DESIGN OF THE
NEWTOWN CREEK WATER POLLUTION CONTROL PROJECT
               THE CITY OF NEW YORK
                 JOSEPH CUNETTA, P.E.
                  ROBERT FEUER, P.E.
                        1967
   PRESENTED AT THE WATER POLLUTION CONTROL FEDERATION
     ANNUAL MEETING, OCTOBER 12, 1967, NEW YORK CITY

-------
              DESIGN OF THE

NSWTOWN CREEK WATER POLLOTION CONTROL PROJECT
            JOSEPH CUNETTA, P.E,
            ROBERT MEUEK, P.E.
                   1967

-------
                               DESIGN OF TOE

               NEWTOWN CREEK WATER POLLUTION CONTROL PROJECT

                           JOSEPH CUNETTA,  P.E.
                           ROBERT FEUER, P.E.
I - INTRODUCTION

    The City of New York is presently pursuing two programs to control

    pollution in its waterways.  These are:

         1.  The Basic Water Pollution Control Program,  which will ultimately

             provide treatment for all the City's wastewater in modern

             treatment plants.

         2.  The Auxiliary Water Pollution Control Program, which will provide

             fcr the retention, degritting and disinfection of combined flows

             during periods of rainfall.  The objective of this program is to

             control combined overflow pollution and insure safe water quality

             where recreational facilities,  particularly new bathing beaches,

             are planned. A prototype 'Auxiliary Water Pollution Control Plant1,

             located at Spring Creek in Brooklyn, is scheduled to be constructed

             in 196?.
    Joseph Cunetta is Deputy Director (Plants)

    and Robert Feuer is Project Engineer,

    Bureau of Water Pollution Control

    Department of Public Works

    City of New York
                                   -1-

-------
The Implementation of the Basic Water Pollution Control Program, which



dates to the beginning of work at the Wards Island Plant in 1931, has



been delayed considerably by the depression of the early 1930's and two



major wars.  Availability of Federal and State construction aid grants



in recent years has added momentum to bring this program to its conclusion



by 1972, thereby allowing New York City to meet its commitments to



regulatory agencies,





As originally proposed, the program envisioned 18 treatment plants and



intercepting sewer systems located about the waterfront areas of the City,



The total design capacity of the proposed plants is l8l£ million gallons



per day (MGD), based on mean dry weather flow.





Figure 1 (next page) - "Plan for Pollution Control", shows the number



and locations of the projects involved in both the Basic and Auxiliary



Programs, including a table of capacities of the Basic Water Pollutiori



Control Projects,





The Newtown Creek Project, together with the 12 modern treatment plants



presently in service, have a combined design capacity of 13U6.5 MGD, thus



accounting for approximately 7k% of the total planned design capacity  for



the City's Basic Program,  The 12 plants in service now treat about  two-



thirds of the City's dry weather wastewater.





The Newtown Creek treatment plant was placed in operation in 196?, with



an initial flow from the Brooklyn and Queens drainage areas only.  The



flow  from the Manhattan drainage area will be added when construction  of



the Manhattan Pumping  Station, now in progress, is completed in 1968,
                               -2-

-------
       BASIC PROGRAM
    INTER POLLUTION CONTROL PROJECTS
            BROOKLYN
     1 HCVTOON CMEK
       no* uuntfam  ml
          BET   >•«•)
     0 TALLMANS ISLAND
     I JUU1CA
     2 IOWCRT 1AY
     3 ROCKAMT
    1 4 POST RICHMOND
     5 BLOOMriELO
    I t OAKKOOO  Ki.KM>
TIIHM8 fC^f I^A-


PLANT Ml
1
1
g
4
5
•
JAMAICA BAY
LOCATION STATUS
MCHOCUT ftASIM PWCLBLOCaiitN
HCHOAIX ST. MCLHL OCSMM
SPUING CHECK DOM
KHOCN usm
THUMSTON BASIN
UPPER EAST RIVER
BRONX
>LANT NO LOCATION STATUS
I VICLC *vt
FARM* OUT ST.
SOOWDVliIW P«
WHITE PVA1NS TO
PUSSLCY CKCK
WtlTCMCSTEH CK W
VESTCtCSTCK CK. E.


QUEENS
»LAIIT NO. LOCATION STATUS
E.OF BCWCRY BAY ST.W
SHAMO CEMTNAL PKWY-
FLUSHIWO RIVER
FLUSHMM KAY S.
2O*" AVI. FLUSHING
FLUSMM BAY N.
COLL.E8K POINT
POWELLS COVC
10 LITTLE MY
II ALLEY CHECK
\t PWOPOSCO BASW
          PLANTS

M OPERATION

UNOCR CONSTRUCTION •

UNDER DESIW    3

FUTURC        O

OMMMN JWOfR CONtrH)

            a
        LEGEND OF SYMBOLS
         POLLUTION  PUMPING  WTERCEPTING  ORAHAGE STORM WATER
         CONTROL  STATIONS    SEWCRS    AREAS    TREATMENT
                                       PLANTS
         CITY  OF  NEW  YORK
DEPARTMENT  OF  PUBLIC  WORKS

                                                              PLAN
                                                                FOR
                                                POLLUTION    CONTROL
                     CMAINAW AMA1
                              e
                <.mn or MAMMI wu»
                                                              FIGURE

-------
II - BASIC DESIGN DATA
         !•  The Newtown Creek Water Pollution Control Project Treatment Plant



             is located at Newtown Creek in the Greenpoint section of the



             Borough of Brooklyn and serves portions of the Boroughs of



             Manhattan, Brooklyn and Queens.





             The treatment plant utilizes the "High Rate" activated sludge



             process and has a design capacity of 310 MGD based on average



             sewage flow from an estimated equivalent contributing population



             of 2,500,000.





             The Plant provides for:  screening, pumping, grit removal, aeration,



             sedimentation, sludge concentration, sludge digestion, disposal of



             digested sludge to sea by vessel, disposal of grit by barges,



             utilization of sludge gas for power and heating, and hypochlorination



             of plant effluent.
             The plant is expected to remove, on an average, approximately




             of the suspended solids and approximately 6/0% of the B.O.D. from



             the raw sewage.






             Figure 2 (next page) - "Flow Diagram", shovis the major operations



             at the treatment plant and at the sewage pumping stations.






