ENVIRONMENTAL PROTECTION AGENCY
         OFFICE OF ENFORH1FNT
                 Audit Inspections
                  of
         Wastewater Sonn
ONAL ENFORCEMENT INVESTIGATIONS CENTER

          DENVER, COLORADO
              AUGUST   ?q

-------
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
OFFICE OF ENFORCEMENT
EPA-330/1-79-004
PERFORMANCE AUDIT INSPECTIONS OF WASTEWATER SOURCES
August 1979
NATIONAL ENFORCEMENT INVESTIGATIONS CENTER
Denver, Colorado

-------
                            CONTENTS



  I   INTRODUCTION 	   1

 II   BACKGROUND REVIEW  	   3

III   NOTIFICATION AND ENTRY 	   5

 IV   FACILITY INSPECTION  	   7

  V   FOLLOWUP ACTION  	  11



APPENDICES

     A    SAMPLE 308 LETTER
     B    TYPICAL PILOT COMPLIANCE MONITORING
            INSPECTION REPORT

-------
                            I.  INTRODUCTION
     Section 402 of the 1972 amendments to the Federal Water Pollution
Control Act required the establishment of a National Pollutant Discharge
Elimination System (NPDES) permit program.  Permits issued to industrial
and municipal sources by EPA or by the State, under EPA auspices, require
the permittee to monitor effluents to verify compliance with limitations
on specified parameters.  Periodically, data are submitted to the permit-
ting agency in a discharge monitoring report (DMR).  Based on these
reports, assuming the data submitted are valid, a regulatory authority
can determine if the permittee is in compliance.

     The EPA has used a variety of methods to determine facility com-
pliance with NPDES permit requirements.  These methods range from a
Compliance Evaluation Inspection (CEI) lasting several hours, to a
Compliance Sampling Inspection (CSI) extending over several days to
weeks, with 24-hour composite sampling of numerous Outfalls.   The CEI
allows compliance to be determined primarily through observation,
records review,  and discussion with the permittee; for example,  "Are
compliance schedules being met?" "Is self-monitoring being conducted?"
The CSI addresses these aspects and in addition,  allows a direct deter-
mination of compliance with the permit limitations.  It can also in-
clude an evaluation of actual techniques employed by the permittee in
performing the self-monitoring requirements of sampling, flow-monitoring,
analyses, quality control, record keeping, and reporting.   This  latter
evaluation is important because it provides an effective means to
determine the validity of the  DMR data.   This in turn is important
because considerable emphasis is placed on tracking DMR data for permit
compliance.

-------
     Because a CSI is resource intensive and does not usually include
an evaluation of the permittee's self-monitoring practices, the concept
of performance audit inspections (PAI) for municipal and industrial
wastewater sources was developed.  The primary objectives of the PAI
are to evaluate the permittee's sampling techniques, analytical proced-
ures, quality control procedures, DMR data, and compliance schedules.

     The NEIC has conducted over one hundred thirty PAI's during the
past three years.  This inspection procedure has been found to be:

     1.   An effective technique for evaluating the acceptability of
          DMR data and identifying and achieving correction of self-
          monitoring deficiencies.

     2.   A valuable screening technique through which serious pollu-
          tion problems can be identified for followup action.

     3.   Less resource intensive than a compliance sampling inspec-
          tion;  the average work days* spent on a PAI is 12 or
          slightly less than 40 percent of the 32 workdays* NEIC
          spent on a compliance monitoring inspection or CSI.

     The procedures NEIC personnel used in conducting a PAI are discussed
in the following sections.  Throughout these inspections the investiga-
tors followed the applicable NEIC Chain-of-Custody and document control
procedures.
*  Direct costs only.

-------
                        II.   BACKGROUND REVIEW
     Prior to conducting a performance audit inspection (PAI) the
available background information was reviewed.   This review has been
found essential for effectively planning a PAI.   It provides infor-
mation on the permittee's operations, permit limitations in force,
compliance schedules, self-monitoring requirements, and past history
of violations.   Some sources of background information generally re-
viewed are listed below.

     A.   NPDES Permit Application - The application provides data on
          wastewater characterization, water pollution control  prac-
          tices, water use, wastewater flows,  numbers, and types of
          discharges (e.g., process wastewater,  and cooling waters).

     B.   NPDES Permit

          1.    Effluent limitations - This portion of the permit pro-
               vides information on qualitative  and quantitative limi-
               tations; for example:   average  and maximum concentrations,
               average daily and maximum daily loads.

          2.    Self-monitoring Requirements -  This portion provides
               the frequency and type of sampling (grab or composite)
               and the flow-monitoring,  analytical, and data reporting
               requirements.

          3.    Compliance Schedule - This provides the schedule of
               events the permittee must accomplish to abate pollution
               and comply with the specified effluent limitations.

-------
£•   DHR Data - Provides a record of effluent quality and permit-
     tee compliance based on self-monitoring data.  A review of
     the data for the past year generally provides a good back-
     ground.

D.   Previous Inspection Reports - Inspection reports from EPA
     Regional and State files, which may describe the process
     operations and pollution control practices, provide the
     investigator team details on pollution problems.  In addi-
     tion, a review of available site maps and process and waste-
     water treatment flow diagrams are beneficial in providing
     familiarity with permittee operations.

E.   Regional andState Files

          A review of both State and EPA regional files can pro-
     vide the compliance history of the permittee.  Consultant
     reports prepared for the permittee on pollution abatement
     facilities are generally good sources of information.   Aerial
     photography, if available, are helpful  in gaining familiarity
     with the source.

-------
                     III.  NOTIFICATION AND ENTRY
     Before conducting an inspection a 308 letter was generally sent
to the permittee defining the authority, the general outline the per-
formance audit would take, the information and data that was to be
furnished during the inspection, and the self-monitoring that would
be evaluated [Appendix A].  The letters either stated the exact dates
when the performance audit inspection was to be conducted, or it gave
a general time frame, such as 'within the next six months'.  The speci-
ficity of the dates depends on the self-monitoring frequency and desired
results.  If the permittee conducts daily monitoring, a general time
period is adequate; however, if the permittee monitors infrequently
(e.g., once-per-week), more specific dates are necessary.  Using non-
specific dates essentially makes the inspection "unannounced" but it
also increases the risk of responsible officials being absent.

     Authority to gain entry to the site is provided in the Clean
Water Act, Section 308 (a)(B) which states, "The Administrator or his
authorized representative upon presentation of his credentials—(i)
shall have the right of entry to,  upon, or through any premises in
which an effluent source is located or in which any records required
to be maintained... are located, and (ii) may at reasonable times
have access to and copy any records, inspect any monitoring equipment
or method required..., and sample  any effluents which the owner or
operator or such source is required to sample for...  ."  The NEIC
investigating team entered the plant through the main gate or through
an entrance designated by the permittee in response to the notifica-
tion (308) letter.   Upon entering,  the investigators introduced them-
selves to a responsible plant official who was either the owner, op-
erator, officer, or agent in charge of the facility.   Identification
credentials were presented.

