EPA-R2-72-038
September 1972                Environmental  Protection Technology
 Development of the Catalytic

 Chamber Process,  Final Report
                                 Office of Research and Monitoring
                                 U.S. Environmental Protection Agency
                                 Washington, D.C. 20460

-------
                                      EPA-R2-72-038
 Development of the
 Catalytic  Chamber  Process,
 Final  Report
                 By
        A.  Gruber and A. Walitt

        Tyco Laboratories, Inc.
          Bear Hill, Waltham,
         Massachusetts  02154
        Contract No. 68-02-0008
         Program Element 1A2013
     Project Officer: Stanley J. Bunas
        Control Systems Division
  National Environmental Research Center
Research Triangle Park, North Carolina  27711
              Prepared for
      OFFICE OF RESEARCH AND MONITORING
    U.S.  ENVIRONMENTAL PROTECTION AGENCY
           WASHINGTON, D.C.  20460
              September 1972

-------
               EPA REVIEW NOTICE

This report has been reviewed by the Environmental
Protection Agency and approved for publication.
Approval does not signify that the contents necessarily
reflect the views and policies of the Agency, nor does
mention of trade names or commercial products constitute
endorsement or recommendation for use.
                      11

-------
                                        ABSTRACT
       The goal of this contract was to continue the development of the Tyco Catalytic
Chamber Process for the simultaneous removal of SO0 and NO  from power plant flue gas.
                                                  &       X
As originally conceived,  the process involved the gas phase oxidation of SO0 with NO9 followed
                                                                       Lt        Lt
by the high temperature absorption of the nitrogen oxides in sulfuric acid.  The dissolved oxides
of nitrogen were recovered and oxidized in a catalytic stripper.  The process produced nitric
and sulfuric acids.
       The results of the program conducted in a 10-SCFM miniplant were:
              1. The SO» gas phase oxidation by NO0 was found to proceed too slowly to permit
the use of practical-sized equipment. However, by contacting the flue gas  with 2 wt % nitro-
sylsulfuric acid in 70% sulfuric acid in a packed bed reactor,  90% removal of SCL could be
accomplished at 225 °F in less than 15 sec.
              2. Absorption of equimolar quantities of NO and N02 was not found to be
controlled by a conventional absorption mechanism, but is probably dependent on a gas phase
interaction of die two oxides. As a result,  the large equipment needed to provide long residence
times makes the process appear relatively expensive for removing SO, and NO  together or
NO  alone.
   x
                                             111

-------
                                   Table of Contents

Section                                                                     Page No.
   I.     SUMMARY [[[       j
   II.     INTRODUCTION [[[       9
         A.  Content of This Report ..........................................       <-,
         B.  Initial Process Concept ..........................................       ,,
         C.  Prior Work
         D.  Contract Goals
                                                                                 < ,
   III.    ENGINEERING SUBCONTRACTOR - THE BADGER
         CORPORATION [[[      13
         A.  Engineering Consultation ........................................      ^3
         B.  Optimization Program ...........................................      j3
         C.  Pilot Plant Design ...............................................      j 3
   IV.    MINIPLANT MODIFICATION AND EQUIPMENT ........................      15
         A.  Existing Equipment .............................................      15
         B.  SO? Oxidation Reactor ...........................................      15
         C.  Scrubber Columns ..............................................      15
         D.  Stripper Columns ...............................................      17
         E.  Liquid Pumps [[[      21
         F.  Gas Pumps [[[      21
         G.  Instrumentation .................................................      22
         H.  Gas Feed [[[      22
         I.  Miniplant Operation .............................................      24
   V.     REACTOR EXPERIMENTS ..........................................      25
         A.  Background [[[      25
         B.  Reactor Experiments:  Effect of UV Radiation ......................      25
         C.  Miniplant Tests:  Effect of Temperature on SO,,
             Oxidation Rate ..................................................      27
         D.  Effect of Acid Irrigation on SO» Oxidation Rate .....................      27
         E.  Instrumentation Considerations ...................................      35

-------
Table of Contents (Cont)

Section                                                                 page NO-
          C.  Initial Experimentation - Parametric Study	      64
          D.  Mathematical Analysis of Experimental Scrubber Data	      67
          E.  Analysis of Scrubber/Stripper Data	      74
   VII.    STRIPPER EVALUATION	      81
          A.  Initial Concept	      81
          B.  Laboratory Scale Stripper Tests	      81
          C.  Miniplant Experimentation	      82
          D.  Analysis of Stripper Mechanism	      83
   VIII.    PROCESS CONTROL	      85
          A.  Goals	      85
          B.  Power Plant Operating Conditions	      85
          C.  Instrumentation Requirements	      87
          D.  Process  Control Requirements	      91
   IX.     ECONOMIC  EVALUATION	      95
         A.  Prior Evaluations	      95
          B.  New Process Concept	      95
          C.  Cost of NO  Removal Only	     101
                     X
   X.     CONCLUSIONS AND RECOMMENDATIONS	     113
         A.  Conclusions	     113
         B.  Recommendations	     114
   XI.    ACKNOWLEDGMENTS	     117
   XII.    REFERENCES	     119

Appendices
   I.     PRELIMINARY ENGINEERING ANALYSIS OF THE TYCO
         CATALYTIC CHAMBER PROCESS BY BADGER CORPORATION	     I-1
   II.     MINIPLANT OPERATION	     II-l
   III.    DATA FROM MINIPLANT REACTOR EXPERIMENTATION	     Ill-1
   IV.    DATA FROM SCRUBBER/STRIPPER EXPERIMENTS	     IV-1
   V.    METAL ION INTERFERENCE IN SCRUBBER AND
         STRIPPER OPERATION	     V-l
                                        VI

-------
Table of Contents (Cont.)








Appendices                                                               Page No.






    VI.    CORROSION IN MINIPLANT EQUIPMENT	    VI-1



    VII.   MATHEMATICAL ANALYSIS OF SCRUBBER/STRIPPER DATA	   VII-1



    VIII.   LABORATORY STRIPPER TESTS	   VIII-1



    IX.    INSTRUMENTATION CALIBRATION	    IX-1



    X.     OXIDATION OF NO TO NO2 FOR MINIPLANT GAS FEED	    X-1
                                        vii

-------
                                    List of Illustrations


Figure No.                                                                       Page No.

   1.          Catalytic chamber process	       3

   2.          Schematic flowsheet of miniplant	      16

   3.          Sketch of 19-ft scrubber	      18

   4.          Miniplant stripper column and catalyst bed support structure	      19

   5.          Stripper column using glass pipe	      20

   6.          Modified miniplant layout	      23

   7.          Miniplant reactor experiments — SO2 oxidation. Effect of
              water vapor in flue gas, residence time,  and temperature	      29

   8.          Configuration of miniplant reactor during initial experimentation
              involving liquid irrigation	      31

   9.          Miniplant reactor experiments — SC^ oxidation. Effect of reactor
              irrigation with 80% H2SO4	      32

   10.         Miniplant reactor experiment — SO2 oxidation.  Effect of acid or
              water irrigation in packed reactor	      33

   11.         Miniplant reactor experiment — SC>2 oxidation.  Comparison of acid
              irrigation,  wetted wall tests,  and no irrigation	      34

   12.         Miniplant reactor experiments - SC>2 oxidation. Comparison of
              wetted-packing reactions with and without additional unpacked
              residence volume	      36

   13.         Miniplant reactor experiment - SO2 oxidation.  Evaluation of low
              O2 level in flue gas	      37

   14.         NOg interference  calibration curve	      39

   15.         Miniplant reactor experiment - SO2 oxidation.  Tracing of
              instrumentation recorder input	     40

   16.         Miniplant reactor experiment - S02 oxidation.  Tracing of
              instrumentation recorder output	      41

   17.         Miniplant reactor experiment - SO£ oxidation.  Comparison of
              acid and nitrose irrigation	      43

   18.         Miniplant reactor experiment.  Effect of HNSO5 concentration
              on SO, removal yield	      45

   19.         Miniplant reactor experiment.  Effect of HNSO- concentration
              on SO2 removal yield	      46

   20.         Miniplant reactor experiment.  Effect of HNSO9 concentration
              on SO2 removal yield	      47



                                             ix

-------
List of Illustrations (Cont.)


Figure No.                                                                      Page No.

  21.        Miniplant reactor experiment. Effect of H2SO4 concentration
             on SO2 removal yield	       48

  22.        Miniplant reactor experiment. Effect of residence time on
             SO2 removal yield	       49

  23.        Interpretation of miniplant reactor experimentation.  Tradeoff
             between HNS02 concentration and irrigation flow rate in achieving
             a specific SO- reaction yield	       50

  24.        Miniplant reactor experiments. Effect of irrigation and
             residence time on SO- removal yield	       51

  25.        Miniplant reactor experiments. Effect of countercurrent versus
             cocurrent reactor configurations  	       53

  26.        Scrubber/stripper parametric study and data sheet	       65

  27.        Series stripper configuration	       69

  28.        First order reaction rate constant KI as a function of NO
             inlet concentration.   Data from Tyco and EPA	*	       76

  29.        Second order reaction rate constant K2 as a function of NOX
             inlet concentration.   Data from Tyco and EPA	       77

  30.        Standard deviation for first order rate constant values,
             85% confidence limits	       78

  31.        Standard deviations  for second order rate constant values	       79

  32.        Graph of power plant operating parameters	       88

  33.        Major process control requirements	       92

  34.        Flowsheet showing the Tyco catalytic chamber process used
             for NO  removal only	       96
                   X
  35.        Proposed flowsheet for catalytic chamber process utilizing
             a wetted reactor for SO, oxidation	      100

  36.        Extrapolation of data from Run 92 to give scrubber column height
             for reducing NOx concentration from 6000 ppm to 100 ppm	      102

  37.        Extrapolation of data from Runs 85c, 86c, 92c, 93,  and  96c to give
             scrubber column height for reducing NOX concentration from
             2000 ppm to 100 ppm	      107

  38.        Catalytic chamber process using a low temperature scrubber	      115

-------
                                      List of Tables


Table No.                                                                     Page No.

    I.         Initial Reactor Studies	      26

    II.        Gas Phase SC>2 Oxidation with NO2 in the
              Presence of UV Radiation	      28

    III.       Degree of Conversion of SC>2 at 150 °C in 80% Sulfuric
              Acid for Various Residence Times with Diffusion of
              SC>2 Being the Rate Limiting Step	      60

    IV.       Degree of Conversion of S02 at 150 °C in 80% Sulfuric
              Acid for Various Residence Time with Rate of Conversion
              Equal to 1/10 of the Diffusion Limited Rate	      61

    V.        Degree of Conversion of SOr, at 150 °C in 80% Sulfuric
              Acid at Various  Residence Times Using Modifying
              Assumptions Presented in Text	      61

    VI.       Parametric  Study and Supplemental Work Plan	      68

    VII.       CC-2 Analysis of Laboratory Stripper Tests	      84

    VIII.      Economics of NOX Scrubbing Plant for 500-MW Power
              Plant Based  on Tyco SO, Removal Process	      97

    IX.       Economics of NOX Scrubbing Plant for 500-MW Power
              Plant Based  on Tyco S02 Removal Process	      98

    X.        Economics of NOX Scrubbing Plant for 500-MW Power
              Plant Based  on Tyco SO2 Removal Process	      99

    XI.       Economics of SO2/NO2 Scrubbing Plant for 800-MW
              Power Plant	      103

    XII.       Economics of SO2/NOX Scrubbing Plant for 800-MW
              Power Plant	      104

    XIII.      Economics of S02/NOX Scrubbing Plant for 800-MW
              Power Plant	      105

    XIV.      Economics of SO2/NOX Scrubbing Plant for 800-MW
              Power Plant	      106

    XV.       Economics of NOX Scrubbing Plant for 800-MW Power Plant	      108

    XVI.      Economics of NO  Scrubbing Plant for 800-MW Power Plant	      109
                             X

    XVII.     Economics of NO  Scrubbing Plant for 800-MW Power Plant	      110
                             X

    XVIII.    Economics of NO  Scrubbing Plant for 800-MW Power Plant	      Ill
                             X
                                            XI

-------
 I. SUMMARY
         During the four and one-half year period between October 1967 and March 1972, Tyco
 Laboratories, Inc., has been involved in the development of the Catalytic Chamber Process for
 the removal of sulfur dioxide and nitrogen oxides from power plant flue gas.  Under contract to
 the Department of Health, Education and Welfare and the Environmental Protection Agency
 (Contracts PH 86-68-75, CPA 70-59, and 68-02-0008),  Tyco has brought the process from the
 conceptual stage through several major modifications to the pre-pilot stage where a reasonable
 decision could be made on its economic and technological viability.
         The development work on the process was aimed at solving one of the major environ-
 mental problems facing our society: air pollution caused by flue gases from power  stations
 burning fossil fuels. A typical 800 MW, coal-burning power plant produces almost 1.5 million
          2
 standard ft /min of stack gas containing about 0.3% sulfur dioxide and 0.05% nitrogen oxides.
 These pollutants are equivalent to 900 tons and 100 tons of sulfuric and nitric acids  (100% basis),
 respectively, being dumped into the atmosphere daily.  Both species represent a serious
 hazard to man and his  artifacts as well as to plant and animal life in general.  The magnitude
 of the sulfur dioxide problem can be demonstrated by the fact that more sulfuric acid equiva-
 lent is dumped into the atmosphere from individual sources than is used for all commercial
applications (and it should be remembered that sulfuric acid is the largest tonnage chemical
commodity marketed today).
         The need for power plant flue gas cleanup is urgent, but the very magnitude of  the
problem which creates this urgency is its biggest impediment.  Flue gas cleanup involves the
handling of enormous volumes of gas; ducts are typically 15 to 20 ft in diameter. Any process
which would require reaction residence times beyond a few seconds is extremely unattractive
economically because of the very high cost of large gas handling equipment. Other major ob-
stacles to a viable process are the need for heat transfer with the flue gas and the disposal
problem of the recovered pollutant. As will be seen, the original concept of the Catalytic
Chamber Process avoided most of the major technological problems, while giving a relatively
attractive economic outlook.
         The process concept is  based on the century-old Lead Chamber Process for sulfuric
acid manufacture. This obsolete process made use of nitrogen dioxide to oxidize sulfur dioxide
(about 13%) to sulfuric  acid, which was formed  in large lead chambers. The nitric oxide which

-------
was formed during this oxidation was slowly air-oxidized back to nitrogen dioxide to permit
the complete oxidation of sulfur dioxide before the gas left the lead chambers.  The gas was
then scrubbed with cold sulfuric acid to remove  residual sulfuric acid and oxides of nitrogen.
The gas was dumped to the atmosphere while the nitrated acid (nitrose) was recycled to permit
continued use of the nitrogen dioxide oxidant.
         Early experimentation at Tyco indicated that sufficiently rapid oxidation of sulfur
dioxide in power plant flue gas (about 0.3%)  could be achieved to convert the gaseous oxide to
sulfuric acid in short enough residence times to permit the use of practical-sized equipment.
The simultaneous  reoxidation of nitric oxide to nitrogen dioxide  could not be accomplished fast
enough to be economically feasible,  making it clear that the Lead Chamber Process could not
be used directly for dilute gas cleanup. In addition, the cold scrubbing of the wet flue gas
(about 7% water) caused excessive dilution of the recycle scrubbing acid, creating a need for
large amounts of heat to  reconcentrate the acid.  Even more heat was needed to recover the
oxides of nitrogen to permit the recycle of both the gasses and the scrubbing acid.
         These problems were conceptually solved  during subsequent experimentation by the
evolution of the Catalytic Chamber Process. (See Fig. 1.)  In this scheme, the dilute sulfur
dioxide is oxidized to sulfuric acid with an amount of nitrogen dioxide equal to twice the stoi-
chiometric requirement.
          SO2 4 2NO2 - S03 4 NO 4 NO2

Thus,  half the nitrogen dioxide is converted to nitric oxide, resulting in a one to one mole
ratio of nitrogen dioxide  and  nitric oxide which is essential for absorption in sulfuric acid:
          NO -I- N02 4 2H2S04  - 2HNSOg  4 H20

The nitrogen oxide and sulfuric acid in the gas stream are absorbed in a high temperature
scrubber.  The scrubber is maintained at a  temperature such that the vapor pressure of water
over the  effluent acid is equal to the partial pressure of  water in the incoming gas (for 7%
water in  the gas the scrubber temperature would be about 250 °F).  In this manner, the process
avoids the pickup of water from the flue gas and thus avoids the  need for additional heat for
concentrating the acid.
         The effluent nitrose from the scrubber  is fed to a chamber packed  with activated
charcoal. Here the dissolved oxides of nitrogen are oxidized to  nitrogen dioxide, which, being
only very slightly  soluble in sulfuric acid, bubbled  out of the acid ready for recycle.

                                activated
          4HNSO, + 2H0O 4  O0     -      4H9SO, 4 4NO9
                a     £t      &   *      i    &   **.       ft
                                charcoal
This stage was shown experimentally to occur in the 250 to 300  °F temperature range,  again
avoiding  the need for heat.

-------
uas to suit.*.
250 °F
7%


H20 __
150 ppm N0y
300 ppm SO2


















Gas
NO
N02
SO0
2
HN(


Air
NO












REACTOR












Gas
N203
1 ^..^VJij







1




\ i







80% H2S04



HIGH
TEMPER ATURE
SCRUBBER


80% H2S04
HNSOp;
1 w

D«
"



ABSORBER

M


Product
HNOg
Flue gas
SOOT





H O



Air .


Product





^

1
1

7
/
/
/
/
///
Y/,







\



J CATALYTIC
, STRIPPHR
/





3000 ppm SOo H so
6000 ppm NO, 2 4
Fig. 1.  Catalytic chamber process

-------
        This catalytic oxidizer solved two major problems: the reoxidation of the nitric oxide
formed in the sulfur dioxide oxidation stage, and the recovery of the oxides of nitrogen from acid
solution.  This stage was the heart of the process at that stage of development.  In combination
with the high temperature scrubber,  the three shortcomings of  the Lead Chamber Process were
avoided,  thus creating a process which apparently could recover both nitrogen oxides and sul-
fur dioxide without the need for additional process heat.
        The sulfur dioxide was recovered as 80% acid, while the oxides of nitrogen were re-
moved from the off-gas of the catalytic stripper/oxidizer by absorption of nitrogen dioxide in
water to form nitric acid. Preliminary cost estimates  showed great promise  for economic
feasibility of the process through the sale of commercial grade  acids.
        As the contract period covered in this report started, the process as outlined above
had been verified in bench scale experimentation as well as preliminary testing of separate
process stages in a 10 SCFM "miniplant"  (pre-pilot scale).  What remained was the integrated
operation of the total process and the establishment of  engineering criteria for scaleup to pilot
level operation at the 2000 to 5000 SCFM level.
        The goals of Contract 68-02-0008, therefore,  included:
               1.  Modification of the existing 10 SCFM miniplant to permit integrated opera-
tion.
               2.  Experimentation in the integrated miniplant to determine probable design
ranges of critical engineering parameters. A  parametric  study showing the effect of the various
parameters was planned.
               3.  Preliminary design of a 2000 to 5000 SCFM pilot plant.
               4.  Evaluation of control levels of SO,  and NC-  attainable through use of the
                                                 £t        X
Catalytic Chamber Process and comparison with desired levels. Goals were 90% removal of
S00 and 100 ppm of NO .
   £t                   X
               5.  Evaluation of the economic feasibility of the overall process and comparison
with EPA standards. For the double removal process (both S02 and NCy, the economic goals
were an installed cost of under $50/KW with an operating  cost of less than 2  mils/KWhr.
               6.  Other goals included preliminary process control evaluations, determina-
tion of a site for the pilot plant,  and  evaluation of the fly ash problem.
        The miniplant was  modified to permit integrated operation based on  data from pre-
vious  experimentation.  Improvements in  sampling and analytical techniques were incorporated.
The scrubber (4-in. diameter column)  was enlarged to a packed height of 27 ft.  The reactor
                                                                           Q
(4-in. dia) was suspended vertically  and enlarged to a total of about 15 ft (1.5 ft of
volume) in three columns which could be used in series or in parallel.  The stripper was also
set up in three columns,  these being 12 in. in  diameter with the packing depth in each being
about 35 in. Provisions were again made  for a choice of series or parallel operation.  Pumps
and heaters were installed which could give the operating  range required of a complete para-
metric study.

-------
         Initial experimentation involved the determination of operating parameters in the sul-
fur dioxide reactor stage.  It became apparent that the purely gas phase interaction between
sulfur dioxide and nitrogen dioxide occurred far too  slowly to be feasible.  Further testing with
improved sampling and analytical techniques established the fact that the fast sulfur dioxide
oxidation reaction observed previously was in reality a liquid phase interaction.  Re-examina-
tion of prior experimentation showed that the liquid phase had always been  present in one form
or another when rapid reaction rates had been observed.  Once this liquid phase reaction was
verified, it was possible to modify the concept of the Catalytic  Chamber Process to include a
stage where the flue gas  containing sulfur dioxide  contacts a liquid phase consisting of oxides
of nitrogen dissolved in sulfuric acid.  Extensive experimentation established a maximum resi-
dence time of 15 sec being required to remove a minimum of 90% of the sulfur dioxide.  Solu-
tions containing 2% wt nitrosylsulfuric acid in 70% sulfuric acid were used to contact flue gas
at 225 °F to accomplish this degree of pollutant  recovery.
         Extensive evaluation of the absorption of  equimolar quantities of nitric oxide and nitro-
gen dioxide in sulfuric acid at elevated temperatures (200-275  °F) revealed that the process  is
probably a two-step operation and not a simple absorption.  Instead of a direct absorption of
nitric oxide and nitrogen dioxide into the  sulfuric  acid, there is apparently a required gas
phase reaction between the two gases to form nitrogen trioxide  which can then be easily
absorbed.  This gas phase interaction is relatively slow (compared to the absorption step), and
the equilibrium at elevated temperatures and low partial pressures is strongly shifted in favor
of the unreacted gases.  The result is that long residence times in packed  towers are required,
thereby greatly enlarging the equipment size.
         In estimating the economics of the process, two approaches were taken in sizing the
scrubber system: first,  the contact in the scrubber would be the same in the full-sized plant
as in the miniplant experimentation (a gas mass flow equivalent to about 20% of flooding); and
secondly, an assumption that the scrubber could be  optimized to approach the industry standard
of about 75% of flooding.  The marked difference between the capital and operating costs devel-
oped by using these two assumptions points out  the importance of scrubber size in the overall
process.
         Using direct scaleup of miniplant data  (L/C of 5.0 and a gas mass flow rate of 282 lb/
hr-ft2),  an 800-MW power plant producing about 1.5 million standard ft  /min of flue gas would
require a scrubber system,  including 106 packed  columns 25 ft in diameter and  53 ft high to
reduce the NO in the effluent to 100 ppm.  The total plant cost would be about $413  million  or
              X.
about $500/KW installed.  Operating costs would  be about $ 96 million or 22.2 mils/KWhr,
clearly an impractically high cost.  If an assumption of 75% of flooding in  the scrubber towers
is made, the costs are $114 million and  $26.8  million, respectively, for  an installed cost of
$140/KW and an operating cost of 5.5  mils/KWhr.  These latter costs are still very high, but
the effect of efficient scrubbing is clearly pointed out. An additional reduction in operating
cost can be achieved by  selling the product acids: if  sulfuric and nitric acids can be sold for
$10 and $40/ton (100%),  respectively,  the operating cost can be reduced  by about 1 mil/KWhr.

-------
         The scrubber operation was evaluated for nitrogen oxide removal only and was found
to be technically feasible,  although costly.  To reduce the concentration of nitrogen oxides from
2000 ppm to 100 ppm in an 800-MW power-plant, it would take 48 packed  towers 25 ft in diam-
eter and 45 ft high if we scaled up directly from miniplant data.  The cost of this plant would
be about $175 million, with an annual operating cost of about  $41 million (8.5 mils/KWhr).
Again, assuming that optimization would permit operation at 75% of flooding in the scrubbers,
the plant cost could be reduced to $43.5 million and the operating cost to $10.9 million (2.3  mils/
KWhr), showing the premium to oe gained by improving the scrubber operation.
         Evaluation of the catalystic stripper/oxidizer was incomplete because of the emphasis
placed on the reactor and scrubber stages. Initial  indications were that the oxidation/desorp-
tion mechanism may be something other than a liquid phase oxidation of dissolved oxides of
nitrogen followed by spontaneous generation of nitrogen dioxide.  The presence of carbon
dioxide and a large proportion of nitric oxide in the effluent gas at low nitrosylsulfuric acid
concentrations (< 0.3%) suggested that the dissolved oxides of nitrogen  were being reduced on
the carbon (and then oxidizing the charcoal). Some nitrogen dioxide was formed by gas phase
oxidation of the nitric oxide, but this reaction is very slow at low nitrose concentrations, and
only about 25 to 40% of the total nitrogen oxide content of the stripper off-gas was in the form
of the desired nitrogen dioxide.  Results in this area are contrary to previously-obtained data
at higher nitrose concentrations, and it could  well be that operation of the charcoal column
under other conditions may cause the necessary liquid phase oxidation.
         Preliminary evaluations of process control requirements were initiated during this
contract. The first step was to ascertain the operating parameters commonly employed in
the power industry.  Information obtained included turn-up and turn-down rates, % of excess
air, stability of air flow rates, operating changes during equipment failure, and stack effluent
properties. Two plants were evaluated: the Astoria,  New York unit of  Consolidated Edison
(primarily oil-fired), and TVA's Chattanooga  station (coal-fired).  Both showed surprisingly
similar operating parameters. In addition, the Brayton Point station (oil-fired) of the New
England Power Co. was briefly evaluated, with conditions being generally the same.
         A general examination of analytical and control instrumentation was made with the
emphasis being placed on response time and operating capabilities. The significant result
of this study was that the current state of the art in control instrumentation and eq uipment is
generally compatible with requirements for a  process as complicated as the Catalytic Chamber
Process.  Specific procedures were not developed,  but it was felt that there were  no problems
that could not have been met with current technology.
         Discussions were held with Consolidated Edison, TVA,  and the New England Power Co.
to ascertain the possibilities of building a pilot plant in conjunction with one of their existing
power stations.  All three expressed interest in pursuing the matter further when the process
had achieved a more advanced state of development.
         Based on the experimentation and analysis performed during this contract, it would
seem that the Catalytic Chamber Process at its current level of development is technologically

                                             6

-------
feasible, but economically impractical.  Control levels of 90% removal of SCL (from 3000 ppm)
and 100 ppm of NO  can be achieved, but at $125/KW capital cost and 5.5 mils/KWhr operating
                 X
cost,  both at least twice the economic goal.  The only future for the process is to improve the
operation of the three primary process stages or to develop more advantageous techniques.
Recommendations for future work were therefore as follows:
               1. Discontinue pre-pilot level experimentation in favor of laboratory bench
scale testing.
               2. Continue the evaluation of the liquid phase SO, oxidation to lower the resi-
dence time required  for 90% reaction.
               3. Re-examine low temperature scrubbing as in the original Lead Chamber
Process.
               4. Continue evaluation of activated charcoal in the stripper/oxidizer and
expand evaluation of previously studied candidate catalysts.

-------
II.  INTRODUCTION
        A.  Content of this Report
        This document reports the work performed by Tyco Laboratories, Inc., and its sub-
contractor,  the Badger Corp., during the one-year period February 1971 to February 1972
concerning the development of the Tyco Catalytic Chamber Process for the removal of sulfur
dioxide and nitrogen oxides from power plant flue gas.  The work was performed under Con-
tract No. 68-02-0008 with the Office of Air Programs (OAP) of the  Environmental Protection
Agency (EPA).  The report will include the experimental and conceptual work accomplished
for the evaluation of the engineering feasibility of the process, as well as consideration of the
economics involved in the full-scale plant construction and operation.
        B.  Initial Process Concept
        At the start of the contract period covered by this report in February 1971, the Tyco
Catalytic Chamber  Process had been conceptualized as shown in Fig. 1. The following discus-
sion describes the process as it was pictured at the start of the program and was based on ex-
perimental evidence from previous  Contract CPA 70-59,  as will be given in Part C of this sec-
tion.
        Wat flue gas is mixed with a recycle stream of nitrogen oxides.  The mixture under-
goes a gas phase reaction in a reactor stage, with the sulfur dioxide being oxidized by nitrogen
dioxide (NO2) to sulfur trioxide which is immediately hydrolyzed to sulfuric acid:

          SO2 4 N02 - NO + SO3                                                     (1)

          S03 + H20 - H2S04                                                        (2)

The gases containing sulfuric acid and mixed oxides of nitrogen are then passed into a high
temperature scrubber where both the product acid and the nitrogen oxides are removed by
countercurrent contact with hot sulfuric acid.  By operating the scrubber at such a temperature
that the vapor pressure of water over the incoming sulfuric acid scrubbing solution is equal to
the partial pressure of water in the incoming reacted flue gas (taking into account  the small
amount of water needed to convert the SOg into 80% sulfuric acid), the sulfuric acid and the
oxides of nitrogen could be scrubbed out without removing any water from the gas. This pre-
vents the dilution of the scrubbing solution.

-------
        It has been previously established during Contract Nos. PH-86-68 and CPA 70-59 that
neither nitric oxide (NO) nor nitrogen dioxide are very soluble in sulfuric acid, but can be
readily absorbed as nitrosylsulfuric acid (HNSO,.) in the acid if the two oxides are present in
equimolar proportions:
          NO 4  NO2  + 2H2SO4 - 2HNSOg + HgO                                       (3)

Thus, the recycle stream of nitrogen oxides has to be adjusted so that the gas leaving the re-
actor stage will  have equimolar quantities  of NO and NO0.
                                                     &
        This technique for the operation of the scrubber stage permits the emission  of a gas to
the atmosphere, meeting projected standards for SO« and oxides of nitrogen.  The high tempera-
ture operation produces a gas which is buoyant enough to be dispersed in the atmosphere without
further reheat.
        The nitrated  sulfuric acid leaving the scrubber is passed to a catalytic stripper, which
simultaneously oxidizes the oxides of nitrogen which have been reduced in the SCL oxidation
reactor and also permits the  complete denitration of the acid  without the addition of heat or the
dilution of the acid. This  is accomplished by the countercurrent contact of the nitrated acid
with air on an activated charcoal catalyst:
          4HNSOg + 2H2O + O2 - 4NO2 + 4H2SO4                                      (4)
When the reduced portion of the oxides of nitrogen are oxidized back to NOg, the equimolar
balance of NO and N0« is upset and the nitrogen oxides are spontaneously evolved. The deni-
trated acid can then be recycled to the scrubber after an amount of product sulfuric acid equiv-
alent to the amount of SO2 oxidized in the reactor has been removed.
        The gas evolved in the catalytic stripper is then available for recycle back to the ente
ing flue gas to continue the removal of additional SOg.  However, if the scrubber /stripper loop
operates at high enough efficiency levels, at this stage there will be excess N0x in the stripper
effluent due to the recovery of additional NO  from the flue gas.  Therefore, a portion of the
                                         A
stripper effluent is passed through a nitric acid absorber, thereby producing additional by-
product acid. The off-gas from the absorber and the remaining effluent from the stripper are
then recycled to the flue gas stream.
        As given here, the primary advantages of the process are:
               1. Both SO0 and NO  are removed from dilute flue gas while producing sulfuric
                          A        X
and nitric acid as salable byproducts.
               2. No additional heat is necessary to operate the process.
               3. The process could be added onto existing power stations with only minor
modification of existing plant equipment.
        C.  Prior Work
        Previous to this contract,  Tyco had developed the process  under two contracts  with
the Department of Health,  Education and Welfare: No.  PH 86-68-75 and No. CPA 70-59.   De-

                                            10

-------
tails of the work performed can be found in the final reports for these two contracts, and only
a summary of the findings will be included here.
        Experimentation showed that the original Lead Chamber  Process was not adequate for
cleaning flue gas because:
               1.  The required reoxidation of NO simultaneous  with SCL oxidation by less than
stoichiometric quantities of NO, in hot, dilute flue gas was too slow to permit reasonable resi-
dence volumes.
               2.  Scrubbing wet flue gas with cold sulfuric acid  caused the dilution of the
acid, thus requiring additional process heat to effect concentration of the acid.
               3.  Stripping the cold nitrose required additional  process heat.
               4.  The process required approximately 40% more fuel than the power plant
was burning to make up the heat required in (2) and (3) above.
        These disadvantages were overcome  with the development of the Catalytic Chamber
Process which showed that:
               1.  Scrubbing of NO   could be effected at high temperatures (in the 250 °F
                                 X
range) and thus avoid picking up water and diluting the scrubbing acid.  Experiments performed
in a 4-in. tower packed with 3/8-in.  Intalox saddles showed 65% removal of NO  from 7000 ppm
concentrations in 8.5 ft of column.
               2.  Nitrose (nitrosylsulfuric acid in sulfuric acid) could be denitrated by contact
with oxygen from air and activated charcoal.  In experiments performed at 260 to 290 °F,  a
99.7% removal of nitrosylsulfuric acid from nitrose solution (containing  0.7% HNSOg) was
achieved in 22 in. of charcoal packing.
               3.  Reactor experiments showed  that  about 95% conversion of S02 to SOg could
be achieved at 300 °F and atmospheric pressure, starting with 3000 ppm of S02 and about 6000
ppm of NO, with a residence time of 15 sec.
               4.  SO0 oxidation and NO reoxidation  could be effected separately without the
                     £t
need for additional process heat.
         D.  Contract Goals
          The goals of Contract No.  68-02-0008 were to (1)  demonstrate process viability by
 continued operation in an  enlarged and integrated 10 SCFM miniplant, including removal of
 SO,, and NO  from simulated flue gas to meet 300 ppm SO2 and 150 ppm NOx specifications  in
 exit gas, (2) establish process and engineering  data for scaleup to a 2000 to 5000 SCFM pilot
 plant level along with potential site locations, and (3) update process economics.
          More specifically,  the work was to  include  the following tasks:
                 1.  Develop engineering data for the SO,, oxidation reactor design.  The reactor
 was to be run separately from the rest of the miniplant to include optimization of reaction,
 temperature, and residence time to achieve  90% conversion yield starting with 3000 ppm SO,, in
 the incoming gas.

                                             11

-------
               2.  Develop design criteria for the NO  scrubber and catalytic stripper.  The
                                                   A
scrubber and stripper were to be operated without the reactor to establish the following operat-
ing parameters in a statistically designed parametric study:
                   a. Scrubber height necessary to reduce the 7000 ppm NO  level to 150 pprn
(also the height of a theoretical transfer unit).  [Note: Approximately 600 ppm NO  are present
                                                                             X
in the initial flue gas  from the power plant furnace.  The remainder results from recycle of
the NO, to the reactor.]
                   b. Temperature range for  scrubber operation
                   c. L/G for scrubber
                   d. L/G for stripper
                   e. Stripper catalyst bed depth
                   f. Stripper gas and acid space velocities
                   g. Stripper operating temperature
                   h. Excess air to stripper.
               3.  Operation of the integrated  miniplant, using a statistically-designed expert^
mental study of major process operating variables.  Of  particular importance is process con-
trol and process sensitivity near optimum conditions, corrosion tests, and the effect of fly ash
contamination through simulated study.
               4.  Development of process control criteria. A preliminary evaluation of pro-
cess control considerations was to be made based on the original process, as given in Section
II.  Such items as the availability of in-line analytical instrumentation, techniques of fluid flo\v
and concentration adjustment,  control  equipment, response time requirements, and power plar^
operating procedures were to be determined. A process control system would be recommended
               5.  Selection of a site for subsequent 2000 to 5000 SCFM pilot plant installation.
Discussions were to be held with utility companies such as Consolidated Edison Company of
New York, the Tennessee Valley Authority,  and other interested utilities to examine the pos-
sibility for locating a pilot plant on the site of an existing power station.
               6.  Prepare a preliminary design for a pilot plant.
        In conjunction with a subcontractor, the Badger Corp.,  a preliminary pilot plant was
to be designed based on the engineering criteria developed in the experimental phases  of the
contract.  The plant design would hopefully be tied to a  specific  location and a specific stack
gas.
                                            12

-------
III. ENGINEERING SUBCONTRACTOR — THE BADGER CORPORATION
        The Badger Corporation was engaged as subcontractor to Tyco for the purpose of pro-
viding additional expertise in the areas of engineering and design.  Badger's role in the contract
was designed to be in three areas: (a) general engineering consultation, (b) design of a com-
puter program for process optimization, and (c) preliminary design of a 2000 SCFM pilot plant.
        A.  Engineering Consultation
        Daring the early stages of the contract, Badger's primary function was to evaluate the
process from a plant design viewpoint and help in the design of experimentation which would
help develop the data needed for the preliminary pilot plant design.  Several meetings were
held between Tyco and Badger personnel to exchange information and develop  ideas for ex-
perimentation. In this area,  Badger  made an initial evaluation of the process and made general
suggestions  given in Appendix I.
        B.  Optimization Program
        Badger utilized their extensive experience in computer optimization of process vari-
ables in chemical plants to develop a program which was intended to help in the analysis of  the
experimental data.  Based on the process conceptualization given in Part I of this report,  a
program was written around process stoichiometry which would permit optimization of the
operating variables. As new experimental data was reported, the process concept was revised
and the program was appropriately modified.  In this manner, the program could be used to
back up the experimental work and keep the laboratory and miniplant work aimed in the proper
direction. As the contract orientation shifted from plant design to reevaluation of process con-
cepts, the optimization work was deemphasized.  At the completion of the contract, Badger had
a partially modified  program which would require several changes to be useful for further
optimization.
        C.  Pilot Plant Design
        During the early stages of the contract, Badger's major contribution in the pilot plant
design area  was to provide assistance in developing the process control system that could be
used with this type of process.  This work will be discussed in some detail in Section VIII of
this report.  During  the latter stages of the contract,  it became clear that the process concept
was not sufficiently developed to permit pilot plant design, and this phase of the work was
discontinued.

                                            13

-------
IV.  MINIPLANT MODIFICATION AND EQUIPMENT
         A.  Existing Equipment
         At the start of this contract, the all-glass miniplant used in Contract No. CPA 70-59
was operable, but needed extensive modification to permit complete evaluation of the process
variables.  The previous contract had established revised operating parameter ranges for im-
portant variables, and it was therefore necessary to change the capacity of certain process
stages to accomplish suitable integrated operation. The SO, oxidation reactor, the scrubber
system, and the stripper stage all had to be modified and enlarged,  which created the need for
changes in pumps, flowmeters, piping systems, and instrumentation.  Fig. 2 shows the flow-
sheet of the miniplant as conceived at the beginning of this contract in  February 1971. As the
contract proceeded,  several additional modifications  were required, and they will be discussed
in the following sections of the report.
         B. SO? Oxidation Reactor

         The reactor used in the prior contract was a horizontal glass tube, 4 in. in diameter
and about 5 ft long. Experimentation during the previous contract indicated that the oxidation
of SOp to SO, (with subsequent hydration to FLSOJ might not be as simple as the equation
SO?  -f NO« = SO, 4 NO would suggest.  The reactor in the miniplant was therefore designed so
that this reaction could be examined in more detail than  in the past.  The reactor was placed  in
                                                            3             3
a vertical configuration and its size increased from about 0.5 ft to about 1.5 ft , with the option
existing for using either one-third of the new reactor or the whole volume.  The first third of
the reactor was  set up so that it could be easily packed,  if necessary,  with some material for
increasing surface area and possibly to spray the gas with a fine acid mist. Later, an option
was  made available for a single 15-ft reactor column to  be installed in series with a liquid
phase feed system. The spray capability was added to simulate the conditions in the chambers
of the Lead Chamber Process Plant and thus evaluate the possibility  that some phase of the
oxidation involved a liquid phase reaction.  The reactor was assembled using a 4-in. glass pipe
and jacketed for heating the simulated flue gas.  Previous experience indicated that a  maximum
temperature of 375 °F  could be achieved in the reactor column.
         C.  Scrubber Columns
         As shown in Fig. 2, the initial plant operation was to utilize a single glass scrubber
                                            15

-------
Bypass to
 stack,

                           T
                         -O-
                   tUK
            Flow meter
                       NO
                  Qxidizer
            Filter
         Gas
        Burnei
 Natural
    gas
TT
              . diluent
               gas (M9 or
               air)   £
ID
                                               Acid feed
                                                               To stack





T


O
T




T
O


                                                                     Corrosion samples
                                                                     (in packing)
                           Bypass to stack
                     Flow meters
                          NO Air
                                             Corrosion
                                             sample
                                             chamber
1
0
T
O
T
T

O
T






•
	 }






f

O
T
O
T
O
-X-



I


-
r-,1


1



9

O
T
O
T
¥





«
                                          Corrosion
                                          sample
                                          chamber
                                          (nitrose, gas)
                                   S -  Sample port

                                   T -  Temperature probe
Corrosion
sample
chamber
(denitrated acid)
                                                                                        Compressed air
Air
                   Fig. 2.  Schematic flowsheet of miniplant (strippers in parallel configuration)

-------
column containing about 7.5 ft of packing (3/8-in. Intalox saddles).  This column was similar
to the one used in the prior contract,  and it was known that scrubbing efficiencies in excess
of 65% could not be achieved in a column of this height.  During the contract period,  it was
therefore decided to enlarge the scrubbing system by adding an additional glass column con-
taining 19 ft of packing. A sketch of this column is shown in Fig. 3. All scrubbing experimenta-
tion was  performed using the two scrubbers (7.5-ft and  19-ft sections) in series.
         D.  Stripper Columns
         In order to achieve stripper  space velocities equal to those used  in the laboratory ex-
perimentation performed in Contract  CPA 70-59, the stripper stage was redesigned to consist
of three  4 ft high x  12-in. diameter columns operated in parallel (see Fig. 2).  The catalyst
was Witco Type 256 activated charcoal 4 x 10 mesh.
         As initially designed,  the stripper columns consisted of Teflon-coated, stainless steel
tubes as  shown in Fig. 4.  The tubes had gas feed ports  at two levels and four ports for thermo-
well probes on the sides.  There were two  openings in the top cover (acid  feed and gas exit)
and an acid drain in the bottom. Ports which connected  to transfer lines were flanged using
standard 150 lb ASA dimensions for easy connection to  1-in. glass pipe. All surfaces which
were to come into contact with acid were coated with Teflon.
         Inside the  tubes provisions were made to support four beds of activated charcoal.
Three-pronged spiders,  resting on half-inch studs welded to the inside wall at four levels,
provided support for the center sag of the fiberglas fabric-wrapped ring which was the actual
support plate for the charcoal. A sketch of this arrangement is also shown in Fig. 4.  The three
strippers were each loaded with approximately 25 lb of charcoal to a depth of about 35 in.
         During the operation of the system, it became obvious that the coating was  not adhering
properly to the surface of the column and the metal was corroding severely (note Appendix VI).
The three columns  were cleaned and recoated with another Teflon formulation  recommended by
duPont, but this coating eventually failed also. Rather than continue to experiment with other
coatings, it was decided to redesign the strippers to use an all-glass system with solid Teflon
gaskets and covers. A sketch of this  new design is shown in Fig.  5.
         This design made use of a glass packing support plate perforated with half-inch holes.
To prevent the activated carbon from falling through the holes, the support plate was covered
with a thin Teflon sheet perforated with quarter-inch holes.  A layer of 3/8-in. saddles was
placed over the  Teflon plate and the carbon placed on top of the saddles.  During several weeks
of operation there was no apparent loss of carbon particles (which were 4 x 10 mesh). This
support design avoided a problem that arose with the fiberglas fabric  support configuration.  In
the earlier design the fine holes of the fiberglas fabric  created such a high pressure drop that
the air pressure required to force air up the  column prevented the uniform flow of acid down
the column.  The new design had no such high pressure drop and uniform flow was easily
achieved.
                                             17

-------
Flowmerer
 li cater
                       u=
         •*—!•

        fr-
Thermo-
  well
            l|J: — Thermowell
                Support place and
                redistributor
                                lixit gas

                                 Thermo well

                                Support plate
                                and redistributor
                  19' Scrubber

                Support plate and
               ' redistributor
                 Support plate and
                 redistributor
£31
                             Reservoir
                                         Immersion heater
    Fig. 3. Sketch of 19-ft scrubber
                   18

-------
                   acid     gas
                   feed     exit
                  J'LJlL
                     24".
                                 3=__Thermowell ports
gas feed-
ports
                                    Bed Support Structure:
                                    Ring with "Y" spider
                                    covered with fiberglass
                                    fabric
Fig. 4.  Miniplant stripper column and catalyst bed support structure
                          19

-------
                            Feed acid


                               Effluent gas



                               Teflon plate
                             Thermowells
                             (equidistant from
                             the center)
                               12-in. x 48-in. glass pipe
                                Packing support plate
                                     (glass)
                      Feed air
                  Acid drain
Fig. 5.  Stripper column using glass pipe
                    20

-------
        E.  Liquid Pumps
        During earlier work on the miniplant in Contracts PH 86-68-75 and CPA 70-59, the
acid had been pumped through the system using piston pumps of standard design (Clark-Cooper
Mark  II Metering Pump), with all wetted parts being made of Carpenter 20 alloy.  These had
required considerable maintenance, and new pumps were ordered for this contract.
        All Teflon pumps (Fluorocarbon Co. Saturn Pump) utilizing a nutating disc design
were used during the early stages of the contract, but these too were unsatisfactory.  The
major problem with this design was the softening of the Teflon at high temperatures which
caused the internal seal to leak,  thus reducing flow to a trickle.  These pumps also had a tend-
ency to  foul  easily, and small particles prevented a good  seal between the nutating disk, thus
sharply reducing its flow.
        The Saturn Pumps were replaced with ECO gearpumps utilizing Hastelloy B construc-
tion to prevent corrosion. Estimates by both Tyco and ECO indicated that Hastelloy B was a
marginal material of construction for long term use,  but  should be adequate for the duration
of the contract (about 50 mils/yr corrosion level). In actual use, however, excessive aeration
of the acid combined with the high temperature, high speed operation of the pump caused ero-
sion of the pump body. This resulted in excessive clearance around the gears which reduced
the acid flow to very low levels.
        The pumps that eventually proved adequate to the task of pumping 80% sulfuric acid at
temperatures over 200 °F were simple peristaltic pumps  manufactured by the Ober Co. for
Cole-Parmer.  The Masterflex Pump using Viton tubing could be used for up to about 36 hr
before tubing replacement was required. This meant that complete runs could be made without
interruption for pump maintenance, and even if tubing replacement was required, the change-
over only took a few minutes and thus avoided long periods of down time.  This certainly was
not a long term answer to the pumping problem for either the miniplant or the larger pilot
plant, but was certainly adequate for the short term requirements of this contract.
        It was interesting to note that on a larger scale,  pumps are readily available that can
handle the operating conditions of this system.  The Durco Co. manufactures duririon centrif-
ugal pumps in  sizes which can handle pumping rates of 5  to 3000 gpm. However,  the  centrif-
ugal pumps could not easily handle the 0.1 to 0.8 gpm required in the miniplant, and smaller
pumps made of duririon are not available.
        F.  Gas Pumps
        The miniplant had two requirements  for pumping of gases: transferring the raw simu-
lated  flue gas, and pulling a gas sample from various points in the process gas loop.  The first
requirement had been met in the original miniplant design by using a blower manufactured by
MGD  Pneumatics Co.  This blower easily provided up to 12 SCFM of raw flue gas.
        The sample pump was a far more difficult problem because of the combination of high
temperature,  high water content, and the corrosive nature of the gas.  After  trying several
pumps which proved inadequate, a low cost diaphragm pump made by Bellfc Gossett (Fluid
                                           21