         2.  DRAINAGE AREA.



             The drainage area served includes portions of the Boroughs of




             Manhattan, Brooklyn and Queens, covering a total area of 15,38? acres,






             a.  MANHATTAN -  The Manhattan portion of the drainage area consists
                                       -U-

-------
                                                                                                                      PLANT EFFLUENT
                                                                                                                      HYPOCHLORINATION
                                                          AERATED
                                                         GRIT CHAMBERS
                                                                Fl
                                                                                                   SEDIMENTATION TANKS

                                                                                               UNITS
                    FORCE  MAIN TUNNEL
                                                                     I.4SHRS. AT 3IOMGD
                                                                                          .-ALTERNATE TO
                                                                                          /DIGESTION TANKS
                                                                                                          SLUDK UNDERFLOW
                                                                                                              EMERGENCY SLUOOE VESSEL
                                                                                                                        '. CREEK CANAL
    SURGE TANK
    AND OOWNMOLE
    SHAFT
                                                                                       AINERIZEO
                                                                                     SKIMMINGS
                                                                                        4 .-TRUCKED TO INCIN
                                                                                        !/ ERATORS OR 3ANI-
                                                                                        r TARY LAND FILLS
                                                  TRUCKED TO  \
                                                  GREENPOINT
                                                  MARINE TRANS-
                                                  FER STATION-N
             RECYCLED DIGESTED SLUDGE
                                           MAIN
                                          SEWAGE
                                           PUMPS
                                                   •AHMINUTOR
                                                   CUTTINGS
                           TRUCKED TO  §
                           INCINERATORS r;
                           OR SANITARY
                           LAND FILLS
TRUCKED TO
INCINERATORS
OR SANITARY
LAND FILLS
WASTE OR EXCESS SLUDGE '
                                                                                                                  IMARY
                                                                                                                  RATE
                                                                                                                  DIGESTION
                                                                                                                   TANKS
                                                           ENGINE GENERATORS
                                        MECHANICAL
                                         SCRCENS
                                        t"OPeNIMGS
           MECHANICAL
            SCREENS
            /fOf€nnsa
                                                              WASTE GAS BURNERS
                                       INTERCEPTING SEWERS
                                       AVERAGE SEWAGE FLOW)
                              BROOKLYN
                               (140 MOD
                                                                                                                                     SLUDGE VESSEL TO 1C
MANHATTAN INTERCEPTING SEWERS
   (ITOK.OD AVERAGE SEWAGE FLOW)
                                                               CITY    OF   NEW  YORK

                                                    DEPARTMENT    OF   PUBLIC   WORKS
                                          NEWTOWN  CREEK  POLLUTION  CONTROL   PROJECT
                                          FLOW DIAGRAM-CAPACITY  310 MGD AVERAGE  SEWAGE  FLOW
                                                                    FIGURE  2

-------
of 1,162 acres of a widely varied character, including the




lower west side of the Borough to West llth Street and the




lower east side to East 71st Street.






The section along the east sice from Chambers Street to East




71st Street is mainly residential, but has in recent years




undergone some change , as evidenced by the construction of




the United Nation? Buildings, new office buildings and several




public and private housing projects.  The Grand Central Section



is occiipied mainly by office buildings and hotels.  The Midtown




Section is predominantly occupied by office buildings, hotels,



theatres, department  stores and restaurants.  Greenwich Village




is a mainly residential area.  From Canal Street to Chambers




Street  light  industrial and mercantile establishments predom-




inate.  The section below Chambers  Street,  to the Battery, is



occupied  mainly  by office buildings, including many skyscrapers




and  some  residential  buildings on the «p.st  side.






The Manhattan drainage area,  due  to its  special character, has



a large non-resident  transient and working  population.  Another




unique  condition,  particularly in the North Branch Section of




the Manhattan interceptor system, is the large inflow of  ground



water.  This  inflow finds its way into the  existing sewer system




via infiltration into the sewers  and pumping of seepage from




large buildings.  To  allow  for this condition, the treatment




plant capacity has been increased by 27  M.G.D.
                    -6-

-------
   b.   BROOKLYN -  The Brooklyn portion of  the drainage  area  covers



        7,191 acres in the northwestern part of the Borough,  Most of



        this area is predominately residential in character,  consisting



        of small private hones, apartment houses and some  low cost



        public housing projects.  Portions  of the Greenpoint  and



        Newtown Creek areas contain numerous light industrial estab-



        lishments*





    c.   QUEENS - The Queens portion of the  drainage area is essentially



        similar in  character to the Brooklyn portion, except  that it



        contains fewer industrial establishments and is  more  sparsely



        populated.   It covers U,036 acres of the western part of the



        Borough.





        Due consideration has been given in the design of  the treat-



        ment plant to industrial wastes in  the sewage to be treated



        from the Greenpoint and Newtown Creek areas.





3.  INTERCEPTING SEWERS



    The main intercepting sewer system, including the force main under



    the East River, has a total length of 16 3/k miles,  of which more



    than 3 miles involved tunnel construction.





    These sewers intercept the flow which was formerly discharged from



    a total of 83 outlets, of which 70 were on the East  River,  11 were



    on the Hudson River and 2 were on Newtown Creek.





    a.  MANHATTAN  - The sanitary flow from the Manhattan  drainage



        area, formerly discharged through fifty-four (5U)  sewer outlets
                           -7-

-------
    into the East River and eleven (11)  sewer outlets into  the



    Hudson River.  These flows are conveyed through two inter-



    cepting sewers that converge at a sewage pumping station on



    the east side of Manhattan*  The flow is then pumped through



    a force main tunnel under tne East River to the treatment plant



    In Brooklyn,





b.  BROOKLYN AND QUEENS  - The sanitary flow from the Brooklyn



    and Queens drainage areas formerly discharged through sixteen



    (16) sewer outlets into the East River and two (2) sewer



    outlets into Newtown Creek.  These flows are conveyed through



    two intercepting sewers which meet at a junction chamber



    located inside the treatment plant site.





    Regulators on the connecting sewers limit the flow to the



    interceptors to approximately twice the mean dry weather flow



    in the connecting sewers.  The excess flows directly to the



    receiving waterway.





    Excess capacity in the intercepting sewers permits some



    storage in the event of a power failure interrupting the



    operation of the pumping stations.





The details of the intercepting sever system of the project



will be the subject of a separate presentation.





Figure 3 (next page) shows the Drainage Plan, Intercepting Sewer



System, Force Main, and the Sites for the Treatment Plant in



Brooklyn and the Manhattan Pumping Station of the Project.
                       -8-

-------
IW^/^MiiiSre-:


                                                                                         CITY  OF NEW YORK
                                                                                   DEPARTMENT OF PUBLIC WORKS

                                                                            NEWTOWN CREEK POLLUTION CONTROL PROJECT
                                                                                       DRAINAGE  PLAN
                                                                                  INTERCEPTING SEWER  SYSTEM
                                                                               SITES FOR PLANT 8  PUMPING STATION
                                                                                           FIGURE

-------
lu POPULATION



   The contributing population is influenced by the varied character



   of the drainage area.  The Borough of Manhattan has a large non-



   resident transient and working population, whereas the Boroughs of



   Brooklyn and Queens have a relatively large industrial wastes



   contribution.





