SEWAGE TREATMENT PLANT
CONSTRUCTION COST INDEX
  U.S. DEPARTMENT OF HEALTH, EDUCATION, AND WELFARE

  Public Health Service

-------
SEWAGE TREATMENT  PLANT
CONSTRUCTION COST INDEX
       Construction Cost Trends
   Municipal Waste Treatment Works
U.S. DEPARTMENT OF HEALTH, EDUCATION,
          AND WELFARE
          Public Health Service
  Division of Water Supply and Pollution Control
        Washington, D.C.  20201

-------
              Public Health Service Publication No. 1069
U.S.  GOVERNMENT PRINTING OFFICE, Washington, D.C.—1963

-------
                       CONTENTS
                                                          Page
Foreword			     v
Introduction			      1
Background			     2
Need for Index	     3
Assumptions and Base Data for Index. _		     5
Development of the Cost Index	     8
Computation of National Index		_ _     12
Computation of Individual City Index	     13
Discussions	     14
Conclusions	     15
References			     16
APPENDICES

A. Map  of  20  Index Cities and  Their Assigned  Areas of   PaBe
     Influence			    18

B. Design Data for a 1.0-MGD High Rate Trickling Filter
     Plant	    19

C. Material and Labor Cost Analysis of the Construction Cate-
     gories for  a 1.0-MGD High Rate Trickling Filter Plant
     at Kansas City, Mo., August 1, 1962 (table)	    22

D. Sewage Treatment Plant Process  Equipment—Manufac-
     turers' Composite Experience Curve and PHS Process
     Equipment Index Curve (figure)	    25

E. Table of Total Plant and Category Costs for  20  Index
     Cities..		    26

F. Cost  Curves for the Eight  Construction Categories  and
     Total Construction of PHS Model Plant, Kansas City,
     Mo., 1962	    28

G. Municipal Waste  Treatment Plant Cost Indexes 1930-62
     (charts and table)			    30

                                                           iii

-------
                        FOREWORD


  Construction costs have risen steadily since the mid-1930's.  The
rate of increase varies between the different construction elements such
as labor, materials and equipment, and between the different types of
construction.
  Contract award data have proven useful for evaluating progress in
waste treatment works construction and in estimating future construc-
tion requirements.  During a period of rising costs, however, such data
need to be adjusted to a standard base to assure comparability. This
can be done through use of an appropriate construction cost index.
Unfortunately, existing construction cost indexes were designed  for
types of construction other than waste treatment works or are too gen-
eral in nature for this purpose.
  After a preliminary investigation of earlier work,  the design of a
construction cost index for municipal  waste treatment plants was
undertaken nearly 2 years ago by  the Construction Grants Branch,
Division of Water Supply and Pollution Control.  Personnel of  the
Construction Statistics Division, Bureau of the Census, and of the De-
partment of Civil Engineering, Northwestern University, were very
helpful in the initial stages  of this  work.  The treatment plant con-
struction cost index, now complete, is presented in this  report.  A com-
panion cost index for sewer  construction is currently under develop-
ment.
  This work was produced by Prof. Raymond M. Jones of Howard
University under the supervision  of Mr.  Peter  P.  Rowan, Chief,
Evaluation Section, Construction Grants Branch,  Division of Water
Supply and  Pollution Control, Public Health Service.  Engineering
consultation was provided by Mr. Paul D. Haney, Black &  Veatch,
Consulting Engineers, Kansas City, Mo., and computer  programing
by Mr. William H. Mills, Jr., of the Basic Data Branch, Division of
Water Supply and Pollution Control, Public Health Service.
                                   DAVID H. HOWELLS, Chief,
                                   Construction Grants Branch,
                                   Division of Water Supply and
                                     Pollution  Control.

-------
                     INTRODUCTION
  Grants-in-aid for municipal waste treatment works construction
authorized under the Federal Water Pollution Control Act in 1956,
have been accompanied by a steady increase in the dollar volume of
construction contracts awarded for these facilities.  An accurate as-
sessment of the increased construction activity and estimate of future
construction needs require a thorough understanding of the changing
purchasing power of the local and Federal funds invested in waste
treatment works construction.  One approach was to consider cost in-
dexes already available. An examination of existing construction cost
indexes, however, disclosed no apparent applicability to waste treat-
ment works construction and it became evident that indexes designed
specifically for sewage treatment plants and  sewers  were needed.
Subsequently a sewage treatment plant construction cost index was de-
veloped and is the subject of this report, the latter portion of which
discusses the several cost indexes examined.
  A price or cost index number is the ratio of the sum of the prices or
costs of a product or service in a given period divided by the sum of
the prices or costs for similar products or services for a base period (1).
A price index differs from a cost index in that a  price index is in-
fluenced by the prices of factors, whereas a cost index is influenced b;
prices  and quantities of factors entering the "standard product" at
two different periods.  More specifically, a

       Construction  p

       Index
where

PI, P2, P3 + ' *  ' PI, are prices of the factors making  up a "standard
product" of construction, "a" is any given construction period, and
"b" is the base period of construction; and a
Index          .b
                                                             (2)
where
Pi,P2, P3 + ' • ' Pn, and "a" and "b" are the same as in equation (1) and
Qi» Qa» Qs + ' * ' Qn are the quantities of  the factors making  up  a
"standard product" of construction.

-------
  The "standard  product" of construction in this development is a
sewage treatment plant of fixed design and specifications, combined
in proper proportion to represent the series evaluated.  The factors
entering are: skilled and common labor, construction materials, proc-
ess equipment, construction equipment, and overhead and profit,
  A cost index may either be a "floating base" type or a "fixed base"
type (#). The "floating base" refers to a quantity variable; i.e., the
quantity (Q) factors may vary from period to period with the price
(P) factors either increasing or decreasing due to internal or external
causes.  The  "fixed base" index  has constant quantity  factors; i.e.,
there  is no change in the quantity (Q) factors from period to period
and consequently the cost  may  vary due to external  causes only.
Indexes of each base type are common.
  This report deals with the development of a fixed base, weighted,
cost index, which  is believed to be a substantially accurate indication
of the purchasing power of funds invested in sewage treatment plant
construction.   There is no better  means of measuring the relative
purchasing power of money than is offered by  a comparison of the
changing prices of the commodities with  which  an industry deals in
the units on which business transactions are based.
                      BACKGROUND

  In its broad and generic meaning, an index number is an average of
relatives or variations.  If the variations measured are those of com-
modity prices, an index of prices is obtained; index numbers of wages,
interest rates, profits, production, and a large number of other meas-
urable phenomena also have been computed.  Each of the applications
of index numbers may be subject to peculiarities of its own; and, in
every case, the average is drawn  for the specific purpose for which it
can appropriately be used.
  Index numbers were first used to measure the rise or fall of prices,
i.e., the inverse movement of the general exchange value of money;
and the  term itself was coined in  this connection.  In 1838 Porter
used the term "index  prices," and in 1869  the  London  Economist
(#) called the sum of the relatives of 22  prices, which it compiled,
the "total index number."  The  term "index number" quickly came
into common usage to denote the  prices of individual commodities
averaged at each period, their total sum, or an average of them—this
last meaning being the most popular.

