United States
Environmental Protection
Agency
                            Air and Radiation
                            (6202 J)
DRAFT
February 1996
r/EFft
A Guide for Methane
Mitigation Projects

Gas-to-Energy at Coal
Mines
 Emissions Overview • Identify Opportunities • Preliminary Site Assessment 4-
 Government Policies • Next Steps • List of Experts • Funding Sources

-------
A Guide for Methane Mitigation Projects
          Gas-to-Energy at Coal Mines
                    DRAFT
        Editors: Dina Kruger and Karl Schultz
        U.S. Environmental Protection Agency
            Office of Air and Radiation
                 February 1996

-------
                                       ACKNOWLEDGMENTS
This report was prepared under Work Assignment 2-15 of U.S. Environmental Protection Agency Contract 68-04-
0088 by ICF Incorporated.  The principal authors were Sonaii Shah and Mary DePasquale of ICF.  The authors wish
to thank Dina Kruger and Karl Schultz of the U.S. Environmental Protection Agency for  guidance and comment
during the preparation of this document.  Mention of trade names or commercial products does not constitute
endorsement or recommendation for use.

This document is a working draft being used by Country Study Program participants to develop methane mitigation
projects.  Users of this document and those implementing methane mitigation projects are encouraged to provide
feedback.  Please direct comments to:

                                  U.S. Environmental Protection Agency
                                           Methane Branch
                                          Mail Code 6202 J
                                         401 M Street, S.W.
                                       Washington D.C. 20460
                                         Tel: 202/233-9768
                                         Fax: 202/233-9569

-------
COMBED VETHAKE  GUIDELINES                                            "ab:e  of


                        TABLE OF CONTENTS

1. INTRODUCTION	.	1
2. OVERVIEW OF COAL NONE METHANE EMISSIONS AND EMISSIONS
REDUCTION OPPORTUNITIES	
2.1 METHANE is A POTENT GREENHOUSE GAS	 4
2.2 METHANE EMISSIONS FROM COALMINING	5
2.3 OPPORTUNITIES TO REDUCE METHANE EMISSIONS FROM COAL MINES	6
2.4 REFERENCES	9

3. IDENTIFY OPPORTUNITIES FOR REDUCING METHANE EMISSIONS	~.ll

4. PRELIMINARY SITE ASSESSMENTS	16

4.1 GENERAL SITE INFORMATION REQUIRED.	16
4.2 IDENTIFY POTENTIAL RECOVERY METHODS AND ESTIMATE GAS PRODUCTION	19
  4.2.1 Gas Production Methods.	19
  4.2.2 Criteria for Selecting a Gas Production Method	25
  4.2.3 Estimate Recovery Potential	25
4.3 IDENTIFY POTENTIAL USES FOR RECOVERED METHANE	27
  4.3.1 Options for Using Coal Mine Methane	27
  4.3.2 Select Use Options for Further Analysis	30
4.4 ASSESS ECONOMIC FEASIBILITY	32
  4.4.1 Costs Analysis	33
  4.4.2 Benefits Analysis	36
4.4 REFERENCES	43

5. IDENTIFICATION AND ASSESSMENT OF KEY GOVERNMENT POLICIES	44

5.1 NATIONAL ENERGY PRICING, SUBSIDIES, AND TAXES	44
5.2 NATIONAL ENERGY SUPPLY PRIORITIES	45
5.3 ENVIRONMENTAL GOALS	45
5.4 FINANCING	46
5.5 TECHNOLOGY DEVELOPMENT ...:	47
5.6 CONCESSION PROCESS	47
5.7 REFERENCES	,	48

6. NEXT STEPS	:	49
6.1 FOCUS ON THE MOST PROMISING PROJECTS	49
6.2 AVAILABILITY OF TECHNOLOGY AND EXPERTISE	52
6.3 MOTIVATE DECISIONMAKERS	53
  6.3.1 Outreach Activities	53
  6.3.2 Demonstration Projects	55
  6.3.3 Information Clearinghouses	55
6.4 REVIEW REGULATORY FRAMEWORK	56
  6.4.1 Evaluate Existing Regulations	:	58
  6.4.2 Develop Feasible Options	59
  6.4.3 Implement Options	59
6.5 OBTAIN PROJECT FUNDING	60
  6.5.7 Review Types of Assistance Available	60
  6.5.2 Identify Funding Requirements	61
  6.5.3 Select Sources of Funding	62
6.6 REFERENCES	.65

-------
of Corners                                               COALBED V.ETHANE GUIDELINES
                 APPENDIX A: DIRECTORY OF SELECT COAL MINE METHANE RECOVERY
                 AND USE EXPERTS IN THE U.S	.	1

                 APPENDIX B: DIRECTORY OF POSSIBLE FUNDING AGENCIES	1
                   International Bank of Reconstruction and Development (IBRD)	2
                   Global Environment Facility (GEF)	3
                   International Finance Corporation (IFC)	4
                   European Bank for Reconstruction and Development (EBRD)	5
                   Inter-American Development Bank (IDB)	6
                   Asian Development Bank (ADB)	7
                   African Development Bank (AfDB)	8
                   Trade Development Agency (TDA)	9
                   17.5. Agency for International Development (USAID)	10
                   Overseas Private Investment Corporation (OPIC)..	:	11
                   Export-Import Bank (EXIMBANK)......	12
                   £7.5. Initiative on Joint Implementation (USIJI)	13

-------
       VETHANT GUIDELINES
                .nirocuci.on
1.  INTRODUCTION
      THIS  report provides guidance for developing programs to reduce
      methane emissions from underground coal mines through coal mine
      methane  recovery  and  use.   Methane  trapped  in the  coal  and
surrounding strata is released during mining.  Because methane is a valuable
source  of  energy,  recovering  and  utilizing  coal  mine  methane  is  an
economically attractive option for reducing greenhouse gas emissions.

This  document  is  directed towards program  managers  responsible  for
developing  greenhouse  gas  (GHG)  mitigation  programs in developing
countries  and countries  with  economies in  transition.    By  focusing  on
identifying  and evaluating  opportunities to  reduce  emissions, this  report
complements the guidance developed by the U.S. Country Studies Program
and materials available  from  related  efforts  of  the  U.S. Environmental
Protection Agency and others.  Furthermore,  as a guidance document for
reducing methane emissions from coal mines, this report assists countries in
fulfilling commitments  under the United Nations Framework Convention on
Climate  Change (UNFCCC)  to  implement  greenhouse  gas  mitigation
programs.

The main goal of this report is to provide  a step-by-step method for performing
a national assessment of the opportunities to reduce methane emissions from
coal mining.  The report presents steps for identifying and evaluating  gassy,
underground coal mines.  Those characteristics that make gas  recovery and
utilization technically and economically attractive are presented.  Additionally,
this report  discusses how national policies  affect the viability  of coal mine
methane recovery projects  and identifies the steps which may be taken to
encourage the development of this resource.

The remainder of this report is organized  into the following five chapters:

2.       Overview of  Coal Mine Methane  Emissions  and Emissions
        Reduction Opportunities: This section provides a brief background
        to the topic of methane emissions and emissions reductions from coal
        mines.

3.       Identify Opportunities to  Reduce  Methane Emissions:   This
        section  describes  a screening  process by  which  the  program
        managers can identify whether underground  coal mines in their
        countries present attractive options for reducing emissions.

4.       Perform Preliminary Site Assessments:  This section presents the
        process for conducting preliminary  site assessments  for individual
        sites or  representative facilities identified as being  good candidates
        for gas recovery projects in Section 3.  Based on this information, the
Given the economic value of methane as
a fuel source and the potential availability
of international donor funding, coal mine
methane recovery and utilization presents
one of the most cost-effective options for
reducing methane emissions.

-------
                                                       ;OAL GUIDELINES
        program  manager  can begin  to  design  an  emissions  reduction
        strategy for this source of methane emissions.

5.      Identify and Assess Key Government  Policies:   This  section
        identifies the key government policies that will promote or hinder coal
        mine  methane  recovery projects. .   Based  on this information,
        potential policy options will be  assessed in the context of national
        priorities.

6.      Next Steps: This section discusses the steps that may be taken by
        program  managers to further  the  development  of  an  emissions
        reduction  program  for underground coal  mines.   Information  on
        international funding sources for coal mine methane recovery projects
        is presented in this section.

Exhibit 1-1 summarizes  how this document  can be used to meet  various
objectives.  The first column lists several common objectives and the  second
column lists the chapter to consult and key elements of that chapter

-------
COALBED  VLTHAKC
;UIDEL!\"CS
 Exhibit 1-1: How to use this Document
                    Objective
 I WANT AN OVERVIEW OF METHANE AS A GREENHOUSE GAS
     •    What are the sources of methane emissions
          and how does  methane contribute  to  the
          greenhouse effect?
                                                  2. Overview Of Methane Emissions And
                                                     Emissions Reduction Opportunities
                                                     2.1 Methane is a Potent Greenhouse Gas
                                                     22 Methane Emissions from Coal Mining
                                                     2.3 Opportunities to Reduce Methane Emissions
                                                         from Coal Mines
 SHOULD I TRY TO REDUCE METHANE EMBSKWS FROM COAL
 MINES?
     •    How do I assess whether we have coal mines
          that  would  be   conducive  to   methane
          emissions reductions?
     •    What data can  I collect to identify promising
          opportunities to reduce  methane  emissions
          from coal mines?
                                                  3. Identify Opportunities For Reducing Methane
                                                      Emissions
                                                      Identify Basins or Coal Regions with Gassy
                                                      Underground Mines
                                                      Determine the number of Large Mines
                                                      Obtain Methane Release Information
                                                      Determine Mine Lifetimes
                                                      Evaluate Energy Demand
 I WANTTO ESTIMATE POTENTIAL EMISSIONS REDUCTIONS
     •    How do I estimate the emissions  reduction
          from individual methane projects?
     •    How do I estimate and compare costs and
          revenues from individual  methane recovery
          projects?
     •    How do I develop  a national assessment of
          emissions reduction and energy production?
                                                  4.  Preliminary Site Assessments
                                                      4.1 General Site Information Required
                                                      4.2 Identify Potential Recovery Methods and
                                                         Estimate Gas Production
                                                      4.3 Identify Potential Uses for Recovered
                                                         Methane
                                                      4.4 Assess Economic Feasibility
 WHAT POLICIES AND REGULATIONS ARE MPORTANT?
     •    What policies affect the economic viability of
          coal bed methane recovery projects?
     •    How can methane recovery  projects  help
          meet other environmental goals?
     •    What  policies   affect  the  availability  of
          financing and technology?
                              POLICIES
5. Identify And Assess Key Government Policies
   5.1 National Energy Pricing, Subsidies, and
       Taxes
   52 National Energy Supply Priorities
   5.3 Environmental Goals
   5.4 Financing
   5.5 Technology Development
   5.6 Concession Process
WHAT CAN I Do NEXT TO FACILITATE A PROJECT?
     •   What additional studies are needed?
     •   How do I remove the barriers that are slowing
         down the process?
     •   Where can I get funding to undertake these
         activities?
                                NEXT
6. Next Steps
   6.1 Focus on the Most Promising Projects
   62 Availability of Technology and Expertise
   6.3 Motivate Decisionmakers
   6.4 Review Regulatory Framework
   6.5 Obtain Project Funding
WHERE CAN I GET ADVICE FROM EXPERTS?
                        Appendix A: Directory of Select Coal Bed Methane Recovery Experts in the
                        U.S.
WHAT ARE THE MAW FUNDING SOURCES APPLICABLE To
COALMINES?
                        Appendix B: Directory of Possible Funding Agencies

-------
 Ove.T.ew
                                     HALOED V.ETIIANE GUIDELINES
                                  2. OVERVIEW OF COAL MINE METHANE EMISSIONS
                                  AND EMISSIONS REDUCTION OPPORTUNITIES
                                  'T'HIS  chapter provides  a brief  background  to  the topic  of methane
                                   J. emissions and opportunities to reduce emissions from underground coal
                                      mines.  First, background information is provided about the atmospheric
                                  importance of methane.  Next,  methane  emissions from coal mines is
                                  discussed.   Finally, the opportunity to reduce methane emissions and the
                                  benefits of reducing emissions are presented.
                                  2.1 Methane is a Potent Greenhouse Gas
Because methane is a source of energy
as weff as a greenhouse gas, reducing
methane emissions coal mines is eco-
nomically beneficial.
Methane (CKU) is an important greenhouse gas and a major environmental
pollutant.  Methane is also the primary component of natural gas and as such
can be a valuable energy source.  Methane emissions reduction strategies
offer one of the most effective means of mitigating global warming in the near
term for the following reasons:

•     Methane (Cft) is one of the principal greenhouse gases, second
       only to carbon dioxide (COa) in its contribution to potential global
       warming. In fact, methane is responsible for roughly 18 percent of the
       total contribution in 1990 of all greenhouse  gases  to  'radiative
       forcing,' the measure used to determine the extent to  which the
       atmosphere is trapping heat due to emissions of greenhouse gases.
       On a  kilogram for kilogram basis,  methane is  a  more potent
       greenhouse gas than C02 (about 24.5 times greater over a 100 year
       time frame).

•     Methane concentrations in the atmosphere have risen rapidly.
       Atmospheric concentrations of methane have been increasing  at
       about 0.6 percent per year (Steele et al.  1992) and have  more than
       doubled over the last two centuries (IPCC 1990). In contrast, C02's
       atmospheric concentration is  increasing at about 0.4 percent per
       year.

•     Reductions in methane emissions will  produce substantial
       benefits  in the short-run.   Methane has a shorter atmospheric
       lifetime than other  greenhouse gases ~ methane lasts  around 11
       years in the atmosphere, whereas C02 lasts about 120 years (IPCC
       1992).  Due to  methane's  high potency and short atmospheric
       lifetime, stabilization of methane emissions will have an  immediate
       impact on mitigating potential climate change.

•     Because methane is a source of energy as well as a greenhouse
       gas, many emissions control options have additional  economic
       benefits.  In many  cases, methane that would otherwise  be emitted

-------
COALBED VETHANE
GUIDELINES
Ov6''v:e\v
            to the atmosphere can be recovered and utilized or the quantity of
            methane emitted can be significantly reduced through the use of cost-
            effective management methods.   Therefore,  emissions reduction
            strategies have the potential to be low cost, or even profitable.   For
            example, methane  recovered from coal mines can be  used as an
            energy source.

    •      Well demonstrated technologies  are  commercially available for
            reducing methane emissions.   For all of the major  sources of
            anthropogenic  methane  emissions  (except  rice  cultivation  and
            biomass burning), cost effective methane reduction technologies are
            commercially  available.    While  offering substantial  emissions
            reductions and economic benefits, these technologies have not been
            implemented on a  wide  scale in the U.S. or globally  because of
            financial, informational, legal, institutional, and other barriers.

    The unique characteristics of methane emissions demonstrate the significance
    of promoting strategies to reduce the amount of  methane discharged into the
    atmosphere.
     2.2  Methane Emissions from Coal Mining

     Methane and coal are formed together during coalification, a process in which
     vegetation is converted by biological and geological forces into coal.  Methane
     is stored within coal seams and surrounding rock strata and is released to the
     atmosphere during mining or through natural erosion.  Typically, significant
     quantities  of methane are  trapped  in the coal and  surrounding  strata of
     underground mines, while little methane  is  associated with  surface-mined
     deposits.

     In underground mines, methane is hazardous in the working areas because
     methane is explosive in concentrations  of  five  to  fifteen  percent  in  air.
     Therefore, all  underground  coal mines  use ventilation systems.   These
     systems pump  large quantities of air through the mine to dilute the methane to
     safe  levels.   In very  gassy  mines,  however,  additional  degasification
     techniques must  be used  along with  ventilation systems.  The  methane
     recovered from these systems is frequently vented into the atmosphere.1

     There are  two important factors that  influence the  amount  of  methane
     generated in coal seams:
                                                         Underground coal nones account for 70 to
                                                         85 percent of methane emissions from the
                                                         coal fuel cyde.
     1  Methane does not typically pose a hazard at surface mines, and ventilation systems
       are not used.  Methane released during the mining of surface deposits disperses in
       the atmosphere and does not reach explosive concentrations.

-------
  Overview
                                       COALBED METHANE GUIDELINES
                                    •      Coal Rank.  Coal is ranked by its carbon content; coals of a higher
                                            rank have a higher carbon content and generally a higher methane
                                            content.2

                                    •      Coal Depth.  Pressure, which increases with depth, tends to  keep
                                            methane in coal seams and surrounding strata from migrating to the
                                            surface.  Thus, within  a given coal rank, deep coal seams tend to
                                            have a higher methane content than shallow ones.

                                    In 1990, the coal fuel cycle (which  includes coal mining, transportation, and
                                    usage) emitted an estimated 24-40 teragrams (Tg) of methane.3 An additional
                                    1.3 Tg of methane was recovered by coal  mines  and used as  an  energy
                                    source.  Underground coal mines were responsible for 70 to 85 percent  of all
                                    emissions, while  surface mines  and the transportation of coal were estimated
                                    to contribute 10 to 20 percent.  Coal combustion was estimated to contribute
                                    the remaining 5 to 10 percent (USEPA1994).
There are many opportunities to expand
the recovery and use of methane fron
gassy underground coal mines.  The
techonolgies are well known and have
been demonstrated worldwide.
2.3 Opportunities to Reduce Methane Emissions
from Coal Mines

Methane recovery and use is technically feasible at many large and gassy coal
mines, but may require a shift in the traditional perception that coal companies
and government authorities have of mine degasification.  Techniques  for
removing methane from mines have been developed primarily for  safety
reasons. Thus,  in many cases the recovered methane  is released  to the
atmosphere with little attention paid to the development of gas use projects. At
mines throughout the world, however,  these same techniques have been
successfully adapted to recover methane, allowing the mines to both improve
mine safety and harness the methane for fuel. Many additional opportunities
exist to expand the use of these technologies and reduce worldwide emissions
of methane into the atmosphere.

There are a variety of reasons why coal mine methane projects are a good
way to reduce methane emissions.  First, individual gassy coal mines can be
large emitters of methane. Therefore, developing a few key projects can result
in significant emission  reductions.   Current data indicate that there  are a
significant number of large and gassy underground mines around the world
that are  good candidates for such emissions reduction projects.

Second, the technologies  for recovering methane in conjunction with coal
mining have been well demonstrated and are currently in use throughout the
                                      In descending order, the ranks of coal are:  Graphite, Anthracite,  Bituminous,
                                      Subbituminous, and Lignite.

                                      One teragram is 106 metric tons, or 1012 grams.

-------
'OALBED  VETIIAXE
   GUIDELINES
Ove"\r'.e\v
   world (see Exhibit 2-1).  The methane recovered using these technologies can
   be used in a variety of ways to meet local energy needs, including: on-site use
   as gas; on-site use to generate electricity; or sale for off-site use to residential,
   commercial, or industrial customers (see Exhibit 2-2).
Exhibit 2-1: Summary of
Underground Mining
Method
Vertical Wells
Gob Wells
Shorthole Horizontal
Boreholes
Longhote Horizontal
Borehole
Cross-measure
Boreholes
Methods for Recovering Methane from
Description
Drilled from the surface to the coal seam several years
in advance of mining.
Drilled from the surface to a few meters above the
coal seam just prior to mining.
Drilled from inside the mine to degasify the coal seam.
Drilled from inside the mine to degasify the coal seam.
Drilled from inside the mine to degasify surrounding
rock strata.
    Exhibit 2-2: Summary of Methods for Utilizing Methane from
    Underground Mines
       Method
    On-site
    Off-site
                       Description
Recovered methane can be used on site directly as gas, or can be
used to generate electricity to meet on-site mine requirements.  For
example, the methane can be used in the coal preparation plant or
for space heating or water heating.  To produce electricity, the
methane can be used to power an engine-generator.
Coal mine owners and developers can sell recovered methane to
nearby industrial, commercial, and residential users.  The quantity
and quality of methane produced and the local demand  for the
energy will determine the distance that the gas must be transported
and how it will be used.  In some cases the methane can be sold to
the local gas distribution network.  Similarly, if more electricity is
produced than is required on site, the excess electricity can be sold
to the local power grid.
   The benefits of recovering and using coal mine methane are summarized in
   the following four main areas:

   •      Economic.   There are several  ways by which coal mine methane
           recovery and use  can lead to economic benefits.  For example,
           methane  recovery  through  degasification  systems   can  reduce
           ventilation costs and improve mine productivity. Also, the mine can
           realize cost savings by using the methane for on-site energy needs.
           Alternatively, the methane can be sold to customers off site.  If the
           cost of recovering and using (or selling) the gas is less than the value
           of the energy derived, the mine will earn a profit.
                                                             In  addition  to   reducing  methane
                                                             emissions,   recovering   coal   mine
                                                             methane has other important benefits:
                                                             the gas can be  used as an  energy
                                                             source;   ventilation  requirements  are
                                                             reduced;   and local  air  quality is
                                                             enhanced.

-------
r\
uve.-v.ew
OALBED V.ETHANE GUIDELINES
Exhibit 2-3: The UN Framework Convention on Climate Change (UNFCCC)

                      The signature of the United Nations Framework Convention on Climate Change (UNFCCC) by around
                      150 countries in Rio de Janeiro in June 1992 indicated a widespread recognition that climate change is a
                      potentially major threat to the world's environment and economic development.

                     The Convention aims to stabilize greenhouse gas concentrations in the atmosphere at a level that
      —3r  - ic~   would prevent dangerous anthropogenic interference with the climate system.  Such a level is to be achieved
   within a time frame sufficient to allow ecosystems to adapt naturally to climate change. The Convention calls for Annex I countries
   to take measures designed to limit emissions of carbon dioxide dioxide and other greenhouse gases, with the aim of returning to
   1990 emissions levels by the year 2000.

   To achieve this objective, the Convention sets out a series of  principles and general commitments.  The key principles
   incorporated in the treaty are the precautionary principle,  the common but differentiated responsibility of states (which assigns
   industrialized states the lead  in combating climate change),  and  the importance of sustainable development.  The general
   commitments, which apply to both developed and developing countries,  are to adopt national programs for mitigating climate
   change; to develop adaptation strategies; to promote the sustainable management and conservation of greenhouse gas "sinks'
   (such as forests); to take climate change into account when setting  relevant social, economic, and environmental policies; to
   cooperate in technical, scientific, and educational matters; and to promote scientific research and the exchange of information.
                                     •      Energy. Coal  mine  methane can  be used to meet the energy
                                             requirements of the mine and nearby areas.  The gas can also be
                                             used as a residential, commercial, or industrial fuel.  This increased
                                             source  of domestic energy can be especially important in nations
                                             where   demand  is  growing  rapidly and  domestic  supplies are
                                             constrained.  The increased reliance on domestic energy resources
                                             can  also  help reduce  energy imports, thereby improving energy
                                             security and the balance of payments.

                                     •      Environment  As explained above, methane is a potent greenhouse
                                             gas.  By  reducing emissions, coal  mine methane  projects fulfill a
                                             country's commitment to the United Nations Framework Convention
                                             on Climate Change (UNFCCC).   The UNFCCC requires developed
                                             countries (also known as Annex I countries) to  adopt measures  to
                                             reduce  greenhouse gas emissions, with the aim  of reducing to 1990
                                             emissions levels by the year 2000 (see Exhibit 2-3).