   The population for project design purposes is essentially based on



   a combination of:  (a) Resident; (b) Resident equivalent of transient



   and working population, and (c) Resident equivalent of industrial



   wastes contribution.






   a.  The ultimate resident population for the entire project drainage



       area is estimated at 1,525,000, of which Manhattan will contribute



       575,000 and Brooklyn and Queens will contribute 950,000.



   b.  The resident equivalent for the Manhattan ultimate transient



       and working population is estimated at li50,OCO (based on an



       estimated total transient and working population of 3,150,000



       with water consumption rate one seventh that of the resident



       population.)



   c.  The resident equivalent for the Brooklyn and Queens industrial



       wastes contribution is estimated at 525,000 (based on an



       estimated industrial wastes flow of 22 MGD with a suspended



       solids concentration three times that of the resident wastewater,



       which is estimated at 125 gallons per capita per day).
                           -10-

-------
    The combination of (a),  (b)  and (c)  results in an estimated



    ultimate equivalent population of 2,500,000 for the project



    design,  of which Manhattan will contribute 1,02?,000 and Brooklyn



    and Queens will contribute 1,)'.?!?,000.






5.  WASTEWATER QUANTITIES AND CHARACTERISTICS



    It was hereinbefore Indicated that the contributing population is



    influenced by the varied character of  the drainage area.  The



    same influences affect the wastewater  quantities and characteristics.





    Essentially,  the wastewater  is a combination of: (a) water consump-



    tion by  the resident population, (b) water consumption by the



    resident equivalent of transient and working population, (c) indus-



    trial water usage and (d) special ground water infiltration and



    seepage.  Records of water consumption as well as specific gaugings



    of sewers, pumping of seepage from large buildings and industrial



    water usage have been used for project design purposes.






    The Manhattan design average flow is estimated at 170 MGD, of which



    lli3 M.G.D. is based on an equivalent population of 1,025,000 (Section



    U) and a per capita water consumption  rate of lliO g/c/d, and 2? MGD



    is based on the special ground water infiltration and seepage from



    the Manhattan  drainage area (Section  2),





    The Brooklyn and Queens design average flow is estimated at IliO MGD,



    of which 118 MGD is based on a resident population of 950,000



    (Section h) and a per capita water consumption rate of 125 g/c/d,



    and 22 MGD is based on the special industrial wastes contribution



    from the Brooklyn and Queens drainage  area (Section 2),
                           -11-

-------
The average design flow for the entire project is the combination



of the Manhattan and Brooklyn and Queens flows, or 310 MGD»






The maximum design flow for the Manhattan area is estimated at



300 MOD, and for the Brooklyn and Queens area at 280 MOD, resulting



in a total maximum design flow of 580 MGD for the entire project.



The daily peak flow for the project design is estimated at U50 MGD.





The wastewater characteristics vary considerably within the drainage



area.  The sewage is essentially domestic in character for the



greater part of the area.  However, the contribution from the



industrialized areas of Brooklyn and Queens is highly concentrated



due to the nature of the wastes.





The project design is based on overall average wastewater values



of 200 ppm suspended solids and 200 ppm BOD for the entire drainage



area.  Total suspended solids and BOD average 517,000 dry pounds



per day, which is equivalent to 0.21 dry pounds per capita per day,



based on the design equivalent contributing population of 2,500,000,





The Manhattan Section of the drainage area is closely built up



and hence contributes relatively low amounts of grit; on the other



hand, the Brooklyn and Queens areas are more sparsely built up



and hence contribute somewhat larger amounts of grit.  Studies



indicate that an overall removal of IuO cubic feet of grit per



million gallons of average design flow for the entire project area



is adequate for design purposes; average grit capture is expected



to average 12UO cubic feet per day.  Maximum capture is assumed at
                        -12-

-------
    12 cubic  feet per million  gallons  of maximum design flow.






    Screenings removal  of 1.0  cubic  feet per million gallons of



    average flow is  considered adequate for the project design.






6.  RECEIVING WATEIWAY



    The effluent from the treatment  plant  is discharged into Class



    "11" (N.T.S.D.H.),  or Class "B"  (I.S.C.) waters in the East River



    through a 12'-On diameter  plant  outfall sewer extending from the



    plant site to the East River,  a  distance of approximately  U,500



    feet.  The outfall  is in India Street  and terminates  into  deep



    water beyond the U.S. Pierhead Line.   Diffusers are included for



    dispersion of the plant effluent into  the receiving waters.





    The plant outfall sewer is designed to discharge a maximum flow of



    U75 MGD,  consisting of a daily peak flow of U50 M3D plus 25 M3D,



    maximum of Thickener Overflow, with a  friction factor of n*.0l5,



    when the  tide in the East  River  is at  elevation /3.00.  This tide



    level is  reached on the average  about  once in two years.





    A spillway is provided to  discharge flows in excess of the hydraulic



    capacity of the plant outfall sewer into Whale Creek  Canal which



    is tributary to Newtown Creek.  During emergency operations, the



    entire maximum design flow may be discharged into Whale Creek Canal.





    Provisions are included to disinfect plant effluent  in advance of



    entry into the outfall sewer to  control the bacteriological quality



    of the effluent as  directed by regulating agencies.   Sodium
                            -13-

-------
    hypochlorite solution  diffused at  the head end of the plant



    outfall will be used for this  purpose.   The outfall has  adequate



    length for contact tine.





7.  INSCRIPTION OF TREATMENT PIANT SITE



    The treatment plant site in Brooklyn is  bounded on  the north



    by Green Street, Marginal Street and Whale Creek Canal;  on the



    east by North Henry Streetj on the south by Greenpoint Avenue,



    and on the west by Provost Street. The  area of the plant site



    is approximately 32 acres.





    The site originally was a generally open and flat area,  except



    for a few run-down structures  which were demolished in advance  of



    the new construction.   Former  low  lying  and underwater portions



    of the area were previously filled in with earth, rock,  debris, etc,



    The fill was in general placed directly  over overlying mud which



    covered much of the low areas  of the site.  Timber  bulkheads  along



    portions of Whale Creek Canal  were additional obstructions.





    Site borings indicated subsurface  ground conditions that generally



    required the use of pile foundations under the major plant



    structures.





    The site is graded to  suit the requirements of the  various plant



    structures and in conformity with  the established grades of the



    adjoining streets.





    Trees, shrubs and lawns are provided to  Rnhance the appearance  of



    the site.

-------
Ill - TREATMENT UNITS



      The treatment plant utilizes the "High Rate" Activated Sludge Process for



      the treatment of a design average flow of 310 million gallons a day from



      an equivalent contributing population of 2,500,000 persons.





      The treatment units include grit chambers, aeration tanks, sedimentation



      tanks and facilities for the hypochlorinatien of plant effluent.  These



      units are designed to achieve removals of seventy percent of the suspended



      solids and sixty percent of the B.O.D. or 362,000 dry pounds per day and



      310,000 dry pounds per day, respectively, from the wastewater.  In addition,



      the plant is expected to remove 1; cubic feet of grit and 1 cubic foot of



      screenings from each million gallons of average flow, or grit removals of



      12UO cubic feet per day and screenings removals of 310 cubic feet per day.





