EPA-650/2-75-057-k

October 1975            Environmental Protection Technology Series
                                          OF FLUE  GAS
                       DESULFURIZATION  SYSTEMS
              MOHAVE STATION, SOUTHERN CALIFORNIA EDISON CO.
                                                       UJ
                                                       O
                                        U.S. Environmental Protection Agency
                                         Office of Research ,ind Development
                                               Washington, D.C. 20460

-------
                                       EPA-650/2-75-057-k
                   SURVEY
               OF  FLUE  GAS
   DESULFURIZATION  SYSTEMS
MOHAVE  STATION,  SOUTHERN  CALIFORNIA  EDISON CO.
                       by

          Gerald A. Isaacs and Fouad K. Zada

          PEDCo-Environmental Specialists, Inc.
              Suite 13, Atkinson Square
                Cincinnati,  Ohio 45246
            Contract No. 68-02-1321, Task 6k
                ROAP No. 21AXC-130
             Program Element No. 1AB013
          EPA Project Officer:  Norman Kaplan

       Industrial Environmental Research Laboratory
         Office of Energy, Minerals, and Industry
       Research Triangle Park, North Carolina  27711
                   Prepared for

       U.S. ENVIRONMENTAL PROTECTION AGENCY
           Office of Research and Development .
               Washington, D. C. 20460

                   October 1975

-------
                      EPA REVIEW NOTICE

This report has been reviewed by the U.S. Environmental Protection
Agency and approved for publication.  Approval does not signify that
the contents necessarily reflect the views and policies of the Environ-
mental Protection Agency, nor does mention of trade names or commer-
cial products constitute endorsement or recommendation for use.
                  RESEARCH REPORTING SERIES

Research reports of the Office of Research and Development, U.S. Environ-
mental Protection Agency, have been grouped into series. These broad
categories were established to facilitate further development and applica-
tion of environmental technology.  Elimination of traditional grouping was
consciously planned to foster technology transfer and maximum interface
in related fields.  These series  are:

          1.  ENVIRONMENTAL HEALTH EFFECTS RESEARCH
          2.  ENVIRONMENTAL PROTECTION TECHNOLOGY

          3.  ECOLOGICAL RESEARCH

          4.  ENVIRONMENTAL MONITORING

          5.  SOCIOECONOMIC ENVIRONMENTAL STUDIES

          6.  SCIENTIFIC AND TECHNICAL ASSESSMENT REPORTS

          9.  MISCELLANEOUS

This report has been assigned to the ENVIRONMENTAL PROTECTION
TECHNOLOGY series.  This series describes research performed to
develop and demonstrate instrumentation,  equipment and methodology
to repair or prevent environmental degradation from point and non-
point sources of pollution.  This work provides the  new or improved
technology required for the control and treatment of pollution sources
to meet environmental quality standards.
This document is available to the public for sale through the National
Technical Information Service,  Springfield,  Virginia 22161".
                 Publication No. EPA-650/ 2-75-057-k
                               11

-------
                       ACKNOWLEDGMENT




     This report was prepared under the direction of Mr.



Timothy W. Devitt.  Principal authors were Dr. Gerald A.



Isaacs and Mr. Fouad K. Zada.



     Mr. Wade H. Ponder, former EPA Project Officer, had



primary responsibility within EPA for this project report.



Information and data on plant operation was provided by Dr.



Alexander Weir, Jr., Southern California Edison Company,



during and subsequent to the survey visit.  Mr. Charles D.



Fleming was responsible for editorial review of this report.



     The authors appreciate the efforts and cooperation of



everyone who participated in the preparation of this report.
                              111

-------
                      TABLE OF CONTENTS



                                                       Page




ACKNOWLEDGMENT                                         ill




LIST OF FIGURES                                        vi




LIST OF TABLES                                         vi



SUMMARY                                                vii




1.0  INTRODUCTION                                      1-1




2.0  FACILITY DESCRIPTION                              2-1




3.0  FLUE GAS DESULFURIZATION SYSTEMS                  3-1




     3.1  Process Description                          3-1




     3.2  Installation Schedule                        3-6




     3.3  Cost Data                                    3-8




4.0  FGD SYSTEMS OPERATING HISTORY                     4-1




     4.1  Performance Test Run                         4-1



APPENDIX A  PLANT SURVEY FORM                          A-l

-------
                       LIST OF FIGURES
Figure

 3-1



 3-2


 4-1
A Simplified Sketch of the Vertical TCA
Type FGD System Which is Installed
on Mohave 1

A Simplified Side View of the Horizontal
FGD Module Installed on Mohave 2

SO? Removal vs L/G Ratio-170 MW Horizontal
Module
Page

3-3



3-5


4-5
Table

 2-1


 3-1


 4-1


 4-2
                       LIST OF TABLES
Pertinent Data on Plant Design, Operation
and Atmospheric Emissions

Summary of Pertinent Data for the S0~
Absorber Modules

Comparison of Operating Time Parameters
Vertical Module - Mohave - SCE

Comparison of Operating Time Parameters
Horizontal Module - Mohave - SCE
Page

2-3


3-7


4-3


4-5
                             VI

-------
                           SUMMARY





     Two prototype sulfur dioxide absorber modules were



installed in 1973 at the Mohave Generating Station of



Southern California Edison Company.  A vertical module rated



at 170 MW was installed to treat a 450,000 scfm portion of



the flue gas from Unit 1 and a horizontal module, also rated



at 170 MW, was installed to treat a similar flue gas portion



from Unit 2.  Units 1 and 2 are identical boilers each



having a maximum net continuous generating capacity of 790



MW.  Each unit burns 390 ton/hr of pulverized coal at full



load.  The heat content of the coal is about 11,500 BTU/lb.



The ash and sulfur content are approximately 10 and 0.4



percent, respectively.



     The vertical absorber was in the process of starting up



when it was damaged by a fire on January 24, 1974.  The unit



was subsequently rebuilt and was restarted for test opera-



tions which were conducted from November 2, 1974, to April



1975.  The unit was modified for additional tests which were



completed July 2, 1975.



