Report 1232-03-81-OR
         Final Draft Guidance for Subpart H

           Of the interim Status Standards

     For Owners and Operators Of Hazardous

Waste Treatment, Storage and Disposal Facilities




                           Prepared By:

                           Robert E. Burr
                        Robin Rodensky Severn
                          Nickolaus Leggett
                           Richard Meyer
                           Harvey Epstein
                          Karry Chriaman

                          November 1981



                      MANAGEMENTSYSTEMS D.VlSIOfJ

                GENERAL
                                      CORPORATION

                    A SUBSIDIARY OF FLOW GENERAL INC.

               7655 Old Springhouse Road, McLean, Virginia 22102
                           Prepared For:


                    The Environmental Protection Aqency
                    Under EPA Concrrict Mo. 68-01-5794

-------
                        Report 1232-03-81-CR
         Final Draft Guidance for Subpart H


           Of the Interim Status Standards

     For Owners and Operators Of Hazardous

Waste Treatment, Storage and Disposal Facilities




                           Prepared By:

                           Robert E. Burt
                        Robin Rodensky Severn
                          Nickolaus Leggett
                           Richard Meyer
                           Harvey Epstein
                          Kerry Chrisman

                          November 1981



                    MANAGEMENT SYSTEMS DIVISION

               GENERAL

               Kt3tAK\_H  3©  CORPORATION

                   A SUBSIDIARY OF FLOW GENERAL INC.
               7655 Old Springhouse Road, McLean, Virginia 22102
                           Prepared For:


                    The Environmental Protection Agency
                    Under EPA Contract No. 68-01-5794

-------
                                 PREFACE

     This draft guidance document has been prepared by the International
Research and Technology Corporation.  In preparing this document, we
have sought and incorporated the advice of the Office of Solid Waste,
Environmental Protection Agency (EPA).  The Regional Offices, the Office
of General Counsel, and the Office of Enforcement have not yet reviewed
this draft guidance document; therefore, this document does not repre-
sent EPA's final views and opinions.

-------
                            TABLE OF CONTENTS

                                                                   Page

 PREFACE	i

 TABLE OF CONTENTS	;

 LIST OF TABLES	v

 1. 0   INTRODUCTION	!_!

 2.0   BASIC RULES FOR THE CLOSURE COST ESTIMATE	2-1

 3.0   BASIC RULES FOR THE POST-CLOSURE COST ESTIMATE	3-1

 4.0   PREPARING AND DOCUMENTING THE CLOSURE AND POST-
        CLOSURE COST ESTIMATES	4-1

      4.1   Costs Based upon Experience of the Owner or
              Operator	4-1
      4.2   Contractor Estimates	4-2
      4.3   Cost Estimating Handbooks	4-3
      4.4   Workups from Labor, Material and Equipment
              Requirements	•	4-4

 5.0   ADEQUACY OF THE CLOSURE COST ESTIMATE	5-1

      5.1   Activities Relevant to All Facilities	5-4
            5.1.1   Treating, Disposing or Removing Inventory	5-4
            5.1.2   Decontaminating tne Facility	5-6
            5. 1.3   Monitoring	5-5
            5.1.4   Professional Engineer Certification	5-6
      5.2   Costs Required Only of Landfills  and Surface
              Impoundments	5-7
            5. 2.1   Cover	5-7
            5. 2. 2   Vegetation	5-3
            5.2.3   Optional Measures	5-9

6.0   ADEQUACY OF THE POST-CLOSURE COST ESTIMATE	6-1

      6.1    Inspections  and  Facility Visits	6-3
      6.2   Reestablishing Cover and Vegetation	6-5
      6.3   Fertilizing	6-5
      6. 4   Mowing	'	6-5
      6.5    Ground-water Monitoring	6-6
      6.6    Maintaining  and  Replacing Fences	6-6
      6.7    Collecting,  Removing and Treating  Leachate	6-6

7.0   REVISING THE  CLOSURE AND POST-CLOSURE COST  ESTIMATES	7-1
                                  iii

-------
8.0   ADJUSTING THE COST ESTIMATES TO ACCOUNT FOR INFLATION	8-1

9.0   SAMPLE COST ESTIMATES	9-1

      9.1   Introduction	9-1
      9.2   Example - Surface Impoundments	9-2
      9.3   Example - Land Treatment Facilities	9-31
      9.4   Example - Landfills	9-56
      9.5   Example - Incinerators	9-75
      9.6   Example - Multiple Process Facility With Tanks
                      and Surface Impoundments	9-91
      9.7   Example - Post-Closure Cost Estimates	9-114
                                  iv

-------
                             LIST OF TABLES

Table                                                              Page

5-1   CLOSURE COST ESTIMATE RAPID CHECKS	5-3

6-1   COSTS OF SELECTED POST-CLOSURE ACTIVITIES	6-4

8-1   HYPOTHETICAL SAMPLE PAGE OF SURVEY OF CURRENT
        BUSINESS	3_3

-------
                            -.0  INIRCDUCIIJN

      EPA has developed standards for financial requirements for owners
 or operators of hazardous waste facilities as part of the Interim Status
 Standards — Subpart H Financial Requirements.  This guidance document
 covers only those portions of Subpart H promulgated on 19 May 1980 and
 the technical amendments  to those regulations.  These portions require
 the owner or operator to  prepare cost estimates for closure and post-
 closure.   At later dates,  Subpart H will also contain final regulations
 covering  liability requirements and financial assurance mechanisms.

      The  purpose  of the cost  estimation requirements is to determine
 the amount  of financial assurance needed.   These requirements  are pre-
 sented in 40 CFR  §265.142  for closure and  40  CFR §265.144 for  post-
 closure.   Each of  these sections  contains  a requirement for a  written
 cost  estimate available on  the premises  (40 CFR §265.142(a)  and 40 CFR
 §265.144(a)),  a requirement for revisions  in  the cost  estimate whenever
 changes are  made  in the applicable  plans  (40  CFR i265.142(b) and  40
 CFR §265.144(b)) and  a requirement  for  annual adjustments  in the  closure
 and post-closure cost estimates  to  reflect  inflation  (40  CFR §265.142(c)
 and 40 CFR  1265.144(c)).  All  owners  or  operators  of hazardous  waste
 facilities,  except  those facilities owned or  operated by  states and  the
 federal government, must prepare closure cost  estimates.  All  owners or
 operators of  facilities in which hazardous wastes will  remain  after
 closure, except those facilities owned or operated by states and  the
 federal government, must prepare a post-closure  cost estimate.  The
 closure cost estimates must be available on the premises on the effective
                i
date of these  regulations, i.e., November 19,  1980, for chose  facilities
not required co have a post-closure plan.  Owners or operators of  land
disposal facilities, or facilities closed as such, will not be required
 to have their  closure and post-closure cost estimates available until
 six months from the effective date of these regulations, i.e., May 19,
 1981, because  of the complexities involved in developing plans and
estimates for  these types of facilities.
                                   1-1

-------
      The  purpose  of  this documenc is co assist the Regional Offices in
 implementing  those sections of the interim status regulations  relevant
 to closure  and  post-closure cost estimates.  Since the bases for the
 cost  estimates  are the closure and post-closure plans,  this section
 should be "read  in association with the guidance for closure and post-
 closure plans.  The  remainder of this document is divided into eight
 sections:   basic  rules for the closure cost estimate;  basic rules  for
 the post-closure  cost  estimate;  preparing and documenting the  closure
 and post-closure  cost  estimates;  adequacy of the closure  cost  estimate;
 adequacy  of the post-closure cost estimate; revising the  closure and
 post-closure cost estimates; adjusting the cost estimates  to account
 for inflation; and sample  cost estimates  for various types  of  facilities,
 The emphasis throughout  this document is  upon interim status.   This  is
 particularly important to  the sections  on adequacy  of cost  estimates,
vhich are designed for rapid review  and inspection.

      Sample cose  estimates have been developed for several kinds of
 facilities  in nhe final section of this document.  The  purpose of  these
 samples is  co illustrate the concepts involved in closure and  post-
 closure cost estimates and the formats which might be  appropriate.   The
 samples are developed  through a series of worksheets designed  to illus-
 trate an  appropriate format for demonstrating the scope and nature  of
 the activities  involved and the key  unit  cost elements  used in arriving
 at the final estimate.  Closure and  post-closure costs  will be highly
 site-specific,  and as  a result,  these worksheets should be  viewed as
 only  general guidance  and  are unlikely to be applicable in  any specific
 case.  In no case should the unit cpsts used in the samples be regarded
 as proper and accurate costs to  be used in developing cost  estimates.
                                  1-2

-------
              2.0   BASIC  RULES  FOR THE  CLOSURE  COST  ESTIMATE

      In  developing closure  cost  estimates  for  interim status,  the
 following  concepts should be used for  guidance.

 2.1   The closure  cost estimate is based  upon the methods  described
      in  the  closure plan.

      A cost  estimate should be prepared  for each activity or sub-activity
 listed in  the closure plan.  The  cost  estimate is based upon the  ac-
 tivities,  quantities and methods  indicated in  the closure plan.   For
 example, a cost estimate should be prepared for treating, disposing  or
 removing inventory.  It  must account for managing the  maximum  inventory
 expected as  indicated in the closure plan.  The method used for treating,
 disposing  or removing the inventory vould be identical to that indicated
 in the closure plan.  For example, if  the closure plan indicates  managing
 1000  tons  of waste, of which 800  tons  are to be disposed  or treated
 on-site  and  200 tons removed to an off-site TSDF, the  cost estimate
 must  include estimates for these  respective costs.

 2.2   "The  estimate  must equal the cost of closure at the  point in  the
      facility's operating life when the extent and manner of its  opera-
      tion  would make closure the most  expensive, as indicated by  its
      closure plan."*

      The goal of  the cost estimate is  to ensure that if at any point in
 time  a facility had to begin closure for reasons unrelated to a catas-
 trophe at  the site, the costs of the closure would not exceed the cost
 estimate.  Thus,  the conditions on which the cost estimate is predicated
will  probably differ significantly from anticipated conditions  at the end
of normal  facility life with respect to amounts of undisposed or un-
 treated wastes on-hand,  status of processing equipment, and area of the
 facility in disturbed condition.
*EPA Interim Status Standards, 40 CFR §265.142(a)

                                   2-1

-------
      For  example,  for purposes of Che cost estimate, the estimate of
maximum inventory  on-site should include the maximum normally expected
on-site.   This  estimate should take account of any long-term cycle of
inventory  on-hand,  and should take account of predictable events  which
may occur  over  the life of the facility, such as adverse weather  condi-
tions  preventing normal activity at a landfill and "down time" to
periodically  rebrick the refractory of an incinerator.   The initial
estimate need not,  however,  include provisions for highly unusual
contingencies unless they exist at the time the facility submits  its
initial cost estimate.  For  example,  the cost estimate  need not include
provision  for such unusual contingencies as the effects of the 50-year
storm  or the failure of a liner in a  major trench calling for removal of
all waste  in  that  trench.  If such events occur over the life of  the
facility and cause  the original maximum inventory estimate to be
exceeded,  the owner or operator should revise the closure plan to
reflect the current situation unless  he can immediately correct the
situation  so that  his original estimate of maximum inventory is not
exceeded.  In cases of doubt,  the Regional Administrator's office should
be contacted as to  the advisability of revising the cost estimate.   In
no case, however,  should the  initial  cost estimate list a maximum inven-
tory  less  than  that actually  on-site.   If normal operating procedures
include steps which would reduce  closure costs,  such  as dredging  of  an
impoundment or capping portions of a  landfill,  it should be  assumed  that
closure will occur  just before  these activities.  Thus,  in the closure
cost estimate all  costs associated with such  procedures should be
included.   This assumption is  to  ensure adequate funds  in the closure
cost estimate for  the situation of forced closure due to an  unforeseen
event  such as business failure of the  facility's owner  or operator.

    If experience  shows that  the  initial cost estimate  over-  or under-
estimated the most  expensive  conditions likely  to occur over  the  life
of the facility, or if those  conditions are no  longer possible, then
revisions may be made in the  cost estimate  as appropriate (see Section
7.0).   For example,  if late in the life of  the  facility the  total
                                   2-2

-------
 disturbed area is only 10 acres but had exceeded  20 acres  earlier,  it
 would be appropriate to revise  the cost estimate  downward.

 2.3  Cost estimates are to be based upon  the operating costs  to  the
      owner or operator of carrying out the planned  activities.

      This means that in developing the cost estimate the owner's or
 operator's depreciation costs, capital recovery factors, and  interest on
 debt need not be included as part of the costs.   For example, capital
 recovery and depreciation factors for earth-moving  equipment  owned by
 the owner or operator and costs of land already owned need not be
 considered as part of the costs of disposing of inventory at  a landfill.
 If equipment must be rented to complete closure activities, however, the
 costs of this rental must be part of the cost estimate.  If the owner or
 operator plans  to contract  out a specific  activity  (e.g., sandblasting
 and steam-cleaning the  equipment on-site,  planting  vegetation), the full
 costs of that contract  would be  the  correct cost estimate.

 2-4  The cost estimates should include  all associated costs necessary to
      carry  out  closure  procedures.

      A cost  estimate  for  a  given activity  must  include  all  costs  asso-
 ciated with  this  activity,  including  fully loaded  labor costs  (i.e.,
 including  fringe  benefits and  overhead), any  costs of supervision,  fuel
 and  maintenance costs for the  equipment used, administrative costs,  and
 provisions for normal contingencies.  Administrative costs  include  all
 costs associated  with taxes and insurance, as well  as  costs of routine
 administration,  paperwork and  reporting.   "Provisions for normal  contin-
 gencies" means that the cost estimates should include a factor for
 unforeseen events that may increase costs,  such as those  routinely put
 into most initial cost estimates.  Such contingencies include  adverse
 weather and other unanticipated complications.  Given the absence in the
 closure plan of  detailed engineering designs, the uncertain nature of
 precise facility conditions at the time of  closure,  and the lack of
 provision for inflation  during the closure  period  (which,  in some cases,
can be quite lengthy), the provision for contingencies should  be

                                   2-3

-------
 generous.   Standard engineering practice shows that in most cases
 a provision for contingencies could reasonably be expected to fall
 within the range of 15 to 25 percent.  The lower end of the range
 is appropriate for smaller facilities which require a short closure
 period and have fewer uncertain variables.  The higher end of the
 range accounts for larger.facilities which may require extensive
 activities and a longer closure period, for which unusual weather
 conditions or uncertain decontamination needs could seriously affect
 the cost of closure.

     A cost estimate for treating inventory in an incinerator would
 include fully loaded  labor costs,  supervision,  maintenance,  utilities,
 any chemicals and catalysts employed, administration,  and provisions
 for contingencies.  Although the cost estimate  should  include all of
 these cost elements,  they need not be documented separately.   Thus, for
 example, well documented unit costs for treating inventory are
 appropriate even if they do not include separate documentation for
 maintenance,  utilities,  or all energy costs.  This  point  is  further
 discussed  in Section  4.0 and examples of an appropriate approach
 are shown  in Section  9.0.
               j

 2.5  The  cost estimates  should be based upon costs in the  year in  which
     the  estimate is prepared;  there is no need  to provide for inflation
     in developing the cost estimate,  as this  will be provided for in
     the  adjustment  procedure.

     Costs  should be based upon current costs.   For  practical  purposes,
 this  means  costs  within one year of the time  of  preparation of  the cost
estimate.  There  is no need  to adjust  data or cost estimates based
 upon  data within the current year  to  the exact  month for  which  the
 cost  estimate  is  dated.
                                   2-4

-------
           3.0   BASIC RULES  FOR THE  POST"CLOSURE COST ESTIMATE

      In  developing  a post-closure cost  estimate for interim status,  the
 following  concepts  should be  used for guidance.

 3.1   A post-closure cost estimate must  be  prepared  for all  facilities
      at  which hazardous wastes  remain on-site  after closure.

      Post-closure cost estimates are required  for landfills  and  surface
 impoundments and land treatment systems at which any hazardous wastes
 remain on-site  following final  closure.  If  an owner or operator of
 a  surface  impoundment originally plans  to  close it  as a storage  or
 treatment  facility  by removing  all  hazardous waste,  but later decides  to
 close it as a disposal facility, he must immediately prepare  a post-closure
 plan  for the facility.  In  similar  fashion,  if the  owner or  operator of a
 land  treatment  facility originally  prepares  a  closure plan based on the
 assumption that treatment will  render the waste non-hazardous but tests
 show  this is not the case,  he must  immediately  prepare  a post-closure
 plan  and cost estimate.

 3-2   The post-closure cost  estimate is based upon the methods described
      in  the post-closure plan.

     The post-closure cost  estimate is based upon the activities, quan-
 tities,  and methods indicated in the post-closure plan.  A cost estimate
should be prepared  for each activity or sub-activity listed in the post-
closure  plan.   For example,  a cost estimate should be prepared to cover
maintenance activities.   It  must reflect the methods to be used in the
post-closure plan and the rates of fertilization, mowing, sprinkling,
and other activities listed  in the post-closure plan.

3-3  The post-closure cost  estimate  should  be prepared for the entire
     area expected  to contain hazardous  waste at the time of final
     closure.
                                   3-1

-------
      The  post-closure estimate should provide for post-closure  care  for
 the  entire  facility as it is expected to exist at the  time  of  final
 closure.  Thus,  if a 180-acre facility is expected to  be  filled at a
 rate  of 10  acres per year, the initial post-closure cost  estimate must
 reflect the costs of post-closure care for the full 180 acres.

 2.4   The  post-closure cost estimate should reflect the costs nf
      purchasing  all necessary labor,  materials and equipment to carry
      out  post-closure requirements.  Unlike the closure cost estimate,
      it may not  be assumed that the owner or operator  already has
      adequate  equipment  for the purpose.

      It is  highly uncertain whether the entire period  of  post-closure
 care  will be carried out by the owner or operator himself, and  whether
 on-site labor  and equipment will be available.  Therefore, the  cost  esti-
 mate  should assume that  all services  required for post-closure  must  be
 contracted  for in order  to ensure financial adequacy.  The post-closure
 cost  estimate  must therefore include  adequate allowance for profits  on
 the post-closure  care services.   For  example,  if regular  mowing  is part
 of the post-closure plan,  the costs must  reflect the costs of hiring a
 service to  carry  out this  mowing,  rather  than the  cost of having a laborer
 of the owner or  operator using  mowing equipment  already in use  elsewhere
by the owner or  operator.   Similarly,  monitoring costs must be  estimated
assuming  it  is necessary to hire outside  help  both  to  take the  necessary
 samples and  to conduct the necessary  laboratory  tests.

 3.5  The post-closure cost estimate must  be  complete and  include all
     associated  costs necessary  to  carry  out  post-closure procedures.

     A cost  estimate for a given activity must  include all costs asso-
ciated with  this  activity,  including  fully  loaded labor costs,  any costs
of supervision,  fuel and maintenance  costs  for equipment used,  adminis-
 trative costs, and  provisions  for normal  contingencies.  Administrative
costs include  all  costs  associated  with  taxes  and insurance, as well
as costs of  routine  administration, paperwork  and reporting.  "Provisions
                                     3-2

-------
 for  normal  contingencies" means that the cost estimates should include a
 factor  for  unforeseen events that may increase costs, such as those
 routinely put into most initial cost estimates.  Such contingencies
 include adverse weather and other unanticipated complications.  Given
 the  absence in the post-closure plan of detailed engineering designs,
 the  uncertain nature of precise facility conditions at the time of post-
 closure,  and the uncertainty of the kinds of maintenance to be required
 during  the  post-closure period,  the provision for contingencies should
 be generous.   Standard  engineering practice shows that the provision
 for  contingencies  could reasonably be  expected to fall within the
 range of  15  to  25  percent.   As  with closure costs,  the documentation
 for  the cost  estimate need  not  break out all of these headings
 separately;  they must,  however, be included in any  unit or activity
 cost estimates  (see  Sections 4.0  and 9.0).   It is particularly important
 in the  case  of  post-closure care  to include supervision and inspection
 requirements  that  normally  might  be neglected in the cost  estimate.
 Since labor may  no longer be readily available on-site,  such routine
 functions as  facility inspection  and supervision and review of  work
 must be explicitly included.

