposal  site usually  voice strong
 objections  to  the facility.

     Alternative  2  - Trenching

     Trenching  is estimated to be  somewhat more expensive  than
 sanitary  landfilling.   Increases  in utility  district costs  would
 range  from  one  to five  percent above  those estimated for Alter-
 native 1.

     Some  local opposition  to this alternative  would be expected
 from those  residents who either would be  displaced or adjacent to
 the facility.   In addition,  some  local real  estate developers
 might  view  this as  an undesirable  use of  potentially developable
 land.   Local  environmental  groups  could  be expected to be  ambiva-
 lent depending on the balance between aesthetic and resource con-
 servation values  extant.

     This  alternative would be readily implementable because no
 changes in  institutional relationships or powers  are recommended
 for this  alternative.   There would be an increase in the functions
 and responsibilities of Knoxville, but this  would not be expected
 to  hinder  implementation to any great extent.

     Alternative  3__- Incineration

      Incineration,  based on the cost  assumptions  and procedures
 used in this  study,  would be overall, the lowest  cost alternative.
 Cost reductions of  four to  five percent  from Alternative 1 were
 estimated for those utility districts participating in regional
 incineration.   Lyon Creek and Forks-of-the-River  STP's would incur
 no  cost change as they  would continue to use sanitary landfilling.

      Some strong local  opposition to  the incinerator would be
 expected from residents in  the vicinity  of the  Knob Creek plant.
                                    -128-

-------
The general public and local environmental groups would be ex-
pected to be ambivalent, at best,  towards incineration.

     No implementation problems are foreseen with this alternative.
There would be no institutional changes required and no significant
additional responsibilities or functions assumed by the City of
Knoxville in operating a regional incinerator.

      Alternative  4 -  Land  Application:  Spray  Irrigation

      Spray  irrigation of sludge is  the  most expensive  of  the  alter-
natives  considered.   Utility  district  costs increase  six  to 13 per-
cent  over  those  for Alternative 1.

      The acquisition  of  the land  and the  construction and operation
of the facility  are expected  to generate  opposition from  the
residents  to  be  displaced  and those that  would  be  living  adjacent
to the facility.   The general public would  probably have  an ambiva-
lent  attitude to the  facility owing to its  rural location.  Local
environmental groups  would probably support this alternative  more
readily  than  any of the preceding alternatives.

      Some  minor  reorganizational  changes, particularly within the
Knox County government,  would be  expected with  the implementation
of this  alternative.   Because Knox County would be involved in the
ownership  and, consequently,  in the operation (primarily  advisory),
an agency  would  need  to be established to administer  its respon-
sibilities and advise the  operation of the  facility.  The City of
Knoxville  would  acquire significant new functions and responsibili-
 ties requiring administrative and technical staff recruitment.

      Alternative 5 -  Land  Application; Composting

      This  alternative is comparable in cost to Alternative 2
 (Trenching).   Increases in utility district costs would be an
 estimated two to six percent  over those of  Alternative 1.

      Some local opposition to this alternative would be expected
 from residents in the vicinity of the  land application site.   The
 general public attitude would probably range from ambivalent  to
 moderately supportive owing  to its rural location  and the availa-
 bility of a cheap compost product.  Local environmental  groups
 would probably support this  alternative more readily  than spray
 irrigation.

      The ease of implementation would  be equivalent  to that  of
 Alternative 4.
                                    -129-

-------
      Alternative  6  -  Resource  Recovery:  IRD

      The  transport  of  digested sludge  to  the  IRD  sludge  processing
 facility, based on  the assumptions made  in this study, is one of
 the  less  expensive  alternatives.  Cost reductions would  be expected
 for  all the utility districts  ranging  from an estimated  one to
 seven percent.  Forks-of-the-River STP would have an estimated
 cost savings of 12  percent owing primarily to its proximate
 location  to the proposed IRD facility.

      The  general  public and most special  interest groups would
 probably  support  this  alternative owing  to its minor community and
 environmental  impacts.

      Because no changes in institutional  relationships or respon-
 sibilities would  be necessary, no implementation problems are
 anticipated for this alternative.

 P^erf o nuance

     Performance  capabilities  of the alternatives have been.evaluated
 utilizing five basic parameters, namely:  1) system effectiveness;
 2) reliability; 3) adaptability; A) calamity resistance; and 5) per-
 manence.

     As noted earlier  in this report, many of the sludge processing
 systems used in the alternatives were based upon either  existing or
 proposed systems  if they would meet the required final sludge charac-
 teristics needed  prior to transport and ultimate disposal.  This was
 done to provide a degree of commonality with the 201 facilities planning
 effort.  Other sludge processing systems provided in the Methodology
 and not proposed  for use in the 201 facilities plans were evaluated
 for  their possible substitution if they would clearly provide a greater
 degree of performance capabilities.  At the level of detail provided
 on a local basis,  no substitutions of systems were identified at this
 time.  Potential operational difficulties of the sludge processing
 systems used in the development of the six sludge management plans
which may adversely affect their performance capabilities are discussed
 in the evaluation below.

     Where,  in addition to the sludge processing systems, the trans-
port and ultimate disposal systens could also be adversely affected
 in maintaining their performance capabilities, these are also noted
and discussed below.  Means of system nonitoring and control are pointed
out such that the  potential for system upset or malfunction could be
mitigated.
                                  -130-

-------
     Alternative 1 - Sanitary Landfills

     As noted earlier, regulatory and public health agencies would
 establish requisite performance criteria such that proper control
 and monitoring of a sanitary landfill operation would occur.  It is
 expected that the overall system effectiveness of this alternative
 would be such that performance criteria would be met.

     The systems  employed in this  alternative  are  relatively simple
and their reliability  good (see Table VII-6  of  the Methodology).
Little mechanical downtime is anticipated  and  transportation sub-
systems are expected to present no operational  problems  based upon  the
existing local history of landfill operation.

     Without proper industrial pretreatment  controls,  the anaerobic
digestion process can be adversely affected; thus,  as  pointed out
earlier, the City must exercise care in what it will  allow dis-
charged to its sewers.  Sand bed  dewatering, because  of  large land
requirements (see Table VII-6 of  the Methodology),  may necessitate
incorporation of covers to allow proper operation during rainy
seasons of the year, although local rainfall records  (see Chapter
IV of this  report)  do  not indicate substantial  problems  in this
regard.

     The overall ability of the system to maintain operational
 integrity and, hence, to be relatively calamity resistant, ranges
 from good to very good (see Table VII-6 of  the Methodology).

     As noted in Chapter V of this report,  the permanence of this
alternative in the Study Area is questionable and thus may be some
degree be expected to serve only as an interim measure usable only
as long as solid waste in the area is also  disposed in sanitary
 landfills.

     Alternative 2 - Trenching

     System effectiveness,  adaptability, and calamity resistance of
 this alternative would be similar  in  nature to  sanitary  landfills
 as discussed  above.

     The trenching  system,  although  simple  in  concept,  is unproven
 in full-scale operation  and would, during the  initial stages of
 operation, be somewhat of an  experimental procedure.   Its relia-
 bility  would  therefore be constrained until local acceptance and
 any  operational  problems were addressed  and solved.   Once these
 difficulties  were  overcome,  the  overall  system should be adequate
 for  the planning horizon of twenty years.
                                   -131-

-------
     Alternative 3 - Incineration

     As noted earlier under Environmental Factors, adherence to
emission standards for the incinerator is not expected to create
difficulties in meeting applicable air quality standards.  Other
sub-systems within this alternative are also expected to meet per-
formance criteria.

     Reliability of the system is expected to range from good to
very good  (see Table VII-6 of the Methodology).  The incinerator
sub-system could also meet new performance criteria by incorporating
a higher degree of emission control, albeit at higher costs to the
users.

     Due to potential explosion hazards and a fair rating for ease
of operation and maintenance (see Table VII-6 of the Methodology),
the ability of the incinerator to withstand a calamity (i.e. an
internal explosion) was such that this sub-system would, under
such circumstances, cease functioning for more than several days.
Thus, on-site storage of the raw dewatered sludge feed would be
required.

     The overall system is expected to be adequate for the twenty
year planning horizon.

     Alternative U - Land Application:  Spray Irrigation

     The overall system effectiveness of this alternative is
expected to be such that all performance criteria can be met.  The
low application rates utilized during the growing season and the
exclusion of Forks-of-the-River sludge is anticipated to provide a
degree of control over  long-term heavy metal build-up in the soils
and crops at the land application site.  City control and monitoring
of heavy metals discharges to its sewers is also expected to pro-
vide a measure of protection in this regard.  The low application
rates and leachate collection, monitoring, and possible treatment
is expected to provide  protection against groundwater contamination
from nitrates.

     The alternative, although complex as a total system, has a low
reliance upon those mechanical systems which could create downtime
problems.

     If new performance criteria are established during the twenty-
year operation period,  the overall system has no reliable and
relatively inexpensive  means of adapting.   No further sludge pro-
cessing procedures beyond digestion have been incorporated and
their inclusion either  at the plants or at the application site
may be either economically disruptive or infeasible due to process
or land constraints.
                                  -132-

-------
     Calamity resistance,  particularly  at  the  land  application
site, is such that if during unanticipated severe weather  the
site were to become flooded, the system would  cease functioning
for more than several days.   Although the  site storage  lagoon  is
provided for just such a potential difficulty, the  impact  of
adverse weather during the application periods could be severe.
Barring the unlikely event of such weather, the alternative  is
deemed to adequate for the twenty-year planning horizon.

     Alternative 5 - Land Application:  Composting

     This alternative was included for evaluation primarily  to
overcome the difficulties noted for the land application (spray
irrigation) system above, namely, a complex system unable to
adapt to new processes and potentially constrained during calamity
events.

     As noted for the spray irrigation system, the composting/
land application system effectiveness is expected  to meet perfor-
mance criteria.  There would also be less likelihood of ground-
water contamination due to  the application of a dewatered, rather
than liquid, sludge.

     Although the composting operation sub-system  has  some reliance
upon mechanical  components, their complexity  is not great and
provision has been made for backup equipment.  Therefore, the
reliability  of  this  system  is  expected to be  good  and  certainly
better  than  spray  irrigation.

      Because provisions  in  this  alternative have been  made for de-
watering at  the  various  plants,  some adaptability, such as enclos-
 ing sand beds  or modifications in pressure filter  chemical feed
 systems, could  be accomplished if future  operational conditions  so
 dictated.   In  addition,  if  the local market  for  a  composted product
 were sufficient, a degree of  operational  adaptability  in  terms of
 the amount to  dispose to the  land application site could  be accom-
 plished.  The  composting operation would  also allow a  greater degree
 of freedom for storage and processing during inclement weather
 conditions,  thus making the overall system more resistant to
 calamity.