     The horizontal module was operated from November 1,



1973, to January 16, 1974, for shakedown purposes.  During a



test program from January 16, 1974 to February 9, 1975, the
                              vii

-------
unit operated for 5927 hours in various test modes.  This



module has been dismantled and removed from the station.



     Particulate and SO- removal efficiencies varied with



the tests that were run.  The emission regulation for this



plant is 0.15 Ib/MM BTU for sulfur dioxide.  Both absorbers



are preceded by electrostatic precipitators operating at



98.2 percent efficiency, but designed at 97.2 percent



efficiency.



     The spent limestone slurry from the vertical absorber



is thickened in a clarifier, vacuum filtered or centrifuged,



and converted to aggregate at an on-site IU Conversion



Systems, Inc. plant.  The filtrate water is returned to the



absorber.



     The spent lime slurry from the horizontal module was



thickened in a clarifier and pumped to a disposal pond.



Calcilox, a sludge stabilizer manufactured by the Dravo



Corporation, was mixed into the thickened slurry before it



entered the disposal pond.  Supernatant liquor was pumped



back from the pond to the absorber.  This system operated in



a closed water loop.  Estimates of capital and annual operating



costs have not been published.



     Pertinent facility and FGD operational data are sum-



marized in the following table.
                            Vlll

-------
                SUMMARY OF FGD DATA - MOHAVE
  Identification
    Vertical
     module
      UOP
 Horizontal
   module
    SCE
Module rating, MW  (net)

Fuel

  Gross heating value, BTU/lb

  Ash, percent

  Sulfur, percent

Process



New or retrofit

Start-up date

Start of test program

Efficiency, %

  Particulates

  so2

Water make-up, gpm/MW  (net)

Sludge disposal
      170

     Coal

   11,500

       10

        0.4

  Wet limestone
 (lime alternate)


     Retrofit

 January 1, 1974

November 2, 1974



  Not available

  Not available

  Not available

 Converted to
 aggregate
    170

   Coal

 11,500

     10

      0.4

  Wet lime
(limestone
 alternate)

  Retrofit

November 1, 1973

January 16, 1974



 Not available

   75 - 98

 Not available

Stabilized in
sludge pond
                              IX

-------
                      1.0  INTRODUCTION




     The Control Systems  Laboratory of the U.S. Environ-



mental Protection Agency  has initiated a study to evaluate



the performance characteristics and degree of reliability of



flue gas desulfurization  (FGD)  systems on coal-fired utility



boilers in the United States.   This report on the Mohave



Generating Station of the Southern California Edison Company



is one of a series of reports on such systems.



     This report is based on information obtained during and



subsequent to a plant survey visit on July 24, 1974.



     Section 2.0 presents pertinent data on facility design



and operation including allowable SO- emission rates.



Section 3.0 describes the flue gas desulfurization system



and Section 4.0 analyzes  FGD system operating history.
                              1-1

-------
                  2.0  FACILITY DESCRIPTION





     The Mohave Generating Station, operated by Southern



California Edison Company (SCE), is located in Clark County,



Nevada, about ten miles north of the southern tip of Nevada.



The plant is situated in a sparsely populated 'desert area.



The Lake Mead National Recreational Area lies 20 miles north



of the plant', and the Fort Mohave Indian Reservation is 10



miles to the south.  The plant is jointly owned by the City



of Los Angeles Department of Water and Power, Nevada Power



Company, the Salt River Project Agricultural Improvement and



Power District and Southern California Edison Company.



     The station consists of two coal-fired generating



units, each rated at 790 MW (net).  The boilers are Combus-



tion Engineering, dry-bottom,  pulverized-coal-fired units.



Unit 1 was placed in service in 1970; Unit 2 in 1971.



     Low-sulfur coal is transported to the station from the



Black Mesa Mine via a 285-mile slurry pipeline.  Average



coal characteristics are 11,500 BTU/lb, 10 percent ash and



0.4 percent sulfur.  The maximum fuel s.ulfur content anti-



cipated for this station is about 0.60 percent,, correspond-



ing to a furnace outlet SO^ concentration of about 1.0



SO-/MM BTU.  The maximum S00 emissions allowed under the
                              2-1

-------
                       a
Clark County Regulation  is 0.15 Ib SO2/MM BTU input to the

boiler.

     Research-Cottrell electrostatic precipitators (ESP),

operating with an efficiency of 98.2 percent,  provides

primary particulate emission control for each boiler.

     The installation of five FGD modules on each boiler at

this station would be necessary to comply with the existing

Clark County regulations.  Module selection will be based on

the results obtained from the operation of the two experi-

mental test modules described in this report.

     Table 2.1 presents pertinent data on plant design,

operation and atmospheric emissions.
a On May 20, 1975 a new Nevada law became effective which
  prohibits the enforcement of the Clark County Air Pollu-
  tion Control regulations on the Mohave Generating Station
  until July 1, 1977 and requires the State of Nevada En-
  vironmental Commission to hold hearings prior to July 1,
  1976 for the purpose of reviewing all contaminant emis-
  sion standards applicable to fossil-fuel-fired steam
  generating facilities.
                              2-2

-------
         Table 2.1  PERTINENT DATA ON PLANT DESIGN,

             OPERATION AND ATMOSPHERIC EMISSIONS
Boiler identification number

Rated generating capacity, MW (net)

Average capacity factor, 1973

Served by stack no.

Boiler manufacturer

Year placed in service

Maximum coal consumption, ton/hr

Maximum heat input, MM BTU/hr

Stack height above grade, ft.

Flue gas rate - maximum, scfm @ 60°F

Flue gas temperature, °F

Emission controls:

  Particulate


  SO,
(treats 450,000 scfm of
each unit only)

S0_ emission rate:

  Allowable, Ib/MM BTU

  Actual, Ib/MM BTU
     1

    790
    2

   790
1
CE
1970
390
10,000
500
1
CE
1971
390
10,000
500
2,100,000  2,100,000

     270       270
   electrostatic
   precipitator
Vertical
absorber
 module
Horizontal
 absorber
  module
 0.15        0.15

    Not available
                              2-3

-------
            3.0  FLUE GAS DESULFURIZATION SYSTEMS





3.1  PROCESS DESCRIPTION



     In 0,971 and 1972 eight different pilot plant FGD



systems were tested at the Mohave Station.  At the con-



clusion of these tests SCE decided that two prototype FGD



modules should be installed at Mohave, each sized to handle



one-fifth of the gas flow from one of the generators.