-------
Handling Div.,  I.T.T.)  was chosen.  This pump required relatively frequent maintenance,  but
the low cost of the unit permitted the use of several spares which could be kept ready for  rapid
installation while the fouled pump was cleaned. By carefully trapping condensed liquid in the
gas lines, the pump could be operated for several days without problems.
        G. Instrumentation
        Instrumentation in the miniplant involved three areas: flow rate determination, tem-
perature measurement, and in-line gas analysis.  No automatic control equipment was used.
Fig. 6 shows the miniplant after final modifications and sample point installation.
               1. Flow rate determination
               All liquid and gas flow rates were measured using in-line glass rotameters as
shown in Fig. 6.  Liquid levels in reservoirs and columns were controlled by visual inspection
and throttle valve adjustment by the plant operators.
               2. Temperature measurement
               Over forty temperature measurement points were utilized to help monitor and
control the process.   Two Esterline Angus twenty-four point recorders were therefore instaHe-j
to continuously monitor the temperature levels, with the data being extracted from the recorder
printout by the plant  operator and recorded permanently on data sheets.
               3. Gas analysis
               At several points in the system, the process  gas lines were monitored for con-
centration of NO0, SO0, and NO. This was accomplished for  the first two gases by analysis
               a     ft
with a duPont Model 400 ultraviolet photometer. Nitric oxide  was monitored with a Beckman
Model 315A infrared analyzer.  In addition, the water content of the gas was periodically moni-
tored with a EG&G Model 2000 dew point hygrometer.
        H.  Gas Feed
        The flue gas feed was simulated by doping the effluent of a natural gas burner with
fur dioxide as shown in Fig. 6.  The exhaust gas from the burner was diluted with air to
the water content of the flue gas fed to the system so that the feed stream contained about 6%
water, 15% oxygen, plus  CO2 and nitrogen. Sulfur dioxide was metered into the controlled ex-
haust gas stream to create any desired concentration.
        Nitrogen dioxide was fed to the system by oxidizing nitric oxide with air.  NO, is a
liquid below 22 °C and is  very hard to handle around room temperature. Previous experience
had shown that the gas condensed  in flow meters and tubing creating a very difficult cleanup
problem.  In order to avoid this problem a large empty reactor chamber was used to oxidize
the NO to NO« before it was fed to the process. Yields of 75 to 85% were obtainable in this
manner.  See Appendix X for a discussion of air oxidation of NO for this application.
                                            22

-------
to
co
OQ
0>
•

2
a
M*
K
a
3
H*«
3
      3
      ET
     1
                Rescr
          Bypass
              me
          Blowe

           Gas
        Burner
                Air
Gas sample

L
Reactor
sample
Flow
_ meter
&S-ffip

1
pir |^\J ^
1 n Flow
j U meter
fi fH
LJtank
T




HNSO,
Concent
NO C
Oxidizei
JL
rat
1
i
ion
t
^esdrv
r
]Flo
met
V
lir
V
sr
^
Gi
19'
Scr
r
i

is sample
f
ll— •
JJ.
b
lo
Q
R
n
J
er
?r
ah
se
*.A
1


•vcU
	 1
cid
To
-»(
s
1
E
2)1 m
sam]
LValve
stack
3as
;amp
I'lo\
1CD
Aclc
Sam
t
j
ale
— P
R\
i
le

t
r
Bypas
ito sta
. \ \ - j
T T Valvet
itijippef:^
. LJ 1 	 1
i i- * *
j
iplcs
test
, cb Filter
1 ^"JF — "^ Stripper
U oypass
I\imp
.ow control
ma ft s
DFlow
meter
                    Natural
                       gas
                                                                           Pump
                                        :ers
                                    Air

-------
         I. Miniplant Operation
         The approach taken during the contract was to operate the miniplant in separate stages
leading up to integrated operation.  First,  the reactor stage was fully evaluated and then the
scrubber/stripper loop was investigated. The emphasis in plant design was on simplification
of operation to aid in the rapid accumulation of data. This was particularly pertinent since the
miniplant was operated by two men per shift. Details of the miniplant operation,  including
data-taking procedures, gas sampling techniques, and mode of shift operation are presented
in Appendix II.
                                            24

-------
V.  REACTOR EXPERIMENTS
       A. Background
       Experimentation on Contract CPA 70-59 indicated that the gas phase oxidation of SO_
                                                                                    Ct
with NO0 occurred very rapidly at 300 °F such that at a concentration of 3000 ppm SO0, about
       ft                                                                       Ci
95% would be converted to H,SO.  in less than 20-sec residence time. These results were
somewhat erratic, but several runs were made that gave consistent yields at this level.  The
only reason for questioning the data was the fact that the residence time of the gas in the sam-
ple lines and analyzer was about 15 of the total 20-sec contact time. To verify this earlier
data, a series of experiments was run in the miniplant using a three-reactor column containing
          g
about 1.6 ft  of volume. The gas sample system was modified so that the gases were in contact
for only about 2 to 4 sec in the sample lines, and the results more closely represented the re-
action occurring in the reactor chamber.
       Initial tests at 300 to 350 °F, using gases containing about 3000 ppm of SO, interacting
with NO  streams providing about 6000 ppm of NO?  and about 2000 ppm of NO,  indicated reac-
       x                                       ^
tion rates of about 15 to 20%, with reactor residence time of 15 sec and  sample line residence
times of about 3 sec.  Table I shows some of the data from these initial runs. These low yields
necessitated a more complete evaluation of the reactor system due to the differences between
the experimental system used in the earlier tests and the more recent miniplant and sampling
system design.
       Clearly, the most significant of these differences was the shorter sample line residence
time although the total contact time was about  the same.  In addition, the sample lines were
modified so that heating was  more uniform and condensation in the lines was greatly reduced.
Rather than using 1/4-in. glass pipe wrapped with heating tapes, the samples were pumped
through 3/16-in. Teflon tubing which was enclosed in aluminum tubing wrapped with heating
tapes. This approach avoided the flanged sections of pipe which were very hard to wrap with
tapes and permitted continuous lengths of uniformly heated tubing which could be easily cleaned.
       To evaluate the effect of these plant modifications as well as examine the operating
parameters of the reactor, a series of miniplant reactor tests were run as discussed  below.
       B. Reactor Experiments;  Effect of UV Radiation
       Initially, two experiments were run to  determine if UV radiation accelerated the gas
                                                                               o
phase reaction between SC^ and NC»2.  An empty 4-in. glass column containing 0.53 ft  of void

                                            25

-------
Table I. Initial Reactor Studies
Reactor temperature (°F)
Gas flow rate (SCFM)
Gas feed: (ppm)
so2
N02
NO
H20 (%)
Effluent gas: (ppm)
so2
N02
NO
Reactor residence time (sec)
Sample line residence time (sec)
Q
Reactor volume (ft )
SO- removal efficiency (%)
Run 4
350
4

3200
6100
1700
-6.0

2750
6050
2200
14.5
~3
1.6
14.1
Run 8
350
4

3050
6000
1400
-6.0

2600
6700
1800
14.5
-3
1.6
14.8
Run 8A
300
4

2950
6000
-6.0

2300
5350
2400
15.5
~3
1.6
18.7
             26

-------
volume (6 ft long) was modified so that a UV source emitted radiation down the length of the
tube.  Gas containing SO,,, N0_, and NO was fed into one end of the column (the end housing
the UV source),  and the gas concentration was monitored before and after passing through.
Two runs were made, as shown in Table II, with the only difference between the two runs being
that in Run 51 the radiation was directed toward the side of the column and was reflected through
the tube by aluminum foil.  In Run 51A, the source was aimed along the length of the tube.  In
both cases,  the radiation passed through a quartz plate which protected the source from the
corrosive gases.
       It is clear from the results of the two runs that the UV radiation had no effect on the
oxidation rate of the SO0 by NO0.  Although there is a consistent NO  material balance error
                      ft       £t                                  X
due to small NO  analysis errors, there is no apparent acceleration of the oxidation of S00.
               X                                                                     s*
       C.  Miniplant Tests: Effect of Temperature on SO, Oxidation Rate

       During the early runs, discussed above, there were indications that temperature had a
significant effect on the S02 oxidation rate.  To evaluate this effect, the reaction was tested
over a range of temperatures at different flow rates in order to vary the reactor residence
time.  At the same time, the effect of water vapor in the gas stream on reaction rate was
evaluated by running the tests with and without the gas burner. It should be noted that the
primary purpose of the gas burner was to introduce water through the oxidation of natural gas.
The gas burner effluent contained about 6% water after dilution.  The results of these tests are
shown graphically in Fig. 7.
       It had been anticipated that the gas phase oxidation of SO- with NO, proceeded according
to the reaction:
         SO2 + N02 -  S03 4 NO

and would proceed at a faster rate at higher temperatures.  The data in Fig. 7 show that just the
opposite was true: higher temperatures brought about lower oxidation rates.  The data also
showed that at lower temperatures the presence of water vapor in the  reaction stream was es-
sential to higher reaction rates.
       In general,  the results  were more compatible with a mechanism involving a liquid phase
reaction rather than the expected gas phase oxidation. The increasing reaction rate at lower
temperatures suggested the necessity of dissolving the gas phase reactants in a liquid phase
before the reaction could take place. Comparing the  Tyco Process with the original Lead
Chamber Process,  it should be noted that one major difference is  the absence of liquid addition
in the SO0 reaction stage.  Much has been written about the complexity of this reaction,  and at
         ft
this stage of experimentation it appeared that the liquid phase addition might  well be essential
to high reaction rates.
       D.  Effect of Acid Irrigation on SOg Oxidation Rate

       To evaluate this concept, a series of experiments was performed in the miniplant reac-

                                            27

-------
          Table II. Gas Phase SO2 Oxidation with N02
                   in the Presence of UV Radiation
                                                     Run 51A
Gas flow rate (SCFM)                     2                2
Column temperature (°F)                250              250
Gas feed: (ppm)
   S02                              2800             3400
   NO2                              5600             6200
   NO                               1500             1900
Effluent gas: no UV (ppm)
   S02                              2000             3100
   NO2                              8600             9050
   NO                               1675             3850
Effluent gas: with UV (ppm)
   SO2                              2050             3100
   NO2                              8500             9050
   NO                               1775             3850
SO2 removal without UV (%)            28.6               8.9
SO2 removal with UV (%)               26.8               8.9

   Notes:  1. Run 51A was run under identical conditions to
              Run 51 except that the UV source was aimed
              directly down the reactor column instead of
              into the wall.
           2. Reaction run in empty glass tube 4 in. x 72 in.
              (0.53 ft3).
                             28

-------
100 -
 90 -
 80
 70
 60
 50
 40
 30
 20
  10
          Run 8D
          2 SCFM
          < 1% H20 in flue gas
Run 8A
4 SCFM
-6% H2O
in flue gas
          Reactor Residence Time
               at 4 SCFM
         °F                Sec
150
200
250
300
350
19.3
17.9
16.6
15.5
14.5
                             Three reactors in series total
                             volume:  1.6 ft3 (first 0.3 fir
                             contained 3/8 in. Intalox saddles)

                             Feed: S02 - 3000 ppm
                                   NO2 - 6000 ppm
                                   NO - 1500 ppm
                                         Run 8B
                                         2 SCFM
                                         ~6% H20 in flue gas
            100
                    200
                   300
400
                           Temperature, °F
   Fig. 7.  Miniplant reactor experiments - SC>2 oxidation. Effect of water
          vapor in flue gas, residence time, and temperature
                               29

-------
tor which was modified to permit irrigation of part of the chamber with a liquid phase.  Fig. 8
shows the configuration of the reactor during this phase of experimentation.  The diagram
                                                                          2
shows that the gas could be  passed through either one reactor chamber (0.64 ft  containing
     3                                                   3
0.3 ft  of 3/8-in. Intalox saddles)  or three chambers (1.52 ft  total),  with only the first reactor
chamber being irrigated. The saddles were placed in this chamber to increase the gas/liquid
contact.
       Figs. 9 and 10 show  the results of irrigating the first reactor  section (containing the
saddles) with 80% sulfuric acid at  gas flow rates  of 2 and  4 SCFM.  It is clear that there is  no
apparent advantage to acid irrigation under the conditions shown.  Fig. 10 also shows the effect
of irrigating the first reactor section with water  rather than acid.  Because of the vaporization
of water above 150 °F, it was impossible to continue the experiments above this temperature
but if the effect could be extrapolated to  higher temperatures, it would appear that again there
would be little advantage.
       During some of the irrigation runs, it had been noticed that, if the acid had been exposed
for a period of time to NO  in the  gas phase before the SCL was  introduced into the flue gas,
initial reaction rate was significantly higher than the eventual steady  state reaction level.
led to the concept involving  the buildup of dissolved NO in the liquid  phase in order to effect
high reaction rates.  To test this hypothesis, the column was irrigated with acid for an
period of time, after which  the acid flow was stopped.  The gas phase reactants were then in-
troduced into the reactor and the effluent concentrations allowed to achieve steady state.  Fig<
11 shows the results of this  test at 2 SCFM.  Clearly, this technique  is far superior to either
the dry reaction mode  or the continuous  acid irrigation.
       Examination of Fig.  11 reveals an anomaly which  should be considered at this point.
The experiment which  involved the continuous irrigation of the reactor with 80% sulfuric  acid
exhibited lower reaction rates than the dry interaction, which apparently contradicts the  pro-
posed liquid phase reaction  mechanism.  This can be explained in terms of the actual conditiOtls
in the reactor during most of the experimentation.  The tests described up to this point were
usually run for a few hours  at the  most and one right after the other.   The net effect is that the
"dry" condition mentioned above was very rarely the case. Even when running without irrig^.,
tion, it took many hours for the saddles  to be completely  dried out from either previous runs
or condensation during unirrigated runs. It is therefore quite likely that, during the "2
burner on, no acid" run shown in several of the graphs, there was a  significant amount of
present on the saddles which improved the reaction due to buildup of  reactant concentration jn
the liquid phase.  The extreme of this wetted condition is  undoubtedly shown  by the top curve j
Fig. 11.
       One more series of tests was run to ascertain the advantage of the presence of a  liqujd
phase. This involved two runs in which the saddles  in the first section of the reactor were
wetted with 80% sulfuric acid before the  reaction was initiated.  In one of the two tests,  the
gases were passed into the other two void sections of the  reactor before analysis,  while in
the second test the effluent gases from the packed section were  analyzed immediately.  The
                                            30

-------
                                         Reactor Volumes
                                         1-0.64 ft3 (0.3 ft3 of saddles
                                         85% void volume)











r •*

MO oxidizer
Three-way
valve






^1
' _ 2-0.44 ft (empty)
By pass 3 r J
. . 1 *} f\ A A f+ f ft »VM^*^ T \
to stack J-0.44 ft ^empty)

/
M
V.



j



4-1.05 ft (empty)
Liquid feed





Flue gas
feed (con-
S i taining /
|L- 	 v SCU /
M
t I
NO Air
feed feed
/
3/8 in
/
/
/
/
•




}
Gas
= _». sample
rvrrr/lnlprV

!
^\x\
V\\N

P



L-

porcelain
Intalox


r









| ]
Jk Jl



























Gas sample
port (outlet)
X T \


^_^


Three- way
valve
saddles
                         Liquid
                         drain
Fig. 8.  Configuration of miniplant reactor during initial experimentation
        involving liquid irrigation
                                  31

-------
   100
   90
   80
   70
   60
>  50
o
»*
 esj
   40
   30
   20
    IO
                            Three reactors in series total
                            volume:  1.6 ft3 (first 0.3 ft3
                            contained 3/8 in. Intalox saddles
                            and was irrigated)
                            Gas flow:  2 SCFM
                                     Run 8B
                                     No irrigation
                                     -6% H2O in flue gas
         Run 8D
         No irrigation
         < 1% H20 in
      _ flue gas
Run 9B
-6% H2O in flue gas
Irrigation of packed
column with 80% H
H0SO. at -30 cc/min
                               I
            100
                  200
                  Temperature, °F
300
400
 Fig. 9.  Miniplant reactor experiments - SO2 oxidation. Effect of reactor
        irrigation with 80%
                                 32

-------
     100-
     90
      80
      70
      60
  1
  cT
  to
      50
      40
      30
      20
                            Run 10
                            Irrigated with 37 cc/min
                                      Reactors in series
                                      total volume:  1.6
                                      ft3 (first 0.3 ft3
                                      contained 3/8 in.
                                      Intalox saddles and
                                      was irrigated)


                                      Gas flow: 4 SCFM

                                      Water content:  ~6%
                         Run 9A
                         Irrigation with 27 cc 'min 80%
                         H2S04
Run 8A
No irrigation
                                  I
               100
                    200             300
                    Temperature, °F
400
Fig. 10. Miniplant reactor experiment - SC>2 oxidation.  Effect of acid or water
        irrigation in packed reactor
                                   33

-------
    100
    90
     80
cf
on
    70
        _ Three reactors in
    60
    50
    40
    30
    20
     10 -
                                       Run 15
                                       Packed reactor wetted with
                                       80% H£SO4 before reaction
                                       started
   series total volume:
   1.6 ft3 (first 0.3 ft3
   of reactor contained
   3/8 in. Intalox saddles)

   Water content:  ~ 6%
   H20

~  Gas flow: 2 SCFM
Run 8B
No irrigation
               Run 9B
               Irrigation with 30 cc/min
                 ~ H2S04
                                I
                                          I
              100
                       200             300

                       Temperature, °F
        400
 Fig. 11. Miniplant reactor experiment - SOg oxidation.  Comparison of acid
         irrigation,  wetted wall tests, and no irrigation
                                  34

-------
results shown in Fig. 12 make it clear that the 24 sec spent by the gas in the empty reactor
sections contributed little or nothing to the reaction which was achieved in the 5 sec in the
wetted saddles.  This key test established that, under the existing conditions and gas concen-
trations of interest,  the oxidation of SO, is achieved in the liquid phase.
       These tests were followed by a series  of experiments which attempted to optimize the
liquid phase oxidation of SOg. The first step was to pack all three reactor sections with 3/8-in.
Intalox saddles and provide irrigation to the top of each column.  This created a situation  where
reactors 1 and 3 were operated with the liquid and gas contacting each other in a cocurrent
manner,  while reactor 2 was in a countercurrent configuration (see Fig. 8).  Several tests were
run in which operating parameters were varied, including acid flow rate,  acid concentration,
and NO concentration (gas phase),  but little improvement  in reaction rate was achieved.
       A
       A typical reaction run is shown in Fig. 13.  With elapsed time running from right to left,
it can be seen that with no acid flowing it took about 1-1/2 hr for the system to reach steady
state.  During this time, the  acid on the saddles was apparently building up in reactant concen-
tration until a steady state condition was obtained.  During  this run, the effect of high oxygen
concentrations in the flue gas was evaluated.  This  high oxygen content is  the result of diluting
the gas burner effluent gas with air in order to reduce the water content of the gas from about
20% to 6 to 8%.  Instead of about 3% Og, which is typical of coal burner flue gas, the simulated
flue gas used in the current experimentation contains about 15% O,. To determine the effect of
this high oxygen level, an apparatus was constructed  which permitted the dilution  of the gas
burner with nitrogen rather than air. Examination  of Fig.  13 shows that the SO, content of the
reactor effluent reached a steady state level of about  1050 ppm after approximately  1-1/2 hr.
At this point, the diluent air  was  replaced with nitrogen and the experiment continued for  an-
other hour under these conditions.  The nitrogen was  then shut off and air returned to the  dilu-
tion line.  It is obvious that these changes had no effect at all on the oxidation rate of SO,. It is
therefore safe to say that, in general, the results of the experimentation  were not affected by
the presence of the high oxygen levels.
       E.  Instrumentation Considerations
       During these last experiments, it  was noticed that there was some apparent interference
by the NO2 on the SO2 reading of the duPont UV Photometer. It was known that NO, absorbed
to some degree at 302 mM  where the SO,  was measured, but this was supposedly  balanced out
through the use of a reference beam which analyzed at a wavelength where SO, and NO, ab-
sorbed equally.  In addition,  there was a balancing  potentiometer which permitted the inter-
fering NO9 to be zeroed out,  so there should have been no  apparent interference by NO, at the
SO, absorbing wavelength. The problem was  that,  at the higher N09 levels used in some of
   2                                                            ^
the tests (up to about 15,000 ppm), this balance was not accounting for the interference.
       Discussions with instrument people at duPont revealed that the balance control was ef-
fective at constant levels of N02 in the SOg-bearing gas  stream.  If the NO, interference was
balanced out at low NO2 concentrations, there might well be very large levels of  interference
                                            35

-------
     100
      90
      80
      70
      60
   §
   *
   O
   oo
      so
      30
      20
       10
Run 15
Packed reactor
wetted with 80%
H2SO4 before
reaction started
0.3 ft3 packed,
1.3 ft3 unpacked
                    Run 8B
                    No irrigation
 Gas flow:  2 SCFM

 Water content:  ~6%
       Run 14
       Packed reactor wetted
       with 80% H2S04 0.3 ft3
       packing 0.2 ft3 unpacked
                                            Run 14
                                            Packed reactor
                                            wetted with 80%
                                            H2S04 0.3 ft3
                                            packing 1.3 ft3
                                           unpacked
                                  I
                100
                   200

                  Temperature, °F
300
400
Fig. 12. Miniplant reactor experiments — SOo oxidation.  Comparison of wetted-
        packing reactions with and without additional unpacked residence volume
                                   36

-------
                                                                             3275 ppm NO
Reactant
concentration
                _ 3000 ppm
                — 1050 ppm
                                Flue gas diluted with
                         Gas feed:

                        1850 ppm NO
                        2500 ppm SO2
                        4800 ppm NO2
Reactor temperature:  360 °F        3
Three reactors, packed with ~ 1.25 ft
of 3/8 in.  Intalox saddles;  no irrigation
                                          2
                                         Elapsed time, hr
               0
         Fig. 13.  Miniplant reactor experiment — 803 oxidation. Evaluation of low O2 level in
                  flue gas

-------
 at high concentrations. DuPont's recommendation was to balance the instrument at zero NO
 concentration and run a calibration curve,  giving SCL interference at various levels of NO
 This was done, and the resulting interference curve is plotted in  Fig.  14.  The curve was ob-
 tained by reading SCL while feeding known concentrations of NO, to the UV cell.  The inter-
 ference level is approximately 30:1, which is about what was predicted by duPont.  (This
 means that 30 ppm of NO, shows up as 1 ppm of SO0.)
                        i                       i
        The high levels of N02 used in this  stage of experimentation caused a difficulty in read-
 ing NO2 concentrations above 1.5% (15,000  ppm) because of the saturation of the measuring
 photocell's ability to  read low light levels.  DuPont recommended a shorter UV cell to effect
 lower total absorbance in the cell.  It was decided to replace the 15-in. cell with a 1.5-in. cell
 rather than put the two in series.  By using a higher gain mode in the photometer amplifier,  «t
 was possible to use the shorter cell without loss in sensitivity at the gas concentrations of in~
 terest (up to  5000 ppm of SO2 and 10,000 ppm of N02 full scale).  The instrument could also be
 used to measure  very low concentrations (500 ppm SO2 and 1000 ppm NO2 full scale),  if de-
 sired.  The advantage of this system is that it is possible to read NCL at both 10,000 ppm ana
 100,000 ppm  full  scale, thus permitting accurate analysis of the lower concentrations in the
 scrubber  and reactor effluents and the higher concentrations in the stripper offgas.
       The short cell was installed and the interference curve run again with the same levels
 of interference being  observed.  All further analysis indicated in this report  was made with
 the short  path UV cell unless otherwise noted.  It was decided that,  since the interference l
 are quite  low at the NO0 concentrations being used throughout most of the experimentation
                      it                                                             *
 this phenomenon would be ignored unless the  SO« concentrations were in the  0 to 500 ppm ran
 Reaction yields in future experiments will not take into account the NO, interference unless
 specifically noted.
       F.  Effect of Irrigation of Reactor with Nitrosylsulfuric Acid
       It  was apparent from the experimentation described above that the concentration of dls_
 solved NO in the liquid phase was of considerable importance in determining the SO, oxidati
 rate. It was therefore decided to irrigate the reactor with HNSOg solutions in H«SO4 rather
 than H«SO. alone.
       Before discussing the runs where  the reactor columns were irrigated with nitrosylsul-.
 furic acid, it will be of value to examine  two  runs  made with 80%  sulfuric acid irrigation in
order to gain some insight into the mechanism of the reaction. The operating data from thea
two 250 °F runs are shown in Figs. 15 and 16 and relate to Runs 27 and 28.
       In  Run 27, the three reactor columns  are irrigated for some time with 80% sulfuric a *j
at the rather  slow rate of about 30 cc/min for all three reactors (i.e., about  10 cc/min each)
While the  acid continued to drip into the reactors,  the SOg input level was set at 3100 ppm
(time zero).  The SO2 valve settings were fixed so that we could return to the same feed rate
and the feed bottle was turned off.
       For the next 1.5 hr,  NO  was fed  to the columns as attempts were made to fix the de-
sired NO and N02 feed rates.  Acid continued to drip during this time.  At the 1.75 hr mark Of

                                            38

-------
a
a

 *


I
4—>
rt
PH
t->
 CM

8
600


500


400


300


200


 100
                                                       o o
                                            8
                                                10
12
                                 NO2 concentration, 10  ppm
                          Fig. 14. NC>2 interference calibration curve
14
                                      39

-------
                                        Adjustment of NOX
                                        feed. Acid irrigating
                                        column. No SO2 feed
     Reaction temperature:  250 ° F


    Acid irrigation:  30 cc/min
      - 5400 ppm
   N02 feed

   2700 ppm
   NO feed
   1000 ppm
Reaction yield'
53.2%
                                   Add SO2 to
                                   NOX gas
                                   stream
                                                               SO.
                                                               T
                                                          NO
                                                                      SO, feed
                                                                     3100
                                                                          ppm
                                                            Reactant
                                                            concentration
                                ELAPSED TIME  (hr)
Fig. 15. Miniplant reactor experiment - SO2 oxidation. Tracing of instrumentation
        recorder input (Run 27:  evaluation of acid irrigation)
                                    40

-------
                    4100 pp
                    Reactor temperature:  250°
                    Irrigation with 20 cc/min
                       80% HSO. (intermittent)
Reaction yield 52.2%
1700 ppm SO2
                                                                             Saddles wetted
                                                                             with acid
                                                                                3550 ppm
                                                                                  1850 ppm

                                                                                4750 ppm
                         3200 ppm NO2
and NO2
feed
                                                                             R cacti) nt
                                                                             concentration
                                         ELAPSED  TIME   (hr)
       Fig. 16. Miniplant reactor experiment - S02 oxidation. Tracing of instrumentation
               recorder output (Run 28:  evaluation of intermittent acid irrigation)
                                              41

-------
this run, the SCL was injected into the gas stream at the previous level and the gas concentra-
tions  were monitored for the next hours. The SO2 level quickly leveled out and showed a reac-
tion yield of 53.2%, based on the 3100 ppm input.  When the S02 was introduced into the system
the NO level  was monitored by cutting the gain in half,  which accounts for the apparently low
reading on the chart.  The NO,, level in the reactor effluent gas did not change much during the
run.
       At the end of the hour of testing, the SOg was turned off and the NO  content measured
at the reactor input side.  It is highly significant that the NO  feed rate was about 3700 ppm
total while the reactor effluent gas during the run exhibited about 10,000 ppm of total NO
                                                                                  X
       The reasonable explanation for this behavior is that the acid on the column (which is
not moving very rapidly at 10 cc/min for each column) absorbed a great deal of NO  during
the 1-1/2 hr  of NO flow rate manipulation,  and when the SO« was added, it rapidly reacted
with the NO  in solution and quickly reached a "steady  state" reaction level. During this reac-
tion period, the oxidation of the SO™ caused the  liberation of NO due to the reduction of the
NO0 values in the nitrose.  The NO  observed in the gas during the reaction far exceeded the
   A                            X
input  NO  due to the reaction.
        X
       This hypothesis is further verified by the system shown in Fig. 16, Run 28. After the
saddles were wetted with 80% sulfuric acid prior to time zero, the NO  and S00 were intro-
                                                                 X       £i
duced into the system almost simultaneously with no acid running.  The SO« saw only gas
phase NO  and virtually pure sulfuric acid at the start  of the run. With time, however, the
         X
NO was gradually absorbed into the acid on the saddles, and the SO, reacted with this NO
at a gradually increasing rate.  When the acid was added to the system on an intermittent
(e.g.,  at the 20-min mark in the test), the reaction rate seemed to level out, but then
to increase when the acid was allowed to sit on the column and absorb NO .
                                                                     A.
       When the gas concentrations leveled out  around the 3-hr mark, it could be seen that th
effluent NO concentration in the gas phase was about the same as the input NO  level (6600
           X                                                              X
ppm feed NO compared to 6300 ppm in the reactor effluent at steady state). This indicated
            X
that the NO was going into the liquid phase to enter into the reaction at the same rate at whiCK
it was leaving and a real steady state had been achieved. If Run 27 had been continued for
several more hours, it is likely that the same steady state conditions would have been achie\»
It is interesting to note that the reaction yield at steady state in Run 28 (52.5%) was about the
same  yield as in the earlier run (27).
       Examination of these two runs makes it clear that it is not the NO  in the gas phase th
is  important to the SO« reaction rate, but the amount of NOx in solution.  It seemed obvious  at
this point to irrigate with HNSOg solutions to introduce the NOx with the acid rather than
for it  to be absorbed in the pure acid from the gas phase.
       Two runs  (29 and 30) were made to evaluate the effect of interacting flue gas with
solutions rather than sulfuric acid solutions. The nitrose  solution used contained 4.4% HNSQ
in  70% sulfuric acid.  The data from these runs  are shown graphically in  Fig. 17 (original
from all reactor experiments are in Appendix III) in comparison to data  from acid-irrigated

                                           42

-------
  100
_ Run 15'
  Wetted column
   90
   80
   70
   60
g  50
0)
M

O  40
   **»-'
   30
   20
    10
                                            Runs 29 and 30
                                            Continuous irrigation with
                                            4.4% HNSO5 in 70% H2SO4
                                            at 20 cc/min total flow;
                                            three packed reactors
                                            (~ 1.2 ft3)
     Run 27	
     Continuous irrigation
     with 80% H2SO4 at
     ~ 25 cc/min total flow
     in three packed reactors
     (~ 1.2 ft3)
      Run 9B
      Continuous irrigation with
      80% H2SO4 at ~ 30 cc/min
      in one tracked reactor
      (0.3 ft3)
              100
                         200

                       Temperature, °F
                                                300
400
   Fig. 17. Miniplant reactor experiment — SO2 oxidation. Comparison of acid
           and nitrose irrigation
                                    43

-------
 runs.  It is clear that there is a definite advantage to irrigating with nitrose as considerably
 higher reaction yields are obtainable. Most of the data available with continuous acid irrigation
 were taken with the partially packed reactor (Run 9B in Fig. 17) and cannot be directly compared
 to the data from Runs 29 and 30, which were made using three completely packed reactors (ton
 solid curve in Fig. 17); but the data from Run 27 can be used as a reference point since it
 too, was made using all three packed reactor columns (single point in Fig. 17).
       These data show a decided advantage to using nitrose solutions rather than dry reactor
 or pure acid  irrigation, although comparison of the new data with earlier runs shows up an an-
 parent inconsistency.  If the data from Run 15 (Figs. 12 and 17) is compared  with Runs 29 and
 30, it would appear that continuous nitrose irrigation is not the only way to achieve high reac-
 tion yields. It should be recalled, however,  that Run 15 was made under essentially nonstead
 state conditions.  The single packed column was wetted with acid and then allowed to interact
 with the gas feed.   The data points reproduced in Fig. 17 were the reaction yields under rela-
 tively constant conditions,  but there is no doubt that after a considerable period of time the
 acid on the column would be removed and the efficiency of the reaction decreased.  During
 time that the data  in Run 15 were taken, there must have been a buildup in the concentration
 HNSOg in the acid remaining on the saddles, and this permitted the more rapid oxidation of
       Experiments were run to evaluate the effect on reaction rate of HNSO. concentration t
 the irrigation acid while maintaining constant HgSO. concentration and constant reactor resi-
 dence time. The results are shown in Figs. 18, 19,  and 20.  It is quite evident from the grar»H
 that increasing the HNSOg concentration causes an increase in reaction rate.
       The effect of varying the H-SCK  strength while maintaining all other conditions consta
 is shown in Fig. 21. As can be noted, decreasing the acid concentration causes an increase i
 reaction rate within the range of conditions studied.
       Fig. 22 shows that the reaction yield increases with increasing reactor residence tinie
 certainly a predictable result.  In this figure, as in Figs.  18 through 21,  the data clearly sho\i.
 that increasing the acid flow rate causes an increase in reaction rate.  This has a bearing on
 the mechanism of the reaction which will be discussed later.
       The data from Figs. 18 through 22 can be combined as in Fig. 23 to give some indicati
of the overall direction  which must be taken to obtain high reaction  yields.  In this graph,  acin
 flow rate was plotted against HNSCX concentration showing lines of constant reaction yield,
constant acid concentration, and constant residence time. This method  of presenting the data
 shows the trade-off between irrigation rate and HNSOg concentration to  achieve the same rea
tion yield.  It is highly significant that below a certain HNS(X  concentration,  the yield cannot
be improved regardless of how much acid is used to irrigate the reactor. Conversely,  below
a certain irrigation rate, the yield cannot be improved even though  the HNSOg concentration
is greatly increased.
       Fig. 24 points out that, although the irrigated column is highly effective in developing
high reaction rates, the wetted columns also are quite effective in causing the oxidation and
                                           44

-------
   100
    80
3   60
QJ
_o
4-t
u
0)
CJ


 CM
O
CO
       J
    40
    20
           4.3% HNSO,
                 1.1% HNSO,
70% H2S04

2 SCFM

250 °F

3 reactors in series
                                                1
              IOO     200    300    40O     500

                        Acid flow, cc/min
   Fig. 18.  Miniplant reactor experiment. Effect of HNSOs concentration on
           SO, removal yield
                                  45

-------
   100
    80
    60
 I
 ^j
 O
 §
 C/3
   40
    20
              I
I
I
                                           1.0% HNSCL
                                         0.53% HNSCL
                  70% H2S04
                  4 SCFM
                  250 °F
                  3 reactors in series
             100     200     300
                  Acid flow, cc/min
               400
               500
Fig. 19. Miniplant reactor experiment.  Effect of HNSO2 concentration on SO2
        removal yield
                               46

-------
  100
   80
   60
c
"-  40
 CM
   20
                                     HNSOC
                          1.26% HNSO,
                                         2 SCFM


                                         250 °F
                      1
1
1
             100     200     300     400


                      Acid flow,  cc/min
               500
Fig. 20. Miniplant reactor experiment.  Effect of HNSO2 concentration on SC>2

        removal yield
                               47

-------
    100
     80
 3   60
 
-------
   100

cf
C/D
                                      250 °F
                                      3 reactors in series
                       1
1
               100     200    300     400
                        Acid flow, cc/min
               500
    Fig. 22. Miniplant reactor experiment.  Effect of residence time on SO2
            removal yield

-------
      4.0
_o
g
c
0)

I
   C/3
   z
      2.0
       1.0
           70% H2SO4
           75% reaction yield
           2 SCFM
                        • 70% H2S04
                         90% reaction yield
                         2 SCFM
                                            3 reactors in series
                                            250 °F

                                            (numbers refer to specific
                                            runs - see Appendix III)
                          38A
                                                 70% H2S04
                                                 75% reaction yield
                                                 4 SCFM
                                                                  44
                 100     200    300     400

                            Acid flow, cc/min
                                               500
Fig. 23. Interpretation of miniplant reactor experimentation.  Tradeoff between
        HNSO2 concentration and irrigation flow rate in achieving a specific
        SC>2 reaction yield
                                   50

-------
   100
    80
2
&   60

s
(H
    40
     20
                                  After one irrigated reactor and two
                                  unirrigated,  wetted reactors
                                  2 SCFM
                                  Run 46
                                  After one irrigated reactor
                                  2 SCFM
                                  Run 46
        After one irrigated reactor and two
        unirrigated, wetted reactors
        4 SCFM
        Run 47
        V
After one irrigated reactor
4 SCFM
Run 47

                  Cocurrent operation:

                  1 irrigated reactor

                  2 wetted, unirrigated
                      reactors

                  250 °F
                                 I
                I
              100     200    300     400
                         Acid flow, cc/min
                       500
  Fig. 24. Miniplant reactor experiments. Effect of irrigation and residence
          time on SC>2 removal yield
                                 51

-------
removal of SO0. This verifies earlier data and has a bearing on the eventual operating mode
             £i
of the reactor.
       Four runs were made in one column only, the first two (Runs 46 and 47) being cocurrent
operation while the other two (Runs 48 and 49) being countercurrent. The data on the cocurrent
runs were taken from analyses made at the end of the first column, although the gases  were
passed through all three columns.  The saddles in the second and third columns were still
wetted with acid from previous runs and undoubtedly entered into the reaction.  The gas effluent
from the third column was also monitored.  The countercurrent runs were made with one col-
umn only.
       Fig. 25 shows the somewhat surprising result that there is essentially little difference
between countercurrent and cocurrent operation. One might expect the countercurrent  mode to
be more effective in  generating high reaction yields, but this is not the case. A possible ex-
planation for this is the stripping of the HNSOg from the acid in the countercurrent mode befor
it gets a chance to react with the SCL entering the reactor from the other end.  This might be
offset by increasing the NO  feed in the gas phase,  which would tend to reduce the evolution of
gas from the acid.
       A series of liquid phase reactor experiments was run in the 15-ft packed miniplant re-
actor (see the data from Runs 52 through 62 in Appendix III). Runs 52  through 59 were  run in
a countercurrent mode while  60 through 62 utilized cocurrent operation.  The significant result
of this testing was that reaction yields in excess of 90% could be achieved in residence  times
under 15 sec.  Realizing that  additional testing would be eventually required to optimize the
operation of the reactor at the pilot plant level,  experimentation was halted at this point be-
cause it was clear that a reactor of practical size could be designed based on the information
already learned.
       Looking back at some of the earlier data (see final report to Contract No. CPA 70-5Q)
it is possible to explain some of the anomalous results in terms of new knowledge.  When the
plant was operated such that there  were long residence times in the sample lines, the reaction
rate apparently increased with time in much the same manner as shown in Run 28 (Fig. 16).
What must have been happening was the condensation of sulfuric acid in the  sample lines fol-
lowed by the absorption of NOx in the condensate. The SOg-bearing gas came through the sam-
pie lines and reacted with the nitrose on the walls the same way it reacts with nitrose on the
saddles. Once steady state was reached, an apparently high reaction was achieved which \va
really occurring almost completely in the sample lines.
       During the testing described above,  these experimental artifacts were avoided.  The
lines were  well heated and not easily contaminated  (and were easily cleaned when there wag
condensation).  The residence time in the sample lines was down to about 2  sec because of
high sample flow rates and the low volume of the short UV analysis cell.  The instrumentatio
behaved very well and data were both reproducible  and reliable.
       In looking over this data, it is clear that the nitrose irrigation concept represents a
new approach to the problem  of obtaining high SOg oxidation rates. There will be a discusaio
                                           52

-------
   100
a   fin-
>>
o
(-1

8
                                    Cocurrent
                                    Run 46
                            Countercurrent
                            Run 48
                                     2 SCFM

                                     73% H2S0

                                     1% HNSO.
                                             5
                                     250 °F

                                     1 reactor
    20-
                                I
                                         I
              100    200    300    400
                       Acid flow rate,  cc/min
                                               500
  Fig. 25. Miniplant reactor experiments. Effect of countercurrent versus
          cocurrent reactor configuration
                                53

-------
 on reaction mechanisms and an analysis of a proposed flowsheet, including this new concept
 later in this report. At this stage in the analysis of the reactor,  it is safe to say that a more
 complete understanding of the reactor has been achieved, and it should be possible to continue
 to develop the process to the point where SO. can be removed from dilute gas streams in a
 practical manner.
        G. SO, Oxidation Reaction Mechanisms
        It was originally assumed that the overall chemical reaction occurring in the reactor
 was a gas phase oxidation:
         NO2 + SO2 - NO + S03

 followed by,  or simultaneously occurring with, hydration to form H.SO..  Experimentation
 during the early phases of this contract showed that this reaction does occur, but at too slow
 a rate to be economically feasible.  However,  subsequent testing showed that irrigation of the
 reactor with sulfuric acid or nitrose solutions gave considerably higher yields at  equal resi-
 dence times,  and the most recent testing indicates 90% yields in less than 15 sec  residence
 time. In order to more fully understand the process and thereby be able to further optimize
 the reactor stage, an in-depth analysis of the liquid phase reaction mechanism was  initiated
       Two earlier studies,  which are of direct relevance to the oxidation of SO. in the liquid
 phase by nitrogen oxide species in equilibrium with gas phase NO  at 25 °C, are discussed
                                                             A
 here. The relevance of this work to our results at higher temperatures is clarified.
       Berl,  et al.  report the results of a study entitled, "The mechanism of the oxidation
 of SO2 by oxygen in the presence of nitrosylsulfuric acid."  The experiment involved the vig-
 orous shaking together of 20 ml of 0.1 molar nitrosylsulfuric acid in sulfuric acid (20 to 80 wt
 %) with approximately 600 ml of a gas mixture consisting of 1/3 oxygen and 2/3 sulfur dioxid
 at approximately 25 °C. The rate of uptake of SO, was measured and found to be constant for
 any given sulfuric acid concentration. This rate was plotted versus sulfuric acid  concentratio
 and found to peak sharply at 57.5 wt % HgSO..  Further studies up to 90 °C indicated similar
 results.  The rates of SO. conversion were much lower in the absence of a  liquid  phase.
           2
       Seel  reported the results of a study entitled, "The nitrous acid-nitrosyl ion equilib-
rium in aqueous sulfuric acid." A very  careful ultraviolet spectroscopic study of nitrose sol
tions at 25 °C indicated that,  whereas nitrous acid is the predominant nitrogen species at sul
furic acid concentrations less that 50 wt % HgSO,, nitrosyl ion (ionized nitrosylsulfuric acim
is the predominant nitrogen species at sulfuric acid concentrations greater than 70 wt % H sr»
In the midrange, nitrous acid exists in equilibrium with hydrated nitrosyl ion, FUNO.4, whj  .**
is, of course, the same as protonated nitrous acid.

        HNSOg  ^  NO+ -I-  HSO4~

        N0+ + HS04~ + H20 *  H2N02+ + HSO4~  *
                                            54

-------
The concentrations of HNOg and HgNOg  are equal at 55 wt % HgSCh.  At 59 wt % H-SCK, the
conversion to H-NCL  is 90% complete.  As the sulfuric acid concentration is further increased,
the H9NO«  becomes less and less hydrated and thus becomes more correctly described at
N0+ (solvated by H2SO4).
       Thus, at 57.5 wt % H2S04:
              1.  Berl observed the highest rates of conversion of SCL to HLSO,
              2.  Seel observed that H-NCL  is  the predominant nitrogen specie in nitrose
                 solutions.
One may reasonably conclude that H-NO,  is the nitrogen specie in nitrose solutions which is
responsible for the rapid conversion of SO, in the lead chamber process and in the Tyco SO»
reactor.
       In making a statement concerning the optimum nitrose concentrations for the Tyco SO,
reactor, one must consider the effects of increasing the temperature  from about 80 °F to the
range of 200 to 300 °F. At 80 °F,  0.1 molar HNSOg, and 64 wt % H2SO4, the partial pressure
of nitrogen oxides is about 0.02 atm whereas at 200 and 300 °F, the corresponding partial pres-
sures are 0.13 and 0.41 atm.  Berl's experiments at room temperature were carried out at
constant HNSO.. concentration whereas our experiments at elevated temperatures are more
              D
closely approximated by conditions of constant vol % NO  in the gas phase. It is entirely pos-
                                                    x                                4
sible that,  at our operating temperatures, we may obtain the highest concentration of HgNOg
(and thus the highest rate of oxidation of SO,,) at some concentration of sulfuric acid higher
than 57.5 wt %.
       We assume that the major portion of the SO0 oxidation occurs in the liquid phase by
                                           +   *
reaction of dissolved SO« and nitrosyl ion, NO . The reaction is assumed to be irreversible,
i.e., the reaction products do not  inhibit the oxidation of SO-. For our  model we postulate the
following processes and possible slow steps:
         (SO2) gas                =   (S02) dissolved                                (D
                                     diffusion gradients in gas phase                 (la)
                                     diffusion gradients in liquid phase               (Ib)
         NO 4 NO2 4 H2SO4       =   2NO"1" 4 2HS04~ 4 H£O                          (2)
                                     diffusion gradients in gas phase                 (2a)
                                     diffusion gradients in liquid phase               (2b)
         S02 4 N0+ 4 H20        =   NO 4 H+ 4 HS03                               (3)
         HSOg 4 NO+ 4 H20       =   NO 4 H2S04 4  H+                              (4)

To make the situation mathematically tractable and to allow us to develop a physical model
which closely approximates a packed column, we find it useful to introduce reasonable sim-
plifications into the model. We will verify by direct calculation that our simplifications are
reasonable.
                                            55

-------
        The first simplification we propose is that we be able to ignore the diffusion gradient
 of SO, in the gas phase.  A typical case which we may use for the purposes of our calculation
 is 3000 ppm SOg at 150 °C over 80 wt % HnSO,.  We may obtain an extrapolated value for the
 solubility of SO, in 80 wt % H,SO4 at 150 °C using the data of Kuznetsov.   Using the data for
 79 wt % H2SO4 and doing a least-squares fit of log (CSQ )  versus 1000/T°K, one obtains statis-
 tical constants which, in turn, yield the value of 1.00 cc SO, dissolve per cc of sulfuric acid
 solution.
                                                   4
        Jost gives estimates for diffusion coefficients.  We find that  for gases,

         D  =-££
              P
 where f = 1 approximately,  rj = viscosity, and p  = density. At STP, D values normally fall in
 the range of 0.1 to 1.0 cm /sec.  We  also find that D is proportional to Tn  where n is in the
 range 1.5 to 2.0. Thus,  at 150 °C we may estimate that D is  approximately equal to 1
 For liquids of the viscosity we are concerned with, D is approximately equal to 10
        To calculate SO, flux we use Pick's first law,
                      £t
         J =  -D
 In the gas phase we assume complete depletion of SO, and a diffusion layer thickness of 0.01
 cm, which results in an SO2 flux of 8.6 x 10~  moles/(cm -sec).  In the liquid phase we as-
 sume complete depletion of the SO2 and the same diffusion layer thickness which,  in turn, re
 suits in an SO9 flux of 8.6 x 10~    moles/(cm -sec).  It is apparent that the limiting flux
                                                                -119
 in the liquid phase.  Thus,  even though the maximum flux of 8.6 x  10     moles/(cm -sec)
 might be occurring in the liquid phase, this is only 0.001% of the maximum flux in the gas
 phase.
       The second simplification we propose is that we be able to ignore step 2  as a rate
 ing step.  The solubility of nitrosylsulfuric acid (0.1 moles/liter for the case given above)
 much greater than the solubility of SO, (8.6 x 10   moles/liter for case given above) for  the
 conditions prevailing in the reactor. There is, thus, a greater driving force for the formati
 of nitrosylsulfuric acid than for dissolved SO9.  We have confirmed experimentally that NO
                                                                                      X
 uptake is very rapid in the reactor. This allows us to disregard step 2 as being rate limitin
 The third simplification we propose is that we eliminate reaction 4 as a rate limiting step.  if
 either reaction 3 or  4 is rate limiting, one would expect that reaction 3 is slower because of
 fact that one does not observe high concentrations of any reaction  intermediate,  such as
We thus dismiss reaction 4 as being rate limiting.                                         *
       Our simplified model now consists of the irreversible bimolecular reaction of one
slightly soluble gas phase species with a dissolved, rather higher concentration liquid phase
species.  To evaluate this model for our system,  a particular configuration was chosen whj .
is compatible with the experimental work that was done. The system chosen was a packed
column with countercurrent gas/liquid flow.  The input SO2 level is assumed to be 3000
                                            56

-------
and the input NO, level to be 3000 ppm at a gas flow rate of 4 SCFM.  The acid feed is assumed

to be 80 wt % H2SO4 with 0.0623 M HNSOg (at 150°) present and a liquid flux of 0.17 gpm. The

HNSCL concentration of 0.0623 M was chosen since it is the equilibrium concentration for 3000
     5
ppm each of NO and NO, in the gas phase at 150 °C in 80 wt % sulfuric acid, as computed from

the data of Berl and Saenger.

