United State*          Office of the Inspector General   September 1991
Environmental Protection     401 M Street, S.W.
Agency            Washington, D.C. 20460
EpA's Office °f the
Inspector General
Annual
Superfund Report
to the Congress
for Fiscal 1990
                           Printed on Recycled Paper

-------
EPA Office of Inspector General Annual Suoertund Report to the Congress for Fiscal 1990   I

                           FOREWORD

     This is our fourth Annual Superfund Report to the Congress,
covering fiscal 1990 activities.   The Superfund Amendments and
Reauthorization Act of 1986  (SARA) requires the Office of
Inspector-General  (OIG) to audit the Superfund program annually
and to report to Congress annually on these required  audits.

     The beginning of the Superfund program created new and
unique cost accounting requirements.  EPA has responded to these
new requirements over the years by significantly improving its
accounting and documentation of Superfund costs on a  site-
specific basis.  However, in our fiscal 1990 Trust Fund audit, we
found continuing problems with the reporting of Superfund
accounting information.  The Agency's Integrated Financial
Management System  (IFMS) did not have a reporting function to
provide complete and accurate reports for EPA management.  Also,
EPA did not transfer complete and  accurate accounting information
from the Contract Payment System to IFMS.

     SARA requires the EPA Administrator to submit to Congress an
annual Superfund progress report each January 1 covering
activities during the prior  fiscal year.  EPA submitted its third
such report, due January 1,  1990,  on November 19, 1990.  SARA
requires the OIG to review that report for reasonableness and
accuracy.  SARA also requires that the Agency report  include our
report.

     Our review of the Agency's report found that information in
the report on several topics was reasonable and accurate.
However, we expressed concern about the accuracy of some data in
the report from the Comprehensive  Environmental Response,
Compensation, and Liability  Information System (CERCLIS).
Problems with the reliability of CERCLIS data found in earlier
reviews had not been fully resolved.

     Our reviews of the Agency's performance in managing the
Superfund program also found significant deficiencies.  We
performed several reviews of EPA's enforcement efforts.  In
reviews of cost recovery collections, we found EPA did not
usually record cost recovery receivables timely and did not act
promptly to collect amounts  owed.  We followed up on  our fiscal
1986 audit of cost recovery  actions and found continued problems.
EPA was still (1) not using  alternative dispute resolution
procedures to collect amounts under $200,000, (2) not centrally
tracking bankruptcy cases and actions,  (3) taking too long to
complete negotiations with responsible parties, (4) not always
taking cost recovery action  before the end of the statute-of-
limitations period, and (5)  not including some key information in
automated management information systems.  We reviewed the
Agency's oversight of responsible  party cleanup activities under

-------
 EPA Office of inspector General Annual Suoerfund Report to the Congress tor Fiscal 1990   II

 settlement  agreements.   In Region 2,  we found  EPA (1)  took 6-36
 months  to review settlement deliverables, thus delaying cleanups,
 (2) did not assess  stipulated penalties for missing settlement
 milestone dates,  (3)  did not  adequately oversee its enforcement
 support contractors,  and (4)  did not  timely bill responsible
 parties for EPA oversight costs.

     We performed two reviews in the  contract  management area.
 We audited  the award  fee process for  Superfund cost-plus-award-
 fee contracts.   We  found that EPA (1)  often rewarded performance
 that was  less  than  satisfactory,  (2)  used different evaluation
 procedures  under different contracts,  and (3)  sometimes did  not
 inform  contractors  timely of  needs for performance  improvement.
 We reviewed the Agency's bidding and  award  process  for the
 Alternative Remedial  Contracting Strategy (ARCS)  contracts.   We
 found that  EPA succeeded in increasing competition,  generally
 awarded the contracts timely  and followed most applicable Federal
 acquisition regulations.   However,  EPA did  not (1)  prepare
 required  independent  cost estimates,  (2) adequately document its
 resource  requirements,  and (3)  establish criteria and  procedures
 to define and  evaluate  a contractor's  efforts  to use small and
 disadvantaged  businesses.

     During .fiscal  1990,  we initiated  a major  investigative
 effort  into the Contract Laboratory Program (CLP).   This complex
 investigation  is  finding fraud  committed by a  number of EPA
 contractors which are part of the CLP.   In  fiscal 1990,  one  major
 consent judgment was  filed as a result of this investigative
 effort.   This  effort  continued  in fiscal 1991,  when it produced a
 number  of indictments and several guilty pleas.

     In addition to reviewing Agency performance, we also take  a
 proactive role  to help  EPA management  prevent  future problems.
 This includes  review  of draft documents and participation in EPA
work group  meetings.  During  fiscal 1990, we continued to help
Agency  work groups  on technical assistance  grants to citizens'
 groups  and  cooperative  agreements with States.

     We are addressing  difficulties in providing  timely and
adequate  audit  and  investigative  coverage of major  EPA contracts,
many of which  support the Superfund program.   We  are requesting
additional  resources  to timely  respond to audit requests from
Agency  contract managers,  and to  identify contractor fraud,  abuse
and mismanagement.  We  are improving coordination with other
Federal audit organizations responsible for auditing many EPA
 contractors.  For several  major Superfund contractors, we are
assuming  Federal audit  responsibilities formerly carried by
others.  We are putting auditors  on site at some  major
contractors  to  provide  ongoing  audit coverage.  We  intend to
audit major EPA cost-type  contracts on a regular  schedule to
identify  problems for correction  during the terms of the
contracts.

-------
EPA Office of Inspector General Annual Suoerfund Report to the Congress for Fiscal 1990
     We are preparing a new long range strategic plan  for
Superfund audits  and investigations.  Our new plan will  address
current and anticipated needs in Superfund, and will coordinate
audit and investigative efforts.

     We will continue to help Agency management deliver  the most
effective and efficient Superfund program through a comprehensive
program of audits,  investigations and fraud prevention.
                                            John C. Martin
                                            Inspector General
             US EPA
 Headquarters and Chemical Libraries                .
     EPA West Bldg Room 3340             H8Q08HOFV
          Mailcode 3404T                  nv/rw    4>^|.nAij*.
      1301 Constitution Ave NW            PftrPfianBrfl UOll8CllOi
       Washington DC 20004              ' on
           202-566-0556

-------
EPA Office of Inspector General Annual Simerfund Report to the Congress for Fiscal 1990	jy

                       TABLE OF CONTENTS


PURPOSE 	    1

BACKGROUND  	    3

HAZARDOUS SUBSTANCE SUPERFUND 	    5

COOPERATIVE AGREEMENTS   	   10
     ALABAMA DEPARTMENT  OF ENVIRONMENTAL MANAGEMENT 	   10
     CALIFORNIA DEPARTMENT OF HEALTH   	   12
     CALIFORNIA STATE WATER RESOURCES  CONTROL  BOARD 	   16
     GEORGIA DEPARTMENT  OF NATURAL RESOURCES   	   19
     KENTUCKY NATURAL RESOURCES AND ENVIRONMENTAL PROTECTION
          CABINET	21
     MISSISSIPPI DEPARTMENT OF ENVIRONMENTAL QUALITY  ....   23
     NEtf YORK STATE DEPARTMENT OF ENVIRONMENTAL
          CONSERVATION   	   25
     NORTH CAROLINA DEPARTMENT OF HUMAN RESOURCES 	   26
     OREGON DEPARTMENT OF ENVIRONMENTAL QUALITY  	   28
     SOUTH ADAMS COUNTY, COLORADO  	   31
     TEXAS WATER COMMISSION - BIOECOLOGY SITE	33
     TEXAS WATER COMMISSION - HIGHLANDS SITE	35
     TEXAS WATER COMMISSION - SIKES SITE	36
     REGION 8 ADMINISTRATION OF SUPERFUND COOPERATIVE
          AGREEMENTS - FOLLOW-UP REVIEW 	   37

REMEDIAL INVESTIGATIONS  AND FEASIBILITY STUDIES  	   41
     BAIRD & McGUIRE COMPANY SITE, HOLBROOK, MA	41
     IRON HORSE PARK SITE, NORTH BILLERICA, MA  	   42
     NYANZA CHEMICAL SITE, ASHLAND, MA 	   43
     SELMA PRESSURE TREATING SITE, SELMA, CA   	   46

PERFORMANCE AUDITS AND SPECIAL REVIEWS  	   48
     COST RECOVERY COLLECTIONS	48
     COST RECOVERY ACTIONS FOLLOW-UP REVIEW 	   52
     OVERSIGHT OF POST-SETTLEMENT ACTIVITIES   	   56
     REGION 4 REMOVIAL ACTIVITIES  	   60
     SUPERFUND INNOVATIVE TECHNOLOGY EVALUATION
          DEMONSTRATION  PROGRAM  	   66
     COST-PLUS-AWARD-FEE CONTRACTS  	   71
     ARCS CONTRACTS BIDDING AND AWARD  	   74
     CERCLIS REPORTING   	   79
     CERCLIS POST-IMPLEMENTATION STUDY SPECIAL REVIEW ....   82
     REGION 5 CONFIDENTIAL DISCLOSURE  STATEMENTS  	   84
     INVESTIGATIVE-DERIVED WASTES SPECIAL REVIEW  	   86
     ENVIRONMENTAL RESPONSE BRANCH SITE-SPECIFIC TIMEKEEPING
          SPECIAL REVIEW 	   87
     BETTER BRITE ZINC SHOP SITE, WI,  UNANNOUNCED SITE
          REVIEW	88

-------
EPA Office of Inspector Ganafal Annual Stiparfund Raoort to the Conorsss for Fiscal 1990	y

     BUNKER HILL SITE,  ID, SPECIAL REVIEW  	  89
     OLIN CORPORATION,  OH, SPECIAL REVIEW	92

XNTERAGENCY AGREEMENTS  	  95
     U.S. ARMY CORPS OF ENGINEERS	95
     DEPARTMENT OF ENERGY 	  95
     FEDERAL EMERGENCY MANAGEMENT AGENCY   	  95
     DEPARTMENT OF THE INTERIOR	96
     INTERNAL  REVENUE SERVICE 	  98
     DEPARTMENT OF JUSTICE  	  98

CONTRACTS	99
     CHEM-TLE'S TERMINATION SETTLEMENT PROPOSAL  	 100
     KAAREN JOHNSON ASSOCIATES TRAINING SUPPORT  SERVICES
          CONTRACT	101

ASSISTANCE TO  EPA MANAGEMENT	103

REVIEW OF AGENCY*S SUPERFDND PROGRESS REPORT   	 106

INVESTIGATIVE  ACTIVITY  	 108

EXHIBIT I	109

EXHIBIT II	113

EXHIBIT III	116

APPENDIX: ACRONYMS AND ABBREVIATIONS  	 119

-------
EPA Office of Inspector General Annual Suoerfund Report to the Congress for Fiscal 1990	1

                             PURPOSE

     This report is provided pursuant  to section  lll(k)  of the
Comprehensive Environmental Response,  Compensation,  and  Liability
Act (CERCLA) of 1980, as amended.  The Superfund  Amendments and
Reauthorizat'ion Act  (SARA) of 1986 amended  that section  of CERCLA
to add several annual requirements for the  Inspector General of
each Federal agency carrying out CERCLA authorities.   These
requirements include four audit areas  and an  annual  report to
Congress about the required audit work.  This report covers
fiscal 1990 audits of Superfund activities.   The  required four
audit areas are discussed below.

     This report contains chapters on  the three mandated areas in
which we performed reviews.  We are also summarizing other
Superfund audit work, assistance to EPA management and Superfund
investigative work which we performed  during  fiscal  1990.   We go
beyond the statutory requirements to provide  the  Congress with
significant results of all of our Superfund work.

Trust Fund

     CERCLA requires ". . .an annual  audit of all payments,
obligations, reimbursements, or other  uses  of the Fund in the
prior fiscal year  .  . . ."  We call this our  Trust Fund  audit.
It is a financial and compliance audit of EPA obligations and
disbursements from the Hazardous Substance  Superfund during the
fiscal year.

Claims

     CERCLA requires an annual audit to assure ".  .  . that claims
are being appropriately and expeditiously considered .  .  . ."
Since SARA did not include natural resource damage claims as
allowable Fund expenditures, the only  claims  provided in CERCLA,
as amended, are response claims.  No claims were  submitted during
fiscal 1990.  In future years, we will audit  claims  large enough
to be considered material.

Cooperative Agreements

     CERCLA requires audits ". . . of  a sample of agreements with
States (in accordance with the provisions of  the  Single  Audit
Act) carrying out response actions under this title  . .  .  ."  We
perform financial and compliance audits of  cooperative agreements
with States and political subdivisions.  In some  instances, our
audits also review program performance.  In addition, we
sometimes review EPA regional management of the cooperative
agreement program.

-------
EPA Office of Inspector General Annual Suoerfund Report to the Congress for Fiscal 1990	

Remedial Investigations/Feasibility Studies (RI/FS)

     CERCLA requires  our "... examination of remedial
investigations and feasibility studies  prepared for  remedial
actions  .  .  .  ."  Our RI/FS examinations provide a technical
review of  the adequacy of  the studies to provide a sound
technical  basis for remedial action decisions.  These
examinations may be done as part of audits of EPA management or
as special reviews by our  technical staff.

-------
EPA Office of Inspector General Annual Stmerfund Report to the Congress for Fiscal 1990	2

                          BACKGROUND

     The Comprehensive Environmental Response, Compensation, and
Liability Act of 1980 (CERCLA), Public Law 96-510, enacted on
December 11, 1980, established the "Superfund" program.  The
purpose of the Superfund program is to protect public health and
the environment from the release, or threat of release, of
hazardous substances from abandoned hazardous waste sites and
other sources where response  is not required by other Federal
laws.  CERCLA established a Hazardous Substance Response Trust
Fund to provide funding for responses ranging from control of
emergency situations to permanent remedies at uncontrolled sites.
CERCLA authorized a $1.6 billion program financed by a five-year
environmental tax on industry and some general revenues.  CERCLA
requires EPA to seek response, or payment for response, from
those responsible for the problem, including property owners,
generators, and transporters.

     CERCLA was revised and expanded by the Superfund Amendments
and Reauthorization Act of 1986  (SARA), Public Law 99-499,
enacted October 17, 1986.  SARA reinstituted the environmental
tax and expanded the taxing mechanism available for a five-year
period.  It authorized an $8.5 billion program for the 1987-1991
period.  It renamed the Trust Fund the Hazardous Substance
Superfund.  The Budget Reconciliation Act of 1990 reauthorized
the program for three additional years and extended the taxing
mechanism for four additional years.

     The basic regulatory blueprint for the Superfund program is
the National Oil and Hazardous Substances Contingency Plan  (NCP),
40 CFR Part 300.  The NCP was first published in 1968 as part of
the Federal Water Pollution Control Plan, and has been
substantially revised three times to meet CERCLA requirements.
The NCP lays out two broad categories of response: removals and
remedial response.  Removals  are relatively short-term responses
and modify an earlier program under the Clean Water Act.
Remedial response is long-term planning and action to provide
permanent remedies for serious abandoned or uncontrolled
hazardous waste sites.

     CERCLA recognized that the Federal Government can only
assume responsibility for remedial response at a limited number
of sites representing the greatest public threat.  Therefore, EPA
must maintain a National Priorities List (NPL), and must update
it at least annually.  The NPL consists primarily of sites ranked
on the basis of a standard scoring system, which evaluates their
threat to public health and the environment.  In addition, CERCLA
allowed each State to designate its highest priority site,
without regard to the ranking system.

-------
EPA Office of Inspector General Annual Suoarfund Report to the Congress for Fiscal 1990           4

     CERCLA section  104(c)(3)  does  not allow EPA to fund remedial
actions unless the State  in which the release occurs enters into
a contract or cooperative agreement with EPA to provide certain
assurances, including cost sharing.   At most sites, the State
must pay 10 percent  of the costs  of remedial action.  EPA may
fund 100 percent of  preremedial activities (preliminary
assessments, site inspections), remedial planning (remedial
investigations, feasibility studies,  remedial designs), and
removals.  For facilities operated  by a State or political
subdivision at the time of disposal of hazardous substances, the
State must pay 50 percent of all  response costs, including
removals and remedial planning previously conducted.

     CERCLA sections 104(c)(3) and  104(d)  authorize EPA to enter
into cooperative agreements with  States or political subdivisions
to take, or to participate in, any  necessary actions provided
under CERCLA.  A cooperative agreement serves to delineate EPA
and State responsibilities for actions to be taken at the site,
obtains required assurances, and  commits Federal funds.  EPA uses
cooperative agreements to encourage State participation in the
full range of Superfund activities  -  preremedial,  remedial,
removal and enforcement.

-------
EPA Office of Inspector General Annual Suoerfund Report to the Congress for Fiscal 1990	5

                HAZARDOUS SUBSTANCE SUPERFUND


SCOPE AND OBJECTIVES

     We contracted with an independent public accounting  (IPA)
firm to perform an audit of EPA's Schedules of Obligations and
Disbursements for the Hazardous Substance Superfund  (Superfund)
for the fiscal year ended September 30, 1990.  The IPA examined,
on a test basis, financial management records at  EPA's Servicing
Finance Offices and accounting points located at  six of the ten
regional offices, three major laboratory facilities, and
Headquarters.  The four regional offices excluded from audit
field work accounted for less than five percent of fiscal 1990
obligations and disbursements.

     As part of the audit, the IPA selectively tested  (using
statistical and non-statistical samples) obligation and
disbursement transactions.  The objectives of this audit were to
determine if EPA:

a.   Presented the Schedules of Obligations and Disbursements
     fairly, in all material respects, in accordance with
     applicable laws, regulations and guidelines;

b.   Complied with laws and regulations which, if not followed,
     might have a material effect upon the Schedules of
     Obligations and Disbursements; and

c.   Established an adequate internal control structure to ensure
     the reliability of applicable financial management records.

     The audit also included a review of the status of findings
and recommendations included in the prior audit reports for
fiscal years 1988 and 1989.  In addition, the IPA performed
agreed-upon procedures regarding certain financial management and
personal property records for fiscal 1990.

     It was not within the scope of this audit to determine the
allowability and allocability of the general support services
cost pools that EPA accumulated and allocated to  Superfund or to
verify the bases for these allocations.

FINDINGS

1.    financial Results of Audit

     During fiscal 1990, EPA obligated over $1.5  billion and
disbursed almost $1.1 billion.  The IPA questioned obligations
and disbursements as shown below for reasons that we summarize in

-------
EPA Office of Inspector General Annual Superfund Report to the Congress tor Fiscal 1990	g

the remaining  findings.  We detail the financial  results  of this
audit  in Exhibits I and II.

                Total        Accented    Ineliaible1  Unsupported2
Obligations   $1,550,587,893  $1,536,775,234 $       0  $13,812,669

Disbursements $1,093,339,957  $1,085,414,782 $ (141,126)   $8,066,301

2.    Internal Control Weaknesses Existed in IFMS

     A material internal  control weakness existed in the
reporting capabilities of the Integrated Financial Management
System (IFMS).  The IFMS  did not have a reporting function to
provide complete  and accurate reports for EPA management.   Also,
complete and accurate accounting information was  not transferred
from the Contract Payment System to IFMS.  In addition, EPA had
not updated the Agency's  accounting procedures into the Resources
Management Directives System since the implementation of  IFMS in
March  1989.

3.    Accounts Receivable

     EPA needed to improve the recording and managing of  accounts
receivable and collections.  Our audit showed that EPA did not
record in a timely manner 51 receivables, totalling $4,620,547,
due for cost recovery actions,  fines and penalties, and State
cost shares.   Also,  EPA did not record in the correct fiscal year
five receivables,  totalling $562,288.  In addition, the Agency
did not assess interest,  totalling $181,468, on 13 receivables
and did not record 23 collections, totalling $2,258,165,  against
their  corresponding receivables.  Furthermore, EPA did not
consistently apply Agency guidance for assessment of interest on
Superfund State Contracts.

     Problems  in  the conversion from the previous system  to IFMS
resulted in an $18.7 million difference in the reconciliation of
the general ledger control account to the subsidiary accounts
receivable ledger.  Until EPA reconciles this difference,  it
cannot determine  the correct amount to report.  As a result,  EPA
cannot manage  and monitor accounts receivable.
     1   Costs questioned because of  an  alleged violation of a
provision of  a  law,  regulation, contract, grant, cooperative
agreement, or other  agreement or document governing the
expenditure of  funds.

     2   Costs questioned because, at the  time of the audit, they
were not supported by adequate documentation and/or had  not been
approved by responsible program officials.

-------
EPA Office of Inspector General Annual Suoerfund Report to the Congress for Fiscal 1990	2

     EPA classified  $56,897,266,  or 90  percent of the total
receivables, as delinquent.   Of this  amount,  $23,649,439 was more
than one year  overdue.  This  may  indicate that the Agency is not
aggressively pursuing collections of  receivables.

4.    Personnel Compensation

     The IPA questioned  ($97,366)  of  the $117,942,517 of recorded
personnel compensation disbursements.   The questioned costs
resulted from  errors in recording redistribution of hours,
unrecorded redistributions  of hours,  lack of documentation to
support transactions, account number  data and hours not in
agreement with source information,  incorrect pay rates, and input
and adjustment errors.  The audit showed a difference of
$11,266,158 between  the total Personnel Compensation costs
reported in the Schedule  of Disbursements and the detailed
payroll records.

     Certain payroll redistributions  were recorded twice in the
Paymerge File, resulting  in negative  dollars and hours charged to
certain account numbers and overcharges to other account numbers.
The problem shows a  weakness  in the design of the internal
controls, allowing these  errors to occur.  In addition, the
operating of control procedures did not ensure that EPA personnel
detected these errors.

5.    Nonpayroll Documentation and Recording Errors

     Based upon the  results from  statistical and non-statistical
sampling, the  IPA questioned  $13,812,659 of nonpayroll
obligations and $8,022,541  of nonpayroll disbursements.  The
reasons for questioned costs  included:   obligating and disbursing
documents not  located, no Superfund justifications on or attached
to obligating  documents,  errors in correcting entries,
documentation  not available because another accounting point
recorded the transactions,  amounts recorded in IFMS not agreeing
with the obligating  and disbursing documents, account numbers
entered incorrectly  into  IFMS, and disbursements recorded in the
wrong  fiscal year.

6.    Accounting for and Controlling Personal Property

     The audit showed 129 property and  equipment items costing
$1,466,884 not recorded in  the Personal Property Accounting
System (PPAS).  The  IPA identified these 129 items from a non-
statistical sample of 412 items costing $2,139,993 purchased
during fiscal  1990.  The  IPA  found considerable improvements in
fiscal 1990 in compliance with Agency policies and procedures on
designating property officials, taking  annual physical
inventories and physically  securing property items purchased

-------
EPA Office of Inspector General Annual Suoerfund Report to the Congress for Fiscal 1990	8

during the fiscal year.  Despite these improvements, not all
accountable property was recorded  in PPAS.

     The primary reason why property items were not recorded in
PPAS was that contracting officers, custodial  officers,  or
receiving personnel did not send documentation of property
purchased and received to the right Property Accountable
Officers.  Agency policies and procedures required them  to send
this documentation.

AGENCY RESPONSE

     In response to the draft audit report, the Agency
essentially agreed with the recommendations and indicated they
would:

     •    Enhance Agency software  to provide for complete and
          accurate transfer and audit trail of data between the
          Contract Payment System  and IFMS.

     •    Complete guidance for recording and  supporting
          transactions in IFMS and for reconciling data  in
          internal and external records and reports.

     •    Issue a memorandum to FMOs noting the audit's  concerns
          on the assessment and accrual of interest on delinquent
          SSC amounts.

     •    Research and analyze the causes for  the understatement
          of Personnel Compensation costs in the Schedule of
          Disbursements, and take  appropriate  action to  prevent
          similar occurrences.

     •    Analyze causes for the negative hours and amounts in
          the Paymerge File, and take appropriate action to
          prevent similar occurrences.

     •    Resolve questioned transactions, and make appropriate
          correcting entries.

     •    Implement a process restricting IFMS users from
          accessing and changing documents outside of  their own
          accounting points.

     •    Re-emphasize requirements for retention of
          documentation for all accounting entries at  the
          recording accounting point and provision of  copies of
          the documentation to other affected  accounting points.

     •    Evaluate the adequacy of existing guidance for
          maintaining documentation when making correcting

-------
EPA Office of Inspector General Annual Suoerfund Report to the Congress for Fiscal 1990            i

          entries  in IFMS,  and issue revised or clarifying
          guidance,  as appropriate.

     •    Obtain certifications from appropriate Regional
          Administrators  and Assistant Administrators that
          corrective actions have been taken to record
          accountable property in PPAS.

     The Agency's  proposed  corrective actions were responsive to
the draft report's recommendations.   Therefore we made no
additional recommendations  in the final report.

     We issued the final  audit report, Audit Report Number
P1SFFO-11-0032-1100385, on  September 16, 1991.  The Assistant
Administrator for  Administration and Resources Management  has 90
days to respond to the report.

-------
EPA Office of Inspector General Annual Sunerfund Report to the Congress for Fiscal 1990	10

                    COOPERATIVE AGREEMENTS

     In fiscal 1990, we issued thirteen audit reports on
Superfund cooperative agreements and one audit report on a
contractor used by a State under several Superfund cooperative
agreements.  We also issued a follow-up report to a prior report
on Region 8's administration of Superfund cooperative agreements.
The combined financial results of the  financial audits of
Superfund cooperative agreements were  as follows:

                                    Federal Share    Total  Costs
Amount audited                         $46,802,470    $50,056,073
Amount accepted                        $35,990,151    $39,205,027
Ineligible costs3                      $ 2,673,022    $ 2,677,634
Unsupported costs4                     $ 6,292,834    $ 6,317,582
Unnecessary/unreasonable costs5        $ 1,846,463    $ 1,855,830

     We summarize fourteen of the audits below.  The audit  of the
State contractor evaluated the contractor's indirect cost rates.
The auditors calculated different rates than proposed by the
contractor.  The contractor agreed to  the rates calculated  by the
auditors.  We questioned no costs in that report.

ALABAMA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT

Scope and Objectives

     We contracted with an independent public accounting (IPA)
firm to perform an interim audit of a  cooperative agreement
awarded to the Alabama Department of Environmental Management
(ADEN) to identify and rank hazardous  waste sites.  The objective
of the audit was to determine whether  costs claimed were
reasonable and allowable under the terms of the cooperative
agreement and applicable regulations.  The audit covered costs
claimed by ADEN from January 1, 1987 through December 31, 1988.
     3  Costs questioned because of an alleged violation of a
provision of a law, regulation, contract, grant, cooperative
agreement, or other agreement or document governing the
expenditure of funds.

     4  Costs questioned because,  at the time of the audit, they
were not supported by adequate documentation and/or had not been
approved by responsible program officials.

     5  Costs questioned because they were not necessary or not
reasonable.

-------
ERA Office of Inspector General Annual Stmerfund Report to the Con
for Fiscal 1990
11
Findings

1.   ADEN Needs To Properly Allocate Program Costs

     ADEN did not properly  allocate repair and maintenance
charges for the computer  to all  assistance agreements.  As a
result, ADEM claimed  $6,021 of excess repair and maintenance
charges under the cooperative agreement.

2.   Indirect Costs Mav Need To  Be Adjusted

     ADEM based its indirect costs for October, November and
December 1988 on an indirect cost rate not approved by EPA.  When
EPA establishes the final rate,  adjustments may be needed.
Financial Results of Audit
                                     Federal Share
         Total Costs
            $477,110
            $471,089
            $  6,021
            $       0
            $       0
Amount audited                            $477,110
Amount accepted                           $471,089
Ineligible costs6                         $  6,021
Unsupported costs7                        $      0
Unnecessary/unreasonable  costs8           $      0

Recommendations

     We recommended  that  EPA Region 4:

     •    Require ADEM to properly allocate program costs among
          assistance agreements.

     •    Require ADEM to make necessary adjustments to reflect
          the final  approved indirect cost rate for the period
          ending September 30, 1989.

     •    Not participate in ineligible costs of $6,021, and
          recover funds due EPA.
     6  Costs questioned because of an alleged violation of a
provision of a law,  regulation,  contract,  grant, cooperative
agreement, or other  agreement or document governing the
expenditure of funds.

     7  Costs questioned because, at the time of the  audit, they
were not supported by  adequate documentation and/or had not been
approved by responsible  program  officials.

