EPA-600/2-76-114
May 1976
Environmental Protection Technology Series
                 TROUGH  CREEK LIMESTONE BARRIER
                        INSTALLATION  AND EVALUATION
                                    Industrial Environmental Research Laboratory
                                         Office of Research and Development
                                        U.S. Environmental Protection Agency
                                                 Cincinnati, Ohio 45268

-------
                RESEARCH REPORTING SERIES

Research reports of the Office of Research and Development, U.S. Environmental
Protection Agency, have  been grouped  into five series. These five  broad
categories were established to facilitate further development and application of
environmental technology. Elimination of traditional grouping was consciously
planned to foster technology transfer and a maximum interface in related  fields.
The five series are:
     1.    Environmental Health Effects Research
     2.    Environmental Protection Technology
     3.    Ecological Research
     4.    Environmental Monitoring
     5.    Socioeconomic Environmental Studies

This report  has been  assigned  to the ENVIRONMENTAL PROTECTION
TECHNOLOGY series. This series describes research performed to develop and
demonstrate  instrumentation, equipment, and methodology to repair or prevent
environmental degradation from point and non-point sources of pollution. This
work provides the new  or improved technology required for the control and
treatment of pollution sources to meet environmental quality standards.
This document is available to the public through the National Technical Informa-
tion Service, Springfield, Virginia 22161.

-------
                                       EPA-600/2-76-114
                                       May 1976
       TROUGH CREEK LIMESTONE BARRIER

         INSTALLATION AND EVALUATION
                     by
               S. Curtis Yocum
     Africa Engineering Associates, Inc.
       Huntingdon, Pennsylvania  16652
            Project No. 14010 FWW
               Project Officer

               John F. Martin
  Resource Extraction and Handling Division
Industrial Environmental Research Laboratory
           Cincinnati, Ohio  45268
    U.S. ENVIRONMENTAL PROTECTION AGENCY
     OFFICE OF RESEARCH AND DEVELOPMENT
INDUSTRIAL ENVIRONMENTAL RESEARCH LABORATORY
           CINCINNATI, OHIO  45268

-------
                              DISCLAIMER
     This report has been reviewed by the Industrial Environmental
Research Laboratory-Cincinnati, U.S. Environmental Protection Agency,
and approved for publication.  Approval does not signify that the
contents necessarily reflect the views and policies of the U.S. Environ-
mental Protection Agency, nor does mention of trade names or commercial
products constitute endorsement or recommendation for use.
                                  ii

-------
                               FOREWORD
     When energy and material resources are extracted, processed, converted,
and used, the pollutional impact on our environment and even on our
health often requires that new and increasingly more efficient pollution
control methods be used.  The Industrial Environmental Research Laboratory -
Cincinnati (IERL-CI) assists in developing and demonstrating new and
improved methodologies that will meet these needs both efficiently and
economically.

     The Trough Creek Limestone Barrier Installation and Evaluation
Project was undertaken to explore the feasibility of providing a low
cost treatment method for abatement of pollution caused by acid mine
drainage.  This report summarizes the findings of a study on the performance
of limestone barriers placed in a stream channel to effect neutralization
of acidity.  The work presented augments other types of mine drainage
treatment studies performed by the Extraction Technology Branch which
involve elaborate handling and pumping mechanisms.  Results obtained
here will especially benefit state and local agencies charged with
clean-up of acid streams.  The guidance presented in this report helps
to define areas where limestone barriers are feasible and to outline
their construction details.  Although the use of limestone barriers is
severly limited by stream quality and flow characteristics, the method
is an effective alternative given the correct conditions.
                                   David G. Stephan, Director
                                   Industrial Environmental Research Laboratory
                                   Cincinnati
                                      iii

-------
                                  ABSTRACT
Six prototype crushed limestone barrier installations were constructed
in Trough Creek in South Central Pennsylvania to demonstrate the neutral-
izing ability of this type structure in low-iron acidic streams.  The
project included a stream gaging and sampling program to evaluate the
effectiveness of limestone barrier performance under actual stream con-
ditions, and to assess the adequacy of design relationships developed
from laboratory research.

Limestone barrier performance was excellent during periods of low stream-
flow, in terms of reducing acidity and raising the pH of the water, but
their effectiveness was marginal at design or average streamflow, and they
were ineffective when high runoffs were experienced.  Limestone barrier
performance deteriorates after the structures are initially constructed
and placed in operation, because progressive accumulations of sediment
clog interstices between the stones, which lessens the hydraulic conduc-
tivity of the barriers, and surfaces of the stones become coated with
silt, which causes a reduction in reactivity of the reagent (limestone)
with flowing acidic water.  The design of limestone barriers should take
these factors into account, and the units should be sized sufficiently
large to overcome this deficiency.

Silted limestone barriers can be restored to porous filtering beds, ap-
proximately equal in performance to initial efficiency, by washing and
rehandling the crushed limestone materials.

This report was submitted in fulfillment of Project Number 14010 FWW by
the Commonwealth of Pennsylvania, Contract No. CR-105, and was prepared
by Africa Engineering Associates, Inc., of Huntingdon, Pennsylvania 16652
under the partial sponsorship of the Environmental Protection Agency.
The work was completed February 15, 1975.
                                    iv

-------
CONTENTS
Disclaimer




Foreword




Abstract




List of Figures




List of Tables




Acknowledgments




Sections




   I       Conclusions




   II      Recommendations




   III     Introduction




   IV      Limestone Barrier Design




   V       Construction of Limestone Barriers




   VI      Flood Damages - Reconditioning and Repairs




   VII     Stream Sampling and Limestone Analysis




   VIII    Limestone Barrier Performance




   IX      References




   X       Appendix




           Technical Report Data
                               vi




                               vii




                               viii








                               1



                               3




                               4




                              10




                              28




                              38




                              46




                              65



                              72




                              73

-------
                          FIGURES

No.                                                       Page

 1  Project Location                                        5
 2  Limestone Barrier Sites                                 8
 3  Limestone Barrier Construction Details - Site No.  1    22
 4  Limestone Barrier Construction Details - Site No.  2    23
 5  Limestone Barrier Construction Details - Site No.  3    24
 6  Limestone Barrier Construction Details - Site No.  4    25
 7  Limestone Barrier Construction Details - Site No.  5    26
 8  Limestone Barrier Construction Details - Site No.  6    27
 9  Completed Limestone Barriers - Site No. 1              30
10  Completed Limestone Barriers - Site No. 2              31
11  Completed Limestone Barriers - Site No. 3              32
12  Completed Limestone Barriers - Site No. 4              33
13  Completed Limestone Barriers - Site No. 5              34
14  Completed Limestone Barriers - Site No. 6              35
15  Flood Damages - Limestone Barriers - Site No. 2        39
16  Flood Damages - Limestone Barriers - Site No. 3        41
17  Flood Damages - Limestone Barriers - Site No. 4        42
18  Sampling Points and Gaging Station - Site No. 1        47
19  Sampling Points and Gaging Station - Site No. 2        48
20  Sampling Points and Gaging Station - Site No. 3        49
21  Sampling Points and Gaging Station - Site No. 4        50
22  Sampling Points and Gaging Station - Site No. 5        51
23  Sampling Points and Gaging Station - Site No. 6        52
24  Performance of Limestone Barriers - Site No. 1         59
25  Performance of Limestone Barriers - Site No. 2         60
26  Performance of Limestone Barriers - Site No. 3         61
27  Performance of Limestone Barriers - Site No. 4         62
28  Performance of Limestone Barriers - Site No. 5         63
29  Performance of Limestone Barriers - Site No. 6         64
                              vi

-------
                                TABLES

No.                                                             Page

 1      Site Locations - Trough Creek Limestone Barriers         11

 2      Design Flows - Trough Creek Limestone Barriers           15

 3      Design Acid Loadings - Trough Creek Limestone Barriers   16

 4      Valentine Limestone Analysis                             17

 5      Quantity of Limestone Provided - Trough Creek
                Limestone Barriers                               18

 6      Chemical Analysis of Crushed Limestone                   36

 7      Sieve Analysis of Crushed Limestone                      36

 8      Construction Cost - Trough Creek Limestone Barriers      37

 9      Reconditioning and Repair Costs
              Limestone Barrier Flood Damages                    45

10      Limestone Analysis - Basket No.  2                        55

11      Limestone Analysis - Basket No.  6                        55

12      Limestone Analysis - Basket No.  8                        56

13      Limestone Analysis - Basket No.  9                        56
                                 vii

-------
                            ACKNOWLEDGEMENTS

Sincere appreciation is expressed to Professor R. Rupert Kountz
(deceased), former professor of Sanitary Engineering and a Director of
the Institute for Research on Land and Water Resources at The Pennsyl-
vania State University, for technical support and guidance offered dur-
ing the planning phase of this project.

The cooperation and continuing support of the personnel of the Pennsyl-
vania Department of Environmental Resources (formerly the Department
of Mines and Mineral Industries) in implementing and administering the
work under this project is gratefully acknowledged.

Gratitude is expressed to Dr. A. J. McDonnell and Research Assistant
F. H. Pearson at the Institute for Research on Land and Water Resources,
The Pennsylvania State University, for cooperation extended during the
course of the project.

The support, guidance and assistance by the Environmental Protection
Agency project officers were greatly appreciated.
                                  viii

-------
                              SECTION  I

                              CONCLUSIONS
Research in the late 1960's at The Pennsylvania State University indica-
ted the feasibility of placing barriers of crushed limestone in streams
to effect reduction of acidity, and it was recommended that limestone
barrier neutralization should be demonstrated in selected prototypes.

Trough Creek, which is located in South Central Pennsylvania, was pollu-
ted with acid  mine drainage in the upper reaches of the watershed.
This stream was selected for prototype limestone barrier installations
at six sites in the watershed because iron and sulfate concentrations of
the water were low, except at one location where the iron concentrations
were in the neighborhood of 30 mg/1.

Alternate schemes for channelling stream flow, along with different
structural configurations and barrier shapes, were incorporated in the
design at the various installations so that an assesment could be made
under actual stream conditions of the most effective type limestone  bar-
rier for reducing the mineral acidity of the water.

During the course of the sampling and analysis portion of the Project,
severe flooding (Tropical Storm Agnes in 1972) was experienced in the
watershed causing damage to completed limestone barriers.  Selected  bar-
riers were reconditioned, repaired, and restored to approximate original
condition.

The sampling and analysis program was authorized to evaluate the per-
formance of the limestone barriers under actual stream conditions, and
to determine the adequacy of design relationships developed from labora-
tory research.  An evaluation of the performance of the Trough Creek
Limestone Barriers, based on results of the sampling program and obser-
vations noted in the field, indicates the following:

     1.  Neutralization of stream acidity can be accomplished by place-
         ment of limestone barriers in a stream channel.

     2.  Limestone barrier performance for the Trough Creek Project  did
         not meet theoretical efficiency.

     3.  Although barrier performance was excellent during periods of
         low stream flow, in terms of reducing acidity and raising the
         pH of the water, their effectiveness was marginal at average
         stream flow, and they were completely ineffective during per-
         iods of high runoffs.

-------
     4.  Limestone barrier performance was more efficient at installa-
         tions where the barriers were long, continuous structures and
         stream flow patterns were diverted by horizontal or vertical
         baffles than it was for the short, multiple unit installations
         set in series in the main channel.

     5.  Limestone barriers are most efficient when they are intially
         installed, or after they have been reconditioned.

     6.  There is a reduction in limestone reactivity that results in
         deterioration of barrier performance after the structures have
         been in service for some time following initial construction,
         and again after they have been reconditioned.

     7.  The rate of deterioration of limestone barrier performance is
         apparently due to two major factors:

              (a)  Siltation whereby sediment accumulations of
                   either silt or iron sludges clog interstices
                   of stones, and

              (b)  Coating of the surfaces of the stones with
                   silt or iron hydroxides.

In view of the deficiencies in performance of the limestone barriers on
the Trough Creek Project, it is questionable whether it is feasible to
attempt to provide in-stream limestone barriers exclusively as the treat-
ment method for area-wide mine drainage pollution abatement, even though
the chemical characteristics of the acid  waters appear suitable to
treatment with limestone.  Rather,  it is believed that construction of
limestone barriers in conjunction with other watershed improvements,
such as backfilling strip mined areas, replanting and possibly some mine
sealing, would be a more practical approach to regional mine drainage
pollution abatement, where the watershed areas and runoff characteristics
are similar to those of Trough Creek.

-------
                             SECTION  II

                           RECOMMENDATIONS
The process of in-stream neutralization of acid mine drainage by lime-
stone barriers should be limited to waters having very low iron con-
centrations.  For the Trough Creek Project, limestone reactivity was
apparently unaffected by armoring of the surfaces of the stones with
iron hydroxides where the iron concentration of the raw water was ap-
proximately 1 mg/1.  At one of the barrier installation sites the iron
concentration was approximately 30 mg/1, and accumulations of iron
sludges in the limestone bed caused almost complete deterioration of
barrier performance within a period of three months.  Additional re-
search could possibly establish the maximum permissible iron concentra-
tion for satisfactory limestone barrier treatment of acid mine drainage.

In the design of limestone barriers, acknowledgment must be made of the
fact that where watershed conditions are such that muddy and silt-laden
streamflows will be experienced, sediment accumulations will progres-
sively seal the limestone beds, and the surfaces of the stones will
become coated with silt.  These conditions will result in a reduction in
limestone reactivity and barrier performance will deteriorate below
theoretical efficiency.  The following recommendations are offered in
this regard:

     1.  The designer should size the units sufficiently large
         to overcome this deficiency.

     2.  A maintenance program should be established to period-
         ically recondition the barriers to restore them to
         approximate original condition so that barrier perfor-
         mance will not deteriorate below required efficiency.

-------
                             SECTION  III

                             INTRODUCTION
GENERAL

Acid mine drainage has long been a pollutant in coal mining areas with
the resultant elimination of most aquatic life in streams, together with
the attendant problems of prevention of natural bio-oxidation of organic
wastes, increased pollutional loadings in receiving waterways, and high
treatment costs when water is withdrawn for human use.  In the United
States the public has recognized the ruinous capacity of coal mine drain-
age, and laws have been enacted to force the coal industry to treat mine
drainage before discharge to natural watercourses.  However, there are
thousands of abandoned mines in the coal fields that continue to gener-
ate acid mine water that discharges directly, without any degree of
treatment, to small streams and tributaries.  In many of these waters
the acidity is less than 100 tng/1, and the iron content is low.

In the late 1960's the Pennsylvania Department of Mines and Mineral
Industries (now the Pennsylvania Department of Environmental Resources)
became very much interested in research conducted at The Pennsylvania
State University in the field of neutralization of acids by percolation
of synthetic iron-free acid  waters through beds of crushed limestone.
d'Laboratory results of these studies indicated that 100 mg/1 of
acidity could be significantly reduced by percolation of the water
through limestone barriers of short length.

Trough Creek, which is located in South Central Pennsylvania, was
selected for a prototype limestone barrier installation project, because
the acid waters in the upper reaches of this stream exhibited chemical
characteristics similar to the synthetic waters used in the laboratory
studies and appeared to be suitable for treatment with crushed limestone.
(For location - see Figure 1.)

A mine drainage pollution abatement program for Trough Creek had been
estimated by the Commonwealth of Pennsylvania to cost in excess of 1.2
million dollars, with average annual maintenance costs of approximately
one-hundred thousand dollars.  This program would have included deep
mine sealing, backfilling, channel improvement and treatment by lime
neutralization of the remaining pollution load.  Because of the low iron
and sulfate concentrations of the waters of Trough Creek, it was believed
that the possibility of reduction of the mineral acidity of the stream
with limestone should be pursued, and the Pennsylvania Department of
Mines and Mineral Industries engaged the Firm of Africa Engineering
Associates, Inc., of Huntingdon, Pennsylvania, to provide consulting

-------
                         PENNSYLVANIA
m
o
O
o
PROJECT AREA

-------
 engineering services  in connection with the investigation and  proposed
 project.   Based  on the aforementioned  research work performed  at  The
 Pennsylvania State University,  together with watershed  investigations
 conducted  by the Commonwealth of  Pennsylvania,  and  field  observations,
 the consultants  found it feasible to construct limestone  barrier  in-
 stallations at six locations  in the headwaters of the basin.

 The preliminary  engineering estimate of the cost of construction  of the
 Trough Creek Limestone Barrier  Installation Project was $172,000.  It
 was felt that if the  limestone  barriers were successful in reducing
 stream pollution from acid mine water  drainage in Trough  Creek, the
 process could be the  key to low-cost treatment of similar polluted
 streams in other parts of the Commonwealth  of Pennsylvania and  the
 Nation.

 PURPOSE AND SCOPE

 The purpose of this investigation and  study is  to evaluate the  effec-
 tiveness and performance of the Trough Creek prototype limestone  barrier
 installations.   The evaluations of the barriers developed herein  are
 based  on the results  of  stream  gaging  and sampling,  analyses of selec-
 ted limestone samples placed  in the barriers,  and field observations of
 the completed structures under  actual  stream conditions during  the study
 period.  The purpose  also is  to assess the  adequacy or inadequacy of
 the design based on the  degree  to which the barriers demonstrated their
 ability of reducing the  mineral acidity in  the  stream in  relation to
 performances expected from laboratory  research  studies.

 This report  includes  a background summary and discussion  of the engineer-
 ing design of the  limestone barriers,  including site selections, and
 comments regarding  construction.   During the course  of the construction
 phase  of the Project  the barriers experienced  severe flooding conditions
 in  June 1972  as  a  result  of Tropical Storm  Agnes, and additional work
 was  authorized by  the Commonwealth of  Pennsylvania  to repair and re-
 condition  some of  the barriers.   Included as supplementary information
 to  this report is  a tabulation  of construction  costs of the original
 project, together with unit costs  of reconditioning  and repairing lime-
 stone  barrier damages  occasioned  by the June 1972 flood.

