PESTICIDE  RINSATE
RECYCLING FACILITIES
DESIGN GUIDE
POLLUTION PREVENTION PAYS PROGRAM
NORTH CAROLINA DEPARTMENT OF NATURAL RESOURCES AND COMMUNITY DEVELOPMENT

James G. Martin
Governor, North Carolina

S. Thomas Rhodes
Secretary, NRCD

-------
                                                  June  1988
             PESTICIDE RINSATE RECYCLING FACILITIES
                               by

                          Terry Ambroz
           Minnesota Agricultural Aircraft Association
                     Prior Lake,  MN  55372
                         Project Officer

                        James S. Bridges
Office of Environmental Engineering and Technology Demonstration
         Hazardous Waste Engineering Research Laboratory
                     Cincinnati,  OH  45268


                This study was  conducted through

                Minnesota Waste Management Board
                      St. Paul,  MN  55108

                             and the

             Minnesota Technical Assistance Program
                     University of Minnesota
                     Minneapolis,  MN  55455
                            REPRINTED
                          BY PERiVMSS.'CW
         HAZARDOUS WASTE ENGINEERING RESEARCH LABORATORY
               OFFICE OF RESEARCH AND DEVELOPMENT
              U.S. ENVIRONMENTAL PROTECTION AGENCY
                     CINCINNATI,  OH  45268

-------
This project was partially supported with a United States
Environmental Protection Agency cooperative agreement through the
Minnesota Waste Management Board and the Minnesota Technical
Assistance Program.


Although the research described in this report  has been funded in
part by the United States Environmental Protection Agency through
a cooperative agreement, it has not been subjected to Agency
review, and therefore does not necessarily reflect the views of
the Agency and no official endorsement should be inferred.

-------
         FINAL  REPORT

PESTICIDE  RINSATE  FACILITIES
         REVIEW DRAWING
        NOT TO BE USED FOR CONSTRUCTION
      DATE OF ISSUE      8-17-87
              AUGUST,  1987

   Prepared through the cooperation of the
   following agencies:

      - Minnesota Agricultural Aircraft Association
      -"Minnesota Plant Food & Chemicals Association
      - U.S. Environmental Protection Agency
      - Minnesota Technical Assistance Program
      - Minnesota Department of Agriculture
      - Minnesota Pollution Control Agency

-------
                         TABLE OP CONTENTS
      Section                                            Paqe
  I.   INTRODUCTION                                         1
 II.   DESIGN CRITERIA                                      2
III.   SYSTEM REQUIREMENTS                                  3
 IV.   ADDITIONAL CONSIDERATIONS                            4
      a.   Rain Water Discharge                             4
          1.  Permanent Roof                               4
          2.  Moveable Roof                                4
          3.  Rain Water Storage                           5
          4.  Rain Water Discharge                         6
      b.   Containment                                      7
      c.   Slab Size                                        7
      d.   Mixing Tanks                                     7
      e.   Water Service                                    8
      f.   Electrical Service                               8
      g.   Storage Tanks                                    8
      h.   Future Roof                                      8
      i.   Underground Storage                              8
      j.   Gravity Discharge                                8
      k.   Drainage                                         9
      1.   Sump                                             9
      m.   Employee Safety                                  9
  V.   OPERATION AND MAINTENANCE OF SYSTEM                  9
      a.   Training of Personnel                            9
      b.   Labelling of Tanks                              10
      c.   Lock Valves                                     10
      d.   Keep Records                                    10
      e.   Sediment Removal                                10
      f.   Minimize Water Use                              10
      g.   Minimize Storage Time                           11
      h.   Water Reuse                                     11
      i.   Proper Flushing of System                       11
      j.   Reuse of Rinsate                                11

-------
   TABLE OF CONTENTS  (Cont'd.)

