.inn,,.. States
                        Environmental Protection
                        Agency
                       jnice ot
                       Solid
P'joiication 9355 0-39F5 j
J-r.e 1992
                              y PeSoonse
  SEBV
Remedial  Action  Report
Documentation for Operable Unit Completion
 Office ot Emergency ana Remedial Response
 Hazardous Site Control Division OS • 220W
                                         Quick Reference Fact Sheet
The progress in moving a site toward the ultimate goal of deletion from the NPL typically involves several
operable units or multiple phases of construction over a period of several years. The purpose of the Remedial
Action Report is to document the activities that occur under each specific remedial action operable unit at
a sue. This report provides documentation that a particular operable unit has met us objectives as well as
summary information for subsequent inclusion in the Superfund Site Close Out Report. The report also
serves as an excellent source of lessons learned for project managers and designers of future remedial action
projects.

The Environmental Protection Agency's (EPA) Superfund Comprehensive Accomplishments Plan (SCAP)
and Strategic Targeted Activities for Results System (STARS) define completion of an operable unit
remedial action as: conclusion of construction activities, performance of a final inspection, determination
that the remedy is operational and functional, and preparation of an operable unit Remedial Action Report.
Acceptance of the Remedial Action Report by the Regional Superfund  Branch Chief, demonstrates the
formal completion of the operable unit remedial action and completes the requirements for meeting the
target.
 Figure 1:  Remedial Action Report Elements
       introduction

       Chronology of Events

       Performance Standards and Construction
       Quality Control

       Construction Activities

       Final Inspection

       Certification that Remedy is Operational
       and Functional

       Operation and Maintenance

       Summary of Project Costs
                     CONTENT OF THE REPORT

                     Figure 1 highlights the essential elements that should
                     be included in the Remedial Action Report.

                     Introduction

                     This section provides a short (approximately I page)
                     general description of the sue and remedy imple-
                     mented. Site location and description, history, com-
                     ponents of the selected remedy, and specific con-
                     taminants dealt with during the remedial action are
                     examples of items to address. Sufficient informa-
                     tion should be provided to permit a reader unfamiliar
                     with the sue to understand the challenges faced by
                     those involved in the remedial action.

-------
Chronology of Events

This section provides a summary  of the  major
events associated with the remedial action. A sug-
gested starting point is the Regional Administrator's
signature on the Record of Decision or the date the
remedial design assignment was issued.

Pprformance  Standards and Construction
        Control
This is probably the most important section of the
Remedial Action Report.  Performance Standards
are the criteria or requirements that the remedial
action contractor met in completing the project.
Performance Standards include cleanup levels, qual-
ity criteria, and other substantive requirements, or
limitations found in the Record of Decision. Each
Performance Standard should be addressed by pro-
viding the standard, the maximum level permissible,
the results of field sampling, the basis for the deter-
mination that the standard was met (except for Long
Term Remedial Actions), and the location and fre-
quency of the  tests.

This section of the Remedial Action Report should
 also provide a summary of the implementation of the
 construction quality control plan and provide an
 assurance that the remedial action is complete.  A
 table should  be included that  lists the types  of
 samples taken and provides a comparison of test
 results with the specified standards to be achieved
 by the remedial action.

 Construction Activities

 This section is a narrative description of the con-
 struction activities undertaken for the remedial ac-
 tion. Quantities excavated* cleanup levels achieved,
 and materials and/or equipment used should be
 addressed in  this section and may be presented in
 tabular format in support of the narrative. The name
 and specific role of the major design and remedial
 action contractors should be provided. Participation'
 by other f&aerattigeneies'SUghjas mcJLJ4S. Army!
 Corps of Engineers or the: U.£  Bureau.of Reclamiat:
  rion should be discussed?
This is also the section where information on  les-
sons learned" should be provided.  While a major
portion of this narrative will deal with problems
encountered during the construction, successes
should be documented as  well.  Included in the
discussion of problems should b* th~ options con-
sidered, the process used to select a final solution,
and the causes of any delays encountered.  The
discussion of successes should include time or cost
saving measures employed or the use of innovative
solutions to problems encountered.