      The treatment plant is distinguished by its unusually compact design in



      which all major plant units are grouped into a minimum number of structures



      in order to afford economies in construction and operation costs.  In



      addition, the compact layout provides for centralized administration and



      for short connections for all major piping and conduits.  Pipe and access



      tunnels connect the Main Building to operating centers at the several



      groups of tanks*  The plant structures are of functional modern architectural



      design and are treated in such a manner as to enhance the area in which



      the plant is located.






      Housed in the Main Building are the screening chamber and pumping station



      for the Brooklyn and Queens flow in addition to facilities for power



      generation, electrical control equipment, heating and ventilation equipment,

-------
air filters and process air blowers, a shop for the servicing of plant



equipment, garage, plant administrative offices, plant laboratory, various



storage and employee utility facilities and the administrative headquarters



and laboratories for the Industrial Section of the Division of Plant



Operations,






Two Control Buildings, one for each tank battery, house the return and



excess sludge pumping stations, effluent water pumping station, chlorination



facilities for sphaerotilus control, scum handling stations, diffuser tube



cleaning facilities, electrical rooms, facilities for plant effluent



hypochlorination, storage rooms and employee utility facilities.





The combination of grit chamber, aeration tank and sedimentation tank



functions into a single tank structure, compartmented to provide for the



foregoing functions in successive chambers is unique and constitutes a



major development in the design of Water Pollution Control facilities.



Two such tank batteries are provided.  This combination of units eliminates



the need for interconnecting conduits and inlet and outlet sluice gates



and generally resulted in economies during construction.   Further economies



&re affected in operation due to concentration of structures and in pumping



power requirements made possible by minimizing hydraulic losses.





Figure U (next page)  "Plant Plot Plan & Plant Layout" shows the major



elements of the Treatment Plant.
                              -16-

-------
HBQDBSnfflBQBDP
Innnnmrolrujinq
                           CITY OF  NEW  YORK

                     DEPARTMENT OF PUBLIC  WORKS
               NEWTOWN CREEK POLLUTION CONTROL PROJECT

                       PLOT PLAN a PLANT LAYOUT

                              FIGURE  4

-------
1.  MAIN BOIUING



    The following facilities are housed in the Main Building,






a.  SCREENING CHAMBER



    Sewage from Brooklyn and Queens is discharged via a 12'-0" x



    9'-0" Intercepting Sewer into the fore bay, which consists of



    four 3'-0" wide channels with stop planks provided at the forward



    ends*  Flow continues to four £'-0" wide screen channels each



    equipped with one 36" x 108" quick closing, hydraulically operated,



    float controlled and manually reset inlet sluice gate.  The gates



    close automatically in the event of a power failure or an inflow



    of sewage in excess of the capacity of the main sewage pumps.






    Temporary racks 3'-C" wide with bars 6" on centers are located



    in the forebsy in order to safeguard against the passage of



    large objects at the start of plant operations.






    The primary bar screens are 5'-0" wide with 1" clear openings.



    Barminutors, 8'-0" wide with 3A" clear spaces between bars,



    serve as secondary screens.  Cuttings are returned to the flow



    downstream of the barminutors.






    Access to the Screening Chamber is facilitated by an automatic



    push-buttcro operated passenger elevator.





    Trash collected from the bar screens is manually sorted  and



    placed in trash cans which are transported to trucks via a
                               -18-

-------
   one ton electric hoist mounted on a monorail system.   The trash



   is disposed at municipal incinerators or at sanitary  landfills.






   After screening, the flow enters a 20'-0" wide wet well shaped



   so as to inhibit the deposition of grit.






b. MAIN SEWAGE PUMPS



   Five 70 MOD vertical, centrifugal or mixed flow type  pumps



   direct driven by electric motors, are provided to pump the



   maximum design flow of 280 MOD with one pump held in reserve.



   Three of the pumping units are variable speed driven by 800 H.P.



   wound rotor induction motors with electrical control equipment



   to regulate pump speeds and discharge rates.  The other two



   pumping units are constant speed driven by 800 w.P. synchronous



   motors.  Strained plant effluent is used as flushing water for



   the wearing rings.






   The Fain Sewage Pumps discharge into a 7'-6" maximum diameter



   welded steel force main which is provided with a flow tube for



   measuring the Brooklyn and Queens flow.  This force main joins



   a 7f-6" diameter reinforced concrete conduit outside the



   Pumping Station which in turn is connected to a conduit designed



   to convey the Manhattan flow.  The two conduits join into a single



   conduit which conveys the total flow to the grit chambers.






c. AIR FILTERS



   Two systems of air filters are provided, one to supply air to



   the engine air intake system and the other to the process air
                          -19-

-------
    system.  Engine  air is  filtered through  seven (7) banks of



    filters, each  consisting of 16 cells  of  permanent metal filter



    media and  having a capacity of 12,000 c.f.iri.  Process  air is



    filtered through six (6) banks of electrostatic  precipitators



    behind vhich are glass  filter bags. Each bank has  a capacity



    of 31,080  c.f.m.





d.  PROCESS AIR BLCWERS



    Six (6) process  air blowers are provided, each  capable of



    delivering 30,000 c.f.m. of process air at. a pressure of 7.75>



    p.s.i.g.    These are multi-stage centrifugal type, direct-



    connected to 1200 H.P. squirrel cage induction motors.  The



    blowers  provide sufficient capacity,  with one blower reserved



    as a spare, to deliver 0.66 cubic feet of air per gallon of



    sewage under aeration based on average sewage flow.  With all



    six blowers in operation the capacity is 0.79 cubic feet per



    gallon of average sewage flow under aeration.





    The  process air main has a maximum diameter of  72"; the air



    has  a velocity of ?300  ft./min. with five blowers  in  service



    and  6350  ft./min. with  six blowers in service.





    Normal process  air  requirements are not expected to exceed



    0.50 cubic  feet per gallon of average sewage flow  which



    requires  four blowers  in service.  The  installation provides



    for  all conditions  of  operation,  including shock industrial



    wastes loadings*
                         -20-

-------
e.  ENGINE - GENERATORS




    Seven (7) Engine-Generator units are provided, with a maximum



    of six (6) available for power generation and one (1) as a



    spare.  The engines are 12-cylinder, V-type, h cycle turbo-



    charged diesels capable of operating on sewage gas having a



    heat value of 600 B.T.U. per cubic foot and on Diesel fuel



    oil.  They can operate selectively as dual-fuel engines with



    any oil-gas ratio.  The engines are rated at approximately



    2800 H.F. at 327 R.P.*T.
    Seven 2500 KVA, 1A&0 volt, generators driven by the seven



    dual fuel engines supply electrical energy for the operation



    of the treatment plant.





f.  ELECTRICAL INSTALLATIONS



    A Ul60 volt, metal -clad switchgear structure has been installed



    for the switching of the following equipment:  seven generators,



    six 12£0 H.P. blower motors, three 815 H.P. variable speed main



    sewage pump motors, two 8hO H.P. constant speed, synchronous



    main sewage pump motors, two auxiliary transformers and four



    unit substation feeders.