       Section                                            Page

       k.  Disposal of Sediment in System                  12
       1.  Cracks                                          12
       m.  Drain System                                    12
  VI.  CONSTRUCTION ESTIMATES                              13
 VII.  EQUIPMENT AND OPERATION MODIFICATIONS               14
       a.  On-Site Cleaning                                14
       b.  Water Reduction                                 14
       c.  Tank Modifications                              15
       d.  Field Collection                                15
       e.  Nozzle Selection                                16
       f.  Safety Hazards                                  17
       g.  Discharge Path                                  17
VIII.  CONCLUSIONS                                         17

-------
                      FINAL  REPORT

              PESTICIDE  RINSATE FACILITIES
Abstract:  The problem of managing pesticide rinsate
materials is described and discussed.  A Report and
generic plan are presented for the design of a reuse
facility which is generally compatible with current
Minnesota operational and regulatory requirements. The
generic design incorporates recommendations for facility
size, construction materials, rinsate storage volumes,
reuse scheduling, and operation and maintenance proce-
dures.  With proper site-specific modifications, the
facility is considered to be adaptable to many facility
locations.

-------
                 PESTICIDE RINSATE FACILITIES
The disposal,  treatment or reuse of pesticide  rinsate  water
has been the subject of much research and on-going debate.
Pesticide  loading  and  mixing  facilities  are  located
throughout the state and vary  substantially from one location
to another.   Facility operators  recognize the  importance  of
proper rinsate handling and have requested assistance with
the design and construction of rinste handling facilities.

This  report  and  accompanying  plan  provides  general
information and design  considerations to assist in the
construction of  better and environmnetally safer  rinsate
handling  facilities.   The information included herein was
prepared  by  Bolton  &  Menk,   Inc.   for  the  Minnesota
Agricultural Aircraft  Association and Minnesota Plant Food
and Chemicals Association through the Minnesota Technical
Assistance Program  with a  grant from  the U.S.  Environmental
Protection Agency.

The primary goal and purpose of this project was to develop
and discuss a generic rinsate  facility  design to:

      - collect rinsate and wash water
      - minimize  site run-off
      - provide short-term  reuse of  rinsate and wash water
      - minimize  extraneous water run-on

Further,  the design has been  planned to be generally afford-
able and reasonably simple  to construct and maintain.   These
conditions are  necessary  to assure a  transition to improved
facilities by operators.

Numerous regulations and rules govern pesticide handling, use
and disposal.  As part  of  this project, several  meetings and
review sessions  were held  with  representatives of all of the
participating agencies.   The basic  purpose of this regulatory
review  was to  determine  the status  of rinsate facilities
relative to current regulations,  enforcement  procedures and
rule interpretations.

During this review, many  possible design alternates were
considered including contingencies for  dealing  with possible
long-term  site  contamination.   Based  upon  proper site
operation,  short-term   storage  periods  and  rinsate

-------
reuse/recycling,  the  resultant  design  and report has
generally  been accepted by the participating review  agencies
as a reasonable method  of  handling short-term rinsate and
wash water.

Operators  should  be  aware that failure to properly  maintain
and operate the rinsate facility, improper discharges, use
for long-term storage and other  activities may ultimately
categorize the facility as a hazardous  waste generator.  This
may subject the operator to expensive clean-up procedures,
long haul disposal and possible  fines.  Further, rules and
interpretations are subject to change.

It is the  intent of the design to  satisfy  the maximum number
of  regulatory rules and concerns and,  yet, maintain a
relatively simple and easy to operate system.   Other  designs
and options are available.  This project has  shown that no
design, including the selected generic design,  is without
some faults.  It is,  ultimately, up  to  the operator to insure
that its facility is  being operated in compliance with appli-
cable regulations and in accordance with appropriate site
requirements.
The facility  has  been designed to attempt  to  minimize  most
or all  of  the chemicals which are released from the facility.
The slab area has been designed of  concrete because it  is the
material which is most resistant  to chemical attack  of the
commonly available construction materials.

The potential for frost heaving and damage  to the concrete
surface is always present  in the Minnesota environment.  The
use  of drains  in  the  granular  base could reduce this
possibility, but the potential  for  chemical infiltration into
the under drain system  is felt  to be too much of  a risk to
take.   For  this reason,  no  underdrains are shown on the
drawings.

