EPA-660/2-74-062

DECEMBER 1974
                       Environmental Protection Technology Series
Feasibility  of  Overland-Flow

Treatment  of  Feedlot Runoff
>5SB
% «X
                                                   UJ
                                    National Environmental Research Center

                                     Office of Research and Development

                                     U.S. Environmental Protection Agency

                                           Corvallis, Oregon 97330

-------
                      RESEARCH REPORTING SERIES
Research reports of the Office of Research and Development,
U.S. Environmental Protection Agency, have been grouped into
five series.  These five broad categories were established to
facilitate further development and application of environmental
technology.  Elimination of traditional grouping was consciously
planned to foster technology transfer and a maximum interface in
related fields.  The five series are:

          1.   Environmental Health Effects Research
          2.   Environmental Protection Technology
          3.   Ecological Research
          4.   Environmental Monitoring
          5.   Socioeconomic Environmental Studies

This report has been assigned to the ENVIRONMENTAL PROTECTION
TECHNOLOGY STUDIES series.  This series describes research
performed to develop and demonstrate instrumentation, equipment
and methodology to repair or prevent environmental degradation from
point and non-point sources of pollution.  This work provides the
new or improved technology required for the control  and treatment
of pollution sources to meet environmental quality standards.

This report has been reviewed by the National  Environmental
Research Center—Corvallis, and approved for publication.   Mention
of trade names or commercial products does not constitute  endorsement
or recommendation for use.

-------
                                              EPA-660/2-74-062
                                              December 1974
FEASIBILITY OF OVERLAND-FLOW TREATMENT OF FEEDLOT RUNOFF
                            by
                     Richard E. Thomas
      Robert S.  Kerr Environmental Research Laboratory
                    Ada, Oklahoma 74820
                     Project 16080 WNU
                  Program Element 1BB045
                   ROAP 21-ASH/Task 004
       NATIONAL ENVIRONMENTAL RESEARCH CENTER
          OFFICE OF RESEARCH AND DEVELOPMENT
         U.S. ENVIRONMENTAL PROTECTION AGENCY
                 CORVALLIS, OREGON  97330
         For Tale by tEr"SuP-"ntendent ot uocuments, U.S. Government Printing OAce
                Washington. D.C. 20402 - Stock No. 5501-00974

-------
                           ABSTRACT
A three-phase study was initiated to explore the practicality of adapting
the overland-flow approach to treatment of runoff from cattle feedlots.  A
six-month period of pilot-scale experiments to determine the feasibility
of the concept was to be followed by field experiments to develop loading
rate information and demonstration projects to verify the utility of the
approach.  This report covers the six-month period of pilot-scale
experiments and six months of data  collection at one field experiment.
The pilot-scale studies were conducted on plots which were 6-feet by
30-feet with a 4.5 percent slope.  These studies indicated that: (1)
loadings of 2 to 3 inches per week were suitable for field testing, (2)
the weekly load should be applied in fractional increments at daily to
three times per week frequencies, and (3) instantaneous spray rates
should be less than 0.10 inch per hour.
The field studies covered in this report were initiated at a 12,000-head
capacity feedlot and utilized a four-component train for runoff collection
and treatment.  The treatment train  included collection lagoons, a storage
reservoir,  the overland-flow area,  and a final polishing pond. Data
from the short period of operation (six months) corroborated the results
of the pilot-scale study and indicated that inclusion of the final polishing
pond substantially improved the overall performance.
This report was submitted in fulfillment of Project Number 16080 WNU,
by the Robert S. Kerr Environmental Research Laboratory under the
sponsorship of the Environmental Protection Agency.  Work was completed
as of June 1973.
                                 11

-------
                       CONTENTS
Sections
I    CONCLUSIONS                                        1
II    RECOMMENDATIONS                                   2
III   INTRODUCTION                                       3
IV   EXPERIMENTAL METHODS                               5
V    OPERATIONAL AND EVALUATION PHASES                  8
VI   DISCUSSION                                         21
VII   REFERENCES                                        23
VIII  APPENDIXES                                         24
          APPENDIX  A                                   25
          APPENDIX  B                                   26
          APPENDIX  C                                   27
          APPENDIX  D                                   28
                            iii

-------
                       TABLES


No.                                                  Page

1    QUALITY OF FEEDLOT RUNOFF—PILOT STUDY             9

2    TREATMENT EFFICIENCY FOR 3.0 INCHES PER WEEK
     LOADING APPLIED IN THREE EQUAL FRACTIONS AT
     0.15 INCH PER HOUR                                 10

3    TREATMENT EFFICIENCY FOR 2.5 INCHES PER WEEK
     LOADING APPLIED IN THREE EQUAL FRACTIONS AT
     VARYING RATES                                    11

4    TREATMENT EFFICIENCY FOR 2.5 INCHES PER WEEK
     LOADING APPLIED IN SEVEN EQUAL FRACTIONS AT
     VARYING RATES                                    13