      This  alternative is expected to be adequate for the twenty-
 year planning horizon.

      Alternative 6 - Resource Recovery.  IRD

     Because the operation and marketing of a fertilizer product  is
 expected to come under close scrutiny by regulatory and public
 health agencies and allowed only if proper percautions are taken,
 the overall system is expected to meet performance criteria.
                                   -133-

-------
     The reliability of tlie system,  particularly during the fer-
tilizer production phase,  is anitcipated to be a complex system
which, as noted in the Methodology,  is unproven on a scale com-
parable to that proposed in this alternative.   Also, as noted
earlier in this chapter, the operation of this phase of the overall
system is in private, not  public,  control which could impact upon
the reliability of the overall system, particularly if the private
operation were to abandon  the project.

     The sub-system of fertilizer  production may, as time pro-
gresses, provide a measure of adaptability in that better processes
could be employed to handle variations in the quality of sludge
input and to produce a product with  wider market and sale potential.
Here again,  the adaptability feature is centered in private and not
public control, which may  present  problems of passing along these
new process costs to the public sector or passing along the savings
incurred in the operation  due to a better sales picture.

     This alternative has  a higher potential for operational prob-
lems due to calamity.  Daily barge traffic from Knob Creek to
Pickel Island could be seriously disrupted during flooding, barge
spills during loading, transport or  unloading, or barge wrecks
while passing under rail and road  bridges.  Digested sludge delivery
via road to Pickel Island  could be impaired and the overall opera-
tion of this alternative crippled  if the road and rail bridge to
Pickel Island were rendered impassable due to flooding and failure
of tbe bridge supports, thus necessitating major repairs.  The
likelihood of such a calamity as bridge failure due to flooding
would however be quite small because of the upstream TVA dams on
the French Broad River.  However,  the potential barging difficul-
ties noted for Knob Creek, although  remote, would create the
necessity of providing an alternate  backup transport mode such as
tank trucking.

     The overall system is expected, with proper safeguards as noted
in this chapter, to be adequate for  the twenty-year planning horizon.
                                  -134-

-------
                            CHAPTER  VII
                            REFERENCES
VII-1      "Trench  Incorporation of Sewage  Sludge," Walker, J.M.
           in Municipal Sludge Management,  Proceedings of  the
           National Conference on Municipal Sludge Management,
           Information Transfer, Inc., Washington, D.C.  (June 1974).

VII-2      "The Economics of Sludge Irrigation," Troemper, A.P.,
           in Municipal Sludge Management, Proceedings of  the
           National Conference on Municipal Sludge Management,
           Information Transfer, Inc., Washington, D.C.  (June 1974).

VII-3      "Composting Sewage Sludge," Epstein, E. and Wilson, G.B.,
           in Municipal Sludge Management, Proceedings of the
          National Conference on Municipal Sludge Management,
           Information Transfer, Inc., Washington, D.C.,  (June 1974).
                                 -135-

-------
                  APPENDIX A




NATIONAL AND STATE/COUNTY AIR QUALITY STANDARDS



 AND AIR QUALITY DATA FOR KNCKVILLE,  TENNESSEE

-------
                           APPENDIX A
         NATIONAL AM) STATE/COUNTY AIR QUALITY STANDARDS

          AND AIR QUALITY DATA FOR KNOXVILLE. TENNESSEE
NATIONAL
            NATIONAL AMBIENT AIR QUALITY STANDARDS**
                                     Primary
                                    Standard
          Secondary
          Standard
                                  ug/nf
ppm
ug/nf
ppm
 Sulfur oxides -
   annual arithmetic mean           80     0.03
   2A-hour concentration           365*    0.14*
   3-hour concentration

 Suspended Particulate matter -
   annual geometric mean            75
   24-hour concentration           260*

 Carbon monoxide -
   8-hour concentration                    9.0
   1-hour concentration                   35.0

 Photochemical oxidants -          160*    0.08*
   1-hour concentration            1

 Hydrocarbons
   (corrected for methane)
   3-hour concentration (6-9am)    160*    0.24*
 Nitrogen oxides -
   annual arithmetic mean          100     0.05
        1300*   0.5*
          60
         150*
        Same as pri-
        mary

        Same as pri-
        mary
        Same as pri-
        mary
        Same as pri-
        mary
  * Not to be exceeded more than once a year.
 ** 40 CFR 50; 36 FR 22384, November 25, 1971, EPA Regulations.
                                  A-l

-------
40 CFR, PART 60 - STANDARDS OF FKRFOR.MAIiCE FOR NEW STATIONARY
SOURCES

60.2 Definitions

     (a)  "Act" means the Clean Air Act (42 U.S.C. 1857 et seq.,  as
          amended by Public Law 91-604, 84 Stat.  1676).
     (c)   "Standard" means a standard of performance proposed or
          promulgated under this part.

     (d)   "Stationary source" means any building,  structure,
          facility,  or installation which emits or nay emit any
          air pollutant.
     (f)   "Owner or operator" means any person who owns,  leases,
          operates, controls, or supervises an affected facility
          or a stationary source of which an affected facility is
          a part.

     (g)   "Construction" means fabrication, erection, or  installa-
          tion of an affected facility.
     (j)  "Opacity" means the degree to which emissions reduce the
          transmission of light and obscure the view of an object
          in the background.
     (v)   "Particulate matter" means any finely divided solid or
          liquid material, other than combined water, as measured
          by Method 5 of Appendix A to this part or an equivalent
          or alternative method.

Subpart 0 - Standards of Performance for Sewage Treatment Plants^

60.150  Applicability and designation of affected facility.

        The affected facility to which the provisions of this sub-
        part apply is each incinerator which burns the sludge pro-
        duced by municipal sewage treatment facilities.
                                  A-2

-------
60.152  Standard for  particulate matter.

        (a)   On and after  the date on which the performance  test
             required to be conducted by  60.8 is completed,  no
             owner  or operator ^f -ny sewage sludge incinerator
             subject  to the provisions of this subpart  shall dis-
             charge or cause the discharge into the atmosphere  of:

             (1)  Particulate matter at a rate in excess of  0.65
                  g/kg dry sludge input (1.30 Ib/ton dry sludge
                  input).

             (2)  Any gases which exhibit 20-percent opacity or
                  greater.  Where the pressence of uncombined water
                  is  the only reason for  failure to meet the require-
                  ments of this paragraph, such failure shall not
                  be  a violation of this  section.

60.154  Test Methods  and Procedures
        (b)  For Method 5, the sampling time for each run shall be
             at least 60 minutes and the sampling rate shall be at
             least 0.015 dscm/min (0.53 dsef/min),  except that
             shorter sampling times, when necessitated by process
             variables or other factors, may be approved by the
             Administrator.
        (c)
             (3)  Determine the quantity of dry sludge per unit
                  sludge charged in terms of either R^.., or R^j.

                  (i)  If the volume of sludge charged is used:
                       S  =  (60 X 10  )
                  or
                                    R_  S
                       SD =  (8.021) -~ (English Units)
                  where:
                        D =  average  Jry  sludge  charging  rate  during
                             the  run,  kg/hr  (English units:   Ib/hr).
                                  A-3

-------
               uV  =  average  quantity of dry  sludge per
                    unit volurae  of  sludge charged to the
                    incinerator, mg/1  (English Units:
                    lb/ft3).
               Sy  =  sludge charged  to  the incinerator during
                    the run, m   (English units:  gal).
               T  =  duration of  run, min (English units:
               _     min) .
        60 x  10   =  metric units conversion  factor,  1-kg-
                    min/m -mg-hr.
           8.021  =  English  units conversion factor,
                    ft^-min/gal-hr.

          (ii)  If the mass  of sludge  charged is used:

                         n  S
               S  = (60)    !? M  (Metric or English Units)

         where:
                S   =  average  dry  sl-idge  charging  rate  during
                     the  run, kg/hr  (English units:  Ib/hr).
               R   =  average  ratio of  quantity  of dry  sludg
                     to quantity  of  sludge  charged to  the
                     incinerator, mg/mg  (English  units:
                     Ib/lb).
                S   =  sludge charged  during  the  run,  kg
                     (English units:   Ib).
                T  =  duration of  run,  min  (Metric or English
                     units).
                60  =  conversion factor,  min/hr  (Metric or
                     English  units).

(d)   Particulate emission rate  shall be  determined by:

     C    = C Q  (Metric  or English Units)
      aw    s s
     where:
          C   = particulate matter mass emissions,  mg/hr
                (English units:   Ib/hr).               _
           C  = particulate matter concentration,  mg/m
            8   (English units:   Ib/dscf).
           Q  = volumetric stack gas flow  rate,  dscm/hr
            S   (English units:   dscf/hr).   Qg and Cg shall
                be determined using Methods 2 and 5,
                respectively.
                         A-

-------
        (e)  Compliance with 60. 152 (a) shall be determined as
             follows:
             C .  =  (10"3) ^ (Metric Units)
              ds          S
             or
                          C
             C .  = (2000) -=52- (English Units)
              ds          bD
             where:

                   C,  = particulate emission discharge, g/kg dry
                     -   sludge (English units: Ib/ton dry-sludge).
                  10   = Metric conversion factor, g/mg.
                  2000 = English conversion factor, Ib/ton.

(39 FR 9319, Mar. 8, 1974; 39 FR 13776, Apr. 17, 1974; 39 FR 15396,
May 3, 1974)
STATE AND KNOX COUNTY

Tennessee Air Quality Act (Tennessee Code Annotated Section 53-3408
et seq.)

Tennessee Air Pollution Control Regulations

Chapter II - Definitions

     The following terms shall, unless the context clearly indicates
otherwise, have the following meaning:

     1.  Air Contaminant is particulate matter, dust, fumes, gas,
         mist, smoke, or vapor, or any combinations thereof.