 3-6  The jost-closure cost  estimate  covers  the  period  beginning at  the
     completion  of closure  of the  facility  and  lasts  for 30  years  there-
     after.

     The post-closure cost  estimate  does not  cover  the  cost  of main-
 taining  any partially closed portions of the  facility during facility
 Life.,  However,  the fact that partial closure has occurred  for portions
of the  facility does not in any way  shorten the  period of post-closure
care  required for the purposes of the post-closure cost estimates.  The
post-closure period begins with the  professional engineer's certifica-
tion  of  adequate closure.  As a result, provision should be made for any
 normal remedial  measures early in  the post-closure period,  such, as
 significant portions of the vegetation failing  to develop adequately.
                                   3-3

-------
3. 7  Pose-closure  expenditures  can  be  expected  to  occur  in  cwo cate-
     gories:  regular  annual  expenditures  and expenditures  chat occur
     with less  than  annual  frequency.   The written estimate of Che
     annual cost of  pose-closure  monitoring and  maintenance is equal co
     Che sum of regular  annual  expenditures plus the expected number of
     non-annual expenditures  times  their costs.

     This can be written as the following  formula:
where P is the annual  post-closure  cost  estimate, A is the size of
expenditures occurring  annually,  Ft  is the number of times over 30 years
non-annual expenditure  i  is  expected to  occur, and N£ is the cost of
non-annual expenditure  i.  There  may, of course, be several kinds of
annual expenditures  and several kinds of non-annual expenditures.
Specific types of non-annual expenditures that need to be considered
include provisions for  special activities resulting from unusual
weather, replacement of equipment,  and provisions for replanting and
other similar activities  in  the two  to five  years following closure.
                                  3-4

-------
                     4.0   PREPARING AND DOCUMENTING THE
                 CLOSURE AND  POST-CLOSURE COST  ESTIMATES

      Although written closure and post-closure cost estimates are
 required,  the regulation -does not specify format or documentation suit-
 able  for this cost estimate.   As a result,  the ultimate requirements in
 this  area  will be  up to  the discretion of the Regional Administrator.
 Certain general guidance  may, however, prove useful.   The cost estimate
 must  ultimately contain at least enough detail so that the Regional
 Office  can make a  reasonable  evaluation of  its validity at the time
 of inspections  during  interim status.

      The overall goal  of  the  cost estimate  and its documentation is to
 provide an  estimate  of the costs  and the  documentation necessary
 to demonstrate  the reasonableness  of the  estimate.  It is  not
 required that  the  cost estimate  have the  kind of detail and  accuracy
 appropriate to  a contractor preparing  a bid for a job.   There is little
 need  for a  highly  polished cost  estimate  since  these cost  estimates are
 for a hypothetical task that  is  to take place in che rather  distant
 future.

      Four  basic  approaches which  might be used  in developing costs  for
 the activities  listed  in the  closure plan are:

      •  Costs based  upon experience of  the  owner or operator
      •  Contractor estimates
      «  Cost estimation handbooks
      •  Workups  from labor, material and equipment requirements

4.1   COSTS  BASED UPON EXPERIENCE OF THE OWNER OR  OPERATOR

     The most directly relevant source  of cost information, in many
cases, will be the experience  of the owner or operator  in operating  the
                                4-1

-------
 facilicy.  An example would be  the costs of treating or disposing of
 inventory on-site, which will normally be a simple continuation of the
 normal operating practices of the business.  In the simplest case, cost
 of treating or disposing of inventory may be computed as the annual
 operating costs divided by the  fraction of a year required for adequately
 treating or disposing of inventory.  Such an estimate could then be
 documented by the past year's accounts, the amount of material treated
 or disposed over that year, and evidence that the year had involved
 relatively typical activities (e.g., if, for a landfill, no trench
 had to be dug or covered over the course of the year, then the year
 might not be considered a suitable example from the viewpoint of
 assuming the most expensive closure conditions likely to occur over the
 life of the facility) .  Given that the requirement that a cost estimate
 be available on-site is either six or twelve months after notification
 of the cost estimation requirement, a variety of closure activities could
 be documented from noting the costs of the activity as  they occur over
 the interim period.*  For example, for a landfill, the  costs and activities
 involved in partial closures could be documented and used as a base for
 unit cost estimates of the cost of final cover.

      Similarly,  costs of monitoring tests  during post-closure will be
 similar to the costs of monitoring tests during  facility life,  though
 gathering samples will be more expensive due to  the need to assume
 purchased labor  and travel to the facility.   Possibly the best source
 for costs and frequency of many kinds-of post-closure non-routine
 expenditures is  the actual experience in maintaining currently partially
 closed portions  of a landfill.

 4.2   CONTRACTOR  ESTIMATES

      A variety of costs,  particularly if services  are to be  purchased
 from a contractor or contractors by  the  owner or operator, may be
*As discussed in Section  1.0,  owners or operators of land disposal
facilities are not  required  to nave their cost estimates available
until twelve months after the  effective date of these regulations.
Owners or operators of  other facility types must have an estimate'
available within six months  of  the effective date of these regulations,
                                  4-2

-------
obtained from contractor estimates.   For  example,  an  owner  or  operator
could ascertain the costs  of  certification by  an  independent professional
engineer by asking several professional engineers  for estimates  of  the
costs of certifying the completion of activities  listed  in  the closure
plan.  If an owner or operator plans  to send either inventory  or con-
taminated residues to an off-site TSDF, inquiries  to  ascertain distances,
hauling costs, and treatment  or disposal  costs would  be  in  order.   It  is
not necessary for purposes of documenting, to have written  and validated
cost estimates.  Adequate  documentation could note who was  contacted
and their approximate estimates.

4.3  COST ESTIMATING HANDBOOKS

     There are a variety of commercial engineering cost  estimation manuals
that provide guides to equipment and labor needs and  unit costs  of
specific operations that may  be relevant  to various activities associated
with closing hazardous waste  facilities.  Such manuals may  be  reasonably
used as a source for cost  estimates for closure costs.   Care must be
taken in using such manuals.  They vary widely with respect to whether
or not unit costs cited include such factors as administration,  normal
contingencies, profits, and whether or not allowances must  be made to
adjust theoretical work rates to normal field conditions.

     From the owner's or operator's view,  care should be taken that an
overestimate is not produced by using estimates which allow for  profits
and capital recovery on equipment when this is not required if he is using
his own equipment for closure.  Distinct underestimates  are possible if
attention is not given to  the indicated need for adjustment of theore-
tical work rates to normal field conditions and for administrative costs.
As a result, suitable documentation for a cost estimate  for an activity
based upon such a handbook would be a copy of the  relevant pages of the
handbook, including those pages providing instructions as to the use of
the unit cost estimates and any adjustments from the cited costs used in
arriving at the unit cost estimate employed in the cost estimate itself.
                                   4-3

-------
4.4  WORKUPS  FROM  LABOR,  MATERIAL AND EQUIPMENT  REQUIREMENTS

     In some  cases,  there may  be  no  way  to  arrive at a  useful  cost
estimate other  than  by  a  detailed workup of the  costs.   Such a workup
would include an estimate  of  the labor, equipment, energy and material
needs for the activity  to.be estimated,  the basis for these assumptions,
and the total time required  for the  activity.  Allowance would then
need to be made for  supervision and  administrative costs and any
necessary adjustments for fully loaded labor and equipment costs.
                                  4-4

-------
                5.0   ADEQUACY  OF  THE  CLOSURE COST ESTIMATE

      For  Che closure cost estimate  to  be  judged  adequate,  It  must  meet
 the  following  criteria:

      1.   The closure cost estimate must contain  cost  estimates  for all
 activities  presented in  the closure  plan.   The cost estimate  must  also
 reflect the quantities and methods associated with all of  the activities
 presented in the closure plan.   (Note  that  the adequacy of  the  cost
 estimate  is therefore dependent  on  the adequacy  of the closure  plan.)

      2.   The closure cost estimate must be  documented  in  order  that the
 bases  for the  cost estimate can  be checked.

      3.   The resulting cost estimate must reflect  the  actual  costs  of
 carrying  out closure.  This can  be determined by a check  of the  sources
 listed for documentation providing that Rule 2 has been met.  A  cross-
 check  can be made by using alternative sources,  i.e.,  if  the  owner's or
 operator's cost estimate is based upon a contractor estimate, this  may
 be checked  through reference  to  a cost estimation  manual, experience of
 other  owners or operators, or inquiries to  other contractors.

     The  cost  estimate must be available upon the  premises for  inspec-
 tion during interim status.   As a result, it will  be useful to have
 available simple and rapid checks as to the adequacy of  the cost esti-
 mate.  The remainder of this discussion is devoted, in part,  to  a  discus-
 sion  of simple checks that could be  accomplished in less  than an hour  or
 two with  the aid of the closure  plan and a  visit to the facility to deter-
mine  the adequacy of the closure plan (see Section 12.Oof the draft
guidance for Subpart G, Closure and Post-Closure Care).  These checks
are not intended for use by owners or operators  and may not be used as a
method for developing a cost estimate.
                                5-1

-------
      If an initial check raises questions as to the adequacy of the cost
 estimate,  several steps may be taken.  First, a copy of the complete
 cost  estimate may be required and reviewed, and a check made of the
 documentation.  It is quite possible that the cost estimate could be
 accurate and fall outside the ranges indicated in the discussion below.
 If, after  review, the cost-estimate still seems inadequate, the owner or
 operator could be specifically requested to make the desired alterations.
 If this approach fails to result in a satisfactory cost estimate, there
 are two possible recourses during interim status.   The Regional Adminis-
 trator  could bring an enforcement case or he could request  part B of the
 permit  application and thus  revise the cost estimate as part of the permit
 application  process.

      Unfortunately,  the annual report of the facility,  though  it must
 include the  cost estimate, does not contain adequate information to
 determine  the accuracy of the cost estimate.   For  example,  the amount
 of inventory on-hand  is not  a required element of  the permit  application.
 Therefore, in order  to check on the accuracy of the  cost estimate,  it
 may be  necessary to visit the facility.   An inspector could then obtain
 copies  of  the closure plan and cost estimate,  and  conduct a quick  review
 of the  key variables  for the closure plan,  as  discussed  in  Section  12.C
 of the  draft  guidance for Subpart G,  Closure  and Post-Closure  Care.

     Table 5-1  shows  the key elements  involved  in  verifying  the  closure
 cost estimate,  listed by major '-ypes  of  activity involved.  For  each
 activity, the major elements required  to  check  the adequacy are  the
 activity indicator  (the variable  that  determines the  degree of  the
 activity, e.g.,  quantity of  inventory, volume of contaminated  soil),
 unit costs (estimates of the unit costs  for each activity of the  facility
 in question) , and sources  for variation  in  unit costs from  facility to
 facility.  Also  included in  this  table are  current typical costs of each
 required activity.  A relatively  wide  range is  used due to variations
depending upon  the region  and upon  the nature of the wastes (e.g., high
hazard wastes have greater costs  than  lower hazard wastes).  As these
 costs are national averages,  more  accurate  estimates would be obtained

                                    5-2

-------
                                                                                TABLE 5-1


                                                            CLOSURE  COST  ESTIMATE  KAl'lD CHECKS
Ki..|uUt.J al \l 1 :>li..s
1 liivuiilury Ul^|iu^al
1 ltt.t.uiil.iiulii il lull uiul
UkLuuuulbbioiiInt;
i Nulillul lii(;
'i Ltrili lt.aci.iii
kt.t4ulli.tj ul lalldllll.> .iiitl
SulBl bill IdlC laipUIIII.llllt.llL..
1 Itivei
a Cl'uy
.! Vt.Kt.Lal lull
Uull.mal
1 1 t.*at.lialt. I ul li.t.1 1011,
Kt.iikiv.il mil li>.llliit.iil
k. (i.i» Monitor lug and
LulluLllun
J A, LI II 1,. n i| .1., .mi.
1 H|lll I 1-IUt III S
ALMVII1 INIlli.MUK
ljuaiillly ut liiviiiluiy
ijuanllly uf r«.!iltlut.>.
VultlUlt. ol !.IMIl.llulllJlt.J ...fll
AiuuullC tjf «.t|ul|>int.iiL .uitl
taclllllub
Nuiubur ul lu^Lb
l.llglllut.1 lloii.
i.uvcr

i>f vt:gt.LaL Ion
UNII uiblb
lln-bllc.. 1U-6UZ ul .ivt.ia|;i.
ull-illi. Jlj|>tla.ll LUbla
Ull-bllo. IOUZ ul ivt.ni;>.
ult-bllt. Jl^pu^.ll LU^Lb
anil liaulluu
Hil-'ilLi. 10-dOJ. ,il avt>i.i|;t.
ufl-bllt. dlii|iu^tll CO^Lb
III! -Mil. 100X ul ivti.iyu
ufl-bllt! JJb|>!l:idl CUbLb
tllltl ll.HI 1 1 IIU
S/liuur til juul ub^ltiiul
Lllg 1 111.1 1 1 llUt.
SdUKCtb III- VAKIAIUIN IN
UNII lOSfS
llll t>ii|jli|j|ic , Ly|>u of bllu,
quality ul dlbpubtil.
iialtiru of wabit.
III! I>II£|||MI| , Ly|>U Ul bill,
<|uallLy ul Jib|iobal.
naLult. uf wabtu
kt.gltjiiiil ( won ILUI lut; ulau
tt.i|iilrmut.ncb
Kt-ljloual
li.i rat,lii|it HaLuru ol t.uvt.1 ,
Ji.bibii ot cuvcr. Lypt. ul
soil
lunailng, llui.r luaLcilai.
[llll.fclll!bb 01 HllCt
ouc>.rlal
IkiiaLlug. naiurt. of covur(
dublgn ul kovur. typu ol
bull, lypu and duiiblcy of
btiud, provision for
leulantlnij
IM'hAI IVUu l-ublb«
Oil-bill. dlb|IUbal t.Ublb by ly^t. ul
lac-lllly.
lllLlllt.1 JIUI - >l(IU-JUU/lull
Landllll - S «0-l50/luil
bin fjt.1.
lni|ioundmt.iil - $ IU- JU/liiu
land litfaliucill - $ 10- 407 lull
llaulliii; LOblb - $ O-'-S IU
pi.r un mil.
llll-bllt. Jltipobal coblb by lypti uf
facility.
liiLlnt-iaior - slUU-^UO/iun
landlill - $ BU- ISO/ lun
Surface
ImpouililiDuiil - $ 10- JO/ 1 on
Land trt!Iltt.fc 1 L IlilC
>SOU-1.SUU |ii.r iuui |ii.r u«.r«.
$300-10.000 |nr 4it.iu
$400-1.^00 |.cf acie

Ol
 I
U)
               *lli^bi! >.0blb art. lor  ^luuntl-ualul luunllui lug alialybt.^  .u  b|».i.ll li.d  In llii- lt,|;iilal lolib,  air  and  jull

                uunlttii lilt; .ut. iiul  ln^ lti.lt..I    (hi! tibClinalt! I- bujuJ un L|I>  iiubl cxlt.il.Ivi! mtiiilKirliii: cliac Lould lie

                ri-t|ulit.J wllhlii a blji uionlh cloburu period.

-------
 using average costs for the specific area.  These costs also must be
 adjusted annually for inflation.  A mechanism for making this inflation
 adjustment is discussed in Section 8.0.

      For example, to check the adequacy of the cost estimate of treating
 or  disposing of inventory,'one would:

      (1)  Determine  the adequacy of  the  estimated amount of  inventory
          (this could most readily be done by  examining the  closure plan
          and facility conditions to  determine whether the closure plan
          adequately reflects  inventory  needs  of the facility);
      (2)  Determine whether, in  the case of treatment facilities  (including
          incinerators), provision has been made for treating, disposing,
          or removing residues off-site  which  result from treating inventory;
      (3)  Multiply the quantity  of inventory in the closure  plan by the
          unit costs given in  the Table; and
      (4)  Consult the variability factors listed in the Table (e.g.,
          throughput, type of  facility,  nature of waste, on- or off-site
          disposal), to determine whether the  facility should be at the
          high or low end of the range for unit costs.

5.1   ACTIVITIES RELEVANT TO ALL  FACILITIES

5.1.1  Treating.  Disposing, or Removing  Inventory

      For facilities not engaged  in disposal requiring post-closure care
(all  types of facilities except  landfills, and surface impoundments and
land  treatment  facilities in which hazardous wastes remain after closure),
treating, disposing or removing  inventory will frequently be the largest
single cost element.  The exceptions  to  this rule of thumb will normally
be situations in  which unusual decontamination problems occur, such as
large amounts of  waste water accumulating at the facility.  The key unit
parameters in determining the  costs of treating, disposing or removing
inventory to an off-site TSDF  are the amount of inventory on-hand and,
for incineration  and processes involving treatment, the relationships
                                   3-4

-------
between inventory processes and residues co be disposed of or treated
on-site or removed to an off-site TSDF.  The quantity of inventory on-
hand will vary enormously depending on the type of facility, the annual
throughput of the facility, and management practices.  For some types of
facilities, inventory can be minimal.  For example, some landfills accept
only trucked-in wastes on a space-available basis.  For such a landfill,
there would very seldom be any inventory at all.  It is also possible,
however, that start-up problems or, in the case of landfills, failure of
a major cell or cells could lead to a situation in which there is an
enormous amount of inventory which cannot be quickly worked off, and this
would have to be accounted for in the cost estimate.

     The unit costs of removing inventory are dependent upon whether the
inventory is to be disposed of or treated on-site or removed to an off-
site TSDF.  In the vast majority of cases at disposal facilities, the
disposing or treating of inventory will take place on-site.  If disposal
or treatment takes place on-site, the unit costs can be expected to
fall between 30 and 80 percent of the prevalent Regional costs for
remo"ing the inventory to an off-site TSDF.  On-site costs will be less
than off-site costs because closure costs r.eed only include the immediate
operating costs of disposing or treating inventory and not factors for
capital recovery, land, etc.  The variation will depend upon the type of
facility, its normal throughput (because of economies of scale, small
facilities will have higher unit costs than large facilities for almost
all types of facilities) , the quality and safety of disposal practices
at the facility, and the nature of the wastes.  For a landfill which always
maintains adequate open trench capacity, inventory disposal costs could
be a very small fraction cf normal off-site landfill disposal costs.  This
is because the costs of building the trench would not need to be included,
and the costs of cover and vegetation are covered separately.  Under these
circumstances, costs for treating or disposing of inventory could
be lower than the 30 percent indicated.  For inventory or residue that
must be removed to an off-site TSDF, unit costs will be 100 percent of
normal off-site costs in the Region, plus appropriate hauling costs.
                                   5-5

-------
 5.1.2  Decontaminating the Facility

      Under certain circumstances, decontaminating the facility could be
 the largest cost element for the facility.  This could be the case if
 large quantities of soil are contaminated, as might occur at any poorly
 run facility or at many improperly run surface impoundments, or if large
 amounts of waste water have accumulated at the facility.   For many
 facilities, however,  decontamination will be a relatively minor cost
 element requiring only general cleanup of equipment and facilities.   The
 key activity indicators for decontaminating the facility  are: quantity
 of  contaminated soil; quantity of contaminated waste water;  and amount
 of  equipment and facilities requiring cleaning.

      For contaminated soil and waste water, the relevant  unit costs  will
 be  those cited  for disposing or treating inventory, i.e.,  costs for
 disposing or treating the soil and water on-site or off-site.   For
 equipment and facilities, the costs will depend uoon cleaning costs
 themselves and  whether or not the residues resulting from cleaning will
 require treatment as  hazardous waste.