-------
     Many companies required that the inspection team upon entering a
facility, sign a visitor's sheet.  This sheet generally had blanks
for the name, times, reason for visit, organization, etc., and the
investigators would sign it.   On some occasions the visitor sheet
contained  a "Visitor's Release" (waiver) relieving the Company from
any liability.   NEIC employees have been instructed not to sign a
sheet containing such a waiver statement.  Once the investigators
explained to the responsible official that they were not permitted by
agency policy to sign such a waiver, the waiver statement was either
crossed out or the team was asked to sign a sheet containing no waiver
statement.

     Entry to a facility was never refused even in those cases where
no specific inspection dates had been provided in the 308 letter.
Employees had been instructed that if entry was refused, they should
not contest the issue with representatives but should obtain the name
and position of the individual representing the permittee and the
reasons for refusing entry.  The inspection team were then to leave
the premises immediately and telephone the Enforcement Specialist as
soon as possible for further instructions.   Subsequent attempts to
secure entry would then be through appropriate legal procedures.
Employees were instructed to completely document the entire sequence
of events concerning any refusal of entry.

-------
                       IV.  FACILITY INSPECTION
     The investigating team assigned to conduct the performance audit
inspection was dictated by the complexity of the source and the moni-
toring requirements.  Generally the team consisted of people with
knowledge and skills in:  (a) flow-monitoring techniques, including
the installation and calibration of flow-measurement devices and in-
struments, (b) sampling techniques including automatic sampling de-
vices, preservation requirements, holding times, etc., (c) analytical
procedures for specified permit parameters, (d) bio-monitoring/micro-
biological procedures, if required by the permit, and, where necessary,
e)  waste treatment technology, operation and maintenance practices,
and industrial production processes.

     The on-site inspection was directed primarily toward verifying
the accuracy of existing (EPA, State) file information, observing and
evaluating sampling, flow-monitoring and analytical procedures and
techniques, reviewing the record-keeping procedures, determining if
NPDES compliance schedules were being met and,  where appropriate,
evaluating operation and maintenance practices.

     Discussed below are the areas the NEIC inspection teams ad-
dressed during the PAI's:

     A,   Determine if file information on process operations and
          plant production rates, where applicable, is current; de-
          termine if existing information on wastewater treatment
          practices is correct.  In many instances background infor-
          mation on these areas did not exist or was limited and
          had to be developed during the inspection.

-------
                                                                 8
B.   Determine if the number and location of the discharges are
     as described in the permit, and if there are any unpermitted
     discharges.   Photographs are very useful in documenting the
     latter-type information.

C.   Determine if the compliance schedules in the permit are
     being, or have been met.

D.   Determine if all pertinent parameters are being monitored;
     for example, have changes in the manufacturing processes or
     waste treatment practices occurred and resulted in different
     discharge characteristics which may require changes in moni-
     toring.

E.   Evaluate permittee sampling procedures in terms of represen-
     tativeness,  frequency,  type of sample (grab or composite),
     compositing techniques  (flow proportional or not), type of
     containers used for specific parameters, and methods of
     collection (automatic or manual techniques).

F.   Evaluate flow-monitoring equipment and procedures in terms
     of:

     a)   Acceptability of devices used,  that is proper instal-
          lation, location,  and accuracy of measurement.
     b)   Frequency of flow-measurement,  for example:  continuous or
          instantaneous.
     c)   Calibration and quality control  procedures used to verify
          accuracy in measurement devices  and instruments.
     d)   Maintenance procedures followed  for measurement devices
          and instruments.

-------
     G.   Evaluate analytical procedures in terms of:

          a)   Preservation techniques and holding times for samples.
          b)   Methods used for parameters specified in the permit
               compared to 304 (h) requirements,
          c)   Methods and adequacy of instrument calibration and
               state of instrument repair.
          d)   Adequacy of the quality control/quality assurance
               (QC/QA) program for all analyses including those
               performed by automated equipment.
          e)   Record-keeping of bench data and accuracy of
               calculations.
          f)   Necessary approvals for use of modified procedures.

               The NEIC generally requested the permittee or the con-
          tract laboratory providing analytical services to analyze
          performance/verification samples.  This was an useful means
          of determining if the permittee's laboratory data were re-
          liable.   The investigators requested that the results be
          sent to EPA as soon as the analyses were completed.  However,
          there were some long delays in receiving the results.  This
          step in evaluating the permittee's analytical performance
          could have been expedited by sending the samples in advance
          of the inspection.

     H.   Review records the permittee uses to prepare the DMRs, such
          as laboratory bench sheets and flow-monitoring records.
          These data were selected at random and tracked from genera-
          tion in the laboratory to the DMRs.

     Although the performance audit was designed to provide informa-
tion concerning the validity of DMR data by evaluating self-monitoring
procedures,  it was also used to collect other important information.

-------
                                                                      10
For example, evaluations of wastewater treatment plant operation and
maintenance (O&M) practices were made during some facility inspec-
tions.  From this evaluation, the effects of O&M practices on the
self-monitoring data could be examined.   In addition, an evaluation
of the treatment facility design vs. actual conditions was made to
determine if the system was over, or under, design load either organi-
cally or hydraulically.

     Following the inspection of the plant, the investigators met
with the permittee for an informal discussion of their findings.   The
issues addressed were deviations from prescribed and/or recommended
procedures.   The team advised the permittee of the proper procedures
and techniques to be followed.   It was generally noted that once the
permittee understood the objectives of the performance audit inspec-
tion — to improve the accuracy of their self-monitoring procedures
and the results — the majority welcomed the information and advice
provided them.

-------
                          V.  FOLLOWUP ACTION
     Subsequent to the performance audit inspection, a written report*
such as that contained in Appendix B was prepared.   The report dis-
cussed discrepancies or deviations from prescribed or recommended
policies.   These reports were sent to the requesting Regional office
for appropriate action where the discrepancies were deviations from
required self-monitoring procedures and techniques; some Regional
offices issued Administrative orders to achieve correction.   A follow-
up inspection to determine the corrective action taken was conducted
by Regional and/or NEIC personnel.  Generally, NEIC investigators
found during the followup inspections that the permittees were making
a conscious effort to correct the deficiencies in self-monitoring
practices.   Although, the NEIC did not experience the situation, judi-
cial  referrals for demonstrated bad faith by failure to correct the
deficiencies as ordered, could be taken.  Moreover, if the performance
audit would have revealed that, for example, compliance schedules were
not being met, there were unpermitted discharges, or there was falsifi-
cation of the records, a judicial referral  could be made initially.