                                             Furthermore, the recovery of methane increases the supply oftiatural
                                             gas, which  has several advantages over other fossil fuels.   The
                                             displacement of coal (and to a lesser degree oil)  with gas will reduce
                                             emissions of S02, NO,, and participates  (USEPA1986). This will lead
                                             to a cleaner local environment.
                                             Safety.  At gaseous concentrations of 5 to 15 percent, methane is
                                             explosive.  Thus the buildup of methane in underground mines poses
                                             a serious safety hazard.   Increased use of degasification systems
                                             may  improve  safety  by  reducing  methane levels  in the  mine.
                                             Techniques for recovering methane before mining (through  use of
                                             vertical wells drilled from the surface, for example) can significantly

-------
COALBED  VETMANE
GUIDELINES
Overview
            reduce the amount of  methane in the coal  when  mining  occurs
            (USEPA, 1993).

    A variety of coal mine methane recovery activities are currently in place around
    the world. There are examples of profitable projects involving gas sales and
    on-site use. However, many more coal mines can implement economically
    viable methane recovery and utilization projects.  In some cases, national or
    local policies hinder these projects from being undertaken. Relevant policies
    should be  evaluated to assess if they encourage or discourage methane
    recovery and utilization projects. Important issues to analyze  include energy
    production and pricing, environmental policy, financing issues, and technology
    transfer policies.
     2.4 References
     Crutzen, P.J. 1991.  "Methane's Sinks and Sources" Nature Ho. 350.  April
             1991.

     IPCC (Intergovernmental Panel on Climate Change). 1990.  Climate Change:
             The  IPCC  Scientific  Assessment     Report   Prepared  for
             Intergovernmental Panel on Climate Change by Working Group 1.

     IPCC (Intergovernmental Panel on Climate Change).  1992. Climate Change
             1992. The Supplementary Report to the IPCC Scientific Assessment,
             Published for the Intergovernmental Panel  on  Climate  Change
             (IPCC),    World   Meteorological   Organization/United   Nations
             Environment Program. Cambridge University Press.  Edited by J.T.
             Houghton, G.J. Jenkins, and J.J. Ephraums.

     Steele, L.P., E.J.  Dlugokencky, P.M Lang, P.P Tans, R.C. Margin, and K.A.
             Masarie.  1992.   "Slowing down of the global accumulation  of
             atmospheric methane during the 1980s." Nature.  Volume 358. July
             23,1992.

     USEPA (United States Environmental Protection Agency).  1986.  Supplement
             A  to  a  Compilation of Air Pollutant Emission Factors; Volume  I:
             Stationary  and  Point  Sources,  U.S.   Environmental  Protection
             Agency/Office  of  Air  Quality Planning  and  Standards, Research
             Triangle Park, N.C.

     USEPA (U.S. Environmental Protection Agency).  1993.  Options for Reducing
             Methane Emissions Internationally, Volume I: Technical Options for
             Reducing Methane Emissions, Report to the Congress, prepared by
             the Office of Air and Radiation, EPA, Washington, D.C.

-------
0\e"\'e\\                                                            COMBED VETHANC  GUIDELINES
                                 USEPA  (U.S. Environmental  Protection Agency).   1994.   International
                                        Anthropogenic Methane Emissions: Estimates for 1990, Report to the
                                        Congress, prepared by the Office of Policy, Planning and Evaluation,
                                        EPA, Washington, D.C.

-------
COALIO  VCTHANC
GUIDELINES
icerui'v 0"jaor;«:iii.:es  "or1 ^ec^cins  ^TKS
    3.  IDENTIFY OPPORTUNITIES FOR REDUCING
    METHANE EMISSIONS

    nPfflS chapter presents a screening process for national program managers
     A to determine if there  are coal mines in their countries that are good
    candidates for emissions reduction projects.   This  screening  of  project
    opportunities requires five important pieces of information:  (1) the  location of
    regions or basins that are known to have gassy mines; (2) the number of large
    mines in those regions; (3) the amount of methane emitted from each mine;
    (4) the expected lifetime of each large and gassy mine;  and (5) potential uses
    of the recovered methane.  This information may be assembled for all mines in
    the nation, or, in those nations with a large number of  mines, for the largest
    mines from each region or basin.

    A step-by-step approach is presented to assess whether opportunities for the
    implementation of gas recovery projects exist.  Each step in the process is a
    hurdle to be  crossed.  If a  hurdle cannot be  crossed,  it is  unlikely that
    promising emissions reduction opportunities exist. For example, if the gassy
    mines in the nation are  likely to close  in the near future,  then  there are no
    emissions reduction opportunities  and  the analysis ceases.  Assuming that
    there are gassy mines,  you may  find  that there can  be  no market for the
    recovered gas. In this case, gas recovery projects cannot be profitable, and
    emissions can only be reduced at a cost. The analysis would only proceed if
    the program manager is willing to consider emissions  reduction options that
    cost money.  In many countries, this step-by-step process is likely to identify
    gassy coal mines with potential for energy  recovery  resulting in emission
    reductions.

    The initial screening steps are as follows:

    1.      Identify   Basins  or  Coal   Regions  That  Contain   Gassy,
            Underground Mines.   The  first step in the screening  process
            involves locating coal basins or regions that have gassy coal mines.
            Typically, coal industry experts will be knowledgeable  regarding the
            gassiness of the underground  coal mines in each mining  region.  In
            the absence  of specific gas  content information, the presence of
            degasification systems, the coal rank, or the coal depth can be used
            as indicators of gassiness.  If suitable coal basins or regions exist, the
            analysis proceeds to the next step.

    2.      Determine the  Number  of Large,  Underground  Mines in Each
            Coal  Basin or  Region Identified.   For initial screening purposes,
            coal mines producing more than 300,000 metric tons of  coal annually
            will be considered as potential candidates.  Coal mines of this size
            could generate enough methane to  support a recovery project.   It
            should be noted, however, that this size criterion  is  not absolute.
            Smaller coal mines potentially could support successful  recovery and
            use projects, given a high level of methane content in the seams.
                                                       The first step in the screening process is
                                                       to determine whether there  are gassy
                                                       underground coal mines in your country.

-------
                                           g  imiss'ons
                                         BALDED  METHANE GUIDELINES
F"  -isial  screening purposes, mines
ft    -it more than 10 cubic meters ot
rnt-.zne per metric ton of coal produced
are regarded as potential candidates.  In
the absence of  data  on gassiness,
secondary  indicators of gas emissions
rates can be used.
3.      Obtain  Information on Methane  Released  During Coal  Mining.
        For initial screening purposes, mines that emit more than 10 cubic
        meters of methane per metric ton  of coal produced are considered
        sufficiently gassy to be regarded as potential candidates.  Like the
        criteria regarding coal production, this criterion is not absolute.  In
        addition, while annual production  data may be readily available,
        information on methane  emissions may  not be available without
        directly  contacting individual mine  operators.  If emissions data is
        unavailable, other indications of gasiness may be used, including in-
        situ methane content, records of outbursts or explosions, or use of
        mine degasification systems.

4.      Determine  Projected Mine  Lifetime.   For  a  project  to be
        economically viable, the mine should  remain open for at least five
        years.  Once again, this minimum lifetime is only an estimation. The
        lifetime  necessary for a  project to be economically viable will be
        specific to each mine.  Because some  nations are liberalizing and
        privatizing their energy sectors, as well as enacting environmental
        legislation that may affect coal consumption, many factors other than
        the geology of the reserve must be considered in estimating the likely
        life time of a coal mine. If this information is not readily available, the
        remaining life span may be estimated by dividing the total remaining
        reserves by the annual production.  Examining  the economic and
        geological status of other  mines  in the basin or region may also
        provide some clues.

5.      Determine Use for the Recovered Methane:  In nearly all cases, the
        mine will be able to use the recovered methane on-site.  Because the
        candidate mines are relatively large, they have significant energy and
        electricity needs for the mining equipment, for the coal preparation
        process, and for water and  space heating.   In cases where the
        amount of methane recovered exceeds on-site energy requirements it
        is important to determine if there are other potential energy customers
        in the surrounding area.

There are a variety of sources from which the above data may be obtained.
These include the following:

•      Various Government  Organizations.  In many nations, the coal
        mines are  owned by the central or local  governments and/or
        government ministries that  may be familiar with the mining industry
        because they  are involved  in energy planning, policymaking, or
        regulation. For this reason, government entities such as the Ministry
        of Coal, Ministry of Industry, Ministry of the Environment, Mine Safety
        Bureau, or Geologic Ministry  or Institute may have readily available
        sources of information.

        For example, many countries have  a ministry that collects  coal
        production and coal reserve data for each mine in the nation.  Also,

-------
'OALBED  VETIME GUIDELINES
           one  or more government agencies  may • collect data  regarding
           methane emissions and mine life time.  Alternatively, if specific data
           are not readily available, industry experts may know if mines in a
           particular basin or region are known to be gassy.  The mine safety
           agency staff might know that mine operators in a particular area were
           experiencing problems due to high methane levels and planned to
           expand their  degasification systems.  Similarly,  central planning
           ministry staff might be aware of likely shifts in coal production among
           mines or mine shutdowns resulting from government actions such as
           coal sector restructuring or additional environmental regulation.

   •      Coal Mine Operators.  If all the information is not readily available in
           a centralized location, it may be necessary to contact individual mine
           operators. Data on methane emissions, in particular, may be  difficult
           to obtain from sources other than those at the mine. Mine operators
           will almost certainly  have this information because it is  needed to
           design and operate their mine ventilation system.  The feasibility of
           contacting individual mine operators however, will depend on the time
           and resources available for conducting this screening step.

   •      Trade   Associations,  Energy   Institutes,    and   Research
           Organizations.  These entities may have some of the necessary
           data, and in fact, may have more data or may be more accessible
           than the government ministries  in some cases.   Some of these
           organizations may prepare energy studies, publish reports, and have
           their own energy databases.

   •      Coalbed Methane Project Developers.   Project developers who
           recover and  use coal mine methane or have done so in the past may
           be a good source of information.  They may be able to assist in
           obtaining the preliminary information or may be willing to share their
           experiences  with those interested in promoting the implementation of
           similar projects.

   Using the information from the above five steps, the initial appraisal can be
   performed.  Exhibit 3-1 lists the questions addressed by each of the five steps.
   If each of the questions listed  in the exhibit can be answered "Yes," there are
   likely to be good opportunities for reducing methane emissions through the
   implementation of gas recovery and use projects.
   Even if one or more questions cannot be answered "Yes," there may exist,
   under certain circumstances, attractive opportunities for reducing emissions.

-------
.ceri:rv  (boonjruies "o
 -ciria  lim'ssions
COALBED YCTHANE
GUIDELINES
 Exhibit 3-1:  Initial Appraisal Results Checklist

      Are there any coal regions that have underground mines?
       Do any of the underground mines in the identified region(s)
       produce more than 300,000 metric tons annually?
                                                                                                 Yes 3   No 3
 4.
  5.
                                            Do any of the mines in the identified region that produce more than
                                            300,000 metric tons annually: 1) emit more than 10 cubic meters of
                                            methane per metric ton of coal produced; 2) employ degasification   Yes -I   No ID
                                            methods; or, 3) exhibit other indications of high methane
                                            emissions?

                                            Do any of the mines that meet the above criteria have a life span
                                            greater than another five years?                            Yes 3   No 3

                                            Do the coal mines meeting the above criteria have significant
                                            energy requirements; OR are there energy requirements in the      Yes 3   No 3
                                            surrounding area?

                                           If the answer is YES to all of the above questions, there are promising options for gas
                                             recovery. Proceed to Chapter 4, where the technical and economic feasibility of
                                                       gas recovery at each candidate site will be evaluated.
The following economic and social conditions would favor gas recovery from
coal mines:

•      High Energy Cost If the cost of alternative fuels - such as oil, coal,
        and conventional  natural gas - is high in  the area surrounding the
        mine,  smaller sites may  be  able  to undertake  a recovery  and
        utilization project profitably.

•      Recovery Systems Already in Place. Some gassy mines already
        may use  degasification systems to  recover methane  for safety
        reasons.  In such cases, the cost of the project would include only the
        cost incurred to employ the recovered methane. Smaller coal mines
        would be potential  candidates  for methane recovery and.utilization
        projects in such cases.

•      Energy Shortage.   Providing  coal  mine  methane to  areas* facing
        energy shortages offers social and economic benefits that will not be
        apparent in  a simple financial  assessment of the particular project.
        The government  may  undertake a gas recovery  project to provide
        households with low cost and clean energy,  thereby improving their
        standard of living. Indirectly, such projects also may have economic
        benefits.  In such cases, the attractiveness of a gas recovery project
        is better  evaluated in terms of the social  value of energy provided
        rather than on a financial cost-revenue comparison.

Finally, it may  be desirable to recover and combust methane recovered from
coal mines even if they do  not meet the criteria listed above.  In  particular,
even  if there  is no opportunity to use the gas  economically,  methane

-------
"OALBED  VCTHANE GUIDELINES               ice-u/v  Oaoonunii'.es  "or- "rtecjcina limiss'.cns.
   emissions can be reduced at relatively low cost by simply collecting and flaring
   the gas.  Such projects may be attractive to investors in developed countries
   who are identifying low-cost options for reducing greenhouse gas emissions
   through joint international action. There are a number of safety issues that
   must be  addressed,  however, before  flaring may be considered a viable
   option. The U.S. Environmental Protection Agency  is currently examining this
   issue.

-------
:n:narv
                     Assessments
OALBED VETIIANC GUIDELINES
        ASSESSMENT
This section presents a pre-feasibffity
site assessment aimed at evaluathg
the technical and economic feasbffity
of gas recovery.  This is a preliminary
assessment,   designed  to  allow
countries to get sufficient data to show
tfiaf there  is  merit  in  pursuing  the
project further.
                                    4. PRELIMINARY SITE ASSESSMENTS
                              'T'HIS section presents guidance for conducting preliminary assessments of
                               A the candidate  sites identified in Section 3.  These assessments will
                              provide a more comprehensive and concrete evaluation of the attractiveness
                              of each of the gas recovery opportunities.  Using site specific  information,
                              project development options that are most technically appropriate and cost
                              effective will be identified.

                              Some countries may not have the technical and labor resources needed to
                              conduct site  assessments.  Appendix A (at the end of this document) lists
                              experts that may be contacted to conduct project feasibility assessments and
                              develop gas  recovery projects.  Furthermore, Chapter 6 presents steps  for
                              identifying and filling gaps  in the availability of technology and expertise
                              required.

                              In most cases, the screening process  in  Section 3  will  identify several
                              candidate sites worthy of this level of analysis. Under this circumstance, a
                              preliminary site assessment can be conducted for each site.  In some cases,
                              however, so  many  sites may be considered candidates that it may not  be
                              possible to conduct preliminary site assessments for each at this time. In this
                              case, it is recommended that several sites with significant emissions reduction
                              potential be selected for assessment.   For example, the mine with the largest
                              estimated  emissions  in each  coal  region or basin  could  be  selected.
                              Alternatively,   sites could  be  selected  to  represent a  range  of mine
                              characteristics. Based on the results of the analysis of these sites, the need
                              for additional preliminary assessments at additional sites can be determined.

                              The preliminary site assessment examines the main factors influencing the
                              attractiveness of gas recovery projects. Section 4.1 describes the general site
                              information required.  Section 4.2 presents the various recovery techniques
                              and Section  4.3 discusses the possible  use options.   Finally, Section 4.4
                              discusses the economic feasibility of these methods.
                                    4.1 General Site Information Required
                                   The preliminary site assessment begins by collecting general site information.
                                   which will be used to examine the following: methods for recovering methane;
                                   the quantity of gas likely to be produced; and the potential uses for the gas
                                   recovered.   For purposes of this preliminary assessment, the amount of gas
                                   that can be produced will be estimated from information on the amount of
                                   methane released  by  the mine during  mining  activities.   The  following
                                   information should be obtained or estimated:

                                   •      Current and Future Coal Production.  Obtain  recent annual coal
                                           production statistics from the mine (metric tons per year).  Estimate
                                           the number of  years that the mine will  continue to produce coal.

-------
'OALBED  VETIIANE GUIDELINES
"Jre!:m:narv Siie Assessment
           Identify whether the  rate of coal production is expected to change
           significantly in the near future.

           Degasification  System.    Identify whether  the  mine  has  a
           degasification system (in addition ot the ventilation system).  Section
           4.2 (below) describes various degasification systems that may be in
           use.

           Methane Emissions. Estimate current and expected future methane
           emissions from  this mining activity.  Options for estimating  this
           quantity include:

           1.  Ventilation System  Emissions:   Methane emissions from  the
               ventilation  system  equal  the methane concentration  in  the
               ventilation air (typicaly less than one percent) times the volume
               of ventialtion air (e.g.,  in cubic meters per day).  The mine's
               engineering  staff  generally  knows  or can  estimate  these
               quantities.

           2.  Degasification  System  Emissions:    If  the  mine  has  a
               degasification system (in addition ot the ventilation system) the
               methane emissions from this system must be estimated  and
               added   to  the  emissions  from   the  ventilation   system.
               Degasification system  emissions are highly  site-specific  and
               must be  estimated from individual mine data obtained from the
               mine's engineering staff. Identify the amount of methane emitted
               (e.g., in  cubic meters  per day) and the'concentration of the
               methane in the gas flow from the degasification system (e.g., in
               percent).

           3.  In Situ Gas Content The methane emissions from the mine can
               be approximated using the in situ gas content of the coal.  At a
               minimum the methane emissions will be equal to the gas content
               per ton times the annual coal production in tons.  In addition to
               these emissions, methane  is generally released from  strata
               surrounding the coal. The emissions from the surrounding strata
               are highly site-specific, but may be equal in magnitude to the
               emissions from the gas in the coal itself. The mine's engineering
               staff can  normally estimate the in situ gas content and emissions
               from surrounding strata if emissions cannot be estimated from
               ventilation and degasification system data.

           Coal Characteristics. The permeability of the coal will influence the
           types of gas production techniques that can be used. Obtain from the
           mine's  engineering  staff  whether  the  coal   has high  or  low
                       ASSESSMENT
       The mine's engineering staff generally
       has sufficient information  to  estimate
       current  methane emissions  from  trie
       mine. Current emissions will be used to
       estimate potential gas production for the
       preliminary assessment

-------
're::m:.ia.T  Siie  Assess.-nenis                                       COALBED V.ETHANE GUIDELINES
                                            permeability.  Permeability of 1-2 millidarcies (md) is considered low,
                                            3-10 md is medium, and permeability of over 10 md is high.4

                                    •      Terrain and Land Use.  The local terrain and land use may impose
                                            constraints  on the types of gas production techniques that can be
                                            used.  Obtain a general description of the local terrain and land use
                                            condition.  In particular, assess whether wells can be drilled from the
                                            land surface into the  coal seam being  mined and its surrounding
                                            strata.

                                    •      On-slte  Energy Requirements.   Estimate  current and expected
                                            future  on-site energy requirements.  Current or potential on-site gas
                                            use (e.g., for coal preparation or water and space heating) may be
                                            estimated in terms of energy requirements (e.g., megaJoules (MJ) or
                                            BTUs  required per day).  Estimate electricity usage in kiloWatt-hours
                                            (kWh) per day.  In  addition to the quantity of on-site energy  use,
                                            estimate the cost of this energy.

                                    •      Potential Off-site Gas Use.  If the mine  is unable to use all the gas
                                            produced, off-site gas  use options must  be examined.  To conduct
                                            this examination,  a general survey  of  energy-using opportunities
                                            around the  site may be required. At a minimum,  determine whether
                                            there is a gas transmission/distribution system  or an electric power
                                            grid in close proximity to the mine.  Also, identify any large energy
                                            using  facilities near the  mine.   A more  detailed survey should be
                                            conducted once it is clear that on-site energy requirements are less
                                            than the amount of energy produced.

                                    It is expected that not all the above information will be available from all the
                                    relevant facilities. As much information should be  obtained as possible within
                                    the time and resources available  so that a reasonable overview of the mine
                                    and its energy situation can be obtained. If necessary, "general usage factors"
                                    regarding energy requirements for the mine can be applied to provide a rough
                                    approximation of the likely energy demand.

                                    One way to obtain this information is to prepare a survey send  it to the mine.
                                    The mine's  engineering staff  should  be able to provide the  information
                                    relatively easily.  If possible, verify the information in follow up  meetings with
                                    the mine personnel.  Once the information is obtained, the assessment moves
                                    to the  next step to identify potential gas production  techniques.
                                      Permeability is a measure of fluids to flow through the coal and surrounding strata.
                                      Permeability is measured in dairies.

-------
COALBED  VETHANE
GUIDELINES
3'ie  Assessment
    4.2 Identify Potential Recovery Methods and Estimate
    Gas Production

    The purpose of this step is to identify one or more potential gas recovery
    techniques that can be  used to  produce gas at the mine site.  The final
    selection of the preferred  technique  requires a  detailed gas production
    assessment that is  beyond the scope of the preliminary  site  assessment.
    However, this step will provide a rough indication  of the alternatives to be
    considered  so the potential  economic performance of the project can be
    examined.

    Each of the major gas production techniques is described in the  next section.
    Following these descriptions, the criteria for selecting one or more method for
    evaluation in the preliminary assessment are presented.
                                                                       ASSESSMENT
    43.1 Gas Production Methods

    Methods for producing gas from active coal mines include vertical wells, short
    horizontal boreholes,  longhole  horizontal boreholes, gob wells, and cross-
    measure boreholes. Vertical wells and gob wells are drilled from the surface to
    the coal seam, while the various types of boreholes are drilled from inside the
    mine. Vertical wells, horizontal boreholes, and longhole horizontal boreholes
    recover methane in advance of  mining, and typically can produce nearly pure
    methane gas. Gob wells and cross measure boreholes recover methane from
    areas that have already been mined and consequently usually  produce gas
    that is contaminated with mine air, so that it is not pure methane.

    This section describes each of the major degasification methods and provides
    information  for determining whether a method might be appropriate for a
    particular mine.
    Vertical Wells
    Description: Similar in design to conventional oil and gas wells, vertical wells
    are drilled from the surface into the coal seam several years in advance of
    mining. In the U.S., they range from 300 to 600 meters in length, depending
    on the depth of the mine. Well spacing depends on reservoir, geological, and
    surface conditions.  In the U.S., well spacing can range from one well  per
    8 hectares (20 acres) to one well per 65 hectares (160 acres).

   .Vertical wells usually require hydraulic fracturing of the coal seam to activate
    the flow of methane.  These wells may produce large quantities of water and
    small volumes of methane during the first several months of operation. As this
    water is removed and the pressure in the coal seam is lowered, gas production
    increases. This water produced by vertical wells is the same water that would
    be removed when the coal is mined. Generally, this water must be treated and

-------
!"e.:.7i:na."V  Siie  Assessments                                       COALI3ED V.ETHANE GUIDELINES
                                    disposed in a manner that is similar to the treatment and disposal performed
                                    for the water produced during  mining.  Since  vertical wells are operated
                                    several years in advance of mining, the equipment for water treatment would
                                    need to be installed and operated sooner than would be necessary if the water
                                    were handled during mining.

                                    Vertical wells typically produce gas with a methane content greater than 95
                                    percent because the methane that is recovered is not diluted with air from the
                                    mine workings.  The total amount of  methane recovered using vertical  pre-
                                    drainage will depend on both the site specific geology and the number of years
                                    the well  is drilled prior to the start of mining.  Recovery of from 50 to over 70
                                    percent  of the  methane that  would  otherwise be emitted  during  mining
                                    operations is possible for operations  drilling vertical degasification wells at
                                    least 10 years in advance of mining.

