SUMMARY REPORT A NATIONAL EVALUATION OF THE DELEGATED CONSTRUCTION GRANTS PROGRAM Prepared for THE ENVIRONMENTAL PROTECTION AGENCY OFFICE OF WATER PROGRAM OPERATIONS Larry Walker Associates January 1981 ------- SUMMARY REPORT A NATIONAL EVALUATION OF THE DELEGATED CONSTRUCTION GRANTS PROGRAM Prepared for THE ENVIRONMENTAL PROTECTION AGENCY /• OFFICE OF WATER PROGRAM OPERATIONS Contract No. 68-03-2674, Task 93 EPA Project Officer Albert Pelmoter Larry Walker Associates January 1980 ------- TABLE OF CONTENTS CHAPTER 1 INTRDDUCTIOJ 1-1 Background 1-1 Purposes of the Evaluation 1-1 Conduct of the Evaluation 1-2 Acknowledgements 1-3 CHAPTER 2 SUMMARY AND RECOMMENDATIONS 2-1 Summary 2-1 Recommendations 2-10 CHAPTER 3 STATUS OF DELEGATION 3-1 The Delegation Process 3-1 Delegated States 3-4 Status of State Assumption of Delegable Functions 3-7 CHAPTER 4 EPA REGIONAL OFFICE PERFORMANCE UNDER DELEGATION 4-1 Progress Toward Delegation 4-2 Organizational Structure and Resources 4-7 Regional Management of the Delegated Program . . 4-11 Grants Processing Procedures 4-15 Processing Times for Regional Reviews 4-21 Regional Monitoring of State Performance .... 4-26 Overall Regional Office Performance 4-29 ------- CHAPTER 5 EVALUATION OF THE PERFORMANCE OF DELEGATED STATES 5-1 Organizational Structure and Resources 5-1 State Management of the Delegated Program . . . 5-9 State Grants Processing Procedures 5-18 Quality of State Reviews 5-23 Processing Times for State Reviews 5-26 Overall State Performance 5-31 CHAPTER 6 PROBLEMS AND NEEDS ASSOCIATED WITH THE DELEGATED CONSTRUCTION GRANTS PROGRAM 6-1 Operational Problems with Delegation 6-2 Problems Associated with the Law and Regulations 6-13 Program Needs 6-26 11 ------- LIST OF TABLES TABLE Page 3-1 STATUS OF STATE DELEGATIONS 3-5 3-2 STATUS OF STATE ASSUMPTION OF DELEGABLE FUNTIONS 3-8 3-3 SCHEDULE FOR FULL DELEGATION 3-11 4-1 TIME FOR FULL STATE ASSUMPTION OF ALL DELEGABLE FUNCTIONS 4-4 4-2 PROCESSING TIMES FOR REGIONAL REVIEWS 4-22 4-3 SUMMARY OF REGIONAL OFFICE MONITORING OF DELEGATED STATES 4-31 5-1 SUMMARY OF STATE INTERACTION ON INDIVIDUAL GRANT PROJECTS 5-21 5-2 PROCESSING TIMES FOR STATE REVIEWS 5-30 LIST OF FIGURES FIGURE Page 5-1 RELATIONSHIP BETWEEN STATE STAFFING LEVELS AND ANNUAL ALLOCATION 5-4 111 ------- CHAPTER 1 INTRODUCTION BACKGROUND In passing the Clean Water Act of 1977 (the Act) , Congress provided for and, in fact, encouraged the Environ- mental Protection Agency (EPA) to delegate day-to-day ad- ministration of the construction grants program to inter- ested and qualified states. By early 1980, two thirds of the states had entered into delegation agreements with EPA, and a number of other states were in the process of negotiating agreements. About this time, the EPA Office of Water Program Oper- ations decided to conduct a nationwide evaluation of the delegated program. The primary impetus behind this was EPA's interest in assuring that delegation be successfully implemented, and its desire to identify any problems that may be developing so they can be corrected at an early stage. PURPOSES OF THE EVALUATION The specific purposes of the evaluation were as follows: 1. To determine the status of delegation in each state and region. 2. To evaluate the EPA regional offices' performance of functions related to delegation. 3. To evaluate the performance of the delegated states. 4. To identify any problems and needs that are devel- oping. 1-1 ------- 5. To develop recommendations for improving the ad- ministration of the delegated program. The evaluation, while it served as a fact finding in- vestigation on the one hand, was strongly oriented towards the development of recommendations for improving the dele- gated construction grants program at the state, the region- al office, and the EPA Headquarters levels. CONDUCT OF THE EVALUATION The authors visited each of the ten EPA regional offices and one delegated state within each region to gather the in- formation necessary to perform this evaluation. Generally, two days were spent in each regional office and three days in each state office. The following states were visited: Region I Region II Region III Region IV Region V Region VI Region VII Region VIII Region IX Region X Connecticut New York Maryland Georgia Michigan Texas Missouri Montana Arizona Idaho These states were selected by the respective regions under general guidance from EPA Headquarters. The objec- tive was to visit the states which had progressed the furthest towards full delegation. This criterion was used with the idea that problems and needs were more likely to 1-2 ------- be apparent in these states than in states which were just beginning to assume the program. During both the regional office and state visits, in- formation was gathered on delegation status/ organizational characteristics, management and operating procedures, and work products. Regional office .and state views on program problems and needs also were solicited. In conjunction with these visits, the performance of each region and state was evaluated, using criteria agreed to in advance by EPA Headquarters. Individual reports evaluating each regional office and state were then prepar- ed. Each region and state was given an opportunity to review and comment on the draft report before it was final- ized and submitted to EPA Headquarters. Subsequently, the present report was prepared, evaluat- ing the delegated program from a national perspective. This report summarizes the findings of the individual field evaluations, identifies program-wide problems and needs, and contains recommendations for improving adminis- tration of the delegated program. The second chapter contains a summary of the report and the recommendations. The third chapter contains a discussion of the status of de- legation throughout the country. The fourth chapter con- tains a generalized evaluation of the performance of the EPA regional offices under delegation. The fifth chapter contains a generalized evaluation of the states' performance in administering the delegated program. Finally, the sixth chapter contains a discussion of programwide problems and needs. ACKNOWLEDGEMENTS The authors wish to gratefully acknowledge the assist- ance and cooperation of the various EPA regional office 1-3 ------- staffs and the state staffs during the conduct of this investigation. Without exception these individuals gave considerably of their valuable time, and they were coopera- tive, constructive and open in their comments. Without such cooperation and openness this evaluation would not have been possible. The authors would also like to acknowledge the help and assistance of Mr. Albert Pelmoter, the EPA project officer on this evaluation. Mr. Pelmoter is the Chief of the Policy Guidance Branch of the Municipal Construction Division within the Office of Water Program Operations. 1-4 ------- CHAPTER 2 SUMMARY AND RECOMMENDATIONS This chapter presents a summary of the findings of the national evaluation of the delegated construction grants program, and of the recommendations which have been formula- ted to improve overall administration of the delegated program. The points outlined below are more fully discussed in the remainder of this report. SUMMARY Status of Delegation 1. The process of delegating full authority to admin- ister the program to the states is a lengthy one, requiring considerable time and effort of both the regional offices and the states. It is not a quick process in cases where everything goes well, and usually at least some problems are encountered. It is therefore not surprising that/ three years after passage of the 1977 Clean Water Act, no state has yet taken over the program in its entirety. In fact/ only about a third of the delegated states are admin- istering the bulk of the delegable functions. 2. To date, 37 states (or 74% of all states) have en- tered into delegation agreements with their respective EPA regional offices. These delegated states coincidently re- ceive 75% of the annual appropriation under the current allotment formula and they have 74% of the active grant projects. 3. Of the 13 non-delegated states, 5 states are cur- rently negotiating delegation agreements and will likely receive delegation in Fiscal Year 1981. Two other states are interested in delegation and are pursuing it with 2-1 ------- their respective regions; they will likely receive delega- tion within the next year or two. The 6 remaining states are not pursuing delegation at this time primarily because of the resource implications. In these states, the current administration has policies against expanding state staff, irrespective of the source of funds. It is unlikely that any of these states will receive delegation within the next several years. 4. Most delegated states are in the process of transi- tion. While the delegated states are taking over adminis- tration of numerous delegable activities from the EPA regional offices, the regional offices are still adminis- tering significant functions in 24 of the 37 delegated states. In addition, under separate agreements with the regions, the Corps of Engineers is performing construction inspections and related construction activities in 33 of the 37 delegated states. So at the present time, in most delegated states, the regions, the Corps of Engineers, and the states are involved in performing functions related to individual grant projects. 5. Within a year, 27 of the 37 presently delegated states will have taken over all delegable functions except those construction related activities typically performed by the Corps of Engineers. 6. It is likely that Corps of Engineers involvement will continue in most states into the foreseeable future. At present, only 4 states have taken over construction inspections and related activities typically performed by the Corps of Engineers. Only 2 additional states plan to take over these activities within the next year. The re- maining states do not plan to take over Corps of Engineers performed activities until they can be assured, through Section 205(g) of the Act, of reliable and adequate funding. Recent amendments to Section 205(g) will greatly increase the reliability of funding, but there remains a question 2-2 ------- as to whether the current 2% level will be adequate to allow some states to take over these activities. EPA Regional Office Performance Under Delegation 1. The regions have been quite aggressive in pursuing delegation agreements with interested states. While the re- gions may have proceeded cautiously with states having little prior experience in the program, in general they were able to negotiate agreements acceptable to both parties. As stated previously, the likelihood that 6 states will not negotiate agreements is due primarily to state administration policies, and is not a reflection of the regional offices' efforts. 2. The rate at which specific delegable functions have been turned over to delegated states has varied considerably, with many states assuming all of the delegable functions (except those typically performed by the Corps of Engineers) within about a year and a half after execution of a delega- tion agreement. In other cases this has taken up to three years. The authors feel that, in several regions, the current delegation schedules can be accelerated, though in most cases they appear reasonable. 3. Some delegation agreements do not provide for dele- gation of all delegable functions. Examples of functions not included in some agreements are Minority Business Enterprises (MBE), Grants Information and Control System (GICS), official project files and payments. 4. There have been some outstanding examples of train- ing provided by the regions to delegated states, but in general the training provided has been rather modest. 5. The present organizational structures in the re- gions, though adequate prior to delegation and even during the current transition period, are generally not well suited for operation under a fully delegated system. The major pro- blems are that most regions divide responsibility for a given 2-3 ------- state among several organizational units and most organiza- tional structures do not reflect the need for specialized monitoring of delegated state performance. 6. The resources currently employed by the regional offices for administration of the delegated program appear adequate, given the present status of delegation. As states assume all of the legally delegable functions, regional re- sources currently employed to perform these functions can be reduced. At the same time, however, resources for overseeing and coordinating the program with the states and for monitor- ing the performance of delegated states will have to be increased. 7. The regions generally employ sound management practices in terms of administering the delegated program, though there are needs for improved management information systems and for the establishment of regular and formalized communications with each of the delegated states. 8. Only one region currently is employing grants processing procedures consistent with the concept of dele- gation and in a way that results in the achievement of benefits conceived to be associated with delegation. Other regions are still making the transition from a non-delega- ted to a fully delegated mode of operation. While these regions are moving in the right direction, they generally are receiving more information and documents than they really need on individual projects, and they generally are not accepting state certifications without at least some review. On the positive side, there appears to be little if any second-guessing of state decisions by the regions. 9. Regional office processing of state certified grant awards and their issuance of findings of no significant im- pact (FNSI's) needs to become more efficient. While regional office processing times for grant awards have been reduced on the average by 42% since delegation, they are still higher than necessary. The combined processing time for the three 2-4 ------- grant awards (Steps 1, 2, and 3) averages 127 days, whereas the authors believe a total combined processing time of between 15 and 30 days is possible for these three awards. 10. The regions are not yet doing a fully adequate job of monitoring the performance of delegated states. Four re- gions (at the time of the field visits) had performed no monitoring at all. Most of the monitoring that had been performed, while detailed and constructive, was narrow in perspective. Most of the monitoring focussed on determin- ing state compliance with the processing procedures outlined in the delegation agreement. Few monitoring programs have taken an in depth look at the quality or processing times of the state's reviews, or at the state's overall manage- ment of the delegated program. State Performance Under Delegation 1. On an overall basis, states appear to be doing a good job of administering the delegated program. 2. The states appear to have adequate resources and acceptable organizational structures to administer the pro- gram considering where the states presently are in delega- tion. There are several isolated cases in which resource levels need to be increased and there are several situations where organizational structures need to be improved. These, however, are relatively minor in significance. 3. The management staffs at the state level appear to be quite capable of managing the program. Most of the state managers, however, at this point in time, appear to be focus- sing their attention on taking over the delegated functions and on dealing with problems and issues associated with individual grant projects. Few state managers have been able to focus attention on managing the program as a whole. 4. State managers could benefit from the development of certain additional management tools, such as a management 2-5 ------- information system, a project tracking system, and a program planning system. States would also benefit from regular and formalized communications with the EPA regional office and some formalized means of communications with grantees and consultants. 5. The grants processing procedures employed by the states appear generally to be adequate and in conformance with the procedures identified in the delegation agreements. Only 3 of 10 states visited, however, actively deal with grantees and consultants during the preparation stage of facilities plans, and plans and specifications. Most states wait until drafts of final products are completed until re- views are made and input provided. 6. State reviews of both facilities plans, and plans and specifications appear to be of very good quality. They are generally thorough and substantive in nature and will likely lead to better, more cost-effective projects. Only in 1 state was a clear deficiency noted (in the review of plans and specifications), while in 2 other states, reviews of inconsistent quality were noted (in one state relative to plans and specifications and in the other relative to facilities plans). 7. State processing times are generally in need of improvement. With several exceptions, states do not appear to be focussing attention on the time spent on their reviews. In several states, total processing times for the 5 main state reviews are approaching 2 years. The authors believe total processing times for these reviews in the order of 8 months is achieveable, given proper attention and the implementation of certain management practices. Problems and Needs Associated with the Delegated Program 1. The objectives which prompted Congress to encourage 2-6 ------- delegation have not, as yet, been achieved: optimal use of state and federal resources has not yet been achieved; duplication has not totally been eliminated; management of the program has not yet been decentralized and the speed of processing grant projects has not been adequately in- creased. The primary reason why these objectives have not been fully achieved is that delegation is not yet fully implemented. Beyond this reason, there are other factors contributing to the lack of achievement of Congressional objectives. Some of these factors are operational in nature and can be corrected through modification of manage- ment practices and procedures. Several others, however, are built into the law and the regulations and will require amendments to those documents to correct. 2. While the transition towards full delegation is well along in most states, the potential benefits of delegation, in terms of elimination of duplication and optimal use of federal and state resources, will not be realized until the delegation process is completed. Short of full delegation, EPA duplication of states' efforts, and EPA resource needs will be proportionally greater than is suggested by the achieved degree of delegation. Likewise, decentralization of management will not come until the delegation process is completed. 3. The involvement of the Corps of Engineers in the delegated program, if not handled properly, can impair achievement of the objective of decentralizing management of the program. The basic problems are that the Corps of Engineers has agreements with the EPA regions and not with the states, and the Corps of Engineers feels it must deal officially through the regions. The states generally, therefore, are not totally responsible for the construction aspects of the program. The exceptions occur when states take over all Step 3 activities from the Corps of Engineers or when states pursue and assume responsibility for the 2-7 ------- Step 3 portion of the program even though the Corps performs many of the activities. In the usual case, however, respon- sibility appears to be divided between the regions, the Corps of Engineers, and the states. 4. The way in which new program requirements are typic- ally implemented also impedes achievement of full delega- tion and the resulting benefits. Typically, regional of- fices administer new program requirements until the delega- tion agreements can be amended to outline detailed proced- ures for the new requirements. As this process generally takes considerable time and as new requirements are common, as long as this process is perpetuated, total delegation of all delegable functions to the states will never quite occur. Therefore, to some extent, unnecessary duplication and time delays will continue to be problems. 5. The increasingly common practice of leaving por- tions of the responsibility for administering new program requirements at the regional level is another problem impeding the achievement of the objectives of delegation. Examples are reviews associated with advanced waste treat- ment, MBE, and Section 316A of the Clean Air Act. Not delegating project-related review functions, for whatever reason, detracts from achievement of the potential benefits of delegation and from the original objectives for which delegation was designed. 6. The fact that certain project-related functions are non-delegable, as per EPA regulations, causes duplication of effort and time delays, and does not appear to result in any benefits over having the states take full responsibility for these functions. Examples of non-delegable functions in- clude civil rights determinations, grant awards, grant amendments, wage rate determinations, bid protests, resolu- tion of audit exceptions, and issuance of FNSI's. Such functions could successfully be taken over by the states. 2-8 ------- 7. In several regions, the issue of whether the re- gions or states have responsibility for interpreting federal regulations and policies has arisen. Related to this issue, a few regions have attempted to impose policies more restrictive than federal policies on delegated states, raising objections from the states involved. 8. The funding available to delegated states through Section 205(g) of the Act appears to be inadequate to allow some states to assume the construction inspection and related activities typically performed by the Corps of Engineers. Three of the ten states visited by the authors were operat- ing at budget levels in excess of their annual Section 205(g) allotment (the states borrowed from reserved funds to make up this deficit). The recent amendments to the Act, tying Section 205(g) funding to the authorizations in the Act will provide near term relief for the deficiency; however, over the longer term, especially if appropriation levels approach authorization levels, the 2% funding level will be inadequate. 9. The fact that EPA will have to continue indefinitely to administer the construction grants program in a small minority of non-delegated states will result in inefficien- cies from a national perspective. Approximately 5 regions will be administering the program in two ways: fully administering the program in one state, and overseeing a fully delegated program in all the other states. Because only a few states (6) will remain non-delegated, it may be advantageous for EPA to either press for delegation in these states or develop an alternative means of administer- ing the non-delegated program in these states. Relief from direct administration of the program in all states would allow EPA to focus its full attention on the broader responsibilities of overviewing the program from a regional and national perspective, and insuring that national water pollution control objectives are being achieved. Where 2-9 ------- Section 205(g) agreements can't be-negotiated, it would be advantageous for EPA to get the States to perform certain grant processing activities under section 106 agreements. 1(K EPA Headquarters needs to develop an oversight program to insure that each regional office is fulfilling its responsibility under delegation and that the national program is achieving the objectives for which it was design- ed. 11. One of the major challenges which EPA Headquarters faces under delegation is how to gain access to the knowledge that the states will be gathering as they administer the program on a day-to-day basis, so that EPA can do an effect- ive job of directing the national program. This will not be an easy task given the fact that approximately 40 states will be administering the program. Without question, the states have to play a stronger advisory role than they have in the past. A key question, however, given the nature of the delegation to the states, is whether the states should be given a role stronger than just an advisory role, for example, whether they should be given a role in program management. RECOMMENDATIONS This section contains the recommendations that have been developed as a result of the evaluation of the delegated construction grants program. Implementation of these recom- mendations will lead to improved administration of the dele- gated program and will allow achievement of the objectives for which the delegated program was designed, namely: • Optimal use of state and federal resources. • Elimination of duplication at the state and federal level. • Decentralization of management of the program. • Speeding up the processing of grant projects. 2-10 ------- The recommendations have been listed under the agencies that will be responsible for their implementation: either the states, the EPA regional offices, or EPA Headquarters. Further, the recommendations have been prioritized into three classes, Priority 1, 2, or 3. Priority 1 recommendations are considered the.most critical to the success of the delegated program and should be implemented as soon as possible. Priority 2 recommendations are important and will lead to significant improvement of the delegated program, but are not so critical that they have to be implemented immediately. Priority 3 recommendations are actions that will lead to desirable refinements of the program and will assist in the achievement of the original objectives of delegation, but their implementation is not as critical as Priority 1 and 2 recommendations. It would not be critical if imple- mentation of these recommendations was deferred for several years. Recommendations for Delegated States 1. Focus increased attention on managing the construc- tion grants program within the state as opposed to focussing only on managing the performance of delegated functions and the processing of projects. The objective in this regard should be to manage the program in a way that best facili- tates achievements of the goals of the Clean Water Act. In addition, states should strive to administer the program in a manner that maintains program integrity and public trust (Priority 1). 2. Develop a management information system which pro- vides program managers with the information they need to make sound program management decisions. Specifically, a monthly management report should be developed which identi- fies what has been accomplished over the past year, the current status of the program, and future projections of 2-11 ------- key items such as obligations, awards, etc. (Priority 2). 3. State program managers should break away periodi- cally from the day-to-day pressures of the program to look and plan ahead. The development of annual program goals and objectives either through the use of a management by objectives approach or the State EPA agreement process is recommended (Priority 2). 4. States should get more aggressive in terms of track- ing and expediting grant projects. State project managers should be charged with closely tracking the projects for which they are responsible, and with taking aggressive action to keep the projects on schedule (Priority 1). 5. In order to assist in tracking and expediting pro- jects, each state should develop and implement a project tracking system suited to the state's needs. This system should provide for the development of detailed and realistic time schedules for each active project, routine monitoring of the actual progress of projects in comparison to the sche- dules, and regular updating of the schedules. The imple- mentation of the project tracking system can be phased, starting initially with a manually maintained tracking system for key projects and eventually going to a computer- ized system (if warranted) for all projects (Priority 1). 