EPA-650/2-73-048c
December  1973
Environmental  Protection Technology  Series
                                                              ^.:.:.v
                                    :;:||||^

                                                                                 111
                                                                                 if;

                                                                                 lii
    	>•:£:*;""'



                                            111
                                                         '.v.v.v.v. *.v.*.v.v.
                                                                                 I
                                                                                 >X'X*X
                                                                                 il

                                                     |||ji||||i;||||^|ii||||||;^i^



-------
                                  EPA-650/2-73-048c
        EVALUATION

OF THE  FLUIDIZED-BED

COMBUSTION  PROCESS

           VOLUME III -
     PRESSURIZED FLUIDIZED-BED
BOILER DEVELOPMENT  PLANT DESIGN
                by
   D.L. Keairns, D.H. Archer, E.J. Vidt,
           and E.F. Sverdrup

    Westinghouse Research Laboratories
     Pittsburgh, Pennsylvania 15235
        Contract No.  68-02-0217
          ROAP No. 21ADB-09
       Program Element No.  1AB013

     EPA Project Officer:  P.P. Turner

       Control Systems Laboratory
  National Environmental Research Center
Research Triangle Park, North Carolina 27711
            Prepared for

    OFFICE OF RESEARCH AND DEVELOPMENT
   U.S. ENVIRONMENTAL PROTECTION AGENCY
        WASHINGTON, D.C.  20460

            December 1973

-------
This report has been reviewed by the Environmental Protection Agency and




approved for publication.  Approval does not signify that the contents




necessarily reflect the views and policies of the Agency, nor does




mention of trade names or commercial products constitute endorsement




or recommendation for use.
                                 11

-------
                            ACKNOWLEDGMENTS

          The results, conclusions, and recommendations presented in
this volume represent the combined work and thought of many persons at
Westinghouse and the Office of Research and Development (ORD).   Westinghouse
subcontracted Foster Wheeler Corporation to prepare the preliminary design
package.
          In particular, we want here to express our high regard for and
acknowledge the contribution of Westinghouse personnel and the  personnel
at ORD who conceived the overall fluidized bed combustion boiler effort
and who. have defined, monitored, and supported the efforts of Westinghouse
and others on the program.  Mr. P. P. Turner, Chief of the Advanced Process
Section, has served as EPA project officer on our work.  Numerous enlight-
ening and helpful discussions have been held with Mr. Turner; with section
members D. Bruce Henschel and Sam Rakes; and with R. P. Hangebrauck,
Chief of the Demonstration Projects Branch.  Personnel from the Westinghouse
Research Laboratories have made significant contributions.  Dr. W. C.  Yang,
Mr. J. R. Hamm and Dr. R. W. Hornbeck participated in the development  plant
design and evaluation.  Mr. P. J. Hopkins, Turbine and Generator Division,
Westinghouse Canada Limited, performed an investigation into turbine
suitability for the development plant.  Mr. G. S. Howard and Mr. W. F. Stahl
of the Westinghouse Gas Turbine Systems Divisions participated  in the
evaluation of the gas-turbine test facility.  Mr. L. W. Zahnstecher,
Foster Wheeler Corporation, served as project manager for preparation  of
the preliminary design.  Foster Wheeler personnel made significant
contributions through their expertise in boiler design.
          We gratefully acknowledge the work of our secretary,  Ms. Sylvia
Nalepa.  We are also grateful to Ms. Nancy Berkowitz who coordinated
the final editing and production work and to Ms.  Deborah Conrad for
typing the editorial material.

-------
                                PREFACE

          The Office of Research and Development (ORD) of the United
States Environmental Protection Agency (EPA) has organized and is sponsoring
a fluidized bed fuel processing program.  Its purpose is to develop and
demonstrate new methods for utilizing fossil fuels — particularly
coal and oil — in utility power plants.  These methods should:
     •  Meet environmental goals for S00, NO , ash, smoke emissions,
                                       £m    X
        and wastes
     •  Compete economically vith alternative means for meeting
        these abatement goals.

          Westinghouse Research, under contract to the Office of Research
and Development (ORD) of the Environmental Protection Agency (EPA), is
carrying out a study to evaluate and develop fluidized bed combustion
and oil gasification in air pollution abatement.  The goals of this work
are:
     •  To identify which fluidized processes might be economically
        employed in utility power plants or industrial boilers to
        reduce SO., particulate, and NO  emissions
                 &                     X
     •  To assist in planning and implementing a program to
        develop the fluidized bed systems deemed effective in
        air pollution control and economical in steam/power production.

          Tasks in the evaluation of fluidized bed combustion set forth
by EPA which have been completed at Westinghouse under a previous
contract are:
     •  To search the technical and patent literature in fluidized
        bed combustion, to canvass commercial organizations with
        expertise pertaining to this field, and to survey the
        market for industrial boilers and utility power systems

-------
     •  To design a fluidized bed industrial boiler and two
        fluidized bed utility power systems — one 300 MW
        capacity, the other 600 MW; and to provide performance
        and cost projections for the equipment designed
     •  To provide technical consultation and assistance on the
        ORD fluidized bed fuel processing program, including both
        combustion and gasification
     •  To conceptualize a development plant which will prove the
        configurational or operating features of the fluidized
        bed boiler designs not confirmed by prior art or experience
     •  To assess the effectiveness and economics of an
        atmospheric-pressure, fluidized bed oil gasification-
        combustion system and to aid in planning for a demonstration
        installation of such a system.

          The results of these surveys, designs, evaluations, and
comparisons were published in a three-volume report, "Evaluation of
the Fluidized Bed Combustion Process," in November 1971 under contract
No. CPA 70-9.
          These results provided the basis for the work performed from
July 1971 to May 1973 which is described in this four-volume report.
Tasks in the evaluation of the fluidized bed combustion process set
forth by EPA under contract 68-02-0217 have focused on the development
of pressurized fluidized bed combustion for power generation and
fluidized bed oil gasification for power generation.   These tasks have
included:
     •  Extensive process evaluation studies of the pressurized
        fluidized bed combustion system for power generation.
        These investigations predict the sensitivity of operating
        and design parameters selected for the base power plant
        design on plant economics; provide additional experimental
                                   vi

-------
 data  on  sulfur  removal  and  sorbent regeneration using
 limestones  and  dolomites; project economics and performance
 for various sulfur  removal  systems, both regenerative/sulfur
 recovery and once-through sorbent; establish a plant operation
 and control philosophy  and  evaluate alternative pressurized
 fluid bed combustion  concepts, both economic  and performance.
 Preparation of  preliminary  plans and a cost estimate for a
 30 MW (equivalent)  pressurized fluidized bed combustion
 boiler development  plant.   The design provides sufficient
 detail to locate a  suitable plant site and to obtain a fixed
 cost  bid for the preparation of detailed plans.  The plant
 will  provide the capability to study effectively the
 remaining technical problems to achieve the greatest
 potential for reducing  emissions and to achieve economical
 power generation.
 Identification  of a project 'team to demonstrate fluidized
 bed oil  gasification/desulfurization for power generation.
 A cooperating utility — New England Electric System (NEES) —
 has been identified to  carry out a 50 MW demonstration
 plant program.  Further process evaluation has been
 carried  out  and experimental data obtained on sulfur
 removal  and  spent stone disposal.
 Evaluation  of pressurized oil gasification for combined
 cycle power  generation.  Oil gasification process concepts
 and options  have been reviewed, material and energy balances
 projected,  performance  projected, and capital and energy
 costs estimated.
 Provision of technical  consultation and assistance on the
 ORD fluidized bed fuel  processing program,  including both
 combustion and  gasification processes.   Technical and
 economic comparisons have been carried out on various
 fluidized bed fuel processing systems and various conventional
means of steam/power generation.
                         vii

-------
          This volume (Volume III) contains the preliminary design of a
30 MW (equivalent) pressurized fluid bed boiler development plant.
The design basis, design details, cost estimate, experimental program,
and recommendations and alternatives for commercializing the process
are presented.  Volumes I and II contain the pressurized fluid bed
combustion process evaluation studie's.  Volume IV presents the work on
fluidized bed oil gasification/desulfurization.
                                 viii

-------
                              VOLUME III
         PRESSURIZED FLUID BED BOILER DEVELOPMENT PLANT DESIGN

                           TABLE OF CONTENTS
                                                                    Page
1.  SUMMARY                                                           1
2.  INTRODUCTION                                                      3
3.  BACKGROUND INFORMATION                                            7
4.  DEVELOPMENT PLANT DESIGN                                         17
    4.1    Design Basis                                              19
    4.2    Flow Diagram                                              22
    4.3    Material and Energy Balance                               22
    4.4    Boiler Module Design                                      22
    4.5    Auxiliary Equipment                                       38
           4.5.1   Dolomite and Coal Preparation and Feed            33
           4.5.2   Water and Steam Supply                            39
           4.5.3   Dolomite and Ash Disposal                         40
           4.5.4   Steam Disposal                                    40
           4.5.5   Particulate Removal                               4Q
           4.5.6   Combustion Gas Disposal                           40
    4.6    Gas-Turbine Test Facility                                 41
           4.6.1   Test Turbine                                      43
           4.6.2   Stationary Test Passages                           45
           4.6.3   Test Rig - Required Engineering                    43
    4.7    Regeneration/Sulfur Recovery                              50
    4.8    Instrumentation and Control                               50
                                                                    52
    4.9    Perspective View
    4.10   Plant Model                                               5g
5.  EXPERIMENTAL PROGRAM                                             59
6.  COST ESTIMATE                                                    63
7.  IMPLEMENTATION                                                   65
8.  REFERENCES
    APPENDIX:  Pressurized Fluid Bed Boiler Development
               Plant Designs and Estimates
                                  IX

-------
                             LIST OF TABLES
                                                                    Page
 1.  Pressurized Fluidized Bed Boiler Apparatus                        15
 2.  Design Basis for Pressurized Fluidized  Bed  Boiler                 21
     Development Plant
 3.  Material Balance                                                 35
 4.  Material Balance                                                 36
 5.  Heat Balance                                                     37
 6.  Survey of Gas Turbines for Development  Plant                      44
 7.  Comparison of Test Turbines for Fluidized Bed  Combustion         45
     Process Development Plant
 8.  Approximate Cost of Rotating Test Rig Based on Solar              49
     Recuperative Centaur Engine
 9.  Cost of Two Test Passages                                        49
10.  Operation of the Pressurized Fluidized  Bed  Combustion             62
     Boiler Development Plant
11.  Capital Cost                                                     63
12.  Demonstration of Boiler Concept                                  67
13.  Demonstration of Plant Concept                                    68
                                    xi

-------
                             LIST OF FIGURES
                                                                     Page
 1.  Pressurized Fluidized Bed Boiler Power Plant                      8
 2.  Pressurized Fluidized Bed Steam Generator for Combined           10
     Cycle Plant
 3.  Process Flow Diagram:  Pressurized Fluidized Bed Boiler          23
 4.  Engineering Flow Diagram:  Proposed Coal Preparation and         25
     Injection System
 5.  Engineering Flow Diagram:  Pressurized Fluidized Bed Boiler      27
 6.  Engineering Flow Diagram:  Spent Solids Letdown and Turbine      29
     Test Rigs
 7.  Pressurized Fluidized Bed Boiler                                 31
 8.  Boiler Section and Details                                       33
 9.  Gas Turbine Erosion and Corrosion Test Facility                  42
10.  Pressurized Fluidized Boiler Plant                               53
11.  30 MW Pressurized Fluid Bed Boiler Demonstration Facility        56
12.  30 MW Pressurized Fluid Bed Boiler Cutaway                       57
13.  Pressurized Fluid Bed Boiler Combined Gas- and Steam-Turbine     66
     Power Plant
                                   xiii

-------
               TABLE OF CONTENTS
                   Volume I
      FLUIDIZED BED BOILER COMBINED CYCLE
            POWER PLANT DEVELOPMENT
                   Volume II
            APPENDICES TO VOLUME I
                   Volume IV
FLUIDIZED BED OIL GASIFICATION/DESULFURIZATION
                      xv

-------
                               VOLUME I
    PRESSURIZED FLUID BED COMBUSTION PROCESS DEVELOPMENT EVALUATION
                                                                         Page
1.  SUMMARY                                                                1
    1.1    Economic Comparison                                             8
    1.2    Environmental Impact                                           11
    1.3    Energy Resources                                               11
    1.4    Technical Uncertainties                                        11
    1.5    Development Status                                             13
    1.6    Comparison with Alternative Technology                         16
2.  ECONOMIC SENSITIVITY                                                  17
    2.1    Basis for Sensitivity Analysis                                 18
    2.2    Operating Conditions                                           28
           2.2.1   Bed Temperature                                        28
           2.2.2   Fluidizing Velocity                                    34
           2.2.3   Excess Air                                             44
           2.2.4   Operating Pressure                                     51
    2.3    Boiler Design                                                  53
           2.3.1   Heat Transfer Surface Configuration                    53
           2.3.2   Heat Transfer Coefficient                               68
           2.3.3   Tube Materials                                         75
           2.3.4   Module Capacity                                        75
    2.4    Particulate Removal System Economics                            78
           2.4.1   Range of Dust Loading and  Particle  Size Distribution    78
           2:4.2   Gas-Turbine Specifications                             78
           2.4.3   Effect of Dust Loading and Particle Size on Cost        82
           2.4.4   Effect of Gas Flow Rate  on Cost                         85
    2.5    Power Plant                                                    93
           2.5.1   Gas-Turbine Inlet  Temperature                           93
           2.5.2   Steam Temperature                                       97
    2.6    Assessment                                                      97
    2.7    Conclusions                                                   101

                                  xvii

-------
                                                                         Page
3.   LABORATORY SUPPORT STUDIES                                           103
    3.1    Introduction                                                  103
    3.2    Apparatus                                                     106
           3.2.1   Modification of  the TG Apparatus                       108
           3.2.2   Operation                                             110
           3.2.3   System Performance                                    113
    3.3    Process Variables                                             114
    3.4    Previous Laboratory Studies                                    ^
    3.5    Summary of the Results                                         116
           3.5.1   Pressure                                              116
           3.5.2   Sulfur Dioxide Concentration                           117
           3.5.3   Temperature                                           117
           3.5.4   Agreement with Previously Reported Data                117
           3.5.5   Stone Type                                            117
           3.5.6   Particle Size                                         119
           3.5.7   Oxygen Concentration                                   119
           3.5.8   Stone Pretreatment                                    119
    3.6    Experimental Program                                          119
           3.6.1   Sulfation of Dolomites                                 119
           3.6.2   Atmospheric Pressure Tests                             122
           3.6.3   Dolomite 1337 at  10 Atmospheres                        128
           3.6.4   Sulfation of  Tymochtee Dolomite at 10 Atmospheres      130
           3.6.5   Effect of Low Sulfur Dioxide Levels                    130
    3.7    Theory                                                         136
    3.8    Kinetics of Dolomite Sulfation                                 137
    3.9    Qualitative Comparison with Fluidized Bed Results              139
    3.10    Quantitative Comparison with Fluidized Bed Results             142
    3.11    Comparison of NCB Data and Westinghouse Data                   144
    3.12    Regeneration                                                  147
    3.13    Previous Regeneration Studies                                  148
    3.14    Conclusions from the Regeneration Experiments                  150
    3.15    Two-step Regeneration Experiments                              151
    3.16    Exploratory Runs                                              157
                                 xviii

-------
                                                                      Page
3.17   Tests with Powdered Calcium Sulfide                            157
3.18   Tests with Sulfided Dolomite                                   158
3.19   Current and Future Experiments                                 160
3.20   Conclusions                                                    163
REGENERATION SYSTEMS ASSESSMENT                                       165
4.1    Introduction and Scope of Investigation                        165
4.2    Regeneration Process Concepts                                  166
       4.2.1   One-Step High-Pressure and Low-Pressure                166
               Regeneration Concepts
       4.2.2   Two-Step Regeneration Concept                          169
       4.2.3   Constant*Load Concept                                  171
       4.2.4   Once-through Operation                                 171
       4.2.5   Wellman-Lord Stack Gas Cleaning Process                171
       4.2.6   Alternative Concepts                                   173
4.3    Process Options and Variables                                  173
4.4    Base Case Designs                                              175
4.5    Economic Results for Base Case Designs                         178
       4.5.1   Process Capital Investment                             178
       4.5.2   Plant Energy Costs                                     178
       4.5.3   Constant Load Concept Economics                        180
       4.5.4   Effects of Boiler Conditions                           180
       4.5.5   Process Cost Comparison                                185
4.6    Process Performance                                            188
       4.6.1   Plant Heat Rate                                        188
       4.6.2   Temperature Control                                    188
       4.6.3   Process Turndown                                       190
       4.6.4   Process Environmental Comparison                       191
4.7    Assessment                                                     193
       4.7.1   Economic Factors                                       193
       4.7.2   Environmental Factors                                  196
       4.7.3   Base Design Feasibility                                202
4.8    Combustion of Low-Sulfur Coals                                 208
4.9    Conclusions                                                    210
                              xix

-------
                                                                          Page
5.  PLANT OPERATION AND CONTROL                                           213
    5.1    Introduction                                                   213
           5.1.1   Plant Criteria                                         213
           5.1.2   Control System Requirements                            214
           5.1.3   Pressurized Fluid Bed Boiler Power Plant Concept       214
    5.2    Unit Start-up                                                  221
           5.2.1   Introduction                                           221
           5.2.2   First Module Start-up                                  234
           5.2.3   Second Module Start-up                                 236
           5.2.4   Third Module Start-up                                  237
           5.2.5   Regeneration System Start-up                           237
           5.2.6   Auxiliary Fuel Storage Requirements                    239
    5.3    On-Line Loading                                                239
           5.3.1   Introduction                                           239
           5.3.2   Sequential Loading                                     241
           5.3.3   Predictive Loading                                     243
           5.3.4   Rapid Loading                                          244
           5.3.5   Loading Events Diagram                                 244
           5.3.6   Dynamic Analysis                                       247
    5.4    Unit Shutdown                                                  249
           5.4.1   Introduction                                           249
           5.4.2   First Boiler Module Shutdown                           249
           5.4.3   Second Boiler Module Shutdown                          254
           5.4.4   Shutdown of Fourth Module                              255
           5.4.5   Emergency Shutdown                                     256
           5.4.6   Dolomite Sorbent Regeneration System Shutdown          258
    5.5    Trips                                                          259
    5.6    Runback, Run-ups, and Limits                                   263
    5.7    Total Plant Control System                                     264
           5.7.1   Introduction                                           264
           5.7.2   Plant Master Control System                            269
           5.7.3   Steam Turbine                                          270
           5.7.4   Boiler Feed Pumps                                      271
                                   xx

-------
                                                                          Page
           5.7.5   Gas Turbine                                             272
           5.7.6   Flash Tank                                              277
           5.7.7   Boiler Module                                           278
           5.7.8   Boiler By-pass                                          280
           5.7.9   Regeneration System                                     281
           5.7.10  Stone Feed System                                       282
           5.7.11  H-S Generator Control                                   284
           5.7.12  CaS04 Reducer Vessel                                    285
    5.8    Conclusions and Comments                                        286
           5.8.1   Conclusions                                             286
           5.8.2   Comments                                                287
6.  ALTERNATIVE PRESSURIZED FLUID BED BOILER CONCEPTS                     289
    6.1    Fluidized Bed Adiabatic Combustor Combined Cycle Power Plant   289
           6.1.1   Adiabatic Combustor Concept                            289
           6.1.2   Cycle Performance                                      290
           6.1.3   Plant Turndown                                         293
           6.1.4   Environmental Considerations                           295
           6.1.5   Fuel Processing Equipment                              295
           6.1.6   Power Plant Cost                                       300
           6.1.7   Conclusions                                            300
    6.2    Recirculating Bed Boiler Design                                310
           6.2.1   Deep Recirculating Fluidized Bed Boiler Concept        314
           6.2.2   Cold Model Studies                                     316
           6.2.3   Bed Tube Heat Transfer Coefficient                     321
           6.2.4   Conceptual Recirculating Bed Boiler Design             323
           6.2.5   Boiler Operation and Performance                       325
           6.2.6   Economics                                              330
           6.2.7   Conclusions                                            333
                                                                          335
7.  REFERENCES
                                  xx i

-------
                           VOLUME 11
          APPENDICES TO VOLUME L (PKKSSURiZED FLUID BED
         COMBUSTION PROCESS DEVELOPMENT AND EVALUATION)
ECONOMIC .SENSITIVITY
A.  Boiler Tube Specifications
B.  Effect of Operating Conditions and Boiler Design ,on
    Boiler Cost
C.  Parametric Study of Elutriation Rate from a Fluidized
    Bed Combustion Boiler
SULFUR REMOVAL
D.  Base Design — High-Pressure One-Step Process
E.  Base Design — Low-Pressure One-Step Process
F.  Base Design -- Two-Step Process
G.  Temperature Control and Process Turndown
H.  Effect of Boiler Conditions
I.  'Once-through Process
J.  Constant Load Concept
K.  Process Comparisons
L.  General Study of One-Step Process
M.  Low-Sulfur Coal
N.  Limestone Wet-Scrubber Cost
PLANT OPERATION AND CONTROL
0.  Part Load Operation
ALTERNATIVE PRESSURIZED FLUID BED BOILER CONCEPTS
P.  Recirculating Bed Boiler Studies
                               xxii

-------
                               VOLUME IV
            FLUIDIZED BED OIL GASIFICATION/DESULFURIZATION
                                                                    Page
1.  SUMMARY                                                           1
    1.1    Introduction                                               i
    1.2    Technology Assessment                                      2
    1.3    Environmental Impact                                       5
    1.4    Development                                                7
    1.5    Conclusions                                                9
2.  ATMOSPHERIC PRESSURE FLUID BED OIL GASIFICATION                  n
    2.1    Process Evaluation                                        H
           2.1.1   Gasification/Desulfurlzation Concepts             11
           2.1.2   Experimental Work                                 13
           2.1.3   Design                                            14
           2.1.4   Evaluation                                        17
    2.2    Demonstration Plant Program                               23
           2.2.1   Scope                                             23
           2.2.2   Location of Utility Partner                       27
           2.2.3   Conclusions                                       31
3.  OIL GASIFICATION FOR COMBINED CYCLE POWER GENERATION             33
    3.1    Introduction                                              33
    3.2    Process Concepts and Options                              34
           3.2.1   Gasifier Air/Fuel Ratio                           36
           3.2.2   Limestone/Dolomite Regeneration Method            37
           3.2.3   Once-through System                               37
           3.2.4   Other Options                                     39
    3.3    Process Specifications and Design Basis                   39
    3.4    Material and Energy Balances                              39
    3.5    Capital Investment Evaluation                             40
    3.6    Performance                                               45
    3.7    Comparison with Alternative Power Generation Systems       49
                                 xxiii

-------
                                                                    Page
    3.8    Shell and Texaco Pressurized Oil Gasification Processes    52
    3.9    Conclusions                                               55
4.  SUPPORT STUDIES                                                  57
    4.1    Introduction                                              57
    4.2    Sulfidation of Calcined Limestone and Dolomite            58
           4.2.1   Conclusions from this Study                       59
           4.2.2   Experimental Methods                              59
           4.2.3   Equipment Problems                                60
           4.2.4   Atmospheric Sulfidation of Tymochtee Dolomite     61
           4.2.5   Further Isothermal Experiment Results             61
           4.2.6   Calcined Dolomite 1359                            62
           4.2.7   Sulfidation at Pressure on Dolomite               64
           4.2.8   Stone Substrates                                  65
           4.2.9   Sulfidation:  Interpretation                      68
           4.2.10  Calcium Utilization                               70
           4.2.11  Fuel Gas                                          70
           4.2.12  Mass Transfer Limits                              71
           4.2.13  Comparison of TG Data and Fluidized Bed Results    72
           4.2.14  Outline of the Apparatus                          73
    4.3    Waste Disposal                                            74
           4.3.1   Conclusions from This Work                        76
           4.3.2   Previous Investigations                           77
           4.3.3   Experiments                                       78
           4.3.4   Initial Investigation                             79
           4.3.5   The Oxidation of Sulfided Dolomite                81
           4.3.6   The Oxidation of Sulfides Prepared from a         87
                   Series of Limestones
           4.3.7   The Kinetics of Oxidation                         87
           4.3.8   Summary                                           88
           4.3.9   Some Implications of the TG Study on              90
                   Calcium Sulfide Oxidation
                                 xx iv

-------
    KKFKKKNCKS
APPENDICES
    A.  Performance of the Oil Gasification Process as a Function
        of the Air/Fuel Ratio
    B.  Space Requirements and Gasifier Start-up
    C.  Evaluation of Oil Gasification Process Costs
    D.  Oil Gasifier Turndown-Variable
    E.  Presentation Document — Clean Boiler Fuel by
        Fluidized Bed Gasification/Desulfurization
    F.  Utility Prospects for Demonstration Plant
    G.  Utilities Visited
    H.  Proposed Utility Agreement
    I.  Utility Manpower Requirement
    J.  Follow-up Meeting Agenda
    K.  Letter of Intent
    L.  Invitation to Bid
    M.  Partial Oxidation Processes
    N.  Material and Energy Balances
    0.  Equipment Design
    P.  Capital Investment
    Q.  Performance and Energy Cost
    R.  Shell and Texaco Process Data
                                  XXV

-------
       CONVERSION FACTORS — ENGLISH TO METRIC UNITS
Length


Area


Volume



Mass



Pressure


Temperature


Energy

Power
English System

     in
     ft
     "3
     ft"*
     gal

     oz
     Ib
     ton

     lb/in2
     in H20

     °F
     °R

     Btu

     Btu/min
Metric Equivalent

      2.54 cm
      0.305 m

      6.45 cm2
      0.0930 in

      16.39 cm3
      28.32 1
      3.785 1

      28.35 gm
      453.6 gm
      907.2 kg

      51.70 mm Hg
      1.865 mm Hg

      1.8 (°C) + 32
      1.8 °K

      252 cal

      252 cal/min
                            xxvi

-------
                             1. SUMMARY

          A 30 MW  (equivalent) pressurized fluid bed boiler development
plant has been conceived to demonstrate pressurized fluid bed boiler
operation.  Such a plant is needed for further development of pressurized
fluid bed combustion combined cycle power plants which offer an
opportunity for minimizing sulfur dioxide, nitrogen oxide.and particulate
emissions; reducing thermal emissions; increasing overall power plant
efficiency;and producing electrical energy from fossil fuels with
reduced capital and energy costs.  The plant will provide the capability
of studying fluid  bed combustion and heat transfer, steam generation,
solids feed and handling, particulate removal, gas-turbine performance,
boiler control, and sulfur dioxide and nitrogen oxide emission control.
          Preliminary designs, cost estimates, experimental program,
schedule,and program alternatives are presented.  This document and
the support material will be used to locate a plant site, to obtain
fixed cost bids for the preparation of detailed plans,and to form a team
to implement the development plant program.   Information received from
continuing laboratory and pilot plant programs will be used to improve
the development plant design and program.
          Detailed design, construction,and  operation of this plant is
recommended for the three-year period 1974-1976 in order that a
demonstration pressurized fluid bed combustion boiler power plant can
be built and operated before the end of the  decade.  The capital cost
for the nominal plant adjacent to a power plant is estimated to be
approximately $10 million.  Operating costs  are estimated to be
between $2.4 and 3 million per year,depending on the plant site.

-------
                            2.  INTRODUCTION

          A recent technical and economic analysis for the Office of
Research and Development, EPA, has shown that power plants using
pressurized fluidized bed boilers can be built which are:
     •  Economical in capital requirements.  Estimated costs for
        such plants are 20 to 30% less than are those for conventional
        steam power plants.
     •  Efficient in operation.  Pressurized fluidized bed boiler
        plants using conventional steam technology are equal in
        overall efficiency to the best of conventional plants —
        about 38%; the use of increased steam temperatures and
        pressures and of increased combustion gas temperatures
        will increase overall plant efficiency to 46% or more.
     •  Effective in pollution abatement.  Pressurized fluidized
        bed boiler power plants meet emission requirements
        established for S0_, NO , and particulates.
                          £    X
          Pressurized fluidized bed combustor test units have and are
being operated to obtain data on sulfur removal; nitrogen oxide
minimization; particulate emissions; boiler tube materials; gas-turbine
component corrosion,  erosion,and deposition and coal feeding.  These
units include bench-scale tests and pilot plant units of ^ 1 MW
equivalent capacity.   A larger fluidized bed combustion boiler facility
is now required to demonstrate:
     •  Operation of  deep fluid beds with commercial heat transfer
        surface
     •  Operation of  multiple  beds
     •  Particulate removal system capability and  reliability
     •  Gas-turbine reliability
     •  SO,  and NO pilot plant emission results.
          *•        X

-------
          Several concepts have been considered for a demonstration
facility to extend the current program and commercialize the pressurized
fluid bed boiler concept.  The following alternatives illustrate the
options available:

     •  Demonstrate the boiler concept with a single fluid bed
        unit  (20  to 30 MW).  The plant could stand alone as a
        development plant or might be integrated with an
        existing  steam-turbine system and/or a process steam
        supply system.
     •  Demonstrate the plant concept with a multiple bed unit
        and gas turbine  (75 to 150 MW).  The plant could be a
        new integrated facility with steam-turbine power
        generation and/or process steam production, or it could
        be retrofitted on an existing steam-turbine plant.
The choice of a development/demonstration facility will depend on the
available funds,  the project team,and the location of a site.  A pre-
liminary design of one concept — a single bed development plant — has
been prepared to  provide a basic plant concept and cost data for
assembling the project team.
          A preliminary design has been prepared for a 30 MW
pressurized fluidized bed boiler development plant.  The design package
was prepared by Foster Wheeler under contract to Westinghouse.  The
boiler comprises  a single fluidized bed of 5 ft  x 7 ft rectangular
cross-section.  Bed depths of 3 to 30 feet are possible to accommodate
tubes for steam generation.  The boiler represents a single bed in a
module of a 300 MW power plant boiler.    Alternative designs
investigated include construction adjacent to a power plant and con-
struction at an independent site;  fluid bed combustor pressures of
170 psig and 320 psig; and coal feed rates from 22,000 Ib/hr and
33,000 Ib/hr.

-------
           Four  approaches  to sulfur removal were considered for the
 development plant:
     •  Once-through operation
     •  Integral boiler—regeneration—(sulfur recovery) system
     •  Two partially independent systems — boiler and
        regenerator/(sulfur recovery)
     •  Regeneration system with flexibility to evaluate
        alternative regeneration/sulfur recovery processes.
 The plant  is designed to study the once-through limestone or dolomite
 sulfur removal  system.  This is recommended for the first generation
 plant based on  the sulfur  removal system study  (Volume I) which
 weighed the energy requirements, economics, make-up stone requirements,
 and environmental parameters.  Provisions are made for a regeneration
 system to  be added at a later date.
           This  demonstration boiler plant would obtain data for the
 design, construction, and  operation of a demonstration power plant
 based on pressurized fluidized bed combustion.  The preliminary plans
 provide a  basis for detailed designs and for overall planning through
 the preparation of site requirements, program schedules, and cost
 estimates  specific for any proposed site.  The plans will be useful
 also in gathering technical ideas for the development plant and in
 focusing attention on the  technical problems which it must solve.
           The Appendix presents the plans and estimates for the plant*
The assembling of a  United States  government,  industry,  and utility team will
 required to undertake the financing, construction,  and operation of the
plant.

-------
                      3.  BACKGROUND INFORMATION

          A 635 MW pressurized fluidized bed combustion boiler power
plant has been designed.     The power cycle schematic is shown in
Figure 1.  Operating at elevated pressure, a fluidized bed combustor
requires a compressor to pressurize the air and to overcome the pressure
loss over the fluidized bed combustor.  At an operating pressure of
10 to 15 atmospheres, excess air of 10 to 15%, and fluidizing velocity  of  6  to
12 ft/sec, a depth of 8 to 15 feet is required to accommodate the heat
transfer surface in the bed; the pressure loss over the bed is thus
four to eight times as large as that over an atmospheric-pressure bed.  The
pumping energy, however, is actually less because of the greater
density of the gas at high pressure.  Energy can be recovered from the
high-temperature, high-pressure gases by passing them directly into a
gas-turbine expander, reducing their pressure to atmospheric as shown
in Figure 1.  This expansion lowers the temperature of the gases by
600 to 800°F, thereby reducing the amount of surface required to
recover heat from the combustion gases leaving the fluidized bed.  The
pressurized system can be operated at higher excess air rates.  Such
operation increases the fraction of gas-turbine power, reduces
combustible losses from the boiler, and increases the waste heat
recovery after the gas turbine.  It also results in improved plant
efficiencies.
          Several boiler systems have been built, tested,or proposed
which incorporate fluidized bed combustion.   These systems, as well as
alternative concepts, have been evaluated.   The early concepts did not
incorporate heat transfer surface or sulfur removal in the bed,and were
generally designed to burn low-grade fuels.   The heat released was
extracted from the combustion gases during their passage through a
conventional boiler.   Recent concepts and studies incorporate heat
transfer surface in the bed to achieve a more compact and efficient
design and/or remove  sulfur during the combustion process by using a
limestone bed.

-------
                Air
                  I
      Compressor
                       k
Coal
Pressurized
    Feed
Limestone
                	^
                         Sulfated
                        Limestone
                                                                                      Dwg. 6182A71
                                  Gas
                                Turbine
                                                        Electric
                                                       Generator
                                          \/
                                                     Particulate
                                                      Removal

                                                       Reheated Steam
                                                       Heat Recovery
                                                     (Boiler Feed Water)
                                                                       Steam     Electric
                                                                      Turbine   Generator
                         Fluidized
                            Bed
                           Boiler
                                                                                         Stack
                                                                Boiler Feed-
                                              Heat Recovery       Water
                                                (Flue Gas)
                                                                       . Water
                                                                    Discharge
                   Figure 1-Pressurized Fluidized Bed Boiler Power Plant

-------
          The boiler design considered most promising consists of four
modules.  The modularized design provides for a maximum of shop fabrica-
tion and standardization, and assists in meeting the turndown require-
ments for the plant.  Each module includes four primary fluidized bed
combustors, each containing a separate boiler function — one bed for
the preevaporator, two beds for the superheater, and one bed for the
reheater.  Evaporation takes place in the water walls.  All of the
boiler heat transfer surface is immersed in the beds, except for the
water walls.  There is no convection heat transfer surface since the
maximum allowable bed temperature is less than the state-of-the-art
gas-turbine temperature.  The fluidized bed combustors are stacked
vertically because of the advantages in gas circuitry, steam circuitry,
and pressure vessel design of deep beds.  Each module contains a
separate fluidized bed or carbon burn-up cell (CBC) to complete the
combustion of any carbon elutriated from the primary beds.  A separate
bed may not be required since carbon losses may be low enough in the
proposed pressurized boiler design with deep beds.  A CBC is not
envisaged if the system is operated with high excess air, which has
the attraction of increasing plant performance by increasing the fraction
of gas-turbine power.  A simplified drawing of a module is shown in
Figure 2.  The 318 MW plant module can be shop-fabricated and shipped
by rail.  The 635 MW plant module is designed to be shipped in sections,
each shop-fabricated.  The primary beds for a 318 MW plant are approximately
5 ft x 7 ft.  The bed depths are approximately 12 ft — sufficient for
the required heat transfer surface.  The carbon burn-up cell (CBC) is
approximately 2 ft x 7 ft.  The CBC contains no submerged surface in the
bed.  The submerged tube bundles are formed by vertical tube platens
or planes, each platen a continuous boiler tube in a serpentine arrange-
ment.  A platen is schematically represented in Figure 2.  The heat
transfer surface can be viewed as horizontal tubes.  The preevaporator
and reheater contain 1-1/2-inch diameter tubes; the evaporator water walls
and reheater bed contain 2-inch diameter tubes.  Details of the boiler
design and the plant layout are presented elsewhere.