 LOCATION AND  GENERAL  BACKGROUND INFORMATION

 The headwaters of Trough  Creek begin in Bedford, Fulton and Huntingdon
 Counties in  South Central Pennsylvania.  The area has had  extensive
 deep and surface bituminous mining operations in the Broad Top Coal
 Field.  The  surface mining contributed greatly  to the pollution loads
 from abandoned deep mines by diversion and  interception of surface
water.  The water quality problem in the stream is that of acid.  Gen-
 erally, the  iron concentrations are less than 1 mg/1, with corresponding

-------
 low concentrations  of  sulfate.  Manganese and aluminum  are not present
 except  for  minute quantities.   The  stream is devoid of  fish  life  in  the
 upper reaches  due to mine drainage.  Trough Creek  is  a  tributary  to  the
 Raystown  Branch  of  the Juniata  River, which is a sub-basin of the
 Susquehanna River.  Trough Creek  initially follows a  northeasterly and
 northwesterly  circuitous route.   At  its mouth, the stream bed is  Eleva-
 tion 670, U.S.G.S.  Datum.  The  total length of Trough Creek  is approxi-
 mately  48 kilometers  (30 miles),  and the watershed is mountainous with
 narrow  valleys flanked  with  steep hills with some widening of the basin
 in  the  vicinity  of  Little Trough  Creek.  The stream flows through shale
 and  sandstone  formations which  contain the previously mentioned bitumi-
 nous Broad  Top Coal Field.   The average stream profile  is 5.2 meters
 per  kilometer  (27.2 feet per mile).  The annual precipitation ranges
 between 89  and 114  centemeters  (35 and 45 inches).

 The  Project received its initial  impetus from the conservation sub-
 committee of the Huntingdon  County Planning Commission.  Finances for
 construction of  the Project  were  provided from the $500 million bond
 issue previously passed by the  Pennsylvania Legislature to support
 "Operation  Scarlift" in the  Commonwealth.

 CONSTRUCTION PHASE  AND  SAMPLING PROGRAM

 The  limestone  barriers were  constructed at six sites  in the upper area
 of the  Trough  Creek Watershed (see Location Map - Figure 2).  Construc-
 tion of the limestone barriers  was started at Site No. 1, the uppermost
 site in the watershed, on July  27, 1970 and progressed downstream.  All
 work under  the original contract was completed on November 26, 1971.
 Extra work, including placement of additional stone rip-rap along creek
 banks,  limestone media replacement, and heavy rock fills, was authorized
 after completion of the original contract, and this work was completed
 in May 1972.   In June 1972 severe flooding occurred throughout the
 watershed as a result of Tropical Storm Agnes, causing scouring of the
 crushed limestone materials, siltation, some erosion  at creek banks,
 and movement of some of the rock fills on the downstream faces of the
 barriers which were used to contain the crushed limestone.   At Site
 Nos. 1,  2 and 4 flood damages were repaired and the barriers restored to
 approximate original condition.   This work was started in September 1972
 and completed  in December 1972 as an extension of the original contract.

The stream gaging and sampling to evaluate the effectiveness of the
barriers began in October 1970 before any limestone had been placed, and
 continued through August 1974.  During that period, the limestone bar-
 riers were constructed and water samples were collected for analysis
 on a monthly basis.   The stream sampling program consisted  of collecting
water samples upstream and downstream from the barriers at  the various
 installations and recording rate of stream flow.   Selected  samples of
 limestone were placed in the barriers and periodically removed,  weighed

-------
FIGURE 2-LIMESTONE  BARRIER SITES

-------
and replaced to attempt to determine loss of weight of limestone, as a
function of time.

-------
                              SECTION  IV

                       LIMESTONE BARRIER DESIGN
GENERAL

The basis of design of the Trough Creek Limestone Barriers was the afore-
mentioned research data that was developed in the late 1960's at The
Pennsylvania State University, which formulated inter-relationships be-
tween acid concentrations, rate of neutralization, stone size, and
stream velocity.

In the design of the limestone barriers, consideration was given to the
possibility of siltation of the crushed limestone materials and scouring
during periods of high stream flow.  It was recognized that either of
these conditions could render the installations ineffectual in terms of
their ability to reduce the mineral acidity of the stream; however, it
was also noted at that time that the proposed project to be undertaken
was somewhat experimental in nature, and that the data to be derived
therefrom could provide valuable information in the design of future
installations of similar types, if the process proved practicable.

Generally, the limestone barrier structures are miniature porous dams,
set within the stream channel, and consist of cores of crushed lime-
stone contained by heavy rock fills on the upstream and downstream
faces.

WATERSHED INVESTIGATION AND SELECTION OF LIMESTONE BARRIER SITES

Prior to retaining the consultant for engineering design and prepara-
tion of drawings and contract documents for construction of the Trough
Creek Limestone Barriers, the Deparment of Mines and Mineral Industries
of the Commonwealth of Pennsylvania conducted an investigation of mine
drainage throughout the watershed in April and May 1968.  This investi-
gation included stream gaging and water sampling of the stream, tribu-
taries, and at sources of mine seepage.

The watershed investigation conducted by the Commonwealth of Pennsyl-
vania indicated that Trough Creek was considered to be alkaline from
Trough Creek State Park to its confluence with the Raystown Branch of
the Juniata River near Marklesburg, Pennsylvania, and that it was con-
sidered to be acid for approximately 22.5 kilometers (14 miles) in the
upper reaches.  The farthermost downstream point of discharge of acid
mine drainage to Trough Creek was found to be the overflow of an aban-
doned drift mine, hereinafter described as Limestone Barrier - Site
No. 5.
                                   10

-------
Except  for  the  overflow discharge from  the abandoned mine at Site No. 5,
results of  chemical analyses of water samples collected throughout the
acid mine discharge areas during the watershed investigation showed
that the pH range of the waters of Trough Creek and the Run leading from
Broad Top City  varied between approximately 3.2 and 5.4; acidity varied
between approximately 5 and 22 mg/1; sulfates varied between approxi-
mately  20 and 40 mg/1; and  (total) iron concentrations were generally
less than one mg/1.  The concentrations of pollution loads from the
overflow discharge at the abandoned mine at Site No. 5 were found to be
approximately 270 mg/1 of acidity and 30 mg/1 total iron.  However, the
rate of flow of the abandoned mine discharge was quite low in comparison
to the  flow in  Trough Creek.

On the  basis of the watershed investigation, field inspections, and con-
sultations  with the research personnel at The Pennsylvania State Univer-
sity, six (6) sites were selected in the upper area of the Trough Creek
watershed for limestone barrier installations.  These Sites are briefly
described in Table 1, and are shown on Figure 2.

      Table 1.  SITE LOCATIONS - TROUGH CREEK LIMESTONE BARRIERS

SITE NO.LOCATION AND DESCRIPTION


  1          Trough Creek - Approximately 183 meters (6001) upstream
             from Village of Woodvale at the spillway of an abandoned
             reservoir.

  2          Trough Creek - Robertsdale - 274 meters (900') more or less,
             upstream from bridge at Post Office.

  3          Trough Creek - 0.8 kilometers (0.5 mile)  more or less,
             north of Robertsdale at junction of Trough Creek and tribu-
             tary from Broad Top City.

  4          Trough Creek - 3 kilometers (2 miles)  more or less, north
             of Robertsdale at Village of Cooks at  junction of Trough
             Creek and small tributary.   Barrier to be located immediate-
             ly downstream from bridge on Route 994.

  5          Tributary draining to Luciana Bottoms, approximately 3 kilo-
             meters (2 miles)  south of Cassville.   Barrier to be located
             at drainage outlet of old Jacobs Mine.

  6          Trough Creek - Upstream from bridge where Trough Creek
             crosses L.R.   31094.

In selecting the limestone barrier sites,  priority  was given to accessi-
bility and close proximity to existing roadways for economical
                                   11

-------
construction and maintenance.  Also of primary concern in the selection
of barrier locations was topography in the areas adjacent to the proposed
sites.  Consideration was given to the possibilty of ponding of a few
feet additional depth of water upstream from the barriers, and it was
believed that minimum property damage would result from the stream ob-
structions at the sites selected.

ENGINEERING DESIGN - LIMESTONE BARRIERS

General guidelines for the design of the Trough Creek Limestone Barriers
were established as an outgrowth of preliminary conferences with Univer-
sity research personnel, Commonwealth of Pennsylvania Officials, and
the consultant, as follows:

     1.  Design flows through the barriers should be determined on
         the basis of approximately one-hundred twenty-five (125%)
         percent of the computed average stream flow.

     2.  Design acid loadings, in terms of pounds per day, at the
         various limestone barrier sites should be determined on
         the basis of approximately one-hundred twenty-five (125%)
         percent times computed loadings at average stream flow.

     3.  Crushed limestone should be furnished in sufficient quantities
         to provide for a theoretical 5-year limestone consumption or
         replacement program, based on the specified calcium carbonate
         content of limestone.

     4.  Although the use of graded limestone of the smaller sizes
         (2.5 cm or 1 inch in size) was recommended in the research
         studies because of the greater surface (contact) area and
         resultant higher neutralization rates, it was decided to use
         larger stone sizes (6.35 to 10.16 cm or 2 1/2 to 4 inches) in
         the barriers to be erected in the stream because the larger
         stones would provide greater stability and be less susceptible
         to washing and scouring during periods of high stream flow.  At
         Site No. 5, where the flow was known to be low and relatively
         constant, it was decided to use the smaller stone size.

     5.  The limestone barriers at Site No. 6, and to some extent the
         barriers at Site No. 4, should be erected to provide additional
         insurance if upstream installations failed or would not provide
         expected degree of treatment.

     6.  Limitations of the Pennsylvania Department of Forests and
         Waters (now Department of Environmental Resources) regarding
         encroachments and stream obstructions in the waters of the
         Commonwealth must be strictly adhered to.
                                   12

-------
      7.   Inasmuch as a follow-up water sampling and stream gaging
          program to evaluate the effectiveness of the limestone
          barrier installations was contemplated during the planning
          phase of the project, it was decided that measuring flumes
          of constant cross-section should be installed in the stream
          for the purpose of measuring stream flow by the velocity-
          area method.

 Detailed design of the Trough Creek Limestone Barriers was based  on in-
 ter-relationships of stone size,  rate of  flow,  barrier length,  superfi-
 cial velocity, retention time, and initial acidity.   The six working
 equations that were developed as  a result of the research in the  late
 1960?s at the Pennsylvania State  University are as follows:

          U = 0.353D  + 0.566Q  -  0.0292L   + 1.060

          T = 0.265DJ0-366 V°'477Lp 1>35

          K = 0.55Cr0-1V0-74D-0'84

          Cf = C.  (1-K)T

          H   = -0.580D  + 0.5840   + 0.0376L  +  1.521

          s = o.4i7rr°-931Q  °-921L -0-562
                    p     p       p
where,   U = average superficial velocity,  fps

        D = stone size,  inches
          P
         Q = flow  rate,  cfs/ft
          P
         L = barrier length,  feet
          P
         T = retention time,  seconds

        K = fractional acid  reduction, sec-1

        C^  initial  acidity, mg/1

        Cf= final acidity, mg/1

        H =  head water depth,  feet

        S = water surface slope

Hydraulic profiles, computed from the above relationships, were
                                  13

-------
Investigated under varying rates of flow through the barriers.  Where
necessary, the slopes of stream beds were altered to provide ample head
between the upstream and downstream limits so that the hydraulic gradient
at design  (average x 1.25) flow was uninterrupted through the barriers.

Determination of Design Flows

The Pennsylvania Department of Forests and Waters  (now the Pennsylvania
Department of Environmental Resources) maintained a stream gaging sta-
tion for the period 1930 to 1957 on Great Trough Creek at a highway
bridge, 0.8 kilometers (0.5 miles) upstream from the confluence of Great
Trough Creek and the Raystown Branch of the Juniata River,  Information
contained in the 1966 edition of the Pennsylvania Department of Forests
and Waters "Bulletin No. 1, Water Resources Bulletin, Pennsylvania
Streamflow Characteristics - Low Flow and Flow Duration" for the Great
Trough Creek Gaging Station was the basis for determining design stream
flows at the various limestone barrier sites.

Following is a tabulation of pertinent data relative to stream flow
characteristics at the Great Trough Creek Gaging Station:

         Drainage Area                  219.1 km2 (84.6 sq. mi.)
         Average Discharge (27 years)     2.7 m^/s (95.1 cfs)
         Max. Discharge (Mar. 17, 1936)    238 m3/s (8,400 cfs)
         Min. Discharge (3 occasions)       0.02 m3/s (0.6 cfs)

By interpolation from the Duration Table of Daily Flow in the Bulletin,
the average (27 year) discharge was exceeded 29.4 percent of the time.

Design (average x 1.25) flows for the limestone barriers were computed
by assuming uniform runoff conditions throughout the watershed, deter-
mining the contributary drainage area above each site by planimeter on
U.S.G.S.  Maps,  and by applying an average discharge rate of 1.232 x 10~2
m3/s per square kilometer (2.7 m3/s-f- 219.1 km2) or 1.124 cfs/sq. mile
(95.1 cfs -f 84.6 sq. mi.).   Design Flows are tabulated in Table 2.
                                    14

-------
        Table 2.   DESIGN FLOWS - TROUGH CREEK LIMESTONE BARRIERS

             (1)              C2)          (3)
           Drainage        Average       Design       Cumulative Design
        Area (Sq.  Mi.)     Flow (cfs)    Flow (cfs)          Flow (cfs)

  1          6.05             6.8          8.5                 8.5

  2          4.10             4.6          5.8                14.3

  3          3.45*           3.9*         4.9*              19.2*

  4          3.66             4.1          5.1                24.3

  6          7.06**          7.9**        9.9**             34.2**

NOTE:   To  convert square miles  to square kilometers,  multiply square
        miles x 2.59.  To convert cfs  to  m3/s,  multiply cfs  x  0.02832.

        (1)   Incremental contributory  drainage area upstream from each
             site
        (2)   Computed - 1.124  cfs/sq.  mi.
        (3)   1.25  x computed  average flow

        *Includes  Run from  Broad  Top City on which Limestone Barrier
        No.  3-C was erected.  The design flow for this  Barrier  was
        3.0  cfs,  and is included in the  cumulative (19.2 cfs) flow
        for  Barriers Nos.  3A and 3B.

      **Includes  watershed area  of 0.22  sq. mi. above  Site  No.  5,
        which drains to Trough Creek  between  Sites Nos. 4 and 6.
        Design Flow of 0.4 cfs used for  overflow at abandoned mine
        at Site No. 5.

Design Acid Loadings - Limestone Barriers

Acid loadings used for design at the various limestone barrier  sites
were determined from results of  analyses of the preliminary water
sampling and stream gaging investigations of the watershed.

The stream flows  that were recorded at the time of the watershed investi-
gation were slightly different than the computed design average flows;
however, the acid concentrations of water samples collected at  the pro-
posed limestone barrier sites were used to determine the design acid
loadings.  As previously mentioned, the design acid loadings were deter-
mined by increasing computed acid loadings by approximately 25 percent
at all sites, except that the barriers to be erected  at Site  Nos.  4 and
6 were to be furnished primarily to provide additional insurance if
                                    15

-------
upstream installations failed to yield expected degree of treatment.

Table 3 shows the design acid loadings at the various limestone barrier
sites.

   Table 3.  DESIGN ACID LOADINGS - TROUGH CREEK LIMESTONE BARRIERS
                                                           (3)
                  (1)                  (2)             5-Year Acid
Site        Computed Acid          Design Acid        Design Loading
No.       Loading (Ibs/day)      Loading (Ibs/day)      (Ibs. x 103)

 1              733                    900                  1,650
 2               42                     50                    100
 3A & 3B*       130                    165                    300
 3C**            68                     85                    150
 4               50                     50                    100
 5              584                    730                  1,330
 6               —                      ~                      —
Totals        1,607                  1,980                  3,630
                                                         (1,865 Tons)
                                                         (1,693 Metric
                                                              Tons)
NOTE:  To convert pounds (Ibs) to kilograms, multiply
       pounds x 0.4536.

  *Limestone Barriers in Trough Creek
 **Run from Broad Top City

(1) Incremental acid loading between each site
(2) 1.25 x computed load
(3) 5-year acid loading shown to nearest 50 x 103 pounds
Crushed Limestone

Since the Trough Creek Limestone Barrier Installation Project was a
prototype project undertaken as a result of research, it was deemed
necessary that the limestone materials to be furnished for the barriers
should not only be effective as a neutralizing agent, but also it was
believed desirable that the materials should be similar in chemical com-
position to those used in the research studies.  The crushed limestone
that was used for the University research work at State College, Pennsyl-
vania, was Valentine Limestone, and was obtained from the Appalachian
Stone Quarry (Division of Martin Marietta).  This quarry is located at
Pleasant Gap, Pennsylvania, approximately 14.5 kilometers (9 miles)
                                   16

-------
 northeast  of  the University;  however,  the  quarry  is  located approxi-
 mately 105 kilometers  (65 miles)  from  the  Trough  Creek Project area.  A
 typical analysis of Valentine Limestone was  furnished by  the  supplier
 and  is shown  in Table  4.