-------
   A price index number, whether it relates to all prices, or merely
 to those of a single commodity group, is a series of averages for price
 distribution at successive dates.  As such, it measures only the change
 in the general tendency of the distribution.  It fails to reveal the
 changes in  their internal structure and conceals changes which may
 reflect on the reliability of the index number as a representative value.
 Only within the last several decades has attention been centered on
 these aspects of changing prices.  Previously, the complex variations
 in the internal price structure, which are of vast economic significance,
 were apt to be regarded merely as troublesome obstacles to the calcula-
 tion of reliable averages.
   History  reveals that price indexes fail to reflect the changes  in
 internal structure, such as technological advances, progressive im-
 provements in business organizations, and changes in the prices of the
 various elements of production, all of which may result in increasing
 output being accompanied by decreasing  money costs.
   Economically, "cost" means the surrender or destruction of value,
 or the performance, of some irksome activity as a means of production
 of commodities or the acquisition of  income.  The classical  school
 gives three  rival explanations of cost; namely, (1) psychological  or
 pain costs,  (2) labor  costs, and (3) money costs, or, expenses of pro-
 duction (3).  Construction cost  encompasses all these  philosophies
 and includes materials, machines, men, and money.   More specifically,
 construction cost is equal to the sum of the cost of:
    (1) Materials    =concrete,  lumber,  iron, steel,  etc.,  used  in
                       construction;
    (2) Machines    = process equipment and contractor's equipment
                       used in construction;
    (3) Men        = skilled and  common (heavy  construction)
                       labor employed during construction; and
     (4) Money      = overhead charged  and profit earned during
                       construction,
 or,
 *   Construction  cost—M1+M2-fM3+M4                     (3)
                    NEED FOR INDEX

  A review of the several general-purpose construction cost indexes,
such as those of the American Appraisal Co., Associated General Con-
tractors, E. H. Boeckh & Associates, Marshall & Stevens, and Engi-
neering News-Record (ENR), disclosed no adequate basis for assum-
ing that any of these accurately measure the changing cost of waste
treatment plant construction due to weight and/or price bias.  From
a practical standpoint, though, an index such as the ENR Construction

     704-8780—68	3                                           3

-------
Cost Index (4) possesses certain advantages. It is well known, simple,
and fairly well understood—having been used for some time in the
construction industry (calculated back to the year 1903).  This index
was established in 1921 to diagnose and track the wild fluctuations in
prices after World "War I.  The quantity factors are:
     (1)  200 hours of common labor (including fringe benefits),
    (2)  25 CWT of structural steel,
    (3)  1.088 Mbf of 2 by 4's S4S lumber,
    (4)  6 barrels  of cement.
  This gives a rudimentary idea of the cost of building materials used
in general heavy construction as well as the cost of common labor.  In
addition, the ENR Construction  Index  is published monthly  over a
fairly broad base, using data from  20  selected cities.  The  disad-
vantages possessed by this  index with respect to sewage treatment
plant construction are:
    (1)  It does not  include the most important commodities used
          ('process equipment and skilled labor)  in this type of con-
          struction—a quantity bias.
    (2)  It does not represent materials cost-in-place or even  on  the
          job, which  could differ substantially from  the wholesale
          prices of these same materials—a price 'bias.
    (3)  It uses a  weighting that is not representative of modern de-
          sign and construction practices—a weight bias.
  The development of a satisfactory index requires the  elimination
of all or as many as possible of the disadvantages inherent in existing
indexes; namely, the quantity, weight, and price biases.  A new index
must  also be comparable throughout the required period  in  which
comparisons are to be made.  Continuity  for former periods can only
be maintained by  calculating backward in time and there are many
reasons why this is sometimes not possible. The labor rates involved
constitute an important reason, especially where the series is long or
where there have been several changes in the components of the index.
In addition, the original data used in computations years ago may not
be readily available, requiring time and resources to assemble.   Some-
times such data are not available.
  There are two possibilities which might be investigated for the elim-
ination or reduction of the biases inherent in available indexes.  The
first would necessitate the use of part of the various general construc-
tion index data (5, 6, 7, 8) and/or primary data from other sources,
e.g., Department of Commerce Reports,  Bureau  of Labor Statistics
(BLS) Reports, and business and government magazines or journals,
to construct, by estimating quantity and weight parameters, an index
number  for sewage treatment  plant  construction.  This alternative
would require that the quantities and weights be estimated and there

4

-------
is considerable uncertainty as to the accuracy Avith which this could be
done.
  The second alternative, the one developed herein, is the construction
of an econometric model from real prices and quantities for a statisti-
cally representative sewage treatment plant utilizing published price
data  that are available for the period investigated.  Theoretically,
this is the best method to pursue, for the index does reflect the true
quantities it represents.  Furthermore, this index lias the obvious ad-
vantage of being its own test for the base period.  Having a fixed base,
surveys could be made from time to time to see if the base still reflects
sewage treatment plant construction practice.  This method will pro-
vide a good measuring stick to study the trends and magnitude of
sewage treatment plant construction in constant dollar values.
ASSUMPTIONS  AND  BASE DATA  FOR  INDEX
  In the development of this construction cost index for sewage treat-
ment plants, designed as a fixed base, weighted index, certain assump-
tions were made:
      1. The hourly output of labor remains constant in  spite of
    changing wage rates. That is, when the wage rates rise (or fall)
    because labor supply lags behind (or exceeds) demand, the hourly
    output of labor is assumed to remain constant.
      2. The quantities  and kinds of materials used will remain con-
    stant and available during the periods under study.
      3. Modern treatment plant construction techniques date back to
    the year 1930.
  "Within the limitations of these assumptions, the index may be used
for (a)  estimating construction and equipment costs at various dates;
(&)  checking present costs with costs for similar work during pre-
vious years; (c) verifying other cost data; and (d)  forecasting future
cost trends.
Weighting

  This index does not reflect the cost of land; engineering, legal, and
fiscal services; and errors, omissions, and changes subsequent to con-

-------
tract  award.  It does include the following "indicators" that are
common to sewage treatment works: (a) cost of materials, (b) cost
of process equipment, (c) construction labor cost,  (d) contractor's
plant costs  (contractor's  equipment), and (e) overhead and profit.
Process equipment is peculiar to sewage treatment works.


Base  Period

  In order to provide a comparable base to other Federal indexes, the
ftf>-month period January 1, 1957, through December 31, 19f>9, was
selected as a base for this index.  This time period conforms to the
postwar base  period for  Federal Index numbers as defined by the
Bureau of the Budget.
Geographical  Locations

  Prices of materials and services vary considerably throughout the
country.  An index based on average prices and costs (countrywide)
would not necessarily be acceptable for local or regional use.  Conse-
quently, regional indexes are necessary for each of the country's major
commercial marketing areas for  which price data are available.
These areas, separated on a county line basis, represent areas of influ-
ence for each of the following 20 trade centers:

          Atlanta, Ga.                     Kansas City, Mo.
          Baltimore, Md.                  Los Angeles, Calif.
          Birmingham, Ala.                Minneapolis, Minn.
          Boston, Mass.                   New Orleans, La.
          Chicago, 111.                     New York, N.Y.
          Cincinnati, Ohio                 Philadelphia, Pa.
          Cleveland, Ohio                 Pittsburgh, Pa.
          Dallas, Tex.                     St Louis, Mo.
          Denver, Colo.                   San Francisco, Calif.
          Detroit, Mich.                   Seattle, Wash.