5    MONTHLY PRECIPITATION, WASTEWATER APPLICATIONS,
     AND RUNOFF DATA, ACRE-FEET                        14

6    AVERAGE POLLUTION PARAMETER QUALITY DATA
     ON SIX TO FIFTEEN SAMPLING DATES                   16

7    TIME-RELATED QUALITY CHANGES AT THE FARM POND
     DISCHARGE                                        18

8    MASS REMOVAL PERCENTAGES FOR THE OVERLAND-
     FLOW AND FARM POND COMPONENTS OF THE
     TREATMENT TRAIN                                  19
                           IV

-------
                      ACKNOWLEDGMENTS
Personnel of Meat Producers, Inc., owners and operators of the feedlot,
provided on-site management and operation of the distribution systems
for the overland-flow area at the field study site. Everett Reeves,
owner and operator of a small feedlot near Ada, Oklahoma generously
provided a site for the pilot study.
Lowell C.  Penrod, Kenneth F. Jackson, Curtis V. Gillaspy, and Robert L.
Smith of the Robert S . Kerr Environmental Research Laboratory staff
carried the major burden of  sample collection and analysis for both
phases of  the project.
                                v

-------
                           SECTION I
                         CONCLUSIONS

The results of a six-month pilot-scale study indicated that the overland-
flow method of treatment has potential for treatment of feedlot runoff.
Liquid loadings of 2 to 3 inches per week applied at instantaneous
loading rates of less than 0.08 inch per hour appeared suitable for field
testing with dosing frequencies in the range of daily to three times per
week.
The results of a six-month field test supported the conclusion that the
overland-flow method of treatment has potential for treatment of feedlot
runoff under humid, subtropical climatic conditions.

-------
                            SECTION II
                       RECOMMENDATIONS

The results of the pilot-scale evaluation and the abbreviated field test
conducted in this study should be utilized to implement several field
tests which will verify the practicality of the overland-flow method for
treatment of feedlot runoff.  These field tests should be conducted at
several locations which are representative of climatic conditions
encompassing the major areas of beef production in the United States.

-------
                           SECTION III
                         INTRODUCTION

GENERAL
This study was initiated to evaluate the practicality of using overland
flow for treatment of runoff from beef cattle feedlots in warm, subhumid
regions. This runoff needs to be retained and treated before it can be
released to surface watercourses without serious pollutional effects.
BACKGROUND
Confinement feeding of beef cattle has increased rapidly in the Plains
States, and rainfall runoff from feedlots has been identified as a major
cause of fish kills in this area.   Runoff from feedlots frequently contains
high concentrations of suspended solids, organics which create bio-
                                                                    2
chemical oxygen demand, and nutrients which accelerate eutrophication.
Retention and treatment of this runoff at cattle feedlots located in this
subhumid area of the Plains States are major problems.
Application of wastewater to the land for reuse or treatment can be an
efficient and economical management approach when land is readily
available, as it is in the vicinity of many feedlot operations.  One method
of land based wastewater management which has been used successfully
is the overland-flow approach for treatment. Overland flow operates
successfully under intermittent or continuous use.   The system can be
managed to achieve efficient removal of suspended solids, biochemical
                                                           4
oxygen  demand, and nutrients from concentrated wastewaters.  Success-
ful use to date has been with wastewaters from other sources, but the

-------
major contaminants were similar to those found in runoff from cattle
feedlots.  Adaptation of the overland approach to runoff from cattle
feedlots would provide the cattle feeding industry with a new tool for
combating a serious problem.
SCOPE AND OBJECTIVES
This study of the overland-flow treatment of feedlot runoff is being con-
ducted in three phases.  The purpose of the three-phase approach was
to address the theoretical approach in stages with decision-making
milestones at the completion of each stage or phase.  The first phase of
the study was a six-month series of pilot-scale  experiments to determine
the feasibility of adapting the overland-flow approach to treatment of
feedlot runoff.  The primary objective for this phase of the study was to
make a quick and qualitative evaluation of several system designs.
Favorable results from this phase would lead to initiation of the second
phase of the study. The  second phase of the study would be the opera-
tion of a large-scale experimental system at a commercial feedlot.  The
objective of this phase was to field test three or four of the most promising
designs evaluated during the pilot-scale study. The field tests were to
be followed by a several-year demonstration of the best system design.
This report covers the six-month series of pilot-scale studies and the
first six months of data collection for one field experiment.

-------
                          SECTION IV
                   EXPERIMENTAL METHODS

The pilot-scale studies were conducted during the winter of 1969 and
1970 at a feedlot located near the Robert S. Kerr Environmental Research
Laboratory, Ada, Oklahoma.  The field tests were conducted during the
winter of 1970 and 1971 at a 12,000-head capacity feedlot located in north
central Texas.
PILOT-SCALE STUDIES
The pilot-scale studies were conducted on a loam soil with a slope of 4.5
percent.  An experimental area measuring 18-feet by 30-feet was bordered
with lawn edging to exclude extraneous surface runoff.  The experimental
area was divided into three plots measuring 6-feet by 30-feet, and a small
weir was installed at the lower end of each plot for collection of runoff
samples.  The native vegetation of mixed  grasses was not disturbed
during the preparation of the  experimental area.
Runoff from  the feedlot was collected and  stored in a sump prior to appli-
cation to  the experimental area.  The wastewater was pumped from this
sump to the overland flow plots through a fully automated sprinkler
application system which could be adjusted over a wide range of oper-
ating conditions.  The wastewater was applied independently to each of
the three experimental plots through a single fixed nozzle which covered
a four-foot diameter circle at the upper end of the plot. Samples of the
wastewater applied to the plots and samples of the runoff from each of
the three plots were collected at 7- to 14-day intervals throughout the
study period.