Accordingly, a Universal Oil Products Company  (UOP) tur-



bulent contact absorber (TCA) vertical module was installed



on Unit 1 to operate using limestone, and a Southern Cali-



fornia Edison four-stage,  countercurrent, horizontal unit



was installed on Unit 2 to use a lime slurry.  Results of



the operational test programs for these two units will be



used to determine the type of full-scale system that would



be suitable for the station.  These results will also be



used to specify equipment for installation at the Navajo



Station to be constructed by the Salt River Project Agri-



cultural Improvement and Power District and possibly for the



Kaiparowitz Station of SCE.



Vertical Module



     Flue gas from the ESP on Unit 1 passes through a 5,500



horsepower booster fan before it enters the vertical module
                              3-1

-------
shown in Figure 3.1.  The UOP unit is designed to treat



450,000 scfm of exhaust gas.  The liquid-to-gas contacting



ratio (L/G) for the unit is 83 gallons of limestone slurry



per 1000 scf of flue gas.  The design gas velocity through



the unit is 12.6 ft/sec.  In its original configuration,



this unit was a four-stage turbulent contact absorber



(TCA).   The unit has-subsequently been modified for further



testing.  Electric power consumption for the TCA system



amounts to about 3 percent of the total generating capacity



of the station, whereas for the horizontal spray chamber



installation on Unit 2 the electric power consumption is



only about one-half as high (1.5%).



     As shown in Figure 3.1, exhaust gas from the Unit 1



boiler passes through an electrostatic precipitator and a



forced draft fan before it enters the TCA.  The gas flows



upward through the absorber, passes through a demister which



is washed continuously, and is reheated from 120° to about



175°F by a direct heat exchanger located in the exit duct.



The boiler supplies the steam for this heater.



     The rate of limestone addition to the FGD system is



equivalent to about 130 percent of the stoichiometric rate



required for reaction with sulfur dioxide in the gas.  Part



of the slurry from the circulation tank is diverted to a



clarifier for thickening.  The thickened sludge can be



dewatered either by a vacuum filter or by a centrifuge.  The



filtrate is returned to the hold tank, and the dewatered
                              3-2

-------
I
u>
                                                                              MOHAVE GENERATING STATION


                                                                          160 MW VERTICAL SCRUBBER SYSTEM
                       Figure 3.1   A simplified  sketch of  the vertical TCA type


                            FGD system which is installed on Mohave  1.

-------
sludge is hauled by truck to an on-site IU Conversion



Systems plant where it is made into aggregate.



     Limestone for the FGD system is purchased in ground



form from La Habra Products in Lucerne Valley, California.



     There are no limestone milling facilities on-site at



the present time.  Instead, finely-ground limestone is



stored in a 300 ton silo.  A slurry tank is provided for the



scrubbing system.



     Separate control rooms are provided for the horizontal



and vertical absorbers.



Horizontal Module



     Flue gas from Unit 2 passes through the ESP and through



a 1750 horsepower booster fan before it enters the hori-



zontal module shown in Figure 3.2.  The booster fan require-



ments for this module are less than for the vertical module



due to a decreased pressure drop through the absorber.  The



module, designed by SCE, was scaled up from a 1 MW pilot



unit previously tested by SCE.  Lime slurry is sprayed from



nozzles in the top of the scrubber perpendicular to the gas



flow.  There is no packing in this spray chamber module.



The module consists of four countercurrent stages with fresh



slurry contacting the gas having the lowest SO2 concentra-



tion.  The unit operates with an L/G of 20-40 gallons of



slurry per 1000 scf of flue gas.  The liquid recirculation



rate can be adjusted over a wide range.  The horizontal



module was designed to treat 450,000 scfm of flue gas.  The
                              3-4

-------
Ul

01
                                             FOUR SCRUBBER STAGES
                                                                                           HOT AIR
                                                                                          INJECTION
                 BOOSTER FAN
MIST ELIMINATOR
                             Figure  3.2   A simplified side view of the horizontal

                                   FGD module installed on Mohave 2.

-------
design gas velocity through the unit is 21.6 ft/sec.  Cleaned



flue gas passes through a demister which is washed inter-



mittently on both sides.  The gas is then reheated from 120°



to about 175°F by indirect heat exchange with hot air.



Ambient air is preheated to about 400°F and is mixed with



the cleaned gases as they exit from the module.  This



causes a 15 to 20 percent dilution of the flue gases.  The



boiler supplies the steam for this heater.



     The rate of lime addition to the FGD system is about



equivalent to the stoichiometric rate required for reaction



with sulfur dioxide in the gas.  Part of the slurry from the



circulation tanks is pumped to a thickener and the underflow



is then pumped to a lined pond, fixed with Calcilox supplied



by Dravo, and allowed to settle.  Supernatant water from the



pond is recirculated to the horizontal module.  The unit



operates on a closed water loop; the only water leaving the



system consists of water in the exit flue gas, water of



hydration in the gypsum product, and a small amount of water



(3% of total water leaving) evaporated in the sludge pond.



     The present goal is to produce a sludge that will



achieve a hardness sufficient to support a load of 2-4 tons



per square foot within three months.  Table 3.1 summarizes



operating design parameters and specifications for the two



FGD modules.
                            3-6

-------
            Table 3.1  SUMMARY OF PERTINENT DATA
                FOR THE SO2 ABSORBER MODULES
                                   Vertical
                                    module
                Horizontal
                  module
L/G ratio, gal./lOOO scfm
Superficial gas velocity,
  ft/sec

Equipment sizes, ft.
Equipment internals



Material of construction

     Shell

     Internals
    83
    12.6

 18 x 40
 x 90 high

 4 stages of
 ping pong
 balls
 rubber lined

polypropylene/
  inconel
 20 to 40 for
 each of four
 stages


     21.6

 15 x 30
x 60 long

 sprays
 various linings

    none
                              3-7

-------
3.2  INSTALLATION SCHEDULE



     Work on the horizontal and vertical modules of the FGD



system at the Mohave Power Plant was initiated in December



1972, and ground was broken in February 1973.  Start-up of



the horizontal unit was achieved on schedule November 1,



1973, but a major malfunction of the generating unit oc-



curred on November 9, so that the start of the test program



was delayed until January 16, 1974.  Start-up of the ver-



tical unit was January, 1974.  However during the last phase



of construction and start-up, on January 24, 1974, a fire



inside the module caused appreciable damage to the internal



rubber lining and other internals, and delayed start of the



test program on that unit until October 31, 1974.