     8  Costs questioned because they were not necessary or not
reasonable.

-------
EPA Office of Inspector General Annual Stinerfund Report to the Conorass for Fiscal 1990	12

Agency Response

     In response to the audit report,  EPA Region 4 indicated:

     •    ADEM's computer maintenance  costs  will be part of its
          indirect cost pool.

     •    No adjustment to  indirect costs was necessary because
          EPA  approved the  rate ADEN used.

     •    ADEM should deduct $6,021 in ineligible costs from its
          next reimbursement request.

CALIFORNIA DEPARTMENT OF HEALTH

Scope and Objectives

     The California State Controller performed on our behalf an
interim audit  of the California Department of Health Services-
Toxic Substances Control Program's  (DHS-TSCP)  accounting
procedures for controlling  costs under the cooperative agreement
for Stringfellow Superfund  site work.   The audit covered the
period from cooperative agreement award on July 28,  1983, through
September 30,  1988.  The audit objectives were to determine the
reasonableness, allowability and allocability of the costs
claimed to date under the Stringfellow cooperative agreement,  and
to determine the adequacy of the DHS's financial management
system under the cooperative agreement.

Findings

1.   Failure to Use the Official State Accounting System

     DHS-TSCP  did not use the official California State
Accounting and Reporting System  (CALSTARS) in accounting for
Stringfellow project costs.  Instead,  DHS-TSCP used manually
prepared spreadsheets compiled from a  combination of sources,
including interoffice memorandums and  piecemeal data extracted
from CALSTARS, to report the source and application of funds for
EPA-supported  activities.   The use of  a manual spreadsheet system
was duplicative, resulted in inaccuracies, and took more time
than using the official State accounting system.  As a result, we
questioned more than $2 million of unreconcliable, duplicate and
unsupported costs.

2.   Inadequate Labor Distribution System

     DHS-TSCP  used an inadequate labor distribution system to
accumulate and claim labor  costs against the cooperative
agreement.  It based most labor costs  claimed on allocations of
employee time  and not actual time charges.   Our prior audit

-------
EPA Office of Inspector General Annual Sunerfund Report to the Congress for Fiscal 1990	13

reports also noted that the DHS-TSCP timekeeping  system
predesignated personnel to various programs, and  claimed  their
labor, fringe, and associated indirect costs on this basis.   The
current DHS time reporting system  is similar, in  that  it
allocates the costs of supervisory and clerical positions as
direct charges to projects based upon the direct  labor hours
spent by the working level staff.  Supervisory and clerical staff
do not fill out timesheets.  Neither method permitted
verification of the validity of employee and related costs
allocated to EPA funded projects.

3.   Failure to Develop an Indirect Cost Rate

     DHS-TSCP did not develop an indirect cost rate proposal  for
periods beginning with the 1987-88 fiscal year.   This  was due to
an inability to identify direct and indirect costs adequately.
DHS-TSCP needed the indirect cost proposal to support  indirect
billings to EPA.

4.   Costs Claimed Not Reconciled

     DHS-TSCP did not establish procedures to reconcile Federal
funds requested to actual disbursement of Federal funds.   As  a
result, DHS-TSCP had overdrawn $165,736 in Federal funds  through
September 30, 1988.

5.   Audit Resources Not Adequately Used

     DHS-TSCP did not adequately use its audit resources.  The
DHS-TSCP has used its audit resources almost exclusively  to
perform external contract cost audits, instead of performing
internal audits of its operating procedures.  In  addition, the
audit group had no audit plan to fulfill its audit
responsibilities.

6.   Lack of Centralized Filing System

     DHS-TSCP had not established a centralized filing system to
maintain documentation applicable to the Stringfellow  Superfund
site.  Without site specific files, errors and omissions
involving the accounting and reporting of costs and other
information are more likely.

7.   Lack of Written Accounting Procedures

     DHS-TSCP had not established written procedures for
preparing and reviewing quarterly Financial Status Reports
(FSRs).  Specifically, it had no procedures detailing  the process
of identifying and summarizing expenditures from  the source
documentation or the official accounting records  to the FSR.   In

-------
EPA Offlca of Inmactor Canard Annual Simerfund Report to tha Congress for Fiscal 1990	14

addition, there was no  provision for  DHS management to review the
accuracy of the completed  FSRs.

8.   Staff Not Trained  in  Preparation of FSRs

     DHS-TSCP did not devote  enough resources to the FSR claiming
process.  One accountant not  thoroughly knowledgeable on how to
accumulate costs shown  on  the FSRs  prepared the FSRs.  In
addition, DHS-TSCP had  not designated any other employee to
assist this employee if he became ill.

9.   Lack of Coordination  Between Accounting and Program Section

     DHS-TSCP's Accounting and Program sections did not
coordinate to assure that  only eligible costs were claimed.  They
had no procedures for the  two sections to mutually review and
certify that costs were accurate before claiming them against the
EPA cooperative agreement.

Financial Results of Audit

                                    Federal Share    Total Costs
Amount audited                         $15,399,411    $15,399,411
Amount accepted                        $11,776,463    $11,776,463
Ineligible costs9*                     $ 1,983,679    $ 1,983,679
Unsupported costs10                     $         0    $         0
Unnecessary/unreasonable costs11        $ 1,639,269    $ 1,639,269

*    In addition to the amount audited, $165,736 was overdrawn
     and therefore ineligible, resulting in total ineligible
     costs of $2,149,415.
     9  Costs questioned because of an alleged violation of  a
provision of a law, regulation,  contract,  grant,  cooperative
agreement, or other agreement or document governing the
expenditure of funds.

     10  Costs questioned because,  at the time of the audit,  they
were not supported by  adequate documentation and/or had not been
approved by responsible  program  officials.

     11  Costs questioned because tl .y were not necessary or not
reasonable.

-------
EPA Offics of Inspactor Goneral Annual Suporfund Raport to tho Conarass for Fiscal 1990	15

Recommendations

     We recommended that EPA Region 9:

     •    Disallow the ineligible  costs questioned for Federal
          participation, and recover the  Federal  share of these
          costs.

     •    Assess the eligibility of the unreasonable costs in the
          report.  In this respect, the Region should assure
          that:  (1) the proper laboratory  testing procedures
          were used to analyze samples taken from the
          Stringfellow site; and  (2) the  equipment rental costs
          charged to the project were reasonable  and necessary.

     •    Suspend all payments to  DHS-TSCP  for its direct labor,
          fringe and indirect costs under the agreement until it
          has demonstrated that it distributes labor charges on
          the basis of actual and  not predesignated charges.

     •    Advise DHS-TSCP of its failure  to meet  the minimum
          regulatory standards necessary  to qualify as a
          responsible grantee, and establish procedures to
          follow-up on DHS-TSCP's  actions to meet these
          standards.

     •    Assure correction of the financial management
          weaknesses noted in the  report.

Agency Response

     In response to the audit report, EPA Region  9 indicated:

     •    DHS-TSCP had prepared an adequate procedure for FSR
          preparation and review.

     •    DHS-TSCP now had two full-time  accountants working on
          accounting and reporting of Federal funds; its Program
          Audits Unit will perform periodic reviews to insure
          that FSR preparation and Letter of Credit drawdown
          procedures are being followed;  and it had formed a work
          group to recommend corrective actions on problems
          related to financial management and grant
          administration.

     •    DHS-TSCP accounting and  program staff began meeting
          regularly to review the  costs being charged against the
          cooperative agreement.

     •    DHS-TSCP implemented the CALSTARS accounting system and
          made several changes to  its  labor distribution system.

-------
EPA Office of Inspector General Annual Sunarfund Report to the Congress for Fiscal 1990	16

          One  change allows direct  charging of the tine of
          clerical, supervisory  and certain administrative staff.

     •    EPA  and DBS established a Memorandum of Understanding
          which provided a framework  for  the review of Superfund
          procurement actions, and  specifically addressed cost
          and  price analysis  requirements.

     •    It required DHS-TSCP to designate a liaison to
          expeditiously resolve  all audit issues,  and submit an
          audit plan relating to the  risk areas identified in the
          EPA  audit.

     •    DHS-TSCP will account  for costs on a project basis
          according to EPA regulations  and guidance.

     •    It required DHS-TSCP to establish a centralized filing
          system for site-specific  files.

     •    It required DHS-TSCP to submit  a corrective action plan
          to provide supporting  documentation on labor
          distribution and cost  categories for past financial
          management records.

     •    DHS-TSCP submitted  an  indirect  cost rate proposal for
          the  State's 1987-88 fiscal  year.

     •    It required DHS-TSCP to develop both a charter and
          annual audit plan to review areas of high audit risk.

     •    Found certain costs to be ineligible,  deferred some
          costs for further review, and required additional
          documentation from  DHS-TSCP on  other costs so that it
          could make a determination.   It required repayment of
          $1,372,356 from DHS.

     •    Would make a determination  whether the State meets
          requirements of a responsible grantee based upon
          corrective action plans it  required the State to
          submit.

CALIFORNIA STATE WATER RESOURCES CONTROL BOARD

Scope and Objectives

     The California State Controller  performed on our behalf an
interim audit  of a cooperative agreement  with the California
State Water Resources Control Board (SWRCB)  for response
activities at  South Bay area  sites.   The  Regional Water Quality
Control Board  (RWQCB) performed  much  of the work under the
cooperative agreement.  The audit objectives were to determine:

-------
EPA Office of Inspector General Annual Suoerfund Report to the Congress for Fiscal 1990	17

a.   Eligibility of costs claimed;

b.   Adequacy of the program management of  the SWRCB and the
     RWQCB; and

c.   Adequacy of the SWRCB's accounting and financial management
     system.

     The audit covered costs claimed by SWRCB  from  September 27,
1985 through September 30, 1989.

Findings

1.   RWQCB Needs Written Guidance  for  Site  Inspections

     RWQCB inspectors do not have  written guidance  on the scope
or the methods for conducting site inspections.   Adequate site
inspection guidance is essential to ensure  thorough and complete
site inspections.

2.   RWQCB Needs Improved Enforcement

     Evidence of RWQCB's inadequate site inspections included (a)
potentially responsible parties  (PRPs) using inadequate
containers with improper labeling  for  the storage of potentially
hazardous waste; (b) hazardous containers not  stored in
designated areas with restricted public access;  (c)  PRPs1
insufficient notification of the RWQCB about the disposition of
known and potentially hazardous materials;  (d)  no enforcement of
permit violations; and  (e) no field follow-up  by RWQCB on
problems identified during site visits.

3.   RWQCB Needs Improved Coordination with SWRCB.  Local Agencies
     and PRPs

     RWQCB did not verify that PRPs obtained permits needed for
the discharge of contaminants into the atmosphere,  soil
accumulation, soil disposal, and carbon filter handling and
disposal, as the cooperative agreement required.

4.   RWQCB Had Inadequate Staffing to  Perform  Site  Inspections

     RWQCB does not have enough site inspection staff to monitor
the toxic waste sites.  This severely  limits RWQCB's ability to
identify potential cleanup compliance  violations by PRPs,
consultants and contractors.

5.   SWRCB and RWQCB Failed to Define  Role  and Mission

     SWRCB and RWQCB did not clearly define the role and mission
of RWQCB in meeting State and Federal  regulations and cooperative

-------
EPA Office of Inspector General Annual Sunarfund Report to the Congress for Fiscal 1990	18

agreement requirements.  As  a  result,  both agencies had problems
in planning and managing available  staff.

6.   SWRCB Did Not Maintain  Detailed Accounting Records

     SWRCB did not have detailed  accounting records supporting
the costs it claimed on Financial Status Reports.   Therefore the
auditors could not determine whether the costs claimed were
incurred, reasonable and allocable  to  the  cooperative agreement.
We questioned all $2,903,899 claimed.

7.   SWRCB Did Not Maintain  a  Centralized  Filing System

     SWRCB did not establish a centralized filing system to
maintain complete file documentation and cost information by
site, as EPA required.

8.   SWRCB Did Not Request Approval for Its Indirect Cost Rate

     SWRCB did not develop indirect cost rate proposals covering
the effective date of the cooperative  agreement through 1988.  It
did not determine or identify  actual overhead costs annually.

9.   SWRCB Needs to Improve  Letter  of  Credit Drawdown Procedures

     SWRCB did no submit the required  reports or listings of
expenditures by site for EPA approval  before requesting funds.
EPA did not adequately monitor the  drawdown of funds by SWRCB.

Financial Results of Audit

                                    Federal Share    Total Costs
Amount audited                          $2,903,899     $2,903,899
Amount accepted                         $        0     $        0
Ineligible costs12                       $        0     $        0
Unsupported costs13                      $2,903,899     $2,903,899
Unnecessary/unreasonable costs14        $        0     $        0
     12  Costs questioned  because of an alleged violation of a
provision of a law, regulation,  contract,  grant,  cooperative
agreement, or other agreement or document  governing the
expenditure of funds.

     13  Costs questioned  because,  at the time of  the audit, they
were not supported by  adequate documentation and/or had not been
approved by responsible program  officials.

     14  Costs questioned  because they were not necessary or not
reasonable.

-------
EPA Office of Inspector General Annual Suoarfund Report to the Congress for Fiscal 1990	19

Recommendations

     We recommended that EPA Region 9:

     •    Disallow the questioned  costs  for Federal
          participation, and recover  the costs.

     •    Advise the SWRCB of its  continuing failure to meet the
          minimum regulatory standards to qualify as a
          responsible grantee,  and establish procedures to follow
          up on SWRCB actions to meet these standards.

     •    Assure that SWRCB and RWQCB correct the programmatic
          and financial management deficiencies.   The corrective
          actions needed include definition of agency roles and
          responsibilities, training  site inspectors, performing
          more inspections, compliance with financial
          recordkeeping requirements  and preparing proper
          indirect cost rate proposals for each fiscal year.

Agency Response

     Region 9 and the DIG were  still  resolving certain issues in
this report as we went to press.

GEORGIA DEPARTMENT OF NATURAL RESOURCES

Scope and Objectives

     We contracted with an IPA  to  perform an interim audit of a
cooperative agreement awarded to the  Georgia Department of
Natural Resources (GDNR) to identify  and rank hazardous waste
sites.  The objective of the audit was to determine whether costs
claimed were reasonable and allowable under the terms of the
cooperative agreement and applicable  regulations.  The audit
covered costs claimed by GDNR from October 1, 1985 through
September 30, 1989.

Findings

1.   GDNR Needs to Ensure that  Only Approved Travel Costs Are
     Charged to the Cooperative Agreement

     GDNR charged travel costs  for employees not approved under
the cooperative agreement.  We  questioned $5,813 of claimed costs
for this reason and because of  accounting errors.

2.   GDNR Needs to Comply with  Record Retention Requirements

     GDNR had destroyed all records for  costs incurred during its
fiscal year ending June 30, 1986.  Federal regulations require

-------
EPA Office of Inspector General Annual Suoerlund Report to the Congress for Fiscal 1990           20

recipients to maintain records for three years after submission
of the final Financial Status Report.

3.   GDNR Claimed  Unsupported Costs

     GDNR claimed  $8,435  of travel, equipment and other costs not
supported by source documentation.

Financial Results of Audit

                                     Federal Share    Total Costs
Amount audited                          $1,229,216     $1,229,216
Amount accepted                         $1,214,968     $1,214,968
Ineligible costs15                       $    5,813     $    5,813
Unsupported costs16                     $    8,435     $    8,435
Unnecessary/unreasonable  costs17        $        0     $         0

Recommendations

     We recommended that  EPA Region 4:

     •    Allow  GDNR to charge travel costs only for approved
          personnel.

     •    Require  GDNR to maintain records for three years after
          submission of the final Financial Status Report.

     •    Not participate in questioned costs of $14,248, and
          recover  funds due EPA.

Agency Response

     In response to the report, EPA Region 4 indicated:

     •    GDNR should comply with record retention requirements.

     •    $9,201 of questioned costs were ineligible and GDNR
          should deduct them from its next reimbursement request.
     13  Costs  questioned because of an alleged violation of a
provision of a law,  regulation,  contract, grant, cooperative
agreement, or  other  agreement or document governing the
expenditure of funds.

     16  Costs  questioned because, at the time of the audit, they
were not supported by  adequate documentation and/or had not been
approved by responsible program officials.

     17  Costs  questioned because they were not necessary or not
reasonable.

-------
EPA Office of Inspector General Annual Simerfund Report to the Congress for Fiscal 1990	21

KENTUCKY NATURAL RESOURCES AND ENVIRONMENTAL PROTECTION CABINET

Scope and Objectives

     We contracted with an  IPA to  perform an interim audit of a
cooperative agreement awarded to the Kentucky Natural Resources
and Environmental Protection  Cabinet  (KNREP)  to identify and rank
hazardous waste sites.  The audit  objectives were to determine
if:

a.   Costs claimed under  the  cooperative agreement were
     reasonable, allowable  and allocable to  the project; and

b.   The State's financial  management,  accounting, procurement,
     contract  administration  and property management systems
     included  adequate controls to assure that costs claimed were
     reasonable, allowable  and allocable to  the project.

     The audit covered costs  claimed by KNREP from March l, 1985
through March  31, 1989.

Findings

1.   KNREP Needs to Record  Costs By Site

     KNREP's timekeeping  system did not record hours worked by
site.  Therefore the site-specific hours could not be reconciled
with the formal time summaries.

2.   KNREP Claimed Costs  Prior to  Effective  Date of Agreement

     KNREP claimed payroll  costs for the last half of February
1985, even though the agreement was not effective until March
1985.

3.   KNREP Needs to Avoid Data Input Errors

     A data input error resulted in charging time spent by an
employee on another project to the cooperative agreement.

4.   KNREP Did Not Use Proper Purchase Authorization Procedures

     KNREP did not submit required cost-effectiveness comparisons
for Federally-funded equipment.

-------
EPA Office of Inspector General Annual Suoerfund Report to the Congress for Fiscal 1990	22
Financial Results of Audit
Amount audited
Amount accepted
Ineligible costs18
Unsupported costs19
Unnecessary/unreasonable costs20

Federal Share
$990,692
$985,988
$ 4,704
$ 0
$ 0

Total Costs
$990,692
$985,988
$ 4,704
$ 0
$ 0
Recommendations

     We recommended that EPA Region 4:

     •    Require  KNREP to implement a timekeeping system
          facilitating the tracking of hours by site as well as
          by activity and project.

     •    Require  KNREP to reconcile hours reported to EPA with
          the  formal timekeeping system and ensure that the data
          reported is accurate.

     •    Require  KNREP to implement procedures to ensure that
          costs  claimed were incurred within the project and
          budget period.

     •    Require  KNREP to develop and implement procedures
          reducing the potential for undetected data input
          errors.

Agency Response

     In response to the audit report, EPA Region 4 indicated:

     •    KNREP  is implementing an automated time accountability
          and  cost recovery system.

     •    Costs  incurred before award are unallowable.
     18  Costs questioned because of an alleged violation of a
provision of a  law,  regulation,  contract, grant, cooperative
agreement, or other  agreement or document governing the
expenditure of  funds.

     19  Costs questioned because, at the time of the audit, they
were not supported by  adequate documentation and/or had not been
approved by responsible program officials.

     20  Costs questioned because they were not necessary or not
reasonable.

-------
EPA Offlcft of Inspsctof Gonoral Annual Supflrfund Raport to ttio Conorsss for Fiscal 1990	23

     •    Costs  incurred  on other projects are ineligible.  KNREP
          agreed that  costs questioned  as incurred on another
          project were in error and will examine procedures to
          reduce the potential for  undetected errors.

     •    KNREP  will comply with cost-effectiveness comparison
          requirements during future procurement actions.

     •    KNREP  should reimburse EPA for $4,704 of questioned
          costs.

MISSISSIPPI DEPARTMENT OF ENVIRONMENTAL QUALITY

Scope and Objectives

     We contracted with an IPA to perform an interim audit of a
cooperative agreement  awarded to the Mississippi Department of
Environmental  Quality  (MDEQ)  to identify and rank hazardous waste
sites.  The objective  of  the audit  was  to determine whether costs
claimed were reasonable and allowable under the terms of the
cooperative agreement  and applicable regulations.  The audit
covered costs  claimed  by  MDEQ from  April 5, 1985 through
April 30, 1989.

Findings

1.   MDEQ Claimed Unapproved Travel Costs

     MDEQ claimed $1,593  in travel  costs for persons not approved
under the cooperative  agreement.

2.   Indirect  Costs May Need To Be  Adjusted

     MDEQ did  not have approved final indirect cost rates for
three periods  during which it charged provisional rates.  If the
final rates differ from the provisional rates,  it will need to
adjust the indirect costs charged.

-------
EPA Office of Inspector General Annual Suoerfund Report to the Congress for Fiscal 1990	24

Financial Results of Audit

                                     Federal Share    Total  Costs
Amount audited                            $435,850       $435,850
Amount accepted                           $434,257       $434,257
Ineligible costs21                         $  1,593       $   1,593
Unsupported costs22                       $      0       $       0
Unnecessary/unreasonable  costs23          $      0       $       0

Recommendations

     We recommended that  EPA Region 4:

     •    Require  MDEQ to charge travel costs only for personnel
          approved under  the cooperative agreement.

     •    Require  MDEQ to make any necessary adjustments to
          reflect  final approved indirect cost rates.

     •    Not  participate in ineligible costs of $1,593, and
          recover  funds due EPA.

Agency Response

     In response to the audit report, EPA Region 4 indicated:

     •    The  travel costs questioned were disallowed because
          they were not related to the program funded by the
          cooperative agreement.

     •    MDEQ should make the necessary adjustments to claimed
          costs if indirect cost rates are approved before
          project  closeout.
     21  Costs  questioned because of an alleged violation of  a
provision of a law,  regulation, contract, grant, cooperative
agreement, or  other  agreement or document governing the
expenditure of funds.

     22  Costs  questioned because, at the time of the audit,  they
were not supported by  adequate documentation and/or had not  been
approved by responsible program officials.

     23  Costs  questioned because they were not necessary or  not
reasonable.

-------
EPA Office of Inspector General Annual Sunarfund Report to the Congress for Fiscal 1990	25

NEW YORK STATE DEPARTMENT OF ENVIRONMENTAL CONSERVATION

Scope and Objectives

     We contracted with an IPA to perform an interim audit of a
cooperative'agreement  awarded to the New York State Department of
Environmental  Conservation (NYSDEC)  for remedial
investigation/feasibility study activities for three sites in New
York State:  Fulton Terminals in Fulton,  Clothier in Granby, and
Volney Landfill  in Volney.   The audit objectives were to
determine:

a.   The adequacy, effectiveness and reliability of procurement,
     accounting  and management controls exercised by NYSDEC in
     administering the cooperative agreement;

b.   NYSDEC1s  compliance with cooperative agreement provisions
     and Federal regulatory  requirements;  and

c.   The reasonableness,  allocability and allowability of costs
     claimed under the cooperative agreement.

     The audit covered costs claimed by NYSDEC from December 31,
1984 through March 31,  1989.

Findings

1.   Fulton Terminal Site

     NYSDEC claimed $60,991  of unsupported costs incurred without
a required subagreement or more than the approved budget.

2.   Clothier  Site

     NYSDEC claimed $158,009 of unsupported costs incurred
without adequate supporting  documentation, without a required
subagreement,  more than the  approved budget,  or without a needed
contract revision.

3.   Volnev Site

     NYSDEC claimed $71,897  of ineligible costs for unacceptable
analytical data, incurred after the cooperative agreement
expired, or outside the scope of the cooperative agreement.  We
also questioned  $2,135 of claimed costs as unsupported which were
more than the  approved budget or not adequately documented.

-------
EPA Offlca of liUDBCtof Ganaral Annual Suoarfund Report to thfl Congress for Fiscal 1990

Financial Results of Audit
Amount audited
Amount accepted
Ineligible costs24
Unsupported costs25
Unnecessary/unreasonable  costs26

Recommendations
Federal Share
   $1,609,172
   $1,316,140
   $   71,897
   $  221,135
   $        0
Total Costs
 $1,609,172
 $1,316,140
 $   71,897
 $  221,135
 $        0
     We recommended  that  EPA Region 2:

     •    Not fund the  ineligible costs.

     •    Evaluate the  appropriateness  of funding the unsupported
          costs.

Agency Response

     In response to  the audit report,  EPA Region 2 disallowed
$73,559 of claimed costs  and, based on  EPA payments, required
NYSDEC to refund $31,657.

NORTH CAROLINA DEPARTMENT OF HUMAN RESOURCES

Scope and Objectives

     We contracted with an IPA to perform an interim audit of a
cooperative agreement awarded to the North Carolina Department of
Human Resources  (NCDHR) to identify and rank hazardous waste
sites.  The objective of  the audit was  to determine whether costs
claimed were reasonable and allowable under the terms of the
cooperative agreement and applicable regulations.  The audit
covered costs claimed by  NCDHR from July 1, 1985 through Hay 31,
1989.
     24
        Costs questioned because of an alleged violation of a
provision of a  law,  regulation,  contract, grant, cooperative
agreement, or other  agreement or document governing the
expenditure of  funds.

     25  Costs questioned because, at the time of the audit, they
were not supported by  adequate documentation and/or had not been
approved by responsible program officials.

     26  Costs questioned because they were not necessary or not
reasonable.

-------
EPA Office of Inspector General Annual Sunerfund Report to the Congress for Fiscal 1990
          27
1.   NCDHR Needs to Comply with Federal Property Management
     Standards

     State accounting policies  did not comply with Federal
Property Management Standards.   They provided for reporting
equipment with a unit price  under $500 as supplies.  EPA
regulations require that  recipients list all real and personal
property purchased under  cooperative agreements.

2•   Indirect Costs May Need To Be Adjusted

     The cognizant Federal agency had not approved NCDHR's final
indirect cost rate for the fiscal year ending June 30, 1989.  If
that agency approves a different rate, NCDHR must adjust claimed
costs accordingly.

3.   NCDHR Claimed Unallowable  Costs

     NCDHR could not provide supporting documents for $1,083 of
claimed supply costs.

Financial Results of Audit
                                     Federal Share
                                        $1,873,445
                                        $1,872,362
                                        $    1,083
                                        $        0
                                        $        0
Total Costs
 $1,873,445
 $1,872,362
 $    1,083
 $        0
 $        0
Amount audited
Amount accepted
Ineligible costs77
Unsupported costs21
Unnecessary/unreasonable  costs29

Recommendations

     We recommended that  EPA Region 4:

     •    Require the  State  to implement procedures to accumulate
          data required by Federal Property Management Standards.
     27  Costs questioned because of an alleged violation of a
provision of a  law, regulation,  contract,  grant, cooperative
agreement, or other agreement or document governing the
expenditure of  funds.

     28  Costs questioned because,  at the time of the audit, they
were not supported by  adequate documentation and/or had not been
approved by responsible  program  officials.

     29  Costs questioned because they were not necessary or not
reasonable.

-------
EPA Office of Inspector General Annual Suoerfund Report to the Congress for Fiscal 1990	28

          These  should include accounting records identifying
          items  acquired  as either  expendable or nonexpendable
          property.

     •    Require NCDHR to make any necessary adjustments to
          reflect approved final indirect cost rates.

     •    Not participate in ineligible costs of $1,083, and
          recover funds due EPA.

Agency Response

     In response to  the audit report,  EPA Region 4 indicated:

     •    NCDHR  used an approved indirect cost rate and therefore
          did not need to adjust claimed costs.

     •    NCDHR  provided  documentation to support $913 of the
          $1,083 questioned.   NCDHR should deduct the ineligible
          balance of $170 from its  next payment request.

OREGON DEPARTMENT OF ENVIRONMENTAL QUALITY

Scope and Objectives

     We contracted with an IPA to perform a final audit of the
core program cooperative  agreement  awarded to the Oregon
Department of Environmental Quality (DEQ).  The audit objectives
were to determine:

a.   The reasonableness,  allocability  and allowability of costs
     claimed under the cooperative  agreement;

b.   The adequacy, effectiveness and reliability of procurement,
     accounting  and  management controls exercised by DEQ in
     administering the cooperative  agreement; and

c.   DEQ's compliance with cooperative agreement provisions and
     Federal regulatory requirements.

     The audit covered costs claimed by DEQ from December 17,
1987 through January 31,  1989.

Findings

1.   Internal Controls Need Strengthening

     DEQ needs to strengthen its internal financial management
controls to comply with Federal regulations.   We found (a) one
instance of an incorrect  allocation of a retroactive pay raise
resulting in overcharging the cooperative agreement; (b) an

-------
EPA Office of hiinector General Annual Suoerfund Report to the Congress for Fiscal 1990	29

inequitable allocation  of  employee  leave and benefit costs; (c)
direct charging of secondary  level  supervision; (d) lack of
verification of accounting system entries;  and (e)  lack of
reconciliation of the travel  costs  charged  with employee
timecards.