     The performance audit inspection followed by a followup inspec-
tion provided a means of assessing the DMR data and improving that
data.   The PAI was found less resource-demanding than a compliance
sampling inspection (CSI) and worked effectively as a screening device
to locate major pollution problems, which could then be scheduled for
an intensive CSI if necessary.
   In conducting an inspection,  the NEIC used a variety of checklists
   to aid in collecting information.  These checklists were found to
   be helpful in streamlining the inspection,  but it was emphasized
   to the investigation team that the checklists were to be used as
   tools, and not the driving force.  That is, the inspection should
   be more than just the completion of blank forms.

-------
    APPENDIX A





SAMPLE 308 LETTERS

-------
                                                                       A-l
                                             Date

ABC Company
     Pursuant to the authority contained in Section 308 of the Federal
Water Pollution Control Act (33 U.S.C. 1318) representatives of the
Environmental Protection Agency (EPA), specifically of the National
Enforcement Investigations Center, or Region V, may conduct an inspec-
tion of your Company's manufacturing operations, together with asso-
ciated waste treatment and discharge facilities, within the next six
months.  The inspection is designed to carry out EPA's responsibilities
under Section 308.  The persons who will be conducting the inspections
will be authorized representatives of the Environmental Protection
Administration as referred to in Section 308 and will present appro-
priate credentials.   They will observe your process operations;
inspect and evaluate your monitoring/field/laboratory equipment and
methods; examine monitoring and calibration records and other appro-
priate records; and will be concerned with related matters.

     The EPA visit will focus on procedures and, accordingly, it is
requested that Company monitoring be conducted under usual practices
and procedures.  On-the-spot observations shall be made of sample
collecting, field preservation of samples, handling and transport of
samples, and field and analytical equipment used in the actual conduct
of analytical/laboratory procedures.   If analyses are conducted by an
outside contractor,  EPA personnel will also evaluate analytical tests
and methods as they are being performed.   Please inform the inspectors
if any tests are conducted other than at your main manufacturing
location.

     It is requested that plant process flow diagrams, waste treatment
plant How diagrams, and treatment plant design data be made available
to the inspectors during the first day of their inspection.

     The EPA inspectors will also provide verification samples for
analytical evalution by the Company for certain pollutant parameters.
The results of these tests, as well as the results of the compliance
monitoring sampling taken during the inspection, should be transmitted
to the EPA's National  Enforcement Investigations Center,  Denver
Federal Center, P.O.  Box 25227, Denver, Colorado 80225, within two
weeks after the EPA inspection.

     Please inform the appropriate plant personnel to expect such an
inspection to ensure a rapid plant entry and to ensure that these
surveys are conducted without unnecessary delay.

     We will appreciate your full cooperation in this matter.

                                   Sincerely yours,

-------
                                                                        A-2
                                             Date

Dear Mr. 	:

Pursuant to the authority contained in Section 308 of the Federal
Water Pollution Control Act (33 U.S.C. 1318) representatives of the
Environmental Protection Agency, specifically, the NEIC office in
Denver, Colorado and/or Region 	 will conduct an inspection of your
Company's manufacturing operations together with associated waste
treatment and discharge facilities.  The inspection is planned for
the week of 	 and is intended to determine degree of
compliance with the requirements of the National Pollutant Discharge
Elimination System issued to your Company.

Our representatives will observe your process operations, inspect and
evaluate your monitoring/field/laboratory equipment and methods;
examine appropriate records; and will be concerned with related
matters.

The EPA visit will focus on procedures, and accordingly, it is reques-
ted that Company monitoring under conditions of the NPDES permit be
scheduled to precisely correspond with this inspection.   We ask only
that the Company conduct its monitoring (for all parameters, if at
all possible) under normal procedures and practices.   On-the-spot
observation shall be made of sample collection, any field preserva-
tion of samples, handling and transport of samples, field and analy-
tical equipment in operation, and the actual conduct of analytical/
laboratory procedures.  If analyses are conducted by an ouside contrac-
tor, please notify your agent that EPA personnel will  evaluate analy-
tical tests and methods as they are being performed.   Please inform
us if these tests are conducted elsewhere than at your main manufac-
turing location.

Please provide the name of any "new"  individual whom we may not have
had contact with in the past (if such is necessary) to enable our
access to the plant.   We would appreciate a list of safety equipment
if required by our people.  Any reports or information that may be
considered confidential by you will be treated in accordance with
Section 308(b) of the Act, but should be properly identified as such
to the EPA, and necessary reasons for confidential claims may need to
be made available to the EPA.   However, "effluent data" is always
considered accessible to the public.

If you have any questions concerning this inspection,  please telephone
	, NEIC, Denver at 	.

                                   Sincerely yours,

-------
                     APPENDIX B



TYPICAL PILOT COMPLIANCE MONITORING INSPECTION REPORT

-------
      Environmental Protection Agency                        B_-|

           Office of Enforcement
      COMPLIANCE MONITORING EVALUATION
             October 27, 1977
National Enforcement Investigations Center
             Denver, Colorado

-------
B-2

-------
                                                                         B-3
                             INTRODUCTION
     On October 27, 1977 personnel from the National  Enforcement Investi
gations Center (NEIC) conducted an MPDES pilot compliance monitoring
inspection at the                                           I The main
purposes of this inspection were to ascertain the quality of the self-
monitoring data reported monthly by the Company to the
                                      and ultimately  to Region   USEPA,
and to determine whether the facility was in compliance with the con-
ditions of its MPDES permit.  As part of this inspection, the design
adequacy of the Company's wastewater treatment facilities and related
operation and maintenance practices were evaluated to determine what
impact they might have on the self-monitoring data.
     The inspection consisted of five basic steps:   1)  observation of
the sample collection, preservation and transport techniques,  2)  visual
evaluation and verification of-*the wastewater flow monitoring  techniques,
3) critical overview of procedures used in analyzing the samples, 4)  a
walk-through inspection of the manufacturing operations and wastewater
treatment facilities, and 5) review of record-keeping procedures, main-
tenance files,"and engineering design data.