One of  the areas which was discussed during  the  preparation
of the plan and report was the need  for a plastic liner and
subdrain under  the gravel base  (leachate  collection  system)
in order  to  collect  any chemicals  which pass  through the
cracks in the concrete surface.  Such a system would  include
drainage pipes in the  gravel base to remove the leachate from
the gravel.  The construction  cost  for the leachate system is
estimated to range from  $2,000 to $3,000.  Collected leachate
may  require  special  handling and disposal, depending upon

-------
pesticide  concentrations,  quantities and migration.   At this
time, participating regulatory agencies are not requiring
rinsate  facilities in Minnesota to have leachate collection
systems.  However,  a leachate  collection  system may  be  a
requirement  on future installations if careful  attention  is
not  paid  to  sealing of  concrete  cracks  and  minimizing
intrusion of chemicals into the surrounding soil.  In light
of possible  future leachate requirements, operators  may wish
to consider  addition of leachate collection  piping and fabric
during initial  construction.

The facility has  been designed to  contain  large volumes of
rinsate material  or rainwater  which falls  on the slab area.
Curbs have been built into the concrete surface to facilitate
the storage.

The concrete slab thickness has been designed to attempt to
carry the average size vehicles which  are used in  these
applications  under normal  soil  conditions.  Unusual  loads or
unusual  soil  conditions  will  necessitate  the  use  of varying
concrete thicknesses.

The amount of  piping which is used in the system  has been
minimized.   Piping  and valves  appear  to  be an ever-present
problem  area and their use is  discouraged.  Frost heaving of
the shallow  pipe  system  may  cause the pipes to break and
chemicals to  be released.

Many other  designs and configurations  are possible depending
upon the use  of the facility.  Careful consideration should
be given to all details prior  to commencing  construction.
   *  SiSIEM REQUIREMENTS.

The need, configuration and size of a rinsate facility  will
be largely dependent upon the individual operation.  It is to
the operator's advantage to  attempt  to minimize the amount of
rinsate material which must be handled and reused.   Several
available articles stress the importance of first determining
the necessity of constructing a permanent rinsate facility.
A  rule  of thumb,  contained in the literature, is  that a
business which operates with less  than 300 equipment hours
per year will find that rinsing and disposing of the dilute
chemical over the application field is more  economical  than
constructing a permanent facility.

-------
IY.1.  ADDITIONAL CONSIDERATIONS^

After the decision has been  made  to construct a permanent
rinsate facility,  several other considerations should be
taken into account  in  the  planning stages.   Several of these
are addressed below:
         Rain HaJtej; Discharges

     One of  the most major decisions which must be made by
     the operator is how to handle  rain water which falls on
     the concrete slab.  Rain water will constitute a large
     volume  of water,  with a one inch rain on  the  aerial
     spray slab amounting  to over 2,500  gallons.  Thus it is
     important to develop a  plan for handling  this  water
     early in the planning stages.  Several options for the
     operator  were  discussed during the review  meetings
     between the involved  agencies.  These options are pre-
     sented  below:

         LJ.  Permanent Roof;

         The preferred method of dealing with rain water is
         to  direct it away before it  comes in  contact with
         the slab and possibly  becomes  contaiminated.   This
         is  best accomplished by providing a roof over the
         slab area.   Such  a roof could be of pole-shed type
         construction  spanning  over the  entire  slab.   A
         roofing  system will not be adaptable for  helicopter
         use.  Roofs for such  uses should be  designed to meet
         the minimum  loads required  by  the local building
         code for commercial applications.  Cost  of  a roofing
         system may range  from  $3,000 to $15,000, depending
         upon size and  construction.
         2... Moveab'le Roof L

         Another  method for directing rain water away from
         the slab would  involve placing a moveable  roof over
         the slab during periods when -the facility  is not in
         use.  The roofing system could range from a solid
         pole-shed type  on a  track system which  could be
         rolled  in and out of position  to  a  simple light-
         weight  frame which could be carried into position
         and a tarp placed over the framework.   Even a series
         of barrels placed under the tarp may suffice to
         direct water off of the tarp.