    Control benchboards located in a central control room in the



    Fain Building provide for the control of the generators,



    blower motors and main sewage pump motors.
                          -21-

-------
        Unit substations consisting of hl60 volt disconnecting  switches,



        U160 to U80 volt transformers and U80 volt metal-clad switchgear



        have been installed for the feeding of hhO volt motor control



        centers, from which feeders extend to auxiliary plant motors,






        The office, service and control areas are illuminated with



        fluorescent lighting.  Operating areas, however,  are illuminated



        with vapor proof or explosion proof lighting.  Street lighting



        and floodlighting post-mounted units and handrail mounted units



        are provided for outdoor areas.






        An alarm annunciator has been installed in the central  control



        room to give audible and visible warning in the event of outage,



        malfunction of major installations, or the leakage or accumulation



        of combustible gases In hazardous areas.






        An automatic telephone system and a coded call system have been



        installed for interior communication.






2.  TREATMENT TANK UNITS



    a.  GRIT CHAMBERS



        Thirty-two (32) aerated t?rit chambers are provided, arranged in



        such a manner so that two errit chambers lead to each of



        sixteen (16) aeration tanks.  pacb erit chamber unit is 27'-0"



        wide, 1E>''-0" S.W.D. at average flow and 2"?'-0" long. Diffuser



        tubes are provided to supply air at a maximum rate of 6 c.f.m.



        per foot of tank length,  renter dividing walls the full length



        of the tank avoid the double spiral flow patterns that  exist



        in the aeration tanks.  A baffle wall between the grit  chambers
                              -22-

-------
    and aeration tanks is provided to minimize the carry-over of



    grit to the secondary treatment units.  A continuous hopper



    under the diffusers is provided in each grit chamber unit for



    grit storage and to permit clam-shell bucket removal.



   "Swingfuser" aerators operated by motorized power units have



    been installed for air degritting.






    The grit chambers, aeration tanks and sedimentation tank units



    are all designed for an average flow of 310 M.G.D. and a maximum



    flow of 580 M.G.D.   The hydraulic design of the Grit Chambers



    is based on a maximum flow of 60U M.O.D. which includes 2k M.G.D.



    thickener overflow, passing through 2ii grit chambers.  The



    maximum flow-through velocity is about 0.1 ft./sec.  The over-



    flow rate at maximum flow of 580 M.G.D. with 32 tanks in



    operation is 26,900 gallons/s.f./day with a detention of 6.0



    minutes.  With the average design sewage flow of 310 M.G.D. and



    32 tanks in operation, the overflow rate is lk,hOO gallons/s.f./



    day and the detention is 11.3 minutes.





    The average removal of grit is expected to be about h cu. ft.



    per M.G, or about l,2'.jO cubic feet per day.






b,  AERATION TANKS



    Sixteen (16) aeration tanks follow the grit chambers, so



    arranged that two grit chambers discharge into each aeration



    tank,  Fach tank is 55'-0" wide x 15'-0" S.W.D. at average flow



    x 200'-0" long.  The aeration tanks have a total volume of
                        -23-

-------
2,500,000 cubic feet or 18.7 million gallons.  The hydraulic



design is based on a maximum flow of 657 M.G.D. passing through



twelve (12) tanks which includes £80 M.G.D. maximum sewage flow,



US M.G.D. return sludge which enters the aerators individually



at the head of each tank, 2k M.G.D. thickener overflow and 5



M.G.D. spray water for foam control.






Air is diffused through the sewage via about 18,820 ceramic



type double air diffuser tubes located at 7^" centers along



the two longitudinal walls of each tank and attached to fixed



manifolds with disconnect fittings at the air headers.  The



double spiral flow pattern towards the center thus engendered



in each tank is aided by a bottom center ridge.





The detention period with all sixteen (16) tanks  in operation



with an average flow of 310 tt.G.D. and 2h M.G.D.  (8£ +) return



sludge is 1.3li hours.  With 16$ _+  return sludge  or 1*8 M.G.D.,



the detention period is 1.26 hours.  The detention period




based on 310 M.G.D. average flow is 1.U5 hours.





The BOD Aerator loading is equal to £17,000  dry pounds/day which



is equal to 206 dry pounds per 1000 c.f. of  Aerator capacity.



The aeration tanks  are designed to operate with sludge  ages



varying  between 0.2 and O.U day.  With  an  0.2  day sludge  age,



 the  BOD  solids loading is 10U,000  dry pounds,  which corresponds



 to 5 pounds of aerator  solids per  pound MISS.   With an O.U day



 sludge age, the BOD solids loading is 208,000 dry pounds,




 which corresponds to 2.5 pounds  of aerator solids
                              -2U-

-------
 per pound MLSS.  The return sludge  rates vary from about B%
 (2h M.G.D.)  to about 16* (U8 M.G.D.).
Aerator solids concentrations vary from about 670 p. p.m. to
about 1320 p. p.m.   Return sludge and  excess  sludge solids
concentrations vary from about 3710 p.p.m. to about 8550 p.p.m.
Excess sludge  flow to  the thickeners  normally vary from about
5,1 M.G.D.  to  about 11,7 M.G.D. when  wasting return sludge.
The maximum flow of waste sludge to the concentration tanks
when  purging the aerators is  2h M.G.D.,  based on eight
concentration  tanks in service with an  overflow rate of about
800 gallons per square foot per day.

With  three  of  the  six  installed blowers in service and average
flow  the air rate  is O.UO c.f. of air per gallon of sewage.
Normally, air  rate will not exceed 0.55 c.f. of air per gallon
of sewage,  which requires four blowers  in operation.  Higher
air rates may  be required,  however, during periods of shock
industrial  wastes  loadings  which may  occur periodically.  With
five  of the six blowers in  service an air rate of 0.66 c.f.
of air per  gallon  of sewage can be delivered, based on an
average flow.

With  three  blowers in  operation,  the  air rates at average flow
are 27 c.f.m.  per  foot of aeration tank, 169 c.f.m. per 1000
pounds BOD  loading and Ij05  c.f.  per pound BOD removed.
                    -25-

-------
    With five blowers in operation, the air rates,  at average  flow,



    are U5.1 c.f.m. per foot of aeration tank,  280 c,f.».  per



    1000 pounds BOD loading and 816 c.f. per pound BOD removed.





    A spray system utilizing strained plant effluent has been



    provided to control aerator foam or frothing.





c.  SEDIMENTATION TANKS



    The sedimentation tanks are of the same number (16) and width



    as the aeration tanks, of which they are a continuation.  Each



    tank is 55'-0" wide x 12'-0n S.W.D. x UOO'-O" long, with a



    total liquid volume of about U,200,000 c.f. (or 31.1 M.G.),  a



    total surface area of 362,000 s.f. and about 126 linear feet



    of weirs per tank at the effluent end.  The spiral flow



    pattern and ensuing turbulence in the aeration tank flow is



    inhibited before entry into the sedimentation tanks by means



    of double wall baffles with staggered openings.  Flow



    straightening vanes help provide a uniform distribution of



    flow.