     NEIC personnel left a standard sample for total suspended solids
(TSS) with the Company's laboratory personnel ano requested that  the

-------
B-4
        sample be  analyzed  and  the  data  results  returned  to  the  NEIC within  two
        weeks.   The  Company uses  the  contract  laboratory  services  of       Labora-
        tories in                      for  analysis  of  their  5-day  Biochemical
        Oxygen Demand  (BOD5)  samples.  To  check  on  the adequacy  of company's
        sample preservation procedures and to  evaluate the accuracy of
        analytical techniques,  NEIC personnel  spiked a portion of  the October
        26th  daily composite  sample with a known BODr  sample and requested that
        both  the spiked  and unspiked  samples be  analyzed  by      .   NEIC  personnel
        also  visited     Laboratories on  November  9th and evaluated their
        labo. atory technique"   In  addition, NEIC personnel  split  with the
        Company personnel the daily wastewater composite  sample  obtained  by  the
        Cc..^any at Outfall  001  for  October 27, 1977.   The split  sample was
        returned to  the  NEIC  laboratories  and  analyzed for TSS.  The door to the
        Company's  sampling  station  at  Outfall  001 was  secured with an NEIC
        padlock during the  entire time that the  October 27th sample was  being
        collected  to insure the integrity  of this sample.

             Based on  the observations made during  this inspection, the  data
        obtained,  and  the information  reviewed,  the inspection form presented
        later in this  report was  completed and conclusions and recommendations
        were  prepared.

-------
                                                                          B-5
                        SUMMARY AND CONCLUSIONS
     On October 27, 1977 personnel from the National Enforcement Invest!
gations Center (NEIC) conducted an NPDES pilot compliance monitoring
inspection at the                                            Wastewater
flow monitoring, sampling, and analyzing procedures were observed and
the wastewater treatment facility design, operation, and maintenance
were evaluated.  The findings and conclusions from this inspection are
discussed below.
Flow Monitoring

     The Company has an 18-inch, standard rectangular weir with end
contractions and a Foxboro Model 40 continuous flow recorder with float
level sensor at Outfall 001.  The weir is not sharp-crested, but rather
appears to be constructed of angle iron stock.  The Company had no
documentation to prove that the weir and flow recorder installation had
been installed and calibrated as a broad crested weir.

     Field measurements of depth of flow over the weir (H) were made by
NEIC personnel.  Using tabulated data for standard sharpcrested rec-
tangular weirs and the H values obtained, instantaneous flow rate values
were determined.  These values were compared against the flow recorder
values for the same times.  The Company data was approximately IIS lower
than the calculated data at high flow rates and about 36% lower at an
average flow. rate.  The differences in flow rates may be attributed to
the fact that the field calculations were made assuming the weir was
sharp-crested (a best available assumption since broad-crested weirs
must be individually calibrated).

-------
B-6
       Alternatively, the Company's weir/flow recorder installation may not be
       accurate, and the data being generated may not be within the +_ 10%
       accuracy range required by the EPA.
       Sampling Techniques

            The Company obtains daily composite samples of the Outfall  001
       effluent with a De Zurik piston type automatic sampler.  Due to  the
       physical construction of this unit,  it is not certain whether accurate
       suspended solids samples can be obtained through the strainer-type slits
       of its inlet.  Also, the De Zurik sampler is configured to obtain a flow
       proportioned sample based on the depth of flow in the wastewater channel.
       The Company's sampler was designed to be used with a sfarp-crested
       rectangular weir and may not be obtaining a  true flow proportioned
       sample wit'i the existing broad-crested weir.

            The sample obtained by the De Zurik sampler is not stored under
       refrigerated conditions during the compositing period.   It is collected
       in a metal  pot which is exposed to the ambient temperature of the samp-
       ling shed.   This deviation from EPA  standard  procedures could signifi-
       cantly affect the BOD,- and TSS data  obtained  from these samples.   At
       elevated temperatures the samples would tend  to degrade and the  sample
       data would  be lower than if proper refrigeration techniques were  employed.
       Analytical  Techniques

            A major  deficiency  noted  in  the Company's analytical techniques  is
       that  the  BOD,,  samples  are  not  set-up for  incubation within  the 6-hour
       time  period recommended  by the EPA.  The  Company uses the contract
       laboratory  services of                                       for the
       BODj.  analyses.  The daily  composite BOD^  samples are acidified and

-------
                                                                          B-7
 stored  in  a  refrigerator at the mill.  On Mondays and Thursdays they are
 sent  via commercial parcel delivery service in unrefrigerated-containers
 to      .   The Company could not produce any corroborative study data to
 indicate that these deviations from standard holding times and preser-
 vation  procedures do not adversely affect the quality of the BODr data
                                                                0
 generated.  Also, nc     or EPA approval of these deviations could be
 produced.

     Company personnel do not analyze replicate or blank samples during
 the TSS tests.  They also do not routinely participate in EPA or State
 quality assurance programs.  Results supplied by Company personnel for
 the TSS check sample left with them by the NEIC inspectors were within
 acceptable limits.  The results of the TSS analyses conducted by both
 the Company and the NEIC on the splits of the Company's daily composite
 sample for October 27, 197/ were essentially identical.  Both the check
 sample and split sample results indicate that the Company personnel  are
 accurately performing the TSS analyses.
     Analytical procedures used by      Laboratories for the
                                                                w
analyses were judged to be acceptable by the NEIC inspectors.  A portion
of the October 26, 1977 effluent composite sample was spiked by the NEIC
inspector with a quantity of a quality control check sample, and sent
along with the unspiked sample to      for analysis.  The data results
returned from the laboratory indicated a 94% recovery of the calculated
spiked value, an acceptable result.


Operation and Maintenance

     It did hot appear during this inspection that the wastewater treat-
ment operations were being optimized, i.e. the visual quality of the
effluent being produced was below that normally anticipated from a
comparable treatment system.  Several factors may contribute to this

-------
B-8
        lack of optimization.   Company  personnel  have  had  less  than six months
        experience operating  the  biological  secondary  system.   There are only
        three individuals  involved  with the  operation  of the  facility and  these
        individuals must also  perform quality  control  functions  for the paper
        mill.  Maintenance of  the weir  in  the  primary  clarifier  was found  to be
        sorely lacking.  Debris accumulated  on the weir and misalignment of the
        unit contribute to short  circuiting  in the clarifier  unit  and additional
        solids loading on  the  secondary unit.   Lastly, certain  design decisions
        (e.g. final  settling  tank weir  configurations, lack of  scum removal from
        the  secondary plant,  return of  sludge  dewatering centrate  directly to
        the  secondary plant,  etc.)  appear  to present a physical  ceiling on the
        quality of effluent which can be produced.


        NPDES Permit Compliance

             The Company's self-monitoring data indicate that since July 1, 1977
        when the new permit limitations went into effect,  there  have been  no
        violations of the  average or maximum daily limitations  for the permitted
        effluent parameters.   Daily average  values for quantities  of total
        suspended solids and BOD5 discharged have been 38% to 88%  and 11 to 65%,
        respectively, of the quantities allowed under  the  permit.  The higher
        values were associated with the biological plant start-up  period.  The
        plant appears to be stabilizing with time.

