TECHNICAL ASSISTANCE PROJECT
 GREELEY WASTEWATER TREATMENT FACILITY
         GREELEY, COLORADO

           JUNE - JULY, 1972
U. S. ENVIRONMENTAL PROTECTION AGENCY
   SURVEILLANCE AND ANALYSIS DIVISION
      TECHNICAL SUPPORT BRANCH
             REGION VIII
            AUGUST 1972

-------
                                           S&A/TSB-4
    TECHNICAL ASSISTANCE PROJECT

GREELEY WASTEWATER TREATMENT FACILITY

          GREELEY, COLORADO

          June - July, 1972
      TECHNICAL SUPPORT BRANCH
  SURVEILLANCE AND ANALYSIS DIVISION

U. S. ENVIRONMENTAL PROTECTION AGENCY
            REGION VIII

            August 1972

-------
                         TABLE OF CONTENTS

                         Section                        Page No.
  I.   Introduction 	   1
 II.   Purpose and Scope	   1
III.   Description of Plant 	   1
 IV.   Summary of Assistance Project  	   4
      A.   Control Testing  	   4
      B.   Process Modifications  	   5
      C.   Performance Results  	   8
  V.   Summary and Conclusions	13
 VI.   Recommendations	14

-------
                             LIST OF FIGURES
                             Figure                         Page No

1.  Plant Flow Schematic	    3
2.  North Plant Performance (% Reduction of 6005 vs Time). .    9
3.  Total Plant Performance (% Reduction of BOD5 vs Time). .   10
4.  Total Plant Performance (Effluent BOD5 - mg/1 vs Time) .   11
5.  Total Plant Performance (Effluent 6005 - Ibs. vs Time) .   12
                                   ii

-------
  I.   Introduction

           The  Greeley Wastewater Treatment  Facility  has  continually
      experienced difficulties  in achieving  the  desired degree  of  treat-
      ment to meet  the State's  requirement of  80 percent  reduction of
      biochemical oxygen  demand - 5  day  (BODc).   The  plant's  main  problem
      is  organic  overload.   Despite  the  overload, modifications in the
      plant's facilities  and in operational  modes have allowed  an  increase
      in  the percentage removal  of 6005  from 40  percent in  April of 1971
      to  the 70 percent range in April of 1972.   Engineers  from the Colo-
      rado State  Department of  Health  and the  Superintendent  of the Greeley
      plant were  responsible for developing  the  necessary modifications  to
      improve the plant's performance.

           In an  effort to further improve the plant's performance, the
      Superintendent of the Greeley  facility requested assistance  from
      the U. S. Environmental  Protection Agency  - Region  VIII.   An assis-
      tance project was initiated at the Greeley plant on June  5,  1972.
      This report summarizes the findings of that project.


 II.   Purpose and Scope

           Plans  have been developed to  provide  for new treatment  facilities
      at  Greeley  to alleviate the organic overload that exists  at  the present
      plant. These facilities  are scheduled for completion in  March  1973.
      Since future  improvements have already been planned,  the  emphasis  of
      this report does not deal  with present plant limitations  and future
      expansions.  Only those portions of the  existing facility that  will
      be  used in  the future are discussed and  modifications that could  aid
      plant performance outlined. The main  purpose of this report is to
      document  the  results achieved  in improving plant performance by im-
      proved operation during the Federal Technical Assistance  Project.


III.   Description of Plant

           Presently the  Greeley wastewater  treatment plant treats the  waste
      from the  City of Greeley  plus  the  wastes from a large packinghouse
      (Monfort  Packing Company).  The  present  facilities  consist of a trick-
      ling filter plant (South  Plant)  constructed in  1955 and an activated
      sludge plant  (North Plant) constructed in  1965.  In the past the
      trickling filter plant was used  to treat the industrial waste and  the
      activated sludge system was used to treat  the domestic  waste.  Odor
      problems  and  mechanical  problems forced  the shut down of  the trick-
      ling filter facility.  During  this time  an attempt  was  made  to  treat
      all the wastes in the activated  sludge plant.   The  gross  overload  on
      the activated sludge system reduced the  plant's efficiency,  resulting
      in  a very poor quality effluent.   New  facilities were planned to  de-
      crease the  load on  the activated sludge  system.  Since  these new
      facilities  were not scheduled  for  completion until  March  1973,  efforts
      to  improve  the effluent quality from the Greeley plant  became necessary.