-------
            Reheated Steam
            Reheatei Bed
                         T8
           Superheated Steam


            Superheater Bed
            Superheater Bed
           Pre-evapcrator Bed
            feed Water
                               I     O
                             <<"
                                CD  m
t
t


                                               110 Ft.
t
   Provision
  LforCarbon
A' Burn-up
    Cell*
 PLANT     VESSEL
 SIZE     DIAMETER.  D
320 mw      12 Ft.
635 mw      17 Ft.
                        BipHltit in iinitui uidiiiiis:
                        ncnt it, lid («I». IK >ilodlj
                 Grade Elevation
                              ELEVATION

               PRESSURIZED FLUIDIZED BED STEAM GENERATOR
                      FOR COPIED CYCLE PLANT
                           FOUR (4j REQUIRED
Figure  2  Pressurized Fluidized Bed Steam  Generator Module
                                       10
                                                                                                    RM-59131

-------
          The effectiveness and economics of a pressurized fluidized
bed boiler power plant have been evaluated.     Demonstrated SCL and
N0x reductions are adequate to meet emission standards.  Energy costs
are projected to be ^ 10% less than conventional power plants using
current power generation technology.  There is thus a large economic
margin for solving technological problems, and there is also the potential
for increasing performance and reducing costs by increasing both gas-
turbine and steam-turbine performance.
          The primary potential advantages of a fluidized bed boiler
power plant are:
     •  Reduced volume and modular construction.   Because com-
        bustion rates are more intense in fluidized beds than in
        the fire box of a pulverized fuel furnace, and because the
        heat transfer surface can be placed in the bed,
        fluidized bed boilers are more compact than conventional
        coal-fired boilers.   Pressurized boiler modules can be
        fabricated in shops  and installed at a power plant site.
        Considerable economies are possible in the fabrication
        and erection of pressurized fluidized bed combustion
        boilers.
     •  Reduced heat transfer surface requirements.   Because heat
        transfer coefficients are an order of magnitude greater
        in fluidized beds than in the fire box of a  conventional
        boiler,  less heat transfer surface is required in the
        boiler.   In a pressurized boiler,  less  heat  is extracted
        from the  combustion  gases after  they leave the fluidized
        bed because they  are cooled by expansion  in  the gas
        turbine.   Further large reductions  in heat transfer
        surface  are thus  possible.   The  heat transfer  surface in
        the  pressurized boiler is * 80%  less than  the  surface in
        a  conventional p.f.  boiler.
                                 11

-------
Reduced steam tube and turbine blade corrosion/erosion
and fouling.  Because the fluidized bed boiler operates
at a maximum combustion temperature far below that in a
conventional boiler, volatilization of alkali metal
compounds and fusion of ash is reduced or eliminated.
Sulfur and vanadium compounds are removed from the
combustion gases by the sorbent.  The corrosion/erosion
and fouling of steam tubes and turbine blades is thus
minimized.  Under these conditions, higher steam
temperatures and pressures may become economically
feasible,and greater efficiency in power generation may
be achieved.  Somewhat greater efficiencies can also be
                                               i
achieved in pressurized fluidized bed combustion by
using gas turbines with high inlet temperatures.
Reduced fuel costs and increased flexibility.  Because
fluidized beds can readily burn crushed coal (fine
grinding is not required), coal with a high ash content,
and a variety of miscellaneous combustibles (from sewage
                                            /
sludge, municipal solid wastes, paper mill liquid wastes,
and oily wastes to residual oil and natural gas), boilers
using such beds can utilize cheap fuels and a wide
variety of fuels to generate power and steam.
Reduced emissions of SO, and NO .  Because a limestone/
                       £•       X
dolomite sorbent can be utilized in a fluidized bed
combustor, SO- reductions of 90 to 95% can be economically
achieved.  The low combustion temperature at which the
bed operates minimizes the formation of NO  by fixation
                                          A
of atmospheric nitrogen.  Production of NO  by oxidation
                                          A
of nitrogen in the fuel is minimized by operating the bed
at high pressure.  Compliance with NO  emission regulations
                                     X
at atmospheric pressure will require design and/or
operating modifications to the boiler.
                          12

-------
          Several characteristics of a pressurized fluidized bed boiler
must be demonstrated:  operation of deep beds with internals, adequate
particulate removal for reliable gas-turbine operation, and sorbent
regeneration of high stone utilization to permit once-through operation.
          Pressurized fluid bed boiler apparatus and support facilities
have been operated to supply information on:
     •  Combustion and combustion efficiency
        -  C carry-over
        -  Burning above bed — C solids and gases
     •  Pollution abatement
        -  S02
           1   Removal
           •   Regeneration
              Recovery
        -  NO  reduction
        -  Particulate
              Formation, ash, and sorbent attrition
           •   Removal
     •  Heat generation and transfer
        -  Combustion in deep beds
        -  Temperature distribution
           Heat transfer coefficient distribution
     •  Reactant feed and distribution
        -  Fuel
        -  Sorbent
        -  Air
     •  Materials
        -  Steam tube
        -  Turbine blade
                                  13

-------
          This information has 'been and is being obtained on different
types of experimental apparatus and on different scales.   A summary of
available and planned pressurized fluidized bed boiler apparatus is
summarized in Table 1.
                                  14

-------
                                                           TABLE 1
                                         PRESSURIZED FLUIDIZED BED BOILER APPARATUS
Type
Location
Capacity
Diameter
Lb coal/hr
Operating Limitations
Temperature
°F
Pressure
psi
Gas Velocity
fps
Purpose
Status
Special Purpose
TG
TG
Fluid bed
Fixed bed
Cold models




Pilot Plants
Semi- batch


Semi- batch


Continuous


Semi- hatch


Westinghouse
CCNY
Argonne
Esso
Westinghouse


Esso


Argonne
Argonne

Esso
Esso

Esso


BCURA


-
- -
2 inch
1 inch
1-1/2 "x9"
4 inch

4 inch?


6 inch 60
3 inch

3 inch


5 inch
12.5 inch 480

2'x4' -x-400


2200

>2000
>2000
ambient
ambient

ambient


1900
2100

2200


2000
1700

1500


450

150
150
ambient
150

40


135
135

150


150
150

90


-


5
1-40
up to 6

up to 10





5


5
10

2


kinetic studies
on sulfur removal/
regeneration

alternative concepts
fluidization and
solids handling
fluidization and
solids handling

sulfur removal/
combustion
regeneration
regeneration
combustion/sulfur
removal
regeneration
combustion/ sulfur
removal
combustion/sulfur
removal

Development Plant



?


5'x7* nominal
22,000

2000


225


15


data for demon-
stration plant

operating

operating
operated
operating
operating




operating
operating

operating
Kov. 1972?

Jan. 1974
Jan. 1974

operated
1969-1971
1973-

preliminary
design, Dec.
1972

-------
                      4.  DEVELOPMENT PLANT DESIGN

          The pressurized fluid bed combustion boiler program at BCURA
demonstrated the feasibility of pressurized fluid bed combustion in an
    2
8 ft  combustor.  Specifically, it demonstrated:
     •  S0_ emissions of £ 0.7 lb/10  Btu
          ^                                f
     •  NO  emissions of 0.07-0.2 Ib NO-/10  Btu
          X                            it
     •  Coal feeding at 3-1/2 and 5 atmospheres
     •  Continuous operation — runs up to 350 hours
     •  No erosion or corrosion of gas-turbine blade test
        passages after 200-hour tests
     •  Particulate removal at ^ 1500°F and 5 atmospheres by cyclones
        proved adequate for turbine blade tests
     •  Adequate boiler tube materials for commercial
        applications
     •  Bed operation with horizontal tube bundle.
          Commercial boiler design operating conditions require that
the bed be operated at higher gas velocity, higher bed pressure, higher
temperature, and with a deeper bed than the BCURA unit.  A development
plant is required to investigate the design, construction, and per-
formance of the proposed boiler plant equipment system design at the
proposed operating conditions so that commercial feasibility might be
assessed.   Several features require a large plant to evaluate the
design and performance:
     •  Operation of deep beds (10 to 20 ft) with horizontal tube
        bundles and headers with aspect ratios < ^ 2.5
     •  Heat generation and temperature distributions
     •  Coal feeding requirements and sorbent distribution in a
        large bed (^ 35  ft2)
     •  Particulate control equipment performance
     •  Heat transfer surface configuration and materials
        requirements
British Coal Utilization Research Association.

                                  17

-------
     •  Gas-turbine blade materials nnd component life
     •  Disengaging height design criteria
     •  Operational techniques — start-up, shutdown, load
        follow, stability
     •  Long-term operability at design and operating conditions
     •  Fabrication, maintenance, and repair of boiler and
        auxiliary components.

The plant is also required to confirm, on larger scale, results obtained
in laboratory and bench apparatus and in pilot plants:
     •  Emissions — SO., NO, CO, C, alkali metals
     •  Combustion efficiencies
     •  Sorbent utilization
     •  Sorbent attrition
     •  Air distribution
     •  Boiler tube materials
     •  Particle carry-over and the sources.

Further, only a full-scale unit will provide solutions to the following
problems:
     •  Erosion that may occur due to full-scale tube configurations
     •  Feed point location distribution requirements for coal and
        dolomite into a full-size fluidized bed (number of feed points
        and their location)
     •  Thermal inertia effects in turndown and start-up of a full-
        scale module
     •  Physical arrangement for maintenance access (tube repair,
        coil replacement, instrument replacement, etc.)
     •  Determination of shop-fabrication methods and costs, and
        the associated shipping protection requirements

                                   18

-------
     •  Mechanical design methods suitable for tube bundle support,
        grid plate support, differential expansion of water-wall
        penetrations, etc.
     •  Investigation of tube vibration over the long span tube
        lengths only utilizable in a full-scale module
     •  Determination of field-erection methods and costs, not
        obtainable from a small-scale unit
     •  Determination of various unusual operating effects on the
        full-scale module mechanical design.  Conditions created
        by an emergency shutdown of the turboexpander or a low-flow
        surge of the centrifugal air supply compressor would be used
        to test the design adequacy of the full-scale module.
     •  Investigation of optimum space utilization and heat transfer
        surface configuration within the fluidized bed can best be
        proved out by testing alternative tube bundle designs in the
        full-scale module.

Other objectives which are being considered for the facility include:
     •  Need to test sulfur recovery system
     •  Feasibility of studying advanced concepts — higher steam
        temperature and pressure, higher gas-turbine temperatures,
        circulating beds, deeper beds (30 ft), higher pressures
     •  Feasibility of expanding to multiple bed operation.

The development plant is planned so that sufficient information can be
obtained to design, build, and operate a demonstration plant of 150 to
300 MW.  Appendix I provides the complete design, and estimates as
prepared for Westinghouse by Foster Wheeler,  Inc.

4.1  DESIGN BASIS
          The development plant design is based on the objectives outlined
for it and for the commercial plant design.   For the plant to provide
sufficient information to design,  build,  and  operate a demonstration power
plant,  the unit must be large enough to:
                                   19

-------
      ••  Test multiple point coal feeding,
      •'  Avoid untypical height/diameter ratios, with, bed' operation
      ••  Test proposed heat transfer surface configurations)
      •  Test effect of bed emissions1 on1 gas-turbine performance1.
These design characteristics, can be met by constructing a fluidized'
bed unit with a capacity equivalent to) one bed in. a 75-to- 100'-MW
       1                                                        e
module.,      The range of operating, conditions: and' design criteria
established  for the plant are summarized' in Table 2\
          The location of the plant is' an important consideration.,,
since large-  quantities of coal and- water are required' and: large- quan-
tities of steam, are p-roduced.   Several advantages, could be achieved' by
locating' the development plant on1 an' existing- power1 plant site1:;
      •  Availability of coal-handling, water preparationyandl
         solids  disposal facilities
      •'  Existing' plant would dispose of steam1
      •  Superheat and' reheat steam generation' cam be studied7 by
         using bleed stream from existirtg plant.
      ••  Utility  partnership1 would minimize1 site development and'
         development time,, and provide plant utilities- and
         maintenance facilities.
Thus,  the preferred location option would be adjacent to a
large  power  plant where  appropriate tie-ins> could be  effected1 for the
supply of utilities,  coal,, boiler feedwater,; andi saturated  steam;; and-' the
return of superheated  steam..  Such a location) would simplify and reduce
the cost of  installation of the developmental test boiler.
          If  it  is  not possible  to locate  adjacent to' a- utility,, then
it will be necessary  to  install  water purification1 equipment,  as: weil
as boiler feedwater  storage,  condensers  for steamyand1 adequate boiler
feedwater pumps.    In  addition1,,  various' auxiliaries, such' as" instrument
air,, cooling  towers, and a packaged' boiler would be required at an1
independent site.
                                   201

-------
                           TABLE 2
     DESIGN BASIS FOR PRESSURIZED FLUIDIZED BED BOILER
                      DEVELOPMENT PLANT
Coal
Sulfur Removal Sorbent
Pressure
Temperature
Gas Velocity
Bed Area
Bed Depth
Ca/S

Heat Transfer Coefficient
Particulate Carry-over
Particle Size
   Coal
   Dolomite
Site
   Air supply
   Excess air
   Air preheat
   Feedwater temperature
   Heat transfer surface
 Pittsburgh No.  8 (4.3% S)
 dolomite  (1337)
 1-20 atm
 1500-2000°F
 6-15 fps
 •». 35 ft2
 4-30 ft
 1-6 for once-through
 2-10 for regeneration
 50 Btu/hr-ft2-°F
 10-30 grains/scf

 -1/4" x 0
 -1/4" x 0 or 1/4" x 28 mesh
 existing power plant
 separate air compressor, motor drive
 > 100% capability
 to 600-850°F
 to 230-500°F
 capability for testing water
walls, preheat, evaporation,
and superheat tube bundles
                              21

-------
4.2  FLOW DIAGRAM
          Figure 3 is a simplified flow diagram of the pressurized
fluid bed combustion boiler development plant.  The plant is adjacent
to a large power plant to which it has access to provide interfaces
with the coal, water, steam, waste stone, and utilities.  Engineering
flow diagrams are shown in Figures 4, 5, and 6.

4.3  MATERIAL AND ENERGY BALANCE
          The material balance and operating conditions for the develop-
ment plant at the projected 100% load nominal design condition are
presented in Tables 3 and 4.  A heat balance for the nominal design is pre-
sented in Table 5.

4.4  BOILER MODULE DESIGN
          The pressurized fluidized bed boiler for the development
plant comprises a single bed of the four required for an 80 MW module.
The steam generator is a water-walled box formed of vertical 1-1/2 in.
tubing within a 12-ft diameter pressure shell approximately 78 feet tall
designed for 320 psig pressure.  The combustor has a rectangular cross-
section 5 ft x 7 ft.  The design of the pressurized fluid bed boiler is
shown in Figures 7 and 8.  The air distributor plate at the bottom of
the box can be raised by as much as 4 feet to vary the distance between
the base of the bed and the bottom of the horizontal steam tubes sub-
merged in the bed.  These steam tubes form sets of parallel vertical
platens of serpentine bends filling the cross section of the bed.
Three sets of platens or heat exchange bundles are provided so that
three different bed heights (and three different amounts of heat
transfer surface in the bed) can- be provided.
          Two tube bundle designs were developed.  One, shown in
Figure 7, supports the tube bundle from headers located in the high-
temperature gas pass.  Spare bundles are used to study different bed
heights.  This design minimizes the number of connections which provides
                                   22

-------
 PAGE NOT
AVAILABLE
DIGITALLY

-------
                                                                TABLE 3

                                                  MATERIAL BALANCE - NOMINAL DESIGN*
u>
In
Stream
No . Daacr
Temp.
lotion T
1 Vet coal from BL ambient
2 Sized Coal 100
3 Dolomite ambient
4 Dolomite ambient
5 Coal to R-101 ambient
6 Spent Dolomite 1600
7 Fines Discarded 1600
8 Fines Discarded 1600
9 Fines Discarded 1600
Pressure Flow
ps la lb/
Rate Particle
hr Composition Size
15 120,000b moisture 10.0 wt.X 1-1/2" x 0
VCM 36.8 wt.X
fixed carbon 45.3 wt.X
ash 7.9
Total 100.0
15 111.240b C 71. 3 wt.X 1/4" x 0
H 5.4 wt.X
0 9.3 wt.X
N 1.3 wt.X
S 4.3 wt.X
ash 8.5 wt.X
Total 100.0
15 150,000b CaC03 49.59 wt.X 1/4" x 28 mesh
MgCO, 49.36 wt.X
Inert s 1.05 wt.X
Total 100.00
15 35,728 same as Stream 3 1/4" x 28 mesh
176.4 mln. 22,000 same as Stream 2 1/4" x 0
176.4 20,979 CaS04 18.0 wt.X 1/4" x 0
CaO 39.3 wt.X
MgO 39.6 wt.X
Inerts 1.8 wt.X
ash 1.3 wt.X
Total 100.0
165 2,900 ash 60.0 wt.X
carbon 30.0 wt.X
dolomite 10.0 wt.X
Total 100.0
165 1,432 same as Stream 7
165 same as Stream 7
         ^Nominal design la Case A-l; see Appendix II.
          Flow rate based on 40 hr. operation per week.

-------
                                                                TABLE 4

                                                  MATERIAL BALANCE - NOMINAL DESIGNa
LO
CTi
Stream
No.
10



11



12
13
14






15
16
17
18
19






Temp
Description °F
Air to C-101 ambient



Air to C-103 100



Air to R-101 500
Air By-passed 500
Flue Gas from R-101 1600






Flue Caa from C-101 1600
Flue Gas to Turb. Cascade 1600
Flue Gas to Quench 1600
Quench Water 200
Flue Gas to SL-101 600






Pressure Flow Rate
ps la Ib/hr I MMSCFD
14.3 366,504 116.8



180 53.500 17.0



175 238,988 76.17
175 73,611 23.46
168 273,737 82.8






165 273,737 82.8
165 60.000 18.1
165 213,737 64.7
185 65,683 131 gpa
atm 339,420 116.1






Composition
o2
N|
H-0
£
02
N2
H^O
£
same as
same as
CO
CO2
H20
°2
N2
SO,
NO
same as
same as
same as

CO,
CO
H20
°2
»2
SO.
WT
20.6 M I
77.3 M Z
2.1 M Z
Total 100.0
21.0 M Z
79.0 M Z
nil
Total 100.0
Stream 10
Stream 10
18.3 M Z
0.2 M Z
8.5 M Z
1.7 M Z
71.2 H Z
148 ppm
198 ppm
Stream 14
Stream 14
Stream 14

11.5 H Z
0.12 M 1
42.9 M Z
1.1 M Z
44.4 M Z
92 ppm
124 ppm
Dust
Loading
ar/ACF










20.8






V3.01
M>.30
*0.30

tO. 30






               design is Case A-l;  see Appendix  II.

-------
                              TABLE 5
              HEAT BALANCE AROUND FLUIDIZED BED BOILER
                           Nominal Design
                            Datum:  77°F
Lb/Hr
Input
Dried coal 22,000
Sensible heat
LHV
Comb, air 238,988
Fresh dolomite 35,728
Fines returned 2,900
TOTAL 299,616
Output
Flue gas 273,737
Spent dolomite 20,979
Fines elutriated 4,900
Reaction heats
Reactions with dolomite
CaCOa + S02 + 1/2 02 = CaS04 + C02
CaCO, = CaO + C02
MgC03 = MgO + C02
No formation
1/2 N2 + 1/2 02 = NO
Incomplete coal combustion
CO, = C + 02
C02 = CO + 1/2 02
Heat loss
TOTAL 299,616
Temp.
°F MM Btu/Hr

77
0
275.0
500 24.98
77 0
1600 1.13
301.11

1650 119.4
1650 8.1
1650 1.9


-3.91
11.4
10.58

0.07
1.69
2.08
0.20
151.51
Heat Available for Steam Generation = 301.11 - 151.51
= 149.6 MM Btu/Hr
Nominal design is Case A-l; see Appendix II.
                                  37

-------
for convenient tube bundle removal or installation and permits a con-
tinuous tube bundle to provide superior fluidized bed hydraulics.  A
second design was conceived which contains three separate bundles which
can be stacked one above the other with three feet of crawl space
between the bundles for assembly and maintenance.  Headers are located
in the preheat air zone where temperatures are low (^ 600°F).  This
design requires extensive cutting and welding to change tube bundles
and has discontinuities in the tube bundle for deep bed operation. ,
Both designs are presented in the Appendix.
         The tube bundles can be operated as either a superheater, an
evaporator, or a preheater; or, by reducing the mass flow, as a combined
evaporator and superheater.
         The use of a refractory backed by structural steel for one or
more walls of the boiler has been considered as a means of simplifying
construction and of easing maintenance.  The water-wall construction,
however, seems to have all the advantages:
     •  Lower cost
     •  Less bulk
     •  Cheaper fabrication, less maintenance
     •  Better means of support for submerged tubes
     •  More heat exchange surface.
The,possibility of locating headers for the tube platens within the
water walls has also been considered as a means of easing the removal
and/or replacement of tube bundles.  More expensive materials and
costlier fabrication techniques would be required, but significant
savings in carrying out repairs would be realized.

4.5  AUXILIARY EQUIPMENT
4.5.1  Dolomite and Coal Preparation and Feed
         Wet coal is received in open-rail cars and in the size range
of 1-1/2 in.x 0.  The cars are unloaded over a hopper below the tracks.
                                   38

-------
The hopper feeds a conveyor to a dryer where coal is dried (from as high
as 10%) down to ^ 3% moisture.  The coal is crushed to 1/4 in. x 0 and then
conveyed to a covered silo for storage.  Coal may then be blended with
dry, crushed dolomite in the order of 10% of the coal.  The coal plus
dolomite is pressured up to boiler fluidized bed pressure, and then it
is injected into the boiler through a Petrocarb pneumatic injection
system.
         The dolomite is received dry and double-screened 1/4 in. to 28
mesh in covered rail cars.  The cars are unloaded in a closed building
into an underground hopper to prevent the picking up of moisture.  The
dolomite is elevated by conveyor to a storage silo, from where it is
either pressurized in a lock hopper and then injected into the boiler
or added to the coal for injection into the boiler.  The dolomite can
be injected above the grid.
         Spent sorbent is discharged from the bottom of the bed, a
position just above the grid, or it may be withdrawn at 24 in., 48 in.,
and 72 in.from the bottom of the tube bundle, depending upon the position of
the grid with respect to the tube bundle.

4.5.2  Water and Steam Supply
         The water and steam are assumed to be available at 2400 psig
at the capacity required by the development plant.  The water at 500°F
and under pressure would be received from the utility power company's
economizer and sent to the water walls for preheating and evaporation.
Saturated water and saturated steam from the flash drum are returned
to the utility company.   Either water or saturated steam is taken from
the utility company and sent to the fluidized bed tube bundle.  The
saturated steam is superheated to 1000°F, or the water is evaporated
in the tube bundle and returned to the utility company.
                                  39

-------
4.5.3  Dolomite and Ash Disposal
         Solids disposal is accomplished by cooling the ash plus the
spent sorbent in a water-jacketed rotary cooler to 300°F from a temperature
of 1750°F, with equipment design adequate for 2000°F.  The ash is then
conveyed to the utility's ash pile for disposal.

4.5.4  Steam Disposal
         Normally, all steam is returned to the utility.  In the case of
an independent site without a nearby utility, the steam from all sources
(flash drum, tube bundle, or water jackets) would have to be condensed,
and the condensate less the blowdown would be returned to the boiler
feedwater storage and pumped into both the developmental boiler and the
package boiler.

4.5.5  Particulate Removal
         Hot flue gas at 1600 to 1750°F and at 155 psig leaves the boiler
together with most of the ash and some dolomite, as well as a small
amount of unburned carbon.  The larger-sized solids are removed from
the hot gases in a single-stage cyclone.  Solids may be returned to
the combustion zone if the carbon loss is high, but it is believed that
the combustion zone is large enough to ensure adequate residence time
for complete reaction of the coal.  With complete combustion and negligible
solid carbon carry-over, the first-stage cyclone dust will be sent to the
cooler through lock hoppers.  The flue gas will then be sent to a final
cleanup consisting of a centrifugal or tornado-type cyclone.  Most of
the particles 5 vi and larger are removed.  If this equipment should
prove unsatisfactory for either gas-turbine or pollution control, space
is allowed for inclusion of alternative particulate removal equipment such
as sand filters or ceramic filters.

4.5.6  Combustion Gas Disposal
         Flue gases from the test cascade or from the turboexpander
will be quenched to drop the temperature.  The pressure will be lowered

                                    40

-------
 to  atmospheric, and  then  the  gas will be sent  to a stack through a
 silencer.   In  a commercial unit, extra heat recovery equipment and
 recuperators would  be  installed on  the turbine exhaust gas  to recover
 the most heat  possible from  the flue gas in order to maximize the
 thermal efficiency.

 4.6  GAS-TURBINE TEST  FACILITY
          A test  facility consisting of a rotating multistage turbine
 and  two stationary  test  passages is recommended for the development
 plant.  This test facility, used in conjunction with analytical studies,
 will allow assessment  of turbine blade erosion or deposition due to
 particulate matter and hot corrosion and/or deposition initiated by
 alkali metal compounds in the gas stream.  The multistage test turbine
 will provide information on the effects on erosion and deposition of
 temperature variations through the turbine flow path, radial pressure
 gradients,  local flows due to stage to stage interactions, and particulate
 carry-over  to  later stages. One stationary test passage,  designed with
 long particulate acceleration nozzles to obtain the high particle impact
velocities that will be typical of an electric utility gas turbine, will
be used to correlate test-turbine erosion to full-scale turbine erosion.
An additional full-scale first-stage turbine nozzle cascade will assess
damage to this  highest temperature  component.   Figure 9    is a schematic
of the test facility indicating the two stationary test passages and
the rotating test turbine.

-------
                                                                                Dwg. 621^18
                                                             Stationary Cascade of-^)
                                                             501 Stator Vanes
Hot Gas From Participate^
Removal Equipment
                                                        Solar
                                                    Recuperative
                                                      Centaur
               Figure 9:  Gas-Turbine Erosion and Corrosion Test Facility

-------
          Conditions selected for the development plant turbine must
ensure operability of a large electric utility gas turbine.   Operating
conditions must be duplicated in such a way that the potential for
condensation of volatile alkali metal compounds - sodium and potassium
chlorides and hydroxides and subsequent reaction to sulfate or molten
sulfate-chloride mixtures - can be studied.  Provision must be made to
measure the rate of deposition of any deposits.  This requires similar
gas and metal temperatures at points of corresponding pressure, and
similarity of flow conditions.  Blading must be of hot corrosion resistant
materials so "hot corrosion" attack of the test turbine will be comparable
to attack of the large turbine.  Erosion damage will be comparable if the
velocities of particulate impact with turbine components are comparable
in both magnitude and impact angle.  A number of turbines capable of
handling the gas flow available from the development plant were identified
(Table 5).  Detailed engineering comparisons were made between the turbines
shown in Table 6.

4.6.1  Test Turbine
          The recuperative version of the Solar Centaur industrial gas
turbine appears attractive for the multistage rotating test vehicle.
This machine is of the right scale for pilot plant operation.  Its gas
flow requirement (42 Ibs/sec) is less than the bed output (76 Ibs/sec)
but is sufficiently large to be useful as a demonstration of the
viability of the overall concept.  The inlet temperature of 1600°F is
acceptable for use on the fluidized bed combustion system, and the
turbine can accept the required 10 atmosphere inlet pressure.
         Corrosion resistance of the first two stages of the Solar
turbine is approximately comparable to that of a modern electric utility
gas turbine.  The third-stage stator nozzles and blades should be replaced
with those made of more hot-corrosion resistant materials such as
alloys having at least the corrosion resistance of MAR 421.
                                    43

-------
                                TABU 6
            SURVEY OF CAS TURBINES FOR DEVELOPMENT PLANT**
Coapany
Cooper Bessemer
Oe Laval
Detroit Diesel
General Electric
General Electric
General Electric
Ingersoll Rand
1-H Heavy Ind.
Lycooing
Mitsui
Nordberg
Orenda
Rolls Royce
Ruston
Ruston
Ruston
SNECMA
SOLAR
Stal-Laval
Turboneca
Turboaeca
Turboaeca
Turbo Power
and marine
Canadian ®
Gas-Turbine
Model PR
Coberra 30 6
TP350 9
501 - K 9
7LM350 6
M1402 5.9
M1502 7.0
JT-35 8.5
T64-1H1-10 12.7
T35 8.0
SB150 6.5
G-55-2 7.4
OT-C-516 4.1
Proteus 7.3
TF1200 6.5
TB3000 5.85
TB1500 4.2
THS2000 14.5
T3001 8.0
HP components 4.0
fro. GT35
Marbore IX 3.85
Marbore VI 3.72
Larzac 9.0
PT12A 7
GG12A T
H101 6.6
Ha Va/PR
38 6.3
34 3.8
31 3.5
44 7.3
39 6.6
45 6.4
31 3.7
24.5 1.9
T T
28.7 4.4
60 8.1
23.8 5.8
43.40 6.0
23.8 3.7
43.0 7.2
23.4 5.5
54 3.7
32.2 4.0
65.0 16.0
17.6 4.6
21.2 5.7
57.0 6.4
T 1
T t
124 18.8
*Source:  Sawyer's Gas Turbine Catalog for 1971
bDevelopment plant design conditions:   plant capacity - 10 to 30 MW;
 airflow, Wa - 20 to 65 Ib/sec; pressure ratio, PR - 10:1; Va/PR - 2.0 to 6.5.
                                44

-------
 PAGE NOT
AVAILABLE
DIGITALLY

-------
         The regenerative configuration of the machine provides both
compressor outlet and hot gas feed in locations that are immediately
           *
accessible.   The recuperative Centaur is virtually identical in all
important characteristics to the present production model of the
Centaur (except for the compressor outlet and hot gas inlet) and should
be reliable.
         Gas velocities relative to blading approach those of a large
electric utility gas turbine (similar to the Westinghouse 501) at the
rotor trailing edges and at the exit to the third-stage stator.  At
other locations in the turbine, however, the gas velocities are considerably
lower, typically reaching only about 50% of the Westinghouse 501 gas
velocities at blade and vane leading edges.
         If the particle velocities exactly follow the gas velocities,
the erosion rate of the Solar blading at the rotor trailing edges and
at the exit to the third-stage stator should be comparable to that in
the Westinghouse 501, while the erosion rates at the leading edges of
stator vanes and rotor blades may be as low as 6% of those at comparable
locations in the full-size machine.  Because of the rapid acceleration
of the gas passing through the stator vanes and the deacceleration in
the rotor blading, particles as small as 2 y in diameter may have too
much inertia to follow the gas flow.  An analysis  of this effect in a
full-scale electric utility turbine showed that the variations in particle
velocities lagged the variations in gas velocity.  This effect increased
with increasing particle size and resulted in particulate velocities
leaving the rotors that were significantly higher than the gas velocity.
A similar analysis of the test turbine flow path must be made to allow
the erosion data to be interpreted properly.
 Note:  In designing this facility, the turbine inlet design must be
 carefully examined to control dust concentrations presented to the
 first-stage vanes.

-------
4.6.2  Stationary Test Passages
          The fact that impact velocities cannot be duplicated in the
rotating test facility is the reason that the stationary passage
erosion tests mentioned earlier are required.  Particle acceleration
nozzles of sufficient length (# 4 ft with nozzles whose flow areas
decrease linearly with length) must be used to provide sufficient time
for particles to reach gas velocity before impacting the erosion targets.
Erosion targets must be carefully designed so that the impact angle as well
as the velocity is accurately known at the locations where erosion rates
are measured.
          First-stage stationary vane erosion/deposition can be
measured in a stationary cascade provided that full-scale vanes are
used in the passage.  Such a cascade would require about 16 Ibs of gas
for each nozzle passage used in the cascade.  The effect of cooling air-
flows on deposition and erosion could be effectively studied in this
facility.

4.6.3  Test Rig — Required Engineering
          The recuperated Solar Centaur turbine has a three-stage
turbine of which the first two stages are used to drive the axial com-
pressor.  The compressor cannot be divorced from the turbine, and the
engine must be bought as a unit which would be mounted on a bed plate
including its own lubrication and necessary control system.  The mani-
folding for the inlet and outlet to and from both the compressor and the
turbine would be part of the package, but Solar would not wish to under-
take the design of the hot gas ducting to the turbine.  They would give
advice in the load transference system to the turbine manifolding.  The
load absorption system for the power turbine, which could be either
generator or water brake, could also be supplied by Solar with the
mounting bed plate.  It would, therefore, be necessary to engineer and
supply for this engine the following:
                                  48

-------
     •  The hot gas ducting to the turbine
     •  The ducting from the axial compressor including the control
        valve gear to allow it to be operated at correct conditions
     •  The cooling arrangements for the load absorption
     •  A control link-up between the hot gas flow control and
        turbine speed to provide overspeed protection.

         Table 8 estimates the cost of the rotating test rig.  (The
costs of reblading third-stage rotors and stators have  not been included.)

                                TABLE 8
                APPROXIMATE COST OF ROTATING TEST RIG
             BASED ON SOLAR RECUPERATIVE CENTAUR ENGINE
                    (Solar-Westinghouse Estimate)

     Basic Cost of Solar Regenerative Gas Turbine       $300,000
     including Generator or Water Brake, Bed
     Plates,  Manifolding, Lubrication and Controls
     Inlet and Exhaust Ducting for Axial Compressor       15,000
     and Control Valves
     Exhaust  Ducting for Turbine Expansion Joint,         30,000
     etc.
     Turbine  Inlet Ducting.  Design and Manufacture       75,000
     including Control Valves
     Cooling  System for Load Absorber                     5Q,000
     TOTAL                                              $470,000

     Table 9  estimates the cost of the two test passages.

                               TABLE 9
                       COST OF TWO TEST PASSAGES
     Design                                             $  60,000
     Manufacture of Two Test Passages                    200.000
     Including Control Valves
     TOTAL                                              $260,000
     Estimated Total Test Facility Cost.                 $730,000
                                   49

-------
 4.7  REGENERATION/SULFUR RECOVERY
          Unlike Che boiler where a design concept  is  established,
 sufficient data are not available to permit  the  selection  of  a  preferred
 regeneration process (see Volume I).   A process  might be selected  for
 the development plant on the basis of available  data,  but  the available
 data are inadequate to design equipment.   Several  key parameters which
 determine the equipment sizing cannot be  specified.   Areas of uncertainty
 include:
      •  Sulfur in the spent stone and stone  circulation rate  from
         the boiler
      •  Regenerator operating conditions  which determine the
         quantity of heat which must be supplied  to or removed
         from the process
      •  SO. or H.S concentration which is related  to  gas supply
         requirements to the regenerator and  the  sulfur recovery
         equipment.

          An evaluation was  made to determine if  a  regeneration  system
 could be designed with sufficient flexibility to study alternative
 processes.   Such flexibility cannot be provided  economically  at this
 time.   Since sufficient information is not available,  the  plant is
 designed for once-through operation,  and  a regeneration system  is not
 included in the preliminary design.   Provisions  are made for  a  regeneration
 system — space,  stone feed to the boiler, and removal —  which can be
 installed at a later date.

 4.8   INSTRUMENTATION AND CONTROL
          Instrumentation and control  for a commercial  plant are discussed
 in Volume I, Section  5.  The development plant will provide the opportunity
 to test and demonstrate  the proposed operating procedure and controls.
         Control of  the boiler differs slightly from the standard
once-through boiler practice but is very similar to the process Industry's
practice.  In a conventional boiler, variation in the steam side
operation affects the radiant combustion zone only very slightly.   In
a fluidized bed unit, however, a slight variation in steam  flow

-------
rate, temperature,or heat transfer immediately affects  the fluidized
bed temperature.
          For the development boiler, the steam pressure is controlled
at 2400 psig, which is in line with modern power plant  practice for
subcritical  installations.  The superheat outlet temperature is
limited to 1000°F; this temperature readjusts the water-flow control
rate to the tubes in the fluidized bed.  The fluidized  bed is main-
tained at the proper pressure by back-pressure control  on the effluent
gas or on a by-pass around the turboexpander.  The temperature in the
fluidized bed is used to readjust the coal feed rate, automatically,
after which the air rate is manually adjusted to provide the excess
combustion air at the desired percentage of the flue gas.
          The reason for manual readjustment of the air rate is that
a very slow response is desired so as not to destroy the fluidized bed
characteristics of the boiler.  Too rapid a response in air rate may
either entrain the entire bed or cause the fluidized bed to collapse.
          The emergency control systems will involve immediate stopping
of the flow of coal to the boiler.  This will occur under such condi-
tions as:
     •  Power loss or failure
     •  Instrument air loss
     •  Low pressure in fluidized bed
     •  High pressure in fluidized bed
     •  Low-pressure combustion air
     •  Low-pressure injection air.
          If the coal flow is halted by an emergency condition, the air-
flow will continue for five minutes and then slowly by-pass the boiler.
The air compressors will then be stopped automatically.
          The demonstration of satisfactory operation of a fluidized
bed boiler depends upon both the efficient generation of steam as well
as upon the reduction of pollutants such as S0_, N02,and particulates.
                                  51

-------
To  reasonably demonstrate satisfactory pollution control,  the effluent
flue gas will be monitored  for particulates, S0_,and NO  ,as well as
for the usual effluents of  CO*, 0-, and CO.
          Particulates can  be monitored by means of a beta gage
attenuation of particles deposited on a moving tape (Freeman Laboratories)
or by means of particles deposited on the surface of piezoelectric
quartz crystals (Thermal Systems, Inc.).  These methods  allow a cal-
culated value of particulate concentration in weight of  solids per unit
volume of gas flow; but it is also necessary to determine particle size
distribution for proper operation of cyclones and dust removal equipment,
and for extended operation  of the turboexpander.   The size distribution
can be determined intermittently by means of a multijet  impactor
(Monsanto Enviro-Chem Systems, Inc.) or by a stack gas sampler
(Anderson 2000).
          Flue gas components such as SO-, NO™, C02, SO, can be analyzed
by infrared and/or ultraviolet methods, oxygen by paramagnetic methods, and
NOX by Chemiluminescence.

4.9  PERSPECTIVE VIEW
          A preliminary arrangement of the development plant equipment
is shown in the perspective drawing shown in Figure 10.   The fluidized
bed boiler is contained within the vertical cylindrical vessel in the
foreground;  behind it and to the right is the coal drying and sizing
equipment.   Coal and dolomite storage silos and feed systems are shown
behind and to the  left of the boiler.  A compressor shelter in the
right foreground has been provided for the air supply  system.
          The entire installation is contained within  a 185 ft x 200 ft
site.   The  top of  the pressurized fluidized bed boiler is about  95 feet
above grade,  and the highest point of the particulate  removal system
is about 115  feet  above grade.
                                  52

-------
 PAGE NOT
AVAILABLE
DIGITALLY

-------
         The structure lias been designed to provide ease of access
to the boiler and its accessory equipment for maintenance and for
normal operating checks.  Also, gravity flow of solids Into the solids
feeding vessels from elevated surge bins is utilized to provide for
maximum solids flow reliability.