  These trade centers are those for which Engineering News-Record
publishes monthly  price data.  The  National Index is based  on the
sum of the cost of  identical plants built in each of the 20 city areas.
A map showing the 20 cities  and their assigned areas of influence is
to be found in appendix A (9).
 Design Characteristics  of Model Plant

   An analysis of contract awards for sewage treatment plants, assisted
 under the Federal Water Pollution Control Act during the  period
 1956 through 1962, revealed an average hydraulic capacity of 1.34

-------
million gallons daily (MGD), a design population of 12,000, and a
contract cost of $40 per capita (10,11}.  The most frequent treatment
process was the high rate trickling filter.  This information was to
provide the basis for the  design of a hypothetical plant, but since
there is very  little difference in the physical size of the structural
components or hydraulic requirements of a 1.34-MGD and a 1.0-MGD
high rate  trickling filter  plant, a 1.0-MGD plant was used as  the
model for  the cost index.  Since various types of sewage treatment
plants are now being constructed, allowances were made to incorporate
unique units in the model plant in order that the index would be valid
for all types of municipal  waste treatment works.  The cost estimate
of this plant was predicated on  idealized conditions,  representing
minimal costs under circumstances prevailing in Kansas City, Mo.,
in August  1962.  Design data and a layout of the plant are  included
in appendix B.  Design characteristics are as follows:

General.  The plant was designed for a population of 10,000 people,
an average flow of 1.0 MGD, a maximum flow of 2.5 MGD, a biological
oxygen demand  (BOD)  of 200 mg/1, a recirculation ratio of 1% to 1,
and an overall BOD reduction of 92 percent.
  The plant includes a comminutor, with a bar screen serving as a
bypass device, Parshall  flume, preaeration tank with grit removal,
primary sedimentation tanks, a settled sewage pumping station with
provision for recirculation, high rate trickling filters, secondary sed-
imentation tank, chlorine contact tank, primary and secondary diges-
ters, and a sludge filter building which also contains an office and
laboratory.  Sludge drying beds are provided as an auxiliary feature.
Facilities to allow for prechlorination and postchlorination are also
provided.

flow Through the Plant.  The plant flow is divided into the follow-
ing segments:
       (1)  By gravity through the comminutor.  Parshall flume, pre-
    aeration tanks, and primary sedimentation tanks;
       (2)  By pumping from the wet well following the primary sedi-
    mentation tanks to a distribution box for gravity application to
    the trickling filters;  and
       (3)  By gravity from the trickling filters to the secondary sedi-
    mentation tank, recirculation structure, chlorine contact tank, and
    to the outfall sewer.

Recirculation of Flow.   Recirculation of plant flow is accomplished
by a pneumatically operated  valve and piping system  connecting the
recirculation structure with the wet well of the pumping station.  The
operation of this valve is automatically controlled by the sewage level
in the pumping station wet well using an air bubbler system.

-------
  Sludge collected in the primary sedimentation tanks is pumped to
the digester and  sludge from  the secondary sedimentation tank is
recirculated, by pumping, to the aerated grit chambers.

Bypass Connections.  Provision for bypassing is provided as follows:
      (1) Between the comminutor and the Parshall flume,
      (2) From the wet well of the pumping station,
      (3) Between the trickling filters and the secondary sedimenta-
    tion tank, and
      (4) From the recirculation structure.

Maintenance.  Separate  drains are provided in each of the basins to
allow for cleaning and maintenance.  The piping and layout of the
aerated grit chambers and primary sedimentation tanks are arranged
so that any combination of these chambers and tanks can be removed
from service.

Other.  Provision is made for doubling the capacity of the plant.  All
utilities are available at the plant site.
          DEVELOPMENT OF COST INDEX
Category  Assignment

  To develop the cost index it was necessary to consider the various
major categories of  a construction job, in  this instance the hypo-
thetical treatment plant.  The construction categories were assigned
as follows:
        A. Excavation and fill,
        B. Reinforced  concrete,
        C. Miscellaneous iron  and steel,
        D. Pipe,  valves, and fittings,
        E. Process equipment, pumps, and motors,
        F. Sand and rock for filter media and drying bed fill,
        G. Buildings, and
        H. Other  items.
  As discussed earlier,  the costs of  land;  engineering; legal and
fiscal services; errors, omissions, and changes subsequent to contract
award are not included since the index is predicated on a contract cost
basis.  For the purpose of estimating these excluded items, an allow-
ance of 20 percent of contract cost can be used.

8

-------
  Basis for Unit Construction Cost.  To obtain the unit construction
  costs for the model plant, it was necessary to determine quantities of
  material and labor required to build the plant.  This was done by a
  quantity analysis of materials and labor for the model plant, utilizing
  prices and wages prevailing in the Kansas City area during August
  1962, as locally reported.

  I/nil Prices for Material and Labor.   To provide for a continuing
  pricing basis, the estimated material prices and labor wages ascer-
  tained by the study of data from the Kansas City area were compared
  with the corresponding  prices and wages reported by Engineering
  News-Record  to be prevailing in Kansas City, Mo., during August
  1962. Where differences were found, the ENR unit value prevailed
  and the quantity of the  unit was adjusted to produce the predeter-
 mined dollar value for the component.  This caused a slight modifi-
 cation in design quantities. The modified design quantities were used
 with the reported unit prices for each of the  20  cities included  in
 this report.  Appendix C lists the  various materials and labor that
 comprise these components for each category of construction of the
 model plant.

 Process Equipment.  Process equipment required a unique approach,
 as an analysis of the literature, manufacturers' catalogs and brochures,
 and discussions with consulting engineers disclosed no standardized
 units of weights or measures as well as no continuing published pric-
 ing data. Since it was found that the process equipment (category E)
 amounts to approximately $156,000, or 34 percent  of the  total plant
 construction cost, it became necessary to establish a common frame
 of reference which could  be priced on a continuing basis from regu-
 larly reported unit prices.
   Consultation with equipment  manufacturers disclosed that process
 equipment factory prices closely follow the production cost of the
 following  combination of  materials with  an  equal  allowance for
 labor.

                                                     Percent
     Steel and machine products	,	90
     Castings and forgings	10
   The process equipment  factory prices, however, are f.o.b. point of
 manufacture and  do not  include freight, royalties, resale, and the
 other after plant costs.  The BLS (12) wholesale prices, which include
these after plant costs, were selected for use with  this category as
 follows:
    Structural Steel Shapes—for steel and machine products,
                                       and
    Pig Iron, No. 2, Foundry—for casting and forgings.

-------
  An index curve was developed using these materials in the pre-
viously  defined ratio for  the process equipment based on  the BLS
wholesale prices.   This curve was submitted  to the manufacturers
for comparison and comment.  In  practically  every  instance,  the
index curve was in close agreement with the manufacturers' experience.
This is demonstrated graphically in appendix D.
Construction Component  Costs

  The following fundamental components are normally used in cost
analyses of construction  work: (a)  material, (£>) labor,  (c)  con-
tractors plant costs, and  (d)  overhead and profit.  Since  material,
labor, and  contractor's plant cost data were available for the model
plant, these components were used as a starting point in developing the
cost index.  The fourth component, overhead and profit, was estimated
on a percent basis of the three preceding  determinate values.  The
allowance for overhead and profit was obtained by using approxi-
mately 15 percent of material costs, 15 percent of contractor's plant
costs, and 25 percent of the labor cost.
  The table on page 11 shows the component costs for the eight con-
struction categories used in the development of the index.
  The following assumptions and explanations refer to the categories
in the table.
       1. It was assumed that the materials used for forms and shoring
    for reinforced concrete  could be used three times.
       2. Category (F), Sand and Rock, includes only the filter media
    of the  trickling filters and the sand fill of the sludge drying beds.
       3. Category (G), Buildings, includes the cost of concrete block,
    brick, doors, and windows, etc., but does not include framing costs
    which  are included under iron and steel or reinforced concrete.
       4. Category (H), Other Items, includes the costs of plumbing,
    heating and ventilating, electrical and other items.
 Category Division

   A review of several studies (13,14,15,16,17,18, 19) made on the
 construction cost of sewage treatment plants revealed that materials
 are, indeed, the chief cost ranging from 48 to 74 percent for all types
 of plants, and between 54 and 66 percent  for trickling filter plants.
 Labor ranged from a low of 20 percent to a high of 29 percent, and
 the "other" (contractor's plant, overhead and profit, etc.) ranged from
 a low of 16 percent to a high of 19 percent. The distribution of con-
 struction cost for the hypothetical plant shown in the table is in close
 agreement with these findings.