       The column utilized was 4 in. in inside diameter, packed with 1/4-in. Intalox saddles.
           fi                               23
Danckwerts  gives an effective area of 1.4 cm /cm  for superficial flow rates of 0.2  cm/sec
                                               7
on a 1/2-in. packing. From U.S. Stoneware data,  we see that a dry area difference of ~ 1.5-
                                             2    3
fold exists, and thus an effective area of 2.2 cm /cm  is expected and will be used in our cal-

culations.  (Note:  In this region, the effective interfacial area is nearly a linear function of the

superficial liquid flow rate (cm/sec so that  we may easily refine our effective area estimate

when we experimentally determine the superficial liquid flow rate).
                                                                                     C
       The calculation we  wish  to make involves the solution of Eq. (5-64) of Danckwerts:
where:
              D.K.B0
         M =   A  *   ;  E  =  l 4      A* )  :  R = KA*D
as:

         E     =   enhancement factor,

         E     =   enhancement factor when rate of reaction is controlled by diffusion,
          i
         M     =   dimension less time quantity,
                                                 2
         DA    =   diffusivity of dissolved gas A (cm /sec),
          A                                2
         Dn    =   diffusivity of reactant B (cm /sec),
          B
         k0    =   second order rate constant for reaction of A (i /g mole sec),
          2
         k     =   liquid film mass transfer coefficient (cm/sec),

         A*    =   concentration of dissolved gas A at interface,  in equilibrium
                  with gas at interface (g moles/cm3),
                                                              3
         B°    =   concentration of B in bulk of liquid (g mole/cm ),

         Z     =   number of moles reacting with each  mole of A, and

         f{     =   average rate of absorption over contact time t.

        For the solutions of these equations, we need estimates of  several parameters. The

 state-of-the-art  in estimating diffusion coefficients involves extrapolation of room tempera-

 ture aqueous data by assuming
                                             57

-------
         Dw
        -=r- = constant,
                          2
 where D = diffusivity in cm /sec,  ^ = viscosity in centipoises,  and T = temperature in °K.
                                                                       _C   O
 Typical diffusion coefficients for ions and slightly soluble gases are 1.5 ± 10  cm /sec at
      4                                              9
 25 °C.   We may extrapolate the data of Schwab and Kolb  and obtain a value of 16.2 centlpoia
 for the viscosity of 80% H2S04 at 150 °C.  The viscosity of water is taken as 1 centipoise at
 25 °C. This leads to D = 1.3 ± 10~6cm2/sec for NO+ or SO2 in  80% H2SO4 at 150 °C.
       As mentioned earlier,  B° (concentration of NO ) is taken as 0.0623 M.  We assume A*
 to be the saturation value or the solubility of SOg. From extrapolation of the data of Kuznets   '
 to 150 °C and the assumption of the validity of Henry's Law, we obtain;

         A* =  1.16 x 10~4m
                                        _2
 From Danckwerts, we obtain k, ~0.6 x 10  cm/sec at 25 °C in water on 1/2-in. Intalox sad-
 dies.  From Danckwerts and also Gehlawat, et al.,   it is shown that k,  is proportional to D
 This leads to k,  = 1.16 x 10~  cm/sec at 150 °C in 80  wt % H^SO..   For k«, the bimolecula-»-
              L,                          „              £  4       Z             ««»*• re_
 action rate constant,  we assume a value ^ 10 f /mol-sec.  (This is equivalent to saying that k
 bimolecular reaction is appreciably faster than the diffusion process.)
       Using the parameter estimates obtained above, we calculate that E,, the instantaneou
 enhancement factor, is equal to 269.5. Similarly, M ^ 2.675 x  10  . From Danckwerts6 we
 confirm that E = E..
       Finally,  R, the average rate of absorption of SO,,, is found to be 3.62 x 10   mol/crr^
 sec.  Now that a value for R at the gas inlet to the reactor is determined, we may begin to c i
 culate the conversion yield. The SO2 flux is 2.528 x 10   mol/sec and the NO"1" flux is
 8.028 x 10~4mol/sec.
       We choose to treat the problem by calculating  the amount of time necessary to reduc
 the SO, level to 99.9% of its input level and then repeat this process until the desired conver-
 sion is attained.  Before completing this calculation, we find the residence time for a typical
 column.  For a 16-ft column, the residence time  is 10.26 sec (Intalox  saddles 75% void
                  4
 void volume 3 x 10  cc;  gas flux 2925 cc/sec at 150 °C).
       The rate of SOg absorption is:
                ,-8        mol
        3.62 x 10
                     cc (total)  - sec
          2                           ~8
for 2.2 cm /cc (total) and for 6.482 x 10   mol SO2/cc (total volume) in the gas phase.
that because of the applicability of Henry's Law and the form of the Danckwerts rate equati
the rate of SO2 absorption (mol/sec) is directly proportional to its concentration in the gas
phase (mol/cc). Thus, the rate given above converts to:
              fraction SO,
                                           58

-------
absorbed. This is the differential rate law for our column.  To obtain the integrated degree of
conversion,  we need to sum the results for slight degrees of conversion as shown below.
       To remove 0.1% of the SCL requires  ^'A*  = 8.13 x 10*  sec = r  sec. At the end of
T sec,  99.9% of the initial SO2 is present.  At the end of n • T sec, 100(0.999)"% of the initial
SO is present. We may  calculate % conversion for various residence times.  Such results are
   2
given in Table III.
       We may continue our calculations and compute  another table corresponding to  conver-
sion at 1/10 of the diffusion limited rate. This would be applicable if the bimolecular reaction
                              C
was slower.  From Danckwerts,  we see that the corresponding E factor of 26.95 occurs for
M = 1600. We may calculate k, and determine conversions as shown in Table IV.
MKL
= 6.0 x 107
- fi n * 1 n*
cc
g mol sec
S.
       Thus,  it can be seen that 90% conversion of SO, will occur in the range of 2 to 18 sec
residence time, and presumably much closer to the lower value. A reasonable series of as-
sumptions of:
         DD 20% lower
          o
         B°  20% lower
         DA 20% higher
          A
         A* Same
         kL 20% lower
provides the results shown in Table V of 90% conversion in 4.4 sec residence time and 99% con-
version  in 8.8 sec.
                                            59

-------
Table III. Degree of Conversion of 803 at 150 °C in 80% Sulfuric
          Acid for Various Residence Times with Diffusion of
          SC>2 Being the Rate Limiting Step (See Text for Full
          Details)
Residence
Time
(sec)
8.13 x 10~4
8.17 x 10~3
0.0857
0.564
1.872
3.75
5.62
7.5
10.00
Column
Length
(ft)
0.0012
0.0128
0.13
0.88
2.93
5.85
8.76
11.7
15.6
% so2
Remaining
99.9
99.0
90.0
50.0
10.0
1.00
0.100
0.00988
0.00045
%so2
Conversion
0.10
1.00
10.00
50.00
90.00
99.00
99.90
99.99012
99.99955
                              60

-------
Table IV.  Degree of Conversion of S02 at 150 °C in 80% Sulfuric
          Acid for Various Residence Time with Rate of Conver-
          sion Equal to 1/10 of the Diffusion Limited Rate (See
          Text for Full Details)
Residence
Time
(sec)
0.00813
0.0817
0.857
5.64
15.39
18.72
Table V.
Residence
Time
(sec)
0.00192
0.0193
0.202
1.35
4.42
8.84
Column
Length
(ft)
0.012
0.13
1.3
8.8
24.0
29.3
%so2
Remaining
99.9
99.0
90.0
50.0
15.07
10.0
% so2
Conversion
0.1
1.0
10.0
50.0
84.9
90.0
Degree of Conversion of SC>2 at 150 °C in 80% Sulfuric
Acid at Various Residence Times Using Modifying
Assumptions Presented in Text (p. 59)
Column
Length
(ft)
0.003
0.03
0.31
2.1
6.9
13.8
% so2
Remaining
99.9
99.0
90.0
50.00
10.00
1.00
%so2
Conversion
0.10
1.00
10.00
50.00
90.00
99.00
                              61

-------
VI. SCRUBBER EVALUATION
       A.  Initial Concept
       As discussed in the introduction to this report,  the purpose of the scrubber is to remove
the oxides of nitrogen from the reacted stack gas, leaving the reactor stage after the oxidation
of the SO,.  This  is to be accomplished without removing water from the gas stream. The
evaluation tests run during this contract were aimed at establishing two capabilities of the
scrubbing system: absorption of NO at the high concentrations present after SO., oxidation by
NO0,  and absorption of low concentrations of NO  that would be present in raw flue gas. In this
   2                                         x
manner the Catalytic Chamber Process could be evaluated for combined NO /SO0 removal as
                                                                      X    ft
well as NO  removal alone after the SO» was removed in a prior gas treatment  step.
          X                          ™
       Prior experimentation, as discussed in the final report to Contract CPA  70-59, had
established that a 4-in. column packed  with 8.5 ft of 3/8-in. Intalox saddles could absorb about
65% of the NO from an equimolar mixture of 3000 ppm each of NO and N00.  Extrapolation of
             x                                                        &
this data indicated that a column about  30-ft high would absorb about 97% of the  NO . Based on
                                                                             X
this work,  the miniplant was used to evaluate the scrubber concept for absorption of NO  from
                                                                                  X
dilute and concentrated gas streams.
       B. Experimental Procedures
       The miniplant was set up as in Fig. 6 with two packed 4-in. diameter scrubber columns
in series containing about 27 ft of 3/8-in. Intalox saddles. The three Teflon-coated stainless
steel strippers were set up in parallel  with the scrubber effluent acid being sent to the bank
of strippers for denitration.  In this manner the scrubber system could be operated continuously
over a long period of time.  It was decided that at the initial stages of scrubber  evaluation,
there was no need to run the reactor stage since the reactor work had already been completed
(see Section V of this report). Therefore, the gas that was fed to the bottom of the large scrub-
ber was composed of a simulated reactor off-gas containing about 6% water and approximately
equimolar quantities of NO and NO« totaling 6000 to 7000 ppm  NOx for the first series of tests.
The gas was passed through the large scrubber into the small  scrubber and then to the stack.
It was analyzed at three points: before and after the large scrubber and after the small scrub-
ber. (At a later stage of experimentation, the gas was also analyzed half way up the large
scrubber.)
                                            63

-------
       Nitrose-free sulfuric acid was fed to the top of the small scrubber with the effluent from
 this column being fed to the top of the large scrubber.  Acid from the bottom of the large column
 was fed to the three strippers in parallel for denitration. The acid was analyzed at the bottom
 of each of the two scrubbers and as a composite at the bottom of the strippers.  Air was fed to
 the strippers (at the bottom) and the effluent dumped to the stack after being analyzed for its
 NO  content.
   A.
       Temperatures in the system were controlled by externally mounted heating tapes and
 column mantles. The goal in temperature control was to feed the acid to each of the columns
 at the required temperature of column operation and use column heaters only to maintain the
 temperature.  It was felt that it would be too difficult and inefficient to heat the acid while in
 the columns, especially in the 12-in. diameter strippers.
       All temperatures were monitored on the two 24-point recorders while the gas analysis
 was performed on the duPont ultraviolet photometer and the Beckman infrared analyzer as in
 previous work.  The acid was analyzed in batch tests using a hydrometer for H-SO, concentra-
 tion and potassium permanganate titration for HNSO, content. (See Appendix II for details of
 the KMnO. titration.)
       C.  Initial Experimentation — Parametric Study
       In order to produce a useful amount of data in a short  period of time, a parametric
 study was developed by Tyco and the Office of Air Programs (GAP) of EPA, which selectively
 varied certain key variables so as to obtain sufficient information in a series of twenty runs to
 develop a good  feel for the scrubber operation.  An outline of  the study combined with a data
 sheet is shown  in Fig. 26.  This study was oriented around a combined NO^SO, removal pro~
 cess, and high  levels of NO were used in the feed stream.
       The first runs were made under the average conditions of the parametric study (see
 column 11 of Fig. 26).  The raw data of these runs (nos. 67 and 68) are shown in Appendix IV
 as are all other scrubber/stripper experimental data.  Run 69 was planned and then omitted.
 Runs 70, 70 (repeat), and 71 were run under the same conditions as the tests performed durin«»
 the preceding Contract No. CPA 70-59, which showed approximately 65% scrubbing in an 8.5 ft
 column.  Run 72 was a followup to 71 in an attempt to evaluate a higher L/G.
       It is clear from examination of the data that the high scrubbing efficiencies expected bv
 extension of earlier tests during the preceding contract were  not achieved in any of these initial
 experiments. Where the data is most reliable,  consistent readings show no better than 75 to
 80% scrubbing instead of the anticipated 98%.  (See Runs 67-72 in Appendix IV.) Confirmation
of the analysis  is obtained from two sources: NOx  material balance and consistent readings
over a long period of time.  The material balance errors of closure are  shown in the table and
are initially quite low (under 10%) in the first two runs, although later runs are more erratic
More will be said about this later. The consistency of the readings is shown by the subruns
given by a letter designation in the table. These subruns show separate  data points taken as
the run progressed and, for the most part,  imply a continuous operation of the plant at a
set of conditions.
                                            64

-------



(tails Lwvl 1
TNA
CNA
LjG
GHSVHD
'^'Nq,' F.G.
1CSQ[' F.G.
Conflg.

O ~ r.
x F.C.
Acid
op
16/hr-ft2
mole/mole
hr'^STP)
ppro
ppm
250
915
3 1
6.4
2000
0
- Serics(2)
Units
SCFM
GFM
SCFM

1 5 3 O
0104,
0.4,0.6,
Kun Nunhrr








l^evel 2 Average
340
3600
6 1
33.8
10000
500
Parallel(3)
Levels
6 1 12 O (5 6)
(0 25)
2. 1,3.1, (9. 85,1.
275
2290
4 6
2O 1

6000
250
SorP



.25)
275
2290
4 6
2O 1

6000
250
S

5.6
O 25
1 25
250 :*«> 2SO 300 300 251) 300 250 275 275 300 250 300 250
915 3600 915 3600 915 3600 915 3600 2290 2290 3600 915 3600 915
31 61 61 31 6.1 31 31 61 46 46 61 31 31 61
64338 33 8 64 64338338 64201201338 64 64 33 8

2OOO 2000 2000 2000 10OOO BOOO 10000 10000 600O 6000 UOOO UOOO ttOOO UOOO
0 0500500 0 0500500250250500500 0 0
SSSSSSSSSPPPPP

3.0 6l 15120 15120 30 61 56 56 61 3.0 12 0 1.5
01 O4 01 04 01 04 01 04025025 04 01 04 0. 1
04 21 21 04 04 21 21 04125185 31 0.6 06 3.1
25C
3600
3 1
33 8

2000
500
P

12.0
0.4
3.1
300
915
6 1
6 4

2000
500
f

1 S
0 1
0 6
250
3600
6 1
6 4

2000
0
P

6 1
0 4
0 6
31X1
915
1 1
33 8

2000
0
P

3 0
0 1
3 1
275
2290
4 6
20 1

600O
250
P

5 6
0 25
1 85
L/CHD
       3
[HNSOS]3'
  hr"1    0.14,0.22,0.58,0.86,(0.36.0.54)  0.54 0.22  0.86  0.22 0.86 0.22 0.86 0.22 0.86 0.54 0.36 0.58 0.14 0.58 0.14 0.58 0.14 0.58 0.14 0.36
16/hr-ft2  81,160,325,640, (302)             302  160   325    81  640   81  640  160  325  302  302  325  160  640   81  MO   81  325  160  302
16/hr-ft2  37,110.148.442,(92.5.270)         270  110   442   110  442  110  442  110  442  270 92.5  148   37  198   37  148   37  148   37 92.5
16/hr-ft2  0.27.1.34.1.41,6.97,(4.14.0.84)  0.84 0.27  1.41  1.41 0.27 0.27 1.41 1.41 0.27 0.84 4.14 6.95 1.34 1.34 6.75   95 1.34 1.34 6.95 4.14

mole/mole ^iVw'"^'?^'!)5'23"0'     M'2 23-°  17'5   *'* 92-* 23"° 17'5  4'4 92'' M-2 22'9 "•' 1S 4 6'"4  3-° "-9 15'4 M'4  3 ° 22 9
  %V    0.14-19.8,(2.99,4.46)            4.46 1.48  0.57  0.14 5.95 3.77 5.65 1.42 15.1 4.46 2.99 1.75 4.96 19.8 0.49 0.77 0.51 2.01 0.19 2.99
  SgW    0.03,0.16,0.40,0.79,(0.32)       O.32 0.16  0.08  0.08 0.16 0.40 0.79 0.79 0.40 0.32 0.32 0.40 0.79 0.79 0.40 0.16 0.08 0.08 0.16 0.32
Tyco Mini -Flam Data
Date
I-., i °F
'NA r
TEJT> °F
QF.G SCFM
QAir SCFM

2 "*
3
rcu~cn 1 1 91 W
3
1
2
3 36V
|Curu F_G_ |juu
1
2
[CSQA] F.G. pnni
1
2
3 5tv
(Cuo/u H.G. 56 V
1 "
3
[CHjol Air %V
























'



1















































































































































































1
NOTES:
1. KEY: 1- Top of NO,, absorber; 2- Middle
3- Top of HNSO5 decomposer; F.G
2. VCatalyst= 3.72 ft3 (series) ; 5. 57 ft3 (
3. AHD= 0.70 ft3 (series); 2.09 ft3 (paral
4. Calculated, assuming that [Cg^sOsl ~ ((























































































































































>
of N(
Flu
>arall
el).
=N01 =





















}x absorber
s gas.
el).
= [CN021 =










































0



















	



=



















                                      Fig. 26.  Scrubber/stripper parametric  study and data sheet.

-------
       Two major problems appeared which contributed to the difficulty of operation and, in
part,  to the low scrubbing efficiency. First of all, there was a great deal of difficulty in a-
chieving continuous operation due to frequent pump failure. This was before the more reliable
peristaltic pumps were installed. More pertinent to the scrubbing problem  was the presence
of a relatively high concentration of dissolved iron and chromium salts. The metal ions were
clearly obvious in the acid as seen by the bright coloration of the acid while the fluid was hot
and the presence of a light-colored  precipitate throughout the system when the acid was cooled.
Appendices V and VI of this report discussed in detail the source and influence of the dissolved
metals on the efficiency of the scrubbing operation, but there did appear to  be a connection
between scrubbing efficiency and metal concentration in the acid.
       Examination of the data for Runs 68 through 72  shows that as each run progressed,
there was a decrease in scrubbing efficiency.  This was due, in part, to the increase in tem-
perature in the scrubbing columns,  but even where the temperature was relatively constant
there was a continued decrease in scrubbing. It is hard to evaluate the start of such an effect
due to the way the system was brought up to operating conditions. Fresh acid was put in the
system and the whole plant started up at room temperature.  The acid was pumped around the
entire loop through both the scrubbers and the strippers.  When the plant was close to operating
temperatures, the NO was introduced into the gas feed and the experimental data taken. By
                     A
this time the acid had achieved the deep, bright green that was indicative of the relatively high
concentration of chromium ion.  Therefore, it was impossible from the data available to deter-
mine  the scrubbing efficiency of uncontaminated acid under the desired operating conditions.
       The source of the metal ions was not immediately apparent.  Due to  the failure of the
Hastelloy B pumps, it was at first assumed that the corroding pumps were the  source;  but after
it was determined that the metal ions were primarily chromium, this source was ruled out
(there is no chromium in Hastelloy  B). The only chromium in the system was in the Carpenter
20 of  the piston pumps (which were  not always in service during these runs  and had not shown
a tendency to corrode this severely in previous runs) and  in the stainless steel of the several
fittings used to connect the pumps into the glass pipe system.  It was not until the end of the
experimentation that the interior of the strippers was examined, and it could be seen that the
Teflon coating had undergone massive failure and the chromium was indeed coming from the
badly corroded stainless steel walls of these columns.  (For a more complete discussion on
corrosion of pumps and  strippers, see Appendix VI.)
       This problem with the coated strippers created a requirement for new stripper columns
New strippers were installed as shown in Fig. 6.  The size and shape of the new columns was
the same as before, so there was no change in operation.
       After the new strippers were installed,  Runs 74 through 81 were made,  which indicated
that under certain conditions it was possible to reduce the scrubber effluent to less  than 150 Ppm
total NO   (see Appendix IV,  Run 74).
       At this stage in the experimentation, the orientation of the program was shifted to low
concentration removal of NOx>  A new parametric study was used to determine the run conditiOn
                                            66

-------
(see Table VI), with NO and NOg being introduced at 250, 500, and 1000 ppm each.
       As indicated in Table VI, the stripper configuration was changed from three parallel
columns (1 ft by 4 ft high) to two columns in series (1 ft by 8 ft high). A diagram of series
stripper configuration is given in Fig. 27.  An in-depth discussion of stripper performance is
given in Section VIII of this report.
       D.  Mathematical Analysis of Experimental Scrubber Data
        In this section, we present a mathematical treatment for the scrubber /stripper experi-
ment.  We also present a short discussion regarding scrubbing mechanisms. Actual data reduc
tion follows at the end of this section and in Appendix VII.
       We consider the experimental data to  be a function of column height, column cross  sec-
tional area, and initial concentrations. Models of first and second order processes are devel-
oped.  Equimolar NO and NO™  are assumed for the beginning of each run when scrubbing is
other than pure first order.
        For first order scrubbing,
where:
         P ,„  =  instantaneous concentration of NO in the bulk gas (atm),
          NO
         t     =  time (sec), and
         K    =  first order rate constant
For second order scrubbing,
                                   and
                                                                                      (3)
            3t      K2PNOPNO,  '
                              u

 For first and  second order processes,
                    .3
         flow  rate (^J =  -r  = G.                                                   (5)
         volume (ft3) =  V = Ah,

         time (sec) = t = — = AhG  » and                                              (6)

         dt=  AG^dh                                                                  (7)
                                            67

-------
             Table VI.  Parametric Study and Supplemental Work Plan
Run
No.
82P
83p
84?
85p
86P
87P
88
89
90
91
92s
93s
94s
95s
96s
97s
98
99
100
101
102
Acid
Flow
GPM
0.25
0.40
0.40
0.10
0.10
0.25
0.20
0.40
0.10
0.10
0.25
0.10
0.40
0.40
0.10
0.25
0.25
0.25
0.62
0.25
0.25
Main
Gas Flow
SCFM
4.9
11.7*
6.0
1.5
2.9
4.9
2.9
2.9
6.0
11.2
4.9
2.9
6.0
11.7*
1.5
4.9
11.7**
4.9
4.9
4.9
4.9
Stripper
Gas Flow
(Total)
SCFM
1.9
3.1
0.6
3.1
0.6
1.9
3.1
3.1
3.1
3.1
0.9
1.6
1.6
0.3
0.3
0.9
0.9
0.9
0.9
0.9
0.9
L/G
Moles/
Moles
4.6
3.1*
6.1
6.1
3.1
4.6
6.2
12.4
1.5
0.8
4.6
3.1
6.1
3.1*
6.1
4.6
1.9**
4.6
11.4
4.6
4.6
 Scrubber temperature:   275 °F         Flue gas composition:
 Stripper temperature:   290 °F        „ n                „*
                                    _2_       NO      WU2

                                     6%      250 ppm   250 ppm
                                             500 ppm   500 ppm
                                            1000 ppm  1000 ppm

 p Parallel strippers parametric study.
 s Series strippers parametric study.
 * Actual gas flow was 8.8 SCFM, giving an L/G of 4.2 mole/mole.
** Actual gas flow was 8.8 SCFM, giving an L/G of 2.6 mole/mole.
                                    68

-------
          Gas exit
Acid feed
4-ft column
sections
         Thermocouple lines

         Charcoal


       Saddles
      Redistributor plate


        Support plate


         Charcoal
                                                       Saddles
                                                      Support plate
                                             Air feed
                                         Acid exit
                   Fig. 27.  Series stripper configuration.
                                    69

-------
for constants A and G.
      Eqs. (1) through (4) become

          dpNO   AK1PNO
                   AK1PN02
           dh
          dpNQ
                = - G - ' and                                       (10)
         dpNO     AK2PNOPN02
                =  - G - '                                          (U)
For the second order process, assume that

       PNO = PN02                                                        (12)


and Eqs. (10) and (11) become


                 AK2PNO
       - dpNO ' -4^   and                                             (13)


                  AK2PN02
       ~ dpN02 = — G - '                                              (I*)
Integrating the first order NO equation,
           P0
            NO   _x
         /P0    PNO dpNO =  '
          *NO
          f
         Jp
       M-£r) • K.AHtrl  •                                             «•>
Integrating the first order N02 equation,


                    =  +KiAHG
                                       70

-------
Integrating the second order NO equation,
        fPNO    2           AK    fH
       J  Q      PNO dpNO=  -— JQ   dh      and
         PNO
        -jj-  -  — =  -KgAHG'1 .                                            (20)
        PNO
Integrating the second order NO, equation,
                                   .                                             (21)
                PN02

Solving for expected P values:
    First order - NO

        PNO=PNOexp(~KlAHG~1} '                                             <22)
    First order - NO2

        PNO  =  PNO  exp (-KiAHcrl) •                                           (23)
            2       2
   Second order - NO

                   P°NQ
        PNO
   Second order -
                                                                                (24)
                    PNOn
        PN02  = ^p^K.AHG-1   '

       Mechanistic tests that seem reasonable are easily devised.  First, plot

              PNO
            }  PNO
versus AHG~ Iog1f.e, and in the region where the plot is linear,  NO is being removed by a
first order process [cf. Eq. (17)].  The first order rate constant, K., is given by the slope.
A similar plot may be made for NO2< Second, plot
                                                                                (25)
                                          71

-------
versus (-AHG   ) and in the region where the plot is linear NO is being removed by a second
order process [cf. Eq. (20) ].  A similar plot may be made for
       Note that in the foregoing tests the intention is to plot all of the data on four plots:
              1.  First order NO plot.
              2.  First order NO2 plot.
              3.  Second order NO plot.
              4.  Second order NO, plot.
Putting all of the runs on  only four plots will have the effect of averaging the data.  By visual
inspection one may determine whether or not the data falls into any significant groups.  When
this has been ascertained, one may perform meaningful, weighted, least- squares fits of
selected data groups to obtain first- and second-order rate constants applicable to various
scrubbing conditions.
       When rate constants have been calculated, one may calculate percentage scrubbing for
various scrubbing conditions and column geometries on the basis of first- or second-order
constants [Eqs. (22)  through (25) ]. For a somewhat more precise treatment, one may derive
rate equations for simultaneous first- and second-order processes.
       If NO were removed by second-order processes only and NO- is both first- and second-
order processes, we would write;
                   = —_	   ,                                                (8)
and
            dpN09    AK1PNO()
                 &            ft  ,             et
        	dh—  = 	G	  +	0	                                     (26)
       We may solve these equations only  if we can obtain an expression relating p   and jx
Experimental observations tend to indicate that except at very low NO levels, we may validly   '
use the approximation:
        PNO = PN02 '                                                               (12)

For NO, we obtain:

        PNO = PNO exp (~K1AHG  )  '                                                (22)

For NOg,
        /»D^,~             NO0               _.,  /»H
                                                     dh
 /»n              KNO«                ,  /•
 f PN02   	^ 2  ,	 =  -AC"1  f
 I                        2                I
J 0       K1PN02 4 K2PN02            -'O
 PN02
                                           72

-------
From the general integral solution:
J
     dx       1  In  a + bx

                      x
           x(a + bx)    a
                                                                                (28)
we obtain
r
                      dp
                        N0
                                  In
Then,
          0      K,Pnn
         pN02     1 N°2
              IK  + Kn°   \
        PN02 \jS + K2PN02/|
                                                                                (29)
O/
/K
PNO ii
2 I
and finally,



PN09 "
— cx.p ^— jv^^vnu ; ,
+ K2PNO? )
2/

0 / -L
K1PN00 exp (~KiAHG )
2
1C -I- K^n" _ F1 - fivn ^-K AHr,~nl
                                                                                (30)
                       2NO
                            2
       We may see if Eq. (31) reduces to Eqs. (23)  or (25) as Kg or


tively. As Kg approaches zero, Eq. (31) becomes:
        PNO
At small values of K^ we may approximate:
        e~x = 1 - x ,
and Eq. (31) becomes
                                                                                (31)
                                                         approach zero,  respec-
                                                                                 (23)
                                                                         (32)
                                                                                 (33)
                           2



 And,  as K1 approaches zero, this becomes:



                        .0


                          '2
 PNOO
                          K2AHcrl  '
                                                                                 (25)
                                          73

-------
Thus, the more general equation (Eq. 31) reduces to the simpler equations (Eqs. 23 and 25) in
the limiting cases.
       We may now calculate percentage scrubbing for various scrubbing conditions and geom-
 etries, using Eqs. (22) and (31) .  The only restrictions that apply are that PN(~ should not be
significantly lower than pNQ  if Eq. (31) is to hold exactly. The necessary calculations may be
easily performed on a computer.
       When we perform the calculations we should be aware that we can make reasonable
guesses at the "chemistry-of-the-scrubbing-process" on the basis of our data treatment.  Our
preliminary guess regarding the rate limiting step in the second order process is that it in-
volves gas phase combination of NO and NOg to form gaseous NgOg which then rapidly dissolves
in the acid. If this view is correct, the K,  values should be reasonably constant for any given
temperature and reasonably independent of  gas flow rate, liquid flow rate, column length, and
column cross-sectional area.  Our preliminary guess regarding the rate limiting step in the
first order process is that it involves dissolution and/or liquid phase disproportionation of
                                                                                        2*
If this view is correct, the K- values should be dependent on temperature, gas flow rate, and
liquid flow rate.
       E. Analysis of Scrubber /Stripper Data
       Both Tyco scrubbing data for 80% sulfuric acid and OAP scrubbing data   for aqueous
base solutions were analyzed. Not all of the Tyco data was utilized.  Experimental scatter was
the primary criterion for excluding data. Only total column scrubbing data were plotted and
discussed in detail; the  10-ft and 19-ft data were not used.
       Before commencing the data reduction, it is possible to obtain an estimate of the degree
of reproducibility obtainable with the Tyco equipment. One may compare the percent removal
for the centerpoint runs which represent the average conditions in the parametric study  in
Table V; data for these  runs: 82, 87, 92,  and 97, are given in Appendix IV).  The scrubbing
efficiencies were 63.2, 72.8,  88.1, and 72.6% NO  removal. The difference in scrubbing effi-
                                             X
ciencies is 9.6% for Runs 82 and 87 and 5.5%  for Runs 92 and 97. The average difference in
scrubbing efficiencies for the series and parallel stripper configurations  is 12.3%. Since the
acid from the stripper was quite well denitrated and would not be expected to influence the re-
sults, we  must view these differences in scrubbing efficiency as an indication that experimental
scatter  is high.  To partially  overcome these difficulties,  we used averaged data for the follo^.
ing analysis presented in this section.
       One may also obtain a good estimate of the scrubber NOx removal imbalance, i.e.,
whether or not NO and NO2 were scrubbed in an equimolar ratio. For this purpose we consult
Table VII- 1 in Appendix VII which is a summary sheet of the Tyco scrubbing data.  The  first
column  gives the run number and the second column gives the flow rate in SCFM.  The  next
columns give inlet and outlet  concentrations in ppm.  The seventh and eighth columns give the
amount  of material scrubbed  from the gas stream (in ppm) and the last column gives the dif-
ference of the values in  the seventh and eighth columns (in % error). Thus, the NO  error
                                            74

-------
value of 20 listed for Run 82AB indicates that 20 ppm more NO than N00 was scrubbed. (The
                                                                  £t
analogous OAF data are presented in Table VII-4 in Appendix VII.) In an attempt to determine
the source of this NO  error,  one may determine average values  of the NO error for certain
                    X
groupings of the data.  This data is presented in Table VII-2 in Appendix  VII.  For the six
groupings listed, the values for the average NO error range from -01 ppm to +32 ppm.
Though the standard deviations in these average values are high (between 140 and 300 ppm),
the value for the average NO  error is 120 ppm more positive for the 80  series than for the
                           X
90 series  (see data tables in Appendices IV and VII for details). This might be indicative of
an analytical error, perhaps caused by a change in the experimental setup or due to a time
dependent factor, such as "drift,"  in the analytical equipment. Also,  there is definitely a
trend toward more positive values of the average NO  errors as the input NO  levels to the
                                                 X                      X
scrubber increase. This might reflect concentration  dependent analytical errors or it might
reflect the air oxidation of NO to NOg.
       In  the foregoing paragraphs,  we have discussed sources of variation in the NO  analyses.
                                                                                X
The deviations noted are of the order of 100 ppm.  The averages of the absolute values of the
NO  errors are  60, 90, and 140 ppm for the 250, 500, and 1000 ppm each of NO and NOg input
levels, respectively.  This amounts to an  error which is 20 to 100% of the output NO levels.
                                                                               X
Since the calculation of rate constant values is  sensitive to rather small deviations in the output
levels, one may expect that the rate constant values we  obtain will show wide variance.  Such is
the case.
       The Tyco data analyzed in this section is presented in Table VII-3 in Appendix VII. The
GAP data is presented  in Table VII-4 in Appendix VII. Rate constants were calculated with the
aid of the  computer programs given in Table VII-5 and Table VII-6 in Appendix VII.  The  result-
ing rate constants are  given in Table VII-7, Table VII-8 in Appendix VII, and Figs.  28 through
31. Only the Tyco results  for the total column  height of 26-1/2 ft are discussed in this section.
       Due to the high variance observed  with these calculations, one may  not draw firm con-
clusions solely on the basis of the numerical values presented here.   Figs.  28 through 31  indi-
cate that the scrubbing reactions are neither pure first order or pure second order reactions.
The upward slope of the Kl plots coupled with the downward slope of the  K2 plots is indicative
of rate limiting  steps which are intermediate between first and second order.  We postulate,
but cannot prove (with  the data presented here), that the observed results are a result of a
bimolecular reaction with some mass transfer  control.  If sufficient data on basic column
parameters were available, we might be able to apply calculations similar to those given in
the section on the reactor mechanism.
       The most conclusive evidence that we have regarding the  scrubbing mechanism comes
from the wide range of experimental conditions covered by the Tyco and  OAP work.  Within
experimental error, essentially the  same scrubbing rate constant values were observed  for
80 wt % sulfuric acid,  water,  alkaline earth hydroxide slurries,  and concentrated sodium
hydroxide solutions. Nitrosyl ion is the stable  nitrogen specie expected to be formed in the
scrubber under  strongly acid conditions,  such as 80 wt  % HgSO^  Nitrite ion is the stable
                                            75

-------
                                      -O NO (Tyco)
                                      -• NO2 (Tyco)

                                         NO (Garcia10)
                                                              86A
                                                                              f\C'P2
                                                                           85
KEY

"A" after run number indicates average

ACP - average of center point runs

Circled numbers indicate Garcia's*" run numbers
(See Table  VII-4 in Appendix VII for data)
        200
400             600             SOO
          Inlet Concentration, ppm
                                                                       1000
                                                                                       I ZOO
  Fig. 28.  First order reaction rate constant KI as a function of NOX inlet concentration
           Data from Tyco and EPA (Garcia 10).                                          °-
                                           76

-------
16 -
                                                                 O  NO (Tyco)
                                                                    NO2 (Tyco)
                                                                    NO (Garcia10)
                                                                    N02 (Garcia10)
12 •
                                                                                  ACPI
            KEY
            "A" after run number indicates average
            ACP - average of center point runs
            Circled numbers indicate Garcia's10 run numbers
            (See Table VII-4 in Appendix VII for data)
                   ACP2
                                               600
too
                 200
                                400
1000
uoo
                                       Inlet Concentration, ppm
     Fig. 29.  Second order reaction rate constant K2 as a function of NOX inlet concentration.
               Data from Tyco and EPA (Garcia 10).
                                                    77

-------
oo
                                                                     500


                                                                 NO  (ppm)
                                                                    A.
1000
                           Fig. 30.  Standard deviation for first order rate constant values, 95% confidence limits.

-------
CO
                        12
                                                                       500
                                                                   N0x (ppm)
1000
                                       Fig. 31.  Standard deviations for second order rate constant values.

-------
nitrogen specie expected to be formed in the scrubber under neutral or alkaline conditions,
such as prevailed in the GAP work. One would expect different rates of formation for these
two species because of the wide variation in pH and water activity.  If the formation of NO+
or NO,,  were rate limiting,  we would have expected a difference in scrubbing rates.  No dif-
ference was observed. Therefore, the theory that the gas phase reaction between NO and NO
is controlling is substantiated.  Another factor is that considering the wide temperature range
one would have expected a wide fluctuation in scrubbing rate if the rate limiting step involved
a liquid phase reaction.
       The only rate limiting steps which we can imagine might be responsible for the observed
results would be diffusion and gas phase formation of NgO, followed by rapid dissolution.  Bi-
molecular  gas phase reactions can have low temperature coefficients  (i.e., reaction rates rnav
be a weak function of temperature), which would correspond with the observed results.
       The Tyco and GAP scrubbing results may be applied to the design of a scrubber if one
takes care not to extrapolate the derived rate constants too far from the concentration regions
in which they were obtained.  It is also necessary to use similar packing materials.
                                            80

-------
VII.  STRIPPER EVALUATION
       A.  Initial Concept
       The catalytic stripper stage of the Catalytic Chamber Process had the function of deni-
trating the acid effluent from the high temperature scrubber and simultaneously oxidizing the
nitrogen oxides to NOg. Since the nitrogen oxides were absorbed as equimolar amount of NO
and NO0,  this meant that half the NO  had to be oxidized.
       2                          x
       Experimentation during Contract CPA 70-59 indicated that exposure of the nitrose solu-
tion to the activated charcoal catalyst in a countercurrent stream of air resulted in a minimum
of 99% denitration, with the off-gas being primarily NO«.  The process had not been evaluated
quantitatively and the reaction mechanism had not yet been determined.  The earlier experi-
mentation had shown that the acid and air space velocities were critical parameters, and ef-
fective (although not optimum) values had been determined.  Work during this contract was to
more completely evaluate the stripper  concept in both continuous miniplant tests and in batch
laboratory scale experiments.
       B.  Laboratory Scale Stripper Tests
       Several experiments were carried out with a stripper column made of 1-in. glass pipe
with a total length of 3 ft. The  packed portion of the column was 29 in. in length. A thermo-
couple well employing a thin-walled, 5-mm glass tube was situated at the  center of the packed
section.  In the later experiments of this series, a thermocouple was also used to determine
the feed nitrose temperature.  Before this, feed nitrose  was at ambient temperature. Nitrogen
or air was used as the stripping gas and  this was not preheated. Column packing was either
1/4-in. Intalox saddles or Witco no. 256 activated charcoal.  Sulfuric acid concentration was
nominally  80 wt %.
       The goals of these batch tests were:
              1. To compare the stripping action of inert and catalytic packings
              2. To determine the maximum obtainable NO« level in the  effluent
                 gas
              3. To obtain an insight  into the stripper  mechanism
The results of these initial experiments are given in Appendix VIII, Table VIII-1.
       Intalox saddles were used as the column packing for Runs 1 through 17.  The sample
lines were not properly heated for these runs so that in cases where the N02 level is unexpec-

                                            81

-------
tedly low, one must allow for the probability of nitric acid formation in the sample lines,
thereby creating NO, analysis errors. This  would be expected at temperatures where the
partial pressure of water was higher than about 20 torr or, in our case, for column tempera-
tures in the range of 280 to 300 °F. The most significant observation that can be made regard-
ing saddles  is that less than 10% stripping of the nitrose occurs at temperatures of 70 to 185 °p
with either nitrogen or air. At 280 to 300 °F, about 50% denitration is accomplished with nitro-
gen and about 90% with air.
       In contrast, significant stripping of nitrose solutions is achieved on activated charcoal
even at room temperature, with either nitrogen or air.  At 185 °F, the stripping was generally
above 90%.  With nitrogen as a stripping gas, large quantities of NO and small quantities of
NO, were observed. With air, the reverse was true.
       The  maximum steady state levels of NO, which were obtained were approximately 3%
However, higher levels were obtained when:  (1)  the acid sample was taken (pressure decrease
in column),  (2) the column was flooded (Run 33), or (3) the column temperature was increased
In these cases, momentary high levels of up to 10% were observed.  Observations of the sort
mentioned above tend to indicate that the NO, absorbs onto the activated charcoal, but that it
can be displaced by oxygen if the nitrose flux is not too great and if the air flux is high enough
Unless the NO- is displaced, there seems to be a tendency for the NO, to be reduced to NO.
Thus,  enrichment of the stripper gas with oxygen might very well enable us to obtain higher
steady state levels of NO,.
       To follow up the experimentation in the 1-in. column, a series of experiments were run
in the 2-in. laboratory stripper in order to evaluate the capability of the stripper to produce a
gas stream containing higher concentrations of NO,. The data obtained during this limited ex-
perimentation are shown in Table VIII-2 in Appendix VIII.
       The data reveal two significant points: almost complete denitration is easily achieved
and the effluent gas stream containing about 3% NO, with fairly poor material balance closure
In view of later developments in the interpretation of the output of the duPont UV photometer
(see Appendix IX), it is quite likely that the N02 concentration is considerably higher than the
figures shown in Table VIII-2. This is due to the fact that the  15-in. cell which was used duri
diese tests cannot give accurate analyses above about 2% NO,. The calibration curve tends to
increase to a peak and then decrease, making it difficult to determine which side of the peak
should be used to interpret the absorption reading.  Use of the 1.5-in. cell eliminates this proh
lem, and tests run in the miniplant strippers usually give better material balances. It is signi-
ficant to note that the percentage of NO in the stripper gas effluent is quite low, usually less
than 10% of the
       C. Miniplant Experimentation
       Data concerning stripper performance is shown in the combined scrubber /stripper d
sheets in Appendix IV. Two primary conclusions can be drawn from the data:  high denitratio
yields are generally achieved, but the gaseous effluent contains a very high proportion of
                                           82

-------
and very little NOg.  Although several experiments were run in the miniplant to try to reverse
this proportion, there was usually an excess of NO present.  The results showing high NO con-
centrations were contrary to laboratory scale test data and necessitated an in-depth examination
of the stripper mechanism.
       D. Analysis of Stripper Mechanism
       Since more than half of the effluent NO  was in the form of NO, there must be some
                                           1\
reductive reaction occurring in the stripper.  One possible reaction would be the reduction of
NO  or HNSO. to NO by reaction with the activated carbon, e.g.:
   A         **
         4HNSO5 4 C + 2H20 - COg +  4NO 4 4H2SO4 .