3.3  COST DATA



     Data on the capital and annual operating costs of the



FGD installations at the Mohave Plant have not been re-



leased.
                              3-8

-------
             4.0  FGD SYSTEMS OPERATING HISTORY


4.1  PERFORMANCE TEST PROGRAM

     The initial start-up for the vertical module occurred

on schedule on January 1, 1974.  However, on January 24,

1974, the module sustained substantial damage from a fire of

undetermined origin.   The following repairs were made.

     1.   All internal structural members were replaced.

     2.   Deformed shell stiffeners were reinforced.

     3.  . Distorted wall plates were replaced.

     4.   Internal piping was repaired or replaced.

     5.   Damaged internals, including demister and grid
          sections, were repaired or replaced.

     6.   Structural distortions were corrected.

     7.   Access door flanges were straightened or replaced.

     8.   Structural reinforcement was added.

     9.   Reheater supports were added.

    10.   Shell was sandblasted and relined with neoprene,
          replacing chlorobutyl rubber that had been used
          originally.

    11.   Distorted gratings and walkways were repaired or
          replaced.

    12.   Reheater shell was replaced.

Repair costs were estimated to be $1.6 million.  Start of

the test program was delayed until October 31, 1974.
                              4-1

-------
Preliminary tests preceded start-up, and a formal test



program was initiated on November 2, 1974.  The program was



concluded on April 30, 1975 with 2342 hours of operation,



after which the system was shut down for modifications to a



grid packed tower for additional tests.  The overall operating



time ratio for the system defined as the time the module



operated as a percentage of the boiler operating time, was



measured to be 60 percent during the first four months.



Operating time data for-the first four months of the test



program appear in Table 4.1.  The reliability of the system



was lower in the first two months of the program than in the



second two months, mainly because of migration of plastic



spheres between adjacent grid compartments in the module, so



that the unit had to be shut down for redistribution of the



spheres and modification of the barrier grids.  Other



problems included pump failures, plugged spray nozzles,



deposits on the demister and at the absorber inlet.



     SCE operated the horizontal module in a short series of



start-up tests that ended on January 16, 1974, when a formal



test program was initiated to assess the performance and



reliability characteristics of the system.  The test program



was concluded on February 9, 1975 after 5927 hours of operation.



Subsequently the module has been dismantled and is being



installed for tests at the Four Corners Plant operated by



Arizona Public Service Company in Farmington, New Mexico.
                              4-2

-------
    Table 4.1  COMPARISON OF OPERATING TIME PARAMETERS

             VERTICAL MODULE - MOHAVE - SCE
Month
11/74
12/74
1/75
2/75
Overall
Operating
time ratio3
46
39
78
84
60
Reliability
50
51
85
84
67
Availability0
39
51
80
88
64
Una vail 5
ability0
34.5
30.8
9.9
11.8
21.8
FGD system actual operating time as a percentage of
Unit 1 operating time.

Actual FGD system operating time as a percentage of the
time that the system was called upon to operate.

Time FGD system was available to operate (whether or
not operated) as a percentage of calendar time.

Time FGD system was unavailable to operate when called
upon to operate as a percentage of calendar time.
                            4-3

-------
     During the one-year program ten separate test blocks

were conducted to obtain performance and operating data.

Both lime and limestone reagents were tested.  SO- spiking

tests were also used to simulate the conditions with higher

percent sulfur -in the coal.  Details of the SO- and particulate

removal performance for this system were presented at the

Atlanta symposium held by EPA in November, 1974.   SO-

removal efficiency as a function of the L/G ratio, shown in

Figure 4.1, ranged between 76 and 98 percent.

     The overall operating time ratio for the system, defined

as the time the FGD system operated as a percentage of the

boiler operating time, was measured to be 73.5 percent

during the one-year operation test.  Month-by-month operating

time data, as published by SCE, appear in Table 4.2.

     Mechanical problems occurred during the test period.

These problems included pump failures, a thickener underflow

drain obstructed by a hard hat, fan alignment problems,

scrubber spray nozzle failures, scrubber shell leaks and

demister blade warping.  In addition, a boiler makers strike

occurred during the test period.
  Weir, Alexander, Jr., et al, "The Horizontal Cross Flow
  Scrubber", Proceedings:  Symposium on Flue Gas Desulfurization
  Atlanta, November 1974, EPA Publication No. EPA 650/2-74-126a,
  pp 357-387.

                            4-4

-------
   100
    95
    90
*«  85
 *


o  80
 CM
O
fcO
    70
    60
    50
   40


   30


   20 —
   10 —
(Courtesy -Southern Californie Edison Co.)
                        1
    0.38% SULFUR COAL


            I         1
     0         5        10        15       20
                        L/6, gpm/1000 scfm

        Figure 4.1   S02  Removal vs  L/G Ratio

               170 MW Horizontal Module.
                              25
30
                             4-5

-------
   Table 4.2  COMPARISON OF OPERATING TIME PARAMETERS

            HORIZONTAL MODULE - MOHAVE - SCE
Month
1/74
2/74
3/74
4/74
5/74
6/74
7/74
8/74
9/74
10/74
11/74
12/74
1/75
2/75
Total
Operating
time ratio3
0.89
0.82
0.73
0.91
0.81
0.79
0.79
1.00
0.58
0.74
0.35
0.52
0.81
0.56
0.74
Reliability
89
82
85
99
92
79
79
100
100
74
40
98
87
56
87
Availability01
89
60
80
99
93
77
63
100
100
68
46
99
90
56
81
Unavail-
abilitya
11
13
12
1
7
20
17
0
0
19
52
1
10
44
13
FGD system actual operating time as a percentage of
Unit 2 operating time.