-------
Whatever  method of tarp  support is selected, the
tarp should not come into  contact with  the  concrete
slab during use -  this  contact with the slab will
contaminate the underside  of  the tarp.   The  rinsate
tank area may  not be adaptable to covering by this
method  since  the  tanks  will be in the way of tarp
placement.   Water  falling  on  this area will need to
be collected in the sump and pumped into a rinsate
tank or directly into the  application equipment.

Cost of  a moveable roof system could  range from $400
for a simple  tarp system to $8,000  or more for a
roll-away  roof.
    Bain SJaie.£ Storages

Storage of all rain water which falls on the slab is
another possibility for the operator.  This option
will be more  appeal ling to the ground applicators
since they are using larger volumes of water to mix
at lower  concentrations,  and thus need more mixing
water.   The  rain  water could be transferred  to
storage tanks by pumping or could  be left on the
slab, and  pumped  directly into application equipment
or mixing tanks as  it  is used.

The ground application slab is designed to contain a
3-1/2 inch rain on  the slab,  which amounts  to about
2,200 gallons.   As such the operator  must either
provide  sufficient  storage for  this volume  of water
or know that  his operation will make use  of this
much  water in  a short period of time.   If this
volume of  rinsate is used in the recommended propor-
tion of  5  percent rinsate to 95 percent clean water,
approximately 44,000  gallons of  mixing water will
result,  all from one 3-1/2 inch rainfall.   The cost
of providing  this additional  storage  during  the
initial  construction will be relatively cheap,  but
the operator must have a good plan for  disposing of
this extra water  without storing it for long periods
of time.

-------
    Bain Water
All of the previous methods  for  dealing with rain
water have either diverted the water away from the
slab before  it  comes  into contact with it or have
contained the contaminated water.   Another alterna-
tive is to discharge  the  rain water from the slab
area after it has fallen on the slab.  This is shown
graphically  on  the plan sheet by  the  pipes which
lead from the sump to  a  ground discharge.

This method  of disposal will  only be acceptable to
the Department  of Agriculture and  the  Pollution
Control  Agency   if the  operator  maintains  a very
clean site and avoids  any  release of chemicals from
the slab.  This will require that the rinsate slab
be rinsed off after each  day's use, or prior to an
impending rainfall.  The discharge pipe  must  lead to
an above-ground  discharge point and not  be connected
to a sewer or tile line.  The discharge point must
be an area which is seeded  or sodded  to grasses.
This will allow  a visual check of  the  discharge
characteristics and the effect of the discharge on
the vegetation.   The key to this arrangement  is that
no grass may be killed or  stressed  by the discharge
flow.   The  operator  will  need to effectively rinse
the pad/  as stated earlier, after  each use.

Another  possibility for avoiding  rain-slab  contact
is to install a  tarp  cover directly on top of the
slab.  Rain  could be  collected on top of the tarp
and removed by pumping or  by  siphon action prior to
use of the slab.

The drawback of this  option is that the bottom side
of the tarp will  be in contact with the  contaminated
slab,  and will thus also come into contact with the
trace of chemicals contained  on the  slab.  For this
reason,  when the tarp is  removed from the slab it
will need to be  pulled  completely off of the slab
with bottom  side up,  and then folded over so that
the contaminated sides are together and  the top does
not become contaminated.   Simply  rolling the tarp
will result in the bottom  to  top  contact which con-
taminates the top and makes  the  top vulnerable to
rain water carrying the  chemicals off of the  slab.

-------
    The important consideration as stated, is that no
    chemicals are released from the  slab.  No vegetation
    may be  killed adjacent  to the  site.   If  improper
    operational procedures  or dead vegetation  are
    noticed  by  inspectors at the  site,   a change  in
    design and operation will be required.  Discharge
    piping will probably be required to be completely
    plugged and complete containment or diversion of all
    rain water will become a necessity.
The concrete  slab of a rinsate  facility  provides an
excellent  spill  prevention site and has  containment
capacity  for  locating  bulk  chemical  containers  and
mixing tanks.  If bulk facilities are to be utilized,
locate them on or near to the rinsate slab and provide
containment around the bulk facilities as required by
state  law.