 10

-------
Construction Categories, Components, Costs and Percent of Costs for a 1.0 High Rate Trickling Filter Plant (Kansas City, Mo.—August 1962)
Construction category
A. Excavation and Fill
B. Reinforced Concrete. _ - , ,
C- Miscellaneous Iron and SteeL
D. Pipes, Valves, and Fittings. _
E. Process Equipment, Pumps
and Motors. 	
F. Sand and Rock 	
G. Buildings _ __ _ _
H. Other Item? -
T. Total Plant 	 ___

Material cost
Dollar value
$7, 370. 99
49, 295. 33
6, 542. 64
26, 241. 57
118, 659. 63
9, 259. 18
6, 167. 23
28, 241. 31
251, 777. 88
Percent of
category
17.01
43.91
51. 13
56.51
75.92
52.62
43.40
47.76
54.49
Labor cost
Dollar value
$11, 184. 44
41, 837. 98
3, 993. 05
13, 244. 17
14, 409. 93
4, 631. 26
6, 533. 50
21, 221. 74
117,055.97
Percent of
category
25.82
37.27
31.20
28.52
9.22
26.32
45.98
35.89
25.33
Contractor's plant
Dollar value
$18, 144. 91
3, 874. 41
249. 52
1, 030. 31
3, 766. 59
1, 002. 99
150. 61
lt 580. 75
29, 800. 09
Percent
of
category
41.88
3.45
1.95
2.22
2.41
5.70
1.06
2.67
6.45
Overhead and profit
Dollar value
$6, 615. 28
17, 287. 97
2, 010. 93
5, 922. 53
19, 453. 79
2, 702. 96
1, 359. 30
8, 085. 49
63, 440. 25
Percent
of
category
15.28
15.40
15. 71
12.75
12.44
15.36
9.57
13.67
13.73
Total category cost
Dollar value
$43, 315. 62
112, 259. 59
12, 796. 14
46, 438. 58
156, 289. 94
17, 596. 39
14, 208. 74
59, 129. 29
462, 034. 29
Percent
of
plant
9.376
24297
2.770
10. 051
33. 826
3.808
3.075
12. 797
100. 000

-------
Computation of  Total  Category Cost

  Since material and labor unit prices are the only cost values his-
torically available in published form, it became necessary to express
contractor's plant, overhead, and profit as a fixed percent of the labor
and material cost.   These percent values were determined from the
estimated costs for these items as reported for the model plant (table,
p. 11).  This was done for each construction category in five steps as
follows:

For  Category A—August  1962:
    (1) Material plus labor cost=$18,555.43
                              =42.83 percent of total category cost
    (2) Contractor's plant cost =$18,144.91
                              =41.88 percent of total category cost
    (3) Material plus labor plus
          contractor's plant cost = $36,700.34
                              =84.71 percent of total category cost
    (4) Overhead  and   profit
          cost                =$6,615.28
                              =15.28 percent of total category cost
    (5) Total category cost for
          excavation and fill   =$43,315.62
                              =100 percent of total category cost

Extending  Unit Prices To Obtain Total Material and Labor Cost.
Unit prices were multiplied by the  total  quantity factors to deter-
mine the total quantity cost for each item.  These total quantity costs
were then combined to yield total category costs for construction in
terms of material and labor. This is illustrated for each category in
appendix C for the Kansas City, Mo., area.
  The combined labor and material cost for each  category was then
increased by the appropriate percent values, allowing for contractor's
plant, and overhead and profit, to obtain the total category cost.  This
procedure was followed for each of the 20 cities over the entire period
of this study, using unit prices prevailing in each location.   The sum
of these total category costs  for a given  time determines the total
plant construction cost for that period.


      COMPUTATION OF  NATIONAL  INDEX

  The first step  in  computing the national index was to determine
the average plant cost for each of the 20 cities over the base period
from  January 1957  through December  1959.  The sum of these 20
average values is the base for the index and equals 100.

12

-------
   The national index for any period is the ratio of the sum of the 20
 cities' plant costs for that period,  to the sum of 20 cities' average
 plant costs for the base period, multiplied by 100.
   For example, the national index for August 1962 was calculated
 as follows:
     Sum of the 20 cities' plant costs for August 1962=$9,552,556.78
     Sum of the 20 cities' average plant costs for base=$8,928,457.60
      period
     National index=$9,552,556.78,
                    $8,028,457.60
                                X100              =       106.99
 COMPUTATION  OF  INDIVIDUAL  CITY INDEX


  The plant index was determined for each city by substituting indi-
vidual city total plant cost in the index formula.  The base period
plant cost is the sum of the average plant costs for the base period
divided by 20.   The ratio of the particular city's plant cost to the base
period cost yields the city index.  For August 1962 :

    Base period average plant cost        =$446,422.88
    Kansas City plant cost               =$462,034.29
    Kansas City index =         '   X 100 - 103.49
              ^        ip44t>,4ifii.oo

  The various category costs and plant costs for the 20 cities for the
base period are included as appendix E.  A graphic presentation of
these costs  (and indexes) for the Kansas City, Mo., area are included
in appendix F.
  Price data for each of the 20 cities for the month of August for the
years 1930 through 1962 were extracted  from the ENR index and the
BLS wholesale prices.  Where these sources did not cover the entire
range of time, interpolation was used based upon similarity of trades
or materials at the commencement of the series.  This was done pri-
marily for  labor values in the early 1930's.  Electronic data proces-
sing equipment was used to calculate the individual city indexes and
the national index for each year.
  Plant indexes for  each of the 20 cities, and the national index from
1930 through 1962 for the month of August, -are tabulated in appen-
dix G.  These indexes will be extended  on a monthly basis from cur-
rent price data published by Engineering News-Record and the BLS
wholesale prices.
                                                             13

-------
                      DISCUSSIONS
  Since waste treatment works have generally been considered to fol-
low the ENR Construction Cost Index, a comparison of this index
to the Public Health Service Sewage Treatment Plant (PHS-STP)
Construction Cost Index was undertaken.
  In order to compare the indexes, both were converted to a base of
1930=100.  The converted PHS-STP Index is included in appendix
G and is shown graphically in the following figure, along with the
converted ENR-C Index.
400
300
200
        CONSTRUCTION COST INDEXES
        1930*100
   1930
                     1940
1950
                                                        I960
  Only during 1930-40 did the two indexes follow a similar path.
Since 1940 there has been a widening divergence between the PHS-
STP Index and the ENR-C Index. Based on 1930= 100, these indexes
in 1962 were 430 for ENR-C and 310 for the PHS-STP Index.
  A comparison of the last 6 years disclosed that the ENR-C Index
has increased at a rate almost twice as great as the PHS-STP Index.
This period of time coincides with the period of increased activity in
the municipal waste treatment works construction field.
  Because the PHS-STP Index is based on information peculiar to
sewage treatment plant construction, its value for this specialized field
is believed to be much greater.
 14

-------
  In order to insure that the PHS-STP Index continues to reflect
current practice in the sewage treatment plant construction industry,
revaluation of the index base will be undertaken periodically at inter-
vals of not over 10 years.   Alteration, revision, or modification of the
index may be required by changes in amount and/or kinds of materials,
new developments, or uses of process equipment.  Changes in con-
struction methods and techniques will  also be considered in each
revaluation.
                      CONCLUSIONS
   (1) Comparison of the PHS-STP Construction Cost Index with
the narrow-based, but widely accepted, ENR Construction Cost Index
disclosed that there were substantial differences.
   (2) The PHS-STP  Index is believed to be representative of cost
changes peculiar to municipal sewage treatment plant construction.
   (3) The study shows that although sewage treatment plant con-
struction costs have increased steadily during the last 30 years, the
rate of increase has declined since 1956.
   (4) This index may  be used to evaluate past construction activity
and to estimate future sewage treatment plant construction cost re-
quirements for the 20 areas of influence in the United States as well
as for the Nation as a whole.
   (5) As an indicator  of sewage treatment plant cost trends and as
a service to the public, the PHS-STP Index will be extended on a
monthly basis, and reexamined periodically to account for changes in
fundamental assumptions.
                                                             15