6. Become more actively involved with consultants and grantees during the facilities planning and design processes. The thrust of this involvement should be to assist grantees and consultants in producing an acceptable product, avoiding common pitfalls and minimizing wasted effort. To accomplish this, the states should maintain regular contact with con- sultants and grantees during planning and design phases, and whenever possible, review and comment on intermediate products. In the facilities planning phase, the state should review population and waste load projections as they are developed, review proposed alternatives before they are evaluated, review cost-effective analyses before 2-12 ------- recommended plans are selected, and finally, review draft facilities plans before local public hearings are held. In the design phase, the state should review a detailed preliminary design report early in the design process, an intermediate set of plans and specifications at approxi- mately the mid-point of design, and a set of preliminary or nearly complete plans and specifications (Priority 1). 7. Focus greater attention on reducing state proces- sing times. Specifically, states should develop processing time goals for all significant reviews and approvals, charge staff with processing documents in accordance with those goals, and routinely monitor actual performance against the goals. Also, states should be more aggressive in getting grantees to respond to state comments within a reasonable time period (Priority 1) . 8. Implement jointly with the EPA regional office regularly scheduled management meetings between the grants program managers within each organization. These meetings should be designed to keep lines of communication open and should be used to discuss such things as new program re- quirements, program status, major program issues, projects of interest to EPA, anticipated outputs over the coming months, problems being encountered, etc. (Priority 1). 9. Establish a formalized means of communication with consultants, grantees and others having an interest in the program. Such communications should address issues on a broader scope than the project-by-project and issue-by-issue communications which typically take place on individual projects. The development of an advisory committee repre- senting the various interests in the program, and the publication of newsletters and/or grants bulletins should be considered (Priority 2 in larger states and Priority 3 in smaller states). 10. Pursue responsibility for the entire program, including the construction portion of the program. Where 2-13 ------- the Corps of Engineers is performing construction-related activities, the states can still assume overall responsi- bility for the construction part of the program, i.e. the state can oversee and coordinate the activities of the Corps of Engineers. A good way to accomplish this is to have a construction management coordinator in a smaller state, or, in a larger state, a construction management unit (Priority 1). 11. Seek all delegable functions associated with the program. Do not hold back on taking certain functions be- cause of a disagreement over the policy behind the function (Priority 1). 12. Actively support amendments to Section 205(g) of the Act which would provide a more adequate amount of admin- istrative funds for delegated states (Priority 2). Recommendations for EPA Regional Offices 1. Delegate all legally delegable functions to the delegated states, including preparation of federal grant offers and environmental assessments, the official project files, GICS and the processing of payments (Priority 1). 2. Examine the phase-in schedules for all delegated states to insure that delegation is moving as rapidly as possible, compressing existing schedules wherever possible (Priority 1). 3. For newly delegated states, phase delegation of individual functions so that entire blocks of functions (as opposed to discreet disconnected functions) are dele- gated. For example, do not delegate some of the functions associated with processing a Step 1 application package without delegating all of the functions associated with that action; similarly, do not delegate some of the func- tions associated with the review of facilities plans without delegating all associated functions (Priority 2). 2-14 ------- 4. When a new requirement is imposed on the program, the states should administer the new requirement from the start. It ought not to be administered initially by the regions. Where an amendment to the delegation agreement or a new appendix is necessary, states should initially administer the requirement in accordance with interim pro- cedures agreed to with the region until the amendment or new appendix is developed. (Priority 1). 5. Encourage the states to assume all program manage- ment responsibilitiesr including responsibility for the Step 3 portion of the program (even though many of the Step 3 activities are performed by the Corps of Engineers). Relative to Step 3, this could be accomplished by encourag- ing the Corps of Engineers to enter into an agreement with the states, or alternatively, specifically delegating the responsibility for managing the Step 3 portion of the program to the states (Priority 2). 6. Devote greater resources and attention to providing better and more intensive training and guidance to states in advance of the scheduled dates for state assumption of dele- gated functions (Priority 1). 7. Encourage states to develop the capablity to interpret federal regulations and policies and to make such interpretations as long as they are found (through the after-the-fact monitoring program) to be consistent with those regulations and policies. Further, do not impose restrictive regional interpretations of national policies on delegated states (Priority 3). 8. Reassess the region's organizational structure and resource needs in light of the impending, fully dele- gated mode of operation. Most regions should be ready to implement any organizational changes prior to the end of calendar year 1981, at which time almost 60% of the states will be fully delegated (Priority 2). 2-15 ------- 9. Develop a means of coming to agreement with dele- gated states as to program direction, goals, and objectives, in addition to the agreements already reached on program resources and outputs. The State EPA agreement can be a useful mechanism for dealing with these issues (Priority 3). 10. Develop a series of management reports (perhaps in conjunction with other regions and headquarters) that meet the region's needs under delegation. The availability of a state-prepared monthly management report (previously re- commended) will help in this regard, but will not be totally sufficient to meet regional needs (Priority 2). 11. Implement jointly with each of the delegated states a regular and formalized means of communication, along the lines of a regularly scheduled management meeting. These meetings should be used to discuss program and pro- ject-related issues and problems, and to insure that the regions and the states are getting the information they need to carry out their responsibilities under delegation (Priority 1). 12. Re-evaluate the need for regional receipt of specific documents and information in relation to individual grant projects. Cease receiving those documents and pieces of information that are unnecessary to the region's func- tioning insofar as taking the project-related actions that it must take under delegation (Priority 2). 13. Implement a regional policy whereby after a func- tion has been delegated, state certifications of individual grant applications are accepted without review of supporting documents. A relatively short, specifically defined initial period of review is acceptable if there is some concern about the state's ability to administer the delegated function. Generally, however, training and guidance in advance of delegation of specific functions is preferable to this approach (Priority 1). 2-16 ------- 14. Focus greater attention on the time expended for regional processing of state-certified grant awards and FNSI's. Specifically, the regions should develop time-based goals for each of these reviews, hold staff responsible for meeting the goals, and routinely monitor actual perfor- mance as compared to the goals. The goals for the proces- sing of grant awards should be in the order of 5 to 10 days each and the goals for issuance of FNSI's should be in the order of 30 days or less (Priority 1). 15. Develop and implement a monitoring and evaluation program to insure that the delegated states are administer- ing the program in accordance with national program goals and in a manner that maintains program integrity and public trust. The guidance currently being prepared by EPA can be used as a starting point for the development of the monitoring and evaluation program (Priority 1). Recommendations for EPA Headquarters 1. Draft and support amendments to Section 205(g) of the Act which would make the source of funding for the states more adequate. Recent amendments to the Clean Water Act have tied Section 205(g) funding to the authorizations contained in the Act, and will make funding far more stable. However, the 2% level will have to be increased to allow states to assume all delegable functions (Priority 2). 2. Amend the State Management Assistance Grant Regula- tions to allow delegation of the following functions: civil rights determinations, final dispute determination, bid protests, and resolution of audit exceptions. Wage rate determinations, currently considered by many regions to be non-delegable, also should be delegated (Priority 1). 3. Initiate actions to legalize delegation of the signing of grant awards to the states. In the interim, while the legal aspects of this are being worked out, 2-17 ------- initiate a procedure whereby both the region and the state sign the grant awards (Priority 2). 4. Initiate a pilot program in several states to delegate NEPA. Based on the results of the pilot program, EPA should make a decision as to whether NEPA should be delegated to the states (Priority 2). 5. Amend the national Corps of Engineers agreements to require the Corps, of Engineers to enter into agreements with delegated states rather than with EPA regional offices, at the time a state has received full delegation of all other delegable functions (Priority 2). 6. Develop a program that will lead to delegation of all 50 states within the next several years (Priority 2). 7. Develop a policy for administering the grants pro- gram in those states which are not interested in or are not capable of administering the delegated program. Consider making use of EPA-staffed field operations offices similar to those in Region X, IPA's to the states, service centers, or some combination of these (Priority 2). 8. Assist EPA regions in the development of management information systems and reports that will meet their needs under delegation (Priority 2). 9. Assist states in the development of management information systems and reports that will allow them to make sound program management decisions (Priority 1). 10. Assist states in the development of several model project tracking systems. At least two models should be developed, one for the larger states and one for the smaller states (Priority 1). 11. Establish several management assistance teams within EPA to assist states in improving their overall management and administration of the delegated program. These teams can be located either in headquarters, in several regions, or at several "service centers". These teams should be made up of trained and experienced people 2-18 ------- with expertize in management and administration. These teams could also be utilized to assist the regions in improving their management of the delegated program (Priority 3). 12. Amend the Regional Report Card System to reflect delegation. As far as delegation is concerned, the report card scores should reflect the regions' progress towards delegation, regional processing times on state-certified documents, the regions' monitoring program, and the perfor- mance of the states within the region (Priority 1). 13. Develop an overall focus for the program, includ- ing a clearly defined objective to work towards and a realistic time frame in which to accomplish this objective. The chosen objective should be the driving force behind administration of the program at the federal, regional, and state levels. The status of progress towards the objective should become a measure of the success of the program. (The 1990 Construction Grants Strategy is intended to develop this focus)(Priority 2). 14. Develop a headquarters program to monitor and oversee delegation (Priority 2). The program should include the following: • An up-to-date system that contains basic informa- tion on the status of delegation, the budget, and the resources associated with each delegated state and each region (much of this information is already maintained within OWPO). • An annual assessment of how well each region is performing its responsibilities under delegation (the report card can be used to supplement this evaluation). • A biennial assessment of how well each state is fulfilling its responsibilities under delegation, drawing upon the results of regional monitoring efforts. 2-19 ------- A means of identifying significant problems and needs associated with delegation. The preparation of a biennial report which sum- marizes the above information and findings and contains recommendations for improving the dele- gated program. For the next several years, an annual report would be desirable. 2-20 ------- CHAPTER 3 STATUS OF DELEGATION This chapter describes the current status of delegation throughout the country. It identifies which states have en- tered into delegation agreements with EPA, and describes the current status of state assumption of delegable func- tions. The chapter begins with a description of the pro- cesses and steps necessary for states to enter into delega- tion agreements and to take over administration of all of the delegable functions. Such background information is valuable in assessing the status of delegation. THE DELEGATION PROCESS The process of delegating authority to administer the construction grants program to the states and the subsequent process of the states taking over all delegable functions is not a simple one. The first requirement for delegation is a state which is interested in delegation and, as assessed by the respective EPA regional office, is qualified for and capable of administering the program. In fact, a number of states are not interested in delegation. Further, in the case of several states, the regions have been hesitant to delegate because of a lack of confidence in the state's ability to run the program. Once an EPA region and a qualified state agree to pursue delegation, a number of actions must be taken before a dele- gation agreement can be executed. The state must make a work load analysis and estimate the manpower needed to take over each aspect of the program. Next, the state generally has to develop an appropriate organizational structure. Finally, the state must get the concurrance of the governor's office and the state legislature to assume 3-1 ------- delegation and to hire the staff needed to administer the program, as indicated by the manpower analysis. Often these requests are forwarded to the governor and legislature in the form of a budget request during the state's normal budget cycle. During this time, the state and the region are normally negotiating the terms of the general delegation agreement and the attached appendices, which describe how the state will perform the individual functions which are to be initially delegated. Generally, a number of specific functions, such as plans of study, infiltration/inflow analyses, etc., are delegated to the state upon execution of the delegation agreement, and the remaining functions are scheduled for delegation over a several year period, as the state adds and trains new staff. The delegation agreement initially includes only those appendices which describe the functions to be delegated upon execution of the agreement. The drafting and negotiation of the appendices which deal with functions to be subsequently delegated take place later, generally just before the state's scheduled assumption of those functions. During negotiation of the delegation agreement, numer- ous points of disagreement may arise between the region and the state. These may include the sequencing of state assumption of specific functions, the magnitude of the state staff to be employed, and the detailed procedures outlined in the appendices relative to each initially delegated function. Differences in opinion between the EPA regional office and the state over such issues can extend the negotiation period. From a regional perspective, the most difficulties arise in developing the first delegation agreement. Once a region goes through the process of developing and negotiating a delegation agreement and appendices with one state, the same agreement and appendices are generally used, with 3-2 ------- only minor changes, for all future delegations within the region. Within a given region, regional office negotiations re- garding delegation generally start with a larger state which has previous, significant involvement in grants pro- gram administration, generally under a Section 106 delega- tion agreement. (Under Section 106 of the Act, many states were reviewing plans and specifications, operation and maintenance manuals, and change orders.) Once the basic agreement and the appendices are worked out with the first state, or when negotiations are fairly far along, the region usually begins negotiating with other states. At the same time, states with only casual initial interest in delegation tend to become more interested, as they observe other states in the region actively pursuing delegation. Upon execution of the delegation agreement, a state generally is given immediate authority to administer the initially delegated functions, with state assumption of the remaining functions phased in accordance with the negotiated time schedule contained in the agreement. Usual- ly less than half of the delegable functions are delegated to the state upon execution of the agreement. Most agree- ments provide a 15 to 36 month transition period for state assumption of all of the remaining functions. Prior to taking over subsequent functions, the state must recruit and train new staff. In some cases, it is necessary for states to establish new civil service classi- fications or increased salary levels to allow recruiting of qualified personnel. In addition, prior to state assump- tion of subsequent functions, new appendices must be draft- ed and negotiated. Sometimes they are drafted initially by the region, sometimes by the states, and, in some cases, it is a joint effort. A number of factors may interfere with state adherence to the schedule contained in the delegation agreement for 3-3 ------- assumption of the remaining delegable functions. The state may encounter difficulty in hiring staff. Either the region or the state (whoever is responsible for preparing the drafts of subsequent appendices) may be diverted to other activities, considered to be of higher priority. There also may be disagreements over the procedures to be included in the new appendices. Any of these occurrences may cause delays in meeting the original time schedule. The bottom line is that the process of delegating full authority to administer the program to the states is a lengthy one, requiring considerable time and effort of both the re- gional offices and the states. It is not a quick process in cases where everything goes well, and usually at least some problems are encountered. It is therefore not surprising that, three years after passage of the 1977 Clean Water Act, no state has yet taken over the program in its entirety. In fact, only 13 states have assumed all the functions except those administered by the Corps of Engineers and one or more new program re- quirements. While many states have executed delegation agreements with their respective regional offices, most are in a transition phase. They are administering some of the functions related to the processing of individual grant projects, but the regions are still administering a number of delegable functions. DELEGATED STATES At the time of this report 37 states have entered into de- legation agreements with their respective regional offices. The states, together with the dates their agreements were executed, are listed in Table 3-1. This table also identi- fies the non-delegated states, including the several states which are currently negotiating agreements with EPA. 3-4 ------- TABLE 3-1 STATUS OF STATE DELEGATIONS* Region Delegated States I New Hampshire Maine Vermont Connecticut Massachusetts Rhode Island II New York New Jersey III Maryland Pennsylvania West Virginia Delaware IV Georgia South Carolina Mississippi North Carolina Kentucky V Illinois Wisconsin Minnesota Michigan VI Texas Oklahoma VII Missouri Nebraska Iowa VIII South Dakota Wyoming Montana North Dakota Colorado Utah IX California Arizona X Alaska Idaho Washington Agreement Date 10/6/78 4/16/79 5/11/79 6/1/79 9/21/79 9/25/80 12/26/78 9/26/79 1/10/79 7/2/79 7/11/79 9/26/80 10/26/78 3/15/79 12/12/79 12/26/79 7/27/80 8/3/78 10/2/78 3/14/79 3/30/79 9/8/78 2/29/80 5/30/79 7/31/79 9/22/80 4/6/79 5/21/79 7/9/79 8/17/79 9/27/79 9/27/79 8/17/78 3/29/79 12/7/78 3/5/79 8/17/79 Non-Delegated States Virginia Alabama Florida Tennessee Indiana Ohiob Louisiana b New Mexico Arkansas" Kansas Hawaii Nevada5 Oregon As of October 1980. These states are currently in the process of negotiating delegation agreements. 3-5 ------- Of interest is that 74% of the 50 states have entered into delegation agreements. These delegated states also, coincidently, receive 75% of the annual appropriation under the current allotment formula and they have 74% of the active construction grants projects (as indicated in EPA's "Activities of the Grants Assistance Programs" July 1979). The 3 largest states which are not delegated are Ohio, Florida, and Indiana. These 3 states account for over half of the appropriations that go to the 13 non-delegated states and 40% of the active projects. Of the 13 non-delegated states, five (Alabama, Ohio, New Mexico, Arkansas and Nevada) are currently negotiating delegation agreements and it can be expected that they will be executed in Fiscal Year 1981. In 2 of the states (Indiana and Hawaii), there is state interest in delegation, but the respective regions have concerns that are causing them to proceed cautiously. In the case of Indiana, the region is concerned that the organizational structure within the existing state agency may not be amenable to administering the program effective- ly. The region is also concerned that the low salary structures in the state may prevent the state from attract- ing and maintaining qualified personnel. The region has asked the state to perform a management and organization study. In the case of Hawaii, the region feels that the state is currently burdened with the task of assuming other delegable EPA programs and lacks sufficient interest at this time to lead to the necessary commitment to the grant program. Therefore, the region is not actively pursuing delegation. The 6 remaining non-delegated states (Virginia, Flori- da, Tennessee, Louisiana, Kansas and Oregon) are not pursu- ing delegation at this time because of the resource implic- ations. In each case, the state's administration has a policy not to expand the state government's staff, even if 3-6 ------- the expansion is to be financed by federal funds. Until these current policies change, it is unlikely that any of these states will seek delegation in the near future, although several of the regions (Region VII in the case of Kansas and Region VI in the case of Louisiana) are active- ly pursuing delegation. In summary, 37 states have executed delegation agree- ments. Five states will likely execute agreements in the near future and two additional states may possibly execute agreements within the next year or two. Six states are not expected to enter delegation agreements within the next several years, if at all. STATUS OF STATE ASSUMPTION OF DELEGABLE FUNCTIONS As stated peviously, most delegated states are in the transition process of taking over administration of the numerous delegable activities from the EPA Regional Offices. Most of the 37 delegated states have taken over significant functions, but at the same time a number of significant functions have not yet been delegated and are still being administered at the regional level. Also, under a separate national agreement with EPA, the Corps of Engineers is performing construction inspections and related activities in 33 of the 37 states. At the present time, in most states there are three agencies administering parts of the construc- tion grants program: the regions, the Corps of Engineers, and the states. The current status of delegation in each of the 50 states in relation to the 28 most significant functions associated with program administration is shown in Table 3-2. This table also indicates the number of states to which each function has been delegated. As can be seen, functions related to plans and specifications, operation and maintenance manuals, change orders, pre-application conferences, and Step 1, 2, 3-7 ------- TABLE 3-2: STATUS OF STATE ASSUMPTION OF DELEGABLE FUNCTIONS Function a STEP 1 Preappli cation Conference Step 1 Application Plan of Study Public Participation Infiltration/Inflow, SSES Environmental Assessment Facility Plan STEP 2 Step 2 Application Value Engineering Bi ddabi 1 i ty/Constructab i 1 i ty Plans and Specifications STEP 3 Step 3 Application User Charge/ICR Sewer Use Ordinance 0 & M Manual Bid Documents Preconstruction Conference Change Orders Interim Inspections On Site Presence Final Inspections Pretreatment ALL STEPS A/E Subagreements MBE Federal Grant Offer Payments GICS Official Files Region I a s s s s s s s s s c s s s s s s s s s c s s s 5 s w s s c s s s s c s c c c s s s w s s s c s s s s s s c c c s NH s s s s s s s s s s s s s s s s s s s s s s s s s R s s s c s s s s s s s s s V7 s s s c s s s s s s s s s s s Rpr s c s c c c c c c TT NY s s s s s s s c s s s s s s s s s c s s s s s Reqion III c c c c c c c s s s s s s s s s s s s s s s s s s s s s s s s s s s s s s s s s s s s c s s c c s c c c s s s s VA c c c c c c c s c s s s c s s c c c Reqion IV Al. c c c c c c c c c c c c c c GA s s s s s s c s s s s s s s s s s s c c c s s s s s s c c c c c c c s s s s s s s c s s s s s s s c c c c s s s s s s s s s s c s s s s s s c s c c c s s s s s s s s s s c s s s s s s s s c c c s i> s s IN c c c c c c c Rec Tl s s s s s s s s s s s s s s b s s s s c s s s s s b IN c c c c c c c c Ml s s s s s s s s s c s s b s b b b b c c c b s s s ion V 1 MN s s s s b s s s s c s s b b b b c b c c c b s s s s OH c c c c c c c Ml s s s b b b b s b b b s s s s s c s b c b s s s s s u> I 00 5 Function delegated to state; cFunction performed by the Corps of Engineers; dl Function performed by EPA *This table includes the 28 most significant functions, but excludes a number of functions typically delegated. ------- TABLE 3-2: STATUS OF STATE ASSUMPTION OF DELEGABLE FUNCTIONS Function3 STEP 1 Preappli cation Conference Step 1 Application Plan of Study Public Participation Infiltration/Inflow, SSES Environmental Assessment Facility Plan STEP 2 Step 2 Application Value Engineering Bi ddabil i ty/Constructabil i t> Plans and Specifications STEP 3 Step 3 Application User Charge/ICR Sewer Use Ordinance 0 & M Manual Bid Documents Preconstruction Conference Change Orders Interim Inspections On Site Presence Final Inspections Pretreatment ALL STEPS A/E Subagreements MBE Federal Grant Offer Payments GICS Official Files Region VI AR LA c c c c c c c c c c c c NM c c c c c c OK s s b s c s s s s s c c s c c c s s TX s s s s s 5 s s s s s s s s s s s s s s s s s s s s s Region VII TA1 c c c c c KS c c c c c MO s s s s s s s s s c s s s s c s c c c s s NB s s s s s s s s s c s s s s c s c c c s s Region VIII CO s s s s s s s s c s s s s c c c s s MT s s s s s s s s c s s s s s s s s s s s s s s s s ND s s s s s c s s s s s c c c s SD s s s s c s s s s c c c s UT s s s s s s s s c s s s s c c c s s WY s c s s s c c c s Region IX AZ s s s s s s s s s c s s s s s s c s c c c s .s s s s s s CA s § $ s s s s s s c s s s s s s c s c c c s s s s s s s HI c c c c c NV c c c c c Region X AK 5 S 5 S g s s s s s c c c s s ID s s s s s S c s s s Q c S C c c s OR c C c, c c c WA s s s s s s s s s c s s s s s s s s Q c c s s s STATE 34 29 27 20 25 22 19 28 21 6 33 25 23 26 33 18 16 32 10 5 10 16 21 2 18 19 23 8 Total CORPS 44 16 28 9 40 45 40 3 EPA 16 21 23 30 25 28 31 22 29 17 25 27 24 17 16 6 9 34 29 48 32 31 24 42 LO I 5 Function delegated to state; c Function performed by the Corps of Engineers; CUFunction performed by EPA This table includes the 28 most significant functions, but excludes a number of functions typically delegated. ------- and 3 applications are the functions for which authority has been delegated to the greatest extent. Of interest, a number of states had been delegated authority to review plans and specifications, change orders and operation and maintenance manuals under Section 106 of the Act, prior to the Section 205(g) delegation agreements. Table 3-2 shows that the least delegated functions are minority business enterprises (MBE) and the various functions that are typically performed by the Corps of Engineers, name- ly, biddability/constructability reviews of plans and spec- ifications, and interim, onsite, and final construction inspections. At the present time, 13 states have assumed all deleg- able functions except for MBE and/or those functions which are typically performed by the Corps of Engineers. These 13 states are listed in Table 3-3. Table 3-3 also lists the dates by which additional states are expected to become es- sentially fully delegated (i.e., all functions delegated except for MBE and those performed by the Corps of Engineers). As can be seen from Table 3-3, within one year, 27 of the 37 delegated states will be essentially fully delegated. It is difficult to anticipate the rate at which states will assume the construction-related activities that are cur- rently being performed by the Corps of Engineers. In fact, it is possible that some states will never assume these responsibilities. Most states are interested in eventually taking over all delegable program functions, including those being administered by the Corps of Engineers. How- ever, at this time, only 4 states (New Hampshire, Maryland, Texas, and Montana) have done so and only 2 additional states (Georgia and Pennsylvania) anticipate taking over Corps of Engineers activities within the next year. Most states plan to continue to rely on the Corps of Engineers to perform these functions in the foreseeable future. 