                                    Although not widely used in the coal mining industry, vertical wells are used by
                                    numerous stand-alone5 operations that produce methane from coal seams for
                                    sale to natural gas pipelines. The use of this recovery method is growing in
                                    the U.S.  Exhibit 4-1 presents a schematic of a vertical degasification well.

                                    Suitability/Technical Feasibility: Vertical wells (along with longhole  horizontal
                                    boreholes) are the preferred recovery technique when nearly pure methane
                                    must be produced. Vertical wells are suitable for mines that have  access to
                                    advanced technology, can plan several years  in  advance of mining, have
                                    medium  or highly permeable coal seams, and have geological characteristics
                                    that permit drilling from the surface.  One advantage of vertical wells  is that
                                    they may be used in conjunction with  virtually all coal mining methods.  U.S.
                                    coal  mines  employing this  technique have successfully  recovered  large
                                    amounts of high quality methane for sale through conventional gas pipelines.

                                    Vertical wells cannot be used on low permeability coals (less than 3 md), when
                                    surface access  is restricted, or when degasification  cannot  be planned in
                                    advance. In low permeability coal seams, vertical wells may not be effective
                                    due to limited methane flow through  the seam.  Additionally, there is some
                                    concern  that in certain geologic conditions the hydraulic fracturing required to
                                    stimulate production from a vertical  well may cause damage to the roof rock,
                                    which would hinder mining operations.  However, U.S. mines employing this
                                    technique have  shown that hydraulic fracturing can be controlled and should
                                    not adversely affect future mining. Finally, due to the need to fracture the coal
                                    seam in  advance  of  mining,  vertical wells   require  a  more  advanced
                                    technological expertise than do some of the other methods.
                                    5 The term 'stand-alone' refers to coatbed methane operations that produce methane
                                      from coal seams that are not being mined. In most cases, these operations recover
                                      methane from deep and gassy coal seams that are not likely to be mined  in the
                                      foreseeable future.

-------
COALBED  VETUANE  GUIDELINES
"Jr'e^nf]'.na''v
     Exhibit 4-1:  Schematic of a Vertical Degasif ication Well
                                                         Vertical Well
    Short Horizontal Boreholes
     Description:  Short horizontal boreholes are drilled from inside the mine (as
     opposed to from the surface) and they drain methane from the unmined areas
     of the coal seam or blocked out longwall panels shortly before mining.  These
     boreholes are typically 10 to 300 meters in length.  Several hundred boreholes
     may be drilled within a single mine and connected to an in-mine vacuum piping
     system, which transports the methane out of the mine and to the surface.
     Most often, horizontal boreholes  have been used for short-term methane
     control during mining.

     Because methane drainage only occurs from the coal seam being mined (and
     not from the surrounding strata), the recovery efficiency of this technique is low
     -- approximately 10 to 18 percent of methane that would otherwise be emitted
     is captured (USEPA1990).  However, this methane is typically 95 percent pure
     methane.  (USEPA 1993a).  Exhibit  4-2 presents a  schematic of a short
     horizontal borehole.

     Su/faM/fy/Tec/in/ca/ Feasibility:   Horizontal  boreholes recover nearly pure
     methane and therefore can be used when high quality gas  is desired. They
     require access to advanced drilling technology and are  most successful when
     the  coal is  relatively  permeable.   As the recovery efficiency  is quite low,
     however, other recovery methods may be preferred for economic reasons.
     Because they drain methane prior to mining, horizontal boreholes can be used
     in conjunction  with all  mining  methods.  They are difficult to implement,
     however, when coal seams are steeply inclined.

-------
;e
OALBED V.ETHANE  GUIDELINES
                   Exhibit 4-2: Schematic of Short- and Longhole-Horizontal Boreholes
                      Mined Area
                                                                     Unmined Area
                                                                Coal Seams
                                                Short Horizontal
                                                 (ore-mining)

                                                Long Horizontal •
                                                 (pre-mining)
                   Longhole Horizontal Boreholes

                   Description:   Like  horizontal  boreholes, longhole horizontal boreholes are
                   drilled from inside the mine in  advance of mining. They are greater than 300
                   meters in length and are drilled in unmined seams using directional drilling
                   techniques.  Nearly pure methane  is recovered and the recovery efficiency is
                   about 50 percent.  Exhibit 4-2 presents a schematic of a longhole horizontal
                   borehole.

                   Suitability/Technical Feasibility: Longhole horizontal boreholes recover nearly
                   pure methane and  therefore can be used when high  quality gas  is desired.
                   They  are  most suitable for  mines  that have  access to advanced drilling
                   technology.  They  are particularly  effective for gassy, low permeability coal
                   seams that require long diffusion  periods.  As they drain methane prior  to
                   mining,  longhole horizontal boreholes can be  used  in conjunction with all
                   mining methods.
                   Gob Wells
                   Description:   The fractured  zone caused by  the  collapse  of  the strata
                   surrounding the coal seam in longwall and room-and-pillar mining is known as
                   a "gob" area.  Following collapse of this area, a significant amount of methane
                   is released.  Gob wells are drilled from the surface to a point 2 to 15 meters
                   above the target seam just prior to mining. In the U.S., they range from 300 to
                   600 meters in length, depending on the depth  of the  mine.   Although the
                   spacing of gob wells varies at each mine, generally two to six gob wells are
                   used per longwall panel.  As  mining advances under the well, the methane-
                   charged coal and strata around the well fractures. The methane emitted from
                   these fractured strata flows into the gob well and up to the surface. A vacuum

-------
COALBED METHANE GUIDELINES
e.:n.viaii\
     Exhibit 4-3: Schematic of a Gob Well
     is pulled on the well in most cases to prevent methane from entering mine
     working areas.  Exhibit 4-3 presents a schematic of a gob well.

     Initially,  gob wells produce  nearly  pure methane.   Over time,  however,
     additional amounts of  mine air can  flow into the gob area and dilute  the
     methane, reducing purity to between 30 and 80 percent.  In some cases,  it is
     possible to maintain nearly pure methane production from gob  wells through
     careful monitoring and management.  For example, the Jim Walter Resources
     mines in Alabama have been able to maintain nearly pure methane production
     from their gob wells.

     Methane  production rates  from gob  wells  can be very  high, especially
     immediately following the fracturing of the strata as mining advances  under the
     well. Jim Walter Resources reports that their gob wells initially produce at
     rates in excess of  56,000  cubic meters per day. Over time, production rates
     typically decline until a relatively stable rate is achieved, typically in  the range
     of 2,800 cubic meters per  day (USEPA 1990).  Depending on the number and
     spacing of the wells, gob wells can recover an estimated 30 to over 50 percent
     of the methane that would otherwise be emitted from the coal  mine (USEPA
     1990).

     Suitability/Technical Feasibility:  Gob wells can be used to  produce medium
     quality gas, and if the initial quality is maintained, can produce high quality gas
     as well.   Such wells are suitable for all types of mining methods  where gobs
     are created, and for mines where wells may be drilled from the  surface.  Gob
     wells can be effectively used in both low and  high permeability  seams as the
     coal seam is fractured by the mining activity.  This fracturing and breaking of
     the seam  and  strata  releases  large amounts  of  methane,  even in  low
     permeability areas.  As with the vertical wells, it is necessary to consider the
     surface conditions when assessing the technical feasibility of using gob wells.
     If it is heavily populated or if the terrain from the surface to the target seam  is
     harsh, it may be difficult to drill a well.  In addition, gob wells may be difficult to
     place in mines where multiple  seams  have  been  mined.   However, the
                                                                                               ASSESSMENT

-------
',e
COALBED  VETI1ANE GUIDELINES
                    Exhibit 4-4: Schematic of a Cross Measure Borehole
                                                                     Unmined Area
                       Mined Area
                                                                 Coal Seams
                                                  Cross-Measure
                   technology required to drill a gob well is not as complex as that required to drill
                   a vertical well.  This is because  hydraulic fracturing  of the coal seam in
                   advance of mining is not required for gob wells.
                    Cross-Measure Boreholes
                    Description: While horizontal boreholes recover methane from the target coal
                    seam, cross-measure boreholes degasify  the overlying and underlying rock
                    strata. These boreholes are drilled from within the mine and generally produce
                    medium quality gas (similar to the gas produced by gob wells) depending on
                    site specific conditions.  In the U.S., these boreholes typically range from 45 to
                    90 meters in length, are developed to depths ranging from 45 to 85 meters,
                    and are installed 60 to 90 meters apart. Cross-measure boreholes recover up
                    to 20 percent of methane that would otherwise be emitted. A schematic of a
                    cross measure borehole is presented in Exhibit 4-4.

                    Suitability/Technical  Feasibility:   Methane  recovered  from  cross-measure
                    boreholes can be used  when medium quality gas is sufficient.  This method
                    requires only a low level of technology, and can be used effectively in both low
                    and high  permeability seams. However, as recovery efficiency is quite low,
                    alternative production techniques may be preferred for economic reasons.

                    Exhibit 4-5 summarizes the characteristics  of the gas production technologies.
                    As shown in the exhibit, vertical wells have the highest recovery efficiency (up
                    to 70 percent) and can typically recover nearly pure methane.

-------
COALBED  VETIIANE
GUIDELINES
;ie   s
    4.2.2 Criteria for Selecting a Gas Production Method

    For purposes of conducting the preliminary assessment, select one or two gas
    production  options for evaluation.  As; mentioned above, when the project
    moves  beyond  the preliminary  assessment a  detailed  gas  production
    assessment will be conducted to select the preferred gas production method.
    Therefore, this selection is strictly for preliminary evaluation purposes.  The
    following criteria are recommended.

    •      Existing  Degasification  System.  If  the  mine  already  has  a
            degasification system that  is optimized to promote  efficient mine
            production, then this existing system should be the primary candidate
            for consideration.

    •      Coal  Mining and  Site  Conditions.   Select  the option  that  is
            consistent with existing coal production conditions.  If the terrain and
            land use activity permit it, vertical wells and gob wells would likely be
            the two options most worthy of consideration.  Both methods have
            high recovery efficiencies. Additionally, both vertical and gob wells do
            not require advanced  in-mine  drilling  technology.   Vertical  wells
            should  not be  considered,  however,  when the  coal  has low
            permeability, or when degasification cannot take place in advance of
            mining. Gob wells cannot be used if the mining technique does not
            produce gob areas.

    •      Gas Quality Requirements.  If nearly pure methane is required for
            gas use, gob wells may be less preferred. In this case, vertical wells
            and in-mine drilling options should  be examined.  If longhole drilling
            can be conducted, its higher recovery rate may make it attractive.

    The selection of the gas production method may need to be revisited when the
    gas use options are examined.  As discussed below, the perferred gas use
    may impose constraints on gas quality and quantity.
    4.2.3 Estimate Recovery Potential

    Once the preferred gas production methods are selected, the amount of gas
    that can be  produced by  each is estimated.  If  a mine  has an  existing
    degasification system, gas quantity and quality are simply estimated based on
    the current performance of the system. This information was collected as part
    of the general site information (see above).   If the mine's engineering staff
    expects that  enhanced production is possible as part of a recovery project,
    increased rates of gas production can be considered.

-------
Exhibit 4-5: Summary of Methods for Recovering Methane from Underground Mining
Method/Description \ Methane Quality Recovery Applicability j Possible Utilization Options
j Efficiency8
Vertical Wells
Drilled from the surface to the coal
seam several years in advance of
mining.
Gob Wells
Drilled from the surface to a few
meters above the coal seam just
prior to mining.
Short Horizontal Boreholes
Drilled from inside the mine to
degasify the coal seam.
Recovers nearly pure up to 70%
methane.
!
May be used with all mine types where the terrain All use options; preferred method for use options
permits drilling from the surface; not suited for low- requiring nearly pure methane.
permeability seams.

Recovers medium
quality gas: methane
mixed with mine air.
Quality can vary over
time.

Recovers nearly pure
methane.
Longhole Horizontal
Drilled from inside the mine in Recovers nearly pure
advance of mining. methane.
Cross-measure Boreholes:
Drilled from inside the mine to Recovers medium
degasify surrounding rock strata. quality gas: methane
mixed with mine air.
Quality can vary over
time.
up to 50%
Can be used with all mining methods that create
gob areas; can be used in low and high permeability
seams; the terrain must allow for surface drilling.
,

up to 20%

up to 50%
Can be used with all mining methods; may not be
suited for low-permeability or steeply inclined
seams; best when used in conjunction with other
degasification techniques.

Can be used with all mining methods; effective in
low and high permeability seams.
Some mines may be able to recover nearly pure
methane from gob wells. In such cases, the use
options would be the same as for vertical wells.
When recovery of high quality methane is not
feasible, gas use would be limited to power
generation and other options that can use medium
quality gas.

Same as vertical wells, though recovery efficiency
is low, so may need to be used in conjunction with
another method.

Same as for vertical wells.

up to 20%
Sources: USEPA 1993a,b.
a Percent of methane recovered that would otherwise be emitted.
Can be used with all mining methods that create Gas use options are limited to power generation
gob areas; can be used in low and high permeability and other options that can use medium quality gas.
seams; best when used in conjunction with other May need to be used in conjunction with another
degasification methods. method as recovery efficiency is low.
	 : 	 , 	


-------
"OALBED YETIIANE GUIDELINES
         S:ie Assessment
    If there is no degasification system in place, the amount of methane that may
    be recovered from a new system can be estimated by  multiplying methane
    emissions from the ventilation  system by the recovery efficiency listed in
    Exhibit 4-5.  The emissions from the ventilation system were etimated as part
    of the general site information.  For example, if a mine emits 600 million cubic
    meters of methane annually from its ventilation system, gob  wells, which
    recover up to fifty percent of the methane emitted, should be expected to
    produce up to 300 million cubic meters of methane annually.  Alternatively,
    vertical wells would produce up to 420 million cubic meters' (70 percent of
    emissions).  Actual gas production will vary with site conditions and system
    operation.

    Exhibit 4-5 also lists the quality of the gas likely to be produced by each of the
    methods. For example, the gob wells would likley produce medium quality
    gas, whereas vertical wells can  produce high quality gas  (nearly  pure
    methane).
                ASSESSMEMT
   4.3 Identify Potential Uses for Recovered Methane

   Methane recovered from coal  mines can be used in a variety of applications.
   In general, any equipment that can use natural gas as a fuel source can be
   operated using coal mine methane.  Additionally,  coal  mine methane  can
   substitue for oil and coal in many applications.  The preferred methane  use
   option at each mine will depend on a variety of factors including the quantity
   and quality of the methane recovered and local energy needs. First, the main
   use options are described. Then, a process for selecting which options to
   consider in the preliminary assessment is presented.
    4.3.1  Options for Using Coal Mine Methane

    The easiest and often least costly option for using coal mine methane is to use
    the gas to fuel equipment at the mine.  Both high quality and medium quality
    gas (methane mixed with air) can be used in a variety of on-site applications,
    including:

    •       Coal Preparation Plants.  Coal preparation involves cleaning and
            drying  the coal. Coal mine methane can fuel the thermal dryers that
            heat the air used to  remove surface moisture from the coal. Although
            coal is typically used to fuel the coal'drying process, the equipment
            can be converted to use gas.  The coal that would have been used to
            fuel the thermal dryer can then be made available for sale.

    •       Mine Boilers. Recovered methane can be used in boilers for space
            and water heating.  For example, some mines may have bath  houses
            or dormitories that require hot water.  Also, in some regions, it may be
            necessary to heat the ventilation air in the winter before it is pumped
In the Rybnik coal region of the Upper
Silesian Basin in Poland, several mines
use recovered  methane  in their coal
drying plants as well as in their boiler
houses.  CONSOL's Buchanan Mine in
Virginia (USA) has displaced the use o1
coal in its preparation plant thermal dryer
with coal mine methane.

-------
S'ie  Assessment                                       COALIJCD V.CTHANE GUIDELINES
                             into the mine.  In the Donetsk Basin in Ukraine, a small amount of
                             coal mine methane is used in mine boilers.

                     •      Cooking.  Mines that have kitchens can use the recovered methane
                             for cooking purposes.

                     •      Water  Treatment   Coal mine  methane  can be used to fuel the
                             process of treating water recovered during mining.  A demonstration
                             project is underway at the  Morcinek mine in Poland that involves
                             using the methane for this purpose. Once the water is treated, it will
                             be used for agricultural purposes.

                     The advantages of using coal mine  methane in these uses on-site include:
                     (1) the gas does not need to be tranported over a long distance; (2) gas quality
                     need only be maintained at the level required for the on-site equipment; and
                     (3) purchase agreements or  other sales  arrangements do not need to be
                     negotiated.  Additionally, experience indicates that only minimal conversion of
                     existing  equipment  is  needed to convert from  other fuels to coal mine
                     methane.

                     An alternative to using the gas on  site in heating,  drying,  and related
                     applications is to use the gas to produce electricity.  The electricity can be
                     used on site or, as discussed below, sold off site.

                     Gas turbines, internal combustion (1C) engines, and boiler/steam turbines can
                     each be adapted to generate electricity from coal mine methane.  However,
                     the most likely choice of a prime mover for a coal mine methane project would
                     be a gas turbine. Boiler/steam turbines are generally not cost effective in the
                     size range typically encountered with coal mine methane projects (e.g., below
                     30 MW), and 1C engines are more sensitive to variations in fuel heating values
                     than are gas turbines.  Furthermore, gas turbines are smaller and lighter than
                     1C engines and  historically have had lower operation and maintenance costs.
                     A methane/air mixture  with a heating value of at  least 13,000 kJ/m3 is  a
                     suitable  fuel for each of the prime mover options.  All of the gas production
                     methods discussed above, including gob wells, can produce gas of this quality,
                     which is the equivalent of about 35 percent methane in air.

                     Generating  electricity is an attractive option because most coal mines have
                     significant electricity loads. Electricity is required to run nearly every piece of
                     equipment including mining  machines, conveyor belts, desalination plants,
                     coal preparation plants, and ventilation fans. Ventilation systems in particular
                     require large  amounts of electricity because they run 24 hours a day, every
                     day of the year.  In the U.S., about 24 kWh of electricity are required per ton of
                     coal extracted from the mine and 6 kWh are required per ton of coal processed
                     in the coal preparation plant.  Several small power generation projects are
                     operating at  coal mines in China, the Czech Republic,  Poland, Australia,
                     England, and Germany (Sturgill 1991).

                     The viability of producing electricity from coal mine  methane may be limited,
                     however, 'if  the  amount  and  consistency  of the  gas produced varies

-------
COALBED VETIIAXE
JUIDL'LINCS
                Assessments
    considerably from  day to day.   For  example, some  gob wells are  not
    predictable with respect to length of production, methane concentration, and
    rate of flow.  Equipment  to blend the air and methane may be needed to
    ensure that variations in heat content remain within an acceptable range for
    the prime mover. A supplemental gas source may be desired, and a reliable
    back-up power source may be required to  guard against potential gas
    production or equipment problems.

    In the event that electricity generating potential exceeds on-site needs, the
    excess electricity can be sold to the  local power  grid.  Because  on-site
    electricity requirements vary by time of day and day of week depending on
    mining activity, the availability of excess electricity for sale may be intermittent.
    Arrangements  will  be required  with the local  power authority  to sell  the
    electricity into the system.

    If on-site use and electricity generation are not feasible, the gas can be sold to
    customers off  site.  The most  attractive off-site  sales  option is to a gas
    transmission or distribution system in  close proximity to the mine.  To be
    viable, the coal mine methane must be processed to meet the specifications of
    the pipeline receiving the gas.  For most coal  mine methane, the principal
    contaminants are water and sand, which can be easily removed.  After being
    processed, compressors are used to pressurize the  gas to  the  appropriate
    pressure for injection into the pipeline.

    In most regions, conventional gas pipelines carry high quality gas, which would
    be the equivalent of nearly pure methane. Therefore, to sell gas to this type of
    pipeline, the coal mine methane recovery system would need to be designed
    and operated in a manner to produce this high quality gas.  If lower quality gas
    were produced it would need to be enriched.  However, enrichment is often too
    costly to be economically viable.

    In some areas, medium quality  gas is  distributed  through  pipelines.  These
    pipelines are typically separate from the pipelines that distribute conventional
    gas,  depending on  the local  pipeline quality standards.   Because coke oven
    gas and methane recovered from coal mines can have similar heating  values,
    in some cases medium quality  coal mine methane can be transported via
    existing coke oven gas pipelines.  If a medium quality gas pipeline is available,
    the constraints on gas quality produced at the mine are reduced.

    To be economical,  the pipeline receiving the coal  mine methane must be in
    reasonably  close proximity to the mine.  Building and operating a pipeline
    solely to carry the  coal mine methane  can be costly, and consequently the
    transport distance  should be  minimized.   If  no suitable  pipelines are in
    proximity to the mine, alternative gas uses near the mine must be identified.

    As described above, coal  mine methane can be used to fuel nearly all types of
    equipment that use natural gas.  Additionally, the gas can be substituted for oil
    or coal in many applications.  Therefore, industrial, commercial, institutional, or
    household energy  requirements near the mine  can  be met using coal  mine
                 ASSESSMENT
 In  the United States,  Jim Walter
 Resources is  selling  high quaSty
 methane recovered from its  mines in
 Alabama  to a  local gas distribution
 company.  The gas  is sold on the
 same  basis as conventional natural
 gas, and in 1994, the company sold
 approximately 3.8 billion cubic meters
 of methane.
Mines  in  the  Fushun  coal  mining
association m  China  are transporting
medium quality coal mine methane off
site.  In 1993,113 million m3 of gas were
recovered, and about 75 percent of the
gas  was supplied to  160  thousand
households for cooking and heating use.
Twenty percent of the methane was used
by the local chemical industry, and the
remaining five percent was used to
generate electricity.

-------
               S.'ie  Assessments
                                       COALBED  V.ETIIANE
GUIDELINES
If the opportunity to use gas on site is
stater to the level of estimated gas
production, direct on-site use will likely
be  the  preferred  use option for
subsequent evaluation.
methane.  The principal limitation to using the gas in these sectors is the cost
of transporting the gas to its point of use.

Coal mine methane can also be used as a feedstock in chemical production.
Methane is a feedstock in several important chemical processes, such as the
synthesis of ammonia, methanol, and acetic acid. Using high quality gas as a
chemical feedstock may be attractive for  gassy  mines in countries  with
substantial domestic  petrochemical   markets.  Alternatively,  high   quality
methane from several small mines could be collected at a central location in
order to meet the volume  required by the chemical  plant.   Currently, in
Poland's Upper Silesian Basin, a small amount of coal mine methane is being
used as feedstock for a chemical plant.

Exhibit 4-6 summarizes the characteristics of these gas use options.
                                    4.32  Select Use Options for Further Analysis

                                    For purposes of conducting the preliminary assessment, each of the major gas
                                    use options should be examined.  When the project moves beyond the
                                    preliminary assessment a detailed gas use assessment will be conducted to
                                    select the preferred option.Jhe following options are recommended.

                                    •      On-site Use.  Compare the on-site energy requirements (estimated
                                           as  part of the general  site  information)  to the amount of gas
                                           anticipated to be produced. If the opportunity to use gas on site is
                                           similar to the level of estimated gas production, direct on-site use will
                                           likely be the preferred use option for subsequent evaluation.  If the
                                           potential for direct on-site gas use is much less than the anticipated
                                           gas production, an alternative use option should be identified.

                                           It is recommended that the estimated gas production be compared to
                                           on-site gas needs on an energy basis. The energy content of the gas
                                           is estimated from its methane  content.  Pure methane has a heating
                                           value of approximately 37 million Joules per cubic meter (MJ/m3)  at
                                           standard temperature and pressure. Gas that is 50 percent methane,
                                           for example, will have a heating value of 50  percent that amount,  or
                                           about 18.5 MJ/m3.