4.10  PLANT MODEL
         A 3/16-in.scale model of the pressurized boiler development
plant and a 3/8-in. scale cutaway of the boiler were constructed.  Photos
of the model are shown in Figures 11 and 12.  These models will be
used to illustrate the boiler concept and to provide a tool for explaining
the development plant concept, selecting a site, and assembling a
project team.
                                  55

-------
Figure 11:  30 MW Pressurized Fluid Bed Boiler Demonstration Facility

-------
Figure 12:  30 MW Pressurized Fluid Bed Boiler Cutaway
                         57
                                                                 RM-59197

-------
                       5.  EXPERIMENTAL PROGRAM

         The experimental program for the pressurized fluidized bed
boiler development plant has three objectives:
     •  To verify that the technical findings made with smaller
        scale equipment  (such as those relating to combustion,
        pollution abatement, heat transfer, materials, etc.)
        apply directly or can readily be extrapolated to large-
        scale equipment
     •  To study technical problems that can only be studied on
        larger scale equipment (such as those relating to coal
        and lime feeding, nonuniform temperature distributions,
        erosion-corrosion-deposition on moving blades of
        turbines, etc.); and to demonstrate that no new technical
        problems (such as vibration and fatigue of boiler tube
        bundles, etc.) are encountered
     •  To explore advanced fluidized bed boiler concepts (such
        as steam generation conditions of 4500 psi/1200°F/1200°F
        with gas-turbine inlet temperatures of 1900 to 2200°F,
        recirculating bed boilers, etc.).
The end goal is to provide the technical and economic information, and
to create the confidence necessary for proceeding with the installation
of a demonstration pressurized fluidized bed combustion power plant.
         In order to meet these objectives and to reach the goal,
measurements are required over a variety of operation conditions — inlet
and outlet flows, compositions, and temperatures — sufficient to carry
out complete material and heat balances.  Such balances permit the
computation of combustion efficiencies and heat transfer rates.  Analyses
of the combustion gas stream emerging from the boiler are required for:
     •  Primary gaseous components — 0_, C0_, H-O, CO, H ,  N-,
        and unburned hydrocarbons
                                   59

-------
     •  Pollutant gases — S0_ and NO
                             £•       X
     •  Particulates — ash, attrlted sorbent, unhurncd carbon
        (both composition and particle size distribution)
     •  Trace contaminants.
Some gas composition profiles across the bed and through the bed and
disengaging zone are desirable.  Occasional measurements of the compo-
sition and particle size of solids at various points in the bed are
helpful in analyzing boiler operation.  Measurements of boiler tube
vibration and fatigue and of tube and turbine blade erosion and corrosion
are required to estimate long-term durability of boiler and turbine.
Operating conditions at which measurements should be obtained include
primarily the pressure, temperature, airflow, fuel/air ratio, sorbent/
sulfur ratio, and bed height over ranges anticipated in the operation
of a commercial plant.
         To convince utilities that the concept of pressurized fluidized
bed boiler operation is practical as well as economical, the boiler must
produce steam reliably, must be capable of easy turndown to 50% of its
capacity, and must produce combustion gases sufficiently clean to meet
pollution control regulations and to provide reliable, long-term turbine
blade life.
         In order to be convincing, the experimental program must produce
data on:
     •  Boiler dynamic operation characteristics
     •  Durability of materials and construction in the boiler and turbine
     •  The ability to provide any maintenance necessary to achieve
        - Uniform and efficient heat transfer
        - Particulate removal from combustion gases
        - Solids feeding to and from a pressurized system.
         To meet the requirements just outlined, the experimental program
must demonstrate continuous,  controllable coal and dolomite feeding in a
sufficient number of feed lines to give uniform bed operation for at least
60 days without interruption.
                                   60

-------
          Concurrent with the boiler proof run, data on NO  and SO.
                                                          A       £f
emission, and on particulate content at the turboexpander inlet, will
be acquired.
          Following a 60-day proof run, the boiler system will be
subject to a series of tests to experiment deliberately with the
start-up, shutdown, and emergency shutdown systems, controls, and
operating techniques »in order to determine the best methods for coping
with and controlling transient phenomena.
          The foregoing experimental program will permit the design
and construction of a full-scale power-producing combined cycle
pressurized fluidized bed boiler.
          The operation of the fluidized bed combustion boiler
development plant will be carried out in three phases outlined in
Table 10. In the first phase of the experimental program, operating
procedures will be proved put; engineering design and performance data
will then be gathered on a variety of coals and limestone or dolomite
sorbents.  In the second phase, overall systems — boiler, gas-turbine,
and regenerator — control and operation will be investigated;  and the
long-term (60-day) boiler run will be carried out.  Finally, in the
third phase of the program, modifications will be made in the boiler
to enable the study of advanced boiler designs and operating conditions.
Tests will then be carried out to evaluate the effectiveness of such
modifications.
                                   61

-------
                           TABLE 10

          OPERATION OF THE PRESSURIZED FLUIDIZED BED
             COMBUSTION BOILER DEVELOPMENT PLANT
Phase I  Boiler Operating Characteristics
         (boiler, test passage, no regeneration)
         •  Ambient T&P operation
            -  Check out solids feeding and withdrawal
                  Fluldization
                  Particle carry-over
                  Water circuitry/boiler tube configuration
            -  Use dolomite only
         •  Ambient T, high P
            -  Check out solids feeding and withdrawal
                  Fluidlzatlon
                  Particle carry-over
                  Water circuitry/boiler tube configuration
            -  Use dolomite only
         •  Start-up Procedure
            -  Check out using start-up burner and dolomite
               w/o coal:  ability to reach 700-800°F
                          water circuitry
                          air control
         •  Operate with low-sulfur, non-caking coal
         •  Operate with low-sulfur, caking coal
         •  Operate with high-sulfur, caking coal

Phase II  Long-Term  (60 day) System Operation
         •  Boiler control capabilities
            turndown, operating ranges
         •  Boiler/gas-turbine expander operation
         •  Operate with boiler/gas-turbine expander/
            regeneration


Phase III Concept Alternatives

          •  Advanced steam conditions
          •  Boiler tube  configuration  alternatives
          •  Higher gas-turbine temperature
          •  Possible expansion of plant  to a  four-bed
             stacked module
          •  Recirculating  bed  concept
                             62

-------
                           6.   COST ESTIMATE

          Factored estimates were prepared for plant capacities from
22,000 Ib coal/hr to 33,000 Ib coal/hr and operating pressures from
170 psig to 320 psig.  Plant costs were prepared for a 'stand alone1
plant —not adjacent to a power plant —and a development plant
adjacent to an existing power plant.  A summary of the capital cost
estimates, factored from quoted equipment costs, is presented in Table 11.
Plant cost for the nominal 22,000 Ib coal/hr plant at 170 psig is
* $10 million erected excluding the gas-turbine test facility.  The
cost of the boiler unit and extra bundles is •*» $940,000 — excluding
erection.  The main air compressor for the 170 psig plant represents
the other major equipment cost:  $940,000 excluding erection.  The
proposed gas-turbine test facility will add ^ $600,000 to the plant
cost.  The operating cost for the plant is estimated to range between
$2.4 and 3 million per year.
                                TABLE 11
                             CAPITAL COST
Coal Capacity
Ib/hr
22,000
33,000
33,000
Boiler Pressure
psig
170
320
320
Site
adjacent to
power plant
adjacent to
power plant
independent
site
Plant Cost
Delivered & Erected
(Factored Estimates)
$ 9,730,000
16,420,000
19,170,000
                                   63

-------
                            7.   IMPLEMENTATION

           The  schedule  presented  in Figure 13 indicates the basic steps
 toward  a  commercial  fluidized bed combustion boiler power system which
 will:
      •  Reduce capital cost
      •  Increase operating  efficiency
      •  Reduce pollutant emissions
 for  electrical energy generation  from fossil  fuels.   Preliminary plans;
 a detailed design, procurement, and construction schedule; and an
 overall plant  cost estimate have been completed.  These plans, schedules,
 and  estimates  will be used to locate  a plant site, to develop financial
 backing,  and to form a  team to construct, operate, evaluate, and lead
 in the  development plant effort.  This team should include EPA (and
 perhaps also other governmental agencies concerned with fuel utilization
 and  power generation),  the electric utility industry, electrical generation
 equipment manufacturer(s), and steam  generation equipment supplier(s).
 Detail  design  and construction of the development plant could begin in
 1974.   Information from various laboratory, bench, and pilot operations
 throughout 1973 and  1974 will be factored in the plant design.  Operation
 of the  development plant could begin  in 1976.  Sufficient information
 will be available from  the development plant to begin design of a
 demonstration  fluidized bed combustion boiler power plant in 1977.
 This plant could be  operational late  in 1980.
           The  program represented by  the development plant design and
 the projected  schedule may be altered to adapt to the project team and
 site selected.  Several demonstration program options are available.
 Five alternatives have been developed for demonstrating the pressurized
 boiler  concept which  account for variations in potential plant sites.
Table 12 presents projected boiler designs, plant output,  and plant costs
 for the five options.  Demonstration of the total power plant concept
 can also be achieved by a number of different system configurations.  Six
 alternatives have been developed and are presented in Table 13.  Possible

                                   65

-------
                                                     Figure  13
                      PRESSURIZED FLUID BED BOILER COMBINED GAS-AND  STEAM-TURBINE POWER PLANT
                                      ILLUSTRATIVE DEMONSTRATION PLANT  PROGRAM
                                          1973 . 1974 1975  1976   1977  1978   1979  1980  1981  1982  1983

        Fluid  Bed  Steam Generator
        Demonstration	
           Preliminary Design              	
           Assemble  Project Team               	
           Detailed  Design/Construction              	
           Operation                                           	 	

        Power  Plant  Demonstration
           Preliminary Design  Analyses                   	
ON          Establish Program                                    	
           (Par t ic ipants/Funding)
           Detailed  Design                                           	
           Construction                                                     	
           Operational  (Experimental)                                                         	

-------
                                                   TABLE  12

                                       DEMONSTRATION OF BOILER CONCEPT

1.
I Ves
(dia
Stand- Alone
sel No. of Coal
/ft) Beds i Input
1 Ib/hr

Independent Air Supply 12 1 22,000


2.
Independent Water Supply
Steam Directly to Condenser
Process Steam



Gas Generator Gas Turbine 12 1 22,000


3.
Steam to Process
Condensate Return
Gas Turbine Power



Gas Turbine with Generator 12 1 22,000


Independent Water Supply
Steam Directly to Condenser


12 2 44,000


4.






Gas-Turbine Pwr. & Process Steam 12 1 22,000
Gas-Turbine with Generator
Steam to Process


Condensate Return 12 2 ^^


5.





Steam Plant Integration 12 1 22,000
Gas-Turbine with Generator

Water from Steam Plant ,, , ,, nnn
Steam to Existing Turbine t*,uuu
Output

180 x 106 Btu/hr
(rejected to condenser)


185 x 103 lb/hra
(process steam)


3.0 MW (G.T. Power)
180 x 106 Btu/hr
(rejected to condenser)
6.0 MW (G.T. Power)
360 x 106 Btu/hr
(rejected to condenser)
3.0 MW (G.T. Power)
185 x 103 lb/hra
(process steam)
6.0 MW (G.T. Power)
370 x 103 lb/hra
(process steam)
3.0 MW (G.T. Power)
27 MW (S.T. Power)b
6.0 MW (G.T. Power)
54 MW (S.T. Power)b
i Cost
j Capital
l( ins tailed equip)

$12.5 x 106



$11.9 x 106



$12.8 x 106


$18.1 x 106


$12.2 x 106


$17.3 x 106


$10.0 x 106

$14.1 x 106

Operating
($/yO

2.5 x 106



1.7 x 106



1.8 x 106


2.7 x 106


1.7 x 106


2.7 x 106


1.7 x 106

2.6 x 106
.Based on process steam conditions of 300 psig and 500°F.
 Based on 2400 psia, 1000°, 1000° steam conditions.

-------
oo
                                                      TABLE 13
                                          DEMONSTRATION OF PLANT CONCEPT

1.

2.
3.
4.


5.

6.




Single Boiler Module

Single Boiler Module
Two Boiler Module
Two Boiler Modules
(back-fitted into
existing steam plant)
Single Boiler Module

Single Boiler Module Steam
Generator for Eugene, Ore.
Installation

Module
(dia-ft)
12

17
12
12


12
(1 bed)
12



G.T.
Model
English Elect.
EA1
W251
W251
W251


Canadian ©
W41 (Mod.)
English Elect.
EA1


Output
™ Cap
Cost
ital Operating
-v. 75 $43.8 x 106 $4.1 x 106/yr


'v.lSO $69.8 x 106 $6.6 x 106/yr
-x.150 $69.8 x 106 $6.6 x 106/yr
^25 $34.9 x 106 $3.4 x 106/yr
additional



30 $26.2 x 106 $2.2 x 106/yr


13 MW (G.T.) $19.3 x 106b
422,000 Ib/hr
of steam at
1450 psia-950°F



     aTotal plant costs
      Installed equipment cost only

-------
boiler designs, gas turbines, and plant costs are indicated in the table.
Selection of a particular system will depend on the project team,
available site, and economics.  An understanding of these and other
options will be used to develop a firm demonstration program.
          The benefits of a pressurized fluid bed boiler power plant
in the economical generation of electrical energy from fossil fuels with
minimal pollutant emissions amply justify vigorous pursuit of the
recommended program.
                                    69

-------
                            8.   REFERENCES

1.  Westinghouse Research Laboratories. "Evaluation of the Fluidized
    Bed Combustion Process."  Final Report to the Office of Research
    and Monitoring of the Environmental Protection Agency on
    Contract CPA 70-9, November 1971.  Available from NTIS as
    PB-211 494,  PB 212 916,  PB  213 152.
2.  National Coal Board (U.K.), "Reduction of Atmospheric Pollution."
    Final Report to the Office of Research and Monitoring of the
    Environmental Protection Agency, June 1971.
                                  71

-------

-------
                   APPENDIX
Pressurized Fluid Bed Boiler Development Plant
             Designs and Estimates

-------
FOSTER WHEELER CORPORATION                                REF.  11-52331
                                                          DATE  April 1973
                                                          PA8E    1
                             INDEX:
                                                          Page No.
 !•   ABSTRACT                                             I~1
 II.  DESCRIPTION OF PLANT
          1)   Description of Plow                          II-1
          2)   Schematic Flowsheet                          II-2a
          3)   Heat and Material Balance                    II-8
          U)   Engineering Flowsheet                        11-12
in. BASIS OP DESIGN                                       III-1
          1)   Range of Operating Conditions                III-3
          2)  Site Location                                III-3
          3)  Auxiliary Systems                            III-li
          U)  Vfcter and Steam Supply and Disposal          III-7
          5)  Spent Dolomite and Ash Disposal              III-8
          6)  Test Cascade and Future Turbine Expander     III-8
          7)  Combustion and Qas Disposal                  III-9
 IV. DETAILED BOILER DESIGN                                IV-1

 V.  DESIGN PROBLEMS AND SOLUTIONS                         V-1

 VI. EXPERIMENTAL PROCRAN
          1)  Startup  and Shutdown Procedure               VI-1
          2)  Boiler Performance Test                      VI-6
          3)  Test for Operability                         VI-7
          U)  Reliability Demonstration                    VI-10
          5)  Tests of Pollution Abatement                VI-10
          6)  Test of  Long Range Objectives                VI-11

-------
FOSTER WHEELER CORPORATION                                REF.   11-5.2331
                                                          DATE   April 1973
                                                          PAGE     ii
                       INDEX  (continued)

                                                          Page  No.

VII.  PLANT CONSTRUCTION

         1)  Safety and Engineering  Control System       VII-1

         2)  Utilities                                    VII-U

         3)  Plot Plan and Elevations                     VII-6

         li)  Schedule of Design and  Construction         VII-6

         £)  Cost Estimate and Economics                  VII-6

-------
FOSTER WHEELER CORPORATION
                         LIST OF TABLES
                                           REF.  H-52331
                                           DATE  April 1973
                                           PAGE
TABLE I

TABLE II

TABLE III

TABLE IV

TABLE V

TABLE VI

TABLE VII

TABLE VIII

TABLE IX

TABLE X

TABLE XI

TABLE XII

TABLE XIII-A

TABLE XIII-B

TABLE XIII-C
Primary Cyclone Efficiency

Material Balance

Heat Balance

Basis of Design

Coal Specification

Sorbent Specifications

Boiler Tube Material

Pressure Drop

Utilities

Capital Requirement

Working Capital

Manpower Requirement

Plant Cost Estimate

Cost Estimate - Major Equipment

Cost Estimate - Materials & Labor

-------
     FOSTER WHEELER CORPORATION
                                            REF.   11-52331
                                            DATE   April  1973
                                            PAGE   iiii
                            DIAGRAMS AND DRAWINGS
FIGURE NO. I

FIQURE NO. II

FIGURE NO. Ill
   a,b,c

FIGURE NO. IV-A

FIGURE NO. IV-B
   1,2,3,U
FIGURE NO. V

FIGURE NO. VI a

              b

              c

              d

              e

            f & g

              h

              i

FIGURE NO. VII

FIGURE NO. VIII a

                b

FIGURE NO. IX a

              b

              c

FIGURE NO. X
 Perspective  View of Plant

 Schematic Flow  Diagram

 Engineering  Flow Diagram

 Original Boiler Design

 Pressurized  Fluidized Bed Boiler

 Effect of Heat  Flux on Burnout

 Steam Separator D-110

 Lock  Hoppers D-112  & D-U3

 Primary Cyclone Seal Drum D-llU

 Primary Cyclone Lock Hopper D-ll£ & D-117

 Quench Drum  D-118 A & B

 Cyclone Drum D-120

 Main Air K.O. Drum D-121

 Injection Air K.O. Drum D-123

 Boiler Performance Heat Balance

 Operating Schedule

 Emergency Control System

 Plot Plant

Plans & Sections

Plans & Sections

Construction Schedule
 After
 Page No.

 See Figure 10, text,
 11-11


 IV-2

 IV-8


 IV-17

 A-II-5

 A-II-5

 A-II-£

 A-II-S

 A-II-5

 A-H-£

 A-II-5

 A-II-S

 VI -6

 VI-1U

 VII-1
VII-7

-------
FOSTER WHEELER CORPORATION
  I.  Abstract



   A coal fed developmental pressurized fluidized bed boiler tu generate



steam and control S02, NOX and particulates has been designed.  Alternates



investigated include construction adjacent to a power plant vs. an inde-



pendent site, coal feed rate at 22,000 Ibs/hr (equivalent to 30 MW) vs.



coal fed at 33j000 Ibs/hr and combustion side pressure of 170 psig vs.



320 psig.



   Flexibility has been designed into a single fluidized bed boiler to



generate steam in one of three different sized tube bundles, two different



fluidized bed grid plates, two different piping arrangements for water-wall



tubes, superficial fluidized bed velocities of 6 to 15 ft. per second and



bed heights of 10 to 30 feet.  Steam is generated at 2l|00 psig and 1000°F.,



with the boiler capable of operating in preheat, evaporation or superheat



mode or all modes in series.



   Capital investment for the case of coal feed rate of 22,000 Ibs/hr. at



170 psig boiler casing pressure is $9,730,000 with the total program cost



for 3 years of operation including capital investment is $17,02U,000. Other



alternates increase both capital and operating expense.

-------
II

-------
 FOSTER WHEELER CORPORATION                                REF.  11-52331
                                                           DATE  April  1973
                                                           PAGE    H-1

 II.  Description of Plant

     1. Description of Flow

     The flow through the plant is  shown in Figure IE,  Process Flow Diagram

 OP-721-U33 and on Engineering Flow Diagrams OP-721-U2.},  U21;, and 1*26.

     The developmental boiler plant includes coal receiving, crushing,  drying

 and  storage.   Both coal and dolomite receiving and storage.  Both coal and

 dolomite are injected into the fluidized bed boiler using a "Petrocarb"-type

 injection system.   Combustion air  from a centrifugal compressor passes down

 the  annulus of the boiler between  the water wall and boiler shell,  then

 passes up through the grid to the  fluidized bed.   Steam  is generated  in the

 water wall tubes and in the tube bundle of the boiler.   Flue gas passes

 through two stages of cyclones to  remove particulate matter.  Part of  the

 flue gas flow is diverted to a turbine cascade to test turbine  blades  and

 the  remainder is vented to the stack.  A portion of the  flue gas can  also

 be diverted to a future turbine expander.   Both ash entrained in the  flue

 gas  and removed by the cyclones and spent  dolomite are depressured, cooled

 and  sent to disposal.

     Wet coal  from railroad hopper  car will be  discharged to the below-grade

 Wet  Coal Hopper, CR-101.   The coal is then conveyed to the Coal Dryer,  RK-101,

 where the moisture content of the  coal is  reduced from 10.0 vt% to 3.3  wt$.

 The  dried coal is  then discharged  to a Vibrating  Grizzly where  all oversized

 coal is  fed to a Coal  Crusher,  SR-101.   The coal  crusher will normally  yield

 coal particle size of  VxO.   Preheated air from Air Heater, H-101, is used

 for  drying the coal.   The  elutriated coal  dust from the  coal dryer is first

 recovered in  the Primary Cyclone,  G-103, and finally in  a Bag Filter, F-102.

 The  recovered particulate matter is  combined with the crushed coal.  The

 coal is then  forwarded by a Redler-type  Dry Coal  Conveyor, CR-102, to the

Coal Elevator, CR-103.  The coal handling  and  processing facility in this

-------
 FOSTER WHEELER CORPORATION                                REF.  11-52331
                                                           DATE  April  1973
                                                           PAGE    II-2

 II.  Description of Plant (continued)

     1.  Description of Flow (continued)

 section is designed for 60 short tons per  hour, based  on  a l|0-hour week.

     The Coal Silo,  D-102,  is  designed to hold  two-days inventory.  The

 silo utilizes a "live shelf"  bin section for supplying of coal  to the

 Lock Hopper, D-105.   The lock hopper will  replenish  the Petrocarb's

 Injection Drum,  D-106.   Four  (U)  coal pneumatic conveying lines are pro-

 vided from the injection drum.   The feed rate  of coal  will be carefully

 controlled to maintain proper boiler bed temperature.

     To  replenish the "live shelf", coal is withdrawn continuously from

 the  coal  silo and  conveyed to the "live shelf" via the coal elevator.

     The fresh dolomite  for the unit will be purchased  as dried  and screened

 to V x 28 mesh.  The dolomite will be conveyed from the  covered railroad

 car  by  Dolomite Conveyor,  CR-10U, and Dolomite Elevator, CR-105, to the

 Dolomite  Silo, D-108.   The dolomite silo is designed to hold two days of

 inventory.   This silo also employs a "live shelf" bin whereby the dolomite

 is first  fed to the  Lock Hopper, D-109, under atmospheric pressure.  Period-

 ically, the  lock hopper is  pressurized and feeds the Dolomite Injector, D-lll,

 to replenish its supply.   The dolomite is fed continuously to the boiler

 from the  dolomite injector under a controlled rate.

     Combustion air required for the fluid bed boiler is provided by the Main

Mr  Compressors, C-101.  Compressor,  C-101, is designed for 185 psia discharge

pressure.  In addition to the combustion air requirement,  Compressors, C-101,

will also provide:

    a. Injection and pressurizing air for the Petrocarb's Bulk Material

    Handling System.  This air is obtained from C-103 which takes suction

    from C-101.

    b. Instrument purge and blowback  air which is  also obtained from C-103,

-------
 PAGE NOT
AVAILABLE
DIGITALLY

-------
            FOSTER WHEELER CORPORATION
                                                                      PAGE     11-3
            II.  Description of Plant (continual)
                1. Description of Flow (continued)
                   b) (continued)
            this portion of air is dried to -UO°F.  dew point.
                   c) By-pass air to Cyclone,  G-101,  to maintain the cyclone
            efficiency required.
                   d) Excess air from the unit which will be vented for  the
            Stack, ST-101.
                Combustion  air enters from the top  of the boiler.   This  air will  also
            be used to protect part of the discharge  line and unprotected portion of
            the  boiler from high temperature.  The  air then  enters  from  the bottom of
            the  boiler through a grid plate.   The grid is equipped  with  perforated
            nipples which divert the air downward to  cool the grid  plate.   Four (U) coal
            injection nozzles enter from opposite sides of the wall tubes.
                Three (3) ignition  guns are provided  above the grid for  startup.   In
n'           addition,  an Air Preheater,  H-102, has been provided.   The preheater will
<•           raise  the bed temperature to 1000  to 1200°F.  to  initiate the coal combustion.
p           The  preheater,  as well  as the igniters, will be  taken out of service as the
           bed  temperature is  established.
                The heat generated in the boiler will be removed by  the horizontal tubes
           bundle as well as the wall  tubes through either boiler feed water preheat,
           steam superheating  or evaporator.  Steam generation in the horizontal  tube
           bundle is based on  a once-through boiler principle.  Steam generation in
           the wall tubes can be on  either a once-through or a forced circulation
           principle.  A Steam Drum, D-110, has been provided to separate the steam
           from boiler feed water as required.
               Three (3) horizontal tube bundles will be provided designed for 60Jg,
           100$  and l£0# of the normal capacity which corresponds to cases  A-2,  A-l,
           A-3.   In addition, a single-loop test coil will also be provided for

-------
 FOSTER WHEELER  CORPORATION                                 REF. 11-52331
                                                           DATE April 1973
                                                           PAGE II ~k


II. Description of Plant (continued)


    1. Description of Flow (continued)

various testing purposes.  The test loop will be designed to test metallurgy

under conditions of erosion, corrosion and severe temperatures.  Heat transfer

can also be tested under conditions of nucleate and film boiling.

    The fluidized medium in the boiler consists essentially of dolomite with


a small amount of coal.  At proper operating temperature, about 9056 of the

S02 generated by the coal combustion will be picked up by the dolomite in


the form of calcium sulfate (CaSOl;).  To maintain a high efficiency of SQ2


removal the dolomite requirement is greater than stoichiometric.  The re-

quired fresh dolomite is fed from top of the bed at a carefully controlled

feed rate to meet the required calcium to sulfur mol ratio.  Spent dolomite

from the unit is withdrawn from the bottom of the bed to the Spent Dolomite

Lock Hopper, D-112 or 113.  The dolomite withdrawal is controlled by the

boiler fluidized bed level controller which regulates one of the two oper-

ating slide valves to the spent dolomite lock hopper.  A bed level recorder

has been provided at the lower section of the boiler.  This recorder is used

for continuous monitoring of the dolomite bed density and height.

    The disengaging space above the boiler bed can be adjusted by extending

part of the outlet pipe into the dilute phase.  The flue gas with its en-

trained dust will be directed to the First-State Cyclones, G-101 A, B, C

or D, where over 88$ of the dust is recovered.  Due to the various oper-

ation modes of the boiler, two of the four cyclones are equipped with spool


pieces whereby one or two cyclones may be taken out of service to maintain

the recovery efficiency.  At normal operating conditions the inlet velocities

to these cyclones are approximately Sh fps.  It is possible to operate the

cyclones at 1$% of rated capacity without appreciable loss of efficiency.

-------
             FOSTER WHEELER CORPORATION                                 REF. 11-52331
                                                                        DATE April 1973
                                                                        PAGE    II-5
                                           TABLE I

                                   PRIMAIff CYCLONE EFFICIENCY



                    Dust removing efficiency is1 a function of particle  size  and  for

                 a given dust size range it is  also a function of velocity.  The

                 following variation in dust removal efficiencies was received from

                 Ducon for various capacities:

                                                 Inlet            Dust  Removal
                                  Capacity       Velocity            Est. Eff.
                                  % of Max.        FPS            	%



                                     100           53.5              89.60

3                                     75           UO.l              88.67

|                                     5            26.7              85.28

-------
 FOSTER WHEELER CORPORATION                                REF.  11-^2331
                                                           DATE" April  1973
                                                           PAGE  II-6

 II.  Description of Plant (continued)

     1.  Description of Flow (continued)

 When the  capacities are  further reduced, provision has been made  to intro-

 duce by-pass  air to the  cyclones  to maintain the  proper velocity  at turndown.

     The dust  recovered from the cyclones will be  directed to  the  Primary

 Cyclone Seal  Drum,  D-lllj..   When this drum reaches its high level  it. will

 discharge the dust to the  Primary Cyclone Lock Hopper, D-11J>, through a

 series  of interlocked valves.   When D-llU reaches its low level,  its  outlet

 valve will be shut to maintain  a  minimum level.   The solid accumulated  in

 D-115 will then be discharged to  the Spent Dolomite Cooler, RC-101.

     The effluent  from Cyclones, G-101, will be forwarded to the Cyclone

 Drum, D-120.  The cyclone  drum  contains four  (I;)  Second-Stage Cyclones,

 G-102A, B, C  &  D.   Again,  two of  the four cyclones will be fitted with  spool

 pieces  so that  one  or more cyclones can be'taken  out of service to suit the

 mode of operation.  When D-120  is full, the dust  will flow to the Secondary

 Cyclone Lock  Drum,  D-117,  through a series of interlocked valves.  The  solids

 in D-ll?  are  then weighed  and discarded to the spent dolomite cooler.

     The flue  gas from G-102 cyclones are then divided into two  streams.  Part

 of the  flue gas will  go  to the  Turbine Cascade unit.  The main  purpose  of this

unit  is for erosion and  high temperature tests of various types of turbine

blades.  Due  to the presence of CO and coal dust  in the flue gas, the flue gas

temperatures may be as high as  2000°F. as a result of after-burning.  The flue

gas is quenched by water to 600°F. or less,before discharging to  the Quench

Drum, D-118B.

    The remaining flue gas stream is also quenched to 600°F.   The boiler

-------
 FOSTER WHEELER  CORPORATION                                 REF.  n-52331
                                                           OATE  April 1973

                                                           PAGE   H-7


II. Description of Plant (continued)


    1. Description of Flow (continued)


back pressure controller is located on this stream downstream of D-118A.


The effluents from D-118A & B is forwarded to the Flue Gas Silencer, SL-101


and finally to the stack.


    Spent dolomite discarded from D-112 or 113, and flyash from D-115 and


D-117 will be forwarded to the rotary Spent Dolomite Cooler, EC-101.  The


waste matter will be cooled to approximately 300°F and discarded via the


Spent Dolomite Conveyor, CR-106.

-------
   TABLE  H

MATERIAL BALANCE
   Case A-l
Stream
No. Description
1 Wet coal from EL




2 Sized Coal






3 Dolomite



k Dolomite
5 Coal to R-101

6 Spent Dolomite





7. Fines Discarded



Temp. Pressure
°F psia
Ambient 15




100 15






Ambient 15



Ambient 15
Ambient 176. U
min.
1600 176. k





1600 165



Flow Rate
Ib/hr Composition
120,00000 Moisture
VCM
Fixed Carbon
Ash
Total
1U,21|Q(*) C
H
0
N
S
Ash
Total
150,00000 CaCOo
MgC03
Inerts
Total
35j728 Same as Stream 3
22,000 Same as Stream 2

20,979 CaSOi.
CaO
MgO
Inerts
Ash
Total
2900 Ash
Carbon
Dolomite
Total
Particle
Size
10.0 wt.g l*g"xO
36.8 "
U5.3 "
7.9
100.0
71.3 wt.g V x 0
5.U "
9.3 "
1.3 "
h.3 "
8.5 "
100.0
U9-59 wt.# V x 28 mesh
U9.36 »
1.05 "
100.00
%" x 28 mesh
V x 0

18.0 wt.Jg ' V x 0
39.3 "
39.6 »
1.8 "
1.3 "
100.0
60.0 wt.^
30.0 "
10.0 "
100.0

-------
                                                     TABLE  II



                                                MATERIAL BALANCE (continued)



                                                    Case A-l
Stream
No.
8.
9.

Fines
Fines
Description
Discarded
Discarded
Temp.
oF
1600
1600
Pressure
psia
165
165
Flow Rate
Ib/hr
U432


Same
Same
Composition
as Stream 7
as Stream 7
Particle
Size


(*)  Flow rate based on 1;0 hr.  operation per week

-------
    TABLE II
MATERIAL BALANCE (continued)
       Case A-l


Stream Temp
Mo.
10



11



12
13
Hi






15
16
17
18
19







Description °F
Air to C-101 Ambient



Air to C-103 100



Air to R-101 500
Air By-passed 500
Flue Gas from R-101 1600






Flue Gas from G-101 1600
Flue Gas to Turb. Cascade 1600
Flue Gas to Quench 1600
Quench Water 200
Flue Gas to SL-101 600








Pressure
psia
1U.3



180



175
175
168






165
165
165
185
Atm








Flow
Ib/hr
366,501;



53,500



238,988
73,611
273,737






273,737
60,000
213,737
65,683
339, U20








Rate
MMSCFD
116.8



17.0



76.17
23.1*6
82.8






82.8
18.1
6U.7
131 gpm
116.1










°2
N2
H20

02
N2
H20

Same
Same
C02
CO
H20
°2
N2
SOo
NO
Same
Same
Same

C02
CO
H20
02
N2
S02
NO



Composition
20.6 M %
77.3 "
2.1 "
Total 100.0
21.0 M %
79.0 "
nil
Total 100.0
as Stream 10
as Stream 10
18.3 M %
0.2 "
8.5 "
1.7 "
71.2 "
1U8 ppn
198 pan
as Stream lU
as Stream lU
as Stream lU

11.5 M % •
0.12 "
U2.9 "
1.1 "
hk.h "
92 ppn
12l| ppr:

Dust
Loading
gr/ACF










20.8






-3.01
~ 0.30
~ 0.30

~ 0.30





M
g

-------
FOSTER WHEELER CORPORATION
REF.   11-52331
DATE  April 1973

PAGE    II- 11
                              TABLE III

                             HEAT BALANCE


                                 around


                         Fluidized Bed Boiler
                               Case (A-l)


                              Datum: 77° F
INPUT
Stream
Dried Coal
Sen. Ht
Chemical (LHV)
Comb. Air
Fresh Dolomite
Fines Returned
Total Input
OUTPUT
Flue Gas
Spent Dolomite
Fines Elutriated
Reaction Heats
Lb/Hr
22,000
238,988
35,728
2,900
299,616

273,737
20,979
U,900

Temp.
op
77
500
77
1600
1650
1650
1650

MM Btu/Hr
0
275.0
2U.98
0
1.13
301.11
119.U
8.1
1.9

Reactions with Dolomite
CaCO-i + SOp + *
CaCO^ = CaO
MgCOJ = MgO
No Formation
*2 + ^2 '
%o2= CaSV
+ co2
NO
i- C02
-3.91
11. U
10.58
0.07
Incomplete Coal Combustion
C02 = C + 0«
co2 = co + %
Heat Loss
Total Output
>2
299,616

1.69
2.08
0.20
151.51
    Heat Available for Steam Generation = 301.11 - l5l«5l
                                        = Hi9.6 MM Btu/Hr

-------
 PAGE NOT
AVAILABLE
DIGITALLY

-------

-------
            FOSTER WHEELER CORPORATION                                REF.  H-52331

                                                                      MTE  April 1973

                                                                      PAGE  HI-1



           III. Basis of Design



                   A pressurized fluidized bed boiler has been designed to demonstrate



                the possibility of pressurized fluidized bed steam generation while de-



                creasing pollution from the combustion of high sulfur coal.  For this



                study, an Ohio Pittsburgh No. 8 Seam coal will be burned at a normal



                rate of 22,000 Ibs/hr with 10# excess air.  The crushed coal is injected



                into a fluidized bed consisting of particles of 28 mesh to %" dolomite.



                The ash formed after combustion is less dense than the dolomite and is



                elutriated out of the bed.  Specifications for the coal and dolomite are



                given in Tables V and VI.



                   Three boiler load conditions, heat and material balances have been



                calculated for corresponding to 60#, 100# and l50# of normal coal rate as



                indicated in Table IV Basis of Design.  The tubes for steam generation



                in the fluidized bed can be operated in the preheat, evaporation or super-



                heat mode.  The water wall tubes can be operated in the preheat and evap-



\                oration mode.  It is also possible to operate the boiler to sequentially



                preheat, evaporate and superheat by supplying boiler feed water preheated



                to 5£0°F. to the water walls- and further penetrating water in the water



                wall tube to 6?2°F.  The preheated water is then evaporated and super-
                                         /•


                heated in the coils in the fluidized bed tubes.  The superheat section



                can also operate as a reheat section as the temperature profile is the



                same but reheat pressure is lower than superheat pressure.



                   Equipment has been designed to supply sufficient fresh dolomite charge



                for a maximum calcium to sulfur mole ratio of 6 to 1 or a regenerated



                dolomite circulation rate to provide a maximum of 10 to 1 mole ratio of



                calcium to sulfur, with makeup of fresh dolomite set at 1056 of the re-



                generated dolomite rate.

-------
                                      SEI-OEI 'ON U1JO.J
                                           TABLE NO.IV



                          PRESSURIZED FLUIDIZED BED COMBUSTION BOILER
Basis of Design
A-l
100
ic.) Ib/hr 22,000
10
/hr 35,728
6/1
238,988
273,737
i psig 335 °0
ic 9.19
M/Btu/hr 1U9.6

A-2
60
13,200
20
21,U37
6/1
156,U28
177,283
218.9
6.00
85.7

..£2*
150
33,000
0
53,592
6/1
325,892
377,966
U83.9
13.28
222.0
                                                                                                                   o
                                                                                                                   CO
                                                                                                                   o
                                                                                                                   o
Case  No.