3-10 ------- TABLE 3-3 SCHEDULE FOR FULL DELEGATION Date for Full Delegation9 State (Region)c Presently Delegated Connecticut (I) New Hampshire (I) Maryland (III) Georgia (IV) Illinois (V) Michigan (V) Minnesota (V) Wisconsin (V) Texas (VI) Montana (VIII) Arizona (IX) California (IX) Washington (X) Cumulative Total By March 1981 By June 1981 By September 1981 By December 1981 By December 1982 By December 1983 Colorado (VIII) Alaska (X) Idaho (X) New York (II) Pennsylvania (III) North Carolina (IV) North Dakota (VIII) Massachusetts (I) South Carolina (IV) Missouri (VII) Nebraska (VII) Vermont (I) Mississippi (IV) Utah (VIII) Maine(I) Rhode Island (I) West Virginia (III) South Dakota (VIII) New Jersey (II) Oklahoma (VI) Wyoming (VIII) 13 16 20 24 27 31 34 Full delegation is defined as including all delegable functions except those commonly performed by the Corps of Engineers and MBE. 'Delegated as of October 1980. •» 'Schedules were unavailable for Delaware, Kentucky and Iowa. 3-11 ------- For several reasons, states are not moving as aggressi- vely to take over the Corps of Engineers-administered activities as they have the EPA-administered activities. Probably the biggest reason is the concern about the adequacy of funding available under Section 205(g) to cover the additional administrative activities, and the uncertain nature of this funding. States either don't have sufficient funds available from Section 205(g) to take over these activities, or, if they do they are concerned about the uncertainty of future funding levels. The problems incurred by California have caused most states to move cautiously into this area. California, once fully delegated, was forced to reduce staff and turn much of the construction related activities over to the Corps of Engineers as a result of reduction in appropriations over recent years and corres- ponding reduction in Section 205(g) funding. The states that presently have sufficient funds are hesitant to add the staff necessary to take over these functions; the states fear that they may later have to lay off staff and once again involve the Corps of Engineers in their program. The states would rather wait until the funding source is made more adequate and predictable. The other reason keeping some states from aggressively moving to take over activities presently performed by the Corps of Engineers is that they feel that the most critical functions are in Steps 1 and 2 of the process. These states are satisfied with having the Corps of Engineers perform the construction-related functions in Step 3 in the near term as long as the Corps of Engineers does a good job. In summary, delegation is in a transition phase, with the construction grants program moving from an EPA-state administered program to a state-Corps of Engineers adminis- tered program. At the present time, all three agencies are performing functions in most states, though EPA is 3-12 ------- essentially out of the program in 13 of the 37 delegated states, administering only the MBE function and several non-delegable functions. Within a year, however, 27 states will be essentially fully delegated. It is likely though, that the Corps of Engineers involvement will continue in most states indefinitely. At present, the Corps of Engine- ers is involved in all but 4 states, and even after a year, they will still be involved in performing construc- tion inspections and related Step 3 activities in 31 of the 37 delegated states. So, whereas the EPA-to-state delegation process will be completed in 27 states within a year, a dual agency involvement, in terms of the states and the Corps of Engineers will continue indefinitely in all but 6 states. 3-13 ------- CHAPTER 4 EPA REGIONAL OFFICE PERFORMANCE UNDER DELEGATION This chapter presents a general evaluation of the per- formance, with regard to delegation, of the EPA Regional Offices. Under delegation, regions continue to have numer- ous and important responsibilities relative to the construc- tion grants program. The more important responsibilities include the following: • To implement delegation in interested and qualified states. • To adequately organize and staff to oversee the delegated program in each state. • To effectively manage the delegated program. • To employ grant processing procedures for state certifications and for non-delegable functions which are consistent with the concept of delegation. • To process state certifications and perform other non-delegable functions in a time-efficient manner. • To effectively monitor and evaluate the performance of delegated states. In addition to the major responsibilities outlined above, the regions have numerous other responsibilities related to delegation, including the interpretation of policies, communication and coordination with EPA Headquar- ters, responding to public and congressional inquiries, etc. The general performance of the ten EPA Regional Offices in each of the six areas listed above is discussed in the following paragraphs. It should be noted that the regional office performance as presented in this chapter is based on field observations made by the authors between May and August of 1980. Since that time the regions have continued to improve their operations under delegation. The result of this continuing improvement is that a number 4-1 ------- of the problems, identified in this chapter may already have been eliminated and a number of the recommendations already implemented. PROGRESS TOWARD DELEGATION The regions are responsible for implementing delega- tion. Specifically, this responsibility includes executing delegation agreements with interested and qualified states, turning over the various delegable functions to the delega- ted states in accordance with a reasonable time schedule, and training delegated state staffs, where needed, in the performance of delegated functions. Insofar as their progress towards entering into delega- tion agreements is concerned, the regions have an impressive record. As indicated in Chapter 3, 37 of the 50 states have executed delegation agreements as of this time. Within a year that number will increase to between 42 and 44, leaving between 6 and 8 states non-delegated. Considering that 6 of the non-delegated states do not wish to pursue delegation because they have policies against expanding state govern- ment staffing, this is an impressive record. The regions generally have been able to negotiate dele- gation agreements with interested states, even if the states had little or no previous experience in the program. In those cases where a state has not established a track record in the program, the regions often require as conditions of delegation, certain changes in the state's organizational structure, resources, procedures and/or employee classifi- cation system. In some cases, especially where the states greatly expanded their staffs, the regions insist on compre- hensive state-developed training programs (Region II in the case of New York), or conduct extensive training programs themselves for the states (Region IX in the case of Arizona). In almost all cases, it appears that if a state is int- 4-2 ------- erested in delegation, the region (even if it has concerns about the state's experience or capabilities) pursues dele- gation, while at the same time trying to build capability at the state level. Another tactic utilized in this situa- tion is to extend the transition period for full delegation. The regions appear to be quite aggressive in implement- ing delegation agreements. Several were active at the Gover- nor's Office level, working to generate state interest in delegation. Others were actively involved in encouraging state legislators to increase state salary levels so that the state could attract qualified personnel to administer the delegated program. One region funded a management and organ- izational study to assist a state in determining the best organizational structure and the resources needed to admin- ister the delegated program. Several regions have sent EPA employees on one- or two-year assignments to the state offices to assist them with getting their programs operating. There is considerable variability in the rate at which regions are turning over administration of specific functions to delegated states. The average time spent or anticipated in each region to delegate all of the activities to the delegated states (except for those activities typic- ally performed by the Corps of Engineers) is shown in Table 4-1. As can be seen, the average time for the states to take over full program administration is 23 months, or just under two years. In a number of regions (Regions IV, V, and IX), states have typically assumed the program in a year and a half. At the other extreme (Region II) the time for full state assumption of the program is three years. A number of factors affect the time required for full delegation, includ- ing the judgement of the individual regional offices and the states as to what is a reasonable time period for transition to full delegation, and the previous experience of the state with the construction grants program. 4-3 ------- TABLE 4-1 TIME FOR FULL STATE ASSUMPTION OF ALL DELEGABLE FUNCTIONS3 Region I II III IV V VI VII VIII IX X TOTAL Number of States 6 2 3 4 4 2 2 6 lc . 3 33 Average Time for Full Delegation, Months9 22 36 24 18 16 26 26 27 19 21 23 aBased on the time spent or anticipated (after signing of the dele- gation agreement) for states to assume authority for all functions except MBE and those functions typically performed by the Corps of Engineers. Only those states where firm target dates for full delegation exist and were available at the time of the study are shown. GDoes not include California, which was already fully administering the program prior to execution of the Section 205(g) delegation agreement. 4-4 ------- At this point in time, the dicussion is somewhat aca- demic, as most of the states presently delegated will be fully delegated within a year. It is felt, however, that it may be possible for several of the current delegation schedules to be accelerated: New Jersey (Region II), Okla- homa (Region VI), and Wyoming (Region VIII). One additional point under "Progress Towards Delega- tion" relates to the fact that the delegation agreements executed by some regions do not provide for delegation of all delegable activities. In some cases, such as MBE, it appears that some regions question whether that function is delegable. In other cases there is no question about delegability; rather, the region has either made a decision not to delegate certain functions or has merely overlooked several functions typically delegated. In these cases, the states have not been aware of, or if they were, have not pressed delegation of these functions. As an example, in one region (Region X), the preparation of preliminary environmental assessments, the preparation of federal grant offers, the processing of interim payment requests, and the maintenance of the official project files have not been scheduled for delegation. In a few other cases, states have been hesitant to assume certain functions. There has also been some slippage of scheduled dates for state assumption of delegable functions in most regions. In general, the slippage appears due to either the regional office or the state, or both, being diverted from perform- ing actions necessary to maintain the schedule, to activi- ties considered to be of higher priority. The training provided by the regions to the delegated states has been quite variable. There are several outstand- ing examples of training provided by the regions. The best example pertinent to a state with little prior experience in the grants program was where a region (Region IX) sent a 4-5 ------- 4-person team of highly qualified personnel to a state (Arizona) for a one-year period on an "IPA" assignment. Two of these people helped the new state staff establish proce- dures, and the other two trained the staff. One person trained the technical staff and one trained the administra- tive staff. This particular effort produced impressive results as the state, with over 90% of its staff on board for less than a year, has a program as good as many of the states with years of experience in the program. Several other regions had impressive on-the-job type training efforts in certain states (Region III in the case of Pennsylvania, Region VIII in the case of Montana, and Region X in the case of Washington). These programs appeared somewhat unique to the given state rather than a regional practice. In the case of Regions VIII and X, these training programs were facilitated by regional operations offices located in the respective states involved. Other regions had on-the- job training efforts limited in scope and directed toward several delegated functions (A/E subagreements, preparation of federal grant offers, preparation of environmental docu- ments, etc.). One region (Region II) required the state to develop and conduct an intensive training program for its new staff. Another region (Region I) is in the process of conduct- ing an extensive training program for all the states within the region relative to the environmental aspects of the pro- gram. To assist with this effort, the region, in conjunction with a private consulting firm, has prepared a detailed envi- ronmental review manual. This manual was designed to assist states in gaining an understanding of EPA's environmental review requirements. It contains all of the procedures and requirements of the major environmental laws, regulations and policies that impact on the construction grant program. This manual is being supplemented with a two-day training session in each of the region's states. 4-6 ------- Even though there are outstanding examples of regional training efforts as noted above, the training more typically provided by the regions to the delegated states has been relatively modest. The training more commonly provided includes the scheduling of the standard EPA training courses in the region, telephone consultation with state staff on specific questions, and the presentation of several lectures on individual review functions in the state offices. In some states with considerable past experience in the program, this level of training is satisfactory; but, in the less experienced states, it falls short of needs. ORGANIZATIONAL STRUCTURE AND RESOURCES As stated in previous sections of this report, most regions are in a transition phase, moving from the previous non-delegated mode of operation towards a fully delegated program. Within a year, this transition period will be complete for approximately 27 of the 37 presently delegated states. In general, the present organizational structures utilized by the regions, and to a lesser extent the resources available, represent a non-delegated mode of operation. The current organizational structures and resource levels, though adequate prior to delegation and even during the transition period, are not well suited for a fully delegated mode of operation. ' The present organizational structures utilized by the regional office water divisions are highly variable. Three regions' water divisions (Regions II, III, and IX) are organ- ized on a geographical branch basis, with each geographical branch being responsible for all of the water program activities within a given state. The remaining 7 regions have programmatic based branches, with each branch respon- sible for a different program area. Within these branches, the individual sections are often organized on a geographi- 4-7 ------- cal basis, with each section being responsible for the particular program in a given state. In 4 of these latter 7 regions (Regions IV, V, VII, and VIII), programmatic activities associated with the construction grants program are divided between two programmatic branches. While the two programmatic branches generally both have state sec- tions, no single person within the regional organizational structure has total responsibility for administration of the grants program in a given state (though one of the two section chiefs may have a lead responsibility). Several regions have implemented organizational changes to accommodate delegation. In one case (Region IX), the region has set up geographical branches to handle all of the water program activities within a given state, and has developed a program support branch to provide technical support to the branches and to coordinate the grants-relat- ed activities in the various branches. Region III has an organizational structure almost identical to that in Region IX. Another region (Region II) already having geographical branches, has developed state-wide program support sections within each of the two geographical branches, separate from the grants processing sections. The state-wide sec- tions have responsibility for programmatic dealings with the individual states, whereas the grants processing sec- tions have responsibility for processing certified grant documents and peforming non-delegated functions associated with individual grant projects. Of the ten regional offices, two are considered to have organizational structures well suited for a delegated mode of operation (Regions III and IX). Four others (Regions I, II, VI, and X) have organizational structures that could easily accommodate a delegated mode of operation, though organizational modifications may be beneficial. The remaining four regions (Regions IV, V, VII, and VIII) should evaluate possible organizational changes to facili- 4-8 ------- tate a delegated mode of operation. In terms of organizational needs under delegation four basic types of needs exist within the regional offices. First, there is a need for resources to process certified grant applications and associated documents. Resources are also needed to perform non-delegated NEPA activities. There is a need for resources to oversee the program, in- cluding day-to-day communication and coordination with the states. Finally, there is a need to monitor the perfor- mance of individual delegated states. Examining each of these four needs and the best way to satisfy each, gives some indication of the type of organiza- tional structure that might be best suited for delegation. For example, the need for program management and coordina- tion with delegated states should be the responsibility of a high level program manager within the regional office, whose responsibilities are limited to a single delegated state (an exception could be made in regions with a large number of small states, where one program manager could be responsible for two states). This suggests the need for a geographical section containing the program manager together with a limited number of staff, to process state certifica- tions and perform non-delegated NEPA activities. These geographical units could also be responsible for other water programs in a given state. Because of the relatively minor resource needs, however, these geographical branches or sections would be small in size. With regard to the regions' monitoring responsibilities under delegation, a different approach is suggested. To adequately monitor the performance of delegated states, regions need to have personnel who are experienced and specialized in particular program activities. For example. the region should have a sanitary engineer who is familiar with facilities planning, design, and other related techni- cal activities. The region also needs expertise in the 4-9 ------- administrative area, the environmental area, and in certain other areas such as user charges, operation and maintenance, etc. It is questionable whether such resources, needed only for monitoring the performance of delegated states, could be duplicated in each of the relatively small geo- graphical branches or sections that have responsibility for program management, processing of certifications, and performance of NEPA functions. This, therefore, suggests utilizing a separate pool of specialized resources for monitoring all of the delegated states within a particular region. Of the existing organizational structures utilized by the regional offices, both Region III and Region IX have organizational structures that are oriented in the above suggested direction. Region IX is probably the best example because that region is well into delegation in both of the two delegated states within the region, whereas Region III is only partially through the transition period towards full delegation. Two other regions (Region I and Region VI), have organizational structures that would easily facilitate changes in the direction of the above suggested organizational structure. It would be desirable to implement any necessary organ- izational changes prior to most of the states within a given region achieving full delegation status. As previously indi- cated, this is approximately a year away for most regions. Therefore, it would be desirable for the regions (except for Regions III and IX) to make organizational studies in the near future so that any recommended changes can be placed in operation over the next year. Three regions are already actively working towards this end (Regions I,V, and VIII). From a resources standpoint, the resources presently employed by the regional offices for administration of the delegated construction grants program appear adequate, given the present status of delegation. At the present time, most 4-10 ------- regions are not only processing state certification packages and performing non-delegated NEPA functions, but are also performing other functions which have not yet been delegated, providing increased training to delegated states, as well as, in some cases, performing various technical and adminis- trative activities on projects that preceded delegation and were not turned over to the delegated states. Within several years, this situation will change and the resource needs of the regional offices should be less than they are at the present time. However, all of the regional resources that are currently employed to perform processing activities during this transition phase cannot be eliminated. As pre- viously stated, even after full delegation, resources will be necessary to process state certification packages, to per- form non-delegated NEPA functions, to oversee the program and to monitor the performance of delegated states. While the need for these four functions currently exists, generally the resources that are being applied for overseeing the program and for monitoring are considerably less than those which are needed under a fully delegated mode of operation. Hence whereas the resources utilized for proces- sing individual grant projects will decrease within the next several years, resource increases will have to be pro- vided in these other areas. REGIONAL MANAGEMENT OF THE DELEGATED PROGRAM Several management tools are critical to successful regional management of the delegated construction grants program. These tools include: • An adequate reporting mechanism that allows the region's management to stay on top of and track the progress of the program in each state. • An effective means of communications with each delegated state. 