     2.  Air__Corvtaminant Source is any and all sources of emission
         of air contaminants, whether privately or publicly owned
         or operated.  Without limiting the generality of the fore-
         going, this term includes all types of business, commercial
         and industrial plants, works, shops, and stores, and heating
         and power plants and stations, building and other structures
         of all types, including multiple family residences, apart-
         ment houses, office buildings, hotels, restaurants, schools,
         hospitals, churches and other institutional buildings, auto-
         mobiles, trucks, tractors, buses and other motor vehicles,
         garages and vending and service locations and stations,
                                 A-5

-------
     railroad locomotives, ships,  boats and other water borne
     craft, portable fuel-burning  equipment, incinerators  of  all
     types, indoor and outdoor, refuse dumps and piles, and all
     stack and other chimney outlets from any of the foregoing;
     provided, however, that neither automobiles, trucks,  tractors,
     buses or other motor vehicles powered by any fuel other  than
     diesel oil and which were manufactured prior to September  1,
     1967, automobiles, trucks, tractors, buses or other motor
     vehicles powered by diesel oil and manufactured prior to
     January 1, 1970, nor automobiles, trucks, tractors, buses
     or other motor vehicles which are equipped to comply  and
     do comply with the Federal "Motor Vehicle Air Pollution
     Control Act" shall be considered or determined to be  an
     "air contaminant source."
 4.   Air Pollution is presence in the outdoor atmosphere of
     one or more air contaminants in sufficient quantities  and
     of such characteristics and duration as to be injurious  to
     human, plant or animal life or  to property, or which
     unreasonably interfere with the enjoyment of life and
     property.

 5.   Ambient Air is that portion of  the atmosphere, external
     to buildings.

 6.   Board is the Air Pollution Control Board of the State  of
     Tennessee.
 9.   Department is the Department of  Public Health of  the State
     of Tennessee.

10.   Effective date of these regulations is April 3,  1972.

11.   Emission is the release of  material to the ambient  air.
15.   Fugitive Dust is any visible emission,  other than water
     droplets, issuing from any source other than through  a
     stack.

16.   Garbage is putrescible animal or vegetable waste.
                             A-6

-------
17.   Hazardous Air Contaminant  is  any air contaminant which
     may cause, or contribute  to,  an increase  in mortality or
     an increase in serious  irreversible, or incapacitating
     reversible illness and  has been so designated  by  the
     Technical Secretary.

18.   Incinerator is any equipment, device or contrivance used
     for disposal of waste of  refuse by burning, excluding
     wigwam burners and air  curtain destructors.
20.  Modification is any physical change in, or change in the
     method of operation of an air contaminant source which
     increases the amount of any air contaminant emitted by
     such source or which results in the emission of any air
     contaminant not previously emitted except that:

     a.  routine maintenance, repair, and replacement shall
         not be considered physical changes, and

     b.  the following shall not be considered a change in
         the method of operation:

         1.  an increase in the production rate, if such in-
             crease does not exceed the operating design
             capacity of the affected source;

         2.  an increase in the hours of operation; and

         3.  the use of an  alternate fuel  if  the source is
             designed to accommodate such  alternate fuel:

     provided, however, that the Technical Secretary  is notified
     within  thirty  (30) days of  such changes.
 22.   New Source  is  any air  contaminant  source constructed  after
      April 3,  1972,  and any air  contaminant source constructed
      prior to  that  date to  which any modification is made  after
      that date.

 23.   New Source  Performance Standard is a standard for the
      emission of an air contaminant promulgated by the Admin-
      istrator of the Environmental Protection Agency and pub-
      lished in the  Federal  Register.
                              A-7

-------
25.   Opacity is that  property of a substance tending to  obscure
     vision and is  measured  in terms  of  percent obscuration.
     As used in these regulations it  does not include obscura-
     tion of vision due  to uncombined water droplets. The  per-
     centage opacity  of  a plume is m "-«»••< cally equal to  twenty
     (20)  times the Ringelmann number for a plume of black
     smoke having equivalent capacity of obscuration.

26.   Open Burning is  the burning of any  matter under such con-
     ditions that the products of combustion are emitted
     directly into  the open  atmosphere without passing directly
     through a stack except  when equipment is provided and  used
     to control fuel-air ratio.

27.   Particulate Ma_t_ter  is any material, except uncombined
     water that exists in a  finely divided form as a liquid or
     a solid.

28.   Parts Ber Billion (ppb) is a term describing parts  of  an
     air contaminant  per billion parts of gas by volume  (1  ppb
     equals 0.0000001 percent by volume).

29.   Parts Per Million (ppm) is a term describing parts  of  an
     air contaminant per million parts of gas by volume  (1  ppm
     equals 0.0001 percent by volume).

30.   Person is any individual, partnership, copartnership,
     firm, company, corporation, association, joint stock
     company, trust,  estate, political subdivision, or any
     other legal entity, or  their legal representative,  agent
     or assigns.

31.   Political Subdivision is any municipality, city, incor-
     porated town, county, district or authority, or any
     portion of combination of two or more thereof.
33.  Process Emission is any emission of an air contaminant to
     the ambient air other than that from fuel burning equip-
     ment, incinerator, wigwam burners, or open burning.
 38.  RingeLnann Chart_ is the chart published and described in
     the U. S. Bureau of Mines Information Circular 8333.
                             A-8

-------
    39.  Salvage Operation is any business,  trade or industry
         engaged in whole or in part, in reclaiming one or more
         items of value.

    40.  Smoke is small gas-borne particles  resulting from incom-
         plete combustion, consisting predominantly, but not
         exclusively, of carbon and other combustible material.
         It does not include water vapor or  water droplets.

    41.  Soiling Index is a measure of the soiling properties  of
         suspended particulates determined by drawing a measured
         volume of air through a known area  of Whatman No. 4 filter
         paper for a measured period of time, expressed as co-
         efficient of haze (COH) per 1,000 linear feet.

    42.  Stack is any chimney, flue, duct, conduit, exhaust, vent,
         or opening of any kind whatsoever capable of, or used for,
         the emission of air contaminants.

    43.  Suspended Particulates is particulate matter which will
         remain suspended in air for an appreciable period of  time.

    44.  Technical Secretary is the Technical Secretary of the Air
         Pollution Control Board of the State of Tennessee.

    45.  Wigwam Burner is a type of burner commonly known as
         tepee, truncated cone, conical burner, or silo burner.

Chapter III__-_Ambient Air Quality Standards

Section I — Applicability

     Ambient air quality standards as given  in Tables I, II, and
III are applicable throughout Tennessee.

     These ambient air quality standards shall not be construed,
applied or interpreted to allow any significant deterioration  of
the existing air quality in any portion of the state.

Section 2 — Definitions

     Primary ambient air quality standards define levels of air
quality believed adequate, with an appropriate margin of safety,
to protect public health.

     Secondary ambient air quality standards define levels of  air
quality believed adequate, with an appropriate margin of safety, to
protect the public welfare from any known anticipated adverse
effects of the pollutant.
                                 A-9

-------
                           TABLE A-l

     TENNESSEE AND KNOX COUNTY AMBIENT AIR QUALITY STANDARDS
           FOR SUSPENDED PARTICULATES SULFUR DIOXIDE.
            CARBON MONOXIDE.  PHOTOCHEMICAL OXIDANTS.
         NON-METHANE HYDROCARBONS, AND NITROGEN DIOXIDE
Contaminants
Suspended
Particulates
Sulfur
Dioxide
Carbon
Monoxide
Photo-
Chemical
Ox id ant
Hydrocarbons
(non-
rne thane)
Nitrogen
Dioxide
Primary Standard
Concentration
3
ug/m
75
260
80
365
10,000
40,000
160
160
100
ppm
by vol.
	
0.03
0.14
9.0
35.0
0.08
0.24
0.05

Average
Interval
AGM
24 hr
AAM
24 hr
8 hr
1 hr
1 hr
3 hr
a .in.
AAM
Secondary Standard
Concentration
3
ug/m
60
150
60
364
1,300
10,000
40,000
.160
160
100
ppm
by vol.
	 	
0.02
0.139
0.5
9.0
35.. 0
0.08
0.24
0.05
Average
Interval
AGM
24 hr
AAM
24 hr
3 hr
8 hr
1 hr
1 hr
3 hr
a.m.
AAM
Note:  1.  All values other than annual values are maximum concen-
           trations not to be exceeded more than once per year.
       2.  PPM values are approximate only.
       3.  All concentrations relate to air at standard conditions
           of 25°C temperature and 760 millimeters of mercury
           pressure.
                                 A-10

-------
4.  ug/m  - micrograms per cubic  meter.
5.  AGM - Annual geometric mean.
6.  AAM - Annual arithmetic mean.
                    TABLE A-2
TENNESSEE AMBIENT AIR QUALITY STANDARDS  FOR SOILING
  INDEX IN COH UNITS PER 1000 LINEAR FEET OF AIR
Primary Standards
Soiling
Index
1.0
3.5
Averaging
Interval
24 hr
average
2 hr
average
Secondary Standards
Soiling
Index
0.6
2.0
Averaging
Interval
24 hr
average
2 hr
average
   Note:  All values are maximums not to be exceeded
          more than once per year.
                         A-ll

-------
                           TABLE A-3

       TENNESSEE AMBIENT AIR QUALITY  STANDARDS FOR GASEOUS
                    FLUORIDES EXPRESSED AS HF
Primary Standards
Concentration
ug/m
1.2
1.6
2.9
3.7
ppb
by vol.
1.5
2.0
3.5
4.5
Averaging
Interval
30 days
7 days
24 hr
12 hr
Secondary Standards
Concentration
ug/m
1.2
1.6
2.9
3.7
ppb
by vol.
1.5
2.0
3.5
4.5
Averaging
Interval
30 days
7 days
24 hr
12 hr
       Notes:  1.  All values are maximums not to be exceeded
                   more than once per year.
               2.  Concentrations in micrograms per cubic
                   meter (ug/m )  are approximate only.
               3.  All concentrations relate to air at
                   standard conditions of 25°C temperature
                   and 760 millimeters of mercury pressure.
Section 4 —

     The standards set forth in this Chapter shall be achieved by
July 1, ,1975.

Chapter V - Visible Emission Regulations

Section 1 — Definition

     As used in this Chapter, existing air contaminant source refers
to such sources as were in operation or under construction prior to
August 9, 1969, and new air contaminant sources refers to such sources
as began construction on or after August 9, 1969.
                                A-12

-------
Section 2 — General

     A.  No person shall cause,  suffer,  allow or  permit  discharge
         of a visible emission from any  new air contaminant  source
         within a density greater than number one (1)  on the
         Ringelmann Chart or an opacity  in excess of  twenty  (20)
         percent for an aggregate of more than five (5)  minutes
         in any one (1) hour or more than twenty  (20)  minutes  in
         any twenty-four (24) hour period.

     B.  On and after August 9,  1973, no person shall cause,
         suffer, allow or permit discharge of a visible  emis-
         sion from any existing air contaminant source with a
         density equal to or greater than number  two (2) of the
         Ringelmann Chart or an opacity  equal to  or in excess  of
         forty (40) percent for more than five (5) minutes in  any
         one (1) hour or an aggregate of more than twenty (20)
         minutes in any twenty-four  (24) hour period.