2.   Inadequate Inventory  Control Systems

     DEQ needs to improve  its inventory control systems to comply
with Federal regulations.   We found (a)  five of 22 pieces of
equipment purchased under  the cooperative agreement did not have
State property tags, and  (b)  DEQ's  centralized inventory for data
processing equipment did not  contain State  property of inventory
tag numbers.

3.   DEO Claimed Ineligible Costs

     We questioned $85,293 as ineligible because (a) a computer
malfunction resulted in personnel costs being overcharged; (b)
DEQ inequitably allocated  employee  leave and benefit costs; (c)
DEQ miscoded timesheet  data into the accounting system; (d) DEQ
directly charged costs  for secondary level  supervision; and (e)
DEQ used an indirect cost  rate not  approved by EPA.

Financial Results of Audit

                                     Federal Share    Total Costs
Amount audited                            $223,919       $235,704
Amount accepted                           $142,890       $150,411
Ineligible costs30                         $  81,028       $ 85,293
Unsupported costs31                        $       0       $      0
Unnecessary/unreasonable costs32          $       0       $      0
     30  Costs questioned  because of an alleged violation of a
provision of a  law, regulation,  contract,  grant,  cooperative
agreement, or other agreement or document  governing the
expenditure of  funds.

     31  Costs questioned  because,  at the time of the audit, they
were not supported by  adequate documentation and/or had not been
approved by responsible program officials.

     32  Costs questioned  because they were not necessary or not
reasonable.

-------
EPA Office of Inspector General Annual Simerfund Report to the Congress for Fiscal 1990	30

Recommendations

     We recommended that  EPA Region 10:

     •    Require  DEQ to  make the following improvements to their
          financial management system:

          1.    Improve the data processing interface between the
                DEQ personnel and payroll systems.

          2.    Establish  procedures to ensure prompt notification
                of  personnel actions (e.g., retroactive salary
                adjustments),  verify entries into DEQ's electronic
                payroll system,  verify costs charged to the
                cooperative agreement to the source documents, and
                reconcile  travel costs to timesheets.

          3.    Develop a  fringe benefit rate for application to
                direct labor costs, or allocate employee leave and
                fringe benefit costs on an equitable basis as
                required by OMB circular A-87.

          4.    Include the costs of secondary level supervision
                in  the indirect cost rate.

     •    Require  DEQ to  make the following improvements to their
          property control system:

          1.    Implement  procedures to make sure it tags all
                nonexpendable equipment when received.

          2.    Centralize the property management responsibility
                within one functional area.

          3.    Establish  procedures to include property tag
                numbers in the central inventory.

     •    Disallow questioned costs for Federal participation.

     •    Recover  $81,028 of Federal funds paid exceeding the
          amount accepted in the audit report.

Agency Response

     This audit was not yet resolved as we went to press.

-------
EPA Offlca of Inspector Ganaral Annual Suoarfund Report to tha Conorass for Fiscal 1990	31

SOUTH ADAMS COUNTY, COLORADO

Scope and Objectives

     We contracted with an IPA to perform two  interim audits and
one final audit of cooperative agreements awarded to the South
Adams County Water and Sanitation District  (SACWSD)  for response
to the Rocky Mountain Arsenal Superfund  site.   The  audit
objectives were to determine:

a.   The reasonableness, allocability  and allowability of costs
     claimed under the cooperative  agreement;

b.   SACWSD's compliance with cooperative agreement provisions
     and Federal regulatory requirements; and

c.   The adequacy, effectiveness and reliability of procurement,
     accounting and management controls  exercised by SACWSD in
     administering the cooperative  agreement.

     The audit covered costs claimed by  SACWSD from April 7, 1986
through July 25, 1989.

Findings

1.   SACWSD*s Contract Procurement  System Needed Improvement

     SACWSD did not have a formal procurement  system complying
with Federal regulations or cooperative  agreement special
conditions.  It did not have written procurement policies and
procedures, and did not follow consistent procurement practices.
SACWSD did not  (a) properly procure all  contracts,  (b)  properly
maintain procurement documentation, and  (c) include all required
subcontract provisions in executed  contracts.   It did not sign an
agreement for one contract.  As a result, SACWSD could not be
sure it awarded contracts to the best  offerers or that awarded
contracts were fair and reasonable.

2.   SACWSD Needed to Improve Chancre Order  Approval Procedures

     SACWSD approved change orders  containing  items not needed to
operate the water treatment facility.

3.   Accounting System Deficiencies

     SACWSD's system to account for cooperative agreement costs
was deficient.  It did not adequately  support  labor costs, base
labor costs claimed on actual costs, reconcile amounts reported
to the  reneral ledger, or account  for  costs by type of expense.

-------
EPA Office of Inspector General Annual Sunerfund Report to the Congress for Fiscal 1990	32

4.   SACWSD's Controls Over  Contractor  Billing Needed Improvement

     SACWSD did not pay contractors in  accordance with contract
provisions.  SACWSD claimed  contract  costs specifically
identified as unallowable  by EPA.   Payments to two contractors
exceeded contract  limitations.

5.   SACWSD's Property Management  System Needed Improvement

     SACWSD's property management  system did not fully comply
with Federal regulations.  In addition,  SACWSD did not obtain
required EPA approval before purchasing equipment.

6.   SACWSD Claimed Unsupported. Ineligible and
     Unnecessary/Unreasonable Costs

     SACWSD claimed:

     (a)  Engineering expenses,  force account costs and equipment
          costs that were  (i)  unsupported, (ii) not approved
          before being incurred, or (iii)  not procured in
          compliance with  Federal  regulations;

     (b)  Change order costs not needed to operate the water
          treatment facility;  and

     (c)  Ineligible engineering costs  exceeding contract limits
          or incurred without a  contract.

Financial Results of Audit

                                    Federal Share    Total Costs
Amount audited                         $10,717,257    $11,075,083
Amount accepted                        $ 7,285,267    $ 7,608,650
Ineligible costs"                      $    65,431    $    65,759
Unsupported costs34                    $ 3,159,365    $ 3,184,113
Unnecessary/unreasonable costs35        $   207,194    $   216,561
     33  Costs questioned because of an alleged violation of a
provision of a  law,  regulation,  contract,  grant,  cooperative
agreement, or other  agreement or document  governing the
expenditure of  funds.

     34  Costs questioned because,  at the time of the audit, they
were not supported by  adequate documentation and/or had not been
approved by responsible  program officials.

     33  Costs questioned because they were not necessary or not
reasonable.

-------
EPA Offlcft of hupBCtOf GOTBTB! Annual Supoffund Roport to the Conor BM for Fiscal 1990	33

Recommendations

     We recommended that EPA  Region 8:

     •    Require EPA review  and  approval of all SACWSD
          procurement actions until the SACWSD procurement system
          fully complies with Federal  regulations.

     •    Direct SACWSD to  improve  its procurement and property
          management systems  to meet the requirements of Federal
          regulations and cooperative  agreement special
          conditions.

     •    Review all change orders  approved by SACWSD to
          determine the need,  allowability,  reasonableness and
          allocability of costs claimed.

     •    Recompute payroll costs claimed using actual costs
          incurred.

     •    Require SACWSD to (1) maintain timesheets,  signed by
          the  employee and  reviewed by the supervisor, to support
          payroll costs;  (2)  periodically reconcile financial
          reports with the  general  ledger;  (3)  establish controls
          to make sure contractors  bill according to contract
          terms; and  (4) document unsupported costs questioned.

     •    Disallow the ineligible costs questioned for Federal
          participation, and  recover Federal funds paid exceeding
          the  amounts accepted in the  audit report.

Agency Response

     As this report went to press,  EPA Region 8 had not completed
resolution of  the audit findings.   An  approved deviation to the
procurement requirements will clear $3,129,153 of the questioned
costs.

TEXAS WATER COMMISSION - BIOECOLOGY SITE

Scope and Objectives

     We performed an interim  audit  of  a cooperative agreement
awarded to the Texas Department of  Water Resources,  the
predecessor agency to the Texas Water  Commission (TWC).  EPA
awarded the agreement for the performance of remedial activities
at the BioEcology Disposal  Site in  Grand Prairie, Texas.  Our
audit objectives were to determine  if:

a.   Costs claimed under the  cooperative agreement were
     reasonable, allowable  and allocable to the project; and

-------
EPA Office of inspector General Annual Suoerfund Report to the Congress for Fiscal 1990	34

b.   The State's  financial management, accounting, procurement,
     contract  administration and property management systems
     included  adequate controls to  assure that costs claimed were
     reasonable,  allowable and allocable to the project.

     The audit covered costs claimed by TWC from March 1, 1986
through June 30,  1989.

Finding

TWC Did Not Maintain Summary Records of Negotiation

     A prior audit  report recommended that TWC maintain a summary
record of negotiation on  all procurements over $10,000.  TWC had
not implemented this recommendation.
Financial Results of Audit
Amount audited
Amount accepted
Ineligible costs36
Unsupported costs37
Unnecessary/unreasonable costs38

Recommendation
Federal Share
   $3,902,626
   $3,902,626
   $        0
   $        0
   $        0
Total Costs
 $6,192,409
 $6,192,409
 $        0
 $        0
 $        0
     We recommended  that EPA Region 6 require TWC to prepare a
summary record  of  negotiations setting forth the principal
elements of negotiations.   This record should contain enough
detail to reflect  the significant considerations controlling the
establishing of price and other terms of the contract.

Agency Response

     In response to  the audit report, EPA Region 6 indicated TWC
would include the  summary record of negotiations in contract
files.
     36  Costs questioned because of an alleged violation of a
provision of a  law,  regulation,  contract, grant, cooperative
agreement, or other  agreement or document governing the
expenditure of  funds.

     37  Costs questioned because, at the time of the audit, they
were not supported by  adequate documentation and/or had not been
approved by responsible program officials.

     38  Costs questioned because they were not necessary or not
reasonable.

-------
EPA Office of Inspector General Annual Suparfund Report to the Congress for Fiscal 1990	35

TEXAS WATER COMMISSION - HIGHLANDS SITE

Scope and Objectives

     We contracted  with an IPA to perform an interim audit of  a
cooperative'agreement awarded to the Texas Water Commission
(TWC).  EPA awarded the agreement for the performance of remedial
activities at  the Highlands Acid Pit site in Harris County,
Texas.  The objective of the audit was to determine whether costs
claimed were reasonable and allowable under the terms of the
cooperative agreement and applicable regulations.  The audit
covered costs  claimed by TWC from September 30, 1982 through
September 30,  1989.

Finding

TWC Claimed Ineligible Indirect Costs

     TWC claimed $9,373 of indirect costs exceeding the amount
authorized under approved indirect cost rates.

Financial Results of Audit
Amount audited
Amount accepted
Ineligible costs39
Unsupported costs40
Unnecessary/unreasonable costs41

Recommendation
Federal Share
   $5,877,842
   $5,868,488
   $    9,354
   $        0
   $        0
Total Costs
 $6,472,050
 $6,462,677
 $    9,373
 $        0
 $        0
     We recommended that EPA Region 6 not participate in the
ineligible costs,  and recover funds due EPA.
     39
        Costs questioned because of an alleged violation of a
provision of a  law,  regulation,  contract, grant, cooperative
agreement, or other  agreement or document governing the
expenditure of  funds.

     40  Costs questioned because, at the time of the audit, they
were not supported by  adequate documentation and/or had not been
approved by responsible program officials.

     41  Costs questioned because they were not necessary or not
reasonable.

-------
EPA Office of Inspector General Annual Suoerfund Report to the Congress for Fiscal 1990	36

Agency Response

     In response  to the audit report, EPA Region  6 obtained  a
refund of $2,656  from TWC.

TEXAS WATER COMMISSION - SIKES SITE

Scope and Objectives

     We performed an interim audit of a cooperative agreement
awarded to the  Texas Department of Water Resources, the
predecessor agency to the Texas Water Commission  (TWC).  EPA
awarded the agreement for the performance of remedial  activities
at the Sikes Disposal Site in Crosby, Texas.  Our audit
objectives were to determine if:

a.   Costs claimed under the cooperative agreement were
     reasonable,  allowable and allocable to the project; and

b.   The State's  financial management, accounting, procurement,
     contract  administration and property management systems
     included  adequate controls to assure that costs claimed were
     reasonable,  allowable and allocable to the project.

     The audit  covered costs claimed by TWC from March 1,  1986
through June 30,  1989.

Finding

TWC Did Not Maintain Summary Records of Negotiation

     Prior audit  reports recommended that TWC maintain a summary
record of negotiation on all procurements over $10,000.  TWC had
not implemented this recommendation.

-------
EPA Office of Inspector General Annual Stmarfund Report to the Congress for Fiscal 1990
                            37
Financial Results of Audit
Amount audited
Amount accepted
Ineligible costs42
Unsupported costs43
Unnecessary/unreasonable  costs44

Recommendation
Federal Share
   $1,162,032
   $1,155,349
   $    6,683
   $        0
   $        0
Total Costs
 $1,162,032
 $1,155,349
 $    6,683
 $        0
 $        0
     We recommended  that EPA Region 6 require TWC to prepare a
summary record of  negotiations setting forth the principal
elements of negotiations.   This record should contain enough
detail to reflect  the  significant considerations controlling the
establishing of price  and other terms of the contract.

Agency Response

     In response to  our audit report, EPA Region 6 indicated TWC
would include the  summary record of negotiations in contract
files.  TWC also refunded $6,683.00 to EPA.

REGION 8 ADMINISTRATION OF SUPERFUND COOPERATIVE AGREEMENTS - FOLLOW-
UP REVIEW

Scope and Objectives

     We conducted  a  special review of EPA Region 8's corrective
actions taken in response to the audit findings and
recommendations of our prior audit of Region 8's Administration
of Superfund Cooperative Agreements (Audit Report No. E5EH7-08-
0005-71992), dated September 30, 1987.  The specific objectives
of our review were to  determine whether:

a.   Region 8 management took the corrective actions indicated in
     its response  to the audit recommendations;
     42
        Costs questioned because of an alleged violation of a
provision of a  law,  regulation,  contract, grant, cooperative
agreement, or other  agreement or document governing the
expenditure of  funds.

     43  Costs questioned because,  at the time of the audit, they
were not supported by  adequate documentation and/or had not been
approved by responsible program officials.

     44  Costs questioned because they were not necessary or not
reasonable.

-------
EPA Office of Inspector General Annual Suoerfund Report to the Congress fof Fiscal 1990	38

b.   Region 8 implemented the corrective actions  in  accordance
     with the Region's action plan and milestone  dates;  and

c.   The actions were effective in correcting  the conditions
     addressed in the audit report.

     Due to its limited scope, the review was  not an audit
following the Government Auditing Standards  (1988 Revision)
issued by the Comptroller General of the United States.

Findings

1.   Pre-Remedial Program Continues to Require Corrective  Actions

     Finding No. 1 of the audit included recommendations that  the
Region improve the (i) timeliness and  effectiveness  of pre-
remedial functions performed under cooperative agreements;  and
(ii) management of National Priorities List  (NPL) sites  included
in cooperative agreements to assure the timely performance of
actions.  The Region agreed with the recommendations.  Our
follow-up review showed the Region had begun timely  action to
correct the conditions leading to the  first recommendation, but
its actions were not fully effective.

     The Region issued "Procedures for Managing Superfund
Cooperative Agreements."  However, the procedures were not fully
effective because the Region did not disseminate  them to all
applicable Regional staff and provide  appropriate training on
their application.  As a result, two of three  Regional Project
Managers (RPMs) we interviewed were not adequately documenting
their evaluations of State pre-remedial work products.

     The Region had agreed to meet the SARA requirements for
completion of preliminary assessments  and site inspections (Sis).
However, we found that 25 (30 percent) of the  84  sites we
reviewed had not met the SARA goal for completion of an  SI.  The
Region had also committed to perform several site-specific
activities by certain dates.  It did not meet  some of these
commitments.

2.   Regional Administration of Cooperative Agreements Needs
     Strengthening

     Finding No. 2 of the audit included recommendations that  the
Region:  (i) take a more active role in the monitoring of  the
recipients' cooperative agreement activities;  (ii) develop
written procedures to help the RPMs perform their administrative
responsibilities;  (iii) assure that the recipients have  the
necessary qualifications to meet the requirements of 40  CFR
30.301 before the award of a cooperative agreement;  (iv) require
that recipients prepare site-specific  schedules for  all  NPL

-------
EPA Office of Inspector General Annual Simerfund Report to the Congress for Fiscal 1990	39

sites; (v) place additional emphasis on updating  and maintaining
the CERCLIS data base; and  (vi) continue to coordinate with the
State of Utah to develop an effective working  relationship.   The
Region agreed with these recommendations.

     Our follow-up review showed that Region 8 implemented
corrective actions on five of the  six recommendations which
effectively addressed the conditions identified in the audit
report.  However, actions on the first recommendation had not
been fully successful.  In response to that recommendation,  the
Region emphasized the value of executing Superfund Memorandums of
Agreement (SMOAs) with the States.  The Region agreed to have
three SMOAs in place and three others in negotiations by the end
of fiscal 1988.  However, as of our review more than a year after
that time, only the State of Utah  had an operational SMOA.

3.   Oversight of Recipient Financial Management  Needs
     Improvement

     Finding No. 3 of the audit included recommendations that the
Region:   (i) prepare written procedures for use in administering
the Letter of Credit method of reimbursement;  and (ii) improve
review of recipient accounting systems.  The Region agreed with
the recommendations.

     Our follow-up review showed that Region 8 timely implemented
its proposed corrective actions.   However, their  actions were not
fully successful in correcting the deficiencies which led to the
first recommendation.  We found that the States continued to
submit the Quarterly Cash Transaction Reports  (SF-272S)  late.  We
found that States submitted 11 (38 percent) of the 29 SF-272s we
reviewed late.

4.   Lack of Corrective Action Tracking System

     Our follow-up review also showed the Region  did not have an
effective system for tracking the  implementation  of corrective
actions agreed to in response to audit report  recommendations.
As a result, Regional management had no assurance of timely,
complete and effective implementation of corrective actions.   The
Region had used the Agency's automated follow-up  system,  which
was terminated in early 1988 because it was inadequate.   The
Region stated it would include all outstanding actions from prior
OIG audit reports when EPA fully implemented its  new audit
tracking system.

-------
EPA Office of Inspector General Annual Siinarfund Report to the Congress for Fiscal 1990	40

Recommendations

     We recommended that  EPA Region 8:

     •    Prepare and  implement an  updated action plan which
          addresses each  of the incomplete corrective actions in
          Audit Report NO.  E5EH7-08-0005-71992.

     •    Enter the corrective action plan from our follow-up
          review into  the Management Audits Tracking System and
          monitor progress  until all corrective action items are
          complete.

Agency Response

     In response to our draft report, EPA Region 8 stated it:

     •    Sent its  comments and findings in a transmittal letter
          with every EPA  review of  State prepared pre-remedial
          deliverables.

     •    Requested each  State in the Region to initiate a SMOA
          with EPA, and offered funding to each State to develop
          and negotiate these agreements.

     •    Implemented  the Agency's  new Management Audit Tracking
          System.

     In response to our final report, EPA Region 8 further stated
it:

     •    Developed standard operating procedures for cooperative
          agreement oversight responsibilities.

     •    Inserted  language in the  performance agreements of Site
          Assessment Managers establishing objectives for the
          management of State site  assessment programs.

     •    Instituted a program to provide training to the site
          assessment staff  twice a  year.

     •    Would complete  the backlog of pre-SARA site inspections
          by the end of October 1991.

-------
EPA Offlca of liMMCtor Gonaral Annual Suporfund Raport to tho Congress for Fiscal 1990	41

         REMEDIAL INVESTIGATIONS AND FEASIBILITY STUDIES

     In fiscal 1990, we issued four reports on remedial
investigation/feasibility study  (RI/FS) reviews.  All  of the
reports were issued as technical reports by the OIG Technical
Assistance Staff.  The reports did not contain recommendations to
EPA management, and required no response from  the Agency.   The
reviews are summarized below.

BAIRD & McGUIRE COMPANY SITE. HOLBROOK. MASSACHUSETTS

Scope and Objectives

     Our review objectives of the RI/FS performed for  the  Baird &
McGuire Company site in Holbrook, Massachusetts,  were  to:

a.   review the EPA-approved work plan for accuracy and
     completeness of the RI/FS;

b.   determine if the work plan omitted essential data
     requirements which delayed the completion of the  remedial
     investigation  (RI);

c.   determine if professional care was used by both EPA and the
     contractor in the work plan preparation,  review and approval
     process; and

d.   determine if the costs and hours  proposed by the  contractor
     and its subcontractors were reasonable for the tasks  added
     after locating the dioxin.

     To perform this review, OIG technical staff  reviewed  site
documents, visited the site and discussed the  site with  the
site's Remedial Project Manager and On-Scene Coordinator.

Findings and Conclusions

1.   The Work Plan Was Not Thorough

     The RI, as first conducted, did not meet  its own  objectives
and did not appear to have a comprehensive review of all
documents related to the site to ensure that a thorough  and
complete work plan was developed.  Therefore,  additional work was
needed for these "unresolved" issues.  This caused the entire
project to take longer than would have been necessary  had  the
work plan been prepared more thoroughly.

     The lack of a thorough work plan  resulted in the  preparation
of an incomplete Health and Risk Assessment for Presence of
Pesticides on Building Walls and Floors.  An additional  site
reconnaissance and sampling trip by the contractor was required

-------
EPA Office of Inspector General Annual Suoerfund Report to the Congress for Fiscal 1990          42

to prepare an  addendum to that assessment.   This resulted in both
a time delay and an increase  in cost.

2.   Wetlands  Issue Not Completely  Examined  In a Timely Manner

     Contamination in site wetlands was  not  completely examined
in the original RI for the site.  This data  gap was filled in
through a Phase II Addendum RI.  The  impact  of low levels of
contaminants to the environment, especially  the wetlands, was not
fully discussed in either the Feasibility Study (FS)  or the
Record of Decision (ROD) for  the site.

3.   Dioxin Contamination Not Investigated in a Timely Manner

     Although  evidence indicating the presence of dioxin was
available before the RI was performed, no dioxin samples were
taken during the original RI.  Later, sampling had to be
postponed and  health and safety requirements modified because of
the presence of dioxin.

4.   Coordination Between Removal and Remedial Programs Was Good

     The site  had a transition from removal  action to remedial
activities.  During this transition,  there was good coordination
between the removal and remedial programs.

5.   Field Pilot Study Not Done During RI/FS

     The Agency's Guidance on Remedial Investigations and
Feasibility Studies Under CERCLA  (June 1985)  indicates that bench
and pilot studies should be done,  if  at  all  possible, during the
RI.  The site  required a field pilot  study of the treatment of
pumped contaminated groundwater.  Although the need for the study
was known, it  was not done during the RI/FS  and had to be done
later.

IRON HORSE PARK SITE. NORTH BILLERICA, MASSACHUSETTS

Scope and Objectives

     Our review objectives of the RI/FS  performed for the Iron
Horse Park site in North Billerica, Massachusetts, were to:

a.   determine if the project cost  increases during the RI/FS
     were attributable to EPA's decision to  expand the work plan
     activities for the RI/FS; and

b.   determine if the contractor used due professional care in
     preparing the final work plan  and its amendments which
     resulted  in an increase  in costs from $610,837 to
     $1,326,000.

-------
EPA Office of Inspector General Annual Simerfund Report to the Congress for Fiscal 1990	43

     To perform this review,  OIG  technical staff reviewed site
documents and discussed the site  with the EPA project officer.

Findings and Conclusions

1.   Phased-Operable Unit Approach  Used Was Appropriate

     The phased operable unit approach used for the site is a
viable alternative sanctioned by  statute and regulation.  It was
appropriate for use at this site  due  to the complexity of the
site.

2.   Final Work Plan and Amendments Were Appropriate

     The final work plan for  the  RI/FS was based on review of
existing information, consistent  with the Agency guidance and
under the direction of the EPA project manager.  The five
amendments to this plan were  directed toward revising the scope
and objectives of the site remedial activities.  Although some of
the additional or revised tasks may have overlapped, this is
sometimes unavoidable at a site this  complex.

3.   Cost of the RI/FS Was Reasonable

     Cost overruns for remedial activities at Superfund sites are
not uncommon given the magnitude  of uncertainties involved in RIs
and the lack of available information.   Considering the magnitude
of environmental sampling and analysis efforts at the site, the
cost of $1.3 million falls within the normal range.

NYANZA CHEMICAL SITE, ASHLAND. MASSACHUSETTS

Scope and Objectives

     Our review objectives of the RI/FS performed for the Nyanza
Chemical site in Ashland, Massachusetts,  were to:

a.   determine if the RI/FS formed  an adequate basis for
     selection of a remedial  action;  and

b.   determine if EPA Region  1 took all reasonable and necessary
     measures to assure that  the  contractor carried out the RI/FS
     as required.

     The scope of our review  was  limited to Phase I of the RI/FS
for the site.

-------
EPA Office of Inspector General Annual Simerfund Report to the Congress for Fiscal 1990	44

findings and Conclusions

1.   The RI Failed to Locate  Significant Areas of Contamination

     Both a 1980 State report and  a 1982 aerial photo
interpretation report indicated a  rectangular  basin which  the
report indicated had been a collection tank which held
wastewater.  However, the RI  which began in 1983 did not include
any sampling in the basin area.  Later sampling found the
presence of organic contaminants in that area  at high
concentrations.  As a result, an emergency removal action  was
conducted.

     The RI/FS also failed to locate 250 buried drums in a sludge
disposal area.  Six years later, the remedial  contractor
uncovered these drums and a removal action was conducted.   The
magnetometer used in the RI/FS in  1983 was capable of detecting
buried drums.

2.   Inappropriate Sampling Methods Led to Erroneous Conclusions
     and Additional Expenditures to Characterize the Site

     Several significant errors in sampling strategy greatly
reduced the value of the Phase I RI/FS.  These errors included
compositing soil samples inappropriately, use  of the wrong type
of monitoring well, failure to filter  groundwater samples,  and
failure to sample adequately  to obtain sludge  volume estimates.

     The contractor's methodology  for  66 soil  samples discussed
in the RI was to take them as composites over  a depth of 68
inches.  The use of this technique is  highly questionable  where
the depth and thickness of the sludge  deposits varies greatly
from sample to sample.  The technique  failed to give an
indication of the amount of contaminated material which needed to
be removed or of the concentrations of contaminants in  the
sludge.  As a result, additional sampling was  required  after the
completion of the RI/FS.

     The contractor used a monitoring  well with a single 17-foot
screen in an area where the presence of nitrobenzene was
suspected.  Because nitrobenzene is a  dense non-aqueous phase
liquid, it sinks through the  groundwater and moves along any
impervious layer or the bedrock underlying the aquifer.
Therefore, a discrete screen  interval  for that area would  be
needed to properly sample for nitrobenzene.  Samples collected
from that well indicated very low  levels of nitrobenzene  (less
than 0.4 mg/1.  More than two years later, EPA's Emergency
Response Team constructed a monitoring well immediately adjacent
to the contractor's well.  The new well was equipped with  a short
screen length at bedrock level.  Samples from  this new  well

-------
EPA Office of Inspector General Annual Suoerfund Report to tha Congress for Fiscal 1990	45

indicated gross contamination with nitrobenzene  (more than  54
mg/1).  As a result, a removal action was initiated.

     Contractor staff did not filter the first two rounds of
groundwater samples collected during the RI.  As  a result,  the
reported concentrations of heavy metals included  the metals
naturally present in the suspended solids in the  samples as well
as in the groundwater.  Since such particulate matter does  not
move with the groundwater, this resulted in sample results
indicating much higher metal concentration than actually existed
in the groundwater.  Therefore, the discussion of heavy metal
contamination was seriously flawed and the costs  associated with
the collecting and analyzing the two rounds of samples produced
information of questionable value.  A third round of samples was
collected which was filtered, but the results from this sampling
were not available for the RI report.

     The contractor failed to sample seven of the eight areas
identified as sludge and fill deposits.  Instead, it relied on
results from an earlier investigation by a different contractor,
despite the fact that both EPA and the State were critical  of the
methodology used in that investigation.  EPA later engaged
another contractor to fill data gaps from the RI/FS as pre-design
work.  This study found no contamination in some  areas where the
RI/FS indicated contamination existed, and significant
contaminations in other areas that the RI/FS had  not identified.
The study found that about 21,000 of the 102,000  cubic yards of
material the RI/FS determined to be contaminated  did not require
excavation.  Furthermore, it found that more than 24,300 cubic
yards of material the RI/FS indicated could be left undisturbed
in fact required excavation.