             As  discussed  above under Flow Monitoring, Sampling  Techniques, and
        Analytical  Procedures,  several  deficiencies were noted during this
        inspection which can adversely  affect  the quality  of the self-monitoring
        data being generated by the Company.   Although the Company's self-
        monitoring data indicates that  the effluent being  discharged at Outfall
        001  is well  within the permit limitations, the accuracy  of this data is
        suspect  and  ft .is  therefore not possible to determine the Company's
        degree of compliance with the flPDES  permit requirements.

             The Company does  appear to have met all of the compliance dates
        stipulated  in the  permit.

-------
                                                                         B-9
                            RECOMMENDATIONS
     The following measures are recommended  to correct  the  deficiencies
noted during this inspection:

     1.    The design and installation of the rectangular weir unit and
          flow recording device located at Outfall  001  should be
          evaluated.  The weir unit as it is currently  installed  is not
          sharp-crested.  If it is found that the flow  recorder and
          composite sampling device being used at this  location were
          designed to be used  with a sharp-crested  weir, a  new sharp-
          crested weir unit should be installed and the flow  monitoring
          and sampling devices accurately adjusted  for  the  new weir.

     2.    Once item 1 above is accomplished, a series of tests should be
          run to prove that the existing De  Zurik sampling  device  can
          accurately collect total suspended solids samples from  the
          wastewater channel.   Corroborative grab sampling  at the  weir
          discharge could be used  for this purpose.

     3.    The sample collection container should be refrigerated  or
          iced so that the sample  is held at 4°C during the compositing
          period.

     4.    The BOD5 sample holding/preservation procedures should  be
          revised to ensure that the samples are held at 4°C  during the
          time period between  when the samples are  collected  and when
          they are set up for  incubation.  The samples  should also be
          set-up for incubation within 6 hours after they are collected.
          These requirements may dictate that the BOD5  analyses be con-
          ducted on-site.   Alternatively,  tests should  be conducted to
          prove that the current BOD5 sample holding/preservation  pro-
          cedures yield accurate data.

-------
B-10
            It should be noted that the Company personnel  stated  during  this
       inspection that the     has given their approval  to the non-refrigerated
       sample collection technique and the current methods of holding/preserving
       the BODr samples prior to analyses referred to in items 3  and 4 above.
       However, no documentation could be produced to substantiate this  claim.

            Although not specifically required by the NPDES permit,  it is
       further recommended that a laboratory quality control  program be  im-
       plemented including the analysis of replicate total suspended solids
       samples and the use of blanks in these analyses.   Routine  participation
       in EPA and/or State check sample programs is also recommended.

-------
                                                                                B-n
             COMPLIANCE MONITORING  EVALUATION  REPORT
                         Date: 10/27/77
                                ignT)
                         Time 7 :1 z^f

                         Region
       ,-ACILlTY
       NAME
      COU.JTY
      Responsible Official
      NPDES Permit No.
LOCATION
MUNICIPALITY
Title
Permit Expiration Date
STATE
Telephone Ho.
Receiving Stream
Inspection Attendees
           Affiliation
      William Abbott
      David  Brooman
    USEPA-flEIC
    USEPA-NEIC
Type of Facility and General  Process  Description
     The Company manufactures about    tons/day of paper napkins  from
     reclainied  fiber.   There are                        paper machines
     at this mill,  one a     ton/day machine and the othtr a     ton/day
     unit.  Only the     ton/day unit was operating during this  inspection.
     The larger machine was  down for scheduled maintenance.

     The majority of the  pulp used at this mill is manufactured by de-
     inking printed broke.    Pulp produced from the broke undergoes
     several washing,  screening,  and  bleaching operations before  being
     used as feed to the  paper machines.   Polyethylene fiber material
     removed in the broke/pulp deinking and screening processes are used
     as supplemental fuels in the Company's boilers.

     The Company has instituted  an extensive water recycle/reuse  program
     at the mill to decrease  the  volume of wastewaters being discharged
     from the facility.   The  reuse program is discussed elsewhere in
     this report.
FACILITY EVALUATION
( 1)
(2 )
(4 )
1.
2.
3.
Records and Reports
Operations and
Maintenance
Sarcoling Procedures
(4)
(2)
if!
4.
5.
6.
7.
1 = Satisfactory
2 = Unsatisfactory
Flow lleasurenents
Laboratory Procedures
Sludge Disposal Practices
Alternate Power
(1)8.
<3>9-
3 = N.A.
4 = Undeterrr.ined
Unathorized Discharge
Other

-------
                                                                                                       33
                                                                                                        I
                                                                                                       IN3
WOES Permi
Outfall
No.
001
t Monitoring Requi
rements
Source of Parameter
Wastewater
Effluent from
wastewater
treatment
facility
serving
paper makipg
operations*
BOD,-
b
TSS
PH
Flow
(Effective
Quantity
Avq. Day
kg/day (Ih/day)
250(550)
300(660)
)
Limitations
Quantity Concentration
Max. Day Avg. Day
kn/day (Ib/day) mq/i
500(1100)
600(1320)
(6.0 to 9.0 units
range)
Monitoring
Frequency
Daily
Daily
Daily
__*
Sample
Tyne
24 hr. Compos it
24 hr. Compos il
Grab
__*
* _
The permit does not specify a monitoring frequency or procedure for flow
 after                   However, the permit conditions prior to this
 date were for continuous flow monitoring.  Apparently, this discrepancy
 was due to a typographical error.  The company does have contiuous flow
 monitoring equipment.

-------
                                                                          B-13
Description of llastewater Treatment Facilities:

     Since the early 1970's the Company has been involved in a program
designed to maximize recycle/reuse of wastewaters generated in the
deinking, pulp preparation and paper machine operations, and thus reduce
the amount of wastewaters which are ultimately discharged from the mill.
Initial stages of this program concerned the segregation of the deinking
and paper mill wastewaters.  Additional screening equipment was installed
to allow the segregated deinking wastewaters to be chemically treated,
settled in a 70 ft. diameter clarifier, and essentially totally recycled
in the process.  White water from the paper machines are re-used exten-
sively as dilution waters for the broke pulp, in the paper machine
showers, and as make-up water elsewhere in the processes.  The Company
has been successful in significantly reducing the wastewaters discharged
from the mill.  Currently, only 60-702 of the pre-closeup wastewater
volume is being discnarged.

     Excessive white water produced at the paper machines which cannot
be recycled and other miscellaneous wastewaters produced in the processes
are discharged to the Company's wastewater treatment facility which is
shown schematically in Figure 1.