4-11 ------- • An effective monitoring program to assure sound state administration of the program the program. In terms of having adequate reporting mechanisms, the regions generally have available to them considerable manage- ment information, primarily as the result of GIGS. Through various programs available from headquarters, most regions produce numerous GIGS reports on a weekly, monthly, and quarterly basis. These reports provide regional managers with information on grant awards, obligations, outlays, and the status of all funds. GICS reports are also used to identify the length of time that various applications have been in-house at the regional offices. Regional office managers appear to be using these and other GICS produced reports to assist them in fulfilling their responsibilities; these reports also are used by state program managers. While many useful GICS reports are available in each regional they were programmed to serve the regions' needs in a pre-delegation mode of operation. Whereas they satis- factorily met the regions' needs at the time, additional needs exist relative to delegation. For example, there are typical pieces of information that are important under delegation that are not currently contained in the GICS system. These include the regional receipt dates for state-drafted environmental assessments and the dates for issuance of FNSI's. The regional reports also do not report on the progress of projects that are currently in the state offices for processing. Nor do they report impor- tant performance-related aspects of the state's administra- tion of the program, such as state processing time for appli- cations, facilities plans, and plans and specifications. Finally, though unrelated to delegation, GICS reports typic- ally do not contain projections of such important things as obligations, awards, etc. While major changes are not necessary, the current GICS 4-12 ------- generated programs should be re-evaluated in light of a dele- gated mode of operation. Re-evaluation should be conducted over the next year so that by the time many of the states become fully delegated, the regions will have the informa- tion they need to carry out their program management respon- sibilities. Because this same need exists in all ten regions, EPA headquarters, possibly in conjunction with several interested regions, should develop a management reporting system to meet these new needs. State-generated management information reports, designed primarily to meet state management needs, may also be of considerable use to the regional offices, in terms of giving them the information they need to carry out their management responsibilities. Beyond the generally adequate existence of GIGS gener- ated information reports, there is great variability in terms of the regional management of the construction grants pro- gram. A number of regions employ rather unique and impres- sive management practices. For example, several regions (Regions V, VII, and X) have developed performance standards for each regional office employee. Some regions have also developed written procedures manuals to clarify internal operating procedures under delegation (Regions VII and X) . Several regions are conducting regularly scheduled and broadly scoped monthly management meetings with each delegated state (Regions V and IX). One region, in the case of a particular state (Region III, in the state of Pennsylvania) is also holding regularly scheduled monthly management meetings with the state. Another region, in one particular state (Region VIII, in the state of Montana), is conducting monthly training sessions with the state. Several regions are also holding semi-annual meetings with all of the states within the region to update them on current developments relative to the construction grants program (Regions III, VIII, and X). Several regions (Region X being a particularly good example) are utilizing the State 4-13 ------- EPA agreement process as a management tool for guiding the direction of the delegated program. Major issues are iden- tified for resolution, and state and regional performance objectives are identified. Finally, one region has developed a rather unique man- agement tool in cooperation and conjunction with one of its delegated states (Region X and the State of Idaho). This is a computerized project tracking system utilizing GIGS. The system will contain a detailed, continuously updated time schedule for each active project within the state. Regularly produced reports will be used by state grants project man- agers to follow the progress of their individual projects, to identify expected receipt dates of various grant docu- ments, and to generate projections of work load. This is the only sophisticated project tracking system that was observed in any of the 10 regions or states visited during this study Though a number of regions have some interesting and progressive management tools, in general there are some add- itional tools and practices that would assist the regions in managing the delegated program. For example, most regions (all but Regions V and IX) would benefit from establishment of a formal and regular means of communication with each delegated state. It is suggested that regions meet on a regular basis with each delegated state. As an alternative, conference calls could be utilized in place of the meetings, as is done in Region V. At these meetings the regions could update the states on new federal policies, programs, direction, and areas of concern, and likewise the states could update the regional offices on state direction, poli- cies, performance and problems. Also, the regions and states could jointly discuss issues or projects of common interest. Adequate communications are of vital importance to the sucess of a delegated program. The common tendency, as delegation is implemented, is to leave communications to chance and for 4-14 ------- regions and delegated states to communicate with one another only as specific problems and issues arise. Communications are so important that they should not be left to chance. If anything, regions and states should err on the side of over-communications rather than under-communications. Re- gularly scheduled, formalized meetings are an effective way of achieving the necessary level of communications between regions and delegated states. Beyond this, regions might want to consider some of the management tools and practices being utilized within other regions, as previously discussed. Such practices include im- plementation of performance standards, written internal pro- cedures, joint meetings with all of the states within a re- gion, and use of the State EPA agreement as a management tool. Another aspect of the region's management of the dele- gated program that deserves mention is the general attitude that exists within the regional offices towards delegation. In general, the attitude appears to be quite positive, both towards delegation and towards the delegated states. The regions appear to be working cooperatively with the states to accomplish the job of administering the program. In summary, the regions generally employ sound manage- ment practices in administering the delegated construction grants program, though there are needs for modifications in the management information system (i.e., GIGS) and for establishment of regular and formalized communications with each of the delegated states. Beyond those two basic needs, implementation of additional management practices employed in several regions may further assist the regions in carry- ing out their management responsibilities. GRANTS PROCESSING PROCEDURES In evaluating the regions' processing of grants under delegation, the following areas were examined: 4-15 ------- • Is the region processing state certified grant applications and other documents in a way consis- tent with the concept of delegation and in a way that avoids duplication of state activities? • Is the region processing state certified applica- tions without second-guessing state decisions? • Is the region receiving more information than it needs under a delegated mode of operation? As indicated previously in this report, most regions are in a transition stage, performing some functions which have not yet been delegated and reviewing state certifications on other functions which have been delegated. Most regions are still grappling with the issue of how they intend to operate under a fully delegated mode of operation. Those regions which have decided how they intend to operate have not yet reached the point where they are comfortably operating in their intended mode. Few regions are presently operating in a mode that results in maximization of the benefits that could be realized from delegating the program to the states. The one exception to the above comments is Region IX, which has been operating in a fully delegated mode for 5 years. In Region IX, the state of California received delegation in 1975 under a special provision, prior to enactment of the Clean Water Act of 1977. Region IX, there- fore, has had time to adjust its operation for a delegated mode. In fact, Region IX has modified its organizational structure, its allocation of resources, its management of the program, and its grants processing procedures to accom- modate a delegated mode of operation. Most regions are moving in that direction, but they have much more to modify, before they reach the mode of operation employed by Region IX. Before commenting on the regions' grants processing procedures, the authors would like to discuss their concept of the manner in which regions should operate in a truly 4-16 ------- delegated mode. First, the regions should receive only those documents from delegated states (relative to individual grant projects) that are necessary for the regions to take the actions that they have to take under delegation. Basically, there are only four actions that the regions must take on individual projects under delegation. The regions must award grants for Steps 1, 2, and 3, and the regions must either issue the FNSI or prepare a federal environmental impact statement. Under a fully delegated mode of operation, no additional actions need to be taken by the regions' water divisions relative to individual grant projects. Second, the regions should accept state certifications without question and, in conjunction with this, rely on after-the-fact monitoring to determine whether or not state performance is in compliance with the terms of the delegation agreement. Regions should not review certified grant appli- cations to double-check and make sure that the state proper- ly certified a project prior to making a grant award. In comparison to this ideal mode of operation under delegation, most regions are in fact receiving more project- related information and documents than are essential under delegation (except for Region IX). While some regions have moved in the direction of reducing the amount of paper and documents they receive relative to individual grant projects, many are receiving the same amount of documenta- tion that they received prior to delegation. Many regions continue to receive correspondence relating to individual projects, operation and maintenance manuals, sewer use ordinances, facilities plans, plans and specifications, change orders, construction inspection reports, etc. None of these items require action by the regions under delega- tion. While no significant problems result from the regions' continuing to receive these documents, this practice does 4-17 ------- result in unnecessary paperwork and unnecessary expenditure of manpower at both the state and regional offices, and it provides a temptation to regional office staff to review, rather than accept, state actions under delegation. Several regions make the argument that they must continue to receive this information in order to perform their monitoring responsibilities. However, most regions are traveling to state offices and reviewing state files and documents in order to review the small percentage (about 10%) of projects that are evaluated as part of the regions's monitoring program. As to the second point in the ideal mode of operation under delegation, most regions, at the present time, are not achieving the objective of accepting state certifications without further reviewing them. Most regions are performing cursory reviews of all state-certified documents, some in greater depth than others. Only 3 of the 10 regions, at the time the evaluations were made, were operating in a mode of accepting without question state certifications and relying on after-the-fact monitoring to assess and evaluate state performance (Regions V. VII, and IX). Most of the remaining 7 regions recognize that their current mode of operation is inconsistent with the concept of a truly delegated mode of operation and they are moving in the direction of the proper mode of operation One common rationale given for regions failing to accept state certification packages without review is that the regions are performing training of the states through this practice. In other words, by reviewing state certification packages prior to grant award and feeding back any deficiencies to the states, the regions are, in effect, training state staff. The authors recognize this approach as a reasonable one, but have several problems with the manner in which it is put into practice. First, in almost every instance, this "training" is unofficial, i.e., it is not recognized in 4-18 ------- the delegation agreement nor is the state made aware that the region is operating in a training mode. This undoubtedly leads to misunderstandings between the states and the re- gions. From a state perspective, it appears that the region has not accepted delegation and/or lacks trust in the state's abilities. The other problem noted is that, invariably, this "training" practice has no defined time limits. In the regions that are utilizing this technique, the regional staffs could not estimate how long this practice might continue. Nor were management personnel within the respective regional offices able to gauge whether their staff was continuing this practice for an unnecessarily long period, or stopping it too soon. Finally, it should be pointed out that this practice requires resources at the regional level and leads to delays in regional actions on grant awards. This "training" appears to have had an impact on regional approvals of recommended projects on only rare occasions, and in some regions it has kept regional staff so busy, they have slighted their monitoring responsibilities. It is defin- itely a practice that should not be extended beyond the time necessary to assure the region that the state has an adequate program. One final comment relative to the regions' processing procedures under delegation relates to the apparent lack of awareness in some regions, below the top managerial level, as to how the regional office is supposed to operate in a delegated mode. In general, the top management within each regional office appears fully aware of the proper mode of operation under delegation and comfortable with the manner in which the region will function under delegation. At the staff levels, different understandings of functioning under delegation often exist. Often times the regional office staff appears not to understand how the regions are supposed to process certified grant applications under delegation. 4-19 ------- It appears as if the regions' management, in these cases, has not formally, or at least effectively, communicated to staff level personnel the role and approach of the regions under a delegated mode of operation. Somewhat related to this is the fact that a number of regions have not yet addressed significant issues that must be addressed to effectuate a successful operation under delegation. As will be discussed later, many regions have not yet fully addressed the methods by which they will monitor and evalu- ate the performance of delegated states nor have they decided on the exact procedures they will use to process state certified documents. In these situations, the authors feel it is important for the regions to fully communicate to staff the proper mode of operation under a fully dele- gated program, and for the regions to place attention on how they will process certified grant applications under a fully delegated mode of operation, as well as how they will monitor the performance of delegated states. In summary, only one region (Region IX) currently is employing processing procedures consistent with the concept of delegation and in a manner that will result in the full achievement of benefits associated with delegation. Other regions are in a transition mode of operation, making the transition from a non-delegated mode to a fully delegated mode. While they are moving in the right direction and making progress, at the present time regions generally are receiving more information and documents than they really need on individual projects and, to varying degrees, they are not meeting the goal of accepting state certifications without review. In order to eliminate these problems, the regions should, in the near future, identify the individual pro- ject-related documents that they need in order to take the actions that they must take on individual projects. Subse- quently, they should stop receiving all other documents. 4-20 ------- Further, the regions should move as rapidly as possible to a truly delegated mode of operation, whereby state certifi- cations are accepted without question, and after-the-fact monitoring is relied upon to assess state performance. Until these actions are taken, the regions and the states will not be operating in a truly delegated mode; duplica- tion, inefficiencies and time delays will continue to exist and the potential benefits of delegation will not be realized. PROCESSING TIMES FOR REGIONAL REVIEWS The regions have to conduct 4 major reviews relative to each grant project in delegated states. Three of these reviews relate to the acceptance of state certifications and the award of grants for Step 1, Step 2, and Step 3 applications. In addition, regions must review the environ- mental aspects of each project and issue the FNSI prior to state certification of the Step 2 application. The average processing times for each of these reviews for each of the 10 regions, both prior to and after delegation are shown in Table 4-2. The processing times shown are those relative to projects within the states that the authors evaluated within each region. Table 4-2 indicates that there has been considerable variability among regions as to the time it takes to pro- cess individual grant applications, both prior to and subsequent to delegation. Several points apparent from the table are of interest. First, delegation does not necessarily result in significant reductions in total pro- cessing time. In several regions processing times after delegation were about the same as processing times prior to delegation. On the contrary, in half of the regions shown in the Table 4-2, delegation brought about 50 to 75 percent reductions in overall processing times. 4-21 ------- TABLE 4-2 PROCESSING TIMES FOR REGIONAL REVIEWS Region I II III IV V VI VII VIII IX X State Connecticut New York Maryland Georgia Michigan Texas Missouri Montana Arizona Idaho Average Processing Time Prior to Deleqation, in davsa Step 1 73(14) 117(74) 149(20) 87(5) 47(19) 84(40) 100(86) 44(6) 20(9) 30(11) Step 2 180(9) 59(33) 299(10) 97(10) 116(18) 184(7) 128(11) 85(4) 20(8) 45(11) Step 3 115(11) 87(34) 174(17) 53(9) 91(18) 77(10) 100(9) 41(6) 17(18) 32(6) Total b 368 263 622 237 254 345 328 170 57 107 220e Processing Time After Delegation, in days Step 1 99(1) 31(19) 121(2) 30(2) 63(17) 65(58) 21(9) 17(16) 5(2) 36(8) Step 2 c 58(12) c 10(5) 99(30) 108(10) 26(8) 11(7) 50) 44(2) Step 3 81(3) 51(4) 142(1) 17(9) 71(12) 67(10) c 11(5) 3(3) c Sub Total c 140 c 57 233 240 147 39 13 112 127 hNSl 124 c c 30 38 48 c 60 c c Total c >c c 87 271 288 c 99 c c Total Change After Deleqation, in days 8 days shorter (l,3)d 123 days shorter 60 days shorter (l,3)d 180 days shorter 21 days shorter 105 days shorter 181 days shorter 131 days shorter 44 days shorter 5 days longer (1,2)d 3 days shorter .c- I NJ Usually, based on the projects processed in the fiscal year prior to delegation. The number of projects processed are These figures only relate to the total average time for the award of Step 1, 2Sand 3 grants and do not consider the time required for issuance of the FNSI (times prior to delegation are unavailable). In several regions, Step 2 c review time probably includes time for issuance of the FNSPs. Information unavailable. Based on difference in total processing times for those steps shown in parentheses. eDoes not include Regions I and III because their totals after delegation were unavailable. If these regions had been included, the average processing time prior to delegation would have been 275 days. ------- Also of interest are the significant reductions brought about by 2 of the regions in the several months prior to the authors' field visits. Region V reduced its total processing time on Michigan projects (for all 3 steps) from 233 days, as shown in the table, to 142 days over the past six months. Likewise, Region VI reduced its total processing time on Texas projects from 240 days, as shown in the table, to just 63 days over the last several months. In both of these cases, the reductions were brought about by the region's top management establishing processing time goals for each of the key reviews performed by the regional office. In both cases, the reduction in processing times was dramatic, almost overnight. One other point of interest in Table 4-2 is that the total processing time after delegation in each of the regions is highly variable, ranging from a low of 13 days in Region IX (in the state of Arizona) to a high of almost 5 months (the processing times f6r Regions V and VI were not referenced because of the recent improvements previous- ly discussed). When one considers that under delegation, the region does not perform a substantive review of the state certifications, it appears that the processing times obtained in Region IX are achievable in other regions, provided attention is focussed by the regional offices on reducing overall processing time. Under delegation, the regions are supposed to accept state certifications without review and basically sign the state-prepared federal grant offer. This action on any given grant award should be able to be completed within 5 to 10 days. Hence the total time that it takes for a region to process grants for all 3 steps should be in the order of 15 to 30 days. Again, from Table 4-2, only Region IX meets this goal, though Regions IV, VI (based on recent improvements), and VIII are not far from the goal. It should be noted that in Region VIII, the regional office is still preparing the federal grant offers. 4-23 ------- Were the state to prepare the federal grant offer, the region would easily be able to reduce its total processing time for all 3 steps on Montana projects to less than 30 days. The authors are confident that all regions can reduce their total processing time for Step 1, 2, and 3 grant awards to less than 30 days in a relatively short period of time, given the following provisions. Namely, the regions must receive state-prepared federal grant offers along with the state certifications, the regions must operate in a truly delegated mode and accept state certification without review, and further, the regions must focus attention on rapid processing of certification documents. Some might question why attention to processing time is important. The average processing time in all regions for the Step 1, 2, and 3 certifications is currently in the order of 4 months. Therefore, reducing this time to approximately 1 month would cut 3 months from the total processing time for individual construction grant projects. Likewise, assuming an average inflation rate of 1% per month, such a reduction would effectively lower the price of each construction grant project by 3%. It would also expand the buying power available through annual appropria- tions. On the national scale, this reduction would amount to an effective savings of $136 million per year (assuming a $3.4 billion appropriation). Of course, the expected benefits of rapid processing of state certifications are based on the assumption that the project is on a fundable portion of the priority list, and that funding is available. Regional processing times for FNSI's are surprisingly low, considering that the regional review of the state- prepared environmental assessment and the issuance of the FNSI is the most substantive review function that the re- gions perform relative to individual grant projects. In general, it appears that the environmental review functions 4-24 ------- are being carried out in the order of 1 to 2 months time. The authors are of the opinion that, in general, this review can be performed in less than 30 days. Region IV, in the case of Georgia's projects, is currently meeting this proposed processing time as is Region V (over the past 6 months) in the case of Michigan's projects. In summary, regional office performance in terms of the processing time for the award of grants and issuance of FNSI's under delegation is generally in need of improve- ment. In several regions, only minor improvement is called for, but in most regions considerable improvement is needed. The authors are of the opinion that the regions can bring about rapid reductions in total processing time, as have several of the regions recently, by focussing more atten- tion on this important aspect of program administration, by implementing relatively simple time management tools, and by operating in a truly delegated mode. More specifi- cal-ly, each region should establish, processing time goals for each of its significant review activities, including the award of Step 1, 2, and 3 grants and the issuance of FNSI's. The processing time goals for grant awards should be between 5 and 10 calendar days for each step, and the processing time goals for the issuance of the FNSI's, after receipt of the state-prepared environmental assess- ment, should be in the order of 30 days or less. Further, the regions should charge staff with meeting these goals and the regions should routinely track actual performance against these goals. The regions should then provide feedback to staff where processing time goals are not achieved. Through implementation of these relatively simple measures, consid- erable reduction in total processing time will result. This, in turn, will result in lower project costs, and will expand the buying power available from fixed allotments of construction grant funds. 4-25 ------- REGIONAL MONITORING OF STATE PERFORMANCE One of the prime functions of the regional offices under delegation is to monitor the performance of delegated states for the purpose of insuring that the states are adequately administering the delegated construction grants program. In general, all of the regional offices are struggling, at least to some extent, with how best to monitor and evaluate the performance of delegated states. Several have attempted on their own to develop rather comprehensive monitoring programs, while the majority of the regions are looking forward to guidance from EPA Head- quarters. Table 4-3 provides a summary of the regional office monitoring performed to date on the delegated states which the authors evaluated. As is shown in Table 4-3, only 6 of the 10 EPA regions have performed a substantive amount of monitoring on the selected delegated state. Three regions have conducted no monitoring at all, and one region has conducted only a very limited amount of monitoring. The monitoring has been weighted heavily towards determining compliance of the state with the procedures contained in the delegation agreements. While most of the regions that have performed monitoring evaluate the quality of the state reviews to some extent, none of the regions take a comprehensive and effective look at the quality of all of the significant state reviews. In addition, only one region evaluates the processing times of state reviews. Several regions have expanded the scope of their moni- toring effort to reach beyond state processing of individual grant projects by focussing attention on evaluating the state's overall management and administration of the dele- gated construction grants program. The monitoring programs in Regions II, IV, and X are particularly impressive in this regard. In addition, 3 of the regions (Regions IV, 4-26 ------- TABLE 4-3 SUMMARY OF REGIONAL OFFICE MONITORING OF DELEGATED STATES9 Region I II III IV V VI VII VIII IX X State Connecticut New York Maryland Georgia Michigan Texas Missouri Montana Ari zona Idaho Responsibility Clear Yes Yes Yes Yes Yes Yes Yes Yes Yes Some Overlap Internal Guidance No * Yes Yes, but Limited No Yes, but Limited No No No Yes * Yes Monitoring Performed No Yes Very < Limited Partial , Mgmt. only Yes No Yes No Yes Yes Before or After Fact — After After — After __ After — After After Focus of Monitorincj Performed by Region State Procedures — Yes Yes No Yes -- Yes -- Yes Yes Quality -- No Yes No Limited -- Yes -- Yes Yes Timing — No Limited No Li mi tec -- Limited -- Li mi tec * Yes Manage- ment — * Yes No * Yes Limited — Limited -- Limited * Yes nternal to Region -- No No * Yes No — Yes -- No * Yes Substan- tiveness — * Yes -- * Yes * Yes -- * Yes -- Yes * Yes -P-- I S3 Based on the monitoring that had been performed by each regional office, on the state within the region that the authors evaluated, prior to the authors' field visits. Especially impressive aspect of the monitoring program employed by the region. ------- VII, and X) are utilizing their monitoring program to look not only at the state's performance under delegation, but also to look internally at the region's performance. In all cases where the regions conduct significant monitoring, the regions' monitoring appears to be substan- tive in nature. It is generally detailed and constructive, and undoubtedly will lead to improved state administration of the delegated program. It should also be noted that, in all cases where the region had performed monitoring, the states which were monitored appeared to be appreciative of the region's monitoring efforts and generally felt that the monitoring was conducted in a constructive and helpful manner. Of the 6 regions which have conducted monitoring, the monitoring program conducted by Region X on the state of Idaho is considered by the authors to be the best monitoring program. This particular monitoring effort looked not only at the state's processing procedures, but also at the quality of the state's review, the time expended on state reviews, the state's overall management of the delegated pro- gram, and in addition, looked at the regional office's performance under delegation. Of interest, the State of Idaho actively participates in the region's monitoring of that state. The only area where this monitoring program was somewhat weak was in the area of evaluation of the quality of state reviews. Two other monitoring programs, namely that of Region II and that of Region IX, are felt to be superior to the other monitoring programs (except for Region X's program). The Region II monitoring program is especially strong in the area of evaluating state management and administration of the construction grants program. The Region IX monitoring program is fairly comprehensive in nature and looks at all aspects of the delegated state program, though the timing and the management aspects are not looked at in 4-28 ------- great detail. One interesting aspect of the Region IX monitoring program is that the region routinely contacts consulting engineers and grantees in conjunction with its monitoring to receive outside input as to state performance. In summary, the regions have not yet developed and im- plemented effective programs for monitoring and evaluating the performance of delegated states. Four regions have performed no monitoring at all, and most of the monitoring that has been conducted, while detailed and substantive, is somewhat narrow in perspective. Most of the monitoring performed to date has dealt with determining state com- pliance with the processing procedures contained in the delegation agreement. In general, the regions need to broaden the scope of their monitoring programs to examine not only the state processing procedures but also the quality and processing times associated with state reviews and the state's overall management of the delegated program. Of those monitoring efforts that have been conducted, the Region X monitoring program is considered to be the best in that it is not only detailed and substantive, but it is also fairly broad in perspective. OVERALL REGIONAL OFFICE PERFORMANCE On an overall basis, the authors rate the performance of the EPA regional offices under delegation as good. Almost all regions have moved aggressively to implement delegation agreements with interested and qualified states. Most regions are proceeding to fully delegate the specific program functions to delegated states over about an 18-month period, though several regions have been slow to turn over specific functions to states. Some outstanding examples of regional efforts to train delegated state personnel have been noted, but the typical regional effort in the area of training has been relatively modest. 