3.   EPA's Contractor Exceeded Its RI/FS Budget Estimate and More
     Than Doubled Its Estimated Time of Completion. Yet Was
     Unable to Produce a Report Which Would Support the Agency's
     Record of Decision fROD)

     The contractor's preliminary work plan stated the RI/FS
would take ten months and cost $480,862.  The RI/FS eventually
took 23 months and cost more than $612,000.  Furthermore, the
Agency spent about $210,000 more in a pre-design  study to
compensate for deficiencies in the RI/FS.  In addition, a Phase
II RI/FS was also required to address groundwater contamination.
This work was included in the preliminary work plan for what
became the Phase I RI/FS.  The contractor's RI/FS did not reveal
any findings differing markedly from several prior studies  done
of the site.

-------
EPA Office of Inspector General Annual Sunarfund Report to the Congress for Fiscal 1990          46

4.   EPA Region 1. Although Aware  of Numerous  Deficiencies on the
     Part of the RI/FS Contractor. Was Unable  to  Effect
     Significant Improvements Despite Repeated Notices of
     Unsatisfactory Contractor Performance

     The Remedial Project Manager  (RPM) assigned  by  EPA Region 1
to monitor this project became aware of deficiencies in the
contractor's performance early in  the course of the  RI/FS.   As a
result, he gave the contractor low scores in the  performance
ratings done for each four-month period to determine the amount
of the contractor's award fee.  In the Work Assignment Completion
Report, he characterized the contractor's performance as
"abysmal" and recommended that no  award fee be given for the
project.  Despite the Agency's knowledge of the contractor's poor
performance, the deficiencies were not corrected, an inadequate
RI/FS was produced, and the Agency had to fill data  gaps through
a pre-design study performed by another contractor.

5.   The RI/FS Failed to Provide an Adequate Basis for Selection
     of a Remedial Alternative

     The deficiencies summarized above resulted in an RI/FS which
did not provide an adequate basis  for remedy selection.   As a
result, EPA had to conduct a pre-design study  to  obtain
additional data to support the ROD.  The significant
discrepancies between the assessments of sludge deposits in the
RI/FS and in the pre-design study  were a major blow  to the
credibility of the Agency.  Two removal actions were undertaken
in response to hazards which were  undetected during  the RI.

SELMA PRESSURE TREATING SITE. SELMA, CALIFORNIA

Scope and Objective

     The objective of our review of the RI/FS  performed for the
Selma Pressure Treating site in Selma, California, was to
determine if there was an adequate technical basis for the
selected remedy as documented in the ROD.  To  perform this
review, OIG technical staff reviewed site documents, visited the
site and met with Region 9 program staff.

Conclusion

     We concluded that there was not an adequate  technical basis
for the selected remedy documented in the ROD  for the following
reasons:

     1.   Too few soil samples were taken to confidently
          calculate the amount of  contaminated soil  requiring
          remediation.

-------
EPA Offlca of Imnactor General Annual Suoerfund Report to the Congress for Fiscal 1990	47

     2.   Solidification/stabilization  treatability test results
          were not available until  after the ROD was signed and
          the results to date have  been inconclusive.  The August
          1989 Treatability Study Report concluded that the
          solidification/stabilization  technologies have
          limitations in applications to areas containing high
          concentrations of metals, pentachlorophenol (PCP) and
          other organics.

     3.   Additional wells  in the shallow,  intermediate and deep
          aquifer north and northwest of the site are needed in
          order to determine if there is an off-site source of
          groundwater contamination that would require off-site
          soil remediation.

     Both EPA and the State have acknowledged that additional
work is required at the site,  and that  it may result in a change
to the chosen remedy included in the  ROD.

Agency Response

     In response to our audit report, EPA Region 9 planned to
install additional monitoring wells and an extraction well to
develop more complete hydraulic data  on the intermediate aquifer.
They also planned a round of sampling of all of the active wells.

-------
EPA Offlea of Inspector General Annual Superffund Report to the Congress for Fiscal 1990          48

            PERFORMANCE AUDITS AND SPECIAL REVIEWS

     In addition to reviews required by  CERCLA,  as amended,  we
conducted other reviews of EPA's management of the Superfund
program.  We summarize below performance audits  and  special
reviews completed  in fiscal 1990.

COST RECOVERY COLLECTIONS

Scope and Objectives

     We reviewed EPA's collection of Superfund cost  recovery
amounts.  Our  audit objectives were to determine if  EPA:

a.   Recorded  cost recovery amounts as accounts  receivable in
     EPA's financial records;

b.   Collected cost recovery amounts in  a timely manner;  and

c.   Assessed  interest upon late payment.

     We reviewed collections resulting from cost recovery
enforcement actions for Superfund sites  in EPA Regions  3,  4  and
5.  We issued  separate audit reports for each  of these  regions,
and a consolidated report to the EPA Deputy Administrator.
Findings were  similar in the three regions reviewed.  We  have not
separately summarized them below.  However, we do summarize  the
responses of the regions as well as that of EPA  Headquarters.   We
judgmentally selected for review 44 of 152 enforcement  actions in
the selected regions for fiscal  years  1987 through 1989.   We also
reviewed oversight costs for 11  cases.   Because  our  samples  were
judgmental and not random, we could not  make statistical
projections on the remaining enforcement actions in  the universe.

Findings

1.   Accounts  Receivable Need to Be Recorded

     Neither Headquarters nor the regions timely recorded
accounts receivable on the financial records of  the  Agency.   For
fiscal 1989, $5.3  million (90 percent) of $5.9 million  of the
payments we reviewed were not timely recorded  as accounts
receivable.  Because EPA had not recorded receivables,  it was not
aware of what  payments were due.  As a result, a payment  might be
diverted, lost or  not paid without the Agency  being  aware of it.
This also results  in late payments with  a resulting  loss  of
applicable interest, as discussed in Finding No.  2.   We found
that EPA did not record accounts receivable because  it:   (a)  had
not established internal controls for  forwarding settlement
documents to the Financial Management Office,  (b) did not
promptly obtain judicial orders  from the Department  of  Justice,

-------
EPA Offlca of IntnaetOT General Annual Suparfund Report to the Congress for Fiscal 1990          49

and (c) did not timely record accounts receivable on the
financial records when it received  settlement  documents before
payment.  In addition, the regions  did not  establish routine
procedures to reconcile Superfund and Office of  Regional Counsel
records with the financial records.

2.   Prompt Action Needed to Collect Amounts Owed

     Neither Headquarters nor the regions were promptly
collecting cost recovery amounts owed to the Superfund Trust
Fund.  Of the 55 settlement documents we reviewed, we found 22
cases (40 percent) of delayed collection of amounts  owed.   Since
the U.S. Treasury Department invests Superfund monies in Treasury
bills, the Superfund Trust Fund lost $103,856  of interest.

    'The failure to collect promptly resulted  from  (a)  delays in
sending accounting data to responsible parties,  (b)  late payment
of amounts due, (c) delays due to responsible  party  requests for
further documentation and/or dispute of cost billed,  and (d)
delays in notifying responsible parties of  the effective date.
These conditions existed primarily  because  the regions did  not
(a) have a system for tracking when they needed  accounting  data
and (b) take consistent action to collect payments promptly.

Recommendations

     We recommended that EPA:

     •    Reconcile records to be sure that it collected cost
          recovery amounts due in the past.  Where it did not
          collect cost recovery amounts, EPA must record the
          amount due as an account  receivable  and take
          appropriate collection action.  Further, the Financial
          Management Office should  notify the  Regional
          Administrator for appropriate corrective action when
          other offices do not provide settlement documents
          timely.

     •    Provide guidance on when  to record amounts owed,
          particularly when under appeal or in litigation,  as
          accounts receivable.

     •    Complete planned corrective actions  cited  in the
          response to the draft report.

-------
EPA Office of Inspector General Annual Suoerfund Report to the Congress for Fiscal 1990	50

Agency Consolidated Headquarters Response

     In response to the draft report,  EPA stated it:

     •    Was working with the  Department of Justice  to make sure
          it•distributed court-approved consent decrees to EPA
          systems.

     •    Provided detailed guidance to regional staffs for
          timely and accurate establishment of accounts
          receivable for cost recovery,  penalties and oversight
          reimbursement.

     •    Included guidance in  two  Directives for current and
          accurate establishment and management of accounts
          receivable.

     •    Would reiterate to all Financial Management Officers
          (FMOs) and Comptrollers the  importance of recording
          receivables into the  system  when finance offices
          receive documents establishing receivables.

     •    Would engage an independent  contractor to perform
          internal control reviews, including a determination on
          the timely recording  of Superfund receivables, at four
          regional finance offices.

     •    Formed cooperative task forces of regional  finance,
          counsel and Superfund offices to address cost recovery
          issues.

     •    Was developing procedures to reconcile records, and was
          reconciling records monthly  with the Superfund program
          offices and regional  counsels.

     •    Was developing periodic reports to help the regions
          reconcile accounts receivable data with CERCLIS data on
          settlements.

     •    Would review regional financial offices' processes to
          determine if they promptly record receivables in the
          financial records.

     •    Would issue a Resources Management Directive defining
          when to record amounts owed  as accounts receivable.

     •    Distributed guidance  on Monitoring and Collecting
          Oversight Reimbursement.

     •    Would review FMO procedures  and controls for oversight
          billing.

-------
EPA OfflcB of Inspflctor GanofBl Annual Suparfund Raoort to tha Compass for Fiscal 1990          51

     In response to the final report,  EPA further stated it:

     •    Would establish a task  force of representatives from
          applicable Headquarters offices and each region to
          coordinate efforts to improve the recording and
          collection of Superfund accounts receivable.

     •    Would issue memorandum  guidance requesting (1)
          reconciliation of all administrative and judicial cost
          records,  (2) checking of all past settlements to be
          sure that accounts receivable are established, and (3)
          an accounting of all collections.

     •    Would establish internal controls over documentation
          required to establish accounts receivable.

Agency Regional Responses

     Each region reviewed also stated  in responses to draft and
final audit reports that it was taking regional actions which
would correct the deficiencies cited in the reports.  We
summarize these actions below by  region.
Region 3
Region 4
          Would have the Office  of  Regional Counsel submit its
          records monthly to the Office of the Comptroller for
          reconciliation.

          Would review and  complete written procedures for
          billing oversight costs.

          Would track oversight  billings through CERCLIS.

          Had a contractor  conduct  a Superfund internal control
          review.

          Would complete a  Memorandum of Understanding on
          procedures for establishing Superfund accounts
          receivable.
          Performed a quality  assurance  review of the billing
          process to be sure that  procedures in EPA's Financial
          Management Manual are  followed.

          Would monthly reconcile  printouts from the CERCLIS and
          Docket systems with  the  Integrated Financial Management
          System (IFMS), and IFMS  reports  to original documents
          on file.

-------
EPA Office of Inspector General Annual Suoerfund Report to the Congress for Fiscal 1990	52

     •    Would establish a work group of  representatives from
          the involved regional units to meet  at least quarterly
          to discuss accounts receivable procedures.

     •    Would notify the referring official  of any  missed
          payment due dates.

     •    Would perform a review of accounts receivable to test
          controls in place to make sure that  all receivables are
          properly recorded, promptly billed and collected, or
          referred to collection agencies  or Office of Regional
          Counsel.

     •    Was reconciling the records of the Financial Management
          Unit with those of the Office of Regional Counsel and
          the Waste Management Division.

     •    Implemented a system for prompt  issuance of written
          notices of the effective date for  cost recovery
          agreements and followed up on all  late payments.

Region 5

     •    Executed a Memorandum of Understanding Concerning
          Superfund Cost Recovery Procedures among the Waste
          Management Division, the Office  of Regional Counsel and
          the Planning and Management Division.

     •    Scheduled an internal control review of accounts
          receivable.

     •    Implemented Superfund Accounts Receivable - Interim
          Operating Procedures.

     •    Began regularly reconciling tracking system reports
          from the Office of Regional Counsel  and the Waste
          Management Division, and will provide the reports to
          the Planning and Management Division.

COST RECOVERY ACTIONS FOLLOW-UP REVIEW

Scope and Objectives

     We conducted a special review of EPA's  corrective actions in
response to our Consolidated Report on EPA's Cost Recovery
Actions Against Potentially Responsible Parties (E5EH4-11-0066-
61534, September 24, 1986).  The purpose of  our follow-up review
was to determine the timeliness and effectiveness of  the Agency's
actions in correcting the reported deficiencies.  The specific
objectives of our review were to determine whether EPA had:

-------
EPA Office of huoectof General Annual Suoarfund Report to the Congress for Fiscal 1990	53

a.   Implemented our recommendations,  and

b.   Realized  improvements in efficiency and  effectiveness.

     Due to its limited scope, the review was not an audit
following the  Government Auditing Standards  (1988 Revision)
issued by the  Comptroller General of the United  States.

Findings

1.   EPA Needs to Actively Pursue sites under $200.000

     The Agency was still not aggressively pursuing  cost recovery
actions against PRPs where it spent less than $200,000  for
cleanup.  Although the Agency had issued guidance on alternative
dispute resolution procedures including arbitration,  the Agency
had not used these alternative procedures for cost recovery
purposes.  The Agency had not used outside attorneys or outside
collection agents in cost recovery.  Four of  the ten regions had
set up cost recovery units.  However,  the General Accounting
Office reported in December 1989 that  some regions did  not have
full-time cost recovery staff.

2.   Bankrupt  Potentially Responsible  Parties Impact on EPA's
     Ability to Recover Costs Under CERCLA

     While EPA had developed a system  to identify and act on
bankruptcies,  the Agency still did not have a centralized way to
track bankruptcy cases and actions, and the money claimed and
collected for  the sites involved.  EPA had issued guidance on
filing claims  against bankrupt PRPs, including actions  against
viable and nonviable PRPs.  However, the Agency  had  still not
incorporated language in their demand  letters identifying EPA as
an official creditor.  The Agency needs to take  these actions to
improve management of cost recovery against bankrupt PRPs.

3.   EPA Needs to Complete Negotiations with  Responsible Parties
     in a More Timely Manner

     Negotiations conducted since our  1986 report still often
exceeded Agency timeframes.  Regions 3 and 4  were not always
completing remedial investigation/feasibility study  (RI/FS)  and
remedial design/remedial action  (RD/RA) negotiations within  the
required 90-day and 120-day timeframes, respectively.   We found
23 (66%) of 35 RI/FS negotiations late in Region 3 and  38 (66%)
of 58 RI/FS negotiations late in Region 4.  For  RD/RA
negotiations,  we found 18 (39%) of 46  late in Region 3  and 19
(45%) of 42 late in Region 4.  While EPA issued  guidance since
our last report to set timeframes and  specific negotiation steps,
and to notify  PRPs of the timeframes,  negotiations were still
delayed.  In addition, Headquarters and in some  cases the regions

-------
EPA Office of Inspector General Annual Sunarfund Report to the Congress for Fiscal 1990           SA

were not monitoring the length and conduct of  negotiations even
though CERCLIS contained this information.

4.   EPA Needs to Identify and Track Statute of Limitations Dates

     Since our previous audit, EPA began using a  three-year
statute of limitations  (SOL) period, tracking  SOL dates,  taking
some cost recovery actions in a timely manner, and  trying to take
cost recovery actions within a year for removals.   However,  the
Agency needs to monitor the regions to be sure they take  timely
action on all SOL sites.  For sites with an SOL date after
October 17, 1989 (three years from SARA's enactment date),  34
open sites out of 226 total sites in Regions 3 and  4 had  exceeded
the SOL date without sufficient action taking  place.   In
addition, these regions had closed 109 of the  226 sites without
taking any cost recovery action.  While Headquarters now  tracks
SOL dates and sends quarterly reports  to the regions,
Headquarters did not monitor to make sure the  regions  addressed
these sites.

5.   EPA Needs to Implement a Comprehensive Management
     Information System to Track Enforcement Activities

     While the Agency had developed a  CERCLA enforcement  system
in CERCLIS that includes many enforcement activities and  much
data, it still manually generated some critical information such
as bankruptcy claims and dollars.  In  addition, management was
not always using this information to actively  monitor  regional
program actions and related results.

Recommendations

     We recommended that EPA:

     •    Encourage a consistent approach in all  regions  for
          pursuing cases under $200,000, including  issuance of a
          demand letter.

     •    Conduct a pilot test using an arbitration board for
          sites under $200,000.

     •    Emphasize to the regions the increased  use of
          alternative dispute resolution techniques to settle
          small cost recovery cases as an alternative  to  filing
          judicial actions.

     •    Encourage and support the regions to establish  cost
          recovery units.

     •    Develop a system to track readily available  information
          on sites with bankrupt PRPs  and associated dollars

-------
EPA Office of Inspector General Annual Sunerfund Report to the Congress for Fiscal 1990          SB

          claimed and collected to  allow EPA management to
          monitor these sites and corresponding actions.

     •    Require that demand letters  contain explicit language
          identifying EPA as an official creditor.

     •    Request that in fiscal 1991  each region do an internal
          control review based on the  results of our report and
          address this issue in their  fiscal 1991 Federal
          Managers' Financial Integrity  Act assurance letter.

     •    Study negotiation timeframes,  analyze the reasons for
          not timely completing negotiations and implement
          negotiation strategies that  permit timely negotiation
          results.

     •    Periodically request regional  status reports, including
          action plans, on initiation  of cost recovery for sites
          where the SOL is about to expire.

     •    Incorporate all bankruptcy claims and costs recovered
          into CERCLIS and make sure that CERCLIS includes all
          cost recovery enforcement actions.

     •    Require that management use  the enforcement information
          for active monitoring of  regional program actions and
          results.

Agency Response

     In response to our draft report,  EPA stated it:

     •    Was piloting programs in  three regions to test
          collection services and alternative dispute resolution
          techniques, including arbitration, for recovering
          removal costs.

     •    Drafted an update of guidance  on written demands for
          cost recovery.

     •    Was reconciling cost recovery  settlement data in
          CERCLIS with collections  data  in the Integrated
          Financial Management System  (IFMS),  and developing a
          Settlements/Collections Report integrating CERCLIS and
          IFMS data.

     •    Analyzed regional performance  in managing negotiation
          timeframes, and identified management improvements it
          would make.

-------
EPA Office of Inspector General Annual Sueerfund Report to the Congress for Fiscal 1990	56

     In response to our final report,  EPA  further stated it:

     •    Would assess the variations  and  relative  performance of
          regional cost recovery programs,  and identify
          transferable management  and  organization  strategies for
          more consistent and effective cost recovery enforcement
          actions.

     •    Planned to develop a specialized bankruptcy report  to
          help regions to track status of  bankruptcy cases in the
          cost recovery enforcement program.

     •    Would distribute the audit report to Regional
          Administrators, and request  that in fiscal 1991 each
          region (a) perform an internal control  review or
          alternate control review based on the results of the
          report and  (b) address the issue in its Federal
          Managers' Financial Integrity Act assurance letter.

     •    Began monitoring regional management of RD/RA
          negotiations moratoria.

     •    Was developing a more specialized SOL report to
          facilitate management of SOL sites.

OVERSIGHT OF POST-SETTLEMENT ACTIVITIES

Scope and Objectives

     We completed reviews of oversight of  Superfund post-
settlement activities by Region 2  and  Region 3.   The Region 3
review produced no findings.  The  purpose  of these  reviews was to
determine the timeliness and effectiveness of regional post-
settlement activities.  The specific objectives of  the Region 2
review were to determine whether EPA is:

a.   Adequately monitoring compliance  with settlements and taking
     effective measures when parties are not in compliance;

b.   Assessing and collecting applicable penalties  and damages
     for noncompliance; and

c.   Adequately monitoring enforcement support contractors'
     oversight of PRP post-settlement  compliance.

     Our Region 2 review focused on settlement documents issued
between Fiscal Years  1986 and 1989.  We judgmentally selected 13
cases from the 37 Federal lead sites with  settlement documents
issued during our review period.   Most documents  issued by the
Region during our review period were for RI/FS activities and our
sample reflected that fact.  In addition,  we chose  a mix of New

-------
 EPA Office of liMMCtor Canard Annual Suoerfund Report to the Congress for Fiscal 1990	£7

 York and New Jersey cases.   We did  not  select cases from Puerto
 Rico, which  had  few cases.   We also made sure that at least half
 had Technical Enforcement Support (TES)  contract assignments.

 Findings

 1.   Length  of Regional Reviews Delay Superfund Cleanups

     Superfund cleanup work was unnecessarily delayed after the
 Region had settled  with the PRPs. The Region took between 6 and
 36 months to approve workplans,  project operation plans and other
 documents required  before beginning field work on RI/FSs, or
 other work phases.   This  occurred because of a lengthy review
 process  which lacked definitive EPA review and approval timeframe
 guidelines.   In  addition, the  Region  maintained no automated
 post-settlement  tracking  system to  monitor the timeliness of PRP
 submissions  or the  overall  status of  settlement cases.   Another
 contributing factor was an  understaffed and overworked project
 manager  corps which could not  always  devote essential review time
 to individual projects.   As a  result, Superfund cleanup actions
 were significantly  prolonged (up to several years),  increasing
 the potential for harm to public health and the environment.

 2.   Region  Needs to Be More Aggressive in Assessing Stipulated
     Penalties

     Region  2 was not  assessing stipulated penalties for
 noncompliance with  settlement  milestone dates.   The  Region did
 not take aggressive enforcement action,  limited its  actions to
 verbal negotiations  or warning letters,  and only sought penalties
 in extreme instances.   The  Region did not assess PRPs as much as
 $1,157,500 in penalties for two of  the  13 cases we reviewed.  As
 a result, there  was  no inducement for PRPs to follow compliance
 order requirements.  This lack of enforcement encourages PRPs to
 delay implementing  important provisions  of the  settlement
 document, thus unnecessarily lengthening the overall cleanup
 process.  This can harm public health and environment.

 3.   Oversight of TES  Contractors Needs  Improvement

     The Region  needed to improve its oversight of TES
 contractors.  The Region  did not effectively monitor the timely
 submission and processing of required contractor reports and
plans; conduct and document field oversight reviews,  quality
assurance audits and contractor  office reviews;  and  emphasize
project manager  training.   These conditions occurred because of
 inadequate monitoring,  untimely  or  lengthy Regional  reviews and
approvals,  lack  of written  procedures, and low  priorities or
insufficient  resources  for  certain  tasks.   As a result,  work
stoppages and unnecessary delays caused  a  longer cleanup process,
EPA did not know if TES tests  or records  were reliable  or

-------
EPA Office of Inspector General Annual Simerfund Report to the Congress for Fiscal 1990	58

accurate, and EPA was not sure that project  managers knew enough
to administer TES contracts adequately.

4.   Oversight Costs Were Not Billed  in  a Timely Manner

     The Region had not sought to  recover cleanup and oversight
costs from PRPs as stipulated in settlement  documents.   Regional
management had given only limited  attention  to enforcing this
settlement requirement.  In addition, project  managers gave this
a low priority, and cost recovery  packages were not adequately or
timely prepared to document costs  claimed.   As a result,  the
Region had not recovered at least  $627,761 for the  Superfund
Trust Fund, on which the Government could have earned interest.

Recommendations

     We recommended that EPA, Region  2:

     •    Develop and implement guidelines on  timeframes for
          Regional review and approval of PRP  submissions.

     •    Develop and implement an automated tracking system to
          monitor specific post-settlement milestone dates.

     •    Consider streamlining the review process  for PRP draft
          submissions.

     •    Review the current project  managers'  workloads and
          determine if it needs to make  reassignments to better
          equalize workloads.

     •    Develop and implement a  systematic approach for
          preserving documentation in project  files.

     •    Aggressively pursue stipulated penalties  when PRPs do
          not comply with settlement  document  requirements.  The
          Region should justify those instances where it does not
          pursue stipulated penalties.

     •    Improve the quality and  timely monitoring of TES
          contractors' required reports  and  workplan submittals
          and compliance with milestone  dates.

     •    Expedite the Regional review and approval system for
          TES deliverables.

     •    Develop timetables and minimum requirements for
          periodic field oversight reviews,  quality assurance
          audits, and contractors' office reviews.

-------
EPA Office of Jnanactor General Annual Stmerfund Report to the Congress for Fiscal 1990          59

     •    Require that project managers  attend prescribed
          training, generally before  performing TES oversight
          responsibilities.

     •    Set up and  implement an  effective system for the timely
          recovery of oversight  costs, requiring the sending of
          mandated settlement document itemized cost accountings
          to PRPs within  90 days of the  end of each fiscal year.

     •    Collect the $627,761 in  oversight costs identified in
          our report.

Agency Response

     In response to our draft audit report,  EPA Region 2 stated
it:
          Would develop guidelines  with New York State setting
          timeframes  for reviewing  PRP submissions.

          Was installing and  implementing an automated post-
          settlement  tracking system.

          Set up a Superfund  Records  Center,  which would result
          in a complete set of organized site files.

          Designated  a full-time  records coordinator  to manage
          and oversee the records center and contractor
          activities.

          Would be more aggressive  in seeking stipulated
          penalties for future violations.

          Would use a Regional monitoring system,  developed for
          the Alternative Remedial  Contracts Strategy contracts,
          for TES contractor  monitoring.

          Formalized  written  procedures for administering TES
          work assignments.

          Drafted a revised contractor fee plan which would
          reward contractors  based  upon the quality of services
          provided rather than the  numerical score.

          Received additional staff positions to reduce the
          workload of project managers and expedite review of TES
          assignments and deliverables.

          Would schedule in-house training based on the TES
          User's Guide, and had set up a computerized tracking
          system to improve the monitoring of RPM training.

-------
EPA Office of Inspector General Annual Suoerfund Report to the Congress for Fiscal 1990	60

     •    Would include provisions  in future TES assignments
          requiring an annual itemized expenditure documentation,
          and would include those expenditures in demand letters
          to PRPs.

     •    Hired a cost recovery  coordinator whose sole
          responsibility  is the  administration of cost recovery
          activities in Region 2.

     •    Would incorporate in all  Administrative Orders language
          providing for interest on all payments not received
          within 30 days.

     In response to the final audit report,  EPA Region 2 further
stated it:

     •    Expected to develop and implement guidelines to improve
          the quality and timeliness  of approval of PRP
          submissions, by developing  a Superfund Memorandum of
          Agreement with  each State and improving the peer review
          process.

     •    Would monitor PRPs1 compliance with settlement document
          requirements and aggressively pursue stipulated
          penalties or justify why  it does not pursue penalties.

     •    Requested enhancements to the TES Work Assignment
          Tracking System based  on  the audit findings.

     •    Was documenting each project manager site visit.

     •    Conducts periodic audits  to make sure both the PRP's
          contractor and  the EPA oversight contractor follow the
          approved Quality Assurance  Plan.

REGION 4 REMOVIAL ACTIVITIES

Scope and Objectives

     We reviewed the EPA  Region  4's implementation of the
removial cleanup program  and related  remedies.   The removial
cleanup approach used removal cleanup authorities to expedite
remedial actions (RAs) at National  Priorities List (NPL) sites.
Our overall audit objective was  to  evaluate the efficiency and
effectiveness of the Region's removial cleanups at eight
Superfund sites.  Our specific audit  objectives were to determine
whether Region 4:

a.   Effectively managed  removial activities to expedite NPL site
     cleanups and delisting at lower  cost than RAs;

-------
EPA Offica of liMpactor General Annual Superfund Report to the Conoresn for Fiscal 1990           61

b.   Obtained State assurances on  selected remedies  and cost
     sharing, under CERCLA section 104(c)(3),  before beginning
     renovial cleanup actions;

c.   Followed CERCLA requirements  for  State and  local  community
     participation in remedial projects;

d.   Followed Federal and EPA procurement regulations  and
     policies in obtaining removial cleanup services;  and

e.   Adequately coordinated remedial and removal sections'
     removial activities.

     We limited the scope of this  review to the  eight  sites on
which Region 4 and Headquarters agreed  in March  1988 to use the
removial approach.