Load Factor % of Normal



Coal Injection Rate (as



Excess Air %



Dolomite Injection Rate Ib/hr




         Mol Ratio Ca/S



Combustion Air Rate Ibs/hr



Flue Gas Rate Ibs/hr



       ACFS @ 16500F & 1?0 psig



Superficial Velocity ft/sec



Heat Absorption by Steam M/Btu/hr
                                                                                                               m m


 -::-It is not necessarily intended that case A-3 be operated with zero percent  excess air;

  rather, A-3 conditions indicate the maxijnum design air, coal and dolomite ratio.                            H-o
                                                                                                                    ro


                                                                                                                    VjJ

-------
 FOSTER WHEELER CORPORATION                                REF. 11-^2331
                                                           DATE  April 1973
                                                           PAGE   III-3

III. Basis of Design (continued)

     1. Range of Operating Conditions

     The boiler has considerable flexibility built into the equipment speci-

fications.  Coal and dolomite can be varied from 1056 to 13$ of normal flow

rates.  Fluidized bed heights can be varied from 3 feet to 30 feet.  Pressure

of the fluidized bed can be varied from atmospheric to 160 psig above the

fluidized bed.  The boiler shell is designed for future operations of up to

320 psig.  Two separate air distribution grids are provided for various

capacities from 60$ to 1J>0$ of normal design.  Three separate steam gener-

ating coils are provided for 60$, 100$ and 150$ of normal steam generation.

Boiler feed water can enter at 212 to 6UO°F. with flow rates of up to

£00,000 Ibs/hr.  The combustion air bypass control can accommodate 0 to 100$

of the total design capacity of the air compressor.

     The fixed parameters are: the use of a single fluidized bed of approxi-

mately 35 square feet in cross-section, a steam pressure of 2UOO psig and

temperature of 1000°F. superheat (when operating in the superheat mode).

     2. Site Location

     The preferred location of the demonstration boiler is adjacent to a

large existing power plant where appropriate tie-ins could be effected for

supply of boiler feed water, coal, power and the disposal of ash and steam,

either saturated or superheated.  Such a location would simplify and reduce

the cost of installation of the development boiler.

     If it is not possible to locate close to the site of an existing utility,

then it will be necessary to provide various auxiliaries to the developmental

boiler such as condenser, water purification equipment, boiler feed water

storage, as well as feed water pumps, and cooling towers.

-------
  FOSTER WHEELER  CORPORATION                                 REF. 11-52331
                                                            DATE April 1973
                                                            PAGE  III-U

III. Basis of Design (continued)

     3. Auxiliary Systems

        a) Compression

           A major auxiliary with respect to cost is the air compression

     systems.  Air is required for combustion, for pneumatic injection,

     for pressuring lock hoppers and for instrument purges as well as

     for instrument air.  Best economy is obtained by compression of air

     from atmospheric to 170 psig and £00°F. in a single two-casing

     centrifugal compressor.  Space is provided to install, at a future

     date, Compressor C-102, motor-driven, to compress air from 170 psig

     to 320 psig in one stage.  A third machine is required to compress

     transport air from 170 psig to 320 psig (i^O psig future) for pneumatic

     transport.  A standby instrument air compressor is supplied to supple-

     ment instrument air from the power plant.

        b) Coal & Dolomite Injection

           Wet coal is received in open hopper cars in the size range of

     l3g" x 0 per coal specifications indicated in Table V.  We have assumed

     1056 moisture to allow for rain wetting.  The cars are unloaded into

     a hopper under the railroad tracks.  The coal is dried to 3% from 10$

     surface moisture to insure uniform flow and then it is crushed to

     V'xO and conveyed to a covered silo for .storage.  Unloading coal is

     scheduled for 8 hours per day, UO hours per week at a rate of 120,000

     Ibs/hr.  Coal is injected from the silo by means of a Petrocarb in-

     jection system.  The Petrocarb system consists of a storage vessel,

     a pressurizing vessel and an injection vessel.  The coal is injected

     into the boiler by means of k injection nozzles.  Injection of the

     maximum rate of 33,000 Ibs/hr of ^"xO coal requires 3,000 SCM of

     pneumatic air when the boiler operates at 160 psig.

-------
FOSTER WHEELER CORPORATION
                                                           REF. 11-52331
                                                           DATE April 1973
                                                           PAGE  III-5
                         COAL SPECIFICATIONS

                            TABLE V

                    OHIO PITTSBURGH NO.  8 SEAM COAL

                 (Source of data:  USBM,  Pittsburgh Pa.)
SAMPLE; Run of Mine - As received
PROXIMATE ANALYSIS (wt. 50 :
Moisture
Volatine Matter
Fixed Carbon
Ash
3.3
39.5
U8.7
100 !o
ULTIMATE ANALYSIS
(includes moisture
C
H
0
N
S
Ash
(wt. g):
)
71.2
90
1.3
U.3
                                                       100.0
GROSS HEATING VALUE;   13,000 Btu/lb

NET HEATING VALUE;     12,500 Btu/lb

ASH ANALYSIS (wt. %): Si02
                      A1203
                      Fe20o
                      Ti02
                                             COAL DENSITY;

                                               Particle
                                               Bulk
                                                                95 lbs/CF
                                                                55   "
                     CaO
                     MgO
                     Na20
                     K00
FUSIBILITY OF ASH; Initial Deformation Temperature
                   Softening Temperature
                   Fluid Temperature

GRINDABILITY (Hardgrove);       50 - 60

FREE SWELLING INDEX;           5 - 5-5
                                                          2080°F
                                                          2230°F
                                                          2U20°F

-------
 FOSTER WHEELER CORPORATION                                 REF.  11-52331
                                                            DATE  Apri
                                                            PAGE    in-6
                                TABLE 71
                          SORBENT SPECIFICATIONS
                            Dolomite Properties
Type Dolomite - BCR 1337

Size - Purchased dry and double-screened in size of 1/U" to 28 mesh.
       (61+00 to 580 microns)

       Recycle size range due to attrition and elutriation is 600
       to 63JJO microns with average size of approximately 2000 microns.

Density of 1/U" to 28 mesh

     A - Particle - 175 Ibs/CF

     B - Bulk     -  95 Ibs/CF

     C - Fluidizing  1^0 Ibs/CF @ 6 ft/sec

Chemical Composition Analyzed as Oxide

                                  Wt. %           Mol %

            MgO                   U5.0            53.00

            CaO                   53.0            Ui.81;

            Msc.                  2.0             2.16
                                 100.0           100.00

Hardness

       Moh - 3.5

-------
 FOSTER WHEELER CORPORATION                                REF-  11-52331
                                                           DATE  April 1973
                                                           PAGE    III-7
III. Basis of Design (continued)

     3. Auxiliary Systems (continued)

        b) Coal & Dolomite Injection (cordbinued)

           Dolomite is received crushed and dried in the size range of 28

     mesh by V in covered rail cars.  The cars are unloaded in a shed by

     means of a hopper under the tracks and then conveyed to a dolomite

     silo.  From the silo the dolomite is injected into the top of the

     boiler fluid!zed bed by means of a Fetrocarb Pneumatic Injector.

           Spent sorbent is discharged from the lower section of the bed,

     i.e., just above the grid.  The grid may be located in any three

     positions, from 3 ft. to 7 ft. below the bottom of the tube bundle.

     Spent sorbent may be discharged at elevations of 2 ft., U ft., or 6 ft.,

     2k"j i|8" or 72" from the bottom of the tube bundle.  A view of the coal

     unloading systems and coal and dolomite silos is shown in Figure 1,

     the plant perspective drawing, in Section I.

     k- Water & Steam Supply & Disposal

        Pressures and temperatures for boiler operation were chosen to repre-

     sent the recent steam generator practice for sub-critical operations.

     The actual pressures will depend upon the adjacent power company's boiler

     design.  Water and steam are assumed to be available at 2600 psig and at

     the capacity required in the developmental plant as shown on Drawing

     OP-721-U33C.  Saturatated water at 6UO°F. and 2600 psig would be received

     from the power plant economizer or heat exchangers.  Sub-cooled water at

     212°F. and 2600 psig would be received from the power plant deaerators.

     Saturated steam and 1000°F. superheated steam are returned to the utility

     company.  The pressure drop in the system was purposely kept low (below

     110 psi for normal flow) in order to fit into the utility company's

-------
  FOSTER WHEELER CORPORATION                                REF.   11-^2331
                                                           DATE   April 1973
                                                           PAGE     III-8

III. Basis of Design (continued)

     U. Water & Steam Supply & Disposal (continued)

     boiler operating pressure drop.  Normally all steam is sent to the

     utility company's power plant for disposal.  Superheated steam may-

     be sent directly to the high pressure turbines.   Saturated  steam may

     be sent to intermediate or low pressure turbines or the pressure may

     be dropped so that the steam can be used for heat exchange.

     J>. Dolomite and Ash Disposal

        Spent dolomite and ash from the bottom of the boiler,  as well as

     ash and carryover removed by cyclones are water-cooled in a rotary

     cooler to 300°F. from a maximum temperature of 1?50°F. in the fluid-

     ized bed.  Water sprays are provided if additional direct contact

     cooling below 300QF. is required.  The ash is then transported to the

     power plant by conveyor.  Alternately the ash can be slurried and

     pumped to the power plant's disposal facility for settling.  It is

     necessary to cool the ash as it is conceivable under certain conditions

     that quantities of unburned char nay be released at a high  temperature

     causing the char to burn in the air.

     6. Turbine Expander and Test Cascade

        A stationary cascade to test turbine blade materials may be provided

     in the flue gas stream after the cyclones.   It is expected  that the

     temperature and pressure of the flue gas will decrease only slightly

     passing through the test cascade.  Space will be provided for future

     installation,  of a small turbine expander to take part or all of the

     flue gas and recover some of the energy residing in the high temperature

     and pressure of the gas.  Such a turbine expander should  be designed

     to operate with an inlet rated for l600°F.  and l£5 psig,  and with flow

     characteristics similar to a commercial utility  gas turbine.   In order

-------
FOSTER WHEELER CORPORATION                                REF. 11-52331
                                                          DATE April 1973
                                                          PAGE
  .  Basis of Design (continued)

    6.  Turbine Expander and Test Cascade  (continued)

    to  control the pressure at the boiler fluidized bed,  a bypass  line

    would be used around an expander operating under  pressure control.

    To  keep the pressure control valve from reaching  too  high a temp-

    erature the bypass line with the control valve in it  would be

    quenched to a low temperature.   To prevent the flue gas  temperature

    from rising too high about 1600°F., which would limit the life of

    the expander turbine blades, the flue gas is tempered with cool air

    (at J>00°F.) from the compressor  C-101,  which air  normally bypasses

    the boiler.

    7.  Combustion Gas Disposal

       Combustion gas from the boiler may be generated at 1600 to  17J>0°F.

    and at pressures up to 160 psig  (320  psig future).  Part or all of

    the flue gas passes through  the  test  cascade.  The flue  gas stream

    is  quenched to below 600°F.  and  the pressure is dropped  by means of

    back pressure control.  The  flue gas  is then sent through a silencer

    to  the stack.

-------
IV

-------
 FOSTER WHEELER CORPORATION                                REF.  11-52331
                                                           DATE    April 1973
                                                           PAGE     IV-1


IV. Detailed Boiler Design

    1. Boiler Design

    The pressurized fluidized bed boiler consists of a single fluidized bed

enclosed with a monofin membrane water wall containing a horizontal serpentine

heat exchange bundle.  The bed and steam generating pressure parts are con-

tained in a 12-foot diameter vessel approximately 78 feet tall designed for

320 psig pressure.  Where possible the test facility was designed to duplicate

a single module of the original 300 MW Foster Wheeler-Westinghouse conceptual

design consistent with the flexibility requirements of the test program.

Boiler Drawings are OP-720-9, OP-72U-82, 83 and 81*.

        a) Boiler Specification

        The boiler is designed to operate at: gas side pressure up to 20

    atm.j bed temperature 1300-20000F; gas velocity 6 to 15 feet per secondj

    bed depth 10 feet to 30 feetj bed plan area 35 square feet;  three heat

    exchange bundles capable of handling bed heat exchange duties of 8j>-7 x

    106 Btu's/hr, 1U9.6 x 106 Btu's/hr and 222.6 x 106 Btu's/hr at l600°F.

        . Each bundle would be capable of operating as an economizer

          or preheater, an evaporator and a superheater.  Furthermore

          the bundles would be capable of operating at reduced mass

          flows as a combined evaporator and superheater connected in

          series with the water walls.  In the latter case, water at

          20°F. below saturation would be fed to the water walls and

          leave the bundles as superheated steam at 1000°F.

        . The water walls.would be capable of operating as a water-

          cooled heat exchanger or an evaporator generating saturated

          steam.

-------
•'I
0
 FOSTER WHEELER CORPORATION                                REF.  11-52331
                                                           DATE  April 1973
                                                           PAGE    IV-2

IV. Detailed Boiler Design (continued).

    1. Boiler Design (continued)

       a) Boiler Specification  (continued)

          . The steam generator would be designed such that  the

            three different heat transfer surfaces, submerged in

            the bed could be interchanged with minimum cost  and

            effort.

          . The boiler would be- designed such that each bundle-

            could be installed  or withdrawn as a single unit.

          . The air distributor1 grid could'  be relocated at three

            different elevations.

          . A variable freeboard height above, the bed would  be;

            provided with  a maximum of  20 feet, for disengagement

            of particles splashed up from, the bed.

          . An overall heat transfer' coefficient of J>0 Btu/hr ft2 °F

            would be used  to determine  surface requirements.

          . The boiler would be installed in one of a variety of  sites-..

        Two> designs were1 proposed, to meet these requirements1.  The first

   design, shown in Figure' IV-A,  contained  three separate bundles stacked'

   one above- the other with three, feet, of crawlspace between bundles, per-

   mitting access for-maintenance.,  Headers were located in- the* preheated

   air zone where temperatures  were, low and. operating conditions  less.

   severe-.  Either1 individual coils1 -or platens or the; entire1 bundle, can

   be pulled to- fulfill changes, in test requirements- or make repairs.,

        The second design shown  in. Figures I.VB-1 through k supported from

   headers' located in the* high  temperature; gas- passes, reducing- the, number

   of connections- that  must, be  broken or made, for removal or1 installation

   of the bundle-.,

-------
 PAGE NOT
AVAILABLE
DIGITALLY

-------
 FOSTER WHEELER CORPORATION                                 REF.   11-52331
                                                            DATE  April 1973
                                                            PAGE   IV-3

IV. Detailed Boiler Design (continued)

    1. Boiler Design (continued)

       The first design has the advantage of utilizing only that coil

    surface area required for either oases A-l, A-2 or A-3 operation.

    The second design always has two spare bundles since each of the

    bundles is adequate for its own operating capacity.  However, the

    first design has the disadvantage of requiring many cutting and

    welding operations on each tube to make any changes in tube bundles,

    adding time and money to any change.  The first design also has the

    disadvantage of using crawlspaces between bundles which would not be

    designed into the commercial units.  These crawlspaces may upset the

    fluidization hydraulics leading to difficulties in scaling-up from

    the demonstration to the commercial unit.  The second design was

    chosen as superior in flexibility and in fluidized bed hydraulics.

       b) Construction

          The steam generator was designed to operate on feed water from

    an existing 2i|00 psig once-through system with a final steam tempera-

    ture of 1000°F.  These conditions are considered to be representative

    of existing power plants.

          The heat transfer surface inserted in the bed consists of one of

    three separate but continuous bundles of horizontal serpentine tubes.

    The surface requirements of each bundle were selected to meet the bed

    duties specified with due consideration given to the duty of the

    enclosure wall.  The smallest bundle consists of forty rows of single

    loop-in-loop,  l^g" O.D. tubes with alternate rows off-set vertically

    (see Drawing OP-72U-8U, Fig. IVB-2) providing a triangular pitch with

    tube spacing of 2.828 inches.  Larger bundles make use of the same

    tube arrangement and tube size.  However, double loop-in-loop and

-------
 FOSTER WHEELER CORPORATION                                REF.  11-£2331
                                                           DATE  April 1973
                                                           PAGE   IV-U

IV. Detailed Boiler Design (continued)

    1. Boiler Design (continued)

       b) Construction (continued)

    triple loop-in-loop construction is used to accommodate higher steam

    mass flows at the higher bed duties with nearly constant steam side

    pressure drop.  The schedule of tube material and wall thickness appears

    in Table VII.  The latter was selected on the basis  of superheating in

    the bundle and should be equally satisfactory for evaporating and pre-

    heating functions providing demineralized water from an existing once-

    through installation is used and no chlorides are present.

       The bundles are constructed with one inlet header and two outlet

    headers operating in parallel.  That is to say alternate tubes feed to

    alternate headers.   This was done so as to support the bundle from the

    headers located within the gas stream.   Continuous bundles in beds 1J>

    to 27 feet deep are too heavy to be supported off lugs attached to the

    water wall.  Individual loops are held together with a sinuous strap

    made of an alloy steel running the full length of the bundle.   The

    sinuous straps are tied to the supporting headers.   In addition to

    supporting individual coils and preventing them from arbitrarily

    expanding of  their own weight, the sinuous straps make the bundle

    rigid and reduce the stress on the tubes at the first tube bend created

    by the bending moment of the cantilevered bundle.

       Two headers  are used in series  at the  outlet  to  facilitate support

   during operation and  simplify  removal during modification.  The first

   is  essentially a collecting header  for  the  tubes in  the bundle.  The

   second header  is a steam-cooled beam supporting the bundle and pro-

   viding access  to either end  for cutting during removal.  The two

   headers are connected with four transfer pipes forming a truss capable

-------
 FOSTER WHEELER CORPORATION                                REF.  11-£2331
                                                           DATE  April  1973
                                                           PAGE   IV-5

IV. Detailed Boiler Design (continued)

    1. Boiler Design (continued)

       b) Construction (continued)

    of discharging steam from the bundle.   The supporting header requires

    a cylindrical insert to form an internal annulus so as to maintain high

    steam velocities, good heat transfer and low mean wall header temperature.

    The two supporting headers penetrate the water walls at four locations.

    The four steam outlet pipes are collected or manifolded into a single

    discharge line outside the boiler.   By connecting two outlet headers

    with a series of transfer pipes judiciously  located along the length

    of the header, sufficient room is provided at either end of the support-

    ing header to cut the header at the time of removal.  Two cuts must be

    made at either end, one on either side of the water wall.  The spool

    section thus formed is removed to provide sufficient room for pulling

    the bundle.  Re-welding of the header requires stress retrieving and

    X-raying the welds.

       The same outlet and inlet header connections will be used for all

    three bundles.  The difference in elevation of the outlet headers  for

    the smaller bundles is absorbed by longer transfer pipes between the

    collecting and supporting header.

       The fluid bed is enclosed with a monofin membrane wall capable

    of withstanding 12 psi pressure differential- (maximum expected with

    a 30' bed) between the preheated air and the products of combustion.

    The water wall enclosure serves as a heat transfer surface,  a partition

    between the preheated air and flue gas, and means of structurally support-

    ing the pressure parts.  It also acts as insulation providing a means for

    designing the shell for high pressure low temperature operation.

-------
 FOSTER WHEELER CORPORATION                                REF.  11-52331
                                                           DATE  April 1973
                                                           PAQE    IV-6

IV. Detailed Boiler Design (continued)

    1. Boiler Design (continued)

       b) Construction (continued)

          The water wall enclosure can be penetrated rather simply.   This

    permits locating larger,  more expensive piping not serving as heat

    transfer surface in cooler gas zones outside of the enclosure surface

    where the environmental conditions are less severe.  Locations of

    water wall penetrations can be changed in the field by simply cutting

    out the section of offset tubing and replacing it with a section of


    straight tubing, or vice versa.

          The water walls also provide a simple means of support with

    appropriate consideration given to load and local stress concentrations.

          The favorable characteristics of the membrane wall already cited

    demonstrate some of the advantages of this type of construction.  On

    the other hand, refractory-lined plate steel greatly complicates tube

    support.  Maintenance will be high, particularly with severe thermal

    cycling associated with a test vehicle.  The wall areas in the immediate

    vicinity of the tube bundles are inaccessible.  Refractory could be

    particularly troublesome if large pieces breaking loose from the wall

    become entrained in the exit flue gases.

          A rough cost estimate indicated one square foot of reinforced


    monofin wall might run $12 per square foot.  A refractory wall,

    constructed of % inch plate with U inches of refractory and 2 inches

    of insulation, would cost approximately $2U per square foot.  About

    20$ additional surface would have to be added to the bundle immersed

    in the bed to compensate for the loss in heat transfer to the wall.

          The load-supporting water wall is constructed of 1-7/8 O.D. inch


    tubes on 2 inch centers.   The remaining two walls are constructed of

-------
FOSTER WHEELER CORPORATION                                REF.  11-^2331
                                                          DATE  April 1973
                                                          PAGE    IV-7

IV. Detailed Boiler Design (continued)

    1. Boiler Design (continued)

       b) Construction (continued)

    1-3/7 O.D. inch tubes on 2 inch centers.  Tube thickness and material

    selection appear in Table VII.  The water walls are reinforced with

    10 W tie bars on variable centers.  As the pressure differential

    across the wall increases the center lines between adjacent tie backs

    decreases.

         Each wall is terminated at both ends by a header.  The headers

    are partitioned such that the water wall circuit nay be operated as a

    single-pass or four-pass heat exchanger in four walls connected in

    series rather than parallel.  Modifying the water walls from single-

    pass to four-pass is achieved by cutting loose the second ring header

    at the transfer pipes and sealing the latter.  The single inlet pipe

    to the primary header then is connected to the feed line.  A similar

    modification is required at the discharge end.

         The bundles and enclosure walls are hung from the shell at the

    uppermost extremity.  Since the shell water walls and preheated air

    are at about the same temperature, expansion problems are minimized.

         All water/steam pressure parts were designed according to Section

    I of the American Society of Mechanical Engineers Power Code.

         The shell is a self-supporting vessel approximately 78 feet high,

    designed according to Section VIII UG27 Un-fired Pressure Vessel

    American Society of Mechanical Engineers Power Code for pressures of 320

    psig at temperatures of J?00°F.  The vessel is constructed of 1-3/8 in.

    thick SA 516-70 steel and lined with a 2-inch layer of batten insulation

    with an 0.0k"aluminum sheathing.  The shell is 12 feet in diameter.

    The size was selected as the maximum diameter permissible for shipment

-------
 FOSTER WHEELER CORPORATION                                 REF.  11-52331
                                                           DATE  April 1973
                                                           PAGE   IV-8

IV. Detailed Boiler Design (continued)

    1. Boiler Design (continued)

       b) Constraction (continued)

    as a complete shop-fabricated and assembled unit and minimum diameter

    for internal access to the water-steam pressure parts.

       The upper section of the vessel is reduced to 8 feet 6 inches in-

    ternal diameter by a conical transition piece to permit installation

    of a removable head by means of a flange connection.

       Preheated air is introduced and flue gas withdrawn through an air-

    cooled pipe penetrating the upper-dished head closing off the top of

    the vessel.   The air-cooled piping penetrates the vessel approximately

    five feet.  A transition piece is attached to its furthermost extremity

    completing a sealed connection to the uppermost point of the water walls.

    A mechanical seal completes the connection.  VJhen broken, it provides

    access to the entire fluid bed and immersed heat exchanger  bundle.  This

    permits removal of the bundle as a single unit.

       The air distributor, shown in Fig. IVB-3» consists of three sections

    of Wrought Incoloy 800 plate,  supported by scalloped bars welded to the

    water walls and completely circumscribing the bed.  The air distributor

    is held in position by wedges inserted between inverted water wall

    hanger supports and the grid plate.  The air distributor contains 598

    bull plugs,  each containing 16,  0.2 inch diameter holes for emitting

    and distributing air to the fluid bed.   The three sections  of air dis-

    tributor are bolted together at the web located in the  plenum chamber.

    This arrangement makes it possible to remove the air distributor and

    relocate it  at any one of three elevations.

-------
 PAGE NOT
AVAILABLE
DIGITALLY

-------
 FOSTER WHEELER CORPORATION                                REF.  11-52331
                                                           DATE  April 1973
                                                           PAGE  IV-9
IV. Detailed Boiler Design (continued)

    1. Boiler Design (continued)

       c) Maintenance

       Access to the fluid bed is achieved through either the removable

    head for major repairs or manways in the pressure vessel and water

    walls for minor repairs.  The manways are located above and below the

    bed and in the transition piece at the flue gas exit.

       The bundles may be removed and interchanged by unbolting the flanged

    head and mechanical seal between the air-gas duct and water wall headers.

    The section comes off as a single unit.  The supporting outlet headers

    must be cut at four locations on either side of the water wall enclosure.

    The lower inlet header must also be cut on both sides of the water wall.

    After the bundle is raised slightly the spool sections formed by the two

    cuts can be removed.  After this the bundle is free to be pulled as a

    single unit.

       Repair of individual tubes requires pulling the entire bundle.  This

    is one of the disadvantages of locating the headers inside of the water

    wall enclosure.  In the original design,  individual coils or platens can

    be pulled up into the freeboard area and repaired without having to remove

    the pressure vessel head.

       Installation of the bundle requires stress relieving and X-raying of

    the header welds.

-------
 FOSTER WHEELER CORPORATION                                REF.  11-^2331
                                                           DATE  April 1973
                                                           PAGE    IV-10

IV. Detailed Boiler Design (continued)

    1. Boiler Design (continued)

       d) Operation

       All three bundles can be operated as either a superheater,  evaporator

    or preheater providing proper consideration has been given to the relation-

    ship between bed duty, waterside mass flows, inlet enthalpy and pressure

    drop.  The cooling fluid must be de-mineralized water, free of chlorides

    to prevent stress corrosion on the stainless steel segments of the bundle.

    The heat flux to the tubes is low according to the design conditions

    specified, 30,000-60,000 Btu/hr ft2.  Therefore, overheating of the tube

    surface in the evaporation mode of the transition from wet steam to dry

    should not present a problem.  Figure V illustrates a typical relation-

    ship between tube metal temperature, heat flux, enthalpy and steam

    quality.

       By dropping the mass flow, the bundles can be operated as a combined

    evaporator and superheater.

       The water walls can be operated as a single water-cooled heat transfer

    bundle in either the single-pass or multi-pass arrangement.   The water

    walls can also be operated as a verticle tube evaporator.

       By selecting the appropriate mass flows and making necessary changes

    in the circuitry piping the water walls can be connected in series with

    the immersed bundle such that the boiler can be operated as a once-through

    boiler with 20°F. of sub-cooling at the feed inlet and 1000°F. at the

    superheater outlet.

       All of these operating modes are subject to restrictions of the

    system pressures, temperatures and operating conditions.  These cannot

    be taken into consideration until a site is selected and specific system

    piping is established.  The boiler was designed to operate on a slip-

-------
 FOSTER WHEELER CORPORATION                                REF.  11-52331
                                                           DATE  April 1973
                                                           PAGE    IV-11
IV. Detailed Boiler Design (continued)

    1. Boiler Design (continued)

       d) Operation (continued)

    stream from a once-through boiler at 21*00 psig.  The feed water would

    most likely come from the economizer outlet*  The saturated steam may

    be produced as superheated steam that has been de-superheated to

    saturation.  Unless a very special boiler is selected with adequate

    temperature control, slipstreams of the size required cannot be taken

    from the boiler at locations between the economizer and superheater

    outlet.

       Table VIII is a schedule of pressure drop for the various modes of

    operation requested in the final design.  These will have to be modified

    to the system requirements by changing header sizes, tube sizes, number

    of tubes or other physical modifications that may be found necesaary.

-------
                                         TABLE  VII
                                                                 IV-12
                                   BOILER TUBE MATERIAL
 ITEM
        DESCRIPTION
      SIZE
                                                                 MATERIAL
               NUMBER
              REQUIRED
21 & 22

23 & 24

25 & 26

27 & 28

29 & 30

31

32


33 A

33 B

33 C

33 D

33 E

34

35

36

37

38

39
Inlet Header

Water Wall Tubes

Water Wall Tubes

W/W Outlet Headers

Transfer Pipe

Superheater #1 Inlet Header

Superheater tfl Outlet
Header

Superheater #1 Tubes

Superheater #1 Tubes

Superheater //I Tubes

Superheater #1 Tubes

Superheater #1 Tubes


Superheater Support Header

Outlet Pipe

Superheater #2 Inlet Header

Superheater #2 Outlet Header

Superheater #3 Inlet Header

Superheater #3 Outlet Header
4" Pipe SCHXX

1 7/8 OD x-220 MW

1 7/8 OD x-220 MW

6"Pipe SCHXX

2 1/2MOD x-200 MW

8" Pipe SCH 160


6"Nom x 1.28 AW

1 1/2"OD x .225 MW

1 1/2"OD x .192 MW

1 1/2"OD x .375 MW

1 1/2"OD x .385 MW

1 1/2"OD x .232 MW


8 5/8"OD x 1 1/2 AW

3 l/2"Pipe .469 Wall

5"Pipe SCH 160

4" Pipe SCHXX

4" Pipe SCH 160

4" Pipe SCHXX
SA-106C

SA-210A

SA-210A

SA-106C

SA-210A

SA-106C


SA-335-TP304H

SA-210A

SA-213-T2

SA-213-T11

SA-213-T22

SA-213-T304H


SA-335-TP304H

SA-335-TP304H

SA-106-C

SA-335-TP304H

SA-106-C

SA-335-TP304H
  1

 43

 32

  1

  6

  1


  2

120

120

120

120

120


  2

  8

  1

  2

  1

  2
  (1)  Numbers refer to items illustrated in Drawing L-725-32,  Figure 1.
  (2)  Superheaters 2 & 3 require the same material as Superheater 1.
  (3)  Superheater 2 requires 2/3 the number of tubes in Superheater 1,
       Superheater 3 requires 1/3 the number of tubes in Superheater 1.

  (U)  SA material specifications may be found in Section II, Materials Specifications
       of the ASME Boiler and Pressure Vessel Code.

-------
                                    TABL13 VITT
                                     SUMMARY

                                       OF

                           PRESSURE DROP CALCULATIONS
                                                                           1V-13
CASE

   Bed Duty BTU/HR x 106
   Bundle Duty
   Wall Duty

Superheater Outlet Temperature
Superheater Outlet Pressure
U  •  50 BTU/HR F2 °F
                                    A-l
                                        A- 2
                                     A-3
MATERIAL
SELECTION
Water Walls
SA 106C
Headers
Bundle
Sec. 1
Sec. 2
Sec. 3
Sec. 4
Sec. 5
(1 Pass)
SA-106C
SA-210 A
SA-213-T2
SA-213-T11
SA-213-T22
SA-213-TP304
149.6
98.3
51.3


1000°F
2400 PSIG
85.7
55.1
30.6

227.6
146.1
76.5

                TUBE
P.P.     I.D.    Ac#    t *         LENGTH

1 7/8    1.435  1.670  0.0018    53


 4.5     3.152  7.80   «.-»—   ™
1 1/2
1 1/2
1 1/2
1 1/2
1 1/2
1.024
1.100
.750
1.700
1.024
                                                   .824  0.0018
                                                   .950  0.001
                                                   .442  0.001
                                                   .385  0.0005
                                                   .824  0.00006
Headers
SA-106C
6.625    5.5   23.6
                                                                   129, 150, 127
                                                                    17,  17,  17
                                                                    27,  27,  27
                                                                    32,  32,  32
                                                                    16,  16,  16

                                                                    35,  59,  35
CASES STUDIED
         (1)  Bundle 1, 2, 3 as a superheater.  Sat. steam in.  1000'F Supht. out
              at 2400 psig.

         (2)  Bundle 1, 2,3 as an evaporator.  Sat. water in.  Sat. steam out
              at 2400 psig.

         (3)  Bundle 1, 2,3 as a preheater.Subcooled water in.  212°F inlet temp.,
              2400 psig.

         (4)  Water walls as a preheater subcooled water 212°F inlet temp., 2400
              psig press. - Single and four pass arrangement.

         (5)  Water walls as an evaporator 20°F subcooled water in at 2400 psig press.
              and saturated vapor put - Single and lour pass arrangement

         (6)  Cpmplete once through system.  20° preheater to water walls. 1000°F
              superheat from bundlef^Single and four pass arrangement of water walls.
 ^Nomenclature appears at the end of Table VIII.

-------
     TABLE VIIT (continued)
          SUMMARY
            OF
PRESSURE DROP CALCULATIONS
	(Continued)	
                                                                        iv-iU
CASE 1. 2. 3
           PRESSURE DROP THROUGH BUNDLE
BUNDLE INSTALLED
Mode of Operation
AP, PSI
W x 103 Lb/Hr j
W/A x 103 Lb/Hr - Ft (inlet)
Mode of Operation
AP PSI
AP
AP
W x 103 Lb/Hr „
W/A x 103 Lb/Hr - Ft (Inlet)
Mode of Operation
AP PSI
AP*
AP*
W x 103 Lb/Hr j
W/A x 103 Lb/Hr - Ft (Inlet)
AT
CASE 4
BUNDLE INSTALLED
Single Pass
AP, PSI
AP*
AP*
W x 103 Lb/Hr
W x 103 Lb/Hr - Ft (Ave.W.W.)
AT..
Four Passes
AP PSI
AP
AP;!
W x 103 Lb/Hr -
W x 103 Lb/Hr - Ft (Ave. W.W.
AT
w
A-l

94.9
255
545

41.9
2.6
44.5
260
556

11.4
4.3
15.7
250
534
390
A-j-2
Superheat
130.1
143
614
Evaporator
51.7
1.9
53.6
147
625
Preheater
14.7
2.9
17.6
150
650
390
A-3

98.4
380
540

43.6
4.0
47.6
390
561

11.4
6.6
18.0
384
560
390
WATER WALL AS A PREHEATER
1

1.22
14.1
15.3
250
148
206

58.5
14.1
72.6
250
) 525
206
2

0.43
14.1
14.5
150
89
206

21.1
14.1
35.2
150
316
206
3

2.81
14.1
16,9
384
228
206

134.2
14.1'
148.3
384
810
206

-------
                               TABLE VHI (continued)

                                     SUMMARY

                                       OF

                           PRESSURE DROP CALCULATIONS

                                   (Continued)
CASE 5
   BUNDLE INSTALLED
      Single Pass
      APf PSI

      APf   o
      W x 103 Lb/Hr
      W x 103 Lb/Hr

      Four Passes
      APf PSI


      W x 103 Lb/Hr
      W x 103 Lb/Hr
CASE 6
   BUNDLE INSTALLED
      Single Pass
      AP£ PSI


      W x 103 Lb/Hr
      W x 103 Lb/Hr
      W x 103 Lb/Hr

      Four Passes
      AP, PSI
      APh

      W x 103 Lb/Hr
      W x 103 Lb/Hr
      W x 103 Lb/Hr
                           Inlet)
WATER WALLS AS AN EVAPORA'






ft (Ave. W.W.)





rt x 10
(Ave. W.W.)





2
Ft_ (Ave.W.W.)
Ft .(Bundle-
Inlet)



2
Ft^ (Ave.W.W.)
Ft (Bundle-
A-l
2.7
8.4
11.1
133

103
66.1
10.0
76.1
133

290

ONCE
1
81.9
8.4
90.3
203
122
435

230.1
10.0
240.1
205
490
435
A-2
2.0
8.4
10.4
81

60
24.5
10.0
34.5
81

170

A- 3
5.42
8.4
13.82
205

157
150.0
10.0
160.0
205

440

THROUGH SYSTEM
2
97.2
8.4
105.6
115
70
490

141.6
10.0
151.6
115
280
490
3
83.0
8.4
91.4
300
182
413

404.6
10.0
414.6
300
730
423

-------
                                                                      IV-16
                             NOMENCLATURE
AP    Pressure Drop   LB/SQ IN.



W     Mass Flow       LB/HR



W/A   Mass Flow Per Unit Area   LB/HR FT2



U     Overall Heat Transfer Coefficient   BTU/HR FT2°F



AT    Temperature Difference   °F



O.D.  Outside Diameter   IN.



I.D.  Inside Diameter    IN.



A     CrossSectional Area   SO.IN.
 c


c     Roughness
Subscripts





f     Friction



h     Static Head



t     Total



W     Water

-------
           1500
ffS
oo n
n •
3 H-
n 3
O 00
M •
•a
o  =

0) O
rr B
» CT
O. C
- (0
  09
  M-
  3
  n>
  09
  a
  a-
  w
                   PRESSURE  -2980PSIA         '

                   FLOW RATE  • 520,000 LB/HR- FT2
                                                                        HEAT FLUX
                                                                        I038TU/HR-FT2]
                                                     PER CENT STEAM
            500
               500
                          600
700        800        900
   ENTHALPY (BTU/LB )
1000
1100
                    553         628       682   695
                       FLUID TEMPERATURE- F
       FIGURE  V   EFFECT OF CHANGE IN HEAT FLUX ON BURN-OUT AND DEPARTURE FROM NUCLEATE BOILING POINTS

-------
V

-------
FOSTER WHEELER CORPORATION                                REF.  11-$2331
                                                          DATE  April 1973
                                                          PAGE   V-l

V. Design Problems and Solutions

   1. Particle Removal from Flue Gas

      Gas from the combustion zone,  at 1600 to 17J>0°F.  and at pressures

   of from l£0 to 320 psig, carries  a certain amount of solid particles

   elutriated from the fluidized bed.  These particles, consisting of fly

   ash,  dolomite and some uriburned carbon which must be removed from the

   gas if the high pressure energy of the flue gas is to be recovered in

   a turbine expander.  It is vital  for the process to recover  as much

   of the pressure energy of the flue gas as possible since the compression

   of the combustion air consumes a  large fraction of the total energy

   input into the boiler plant.   The removal of particulates a  high temp-

   eratures and pressures is not an  easily solved problem.  At  the high

   temperatures electrostatic precipitators lose efficiency. Cyclones

   may remove much of the particulates above" a certain  size range,  but

   removal efficiency tends to decrease below about 10  to 20 microns.