 5.1.3   Monitoring

     A  facility must  continue monitoring practices  during  the  closure
 period;  therefore,  some costs must  be  included for  monitoring.  The
 costs may be estimated using  the  current lab  costs  for  the tests in
 the  Region and  will vary  regionally and  according to  the monitoring plan
 in place  for the facility.

 5.1.4   Professional Engineer  Certification

     The  closure  cost  estimate  must  include provisions for the costs of
certification by  an independent professional  engineer.  Like monitoring,
 this will  normally  be  a relatively  minor cost  element.  The activity
indicator  for certification is  the hours spent  on-site by the professional
engineer, which will normally depend upon  the  length of the closure period
and the amount of activity which must take place.  The unit cost parameter
is dollars per hour of professional engineer  time in the Region.

                                    5-6

-------
 5.2  COSTS REQUIRED ONLY OF LANDFILLS AND SURFACE EIPOUNDMENTS

 5.2.1  Cover

      Some form of cover will usually be required for both landfills and
 surface impoundments which have hazardous wastes remaining after
 closure.   Cover and the associated vegetation (see Section 5.2.2) will
 normally  be the dominating element in determining the costs of closure
 for a landfill or surface impoundment.

      The  materials  to be used will depend on the types of soil available
 on-site as  well as  the conditions  of the facility.   Since purchasing
 soil off-site  is costly, it is likely that most  owners or operators
 will use  soil  available on-site, if at  all possible,  for the final cover,
 i.e.,  the layer with low permeability and the layer  capable of supporting
 vegetation,  if  applicable.   It is  possible to improve the quality of
 available soil  by blending  various  soils,  using  soil  additives,  or making
 other  provisions which  would  provide equivalent  protection.   For example,
 soil blending and synthetic additives may  decrease the permeability of
 the  on-site  soil as  well as make certain  soils more capable  of supporting
 vegetation.  In addition to improving the  quality of  available soil,
 the  Agency anticipates  that many owners or operators  will  use  membrane
 liners  protected  above  and  below by  buffer soil  layers  instead of  com-
 pacted  clay  for  the  layer of  the cover with  low  permeability.  These
 membrane  liners  may  be  cost effective if adequate on-site  soil material
 is unavailable  or an acceptable degree of  compaction  is  not  possible at
 a particular facility,  given  the wastes disposed or facility conditions.

     When clay  is used  as a liner material,  the key activity indicators
 are  acres not yet covered and  the depth of  the cover.  As noted in  the
 closure plan, decisions as  to  the depth of the cover and the adequacy of
 on-site materials are dependent on engineering judgment and are not
 covered in this guidance document.   The costs associated with such cover
may vary from S500 to $1500 per foot per acre of cover.  The key sources
of variation are:
                                   5-7

-------
      (1)   The amount and nature of terracing to be used in the cover;
      (2)   The depth of the area to be filled in the case of surface
           impoundments;
      (3)   The nature of the cover, including whether or not treatment
           is required to achieve proper degrees of impermeability; and
      (4)   The design of the cover.

      For  synthetic liners,  the key activity indicator is the acres not
 covered.   The costs associated with such covers vary widely,  depending
 on  the  type of material chosen and the thickness needed to ensure adequate
 low permeability.   It is not the purpose of this document to  assess
 alternative materials or to provide guidance as to the level  of per-
 meability which is acceptable.  The costs associated with installed
 liner material per acre vary from $5,000 to 320,000 per acre.   The key
 sources of variation are:

      (1)   The amount and nature of terracing to be used in the cover;
      (2)   Type of  liner material chosen; and
      (3)   Thickness of material necessary to achieve desired  degree of
           permeability.

 5.2.2  Vegetation

      For  most facilities, some vegetation will  be  required in  order to
 stabilize the cover and  prevent erosion  problems.   The key activity
 indicators  are  the number of  acres in need of vegetation (which may include
 areas previously seeded  but for which vegetation has  not properly
 developed)  and  the type  of  vegetation to be employed.   Unit costs  can
be expected to  range from $400 to  $1,500 per acre.  The lower  end  of
 the range would represent the costs of minimum  fertilization and planting
with  no provision  for  reseeding and replanting  of  any  kind.  The maximum
costs would represent  the costs of providing a  lawn-type cover.  Other
key variables in determining  cost  of  vegetation  are:
                                   5-8

-------
      (1)   The  type  of  soil  (including  determining the  degree  of
           fertilizer required);  and
      (2)   The  type  of  seed  used.

 Establishing complete  vegetation within  the  90  days  to  six months  over
 which closure  will  normally take place cannot be  attained.  As a result,
 some costs associated  with  developing  and  establishing  vegetation  will
 probably  take  place early in the post-closure period.   Therefore,  the
 adequacy  of the closure plan with respect  to vegetation should be  checked
 in coordination with an examination of the provisions  for maintaining
 vegetation in  the early years of the post-closure plan.

 5.2.3  Optional Measures

    Three kinds of  optional measures,  bearing significant costs, may be
 necessary at some facilities:  collection, removing and treating leachate;
 collecting gas; and additional measures  required  to protect human  health
 and the environment.   Even  for facilities  with  leachate collection systems,
 the cost of leachate collection, removal,  treatment and disposal for
 closure will normally  be the relatively minor cost of occasionally
 collecting the leachate and hauling it away to  an off-site TSDF.   In
 certain rare cases, leachate build-up may  be great enough to require
 an extensive on-site treatment and disposal system.  If this is the
 case,  this could be a  significant cost during the closure period.
 Maintaining an existing gas collection system normally will be a rela-
 tively minor cost.   At certain facilities, additional activities may
 be required to ensure  the protection of human health or the environment,
 such as those discussed in Section 9.0 of  the draft guidance for Subpart G.
 Such measures could be extremely expensive and would constitute a large
 share of closure costs; however, the exact combination of necessary
measures will be extremely site-specific.
                                 5-9

-------
              6.0   ADEQUACY OF THE  POST-CLOSURE  COST  ESTIMATE

      For the pose-closure cose  estimate to be judged adequate,  It must
 meet the following criteria:

      1.   The post-closure cost  estimate must contain cost estimates for
 all  activities  presented  in  the post-closure plan.   The  cost  estimate
 must also reflect the  quantities and  methods associated  with  all of the
 activities.presented in the  post-closure plan.   (Note  that  the  adequacy
 of  the cost estimate is therefore  dependent  on  the adequacy of  the post-
 closure  plan.)

      2.   The post-closure cost  estimate must be documented so that the
 bases for the cost estimate  can be checked.   Documentation may  be
 performed in a variety of ways; however, it  must be  provided  in such
 a way that the sources can be reviewed and judged by an  outside party.
 For  example,  if an owner  or  operator  states  that a cost  estimate was
 taken from an engineering cose  estimation manual,  the  estimate  could
 be  easily verified.

      3.   The  resulting cost  estimate  must reflect  the  actual  costs of
 carrying  out  post-closure  activities.   This  can  be determined by a check
 of  the sources  listed  for  documentation providing  that Rule 2 has been
 met.  A  cross-check can be made by  using alternative sources, i.e.,  if
 the  owner's  or  operator's  cost  estimate is based upon  a  contractor
 estimate,  this  may be  checked through  reference  to a cost estimation
 •nanual,  experience of  other owners  or  operators, or  inquiries to other
 contractors.

     The  cost estimate must be  available  on  the  premises  for inspection
during interim  status.   As a result, it  will be  useful to have available
 simple and  rapid  checks as to the adequacy of the cost estimate.   The
 remainder of this  section is devoted  to a discussion of  simple  checks
of the costs of specific activities that  could be used with the  aid of
 the closure plan and a  visit  to  the facility to determine the adequacy
of the post-closure plan (see Section  12.0 of the draft guidance  for

                                   6-1

-------
 Subpart  G,  Closure and Pose-Closure Care).   These checks are not
 intended for use by owners and operators and may not be used as a method
 for  developing a cost estimate.

      If  an  initial check raises questions as to the adequacy of the cost
 estimate, several steps may be taken.   First, a copy of the complete
 cost  estimate may be requested and reviewed, and a check made of the
 documentation.   It is quite possible that the cost estimate could be
 accurate and fall outside the ranges indicated in the discussion below.
 If, after review,  the cost estimate still seems inadequate, the owner  or
 operator could  be specifically requested to make the desired altera-
 tions.   If  this approach fails to result in a satisfactory  cost estimate,
 there are two possible recourses  during interim status.   If the cost
 estimate is-obviously completely  inadequate, the Regional Administrator
 may start an enforcement action or he  may request part B of the permit
 application  and revise the cost estimate as part of the  permit  applica-
 tion  process.

      Unfortunately,  the annual report  of the facility,  though it must
 include  the  cost estimate, does not contain adequate information to
 determine the accuracy of the cost estimate.  Therefore,  in order to
 check on the adequacy of the cost estimate,  it may be necessary to visit
 the facility.   An  inspector could then obtain copies of  the post-closure
 plan  and cost estimate and conduct a quick  review of the key  variables
 for the  post-closure plan, as discussed in  Section 12.0  of  the  draft
 guidance for Subpart G,  Closure and Post-Closure Care.

      Table 6-1  shows the costs of certain activities  which  may  be asso-
 ciated with  post-closure cost estimates.  This  is  a  list  of  selected
major activities,  and is not intended  to reflect all  possible post-
closure  activities.   These activities  have  been broken down by  key cost
elernencs rather  than by  elements  of the post-closure  plan.  For  example,
one heading  in  Table 6-1 is  "Inspections and Facility Visits."   The  table
simply shows  the expected costs of  such visits  per hour  on-site.  Deter-
mining the number  of inspections  and facility  visits  required will be

                                    6-2

-------
 highly site-specific and will depend upon the post-closure plan.  Further,
 these inspections and facility visits may serve a variety of purposes in
 the post-closure plan.  For example, inspections and facility visits may
 be for the purpose of ensuring adequate erosion control, maintaining
 surveyed benchmarks, obtaining ground-water monitoring samples, or check-
 ing the adequacy of leachate collection facilities.

      Table 6-1,  for each activity indicated, shows an estimate of unit
 costs and notes  the sources of variation in these unit costs.  The unit
 costs are given  in 1980 dollars.   In order to maintain the accuracy of
 Table 6-1, it should be updated on an annual basis to reflect inflation.
 A. discussion of  the methods for adjusting the cost estimates to account
 for inflation is provided in Section 8.0.  The sources of variation in
 unit costs are specific to the headings listed.   Two generic sources of
 variation, however,  have not been noted.   First,  all costs can be
 expected to vary regionally and locally.   Ideally,  these national esti-
 mates of unit costs  should be replaced by costs  developed from experience
 for the region or state in which  the facility is  located.  Second,  all
 costs will vary  with the remoteness  of the facility.   Since most post-
 closure activities  are relatively small in scale  and  may involve only
 a  few days on-site,  significant travel time to and  from the facility
 will have  a noticeable effect on  almost all costs.

 5.1   INSPECTIONS AND FACILITY VISITS

      As  noted above,  inspections  and facility visits  may be needed for a
 variety  of purposes.   The  unit  costs given will thus  be  relevant  in
 checking  the  costs of  a  variety of activities.  The  estimated unit  costs
 in  1980 dollars  are  $20  to  $100 per  hour  on-site.  The chief  source  of
 variation  in  these unit  costs will be  the  professional level  of  the
 personnel  involved.  It  will normally  be useful to have an inspection or
 facility visit by a  professional  engineer  at  least once  a year.   Inspections
 and  facility  visits  by less  technically qualified personnel will  depend  upon
 Che specifics of the post-closure plan, the climate, and  the  size and
nacure of  the facility.

                                   6-3

-------
                                TABLE 6-1

                COSTS  OF SELECTED POST-CLOSURE ACTIVITIES
     ACTIVITY
UNIT COSTS*
SOURCE OF VARIATION
   IN UNIT COSTS**
  1. Inspection/Facility
     Visits

  2. Reestablishing
     Cover and  Vegetation
  3. Fertilizing
  &.  Mowing

  5.  Ground-water
     Monitoring

  6.  Maintaining ana
     Replacing Fences

  7.  Collecting, Removing
     and Treating Leachate
$20-100/hr. on-site   Professional level
                      of personnel
S300-1500/acre
$50-200/acre


$10-30/acre

S200-600/well


S.20-.80/f=./yr.


S. 20-.80/gallon
Amount of erosion
Nature of cover
Type of soil
Amount & density
  of seed

Amount of fertilizer
Method of spreading
Monitoring plan
requirements

Type of fence
Climate

Chemical composition
  1980 dollars.
**
  All costs of all activities vary by region and with the remoteness
  of the facility.
                                 6-4

-------
6.2  REESTABLISHING COVER AND VEGETATION

     Reestablishing cover and vegetation may be necessary for a variety
of purposes, including:

     •  Replanting to establish vegetation not adequately established
        during closure;
     •  Replanting to repair minor erosion or rodent control
        problems ;
     •  Reestablishing cover lost as a result of a major contin-
        gency, such as a major storm or flood; and
     •  Reestablishing cover to correct for subsidence problems.

     The costs of this activity in 1980 dollars may range from S300  to
$1,500 per acre.  This cost will vary according to the nature of the
cover, the type of soil used, and the amount and density of seed.  In
addition, the costs can be expected to vary according to the amount of
erosion or subsidence which necessitates replacing the topsoil or cover
material.  The lowest costs are for simple replanting, and the highest
are for reestablishing and compacting as well as reseeding substantial
portions of the clay cover and topsoil.

6.3  FERTILIZING

     Depending upon the vegetation, topsoil employed, and climate, some
fertilization may be necessary.   The frequency will be highly variable.
The estimated range of costs for this activity is $50 to S200 per acre
with the variation dependent upon the amount of fertilizer and the
method of spreading it.

6.4  MOWING

     Mowing is necessary in any climate in which deep rooted vegetation
Jiay readily be established.  In most cases,  it will be the most  cost
effective means of preventing such deep rooted vegetation.  In some

                                   6-5

-------
 climates,  mowing requirements may be minimal or tnere may be more cost
 effective  methods than mowing for ensuring that deep rooted vegetation
 does  not become established.  The estimated range of costs in 1980
 dollars  is S10 to $30 per acre.
6.5   GROUND-WATER MONITORING

      At  all  facilities,  a ground-water monitoring program of  some  kind
will  be  required.   In addition to the costs of associated site  visits
to gather  samples,  these costs will be based on the  average costs  of
the tests  required,  which are the result of the monitoring plan require-
ments .

6.6   MAINTAINING AND REPLACING FENCES

     Many  facilities will be required to have some kind of fence as
security during the  post-closure  period.   Assuming the use of some type
of chain link  fence, provision will need to be made  for replacing  the
fence at least once  over the 30-year post-closure period.  In addition,
some provision must  be made  for inspecting and maintaining the  fence.
It is estimated that the cost of  such maintenance and replacement will
be S.20  to S.80 per  linear foot of  fence per year.   The variation  is
dependent upon the type  of fence  used and the severity of  the climate.

6.7  COLLECTING, REMOVING, AND TREATING LEACHATE

     At some facilities,  a system for collecting, removing, and treating
leachate may be required during post-closure.   The estimate given here is
based on the assumption  that a small amount of  leachate will be collected
periodically and removed to  an off-site TSDF.   The costs of an extensive
leachate collection  system requiring treatment  on-site would normally be
much higher.  The estimated  range  in costs  is  from $.20 to $.80 per
gallon of leachate removed,  with  the range  in  the costs depending in part
upon the chemical composition of  the leachate.
                                   6-6

-------
      7.0  REVISING THE CLOSURE AND POST-CLOSURE COST ESTIMATES

     The closure and post-closure cost estimates must be revised when-
ever a. change in the closure or post-closure plan is made that affects
the costs of closure or post-closure care.  Changes to closure and post-
closure plans are discussed in Sections 11.1 and 11.2 of the guidance
for Subpart G of the Interim Status standards.  Changes in the closure
plan which may cause a revision in the closure cost estimate include:

     •  Change in facility size and/or capacity;
     •  Changes in technology that may affect treatment and disposal or
        decontamination techniques,  type of cover chosen,  etc.;
     •  Changes in the closure schedule which alter the length of
        the closure period by greater than one month (e.g.,  severe
        weather conditions may halt construction activities and
        extend the  closure period  by more  than one  month);
     •  Changes in the schedule of periodic activities  which
        affect activities  required at closure  (e.g.,  failure  to
        partially close a  facility would mean  that  a larger  area
        than  previously estimated  would need to  be  closed at
        closure;  the  closure  plan  must  always  account  for  the
        maximum  extent  of  the  operation open at  any  time over  the
        life  of  Che  facility);
    •   Changes  in  types and/or quantities  of  wastes chat affect
       activities  required at closure  (e.g.,  the type and/or
       quantity  of waste  on-site  at  closure will affect the
       choices of  treatment and disposal;  for example, the amount
       of waste removed to an off-site TSDF by the owner or operator of
       an incinerator depends on  the types and quantities of resid-
       uals that remain after burning the wastes.  The
       types and quantities of waste can also affect monitoring
       requirements and cover requirements);
                               7-1

-------
     •   Change  in maximum quantity of inventory ever expected on-
         site;
     •   Change  in cover requirements from what was  originally
         proposed;
     •   Changes  in ground-water monitoring requirements  as  a  result
         of  an owner's  or operator's operating experience or new data
         which was not  available when the plan was written.  The ground-
         water monitoring regulations stipulate that all  or  part of the
         requirements may be waived if there is a low potential  for
         pollution (§265.90).  Revisions  will also be likely when the
         EPA provides more guidance and  technical engineering  data on
         the kinds of monitoring appropriate for hazardous wast3 facil-
         ities; and
     •   Operating contingencies during  closure which may affect closure
         requirements (e.g. ,  inclement weather causes construction
         problems;  more  contaminated soil needs to be disposed
         at  closure than anticipated as a result of  problems occurring
         during operation) .

     Changes in  the post-closure plan which  niay cause a  revision m cne
post-closure cost  estimate  include:

     •   Change in  facility  size which will  affect the extent of
        maintenance required;
     •  Changes  in monitoring  requirements  as  a  result of an
        owner's or operator's  operating  experience,  new  data which was not
        available when  the  plan was written  or modifications approved by
         the Regional Administrator  (e.g., changes in  the number of wells
        monitored and samples,  the  frequency of analyses, types of
        analyses required) .  During the  30-year post-closure
        period,  the owner or operator may petition the Regional
        Administrator to discontinue or  alter  the monitoring
        requirements; alternatively, under certain circumstances,
                                   7-2

-------
    the  Regional Administrator  may  require  an  owner  or  operator
    to continue monitoring beyond 30  years.  Revisions  will also
    be likely when  the EPA provides more  guidance  and  technical
    engineering data on  the kinds of  monitoring  appropriate
    during post-closure;
•   Changes in annual"routine maintenance,  including changes
    in the nature and frequency of  the activities  required
    (e.g., a more extensive erosion control program may be
    required than originally anticipated);
•   Changes in activities required on an  intermittent basis
    or changes in the frequency of these  activities  (e.g.,  an
    accelerated replanting schedule or more frequent replace-
    ment of wells than anticipated);
•   Operating contingencies which occur during the life of  the
    facility or pose-closure which affect post-closure  ac-
    tivities (e.g.,  severe weather conditions affecting acti-
    vities required for erosion control, cover maintenance,
    or maintenance of diversion structures);
•   Changes in surrounding land use  (e.g., if the population
   density increased,  the measures  needed to maintain
    facility security might change;  ground-water monitoring
   program might be affected);
•  Changes in monitoring and maintenance technology; and
•  Modifications approved by the Regional Administrator;  the
   owner or operator may petition the Regional Administrator
   to allow some or all  of the requirements for post-closure
   to be discontinued  or altered before the post-closure  period
   is ended;  any such  changes  can only  be made after the
   post-closure  period begins  and would constitute a revision
   to the post-closure plan  made  during post-closure.
                             7-3

-------
      Revisions may be desirable chat either raise or lower the closure
and  post-closure  cost estimates.   For example,  the closure cost estimate
may  need  to  be revised and increased if partial closure schedules  are
not  met or if  there is unexpected  accumulation  of inventory due to
temporary problems at the facility.   It is  quite possible, however,  that
the  cost estimate may need to  be revised  downward.  A facility may have
very  large inventory due to temporary start-up  problems at the time  the
cost  estimate  is  first developed which is later reduced to a more  normal
inventory. In  such a situation, revising the closure  cost  estimate
downward would  be reasonable.   It  is also possible,  given  the  rapid
development  in some types of hazardous waste disposal,  that new technol-
ogies may offer much less expensive  means of carrying out  certain
activities than are now envisioned.   This would also be a  legitimate
cause for revisions of the plan and  cost estimate.
                                   7-4

-------
                     8.0  ADJUSTING THE COST ESTIMATES
                            TO ACCOUNT FOR INFLATION

      Subpart  H  of  the  Interim Status  Standards  requires that both the
 closure  and post-closure  cost estimates be adjusted annually for infla-
 tion.  This adjustment is  to  take  place on the  anniversary of the
 effective date  of  the  regulations,  November 19,  1980.  Although owners
 or  operators  of  land disposal facilities are  not required to have
 estimates available until  May 1981  (six months  from the effective date
 of  these regulations) ,  all owners  or  operators  are  required to  adjust
 their estimates  beginning  in  November 1981 and  annually thereafter.
 Adjustments of  the post-closure cost  estimate for inflation need not
 take place once  the facility  is closed.