Actual FGD system operating time as a percentage of the
time that the scrubbing system was called upon to operate.
Time FGD system was available to operate (whether
or not operated) as a percentage of calendar time.

Time FGD system was unavailable to operate when called
upon to operate as a percentage of calendar time.
                            4-6

-------
   APPENDIX A




PLANT SURVEY FORM
        A-l

-------
                     PLANT SURVEY FORM

               NON-REGENERABLE FGD PROCESSES



 A.  COMPANY AMD PLANT INFORMATION

     1.  COMPANY NAME         	Southern California Edison

     2.  MAIN OFFICE          	Rosemead, California	

     3 .  PLANT MANAGER        	G.L.  Fraser	
     4 .  PLANT NAME           	Mohave Generating Station	

     5.  PLANT LOCATION       	Laughlin, Nevada	

     6.  PERSON TO CONTACT FOR FURTHER INFORMATION Dr. A. Weirf Jr.
                                             Principal Scientist for
     7.  POSITION                            Air Quality	

     8.  TELEPHONE NUMBER                    (213) 572-2785	
                                                       1899 Johnson
     9.  DATE INFORMATION GATHERED           	
    10.  PARTICIPANTS IN MEETING                 AFFILIATION

          Mr. John Johnson	              Southern California Edison

          Mr. Dick Ynnng	              Southern California Edison
                                              Environmental
          Mr. Wade Ponder	              Protection Agency	
                                              Environmental
          Mr. John Busik	              Protection Agency

          Mr. Tim Devitt	              PEDCo-Environmental

          Mr. Fouad Zada	              PEDCo-Environmental

          Mr. Tom Ponder	              PEDCo-Environmental
NOTE:   Data in body of report have been updated subsequent to
        the collection of data for Appendix A.
                              A-2

-------
B.  PLANT DATA.   (APPLIES TO  ALL  BOILERS AT THE PLANT).
CAPACITY, MW
SERVICE (BASE, PEAK)
FGD SYSTEM USED
BOILER NO.
1
7Q0
Base
None
2
7QQ
Base
None












C.  BOILER DATA.  COMPLETE  SECTIONS (C)  THROUGH  (R) FOR EACH
                  BOILER  HAVING  AN FGD SYSTEM.
     1.  BOILER IDENTIFICATION  NO.

     2.  MAXIMUM CONTINUOUS  HEAT INPUT
     5

     6
                                   19066:22266

                                   20,000	
         MAXIMUM CONTINUOUS  GENERATING CAPACITY
                                                    790
MM BTU/HR

MW
     4.  MAXIMUM CONTINUOUS  FLUE GAS RATE.  4.200.000    SCFM  @  60°F
BOILER MANUFACTURER              Combustion Engineering

YEAR BOILER PLACED IN SERVICE   1970 & 1971	
     7.  BOILER SERVICE  (BASE LOAD,  PEAK, ETC.)  Base Load

     8 .  STACK HEIGHT                             500'	

     9.  BOILER OPERATION  HOURS/YEAR (197 )

    10.  BOILER CAPACITY FACTOR *                N/A

    11.  RATIO OF FLY ASH/BOTTOM ASH
                                         Available
                                         N/A
      * DEFINED AS:   KWH GENERATED IN YEAR
                      MAX.  CONT.  GENERATED CAPACITY IN KW  x  8760  HR/YR
                              A-3
                                          5/17/74

-------
D.  FUEL DATA

    1.  COAL ANALYSIS  (as received)

             GHV  (BTU/LB.)

             S %

             ASH %
MAX.
12.000


MIN.
11.000


AVG.
11.500
0.38
10.03
    2.  FUEL OIL ANALYSIS  (exclude start-up  fuel)

             GRADE                      	

             S %                        	

             ASH %
E.  ATMOSPHERIC EMISSIONS

    1.  APPLICABLE EMISSION REGULATIONS

        a)  CURRENT REQUIREMENTS

            AQCR PRIORITY CLASSIFICATION
            CLARK COUNTY APCD
            REGULATION & SECTION NO.

            MAX. ALLOWABLE EMISSIONS
            LBS/MM BTU   (County)

        b)  FUTURE REQUIREMENTS,
            COMPLIANCE DATE

            REGULATION & SECTION NO.

            MAXIMUM ALLOWABLE EMISSIONS
            LBS/MM BTU
PARTICULATES
    SO-


26-2A, B, C
0.064


26-2D
0.15
June 30, 1977
June 30, 1977
June 30, 1977
June 30, 1977
June 30, 1977
June 30, 1977
        PLANT PROGRAM FOR PARTICULATES COMPLIANCE
         Test Modules Program then install  Production Scrubbers,

         See EPA Order - See July 9,  1974 Clark County Order



    3.  PLANT PROGRAM FOR SO2 COMPLIANCE  	
                              A-4
       5/17/74

-------
F.  PARTICULATE REMOVAL




    1.  TYPE




        MANUFACTURER




        EFFICIENCY: DESIGN/ACTUAL




        MAX. EMISSION RATE*  LB/HR




                            GR/SCF




                          LB/MMBTU
MECH.





E.S.P.
Research
Cot'tr^ll
97.2/98.2



FGD





        DESIGN BASIS, SULFUR CONTENT
                                                 0.5
G.  DESULFURIZATION SYSTEM DATA




    1.  PROCESS NAME




    2.  LICENSOR/DESIGNER NAME:




                       ADDRESS:




             PERSON TO CONTACT:




                 TELEPHONE NO.:
To Be Determined
    3.  ARCHITECTURAL/ENGINEERS, NAME:




                       ADDRESS:    	




             PERSON TO CONTACT:    	




                 TELEPHONE NO.:
    4.  PROJECT CONSTRUCTION SCHEDULE:




        a)  DATE CF PREPARATION OF  BIDS  SPECS.