   Removal of smaller particles  is slightly improved by the  use of  many

   very  small cyclones,  such as  "Multiclones" or by the use  of  reverse

   flow  cyclones  such as the "Aerodyne" type.  For operation of the

   pressurized fluidized bed boiler  a first-stage cyclone removes bulk

   carryover of particles greater than 20 microns.   These may be removed

   from  the system or returned to the fluidized bed.  The flue  gases next

   go to an Aerodyne cyclone which removes most of  the  particles above

   6  microns.   However,  if this  removal is still not adequate to meet

   the required dust loading 
-------
FOSTER WHEELER CORPORATION                                REF 11-$2331
                                                          DATE April 1973
                                                          PAGE   V-2

V. Design Problems and Solutions (continued)

   2. Fluidization Hydraulics

      The fluidized particle- consists of dolomite in the size range of

   Vx28 mesh (595 to 6350 microns).  The large,  average particle size

   may be reduced slightly by attrition} however, it will still be necessary

   to operate at a high gas velocity.  It is felt that the smaller particles,

   especially unburned coal, may be elutriated out of the bed very rapidly.

      High gas velocity and large particles tend to produce surgining,

   slugging and bumping fluidized beds.

      It is felt'that during the preliminary operation it will be necessary

   to experiment with the effect of particle size on smoothness of fluid-

   ization.  Directionally, it may be necessary to reduce the top size of

   dolomite from V to k or^S mesh.  The smaller, average particle size may

   reduce capacity by limiting gas velocity but the smaller size should

   improve heat transfer and smoothness of fluidization.

   3. Steam and Boiler Feed. Water

      It has been assumed that the pressurized fluidized bed boiler will

   be located adjacent to> an existing power plant.  The experimental, boiler

   will take saturated steam from the existing power plant and return super-

   heated steam, or the experimental boiler will take preheated water and

   return saturated steam.

      Since the adjacent power plant has not been specified, it has been

   necessary to' design the experimental boiler on the basis of a series of

   assumptions as to steam pressure, superheat temperature and also the

   pressure drop through the experimental boiler.  If the system pressure

   drop is too high it will be impossible to get steam back into the power1

   plant's system in which case it may be necessary to break the pressure to>

   some lower stage on the power plant1s turbine interstage pressure.

-------
FOSTER WHEELER CORPORATION                                 REF.  11-^2331
                                                           DATE April 1973
                                                           PAGE   7-3

V. Design Problems and Solutions (continued)

   3. Steam and Boiler Feed Water (continued)

      It also may be very difficult to convince a power plant to tap into

   the power plant's main boilers to remove saturated steam and return

   saturated steam to the power plant's superheaters.  This could upset

   the firing balance of the power plant.

      It may be better to operate the test facility without tapping into

   the power plant's boiler.  Boiler feed water can be taken from the

   power plant's boiler feed water preheaters and exchangers and this

   water sent to the fluidized bed boiler water tubes for preheat and

   evaporation.  From the water wall tubes steam and water flows to the

   tube bundle in the fluidized bed to complete evaporation and then to

   superheat to 1000°F.  The high pressure superheated steam would then

   be sent directly to the power plant turbine without disrupting the

   power plant boiler.  The fluidized bed tubes would have to be designed

   specifically for this case as it is necessary to maintain high mass

   velocities to prevent burn-out of evaporation tubes.  Each section of

   tubes would contain sufficient instrumentation to evaluate design

   parameters of heat transfer, hydraulic and pressure drop so that future

   fluidized bed boilers may be designed with confidence..

   it. Bundle and Tube Removal from the KLuidized Bed

      In conventional boilers, each pass (platen) penetrates the water

   wall at the inlet and outlet so that the tubes are headered outside the

   water wall in the relatively cold sections of the boiler.  In the pressur-

   ized fluidized bed boiler it has been decided to header internally even

   though the headers are now a more expensive, thicker-walled alloy.  This

   means that fewer penetrations of the water wall are required (two headers

   instead of 80 passes).  It is estimated that removal of the entire tube

-------
 FOSTER WHEELER CORPORATION                                REF.  11-52331
                                                           DATE  April 1973
                                                           PAGE   V-U

V.  Design Problems and Solutions (continued)

   U. Bundle and Tube Removal from the Fluidized Bed (continued)

   bundle with internal headers will require  two weeks and $10,000 vs. 3

   weeks and $20,000 for external headers.

   J>. Start-up Heaters

      To support combustion it is necessary to heat the combustion zone

   to at least 700 to 800°F..

      An air preheater has been provided to preheat air to 1200°F.   When

   the fluidized bed is held at a low level,  the preheated air can heat

   the bed plus the tubes in a reasonable time interval to 1000°F.   To

   avoid overstressing the grid an insulated  plate is placed  above the

   boiler nozzle connected to the preheater to prevent radiation damage.

   If additional heat input is required when  the bed level is high or when

   the steam flows in the tubes at a high capacity additional heat may be

   supplied by firing three ignitor-combustor guns directly into the

   fluidized bed above the grid.

   6. Shell Insulation

      To contain combustion at high temperature and pressure  it  is  desirable

   to reduce the temperature of the enclosure shell to a point where the

   allowable stresses are reasonable,  i.e., less than 600°F.   This  may be

   accomplished by using internal refractory  insulation,  or alternately,

   the shell may be cooled by surrounding the combustion zone by water-

   wall tubes.  The tubes are used to preheat or evaporate water, which

   means that the water-wall temperature is less than 6?0°F.   The annular

   space between the water-wall and the pressure shell is cooled by com-

   bustion air.

-------
FOSTER WHEELER CORPORATION                                REF.  11-52331
                                                          DATE  April 1973
                                                          PAGE    V-5

V. Design Problems and Solutions (continued)

   6. Shell Jjiaulation (continued)

      It has been decided to use water walls similar to conventional

   boilers for the following reasons:

      a) The water walls in general can be designed for higher heat

      recovery and thermal efficiency than refractory insulation.

      b) Water walls take up less space than insulation.

      c) Insulation would have to be covered with a hard facing

      refractory  to resist erosion.

      d) Water walls can be built to take slight pressure differential.

      e) Water walls reduce the structural steel requirement by acting

      as supports for coils in the bed and for the grid.

   7. Steam Tube Orientation

      Steam tubes may be positioned horizontally, vertically or at an

   angle.  It may be expected that the position of the tubes can effect

   heat transfer rates,  smoothness of fluidization and erosion.  Heat

   transfer rates, as pointed out by Genetti,  et al.  (l),  suffer when

   tubes are positioned  at an angle.  The same authors indicate that

   vertical bare tubes have slightly better heat transfer rates than

   horizontal tubes in the particular size range of 100  to  200 microns.

   However,  for larger-size particles (UOO microns),  there is no difference

   in heat transfer between horizontal and vertical tubes  at any velocity.

      The heat transfer  rate was  calculated by the method  Vreedenburg(2)  for

   the normal capacity Case A-l.   This method  indicates a  slightly better
      Genetti, W.E.j Schmall, R.A. & Grimmett, E.S.
      AIChE Symposium Series, Fluidization No. 116, Vol. 67, p. 90, 1971

  (2) Vreedenburg, H.A., Chem. Eng. Sci., Vol. 9, p. 52, August 19!?8.
      Chem. Eng. Sci., Vol. 11, p. 27U  (I960)

-------
FOSTER WHEELER CORPORATION                                REF.   llr$2331
                                                          DATE   April 1973
                                                          PAGE     V-6

V. Design Problems and Solutions (continued)

   7. Steam Tube Orientation (continued)


   heat transfer for vertical tubes than for horizontal.  However,  if the

   method of Wender and Cooper(l) for vertical tubes transfer rate is com-


   pared with horizontal tubes by the method of Vreederiburg,  the horizontal

   tubes show a better heat transfer rate.


      From the literature it is difficult to determine if horizontal tubes


   are superior to vertical.  However, for deep fluidized beds  of 10 to


   30 feet, as designed into the developmental boiler,  the horizontal tubes

   may exhibit superior heat transfer characteristics since horizontal tubes

   tend to act as baffles breaking the bubble growth which is detrimental

   to good heat transfer rates.

      Tube position can also effect erosion.  Zenz(2) indicated  that erosion

   is a function of velocity to some power  exponent ranging from 3  to 6,  as

   well as the distance from nozzle to target.   This author also points out

   that in pneumatic transport, there is often severe erosion on the outer

   radius of elbows due to the impact of the curved wall of the bend.  Similarly,

   the impact of the fluidized particle will be greater against horizontal tubes

   than vertical tubes.  For the horizontal configuration, it is necessary to

   weld a small impingement plate on the bottom rows of tubes.   Similarly,  for

   vertical tubes,  the bottom 180° bends must be protected by welding a wear

   plate to the bottom U bends.


      Both horizontal and vertical tubes must be well-supported or  vibration

   will cause serious mechanical difficulty.  We propose that the fluidized

   bed unit be constructed in such a manner that either horizontal  or vertical

   bundles can be used with headering occurring internally to the water walls,
  (l)Wender, L. & Cooper, G.T., AIChE J., Vol. h, p. l£, March 1958

  (2)Zenz, F.A. & Othmer, D.F., "Fluidization and Fluid-Particle Systems",
    Reinhold Publish. Corp., New York (I960) p. 338

-------
              FOSTER WHEELER CORPORATION                                 REF. 11-$2331

                                                                        DATE April 1973

                                                                        PAQE   V-7


             V. Design Problems and Solutions (continued)


                7. Steam Tube Orientation (continued)


                so that replacement need only involve cutting and rewelding the header


                instead of each pass of the tube bundle.  For the test facility hori-


                zontal tubes were chosen.


                8. Position of Cyclones


                   Cyclones in fluid, bed operation can be positioned above the fluid-


                ized bed in the same vessel as the fluidized bed or they may be


                positioned externally to the fluid bed vessel.  It has been decided


                to position the cyclones externally.  This will allow an increase in


                flexibility by using multiple cyclones in parallel so that the removal


                of one, two or three units will maintain a high efficiency at all


                capacities.  External installation will allow experiments on cyclones


                and measurements of cyclone efficiency.


                9. Coal Injection


3                  Coal feeding and control of rate and uniformity of feed rate is
y
;

i               a difficult problem.  It has been decided to use a Petrocarb-type


"               of feeding system.  The total coal feed is weighed into lock hoppers


                and then fed into a special injector vessel containing multiple nozzles


                to uniformly inject the coal by means of hydraulic transport.


               10. Shell Size


                   It was decided to restrict the shell diameter of the development


                boiler to that used in a commercial design, i.e.,  the maximum capable


                of shipment by rail so that the vessel can be shop-fabricated.   In


                this  case the  diameter of 12'0"  was chosen and this allowed reasonable


                internal  area  for headers and flexibility for various pipes penetrating


                the shell.  No advantage could be seen in increasing the diameter beyond


                12'0"  for the  development plant  boiler.

-------
VI

-------
 FOSTER WHEELER CORPORA! I ON                                REF.  n-52331
                                                           DATE   April 1*73
                                                           PAGE     VI-1
VI. Experimental Program

        The experimental program and test procedures are the minimum re-

    quired to meet the objectives of the demonstration boiler as outlined

    in the Introduction in Section I.  The sequence of operation of the

    pressurized fluidized bed boiler including tests and experiments has

    been divided into the following phases:

        1. Startup

        2. Boiler Performance Test

        3. Tests for Operability

        IK Reliability Demonstration

        5. Tests of Pollution Abatement

        6. Tests of Long Range Objectives

        Some of the tests can be performed concurrently.  For instance,  the

    heat transfer should be analyzed for every operation or  test on the  boiler.

        In all phases it is planned to  operate the boiler with a coal feed of

    Ohio Pittsburgh Number 8 Seam Coal.   The sorbent will be BCR 1337 Dolomite.

    Testing other types  of coal  or sorbent will extend  the test  period.

        1. Startup and Shutdown  Procedure

        Prior to the initial startup, careful  and thorough preparation is

    a prerequisite for satisfactory performance eliminating much trouble

    and  delay during the initial  startup.   A final inspection should be

    given  to  all vessels before bolting of  the manways.   Refractory-lined

    vessels of 12  feet in diameter  or less  and piping of monolithic con-

    struction are  cured and dried by others.  Depending on the actual site

    for  this  plant,  the cyclone drum, D-120 may be too large  to be shipped

    in one piece.  In  this case, D-120 will be field-fabricated and the

   refractory linings installed on site.  The main air compressor, C-101,

   and air preheater, H-102, could be used for drying of the refractory

-------
FOSTER WHEELER CORPORATION                                REF.   11-52331
                                                          DATE   April 1973
                                                          PAGE       VI-2
VI. Experimental Program

    1. Startup and Shutdown Procedure (cont'd)

    lining of this vessel.  After curing and drying of refractory-lined

    vessel cracks may develop.  Small cracks of refractory-lined vessels

    are normal.  However,, when the crack is larger than 1/8" in width and

    IV in depth, the crack shall be repaired prior to startup.

       Particular attention must be given to the inspection of  the Fluid-

    Bed Boiler.  The wall tubes and horizontal tube bundle should be checked

    for signs of leakage.  Care should be given to thorough cleaning of the

    instrument purge line.  After the instrument lines have been cleaned,

    be sure that the proper restriction orifice plate has been  put back

    on the purge line.  Piping supplying purge or aeration medium other

    than instruments should be prepared in a like manner whenever particu-

    late matter may be present.

       During initial startup all instruments must be completely checked

    out.  This is particularly important for the ELuidized Bed  Boiler unit.

    The control valves should also be checked out for operability, i.e.,

    stem travel, action on air failure,  etc.   All transmission  systems  for

    each instrument shall also be inspected.

       Preliminary Preparation

       Utilities required for the startup shall be verified that all are

    in service or in readiness.  A thorough check for readiness of the

    following utilities or service is required:

       a) Instrument air supplied to all instruments as required.

       b) Electric power available for all drivers.

       c) High pressure boiler feed water and saturated steam are  avail-

          able for the fluid bed boiler.

-------
 FOSTER WHEELER CORPORATION                                 REF. 11-52331
                                                            DATE April 1973
                                                            PAQE  VI-3

VI. Experimental Program (continued)

    1. Startup and Shutdown Procedure (continued)

       Preliminary Preparation (continued)

       d) Medium pressure steam is available for Air JPreheater, H-102.

       e) Cooling water must be available.  Cooling water flow may be

          established through the equipment required for startup.

       f) Fuel oil should be made ready for the Air Preheater, H-102.

       g) All fire fighting and other equipment.

       h) Verify that all blinds are removed or is the normally open

          position for operation.

       Establish Air Flow

       Before running-in the compressors,  all auxiliary systems shall

    be carefully inspected.  Oil reservoirs, lubricators and oil lines

    shall have clean oil circulated for verification of cleanness.   This

    oil should then be discarded and the proper lubricating oil supplied.

    During run-in of the compreesor, all controls of the lubricating

    system must be made to function correctly and satisfactorily.  All

    alarms and safety devices must be verified as to proper settings

    and correct function.

       At the completion of compressor run-in,  the Main Air Compressor,

    C-101,  shall be put into service.  Due to the high discharge temper-

    ature of  this  compressors,  a temporary air cooler may be required during

    the initial startup to minimize thermal shock to refractories.   The  air

    velocity  in the fluidized bed boiler shall  be maintained at 3 to k fps

    and the air temperature set at approximately 2j?0°F to 300°F.

       All refractory-lined vessels  should be heated at this time.   This

    is  accomplished by  opening  the balance line on vessels D-112, 113, llU*

    115 and 11? to  admit the heated  air  or flue gas and crack open the vent

    valve on each of these vessels.

-------
 FOSTER WHEELER CORPORATION                                REF.  11-52331
                                                           DATE April 1973
                                                           PAQE  VI-U


VI. Experimental Program (continued)


    1. Startup and Shutdown Procedure (continued)


       Establish Air Flew (continued)


       At the same time, the Injection Air Compressor, C-103, shall be put


    into service to establish the required pressurizing and injection air


    for the Petrocarb system.  The instrument purge air from the Package


    Purge Air Dryer, A-102, shall also be put into service.


       Loading of Coal and Dolomite


       Next, the coal and Dolomite Silos, D-102 & 3, shall be filled.  The


    Lock Hoppers, D-10J> and 109, and the Injection Hoppers, D-106 and 111,


    shall be made ready for startup.  At this time, the Petrocarb's system


    shall be subject to thorough inspection and tests.  Particular attention


    shall be given to the performances of the Coal Crusher, SR-101, Coal


    Dryer, RK-101, and the various conveying systems.  At the completion of


    the initial tests of the Petrocarb system, the dolomite shall be in-


    jected into the boiler to a bed height of approximately four (U) feet.


       Initial Startup

       The air temperature to the boiler shall be increased gradually until


    it reaches the discharge temperature of the air compressor.  At this


    time, saturated boiler feed water at 2UOO psig shall be circulated through


    the wall tubes to the Steam Separator, D-110, and back to the power plant.


    Saturated steam at 2^00 psig shall be admitted to the horizontal tube


    bundle at a reduced rate of approximately 70,000 Ib/hr.  Next, the Air


    Preheater, H-102, is put into service.  The fluidized bed temperature


    shall be brought up very gradually by the air preheater at a rate not


    exceeding 100°F per hour, until a bed temperature of 1000°F to 1200°F


    is established.  Next, one of the four coal injection lines should be

-------
 FOSTER WHEELER CORPORATION                                REF. 11-52331
                                                           DATE  April 1973
                                                           PAGE   VI-£

VI. Experimental Program (continued)

    1. Startup and Shutdown Procedure (continued)

       Initial Startup (continued)

    placed into service at a minimum coal injector rate.  As the coal com-

    bustion takes place, the air preheater firing rate shall be reduced.

    When it is determined that the coal combustion will maintain the

    fluidized bed temperature, the air preheater shall be taken out of

    service completely.  During the initial startup,  the bed temperature

    shall be maintained at around lUOO°F to 1^00°F.  The fluidized bed

    level and boiler feed water and saturated steam feed rates shall be

    adjusted to maintain the bed temperature as the coal rate is increased.

       The operation will be continued until the required coal injection

    rate is established.

       Spent dolomite from the boiler will be discarded to the Spent Sorbent

    Lock Hoppers,  D-112 and/or 113,  and then to the Dolomite Cooler,  RC-101,

    for disposal.

       Normal Shutdown

       The following shutdown procedure covers a normal,  scheduled and

    complete shutdown such as would  be required for turnaround and in-

    spection.

       Over a period of several hours,  the coal rate  to the boiler shall be

    reduced.   During this time,  the  air rate shall  also be cut back to main-

    tain a low oxygen content in the flue  gas.   When  the boiler bed temper-

    ature reaches  1000°F.   The coal  injection lines shall  be  cut  off  one at

    a  time until the coal feed is  completely cut off.   The dolomite feed to

    the  unit shall also be  stopped.   The compressed air, however,  should be

   maintained to  facilitate  the withdrawal  of  the  dolomite.  When the bed

   temperature reached 6£0°F, the water quench to  the Quench Pot, D-119,

-------
FOSTER WHEELER CORPORATION                                REF.   11-^2331
                                                          DATE   April 1973
                                                          PAGE     VI-6

VI. Experimental Program (continued)

    1. Startup and Shutdown Procedure (continued)

       Normal Shutdown (continued)

    shall be taken out of service.  The residual dolomite and fly-ash in

    the system shall be emptied to the Dolomite Cooler, EC-101.  At the

    end of the operation, the boiler pressure shall be reduced gradually to

    atmospheric pressure to complete the shutdown.

       Schedule

       The schedule for startup after acceptance of the boiler plant from

    the contractor allows four (1;) months for initial startup.   This time

    period allows for repairs and minor modifications as well as training

    of operators.

    2. Boiler Performance Tests

       The performance test for the Fluidized Bed Boiler unit shall be

    adopted from the American Society of Testing Materials Power Test

    Code^1).  The Code is intended primarily for conventional steam

    generation units.  Minor modifications, therefore, must be made for

    the performance tests of the Fluidized Bed Boiler.  Figure VII offers

    a format for evaluating the Fluidized Bed Boiler unit performance.

    The major modifications included in this form deals with the reaction

    and sensible heats of S02 sorption, and formation of CaO and MgO, etc.

    Other modifications are minor and are self-explanatory.

       For a large commercial unit, the efficiency of the power generation

    will be high due to the inclusion of waste heat boiler, turbine expander,

    as well as turbine steam generation.  However, for the demonstration unit


    (1) American Society of Mechanical Engineers PTC U.1-196U Power Test
        Codes Steam Generation Units, herein, is believed to be in general
        agreement and intention of the ASME Code.

-------
 PAGE NOT
AVAILABLE
DIGITALLY

-------
FOSTER WHEELER CORPORATION                                 REF. 11-$2331
                                                           DATE April 1973
                                                           PAGE   VI-7

VI. Experimental Program (continued)

    2. Boiler Performance Tests

    these facilities have been deleted for reason of economy.  To have a

    meaningful determination of the Fluidized Bed Boiler efficiency, the

    above facilities should be accounted for.  A time period of one month

    is allowed for the performance tests.

    3. Tests for Operability

       A series of tests are required to determine operability and response

    of the unit.  Operating factors such as capacity turndown, stability

    at low capacity, response and tracking, testing for entrainment, heat

    transfer, fluidization, removal efficiency of particles from flue gas,

    efficiency of combustion and corrosion-erosion tests are required.

       After the boiler performance test at normal (A-l Case) conditions,

    it is necessary to test turndown from normal capacity with combustion in

    the boiler and all auxiliaries operating.  Turndown of coal feed (with its

    proportionate air quantity) will drop the temperature of the fluidized

    bed since the heat transfer area is fixed and the transfer rate in a

    fluidized bed is approximately constant with velocity.  A drop in temper-

    ature of the bed below llj.OO°F may tend to reduce the sulfur removal capacity

    of the dolomite. To maintain a temperature above lUOO°F with adequate

    sulfur removal capacity in the bed, it may be necessary to drop the level

    in the bed as the coal feed is decreased.  At some low capacity the fluid-

    ization and heat transfer will suffer due to low velocity and low level

    of the bed.  In addition to capacity turndown, it is desirable to test

    fluidized bed pressure turndown.  The pressure can be reduced from 160

    psig to a few psig above atmospheric pressure.  The compressor will still

    operate at its design point, however, most of the gas will be bypassed

-------
 FOSTER WHEELER CORPORATION                                 REF.  11-52331
                                                           DATE  April 1973
                                                           PAGE    VI-8

VI. Experimental Program (continued)

    3. Tests for Operability (continued)

    around the boiler and the coal feed will be reduced from normal rate

    to the lowest controllable rate, i.e., approximately 10/6 of normal.

    A one-month period of operation is required to evaluate turndown.

    Turndown tests should not be performed when the boiler is operating

    under evaporation mode due to the danger of loss of nucleate boiling

    promoting tube burn-out due to low flow and low velocity through

    fixed-sized tubes.

       Both heat transfer and hydraulics, which includes the determination

    of flow vs. pressure drop for both the steam side as well as the fluid-

    ized bed side, and fluidization characteristics such as slugging of the

    bed,  clinkering, etc., will be evaluated during every experimental run

    and therefore separate runs are not required.

       Operation to test entrainment can be effected by lowering an internal

    air-cooled chimney from the outlet of the bed into the free space above

    the bed.  The internal chimney is welded or cut to fix the disengagement

    height.  This will allow an evaluation of the effect of freeboard for

    various velocities on entrainment.  A total elapsed time of four (U)

    months may be necessary for this operation due to the down-time required

    to modify the internal chimney.

       Particulate removal efficiency can be evaluated at different velocities

    of flue gases.  Tests can be performed by sampling between the boiler

    and the Ducon cyclone, between the Dueon and the Aerodyne cyclone and

    also after the Aerodyne cyclone and after the quench.  Velocity can be

    varied by varying flue gas quantity, by changing the number of cyclones

    in the flue gas stream and also by bypassing clean air into the cyclones.

    Two (2) months are required for testing cyclone efficiencies.

-------
FOSTER WHEELER CORPORATION                                REF.  11-£2331
                                                          DATE  April 1973
                                                          PAGE   VI-9

VI. Experimental Program (continued)

    3. Tests for Operability (continued)

       The efficiency of combustion will be evaluated for each test pro-

    cedure.  Steam production, coal feed rate, amount of carbon in the

    entrained particulate, unburned GO and hydrogen in the gas  will be

    analyzed for each test to calculate the combustion efficiency.

       Corrosion-erosion testing will proceed during all tests  by in-

    spection of all existing equipment between tests, as well as by

    inserting a special test loops in the fluidized bed.  Each loop will

    usually be constructed of a single material such as TP3014H  (18-8) to

    evaluate erosion-corrosion, as well as welding metallurgy.   Loops can

    be tested during other boiler test operations.

       In addition to the test loop, the entire boiler unit will confirm

    materials selection and bundle design by periodic inspection of those

    portions exposed to the fluidized bed by measuring metal thickness.  An

    important part of the materials testing will be derived from the operation

    of the turbine cascade tester.  Separate test periods for erosion are not

    required as erosion will be determined after every shutdown.

       Heat Transfer and Fluidization

       Various temperature points have been provided for both the horizontal

    tube bundle and the wall tubes.  The heat transfer rates of the dense

    bed section,  the dilute phase as well as the section immediately above

    the dense bed can be computed.

       Operating a fluidized bed unit with relatively large particle size may

    sometimes result in slugging problems.   The closely-packed  horizontal

    tube bundles  will reduce coalescence and slugging tendency.  Radioactive

    probe has been provided.  The probe could be located at various elevations

    of the unit to monitor the slugging height.

-------
FOSTER WHEELER CORPORATION                                 REF. 11-52331
                                                           DATE April 1973
                                                           PAGE   VI-10


VI. Experimental Program (continued)


    3. Tests for Operability (-continued)


       The movement of individual particles past the tubes will be  of


    importance.  Short-lived radioactive .particles .may be used .to study


    the movement of the particles, the turn-over rate, .residence -tune,


    etc., through the horizontal tube bundle, in a manner similar to their


    use in commercial 'catalytic fluid .bed systems.


       Three (3) sample  'Connections have been -provided on the dense bed


    and one on the spent dolomite line.  With these .samples it will be


    possible to study the degree of particle size separation, at various


    heights of the bed.


    1;. Reliability Demonstration


       In the process industry a new plant is .usually accepted as operable


    if the installation-can be'demonstrated 'to -operate, at .-full .capacity


    for some minimum .period, such as 'ten days.  'However-, in order to demon-


    strate reliability, a developmental .boiler -must 'operate -at -full capacity


    for an extended period of 'time.  It has been assumed 'that a one-year


    period of time will be .required .for operation .under normal capacity


    (A-l design case) to adequately demonstrate reliability.


    5. Tests for Pollution Abatement


       Those factors in the operation of 'the pressurized 'fluidized .bed


    boiler effecting S02, NOX and iparticulate matter are:


          . Calcium/sulfur -ratio


          . Bed temperature


          . Bed -height


          . Excess 02 in flue gas


          . Operating pressure
                              i

          .. Feed and removal locations

-------
 FOSTER WHEELER CORPORATION                                 REF. 11-52331
                                                           DATE April 1973
                                                           PAGE VI-11
VI. Experimental Program (continued)

    5. Tests for Pollution Abatement (continued)

       In order to test the effect of the above variables on emissions of

    S02 , NOX and particulates, a set of experiments have been developed.

       Case A-l will offer an ideal case for pollution control tests.  In

    this case the excess C>2 in tlie ^ue S38 can ^e increased to 5 mol£.  The

    normal bed depth of approximately nineteen (19) feet will offer adequate

    latitude to study the effects of bed depth.  The suggested parameters

    to be used in this study will be as follows:

          Bed Temp. °F             13*0   ll£0   1550   1650   1750
          Ca/S Mol Ratio              2      3      k      $      6
          Bed Depth, Ft.              9   H-5     Hi-   16.5     19
          Ex 02 in Flue Gas,Mol %     0   1.25    2.5   3.75      5
          Operating Press. Atm. Abs.  5   6.25    7.5   8.75     10

       The above parameters may be evaluated by means of 33 experiments.

    It is not our intent to commit the operation of the developmental boiler

    to the full 33 experiment block, since preliminary operation of the boiler

    will show that some of the proposed factorial tests may not provide use-

    ful data.

    6. Test of Long Range Objectives

       The long range objectives studies include testing those factors which

    may improve steam generating efficiency, reduce S02, NOX and particulate

    pollution and will demonstrate the operability of a complete steam

    generation facility.

       a) Study of different coals and sorbents to improve pollution

       removal efficiency.

       b) Study of granular bed filter or alternate systems to increase

       particle removal efficiency.

-------
FOSTER WHEELER CORPORATION                                 "EF. 11-52331
                                                           DATE  April 1973
                                                           PAGE   71-12


VI. Experimental Program (continued)


    6. Test of Long Range Objectives (continued)


       c) Study of turbo-expander operating characteristics to re-


       cover as much compression power as possible, including ex-


       pander control and its interaction with the air compressor.


          The turbo-expander will demonstrate operability and control.


       Metallurgy will be determined by operation of the turbine cascade


       tester.

       d) Alternate tube bundle designs can be studied to improve space


       utilization, heat transfer, reduce tube cost and perhaps reduce


       erosion.

       e) High steam temperature and pressure, while increasing capital


       investment, should increase power generating efficiency.  The


       feasibility of designing the fluidized bed developmental boiler


       for steam at 6500 psig and 1300°F was investigated.  An advantage


       of operating at extreme conditions in a fluidized bed is that the


       tube metal temperature can be kept relatively low allowing a reason-


       able design stress on the tubes.  If the fluidized bed temperature is


       assumed to operate at a maximum of 1750°F when the steam temperature


       is 1300°F., the skin temperature will be less than 1360°F.


          An Inconel material Number 625 (ASTM RliWi) annealed has a rupture


       stress of 18,000 psi for $0,000 hours of service according to Inco


       Bulletin T-l|20.  If an allowable stress of 15,000 psi is assumed


       and with a tube thickness tolerance of + 15/6, the O.D. of a 1" I.D.


       tube would be less than 1-3/U".  This thickness-diameter ratio is


       near the limit for hot bending of Inconel 625.  At any thickness,


       powerful equipment is required for heat forming which can only be


       done in the 1950 to 2l50°F. range.

-------
FOSTER WHEELER CORPORATION                                 REF. 11-52331
                                                           DATE April 1973
                                                           PAGE   VI-13

VI. Experimental Program (continued)

    6. Test of Long Range Objectives (continued)

       e) (continued)

          The developmental boiler has a small test loop which can be

       designed for high temperature and pressure steam generation.

       In addition to the test loop, some auxiliary equipment such as

       a high-head plunger pump, a hairpin exchanger to preheat water

       and a quench to reduce steam temperature, plus a pressure re-

       ducing station and proper instrumentation to monitor and control

       flow, pressure and temperature, must be provided.  After success-

       ful operation of the test loop, a small bundle could be provided

       in the developmental boiler for actual steam generation including

       preheat,  evaporation and superheat in the fluidized bed boiler.

       f) Study fluidized bed combustion at higher pressures.   The plant

       is mechanically designed to operate at 320 psig in the  fluidized

       bed.   However, to increase pressure from 160 psig to 320 psig it

       is necessary to insert an additional centrifugal compressor on

       the combustion air (Compressor C-102).

       g) Demonstrate operability of the complete power plant  installation.

       This  will require additional fluidized beds for preheat evaporation,

       superheat as well as for reheat.   The water side will be piped in

       series through the fluidized beds.   The coal,  dolomite,  air and

       flue  gas  will be piped in parallel.   The beds  do not have to be

       stacked but all three can be built at grade level.   Additional

       equipment besides the turbo-expanders will be  steam turbo-generator,

       condenser,  boiler feed water treatment,  deaerator,  boiler feed water

       pumps,  electrical switch gear and transformer,  heat exchangers.

-------
WESTINGHDUSE RES. LAB
PRESSURIZED FLUIDIZED BED COMBUSTION BOILER
PITTSBURGH, PA.
                                                     FIGURE VIII a

                                                  OPERATING SCHEDULE
TASK
1
2
3
U


6



NAME
START-UP
OPERABILITY CHECKOUT
BOILER PERFORMANCE TEST
RELIABILITY DEMONSTRATION
TT?^T^ TTHP POT T TTTTOW POWPTJOT

LONfr RAMfiF TF^T^



1ST. Yr.
••
•
—







2ND. Yr.



_






3RD. Yr.










llTH. Yr.










^TH. Yr.






























(D (B •
^t:

-------
VII

-------
 FOSTER WHEELER CORPORATION                                REF.  11-$2331
                                                           DATE  April 1973
                                                           PAGE  VII-1
VII. Plant Construction

     1. Safety and Emergency Control System

        The boiler emergency shutdown trip system is shown on figure VIII-b.

     In general, the procedure to be followed in an emergency is to follow

     the pattern of a normal shutdown as closely as possible except where

     particular emergency conditions require more drastic action.

        a) Low Flow of Boiler Feed Water to Tube Bundle

        When the boiler feed water to the tube bundle drops to its low

     flow set point, an alarm will sound.  This will allow the operator an

     opportunity to correct the situation.  However, should the boiler feed

     water flow rate continue to fall to its low-low flow set point, the

     low-low flow switch (FSLL) on the boiler feed water circuit trips

     the injection and pressuring air to the Injection Drum,  D-106, to cut

     off the coal feed to the boiler.  The switch will also actuate one point

     of a multi-point, multi-variable alarm annunciator to indicate such an

     emergency has taken place.  The low-low flow switch shall be set to avoid

     high tube skin temperature of the tube bundle.  During evaporation oper-

     ation the flow switch shall be set within its minimum nucleate boiling

     range.  When it is determined that adequate boiler feed water cannot

     be obtained, the unit will shut down under normal shutdown procedure.

        b) Low Flow Saturated Steam to Tube Bundle

        The same type of protection has been provided for the saturated

     steam circuit to the tube bundle as that provided for boiler feed water.

     The coal feed to the boiler will be cut off when the saturated steam

     reaches its low-low flow set point.  This is necessary to avoid excess

     tube skin temperature of the bundle.

-------
             FOSTER WHEELER  CORPORATION                                 REF. 11-52331
                                                                       DATE April 1973
   VII  PLANT CONSTRUCTION   (continued)                                PAGE VII-2
        1. Safety and  Emergency Control System  (continued)
           c. Low Flow of Boiler Feed Water  to Wall  Tubes
              The wall tubes of the boiler are also  protected against  abnormal low boiler
        feed water flow rate.   The low-low flow switch will trip  the coal feed to the boiler.
        The  low-low now switch (FSLL) should be  set within its minimum nucleate boiler range.
           d. Tube Bundle Rupture
              In the event  of a tube leak or rupture of  the tube  bundle, the high pressure
        boiler  feed water or steam to the unit must  be cut off to protect the boiler. The
        flow rate of the boiler feed water or saturated  steam to  the unit is continuously
        monitored against the corresponding  preheated boiler feed water, saturated steam
        or the  superheated  steam product.  When the  flow differential  relay senses an ab-
        normal  difference in flow rates of the  two streams, the high flow differential
        switches, (FDSH) will cut off the boiler feed water or saturated steam as well as
        the  coal feed  to the boiler.
           e. Water Wall Tube Rupture
s             The pressure  drop data across  the water wall tube will be monitored contin-
        ually.  In the event of a wall tube  leak  or  rupture, the  pressure drop across the
        wall tubes will drop and the low pressure differential switch  (HDSL) will trip  the
        boiler  feed water to the wall and coal  injection to the boiler.
           f. Dilute Phase  High-High Temperature
              The boiler bed temperature is  controlled by coal injection rate to the unit.
        The  dilute phase of the unit may at  times experience higher temperature than the
        bed  due to possible after-burning.   A high temperature alarm and  emergency water
        spray system have been provided on the  dilute phase to control its temperature.
        However, should the dilute phase temperature continue to  climb, a high-high
        temperature switch, (TSHH) will trip off  the coal injection to the boiler.
°

-------
 PAGE NOT
AVAILABLE
DIGITALLY

-------
             FOSTER  WHEELER CORPORATION                                 REF.  11-52331
                                                                       DATE  April 1973
                                                                       PAQE  VII-3


             VII.  PLANT CONSTRUCTION (continued)

                  1.   Safety and Emergency Control  System (continued)

                       g.   Low Pressure Flue Gas

                           A loss of flue  gas pressure  due either  to  back pressure

                  control valve  or  rupture disc failure,  should cut  off the main air

                  and coal injection to the boiler.  This is necessary to avoid an

                  excessive superficial velocity  through  the unit to control the

                  dolomite elutriation loss.

                       h.   Loss of Main Air

                           On loss of main air from  the Main Air Compressor, C-101,

                  the low flow switch from the main air will cut off the coal and

                  dolomite to the boiler,  followed  by  normal shutdown  procedure.

                       i.   Power  Failure


                           During a  power  failure, emergency power shall be made available

                  for the electronic instruments, solenoid actuators and the slide valves.

9                 Motor driven compressors,  pumps,  spent  dolomite cooler, RC-101, and
0
                   the coal/dolomite preparation and injection system will be inoperable.


                   The safety circuit is so arranged that on trip of the circuit, coal


                   and dolomite injection to the boiler will be cut off.  An interlock


                   system will be provided on the spent dolomite cooler, RC-101, to shut


                   off all spent solids to the cooler during power failure.

                      j.  Cooling Water Failure


                          Upon failure of the cooling water, the main air compressor,


                   C-101, and the injection air compressor, C-103, will be shut down due


                   to excessive discharge temperatures.  The loss of main air will in turn


                   cut off the coal injection to the boiler.  When the spent dolomite


                   cooler, RC-101, senses a low flow of cooling water,  the low flow switch

                   will cut off all spent solids to the cooler and shut off the fresh

                   dolomite to the boiler.