If this  were the case the off-gas would show COg. The long path (one meter) infrared batch
cell was  calibrated for CO«  and  the gas  from several of the laboratory stripper runs (see
Table VIII-1 in Appendix VIII) were analyzed for CO,.  The results of this analysis are shown
in Table  VII.  One may calculate, using average values for Runs 38 through 41 (and using
2.83 ml/min of nitrose, of specific gravity,  1.73 g/ml containing 0.90 wt % HNSO-),  that if
all of the HNSOg reacted with C  to produce NO and CO2, one would obtain a partial pressure
of CO« corresponding to 1.943 cc/min of CO2 or 0.0096 atm CO,. This compares with the
average  measured value of 0.0095  atm CO2-
       This analysis leads to the conclusion that the activated charcoal is not acting as a cata-
lyst, but is  entering into a reaction with the nitrose to effect denitration.  This is contrary to
the experimental evidence developed earlier in the development of this process.  Laboratory
batch tests showed definite evidence of catalytic behavior of several materials in addition to
carbon (see the Final Report for Contract No. CPA 70-59). Clearly, the results  with carbon
are not encouraging,  but considerably more work would have to be done before the catalytic
approach to denitration of nitrose  is ruled out.
                                             83

-------
            Table VII.  CO% Analysis of Laboratory Stripper Tests*
                       (Feed gas CO, concentration =
                        Run                   CQ2
                         31                      0.0344
                         34                      0.0252
                         35                      0.0143
                         38                      0.0060
                         39                      0.0144
                         40                      0.0090
                         41                      0.0085
                         42                      0.0094
                         43                      0.0058
                         44                      0.0147
                         45                      0.0118
                         46                      0.0038
* See Table VIII-1,  Appendix VIII, for details of these experiments.
                                     84

-------
VIII.  PROCESS CONTROL
        A.  Goals
        One of the goals of this contract was to examine the Catalytic Chamber Process in
terms of the process control that would be necessary to operate a full-scale plant. This task
was taken on early in the development of the process because of two anticipated problems: the
large scale of the gas handling system, and the need to accurately control the NO/NO, ratio to
maintain an equimolar gas mixture in the feed to the high temperature scrubber.
        The objectives of the process control studies were: (1) to determine the magnitude of
upset conditions that the process must accommodate, (2) to determine how rapid detection and
response must be to control the process during upset conditions,  (3) to survey and assess the
adequacy of existing and potential analytical and control equipment to satisfy the above require-
ments, and  (4) to recommend a process control system to the EPA.
        B.  Power Plant Operating Conditions
        To establish the magnitude of power plant upset conditions affecting the Tyco process,
discussions have been held with TVA, Consolidated Edison Co. (N.Y.). and New England Power
Co.
        Discussions with William Thompson of TVA (Chattanooga)  provided information on
the operating conditions of a typical TVA coal-fired power plant.  A summary of these discus-
sions follows:
                1. Turndown rate;  Under normal controlled conditions,  plant output is changed
(turndown or turnup) at the rate of 3 MW/min for 125 to 550 MW power plants.
                2. Normal operating schedule;  Under normal operating conditions, a 550 MW
power plant will deliver between 400 and 550 MW.  Full load is usually delivered between 8 a.m.
and 7 p.m.,  with the output being reduced after 7 p.m. Demand production and scheduling can
be done on a weekly basis assuming normal operation.
                3. Air control; Under normal operating conditions (between 400 and 500 MW),
130% excess air is used: 120% at the combustion zone and 10% at the stack. Air flow is con-
trolled automatically to within 5%.  When operating below normal conditions (200 to 400 MW),
140% excess air is used. There is considerable  variation in air flow control under catastrophic
turndown conditions.
                                           85

-------
                4.  Stack effluent properties: At full load, the flue gas analyzed about 7%
water (assuming 10% water in the coal) and 2500 ppm SO- (3% S in the coal).  NO  is usually not
determined.  (The sulfur in the coal at the Shawnee plant varies between 1 and 4%.  Thus,
greater stack gas SCL fluctuations are noted on a week-to-week basis than on a day-to-day
basis as sulfur varies with the coal shipment.)
                5.  Operating conditions; During normal operations, the load is changed by
pulling one pulverizer out which would feed one level of burners in the furnace. The tempera-
ture of the burner is probably not changed, but the length of the burning zone varies, i.e., the
height of the high temperature zone is reduced.  When operating below normal power output
(300 MW or lower),  supplementary oil torches are needed.  When coming up in temperature
the limiting factor is the metal temperature in the turbines. The output is therefore increased
at a maximum of 3 MW/min even if the line voltage or grid voltage must change as a result.
In the case of equipment failure, the following changes occur:
                   a. Turbine failure: 500 MW drops to 0 MW in seconds
                   b. Loss of one pulverizer: loss of 20-40 MW in seconds
                   c. Loss of pump:  loss of 1/3 to 1/2 load in seconds
The plant can operate at 200 MW or less as repairs are made.  Wide fluctuations of excess air
would be experienced during equipment failure until control would be established manually to
the desired level.
         It must be noted that the power demand requirements on the TVA system do not nor-
mally fluctuate to the extent encountered by primarily urban electric utilities, such as the
Consolidated Edison Co. of New York. To assess this factor, discussions were held with
Joseph Cunningham, Plant Engineer, Astoria (N.Y.) Power Station,  Consolidated Edison Co.
Throughout these discussions,  it was noted that despite the greater fluctuations in demand
profile, the response rate of the equipment to such fluctuations, as well as operating conditions
are virtually identical.
        Total generating capacity of Consolidated Edison (N.Y.) as of July 1, 1970,  was 8,039
MW.  The Astoria station,  representing approximately 18% of Consolidated Edison's generating
capacity,  contains five units with nominal capacities as follows: unit 1 — 180 MW, unit 2 —.
180 MW, unit 3 — 335 MW, unit 4 — 380 MW, and unit 5 — 380 MW. [Note: Units 1 — 3
were oil fired, unit 4 was being converted from coal to oil,  and unit 5 was scheduled for con-
version upon completion of unit 4.]
        For the entire Consolidated Edison system, peak loadings occur during summer week-
day afternoons between 3 and 4 p.m. Winter peaks occur from 5 to 6 p.m. as industrial and
lighting loads overlap. Due to the mix of plant efficiencies present in older utilities, these
system peaks are not necessarily reflected at the Astoria station. In practice, the least ef-
ficient generating units are turned on last and turned off first.  Thus, the Astoria load profile
being buffered by the rest of the system, requires the nominal maximum output from 9 a.m.
to 10 p.m.
                                            86

-------
         Differences in generating efficiencies of units within a given station are also signifi-
cant. The three larger generating units at Astoria operate at a higher efficiency than the two
older units. Thus,  the large units are operated at a continuous level throughout the day;
changes in station output are made by thorough controlling of the smaller units. The interplay
within units is shown most clearly in Fig. 32,  which represents the operating parameters of
one of the smaller (180 MW) units.  Note the continuous daytime and evening operation at maxi-
mum levels. Dips in power  output occur at noontime and after 10 p.m.  Minimum levels are
reached between 3 to 4 a.m.
                1.  Turnup and turndown rates;  2 to 4 MW/min is usually practiced,  although
the capability exists for controlled rates up to 8 MW/min. Control of process air feed is done
automatically as with TVA.
                2.  Normal  operation; The larger,  more efficient units operate at their nom-
inal maximum capacity 24 hr/day.  The smaller, less efficient units follow the load profile
described above. Minimum operating levels of 25% of unit capacity  are used.
                3.  Air control; Units operating at the nominal maximum are run at 120 to
125% air.  When run at reduced power, up to 150% air is used to maintain steam temperature.
A 5 to 10% higher air excess is normally used in burning coal as compared to oil.
                4.  Equipment  failure;  The most common failure appears to be rupture of a
boiler tube.  Units are shut  down during repairs. The effects of feed pump failures are de-
pendent on the specific unit. The two smaller units have three pumps each. Pump failure thus
results in the abrupt loss of about 40 MW.  The  three larger units operate with only one large
   mp each. Each unit has a 1/2-size backup pump which must be turned on immediately in
the event the main pump fails.  Rapid fluctuations in stack gas composition are to be  expected
.  event of such failures as  well as during  startup operations.  Startup times range from 3 to 6
   (depending on unit size) before the unit can generate sufficient power to  go on grid (minimum
operating level). The unit continues up on  grid at 2 to 4 MW/min (8 MW/min maximum) until
it reaches the demand operating level.
         A meeting was held with New England Power Co. concerning plant  operating  conditions
as well as pilot plant site considerations.  Section X discusses this meeting in detail; but, in
  eneral,  the operating conditions and techniques did not vary significantly  from those indicated
above for TVA and Consolidated  Edison.
          C.  Instrumentation Requirements
          Regardless of the  detailed control system selected, careful analysis  of available ana-
 lytical instrumentation will be required.  Measurements of  water,  sulfur dioxide, nitrogen
 dioxide,  nitric oxide concentrations, stream  flow rates, and stream temperatures are cur-
   ntly  expected to  be mandatory  in the final control scheme. A preliminary analysis of avail-
  ble instrumentation for the measurement of  SO«, NO,, and NO has been carried out, with
 -articular emphasis on automatic continuous  analysis and control.  Manufacturer's literature
                                            87

-------
Fig. 32. Graph of power plant operating parameters.
                     88

-------
was first surveyed to establish preliminary applicability.  Where required,  the appropriate
technical assistance groups were contacted for more detailed information. Only instrumenta-
tion capable of being integrated with process control devices was considered in detail. The
various analytical methods were organized into the following measuring techniques:  spectro-
scopic, electrochemical, colorimetric (wet chemical), and gas chromatographic.
                1.  Spectroscopic instruments
                Both Beckman and duPont produce spectroscopic instruments suitable for pro-
cess control use. NO» and SCL are readily analyzed in the UV region using the 436 m/J and
302 mM wavelengths, respectively.  Although the instruments are basically similar in approach,
the duPont 400 series photoanalyzer has the advantage that the sample cell can be run at ele-
vated temperatures.  The condensation of water and the resulting alteration of sample stream
composition can thus be avoided.
         Since NO is practically transparent in the UV region, IR analysis using the 5250 mjz
band is usually used. Water interferes in the IR region; thus, the sample must first be passed
through a cold trap or a desiccant for drying.  The analysis is then carried out at ambient
temperatures. Alternatively the NO may first be oxidized to NO_ (using a charcoal catalyst
and a source of oxygen) and the total NOg measured in the UV region.  The  measured NO levels,
which are determined by differences in the NO- concentration before and after oxidation, would
not be expected to be sufficiently  accurate, particularly where low concentrations of NO must
be determined.
         The response rate of spectroscopic instruments to changes in concentration at constant
sample stream flow is determined by the volume of the sample cell. The longer sample cells
required for the measurement of  lower concentration levels present the most serious limita-
tion.  However, worst case response times of 15 sec are quoted for instruments of this type.
Instrument costs are on the order of $3,000 per  installation.
                2.  Electrochemical methods
                NO, SO2, and NO,,,  when dissolved in an electrolyte, are electrochemically
active; i.e., they can be oxidized or reduced (in the case of N0« and SO,) by the passage of an
electrical current.  Devices based on this principal are being sold by Dynasciences (a Division
 f Whittaker)  and Environmetrics.  Conversations with both manufacturers indicate that the
devices are identical.
         The sensor in all cases is a  simple electrochemical cell consisting of a porous mem-
brane, an electrolyte, and a reference electrode.  The potential of the cell  is maintained by an
electronics package which also measures the current output (which is proportional to the quanti-
ty of sample reaching the cell).  Sample temperatures are limited to 110 °F or less  in order to
avoid damage to the electrochemical device.
         Both  manufacturers claim devices which can measure the presence of SO2 without in-
terference from NO or NOg. Units which measure NO2 in the presence of SO,, appear to require
                                            89

-------
either a scrubber to remove the SO, or a separate SCL detector to null out the SCL current.
Only Environmetrics claims to be able to measure NO independently of NOg.  The units are
relatively inexpensive ($250 for the sensor and $2,000 for an electronics unit capable of
handling two separate signals) and compact. Demonstrations of these devices are currently
being arranged. Particular attention must be paid to problems (e.g., water condensation) in-
herent in the reduction of sample temperature. In this area, Dynasciences has a device avail-
able which uses a porous membrane to separate a portion of the gas to  be measured from the
hot stream. Cooling of this relatively dilute sample stream would not be expected to cause
condensation.
        Although rapid when compared to the process conditions, the response rate of this
type of detector is significantly slower than that of the spectroscopic instruments.  Depending
on the details of sensor design which determine the diffusion rate of the dissolving gas, re-
sponse times are reported to range up to several minutes for 90% of full-scale reading.
               3.  Colorimetric analysis
               Many analytical devices based on the automation or semi-automation of the
classical chemical techniques for the analysis of dissolved  gases are available. Most of these
units are designed for ambient (low ppm) levels of pollutant gases.  Due to relatively long cycle
times and/or limited concentration ranges, their application to source  and process concentra-
tion levels is questionable.
               4.  Gas chromatography
               This method  may be divided into a measurement or detection stage and a column
or separation stage. Automated gas sampling can be performed at the process stream  tempera-
ture.  Once a sample is taken, it can be readily transferred through heated tubing to the analyt-
ical column.  Ideally, the column would first separate and isolate each  gas component and pass
them over a detector. The sensitivity of this detector determines the sensitivity of the method.
The analytical column determines the selectivity. In principle, this method should have con-
siderable versatility.
        Commercial process control chromotographs (Bendix Corp., Applied Automation)
typically include automated sample stream switching, multiple columns (to permit relatively
complex separations), and thermal conductivity detectors,  as  well as the electronics required
to convert what is basically a batch output (e.g., a peak area) into a trend-following signal
which could be used for set-point control. Prices range from  $10,000 and up for installations
capable of handling two or three sample points.
        Instrument response times would be dependent on the cycle time of the particular
analytical column being used.  Thus, from both the  process control and analytical  standpoint.
column selection presents the most difficult problem. Single column separation of NO0, NO
                                                                                 A     *
and SO9 in the presence of the other flue gas components is not likely.  Although specific in-
formation was not obtained,  Bendix Corp. claims to have experience in such  separations using
multiple column technology.

                                            90

-------
         Based upon a survey of presently available instrumentation, it appears that instruments
using spectroscopic measuring techniques are the only units sufficiently flexible in terms of
operating range and temperature to allow their further consideration. The main advantages of
the spectroscopic approach lies in the limited amount of sample preparation required as well
as the inherently continuous output signal.  The response of this instrument type is adequate for
integration with process control devices.
         D.  Process Control Requirements
         A preliminary evaluation of the major process control requirements (Fig. 33) was
performed during the current contract. Three major control loops are shown: (1) reactor con-
trol,  including control of NO/NO2 ratio, (2) control of the L/G ratio in the scrubber,  and (3)
control of the NO2 concentration in the stripper offgas. Also indicated is the overall control
of process stream flows required to maintain the Tyco process in an operating mode subser-
vient to that of the power plant.
         Three conceptual  design changes in the overall system were also made.  First, note
that the NO, recycle stream is introduced prior to the main process blower in order to take
advantage of all available mixing capability.  (Since the flow velocity in the process blower is
quite high and since the stream temperatures are well above the dew point, corrosion problems
in the blower should not be increased significantly.)  A  second alteration involves recycling of
some of the acid wash (produced during fly ash concentration) into the scrubber.  In addition to
reducing subsequent neutralization costs, this procedure allows the scrubber to be operated at
a higher temperature than  that required to produce product acid at the desired concentration.
Excess water is removed by the  scrubber, but the concentration is closely controlled by adding
the dilute acid wash back in. In this manner, small fluctuations in scrubber temperature will
not seriously affect product acid concentration.  The temperature control requirements involved
in scrubber operation are therefore reduced. In addition,  final modification places the power
plant's  stack fan after the isothermal scrubber.
                1.  Reactor control
                As diagrammed, control of the oxidation reactor is obtained by adjusting the
flow rate of the recycle NO2 stream in order to maintain a constant  1:1 ratio of NO to NO, in
the reactor output.  Reactor response to changes in NO, and SO2 inputs will be extremely fast
(seconds), since the equivalent holdup time (determined by the rate constant of the reaction) is
    roximately 14 sec> An alternative to this feedback control approach, which avoids the mea-
 urement of NO (the more difficult analysis), is also possible.  Feedforward control, based on
measurements of SO2 and NO2 going into the reactor, is feasible if: (1) the ratio of NO, to NO
.  the power station flue gas is constant for all operating levels, (2) no reoxidation of NO occurs
 rior to the scrubber, and (3) a history of suitable emission control in the exit flue gas has been
demonstrated.
                                             91

-------
CO
to
                 FLUE GAS
             KEY
        RFC  Recording Flow Controller
        HPC  Recording Pressure  Controller
        RTC  Recording Temp. Controller
        RFM  Recording Flow Meter
        RTI  Recording Temp. Indicator
        RPI  Recording Pressure  Indicator
        RC1  Recording Cone. Indicator
        LLC  Liquid Level Controller
        	  Control Path
         D  Control Signal Processing
         A  Signal Subtraction
         ~i~  Signal Division
        RFI  Recording Flow Indicator
        FRT  Recording Flow Transmitter
         O  Hand Valve
                                                                              BLOWER     Setpoint. .
                                                                                           L/G
  FLY ASH     CATALYTIC   ACID
SEPARATOR     STRIPPER    COOLER
                                                      PRECIPITATOR #3
                                                                             Fig. 33.  Major process control requirements.

-------
                2.  Scrubber control
                By designing the scrubber to handle the maximum possible flue gas flow at the
desired operating efficiency, scrubber control is reduced to a simple maintenance of the L/C
ratio.  As long as the L/G ratio is held constant (by controlling the acid feed from the stripper),
it is anticipated that scrubber efficiency  will be  maintained at all operating levels.
                3.  Stripper control
                Here again,  the control  system  is simplified by ensuring adequate stripper
capacity to handle the maximum nitrose  flow. A feedback loop adjusts a variable speed blower
to obtain 10% NO, in the stripper offgas. As designed,  that portion of the 10% NCL stream not
required by the  SCL oxidation reactor is  diverted to the nitric acid plant. The flow rate  to the
acid plant is thus subject to variations dependent on the flue gas input.  It is possible to main-
tain a constant flow rate in this stream (by bleeding additional air into the stripper off gas),
but constancy of both flow and composition is impossible. The preferred operating mode of
the nitric acid plant will determine whether the  constant flow rate or composition control is
preferable.
         An evaluation was also made on suitable startup procedures. In general, power station
outages from key facilities are infrequent, let us say 1 to 2 times per year.  However,  once
they occur (through either equipment failure or  scheduled maintenance), downtimes on  the
order of days to weeks may be expected. During these intervals, the Tyco process must be
maintained in a mode capable of relatively rapid startup.
         The overriding criteria during  both startup and standby operation are the maintenance
of operating temperatures (to ensure rapid and  efficient startup) and the storage of NOx (to
avoid both further expense and contamination).
         Storage of the NO  can be accomplished most easily in a low pressure liquid NO?
                         X                                                          "
tank. During normal process operation, the tank is filled by routing stripper offgas through
a compressor and ammonia chilled condenser.  Since NO- is a liquid at 70 °F and 1 atm pres-
  re elaborate pressure vessels are not required.  As is indicated in Fig. 35, the operating
  moerature of the scrubber and stripper will be maintained by circulating sulfuric acid (any
 "trose will be removed by  the stripper) through a steam heat exchanger.
         In the event of a power station outage,  the flue gases are first bypassed directly to
the stack blower.  The acid loop heat exchanger is then activated to maintain operating tem-
  rature.  HNSO,- present in the acid loop is removed by the hot stripper and sent to either
MO  storage or to the HNOg plant. Once the HNSO, is removed, the stripper  blower will turn
 ff  Pure H SOA will continue to circulate until the system is reactivated.
         System startup is accomplished by  allowing the hot flue gas to pass through the reactor
 nd scrubber. NO2 is bled directly from the NOg tank so as to maintain the proper  NO/NO-
 atio at the reactor outlet.  Effective scrubbing and stripping can commence immediately since
the units are maintained at their operating temperature. The NO2 (from storage) can  be shut
                                            93

-------
off once the stripper offgas reaches the 10% N02 level.  The length of this period will be deter-
mined by the HNSO. holdup in the acid system.
        Once the system has stabilized, the NO2 level in the storage tank can be replenished
by diverting the stripper offgas through the condenser. Thus,  both startup length and frequency
will determine the NO2 storage requirements. Obviously, initial startup of the Tyco process
can be effected through the use of purchased NO«.
        Tank storage of the NO  values as a nitrose solution has also been considered. Svs-
                              X                                                     *
tern startup would  be accomplished by bleeding the stored nitrose solution directly into the
stripper.  If the stripper is bypassed during standby operation, the nitrose can be stored in the
acid loop itself.  In this case,  the scrubber would have to be started with a hot stream of pure
FLSO. (from storage) in order to avoid stripping of the nitrose solution during process startun
A major advantage of nitrose storage is that it permits the  scrubber to be constructed from less
expensive materials which are passive in nitrose solutions.  Use of such materials would, of
course,  reduce plant investment.
        Selection between the alternative methods of NO  storage must consider the economics
of each approach.  Without further experimental backup at the  2000 SCFM level, it is premature
to select the ultimate NO  storage technique.
                       X
                                            94

-------
IX. ECONOMIC EVALUATION
        A.  Prior Evaluations
        Economic evaluations of the Tyco Catalytic Chamber Process have been made earlier
in the development of the process by Tyco and by the Tennessee Valley Authority (TVA) (under
contract to OAP).  Both analyses showed a required investment of about $12 to $16 million for
removal of 90% of the SCL and 60% of the NO  from an 800 MW coal burning power station
whose stack gas contained about 2200 ppm of SO, and 600 ppm of NO  . Based on the salability
of sulfuric and nitric acid,  at $12 and $40 per ton (100%), respectively,  the add-on facility
would operate at about the break- even level.  (See the final report for Contract No. CPA 70-59
for details of this  economic analysis.)
        During the contract discussed in this report, an initial economic analysis of the pro-
cess used only for NO removal was presented to OAP.  (A suggested flowsheet is presented
in Fig. 34.)  Assuming 75% removal of 600 ppm NO  and the manufacture and sale of nitric
acid  the plant would cost about $12  million and would add $1.48 per ton of coal to the operat-
ing cost of a 500- MW power station.  Details of this analysis are shown in Tables VIII,  IX, and
X  The analysis was based on the experimental data from Contract CPA  70-59.
        B. New Process Concept
        As a  result of the  experimentation performed on this contract,  there has been a change
.   the process concept as well as an overall enlargement of the plant size. The conceptual
  hange involves the use of a liquid phase reactor to oxidize the SO,.  This reactor would be
larger than the one used in previous process  evaluations and  would be more costly because
  f the need for either packing or spray tower construction. Fig. 35 shows a proposed flowsheet
            new reactor concept.
                1. Reactor cost
                It is difficult to size the new reactor because of the limited amount of data
    ilable, ^m assuming the 14-sec residence time required in the miniplant for 90% reaction
  ields, we would need about 1000 ft of columns.  These could be set up as 20 columns,  25 ft in
diameter and 50 ft high,  packed with 3- in. Intalox saddles.  The estimated cost of such columns
would be about $6 million.  Further optimization of reactor design and contact methods should
reduce the residence time and reactor cost.
                                            95

-------
              low NOX gas
              to stack
                   NO
                      x
                 Scrubber
                                 Nitrose
                          NO
                                                      Nitrose
                                                   decomposer
                             HNO,
          Flue gas after SC>2 removal;
          high NO
Air
Fig. 34. Flowsheet showing the Tyco Catalytic Chamber Process used for NOX removal only.
                                        96

-------
           Table VIII.  Economics of NOX Scrubbing Plant for 500-MW

                      Power Plant* Based on Tyco SC>2 Removal Pro-
                      cess
                       Estimated Major Equipment Cost

1.


2.
3.

4.

5.
6.


7.
8.

Item
Scrubber


Packing
Stripper

HNOg Absorber

Filter
Product Storage
Tank

Exhaust Fan
Pumps

Use
NO scrubbing
X.


For Item 1 - Scrubber
Denitrification

HNOQ Production
o

Remove ash from acid
Hold HNO3


Provide differential pressure
2 stages of pumping to scrub-
ber and to stripper
No.
4


12,000 ft3 ea.
2

1

4
2


4
—

Size
250,000 SCFM $1
20 ft dia
40 ft high
3" Intalox Saddles
20 ft dia
30 ft high
30 ft dia
60 ft high

50,000 gal
15 x 40
or 20 x 22
-12" H20
Total
54,000 GPM
Cost
,500,000


500,000
500,000

400,000

250,000
50,000


100,000
150,000

                                                       TOTAL
Use Lange Factor of 3.5
              Total Installed Cost = 3.5 x 3.45 x 106 =
 $3,450,000
$12,100,000
 * 1 x 106 SCFM
  600 ppm NO  (75% recovery)
             A
                                    97

-------
                 Table IX.  Economics of NOX Scrubbing Plant for 500-MW
                           Power Plant Based on Tyco SO2 Removal Process

                                 Annual Operating Costs

Materials
  Charcoal replacement                                              $  500,000

Direct Labor                                                           110,000
Supervision                                                              30,000
Maintenance        5% of fixed capital                                    605,000
Supplies           15% of maintenance                                     90,800
Utilities
  Power                                                                250,000
  Water                                                                 10,000
  Heat            (startup only)                                          50,000

TOTAL DIRECT COST	     $1,645,800

Payroll Burden     (20% of direct labor and supervision)                     28,000
Plant Overhead     (50% of direct labor,  supervision,                      417,900
                  maintenance,  and supplies)
Packing and                                                             100,000
  Shipping
Waste Disposal                                                          50,000

TOTAL INDIRECT COST	     $  567,900

Depreciation       (10% of fixed capital)  non-regulated                   1,210,000
                                      (regulated:  $403,000)
Taxes             (2% of fixed capital)                                    242,000
Insurance         (1% of fixed capital)                                    121,000

TOTAL FIXED COST	non-regulated	     $1,573,000
                                     Regulated:  $766,000)

TOTAL OPERATING COST	non-regulated	     $3,786,700
                                     Regulated:  $2,979,700)
                                          98

-------
                  Table X. Economics of NOX Scrubbing Plant for 500-MW
                           Power Plant Based on Tyco SOo Removal Process

                                    Net Process Cost
Credit       19,100 tons/yr (100% HNOg) at $40/ton ..........    $764,000

Net Cost     (regulated)           $2,979,700
                                  - 764,000

                                 $2,215,700


                                         ...............    *1.48/concoa,
Met Cost     (non-regulated)       $3,786,700
                                   - 764,000

                                 $3,022,700


              or   yffiffpfo - _ ...............    $2.02/ton coal
                    1,500,000 tons coal/yr                             v    '
                                           99

-------
  Reactor
                  NO
              H20  _

                  Nitric
                   Acid
               Absorber
        Raw flue
          gas
                                    To stack
                                                Scrubber
1

fc
;ilute
MCO
. 	 f
70% H2SO
.-J
1
Nit
Ab
rose
jorb
I
                                      24     Product
                                                 W/UNSOC
                                                NO, NO,
                                                            Stripper,'
                                                           Oxidizer
                                    70%
                                    (cone. HNSO5)
                                                          Air
                                80% H.SO.
                                      I   4
NO
NOr
Product H-SO.
         £i
                     Product HNO,
Fig. 35. Proposed flowsheet for Catalytic Chamber Process utilizing a wetted reactor for
        SO0 oxidation.
                                      100

-------
              2. Scrubbing Costs — S02/N0  Removal

              If the process were used for removing both SO2 and NO  , it would be necessary
to have packed towers about 105 ft high to reduce the concentration of NO  from 6000 ppm total
                                                                    X
NO plus NOg to  100 ppm total NOx. This figure is developed from visual extrapolation of data
produced in Run 92 (see Appendix IV), as shown in Fig. 36. If we assume an L/G of
5.0 moles/mole and a gas flow of 282 Ib/hr-ft  as used in the miniplant experimentation,  we
would need about 53 columns 25  ft in diameter and 105  ft  high, packed with 3-in.  Intalox saddles
(although it would be better to use 106 columns half as high to avoid ground loading problems).
These shorter columns  would cost about $1  million each  for a total purchased cost of  $106
million. Assuming a 3.5 factor for installation and auxiliary equipment, the scrubbing facility
alone would cost about $370 million,  clearly an unreasonable expense for this process. The
total capital and operating expenditures are  estimated in  Tables XI and XII.
        Typical commercial operation of a packed column, such as the  scrubber, is at 75% of
flooding.  If it can be assumed that subsequent process optimization would allow operation at
75% of flooding with the  same L/G and column height,  we would then need 12 columns 25  ft in
diameter and  105 ft high, packed with 3-in.  Intalox saddles, or 24 columns half as high.  The
purchased cost of these columns would be about $24 million or about $84 million installed.  The
entire plant would cost about $114 million, as shown in Table XIII,  or  over $140/KW installed
for an 800-MW power plant.  Estimated operating costs are shown in Table XIV.  Comparison
of Tables XI and XII with XIII and XIV show how strongly dependent the capital and operating
costs are on scrubbing efficiency. Economical implementation of the Catalytic Chamber Pro-
cess clearly depends on increasing the scrubber gas loading and decreasing the reactor
residence time.
        C.  Cost of NO  Removal Only
                     X
        In sizing the  scrubbing facility for removing NO  only, the same two scrubber flow rates
                                                    X
were used as  with the combined S02/NO  system discussed above.  The data from Runs 85c,
96c, 92c, and 96c indicate that about 90% of an equimolar NO/N02 gas stream containing 1000
ppm of each can be removed in about 27 ft of packing at an L/G of about 5.0 moles/mole and a
gas mass flow rate of 282 Ib/hr-ft .  Extrapolation of the data, as shown in Fig. 37, indicates
that the gas could be cleaned to  100 ppm total NO  in about 45 ft of packing.  The cost of a plant
to accomplish this would be about $175 million, with an annual operating cost of about $41.0
million (8.5 mils/KWhr).  See Tables XV and XVI for details.
        If we again assume that optimization of the system would allow us to operate at 75% of
flooding with a similar column height in the scrubber,  we would need less scrubbing capacity
and the plant cost would drop to $43.5  million. The operating cost would then be $10.82 million
or 2.3 mils/KWhr.  Tables XVII and XVIII present the breakdown of this analysis.
                                            101

-------
    1
    CJ
    OS
                           40                80




                                Scrubber height, ft
120
Fig. 36. Extrapolation of data from Run 92 to give scrubber column height for reducing

        NOv concentration from 6000 ppm to 100 ppm.
                                      102

-------
       Table XI.  Economics of SoJNO2 Scrubbing Plant for 800-MW Power Plant

                         Tyco Catalytic Chamber Process

                         Estimated Major Equipment Cost

                Basis:  282 Ib gas/ft2-hr (Miniplant data)
    Item

1.  Scrubber
    Use
NO scrubber
   A
2. Stripper     Acid denitrification
3.  HNO~
   Absorber
4. Filter


5. Product Stor-
   age Tanks

6. Exhaust Fan


7. Pumps
HNOo production
Remove ash from
acid

Hold HN03 and H2SO4
Provide differential
pressure

3 stages of pumping
to scrubber, stripper,
and reactor
g   Reactor     Oxidize S02
9.  Nitrose
    Absorber
Nitrose production for
reactor feed
 No.

106
     Size
                                                      Cost
 16



  1


  8
 20


   1
              Using Lange Factor of 3 5:
                TOTAL INSTALLED COST =
 27,000 SCFM    $ 106,000, 000
 25 ft dia
 53 ft high
 packed with 3-in.
 Intalox saddles
20 ft dia
30 ft high


30 ft dia
60 ft high
         50, 000 gal
                                                     4,000,000
      400, 000
                       350,000
                       200,000
          12-in.H2O             300,000


          Total 85,000  GPM     400,000
50 ft high
25 ft dia

15 ft dia
40 ft high
    6,000, 000


      250,000


$ 118,900,000


$ 413,000,000
                                       103

-------
Table XII.   Economics of S09/NOV Scrubbing Plant for 800 MW Power Plant*
                           £t    X


                    Tyco Catalytic Chamber Process


                         Annual Operating Costs
                                  2
                Basis: 282 Ib/hr-ft  scrubber gas flow (Miniplant data)
Catalyst replacement (2 replacements per year)      $   2, 000,000
Direct labor                                             250,000
Supervision                                              75,000
Maintenance    5% of fixed capital                      20,600,000
Supplies       15% of maintenance                       3,100,000
Utilities
   Power                                             4,000,000
   Water                                               100,000
   Heat (startup only)                                    100,000

TOTAL DIRECT COST                              $ 30, 325,000


Payroll burden (20% of direct labor and supervision)         65.000
Plant overhead (50% of direct labor, supervision,        12,013,000
   maintenance, and supplies)
Packing and shipping                                     100,000
Waste disposal                                           50, OOP

TOTAL INDIRECT COST                            $ 12,228,000


Depreciation  (10% of fixed capital;  non-regulated)       41, 300,000

Taxes        (2% of fixed capital)                      8,260,000

Insurance     (1% of fixed capital)                      4, 130,000

                                                   $ 53,690,000


TOTAL OPERATING COST (non-regulated)           $  96,243,000

                         or 19.8 mll/KWhr


*  330 days of operation per year at 75% capacity
                                  104

-------
     Table XIII.  Economics of SO2/NOx Scrubbing Plant for 800-MW Power Plant


                           Tyco Catalytic Chamber Process


                           Estimated Major Equipment Cost

                 Basis:  75% of flooding in scrubber
   Item

I  Scrubber
                     Use
No.      Size
2.   Stripper
3. HNO«
   Absdrber

4. Filter
                  NO  scrubbing
                  Acid denitrication
                  HNO, production
                  Remove ash from
                  acid
5   Product Stor-   Hold HNOo and H0SO,
    age Tanks             J      ^

6.  Exhaust Fan    Provide differential
                  pressure
7.   Pumps



8.   Reactor
9   Nitrose
    Absorber
                  3 stages of pumping
                  to scrubber,  stripper,
                  and reactor
                  Nitrose production for
                  reactor feed
24        120,000
           25 ft dia
           53 ft high
           packed with
           3-in. Intalox
           saddles

 4        20 ft dia
          30 ft high

 1        30 ft dia
          60 ft high
                                                  50,000 gal
                                                    12-in.H20
         Total 85, 000 GPM
20       50 ft high
         25 ft dia

 1       40 ft high
         15 ft dia
                                                                        Cost
                                                                    $ 24,000,000
        Using Lange Factor of 3.5:
           TOTAL INSTALLED COST =
    1,000,000


      400,000


      350,000


      200,000


      150,000


      250,000



    6,000, 000


      250,000


 $ 32,700,000

$ 114,000,000
                                       105

-------
Table XIV.   Economics of SO9/N
-------
                          20                40

                           Scrubber height,  ft
60
Fig. 37. Extrapolation of data from Runs 85c,  86c, 92c, 93c,  and 96c to give scrubber
        column height for reducing NOX concentration from 2000 ppm to 100 ppm.
                                     107

-------
Table XV.   Economics of NOX Scrubbing Plant for 800-MW Power Plant

                        Tyco Catalytic Chamber Process

                        Estimated Major Equipment Cost

            Basis: 282  Ib gas/hr-ft2 (Miniplant data)

   Item           Use                No.         Size
                Cost
1.  Scrubber    NOV scrubbing
                 X
27,000 SCFM $ 40,000,000
25 ftdia
45 ft high
3.
4.
5.
6.
Stripper
HNO,
Absorber
Filter
Product
Storage
Tank
Acid denitrification
HN03 production
Remove ash from acid
Hold HNO3
3
1
4
2
7.  Exhaust fan  Provide differential
               pressure

8.  Pumps      2 stages of pumping
               to scrubber and stripper
        Using Lange Factor of 3.5:
             TOTAL INSTALLED COST =
10,000
t3ea
3
1
4
2
4
-
3-in.Intalox
saddles
20 ft dia
30 ft high
30 ft dia
60 ft high
-
50, 000 gal
- 12-in H20
Total 50.000GPM
8,000,000
750, 000
400,000
200,000
50,000
200,000
300,000
            $   49,900,000

            $ 175,000,000
                                     108

-------
Table XVI. Economics of NO  Scrubbing Plant for 800-MW Power Plant'
                           A


                      Tyco Catalytic Chamber Process

           Basis:  282 Ib gas/hr- ft2 (Miniplant data)

                        Annual Operating Costs
Catalyst replacement (twice per year)               $   375,000
Direct labor                                           20°,dou
Supervision                                             60,000
Maintenance          5% of fixed capital                8,750,000
Supplies            15% of maintenance                1,310,000
Utilities
   Power                                             2,000,000
   Water                                               100,000
   Heat (startup only)                                   150,000

TOTAL DIRECT COST                               12, 925, 000

Payroll burden (20% of direct labor supervision)            52,000
Plant overhead (50% of direct labor, supervision,        5,160,000
   maintenance,and supplies)
Packing and shipping                                     20,000
Waste disposal                                          50,000


TOTAL INDIRECT COST                              5, 282, 000

Depreciation (10% of fixed capital)                     17.500, 000
Taxes       (2% of fixed capital)                      3,500,000
Insurance    (1% of fixed capital)                      1,750,000
TOTAL FIXED COST                              $22,750,000

TOTAL OPERATING COST (non-regulated)          $ 4Q 957 Q00
                        or  8.5 mil/KWhr
 *330 days operation per year at 75% capacity
                                 109

-------
     Table XVII.  Economics of NOV Scrubbing Plant for 800-MW Power Plant
                                A

                        Tyco Catalytic Chamber Process


                         Estimated Major Equipment Cost

                 Basis:  75% of flooding in scrubber
   Item
                   Use
   Scrubber    NOV scrubbing
                 A
                      No.

                      12
2. Packing    For item 1 - scrubber   20,000



3. Stripper    Acid denitrification
                                     ft3ea
4. HNOo       HNO« production
   Absofber        °
5. Filter

6. Product
   Storage
   Tank
Remove ash from acid

Hold HNO0
2


1


4

2
7. Exhaust Fan Provide differential
               pressure

8. Pumps      2 stages of pumping
               to scrubber and stripper
         Using Lange Factor of 3.5:
                     INSTALLED COST =
   Size

120,OOOSCFM
   25 ft dia
   45  ft high

3-in. Intalox
saddles

20 ft dia
30 ft high

30 ft dia
60 ft high
                                                50, 000 gal
                                                      H2O
                                                Total 50,000 GPM
    Cost

$  10,000,000



    2,000,000



      500,000


      400,000


      200,000

       50,000



      100,000


      150,000
                                                                 $  12,400,000


                                                                $   43, 500, 000
                                      110

-------
Table XVIII.  Economics of NOV Scrubbing Plant for 800-MW Power Plant*
                            X

                       Tyco Catalytic Chamber Process

                          Annual Operating Costs

            Basis: 75% of flooding in scrubber
Catalyst replacement (twice per year)                 $  250, 000
Direct labor                                            150,000
Supervision                                             50,000
Maintenance         5% of fixed capital                2,170,000
Supplies            15% of maintenance                  325,000
Utilities
   Power                                               750,000
   Water                                                25,000
   Heat (startup only)                                    50, 000
TOTAL DIRECT COST                                3,760, 000

Payroll burden (20% of direct labor supervision)            40,000
Plant overhead (50% of direct labor, supervision,        1, 350, 000
   maintenance, and supplies)
Packing and shipping                                     20,000
Waste  disposal                                          50,000
TOTAL INDIRECT COST                              1, 460, 000

Depreciation (10% of fixed capital)                     4,350,000
Taxes       (2% of fixed capital)                        870,000
Insurance    (1% of fixed capital)                        435,000
TOTAL FIXED COST                               $5,655,000

TOTAL OPERATING COST (non-regulated)           $10, 875, 000
                          or 2.3 mil/KWhr
 * 330 days operation per year at 75% capacity
                                   111

-------
X.  CONCLUSIONS AND RECOMMENDATIONS
       A.  Conclusions
              1. The gas phase oxidation of SO, by NO, is too slow to be practical with feed
SO levels of 3000 ppm.  Residence times of several minutes at 250 to 300 °F would be neces-
sary to achieve 90% oxidation.  This would necessitate reactor volumes of several million cubic
feet which would be extraordinarily expensive as well as creating enormous technological  and
logistical problems (e.g., a 5 million cubic foot reactor could be envisioned as 3 miles of  20-ft.
diameter ducting).
              2. Liquid phase oxidation of SO, using 2 wt%HNSO,.  in 70% H,SO. can be ac-
complished in packed towers in residence times of about 15  sec for 90% SO« oxidation. The
data indicates that the reaction is probably not  diffusion controlled, with the limiting step  being
the liquid phase reaction itself.  Techniques for providing a  more intimate gas/liquid contact
should be able to reduce the residence time down to a workable 10-sec time.
              3, The rate of absorption of equimolar quantities of NO and NO, in 80% sulfuric
acid at 250 °F is not controlled by the individual absorption of the two gases. It appears to be
dependent on a gas phase interaction between the two  species to form N,Og, which is  readily
absorbed at these conditions.  The gas phase reaction is probably slower than the absorption
step, in  addition to which the equilibrium at these elevated temperatures is shifted towards
the unreacted species.  These conditions make  the absorption from dilute gases very slow com-
pared to absorption in cool acid under the more concentrated conditions of the standard Lead
Chamber Process.
              4. At 250 to 300 °F, in the presence of less than 0.3% nitrosylsulfuric  acid and
air  the  activated charcoal does not behave as  an oxidizing catalyst.  Thus,  in the stripper/
oxidizer state the charcoal probably enters into a reaction with the nitrated sulfuric acid to
form NO and CO,.  This is contrary to results  obtained at higher nitrosylsulfuric acid con-
centration and should be verified by further experimentation.
              5. The cost of an add-on Catalytic Chamber Plant to remove both SO,  and NO?
from power plant stack gas would cost about $413 million for an 800 MW plant if its size were
based on miniplant data directly. Its operating cost would be almost 20 mil/KWhr. If the plant
were sized using an industry practice level of 75% of flooding in the scrubber, the plant cost
 ould be reduced to $114 million with an annual operating cost of about  $27 million or $125/KW
and 5.5 mil/KWhr respectively.

                                             113

-------
              6.  If the process were used to remove NO only from the stack, the plant cost
                                                     A
would be about $175 million and the annual operating cost about $41 million if miniplant data
were used directly for scale-up. If 75% of flooding were used here in the scrubbers, the costs
would drop to  $43.5 million and $10.8 million, respectively.  This  would be equivalent to $B5/KW
installed cost and 2.3 mil/KWhr operating cost. Both of these sets of cost estimates bring out
the importance of efficient scrubbing operation.
              7.  The overall conclusion is that the Catalytic Chamber Process at its  current
level of development is technologically feasible but economically impractical.  Major changes
must be accomplished in the three primary process stages — SO, oxidation reactor, NO
adsorber, and NO  stripper/oxidizer — before we have a process of sufficient practicability
to justify pilot plant evaluation.
       B. Recommendations
       In order to bring the Catalytic Chamber Process to a level  of development which would
justify larger  scale evaluation, basic changes must be made in the process. Experimentation
to develop these changes should be conducted on each stage  separately at the bench scale,
rather than the integrated miniplant level, to avoid having equipment problems overshadow
basic technological problems.  The three primary process stages should be examined:
              1.  The liquid phase reaction for the oxidation of SOg with nitrose should be
examined further to see if spray towers or other gas/liquid contractors can be used to reduce
the residence time from 15 sec to the order of 5 sec. The current achievement level  of 90%
reaction in somewhat under 15 sec is not out of the question, but it does require a packed tower
having a volume of over 300,000 ft , which would be quite costly.  Considering that no effort
had been made to optimize the contact method in the current contract, it is hard to imagine that
considerable improvement in residence time cannot be accomplished.
              2.  Since the NO and N02 do not interact in the gas phase fast enough to permit
the use of a high temperature scrubber concept, it may be advantageous to return to the original
Lead Chamber Process and use a low temperature  scrubber (at about 100 ° F). The actual NO/
NO, reaction rate would be slower,  but the equilibrium would be shifted to the NgOg side which
should make the overall process much faster.  The process economics looked poor when the low
temperature scrubber was originally examined, but it may be possible to  avoid the large heat
loss needed to concentrate all the recycle acid by  modifying the technique somewhat.  One ap-
proach would be to withdraw only part of the acid and concentrate  it to about 95% acid, with-
draw product acid, and men return the remainder to the diluted recycle acid,  thus concentrating
the recycle stream back to the desired level. In this case there would be no need to recycle the
most concentrated acid possible (since this is not the market acid), and it would be advanta-
geous to work  at the lowest concentrations, compatible with the process concept.  Recent work
shows this is about 67% sulfuric acid. A low temperature process which might be practical is
shown in Fig.  38.

                                            114

-------
                                              To stack
so2
Oxidizer
         Flue gas
                                LJ
Nitric
Acid
Absorbe:
                                                                             Product
                                                                             95% HS
          Fig.  38.  Catalytic Chamber Process using a low temperature scrubber.
                                          115

-------
              3. More detailed studies  should be made of the interaction between dissolved
NO  and activated charcoal to see if there are conditions under which the system can oxidize
   X
NO  rather than reduce it. The data obtained in the contract are not in complete agreement
   X.
with earlier data obtained at higher nitrosylsulfuric acid concentrations.  Prior work also
showed that other candidate catalysts denitrated the nitrose, although not as well as the acti-
vated charcoal.  Further tests should be made with these, including silicon  nitride,  tungsten
carbide, boron carbide,  and others (see final report to Contract  CPA 70-59).
       If work in any of these three areas is not successful, the  development of the Catalytic
Chamber Process should be discontinued.
                                             116

-------
XI. ACKNOWLEDGMENTS
       The work summarized in this report was sponsored by the National Environmental
Research Center, Environmental Protection Agency.  The guidance and assistance of the
project Officer, Mr. Stanley J. Bunas is acknowledged with sincere thanks.
       The report was prepared by Arnold H. Gruber and Arthur Walitt of the Corporate
Technology Center, Tyco Laboratories. The authors are grateful to the following Tyco
personnel for their significant contributions:  Dr. David Cogley, Mr. Lewis Gaines and
Or. S. Barry  Brummer,  along with the pilot plant crew — Edward Broderick, Arthur Chernosky,
Irving Frutkoff, Mourad Ghobrial, Gary Hanson, Kamal Ladha,  and Vincent Sljaka.
       Acknowledgment is also gratefully given to the efforts and contributions of our sub-
contractor, The Badger Company,  and particularly Dr.  T.C. Dauphine, Mr. George A.
Randall and Mr. Stephen T. Williams.
       In addition,  we would also like to acknowledge the helpful discussions with
k/lr. William  Thompson of the Tennessee Valley Authority, Mr. Roger Ramsdell and Mr.
Joseph Cunningham of the Consolidated Edison Company of New  York,  and Mr. Sashil Batra
of the New England Power Service  Company.
                                            117

-------
XII.  REFERENCES



!.     E. Berl, H. Hillebrandt, and K. Winnacker, Z. Anorg. Allg. Chem., 214, 369 (1933),



2.     F. Seel and R.Z. Winkler,  Physik. Chem. N.F.,  25, 217 (1960).



3.     D.A. Kuznetsov, J. Chem. Ind.,  16, 3 (1941).




4      W. Jost,  Diffusion in Solids, Liquids, and Gases, Chapters X and XII.




5>     E. Berl and H.H. Saenger,  Anorg. u. Allg. Chem., 202, 113 (1931).