Findings

1.   Region 4 Did Not Accomplish Removial Program Obiactives

     Region 4's removial cleanup approach of using removal
authorities for remedial cleanups  did not accomplish its goal of
expediting cleanup and deleting hazardous waste  sites  from  the
NPL.  In March 1988, Region 4 and  the Office of  Emergency and
Remedial Response  (OERR) in Headquarters agreed  on eight sites
for removial cleanup activities.   Of these eight sites,  Region 4
had only partially cleaned up three sites after  more than two
years and obligating more than $15 million.  Lack of defined
policies and procedures to carry out the removial cleanup
program, inadequate coordination and oversight of removial
actions, noncompliance of selected sites with  Office of Solid
Waste and Emergency Response  (OSWER) criteria, and remedy
changes, along with State opposition to selected remedies,
resulted in significant delays in  removial cleanups  and about
$3.86 million in potentially excessive  cleanup costs ($3.26
million) and questionable obligations  ($600,000).

2.   Statutory Requirements for Superfund State  Contracts fSSCsl
     and State/Public Participation Disregarded

     Region 4 did not provide States "substantial and  meaningful"
roles in removial activities.  When initiating quick cleanup
starts at selected removial sites, Region 4 frequently did  not
seek or disregarded input or participation from  States and
affected communities.  At two of the eight removial  sites,  Region
4 did not execute the required SSCs before cleanup actions  began.
Although EPA had signed SSCs at two other sites,  the Region did
not follow contract provisions on  remedy changes, cleanup starts,
and cost overruns.  EPA frequently changed ROD remedies and
cleanup goals without State or citizen  input.  Minimizing

-------
EPA Office of Inspector General Annual Superfund Report to the Congress for Fiscal 1990	62

participation from States and the public delayed cleanups and
increased cleanup costs.

     The Region bypassed the input of States and other affected
parties in trying to obtain RA starts and expedite NPL site
cleanups under the removial approach.  This situation resulted
from the use of removal authority for cleanup actions although
the sites were remedial projects.  Unlike remedial procedures,
removal actions address more immediate hazards and do not require
as much State and public participation as do remedial cleanup
actions.  The removial approach of using both removal and
remedial procedures created conflicts over which would dominate
as well as which program's staff would be responsible for
implementation.  In addition, Superfund program managers were
often uninformed about individual site actions of On-Scene
Coordinators (OSCs) and Remedial Project Managers  (RPMs).  These
managers had no adequate system for monitoring site activities
for compliance with applicable laws and regulations.

3.   Region 4's Removial Program Omitted or Rushed Key Procedures
     in the Remedial Cleanup Process

     Region 4 omitted or inadequately completed key remedial
requirements to obtain RA starts and speed cleanup actions at
removial sites.  The Region inappropriately changed ROD remedies
and cleanup levels and rushed ROD signatures before adequately
characterizing sites.  Due to remedial investigation/feasibility
study (RI/FS) data gaps, the Region needed to collect additional
information to correct discrepancies in remedies and cleanup
levels.  In some instances, the Region had to do additional site
testing and get more information to address State concerns.  The
Region also replaced Remedial Designs (RDs) with conceptual
designs.  It used Emergency Response Cleanup Services  (ERCS)
contractors or their subcontractors for sampling, testing and RD
work contrary to OSWER directives.  Furthermore, Region 4 did not
always involve States in removial cleanup decisions and obtain
SSCs from applicable States (see Finding 2).  Certain State
officials stated that the Region omitted these key steps to
achieve RA starts  (program goals), or "bean counts."  In
addition, some site files showed changes in RODs and cleanup
levels to qualify sites under the removial program criteria.

4.   Questionable Response Actions at Removial Sites

     Proposed removial response actions appeared excessive or
inappropriate at seven of the eight sites.  The Region proposed
or began removial activities at four sites based on claimed
immediate or substantial threats despite minimal levels of
contamination.  According to State officials and site
documentation, the Region undertook many of the removial actions
to meet Regional performance goals rather than critical

-------
EPA Office of Inspector General Annual Suoarfund Report to the Congress for Fiscal 1990	63

environmental needs.  None of the removal actions were time
sensitive.  The Region drafted Action  Memoranda for  seven  of  the
eight removial sites warning of immediate and serious hazards to
public health or the environment which site documentation  did not
support.  The actual site conditions were not always as  serious
as described in the memoranda.  These  sites had been on  the NPL
for many years and progressed to the ROD stage, and  the  Region
had not documented changes in site conditions.  For  five of these
sites, the Region had completed removal actions in the early
1980s.  These early removals generally mitigated the immediate
threats.  In addition, later removial  actions taken  at Geiger,
Independent Nail and Palmetto Wood did not support the immediate
threat assertions made in the Action Memoranda.  The actions
appeared excessive or unnecessary.  In addition, the Region's
selection of three sites for removial  actions was inconsistent
with removial guidance.  As a result,  the Region spent large  sums
on inappropriate sites with only minimal threats to  human  health
and the environment.

5.   Questionable Use of ERGS Contractors/Subcontractors for
     Remedial Activities

     Region 4 created potential conflict of interest situations
by using ERGS contractors or their subcontractors to perform
remedial design, sampling and site characterization  activities.
EPA OERR approved the Region's use of  ERGS contractors to  perform
removial cleanups.  Contrary to OSWER  Directive 9360.0-03B,
Region 4 tasked ERGS contractors or their subcontractors to
identify and define, through sampling  and/or analysis, what was
to be cleaned up; design the cleanup system; and perform the
actual remedial construction.  The Region took these actions  to
speed the cleanup process, assuming that ERGS contractors  and
subcontractors had the skill to characterize the sites and take
appropriate cleanup actions.  Permitting a single contractor  or
its subcontractor to perform every step in the cleanup process
creates potential for data manipulation for the contractor's
financial benefit.

Recommendations

     We recommended that EPA Region 4:

     •    Make sure all future removial actions follow program
          requirements.

     •    Issue formal guidance and procedures for the removial
          program to facilitate cooperation and coordination
          between the Region's remedial and removal  staffs, end
          duplication of effort among  staff personnel, and
          specify the duties, responsibilities, and  individual
          roles of the Region's remedial and removal staffs.

-------
EPA Offlca of IniPBCtof Gonafal Annual Supsifund Raoort to ths Conoress for Fiscal 1990	6A

     •    Establish controls to make program managers strictly
          accountable for following established procedures to
          ensure the integrity of EPA programs and maintenance of
          the public trust.

     •    Adequately determine the type and extent of
          contamination before selecting future sites for
          removial cleanups.

     •    Develop controls keeping managers informed of removial
          and remedial actions and making sure staff follows
          CERCLA and Agency policies for State and public
          involvement and for SSCs in NPL cleanup activities.

     •    Instruct removal and remedial staffs to comply strictly
          with SSC provisions.

     •    Require documented justifications for any changes in
          ROD remedies and cleanup goals and omission of any key
          remedial requirements such as RDs.

     •    Establish controls to be sure that the Region conducts
          complete RI/FSs, does not rush RODs to execution, does
          not begin removial cleanup actions before adequately
          characterizing sites, and selects only the most cost
          effective remedies adequately protecting human health
          and the environment at removial sites.  These controls
          should include an in-depth independent, second party
          review of any RODs signed or RAs begun in the fourth
          quarter of each fiscal year to be sure they are
          justified and adequate.

     •    Instruct Regional staff not to arbitrarily change RODs,
          remedies and cleanup goals to reduce RA time and costs
          to qualify sites for the removial program.

     •    Establish procedures to be sure statements in removal
          Action Memoranda clearly reflect documented site
          conditions.

     •    Establish adequate controls over removal and remedial
          activities to be sure cleanup actions among removial
          sites are consistent, eliminate duplicate contractor
          services, and follow OSWER program criteria in
          selecting removial sites.

     •    Remind Regional staff the OSWER Directive 9360.0-03B
          restricts the use of ERCS contractors in cleanup
          actions, and establish controls to be sure they follow
          it to prevent actual, apparent or potential conflicts
          of interest.

-------
EPA Offlca of huDBCtor Ganaral Annual Suoerfund Rflnort to tho ConoraM for Fiscal 1990	65

Agency Response

     In response to our draft report,  EPA Region  4  stated it:

     •    Would follow Headquarters removial  guidance.

     •    Would develop formal standard operating procedures to
          detail removial administrative procedures and define
          specific roles of remedial and removal  personnel,  if
          the Region continues to  use  removials.

     •    Would develop a system of controls  to be  sure it
          follows SSC regulations.

     •    Would follow OSWER Directive 9355.3-02, Interim Final
          Guidance on Preparing Superfund Decision  Documents,
          when making changes in RODs, remedies or  cleanup goals.

     •    Would follow OSWER Directive 9360.0-03B.

     In response to our final report,  EPA Region  4  further stated
it:
          Would make sure that all RI/FSs  are  peer reviewed and
          the reviewers concur before proceeding with ROD
          signature.  The Regional Branch  Chief  and Division
          Director will independently review the proposed plan
          before releasing  it to the public  and  asking the
          Regional Administrator to sign the ROD.   Region 4 will
          make sure that it uses the nine  remedy evaluation
          criteria set forth in the National Contingency Plan
          appropriately when selecting a remedy.   The Region will
          document the site file appropriately to reflect these
          reviews.

          Would have the Regional Branch Chief and the Division
          Director review and approve all  significant changes to
          RODs or remedies, and appropriately  document the review
          and approval process in the site file.

          Would issue the latest OSWER guidance  on preparation of
          removal Action Memoranda to Emergency  Response and
          Removal Branch personnel, and hold a seminar on the
          preparation of Action Memoranda.

          Would develop controls to make sure  staff follows OSWER
          Directive 9360.0-03B on actual,  apparent or potential
          conflicts of interest involving  ERCS contractors or
          their subcontractors, and present  seminars on this
          topic.

-------
EPA Office of Inspector General Annual Suoerfund Report to the Congress for Fiscal 1990	66

SUPERFUND INNOVATIVE TECHNOLOGY EVALUATION DEMONSTRATION PROGRAM

Scope and Objectives

     The purpose of the audit was  to determine the  success of the
Superfund Innovative Technology Evaluation  (SITE) Demonstration
Program in encouraging the development and  use of innovative
technologies to achieve more permanent protection of  human
health, welfare, and the environment.  Our  audit objectives were
to determine if:

a.   EPA planned technology demonstrations  in  accordance with
     SARA;

b.   EPA conducted and evaluated technology demonstrations in a
     timely manner;

c.   Completed demonstrations were leading  to  a more  widespread
     use of the technologies and more effective site  cleanups;
     and

d.   EPA had adequate internal controls  in  place to guard against
     fraud, waste and abuse.

Findings

1.   Improvements Needed in Matching Technologies with Hazardous
     Waste Sites for Demonstration Purposes

     Problems  in locating sites for technology demonstrations
delayed the Demonstration Program.  Matching technologies to
specific sites had been a difficult and  time-consuming task,
frequently taking a year or longer.  SITE officials repeatedly
asked the regions to volunteer prospective  sites since they
didn't have a universe of hazardous waste sites with  known
characteristics.  This delayed site matching.   Relying on the
regions to suggest sites was a major cause  of  the site matching
problem.  When we finished our audit work,  program  officials had
developed a data base to help match sites,  but still  relied on
the regions to provide timely and  accurate  detailed site
information.

     Some regional Superfund officials were reluctant to
recommend sites and participate in the program because of the
limited time they have to clean up sites.   In  addition,  some
Remedial Project Managers  (RPMs) and On-Scene  Coordinators (OSCs)
we contacted were unwilling to recommend sites.  There was little
or no incentive for them to do so,  since they  had little
documented information on successful technology demonstrations.
These individuals were not tracked or held  accountable for

-------
EPA Office of Inspector General Annual Sunerfund Report to the Congress for Fiscal 1990	67

participation  in the SITE Program  but  instead  were primarily
accountable for cleanup of sites.

     Developers turning down sites, developers exiting  from the
program, and proposed technologies having a limited  scope  of
treatment also affected the Agency's site matching process.   The
SITE Program needed to address all these factors  to  increase the
number of demonstrations and thus  provide reliable,  documented
information to RPMs and OSCs to aid in cleanup decision-making at
Superfund sites.

2.   Improvements Needed in Reporting  Results  for Completed
     Demonstrations

     The SITE  Program needed to address lengthy reporting  periods
and delays in  issuing final technology demonstration reports.
The program had taken as long as 22 months to  publish these
reports.  The  reports were critical because they  were the
principal means of informing RPMs, OSCs and Superfund cleanup
contractors about the in-depth demonstration results.   Extensive
rewrites and a long review process by  EPA, the demonstration
contractor, the technology developer,  and other report  reviewers
had delayed the reporting process.  In addition,  the Office of
Research and Development (ART) needed  to shift from  their  normal
long range focus of 3-5 years to the shorter period  of  under two
years for the  SITE process.  SITE  management set  a new  timeframe
of 18 months for the entire demonstration process.   SITE
officials needed to explore possible alternatives to identify and
eliminate bottlenecks in the reporting process.

     The lack  of reported information  and documented results
handicapped the success of the program.  In fact, 30 percent of
the individuals we contacted in the regions told  us  they had not
heard of the SITE Program or were  not  familiar enough with it to
answer our questions.  These OSCs  and  RPMs are the ultimate EPA
users of the demonstrated technologies.  While those familiar
with the program thought it was a  very good idea, they  had not
received enough information about  specific demonstration results
to encourage them to use innovative technologies.  As a result,
the use of these innovative technologies to more  permanently
clean up Superfund sites was hindered.

3.   Improvements Needed in Ensuring Adequate  Contractors'
     Performance and Cost Control

     RPMs, OSCs, developers and SITE officials repeatedly
expressed concerns about contractors'  performance in such  areas
as experience, writing reports, and time delays.  In addition,
program officials and SITE management  did not  appear to be
adequately controlling contractor  costs and overall  project
costs.  The nine projects we reviewed  frequently  had significant

-------
EPA Office of Inspector General Annual Suoerfund Report to the Congress for Fiscal 1990	68

cost increases and tine extensions.  We  found  increases  to
original cost estimates that were as high as 137  percent with an
overall average of over 98 percent.  This cost growth  is
especially important because the contractors received  significant
portions of Demonstration Program funds  during fiscal  1987
through 1989.

     We found that award fees were not always  consistent with the
project time delays and increased costs.  SITE management needed
to adequately use the award fee determinations to communicate
performance results and the need for high quality work to the
contractors.  Further, the SITE Program  needed improvements  to
make sure contractors performed adequately and controlled costs.

4.   The SITE Demonstration Program Discouraged Distribution of
     Federal Funds to Developers

     The Demonstration Program discouraged distribution  of
Federal assistance to technology developers.   No  developer had
received funding assistance as of October 1, 1989.   SITE
officials told us they took a conservative approach  to providing
funding because they were unclear what Congress intended.  In
addition, they told us they feared providing funds to  developers
would limit available funds remaining to conduct  the program.
Four of five developers we talked with believed funding  impeded
the program, and two stated they would not participate again in
the program because of a lack of funding.  Further,  while no
technology developers received funding,  EPA paid  its SITE
contractors about 80 percent of the program's  $34.6  million
budget during fiscal 1987 through 1989.  Finally, 11 developers
have exited the program without demonstrating  their  technologies.
The Agency gained little from these developers, despite  a cost of
about $2.6 million.  Because EPA did not fund  developers,  the
Demonstration Program may have discouraged developers  of other
promising technologies from applying for admission to  the
program.

Recommendations

     We recommended that EPA:

     •    Review and analyze why developers exit  the
          Demonstration Program so it can use  this information in
          selecting future technologies.

     •    Begin SITE technology demonstrations using more than
          one technology.

     •    Formalize the number of site locations  at  which a
          developer can refuse to conduct a demonstration.

-------
EPA Offlca of Inspector General Annual Suporfund Report to tha Conorasg for Fiscal 1990          69

     •    Add  SITE  demonstrations to the performance indicators
          or elements  of  management tracking systems.

     •    Explore and  develop other incentives for regional RPMs
          and  OSCs  to  offer their sites for SITE technology
          demonstrations.

     •    Make SITE management formally accountable for meeting
          reporting milestones.

     •    Consider  alternatives for performing a detailed review
          of the process  for preparing  and issuing SITE reports,
          such as a Management Systems  Review.

     •    Evaluate  publication alternatives to speed up the
          actual distribution process.

     •    Prepare a videotape or presentation of the
          Demonstration Program's goals and objectives and
          present it to all Superfund personnel.

     •    Require adequate justification for individual funding
          increases.

     •    If it cannot improve contractor performance in key
          areas, such  as  report writing, keep those functions in-
          house on  future projects.

     •    Reinforce to contractors  and  project managers the use
          and  importance  of the award fee process.

     •    Consider  for the next contract period a different
          contract  type to more fairly  balance risk between EPA
          and  the contractors.

     •    Seek further clarification from Congress on legislative
          intent on funding for technology developers.

     •    Reduce the amount of financial information required
          from prospective developers.

     •    Formalize the amount of time  expected to award funds to
          developers,  and convey this information to developers
          applying  under  new solicitations.

     •    Request additional funds  for  developer funding.

Agency Response

     In response to our draft report, EPA stated it:

-------
EPA Office of Inspector General Annual Sunerfund Report to the Congress for Fiscal 1990           70

     •    Demonstrated the first combination of technologies in
          the SITE Program.

     •    Would screen technologies accepted under the  SITE-005
          solicitation to identify possible technology  matches
          and investigate possible combinations.

     •    Would change the SITE-006 solicitation  to  require
          developers to assess their function in  a combination
          approach.

     •    Would encourage applicants to propose potential  sites
          in their applications.

     •    Is tracking demonstration program progress quarterly
          through the SITE Milestone Checklist report.

     •    Would review the publication process and consider
          whether to do this as a management system  review.

     •    Prepared one videotape on the SITE Program and showed
          it to the Superfund '89 conference, and plans to
          prepare a videotape on the Alternative  Treatment
          Technologies Information Center.

     •    Will reinforce and emphasize the award  fee process to
          SITE contractors and Project Managers.

     •    Met with the EPA Contracts Management Division on the
          possible use of different contract types.

     •    Will develop a statement for future solicitations on
          the time expected for award of competitive cooperative
          agreements.

     In response to the final audit report, EPA further stated
it:

     •    Completed a review of the reasons developers  exit the
          demonstration program.

     •    Added to the selection process a screening of all
          developers' proposals for their potential  capabilities
          to use "treatment train" technologies.

     •    Would include regional site nominations for SITE
          demonstrations as a reporting measure in the  Strategic
          Targeted Activities for Results System  (STARS).

     •    Would perform a SITE Management Review.

-------
EPA OfflcB of Inspector GanBral Annual Supcrfund Report to the Conoross lot Fiscal 1990	71

     •     Implemented  interim improvements in the publication
           distribution process.

     •     Prepared  several  video tapes  on SITE for use in the
           Basic Training  Academy for RPMs and OSCs.

     •     Directed  project  managers to  pay closer attention to
           contractor performance and requests for work assignment
           resource  increases  and justifications.

     •     Reviewed  the contract  type used, and decided that Cost-
           Plus-Award-Fee  was  still  the  most appropriate
           mechanism.

     •     Would state  in  future  solicitations that it would take
           eight months to award  funds to developers.

     •     Would review resource  levels  for the SITE program at
           the time  of  Superfund  reauthorization.

COST-PLUS-AWARD-FEE CONTRACTS

Scope and Objectives

     We audited the award fee process for Superfund cost-plus-
award-fee  (CPAF) contracts.   Our audit  objectives were to
determine  if:

a.   Award fees effectively motivated contractors to excellence;

b.   Award fee plans and  procedures were consistent among
     Superfund programs;

c.   The award fee  process  adhered  to Federal Acquisition
     Regulations (FAR), award fee plans developed by the Agency,
     and Superfund  program  user  manuals; and

d.   EPA completed  the award  fee process in a timely manner.

     We conducted audit field work  at EPA Headquarters and Region
3.  We reviewed award  fee records compiled by Headquarters
officials  and personnel in  all ten  EPA  regions.   We reviewed 21
of the 98  active Superfund  contracts as of June 2,  1989.  We
reviewed all active Superfund contracts except remedial program
contracts  addressed in a  July 1988  General Accounting Office
report, contracts that did  not provide  award fees,  region-
specific contracts  other  than Region 3  ARCS awards, and contracts
with a potential value of less than $30 million.   The 21
contracts  reviewed  covered  five  Superfund programs and were
potentially worth over $2.2 billion.

-------
EPA Office of Inspector General Annual Sunarfund Report to the Congress for Ftecal 1990	72

Findings

1.   Award Fees Often Failed to Achieve Excellence

     The Agency rewarded performance that was less than
satisfactory.  We believe paying award fees for less than
satisfactory work does not meet the intent of the award fee
concept in the FAR, to motivate the contractor to excellence.
Under three of the eight contracts in place for more than  a year,
EPA rewarded contractors for work rated satisfactory and
sometimes less than satisfactory.  For example, EPA rated  85
percent of the work of one contractor no better than
satisfactory, and 60 percent of the work of a second contractor
as marginal or deficient, yet both received award fees.
Moreover, a third contractor collected award fees despite
charging the government for unreasonable costs.  In addition to
the award fees, all 21 contracts reviewed provided contractors
with base fees even when contractor efforts were seriously
deficient.  However, the FAR allows EPA to reduce the payment of
any fee, base or award, for performance not meeting contract
requirements.

2.   EPA's Performance Evaluation Procedures Varied By Contract

     EPA needs to revise evaluation procedures for Superfund
contractors.  Because the evaluation procedures differed,  the
Agency did not provide award fees in a uniform manner.  Moreover,
the administrative effort used for evaluation was not always
justified by the size of the award fees.  EPA evaluators spent
more effort rating the performance on the smaller Environmental
Services Assistance Team contracts than on the much larger
Alternative Remedial Contracting Strategy contracts.  The  rating
categories the Agency used to evaluate contractors were not
consistent.  Of the 21 contracts reviewed, 14 had five rating
categories while seven had only four.  Also, the amounts of award
fees available for each category varied among contracts.   As a
result, one contractor providing unsatisfactory work could
receive 20 percent of the available award fees, while another
contractor could receive 35 percent for similarly unsatisfactory
work.

3.   Late Appraisals Hinder the Award Fee Process

     The Agency did not always use award fee evaluations to
provide contractors with timely feedback on their performance.
The FAR and most of the contract award fee plans required  such
notice.  One contractor lacked such feedback for more than a
year.  Other contractors provided marginal or unsatisfactory work
for months without formal notification from EPA.  As a result,
contractors continued to perform less than adequately, and were
not informed where they needed to improve.

-------
EPA Office of Jnipactor Ganaral Annual Suoarfund Report to tha Conorass for Fiscal 1990          73

Recommendations

     We recommended  that  EPA:

     •    Monitor  future  Environmental  Services Assistance Team
          Zone  I award fee evaluations,  and terminate the
          contract if  future evaluations show any widespread
          return to  the deficient performance in the first three
          performance  periods.

     •    Restrict the payment of base  fees as permitted by the
          FAR  if services performed under any Agency CPAF
          contract do  not meet contract requirements.

     •    Restructure  all Agency CPAF contracts to provide no
          award fees for  less  than  satisfactory work, and allow
          only  reduced amounts for  work no better than
          satisfactory.

     •    Determine  and recoup the  actual costs and base fees
          inappropriately charged against contracts, as detailed
          in the audit report.

     •    Establish  consistent procedures for CPAF contracts to
          provide  award fees in a uniform manner.  Each contract
          should have  the same number of rating categories and
          the percentage  of award fee available for each category
          should be  consistent.

     •    Modify future contracts to eliminate the award fee
          aspect when  the contract  value is small or when EPA
          does  not spend  what  it planned.

     •    Emphasize  to all involved personnel,  and include in
          their performance agreements,  the importance of
          completing evaluations.

     •    Not process  any work assignments for managers who are
          late  in  completing their  award fee evaluations.

Agency Response

     In response to  the draft  audit report,  the EPA stated it:

     •    Informed the Environmental Services Assistance Team
          Zone  I contractor that EPA was seriously considering
          not exercising  the first  option period but instead
          recompeting  the requirement.   Due to performance
          improvements, EPA continued the contractor, but the
          first option period  was split into a four-month period
          and an eight-month period.

-------
EPA Offica of Inspflctof General Annual Supsffund Report to tha Conoress for Fiscal 1990	74

     •    Formed a task force to evaluate the  scale used for
          award fee determinations  in  all remedial  contracts.

     •    Would develop a work plan to ensure  implementation of
          the OSWER Directives requiring timely  evaluation in all
          CPAF contract Work Assignment Managers' job performance
          standards.

     In response to the final audit report, EPA  further stated
it:

     •    Established a no award fee policy for  unsatisfactory
          performance.

     •    Set up a work group to review and revise  Agency award
          fee procurement regulations.

     •    Would issue a memorandum  emphasizing the  provisions of
          the Inspection of Services clause  (FAR 52.246-5)  and
          the need to review closely instances of reperformance
          within contractors' control  and attributable to poor
          technical workmanship or  management  oversight.

     •    Reviewed the charges the  audit stated  should be
          recouped, and found some  of  them were  appropriate.  On
          one contract, EPA instructed the firm  to  stop charging
          non-dedicated corporate management level  of effort to
          the contract, and developed  an action  plan to further
          research and resolve the  issue.

     •    Would issue a new or revised OSWER Directive
          emphasizing to all personnel involved  in  the award fee
          process that completing contractor performance
          evaluations in a timely manner is essential, and amend
          an OSWER Directive to include such a requirement in
          performance standards for Work Assignment Managers.

     •    Would set up an OSWER work group to  study award fee
          contracting issues, including evaluation  timeliness.

ARCS CONTRACTS BIDDING AND AWARD

Scope and Objectives

     We reviewed the Agency's bidding  and award  process for the
Alternative Remedial Contracting Strategy  (ARCS)  contracts, which
have a potential value of $6.6 billion.  Our intent was to
identify control weaknesses or make observations for change early
in the ARCS process.  Our review objectives were to determine if:

-------
EPA Offlca of Innpflctof Ganaral Annual Suparfund Raoort to tha Conorass for Fiscal 1990	"75

a.   EPA awarded ARCS contracts in accordance with Federal  and
     EPA acquisition regulations;

b.   EPA awarded ARCS contracts timely; and

c.   The ARCS program resulted in more firms participating  in the
     remedial program.

     We judgmentally selected two ARCS contracts  from the second
cycle of the ARCS procurement process for review, assuming  that
the Agency would have identified areas in the first cycle to
improve the procurement process in later cycles.  We limited the
scope of our work primarily to the procurement process  leading  to
award of an ARCS contract.  We did not review the implementation
of ARCS contracts.  Our review work was performed in Headquarters
and Region 3.

Findings

1.   ARCS Contracts Were Awarded Consistent with  Acquisition
     Regulations

     The ARCS procurement process complied with applicable
Federal and EPA Acquisition Regulations (EPAAR).  Except for
preparing an independent cost estimate, EPA complied with or
obtained an appropriate deviation from the FAR.   In addition, the
two contract files reviewed contained the required documentation
such as the summary of negotiations, approved deviations from
prescribed regulations, and determinations and findings
statements.  The contracts also contained the clauses required  by
the FAR for CPAF contracts.  EPA also required all Architect and
Engineer Evaluation Board members to complete separate  financial
interest statements.  EPA held several symposia to brief industry
about the new contracting strategy.

2.   ARCS Contracts Were Generally Awarded Timely

     EPA met its overall time goal for awarding all ARCS
contracts despite the complexities of a new contract mechanism
and the great effort to conduct cost and price analyses of  over
100 firms associated with the prime ARCS contractors.   The  awards
exceeded the program requirement to have a new contract mechanism
in place before the existing Remedial Planning Contracts expired
in September 1990.  EPA awarded 45 contracts beginning  January  1,
1988 and ending June 28, 1989, an elapsed time of 18 months.  EPA
took longer than its goal of nine elapsed months  from receiving
acceptable procurement rationale documents to the first contract
award for all three ARCS procurement cycles.  However,  we
identified no adverse effects to the remedial program from  the
failure to meet this goal.

-------
EPA Office of Inspector General Annual Suoerfund Report to the Congress for Fiscal 1990	76

3.   ARCS Increased Competition

     EPA net an overall goal of increased competition  by  awarding
45 ARCS contracts to 23 firms.  Of the 23 prime contractors,  11
were new to Superfund.  Also, 52 team subcontractors new  to
Superfund were associated with ARCS prime contractors.  The
structure of the ARCS program ensured many more contracts than
under the previous three large Remedial Planning  Contracts.   The
ARCS structure also maintained competitive pressure after award
because EPA would base the annual assignment of work on the
quality of past performance.