     C.  On and after August 9, 1975, the provisions of  subsection
         B of this Chapter shall no  longer be applicable and all
         air contaminant sources shall be construed as new sources
         for the purpose of  this Chapter.
     E.  It is expressly intended that in testing compliance with
         subsections A and B that visible emissions tending to
         produce a black plume will be evaluated in terms of the
         Ringelmann scale and that visible emissions tending to
         produce a non-black plume will be evaluated in terms of
         equivalent opacity and expressed as percent opacity.

 Chapter VI - Non-Process JEmission Standards

 Section  1 — General Non-Process Particulate Emissions

     A.  No person  shall  cause,  suffer,  allow  or permit particulate
         emissions  in  excess  of  the  standards  in this  Chapter.

      B.  In  any  county where  one  or  more sources are  emitting
         particulates  at  rates  in  conformity with  applicable maxi-
         mum  allowable emission rates and the  ambient  air quality
          standard  for  particulate  matter is being  exceeded, the
          Board shall  be responsible for setting an appropriate
          emission standard for each source contributing to the
          particulate  matter in the ambient air of  the county, at
          such value as the Board may consider necessary to achieve
          the desired  air quality.
                                  A-13

-------
    C.  The owner or operator of an existing fuel burning
        installation proposing to make a modification of this
        source  or to rebuild or replace it shall only take such
        action  if it will result in the source meeting the maxi-
        mum allowable  particulate emission standards for a new
        fuel  burning installation.

    D.  As used in  this  chapter, existing installations or equip-
        ment  shall  mean  such as were  under construction or in
        operation prior  to  the effective date of these regulations.

Section 2  — Non-Process  Particulate Emission Standards
     C.  Incinerators

         From and after the effective date of these  Regulations,
         the maximum allowable particulate emission  from incinera-
         tors shall be as indicated in Table 1 of  this Chapter.
         It is further provided that from and after  July 1,  1975,
         the particulate emission standards as given for existing
         incinerators shall no longer be applicable  and the  parti-
         culate emission standards as given for new  incinerators
         shall be applicable to all incinerators.
                             TABLE A-4
             MAXIMUM ALLOWABLE PARTICULATE EMISSION
                   STANDARDS FOR INCINERATORS
Rated of Operated Charging
Rate in Pounds per Hour
Less than 200
200 to 2000
Greater than 2000
Greater than 2000*
Emission Standard in
Percent of Charging Rate
New
Incinerator
0.2
0.2
0.1
0.075
Existing
Incinerator
0.6
0.4
0.4

     * For Knox County
                                 A-14

-------
         Incinerators having 2.5 cu ft furnace volume or less
         used solely for the disposal  of  infective dressings and
         other similar material shall  not be  required to meet
         these emission standards.

Section 3 — General Non-Process Gaseous  Emissions

     A.  No person shall cause,  suffer, allow or permit gaseous
         emissions in excess of  the  standards in this Chapter,

     B.  Any person constructing or  otherwise establishing an air
         contaminant source  emitting gaseous air contaminants
         after the effective date of these regulations shall
         install and utilize the best equipment and  technology
         currently available for  controlling such gaseous  emission.

Section 4 — Sulfur Oxides

     A.  General Provisions,

         1   In  any county where one or more sources  are sitting
             sulfur oxideUd all = ^--th^county^re


             sr^^
             or  620 parts per million correctea >•" ^J v
             excess £r by volume calculated  BS sulfur dioxide
             fSul)  and the ambient air  quality for sulfur dioxide
             (b\)2)  aua uue *" ,      _ „,  ct,flii he responsible for
             is being exceeded, the Board  shall be    P
             setting emission standards for """^   f  he count
             to the sulfur oxides in the anbient air oi- *•        -
             at such value as the Board may consider ncc^sary
             achieve the desired air quality.



     B.  Emission Standards
                       -.

                          i  1973   the ou-ner or operator of an air
            After January 1,  1973,  theown       j   effective dac
            ing:
                               A-15

-------
             a.  440 ppm corrected to 15 percent excess air when
                 liquid fossil fuel is burned (equivalent to 0.80
                 Ibs per million Btu heat input, maximum 2 hour
                 average).

             b.  620 ppm corrected to 15 percent excess air when
                 solid fossil fuel is burned (equivalent to 1.2
                 Ibs per million Btu heat input, maximum 2 hour
                 average).

             c.  Where different fossil fuels are burned simultan-
                 eously in any combination,  the applicable standard
                 shall be determined by proration.  Compliance shall
                 be determined by using the  following formula:

                           Y (0.80) + Z (1.2)
                                X + Y + Z

                 where:

                       X is the percent of total heat input derived
                       from gaseous fossil fuel and,

                       Y is the percent of total heat input derived
                       from liquid fossil fuel and,

                       Z is the percent of total heat input derived
                       from solid fossil fuel.

         3.  It shall be the responsibility  of  the owner or operator
             of such air contaminant source  to monitor or otherwise
             demonstrate that sulfur oxides  in gases discharged from
             the source do not exceed the applicable concentration.
Section 5 — Nitrogen Oxides

     A.  Emission Standards

         1.  New Air Contaminant Sources

             Air contaminant sources with a total heat input of
             250 million Btu's per hour or greater constructed
             after April 3, 1972,  shall not cause, sulfer,  allow
             or permit the emission of nitrogen oxides (measured
             as N02) in excess of  the following:
                                A-16

-------
            a.  165 ppm corrected to 15 percent excess air when
                gaseous fossil fuel is fired [equivalent to 0.20
                Ibs of nitrogen oxides (measured as NO2) per
                million Btu heat input, maximum 2 hour average}.

            b.  227 ppm corrected to .15 percent excess air when
                liquid fossil fuel is firec [equivalent to 0.30
                Ibs of nitrogen oxides (measured as NC^) per
                million Btu heat input, maximum 2 hour average].

            c.  525 ppm corrected to 15 percent excess air when
                solid fossil fuel is fired [equivalent to 0.70
                Ibs of nitrogen oxides (measured as N02) per
                million Btu heat input, maximum 2 hour average].

            d.  When different fossil fuels are burned simultan-
                eously in any combination the applicable standard
                shall be determined by proration.  Compliance
                shall be determined by using the following
                formula:
                          X (0.20) Y (Q.30) Z (0-70)
                                  X + Y + Z
                where:
                      X  is the percent of total heat input derived
                      from gaseous fossil fuel and,

                      Y  is the percent of total heat input derived
                      from liquid fossil fuel and,

                      Z  is the percent of total heat input derived
                      from solid fossil fuel.

Chapter IX - Construction and Operating Permits

Section 1 — Construction Permits

     A.  On and after April  3, 1972,  no  person shall begin the con-
         struction of a  new  air contaminant  source or the modifica-
         tion of an air  contaminant  source  existing prior to
         April 3, 1972,  which may result in the discharge of air
         contaminants without first  having  applied for and received
         from the Technical  Secretary a construction permit for the
         construction or -modification of such air contaminant source.

     B.  The application for a construction permit shall be made on
         forms available from the Technical Secretary not less than
                                A-17

-------
         ninety (90) days prior to the estimated starting date of
         construction.

     C.  In the event the requirement for a construction permit
         prior to the construction of a new air contaminant source
         or the modification of any existing air contaminant source
         will create an undue hardship on the applicant, the appli-
         cant may request of the Technical Secretary a waiver to
         proceed with construction or modification prior to the
         issuance of a Construction Permit.  The applicant for a
         waiver shall explain the circumstances which will cause
         such undue hardship.  If a waiver is granted, the appli-
         cant shall, as soon as reasonably practical, submit a
         report containing such information as would have otherwise
         been required in filing for a construction permit.

         The applicant, after a waiver is granted, proceeds at his
         own risk; and, if after construction or modification has
         begun or been completed, the proposed or completed
         installation does not meet with the Technical Secretary's
         approval, alterations required to effect such approval
         shall be made within a reasonable time as specified by the
         Technical Secretary.  In no case shall this reasonable
         time exceed 180 days after notification that the con-
         struction or modification does not meet the Technical
         Secretary's approval.

     D.  Construction permits issued under this section are based
         on the control of air contaminants only and do not in any
         way affect the applicant's obligation to obtain necessary
         permits from other governmental agencies.

     E.  The Technical Secretary shall not grant a permit for'the
         construction or modification of any air contaminant source
         if such construction or modification will interfere with
         the attainment or maintenance of the secondary air quality
         standards or will violate any provision of these regula-
         tions.

Section 2 — Operating Permit

     A.  Any person planning to operate an air contaminant source
         constructed or modified in accordance with a construction
         permit issued by the Technical Secretary, in Section 1,
         shall apply for and receive an operating permit from the
         Technical Secretary within sixty (60) days after commence-
         ment of the operation of said air contaminant source.
                                 A-18

-------
    D.  Application for an operating permit shall be made on
        forms available from the Technical Secretary and signed
        by the applicant.  Such application for an operating
        permit shall be filed with the Technical Secretary not
        less than thirty (30) days prior to the expiration of an
        existing operating permit.

    E.  The operating permit shall only be issued on evidence
        satisfactory to the Technical Secretary that the operation
        of said air contaminant source is in compliance vith any
        standards or rules and regulations promulgated by the Board
        and that the operation of said air contaminant source will
        not interfere with the attainment or maintenance of the
        secondary air quality standard.  Such evidence may include
        a requirement that the applicant conduct such tests as are
        necessary in the opinion of the Technical Secretary to
        determine the kind and/or amount of air contaminants
        emitted from the source.  Standard operating permits shall
        be valid for a period of one  (1) year or for such longer
        period of time as the Technical Secretary may designate.
        A permit issued  for  a period  of less than one (1) year
        shall be designated  as a  temporary permit.

    F.  Any person  in possession  of an operating permit  shall
        maintain said operating permit readily  available for
        inspection  by the Technical Secretary or his designated
        representative on the operating premises.