                Table  4,  VALENTINE LIMESTONE ANALYSIS

       Substance                              Percent by  Weight

         CaC03                                     96.800
         MgC03                                       1.630
                                                     0.800
                                                     0.500
         P                                            0.003
         S                                            0.035

 During preparation of  the Contract Specifications for construction of
 the  Trough Creek Limestone Barrier Installation Project an effort was
 made to locate  a suitable source  of limestone (high  in calcium carbon-
 ate) close to the Project area to minimize haulage and keep construction
 costs  as low  as possible.  However, it was found that limestones in
 active quarries in Central Pennsylvania near the Project  area were dolo-
 mitic  limestones, high in magnesium carbonate (approximately 30 to 40
 percent  by weight), and according to previous research studies, would
 probably not  be as effective  a neutralizing agent as the  limestones
 from the Appalachian Stone Quarry.  With the foreknowledge that con-
 struction  costs would be somewhat higher than originally  expected be-
 cause  of long hauls for delivery of materials, the Contract Specifica-
 tions  stipulated that the calcium carbonate content of the limestone
 to be  furnished for the barriers shall not be less than 95 percent by
weight.

As previously noted under the general guidelines for design of the
barriers,  it was decided that crushed limestone should be furnished in
 sufficient  quantities to provide for a theoretical 5-year replacement
based on the calcium carbonate content of the limestone;  and that the
barriers at Site No.  6, and to some extent the barriers at Site No. 4,
 should be  erected to provide additional insurance if upstream installa-
tions  failed or would not provide the expected degree of  treatment.
Also,  the  size  and shape of the barriers was governed by  site topography
and  limitations of the Commonwealth of Pennsylvania regarding stream
obstructions.   Table 5 shows a tabulation of the theoretical 5-year
quantity of limestone required at each site compared to the amount
actually provided.   The amounts provided,  as shown in the Table,  are
quantities computed from the detailed contract drawings.
                                  17

-------
Table  5.   QUANTITY OF LIMESTONE PROVIDED TROUGH CREEK LIMESTONE BARRIERS
                (1)                 (2)                      (3)
           5-year Acid      Limestone Required         Quantity of
 Site        Loading         5-year Replacement      Limestone Provided
 No.        (Ibs. x 1Q3)     	(c.f.)	(c.f.)	t

 1           1,650              19,470                  13,300
 2             100                1,180                    A,600
 3             450                5,310                    6,100
 4             100                1,180                  15,300
 5           1,330              15,700                  16,800
 6              -                 -                     29,000

 NOTE: To convert pounds (Ibs.) to kilograms, multiply pounds x 0.4536
      To convert cubic feet (c.f.) to m^, multiply c.f. x 0.02832

      (1)  Reference Table 3
      (2)  Computed quantity based on the following limestone properties:

                               96%  CaC03
                               Specific Gravity =2.7
                               53% Solids

      (3)  Determined from detailed Contract Drawings
Although the quantity of limestone furnished at Site No. 1 was less
than the theoretical 5-year computed quantity, it was believed to be
adequate because it did provide limestone for a calculated 3.4 year sup-
ply, and surplus materials were being furnished at other downstream
sites.

Gaging Flumes - Measurement of jtream Flow

Gaging flumes of constant cross-section were proposed at each site so
that during the sampling program the rate of flow could be measured
by the velocity-area method in the main channel and tributaries.   The
gaging flumes were proposed to be grouted stone rip-rap construction,
7.6 meters (25 feet) in length, and the slope of the invert to be 0.40
percent.  The cross-sections of the flumes at the various sites were
sized on the basis of the following design criteria.

     1.  Design (flood) flows to be computed from upstream
         contributary drainage areas and proportioned to the
         maximum discharge rate of 238 m^/s (8400 cfs) for the
         watershed having a drainage area of 219.1 square
                                   18

-------
         kilometers (84.6 sq. mi.) and which was recorded March 17,
         1936 at the Great Trough Creek Gaging Station.

     2.  Depth of water in the proposed flume channels to be
         approximately 0.3 meters (one foot) at computed average
         stream flow.

     3.  Use n = 0.015 in the Kutter formula for grouted stone
         masonry, and n = 0.013 for vitrified clay channel pipes.

All flumes were sized to accomodate design flood flows.  Wherever pos-
sible, the flumes were installed upstream from the barriers such that
the profile of the hydraulic gradient of stream flow through the flumes
would be unaffected by any water build-up on the upstream faces of the
barriers at design (average x 1.25) flow.  Where topography dictated
that flumes be installed downstream from the barriers, they were posi-
tioned low enough so that the profile of the hydraulic gradient of
stream flow through the barriers would be unaffected by flow through the
flumes at computed average streamflow.

Comments Regarding Design

The undertaking of construction of the prototype Trough Creek Limestone
Barriers for the purpose of neutralizing acid mine drainage by the pro-
cess of in-stream treatment with crushed limestone was the first such
endeavor for an entire watershed pollution abatement project where the
range of stream flow was of the magnitude of Trough Creek.  At the out-
set, it was recognized that there were a number of uncertainties associ-
ated with the project that suggested potential problem areas, such as
possible siltation, erosion, and scouring of the crushed limestone.
Furthermore, it was not known if a certain degree of armoring of the
surfaces of the limestone might occur where the materials remained un-
disturbed for long periods of time, even though the iron concentrations
were low.

In attempting to establish the general guidelines for engineering design
of the Trough Creek Limestone Barriers, acknowledgment was made of the
fact that normally stream sampling in connection with design is more
comprehensive in scope than that performed for this project at the pro-
posed barrier sites.  A more extensive preliminary water sampling pro-
gram at the proposed barrier sites may have altered somewhat the design
acid loadings and projected theoretical quantities of limestone required
for 5-year replacement.  However, in view of the nature of the uncertain-
ties previously noted,together with the lack of factual information
pertaining to limestone reactivity and barrier performance under actual
stream conditions, it was believed that the additional time that would
be involved in conducting a comprehensive water sampling program at each
site to determine more precisely the design acid  loadings was not
                                   19

-------
justified.  It was also believed that any deficiencies in design cri-
teria developed from laboratory research, together with possible detri-
mental physical aspects that would render the barriers ineffective, would
become manifest in the stream sampling, analysis and evaluation project
that would be conducted during and after construction of the limestone
barriers.

Barrier Configurations and Details

Topography in the areas adjacent to the proposed limestone barrier sites,
together with limitations set forth by the Commonwealth of Pennsylvania
regarding channel changes and stream obstructions, dictated to some
degree the configurations of the limestone barriers.  Also, it was felt
that different stream flow patterns and barrier shapes should be in-
corporated in the design of the Project to see which scheme proved to be
the most effective under actual stream conditions in reducing the mineral
acidity of the water.

In Pennsylvania it is necessary to obtain a permit from the Department
of Environmental Resources to construct any dam or other water obstruc-
tion, or in any manner to change or diminish the course, current or
cross-section of any stream having a drainage area of more than 1.3
square kilometers (one-half eq. mi.).  For the Trough Creek Project a
permit was required for each limestone barrier installation, except at
Site No. 5 where the drainage area above the site was 0.57 sq. km. (0.22
sq. mi.)-  General requirements for permit approval for the Trough Creek
Limestone Barriers included the following stipulations:

     1.  Existing stream channels shall be widened and the stream
         beds reshaped in the limestone fill areas.  The extended
         creek banks shall be lined with heavy rocks to top of
         bank on each side of the barriers to prevent erosion dur-
         ing periods of high water and scouring stream flow.

     2.  Limestone barriers shall be constructed to heights not
         exceeding 0.9 meters (3 ft.) above existing stream bed
         elevation.   In this connection, where it was necessary or
         desirable to provide limestone fills greater than 0.9
         meters in depth, existing stream beds were lowered such
         that elevation of the top of the barriers was not more
         than 0.9 meters above existing stream bed.

The proposed limestone barriers at Site No. 1 were located at the outlet
end of a shallow abandoned reservoir.  The design included horizontal
and vertical baffles to provide an extended contact period for the acid
water with the crushed limestone.

At Site Nos. 2 and 3 where the creek banks were well defined, two bar-
                                   20

-------
 riers at  each  site were proposed  in series in the main channel of
 Trough Creek,  and one barrier in  the Run from Broad Top City at Site
 No. 3.  The barriers at these sites were approximately 7.6 meters  (25
 ft.) in length and extended from  creek bank to creek bank in the stream
 channel.  Rock barriers, consisting of large stones placed in the main
 channel from creek bank to creek  bank, were provided upstream from the
 limestone barriers for the purpose of collecting floating debris during
 periods of low and average streamflow.

 At Sites  Nos.  4 and 6 where the creek banks were not well defined, the
 design included jetty-type structures to be erected alternately from
 each creek bank and extending into the main channel.  Additional crushed
 limestone, approximately 0.3 meters (one foot) in depth, was provided in
 the channel.   Horizontal concrete baffle walls and vitrified clay pipe
 cross drains were proposed to divert low or average streamflows such
 that a longer  contact time for neutralization would be afforded.   Stil-
 ling basins were provided upstream from the limestone barriers to settle
 out mud and sediment.

At Site No. 5, the overflow outlet of an abandoned mine, the proposed
barrier simply included clearing, excavation,  and completely filling
 the outlet area with crushed limestone to a computed depth such that
design flow would be below the surface of the limestone materials.

In March 1970 the Commonwealth of Pennsylvania authorized the advertise-
ment for bids for construction of the Trough Creek Limestone Barrier
Installation Project.  Details of the limestone barriers at the various
sites are shown on Figures 3 to 8 inclusive.
                                  21

-------
<.
                                             SECTION  THROUGH BASE  LINE
                                                                                        peoTEC-r is
                                                                                 11   ,-^6^^"^'
                                                                                 .//T
                  riMAL corsroues SHOWH INDICATE
                  LIMITS OF LIMESTONE FILL MID
                  FIHISHZD aeadifJG. see DETAIL HT
                  eiQHT foe EXCAVATION LIMITS
                  fT
                      PLAN-LIMESTONE
                    BAP&EBS A/2* IA  *  IB
                         to  to   o	eo

                                fffr

                                Figure 3.  Limestone  Barrier  Construction  Details—Site No. I
                                                                                                            LIMESTONE
B
•

-------
„
PZxW  - LIMESTONE
                                                                           2 A * ^ &
        SECTION     LIMESTONE  BABBIEP N? ^ 5
                                                              TRAUSVEPSE  SECTION
                                                             LIMESTONE
                           Figure  4.  Limestone Barrier  Construction Details—Site No. 2

-------
     -PLAN-
            3A ,36 4 3C ~
vrtff"-' -' „ ,f


    L/ME5TOME-
      STREAM  PROFILE.
SECT/ON  - LIMESTONE BA2ZIE2
              e > o  2
            SCAL£ /f/ffcr
Figure 5.  Limestone Barriers Construction Details—Site No.  3

-------
-
                                                                                                                -JZQCK FfLL-

                                                                                                                LA(D LOOSE

                                                                                                                W* ;5£7»«--
                                                                                                                S££ 3*£ETa
                                                                                                    LIMESTONE BflEZtEZ A/S 4C

                                                                                                          Jfit Ei. iSfO.O )
                                                                           <~m- o f at*w


                                                                        '•LIMESTONE
             P. I. NS. t


              X'» W
              £ - 33.^1



                  MS 4 A
                                                                            (oorroM £i.. isii.c.
                                         PLAN - LIMESTONE  BAPPIEP5  N^ 4A. 48  * 4C
                                                  m'-aaeei£.a UO.AA
                                                  T-aAjrei&es *sos *8f(^
                                                               \  FiLL*/tTH U*f£5TOM£ *f£&* 727    ^-
                                                              F3
- Ltfi1£3~TO*/£   Ftt± •
                                                                -JSOCK ffiL
                                                                we {.ease
                    eOCIC fJLL
                    LA Jo tocse.
                                   fa.
                            - BOTTOM El. l£ll.O
                                                         SECTION -  PROPOSED STREAM  CHANNEL
                                                                                  • t m
                                                                                   52
                                                                                   rtfffr
                                Figure  6.  Limestone  Barrier Construction Details — Site No.  4

-------
                                                                                        If*  °
'-
r
                                                       - PLAN -
                                          LIMESTONE  BARRIERS  N^ 5A t SB
                                               PROFILE - LIMESTONE  BhRglER N* SA
                                                                                        NOTE-
                                Figure  7.   Limestone  Barrier  Construction Details—Site No. 5

-------
                                                 -KIP - ^«» CfCfK
                                                / 6JWK LiHIHG
                                                 X-

                                                 \
            -  LIMESTONE  BARRIERS  A/^
                                           NOTE '•
                                                              EXIST G80UMO
 7- Htnerj «/ t* t
 ,ts'~ B*eatta tJo &m
     SECTION - PROPOSED STREAM CHANNEL
Figure 8.  Limestone  Barrier  Construction  Details—Site No. 6

-------
                              SECTION  V

                   CONSTRUCTION OF LIMESTONE BARRIERS
GENERAL

In June 1970 the Contract for "Construction of Limestone Barriers -
Trough Creek Watershed," Contract No. SL-121-1, was awarded by the
Commonwealth of Pennsylvania in the amount of $184,450.00.  The work
under the Contract consisted of construction of limestone barrier instal-
lations at six locations in the watershed and included site clearing,
stream channel widening and lowering existing stream beds, and the fur-
nishing and placing of stone rip-rap creek bank linings, grouted stone
rip-rap gaging flumes, concrete masonry, heavy rock fills, piping, and
crushed limestone.

The work was started on July 27, 1970 at Site No. 1, the uppermost site
in the watershed, and progressed downstream.  The sequence of construc-
tion of the barriers at the various sites is shown in SECTION VII,
STREAM SAMPLING AND LIMESTONE ANALYSIS, where a correlation is made of
the acidity of the waters of Trough Creek relative to installation of
the barriers.  Construction costs for the original contract plus cer-
tain extra work allowances are shown in Table 8 in this Section.  A
description of limestone barrier damages caused by flooding in 1972 are
presented in Section VI, together with measures that were adopted for
reconditioning and barrier repairs, and costs of correction.

Construetion Requ irements

All work on Contract No. SL-121-1 was performed on private property
where easement agreements had been previously acquired.  The contract
included the usual requirements regarding responsibilities in connection
with ingress and egress over the properties for the purpose of construc-
tion, clean-up, and disposal of waste materials.  Limestone barrier
installations were constructed, complete, in consecutive order beginning
at Site No. 1 and the work proceeded downstream to Site No. 6.  At each
limestone barrier site all work was completed and stream flow directed
through the barriers before the contractor moved his operations to suc-
ceeding downstream installations.  The contract specifications stipulated
that the sequence of such work at each site shall be performed in the
following order:

     1.   Site clearing, including access roadways, and the removal
         and disposal of trees, stumps, brush and general clearing
         preparatory to excavation.

     2.   Excavation, including removal and disposal of all materials

                                   28

-------
         necessary for lowering existing stream beds and relocating
         stream channels to the lines and subgrades shown on the con-
         tract drawings.  The Contractor was required to employ such
         protective measures as were necessary to prevent pollution of
         the stream with fuels, oils, sediment or other harmful materials.
         The Contract required that all excavations be completed before
         placement of rolled fills, stone rip-rap, rock fills,  concrete
         masonry and crushed limestone.

     3.  Placement of rolled earthen fills.

     4.  Placement of stone rip-rap on creek banks to prevent bank
         erosion.  The specifications required that at least 30 per-
         cent of the stones for rip-rap shall weigh not less than 90.7
         kilograms (200 pounds) and at least 20 percent shall weigh mpre
         than 9.1 kilograms (20 pounds).

     5.  Placement of concrete masonry for cut-offs and baffle walls.

     6.  Placement of rock fills at the proposed upstream and downstream
         faces of the barriers, and at other locations used to confine
         and prevent washing of the crushed limestone.  The specifica-
         tions required that at least 60 percent of the stones for rock
         fills shall weigh not less than 90.7 kilograms (200 pounds) and
         at least 90 percent of the stones shall weigh more than 9.1
         kilograms (20 pounds).

     7.  Placement of crushed limestone in the barriers was the last
         step in the sequence of construction at each site.  The speci-
         fications required that the limestone materials be stored on
         hard and clean elevated surfaces, sloped to the outer edges
         to insure proper drainage and to prevent possible accumulations
         of mud and silt on the stone surfaces during storage.   The
         contract also required that the crushed limestone be placed in
         the stream as nearly as practicable in its final position.
         Bulldozing of limestone materials into place, or the traveling
         over previously placed materials with heavy equipment was pro-
         hibited.  Placement of the crushed limestone on prepared stream
         bed surfaces was started at the furthermost point upstream and
         proceeded downstream.  Table 6 shows a chemical analysis of
         the limestone materials furnished for the Trough Creek Project,
         and Table 7 shows the sieve analysis of the materials.

Illustrations of the finished limestone barriers, as they appeared shortly
after construction was completed, are shown in Figures 9 to 14 inclusive.
                                    29

-------


FIGURE 9 - COMPLETED LIMESTONE BARRIERS - SITE No.  1

-------
FIGURE 10 - COMPLETED LIMESTONE BARRIERS - SITE No. 2

-------
FIGURE 11 - COMPLETED LIMESTONE BARRIERS - SITE No. 3

-------
u
—
                              FIGURE 12 - COMPLETED LIMESTONE BARRIERS - SITE No. ~k

-------
-


                              FIGURE 13 - COMPLETED LIMESTONE BARRIERS - SITE No.  5

-------
UJ
Ul
                                                                 .   **

                                                        '
                                                        £

                               FIGURE 14 - COMPLETED LIMESTONE BARRIERS - SITE No. 6

-------
           Table 6.  CHEMICAL ANALYSIS OP CRUSHED LIMESTONE

           Chemical Substance            Percent by Weight

             Iron                              0.10
             Calcium Oxide                    55.50
             Magnesium Oxide                   0.70
             Loss on Ignition                 42.15
             Other                             1.55

           Calculated from CaO plus MgO

             Calcium Carbonate                99.06
             Magnesium Carbonate               1.46


             Table 7.  SIEVE ANALYSIS OF CRUSHED LIMESTONE

               Screen Size              Percent Passing

                10.16 cm (4")                 100

                 6.35 cm (2 1/2")              34
Construction Costs

On November 28, 1971 all work under the original contract was completed,
and the total value of this work was $184,338.60.  In February 1972
extra work was authorized at Site Nos. 1, 4, 5 and 6.  The extra work
included replacement of approximately 15.3 cu. meters of crushed lime-
stone at Site No. 1, placement of some additional- stone rip-rap on creek
banks at Site Nos. 4 and 6 to help prevent bank erosion, and placement
of heavy rocks and a 60.96 cm (24-inch) grout-filled corrugated metal
pipe (placed approximately perpendicular to channel flow and sloped away
from the creek bank) to act as a deflector and to help prevent scouring
of the crushed limestone in the channel of Limestone Barrier No. 1-B at
Site No. 1.   The authorized extra work also included scarifying and re-
distributing the crushed limestone in the barrier at Site No. 5, where
accumulated iron sludges had clogged the voids in the limestone materials
and neutralization of the acid was not being effectuated.  The total
value of the extra work was $6,784.00; it was started in April 1972 and
completed in May 1972.