        b)  DATE OF REQUEST FOR BIDS




        c)  DATE OF CONTRACT AWARD




        d)  DATE ON SITE CONSTRUCTION  BEGAN




        e)  DATE ON SITE CONSTRUCTION  COMPLETED




        f)  DATE OF INITIAL STARTUP




        g)  DATE OF COMPLETION OF SHAKEDOWN




     *At Max. Continuous Capacity




                              A-5
              DATE
           5/17/74

-------
    5.  LIST MAJOR DELAYS  IN CONSTRUCTION  SCHEDULE AND CAUSES:
    6.  NUMBER OF SO2 SCRUBBER TRAINS USED
    7.  DESIGN THROUGHPUT PER TRAIN, ACFM  @     °F  	

    8.  DRAWINGS:  1)  PROCESS FLOW DIAGRAM  AND MATERIAL BALANCE

                   2)  EQUIPMENT LAYOUT



H.  SO2 SCRUBBING AGENT   -  To be Determined

    1.  TYPE                                 	

    2.  SOURCES OF SUPPLY                    	
    3.  CHEMICAL COMPOSITION  (for each source)

        SILICATES                            	

        SILICA                               	

        CALCIUM CARBONATE                    	

        MAGNESIUM CARBONATE
    4.   EXCESS SCRUBBING AGENT USED ABOVE
        STOICHIOMETRIC REQUIREMENTS

    5.   MAKE-UP WATER POINT OF ADDITION

    6.   MAKE-UP ALKALI POINT OF ADDITION
                             A-6                  5/17/74

-------
 a u teas
   -lg)
                                                                     ST.-
                       TO TS3IKS
                                                                                             FROM TRAINS
SOj SCRUBBIR1	'	1  fi>,   T

         fcyys.-s?h^1
         f V 5r^' — -'• <^^^^

         r-J
                                  FVFROM TR

                                  1    e
  SLUDGE TO
  DISPOSAL SITE
CIEAH CAS 10 STACK




      ff)
                                                                                           WATER MAKEUP
                                                                                      @
                                                                                             TO TRAINS
                                                                                             TO TRAINS
                         LIME/LIMESTONE SLURRY
STREAM NO.
RATE. Ib/hr
flCFM
CPM
PARTICIPATES. Ib/hr
S02. Ib/hr
TEMPERATURE. °F
TOTAL SOLIDS. =o
SPECIFIC GRAVITY.

CO









CO


-






CO




-
•


,

CO









CO









CO


f 	






CO



•





CO









CO

f







C"D
\
' '-, N




'
r . .


OD
• ; J
^

- .- .^


j
: 	

OD



'





C»3)









STREAM NO.
RATE. Ib/hr
ACFM
CPM
PARTICIPATES. Ib/hr
S02 . Ib/hr
TEMPERATURE. °F
TOTAL SQLIOS . %
SPECIFIC GRAVITY

CM)




-- - 	




C>5)









C«D

„







'IT!
^'









1 C'»)
£
'-








tt»>
'


11





Cao]









^
f








(22)









C»)




	



.
CM) \ C*!
•
-,,.„*-',- !
' !
-.-. ^ I
	 - .
• :
. ,,,„,,,
	 !
i
Cz§)









I.    Representative flow  rates based on operating data  at maximum continuous load
                                                                                                              5/17/7.

-------
J.  SCRUBBER TRAIN SPECIFICATIONS - To be determined
    1.  SCRUBBER NO. 1

        TYPE   (TOWER/VENTURI)
        LIQUID/GAS RATIO, G/MCF @
        'GAS VELOCITY THROUGH SCRUBBER, FT/SEC

        MATERIAL OF CONSTRUCTION

        TYPE OF LINING

        INTERNALS:

           TYPE  (FLOATING BED, MARBLE BED,  ETC.).

           NUMBER OF STAGES

           TYPE AND SIZE OF PACKING MATERIAL

           PACKING THICKNESS PER  STAGED

           MATERIAL OF CONSTRUCTION, 'PACKING:

                                    SUPPORTS:
        SCRUBBER NO.  2       -  Same as Scrubber No.  1

        TYPE  (TOWER/VENTURI)                    	
        LIQUID/GAS RATIO, G/MCF  @     °F          	

        GAS VELOCITY  THROUGH SCRUBBER,  FT/SEC  	
        MATERIAL OF CONSTRUCTION                	

           TYPE OF LINING                      	

        INTERNALS:
           TYPE  (FLOATING BED,  MARBLE  BED,  ETC.)	

           NUMBER OF  STAGES                      	
           TYPE AND SIZE OF PACKING MATERIAL    	
 a) Scrubber No. 1 is the  scrubber  that  the flue gases first
    enter.  Scrubber 2  (if applicable) follows Scrubber No. 1.
 b) For floating bed, packing thickness  at rest.

                                                  5/17/74
                              A-8

-------
       PACKING THICKNESS PER STAGE (b)

       MATERIAL OF CONSTRUCTION, PACKING:.

                                SUPPORTS:.

3.   CLEAR WATER TRAY  (AT TOP OF SCRUBBER)

    TYPE

    L/G RATIO

    SOURCE OF WATER


4.  DEMISTER

       TYPE   (CHEVRON, ETC.)

       NUMBER OF PASSES  (STAGES)

       SPACE BETWEEN  VANES

       ANGLE OF VANES

       TOTAL DEPTH OF DEMISTER

       DIAMETER OF DEMISTER
       DISTANCE BETWEEN TOP OF  PACKING
       AND BOTTOM OF DEMISTER

       POSITION (HORIZONTAL, VERTICAL)

       MATERIAL OF CONSTRUCTION

       METHOD OF CLEANING

       SOURCE OF WATER AND PRESSURE

       FLOW RATE DURING CLEANINGS, GPM
       FREQUENCY AND DURATION OF CLEANING

       REMARKS  	
5.  REHEATER

       TYPE (DIRECT, INDIRECT)
b) For floating bed, packing thickness  at rest.