                                    •      Electricity Generation.  If on-site gas use is not feasible, or if the
                                           amount  of gas produced  greatly exceeds on-site needs, electricity
                                           production may be  an attractive  option.    Compare the on-site
                                           electricity  requirements  (estimated  as  part of  the  general site
                                           information) to the amount of  electricity that  can be generated from
                                           the gas anticipated to be produced. The amount of electricity that can
                                           be generated from the methane may be estimated using the following
                                           formula:

-------
COALBED  VETIIANE
SIDELINES
'J:>e.!:ri::iariv S'ie Assessments
                              Electricity Generated (kWh) =
                  [Gas Recovered (ms) x Heating Value of the Gas (MJ/m»)] /
                              Generator Heat Rate (MJ/kWh)
            The generator  heat rate varies somewhat among  generation
            technologies, but can be assumed to be about 11.6 MJ/kWh, which is
            appropriate for combustion turbines.

            Using these values,  an example  calculation of potential electricity
            production  is as follows.  Assume that 200,000 mVday of  gas is
            produced that is 50 percent methane. The heating value of the gas is
            18.5 MJ/m3. The total electricity that can be produced is therefore:
            200,000 m'/dayx 18.5 MJ/m'/  11.6MJ/kWh  =  318,965 kWh/day.
            The generator capacity  is this value divided by 24 hours, or about
            13,300 kW, or 13.3 MW.

            If  on-srte requirements  are  much  less than.potential electricity
            production, then off-site electricity sales may be required to make
            electricity production  economically feasible.  Such off-site sales may
            be less attractive than  off-site gas sales, discussed next.  Also, a
            combined gas use/electricity production approach can be examined in
            which a portion of the gas is  used directly or  sold,  and  a portion is
            used to produce electricity.
       ff an off-site customer in dose proximity
       to the mine can use  the gas  without
       costtygas enrichment or processing, this
       use option will be attractive.
Exhibit 4-6: Summ
Option
Direct use on-site
On-site electricity
generation
Sale into an Existing
Gas Distribution or
Transmission
System
Sale directly to an
industrial,
residential, or
commercial user
Chemical Feedstock
ary of Coal Mine M<
Min. Quality
Necessary
Medium
Medium
High
Medium
Medium
High
jthane Use Options
Applicability
Suitable for most mines, can be used
to fuel coal preparation plants, heat
space and water, and treat water
Most suitable for mines with large
electricity needs, especially those
which already produce their own
electricity.
Most suitable for mines using
premining degasification and located
near existing high quality gas
pipelines.
Most suitable for mines located near
medium quality pipelines.
Suitable for mines located near
industrial or commercial facilities, or
near residential areas.
Most suitable for very gassy mines
using degasification techniques that
recover nearly pure methane and are
located near chemical plants.

-------
                 ie  Assessments
                                          OALBED V.ETHANE  GUIDELINES
If off-site sales appear to be required,
both electricity  sales and gas sales
should be evaluated as part of the
preliminary assessment
•      Off-site Gas  Sales.    Generally, off-site  gas  sales should  be
        considered when the above on-site use options are not attractive.
        Some site-specific conditions, however, may make off-site gas sales
        the  most attractive  gas  use option.   In  particular,  if an  off-site
        customer in close proximity to the mine can use the gas without costly
        gas enrichment or processing, this option will be attractive.  Off-site
        gas sales can also be examined in combination with on-site use.

        To assess the off-site gas sales option, a brief survey of potential gas
        use in the area around the mine is warranted. Identify the location of
        existing gas pipelines as well as potential industrial, commercial, or
        residential customers. The distance to these potential gas customers
        should be  determined because  distance is  one of the key driving
        factors of the cost of supplying gas to them.

The choice between off-site electricity sales and off-site gas sales will depend
on site-specific conditions.  The  advantage of off-site electricity sales is that
the gas quality need only be  maintained  at the level required for the on-site
electric power generator system. If only medium quality gas is produced, this
advantage can be important.  The disadvantages are that an electric power
grid must be near by, and a power sales agreement must be negotiated.  The
price at which the electricity can be sold will determine the economic feasibility
of this approach.

The advantage of off-site gas sales is that if a customer is near by, the cost of
producing and transporting the gas can be quite low.  However, if  the gas
customer needs high quality gas and only medium quality gas is produced  by
the mine, the enrichment cost may make the project uneconomical. Given the
site-specific nature  of the choice between  these off-site sales options, it is
recommended that if off-site sales  appear to be required, that both electricity
sales and gas sales be evaluated  as part of the preliminary assessment.  If
either or both of the options  appears promising based on the preliminary
assessment results, they can both be evaluated in subsequent site-specific
studies.
                                   4.4 Assess Economic Feasibility

                                   The purpose of evaluating the economic feasibility of the project options is to
                                   ensure that the project meets a target level of cost effectiveness. There may
                                   be several goals of a gas  recovery  project: profitability; energy supply; or
                                   emissions reductions (or a combination of the three).  If only profitable projects
                                   are to  be considered, then revenues must exceed costs. If a net cost can be
                                   incurred to reduce methane emissions and meet other environmental goals,
                                   the threshold may be set in terms of cost per ton of emissions (e.g., $2/ton of
                                   CO? equivalent emissions avoided).  Alternatively, if the goal of the project is to
                                   meet national or local energy demands, the threshold may be set in terms of
                                   cost per unit of energy supplied  (e.g., $0.07/kWh).   Regardless of  the

-------
COMBED VETHANE
GUIDELINES
"J"
   8:rn.:ia'-y
Assessment
    objective, the capital and operating costs of the project must be estimated and
    balanced against the estimated revenues and other benefits.

    Information from all parties potentially involved in the gas recovery project
    should be  considered  at this  stage of the assessment,  including potential
    energy users, the facility owner  or operator, and equipment suppliers.  If
    energy production or prices are regulated, information from the appropriate
    ministries should be obtained  as well to help assess potential costs and
    revenues.  First, the cost analysis is presented, followed by the benefits
    analysis, which  includes a  discussion of how to compare the costs and
    benefits to assess economic feasibility.

    It should be noted that labor and equipment costs can vary significantly among
    countries and regions within countries. The dollar cost estimates presented in
    this section represent U.S. prices. Potential additional transportation costs or
    tariffs are not reflected. Additionally, operating and maintenance costs include
    labor charges, which can vary significantly.  Adjustments  to local currencies
    and cost conditions should be attempted whenever possible.
                                                                        ASSESSMENT
    4.4.1  Costs Analysis

    Costs of recovering and using coal mine methane are highly dependent on the
    amount of gas  involved, the specific technologies used, and site-specific
    factors. The cost estimates developed as part of this preliminary assessment
    will be compared to revenue (or cost savings) estimates to make a  rough
    assessment of the economic viability of the project alternatives. If one or more
    alternative  project configurations  looks  promising,  "more  detailed  cost
    estimates will be conducted  as part  of subsequent  more detailed studies.
    Therefore, the  cost  estimates  prepared here  are  solely  for  preliminary
    assessment purposes.

    As with all project evaluations, both capital costs and annual operating costs
    will be considered.   To estimate these costs,  a listing of each piece of
    equipment required must first be prepared. Exhibit 4-7 lists the major pieces of
    equipment required for the project configurations that may be considered. As
    shown in the exhibit, three main systems are required for all projects:  the
    degasification system; the gas collection and gathering system; and the gas
    processing system. If the mine already has one or more of these systems, and
    does not plan modifications for this project, then the costs for the existing
    components may be excluded.  For example, some mines will already have a
    degasification system in place and operating.

    The pieces of equipment required for on-site gas use,  electricity production,
    and off-site gas use are also listed. Gas enrichment equipment is listed for off-
    site  gas  sales,  but will only be  required  when the gas  quality must be
    enhanced.

-------
i-roa-v "Siie Assess-nenis                                        COALBED  VETIIANE GUIDELINES
                               In addition to the costs for these pieces of equipment, additional costs that
                               must be considered include:

                               •      System Design.  The costs of the system design and construction
                                       management may be on the order of 15 percent of the total capital
                                       cost for the project.

                               •      Legal.  Siting, permitting, and land use requirements must  be  met.
                                       These costs, which can be substantial, include the costs of obtaining
                                       necessary permits and licenses, and potentially installing  pollution
                                       control equipment.

                               •      Financing.  Financing costs include the cost for obtaining financing
                                       as well as interest payments. These costs depend on the financing
                                       method and project specific factors.

                               •      Rights-of-Way.  Costs of obtaining rights-of-way to run pipelines or
                                       power lines must be considered and may be substantial.

                               Experience in the U.S. indicates that these additional non-equipment costs can
                               be substantial.  However, due to their site-specific nature, general cost factors
                               cannot be provided to estimate each type of cost.

                               Given  this approach, the equipment capital and  operating costs  are the
                               primary costs estimated in the preliminary assessment  Exhibit 4-8 provides
                               cost coefficients for the main pieces of equipment required. It must be noted,
                               that costs  will vary significantly among projects and among countries.  The
                               costs presented here are based on U.S. experiences and technologies and are
                               presented in U.S. dollars.

                               To estimate project costs, perform the following:

                                       1.  Define the project configuration in terms  of the gas production
                                           system  and gas use option.

                                       2.  Identify the  pieces  of  equipment  required  for  the  project
                                           configuration.  Do not include equipment that the  mine already
                                           has  in  place (e.g., if the mine  has  an existing degasrfication
                                           system).

                                       3.  Select a project lifetime, for example between 10 and 20 years.
                                           The sensitivity of the costs and benefits to the project lifetime can
                                           be examined.

                                       4.  Estimate the average annual amount of coal mined  (in tons)
                                           during the life of the project.

-------
OALBED VLTIIANT  GUIDELINES
rjy-e.''n::ia"v S!ie Assessment
           5.   Estimate the average daily total gas production during the life of
               the project (cubic meters per day).

           6.   If off-site gas sales are anticipated, estimate the distance to the
               point of sale (in meters).

           7.   Using the cost coefficients in Exhibit 4-8, estimate the capital and
               operating costs for the system components required.

           8.   Summarize the estimated costs to show one-time capital costs in
               yearl,   and   recurring  capital   costs   and  operation   and
               maintenance costs in each year of the project. Add a percentage
               of the one-time capital costs (e.g.,  20 percent) to account for
               system design and other costs.

   For example, to estimate the costs for gob wells, the annual  average  coal
   production (tons per year) is used to estimate the number of wells required per
   year.  The cost per well ($25,000 to $50,000) is multiplied by the number of
   wells required per year to estimate the annually  recurring cost of installing
   these wells.

   If vertical wells are planned instead of gob wells, the number of wells required
   is estimated using the total planned coal production over the life of the project.
   The cost per well is then used to estimate the total one-time capital costs for
   these wells, which is  incurred at the start of the project.  Unlike  the other gas
   recovery wells which are drilled throughout the life of the project  as the coal is
   mined, all the vertical wells are typically drilled at the beginning of the project.
                      ASSESSMENT
Exhibit 4-7: Summary ol
System Component
Degasification System
(Required for all options)
Gas Collection and
Gathering System
(Required for all options)
Gas Processing System
(Required for all options)
On-site Gas Use System
Electric Power Generation
System
Off-site Gas Sales System
F Major Pieces of Equipmen
Purpose
Withdraw the gas from the
coal and and/or surrounding
strata.
Collect the gas from the
withdrawal wells to a central
point for use or sale.
Remove water and
impurities from the gas.
Convert on-site equipment
for direct gas use.
Produce electricity from the
recovered coal mine
methane.
Prepare and transport gas to
an off-site customer.
t Required
Equipment Required
• Withdrawal wells (vertical; gob; or in-mine)
• Water treatment and disposal equipment
(required only for vertical wells)
• Wellhead exhauster/blower
• Wellhead and satellite compressors to move the
gas to the central collection point
• Gathering line
• Wellhead separator
• Dehydrator
• Preparation plant conversion equipment
• Gas turbine
• Utility interconnect
• Gas enrichment equipment
• Sales compressor
• Sales meter and gas analyzer
• Transmission pipeline

-------
"e.'.-ninarv S'.e Assess.-nenis                                       COALI3ED  V.ETHANE GUIDELINES
                                  The other cost components are estimated in a similar manner.  Compressor
                                  requirements, for example, are estimated based on the horsepower (HP)
                                  required per million cubic meters of gas production per day and the cost per
                                  HP. Gathering line costs are estimated based on distance estimates.

                                  It should be emphasized that the cost ranges are representative of conditions
                                  found in the U.S.  For an initial evaluation, values in the middle of the ranges
                                  presented may be used. However, if possible, site-specific conditions should
                                  be considered in selecting values from the ranges. Particularly important site-
                                  specific factors may include well depths, water treatment requirements (vertical
                                  wells  only),  gathering  line distances,  gas enrichment  requirements,  and
                                  equipment conversion costs.
                                  4.42 Benefits Analysis

                                  The goals of a gas recovery project may be several - profits from revenues or
                                  cost savings, energy supply, and/or emissions reductions. The benefits of gas
                                  recovery  will  be evaluated  in terms of these project goals.  The benefits
                                  analyzed in this section include: revenues generated from the utilization of the
                                  gas; energy supplied; and methane emissions avoided.
                                  Revenues/Savings

                                  The revenue from the project is estimated as the amount of energy (gas or
                                  electricity) produced multiplied by its price. If the energy is used to offset on-
                                  site energy costs (e.g., coal, natural gas, oil, electricity), the value of this offset
                                  is counted as revenue to the facility. If the energy is sold, the revenue is the
                                  quantity sold times the price. Tax credits or other government incentives may
                                  supplement these revenues.

                                  The value of the energy will vary according to local energy prices.  These
                                  prices may be negotiated with individual suppliers or customers, or may be set
                                  by national or state  policy.  Important factors affecting energy prices include
                                  the price of competing sources of energy, supply reliability, energy subsidies
                                  and taxes, and the quantity purchased.

                                  The revenue or savings resulting from each  project  must be estimated using
                                  local  information obtained  from  electricity/energy authorities.   A  brief
                                  description of how these values may be estimated is as follows.

                                  •      On-Site Use.  The savings associated with the use of coal mine
                                          methane on-site are estimated using the cost of the fuel displaced, or
                                          the value of the coal that otherwise would  have been used.  These
                                          values should be estimated from on-site energy consumption records.

-------
Exhibit 4-8: Gas Recovery and Utilization Cost Factors
   System Component/
   Equipment Required
                                      Number or Size of Units Needed
                                                                   Cost Per Unit
                                                                    Comments
Degaslfication System (Cost to drill, Install, and complete wells and boreholes)
Gob Wells
                                 1 well for every 200,000 to 500,000 tons of coal mined
                                 each year.  This estimate was derived by assuming
                                 that approximately 1 million tons would be mined per
                                 longwall panel and that from 2 to 5 wells would be
                                 drilled  per  panel.    More  accurate data  can  be
                                 substituted  if  more detailed information  is available
                                 regarding longwall panel sizes and well spacing.
                                                   $25,000  to $50,000 per  well.   This  estimate
                                                   assumes that drilling costs are roughly $90 to $140
                                                   per meter of well depth.
                                                 Cost for drilling gob wells is  an annual capital cost
                                                 (incurred each year).  The rate of advance of mining
                                                 dictates when gob wells are drilled.
                                                                                                                                     Cost per well includes cost of hydraulic fracturing of coal
                                                                                                                                     seam  to stimulate  gas production.  Cost  for drilling
                                                                                                                                     vertical wells is a one-time capital cost. Total number of
                                                                                                                                     wells required over project lifetime may be drilled during
                                                                                                                                     first year so that individual wells can produce gas for as
                                                                                                                                     long as possible before being mined through. However,
                                                                                                                                     if up-front capital  is limited, well drilling can be spread
                                                                                                                                     out throughout the life of the project.
Pre-mining Vertical Wells
1 well  for every 250,000 to 1,000,000 tons of  coal
mined over the life of the project.  This estimate was
developed assuming well spacing of from 20 to 80
acres.
$100,000 to $500,000 per well
Longhole Horizontal Boreholes
                                 1 longhole borehole drilled each year per 1 million tons
                                 of coal (approximately 1 borehole per longwall panel).
                                 Typical  length of longhole borehole may be  1200
                                 meters.                             	
                                                   $60,000  to  $100,000 per 1  million  tons  of  coal
                                                   (approximately 1 longwall panel). Estimate assumes
                                                   borehole length of approximately 1200 meters and
                                                   drilling cost of $50 to $80 per meter.
                                                 Drilling  longhole  horizontal  boreholes is an  annual
                                                 capital  cost  (incurred each year).  Rate  of  drilling
                                                 longhole horizontal boreholes determined by  rate of
                                                 advance of mining.
Shorthole Horizontal Boreholes
                                 4,500  meters  of borehole  drilled  each  year per
                                 1 million tons of coal (approximately 1 longwall panel).
                                 Shorthole    horizontal    boreholes   are    drilled
                                 perpendicular to  the  longwall panel.   This  estimate
                                 assumes 30 boreholes are drilled into the longwall
                                 panel and that each borehole is 150 meters long.
                                 Given  that a typical longwall  panel  is about 1800
                                 meters long, boreholes would be spaced every 60
                                 meters.
                                                   $30 to $50 per meter or $135,000 to $225,000 per 1
                                                   million tons of coal (approximately 1 longwall panel).
                                                 Drilling  Shorthole horizontal boreholes is an  annual
                                                 capital  cost  (incurred  each year).   Rate  of  drilling
                                                 Shorthole horizontal boreholes is determined by the rate
                                                 of advance of mining.
Capital Cost for Water Disposal
Costs for Vertical Pre-Mining
Degasification Wells
                                 1 disposal system needed per project.
                                                   Range:  $100,000 to $2,800,000.  Capital costs vary
                                                   substantially  depending  on  local  environmental
                                                   conditions and disposal requirements. The low end
                                                   of the range of capital costs is for a simple aeration
                                                   system with discharge to surface water, which may
                                                   be used for relatively low volumes in some areas.
                                                   The higher end cost represents deep-well injection,
                                                   which may be required in some areas.
                                                 Cost for a water disposal system are a one-time capital
                                                 cost.  Note that a coal seam is dewatered as part of the
                                                 normal mining process.  Accordingly, the same water
                                                 produced  from pre-mining degasification wells  would
                                                 otherwise  have been removed as  part of the  normal
                                                 mining process. Therefore, unless  there is significant
                                                 recharging of the  water table during the time between
                                                 well drilling and mining, costs for water disposal should
                                                 not be considered as an incremental  cost associated
                                                 with a degasification project.  However, costs would be
                                                 incurred at the time of well drilling, as opposed to at the
                                                 time of mining.	

-------
Exhibit 4-8: Gas Re ory
System Component/
Equipment Required
Operating Cost for Water
Disposal for Vertical Pre-Mining
Degasification Wells
and Utilization Cost Factors
Number or Size of Units Needed
Water production might range from 17 to 70 barrels per
thousand cubic meters of gas produced. Water
production will be highly site specific. Water
production is significantly higher during the first years
of production.
Cost Per Unit
Annual operating costs for water disposal range from
$0.02/barrel to nearly $2/barrel. The lower operating
cost is typical for a simplified aeration system, while
the higher operating cost is typical for a system
requiring transport to an off-site disposal location.
Comments

Gas Collection and Gathering System Costs
Wellhead exhauster/blowers for
gob wells
Wellhead and satellite
compressors for all degasification
systems.
Gathering Lines from Satellite
Compressors to Central
Collection Point
Gathering Lines for Gob Well
System: Lines from the wells to
the Satellite Compressor
Gathering Lines for Pre-Mining
Vertical Well Degasification
System: Lines from the wells to
the Satellite Compressor
Gathering Lines for In-mine
Borehole Systems: Lines from
the wells to the Satellite
Compressor
1 blower per maximum number of gob wells drilled in a
year. Number of gob wells drilled annually estimated
above based on annual coal production.
14,000 to 25,000 HP per million cubic meters per day
of total gas production (maximum projected daily gas
production).
6,000 to 25,000 meters of gathering line, depending on
overall size of project and whether there is more than
one gob field.
Movable Lines from Gob Wells to Satellite
Compressors: 2,500 meters per 1 million tons of coal
mined annually (assuming a typical longwall panel
may contain 1 million tons of coal).
Lines from Wells to Satellite Compressors: 3,000
meters per well.
Underground Lines: 2,500 meters per 1 million tons of
coal mined (assuming a typical longwall panel may
contain 1 million tons of coal).
$20,000 per gob well.
S650/HP
Average: $26/meter. Ranges from $13/meter to
$46/meter, depending on whether line is buried,
material used (HPDE or steel), and size of line.
Most projects will require a combination of less
expensive and more expensive piping material.
Average: $26/meter. Ranges from $13/meter to
$46/meter, depending on whether line is buried,
material used (HPDE or steel), and size of line.
Most projects will require a combination of less
expensive and more expensive piping material.
Average: $26/meter. Ranges from $13/meter to
$46/meter, depending on whether line is buried,
material used (HPDE or steel), and size of line.
Most projects will require a combination of less
expensive and more expensive piping material.
$20/meter
If a mine already uses gob wells, the mine will already
have an exhauster/blower at the wellhead.
Horsepower includes total horsepower for wellhead
compressors and satellite compressors.
One-time capital cost. Highly dependent on site-
specific conditins.
Lines running from gob wells to satellite compressor can
be moved from year to year as some gob wells stop
producing and others come on-line. (A typical gob well
might produce gas for a few months to a few years,
though typically will produce gas for less than one year).
Since gathering lines can be moved, costs for
purchasing gathering lines is a one-time capital cost.
However, the cost for moving and installing gathering
lines is an annual cost. Roughly half of the costs shown
are for recurring (i.e., annual) installation costs.
Cost for purchasing and installing gathering lines is a
one-time capital cost. Lines running from vertical wells
to satellite compressors would not be moved on a
regular basis, since vertical wells will likely produce gas
for many years.
Underground lines can be moved from one borehole to
another. Cost for purchasing line would be a one-time
capital cost, while cost for moving and re-installing lines
would be an annual cost. Roughly half of the costs
shown are for recurring (i.e., annual) installation costs.

-------
Exhibit 4*8: Gas Recovery
System Component/
Equipment Required
and Utilization Cost Factors
Number or Size of Units Needed
Cost Per Unit
Comments
Gas Processing System
Wellhead Separators
Glycol Dehydrator Capital Cost
Dehydration Operating Cost
For surface wells: 1 separator for each well
(1 separator for maximum number of wells drilled per
year).
For in-mine boreholes: 1 separator is needed for every
four longwall panels drilled (every 4 million tons of coal
drilled each year). Since separators can be moved,
total number of separators needed would be based on
maximum number of longwall panels drilled each year.
1 Dehydrator per project.

$2,000 per separator
Initial capital cost: $30,000 to $50,000.
Annual operating cost: $3,000 per year
Wellhead separators are a one-time capital cost.
Because vertical wells produce simultaneously, one
separator is required for each well drilled. Because gob
wells and in-mine boreholes produce sequentially, one
separator is needed for the maximum number of wells
drilled in a single year. For long project lifetimes (more
than 15 years), separators may need to be replaced
once.
Dehydrator costs are a one-time capital cost. For long
project lifetimes (more than 15 years), the dehydrator
may need to be replaced once.