Construction costs for the original project, together with costs for the
extra work authorized in February 1972, are shown in Table 8, and in-
clude a breakdown of quantities of work and materials at the various
sites.
                                   36

-------
                                       Table 8. CONSTRUCTION  COST - TROUGH CREEK LIMESTONE BARRIERS
Contract Iten - Description Unit
Site Clearing (Lump Sum)
Excavation and Disposal C.T.
Rolled Embankment C.T.
Rip Rap Creek Bank Linings S.T.
Grouted Stone Rip-Rap S.T.
Concrete Masonry C.T.
Rock Klls C.T.
12-Inch V.C. Channel Pipe L.F.
18-Inch V.C. Channel Pipe L.F.
2l*-Inch V.C. Pipe L.F.
30-Inch V.C. Pipe L.F.
2U-Inch C.H. Pipe L.F.
Crushed Lines tone C.T.
Quantities - Trough Creek Limestone Barrier Site No.
1

116
80
170
82
10.5
175
-
-
25
-
120
531
2

1,082

171
137
1*
269
-
-
-
-
-
188
3

832
100
36
1ft
7
220
-
-
25
-
-
33U
U

2.U10
U7
ma
169
33
332
-
25
-
138
-
539
5

U56
-
-
1*3
It
15
25
-
-
-
-
688*
6

U.U10
882
U19
203
65
50
-
-
-
276
-
1,076
Total Unit
Quantity Price Amount
$15,000.00 $ 15,000.00
9,306 2.UO 22.33U.UO
1,109 1.60 1,996.20
9l»U 12.00 11,328.00
798 18.00 U*,36U.OO
153.5 80.00 12,280.00
1,577 12.00 18,92ii.OO
25 20.00 500.00
25 2U.OO 600.00
50 30.00 1,500.00
Ullt 18.00 7,152.00
120 30.00 3,600.00
3,356 2U.OO 8o,51*U.oo
*  Prior to conpletion of the work the Contractor was authorized to scarify and redistribute
   th« lisestoae materials at Slt« No. 5, as iron sludge began to accumulate, for a lump son
   price of $700.00, bringing the total cost of vork under the original contract  to $191,122.631
                                                                                                          Total Value of Work
$190,1*22.60

-------
                             SECTION  VI

              FLOOD DAMAGES - RECONDITIONING AND REPAIRS
GENERAL

In March 1972 heavy rainfall, accompanied by warm weather that melted
deep snow in the Trough Creek Watershed, caused flooding at the lime-
stone barrier sites.  Local residents reported these flooding condi-
tions to be the worst in many years in some areas.  The spring flooding
and high stream runoffs in March 1972 caused silting of the crushed
limestone at Site Nos. 3, 4 and 6, and creek bank erosion was noted at
Site Nos. 1, 3 and 6.  Some scouring of the crushed limeston and dis-
placement of rock fills occurred at Site Nos. 1, 2 and 3.

In late June 1972 severe flooding occurred throughout the watershed as
a result of Tropical Storm Agnes.  The extent of damages to the lime-
stone barriers following the June flood was greater than that experi-
enced in March, and included considerable silting of the crushed lime-
stone beds, displacement of heavy rock fills at certain locations, creek
bank erosion, and some scouring of the crushed limestone.

Presented below is a description of the effects of flooding at the
various limestone barrier sites,

     Site No. 1.  High waters overflowed the horizontal concrete baffle
     in Barrier No. 1-B.  Silting was noted at the lower end of the
     barrier, and some crushed limestone materials were scoured and de-
     posited in the grouted stone rip-rap flume.  Creek bank erosion
     occurred downstream from the flume.

     Site No. 2.  At Barrier No. 2-B the March 1972 flood caused debris
     build-up on the upstream side of barrier, some silting, but very
     little scouring of the limestone materials.  At Barrier 2-A a few
     large stones were displaced on the downstream face of the barrier,
     and minor silting and some scouring of the limestone materials were
     noted following the March flood.

     Damage resulting from the June flood at Site No. 2 included some
     movement of heavy rock fills, and the scouring and washing down-
     stream of approximtely three-quarters of the limestone materials
     in Barrier No. 2-A, and approximately one-half of the limestone
     materials in Barrier No, 2-B.  Also, considerable deposits of mud
     and gravel were noted immediately upstream from Barrier No. 2-B
     and the Rock Barrier.  (See Figure 15)
                                   38

-------
_
~
                            FIGURE 15 - FLOOD DAMAGES - LIMESTONE BARRIERS - SITE No. 2

-------
Site No. 3.  The most extensive flood damage was experienced at
this site, where the slope of the stream bed is steeper than at
any of the other limestone barrier sites.

The March flood damages included displacement of a few large stones
in the rock fills on the downstream faces of Barrier Nos. 3-A and
3-B, which are located in the main channel of Trough Creek.  As
a result, some scouring and washing downstream of the crushed lime-
stone material occurred.  Also, there was evidence of minor silta-
tion of the limestone materials, and creek bank erosion was noted
downstream from Barrier No. 3-A.

The magnitude of the June flood damages at Site No. 3 was greater
than that experienced in March.  At Limestone Barrier No. 3-A,
nearly all the limestone materials were scoured and washed down-
stream, and approximately one-half of the heavy rock fills were
displaced.  Approximately three-quarters of Limestone Barrier No.
3-B was washed away, including the limestone materials and rock
fills.   The limestone materials in the approximate upper two-thirds
of Limestone Barrier No. 3-C were scoured and washed downstream.
(See Figure 16)

Site No. 4.  The most serious effect of flooding at this site was
siltation.  The effects of both the March and June floods were
similar, except that siltation following the June flood was more
pronounced.  Large quantities of mud and silt were deposited in the
stilling basin upstream from the barriers, and also in the main
channel downstream from the barriers.  Silt deposits on the bar-
riers and in the limestone filled channel area choked voids and
prevented filtering action through the crushed limestone mater-
ials.  (See Figure 17)

Site No. 5.  There was no apparent damage to the barrier at this
site from surface runoffs.

Site No. 6.  Flood waters at this site caused silting of the bar-
riers,  stilling basin and stream channel similar to the conditions
noted at Site No. 4, with the resultant clogging of voids in the
crushed limestone materials.  Approximately one-half of the lime-
stone materials in Barrier No. 6-B were washed downstream during
the June flood.  There was no apparent scouring of the limestone
materials during the March flood.
                                40

-------
FIGURE 16 - FLOOD DAMAGES - LIMESTONE BARRIERS - SITE No,  3

-------
FIGURE 17 - FLOOD DAMAGES - LIMESTONE BARRIERS - SITE No. 4

-------
Reconditioning and Repairs - Limestone Barriers

When flood waters receded in the Trough Creek Watershed following the
June 1972 flood, an assessment of damages was made at each site to de-
termine costs involved in restoring the limestone barriers to approxi-
mately original condition.  The total estimated cost of construction
for restoring the barriers at Site Nos. 1, 2, 3, 4 and 6 was $68,080.

In August 1972 the Commonwealth of Pennsylvania approved extra work
expenditures under Contract No. SL-121-1 for restoring the limestone
barriers at Site Nos. 1, 2 and 4.  No additional work was authorized
at Site Nos. 3 and 6.  The restoration work at Site Nos. 1, 2 and 4
included excavation and disposal of mud and silt deposits, furnishing'
and placing rock fills on the downstream faces of barriers at Site No. 2
and in the channel at Site No. 4, furnishing and placing additional rip-
rap creek bank linings at all three sites, rehandling and washing the
crushed limestone materials remaining in the barriers to remove silt
and restore the barriers to porous filtering beds, furnishing and placing
new crushed limestone to replace materials washed away during the floods,
and seeding ground surfaces adjacent to the barriers to help prevent
soil erosion and washing.  All work in connection with reconditioning
and repairs of the limestone barriers was performed during periods of
low stream flow.

The restoration work was started in late September 1972 and completed
in early December 1972.   A breakdown of quantities of work and materials
at the various sites,  together with unit costs for such work are shown
in Table 9.

The procedures adopted for rehandling and washing the crushed limestone
at each site were as follows:

      1.   Channels or  drainage ways were excavated through the barriers
          parallel to  streamflow between the downstream and upstream
          limits.

      2.   The silted limestone materials were excavated and stockpiled
          on each side of the  drainage channels.   Equipment used for
          this work was  a combination dozer with a small backhoe and
          front-end loader.

      3.   The stockpiled silted limestone materials were rehandled,
          cleaned  and  washed with water under pressure,  and replaced in
          final position in the barriers.   A portable pumping unit that
          took suction from the stream was used  for washing.   This unit
          was a centrifugal pump with 3-inch suction and 3-inch discharge
          pipe connections,  driven by a 12-horsepower gasoline engine,
          and delivered  approximately 100 gallons per minute at a
                                   43

-------
         corresponding total dynamic head of 100 feet.  The end of
         the 3-inch discharge hose was equipped with a 1 1/2 inch steel
         pipe nozzle.

     4.  New crushed limestone was furnished and placed in the barriers
         to finished lines and grades to replace materials washed away
         during the floods.

Washing, and the placement of the crushed limestone materials in final
position, was started at the upstream extremities of the barriers at
each site and the operations progressed downstream so that sediment from
washings would not clog or coat the surfaces of previously cleaned
materials.

The reconditioning and repair work that was undertaken at Site Nos. 1,
2 and 4 after the June 1972 flood was successful in restoring these
limestone barriers to porous filter bed structures, approximately equal
in condition to that which existed when they were initially installed.
The washing and rehandling operations thoroughly cleaned the crushed
limestone rock surfaces that had become coated with clay-like materials
and slimes, thus restoring the neutralizing ability of the carbonate
rocks.
                                   44

-------
  Table 9.  RECONDITIONING AND REPAIR COSTS - LIMESTONE BARRIER FLOOD DAMAGES
Description
Excavation
Rip-Rap Creek
Bank Lining
Rock Fills
New Crushed
Limestone
Rehandle and Wash
Existing Crushed
Limestone
Seed Ground
Surfaces
Unit
Cu. Yd.
Sq. Yds.
Cu. Yds.
Cu. Yds.
Cu. Yds.
Acre
Quantities - Site No.
1
20
25
8
103
100
0.23
2
455
290
95
120
50

4
515
130
115
250
250
0.25
Total Quantity
990
445
218
473
400
0.48
Unit Price
$ 2.40
12.00
12.00
24.00
8.40*
2,000.00
Amount
$ 2,376.00
5,340.00
2,616.00
11,352.00
3,360.00
960.00
                                              Total
$ 26,004.00
The unit price of $8.40 per cubic yard for rehandling and washing
silted crushed limestone that remained in the barriers after  the  floods
was a negotiated price not included in the original contract, and
represented 35 percent of the contract bid price for furnishing and
installing new materials.

NOTE:  To convert cubic yards (cu. yds.) to cubic meters, multiply
       cu. yds. x 0.7646
       To convert square yards  (sq. yds.) to square meters, multiply
       sq. yds. x 0.8361
       To convert acre to hectare, multiply acre x 0.4047
                                     45

-------
                             SECTION  VII

                STREAM SAMPLING AND LIMESTONE ANALYSIS
GENERAL

Stream gaging and water sampling in connection with the evaluation of
the performance of the Trough Creek Limestone Barriers was conducted on
a monthly basis.  This work was started prior to placement of any crushed
limestone materials in the stream, and continued through the construc-
tion phase and for an additional period of time of approximately 17
months after completion of construction and flood damage repairs.  Se-
lected samples of limestone were placed in stainless steel containers
in the harriers during construction, and were periodically removed,
weighed and replaced.  Electron tnicroprobe and X-ray diffraction inves-
tigations were made on limestone samples to determine the chemical com-
position of deposits formed on the stones, and a determination was made
of various algae and protozoan species mixed with the inorganic coating
materials on the stones.

Eight (8) stream gaging stations were provided for measuring stream-
flow through the individual barriers, and fifteen (15) water sampling
points were established.  Figures 18 through 23 show the stream gaging
stations and water sampling points at the various limestone barrier
sites.

Stream Gaging

Streamflow was measured in gaging flumes of constant cross-section by
the velocity-area method.  Velocity was measured by a Gurley "Pigmy"
current meter, except that a timed surface float was used under certain
conditions when streamflow and depth of water was so low that meter
readings appeared erratic.

During the construction phase of the Project, water samples were col-
lected monthly at each of the six (6) limestone barrier sites.  At the
sites where gaging flumes were in place, streamflow was measured as noted
above.  However, at proposed downstream sites where gaging flumes had
not been constructed, water samples were collected and streamflow was
noted either "Estimated" or "Not Recorded."  "Estimated" streamflow de-
terminations were made either by surface float or current meter, where
all streamflow appeared to be confined to stream sections where the vel-
ocity could be measured and the cross-sectional area reasonably deter-
mined.  Where the pattern of streamflow was such that a reasonable esti-
mate of flow could not be determined, it was noted "Not Recorded."
                                   46

-------
_-
-~-
                                                                                        GENERAL  LOCATION  PLAN

                                                                                        LIMESTONE SAgglER.5 -SITE N-i
                                                                        I    SAMPLING POtNT
                               Figure 18.  Sampling  Points and Gaging Station —Site No. I

-------
y-
GENERAL  LOCATION   PLAN       „.
LIMESTONE  BARRIERS  - SITE A/g 2
                              •to  go
                           Figure  19. Sampling Points and  Gaging Station —Site No. 2

-------
                                                    LIME.STOUB SABGIEP M* 3C
LIMESTONE. BOKKIEK N* 3 A
 SAMPLING PO/AIT
   A/s 3A-D
                             SAMPLING POINT
                              /V* 38-0
  GENEZAL LOCATION PLAN
LIMESTONE BARRIERS -SITE A/fi 3
                                                          PO/MT   \ \ \
        SCALE
                    Figure  20.   Sampling  Points and Gaging  Station —Site No.  3

-------
       SAMPLING.  POINT
                                                                               GAGING
                                                                               FLUME
SAMPLING
POINT N*4-U
                          X
^L/M£5TONE B»KGl€K MS 4 C

      GENEPAL  LOCATION  PLAN
  LIMESTONE  BARRIERS -SITE  A
                  Figure 21.   Sampling  Points and Gaging  Station—Site No. 4

-------
                                                                       V M
                                                                       13 4 a>
                                                                       M « C
                          -PZ.XW-

           LIMESTONE  BARRIERS  N^ 5A  453
                        10  It  0
Figure 22.  Sampling  Points  and Gaging Station — Site No. 5

-------
~-
                                            SAMPLING PO/N T
                                              A/2 6-D
                                                                                 '—SAMPLING  POINT
                                                                                      AJt 6-U
    GENERAL  LOCATION PLAN
LIMESTONE BARRIE8S  -SITE N° G
                            Figure  23.  Sampling  Points and Gaging Station—Site No. 6

-------
Water  Sampling

At each  site, water  samples were collected upstream and downstream  from
the  individual barriers.  The collected water samples were packaged and
sent to  testing  laboratories designated by the Commonwealth of Pennsyl-
vania.   The water sample analysis consisted of determinations of pH,
acidity, alkalinity,  sulfates and iron.  The testing laboratories were
under  contract with  the Commonwealth for performing such services,  and
throughout the course of this sampling program, four separate laborator-
ies  conducted the chemical analyses.

During the construction phase of the Project, only one monthly sample
was  collected in the main stream and tributary at uncompleted limestone
barrier  sites.   As previously mentioned, restoration work was undertaken
at Limestone Barrier  Site Nos. 1, 2 and 4 to repair 1972 flood damages.
Although the barriers at Site Nos. 3 and 6 were not included in the
authorized restoration work, water samples were collected and analyzed
at these sites for the full sampling program period.  When it became
obvious  that barrier  performance at Site No. 5 was no longer effective
because  iron sludges  had coated rock surfaces and clogged voids in  the
crushed  limestone materials, water sampling at this site was discontin-
ued.

A complete tabulation of the results of analysis of water samples col-
lected during the study period is presented in the Appendix.  Figures
.24 through 29 show a  plotting of pH values at the various sites, up-
stream and downstream from the barriers.  These figures also show the
rate of  stream flow at the time of sample collection, and the sequence
of construction  of the limestone barriers.

As previously noted,  iron concentrations were generally less than 1
milligram per liter at all sampling points, except at Site No. 5.  The
results  of the sampling program are discussed in SECTION VII.