Bulk facilities  may necessitate  special permitting  and
secondary  containment requirements be  met.  These items
should be  carefully  considered  before utilizing  the
facility for such  use.
The size of the facility has been selected to fit the
average size  of  equipment in use.   It has  also  been
assumed that the ground equipment in use is capable of
having its  spray bars washed out  in the folded position.
If equipment size or operations vary, or if new equip-
ment is likely to change the operation in the  future, it
may be wise to change the pad size or shape to accomo-
date these  variations.
d.*.  nixing Tanks;

Consider siting  mixing tanks on the  rinsate  slab  or
directly adjacent to  contain  any  potential  spills
generated in  this operation.   The  plans show  areas
adjacent to  the  slab  which could  be used for  this
purpose. Other size  modifications of the slab may  be
advantageous to provide  this  additional use area.

-------
fij.  Water  Service;

If onsite water is needed, provide a water service of
adequate capacity to the mixing area with' an approved
air gap  to prevent back  contamination of  the  water
supply.
    Electrical Service;

If needed,  supply electrical power to the slab area to
run electrical pumps and power washers.
    Storae
Determine  the number of storage rinsate tanks which will
be required to meet the individual operational needs.
This number will depend upon the chemical  varieties
being used and the time of year of their application.
The Minnesota Department of Agriculture recommends that
one storage tank be installed for each crop  on which
pesticides are applied. Avoid any label violations by
mixing inappropriate chemicals.
    Future

Consider siting the pad in a area suitable for future
placement of a roof over the slab if a roof  is not built
immediately.  A roof will direct  rain water off of the
slab area,  and can serve as protection  for equipment
from long-term weather damage.
    Underground Storage;

Avoid  the  use  of  any  underground storage  tanks  or
vessels.   The  Environmental  Protection Agency  may
require that any underground facility include double
containment of the stored liquids, monitoring for any
leaks,  and  extensive testing around such vessels.
    Gravity Discharge;

If the elevation  of  the site allows,  consider  directing
the rinsate into the  storage  tanks  by gravity rather
than  pumping.   This  is  shown  on the detail  on the
ground-based plan sheet.   Containment around the  storage
                      8

-------
     tanks for this material will be required.   This method
     obviously has  advantages in that the liquid  does  not
     have to be pumped  twice.
     Ji*.  Drainage;

     Design  the  area around  the rinsate  pad so that  all
     drainage will run  away from the slab.  Never  slope an
     area to drain  onto  the  pad.
     The collection sump  could be a  pre-cast  unit,  made
     either  from precast  concrete  pipe sections  with  a
     precast  base, or  precast to the size and shape as drawn.
     Waterstops  should be installed at all joints.  Also,  a
     stainless steel tank could be used for this sump if it
     came equipped with a top flange to assure  a  good water-
     tight  connection to the slab concrete.  Check with local
     suppliers  for  availability.
     HU.  Employee Safety^

     Provide for employee safety  and sanitation needs  as
     required  by  pesticide  regulatory  requirements and OSHA.
     Showers and  eye  wash  facilities should be considered  as
     required  by  these agencies.
              AUQ MAINTENANCE Q£ SYSTEM
In order for the rinsate  facility to be effective and remain
in compliance with  all agency  laws/ proper maintenance  and
operational  techniques must be  adopted  by the  user.   The
following points are necessary  considerations  which  must be
addressed by the operator.

     a*.  Training of. Personnel;

     All employees who  will be  loading or cleaning equipment
     must be  familiar with the operation  of the  system.
     Special time should be set aside to adequately  prepare
     all personnel for  the  operation of the system to avoid
     any label violations or potential damage claims.