On-Site Gas Use System
Preparation plant conversion
equipment

$250,000 to $750,00
Initial capital cost (depends on site-specific equipment
requirements).
Electric Power Generation System
Gas Turbine Capital Cost
Gas Turbine Operating Cost
Utility Interconnection Cost
Installed capacity of the turbine in kiloWatts (kW)

Initial cost per project.
$1,100/kW installed capacity.
$0.01/kWh of electricity generated.
$300,000 to $500,000 per project.
Initial capital cost. Capacity estimated based on gas
production and engine-generator heat rate (see text).
Annual operating cost. Electricity generated estimated
based on gas production and engine-generator heat
rate (see text).
Initial capital cost.
Off-Site Gas Sales System
Gas enrichment equipment
capital cost.
Gas enrichment system operating
cost.
Sales compressor to bring the
gas to pipeline pressure
Sales meter and gas analyzer
Transmission Pipeline
One system per project.

3,500 MP per maximum expected production in million
cubic meters per day. Compressor HP needed will
vary based on pressure of sales pipeline and distance
to sales pipeline or pressure required by industrial end-
user and distance to end-user.
1 sales meter and gas analyzer per project
Length of transmission pipeline will vary substantially
depending on distance between mine and commercial
pipeline or industry end-user.
$1 to $3 million, depending on gas flow rates and
gas quality.
$3.50 per thousand cubic meters of gas enriched.
$650/HP
$20,000 per project.
$32/meter.
Initial capital cost. Enrichment will not be required for
gas produced from vertical pre-mining degasification
wells or horizontal boreholes. Gas produced from gob
wells or cross-measure boreholes, however, may
require enrichment. Enrichment equipment includes
cost for pressure swing adsorption system and a
catalytic deoxygination unit.

Initial capital cost.
Initial capital cost.
Initial capital cost.

-------
S:le  Assessment                                       COALBCD  V.ETHANE GUIDELINES
                     •       Electricity Sales.  If electricity is to be distributed through the electric
                             power grid, the  owner/operator of the grid (such as  a national
                             electricity company) will typically purchase the electricity at the point
                             at which it enters the grid. There are a variety of methods by which
                             the electricity price may be determined.  For example, the price could
                             be set  at the average  marginal cost  of  generating  electricity
                             elsewhere in the system, or it could be set at the price given to
                             electricity producers using conventional fuels.  It is recommended that
                             potential pricing arrangements be explored with the proper authorities
                             as part of this preliminary assessment.   In some cases, the electric
                             power generation aspect of the project is best developed jointly witk
                             the electric power authority.

                     •       Sale of Gas.  The expected price  of gas sold directly to customers
                             can be based on the price of alternative fuels, such as propane, oil,
                             natural gas or coal, on an energy basis (e.g., price per million Joules).
                             The relevant fuel price to use depends  on which fuel the coal mine
                             methane  will be  replacing.   The  price of gas sold to  a pipeline
                             company can be based on the price paid for other gas supplies on a
                             comparable energy  basis.   If the customer must convert his
                             equipment to use the coal mine methane,  the gas may need to be
                             sold at a discount.

                     •      Tax credits. Tax credits or other government programs can also
                             affect project revenues.  Some government programs may offer tax
                             credits or subsidies for producing energy  from  non-conventional
                             sources,  including coal mines. The applicability of these  incentives
                             usually depends on the structure of the project and the coal mine
                             owner/operators' tax situation. Therefore, a complete understanding
                            of the tax laws  and their application is critical to  ensuring a project's
                            ability to take full advantage of the incentives.
                                                                                          \

                     Under some conditions royalties are paid to the resource owner. Royalties can
                     be viewed as compensation  for gas  rights or  as  a financial  incentive for
                     allowing  the project to be developed.  Royalties are usually estimated as a
                     percentage of total revenue or energy produced.  Any royalty payments should
                     be subtracted  from the revenue estimate prior to  comparing  costs  and
                     revenues from the project developer's perspective.
                    Cost/Benefit Analysis

                    Once the revenues  are  estimated, they must be compared to the costs
                    (estimated in the previous section).  This comparison requires a time profile of
                    the project's costs and revenues.  From the  information above, the capital
                    costs,  annual  operating  costs,  and annual  revenues can  be  estimated.
                    Possible increases or decreases in energy prices and gas production over the
                    life of the project should be taken account when estimating annual revenues
                    and savings. For purposes of evaluation, it  can be assumed that the project

-------
'OALBED  V.LTHAXC GUIDELINES
                Assess Tierus
   continues for 10 to 20 years, and the annual operating expenses are incurred
   each  year.   Using  the  time profile of costs  and  revenues,  three  main
   techniques can be used to determine the economic feasibility of the project:

   •      Payback Method.  The payback  method involves determining the
           number of years  it would take for a project to generate profits equal to
           the initial capital outlay.  The advantage of this method is that it is
           simple.  It may be particularly suitable where there is a great amount
           of risk and uncertainty associated with a project and the emphasis is
           on recovering capital expenditures as quickly as possible.  Its main
           drawbacks are that it does not consider the costs and benefits that
           accrue at the end of the payback period and that it takes no account
           of the time when costs are incurred or benefits received The payback
           method is appropriate  to use when making  a rough preliminary
           assessment of a project's economic feasibility.

   •      Discounted  Cash Flow Method.  The  basic premise  of the
           discounted cash flow technique is that costs or benefits occurring in
           the future  are worth less that those occurring now. This means that
           costs and  benefits cannot simply be added up over the years of the
           project.   The costs and benefits  in each year of the project are
           adjusted by a discount  factor so that costs  or benefits occurring in
           one  year can be compared with the costs or benefits occurring in
           another year. The discounted costs and benefits in each year can be
           aggregated to give a net present value (see Exhibit 4-9) of future
           cash flows of the project. The discount rate used will normally be
           chosen on the basis of prevailing interest rates or on the basis of the
           minimum desired rate of return for the project,  jf the  net present
           value is positive, the appraisal shows that the project is capable of
           yielding this  minimum rate of return.

   •      Internal Rate of Return  Method.  The internal rate of return  (see
           Exhibit 4-10) is the discount rate at which the present value of the
           project would be zero.   This  value shows  the total  rate of return
           achieved by the project. This rate can be compared to return rates
           from alternative investment opportunities.

   Sensitivity analyses  should  be carried out to examine how changes  in key
   parameters  such  as electricity  prices or  gas production can  affect the
   economic viability of the  project.  These sensitivity analyses can carried out
   before the financing arrangements for the project have been worked out and
   are useful in providing an  initial indication  of the project's viability.  Further
   analysis can be conducted to examine the implications for viability of different
   financing schemes.
                 ASSESSMENT
Exhibit 44: Net Present Value
The  Net  Present Value (NPV) is  the
present value of a project's cash flows,
including  all  investment costs.   If  the
NPV is greater than 0,  a project is
considered  to  be  profitable at  the
chosen discount rate.  The net present
value can be expressed as follows:

            n   ACF
  NPV=  y  	'—-IO
where:

ACFt
r
10
n
           annual cash flow in year't
           discount rate
           initial cash outlay
           life of the project
Exhibit  4-10:   Internal Rate  of
Return
The Internal Rate of Return is calculated
as follows:
       n
   =   I
              ACF
                         — IO
where:

ACFt
10
n
IRR
        = annual cash flow in year t
        = initial cash outlay
        = life of the project
        = internal rate of return.

-------
                              Tie-US
                                        COALBEDV.ETIIANE GUIDELINES
                                     Energy Supplied

                                     The cost effectiveness of a gas recovery project may be evaluated in terms of
                                     the quantity of energy supplied.  The cost of gas recovery would be compared
                                     with alternative energy supply options to determine the most cost effective
                                     option.  The threshold level of cost effectiveness may be set in terms of energy
                                     supplied per unit cost. For example, gas recovery projects that supply energy
                                     at a cost of $0.07/kWh may be defined as being cost effective if the marginal
                                     cost of alternative electricity supply options is $0.07/kWh.

                                     In some cases, energy from the gas  recovery project may be provided to
                                     customers who otherwise would be using wood (e.g., for residential cooking).
                                     In this case, the value of preventing over-harvesting of forest resources may
                                     be the measure of cost effectiveness for the project. An alternative may be to
                                     set a threshold level in terms of the number of households served by the
                                     energy  supplied.   This would require data on average household energy
                                     consumption. For example, a cost effective project may be one that costs less
                                     than $3 per household served.  Such evaluations are prudent particularly in
                                     areas of energy scarcity.
Benefits of  emission  reduction are
difficult to evaluate in monetary terms as
they do not accrue directly to a project
developer.  However, such benefits are
important to consider in the formulation
of national energy policy and tax and
subsidy    regimes   for   emissions
mitigation or renewable energy projects.
Emissions Avoided

Recovery and utilization of methane from coal mines prevent the release of
methane and provide a clean energy source. Methane is a potent greenhouse
gas; over a 100 year period, a ton of methane emitted into the atmosphere has
the equivalent global warming impact of about 21  tons  of carbon dioxide.
Combusting the coal mine methane prevents its emission into the atmosphere,
thereby reducing greenhouse gas emissions

Although the emphasis of this  document is  to  identify projects  that  are
economically viable  in  their  own right,  gas  recovery  projects  may be
implemented specifically to reduce methane emissions from the mine.  The
economics of such a project will be evaluated in terms of the cost of emissions
avoided.  For example, a threshold level of cost effectiveness may be set at
$50 per ton of methane emissions avoided.  If the project costs less thgn $50
per ton of methane emissions avoided, the project is considered cost effective.

The emissions impact of a gas  recovery projects is, simply, the amount of gas
recovered and combusted. The methane emissions avoided can be expressed
in terms of carbon dioxide emission avoided using a Global Warming Potential
of methane equal to 21.6 The following equation expresses the relationship.
                                       The Global Warming Potential (GWP) is a measure of the relative warming impact of
                                       a gas relative to the warming impact of carbon dioxide.  One gram of methane has
                                       21 times the impact of one gram of carbon dioxide over a 100 year period.

-------
COALBED VETIIANE GUIDELINES

le   ssessment
                   COz Equivalent Emissions Avoided (tbns/yr)

          Cm Emissions Avoided (tons/yr) x 21 tons COz Equivalent/ion Cfe
     !y expressing the emissions reduction in terms of an equivalent amount of
     arbon dioxide, the reductions from this project can be compared to alternative
    methods of reducing greenhouse gas emissions.  The extent to which the
    recovered coal mine methane is substituted for more polluting fuels, emissions
    of other pollutants will also be reduced.
    4.4 References
                                                                                           ASSESSMENT
    Sturgill, C.  1991.  Power Generation: On-Site Use and Sale to Utilities.
            Prepared for US EPA Office of Air and Radiation,  EPA, Washington,
            D.C.

    USEPA (U.S. Environmental Protection Agency).  1990.  Methane Emissions
            from Coal Mining: Issues and Opportunities for Reduction, Office of
            Air and Radiation, EPA, Washington, D.C.

    USEPA (U.S.  Environmental  Protection Agency).   1993a.   Anthropogenic
            Methane Emissions in the United States, Report to the Congress,
            prepared by the Global Change Division, Office of Air and Radiation,
            EPA, Washington, D.C.

    USEPA (U.S. Environmental Protection Agency).   1993b.   International
            Anthropogenic Methane Emissions: Estimates for 1990, Report to the
            Congress, prepared by the Office of Policy, Planning and Evaluation,
            EPA, Washington, D.C.

    USEPA  (U.S.  Environmental  Protection  Agency).   1995.    Economic
            Assessment of the Potential for Profitable Use of Coal Mine Methane:
            Case Studies  of  Three Hypothetical U.S. Mines, prepared  by the
            Office of Policy, Planning and  Evaluation, EPA, Washington, D.C.

-------
LovenrnerK  Jo.:c.es
:OALBED  VETHANE  GUIDELINES
                              5. IDENTIFICATION AND ASSESSMENT OF KEY
                              GOVERNMENT POLICIES
                                  THE government can play an important role in developing domestic coal
                                  mine methane resources. The policies that it formulates can promote or
                              hinder the recovery and use of this clean energy source.  The purpose of this
                              section is to: 1) identify the key policies that will affect the development of coal
                              mine methane projects; and 2) assess whether these policies pose  barriers
                              that must be overcome  or are potential leverage  points to promote project
                              development.  Although  there are various policies that can encourage coal
                              mine methane projects,  it  is not possible to recommend a general set of
                              policies for every circumstance.  Rather, policies must be tailored individually
                              to suit each country.
                              5.1  National Energy Pricing, Subsidies, and Taxes

                              A primary barrier to coal mine methane recovery and use in both developing
                              and developed countries is often artificially low energy prices.  Conditions
                              influencing electricity and  natural gas  prices, such as  government energy
                              policies and subsidies, can have an important effect on the economic viability
                              of coal mine projects.

                              Energy subsidies can both help and  harm coal mine methane recovery and
                              utilization projects.  Artificially low energy prices can pose a  barrier to coal
                              mine methane utilization. If the prices  of natural gas, oil, and coal are less
                              than the cost of producing coal mine  methane, it will be difficult to develop a
                              profitable coal  mine methane  project.  Using market prices  for natural
                              resources would allow coal mine methane to compete fairly.  If even under
                              market prices coal  mine  methane is uncompetitive, however, the government
                              may offer tax credits or other financial incentives to encourage these projects
                              because of their environmental and safety benefits.

                              Energy taxes must also be assessed for their impact on gas recovery projects.
                              Energy taxes based on fossil carbon content would give recovered  methane
                              an edge over coal  and oil. Similarly, higher taxes on imported energy would
                              allow domestic  coal mine methane to be more competitive.  Depending on a
                              nation's energy goals, the tax structure may prefer one source  of energy over
                              another.

                              For example, in the United States, several federal, state, and local incentives
                              are available for coal mine methane  projects, such as the Internal  Revenue
                              Service (IRS) Section 29 Tax Credit (see Exhibit 5-1).

-------
COALBED  VLTHA.NE
GUIDELINES
0 oven men;.  . o.:c:es
                                                                                                POLICIES
    5.2 National Energy Supply Priorities

    The nation's energy supply goals will  help determine the emphasis placed
    upon coal mine methane development  There are two main national energy
    concerns that may affect coal mine methane promotion: supply security and
    increasing domestic demand.

    Many nations are concerned about relying on foreign sources of energy.  The
    most notable example is reluctance of many nations to depend on oil and gas
    from unstable regions.  Because the price of natural resources has a great
    impact on a nation's economy, and domestic sources of energy are considered
    to be more stable, many  nations share the common goal  of increasing
    domestic natural resources.  Therefore, nations may choose to encourage coal
    mine methane recovery and utilization  to expand their domestic supply of
    energy.

    For nations where energy demand is growing rapidly and there are shortfalls in
    supply, energy policy may include the development of coal mine  methane to
    help meet the  nation's energy  needs.   For example,  in  many developing
    nations, the shortage of energy has slowed down the process of electrification
    of towns  and villages.  The use of coal mine methane as  a fuel to generate
    electricity could  help to meet the goal of universal electrification. Furthermore,
    the use of domestically produced energy will decrease the amount of foreign
    exchange required to import energy.  Many developing countries and those
    with economies in transition face a shortage  of foreign  exchange.  Coal
    restructuring may force uneconomic or unsafe coal  mines to close down, which
    may cause some economic hardships.   However,  the benefits that coal mine
    methane  recovery produces, including jobs and safer, more profitable mines,
    can offset the losses.

    If coal  mine methane recovery and utilization  is consistent with a nation's
    energy supply priorities, it may be easier to create policies to promote  its
    development.    For example,   a  detailed  resource assessment  may be
    undertaken or information on technologies, financing, and pertinent policies
    can be made publicly available.  If, however,  a nation has ample quantities of
    domestically produced energy, it may not involve itself in the issue simply for
    the  purpose  of expanding energy supplies.    Rather,  in  such cases,
    environmental goals may be more important.
                                                        Exhibit 5-1: U.S. Internal Revenue
                                                        Service (IRS) Section 29 Tax Credit

                                                        This  is  a  U.S.  federal  tax credit for
                                                        producing energy from non-conventional
                                                        sources, including coal mines. This tax
                                                        credit applies to wells drilled before 1992
                                                        and will expire on January 1,2003.  When
                                                        the tax credit was established in 1979, the
                                                        value of the credit was set at $0.52 per
                                                        thousand cubic feet of gas. The value of
                                                        the credit changes annually, depending
                                                        on a number of factors,  including  the
                                                        domestic oil price and the inflation rate. In
                                                        1994,  the  credit  equaled  $0.90  per
                                                        thousand cubic feet of gas.
    5.3 Environmental Goals

    A nation's environmental goals will also play a large role in determining the
    importance given to coal mine methane projects. Coal mine methane may be
    encouraged when  environmental  issues are placed highly on  the  national
    agenda.  The two main  issues concerning  environmental policy and  their
    impact on coal mine methane can be divided into a global concern and a
    local/national concern.

-------
r\ev Liovernnneni ru.c.es
:OALBED VETUAXE GUIDELINES
                                    As explained in Chapter 2, methane is a greenhouse gas, affecting the global
                                    environment. If a nation has an active interest in reducing methane emissions,
                                    it may promote the recovery of methane from coal mining.

                                    Both national and local environmental policy may  call for the use of cleaner
                                    fuels to reduce local pollution and for the clean up  of water discharged during
                                    mining. Coal mine methane can be used to displace more polluting fuels, such
                                    as coal or oil.   Methane has several advantages over other fossil fuels.
                                    Emissions  of  S02, NO,, and  particulates can  be reduced through the
                                    displacement of coal (and to a  lesser degree oil) with gas.   Natural gas
                                    combustion  produces no  802  or paniculate emissions,  and lower  NO,
                                    emissions.

                                    Coal mine  methane can also  be used to treat mine water  before  it  is
                                    discharged into rivers or used for other purposes. The disposal of this water is
                                    a significant local environmental  problem in many countries.  As  described
                                    above, a  demonstration project is underway at the Morcinek mine in Poland
                                    that involves using coal mine methane for this purpose.
                                    5.4  Financing

                                    In order  to  assess the impact of government  investment polices on the
                                    financing  of  coal mine methane projects, one must look at both the overall
                                    investment regime and the financial regulations specifically concerning coal
                                    mine methane. When studying the overall regime, it is necessary to look at the
                                    corporate  tax  structure, import and export taxes  and quotas,  and  laws
                                    concerning foreign ownership.  Low limits on foreign ownership and a high
                                    corporate tax structure in comparison to other nations with potential coal mine
                                    methane projects may pose barriers to foreign investors.  In cases in which the
                                    equipment must be imported from abroad, high  import duties will place a
                                    burden on both domestic and foreign investors.

                                    The government also may have financial regulations dealing specifically with
                                    coal mine methane. For example, low interest loans, tax credits, loans, grants,
                                    and subsidies for coal mine methane projects will ease the financial burden on
                                    the investor.  As mentioned above, the use of such incentives will depend on
                                    the overall energy and environment goals of the government.

                                    For example, in the  U.S., many state  governments provide grants or low
                                    interest loans to projects that improve the environment or increase the local
                                    supply of clean fuels.  As coal mine methane projects can do both, they may
                                    be eligible to receive various  types of  state  funding.   Examples of  such
                                    programs include one by the Pennsylvania Energy Development Authority that
                                    provides loans and grants for the development of new sources of energy, as
                                    well  as the  Indiana  Recycling and Energy Development  Program, which
                                    provides  assistance for the development of  new energy  resources  and
                                    recycling programs.

-------
OAL13ED VETIME GUIDELINES
.-\ev
o..c:es
                                                                                             POLICIES
   5.5 Technology Development

   As some of the technologies associated with coal mine methane recovery and
   utilization may not be  available in many nations, the government's policy
   towards the development of technology is important to assess.   There  are
   various ways in  which  the government can encourage the development of
   technologies specific to coal mine methane projects:

   •      Encourage foreign participation in coal mine methane projects.
          This would allow foreign technology to be introduced without requiring
          domestic capital.   Foreign participation,  however may bring forth
          issues of ownership of the recovered methane.  These arrangements
          may thus require detailed contracts regarding use and rights of both
          parties involved, discussed further in section 5.6 below.

   *      Lower  import  duties,  taxes, and restrictions  on  required
          technologies, thereby reducing the cost  of a coal mine methane
          project.

   •      Fund demonstration projects at domestic  mines  to allow  the
          industry to see  and understand new technologies.

   •      Organize study tours and training trips abroad for key personnel
          so that they may leam from the experiences of other nations.

   •      Finance research and development into  recovery and use methods
          to assist the local industry.

   If technology is a strong  barrier to the  development of coal mine methane
   projects, government policies that encourage the transfer of technology and
   the development of  local  technology can help promote these projects.  An
   important part of technology transfer that must not  be overlooked is the need
   to ensure the safety of those using the equipment. Governments could involve
   safety  and certification agencies to examine and evaluate the technology; in
   some cases a formal licensing or approval process could be established.
  5.6 Concession Process
  Through the granting of natural  resource concessions, governments can
  encourage project  development.   In granting a concession, a government
  authorizes a developer to extract and sell a natural resource.  Typically, the
  grantee pays to obtain the concession, and often is required to pay a royalty
  based on the amount of resource extracted.

  There are two main issues that must be analyzed in this process. First, before
  the concession process can begin, the issue of ownership of the coal mine
  methane must be resolved.  If natural resources are  owned by the private
  sector, coal mine methane resources can belong to the owner of the surface

-------
\'ev Governme.ii  :jo.:c:es                                             COALBED V.ETHANE GUIDELINES
                                    rights, the owner of the coal rights, or the owner of the oil and gas rights.  If
                                    natural resources are nationalized, it may be uncertain whether the national or
                                    regional government has the authority to grant concessions. This uncertainty
                                    can prevent projects from being developed.  Furthermore, in nations in which
                                    the natural resource  sectors are  being  privatized, the laws  concerning
                                    ownership may be in flux.

                                    The second matter concerns the clarity, efficiency, and stability of the actual
                                    concession  process.   A long, complex concession process can  act as  a
                                    deterrent to investment in coal mine methane resources.  Common problems
                                    faced by investors include delays in the decision making process, confusion
                                    over who is in charge, sudden changes in regulations, and the reversal of
                                    decisions.   These problems  are exacerbated in  nations where all  natural
                                    resources were previously owned by the government and  the  concession
                                    process  is still  being  formulated.  The following questions  are  useful in
                                    determining whether the current concession process may be a potential barrier
                                    to project development:

                                    •      Who should be contacted for questions concerning various steps of
                                           the concession process? Is it clear exactly who is in charge of what
                                           step and are those persons easily accessible?

                                    •      How long does the concession process take?

                                    •      Once a decision has  been  made, what is the likelihood of it being
                                           overturned?

                                    Clear laws concerning coal mine methane ownership and a clear, efficient, and
                                    stable concession process will help to promote coal mine methane projects.
                                    5.7  References

                                    USEPA  (U.S.  Environmental  Protection  Agency).   1993.   Anthropogenic
                                            Methane Emissions in the United States, Report to the  Congress,
                                            prepared by the Global Change Division, Office of Air and Radiation,
                                            EPA, Washington, D.C.

                                    USEPA  (U.S.  Environmental  Protection Agency).   1994.    International
                                            Anthropogenic Methane Emissions: Estimates for 1990, Report to the
                                            Congress, prepared by the Office of Policy, Planning and Evaluation,
                                            EPA, Washington, D.C.