Limestone Analysis

The limestone analysis phase of the sampling program to evaluate the
effectiveness of the  Trough Creek Limestone Barriers consisted of placing
selected samples of limestone in the barriers in 22.86 cm x 22.86 cm x
22.86  cm (9" x 9" x 9") stainless steel baskets.  The baskets were of
welded construction and were fabricated from 2,54 cm x 2.54 cm x 0.32 cm
(1" x  1" x 1/8") angle frames and 0.305 cm (0.120") wire screens.  Wires
for screens were spaced 2.54 cm (1") center to center both ways.   Twelve
baskets  (two at  each  limestone barrier site) were installed in the bar-
riers  in 1971 and 1972 following completion of the work under the origi-
nal construction project.  Initially it was intended that the baskets be
removed  from the barriers at each site at three month intervals and be
                                   53

-------
analyzed for:

      (a) Loss of weight as a factor of time and flow
      (b) Tendency for deposits to form on the limestone
      (c) Chemical composition of any deposits

In this connection, vandalism was a problem at Site Nos. 1 and 2, and
some of the baskets at other sites were washed away or damaged during
the March and June 1972 floods.  Of the original twelve baskets that
were installed in the barriers only four baskets were recovered which,
upon loss of weight analysis, appeared to provide reasonably accurate
data.  These baskets were subsequently placed in the barriers at Site
Nos. 1, 2 and 4 following completion of flood restoration work in late
1972.

The schedule for removal and replacement of limestone filled baskets at
three month intervals could not be strictly adhered to, because it was
not possible or practical under certain conditions due to the nature of
streamflow in Trough Creek.  The baskets had to be placed near the
bottom of the barriers to insure that they would be submerged during
periods of low stream flow.  Installation of the baskets during average
or high streamflow would have required the use of heavy construction
equipment, which could have damaged the baskets and abraded the stones
during installation and/or removal, thus increasing the probability of
error in the loss of weight analysis.

Usually when baskets were removed from the barriers for sampling, silt
deposits, ranging from light to severe, were present in the voids of
the limestone pieces.   The limestone samples in each basket were washed
with clean water, scrubbed lightly with a soft fiber brush, dried,
weighed and then returned to the barriers.  Tables 10 through 13 show
loss of weight of the limestone samples in the four baskets that were
preserved and protected during the study period.-

A review of the limestone analysis indicates that the rate of loss-of-
weight (percent  per year) fluctuated over a wide range.  This variation
is attributed to the fact that sediment deposits clogged interstices
between the stones, thus inhibiting free stream flow through the baskets
and lessening the opportunity for reaction of the limestone with flowing
acidic water.  This matter is discussed in detail in SECTION VIII.  Al-
though the average rate of limestone consumption appeared to be in the
neighborhood of 3 to 5 percent per year,  it would be ill-advised to
attempt to predict the life of the limestone barriers on the basis of
the results of this loss-of-weight analysis.
                                   54

-------
Table 10. LIMESTONE ANALYSIS - BASKET NO. 2
Date Inatalled (I)
Date Removed (R)
2/10/71
2/3/7?
2/8/72
l/2li/73
2/8/73
8/10/73
8/21/73
12A3/73
1/3/7U
S/10/7U
5/23/7U
8/2/7U
Table 11.
(I)
(R)
(I)
(R)
(I)
(R)
CD
(R)
(I)
(R)
(I)
(R)
Weight Loaa of Weight Time
(Ke) (Kg) (Sara)
12.1714
0.1,714 3S8
12.0
12.0
0.013 351
11.987
11.987
0.212 183
11.775
11.775
0.123 111
11.652
11.652
0.193 126
11.1*59
11.U59
0.100 70
11.359
Rate of Loaa Conulatlra Loaa
of Weight of Weight
Wjwr yew) (Ka)
3.87U O.lrfli
0.112 0.1.87
3.528 0.699
3.U36 0.822
U.797 1.015
li.552 1.US
Total EUpeed
Time
(Oaya)
358
709
892
1,003.
1,129
1,199
LIMESTONE ANALYSIS - BASKET NO. 6
Date Inatalled (I)
2/8/72
5A8/72
6/20/73
12/13/73
1/3/7U
S/10/7U
5/23/714
8/2/7U
(I)
(R)
(I)
(R)
(I)
(R)
(I)
(R)
Weight Loaa of Weight Time
flC^ IK,) tDM)
12.5
0.122 100
12.378
12-37fl 0.279
12.099
"•°" 0.098 126
12.001
0.165 70
11.836
Rate of Loss Cumulative Loaa
of Weight of Weight
« per year) (KB)
3.562 0.122
U.67U O.ljOl
2.3U6 O.U99
7.170 0.66ti
Total Elapsed
Tine
(Days)
100
276
U02
1*72
                                       55

-------
Table 12.  LIMESTONE ANALYSIS - BASKET NO. 8
Date Installed (I)
Date Honored (H)
2/8/72
5A8/72
1/2U/73
12/13/73
1/3M
5AO/7U
5/23/7U
8/2/fl
Table 13.
(I)
(R)
(I)
(R)
(I)
(R)
(I)
(R)
Hate of toss
Weight loss of Weight Tine of Weight
(Kc) UK) (Days) « per year)
12.9
0.02$ 100 0.708
12.875
12.875
0.325 323 2.852
12.555
12.555
0.173 126 3.992
12.382
12.382
0.273 70 11.1*98
12.109
emulative Loss
of Weight
(X*)
0.025
0.350
0.523
0.796
Total Elapeed
Time
(Days)
100
b23
5I«9
619
LIMESTONE ANALYSIS - BASKET NO. 9
Date Installed (I)
2/6/72
l/2li/73
2/8/73
8/10/73
8/21/73
12A3/73
1/3/7U
5AO/7U
S/23/7U
8/2/7U
(I)
(R)
(I)
(R)
(I)
(R)
<«
(R)

-------
Limestone Coatings

After  the barriers were  in  service  for some  time,  the coatings on sur-
faces  of the crushed  limestone materials were examined for chemical
composition and biological  growth.  The Pennsylvania Fish Commission
collected stone samples  in  July 1971 at Site Nos.  1, 2 and 3.  They
found  that the material  coating the limestone at each site contained
a  significant amount  of  inorganic materials.  Attached to and mixed
with this material were  various forms of algae and protozoan species.
At  the time of the Fish  Commission  sampling  the barriers at Site No. 1
had been in service for  approximately 9 months, at Site No. 2 for approx-
imately 6 months, and at Site No. 3 for approximately 3 months.  The
results of the biological survey were as follows:

     Site No. 1 - Diatoms and protozoans abundant  in the film coating
                  the limestone.
     Site No. 2 - Diatoms replaced  by filamentous  algae which were
                  abundant.  Protozoans were reduced in number and
                  diversity.
     Site No. 3 - Film consisted primarily of inorganic materials,
                  with very few protozoans or algae forms present.

Deposits on limestone samples collected from the barriers were also
examined and anlyzed by X-ray diffraction, and later by electron micro-
probe  to determine elements present in the coating materials.  In July
1972 the coatings from limestone samples collected from each limestone
barrier site (six total) were scraped off and subjected to X-ray diffrac-
tion analysis.   All samples showed poor crystallinity, making phase iden-
tification difficult.. The materials that were;identified were calcite
(from  the limestone), quartz and gypsum.   Visually it could be seen
that iron oxides were present in the rock coatings, but since the X-ray
patterns did not show the presence of any iron compounds, they were as-*
sumed  to be amorphous (amorphous or non-crystalline materials will not
give an X-ray diffraction pattern, hence cannot be identified by this
technique).

In November 1972 an electron microprobe investigation was made of the
deposits on limestone samples collected from the barriers at Site. Nos.
2, 3 and 5.   Two wavelength scans were made of the deposits on these
samples, and the analysis showed the following elements present:

     Site No.  2 - Silicon,  Potassium,  Aluminum, Iron
     Site No.  3 - Aluminum, Silicon, Titanium, Potassium, Calcium,
                  Iron
     Site No,  5 - Calcium,  Aluminum, Iron, Silicon, Potassium,  Sulfur

One wavelength scan was made of a limestone sample collected from the
                                    57

-------
barrier at Site No.  1.  The coating deposits on the surface of this
stone were removed prior to analysis, and the investigation of this
sample did not show any elements being absorbed.
                                  58

-------
                                        STREAMFLOW cfi
19    IS     17    16    15    14    13    12
                                                           BARRIERS AT THIS SITE
                                                           RECONOITIONEO 10/10/72
                                                             FLOOD-JUNE, 1972
               pH UPSTREAM

               pH DOWNSTREAM

               FLOW
                                                           LIMESTONE BARRIERS SITE I
                                                                     KV26/7D
            Figure  24.   Performance  of Limestone  Barriers—Site  No.
                                                    59

-------
                   30
                                             STREAMFLOW (cfi)
                                             20	15
                                                                             BARRIERS AT THIS SITE
                                                                             RECONDITIONED  12/5/TZ
                                                               FLOOD-JUNE, 1972
    —•—•— pH UPSTREAM
             pH DOWNSTREAM
          — FLOW
LIMESTONE »ARRIERS AT SITE Z
CONSTRUCTED  I/2Z/7I
LIMESTONE JARRIERS AT SITE  I
CONSTRUCTED  IO/26/7O
                                                     •-
          Figure  25.  Performance  of Limestone  Barriers  —Site  No.  2
                                                  60

-------
                                             STREAMFLOW (cfs)

                                             25         ZO
 __ _ — PH UPSTREAM
          pH DOWNSTREAM
 	FLOW
 IMESTONE BARRIERS AT SITE 3
CONSTRUCTED  4/Z9/7I
                                                         FLOW NOT WCORDED

                                                               I
LIMESTONE BARRIERS AT SITE !
CONSTRUCTED   1/22/71
LIMESTONE CARRIERS AT SITE. I
CONSTRUCTED  10/26/70
        Figure  26.   Performance   of   Limestone   Barriers —Site  No.  3
                                                61

-------
 90
            80
                       70
  STREAMFLOW (da)
60         50      	40
                                                                   30
                                                                              20
                                                                                         10
                                                                    LIMESTONE BARRIERS AT SITE 4
                                                                    CONSTRUCTED  8/2O/7I
                                                                                                     JAN.
— — — pH UPSTREAM
——— pH DOWNSTREAM
	FLOW
                                  LIMESTONE BARRIERS AT SITE 3
                                  CONSTRUCTED 4/29/71
                                                                    LIMESTONE BARRIERS AT
                                                                    CONSTRUCTED   1/jJ/Tl
                                                                    LIMESTONE BftRBIEBS AT SITE  I
                                                                    CONSTRUCTED  IC/26/70
                                                                   JAN

                                                                   z o

                                                                   o~
        Figure  27.   Performance   of   Limestone  Barriers—Site No. 4
                                                62

-------
                                STREAMFLOW  (cfs)
                                2
     pH UPSTREAM
    ' pH DOWNSTREAM
     FLOW


FLOOD- JUNE, 1972
                                                                                  JAN.
                                                                                  Q

                                                                                  -•
N
!„
                                                                        1
                                                                                  .1
                                                                                  :-
                                                                                  JAN.
                                               LIMESTONE BARRIERS AT SITE 5
                                               CONSTRUCTED     5/2O/7I
                                                                         \
                                                                             ^> -
                                                                            t   -
                                                                            i
                                                                                  JAN.
Figure  28.   Performance  of  Limestone  Barriers—Site No. 5
                                    63

-------
90
           60
                      70
   STREAMFLOW  (cfs)
60	50	
                                                        40
                                                                    30
                                                                               20
                                                                                          10
                                                                     LIMESTONE BARRIERS AT SITE 6
                                                                     CONSTRUCTED    11/26/71
                                                                     LIMESTONE BARRIERS AT SITE 4
                                                                     CONSTRUCTED   8/20/71
                                                                     JAN.

                                                                     Q

                                                                      •



                                                                     VI

                                                                     •I

                                                                     LIMESTONE BARRIERS AT SITE 3
                                                                     CONSTRUCTED     4/29/71
           pH UPSTREAM
           pH DOWNSTREAM
           FLOW
                                   LIMESTONE BARRIERS AT SITE 2
                                   CONSTRUCTED    1/22/71
                                                                     LIMESTONE BARRIERS AT SITE I
                                                                     CONSTRUCTED   O/26/7O
JAN.
                                                I.H
        Figure   29.   Performance  of  Limestone  Barriers—Site  No.  6
                                                 64

-------
                               SECTION  VIII

                      LIMESTONE BARRIER PERFORMANCE
 GENERAL

 The  performance  of  six  Trough Creek prototype  limestone barrier  instal-
 lations  was  observed  during and after  the construction phase of  the pro-
 ject for the period extending from October 1970, when the first  barrier
 was  erected,  to  August  1974.  Information gathered  throughout the samp-
 ling program period,  together with observations noted in the field, made
 it possible  to evaluate the effectiveness of in situ limestone barriers
 over a wide  range of  stream conditions.  The field  observations  and t"he
 data collected during the sampling program also provided useful  infor-
 mation in evaluating  the extent to which design relationships used for
 this project, that  were developed from laboratory research, could be
 supported.

 It is apparent from even a cursory examination of the results of the
 stream sampling  program that the limestone barriers, as constructed,
 were not  successful in  providing workable facilities satisfactory for
 area-wide abatement of  pollution from  acid mine drainage in the upper
 reaches of the Trough Creek Watershed.  Although barrier performance
 was  excellent during  periods of low stream flow, in terms of reducing
 acidity and raising the pH of the water, their effectiveness was mar-
 ginal at  design  flows,  and they were completely ineffective when high
 runoffs were experienced.  Also, it is apparent from a review of the
 results of the stream sampling program that limestone barriers are
 most  efficient when they are initially installed, or after they have been
 otherwise restored  by reconditioning and repair work similar to that un-
 dertaken  following  the  1972 flood.  For the Trough Creek Project, lime-
 stone barrier performance deteriorated after the the structures had been
 in service for some time following initial construction, and again after
 the  barriers had been reconditioned following flood damage restoration
 work.

 Deterioration of Limestone Barrier Performance

 The rate  of deterioration of limestone barrier performance is apparently
 dependent upon two major factors;  namely, siltation and coating of the
 surfaces  of the stones.   The most serious cause of barrier deterioration
 for  the Trough Creek  Project appeared  to be sealing of the crushed lime-
 stone materials,  whereby sediment accumulations of either silt or iron
 sludges clogged interstices between the stones.  The result of such clog-
 ging not  only reduces the effective porosity and hydraulic conductivity
of the crushed limestone beds,  but also lessens availability of the
reagent (limestone)  to flowing acidic water.

                                   65

-------
When  limestone barriers are  initially constructed, or after they have
been  reconditioned, almost all of  the limestone materials are available
for neutralization.  However, after  sediment deposits begin to accumu-
late  and  clog voids in the limestone materials, the  streamflow pattern
through a barrier begins  to  channel, causing short-circuiting of the
flow  and  the resultant reduction in  retention  time.  The hydraulic
capacity  of limestone barriers likewise diminishes as silt deposits
accumulate, because the permeability of clogged or partially clogged
beds  becomes substantially reduced.

The other factor that causes deterioration  of  the performance of
limestone barriers is coating of the surfaces  of the stones with silt
or iron hydroxides.  During  periods  of turbid  or muddy  streamflow, silt
collects  on the surfaces  of  the stones.  The effect  of coating of the
stones is a buffering action that  effects a reduction in the neutrali-
zing  ability of the limestone.  Although the silt coatings are easily
removed physically by washing, they do not have a tendency to wash or
flake off in the stream.  Rather,  they tend to build up over a period
of time, depending on stream conditions, and progressively lessen lime-
stone reactivity.  It was also found that during the warmer months of
the year algae growths were mixed with the inorganic coating materials.

For the Trough Creek Project, the combined effect of coating of the sur-
faces of the stones and sealing of the beds was that deterioration of the
performance of the limestone barriers was experienced within a few months
after initial construction, and again after reconditioning.   It should be
noted, however, that except where the surfaces of the stones become ar-
mored with iron hydroxides, the upper layer of limestone appears to
remain effective, because the barriers continued to neutralize acidity
when  stream flow was very low.

General Observations - Silting of Limestone Barriers

Where limestone barriers are to be installed to neutralize acidity in
streams subject to severe flooding and a wide variation of flow,  acknow-
ledgment must be made of the fact that sediment deposits will tend to clog
voids in the crushed limestone materials and stone surfaces  will become
coated with silt.   In this connection,  the following observations were
noted for the Trough Creek Project:

     1.   Silting,  and the resultant clogging of voids of limestone
         materials,  is more pronounced  during the first year after
         installation,  because:  (a) existing stream beds and streamflow
         patterns were altered,  and (b)  vegetation and  natural ground
         cover adjacent to the structures was disturbed  and/or des-
         troyed during the construction operations,  thus increasing
         the possibility of soil erosion from surrounding areas.
                                    66

-------
     2.  Where limestone barriers are constructed in areas where the
         slope of the stream bed is steep, such as at Site No. 3, con-
         sideration should be given to lining both the creek banks and
         channel with rocks for the entire reach of stream to prevent
         erosion, and also the placement of large stones in the channel
         area approaches to disrupt and disperse streamflow patterns.

     3.  Stream channel approaches to the limestone barrier sites should
         include provisions for dissipating the kinetic energy of stream
         flow.  The work under the Trough Creek Project included con-
         struction of grouted stone rip-rap flumes at each site for the
         purpose of measuring the rate of stream flow during the samp-
         ling program.  At Site Nos. 3, 4 and 6 the flumes were installed
         upstream from the barriers and provided a straight, fairly
         smooth channeled water course of constant cross-section with
         invert elevations higher than what was expected to be normal
         water level.  During periods of high runoffs the streamflow
         through the flumes approaches scouring velocity, and apparently
         stirs and churns previously settled mud and silt in the stilling
         basin areas, carrying these materials onto the barriers.