     Data for calculating  the  inflation  adjustment  factor must  be ob-
 tained from the  "...annual  Implicit Price  Deflator  for  Gross  National
 Product as published by the U.S. Department of Commerce."*  This  price
 deflator is published  in the  Survey of Current Business,  a U.S.  Depart-
 ment of Commerce, Bureau of Economic  Analysis, publication,  and  in
 Economic Indicators, a Council of Economic Advisors  publication.  These
 documents are published monthly and subscriptions may be  obtained  from
 Superintendent of Documents,-U.S. Government  Printing Office,
Washington, D.C., 20402.  This information also may  be  obtained by
calling the Bureau of Economic Analysis, U.S. Department  of Commerce.

     The GNP price deflator was chosen as an appropriate  inflation index
and is more, accurate than the more readily available Consumer Price
Index and Wholesale Price Index.  However, it is not as widely published
as the other two indices.   Thus, the  typical hazardous waste  facility
owner or operator,  in the normal course of his business, will not have
data on the implicit price deflator for GNP or copies of  the Survey of
Current Business or Economic Indicators.  Copies of   these publications
*EPA Interim Status Standards, 40 CFR §265.142(c)

                                   8-1

-------
 also may not be readily available in small libraries co which the
 owner or operator might have easy access.  As a result, the EPA
 Regional personnel must have available the most recent editions of
 che Survey of Current Business or Economic Indicators and provide the
 necessary adjustment factor to owners or operators who telephone or
 write for this information.

      Table 8-1 shows a sample  of the section in the Survey of Current
 Business  in which the GNP implicit price  deflator  may be  Eound.   The
 table is  constructed to show how this section might appear on 19 Novem-
 ber  1981,  the "first anniversary of  the effective  date  of  the regula-
 tion."  The numbers  shown are  hypothetical,  as this guidance  document is
 being  written in  May 1980.   The  implicit  price deflator to be used  is
 the  first  for which  numbers appear,  i.e.,  the one  labeled  Gross  National
 Product as  underlined in Table 8-1.   The  note "Index,  1972=100"  may be
 ignored.   The method of calculating  the inflation  adjustment  factor
 required by the regulation  makes  the index year chosen  and changes in
 the  index  year irrelevant.   The regulation states:

      "The  inflation  factor  must  be calculated by dividing  the
      latest published annual Deflator by  the  Deflator  for  the
      previous  year."*

GNP deflators  are  normally  developed both quarterly and annually.  The
 regulation  requires  the  use  of the deflator listed  in the  column headed
 "annual totals."   The quarterly data should be  ignored  entirely.  The
calculation of the inflation adjustment factor should use,  for the
 Latest published  annual  implicit  price  deflator, the deflator  for 1980
 (circled in the chart).   The deflator  for the  previous  year will then be
EPA Interim Status Standards, 40 CFR §265.142(c).
                                     8-2

-------
                       TABLE 8-L
HYPOTHETICAL SAMPLE PACK OF SURVEY OF CURRENT BUSINESS

^

oo
OJ









is in
ri/'j
IWII
Alum 1 1 I..I il
I'llH
III IV
I'l/'J
1
I.IIIIKAI iinsiiii". i mill. MI IK:,

•I 	 Iv 	 '.iMsiuiil ly Ail|.islr,l )
iiii|.iii ii |u i i- .ii-ri ui'.i .
tin •! Ni l..iil |.i,..lii,l hull i., llli'Hnl
HIM il.i i. ....i ... . ,i,,
ii 	 i.u ill • i: 	 	 . ,i..
'•• 1 Vl, . . ,|,, .
i.i,... pi 1 v.i . .l.,ini. .1 I, luv. Hliiii'iil .
1 1 hi' 1 luv 1 	 1 . «|,i
II. .111 .1.1. il 1 il . ,|,,
((.•-.I I. ul l.il . . . ,).,
*»IVI 	 Ill 1*. Ill |..l,l.l . .111,1 M'lvllts .1.1
'••I. Il . .1.,
Si .il 	 1 li>. 1 1 ,),,











	










(T/sjj,









IM /,;









I Mi All









K.II II







II
1(1 1 II ll'l 1


IM rtl







III 1 IV
I'dllP
• ~f M
"in"
IV
(.
1
II
V SIM 1.". -('.ml liiui .1


\hl H\









I/O II,









l/ll /'•









I/ . I/,









'"' '''









I// Ml









IIH II









ll'l 1,1,




;

i
1
                                                                               IHI M.

-------
 che deflator  cor  1979  (also circled  LI  che  chare).*  Using che example

 provided, che inflacion adjusCmenc faccor is  Chen calculated as che

 annual implicic GNP deflacor for  1980 divided by che annual iraplicic GNP
 deflator for  1979, as  follows:
                                  175.13
                                  165.50
 resulting in an inflation adjustment  faccor of 1.058.  This number is

 Chen multiplied by the last cost estimate to obtain the new current cost

 estimate.  These numbers are hypothetical and do not represent actual

 1981 data; they are presented solely  to illustrate how to use the Survey

 of Current Business to make che necessary calculation.
*The GNP implicit price deflator for a given year may be subject to
revision.  If the figure cited in a previous issue is different from
the figure cited for the same quarter in che current issue, the owner
or operator should use the current figure.  If the owner or operator
is requesting this information by telephone, he should ask for the GNP
implicit price deflator for the previous year and for the year prior
to the previous year.
                                   8-4

-------
                        9.0   SAMPLE  COST ESTIMATES

9.1   INTRODUCTION

      This  section  provides samples  of  cost  estimates  for closure  of
surface  impoundments, land treatment facilities, landfills,  inciner-
ators, and a  multiple process  facility with tanks and  small surface
impoundments.  A sample post-closure cost estimate for landfills  is also
provided.  The purpose  of these sample cost estimates  is to  illustrate
the concepts  involved in a proper cost estimate and suitable  formats
which might be employed.  However,  neither  the cost estimates  in  total
nor the  unit  costs are designed to  be  applicable to any specific
facility.  Neither the total costs  nor the  unit costs used in
these cost estimates should be considered targets when the owner  or
operator prepares his own cost estimate.

      The cost estimates are prepared in the  form of a series of work-
sheets.  This was considered the simplest mechanism for providing a
careful, easily checked cost estimate.  In  the sample cost estimates
given, each worksheet is accompanied by an  explanation of each item on
the worksheet.  These explanations  are designed to help indicate how the
worksheet was developed.  Explanations of this type would not be appro-
priate in the cost estimate prepared by the owner or operator.  Instead,
the owner or operator would include, for each item in the cost estimate,
reference to the appropriate section of the closure or post-closure plan
as applicable, and any necessary documentation as to the accuracy of
specific unit costs.
                                9-1

-------
9.2                   EXAMPLE -  SURFACE  IMPOUNDMENTS

     Sludge  from an  industrial  wastewacer  treatment  plant is pumped  to
a four-acre  surface  impoundment for  stabilization.   It  is assumed that
at the time  of closure,  the  contents of the  impoundment will measure a
depth of 3 feet; this material  will  be  90  percent water and 10 percent
solid sludges.  The  total  depth of the  impoundment will be 5 feet
(allowing 2  feet of  freeboard above  the surface of the  liquids) .  It
is further assumed that  all  necessary equipment required to complete
closure will have  to be  rented,  as none is available on-site (the
costs of equipment rental  and manpower  will  be factored into the unit
cost estimates for various operations).  The costs of closure are
developed for two options: 1) completely disposing of wastes on-site,
and 2) removing all  hazardous materials  from the facility prior to
closure.
                                   9-2

-------
               SAMPLE CLOSUR^ COST ESTIMATING WORKSHEETS:
          SURFACE IMPOUNDMENTS IN WHICH WASTES REMAIN AT CLOSURE

 A-    Removing  Free  Liquid  and Decontaminating the Facility
      In  this case,  it is assumed that  free  liquids can be removed by
 evaporation.   Alternative  possibilities that might be necessary and would
 result in somewhat  different  cost estimates  are  the transporting of free
 liquids  to an  off-site TSDF and  the  disposing of free liquids into surface
 waters after suitable treatment,  either through  a treatment facility already
 in place  or a  package treatment  facility.   For this example,  all contam-
 inated soil is disposed of in the impoundment; therefore,  no  additional
 costs are associated with decontaminating the soil.
      1.   Method  used:  As noted  above,  the  method used for removing the
 free liquid is evaporation.
      2.   Time required to evaporate liquid:   The calculations  to  justify
 this time would be  taken from the closure plan.   It  is  assumed  that  70 days
 would be  required for evaporation of free liquids.
      3.   Cost of routine operations per day:  This  includes  the cost of
 inspecting the facility required  once a week  and  any  minor  maintenance
 work that would need  to be done as a result of these  inspections.
      4.   Cost of maintenance during evaporation  (Line  2 x  Line 3):  Cost
 of routine operations  at S10  per  day times 70  days  results  in a total cost
 of maintenance of S700.
      5.   Volume of  remaining sludge:  The volume of  the remaining sludge
 is given  as 1936 cu.  yds. based on the initial assumption that  the liquid
 in the pond is 10 percent sludge.
      6.   Source of  sorbent materials:  In this case, the sludge is  to be
 solidified  and buried  on-site in  the surface  impoundment.   As a result,
 sorbent materials are  needed.  It  is assumed,  for  the example,  that  sorbent
 materials  must be purchased off-site.
      7.   Cost of sorbent materials:  Assume  that  sorbent materials  (e.g.,
 cement kiln dusts) are  needed  on  a one-to-one  ratio to  the  sludge and must
be purchased with a delivered  cost of S3.25 per cu. yd.  The  total cost
 is 36,292.
      8.   Unit cost of  mixing  and stabilization:   The unit  cost of mixing
 soroent material with  sludge  is assumed to be  SI.60 per cu. yd.
                                   9-3

-------
      9.  Cose of mixing and stabilization:  This is calculated as 1936 cu.
 yds. of sludge plus 1936 cu. yds. of sorbent material, for a total of 3872
 cu. yds.  This is multiplied times $1.60 per cu. yd., to give a total cost
 of $6,195.
     10. Total cost of removing free liquids and sludge stabilization
(Line 4 + Line 7 + Line 9):  The sum of the above costs is $13,187.
     11. Decontaminate equipment:  The assumed costs for decontaminating
equipment is $500.
     12. Decontaminate and  flush any pumps or liquid lines:  The assumed
costs for decontaminating equipment is S2000.
     13. Disposing or treating residues from decontamination:  Assume that
the costs for disposing or  treating liquids and  residues from the above
decontamination processes is $1000.
     14. Total costs of all activities on Worksheet A  (Line 10 + Line 11 +
Line 12 + Line 13):  The sum of these activities is $16,687.

3.    Placing Final Cap
     1.  Area to be capped: The area directly requiring a cap is  4 acres
(19,360  sq. yds.)  In addition, it  is assumed that  an  additional acre of
land area  (4840 sq. yds.) surrounding the  impoundment, containing  dikes,
etc., will  require vegetation  and,  therefore, must  undergo some prepara-
tion.
     2.  Required  impermeable  material:   It  is assumed that  25,813 cu. yds.
of  impermeable material will be  required  (19,360 sq.  yds.  x  4 ft.  depth).
     3.  Source of impermeable material:   It  is  assumed  that suitable
impermeable material  can  be obtained  through  bulldozing  dikes and  other
appurtenances on-site.
     4.  Cost of  material:   Since  the material  is  available  on-site,  there
will be no  cost.
     5.  Required topsoil:   At the sample facility, it is  assumed  that  2  feet
of  the  topsoil will  be  required in order  to ensure adequate  cover  so  chat
 roots  of the  vegetation will not  penetrate the cap.  It  is,  therefore,
 assumed that  16,133  cu.  yds.  of topsoil (24,200  sq. yds.  x 2/3  yd. depth)
will be required.
      6. Source of topsoil:  In this case, it is assumed that  topsoil is
 available  on-site at a relatively short haul.
                                    9-4

-------
      7.  Cost of  topsoil:   Since  the  copsoil is available on-site,  there
 will be no cost.
      8.  Cost per cubic  yard for  hauling,  compacting  and grading:
 It is assumed in this case that the unit  cost of  those  services  is
 $1.60.
      9.  Cost of  placing impermeable  portion of cap  (Line 2 x  Line
 8):  The result  of these  assumptions is  that the cost  of the cap
 in place (with suitable grading) is $41,301.
      10.  Cost  of placing topsoil (Line 5  x Line 8):  The cost of
 placing the topsoil,  given the above assumptions, is $25,813.
      11.  Total cost  of  cap  (Line 4 + Line 7 + Line 9 + Line 10):
 Summing the above  elements,  the total  cost  for the capping operation
 is 567,114.

 C.    Planting Final Vegetation
      1.  Area to  be vegetated:  The area to be vegetated is assumed to
 be 5 acres.
      2.  Type of  vegetation  to be used:  The closure  plan specifies that
 coarse field grass  (a  mixture of rye grasses and Kentucky fescue) will
 be employed for  final  vegetation.
      3.  Quantity of  seed per acre:   Based on discussions with facility
 operators,  we assume that  150 pounds of seed will be used per acre.
      4.  Cost of  seed per pound:  Calls to local suppliers determined
 that seed is available at  $.50  per pound.
      5.  Total cost of seed  (Line 1 x Line 3 x Line 4):  Given the
above assumptions, the total  cost  of seed will be $375.
      6.  Type of  fertilizer  to be used:  Given the topsoil and
climatic conditions at the sample  site, 10/10/10 fertilizer is
assumed to be adequate.
      7.  Quantity of  fertilizer per acre:   Discussions with local
suppliers indicated that  .25  tons  per acre would be a reasonable
 fertilizer application rate.
      8.  Cost of fertilizer  per ton:   Calls to local suppliers determined
 that fertilizer is available  for S200 per ton.
      9.  Total cost of fertilizer (Line 1 x Line 7 x Line 8):   Given
the above assumptions, the total cost of fertilizer will be $250.
                                    1-5

-------
       10.   Cost  of soil preparation per acre:   Soil preparation,  including
both  disking and fertilizing,  is assumed to be $135 per acre  (including
equipment  rental costs).
       11.   Total cost of  preparing soil (Line  1 x  Line  10):   The  total cost
of preparing soil (excluding materials) is  assumed to be $675.
       12.   Cost  per acre  for seeding:   It is assumed that seeding the
sample site will cost $200 'per acre (including equipment rental costs).
       13.   Total cost of  seeding (Line  1 x  Line 12):  The total cost of
seeding (excluding materials)  is assumed to be $1000.
       14.   Cost  per acre  of mulching:   The  cost per acre of purchasing
and applying a hay mulch  is assumed to  be $140.
       15.   Total cost of  mulching (Line 1 x Line 14):   The total  costs of
mulching (including the costs  of hay) are assumed  to be $700.
       16.   Total costs  for vegetation  (sum  of  Lines  5, '9, 11, 13, and 15):
Total  costs  for  establishing vegetation are $2950.

D.  Ground-water Monitoring
       Assume that  closure of the surface impoundment will require a total
of 90  days.   In  order to  determine the  maximum possible ground-water
monitoring  costs,  the most extensive monitoring  needed  at closure is
assumed.  Assuming that ground-water quality analyses are required
annually and ground-water contamination analyses are required semi-
annually, the most expensive case is that in which both  sets *of analyses
are required during the 90-day closure  period.
       1.  Number of wells monitored:  For the  sample surface impoundment,
it is  assumed that six  wells would need to  be  monitored.
       2.  Number of samples per well:   One  sample is taken per well for
both analyses.
       3.  Total  number  of samples (Line 1 x Line 2):  Given the above
assumptions, six samples  are required.
       4.  Number of hours required for  collecting the sample:  It is
assumed that experience has shown that  two  hours are sufficient to gather
samples from each  well.
       5.  Total  number  of hours  required  for collecting  the samples
(Line  3 x Line 4):   For six samples, 12 hours would be  required for
collecting  the samples.
                                    9-6

-------
       6.   Number of hours required for preparing and delivering the sample:
 It is  assumed for the example that this can be done in two hours.
       7.   Person-hour costs for collecting samples:  Assume that the fully-
 loaded costs  for labor required for sample collection, preparation and
 delivery  averages $15 per hour.
       8.   Total sample and. collection costs ((Line 5 + Line 6)  x Line 7):
 This results  in total sampling and collection costs of S210.
       9.   Number of ground-water quality analyses:  One analysis must
 be made for each well sample,  for a total of six.
       10.  Number of ground-water contamination analyses:   One  analysis
 must be made  for each well sample,  for a total of  six.
       11.  Unit cost of ground-water quality analysis:  It is assumed
 that the  cost  of an analysis  for the following parameters  is $77 per
 sample:
                          Chloride -  $6.00 per sample
                          Iron  -  $12.00  per sample
                          Manganese - $12.00  per  sample
                          Phenols  -  $25.00 per sample
                          Sodium  - $12.00  per sample
                          Sulfate  - S10.00 per sample
       12.   Unit  cost  of  ground-water  contamination analyses:  It is
assumed that the  cost  of  an analysis  for  the following parameters is
$108 per sample:
                          pH -  S4.00  per sample
                          Specific Conductance -  $4.00  per  sample
                          Total Organic Carbon -  $25.00  per sample
                          Total Organic Halogen - $75.00 per sample

      13.   Total ground-water quality analysis costs (Line 9 x Line 11):
For six samples at $77 per analysis,  this yields a  total cost of $462.
      14.   Total ground-water contamination analysis costs (Line 10 x
Line 12):   For six samples at $108 per analysis, this yields a total
cost of $648.
      15.   Total analyses costs  (Line 13 + Line 14):  The total analyses
costs,  therefore, are $1,110.
                                   9-7

-------
       16.  Number of technical hours for administration:  This includes all
 time necessary to administer and report the data from the analysis and is
 estimated as eight hours.
       17.  Person-hour technical costs:  The fully-loaded cost required
 for this work is assumed to be $30 per hour.
       18.  Total technical costs for administration (Line 16 x Line 17):
 Given the above assumptions, total costs for administering the tests are
 assumed to be S240.
       19.  Number of clerical hours:  Assume for this case that five hours
 of  clerical time are required to produce the necessary reports.
       20.  Person-hour clerical costs:   Assume the fully-loaded costs for
 clerical work are $8 per hour.
       21.  Total clerical costs (Line 19 x Line 20):   Given the above
 assumptions,  the total clerical costs are $40.
       22.  Total administrative costs (Line 18  + Line 21):   The sum of
 technical and clerical costs are then $280.
       23.  Monitoring equipment maintenance:   It is assumed that  an
 average of $150 is required for a 90-day period to ensure adequate
 maintenance of adnitoring equipment and ,wells.
       24.   Total monitoring costs (Sum of Lines 8,  15,  22,  and 23):
 Total  monitoring costs,  excluding administration and  contingencies,  are
 then  S1750.