                                      1

-------
The old trickling filter plant was modified and made operable to
serve as a pre-treatment system for the packinghouse wastes.   The
filters were placed back in operation in December 1971.   The  pre-
treated waste from the trickling filter plant was then mixed  with
the incoming domestic waste and treated in the activated sludge
system.  Pre-treatment of the packinghouse waste on the trickling
filters greatly reduced the organic load on the activated sludge
plant.

     Figure 1 shows the various units at the Greeley facility.  The
activated sludge plant is located on the north side of the receiving
stream (the Cache La Poudre River) and the trickling filter plant is
located on the south side of the river.  Sludge handling facilities
(anaerobic digesters) are located on the south side of the river.
All waste initially enters the plant on the south.  Waste that has
been pumped to the north side of the river for treatment in the
activated sludge plant flows under the river to the south side for
disinfection in the chlorine contact tanks prior to discharge.

     Future plans call for the construction of an anaerobic,  aerobic,
facultative lagoon system to be built to treat the packinghouse waste
and the waste activated sludge.  Domestic waste will continue to be
treated in the activated sludge plant.  The trickling filter plant
and its appurtenances are scheduled to be abandoned.

     Emphasis during the technical assistance project was placed on
the operation of the activated sludge facility.  Therefore, units
and operational controls for this portion of the facility will be
described in more detail.

     Incoming raw sewage and industrial waste which has been
pretreated on the trickling filters are pumped to a splitter box
on the north side of the river.  Sewage flows by gravity from the
splitter box to the two primary clarifiers.  Each primary clarifier
has a central sludge thickening compartment.  Prior to assistance,
sludge at times became too thick to pump from the primary clari-
fiers.  Two 75 gpm piston pumps remove the sludge from the primary
clarifiers and pump it to the anaerobic digesters on the south side
of the river.  Effluent from the primary clarifiers flows to a
channel located between the two aeration basins.  Gates along the
channel allow settled sewage to be applied at three locations along
each aeration basin.  Prior to the assistance project all sewage was
applied through the gate at the head end of each aeration basin.
Mixed liquor from each basin flows to two final clarifiers.  Clarified
effluent is transported under the river to the chlorine contact basin
on the south side and then is discharged to the Cache La Poudre River.

     Return sludge is removed from the final clarifiers by suction
type scraper arms and pumped by two centrifugal pumps through a
common header back to the aeration basins.  Return sludge can be
added to the aeration basins at three separate locations along each

-------
ACTIVATED SLUDGE PLANT
       Secondary  1Clarifiers
Aeration
 Tanks
                         Activated
                         Sludge Control
                             Building
          SplitterA
            Box    «-
                                                           TRICKLING  FILTER PLANT
                                                           Chlorine Contact Chamber
                                                                                            Trickling
                                                                                             Filters
                                                                                                       FIGURE 1
                                                                                                 FEDERAL ASSISTANCE RKXJECT
                                                                                              Bumpy VfeSTBWTER TREATm«T FACILITY
                                                                                                   Jue 1372 TO JULY ]972

                                                                                                   PLANT FLOW SOCWTIC
                                                                                                        Sludge Drying
                                                                                                            Beds
                                                                                                         North
                                                    Domestic  Waste
                                                            -.      ,, ,,.».      (    primary
                                                              \^J Clarifier  V^./Clarifier

                                                            Grit Chamber   .S
                                                                         rCComminutor


                                                                   Industrial Waste

-------
     tank.   Sludge  is wasted  from  the  system by  partially  closing  the  valves
     along  the  return sludge  header, and  thus  forcing  the  return sludge  up
     to  the splitter box where  the wasted sludge is  diverted  to the  primary
     clarifiers.  Measurement of waste sludge  flow  is  accomplished by  the
     use of v-notch  weirs.  Return sludge flow is measured by an in-line
     propeller  type  meter,  accurate to 100 gpm.   Return  sludge flow  rates
     are adjusted by opening  or closing a butterfly  valve.  Gate valves  are
     used to control the distribution  of  return  sludge to  each aeration  basin.