     The wastewaters are pumped from the mill and first enter a 40 ft.
diameter primary treatment clarifier unit.   Polyelectrolyte is added to
the wastewater at the influent well of this clarifier to aid in the
precipitation of solid materials.   Sludge accumulated in the clarifier
can be handled in two alternate manners.   It can be pumped directly to
the 70 ft.  diameter clarifier mentioned above,  collected and thickened
in this unit and then puinped along with the 70 ft.  clarifier sludge to
the sludge  dewatering facilities  discussed  later.   This is the normal
operating mode.  In the alternate  mode, sludges from the 40 ft.  and 70
ft. clarifiers are pumped directly to the sludge dewatering facilities.

-------
B-14
           Effluent from the 40 ft.  clarifier is  routed  to  the  first  stage  of
      a two-stage                activated  sludge system.   The  wastewater  is
      combined with the  first stage  return  sludge and  aerated in  an 8000
      gallon aeration tank for approximately  1.4  hours.   Nutrients  in the  form
      of gaseous ammonia and phosphoric  acid  are  added to the primary clarifier
      effluent to maintain a BOD:M:P ratio  of 100:3.0:0.5.   The first stage
      unit's aeration system is operated so as  to maintain  a dissolved oxygen
      concentration in the mixed liquor  of  0.5  to 1.0  mg/1  and, hence,  promote
      the growth of bacteria in this stage.

           The mixed liquor from the first  stage  aeration enters  a  163,000
      gallon capacity, rectangular settling tank  through a  common-wall  diffuser.
      Sludge is removed  from the tank by siphon pipes  supported on  a  bridge
      mechanism whicn traverses the  length  of the tank.   The sludge is trans-
      ported by a channel  to a sump.   From  here it is  recycled  by airlift
      pumps to the first stage aeration  basin (return  sludge) or  wasted and
      combined with sludge from the  70 ft.  diameter clarifier for final sludge
      dewatering.   Scum  which accumulates in  the  settling tank  is skimmed  by
      mechanisms on the  traveling bridge, collected and  introduced  back into
      the return sludge  channel mentioned above.   There  is  np_ discrete scum
      collection/disposal  system.

           Effluent from the first stage settling tank is collected in two
      sets of double in-board weirs  which traverse the length of  the  tank
      parallel  to the direction of.flow.  The first stage effluent  is fed
      to the second stage  biological  unit.  This  stage is essentially identical
      in design to the first stage with  the only  minor differences  being  in
      unit volumes and the following operational  parameters.  The dissolved
      oxygen concentration in this stage is maintained at 2.0-3.0 mg/1.  The
      higher dissolved oxygen level  plus a  reduced GOD,-  loading rate  promotes
      the growth of protozoa in this stage.   Sludge wasted  from the second
      stage is  returned  to the first stage  aeration unit.

-------
                                                                         B-15
     The effluent collection weirs on the second stage settling tank are
identical to those of the first stage.  The weir design appears to
encourage short circuiting of solids to the tank effluent.  This short
circuiting is less critical in the first stage since it is followed by
the second stage units.  However, any solids lost due to short circuiting
in the second stage are discharged directly to the receiving waters.

     The effluent from the second stage settling tank flows by gravity
to the Company's effluent sampling and flow monitoring station at Outfall
001 and then a short distance later is discharged directly into
           Backwash water from the Company's process water filtration
plant is combined with the treated wastewater just prior to the sampling
station.

     Sludge dewatering equipment at the facility consists of two centri-
fuges operated in parallel.  Feed to the centrifuges can be combined
sludges from the 70 ft. and 40 ft. clarifiers plus waste activated
sludge -from the biological systems (normal mode) or separated sludges
from the 70 ft. and 40 ft. clarifiers plus the waste activated sludges
(alternate mode).  In the normal mode, the centrate from the centrifuges
is routed to the effluent launder of the 40 ft. clarifier and then
directly to the                unit.  In the alternate mode the centrate
is routed to the influent well of the 40 ft. clarifier and receives
primary treatment.  Sludge cake produced by the centrifuges is hauled to
a Company owned landfill  where it is buried.

     The Company is currently reworking an existing earthen basin located
between the mill and              .   The reworked basin will  have an
impervious clay liner and will be used as an emergency spill  basin.  The
mill proper has no back-up electrical  power system; hence, the pumps
which transport wastewater to the treatment plant and recycle much of
the process water would be inoperable during a mill power outage.   In
this event, uastewaters resulting from basement flooding would be

-------
B-16
       diverted by gravity to the emergency spill  basin.  The contents of the
       70 ft. clanfier would also be diverted to this basin whenever the
       clarifier is taken out of service for major maintenance.  There will  be
       no direct discharge from the emergency basin to            The basin
       contents will be pumped to the head of the treatment system's primary
       unit using portable pumping equipment.

-------
                                                              B-17
                    A v-w_i j 11"   .  ,
                       Activate ch
-------
B-18

      Average  Treated  Has tewater  Flow  of Faci1ity?    Approximately 1.0 MOD


      Averaoe  Design F1ow  of Mastewater  Treatment Facility:   1.0 MGD	
      Alternate  Electric  Power  Source  fXX"' Dual  Feed   /  / Renerator /  / None


      	~~7 Other (Explain):



      Adequats Alarm System  for Power or  Equipment  Failures? J? Yes /~7 No


      If  no, explain:
     Observed Appearance of Effluent, Receiving Stream or Drainage '-/ay:

        The effluent at Outfall 001 was milky white, quite turbid and

        ocassionally had large paper solids in it.



        The effluent plume discolored the receiving waters for a considerable

        distance,
     Consulting Engineer Retained or Available for Consultation on Operating

     ana Maintenance Problems? /v~~' Yes  /~~~ No
     	  LJ^j      L-J
     If yes, who?
     Are lagoons Used  in Treatment Process?  ,/x- Yes   /==t No

     If yes, what  is treatment function?   jhe Company has an emergency holding

        lagoon which can be used  to collect excessive spills in the mill basement,

        used for clean-out of treatment facility units, etc.

          Are lagoons  lined?  QJ Yes  /~7 No  If yes, what material?

                   The  lagoon will be clay lined
          Condition of lining?
                               The lagoon was still under construction

          Condition of dikes?
                               Still under construction.