-------
 FIELD TESTS
 The field tests were conducted on an Austin silty clay with a natural
 slope of 3 to 5 percent. An experimental area of eight acres was divided
 into two areas with terraces at a spacing of about 250 feet.  Additional
 earthwork was conducted to exclude extraneous runoff and to permit
 operation of four separate experimental plots of about two acres each.
 The rainfall runoff from the 33 acres of cattle pens was collected initially
 in four lagoons with a combined surface area of about 22 acres.  After a
 variable period of settling in these lagoons, the collected runoff was
 pumped into a newly constructed reservoir for storage until it was
 pumped to the overland-flow area. Distribution to the overland-flow
 area was achieved through a fully automated sprinkler system equipped
 with rotating impact nozzles.  The distribution system was designed to
 permit operation of the four experimental areas at different loadings and
 different frequencies of application.  Runoff from the overland-flow areas
 was measured continuously  with Stevens A-35 stage recorders installed
 on H-flumes and then directed into an existing  farm pond with a storage
 capacity of about 4.5 acre-feet below the spillway.  Discharge from the
 farm pond was measured continuously with a Stevens F-l stage recorder
 installed on a 150 degree V-notch weir.  Precipitation at the project site
 was measured with a weighing, continuous recording rain gauge. The
 layout of the treatment train at the field site is shown in Figure 1 and
 includes the stations at which liquid samples were collected for analysis.
 Water samples collected during the pilot-scale study and the field tests
 were analyzed for pH,  conductivity, total suspended solids, chemical
 oxygen demand, 5-day biochemical oxygen demand, total organic carbon,
 total phosphorus, ammonia nitrogen, nitrate nitrogen, and nitrite nitrogen
 according to Environmental Protection Agency Methods.   Kjeldahl nitro-
                                                       7
 gen was analyzed by Technicon Auto Analyzer Methodology  which has
been checked against the Environmental Protection Agency Methods.
Samples collected during the field tests were also tested for algal
                                                             Q
productivity using the Environmental Protection Agency Method.

-------
LOCATION
                 Storage
                 Reservoir
         Diversion 
-------
                           SECTION V
             OPERATIONAL AND EVALUATION PHASES

 The use of short-term, pilot-scale studies was selected as an efficient
 approach to develop and demonstrate a substantially new application of
 the spray-runoff approach for land treatment of a wastewater. The pilot-
 scale studies would provide a quick  evaluation of many operational
 arrangements,  and the best of these would be given a much more thorough
 evaluation during the field test.
 PILOT-SCALE STUDIES
 The initial two-month period of study was used to evaluate loadings  of
 1.0, 2.0,  and 3.0 inches per week while holding the rate and frequency
 of application constant.  A second two-month period was used to evaluate
 the effect of different application rates while keeping the loading and
 frequency of application constant.  The final two-month period was  used
 to evaluate further changes in the rate of application and more frequent
 applications. Nine design and operational combinations were evaluated
 during the six-month pilot study.  The weekly loadings tested ranged
 from 1.0 inch per week to 3.0 inches per  week;  application frequencies
 tested were 3 and 7 times per week; and the rate of application during
 the spray period ranged from 0.036 to 0.15 inch per hour.
 The feedlot runoff being applied  to the experimental plots was sampled
 nine times during the pilot study.  The results of the analyses run on
 these samples are tabulated in Table  1. The minimum and maximum
values show that the quality of the feedlot runoff being applied to the
experimental plots was quite variable.  Maximum concentrations for

-------
     Table 1. QUALITY OF FEEDLOT RUNOFF—PILOT STUDY
Parameter
pH
Conductivity , y mhos
Minimum
7.2
2,200
Maximum
8.3
4,500 3
Mean
7.7 (median)
,300
(Concentration, mg/liter)
Total Suspended Solids
Chemical Oxygen Demand
Total Organic Carbon
Total Phosphorus
Total Nitrogen
Kjeldahl nitrogen
Ammonia nitrogen
Nitrate nitrogen
Nitrite nitrogen
64
790
250
18
43
42
10
<0.05
<0.05
1,059
2,350 1
820
42
162
160
51
3.4
1.8
390
,400
440
28
86
85
29
0.5
0.4
several of the parameters were more than three times greater than the
minimum values.  This variation in the quality of the feedlot runoff can
be attributed to differences in the quality of runoff from individual
runoff events and to changes which occurred as the collected runoff
was standing in the sump between runoff events.  The quality data in
Table 1 are for  a small capacity drain and fill sump and may not be
representative of the quality of runoff which would be retained in large
capacity holding lagoons.
The initial plot  trial was designed to evaluate weekly loadings of 1.0,
2.0,  and 3.0 inches per week while  holding the rate and frequency of
application constant.  The rate of application was 0.15 inch per hour,
and increments equal  to one-third of the weekly load were applied on
Mondays, Wednesdays, and Fridays . The results of this trial showed
that the 1.0  and 2.0 inches per week loadings did not produce any runoff