6<     P.V. Danckwerts, "Gas-Liquid Reactions, " McGraw-Hill Book Co. (1971).



n      U.S. Stoneware, Bulletin S-31-R.
I •



8.     J.K. Gehlawot and M.M. Sharma, Chem. Eng. Sci., 23, 1173 (1968).




o      G. Schwab and E.Z.  Kolb, Physik. Chem., 3, 52 (1955).
y*                                            —


IQ     L. Garcia,  "Adsorption Studies of Equimolar Concentrations of NO and N02

       in Alkaline Solutions, " Second International Limestone-Wet Scrubbing Symposium,

       New Orleans, November 1971.
                                            119

-------
                 APPENDIX I.  PRELIMINARY ENGINEERING ANALYSIS OF THE
                             TYCO CATALYTIC CHAMBER PROCESS BY BADGER
                              CORPORATION
        T. C. Dauphine' of Badger Corp. evaluated the Tyco/Catalytic Chamber Process
during the first month of the contract and made recommendations for continued experimenta-
tion based on Badger's experience in the operation of pilot-plant facilities as well as the design
and construction of full-scale plants. Experiment  equipment was  modified after consultation
with Dr. Dauphine'and George Randall of Badger.  The following are excerpts from Dr. Dauphine''s
report.
        A.  Introduction
        Badger has been asked to review the data and correlations made available to Tyco and
to advise on additional information that  may be desirable or necessary for proper definition of
the process.
        After reviewing the available information and discussing the process conceptions with
representatives of both Tyco and Badger,  I have the following comments and suggestions.
        B. General Background
        An essential  requirement of the  Tyco process is that it must function at high effective-
ness over the maximum  range of operating rates and conditions of the power plant itself.  These
 eqUirements thus differ from those of most process plants which are set up for relatively nar-
row design conditions concerning feed rates and specification, our system must be designed to
maintain the effectiveness.of the equipment and controls in spite of relatively  large variations
in feed rate and composition during the  daily cycle.
        For future experimentation,  we  have agreed to consider the problems  involved with a
coal fired plant.
        The process  problems caused by variation  in water concentration in the flue gas must
be studied and understood.
        A unique feature  of the Tyco catalytic process is the high temperature scrubbing of
stack gas with 80% sulfuric acid to remove sulfur oxides and nitrogen oxides without absorption
of net water into the acid system.  Water input into stack gas is subject to change, even at
constant firing rate.
                                            1-1

-------
       C.  Reactor (SO2 Oxidizer)

       The reactor mixes a relatively small stream containing N02 (from the catalytic strip-
per) with a large volume of incoming flue gas to oxidize contained SO0 to S00.  The reaction
                                                                £      O
involved is:
         2NO2 + SO2  = S03 + NO2 H- NO .

       Past laboratory work has indicated that this reaction in small-scale equipment proceeds
very rapidly almost to completion.  However, as the scale increases, the reaction does not
appear to proceed as rapidly.
       For commercial scale operation,  the problems inherent to very dilute gas phase reac-
tions and problems of mixing large gas streams must be considered and solved.
       There also exists a question whether the reaction proceeds rapidly under dry conditions
(above the dew point)  or depends upon the presence of liquid acid film.
       Another question concerns the effect of light in catalyzing the reaction (in miniplant,
this reaction has been studied in Pyrex glass equipment).
       Experiments now being contemplated will determine the effect on the reaction of addi-
tional surface to volume, both wetted and dry.
       Other experiments should be made to determine the effect of larger scale on reaction
rate.
       Temperature (between practical limits  anticipated in a plant) should be explored.
       Whereas it is desirable to have the input ratio of NO2 to SO2 equal to 2:1 so that a
mixture of NgOg results, it would be well to explore the effect of ratios different from this
to learn what may happen if operating conditions are upset.
       For some of these experiments, it may be useful to set up bench equipment separate
from the miniplant so that it could run independently from the miniplant to explore a broad
range of conditions.  Such a setup need not be glass and preferably might be of  suitable metal
for short time use, and can be useful to get corrosion information.
       It would be desirable to know if there is unconverted S02 in the  exit stream from the
reactor, how much SOg is present as sulfuric acid mist, the amount of NO2 and NO in the  exit
gas,  the effect of fly ash upon the reaction, the effect of soot upon the reaction as  well as the
effect of various amounts of water in the flue gas feed upon the dew point, and the  resultant
acid condensate which might be formed at high water content levels.
       A device which may be useful both for contacting the gases and for dust and mist re-
moval is a  "Sirocco" centrifical device which has been used commercially to remove dust  and
mist from SO2 gas streams from Pyrites burners.
       A check in the literature for materials which might catalyze or  poison the reaction is
also suggested.
       D.  High Temperature Scrubber
       The high temperature scrubber uses  80% sulfuric acid at  about  250 °F to scrub out SO
                                                                                        3*

                                           1-2

-------
 H2SO4, and NOX ft"0"1 me oxidized flue gas. By controlling the acid inlet temperature, the
 water vapor leaving with exit flue gas can be controlled to equal that entering, thereby eliminat-
 ing dilution of acid. Since the amount of water entering per mole of flue gas will change with
 time, a suitable means for control must be developed.
        One alternate would be to shift the temperature of the scrubbing acid to keep the partial
 pressure of the water vapor in the exit gas  equal to that in the entering gas. This might be
 accomplished with relatively little lag by use of a suitable heater (and cooler).
        Another alternate would be to operate the scrubber at a temperature high enough to
 eliminate the maximum amount of water which might enter the  system and to inject water (as
 required)  into the inlet gas to maintain a constant and predetermined partial pressure.
        Calculations based on probable changes in water partial pressure will help determine
 which system might be preferable and what range of variables should be studied now.
        This scrubbing equipment  must have the ability to operate efficiently at rates well below
 the maximum design throughout; packed scrubbers are not very satisfactory in this regard and
 operate efficiently only over a narrow range of throughput, fairly close to the flooding velocity.
 Channelling of liquid and vapor at lower rates results in poor contact and diminished efficiency.
 The problem becomes much more severe as the diameter of the equipment becomes larger and
 the devices to distribute liquid and vapor within the system become  more awkward and ineffec-
 tive.
        This may be overcome by  using a number of parallel scrubbers, each using a suitable
high ratio of neiSnt to diameter, and planning to shut off one or more scrubbers from the sys-
tem as throughput is diminished in order to maintain optimum loadings in the remaining operat-
ing columns. In consideration of this, the miniplant work should avoid studying  scrubber packed
sections which are abnormally short in relation to their diameter; and such ratio of dimensions
should not be considered for commercial equipment.
        It is important to know accurately whether serious mist removal problems may exist,
narticularly regarding the flue gas stream from the scrubber.  Mist formation in the reactor
and its presence in the feed to the scrubber is probably of no concern,  since the scrubber itself
should be an effective mist remover.
        Two approaches appear  interesting for eliminating mist.  The first is to  design the
scrubber for low exit gas velocities so mist formation will be minimized and can be removed
by  a simple "demister" in the top of the column. The second is to provide additional mist
eliminators,  assuming that it is cheaper to provide this equipment and design the scrubbers
for higher exit velocities.
        The Sirocco unit for dust and mist removal should also be considered for scrubber exit
trSiS in case mist is a problem;  it  also provides additional pressure  for moving gas.
        It is doubtful that operation in laboratory equipment can give any realistic results con-
cerning mist formation.  A review of conventional sulfuric acid technology may  provide prac-
tical information on this point.
                                            1-3

-------
       The high temperature scrubber has been designed to obtain a given efficiency of NO
                                                                                      X
removal, with the NO,/NO mol ratio being maintained at unity in the entering gas.  The effect
of different NO2/NO ratios in the entering gas, and a range of liquid/gas ratios, on the effi-
ciency of the NO absorption must be explored over the maximum probable range of variation.
                A
It is very important to know how sensitive the efficiency of scrubbing is to variations in these
ratios.  If both SO, and NO  removal are relatively unaffected by changes in these ratios,  it
will make control of the commercial unit easy and indicate a high probability of success for
this essential part of the Tyco process.
       The effect of fly ash upon the scrubber and its operation should be established soon.
Fly ash contains a number of metallic impurities, some soluble in the acid, which could affect
the chemical reaction in the scrubber.  It must also be prevented from physically plugging
lines and equipment.  A simple test would be to suspend fly ash (or leach it), with 80% sulfuric
acid used in scrubbing,  and use this in the miniplant to check results against those obtained
when using pure 80%  sulfuric acid.
       Fly ash may be scrubbed out in the acid and at some point  would have to be removed
from the acid and discarded. The handling properties of typical fly ash in appropriate concen-
trations in sulfuric acid can be checked on the bench, along with characteristics for drainage
filtration, and centrifuging. Simple  experiments could give indications whether fly ash cake
has "setting up" or "blinding" properties which would make removal in the plant difficult and
expensive. Such experiments should check properties of filtered,  neutralized (or alkaline)
fly ash as well as for abnormal handling problems.
       For a given plant,  the gas rate through the scrubber is fixed between certain practical
limits.  Work in the miniplant should determine the minimum acid scrubbing rate (L/G) needed
to attain specified removal of SO- and NO and performance over a range of higher  L/G ratios
These figures are needed  for optimizing design of the scrubbing unit and minimizing acid cir-
culation rate.
       Another variable planned for miniplant study is the effect of operating temperature upon
efficiency over a practical temperature range.
       Past runs have been explored at maximum concentrations of NO^Q in tne inlet gas,  and
the scrubber has not been able  to reduce exit concentration to the desired limit. For assurance
in design, it is desirable to know what happens at very dilute concentrations of N_O, approach-
ing design concentration in exit gas.  Additional runs in the miniplant are suggested with very
low concentrations of NgOg in the gas inlet, other conditions of operation being similar to pre-
vious runs.
       E.  Catalytic Oxidizing Stripper
       The heart of the Tyco catalytic process is the catalytic oxidizing stripper, which  in-
volves most of the unique  and developmental features of the process. The stripper  accom-
plishes two things: first,  it contacts the sulfuric acid-nitrose solution from the high tempera-
ture scrubber with oxygen (air) over an activated charcoal catalyst, so that HNSOg is oxidized
                                           1-4

-------
and hydrated to NO2 and H2SO4; second, it strips NOg from the sulfuric acid to produce sale-
able acid. To date, the most successful operation has been with use of 4 x 10 mesh pellets of
No. 256 activated charcoal obtained from Witco.
        For the small equipment used to date,  this size charcoal packing is appropriate, but
would have disadvantages  for industrial scale use.  First, the mesh size is very small for use
in large equipment for countercurrent gas-liquid contacting and may result in high pressure
drop and inefficient vapor-liquid contact.  Second, the material is mechanically weak and fri-
able, and it  may break up and dust in beds deeper than 2 ft. (The manufacturers claim  that
it has been run in deep beds, and this is usual for decolorization of liquids;  but conditions are
quite different for its use  as a tower packing for countercurrent contact of gas and liquid.)
        A search of other available activated charcoals is suggested to try to obtain some of
larger size, better mechanical strength, minimum friability and dusting tendencies, and long
catalyst life.
        Such exploration of their available activated charcoals can use the bench scale single
tube screening test already used to  select activated carbon from other potential catalysts.
        Catalyst life requires continued research for selected  catalysts of good initial character-
istics. Current studies show negligible loss of activity after passing  78 volume acid/volume
catalyst.
        It is  recommended that future experimentation include determination of the effect of fly
     and soot on catalyst life and activity.  In particular,  a few simple tests to delineate whether
      impurities will  impose any new problems or restraints are desirable at an early date.
        Past  experiments on  Witco activated charcoal  have shown that scrubber operating tem-
perature (at least 290 °F)  and air rate must be maintained at suitable levels to prevent  rapid
loss of catalyst activity. Obviously, if new alternate  catalysts seem worth study, this type of
•nforrration  must be obtained for them.  In addition, further experiments at higher temperatures
   e suggested, with the catalyst used for forthcoming miniplant experiments.
        Tests on the oxidizing stripper,  using  fixed bed charcoal packing, should determine
efficiency of contact over  this packing, the effect of changing liquid/gas ratios, and the limiting
 apacity of the packing for acid and air flow (flooding characteristics).
        It would be desirable in this equipment, as well as in the scrubber, to determine heat
 ffects; however, the nature and type of equipment available would appear to render this  im-
practical.
        Corrosion tests on various metals should also be run in the inlet and outlet from this
 Vstem.  Any effect of dissolved metal upon catalyst reactivity,  acid purity, etc.,  should be
noted,  as well as corrosion  rate.
        It may also be interesting to test the stripping of nitrose from sulfuric acid solutions
 ising bench  tests and simple equipment, removing  the carbon catalyst and having present,
•nstead, contaminants from  fly ash  and soot.  This  test could discover if any useful catalytic
activity came from their presence.
                                             1-5

-------
       There may be hazards at some temperature levels in having an oxidizable bed of char-
coal in contact with air and an oxidizing acid.  Small-scale tests are proposed to determine
upper temperature limits which would be safe for operation and to eliminate the possibility of
explosive ignition of the carbon bed.
                                            1-6

-------
                            APPENDIX II: MINIPLANT OPERATION

       A.  Overall Approach
       During the scrubber/stripper studies, the operators had to record 27 temperatures,
7 fluid flows, 27 heater control settings (controlling 52 individual heaters), and 11 gas sample
concentrations plus 3 complete acid analyses, in addition to keeping track of a variety of pro-
cess equipment indicators (reservoir levels, column drainage levels, cooling water flows,
pump and blower performance, and sample system operation and overall system integrity).
Reactor experiments required 8 temperature points, 6 flow rates, and 10 heater control set-
tings as other checks and analyses.  (Data sheets showing the information required during the
experiments are  shown in Tables II-l through II-4.) Since it was necessary to record a complete
set of data on an hourly schedule,  a large task for 2 men, it was  important that the plant be  set
 _ as conveniently as possible.  This was accomplished by installing all controls on the upper
level of the two-level miniplant. The only tasks that had to be performed on the lower level
were the sampling of the acid effluent from the 19-ft scrubber and the enlarged vertical reactor
(these,  too, could have been taken on the upper level, but there would have been a concentration
lag due to the volume in the reservoirs).  To further simplify operation,  a closed circuit tele-
 ision system was installed to monitor the reservoir levels on the lower plant level, with the
level controls being located on the upper level.
       B.  Gas Sampling System
       Gas samples were taken at two points in the reactor system (as shown in Fig. 6) at the
"nlet and at the outlet. Samples were required at five locations in the scrubber/stripper studies:
(1) inlet to 19-ft scrubber,  (2) halfway up the 19-ft scrubber,  (3) exit from the 19-ft scrubber
(feed to 7.5-ft scrubber), (4) exit from the  7.5-ft scrubber, and  (5) exit from the strippers. In
order to take these samples and analyze them in one system of analytical instrumentation, a
manifold system had to be arranged as  shown in Fig.  II-l.
       The system utilized two UV cells for analysis of NO2 to give accurate analysis at two
 oncentration levels which differed by an order of magnitude,  1% full scale and 10% full scale.
These ranges were expected from the scrubber system and stripper system, respectively.
                                             II-l

-------
                             Table II-1.  Reactor Data Sheet
                                                            DATE:

                                                            RUN:
TIME

FLOWS

  Infrared Sample
  Total Sample
  O2: psig
     SCFM
  NO: psig
      SCFM
  Low Air: psig
          SCFM
  SO2: psig
      SCFM
  High Air: SCFM
  H2S04
  HNSOg Concentration

TEMPERATURES

  Blower Inlet
  Inlet Reactor 1
  Ultraviolet Analyzer
  Acid Feed
  Middle Reactor 1
  Bottom Reactor 1
  Middle Reactor 2
  Middle Reactor 3

VOLTAGES
 Middle Reactor 1
 Bottom Reactor 1
 Middle Reactor 2
 Bottom Reactor 3
 Top Reactor 3
 Acid Feed
 Top Reactor 2
 Inlet to Reactor 1
 Bottom Reactor 2
 Top Reactor 1

CHECKLIST

 Gas Burner
 Cooling Water
 Drains
 Acid Level

 OPERATOR


                                         II-2

-------
TEMPERATURE

 Scrubber 2 Reservoir
 Top of Stripper No. 1
        "        No. 2
        "        No. 3
 Middle of Stripper No. 1
        "          No. 2
        "          No. 3
 Bottom of Stripper No. 1
        11          No. 2
        »          No. 3
 Acid Feed: Lower
            Middle
            Top
 Stripper Reservoir

VARIACS

 Acid Feed Line
 Acid Feed (Res)
 Acid Feed Tapes
 Stripper Heaters Top
                 Middle
                 Bottom
 Acid Feed
 Top Stripper Tapes

FLOWS

 Acid
 Air to Stripper

CHECKLIST

 Res. Level
 Exit Level
 Flows
OPERATOR
                             Table II-2. Stripper Data Sheet

                              Run No.                Date

                              Time
Sheet No.
                                          II-3

-------
                          Table II-3.  Scrubber No. 2 Data Sheet

                                 Run No.             Date            Sheet No.
                                 Time
TEMPERATURES

 Main Air Feed
 Inlet Air
 Acid Feed: Top
            Middle
            Bottom
 Feed Res (Scr 4 Res)
 Sample Line

CONTROL VARIACS

 Main Air
 Gas Feed to Scr Bottom
 Gas Feed tc Scr Bottom
 Top (1 ft Mantle)
 Top (4 ft Mantle)
 Top/middle (4 ft Mantle)
 Middle (1 ft Mantle)
 Middle/Bottom (4 ft Mantle)
 Bottom (4 ft Mantle)
 Bottom (1 ft Mantle)
 Acid Feed: Immersion Heater
 Acid Feed: Tapes
 Reservoir

FLOWS
 Main Air Meter Reading
 Main Air Flow
 Acid
 NO to Oxidizer Meter Reading
 Air to Oxidizer Meter Reading
 SO2 Feed Flow Meter Reading

CHECKLIST

 Reservoir Level (TV)
 Gas Burner

OPERATOR
                                         II-4

-------
                         Table II-4.  Scrubber No. 4 Data Sheet

                               Run No.               Date            Sheet No.

                               Time
TEMPERATURES

 Acid Feed
 Gas Feed: Top
           Middle
           Bottom
 Feed Res (Stripper Res)

CONTROL VARIACS

 Feed Res (Stripper Res)
 Bottom Mantles
 Middle Mantles
 Top Mantles
 Acid Feed: Top Immersion
 Acid Feed: Tapes
 Gas Feed
 Reservoir

_FLOWS_

 Acid Feed

CHECKLIST

 Reservoir
 Heater
 Column Exit
 Leaks
 Sample Box
 Sample Line

OPERATOR
                                        II-5

-------
From top of
strippers
     From
     before
     reactor
     DuPont \JV Photometer
 f ~ ~1?" ceH   ~ 11/7" -c<
                                    n/7" ~ein-
                                Manometer
                          n
    Air
    pump
                   Flow meter
                                        Flowmeter
                                                 T6
   Calibration gases


 O \»—  From top
Vp       of scrubber
               From after
               reactor
                                                                      Recorder
Dew-
point
Hygron
          ?
                                                                        Beckman
                                                                        IR Analv:
                  t
                                                                     eter
                                                                               Flowmeter
      Condenser
         To before reacto
                                                                                            To stack
                             T
                          To after
                          reactor
                             Fig. II-1.  Flowsheet of gas analysis system.

-------
       The gas was pumped out of the miniplant with a small diaphragm pump (about 0.5 SCFM)
and fed to the system shown in Fig.  II-1.  The gas analysis system was  set up so that the gas
could be returned to the miniplant after it had been analyzed to avoid intermittant fluctuations
in process flow levels.
       The gas sample was controlled at constant temperature and pressure in the analyzers.
This was more important than constant flow rate since the duPont and Beckman instruments
both based their analysis on the number of molecules in the path of the radiation beam.  A
manometer and temperature readout were installed in the sample system near the UV photo-
meter.
       The most important feature  of the gas sampling system was the control of the condition
of the sample.  It was necessary to  avoid condensation of liquid in the sample lines, a condition
which had been known to cause erroneous results in sample analysis.  The sample lines were
Teflon tubes encased (two or  three at a time) in aluminum tubes which  were wrapped with heat-
ing tapes.  In this manner, the gas  sample could be kept at about 275 °F while it was outside
the miniplant.
        If the temperature dropped much below this level, condensation was formed with cor-
roded the stainless steel fittings used in the sample system.  The corrosion products tended to
block the sample line, resulting in  either a high pressure drop (making it difficult to maintain
the proper pressure in the system) or a complete blockage of the lines.  The system was set
up so that an individual line could be isolated and washed with water without removing  it from
the aluminum tubes.  Although the system was workable as used, it was concluded that a more
desirable system would utilize individually traced lines.  These are more expensive than the
system used,  but they involve far less maintenance.
        Nitric oxide was analyzed with the Beckman infrared analyzer,  as shown in Fig. II-1.
The primary consideration in this analysis was  the removal of water from the gas sample
before it reached the analyzer because water interferes with the quantitative analysis of NO
in the infrared region of the  spectrum.  To remove the water, the sample was passed  through
a cold trap.  Experience showed that a large U-tube filled with saddles and immersed  in alcohol
at -35 °C would drop out most of the water without removing significant amounts of nitrogen
oxides. The trap had a tendency to plug up with ice several times a day, but a quick-disconnect
 system allowed the replacement  of the trap in a few minutes and very little time was lost in
 this type of maintenance.  An operator learned to recognize the sudden erratic behavior of  the
 Beckman analyzer output as the symptom of a plugged cold trap.
        C. Data-Taking Procedures
        As noted above,  a complete set of data was taken every hour during a run. A  run was
 not considered to be complete until the essential data were constant for two consecutive sets
 of readings.  The temperatures were taken off the printout of the 24-point  recorders and logged
 onto the data sheets shown earlier. The recorder charts themselves were not retained. Based
 on the temperature readings, heating rates were adjusted whenever necessary.
                                            H-7

-------
        Gas sampling was performed continuously, with SOg, NO,, and NO being analyzed at
 each sample point. A gas concentration was considered to be meaningful if the output of the
 analyzer instrument was constant for 5 to 10 min.  Since SOg and NO2 were analyzed on the
 same instrument, it took several minutes to get a complete analysis at any one sample point
        Acid samples were taken from all required points within a few minutes of each other
 and analyzed later for acid strength (percent sulfuric acid)  and nitrosylsulfuric acid content
 In this manner it was hoped that all the data would come close  to giving the process condition
 at one particular time.  The acid strength was obtained with a hydrometer (correcting for tem-
 perature) and the nitrosylsulfuric acid content determined by titration with potassium perman-
 ganate in acid solution:
         5 HNSO. +  H MnO, 4 2H.O  -»  5H.,SO4 -f HNO, + 2Mn(NO0)0 .
                0         1     £i         61       O          0 ^
        The acid analysis is quite rapid, except in very dilute solution where it takes as much
 as 15 min for the color change to become permanent.  With HNSO- concentrations above 0.1%
 the titration takes less than 5 min and is  quite accurate and reproducible.  At lower concentra-
 tions the variation between replications can be as much as 5%.
       The NOx content of the acid can be determined by an alternate procedure: the nitrometer
 In this case the reducible nitrogen oxides (NO,"",  NO,") are reduced with mercury to NO gas
 which is evolved from the solution.  The volume of the NO is measured and the original amount
 of HNSO- can be calculated if it is assumed that all the NO  was present as N000. This is  a
        o                                             x                2 3
 very accurate method but is very time consuming because it takes a long time for the mercury to
 react with all the NO in the acid solution.  In addition, it is not too accurate for very dilute
 solutions since a small error in reading the colume of NO can  make a sizable error in the
 HNSOg concentration. All analyses performed during the normal course of miniplant experi-
 mentation was done by permanganate titration with occasional checks  with the nitrometer on
 the more concentrated samples.
       Fluid flows were recorded once an hour, but were monitored frequently by the miniplant
 operators.   This was accomplished by observing rotameter  settings as well as liquid levels in
 the reservoirs.
       D. Shift Operation
       Experimentation in the miniplant was performed in continuous "batch" operations. The
 equipment was run in a continuous fashion for several hours at a time to accomplish the goals
 of a  particular experiment. Then the conditions were changed and another "batch" experiment
 was  performed. This type of testing might have lent itself to an 8-hr  day program, except for
 the fact that it took several hours to bring the plant up to temperature.  Because of limitations
 in the heating equipment and the necessity for slow heating rates on the all-glass piping and
columns, it took 4 to 8 hr to achieve thermal steady state.
       Due to these requirements and the desire to accomplish as much  experimentation as
possible during the contract period,  the plant operation was conducted on a two or three shift,
                                          II-8

-------
5-day week basis.  Two operators were present at all times during the three shift work.  For
the last several weeks of the contract period, the plant was operated for two shifts per day to
permit more time during the experimentation for data analysis. The plant was maintained at
about 200 °F during the 7-hr period that it was unattended, which cut down the heating time to
under 4 hr.  This left about 13 hr for experimentation and shutdown. The two shift operation
had another advantage in that it provided at least 4 hr every day for equipment maintenance and
sample system cleanout. This permitted smoother plant operation during the experimental
period.
                                            II-9

-------
APPENDIX III. DATA FROM MINIPLANT REACTOR EXPERIMENTATION
                          III-l

-------
             Table III-l.  Miniplant Reactor Experiment— Irrigation
                         with Nitrose [Three Reactor Columns (1.6
                         Packed with 3/8-in. Intalox Saddles, Acid Feed
                         4.4% HNSOg in 70% H2SC>4 at 20 cc/min]
   Run No.
Reactor temperature, °F
Gas flow rate (SCFM)
Feed SO, (ppm)
Feed NO, (ppm)
Feed NO (ppm)
Feed H00 (%)
       £i
Outlet SO, (ppm)
Outlet N02 (ppm)
Outlet NO (ppm)
Reactor residence
 time (sec*)
SOp removal efficiency,  $
 30A    308     30C
 225    225     225
   222
3450   3450    3450
4000 10,400    4000
2325   6000    2325
 ~6    ~6     ~6
 650    700     450
3700 16,400   -5500
4700   6800    4850
34.2   34.2    34.2
                        70.5   87.4   84.2    94.0     91.3
29A
250
2
3550
4000
2325
~6
1200
3900
3850
33.2
29B
225
2
3550
4000
2325
~6
600
4200
5000
34.2
SOD
200
2
3450
4000
2325
~6
150
5300
5300
35.8
30E
200
2
3450
10,400
6000
~6
400
11,800
6600
35.8
                        100
100
 * Sample line residence time was less than 1 sec using the short LJV cell.
** NO, interference was taken into account.
                                    III-2

-------
 I
CO
                                                                                         Table 111-2. Miniplant Experiments — Irrigation with
                                                                                                     Nitrose [Three Reactor Columns (1.6 ft3)
                                                                                                     Packed with 3/8-in. Intalox Saddles*]
Run No.
Reactor temperature (°F)
Gas flow rate (SCFM)
Gas feed:
SO. (ppm)
Ndn (ppm)
NO (ppm)
Acid flow rate (cc/min)t
Acid feed:
HNSOg (%)
H2SO4 (%)
Gas effluent:
SO2 (ppm)
NOo (ppm)
NO (ppm)
Acid effluent:
HNSOjj (%)
H2S04 (%)
Reactor residence
time (sec)
Reaction yield (%)
NOx material balance
error flb) t
* Reactors 1 and 3
f Total flow to all

(Material balance
31
250
2

3450
0
0
15

4.3
70.0

1900
2900
4250

0.33
66.5
33.2

45.0
-134


250
2

3450
6400
2725
15

4.3
70.0

1100
6100
4700

0.27
64.4
33.2

68.0
10


250
2

3450
6400
2725
60

4.3
70.0

760
16,900
6200

0.78
69.0
33.2

78.0
-16

were in cocurrent flow rate;
3 reactors.
NO
r-rwT

(in) —

N0x
N0v (out)
X
(in)

225
2

3450
6400
2725
60

4.3
70.0

550
18,400
7000

	
—
34.2

84.0
	

reactor 2

- x 100.
32A
250
2

3100
5800
2375
25

1.12
70.8

1150
4000
4400

	
—
33.2

62.9
—


250
2

3100
5800
2375
50

1.12
70.8

850
4400
4100

	
—
33.2

72.6
—


250
2

3100
5800
2375
100

1.12
70.8

750
4900
1500

0.64
71.3
33.2

76.5
30

was countercurrent.






                                                                                                                             32B

                                                                                                                             250
                                                                                                                               2
                                                                                                                             135
                                                                                                                            0.63
                                                                                                                            68.7
                                                                                                                            33.2


                                                                                                                            74.1
          250
            2
                                                                                                                            2900    2900
                                                                                                                            6600    6600
                                                                                                                            2650    2650
                                                                                                                                     240
         0.63
         68.7
 750     600
8500   13,400
5000    6000
                                                                                                                                    0.37
                                                                                                                                    64.7

                                                                                                                                    33.2
         79.3

         -42
33A
250
2
3425
0
0
32
1.23
78.9
2900
250
1050
—
33.2
15.5
—

250
2
3425
5500
1700
32
1.23
78.9
2150
3900
2550
1.54
76.3
33.2
37.2
2

250
2
3425
5500
1700
165
—
1700
3000
1800
1.39
76.3
33.2
50.1
6

250
2
3425
0
0
165
—
2650
2900
—
33.2
22.9
—

-------
                                                          Table III-2.  (Continued)
Run No.
Reactor temperature (°F)
Gas flow rate (SCFM)
Gas feed:
SO2 (ppm)
NO2 (ppm)
NO (ppm)
Acid flow rate, cc/mint
Acid feed:
HNSOg (%)
H2S04 (%)
Gas effluent:
S02 (ppm)
NO2 (ppm)
NO (ppm)
Acid effluent:
HNSOg (%)
H2S04 (%)
Reactor residence
time (sec)
Reaction yield (%)
NOX material balance
error (%) t
* Reactors 1 and 3
t Total flow to all
1 Material balance
33B
300
2

3050
6000
2050
60

1.27
79.6

2550
4600
3100

—
29.9

16.4

were in

300
2

3050
6000
2050
160

1.27
79.6

2200
4100
3075

—
29.9

27.9

cocurrent

300
2

3050
6000
2050
160

1.27
79.6

2150
4000
3350

1.03
77.3
29.9

29.5
14
flow rate,
34
260
2

3500
7000
2050
15

1.46
60.0

2100
3400
2900

—
32.9

40.0
reactor 2

260
2

3500
0
0
15

1.46
60.0

2900

—
32.9

17.1

260
2

3500
7000
2050
57

1.46
60.0

1250
4100
4700

—
32.9

64.4

260
2

3500
7000
2050
150

1.46
60.0

550
6100
6000

—
32.9

84.3

260
2

3500
7000
2050
185

1.46
60.0

425
6100
6600

—
32.9

87.8
35
250
2

3200
6500
2400
60

1.13
53.0

200

—
33.2

93.8

250 250
2 2

3200 3200
6500 0
2400 0
60 60

1.13 1.13
53.0 53.0

50 600

— —
33.2 33.2

98.4 81.3
36
250
2

3200
5050
1775
15

1.13
71.6§

1200

—
33.2

62.0
37
250 250 250
2 22

3200 3150 3150
5050 0 0
1775 0 0
50 25 80

1.13 0 0
71.6§ 79.8** 79.8**

2200 3150 3150

— — —
33.2 33.2 33.2

31.7 0 0
was countercurrent.
3 reactors.
error =
NOx (in) -
- NO (out)
- x mn








                                   (in)
 §2.24%HNO3 added.


**2.95% HNO, added.
            o

-------
                                                                                            Table III-2. (Continued)
en
Run No.
Reactor temperature (°F)
Gas flow rate (SCFM)
Gas feed:
SOn (ppm)
NCJ2 (ppm)
NO (ppm)
Acid flow rate (cc/min)
Acid feed:
HNSOg(%)
H2SO4 (%)
Gas effluent:
SO2 (ppm)
NO™ (ppm)
NO (ppm)
Acid effluent:
HNSO5 (%)
H2SO4 (%)
Reactor residence
time (sec)
Reaction yield (%)
NOX material balance
error ft)
38
250
2

3100
4700
1225
20

1.17
71.25

1400
3900
2600

1.58
74.9
33.2

54.8
-14

38A
250
2

2950
5500
1775
60

1.04
70.7

1150
4200
2900

—
—
33.2

62.7
—

* Reactors 1 and 3 were in cocurrent flow
t Total flow to all 3 reactors.

j Material balance

NO



250
2

2950
5500
1775
140

1.04
70.7

400
6100
4400

—
—
33.2

86.4
—


250
2

2950
5500
1775
260

1.04
70.7

150
6800
4625

—
—
33.2

94.9
—

rate, reactor 2

250
2

2950
0
0
260

1.04
70.7

500
3600
4400

—
—
33.2

83.1
—

39
250 250 250
2 22

3200 3200 3200
5500 5500 5500
1900 1900 1900
33 50 181

1.26 1.26 1.26
80.4 80.4 80.4

2000 2250 1850
— — —

— — —
— — —
33.2 33.2 33.2

37.5 29.5 42.2
— — —

40
250
2

3200
6100
2100
70

2.06
79.3

1100
3100
2100

—
—
33.2

65.6
—


250
2

3200
6100
2100
140

2.06
79.3

950
4000
3100

—
—
33.2

70.3
—


250
2

3200
6100
2100
260

2.06
79.3

500
2500
2325

—
—
33.2

84.4
—


250
2

3200
0
0
260

2.06
79.3

1150
300
4250

—
—
33.2

64.0
—

was countercurrent.
(in) — NO., (out)

NO (in)
A

x 100.













                                    50.45% HNO, present.
                                               o

-------
                                                                    Table III-2.  (Continued)
Run No.
Reactor temperature (°F)
Gas flow rate (SCFM)
Gas feed:
SO2 (ppm)
N02 (ppm)
NO (ppm)
Acid flow rate (cc/min) t
Acid feed:
HNSO5 (%)
H2S04 (%)
Gas effluent:
S02 (ppm)
N02 (ppm)
NO (ppm)
Acid effluent:
HNSO5 (%)
H2SO4 (%)
Reactor residence
time (sec)
Reaction yield (%)
NOX material balance
41
250
4

3850
7500
2900
55

1.0
71.1

3000
900
3625

—
16.6
22.1
—

250
4

3850
7500
2900
55

1.0
71.1

2275
5800
4400

0.59
72.9
16.6
40.7
6

250
4

3850
7500
2900
120

1.0
71.1

1175
7500
5400

0.96
72.6
16.6
69.6
-18

250
4

3850
7500
2900
280

1.0
71.1

550
8500
6000

0.70
71.2
16.6
85.5
-11

250
4

3850
7500
2900
500

1.0
71.1

0
7500
5600

0.86
69.6
16.6
100
-4

250
4

3850
0
0
500

1.0
71.1

375
5500
5900

	
16.6
90.3
—
42
250
4

3150
5600
1950
120

0.91
75.8

2150

—
16.6
31.8
—

250
4

3150
5600
1950
255

0.91
75.8

1850

	
16.6
41.5
—
43
250
8

3050
6100
2325
110

1.06
69.7

2050

z
8.3
32.8
—

250
8

3050
6100
2325
280

1.06
69.7

1400

z
8.3
54.1
—
44
250
4

3200
6500
2175
64

0.53
70.0

1775
4350
3225

0.45
70.0
16.6
44.6
13

250
4

3200
0
0
64

0.53
70.0

2825
200
950

z
16.6
11.7
—

250
4

3200
6500
2175
122

0.53
70.0

1400
4600
3500

0.45
71.0
16.6
56.3
9

250
4

3200
6500
2175
257

0.53
70.0

1225
5000
3850

0.42
70.0
16.6
62.0
5

250
4

3200
6500
2175
484

0.53
70.0

1075
4725
3750

0.39
70.6
16.6
66.6
13
error (%) t
      * Reactors  1 and 3 were in cocurrent flow rate, reactor 2 was countercurrent.
      t Total flow to all 3 reactors.

                                NO  (in) —NO  (out)
      t Material balance error = 	-	  x 100.
                                      N0x (in)

-------
                                                            Table III-2. (Continued)
Run No. 45
Reactor temperature (° F) 250
Gas flow rate (SCFM) 6
Gas feed:
S02 (ppm) —
NOjj (ppm) —
NO (ppm) —
Acid flow rate (cc/min)f —
Acid feed:
HNSO5 (%) —
H2SO4 (%) —
Gas effluent:
SO2 (ppm) —
N02 (ppm) —
NO (ppm) —
Acid effluent:
HNSOg (%) —
Reactor residence —
time (sec)
Reaction yield (%) —
NOX material balance —
error (%) t
46$
250
2

3300
6400
1800
15

1.12
71.5

2550
6100
3850

1.64
72.8
24.9

22.7 **
-23

250
2

3300
6400
1800
42

1.12
71.5

2300
6700
4025

1.85
80.4
33.2

30.3
SeTT
-38

250
2

3300
6400
1800
57

1.12
71.5

2400
6700
3975

2.1
74.9
33.2

27.7
TO
-47

250
2

3300
6400
1800
89

1.12
71.5

1500
7700
4625

1.36
77.9
33.2

54.6
TO
-39

250
2

3300
6400
1800
134

1.12
71.5

1400
8600
5000

0.81
67.7
33.2

57.6
-22

250
2

3300
6400
1800
248

1.12
71.5

900
8125
4025

0.65
72.9
33.2

72.9
T5o
9

250
2

3300
0
0
248

1.12
71.5

975
6200
4850

	
33.2

70.6
SO

 * Reactors 1 and 3 were in cocurrent flow rate; reactor 2 was countercurrent.
 f Total flow to all 3 reactors.
   Material balance error
N0x (in) — N0x (out)
      N0x (in)
                                                   x 100.
475
250
4
3250
6200
1950
29
0.96
73.4
2925
4950
3500
—
16.6
10.0 **
2O
—

250
4
3250
6200
1950
82
0.96
73.4
2600
5000
3550
0.62
16.6
20.0
2O
3

250
4
3250
6200
1950
179
0.96
73.4
2200
4600
4000
0.67
74.4
16.6
32.4
Z3TO"
7

250
4
3250
6200
1950
220
0.96
73.4
1950
4900
4025
0.63
73.7
16.6
40.0
5O
8
 § One reactor: cocurrent operation — effluent data for one column only.
** The yield values represent SO2 removal rates after one irrigated column (above the slash line) and after the third reactor;  i.e., one
   irrigated reactor and unirrigated,  but wetted packed columns (below the slash line).

-------
                                                              Table III-2.  (Continued)

    Run No.                    485                                49 §
Reactor temperature (°F)       250      250     250     250       250     250       250
Gas flow rate (SCFM)            2222          44         4
Gas feed:
  SO, (ppm)                  3050     3050    3050    3050       3450     3450      3450
  NCT2  (ppm)                  5850     5850    5850    5850       5900     5900      5900
  NO (ppm)                   1950     1950    1950    1950       2200     2200      2200
Acid flow rate (cc/min) t        29       59     136     204        30     180       350
Acid feed:
  HNSO5 (%)                  0.95     0.95    0.95    0.95       0.95     0.95      0.95
  H2SO4 (%)                  72.7     72.7    72.7    72.7       72.7     72.7      72.7
Gas effluent:
  SO, (ppm)                  2175     1550    1275    1200       —     —        —
  NOJj (ppm)                  4600     5200    5300    5600       5500     4500      4400
  NO (ppm)                   3750     4700    5050    5100       3350     3900      2650
Acid effluent:
  HNSOg (%)                  0.54     0.56    0.79    0.89       0.71     0.67      0.69
  H2S04(%)                  75.5     74.7    73.9    73.9       71.0     70.9      71.2
Reactor residence             33.2     33.2    33.2    33.2       16.6     16.6      16.8
  time (sec)
Reaction yield (%)             28.7     49.0    58.5    60.0        9.9     27.3      31.7
NOX material balance            1       -8-10-13        -6       8        20
 error (%)  $
       * Reactors 1 and 3 were In cocurrem flow rate;  reactor 2 was countercurrent.
       t Total flow to all 3 reactors.
                                NO (in) — NO  (out)
       t Material balance error =	—u/.  ..  ,x	 x 100.
                                        x 'ln'
       §One reactor was countercurrent.
                                     m-8

-------
                                                         Table III-3. Miniplant Reactor Experiments — Irrigation with Nitrose (One 15-ft Reactor in Counter current
                                                                     Operation Reactor Packed with 3/8-in. Intalox Saddles)
 i
to
Run No.
Reactor temperature (°F)
Gas flow rate (SCFM)
Gas feed:
SO2 (ppm)
NO, (ppm)
NO (ppm)
Acid flow rate (cc/min)
Acid feed:
HNSOg (%)
Gas effluent:
SO2 (ppm)
NO2 (ppm)
NO (ppm)
Acid effluent:
HNSOg (%)
Reactor residence
time (sec)
Reaction yield (%)
NOX material balance
error (%)
dc\ f n«-n.-iril It'll 0 «*-•<=»
52
210
2

3500
5800
1900
330

1.9
76.0

850
7200
4700

1.2
76.3
29

76.0
+ 21


208
2

3500
5800
1900
330

1.8
72.0

750
5100
3850

1.0
72.3
29

78.5
+ 33
NOx(in) -
52A
218
2

3100
6250
1775
320

1.10
69.4

750
10,800
5010

0.77
69.5
28

75.9
-7
NOX (out)

222
2

3100
6250
1775
320

0.78
72.1

550
4350
4100

0.47
72.4
28

79.0
+ 23
                                                                                                       100
                                                                                                       0.8
                                                                                                      71.3
1350
4300
4200
                                                                                                      0.39
                                                                                                      71.3
                                                                                                        14
                                                                                                      51.7
                                                                                                       -1
                                                                                                                 20
          1.29
          73.1
 100
4000
3750
          0.81
          72.3

            28
          98.5
          + 12
                                                                                                                           25
          1.26
          73.1
 300
4650
4200
          0.89
          72.9
            28
          89.7
           + 1
                                                                                                                                     35
          1.53
          73.1
 100
5600
4250
          0.93
          73.0
            28
          96.4
            -2
                                                                                                                                               35
          1.53
          73.1
 325
5700
4025
          0.93
          73.0
            28
          88.8
            -1
                                                                                                                                                          230
             0.06
             68.1
-1700
 4100
 3550
             0.14
             68.4
               27
             42.5
             -10
                                                                                                                                                                       180
              2.13
              69.8
  1850
18,000
  3100
              0.20
              70.4
                27
              43.9
              + 18
                                                                    NOX (in)
                                     fUnstahle system.

-------
                                                                                  Table III-3. (Continued)
 I
H»
o
Run No.
Reactor temperature (°F)
Gas flow rate (SCFM)
Gas feed:
SO, (ppm)
Ntt (ppm)
NOlppm)
Acid flow rate (cc/min)
Acid feed:
HNS05 f%)
H,SO. (%)
2 4
Gas effluent:
S02 (ppm)
NO2 (ppm)
NO (ppm)
Acid effluent:
HNS05 (%)
Reactor residence
time (sec)
Reaction yield (%)
NOx material balance
error {%)
'Material balance
56B
217
2

3300
5900
1050
200

1.66
69.8

1000
15,000
2900

0.26
69.8
28
66.6
+ 18
N0x

56C
201
2

3300
5900
1050
210

1.86
69.4

700
12,000
2900

0.23
69.8
29
78.8
+ 38
(in) - N0x (out)
N0x (in)
57A
201
2

3000
5875
2200
45

1.65
67.8

I100J
15,000
~6000

0.16
68.9
29
63.2
-76
57A'
200
2

3250
0
0
35

2.16
70.1

2300
5000

0.25
67.3
29
29.3


200
2

3250
6000
1800
35

2.16
70.1

500
4500
5000

0.25
67.3
29
84.6
+ 16
57B
225
2

3250
6000
1800
50

2.69
69.5

800
6000
5050

0.55
73.6
28
75.5
+ 18

226
2

3250
6000
1800
35

—

875
8000
5050

—
28
74.4

57B'
225
2

3300
6100
2600
35

2.55
71.6

250
2400
6000

0.21
70.4
28
92.5
+ 35
57C
250
2

2675f
6200
2400
40

2.40
70.0

1450f
8600
7000

0.82
76.6
27
45.9
-25
58
220
2

2575f
7500
3175
30

1.01
72.4

150f
7500
2550

0.62
72.7
28
94.3
+ 10

220
2

2625f
7500
3175
30

1.19
72.6

250f
7500
2550

0.59
72.7
28
90.5
+ 13
59
225
4

3200f
6400
2150
35

0.92
72.0

450f
3800
2800

0.52
72.3
14
79.6
+ 25
                        tCorrected for zero error.

                        ^Instruments in error.

-------
                                            Table III-4. Mlniplant Reactor Experiments — Irrigation with Nitrose (One 15-ft
                                                        Reactor in Cocurrent Operation Reactor Packed with 3/8-m. Intalox
                                                        Saddles)

Run No.
Reactor temperature (°F)
Gas flow rate (SCFM)
Gas feed:
SO2 (ppm)
N02 (ppm)
NO (ppm)
Acid flow rate (cc/min)
Acid feed:
HNSO5 (%)
H2S04 (%)
Gas effluent:
SO2 (ppm)
N02 (ppm)
NO (ppm)
Acid effluent:
HNS05 (%)
H.SO. (%)
2 4
Reactor residence
time (sec)
Reaction yield (%)
NOV material balance

60
228
4

2450t
6000
2850
205

1.3
71.0

400t
3550

0.8
72.1
14

83.8
—


228
4

2450f
6000
2850
200

1.5
71.5

400t
4100
3425

1.08
71.0
14

83.7
421


213
4

3200f
6400
1800
200

1.93
72.2

250f
7100
~5500

0.61
71.2
14

92.4
+ 15
61

221
4

3300f
6300
3025
30

1.83
70.3

soot
4900
5000

0.31
70.4
14

75.7
+ 6
62A

222 J
4

2875 1
6000
1000
305

1.29
70.4

350f
6600
2375

0.78
70.7
14

87.7
+ 22
62B

222 {
4

2575f
6160
2250
380

2.65
71.3

150f
12,500
11,400

1.27
72.3
14

94.3
-3
erVor (%)
                                 NOx (in) - NOX (out)
        *Material balance error =	
                                       N0x (in)

        tCorrected for zero error.

        JReactor  temperature:  top - 195 °F, middle - 234 "F, bottom - 230 °F.