-------
b_».  Labelling  of  Tanks;

All tanks,  whether contai
rinsates, or mixing  tankSi
as to their contents.  If rinsate tanks are to contain
more than one chemical type, this should also be noted
rS M ^ V» f± 1 ^ V>^ 114 V* fm
                        Lning  bulk  pesticide,  pesticide
                        , should be adequately labelled
                „ .. „ w.  A F rin ca h » <• a n 1^ c a r o ^ n /-•« n +• a i n
... v*^ ........ >-.._ ,,..pni i r>a1 h
on the labelling.
G.J.  Lgck Valves:_

All valves on the system and on the storage tanks should
be capable  of being locked.  This will avoid  inadvertent
operation both  by  employees and  by vandals.
         Records;

A record should  be  kept of the approximate concentration
of chemicals in each storage  tank.   If a spill of con-
centrated chemical  should occur on the slab,  this  should
be carefully  accounted  for in  the  records,  and the
material adequately diluted  for further reuse.   Sampling
and testing  for  chemical concentrations may be  necessary
to establish safe  reuse  rates.
Sj.  Sediment Removals

Build-up and disposal  of dirt and sediment in the  system
will need  to be regularly addressed by the operator.
One way  of  substantially reducing  the amount of this
sediment is  to remove as much  of it as possible  in the
field before bringing the vehicle back to the rinsate
facility. This can be accomplished  by means of  physical
removal  of  the dirt or by use of water pressure.
!_,.  Minimize
Every attempt should be made to minimize  the  amount of
water which must be handled  in  the rinsate  facility.
Handling the rinsate material  will cost  money, and  any-
thing which can be  done to minimize  the volume handled
will save  the  operator  money.  Consideration  should be
given to use of a  pressurized power washing system for
cleaning of equipment,  rather than using water indis-
criminately from the water supply.  Also, the regulatory
agencies do not at this time require that water used for
washing  off  the exterior of application  equipment be
                      10

-------
collected in the cinsate facility  if  it does not result
in accumulation of chemicals  in  the  soil.  This  will
also minimize the amount  of  dirt and sediment which
enters the storage  tanks.   Do not  wash the equipment in
the same place  consistently to avoid the  build-up of
chemical contamination.
             Sioia.se.
An attempt  should be made  to reuse rinsate water  as
quickly  as  possible following  storage.   Long-term
storage  of  rinsate  may subject  the operator  to  the
requirements of  the  EPA  concerning hazardous waste gen-
eration.  Also,  quick  reuse may  help to  reduce  the
amount of sediment which settles out and  is  collected in
th e sy st em .
 ljL  Water
Rinsate water should never be stored when there is not
expected to  be a  time  when this  material  can  be reused.
Attention to future spraying jobs and schedules  will
help to minimize  this  problem.   Every attempt should be
made to rid the  system of rinsate prior to the end of
the spray season.   This is  especially true  when  cold
weather sets in.   All  rinsate must be removed from the
storage tanks, pump, hoses and sump and reused prior to
freezing temperatures to avoid frost damage to  these
apparatus.
L*.  Proper Flushing fif System;

After each use of  the  rinsate facility,  all  surfaces
which have come in contact with rinsate material must be
adequately washed.   This includes the collection slab,
sump, pump, hoses,  and cleaning equipment.
    Reuse af Rinsate;

The  rinsate  water  should be  reused with the same
chemical or a  compatible chemical application.  The rate
of reuse of  rinsate  recommended by  the Department of
Agriculture is 5  percent with  95  percent clean water (1
part  rinsate with  19 parts  clean water).  As  noted
earlier, this  reuse rate will result in large volumes of
make-up water if  rain water  is collected.
                     11

-------
    Qi£fi££3l fii Sedimgnt iD Systems
Over time,  sediment  and  deposits are sure to collect  in
the pumping sump and the storage tanks.  The regulatory
agencies have  a major concern about the disposal of this
material.   In  order  to be in strict compliance with all
hazardous waste laws, the material  should be analyzed to
determine its  chemical  constituents  and concentrations.
If  the  material contains higher concentrations than  is
allowed, it would be considered a hazardous  waste and
would need to be placed in  an acceptable vessel and
shipped  to a  suitable hazardous  waste  containment
facility.  As a consequence,  every attempt  should  be
made to  minimize the amount of  sediment which enters the
system.  This will include washing the exterior of the
application equipment off of the slab whenever  possible.
Consideration  should be  given  to agitation of the sedi-
ment material  at frequent time intervals and reapplica-
tion of  this solution as a  dilution material.   This may
cause problems  with some  application equipment, but
appears  to  be  the  most  reasonable  method of disposal  at
this time.