-------
 from the experimental plots .  The treatment achieved for the 3.0 inches
 per week loading is presented in Table 2. The concentration of most
 constituents was not reduced or was only slightly reduced by the
 overland-flow process .  The treatment efficiency did not approach
 desirable levels,  and  it was evident that this mode of operation had little
 potential for field testing .
 A second plot trial was initiated to evaluate rates of application of 0. 05,
 0.075, and 0.10 inch per hour while holding the weekly load and fre-
 quency of application  constant. The weekly load chosen was 2.5 inches
 per week and the frequency of application was the same three-times-per-
 week schedule used in the initial trial. The results of the second  pilot-
 scale trial showed that a loading of 2.5 inches per week would produce
 runoff for each of the selected rates of application under the selected
 conditions of operation.  The treatment achieved for this trial is
 summarized in Table 3.  The treatment efficiencies were somewhat
 better than for the first trial, and data were obtained for qualitative
Table 2 .  TREATMENT EFFICIENCY FOR 3. 0 INCHES PER WEEK LOADING
   APPLIED IN THREE EQUAL FRACTIONS AT 0.15 INCH PER HOUR

Parameter, mg/1
Total Suspended Solids
Chemical Oxygen Demand
Total Organic Carbon
Total Phosphorus
Total Nitrogen
Kjeldahl nitrogen
Ammonia nitrogen
Nitrate nitrogen
Nitrite nitrogen
Applied
feedlot
runoff
90
1,297
291
19.0
50.7
50
17
0.1
0.6
Plot runoff
Concentration %
103
1,025
248
18.7
44.9
39
9.8
5.0
0.1
Reduction
0
21
15
2
11
22
42
0
83
                                 10

-------
Table 3.  TREATMENT EFFICIENCY FOR 2.5 INCHES PER WEEK LOADING
     APPLIED IN THREE EQUAL FRACTIONS AT VARYING RATES
Plot runoff from
Parameter, mg/1
Total Suspended Solids
Chemical Oxygen Demand
Total Organic Carbon
Total Phosphorus
Total Nitrogen
Kjeldahl nitrogen
Ammonia nitrogen
Nitrate nitrogen
Nitrite nitrogen
Applied
feedlot
runoff
556
1,586
554
34
112.1
111
38
0.8
0.3
0.05 in
loading
Cone.
444
1,376
478
30
75.9
75
14
0.7
0.2
./hr.
rate
%Red.
20
13
14
12
32
32
63
12
33
0.075 in./hr.
loading rate
Cone .
331
1,188
388
23.5
63.1
60
10
2.8
0.3
%Red.
40
25
30
31
44
46
74
-
0
0.10 in.
loading
Cone.
349
1,260
462
25.4
82.4
80
12
2.0
0.4
/hr.
rate
%Red.
37
21
17
25
26
28
68
-
-

-------
 comparison of the three rates of application. Suspended solids and
 chemical oxygen demand removals were similar for the 0.075 and 0.10
 inch per hour rates while removal of these components was substantially
 less for the 0.05 inch per hour application rate.  The 0.075 inch per
 hour application rate was somewhat better than the other two rates
 for the remainder of the parameters.  Overall,  an application rate of
 0.075 inch per hour gave the best treatment for a weekly loading of 2.5
 inches  applied in three equal fractions on Mondays, Wednesdays, and
 Fridays.
 A third and final plot trial was designed to test even lower rates of
 application by dividing the 2.5 inches per week loading into daily incre-
 ments.  The rates of loading  tested in this trial were 0.036, 0.045, and
 0.060 inch per hour, and results of the  trial are summarized in Table 4.
 Treatment efficiencies were better than  for either of the previous trials
 and were surprisingly good for such a short duration test on small plots.
 The intermediate rate of 0.045 inch per  hour performed somewhat better
 for removal of chemical oxygen demand, organic carbon, and phosphorus;
 otherwise, performance was  similar for all three application rates.
 FIELD TESTS
 The field tests were intended to run for a period of two years and to
 provide for comparison of four operational approaches involving differ-
 ent weekly loads and rates of application at a frequency of three appli-
 cations  per week. The  actual period of  field testing lasted  only six
 months  from October 1970  through March 1971,  when it became necessary
 to terminate the study.  No attempt will be made to separate the results
 for different loadings and rates of application for this short test period,
 and the data collected will be combined to show the overall treatment
 achieved by the overland flow and farm  pond segments of the treatment
 system.
 Water Balance Data
During the brief period of the field study, a total of 20.2 acre-feet of
feedlot runoff was applied to the overland-flow area.  Rainfall added an
                                12