 E.  Fence Maintenance
       In  this  case,  it  is assumed that  the  area to be  enclosed is 5  acres
 (24,200 sq.  yd.).  Assuming that  the site  is square, each side is 156
yards.  The perimeter of  the site is then  624 yards.
       1.   Length of  fence to be replaced:   Since this  facility is to  retain
hazardous compounds,  the  integrity  of its  security fence  is  important.
Our estimate  is  that  10%  of the existing perimeter security  fence will
have to be replaced due  to  wear and corrosion.
       2.   Unit  cost of  replacing  fence:  The security  fence  is  a galvanized
6-foot high chain link  fence made of #9 wire.   The installed unit cost
of replacement  sections  is  $13.06 per linear foot.
                                    9-8

-------
       3.   Total cost of replacing fence (Line 1 x Line 2):
 The cost  of replacing the damaged fence sections is the product of the
 length of fencing needing replacement and the unit cost of  replacing
 the fence,  for a total of $2429.

 F.     Professional Certification
       1.   Number of person-hours  required for inspections:   It is assumed
 that 80 hours  are required for periodically inspecting all  aspects of
 closure of  the surface impoundment.
       2.   Cost per person-hour:   In  this  case,  assume  that  a registered
 independent professional  engineer may be  hired  at  a cost  of $75 per hour.
       3.  Total costs  of  independent  professional  engineer's time (Line
 1 x Line  2):   This yields a  total cost of $6000 for the independent
 professional engineer.
       4.  Number of technical  hours required  for administrative duties:
 Assume that eight hours are  required  from the owner's  or  operator's  staff
 for  administrative duties  connected with  employing  an  independent
 professional engineer.
       5.  Person-hour  costs  for technical administrative  duties:   It  is
 assumed that the  total fully-loaded costs  for the owner's or operator's staff
 are  S30 per hour.
       6.  Total  administrative costs  for  technical  labor  (Line  4 x Line
 5):  Given  the  above assumptions,   the  total administrative costs for
 technical labor are $240.
       7.  Number  of clerical hours required for administrative duties:
Assume that  five  hours of clerical time are required for  the necessary
 typing and  certification.
      8.  Person-hour costs for clerical administrative duties:  Fully-
 loaded costs of clerical time are assumed to be $8.
      9.  Total administrative costs for clerical labor (Line 7 x Line 8):
Given the above assumptions, total clerical costs are $40.
      10.   Total administrative costs  (Line 6 + Line 9):  Summing	  '
technical and clerical labor, the  total administrative costs are $280.
      11.   Total certification costs (Line 3 + Line 10):  The total costs
for certification, including the engineer's fees and administrative costs,
is  then S6280.

                                   9-9

-------
G.   Total Costs  Including Administration and Contingencies
     Items 1 through 6  give the costs of all activities on each of the
preceding worksheets.   Line 7 is  the total of Lines 1 through 6,
397,210.
     8.  Administration:  For administrative tasks, including taxes,
insurance, and administration and supervision not included elsewhere,
a total of 15 percent of  total costs from Line 6 is used.
     9.  Contingencies:   A general provision for contingencies of 15
percent of Line 6 has been included.
     10.  Total costs of  closure  (Line 7 + Line 8 + Line 9):   The
estimated total costs for closing the surface impoundment for the situation
in which all wastes remain in the impoundment are estimated for the sample
case to be 3126,373.
                                  9-10

-------
                           SURFACE IMPOUNDMENTS
                    (All wastes  remain  in impoundment)
                    WORKSHEET  A  -  REMOVING FREE  LIQUID
                    AND DECONTAMINATING  THE  FACILITY
 1.
 2.
 3.
 4.

 5.
 6.
 7.

 8.
 9.
10.

11.
12.

13.

14.
Method used
Time required to evaporate  liquid
Cost of routine operations  per day
Cost of maintenance during  evaporation
(Line 2 x Line 3)
Volume of remaining sludge
Source of sorbent materials
Cost of sorbent materials
($3.25/cu. yd.; 1.1 ratio)
Unit cost of mixing
Cost of mixing and stabilization
Total cost of removing free liquids and sludge
stabilization (Line 4 + Line 7 + Line 9)
Decontaminating equipment
Decontaminating and flushing pumps and liquid
liners
Disposing or treating residues from
decontamination
Total costs of all activities
(Line 10 + Line 11 + Line 12 + Line 13)
Evaporation
70 days
$10
$700

1936 cu. yds.
Off-site
$6292  •

$1.60/cu. yd.
S6195
313,187

SSOO
$2000

$1000

$16 -, 687
                                   9-11

-------
                            SURFACE  IMPOUNDMENTS
                     (All wastes  remain in  impoundment)
                          WORKSHEET  B  - FINAL  CAP
 1.   Area to be capped                                        19,360 sq. yds.
 2.   Required impermeable  material  (including                 25,813 cu. yds.
      provision for suitable  slope)
 3.   Source of material                                       On-site
 4.   Cost of material                                         0
 5.   Required topsoil                                         16,133 cu. yds.
 6.   Source of topsoil                                        On-site
 7.   Cost of topsoil                                          0
 8.   Cost per cu. yd. of hauling, compacting, and             $1.60
      grading impermeable material
 9.   Cost of impermeable portion of cap                       $41,301
      (Line 2 x Line 8)
10.   Cost of placing topsoil (Line 5 x Line 8)                $25,813
11.   Total cost of cap (Line 4 + Line 7 + Line 9 4- Line 10)   $67.114
                                     9-12

-------
                           SURFACE IMPOUNDMENTS
                    (All wastes  remain in impoundment)
                 WORKSHEET C  -  PLANTING FINAL VEGETATION
 1.   Area to be vegetated
 2.   Type of vegetation  to be used
 3.   Quantity of seed per acre
 4.   Cost of seed per pound
 5.   Total cost of seed  (Line 1 x Line  3  x Line 4)
 6.   Type of fertilizer  to be used
 7.   Quantity of fertilizer per acre
 8.   Cost of fertilizer  per ton
 9.   Total cost of fertilizer (Line 1 x Line  7  x
      Line 8)
10.   Cost of soil preparation per acre  (excluding
      materials)
11.   Total cost of preparing soil (Line 1 x Line 10)
12.   Cost per acre of seeding (excluding  materials)
13.   Cost of seeding (Line 1 x Line 12)
14.   Cost per acre of mulching
15.   Total mulching costs (Line 1 x Line  14)
16.   Total costs for vegetation
      (Line 5 + Line 9 + Line 11 + Line  13 -I- Line 15)
5 acres
Coarse grass
150 Ibs.
$.50/lb.
$375
10/10/10
.25 tons
$200/ton
$250

S135

$675
$200
$1000
$140
$700

$2950
                                   9-13

-------
                           SURFACE IMPOUNDMENTS
                    (All wastes  remain in impoundment)
                   WORKSHEET D - GROUND-WATER MONITORING
 1.   Number  of wells  monitpred
 2.   Number  of samples  per well
 3.   Total number  of  samples  (Line  1  x Line  2)
 4.   Number  of hours  required for collecting the
      sample  (per sample)
 5.   Total number  of  hours required for collecting
      the samples (Line  3  x Line 4)
 6.   Number  of hours  required for preparing  and
      delivering samples
 7.   Person-hour costs  for collecting  samples
 8.   Total sampling and collection  costs
      ((Line  5 + Line  6) x Line  7)
 9.   Number  of ground-water quality analyses
10.   Number  of ground-water contamination analyses
11.   Unit cost of  ground-water  quality analysis
12.   Unit cost of  ground-water  contamination
      analysis
13.   Total ground-water quality analysis costs
      (Line 9 x Line 11)
14.   Total ground-water contamination  analysis costs
      (Line 10 x Line  12)
15.   Total analyses costs  (Line 13  + Line 14)
16.   Number  of technical  hours  for  administration
      (e.g.,  reporting data to EPA)
17.   Person-hour technical costs
18.   Total technical  costs  for  administration
      (Line 16 x Line  17)
19.   Number  of clerical hours
20.   Person-hour clerical  costs
21.   Total clerical costs  (Line  19  x Line 20)
6 wells
1 sample
6 samples
2 hrs.

12 hrs.

2 hrs.

$15
$210

6 analyses
6 analyses
$77
$108

$462

$648

$1110
8 hrs.

$30
$240

5  hrs.
$8
$40
                                    9-14

-------
WORKSHEET D (continued)

22.  Total administrative costs (Line 18 + Line 21)    $280
23.  Monitoring equipment maintenance                  $150
24.  Total monitoring costs                            $1750
     (Line 8 + Line 15 + Line 22 + Line 23)
                                 9-15

-------
                          SURFACE  IMPOUNDMENTS
                   (All wastes  remain  in impoundment)
                    WORKSHEET  E -  FENCE MAINTENANCE
1.   Length of fence  to be replaced                   186 feet
2.   Unit cost of replacing fence                     $13.06/linear ft.
3.   Total cost of replacing fence                    $2429
     (Line 1 x Line 2)
                                  9-16

-------
                           SURFACE IMPOUNDMENTS
                     (All wastes  remain  in  impoundment)
                 WORKSHEET F - PROFESSIONAL CERTIFICATION
 1.   Number of person-hours required  for  inspections           80  hrs.
 2.   Cost per person-hour                                      $75
 3.   Total costs of independent professional engineer          $6000
      certification  (Line 1 x Line  2)
 4.   Number of technical hours required for administrative     8 hrs.
      duties
 5.   Person-hour costs for technical  administrative            $30
      duties
 6.   Total administrative costs for technical labor            $240
      (Line 4 x Line 5)
 7.   Number of clerical hours required for administrative      5 hrs.
      duties
 8.   Person-hour costs for clerical administrative duties      S8
 9.   Total administrative costs for clerical labor             $40
      (Line 7 x Line 8)
                                  i
10.   Total administrative costs (Line 6 +• Line 9)
11.   Total certification costs (Line 3 + Line 10)
                                      9-17

-------
                           SURFACE  IMPOUNDMENTS
                    (All  wastes  remain  in  impoundment)
  WORKSHEET G - TOTAL  COSTS  INCLUDING  ADMINISTRATION AND CONTINGENCIES
 1.   Cost of removing  free  liquid and decontaminating       $ 16,687
      the surface and ancillary  facilities  (From Worksheet A)
 2.   Cost of final cap  (From Worksheet B)                   $ 67,114
 3.   Cost of planting  final vegetation (From Worksheet C)   $  2,950
 4.   Cost of ground-water monitoring (From Worksheet D)     $  1,750
 5.   Cost of fence maintenance  (From Worksheet E)           $  2,429
 6.   Cost of professional certification  (From Worksheet F)  $  6,280
 7.   Total of Line 1 through Line 6                         $ 97,210
 8.   Administration                                         $ 14,581.50
 9.   Contingencies                                          $ 14,581.50
10.   Total costs of closure (Line 7 + Line 8 + Line 9)      $126.373
                                   9-18

-------
                SAMPLE  CLOSURE  COST  ESTIMATING  WORKSHEETS:
      SURFACE  IMPOUNDMENTS  FROM WHICH WASTES ARE  REMOVED AT  CLOSURE

A.   Removing  All  Free Liquids and  Sludge
     It  is assumed in  che sample  case chac  free liquids  will be  removed
through  evaporation and  that sludge will be placed  in a  tank truck and
disposed off-site.  A  variety  of  other options are  available.  For  removing
free liquids,  both transporting to  an off-site TSDF and  treating and
discharging to  surface waters  are other options that could be  used.   For
removing sludge, solidification could take  place  at the  site,  and  the
solidified sludge  either disposed in an off-site  landfill or in  a  landfill
on-site, if there  was  one with interim status  or  a  permit on-site.
     1.  Method used:  As noted above, it is assumed in  this case  that
evaporation is  the method used to remove free  liquids.
     2.  Time  required to evaporate liquid:  Based  on calculations  that
would be shown  in  the  closure  plan, it is assumed for the sample case that
70 days  would be required to evaporate liquid.
     3.  Cost of routine operations per day:   This  factor includes  the
required weekly inspection  of  the surface impoundment  and a  minimum allot-
ment for necessary maintenance revealed by  such inspections.   This  is  esti-
mated to be S10 per day.
     4.  Cost of maintenance during evaporation (Line  2  x Line 3):  The
total cost of maintenance of the  surface impoundment  is  equal  to 70 times
$10 for a total of $700.
     5.  Estimated volume of sludge:  Given the size  of  the  surface impound-
ment and the assumption of  10 percent sludge,   1936  cu. yds.   of sludge  will
remain after evaporation of free  liquids.
     6.   Cost per cu.  yd. of removing sludge off-site:   It is assumed
 that off-site removal of sludges  can be  obtained  for 340 per cu. yd.   This
cost takes into account the fact  that the off-site TSDF  facility  will
have to mix and stabilize the sludges,  and assumes  that  they will, therefore,
charge a premium for this service.
     7.   Removal costs per cu.  yd.:   It  is assumed  for the sample facility
that removal costs are SI.60 per cu. yd.  (including equipment rental).
                                   9-19

-------
      8.   Hauling costs per cu.  yd.:  It is assumed that the nearest  land-
 fill  is  20  miles away.  Unit costs of trucking the sludge- from the  impound-
 ment  to  the landfill is assumed to be S3/cu.  yd.,  based on discussions
 with  trucking  industry personnel.
      9.   Total costs (per cu.  yd.) of disposal (Line  6  + Line  7  + Line  8):
 Total costs of off-site disposal are S44.60 per cu. yd.
    10.   Cost  of  removing sludge (Line  5  x Line 9):   Given  these  assumptions,
 the cost  of  removing sludge  is  386,346.
    11.   Total costs (Line 4 + Line 10):   Total costs for  removing free
 liquids and  sludges  is  $87,046.

 B.  Decontaminating  the Facility
      1.   Surface area of contaminated soil:   It is  assumed  that  19,360
 sq. yds.  (the  entire surface area  of the  surface impoundment)  has contami-
 nated soil.
      2.   Depth of removal:   It  is  assumed in  the sample  case that this  soil
 must  be  removed to a depth of  1 foot to ensure that no  soil contaminated
 vith  hazardous  waste remains in the surface  impoundment.
      3.   Total  volume to be  removed (Line 1  x Line  2):   The resulting total
 volume to be removed is 6453 cu. yds.
      4.   Cose  of  removal per cu. yd. :   The assumed  cost  of  removing soil is
 SI.60  per cu.  yd. (including costs of renting equipment).
      5.   Total  cost  of removal  (Line 3  x  Line 4):   The  resulting  costs  for
 the sample  case of removing  the contaminated  soil  are $10,325.
      6.   Cost  of  hauling to  off-site landfill per  cu. yd.:  The assumed
 hauling costs  to  an  off-site landfill for final disposal of the contaminated
 soil  are  $3  per cu.  yd.
      7.   Total  cost  of hauling  (Line 3  x  Line 6):   The  resulting  total
 costs  of  hauling  are $19,359.
      8.   Fee per  cu.  yd.  for disposal in  off-site  landfill:  It is assumed
 that  the  charge per  cu.  yd.  for off-site  disposal at  the chosen landfill
has been determined  to  be  $30 per  cu. yd.
      9.   Total  cost  of  disposal (Line 3 x Line 8):  The  total  costs for
 disposal, excluding  hauling  and soil removal,  are then  $193,590.
                                  9-20

-------
    10.  Decontaminating equipment:   It  is  assumed that  equipment can be
 decontaminated for  $500.
    11.  Decontaminating and  flushing pump  and liquid  lines:   Assume that
 this  can  be  done at the sample  facility for  $2000.
    12.  Disposing or treating residues from  decontamination:   It is
 assumed that residues  resulting from the  above  decontamination steps
 must  be disposed of at a cost of $1000.
    13.  Total costs  (sum of  Lines 5,  7, 9,  10, 11, and  12):  The total
 costs for decontaminating the surface  and ancillary  facilities
 are $226,744.

 C.  Ground-water Monitoring
    Assume that  closure of  the  surface impoundment will require a  total
 of 90 days.   In  order  to determine  the maximum  possible ground-water
 monitoring costs, the  most  extensive monitoring needed during  closure  is
 assumed.  Assuming  that ground-water quality analyses  are required  annually
 and ground-water contamination  analyses are required semi-annually,  the
 most expensive case is  that in  which both  sets  of analyses are required
 during  the 90-day closure period.
    1.  Number of veils monitored:   For the sample surface impoundment,  it
 is assumed that  six wells would need to be monitored.
    2.  Number of samples per well:  One sample  is taken per well for
 both analyses.
    3.  Total number of samples  (Line 1 x Line 2):  Given the above
 assumptions, six samples are required.
    4.  Number of hours required for collecting  the sample:  It  is assumed
 that experience  has shown that  two hours are sufficient to gather samples
 from each well.
    5.  Total number of hours required for collecting the samples: (Line 3
 x Line  4):  For  six samples, 12 hours would be required for collecting
 the samples.
    6. Number of hours required for preparing and delivering the samples:
 It is assumed for the example that experience has shown that this can
be done in two hours.
                                  9-21

-------
     5.  Person-hour  coses  for  technical administrative duties:  It is
 assumed that  the  total  fully loaded costs  for the owner's or operator's
 staff are S30 per hour.
     6.  Total administrative costs for technical labor (Line 4 x Line 5):
 Given the above assumptions, the  total administrative costs for technical
 labor are S240.
     7.  Number  of clerical hours  required  for administrative duties:  Assume
that five hours  of clerical time are required for the necessary typing and
certifications.
     8.  Person-hour  costs  for  clerical administrative duties:  Fully-loaded
costs of clerical  time are  assumed to  be  S8.
     9.  Total administrative costs for clerical  labor (Line 7 x Line 8):
Given the above  assumptions, total clerical costs are S40.
    10.  Total administrative costs (Line 6 •+• Line 9):  Summing technical
and clerical  labor,  the  total administrative costs are S280.
    11.  Total certification costs (Line  3  •+• Line 10):  The total costs  for
certification, including the engineer's fees and  administrative costs, is
then $4780.