          The activated sludge  portion of the  plant  was  designed to  achieve
     80% removal at  aeration  basin loadings of 78 Ibs. of  8005 per 1000
     cubic  feet (13,200 Ibs.  8005  /day).   Present loadings on the  aeration
     portion of the  activated sludge plant are approximately  110 Ibs.  8005
     per 1000 cubic  feet of aeration basin volume (18,500  Ibs. BOD5/day)
     or  about 140 percent  above design.   Present flows to  the activated
     sludge portion  of  the  plant are less than the  average design  flow
     rate of 7  mgd.


IV.   Summary of Assistance  Project

          Little could  be  done  to  improve the  performance  of  the pretreatment
     trickling  filters  due  to the  limited recirculation  capabilities.  There-
     fore,  the  major emphasis of the technical assistance  project  was  the
     operation  and  control  of the  activated sludge  portion of the  plant.

     A.    Control Testing

             The superintendent of the Greeley facility  had initiated  a
          program of control  testing.   These tests were  modified slightly
          and used  to control the  plant's performance.   The control  tests
          used  were  dissolved oxygen tests, centrifuge tests, turbidity,
          settleability tests,  and sludge blanket depths.   These tests
          were  conducted five times a  day by plant  personnel.

             A  dissolved oxygen meter  was used to measure  the oxygen
          concentrations of the mixed  liquor in  the  aeration  basins. Since
          the plant  is  organically overloaded, the  determination of  dissolved
          oxygen was necessary  to  indicate those conditions which  depleted
          the availability  of oxygen.

             Centrifuge testing was used  to determine  rapidly the  variations
          in solids  concentrations throughout  the day, as  well as  day  to day.
          Tests were conducted  on  the  mixed liquor,  return sludge, and
          primary sludge.   The  centrifuge tests  resulted in a percent  solids
          determination.   A correlation between  percent  solids by  centrifuge
          and solids by weight  was determined.  The  results of this  corre-
          lation indicate  that  one percent solids from the centrifuge  test

-------
     on mixed liquor and return sludge was equivalent to 660 mg/1
     solids by weight.   This factor will  change as the sludge
     characteristics change.

        Turbidity tests were conducted on the effluent from the
     final clarifiers to monitor improvements in performance prior
     to obtaining a BOD5 test result.

        Settleability tests were conducted on the mixed liquor to
     monitor and observe sludge settling characteristics.

        Sludge blanket depth determinations were made on the final
     clarifiers to monitor changes in  the depth of the blanket.
     Depth determinations were also made on the sludge in the pri-
     mary clarifiers.

        Results of these tests were used to perform daily calculations
     and to develop graphs that are used to control the activated sludge
     process.

B.   Process Modifications

        Various changes were made in the operational mode of the
     activated sludge portion of the Greeley facility.

        Conditions as they existed prior to Federal assistance are
     outlined below:

        All sewage was  loaded at the head of each aeration basin.
     Return sludge was  pumped to the head end port and the center
     port along each aeration basin.  Rates for returning sludge
     were set at twenty-five percent of the incoming flow.  A
     minimum of 500 gpm per pump or 1000 gpm return sludge rate had
     been established.

        Mixed liquor concentrations were built from 300 to 500 mg/1
     on Monday to 900-1000 mg/1 on Friday.  Mixed liquor concentra-
     tions were dropping dramatically  over the weekend when the waste
     from the packinghouse decreased.

        Activated sludge was being wasted to the primary clarifiers
     only on Wednesday, Thursday and Friday.  Mixed liquor was re-
     turned to the splitter box which  directs the flow to the pri-
     maries to effect the removal of solids.  No controlled  wasting
     was performed on the weekend or on Monday or Tuesday.

        Modifications that were made to the above operational mode
     are outlined below:

-------
   Incoming sewage was "step" loaded to the aeration basins,
i.e., the sewage was loaded through each of the three gates
along the aeration basin.  This modification was made because
of the excessive organic load on the plant.  The organic over-
load requires an amount of oxygen greater than the plant was
designed to provide.  Step loading equalizes the demand for
oxygen throughout the aeration basin, thus optimizing the use
of oxygen.  Oxygen profiles were conducted along the side of
the aeration basin to determine the optimum gate settings.
For example, higher dissolved oxygen values in a portion of
the aeration basins indicated that more of the incoming sewage
load should be applied to that section.