    Settled sludge is scraped mechanically from each of the tanks



    to cross collecting channels located at the center of the



    tanks.  Sludge is withdrawn from sumps in the cross-collecting



    channels by hydrostatic lifts and is conveyed to wells.



    Return sludge is pumped to the head of the aeration tanks.



    Excess sludge is pumped to the concentration tanks.
                        -26-

-------
Effluent from the sedimentation tanks passes over transverse



and short longitudinal weirs at the far end of each tank at



a rate of 1?U,000 gallons per day per foot of weir, based on



310 M.3.D. average sewage flow.





Scum and grease removal is effected mechanically by skiraning



and collecting mechanisms at the head erd of the tanks and is



conveyed to scum tanks, from which it can be disposed at City



incinerators or sanitary landfills.





Stop planks and sluice gates are provided in the space between



the baffle walls at the beginning of the sedimentation tank



compartments to permit taking two aeration  tank units out of



service in each of the two tank batteries without taking the



corresponding sedimentation tank units out  of  service, when



operation at lower aerator detention periods is warranted.





With  average sewage flow of 310 K.G.D. and  sixteen sedimentation



tanks in  operation, the detention is 2.U3 hours,  the  overflow



rate  is about  880  gallons per  square foot per  day and the  sludge



underflow rate varies from  30  M.G.D. to  60  M.G.D.  The  flow-



through velocity in  the units  at average sewage  flow  plus



10£ return sludge  is  about  3-0 feet per  minute and the  vertical



 settling velocity is  about 0.09 feet per minute  (about  one



 inch per  minute).  The units  are  set so  that the average W.3.



 level is at elevation +13.0,  which allows  discharge of  a
                           -27-

-------
maximum flow of approximately li?5 M.G.D., which includes



l£0 M.G.D. (daily peak flow) of plant effluent and 25 M.G.D.



of thickener overflow, through the 12'-0" diameter outfall



sewer when the tide in the East River is at elevation +3.0



and the friction factor n» 0.01?.






Hydrostatic lifts are used for withdrawing sludge from the



sedimentation tanks.  A conduit conveys the sludge to a pump



well from which return and excess sludge is withdrawn by



centrifugal pumps.  Return sludge is pumped to the head end



of the aeration tanks and excess sludge is pumped to the



concentration tanks.  Excess sludge Quantities, when wasting



return sludge, range from about ? M.G.D. to about 12 M.G.D,



When purging the aeration tanks a maximum rate of about 2U.O



M.G.D. may be reached.  The flow to the concentration tanks



is maintained more or less constantly at 2k M.G.D. by adding



aerator effluent to the return sludge waste as required.





Plant effluent is discharged to the East River via a 12'-0"



diameter reinforced concrete outfall sewer equipped with



diff users.  An emergency spillway into Whale Creek Canal is



provided for such times when the hydraulic capacity of the



outfall sewer may be exceeded,





Disinfection of plant effluent is affected by the use of



sodium hypochlorite which is added to the flow at the head



end of the plant outfall sewer.
                    -28-

-------
         The hypochlorination equipment and storage tanks are  located



         in the Aeration Control Building.  No special contact chamber



         is required as the outfall sewer is of sufficient length to



         provide adequate contact time to affect optimum bacterial kill.





3,  SIPDGE PROCESSING FACILITIES



    a.  CONCENTRATION TANKS



        Two (2) independent excess sludge pumping stations pump  the



        excess or waste sludge to eight (8) concentration tanks.





        The concentration tanks,designed for "Dense Sludge" operation,



        are 70'-Ow diameter x 10f-0n S.W.D. reinforced concrete  tanks



        with 7'-On deep center cones and are equipped with heavy duty



        Dorr-Oliver Company thickening mechanisms of the latest  design



        for moving "dense" sludge to an annular trench in the center



        of the tank.  Thickener overflow is discharged over peripheral



        V-notched weirs into effluent troughs and is processed for



        treatment with the screened sewage.  Thickener overflow  may



        also be discharged directly to the plant outfall sewer when



        quality permits.





        Thickened sludge is removed from the concentration tanks and



        discharged through short lines to the digestion tank



        recirculation piping by positive displacement pumps located



        under the center annular sludge trench.





        A new operating technique is used which was developed in New



        York City in recent years and which indicates that substantial
                             -29-

-------
reduction In digested sludge volume to be barged to sea is



achieved by recycling up to about 50/5 of the digested sludge



through the concentration tanks.  The total solids to the



concentration tanks when this procedure is used is U75,000 dry



pounds per day, of which 362,000 dry pounds per day are raw



excess sludge solids and 113,000 dry pounds per day are



recycled digested sludge solids.





The surface area and volume of each tank (exclusive of the



bottom cone) are respectively 3,800 square feet and 38,000



cubic feet.





The eight concentration tanks have a combined design solids



loading of 11.2 Ibs./s.f./day when thickening raw excess sludge



only and 15.6 Ibs./s.f./day when thickening raw excess sludge



combined with recycled digested sludge for "Dense-Sludge"




operation.





Aerator liquor is added to the return sludge waste to maintain



liquid detention in the concentration tanks within reasonable



limits.  The maximum aerator effluent waste is 2lj M.G.D. when



purging the aerators, under which condition the overflow rate



in the concentration tanks is 780 gallons per square foot




per day.





The Sludge Volume Ratio  (SVR) ranges from about O.L day to



1.1 days with the sludge blanket contained in the  cone of



the tank bottom.  Liquid detention time  in the concentration
                     -30-

-------
    tanks at 2k M.G.D. is about 2.3 hours.  Thickened sludge


    varies from about 12% solids to about k% solids, with an


    average concentration of about &%9 in which case the flow

                                 4&O
    of thickened sludge is about && g.p.m., assuming the


    recycling of digested sludge.



    The concentration tanks are located adjacent to the digestion

    tanks.  Galleries interconnect the units and house equipment


    and piping.  The tanks are arranged and piped to permit inde-


    pendent operation of two concentration tanks to one digestion


    tank, or any combination of units which may result in improved


    efficiency.



b.  DIGESTION TANKS


    Thickened raw sludge from the concentration tanks is digested


    in six (6) 80'-0" diameter x U2'-0" S.W.D. "High Rate" sludge


    digestion tanks equipped with fixed steel covers having a


    total liquid capacity of approximately 1,270,000 cubic feet.


    These tanks provide about one half cubic foot of tank


    capacity per capita of design equivalent contributing population.