£.   Total Costs  of  Closure Including  Ad-iniscration ar.c  Cor.tinser.c.es
     Items 1  through  4 summarize the costs  of the activities on each of
.the previous  worksheets.
     5.  Total of  Lines  1 through  4:   The total costs for the activities
listed in Lines  1  through 4 are 3320,350.
     6.  Administration:   The costs for administration, which includes
insurance, taxes,  and supervision  and  administration not  included elsewhere,
are assumed  to be  15  percent of Line 5.
     7.  Contingencies:   A provision for  contingencies of 15 percent of
Line 5 has been  included.
     8.  Total costs  of  closure (Line  5 + Line 6  + Line 7):  The total
costs of closure including administration and contingencies for the sample
surface  impoundment,  in the case where all  wastes are removed from the
impoundment,  are 5416,455.
                                   9-22

-------
     7. Person-hour coses  for collecting samples:  Assume  that  the fully-
loaded costs  for labor required  for collecting,  preparing and  delivering
the  samples averages  $15  per hour.
     8. Total  sample and collection  costs  ((Line  5 + Line  6)  x  Line 7):
This results  in total sampling and  collection costs of  S210.
     9. Number of ground-water quality analyses:  One analysis  must be
made for each well sample, for a  total of six.
   10. Number of ground-water contamination analyses:   One analysis must
be made for each well sample, for a total of six.
   11. Unit cost of ground-water  quality analyses:  It  is assumed
that the cost of an analysis for  the following parameters is $77  per
sample.
                       Chloride - $6.00 per sample
                       Iron - $12.00 per sample
                       Manganese  -  $12.00 per sample
                       Phenols -  $25.00 per sample
                       Sodium - $12.00 per sample
                       Sulfate -  $10.00 per sample
   12. Unit cost of ground-water  contamination analysis:  It is assumed
the cost of an analysis for the following parameters is $108 per
sample.
                       pH - $4.00 per sample
                       Specific Conductance - S4.00 per sample
                       Total Organic Carbon - $25 per sample
                       Total Organic Halogen - $75.00 per sample
   13. Total ground-water quality analysis costs (Line 9 x Line 11):
For six samples at $77 per analysis, this yields a total cost of  $462.
   14. Total ground-water contamination analysis costs  (Line 10 x
Line 12):   For six samples at $108 per analysis, this yields a total
cost of $648.
   15. Total analyses costs (Line 13 + Line 14):  The total analyses
costs, therefore,  are $1110.
   16. Number of technical hours for administration:   This includes
all time necessary to administer and report the data from the analysis
and is estimated as eight hours.
                                  9-23

-------
    17.   Person-hour cechnical coses:   The fully-loaded cost  required  for
 Chis work  is  assumed Co be 330 per hour.
    18.   Total technical costs for administration (Line 16  x  Line  17):
 Given  the  above  assumptions,  total costs  for administering the  tests  are
 assumed  to be S240.
    19.   Number of  clerical hours:   Assume for this  case that five hours
 of  clerical time are required to  produce  the necessary reports.
    20.   Person-hour clerical  costs:   Assume the  fully-loaded costs for
 clerical work are  S8 per hour.
    21.   Total clerical  costs  (Line 19 x Line 20):   Given the above
 assumptions,  the total  clerical costs are $40.
    22.   Total administrative  costs (Line  18 + Line  21):  The sum of
 technical  and clerical  costs  are  then $280.
    23.   Monitoring equipment  maintenance:   It is assumed that an average
 of  S150  is required  for a 90-day  period to  ensure adequate maintenance
 of  monitoring equipment and wells.
    24.   Total monitoring costs  (sum of Lines 8,  15, 22, and  23):  Total
 monitoring costs,  excluding administration  and contingencies, are then
 S1750.

 D.  Professional Certification
    1.   Number of  person-hours  required for  inspections:   It  is assumed
 that 60  hours  are  required for  periodic inspections of all aspects of
 closing  the surface  impoundment.
    2.   Cost  per person-hour:   In  this case,  assume that a registered
 independent professional engineer  may be  hired at a cost of  $75 per
hour.
    3.   Total  costs  of  independent  professional engineer's time (Line
 1 x Line 2) :  This yields  a total  cost of $4500 for the independent
 professional  engineer.
    4.  Number of  technical hours  required  for administrative duties:
Assume that eight  hours-are-required  from the owner's or operator's staff
 for administrative duties  connected with  employing an independent
 professional  engineer.
                                  9-24

-------
                           SURFACE IMPOUNDMENTS
                    (All wastes removed from impoundment)
             WORKSHEET A - REMOVING ALL FREE LIQUIDS AND SLUDGE
 1.   Method used                                              Evaporation
 2.   Time required to evaporate liquid                        70 days
 3.   Cost of routine operations per day                       $10
 4.   Cost of maintenance during evaporation                   S700
      (Line 2 x Line 3)
 5.   Estimated volume of sludge                               1936 cu< yds.
 6.   Cost of  removing sludge off-site per cu.  yd.             540
 7.   Removal costs per cu. yd.                                $1.60
 8.   Hauling costs per cu. yd.                                $3.00
 9.   Total costs per cu. yd. of disposal                      $44.60
      (Line 6 + Line 7 + Line 8)
10.   Costs of removing sludge (Line 5 x Line 9)               586,346
11.   Total costs (Line 4 + Line 10)                            $87.046
                                    9-25

-------
                          SURFACE IMPOUNDMENTS
                  (All  wastes  removed from impoundment)
   WORKSHEET B -  DECONTAMINATING SURFACE AND ANCILLARY  FACILITIES
 1.   Surface area of  contaminated  soil
 2.   Depth of removal
 3.   Total volume to  be  removed  (Line 1  x Line 2)
 4.   Cost of removal  per cu. yd.
 5.   Total cost of removal  (Line 3 x Line 4)
 6.   Cost of hauling  to  off-site landfill per cu. yd.
 7.   Total cost of hauling  (Line 3 x Line 6)
 8.   Fee per cu. yd.  for disposing in off-site landfill
 9.   Total cost of disposal  (Line  3 x Line 8)
10.   Decontaminating  equipment
11.   Decontaminating  and flushing  pump and liquid lines
12.   Disposing of residues from decontamination
13.   Total costs (sum of Lines 5,  7, 9,  10, 11, and
      12)
19,360 sq. yds,
1 ft.
6453 cu. yds.
$1.60
$10,325
$3
$19,359
$30
$193,590
$500
$2000
$1000
$226,774
                                   9-26

-------
                           SURFACE IMPOUNDMENTS
                   (All wastes removed from impoundment)
                   WORKSHEET C - GROUND-WATER MONITORING
  1.    Number  of  wells  monitored                          6  wells
  2.    Number  of  samples  per well                          1  sample
  3.    Total number  of  samples  (Line  1  x Line 2)           6  samples
  4.    Number  of  hours  required for collecting the        2  hrs.
       sample  (per sample)
  5.    Total number  of  hours required to collect           12 hrs.
       the samples (Line  3  x Line 4)
  6.    Number  of  hours  required for preparing and          2  hrs.
       delivering samples
  7.    Person-hour costs  for collecting  samples            $15
  8.    Total sampling and collection  costs  ((Line          $210
       5 + Line 6) x Line 7)
  9.    Number  of  ground-water quality analyses             6  analyses
10.    Number  of  ground-water contamination analyses       6  analyses
11.    Unit cost  of  ground-water quality analysis          $77
12.    Unit cost  of  ground-water contamination analysis    $108
13.    Total ground-water quality analysis costs           $462
       (Line 9 x  Line 11)
14.    Total ground-water contamination analysis costs     $648
       (Line 10 x Line  12)
15.   Total analyses costs  (Line 13 + Line 14)            $1110
16.   Number of  technical hours for administration       8 hrs.
       (e.g.,  reporting data to EPA)
17.   Person-hour technical costs                        $30
18.   Total technical costs for administration           $240
       (Line 16 x Line 17)
19.   Number of clerical hours                           5 hours
20.   Person-hour clerical costs                         $8
21.   Total clerical costs  (Line 19  x Line 20)           $40
22.   Total administrative costs (Line 18 + Line 21)      $280
                                   9-27

-------
23.   Monitoring equipment maintenance
24.   Total monitoring costs
      (Line 8 +• Line 15 + Line 22 + Line 23)
                                   9-28

-------
                           SURFACE IMPOUNDMENTS
                    (All wastes removed  from impoundment)
                 WORKSHEET D - PROFZSSIGNAL CERTIFICATION
 1.   Number of person-hours required for inspections
 2.   Cost per person-hour
 3.   Total costs of independent professional engineer
      certification (Line 1 x Line 2)
 4.   Number of technical hours required for administrative
      duties
 5.   Person-hour costs for technical administrative duties
 6.   Total administrative costs for technical labor
      (Line 4 x Line 5)
 7.   Number of clerical hours required for administrative
      duties
 8.   Person-hour costs for clerical administrative duties
 9.   Total administrative costs for clerical labor
      (Line 7 x Line 8)
10.   Total administrative costs (Line 6 -t- Line 9)
11.   Total certification costs (Line 3 + Line 10)
60 hrs.
$75
$4500

8 hrs.

$30
$240

5 hrs.

38
$40
                                     9-29

-------
                           SURFACE IMPOUNDMENTS
                   (All wastes removed from impoundment)
             WORKSHEET E - TOTAL COSTS OF CLOSURE  INCLUDING
                      ADMINISTRATION  AND CONTINGENCIES
1.   Cost of removing free liquids  and  sludge            $ 87,046
     (From Worksheet  A)
2.   Cost of decontaminating facility (From             $226,774
     Worksheet B)
3.   Cost of ground-water  monitoring (From  Worksheet C)  $  1,750
4.   Cost of professional  certification (From            $  4,780
     Worksheet D)
5.   Total of Line 1  through Line 4                      $320,350
6.   Administration                                      5 48,052.50
7.   Contingencies                                       $ 48,052.50
8.   Total costs of closure  (Line 5 +• Line  6 + Line 7)   $416.455
                                   9-30

-------
 9-3                EXAMPLE - LAND TREATMENT FACILITIES

      The following cost  estimates were developed for a land treatment
 facility consisting of 50  acres  of active fields for the processing of
 biodegradable  hazardous  waste.   In addition to the disposal fields, the
 land  treatment facility  is equipped with  a surface impoundment for waste
 storage  and  a  separate surface impoundment for collecting run-off water.
      The land  treatment  facility is designed to receive organic industrial
 sludge of high liquids content.   This  waste is applied to the  land treat-
 ment  fields  at an  application rate of  100 wet tons/acre (solids applica-
 tion  rate ~5 tons/'acre) .
      Waste received  by the facility is stored in a lined surface impound-
 ment.  The surface  impoundment is  5 feet  deep (3 feet  of waste and 2  feet
 of  freeboard)  and  has a  surface  area of 1.23 acres.  This corresponds  to
 a waste  holding capacity of  160,700 cubic feet.   A pump system is  avail-
 able  for transferring this  liquid  waste to  the tank trucks.
      The waste  from  the waste storage  surface impoundment  is spread on
 the fields using tank trucks.  During  the  first  90  days  of  the  planned
 closure  period, all  of the waste inventory will  be  disposed on  the fields.
 This disposal will require one application  to  the  field.  Later in the
 closure  period, run-off water from  the  separate  run-off water surface
 impoundment will be disposed of in  the  same  manner.  This run-off  water
will have a very low concentration  of hazardous vastes.  Disking of the
 fields will be conducted  shortly after  each  spreading  to mix the waste
with  the  soil and a second disking will be done  two to  three weeks after
each spreading.  Periodic disking will  continue on a bimonthly basis
 thereafter.
     During this prolonged closure period, the surface impoundments will
be closed as well.   Each  of the two surface impoundments has its own
closure plan as shown elsewhere in this guidance document.  Therefore,
the costs of decommissioning the  surface impoundments are not computed
in this example.
                                   9-31

-------
               SAMPLES  CLOSURE COST ESTIMATING WORKSHEETS:
                        LAND TREATMENT FACILITIES
A.   Disposing of  Waste Inventory
     1.   Maximum  inventory to  be disposed:   For  this  case,  the waste
storage surface  impoundment is  filled  to  its  maximum capacity  of 5000
tons of low solids waste (or 1,198,878 gallons with  a  waste  density
similar to water).
     2.   Amount of  run-off water to be disposed:  a similar
amount of somewhat contaminated water  is  expected  to be  disposed of
from the surface water  run-off  impoundment.   This  mildly contaminated
water is to be disposed of  in the same manner as  the inventory.
     3.   Total  material to be  disposed (Line 1 +  Line 2):   All of these
impounded liquids  (waste and run-off)  are to  be disposed of  on-site by
spreading on  the land treatment facility  fields.
     4.   Application rate:   The waste is to  be applied  to the field by
aeans of tank trucks equipped with spray  bars.  The  application rate of
100 tons/acre corresponds to a  solids  application  rate of 5  tons/acre.
This application rate has been  found to be acceptable  based  on tne
operating experience of the facility.
     5.   Acreage  utilized:   All 50 acres of  the land  treatment facility
are in active operation and will be available for  the  disposal of the
waste inventory  and run-off.  This is  the lowest cost  option for disposing
inventory available to  this  facility.
     6.  -Number of applications in  the closure period:  Two applications
are planned.  One  application is the liquid waste  inventory  which will
be completed within the first 90 days  of  the  closure period  as required
by the interim status regulations.  Subsequently,  an application of the
captured run-off water  is planned.
     7.   Unit cost of  spreading:  The unit cost of  spreading  the
liquids on the land treatment fields is $0.48 per  ton  or S48 per acre
at the application rate of  100  tons per acre.
     8.   Total  cost of spreading  (Line 5 :: Line 6 x Line 7):  The total
cost of spreading  the waste  inventory  and  the captured run-off water is
the product of the acreage  treated, the number of  applications and the
unit per acre cost of spreading.
                                   9-32

-------
     9.   Number of diskings required:  A total of ten diskings will be
required throughout the closure period.  Four of the diskings will be
carried out in the first part of the closure period (immediately after
each of the two applications and several weeks after each application).
Six additional diskings will be conducted throughout the rest of the
closure period.
    10.   Unit cost of disking:  The unit cost for disking the land treat-
ment fields is the sum of tractor and implement costs and equipment
operator labor costs.  The equipment cost for disking is $.79 per acre.
The cost is for both the tractor and the tandem disk.  It includes
insurance, taxes, repairs, fuel and lubrication but it does not include
interest and depreciation.  The labor cost (fully-loaded) is $20 per
hour.   The disking is accomplished at the rate of .167 hours per acre.
                                                               *
In addition, excra labor time is required for related handling and care
of the equipment.  Thus, the actual labor time per acre is 1.2 times the
inclement time, yielding a labor rate of $4.01 per acre.
    11.   Total cost of disking (Line 5 x Line 9 x Line 10):  The cost of
disking the land treatment fields is the product of the acreage utilized,
the number of diskings required during closure and the unit cost of
disking.
    12.   Total costs for disposing of inventory (Line 8 + Line 11):
The total cost for disposing of the waste inventory and run-off water  is
the sum of the total spr&ading costs and the total disking costs.  After
completing the land treatment, the hazardous waste will be completely
decomposed.

B.   Decontaminating the Land Treatment Facility
     1.   Area of facility contaminated:  It should be noted that the
1200 sq. yds. of contaminated soil does not include any of the land
treatment fields where controlled decomposition is occurring.
     2.   Depth of material removed:  The contaminated soil is removed
to a depth of 1 foot (.33 yds.).  The soil at this land treatment facility
is relatively impermeable.  This makes a depth of 1 foot realistic for
tne excavation for the contaminated soil (since the mobility of the
hazardous waste is restricted).  The soil density is 90 Ibs./cu.  ft.
                                  9-"

-------
      3.    Unit  cost  for removal:  The contaminated soil is removed  and
 loaded  into  spreaders  using rented earth-moving equipment.  This  excava-
 tion  and  loading  operation is estimated to cost $1.60 per cu.  yd. of
 contaminated soil.
      4.    Cost  of removing contaminated soil (Line 1  x Line 2  x Line  3):
 The cost  of  excavating,  removing and loading the contaminated  soil  is
 the product  of  the volume of the soil handled and the unit cost of  the
 operation.
      5.    Quantity disposed on-site:  All of the contaminated  soil  is to
 be disposed  on  the land  treatment fields (on-site).   The  contamination
 in the disposed soil will decompose under supervised  conditions.  This
 contaminated soil will be spread after the waste inventory has been dis-
 posed.  The contaminated soil will be spread on the fields at  least
 several weeks after the  last of  the waste inventory is  spread.
      6.    Quantity disposed off-site:   No contaminated  soil is to be
 disposed off-site due to the much higher cost of off-site  disposal and
 the availability  of the  land treatment fields.
      7.    Application rate:   An  application rate of 10  tons  of contami-
 nated soil per acre is used.   This solids application  rate is acceptable
because the waste concentration  in the soil is  quite  low.
      8.   Acreage utilized:   The contaminated soil is  spread on the
 entire 50 acres of the land  treatment  facility.
      9.   Number  of applications:   Only one application is  required to
dispose of the entire volume  of  contaminated soil.
    10.   Unit cost of spreading:   The unit cost  for  the spreading of
 the contaminated  soil is  the  sum of tractor and  implement  costs and
equipment operator labor costs.   The equipment  cost for1spreading the
waste is S.95 per acre.   This  cost is  for both  the tractor and the spreader.
 It includes insurance, taxes,  repairs,  fuel and  lubrication  but it  does
not include interest and  depreciation.   The labor cost  (fully-loaded)  is
S20 per hour.  The spreading  of  the waste is  accomplished  at the rate  of
 .211 hours per acre.   In  addition,  extra  labor  time is required for re-
lated handling and care  of  the equipment.   Thus,  the actual labor time
per acre is 1.2 times the  implement time,  yielding a labor rate of $5.06
oer acre.
                                  9-34

-------
      11.   Total  cose of spreading (Line 8 x Line 9 x Line 10):   The cost
 of  spreading  che soil is the product of the acreage and the unit cost
 per acre.
      12.   Number of  diskings:   The  spread soil is disked to mix it with
 the soil of the  land treatment  fields.   This one disking is conducted
 shortly after  the contaminated  soil is  spread on the fields.
      13.   Unit cost  of disking:   The unit cost for disking  is $4.08/acre.
 This  cost  includes equipment costs  of $.79  per acre for the tractor and
 the tandem disk.   This cost  includes insurance,  taxes,  repairs,  fuel and
 lubrication; but it  does not include interest and depreciation.   Labor
 cost  is included at  a cost of $20 per hour.
      14.   Total  cost of disking  (Line 8 x Line 12 x Line 13):   The total
 cost  for this disking is the product of the  acres disked and the  unit
 cost  per acre.
      15.   Total  cost of disposing of contaminated soil  (Line 4 +  Line
 11  +  Line  14):   The  total cost of disposing  of the  contaminated soil  is
 the sura of the cost  of removing  the  soil, spreading the  soil, and  disking
 the spread soil.
      16.   Cost of  decontaminating equipment:   At  the end  of the closure
 period, the equipment  used on-site will be decontaminated by washing
with  detergents.   The  run-off cleaning water  will be collected for dis-
posal.  A  cost of  S1000 is estimated  for  this  task.
      17.  Disposing  or treating of residues  from  equipment decontamina-
tion:   The  wastewater  from the washing and other cleaning residues will
be disposed off-site at  a cost of approximately $1000.  Off-site disposal
of  this residue  is required because  the land  treatment facility is
ceasing operation.
      18.  Total  cost of  decontaminating the  facility  Line 15 + Line 16 +
Line  17):   The total cost of decontaminating  the  land treatment  facility
is  the sum of the  costs  of soil disposal, equipment decontamination,
and decontamination  residue disoosal.
                                  9-35

-------
C.   Monitoring Activities  (Ground-Water and  Soil)
Ground-Water Monitoring
     It is assumed  that  closure  of  the  land  treatment  facility will re-
quire a total of  15 months.   In  order  to determine  the maximum possible
ground-water monitoring  costs, the  most extensive monitoring needed
during closure is assumed.- Assuming that ground-water quality analyses
are required annually and  ground-water  contamination analyses are required
semi-annually, the most  expensive case  is that in which two ground-water
quality analyses and three  ground-water contamination analyses are required
during the 15-month closure period.
     1.   Number of wells monitored:  Eight sampling wells are operated
to monitor the composition of the ground-water at the land treatment
site.  Seven of the wells are downgradient from the land treatment fields
and one well is upgradient.
     2.   Number of samples taken:  Three "cycles" of ground-water samp-
ling will be conducted during the 15-month long closure period.  Two
ground-water quality analyses and three ground-water contamination
analyses are to be carried out.  One sample may be used for both the
ground-water quality and the ground-water contamination analysis.  There-
fore, during the closure period, a  total of three samples are taken
from each well.
     3.   Total number of samples (Line 1 x Line 2):  The total number
of ground-water samples  taken during the closure period is the product
of the number of monitoring wells and the number of samples taken from
each well.
     4.   Number of hours  for collecting the  sample (per sample):  Taking
ground-water samples is  a rather time-consuming practice.   The well is
pumped dry and allowed to refill.   Then a sample is taken.  The land
treatment facility experience is that approximately two hours are re-
quired for each ground-water sample (including some time for moving about
the fields).
     5.   Total number of hours  for collecting the samples (Line 3 x
Line 4):  During the extent of the  closure period, 24 samples will have
to be collected, requiring 48 hours of  labor.
                                  9-36

-------
     6.   Number of hours for preparing and delivering  che sample:   The
ground-water samples must also be prepared and delivered to  the  labora-
tory for analysis.  This work requires about three hours for a set  of
eight samples  (one from each monitoring well).
     7.   Total number of hours for preparing and delivering the sample
(Line 2 x Line 6):  The to'tal number of ground-water sample preparation
and delivery hours in the closure period is the product of the number
of sets of samples (cycles) and the unit operation requirement of three
hours labor.
     8.   Person-hour costs for collecting and handling samples:  The
person-hour fully-loaded labor rate for taking and handling the ground-
water sample is $15 per hour.  This is the same labor rate as during
the operating period of the land treatment facility.
     9.   Total ground-water sampling and collection costs ((Line 5 +
Line 7) x Line 8):  The total cost of ground-water sampling is computed
by multiplying the hours required by the labor rate of $15 per hour.
    10.   Number of ground-water quality analyses:  Sixteen ground-water
quality analyses are required during the closure period.  Two analyses
are required for each well.
    11.    Number of ground-water contamination analyses:  Twenty-four
ground-water contamination analyses are required during the closure
period.   Three analyses are required for each well.
    12.    Unit cost of ground-water quality analysis.  It is assumed
that the cost of an analysis for the following parameters is S77 per
analysis.
          Chloride                 $ 6/sample
          Iron                     $12/sample
          Manganese                $12/sample
          Phenols                  $25/sample
          Sodium                   $12/sample
          Sulfate                  $10/sample
    13.    Unit cost of ground-water contamination analysis:  It is
assumed chat the cost of an analysis for the following parameters is
$108 per analysis:
                                  9-37

-------
           pH                       S 4/sample
           Specific Conductance     S 4/sample
           Total Organic Carbon     $25/sample
           Total Organic Halogen    $75/sample
      14-16.   Total ground-water chemical analyses costs:   The  unit  costs
per analysis are multiplied by the number of analyses  to  yield the  costs
for each  type of analysis.   These two costs are added  together to compute
the total  analyses costs.