Concurrent Studies - Trough Creek Limestone Barriers

In November 1972, the Institute For Research On Land And Water Resources
at The Pennsylvania State University initiated additional research rela-
tive to the reactivity of limestone with acid mine waters.   (3)This
research work was undertaken after the limestone barriers at Site No. 1,
2 and A had been substantially restored to approximate original condition
following damages experienced as a result of the June 1972 flood.  The
water sampling and analysis portion of the University study was conducted
concurrently with the sampling program under this evaluation project;
however, the chemical analysis and the laboratory testing procedures at
the University were considerably more comprehensive in scope.

The University Study concluded basically that limestone barriers can be
used effectively to neutralize acid waters if they are designed properly
and if the iron concentrations are sufficiently low.  The study indicated
that the proper design was found to depend very heavily on the reduction
of reactivity of the limestone due to deposits of silt and precipitates
which may have formed.  For the barriers in Trough Creek this reactivity
was found to have apparently decreased five-fold from limestone reacti-
vity monitored under clean conditions in the University laboratory.

As a consequence of this University study, a set of design graphs was
generated which incorporate the reduction in limestone reactivity so
that the designer can take this factor into account and build the system
sufficiently large to overcome this deficiency.   The University concluded
                                    67

-------
that even with the increased volume requirement, limestone barriers
appear to provide a reasonably economical solution for neutralization
of acid waters under conditions of low iron concentrations,

Evaluation - Limestone Barriers

The undertaking of construction of the Trough Creek Limestone Barrier
Installation Project was the first such endeavor for in-stream treat-
ment of acid mine drainage for an entire watershed where the range of
streamflow was of the magnitude of Trough Creek.  The design relation-
ships used for this prototype project were developed from laboratory
research in the late 1960's at The Pennsylvania State University,
Presented below are evaluations of the design relationships based on
the experiences of the performance of the Trough Creek Limestone Bar-
riers.  These evaluations are based on results of the sampling program
and field observations noted during the study period October 1970 to
August 1974.

     1.  The performance of the limestone barriers, in terms of redu-
         cing acidity and raising the pH of the water, did not reach
         theoretical efficiency,  except for a short period of time at
         Site No.  5.   A possible explanation for the reason they did
         not  reach theoretical efficiency is that the design relation-
         ships for reduction of acidity were formulated from labora-
         tory experiements using synthetic acid waters of both 50 and
         100  mg/1 initial acidity; whereas, initial stream acidities
         (upstream from the barriers) for the Trough Creek Project
         were  only in the neighborhood of 10 to 20 mg/1, except at
         Site No.  5 where initial acidity was approximately 150 to
         200  mg/1.   If initial acidity in the stream had been some-
         what higher,  the percent reduction of acidity may have been
         greater.

     2.  Limestone  barrier performance was more efficient for the long,
         continuous barriers at Site Nos.  1,  4 and  5 than it was for
         the  short, multiple barriers at  Site Nos.  2 and 3.   The lab-
         oratory research thesis  postulated that' acidity reduction is
         proportional  to the total length of  the barrier, without regard
         to whether it is an integrated long  structure or comprised of
         segregated  short units.   At Site Nos. 2 and 3 two short bar-
         riers,  approximately 7.6 meters  (25  feet)  in length, were
         positioned in series in  the.main channel of the stream.   At
         Site Nos.  1 and 4 the barriers were  interconnected  with shallow
         limestone  fills and the  barrier  at Site No.  5 consisted of a
         single  structure.   The limestone fill areas for the barriers
         at Site Nos.  1,  4 and 5  were all in  excess of 45.7  meters (150
         feet)  in  length.
                                   68

-------
3.  The performance of the limestone barrier at Site No.  5 was
    excellent after completion of initial construction.   The
    characteristics of the raw acid mine drainage at this Site
    were approximately 150 to 200 mg/1 acidity and 30 mg/1 (total)
    iron.  Within a period of approximately three months  the per-
    formance of this barrier, for all practical purposes, com-
    pletely deteriorated because of accumulations of iron sludges
    in the limestone bed and armoring of the surfaces of  the stones
    with iron hydroxides.

4.  Initial performance of the limestone barriers was good at all
    other sites (Nos. 1, 2, 3, 4 and 6), where iron concentrations
    of the water were approximately 1 mg/1 or less, but perform-
    ance also deteriorated to a considerable degree after a few
    months following completion of construction.  This deterior-
    ation is attributed to sediment accumulations sealing the lime-
    stone beds and also coating of the surfaces of the stones with
    silt.  This condition was discussed in detail previously in.
    this SECTION.

5.  The performance of silted limestone barriers can be restored
    to approximate initial efficiency by performing recondition-
    ing work similar to the procedures adopted for flood  damage
    repairs at Site Nos. 1, 2 and 4.

6.  It was difficult to attempt to assess the accuracy of hydraulic
    design relationships regarding head losses, stone size and flow
    through the barriers, because sediment deposits accumulated in
    a short period of time following completion of construction,
    causing "dead spots" in the barriers and channelling  flow
    through indeterminate areas.  However, the head loss  relation-
    ships seemed to be confirmed by observations noted over a limi-
    ted range of streamflow during the short period of time the
    barriers were in clean condition.

7.  Although the research thesis recommended the use of  small stone
    sizes for the crushed limestone materials, consideration must
    be given to the magnitude of high runoffs and flood flows that
    might occur that will cause scouring of the materials.  For the
    Trough Creek Project a considerable degree of scouring was
    experienced, even though the larger stone sizes (6.35 cm to 10.16
    cm, or 2 1/2" to 4") were used in the barriers.
                              69

-------
Comments Regarding Future Limestone Barrier Design

On the basis of the conditions experienced with the Trough Creek lime-
stone barriers, it is apparent that the design of such units must take
into account the effect of deteriorating barrier performance caused by
siltation and coating of the surfaces of the stones.  The five-fold re-
duction in limestone reactivity noted in the recent Pennsylvania State
University research study would appear to provide an ample factor of
safety for design.  Likewise, it seems apparent that in the design of
limestone barriers, the size of the units should be determined from
design flows greater than those used for this project.  (Design flows
for Trough Creek Limestone Barriers were 1.25 times computed average
flow.)  A considerable portion of the Trough Creek Project watershed
consists of wooded lands, some farms, and other areas where acid mine
drainage would not be generated from surface runoffs.  Originally, it
was believed that ample dilution of stream acidity would be afforded
during periods of high surface runoff from these areas.  The results
of the sampling program indicate that a more realistic value for design
flow would appear to be approximately 300 percent of computed average
streamflow, depending on watershed conditions.

Barrier configuration will naturally depend to a certain degree on top-
ography of the areas adjacent to proposed structures.  However, barrier
performance will probably be more efficient if the units are long, con-
tinuous structures, flat and relatively shallow (approximately 1 meter
or 3 feet in depth or less), and constructed in areas where adequate
hydraulic gradient is available under all conditions of streamflow.

It is evident that a maintenance program should be established to period-
ically recondition limestone barriers so that performance will not de-
teriorate beyond required efficiencies.   The scheduling and extent of
such maintenance work would be dependent on local conditions and water-
shed runoff characteristics.

A reasonable estimate of the life of properly operated limestone barriers
could not be determined from the limestone loss of weight analysis, be-
cause of the siltation problems noted in SECTION VII.  However, with the
excess volume of limestone needed to compensate for reduction in lime-
stone reactivity, together with the larger structures required to accomo-
date high design flows, the amount of crushed limestone materials that
would be furnished for properly sized units would undoubtedly provide
ample reagent for many years.

In view of the deficiencies in performance of the limestone barriers on
the Trough Creek Project, it is questionable whether it is feasible to
attempt to provide in-stream limestone barriers exclusively as the
treatment method for area-wide mine drainage pollution abatement, even
                                    70

-------
though the chemical characteristics of the acid waters appear suitable
to treatment with limestone.  Rather, it is believed that construction
of limestone barriers in conjunction with other watershed improvements,
such as backfilling strip mined areas, replanting and possibly some
mine sealing, would be a more practical approach to regional mine
drainage pollution abatement where the watershed areas and runoff
characteristics are similar to those of Trough Creek.
                                  71

-------
                              SECTION IX
                              REFERENCES
1.  Yen, Alan Fong - I, Design of Limestone Barriers in Acid Mine
    Water Streams, A Thesis in Civil Engineering,  The Pennsylvania
    State University, University Park,  September,  1969.

2.  Africa Engineering Associates, Inc.,  details reproduced from
    Plans for Contract No.  SL-121-1, Construction of Limestone
    Barriers - Trough Creek Watershed - Huntingdon and Bedford
    Counties, Pa., prepared for Department of Mines and Mineral
    Industries, Commonwealth of Pennsylvania, by Africa Engineering
    Associates, Inc., Consulting Engineers, Huntingdon, Pa., 1970.

3.  Pearson, F. H. and McDonnell, A. J.,  "Neutralization of Acidic
    Wastes by Crushed Limestone, "Research Publication No.  79, and
    "Evaluation of Prototype Crushed Limestone Barriers for the
    Neutralization of Acidic Streams,"  Research Publication Number
    80, Institute for Research on Land  and Water Resources, The
    Pennsylvania State University, University Park, Pennsylvania,
    June, 1974.
                                 72

-------
                           SECTION  X

                           APPENDIX


                                                  Page

A.  Key to Symbols Used in Reporting Results
     of Water Analysis and Sample Collections      74

B.  Water Analysis - Site No. 1                    75

C.  Water Analysis - Site No. 2                    78

D.  Water Analysis - Site No. 3                    80

E.  Water Analysis - Site No. 4                    84

F.  Water Analysis - Site No. 5                    88

G.  Water Analysis - Site No. 6                    90
                          73

-------
                         COMMONWEALTH OF PENNSYLVANIA
                   DEPARTMENT OF ENVIRONMENTAL RESOURCES
                   BUREAU OF PLANNING AND COAL  RESEARCH

       TROUGH CREEK LIMESTONE BARRIER INSTALLATION AND  EVALUATION
                             PROJECT NO. 14010 - FWW
       	CR-105 	

KEY  TO SYMBOLS USED IN REPORTING RESULTS OF WATER ANALYSIS AND SAMPLE
                                  COLLECTIONS

  *      Estimated stream flow. Accurate measurements of Stream Flow were not made until
         grouted rip-rap measuring flumes were constructed.

  N.R.   Stream Flow not Recorded. Flow pattern of stream was such that a reasonable
         estimate  of the rate of flow could not be made at time of sample collection.

         Values not reported by Testing Laboratory.
IQUENCE OF
Site No.
\
2
3
4
5
6
CONSTRUCTION - LIMESTONE BARRIERS
Date Started
July 27, 1970
October 27, 1970
January 25, 1971
May 20, 1971
May 3, 1971
August 20, 1971
Date Completed
October 26, 1970
January 22, 1971
April 29, 1971
August 20, 1971
May 20, 1971
November 26, 1971
(Extra Work)
Change Order No. 1
  1,4,5,6         April, 1972              May 15,1972

(Extra Work)
Change Order No. 2
  1,2,4         September 26,1972          December 5,1972
NOTE:    To convert cubic feet per second (cfs) to m3/s; multiply cfs x 0.02832
                                      74

-------
TROUGH GREEK LIMESTONE BARRIER INSTALLATION AMP EYALUATIOK
SHEET I WATER ANALYSIS
Sampling
Date
10/2/70
10/28/70
11/27 /YO
12/30/YO
1/26/71
2/26/71
3/30/71
U/28/71
5/28/71
7/2/71
3/5/71
8/31/71
10A/71
iiA/n
12/1/71
l/h/72
2A/72
2/28/72
Flow
(cfs)
0.25*
0.8U
8. It
10.2
7.0
12.0
5.0
0.8U
U.2
0.13
0.78
0.00
0.26
2.6
•5.26
3.9
2.2
U.9
- SITE NO. 1
PH
1-TJ
3.8
3.8
U.U
U.3
U.3
U.6
U.6
U.3
U.I
U.6
3.7
Samples
3.7
3.9
U.O
U.2
3.9
U.I
1-D

6.0
5-2
U.6
U.8
U.8
U.8
5.5
U.7
7.2
5.6
Acidity Alkaltolty
"(rogA) (mgAl
1-TJ
32
32
6
8
8
0
10
12
0.6
—
22
not collected - no
6.1
U.8
a. 8
5.2
U.U
U.I
22
6
U
u
8
U
l-D 1-U
0
U
0 0
10
u o
0 0
12 —
8
__
U
0
flow
—
0
0
—
6
2
1-D

8
0
0
0
U
—
0
6
uu
0

8
0
0
6
~
SOU (me/3
(mgA!
1-U ]
105
70
—
2lt
PROJECT NO
. 1U010 - FWW
CR-105
L) Iron (wRA)
1-U
L-D Total
0.55
6.25
0.25
28 1.7
1-D
Ferrous




32 100 3.3
32
28
36
UO
20 0.35
28 0.1
28 0.55
28 0.1
UU 80 0.1
75 75 6.0


95 75 0.3
UO 30 0.1
2U 18 0.1
UU UO 0.1
38
UO 0.1
Itlt UO 0.1
0
0
0
0
0
0

0
0
0
0
0
0
Total

O.Y
1.65
5.25
0.35
0.7
0.1
0.35
0.1
1.1
U.2

0.1
0.1
0.1
0.1
0.1
0.1
Ferrous





0
0
0
0
0
0

0
0
0
0
0
0

-------
TROUGH CHEEK LIMESTONE BARRIER INSTALLATION AND EVALUATION
(Con't)
Sampling
Date
3/31/72
U/25/72
5A8/72
7/5/72
7/2h/72
8/22/72
9/26/72
10/26/72
11/30/72
1/8/73
2/15/73
3/30/73
U/23/73
5AO/73
6/7/73
7A6/73
8A7/73
10A6/73
10/2U/73
SHEET II
Flow
(cfs)
N.R.
7.0
6.6
7. *
O.U
0.05*
c.oo
0.00
8.7
7.0
12.0
7.0
12.0
U.8
2U.7
0.3
trickle
trickle
O.U
WATER ANALYSIS - SITE
pH
1-U
U.6
U.7
U.2
U.7
U.9
5.1
Samples
n
U.3
5.o
U.5
5.5
U.6
U.5
U.6
U.8
6.7
6.1
3.9
NO. 1
Acidity
(BRA)
1-D
U.7
U.8
U.8
U.9
7.2
7.0
not
n
7.1
5.5
5.9
5.1
U.7
U.7
U.8
7.0
7.2
7.0
6.6
1-U
9
8
8
12
1U
16
collected -
ti
n
3
7
. 3
9
8
10
8
0
0
18
1-D
25
7
n
10
8
15
no flow
,,
9
7
6
5
6
10
5
0
0
0
10
PROJECT NO. 1U010 - FWW
Alkalinity
1-U
2
2
~
—
—
2


0
9
0
0
0
0
0
0
0
0
0
1-D
3
2
—
—
—
U5


18
12
0
0
0
0
0
20
52
Uo
10
SOU (mgA)
1-U
20
2U
21
29
2U
31


27.5
22.5
2U
20
22
26
22
29
2U
26
Uo
1-D
25
26
25
30
26
37


29
25
17
20
2U
26
2U
2U
26
36
60
CR-105
Iron (m
1-U
Total Ferrous
0.21 0.12
0.32 0.08
0.33 0.06
O.U7 0.06
0.33 0.06
0.52


0.20 0.02
0.21 O.C8
0.2 <0.2
0.1
<0.1
0.2 <0.2
<0.1 
-------
TROUGH CREEK LIMESTONE BARRIER INSTALLATION AND EVALUATION
(Can't) SHEET HI WATER
Sampling How
Date (cfs)
11/23/73
12A9/73
2AU/7U
3A/7U
UA1/7U
U/30/7U
5/28/7U
6/27/7U
8/5/74
3.7
8.6
6.9
12.0
7.1
7.1
8.1
6.7
Trickle
ANA1TSIS - SITE NO, 1
Tfl
1-0
3.8
U.2
u.u
U.o
U.2
U.3
lt.5
U.l
5.6
1-D
U.I
U.3
u.u
U.3
U.2
U.3
U.6
U.1
6.5
Acidity
(npA)
1-U
8
U
6
U
6
6
2
10
8
1-D
10
2
6
8
6
6
2
10
6
Alkalinity
CragA)
1-U
0
0
0
0
0
0
0
0
12
1-D
0
0
0
0
0
0
0
0
82
PROJECT NO. 1U010 - JWW
SOj, (mgA)
1-U
35
23
20
26
U5
23
27
26
26
1-D
33
22
21
27
35
26
26
2U
30
CH-105
Iron (n
1-0
Total Ferrous
0.1U6 	
0.1U6 	
0.1U6 	
0 	
0
o —
0 	
o —
o —
eA)

1-D
Total
0.1U6
0.1U6
0
0
0
0
0
0
0
Ferrous
. —
	
_ __
	

- —
	
	
_ __

-------
                                                                                                                        TftOUQH CREEK LDESTCTTE 3ARRIEt TH3TAU.ATIM AHD EVAMHTIOK
oo
SHEET I
Date
10/2/TO
10/28/70
11/27/70
12/30/70
1/26/71
2/26/71
3/30/71
U/28/71
S/28A1
7/2/71
s/sm
8/31/71
10A/71
11/1/71
12/1/n
l/U/72
2A/72
2/28/72
3/31/72
U/25/72
SAB/72
7/5/72
7/2U/72
8/22/72
WATER ANALYSIS
Plow
(cfs)
0.65*
2.0
9.6
U.6
8.U
20.0
1U.8
2.1
S.o
0.6
1.35
0.01
0.61
8.5
S.o
6
6.5
6.8
8.1
20.3
1U.O
19.3
0.7
0.06