-------
:OAL GUIDELINES
\ex. SI
  6. NEXT STEPS
          section outlines the next steps for evaluating and implementing coal
     mine methane recovery and utilization projects in developing countries and
  countries with economies in  transition.  The steps encompass a  range of
  initiatives that may  be tailored to meet individual country objectives.  These
  initiatives are divided into the following five main areas:

  •      Focus on the Most Promising Projects.  This section presents next
          steps for focusing on the most promising coal mine methane projects
          in your country.

  •      Availability of  Technology and Expertise. This section  identifies
          approaches for assessing whether the  technology  and expertise
          required for implementing projects are available.

  •      Decisionmaker Motivation.  This section presents approaches for
          motivating decisionmakers to undertake coal mine methane recovery
          and utilization projects.

  •      Resolution of  Regulatory  Issues.   This section lists regulatory
          issues that should be examined to assess whether existing policies
          hinder or  further  the goal of implementing coal mine  methane
          projects.

  •      Funding. This section identifies possible sources of funding for these
          next step activities.

  Exhibit 6-1 summarizes how  this  chapter  can be used  to  meet various
  objectives. The first column lists several common  objectives and the second
  column lists the chapter section to consult.
  6.1  Focus on the Most Promising Projects

  Although the site screening and preliminary assessments discussed above in
  chapters 3 and 4 may show  that a variety of promising  projects  exist, the
  available data may be insufficient for identifying the most promising project
  opportunities.   In particular,  if there are a  large number of gassy mines,
  detailed site-specific information on all the sites may not have been collected
  in the screening step  (chapter 3) because of the level of  resources that are
  required.  This section provides guidance for collecting additional site-specific
  information that will enable prefeasibility assessment activities to be focused
  on the most promising opportunities. This initiative is only required when there
  are a large number of potential sites that need to be evaluated.

-------
                                                        :OAL GUIDELINES
Exhibit 6-1: How to use this Chapter
Objective: i Section to Consult:
To focus on the most promising
coal mine methane projects.
To assemble the technology and
expertise needed to develop
coal mine methane recovery and
utilization projects.
To motivate derisionmakers to
invest in and implement coal
mine methane projects.
To identify and eliminate
regulatory barriers.
•
To obtain funding for program
development or project
implementation.
Section 6.1 - Focus on the Most Promising
Projects summarizes steps for collecting
additional data on candidate sites to better
focus efforts.
Section 6.2 - Availability of Technology and
Expertise presents steps for identifying and
filling gaps in the availability of technology and
expertise needed to develop projects.
Section 6.3 - Motivate Decisionmakers
presents options for assisting decision makers
and providing incentives.
Section 6.4 - Resolution of Regulatory
Issues discusses those policies and regulatory
structures that should be reviewed to identify
potential barriers.
Section 6.5 - Funding presents candidate
funding sources that can be consulted.
To collect this information, a specific program activity should be defined with
data collection as its objective.  Such an initiative was conducted in the United
States to  identify the most promising coal mine  methane opportunities (see
Exhibit 6-2). Section 6.5 describes funding sources that may be contacted to
obtain funding for these types of activity.  A sample five step program plan for
collecting the necessary data is as follows:

Step 1:  Define Minimum Information

The first task is to define the minimum information that is required for each
coal mine. As discussed in Chapter 3, the three primary factors that makes a
site a promising opportunity for gas recovery and use are 1) coal production of
at least 0.3 million tons of coal annually, 2) methane emissions of at least nine
cubic meters per metric ton of coal  produced, and 3) a remaining life span of
at least five years. Therefore, it is recommended that this information collection
effort focus on obtaining the best possible information on three factors:

•      The number of tons of coal produced annually;

•      Methane emissions per ton of coal mined; and

•      Remaining mine lifespan.

-------
COAL
GUIDELINES
                                                                                                   \exi Sieos
    Exhibit 6-2:  US EPA Coal Mine Profiles Project

    The  US EPA Coal Mine  Profiles  Project was developed to identify the most
    promising coal mine methane  project  opportunities in the United  States.  This
    information is  being provided to coal mine owners and operators, electric utilities,
    natural gas pipeline companies, state and local government officials, and potential
    project developers. Based on publicly available data collected primarily from state
    and federal reports and industry press, a minimum data set was developed for large
    and gassy mines from which a profile is created. These profiles are then used to
    identify those mines that may offer attractive energy development opportunities.

    The profile for each coal mine has the following information:
             Coal mine location and operating status;
             Coal production;
             Methane emissions;
             Energy potential of the methane (including the amount of electricity that
             may be generated from the recovered methane);
             Existing methane recovery and use;
             Distance from mine to a pipeline;
             Nearby institutional or industrial .facilities; and
             Contact information (i.e., coal mine owner/operator).
    Based on this information, the gas recovery and use potential and associated
    environmental and energy benefits from a potential project are estimated. These
    profiles are currently available from the US EPA for over 80 mines in 10 states.
   Additional  information  on  energy  needs surrounding  the coal  mine  and
   potential consumers in the area may also be collected if the information is
   readily  available.   Since  methane can be  used at the  mine  itself,  this
   information is not on the list of the minimum information required.

   Step 2: Define the Data Collection Method

   The purpose of this second step is to define how the data  will be collected.
   Options may include working with local government officials who collect  coal
   production and methane emissions data or surveying individual coal mines to
   collect  or estimate this data. The techniques to be used to collect the  data
   should  be selected based on the type of information most likely to be available
   and the resources available for collecting the data. It may be appropriate to
   test  several different  data  collection  methods  before  settling on   the
   recommended approach.

   Step 3: Develop a Data Handling System

   The purpose of this third step is to develop a system for handling the coal mine
   data.   A  database program  can be  used to  organize the data  so  the
   subsequent  data analysis  and  evaluation is facilitated.   Data handling and
   quality control procedures should be  developed as part of this step, including
   checking the accuracy of both the data collection and data entry activities.

-------
\exi s\eos                                                                             COAL GUIDELINES
                                    Step 4: Collect the Data

                                    In this step the program personnel collect the data according to the method
                                    defined in step  2.  The data are entered into the data system developed in
                                    step 3.

                                    Step 5: Analysis and Recommendations

                                    Based on the data collected, the gas recovery and use potential for candidate
                                    coal mines is  estimated (Chapter 4  presents equations for estimating gas
                                    recovery). The most promising project opportunities will be those that produce
                                    the most gas in areas that can use the energy.  A list of the most attractive
                                    projects can be created, along with the information available on each.

                                    Once the most promising opportunities are identified, this information can be
                                    disseminated to potential project developers to promote the projects (see
                                    section 6.3).
                                    6.2  Availability of Technology and Expertise

                                    Specific technical expertise is required to plan and  implement coal mine
                                    methane  recovery and  utilization projects.   Additionally,  access  to  and
                                    experience with specialized drilling and gas monitoring equipment are needed.
                                    The absence of the necessary expertise and equipment can be a significant
                                    barrier to the implementation of these projects. This issue may be particularly
                                    important in developing countries and countries with economies in transition
                                    because technical and labor resources may not be available to construct and
                                    operate the projects.

                                    Once it has  been determined that promising opportunities exist, necessary
                                    expertise and equipment should be located.  Ideally, one or more local experts
                                    with coal mine methane recovery and use expertise should be identified.  For
                                    example, a request for qualifications can be issued to identify local or regional
                                    individuals and organizations with the necessary expertise.

                                    In some cases a coal mine methane expert familiar with the latest technologies
                                    may  not exist in the nation. In this circumstance, a program can be organized
                                    to train local personnel in the detailed aspects of coal mine methane recovery
                                    and utilization. Training programs could include visits to existing projects in
                                    other countries as  well as  inviting  experts  from other countries  to  give
                                    seminars.

                                    To augment  local expertise, nations may wish to contact foreign companies
                                    with  the expertise necessary to complete the project.  Foreign involvement
                                    may  take any of a variety of forms, including the build-operate-transfer (BOT)
                                    financing model. The BOT is currently  being used for various infrastructure

-------
:OAL GUIDELINES
Nexi S;eos
  projects  in developing countries and is applicable for coal mine methane
  projects as well.  Such arrangements with foreign companies allow technology
  to be introduced without requiring the use of domestic capital. For countries
  that have limited or no experience with  coal mine methane recovery  and
  utilization, this  may  be an attractive short-term option.   Appendix A  lists
  selected U.S. coal mine methane development experts available to provide
  training or participate in project development.
  6.3 Motivate Decisionmakers

  Because coal mine methane recovery and utilization projects are relatively
  new in many countries, steps to motivate decisionmakers may be necessary to
  get promising projects built.  Examples of decisionmakers include coal mine
  owners, government officials in the energy and environment ministries, and
  potential project developers.   In addition to financial incentives, several
  targeted initiatives have proven effective for both raising  awareness regarding
  the benefits of such projects, as well as creating the nucleus  of interested
  parties  needed to  create  a viable  project.   Three  main initiatives are
  recommended to provide the information needed to motivate decisionmakers:
  outreach activities, demonstration projects, and information clearinghouses.

  6.3.1 Outreach Activities
 Because the concept of recovering and utilizing methane from coal mines may
 be unfamiliar, outreach activities may be required to educate and motivate the
 community and its  leaders on the  technology and  benefits  of coal mine
 methane projects.  Outreach should be targeted to the following parties:

 •      Coal mine owners and operators, who may not recognize  the
         resource they have;

 •      Potential users of coal mine methane, who may not recognize the
         opportunity to obtain low cost energy;

 •      Energy planners, who may not recognize how energy from coal mine
         methane can contribute to meeting local energy needs; and

 •      Environmental and community groups,  who may not be aware of
         the environmental and safety benefits  of coal mine methane projects.

 Outreach activities to educate and motivate these parties must be defined in
 terms of the message that is being delivered and the mechanism that is used
 to deliver the message.  The message must include the information needed to
 educate and motivate each target group.  The information must be presented
 in a way that each target group can  understand, and  must be delivered in a
 manner that ensures that each target group receives and assimilates  the

-------
\exi
COAL
GUIDELINES
                                         Exhibit 6-3: The US EPA Coalbed Methane Outreach Program

                                                           EPA's Coalbed Methane Outreach Program encourages the
                                                           use of coal mine methane as an energy resource. EPA enlists
                                                           the support of coal mine owners and operators, electric utilities,
                                                           state agencies, private financiers, and project developers to
                                                           reduce  methane  emissions from  coal  mines through the
                                                           development of profitable energy recovery projects.

                                        The Coalbed Outreach Program promotes coal mine methane  recovery and use
                                        projects in the U.S. as well as in countries such as Russia, China, Poland, and
                                        Ukraine. Projects undertaken by the Program in the U.S. include:

                                        •    Profiles of the gassiest mines in the nation (these profiles are discussed above);
                                        •    Guides to possible sources of funding for coal mine methane projects in  West
                                             Virginia and Pennsylvania, two state with several gassy mines;
                                        •    Study of the barriers facing coal mine methane projects and possible solutions to
                                             these barriers; and
                                        •    Detailed technical and financial feasibility assessment for potential coal  mine
                                             methane project developers.

                                        To  promote coal mine  methane projects abroad,  EPA has  helped establish
                                        clearinghouses in Poland, Russia,  and  China. EPA has also written reports on the
                                        coal mine methane potential of these nations and has profiled some of the gassiest
                                        mines.  At present EPA is working with the Chinese Coalbed Methane Clearinghouse
                                        to develop a financial model to evaluate coal mine methane projects in China.
                                      information.    Because  each  target  group  is different,  separate  outreach
                                      strategies may be needed for each.

                                      For example, outreach to national planners and decisionmakers may employ
                                      existing  decisionmaking processes.   Alternatively, outreach to local officials
                                      responsible for the local coal industry may require  seminars, training sessions,
                                      or technical guidebooks to inform them of the coal  mine methane recovery and
                                      utilization opportunities.  Options for reaching potential foreign partners may
                                      include conducting studies through international funding agencies (discussed
                                      below in section 6.5) or issuing requests for  proposals for specific projects or
                                      studies.  Exhibit 6-3 summarizes the outreach program currently being used in
                                      the United States to reach these various groups.
                                       Exhibit 6-4: Demonstration Project in Russia

                                       During its visit to Russia in 1995, the EPA identified a demonstration project at the
                                       Kirov mine in the Kuzbass coal basin.  This project would use methane recovered
                                       from the  degasification systems to fuel the three central boilers.  At present, these
                                       boilers run  on coal.  Currently, EPA is preparing a project opportunity report on this
                                       project. This report will be distributed to potential lenders.

                                       The successful implementation of this  demonstration  project  will facilitate the
                                       development of other coal mine methane projects in Russia.	

-------
COAL
GUIDELINES
Ne'xi Sieos
   6.3.2   Demonstration Projects

   Sometimes information is not enough to promote the use of a new technology.
   Users may want to see the technology in use. Demonstration projects are an
   effective tool to test and promote the effectiveness of  coal mine methane
   recovery and use projects, especially in developing countries and countries
   with economies in transition where such  projects may  be uncommon.  By
   providing analysis,  technical  support,  and funding,  the government can
   facilitate projects to serve as examples for the industry as a whole.

   In selecting projects  to support and  promote, several criteria should be
   considered, including: choice of technology, time frame for the project, type of
   government  assistance  required,  and  how  projects  will  promote the
   government's goals.  In most cases,  after a  specific  project  is selected,
   technical and financial analyses will be  required  to evaluate the effectiveness
   of the technology, as well as its costs and benefits.

   Upon completion of the demonstration project, the results of the project must
   be   summarized,  including  both  positive  and  negative  aspects  and
   recommendations for improvement. This information must be disseminated to
   promote the technology.  The demonstration site itself can then be used for
   training and education purposes.
  6.3.3 Information Clearinghouses

  To  provide  owners, developers, regulators, and  other stakeholders  with
  comprehensive information concerning  all aspects of coal mine  methane
  recovery and utilization  technology, finance, and economic development, a
  central   information  clearinghouse   could  be  established.  Information
  clearinghouses provide  a  central location for  information where current
  environmental,  technical,  financial,  and  business contact information  is
  available.

  The clearinghouse can function at the national level of the  country and can
  involve  professionals from  leading research and development laboratories,
  educational institutes, industries, and  other organizations.  The clearinghouse
  can strengthen the existing infrastructure  of national  and regional bodies
  involved in the training,  information dissemination and implementation of the
  programs in energy efficient technology. It can also facilitate training programs
  and interactions with local and international experts.

  The clearinghouse can also assist in developing the technical capabilities  of
  non-governmental organizations, consultants, industry associations, and any
  other groups engaged in  the promotion of energy efficiency activities.  This can
  be done by conducting regular training programs (both in the field and in the
  classroom},  thereby exposing the  participants to  the  latest  tools  and
  techniques.

-------
\ex-  S:eos                                                                              v#AL C-UIDELINCS
                                   At a minimum, the information clearinghouse should contain information in the
                                   following areas:

                                   •       profiles of gassy mines;
                                   •       current technologies and new research;
                                   •       coal mine methane ownership laws;
                                   •       permitting requirement;
                                   •       applicable energy purchase rules (if any);
                                   •       international and domestic capital/funding sources; and
                                   •       government energy development policies.

                                   An automated index of  all  materials  could be made available electronically
                                   through a bulletin board, or as a "fax-back" system.  A collection of hardcopy
                                   materials could also be assembled for use by anyone interested in coal mine
                                   methane projects. US EPA  has helped establish three clearinghouses abroad.
                                   A  description of these clearinghouses along with their contact information is
                                   presented in Exhibit 6-5.
                                   6.4    Review Regulatory Framework

                                   Regulatory barriers are key obstacles facing potential coal mine methane
                                   projects in  many  developing  countries and countries  with  economies in
                                   transition.  In many of these nations, the regulatory frameworks do not address
                                   issues related to coal mine methane recovery and use projects. This is not
                                   unusual, given that such projects may be relatively new in these countries.

                                   There are many types of regulatory barriers that a project may face.  For
                                   example, local, state, and national ownership and permitting legislation can
                                   obstruct coal mine methane projects.  Artificially low energy prices can pose a
                                   barrier to coal mine methane utilization if the prices of alternative fuels are less
                                   than  the cost  of coal mine methane.  Furthermore,  in most developing
                                   countries

-------
Exhibit 6-5: Coalbed Methane Clearinghouses


  The Polish Coalbed Methane Clearinghouse

The   Polish  Coalbed  Methane  Clearinghouse,
established in January, 1991, is part of the Polish
Foundation for  Energy Efficiency  (FEWE) and is
jointly sponsored by the FEWE and the US EPA.
The clearinghouse provides consulting services to
public- and private-sector clients (e.g., assisting
contractors with pre-feasibility studies on directional
drilling and gob gas recovery), hosts workshops,
and publishes journals, brochures, and newsletters
(e.g.,  the Silesian Coalbed  Methane Newsletter).
Together,  EPA and  the  Polish  Clearinghouse
prepared  a report entitled  "Reducing Methane
Emissions from Coal Mines in Poland: A Handbook
for .Expanding  Coalbed  Methane  Recovery and
Utilization in the Upper Silesian Basin."  This report
profiles the top candidate mines  in Poland,   For
more information, contact:

              Jan Surovka, Director
      Polish Coalbed Methane Clearinghouse
               ul. Powstancow41a
            40-024 Katowice, Poland
             48-3-10355114 (phone)
              48-3-10355120 (fax)
   Chinese Coalbed Methane Clearinghouse

The Chinese Coalbed Methane Clearinghouse was
established  in  August  1994  in  Beijing.   The
Clearinghouse is part of  the  Ministry of Coal
Industry's (MOCI) China Coal Information Institute
and is jointly funded by the MOCI and the US EPA.
Activities of the  Clearinghouse include  providing
consulting   services,   hosting  seminars   and
conferences, and  publishing the  journal China
Coalbed Methane in both English and Chinese.  In
a joint report with EPA entitled "Reducing Methane
Emissions from Coal Mines in China: The Potential
for   Coalbed   Methane    Development,"   the
Clearinghouse   has    profiled    coal   mining
administrations that have the top candidate mines
for  coalbed methane  projects.    For further
information, contact:
           Mr. Sun Mayouan, Director
     China Coalbed Methane Clearinghouse
               21 Hepingli Beijie
                P.O. Box 1419
             Beijing 100713, China
            86-10-420-1328 (phone)
              86-10-421-5187 (fax)
         adb310@istic.sli.ac.cn (email)
    Russian Coalbed Methane Clearinghouse

The Russian Coalbed  Methane  Clearinghouse
opened in 1995 in Kemerovo.  It is located at the
Russian  Institute of Coal  and  is affiliated with
Partners in Economic Reform (PIER) and the U.S.
EPA. Like the other Clearinghouses, the Russian
Clearinghouse is promoting the development of
coal mine  methane  projects  by disseminating
information.  It assisted the U.S. EPA in preparing a
report entitled The Potential for Coalbed Methane
Development" which includes profiles of the  top
candidate mines.    The Clearinghouse is  also
working  with EPA  to  develop a  demonstration
project'at the Kirov mine (see  box above).   For
further information, contact:
           Dr. Oleg Tailakov, Director
    Russian Coalbed Methane Clearinghouse
                Institute of Coal
                  Room 208
              Rukavishnikova 21
           Kemerovo 65061, Russia
        root@tailak.kemerovo.su  (E-mail)

-------
\exi Sieos                                                              COALBED VCTIIANC GUIDELINES
                                    and countries with economies in transition, all major power and natural gas
                                    producers and distributors are or have been State-owned. Privatization of the
                                    energy industry is only recently occurring in many countries; therefore, the
                                    concept of private, independent power producers or private gas producers may
                                    be unfamiliar (Watts, 1995).   These, and other barriers,  are  discussed in
                                    Chapters.

                                    The following is  recommended to review the  regulatory framework for coal
                                    mine  methane  recovery and  utilization:   identify and  evaluate existing
                                    regulations;  develop feasible options for removing  barriers  that will not
                                    compromise  other  regulatory  objectives;. and  implement the  necessary
                                    changes.
                                    6.4.1 Evaluate Existing Regulations

                                    To evaluate the  existing situation, the relevant laws, rules, regulations,  and
                                    policies must first be identified  and summarized  by conducting literature
                                    reviews and contacting  appropriate regulatory and legislative experts.   In
                                    addition, attention must be paid to institutional arrangements.  The following
                                    steps should be undertaken:

                                    •      Step 1:  Identify Decisionmakers.  The purpose of this step is to
                                            identify the key decisionmakers involved in the approval of coal mine
                                            methane  projects.   These  decisionmakers  may  include local,
                                            provincial, or national regulatory bodies that are involved  in coal
                                            production,  land  ownership,  energy  production,  financing,  and
                                            equipment purchasing/importing.

                                    •      Step 2:  Identify Decision Criteria.  The purpose of this step is to
                                            identify the decision criteria used by the key decisionmakers and the
                                            underlying objectives they are trying to achieve.  This information
                                            would be obtained principally through contacts with the  relevant
                                            agencies and institutions  in the country.

                                    •      Step 3:  Identify Typical Project Development Path.  The purpose
                                            of this step is to describe the typical path that a project would take in
                                            order to  be developed. A concise listing of the major steps in getting
                                            the project  defined,  approved,  financed,  and  built should be
                                            developed  based  on discussions  with  the  relevant  institutions
                                            involved. This summary of the project development path could then
                                            be  used to promote the implementation of coal mine methane
                                            projects.

                                    The  results of the above steps should be compiled in a concise summary
                                    report highlighting the policies and current practices affecting gas recovery and
                                    use the options available to the government to reduce the barriers to projects.
                                    Any  policies or requirements that significantly add to the cost  of the  project,

-------
'OALBED V.ETHAN'E GUIDELINES
                                                                                            Nexi Sieos
  create uncertainty in the viability of the project, or delay its implementation
  should be identified as major barriers requiring further analysis.
  6.42 Develop Feasible Options

  The purpose of this section is to develop available options for overcoming any
  major barriers identified above.  The options selected will be those that most
  effectively promote the government's development objectives and are feasible
  in terms of political acceptance, effectiveness, secondary impacts, costs, and
  legality.

  An  Evaluation Team  consisting of the  decisionmakers  and  participants
  involved in coal mine methane recovery and utilization can be established as a
  working  group to  guide this process,  This group would  be charged  with
  ensuring  that  the recommended options incorporate  the views  of the
  representative stakeholders in each area. At a minimum, the Evaluation Team
  should include the following groups:

  •       Regulatory Community:  municipal agencies, local  government
          regulators, ministries in charge of power, coal, natural gas, and the
          environment, and others;

  •       Owner, Operator, and Developer Community:  coal mine  owners
          and operators, recognized local, national, or international coal mine
          methane project developers; and

  •       Financial  Community:  local, national, or international grant/loan
          agencies and venture capitalists.

  The assessment of available options will involve considerable debate on which
  options can  be implemented without compromising other pressing national
  priorities. As such, proposed  regulatory changes must be viewed in the context
  of their impact on other national priorities.
  6.4.3 Implement Options

  Using the input and recommendations of the Evaluation Team, the options or
  optimum mix of options can be implemented.  The implementation strategy will
  depend on the type of  option to be implemented.   Implementation strategy
  options include, among others:

  •       legislative/regulatory  actions  (environmental,  safety,  ownership,
          import restrictions);

  •       administrative  and  executive  actions  (committees,  meetings,
          conferences);

-------
                                                                              OALBED VETIIANC GUIDELINES
                                    •       inter-governmental liaison actions (local,  municipal, national, inter-
                                            national); and

                                    •       outreach (training programs, demonstration projects, etc.)