Soil  Monitoring
      17.   Number of soil core  samples:  Soil core samples  are  taken
throughout the closure  period.   Four samples are taken in  each quarter
of the first year.   In  the  fifth quarter of the closure period, 50
core  Samples are taken  (one from each acre of the land treatment facility).
This  last  set of 50 samples confirms that the waste has decomposed  during
the closure  period.   Thus,  a total of 66 soil core samples are taken in
the closure  period  (15  months  in duration).   Most of these samples  are
taken below  the  zone  of waste  incorporation to monitor any waste movement
:3':ards the  vater taole.  A few of the samples are taken from  the zone
of incorporation as well to monitor the decomposition  of the waste  material.
      18.   Labor  hours required  for each core sample:   The  taking of a
soil core  sample is a relatively simple process.   Most of  the  time  allo-
cated to taking  each  sample is  movement between the sample-taking locations.
     19.   Labor  unit  cost for  collecting core samples:  The unit cost of
the labor  for  soil  core sampling is  S15 per  hour fully-loaded.
     20.   Total  cost  of collecting the soil  samples (Line  17 x Line 18 x
Line 19) :  The  total  cost for  taking soil core samples  is  the  product of
the number of  samples taken, the hours  required for each sample, and the
labor rate.
     21.   Unit soil core sample  analysis  cost:   The chemical analysis of
each soil  sample  involves the measurement of  10  parameters (organic matter,
total dissolved  solids,  total nitrogen,  cadmium,  arsenic, lead, mercury,
chromium,  zinc,  and copper).  Preparing each  sample costs $10  and each
parameter  costs  S5.   Thus,  the  net cost per  soil sample is S60.
                                  9-38

-------
     22. Total soil core sample chemical analysis cost  (Line  17 x Line 21):
The total chemical analysis cost for the soil core samples  is  the product
of the number of samples taken and the unit.analysis cost per  sample.

Lysimeter Sampling of Soil Moisture
     23. Number of lysimeter samples:  Soil moisture samples are taken by
means of a lysimeter.  This extracted water is then analyzed for contami-
nation in the same way that the ground-water sanples are chemically analyzed.
Four soil moisture samples are taken during each quarter of the closure
period.  Since there are 5 quarters, a total of 20 samples are taken.
     24. Labor hours required for each lysimeter collection of soil
moisture:  One hour of labor is required for collecting and handling each
sample.  This includes time spent moving about the field.
     25. Labor unit cost for collecting samples:  The unit: labor cost for
collecting these samples is S15 per hour fully-loaded.
     26. Total sampling cost for lysimeter collection of soil moisture
(Line 23 x Line 24 x Line 25) :  The total cost for collecting soil moisture
                                                          0
samples is the product of the number of samples taken,  the labor required
for each sample, and the labor rate.
     27. Unit cost for moisture sample analysis:  The unit cost for each
chemical analysis is S150.  This is based on the land treatment facility's
experience with ground-water contamination analysis and soil moisture
chemical analysis.
     28. Total cost for moisture sample chemical analysis (Line 23 x
Line 27):  The total cost for the soil moisture chemical analysis is
the product of the number of samples taken and the cost of chemically
analyzing each sample.

Administrative Costs
     29. Number of technical hours for administration:  The land treat-
ment facility also requires the allocation of some technical supervisory
labor to administer the closure monitoring program.   Approximately two
days of such supervisory labor will be required in small blocks of time
expended throughout the closure period.
                                  9-39

-------
     30. Person-hour  technical coses:   The fully-loaded  labor cose for
chese technically qualified employees  is  $30 per  hour.
     31. Total technical  costs for administration (Line  29 x Line 30):
The cost of this technical  administration is the  product of the required
technical administration  hours and the technical  labor rate.
     32. Number of clerical hours:  Clerical support  is  required for the
monitoring administration activity.  Two  days of  clerical labor will be
needed in small blocks  of time expended throughout  the closure period.
     33. Person-hour  clerical  cost:  The  fully-loaded labor rate for
clerical labor at the land  treatment facility is  $8 per hour.
     34. Total clerical costs  (Line  32 x  Line 33):  The  total clerical
costs for administering the monitoring activity is  the product of the
hours required and the  clerical labor  rate.
     35. Total administrative  costs  (Line 31 + Line 34):  The technical
and clerical administrative costs  are  added  together  to yield the total
administrative costs  for  the monitoring program (both soil and ground-
water) for the entire closure  period.

Maintenance Costs
     36. Monitoring well maintenance:  The  cost of maintaining the ground-
-.vater monitoring wells is estimated  to be S750 for the entire closure
period.  No well replacements are anticipated during the closure period.

Cost Summaries for Monitoring
     37. Total cost of ground-water monitoring (Line 9 + Line 16 T Line
36) :  The total cost for ground-water monitoring is the sum of the costs
of sample collection, chemical analyses, and monitoring well maintenance.
     38. Total cost of soil core sample monitoring (Line 20 •+• Line 22):
The total cost of soil core sample monitoring is the sum of the costs
of collecting the samples and chemically analyzing the samples.
     39. Total cost for soil moisture (lysimeter) monitoring (Line 26 +
Line 28):  The total cost for soil moisture monitoring by means of lysimeter
samples is the sum of the costs of collecting che samples and chemically
analyzing the samples.
                                   9-40

-------
      40.   Total  administrative  coses  (Line  35):   The total administrative
 costs,  both  clerical  and  technical,  for  the monitoring program are repeated
 here.
      41.   Total  monitoring costs  (Line 37 + Line 38 + Line 39 + Line 40):
 The total  cost for  the  entire closure period monitoring program is the
 sum of  the costs of ground-water  monitoring,  soil core testing,  lysimeter
 testing, and  the administrative costs.   All of  these costs are reliably
 known from the operating  experience of the  facility.

 D.   Fence Maintenance
     For a land  treatment facility consisting of 50 acres  of  active fields,
 assuming that the site  is square, each side is 1475.8 feet.   The perimeter
 of the  site  is then 5903.2 feet.
     1.    Length of fence to be replaced:   Since the land  treatment facil-
ity has  a prolonged  closure period and possible post-closure activities,
 it is necessary  to  maintain the security fence along the field perimeters
 in good condition.  We  have estimated that  10% of  the fencing will be
 corroded and damaged  to the point of requiring replacement.
     2.    Unit cost of  replacing  fence:  The  security fence is a galvanized
 metal 6-foot high chain link fence made of  #9 wire.   The installed unit
 cost of replacement sections is $13.06 per  linear  foot.
     3.    Total  cost  of replacing fence  (Line 1  x  Line  2):  The  cost of
 replacing  the damaged fence sections is the product  of  the length  of the
 fence needing replacement  and the unit cost of replacement, for  a  total
 of S7705.

 E.   Repair of Drainage Channels
     1.    Length of drainage channels:  The land treatment facility's
drainage channels are an  important part of  the containment system.  They
channel run-off water to a surface impoundment.   Our estimate is that
500 feet of these channels will have to be replaced during the closure
period.
     2.    Channel volume per unit length:  The channels have a square
cross  sectional area measuring 3 feet by  3 feet.   This results in a
volume of 0.33 cu. yds.  per linear foot of channel length.

                                   9-41

-------
     3.   Channel excavation unit cost:   The unit  cost of excavating  the
channels with a backhoe  is  $.67 per cu.  yd.   This  work would be performed
by a contractor and  is based on contractor estimates.
     4.   Total channel  excavation cost  (Line 1 x  Line 2 x Line 3):  This
total cost is the product of the length  of the drainage channels required,
the volume per unit  length,  and the unit excavation cost.
     5.   Unit cost  of hand  grading:   The inner surface of the channels
must be shaped and prepared  for seeding.   This work is performed by hand
at a unit cost of $.02 per sq.  ft.   This work will be performed by a
contractor and is based  on contractor  estimates.
     6.   Channel surface area:   The  inside  surface of the new channel
is approximately 4500 sq. ft.  in area.   All  of this area must be shaped
and prepared.
     7.   Total cost of  hand grading  (Line 5 x Line 6):  The total cost
of this hand grading is  the  product of the unit cost and the surface
area of the channels.
     8.   Total replanting cost:   The  total  cost of seeding, fertilizing
and mulching the channel surface is estimated at $50 by a contractor.
     9.   Total channel  repair  cost (Line 4  + Line 7 +• Line 8):  The
total cost of cnannel repair is  the sum  of the e::cavacion cost, hand grac-
ing cost and replanting  cost.

^•    Management Inspection of  Land  Treatment Facility Operations
     1.  Number of technical management  person-hours required for each
inspection :  The prolonged closure  period for the  land treatment facility
and the recurring operations of  spreading and disking necessitate an
inspection program conducted by facility management throughout the closure
period.  Each one of these inspections requires 8 hours of technical manage-
ment time.
     2.  Inspection  frequency:   The inspections are conducted once per
month throughout the closure period.  On each inspection, the manager
checks the progress  of the facility operations: spreading,  disking,
sampling, decontamination, etc.
     3.  Duration of closure period:  To allow the hazardous waste to
decompose, the closure period-must  be  15  months in duration.

                                  9-42

-------
      4.    Total technical management person-hours required for inspections
 (Line 1  x  Line  2 x Line 3):   The technical hours required for the actual
 inspections  are the product  of the number of hours for each inspection
 and  the  total number of inspections required.
      5.  Person-hour costs for technical management duties:  The person-
 hour  cost  for this technical supervisory labor  is $30 per hour (fully-
 loaded labor rate).
      6.  Total  technical management costs for inspections (Line  4 x Line
 5) :   The technical cost for.  the  inspections  conducted throughout the
 closure  period  is  the product  of the total inspection technical  hours
 and the  technical  labor rate.
      7.  Additional  technical  management labor  required:   A small amount
 of additional technical time will  be required for managerial tasks
 associated with the  inspections  (such as writing reports).   Approximately
 8 percent  to 10 percent of the inspection time  is required for this
 additional work.
      8.  Total  cost  of  additional  technical  management  labor (Line 5 x
 Line  7):  The cost of  this additional technical  labor is  the product of
 the additional  hours  required  and  the tecnnical  labor rate.
      9.  Total  cost  of  technical nanagenent  labor (Line 6  + Line  8):
 The total cost  of  all  the  technical  labor  required  is  the  sum of  the
 labor directly  spent on inspections  and  the  labor related  to  inspections.
    10.  Mumber  of clerical hours  required:  Clerical  labor  is needed  to
 support  the periodic inspections of  the  land treatment  facility.    Only
 a modest amount  of clerical labor  is required.
    11.  Person-hour costs for clerical  labor:  The labor  rate for
 clerical labor  at  this  facility  is  $8 per hour.    (This is a  fully-loaded
 labor rate.)
    12.  Total  cost  for clerical labor (Line 10  x Line  11):   The  total
 cost for the needed clerical labor is the product of  the clerical hours
and the clerical labor  rate.
    13.  Total  inspection  cost (Line 9 + Line 12):  The total cost of the
 inspection  program is the  sum of the technical labor  costs and the cleri-
cal labor costs.
                                   9-43

-------
G.    Professional Certification
      1.   Number of person-hours required for inspections:   Approximately
one week of  professional time will be required to certify  the proper
closure  of  the land treatment facility.  Most of this  professional work
will  be  an  independent professional engineer as specified  by the  interim
status regulations.   The professional engineer will be assisted by a soil
specialist who will evaluate the soil samples taken during the closure
period.
      2.   Cost  per person-hour:   The contracted cost of these professionals
is $75 per hour based on their  current quotes for these services.
      3.   Total costs of professional engineer's time (Line 1 x Line 2):
The total cost for these contracted professional services  is the  product
of the number  of hours required and the quoted hourly  rate.
      4.   Number of technical hours  required for administrative duties:
The land  treatment facility technical staff will need  to devote 8  hours
of time  to administering this certification.
      5.   Person-hour costs  for  technical administrative duties:  The
fully-loaded labor rate for the technical staff is  S30/hour.
      6.   Total administrative costs for technical labor (Line  4 x  Line 5):
The technical  administrative costs  for the  land treatment  facility is the
product of the number of technical  hours required and  the  technical labor
rate.
      7.   Number of clerical hours required  for  administrative  duties:
Eight hours of  clerical work are required to  support the administration
of the certification.
     8.   Person-hour costs  for  clerical administrative  duties:  The
fully-loaded labor rate for clerical  workers .at  this facility  is $8/hour.
     9.   Total administrative costs  for clerical  labor  (Line 7 x Line 8):
The total clerical labor costs  are  the product  of  the  labor  rate and
the number of  hours  required.
    10.   Total  administrative costs  (Line 6 + Line 9):  The  total adminis-
trative costs  are  the  sum of  the technical  labor  cost and  the clerical
labor cost.
    11.   Total  certification  costs  (Line  3 +  Line LO):  The  total cost
for certification  is  the  sum  of  the costs of  the  professional engineer
                                   9-44

-------
and  che  administrative  costs.

 H-   Total Costs Plus Administration  and  Contingencies
      Items 1  through  7  give  the  costs  of  each major  closure  function on
each  of  the preceding worksheets.  Line 8 is the  total  of Lines  1  through
7, $39,389.
      7.  Administration:  All additional  administration  costs are  com-
puted by multiplying the subtotal  (Line 8) by 15  percent.
     8.  Contingencies:  Allowance for contingencies is  computed by
multiplying che subtotal (Line 8) by 15 percent.
     9.  Total costs of closure  (Line 8 + Line 9  + Line  10):  A grand
total for land treatment facility closure costs is computed by adding
together the costs from the worksheets and the allowances for additional
administration and other contingencies.
                                  9-45

-------
                        LAND  TREATMENT FACILITIES
                WORKSHEET A - DISPOSING OF WASTE INVENTORY

 Method of Disposal:  Spreading on  the Land Treatment Fields
 1.   Maximum inventory  to be disposed

 2.   Run-off water to be disposed
 3.   Total material to  be disposed  (Line 1 + Line 2)
 4.   Application rate (wet weight)
 5.   Acreage utilized
 6.   Number of applications in the  closure period
 7.   Unit cost of spreading
 8.   Total cost of spreading (Line  5 x Line 6 x Line 7)
 9.   Nuzrber of diskings required during the
      closure period (excluding one  disking for
      decontamination)
10.   Unit cost of disking (equipment cost and labor)
11.   Total cost of disking (Line 5  x Line 9 x Line 10)
12.    Total cost for disposing of inventory and
      run-off water (Line 8 + Line 11)
5000 tons of
liquid waste
5000 tons
10,000 tons
100 tons/acre
50 acres
2
$48/acre
$4800
10
$4.80/acre
$2400
$7200
                                    9-46

-------
                        LAND TREATMENT  FACILITIES
                WORKSHEET B -  DECONTAMINATING THE FACILITY
  1.    Area  of  facility contaminated
  2.    Depth of material removed
  3.    Unit  cost  for  removal  (including machinery  rental)
  4.    Cost  of  removing the contaminated  soil
       (Line 1  x  Line 2 x Line  3)
  5.    Quantity of contaminated soil disposed on-site by
       landspreading
  6.    Quantity of contaminated soil disposed off-site
  7.    Application rate
  8.    Acreage utilized
  9.    Number of  applications
10.    Unit cost  of spreading (equipment  cost and  labor)
11.    Total cost for  spreading the contaminated soil
       on the land treatment fields (Line 8 x Line 9
       :•: Line 10)
12.    Nunmer of diskings carried out to  assist
       in disposing of contaminated soil
13.    Unit cost of disking (equipment cost and labor)
14.   Total cost for disking the spread soil into the
       land treatment soil (Line 8 x Line 12 x Line 13)
15.   Total cost of disposing of the contaminated soil
       (Line 4 + Line 11 + Line 14)
16.   Cost of decontaminating equipment
17.   Disposing of residues from equipment decon-
      tamination
18.   Total cost of decontaminating the facility
       (Line 15  + Line 16 -I- Line 17)
  1200  sq.  yds.
 .33  yds.  (1 ft.)
 $1.60/cu.  yd.
 $633.60

 396  cu. yds.
 (481 tons)
 0
 10 tons/acre
 50 acres
 1
 $6/acre
 $300
$4.80/acre.
$240

31173.60

$1000
$1000

$3173.60
                                   9-47

-------
                         LAND TREATMENT FACILITIES
                    WORKSHEET C - MONITORING ACTIVITIES
                    (GRQUHD-WATER AND SOIL MONITORING)
 Ground-r7acer Monitoring
 8
 9

10
11
12
13
14

15

16
     Number of wells monitored
     Number of samples  taken  at  each well  (1  per  cycle)
     Total number of samples  (Line  1 x Line 2)
     Number of hours for  collecting the  sample  (per sample)
     Total number of hours  for collecting  the samples
     (Line 3 x Line 4)
     Number of hours for  preparing  and delivering sample
     (per each sampling cycle of eight wells)
     Total number of hours  for preparing and  delivering
     sample (Line 2 x Line  6)
     Person-hour costs for  collecting and  handling samples
     Total ground-water sampling and collection costs
     ((Line 5 + Line 7) x Line 8)
     Number of ground-water quality analyses
     Number of ground-water contamination  analyses
     Unit cost of ground-water quality analysis
     Unit cost of ground-water contamination  analysis
     Total ground-water quality analysis costs
     (Line 10 x Line 12)
     Total ground-water contamination analysis costs
     (Line 11 x Line 13)
     Total ground-water chemical analyses  costs
     (Line 14 + Line 15)
Soil Monitoring
     Soil Core Sampling:
     Number of soil core samples taken during the
     closure period
     Labor hours required for each  core sample
     (includes movement between sampling locations)
     Labor unit cost for collecting core sample
17
18
19.
3 wells
3 samples
?4 samples
2 hours
48 hours

3 hours

9 hours

$15/hour
$855

16 analyses
24 analyses
$77
$108
$1232

$2592

$3824
66 samples

.5 hours

S15/hour
                                   9-48

-------
WORKSHEET  C  (continued)
 20.
21.
22,
23.