-------
Table 4.  TREATMENT EFFICIENCY FOR 2.5 INCHES PER WEEK LOADING
     APPLIED IN SEVEN EQUAL FRACTIONS AT VARYING RATES

Plot runoff from
Parameter, mg/1
Total Suspended Solids
Chemical Oxygen Demand
Total Organic Carbon
Total Phosphorus
Total Nitrogen
Kjeldahl nitrogen
Ammonia nitrogen
Nitrate nitrogen
Nitrite nitrogen
Applied
feedlot
runoff
460
786
300
24.9
62.5
62.0
19.5
0.3
0.2
0.060 in./hr.
loading rate
Cone.
184
575
205
19.2
24.9
24.0
1.0
0.2
0.7
%Red.
60
27
32
23
60
61
95
33
-
0.045 in./hr.
loading rate
Cone.
188
537
160
14.7
23.4
23.0
1.5
0.2
0.2
%Red.
59
32
47
41
63
63
92
33
-
0.036 in./hr.
loading rate
Cone .
192
630
225
17.6
24.6
24.0
2.0
0.2
0.4
%Red.
58
20
25
29
60
61
90
33
-

-------
 additional 4.2 acre-feet of loading to make a total loading of 24.4 acre-
 feet of liquid to the overland-flow area.  Evaporative losses and some
 deep percolation resulted in about 60 percent of the applied wastewater
 being lost on the overland-flow area, and only 9.0 acre-feet of liquid
 was discharged from the overland-flow area to the farm pond.  Addi-
 tional evaporative and seepage losses very likely occurred in the farm
 pond, but the discharge from the farm pond was 9.6 acre-feet due to an
 undetermined amount of surface runoff from other sources entering the
 farm pond. Monthly data for rainfall, wastewater applications, and the
 two points of runoff measurement are summarized in Table 5.  These
 data will be combined with chemical quality data in a subsequent section
 to show the treatment efficiency in terms  of mass removals.
 Chemical Quality Data
 Chemical quality data were collected at four points in the treatment train.
 These points were the collecting lagoon,  the newly constructed holding
 lagoon, the combined runoff from the overland-flow area, and the dis-
 charge weir of the farm pond.   The major points of interest for this study
Table 5.  MONTHLY PRECIPITATION, WASTEWATER APPLICATIONS,
                AND RUNOFF DATA, ACRE-FEET
Applied to overland-flow area
Month
October
November
December
January
February
Total
Precipitation
1.5
0.3
0.6
0,7
1.1
4.2
Feedlot
runoff
5.4
5.3
4.0
2.0
3.5
20.2
Total
6.9
5.6
4.6
2.7
4.6
24.4
Runoff
overland
flow
0.6
1.5
3.5
1.6
1.8
9.0
Discharge
from farm
pond
0.3
1.2
3.3
2.2
2.6
9.6
                               14

-------
 were the holding lagoon (the liquid being applied to the overland-flow
 system) , runoff from the overland-flow area,  and the discharge weir of
 the farm pond (final effluent from treatment train). The average chemical
 quality at the four sampling stations is presented in Table 6.  The quality
 of feedlot runoff in the collecting lagoons did not exhibit any definite
 trend of quality change during the six-month  study period, as is shown
 by the data in Appendix A,  There was a substantial change in quality
 upon pumping the liquid from the collecting lagoons to the newly con-
 structed holding lagoon.  The apparent increase in total dissolved solids
 upon pumping the liquid from the collecting lagoons to the holding lagoon
 is an artifact of data collection.   The holding  lagoon was filled in late
 September with feedlot runoff which had been stored in the collecting
 lagoons for up to a year.  As is shown by the data in Appendix A and
 Appendix B, this charge of wastewater had a total dissolved solids con-
 tent  greater than that of the  feedlot runoff accumulating in the runoff
 lagoons during the study.   The total dissolved solids of the second
 charge to the holding lagoon (pumped in early January) was comparable
 to the total dissolved solids content of the collecting lagoons.  The quality
 changes effected by the overland-flow area are modest, but it should be
 recognized that these quality changes were accompanied by evaporative
 losses and  soil percolation which reduced the  quantity of liquid from the
 24.4 acre-feet applied to 9.0 acre-feet which flowed into the farm pond.
 This 63 percent reduction in the quantity of liquid flowing from the
 overland-flow area into the farm pond represents a dramatic reduction in
 mass loading of pollutants on the farm pond in relation to a direct dis-
 charge to the pond.  The substantial quality changes observed between
the overland-flow area and the farm pond discharge (changes in the  farm
pond) are partly due to dilution by the undetermined amount of runoff
entering the farm pond from other sources in addition to metabolic con-
versions by life in the farm pond. The comparatively low total dissolved
solids content of the farm pond discharge is indicative of this dilution
effect.
                                15