          Any seepaoe  evident?  (__/ Yes   • x/ No

-------
                                                                              B-19
NOTATIONS 8Y EVALUATOH
OPEq*-|C'l .'.O VAlriTE.-: asCE PPCOLC"! EE *ICI ENCI ES
C'-'CC" E * C •* 3*" "-E •••OLL ?«INC I'E^S I'. TE"*.'S OF Tr-ClP FSTlMftTFD ASPERSE * e *" E C T OS T n E PERFORMANCE O e- • ^ e- pt_..- -
IT EM
S~ •' • f C2^ = t. :"E"T
"EIIO.1.1- =!. TT»IM'IG
c?i"J"" o : UOC:T
L^'J'ATC3 ' ;3'.T=OL
I'.STTJ"C IT-TIC'i
l'.2'wfT=l-'. «SST£ [ij /\
P-ANT CuSCL£5£MCE
EC'JIS";'.T c»!LUr1E
THE»Tli/C«JT PnOCECSES
SLUOIE HANDLING
AN? PROCESSING
ECUIPMEH- MilNTENiNCE
SP*Pi '-'iRTS 1 IVE'iTOa Y
PO*En FAILLf=;i


M.JOS
X


X
X





v




h>iNOR















NONE

X
y



X
X
\
X

x
X


ITEM
O.-ERLOiOS 't.pc;
MVDR »ULIC
PCRIOCIC
CONTINUOUS
ORC ANIC
PERIODIC
COrtTINUOUS
OVE°LO^O C AUSEIS)
Unit underdesigned
ind/or mill water recycle
nroaram has not been
maximized


OTHER
Treatment Plant Design
MA J30
X
X

X




X





X
MIISC^ '.O'.£


X

X
Y
V





1
1

DESCRIBE BRIEFLY TrlE MAJOR PROBLEMS IN3ICATCD ABOVE
      1. Staff Complement:  The wastewater treatment staff is also responsible
      for product quality control functions in the mill.   It did not appear
      during this inspection that the existing 3 man staff can adequately
      perform both functions.
      2. Laboratory Control:  Problsms were noted with the Company's sample
      preservation and handling procedures as discussed elsewhere in this report
      3. Instrumentation:  Problems were noted with the weir installation at
      Outfall 001 as discussed elsewhere in this report.
      4. Equipment Maintenance:  Problems were noted with maintenance of the
      primary-clarifier unit as discussed later in this report.
      5. Hydraulic Overloads:  The primary clarifier is underdesigned for the
      existing flow rates.
      6. Treatment Plant Design:  The weirs on the final  clarifiers of the
                     biological system encourage unit short circuiting due
      to their orientation and location.  Also, there is  no way to physically
      remove scum from the biological system.  Scum which is collected from
      the final  clarifiers is returned to the aeration system in the
      return sludge stream.

-------
B-20
                            SELF-MONITORING
      On  the  foil ovn' nq  items, code 1 = yes, 2 = no, 3 = undetermined,

                             4 = not applicable.

      RECORDS AND  REPORTS

      T~ 1.  Prooerly  maintained records of date, exact place and time of
             sampling.

     £\7 2.  Properly  maintained records of the dates samples were analyzed.

     /T" 3.  Prooerly  maintained records of who performed the analyses.

        _  4.  Properly  maintained records of the analytical techniques and
             methods used.

      17 5.  Properly  maintained records of the results of analyses.
       / 6.  Records maintained for a minimum of three years including all
             original strip chart recordings (continuous monitoring instru-
             mentation calibration, maintenance records).

     f~-\~/ 7.  Plant operating records kept including operating logs of each
             treatment unit.

     /j7 8.  Results of sample analyses correctly calculated and recorded.

     f~\/ 9.  Self-monitoring frequency and oarameters conform to permit
             requirements.

     ,'J7 10- Laboratory records consistent with DMR data.

     /"a/ 11- Records maintained of major contributina industries using
             publicly owned treatment works.

        ' 12.  Records maintained of major contributing industries'  compliance/
              non-compliance status.

     /j7 13.  Quality assurance records kept including spiked samples, laboratory
              equipment calibration, etc.

     Other Comments on Records and Reports:

-------
                                                                           B-21
 FLO'-.'  MEASUREMENT NOTE:  l=Yes, 2=ilo, 3=Undetermined. 4=Not applicable


 /j3   1.   Primary measuring  device  (weir,  parshall  flume,  magmeter,  etc.)
          properly  installed.
                              Type  of device    See note below  .	

  ~Y   2.   Calibration  frequency adequate.
                              Date  of last calibration    Monthly	

 _'~]   3,   Flow measurement records  properly maintained.
                              Method (automatic, manual, etc.) Automatic

 /~3   4.   Primary flow measurement  device  properly  operated  and maintained.

/~J   5.   Secondary  instruments (totalizers, records, etc.)  properly
          operated and maintained.

 /""I   5.   Flow measurement equipment adequate to handle expected  ranqes  of
          flow rates.

 OtherComments on Flow Measurement:
        The Company  monitors effluent flow at Outfall 001 with an 18"
   standard suppressed rectangular  weir  installation.  Depth of flow
   over the weir  is  measured by a float  in a stilling well connected to
   a  Foxboro Model  40  flow recorder.  The  problems  with the  instaMation
   are that the weir is  not  sharp crested  and the approach velocity  in the
   weir channel appears  to be excessive.   The weir  plate appeared to be
   constructed out  of  angle  iron stock.  The weir crest measured  approxi-
   mately- 2". The Company had no documentation to  indicate  that  the weir
   had been installed  and calibrated as  a  broad crested unit.
        Field measurements made by  the NEIC inspection team  indicated that
   the flow recorder unit read approximately 111 low at about 1200gpm and
   36% low at about  BOOgpm.   These  flow  rates were  the maximum and average
   values respectively experienced  on this day.  The field calculations  were
   made assuming  the weir was sharp crested.
   SAMPLING

/1~7 1.  Locations adequate  for representative samples.

 Xj7 2.  Parameters and frequency agree with permit.

/y 3.  Method of sample collection:  Hanual  '"j
                                      Automatic jf7

 /'~ 4.  Sample collection method is adequate.  See  note 1  on next page.

/jj~ 5.  Water intake sampled and analyzed, if required by permit.

/""]" 6.  Additional  monitorinq and analyses beinq performed more
        frequently than required by permit.

-------
            1  = Yes, 2 = No, 3 = Undetermined, 4 = Hot applicable
B-22     __
        	2   7.  '-/hen answer to No. 6 is yes, results are beinn reoorted in
                 permittee's Discharge Monitorina Form (EPA Mo. 3320-1).

        /~  8.  When necessary during compositinci, samples are prooerly iced.

        , ~  9.  Proper preservation techniques used.  See Mote  2 be.1ow

        _j~ 10.  Flow proportioned samples obtained where required by nermit.
         	                   See  Note  1  below.
        •  2  11-  Sample holdina times prior to analyses in conformance with 40
                 CFR 136.3 regulations.   See  note  3  below.