   At the start of the project, it was decided to try and
build the mixed liquor solids concentration to a maximum
value.  It was felt that increased solids could better handle
the organic overload.  As the solids concentration was increased,
the effluent clarity from the final clarifiers increased.  How-
ever the effluent quality as measured by the suspended solids
concentration from the chlorine contact tank decreased.  It was
determined that a cross-connection existed between the plant
effluent and mixed liquor from the aeration basins.  A partially
closed valve was discovered to be the source of the cross-
connection.  This leaky valve explains  why the plant personnel
had been unable to maintain a solids concentration over the
weekends when the packinghouse waste was eliminated.  After this
valve was shut completely off, solids built rapidly in the system.
It was felt that dissolved oxygen would be the critical factor
controlling the amount of solids that could be maintained.   How-
ever, bulking of solids from the final clarifiers proved to be
the most critical factor.

   Solids were wasted from the system by partially closing the
valves which controlled the distribution of return sludge to the
aeration basins.  Flow adjustment of the desired quantity of
waste sludge was relatively easy to accomplish by measuring the
head on V-notch weirs.  But, adjustment of the partially closed
return sludge valves to obtain an even distribution of solids
to each aeration basin was difficult to accomplish.  Flow dis-
tribution of the return sludge to the aeration basins had to be
"eye-balled" and then one-half hour after a setting was made,
samples had to be collected from each aeration basin and percent
concentration by centrifuge had to be determined to find if a
solids imbalance due to return sludge flow differences had
occurred.  Each time the return flow rates were readjusted, the
waste sludge flow rate changed due to the common header.  Also,
each time return flow rates were increased or decreased, the
head on the gate valves changed, thus requiring a readjustment
of the flow distribution between the two aeration basins.  To

-------
correct these difficulties would require flow measuring devices
(i.e., weir boxes) on the discharge return sludge ports.  It would
also be more desireable to have a separate line for sludge wasting
which would eliminate the difficulties with a common header.

   Return sludge rates were increased during the assistance project
from the rate of twenty-five percent of the incoming flow to selected
arbitrary rates.  Rates were adjusted to the maximum return flows
possible throughout most of the day.  These rates were reduced at
night and increased in increments in the morning as the flow increased.

   During the initial portions of the assistance project and after
the cross-connection was discovered, sludge was wasted to keep the
final clarifiers from bulking solids.  This required wasting rates
of 500 to 700 gpm during the week when the packinghouse was in oper-
ation.  Wasting at these rates pinpointed the bottleneck in the
plant's capabilities.  Waste activated sludge was pumped to the
primary clarifiers which are equipped with central sludge thickening
compartments.  The sludge is then pumped, at a maximum rate of 150
gpm, to the anaerobic digesters on the south side of the river.
The sludge produced by a high rate activated sludge process (i.e.,
110 Ibs. BODc per 1000 cubic ft.) generally does not settle or
concentrate well.  It was quickly determined that the sludge
thickeners could not cause thickening of the 500 to 700 gpm of
waste sludge to a degree that all solids could be removed by the
available 150 gpm sludge pumps.  Therefore, the primary clarifiers
filled with solids and effluent suspended solids from the primary
clarifiers increased from less than 100 mg/1 to greater than 300
mg/1.  These septic solids placed an extreme overload on the aera-
tion portion of the activated sludge system.  It is doubtful that
the anaerobic digesters which are already overloaded could have
handled the solids that were wasted even if they could have been
removed from the primary clarifiers.

   After the limitation on sludge pumping and thus wasting of
activated sludge was determined, an effort was made to develop
a satisfactory operational mode.  It was decided to continue
to operate the aeration portion of the system to get optimum
solids production, since a large portion of the BODs in the
waste is used in assimulative and endogenous respiration during
cell growth.  Wasting to the primaries was then optimized by
monitoring the sludge blanket in the primary clarifiers. Wasting
was continued until the primary clarifier blankets began to
increase to the point that "bulking" of solids from the primaries
would occur.  In this manner, all the solids that could be
handled by the system were removed.  Also, all the 8005 that
could be utilized in solids production was removed.  Those solids

-------
    that could not be removed by the system were lost in the  effluent.
    This mode of operation provided the maximum degree of treatment
    from a grossly overloaded plant.