    All six (6) tanks have been equipped with four mechanical


    mixers and have been designed as primary digesters.  Operation


    utilizing stage digestion is not provided for as such. However,


    two of the tanks are capable of dual operation to act as either


    primary or secondary (gas extractor) digesters.  Accordingly,


    the two dual-operation tanks were constructed with inverts


    three feet lower than the rest in order to provide for


    gravity flow when operating as secondary tanks*
                        -31-

-------
The average daily design input of raw excess sludge to the
                         &j3,£>c>p
digestion tanks is about 333ZJ&S38Lgallons.  The daily solids

input is about 362,000 dry pounds per day of raw sludge

solids and 113,000 dry pounds per day of recycled digested

sludge solids, for a total of U75,000 dry pounds of solids

per day, of which 1$% of the raw sludge solids is volatile

solids.  The volatile solids destruction is assumed to be

5056 or 136,000 dry pounds per day, thus leaving a remainder

of 226,000 dry pounds per day of solids in the digested

sludge.  The detention time utilizing all 6 tanks is 17.6

days, with the raw sludge having an  8% solids concentration.

With 6 tanks in operation, the volatile solids added will be

6.L dry pounds/c.f./month.


The solids concentration of the sludge barged to sea is 1.6%

when recycling digested sludge to the concentration tanks.

Otherwise the solids concentration is about 5,C#.  The average

quantity of digested sludge barged to sea is 356,000 gallons

per day when recycling digested sludge and otherwise  ^U3,000

gallons per day.


Raw and recycled digested sludge is  discharged to  each digester

through an influent pipe extending to the middle of the tank

and outletting six feet below the liquid level, or through any

of the four dovn-draft tube mixers in each tank.   Separate

external sludge heaters and circxtlating heating pumping units

are provided for the six tanks.  Sufficient heat is provided
                     -32-

-------
for the maintenance of a 95° F temperature level,  the influent



sludge having a temperature of about $0° F.






Each digestion tank is equipped with four "downdraft" tube



mixers of 7,£00 g.p.m. capacity which are capable of turning



the entire tank contents over once every half hour.  Scum



accumulation and foaming is inhibited by this design.






Sludge gas is withdrawn from the six Digestion Tanks at a



normal rate varying from about 2,000,000 cu. ft./day to



3,000,000 cu. ft./day, with an average of about 2,500,000



cu. ft./day or about 1.0 cu. ft. per capita per day.  About



90% of the gas is expected to be produced in the four "High-



Rate" tanks and about 10$ in the two secondary tanks (gas-



extractors).  The average quantity of gas withdrawn from



one of the four "High-Rate" tanks is about 563,000 cu. ft./day.



Gas piping in all tanks is sized to permit withdrawal at



hourly rates up to 2ig times the maximum expected average rate.



Excess gas not used by the engines or boilers is stored in



a 300,000 cubic foot capacity Wiggins type gas holder.  Excess



gas will be burned by four (U) waste gas burners, each having



a capacity of 20,000 cubic feet of gas per hour.






SLUDGE STORAGE TANKS



Digested sludge is stored in two 80»-0" Dia. x 21«-0" ewd x



12'-0" cone sludge storage tanks located on the plant site



and similarly sized sludge storage tank located at the East



River, at which location a dock is provided to accommodate
                    -33-

-------
sludge vessels which barge the digested sludge to sea for



disposal.  A 16" sludge line conveys the sludge from the plait



to the loading dock and adjacent storage tank.  An emergency



sludge loading facility is provided near the plant on Whale



Creek Canal.
                     -3U-

-------
IV.  MANHATTAN FDMPING STATION



     Sewage from the Manhattan portion of the drainage area is conveyed via



     an interceptor sewer system to a pumping station located at East  13th



     Street and Avenue "D".  This structure, presently still under construction,



     is expected to be completed in 1968.  Hydraulic design and treatment



     statistics presented in this paper are predicated on this facility



     being in operation.





     An average flow of 170 M.G.B. from the Manhattan drainage area will be



     discharged into the forebay of the Manhattan Pumping Station ahead of



     the Screening Chamber.  The forebay consists of an expanding section



     leading to four 3'-6" wide channels with stop planks provided at the



     forward ends.





     The Screening Chamber consists of four 5'-6" wide screen channels with



     one U2" x 108" quick closing hydraulically operated, float controlled,



     manually reset inlet sluice gate located in each channel.  The gates



     will close automatically to protect the chamber against flooding which



     might occur during a power failure or during an inflow of sewage beyond



     the capacity of the sewage pumps.  One 66" x 108" hydraulically operated



     manually controlled sluice gate is provided at the discharge end of



     each screen channel.





     Three sets of screens are provided in each of the channels ahead of



     the main sewage pumps.  These include temporary hand cleaned coarse



     racks and primary and secondary bar screens.  The temporary racks are



     3'-6" wide with bars 6" on centers and are located in the foi-ebay in



     order to prevent the passage of large objects into the pumping station



     during start of operations.

-------
The primary bar screens are 5'-6" wide with 1^" openings and the secondary



bar screens are £'-6" wide with 3/U" openings.  The screenings handling



system will be the first planned attempt to mechanize screenings handling.



Previous designs have proven to be expensive and sloppy, with extremely



high labor operating cost.  Longitudinal and transverse conveyors are



provided, with reversible operation.  Screenings handling and conveyance



is mechanized to afford efficiency in this phase of the operation, with



the screens, skip hoist and horizontal conveyors automatically operated



by pneumatic and other controls.  Sorted screenings are containerized to



facilitate trucking to disposal at municipal incinerators.





After screening, the Manhattan sewage will flow into a wet well suitably



shaped to prevent grit deposition.  The main sewage pumps will draw



suction from the wet well and will discharge into a welded steel force



main with a maximum diameter of 8'-6" located  inside the pumping station.



A flow tube is provided in this line to measure the flow.  Readings



will be transmitted to the treatment plant via leased telephone wires.





The Manhattan flow is expected to range from a maximum of 300 M.d.D. to



a minimum of 90 K.G.D. with an average of 170  M.G.D.  Five 100 M.O.D.



pumps of the vertical centrifugal or mixed flow type with variable



speed, direct driven by five  l£00 F.P. wound rotor induction  motors, are



provided.  These pumps are designed to operate under a head of 75 feet.



Utility purchased electrical  energy is to be obtained from a  217/h60



volt 3 phase, h wire distribution bus erected  by the Consolidated



Edison Company.  The bus  is to be supplied by  four 2000 KVA transformers



installed under the  sidewalk  along Avenue D.   Each transformer will be
                               -36-

-------
connected to a separate high voltage feeder.





A 30'-0" diameter surge tank located over the downtake shaft in



Manhattan is provided to eliminate surges and protect the force main



against undue pressures in the event of a power failure at the Manhattan



Pumping Station which would instantaneously stop the main sewage pumps.



The surge tank is designed so as to maintain continuously complete



submergence of the force main, especially during the initial drawdown



and forward surge.