4-29 ------- The organizational structures and the resources util- ized by the regional offices to oversee the delegated construction grants program are considered adequate at the present time. Currently, most regions are in a transi- tion phase, between a non-delegated and a fully-delegated mode of operation. At the time when most of the states within each region become fully delegated, the current organizational structures, with a few exeptions, will no longer best serve the region's needs. Most regions, there- fore, need to reassess their organizational structures in light of the impending, fully delegated mode of operation. They also need to reassess their resource needs for this situation. Chapter 3 of this report indicated that within a year, 27 of the 37 currently delegated states will be fully delegated. This establishes the time frame over which the regions should re-evaluate their organizational structures and their resource needs. Of all the regions, two (Region III and Region IX) are considered to have the organizational structures most suited to delegation. The regions generally employ sound management practices for overseeing the delegated program. However, the GICS based management information system needs to be updated to meet the regions' needs under delegation, and the regions need to establish regular and formalized communications with each delegated state. In terms of grants processing procedures employed by the regional offices, most regions, as previously stated, are in a transitional period, still performing certain non-delega- ted functions as well as approving state-certified documents. Because of this, regions are still grappling with how they intend to operate in a fully delegated mode. Only one region (Region IX) is currently employing processing procedures con- sistent with the concepts of delegation, in a manner that will result in the achievement of the expected benefits of delegation. The other regions, while they are moving in 4-30 ------- the right direction, are receiving more information and documents than they need on individual grant projects, and they are generally not achieving the objective of accepting state certifications without review. Regional office performance in terms of the processing times for award of grants and the issuance of FNSI's under delegation is generally in need of improvement. There has been overall improvement in processing times in most of the regions since delegation, but there is considerable room for additional improvement. Whereas the average regional pro- cessing time for award of grants for all three steps of a typical construction grants project is about 4 months, it should be possible to reduce this total processing time to less than 1 month. That this is possible is evidenced by the processing times acheived in several regions. In order to reduce processing time, the regional offices need to focus additional attention and effort in this critical area. More specifically, each regional office should de- velop processing time goals for each of its key reviews, and should routinely monitor actual performance against those goals. The processing time goals for the issuance of grant awards should be between 5 and 10 days, and the processing time goals for the issuance of FNSI's should be 30 days or less. Through implementation of these relatively simple measures, considerable reduction in processing time will result. In turn, this will lead to reduced project costs and expanded buying power from annual appropriations. In terms of monitoring the performance of delegated states, 6 of the 10 regions have performed substantive monitoring on the delegated states. Four regions have not conducted any significant monitoring. The monitoring that has been conducted, while detailed and substantive in nature, is generally narrow in scope. Most of the monitor- ing has been oriented towards determining state compliance with the procedures outlined in the delegation agreement. 4-31 ------- Few monitoring programs adequately evaluate the quality of state reviews, the processing time of state reviews, or the state's overall management and administration of the delegated construction grants program. 4-32 ------- CHAPTER 5 EVALUATION OF THE PERFORMANCE OF DELEGATED STATES This chapter presents a general evaluation of the per- formance of the 10 delegated states visited in conjunction with the national assessment of the delegated construction grants program. The performance of these states, in terms of administering the delegated program, was evaluated in the following areas: • Organizational Structure and Resources • State Management of the Program • Grant Processing Procedures • Quality of State Reviews • Processing Time for State Reviews The general evaluation of the 10 delegated states is contained in the following paragraphs. As was noted in the previous chapter, the observations and recommendations contained in this chapter are Abased on field visits made to the state offices between May and August of 1980. As a result of state efforts made since that time, a number of the problems identified in this chapter may already have been eliminated and a number of the recommendations already implemented. ORGANIZATIONAL STRUCTURE AND RESOURCES In general, based on the 10 states evaluated, the delegated states have adequate resources to properly admin- ister the construction grants program. Only in certain units within several states were deficiencies in resources observed. For example, the state of Maryland, adequately staffed in most areas, is considered to have a shortage of staff in the project management unit. The personnel in this unit are charged with reviewing the facilities plans 5-1 ------- and managing each project throughout the three steps of the construction grants process. Given the broad responsi- bilities of this unit, additional resources are needed to properly fulfill the responsibilities. In the state of Georgia, whereas sufficient engineering and technical staff exist within the program, the administrative staff and the proposed staffing for the construction inspection activities are judged to be on the light side. In the state of Texas, several additional positions are needed to staff the environ- mental unit, the unit that is responsible for the prepara- tion of the preliminary environmental assessments. In the state of Montana, which has a grants staff of under a dozen people, two additional staff are needed, one to serve as an assistant to the chief of the Constructions Grant Section, and another to coordinate the construction activities within the state. Beyond these instances, the resources employed by the states to administer the delegated program appear to be adequate. Of interest, only one state out of the ten visited, the state of New York, has been unable to fill budgeted positions. Many other states complained of low salary levels and of the difficulty in hiring and keeping engineers, but in fact the states visited were generally staffed close to the current budget levels. Several states, to accommodate low salaries paid engineers within the state, hired persons with other technical backgrounds to fulfill tasks commonly fulfilled by engineers. For example, the state of Arizona hired non-engineering professionals (a lawyer, a planner, etc. ) to review facilities plans. Likewise, the project managers in the Maryland project management unit are non-engineers. In both of these cases, the non-engineering professionals worked under the direction of an experienced professional engineer. Also, many states have set up administrative units containing non-engineers, for the purpose of removing much of the administrative work load from the engineering 5-2 ------- staffs so that engineers can concentrate primarily on technical matters. In several instances, states were able to get the state legislature to elevate the salaries for newly hired engineers above the level that would normally be paid. EPA regional offices have assisted the states in getting these higher salary levels. As stated previously, only the state of New York has had serious problems hiring necessary staff. The problems encountered in New York are not due to engineering salary levels. They are due to a number of civil service related problems. No one problem has stood in the way of the New York hiring program, but rather three or four problems have each resulted in keeping the state from hiring twenty or so additional personnel. In spite of these problems, the state currently has a staff of 215 people, compared to the ultimate objective of 283 people, and is only about 20 people behind the hiring schedule contained in the delega- tion agreement. Figure 5-1 contains a graph of the personnel to be employed at "full delegation" within each of the ten dele- gated states in relation to the federal allocation to the state (based on a $3.4 billion national appropriation). As can be seen, there is a close relationship between state staffing levels and the federal allocation to that particular state, although state staffing levels generally were determined based on a detailed manpower analysis. Some of the variations found from the midline of the envel- ope of curves readily can be explained. For example, the author previously noted that the state of Georgia needed additional administrative staff and construction personnel. This would elevate the state resources towards the middle of the envelope of curves. The state of Maryland, on the high side of the envelope, is fully administering all of those activites that are traditionally performed by the Corps of Engineers in other states, including biddability/construct- 5-3 ------- FIGURE 5-1 RELATIONSHIP BETWEEN STATE STAFFING LEVELS AND ANNUAL ALLOCATION 03 O to &- 01 ex 01 CO s- O) 300 400 Annual Federal Allocation to State, in millions of Dollars (Based on a $3.4 billion national appropriation) 5-4 ------- ability reviews, interim inspections, on-site inspections and final inspections. Because of the close relationship found, it is suggested that Figure 5-1 be utilized as a preliminary basis for estimating staffing needs in states which are not yet delegated. The authors explored the relationship between the number of active projects within a given state and the staffing level, but found little relationship and considerable vari- ability between states. Therefore, it is felt that the re- source/federal allocation relationship is the best approach for estimating and evaluating resource needs. An additional aspect of the general subject of resources is the adequacy of the federal funding available to delegated states for program administration under Section 205(g) of the Act. Three of the ten states visited are operating with budgets in excess of the administrative funding annually available from Section 205(g), i.e., in excess of 2% of their allocation. In all three cases, the states are making up their current budget deficit by borrowing from Section 205(g) funds that had been reserved during the initial years of the Act, but went unused because the state was not yet fully staffed. The 3 states that are currently operating on budgets in excess of the annual provisions of Section 205(g) are Connecticut, Arizona, and Idaho. Further, 3 additional states, Michigan, Missouri, and Montana, will be at the level of 2% of their allocation or in excess of that level within one or two years from now. It should also be pointed out that none of these 6 states is administering any of the activities typically performed by the Corps of Engineers (except that Connecticut is performing some interim inspec- tions). From this, it appears that the 2% funding available from Section 205(g) of the Act is not adequate on a long- term basis in more than half of the ten states visited. Furthermore, the 2% funding is only sufficient in the short-term because of the present ability of most states 5-5 ------- to utilize funds which were reserved during the early years of delegation before the states were fully staffed. This problem will be discussed more fully in Chapter 6. In summary, with a few isolated exceptions, states are adequately staffed to properly administer the delegated con- struction grant program (given the current status of dele- gation in those states). However, the administrative fund- ing available to delegated states through Section 205(g) of the Act is not adequate in most states to allow the states to take over construction related activities being performed by the Corps of Engineers. The 10 states visited during this national evaluation offer a number of varying organizational approaches to admin- istering the delegated construction grants program. The organizational structures vary from the situation iii the state of Montana, where a single organizational unit of eleven people with a single supervisor administer all aspects of the construction grants program, to that in the state of Idaho, where construction grants projects are processed by one of the three state regional offices with the state's central office having coordinating and quality control res- ponsibilities, to the structure in the state of New York, where program administrative responsibilities are divided between three offices of the Department of Environmental Conservation. Though the organizational structures of the 10 states vary considerably, the organizational structures are generally considered adequate. Several problems were observed, but none so serious that they need immediate atten- tion, although some do merit watching over future years. The authors feel that 4 of the states visited have organizational structures that are less than ideal and that these states should remain sensitive to the potential prob- lems which could develop. If problems are observed, the states should consider organizational changes. The first of these four states is the state of New York where, as 5-6 ------- previously stated, three major offices under the Department of Environmental Conservation have significant construction grants program related responsibilities. The commissioner of the department, who is also responsible for all conser- vation and natural resources related activites in the state, is the only person with total responsibility for the con- struction grants program. Further, within the Office of Environmental Quality, the office having the major responsi- bility for the program, responsibility for the program is currently divided between two division directors who share equally that office's responsibilities for administering the grants program. A recent proposal would have the grants-related activities currently being administered by one of these divisions, the Water Division, transferred to the other division, the Construction Management Division. This organizational change, if it does go forward, will take care of perhaps the most serious organizational problem in the state of New York. While the remaining organizational structure is far from ideal, the authors investigated the rationale for dividing the program between three offices, and concluded that little other choice exists, without changing the overall structure of the department. Therefore, the New York staff involved in grants program administration is faced with the challenge of trying to make a less than ideal organizational structure work effectively. It appears that the state is doing a fairly good job in this regard. Three other states, Georgia, Michigan, and Arizona, have less than ideal organizational structures. The primary organizational problem in these states is that significant program-related activities are not totally under the control of a single program manager. In the case of Georgia, the authors recommended that the construction grants program manager take responsibility for program activities not currently under his direction, at the time the state takes on construction-related activities currently being performed 5-7 ------- by the Corps of Engineers. In the other two cases, the authors recommended that the states just watch these sit- uations closely, and if problems start to develop, con- sider moving these other activities under the authority of a single construction grant program manager. Several other states, in the view of the authors, have organizational structures that need improvement in certain areas. For example, the authors feel that the Georgia organizational structure needs strengthening in the adminis- trative area. The Missouri organizational structure needs units added to handle environmental matters, construction- related matters, and administrative matters. The Montana organizational structure needs an assistant construction grants section chief to help the section chief supervise the staff under him. Several states need a construction management coordinator to oversee the construction aspects of the program. Of interest is the previously referred to organizational structure existing in the state of Idaho. In the case of Idaho, the state's central office is responsible for the construction grants program from a programmatic standpoint, whereas the state's three regional offices are responsible for performing all project review and project related admini- strative activities. The state's central office performs a quality review function of regional actions on key docu- ments and provides guidance to and coordinates the efforts of the individual regional offices. Whereas initially the authors had some concerns with this organizational structure, it was apparent upon investigation that the organization was working quite effectively, primarily because of the strong working relationship existing between the state's central office and the three regional offices. It was clear to the authors that, whereas organizationally the construction grants staff in the regional offices did not answer to the program managers in the state office, from a 5-8 ------- programmatic standpoint they did. The authors are satisfied that, while this is an unusual organizational structure, it is operating effectively. In fact, it appears that this unusual organizational structure has led to better management and better coordination than typically exists between organizational units that are housed in the same offices. In the case of the state of Idaho, the staff acknowledged that dividing responsibilities between the state's central and regional offices presented potential problems and therefore a number of effective management practices were implemented to minimize the potential prob- lems . In summary, the states' organizational structures for administering the delegated construction grants program are generally considered adequate. The only exceptions are the several states which have organizational structures that need expanding or strengthening, and several others which have organizational structures where some significant construc- tion grants-related activities are not under .the direction of a single program manager. STATE MANAGEMENT OF THE DELEGATED PROGRAM In evaluating the adequacy of state management of the delegated construction grants program, the authors consid- ered the following factors: • The apparent capability of the state's manage- ment staff. • Whether the state has an adequate information reporting system to provide managers with the information they need to manage the program. • Whether the state has an adequate system for planning, directing and controlling the conduct of the program. • Whether the state has an adequate method for 5-9 ------- tracking, controlling and where appropriate, expediting the progress ,of individual grant projects. • Whether the state adequately communicates with the EPA regional office as well as with grantees, consultants and other outside interests. In general, the authors are impressed with the state managers of the construction grants program. These individ- uals were generally experienced in the program prior to delegation, and they appeared energetic and dedicated to- wards doing a good job in the program. They also appear to attach a sense of importance to performing their jobs well and they seem to have a good sense of perspective as to which of the many aspects of the program are most import- ant and which are of lesser importance. Based on the review of the 10 delegated states, the authors have no qualms about the management capabilities that exist at the state level. All of the states visited have managers who are fully capable of doing an excellent job of administering the program. The authors found a great deal of variability in the adequacy of the states' information reporting systems to give state managers the information they need to properly manage the program. Four of the ten states visited have little or no information reporting systems available to the program managers. Several states, including Maryland, Michigan, Montana, and Idaho, have monthly reports which describe the current financial status of the program within the state as well as significant activities completed during the previous month (such as grant awards, certifica- tions, etc.). Two states, New York and Texas, are using GIGS to a considerable extent to meet their management information needs. The state of Texas, to meet its infor- mation needs, produces some 40 GIGS reports- many of which were programmed by the state staff. The state of New York 5-10 ------- has the widest array of management information reporting of any of the states visited, expecially at the program- wide level. In addition to its GICS reports, the state updates the project priority list and the schedules associ- ated with the projects on that list on a monthly basis, produces a monthly project milestone tracking report, and produces a monthly accomplishment report. In general, while there are some interesting and useful management reports being prepared in a number of the delega- ted states, the authors feel that there is a need for more extensive information reporting in most states, especially at the program-wide level. Each state responsible for administering the construction grants program should have a monthly management report which describes the current status of the construction grants program within that state, records past outputs and accomplishments at least over the previous year, and projects key activities and accomplish- ments, including awards and obligations. While many states have monthly management reports that adequately describe current program status, few of these reports take an historic view of the accomplishments within the program, and none contain projections of future activities. Projecting fu- ture activities is essential if program managers are to be on top of the program and are to manage it in a pro- active rather than a reactive manner. A number of states have sound management tools to assist them in planning, directing, and controlling the conduct of the delegated program. One state, Maryland, has developed program goals which are included in a regularly produced report for the Governor. Another state, Idaho, in conjunc- tion with the EPA regional office, is using the State EPA agreement as a means for planning future program activities and direction. Three states. New York, Georgia, and Arizona, have management by objective (MBO) systems in place and operating, primarily at the staff level. In these systems 5-11 ------- each staff member negotiates a set of performance object- ives with his supervisor and then conducts his activities towards the end of meeting those objectives. In the case of the MBO systems in Georgia and Arizona, the performance standards at the staff level include such things as output levels expected and processing times for various reviews performed by staff. The state of Connecticut also is in the process of implementing an MBO system, though it will take several years to fully implement. The authors were impressed by the MBO system utilized in these states, especially where the objectives which were developed dealt with important criteria such as outputs and project processing time. It should be noted that in the 2 states (Georgia and Arizona) where performance standards contain processing time standards, processing times are less than the average in the other states. The use of MBO or performance standards appears to yield positive results. The authors believe that the MBO approach is a good management tool, though additional benefits would accrue from this tool if it were applied not only to the staff performance, but also to the program level. It would be beneficial for all states to employ some type of long-range planning mechanism such as MBO. It is very easy for state program managers to become engrossed in the day-to-day pressures of processing individual construction grants pro- jects and to never look ahead or plan ahead or spend time trying to anticipate problems and develop solutions to them before they become crises. With the exception of 2 states, Maryland and Missouri, the states visited appear to be focussing their attention primarily on immediate problems and issues rather than looking and planning ahead. All states should employ some type of system that forces them to periodically remove themselves from the day-to-day pressures of the program and to look and to plan ahead. Again, an MBO approach is 5-12 ------- a useful tool in accomplishing this objective. Several states have developed rather comprehensive training programs to assist in their management of staffs which are almost entirely new to the program. The state of Missouri has a full time training coordinator and a very extensive technical, administrative, and skill-oriented training program for all of its staff members. The state of Arizona has drawn upon EPA regional office resources, available for one year IPA assignments to train its staff on an on-the-job basis. The state of Idaho, primarily because of the organiza- tional structure previously discussed, is in the process of developing a quality control program to insure that project level reviews are of adequate quality. Only 2 of the 10 states visited (Georgia and Idaho) have developed project tracking systems that allow them to follow closely the progress of individual projects throughout the entire construction grants process. The state of Georgia has developed a key project tracking system which is manually updated on a continual basis. Key projects have been chosen primarily on the basis of their dollar size and their impact on the overall state rate of obligations. The state of Idaho, in conjunction with the EPA regional office, has developed a rather extensive computerized, project tracking system that, when fully implemented, will project work load and key document receipt dates as