C.  Performance Results

       The performance of the North (activated sludge) plant  is
    depicted in Figure 2 by the plot of percentage reduction  of
    BOD5 versus time.  Prior to assistance the 7-day moving average
    indicates that the percent reduction of 8005 was approximately
    65 percent.  After assistance the percent reduction of BODg was
    between 80 and 90 percent.  The fluctuation in the percentage
    reduction of BOD^ after assistance reflects the somewhat  spor-
    adic loss of solids that occurs.   As outlined previously, the
    system cannot handle all of the solids and therefore some
    solids must be lost in the effluent.  It is important to  note
    that the efficiency of removal  from the North plant is calculated
    on the load to that facility.  In-plant loads (i.e., digester
    supernatant) are discharged to the North Plant.  Therefore, it
    is possible for the North plant to have an efficiency equal to
    or greater than the total plant efficiency.

       Figure 3 shows the total plant performance for percent
    reduction of BODg.  A gradual increase in percent reduction
    was occuring prior to the start of the Federal Assistance
    project.  This increase reflects the improvement in performance
    of the trickling filter with the warmer summer temperatures.
    After the start of the Federal  Assistance project, percentages
    of BODg reduction, as indicated by the seven day moving average,
    increased from the 70 percent range to the 80 and 90 percent
    range.  Again the sporadic loss of solids from the activated
    sludge plant prevents the development of a consistent removal
    pattern.

       Figure 4 depicts the improvement in plant performance  as
    measured by effluent BODg concentration.  The decline in
    effluent concentration prior to assistance is due to the  increased
    performance of the trickling filters.  The effluent BODc, as
    indicated by the seven day moving average, had decreased  to
    approximately 105 to 110 mg/1 prior to assistance.  After assistance
    the 7-day average effluent BODs concentration ranged from 28 to
    90 mg/1 with an average of about 60 mg/1.  Thus, after Federal
    Assistance was initiated, the effluent 6005 concentration was
    reduced by at least 15 mg/1 and as much as 82 mg/1 with an
    average reduction of about 45 mg/1.

       Figure 5 shows the pounds of BODg in the effluent versus time.
    Again the decline of BODg in the effluent prior to assistance is
    due to the increased performance of the trickling filters.  The
                                8

-------
                                                                                7-Day Moving Avg.
                                                                                        Daily Values
                                                                                                                            FEDERAL ASSISTANCE REJECT
                                                                                                                        GREELEY WASTEWTER TREATMENT FACILITY
                                                                                                                              JUNE 1972 TO JULY 1972
                                                                                                                             NORTH Piwr PERFORWNCE
                                                                                                                             PERCENT REDUCTION OF BOifc
50
                                                                          TIME

-------
                                                                        Daily  Values
                                                           »•	7-Day
                                                         % Moving Average
                                                                                                                         FEDERAL ASSISTANCE PROJECT
                                                                                                                     GREELEY WASTEWATER TREATMENT FACILITY
                                                                                                                           JUNE 1372 TO JULY 1972
                                                                                                                           TOTAL PLANT PERFORMANCE
                                                                                                                          PERCENT REDUCTION OF BOD5
                                                                                                                                   vs
                                                                                                                                  Tin-
50
    5/15
20

-------
  200
  160
CH20
 UN
Q
O
CD
   80
                                                                                                                         FIGURED

                                                                                                                  FEDERAL ASSISTANCE PROJECT
                                                                                                              GREELEY WASTEWATER TREAirtNT FACILITY
                                                                                                                   JUNE 1972 TO JULY 1972
                                                                                                                   TOTAL PLANT PERFORMANCE
                                                                                                                    EFFLUENT BODc (MG/L)
                                    7 Day Moving Average
                                          Daily value
         5/15     20
25
30
6/5
10
 15

TIME
20
25
30
7/5
                                                                                                                                      10
                                                                                                                     15

-------
   10
CO

-------
         BOD5 in the effluent, as indicated by the seven day moving
         average, had decreased to between 5000 and 6000 Ibs./day
         prior to assistance.   After assistance the seven day moving
         average indicates a BODg load in the effluent that is quite
         variable, but less than the effluent BOD5 load before assis-
         tance.   Data for the time period represented in Figure 5 was
         grouped and averaged.  Prior to assistance, the average BOD5
         load discharged to the river was 6500 Ibs./day.  After assis-
         tance the average BODs load discharged to the river was 3500
         Ibs./day which represents a decrease of 3000 Ibs.  of BODg per
         day (population equivalent of about 15,000 people) discharged
         to the Cache La Poudre River.