-------
                          REFERENCES
 1. Mudgett, B. D.,  "Index Numbers."  John Wiley &  Sons, New York, N.Y.
     (1951).
 2. Anon., "Encyclopedia  of Social Sciences."  Vol. 7,  p. 652, Macmillan Co.,
     New York, N.Y. (1935).
 3. Anon., "Encyclopedia  of Social Sciences."  Vol. 4,  p. 467, Macmillan Co.,
     New York, N.Y. (1935).
 4. Anon., "ENR's 1956-57 Annual Report on Construction Cost.''  Engineering
     News-Record, 159,16, 83 (Get. 17,1957).
 5. Fick, H. H., "Coat Indexes for Water Works Property."  Journal American
     Water Works Assn., 45,779 (August 1953).
 6. Fick, H. H., "Weber,  Fick and Wilson  Water Works Index."  Engineering
     News-Record, 168,12,87 (Mar. 22,1962).
 7. Handy, W. W., "Public Utility Construction Cost Index Service."  W. W.
     Handy, Consulting Engineer, Baltimore, Md., Bull. No. 1 (1924).
 8. Whitman,  E. B., "Public Utility Construction  Cost  Indexes and Financial
     and  Operating Ratios." Whitman, Requardt & Smith, Consulting  Engi-
     neers, Baltimore, Md., Bull. No. 24 (1936).
 9. Thoman, J. R.,  and  Jenkins, K. H.,  "How To Estimate Sewage Plants
     Quickly."  Engineering News-Record, 161, 26,  64  (Dec. 25, 1958).
10. Rowan, P.  P., Jenkins, K. H., and Butler, D. W., "Sewage Treatment Con-
     struction Cost."   Journal Water Pollution Control Federation, 82, 6,  594
     (June 1960).
11. Howells, D. H., and DuBois,  D. P.,  "Design Practices and Costs for  Small
     Secondary  Sewage  Treatment  Plants in the Upper  Midwest."  Sewage
     and  Industrial Wastes, SO,  11, 1327  (November 1958).
12. Anon., "Wholesale Price Index."  Bull. No. 1168, Oha. 1 and  10, U.S.  Dept.
     of Labor, BLS, Washington, D.C. (1954).
13. Logan, J,  A., "An  Analysis of the  Economics of Sewage Treatment.*'  Un-
     published report, Northwestern University Technological Institute (1962).
14, Anon., "Materials Chief Cost in Building New Sewage Works."  Sewage and
     Industrial Wastes, 23, 9,1123 (September 1951).
15. Anon., "Construction  Studies of  PWA  Projects." Federal Works Agency,
     Exhibits 33a, 34a, and 35a, Washington, D.C. (1943).
16. Picton, W.  L.,  "Distribution of the  Dollar  Expenditure for Water and
     Sewage  Works—New  Construction,  1952."   Business Service Bulletin
     No.  55, U.S. Dept. of Commerce, Washington, D.C. (August 1954).
17. Picton, W.  L., "Distribution of Water and  Sewer Utilities Capital  Ex-
     penditures in  1958."  Construction Review,  7, 2, 11 (February 1961).
     U.S. Dept. of Commerce, BDSA, Washington, D.C.
18. Anon., "Relative Cost of Material  and Labor—Construction  of  Water and
     Sewage  Systems."  Monthly Labor Review, 40, 1,  145 (January 1935).
19. Dyer,  H. B., "Relative Cost  of Material and  Labor—PWA  Construction."
     Monthly Labor Review, 41,1,117 (July 1935).
16

-------
Appendices
                 17

-------
APPENDIX A
The 20 Index Cities and Their Assigned Areas of Influence
18

-------
APPENDIX B


Design Data for a 1.0-MGD High Rate Trickling Filter Plant

DESIGN SPECIFICATIONS

1. Comminutor and  Par shall Flume
  The comminutor structure and comminutor are sized for an average
flow of 1.0 MGD and a maximum flow of 2.5 MGD. The channel of
the comminutor structure is 1'3" wide.  With the use of stop plates,
flow can be diverted either through the comminutor or a hand-cleaned
bar screen.
  The  Parshall flume has a 12"  throat and is sized on  the same
basis as the  comminutor.  This is the only metering device used in
the treatment plant.
2. Preaeralion  Chamber
  The  preaeration chamber includes two rectangular units  with a
combined detention time of 45 minutes based on a flow of 1.0 MGD.
The inside dimensions of each chamber are 8'0" wide,  26'0" long,
and a water depth of ll'O".
  Aeration  is provided by blowers forcing air  through  diffusers.
Each blower is sized to deliver 70 cfm of free air. This amount of air
allows for 0.1 cubic foot per gallon of sewage based on a flow of 1.0
MGD.  These blowers are sized so that one unit shall act as a standby.
  Mechanical grit-collecting equipment provides for removal of col-
lected grit and a manually operated skimmer is used to remove scum.
3. Primary  Sedimentation Tank
  This tank contains two parallel operated mechanically cleaned rec-
tangular units, at  design flow having combined rates of: Surface set-
tling rate, 1,000 gpd per square foot; detention time, 1.5 hours; weir
rates, 10,000 gpd per linear foot.
  The inside dimensions of each tank are 12'6" wide, 40'0" long,
with an average water depth of 8'4".
  A manually operated skimmer is used to remove scum.
4. Pumping  Station
  The pumping station has three 1.0-MGD, constant speed, vertical-
turbine-type pumps which are located directly  above the  wet  well.
Space is provided for the installation of two additional pumps when
required for plant  expansion.

                                                           19
    704-aTa o   ea    t

-------
   These pumps are automatically controlled by the levels of the sewage
 in the wet well using an air bubbler system, to maintain a flow of 3
 MGD to the trickling filters, providing a recirculation ratio of from
 1,5 to 1 to 0.2 to 1 as total plant flow varies.  The pumps discharge
 through a 12" discharge line to the distribution box.
  The wet well dimensions are 7'0" wide, 26'0" long, and the depth
 below the pump base is 14'0".

 5.  Trickling Filter
  The trickling filters consist of two units.  The hydraulic loading on
each filter of 10 MGD based on a total plant flow of 1.5 MGD.  Each
unit has an inside diameter of 65'0" and the minimum filter media
 depth above the underdrains is 6'0".
  For future needs, provision is made in the distribution box to serv-
ice two additional filters.
  The rotary distributor and jets for each filter are sized for  a mini-
 mum rate of 520 gpm and a maximum rate of 870 gpm.
 6.  Secondary Sedimentation  Tank
  Secondary settling is provided by a single, mechanically cleaned,
 rectangular tank having a surface settling rate of 800 gpd per square
foot.  Weir rates, 10,000 gpd  per linear foot.  Design flow for this
unit is 1.5 MGD.
  This tank is 25'0" wide, 75'0" long, and has an average water depth
of 8'0".

 7.  Chlorine Contact Tank
  The rectangular chlorine  contact tank has a detention time of 45
minutes based on a flow of 1.0 MGD. The tank dimensions are 16'0"
 wide, 26'0" long, and the  average water depth of lO'O".  Wood baf-
fles are  placed to prevent  currents and to allow for adequate  mixing
of the chlorine.
 8.  Chlorinators
  Two automatically controlled, solution-fed chlorinators are pro-
vided.  One chlorinator feeds the  influent  end of the aerated grit
chamber and the other chlorinator feeds the chlorine contact tank.
These chlorinators are located together in a well-ventilated build-
 ing with automatic chlorine detection  devices for safety purposes.
  The chlorine storage building is equipped with a hoist and a hoist
rail for unloading chlorine cylinders from a truck.  This building has
space available to store seven 1-ton cylinders.
 9.  Digesters
  Two digesters are provided—one for primary, and one for second-
ary sludge. A structure,  located between  the digesters, houses the
heat exchanger, motor control center, and sludge pumps.