4.   Independent Cost Estimate for Future ARCS Contracts  Needed

     EPA did not independently prepare cost estimates  for ARCS
contracts, as required by the FAR.  Doing so would have provided
additional assurance EPA had negotiated a fair and reasonable
price.  EPA prepared a one-page analysis of the major  cost
categories for various sizes of ARCS contracts before
negotiations, but it did not include enough detail to  be
considered an independent Government estimate.  EPA contract
negotiators relied on other means to negotiate what they
considered to be a fair and reasonable price.  EPA technically
reviewed each cost proposal and compared it with  other offerers'
cost proposals submitted for a region or zone.

5.   Better Documentation of Estimated ARCS Zone  Requirements Is
     Needed

     Documentation supporting EPA's estimates of  annual technical
hours needed and contract costs for each ARCS zone was not
available.  Additionally, individual acquisition  plans (lAPs)
prepared for each of the three ARCS procurement cycles did not
consistently identify estimated resource requirements.  Thus  EPA
managers lacked basic data for justifying contract needs  or
comparing estimated program requirements with contract award
results and analyzing the variances.  lAPs developed for  Cycles
II and III did not contain the estimated contract value and/or
the estimate of technical hours needed by the regions.  In
addition, EPA did not sufficiently document the reasons for large
variances in planned versus actual procurement awards.

6.   Guidance Needed for Use of Small and Disadvantaged
     Businesses

     EPA required each ARCS bidder to submit a subcontracting
plan addressing the use of small or disadvantaged businesses.
However, EPA did not establish criteria and procedures to define
and evaluate a contractor's "good faith" efforts  and to make  sure
EPA would act consistently when determining actual performance.
The 45 ARCS contracts resulted in 113 team subcontractors,

-------
EPA Office of IniMctor General Annual Suoerfund Report to the Congress foe Fiscal 1990          77

including 49  (43 percent) small or disadvantaged businesses.
While this number is encouraging, there are  no guarantees that
the prime contractors will actually assign work to  these firms.
The Performance Evaluation Board's report did  not contain a
mandatory section requiring specific comments  on the
subcontracting plan goals.

Other Comments

1.   Cost Competition Not Used as a Selection  Factor in Awarding
     ARCS Contracts

     EPA, consistent with the SARA requirements to  follow the
Brooks Act requirements under the FAR, did not use  cost
competition as a selection factor in evaluating offerers with
which to negotiate ARCS contracts.  Agency officials believed
they negotiated and obtained fair and  reasonable prices for each
ARCS contract consistent with FAR requirements.   Without cost
competition as a selection factor, we•cannot be sure the
contracts were awarded at the lowest possible  cost  consistent
with receiving high quality technical  services.

2.   Inspection Clause Could Be Strengthened

     EPA might pay contractors unnecessary costs for poor quality
work that must be redone.  A standard  FAR inspection clause
included in all ARCS contracts states  that if  a contractor's work
is not acceptable and must be redone,  the Government must pay the
contractor in order for the Government to obtain acceptable
quality work.  As a result, the Government absorbs  the  cost no
matter how many times it takes the contractor  to provide an
acceptable product or service.

Recommendations

     We recommended that EPA:

     •    For future architect-engineer contract awards,  comply
          with, or request a deviation from, the FAR requirement
          for preparing independent Government cost estimates.

     •    Provide support for planning estimates of level of
          effort hours needed and cost estimates before accepting
          the procurement planning request.

     •    Document and keep for historical reference the reasons
          for variances between overall hour/cost estimates and
          the actual potential hours/costs in  ARCS  contract
          awards.

-------
EPA Office of Inspector General Annual Superfund Report to the Congress for Fiscal 1990	78

     •    Document  and retain the current analysis and decisions
          on ARCS contract workload to assist future management
          analysis  and decisions.

     •    Establish written evaluation criteria for defining
          "good  faith" efforts towards meeting subcontracting
          goals.

     •    Provide written guidelines to help contracting officers
          evaluate  contractor compliance with a subcontracting
          plan.

     •    Require all  Performance Evaluation Boards to include a
          mandatory section on the  contractor's compliance with
          the contract's  subcontracting plan in each award fee
          evaluation.

     •    Determine the desirability and feasibility of providing
          current and  future ARCS contractors with additional
          incentives encouraging them to exceed subcontracting
          plan goals.

Suggestions

     In connection  with our "Other  Comments," we suggested that
EPA:

     •    assess the need to amend  SARA to allow EPA to use cost
          competition  in  future Superfund Architect-Engineer
          contracts.

     •    request from the Civilian Agency Acquisition Council a
          deviation from  the FAR inspection clause requiring the
          Government to reimburse a contractor's cost to repeat
          unacceptable work,  if that is found to be warranted.

Agency Response

     In response to the draft audit report, EPA stated it would
comply in the future with the FAR requirement for an independent
Government cost estimate.

     In response to the final audit report, EPA further stated
it:

     •    Would be  able to prepare  realistic cost estimates to
          support planned level of  effort hours needed before
          beginning future remedial architect/engineer
          procurements.

-------
EPA Office of Inipectof General Annual Suoerfund Report to the Congress for Fiscal 1990	79

     •    Would involve the Office  of  Small and Disadvantaged
          Business Utilization  in reviewing and evaluating "good
          faith" efforts of ARCS contractors to meet and exceed
          the  goals  for using small and disadvantaged businesses.
          EPA  will also allow representatives of that Office to
          meet with  Performance Evaluation Boards.

     •    Would send a letter to all ARCS contractors
          highlighting the importance  of good faith efforts to
          achieve and exceed small  and disadvantaged business
          utilization goals.

     •    Requested  regional contracting officers to issue with
          each remedial design  work assignment a bilateral
          modification containing FAR  52.236-23, Responsibility
          of the Architect-Engineer Contractor.  This clause
          states "the contractor shall,  without additional
          compensation, correct or  revise any errors or
          deficiencies in its designs,  drawings, specifications,
          and  other  services."

CERCLIS REPORTING

Scope and Objectives

     We audited the  accuracy, reliability and consistency of
standard Comprehensive Environmental Response,  Compensation, and
Liability Information System  (CERCLIS)  reports.  Our objective
was to determine whether reporting  was accurate and reliable.

     The audit reviewed CERCLIS reporting and related controls as
they existed from June through  September 1989.   We conducted the
audit primarily at Headquarters.  We also visited Regions 2 and 3
to obtain background information and users' views on working with
CERCLIS.

findings

1.   CERCLIS Report  Program Documentation Needs Significant
     Improvement

     Documenting a program's specific  steps and the reasons for
these steps is vital so future  programmers can modify programs
correctly,  with only one exception, all the program source
code45 we examined contained no  documentation comments and did
not agree with descriptions of  report  logic prepared by
     45  A computer program written  in a  high level (English-like)
language.  It must be changed to  a  machine language format (load
module) before it can be processed  by a  computer.

-------
EPA Office of Inspector General Annual Suoerfund Report to the Congress for Fiscal 1990          80

contractors.  It will be very difficult  for future  programmers to
change these reports.  They may even need to  rewrite programs
completely rather than simply change them because they won't know
how the programs work.  In addition, without  a good understanding
of how these programs select and process records, it may become
impossible to resolve questions about  the meaning of reports and
their relation to other reports.   In fact, it may become
impossible to rely on them at all.

2.   Improvements in CERCLIS Report Library and Change Controls
     Are Needed

     Control over report programs  was  not adequate.   Programmers
could change reports without approval.   Control over programming
was so weak that the correct source code for  one production
report could not be found.  Therefore  users cannot  rely upon
reports produced by these programs because they cannot be certain
that the correct and error-free version  of a  program is being
executed.  If users cannot rely on these reports, they will
either not use them or use them with considerable risk.   Except
for Superfund Comprehensive Accomplishments Plan reports,  EPA was
not using CERCLIS reports for day-to-day management decision
making.  Information in related reports  was inconsistent because
of the same lack of control.  A comparison of reports which would
appear to users to list identical  items  showed significant
differences.

3.   Formal Testing Procedures for CERCLIS Reports  Are Needed

     EPA did not have formal testing and acceptance procedures
for programming new reports or changing  old reports.  If CERCLIS
officials did not receive negative comments on a report from
field users, they assumed all was  well.  The  number of coding
errors found in the five reports reviewed shows the serious flaws
in this methodology.  In fact, one report understated prior year
obligations for one region by $500 million.

Recommendations

     We made no recommendations in the final  audit  report because
the Agency had taken adequate action to  correct the deficiencies
found.

Agency Response

     In response to our position papers  and draft report,  EPA
stated it would:

     •    Insert comments into the code  when  it examines reports
          for inclusion in the national  library, and modify the
          CERCLIS Reports Library  to reflect  the changes.

-------
EPA Office of Inspector General Annual Suoerfund Report to the Congress for Fiscal 1990	81

     •    Require sign-offs from the EPA program  office (report
          owner) for all report specifications, reports library
          documentation, test/sample reports,  and report
          modifications before reinstatement to the production
          reports menu.

     •    Comprehensively review all future report documentation
          for adherence to selection criteria  standards and
          Federal documentation standards.

     •    Place all source programs and load modules in a
          centralized library.

     •    Require that the program offices and the reports
          librarian approve all changes to the production program
          library, and that the librarian make sure the library
          contains the latest approved copy of each program.

     •    Record any changes to source code within the program in
          the form of comments, and update a report change log
          for each report modification.

     •    Consult the reports librarian when changing  one program
          report to see if related or affected programs need  to
          be changed.

     •    Let users know by electronic mail of changes to a
          report.

     •    Review reports usage analysis and ask for user comments
          to identify all reports critical to  end of the year
          reporting and fiscal 1990 planning,  and give those
          reports highest priority for review  and correction.

     •    Place each critical report on a fast track for systems
          analysis, program confirmation and sign-off,
          reprogramming, verification of code  against  select
          logic, testing, approval by program  office and
          submission to the National Library.

     •    Remove all reports not identified as critical from  the
          CERCLIS National Reports Menu.  Make these reports
          available only through a special menu on the production
          system until verification, testing and  release of each
          report.

     •    Allow changed or new reports only through a  report
          change or new report request form.

-------
EPA Office of Inspector General Annual Simarfund Report to the Congress for Flteal 1990	82

     •    Use  report documentation, specifically specification
          forms and report  layouts, to  validate the successful
          development of new  reports.

     •    Have program offices  or report  owners evaluate a report
          to verify validity  while  independent report developers
          are  testing the report.

     •    Not  allow users access to reports  before testing is
          complete.

CERCLIS POST-IMPLEMENTATION STUDY SPECIAL REVIEW

Scope and Objectives

     We reviewed the Comprehensive  Environmental Response,
Compensation,  and Liability Information System (CERCLIS)  post-
implementation evaluation.  Our objective was to evaluate the
adequacy of the work performed  and  the  response of management to
its conclusions and recommendations.

     We conducted the review  at EPA headquarters.   We examined
the study's work plan and final report, and  interviewed
appropriate staff.  Due to  its  limited  scope,  the review was not
an audit following the Government Auditing Standards (1988
Revision) issued by the Comptroller General  of the United States.

Findings

1.   Certain Post-Implementation Evaluation  Findings Are Suspect

     Four tasks did not receive enough  independent testing and
verification.  These tasks  involved data  management, change
controls, data base integrity and security.   The contract team
performing the study relied solely  on interviews,  surveys and
available documentation in  their evaluation  of the system.
Without independent verification and  testing of procedures, there
can be no assurance that controls are actually in place and
effective.  As a result, the  study's  conclusions for these tasks
are suspect and EPA must attempt evaluations again at additional
cost to the Government.  Weaknesses overlooked in any of these
four critical  areas could adversely affect the life of the system
because users  would not be  able to  rely on it for their
information needs.

2.   A Software Assessment  Should Be  Performed

     The contract team did  not  perform  the planned assessment of
software quality.  The evaluation was to  have included the
adequacy of edits, the ability  of data  elements to support
reporting requirements, and ease of maintenance.  Responsible

-------
EPA Offlca of ifUDflctof Gammy Annual Suoorfund Rapoit to th9 Conoross for Fiscal 1990	83

officials stated that the assessment will  not be done in the
future because of the OIG's work  on CERCLIS  Reporting.   However,
the OIG limited its review to  report programming.   Without a
thorough review of software quality, EPA cannot be sure that the
system meets information needs, information  is accurate, and
future maintainers of the system  can be  effective and efficient.

Recommendations

     We recommended that EPA:

     •    Include independent  testing  and  verification procedures
          in OSWER system evaluations.

     •    Make evaluations of  the data management, change
          controls, data base  integrity  and  security.

Agency Response

     In response to our final  report,  EPA  stated it:

     •    Would make sure OSWER project  managers understand the
          need for independent testing and verification
          throughout the system life cycle and include this in
          their plans.

     •    Created a task force charged with  ensuring ongoing data
          management.  The task force  identified critical data
          quality issues and developed CERCLIS monthly audit
          reports in response  to  these issues.

     •    Instituted and documented a  formal change process
          addressing emergency and routine change requests,
          analysis and review, decision  making,  and
          implementation.

     •    Reviewed and revised all major standard reports for
          consistent formats,  field headers  and select logic; and
          were working to improve select logic maintenance and
          access.

     •    Assigns accounts and passwords only to Headquarters,
          regional and contractor staff  requiring direct access
          for data base maintenance, report  retrieval or software
          development.  Monthly access reviews by the National
          Computer Center and  regional local area network
          security will provide the level  of security required by
          EPA's Information Security Manual.

-------
EPA Office of Inspector General Annual Superfund Report to the Congress for Fiscal 1990	84

REGION 5 CONFIDENTIAL DISCLOSURE STATEMENTS

Scope ami Objectives

     We audited Region 5's compliance with  the Ethics in
Government Act of 1978, Executive Order No.  11222,  and 40 CFR
Part 3, Employee Responsibilities and Conduct.   We reviewed the
responsibilities of both Region  5 Deputy Ethics Officials,  the
Regional Administrator and the Regional Counsel.   Our overall
audit  objective was to determine whether the Deputy Ethics
Officials made sure employees followed  Government rules on
financial interests and investments, outside employment,  and
other  outside activities.  Our specific objectives were to
determine whether the Deputy Ethics Officials were:

a.   Properly identifying and notifying employees to file
     Confidential Statements of  Employment  and Financial Interest
     (confidential statements) as required  under 40 CFR 3.302(b)
     and (c);

b.   Making  sure applicable employees properly and promptly file;
     and

c.   Properly reviewing the financial interests and outside
     employment of employees for potential  conflicts,  and
     promptly resolving any conflicts.

     Our review did not include  Region  5 employees in the Senior
Executive Service.  EPA requires them to submit Executive
Personnel Financial Disclosure Reports  to EPA's Deputy General
Counsel in Headquarters.  Our audit period  was October 1, 1988
through December 31, 1989.

Findings

1.   Problems Persist in Collecting Confidential Statements

     Region  5 did not effectively collect confidential statements
because it did not have formal written  procedures nor had it
implemented  a proposed automated system to  make sure it timely
received all confidential statements.   The  Regional Administrator
inaccurately certified to the EPA Ethics Official that
confidential statements were required from  97 employees below the
GS/GM  13 level and that they all complied with this requirement.
Our review showed that 99 employees below the GS/GM 13 level were
required to  file and that only 59  (60%)  of  these employees
submitted a  confidential statement.  Consequently,  for those
employees who did not submit confidential statements,  the
Regional Administrator was unlikely to  be aware of conflicts of
interest between the employees'  EPA duties  and responsibilities
and their personal financial interests  and  activities.  Besides

-------
EPA Office of Inspector General Annual Suoerfund Report to the Congress for Fiscal 1990          85

not having formal written procedures,  the  employee designated to
administer the program had no formal training  in reviewing
statements for possible conflicts  of interest.

2.   Confidential Statements Need  to Include Spouse.  Child and
     Blood Relative Data

     Few employees who submitted confidential  statements included
information about the employment and financial interests of
spouses, minor children or blood relatives residing with the
employee (relatives).  Only 60 of  307  confidential statements
submitted to the two Deputy Ethics Officials showed this type of
information.  We determined that 25 married Superfund employees
did not include spousal information on their confidential
statements.  We contacted five of  these employees, all of whom
said their spouses were employed.   One employee told  us her
spouse worked  in an environmental  related  industry,   without
complete disclosure of required information, a Deputy Ethics
Official can not completely assess conflicts of interest.  This
condition usually occurred because employees did not  understand
they had to provide this information,  although instructions were
on the back of the form.

Recommendations

     We recommended that EPA Region 5  ensure completion of the
corrective actions planned in response to  our  draft report, and
provide us a written action plan with  specific milestone dates to
implement their planned actions.

Agency Response

     In response to the draft audit report,  EPA Region 5 stated
it:
          Would issue a detailed memorandum with a sample
          confidential statement attached  to  all employees
          required to file a confidential  statement.

          Would put their procedures  in writing.

          Established a checklist  as  a tickler system to remind
          new employees to submit  confidential statements.

          Would provide ethics training to employees  responsible
          for reviewing the confidential statements.

          Would further clarify and emphasize the requirements
          covering employment and  other financial interests of
          spouses, children and other relatives.

-------
EPA Office of Inipector General Annual Suoerfund Report to the Congress for Fiscal 1990	86

     •    Sent follow-up memoranda  to  all  affected employees
          requesting submission of  spousal,  minor children and
          relative information, where  applicable.

     In response to our final  report,  EPA  Region 5 provided
Action Plans for implementing  the above  planned actions.

INVESTIGATIVE-DERIVED WASTES SPECIAL REVIEW

Scope and Objectives

     We conducted a special review  of  EPA's  policy for disposing
of wastes stemming from pre-remedial site  investigations.   We
became aware of this issue while conducting  a survey of the pre-
remedial program's management  of Field Investigation Teams
(FITs).  It was not an audit.  We reviewed existing and proposed
EPA regulations and policies,  and current  waste disposal
practices.  Field work was done in  EPA Regions 5, 6 and 9, and in
EPA Headquarters.

Findings

     OSWER had no specific formal guidance for disposing of
wastes stemming from pre-remedial site investigations.  OSWER
recognized that this issue needed attention  and planned to issue
formal guidance.  However, OSWER delayed formal guidance while
OSWER and EPA regions tried to resolve concerns about disposal
costs and waste quantities for off-site  disposal.  Because there
was no formal guidance, situations  occurred  that unnecessarily
alarmed the public.  In one instance,  the  Agency's FIT contractor
employees discarded personal protective  gear and other materials
in a public park garbage container.  This  alarmed the park
district employees who found the material  and thought they had
touched contaminated material.  It  also  resulted in the fire and
police departments treating the incident as  a hazardous material
release.  In another instance, the  lack  of an EPA signature on a
hazardous waste manifest resulted in a FIT subcontractor leaving
two drums marked "hazardous" on a roadside for a short time.

Recommendations

     Because the Agency agreed to implement  the recommendations
in our draft report, we made no further  recommendations in our
final report.

Agency Response

     In response to our draft  audit report,  EPA agreed to issue a
directive and guidance on investigative-derived waste.  OSWER
issued Directive Number 9345.3-02 on Hay 24, 1991, which included

-------
EPA Office of Inspector General Annual Superfund Report to the Congress for Fiscal 1990	87

final guidance on Management  of Investigation-Derived Wastes
During Site Inspections.

ENVIRONMENTAL RESPONSE BRANCH  SITE-SPECIFIC TIMEKEEPING SPECIAL REVIEW

Scope and Objectives

     We audited overtime claims and payments to determine if EPA
had adequate and functioning  controls  to  prevent and identify
waste and abuse.  We  issued the final  audit report on August I,
1990 (E1MMF9-11-0039-0100419).  During the audit,  we determined
that some Superfund timesheets of  Environmental Response Branch
(ERB) staff showed account numbers different from those listed on
printouts from the Agency's accounting system.   As part of the
special review, we tried to reconcile  these differences by
reviewing available documentation  and  discussing the matter with
appropriate officials.

Findings

     We found that EPA did not charge  all appropriate costs
accurately to site-specific accounts.   Of the 159 fiscal 1988 and
1989 ERB timesheets in our sample, 79  (49 percent)  listed site-
specific accounts to  be charged.   However, the corresponding
hours recorded in the accounting system were charged to the
employees' regular Fixed Account Numbers  instead.   Further, the
Superfund Accounting  Branch could  not  locate 11 (18 percent) of
the 60 timesheets we  requested from their files.  Unless EPA
corrects these situations, it may  lose monies from future cost
recovery.  There were no written procedures on the processing or
input of site-specific redistribution  corrections.

Suggestions

     We suggested that EPA:

     •    Resolve the cases we identified in our review and
          determine whether other  similar cases exist and need
          resolution.

     •    Require that procedures  on site-specific redistribution
          corrections be written.

     •    Consider submitting timesheets  to the Headquarters
          Accounting  Operations Branch instead of the Region 2
          Financial Management Office  for current pay period
          timesheets  processing.

-------
EPA Office of Inspector General Annual Suoerfund Report to the Congress fof Fiscal 1990          88

Agency Response

     In response to the special report,  EPA:

     •    Reviewed all  site-specific charges for fiscal 1990.

     •    Agreed to resolve  the cases identified in our review.

     •    Agreed to review all site-specific charges for fiscal
          1989.

     •    Agreed to update Office of Emergency and Remedial
          Response  (OERR)  procedures for timekeeping and site-
          specific charging,  and provide training in them for all
          OERR managers and  timekeepers.

BETTER BRITE ZINC SHOP SITE, Wl, UNANNOUNCED SITE REVIEW

Scope and Objectives

     We performed an unannounced site review at the Better Brite
Zinc Shop Superfund removal  site in DePere,  Wisconsin.
Unannounced site reviews include a site  visit while a removal is
in progress.   While at  the site,  auditors observe conditions,
review documentation and interview personnel.  There is follow-up
work at the EPA regional office to review documentation that is
not at the site and to  interview appropriate personnel.

     Our review objectives are to determine the adequacy of:

     •    osc  compliance with removal directives and guidance;

     •    The  OSC's controls in monitoring the cleanup work and
          on-site spending;  and
          The technical  assistance provided by the Technical
          Assistance Team (TAT)  contractor.
Findings
     The site was  inactive at the time of our visit.  During our
site visit, we saw a  former shop employee entering the site.  EPA
officials told us  that  EPA did not control the site at the time.
Therefore, the potentially responsible party had access to the
site and apparently could let others onto the site at its
discretion.  We also  saw children playing at the site.  Part of
the removal action included removing contaminated soil.  There
were no fences or  ropes controlling access to the contaminated
soil.

-------
EPA Office of Inspector General Annual Suoerfund Report to the Congress for Fiscal 1990	89

Recommendation

     We recommended that EPA Region 5 consider posting warning
signs  at the  site  to alert the public of the potential for health
risk.

Agency Response

     In response to our audit report, EPA Region 5 posted warning
signs  at the  site  within three days of receiving the report.

BUNKER HILL SITE, ID, SPECIAL REVIEW

Scope and Objectives

     We performed  a special review in response to a confidential
complaint against  the Regional Administrator (RA),  Region 10.
The complainant alleged that the RA blocked or delayed the
normally routine actions of the Hazardous Waste Division (HWD) to
enforce Superfund  requirements against the Bunker Limited
Partnership  (BLP),  owners of the Bunker Hill Superfund site in
Kellogg, Idaho.  The specific allegations against the RA were:

a.   The RA would  not allow the HWD staff to order BLP to respond
     to various concerns of EPA about the company's salvage
     activities, site maintenance,  site security and the
     containment of hazardous materials.

b.   The RA refused to allow HWD to notify BLP that they were a
     Potentially Responsible Party (PRP)  for financing the
     cleanup of the site.   He refused to notify the company even
     after mounting evidence that its action,  or lack of action,
     was contributing to the further pollution of the site.

c.   The RA discussed the negative impact of EPA enforcement
     action on the value of the company's stock offering at a
     meeting in Region 10 in January 1988.   Both HWD staff and
     BLP officials were present.

     This was a special review,  and not an audit following the
Government Auditing Standards (1988 Revision)  issued by the
Comptroller General  of the United States.   We did not conduct a
review of the Bunker Hill site.   We made no recommendations.

Conclusions

     The RA took extraordinary measures to prevent the HWD staff
from performing the  normal and proper activities required to
enforce the Superfund regulations.   From August 1986 through
October 1989, the  RA blocked or delayed any formal enforcement
actions against BLP  despite the recommendations of the HWD staff.

-------
EPA Office of Inspector General Annual Suoerfund Report to the Congress for Fiscal 1990           90

As a result, EPA did not take timely enforcement  action  against
BLP.  This failure had serious consequences:

     •    The smelter complex within the Superfund site
          deteriorated to the point that, in October 1989,  the
          Agency for Toxic Substances  and Disease Registry
          (ATSDR) declared it a public health hazard.

     •    The partners have transferred all of BLP's assets to
          newly formed corporations through various stock and
          property transfers.  As a result, collections  for the
          Superfund cleanup activities will be much harder.

     •    The company's uncontrolled salvage activities  may have
          resulted in the sale of highly contaminated  equipment
          and material to, in some cases, uninformed buyers.   For
          example, an unknown quantity of lead-contaminated
          railroad ties have disappeared from the site.

     We summarize our specific conclusions below.

1.   RA Delayed Issuance of Administrative Orders

     HWD staff noted several indications of environmental threats
due to conditions at the site over the years.  These included  an
October 1986 fire, removal of railroad ties with  extremely  high
levels of lead, and salvage operations disturbing large
quantities of asbestos-containing material.  HWD  staff discussed
the issues with BLP on many occasions.  Although  BLP officials
continually stated that they wanted to cooperate, little progress
was made on the issues.

     HWD staff drafted an administrative order against BLP  in
November 1986, but did not issue it because of the RA's  stated
desire to resolve conflicts informally.  On November 12, 1987,
the HWD Director sent a letter to BLP  stating that an
administrative order would govern any  future salvage activities.
BLP could negotiate the terms of the order with EPA.   However,
EPA would issue a unilateral administrative order if it  could  not
reach an acceptable agreement with BLP.  The HWD  Director took
this action without telling the RA because he did not  believe  the
RA would approve.

     The HWD Director's letter was discussed at a meeting called
by the RA in January 1988.  The RA stated there would  be no need
to issue an administrative order.  HWD staff spent 1988  trying to
negotiate with BLP officials.  However, BLP officials  continued
to deny they were doing anything wrong, and to deny access  to
their facilities.  Although the RA was repeatedly informed  about
the hazardous conditions at the site,  he would not change his
decision.

-------
EPA Office of Inspector General Annual Superfund Report to the Congress for Fiscal 1990           91

     In the middle of 1989, EPA staff  secretly discussed with the
resident ATSDR staff the possibility of performing a public
health review at the site.  ATSDR  agreed, and  determined that
chemical and physical hazards at the smelter complex presented a
significant risk to public health.  On October 5, 1989,  ATSDR
issued a Public Health Advisory for the Bunker Hill smelter
complex.  ATSDR issues Public Health Advisories only under
extraordinary conditions, and ATSDR had issued fewer than a half
dozen nationwide since the Superfund program began.

     In October 1989, Region 10 officials conducted an  inspection
and assessment of the smelter complex.  They confirmed  the  ATSDR
findings and observed additional threats requiring immediate
actions.  On October 24, 1989, EPA finally  issued a unilateral
administrative order to BLP and other  PRPs  for the site requiring
the performance of needed response actions.  This was almost
three years after HWD staff first  sought enforcement action
against BLP.

2.   RA Delayed Notification that  BLP  Is a  PRP

     In 1984, the previous RA and  the  HWD staff decided to  name
Gulf as the site's sole PRP.  They believed Gulf was the primary
cause of the pollution.  They planned  to name  additional PRPs as
conditions changed and they identified other companies.

     In December 1987, Gulf presented  a fairly detailed argument
for EPA to name more PRPs.  On January 11,  1988, the HWD Director
signed a background paper and an options paper addressed to the
RA.  The Director stated that BLP  had  contributed to many of the
problems at the site, and recommended  the immediate naming  of BLP
as a PRP.  However, the RA adamantly opposed sending BLP a  PRP
notice letter.

     Having failed with Region 10, Gulf presented its evidence to
EPA Headquarters officials.  The Assistant  Administrator for
OSWER agreed that EPA should name  more PRPs.   He asked  the  CERCLA
Enforcement Division Director to resolve the conflict between the
RA and the HWD staff.  The Director's  primary  goal was  to modify
the standard PRP notice letter language into a form that the RA
would accept.  His attempt to discuss  this  with the RA  by
telephone turned confrontational and they reached no conclusion.