                                              5/17/74
                          A-9

-------
   DUTY, MMBTU/HR
   HEAT TRANSFER SURFACE AREA  SQ.FT..
   TEMPERATURE OF GAS:   IN	OUT

   HEATING MEDIUM SOURCE           	

        TEMPERATURE & PRESSURE      	
        FLOW RATE                   	LB/HR

   REHEATER TUBES, TYPE AND
   MATERIAL OF CONSTRUCTION         	
   REHEATER LOCATION WITH  RESPECT  TO DEMISTER.
   METHOD OF CLEANING
   FREQUENCY AND DURATION  OF  CLEANING __
   FLOW RATE OF CLEANING  MEDIUM	LB/HR

   REMARKS 	        	
SCRUBBER TRAIN PRESSURE  DROP  DATA        INCHES OF WATER

   PARTICULATE SCRUBBER                   	

   S02 SCRUBBER                           	
   CLEAR WATER TRAY

   DEMISTER

   REHEATER

   DUCTWORK


   TOTAL FGD SYSTEM
                      A-10                 5/17/74

-------
    7.  FRESH WATER MAKE UP FLOW RATES AND POINTS OF ADDITION

           TO:  DEMISTER     	
                QUENCH CHAMBER
                ALKALI SLURRYING

                PUMP SEALS 	

                OTHER 	
                TOTAL	

           FRESH WATER ADDED PER MOLE OF SULFUR  REMOVED

    8.  BYPASS SYSTEM

        CAN FLUE GAS BE BYPASSED AROUND FGD SYSTEMS 	

        GAS LEAKAGE THROUGH BYPASS VALVE, ACFM 	
K.  SLURRY DATA  -  TO Be Determined
    LIME/LIMESTONE SLURRY MAKEUP TANK

    PARTICULATE SCRUBBER EFFLUENT
    HOLD TANK  (a)
    SO2 SCRUBBER EFFLUENT HOLD
    TANK (a)
pH



%
Solids



Capacity
(gal)



Hold up
time



L.  LIMESTONE MILLING AND CALCINING FACILITIES:   INDICATE  BOILERS
    SERVED BY THIS SYSTEM.
        TYPE OF MILL  (WET CYCLONE, ETC.)

        NUMBER OF MILLS

        CAPACITY PER MILL

        RAW MATERIAL MESH SIZE

        PRODUCT MESH SIZE
                T/HR
                             A-ll
5/17/74

-------
        SLURRY CONCENTRATION IN MILL

        CALCINING  AND/OR SLAKING FACILITIES

        SOURCE OF  WATER FOR SLURRY MAKE UP OR
        SLAKING  TANK
M.  DISPOSAL OF SPENT LIQUOR  _  To  Be  Determined

    1.  SCHEMATICS OF SLUDGE  &  FLY ASH  DISPOSAL METHOD

        (IDENTIFY QUANTITIES  OR SCHEMATIC)   	

    2.  CLARIFIERS   (THICKENERS)

           NUMBER                            	

           DIMENSIONS                        	
           CONCENTRATION OF SOLIDS  IN  UNDERFLOW

    3.  ROTARY VACUUM FILTER

           NUMBER OF FILTERS                 	

           CLOTH AREA/FILTER                 	
           CAPACITY                  	TON/HR  (WET CAKK)

           CONCENTRATION OF SOLID'S  IN  CAKE  	

           PRECOAT  (TYPE, QUANTITY,  THICKNESS)   	

           REMARKS 	
    4.  SLUDGE FIXATION

           POINT OF ADDITIVES INJECTION

           FIXATION MATERIAL COMPOSITION

           FIXATION PROCESS  (NAME)
           FIXATION MATERIAL REQUIREMENT/TONS OF DRY SOLIDS OF SLUDGE
                                                   5/17/74

                              A-12

-------
            ESTIMATED POND LIFE,  YRS.
            CONCENTRATION OF  SOLIDS  IN  FIXED SLUDGE

            METHOD OF DISPOSAL OF  FIXED SLUDGE 	
            INITIAL SOLIDIFICATION TIME  OF FIXED SLUDGE

     5.  SLUDGE QUANTITY DATA   -   To Be Determined

            POND/LANDFILL SIZE  REQUIREMENTS,  ACRE-FT/YR

            IS POND/LANDFILL ON OR OFFSITI3	

            TYPE OF LINER                  	
            IF OFFSITE,  DISTANCE  AND  COST OF TRANSPORT 	

            POND/LANDFILL DIMENSIONS  AREA IN ACRES 	
                                      DEPTH IN FEET 	
            DISPOSAL PLANS;  SHORT  AND  LONG TERM
N.   COST DATA   - To Be Determined

     1.   TOTAL INSTALLED CAPITAL COST

     2.   ANNUALIZED OPERATING COST
                                                   5/17/74
                               A-13

-------
3.
COST BREAKDOWN
COST ELEMENTS
CAPITAL COSTS
SO- SCRUBBER TRAINS
2
LIMESTONE MILLING
FACILITIES
SLUDGE TREATMENT &
DISPOSAL POND

SITE IMPROVEMENTS
LAND, ROADS, TRACKS,
SUBSTATION
ENGINEERING COSTS
CONTRACTORS FEE
INTEREST ON CAPITAL-
DURING CONSTRUCTION
ANNUALIZED OPERATING COST
FIXED COSTS
INTEREST ON CAPITAL
DEPRECIATION
INSURANCE & TAXES
LABOR COST
INCLUDING OVERHEAD
VARIABLE COSTS
RAW MATERIAL

UTILITIES
MAINTENANCE

INCLUDED IN
ABOVE COST
ESTIMATE
YES NO
EH EH
EH o
EH EU

1 1
EH EH

ED EH
EH EH


EH EH
EH EH
EH EH
EH EH

EH EH

IH EH
EH EH

ESTIMATED AMOUNT
OR % OF TOTAL
INSTALLED CAPITAL
COST






















      A.
      B.
                               A-14
                                                      5/17/74

-------
     4.  COST FACTORS

         a.  ELECTRICITY

         b.  WATER

         C.  STEAM  (OR FUEL FOR  REHEATING)

         d.  FIXATION COST	
         e.  RAW MATERIAL PURCHASING COST

         f.  LABOR:  SUPERVISOR        	

                     OPERATOR          	

                     OPERATOR  HELPER  _.	