20

-------
  The primary unit is 25'0" inside diameter and has a capacity of
1.0 cubic feet per capita based on 10,000 population.  This unit has
a fixed cover and the sludge is heated and mixed with two draft-tube-
type mixers.
  The secondary unit is 35'0" inside diameter and has a capacity of 2.0
cubic feet per capita based on 10,000 population. This unit has a float-
ing cover and the sludge is not mixed or heated.
10.  Sludge Filter Building
  This building contains a vacuum filter, chemical storage space, labo-
ratory and office.  The filter is designed for an allowable loading of 6
pounds dry solids per square foot per hour.  Provision  is made for
conditioning chemicals.
11.  Sludge Drying Beds (Auxiliary)
  The drying beds consist of three underdrained rectangular units.
Dimensions of each unit are 40'0" wide, 60'0"  long, with earthen
sides.  These  beds allow for  a loading of 0.75 square foot per capita
based on 10,000 population.
                         r
                                                     i    i
                                              L
10
10
10
Plan View of the Public Health Service Index 1.0-MGD High Rate
                      Trickling Filter  Plant
      1. Comminutor and Parshall Hum*
      2. Preaeratton Grit Chamber
      3. Primary Settling Tank
      4. High Rate Trickling Rlt»r
      5. Final Settling Tank
      6. Recirculatlen Structure
 7. Chlorine Contact Tank
 8. Sludge Digesters
 9. Sludge Filter Building
10. Sludge Drying Beds
11. Chlorine Storage Racks
12. Chlorlnation Building
                                                                21

-------
APPENDIX €
   Material and Labor Cost Analysis of the Construction
                                 Plant at Kansas City,
Category

Excavation and
Fill

Reinforced
Concrete


Miscellaneous
Iron and Steel



Piping, Valves,
and Fittings

Process Equip-
ment, Pumps
and Motors

Sand and Rock


Buildings
Other Items
Total Plant.


Components
Rock (cu yd) 	
Earth and sand (cu yd) . _

Transit mixed concrete
(cu yd)
Reinforcing steel (100 Ibs)
Plyform (1,000 sq ft) -


Structural shapes (100
Ibs)
Cast Iron (tons) 	 	
Reinforcing steel 	


Cast Iron (tons) 	
Vitrified clay pipe (ft) 	
Reinforced concrete pipe
//+•»
(ti)
Structural steel shapes
(100 Ibs)
Pig iron, No. 2 Foundry
tons)
Crushed stone (tons) 	
Sand (tons) 	 	 , 	
Common brick (1,000) _--
Concrete block (each) 	
Common brick (1,000)
Structural steel (100 Ibs)-
Structural steel shapes
(100 Ibs)
Pig iron, No. 2 Foundry
(tons)

Material
Quantity
1, 559. 05
2, 156. 31

I, 793. 42
2, 196. 15
46 30


192. 21
6. 88
507. 27


127. 69
747. 45
1, 952. 40

15, 392. 86
356. 87

3. 017. 14
267. 37
61.92
9, 883. 64
28.07
280. 28
3, 663. 50
84.94



Unit cost
$2. 10
1. 90

13.50
7. 10
205 00


10.34
138 60
7 10


138 60
3.751
2.94

6. 167
66.50

2 10
1 90
39.00
.22
39.00
10.34
6. 167
66.50



Item cost
$3, 274. 00
4, 096. 99
7, 370. 99
24, 211. 17
15, 592. 66
9, 491. 50

49, 295. 33
1, 987. 45
953. 57
3, 601. 62

6, 542. 64
17, 697. 83
2, 803. 68
5, 740. 06
26, 241. 57
94, 927. 77
23, 731. 86
118, 659. 63
6, 335. 99
508. 00
2, 415. 19
9, 259. 18
2, 174. 40
1, 094. 73
2, 898. 10
6, 167. 23
22, 592. 80
5, 648, 51
28, 241. 31

22

-------
Categories for a 1.0-MGD High Rate Trickling Filter
Mo., Aug. 1,  1962

Class/Trade
Equipment operators 	
Common labor 	


Carpenters - 	
Equipment operators 	
Ironworkers 	
Common labor 	


Ironworkers 	
Common labor 	


Ironworkers 	
Common labor 	 	 	

Iron workers 	
Common labor 	


Bricklayers 	
Common labor 	

Bricklayers 	 	 	 	
Carpenters - 	
Common labor 	


Electrical workers 	
Common labor 	




Labor
Man-hours
2, 040. 67
1, 159. 05


2, 727. 80
1, 054 57
1, 406. 57
7, 483. 16


662. 61
460. 43


2, 193. 20
1, 535. 52

1, 563. 30
2, 818. 63


314 46
1, 135. 84

697. 11
361. 03
735. 94


3, 108. 00
2, 512. 41





Unit cost
$3. 845
2.88


3. 875
3. 845
4. 025
2. 88


4.025
2.88

'
4025
2.88

4025
2.88


4325
2.88

4 325
3. 875
2.88


4 50
2.88





Item cost
$7, 846. 38
3, 338. 06

11, 184 44
10, 570. 22
4, 054 82
5, 661. 44
21, 551. 50

41, 837. 98
2, 667. 01
1, 326. 04

3, 993. 05
8, 827. 63
4, 416. 54

13, 244 17
6, 292. 28
8, 117. 65

14, 409. 93
1, 360. 04
3, 271. 22

4, 631. 26
3, 015. 00
1, 398. 99
2, 119. 51

6, 533. 50
13, 986. 00
7, 235. 74

21, 221. 74



Category
cost



$18,555.43





91, 133. 31



10, 535. 69



39, 485. 74


133, 069. 56



13, 890. 44



12, 700. 73



49, 463. 05
368 833 85

                                                    23

-------
 APPENDIX D
 Sewage  Treatment  Plant Process  Equipment—Manufac-
   turers'  Composite Experience Curve and Public Health
   Service Process  Equipment  Index  Curve  [1957—59rz
   100]
  1251-
  100
I
                                          PHS Index i
                                         Manul'i Cr.+ «
      ''*'
            I  I  I I  I  I i  •  i I  I  I I  I  I I  I  I I  I  I I  I  I I  I  I
   1930      1935      1940

  *No data available prior to 1947.
1945
Year
1950
1955
I960
                                                       25

-------
APPENDIX E
                           Total Plant and Category
                                       [Base period
Cities
Atlanta - .__ 	 _ 	
Baltimore. 	 -, 	
Birmingham _ 	
Boston 	
Chicago 	 . 	 .-_.
Cincinnati 	 T 	
Cleveland 	
Dallas _ 	 - 	 	 -
Denver 	 .-_.
Detroit _ 	 	
Kansas City __ 	 _ - 	
Los Angeles 	 	
Minneapolis 	 	
New Orleans 	
New York City - - 	 	
Philadelphia 	
Pittsburgh- __ 	
Sti Louis 	 	 	 	 	
San Francisco „,_.. 	 „-
Seattle 	 	

A
Excavation and
Fill
$38, 968. 84
44, 987. 34
38, 346. 71
46, 405. 67
47, 959. 21
44, 215. 51
48, 986. 24
38, 404. 74
33, 549. 13
48, 214. 81
38, 064. 57
44, 360. 65
43, 582. 71
35, 781. 02
45, 979. 51
45, 450. 78
46, 440. 61
44, 389. 23
41, 929. 21
48, 924. 66

B
Reinforced
Concrete
$102, 780. 01
106, 917. 38
99, 453. 02
115, 605. 53
112, 281. 77
110, 280. 43
118, 404. 79
96, 963. 79
101, 193. 47
115, 094. 40
107, 001. 00
107, 830. 16
113, 942. 45
98, 666. 13
131, 252. 81
113, 417. 21
113, 255. 40
111, 130. 01
113, 169. 69
111, 937. 89