-------
    FOSTER WHEELER CORPORATION                                REF.  11-^2331
                                                              DATE  April 1973
                                                              PAGE  ttl-fc

VII  PLANT CONSTRUCTION (Continued)

     1. Safety and Emergency Control System (continued)

        k. Loss of Instrument Air

           All control valves during instrument air failure will fail in

      a safe manner.  The coal and dolomite injections to the boiler will

      be cut off.  Control valves for the boiler feed water or saturated

      steam to the tube bundle or water walls will be in locked position

      and continuously admitting boiler feed water or saturated steam through

      the tubes.  The main air compressor,(C-101),will be taken out of ser-

      vice.

        1. Manual Shutdown

           The unit can also be brought down manually through hand switches.

      One hand switch will be located on the instrument board, and another

      one mounted locally.  In the event of a fire, failure at the main power

      plant or any other reason, the manual shutdown switch will trip the

      safety circuit to cut off coal/dolomite to the boiler, block off spent

      solids to the spent dolomite cooler, (HI-101), and shut down the main

      air to the unit.


      2. Utilities

      Table XEsummaries the utility requirements for four cases.

               Coal          Design        Inclusion of
               Capacity      Pressure      Expander and
      Case     TPD           PSIG          C-102	      Location

       I         26k           160              No         ) Adjacent
      II         396           320              No         ) to a Power
     III         396           320             Yes         ) Plant
      IV         396           320              NO         Stand Alone

-------
                                             TABLE NO. IX
CASE NO.

Coal Feed Rate  TPD

Fluid Bed Pressure PSIG

Inclusion of Expander and
C-102 Compressor

Dolomite TPD

I   Power in KW

    a)  13.2 K7, 30,60
    b)  U.16 KV, 3Cf,60
    c)  UUO V, 30,60
    d)  110 V, 30,60

           TOTAL POWER, KW

II  Cooling Water GPM

III Treated Water

IV  Fuel Oil MM Btu/Hr

V   Cooling Tower Make up Water GPM
UTILITY
I
26U
160
No
U32
15,70U
7U6
92
Uo
16,582
2,885
57
3.17
_
SUMMARY
II
396
320
No
6U8
21,221
7U6
110
Uo
22,117
U,OUU
85
U.76
—
III
396
320
Yes
6U6
21,221
3,838
110
25,209
U,63l
85
U.76
—
IV
396.
320
No
6U8
21,221
3,827
380
60
25,U88
*
**
U.76
800
3
m
30
m
m
S
§
so
*




»» >» m
0 -1 Tl
mm'
*   Stand-alone unit contains own cooling towers requiring only makeup water
    at 5# of circulation rate.

•s*  Sttand-alone unit has demineralizer to produce both quench and boiler feed water.
 I H'Ul
VAM l\3
  \O

-------
FOSTER WHEELER CORPORATION                                REF.  11-52331
                                                          DATE  April 1973
                                                          PAGE  VII-6

VII.  PLANT CONSTRUCTION AND OPERATION (continued)

      3.  Plot Plant and Elevations

          Plot plan and elevations are shown on drawings OP-721-588,

          589, & 590.  The plot plan was based upon the assumption and

          that the pressurized, fluidized bed boiler would be located

          adjacent to an existing power plant.  Dolomite would be  trans-

          ported to the plant site by"rail.   The dolomite would be dry and

          double-screened.  Covered rail hopper cars would be required and

          unloading would occur under a covered shed to prevent wetting by

          the rain.  Coal may be introduced by conveyor from the utility

          plant's stock pile or it may arrive by open hopper- rail  cars.

          Steam and boiler feedwater are piped from the development

          boiler to the Utility Plant.  Spent dolomite and ash are sent

          to the utilities ash disposal system by conveyor.

      U.  Schedule of Design and Construction

          The schedule of design and construction is hown in Figure X.

          Completion of design and construction will require 20 months.

      5.  Cost Estimate and Economics

          A series of cost estimates are presented for various capacities

          and design pressures.  Case I has a plant capacity of 22,000

          Ibs/hr coal feed (A-l Material Balance) and a design pressure

          of 170 psig in the boiler.  Case II refers to 50# higher

          capacity of 33,000 Ibs/hr coal feed (A-3 Material Balance)

          and an operating pressure of 320 psig but minus the high

          pressure compressor C-2 and minus the turbo-expander C-U.

          Case III at 33,000 Ibs/hr of coal feed and 320 psig includes

          the high pressure compressor and expander.  Case IV refers to

          a stand-alone boiler not adjacent to a power plant.

-------
 PAGE NOT
AVAILABLE
DIGITALLY

-------
WESTINGHDUSE RES. LAB
PRESSURIZED FLUIDIZED BED COMBUSTION BOILER
PITTSBURGH, FA.
REF:  11-52331
DATE:  April 1973
PAGE:  VII-7
                                                       FIGURE X

                                           DESIGN AND CONSTRUCTION SCHEDULE
MONTHS
TEARS
PRELIMINARY DESIGN

DETAIL ENG. DESIGN
MAJOR EQUIPMENT

REQUISITION

PURCHASE
DELIVER
DRAFTING
CONSi.AUul.LON

1
0
?
N
3
D
1972



U ! 5 6 7 8 9 10 11 12,13
j IF M i A |M j j A|SJO
1973
i
•



























;







i ; i ,

*



(£)••••<£)

(?) —
!
;

!
'Ill
iu 15
N!D








•"©
•
,


16 17 18 19120 21 22I23 2k J25. 26^27 ' 28
J i F M :A ;
M ' J J | A
197U



:
,
,


! ± 	
W



l
1
1
!
: ! i
i

•

; ;
! 1
J I
• I '
! !
1 ' •
; )
; j
i i
i
i ;
1 '
i 1
i 1
i |
sj
0 'N
D I

i








i
!
1


'
-t;
j
i




n™
i
i
'
•
j
i


•
i
i

-------
.FOSTER WHEELER CORPORATION                                REF.   11-52331
                                                          DATE   April 1973
                                                          PAGE   VII-8


VII.  PLANT  CONSTRUCTION AND OPERATION  (continued)

      5«   Cost Estimate and Economics (continued)

                   Coal Capacity   Boiler Pressure    Comp.       Plant Cost
           Case       Ibs/hr  	      psig          C-23C-U   Delivered •& Erected

           I        22,000           170             omit     $ 9,730,000

           II        33,000           320             omit      13,61;0,000

           III       33,000           320           include     l6,U20,000

           IV        33,000           320             omit      16,390,000

           An alternate case was considered when the developmental plant is

           located at an independent site some distance from any power

           plant.  This alternate adds $2,750,000 to either Case II or

           Case HI to cover additional equipment such as water treatment,

           condensers, boiler feed pumpts, etc. required at our independent

           site.

           The total program cost considering a three-year operation with

           Case I (A-l Material Balance) installation amounts to $17,02U,000.

           The total program with a Case II (A-3 Material Balance) install-

           ation for a five-year period, including long-term experimental

           projects amounts to $29,515,000.  Details are presented in

           Table X.  It has been assumed that no credit can be taken for

           intermittent steam generation.

           Tables XI and XII present the working capital required and the

           operation manpower requirements.  Tables XIII-A, XIII-B and

          XIII-C present a breakdown of the cost estimates for Case II.

          Details of the estimates may be found in Appendix I.

-------
FOSTER WHEELER CORPORATION                                REF. 11-$2331
                                                          DATE  April 1973
                                                          PAGE    VII- 9
                             TABLE X

                       CAPITAL REQUIREMENTS FOR
                         DEVELOPMENTAL BOILER

                                               Case I        Case II
     A.  Capital                              (3 years)      (5 years)

        1.  Fixed Capital Investment         $ 9,730,000    $13,6UO,000

        2.  Working Capital                      $95.000        816.000

                                            $10, .325, 000    $1U, U#, 000
     B. Operations

        1. Labor @ $12,000/yr (3)            $1,9UO,000    $ 3,21*0,000

        2. Utilities (1)  (2)                 2,UU8,000      5,1*90,000

        3. Coal & Dolomite  (1)  (2)          2,030,000      5,100,000

        U. Maintenance (@ 3#/yr)            _ 876.000      2.0U5.000

                       Operating Cost        $.7.29U.OOO    &L$.895.000

           Total C ash Requirement            1 7, 6l9, 000     30, 331, 000

           Less return of working capital       595.000        816.000

               TOTAL COST OF PROJECT        $17,021,000    $29,515,000
     NOTES:

             (1) Assumes on-stream factor of $Q% at normal rate.

             (2) Unit cost of utilities, coal & dolomite on next page.

             (3) Yearly rate includes fringe benefits and administration.

-------
FOSTER WHEELER CORPORATION                                 REF. 11-52331
                                                           DATE  April'1973
                                                           PAGE  VII-10
                            TABLE No. XI


                           WORKING CAPITAL



1. One Month Inventory                                   CASE T        CASE-I][

      a) Coal         @ $6/T   (l)                      $U8,000       $ 72,000

      b) Dolomite         @ $5/T   (1)                   65,000         98,000

2. One Month Wages plus Administration

      5U men @ $12,000/yr       (2)                      51|,000         5U,000

3. Utilities (A-l Case), One Month

      a)  Power    © $0.01/kw                           119,000        159,000

      b) Water          @ 100/1000 gallons               12,000         17,000

      c) Treated Water         @ $1/1000 gallons          3,000          UjOOO

      d) Fuel Oil          @ $6/bbl                       2,000          3 ,'000

k* One Year of Maintenance Equipment @ 3% TFI           292,000        t;09,000

                        Total Working Capital         $ £9^000     $ '816,000


NOTES:

   (1) Highly dependent on source of material .and location of
       plant site.

   (2,) Yearly rate includes fringe benefits 'and .'general administration.

-------
                                      SE1-OEI "ON
                                                TABLE NO.  XH

                                           MANPOWER REQUIREMENTS
                                                                                 Total                              *
                                                              Men/Shift          Men        Total                  ^
                                                                                 ~~~~~~                              m
                                                                                                                    m
                                                                                                                    3O
  I. Supervision                                                                                                    0
                                                                                                                    •so
     Plant Manager                                                                 1                                ^>
     Shift Foremen                                                1                U                                g
     Maintenance Foreman                                                           1                                ^
     Chemist & Engineers                                                           3                                §
     Secretary - Clerk                                                             1         	

                                                             Sub-total             10          10

 II. Operators

     Goal Handling &. Preparation (l shift/D @ 5 days/wk)          -                U
     Dolomite & Coal Injection                                    1                h
     Compressors                                                  1                k
     Boiler                                                       1                h
     Lock Hoppers & Ash Disposal                                  1                k
     Utilities                                                    1                U
     Control House                                                2                8         	
                                                             Sub-total             32          32

III. Maintenance                                                                                                2 2 S
     ~~~--~~— """^                                                                                                o -i ^i
                                                                                                                m m •
     Instruments                                                  1                U
     Electrical                                                   1                U
     Welder - Boilermaker                                         1                U        _
                                                                                                                  H-
                                                             Sub-total             12          12


                                                             TOTAL MANPOWER              =     $h

-------
FOSTER WHEELER CORPORATION                                REF.  11-52331
                                                          DATE   April 1973
                                                          PAQE     VII-12
                             TABLE XIII-A
                             COST ESTIMATE
                                              CASE II          CASE III
    Materials                                $6,607,000       $7,763,000
    Labor                                     5,131,000        6,370,000
    Const. Insurance                             72,000           87,000
    Engineering & Fee                         1,830,000        2,200,000
                                            $13,61*0,000      $16,U20,000

-------
  FOSTER WHEELER CORPORATION
                          REF.   11-52331
                          DATE   April 1973
                          PAGE    VIE-13
                          TABLE HIIB
                         COST ESTIMATE
                        MAJi
PMENT
ITEM
R-101
D-no
D-112
D-113
D-llli
D-n5
D-n6
D-117
DESCRIPTION
Boiler + Extra Bundles
Steam KO Drum
Spent Dolomite Lock Hopper
it ii it M
Primary Cyclone Seal Drum
11 " Lock Hopper
Secondary Cyclone Seal Drum
" " Lock Hopper
D-118 A&B Quench Drum
D-120
D-121
D-122
D-123
E-101
E-103
RC-101
ST-101
C-101
C-103
A-101
F-101
H-102
G-101
G-102
Cyclone Drum
Main Mr KO Drum
ii it it ii
Injection Air KO Drum
Main Air Com. Exch.
Main Air Comp. Exch.
Dolomite Cooler
Stack
Main Air Compressor
Injection Air Compressor
Instrument Air Compressor
Intake Air Filter
Peabody Heater
First Stage Cyclones (U) + Valves
Second Stage Cyclones (U) + Valves
MATERIAL
COST $
938,700
17,600
20,900
20,900
20,600
20,900
20,600
20,900
18,600
32,300
12,000
9,300
3,900
2$,000
5,000
60,000
26,000
9UO,000
155,000
8,100
8,600
28,700
102,500
180,500
CR-106  Spent Dolomite Conveyor

A-102   Purge Air Dryer

SL-101  Flue Gas Silencer
                               Major Equipment Cost

                               Labor to Erect Equipment
                                 20,200

                                 10,000

                                 25,000
                             $2,751,800

                             $   550,000

-------
    FOSTER WHEELER CORPORATION                                REF.  11-52331
                                                              DATE  April 1973
                                                              PAGE  VH-Ui
                               TABLE XIIIC

                              COST ESTIMATE

                        CASE: II  _ TOTAL MATERIALS & LABOR
                                                     MATERIAL          LABOR
                                                       COST             COST


Foundations, Paving & Cone. Structures             $   ?li,000        $ U;2,000

  Structural Steel & Pipe Supports                    127,000           89,000
  Building                                             28,000           l£,000
  Piping                                              l|12,000          U00,000
  Instruments                                         137,000           59,000
  Electrical                                        1,225,000        1,270,000
  Insulation                                           85,000          127,000
  Testing                                               2.200           U2.000

                     Total Other Equipment         $2,110,200       $2,171,000

Process Equipment                                   2.75l»800          550,000

                                                   $lt, 862,000       $2,721,000

Coal & Dolomite Injection (D&E)                     1.7li5.000           -0-

                                                   $6,607,000       $2,721,000

Field Supervision & Indirect Labor                      -            2.UlO,000


        Total Material and Labor                   $6,607,000       $5,131,000

-------
Al

-------
FOSTER WHEELER CORPORATION                                REF.   11-52331
                                                          DATE   April 1973
                                                          PAGE   AI-1
                           APPENDIX I

                         BASIS OF ESTIMATES


     Plant costs presented in Section VII for various cases are based

upon equipment quotations, equipment estimates plus standard account

factors for piping, Instruments and other materials and labor.  Factors

are obtained by experience on chemical, petroleum and steam generating

plants of comparable size and complexity.  A set of estimating backup

sheets detailing plant costs is included.  Equipment items marked "Q"

•are obtained from vendors quotations, those items marked "E" are

estimated equipment.  Accounts marked "F11 are factored based on

experience with comparable plants.


     In  transforming the estimate from Case II, representing a design

at 320 psig boiler  casing and 33,000 Ibs/hr coal rate to 170 psig and

22,000 Ibs/hr coal  rate  (Case I), the plant cost decreased from $13,61$,000

 to $9,730,000.  Approxljnately $352,000 of this difference  was due to the

 decrease in pressure and a $3,558,000 decrease was due to  the drop  in

 capacity.  The influence of  capacity on cost was factored  for ,all

 equipment except  the boiler  remained the same  size only the two smaller

 steam coils  being retained.  The  influence of pressure on  cost was

 calculated on an item  by item basis using such methods as  cost per  unit

 weight for pressure vessels  to  arrive at a plant cost for  170 psig

 design.   These plant costs are  indicated in Foster Wheeler Corporation's

 letter of February 15,1973  to Westinghouse and the costs are detailed  on

 work sheets  under Case I.

-------
                  FOSTER WHEELER CORPORATION
                         Kngineers • Manufacturers • Constructor!
                  110 SOUTH ORANGE AVENUK. LIVINGSTON. N. .1. 07039
BRANCHES IN PRINCIPAL CITIES OF
THE UNITED STATES AND AFFILIATES
IN CANADA. LONDON. PARIS. MILAN.
MADRID. TOKYO AND MELBOURNE
       CABLE ADDRESS
REWOP LIVINGSTON HEW JERSEY
      TELEPHONE 533-1100
       (AREA CODE 2011
                                 February 15, 1973
        Mr. E. J. Vidt, Senior Research Scientist
        Westinghouse Electric Corporation
        Research & Development Center
        Beulah Road
        Pittsburgh, Pa. 15230
                                Subject:  Pressurized Fluidized Bed
                                          Combustion Boiler
                                          FW 11-52331
                                          Letter No. hi	
        Dear Mr. Vidt:

        Enclosed please find four (U) copies of the revised estimate based
        upon 2/3 capacity and a reduction of pressure from 350 psig to 170
        psig.  Equipment sizes, with the exception of the boiler, have been
        changed to reflect the lower capacity.

        The reduction in pressure decreases costs $352,000 from the base
        case, or 9J6 of the difference between $13,6liO,000 and $9,730,000.
        The change in capacity represents 9l£ of the above difference or
        $3,558,000.

                                Very truly yours,
                                L. W. K&hnstecher
                                Process Technology Manager
        Enclosures

-------
FOSTER  WHEELER CORPORATION, 110 SOUTH  ORANGE AVE., LIVINGSTON,  N,
                    ESTIMATE SUMMARY
                                                35
J.

«5
1
o
o
I.


CUSTOHE
LOCATIO
SUBJECT

N PlTTS P,uD CM, PA. HATF I7-U-7Z (CI5V).
Pl.ll=-S C\ t O (E C? /\Tl 0 ^ P 1 . A 1 -• T eucer HA 1 AC 4-
,3 56 57 ^ »A 66 £ K $ PA
CODE
1000
2000
3000
WOO
5000
6000
7000
6000
9000



























RECAP
DIRECT MATERIALS
SUBCONTRACTS -HAT1 L S LABOR
SUBCONTRACTS -LABOR ONLY
DIRECT LABOR ( KH)
INDIRECT MATERIALS & TOOLS
INDIRECT LABORS SUPERVISION
PAYROLL BURDEN
HOME OFFICE ( TT1M}
MISCELLANEOUS (l«So It. A^Ctl



TOTAL COST (ACCTS 1000-9000)
ESCALATION
-MATERIALS
-LABOR
-SUBCONTRACTS

LABOR PRODUCTIVITY


TOTAL EST. COST-ON-BOOKS
CONTINGENCY
-MATERIALS
-LABOR
-SUBCONTRACTS
coKnR.ACTon.'s e«c,i»J
Aw& pRocoaiS^e^-
AMb pees FOR tii= 10





)
V
}







)
{
)






)
t
j
eifl?.\»in
Cfl> i,-**
-P-AL
\
A Si >i P P.CS 1- V T 1
SELLING PRICE ^A^^P^ox, \?^T> ^^^^c- )





SAY


p^lSSS
7527
'6^0


300 a


2.008




87



\4-2-ZO


h*\ o ^ ti





1 £\ 'J "? Q


tSOKi(S

\
/
r i\S ^
\
J
\ 4,4^ S

)&4zo


^BA?^
6^06
5*18


7^1 1 Q


14 1 o




7Z



\ \ ^.\o


MOW&





1 1 R I o


K)O)5t=L



l^ Z3


l^^33

\?£4o


CASE I
Vj^^oPSV*
47^1
4o7


IC.IO


Y6 (o




5T2



^4>ci


V^oto»te





V^'l Z n


^ 0 ».^ £



1 2.C|7


9T2."7

17JO



































S




£ xcLu^e-o ', - CATALYST^ CHG>*»C.AI.SJ TAX^S £OYA tries .







-------
                                        OTTO/HI
        WE ^ T i N r, ^ o .^ T
                         4
                                                        Botlnate Date  9-17-72.
                                                        CtJ—hry  Date \2--\\--11.
                                                                         _Of_^L_
                                                                  Pago.
 It.m
 Ho.
               D«8oriptioa
                                        8i»« or Duty
                                                           1000
                                                                   2/3000
Material
 Coat I
Subeontr.
  MftL 8
                                                                             4000
 Labor
[lanhoura
            Proeesa Equipment

         £. O A I
         "t
                                                             ooo
b-lo
              (To A L V4 o p p t. a
                                                                        .0
         C o /x »  S v uo
                                                                            iev)fA-
               HEATER.
                                                                   f-oot.
   1>
         C.OA.U
                fir AS B LewfflL
p\o
             FtUTEg.
fc-io
         COAL E
                                       S*W X 6»' H X 6,' U
                                                                   Q
                                       PeTO.OCA.RB
                                                             ooo
                                                                          o
                                       Q 0 0 T S
                  V\\X
                          , c, =
         Locvc
                                                  OA
         TMJfee>Tog.
>Llo9
                                  14.0?
                                         1  «    1   II
                                         -O XlOO-O
D-IM
t
              KAITE.
                                                                   Q
                                                                                    i
                                                              ooo

-------
                                                   L A
Location ?; T': • • P.l»' - ^ -i.  >'
Tjrp«..Elan* Ptle '^ •.. ov-iv
Eotiaat*  Do..
Botinat*

-------
Pliant
       W£
            5>TiKC.moo^^
Location P\n T^. ... u .  c^ v-u  V'.* .
:M  LAB    Classification.
	 Botiaate No._U
tjrpe Plant             .     .
Capacity   TL.T i=. \ t -\  < \ •=. ^\ £T-.N ; (\\ f\  p
                                              B>£
                                                      Entiaate Pat*  \ o -4-11.
                IT
                                                              .Page	4^ot_*
Code


400
410
421
430
440
450
452
460
Wi
470
|
^•00

I ''JO

700

19X0
Cao
| "50
O'lO

930
r,«.Q
950
960
970
|990











Deseriptioa
Other Material

Civil Work
Earthworki Devateriajr
Pilins '
Concrete Foundations
R-v^Vs, Paving, Tsas'-iff
EloTatod ConerAte Structures
Conorote Yard Pin« Supports
Structural Stool & Plat fores
Stool Yard Pipe Supports
Bnildi&eo
»
Piping ()i>i t \..w ff\ e f^ 3 *.CKIST)

Xor*trv-ionta Cmc< • ^^^'-V'ut. '"*.'•

Klnotrical

Ir^itlition - Pipo
Ir^nXition - Sqnipaont
Painting
?ircproofing

Tenting
C'lt^lTitn ti ChftrvJLc"3,'J
Hiinton^^co Bonipnont
Firo Protection Equip.
Spxirn Pnrtn
Othor Mioo. Equip.




Quantity


—
M4CL *^o
NOMt
^»
—
—
K.\OUls
	
—
	

	

	




_
—
—
tJOKie

	
1&0I4C
v46vae.
slAfiC
140146
i4o«4e

.


Total Othor Hatnrial
Totnl Procano Kqnipriont
Total Direct Ilatla. Sube. & Labor




loop
Material
Cost t













^T-
4S


•^Lt^.

137

I|2.2.S









Z

-








\f\ffS
441*


















ooo
000
....

900

OOO

o*e

- —







ze>o
-
—







£00
100
000,

1
I*

2/300J
Suboe
M&I








1 97
AS
5*



F;

•70

F —







^% ^p
^r ir
93
4*>


—
... _.
	


— --




5*18 <

5"jg




•ntr.
S








poo
ooe
ooo





90O

—





40
Direct
Manbouri




._ .


p 	
F 	



^800
3loc
	

^000

5^ToA


|i»*f o»«»

>00
too
poo


—
----
	


--




&OO

F • --


p-



4t-Oe>

	
—

--





|| ffoco'
0oO




00
Labcr
Coot S







_
	 .


.










—






--
—






\U>ot
Z.4I000240C




1







-
- _















1^







— 1





>0fl
too
too
—\


1

-------
All

-------
0
             FOSTER WHEELER CORPORATION                                REF.  11-52331

                                                                       DATE  April 1973

                                                                       PAGE  A-II
                                      APPENDIX II



                                  EQUIPMENT SPECIFICATIONS
              The following Appendix includes equipment specifications covering:





                  1.   Vessels



                  2.   Coal and Dolomite Receiving and Preparation Systems.



                  3•   Compressors



                  U.   Exchangers


                                                 1W'
                  5.   Instrumentation and Analyzers



                  6.   Piping



                  7.   Vendors Proposals

-------
      FOSTER WHEELER CORPORATION
REF. 11-52331
DATE April 1973
PAGE A-II-1
A-II. EQUIPMENT SPECIFICATIONS

          Equipment List

               The following items are included within the scope of the proposed

          plant.

                              Item No.   	Service	

          REACTOR             R-101       Fluidized Bed Boiler

          DRUMS               D-101       Wet Coal Hopper

                              D-102      Coal Silo

                              D-105      Lock Hopper

                              D-106      Injector Hopper

                              D-10?      Dolomite Receiving Hopper

                              D-108      Dolomite Silo

                              D-109      Lock Hopper

                              D-110      Steam Separator

                              D-111       Dolomite Injector

                              D-112      Spent Sorbent Lock Hopper

                              D-113      Spent Sorbent Lock Hopper

                              D-11U      Primary Cyclone Seal Drum

                              D-115      Primary Cyclone Lock Hopper

                              D-11?      Secondary Cyclone Lock Hopper

                              D-118A     Quench Drum

                              D-llbB     Quench Drum

                              D-120      Cyclone Drum

                              D-121       Main Air K.O. Drum

                              D-123      Injection K.O. Drum

-------
      FOSTER1 WHEELER: CORPORATION

A-II.EQUIPMENT SPECIFICATIONS, (continued);
                              Itemi No•«.    Servica
          T'ANK                TK'-IOT      Fuel. Oil Storage Tank
          EXCHANGERS          E-10T       Compressor Air Cooler
                              Ei-103       Compressor Air Cooler
                              H-101'       Air Heater
                              H-102       Air' Preheater
                              RC-tOT      Spent Dolomite Cooler
                              RK-TOT      Coal Dryer
                              C-101       Main Air Compressor
                              C-103       Injection Air Compressor
                              P-101A&B    Fuel Oil Pumps
                              B-101       Air Blower
                              B-102       Vent Gas Blo-wer
                                          Intake Air Filter
                                          Bag Filter
                                          First Stage Cyclones
                                          Second Stage Cyclones
                                          Primary Cyclone
                                          Wet Coal Conveyor
                                          Dry Coal Conveyor
                                          Coal Elevator
                                          Dolomite Conveyor
                                          Dolomite Elevator
                              CR-106      Spent Dolomite Conveyor
                                                       REE., I1j-5233)1
                                                       DATE.  April. 1973)
                                                       PAGE  A-II-2
HEATERS.

ROTARY COOLER-
KILN
COMPRESSORS'

PUMPS
BLOWERS

FILTERS             F-101
                    F-102
CYCLONES            G-101
                    G-102
                    G-103
MATERIAL CONVENING  CR-101
                    CR-102
                    CR-103
                    CR-10U
EQUIPMENT

-------
              FOSTER WHEELER CORPORATION



        A-II.EQUIPMENT SPECIFICATIONS  (continued)

                                      Item No.

                  MISCELLANEOUS
                                   REF.  11-52331
                                   DATE   April 19?3
                                   PAGE   A-II-3
                  FUTURE
a
2
                          Service
A-101       Instrument Air  Compressor & Dryer

A-102       Purge Air Dryer

SL-101      Flue Gas Silencer

SR-101      Coal Crusher

ST-101      Stack

            Control House

            Compressor House

            Rail Unloading  Shed

            Coal Injection  Shed

A-201       Water Treater

C-102       Main Air Compressor

C-10I;       Turbine Blander

D-122       Main Air K.O. Drum

E-102       Compressor Air  Cooler

E-201       Steam Condensers

FT-201      Cooling Towers

P-201       Booster Pumps

P-202       BFW Pumps

P-203       Cooling Dfeter Pumps

P-20U       Injection Water Pumps

TK-201      BFW  Storage Tank

-------
      FOSTER WHEELER CORPORATION                                REF. 11-52331
                                                                DATE April 1973
                                                                PAGE  A--II-U

A-II.  EQUIPMENT SPECIFICATIONS (continued)

          Vessels

               Pressure vessels and atmospheric drums are included in this section

          on the basis of the specifications noted on the following drawings and

          as given below:

          Item No.    	Service	   Drawing No»



          D-110      Steam Separator                             OP-72U-852A

          D-112      Spent Sorbent Lock Hopper                   OP-72U-8U9A

          D-113      Spent Sorbent Lock Hopper                   OP-72U-8U9A

          D-11U      Primary Cyclone Seal Drum                   OP-72U-85QA

          D-115      Primary Cyclone Lock Hopper                 OP-72l|-8!?1 A

          D-117      Secondary Cyclone Lock Hopper               OP-72U-851A

          D-118A&B   Quench Drum                                 OP-72U-853A

          D-120      Cyclone Drum                                 OP-72U-898&899

          D-121       Main Air K.O. Drum                          OP-72U-85U

          D-123      Injection K.O.  Drum                         OP-72U-860A

               All  pressure vessels shall be designed,  constructed,  inspected

          and tested in accordance with the ASME Boiler and Pressure  Vessel

          Code,  Section VIII,  Division 1, latest revision and  all applicable

          addenda.   Drums which will operate at atmospheric pressure  shall

          generally adhere to  the  requirements of the code, but  actual con-

          struction shall be in accordance'with what  is referred to as "Good

          Commercial Practice."

-------
      FOSTER WHEELER CORPORATION                                REF.   11-52231
                                                                DATE   -Aoril 1973
                                                                PAGE   A-H-5

A-II. EQUIPMENT SPECIFICATIONS (continued)

               The dual layer linings required for some of the vessels shall

          consist of a lightweight insulating castable adjacent to the vessel

          wall to give the desired reduction in temperature and a covering

          layer of dense refractory castable to protect the insulating layer•

          Both linings shall be gunned in place, if possible, and shall be sup-

          ported by anchors welded to the vessel shell.  Casting or trowelling

          of the lining, will be allowed if access prevents the gunning operation

          from being employed.  The lining shall be installed in the vessel

          fabricator's shop.  The curing and drying of the lining installation

          shall also be performed in the shop prior to shipment of the vessels

          to the job.

               The lining thickness requirements are specified on the vessel

          drawings.  The materials shall be as follows, or the equivalent thereof:

          Insulating Castable -          AP green Light Weight Castable VSL-J>0

                                         as manufactured by AP Green Refractories

                                         «•

          Refractory Castable -          Lo - Abrade as manufactured by AP Green

                                         Refractories Co.

-------
FOSTER WHEELER CORPORATION
ITEM NO.

QUANTITY;

PURPOSE;

DESCRIPTION:
SPECIFICATIONS!
                                      REF.  11-52331
                                      DATE   April 1973
                                      PWE   A-II-6
OM-101 Coal Preparation Unit

One (1)

To dry and crush coal to proper size range.
                     Vet coal will be received from an existing' hopper at
                     a size of l*g" x 0".  The coal is elevated, dried and
                     crushed.

                     Supplier's equipment starts at the elevator after the
                     existing feed hopper.  Supplier's equipment at the
                     injection system.
                     1.  Capacity - 120,000 Ibs/hr of wet coal.

                     2.  Maximum moisture- assume 10$ by wt.

                     3.  Coal type - Ohio Pittsburgh No. 8 (see table of properties).

                     li.  Operation - one shift of 8 hrs. per day for five days
                         per week at design capacity.  For operation at maximum
                         capacity of $Q% over design (180,000 Ibs/hr) assume
                         operation for two shifts per day for five days per week.

                     5.  Duty;  a)  To dry coal from 10$ by wt. to 3% by wt.

                                b)  To crush coal from l^g" x 0" with minimum
                                    fines below £00 microns.

                     6.  Turndown required - none.  (Operates  UO hours per week)

                     7.  Materials - suitable for size and type of coal indicated.

                     8.  Location - equipment will be located outdoors in Midwestern
                         USA.

-------
 PAGE NOT
AVAILABLE
DIGITALLY

-------
 FOSTER WHEELER  CORPORATION
                                                           REF. l
                                                           DATE  April 1973
                                                           PAGE  A-II-7
ITEM NO.;

QUANTITY;

PURPOSE:
OM-102 Coal injection unit

One (1)

Coal is continuously fed into reactor at a uniform
controlled rate through multiple feeders.
DESCRIPTION;
SPECIFICATION:
Dry and crushed coal is pneumatically conveyed from
existing storage silos, at a uniform feed rate to a
to a Petrocarb, Inc. or equal multiple injection
method.  The supplier's equipment starts at the storage
silos and ends at the reactor.

1.  Capacity - continuous
    Coal - 33,000 Ibs/hr max.

2.  Coal - V x 0" with 3.35? by wt. moisture

3.  Operation - continuous, 3 shifts per day, 7 days
    per week.

h'  Pressure at reactor (receiver for injection)

    a)  Normal - 170 psig
    b)  Design - 320 psig

5.  Feed Points

    a)  Four (h) active lines
                    6.   Approximate  dimensions  for feeder  lines  about 50  ft.
                        lateral and  hO  ft.  vertical.

                    7.   Turndown required - to  2,200  Ibs/hr  (10# of  A-l Case)

                    8.   Materials -  suitable for continuous  operation with  size
                        and characteristics of  coal indicated.

                    9.   Location - equipment will be  located outdoors in Mid-
                        western USA.

-------
FOSTER WHEELER CORPORATION                                REF.  11-52331-
                                                          DATE  April 1973
                                                          PAGE  A-II-8
A-II.  EQUIPMENT SPECIFICATIONS

       2.  Coal Preparation Alternate

           An alternate quotation Has received for a coal crusher and

       dryer from Williams Patent Crusher and Pulverizer Company, Inc.

       as a possible replacement for part of the Petrocarb Coal

       preparation equipment.  This proposal is included as well as a

       comparison of the estimated coal size distribution from

       Williams and from Petrocarb.  It can be seen that the Williams

       crusher claims a reduction of coal to 0 x 1/U" size with less

       fines than the Petrocarb system.  However, due to the higher

       cost of the Williams  crusher, it was decided to use the

       Petrocarb system.

-------
     WILLIAM*
         IATE>
WENT CRUSHER**/PULVERIZER Cajnc.
                CABLE AOORESS("OU5H£R:ST.LOUIS"
                                                           A-II-9
CRUSHERS
GRINDERS
                                               SHREDDERS
                                               AIR SEPARATORS
                                        TELEPHONE: AREA'CODETl 4 e'n.3348
                                        270l-'272r3-'NORTH BROADWAY
                                        SI. LOUIS, MO., U.S.A. 63102


                                        September 20, 1972
       Foster Wheeler Corp.
       110  South Orange St.
       Livingston, N.J. 07039

       Attention:  Mr. L. W. Zahnstecher
                  Subject:  Your Ref: FW11-52331
                            Westinghouse Research Laboratory
       Gentlemen:
       This  is in reply to your September 1st request for a price
       estimate and information on our coal preparation system.

       Williams can provide a complete engineered package system entirely
       automated, with our patented inert gas system to prevent
       explosions and fires, and because the entire system is under
       negative pressure it is clean and dustless.

       We understand the system capacity and function is to handle
       60 tons per hour of 10% moisture coal, to be crushed from 1%"
       x o to kn x Q with the moisture reduced to less than 3%.

       Based on the coal feed to the system containing 1% or less
       minus 40 mesh (U.S. Std.)  equivalent to 420 microns,  the
       approximate size distribution of the minus V product is as
       follows:
USHERS.GBinOEqaSHREODERS.PUlVERIZERS.ROLLERmiLLS.fllBSEPBBPTOBS.VIBRBTinGSCREEnS.COMPLETE PinnT8.»CCESSORIES

-------
                                                     A-II-10
2     To Poster Wheeler Corp,
                  Date September 20, 1972
Sieve Size (U.S. Std.)

  1/4"
  6 pesh
 10 mesh
 40 mesh
100 mesh
200 mesh
 Cumulative Percent Passing

From Crusher System   From External Screen
     86.7
     54.1
     38.4
     13.5
      4.0
      1.4
100
 62.4
 44.4
 15.6
  4.6
  1.6
From our discussions with Mr. Ed. J. Vidt of Westinghouse we
learned they intend to screen the one-pass crushed product  and
recycle the oversize.  This insures an absolute control^on  100%
passing V top size and avoids over-crushing to result in an
absolute minimum of fines as indicated above.

Please refer to page 4 of the enclosed Bulletin No.  856.  This
illustrates the system we propose to furnish except  that item
(B) Roller Mill will be replaced by an Impact Mill similar  to
that shown by figure 1840- page 9 of the enclosed Bulletin  No.
723.  And item  (D) Spinner Separator will be replaced by a  Venturi
Separator.

Basically the system will consist of the following major
components:

(1) Vibratory Feeder with Automatic Feed Control Panel

(2) #5100 Impact Mill with V-Belt Drive and  200 HP Motor

(3) Venturi Separator
(4) Cyclone Collector, heavy duty vacuum type. Rotary Discharge
Valve, chain drive and 5 HP gear motor.

(5) Main Fan, heavy duty high static type, with drive and  600 HP
Motor.  Rated at 74,000 SCFM.

(6) Air Duct for closed circuit Air System,  including Inert Gas
Duct Circuit.

-------
                                                     A-II-11
       To pogter wheexe,. Corp.                  Date September 20, 1972
(7) Air Heater, 25 million BTU capacity per hour, having
Automatic Ignition, latest Minneapolis-Honeywell Control Panel as
manufactured for Williams Crusher Company utilizing R4138A Flame
Safety Programmer and R7161C VersatroniK indicating high
temperature limit; Automatic Mill Temperature Control with
Partlow Recording Instrument suitable for modulating flame;
Controls mounted in a NEMA 12 Panel/ wired and piped, shipped
as a package including hot air duct to Mill.