    G.  Operation of each air contaminant  source shall be  in
        accordance  with  the  provisions and  stipulations  set  forth
        in  the operating permit.
Section 3
     No person shall discharge from any source whatsoever such
quantities of air contaminants, uncombined water, or other
materials which cause or have a tendency to cause a traffic hazard
or an interference with normal means of public transportation.
Section 4 — Exemptions

     A.  No person shall be required to obtain or file a request
         for a State permit due to ownership or operation of the
                                 A-19

-------
         following air contaminant sources unless specifically
         required to do so by the Board:

         1.  Mobile sources such as:  automobiles, trucks,  buses,
             locomotives, planes, boats and ships;

         2.  Fuel-burning equipment of less than 500,000 Btu per
             hour capacity;

         3.  Particulate emissions from a single stack, of  an air
             contaminant source, discharging less than 0.5  Ib per
             hour of non-hazardous particulates or the total par-
             ticulate emissions from an air contaminant source
             amounting to less than two (2) pounds per hour of non-
             hazardous particulates, whichever is the more
             restrictive.  This exemption does not apply to inci
             incinerators;

         4.  Equipment used on farms for  soil preparation,  tending
             or harvesting of crops or for preparation of feed to
             be used on the farm where prepared;

         5.  Operations exempted under Chapter IV (Open Burning)
             of these regulations;

         6.  Sources within the counties  of Shelby, Davidson,
             Hamilton and Knox until such time as the Board shall
             determine that air pollution is not being controlled
             in such county to a degree consistent with the sub-
             stantive provisions of the Tennessee Air Pollution
             Control Act and regulations  adopted pursuant thereto.

     B.  Notwithstanding the exemptions granted in Section  4A above,
         no person shall discharge, from  any source whatsoever, such
         quantities of air contaminants or other materials  which
         cause or have a tendency to cause injury, detriment,
         annoyance, or adverse effect to  the public.

Amendments to the Regulations. 19 June 1973

1.  Chapter II (Definitions) is amended by adding a new definition
    as follows:

    Point Source shall have the same meaning as defined in  Part 51
    of Title 40 of the Code of Federal Regulations.

2.  Chapter VI is amended by deleting entirely Section 4 and renum-
    bering the remaining sections accordingly.
                                A-20

-------
6.  Add the following Chapter XIV  -  Control of  Sulfur Compounds
    Emissions

Section I — General Provisions

     A.  For the purpose of this chapter  each county in Tennessee
         will be classified by the Board  into one  of three  cate-
         gories, defined as Class  I, Class II,  and Class  III.
         Ambient concentration limits  expressed as micrograms  per
         cubic meter which define  the  classification system for
         sulfur oxides are:

                                Class  1     Class II     Class III
                              Greater  Than   From  - To    Less  Than

         Annual Arithmetic        100           60-100          60
            Mean
         24-hour Maximum          455          260-455         260
         3-hour Maximum                        l,300a       1,300

              a Any concentration above 1,300 ug/tn

     B.  The above classification will be based upon measured
         ambient air quality, where known, or where not known,
         estimated air quality in the area of maximum sulfur oxide
         concentration.

     C.  The more restrictive classification will  be chosen where
         there  is a  difference between the maximum value(s) and the
         annual arithmetic mean,  e.q., if a county is a Class I with
         respect to  the  annual arithmetic mean  and Class II with
         respect to  a  24-hour maximum value, the  Classification will
         be Class I.

     D.  Where  a county  is classified  a Class  I county on  the basis
         of measured or  estimated air  quality  levels reflecting
         emissions  predominantly  from a  single point source,  it
          shall  be further classified  as  a Class IA county.

     E.   In any county where one  or more sources  are emitting sulfur
          oxides and all sources within the county are meeting the
          applicable emission standards of 1.6, 3.0, or 4.0 lb/10 Btu
          for fuel burning sources and 2000, 1000, or 500 parts per
         million for process sources  and the ambient air quality for
          sulfur dioxide is being  exceeded, the Board shall be respon-
          sible for  setting emission standards  for sources  contributing
                                 A-21

-------
         to the sulfur oxides in the ambient air of  the county,  at
         such value as the Board may consider necessary to achieve
         the desired air quality.

Section II — Non-Process Emission Standards

     A.  On and after July 1, 1975,  the  owner or operator of  an  air
         contaminant source located  in a Class I County shall not
         cause, suffer,  allow,  or permit the emission from that
         source of  sulfur oxides (calculated as sulfur dioxide)  in
         excess of  1.6 Ibs per  million Btu  heat input, maximum 2
         hour average.

     B.  On and after July 1, 1975,  the  owner or operator of  an  air
         contaminant source located  in a Class II County shall not
         cause, suffer,  allow or permit  the emission from that source
         of sulfur  oxides (calculated as sulfur dioxide)  in excess
         of 3.0 Ibs per  million Btu  heat input, maximum 2 hour
         average.

     C.  On and after July 1, 1975,  the  owner or operator of  an  air
         contaminant source located  in a Class III County shall  not
         cause, suffer,  allow or permit  the emission from that source
         of sulfur  oxides (calculated as sulfur dioxide)  in excess
         of 4.0 Ibs per  million Btu  heat input, maximum 2 hour
         average.
     H.   After  January 1,  1973,  the  owner  or  operator  of  an  air
         contaminant  source  with more  than 250 million Btu per hour
         heat input,  constructed after April  3,  1972,  shall  not
         cause, suffer,  allow or permit  the emission from that
         source of  sulfur  oxides (calculated  as  sulfur dioxide)  in
         excess of  the following:

         a.  0.80 Ibs per  million  Btu  heat input, maximum 2  hour
            average, when liquid  fossil is burned.

         b.  1.2 Ibs  per million Btu heat  input, maximum  2 hour
            average, when solid fossil  fuel  is  burned.

         c.  Where  different fossil  fuels  are burned simultaneously
            in any combination, the applicable  standard  shall be
            determined by proration.  Compliance shall be deter-
            mined  by using  the  following  formula:
                               A-22

-------
                      Y  (0.80) + Z (1.2)
                          X + Y + Z
            where:
                  X  is  the percent of total heat input derived
                  from  gaseous fossil fuel and,

                  Y  is  the percent of total heat input derived
                  from  liquid fossil fuel and,

                  Z  is  the percent of total heat input derived
                  from  solid fossil fuel.

Amendments to the RegulationsT 9  October  1973

     Chapter XIV, Section 1,  is amended by adding the following
subparagraph (F) to  read:

    "F.  The following is the Board designation of  counties
         adopted pursuant to paragraph  (A) above:

              Class 1A - Polk

              Class 1  - Sullivan, Roane, Maury

              Class 2  - Humphreys

              Class 3  - All other counties in the State."

Amendments to the Regulations. 10 May 197A
      3.  That Chapter III  (Ambient Air Quality Standards) be and
         the same  is hereby amended by deleting in Table 1, the
         secondary standard for Sulfur Dioxides for  the A.M. and
         24 hour average interval and having  such standard read
         the same  as the primary standard.
                                  A-23

-------
                         AIR QUALITY
                    KNOXVILLE-KNOX COUNTY

                   SUSPENDED PARTICULATES
                 Annual Geometric Mean (AGM)
                          (pg/m3)
Station    1973     1974                Location
  012      47.7     41.7    Rutledge  Pike  (Skaggston Sch.)
  013      32.5     29.6    Beaver Cr. Dr.  (Hallasdale-Powell
                               Lab)
  014      48.0     48.1    Hendon Chapel  Rd.  (Gap Creek Sch.)
  003      81.6     73.6    Locust St. & Cumberland Ave.
  005      96.5     88.7    Papermill Rd.  & Westover Dr.
  006      59.5     56.1    Young High Pike &  Chapman Highway
  007      71.1     71.8    Asheville Highway  & Tulane Ave.
  008      84.4     74.6    1-95 & Heiskell Ave.
  Oil      95.4    103.0    17th Street fi,  Dale Ave.
                               A-24

-------
                          APPENDIX B
GENERAL WATER QUALITY CRITERIA FOR THE DEFINITION AND CONTROT
              OF POLLUTION IN THE WATERS OF TENNESSEE

-------
                                              APPCNOIX e

                    6ENEUL VATER QUALITY CRITERIA FOR THE DEFINITION AND CONTROL OF
                                POLLUTION  IN  TH£ WftTERS OF TENNESSEE
                                     Adopted  en October 26. 1971
                          Amended on December 14, 1971 and October 30.  1973
                                Tennessee Viler Quility Control Board
The Vater Quality Control  Act of 1971, Chapter 16* Public Act* of J971 u i-end*d by Chapter J86,  makes It the
doty of the Water Qjality  Control Board  to study and  investigate ill problem concerned with the pollution of
the waters of the State  and with its prevention, abatement, and control and to establish such standards of
quality for any v»ter» of  the State  in relation to their re«son«bl« and necessary use as the Board shall deem
to be tn the public interest and establish general policies relating to existing or proposed future pollution
•t the Board shall deem, necessary to accomplish the purpose of the Control Act.  The following general consider-
ations and criteria are  officially adopted by  the Board as a guide In determining the permissible conditions of
ttalen with respect to pollution and the preventive and corrective measures required to control pollution In
various waters or in different sections  of the same waters.
GENERAL CONSIDERATIONS

      1.  Waters have »any uses which In the public interest arc reasonable and necessary.  Such uses Include:
          sources cf water supply for domestic and industrial purposes; propagation and maintenance of fish and
          «th*r desirable  aqautic life;  recreational  boating and fishing; the linal disposal of municipal sewage
          and Industrial waste following adeovate treatment; atock watering and irrigation; navigation; genera-
          tion of power; and th« enjoyment of  scenic  and esthetic qualities of the waters.
      Z.  The rigid application of uniform water quality is not desirable or reasonable because of the varying
          l»e* of such waters.  The assimilative capacity of a stream for sewage and waste varies depending upon
          various factors  including the  following,  volwoe of flo-. depth of ch.on.1. the presence of falls or
          rapids,  rate cf  flow,  temperature, natural characteristics, and the nature of the stream.  Also the
          relative laporlance assigned to each use -ill differ for different w*ter« and sections of waters  :
          throughout the stream.