C
Miscellaneous
Iron and Steel
$12, 279. 14
12, 864. 07
12, 088. 07
13, 222. 69
12, 381. 49
13, 083. 64
12, 309. 09
12, 430. 90
12, 902. 00
12, 605. 16
12, 359. 98
12, 426. 52
13, 145. 45
11,623.00
14, 074. 87
13, 001. 86
12, 128. 17
12, 704. 97
13, 947. 90
13, 290. 28

26

-------
Coats for 20 Index  Cities
=1957-59]
D
Pipes, Valves,
and Fittings
$39, 666. 30
41, 768. 17
37, 536. 12
45, 383. 76
46, 665. 89
41, 437. 68
44, 081. 30
38, 758. 30
40, 988. 08
46,008.11
41, 105. 66
45, 822. 95
48, 644. 77
39, 564. 92
48, 053. 44
46, 040. 45
45, 219. 28
42, 366. 08
45, 715. 20
46, 582. 22
E
Process
Equipment
Pumps and
Motors
$147, 551. 33
150, 111. 63
148, 125. 56
151, 738. 62
153, 025. 61
150, 980. 72
153, 034. 36
147, 754. 25
149, 278. 50
152, 870. 31
150, 132. 54
152, 130. 06
150, 786. 75
147, 840. 29
155, 340. 89
152, 377. 02
151,609.05
151, 559. 16
152, 116. 13
151, 738. 44
F
Sand and Bock
$15, 305. 22
19, 042. 68
17, 351. 12
16, 103. 60
18, 910. 08
19, 570. 56
24, 476. 48
15, 956. 77
14, 565. 64
19,989.20
15, 774. 13
18, 094. 30
23, 192. 07
14,034. 11
18, 160. 31
18, 481. 90
17, 325. 70
16, 154. 48
18, 002. 70
21,618.97
o
Buildings
$11, 181. 23
12, 204. 83
11, 246. 13
13, 452. 13
13, 719. 77
13, 116. 51
13, 917. 71
12, 438. 25
12, 452. 99
14, 225. 80
12, 762. 89
12, 572. 86
12, 833. 13
12, 692. 99
15, 652. 91
14, 024. 06
14, 084. 44
14, 132. 55
14, 287. 67
14, 260. 67
H
Otber Items
$50, 734. 54
52, 238. 85
50, 814. 61
54, 348. 44
56, 203. 55
54, 408. 80
56, 210. 82
50, 561. 91
52, 520. 43
56, 794. 93
53, 611. 04
56, 138. 26
54, 083. 41
50, 913. 94
59, 108. 81
56, 138. 83
56, 792. 89
56, 237. 34
56, 149. 54
55, 182. 43
T
Total Plant
$418, 466. 64
440, 134. 97
414, 961. 39
456, 260. 39
461, 147. 33
447, 090. 94
471, 420. 75
413, 268. 83
417, 450. 19
465, 802. 75
430, 811. 81
449, 375. 78
460, 210. 75
411,116.39
487, 623. 61
458, 932. 06
456, 855. 53
448, 673. 78
455,318. 11
463, 535. 61
    704-878 O—6ft-
                                                     27

-------
APPENDIX F
Cost Curves by Category for a 1.0-MGD High Rate Trickling
     Filter Plant, Kansas City, Mo., August 1930-62
                      [1957-59=100]
160
140
,-JSO
§.(00
eyt
J. 80

40
90

Excavation and Fill Material
I \
•
-
-
: :
: 	 	 ''.
'. ". 1, , , ,1 ,, , , ! , ,, J ,, ,, 1, ,,. 1 ,"
160
140
^,190
§100
4*%
^ 80
3«
40
90
-
-
" Reinferecd Concrete ~
: _, 	 •'"":
/*"
«*
: ,.-/ i
"•*
1 1 1 1 [ 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 i 1
   1930  (935  1940  I94S  1950  I95S  I960
               Yco
1930  1935  1940  1945  1950  1955  I960
            Year
160
(40
^.190
§100
Jl 80
40
90

-
.
Miicellancout Iron and Steel
-


-
•Ti-.-r4-T-i-r"HTrTl-!T7" i Ti i 1 i 1 i i i i 1 i
160
140

§100
J, 80
40
90

-
_
Pipet, Valve* and Fittingi
-
-
.„-—*""-
-,..„ 	 —..-'**
J i I 1 t I i c i 1 i i i i j | p | J 1 M I I 1 i 1 i 1 1 |
   1930  1935  1940  1945  1950  1955  (960
               Year
(930  1935  1940  1945  1950  1955  I960
            Year
28

-------
160
140
f'80
§100
*» 80
3-
40
M

19
160
140
2.100
w
•£ 80
40
SO
19-






"
Proccii Equipment, Pumpi and /
. Motor, /
; rx \
t
'- ,. /' :

*. . , , 1 , , . , 1 , . . . 1 . , , , 1 , , , • 1 , , , 1 1 l"
30 1935 1940 1945 1950 1955 I960
H
-
I Buildin, -
•TTivrfTwr+iTr 1935 1940 1945 1950 1955 I960
Y«ar
1
•
,'"'-
/ \
i ,,l, ,1 ili"
1955 I960
29

-------
APPENDIX  G
                  Municipal Waste Treatment Plant Cost
                                         [1957-59
Years
1030
1931
1932
1033
1034
1035
1036
1037
1038
1039
1040
1041
1042
1043
1044
1MB
1046
1047
1048
1040
1950
1951
1962
1953
1954
1955
1956
1957
1958
1950
I960
1961
1062
Atlanta
20.37
32.00
31.25
30.12
33.43
32.89
34.19
37.97
36.45
36.71
37.37
38.09
38.31
38.03
30.00
39.54
45.94
53.51
61.06
60.72
64.01
68.78
71.08
75.65
76.46
81.06
86.48
92.73
96.05
96.63
97.71
98.68
100.31
Balti-
more
34.02
33.60
32.53
33.08
35.17
35.28
35.74
30.12
37.95
38.08
38.69
30.72
40.55
41.09
41.20
41.03
47.10
54.45
63.60
65.46
60.41
73.67
76.48
80.77
82.02
84.61
80.30
06.62
100.08
102.46
103.20
103.67
105.19
Bir-
ming-
ham
32.37
28.32
27.33
28.57
30.12
30.72
32.31
35.51
33.64
33.80
34.44
35.27
38.30
38.32
38.32
30.02
43.87
61.16
59.02
60.37
63.37
67.82
71.10
75.07
76.31
80.31
85.08
90.68
93.76
95.82
98.08
97.25
06.86
Boston
34.33
31.45
31.42
30.74
33.79
34.72
34.58
38.37
37.16
37.65
38.54
40-15
41.99
41.86
42.68
42.46
46.69
55.02
66.27
67.80
71.22
76.02
78.47
81.43
84.10
89.09
04.76
100.41
103.36
105.84
106.88
107.86
108.27
Cblcago
37.26
34.78
32.81
35.03
36.75
36.78
37.08
39.60
39.96
40.81
40.75
41.04
42.21
42.32
42.31
43.56
47.26
57.48
66.38
67.39
70.39
75.79
78.06
83.32
86.59
80.54
05.02
102.10
104.60
107.39
107.61
108.94
109.41
Cincin-
nati
36.00
32.25
31.22
31.82
34.00
36.68
35.06
39.24
37.24
38.19
39.24
30.40
40.10
40.58
40.78
41.48
46.14
65.86
66.44
65.36
69.07
73.99
77.22
80.06
83.41
86.86
92.17
98.74
102.15
102.60
104.73
107.04
107.54
Cleve-
land
39.06
36.87
31.26
32.21
37.10
37.10
37.66
41.26
39.32
39.66
40.04
42.20
41.09
42.00
43.00
44.52
60.14
68.53
67.04
70.52
74.33
78.08
83.11
87.47
80.14
04.19
09.18
105.30
107.04
107.13
108.71
109.71
110.62
Dallas
35.24
35.09
30.24
32.18
33.72
32.19
33.03
35.33
35.45
35.80
36.66
37.30
40.79
40.76
41.37
42.04
46.54
53.05
62.69
63.87
66.15
71.28
72.61
75.11
76.74
79.66
84.63
01.11
03.64
95.74
06.64
96.39
07.23
Denver
37.51
34.69
31.31
31.47
35.30
35.32
36.24
40.23
39.03
30.06
39.44
30.69
39.69
41.80
41.46
41.75
46.52
65.61
63.65
63.49
67.68
71.02
73.68
77.43
78.63
82.33
86.15
91.32
94.10
98.13
09.43
99.43
101.16
Detroit
31.86
30.81
29.07
27.04
30.78
31.80
32.35
37.88
36.82
36.84
36.45
38.17
40.01
30.52
41.00
41.78
46.82
56.32
66.64
65.00
72.06
77.14
80.42
85.00
88.10
02.13
07.66
102.34
105.65
108.09
100.88
110.73
111.70
Kansas
City
32.45
34.78
30.35
29.61
33.53
34.70
35.82
38.62
38.24
35.27
38.47
38.66
30.82
41.31
41.84
41.78
46.39
52.66
62.20
63.33
68.25
72.24
76.06
79.16
81.24
85.93
00.08
94.54
97.70
100.43
101.72
102.77
103.49
30