Final Inspection

This section documents the pre-fmal and final in-
spections conducted by the contracting party and
contractor at the completion of construction of the
operable unit.  The section should contain a brief
description of the deficient construction items (punch
list) reported and resolved during the pre-final and
final  inspections and a  list of attendees at the
inspection(s).  The final resolution of all deficient
 items should be documented.

 Certification  that Remedy is Operational and
 Functional

 For those operable units where the Remedial Action
 includes a shakedown period (e.g., operation of a
 system for the treatment of leachate or ground wa-
 ter), the Remedial Action Report should include a
 statement that the work was performed within de-
 sired  specifications and that the remedy is opera-
 tional and functional. For other operable units (e.g.,
 the excavation and off-site disposal of contaminated
 soil)  the certification will be an affirmation that
 performance standards have been met The basis for
 the determination should also be provided.

 Operation and Maintenance

 An operation and maintenance plan is required for
 virtually all remedial actions. This section should
 tdiiscuss the highlights of the operation and mainte-
  nance plan, as well as provide insight to potential
  problems/concerns.

-------
Summary CT Oroiect Costs

This section should provide the final costs for the
project and compare them to the original remedial
action estimate. It is required for fund-lead projects
and provided whenever possible for Potentially Re-
sponsible Party lead projects. Presentation of this
i nformation may be in tabular or narrative form. The
need for and cost of any modifications during con-
struction should  be  noted in this section.  If the
project was performed by PRPs, a summary of the
EPA oversight costs should also be appended to the
report.

PREPARATION OF THE REPORT

The Remedial Acnon Report should be prepared by
someone familiar with both the design and construc-
tion ef forts associated with the remedial action. This
familiarity provides the best background to discuss
the successes and difficulties of the project. This
.•oiowiedge is often iimiteo :o just ;wo parties  :.~.e
EPA Remerha!  Project Manager iRPVH and :he
contr.-cting party for the remedial action (e.g.. the
PRPs. the U.S. Army Corps of Engineers, the State.
or EPA's ARCS contractor).   In either case, the
contracting party has had a major role in the imple-
mentation of the project. While the EPA RPM can
and sometimes  may prepare the Remedial Action
Report, it is recommended that the contracting party
be tasked to  prepare the report as pan of the work
assignment, IAG, or settlement agreement.

Figure 2 is a flow diagram showing the individuals
typically responsible for preparation, review, and
approval of the  Remedial Action Report under the
several possible scenarios. For most operable units
the Remedial Action  Report should  be prepared
within sixty days of the  Final Inspection  of the
completed construction.    However, for systems
requiring a shakedown period, the report should be
drafted at the completion of construction and final-
 Figure 2: RA Report Preparation, Review, and Approval

-------
.zed wiimn sixty days of the detenomauon that the
system is operational and functional.  The recom-
mended  maximum report length is twe.uy   (20)
pages.  The Remedial Action  Report should be
signed and dated by the preparer and submitted to
the EPA RPM for review and comment.  Formal
completion of the Remedial Action as weh as the
Remedial Action Report occurs with the approval of
the report by the Regional Superfund Branch Chief.

A Remedial Acnon Report should be prepared fol-
lowing each operable unit remedial acdon. When
there is more than one operable unit at a site, a Site
Close Out Report (Preliminary, Interim or Final)
snouid be prepared following the successful tn:pie-
mentanon of the final operable unit remedial acaon.
Only one Site Close Out Report should be prepared
for the entire  site, regardless  of the number of
operable units. The Remedial Acaon Reports for the
individual operable units should be used as die basis
for development of the Site Close Out Report The
preparation of Site Close Out Reports is covered m
Procedures for  Completion and Deletion of Na-
tional Priorities List Sites. EPA/540/G-89/002, dated
Apnl, 1989 and subsequent updates.
   For additional information on Remedial Action Report preparation please contact:

                           Office of Emergency and Remedial Response
                                 Hazardous Site Control Division
                      Design and Construction Management Branch* (OS-220W)
                                        (703) 308-8393

  	* Call your RD/RA Regional Coordinator	
 v>EPA
       United States
       Environmental Protection
       Agency
       Washington, DC 20460

       Official Business
       Penalty for Private Use
       5300
                        First-CUss Mail
                        Postage and Fees Paid
                        EPA
                        Permit No. G-35

-------