      5.  to permit reasonable and necessary uses of the waters of the State,  existing pollution should be cor-
          rected as rapidly as practical and future pollution controlled by treatment plants or other measures.
          There Is an economical balance between the cost of sewage and waste treatment and the benefits re-
          eetved,   tfilhln  permissible limits,  the dilution faetoV'and the assimilative capacity of surface water
          Should be utilized.  Vaste recovery,  control of rates and dispersion of waste into the streams, and
          control cf rates and characteristics of flow of water* in the stream where adequate, will be .considered
          to be a aieana of correction.
      «.  Sewage,  Industrial wastes, or  other  wastes, as defined In the Water Quality Control Act of 1971,
          Chapter 16* Public Acts of 1971, as  amended by Chapter 386, shall not be discharged Into or adjacent
          to streams or other surface waters in such  quantity and of such character or under such conditions
          of discharge in  relation to the receiving waters as will result in visual or olfactory nuisances, un-
          *»« Interference to other reasonable and necessary uses of the water, or appreciable damage to the
          natural processes cf self-purification.  In relation to the various qualities and the specific uses of
          the receiving waters,  no sewage, industrial wastes, or other wastes discharged shall be responsible
          for conditions that fail to »ect the criteria of water quality outlined below.  Bypassing or accidental
          apllla will  not  be tolerated.

          the criteria of  water quality  outlined below are considered as guides In applying the water quality
          objective. |n order to Insure  reasonable and necessary uses of the waters of the Slate.  In order to
          protect the public health and  maintain the water suitable for other reasonable and necessary uses; to
          provide t,r future development; to allow proper iharing ef available water resoureesj and to meet th,
          needs of particular situations, additional criteria will bo set.
                                                  B-l

-------
OUTER I* OF WCP CO'OITIOtt
      ].  Domestic Raw Water Supply
          (t)  Dissolved Oxygen . There >htll always bt »uf Tie lent dissolved oxygen present to prevent
              •dor* of decomposition and other offensive conditions.
          (b)  pH  t The pH value shall lie within the range of 6.0 to  9.0 and shall net fluctuate more
              than 1.0 unit In this range over a period of 24 hour*.
          (e)  Kardnes* or Mineral Compounds - There shall be no substances  added to the waters that will
              Increase the hardness or mineral content of the water*  to  such an eitent to appreciably
              letpalr the usefulness of the water as a source of domestic  water supply.
          (d)  Total Dissolved Solids - The total dissolved solids snail  at  no lime e«ceed £00 mg/1.
          (c)  Solids, Floating Materials and Deposits - Tr.ere shall be no distinctly visible solids,
              scum, foam,  oily sleek,  or the formation of slimes,  bottom  deposits  or sludge banks of
              such (It* or character as may impair the usefulness: of  the  water as  s source of domestic
              water supply.
          (0  Turbidity or Color - There shall be no turbidity or color sdded In amounts or character-
              istic* that cannot be reduced to acceptable concentrations  by conventional water treat-
             ment processes.
          (gl Tnpcrstur* .  The maximum water temperature change  shall not Vxceed  3C  relative to an
             upstream control  point.   The temperature  of the water shall not  exceed 30.5 C and the
             •ailMM rate of change  shall not exceed 2C  per hour.  The  temperature of Impoundments
             •her* stratification occurs  will  bt measured  at a depth of  S feel, or aid-depth which.
             «ver Is less,  and the temperature In flowing  stream shall  be Measured at aid-depth.
          (h) lHa»ii'iiii'ial Coliform - The concentration  of the  fecal eel if era group shall  not ex-
             ceed 1,000 per 100 ml.  as the logarithmic Man based on a minimum of 10 samples col.
             Itctetf from  s  given sampling site aver  t period of not more than SO  consecutive days
             with Individual samples  being collected at  intervals of not less than 12 hours.   In
             addition,  the  concentration  of the fecal coliform group in any individual sample shall
             not exceed S.OOO  per 100 ml.
         (I) Taste or Odor  - There shall  be no substances  added which will result In taste or odor
             that prevent the  production  of potable water by conventional water treatment processes.
         (fl Toxic Substances  - There  shall  be no toxic substances added to the waters that  will
             •reduce toxic  conditions  that  Biter!ally affect man or animals or impair the safety of
             • conventionally  treated  water supply.
         W Other Pollutants  - Other  pollutants  shall net be-added te the water  in oyantlties  that
             •ay be  detrimental  to public  health  or  impair the usefulness of  the  water as •  source of
             domestic water supply.

     2.   Industrltl Water Supply

         (el Dissolved Oxygen - There shall  always be sufficient  dissolved oxygen present  to  prevent
             •dor* of decomposition and other offensive conditions.
         (b) fH - The pH value shall lie within the range of C.O  to 9.0 and shall not  fluctuate  mere
             thin 1.0 unit  In this range over a period of 24 hours
         (•) Nardne** er Mineral Compounds - There shall be no substances added to  the water*  that
             will Increase  the hardness or mineral content of the waters to such an extent as to ap-
             preciably Impair the usefulness of the water as a source of industrial water  supply.
         (d)  fatal Dissolved Solids . The total dissolved solids  shall  at no time cmceed  500 mo/1.
         (•) Solids, Floating Materials and Deposits - There shall be no distinctly visible solids,
            •cum, foam, oily sleek, or the formation of slime*,  bottom deposits or sludge banks of
            •uCh tit* or character as may Impair the usefulness  of the  water a* a e ounce  of  industrial
            inter supply.
         (0 Turbidity or Color . There shall! be no turbidity or color  added] In amounts or character.
             Ittles that cannot be reduced to acceptable concentrations by conventional water treatment
            processes.
                                             B-2

-------
(g)  Temperature -  The  ma»i»i>»  water  temperature chanos shall not exceed X* relative  to  on wpstrea*
    control  point.   The  tc«perature  of  the  «»t«r thSU not exceed SO. S°C end the maximum rat* of
    change ahall not e.ceed JC°  per  hour.   The temperature af impoundments where stratification
    »^.^r» will b« measured it • depth  of S feet, or ••d-dcp'.h whichever i« leaa,  »nd th« tempera-
    ture In flowing streams shall  be measured at mi'd-deplh.
(h)  Taste or Odor  - I'.crc  chill  be no Substance* added that "ill mull In taste or odor that
    would prevent  the  <.•'*  of the water  for  industrial processing.
(I)  Te«lc Substaneel   .here shall be no substances added to the water* that may produce to«ie
    Condition! that v-11  adversely affect th- water for industrial processing.
|J1  Other Pollutants - Other pollutants shall not be added to the waters in quantities that  nay
    adversely affect the water for industrial processing.

Hah and Aquatic Lif«
(a) Dissolved Oxygen - The dissolved oxygen shall be • mi'nlmum mf 5.0 mg/1 except  In  limited
    sections of slrea«s  where, (i). present  technology cannot restore the water quality to the;
    desired «ininu« of 5.0 e.j/1  dissolved oiyoen, (:i) the cost of Meting th« standards is
    ccononically prohibitive «hen compared  with  the e« pee ted benefits to be obtained, or
    (III) the natural  qualities of tht water  are less t«,n the desir«tl «ini^. of  5.0 »9/l
    dissolved o«ygen.   Swch exceptions shall  b«  determined on a«  individual basis  but in no
    Instance shall  the dissolved o.ygen concentration be lets th»n 3.0 «9'1.   Th«  dissolved
    exyo.en concentration shall be measured at -id-depth  in waters h.vii-i . total depth of
    Un (10) feet  or less  and at  a depth of five (SI  feet  in water,  havino, •  total depth of
    greater  than  ten  (13)  feet.   The dissolved oiyoen concentration  of recooflited  trout
    •trttns  shall  not be less than 6.0 *g'l.
(b) pH .  The pH value shall lie within  the ranae of 6.5 to 8.5  and shall not  fluctuate -ore
    than J.O unit  In  this  range over •  period of 24 hour*.
(e) Solids,  Floating Materials  and Deposits - There shall  be no distinctly visible solids.
    seu». foa*. oily «leek, or  the  formation of aliaes.  botto*  deposits  or slwdge  banks  of
    such size  or  character that xay  be  detrimental  to fiah end  aoxatie life.
(d) Turbidity  or  Color - There  shall be no turbidity or color added in such amounts  or  of
    Such character that will  naterially affect fisn and aquatic life.
(e) Temperature -  The naxinu* water  temperature change shall not exceed 3C° relative to an
    vpslrea* control  point.   The  temperature of the water shell not eieeed 30.5°C and the
    •ax!*u« rate  of change shall  not exceed X' per hour.  The temperature of recogniied
    trout waters  shall  not exceed JO°C.  There shall be no abnormal le-perature changes that
    •ay affect aquatic  life unless  caused  by natural conditions.  The temperature of impound-
    mjeflls where stratification  occurs  will be measured mt a depth of 5 feet,  or aid*depth
    whichever  Is  less,  and the  te»xrature in flowing streams shall be measured at aid-depth,
 (f) Taste and Odor -  There shall  be no substances added that will impart unpalatable flavor
    to fish or result in  noticeable offensive odora in the vicinity of the water  or  otherwise
     Interfere  with fish or aquatic  life.
 (g) Toxic Substances  .  There  shall  be  no substances added to the waters that  will produce
     toxic conditions  that affect fish or aquatic life.
 (h) Other Pollutants  -  Other  pollutants shall not be added to the waters  that will  be
     detrimental to f!sh or aquatic  life.
 (H 
-------
 4.  fieer«ttlen
     (•) Dissolved 0*ygen - There shall always be sufficient dissolved e«ygen present to prevent
        •dors of decomposition end ether offensive conditions.
     (b] pH - The pH value shall lie within the range of 6.0 to 9.0 end shall not fluctuate «ore
        then 1.0 uo«t In this range ever a period of i4 hour«.
     (o) Solids, Roiling Material! and Deposit* . Tr>er« shall  b« no distinctly visible solids,
        •cum, foam, oily sleek, or the formation of slime.,  cotton deposits or sludge banks of
        •ueh (tie or character that may be detrimental  to recreation.
     (d) Turbidity or Color - There shall be no turbidity or color »dded in tueh amounts or
        «haraeler that will result in an objectionable  appearance to the water.
     {•) Temperature - *h< •»«'•«"" water temperature change shil]  not exceed X  relative to
        an upstream control point.  The te«-p«r»ture of  the water shall not oceed 30.5°C and
        iht cailnun rate of change shall not c«ceed 2C   per hour.  The temperature of impound-
        menls where stratification occurs will  be Matured at % depth of 5 feet,  or mid-depth
        whichever Is less, and the teaper.lure  in flowing strewn shall  be measured at mid-depth.
     |fl «|UMi!il«3i««l Colifor. - The concentration of the fec.l col if or. group shall not e»-
        ceetf 300 per 100 ml. a* the logarithmic mean based co • minimum  of 10 samples collected
        froa a given sampling cite over s period of not more than S3 consecutive days with In.
        dividual samples being collected at intervals of not less than 12 hours.   In addition,
        the concentration of the fecal eolifor* group in any Individual  sample shall not e«eeed
        1.000 per 100 ml.  Water areas in the vicinity  of d
-------
             (.)  Har*...* „ Mineral Co-pou-a, - TMr. .hall  t* *, a^to-c., .,«.< „ Mt.r lh.t  „,„