well as track the progress of all active grant projects. This particular program, now fully developed but not yet imple- mented, will operate off of GIGS. This is the only project tracking system existing in the states visited that deals with all projects in a fairly sophisticated manner. Further, it is the only attempt observed to project future work load. Several other states employ systems for following the progress of individual projects that border on a project tracking system. The state of New York regularly updates 5-13 ------- the schedules of individual projects contained on the priority list and produces a monthly milestone tracking report on all projects that are scheduled for grant award during the current fiscal year. The monthly milestone tracking report also identifies specific problems that may keep a project from reaching the grant award stage prior to the end of the fiscal year. The states of Michigan and Arizona also utilize the project priority list and the target certification dates as a means of tracking indivi- dual projects. In general, these types of systems, while they are in the right direction, do not fully satisfy the needs of the states in terms of a project tracking system. The authors believe that all states responsible for administering the construction grants program should utilize some type of project tracking system. Small states do not need a system as sophisticated as the Idaho system, but even the large states would benefit through implementation of a system as simple as the manually maintained state of Georgia system. Only with the use of a project tracking system can states stay on top of the progress of projects and keep them moving as rapidly as possible through the long, complex construction grants process. A project track- ing system should have certain features. It should have rather detailed schedules for each active project, should provide for routine monitoring of the actual progress of projects against the schedules, and should provide for the continual updating of project schedules. In addition, the system should be supplemented with aggressive effort on the part of the state to maintain the schedules and, where neces- sary, expedite projects. In terms of this latter point, some states appeared to have a sense of apathy insofar as the need to expedite pro- jects and the state's ability to do so. In some states there seemed to be the feeling that if a project was delayed as a result of a grantee or a consultant not acting with 5-14 ------- reasonable haste, then that was the grantee's problem and not the state's problem. The authors would disagree with that philosophy. The faster the projects move through the system, the sooner they get built, the sooner the national and state water pollution control goals (for which this program was designed) are achieved, and the greater the buying power which the state gets with its fixed allocation of federal construction grant funds. It most certainly is in the states' interest to move construction grants projects of good quality through the complicated three-step process as rapidly as possible. A project tracking system along with an aggressive state attitude toward maintaining project schedules is a necessary tool if this difficult task is to be accomplished. In terms of the final factor for evaluation, i.e., state communication with the EPA regional offices as well as with grantees and consultants, several states employed practices to accomplish this. The state of Arizona meets wi'th the management staff of the EPA regional office on a monthly basis to discuss program and project-related activ- ities, problems and issues. The state of Michigan accomp- lishes this same purpose through the use of monthly confer- ence calls with the EPA regional office. These are the only two states visited, which on a regular and formalized basis meet with the EPA regional offices. Communications between delegated states and their respective EPA regional offices are of utmost importance, too important to leave to chance. As recommended in the previous chapter on the regional offices, all regions and states should meet on a regular basis to discuss current program and project related issues, similar to what is being done in both the states of Arizona and Michigan. As far as communicating with grantees, consultants, and other outside interests is concerned, several states are employing outside advisory committees for this purpose. 5-15 ------- The state of Maryland has a very active advisory committee in place and is devoting two man years of effort towards servicing this committee. The committee assists the state in identifying and resolving program-related issues. The states of Georgia and Texas are in the process of institu- ting advisory committees and are well along in that process. The authors noted that in the state of Maryland, detailed minutes are produced at the monthly advisory com- mittee meetings and then are distributed widely throughout the state. Thus the advisory committee also serves as a mechanism to distribute current program-related information to all of those interested in the construction grants program. In addition, several states have regularly published documents that are routinely sent to grantees and consult- ants. The state of New York produces Technical Information Pamphlets (TIPS) that address technical matters associated with the construction grants program. The TIPS are sent out to all consultants active in the grants program within the state. The state of Montana has policy statements that it distributes within its own staff as well as to consultants active in the program. The state of Maryland has both a series of construction grants memos and several technical bulletins which have been distributed to consult- ants. The state of Michigan holds periodic workshops with consulting engineers, oriented towards educating the con- sultants in new program requirements but also dealing with current issues identified by the consultants as well as by the state. The authors believe that for states to do the best possible job of managing the construction grants program, they need to employ an effective means of communicating with consultants, grantees, and others having an interest in the program. While communication typically takes place on a project-by-project basis, there is a need for communi- 5-16 ------- cation in a broader sense, beyond just a project-by-project type of discussion which benefits only a single grantee or consultant. In summary, the authors were impressed with the manage- ment staffs of the 10 states which were visited. The management staffs in these states appear to be fully capable of doing an excellent job of administering the construction grants program. State managers to this point in time, however, have focussed their efforts primarily on taking over the delegated program from EPA and on dealing with issues and problems associated with individual construction grant projects. Few, at this stage, have had time to make the transition into taking a broader management perspective, a perspective focussed on managing the program as opposed to just managing the processing of individual projects. Undoubtedly, states will make the transition naturally into fulfilling their broader program-wide management res- ponsibilities. Much faster progress could be made in this reg'ard, however, if the states implemented several key management tools. The construction grants program is so large and so complex that no program manager can do a proper job of managing the program, no matter what his/her managerial ability, without a fairly sophisticated set of management tools. For example, every state visited needs to improve and expand its current management information report- ing system. All states need a management information sys- tem that tells them what they have accomplished in the past, the current status of the program, and where the program is headed in the future. Further- all states need a project tracking system that will allow state project reviewers to closely track and, where necessary, expedite the progress of individual grant projects. States need some type of system, such as MBO, to force them to remove themselves from the day-to-day pressures of the construction grants program and to look ahead and to plan ahead. States 5-17 ------- also need to work at improving communications both with the EPA regional offices and with grantees,- consultants, and other outside interests. STATE GRANTS PROCESSING PROCEDURES In general, states appear to be utilizing sound grants processing procedures. There appears to be a clear delinea- tion of responsibility between the various organizational units within each state organization, there does not appear to be any overlapping reviews or inefficiencies, and no procedures are employed that appear to be unnecessary or to have only minimal benefits. Further, based primarily on the EPA monitoring that was performed, states generally appear to be complying with the terms of the delegation agreements relative to the specific processing procedures contained in those agreements. The authors have one general comment to offer that relates to processing procedures and applies to most states —that is, most states need to more actively deal with grantees and consultants during the preparation stage of facilities plans, and plans and specifications. A summary of state interaction with grantees and consultants on indi- vidual grant projects in each of the 10 states visited is presented in Table 5-1. As can be seen from Table 5-1, most states are conducting a pre-application conference with individual grantees. Only about half of the states, however, provide intermediate review of the facilities plans. The other half of the states generally wait for a draft facilities plan before they become involved in review- ing the facilities planning effort. Two states review only the final facilities plan, i.e., after the grantee has gone to public hearing and officially adopted the plan. 5-18 ------- TABLE 5-1. SUMMARY OF STATE INTERACTION ON INDIVIDUAL GRANT PROJECTS State Connecticut New York Maryland Georgia Michigan Texas Missouri Montana Arizona Idaho Pre-appli- cation Conferences Yes No Yes Yes Yes Single Conference for all Yes If Grantee requests Yes Yes Interned. Fac. Plan Reviews No Limited No Yes Mid- course Review No No Yes Yes Yes Draft Fac. Plan Review Yes Yes Yes Yes Yes No No Yes Yes Yes Final Fac. Plan Review Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Prelim. Design Review. No Li mi tec No Yes Li mi tec No ^ Yes Yes No Yes Intermed. Design Review No No No Yes No No No No Limited Yes Prelim. Plans & Specs Review No No Yes Yes Yes No No Yes Yes Yes Final Plans & Specs Review Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Comments Admin, order w/ schedule on all projects. On P&S, field visit, operability review P&S operability review Active construction mgmt.. program, small communities program Active state involvement during fac. planning, P&S On P&S, field visit, review w/ operator P&S operability review Active construction mgmt. program Site, geologic survey during facility plan review Payment schedules require interned, submittals. Operability review at 80% of construction. Comprehensive design review report prepared Active State involvement during fac. ping. Active Construction Mgmt. Program Active State involvement during fac. planning, P&S ------- Six of the ten states do not review the plans and speci- fications during the design preparation phase of individual grant projects, but rather, they wait until at least prelim- inary plans and specifications (90-100% complete) have been submitted before they review the design in any signi- ficant way. Two states, namely Georgia and Idaho, review designs throughout the design preparation process. They initially review preliminary design reports and then they perform intermediate design reviews at approximately the halfway point in the design process, prior to reviewing preliminary and then final plans and specifications. These same states are performing similar in-progress reviews during the facilities planning process. In both states, after the pre-application conference there is continual dialogue and review of intermediate products of the facili- ties planning process prior to receipt and review of the draft facilities plan. The state of Montana also has a continuous dialogue and review with the consultant during the facilities planning process. Continuous review of intermediate products during the facilities planning and design preparation phases of the program are highly desirable procedures for effective ad- ministration of the construction grants program. Such reviews accomplish a number of things. First, they prevent the consultant and the grantee from taking a direction that is not acceptable to the state and which is therefore wasting effort, time, and money. Second, they place the state in a much stronger position in terms of having an impact on the proposed facilities plan or design. It is much easier to influence a consultant's direction in both the planning and design processes when the state comments during the process rather than waiting until the consultant has finalized the plan or design, convinced the grantee that it is the best possible approach, and then submitted it to the state for review. The consultant generally 5-20 ------- resists suggested changes at this point in time because his professional reputation is at stake. At the same time, the state is constrained by a deadline and is not as free to propose significant changes in the planning or design. Also, the benefits of proposed changes have to be weighed against delays in project implementation. A final benefit of continuous and intermediate review is that the processing time for the final product can be shortened considerably if the state has followed the project closely throughout its developmental stages. By the time a facili- ties plan is submitted, the state has already dealt with a number of key aspects of that plan and is fairly familiar with it. Therefore, the state reviewer can proceed more rapidly through the review process. The same benefits apply to the review of plans and specifications. Beyond the above general comment, the authors observed a number of interesting approaches utilized by states in the processing of individual grant projects. The state of Connecticut, for example, issues administrative orders con- taining fairly detailed time schedules on all projects at the time a project's Step 1 application is approved. These orders and the associated time schedules are then used to track and keep on schedule individual projects. Several states, namely New York, Connecticut, Michigan, and Texas,- are performing operability reviews of plans and specifica- tions, using personnel who are familiar with the operation and maintenance aspects of treatment plants to perform this function. In the case of Texas, the state has a small unit made up of licensed plant operators who perform the review. The state of Maryland has an assistance program for small communities, administered under contract, by the state agency that is responsible for the planning, construc- tion and operation of all state-owned water and sewage facilities. This state agency also is the single largest grantee in the state of Maryland (in terms of having the 5-21 ------- greatest number of active grant projects), and is therefore very familiar with the construction grants process. There are other interesting approaches utilized by sev- eral states in administering various aspects of the con- struction grants program. The states of Maryland and Texas have active and impressive construction management programs.. The state of Missouri conducts detailed site and geologic surveys on all project sites during the facil- ities plan review stage to prevent problems that have typically occurred in the past due to a lack of adequate site information. The state of Montana places requirements for intermediate submittals of facilities plans, and plans and specifications, in the payment schedules associated with individual grant projects. Payments are not made unless these intermediate submittals are made. Montana also conducts operability reviews of treatment plants when construction is about 80% complete. The idea here is to identify necessary operations-related changes at a point in time when changes can be made more easily, i.e., before the contractor completes construction and moves off the site. The state of Montana also produces a very comprehen- sive design review report in conjunction with its review of each construction grants project. The design report is divided into various sections, including process design, hydraulic design, operability, safety/ and specifications. Also of interest in this regard, the state of Montana makes its own detailed design calculations to check the adequacy of the process and hydraulic designs of each project. Several other states, including the states of Georgia, Idaho and Arizona, also perform detailed design calculations for use in their review of proposed designs. In summary, the state procedures for processing indivi- dual grant projects are generally considered adequate. The one need that most states have in this area is to more actively review intermediate products during the facilities 5-22 ------- planning and design preparation stages. During the facili- ties planning stage, the state should review population and flow projections as they are developed, review proposed alternatives before they are evaluated, review cost-effec- tive analyses before recommended plans are selected, and finally review draft facilities plans before local public hearings are held. In the design phase of the program, states should require the submittal of and review detailed preliminary design reports, should review a set of plans and specifications at approximately the mid-point of the design process, and should review preliminary, or nearly complete plans and specifications. Such intermediate re- views should minimize wasted effort on the part of the consultant, allow the state to have a much greater impact on projects, and should speed up the review of individual projects. The end result will be better projects construc- ted sooner and at lower costs. QUALITY OF STATE REVIEWS In evaluating the adequacy of the state reviews from a quality standpoint, the authors focussed primarily on the technical reviews performed by the state on facilities plans, and plans and specifications. These are key state reviews in that they have the greatest potential for influ- encing the selection, cost, and adequacy of a project. To perform this evaluation/ the authors reviewed the files on several projects which recently received state facilities plan approval, and plans and specifications approval. Usu- ally 4 to 6 projects were reviewed in each of these two areas. In evaluating state reviews, the authors addressed sev- eral questions. First, were the state reviews thorough and detailed or were they cursory in nature? Second, were the state reviews substantive, i.e., were they such that 5-23 ------- they would have positive impacts op significant aspects of the project, such as the performance of the project, its cost, its environmental impact or its operability? If a review was found to be thorough and detailed and substan- tive as defined above, it was concluded that the review was of good quality. By evaluating 4 to 6 reviews in each category, the authors were generally able to get a reason- able indication of the quality of these key state technical reviews. Based on these evaluations, the authors conclude that the state reviews of facilities plans, and plans and specifi- cations are generally of very good quality. They generally appear to be thorough and detailed and substantive in nature and, in the eyes of the authors, will lead to better, more cost-effective projects. There are several exceptions to this general finding. One state has plans and specifi- cations reviews that, while very detailed, are not considered to be substantive in nature. These reviews deal with things like dimensional errors, missing sections or profiles. and inconsistencies contained in the plans and specifica- tions. In the eyes of the authors, these reviews are more along the lines of biddability/constructability reviews, and miss key aspects of the design, such as the adequacy of the process design, the cost-effectiveness of various aspects of the design, and the operability of the facility. In one other state, some of the plans and specifications reviews are very good, while others lack thoroughness and do not appear to be substantive. In this case and a similar case regarding the inconsistent reviews of facilities plans in another state, the authors were hesitant to draw any sweeping conclusions because of the small sampling of projects that were reviewed. Rather, it was recommended that these 2 states make a more detailed and in depth review of their own technical reviews in each of these areas. If the authors' preliminary observations are sub- 5-24 ------- stantiated, then the states will have to try to improve their reviews. There are two states in which the reviews of plans and specifications are substantive, thorough, and detailed but which do not contain any indication that the process design had been reviewed. In both cases, the states pointed out that process-related reviews are generally conducted during the latter stages of the facilities planning review process. The authors were unable to totally substantiate this and there- fore recommended that both of those states take a closer look at the situation to insure that the process design review was not falling through the cracks, somewhere between the facilities planning and design stages. In this regard, the authors also have concern as to whether a good process review can be made before the consultant really becomes involved with the details of the design; this concern is based on the general nature of the process-related informa- tion that is available at the facilities planning stage. The authors prefer the approach utilized in several states whereby a detailed preliminary design report, containing plant layouts, unit sizings and loadings, etc., is submitted to the state for detailed review early in the design process. In summary, the state reviews of both facilities plans, and plans and specifications appear to be of very good quality. They are generally detailed, thorough, and sub- stantive in nature and will likely lead to better, more cost effective projects. Only in 1 state was a clear deficiency noted (in the review of plans and specifications), while in 2 other states inconsistent reviews (in one case of plans and specifications and in the other case of facil- ities plans) were noted. Further, the authors found that two states may be not giving proper attention to the process design review aspects of treatment facilities because of an overlap with the facilities planning review. 5-25 ------- PROCESSING TIMES FOR STATE REVIEWS The processing times of state reviews and approvals of grant applications and key documents is an important aspect of state administration of the construction grants program. The time spent conducting state reviews impacts on the rate at which clean water goals are achieved, on the cost of proj- ects, as well as on the buying power available from a state's annual allotment of the national construction grant funds. In evaluating state performance in this area, the following factors were considered-- • Does the state have reasonable time targets or goals for its key reviews? • Does the state have an adequate internal manage- ment system that encourages achievements of these goals? • Are the actual approval times since delegation generally consistent with the state's time goals? • Are the actual review and approval times for key documents adequate or are they in need of improvement, based on the following criteria: Step 1, 2, and 3 applications certified within one month. Facilities plans approved within three months. Plans and specifications approved within two months. Only 3 of 10 states have processing time goals for key state reviews. One of these, the state of Georgia, has pro- cessing time goals for its reviews written into the perfor- mance standards for each employee. The uniform state stan- dard is to respond to all documents submitted by the gran- tee or consultant and acknowledge receipt, within 5 days of receipt. Further, the state has a goal of preparing comment letters on all documents within 30 days of receipt. 5-26 ------- The management system employed to encourage achievement of these goals is a regularly scheduled performance evaluation of each employee. The employee's performance is judged in part as to whether or not he was able to meet these goals on his projects. The state of Arizona utilizes an almost identical approach to encouraging rapid processing of pro- jects. The results of this type of approach are quite impressive, as indicated in Table 5-2, which summarizes state processing times for all 10 states for each of the key review activities. The state of Idaho has processing time goals written into its delegation agreement with the EPA regional office. For example, in the delegation agreement appendix which deals with plans and specifications, the region has identi- fied processing time goals for the state. The region then, as part of its routine monitoring of state performance, checks the actual state performance in comparison with the review times contained in the delegation agreement. Again. as a- result of this system, the review times in the state of Idaho, as compared to most of the other states, are impressive. In the other 7 states, there are no set time goals nor are there established management systems to encourage rapid processing of grant documents. Generally, the approach in the other states is to try to get the documents out as rapidly as possible, though no specific definition of "as rapidly as possible" is made. In some cases, states are attempting to complete their reviews in sufficient time to meet target certification dates which are contained in the project priority list. Such an approach does not appear to be effective in terms of reducing processing times either because the certification dates are outdated, or if they are updated, they are updated only a month ahead of the current month. 5-27 ------- TABLE 5-2. PROCESSING TIMES FOR STATE REVIEWS State Connecticut tew York Maryland Georgia Michigan Texas Missouri Montana Arizona Idaho AVERAGE Processing Time, Jn daysa Step 1 Applications 55(3) a 38(4) 51(6) 94(T6) 101(101) 218(6) 37(10) 18(2) 17(11) 84 Facilities Plan Review time included in Step 2 Comments only 135(9) b 43(9) 228('8) Not delegated 212(3) b b 160 Step 2 Applications 175(7) b 41(4) 49(8) 75(23) 130(17) 114(6) 9(15) 21(2) 18(3) 57 Plans and Specifications 270(9) 145(4) 66(6) 26(4) 162(26) 100(15) 270(5) 113(5) b b 144 Step 3 Applications 166(3) b 92(6) 73(6) 107(11) 111(13) Not delegated 55(6) 22(3) 9(1) 79 Total 666 b b 242 666 b 426 b b 524 Ui ro oo Based on approvals since delegation of a particular function, or if records were poor, on a sampling of recent approvals. Numbers shown in parentheses are the number of approvals made. Processing times were not available either because the function had not yet been delegated, or because no approvals had been made since delegation, or because of a lack of records. ------- Comparing the processing times contained in Table 5-2 with the general criteria which the authors previously out- lined , makes it apparent that with the several exceptions already noted (the states of Georgia, Arizona, and Idaho). state processing times are in need of considerable improve- ment. Of particular interest is the total processing time required for all 5 of the key state reviews. In several states, where information is available, the total state review time is aproaching two years. This means that each project is delayed approximately two years pending state review and approval. Likewise, achievement of state water pollution control goals that will be affected by those projects are delayed two years, the costs of those projects are elevated in excess of 20% due to inflation and the buying power of the state's annual allocation of funds is likewise reduced by over 20%. Clearly, substantial bene- fits will result if these long review times can be shortened. Most states need to focus greater attention on processing grants-related documents in a time-efficient manner. The short review times observed in the 3 states previously mentioned, together with the authors' findings that those particular states are doing a good job from a quality standpoint, indicates that shorter reviews are possible without sacrificing the quality of the reviews. Because of the importance of time-efficient reviews in program administration, each state should identify as a major program goal over the next year a significant reduc- tion in the processing time for approval of key documents. To facilitate achievement of this goal, processing time goals should be established for the 5 key state reviews, along the lines of the criteria listed earlier in this section. Further, each state should regularly monitor actual performance against the processing time goals that have been established and give feedback to staff whenever processing times are inconsistent with these goals. 