2-U
U.6
U.7
U.9
U.6
U.7
S.O
U.8
U.7
U.U
U.2
s.s
U.o
U.7
U.3
5.3
5.0
U.2
U.U
i.8
6.1
U.8
5.U
5.2
U.8
PH
2B-D

U.6
S.O
S.O

U.6
U.7
5.U
6.3
U.8
U.7
5.2
5.1
U.I
U.8
k.6
3.9
U.9
S.U
5.8
6.1
- SITE KO. 2
Acidity (n*.A)
2A-D

5.7
S.o
5.0
5.1
U.9
6.0
5.6
6.U
5.2
U.7
5.2
U.8
U.3
U.8
U.9
3.7
U.9
5.3
7.2
6.9
2-D
16
3
10
10
0
U
8
2
U
8
0
12
0
6
0
—
U
2
7
6
5
5
22
20
2B-D

0
U
8

— ..
0
0
~
10
u
2
—
6
—
8
10
6
6
9
27
2A-D

2
16
8
U
0
—
—
—
—
8
—
—
U
—
6
12
U
6
9
19
Alkalinity (iaeA)
"2^5 2B-D 2A-D
0
U
0
0
0 0
0 0
—
0
	 6
0
0 0
— 10
0
—
0
2 It
..
18
1 1
U o
_
—
—
1 16

0
0
—
0
0
6
h
22
U
"
10
2
—
18
2
0
—
—
—
3U
PROJECT KO.
SO . .
U (*x/l) *•
2-0
68
26
20
22
2S
36
2U
1.2
ii
60
75
30
30
28
U8
UO
30
21
23
?7
29. 5
i.7
2U-D

26
2U
?U

32
70
38
70
75
U2
2a
18
UO
UO
23
26
2U
27
29
..
2A-D

28
32
32
JU
32
50
5U
85
Uo
22
38
38
UO
28
28
28
17
?7
31
—
rote.
o.US
2.1
0.2
O.U
1.15
1.0
0.1
0.3
0.1
0.1
0.6
1.1
0.1
2.2
1.0
0.1
0.1
0.1
0.19
0.36
0.30
0.26
2.88
0.23
lllOlO -
FWW


CR-105
Iron («K/1)
•U 2B-D
P»m)us


O.U
0
0
0
0
0
0
0
0.1
0
0
0
0
0.12
0.13
0.12
0.06
0.03
—
To til

0.35
0.2
0.1

0.2
i.U
1.1
5.5
0.1
0.1
0.1
0.1
0.3
0.3
0.19
0.26
O.U1
0.2U
0.32
0.83
Ferrous


0
0

0
0
0
0
0
0
0
0
0
0
O.OB
0.12
0.10
0.06
O.C3
—
2A-D
Tot«i

O.U
0.2
0.1
o.US
0.1
o.S
0.6
2.0
0.1
0.1
0.1
0.1
0.1
0.1
0.09
0.20
0.32
0.23
0.23
0.75
Ferrous


0
0
0
0
0
0
0
0
0
0
0
0
0
0.02
0.03
0.08
0.03
0.03
w

-------
                 (Con't)  SHEET n     WATER AMIJSIS  -  SHE HO.  2
-J
VO
S*ipUng
9/26/72
10/26/72
11/30/72
1/8/73
2/15/13
3/30/73
1/23/73
5/10/73
6/7/73
7/16/73
8/17/73
10/16/73
10/2U/73
11/23/73
12/19/73
2AU/7U
3A/7U
UA1/TU
U/30/7U
5/28/7U
6/27/7U
B/5/74
now
(cTa)

Swnlee
1U.3
8.6
1U.8
11.5
37.5
30.5
37.1
o.u
trickle
trickle
0.5
6.8
1U.8
16.9
.31-0
1U.2
15.8
10.5
13.3
OS
J*
9_TT 9t^fi 91 «T)
not collectod - no
not collected - DO
U.8 U.9 U.9
U.7 6.5 5.8
5.9 5.0 5.6
5.0 5.2 5.3
U.9 5.0 U.9
5.0 5.1 5.2
5.0 5.1 5.1
U.3 6.8 6.U
6.8 6.2 6.6
U.6 6.9 6.5
U.U 5.8 5.8
U.1 U.1 U.2
h.5 U.6 U.S
U.8 U.8 U.B
U.S U.6 U.7
U.S U.8 U.6
U.6 U.9 U.9
5.0 S.o 5.1
U.6 U.S U.S
4.8 6.2 6.2
Aeldltr (»E/«
4_rt 4D n <*« n
flow
flow
6
6
7
8
U
8
8
8
0
6
10
8
U
2
U
u
u
2
8
10


5
U
6
U
U
8
6
0
0
0
10
8
u
U
2
U
U
2
6
6


U
2
3
U
8
U
6
0
0
0
10
10
2
2
U
u
2
2
8
8
All
*, t]


1
2
0
0
0
o
0
0
30
0
2
0
0
2
0
0
2
6
2
4
[O4n4t^


2
lU
0
0
0
0
0
0
IB
32
U
0
2
U
2
2
U
6
0
42
A* T\
— 2A~D

2
9
0
0
0
0
0
0
1U
36
10
0
0
6
2
U
u
u
0
44
sc
2-0

23
22
17
15
12
31
26
38
S3
to
35
32
26
19
2k
30
2U
23
2U
36

2B-3

23.5
21
17
10
19
2U
29
3U
58
US
UO
27
20
19
22
US
21
26
20
38
I
2A-D

23
21
17
20
17
lU
36
3U
U6
SO
35
30
20
19
23
30
18
2U
20
39
CS-105
Iron f«E/l)
2-0 26-D


0.18 0.02 0.21 0.02
0.10 0.03 0.12 0.08
0.1 <0.1 0.1 
-------
TROUGH  CREEK LIMESTONE  BARRIER  INSTALLATION AND EVALUATION



SHEET I

Sampling
Date
IO/2/7O


0/28/70

II/27/7O


I2/3O/7O


1/26/71


0 2/26/71

3/3O/7I


4/28/71


5/28/71


7/2/71


8/5/71

8/31/71


W/l/71


Flow
(Bfs)
I.O-
0.6 +
1.6 •
2.9 »
IS*
12.5 •
1.2*
13.7»
18.3*
3.O*
21.3*
10.7 •
1 .0*
11.7*
N.R.
N.R.
18.0*
3.9*
21.9*
3.75
O.65
4.4
6.7
4.9
11.6
0.75
0.31
1.06
§Ji
3.63
O.O9
O
O.O9
2.81
0.46
3.27


3-U
4.7


5.1

4.6


4.3


4.8




4.4


4.4


4.3


4.2


5.7

4.3


4.9


WATER ANALYSIS - SITE NO. 3

pH Acidity (mg/l) Alkalinity (mg/l)
3-T 3B-D 3A-D 3-U 3-T 3B-D 3A-0 3-U 3-T 3B-D 3A-0
0 9O
4.6 IO
4.6 IO
4 4
43 6
16 O
4.8 10 O
4.7 0( ) O
4 O
4.8 4 O
4.4 6 O
4 0
4.9 0 0
4.7 O O
5.O 2 0
6-3 0 2
4
4.8 K>
4.7 14
6 0
4.8 6 O
5.O O O
4
4.6 — 6
4.4 4.4 44 — —
10
4.6 2
4.6 5.O 0 O O O
2
4.4 6
5.5 6.0 00 0 O
2
__ --
4.9 5.6 14 8
— 6
46 4
5.O 5.4 0 16 O
PROJECT NO. 14010 -FWW
CR-105
Iron (ma./l)
S04 (mg/t) 3-U 3-T 3B-D 3A-D




3-U 3-T 38-D 3A-D Total Ferrous Total Ferrous Total Ferrous Total Ferrous
72 0.35
44 055
48 o.l
8
12 O.I
O.25
0.2
0.4
36 0.4
12 1.2
22 0.8
36 0.55
20 0.8
32 1.9
28 O.25
22 O.25
24 O.I
28 O.I
24 O.I
28 0.3 0
24 O.6 0
40 O.4
28 0.2 O
38 O.I 0
48 40 O.2 O O.3
80 O.I 0
28 O.I O
6O 80 O.4 O 0.4
38 1.3 O
24 O5 0
44 38 1.7 O O.I
7O O.t 0
— — — _ _
6O 6O O.3 O O.8
38 O.I O
24 O.I 0
38 38 O.I O O.I





















0


0


O

O




O

-------
                                                            TROUGH  CREEK  LIMESTONE BARRIER INSTALLATION AND EVALUATION
oo
SBEE3LJE
Sampling
Data
II/I/7I
12/l/Tt
1/4/72
2/1/72
2/28/72
3/31/72
4/25/72
5/B/72
7/5/72
7/24/72
8/22/72
9/26/72
Flow
(eft)
t.2
.6
11.8
6.4
2.5
8.9
'1:1
15.7
2*1
HO
15.5
5.9
21.4
9.6
»'.:!
26.3
7.0
33.3
155
5.6
21.1
225
7,0
29.5
1.0
0.8
1.8
0:3
ft
O.II
O.OO
O.II

3-U
4.8
5.1
5.1
4.2
4.7
4.5
3.7
4.4
SI
5.1
5.1
4.3
WATER ANALYSIS - SITE NO 3

3-T
4.6
4.7
4.9
4.3
4.4
5.2
4.4
5.O
53
5.2
5.O

pH Acidity (mg/l) Alkalinity (ma/I)
3B-D 3A-0 3-U 3-T 3B-O 3A-D 3-U 3-T 3B-O 3A-D
- 2
5.1 5.O 4 - — 42
O O
5.4 5.4 O — O 4
6
4
5.1 53 0 — O 6
4.3 4.4 6 12
" 2 2 .
4.7 4.9 - 46
II 0
6 2
4.6 4.6 IO IO 21
13 O
6 0
3.9 3.7 II 13 O O
IO
4.7 4.8 97 -. _
9
5.2 5.1 O 8
IO
6.8 6.1 69 ™ —
K> 2
13 2
7.6 55 5 15 75
IS O
5.5 5.5 II 12 28
PROJECT NO. 14010 -FWW
CR-105
Iron (rng/l)
SO« lma/1) 3-U 3-T 3B-D
3-U 3-T 3B-0 3A-D Total Ferrous Total Ferrous Total Ferrous
34 0.1 O
22 1 .9 O
24 3O O.2 0
4O O.I O
48 O.2 O
48 4O O.I O
01 ° o, o
28 42 O.I O
30 38 °'2 ° 0. 0
44 4O O.I 0
38 0.1 O
50 O.I 0
28 28 O.I 0
29 0.21 0.20
16 O.I9 O.O8
31 3O O.I4 O.K>
25 O.26 0.08
20 O.32 O.O3
25 29 O.34 O.I2
29 O.58 O.O3
2O O.32 O.IO
25 24 O.5O O.O2
33 0.34 O.O6
18 O.I4 O.O6
29 28 O.23 O.O6
39 O.I8 O.O2
13 O.07 O.O3
16 29.5 O.IO O.O8
0.27 —
O.IO —
O.23 —
I4O O.I6 O.O3
116 76 O.2O O.O6

3A-D
Total Ferrous
O.I O
O.I O
O.I O
O.I 0
O.I O
O.I9 0.18
O.32 O.O8
O.45 O.O8
O.2I 0.06
O.O5 O.O3
O.2I
O.O9 O.O2

-------
                                                             TROUGH  CREEK  LIMESTONE  BARRIER INSTALLATION  AND EVALUATION
ISJ



SHEET HI WATER ANALYSIS - SITE NO. 3

Sampling
Date
IO/26/72

II/3O/72


1/8/73


2/15/73


3/3O/73

4/23/73


5/IO/73

6/7/73

7/16/73

8/17/73


IO/I6/73


IO/24/73


11/23/73


Flow
(eft)
0.41
0.14
0.55
16.0
2.7
18.7
9.9

,5.8
16.3
4 1
20i4
14.3
5.2
,9.5
62.5
12.0
74.5
31.9
4.O
35.9
40.5
5.0
45.5
0.3
84
0:2
Trickle
0.2
O.5
Trickle
0.5
0.6
O.2
0.8
8.8
iai

PROJECT NO. 14010 -FWW
CR-IO5
Iron Gng/l)
DH Acidity (mq/l) Alkalinity (mg/l) S04 (mg/l) 3-U 3-T 38-0 3A-D
3-U 3-T 3B-D 3A-0 3-U 3-T 3B-D 3A-D 3-U 3-T
6.3 13 18
5.3 5 5
6.3 6.6 IO 8
5.1 IO 2
4.8 8 2
4.8 5.O 56
4.7 4 2
5.4 3 5
4.7 4.8 8 6
5.7 8 O
5.O 4 O
5.O 4.8 6 7
48 7 0
5.2 4 0
4.9 4.9 6 6
5.1 4 0
4.9 5 O
5.1 5.3 4 7
5.1 8 0
5.0 8 0
5.2 5.2 66
4.8 8 O
5.O 8 0
4.8 4.8 8 IO
4.5 10 0
4'8 5.5 4.7 8 4 ,0 °
4.8 IO O
6.2 4 O
5.4 6.3 4 6
4.8 4 0
5.6 4 O
6.2 6.8 40
5.0 8 2
45 6 2
4.7 5.2 84
44 4 O
4.2 6 O
4.9 4.2 6 6
38-D 3A-0 3-U 3-T 3B-D 3A-D Total . Ferrous Total Ferrous Total Ferrous Total Ferrous
45 0.20 O.O2
IO.5 O.O4 O.02
5 18 3L5 31 0.14 O.O2 O.IO O.O2
19.5 0.20 O.O6
IO.5 O.O9 0.02
26 22.5 195 O.I9 O.O3 O.23 O.O2
23 O.2I O.O6
12 " O.IO O.O6
2 2 2O.5 21 O.I8 O.O6 0.19 O.O8
22 0.3 CO.2
IO CO.I CO.I
O O 14 24 CO.I CO.I O.2 CO.2
15 0.2
5 O.I
0 O 15 2O 0.2 — O.I
26 0.9
IO 0.3
O O 19 22 0.9 -- O.7
19 CO.I CO.I
14 CO.I 40.1
0 O 14 17 CO.I CO.I CO.I CO.I
22 CO.I CO.I
14 
-------
                SHEET  BE     WATER  ANALYSIS   -  SITE  NO. 3
                     TROUGH   CREEK   LIMESTONE  BARRIER INSTALLATION  AND EVALUATION
                                             PROJECT  NO.  14010-FWW
                                                         CR-105
Sampling     Flow   	fH	Acidity (mg/l)	AlkoUnity (ma/1)	SCV (mg/l)	3-U
	Dot*      (ct«)   3-U  3-T 38-D  3A-D  3-U 3-T 3B-O 3A-D 3-U 3-T 3B-D  3A-D  3-U 3-T  3B-D  3A-D Tbtoi~Fei
                                                                                                                          3-T
                                                                                                                              Iron (mg/l)
                                                                                                                                       3B-0
                                                                                         "3AO
                                                                                                               Ferrous Total Ferrous  Totol Ferrous  Total Ferrous
oo
         12/19/73     16.5   4.4
                     3.0       4.5
                     19.5            4.5   4.5

         2/14/74     I as   4.7
                     5.4       4.7
                    24.9            4.7   4.8
         3/1/74     32     4.7
                     4O
                                4.5
                                    4.8    4.7
         4/11/74     I6J    4.6
                     6.1         4.6
                    22.2            4.6   4.6
         4/30/74
                           4.7
                    26.2
                               4.7
                                    4.9   4.9
         5/28/74    13.2    4.7
                     6.1        4.5
                    19.3             4.9    4.9


         6/27/74    16.5    4.8
                     65        4.5
                    23.O             4.8    4.8


         8/5/74     05    4.8
                    O.I        4.8
                    0-6             5.3    5.4
 4    4
                                                          4    2
                                                          4    2
                                                          4    2
                                                         4     2
2    2
4    6
                                                         6    6
                   O     O
                                                                            2    4
                                                                            4     2
                                                                            2    4
                                                                            4    4
                   2    4
                  4    6
                                                                           6   2O
                             26
                             14
                                                                                      23
                             25
                                                                                      21
                             25
                             22
                             53
                                  14
                                 35
                                 14
                                      23    23
                                                                                                      I I
                                                                                               19    22
                                                                                               2O    45
                                                                                               13     14
                                      12     28
                                      14    26
                                                                                              43    43
                                                 0.146
                                                 0.146
                                                              O.146  —
                                                              0.146  —
                                                                          O.I46
                                                                                                                                    0.146
                                                                                       0.146
                                                                                                                                                O.I46
                                                              O.I

-------
TROUGH  CREEK  LIMESTONE  BARRIER INSTALLATION AND EVALUATION
PROJECT NO. 14OIO-FWW
SHEET I
Sampling
W/2/7O
D/28/7O
1I/27/7O
12/30/70
2/26/71
V30/7I
4/28/71
5/28/71
7/2/71
8/5/71
8/31/71
KJ/I/7I
1 1/1/7 1
12/1/71
1/4/72
2/1/72
flow
1.2*
0.3"
5.0»
MR.
N.R.
N.R.
MR.
N.R
N.R.
N.R.
8$
3.85
O.O8
O.O3
0.11
3.68
036
4.O4
I8£
1.8
20.4
163
1.5
18.3
19.4
2.0
21.4
•a
15.8
WATER
PH
4.6
6.7
5.0
4.7
4.6
5.5
4.9
5.0
4.6
6.5
4.6
6.8
6.2
7.0
6.8
6.8
5.6
6.7
6.3
6.3
5.3
6.4
5.3
6.7
4.4
5.9
ANALYSIS - SITE NO. 4
Acidity (mg/l)
IO
O
4
2
6
O
16
4
O
2
O
6.5
8.7
0
6.4
5.7
53
6.1
4
5.0 0
Alkalinity (mg/t)
O
12
4
O
0
O
--
O
0
14
28
0
20
12
14
36
18
O
4O
12
IO
80
2O
6
18
18
4
16
40
IO
0
SO* (mg/l)
4.11 A-T 4-H
\J "T 1 ** U
56
36
—
—
22
24
36
28
22
24
28
24
44
30 30
22
22
3O
38
48
38
30
38
22
38
24
30
3O
28
4O
48
42
54
CR-105
Iron (mg/l)
4-U 4-T
Totol Ferrous T otol Ferrous
O.67
0.6
O.I
O.35
0.3
O.3 O
O.I O
O.4 0
0-1 O
0.3 0
O.I O
0.7 0
1.3 O
0.5 0
0.3 0
O.5 0
O.I O
O.I O
O.4 0
0.5 0
O.I 0
0.2 O
O.I 0
I.O O
O.I O
O.3 O