                                    The above options must be evaluated on an ongoing basis in terms of their
                                    ability to promote promising projects. A structured program of data collection
                                    for monitoring the progress of the objectives may be developed in this regard.
                                    Once data has been collected, reviewed, and analyzed, an evaluation of the
                                    impact of the option  can be  made and the established  objectives can be
                                    retained or modified as appropriate.
                                    6.5    Obtain Project Funding

                                    Each of the activities discussed  above  requires resources, as  does  the
                                    implementation of individual projects.  This section lists steps for obtaining
                                    assistance from international funding agencies for these initiatives.  The key
                                    steps are to review the  types  of assistance available,  identify  funding
                                    requirements, and select specific source(s) of funding.  Once the appropriate
                                    source of funding has been identified, a project proposal can then be prepared
                                    in accordance with the specific criteria of the funding agency.
The  first  source of  funding  that
countries should consider is forming a
partnership  with  local and  foreign
private  sector project  developers.
This method is often the quickest and
cheapest method of obtain funding.
However,  such  funding  is  only
available for projects that are dearly
profitable.  For projects with a lower
economic rate of return, funding may
be   available   from  international
agencies.
6.5.7 Review Types of Assistance Available

The main types of assistance offered by  international funding agencies are
grants, loans, and other packages (including loan guarantees, venture capital
funds, and business consulting assistance).  These types of assistance are
available  to  both governments  and  businesses.   In some  cases, the
government may reallocate the funds to  eligible businesses.   The funds
provided may cover  costs  to  conduct feasibility  assessments,  implement
demonstration projects, or acquire equipment and technical expertise.  The
main types of financial assistance are further described below:

4      Grants.  These are direct monetary payments for specific projects
        that do not need to be reimbursed.  For example, grants may be used
        to develop a demonstration project or to fund a training program  to
        enhance local expertise.

*      Loans.  These are made by the funding agencies directly to the
        eligible parties and  must be paid  back in a specified period of time.
        Typical  recipients of such loans may be government agencies (for
        direct  use  or  reallocation  to  businesses);  or   businesses  in
        manufacturing,  industrial  export/import   services,   or  technology
        development.

-------
"OALBED VETHANE  GUIDELINES
Nexi Sieos
          Other.   Loan  guarantees, venture  capital  funds,  and  business
          consulting services are some of the other types of assistance that are
          offered by these institutions. These are described below:

          •       Loan Guarantees are commitments to repay the lender if the
                  borrower defaults.   In  these  cases,  a  funding agency
                  guarantees its proportionate share of loss in accordance with
                  the percentage of the  guarantee.   Loan guarantees  are
                  important to mitigate risk at projects that have a high degree
                  of uncertainty.

          •       Venture Capital Funds offer loans or equity to support the
                  start-up of  new  businesses  or expansion  of  existing
                  businesses.  Funding agencies  may appropriate funds or
                  generate funds from private investors by selling shares in the
                  company.

          •       Business Consulting Services include technical, managerial,
                  and financial consulting and support  services.   Typical
                  sources of such assistance  are  governments,  multilateral
                  and bilateral agencies, and business- and research-related
                  entities.  Technical services may range from  providing
                  technology transfer to providing engineering assistance to
                  offering  use  of  research  and  development  facilities.
                  Managerial   consulting  includes   offering    seminars,
                  workshops,   and   consultations   on   improving  project
                  operations.   Financial consulting may involve assistance in
                  creating packages to finance a project or group of projects.
  6.52 Identify Funding Requirements

  The type of funding required is driven primarily by two factors: the objectives
  of  the  program,  and the country's resource allocation.  These are briefly
  described below.

  •       Program Objectives. Government programs aimed at exploring the
          opportunities for coal mine methane projects (e.g., by conducting
          feasibility  studies)   would  most  likely  seek  grants  or  other
          concessional funds.  On the other hand, businesses and government
          agencies pursuing profitable projects are eligible  for loans,  loan
          guarantees, and venture capital funding.

  •       Resource Allocation.  The extent of economic development and
          resource endowments for a given country will  determine its financial
          requirements.  Countries with a  low GNP per capita  will typically
          require grants to undertake coal mine methane projects.  Some
          countries may face  difficulty  when securing loans,  if they have
          creditworthiness problems.

-------
\exi Sieos                                                              COMBED  VLTIIANE GUIDELINES
                                   Once the funding  requirements have  been assessed, the next step is to
                                   identify the funding available.
                                   6.5.3 Select Sources of Funding

                                   There are a wealth of possible funding sources which provide assistance that
                                   can  be used for coal mine methane projects. These include  multilateral
                                   institutions, regional development banks, U.S. government agency programs,
                                   country- and region-specific enterprise funds, and other institutions. Exhibit 6-
                                   5 lists funding sources most applicable to coal mine methane recovery and
                                   use projects, and summarizes the types of funding offered by each. Summary
                                   profiles  of the funding agencies are presented  in Appendix B.  The main
                                   categories of funding sources are briefly described as follows:

                                   •      Private  Sector.   Funding may  be available from private  sector
                                           associations or firms interested in coal mine methane recovery.  Such
                                           funding is most commonly available for projects with a high expected
                                           rates  of  return  and usually  takes the form  of a profit-sharing
                                           partnership. This method is often the quickest and cheapest method
                                           of obtaining project funding.

                                   •      World  Bank  Institutions.  The  World Bank  institutions  fund
                                           environmental  and  energy infrastructure  projects in  developing
                                           countries for  which the procurement of technical assistance, civil
                                           works,  materials and equipment, are necessary.   These agencies
                                           provide grants and loans to government ministries and businesses,
                                           which implement projects under local procurement and  contracting
                                           regulations. Examples of such institutions include the World Bank
                                           itself (also  known as the International Bank  for Reconstruction and
                                           Development), International Finance Corporation (IFC),  and  the
                                           Global Environment Facility (GEF).

                                   •      Multilateral Development Banks.  These are international lending
                                           institutions  owned by member countries that  promote economic and
                                           social development in developing member nations by providing Joans,
                                           technical assistance, capital investment, and help with economic
                                           development plans.  Examples of such institutions include the  Asian
                                           Development Bank (ADB), the European Bank for Reconstruction and
                                           Development  (EBRD),  and the  Inter-American Development  Bank
                                           (IDB).

                                   •      U.S. Government Agency Programs.   There  are several  U.S.
                                           government agencies that promote development by funding feasibility
                                           studies, training programs, and seminars in developing countries.  In
                                           most cases,  these  agencies/programs support projects that offer
                                           export or investment potential for U.S. enterprises.  Examples of such

-------
COALBED  VETHANE GUIDELINES
Nexi Sieos
          agencies/programs include the Trade  Development Agency  (IDA)
          and the Overseas Private Investment Corporation (OPIC).

   •      U.S. Initiative on  Joint  Implementation (USIJI): The USIJI is a
          voluntary  private program  that  provides  recognition  and  select
          technical assistance  to U.S. companies implementing greenhouse
          gas reduction projects in other  .countries.   While no funding  is
          available through the USIJI, projects that meet the USIJI criteria will
          be  likely to attract U.S. investors  solely on the recognition of USIJI
          acceptance.

   For more information on the types of funding available and sources of funding
   for coal mine methane recovery and use projects contact:

                    U.S. Environmental Protection Agency
                              Methane Branch
                             Mail Code 6202 J
                            401 M Street, S.W.
                          Washington D.C. 20460
                            Tel: 202/233-9768
                            Fax: 202/233-9569

-------
Exhibit 6-5: Summary Table of Promising So
Name of Agency
World Bank Agencies/Programs
International Bank of Reconstruction and
Development (IBRD)
Global Environment Facility
International Finance Corporation (IFC)
Multilateral Development Banks
European Bank For Reconstruction and
Development (EBRD)
Inter-American Development Bank (IDB)
Asian Development Bank (ADB)
Africa Development Bank' (AfDB)
U.S. Government Agency Programs
Trade Development Agency
United States Agency For International
Development (USAID)
Overseas Private Investment Corporation (OPIC)
Export-Import Bank (EXIMBANK) of the United
States
U.S. Initiative on Joint Implementation (USIJI)
ureas of Funding and Other Assistance
Type of Assistance Provided I Comments
Grants j Loans I diner*



	
/



/
7
'

'
J



/

/

/
/
/
/


	
/
/

/
/
/

/
/
/
/

/
/
/
/
/
The World Bank finance capital infrastructure projects through the International Bank for
Reconstruction and Development (IBRD) and its affiliates - IFC,' IDA, and MIGA.
GEF funds the difference between expected project revenues and project costs.
Therefore, GEF funding is ideal for conducting feasibility assessments.
IFC provides loans and other financial packages to private sector enterprises only. The
minimum support provided by IFC is $10 million.

EBRD provides loans, equity, and guarantees to Central and Eastern European countries
for developing into market-based economies.
IDB provides loans for development projects in Latin America and the Caribbean. Grants
are available for poorer member countries.
ADB provides loans for the economic and social advancement of member countries.
Concessional funds are available through special funds established by the ADB.
AfDB provides loans for the economic and social advancement of African countries.
Grants are available for the poorest countries through special funds.

TDA provides funding to projects in developing countries that offer export or investment
potential for U.S. enterprises. The average grant size ranges from $300,000 to $400,000.
USAID's Office of Environment, Energy, and Technology assists in developing market-
based solutions to environmental problems in developing countries.
OPIC provides funding by facilitating U.S. private investment in developing countries
through loans, loan guarantees, and special services.
EXIMBANK provides loans and guarantees to foreign buyers of U.S. goods and services.
The bank finances up to 85% of the U.S. export value.
Projects that meet the USIJI criteria are likely to attract U.S. investors seeking to obtain
recognition and other amenities available to U.S. participants in the USIJI program.
t This includes loan guarantees, venture capital funds, consulting services etc.

-------
COALDED VETHANE GUIDELINES
    6.6  References

    Watts;  Robert A.,  (1995)  Profitable  Market  Opportunities  for Pollution
            Prevention • International Market Opportunities,  Presentation for US
            EPA Atmospheric Pollution Prevention Division Forum, April 10,1995,
            Washington D.C.

-------
OALDED VETHANE GUIDELINES                                          Aooenclx A
  APPENDIX A: DIRECTORY OF SELECT COAL MINE METHANE RECOVERY AND USE
                              EXPERTS IN THE U.S.
               Listing of experts does not constitute endorsement or recommendation for use.

-------
PROJECT DEVELOPMENT
Name j Address
1 . Alternative Energy Development, j 8455 Colesville Road, Suite 1 225
lnc- | Silver Spring, MD 20910
2. Burns and Roe NIS Consortium i 1 400 K Street N.W., Suite 910
j Washington, DC 20005
3. Dominion Energy Advisors I 14389 Emerald Pool Drive
j Centreville, Virginia 22020
4. Energy Resources International, I 1015 18th Street NW
lnc- | Washington, DC 20036
•
;
5. HVS Consulting j 4898 Hartland Parkway
| Lexington, KY 40515
6. ICF Incorporated j 1 850 K St., NW, Suite 1 000
| Washington, DC 20006
7. ICMG / El. Lasseter & Associates j 3610 Watermelon Road
i Suite 104
! Northport, AL 34576
8. I. Havyrluk and Associates j P.O. Box 252
| Carnegie, PA 15106-0252
9. Murray & Associates j 200 Union Blvd.
| Suite 215
| Lakewood, CO 80228-1830
10. Resource Enterprises j 1 245 East Brickyard Rd.
| Suite 170
| Salt Lake City, UT 84106
1 1 . United Energy Development i Park West One, Suite 1 70
Consultants j Pittsburgh, PA 15275

Contact Person
Mathew S. Mendis, President
Tel: (301)608-3666
John Leonhardt
Tel: (202)898-1500
Charles M. Boyer
Engineering Consultant
Tel: (703) 803-6007
David W. South
Vice President
Tel: (202)785-8833
Hilmar von Schonfeldt
Tel.: (606) 272-71 12
Mary DePasquale, Project Manager
Tel.: (202) 862-1 124
Edward L. Lasseter
President
Tel: (205) 759-2046
Ihor Havryluk, President
Tel.: (412) 343-3285
	
Keith Murray
President
Jeffrey Schwoebel, Vice President
Tel. (801) 467-9981
;
Isaias Ortiz
Tel.: (41 2) 787-7880

Area(s) of Expertise
Project Development
Project Development
Project Development
Project Development
Project Development
Project Development; Gas Use
Gas Production, Project Development
Project Development
Project Development
Project Development, Gas Production and Resource Assessment
Project Development
1

-------
GASI

1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
PRODUCTION MO RESOURCE Assessm
Name
Amoco Production Company,
Natural Gas (International)
Bureau of Economic Geology
University of Texas
CD Exploration, Inc.
Conoco, Inc.
CONSOL, Inc.
Enron Exploration Company
GeoMet, Inc.
Gustavson Associates
Halliburton Energy Services
ICMG / El. Lasseter & Associates
j
avr
Address
550 West Lake Park Boulevard
Houston, TX 77079-2696
University Station
BoxX
Austin, TX 78713-8924
5485 Beltline Rd. STE 280
Dallas, Texas 75240
P.O. Box 2197
Houston, TX 77252
Route 1, Box 119
Morgantown, WV
1400 Smith Street
Houston, TX 77002
1 826 3rd. Ave., North
Suite 301
Bessemer, AL 35020
5757 Central Avenue
Suite D
Boulder, CO 80301
Halliburton Center
Suite 2300, 5151 San Ripe
Houston, TX 77056
3610 Watermelon Road
Suite 104
Northport, AL 34576

Contact Person
Bruce N. Erickson
Marketing Advisor
Tel: (71 3): 556 41 28
Andrew Scott
Research Associate
Tel: (512)471-1534
James W. Akers
Mining Engihneer
Tel: (214) 392-1880
John Oehler
Tel: (713)293-6292
Pramod Thakur
Tel.: (304) 983-3207
J.Bradley Williams
Director, Oil & Gas Ventures
Tel: (713) 853-4777
Bret Camp
Senior Vice President
Tel: (205) 425-3855
John B. Gustavson
President
Tel: (303)443-2209
Bruce D. Thomas
Regional Technical Manager
Tel: (71 3) -624-2000
Edward L Lasseter
President
Tel: (205) 759-2046

Area(s) of Expertise
Gas Production and Resource Assessments
Gas Production
Gas Production
•
Gas Production
Gas Production and Resource Assessment
Gas Production
Gas Production
•
Gas Production
Gas Production
Gas Production, Project Development
•
•

-------
GAS
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
PRODUCTION AND RESOURCE ASSESSM
Name
Jim Walters Resources, Inc.
LAHD Energy, Inc.
Lapp Resources, Inc.
North American Drillers
Pennsylvania State University
Pocahontas Gas Partnership
Raven Ridge Resources, Inc.
Resource Enterprises
The River Gas Corporation
Taurus Exploration
Union Texas Petroleum
ENT
Address
P.O. Box 133
Brookwood, AL 35444
P.O. Box 2185
Granbury, TX 76048
4900 Sportsman Drive
Anchorage, AK 99502-4169
Rt. 9 Box 106-C
Morgantown, WV 26505
Hosier Building
Pennsylvania State Univ.
University Park, PA 16802
P.O. Box 200
Mavisdale, Virginia 24627
584 25 Road
Grand Junction, CO 81505
1245 East Brickyard Rd, Suite 170
Salt Lake City, UT 84106
511 Energy Center Blvd.
Northport, AL 35476
2101 Sixth Avenue North
Birmingham, AL 35203-2784
1330 Post Oak Boulevard
P.O. Box 2*120
Houston, TX 77252-2120

Contact Person
Charles Dixon, Senior Vice President,
Engineering
Tel.: (205) 554-6106
David Elliot
Tel: (817)- 326-2562
David W. Lapp!
President Tel: (907) 248-7188
Bill Maloney
President Tel: (304) 291-0175
Jan Mutmansky
Tel: (81 4) 863-1632
Raja V. Ramani
Tel: (814) 863-1617
Randall Albert
Program Manager
Raymond Pilcher, President
Tel.: (970) 245-4088
Jeffrey Schwoebel, Vice President
Tel. (801) 467-9981
Joseph Stevenson
Vice President
Tel: (205) 759 31 88
Walter Ayers, JR.
Senior Exploration Geologist
Tel: (205) 326-2774
R..D LoPiccolo
Project Manager
Tel: (713) 968-2522

Area(s) of Expertise
Gas Production and Resource Assessment
Gas Production
Gas Production
Gas Production
Gas Production and Resource Assessment
Gas Production
Gas Production and Resource Assessment
Project Development, Gas Production and Resource Assessment
Gas Production
Gas Production
Gas Production

-------
GAS USE

1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
Name i
Allison Gas Turbines !
i
AquaTech Services, Inc. j
i
Black Warrior Methane Corp.
;
i
i
•
Energy Systems Associates
Gas Separation Technologies
ICF Incorporated
International Fuel Cells
Michael Baker Engineering Group
Nitrotec Engineering
Northwest Fuel Development
Powerbridge
Address i
P.O. Box 420
Indianapolis, IN 46206
P.O. Box 946
Fair Oaks, CA
P.O. Box 140
Brookwood, AL 35444
300 Gateway Two
Pittsburh.PA 15222-1402
1667 Cole Blvd.
Suite 400
Golden, CO 80401-3313
1 850 K St., NW, Suite 1000
Washington, DC 20006
195 Governors Highway
P.O. Box 739
South Windsor, CT 06074
4301 Dutch Ridge Road
Beaver, Pennsylvania 15009
61 1-M Hammonds Ferry Road
Linthicum, MD
P.O. Box 35833
Canton, OH 44735
3710 Rawlins Street
Suite 1060
! Dallas, TX 75219
Contact Person | Area(s) of Expertise
R.F. Merrion, Director Gas Use
Tel: (317)230-411 j
John Tait, Principal j Gas Use
Tel: (91 6) 723-51 07 j
R.G. Sanders, President/ General
Manager
Tel.: (205) 554-6288 j
Roger Clicked
Tel: 412-392-2390
Gas Use
Gas Use
Jerry Comer Gas Use
Tel: (303)-232-0658
Mary DePasquale, Project Manager
Tel.: (202) 862-1 124
Fax:(202)862-1144
Murdp J. Smith
Tel: (203) 727-2269
Rebecca Rannich
Tel: (412)495-4042
Joseph D'Amico
! President
Tel: (301) 636-7200
Dale R. Jesse
V.P. Engineering
Tel: (909) 736-1 203
James R. Clemments
President
Tel: (21 4) 520-81 77
Project Development; Gas Use
Gas Use
Gas Use
Gas Use
Gas Use
Gas Use

-------
GAS USE
| Name 1 Address
12.
13.
14.
15.
Solar Turbines Inc.
.
Stord, Inc.
UOP
Viking Systems
818 Connecticut Ave., NW
Suite 600
Washington, DC 20006-2702
309 Regional Road South
Greensboro, NC 27409
13105 Northwest Freeway, Suite
600
Houston, TX 77040
20270 William Pitt Way
Pittsburgh, PA 15238
Contact Person
Peter A. Carroll
Vice President
Tel: (202) 293-4327
Jeff Johnson
Tel: (910) 668-7727
Ronald J. Buras
Account Representative
Tel: (713) -744-2881
Jack Saluja
President
Tel: (412) 826-3355
Area(s) of Expertise
Gas Use
Gas Use
Gas Use
Gas Use

-------
APPENDIX B:  DIRECTORY OF POSSIBLE FUNDING
AGENCIES

Profiles of the following funding agencies are provided:
World Bank Agencies/Programs
  International Bank of Reconstruction and Development (IBRD)
  Global Environment Facility (GEF)
  International Finance Corporation (IFC)

Multilateral Development Banks
  European Bank For Reconstruction and Development (EBRD)
  Inter-American Development Bank (IDB)
  Asian Development Bank (ADB)
  Africa Development Bank (AfDB)
U.S. Government Agency Programs
  Trade Development Agency (IDA)
  United States Agency For International Development (USAID)
  Overseas Private Investment Corporation (OPIC)
  Export-Import Bank (EXIMBANK)
U.S. Initiative on Joint Implementation

-------
Aooencix 3
                                                 VETIIANE GUIDELINES
The World Bank, through its affiliates
mm, IDA, IFC, and MIGA, provides
financial  assistance  to  developing
countries  for  social and  economic
development projects.
International Bank of Reconstruction and Development
(IBRD)

Overview:  The World Bank, established in 1945, comprises the International
Bank for Reconstruction and Development (IBRD)  and its  affiliates: the
International Development Agency, the  International Finance Corporation
(IFC), and  the Multilateral  Investment  Guarantee Agency (MIGA).   155
member countries have subscribed capital to the Bank enabling it to finance its
lending  operations primarily from its  own  borrowing  in  capital  markets.
However, a substantial portion of the IBRD's resources  also come from the
retained earnings and the flow of repayment.

The  World Bank finances capital infrastructure, such as  roads  and railways,
telecommunications, and  port and power facilities.   However, the Bank's
development strategy emphasizes investments that can directly affect the well-
being of poor people in developing countries by making them more productive
and  integrating them as active partners in the development process.   The
Bank's efforts to reduce poverty include investments  to improve education,
ensure  environmental  sustainability,   expand   economic   opportunities,
strengthen population-planning, health and nutrition services, and develop the
private sector.

Criteria: The IBRD's charter requires that it: (1) lend for  productive purposes
to stimulate economic  growth in developing countries;  (2) pay due regard to
the   prospects of repayments;  (3) make loans  to  governments or  with
guarantees  from the government; (4) not restrict procurement  to purchases
from any particular member country;  and (5) make  lending  decisions on
economic considerations alone.

The IDA provides assistance to poorer developing countries, i.e., those with an
annual per capita gross domestic product of $580 or less, expressed in 1989
U.S.  dollars. Terms of the IDA loans are less stringent than those of "regular"
IBRD loans.

The  IFC is legally and financially a separate entity.  Its purpose is to promote
growth in the private sector of the less developed country economies, largely
by taking equity positions in projects (see profile).

The  MIGA encourages equity investment and other direct investment trtrough
the mitigation of non-commercial investment  barriers.  MIGA must: (1) offer
investors guarantees against  non-commercial  risks;  (2) advise  developing
member countries on policies, programs, and procedures related to foreign
investment; and (3) sponsor a dialogue between the  international business
community and host governments on investment issues.

Contact Information:  For further information, contact

                           The World Bank
                          1818 H Street, N.W.
                     Washington D.C. 20433 USA
                          Tel: 202/477-1234

-------
HALOED VETHANE GUIDELINES
                                                                                          Airjeric'.x  3
 Global Environment Facility (GEF)

 Overview: The Global Environment Facility (GEF), an organization established
 by the United Nations  Development Program (UNDP), the United  Nations
 Environment  Program  (UNEP), and the World  Bank, offers  grants  and
 concessional funds to developing countries for projects that are beneficial to
 the global environment.  GEF funds are used to cover the difference between
 the costs of a project undertaken with global environmental objectives in mind,
 and the  costs  of  an  alternative  project  that  the  country  would  have
 implemented  in  the absence  of  global environmental concerns.   GEF
 resources are available to  projects that address the following four areas:
 climate change,  loss of biological diversity, pollution of international waters,
 and depletion of the ozone layers.  Listed below are several  types of projects
 that the GEF may fund.

 •       Technical  assistance  projects focused  on  human development,
        capacity building, training, and information sharing;
 •       Feasibility studies  for investment projects and complex technical
        assistance projects;
 •       Small grants for community-based grassroots organizations and non-
        governmental organizations in developing nations; and
 •       Grants  to investment projects to fund  the  incremental costs  of
        achieving global environmental benefits.