The 8'-6" down take shaft of the force main tunnel to the Treatment Plant



in Brooklyn is located directly under the surge tank and descends to



more than 300 feet below grade.  The rock tunnel passes more than 300



feet beneath the East River to Brooklyn.  The uptake shaft, at the plant



site, is ?'-6" diameter.  The shafts, tunnel and junctions are so



designed as to permit the passage of a cleaning mechanism to restore the



hydraulic efficiency of the conduit, if required.
                               -37-

-------
V.  PROJECT COSTS



    The Newtown Creek Water Pollution Control Project, when complete, will



    have cost approximately $167,000,000 which expense has been financed with



    New York City capital budget funds and State and Federal Assistance under



    four different programs,






    When the design of the project was initiated the only available State



    assistance program applicable was in connection with design and borings.



    In accordance with this law, New York City has received $595,000 for



    preliminary design, $1,785,000 for final design and $26l,ii27 for borings,



    for a total of $2,61a,l*27.





    The only Federal Aid program in effect when Newtown Creek's first



    construction contracts were awarded afforded the City a grant of $250,000



    in connection with only one contract, the Plant Outfall,





    It was not until 1965 that any really meaningful State and Federal Aid



    programs were legislated.  In accordance with Article 12, section 12636



    of the State Health Law and 33 U,S,C. h66 et. seq, of the Federal law,



    New York City has contracted for an additional $38,596,507 in aid in



    connection with this project, on a "pickup" basis for contracts in



    progress or not awarded as of May 12, 1965,  Accordingly, about $12U,000,000



    of Mew York City capital funds will have been spent on the Newtown Creek



    project with approxlmately $39,000,000 being financed with State and



    7edferal Aid.  Stated differently, the City will have paid almost 76$ of



    trie total cost of the project, with the State and Federal Governments




    payin? 2k?,
                                     -38-

-------
The design of the Newtown Creek Project was done entirely by the



engineering staff of the Division of Plant Design, Bureau of Water



Pollution Control of the Department of Public Works,  The estimated



$6,U28,000 design costs, which include overhead and fringe benefit



costs, represents only about U.I per cent of the total construction



cost.





A carefully prepared design has kept the cost of change order work



well below the magnitude and cost levels which were expected for this



project, and most of these change orders were issued for the purpose



of making design improvements or were in connection with unforseen and



unforseeable subsurface conditions encountered by the contractors.





Figure 5 (next page) shows a breakdown of costs for the Newtown Creek



Water Pollution Control Project.
                                 -39-

-------
                  FIGURE 5
NEWTOWN CREEK WATER POLLUTION CONTROL PROJECT
                PROJECT COST
                                                     Estimated Add'l
Contract
NO.
A.
1.
1A.
2A. and B
2C.
3.
1*.

5.
6.
XM.
7.
8.
9.
Description
Property Fence
Borings F.M, (East River
Morgan Avenue Intercepting Sewer
Sec. in Johnson Avenue
Kent Avenue Intercepting Sewer
Kent Avenue Intercepting Sewer
North Branch Intercepting Sewer
South Branch Int. Sewer East Side
South Branch Intercepting Sewer
Battery Park Underpass
South Branch Int. Sewer West Side
Plant Outfall
Sewer Under Brooklyn Crosstown
Manhattan Avenue and India Street
Plant - Structures and Equipment
Plant - Plumbing
Plant - Heating and Ventilating
Bid Price
$ 8,699.60
70,221.00
10, 3U6, 260.00
„—
5,098,881.00
7,152,555.00
19,l8l,99l*.50
21,939,520.00
761*, 879 .00
6,356,1*68.00
5,113,907.00
39U, 700.00
1*2,870,850.00
1,11*7,000.00
880,000.00
Change in Cost
to 3/67
$ 	
+ 52,760.60

+ 90,279.03
+ 233,831.57
+ 370,190.10
+ 1,005,91*3.77

+ 378,852.31
+ 352,035.21*
—-. „
+ 288,595.31
+ 1,250.00
+ 1*2, 893. Ul
Cost Subsequent
to 3/67
Ip *•••••*»
	
1,000,000.00
—

500,000.00
1,500,000.00

—
—
- — .
350,000.00
1,000.00
200,000.00
Estimated
Total Cost
$ 8,699.60
70,221.00
10,399,020,60
1,000,000.00
5,189,160.03
7,386,386.57
20,052,181*.60
2l*,l*tf,l*63.77
76U,879.00
6,735,320.31
5,1*65,91*2.21*
39U, 700.00
1*3,509,10*5.31
1,11*9,250.00
1,122,893. la

-------
                                   FIODHE  £ ( CONTINUED )
                                                                             Estimated Add'l
Contract
NO.
10.
11.
12.
13.
H».
15.
16.
17.
18.
19.
20.
21.

Description
Plant - Electrical Work
Manhattan Pumping Station
Structures and Equipment
Manhattan Pumping Station
Plumbing
Manhattan Pumping Station
Heating and Ventilating
Manhattan Pumping Station
Electrical Work
Force Main
Sludge Line, Storage Tank & Dock
Structures and Equipment
Sludge Line, Storage Tank & Dock
Plumbing
Sludge Line, Storage Tank & Dock
Heating and Ventilating
Sludge Line, Storage Tank & Dock
Electrical
Furniture and Equipment
"Newtoun Creek"
New Sludge Vessel
TOTALS (CONSTRUCTION)
DESIGN (INCL. ADMINISTRATION)
SUPERVISION OF CONSTRUCTION (EST. )
Bid Price
$ 3,88U,000.00
8,Ui2, 130.00
83,986.00
113,UiO.OO
938,000.00
6,U63,9U9.75
3,059,666.00
38,250.00
89,900.00
59,887.00
32U,000.00

3,837,000.00
$lU8,660,lli3.85
Change in Cost
to 3/67
$+ 16,18U.U7
0
0
0
0
- 575,U60.53
+ 89,320.31
0
0
0
0

0
$+2,3U6,675.59
Cost Subsequent
to 3/67
$ 100,000.00
500,000.00
5,000.00
10,000.00
30,000.00
—
5,000.00
750.00
1,500.00
1,000.00
0

50,000.00
$ l4,25k, 250.00
Estimated
Total Cost
$ U,000,l8luU7
8,91*2, 130.00
88,991.00
123,Ul40.00
968,000.00
5,888,W9.22
3,153,986.31
39,000.00
91,liOO.OO
60,887.00
32ii,000.00

3,887,000.00
$155, 261,069. Ui
6,U28, 1*86.62
5!265*382.06
TOTAL PHOJECT COST
$166,95U,938.12

-------
                            ACKNOWLEDGEMENTS



     The Newtown Creek Water Pollution Control Project was designed and



construction was supervised by personnel of the Department of Public Works,



presently under Commissioner Eugene E. Hult and Deputy Commissioner and



General Manager Frederic A. Davidson, Jr,  The project was under the



direct supervision of the Bureau of Water Pollution Control under Director,



Martin Lang, Deputy Director, Joseph Cunetta and former Directors, R,H. Gould,



W.A. O'Leary and S.W. Steffensen.

-------