4-D
TOtQi Ferrous








4.4 O
O.I O
O.I 0
O.3 O
O.I 0
O.I 0
O.I O

-------
TROUGH  CREEK  LIMESTONE BARRIER INSTALLATION  AND EVALUATION
PROJECT WO. I40IO-FWW
SHEET H
Sampling
Date
2/28/72
3/31/72
4/25/72
5/B/72
7/5/72
00
Ul
7/24/72
8/22/72
9/26/72
W/26/72
U/3O/72
1/8/73
2/B/73
Flow
(efsl
39.1
£?
55 JO
22.6
3.2
25.8
39.4
£3
o2?
3j6
05
O.5
I.O
OJ6
O.07
O.23
O.57
O.45
1.02
372
42.9
20JO
2.5
225
281
5.7
33.8
WATER ANALYSIS - SITE NO. 4

4-U
4.9
4.7
4.O
4.7
5.6
7.3
7.3
5.9
6.8
43
5.5
4.8
pH Acidity (mg/l) Alkalinity (m)/\)
4-T 4-D 4-U 4-T 4-D 4-U 4-T 4-D
24
62 — 58
5.6 — 32
O.9 I.O
7.1 4 12
5.1 7 1
6.2 " 8 ° 7
45 9 O
1
50 -- 3
5.7 — 6
7
7.1 7
6.5 7
53 5 K) ""
65 4
5 8
6.O 9 25
7.4 5 18
32 II
6JO 16 27
7.1 8 33
63 * O 20
68 O 10
6 2
7.4 O 17
7.1 5 8
4 5
65 0 12
53 0 9
9 O
66 O 1
5.6 3 O
CR-105
S04 (mg/l) 4-U
4-U 4-T 4-D Total Ferrous
3O O.I O
24
24
27 0.19 O.I
20
30
21 ^ 0.33 O.O3
23
17 O.3O O.O6
21
2O
28 O.I4 O.O3
18
26
IL5 O.4I OXD3
235
19.3
O.I2
31 O.I6 O.O6
IL5
23
26 O.IO O.O2
12.5
22
165 O.I8 O.O3
8
14
19.3 O.09 O.O6
12.5
18
17 O.I 3
0.20 0-O6
O.27
0.23 O.IO
0.20 O.O3
O.I2 O.O3
O.I9 O.IO
O.2 <0.2

-------
                                                              TROUGH  CREEK LIMESTONE  BARRIER INSTALLATION AND  EVALUATION
00
SHEET ffl
Sampling
Date
3/3O/73
4/23/73
5/IO/73
6/7/73
7/16/73
8/17/73
10/16/73
O/24/73
M/23/73
12/19/73
2/14/74
3/1/74
Flow
fcfs)
23.O
88.8
10.2
99.O
42.2
2.5
44.7
80.7
3.3
84.0
1.6
0.2
1.8
0:2
8;3
Ol7
8:?
0.7
9JO
I.I
10.1
4l'.0
315
44 .0
6.0
5O.O
! WATER

4-U
5.0
5.6
5.6
5.O
6.4
6.9
&3
5.1
4.4
4.7
5.2
5.1
PH
4-f
6.8
6.3
6.7
6.8
6.5
6.8
6.9
6.1
5.6
5.6
5.8
5.6
ANALYSIS -
Acidily
SITE NO.
(mo/I)
4-D 4-U 4-T 4-D
6
O
6.6
3 o
6.O
4
0
6.0
8 o
6.0
0
0
6.2
O
O
6.6
° 0
6.8
4
6
5.9
6
2
5.2
2
4
5.2
4
5.3
2
5.5
1
2
4
6
O
O
O
4
6
2
4
4
4

Alkalinity
4-U
0
0
0
0
4
18
12
4
0
2
6
6
lmg/1)
4-T 4-D
6
2
10
6
10
24
26
20
4
8
14
14
O
0
O
0
2
16
26
6
2
2
6
8
PROJECT NO. 14010 -FWW
CR-105
Iron (mg/l)
SO* (mg/l) 4-U 4-T . 4-D
4-U 4-T 4-D Total Ferrous Total Ferrous Total Ferrous
2O O.I —
3 O.4
10 O.2
26 6.4
10 15
12 6.5
19 
-------
                                                             TROUGH  CREEK  LIMESTONE  BARRIER INSTALLATION  AND EVALUATION
00


SHEET IZ WATER

Sampling
Dote
4/11/74


4/3O/74


5/28/74


6/27/74


8/5/74



Row DH
fcfs) 4-U 4-T
203 StS
3.2 5.8
24.O
26.2 5.7
3.8 6.0
SOX)
20.5 5.7
2.5 5.5
23.O
25.0 5.4
3.O 5.2
28.0
O.8 6.1
O.I 63
O.9
PROJECT NO. I40IO-FWW
ANALYSIS - SITE NO. 4 CR-105
Iron (ma/I)
Acidity (ma /I) Alkalinity (ma/I) SO* (ma/1) 4-U 4-T 4-D
4-D 4-U 4-T 4-D 4-U 4-T 4-D 4-U 4-T 4-D Total Ferrous Total Ferrous Total Ferrous
2 6 3O O —
4 20 30 O —
55 2 6 4O O
4 6 17 0 —
4 24 6 O —
5.6 6 10 16 O
2 IO 18 O
2 22 8 0
5.1 4 6 19 O —
4 6 17 0
8 2O 8 0.4
5O 4 IO 12 O
4 20 16 O
4 22 9 O.I
5.9 8 16 24 O —

-------
                                                                             TROUGH CREEK LIMESTONE BARRIER INSTALLATION AND EVALUATION
00
00
SHEET I WATER ANALYSIS - SITE NO. 5
Sampling
Date
10/2/70
12/30/70
lt/28/Tl
5/28/71
7/2/71
8/5/71
8/31/71
10/1/71
11A/71
12A/71
l/It/72
2A/72
2/28/72
3/31/72
It/25/72
5A8/72
7/5/72
7/2U/72
8/22/72
Flow
(cfs)
0.2*
N.R.
N.R.
0.2
0.2
0.15
0.12
0.28
0.2
0.3
O.li
O.li
Site
0.5
0.96
1.0
1.15
o.5
0.6
PROJECT NO. 11,010 - FWW
Acidity Alkalinity
PH (mR/l) T^TTT SOU (mRA)
5-U 5-D 5-U
3.1 600
2.9 180
3.0 200
5.7
5.5
6.2
U.3
3.U
3.U
3.6
3.1
2.5
not accessible - Snow
3.0
3.6
3.6
lt.2
3.5
U.2
5-D 5-U
0
0
0
—
0
—
61t
96
108
80
5k
130

151
97
71*
97
93
95
5-D 5-U 5-D
750
Uoo
350
6 310
0 320
2k 310
270
320
320
220
It25
300

0 210
0 310
2k6
21,6
208
0
eft- 105
Iron (rag A)
5-U 5-D
Total Ferrous Total
lit
37.5
20 8
O.li5
O.li
1.8
2.9
2.8
15.5
3.8
2
2.9

2.88
U.80
2.30
3.81,
3.96
676

Ferrous



0
0
0
0
0.3
1.3
0.2
0.1
0.6

0.98
0.20
0.27
0.12
0.12
..

-------
                                                                                TROUGH CREEK LIMESTONE BARRIES INSTALLATION AlID EVALUATION
(Con't) SHEET II
Sampling
Date
9/26/72
10/26/72
11/30/72
1/8/73
2/15/73
Flow
(cfs)
0.2
0.16
0.53
0.30
Samples
WATER ANALTEIS

pH
5-U 5-D
3.8
3.9
3.3
3.0
Not Collected -
- SITE NO. 5

Acidity AlkaHMty
(mg/1) (mg/1) h (n
5-U 5-D 5-U 5-D 5-U
79
70 30-
190
1UO
Site Not Accessible
PROJECT NO. 1U010 - fWW
CR-105
Iron (m|
iR/1) 5-U
5-D Total Ferrous
290
220
220
180


zA)
5-D
Total
13.0
22.0
10.6
3.6



Ferrous
0.2k
0.18
0.22
0.2J,

00

-------
                                                                             TROUGH CREEK LIMESTONE BARRIER INSTALLATION AND EVALUATION
vO
o
SHEET I
Sampling
Date
10/2/70
10/28/70
11/27/70
12/30/70
1/26/71
2/26/71
5/28/71
7/2/71
8/5/71
6/31/71
10A/71
11/1/71
12A/71
l/U/72
2/1/72
2/28/72
3/31/72
U/25/72
5A8A2
WATER ANALYSIS - SITE NO
Flow
(cfs)
2.5*
N.R.
N.R.
N.R.
N.R.
N.R.
N.R.
N.R.
N.R.
1.05
6.65
N.R.
50.3
33.3
17.3
71.0
18.3
65.0
3U.O

6-U 6-D
U.7
U.9
U.7
U.3
U.6
U.8
5.7
6.U
6.3
6.1
5.5
5.8
5.9 6.0
6.0 6.0
5.0 5.2
5.3 5.U
U.9 5.o
U.6 U.6
5.7 6.U
. 6
Acidity
6-U 6-D
1U
U
2
6
0
2
—
—
—
6
0
—
—
..
2
__
7 1U
7 8
U 2
PROJECT NO. IU.010 - PVW

(roe A)
6-U 6-D

6
0
0
0
0
U
6
6
—
0
10
18 10
U 6
8
1U 20
1 2
1 1
__ __
s^u (mgA)
6-U 6-D
58
~
--
28
2U
28
32
Uo
U2
95
Uo
22
UO 2U
22 2U
UO 28
38 UU
23 31
23 25
21 16
CR-105
Iron (mgA)
6-U
Total
0.1
0.1
0.5
1.9
1.1
0.65
o.U
0.8
o.U
0.7
0.1
1.0
0.3
0.1
0.1
0.1
0.2U
0.29
0.69

Ferrous





0
0
0
0
0
0
0
0
0
0
0
0.1
0.03
0,65
6-D
Total Ferrous












0.5 0
0.1 0
0.3 0
0.1 0
0.19 0.18
0.21 0.02
O.Ul 0.12

-------
TROUGH CREEK LIMESTONE BARRIER INSTALLATION  AMP EVALUATION
(Con't)
Sampling
Date
7/5/72
7/2lo/72
8/22/72
9/26/72
10/26/72
11/30/72
1/8/73
2/15/73
3/30/73
1./23/73
f/10/73
6/?/?J
7A6/73
8A7/73
30A6/73
10/2it/73
11/23/73
12A9/73
SHEET n
Flow
(cfs)
108
5.3
2.0
o.5
2.1
62.5
1|5.0
51.6
35.5
206
62.0
95
2.8
0.5
2.3
1.5
n.5
65.0
WATER ANALYSIS
pH
6-U
5.7
6.6
6.0
5.7
6.0
5.o
5.5
5.2
5.7
5.5
5.9
5-5
5.9
6.1,
5.3
5.1t
5.1
U.8
6-D
6.2
6.8
7.5
6.8
6.2
U.7
5.7
5.2
6.h
5.5
5.9
5.fc
6.1
6.8
5.9
5.1
5.1
h.9
- SITE NO. 6
Acidity
(ME/I)
'6-U
6
6
13
23
If
5
10
7
It
2,
6
Uf
It
2
1»
8
8
It
6-D
7
7
7
8
1
U
It
U
2
6
k
it
0
0
2
6
U
2
Alkalinity
6-U
—
—
7
7
6
5
2
0
0
0
0
0
0
0
0
14
2
2
6-D
—
—
11
17
13
1
ii
0
0
0
0
0
0
0
0
It
2
2
S% (*/
6-U
30
25.5
—
U8
25.5
16
19
17
12
17
111
2k
29
2U
72
U5
27
23
PHOJECT MO,
. ll<010 - P/JW

CR-105
Iron (mp;/3)
T/I) 6-U 6-D
6-D
2?
27
—
514
25.5
16.5
20
lit
12
17
17
22
38 •
38
67
ItO
29
18
Total
0.63
O.Z?
0.23
O.ltl
c.U
0.29
0.29
0.3
0.2
0.5
0.2
0.1
<0.1
0.-2
0.1
0.
0
0.11*6
Ferrous Total
0.03 0.50
0.03 0.33
0.29
0.12 0.36
O.C2 1.06
0.02 0.29
0.10 0.33
<0.2 0.3
	 0.2
	 1.2
0.2 <0.2
<0.1 <0.1
- - <0.1
	 0.3
-- 
-------
                                                                              TROUGH CREEK LIMESTONE BARRIER INSTALLATION AND EVALUATION
(Con't) SHEET III
Sampling Plow
Date (of a)
2/lli/7lt
3A/7lt
UA1/7U
V30/7U
5/28/7lt
6/27/7U
8/5/74
U5.5
65
33
38
tt6
ItO
1.3
HATER ANALYSIS •
pH
6-TJ
5.2
5.U
5.5
5.5
5.U
5.3
5.0
6-D
5.2
5.1t
5.6
5.6
5.6
5.3
5.8
- SITE NO. 6
AcidjLty
6-U
2
2
It
It
It
It
4
6-D
U
2
1*
It
2
8
6
Alkalinity
(n

It
It
It
6
It
It
4
ig/lj
6-D
U
6
6
It
6
It
10
SO
S-U
16
17
35
22
23
23
43
HtOJECT NO. U010 - FWW
>KA)
6-D
lit
17
30
26
25
27
43
CR-105
Iron (mf»A)
6-U
Total Ferrous
0.1^6 	
0 	
0 	
0
0 	
0
0 	
6-D
Total
0
0
0
0
0
0
0.2
Ferrous
	

	
	
	

_ —
VO
ro

-------
                                    TECHNICAL REPORT DATA
                            (Please read Instructions on the reverse before completing)
 1. REPORT NO.
    EPA-600/2-76-114
               3. RECIPIENT'S ACCESSION-NO.
 4. TITLE AND SUBTITLE

   TROUGH CREEK LIMESTONE BARRIER
   INSTALLATION AND EVALUATION
               5. REPORT DATE
                  May  1976  (Issuing Date)
               6. PERFORMING ORGANIZATION CODE
 7. AUTHOR(S)

    S.  Curtis Yocum
               8. PERFORMING ORGANIZATION REPORT NO

                     CR-105
 9. PERFORMING ORGANIZATION NAME AND ADDRESS
   Africa Engineering Associates,  Inc.
   109  Fourth Street
   Huntingdon,  Pa.  16652
               10. PROGRAM ELEMENT NO.

                  1BB040.  05-03-0LA-01
               11. CONTRACT/GRANT NO.

                  14010  FWW
 12. SPONSORING AGENCY NAME AND ADDRESS
    Industrial Environmental  Research Laboratory
    Office of Research and Development
    U.S.  Environmental Protection  Agency
    Cincinnati, Ohio  45268	
               13. TYPE OF REPORT AND PERIOD COVERED
                  Final  Report.  6/70-2/75
               14. SPONSORING AGENCY CODE
                   EPA-ORD   •
 15. SUPPLEMENTARY NOTES
 16. ABSTRACT                	
    Six  prototype crushed limestone barrier installations  were constructed in  Trough
    Creek in South Central Pennsylvania to demonstrate  the neutralizing ability  of
    this type structure in low-iron acidic streams.

    Limestone barrier performance was excellent during  periods of low streamflow,  in
    terms of reducing acidity  and raising the pH of  the water, but their effectiveness
    was  marginal at design or  average streamflow, and they were ineffective when high
    runoffs  were experienced.   Limestone barrier performance deteriorates after  the
    structures are initially constructed and placed  in  operation, because progressive
    accumulations of sediment  clog interstices between  the stones, which lessens the
    hydraulic conductivity of  the barriers, and surfaces of the stones become  coated
    with silt, which causes a  reduction in reactivity of the reagent (limestone) with
    flowing  acidic water.  The design of limestone barriers should take these  factors
    into account, and the units should be sized sufficiently large to overcome this
    deficiency.

    Silted limestone barriers  can be restored to porous filtering beds, approximately
    equal in performance to initial efficiency, by washing and rehandling the  crushed
    limestone materials.
 7.
                                KEY WORDS AND DOCUMENT ANALYSIS
                  DESCRIPTORS
  b.lDENTIFIERS/OPEN ENDED TERMS  C.  COS AT I Field/Group
   *Limestone
   *Neutralizing
    Water  pollution
    Mines  (excavations)
 fcAcid mine  drainage
  Water pollution treatment
  Pennsylvania
  Trough  Creek
  Limestone  barriers
    08/H
    13/B
    13/M
 8. DISTRIBUTION STATEMENT

    RELEASE TO PUBLIC
  19. SECURITY CLASS (This Report)
      UNCLASSIFIED
21. NO. OF PAGES
    101
  20. SECURITY CLASS (Thispage)
      UNCLASSIFIED
22. PRICE
EPA Form 2220-1 (9-73)
93
                                                   U.S. GOVERNMENT PRINTING OFFICE: 1976-657-695/5*23 Region No. 5-11

-------