Another  possibility  appears to be land  spreading of this
material so as to minimize any high concentrations  in
any one  pi ace .
    Cracks t.

Contraction joints and random  cracks  which develop in
the concrete surface roust be sealed routinely to prevent
water  and  chemical  intrusion.   Also, control  joints
which are cut  into the concrete  surface during construc-
tion  must  be  cleaned and resealed about every  five
years, or as often as the material  seems  to pull  away
from the concrete.  The cracks should  first be  sawed or
routed to remove old sealing material and debris, and
then sealed with  a chemical resistant poured  sealing
material.   See the  plans  for  a  sealing  material
reference.  A detail  for sealing of cracks is included
at the rear of this report.
m*.  Drain Systems

Prior to cold weather all tanks, piping and pumps must
be drained  completely to  avoid frost damage  and the
rinsate reused.  The sump area should be  sealed to avoid
water entry into the sump and the outlet piping.
                     12

-------
  .•.   CONSTRUCTION
The estimated cost of constructing these cinsate systems has
been prepared.   Construction  costs will vary  substantially,
depending upon the cost  of local  materials and availability
of competent local contractors.  Also, many applicators will
elect to  do  a  large  portion  of  the work themselves,  which
will affect the projected costs.


                       GROUND  APPLICATOR
      Soil Testing                            $   1,500.00
      Site Engineering                           1,300.00
      Concrete:    25 C.Y. @ $55/C.Y.              1,375.00
                  Forming,  Reinforcing & Labor    1,800.00
      Excavation                                   230.00
      Gravel Base:  25 Tons @ $6/Ton                150.00
      Storage Tanks                              1,300.00
      Pump and Hose                                600.00
      Electrical Work                              400.00
                TOTAL                         5   8,655.00
                       AERIAL APPLICATOR
      Soil Testing                            $   1,500.00
      Site Engineering                           1,600.00
      Concrete:   70 C.Y. @ 555/C.Y.               4,345.00
                 Forming,  Reinforcing & Labor     5,800.00
      Excavation                                   900.00
      Gravel Base: 150 Tons @ $6/Ton               900.00
      Storage Tanks                                820.00
      Pump and Hose                                350.00
      Electrical Work                              300.00
                TOTAL                         $  16,515.00
In addition to the costs shown  on  the  above  estimates,  other
considerations could  affect the  final total  construction
cost.  These include:
                           13

-------
       If  the present electrical  or water services are  not in
       the vicinity of the facility,  the cost to run these
       services to an accessable  point.

       If  a connecting  road or access  point needs  to be
       constructed, the cost of this additional work.

       The cost for rainwater protection,  storage  or removal
       must be added  into  the above  estimates.   As stated
       earlier, this cost may be  as low as $100 for  rainfall
       which  is directed off the  site by a discharge  pipe, to
       as  high as $15,000 for a permanent roof.
   ju  EQUIPUEUT MQ OPERATION MODIFICATIONS.

Several potential  modifications to existing  equipment or
operations have been  identified during the course of this
investigation.  These modifications  could help  to reduce the
amount of  unused chemical  and the amount of rinsate material
which needs to be handled.

     S^. Qn-Site Cleaning;

     As pointed out  earlier,  a small applicator  using a
     minimum  amount of equipment may find the investment  in a
     permanent rinsate facility  to be prohibitive.  One of
     the options which is available instead of the use  of the
     fixed facility is to  rinse all tanks  and  spray bars in
     the field.  For ground applicators this can be accomo-
     dated by bringing  a  container of clean  water to the
     site. For aerial applicators and ground applicators,
     several  manufacturers have  systems available which can
     be mounted to supply a quantity of clean water on the
     aplication rig.   This  container  is  filled during the
     final application load, and is then used to rinse the
     tank  and spray bars over the field.  Rinsate concentra-
     tions should be considered  in calculating overall  appli-
     cation rates to  avoid excessive dosing or label viola-
     tions.
         Water Reduction;

     As mentioned earlier, every attempt should be made to
     reduce the  amount of water which needs to be collected
     in the rinsate  system.   The  use of  a  power washer or
     other means of increasing the pressure and decreasing
     the amount  of water used is recommended.
                          14