5-29 ------- Another important aspect of reducing processing time is to expend effort towards insuring rapid turnaround at the grantee and consultant level. The processing times shown in Table 5-2 include not only the state time for commenting on the initial submittal.- but also grantee response time, as well as subsequent review time expended at the state level. Time expended at the grantee level in responding to state comments is as costly as time spent at the state level in preparing initial comments and reviewing subsequent submittals. The states must take responsibility for insur- ing that grantee responses are received in a reasonably short amount of time. Several recommendations made earlier in this chapter will assist states in reducing processing times. An early and continuous involvement of state reviewers in the facil- ities planning and design preparation stages should allow states to review intermediate products (without stopping the consultant's progress) and therefore reduce the state processing time of final products. Not only should state processing time be reduced.- but also it should be less likely that the grantee will have to make a major change in the facilities plan or design, that would otherwise tend to delay grantee response time. Also, implementation of a project tracking system and an aggressive effort by the state to maintain projects on schedule will be valuable in reducing grantee response time and insuring rapid processing time at the state level. In summary, with several exceptions, state processing times are in need of considerable improvement. States need to focus a significant amount of attention on reducing their total processing times. Implementation of certain manage- ment tools, such as the establishment of goals for each key review performed by the state, and routine tracking of actual performance against those goals will be of considerable ass- istance in this effort. Greater involvement by state staff 5-30 ------- with grantees and consultants during the facilities planning and design preparation phases of projects, and implementa- tion of a project tracking system will also be of assist- ance in this regard. OVERALL STATE PERFORMANCE On an overall basis, states appear to be doing a good job of administering the delegated construction grants pro- gram. In general they appear to have adequate resources to administer the program and acceptable organizational structures. There are several isolated cases in which resource levels need to be increased and there are several situations where organizational structures need to be stren- gthened. These cases, however, are relatively minor in significance. The management staffs at the state level appear to be quite capable of managing this large complex program. Most of the state managers, however, appear to be focussing their attention and efforts on taking over the delegated program and on dealing with problems and issues associated with indi- vidual grant projects. Few state managers, at this point in time, have been able to focus attention on managing the program as a whole. While this change in management focus will undoubtedly evolve over time, (given the capability of the state managers), implementation of certain manage- ment tools would assist state managers in making this transition at a faster rate. Specifically, each state should employ certain key management tools. These should include: • A management reporting system which provides program managers with information on current program status, past performance, and future projections. • A project tracking system. 5-31 ------- • A system such as MBO which provides the state with a mechanism to look and to plan ahead. • Regular and formalized communications with the EPA regional office. • Some formalized means of communications with grantees and consultants such as an outside advisory committee, or regular publications or bulletins, or both. With the addition of these management tools and the capa- bility of the state managers, there is no question that the construction grants program can be properly managed at the state level. In terms of grants processing procedures, the proce- dures employed by the states appear to be generally adequate and they appear to be in conformance with the procedures identified in the delegation agreements. The major recom- mendation in this area is that states become more actively involved with grantees and consultants during the facilities planning and design preparation stages. Each state should review intermediate products as they are produced in both the facilities planning and design phases of the program, as a few states are now doing. Such intermediate reviews will minimize misdirection on the part of the consultants during both these phases of the program, thereby reducing engineering costs and wasted effort. In addition, inter- mediate reviews will allow the state to have greater impact on these projects and will reduce the processing times for state reviews. As a result, the cost of the projects at the local level will be less and, at the same time, the buying power of the states' annual allotment of federal construction funds will be increased. The states appear to be consistently doing a very good job in terms of the quality of their reviews. In general, state reviews of facilities plans, and plans and specifica- tions were found to be detailed, thorough, and substantive 5-32 ------- in nature. These reviews undoubtedly will lead to better and more cost-effective projects. The only problems observed involved just a few states. In the case of 1 state, reviews of plans and specifications, while detailed, were found to be non-substantive, and in 2 other states inconsistent reviews in terms of thoroughness and substantiveness were found (in one state related to design reviews and in the other related to facilities plan reviews). In each of these cases the state was encouraged to perform its own evaluation to confirm" the authors' preliminary findings, and take corrective action if necessary. In terms of the processing times for their reviews, most states need to make significant improvements. While several states are performing well in this area, total review times for the 5 key state reviews is approaching several years in some states. Most states need to focus greater attention on reducing their processing times. Implementation of rela- tively simple measures, such as the establishment of time- related goals for each key review and regular monitoring of actual performance against those goals, would greatly assist the states in reducing processing times. Also of assistance in this regard would be more active state involve- ment with consultants and grantees during the facilities planning and design preparation stages, and implementation of a project tracking system, both of which were recommended earlier. 5-33 ------- CHAPTER 6 PROBLEMS AND NEEDS ASSOCIATED WITH THE DELEGATED CONSTRUCTION GRANTS PROGRAM When the Clean Water Act of 1977 was passed, Congress provided for and encouraged delegation, with the following objectives in mind: • That it would lead to optimal use of state and federal resources. • That it would eliminate duplication at the state and federal level. • That it would lead to decentralized management of the program. • That it would speed up the processing of grant projects. Based on field visits and evaluations made as a part of this study, it is clear that these objectives have not, as yet, been achieved. Perhaps the major reason for this is that delegation is not yet fully implemented. While many states have entered into delegation agreements, only about one-third of those states are administering all of the delegable functions and most of those states have become fully delegated only within the past few months. At the time the authors made their field evaluations, none of the 10 states visited were fully delegated. Beyond the fact that delegation is still in a transition phase, there are other factors contributing to why congres- sional objectives have not been achieved. These factors will not necessarily disappear when delegation is fully implemented. Some of these impediments are operational and are correctable through modification of management practices and procedures. Several others, however, are built into the law and the regulations which established delegation and therefore, to be remedied, will require 6-1 ------- amendments to those documents. These problems, as well as additional program needs, are discussed in the remainder of this chapter. OPERATIONAL PROBLEMS WITH DELEGATION Transition to Full Delegation not yet Complete The objectives of delegation obviously cannot be a- chieved until delegation is fully implemented, i.e., until states are administering all of the legally delegable func- tions. What may not be obvious, however, is that when the program is partially delegated, the resulting benefits are not directly proportional to the benefits that can be expected from full delegation. To the contrary, the result- ing benefits are considerably less. For example, a program that is 75% delegated in a certain state does not result in 75% of the benefits of full delegation. It does not reduce regional manpower requirements for processing pro- jects by 75%, nor does it eliminate 75% of the duplicative review, nor does it reduce processing times by 75% of the reductions possible at full delegation. The above point can be illustrated by referring to the original objectives of delegation and then examining several examples encountered in the field visits. Consider the second objective, the elimination of duplication. Under a partially delegated program, there is duplication of effort on functions which have already been delegated because individual review functions are not totally isolated from one another. An illustrative example is where a state had been delegated the authority to review and certify plans of study and Step 1 grant applications, but had not yet been delegated the authority to review and approve A/E subagreements. In this case it is readily apparent that 6-2 ------- there is duplicative handling of the A/E subagreement by both the state and the EPA regional office. But, what is not so obvious, is that there is also duplicative review of the plan of study-and the Step 1 application. For, in order to properly review the A/E subagreement, the EPA regional office must also review the plan of study and the Step 1 application. The plan of study describes the project and the scope of work for the facilities planning study. The EPA reviewer must have an understanding of the scope of work if he/she is to properly evaluate the resonableness of the subagreement. He/she must also check certain infor- mation contained in the application itself to insure that the subagreement is consistent with the cost and descrip- tion of work described in the application, which will in turn be the basis for the Step 1 grant. So in this example, whereas at first glance* duplica- tion appears to have been eliminated on 2 of 3 functions, it actually has not been eliminated. This example can also be used to illustrate that optimal use of federal and state resources (the first objective) is not achieved to the extent that would be expected with 2 of 3 key review functions associated with the Step 1 grant delegated. That optimal use of federal and state resources does not occur in proportion to the degree of delegation is further verified by the fact that most of the states visit- ed had the majority of the delegable tasks delegated to them at the time of the visits and were generally close to the full staffing levels called for in the delegation agreement. Yet, the regional staffs (with some exceptions) were essentially at or near the strength they had been prior to delegation. In general, the regional staffs appeared to be busy and, in a number of cases, unable to keep up with the work load. It might be argued that this is the result of new regional work load responsibilities associated with training and monitoring state staff. How- 6-3 ------- ever, the authors observed no monitoring programs and only one training program that utilized more than a fraction of a man year in a given state. While this may be due partial- ly to the considerable number of special activities over the past year (AST/AWT, the deferral, etc.)* part of the reason is also that, even in a substantially delegated program, regions must continue to perform a number of overlapping, project-related review activites. Consider now the relative achievement of the third objective of delegation, the decentralization of management to the states. With delegation in a transition phase, the take over by the states of the program management is also in a transition phase. In general, the authors did not sense that the states feel responsible for managing the program as yet, even if they have substantial delegation and are expending much greater manpower than are the regions on the state's projects. The current atmosphere is more one of shared responsibility. The regions probably still feel greater responsibility for program management than do the states, because the regions previously had a position of full program management responsibility. The states, on the other hand, had little program management responsibili- ties and with the laborious task of taking over the project review responsibilities and hiring and training new staff, they have not developed an attitude whereby they feel responsible for all aspects of the program. Therefore, while project management responsibilities may have been shifted to the states to a considerable extent, program management responsibilities have been slower to shift. The slower shifting of program management responsibil- ities may be due in part to the fact that most states do not yet have all of the project-review responsibilities; it therefore is difficult for them to feel responsible for the program. Before the states assume responsibility for managing the program, they must feel that they are respon- 6-4 ------- sible for the program. They must feel that if things go 'well, they are responsible and, likewise, if things go poorly they are also responsible. The feeling of respon- sibility that must precede state assumption of program management responsibility probably will not occur until sometime after all of the project review responsibilities have been delegated to the states. Even then, it will not necessarily occur. One development that may make it difficult to decentral- ize program management, even after full delegation, is the entry of the Corps of Engineers into the program. The Corps of Engineers' heavy involvement in most states in the Step 3 portion of the program brings with it some subtle sugggestions that may impare the states' developing a feeling of responsibility for the program and subsequently assuming program management responsibilities. The entry of the Corps of Engineers into the program, and particularly .the way in which the Corps of Engineers has been brought into the program, suggests that the states will not be responsible for the program after all. It suggests that the states will only be responsible for reviewing certain aspects of indi- vidual construction grant projects, and that EPA will continue to have prime responsibility for managing the program. This subtle suggestion evolves from the fact that the EPA regions have delegated portions of the project review responsibilities to the states (namely, Steps 1 & 2) and portions of the project review responsibilities to the Corps of Engineers (namely, Step 3 construction-relat- ed activities). Further, the Corps of Engineers feels it cannot work directly for or with the states, it can only perform work (at least officially) for another federal agency. Therefore, officially the Corps of Engineers deals through the EPA regional office. The Corps of Engineers has its agreement with the regions and transmits originals 6-5 ------- of its inspection reports, etc. to the regions, with copies to the states. In this situation, it will be difficult for the states to assume responsibility for the program. Because the Corps of Engineers' agreement and official communications are with EPA, rather than with the states, the states are not respon- sible for a significant aspect of the program, the construc- tion aspect. Without responsibility for all aspects of the program, the states cannot assume responsibility for the program. Unless something is changed, therefore, even after "full delegation" to the states, Congress1 objective of decentralization of program management will not be re- alized. An additional problem with the current arrangement with the Corps of Engineers is that it has the effect of dividing responsibility for the program, with the result that no one is clearly responsible or held accountable if problems occur during Step 3. To get the job done, especially one as big and as complex as administration of the construction grant program, total program responsibility has to be concentrated in a single organization, and perhaps in a single individual. When responsibility is divided, as it is in this situation, no one person or organization is responsible. Of interest is the fact that one of the objectives of delegation was to remove a layer of government from the ad- ministration of the program. With the Corps of Engineers involvement, there are now three agencies involved in the processing of individual grant projects. This is not to say that bringing the Corps of Engineers into the program was a mistake. On the contrary, their involvement appears to be quite beneficial and the authors see nothing wrong with their continuing to be involved. The problem is the way in which the Corps of Engineers has been brought in- that is, with the Corps of Engineers essentially working for EPA at the same time that the states are supposed to 6-6 ------- be assuming responsibility for the program. The obvious solution to this situation is to have the Corps of Engineers work under the direction and control of the states. This can be accomplished in several ways. Rath- er than the Corps of Engineers entering agreements with each regional office, they could enter an agreement with each delegated state. Alternatively, EPA could delegate, as one region has done, the responsibility for managing the Step 3 portion of the program to the states. These alternatives in essence make the states responsible for all aspects of Step 3, including the work performed by the Corps of Engineers, and allow the states to assume a total program management role. Unless an alternative along the lines of those suggested above is implemented, true decentralization of management can only take place if the delegated states take over, as some already have, those Step 3 functions that are commonly ad- ministered by the Corps of Engineers, removing the Corps of Engineers from the program entirely. As discussed earlier in this report, state assumption of Corps of Engi- neers activities is unlikely to occur in the near future, because of the limitations on and the instability of Sec- tion 205(g) funding. In terms of Congress1 last objective of delegation, speeding up the processing of grants, it is clear from the discussion in Chapter 4 that delegation does not necessari- ly result in significantly faster processing at the region- al offices. While delegation should theoretically enable regions to reduce their processing times significantly, other management practices in conjunction with delegation are necessary if this goal is to be accomplished. Again, without these additional management practices, even comple- tion of the transition to full delegation will not cause this goal to be achieved, at least to the degree which is possible. 6-7 ------- Further, to speed up the processing of projects through delegation, one cannot focus only on regional processing time. While the time for regional processing of projects should be able to be reduced significantly (with the addi- tional management practices referred to above), delegation gives the states the responsibility for processing projects in accordance with all of the federal requirements that previously had burdened and slowed EPA's reviews. Transfer- ring this review responsibility to the states does not mean that the states will be able to process the documents any faster. In fact, as pointed out in Chapter 5, state processing times under delegation (with a few exceptions) have not been very good. While statistics on state processing time prior to dele- gation are not generally available. the authors would venture to guess that the total processing time for projects has increased, rather than decreased, at this stage of delegation. This guess is based on the moderate reduction in EPA processing times noted in Chapter 4 and the likeli- hood that state processing times have increased to a great- er extent, due to the new federal requirements the states are now administering. Delegation alone will not result in the achievement of Congress1 objective of speeding up the processing of grant projects. Delegation in combination with implementation of certain management practices, discussed in Chapters 4 and 5, can result in achievement of these objectives. In summary then, one of the problems with the delegated program at this stage is that it is only partially implemen- ted. Most states are still in the transition phase of taking over project-related review functions from the EPA regional offices. While this transition is well along in most states, the potential benefits of delegation, in terms of elimination of duplication and optimal use of federal and state resources, will not be apparent until 6-8 ------- delegation is completed. Short of full delegation, EPA duplication of states' effort and EPA's resource needs will be higher than is suggested by the achieved degree of delegation. Likewise, decentralization of management and state assumption of program management responsibilities will not come until the delegation process is completed. When the delegation process is completed, the current way in which the Corps of Engineers is involved in the program will prevent achievement of the third objective, though there are several ways in which both continued Corps of Engineers involvement and state assumption of program man- agement responsibilities can occur. Finally, while partial delegation has probably not had an impact on the processing time of projects (except perhaps in the negative sense), full delegation in itself will not result in achievement of this objective. Full delegation however, together with implementation of certain management practices, can enable realization of this final objective. So, partial delegation has not resulted in any signifi- cant realization of congressional objectives. When full delegation is completed, two of these objectives will for the most part, be realized (optimizing resources and elimi- nating duplication) and the realization of two others (decentralization of management and speeding up project processing times) will be enhanced, though full delegation alone will not cause realization of these objectives. Other measures will also be necessary. Based on the conclusion in the above discussion, i.e., that partial delegation does not yield significant benefits, and based on the discussion in Chapter 5. that even relatively inexperienced states have been able to take over the program quite rapidly, it appears that EPA should move as rapidly as possible towards full delegation in all delegated states. Further, newly delegated states should be guided through the transition process at a faster pace than were many of the 6-9 ------- initially delegated states. To do this, greater EPA train- ing and guidance will undoubtedly be required. Regional Practice Of Administering New Requirements Another problem which impacts implementation of full delegation, observed during the field evaluations, occurs when new program requirements are issued, usually in the form of a new Program Requirements Memo (PRM). It is common practice, when a new program requirement becomes effective, for the regional office to initially administer the new requireement; the regional office continues admini- stering the new requirement until the region and the state can negotiate an amendment to the delegation agreement to specifically address the new requirement. This appears to be the case even when the state has received delegation of other program aspects related to the requirement. For ex- ample, the state may already have been delegated facilities plans, but when the public participation or some similar requirements become effective, EPA would initially adminis- ter these new requirements. The effect of this type of approach, given the fact that new program requirements appear continually, is that the states never quite have full authority to administer all of the legally delegable functions associated with individual grant projects. Rath- er, the regions are continually in the position of having to review state-certified documents to check for the new requirement that has not yet been delegated, because an amendment to the delegation agreement has not yet been negotiated. What previously had been full delegation of a function reverts back to a partial delegation. Invariab- ly, this type of approach results in duplication of effort and time delays. Often these time delays are quite signif- icant because of the fact that the requirement is a new one and the regions are not initially certain how they want to administer it. 6-10 ------- Perpetuation of the practice discussed above will pre- vent total delegation from occurring, and therefore will impede achievement of the objectives for which delegation was designed. The authors see no reason why, when a new program requirement is issued, that the regional staff cannot immediately meet with state staff to discuss admini- stration of this new requirement. Most probably a similar discussion has to be held within the regional office when the region takes on administration of a new requirement; so, why not replace that internal discussion with a discus- sion with the delegated states? The interim procedures to carry out this new program requirement can be negotiated with the state and then utilized until a formal modification to the delegation agreement can be negotiated. Such a prac- tice would maintain all delegable project review activities at the state level even in the wake of continuing implemen- tation of new requirements. Likewise, it would eliminate duplication of effort related to the new function, would reduce manpower requirements at the regional level, and would reduce the processing time associated with individual grant projects. New Program Requirements Which Are Non-Delegable One other aspect of new program requirements that is of concern relates to the increasingly common practice of leav- ing portions of the responsibility for new program require- ments at the regional level, i.e., essentially identifying certain functions as non-delegable. The AST/AWT reviews certainly are reflective of this approach (though EPA did not have much choice on this), and similar approaches seem to be taken in regard to other new program requirements, such as MBE, pre-construction lags, and the PRM on Section 316A of the Clean Air Act. The practice of identifying functions as non-delegable appears to be born out of a philosophy that whereas EPA can entrust the states to 6-11 ------- perform many functions, there are certain functions which only EPA can perform. Again, as