                     MAINTENANCE       	
                               $/TON  OF  DRY  SLUDGE

                              	 $/TON  OF DRY  SLUDGE

                              _ HOURS/WEEK	WAGE
O.   MAJOR PROBLEM AREAS:   (CORROSION,  PLUGGING,  ETC.)
      To Be Determined
     1.   S02 SCRUBBER, CIRCULATION TANK AND PUMPS.
          a.
PROBLEM/SOLUTION.
     2.   DEMISTER

               PROBLEM/SOLUTION.
     3.   REHEATER

          PROBLEM/SOLUTION.
                               A-15
                                                   5/17/74

-------
4.   VENTURI SCRUBBER, CIRCULATION TANKS AND  PUMPS


     PROBLEM/SOLUTION	
5.   I.D. BOOSTER FAN AND DUCT WORK


     PROBLEM/SOLUTION	
6.   LIMESTONE MILLING SYSTEM OR LIME  SLAKING


     PROBLEM/SOLUTION	
7.   SLUDGE TREATMENT AND DISPOSAL


     PROBLEM/SOLUTION	
                                              5/17/74
                         A-16

-------
     8.   MISCELLANEOUS AREA INCLUDING BYPASS SYSTEM

          PROBLEM/SOLUTION	
P.   DESCRIBE FACTORS WHICH MAY NOT MAKE  THIS A REPRESENTATIVE
     INSTALLATION	
Q.   DESCRIBE METHODS OF SCRUBBER CONTROL UNDER FLUCTUATING
     LOAD.  IDENTIFY PROBLEMS WITH THIS  METHOD AND SOLUTIONS.
     IDENTIFY METHOD OF pH CONTROL AND LOCATION OF pH PROBES.
                               A-17                5/l7/74

-------
        R.    COMPUTATION OF  FGD SYSTEM AVAILABILITY FACTOR
                             BOILER RATING OR MAXIMUM CONTINUOUS CAPACITY,  MW
PERIOD
MONTH/YEAR












FLUE GAS DESULFURIZATION MODULES
MODULE A
DOWN DUE TO
BOILER
(HRS)












MODULE
(HRS)












MODULE B
DOWN DUE TO
BOILER
(HRS)












MODULE
(HRS)












MODULE C
DOWN DUE TO
BOILER
(HRS)












MODULE
(HRS)












MODULE D
DOWN DUE TO
BOILER
(HRS)












MODULE
(HRS)












CO
       Availability  factor computation:   1.
Divide boiler capacity by the number of modules
and obtain MW/module = x
Multiply boiler capacity by number of hours
during period = a
Add all down times due to module trouble for all modules
during period = b
Add all down times due to boiler trouble or reduction
in electricity demand for all modules during period = c
Availability factor = [a " X_(b+c)]100  =     %
                          ci ~ ]t C
                                                                                   5/17/74

-------
                                 TECHNICAL REPORT
                          (Please read Instructions on the reverse
        DATA
        before completing)
 1 REPORT NO.
 EPA-650/2-75-057-k
                                                       3 RECIPIENT'S ACCESSION-NO.
 4. TITLE AND SUBTITLE
 Survey of Flue Gas Desulfurization Systems
 Mohave Station, Southern California Edison Co.
               5 REPORT DATE
               October 1975
               6. PERFORMING ORGANIZATION CODE
 7 AUTHOR(S)

 Gerald A.  Isaacs and Fouad K. Zada
                                                       I. PERFORMING ORGANIZATION REPORT NO
 9 PERFORMING ORGANIZATION NAME AND ADDRESS
 PEDCo-Environmental Specialists, Inc.
 Suite 13, Atkinson Square
 Cincinnati, Ohio 45246
               10. PROGRAM ELEMENT NO.

               1AB013; ROAP 21ACX-130
               11. CONTRACT/GRANT NO.

               68-02-1321, Task 6k
 12. SPONSORING AGENCY NAME AND ADDRESS
 EPA, Office of Research and Development
 Industrial Environmental Research Laboratory
 Research Triangle Park, NC 27711
               13. TYPE OF REPORT AND PERIOD COVERED
               Task Final: 7/74-9/75  	
               14. SPONSORING AGENCY CODE
 15. SUPPLEMENTARY NOTES
 16. ABSTRACT Tne report givcs results of a survey of the flue gas desulfurization (FGD)
 systems at Southern California Edison's Mohave Generating Station.  Two prototype
 170 MW SO2  absorber systems were installed:  a vertical module treated a portion of
 the flue gas from boiler unit 1; and a horizontal module treated a similar flue gas
 portion from unit 2.  Each unit has a maximum net generating capacity of 790 MW,
 burning coal with a heat content of about 11,500 Btu/lb.  Ash and sulfur contents of
 the coal are  about 10  and 0.4 percent, respectively. The vertical absorber was
 damaged by fire during startup on January 24, 1974. After repairs, test operations
 were conducted from November 2, 1974, to April 1975.  The unit was then modified
 for additional tests which were completed on July 2, 1975. The horizontal module,
 after operating for 5927 hours in various test modes from January 16, 1974,  to
 February 9,  1975, was  dismantled and removed from the  Station.   Particulate and
 SO2 removal efficiencies varied with the tests that were run.  Emission regulation
 for this plant is 0.15  Ib/MM Btu for SO2.  Both absorbers are preceded by electro-
 static precipitators.  Spent slurry from each absorber was dewatered and
 stabilized, and the water was returned to the FGD system.  Estimates of capital and
 operating costs have  not been published.
 7.
                             KEY WORDS AND DOCUMENT ANALYSIS
                 DESCRIPTORS
                                          b IDENTIFIERS/OPEN ENDED TERMS
                           c. COSATI Field/Group
 Air Pollution      Coal
 Flue Gases        Combustion
 Desulfurization    Electrostatic Precip-
 Sulfur Dioxide        itators
 Absorbers (Equipment)
 Columns (Process
   E ngineering)	
  Air Pollution Control
  Stationary Sources
  Particulate
  Horizontal Absorber
  Vertical Absorber
 13B
 21B
 07A,07D
 07B
2 ID
13. DISTRIBUTION STATEMENT

 Unlimited
  19 SECURITY CLASS (This Report)
   Unclassified
21. NO OF PAGES
    46
  20 SECURITY CLASS (Thispage)
   Unclassified
                           22 PRICE
EPA Form 2220-1 (9-73)
A-19

-------