                          1 r""1 lc 7* '" •""* ••  u  !— ip iu — **• "»""**  -'«•'"• —
                          orin, «.t.r,.a. and t*oo,it, -  T*,r. .h.M W ^ di.tinctl, vilibl. ,oli(to
                           aleck. or tht for-ation .f .li..,, t,Uo. ^^ „.  (                   '
                or character *l to interfere with  liveitock nttrinf «nd «il«flif«
                Te-pyr.tor. . Th. t«««tur. ,t ti»  «t.r ,h,ll o.t  u,  „,„„ ...'
                M le Inltrfere with it» o*«  for li.cttoeli vttcring «vd  wilifllf*.
            (f) To«!c Sutst.nco - Ther. »*..]] be no lvb*t»ncc> idd»d «e «ter Ih.t ,!J1 pro4«« to.le
                       >n   h«*  .111 iffect l«« »lt«r for  }<
                                                                                      ,
            («)  Othtr PolJUt»"U - Other poIIuUnts »"UI  not tx .««d t.-th, w,Ur In quwtili*»  ^sleh „,
                t* AtrlMntd  to ft« viler for livuUck  vatcring »nd »il
        7.  K

            (t) 0!»»«l«ii 0»«t« - Th«r« |K,11  tlvira I* ioffiettnt dittelnd o.yjet. ^»tnt |» pr««nt odor.
               of o^eotposllion and other  effrosiv* condition!.
            (bj Kir*»ei» or Mineral Cenptunets - Th«r* thtll be no »u»«t*ne«« iddett U the »»t»r that will In.
               erc*l« t>>* *Infrr»l content  to (ueh a* »tent u 10 i«p*ir It* v»* for navigation.
            foj S»Itd»,  Hoitin^ Material*  and Cepoiitj - llwni ah»JJ b« no (flatinetly viifbl*  falFds,  teumi
               fM«,  oUr alttk,  or  th* foreation cf tlioea,  botto» deposit* or tludg* bank* of such ,(,.
               or ektf»et«r U t» interf«r« «ith nawi^atron.
           (4)  T«*per*t«r* - Tfte  tenperaWr* e-f the v»t*r  thaJI not b« rai»«d or le«*r«d to aueh an extent
               •» t« Interfere with  !t» i»»« ''or navisation purposes.
           (•) To*Ie Sut»t»vc« . Th«i I »hall  be no lutntanctt a**n» t« «t«r th»t .111 produce lo«fe cww
              oHtloni that xlll affect the *ater for navigation.
           Cfl Other Pollutar-j - Other pollutants «htll «t be add** to tho «t«r I« «mntltla» ««ifeh  **y
              bo 4alriMfltal i« th< vattr* u<«d  for navigation.
These criteria thouU not d« construed as per«lttJP9 the de9ra<*at(«n of Moh«r oyality wter  when weh can
»• prtventtd b/ reuoniblt pollution control oeaiuru.   The above eonditioni art recognirid a» applying to
wtere affected by the diwharga  of  *ewt»e and/or indj*lri«l vwte or other wait, and  not rewriting fro.
tutor*!
      J.  Conventional Water Treatment - Conventional «ler tntaUent a»  referred to In th» erlierfi denote*
         «o*9u}at)a>\  atiiwnlation,  filtration and ehlorinatlon.
      Ji,  Klxfoo Zone - *;*<•* »*» refer*  to U.i »eetfon orflo-ing ttrea* or l«p*uftd.d «at«r» n«e*t**ry
         for tttlvtoli to beee«e rf;*p«r,ed.  T>« «!«J»a ion. Meeasw? !n «*eh P.rtfc«:»r 
-------
      8,  In general, deviations fro* nor«al water condition  «ey be undesirable, but tho nt«  and extent
          •f the deviation! should be considered In Inleroreting  the above criteria.
      C.  The criteria and standards provide that all  discharges  of se»age. Industrial waste, and  other
          •rule* vlll receive the best practicable treatment (secondary or the equivalent) or central
          according to the policy and procedure of the Tennessee  Water Quality Control Board,   A degree
          of trea'tMent greater than secondary when necessary to protect the- water uses will be  required
          for (elected ac.jge and waste discharges.

TCWtSSCE ANTIDECRaDATION  ST*TtM£NT
      1.  Tn* Standards and Plan adopted are designed  to  provide  for the protection of existing water
          quality and/or the upgrading or "enhancement* of water  quality In all waters within Tennessee.
          It I* recognlied that  tome waters  nay have eiistlng  ability better than established standards.
      2.  The Criteria and Standards shell not  be construed  as permitting the degradation of these
          Klgner quality waters  when such can be prevented by  reasonable pollution control measures.
          In this regard,  existing high quality witer  will be •aintained unless and until It is affirma-
          tively denonstrited to the Tennessee  Water Quality Control Board that i change Is justifiable
          as t  result of necessary social  and eeononic development.

      9.   til  dlschtrges of sewage,  industrial  waste, or other waste shall  receive the best practicable
          treatment  (secondary of  the equivalent) or control according  to the  policy «nd procedure of
          the Tennessee Viler Ouality Control Board.  * degree of treaUent oreater than secondary when
          necessary  to protect the  water uses will be required for selected sewaoe and waste  discharges.
      4.   In Implementing  the provisions of  the  above as they relate to Interatste atreans.  the  Tennessee
          Viler Quality Control  Board will cooperate with the appropriate Federal  Agency in order to
          ssslst In carrying out responsibilities under the Federal  Water Pollution Control Act. as amended.
                                             B-6

-------
            APPENDIX C
FEDERAL WATER POLLUTION CONTROL
       DISCHARGE STANDARDS

-------
                           APPENDIX C
     The goals of the Federal Water Quality Control Act Amendments
of 1972 (the Act) require that publicly-owned treatment works
utilizing treatment and discharge meet secondary treatment as
defined by the Environmental Protection Agency by July 1, 1977,  or
June 1, 1978 (for new construction).  The secondary treatment
standards were given in ^38 CFR 159 (August 17, 1973)  and are shown
in Table C-l below.
                            TABLE C-l
                  SECONDARY TREATMENT STANDARDS
Parameter
BOD5 (mg/D*
SS (mg/D*
Fecal Colifonn**
(No./lOO ml)
pH
30 Consecutive Days
30
30
200
6-9
7 Consecutive Days
45
45
400
6-9
  *  Arithmetic Mean
 **  Geometric  Mean
                              C-l

-------
      APPENDIX D
SOLID WASTE REGULATIONS
  STATE OF TENNESSEE

-------
                           APPENDIX E>

                     SOLID WASTE REGULATIONS


REGULATION 1.  DEFINITIONS

     A.   Bulky Waste - Large items of  refuse such as  but  not
         limited to appliances,  furniture,  auto or large  auto
         parts,  trees and branches, and  stumps.

    B.  Composting  - The controlled biological decomposition of
        solid organic waste material under aerobic conditions,
        which shall produce an end product free of pathogenic
        organisms,

    C.   Commissioner - The Commissioner  of the Tennessee  Depart-
        ment of  Public Health or his authorized representative.

    D.   Department - The  Tennessee Department  of  Public Health.

    E.   Garbage  - All kitchen and table waste, and  every accumula-
        tion of  animal or vegetable waste that attends or results
        from the preparation, dealing on or handling of food stuffs,

   F.  Hazardous Waste - Includes,  but is not necessarily limited
       to, explosives,  pathological wastes,  radioactive materials,
       and certain chemicals  which  shall  be  determined by the
      Department.

  G.  Health  Officer - The director of a city, county, or
      district  health department having jurisdiction over the
      community health in a specific area, or his authorized
      representative.

  H.  Incinerator - A solid waste burning device which provides
      acceptable controlled combustion resulting in a nuisance m
      free residue composed of little  or no combustible or
      organic material.

 I.  Industrial Waste -  All  solid wastes which result from
     industrial processes and manufacturing operations.

 J.  Open Burning - The burning of any matter under such con-
     ditions  that the products of combustion are emitted
     directly into the open atmosphere.

 K.   Open Dumping  - The depositing of  solid  wastes into a body
     or  stream of  water  or onto  the surface  of the ground
                            D-l

-------
    without compacting the wastes and covering with suitable
    material to a depth and at such time intervals as pre-
    scribed in these regulations.

L.  Person - Any and all persons, natural or artificial,
    including any individual, firm or association, and
    municipal or private corporation organized or existing
    under the laws of this State or any other state, and any
    governmental agency or county of this State.

M.  Refuse - Putrescible and nonputrescible solid wastes
    except body wastes, including, but not limited to, garbage,
    animal carcasses, rubbish, incinerator residue, street
    cleanings, and industrial waste.

N.  Rubbish - Nonputrescible solid wastes, consisting of both
    combustible and noncombustible wastes, such as, but not
    necessarily limited to, paper, cardboard, tin cans, yard
    clippings, wood, glass, bedding, crockery, plastics,
    rubber by-products, or litter of any kind.

0.  Solid Waste - Garbage, refuse, and other discarded solid
    materials, including solid-waste materials resulting from
    industrial, commercial, and agricultural operations, and
    from community activities, but does not include solids or
    dissolved material in domestic sewage or other significant
    pollutants in water resources, such as silt, dissolved or
    suspended solids in industrial waste water affluents,
    dissolved materials in irrigation return flows or other
    common water pollutants.

P.  Solid Waste Disposal System - The relationship of the
    coordinated activities of and resources for processing and
    disposal of solid wastes within a common geographical area
    and under the supervision of any person or persons engag-
    ing in such activities.

Q.  Solid Waste Processing - An operation for the purpose of
    modifying the characteristics or properties of solid
    wastes to facilitate transportation or disposal of  solid
    wastes including, but not necessarily limited to, incinera-
    tion,  composting,  separation, grinding, shredding,  and
    volume reduction.

R.  Solid  Waste Disposal - The process of placing, confining,
    compacting,  or  covering  solid waste except when such  solid
    waste  is  for  reuse, removal,  reclamation, or  salvage.
                            D-2

-------
       S.
T.
           Transfer Station - An approved place for consolidation or
           temporary storage of solid waste prior to transportation
           to a processing operation or the final disposal site.
          Household - Those who dwell under
          pose  a  family.
                                                 ^-me roof  and  com-
  REGULATION  2.   REGISTRATION OF DISPOSAL  OR PROCESSING OPERATION
      A.
           Registration Required - No person,  except as herein
           specified, shall operate or maintain a solid waste pro-
           cessing  facility or disposal facility or site within the
           State of Tennessee without making application for and
           receiving acknowledgement from the Commissioner.  It is
           the intent of this section to exempt from registration
           the individual householder disposing of solid waste from
           his own household upon his own land providing this does
           not create a public nuisance.
      Q •
      C.
          Change of Ownership - In the event of an intended  change
                                  waste processing facility  or a
          by the proposed new owner at
          to the proposed change, of ownership.
                                       '
                                SPIRAL.  STATE.  OH OTHER
                       to "«£ Mission to the granting agency.
are submtte  fro.
off JUially adopted a plan for
are included in
                                                               ""0
                                               ^ ^   ,„„
                                         .«* jurisdictions.
                                                  ln acco
with these regulations
                                D-3

-------
REGULATION 5.   SOLID  WASTE  DISPOSAL  SYSTEM DESIGN AND CONSTRUCTION

     ** •   • • •

     B.   Processing Facilities  -  Incinerator  (1,000  Ibs/hr capacity
         or greater),  composting  plants,  transfer stations,
         hazardous waste  processing  and other  processing methods.