indicated previously in this chapter, not delegating project-related review func- tions, for whatever reason, detracts from the achievement of the potential benefits of delegation and of the original objectives for which delegation was designed. Question Of Authority To Interpret Federal Policy Another problem in several regions relating to the div- ision of responsibilities between the regional offices and the delegated states is the issue of authority for inter- pretation of federal regulations, PRM'S, and other program policies. Do the states have authority to make interpreta- tions of these requirements, or does the authority rest solely with the regional offices? A related question is whether the regional offices have the authority to impose policies more restrictive than national policies on the states. This latter question arose during the field visits when it was found that several regions had developed region- al policies more restrictive than federal policies in a given area and were imposing those policies on delegated states. An example is a region that for years had utilized a fairly restrictive policy on the funding of intercepter sewers, considerably more restrictive than the federal policy. The issue is whether or not that region could impose the restrictive policy on its delegated states, or whether the delegated states have the authority to use a different interpretation, as long as it is not inconsistent with federal policy. The authors believe that the states should have the re- sponsibility for interpreting EPA regulations and policies related to their projects unless a proposed interpretation has national policy implications, in which case EPA head- quarters should resolve the issue. The authors do not believe that the EPA regions should impose their own inter- 6-12 ------- pretations, outside of interpretations made at the national level, on delegated states. There is an argument for consistency of interpretation at the national level, and there is an argument for consistency at the state level. There does not appear to be an argument for consistency at the regional level under the concept of delegation. PROBLEMS ASSOCIATED WITH THE LAW AND REGULATIONS Beyond the problems associated with delegation which stem from current operating procedures and practices, there are several problems which have their roots in the laws and regulations which apply to delegation. A Number Of Project-Related Functions Are Not Delegable One problem that will impede achievement of the object- ives of delegation is that even under "full delegation", EPA retains responsibility for performing a number of project-related functions on each construction grants pro- ject. The project-related functions which EPA regula- tions identify as non-delegable and which EPA retains responsibility for are as follows: On All Projects • Civil Rights Determinations • NEPA Review and Issuance of the FNSI • Award of Step 1, 2, and 3 Grants • Amendments to Step 1, 2, and 3 Grants • Wage Rate Determinations (Federal policy prevents delegation) • Minority Business Enterprise (Federal policy pre- vents delegation) On Some Projects • Bid Protests • Resolution of Disputes 6-13 ------- • Resolution of Audit Exceptions • Resolution of Issues on Projects of Overriding Federal Interest • Preparation of Federal Environmental Impact State- ments In each of the above cases, documents must be passed from the state to the regional office, a review made by the region, and a decision rendered and transmitted back to the state. In the case of the EPA project level reviews performed on all projects, the state has already reviewed and approved the respective documents before transmitting them to the regional office, because transmitting an unacceptable document would lead to further delays. Thus, these reviews generally constitute a duplication of effort and, as a result, less than optimal use of federal and state resources. Because of the requirement that states transmit the documents to the regional offices, and the subsequent required EPA review, processing time is extended over what it would be if only the state reviewed the document. In two of the cases where EPA occasionally becomes in- volved in projects, namely bid protests and audit resolu- tion, duplication of effort also results. In the case of a bid protest, the state is already familiar with the project, and probably with the nature of the bid protest because of its processing of the plans and specifications and the bid documents. The EPA regional office is not familiar with the project. Therefore, someone from the regional office has to get the background on the project and the protest. Often he/she relies on briefings and information received from the state staff member who is already familiar with the situation. The logistics, namely the separation of the state and regional offices, further add to the difficulties of the process. Thus, because EPA, rather than the state, must process bid protests, additional unnecessary resources have to be expanded both by EPA and the state. Similar problems exist in the case of audit resolution. 6-14 ------- While more efficient use of manpower and time savings would result if all of these project-related review functions were delegated, the question remains as to whether something would be lost or risked if this were done. In relation to MBE, civil rights determinations, wage rate determinations, bid protests and audit resolution, the authors feel that the answer to that question is "no". There may be some who argue that the states cannot be trusted to carry out these actions. One gets the impression that this feeling exists in regard to MBE. Yet, it seems inconsistent to trust the states with complex multi-million dollar decisions and not to trust them to determine whether a consultant made a good faith effort to involve MBE's. The latter types of functions are relati- vely simple and easy compared to the functions the states have already been entrusted with. When one considers the "consequences of error" for one of these non-delegated functions and the "consequences of error" for the cost- effectiveness and design reviews that the state does, there is no comparison. The consequence of occasionally approving a contract where a good faith effort was not made to secure MBE involvement is relatively minor, assuming that the region's monitoring program will insure that such actions are minimized. On the contrary, the consequence of a non-cost-effective project being built can be the permanent loss of millions of taxpayers dollars. The consequence of an inadequate design being approved can likewise be the loss of millions of dollars and an unnecessary and substantial delay in cleaning up a serious pollution problem. Refraining from delegating these few remaining project- related actions causes duplication of effort, time delays, and does not seem to result in any benefits over having the state take responsibility for them. The after-the-fact mon- itoring conducted in conjunction with delegation should be 6-15 ------- able to identify any problems in the states' handling of these reviews. The cases of grant awards and NEPA are a little different. Making the grant awards is the action to award the federal funds, and it can be argued that only the federal government ought to take such action. In reality, however, the action of awarding the grant is strictly ministerial under the delegated mode of operation. Basical- ly, the region receives a state certification, a checklist and the typed federal grant offer. No meaningful informa- tion related to the project is submitted with the package. If the state certifies the project and demonstrates with the attached checklist that all federal requirements have been satisfied, then the region is supposed to make the award. In effect, then, the significant action is taken at the state level when the project is certified. No action, consistent with the terms of the delegation agree- ment, could be taken by the region to modify the project or not make the award. Therefore, no readily apparent benefit is associated with the regions, as opposed to the states, making the awards. The cost of this practice, on the other hand, is duplication of effort and lost time. Based on Table 4-2, the regions currently average 4 months total to make the 3 grant awards involved in a typical project. Assuming a 1% per month inflation rate and a $3.4 billion national appropriation, the process of having the regions make the grant awards is currently costing $182 million per year in terms of lost buying power. Assuming that total regional processing time for all 3 awards can be reduced to one month, as the authors believe it can, the lost buying power, while reduced, is still a significant amount, $45 million. The authors see two other advantages to delegating grant awards to the states. First, such a practice removes the regions from the uncomfortable situation they are 6-16 ------- in under delegation—especially the regional official who signs the grant award. By signing his/her name and making the grant award, the regional official is taking the res- ponsibility for releasing federal funds for the subject project. In the eyes of the public, he/she is responsible for that project being a good one. If the project is a disaster, he/she in effect would be held responsible by the public. Yet, under delegation, the regional official cannot question the project and he/she basically has no information available with which to evaluate whether the project is a good one or a poor one. The regional official must trust that the state has done a good job on the project and must trust the region's monitoring program to identify any state processing deficiencies that might allow poor projects to pass through the system. Being that monitoring programs are conducted after the fact and generally look only at about 10% of the states' actions, this is not a comfortable position to be in, ,as several Regional Water Division Directors have indicated to the authors. Having the state make the grant awards would remove the regions from this position. One other negative aspect of having the region make the actual grant awards is that it removes some of the responsibility from the state. If there is a problem, the state can point to the region which signed the award. While the state actually took the significant action, the public would tend to hold EPA responsible and it would be difficult for EPA to argue that they are not responsible, although they signed the grant. This situation, i.e., ambiguous assignment of responsibility for project level decisions, has the effect of relieving (to some extent) the state of responsibility for the projects and the program. If anything goes wrong, there is at least a chance that EPA will have to share the responsibility. 6-17 ------- The authors believe that the states will better admin- ister the program if they are not in a position of sharing responsibility. If the states know that if there are any mishaps associated with a project or the program, they are responsible, the weight of that responsibility (especially for a program as large as the construction grants program) will encourage them to more carefully review projects and manage the program. Requiring that the states make the grant awards, then, shifts responsibility to the states, removes the region from an uncomfortable position, reduces EPA manpower requirements, eliminates duplication, and saves time and money, all of which are positive. On the negative side, there may be a legitimate con- cern, that as EPA delegates the program and reduces its resources, EPA may lose interest in the program and not support it politically as vigorously as it has in the past. Keeping grant awards at the regional office level may tend to maintain a strong EPA interest in the program. It also may encourage regions to conduct meaningful monitor- ing programs, which in turn will hold the states more accountable for doing a good job of administering the program. In these respects, keeping grant awards at the regional level may be beneficial. Again, the non-delegated NEPA functions are different than the non-delegated functions referred to earlier, in that the environmental review that the EPA regional offices make of individual grant projects is the one substantive review made under delegation. The primary purpose of this review, according to the EPA regulations, is to determine whether a federal environmental impact statement will be required under the National Environmental Policy Act. Based on the review, either an environmental impact statement is prepared or, more commonly, a finding of no signifi- cant impact (FNSI) is issued. There are probably several 6-18 ------- reasons why NEPA responsibilities were the only substantive non-delegated function when the Section 205(g) regulations were formulated. One reason is that environmental groups were concerned about whether or not states would have the same environmental ethic that EPA has demonstrated over the years. Because of this concern, environmental groups opposed the concept of delegation. Refraining from delega- tion of NEPA responsibilities would certainly make these groups more comfortable with delegation. There is also some question as to whether the federal NEPA responsi- bilities can be delegated to states. There are several federal programs, however, where the responsibilities for NEPA have been delegated to the states. In one case, such delegation was provided for in the federal legislation cover- ing the particular program involved. From this standpoint then, the concept of delegating NEPA responsibilities to states is not without precedent. Again, as in the other cases discussed, the advantages of delegating NEPA would be a savings in manpower, elimina- tion of additional duplication of effort, the saving in time and therefore money, and more clearly placing responsi- bility for all aspects of the program on the delegated states. In essence, while NEPA cannot be delegated to states under existing EPA regulations, most states are performing, or are planning to perform, many of the necessary preliminary activities associated with the EPA NEPA review. Most states under delegation will be preparing the environ- mental assessments on which the regional office issuance of a FNSI will be based. Of the 10 states visited by the authors, 5 of those states were preparing environmental assessments. In these states, the EPA regions were review- ing the assements, making any changes that they felt were necessary, and when they were satisfied, were issuing the FNSI. 6-19 ------- In the usual situation, early in the period of time during which the states were preparing the environmental assessments, the regions had a number of problems with the state-prepared assessments. The primary problems were that the assessments lacked sufficient detail or did not cover certain environmental issues of concern to the regional office. Over time, however, in each case, the prepara- tion of the environmental assessments gradually improved to the point that the regional office was generally satis- fied with the assessments that had been prepared. Occasion ally, however, additional information was requested for placement into the assessment, or editorial changes were made. In no cases that the authors were made aware of (either by the states or by the regional offices), did the regional review of an environmental assessment lead to a modification of a project or to a federal decision to prepare a federal environmental impact statement. In several states, the state preparation of the environmental assess- ment had reached a level of satisfaction to the regions, such that the regions were not making any modifications to the assessments, but were just reviewing them and issuing the FNSI. Thus, while NEPA cannot now be legally delegated, much of the work associated with NEPA is, in fact, being perform- ed by delegated states. Further, the work that the states are doing generally appears to be satisfactory to the EPA regional offices, once the state gains an appreciation of what the region wants in the assessments. In the authors' opinion, then, the one remaining substantive regional re- view associated with delegation has reached the point in some states where regional action is no longer substantive; rath- 6-20 ------- er- the regions are accepting state determinations. Based on this experience- the authors conclude that the states which they observed (and possibly other states) have demonstrated to the satisfaction of the EPA regional office that they have the environmental ethic to administer the NEPA aspects of the program. Once this has been demonstrat- ed to a regional office, it appears to the authors that before-the-fact regional office review and approval of NEPA documents and regional issuance of the FNSI, serves limited, if any, benefit. The authors realize that this is a sensitive issue and EPA would certainly be wise to carefully consider all of the ramifications before moving to delegate NEPA to any state. At the same time, the authors point out that administration of NEPA aspects of the program is another project-related function that has to be performed by EPA under the current system of delegation, and therefore detracts, at least to some extent, from achievement of the initial objectives of delegation. To delegate NEPA, along with the other project -related activities described previously, would further enhance achievement of the objectives for which delegation was intended, namely optimization of federal and state resources, elimination of duplication, decentralization of management, and speeding up of the processing of grants. In monetary terms, again using the 1% per month inflation rate, and assuming that the regional offices can reduce their NEPA review times to 30 days, continuing to have the final NEPA sign-off in the regional offices costs $45 million per year, based on a $3.4 billion per year appropriation. Inadequacy Of Section 205(g) Funding A second problem stemming from the law, and more speci- fically from Section 205(g) of the Clean Water Act relates to the provision for funding. Section 205{g) provides states 6-21 ------- with up to 2% of their annual construction grants allotment for program administration. There are two basic problems with this system of funding. The first problem is that congressional appropriations, especially in recent years, have not been predictable. There has been at least one year since the Clean Water Act of 1977 was passed wherein it appeared that Congress would not make an appropriation, and in at least one other year an extremely low appropria- tion appeared highly possible. A funding system which bases administrative funds on erratic and unpredictable congressional appropriations is not a reliable funding system, and causes delegated states to act fairly conserva- tively in terms of adding staff. One instance that brought this problem to the forefront was the experience in the state of California, which had already staffed up to a fully delegated level, when the Section 205(g) provision was added to the Act. The state had no reserve funds to fall back on (as did other states) when Section 205(g) was added, and basically had to rely on the annual 2% of the state's share of the national appropriation. Since the Act was passed, however, the appropriations have decreased each year. As a result, the state had to reduce its budget each year, at the same time reducing staff associated with the construction grants program. Over the last several years, the staff has been reduced from a level of 165 to a current level of 111. Along with these reductions, the state has been forced to reduce its level of review of projects, and to turn much of its construction-related activities over to the Corps of Engineers. Previously, the Corps of Engineers had not been involved in the California program because the state had an established construction manage- ment program. 6-22 ------- Many of the states involved in the construction grants program are quite familiar with the situation in California, and therefore most of them are very cautious about taking on additional program activities. Particularly affected are those activities being administered by the Corps of Engine- ers. Within the next year or so, most states will have been delegated administrative responsibility for all of the delegable Step 1 and 2 activities. Most states would like to take over construction-related activities as well so that they have all aspects of the program under their direction and control. However, given the funding uncertain- ties that currently exist, and given the significant staff resources necessary to take over those activities being performed by the Corps of Engineers, most states will not seek, in the foreseeable future, delegation of these activi- ties. No state wants to add staff to take over these add- itional activities and to then find themselves in the situation that California found itself in. There is an additional problem with the current system for funding state administration of the delegated grants program. Specifically, the 2% funding level appears to be inadequate for many states to properly administer all aspects of the program. Of the 10 states that were visited in conjunction with this study 3 states had operating budgets in excess of 2% of their allocation. These budget deficits were being made up by utilizing Section 205(g) funds that had been reserved in the early years of the Clean Water Act of 1977, before the states had increased their staffs so as to function under delegation. Within a year or two another 3 of the states visited expect to be at the 2% funding limit, as they continue to add staff and as personnel costs increase. Therefore, more than half of the 10 states visited will soon be operating with budgets at, or in excess of the 2% allotment. 6-23 ------- The authors feel that Congress should act to provide states with a more stable source of funding for administra- tion of the construction grants program and that funding has to be increased above the 2% level. Recently enacted legislation tying Section 205(g) funding to the authoriza- tion level will greatly assist in stabilizing funding. However, funding may still prove to be inadequate in magni- tude if appropriation levels approach authorization levels. Delegation is Optional With The States Another problem resulting from the Act is that the choice to pursue delegation is left to the respective discretion of the EPA regional offices and the individual states. If either party desires not to pursue delegation, then delegation is not implemented. As pointed out in Chapter 3, most of the remaining non-delegated states are states which have chosen not to pursue delegation, primari- ly because of a concern about the impact of the additional resources required on the size of state government. Initially, this situation did not appear to present any problem. It now appears, however, that within one year, between 42 and 44 states will be delegated and it is likely that within several years approximately 90% of the 50 states will have entered into delegation agreements with EPA. This leaves a small number of states which will not have delegation. In turn, this will require, at least as presently conceived, the respective EPA regional offices to administer the program in those non-delegated states. Thus, approximately 5 EPA regional offices will be adminis- tering the program in two different ways. On the one hand, they will have program level responsibilities and project responsibilities in one state within the region, and only program level responsibilities in the other states. The authors feel that this mixing of responsibilities be- 6-24 ------- tween program level and project level, especially since the non-delegated states will be a small minority is an inefficient way to administer the program from a national perspective, and certainly from EPA's perspective. The authors feel it would be desirable to develop a system that would essentially lead to full delegation of all 50 states within the next several years. Another basis for the authors' suggestion is their observation, during visits to 10 delegated states throughout the country, that states have shown considerable ability to take on administration of the delegated program. The authors are convinced that the remaining non-delegated states, given adequate resources and given assistance from EPA in the initial periods of delegation, can effectively assume and administer the delegated program. Having all 50 states delegated would allow EPA to focus on fulfilling a broader responsibility related to the con- struction grants program, that 'is, the responsibility of overviewing the program from a regional and from a national perspective to insure that the program is being properly administered and that national water pollution control objectives are being achieved. In summary, concerning the problems with delegation that are built into the system itself, the authors believe that the EPA regulations should be amended to allow delega- tion of all project-related responsibilities to the states.- that the level of funding should be increased above the 2% level and that EPA, perhaps with congressional assistance, should develop a mechanism to achieve delegation in all 50 states. 6-25 ------- PROGRAM NEEDS EPA Headquarters Needs In order to evaluate and monitor the delegated construc- tion grants program, EPA Headquarters needs to perform the following tasks: • Establish and maintain an up-to-date information sys- tem that contains the following information for each state: - Certain background information on each delegated state. - Current information on the status of delegation in each state. - Information on the budget and manpower resources associated with each delegated program. - Summary of this information on a national level. • Perform an annual assessment of how well each region- al EPA office is fulfilling its responsibilities under delegation. • Perform a biennial assessment of how well each state is fulfilling its responsibilities under delegation. • Identify, based on the above assessments, significant problems that exist or are arising, either within individual states or regions, or with the delegated program as a whole. • Finally, EPA needs to prepare a biennial report on delegation which summarizes this information, asses- ses the overall impact of delegation and whether the program's objectives are being achieved, and identifies recommendations for improving the pro- gram. In the early years of delegation, EPA may want to produce this report annually. 6-26 ------- Need for State Involvement in Program Management One of the more difficult problems facing EPA (and particularly EPA Headquarters) while operating in a delegated mode is how to direct the national program in a way that best facilitates achievement of the goals of the Act. What makes this task so difficult is that under delegation, EPA (both headquarters and the regions) will be removed from the day-to-day administration of grant projects and the program. EPA will not be in a position to identify program problems and needs directly, nor will they be able to accurately evaluate the impact of potential national directives on the program. Under delegation, only the states will have the capability to provide this information. In other words, under delegation EPA retains the responsibility for directing the national program, but the states, who are administrating the program on a day-to-day basis, have much of the knowledge needed to provide this direction. The challenge, under delegation, then, is. to make the knowledge that the states will be gathering as they admin- ister the program available to EPA so that they can do an effective job of directing the national program. This will not be an easy task. The key obviously is communications. But how does EPA Headquarters communicate with 40 or 50 states? Should the EPA regions continue to serve as key communication links between the states and EPA Headquarters, or should the states communicate directly with Headquarters? Beyond the opportunity to communicate with EPA Headquarters, should the states play primarily an advisory role or should they be given a stronger role in program management? These questions all involve significant issues that must be addressed if EPA is to continue to effectively direct the national program under a, delegated mode of operation- 6-27 ------- |