            The results outlined above indicate a definite improvement
         in performance of the Greeley facility.  The majority of this
         improvement is due to the discovery of a partially opened
         valve which provided a cross-connection between the mixed
         liquor and the final  effluent.   Also, change of the operational
         mode caused an improvement in effluent quality as measured by
         BODs.  Consistent effluent quality will be difficult to achieve
         at the Greeley plant due to the organic overload received at
         the plant and the plant's inability to handle sludge solids
         which causes sludge bulking.


V.  Summary and Conclusions

         Modifications to the Greeley Facility have allowed an increase
    in the percentage removals of BOD5 from 40 percent in April of 1971
    to the 70 percent range in April of 1972.  Engineers from the Colo-
    rado State Department of Health and the Superintendent of the Greeley
    plant were responsible for developing the necessary modifications to
    improve the plant's performance.  At the request of the plant Super-
    intendent, assistance was provided by the U. S. Environmental Protection
    Agency.  Percentage removals were increased to the 80 percent range
    during the course of this assistance.  During certain periods, 7-day
    average removal efficiencies were in the 90 percent range.  As a
    result of the improved efficiencies a reduction about 3000 Ibs. of
    BOD  per day has been removed from Greeley's effluent.

         The majority of the improvement at the Greeley plant was due to
    the discovery of a partially opened valve which provided a cross-
    connection between the mixed liquor from the activated sludge plant
    and the final effluent.  An improved operational mode for the
    activated sludge portion of the plant also resulted in improved
    effluent quality.  Consistent effluent quality will be difficult
    to achieve at the Greeley plant due to the organic overload
    received at the plant and the plant's inability to handle sludge
    solids which causes sludge bulking or loss of solids.


                                    13

-------
           Achieving optimum reduction  of BODs  at  the  Greeley plant will
     require close control  over the  activated sludge portion  of the
     facility.   The plant will  have  to  be controlled to  obtain the  maximum
     reduction  of 6005 by assimulative  and endogenous  respiration and the
     maximum removal of solids  with  the present sludge handling facilities.

           The  majority of  difficulties that presently exist  at the Greeley
     plant should be alleviated by the  addition of a new facility that is
     under construction.  However, several areas within  the plant that will
     continue to be used in the future  should be modified or  evaluated.
     These are:

           1.  Weir boxes should be  placed on the  return sludge ports
               to each aeration basin so that equal flow distribution
               and the resulting solids distribution can be achieved.

           2.  Flow control and flow measuring  devices should be modified
               on the return sludge  system so that increments of flow
               less than ±100 gpm can be set and maintained.

           3.  The sludge wasting system should be a separate system to
               avoid the balancing problems that occur in a combined
               system.

           4.  The primary  sludge pumping capabilities should be evaluated
               to see if they will be adequate  for future needs.

VI.  Recommendations
           The following recommendations  are made:

           1.   Control  testing should be  continued  at the Greeley facility
               to aid in the operation of the activated sludge portion of
               the plant.

           2.   The activated sludge portion  of the  plant should be operated
               to obtain maximum solids production  from the reduction of
               BODc, thus  optimizing the  reduction  of BOD5 as  a result of
               cell  assimulation and endogenous respiration.

           3.   The maximum amount of solids  that can  be handled by the
               present sludge handling system should  be removed daily.
               This  will increase solids  and associated 6005  removals
               and will  minimize the amount  of solids that will be lost
               in the effluent.

           4.   The operational mode initiated during  Federal  Assistance
               should be continued (i.e., step loading, maximize mixed
               liquor concentrations, etc.).
                                     14

-------
5.  Weir boxes should be placed on the return sludge ports to each
    aeration basin to allow for adjustment of flow distribution.

6.  Return sludge flow control and measuring control should be
    modified to allow for the adjustments of flow less than
    ±100 gpm.

7.  Sludge wasting (both primary and activated) should be evaluated
    to determine if these systems will be adequate for future needs.
                           15
                                                         GPO 844 • 880

-------