-------
Table 6.  AVERAGE POLLUTION PARAMETER QUALITY DATA
         ON SIX TO FIFTEEN SAMPLING DATES
Pollution parameter , mg/1
Total Dissolved Solids
Total Suspended Solids
Chemical Oxygen Demand
Biochemical Oxygen Demand
Total Phosphate
Total Nitrogen
Collecting
lagoons
1,110
195
430
63
13.5
27.7
Holding
lagoon
1,400
104
350
28
4.0
15.4
Overland-
flow runoff
1,480
63
310
12
2.0
13.4
Farm pond
discharge
660
12
125
5
0.5
5.4

-------
The data summary presented in Table 6 does not show time-related changes
in quality,  Operations at the feedlot and the short duration of the study
prevented observation of meaningful time-related quality changes at all
sampling points except for the farm  pond discharge.  Some time-related
quality changes for this sampling station are summarized in Table 7.  The
total dissolved solids increased substantially for about 3 months and then
stabilized at about 60 percent of the  total dissolved  solids content of the
runoff coming from the overland runoff area.  The suspended solids, total
phosphorus,  and total nitrogen content of the farm pond discharge showed
similar time-related changes, but they did not show a steady increase with
increasing  time of operation.  It would obviously require a much longer
test period to observe meaningful changes for these parameters.  The
chemical oxygen demand also exhibited an irregular pattern of changes,
but it did show a definite increase with time, as did the biochemical
oxygen demand.  Although the biochemical oxygen  demand did show a
definite increase with time, it appeared to be stabilizing at a value which
would be suitable for downstream release under very stringent regulatory
controls based on the  5-day biochemical oxygen demand test.
Mass Removal Data
A more representative presentation  of the removals achieved by individual
components of the treatment train can be presented by combining the
water balance data and the chemical quality data to obtain mass removals.
This approach makes appropriate adjustments for the influence of evap-
orative losses, retention in the soil, losses to deep percolation, and
dilution from other runoff sources.  The data used to produce Tables 5
and 6 have been combined into mass removal percentages in Table 8.
This evaluation shows that the overland-flow component of the treatment
system accounts for the major removal of constituents on a  mass basis,
while the chemical changes and probable dilution which occurred in the
farm pond contributed substantially to achieving the overall removals in
the 80 to 90 percent range.
                                17

-------
                    Table 7.  TIME-RELATED QUALITY CHANGES AT THE FARM POND DISCHARGE
oo
Parameter, mg /I
Total Dissolved Solids
Total Suspended Solids
Chemical Oxygen Demand
Biochemical Oxygen Demand
Total Phosphorus
Total Nitrogen
0
342
4
78
2
0.4
4.4
35
437
9
71
2
0.2
3.5
Days of system operation
63 97 107
477
9
92
2
0.2
3.6
848
16
149
5
1.0
6.7
832
7
166
5
0.5
6.3
127
780
4
134
6
0.4
5.1

-------
Table 8.  MASS REMOVAL PERCENTAGES FOR THE OVERLAND-FLOW
    AND FARM POND COMPONENTS OF THE TREATMENT TRAIN
Parameter
Total Dissolved Solids
Total Suspended Solids
Chemical Oxygen Demand
Biochemical Oxygen Demand
Total Phosphorus
Total Nitrogen
Overland-
flow area
73
59
71
77
78
67
Farm pond
9
30
12
13
12
19
Combined
82
89
83
90
90
86
Algal Productivity Tests
The algal assay procedure has been developed as a method for determining
the potential of a water to stimulate algal growth and hasten eutrophication.
This test was included in the field study to measure the before and after
treatment response because feedlot runoff is known to have a comparatively
high potential to stimulate algal growth.  The liquid being sprayed on the
overland-flow area and the discharge from the farm pond (the end of the
treatment train) were the sampling points selected for the algal produc-
tivity tests . One test was conducted in December after 10.7 acre-feet of
feedlot runoff had been applied to the overland-flow area.   The results
of the test for this  sampling date were 100 growth units for the before
treatment sample and 18 growth units for the after treatment sample.  The
combined effect of the overland-flow area and the small farm pond on the
water quality resulted in a decisively lower potential to stimulate algal
growth.   A second test was run in February after an additional 9.5
acre-feet  of feedlot runoff had been passed through the treatment system.
The results of the algal productivity test for samples taken on this date
were comparable to those for the previous sampling date.  The results of
this test were  120 growth units for before  treatment and 25 growth units
                                 19

-------
for after treatment.  The close agreement of the results for these two
sampling data suggests that the capability of the treatment train to
curtail the potential of the feedlot runoff to produce algal growth was
relatively stable.
                                20