(8) Fabric Dust Collector with 11 ounce woven dacron bags
complete with reverse jet blowers, factory assembled blow
ring carriage, housing braced for 16" water gauge internal
static pressure, pre-wired electrical controls for pressure con-
trolled cycling of blow ring carriage; factory assembled
complete with V type hopper; screw conveyor, airlock, and
drive motor.

(9) Auxiliary Exhaust Fan, heavy duty type with V Belt
drive and 250 HP Motor.
Total system price- approximately for estimating $320,000.00

F.O.B. factory.

Shipment approximately 25 weeks.

It is difficult for us to estimate the amount of sulfur
released to the atmosphere, but the dust emmission will be
practically negligible.

 We are represented in your area by Brumitt Associates with
 Mr.  Ron Schmidt at P. O. Box 265, Madison, N.J. 07940 -
 (201)  - 377-2195.

 Please let us know how we can be helpful as you proceed.

                                 Yours very truly,

                       WILLIAMS PATENT CRUSHER & PULVERIZER CO.
                                rJ. P. Hensel
                                 Regional Sales Manager
 JPH/JS

-------
E-465
                                                                 A-II-12
                      ESTIMATED PARTICLE SIZE DISTRIBUTION
                                      OF
                                 PREPARED COAL
    100
1000
  Microns
                                                                             Q.I
 Petrocarb,  Inc.
10/2/72  HR

-------
 FOSTER WHEELER CORPORATION
                                      REF.
                                      DATE    April 1973
                                      PAGE     A-II-13
ITEM:

QUANTITY:

PURPOSE:


DESCRIPTION:
SPECIFICATION:
OM-103 dolomite loading and injection system

One (1)

To unload fresh dolomite from railroad hopper cars and
feeding the dolomite to pressurized reactor through lock
hoppers.
Dry and screened dolomite shall be fed from railroad
spur track to silo (s) for inventory storage.  The
dolomite shall then "be fed from a live shelf bin to
lock hopper.  When the lock hopper is full, the unit
shall be pressurized and feeding to a injection drum.
Dolomite shall then be fed from the injector to the
reactor under pressure and at a continuous rate.

1.  Capacity

    a.  Silo(s) - l800 short tons (approximately two-days
        inventory).

    b.  Dolomite injector - Dolomite injector shall be
        sized for feeding the reactor at a maximum rate
        of 28 ST/Hr at a uniform and continuous rate.

2.  Dolomite Feed

    a.  Dried and double-screened lA" x 28 mesh

    b.  Bulk density 9$ lb/cf.

    c.  Skeletal density - 175 lb/CF

3.  Operation

    a.  Silo (s) - silo shall be designed for intermittent
        operation.

    b.  Feeding the reactor from the lock hoppers must be
        continuous and uniform in the feeding rate.

    c.  Pollution abatement - dust generated during loading
        of the silo and lock hoppers shall be recovered.

-------
 FOSTER WHEELER CORPORATION                                REF. 11-52331
                                                           DATE  April" 1973

     NO:              OM-103 Dolomite Loading (continued)
SPECIFICATION;        U.  Pressure
                          a.  Silo(s)

                              a.  Silo(s)

                                  i)  Normal operation - atmospheric on top head.
                                 ii)  Design-atmospheric on top head

                              b.  Lock Hopper

                                  i)  Normal operation - 170 psig
                                 ii)  Design - 320 psig

                              c.  Injector

                                  i)  Normal operation - 170 psig
                                 ii)  Design - 320 psig

                      5.  Approximate Dimension

                          a.  Railroad hooper cars will be located approximately
                              300 feet from the silo(s).

                          b.  The dolomite injector will be located IjQ feet,
                              laterally, from the silo(s).

                          c.  The dolomite injector will be .feeding the reactor
                              at an elevation of 80 feet above the grade.

                      6.  Turndown Required

                          Required turndown is to  3,573 Ibs/hr (IQg  of A-l  Case)

-------
FOSTER WHEELER CORPORATION                                 REF.  11-52331
                                                           DATE  April 1973
                                                           PAGE  A-II-15

ITEM NO.:              G-101 A, B, C & D  First Stage Cyclones

SERVICE!               Fluidized Bed Boiler

NO. OF STAGE;          One (l)

NO. OF CYCLONES        Four (k)
PER STAGE;

TYPE OF CYCLONE;       Ducan Type 700 VM, size 200 or equal

OPERATING CONDITION;

  Cases                                 A.1           A.2           A.3
  No. of Cyclone in Service             3             2             h
  Fluid                                 	Flue   Gas	—
  Operating Temperature, °F             1,600         1,600         1,600
  Operating Pressure, PSIA              169.7         169.7         169.7
  Atmospheric Pressure, psia             11*.7          ll«7          ll*.7
  Capacity, ACM                       19,750       12,81*7           27.155
  Gas Characteristics (Ex. Dust)
    Density, Lb/CF                      0.231           0.230        0.232
    Average Mol Wt.                    30.16           30.0U        30.30
    Viscosity, centipoise              	0.01*3	
  Dust Loading Grains/CF                28.9           26.7         31.58
  Inlet Velocity, fps                   51^.9           53.5         56.6
  Pressure Drop inches W.G.
    Inlet to Outlet                     15.7           15.0         16.8
    Inlet to Dipleg                     22.6           21.6         2l*.0
  Dipleg Diameter                       	8"	
  Cyclone solid emission grains/ACF      3.005       2.789           3.21*6

Dust Characteristics

Composition
  Ash (Fly ash)                         	60 Wt. %	
  Dolomite                              	10 Wt. %	
  Carbon                                	30 Wt. %	
Particle Size Distribution. grains/CF
 (at inlet to cyclone)
  Less than 1 micron                    	0.05
  1  to 3 microns                        	0.1*79
  3 to 5 microns                        	0.77li
  5 to 10 microns                       	2.161
  10 to 20 microns                      	2.21*2
  20 to 50 microns                      	3.8?2
  50 to 100 microns                     	5.095
  Larger than 100 micron                	5«706

-------
FOSTER WHEELER CORPORATION                                 REF.   11-52331
                                                           DATE    April 1973
                                                           PAGE    A-II-16

ITEM NO.;                G-101 A, B, C & D First Stage Cyclones (Cont'd)
    Apparent Particle Density gin/ml

      Flyash                                 	0.5
      Dolomite                               .-	r.2.8
      Carbon	1.2
    Design Condition

      For internal Ingtallation
        Temperature,  F.                     	2,000--
        Pressure, psi                        	'2—
      For External Installation
        Temperature, °F                      	2,000-
        Pressure, psig                       	-320—
    Notes:

    1.  For external installation the exposed surface of the cyclones, shall
        be kept at 300°F (max.).

    2.  Dimension insdie of the lined icyclone shall be the same as for the un-
        lined cyclone.

-------
 FOSTER WHEELER  CORPORATION                                 REF. 11-52331
                                                            DATE April "1973
                                                            PAGE   A-II-17

 ITEM ND.;                     G-102 A, B, C &. D Second Stage Cyclones

 SERVICE;                       Fluidized-Bed Boiler

 NO. OF STAGE;                 One

 NO. OF CYCLONES               Four
 PER STAGE;

 TYPE OF CYCLONES;             Aerodyne Series S Type III Model 1»500 or equal

 OPERATING CONDITION;

  Cases                                 A.1             A. 2            A.3
  No.  of  Cyclone in Service                3            2             1|
  Fluid                                 ------------- Flue Gas — - --------
  Operating Temperature,  °F             1600            1600          l6oo
  Operating Pressure,  psia.             168.U           168.6         168.1
  Atmospheric Pressure, psia           1U.7           1U.7          l[i 7
  Capacity, ACFM                       198^9           12,908        27839
  Gas  Characteristics  (Ex. Dust)
     Density, Lb/CF                     0.2295          0.2289        '0.2301
     Average Mol Wt.                     30.16           30.0&         30.30
     Viscosity, centipoise              O.Oltf           0.0lj3         0.0li3
  Dust Loading, Grains/CF              2.896          -2-.7761         3.220
  Pressure Drop,  Inc. W.G.
     Primary Gas                         5.5             5.«J           5.5
     Secondary Gas                      21.0            21.0          21 0
     Dip Leg                             +2.0            +2.o          +2.'0
  Cyclone Solid Emission, grains/ACF    0.295           0.27lj         0.321
  Ace. Cyclone efficiency, %           90.1            90. i          90


Dust Characteristics
    ^^^^^"•^^^^^•^"^^•"•^

Compositipn  wt.
  Ash (Flyash)                        __________________ 50
  Dolomite                            __________________ lo
  Carbon                                                ,

-------
FOSTER WHEELER CORPORATION



Case

Particle Size Distribution
Particle Size
1.27
5.55
12. kO
2U.89
U6.62
77.81
81.67
85«5li
89.1*1
93*.27
97.09
100.88
10U.59
108.23
111.77
Less Than
Microns
n
n
n
"
it
n
n
n
n
n
n
n
n
n
Apparent Particule Density em/ml

  Flyash
  Dolomite
  Carbon
Design Condition

For Internal Installation
  Temperature, °F
  Pressure, psi
              REF.  11-523U
              DATE   April iy?3
              PAGE   A-II-13

A.I            A.2
                                                 Ace, Weight Percent
Inlet Outlet
9.62 18.7
57.55 97.2
85.03 100.0
92.58
95.61
96.76
97.29
97.73
98.09
98.37
98.62
98.85
99.06
99. 2h
99. kO


Inlet Outlet
9.57 U8.5
57.29 97.2
8U.91 100.0
92.1i9
95.56
96.69
97.23
97.68
98.05
98.3U
98.59
98.83
99.03
99.22
99.38
	 p g 	
	 1 .<> 	
Inlet
9.73
58.22
85.32
92.80
95.8U
96.93
97. UU
97.85
98.19
98.U5
98.70
98.93
99.12
99.29
99.U5


Outlet
U8.75
97.3
100.0














           ——2

-------
FOSTER WHEELER CORPORATION
                                  REF. 11-52331
                                  DATE  April 1973
                                  PAGE  A-II-19
ITEM;

QUANTITY;
TYPE;  '
TYPE DRIVE;

PROCESS PERFORMANCE;
NOTES;
C-101  Main Air Compressor

One
Multistage Centrifugal
Motor

Fluid                                   Air
Intake Temp., T1                        77
Atmospheric Pressure, PSIA              lU.7
Intake Pressure, PSIA                   1U>3
Discharge Pressure, PSIA                185
Desired Discharge Temp.,  F             500
Capacity MMSCFD (Dry) (No Neg Tol)      .llU.l
Moisture Content at Intake, Vol. %      2.1
(1)  Intake temperature will vary from-10°F to 95°F.  At temperature below
     design the intake capacity will remain constant.
(2)  When Intercoolers are required, allow 5 PSI pressure drop.  Air outlet
     temperature from the coolers 110°F (Min.).

(3)  Vendor to provide complete self-contained oil lubricating system.

(h)  Air filter and intake silencer will be provided by others.

(5)  Buffer seal gas will be made available, if required.

-------
FOSTER WHEELER CORPORATION                                REF.  11-52331
                                                          6ATE  April 1973
                                                          PAGE  A-II-20
ITEM:                 C-103 Injection Air Compressor

QUANTITY:             One

TYPE;                 Single Stage Centrifugal

SERVICE;              a.  Injection and Pressuring air to Petrocarb Unit
                      b.  Aeration air to hoppers
                      c.  Purge air for instruments

DRIVE!                Motor

PROCESS PERFORMANCE;  Fluid                               Air
                      Intake Temp., °F                    100
                      Atmospheric Pressure, PSIA          lU.7
                      Intake 'Pressure, PSIA               180
                      Discharge Pressure, PSIA            315
                      Capacity MMSCFD                     17.0
                      Moisture Content at Intake, Vol.£   Saturated
NOTES:
        (1)  Compressor casing shall be designed for U65 psia discharge
             pressure.

        (2)  Compressor will take suction from Main Air Compressor, C-101.

        (3)  Vendor to provide complete self-contained oil lubricating
             system.

-------
 FOSTER WHEELER CORPORATION                                REF. 11-52331
                                                           DATE   April 1973
                                                           PAGE   A-II-21


ITEM;                F-101 Intake Air Filter

QUANTITY;            One

SERVICE;             Main Air Compressor

PROCESS PERFORMANCE;
                     Fluid                            Air
                     Intake Temp. °F                  -10 to 95
                     Atmospheric Pressure, psig       lU.7
                     Capacity MMSCFD                 HU.U
                     Allowable Pressure Drop
                       across intake line, psi        0.3 max.
                     Allowable Noise Level dBA        90 max. (1)
                     Intake Line Size Inches          1(8 max.

NOTES;
       (1)  The noise level of the suction line shall be kept at 90 dBA at
            less at 10 feet from air intake.  If necessary, an intake silencer
            shall be provided.

       (2)  Total pressure drop of the intake filter and silencer should not
            exceed 0.3 psi.

       (3)  The intake air filter shall have weather louvres.

-------
 FOSTER WHEELER CORPORATION
                                                                                           A-II-22
                                                                                PUMP PROCESS DATA
CUSTOMER   Westinghouse Research  Laboratory
            Pittsburgh. Pa.
            P-101  A&B
LOCATION
ITEM  NO.
SERVICE
SPARE ALSO COMMON TO  ITEM
             JOB  NO	
             SHEET —L
                                                                        11-52331
OF
                                                                             1
            Fuel  Oil Pump
                                                       REV.
                                                       DATE
                                                             BY
   PUMP TYPE:    []  CENTRIF.    0 RECIP.  POWER Q RECIP.  STEAM Q ROTARY
                                                         one
   NUMBER OF PUMPS REQUIRED:  Two

   TYPE OF DRIVER:     Motor
                                        OPERATING

                                        OPERATING
               one
  SPARE

  SPARE
                                                                               METERING
                                                                                   one
                                         one
                                        DUTY:  D CONTIN.      D INTERMITT .«  APPROX.,
                                                                                   2080
                                                                                          HRS/YR.
                                 PROCESS  REQUIREMENTS PER  PUMP
 OPERATING CASE
                                      Desii
                                                                              MINIMUM
                                                                              FLOW CASE
                                                                                                  JSE
 LIQUID
                                      No.
                                      Fuel Oil
 PUMPING TEMP.: NORMAL
                                  OF
                                        130
                EXPECTED MAX.
                                        130
 SR.GR. 9 P.T.:
                      RATED (MIN.)
0.03
                EXPECTED .MIN.
 VAPOR  PRESS. 9 P.T.
                               PSIA
                                          0.1
 VISCOSITY 9 P.T.
 CAPACITY « P.T.:
                                CKS
                    REQUIRED U.S. GPM
                      NORM. U.S. GPM
 DISCH. PRESS.;
                      REQUIRED  PS10
 SUCT. PRESS.:
                      REQUIRED  PSIG
 DIFFERENTIAL PRESS.
                (MAX.  POSSIBLE) PSIG
                                P5I
                                        ISO
 DIFF.  HEAD (CENTRIF.PUMPS  ONLY)   FT
 HPSH AVAILABLE
                                 FT
 CORROSION/EROS ION FROM
                                        Nil
 SPECIAL DETAILS
 FLOW CONTROLLED BY
                           LC
                                          TC
                                                                                     D OTHER
 METHOD OF STARTING SPARE PUMP;
                                      LJ  MANUAL	D AUTOMATIC
 DRIVER STEAM: INLET
              EXHAUST
 NOTES:
MATERIALS RECOMMENDED
                                          CASING
                                 INTERNALS

-------
 FOSTER WHEELER CORPORATION                                 REF.  11-52331
                                                           DATE  April 1973
                                                           PAGE  A-II-23


 ITEM:               RC-101  Spent Dolomite Cooler

 QUANTITY;           One (1)

 PURPOSE;            To cool spend dolomite and fly ash from various look hoppers.

 DESCRIPTION;        Spend dolomite at elevated temperature and pressure will be
                    fed first to the lock hoopers.  Periodically the lock hopper
                    will be depressured  discharging the dolomite into the
                    spent dolomite cooler.  Fartciulate (fly ash) recovered
                    from various cyclones will also be discharged to the
                    appropriate lock hoppers for loading to the same cooler.

 SPECIFICATION;

                                       Spent
                                      Dolomite      Fly Ash        Design

 Operating Temp., °F (Inlet)           1,750          1,600
 Operating Pressure                    Atm.           Atm.
 Design Temperature, °F                2,000          2,000         2,000
 Design Pressure                       Atm.           Atm.          Atm.
 Capacity, TPH (Normal)                15.75          2.3U
 Capacity, TPH (Design)                21.3           3.2           2l|.5
 Desired Cooler Outlet Temp., °F       300 (Max.)     300 (Max.)    300 (Max.)
 Particle Size
                                      ^' x 0
 Less than 20 microns                                 28 Wt. %
          20-50 microns                              19 Wt. %
          ^0-100 microns                             25 Wt. %
Greater than 100 microns                             28 Wt. %

Particle Bulk Density, Lb/CF            95           31

NOTES;

 1.  In order to protect the down stream equipment, the outlet temperature of
    the spend dolomite cooler must not exceed 300°F at the rated capacity of
    2lu5 TPH.

2.  The cooler shall be designed to handle very fine particles from spent
    dolomite and/or fly ash.

3.  Cooling water to the unit will be available at 85°F and 50 psig.  Cooling
    water return shall be restricted to 12QQF.

-------
FORM NO. 135-128 A
   MATERIAL   REQUISITION
    FOSTER WHEELER CORPORATION
110 SOUTH ORANGE AVENUE, LIVINGSTON, N. J.
    A-II-21
  SHELL &  TUBE
   EXCHANGERS
PAGE  1 OF 1
CONTRACT NO. 11-52331 | REQ'N. NO. | DATE
CUSTOMERS NAME
Westinghouse Research Lab.
| LOCATION Pittsburgh, Pa.
9/13/72

SUPERSEDED BY
CHANGE NO.
DATE
SERVICE OF UNIT
C- I C-2 C

Compressor Air Cooler
SIZE UU» x 18'0" TYPE A-J-S
SQ.FT. SURF. /UN IT 'fffff 9700 SHELLS/UNIT

PERFORMANCE

FLUID CIRCULATED
TOTAL FLUID ENTERING
VAPOR
LIQUID
STEAM
HON-CONDENSABLES
FLUID (VAPORIZED)(CONDENSED)
STEAM CONDENSED

GRAVITY
VISCOSITY
MOLECULAR WEIGHT Vapor Mix
SPECIFIC HEAT
THERMAL CONDUCTIVITY
LATENT HEAT
TEMPERATURE IN
•TEMPERATURE OUT
OPERATING PRESSURE. INLET
NO. PASSES PER
SHELL
VELOCITY
PRESSURE DROP -
ALLOW. ICALC'D.
FOULING RESISTANCE, MIN.
HEAT EXCHANGED
TRANSFER RATE -
SHELL
-3 C-4 C-5

C-6

ITEM NO. E-101
nSfiyj1 CONNECTED IN

one SQ.FT. SURF. /SHELL 'ffrff
OF ONE UNIT
SIDE
Air
3&6.50U
361 .666
LB/HR
LB/HR
LB/HR
LB/HR
U83H
LB/HR
LB/HR
LB/HR


28.6
BTU/LB-°F
BTU/HR-FT-OF
BTU/LB
385
110
°F
OF
35 (P£H)(PSIQ)
Divided Flow
FT/SEC
li.O PSI I
0.002
- BTU/HR. 2L. LOO. 000
SERVICE 28.08
PSI


TUBE SIDE
Cooling Water
977 .200
LB/HR
LB/HR
(195U GPM) 977.
200 LB/HR
LB/HR
LB/HR
LB/HR
LB/HR



BTU/LB-°F
BTU/HR-FT-OF
BTU/LB
85
110
50
Two
5.9
10.0 PSI I
°F
OF
fcBSWHPSIG)

FT/SEC
PSI
0.002
MTD CORRECTED-OF 89.6
CLEAN


CONSTRUCTION OF ONE SHELL
DESIGN PRESSURE
TEST PRESSURE
DESIGN TEMPERATURE
TUBES C-STL
SHELL C-STL
75
Per Code
L35
PSIG
PSIG
OF
75
Per Code
160
PSIG
PSIG
OF
(3) NO. 1110 O.D. 3/U" BWG1U flm?? LENGTH18'0» PITCH 1"
Lh" I.D.
CHANNELXfflUfiSJKKX c-STL
TUBESHEET - STATIONARY C-STL
BAFFLES - CROSS
BAFFLES - LONG
TUBE SUPPORTS
C-STL TYPE DHL SEGM
TYPE
SHELL COVER C-STL (Mt&fi)(REMOV)
CHANNEL COVER C-STL

TUBESHEET - FLOATING C-STL
FLOATING HEAD COVER C-STL
IMPINGMENT PROTECT I ON Place Shell

Inlet on
vapor belt - leave K.O. on bottom for
TUBE TO TUBESHEET JOINT Expanded
exiting vapor

GASKETS
CONNECTIONS - SHELL SIDE IN 30"
CONNECTIONS - TUBE SIDE IN 10"
CORROSION ALLOWANCE - SHELL SIDE 1/8 IN
CODE REQUIREMENTS ASME VHI-Div. 1
OUT (2) 22" RATING 150
OUT 10" RATING 150
#RF
#RF
TUBE SIDE 1/8 IN.
TEMA CLASS B

REMARKS: 1 NOZZLE & SUPPORT LOCATION TO' BE AS NOTED ON F.W. STD. 2IBII.I
2 FOR GENERAL NOTES REFER TO REQ'N.
WHICH IS AN INTEGRAL PART OF THIS REQ'N
(3) Wolverine finned tube (19 F/I) #60-195065 or equal





-------
FORM NO. 135- 128 A
   MATERIAL   REQUISITION
    FOSTER WHEELER CORPORATION
110 SOUTH ORANGE AVENUE, LIVINGSTON, N. J.
   A-II-25
  SHELL & TUBE
   EXCHANGERS
PAGE  1   OF 1
CONTRACT NO. 11-52JJ1
CUSTOMERS NAME Westinghouse Research Lab.
I REQ'N. MO. | DATE
|LOCATIONPittsburg, Pa.
9/2/72

SUPERSEDED BY
CHANGE NO. C- 1 C-2
DATE
SERVICE OF UNIT Comp. Air Cooler
SIZE 21" x 20 "0" TYPE AES
C-3 C-4 C-5

C-6

ITEM NO. E-103
7&&V CONNECTED IN
SQ.fT.SURF./UNIT^ffftf' 96li SHELLS/UNIT one SQ.FT. SURF. /SHELL (Jffi

f 96U
PERFORMANCE OF ONE UNIT

FLUID CIRCULATED
TOTAL FLUID ENTERING
VAPOR
LIQUID
STEAM
NON-CONDENSABLES
FLUID (VAPORIZED)(CONDENSED)
STEAM CONDENSED
GRAVITY
VISCOSITY
MOLECULAR WEIGHT
SPECIFIC HEAT
THERMAL CONDUCTIVITY
LATENT HEAT
TEMPERATURE IN
•TEMPERATURE OUT
OPERATING PRESSURE. INLET
NO. PASSES PER SHELL
VELOCITY
PRESSURE DROP - ALLOW. JCALC'D.
FOULING RESISTANCE, MIN.
SHELL SIDE
Air
h0612

LB/HR
LB/HR

536


U03
LB/HR
LB/HR
LB/HR
LB/HR
LB/HR







BTU/LB-°F
BTU/HR-FT-OF
BTU/LB
500 °F
100
OF
170 (mSHPSIO)
One

li PS
0.002
HEAT EXCHANGED - BTU/HR. h. 120. 000
TRANSFER RATE - SERVICE hi. 8

FT/SEC
1 PSI

TUBE SIDE
C.W.
27U.667

5U9 GPM

LB/HR
LB/HR
LB/riR
LB/HR
LB/NR
LB/HR
LB/HR



BTU/LB-°F
BTU/HR-FT-OF

85
100
50
Two
BTU/LB
OF
OF
COUCH PSIG'

FT/SEC
6 PSI I
0.002
MTD CORRECTED-jPJ °F 97.5
CLEAN
PSI



CONSTRUCTION OF ONE SHELL
DESIGN PRESSURE
TEST PRESSURE
DESIGN TEMPERATURE
200
PSIG
PSIG
600
OF
TUBES CS NO. 252 O.D. 3/li BWG 1h W
SHELL CS 21"I.D.
CHANNEL XKJOHBSEK CS
TUBESHEET - STATIONARY CS
BAFFLES - CROSS CS TYPE SEGM'T
BAFFLES - LONG TYPE
75

150
PSIG
PSIG
OF
ft LENGTH ?0'0" PITCH 1" So.
SHELL COVER CS *£
SDERlfREMOV)
CHANNEL COi/ER CS
TUBESHEET - FLOATINGCS
FLOATING HEAD COVER CS
IMPINGMENT PROTECTION Yes


TUBE SUPPORTS
TUBE TO TUBESHEET JOINT Rolled
GASKETS
CONNECTIONS - SHELL SIDE IN 10"
CONNECTIONS - TUBE SIDE IN 6"
CORROSION ALLOWANCE - SHELL SIDE 1/8 IN
CODE REQUIREMENTS ASMF. VTTT Div. 1
OUT 1QH RATING 300
OUT 6" RATING 1 50
TUBE SIDE 1/8 IN
TEMA CLASS R
# RF
# RF


REMARKS: I) NOZZLE 4 SUPPORT LOCATION TO BE AS NOTED ON F.W. STD. 2IBII.I
2) FOR GENERAL NOTES REFER TO REQ'N.
WHICH IS AH INTEGRAL PART OF THIS REO'N





-------
FOSTER WHEELER CORPORATION                                REF. 11-52331
                                                          DATE    April 1973
                                                          PAGE    A-II-26
ITEM NO.;           A-101 Instrument Air Compressor & Dryer

QUANTITY:           One (1)

SPECIFICATION;      Complete instrument air package system including air com-
                    pressor, filter, water trap, dual automatic pressure switch
                    dryer and all necessary attenting equipment.

                         Air capacity/ SCFM                      70Q
                         Ambient Temperature:                    95 F
                         Moisture content of Intake Air          saturated
                         Dew point of instrument Air             -UO°F
                         Atmospheric Pressure                    lit.7 psia
                         Compressor Drive                        motor

                    The instrument air shall be free of foreign matter and
                    dried to -ljO°F dew point at all time.  The instrument
                    air shall be made available at the battery limit at 100
                    psig and 100°F.

-------
FOSTER WHEELER CORPORATION
                                        REF.  11-52331
                                        DATE  April 1973
                                        PAGE  A-II-27
ITEM;

QUANTITY;

SPECIFICATION;
 A-102 Package Purge Air Dryer
 one
 Complete instrument purge air dryer including feed gas
 cooler, oil filter, dual automatic pressure switch
 dryer and all necessary attenting equipment.
                    Air Capacity, SCSM

                    Inlet Temperature, °F

                    Inlet Pressure, psia

                    Moisture Content

                    Dew Point of air Required,  °F
                                         1,000

                                           200

                                           U65

                                         Sat.

                                           -liO
NOTES;
1 .  An air cooler shall be provided upstream of the dryer,
    complete with separator and water trap.

2.  The purge air shall be free of foreign matter and dried
            dew point at all times.
                   3»  Cooling water will be available at 85 F and 50 psig.
                       Cooling water outlet temperature should not exceed 120°F.

-------
   FOSTER WHEELER  CORPORATION                                 REF. 11-52331
                                                             DATE   April 1973
                                                             PAGE    A-II-28

A-II.  EQUIPMENT  SPECIFICAnONS (continued)

      5. Instrumentation & Analyzers

            The purpose of instrumentation is to control the process, to

      indicate the performance of the unit and to effect safe action in the

      case of emergency conditions.

            Instrumentation shall be as shown on Engineering Flow Diagrams

      OP-721-l£3, )&k and 1^6.  Instruments and controls are identified by

      a system of letters (and numbers) generally in accordance with the In-

      strument Society of American Standard Sjj.l  Additional symbols, if used,

      will be explained by suitable notes on the flow diagrams.  Pneumatic

      transmission shall be utilizedj however, provision shall be made for

      computer data logging.

            The instrument panel shall be full graphic, with miniature in-

      struments and a maximum instrument density of 2.5 maximum per lineal

      foot.

            Analyzers shall be provided for measuring the composition of flue

      gases from the Reactors and the flue gas leaving the Quench Scrubber.

      Also, the ash from the boiler and the cyclones shall be analyzed to

      determine the extent of conversion of the coal.  The components to be

      analyzed are listed on the flow diagrams at the required points.

            The selection, sizing and design of relief valves or other reliev-

      ing systems shall be generally in accordance with API Standards, ASME

      vessel codes, or applicable piping codes.

            Instruments and their connections shall be located for maximum

      convenience in operating and servicing the instruments, and shall be

      oriented so as to avoid obstruction of aisles and platforms.  Control

-------
   FOSTER  WHEELER CORPORATION                                 REF. 11-52331
                                                             DATE   April 1973
                                                             PAGE   A-II-29
A-II. EQUIPMENT SPECIFICATIONS (continued)
      5.  Instrumentation & Analyzers (continued)
      valves shall be accessible  from grade or platforms.  Local pressure
      gauges, dial thermometers and test veils shall be located so  as  to
      be  at a visible level, and  test points shall be readily accessible.
      All instruments requiring adjustment must also be accessible  for
      servicing from grade, walkways, ladders or  platforms.   Accessibility
      from grade may be from a portable ladder and,  for transmitters,  from
      a portable platform.
      6.  Piping
             Piping, the general  arrangement of same with  respect to equip-
      ment and instrumentation, shall be as shown on Engineering Flow  Diagrams
      OP-721-li33, OP-721-lj2U and  OP-721-U26.  As  a minimum requirement,  the
      design of piping shall be in accordance with the  latest revision of the
      Code for Pressure Piping, ANSI B31.3.
             Materials of construction for pipe lines and  equipment are  noted
      on  the Engineering Flow  Diagrams listed above. To explain the symboli-
      zation utilized for each pipe line,  the following example is  employed:
                      	3"  - 300# CS-1	
                               (600°F - HCJ
             Above the line, in order:
               a) Line size (3")
               b) Nominal ANSI rating for  flanges (300#)
               c) Material specification (CS)
               d) Corrosion allowance (l)
             Below the line, in order:
               e) Operating temperature, usually  maximum (600°F)
               f) Insulation requirement (HC)

-------
   FOSTER WHEELER CORPORATION                                REF.   11-$2331
                                                             DATE   April  1973
                                                             PAGE     A-II-30
A-II. EQUIPMENT  SPECIFICATIONS (continued)
      6. Piping  (continued)
             For identification of all symbols on the flow diagrams, the
      following  represent a further breakdown of the symbols:
             ANSI Ratings
             l£0#    - Equivalent to l£0# HF
             300#    - Equivalent to 300# RF
             2$00#   - Equivalent to 2$00# RTJ
             2!>00#+  - Above the requirements of 2$00# RTJ.  A review of
                       the nominal 2J?00# rating would be necessary to
                       determine what changes, if any, should be made to
                       existing standard dimensions to make the 2£OQ# RTJ
                       rating suitable for the pressure and temperature
                       conditions.
             SPCL.   - Special considerations required for piping (see
                       below for further data).
             Materials
             CS      - Carbon Steel
             1% Cr   - 1^6 Chrome, ^ ifcly
             Corrosion Allowances
             1 - Nominal, equal to .0£" for carbon steel, .03" for alloy
             2 - 1A6"
             3 - 1/8"
             li - VU"
             Insulation Requirements
             NI - Not to be insulated
             HC - To be insulated for heat conservation
             PP - To be insulated only where required for personnel (burn)
                  protection

-------
   FOSTER WHEELER  CORPORATION                                 REF.   11-52331
                                                             DATE   April 1973
                                                             PAGE   A-II-31

A-"II.  EQUIPMENT SPECIFICATIONS (continued)

     6. Piping (continued)

            The line sizes  and operating  temperatures as given  for each line

     are self-explanatory.

            With  reference  to the above rating classification designated as

     "SPCL", this particular classification has been used for pipe lines

     operating at high internal temperatures.  Such lines will  require  a

     dual layer lining and  should consist of a layer of lightweight insulat-

     ing castable adjacent  to the pipe wall, to give a desired  reduction in

     metal temperature, and a covering layer of dense refractory castable

     to protect the insulating layer.  Both layers must be gunned  in place

     and supported by anchors welded to the pipe wall.  Casting or trowelling

     of the lining is allowed if access prevents gunning.

            Recommended materials and thicknesses are as follows:

               a) Insulating Castable

                  VSL-£0 as manufactured by A. P. Green Refractories

               Co.  Thickness of layer - $%".

               b) Refractory Castable

                  Lo-Abrade as manufactured by A. P. Green Refractories

                  Co.  Thickness of layer - J&§".

               c) Anchors

                  £/l6" diameter Nelson studs, Type 321 stainless steel,

               welded to pipe wall,  with £/l6" diameter refractory clips

               (see anchor detail on vessel drawings where shell requires

               similar dual layer lining) and heavy hex nuts, Type 310

               stainless steel,  attached to stud.

-------
   FOSTER WHEELER CORPORATION                                REF.   n-#331

                                                            DATE   April 1973
                                                            PAGE   A-H-32


A-II.  EQUIPMENT SPECIFICATIONS (continued)

     7. Vendors' Proposals

            Included in this section are several of the vendors'  quotations

     that were received in connection with requests for price and engineer-

     ing data for the various equipment items.  Wherever the information was

     useful for further descriptive purposes, it has been made a part of

     the process and mechanical specifications for the individual items of

     equipment.

-------
                                                                         A-II-3J
              PETROCARB, INC. zso BROADWAY. NEW YORK. N Y 10007
         CABLE ADDRESS "CABOCARB* NEW YORK

                   207-esto
                                                       November 8, 1972
 Foster  Wheeler Corporation
 110 South Orange Avenue
 Livingston,  New Jersey 07039

     Attention: Mr.  L.  W.  Zahnstecher,  Process Technology Manager
      Subject: Coal Preparation and Injection System and
                Dolomite Injection System (Ref. No. 11-23351)
                Petrocarb  Projects E-465 and E-467	

 Gentlemen:

 This will  confirm our  telephone conversation concerning our revision of
 costs in  connection with  the subject projects.  We have reviewed our estimate
 of the  coil  preparation and injection  system as well as the dolomite injection
 Bystem.

 The pre-blending of coal  and dolomite  have been eliminated.  The coal will
 be fed  batch-wise from the upper "live shelf" directly into the "storage
 injector".   A special  valve will be used to control the batch  of coal and
 will receive its impulse  to open by the cycle logic and will close based on
 an impulse  from a special probe in the storage injector.

 The revised  estimated  installed cost of the coal injection system is $425,000.00.
 The primary  advantage  of  this change is that the live shelf can contain a much
 greater weight of coal or,  if desired, the coal storage silo could be reduced
 in total  volume and height.   This is of course dictated by your desired storage
 volume.

 The dolomite bin, steel supports, foundations, and bucket elevator will not
 be needed since this equipment is being replaced by the dolomite system referred
 to in our letter of September 6,  1972.  This change results in a credit of
 $70,000.00 which changes  the coal preparation system estimated cost to
 $730,000.00  with a  total  for coal preparation and injection of $1,155,000.00.

 Our earlier  estimate of $590,000.00. for the dolomite system is still applicable.
Please let us know  if we  can be  of further service.-
                                                      Very truly yours,
HRrjml
cc: Mr.  R.  W.  Bryers
Harold Reint
President

-------
                                                            A-II-3U
"
  DUCON
     DUCON  CO!M!PANY,  INC.
.EAST SECOND STREET •• (M.IN.EOUA. 'NEW VY*ORK 1I15O1
TEL1 516 741-61OO • CABUEt (DUCON iMINEOLANY • TWX <51O .222-0861
                                       .September 19,  1972
   •Foster Mheel-er Corp..
   110 South Orange  Ave.
   Livingston,, ;New -Jersey
   .Attention:  .'Mr.. Chen
   .Subj.ect-:  Customer .Reference 'Number F.WC  11-52.33,1
             Ducon Proposal P72-437
   !Dear Mr. Chen1:
   In response to your  letter >of' September  >6.,  197,2., I ihave
   enclosed our .budgetary estimate £or four !(4!) Ducon YM '700
   Size 200 (Cyclones -along with icop&es of our  Engineering
   Design iData .Sheets  (Tables 1-6') outlining ;expected Cyclone
   operating results for  your conditions,.
   Design Data For  External Installati
-------
THE DUCON COMPANY. INC.                                  A-II-3J?