        Other  Comments on Sampling Techniques:
        l)The Company  uses  a  DeZurik  Automatic Sampler  and  Flow Meter, Model
        SN34450,  to  obtain  a  24-hour  composite sample from  behind  the weir
        at Outfall 001.   The  sampler  has  a  series of  vertical slits immersed
        in the  wastewater stream through  which the  sample enters  the unit.
        These slits  may  act as  a strainer thus preventing the unit from obtain-
        ing a representative  TSS sample.   The  DeZurik sampler has  a physical
        configuration  which permits  it  to obtain a  flow proportioned sample,
        based on  the depth  of flow in the wastewater  channel.   The Company's
        unit was  designed to  be used  with a  sharp-crested rectangular weir and
        may not be obtaining  a  true  flow  proportioned sample with  the broad-
        crested weir actually installed at  Outfall  001.  2}The  composite sample
        is not  refrigerated during the  compositing  period.  It  -!s  stored at the
        ambient temoerature of  the sampling  shed.   3)The BOD.- samples which are sent
        tc a contract  lauoratory for  analysis  are not analyzid  within the 6-hour
        holding time recommended by  the EPA.
        LABORATORY PROCEDURES:
        /2/ 1. . EPA  approved  analytical  testing orocedures  used (40 CFR  136.3).

        /_2_-' 2.  If alternate  analytical procedures  are  used, proper approval
               has  been obtained.

        fij 3.  Parameters  other than those  required  by the permit are analyzed.

        /~\7 4.  Commercial  laboratory utilized.
            (For BODj. analysis only)         Name	
                    3                         Address_

        /~ 5.  Commercial  laboratory State  certified.

        /j7 6.  Satisfactory  calibration  and maintenance of instruments and
               equipment.

        /P 7.  Quality  control  procedures used. see  note 1 on  next paae

        /?/ 8.  Duplicate samples  are analyzed. 	%  of time.
                      See  Note 1.

-------
     1  = Yes,  2  = No,  3  =  Undetermined,  4  =  Not  applicable               B~23

      9-  Spiked samples are used.      	% of time.

 /j~ 10.  Laboratory records properly maintained.

 /j~" 11.  Laboratory employees  qualified.

 General Comments on LaboratoryProcedures:
1.  Company personnel  do not run duplicate and blank TSS analyses.
These quality control  procedures should be implemented.
2.  If the Company opts  to run  BOD^ analyses at the plant rather
than send them to a contract laboratory, a quality control  program
should be established for these analyses also.
3.  All analytical procedures observed at the      Laboratories
appeared to be satisfactory.
 Resultsjjf NEIC Quality  Control Check  SamplesAnalyzed  byLaboratory
The company reported a value-of 42 mg/1 TSS (true value 51  mg/1)
on a check sample supplied by inspection team.   The value obtained
is acceptable.

A portion of the effluent composite dated 10/26/77 was spiked with
10ml of a quality control check sample (5840 mg/1 as a concentrate)
and delivered to      Labs along with the unspiked composite.  Results
yielded 94% recovery, which is acceptable.
Results of Cgmpany-EPA NEIC Split^ Sample Analyses:

                                                    The effluent
composite of 10/27/77 was split and analyzed for TSS by both EPA and
Company personnel.  The  EPA result was 40 mg/1; the Company value was
42mg/l.  These values are essentially  identical.

-------
B-24         1 = Yes,  2 = flo,  3 = Undetermined,  4 = Mot applicable

        OPERATION  AND  MAINTENANCE


             1.  Standby pov/er or other equivalent provisions provided.

        ~  2.  Adequate alarm system for pov;er or equipment failures available.

        ~'  3.  Reoorts on alternate source of power sent to EPA/State as
                required by permit.

        '"T  4.  Sludges and solids adequately disposed. Sludge  disposal  site
        	       was not observed.
       	2   5.  Any non-permitted discharges.

             6.  Any by-passing since last inspection.

             7.  Regulatory agency notified of by-passing.
                             Dates                ,
       ,_2  8.  Any effluent limitations violations experienced.

       ,~  9.  All treatment units in service.

       /iTT 10.  Any hydraulic and/or organic overloads experienced.

       _2,  11.  Treatment facility properly operated and maintained.  See  notes  belo1..

           12.  Consulting engineer retained or available for consultation on
              . operation and maintenance problems.

           13.  Preventive maintenance records files kept.

           14.  Qualified operating staff provided.

           15.  Established procedures available for training new operators.

           16.  Files maintained on spare parts inventory,  major equipment
                specifications,  and parts and equipment suppliers.

         .  17.  Instructions files kept for operation and maintenance of each
                item of major equipment.

       Other Comments on Operation and Maintenance
        It was apparent during this inspection that the wastewater  treatment
        system was not being operated  in  an optimal mode and  that proper main-
        tenance was.not being administered to the treatment equipment.   These
        judgements are based on  the observed quality of the effluent being
        produced as well as visual observations of the treatment processes
        and general housekeeping in the treatment plant area.   Specific  points
        noted include:  1) The 40 ft.  diameter primary clarifier's  effluent
        was very turbid and appeared to contribute an inordinate TSS load
        to the secondary treatment units.  The primary clarifier unit is

-------
     1  =  Yes,  2  =  Mo,  3  = Undetermined, 4 = Not applicable               B"25

obviously hydraulically overloaded.  However, the effluent weirs were
badly out of  level and clogged with debris and obviously contributed
to short circuiting in the clarifier.  2) Although the Company is
reportedly using polyelectrolytes to improve the solids removal  in the
primary clarifier, there was no evidence that jar tests are routinely
run  to optimize polyelectrolyte addition rate.  Also, the poly-
electrolyte is added directly to the influent well of the clarifier.
It is doubtful whether optimum mixing of the polyelectrolyte and waste-
water occurs  at this location.  3) The centrate from the sludge  de-
watering processes are introduced directly into the primary clarifier
effluent launder.  Any solids contained in this centrate are there-
fore passed on directly to the secondary treatment units.  4) General
housekeeping  at the treatment facility was poor.  Of particular  note
were the sludge dewatering and sludge handling facilities.

It appears as though the majority of the operations and maintenance
problems noted are directly related to an inadequately sized waste-
water treatment staff as discussed elsewhere in this report.
PERMIT VERIFICATION

/1   1.  Correct name and mailing address of permittee.

£a/  2.  Facility as described in permit.

/j7  3.  Principal product or products, and production rates conform
         with those set forth in permit application.

     4.  Treatment processes as described in permit application.

     5.  Notification given to EPA/State of new, different or increased
         discharges.

     6.  Accurate records of raw water volume and correct intake
         location.

1  }   7•  Number and location of discharge points as described in permit,

/T1  8.  Correct name and location of receiving waters.

-------