-------
                            SECTION VI
                           DISCUSSION

 The results of the pilot-scale study must be interpreted in proper per-
 spective since the experimental procedures were selected specifically to
 produce qualitative information quickly.  Relatively low efficiencies were
 anticipated because the length of the  slope was about 15 percent of that
 normally used for overland-flow and  the duration of each trial was a small
 fraction of the time a  soil system needs to stabilize at its expected treat-
 ment capability.  In light of these  experimental limitations,  the removals
 achieved in the pilot-scale study were very encouraging for development
 of a successful system.  The comparatively low removals for chemical
 oxygen demand and total organic carbon were used as indicators that
 verified the expected resistance of organics in the feedlot runoff to bio-
 oxidation,  and the field test area was designed with 250-foot terrace
 spacing to  provide a long residence time for the overland-How area.  It
 was anticipated that this spacing would provide sufficient time for
 microbial oxidation of most of the resistant organics.
 Just as the results of  the pilot-scale study must be  considered in relation
 to the desire to achieve quick qualitative results, the field test results
 presented in this report must also be  considered in light of the short
 duration of the test.  The short duration of the field test is a distinct
 disadvantage because the treatment system had not operated long enough
 to approach a stable condition, and the results observed are only indica-
 tive of what the overland-flow approach might achieve during a winter
 season start-up with a feedlot runoff which had been stored for many
months prior to application to the overland-flow  system. Behavior of
                                 21

-------
an overland-flow system during this period is usually indicative of
long-term behavior although treatment efficiencies are somewhat lower
than those for long-term behavior.  Regardless of the fact that other
overland-flow systems have shown improved treatment efficiencies after
a year or two of operation, establishment of the overland-flow approach
as a viable treatment alternative for management of feedlot runoff will
require long-term studies at several locations representing differing
climatic conditions.
                              22

-------
                          SECTION VII
                          REFERENCES

 1.    Loehr, R. C. Pollution Implications of Animal Wastes—A Forward
      Oriented Review. U.S. Dept. Interior, Fed. Water Pollution Contr.
      Admn., Ada, Oklahoma.  Report No. 13040	07/68.  July 1968.
      175 p.
 2.    Miner, J. R., R. I. Upper, L. R. Fina, and J.  W. Funk. Cattle
      Feedlot Runoff—Its Nature and Variation.  J. Water Pollut.  Contr.
      Fed. 38: 1582-1591, October 1966.
 3.    Luley,  H. G. Spray Irrigation of Vegetable and Fruit Processing
      Wastes. J. Water Pollut. Contr. Fed.   35: 1252-1261, October 1963.
 4.    Law, J. P., Jr ., R. E.  Thomas and L.  H. Myers.  Cannery Waste-
      water Treatment by High-Rate Spray on Grassland.  J. Water Pollut.
      Contr.  Fed. 42:1621-1631, September  1970.
 5.    Field Manual for Research in Agricultural Hydrology.  U.S. Dept.
      Agr., Beltsville, Maryland.  Handbook No, 224, September 1962.
      215 p.
 6.    Methods for Chemical Analysis of Water and Wastes. Environmental
      Protection Agency, Cincinnati, Ohio. EPA Report No.  16020—07/71,
      July 1971.  312 p.
 7.    Technicon Auto-Analyzer Methodology, Industrial Method 29-69A.
      Technicon Corporation, Tarrytown, New York.  1970.  3 p.
8.    Algal Assay Procedure—Bottle Test, National Eutrophication
      Research Program. Environmental Protection Agency, Corvallis,
      Oregon.  August 1971.  82 p.
                                23

-------
                      SECTION VIII

                      APPENDIXES


Appendix                                              Page

   A      WATER QUALITY DATA FOR THE RUNOFF
          COLLECTING LAGOONS                          25

   B      WATER QUALITY DATA FOR THE NEWLY
          CONSTRUCTED HOLDING LAGOON                  26

   C      WATER QUALITY DATA FOR RUNOFF FROM
          THE OVERLAND-FLOW AREA                      27

   D      WATER QUALITY DATA FOR THE FARM POND
          DISCHARGE                                   28
                           24

-------
Appendix A.  WATER QUALITY DATA FOR
  THE RUNOFF COLLECTING LAGOONS
Date
10-1-70
11-4-70
12-2-70
1-5-71
2-4-71
2-24-71
3-25-71
Mean
TDS
1,316
1,122
1,059
959
1,128
1,169
1,046
1,114
Parameter concentration ,
TSS COD BOD
174
107
216
267
174
136
292
195
620
314
386
396
403
298
569
426
165
15
23
-
65
31
80
63
mg/1
T-P
21.3
17.0
11.1
11.3
13.6
12.6
7.9
13.5
T-N
39.9
14.7
18.9
25.4
28.1
35.6
31.1
27.7
                25

-------
Appendix B.  WATER QUALITY DATA FOR THE
  NEWLY CONSTRUCTED HOLDING LAGOON
Date
10-1-70
10-15-70
10-22-70
11-4-70
11-19-70
12-2-70
12-17-70
1-5-71
1-21-71
2-4-71
2-11-71
2-18-71
2-24-71
3-11-71
3-25-71
Mean
TDS
1,720
1,743
1,769
1,719
1,698
1,688
1,682
1,024
-
1,014
1,033
1,005
-
1,051
1,032
1,398
Parameter concentration,
TSS COD BOD
112
35
39
39
56
81
92
180
102
127
146
130
156
188
80
104
490
419
324
335
331
362
368
302
231
367
345
357
346
348
365
353
26
-
-
15
-
6
-
-
-
25
-
-
27
-
69
28
mg/1
T-P
2.8
3.1
3.3
3.1
2.8
3.7
3.7
7.0
5.4
4.6
4.4
4.6
3.6
3.4
4.0
4.0
T-N
26.6
15.8
16.3
13.7
13.0
15.2
21.5
15.5
12.8
11.5
12.9
15.0
12.5
11.5
17.2
15.4
                 26