-------
APPENDIX IV. DATA FROM SCRUBBER/STRIPPER EXPERIMENTS
                        IV-1

-------
Run No.
 NA
 HD
      Gas
 Acid
SCFM

 GPM

SCFM
                                          67
                              Table IV-1. Scrubber/Stripper Data

                                                    68 (Repeat of 67)
               240/   230/   230/   235/  265/
               300    300    300    300   300

               240/   240/   250/   250/  240/
               290    300    310    315   310
                                           5.6
[C 1
5

[C ]
24

[CNQ ]
2


NO Scrubbing
rSoJ


NO Mail. Bal.
X
[c 0]
2
1
2
3
1
2
3**
Flue Gas
1
2
3
Efficiency
Flue Gas
1
2
3
Error

Flue Gas ***
Air
wt%
"
11
wt%
1'
"
ppm
"
"
ii

ppm
It
if
ir
%



	
	
	
	
	
—
3900
—
3400
—
—
1300
950
erratic
—
	

~6
~1
                                                  5.6     5.6    5.6    5.6
                                          0.22   0.22    0.22   0.22   0.22
                                                 0.08    0.11   0.22    —
                                                 0.34    0.37   0.76    —
                                                 0.08    0.09   0.18    —

                                                  —    76.6    —     —
                                                  —    78.0    —     —
                                                  —    77.4    —     —

                                                 4150   3450   3600   3050
                                                  875    400    500      0
                                                 1000    400      0    350


                                                 71.1   73.2   68.3   66.4

                                          1300   2600   2375   2735   3025
                                                 1075   1150   1500   2050
                                                 1225   1400   1900   1850


                                           —     8.9    -1.9  -51.8    —

                                                  ~6     ~6    ~6    ~6
A
145/
205
ISO/
200
5.6
0.24
—
	
B
140/
285
160/
190
5.6
0.24
0.30
74.7
C*
1807
285
170/
220
5.6
0.22
—
—
D
2007
285
2007
220
5.6
0.22
0.17
0.25
0.08
76.0
76.0
76.0
E
2457
280
2007
220
5.6
0.22
0.15
0.23
0.06
76.0
76.0
76.0
F
2457
280
2007
220
5.6
0.22
—
—
G
250/
278
230
5.6
0.2
0.23
0.29
0.14
76.0
76.0
76.0
H
2507
278
230
5.6
0.2
—
—
I
2457
275
235
5.6
0.2
0.16
0.27
0.06
76.3
76.3
76.3
J
2457
275
235
erratic
0.2
0.59
0.35
0.18
75.5
82.1
75.7
                                                   3300  3900   3200   3150   3300  2300   3100   3300   3450  3450
                                                    800    375   3175   2100   2000  1800   2325   2050   1450   —
                                                   2500    —   5050   2900   3175   —    3025    —    2000  5050


                                                   79.0   90.0   21.0   39.6   58.8   51.8    40.6    36.0   52.T   61.0
                                                   2900   2950   4100   3975
                                                    500    300   2600   2200
                                                    500    —    3500   2400
4700   4325  4100   3500   3625   3350
1300   1400  1900   2300   1900    —
1950    —   2200    —    2500   5100
                                                    —    —     —     2.3    22.9   —

                                                    ""O    "-6    —6    -^G     -^6     ~6
              9.3     —     9.1    —

              ~6     ~6     ~6    ~6
                                                                                                      •f
                             Key to Effluent Streams:    1 - N0x scrubber 4;  2 - NO scrubber 2;  3 - stripper.

                            *Plant shut down after 68E and started up again. Sample line problems (this is where
                             the Teflon sample lines fused and gave us difficulty).
                           **No SO2 was fed to the scrubbers during Runs 68-72.
                          ***No H2O analyses were made on the scrubber and stripper effluent gases.

-------
                                                                                               Table IV-1. (Continued)
<
CO
                     Run No.
                      NA
                      HD
                     -'Flue Gas
                     [CHNSOC
                      "N0n
                1
                2
                3

                1
                2
                3

             Flue Gas
                1
                2
                3
NO Scrubbing Efficiency

[CNO]         Flue Gas
                1
                2
                3

NO Mail. Bal. Error

fCH n]        Flue Gas
  H2U         Air
 op



 °F

SCFM

 GPM

SCFM

 wt%

  II

 wt%

  M

 ppm
                                                 ppm
70(2
A
230/
260
250/
270
5
0.19

0.03
0.51

78.2
78.0

2800
400
700

27.5
3650
1050
950

-43.7
C
~*> 1
Strippers)
B
2357
265
255/
275
5
0.16

0.03
0.51

78.2
78.0

2900
550
900

76.4
3350
925
875

	
— fi
-1
C
2357
265
255/
275
5
0.16

0.08
1.05

78.4
78.6
—
2950
700
1000

77.4
3425
750
875

__
-6
«
D
240/
270
2407
295
5
0.17

0.42
1.13
0.21
77.9
78.7
78.2
3500
1200
1350
—
71.3
3175
750
850
—
-82.8
~6

E
255/
305
245/
295
5
0.14

	
	
—
	
	
—
3800
1125
1200
—
72.4
3425
875
950
—
—
— fi
— 1
F
2557
305
245/
295
5
0.14

0.29
0.80

77.3
78.0
78.7
3350
1300
1400
—
65.8
3350
1000
1100
—
—
-6
•f
G
2607
280
245/
295
5
0.16
2.25
0.31
0.81
0.31
77.5
78.0
78.9
3650
1300
1300
—
67.9
3350
950
1075
—
-15.4
-6
«
70 Repeat (2
H
2457
260
-260
5
0.16

	
—
—
	
—
—
3100
300
1600
—
74.5
3750
1400
2250
—
—
~6
<•
J
170/
265
330/
280
5
0.18

0.02
0.45*
0.01
	
—
—
3050
400
600
—
79.0
3350
950
925
—
-20.5
~6
4
Strippers)
K
175/
260
230/
280
5
—

—
—
—
—
—
—
3300
400
1000
1400
82.0
3350
800
1100
1800
—
~6
-1
L**
240/
260
230/
285
5
—

—
—
—
80.4
79.3
78.9
3600
1200
1700
—
58.0
3300
1400
1725
—
—
a
«
71
AT
230/
~250
-240
5
0.18

—
—
—
—
—
—
2900
1900
2700
—
51.4
2550
750
950
—
—
-1
— 1

BT
1707
255
1907
240
5
0.18

0.07*
0.25*
0.02*
77.0
77.0
77.0
3000
2300
2900
—
36.0
2150
1000
1025
—
-27.0
-1
<•

CJ
170/
255
225/
260
5
0.16

0.07*
0.38*
0.05*
77.2
77.2
77.2
3000
2000
2700
—
50.6
2850
925
1050
—
-20.0
~6
~ 1
                                                  Key to Effluent Streams:

                                                 *L'sing acid blank for analysis,
                                                "Instrumentation problems.
                                                 tDry gas feed.
                                                 JWet gas feed.
                                                       1 - NOV scrubber 4; 2 - NOX scrubber 2; 3 - stripper.

-------
                              Table IV-1. (Continued)

Run No.
Relative Time hr.
TNA °F
T2 - Avg. °F
T4 - Avg. °F
THD °F
THD - Avg. °F
QFlueGas* SCFM
QAcid CPM
QAir** SCFM
[CHNS051 1 wr%
2
3>t

[CH2SO41 L wt,^
2,
3
[CfjO2l Flue Gas ppm
1
2
3
4
[Cfjol Flue Gas ppm
1
2
3
4
NO Scrubbing Efficiency
10.0ft. %
19.0ft.
26.5ft.
NOx Matl.Bal. Error %
74
A
0
1907
290
252
210
230/
255
247
5.6
0.28
2.55
-
-
~
-
~
~
500
-
50
_
1100
-
550
_

_
_
-
-

B
0.5
190/
290
252
217
2307
255
247
5.6
0.28
2.55
-
-
-
-
-
-
500
-
55
_
1000
-
325
_

_
_
-
-

C
1.0
195/
280
252
217
240/
260
250
5.6
0.27
2.55
-
-
-
-
-
-
450
-
75
_
725
-
375
_

_
_
-
-

D
2.25
195/
280
252
217
240/
260
250
5.6
0.28
3.6
0.02
0.06
0.03
69.8
69.8
69.8
575
110
170
20
450
175
160
150

_
.
71.0
10.0

E
3.75
1957
280
252
207
2407
260
250
5.6
0.28
3.6
-
-
-
-
-
-
580
70
120
:
300
150
100
~



75.0
-

F
5.25
1907
250
227
207
2457
255
250
5.6
0.28
3.6
.008
.015
.019
78 0
77.7
77.3
470
10
70
~
300
110
100
-



84.5
-

G
7.25
1957
250
227
213
245 /
250
250
5.6
0.26
3.6
-
-
-
_
-
-
_
30
-
0
_
100

110



83.2
-

H
8.25
1957
250
231
213
2457
250
250
5.6
0.31
3.6
.007
.008
.005
78.0
77.3
77.9
645
-
40
-
450
_
75
-



89.0
-
75
A
0
2107
290
272
253
245 /
260
255
5.6
0.25
3.4
0.05
256
.010
79 2
77.2
79.2
3100
1000
1300
1350
3725
650
1000
5800



76.0
6.3

B
0.5
2107
290
272
255
2457
260
254
5.6
0.25
3.4
.049
.258
.015
78.2
78.2
78.2
3100
1000
1300
1300
3725
675
1050
6000



75.5
-6

C
1.5
210/
290
272
255
245'
260
254
5.6
0.25
3.4
049
.258
.015
78 2
78 2
78.2
3100
1000
1300
1450
3760
575
950
5900



77.0
-6

D
3.0
2157
275
252
232
255 /
265
258
5.6
0.25
1.9
070
320
.008
77 9
77 '9
78.2
3100
1000
1250
5100
3850
500
775
8200



78.4
-2.2
Key to Effluent Streams:
,tThe flue gas contains ^ 6% H2O.
  The air fed to the strippers contains ^1
                          1 - NO scrubber 4 (7.5 ft.); 2 - NO  scrubber 2 (19 ft.)
                          3 - stripper; 4 - NOX scrubber 2 (halfway up the 19 ft.  scrubber).
                                       ,H20.

-------
                                                                   Table IV-1.  (Continued)
Run No.
 NA
'HD
 Flue Gas
 Acid
 Air
[C
  NCL
                1
                2
                3
                1
                2
                3
             Flue Gas
                1
                2
                3
NO Scrubbing Efficiency
[CNfJ        Flue Gas
                1
                2
                3

NO Matl. Bal. Error
[CH „]       Flue Gas
  H2°          Air
SCFM

 GPM

SCFM

 wt%
  rt


 wt%
  If
  II

 ppm
                            ppm
72
A
ISO/
260
250/
270
4
0.17
0.30
0.64
0.21
77.5
71.2
77.7
3050
2250
2300
45.4
3050
1075
725
-47.3
~6
~1
B
ISO/
265
250/
270
4
0.16
0.30
0.60
0.30
76.6
77.7
77.5
3100
2150
2250
48.4
3100 -
1050
825
-16.4
~6
4
C
ISO/
260
255/
270
4
0.18
0.70
0.76
0.30
77.3
77.3
77.3
3100
2300
2400
44.8
-3400
1150
775
-44.4
~6
~1
                             Key to Effluent Streams:
                                                        1 - NO scrubber 4;  2 - NO  scrubber 2; 3 - stripper.
                                                              X                 X

-------
                             Table 1V-1.  (Continued)
          Run No.
Relative Time

TNA

T2 - Avg.
^4 - Avg.

TIID

THD -  Avg.

Q Flue Gas
Q Acid
QAir
            1
            2
            3
            1
            2
            3
                    hr.
  °F

  "F

  op

SCFM

 GPM

SCFM

 wt%



 wt%



 ppm
[CNO!
                    pp
          Flue Gas
            1
            2
            3
            4
          Flue Gas
            1
            2
            3
            4
NO Scrubbing Efficicnc
   x      10.0ft.
          19 0 ft
          26.5 ft.
N0x Matl.Bal. Error
76
A
0
220/
275
264
242
240/
260
251
5.6
0.26
1.9
;
-
540
150
B
1.0
2307
280
264
242
250/
260
251
5.6
0.27
1.9
.009
.038
.006
78.7
78.7
78.6
550
235
350
330
C
4.75
215'
260
231
252
2507
260
253
5.6
0.27
1.9
.015
.032
.002
79.1
78.7
78.9
620
360
320
D
5.25
225/
265
234
231
2507
260
252
5.6
0.28
1.9
.015
.032
.002
79.1
78.7
78.9
600
330
350
380
                             825    700    450    475
                             350    275    150    150
                                    300    150    200
                                   2050     -     3025
                                                           77'
                                                           1257
                                                           260

                                                           244
                                                           243
                                                           240/
                                                           255
                                                           251
                                                            5.6
                                                           0.25
                                                            1.9

                                                           0.19
                                                           .023
                                                           .015
                                                           78.6
                                                           78.2
                                                           78.9
                                                            330
                                                            300
                                         150
                                         150
78**
A
0
220'
270
264
235
2407
260
251
5.6
0.25
1.9
.011
.037
.007
79.1
79.7
79.4
530,
100X
400,
300^
B
3.0
220/
270
259
237
240/
260
251
5.6
0.25
1.9
015
.022
.007
78.2
77.9
78.3
850
300
370
150
1075
475
400
2000
                            63.5
                                   59.3
                                    8.5
                       52.3
                       -2.3
55.4
57.2
60.0
43.0
   Key to Effluent Streams:
                            1  - NO scrubber 4 (7.5 ft.);  2 - NO* scrubber 2 (19 ft.)
                            3  - stripper; 4 - NOX scrubber 2 (halfway up the 19 ft. scrubber).
 ,tNoisy run - levels hard to determine.
   New NO oxidizer - 0.05 ft3.
  ''Readings not steady.
                                        IV-6

-------
                                                                                     Table IV-1. (Continued)
<



Run No.
Relative Time

TNA
T2 - Avg.
T4 - Avg.
THD
THD - Avg
Q- Flue Gas
Q Acid
QAir
[CHNS05]

[CH so 1
24

[CNO2I



[CMQ]













1
2
3
1
2
3
Flue Gas
1
2
3
4
Flue Gas
1
2
3
4


hr.

°F
op
°F
op
op
SCFM
GPM
SCFM
wt%

wt%
"
"
ppm
11
"
M
ppm


11
"
79
A*
0
275 /
270
262
242
240 /
260
252
2.8
0.12
1.9
.009
018
.013
78.7
78 6
78.6
500
0
190
-
-
450
225
150

-

B
16.5
2257
275
259
245
2557
270
260
2.8
0.12
1.9
-
-
_
-
-
470
180
_
0
-
450
275
_
650
-

C
19.25
2257
275
259
257
255 /
270
260
2.8
0.12
1.9
015
.026
.007
80.2
80.3
80.0
490
120
_
-
-
450
175
_
-
-

D
21.0
225/
275
259
257
255/
270
260
2.8
0.12
1.9
010
040
.007
79.6
79.6
79.6
840
180
-
0
-
825
400
-
2500
-
NO Scrubbine Efficiency
X


10.0ft.
19.0ft.
26 5 ft.
%
%
y
70
-
_
70.0
-
_
50.5
-
-
69.0
-
-
67.5
                                             NOx Matl.Bal. Error
80
A
0
250/
280
269
262
180/
265
227
2.8
0.25
1.9
022
.029
.022
80.0
80 0
80.0
570
130
550
175
67.0
29.4
B
3.5
255 /
280
265
267
250/
265
259
2.8
0.26
1.9
015
019
.001
79.8
79.8
79.8
460
85
500
300
60.0
27.1
C
6.5
260/
285
267
272
260/
275
267
2.8
0.26
1.9
-
-
490
50
500
260
68.7
-
D
7.0
260/
285
267
272
260/
275
267
2.8
0.26
**
.015
022
.011
80.7
80.7
80.7
515
100
185
150
425
200
110
1675
68.2
16.9
E
7.5
260/
285
267
272
260/
275
267
2.8
0.26
1.9
-
;
85
1100
;
-
F
7.75
260/
290
267
272
260/
280
267
2.8
0.26
1.9
-
;
550
90
190
65
425
260
125
1065
62.1
-
                                                        Key to Effluent Streams:
1 - NOX scrubber 4 (7.5 ft.); 2 - N
-------
00



Run No.
Relative Time
TNA
T2 - Avg.
T4 - Avg.
THD
THD - Avg.
Q Flue Ga$
Q Acid
QAir
[CHNSCkl


[Cf^soJ










1
2
3
1
2
3
[CN02] Flue Gas



[CNO] Flue




2
3
4
Gas
1
2
3
4
hr.
°F
°F
OF
°F
°F
SCFM
GPM
SCFM
wt%
"
"
wt%
11
"
ppm
"
"
"
ppm
"
"
"
"
81
A
0
2607
280
271
271
260/
280
267
2.8
0.26
1.9
015
.049
.011
80 9
80.9
80.9
1100
150
310
-
-
1080
325
160
-
-

A'
0.25
260/
280
271
271
260 /
280
267
2.8
0.26
1.9
_
-
-
_
-
-
145
-
250
-
.
260
-
2900
-

B
1.5
2557
285
268
272
265/
280
270
2.8
0.26
1.9
.008
.013
.011
80 6
80 7
80.2
1000
190
300
270
-
1050
260
125
2150
-

C
2.5
255/
285
268
272
265/
280
270
2.8
0.26
1.9
.004
.007
.006
80.6
80.6
80.9
1000
-
-
_
850
_
-
-
-

D
4.0
255/
285
266
274
265 /
280
271
2.8
0.26
1.9
.003
014
.006
80.9
80.9
80.7
1050
150
240
200

1050
250
160
2385

NO Scrubbing Efficiency
x 10
19
26.
NOX Matl.Bal
Oft.
Oft
5 ft.
. Error
V
/D
(r
"

_
_
78.3
9.8
_
.
81.5
-
_
_
78.0
61.8
_
_
_
-
_
_
81.0
59.8
           Table IV-1. (Continued)

                           82(a)
                            A

                            0

                           220/
                           280

                           207

                           235

                           245/
                           270

                           258

                            4.9
                           0.26

                            1.9

                           .026
                           .019
                           .015
                           82 0
                           82 0
                           82.0

                            275
                            170
                            200
                             85
                                                                                                                              D
                                                                                                               2.0    4.75   5.5    6.0   6.75   7.5
245/
280
271

269
250 /
270
261

 4.9
0.26
 1.9
.017
.026
.011
80.5
81.1
81.5
 265
 150
 180
  20
                                                                                                         250     235
                                                                                                         170     100
                                                                                                         175     100
                                                                                                         200     165
                                                                                                                      260/
                                                                                                                      295
                                                                                                                      279
                                                                                                                      271
                                                                                                                      265/
                                                                                                                      290
                                                                                                                      279
                                                                                                                       4.9
                                                                                                                      0.23
                                                                                                                       1.9
                                                                                                       28.5
                                                                                                       34.3
                                                                                                       13.7
                                  44.0
                                  50.0

                                 -10.9
 275
 140
 200

 210

 450
 250
 225

 275


33.2
41 4
45 0
265/
295
280
271
280/
300

289
 4.9
0.23
 1.9
 031
 061
.013
81.9
81.9
80.7
 230
 120
 165
  15
 185
 275
 225
 150
 280
 235

 7.8
37.7
31.8
-103
              2657
              295
              280
              271
              280,'
              300

              289
               4.9
              0.23
               1.9
 230
 105
 150
  0
 190

 235
 140
 135
 200
 160


24 7
38.7
47.4
270/
275

285

273

2857
305

292

 4.9
0.23

 1.9

.035
 068
.010

81 5
81.3
81.1
 230
  95
 135
  0
 170

 235
 155
 135
 195
 160
              270/
              295

              285

              273

              285/
              305

              292

               4.9

              0.23

               1.9
230
 95
135
 0
160

235
250
135
195
160
                           29.0   31 2
                           41 9   41 9
                           47.3   47.3
                          <-100
                                                    Key to Effluent Streams:
1 - NOX scrubber 4 (7.5 ft.); 2 - NO., scrubber 2 (19 ft )
3 - stripper;  4 - NOX scrubber 2 (halfway up the 19 ft. scrubber).

-------
                                Table 1V-1.  (Continued)



Run No.
Relative Time
TMA
NA
T2 - Avg.
T4 - Avg.
T
HD
THD - Avg.
Q Flue Gas
Q Acid
Q Air
lcHNSOsl

fcH2SO4'

[CN02] Klue




[CNQ] Flue














2
3
2
3
Gas
1
2
3
4
Gas
1
2
3
4
hr.
01-
'"
OF
"p
°F

°F
SCFM
GPM
SCFM
wt%

wt%
"
ppm

"
"
"
ppm
n
"
"
"
NO- Scrubbing Efficiency
x 10
19
26.
NOX Matl.Bal
Stripper Matl
Oft.
Oft
5 ft.
%
%
%
82(b)
A
0
265/
300
284
271
285/
310
295
4.9
0.23
1.9
-
-
-
-
485
265
320
0
365
500
275
255
175
325
Not
Steady
State
45.3

B
0.75
27 5 /
300
284
284
285/
310
293
4.9
0.23
1.9
-
-
-
-
-
250
305
200
350
-
250
240
2600
250

39.0
44.7
49.0
.Error %
.Bal.
Error %
Key to Effluent Streams:

-
1 - NOX scrubber
3 - stripper; 4 -

C
2.0
265/
295
281
279
280/
300
292
4.9
0.23
1.9
.033
.059
.014
80 6
80.9
81.1
490
210
255
190
315
500
140
175
2600
275

40.3
56.6
64.5
-50
-
4(7.5

D
3.0
270/
300
283
277
280/
305
295
4.9
0.23
1.9
037
.059
.011
80 7
80 7
81.1
490
150
230
250
240
550
150
175
2900
275

49.7
58 4
70.7
-49.5
-
ft.); 2
NOX scrubber
82(c)
A
0
270/
300
283
277
265/
305
292
4.9
0.24
1.9
.048
066
.018
81 3
81 5
81.3
1050
570
680
390
770
950
300
400
4200
550

35.0
46.0
56.5
6.5
-66.8

B
1.5
270 /
300
283
277
265 /
305
292
4.9
0.24
1.9
041
066
.022
81.3
81.3
81.1
1050
490
600
80
680
925
250
400
1550
550

37.6
49.3
63.2
14.3
19.4
- NOX scrubber 2
2 (halfway
up the

C*
3.5
270/
300
283
277
265/
305
292
4.9
0.24
3.8
037
066
.019
81.5
81.5
81.3
1000
420
-
10
-
950
225

1025
-

-
_
67.2
6.5
7.2
(19ft.)
19 ft. scrubber).
High stripper air.
                                        IV-9

-------
 I

O
                                                                   83a
                                                                              83b
           Table IV-1.  (Continued)


         83c       83a'       83b'
                                               Run No.
                                     Relative Time
                                                          hr.
                                                                                                                                           83b"
TNA
T2 - Avg.
T4 - Avg.
THD
T
1 HD - Avg.
QFlue Gas
QAcid
QAir (St)
fCHNS05l 1
3
fcH2SO4l 1
3
fCNO2l F'116 Gas
1
2
3
4
[CNO] Flue Gas
1
2
3
4
°F
"F
"F
"F
"F
SCFM
GPM
SCFM
wt*

wt%

pRm




ppm




275/
310
279
295
240/
270
250
8.6
.40
3.1
.015
.022
.015
80.9
80.9
80.9
320
0
10
50
30
250
250
300
550
325
255/
295
284
265
235/
270
254
8.6
.40
3.1
.018
026
.018
80.7
80.7
80.7
480
0
0
10
10
575
470
475
375
475
260/
285
273
272
230/
270
253
8.6
.40
3.1
.018
.037
.018
80.9
80.9
80.9
1100
0
0
5
0
1000
700
700
500
650
250/
275
253
265
250/
275
-
8.8
.39
3.1
.022
.033
.014
80.9
80.7
80.9
240
65
95
15
140
240
120
125
650
150
260/
290
287
275
260/
275
-
8.8
.38
3.1
.018
.029
.015
80.8
80.6
81.3
520
320
375
130
435
475
225
275
1000
350
280/
285
282
280
270/
280
-
8.8
.38
3.1
.029
066
.018
80 4
80 4
80.6
975
490
500
340
615
1050
385
500
2000
635
280/
295
283
287
270/
290
_
8.8
.39
3.1
.026
.070
.018
80.9
80 7
82.3
925
455
515
300
625
1000
375
460
1975
575
260/
280
269
269
270/
285
_
8.8
.39
3.1
.018
030
.015
82.6
81 2
82.0
530
250
310
100
410
490
240
275
1225
360
275/
285
_
280
265/
285
275
6.0
.40
.6
018
025
!014
79.4
79 1
79! 1
240
60
90
50
110
300
140
160
1675
240
2757
280

279
27 O/
285
281
6.0
.40
.6
.015
022
[on
79 4
79 4
79^4
260
80
120
0
120
275
125
125
1400
175
NO Scrubbing Efficiency
x 10.0ft
19.0ft.
26.5 ft.
NOx Matl.Bal. Error
w
ft

%
37.7
45.6
56.1
21.6
54.0
55.0
55.0
31.1
69 0
66.7
66.7
42.6
39.6
54.3
61.7
6.7
21.1
34.7
45.2
16.2
36.7
49.4
55.7
12.7
37 7
49 4
56.9
7.8
24.5
42 6
52 .'0
20.2
35 2
53 7
63^0
-18.0
44.9
54 2
61 ! 7
4.3
                                                      Key to Effluent Streams:
1 - NOx scrubber 4 (7.5 ft.);  2 - NOX scrubber 2 (19 ft.)
3 - stripper;  4 - NOX scrubber 2 (halfway up the 19 ft. scrubber).

-------
                                     Table IV-1. (Continued)
                                84c

Run No.
Relative Time
TNA
T2 - Avg.
T, - Avg.
4 6
THD
THD - Avg.
Qplue Gas
QAcid
Q Air (St)
2
3
[CH2S04] 1
3
[CNQ2] Flue Gas
2
3
4
[Cjsiol F^ue <~'SLS
1
2
3
4


hr.
op
°F
°F

op
SCFM
GPM
SCFM
wt_%
wt%
ppm
"
ppm
••
NO Scrubbing Efficiency
x 10.0ft. %
19.0ft.
26.5ft.
NO Matl. Bal. En
ror%


0
280/
280
_
280
275/
290
281
6.0
.40
.6
.015
037
.011
80.0
80.0
80.0
530
190
270
280
260
500
150
175
3025
275
48.1
56.1
67.0
-1.8
— — -

1.0
27 5/
275
_
274
275/
290
281
6.0
.40
.6
018
.037
.011
80 0
80.0
80.0
500
200
;
475
110
-
68.2
-3.8
— 	

0
270/
280
-
274
275/
290
281
6.0
.40
.6
.019
041
.008
80.2
80.2
80.2
1050
415
515
1100
530
1050
250
325
6000
550
48.7
60.0
68.3
25.2
B

0.5
260/
280
271
270
27 5/
295
285
6.0
.40
.6
.023
.038
.011
80 4
80.4
80.4
1000
420
-
1100
250
:
68.1
28.9
A B* C** D**

0 5.0 5.25 6.0
265/
290
283 -
276 -
270/
300
289
1.4 -
0.1 -
3.1 -
.019
022 -
.011
83.6
83.6
83.6
1000 HW) fsQ/l 840
60 35 40 10
95 - - 15
80 100
150 50
1250 IW W 900
250 375 400 400
225 - - 375
500 865
350 350
77.7
QC Q _
OO .0 7 R S /
86-2 8i;s 79-5
63.6
A

0
270/
315
280
292
235/
290
269
1.4
.11
3.1
_
_
200
0
0
50
250
150
150
250
125
;
-
B

1.25
245/
310
278
278
235/
290
269
1.4
.13
3.1
019
022
.011
80.7
80.7
80.7
210
5
30
70
250
150
175
175
46.7
56 5
66.3
-14.7
C

1.75
2457
310
278
278
235/
290
269
1.4
.13
3.1
022
034
.015
80.7
80.7
80.7
230
30
-
250
125
-
67.7
-36.6
 "Two measurements of feed level.
"'Difficulty in achieving steady readings
- sample lines probably plugged.

-------
                                                                                           Table IV-1.  (Continued)
t-»
to
                                                                  85b
Run No.
Relative Time hr.
TNA °F
T2 - Avg. »F
T4 - Avg. op
THD °F
T
1 HD - Avg. "F
Q Flue Gas SCFM
Q Acid CPM
Q Air (St) SCFM
[CuMsoJ 1 wt %
a 2
3
[CH2S04] 1 wt,%
3
[CNO2J Flue Gas ppm
2
311
4
[CNQ] Flue Gas ppm
1 "
2 "
3
4
NO- Scrubbing Efficiency
x 10.T) ft. %
19.0ft. 'y
26.5ft.
NOxMatl.Bal. Error %
A
0
260/
290
276
274
240/
285
265
1.4
0.12
3.1
.023
.038
.011
80.9
80.9
80.9
550
80
140
20
210
475
100
125
525
200

60.0
74.1
82.4
-7.3
B
1.0
255/
275
260
268
240/
290
267
1.4
0.12
3.1
.030
.041
.014
80.9
80.9
80.9
540
70
110
0
150
500
100
125
700
160

70 2
77 4
83.7
-5.0
A
0
250/
280
263
268
240/
290
268
1.4
0.12
3.1
.041
.114
.023
81.3
81.3
81.3
1100
90
130
10
180
1000
75
90
625
150

84.3
89.5
92.1
-42.1
B»
1.0
260/
280
270
267
240/
290
267
1.4
0.12
3.1
\
-
1100
240
:
975
100
-

83.4
-
A
0
250/
290
269
290
280/
330
312
2.9
0.1
0.6
.023
.023
.016
84.5
84.5
84.3
230
140
150
10
130
225
90
100
100
150

45.5
49.5
18.2
B
1.25
250/
285
272
278
-
-
2.9
0.08
0.6
.018
.026
.0145
85.2
83.3
84.0
250
170
190
1
250
100
100

42.0
46.0
-13.2
A
0
260/
295
279
271
285/
320
306
2.9
0.1
0.6
.018
013
.015
82.7
81.3
81.9
550
160
400
385
-0
3900

-
68.7
B
1.0
260/
295
281
267
285/
320
299
2.9
0.11
0.6
.024
.009
.013
83.1
83.1
84.5
570
210
25
400
305
325
0
10
3900
125

54.0
70.5
76.5
<50
A
0
270/
285
278
274
285/
310
296
2.9
0.12
0.6
.011
.011
.013
84.5
82.7
83.6
510
110
140
1140
200
400
25
85
4050
125

64.3
85.2
<50
B
0.5
270/
285
278
274
285/
310
296
2.9
0.12
0.6
.011
.013
.011
84.7
83.1
84.5
510
110
155
1400
125
400
15
100
3975
315

64 5
72.0
86.4
68.5
C**
5.0
220/
310
268
260
270/
305
285
2.9
0.11
0.6
032
.101
.052
81.5
82.3
82.2
540
10
90
-1200
625
100
135
-5000

80.5
91.4
13.2
D
7.5
265 /
295
281
276
290 /
310
303
2.9
0.10
0.6
.013
.090
.013
83.3
80. 5/
82.5
525
55
95
650
110
700
140
150
4400
230

74 0
79.9
84.2
-32.7
                                                    "Heater failed;  copper powder exposed to acid in Scrubber 2
                                                  "Acid flow variations - wide temperature fluctuations.
                                                    /System was cooled down between 5.0 and 7.5 hours and may have picked up some water

-------
                                                                                    Table IV-1. (Continued)
 I
l-t
CO
                                                             86c
                                                                              86d*
                                                                                         87 a
                                                                                                    87b
                                                                                                               87c
                                                                                                                          88a
                                                                                                                                     88b
Run No.
Relative Time hr.
TNA
T2 - Avg.
T4 - Avg.
THD
OF
°F
°F
°F
THD - Avg. UF
Q Flue Gas SCFM
Q Acid
Q Air
[QHNSOS]
[CH2S041
[CN021

[CNO!
GPM
SCFM
1 wt%
2
3
1 wt%
2
3
Flue Gas ppm
1
2
3
4
Flue Gas ppm
1
2
3
4
NO Scrubbing Efficiency
x 10 () ft. %
19.0ft. (t
26.5ft.
NOV Matl.
. Bal. Error %
0
260/
295
283
274
300/
320
305
2.9
0.1
0.6
026
.106
.015
83.1
82.5
82.5
930
15
60
790
110
1075
125
125
4850
225
83.3
90.8
93.0
25.7
1.5
270/
290
284
277
290/
320
306
2.9
0.1
0.6
030
.114
.019
83.1
83.1
82.5
1000
15
50
780
100
1050
125
125
4700
175
86 6
91.5
93.6
24.0

250/
290
270
277
300/
320
312
2.9
0.1
0.6
329**
.038
82.3
82.7
1000
20
490
60
1100
150
175
88.9
91.9
-79.0

260/
290
273
273
270/
290
279
4.9
.25
1.9
.015
.022
.011
82 0
81.6
84.6
260
120
150
90
185
225
110
125
475
140
33.0
43.3
52.6
4.1

270 /
285
278
278
280/
290
285
4.9
.25
1.9
.018
.029
.015
82.3
81.9
81.9
520
205
265
430
350
550
150
165
2025
300
39.3
50 5
67.5
35.8
.
270/
290
275
276
280/
295
287
4.9
.25
1.9
.029
.081
.018
81.4
81 2
81.6
1000
365
445
1280
580
1000
180
250
3390
390
51 5
65.3
72.8
5.9
_
255 /
290
284
262
270 /
285
274
2.9
0.2
3.1
.019
030
.011
81.3
81.3
81.3
230
70
80
70
90
280
160
200
250
340
33.3
45.1
54.9
-
_
260;
280
273
269
270/
285
275
2.9
0.2
3.1
.027
038
.017
81.5
81.5
81.5
510
130
160
90
230
490
150
160
640
225
54.5
68 0
72.0
~
A
0
265/
290
280
272
270/
280'
274
2.9
0.2
3.1
030
.068
.022
81.7
81.7
81.7
1000
150
220
200
340
950
350
375
1225
475
58.2
69.5
74.4
"
B
1.25
27 O/
290
278
273
270/
280
272
2.9
0.2
3.1
.034
061
.019
81.7
81.7
81.7
950
130
_
1050
350
76.0

                                               *Run made with Scrubber 2 only (19-ft.of column).
                                              * 'Concentration double-checked.
Fresh acid from stripper fed to Scrubber 2 directly.

-------
                                                 Table IV-1. (Continued)
 I
H>
it*



Run No.
Relative Time
TNA
T2 - Avg.
T4 - Avg.
T HD
T HD - Avg.
Q Flue Gas
Q Acid
Q Air
[CHNSO 1
HN 5

[CH2S041

ICN02] Fli











1
2
3
1
2
3
je Gas
1
2
3
4
[CNQ] Flue Gas



NO Scrubbir
x 10
19
26,
2
3
4
hr.
°F
"F
°F
op
°F
SCFM
GPM
SCFM
wt%
"
"
wt%
"
ppm
rt
*•
rt
ppm
"
*'
"
92a
A»
0
260/
295
273
280
270/
295
283
4.9
0.25
0.9
.019
026
.008
81.5
81.5
81.5
270
125
150
20
160
250
125
140
1150
165

B
1.0
265/
300
288
270
285/
300
292
4.9
0.25
0.9
.019
026
.011
81.5
81.5
81.5
270
140
-
-
-
240
125
-
_
-
ig Efficiency
.lift.
.Oft.
.5ft.
7?
fr
"
37.6
44.3
52.0
-
-
48.3
NOX Mail. Bal. Error
                                                                      -14.9   -7.8
92b
A
0
255/
280
269
270
290/
300
296
4.9
0.25
0.9
-
~
480
40
80
**
160
550
160
175
**
240
61.3
75.5
80.6
-
B
1.25
260/
290
275
273
280/
300
294
4.9
0.25
0.9
0.02
0.08
.007
82.1
81.9
81.9
560
40
80
325
130
470
150
160
2375
225
65.5
76.7
81.6
-57.2
C
1.75
-
-
-
-
-
-
-
-
\
-
450
575
-
-
                                                                       92c
                                                                       250/
                                                                       285

                                                                       279

                                                                       269

                                                                       285/
                                                                       295
                                                                       290

                                                                        4.9
                                                                       0.25

                                                                        0.9
                                                                        015
                                                                       0.16
                                                                       .006

                                                                       80.9
                                                                       80.8
                                                                       80.9
                                                                       1125
                                                                        145
                                                                        260
                                                                       1100
                                                                        420
                                                                       1100
                                                                        120
                                                                        175
                                                                       4700
                                                                        320


                                                                       66.7
                                                                       80.4
                                                                       88.1

                                                                      -50.8
                                                                                                                       -1125
                                                                                                                        1150
                                                                                                                                  93a
260/
290

273

271

280/
290

278

 2.6

 0.1
 1.6
.011
.049
.009
82.1
80.8
81.2
 280
   0
  10
   0
  25
 225    225
  85    100
 100
 375
 130
                                                                                                                                  69.3
                                                                                                                                  78.2
                                                                                                                                  83.2   78.2

                                                                                                                                 -32.0
275
 10
                                                                                                         93b
260/
305

280

271

280/
300

286
 2.6

 0.1

 1.6
.007
.051
.006

81.8
81.3
81.1
 500
   0
   0
   0
  10
 475
 150
 135
 450
 200


71.3
86 1
84.6
11.6
470
  0
                  500
                  150
                •All runs after 92 were made with 2 strippers in series.
               "Pump broke - reading unsteady.

-------
                                                                                   Table IV-1. (Continued)
                                                           93c
en
Run No.
Relative Time hr.
T NA °F
T2 - Avg. °f
T4 - Avg. -F
THD °F
T HD - Avg. "F
Q Flue Gas SCFM
Q Acid GPM
Q Air SCFM
[QHNS051 1 wt,*
3
[CH2S041 1 wt*
3
[CNOol F\ue Gas ppm
2
3
4
[CNO] Flue Gas ppm
2
3
4
NO Scrubbing Efficiency
x 10.0ft. %
19 0 ft
26.5ft.
NO Matl.Bal. Error %
A B
0
260/
295
274
280
270/
305
286
2.6
0.1
1.6
.016
096
'.009
81.1
81 4
80.4
1200 900
10 0
40
_* -
190
1070 1025
200 175
200
_ *
300

78.4
89.4
90.7 91.9
29.3
A
0
250/
270
264
257
270/
275
272
6.0
0.4
1.6
.023
.037
.011
81.3
81.3
81.3
240
50
70
10
130
225
200
200
700
200

29 1
40 8
46.2
-65.5
B

250/
270
264
257
270/
275
272
6,0
0.4
1.6
.018
.030
.011
81 3
81.3
81.3
230
30
70
_
120
241
225
225

225

26.6
37.2
45.7
-39.3
A

250/
270
264
257
270/
275
273
6.0
0.4
1.6
026
041
.015
81.3
81.3
81.3
540
90
150
20
280
550
250
280
noo
350

42.2
60.6
68.8
2.4
B

2707
290
273
279
2757
280
279
6.0
0.4
1.6
.022
.034
.011
81.3
81.3
81.3
530
80

_
-
525
280
_
-
-

-
-
65.9
4.9
A

2707
290
273
279
2757
280
279
6.0
0.4
1.6
030
053
.015
81.3
81.3
81.3
1100
300
470
230
630
1050
350
375
1450
550

45.1
60.7
69.8
23.4
B

2607
290
268
275
2807
280
279
6.0
0.4
1.6
037
056
.015
81.3
81.3
81.3
1100
290
-
-
-
950
375
-
-
-

-
-
67.6
10.0
A

250'
285
258
268
2707
270
272
8.8
0.4
0.3
;
-
_
-
265
100
160
-
-
250
180
175
-
-

-
35 0
45.6
-
B

250'
285
258
268
2707
270
272
8.8
0.4
0.3
019
.030
.011
80 7
80 7
80.7
300
135
185
730
220
180
135
140
3250
150

22.9
32.3
43.8
-20.2
C

255
280
271
264
270,'
270
272
8.8
0.4
0.3
-
-
-
-
270
-
-
-
175
-
-
-

-
-
-
-
D

255 '
280
271
264
270'
270
272
8.8
0.4
0.3
-
-
_
-
230
85
-
-
-
250
175
-
-
-

-
-
-
-
                                             'Possible instrumentation problem - plugged sample lines.

-------
                                                   Table IV-1. (Continued)
          Run No.
Relative Time

TNA

T2 - Avg.
T4 - Avg.

THD

THD - Avg.
Q Flue Gas

Q Acid
Q Air

[CHNSO51    1

            3
            1
            2
            3
                   hr.
                   °F

                  SCFM

                   GPM

                  SCFM

                   wt%



                   wt%
         Flue Gas  ppm

            2
            3
            4
         Flue Gas  ppm

            2
            3
            4
NC> Scrubbing Efflclenc
   x     10.0 ft.
         19.0ft.
         26.5ft.
NOX Matl. Bal. Error
95b
A
0
255/
280
271
264
270/
270
272
8.8
0.4
0.3
.026
.037
.011
80.9
80.9
80.9
500
190
280
2900
360
550
280
300
6000
400
27.6
44.8
55.2
7.8
B
0.75
250/
280
270
263
275/
280
280
8.8
0.4
0.3
.023
.033
.015
80.9
80.9
80.9
615
320
575
275
50.0
17.0
95c
A
0
245/
280
269
264
270/
290
276
8.8
0.4
0.3
.060
.079
.015
80.7
80.7
80.7
910
310
420
6500
570
950
400
475
8000
640
34.9
51.9
61.8
-1.1
B
1.75
260/
285
276
267
280/
280
281
8.8
0.4
0.6
~
™
5750
6000
-
-
C
3.25
260/
285
275
277
280/
285
283
8.8
0.4
1.2
~
-
1700'
4250'
-
-
                *Sharpdrop - then slow decrease to these levels.
                                 IV-16

-------
                                                                                       Table IV-1.  (Continued)
                                               Run No.
<
 i
Relative Time

TNA

T2 - Avg.

T4 - Avg.

THD

THD - AvS.
Qplue Gas

Q Acid
Q Air (St)

[CHNSOS]   '


[CH2S04I
                                                       hr.

                                                       op


                                                       °F
                    °F

                  SCFM

                   GPM

                  SCFM

                   wt^c


                   wt%
                                                         m
[CN021  Flue Cas    PP

            2
            3
            4

        Flue Gas    ppm
            1
            2
            3
            4
NO  Scrubbing Efficiency
   x      10 0 ft      %
          19 Oft.
          26.5ft.

NOX Matl Bal. Error   %
90a
A
0
260'
280
271
273
270
290
281
6.0
.12
3.1
.026
037
.011
80.4
80.4
80.4
270
130
150
0
190
250
125
150
260
175
29.8
42.4
51.0
8.8

B
1.25
260,'
290
275
Til
270,'
300
281
6.0
.12
3.1
-
-
-
_
_
-
250
100
-
-
-
275
150
-
_
-
.
.
52.5
-
90b
A
0
2607
290
275
277
2707
300
281
6.0
.12
3.1
034
105
.015
80.7
80.7
80.7
490
250
280
10
350
550
225
240
640
260
41 3
50 0
54.3
-14.4

B
1.25
2607
285
277
273
270'
310
287
6.0
.12
3.1
-
-
-
-
-
-
470
220
-
-
-
525
175
-
-
-
_
-
60.5
-
90c
A
0
2707
290
278
283
2707
310
288
6.0
.12
3.1
023
265
.011
81.3
81 3
81.3
1050
450
500
50
600
1100
275
350
1775
500
48 8
60 5
66^3
-30.7

B
1.50
255 /
300
283
275
2707
310
289
6.0
.12
3.1
_
_
-
_
_
-
1100
450
_
_
-
1100
290

_
-
.
_
66.4
-
90d

-
255 /
300
283
275
275
210
289
6.0
.12
3.1
037
634
.019
81.3
81.3
81.3
2000
900
940
130
1100
2050
375
475
2600
700
55.5
65.1
68.5
-53.5
91a
A
0
2357
275
261
257
2807
310
297
11.2
. l
3.1
Oil
022
.007
81.7
81.7
81.7
200
140
145
400
160
225
175
200
60
225
9.4
18.8
25.8
13.4

B
1.0


-
-


-
-
-
-
-
-
-
-
-
-
200
160
-
-
-
225
175
-
-
~
-
-
21.2
-
                                                                                                                                             91b
                                                                 245 /
                                                                 285
                                                                 262
                                                                 270
                                                                 290'
                                                                 315
                                                                 298
                                                                 11.2
                                                                   .1

                                                                  3.1
                                                                  019
                                                                  030
                                                                 .011
                                                                 82 3
                                                                 82 3
                                                                 82.3
                                                                  480
                                                                  240
                                                                  260
                                                                   80
                                                                  300
                                                                  550
                                                                  350
                                                                  460
                                                                 1100
                                                                  450
                                                                                                                                                    0.75
                                                                                                                 510
                                                                                                                 250
                                                                                                                                                     500
                                                                                                                                                     300
                                                                                                                                              27 2
                                                                                                                                              35.9
                                                                                                                                              42.7  45.5
                                                                                                                                              34.7
                                                    Kev to Effluent Streams:
1 - NOX scrubber 4 (7.5ft.);  2 - NOy scrubber 2 (19 ft.)
3 - stripper; 4 - NO  scrubber 2 (halfway up the 19 ft. scrubber).