 Criteria: The GEF has established general criteria for all areas in which it may
fund projects, as well as criteria specific to each of the four areas. The general
points which are assessed include:

•       Potential to benefit the global environment;
•       Contribution to  human welfare and sustainable development;
•       Financability of project without GEF support;
•       Scientific and technical basis of project;
•       Plans for evaluation and dissemination of results;
•       Host nation political, legal, economic, and administrative conditions
        under which the project must be executed
•       Development of human and institutional resources;
•       Plans for post-GEF project continuation; and
•       Involvement of  local communities.

Contact Information: For further information, contact the GEF at:

               GEF Administrator, Environment Department
                              World Bank
                          1818 H Street, N.W.
                        Washington, DC 20433
                          Tel: 202/473-1053
                          Fax: 202/477-0551
                                                                             GEF will fund only those  projects
                                                                             which cannot pay for themselves, Le.,
                                                                             whose project costs exceed project
                                                                             revenues.  Therefore, GEF funding is
                                                                             ideal   for   conducting
                                                                             assessments.

-------
Aooe.icix  3                                                              COALDED  VETHANE  GUIDELINES
                                    International Finance Corporation (IFC)

                                    Overview:  The International Finance Corporation (IFC) was established  in
                                    1956 to help strengthen the private sector in developing countries.  IFC lends
                                    directly to the private sector.  IFC aids private sector development by providing
                                    long-term loans, equity investments, guarantees and "stand-by financing", risk
                                    management and "quasi-equity  instruments", such as subordinated  loans,
                                    preferred stock, and income notes.  IFC  advisory services and technical
                                    assistance help private business increase their chances of success.  Other
                                    relevant information on IFC is as follows:

                                    •       Source of funds: About 80% is borrowed in the international financial
                                            markets through public bond issues private placements and 20%  is
                                            borrowed from IBRD;
                                    •       Lending.  Each year,  IFC  approves about $4 billion  in  financing,
                                            including  syndications and  underwriting for private-sector projects  in
                                            developing countries. The minimum amount of IFC support available
                                            is $10 million; and
                                    •       Loan Conditions:  Interest rate on IFC loans and financing are based
                                            on market rates, which vary between countries and projects; maturity
                                            on loans ranges from 3 to 13 years.

                                    Criteria: Project proposals will be  assessed on the basis of  the following
IFC  will  provide loans and other     information:
financial     instruments     (equity
imestments^uarant-ees^etc.)tothe     9       Project Description, brief description of the project and current status;
ornate  sector only.   The  mnmum               '      ,_._,..           L.        . ._  .
support provided by IFC is $10 mason     *       Sponsorship and Management history  and business  of  sponsors,
                                            management arrangements, and technical arrangements;
                                    •       Markets and Sales: market orientation (export/domestic), production
                                            volumes  and  sales  objectives,  potential users and distribution
                                            channels, and relevant tariffs and protective measures;
                                    •       Technical Feasibility: equipment availability, labor and  infrastructure
                                            facilities, resource accessibility, and potential environmental issues;
                                    •       Financing Requirements:  breakdown  of  project  costs,  proposed
                                            financial plan, type of assistance sought, and expected profitability;
                                    •       Government Regulations: government controls, exchange controls,
                                            tax regulations, export/import licences, and price controls applicable
                                            to the  project.

                                    Contact Information: For further information, contact the IFC at:

                                                        International Finance Corporation
                                                            18501 (Eye) Street, N.W.
                                                            Washington, D.C. 20433
                                                              Tel.: 202/477-1234
                                                              Fax: 202/477-6391

-------
COALBED  VETIIANC GUIDELINES
               A'ooenc'.x
    European Bank fot Reconstruction and Development
    (EBRD)

    Overview: The European Bank for Reconstruction and Development (EBRD)
    is a multinational institution set up with the specific aim of assisting countries
    of central and eastern Europe to develop into market-oriented economies. The
    EBRD provides financial assistance to both the private and public sector. The
    types of financial instruments offered  include: loans; equity and quasi-equity
    investments; and guarantees.  Other information about EBRD financing:

    •       Minimum Loan Amount. The minimum lending requirement for the
            Bank is ECU 5 million ($6.5 million, as of November 1995).
    •       Interest Rates:  Interest  rates are set at a  margin over  a market
            benchmark (usually LIBOR  - London Interbank Offered Rate). Loans
            can be either variable rate or fixed rate;
    •       Loan Term. Maturities generally range,from 5 to 10 years, depending
            on the individual operation requirements; and
    •       Currency.  The EBRD lends in  hard currencies - US dollar, the
            Deutschmark, andtfie ECU.

    Criteria: The first step in  the approval process is  the  Concept Clearance
    stage.  Prospective  borrowers  approach the banking  staff  to advise  on
    procedure and  potential structuring options.  Based on information on the
    scope  of   the project,  financing  requirements,   and  technical  and
    economic/commercial aspects, the Bank will determine whether the project fits
    within its guidelines and strategies.

    If the project is cleared, a Mandate  Letter, defining the legal requirements for
    entering to a relationship with the Bank, is signed and an Operation Leader is
    assigned as the key Bank contact for the project.  The next stage is the  Initial
    Reviewwhich requires detailed project information, including:

    •       detailed description of the enterprise, project, and key personnel;
    •       financial statements audited to international standards;
    •       financial projections about the viability of the project;
    •       regulations applicable to the project; and
    •       assessment of the environmental impact of the project.

    Once the project has cleared  Initial Review, it has to pass Final  Review by the
    Bank's Operation Committee.  This evaluation process covers financial,  legal,
    economic, technical, and environmental issues.

    Contact Information: For further information, contact:
                         EBRD, One  Exchange Square
                      London EC2A2EH,  United Kingdom
                             Tel: 44 71 338-6282
                             Fax:4471338-6102
EBRD provides  bans,  equity,  and
guarantees to countries of central and
eastern Europe that are developing
into market-based economies.

-------
::x 3
                                                                              "OALBED VLTIIANE  GUIDELINES
IDB provides loans to governments
and private sector agencies for social
and economic development projects in
Latin America  and the Caribbean.
Grants   are  available  for  poorer
member countries.
                            Inter-American Development Bank (IDB)

                            Overview: The Inter-American Development Bank (IDB) is  a multilateral
                            development  bank created to help accelerate  the economic and  social
                            development of its member countries in Latin America and the Caribbean. The
                            IDB provides the following types of assistance to its member countries: loans
                            and other financial instruments;  concessional funds for needier  countries
                            (through  its  Fund  of Special Operations);  and  technical assistance  to
                            strengthen regional development institutions and help identify and implement
                            investment projects. Other relevant information about the IDB is as follows:

                            •       Extent of Financing. The IDB finances a certain percentage  of project
                                    costs, ranging from 50% for more economically developed  countries
                                    to 80% for poorer countries.
                            •       Loan Conditions: Interest rates on IDB loans and financing are based
                                    on market rates, which vary between countries and projects; maturity
                                    on loans ranges from 15 to 25 years.
                            •       Capital Resources: The IDB has a capitalization of over $100 billion
                                    that can support a level of annual lending of over $7 billion.

                            Typical borrowers of IDB funds include governments, ministries, or an agency
                            or utility under a ministry.  The borrower makes the key decisions on awarding
                            contracts for engineering, design,  project management, works  construction,
                            and purchase of capital goods. While governments and  related agencies are
                            the primary recipients of IDB funds, private sector enterprises too are eligible
                            for some forms of assistance.

                            The IDB has an  Environmental  Division that monitors the environmental
                            component of the  Bank's  operations and  develops  loans and  technical
                            assistance packages specifically directed towards protecting the environment.

                            Criteria: The following analyses are conducted to evaluate project proposals:

                            •       Institutional: borrower's administrative  and operational  capability to
                                    carry out the project;
                            •       Technical technical equipment, labor, and infrastructure required;
                            •       Socio-economic, social and economic costs and benefits, impacts on
                                    trade, income distribution, production, and employment; and
                            •       Environmental environmental impacts of the project.

                            Contact Information: For further information, contact:
                                               Inter-American Development Bank
                                                 1300 New York Avenue, N.W.
                                                 Washington D.C. 20577 U.S.A
                                                      Tel: 202/623-1000
                                                      Fax:  202/623-3096

-------
COALBED VETHANE GUIDELINES
              A'j'jenc'x  3
    Asian Development Bank (ADB)

    Overview: Established in 1966, the  Asian  Development Bank (ADB) is  a
    multilateral development bank whose  primary objective is poverty alleviation
    through sustainable economic growth  in Asia  The Bank has 35 developing
    member countries,  of which China,  India,  and Indonesia  are the largest
    recipients.  ADB assistance is channeled into the following sectors: agriculture
    and agro-industry; energy; industry and non-fuel minerals; financial services;
    transport  and  telecommunications;  social  infrastructure (e.g.,  education,
    health); and urban development.

    Typical borrowers of ADB funds include governments, ministries,  or an agency
    or utility under a ministry.  The borrower makes the key decisions on awarding
    contracts for  engineering, design, project management, works  construction,
    and purchase of capital goods. While governments and related  agencies are
    the primary recipients of ADB funds, private sector enterprises too are eligible
    for some forms of assistance. For private sector support, a project must play a
    catalytic role  in the development of the country.  For such projects, ADB
    assistance is  limited to 50% of project  costs or up to $50 million, whichever is
    less. The minimum loan is $5 million.

    The financial resources  of the Bank consist of ordinary capital resources
    comprising subscribed capital from member countries, reserves and funds
    raised  through  borrowings; and  Special   Funds,   including the  Asian
    Development  Fund, which is made up  of contributions from member countries
    and other accumulated income; and the  ALGAS fund, which is designed to
    support GHG  mitigation activities in developing member countries.

    Criteria: The projects or programs are analyzed in terms of:

    •       the borrower's capacity to finance and administer the project;
    •       its economic, technical, and environmental feasibility; and
    •       its social and economic benefits to the recipient country:

    Contact Information: For further information, contact:

                            Asian Development Bank
                 Office of the Environment and Social Development
                     6 ADB Avenue, 1501 Mandaluyong City
                         0401  Metro-Manila, Philippines
                              Tel.: 632/813-2148
                               Fax: 632/741-7961
ADB provides loans for the economic
member  countries.    Grants  are
available   through   special   funds
established by  the ADB (e.g., ADF,
ALGAS).

-------
                                                                              COALBED  V.ETHANE  GUIDELINES
AIDB provides bans for the economic
and social  advancement of African
countries. Grants are available for the
poorer countries through Vie Africa
Development Fund  ami  the Nigeria
Trust Fund.
                                       African Development Bank (AfDB)

                                       Overview: The African Development Bank (AfdB) is a multilateral development
                                       bank whose primary objective is to finance economic and social development
                                       in African countries. It achieves this objective through the provision of: loans
                                       and other financial instruments; technical assistance and institutional support;
                                       and mobilization of external resources for investment in Africa.  Grants and
                                       other concessional  funds are allocated for the poorest countries through the
                                       African Development Fund (ADF) and the Nigeria Trust Fund (NTF). The main
                                       criteria for defining the poor countries is GNP per capita.  The loan terms are
                                       as follows:
Terms
Interest Rate
Service Charge
Repayment Period
AfDB
Variable'
1%
20 years
ADF
None
0.75%
50 years
NTF
4%
0.75%
25 years
t The interest rate is reviewed every 6 months. As of June 30, 1995, the rate was 7.42%
Typical  borrowers  of  AfDB  funds  include  governments,  ministries, or an
agency or utility under a ministry.  While governments and related agencies
are the  primary recipients of AfDB funds, private sector enterprises too are
eligible for some forms of assistance.   For private sector support,  AfDB
assistance is limited to a third of project costs. The size of private sector loans
are generally in the $100,000 to $10 million range.

Criteria: The AfDB approves projects or program financing only on the basis of
appraisal reports prepared and submitted by the Bank's own staff, even where
a project have been previously  appraised by other co-financing institutions.
The appraisal process  accounts for the following:

•       the borrower's administrative and operational capability to carry out
        the project;
•       technical equipment, labor, and infrastructure required and available;
        and
•       social and economic costs and benefits.

Contact Information:  For further information, contact:

                       African Development Bank
                         01 BP1387 Abidjan 01
                          Cote d'lvoire, Africa
                           Tel: 225/2041 18
                           Fax: 225/204006

-------
OALBED VETHANE-GUIDELINES
             Aovjenc:x
   Trade Development Agency (TDA)

   Overview: Established in 1980, the U.S. Trade Development Agency (TDA) is
   a government organization that promotes U.S. exports by providing grants for
   feasibility studies for large development projects  in .developing and middle
   income countries.  The purpose of these grants is to provide U.S. firms with
   the opportunity to undertake feasibility studies  for large overseas  projects,
   thereby  increasing  the  chance  that they  will  be  involved  in  project
   implementation.  TDA grants the funds on the condition that U.S. firms are
   utilized to conduct  the  study.     TDA is currently involved in: energy,
   environment, mining and minerals development, health care, manufacturing,
   telecommunications, transportation, water resources, agriculture, and aviation.

   There are two types of studies which the TDA may fund: (1) feasibility studies
   for projects in which U.S. companies intend to make equity investments, and
   (2) feasibility studies for public sector projects. Before TDA funds a feasibility
   study, experts are hired to develop reports regarding the feasibility study and
   the project to be implemented at the conclusion  of the study.   If the TDA
   decides to fund the  feasibility study, it  asks interested firms to submit
   proposals. The host government decides which of the competing companies
   will undertake the study.

   The agency  may provide up  to one million dollars per study,  although the
   average grant amount ranges between $300,000 and $400,000.  While up to
   20 percent of the TDA funding may be used to pay subcontractors in the host
   country, the remainder must be used for services sourced in the U.S.

   Criteria:  All feasibility study proposals must include the following information:
   project description; U.S. export potential; information on host country partners;
   evidence of the host nation's  commitment to the project; justification for why
   TDA funding is needed; a financial analysis of the project; an assessment of
   foreign competition for project implementation; and the impact of the project on
   U.S. labor. A few of the most important criteria include:

   •       The project must be a development priority for the host country.
   •       The export potential of the project  must be significantly greater than
           the  cost of TDA assistance.
   •       The procurement process must be open to U.S. firms.

   Contact Information: For further information, contact the TDA at:

                          Trade Development Agency
                               Room 309, SA-16
                        Washington, D.C. 20523-1602
                             Tel.:  703/875-4357
                              Fax:  703/875-4009
TIM will provide giants to conduct
feasibility  studies  in  developing
countries on  the condition  ttaf U.S.
firms be hoed to conduct the study.
The average  grant size ranges from
$300,000 to $400,000.

-------
   AoDenclx 3
                                                  V.ETHANE GUIDELINES
USAID's    Office    of    Energy.
Environment,    and    Technology
provides   grants   and   tec/mica/
assistance to developing countries for
meeting    their   energy     and
environmental needs.
                                       U.S. Agency for International Development (USAID)

                                       Overview: USAID's Office of Energy, Environment, and Technology assists
                                       developing countries and emerging economies find market-oriented solutions
                                       to their energy and environmental problems. The Office's programs address
                                       three  main  issues:  1) high rates of energy demand  and economic growth
                                       accompanies with  lack  of energy,  especially in  rural areas;  2) financial
                                       problems, including lack of investment capital;  and 3) growing environmental
                                       threats, especially global climate change, acid rain, and urban air pollution.
                                       The Office focuses its efforts in the following areas:

                                       •       Energy Efficiency
                                       •       Renewable Energy Project Development
                                       •       Private Sector Energy Development
                                       •       Energy Technology Innovation
                                       •       Training/Technical Assistance
The Office has two main strategies for achieving its objectives:
•       Tapping  U.S.   Know-how.  The  Office  arranges  cooperative
        relationships between developing countries and  U.S.  energy and
        environment industries,  multilateral development  banks,  and  non-
        governmental organizations; and
•       Promoting Private Sector Initiatives: The Office assists countries put
        in place market-oriented policies and institutions to support private
        environment and energy initiatives.

The types of assistance  offered include: financing (loans, investment funds);
policy, legislative, and   regulatory  development  assistance; reports  and
workshops on market conditions and opportunities; and engineering and other
technical assistance.

Criteria:  The  criteria for USAID  fund  varies  on a  case-by-case basis.
However,   the following  points  are  generally considered  in the  project
evaluation process:

•       Potential of the project to meet its goals
•       Contribution to human welfare and sustainable development;
•       Scientific and technical basis of project;
•       Host nation political, legal, economic, and administrative conditions

Contact Information: For further  information, contact:

          U.S. AID: Office of Energy, Environment and Technology
                          Room 508, SA-18
                     Washington D.C. 20523-1810
                          Tel.: 703/528-4488
                          Fax: 703/528-2280

-------
"OALBED VETHANE GUIDELINES
              AoDenclx  3
    Overseas Private Investment Corporation (OPIC)

    Overview: OPIC is a U.S. government agency that provides  loans, loan
    guarantees, and  political  insurance to American business ventures in the
    developing world.   These services are  provided to those projects that are
    economically and technically  sound but  are  unable to receive  sufficient
    financing  or insurance from the commercial sector.  Projects supported by
    OPIC must have a positive effect on the U.S. economy, be financially sound,
    and provide significant benefits to the social and economic development of the
    host nation. While OPIC does not require the foreign enterprises to be owned
    entirely by U.S. interests,  generally the U.S. investor is expected to  own at
    least 25 percent of the equity in the project.  Neither financing nor insurance
    will be  available for investments in business that are majority owned  by a
    foreign government.  Furthermore, only the portion of the investment made by
    a U.S. investor may be insured by OPIC.

    OPIC's finance division offers loans and loan guarantees. Loans are generally
    granted to small U.S. businesses and range from $2 million to $10 million. For
    larger projects, in the $10 million to $75 million range, loan guarantees are
    provided.   OPIC's insurance division offers coverage against the following
    three risks:  currency inconvertibility, expropriation, and political  violence.
    Other investor services  provided by OPIC include investment missions and
    outreach activities.

    Criteria: Eligible projects must meet the following criteria:

    •      Positive effect  on the U.S. economy:  Projects must demonstrate
           positive balance of payments and employment effects on the U.S.
           economy;
    •      Development contribution: Projects must benefit the economic and
           social development of the host nation;
    •      Performance requirements:  OPIC will not become involved in any
           project subject to performance requirements that  will reduce the
           potential for U.S. trade and employment benefits.
    •      Environmental impact:  the project should not have an unreasonable
           or major adverse impact on the host nation's environment; and
    •      Worker's  rights:    All  projects supported  by  OPIC  must  meet
         -  internationally recognized standards with regards to worker's rights.

    Contact Information: For further information, contact OPIC at:
                    Overseas Private Investment Corporation
                          1100 New York Avenue, N.W.
                            Washington, D.C. 20527
                              Tel.: 202/336-8799
                              Fax: 202/408-9859
                     Fax-ion-Demand System: 202/336-8700
OPIC will provide loans and  loan
guarantees tor projects in developing
countries tfiaf US enterprises have a
stake in.   The project must have a
positive effect on the US economy.

-------
 ADDeicix
                                      COALBCD V.ETHANE GUIDELINES
EXIMBANK   provides   loans   and
guarantees to foreign buyers of US
goods and services. The bank covers
up to 85% of the US export value.
Export-Import Bank (EXIMBANK)

Overview: The Export-Import Bank (EXIMBANK) of the United States is a U.S.
Government agency that facilitates the export financing of U.S. goods and
services to foreign buyers.  EXIMBANK supports export sales by providing
direct loans to foreign buyers,  guarantees to U.S. and foreign commercial
lenders for credit  risk protection, export credit  insurance, to U.S. exporters
against failure of foreign buyers to meet payment obligations, and pre-export
financing for small  business through its Working Capital Guarantee Program.

Relevant information about EXIMBANK loans includes:

•       Types of Loans: EXIMBANK provides  both direct and  intermediary
        loans.  Direct loans are provided to foreign buyers of U.S. exports;
        intermediary loans fund parties that extend loans to foreign buyers;
•       Interest Rates:  EXIMBANK loans  carry  the lowest interest rate
        permitted under the OECD Arrangement for the market and term. ,
        this rate is the  OECD Commercial Interest Reference Rate (CIRR),
        which changes  monthly. For relatively poor countries, lower interest
        rates loans are available; and
•       Extent of Assistance: Loan and guarantee programs cover up to 85%
        of the U.S. export value.

Criteria: Transactions are evaluated  in terms of  the creditworthiness of the
buyer, the buyers country, and the exporters ability to perform. In general the
following information is assessed:

•       Financial Data:  Balance sheets and income statements for the past 3
        years for the buyer and any guarantors);
•       Credit Data: at least two credit references are checked;
•       Technical Feasibility,  technical  characteristics   of  the  project,
        breakdown  of  costs,  project  scheduling,  participant  profiles,
        environmental aspects, etc.; and
•       Applicant and Exporter Data: Evidence  of the applicants  ability  to
        implement the requested loan or guarantee.

Contact Information: For further information, contact:

                 Export-Import Bank of the United States
                       Credit Information Section
                      811 Vermont Avenue, N.W.
                        Washington D.C. 20571
                          Tel: 202/377-6336
                          Fax: 202/566-7524
                 Fax -on-Demand system:  800/424-5201

-------
:OALBEU VETIIANE GUIDELINES
             Aooenc'.x  !3
    U.S. Initiative on Joint Implementation (USIJI)

    Overview: The U.S. announced its Initiative on Joint Implementation (USIJI)
    in October 1993.  This voluntary pilot program provides recognition and select
    technical  assistance to  U.S.  greenhouse gas reduction projects  in  other
    countries.  This program allows U.S. companies to reduce emissions at a
    lower cost than would be incurred by projects undertaken at  home.  U.S.
    government agencies involved in  this program include the Environmental
    Protection Agency, the Department of Energy, the Department  of State, the
    Agency for International Development, the Department of Commerce, and the
    Department of Agriculture, among others.

    The benefits of this program to U.S. participants include public recognition,
    including use of the USUI logo and media events, and technical assistance.
    This assistance may include help in obtaining host country acceptance of the
    project, identifying or developing methodologies for establishing a greenhouse
    gas emissions baseline, and guidance on how to monitor and verify emissions
    reduced or sequestered.  For foreign participants, the benefits may include
    technology transfer, investments  in technologies that benefit the  global
    environment as well as  the local  economy, employment opportunities and
    training, and local environmental benefits.

    Eligible program participants include U.S. citizens, U.S. companies, and any
    U.S. federal, state, and local government entity. Foreign partners may include
    private citizens and public entities of all nations that have ratified the  United
    Nations Framework Convention on Climate Change (UNFCCC).

    Criteria: Projects accepted into the USIJI program must:

    •       obtain host country acceptance;
    •       prove that the specific measures to reduce or sequester greenhouse
           gases are being undertaken as a result of USIJI or in its anticipation;
    •       provide sufficient and reliable data to establish a baseline of current
           and future greenhouse gas emissions;
    •       provide for the tracking of emissions reduction or sequestration;
    •       allow for external verification of emissions reduction or sequestration;
    •       identify benefits  or negative effects  on the economic and social
           development of the host country and on the local environment.

    Contact Information: For further information, contact:
                             The USIJI Secretariat
                    600 Maryland Avenue, SW  Suite 200 East
                            Washington, D.C. 20585
                              Tel.: 202/426-0072
                    Fax-on-Demand System: 202/260-8677
Projects that meet the USUI criteria
are likely  to attract  US  investors
seeking the recognition and other
amenities available to participants in
the USUI program.

-------