-------
Appendix C.  WATER QUALITY DATA FOR RUNOFF
      FROM THE OVERLAND-FLOW AREA
Date
10-7-70
10-15-70
10-22-70
10-28-70
11-4-70
11-12-70
11-18-70
12-2-70
12-11-70
12-17-70
1-21-71
2-4-71
2-11-71
2-18-71
Mean
TDS
1,543
1,488
1,667
1,678
1,698
1,438
1,640
1,653
1,664
1,614
1,277
965
1,220
1,150
1,478
Parameter concentration, mg/1
TSS COD BOD T-P
4
32
46
34
46
38
41
73
93
60
104
124
-
124
63
333
302
306
308
312
322
320
318
300
329
253
281
-
291
306
0.7
0.8
1.0
0.9
12 1.2
1.4
1.2
10 1.4
1.6
2.1
3.1
14 2.7
4.8
4.4
12 2.0
T-N
15.0
12.9
13.6
13.8
13.4
14.2
14.0
12.4
14.2
14.1
13.0
10.2
-
14.1
13.4
                    27

-------
Appendix D.  WATER QUALITY DATA FOR THE
         FARM POND DISCHARGE
Date
10-1-70
11-4-70
12-2-70
1-5-71
2-4-71
2-24-71
3-25-71
Mean
Days of
operation TDS
0
35
63
97
107
127
158
-
342
437
477
848
832
780
874
656
Parameter concentration, mg/1
TSS COD BOD T-P T-N
10
19
11
24
8
6
6
12
78
71
92
149
166
134
183
125
2
2
2
5
5
6
12
5
0.4
0.2
0.2
1.0
0.5
0.4
1.0
0.5
4.4
3.5
3.6
6.7
6.3
5.1
8.0
5.4
                  28

-------
                                    TECHNICAL REPORT DATA
                            (Please read Instructions on the reverse before completing)
 1. REPORT NO.
 EPA-660/2-74-062
             3. RECIPIENT'S ACCESS! OI*NO.
 4. TITLE AND SUBTITLE
    FEASIBILITY OF OVERLAND-FLOW TREATMENT OF
    FEEDLOT RUNOFF
             5. REPORT DATE
                   June 1974
             6. PERFORMING ORGANIZATION CODE
 7. AUTHOR(S)

    Richard E. Thomas
             8. PERFORMING ORGANIZATION REPORT NO.
 9. PERFORMING ORG -\NIZATION NAME AND ADDRESS
    Robert S . Kerr Environmental Research Laboratory
    Post Office Box 1198
    Ada, Oklahoma 74820
              10. PROGRAM ELEMENT NO.
                  1BB045
              11. CONTRACT/GRANT NO.
 12. SPONSORING AGENCY NAME AND ADDRESS
    U.S. Environmental Protection Agency
    National Environmental Research Center
    Office of Research and Development
    Corvallis,  Oregon  97330
              13. TYPE OF REPORT AND PERIOD COVERED
                Final   10/71 to 6/73
              14. SPONSORING AGENCY CODE
 15. SUPPLEMENTARY NOTES
 16. ABSTRACT
    This report covers six months of pilot-scale experiments and six months of data
    collection at one field experiment.

    The pilot-scale studies were conducted on plots which were 6-feet by 30-feet
    with a 4.5 percent slope.  These studies indicated that:   (1) loadings of 2 to 3
    inches per week were suitable for field testing, (2)  the weekly load should be
    applied in fractional increments at daily to three times per week frequencies,
    and (3) instantaneous spray rates should be less than 0.10 inch per hour.

    The field studies covered in this report were initiated at a 12, 000-head capacity
    feedlot and utilized a four-component train for runoff collection and treatment.
    The treatment train included collection lagoons, a storage reservoir, the overland-
    flow  area, and a final polishing pond.  Data from the short period of operation
    (six  months) corroborated the results of the pilot-scale study and indicated that
    inclusion of the final polishing pond substantially improved the overall performance.
 7.
                                KEY WORDS AND DOCUMENT ANALYSIS
                  DESCRIPTORS
b.lDENTIFIERS/OPEN ENDED TERMS
c. COSATI Field/Group
   Agricultural wastes
   Waste treatment
   Nitrogen cycle
   Phosphorus cycle
 Overland flow
  02/03   Pri.

  14/03   Sec.
 8. DISTRIBUTION STATEMENT

   Release unlimited.
19, SECURITY CLASS (This Report)
21. NO. OF PAGES
     28
                                              20. SECURITY CLASS (Thispage)
                           22. PRICE
EPA Form 2220-1 (9-73)
                       U. S. GOVERNMENT PRINTING OFFICE: 1974-697-651 /63  REGION 10

-------