         1.  Incinerators - Processing facility design and con-
             struction shall  be such as to produce a facility
             which will preserve  the prescribed quality of the
             environment  and  provide the  maintenance of good
             health and safety  of the operators.  This regulation
             shall also require compliance with other applicable
             Tennessee environmental control regulations.  Plans
             and  specifications shall be  prepared by an engineer
             licensed  to  practice in Tennessee and shall contain
             the  following:

             a.   A master plan  for the area lying within a one
                 mile  radius  of the  site.   This plan shall be
                 drawn at a scale of not  less  than 1 in. = 400 ft.
                 It shall indicate existing roads, bridges,
                 streams, rail  facilities,  water impoundments,
                 land  use,  zoning, topography  - 20 ft contour
                 interval,  water  and waste water treatment
                 facilities,  water supply  sources, and other
                 utilities  adjacent  to or  located on the site.
                 It shall show  the proposed site, location of pro-
                 posed access roads,,and major drainage routing.

            b.   A site plan  for  the area  lying within the desig-
                 nated site boundaries.  This plan shall be drawn
                 on a  scale of  not less than 1 in. = 100 ft.  On
                 this  plan  shall  be  noted  site boundaries, topography
                 - 5 ft contour intervals,  on-site structure, access
                 roads, drainage  appurtenances, sanitary facilities,
                 utilities, water supply,  waste water collection and
                 treatment  facilities, and any other facilities
                 utilized in waste processing.

             c.   A set of drawings and specifications for equipment
                 and buildings  shall  be included.

            d.   Such  other drawings  and details as  may be required
                 by the Department.
                                D-4

-------
   e.  Traffic control information in the area of the
       processing facility must be evaluated.   Such
       evaluation shall be reflected in a letter from
       the controlling traffic authority indicating
       that the operation of a processing facility at
       the proposed site will be acceptable.   A map of
       the proposed route to and from the designated
       disposal site shall be submitted to the Depart-
       ment.

   f.  A manual containing operational procedures must
       be submitted to the Department.  This manual
       must include but not necessarily limit to:
       operating hours, personnel duties, odor and
       vector control, waste processing sequence, fire
       and accident prevention, site and equipment
       maintenance, and any other operations necessary
       for the maintenance of an approved system.

   g.  Operation and/or construction plans shall indicate
       an acceptable method of handling solid waste  in
       the event of a  failure in the primary processing
       facility.

   h.  A proposal  shall be submitted for  the disposal
       or use of processed waste.

2. Composting Plants  - Plans  and  specifications  shall be
   prepared  by an  engineer  licensed to practice  in
   Tennessee and shall contain the  following:

    a.  A master plan  for  the area lying within a one mile
        radius of  the  site.   This  plan shall be drawn at  a
        scale of not less  than 1 in. = 400 ft.   It shall
        indicate existing  roads, bridges, streams,  rail
        facilities, water  impoundments, land use, zoning,
        topography  - 20 ft contour interval,  water and
        waste water treatment facilities, water supply
        sources, and other utilities adjacent to or
        located on the site.  It shall show the proposed
        site, location of  proposed access roads, and major
        drainage routing.

    b.  Construction plans and specifications in
        sufficient detail to indicate the actual construction
        required.

     c.  Plans for use of the composted material.
                         D-5

-------
        d.   Such other drawings and details as may be
            required by  the Department.

        Compost plant design  and  construction shall be such
        as  to  produce a  facility  which will preserve the
        prescribed  quality of  the environment and provide
        for the maintenance of good health and safety of the
        operators.
    3.
    4.   Hazardous Waste Processing Other Processing Methods -
        Plans  and specifications  shall be prepared by an
        engineer licensed  to  practice in Tennessee and shall
        contain  the  following:

        a.  A  master plan  for the area lying within a one mile
           radius of the  site.   This plan  shall be drawn at a
           scale of not less than 1 in. =  400 ft.  It shall
           indicate existing roads, bridges, streams, rail
           facilities, water impoundments, land use, zoning,
           topography - 20 ft contour interval, water and
           waste water treatment facilities, water supply
           sources, and other utilities adjacent to or
           located  on the site.  It shall  show the proposed
           site, location of proposed access roads, and major
           drainage routing.

        b.  Construction plans and specifications in sufficient
           detail  to indicate the actual construction required.

        c.  Such other drawings  and details as may be required
           by the Department.

        Hazardous waste processing and other processing methods
        shall  be such as to preserve the prescribed quality of
        the environment and provide for the maintenance of good
        health and  safety  of  the operators.

C.  Disposal Facility or Site

    1«   «•«

    2.   Sanitary Landfill  - Basic design  considerations:

        a.   Site selection -  No  site shall  be subject  to
            flooding. Geologic  conditions  shall be such as
            not to  permit  pollution of  the  ground water.
                            D-6

-------
       Sufficient soil cover or other material  approved
       by the Department shall  be  available, preferably
       at the site,  for covering the waste  at the
       required  intervals and to the required depth.
       The  site  must  comply  with local zoning require-
       ments  and land  use planning.

      Access Roads - All-weather roads shall be pro-
      vided  to  the disposal  site and shall be of such
      design and construction as to safely accommodate
      the traffic using  the site.   On-site roads shall
      be all-weather or, in lieu thereof, wet-weather
      disposal areas shall be provided.

      Site  Drainage  - All surface  water  shall be
      diverted around the operations area.   Water  shall
      not be  allowed  to accumulate at any location on
      the site unless  such location has been approved
      by  the  Department.

      Site Fencing - Access  to  the  site shall be con-
      trolled by means  of gates which may be locked
      and by  fencing if such become necessary.  All
      fencing and gates shall be of sufficient height
      and strength to serve the purpose intended.
   SOLID WASTE DISPOSAL SYSTEM OPERATION
A   General - The operation and maintenance of all solid
    waste disposal systems shall be such as not to endanger
    the public health or safety, not to adversely affect the
    quality of the environment and to provide for the proper
    processing and disposal of solid waste.

B.   Processing Facility

    1.  Incinerators - Incinerator operation shall be  such
        that the requirements of the Tennessee  Air Pollution
        and  local control regulations are met.

            Access  to Site -  Access to the incinerator shall
            be  limited to the hours in which authorized
            operating personnel  are on duty at  the site.
a
u   cff* Sforaee - All solid waste disposed of  at  the
"'    " "a  8be confined to the designated during
    are!.  Storage of the waste at the site shall  be
    kept to a minimum.
                   D-7

-------
    c.  Supervision of Operation - An incinerator shall
       be operated under the supervision of a responsible
       individual who is thoroughly familiar with the
       operating procedures established by the designer.

    d.  Incinerator Residue - An incinerator shall be so
       operated that  the residue produced will contain
       little or no combustible or organic material.
       All  incinerator  residue shall be disposed of in
       a sanitary manner.

2.   Composting Plants

    a.  Access to  Site - Access to  the  composting plant
        shall be limited to  the hours in which authorized
        operating  personnel  are on  duty at  the site.

    b.   Site Storage - All  solid waste  disposed  of  at  the
        site shall be confined to  the designated dumping
        area.  Storage of  the waste at  the  site  shall  be
        kept to a minimum.

    c.  Supervision of Operation - A composting  plant
        shall be operated under the supervision  of a
        responsible individual who is thoroughly familiar
        with  the operating procedures established by the
        designer.

    d.  Nongradable Solid Waste - Solid waste which is not
        degradable by compost methods and is a resulting
        by-product of a composting plant shall be
        disposed of in  a sanitary manner.

    e.  Use of Composted Solid Waste - Composted solid
        waste offered for use by the general public shall
         contain no pathogenic organisms, shall be innoc-
         uous, shall be  nuisance free,  and  shall not
         endanger  the  public health or  safety.

 3   Transfer Stations,  Hazardous Waste Processing Plants,
    and  Other Processing Methods - Operation of transfer
     stations, hazardous waste processing plants,  or other
     processing methods shall be such that  the intended
     function of the facility will  be best  served,  that
     the public health and  safety will  not  be endangered,
     and that nuisances will not be created.  Specific
     operating procedures  for each installation  shall  be
     approved by the Department prior  to initiation of
     operation.
                         D-8

-------
       C.   Disposal  Facilities  and  Sites

           1.   Sanitary Landfill
                  Handling of Special Wastes - Dead animals, sewage
                  solids or liquids, and other materials which are
                  either hazardous or hard to manage shall be
                  disposed of in a sanitary landfill only if
                  special provisions aie made for such disposal and
                  are approved by the Department.
                  Drainage and Grading - The entire site  shall  be
                  graded and/or provided with drainage  facilities
                  to minimize run-off  onto the sanitary landfill,
                  to prevent  the erosion of earth  cover,  and  to
                  drain rain  water  falling on the  surface of  the
                  sanitary landfill.   The final surface of the
                  sanitary landfill shall be graded  to  drain, but
                  no surface  slope  shall be so  steep as to cause
                  erosion of  the cover.   The surface drainage
                  shall be consistent  with the  surrounding area
                  and shall in no way  adversely affect proper
                  drainage from these  adjacent  lands.
             FOR  avPEOVAL OF A "SPECIAL" SOLID WASTE
by the Department.

     A thorough understanding of the nature of a -Jjcj-j ^J"
be gained to insure that the waste can £• *£"£ £ thj well  being
sit! without posing a threat to public health  or        ^ whafc
                                D-9

-------
     1.  Physical Characteristics

         a.  color

         b.  texture

         c.  density

         d.  viscosity

     2.  Chemical Characteristics

         a.  A complete chemical analysis

     3.  Generation Source

         a.  Schematic flow diagram of the manufacturing process
             which creates the waste stream

                       or

         b.  Schematic flow diagram of waste treatment  facilities
             if special waste is resultant from waste treatment.

     4.  Quantity

         a.  Amount taken to processing or disposal  facility per
             trip (Ibs or yds).

         b.  Number of trips in a stated amount of time.

     5.  Location, ovner, and registration number of the site at
         which processing or disposal will occur.

     This information should be sent to Mr. Jerry Loftin, Suite 320,
Capitol Hill Building, Nashville, Tennessee 37219.


                                     "US. GOVERNMENT PRINTING OFFICE: 1WJ-210»10:7»
                                 D-10

-------