     On October 18, 1988, the HWD  Director  sent the revised PRP
notice letter and an attached request  for information to BLP.
HWD informed Gulf and the local community that EPA had  notified
BLP it was a PRP.  However, the RA continued to insist  that the
letter was not a notice letter, and BLP was not a PRP.   For the
next year, BLP refused to provide  the  information EPA requested
unless EPA granted it a specific confidentiality agreement.

-------
EPA Office of inspector General Annual Suoerfund Report to the Congress for Fiscal 1990	92

     When ATSDR issued its  report,  the  RA reversed his position.
Region 10 sent a second notice letter and information request to
BLP on October 4, 1989.

3.   Discussion of Value  of Stock  Issue

     Within the limited scope  of our  review,  we found no evidence
that the RA discussed the impact of EPA's enforcement action on
the value of the company's  stock offering,  although BLP officials
raised the issue at the meeting.

Agency Response

     The EPA Deputy Administrator  replied to the report
expressing his deep concern about  the findings.   He also reported
that the RA whose actions had  been reviewed had resigned and an
Acting RA had been appointed.   He  stated he had:

     •    Directed the Acting  RA to give priority attention to
          the Bunker Hill site and any  risk concerns associated
          with it.

     •    Directed the Assistant Administrator for Enforcement to
          visit the Region  and review with the Acting RA all
          significant pending  enforcement actions with special
          attention to the  Bunker  Hill  site.

     •    Asked the Assistant  Administrator for OSWER to work
          with the Region to address  any immediate risks.

OLIN CORPORATION. OH, SPECIAL REVIEW

Scope and Objectives

     We performed a special review of EPA Region 5, State of
Ohio, and EPA's Office of Criminal Investigations (OCI) actions
concerning Olin Chemical  Corporation's  (Olin)  closed waste
management facility in Ashtabula,  Ohio.   We performed this review
because of an allegation  a  citizen sent to the White House.  This
citizen alleged that EPA  Region 5  willingly and knowingly
neglected to sample and test Toluene  Diisocyanate (TDI) during a
1984 investigation of Olin.  OCI and  the Federal Bureau of
Investigation  (FBI) had jointly conducted an investigation in
1984 to determine if Olin properly closed its hazardous waste
facility.  The Region 5 Waste  Management Division provided
technical support to the  investigation.   The citizen also later
alleged that EPA limited  the scope of their investigation to a
proper closure of the Olin  facility under the Resource
Conservation and Recovery Act  (RCRA)  and did not consider other
contaminated areas.

-------
EPA Offlca of Inspector General Annual Suoarfund Report to the Conorasa for Fiscal 1990	93

Findings


      Contamination

      Neither OCI  nor Region 5's Waste Management Division
employees  knowingly or willingly neglected to test for TDI during
the  1984 investigation of Olin.  EPA took soil samples at the
Olin site  and analyzed them.   The analysis showed concentration
of contaminants in three  areas of the facility higher than the
levels specified  by Olin's closure plan.   However,  only one of
these areas  was subject to the closure plan.   The other two areas
showed elevated concentrations of two other hazardous wastes.

      OCI and the  FBI concluded that the closure met applicable
RCRA requirements.   They  also did not find that Olin reported
false information or knowingly concealed any conflicting data.

      Region  5's Associate Regional Counsel stated that, because
there was  soil contamination in a non-RCRA regulated area of the
Olin facility, the soil data collected by EPA would be evaluated
to determine whether the  soil should be remediated under CERCLA.
The  Region 5 RA stated in an October 18,  1985, letter that an
inspection was to begin of Field Brook Stream, a Superfund site
adjoining  the Olin site.   This inspection was to include sampling
at the Olin  site.

2.    A Site  Inspection of Olin Will Show Extent of Contamination

      The site inspection  of Field Brook Stream did not include
sampling at  the Olin site in those locations of concern.  It
addressed  ground  water contamination from the Olin site, but not
possible TDI contamination.   In addition,  the Waste Management
Division did not  use the  OCI  sampling data to help determine the
level of contamination at the Olin site.   Unless Region 5 (1)
determines that the site  does not contain TDI or other hazardous
substances and (2)  reviews OCI sampling data, decisions about the
proper cleanup action may not be adequate to protect the public
health and the environment.

Recommendation

      We recommended  that  EPA  Region 5 complete the  corrective
actions planned during our review.

Agency Response

      During  our review, EPA Region 5  stated it:

      •     Directed  an EPA contractor  to perform a site inspection
           at the  site.

-------
EPA Offlcfl of Impactof GonBfsl Annual Suporfund Rooort to tho Conorass for Fiscal 1990	94

     •    Would draft letters to 23 companies, including 01in,
          that closed facilities before the 1987 RCRA Amendments.
          The letters would request the companies to  show that
          their closed facilities follow current closure
          requirements.   If a facility is not in compliance,  EPA
          would require the company to develop a plan to close
          and manage  the site properly over the next  30  years.

     In response to the final report, EPA Region 5  further stated
it sent a letter to Olin requiring Olin to clean up the  facility
to background levels  as stipulated in the 1987 RCRA Amendments.

-------
EPA Offico of bi8D6CtOf Gonofsi Annunl SuDBrfund Rsoort to ttis Conorsss for Fiscul 1990	95

                    INTERAGENCY AGREEMENTS

     EPA enters into interagency agreements  (lAGs) with  several
other Federal agencies to perform Superfund tasks.  The  Offices
of Inspector General or other audit organizations of the
receiving agencies audit the cost records for these agreements.
The EPA OIG also issues these audit reports to EPA with  a  cover
letter for any action EPA may need to  take.  In  fiscal 1990,  we
issued eight of these reports to EPA management.  We summarize
the eight audits below by agency audited.  CERCLA requires other
Inspectors General, like EPA's, annually to audit their  agency's
use of the Superfund and report on that audit to the Congress.

U.S. ARMY CORPS OF ENGINEERS

     The U.S. Army Audit Agency audited the fiscal 1988  Superfund
financial transactions of the U.S. Army Corps of Engineers (COE).
In general, fiscal 1988 COE Superfund  obligations and
disbursements were properly supported  and accurately recorded and
reported.  However, no supporting documentation  could be found
for one obligation for $187,292.  The  Audit Agency also  found one
disbursement transaction for an incorrect amount, which  the COE
corrected during the audit.

Recommendation to EPA

     We recommended that EPA obtain a  written response from the
COE on resolution of the $187,292 obligation.

Agency Response

     In response to our audit report,  EPA reported it had
received a written response from the COE documenting the
obligation.

DEPARTMENT OF ENERGY

     The Department of Energy (DOE) OIG audited  the fiscal 1988
Superfund costs incurred by the DOE on lAGs with EPA.  The audit
showed no questioned, unsupported or unresolved  costs.   However,
the DOE had not claimed $449,234 as an added factor cost for
administration and depreciation as required in DOE Order 2110.1A.
The EPA OIG made no recommendations to EPA management as a result
of this audit.

FEDERAL EMERGENCY MANAGEMENT AGENCY

     The Federal Emergency Management  Agency (FEMA) OIG  audited
FEMA's administration of the temporary and permanent relocation
program under Superfund.  The audit covered fiscal 1988  program
activities and spending.  The FEMA OIG found that FEMA had

-------
EPA Office of Inspector General Annual Superfund Report to the Congress for Fiscal 1990          96

effectively administered the  temporary  and permanent relocation
program and generally spent funds  for eligible purposes.
However, the FEMA OIG found a continuing  need for FEMA to improve
its cost reconciliation and reporting for the relocation  program.
Specifically,  financial reports used unreconciled data resulting
in at  least $83,200 in improper charges to Superfund sites and
accounts.  Also, the FEMA OIG found overpayments under the
permanent relocation program  resulting  in questioned costs of
$6,300.  The FEMA OIG made appropriate  recommendations and FEMA
officials generally concurred and  proposed corrective actions.

Recommendation to EPA

     We recommended that EPA  not reimburse FEMA for  the $6,300
overpayment, or adjust future billings  for that amount.

Agency Response

     In response to our audit report, EPA stated it  could not
withhold the funds from FEMA  because they were in an allocation
transfer agreement.  The agreement transferred appropriated funds
to FEMA, and delegated obligational and spending authority to
FEMA.  FEMA assured EPA it would collect  the overpayment  from the
contractor which received it, and  credit  the Superfund site.

DEPARTMENT OF THE INTERIOR

     The Department of Interior  (DOI) OIG conducted  several
audits of DOI  Superfund activities.  The  EPA OIG issued these
audit reports, sending the audit results  to EPA management.
These reports  included results of  audits  of fiscal 1987
reimbursement  expenditures by the  U.S.  Geological Survey  and the
U.S. Fish and  Wildlife Service; and fiscal 1988 reimbursement
expenditures by the Office of Environmental Project  Review, the
U.S. Fish and  Wildlife Service, the Bureau of Reclamation and the
U.S. Geological Survey.

Fiscal 1987 Interagency Agreements

     The fiscal 1987 audits of the U.S. Fish and Wildlife Service
and the U.S. Geological Survey found that these bureaus sometimes
conducted valid Superfund work activities before they had
accepted lAGs  and charged some costs incorrectly to  Superfund
lAGs.  The DOI OIG resolved these  findings with DOI  management.

     The EPA OIG recommended  that  EPA emphasize to Headquarters
and regional offices the need to issue  lAGs before starting work
or, if they can't, timely document EPA's  request for services
through a memorandum to the other  agency.  When work begins
before executing an IAG, the  agreement  should reflect when work
actually began.

-------
EPA Office of Inspector General Annual Suoerfund Report to the Congress for Fiscal 1990	97

     In response to our audit report,  EPA  sent out  a memorandum
emphasizing that work should not begin under an IAG until both
parties execute a formal agreement.  EPA also emphasized that
valid reasons may exist for exceptions to  this policy,  including
emergency responses or unplanned delays in funding  availability.
The Action Official may approve an  IA6 project period beginning
before execution of the IAG, if the program Decision Official
justifies costs incurred within the appropriation period in
current legislation.  Failure to provide such justification could
jeopardize reimbursement for costs  incurred before  execution of
the IAG.

Office of Environmental Project Review • fiscal 1988

     The DOI OIG found that the Office of  Environmental Project
Review did not maintain accurate and complete cost  records of
reimbursable expenses charged to Superfund activities.   The
Office could not substantiate that  about $1.1 million charged to
the IAG was for Superfund-related work.  Without accurate and
complete accounting, EPA may not be able to recover the costs
from responsible parties.

     The Office also did not let EPA know  that it did not
obligate "no year" funds of $805,000 from  prior Superfund lAGs by
the expiration date of the lAGs.  Thus EPA was unable to
reauthorize the funds to other critical Superfund program needs.

     The Office agreed with the audit  findings and  specified
actions underway to implement the corrective actions recommended
by the DOI OIG.  The EPA OIG made no recommendations to EPA
management as a result of this audit.

Fiscal 1988 - Three DOI Bureaus

     The DOI OIG questioned the indirect cost rates used by the
U.S. Fish and Wildlife Service, the Bureau of Reclamation and the
U.S. Geological Survey.  The bureaus did not develop indirect
cost rates in accordance with EPA Comptroller Policy Announcement
87-10.  That Announcement requires  other Federal agencies to
certify "(1) that any indirect costs incurred in billings to the
Environmental Protection Agency represent,  in accordance with
U.S. Comptroller General principles, indirect costs that would
not have been otherwise incurred by the performing  agency or (2)
that statutory authority exists for charging other  than the
incremental costs of performance."

     All three DOI bureaus disagreed with  the questioning of the
indirect cost rates.  A memorandum  from the DOI Office of
Solicitor asserted that the EPA Announcement is inconsistent with
the U.S. Comptroller General's principles.   EPA informed the EPA

-------
EPA Office of Inspector General Annual Suoarfund Ranort to the Conora«« for Fiacal 1990          98

OIG that it was revising the Announcement  considering DOI's
position.

     The EPA OIG recommended that  EPA  continue to work on the
indirect cost criteria issue and revise Comptroller  Policy
Announcement 87-10.  EPA issued Comptroller Policy Announcement
91-04 on January 9, 1991, superseding  Comptroller Policy
Announcement 87-10.

INTERNAL REVENUE SERVICE

     The Internal Revenue Service  (IRS) Inspection Service
reviewed the IRS fiscal 1988 IAG with  EPA  for  statistical
tabulations on environmental taxes categorized by chemical type.
The IRS had generally followed the terms of the IAG  and costs
billed to EPA were reasonable.  However, the Inspection Service
found that:

     •    IRS1 actual fiscal 1988  costs  ($120,266) were
          significantly more than  the  IAG  amount ($32,000).

     •    The IAG did not clearly  state what work IRS was to
          perform.

     •    IRS did not report earnings  as actual costs were
          incurred and did not bill EPA quarterly, as required.

     •    IRS service centers did  not  effectively perform
          their responsibilities in support of the Superfund
          project.

     IRS management agreed with the findings and proposed
corrective actions.  The EPA OIG made  no recommendations to EPA
management as a result of this audit.

DEPARTMENT OF JUSTICE

     The Department of Justice OIG audited the Department's Land
and Natural Resources Division's  (LNRD) implementation of a
fiscal 1988 IAG with EPA.  The audit showed no material
discrepancies in the fiscal 1988 Superfund costs reported by the
LNRD to EPA.  However, it found internal control weaknesses
related to time reports and travel documents.   In addition,  the
LNRD needed to change its system of accounting for Superfund
costs to more accurately account for costs of  travel for multiple
cases.

     In general, the LNRD agreed with  the  audit findings and
identified corrective actions it was taking.   The EPA OIG made no
recommendations to EPA management  as a result  of this audit.

-------
EPA Office of Inspector General Annual Suoarfund Report to the Congress for Fiscal 1990          99

                           CONTRACTS

     The OIG is responsible for conducting  and supervising
independent and objective audits of Superfund  programs and
operations.  To carry out this responsibility,  the OIG performs
financial and  compliance audits of EPA contractors.   Each of the
Public Laws authorizing EPA to award contracts provides the
Agency authority to audit and examine  the books and  records of
the contractors and subcontractors receiving Federal funds.  Each
EPA contract also contains audit provisions.   Our primary audit
objectives are to determine (1) whether the controls exercised by
the contractors and subcontractors through  their accounting,
procurement, contract .administration,  and property management
systems are adequate to account for costs claimed; and (2)  costs
claimed are reasonable, allowable, and allocable, in accordance
with applicable laws and regulations,  to the sponsored project.

     Audits of contracts not only yield financial benefits to the
Agency, but also aid in improving Agency management.   We expect
to devote increased resources to auditing EPA  contractors and
subcontractors given the increased size of  the program and EPA's
conduct of more actual cleanups.  These audits also  play an
integral part  in supporting EPA's cost recovery actions.

     During fiscal 1990, we issued 20  Superfund contract audit
reports.  The  combined financial results of these audits were as
follows:

     Total Costs Audited                     $346,844,221
     Total Costs Accepted                    $345,406,173
     Total Costs Ineligible46                 $  1,314,354
     Total Costs Unsupported47                $   123,694
     Total Costs Unnecessary/Unreasonable48   $          0

     The OIG can choose to have the audits  performed by in-house
staff, independent public accounting firms, or another Federal,
State or local audit agency.  During fiscal 1990, our Superfund
     46  Costs questioned because of an alleged violation of a
provision of a law, regulation, contract, grant,  cooperative
agreement, or other agreement or document governing  the
expenditure of funds.

     47  Costs questioned because, at the time of  the audit,  they
were not supported by adequate documentation and/or  had  not been
approved by responsible program officials.

     48  Costs questioned because they were not necessary or not
reasonable.

-------
EPA Offlca of huoactof Ganaral Annual Sunarfund Report to the Conoraaa for Fiscal 1990         100

financial and compliance audits of  contracts were performed as
follows:

     Audits Performed by OIG  Staff                              2
     Audits Performed by Independent  Public Accountants       11
     Audits Performed by Defense  Contract Audit Agency         7

     Exhibit III contains a listing of  all Superfund audit
reports issued by the 016 during  fiscal 1990.

     We summarize three particularly  significant contract audit
reports below.

CHEM-TLE'S TERMINATION SETTLEMENT PROPOSAL

Scope and Objectives

     The Defense Contract Audit Agency  audited a Chem-Tle
Environmental Services, Inc.  termination settlement  proposal.
EPA terminated the contract for the convenience of the government
and the contractor submitted  the  proposal for $666,601 on a total
cost basis.  The objective of the audit was to determine whether
the settlement proposal was free  of material misstatement.

Findings

1.   Chem-tle Did Not Establish an  Acceptable Accounting System

     The contractor's accounting  system was not acceptable for
government contracting under  section  H.30 of the contract.
However, the auditors performed the review to the extent possible
in the circumstances.

2.   Chem-Tle Proposed $622.577 of  Costs That Were Questioned

     The auditors questioned  $622,577 of proposed costs involving
(1) unsupported General and Administrative expense costs, (2) a
difference between the fixed  labor  rates and the actual salary
claimed,  (3) unsupported travel,  lodging and per diem costs, (4)
direct charges to the contract for  insurance costs,  (5) quality
assurance costs lacking supporting  documentation, (6)  costs never
paid by the contractor,  (7) directly  charged start-up costs that
the contractor should have included in  the overhead  pool, and (8)
ineligible overhead costs.

-------
EPA Offlea nf Immaetor Ganaral Annual Sunarfund Raoort to tha Connrass for Fiscal 1990
                           101
Financial Results of Audit
Amount audited
Amount accepted
Ineligible costs49
Unsupported costs30
Unnecessary/unreasonable costs31

Recommendation
Federal Share
     $666,601
     $ 44,024
     $622,577
     $      0
     $      0
Total Costs
   $666,601
   $ 44,024
   $622,577
   $      0
   $      0
     We recommended  that the Contracting Officer make a final
determination on the costs questioned.

Agency Response

     In response to  our audit report,  the EPA Contracting Officer
sustained the $622,577  of ineligible costs we questioned.

KAAREN JOHNSON ASSOCIATES TRAINING SUPPORT SERVICES CONTRACT

Scope and Objectives

     An independent  public accounting firm audited the costs
claimed by Kaaren  Johnson Associates,  Inc. under a level-of-
effort cost-reimbursement type contract.  The contract was for
the design, development and delivery of training services to
EPA's Office of Solid Waste and Emergency Response.  The
objective was'to determine the allowability, allocability and
reasonableness of  the $2,298,272 claimed.  We summarize here two
audit reports issued on these costs.

Findings

1.   Kaaren Johnson  Associates Claimed Ineligible Costs

     The contractor  claimed $691,777 of costs ineligible under
the terms of the contract and the Federal Acquisition
     49
        Costs questioned because of an alleged violation of a
provision of a  law,  regulation,  contract, grant, cooperative
agreement, or other  agreement or document governing the
expenditure of  funds.

     50  Costs questioned because, at the time of the audit, they
were not supported by  adequate documentation and/or had not been
approved by responsible program officials.

     51  Costs questioned because they were not necessary or not
reasonable.

-------
EPA Office of Inspector General Annual
              1990
         102
Regulations.  The ineligible  costs  included (1)  lease termination
costs,  (2) equipment and  building lease payments after the
contract period,  (3) overhead,  fringe benefits and fees applied
to the  ineligible direct  costs,  and (4)  the difference between
the overhead and fringe benefit rates used and the rates
recommended by the auditors.

2.   Kaaren Johnson Associates  Claimed Unsupported Costs

     The contractor claimed $120,958  of unsupported costs
including  (1) award fees  not  yet determined,  (2)  legal and
accounting fees for which the contractor was unable to provide
adequate documentation for services provided,  (3)  other direct
costs not supported by vendor invoices,  and (4)  fees applied to
the unsupported costs.
Financial Results of Audits
Amount audited
Amount accepted
Ineligible costs52
Unsupported costs13
Unnecessary/unreasonable  costs54

Recommendations
Federal Share
   $2,298,272
   $1,485,537
   $  691,777
   $  120,958
   $        0
Total Costs
 $2,298,272
 $1,485,537
 $  691,777
 $  120,958
 $        0
     We recommended that  EPA not reimburse questioned costs and
evaluate the appropriateness of  participating in set-aside costs.

Agency Response

     In response to our audit reports,  the EPA Contracting
Officer sustained questioned costs of $715,984.32.   However,
n rjotiation of the contractual claim has been delayed due to the
contractor's bankruptcy proceedings.
     52  Costs questioned  because of an alleged violation of a
provision of a  law, regulation,  contract,  grant,  cooperative
agreement, or other agreement or document  governing the
expenditure of  funds.

     53  Costs questioned  because,  at the time of  the audit, they
were not supported by  adequate documentation and/or had not been
approved by responsible program  officials.

     14  Costs questioned  because they were not necessary or not
reasonable.

-------
                 ASSISTANCE TO EPA MANAGEMENT

      In  addition to  performing audits  and investigations,  the
Office of  Inspector  General  (OIG)  responds to  EPA management
requests for  OIG input  in  the development of regulations,
manuals, directives,  guidance and  procurements.  These  are
proactive  efforts to prevent problems  that might later  result in
negative audit  findings or investigative  results.   The  OIG
reviews  and comments on draft documents prepared by Agency
offices.   In  some instances, an OIG staff person attends meetings
of an EPA  work  group to provide input.  Fiscal 1990 was an active
year  for OIG  preventive assistance to  EPA management  in the
Superfund  area.

Technical Assistance Grants

      The EPA  Administrator requested in fiscal 1987 that the OIG
work  closely  with the Superfund office to develop and administer
the technical assistance grants program.   This program  assists
groups of  persons affected by Superfund sites.  Because these
grants are awarded to small groups without grants experience or
much  administrative  structure, the Administrator recognized that
this  program  presented  special management challenges.   In
response to this request,  in fiscal 1990  the OIG continued to
participate in  work  group  meetings and review  draft program
documents.

Cooperative Agreements

      We  have  been conducting Superfund cooperative  agreement
audits for several years and have  frequently found  significant
deficiencies.   These  audits are now statutorily required.   EPA
published  a regulation  on  cooperative  agreements and  Superfund
State Contracts for  Superfund Response Actions as an  interim
final rule in fiscal  1989.  The Agency cited the development of
this  regulation the Agency as a response  to our "capping"  report
on cooperative  agreement audits issued in fiscal 1987.  The OIG
helped to  develop this  regulation  by actively  participating in
workgroup  meetings and  review of drafts.   In fiscal 1990,  the OIG
also  participated in  development of the final  rule, issued on
June  5,  1990.

Coordination with Other Agencies

      Since EPA manages  the Hazardous Substance Superfund (Trust
Fund), EPA's  OIG  took on the task  of informing the  Federal OIG
community  (as well as appropriate  audit organizations)  of  the
mandated audit requirements.  The  Superfund Amendments  and
Reauthorization Act of  1986 (SARA) requires "...  the  Inspector
General of each department, agency or  instrumentality of the
United States which is  carrying out any authority.   .  ." under

-------
EPA Office of Inspector General Annual Suoerfund Report to the Congress for Fltcal 1990         104

SARA to conduct an annual audit of  uses  of  the Superfund.   In
July 1987, we formed a work group of representatives from several
OIGs and other audit organizations  of  those Federal departments
or agencies with significant  Fund-financed  responsibilities under
CERCLA or Executive Order 12580.  The  objectives  of our work
group are to:

     •    Clarify the statutory requirement;

     •    Coordinate schedules and  reports  under  the mandatory
          annual audit requirement;

     •    Discuss funding mechanisms for the mandatory audit
          work; and

     •    Discuss program areas of  concerns or audit findings.

     To accomplish these objectives, we  held two  work group
meetings this year and made individual contacts as needed.

     We continue to work with other OIGs and audit officials to
resolve Superfund accounting  and control problems.   The work
group identified the allowability of indirect  cost charges by
other Federal agencies for Superfund work as an issue.  As a
result, EPA officials began revising Agency policy on the
allowability of indirect costs.  In addition,  individual meetings
were instrumental in resolving misunderstandings  between EPA and
another Federal agency on the allowability  of  costs and
recordkeeping practices.

Superfund Orientation Course

     As Superfund spending has increased and the  program has
expanded and developed, the OIG has recognized a  need to be sure
that its auditors and investigators who  review Superfund have a
good understanding of the program.  Therefore,  we have developed
a special orientation course  explaining  the key aspects of the
Superfund program, including:

     •    Superfund and related legislation and regulations;

     •    The removal, remedial and enforcement parts of the
          Superfund program;

     •    Organizational structure  and functions  of EPA offices
          delegated specific  Superfund responsibilities; and

     •    The OIG's role and  responsibilities  concerning
          Superfund and the type of Superfund  audits the OIG
          performs.

-------
EPA Office of Inspector General Annual Simerfund Report to the Congress for Fiscal 1990	105

     All OIG  employees and OIG audit services  contractor
employees performing Superfund audits will take  this course.  We
will also offer  the course to other Federal OIGs and audit
organizations who perform audits in their own  agencies.   We
presented a pilot session of this course to a  cross-section of
OIG personnel in July 1990.  Following this session,  we made
additional changes to the instructional materials.   We listed the
course in the OIG Training and Development Sources  course
catalog.  The OIG will offer the course in fiscal 1991.

-------
EPA Office of Inspector General Annual Suoerfund Report to the Congress for Fiscal 1990	106

         REVIEW OF AGENCY'S SUPERFUND PROGRESS REPORT

     Section 301(h) of CERCLA, as amended by SARA, requires that,
•'On January 1 of each year the Administrator of the Environmental
Protection Agency shall submit an annual report to Congress of
such Agency'on the progress achieved in implementing this Act
during the preceding fiscal year."  The provision also requires
the inclusion of seven specific areas in the report.  CERCLA
requires the Inspector General to review this report "... for
reasonableness and accuracy and submit to Congress, as a part of
such report a report on the results of such review."

     The third Annual Report was due to Congress on January 1,
1990, covering fiscal 1989 activities.  The report was not
submitted to Congress until November 19, 1990.  Our review of the
report was submitted on October 18, 1990, to the Administrator
(Audit Report No. E1SFFO-11-0018-1100026).  Most of our audit
work for this review was conducted during fiscal 1990.

     Key information in some topics in the Annual Report was
reasonable and accurate.  However, we had concerns about the
reasonableness and accuracy of selected information from the
Comprehensive Environmental Response, Compensation, and Liability
Information System (CERCLIS).

     In our reviews of the fiscal 1987 and 1988 Annual Reports,
we identified problems with the accuracy of CERCLIS data on the
pre-remedial, removal and remedial programs.  Significant
portions of the accomplishments claimed in those reports were not
supported by valid source documents in the regions, and some
accomplishments were not recorded in the correct fiscal year.  In
a few cases, accomplishments were double counted in different
years, or did not meet the Agency's definition of an
accomplishment at all.  In contrast, we found enforcement data in
CERCLIS to be much more accurate.

     Throughout the course of these two reviews, we brought our
concerns to the attention of Office of Emergency and Remedial
Response (OERR) management.  After the fiscal 1988 audit, OERR
officials advised us of two corrective actions they were taking:
establishing a CERCLIS Data Quality Work Group to review input
controls; and performing monthly data quality audits.  However,
these actions did not occur in time to impact the fiscal 1989
data.

     We commend OERR for taking some actions to improve the
quality and reliability of the CERCLIS data.  However, at the
time of our audit, the actions actually taken did not fully
address our concerns.  The Work Group had not done any source
document data accuracy audits.  The Work Group actions had helped
to ensure that CERCLIS entries meet the official Agency

-------
   Office of Inspector General Annual Suoerfund Report to the Congress for Fiscal 1990         107

definitions of accomplishments and  are  complete.   However,  we
remained concerned about the validity of the support for data
entries in CERCLIS.  OERR had not performed  a detailed review of
input controls.

     As we found in our reviews of  the  last  two Annual Reports,
the process used to prepare the fiscal  1989  Annual Report was not
fully effective.  Although the Annual Report was  due to Congress
January 1, 1990, it was not submitted to the Office of Management
and Budget until March 1990.  One reason for this was the
lateness in issuing prior years' reports.  In fact,  while the
Report Coordinator was preparing the fiscal  1989  report,  he was
still devoting much of his time to  the  fiscal 1988 report (which
did not go to Congress until April  1990, 15  months after it was
due).  Similar delays in preparing  the  fiscal 1987 report slowed
the fiscal 1988 process.