                              -2-
   Ducon Proposal P72-437

   The estimated price for four (4) Ducon VM 700 Size 200
   Cyclones is
   Eighty to Ninty Thousand Dollars	($80,000 - $90,000)
   Our Granular Bed estimate will be forthcoming.
                                      Sincerely,
                                      THE DUCON COMPANY, INC.
                                      D. Buzzelli
   DB:aw

-------
                                                          A-II-36
             THE  DUCON COMPANY, INC.
I'JCDN        i«7 i.Ai.r t,f_c-.oNi> :vir
-------
PROGRAM: BOCYIO
                                           DATE: 10/20/72
                    THE  DUCQN m.  INC.
                   147  F.  SECOND STREET
                   KJLNLOLA,  N.Y.  J I50t
                                                                   A-II-37
CUSTOMER: FOUIL

CUBIUMLk KEFF.KCNCE NUMBER:  I-MC ll-L.1'331

DUCON REFERENCE NUMDER! H72-43/

                       TABLE  I

   DUCON CYCI.DNE OPERATING  ANLi Dl 'H-IN DATA SHEET

CYCLONE SELECTIONS NO. OF STAGES
TOTAL GAfi FLOW
TOTAL GAS FLOW AT' OPERATING CONDITION
OPERATING GAJ5 UIINSJTY 6> COND.
OFF-RATING VIUCU5JIIY  (4 COND.
OPERATING tirtii TLMPF-RrtTURE
OPERATING liAU I'KIZSRDKE
PART I CUE DENSITY
OPF.kAT I NO UUL1LH INLET LOADTMO
OPERA T] NO QOL1L5J INLET LOAIUNl)

CYCLONE GTA13ES
CYCLONE SIZE
CYCLONE IYPE
CYCI ONE MO-NIL
NO. 01" CYCLONES
OPERATING DAS FLOW PER CYCLONE
CYCLONE INLET VI LOCITY
        KALI AT I ON VELOCITY
        FRACTIONAL EFFICIENCY  CURVE NS.
        OUTLFI  TO INLCT RATIO
           iOJillUE UROP
        mp-i.ru SUCTION
        DIP-LCD DIAMETER
        J10L1D3 RATE.
        SULIDO LOliS  RATE
        SOLIDS I. Ml Gf. JON
CYCLONE
CYCLONE
CYCLONE
CYCLONL"
CYCLONT.
CYCLONE
TOP-LEG
CYCLONE
CYCLONE
ACC. CYCLONE. Ll> J CIENCY
OUTLET PARTICLE  DISTRIBUTION 01  STAGT. 1
                                                   37-/99D
       LPS/HR
       ACFM
       LUS/CF
       cr
       DEG.F.
       I'UTA
       I.DS/CF
       LPS/HR
       (3RA1NG/ACF
                                                   0.2320
                                                   0.0430
                                                      1600
                                                   1A9.70
                                                     - 4?. 0

                                                     31'.60

                                                     FTRJiT
                                                      200
                                                      VM
                                                      700
  A709 ACFM
  56.A FT/fiCC
  2:i.O Fl/GFiC
  46.4
  I . 50
  16.0 IN.WO.
  24.0 IN.WG.
     0 IN.
  1.31 LK8/SEC-SG.FT.
7GG.57 LDG/HR
 3.246 GR/ACF
 09.73 7.

PAP f
1 1
















1C! E SIZE
;. ; THAN
1 .27
'...ns
II1. 40
">4 . JJ9
46.A'.»
V7 . Ji I
{(1.67
!i:).54
tlV.41
VJ.1'7
v/,09
100.00
104.-J9
lOJt. 23
ill.//
INLET
ACC. Ul)T.
PERCliNT
1.0
A.O
11.0
16.0
21.0
IV). 0
31.0
36.0
41.0
4A.O
Sl.O
56.0
61.0
66.0
7i.O
OUTLF.T
ACC. UGT
PIL'RCENT
9. 7 A
50.2?
on. 3?
92.00
95.04
96.93
97.44
97.05
90.19
90.45
90.70
90.93
99.12
99.29
99. 41,

-------
PROGRAM: BOCYIO
DATES 10/20/72
                    THE  DUCON  HO.  ]NC.
                   147  E.  SECOr'Ji  j:TR' ET
                   WNEQLA»  N.Y.  U'-Ol

CUSTOMER! FOSTLK  UHCl '  > r'

CUblOMLR REFLRErtCE NllnuEk: F'WU il-b >31

DUCON REFERLHl.l£ NUrtfcLK!  P72-43/

                       TABLE

   DUCON CYCLONE  OPERATING ANji itKJGH DATA SHEET

CYCLONE SELECiIQN: NO. OF STAGE!.
TOTAL GAR FLOW
TOTAL CAS FLOW AC OPERATING  CONlIT10N
OPERATING GAG DENSITY  @ COND.
OPERATING VISCOSITY @  COND.
OPERATING OAS flTMPEKATURE
OPLRATJNO GAG PRESSURE
PARTICLE DENSITY
OPERATING SOL1DB  INI.LT LOADING
OPERATING SOL JDS  JNLLT LOADING

CYCLONE STAGES
CYCLONE SIZE
CYCLONE TYPE
CYCLONE MUHKL
NO. OF CYCLONCy
OF-ERAI ING GAS FLOW PER CYCLONE
CYCLONE INLtl VELOCITY
CYL:I ONE SALTATION VELOCITY
CYCLDNE FRA'CUOHAL Q FICIENCY  CURVF.  N J.
CYCLUNi: mJTLFf TO INI F.I RATIO
CYCLONE PRESSURE  DRUH
CYCLONE LUI'-LLG SUCTION
CYCLONE PIP-LEG DIAMLTE.R
D3P-LCG SOLIDS KATE
CYCLONE SOLIDS LOSS RATE
CYCLONE SOLIDS EMISSION
ACC. CYCLONE EI-FICCCNCY

OUTLET PART1ULK DISTRIBUTION OF STAGF 1
                       A-II-38
                               PAI-T1CI.F SI7E
                                 LllSfi 1HAN
                                     1.J7
                                     5.S5
                                     12.40
                                     24.89
                                     46.6 '
                                     77.01
                                     HI.67
                                     85.54
                                     89.41
                                     93.27
                                     97.09
                                   100.83
                                   104.59
                                   108.23
                                   111.77
               LBS/HR
               ACFM
               LBS/CF
               CP
               HEB.F.
               PS1A
               LDS/CF
               LDS/HR
               GRAINS/ACF
17H059
 3 2047
0.2310
0.0430
  1600
169.70
  42.0
  2740
 2A.70

 FTkBl
   200
   VM
   700
          64,>4 ACFM
          53.5 FT/SEC
          22.0 FT/SEC
          4/.4
          i.r»o
          lb.0 IN.'UG.
          21.7 IN.WG.
             0 IN.
          1.00 LD5/SCC-SQ.FT.
        307.11 LDS/HR
         2.709 Gk/ACF
         Q9.b?i X
        TNLET
      ACC.  UGT.
       PERCtNT
          1.0
          A.O
         11.0
         16.0
         21.0
         26.0
         31.0
         36.0
         41.0
         46.0
         Cl.O
         56.0
         61.0
         66.0
            OUTLET
           ACC. WOT.
            PERCENT
              9.5/
             57.2V
             04.91
             92.49
             95.56
             96.69
             97.23
             97.60
             90.00
             98.34
             90.59
             98.83
             99.03
             99.22

-------
PROGRAM: BOCYIO
DATE: 10/20/72
                     THE  DUCON  CO.  'MC.
                   14,'  F.  SECOND  Sfl ' F.I
                   h]NE.OLA»  N.Y.  J Kj

CUS'lOMEk: FOSTER WIOLLrt

CUSTOMEK REFLRENCE rtllhUERs I  Wlv I I-Ij

DUCON REFERENCE NUMHERs  P72-43'

                       TAHLE

   DUCON CYCLONE OPERATING AND DL'filNN DATA SHEET

CYCLONE SELECTION: NO. OF STAGES
TOTAL GAS FLOW
TOTAL GAS FLOW AT  OPERATING  CONDITION
OPERATING GAS DENSITY  Q  COND.
OPERATING VISCOSITY.  @  COND.
OPERATING GAS TEMPERATURE
OPERATING GAS HtEGSURE
PARTICLE DFNStTY
OPERATING SDLms INLET LOADING
OPERATING UOI.TUS INII.T LOADING

CYCLONE STAGES
CYCLONi: 55IZF.
CYCLONE TYPE
CYCLONE MOIiEL
NO. OF CYCLONES
OPERATtNG DAI, FLOW PER CYCLONE
CYCLONE INLET VELOCITY
CYCLONE SALTftTION  VELOCITY
CYCLONE PRAC'i TONAL FFF-ICIENCY  CURVE NO.
CYCLONE DUTI I T TO  INI.H  RATIO
CYCLONF. h'RLSSURE DROI'
CYCLONE HIP-LCG SUCFLDN
CYCLONE HIP-LEG DlAMRfER
DIP-LEG SOLTDS RATE
CYCLONE HOLIUS LOGG  RATE
CYCLONE SOLIDS EMISSION
ACC. CYCLONE EFFICIENCY

OUTLET PARTICLE DISTRIBUTION OF BTnOE 1
                                                                  i-n-39
                               PAKCYCLE  SIZE
                                  I F :>«J  THAN
                                     1.27
                                     5.55
                                     J2.40
                                     24.09
                                     46.62
                                     77.81
                                     81.67
                                     05.54
                                     09.41
                                     93.27
                                     97.09
                                    100.Ill)
                                    104.59
                                    JOU.L'3
                                    I 1.1 .V/
        273735
         19750
        0.2310
        0.04'JO
          1600
        169./()
          42.0
          409'J
         20.90
LBS/HR
ACFM
LBS/CF
CP
FiEG.F.
PS FA
LPS/CF
LB'J/HR
GUAING/ACF
         FIRST
           200
           VM
           700
             3
          61183 ACFM
          54.9 FT/SEC
          22.0 FT/SEC
          47. J
          1..50
          15.7 IN.UO.
          2i>.6 IN.UG.
             0 IN.
          1.16 LBH/SEC-SG.FT.
        500.69 LP5/HR
         3.005 GR/ACF
         89.60 X
        INLF.F
      ACC.  WG1.
       PERCENT
          1.0
          6.0
         11.0
         16.0
         21.0
         26.0
         31.0
         36.0
         41.0
         46.0
         51.0
         'JA.O
         61.0
         66.0
         71.0
     OUTLLTT
    ACC. UGT.
     PERCENT
       9.62
      57.55
      US. 03
      92.50
      95.64
      96.76
      97.29
      97.73
      90.09
      90.37
      90.62
      90.85
      99.06
      99.24
      99.40

-------
                   J.-T/  f..  &C.UUNU bIKLLI
                    MINEOLAr N.Y. 11501

ClJSJTUhLR: I'GSTER  WHEELER

CUG'lOMER KlIFIiRENCE NUMBER: FUC 11-52331

MJCON RLFCRLNCF NUMBER: P72-437

                        TABLE  3A

   DUCON CYCLONE  OPERATING AND DESIGN DATA SHEET

CYCI ONE SELECTION: NO. OF STAGES
TOTAL GAS FLOW
TOTAL DAS.! fi.OW AT OPERATING CONDITION
OPERATING lirtS DENSITY  G COND.
OPERATING VISCOSITY @  COND.
OPERATING IjAS TEMPERATURE
OPERATING GAS PRESSURE
PARTICLE DENSITY
OPERATING SOLIDS  INLET LOADING
DPFKATING UOL1DS  INLET LOADING

CYLLONK
A-II-ltO
CYlJLilNE lYi'E
CYC.LflNE MO»JC.L
NO. OF CYCLONES
UI'EIVJING RAS  FLOW PFR CYCLONE
CYCIUNF INLET  VELOCITY
CYCLUNE SALTATION  VELOCITY
CYCLONE KPACTIONAL LFFICIENCY I
CYI:LUNC m. LEI TO  INLET RATIO
CYCLONE n«: SSURE UKOP
(JYCLONC DII'-LEC SUCTION
UYCI.ONC DTI'-LCG DIAMETER
Ull'-l i G SUI IDS KATE
CYU.dNL SHI [DS I.OKJ5 KATE
CYCI ONt 'Jdl IDS EMISSION
ACU. CYCLUME EFFICIENCY

OUril-T PftUl [CLE DISTRIBUTION OF STAC5E 1
s

IDITION















URVE NO.








STAGE 1

PARTICLE SIZE
LESS THAN
1.27
5.55
12.40
24.09
46.6?
77.01
81.A7
85.54
89.41
93.27
97.09
100.88
104.59
LOS. 23
111.77
115.19
11B.48
121.62
1 .
•205123 LBS/HR
14800 ACFM
0.2310 LB8/CF
0.0430 CP
1600 FiEG.F.
169.70 PSIA
42.0 LBS/CF
3666 LbS/HR
20.90 GKAINS/ACF
FIRST
200
VM
700
3
4933 ACFM' '
41.1 FT/SEC
18.0 FT/SEC
52. 8
1.50
8.U IN.WG.
13.8 IN.WG.
R IN.
O.B6 LPS/SEC-SO.FT
41^.36 LBS/HR
3.274 GR/ACF
88.67 '/.

™' ET OUTLET
ACC,. UGT. ACC. WU1.
PERCENT PERCENT
1.0 8. 03
6.0 52.96
11.0 . 02. 54
16.0 90.fi:>
21.0 94.01:
26.0 9r..3V
31.0 96.0"
36.0 96.70
41.0 97. W
46.0 97.AIJ
51.0 9JI.OA
56.0 98. 3/
61.0 98.63
66.0 98.86
71.0 99.00
76.0 99.27
81.0 99. 4S
86.0 100.00

-------
                   l ll-k.l«UI\
         KF.FHRLNCE NUHBER: FUIC 11-52331

DUCOH RLFEKtNUL- NUMULK: I-V2-437

                        TAULE   3B

   JiUCllN CYCI ONE OPLKAT CNG AND DESIGN DATA  SHEET

CYCI UNF: nn ECTIDN: NU. m  STAGES
           I I OW AT (II1! RAITNO CONDITION
           (Jrt.S IIF'NSI If 6  C'UND.
           VTGL'UfilTY  G> HOND.
           CASJ lEMhTKATURC
                                                         A-II-U1
TOTAL OiV.5
on .RA 11 NO
OITUATINO
OPL'KA I
OPF'KAHNG  CAS PRESSURE
        I DfN;iJTY
       I NO  SiOl.tJiS INLET
           SUlIPS INLET LOADING
                                                          1
                                                     13A868 LUii/HR
                                                       90Vii ACFM
                                                     0.2310 LPU/CF
                                                     .0.0430 HP
                                                       1AOO Ll.fi. I- .
                                                     1A9.70 PS] A
                                                       4i». o i  w/cr
CYCLONt.
CYCLUNb  iJIZt.
(.YCLflNf  lYPT
CYQflNI
CYCI.UNF
I:YI:I.DNI
NO. Of  CYCLOMfS
DITRAllNli  fiAf> TLUU PER CYCLONE
CYCLONI' liNlFT WEI.OHITY
         rtl.lAntlN VkLOCITY
         HACFIONAL FFriClENCY CURVE NO.
         OUTI n TO INLET RATIO
                  URUP
I'.YCLONC
CYCLONE
nil-'-l LU
CYCI.UNF
TYCI ONC
         IiLI'-l.liG D I rtHFTCK
         JJOLJIiii UA1F
         fjui rns i.una RATE
         soi. i no r MISSION
ric;c. CYCI ONI"  rr-nciCNCY

iMJllbT PAKIltlLE DISTRIBUTION OF STAGE 1
              of-
                                                      28.90 RRAINS/ACF

                                                      FIRST
                                                        200
                                                        VM
                                                        700
                                                          3
                                                       3292 ACFM
                                                       27.4 FT/SEC
                                                       13.0 FT/SEC
                                                       7b.4
                                                       1.50
                                                        3.9 IN.UG.
                                                        7.3 IN.WG.
                                                          0 TN.
                                                       0.5',i I.PS/SEC-SO.FT.
                                                     360.08 LUK/IIK
                                                      4.2b4 GR/AOF
                                                      85.28 X

PARTICLE SIZE
LEGS THAN
1.27
5. 55
12.40
:>4.89
4A.62
77.81
81.67
80.54
R9.41
93.27
97.09
100.811
104.59
100.23
1 1 J . 77
IJO.J9
1 i(!.4i!
Ji»I.A2
U'4.60
127.39
INLET
ACC. WCT.
PERCF.NT
L.O
6.0
11. 0
16.0
21.0
26.0
31.0
36.0
41.0
46.0
51.0
56.0
6J.O
66.0
/l.O
7A.O
Hl.O
U6.0
91.0
96.0
ouTir r
ACC., m:
PIII
-------
                                                          A-II-U2
              THE DUCON COMPANY,  INC.

DUCQN         1<*7 EAST SECOND STREET  • MINEOLA, NEW YORK MSO1
                 TEL- S16 741-61OO • CABLE. DUCON MINEOLANV • TWX S1O 222-9861
                                      November 10, 1972
  Foster Wheeler Corp.
  Process Design 'Department
  Process Plants Division
  110 South Orange Ave.
  Livingston, New Jersey  07039

  Attention:  Mr. C.W. Chen

  Subject:  Ducon Proposal P72-437

  Gentlemen:
  In response to your request, I have roughly estimated
  the cost for eight (8) 8" Trickle Valves  made out of
  Hastalloy 188 to be about twenty five thousand dollars
  ($25,000).  This .should not be taken as a final price.
  A finalized estimate would require  my investigating the
  cost in much greater detail.

  We hope the above is sufficient .for your present needs
  and should you have any questions,  please do not hesitate
  to contact us.

                                      Very truly yours,
                                      THE DUCON COMPANY, INC,
                                      >D.  Buzzelli

  DB:aw
        AIR 'I- O I I..I I I I O N 
-------
                                                               A-II-U3
       AERODYNE    DEVELOPMENT    CORPORATION
       24340 MILES ROAD, CLEVELAND, OHIO 44128   •   Telephone: 218/292-2828
                                    November 7, 1972
           Mr. C. W. Chen
           Process Plants Division
           Foster Wheeler Corporation
           110 South Orange Ave.
           Livingston, New Jersey 07039

           Dear Mr. Chen:

           Four (4) Model 4500 Type "S" Collectors fabricated of Hastellory
           188 would cost $42,000 each for a total of $168,000, fabricated
           10 gauge.

           Our quotation is good for 90 days, prices are P.O.B. Cleveland,
           Ohio. Our terms are net 30 days.

           Thanking you, we are

                                    Very truly yours,

                                    AERODYNE DEVELOPMENT CORP,
           MG:rec                   Mack Gordon
DUST COLLECTORS •  LIQUID-SOLID SEPARATORS • MATERIAL HANDLING VALVES •  OIL SKIMMERS

-------
                                                   A-II-U*
             THE  DUCON COMPANY,  INC.

DUCDN        147 EAST SECONO STREET • MINEOL.A, NEW YORK 1I5O1
                 TEL. 516 741-blOO • CABLE DUCON MINEOUANY • TWX 51O 222-9861
                                    September 27, 1972
 Foster Wheeler Corporation
 110 South Orange Avenue
 Livingston, New Jersey   07039
 Attention:  Mr. C. Chen
             Process Design Department
             Process Plants Division

 Subject:  Ducon Proposal P72-437
           Granular Bed Filter

 Gentlemen:

 In accordance with your inquiry dated September 16, 1972,
 we are pleased to offer our -proposal on a Ducon Granular
 Bed Filter for use as a secondary particulate removal
 pressurized system*

 General Arrangement

 For this service our selection consists of two (2)
 Size 51/204 GB filter units operating in parallel.

 Note, that the two filters should be arranged for con-
 nection to a common gas inlet line.  Each filter unit
 during normal operating would handle 1/2 of the total
 gas flow.  The clean gas from each should discharge to
 a common gas line.  This arrangement can be modified to
 suit the plant's requirements.

 VJithin this arrangement one of the two filters could be
 isolated by means of valving on the gas inlet and gas out-
 let, without interrupting the operation of the other
 filter.
       AIR POLLUTION CONTROL EQUIPMENT • PNEUMATIC CONVEYING SYSTEMS

-------
nurnu   THE DUCON COMPANY. INC.
1UCUN
                                     -2-

          Ducon Proposal  P72-437



          Details of Construction

          The  filter consists of a Carbon  steel  pressure vessel
          casing, furnished with a suitable  thickness  of internal
          insulating castable refractory lining.  The  refractory
          lining will be  supported by Stainless  Steel  tines, welded
          to the vessel shell.   The vessel is fitted with  an in-
          ternal Type 310  Stainless Steel  plenum which supports
          the  filter elements and acts as  a  clean gas  collection
          chamber.

        •Each vessel will be shipped in two major pieces, an upper
          section containing  the shop installed plenum and a lower
          cone section, thus  a  circumferential field weld on the
          shell  would be required.  The  filter elements, filter
          blow back  manifolds,  internal  inlet ducts, walkways, etc.,
          v/ould  be shipped loose for field installation.  The erec-
          tion sequence would be as follows:

          1.  Erect vessel support structure.

          2.  Move lower cone section with loose internals to in-
             side support structure.

          3.  Install vessel upper section.on support  structure.

          4.  Install erection clips at field seam.

          5.  Move bottom cone section into place and  secure with
             erection clips.

          6.  Weld circumferential seam.

          7.  Install target plate and platforms.

         8.  Gun castable refractory on vessel shell.

          9.  Install filter elements.

        10.  Install external blow back piping.

        11.  Make external piping connections.


        •NOTE:  The number of pieces and sections of each module,
         and the amount of field welding required may vary depend-
         ing on shipping limitations from point of manufacture to
         plant site.

-------
                                                                 A-II-L6
DION   ™E DUCON COMPANY. INC.
                                     -3-


         Ducon Proposal P 72-4 3 7


         Performance

         Based on your process conditions and the dust character-
         istics which you indicate, we would anticipate that the
         Ducon Type GB Filter would operate at an efficiency of
         approximately 9Q%.  Not having experience with this pro-
         cess, we would strongly recommend that a pilot operabion
         be initiated prior to a commercial unit.


         Prices

         We would estimate that the approximate selling price for
         these units would be as follows:
•
         Vessels                                     $162,000 Each
        •Filter elements (310 Stainless Steel)       $ 41,400/Module
        •Blow back piping, valving and instruments   $  8,470/Module

         With regard to the design of the vessels required to
         encase the Ducon Granular Bed Filter and the structural
         steel support required for these modules, preliminary
         calculations indicate that at 175 PSIG design pressure
         and 650° shell design temperature, material thicknesses
         in excess of 1% inches would be required.  Furthermore,
         due to the extremely high inbernal temperature and pres-
         sure, the blow back system would have to be specially
         designed also.  The analysis required in order to proper-
         ly design these vessels is involved and time consuming.

         The Ducon Company has the capability of performing this
         design work for a fee of seven thousand dollars ($7,000.00),
         which includes five thousand five hundred dollars (£5,500.00)
         for the vessel and structural design and one thousand five
         hundred dollars ($1,500.00) for the special design of the
         backwashing system.

         This amount will be credited toward a Purchase Order for
         the Ducon Granular Bed Filter for this service, if the
         project were to proceed.
        •NOTE:  Two vessels are required.

-------
                                                                  A-ll-Uf

     THE OUCON COMPANY. INC.
JCQN


                                  -4-




        Ducon Proposal P72-437
        Delivery of equipment could be made  approximately four
        to six months after receipt of approval drawings,  and
        we would estimate that the field erection  time would be
        one to one and a half months*  We are enclosing  three
        copies of our Process Data Sheet and three copies  of our
        sketch SP 72-43 7-1 for your inspection.

        We hope that the above and enclosed  is satisfactory for
        your present needs, and if we may be of further  service
        please do not hesitate to contact us*

                                           Very truly yours,
                                           THE DUCON COMPANY,  INC,
                                               < * t   f  «
                                           A* Tesoriero
        AT taw
        cc:  B. Kalen

-------
                                                 A-U-U8
Operating Data Sheet for Granular Bed Filter
   Customer: Poster Wheeler Corporation
   Customer Reference:  FWC11-52331
   Ducon Reference:  P72-437

Number of Units
Size of Unit
Total Gas Plow
Total Gas Flow at Condition
Gas Molecular Weight
Gas Temperature
Gas Pressure
Gas Density at Condition
Gas Viscosity at Condition
Apparent Particle Density
Inlet Dust Load
Inlet Dust Load
Filter Efficiency
Outlet Dust Load
Outlet Dust Load
Outlet Dust Load
Total Bed Area
Flow to Bed Ratio
Superficial Bed Velocity
Pressure Drop
Design Backwash Cycle
Backwash Flow Required
Backwash Pressure Required
No. of Filter Elements
N'o. of Compt. per Element
Grade of Sand
CASES


SCPK
ACFM

op
PSIA
tt/CFT
Cp
#/CFT
#/HR
GR/ACFT
%
#/HR
GR/ACFT
GR/SCFT
FT2

FPS
IN W.G.
Win.
SCFM
PSIG



A.I
,2

60,500
19,665
30016
3.600
155
Oo232
,043
42
390 o 12
2.352.

8
.0475
.0155
408
48.2
.805
20-23
5
450




A.2
2
2-51/204
39,500
12,791
30.04
1600
155
0.231
.043
42
237.05
2.162
98 +
4.8
.0438
.0142
408
31.4
.523
10-15
5
450
360
5 I/Module
16
1/4
A. 3
2

89,000
27,038
30.3
1600
155
0.233
.043
42
500.37
2.159

10
.0432
.0132
408
66.3
1.11
28-33
5
450





-------
Operating Data Sheet for Granular Bed Filter
   Customer: Poster Wheeler Corporation
   Customer Reference:  FWC11-52331
   Ducon Reference:  P72-437
                                                  A-II-U9

Number of Units
Size of Unit
Total Gas Flow
Total Gas Flow at Condition
Gas Molecular Weight
Gas Temperature
Gas Pressure
Gas Density at Condition
Gas Viscosity at Condition
Apparent Particle Density
Inlet Dust Load
Inlet Dust Load
Filter Efficiency
Outlet Dust Load
Outlet Dust Load
Outlet Dust Load.
Total Bed Area
Flow to Bed Ratio
Superficial Bed Velocity
Pressure Drop
Design Backwash Cycle
Backwash Flow Required
Backwash Pressure Required
No. of Filter Elements
No. of Compt. per Element
Grade of Sand
CASES


SCFK
ACFM

«p
PSIA
tt/CFT
Cp
#/CFT
#/HR
GR/ACFT
%
tt/HR
GR/ACFT
GR/SCFT
FT2

FPS
IN W.G.
Min.
SCFM
PSIG



A.I
2

609 500
19,665
30.16
1600
155
0.232
.043
42
398.12
2.362.

8
,0475
.0155
408
48,2.
o805
20-23
5
450




A.2
2 .
2-51/204
39 fl 500
12,791
30.04
1600
155
0.231
.043
42
237.05
• •2.162
98+
4.8
.0438
.0142
408
31.4
.523
10-15
5
450
360
51/Modu.le
16
1/4
A. 3
2

89,000
27,038
30.3
1600
155
0.233
.043
42
500.37
2.159

10
.0432
.0132
408
66.3
1.11
28-33 .
5
450





-------
                                                 A-II-50
Operating Data Sheet for Granular Bed Filter
   Customer: Poster Wheeler Corporation
   Customer Reference:  FWC11-52331
   Ducon Reference:  P72-437

Number of Units
Size of Unit
Total Gas Flow
Total Gas Flow at Condition
Gas Molecular Weight
Gas Temperature
Gas Pressure
Gas Density at Condition
Gas Viscosity at Condition
Apparent Particle Density
Inlet Dust Load
Inlet Dust Load
Filter Efficiency
Outlet Dust Load
Outlet Dust Load
Outlet Dust Load.
Total 3ed Area
Flow to Bed Ratio
Superficial Bed Velocity
Pressure Drop
Design Backwash Cycle
Backwash Flow Required
Backwash Pressure Required
No. of Filter Elements
No. of Compt. per Element
Grade of Sand
CASES


SCFK
ACFM

op
PSIA
tt/CFT
Cp
#/CFT
#/HR
GR/ACFT
of
/J
tt/HR
GR/ACPT
GR/SCFT
FT2

FPS
IN W.G.
Win.
SCFM
PSIG



A.I
2

600500
195,665
30.16
1600
155
Oo232
«043
42
390012
2.362.
•
8
0OA75
.0155
408
48 „ 2
o805
20-2?,
5
450




A.2
2
2-51/204
39,500
12,791
30.04
1600
155
0.231
.043
42
237.05
2.162
98+
4.8
.0438
.0142
408
3104
.523
10-15
5
450
360
51/Nodule
16
1/4
A. 3
2

89,000
27,038
30.3
1600
155
0.233
.043
42
500,37
2.159

10
.0432
.0132
408
66n3
1.11
28-33 ..
5
450





-------
IOM
                  -  SS
S" S
                                                                                              .? I C(
                                                                                              ^ i o
                                                                                              V. t 
-------
                     <"\
                       i~. -SS
 I UMCi '•
v c. 3 1 <•-, t *  ~vv. '. -^ c u v u
 rro > M T  e n--.
                              \ ' / :; V t
                                                   Fi LTL v. e v.e
                                                         .-[- I-\/\L
                                                                                         A-II-52
                                                                                      SP72-437-',

-------
      i '• •*!''  " one -SVIOT "
YX. CI£,H w. 'i-j crai-
 3"0 \ sv T t r r . (z I ".
                                                                                          A-n-53
PI LVL' V.  EL ewi CM i-i     S' S   3 I d


     iV'.V VV-. W\ U        -^3   i'vO

                                                                                         \A6US \VlC>

-------
                                                                         A-II-&
                         PMC  CORPORATION

                  LINK-BELT MATERIAL HANDLING SYSTEMS DIVISION

              3400 WALNUT STREET. COLMAR. PENNSYLVANIA 18918 • TELEPHONE (818) 888-0881
                                            September 14, 1972
Foster Wheeler Corporation
110 South Orange Avenue
Livingston, N. J.   07039

      Attention:    Mr. C.  W. Chen

      Subject:      Spent  Dolomite Cooler
                   Westinghouse Research Laboratory
                   Your Inquiry N.O. FW 11-52331
                   Item RC-101

Dear Mr. Chen:

Thank you for your inquiry of August 23 which was received here on August 30.
We trust the delay in getting an answer to you has not inconvenienced you too
greatly.

Based upon the information supplied to us, we are pleased to  offer a tentative
recommendation of a roto fin cooler to handle spent dolomite  and fly ash from
1600° to 1750° initial temperature, and cool down to about 300° F.   For design
purposes we are assuming a feed temperature  of 2000° F.  however and cooling
down to 300° F. at the rate of 24. 5 TPH.

Our tentative selection would be our No.  600 RF16 Roto-Fin Cooler.   This
unit would be as described in our Book 3406, a copy of which is attached
for your reference.   Page 25 of this book has some preliminary dimensional
information which would be of help in determining space requirements.

We would include with the equipment a mild steel rotor of our tube design and
which would be modified to handle the temperatures above.   It  would be complete
with a drive and reducer, a hood, and tank, and temperature  recorders for the
inlet and outlet material temperatures.
  ENGINEERED PROGRESS IN THE CREATIVE DESIGN. MANUFACTURE AND CONSTRUCTION OF MATERIAL HANDLING AND PROCESSING SVSTEMS

-------
                                                                         A-H-55
                        FMC  CORPORATION

                 LINK-BELT MATERIAL HANDLING SYSTEMS DIVISION


Page 2                                September 14, 1972
                                      Foster Wheeler Corporation

The approximate price for the above equipment would be $60, 000. 00 f. o.b.
Colmar, Pa.

Delivery at the present time for this equipment is running about 25 weeks.

With the preponderance  of small particles in the material, the biggest
advantage here would be  the lack of a requirement for any air moving
through the unit.  All of the cooling would be done indirectly with the use
of water at 85°.   However, to maintain a 120° exit water temperature,
our calculations indicate that the pumping requirements would be some-
thing in the range of 1500 GPM.  You may want to review the exit water
requirement in view of the large amount of water needed.

After you have had a chance to look over our quotation, we would be pleased
to discuss it with you at greater length.  However, if you have any questions
that need immediate answers, please don't hesitate to call us.

                                      Very truly yours,

                                      FMC CORPORATION

                           Link-Belt Material Handling  Systems Division
                                      V. A.  Cheney  f~~
                                      Manager       \
                                      Dryers and CooleXg
VAC/sb
End.

-------
                       RC-101   Dolomite Cooler
  t
WARM
WATER
                                                                             SECTION A A

Roto- Fin
number
300
400
-**- 600
800
1000
A
B

3-0
4-0
6-0
8-0
10-0
0-4
0-4
0-6
0-8
0-10
C
D
E
FCET AND INCHES
0-9
1-0
1-10
2-4
3-4
0-9
1-0
1-10
2-4
3-4
1-0
1-2
1-4
2-0
7-8
f 1 G

2-3
2-9
3-9
5-0
6-3
4-6
5-4
7-8
10-1
13-2
            Have dimemioni certified for inilallation purpoiei.
                                                                                  FMC/UNK-BELT • 25

-------
              Peabody Engineering Corp
              835 Mope Slrool | Slamfotd. Conncchcul 069071 Telephone 203 327-7000
                                                                      A-II-57
°eabody Engineering
             Peabody Proposal No. 72-306

             November 27, 1972

             Foster Wheeler Corporation
             110 South Orange Avenue
             Livingston/ New Jersey  07039

             Attention:  Mr. Chen
             Reference:
             Gentlemen:
Pressurized Air Heater
PEC Proposal No. 72-306
             This letter is to confirm the information related verbally
             to your Mr. Chen at our meeting on November 16.

             In review, the system is to be designed for the following
             conditions:
               Heat release
               Inlet temperature
               Outlet temperature
               Furnace pressure (operating)
               Furnace pressure (design)
               Fuel
               Atomization
               Atomization pressure

               Location
               Arrangement
                          35.0 MM BTU/hr.
                          500° F.
                          1500° F.
                          150 PSIG
                          320 PSIG
                          No. 2 oil
                          Steam
                          100 PSIG above furnace
                           pressure
                          Outdoors
                          Vertical
             The overall dimensions and weight of the equipment is as
             illustrated on the attached sketch.  For vertical up-fired
             arrangement as illustrated on the attached sketch, add
             approximately 6'-6" to the length of the unit to obtain the
             elevation of the outlet flange above the supporting steel
             base plate.

             We can furnish this unit complete with shell, super-duty
             firebrick and insulating material (shipped loose), burner,
             ignitor, FIA approved flame failure panel, oil valving and
             temperature controls, including electrically operated
             control valve, temperature controller and high temperature
             instrument.  Our budget price for this equipment is THIRTY-
             ONE THOUSAND ONE HUNDRED FORTY DOLLARS ($31,140.00).
                                                       continued...

-------
                                                         A-II-58
Peabody Proposal 72-306
Page Two

The equipment would be supplied with all components, except
flame failure panel, shipped loose for wiring and piping by
your personnel in the field.  If you choose to have Peabody
complete all such piping and wiring in our shops prior to
shipment we would charge an additional TWO THOUSAND SIX HUNDRED
DOLLARS ($2,600.00) for that service.

Further if you choose to deduct the temperature controls from
our supply our price will be reduced by TWO THOUSAND FIVE
HUNDRED DOLLARS ($2,500.00).

Our preliminary price for a Duplex pump set to supply the
oil at 300 PSIG is THREE THOUSAND FIVE HUNDRED DOLLARS
($3,500.00).

All prices are net, F.O.B. shipping points.

If further requirements evolve on this project on either this
portion or the two (2) burners previously quoted, please
contact the writer directly.
Yours very truly,
PEABODY ENGINEERING
Felix D'Avanzo
FD'A/mp
Letter in Duplicate

-------
OIL ftTOt.H7.ER
 OR GAS GUM
                                                                                                                                                              I

-------
 BIBLIOGRAPHIC DATA
 SHEET
                   1. Report No.
                   EPA-650/2-73-048a thru -d
3. Recipient's Accession No.
 4. Title and Subtitlc
              Pressurized Fluidized-Bed Combustion Process
Development and Evaluation,  Volumes I, H , m, and IV
(Vol H, Appendices; Vol HI, Boiler Development Plant Design;
             *
5- Report Date
December 1973
                                                               6.
     TV
 7. Auihor(sr)
 D. L.  Keairns
                D. H.  Archer et al.
                                                               &• Performing Organization Rept.
                                                                 No.
 9. Performing Organisation Name and Address
 Westinghouse Research Laboratories
 Pittsburgh, Pennsylvania 15235
                                                               10. Project/Task/Work Unit No.
                                                                ROAP 21ADB-09
                                                               11. Contract/Grant No.

                                                               68-02-0217
 12. Sponsoring Organization Name and Address
 EPA, Office of Research and Development
 NERC-RTP, Control Systems Laboratory
 Research Triangle Park, North Carolina 27711
                                                               13. Type of Report & Period
                                                                 Covered
                                                               Final  July 1971  to
                                                                      May 1Q73
                                                               14.
 IS. Supplementary Notes
u. Abstracts
              rep0rt presents: results of a process evaluation of the pressurized
 fluidized-bed combustion (FBC) system for power generation; preliminary plans and
 a cost estimate for a 30-MW pressurized FBC boiler development plant; identification
 of a project team and program to demonstrate FB oil gasification/desulfurization for
 power generation on a 50-MW plant; and evaluation of pressurized oil gasification for
 combined- cycle power generation.  It identifies  no problems which preclude  the
 development of pressurized FBC combined- cycle power plants and FB oil gasification
 power plants which can generate electrical energy within environmental goals at lower
 energy costs than competitive systems. Work reported here, a continuation of earlier
 FBC process evaluation efforts , is aimed at the development and demonstration of
 these FB fuel processing systems.
 17. Key Words and Document Analysis. 17o. Descriptor;,
 Air Pollution
 Combustion
 Gasification
 Fluidized Bed Processing
 Desulfurization
 Oils
 Fossil Fuels
 Wastes
 Electric Power Generation
 17b. Identifiers,'Opcn-Lndcd Terms
 Air Pollution Control
 Stationary Sources
 Fluidized-Bed  Combustion
17c. COSATI r-ield/Gioup
                              21B
 18. Availability Statement
                 Unlimited
                                                    19. Security Class (This
                                                      Report)
                                                        UNCLASSIFIED
                                                    20. Security Class (This
                                                       Page
                                                    	UNCLASSIFIED
         21. No. of Pages
              252
                                                                        22. Price
FORM NTIS-35 (REV. 3-721
                                      AII-60
                                                                        USCOMM-DC I495Z-P72

-------