-------
Indexes, 1930-62, August Values
=100]
Los
Angeles
80.88
31.41
27.08
29.80
85.69
34.86
33.08
37.28
38. 3«
36.91
36.01
36.46
40.00
40.19
40.10
40.42
48.60
64.26
64.87
6S.42
68.64
73.08
76.31
80.02
82.70
87.01
02.46
08.46
102.61
106.66
107.86
108.63
110.66
Mlnne
apolis
30.07
20.40
28.14
28.62
31.68
31,46
34.04
40.13
38.40
38.66
30.12
30.67
40.34
40.11
40.70
41.62
46.68
66.68
66.13
66.12
60.10
74.67
76.10
81.68
84.66
88.80
94.27
00.84
104.60
107.71
108.80
109.03
110. 10
New
Orleans
31.16
28.60
27.31
20.09
81.66
32.10
32.28
36.64
34.40
34.46
36.00
87.36
40.61
30.28
30.27
41.38
44.10
61.30
60.87
61.23
66.08
60.13
71.47
74. 71
76.00
79.89
86,17
00.16
93.43
06.20
06.00
07.41
08.88
New
York
41.30
38.18
86.71
36.72
37.20
36.81
36.24
41.00
30.68
30. 82
40.33
41.24
41.60
41.64
41.80
43.00
47.61
67.67
68.16
68.18
73.27
77.61
80.41
84.80
88.20
02.66
00.06
106.31
110.44
114.78
116.10
118.30
110.48
Phila-
del-
phia
33.03
31.96
28.46
29.27
34.29
36.84
36.26
30.76
38.17
30.06
40.73
41.30
43.16
48.22
44.33
46.40
40.00
69.03
66.63
67.82
71.04
77.62
70.80
84.62
86.47
01.44
06.18
100.30
106. 76
103.86
104.62
106.62
107.82
Pitts-
burgh
36.18
33.02
30.23
20.11
32.09
32.80
36.98
42.76
40.81
41.11
40.47
41.67
43.70
43.44
48.67
44.40
49.48
68.60
66.76
68.60
71.67
76.60
78.30
83.66
86.00
89.26
01.40
100.06
104.06
107,30
108.20
07.81
10.84
St.
Loots
36.66
37.04
32.66
32.61
36.78
33.86
34.81
30.91
38.12
38.16
30.66
40.61
41.86
42.24
42.38
43.63
40.24
67.22
66.00
66.61
60.06
74.40
77.80
81.40
83.16
04.17
02.02
07.03
102.07
104.02
106.64
106.28
08.20
Sao
Fran-
cisco
37.17
36.64
83.07
84.86
36.26
36.30
36.06
40.41
38.70
38.86
30.70
40.67
41.98
42.68
42.07
43.18
47.06
66.70
66.16
67.26
70.18
74.24
77.40
80.07
83.88
88.11
02.41
100.01
103.47
04.68
08.08
08.66
00.61
Seattl
81.02
31.47
27.87
27,71
33.33
83.36
33.62
40.07
38.40
38.40
38.67
30.60
41.20
42.60
42.60
46.12
48.20
66.64
66.60
67.80
70.70
76.67
78.62
80.60
84.33
87.67
04.12
100.88
106.67
107.86
00.20
11.63
12.40
Nation
al aver
ages
(1987-M
-100
34.43
83.12
30.48
30.98
34.12
34.10
34.84
30.00
37.77
37.02
38.67
30.41
40.02
41.23
41.67
42.40
47.17
66.61
64.76
66.61
69.32
73.92
76.76
80.77
82.80
87.23
91.87
98.04
101.60
103.66
104.06
06.83
06.90
Nation
a] are
age
(1930-
100)
100.00
06.18
88.61
80.06
00.08
09.28
101.17
113.26
100.68
110. 12
112.00
114.44
118.83
110.73
120.72
123.13
136.98
161.40
188.03
190.63
201.30
214.66
222.91
234.66
240.46
263.81
266.79
284.71
294.76
301.00
304.80
307.33
310.70
Year
1030
1031
1032
1033
1934
1038
1036
1037
1088
1030
1040
1041
1042
1043
1044
1046
1046
1047
1048
1049
1060
1061
1062
1063
1064
1066
1066
1067
1068
1960
1060
1061
062
                                                31

-------
APPENDIX  G—(Continued)

      Individual City Indexes  and National Index

City Index   H^^^^MHMB      National Index •• M •
  1930  1935  1940  1945
                Yea
                    1950  1955  I960
  1930  1935  1940  1945
                Ye,
                    1950 1955  I960
  1930  1935  1940  1945
                Year
IV 5

no

75
                    1950  1955  I960
1*
  IS
Cleveland
  1930  1935  1940  1945
                Year
 1*9


 100
       Denver

 751
  19
                    1950  1955  I960
  1930  1935  1940  1945   1950  1955   I960
                Year
                                               Dolrtmofc
                                          1930  1935  1940  1945  (950  1955  I960
                                                        Year

                                         185


                                         100
                                               Boom
                                         75
                                         19
                                                                 I .... I
                                          1930  1935  1940  1945  1950 1915  I960
                                                       Year
                                         125

                                         100

                                         75




                                         a
                                               Cincinnati
                                          (930  1935  1940  1945  1950 1955  I960
                                                       Year
                                         100

                                         75

                                        I.

                                         U
                                               Dollai
                                          1930  1935  1940  1945  1950 1955  I960
                                                       Year
                                          1930 1935  1940  1945  1950  1955  I960
                                                        Ytar
 32

-------
 100

C
       Kama* City
 1930   1995   1940   1945   1950  1955   I960
                     Year
ISS


!00


 75
Lot Angelci
    I I  I 1 ' '  ' * '  * * ' '  . I "  ' I i I  I I I  ' I I  ' J I I  I
 1930   1935   1940   1945   1950   1955   I960
                     Year
 1930   1935  1940   1945   1950   1955   I960
                     Year
                                                         IS5


                                                         100
                                                                 New Orleani
                                                           1930   1935  19
                            1950   1955
125


100
        r^cwYorlc
        . I..... I.
 1930   1935   1940   1945   1950  1955   1960
                     Yccr
,00


 75
                                                                 Phil
-------