     However, this year's process was much more efficient and
effective than in the past.  For example, the delivery of the
draft to the Office of Management and Budget occurred six months
earlier than in the prior year.  According to the Report
Coordinator, centering the fiscal  1989  report around a definite
theme (the Superfund pipeline, i.e., the cleanup  process from
site identification to actual remediation),  having increased
resources to work on it, and simplifying its format all
contributed to a more timely and readable report.

-------
EPA Office of Ininactof General Annual Suoerfund Report to the Congress for Fiscal 1990	108

                      INVESTIGATIVE ACTIVITY

     During fiscal 1990, the number of Superfund  investigations
conducted by the OIG  increased by  26 percent over fiscal 1989.
At the end of  fiscal  1990, there were 53 active Superfund
investigations, 25 percent of all  active OIG investigations at
EPA.

Contract Laboratory Program

     During fiscal 1990, the Office of Investigations initiated a
major investigative effort within  the Superfund program to detect
fraud in the Contract Laboratory Program  (CLP).   This effort is
directed at a  number  of CLP contractors.  Laboratory analyses
under the CLP  are the empirical basis for the entire Superfund
program.  Based on analysis of samples by these laboratories for
the presence of hazardous substances, the Superfund  program makes
cleanup decisions.  Fraudulent analyses could result in a danger
to the public  health  and safety, as well as  the unnecessary
expenditure of cleanup funds.  In  addition,  fraudulent analyses
could hinder the Department of Justice's efforts  to  collect the
cost of cleanups from responsible  parties.   Although the CLP
investigation  is very complex and  time consuming, significant
results have already  been achieved during fiscal  1990.

     Roy F. Weston, Inc., of Lionville, Pennsylvania,  has paid
the government $750,000 as part of a consent judgment arising
from charges that the company submitted false claims for payment.
These charges  were part of a civil action filed by the Department
of Justice under the  False Claims  Act.  Weston Analytics,  a
division of Roy F. Weston, Inc., obtained a  contract under the
CLP in June 1987 to perform certain laboratory tests on soil and
water samples  at its  laboratory in Lionville.  A  test for
volatile organic compounds had to  be performed on each sample
within ten days of receipt to ensure accurate results.   Weston
Analytics failed to complete certain of these tests  on time,
concealed this failure by backdating its testing  equipment,  and
then fraudulently billed EPA for the tests.   This practice
continued over the course of a year.  As a result, some of the
results submitted to  EPA were unreliable, and EPA's  responses to
environmental  hazards could have been affected.   In  addition to
the payment of $750,000, Weston agreed to voluntarily withdraw
from certain kinds of laboratory work at the Lionville facility
for a period from four months to a year, subject  to  EPA's
satisfaction with the compliance program Weston initiated in
response to the Federal investigation.

     This investigative effort continued into fiscal 1991.   A
number of indictments and several  guilty pleas resulted from this
effort in fiscal 1991, which we will discuss in next year's
report.

-------
EPA Office of Inspector General Annual Superfund Report to the Congress for Fiscal 1990 109
                                                                EXHIBIT I
                            UNITED STATES
              ENVIRONMENTAL PROTECTION AGENCY
                          WASHINGTON, D.C.
               HAZARDOUS SUBSTANCE SUPERFUND
                    SCHEDULE OF OBLIGATIONS
            FISCAL YEAR ENDED SEPTEMBER 30, 1990

Description                     Total        Accepted   Ineligible  Unsupported
Personnel Compensation &
  Benefits             $  156,428,448  $ 156,428,448  $        - $
Travel and Transportation
  of Persons               11,451,577      11,451,577
Transportation of Things        726,135         726,135
Rent, Communications and
  Utilities                 25,659,392      25,659,392
Printing and Reproduction      1,307,914       1,307,914
Other Contractual Services 1,121,549,372    1,108,464,764           -  13,084,608
Supplies and Materials         5,593,985       5,593,985
Equipment                  22,503,193      22,501,342           -      1,851
Land and Structures            270,414         270,414
Grants, Subsidies and
  Contributions            205,133,645     204,590,562           -     543,083
Insurance Claims and
  Indemnities                   5,143          5,143
Interest                          -             -
Unidentified                  (41.325)       (224.442)  	-      183.117
    GRAND TOTALS         Sl.55Q.5B7.flQ.3   $1.536.775.234  $            $13.812.659
The accompanying note  is an integral  part of this schedule.

-------
EPA Office of Inspector General Annual Superfund Report to the Congress for Fiscal 1990	110

                                                          EXHIBIT I
                                                         (continued)

                          UNITED STATES
               ENVIRONMENTAL PROTECTION AGENCY
                        WASHINGTON, D.C.

                HAZARDOUS SUBSTANCE SUPERFUND
                NOTE TO SCHEDULE OF OBLIGATIONS
              FISCAL YEAR ENDED SEPTEMBER 30, 1990

NOTE 1. SUMMARY OF SIGNIFICANT ACCOUNTING POLICIES

Basis of Presentation

     The Schedule of Obligations was prepared from information
provided by the EPA Financial Management Division based on
financial information contained in the Integrated Financial
Management System (IFMS) for the fiscal year ended September 30,
1990.  EPA's policy is to prepare this schedule in conformity
with accounting policies and procedures that are prescribed by
the Office of Management and Budget  (OMB),  which is a
comprehensive basis of accounting other than generally accepted
accounting principles.  This schedule is not intended to present
either the financial position or the financial results of
operations in conformity with generally accepted accounting
principles.

     Obligations, as presented in this Exhibit, were reported by
the Financial Management Division from the Year to Date
Obligation and Expended Totals Report, prepared from information
contained in the IFMS General Journal File for the current fiscal
year appropriation.  Total obligations from this report amounted
to $1,550,587,893.  The total reported obligations above were
compared to total obligations of $1,536,678,529, as shown on the
Report on Budget Execution (SF-133),  submitted to the OMB on
November 29, 1990.  The difference between the obligations
reported to us and the obligations reported to OMB amounted to
$13,909,364.  The was reconciled by adding to, or subtracting
from the Money Available by Appropriation (a monthly report),
certain general ledger account balances as of September 30, 1990,
to determine the obligations incurred and reported to OMB.  The
reconciling items consist of miscellaneous receipts, uncollected
debt allowances, discounts lost, and reimbursements, which should
not be included in obligations reported to OMB, and have been
consistent reconciling items in prior years.

     Included in the Schedule of Obligations is ($41,325), for
which there was no object class assigned to the transactions in
the General Journal File of IFMS.  We were informed by EPA
officials that no object class was required for certain

-------
EPA Office of hupector General Annual Suoarfund Report to the Congress for Flsrffl 1990	

                                                           EXHIBIT I
                                                          (continued)

transactions such as year-end accruals  and cash receipts.  The
unidentified object class  amount on the schedule was immaterial
in relation to total obligations.

Recording Transactions - Obligations - Nonpayroll

     Obligations are amounts  of orders  placed,  contracts awarded,
services received, travel  performed and similar transactions
during a given period that will require payments during the same
or future periods.  Such amounts reflect adjustments for
differences between obligations previously recorded and actual
disbursements  to liquidate those obligations.  The term
"obligation" includes both obligations  that have matured (legal
liabilities) and those that are contingent upon some future
performance, such as providing services or furnishing materials.
Obligations represent funds obligated in the current fiscal year
against the current fiscal year's appropriation, which may
include carry-over authority  for appropriations from prior years.
Obligations are recorded for  budgetary  purposes by appropriation
at the time they are incurred.

Recording Transactions • Obligations - Payroll

     Payroll obligations are  based upon actual personnel
compensation and benefits  recorded biweekly in the payroll
subsystem  (EPAYS) plus accruals at month-end and year-end.
Personnel compensation obligations amounted to $130,273,893,
which, based on EPA policy, were recorded as obligations for
budgetary accounting purposes.

Legal Limitations - Administrative Expense Ceiling

     Funding for the Superfund program  is achieved through a
separate annual, no-year appropriation.  The legal limitation set
by Congress on the Superfund  appropriation requires the Agency to
stay within an administrative expense ceiling.   Congressional
intent was to  limit intramural expenses to ensure that the
primary function of the Superfund of cleaning up hazardous waste
sites was protected.  Agency  policy is  that the legally binding
administrative expense ceiling placed on the Superfund
appropriation  be managed by the Office  of the Comptroller through
a distribution of specific ceilings to  the individual Responsible
Planning and Implementation Officers.

     Public Law 101-144, dated November 9, 1989, provided funding
to carry out the Comprehensive Environmental Response,
Compensation,  and Liability Act of 1980, with $1,575,000,000 for
fiscal 1990, to be derived from the Hazardous Substance

-------
EPA Office of Inspector General Annual Suparfund Report to the Congress for Fiscal 1990	112

                                                            EXHIBIT I
                                                          (continued)

Superfund, plus sums  recovered on behalf of the Hazardous
Substance Superfund in excess of $82,000,000 during fiscal  1990,
with all such  funds to remain available until expended.  The  law
also provides  that  no more than $220,000,000 be available  for
administrative expenses.   Added to this amount was $48,094,299  of
carryover authority available for Superfund administrative
expenses.

     Our analysis of  the  administrative expenses for the year
indicated that the  Superfund program obligated $223,675,787,  or
14.4% of total obligations,  for these administrative expenses,  as
defined by Agency policy.   The Agency defined administrative
expenses to include all object classes in the Schedule of
Obligations except  Other  Contractual Services, Land and
Structures, and Grants, Subsidies and Contributions.  These
amounts are within  the dollar limitation set by Congress,
adjusted by the carryover authority amount.

-------
EPA Office of Inspector General Annual Stmerfund Report to the Congress tor Fiscal 1990 113
                                                                 EXHIBIT II
                            UNITED  STATES
              ENVIRONMENTAL PROTECTION AGENCY
                          WASHINGTON,  D.C.
               HAZARDOUS SUBSTANCE  SUPERFUND
                   SCHEDULE OF DISBURSEMENTS
            FISCAL YEAR  ENDED  SEPTEMBER 30, 1990
Description                     Total       Accepted
Personnel Compensation &
  Benefits               $141,524,181    $141,621,547
Travel and Transportation
  of Persons                10,746,635      10,746,394
Transportation of Things         588,266        588,266
Rent, Communications and
  Utilities                 25,078,845      25,078,845
Printing and Reproduction      1,247,837      1,247,837
Other Contractual Services   749,045,638     748,973,024
Supplies and Materials        4,652,735      4,652,472
Equipment                  21,859,048      21,858,843
Land and Structures             15,352         15,352
                                                   Ineligible    Unsupported
Grants, Subsidies and
  Contributions
147,363,164     146,766,597
Insurance Claims and
  Indemnities                   5,143          5,143
Interest                         (17)          (17)
Unidentified               f 8.786.870)    fl6.139.521)
   GRAND TOTALS
                                                   $ (110,817)   $
                                                     (30,362)
                                                          50
                                          13,451

                                            241
 72,611
   263
   205


626,929
                                       7.352.601
                       SI.093.339.957  Si.085.414.782   $ (141.1261   $8,066,301
                       ^^^^^^^^^^^^^^^^^s  ^^^^ss^^^^ssssssssss   «_^_L_SSX^^^_ *   • • • • • • • •••
The  accompanying note is an integral part of this schedule.

-------
EPA OffiM of lo»POCtOf General Annual Suoerfund Report to the Conoraas for Fiscal 1990	114

                                                          EXHIBIT II
                                                         (Continued)


                          UNITED STATES
               ENVIRONMENTAL PROTECTION AGENCY
                        WASHINGTON, D.C.

                HAZARDOUS SUBSTANCE SUPERFUND
               NOTE TO SCHEDULE OF DISBURSEMENTS
              FISCAL YEAR ENDED SEPTEMBER 30, 1990


NOTE 1. SUMMARY OF SIGNIFICANT ACCOUNTING POLICIES

Basis of Presentation

     The Schedule of Disbursements was prepared from information
provided by the EPA Financial Management Division based on
financial information contained in the Integrated Financial
Management System (IFMS) for the fiscal year ended September 30,
1990.  EPA's policy is to prepare this schedule in conformity
with accounting policies and procedures that are prescribed by
the Office of Management and Budget (OMB),  which is a
comprehensive basis of accounting other than generally accepted
accounting principles.  This schedule is not intended to present
either the financial position or the financial results of
operations in conformity with generally accepted accounting
principles.

     Disbursements, as presented in this Exhibit,  were reported
by the Financial Management Division from a combination of
disbursement data for appropriations 68-20X8145 and 68-20M8145
taken from the year To Date Disbursement Totals Report, prepared
from information contained in the IFMS General Journal File.
Total disbursements from this report amounted to $1,093,339,957.
The total reported disbursements agreed to total outlays of
$1,093,339,957 from the Report on Budget Execution (SF-133),
submitted to the OMB on November 29, 1990.

     The Schedule of Disbursements includes ($8,786,870) for
which no object class was assigned to the transactions.  We were
informed by Agency officials that no object class was required
for input of certain transactions.  The majority of transactions
with no object class were processed as automatic disbursements
and travel vouchers which were offsetting transactions affecting
Accounts Payable, Non-Federal in the general ledger.   Also, a
small number of transactions with high dollar amounts were
processed as cash receipts for a balance sheet transfer.  The
transaction code for cash receipts was used to debit general
disbursements and credit various general ledger accounts for

-------
EPA Office of Inspector General Annual Simerfund Report to the Congress for Fiscal 1990	115

                                                            EXHIBIT II
                                                           (Continued)

advances previously recorded as disbursements.   The cash receipt
transactions were used to reverse the original transaction when
funds were received for reimbursements, such  as travel advances,
collection of  Superfund State Contracts, and  Interagency
Agreements.

Recording Transactions - Disbursements • Nonpayroll

     Disbursements represent the amount of  cash outlays made to
liquidate obligations.  These cash outlays  represent funds
disbursed during the current fiscal year against either prior
years' or current year's appropriations.  Nonpayroll
disbursements  are recorded on the cash basis  of accounting.

Recording Transactions - Disbursements • Payroll

     Personnel compensation disbursements are recorded biweekly
in the payroll subsystem (EPAYS).  Disbursements from the
Schedule of Disbursements amounted to $117,942,517,  which
represented personnel compensation costs paid during fiscal 1990
on a cash basis.   However, our review indicated that the
personnel compensation costs reported on a  cash basis should have
been $129,208,675.   See Finding No. 4 for additional details.

Recording Transactions - Property and Equipment

     EPA's policy is to capitalize property and equipment with a
cost greater than $5,000 and a useful life  of two years or
greater.  Disbursements for equipment recorded in this Exhibit
are presented  on a cash basis,  including capitalized and non-
capitalized items.

-------
EPA Office of Inspector General Annual Superfund Report to the Congress for Fiscal 1990 116
                                                                EXHIBIT III
                                                                  1 OF 3
                    SUPERFUND AUDIT REPORTS
                    ISSUED  DURING FISCAL 1990

INTERNAL AND MANAGEMENT AUDITS  AND SPECIAL REVIEWS
Final
Report
Number   Description

Reviews Required By CERCLA
0100227  EPA PROGRESS REPORT REVIEW, FISCAL 1988
0400040  RI/FS REVIEW, BAIRD & McGUIRE, MA
0400039  RI/FS REVIEW, IRON HORSE PARK, MA
0400038  RI/FS REVIEW, NYANZA, MA
0400041  RI/FS REVIEW, SELMA TREATING CO., CA
0100492  TRUST FUND AUDIT, FISCAL 1989

Performance Audits
0100274  ARCS CONTRACTS BIDDING AND AWARD
0100187  CERCLIS REPORTING
0100415  CONFIDENTIAL DISCLOSURE STATEMENTS-REG 5
0100222  COST-PLUS-AWARD-FEE CONTRACTS
0100207  COST RECOVERY COLLECTIONS-HQ REPORT
0100172  COST RECOVERY COLLECTIONS-REGION 3
0100152  COST RECOVERY COLLECTIONS-REGION 4
0100126  COST RECOVERY COLLECTIONS-REGION 5
0100230  OVERSIGHT OF POST-SETTLEMENTS-REGION 2
0100485  OVERSIGHT OF POST-SETTLEMENTS-REGION 3
0100519  REMOVIAL ACTIVITIES-REGION 4
0100228  SF  INNOVATIVE TECH. EVAL. (SITE) PROGRAM

Follow-Up Reviews
0400013  COOPERATIVE AGREEMENT ADMIN.-REGION 8
0400036  COST RECOVERY ACTIONS AGAINST PRPS

Special Reviews
0400006  BUNKER HILL SITE, ID
0400019  CERCLIS POST-IMPLEMENTATION STUDY
0400044  DISPOSAL OF WASTES FROM SITE INSPECTIONS
0400007  OLIN CORPORATION, OH
0400027  SITE-SPECIFIC TIMEKEEPING-ENV. RESP. BR.
0400023  UNANNOUNCED SITE REVIEW-BETTER BRITE, WI
Audit
Control Number
E1SFF9-11-0015
E1SGG7-14-0003
E1SGG8- 14-0002
E1SGGB-14-0004
E1SGG9- 14-001 3
P1SFF9-1 1-0032
E1SGB9-11-0021
E1SFF9-15-0023
E1SFFO-05-0111
E1SFF9-03-0144
E1SJF9-05-0274
E1SJF9-05-0274
E1SJF9-05-0274
E1SJF9-05-0274
E1SJC9-02-0055
E1SJDO-03-0185
E1SGB9-04-0016
E1SKF9-11-0031
E1SGG9-08-5000
E1SJGO-11-0022
E6FGGO- 13-2005
E1SFGO-15-0020
E1SGG9-05-0275
E6FGG9-05-0480
E1SHF9-11-0039
E1SHGO-05-0192
Date
Report
Issued
3/28/90
9/27/90
9/27/90
9/27/90
9/27/90
9/24/90
4/20/90
3/12/90
7/25/90
3/28/90
3/28/90
3/ 6/90
2/14/90
1/25/90
3/29/90
9/19/90
9/27/90
3/28/90
3/30/90
9/24/90
1/30/90
6/14/90
9/28/90
21 5/90
8/ 7/90
6/29/90

-------
EPA Office of Inspector General Annual Superfund Report to the Congress for Fiscal  1990 117
EXHIBIT III
2 OF 3
SUPERFUND AUDIT REPORTS
ISSUED DURING FISCAL
Final
Report
Number Audi tee
COOPERATIVE AGREEMENTS
0300035 ALABAMA DEPT. OF ENV. MANAGEMENT-PA/ SI
0300037 CALIFORNIA DEPT. OF HEALTH-STRINGFELLOW
1990

Audit
Control Number

P5BGN9-04-0189
S5BG*8-09-0202
0300098 CALIFORNIA ST. WATER RES. CONTR. BD.-S. BAY S5BKN9-09-0267
0300048 GEORGIA DEPT. OF NATURAL RESOURCES-PA/SI
0300010 KENTUCKY NAT. RES. & ENV. PROT. CAB. -PA/SI
0300045 MISSISSIPPI DEPT. OF ENV. QUALITY-PA/SI
0100245 NEW YORK ST. DEPT. ENV. CONS. -MULTI -SITE
0300049 NORTH CAROLINA DEPT. OF HUMAN RES. -PA/SI
0300095 OREGON DEPT. OF ENV. QUALITY-CORE PROGRAM
0300096 S. ADAMS CTY., CO-ROCKY MT. ARS./COM. CITY
0100078 TEXAS WATER COMMISSION-BIOECOLOGY SITE
0300033 TEXAS WATER COMMISSION-HIGHLANDS SITE
0100079 TEXAS WATER COMMISSION-SIKES SITE
0100043 LOCKWOOD ANDREWS NEWMAN-TEXAS CONTRACTOR
INTERAGENCY AGREEMENTS
0100029 ARMY CORPS OF ENGINEERS-FISCAL 1988
0100027 ENERGY DEPARTMENT-FISCAL 1988
0100213 FED. EMERGENCY MGMT AGENCY-FISCAL 1988
0100058 INTERIOR DEPT-FWS & USGS-FISCAL 1987
0100428 INTERIOR DEPT-ENV PROJ REV-FISCAL 1988
0100475 INTERIOR DEPT-FWS, RECLAM. & USGS-FY88
0100200 INTERNAL REVENUE SERVICE-FISCAL 1988
0100080 JUSTICE DEPARTMENT-FISCAL 1988
P5BGN9-04-0213
P5CGN8-04-0091
P5BFN9-04-0190
P5BGL9-02-0366
P5BGN9-04-0129
P5CHN9-10-0151
P5BHN9-08-0092
E5BGL9-06-0133
P5BGN9-06-0188
E5BGL9-06-0134
E5DGLO-06-0041

M5BFLO-11-0017
M5BFLO-11-0016
M5BFLO-1 1-0023
M5BFL9-1 1-0046
M5BFLO-1 1-0034
M5BFLO-1 1-0035
M5BFLO-1 1-0024
M5CFLO-11-0019

Date
Report
Issued

3/27/90
3/30/90
9/28/90
5/ 1/90
11/17/89
4/20/90
3/30/90
5/ 3/90
9/27/90
9/27/90
12/13/89
3/20/90
12/13/89
10/25/89

10/16/89
10/16/89
3/26/90
ll/ 9/89
8/13/90
8/24/90
3/19/90
12/15/89

-------
EPA Office of Inspector General Annual Superfund Report to the Congress tor Fiscal 1990 118
                                                                EXHIBIT III
                                                                  3 OF 3
                    SUPERFUND AUDIT REPORTS
                    ISSUED DURING FISCAL 1990
CONTRACT AUDITS

Final
Report
Number   Auditee

Preaward Proposals
0100427  ECOLOGY AND ENVIRONMENT,  NY
0300093  FOUR  SEASONS INDUSTRIAL,  INC., SC
0100362  JACOBS ENGINEERING GROUP,  INC., CA
0300007  O.H.  MATERIALS COMPANY, OH-ZONE 4A
0300036  O.H.  MATERIALS COMPANY, OH-EQUIP. RATES
0300047  O.H.  MATERIALS COMPANY, OH-EQUIP. RATES
0300084  OHM REMEDIATION, OH
0100354  RADIAN CORPORATION, TX
0100426  RADIAN CORPORATION, TX
0300023  REIDEL ENVIRONMENTAL SERVICES, OR
0300001  WESTINGHOUSE HAZTECH,  GA

Interim Audits
0100047  CDM FEDERAL PROGRAMS CORPORATION, MA
0200004  O.H.  MATERIALS CORPORATION, GA-PALMETTO

Final Audits
0100182  CHEM-TLE ENVIRONMENTAL SERVICES, CA
0100224  KAAREN JOHNSON ASSOCIATES, MD
0100225  KAAREN JOHNSON ASSOCIATES, MD
0100226  KAAREN JOHNSON ASSOCIATES, MD
0100026  SRI INTERNATIONAL, CA

Indirect Costs
0300029  O.H.  MATERIALS COMPANY, OH-FISCAL 1988

System Survey
0300027  NUS CORPORATION, MA-FISCAL 1986
Audit
Control Number
D9AKLO-02-0306
P9AHNO-04-0326
D9AKLO-09-0223
P9AHN9-05-0460
P9AHN9-05-0347
P9AHNO-05-0260
P9AHNO-05-0365
D9AKLO-06-0207
D9AKLO-06-0222
P9AHN9-10-0167
E9AHN9-04-0344
D9BFLO-01-0022
E9BHM9-04-0233
D9CHLO-09-0127
P9CFL9-11-0043
P9CFL9-11-0043
P9CFL9-11-0043
D9CKLO-09-0023
P9DHN9-05-0439
P9EGN9-01-0230
Date
Report
Issued
8/ 9/90
9/20/90
6/27/90
10/31/89
3/27/90
4/27/90
8/16/90
6/22/90
8/ 7/90
21 1/90
10/17/89
10/27/89
12/ 1/89
3/ 7/90
3/28/90
3/28/90
3/28/90
10/13/89
2/22/90
2/15/90

-------
EPA Offlca of bisnactor Ganaral Annual Suoarfund Raoort to the Conorass for Fiscal 1990
                                           119
             APPENDIX: ACRONYMS AND ABBREVIATIONS
AOEM

ARCS
ATSDR

BLP
CA
CALSTARS

CERCLA

CERCLIS
CFR
COE
Confidential
statements
CPAF
DEQ

DHS

DHS-TSCP

DOE
DOI
EPA
Alabama Department of Environmental
Management
Alternative Remedial Contracting Strategy
Agency for Toxic Substances and Disease
Registry
Bunker Limited Partnership
California
California State Accounting and Reporting
System
Comprehensive Environmental Response,
Compensation, and Liability Act of 1980, as
amended
Comprehensive Environmental Response,
Compensation, and Liability Information
System, the Superfund management information
system
Code of Federal Regulations
Corps of Engineers
Confidential Statements of Employment and
and Financial Interest
Cost-plus-award-fee (contract type)
Department of Environmental Quality, State of
Oregon
Department of Health Services, State of
California
Department of Health Services-Toxic
Substances Control Program, State of
California
Department of Energy
Department of Interior
Environmental Protection Agency

-------
EPA Office of Inspector General Annual Sunarfund Report to the Congress for Fiscal 1990	120
EPAAR                Environmental Protection Agency Acquisition
                     Regulations
ERB                  Environmental Response Branch (EPA)
ERCS                 Emergency Response Cleanup Services
FAR                  Federal Acquisition Regulations
FBI                  Federal Bureau of Investigation
FEMA                 Federal Emergency Management Agency
FMO                  Financial Management Officer
FS                   Feasibility Study
FSR                  Financial status Report
FWS                  Fish  and Wildlife Service, U.S. Department of
                     the Interior
FY                   Fiscal year
GA                   Georgia
GDNR                 Georgia Department of Natural Resources
HQ                   Headquarters
HWD                  Hazardous Waste Division  (EPA Region 10)
IAG                  Interagency agreement
IAP                  Individual acquisition plan
ID                   Idaho
IFMS                 Integrated Financial Management System  (EPA)
IPA                  Independent public accounting firm
IRS                  Internal Revenue Service
KNREP                Kentucky Natural Resources and Environmental
                     Protection Cabinet
LNRD                 Land  and Natural Resources Division
                     (Department of Justice)
MA                   Massachusetts

-------
EPA Office of Inspector General Annual Sunaffund Report to the Conor«s« for Fiscal 1990
                                           121
MD

MDEQ


mg/1

NCDHR

NCP or National
Contingency  Plan

NPL

NY

NYSDEC


OCI

OERR


OH

OIG

OMB

OR

ORD

OSC

OSWER


PA

PA/SI

PPAS

PRP

RA
Maryland

Mississippi Department of Environmental
Quality

milligrams per  liter

North Carolina  Department of Human Resources

National Oil and Hazardous Substances
Contingency Plan, 40  CFR Part 300

National Priorities List

New York

New York State  Department of Environmental
Conservation

Office of Criminal Investigations (OCI)

Office of Emergency and Remedial Response
(EPA)

Ohio

Office of Inspector General

Office of Management  and Budget

Oregon

Office of Research and Development (EPA)

On-Scene Coordinator

Office of Solid Waste and Emergency Response
(EPA)

Preliminary Assessment

Preliminary Assessment/Site Inspection

Personal Property Accounting System (EPA)

Potentially Responsible Party

Remedial Action or Regional Administrator
(EPA)
RCRA
Resource Conservation and Recovery Act

-------
EPA Office of Inspector General Annual Sunerfund Report to the Congress for Fiscal 1990
                                           122
RD
RD/RA
RI
RI/FS
ROD
RPM
RWQCB

SACWSD

SARA

SC
SF
SI
SITE

SMOA
SOL
SSC
SWRCB

TAT
TDI
TES
Trust Fund
TWC
TX
Remedial Design
Remedial Design/Remedial Action
Remedial Investigation
Remedial Investigation/Feasibility Study
Record of Decision
Remedial Project Manager
Regional Water Quality Control  Board,
California
South Adams County  (Colorado) Water and
Sanitation District
Superfund Amendments and Reauthorization Act
of 1986
South Carolina
Superfund
Site Inspection
Superfund Innovative Technology Evaluation
program
Superfund Memorandum of Agreement
Statute of limitations
Superfund State Contract
State Water Resources Control Board,
California
Technical Assistance Team
Toluene diisocyanate
Technical Enforcement Support  (EPA contracts)
Hazardous Substance Superfund
Texas Water Commission
Texas

-------
EPA Office of Inspector General Annual Suparfund Report to the Congress for Fiscal 1990          123

USGS                  United States  Geological Survey,  Department
                       of  the Interior

WI                     Wisconsin

-------