-------
                                                                                                Table 1V-1. (Continued)
i-*
oo

Run No.
Relative Time
TNA
T2 - Avg.
T4 - Avg.
THD
THD - Ave-
QFlue Gas
QAcid
Q.Mr (St)
[CHNS051 1
3
[CH2S04] 1
3
[CNO21 Flue Gas
2
3
4
[CNQ] Flue Gas
2
3
4


hr.
°F
°F
°F
°F
op
SCFM
GPM
SCFM
wt%
11
wt%
"
ppm
"
"
"
ppm
"
"
"
NO Scrubbing Efficiency
x 10.0ft. %
19.0ft.
26.5ft.
ir
"
91c
A
0
250/
295
262
278
295/
310
303
11.2
.1
3.1
034
.205
.015
82.7
82.7
82.7
1100
400
490
170
660
1050
450
525
2400
650
39.1
52.8
60.5

B
1.50
-
-
-
-
-
-
-
-
:
-
-
-
1150
475
-
-
-
1075
480
-
-
-
_
-
57.1
                                             NOX Mart. Bal. Error
             27.2
91d
A B
0
250/
305
263
278
290/
305
300
11.2
.1
3.1
.046
.589
.023
82.9
82.9
82.9
2000 2000
280 300
420
660
710
2100 2050
650 550
750
4100
1000
58.3
71.5
77.3 79.0
25.9
96a
A
0
270/
280
277
275
280/
295
288
1.5
.12
.3
.007
.018
.007
80.1
80.3
80.3
240
0
50
0
120
290
150
110
1000
140
50.9
69.8
71.7


B
1.0
265/
290
275
276
380/
310
291
1.5
.12
.3
-
;
260
10
300
125
75.9

96b
A
0
240/
285
275
267
280/
320
302
1.5
.13
.3
.006
048
.008
81.0
80.2
80.4
520
35
20*
565
380*
550
175
225*
2375
225*
43.5
77.1
80.4

B
1.75
240/
290
274
269
240/
310
302
1.5
.13
.3
":
;
500
0
550
300*
73.2
96c
A B
0 1.0
265/
290
272
278
295/
305
302
1.5
.13
.3
Oil
.075
.007
80.2
80.2
80.6
900 1000
10 10*
90
490
210
1000 1000
200 175*
225
3250
350
70.5
83.7
88.9 90.8
                                                             Key to Effluent Streams:    1 - NOX scrubber 4  (7.5 ft.); 2 - N
-------
                                                                                            Table IV-1. (Continued)
 i
H*
CO
Run No.
Relative Time
TNA
T2 - Avg.
T4 - Avg.
THD
THD - Avg.
Qplue Gas
QAcid
QAir (St)
[CHNS051 1
3 2
3
£CH2S04] 1
3
[CN021 Flue Gas
2
3
4
[CN01 Flue Gas
2
3
4

hr.
°F
°F
°F
°F
"F
SCFM
GPM
SCFM
wt%
wt%
pprn
ppm
NO Scrubbing Efficiency
x 10.0ft. %
19 0 ft.
26 5 ft.
97 a
A
0
240/
280
258
259
270/
280
274
4.9
.25
.9
.019
023
.011
80 4
80.4
80.4
280
175
195
50
220
225
100
100
950
125
31 7
41 6
45 5

B
1.25
250,'
280
261
269
2707
285
279
4.9
.25
.9
-
-
270
170
225
100
45.5
97b
A
0
2507
290
263
270
275/
280
279
4.9
.25
.9
006
047
.006
80.3
80 2
80.3
500
155
225
160
295
500
220
250
1950
350
35.5
52 5
62 5
B
1.25
250/
280
265
263
2707
285
279
4.9
.25
.9
-
-
480
170
550
180
66.0
                                                                                                    97 c
                                                                                                    250'
                                                                                                    285
                                                                                                    268
                                                                                                    268
                                                                                                    2807
                                                                                                    290
                                                                                                    285
                                                                                                     4.9
                                                                                                     .25
                       005
                       094
                      .007
                      80 2
                      79.9
                      80.0
                      1025
                       360
                       500
                       560
                       590
                      1090
                       220
                       285
                      4600
                       500
                             1.0
                             250 /
                             285
                             268
                             272
                             2807
                             290
                             287
                              4.9
                              .25
                               .9
                                                                                                           1000
                                                                                                            360
                                                                                                           1125
                                                                                                            235
                                                                                                    48 5
                                                                                                    62 9
                                                                                                    72 6   72.0
98a
A
0
250/
280
264
267
280/
290
288
8.6
.25
.9
007
031
.009
80 4
80 0
80.0
265
160
200
30
230
265
170
175
1650
225
14 2
29.2
32.7

B
1.0
245'
280
261
263
280 /
290
287
8.6
.25
.9
_
_
-
_
-
-
270
155
_
-
-
275
200
-
_
-
.
-
34.9
98b
A
0
2407
275
260
271
2807
290
285
8.6
.25
.9
007
046
!006
79.8
79.5
79.8
475
240
305
165
355
525
285
300
1410
375
27.0
39 5
47.5

B
1.25
2407
275
260
271
2807
290
285
8.6
.25
.9
-
-
-
-
-
-
480
245
-
-
-
550
285
-
-
-
_
-
48.5
                                                    Kev to Effluent Streams:
1 - NOX scrubber 4  (7.5ft.); 2 - NOX scrubber 2 (19ft.)
3 - stripper  4 - NOX scrubber 2  (halfway up the 19 ft. scrubber).

-------
                                                                                        Table IV-1.  (Continued)
to
o
         Run No.

Relative Time        hr.

TNA                -F

T2 - Avg.           op

T4 - Avg.           »F

THD                °F

THD • AVK-          °F
QFlue Gas         SCFM

QAcid             GPM

QAlr (St)          SCFM
            1       wt%
            2
            3

[CH2S041    1

            3
[CN02]  Flue^Cas

            2
            3
            4

[Cj^fj]  Flue Gas
            1
            2
            3
            4

NO  Scrubbing Efficii
  x     10.0ft.
         19.0ft.
         26.5ft.
                                                      ppm
99a
A
0
-
280
180
230
45
270
275
125
125
1300
170
20.7
36.0
45.0

B
0.50
~
385
215
250
125
46.5

C
1.50
185/
210
193
197
275/
380
278
4.9
.25
.9
.009
.020
.008
72.9
72.5
72.5
255
110
130
65
175
300
175
180
1125
250
23.4
44.1
48.6
99b
A
0
190/
210
199
198
270/
280
277
4.9
.25
.9
.009
.043
.007
73.0
72.6
73.0
530
200
260
135
335
555
245
255
1550
350
36.9
52.5
59.0

B
0.75
~
520
205
560
260
56.9
99c
190/
210
200
201
275/
280
279
4.9
.25
.9
.017
.100
.009
73 0
72.7
72.9
1050*
360
460
515
575
1060*
225
275
4290
475
50.2
65.2
72.3
99d
A
0
190/
215
199
201
275/
280
278
4.9
.25
.9
021
.197
.011
73.1
72.8
73.0
2050
670
830
1550
955
2025
300
400
•-5800
750
58.2
69.8
76.2

B
1.00
-
2050
670
2100
300
76.6
lOOa
ISO/
210
199
185
250/
260
255
4.9
.62
.9
.006
.027
.006
74.7
74.0
74.2
270
10
15
280
270
125
135
2325
72.2
75.0
lOOb
185/
210
195
199
200/
230
223
4.9
.62
.9
.006
.056
.004
74 4
74.0
74.2
535'
40
110
1000
555'
300
300
3225
67.4
68.8
                                                   Key to Effluent Streams:
                                        1 - NO, scrubber 4 (7.5ft.); 2 - NO,, scrubber 2 (19ft.)
                                        3 - stripper: 4 - NOX scrubber 2  (halfway up the 19 ft. scrubber).
                                                   Erratic response - probably UV cell contamination.

-------
                                                                                            Table IV-1.  (Continued)
 i
to

Run No.
Relative Time
TNA
T2 - Avg.
T4 - Avg.
THD
THD - Avs-
QFlue Gas
QAcid
QAir (St)
[CHNS05] 1
3
[CH2S04] 1
3
[CNO?] Flue Gas
L 1
2
3
4
[CNOI Flue Gas
2
3
4


hr.
op
op
op
°F
°F
SCFM
GPM
SCFM
wt%
"
wt%
"
ppm
"
"
11
ppm
"
"
**
lOOc
A B
0
185/
210
192
192
220/
230
226
4.9
.62
.9
010
.093
.006
74.3
73.6
74.3
1100 1050
195
295 275
210
-
1025 1060
160
175 225
4350
-

C

-
-
-
-
-
-
-
-
-
-
:
-
1100
-
-
-
975
-
-
-
NO Scrubbing Efficiency
x 100ft.
19.0ft.
26 5ft
CP
/o
»r
"
-
78 0 76 3
83.3
-
-
-
                                                                                            IQlb
                                                                                              A

                                                                                              0
             4.9

             .25

              .9
            .015
             022
            .011

            79.1
            79.1
            79.1

             120
              30
              30
              30
              60
             650    650
             500    460
             475
             900
             475
                                                                                                     65
                                                                                                     20
                                                                                            30 5
                                                                                            34.4
                                                                                            31.2
                   32.9
                                                                                                             lOlc
240/
300

283
270

2607
265

262
 4.9

 .25

  .9
 018
.022
.015

79.1
79.1
79.1
 240
  40
  60
 120
  95
1150
 850
 850
1725
 875


30.2
34.5
36 0
                                                                                                                     220
                                                                                                                    1150
                                                                                                                              lOld
                                                                                                                              240/
                                                                                                                              290

                                                                                                                              281

                                                                                                                              257

                                                                                                                              260/
                                                                                                                              270

                                                                                                                              265

                                                                                                                               4.9

                                                                                                                               .25
.018
 022
.011

79.1
79.1
79.1
 320
  40
  60
 370
 110
2200
1675
1700
3025
1800


24 2
30.2
31.9
                                                                                                                                      330
                                                                                                                                     2325
                                                                                                                                               102a
210/
290

276
251

265/
275

269
 4.9

 .25

  .9
.018
 026
.011

79.1
79.1
79.1

 350
 240
 260
  75
 270

  75
  60
  60
 175
  60
350
250
 75
 40
                                                               22.4
                                                               24.7
                                                               29 4   29.4
                                                       Key to Effluent Streams:
1 - NOX scrubber 4  (7.5 ft.);  2 - NO  scrubber 2  (19 ft.)
3 - stripper;  4 - NOX scrubber 2 (halfway up the 19 ft. scrubber).

-------
                                                                            102b
to
to
Run No.
Relative Time
TNA

"^2 " Avg.
T~4 - Avg.
THD

THD - Av8-
QFlue Gas
QAcid
QAir (St)
[CHNSO5] 1
3
[CjbsoJ 1
2
3
[CNO21 Flue Gas
2
3
4
[CNO1 Flue Gas
1
2
3
4

hr.
°F

°F
"F
°F

°F
SCFM
GPM
SCFM
wt%
"
wt*
11
"
ppm
tf
"
"
ppm

11
"
"

0
210/
290
275
247
270/
275
271
4.9
.25
.9
.018
.033
.015
79.1
79.1
79.1
490
330
360
110
380
100
60
75
500
75




_
_


_
_
.
.
-
.

_
-
500
330

_
.
100
60

_
-
NO Scrubbing Efficiency
10.0 ft.
19.0ft
26.5ft.
V
7o
tr
**
22.9
26 3
33.9
_
_
35.0
         Table IV-1.  (Continued)

 102c      102d
 220/
 285

 277
 251
 270/
 270
 270

 4.9
 .25
   .9
 .022
 .041
 .018
79.1
79.1
79.1
1000*
 620
 700
 220
 705
 225*
 100
 110
 725
 130
                                                                                           31 8
                                                                                           33.9
                                                                                           41 2
 230/
 295

 278
 260
 265/
 270

 268

  4.9
  .25
   .9
 .026
 .059
 .018
 79  1
 79.1
 79.1
 2000
 1300
 1350
 490
 1350
 350
 175
 200
 925
 225

33.0
34 0
37.2
                                                            Key to Effluent Streams:
                                                                                      1 - NO, scrubber 4 (7.5 ft.); 2 - NOX scrubber 2  (19 ft  )
                                                                                      3 - stripper; 4 - NOX scrubber 2  (halfway up the 19 ft. s'crutter).
                                                             Erratic response - probably UV cell contamination.

-------
                 APPENDIX V. METAL ION INTERFERENCE IN SCRUBBER
                               AND STRIPPER OPERATION
       A.  HNSOC Determination — Interference by Corrosion Products
          	o	
       During the course of miniplant experimentation it was necessary to analyze the acid
streams for HNSOg content.  The standard procedure, whereby acid samples are titrated to
a pale pink endpoint with aqueous 0.1N KMnO. solution,  was found to indicate inordinately high
concentrations of oxidizable material in the acid streams. Calculations of available material
and our past experience with similar experiments led us to believe that oxidizable materials
other than HNSOg must be present in the acid.  The source of these interfering materials was
believed to be corrosion products of metal alloys exposed to the acid streams.  Visible spectro-
photometric analysis,  laboratory corrosion tests,  and replacement of some of  the parts of the
miniplant equipment suggested that the major source of  corrosion products was probably stain-
less steel. Of the possible stainless steel locations in the acid feed stream,  the strippers of-
fered the highest surface area if the Teflon lining had failed.  Dismantling and inspection of the
interior of the strippers revealed that the Teflon lining had failed and  severe corrosion had
occurred.
        The principle components of SS316 are iron, chromium, nickel, manganese, and molyb-
denum.  If the reaction of any of these species with carbon is rapid or if corrosion is rapid,
then one or more of them could be in a reduced state while present in  the acid.  Titration with
permanganate would then result in an indication of oxidizable material present  which could be
mistaken for HNSOg.  Iron in sulfuric acid could be present as Fe   or Fe  ;  chromium as
Cr   or Cr   (oxidation to chromate is slow and occurs only with very strong oxidants;  nickel
as Ni   , manganese as Mn4 , Mn4 , Mn    (oxidation to permanganate would be unlikely; and
molybdenum as Mo   , Mo,  Mo+ , Mo, and perhaps Mo   .  Contact with the air for a
sufficient period of time would probably be sufficient to  oxidize any of them  somewhat. We
have found that  samples  which give high errors by KMnO, titration (relative to nitrometer re-
sults) when recently removed from the miniplant give much smaller errors  by KMnO4 titration
after a week's storage in a closed container. A small error,  equivalent to perhaps 0.04 wt %
HNSOK, is still observed (relative to the nitrometer results).  Experiments  with synthetically
prepared solutions using chromic and nitrosylsulfuric acid solutions lead us to believe that
this error is due to the slow oxidation of chromic ion to chromate by  KMnO,.  Nitrosylsulfuric
acid does not oxidize chromic ion to chromate.

                                           V-l

-------
       Interference by corrosion products can be avoided by using the nitrometer to analyze
for HNSO- instead of the KMn04 titration. Other titrimetric methods can probably be devel-
oped; however, the time required for such an undertaking would be excessive, considering the
availability of the nitrometer procedure.
       B. Effect of the Presence of Corrosion Products on HNSO,.
          Solubility and Scrubber Performance	
       The presence of corrosion products could lessen scrubber performance by decreasing
the solubility of HNSO- at any given partial pressures of NO and NOg. This effect would be
observed on the scrubber column as a decrease in overall scrubbing efficiency.  However, all
sections of a large scrubber would have the same efficiency per unit length.  Thus, if the bot-
tom section of the scrubber was scrubbing NO  from the gas phase, the top section would fur-
                                          X
ther reduce the gas phase NO  concentration as long as the acid entering the column was free
of dissolved HNSO..
                 5
       One may treat the problem of decreased HNSO.. solubility in the following semiquantita-
tive manner. The dissolution reaction is:
        NO + NO2  4 2H2SO4 = 2NO4 4 2HSO4~ 4 HgO  .

One may write an equilibrium constant expression for this reaction:

             [N04]2[HS04"]2[H20]
If one sets PNQ = pN~  = p and if one disregards small changes in solvent concentrations (i.e.,
H-O and HgSOJ,  this expression reduces to:
        K =
and it may be rearranged to solve for HNSO- solubility:

        HNSO, = [NO4] =   P^K     .
             5            [HS04~]

HNSO-, which dissociates in sulfuric acid to form NO and HSO4 , decreases in solubility as
the HSO.  concentration increases. If any increase occurs in HS04  concentration, the solu-
bility of HNSO.  decreases proportionately.
       We know that corrosion products are present in the hot scrubber acid at a concentration
close to the saturation value.  Precipitation of metal salts is observed during cooling of the sys-
tem. We can estimate the concentration of dissolved metal salts to be several moles per liter
from a casual observation of the volume of solids which precipitate out when scrubber acid
samples are cooled.  The solids content  is approximately 5 vol %.  The corrosion products are
                                          V-2

-------
undoubtedly present as bisulfates, since there are no other anions present in appreciable con-
centration. Since the metal ions which we would expect to be present are polyvalent, there will
be at least two bisulfate ions present for each metal ion which is present.  We may conserva-
tively estimate that the increase in bisulfate ion due to the presence of corrosion products in
the scrubber is 5 M.
        Now that we have estimated the increase in bisulfate concentration,  we must estimate
the original bisulfate concentration if we are to obtain a proper  notion of the expected decrease
in HNSO-  solubility. lonization Constants of Acids and Bases, by Albert and Serjeant, lists for
the first dissociation of H-SO. a pK  of -3.0.  The Hammet acidity function is -3.0 at a sul-
furic acid concentration of 6 M, according to the same authors.   Using these two values and
                                              i       _1UL
simple mass balance expressions for H2O, FLO ,  HSO.  , and  H-SO,, one may estimate that
at 80 wt % H2SO. (14M HgSOA  the bisulfate concentration is approximately 4M at room tem-
perature.  At the higher temperatures encountered in the scrubber, the extent of dissociation
Is probably greater and the bisulfate concentration might be 5 or 6 M.
        Thus, the concentration of bisulfate is approximately 5 M in the absence of corrosion
products and might be as high as 10 M in the presence of corrosion products.  This doubling of
bisulfate concentration would result in halving of the HNSO- solubility according to the equations
we developed above. This decrease in solubility could halve the efficiency of the scrubber.
Ilius, the scrubbing efficiency,  which is about  70%,  might well be expected to provide higher
recoveries of NO  in the absence of excessive amounts of corrosion products.
        The number of assumptions involved in our treatment of HNSOg solubility (and its de-
pendence  on corrosion products) makes it advisable that  we consider the results of our calcula-
tions to be semiquantitative.  It  would be possible to measure HNSCX solubility in the presence
and absence of corrosion  products.
        C. Effect of the Presence of  Corrosion Products on Stripper Performance
        The performance of the stripper directly affects the extent to which the scrubber may
 -remove NO from the gas phase. If the feed acid to  the scrubber contains residual HNSOg that
 was not removed by the stripper, then there will be  a residual  gas phase N0x level equal to or
 greater than the equilibrium partial pressure of NO   corresponding to the  equilibrium value for
 the feed acid.  The behavior of the scrubber will be such that the lower portions of the scrubber
 will operate fairly well (because of the high gas phase NOx input levels), but the upper  sections
 Of the scrubber will remove very little more NO   (due to the residual liquid phase HNSO&).
        Corrosion products present in the acid loop precipitate out of solution when the system
 is cooled. This problem  is probably very serious in the stripper, where precipitation can
 result in  the blockage of pores in the activated charcoal and a  resultant drastic decrease in
 available surface area. Such blocking could drastically reduce stripper performance.  This is
 a difficult hypothesis to check directly, but the scrubber behavior supports this view.
                                             V-3

-------
                  APPENDIX VI. CORROSION IN MINIPLANT EQUIPMENT
       At the beginning of the testing we employed three Eco gear pumps made of Hastelloy B
bodies with carbon wear plates and bearings.  This construction was recommended for the ap-
plication by the manufacturer,  whose experience indicated that these materials would withstand
the corrosive nature of hot sulfuric acid and,  in fact, claimed that other similar pumps were
sold for this purpose.  Examination of standard corrosion tables indicated that the Hastelloy B
material was marginal for long-term application, but should be satisfactory for a period of
several months.
       One pump was  purchased early in the program, tested under the desired operating con-
ditions, and showed the capability of pumping over one gallon per minute of hot sulfuric acid
(only 0.4 GPM was required for the test series). Upon this successful evaluation, two more
identical pumps were purchased and installed in the  system.
       When the testing was begun, it was noticed that the pump capacity seemed to drop some-
what as the temperature increased.  Extended operation of the system caused all three pumps
to eventually lose their capability to pump the minimum required quantity of acid.  The pumps
failed in order of their installation into the system.  Examination of the interior of the pumps
showed that there was extensive corrosion and erosion of the pump bodies as well as the drive
shaft and the drive gears.  The pump manufacturer was shown the results of only a few days of
operation, and he recommended replacement of the Hastelloy B drive gear with a carbon drive
gear, but this did not prove to be adequate. The corrosion of the pump bodies created a large
clearance between the pumping gears and the bodies, and the resulting back slip of fluid pre-
vented adequate pumping.
        The pump manufacturer cooperated with us to the extent that he supplied us with sam-
ples of his pump parts to evaluate in the desired application, but it is clear that  the highly cor-
jrosive conditions aggravated by the highly turbulent  conditions present in a gear pump plus the
presence of air bubbles causing aeration of the corrosive fluid all combine to rule out the use
of available  materials in our system. As shown in Fig. VI-1, samples of Hastelloy B, Hastelloy
C  Carpenter 20, and  stainless steel 316L all failed quite badly under  the plant's operating con-
ditions.  (Note; An obvious question would be how our Carpenter 20 piston pumps have survived
almost 2 yr of intermittant use without  apparent failure.  The answer appears to be in the na-
                                           VI-1

-------
  ALLOY  20
HASTELLOY  C
                                     cc
                                     0 •
   HASTELLOY  B
   316 STAINLESS
Fig. VI-1. Photographs of corroded pump parts showing comparison with untreated parts;
      the Hastelloy B sample came from one of the Eco pumps in miniplant service.'
                      VI-2

-------
turc of die piston pump, which is essentially a low-speed mechanism with no tight tolerance
requirements.  Both the piston and the pump head cavity could corrode slowly under the non-
turbulent conditions of this pump's operation and  there would be little or no danger  of pump
failure.  The only problem might involve the ball  checks and,  indeed, these did show signs of
excessive corrosion and reduced operating efficiency.)
       This experience with the pumps did provide a qualitative input to the program in terms
of the utility of various materials of construction. Clearly, Hastelloy B and C arc incapable of
standing up to the corrosive nature  of the liquid system.  Carpenter 20 is marginal and may  be
of value  in certain  applications.
       B.  Strippers
       As mentioned in Appendix II, examination of the strippers after 2 to 3 weeks of opera-
tion showed that the Teflon coating had undergone catastrophic failure. When the cover of one
of the  strippers was removed, die appearance of the coating was as shown in Fig. VI-2. The
acid had obviously  penetrated the Teflon at a great many points, apparently through pinholes
in the  coating.  The acid then corroded the stainless steel of the stripper walls and the coating
was peeled back as the corrosion occurred in a circular manner.  The result was that the coat-
ing failure took the form of a great  many small circles being cut out of the Teflon.  Many of
these circles interconnected with each other and  some of the coating came off in lace-like
films. In other areas the coating was completely removed, and there was a thick (up to 1/4 in.)
buildup of precipitated  metal salts on the walls.   It should be noted that the coating used was
recommended by duPont for  this application,  with the actual coating applied by a duPont ap-
proved vendor.
       A light-colored precipitate was obtained  by cooling the acid circulated through the  sys-
tem. X-ray diffraction analysis of  this precipitate disclosed that the material was Fc-^O.).,.
       This experience indicates that Teflon coating is virtually worthless  in this type of appli-
cation.  It is also apparent that Type 316L stainless  steel is unusable for hot nitrosylsulfuric
acid solutions.  It should be pointed out that Teflon lining of equipment has not been ruled out
by this work and remains to be tested.  (Teflon lining has the advantage of being a relatively
thick,  continuous layer applied by extrusion techniques as opposed to the thin spray-and-bake
application of die Teflon coating which is prone to pinholes.)
                                             VI-3

-------
Fig. VI-2. Photograph of the top of a stripper column after 3 weeks service showing
          damaged coating.
                                  VI-4

-------
APPENDIX VII.  MATHEMATICAL ANALYSIS OF SCRUBBER/STRIPPER DATA
             Table VII-1. Tyco Scrubbing Data Summary Sheet



                Table VII-2.  Average Values of NO  Error
                                                X.


                    Table VII.3.  Tyco Scrubbing Data



                     Table  VII-4. OAF Scrubbing Data



              Table VII-5.  Computer Program for Tyco Data



               Table  VII-6.  Computer Program for GAP Data



              Table VII-7. Rate Constants from the Tyco Data



              Table VII-8.  Rate Constants from the GAP Data
                                 VII-1

-------
             Table VII-1. Tyco Scrubbing Data Summary Sheet
RUN
82AB
82BD
B2CB
83AP
83BP
83CPB
84AB
84BA
84CA
B5AB
05DT
85CPA
86A ,
86BPD
86CB
87A
878
87C
92 A A
92B. i
92CA
93AA
93BA
93CA
94 AB
94BA
94CA
95AB
95BA
95CA
96A.,
96 B A
96CA
97AA
978A
97CA
4.9
4.9
4.9
8.8
a. a
8.0
6.0
6.0
6.0
1.4
1.4
1.4
2.9
2.9
2.9
4.9
4.9
4.9
4.9
4.9
4.9
2.6
2.6
2.6
6.0
6.0
6.0
8.8
8.8
8.8
1.5
1.5
1.5
4.9
4.9
4.9

INLET
235
500
925
240
475
10'i.i
275
50:
1050
250
50.')
10.J.
2'5
70.!
1050
21:5
500
10 :>
250
470
llOd
2?5
475
1070
240
500
1050
180
500
950
290
500
100.)
225
500
1090
NO
27 FT
10i)
150
250
120
225
375
125
150
250
150
ion
75
90
140
125
110
150
180
125
150
120
85
150
200
225
250
350
135
280
400
150
175
200
100
220
220
N02
INLET
265
470
1050
240
520
925
260
530
1050
210
540
110.)
230
525
100 )
260
520
1000
270
560
1 25
280
50;)
1200
230
540
1 00
300
500
910
240
520
900
280
50
1025

27 FT
150
150
490
65
320
45
80
190
415
5
70
90
140
50
15
120
205
365
125
40
145
0
0
10
30
90
300
135
190
310
0
35
10
175
15b
360
                                                 DNO   ON02
                                                 135
                                                 40  i
                                                 675
                                                 120
                                                 250
                                                 625
                                                 150
                                                 350
                                                 80;,

                                                 400
                                                 925
                                                 135
                                                 560
                                                 925
                                                 H5
                                                 40;)
                                                 820
                                                 125
                                                 320
                                                 980
                                                 140
                                                 325
                                                 870
                                                 15
                                                 300
                                                 70!)
                                                 45
                                                 270
                                                 500
                                                 140
                                                 375
                                                 80
                                                 125
                                                 280
                                                 870
 1!.5
 320
 560
 175
 20;;
 470
 180
 340
 635
 205
 470
1010
  90
 470
 985
 140
 315
 635
 145
 520
 980
 280
 50'i
1 90
 200
 450
 80;)
 165
 310
 600
 240
 485
 890
 105
 345
 6  5
NOX ER

   20
   80
  li.5
  -5.,

  15
  -30
   10
  165
 -105
  -70
  -85
   M r\
   9fl
  -60
  -25
 -140

 -320
 -185
 -150
 -lO.i
 -120
  -40
  -50

 -110
  -90
   20
  -65
  205
                                VII-2

-------
Table VII-2. Average Values of NO  Error (at 95% Confidence Level)
                               A
         For 80's              NO  error  =  32 ± 180
                                As


         For 90's              NO  error  =  - 91 ± 220
                                X


         For80's490's        NO  error  =  - 30 ± 230
                                A


         For 250 ppm          NO  error  =  - 58 ± 140
                                X


         For 500 ppm          NO  error  =  - 41 ± 200
                                X


         For 1000 ppm         NO  error  =  10 ± 300
                                X
                              VII-3

-------
Table VH-3. Tyco Scrubbing Data
NO
RUN
82AB
82BO
82CB
83AP
83BP
83CPU
04AU
84L5A
U4CA
(35 AO
8bD :
flbCPA
86 A •
86BPU
86CO
87A
878
87C
92AA
92Bi;
92CA
93 A,;
93BA
93CA
94 AB
94BA
94CA
95AB
9b8A
95CA
96AA
968A
96CA
97AA
9713A
97CA
Q
4.9
4.9
4.9
a.a
a.a
a.a
6.0
6.0
6.0
1 .4
1.4
1.4
2.9
2.9
2.9
4.9
4.9
4.9
4.9
4.9
4.9
2.6
2.6
2.6
6.0
6.0
6.0
a.a
a.a
a.a
1.5
1.5
1.5
4.9
4.9
4.9
INLET
235
550
92b
240
475
10:. 0
275
bOu
lUbil
2bU
50.'
lOUU
22b
70n
lObO
22b
bbO
10U ^
2bO
47u
IICK)
22b
47b
1070
240
5bO
1050
180
bbu
950
290
5:50
1000
2^b
50U
1090
9.bFT
200
275
b')0
150
350
b7b
175
27b
b- 0
175
160
IbU
IbU
230
17b
140
30!)
390
165
2,Jb
320
130
20:)
30U
2^5
3bO
5bO
150
40 1
640
140
225
350
125
350
50;)
19 FT
10:)
175
40D
125
275
460
125
17b
32b
17b
12b
90
ion
Ibi)
12b
12b
Ibb
2bO
140
160
175
100
13b
20
22b
280
375
140
30 0
475
1:0
225
225
100
250
285
27 FT
10!)
IbO
2bU
120
225
375
125
150
2bO
150
10.'
7b
90
141)
12b
i ; u
IbO
lao
125
ibn
120
ab
IbO
200
22b
2bO
350
13b
280
40;)
150
175
200
100
220
220
INLET
265
470
1050
240
52 (J
92b
26U
b3!)
10b()
210
bin
110; >
23u
525
10 ' • J
T(j(J
b?:)
1 0 : i . i
27!)
bbt)
1125
28!)
bnn
12!).'
23U
b 4 D
HUiJ
300
50 (J
910
240
52U
90u
280
50 J
1025
N02
9.5FT
2UO
240
680
14!)
435
62b
120
2b()
b3(J
70
IbiJ
IfllJ
13;)
1 n

, .^
3;>;i
L>» U
1 f > 1 1
13.)
42!)
2b
0
190
12!)
230
630
220
3ta!)
b70
120
380
210
220
29 b
b90
19 FT
180
230

95
37b
bib
12!)
271)
bib
2b
1 10
130
Ibi)
9b
bii
' b'i
<:I,D
4- -b
Ibi)

2o;j
10

4il
7:j
IbO
470
18b

420
bO
20
90
19b
225
50,
27 KT
1 bO
IbO
4 ') II
ijb
32!)
4V)
fifl
1 90
4 ; ^
!-,
7i)
'•»!)
1 •' !j

* u}

1 a. i J
20L,
3o b
12b
;» ' i
145
(J
0
1 i'
.*) : 1
1 )i '•
3i.
1 s^-
i - • . j
1 -if'
3 1 n
j
3b
1 1 1
1 7b
Ibb
3di)
            VII-4

-------
                     Table VII-4. GAP Scrubbing Data
                                                   10
RUN
     NO
INLET  OUTLET
    N02
INLET  OUTLET
                                               UNO
NOX ER>
14-1
14-2
14-3
14-4
14-5
14-6
15-1
15-2
15-3
15-4
15-5
15-6
17-1
17-2
17-3
17-4
17-5
17-6
18-1
18-2
18-3
18-4
18-5
18-6
273
370
475
575
695
013
256
343
451
555
664
769
253
366
462
598
681
758
253
345
450
552
651
769
215
268
330
368
434
553
204
250
331
393
463
521
187
26i,
331
405
4
-------
                     Table VII-5. Computer Program for Tyco Data


/RATES/
11.02 JSJM/ CALCULATION OF RATE CONSTANTS FOR C-141 SCRUBBING EXPERIMENTS
ON NO AND N02
11.03 A=PI/36.0. CJ=0
11.04 H1=26.5.H2=19.0.H4=9.5
11.05 DEMAND INPfOUP
11.06 OPEN INP FOR INPUT AS FILE 3
11.07 OPEN OUP FOR OUTPUT AS FILE 4
11.08 TYPE "
  RUN   GAS  HEIGHT   AHG-1      PO/PX     LNIPO/PX)  1/PO-l/PX     Kl         «2

fl
11.21 READ FROM 3: X .Q.N20.N21 .N22.N24 »N10»N11»N12.N14
11.211 DO PART 13
11.22 00 PART 12
11.225 CJ=CJ-H
11.226 DO PART 14 IF FP CJ/5=0 IPAGING ROUTINE
11.23 TO STEP 11.21
12.21 R11=(N10/N11)»R12=(N10/N12}.R14=(N10/N14)
12.22 L11=LOG(R11) .L12=LOG (R12 ) .L14=LOG(R14)
12.23 AG1=(A*H1)/Q.AG2=(A*H2)/Q.AG4=(A*H4)/Q
12.2t F11=L11/AG1»F12=L12/AG2.F14=L14/AG4
12.311 R21=(N20/N21)»R22=(N20/N22).R24=(N20/N24)
12.312 L21=LOG (R21 > » L22=LOG ( R22) »L24=LOG (R24 )
12.313 F21=L21/AG1»F22=L22/AG2.F24=L24/AG4
12.321 D11=(1/N10)-(1/N11).D12=<1/N10)-(1/N12)»D14=<1/N10>-(1/N14)
12.322 S11=-D11/AG1.S12=-D12/AG2»S14=-014/AG4
12 .331 D21= (1/N20) -(1/N21) .022= (1/N20 ) -(1/N22 ) .024= (1/N20 ) - (1/N24)
12.332 S21=-D21/AG1»S22=-022/AG2.S24=-D24/AG4
12.101 TYPE IN FORM  69: X.HI,AG1»R11.Lll.Dll.Fll,S11
12.4011 WRITE ON 4 IN FORM 69! X»H1»AG1»R11^L11^D11»F11rSll
12.402 TYPE IN FORM  69: X»H2»AG2,R12»L12,D12tF12»S12
12.4021 WRITE ON 4 IN FORM 69! X»H2»AG2»R12»L12»D12»F12»S12
12.403 TYPE IN FORM  69: X »H4 »AG1 »R11»L11 »D14 »F14. »S11
12.4031 WRITE ON 4 IN FORM 69: X .HI »AG4 .Rl^.Ll^Ol^Flt, S14
12.10H TYPE " "
12.411 TYPE IN FORM  70: X»H1»AG1»R21»L21»D21»F21»S21
12.4111 WRITE ON «* IN FORM 70: X »H1» AG1 >R21 >L21.021 .F21» S21
12.412 TYPE IN FORM 70: XrH2rAG2.R22.L22.D22.F22.S22
12.4121 WRITE ON 4 IN FORM 70: X.H2.AG2.R22.L22.D22.F22.S22
12.413 TYPE IN FORM  70: X »H4 . AG4 .R24 >L24^ .024 »F24> .524
12.4131 WRITE ON 4 IN FORM 70: X.H4.AG4.R24.L24.D24.F24.S24
12.414 TYPE "

tf
13.11 tSHORT PART TO IGNORE ANY INCOMPLETE DATA  SET
13.12 CM=0.000001
13.21 TO STEP 11.21  IF Q=CM
13.22 TO STEP 11.21  IF N20=CM
13.23 TO STEP 11.21  IF N21=CM
13.24 TO STEP 11.21  IF N22=CM
13.25 TO STEP 11.21  IF N24=CM
13.26 TO STEP 11.21  IF N10=CM
13.27 TO STEP 11.21  IF N11=CM
13.28 TO STEP 11.21  IF N12=CM
13.29 TO STEP 11.21  IF N14=CM
14.11 TYPE "SL

n
14.12 DO STEP 11.08
                                      VII-6

-------
                      Table VII-6. Computer Program for OAP Data10


/GRATES/
j.1. 02  ISJM/  CALCULATION OF  RATE CONSTANTS  FOR C-141 SCRUBBING EXPERIMENTS
ON NO  AND  N02
11.05  A=(PI/<*>*(2. 25/12)*(2. 25/12) ,  CJ=0
1 1.04  Hl=1.5
1 i .05  DEMAND OUP
11.06  OPEN /L6D2/ FOR INPUT AS FILE  3
11.07  OPEN OUP FOR  OUTPUT AS FILE 4
11.08  TYPE "
   RUN    GAS  HEIGHT   AHG-1      PO/PX     LNIPO/PX)   1/PO-l/PX     Kl         K2
11.21  READ FROM 3!  X >N20 »N21 rNIO »N11
1  .22  DO PART 12
1 1.225 CJ=CJ-H
1  .226 DO PART 1«V IF FP CJ/30=0 » PAGING ROUTINE
11.23  TO STEP 11.21
12.21  R11=(N10/N11)
12.22  L11=LOG(R11)
12.23  AG1=(A*H1)/Q
12. 2M-  F11=L11/AG1
12.311 R21=(N20/N21)
12.312 L21=LOG(R21)
12.313 F21=L21/AG1
,2.321 D11=(1/N10)-(1/NU>
12.32.: S11=-D11/AG1
12.331 D21=(1/N20)-(1/N21)
12.332 S21=-D21/AG1
12.401 TYPE IN FORM 69: X rHl t AG1»R11 .LI 1»011 »F 11 »S11
12. H011 WRITE ON 4  IN FORM 69: X .HI ,AG1 .Rll »L1 1 »D11 ,F1 1 »S1 1
12.411 TYPE IN FORM 70: X >H1 »AG1 .R21 »L21 »D21 >F21 »S21
12.41H WRITE ON 4  IN FORM 70: X »H1 » AG1 »R21 »L21 »D21 »F21 »S21
1<+.11  TYPE "8L


1<+.12 00 STEP 11.08
lb.ll »SJM-DRC» CONVERSION OF  LOU GARCIA GRAPHICAL  DATA ,  FEB  1972
.,5.12 Q=20/60» NCT=2^» CNT=0
15.21 OPEN /LGD/ FOR INPUT AS  FILE  b
!5.22 OPEN /LGD2/  FOR OUTPUT AS FILE 6
15.31 READ FROM 5:  X»X1C» YlCr X2C •  Y2C
15.32 CNT=CNT + 1
l5.4l N10=100*10-(0.0752*X1C )
ib.42 R1A=(2.5E-5)*10-(0.07265*Y1C)
1«5.£*3 Nll = N10-( (R1A*(9.91E6)/60)/Q)
t>3.46 N20=100*10- (0.07525*X2C )
•.5.17 R2A=(2.5E-5)*10»(0.07265*Y2C)
15.18 N21=N20-( (R2A*(9.91E6)/60)/Q)
!5.bl WRITE ON 6 IN FORM  6: X> N20r  N21 • N10»  Nil
lb.6l TO STEP 15.81 IF  CNT=NCT
15.62 TO STEP 15.31
!5.81 CLOSE 5
15.82 CLOSE 6
15.83 DO PART 11

      61
                                          VII-7

-------
                      Table VII-7.  Rate Constants from the Tyco Data
RUN
GAS  HEIGHT    AHG-1
                                 PO/PX
LN4E-oi
421E-02
628E-01
8H4E-01
421E-02
2.628E-01
1.
9.
2.
1.
9.
8' 4E-01
421E-02
628E-01
884E-01
421E-02
2.
2.
1.
1.
1.
1.
3.
3.
2.
3.
2.
1.
3.
2.
1.
2.
1.
1.
2.
1.
1.
3.
2.
1.
2.
1.
1.
1.
1.
1.
350E+00
350E+00
175E+00
767E+00
472E+00
325E+00
6 -7E+00
143E+00
OOOE+00
133E+00
043E+00
958E+00
700E+00
312E+00
682E-t-00
143E-I-00
750E-I-O.J
544E+00
OOOE+00
920E-»-00
600E+00
692E+OU
526E+00
714E+00
111E+00
727E+00
357E+00
625E+0!.
387E+00
195E+00
8.544E-01
8.544E-01
1.613E-01
5.691E-01
3.868E-01
2.814E-01
1.299E+00
1.145E+OU
6.931E-01
1.142E+on
7.147E-01
6.721E-01
1.308E+00
8.383E-01
5.199E-01
7.621E-01
5.596E-01
4.345E-01
6.931E-01
6.523E-01
4.700E-01
1.306E+00
9.268E-01
5.390E-01
7.U72E-01
5.465E-01
3.051E-01
4.855E-01
3.269E-01
1.785E-01
-5.745E-03
-5.7U5E-03
-7.447E-04
-2.893E-03
-1.782E-03
-1.226E-03
-4.848E-03
-3.896E-03
-1.818E-03
-U.539E-03
-2.220E-03
-2.039E-03
-2.919E-03
-1.419E-03
-7.371E-04
-1.08nE-03
-7.143E-01
-5.182E-04
-4.167E-03
-3.833E-03
-2.50 E-03
-1.122E-02
-6.360E-03
-2.976E-03
-2.339E-03
-1.531E-03
-7.519E-04
-1.202E-03
-7.136E-04
-3.758E-04
1
2
9
1
1
1
2
3
4
2
2
3
2
2
3
1
1
2
2
3
4
n
M
5
2
2
3
1
1
1
.eioE-i-of)
.52bE+0
.532E-01
.206E+0'
. 143E+00
.6f,3E*0
.753E+0
.384E-I-0.)
.097E+0:i
.420E1-0
. 112E+0
.972EtO -
.772E+0 )
.477E+0 !
.073E+0!i
.615E*0
.65aEfQ
.568EfO
.638E+0,-
.462E-t-0'o
.989E<-0 i
.971E + 0::
.919E+0 .
.721E+0
,843Eton
.901E+00
.242E+00
,848E-t-Oii
.735E>OU
.895E+0(J
1.217E-02
1.698E-02
4.401E-03
6.130E-D3
5.26i. E-03
7.249E-03
1.027E-02
1.1CJ1E-!J2
1.075E-02
9.GKJE-03
0.501E-D3
1.20'iE-fi:.'
6.105E-03
4.193E-11 1
4.357£-,-)3
2.306E-n^
2.1. £-1)3
3.063E-..K.
1.506E-02
2.035E-02
2.G54E-0?
4.2f>9E-02
3..',75E-02
3.159E-02
8.901E-03
8.126E-03
7.981E-03
4.574E-03
3.947E-03
3.989E-03
                                        VII-8

-------
RUN
     Table VII-7.  (Com.)
      GAS   HEIGHT    AHG-1
PO/PX
LN(POXPX)  1/PO-l/PX
                                    Kl
03CPB
03CPB
83CPB
03CPB
O3CPO
83CPB
-4AO
O4AO
O^AO
flUAO
fli+AU
flUAB
8HOA
04BA
fl4BA
Q4BA
8<+BA
Q4DA
fjfC A
rj4C A
84C A
04CA
84CA
84CA
fl'.jAO

of) AB
05AH
flrjAB

"NO"
"NO"
"NO"
"NC2"
"N02"
"N02"
"NO"
"NO"
"NO"
"N02"
"N02"
"N02"
"NO"
"NO"
"NO"
"N02"
"N02"
"N02"
"NO"
"NO"
"NO"
"N02"
"N02"
"N02"
"NO"
"NO"
"NO"
"N02"
"N02"
"N02"
26.50
19.00
9.50
26.50
19.0
9.50
26.50
19.0.)
9.50
26.50
19.0 >
9.50
26.50
19.00
9.50
26.50
19. On
9.50
26.50
19.0D
9.50
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.0.)
9.50
2
1
9
2
1
9
3
2
1
3
2
1
3
2
1
3
2
1
3
2
1
3
2
1
1
1
5
1
1
5
.628E-01
.0 V4E-01
.421E-02
.62RE-01
.R.-4E-01
.421E-02
.854E-01
.763E-01
.3R2E-01
.B54E-01
.703E-01
.302E-01
.854E-01
.763E-01
.3R2E-01
.854E-01
.763E-01
.3O2E-01
.8-54E-01
.763E-01
.382E-01
.854E-01
.763E-01
.3R2E-01
.652E+00
.184E+0
.92?E-01
.652E+0'
. 1R4E+0<|
.92 E-01
2
2
1
2
1
1
2
2
1
3
2
2
3
2
1
2
1
2
^
3
1
2
2
1
1
1
1
4
8
3
.6-,7E*0
.174E + O.I
.739E-I-0;)
.03^E + 0,i
.796E*00
.480E>no
.200E+0
,20f)E-»-Or)
.571E+OM
.250E+0;)
.167E+00
.167E+OG
.3 E+0
.857E+01
.810E+00
.7Q9E-t-Oi'i
.963E+OH
.030E-fOr,
.200E+00
.231E40.)
.909E400
.530E+00
.039E+0
.981E+00
.6f.7E+0,;
.429E+00
.429E+OU
.200E+01
.40HE+00
.OOi'E + 00
9
7
5
7
5
3
7
7
4
1
7
7
1
1
5
1
6
7
1
1
6
9
7
6
5
3
3
3
2
1
.800E-01
.765E-01
.b34E-01
.095E-01
.856E-01
.920E-01
.Rn5E-01
.8''5E-01
.520E-f)l
. 179E + OI
,732E-ni
.732E-01
.204E+O.S
.OSOE + O'i
.978E-01
.026E+0
.745E-01
,12,'E-Ol
.435E + 0.'
.173E + 0 -'
.46.. E-01
.283E-01
.124E-01
.837E-01
.108E-01
.567E-01
.567E-01
.738E+O.I
.128E+0'.!
. Q9C>E+QC,
-1.
-1 .
-7.
— 1 i
-0.
"* ^J <

-4 ,
-2,
-a.
— li
^h
-4
-3
-1
-3
™ 1
~ i
-3
-2
-0
-1
-9
-9
-2
-1
-1
-1
-3
-9
,0. .7E-D3
, 174E-H3
, 391E-04
. I 7E-03
.607E-04
, in')E-04
. v>4F-m
. 304E-D3
.078E-03
.654E-03
."a7F.-03
.4R7F-03
.6. .7E-03
.714E-03
.63--.E-03
.376E-03
.017E-03
,95'.C-03
.048E-03
.125E-03
.658E-04
.457E-03
.894E-04
.34 C-04
.6»7E-03
.714E-03
.714E-03
.952E-01
.524E-02
.524E-03
j 75°Ef
4.12 LEfO .'-..^.Vltr-i!^
G.H74F.-.-0 7.n4uf-;..',
2.70 E4-.I . 4.?.-:'-)F -,,.',
3.1 ORE +i") ! 4.'.")r',(>.C;-(l?)
4.16'F+n 5.:.!inr-fi -,
2.046E+0 1. ' .*,^t.-;u'
2,R53F+n- I .',7 if- )-
.^.271E + 0 : i .'ji'U,-- ,•
3.nr,nH.tn ?. <-v - ,.
2.79t-5Efii ' ..,.'->-- i/
r>/-9(iF+.) .•,.,'•.'•.!.-!./
3.124E + 0 ^ .:-V. R- •
3 .7Q:'F rf) 1 . "j4 f-.. '
4.327F + H ' 1 . .:.WL-:..
2.6 2E+0 . f'..7,.:ir- .-,
2.4- IF. + O • 6.S7 >'.-•• •
5.154E+0 l.-».''.l>.i''
3.723E + 0 7.9.iVP- :,
4.24-E + O 7..',n F-, 7,
4.6flnEt : f,.?.. F-,. ;,
2.40REr,l '. T-\ It-,,.',
2.57RE+0 J.:-,anr- •,
4.9-Rr+n .L?-..'.^-,::
3.092E-01 l.(jl4E-iU
3.012E-01 1.4 7E-0.1,
G.023E-ni r.f^SE-n-,
2.;.'63E + U. l..;i2E-iii
1.797Ef'l 2.97r>E-l)r
1.85 Erii 1 .f.DOE-n,1
                                        VII-9

-------
    Table VU-7. (Cent.)
RUN
GAS  HEIGHT   AHG-1
                                PO/PX
LN(PO/PX)  1/PO-l/PX
Kl
                                     K2
85BI,
8561)
85BO
85BI5
85BI1
858(3
85CPA
SSCPA
85CPA
85CPA
85CPA
85CPA
86AA
86AA
S6AA
86 A A
86AA
86AA
86BPD
86BPD
86BPD
86BPD
86BPD
flfiRPD
86CB
86CB
86CB
86CB
flACR
86CB
"NO"
"NO"
"NO"
"N02"
"N02"
"N02"
"NO"
"NO"
"NO"
"N02"
"N02"
"N02"
"NO"
"NO"
"NO"
"N02"
"N02"
"N02"
"NO"
"NO"
"NO"
"N02"
"N02"
"N02"
"NO"
"NO"
"NO"
"N02"
"N02"
"N02"
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.00
9.50
1.652E+00
1.184E+0
5.922E-01
1.652E+00
1.184E+00
5.922E-01
1.652E+00
1.18UE+00
5.922E-01
1.652E+00
1.184E+00
5.922E-01
7.971E-01
5.717E-01
2.859E-01
7.974E-01
5.717E-01
2.859E-01
7.974E-01
5.717E-01
2.85QE-01
7.97UE-01
S.717E-01
2.859E-01
7.974E-01
S.717E-01
2.859E-01
7.97«*E-01
5.717E-01
2.859E-01
5.00UE+00
4.000E+00
3.125E+00
7.714E+00
4.909E+00
3.600E+00
1.333E+01
1.111E+01
6.6G7E+00
1.222E+01
8.462E+00
6.111E+00
2.500E+00
2.250E+00
1.500E+On
1.6«»3E+0
1.533E+00
1.769E+00
5.000E+00
1.667E+00
3.043E+00
9.5f5E+00
5.526E+00
4.773E+00
8.^00E+00
8.^ooE+on
6.000E+00
6.667E+01
2.000E+01
i.oonE+oi
                                          2.590E+00 -1.233E-02
                                          2.108E+00 -l.OUE-02
                                          1.897E-1-00 -5.6o7E-03

                                          2.503E-I-00 -1.020E-02
                                          2.136E+00 -6.783E-03
                                          1.810E+00 -
                                          9.163E-01 -6.667E-03
                                          8.109E-01 -5.556E-03
                                          4.055E-01 -2.22rE-03

                                          ^.964-E-Ol -2.795E-03
                                          4.27*tE-01 -2.319E-03
                                          5.705E-01 -3.34t.E-03
                                          1.609E+00 -5.714E-03
                                          1.540E+00 -5.238E-03
                                          1.113E+00 -2.919E-03

                                          2.256E+00 -1.628E-02
                                          1.710E+00 -8.622E-03
                                          1.563E+00 -7.186E-03
                                          2.128E+00 -7.0^8E-03
                                          2.128E+00 -7.0«t8E-03
                                          1.792E+00 -4.762E-03

                                          <+.200E+0  -6.567E-02
                                          2.996E+OU -1.900E-02
                                          2.303E+00 -9.000E-03
                                                          1.568E+00
                                                          1.515E-»-nn
                                                          1.803E+00
                                                          3.057E+0.)
                                                          1.149E-1-0
                                                          l.«+18E+On
                                                          l.«H8E+Of)

                                                          6.2?5E-01
                                                          7.176E-01
                                                          2.018E+00
                                                          3.893E+00

                                                          2.829E+0;
                                                          2.990E+.1
                                                          2.669E+00
                                                          3.722E+0,'
                                                          6.268E+00

                                                          5.267E+0.1
                                                          5.210E+0 t
                                                          8.055E+00
                                                                           7.047E-n,'J
                                  8.360E-03
                                  9.717E-03
                                  7.773E-03
                                                                     U.056E-03
                                                                     1.17nE-,)2
                                  7.tfv..E-(13
                                  9.162E-;! j
                                  1.021E-0?