-------
         Modifications;
 The  amount of  mixed chemical left in the application
 equipment  should be  minimized  wherever  possible.
 Several  manufacturers  supply  a "goose neck" type of
 apparatus  to pick up as much remaining  chemical  in the
 dump box area of an aircraft as  possible.  The approxi-
 mately 1  to 5  gallons of dilute  chemical  that would
 otherwise  be wasted in  this area is then able to be
 used.   This device  is  shown  on  the  drawing  below.
 Perhaps similar modifications are possible for  ground
 based applicators  also.
    AIRCRAFT SPSAY  TANK
    AIRCRAFT SPRAY TANK
   Figure 1  - Unmodified
   chemical  pick-up.
Figure 2 - "Goose
neck" to pick up
greater amount of
mixed chemical.
          Collection;

Mobile applicators without a fixed base rinsate facility
may need to adapt a simple method to  collect  rinsate in
the field during cleaning  operations.   A very  simple
system is shown in the following sketch which  allows
collecting rinsate from washing of  the spray  bar.  This
system will work best if  the two spray bars are valved
independently and cleaned one at a time under  reduced
pressure.  The collected rinsate material will run into
a small container beneath the aircraft or truck.
                     15

-------
Disposal  of the collected rinsate  will be similar  to
that  for fixed  base operators.   The material can  be
pumped from the container beneath  the equipment  to a
storage tank on a vehicle.   If  a fixed  base rinsate
facility  is available,  the material can be hauled  to
this  facility and  transferred to other  storage  or  reuse
containers.  If this facility is not  available, the
material can be used in a mixing tank on the  mobile rig
at the  prescribed  reuse rate.

The exterior  of  the equipment  could be washed and the
water  not collected,  unless  the site is used  repeatedly
and a chemical build-up is possible.
                 Container— Pump from
                 Htr» to Storage           ^Partial Stcfjan of li"
                                       flattie

                                            Spray Monti
         Install indwdint Valves en Both
         Spray Ban so Out Sidt eon bo
         Gtmmd at t Time.
A suitable container could be  used  beneath  the  spray  or
dump tank to collect rinse water from the tank area.
g.j.  Nozzle Selection;

Spray  bars on all  equipment  should be  equipped with
"suck -back" nozzles  which will  close  completely when  the
equipment  is running and producing a vacuum.  This will
help to prevent any dripping from leaky nozzles.
                      16

-------
      *  Safety
     Applicators  should police  their facilities and  be  aware
     of potential hazards.  Particular care should  be  taken
     around outlets and valves from bulk storage  facilities,
     mixing tanks and rinsate  storage tanks.  A vandal  or  the
     collision  of a passing vehicle could easily  break  these
     connections  and  allow  the spillage of massive amounts of
     chemicals.   Simple  safety  precautions  beforehand  could
     easily avoid this  type  of problem.
         Discharge

     The operator  should note the drainage paths from all
     facilities.  Dikes  and  diversions which  can  either slow
     or eliminate the entry of spilled chemicals  into  storm
     sewer systems,  lakes or rivers may be cheap insurance to
     avoid future accidents, and  regulatory  action.
    i.  CONCLUSIONS.

Pesticide  rinsate handling and  reuse  has become a major
concern of regulatory  agencies  and environmental  groups.   In
order to stay in compliance with  the  laws governing  rinsate
generation and reuse,  the applicator must take  positive  steps
toward collecting and  disposing of this material.   The system
shown on these plans and discussed in this report  attempts  to
deal with these  issues in a  cost effective manner.

Because the field of pesticide handling is a relatively new
science,  changes  may  be  made  in the future  in the way
chemicals are handled  and applied, or rinsates  collected.

The applicator  should begin immediately to  plan  for  present
and  future needs  in  a  rinsate  facility and to dedicate
financial resources to the proposed improvements.   The future
view of regulatory agencies  toward pesticide applicators may
be  largely influenced  by  the ability  of the operators  to
control  all  their wastes  and make  a  dedicated effort  to
comply with all  regulations.
                           17

-------
 PAGE NOT
AVAILABLE
DIGITALLY

-------