                                  2.041E-02
                                  l.riOBE-02
                                  8.83-)E-03
                                  1.237.E-02
                                  8.235E-02
                                  3. '23E-02
                                  3.1U8E-0?
                                        VII-10

-------
    Table VH-7. (Cont.)
RUN   GAS   HEIGHT   AHG-1
PO/PX
LN(POXPX)  1/PO-l/PX
Kl
K2
87A
#7A
87A
87A
87A
87A
87B
87B
87B
87D
878
87B
87C
87C
87C
87C
87C
87C
92AA

g2A'
c52 A A
92AA
92 A V
£?2B''
p2B> •
c?2B~
2BD
ej2B^
o2BH
"NO"
"NO"
" NO"
"N02"
"N02"
"N02"
"NO"
"NO"
"NO"
"N02"
"N02"
"N02"
"NO"
"NO"
"NO"
"N02"
"N02"
"N02"
"NO"
"NO"
"NO"
"N02"
"N02"
"N02"
"NO"
"NO"
"NO"
"N02"
"N02"
"N02"
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.0
9.50
26.50
19.00
9.50
26.50
19.0
9.50
26.50
19.0
9.50
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.00
9.5fl
U.720E-01
3.3R4E-01
1.692E-01
4.720E-01
3.3RUE-01
1.A92E-01
4.720E-01
3.3R4E-01
1.692E-01
4.720E-01
3..1R4E-01
t.ft92E-01
4.720E-01
3.384E-01
1.692E-01
4.720E-01
3 TO liC~ f\ 1
• »J Cl *T t U A
1.692E-01
4.720E-01
3.3R4E-01
1.692E-01
U.720E-01
3.38HE-01
1.A92E-01
4.720E-01
3,38tE-01
1.A92E-01
U.720E-01
3.38fE-01
1.692E-01
2(
1,
!'
2,
1,
1,
3
3
1
2
1
1
5
4
2
2
2
1
2
1
1
2
1
1
3
2
2
1
7
4
.045E+0,'
.800E+00
.607E+0
,167E-»-00
.733E+0
.105E+00
.667E+00
,333E>00
.833E+00
.537E+00
.962E+00
.1+86E-I-00
.5b6E+00
.00 E+00
.564E+00
.740E>00
.2f7E+00
,72tE+00
.OOOE+00
.786E+00
.515E+00
.160E-I-00
.800E+00
.6B7E+00
.133E+00
.937E+00
.089E+00
.^OOE+01
.OOOE+00
.308E+00
7,
5,
It
7,
5,
3,
1
1
6
9
6
3
1
1
9
1
8
5
6
5
^
7
5
5
1
1
7
2
1
1
•156E-01
,87fiE-01
.745E-01
.732E-01
.500E-01
.403E-01
.299E-t-On
.204E+OiJ
.061E-01
.308E-01
.711E-01
.959E-01
.715E+00
.386E+OI1
.416E-01
.008E+0;)
.097E-01
.t^7E-01
.931E-01
.798E-01
.15r)E-01
.701E-01
.878E-01
.232E-01
.142E+00
,078E+0:i
.360E-01
.639E+00
.946E+00
.460E+00
-4.
-3.
-2.
-4.
-2.
-1.
-4 .
-t.
-1.
-2,
-1,
-9,
^
-3
-1
-1
-1
-7
-I*
-3
-2
-4
-2
-2
-1
-4
-2
-2
-1
-5
646E-D3
5:>6E-D3
698E-03
487E-03
821E-03
•559E-03
,R4->E-03
>?f 2E-03
,51r.E-03
,95f.E-03
.851E-03
.341E-OU
.5h6E-03
.orn)E-n3
.564E-03
.710E-03
.217E-03
.2U1E-04
.0" E-03
.lt3E-03
,061E-n3
.296E-03
.963E-03
.516E-03
.539E-03
.122E-03
.317E-03
.321E-02
.071E-02
.907E-03
1.516E+0
1.737E+0-
2.804E + 0!!
1.63RE + 0':
1.626E-1-0.
2.011E-I-0:'
2.753E+t)n
3.558E+00
:s.583E+o;i
1.972E+0..
1.9 i?F. + 0^;
2.3^0E + n.;
3.63^+n.)
4.097E+0'i
S.OfiHE+n.i
2.136E+OH
2.393E + 0 •!
3.2,.'OE + i)
1.469E+OH
1 .714E+0''
2.456E-I-01.
1.632E + 0 ••
1.737E+On
3.093E+0'i
2.420E+00
3.184E+0"
^.354E+On
5.:.-92E+Oi)
5.751E+00
8.632E+0;^
9.R4r>E-03
1 .051E-Oi;
t .rj9SE-02
9. SORE-OS
M.3-.5F-0 ;
9.2UjF-i)3
1 .027F.-H,':
1 .?'j4F-i-)P
8. 95 E-O.'i
A.?.,lF-,n
S.-^nPK-.'i '
r. . ,?^ -,!.,
9.653F-M.'
fi.'>f> E-0.'
Q.2'*riE-fn
3.f.R..F-:i'>
,J«OO • r ^ ' ' . J
^ ? f\ il F ^ i ' "*t
*.*7V.-9E-n2
^.91PE-0?
3.16..E-02
3.1+91E-02
                                         VII-11

-------
RUN
     Table V1I-7.  (Cont.)
GAS  HEIGHT    AHG-1
                                 PO/PX
LN(POXPX)   1/PO-l/PX
                                                               Kl
K2
92CA
92CA
92CA
92CA
92CA
92CA
93AA
93AA
93AA
93A«
93AA
93BA
93BA
93BA
93BA
93BA
93BA
93CA
93CA
93CA
93CA
93CA
93CA
94 AR
94AB
94AB
9UAB
9UAB
9UAR
"NO"
"NO"
"NO"
"N02"
"N02"
"N02"
"NO"
"NO"
"NO"
"N02"
"N02"
"N02"
"NO"
"NO"
"NO"
"N02"
"N02"
"N02"
"NO"
"NO"
"NO"
"N02"
"N02"
"N02"
"NO"
"NO"
"NO"
"N02"
"N02"
"N02"
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.00
9.50
3
1
3
1
.720E-01
.384E-01
.692E-01
.720E-01
.384E-01
.692E-01
8.89«*E-01
6.377E-01
3.189E-01
8
6
3
8
6
3
8
6
3
8
6
3
a
6
3
3
2
1
3
2
1
.894E-01
.377E-01
.189E-01
.891+E-01
.377E-01
.189E-01
.377E-01
.189E-01
.894E-01
.377E-01
.189E-01
.894E-01
.377E-01
.189E-01
,85«4-E-01
.763E-01
.382E-01
.854E-01
.763E-01
.382E-01
9
6
3
7
2
2
2
1
2
2
1
3
3
2
5
5
5
5
5
3
1
3
6
1
1
1
.167E+00
.286E+00
.137E+00
.759E+00
.327E+00
.679E+00
.6U7E+00
.250E+00
.731E+00
.800E+07
.800E+01
.120E+01
.167E+00
.519E-I-00
.375E+00
.OOOE+07
.OnOE+07
.OOOE-t-07
.350E-fOn
.350E+00
.567E+00
.200E+02
.OOOE+01
.316E+00
.067E+00
.067E+00
.067E+00
7.667E+00
3.286E+00
1.917E+00
2.216E+00
1.838E+00
1.235E+00
2.049E+00
9.853E-01
9.731E-01
8.109E-01
5.486E-01
1
3
2
.715E+01
.332E+00
.iH6E-(-0()
1.153E+00
1.258E+0
8.650E-01
1
1
1
1
1
1
3
1
J
.773E+01
.773E+01
.773E+01
.677E-I-00
.677E+00
.272E+00
.101E+00
.843E+00
M c ii F~»n ?
n E^IL F •• 02
tl^flF-r-f)?
2.037E+00
1.190E+00
6.506E-01
-4.805E-03
-2.216E-03
-6.008E-03
-2.957E-03
-7.320E-03
-5.5b6E-03
-3.21flE-03
-l.OOOE+05
-9.643E-02
-3.643E-02
-4.561E-03
-5.302E-03
-2.895E-03
-l.OfViE+05
-1.0DfiE+05
-t.065E-03
-2.39 E-03
-9.917E-02
-2.417E-02
-1.430E-03
-2.778E-04
-2.778E-04
-2.778E-04
-2.899E-02
-9.938E-03
-3.986E-03
7.298E+0
4.341E+00
5.821E+00
1.272E+00
1.720E-K) ,
1.928E+01
7. 577^+0
1.296E+0 I
1.973E+0
2.713E + 0 i
2.780E+01
3.98r,E+00
5.383E+00
5.780E+0
1.674E-01
2.3 5E-01
H.671E-01
5.285E+OU
1.573E-02
1.420E-02
1.310E-02
1.273E-02
8.739E-03
0.r,19E-03
8.230E-0.5
8.712F-03
1 .019E-0?
I .r>i2F;-n i.
9.07RE-03
i!S,Efn5
7.523E-0 'i
3.790E-02
1.3R9E-02
l!o05E-03
2.01i'E-03
7.520E-02
3.f)9f,E-02
2.R .^E-0?
                                         VII-12

-------
    Table VH-7. (Cont.)
RUN   GAS  HEIGHT   AHG-1
PO/PX
94BA
94BA
910A
gUBA
g^CA
guCA
gtCA
g5AB
g5AB
95AB
95AB
95AB
g5AB
gSBA
95BA
gSBA
95BA
gSBA
95BA
95CA
gSCA
gSCA
95CA
P5CA
95CA
"NO"
"NO"
"NO"
"N02"
"N02"
"N02"
"NO"
"NO"
"NO"
"N02"
"N02"
"N02"
"NO"
"NO"
"NO"
"N02"
"N02"
"N02"
"NO"
"NO"
"NO"
"N02"
"N02"
"N02"
"NO"
"NO"
"NO"
"N02"
"N02"
"N02"
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.0"
9.50
26.50
19.00
9.50
3.854E-01
2.763E-01
1.382E-01
3.B54E-01
2.763E-01
1.382E-01
3.854E-01
2.763E-01
1.382E-01
3.854E-01
2.763E-01
1.382E-01
2.628E-01
1.8R4E-01
9.421E-02
2.628E-01
9.421E-02
2.628E-01
1.8R^E-01
P.628E-01
1.88*fE-01
Q.421E-02
2.628E-01
g!421E-02
2.628E-01
9!l21E-02
2.200E+00
1.571E+00
6.000E+00
3.600E-I-00
1.929E+00
3.onoE+on
2.800E+00
1.909E+00
3.667E+00
2.340E+00
1.7^6E+00
1.333E+OU
1.286E+00
1.200E+00
2.222E+00
1.622E+00
1.364E+00
1.964E+00
1.833E+00
1.375E+00
2.632E+00
1.786E+00
1.389E+00
2.375E-1-00
2.000E+00
2.935E+00
2.167E+00
1.596E+00
LN(POXPX)  1/PO-l/PX
          7.805E-01 -2.182E-03
          6.751E-01 -1.753E-03
          4.520E-01 -1.039E-03

          1.792E+00 -9.259E-03
          1.281E+00 -M..815E-03
          6.568E-01 -1.720E-03
                                          1.09QE+00 -1.905E-03
                                          1.030E+00 -1.71^E-03
                                          6.166E-01 -8.650E-04

                                          1.29f'E+00 -2.424-E-03
                                          8.503E-01 -1.219E-03
                                          5.573E-01 -6.782E-04
          2.877E-01  -1.852E-03
          2.513E-01  -1.587E-03
          1.823E-01  -1.1HE-03

          7.985E-01  -1.074E-03
          4.834E-01  -2.072E-03
          3.102E-01  -1.212E-03
6.751E-01  -1.753E-03
6.061E-01  -1.515E-03
3.185E-01  -£
Kl
                                                                2.0U6E+0
           9.676E-01  -3.263E-03
           5.798E-01  -1.571E-03
           3.285E-01  -7.778E-OU
           8.650E-01 -1.I+47E-03
           6.931E-01 -1.053E-03
           3.950E-01 -5.099E-04

           1.077E+00 -2.127E-03
           7.732E-01 -1.282E-03
           IU678E-01 -6.555E-04
K2
                                  5.6  1E-0')

                                  7.519E-03


                                  1.
2.850E+Ou
3.726E-1-0
4..680E+0 .
3.371E+0
3.077E + 0 ••••
U.034E+0-
6.203E-03
6 . 2b' E — 0/>
«*.900E-.i3
                                                                 1.095E + 0 i
                                                                 1.935E + 0!)

                                                                 3.039EtO';
                                                                 2.5f» E+n ;
                                                                 3.292E+0-!
                                                                 2.569E + 0 i
                                                                 3.217E+00
                                                                 3.682E+0
                                                                 3.077E+0 )
                                                                 3.292E+00
                                                                 3.679E+00
                                                                 4.193E+00
                                  7.n^7r-.).i
                                  R.^p-E-n^
                                  1. :.7')E-02

                                  1.5 OE-02
                                  1. ' 0'.F-n2
                                  1.207E-0,?
                                            fi.O'*2E-f).''j
                                            7.237E-03
                                                                 4.966E+00
                                  5.50RE-03
                                  5.587E-03
                                  5.»tl2E-03

                                  8.094E-03

                                  fi!958E-03
                                        VII-13

-------
 RUN
      Table VII-7. (Cont.)
GAS  HEIGHT   AHG-1
                                PO/PX
LN(POXPX)  1/PO-l/PX
                         Kl
                                                                               K2
96AA   "NO"  26.50  1.542E+00  1.933E+00  6.592E-01  -3.218E-03   4.276E-01   2.08KE-03
96AA   "NO"  19.00  1.105E+00  2.636E+00  9.694E-01  -5.G43E-03   8.770E-01   5.105E-03
96AA   "NO"   9.50  5.527E-01  2.071E+00  7.282E-01  -3.695E-03   1.318E+0:i   6.685E-03


96AA  "N02"  26.50  1.512E+00  2.40i>E+07  1.699E+01  -l.OOOE+05   1.102E+01   6.486E+OU
96AA  "N02"  19.00  1.105E+00  4.800E+00  1.569E+00  -1.583E-02   l.m9E+0;i   1.432E-02
96AA  "N02"   9.50  5.527E-01  2.00IE+00  6.931E-01  -4.167E-03   1.254E+00   7.539E-07,
96BA
96BA
96BA
96BA
96BA
96BA
96CA
96CA
96CA
96CA
96CA
96CA
97AA
97AA
97AA
97AA
97AA
97 AM
97BA
97BA
97BA
97RA
97RA
97BA
"NO"
"NO"
"NO"
"N02"
"N02"
"N02"
"NO"
"NO"
"NO"
"N02"
"N02"
"N02"
"NO"
"NO"
"NO"
"N02"
"N02"
"N02"
"NO"
"NO"
"NO"
"N02"
"N02"
"N02"
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.00
9.50
26.50
19.00
9.50
1
1
5
1
1
5
1
1
5
1
1
5
(*
3
1
4
3
1
3
1
U
3
1
.542E+00
. losE-t-no
.r)27E-01
.542E+00
.105E+On
.527E-01
.5U2E+00
.105E+00
.527E-01
.542E+00
.105E+00
.527E-01
.720E-01
.384E-01
.692E-01
.720E-01
.384E-01
.692E-01
.720E-01
.384E-01
.692E-01
.720E-01
.384E-01
.692E-01
3
2
1
2
1
5
2
9
4
2
2
1
1
1
1
2
2
3
2
1
.143E+00
.4U4E+00
.486E+01
.600E-I-01
.368E+00
.onoE+oo
.857E+00
.onoE+oi
I286E+00
.250E+00
.250E-t-00
.800E+00
.600E+00
.436E>00
.273E+00
.273E+00
.OOOE+OO
.226E+00
.222E+00
.695E+00
1.145E+00
8.938E-01
S.938E-01
2.698E-I-00
3.258E+00
3.137E-01
1.609E+00
1.492E+00
1.050E-I-00
4.50!)E-»-0;)
ll455E+00
8.109E-01
8.109E-01
5.878E-01
4.700E-01
3.618E-01
2.412E-01
8.210E-01
6.931E-01
3.567E-01
1.171E+00
7.985E-01
5.276E-01
-3
-2
-2
-2
-7
-14.
-3
-1
-9
-1
-3
-5
-5
-3
-2
-1
-9
-2
-2
-8
-2
-1
.896E-03
.62i-E-03
.626E-03
.808E-02
.085E-Ot
.0: E-03
.857E-03
t8o9E-02
.OOOE-02
.651E-03
.5!)6E-03
.556E-03
.143E-03
.5157E-03
.545E-03
.OOOE-03
.571E-01
.452E-03
.390E-03
7.428E-01
8.006E-ni
1.617E+n
1.750E-t-0
5.675E-01
1.3U9E+0
2.919E+0.1
2.083E+0'/
1.718E-t-0",
2.397E-I-O.J
9.959E-01
1.069E+0.
1.425E+00
2.048E+01!
2.108E+0!i
2.360E-I-OI)
3.119E+OU
2.5^7E-0.1>
1.728E-02
1.282E-n7,
2.595E-03
3.i:f,E-03
3.360E-03
9.0n7E-03
1.17 E-i)?
1 .6<*2E-02
2.102E-02
4.540E-03
4. 601 E-03
5.737E-03
5.393E-03
5.9UE-03
5.06- E-03
9.432E-03
7.2 4E-03
8.215E-03
                                        VU-14

-------
RUN
     Table VII-7. (Cont.)
GAS  HEIGHT   AHG-1
PO/PX
LNtPO/PX)  1/PO-l/PX
Kl
                                                                         K2
97CA
97CA
97CA
97CA
97CA
97CA
"NO"
"NO"
"NO"
"N02"
"N02"
"N02"
26.50
19. On
9.50
26.50
19.00
9.50
<+.720E-01
3.384E-01
1.692E-01
f .720E-01
3.3R4E-01
1.692E-01
4.955E+00
3.825E+00
2.180E+00
2.817E+00
2.050E+00
1.737E+00
1.600E+Ofi
1.341E+0)
7.793E-01
1.046E+00
7.178E-01
5.523E-01
-3
-2
-1
-1
-1
-7
.62RE-03
.591E-03
.083E-03
.802E-03
.024E-03
.193E-04
3
3
H
2
2
3
.391E+00
.964-E+OO
,60.'>E + Oi)
.217E+0(
.12iE*m,
.265E + 0^i
7
7
6
3
3
H
.687E-03
.f>50E-OJ
.39 'E-JI3
.019E-03
.(T27E-03
.251E-03
     IN STATEMENT  11.21:  END OF FILE ON INPUT
                                         vn-15

-------
                            Table VII-8. Rate Constants from the GAP Data10
         DO PART 15
             OUP = »GAROUT
          RUN
GAS  HEIGHT   AHG-1
PO/PX
LN(POXPX)  1/PO-l/PX
                                                                              Kl
                                                                                         K2
14-1
11-1
._. lt-2
14-2
11-3
11-3
14-4
14-4
14-5
14-5
14-6
14-6
15-1
15-1
15-2
15-2
15-3
15-3
15-4
15-4
15-b
15-5
15-6
15-6
17-1
17-1
17-2
17-2
17-3
17-3
17-4
17-4
17-5
17-5
17-6
17-6
18-1
18-1
18-2
18-2
18-3
18-3
18-4
18-4
18-5
	 Tfr-5
18-6
18-6
"NO"
"N02"
•LNQ1
"N02"
"NO"
"N02"
"NO"
"N02"
"NO"
"N02"
"NO"
"N02"
"N0lf
"N02"
"NO"
"N02"
"NO"
"N02"
"NO"
"N02"
"NO"
"N02"
"NO"
"N02"
"NO"
"N02"
"NO"
"N02"
"NO"
"N02"
"NO"
"N02"
"NO"
"N02"
"NO"
"N02"
"NO"
"N02"
"NO"
"N02"
"NO"
"N02"
"NO"
"N02"
"NO"
"N02"
"NO"
"N02"
1
1
	 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
.50
.50
,50.
.50
.50
.50
.50
.50
.50
.50
.50
.50
.50
.50
.50
.50
.50
.50
".50
.50
.50
.50
.50
f50
.50
.50
.50
.50
.50
.50
.50
.50
.50
.50
.50
.50
.50
.50
.50
.SO
.50
.50
1.243E-01
1.243E-01
1.243E-01
1.243E-01
1.243E-01
1.243E-01
1.243E-01
1.243E-01
1.243E-01
1.243E-01
1.243E-01
1.243E-01
.243E-01
1.243E-01
1.243E-01
1.243E-01
1.243E-01
1.213E-01
1.213E-01
1.213E-01
1.243E-01
1.243E-01
1.243E-01
1.243E-01
1.243E-01
1.243E-01
1.243E-01
1.243E-01
1.243E-01
1.243E-01
1.243E-01
1.243E-01
1.243E-01
1.243E-01
1.243E-01
1.243E-01
1.243E-01
1.243E-01
1.243E-01
1.243E-01
1.243E-01
1.243E-01
.50 1.243E-01
.50 1.243E-01
.50 1.243E-01
.50
.50
.50
1.243E-01
1.243E-01
1.243E-01
1.268E+00
1.243E+00
1_.38_QE±P_0
1.351E+00
1.439E+00
1.409E+00
1.561E+00
1.563E-t-OU
1.602E+00
1.578E+00
1.469E+00
1.913E+00
.254E+OU
1 .239E+00
1.330E>00
1.350E+00
1.361E+00
1.395E+00
1.412E+O.I
1.445E-KK)
1.43JE+0!)
1.465E+00
1.176E+OU
i.biie+oo
1.351E+00
1.514E+00
1.379E+00
1.516E+00
1.396E+OU
1.580E+0!)
1.477E+OH
1.653E+00
1.528E+OU
1.652E+00
1.561E+00
1.684E+00
1.277E+OU
1.202E+00
1.326E+OU
1.363E+0(J
1.342E+00
1.318E+OU
1.381E+OM
1.413E+00
1.453E+00
1.129E+00
1.172E+00
1.185E1-00
2.
2.
3_.
3.
3.
3.
4.
4.
4.
376E-01
177E-01
220E-01
009E-01
637E-01
128E-01
452E-01
463E-01
716E-01
4.561E-01
3.842E-01
6.486E-01
2.
2.
2.
2.
3.
3.
3.
3.
3.
3.
3.
Hi
3.
4.
3.
4.
3.
4.
3.
5.
4.
5.
4.
5.
2.
1.
2.
264E-01
116E-01
850E-01
999E-01
084E-01
327E-01
151E-01
682E-01
595E-01
822E-01
891E-01
125E-01
OuSE-01
149E-01
215E-01
161E-01
334E-01
576E-01
90UE-01
027E-01
238E-01
022E-01
455E-01
211E-01
4t;2E-01
839E-01
82aE-01
3.098E-01
2.913E-01
2.759E-01
3.
3.
3.
i.
3.
3.
226E-01
461E-01
738E-01
571E-01
867E-01
953E-01
-9
-9
-1
.822E-04
.347E-04
.026E-03
-9.892E-04
-9.232E-04
-9.087E-04
-9.756E-04
-1.023E-03
-ti.bhlE-04
-8.742E-04
-5.765E-04
-1.151E-03
-9
-9
-9
-9
-a
-8
-7
-«
-fa
-7
-6
-6
-1
-2
-1
-1
-a
-i
-7
-1
-7
-9
-7
-8
— J.
-8
-9
~-i
-7
-7
-6
-7
-6
-6
-6
-6
.937E-04
.361E-04
.613E-04
.974E-04
.009E-04
.741E-04
.42:JE-04
.0 '9E-04
.5iaE-04
.005E-04
.186E-04
.384E-04
.38. E-03
.035E-03
.035E-03
.482E-03
.563E-04
.3oOE-03
.973E-04
.163E-03
.749E-04
.817E-04
.402E-04
.&M3E-04
.091E-03
.102E-04
.45:jE-04
. 067E-03
.613E-04
.135E-04
.893E-04
.477E-U4
.9G2E-04
.582E-04
.140E-04
.168E-04
1.912E+OU
1.752E+0-J
2.592E+00
2.422E+OU
2.927E + 0'J
2.759E + 0!)
3.58JEfOii
3.592E+0,)
3.795E+UJ
3.670E+0',)
3.092E-I-0')
5.2 :OE+0 )
1.82, :£ + ()•)
1.727E+0 i
2.^94E+0:,
2.413EtO'f
2.482EtOn
2.67,'E + O !
2.7/,'EfO'i
2.064EtO!'
2.89JE+0
3.076E + 0;;
3.131E+0 ')
3. ^20E MI;;
2.419E+0
3..) 9EfO <
2.58,'.E + 0 i
3..549E+0 i
2.b83EfO!i
3.6fl3EtO-i
3.138EMD '
4.0't6Ei-0 i
3.41.EK)-.
4.042E*0'.
3.506E<-0,i
4.194E+00
1.965E+0 )
1.480EK) ,
2.27P.E + 0.,
2.493E-t-Oii
2.369EfO -..
2.2J1E+00
2.596E4-0 ;
2.785EfOJ
3.0.i9E+U:i
2.874E+OJ
3.112E+OD
3.182E+UO
7.905E-03
7.523E-U3
8.259E-03
7.962E-Ui
7.430E-Ui
7.314E-U3
7.8bl£-03
a.2J'Jt- )j
6.973E-'J^
7.03DE-03
4.b':-UE-(J3
9.2obt-03
7.9 .flt-U3
7.5.'i4E-()^
7.,-'3/t-U.^
«.U27t-!J5
6.4 c,E-U3
7.U3bE-rJ3
b.973E-D3
6.4 bt-0.}
b.i246L-:Jj
b.638E-UJ
4.97')E-03
.. b.l3;it-tu
1.' 7E-DJ
1.638E-02
G.J UL-JJ
1.I93E-U2
6..491E-03
1.D71E-02
f..417E-;)3
y.359E-03
b.;M7L-'J3
7.901t.-;i3
5.9b7E-03
7.149E-U3
f. . ?c;3L-n j
i'.521E-03
7.iilOE-!J3
8.5f>4E-(J3
6.127L-03
5.743E-Q3
5.M7E-03
6.i)lflE-03
5.6U3E-05
5.297E-03
4.9U2E-U3
4.964E-03
UJ
        ERROR  IN STATEMENT  11.21:  END OF FILE ON  INPUT
                                               VII-16

-------
APPENDIX VIII. LABORATORY STRIPPER TESTS
                 VIII-1

-------
                                                                                          Table V1II-1
                                                   G
                                          L     (cc/min
                  Run    Date    Page  (cc/min)  at SIP)   Gas
 i
bo
  1   27 July    60
  2            61
  3
  4
  5

  6
  7   28 July
  8
  9
 10
 11
62

62
64

 I
65
 12
 13   29 July   67

 14
 15
 16
 17
 18   30 July   69
19   2 Aug     71

20   2 Aug     71
                                          4.5
5.4
4.6
4.2
3.7

3.7
4.3
4.9
4.5
4.3
4.3
                                         4.1
                                         4.9

                                         4.8
                                         4.1
                                         5.5
                                         5.0
                                         8.3
                                         5.1
                                                  100
250
100
250
100

250
100
250
100
250
250
                250
                100

                250
                100
                250
                250
                                                 100
                                                 250

% H2S04 % HNSOg Column Ac
Gas Jn Out In Out" Stripping NO, NO (°F) (°
N





A





2 '





T





)0 80 1
	
—
—
—
—
id
up
Fl Packing
.0 1.0 0 0.0 0.0 RT RT Sac
0.9 10 0.0 0.0 RT
0.9 10 0.3 0.0 170
0.9 10 0.4 0.0 170
0.6 40 0.7* ~5.0 300
0.3 70 0.7 -3.2 280
— 0.9 0.9 0 0.0 0.0 RT
—
—
—
t
*
N2 82 8








—
N2
N2







2



0 0.0 0.0 RT
0 0.3 0.0 172
1 0 0.3 0.0 174
0.07 90 -2* 0.0 270
0.17 80 -1.2 0.0 271
0.9 0 0.0 0.0 RT
0.9 0 0.0 0.0 RT
0 0.2 0.0 185
0 0.3 0.1 182
0.5 45 ~1 0.6 280
















0.82 — — — — 	 — Ca
0.74 0.42 43 0.0 0.0 RT RT
0.74 0.60 19 0.0 1-2 RT RT
Idles
















rbon


                                                                                                                                                Cold
                                                                                                                                                Trap
                                                                                                                                                Sieves
                                                                                                      Cold
                                                                                                      Trap
                                                                                                                                               Sieves
                                                                                                                                               Sieves
                                                                                                                        Comments

                                                                                                                        Runs 1-6 of doubtful
                                                                                                                        validity were, there-
                                                                                                                        fore, repeated as Runs
                                                                                                                        13-17
                                                                                                                                                         *NO2 fluctuating pro-
                                                                                                                                                         bably due to top of
                                                                                                                                                         column being cold
                                                                                                                *NO2 fluctuating pro-
                                                                                                                bably due to top of
                                                                                                                column being cold
                                                                                                                fS.G. =  1.742 at  82 °F
                                                                                                                *S.G.= 1.735 at 84 "F
                                                                                                                                                         Column blocked with
                                                                                                                                                         fines. Wash with 80%
                                                                                                                        Heat sample lines at
                                                                                                                        outlet but not at top of
                                                                                                                        column
                                                                                                                        NO2 jumps up to ~1%
                                                                                                                        every time a sample is
                                                                                                                        taken even though no
                                                                                                                        air enters the system

-------
                                                                                   Table VIII-1. (Continued)
 i
CO
G
L (cc/min
Run Date Page (cc/min) at STP) C
21 2 Ai
22
23
24
25
26 3 Aj.
27
28
29
30
31 4 Ai
32
33

34
35
36
37 5 At
38
39
40
41
g 71 5.0 100 I
4.0 250
3.9 100
4.9 250
72 ~4 100 t
g 74 8.0 100
6.1 250
6.5 1C
6.6
\ 6.6
g 77 5.7
83 3.3
83 3.3
to


77 3.3 200
2.7
2.8
g 84 2.9
85 2.9
85 2.6
87 3.2
87 2.6
42 6 Aug 88 2,8
43
44
45
46
88 2.3
89 2.8
91 4.1
91 4.7
% H,SO. % HNSOK
24 5 c
as In Out In Out Stri{
2 «i
Lir
7





N2
N2
t
!•
Lir 8
'2
Air



1




2 82 0
1
9 79 0.

81
79 2.
Column Acid
c % % Temp Column
jping NO0 NO (°F) (°F) Packing Dryer Comments
74 0.03 96 0.0 >5 173 B
0.02 97 0.0 >5 172
0.02 97 0.0 >5 320
0.02 97 0.0 >5 317
— — 0.2 0.0 320
62 0.85 8 0.3 0.0 RT
0.86 7 0.2 0.1 RT
0.94 0 0.3 0.0 181
0.03 97 2-14 >5 338
1 0.13 94 ~2 >5 326
80 2.1 0
— 0.85 0
— 0.85

—
—
—
0—0.
T — 0.




86 0
90 <0
03 £
02 9




09 9
01 11
19 0.4 >5 280
8 0.4 >5 271
-10 0.2 271

0.7 0.7 265
<0.4 >5 262
0.0 >5 287
T Cai








0 1.2 0.0 280 280
W 0.1 >5 190 185
0.0 >5 237 246
0.0 >5 270 268
0.0 >5 313 317
— 0.83 0.08 90 Ito6 0.0 190 185
—
—
—
0.04 95 ~1 0.0 226 230
<0.01 100 1.8 0.0 277 256
<0.01 100 1.6 0.0 304 296
— 0.01 0
.0 — 0.0 0.0 312 270 1
rbon Si
eves 	


Air run for only 15 min
NO2 climbing
Cold 	
Trap













	
	
	
	
High NC^ occurred on
flooded column. Returned
to lower NO2 when
column stopped flooding
	
	
	
	


	
	
	
	
As temp rose from 280
to 304 NO2 rose to about
8% and then decreased to
1.6% within an hour


-------
                                 Table VIII-2
No.
1
2
3
4
5
6
7
8
9
10
11
Feed Acid
Concentration
(% HNSOg) *
0.59
0.59
0.59
0.68
0.83
0.73
0.59
0.83
0.83
0.83
0.83
Air Feed
Rate
(cc/min)
800
800
800
800
800
800
400
400
400
400
400
NO in Effluent (%)
Percent
N00 NO Denitration
1.50
1.52
1.20
3.20
3.52
1.30
1.06
2.16
2.96
3.76
3.36
0.11
0.11
0.10
0.09
0.17
0.63
0.04
0.29
0.27
0.16
0.19
99.0
99.3
**
99.0
98.9
**
**
71.1
99.0
**
**
Material
Balance
Error (%) t
16.5
25.7
41.2
-35.4
2.8
35.1
76.0
37.9
56.5
41.0
53.9
 * Acid fed at 10 cc/min.

** ~ 99% denitrated.


 f Material balance error =
NO  (in)  - NO (out)
   X          A.

     NO  (in)
        A.
                                     VII1-4

-------
                      APPENDIX IX.  INSTRUMENTATION CALIBRATION

       A. Calibration of the UV Spectrophotometer for NO2 at Concentrations Above 1%

       During most of the early experimentation, the UV analyzer has been used for the anal-
ysis of NO2 at concentrations up to 1% NOg.  During some of the stripper experimentation (Sec-
tion VIII of this report), the UV analyzer was used in  cases where the expected NO« concentra-
tions were as high as  10%.  To allow us to use the UV spectrometer in this NO0 concentration
                                                                        £t
range, we have checked the response curve by preparing known gas samples. The dependence
of the response curve on flow rate, cell temperature (i.e.,  span setting), and diluent gas was
determined.
       The gas samples were prepared by mixing (at  constant flow rate) NO, O,, and Ar or
N2 in the N0x reactor, allowing sufficient time for greater than 98% conversion to NOg. The
residual NO concentration was determined and corrected for.  Using properly calibrated flow
meters, it was possible to prepare gas mixtures containing up to 15% NO-.  The  UV spectro-
meter gain was set at one concentration, with a  known gas  sample standard mixture from
Matheson. Then the higher concentration samples we prepared were passed through the UV
and IR cells,  and a UV spectrometer calibration curve was constructed.  The spectrometer
response was found to be sensitive to cell temperature (span setting) flow rates but independent
of the diluent gas (N« or Ar),  as expected. Three typical response curves are shown in Fig.
IX-1.
       The unusual shape of the response curves indicates that a linear extrapolation from low
concentrations will give inappropriate analyses. The  dual-valued curves make it difficult to
determine which of two possible concentrations might be indicated by any given recorder re-
sponse (e.g.,  150). Representatives of duPont indicate that these problems can be most readily
overcome by using a shorter analysis cell.  Up to this time a 15-in. cell had been used. A new
1.5-in. cell was installed in the spectrometer to overcome  the problem.
       The change in shape of the response curves, as slow rate and cell temperature  are
varied,  deserves special attention.  It verifies the importance of heated sample lines, a ther-
mostatted sample warmer by the UV analyzer, and  standard flow rates.  This was used, in both
laboratory and miniplant experimentation.
       B.  IR  Spectrometer Calibration
       The IR spectrometer gain was first adjusted with a  known gas mixture from Matheson.
                                          IX-1

-------
    300
o
CO


I
CD
OJ
OS

(H
0)
4-J


E

2
200
C/3
    100
                                                   Hot 0.8 i/min

                                                   span  482
Hot 2.0 I /min

span 424
                                                            /min
                                                 !old 2.0

                                               span 234
                                                  10
                                                                        15
                                 Mole % NO0
     Fig.  IX-1.  UV spectrometer calibration curve for NO2 with the 15-in. cell.
                                   IX-2

-------
The IR cell was calibrated for high NO concentrations (0 to 100%) by feeding known mixtures
of NO and Ar to the IR cell.  The calibration curve is mildly dependent on flow rate.  A typical
calibration curve is given in Fig. IX-2.  The basic conclusion one may draw is that accurate
analysis for NO above the 1% level requires very careful standardization techniques, and such
measurements should be avoided, if possible.
                                            IX-3

-------
   200
             (100% NO)
    150

-------
           APPENDIX X. OXIDATION OF NO TO NO2 FOR MINIPLANT GAS FEED

       Miniplant experimentation requires a source of NO» for the oxidation of SO,. Sufficient
NO, is required to form 6000 ppm NO, at 12 SCFM.  It is preferable to have an easily regulated
NO  supply with less than 10% of the NO  present as NO.  Higher fractions of NO place an undue
   **                                 X
loading on the scrubber and the stripper.
       Of the three possible sources of NO :
              1.  Commercial NO0,
                                £t
              2.  Homogeneous oxidation of NO, and
              3.  Catalytic oxidation of NO,
we conclude that the most expedient and satisfactory  source is homogeneous oxidation of NO.
Use of commercially available NO™  involves additional handling and  control problems which
may be avoided using NO as a source.  Catalytic oxidation of NO with air and activated charcoal
(dry) has been shown to involve the potential dangers of thermal runaway at high NO concentra-
tions,  e.g., temperature  changes of 44 °F/sec have been observed with 11.6% NO in air.
       Homogeneous oxidation of NO with O9  was studied using Ar and N-  as diluent gases.
The gases were obtained  in high pressure cylinders from Matheson  and Airco. In-house com-
pressed air was used without drying.  The reactor, a 4 ft. length of  4-in. glass pipe, was held
at an ambient temperature of about 70  °F.  Gas sampling lines leading to the UV and IR  cells
were 3/16-in. I.D. Teflon lines with a total length of about 30 ft.  The flow rate from the reac-
                                               o
tor, through  the UV cell up to the IR cell,  was 2 ft /min.  The residence time in the sample
lines was about 0.2 sec.  Residence time in the UV cell was less than  1 sec. One may thus
ignore sampling line-residence times in kinetic calculations. Experimental results are pre-
sented in Fig. X-l.
       To allow for the performance of a sufficient number of experiments in a reasonable
time, we must pay careful attention to possible sources of analytical errors. In the present
case, we must consider the results obtainable with the UV and IR analyzers. As discussed in
Appendix IX, concentrations above 2%  (as measured by either analyzer) may be expected to
give only semiquantitative information about the gas being analyzed.  At concentrations between
500 ppm and  1%,  low baseline drift and frequent calibrations yield data accurate to ± 2% of the
indicated value. We can  most accurately evaluate rate constants by using data corresponding
to the 500 ppm in 1% regions and in concentration regions where the kinetic equations are not
                                           X-l

-------
    o
    z

    a
                                 % NO as input
Fig. X-l.  Conversion of NO to N02 at room temperature without a catalyst (argon flow

          was 1740 ml/min).
                                   X-2

-------
sensitive to small analytical errors (10 to 90% conversion of NO to NO,).  These requirements
are met by the starred data in Fig. X-l, and the rate constants so obtained may be used to cal-
culate results which would otherwise require excessive experimentation.
       The reaction 2NO -f 0-  -  2NO, is  expected to obey third-order kinetics, and this has
been verified by M. Bodenstein [Z. Elektrochem 22, 327 (1916) and Z. Physik. Chem., 100, 68
(1922) ].  If we denote the initial O, partial pressure by a (atm) , the  initial NO partial pressure
by b (atm), the  instantaneous partial pressure of NO- by x (atm), and time by t (sec), the rate
of formation of  NO, is  then given by:
                 tt

        §= K(a-J)  (b-x)2
The integrated form is:
                                            i
or the equivalent form
         1      1    ,   1        2a-x    b        Kt
         E   ~ B=x
Given a value for a, b, x, and t, one may solve for the rate constant K.  In our case,  the
values were:
a =
b =
x =
t =
which leads to
0.169 atm O»
0.030 atm NO
0.86 b
44.1 sec
                     -2   -1
         K =  29.3 atm  sec    .
Now that we have solved for K, it is possible to predict the residence time required for any
degree of conversion of NO to NOg and starting with any desired initial O2 and NO partial pres-
sures.
       We know from experimental data of Fig. X-l that it is possible to achieve 95% or greater
conversion of NO to NO,  at high O, concentrations. It is of interest to know what might happen
if air were used with NO at varying residence times. This is easily calculated. In Table X-l,
we present the time necessary to reach the specified conversion of NO to NO, starting with
various NO partial pressures.
       The information which is of more direct use to us concerns the number of linear feet
required to generate sufficient NO, for 6000 ppm of usable NO, in a 12 SCFM gas stream.  At
99%  conversion of NO to NO,, one obtains 98% usable NO,, and to get 6000 ppm usable NO,,
one needs:
                                           X-3

-------
                  Table X-l.  Conversion of NO to NO  with Air (See Text)
Starting
NO(%)
3
10
20
25
29
J. J.111^
0.8
23.4
8.6
6.50
7.09
9.1
VNS k/LSW^-AJ. 0-W* N.
0.9
53.2
20.2
17.0
20.9
34.2
/v t* r N^A I^JAV** yi^ v
0.95
113.2
44.0
39.8
54.1
119.8
—/
0.99
595
238
235
367
1532
        12 SCF,!V °>006 =  0.0735 SCFM of NO.
              0.98
Similarly for 95,  90, and 80% conversion, one requires 0.80,  0.90, and 0.120 SCFM of NO,
respectively.
       To calculate F, the required number of cubic feet of NO reactor volume, we use the
                                                           X.
formula:
Where T = the time in seconds to achieve the desired degree of conversion, S = the number of
SCFM of NO feed required at the specified degree of conversion, 60 = the number of sec/min,
and F = the fraction of gas entering the reactor which is NO. The number of linear feet of re-
actor required is F/0.0873.  Using this formula,  Table X-2 and Fig. X-2 were prepared.
       Fig. X-2  vividly illustrates that greater than 95% conversion of NO to NO, conversion
with air can be expected with 10 ft of piping as long as the portion of NO going into the NO
                                                                                   -A.
reactor is between 10 and 29%.  It also illustrates that, if the portion of NO going into the NO
                                                                                      A
reactor is much  less than 10%,  drastically larger reactors  are required to achieve high yields
of N02.
                                          X-4

-------
 Table X-2.  Required Length of 4-in. NO Reactor to Oxidize
            NO to NO2 with Air and Obtain 6000 ppm NO2 in
            a 12 SCFM Stream by Dilution

              Length of Reactor for Specified Conversion (ft)
Starting
N0(%)

   3

  10
  20
  25

  29
0.8
17.8
1.97
0.76
0.66
0.71
0.9
30.5
3.44
1.47
1.41
2.02
0.95
57.7
6.72
3.03
3.28
6.32
0.99
278
33.4
16.5
20.6
74.1
                          X-5

-------
Fig. X-2.  Conversion of NO to NO2 at room temperature without catalyst (number of linear
          feet of 4-in. pipe required to give 6000 usable ppm NC>2 when diluted into a  12-SCFM
          stream;  see text).
                                         X-6

-------