24.

25.
26.

27.
28.
      Total  cost  of  collecting  soil  samples for the entire
      closure  period (Line  17 x Line 18 x Line 19)
      Unit soil core sample analysis cost (10 parameters)
      Total  soil  core sample chemical analysis cost
      (Line  17 x  Line 21)
      Lysimeter Sampling of Soil Moisture;
      Number of lysimeter samples  taken during the
      closure  period
      Labor  hours  required  for  each  lysimeter collection
      of soil  moisture
      Labor  unit  cost for collecting samples
      Total  sampling cost for lysimeter collection
      of soil  moisture  (Line 23  x Line  24 x Line  25)
      Unit cost for  moisture sample  analysis
      Total  cost  for moisture sample  chemical analysis
      (Line  23 x Line 27)
Administrative Costs
29.  Number of technical hours  for  administration
30.  Person-hour  technical  costs
     Total  technical costs  for  administration
      (Line 29 x Line 30)
     Number of clerical hours
     Person-hour clerical cost
     Total clerical  costs  (Line 32 x Line  33)
     Total administrative costs (Line  31 + Line 34)
Maintenance Costs
36.  Monitoring well maintenance (includes maintenance
     of associated equipment)
Cost Summaries for Monitoring
37.  Total cost of  ground-water monitoring for the
     closure period  (Line 9 + Line 16 + Line 36)
38.  Total cost of soil core sample  monitoring for
     the closure  period (Line  20 + Line 22)
31,

32,
33.
34,
35.
 $495

 $60
 $3960


 20

 1 hour

 $15/hour
 $300

 $150
 $3000
16 hours
$30/hpur
$480

16 hours
$8
$128
$608

$750
                                                              $5429
                                                              S4455
                                   9-49

-------
WORKSHEET C  (continued)

39.  Total cost for soil moisture  (lysimeter) monitoring      S3300
     for the closure period (Line  26 + Line 28)
40.  Total administrative costs (Line 35)                     $608
41.  Total monitoring costs for the entire closure  .          $13,792
     period  (Line 37 + Line 38 +• Line 39 + Line 40)
                                  9-50

-------
                       LAND TREATMENT FACILITIES
                    WORKSHEET D - FENCE MAINTENANCE
1.   Length of fence Co be replaced                        590 feet
2.   Unit cost of replacing fence                          S13.06/linear ft
3.   Total cost of replacing fence (Line 1 x Line 2)        $7705
                                 9-51

-------
                        LAND TREATMENT FACILITY
                WORKSHEET E - REPAIR OF DRAINAGE CHANNELS
1.   Length of drainage channels requiring excavation
2.   Channel volume per unit length

3.   Channel excavation unit cost
4.   Total channel excavation cost
     (Line 1 x Line 2 x Line 3)
5.   Unit cost for hand grading
6.   Channel surface area to be prepared by hand
7.   Total cost of hand grading (Line 5 x Line 6)
8.   Total replanting cost (including seed,
     fertilizer and mulch)
9.   Total channel repair cost
     (Line 4 + Line 7 + Line 8)
500 feet
.33 cu. yds.
per linear ft.
$.67/cu. yd.
$11.05

$.02/sq. ft.
4500 sq. ft.
$90
$50

$250.55
                                  9-52

-------
                         LAND TREATMENT FACILITIES
                 WORKSHEET F - MANAGEMENT INSPECTION OF  LAND
                        TREATMENT FACILITY OPERATIONS
 1.   Number of technical management person-hours
      required for each inspection of the land treatment
      facility
 2.   Inspection frequency
 3.   Duration of closure period
 4.   Total technical management person-hours required
      for inspections during the closure period
      (Line 1 x Line 2 x Line 3)
 5.   Person-hour costs for technical management duties
 6.   Total technical management costs for land treatment
      facility inspections (Line 4 x Line 5)
 7.   Additional technical management labor required
      related to the inspection program
 8.   Total cost of the additional technical management
      labor (Line 5 x Line 7)
 9.   Total cost of technical management labor
      (Line 6 + Line 8)
10.   Number of clerical hours required
11.   Person-hour costs for clerical labor
12.   Total cost for clerical labor (Line 10 x Line 11)
13.   Total inspection cost (Line 9 + Line 12)
8 hours
1 per month
15 months
120 hours
$30   '
$3600

10 hours

S300

$3900
                                   9-53

-------
                         LAND TREATMENT FACILITIES
                  WORKSHEET G - PROFESSIONAL CERTIFICATION
 1.   Number of person-hours  required  for  inspecting
      the land treatment  facility  and  its  operating records
 2.   Cost per person-hour
 3.   Total costs of professional  engineer's  time
      (Line 1 x Line 2)
 4.   Number of technical hours  required for  administrative
      duties
 5.   Person-hour costs for technical  administrative duties
 6.   Total administrative costs for technical labor
      (Line 4 x Line 5)
 7.   Number of clerical  hours required for administrative
      duties
 8.   Person-hour costs for clerical administrative duties
 9.   Total administrative costs for clerical labor
      (Line 7 x Line 8)
10.   Total administrative costs (Line 6 + Line 9)
11.   Total certification cost (Line 3 + Line 10)
40 hours

$75
S3000

8 hours

$30
$240

8 hours

$8/hour
$64
                                   9-54

-------
                         LAND TREATMENT FACILITIES
               WORKSHEET H - TOTAL COSTS PLUS ADMINISTRATION
                              AND CONTINGENCIES
 1.   Cost of disposing of inventory (From Worksheet A)       $ 7,200
 2.   Cost of decontaminating the facility (From Worksheet B) $ 3,173
 3.   Cost of monitoring (From Worksheet C)                   $13,792
 4.   Cost of fence maintenance (From Worksheet D)            $ 7,705
 5.   Cost of repairing drainage channels (From Worksheet E)  $   251
 6.   Cost of management inspections (From Worksheet F)       $ 3,964
 7.   Cost of professional certification of closure           $ 3,304
      (From Worksheet G)
 8.   Total of Line 1 through Line 7                          $39,389
 9.   Administration                                          $ 5,908
10.   Contingencies                                           $ 5,908
11.   Total costs of closure (Line 8 + Line 9 + Line 10)      $51,205
                                   9-55

-------
9.4                         EXAMPLE - LANDFILLS

     For  illustrative  purposes,  a sample cost estimate  has  been  developed
for a landfill with  the following characteristics:   the landfill has  been
in operation  for  10  years  and  covers approximately  75 acres.   Sixty-five
acres have been partially  -closed (i.e.,  they have been  filled  with  waste,
an adequate cap and  vegetative cover established and maintained).   Ten
acres of  the  landfill  are  currently in active use and have  not received
final cap or  cover but are largely filled.   Of the  65 acres which have
received  final cap and cover,  it is assumed  that approximately 5  acres
are in need of revegetation due  to failure of original  vegetation over
the life  of the facility.   The landfill accepts hazardous solid  waste re-
ceived in trucks.  Waste is  received for this site  in 55-gallon drums.
                                   9-56

-------
           SAMPLE CLOSURE COST ESTIMATING WORKSHEETS:  LANDFILLS

 A.    Disposing of Inventory
      1.   Volume of waste when processed for landfill disposal:   It is
 estimated from the closure plan that the most expensive closure conditions
 likely to occur over the life of facility would result in 900 55-gallon drums
 of  waste to be disposed and no trench yet constructed for their disposal.
 This  situation would occur when existing trenches  had been filled but not
 yet capped,  and waste continued to  be accepted for further disposal.
 This  estimate  should be based on the volume of the waste after  conducting
 the necessary  processing prior to disposal.   For example,  if  sludge is
 taken in,  the  proper volume to be used is that of  solidified  sludge,  not
 the volume of  the sludge as it enters the facility.   In this  case,  since
 waste is  accepted in drums  only,  there is no need  for further calculation.
      2.   Estimated volume  of  contaminated soil residues  disposed
 of  through on-site landfill operations:   This  volume  is  determined  from
 Worksheet  B.
      3.   Total volume  of wastes  to  landfills on-site  (Line  1  +  Line 2):
 In  this  case,  the total  volume to be  landfilled on-site  is  the  volume  of
 inventory  (800 cu.  yds.) plus  the estimate volume  of  residues and con-
 taminated  material to  be disposed of  on-site from  Worksheet B (600  cu.
 ,-ds.).   It  is  possible  in some cases  that not  all  inventory could be
 disposed of on-site.   For example,  if  two wastes normally are neutralized
 by  combination, and  there is  inadequate  volume  of  one of the wastes to
 complete neutralizing  the second waste at the  time closure commences,
 some  portion of the second waste would have  to  be  disposed of off-site.
      4.  Estimated cost of constructing a trench:  The cost of construct-
 ing a trench adequate for 1400 cu. yds. of material of the type indicated,
 including adequate liner, is estimated as $18,000,  based upon past  trench
 construction experience at  the facility.
     5.  Estimated cost of placing wastes in trench (excluding final
 cover and vegetation):  Based on the annual volume  and operating costs
of  the facility (excluding profits and depreciation), it is estimated
that the costs  of placing this waste will be $6000.
                                  9-57

-------
      6.   Total  cost  of disposing of  inventory (Line  4 + Line 5):  The
 total  cost  of disposing of inventory are then the  sum of Lines 4 and 5.

 B.   Decontaminating the Facility
      1.   Area of facility contaminated:  It is assumed  in  the  example  that
 at  the end  of facility life,  approximately  1800  sq.  yds. of the surface of
 the  facility will  show sufficient contamination  to justify its disposal
 as hazardous waste.
     2.   Depth  of  material removed:   It is  assumed that removal to 1 foot
 will be necessary.
     3.   Cost of removal:   The  assumed  cost of removing this material
 is $1.40  per cu. yd.  for a total cost of $840.   This does not include
 the  costs of disposing of  the material.
     4.   Quantity  disposed on-site:   For the  sample  problem, it is
 assumed that all 600  cu. yds. will be disposed on-site.
     5.  Quantity disposed at an off-site TSDF:  None of the material
 removed will be disposed off-site.
     6.  Cost to decontaminate  equipment:   It is assumed that $1000 will be
 sufficient  for decontaminating  equipment.
     7.  Volume of waste resulting from  decontaminating equipment:  It
 is estimated that  25  cu. yds. of material will need  to be disposed of
as a result of decontaminating  equipment.
     8.  Unit cost of  off-site  disposal:  Contact with other area
 hazardous waste disposal facilities indicates that land disposal for
 these wastes would currently  cost  $40/cu. yd.
     9.  Unit cost of  hauling:   Hauling  this small quantity of  residue
 20 miles  to nearest  landfill will  cost  $10  per cu. yd.  according to
 local trucking concerns.
    10.  Total cost of  off-site disposal  (Line 7 x Line 8):  Total costs
of disposing residue are then $1000.
    11.  Total cost of  hauling  (Line  7 x Line 9):  Total cost of hauling
 is then the unit cost  of hauling times  the  total volume of  residues to
be disposed.
    12.  Total cost of  decontaminating  the  facility (Line 3 •!• Line 6  +  Line
 10 + Line 11):  Total  costs are then  $2850.

                                   9-58

-------
C.   Placing Final Cap
     As noted in the summary of  this example, it has been  assumed  that
the equipment for all necessary  earth work is available  on-site.   As  a
result, costs for placing a final cap over the  fill area include only
labor, operating costs, and materials, not costs associated with rent-
ing equipment or capital recovery factors for purchased  equipment.
     1.  Area to be capped:  The example assumed that 10 acres, or 48,400
sq. yds., will remain open and require both a clay cap and topsoil.
     2.  Type of material used for impermeable  layer:  Clay is  the
impermeable material specified in the closure plan.
     3.  Depth of impermeable layer:  It is assumed that 2 ft.  of  clay
will provide an adequate cap.
     4.  Volume of material required (Line 1 x  Line 3):  The amount of
clay required is 32,428 yds. (48,400 x .67 yds.).
     5.  Source of impermeable material:  It is assumed  that clay  is
available on-site as a result of previous excavations, at a haul distance
of 800 yds. or less.
     6.  Cost of impermeable material:  Because the material is available
on-site, the cost is zero.
     7.  Depth of topsoil required:  It is assumed that  2  ft. of topsoil
will be adequate to ensure that  the roots from  vegetation of the fill
area do not penetrate the clay cap.
     8.  Volume of topsoil required (Line 1 x Line 7):   The amount  of
topsoil required is 32,423 cu.  yds.
     9.  Source of topsoil:  Again, it is assumed that adequate topsoil
is available on-site from previous excavations.
    10.  Cost of topsoil:  The cost in this case is zero, since the
material is available on-site.  (If topsoil were not available on-site,
a cost estimate would have to be developed through discussions with local
suppliers,  etc.)
    11.  Cost per cu. yd. for hauling, spreading and compacting clay and
topsoil:  In the example, it is assumed that  this can be done for $1.20
per cu. yd.
    12.  Cost of placing impermeable portion  of  cap (Line 4 x Line  11):
Based on these assumptions, the costs of placing the impermeable portion

                                   9-59

-------
 of  che cap would be $38,914.
      13.  Cost of placing topsoil (Line 8 x Line 11):  Based on the assump-
 tions, the costs of placing topsoil are also $38,914.
      14.  Total costs of final cap (sum of Lines 6, 10, 12, and 13):   The
 total costs of the final capping operation will be $77,828.  This does
 not  include administrative- expenses or contingency planning,  both of
 which are calculated on Worksheet G.

 D-    Planting Final Vegetation
      As in the above worksheets, it is assumed  that all necessary equip-
 ment  is available on-site,  but that material and labor costs  will be
 accrued during the closure  exercise.
      1.   Area not yet vegetated:  The  area remaining open  at  the  time
 of closing is 10 acres.
      2.   Area already closed but requiring replanting:   It is assumed
 in this case  that 5 acres  of the closed portion of the landfill require
 replanting,  due to the failure of original vegetation efforts.
      3.   Total area to be planted (Line 1 + Line 2):  . The  sample
 case  provides for 15 acres  to be planted during closure.
      4.   Type of vegetation to be used:   In  this  example,  it  is assumed
 that  coarse field grass  (a  mixture  of  rye grass  and  Kentucky  fescue)
will  be employed for final  vegetation.
      5.   Quantity of seed used per  acre:   According  to  industry suppliers,
 150 Ibs.  of seed should  be  applied  per  acre.
      6.   Cost  of seed  per pound:  Calls  to local suppliers determined that
seed  is available  at $.50/lb.
      7.   Total  cost  of seed  (Line 3  x Line 5 x Line 6):  Given the above
assumptions,  the total cost  of  seed  will  be $1125.
     8.   Type of  fertilizer  to  be used:   Given  the topsoil and climatic
conditions, 10/10/10  fertilizer  is assumed to be adequate.
     9.  Quantity  of  fertilizer  per  acre:  .25  tons is assumed to be
reasonable, given  the quality  of  topsoil  and the climatic conditions.
    10.  Cost of  fertilizer  per  ton:  According to local suppliers,
fertilizer is available  for  $200/ton.
                                   9-60

-------
      11.   Total  cost  of  fertilizer  (Line  3  x  Line 9  x Line  10):   Given
 the  above  assumptions, the  total  cost  of  fertilizer  is $750.
      12.   Cost of  soil preparation  per acre:   Preparing the soil includes
 both disking and fertilizing and  is assumed to be $100 per  acre.
      13.   Total  cost  of  preparing soil (Line  3 x  Line 12):   The  total
 cost of preparing  soil,  excluding materials such  as  fertilizers, is,
 given the  above  assumptions, $1500.
      14.   Cost per acre  of  seeding  (excluding cost of seed):   It is
 assumed for the  sample facility that seeding  will cost $150 per  acre.
      15.   Total  cost  of  seeding (excluding  seed)  (Line 3 x  Line  14):
 Given the  above  assumptions, the  total cost of seeding for  the facility is
 $2250.
      16.   Cost per acre  of  mulching:   The cost per acre of  purchasing  and
 applying a hay mulch  is  assumed to be  $120.
      17.   Total  mulching costs (Line 3 x Line 16):   Given the  above assump-
 tions, total mulching costs, including costs  of hay,  are $1800 for the

      18.   Total  costs for vegetation (sum of  Lines 7,  11, 13,  15, and  17):
 The  total  costs  for establishing  vegetation are $7425.

 E.   Gjround-water  Monitoring
     Assume that closure of the landfill will  require  a total of 90 days.
 In order co determine the maximum possible ground-water monitoring costs,
 the most extensive monitoring needed at closure is assumed.  Assuming
 that ground-water  quality analyses are required annually and ground-water
 contamination analyses are  required semi-annually, the most expensive
 case is that in which both sets of analyses are required during  the 90-
day closure period.
     1.   Number of wells monitored:  For the sample landfill, it is assumed
 that eight wells would need to  be monitored.
     2.   Number of samples per well:   One sample is taken per well for
both analyses.
     3.   Total number of samples  (Line 1 x Line 2):   Given the above
assumptions, eight samples are  required.
                                   9-61

-------
       14.   local ground-water contamination analysis costs (Line 10 x
  Line 12):   For eight samples at $108 per analysis, this yields a total
  cost of  $864.
       15.   Total analysis costs (Line 13  + Line 14):  The total analyses
  costs, therefore,  are $1480.
       16.   Number of  technical hours  for  administration:   This  includes
  all  time necessary to administer  and report  the data  from the  analyses
  and  is estimated as  8 hours.
       17.   Person-hour technical costs:   The  fully-loaded  cost  required
  for  this work  is  assumed  to be  $30 per hour.
       18.   Total  technical costs for  administration  (Line  16 x  Line  17):
 Given the  above  assumptions,  total costs  for administering the tests
 are assumed to be  $240.
      19.   Number of clerical hours:  Assume for  this case that  5 hours oJ
 clerical time are  required to produce the necessary reports.
      20.   Per-hour clerical costs:  Assume the fully-loaded costs for
 clerical work are  $8 per hour.
      21.   Total administrative costs (Line 19 x Line 20):  Given the above
 assumptions, the total clerical costs are S40.
      22.   Total administrative costs (Line 18 +'Line 21):   The sum of
 technical and clerical costs are then S280.
      23.   Monitoring  equipment maintenance:   It is assumed that an average
 of  S150  is  required for a 90-day period  to ensure adequate maintenance of
 monitoring  equipment  and wells.
      24.  Total monitoring costs (sum of  Lines  8, 15,  22,  and  23):   Total
 monitoring  costs,  excluding  administration and  contingencies, are then
 $2195.

 F.    Fence  Maintenance
      For a  75-acre  site,  assuming  that the site  is  square, each side  of
 the site is  1807  feet  in  length.   The perimeter  of  the site is  then
 7228  feet.
      1.   Length  of fence  to be  replaced:  It is  expected  that  some
sections of  Che  facility's security fence will have  corroded and will
have  to be  replaced.   Our estimate is that 10% of  the perimeter  fence
will have to be  replaced.
                                  9-63

-------
      2.   Unit  cost  of replacing fence:   The security  fence  around  the
 facility perimeter is  a galvanized metal chain  link  fence  6  feet high.
 This fence is made of  #9  wire.   The unit replacement cost  for this
 fence is $13.06 per  linear  foot.
      3.   Total cost of replacing  fence  (Line 1 x Line 2):  The cost of
 fence replacement is the  product of the  length of fence needing re-
 placement and the unit  cost of replacement,  for a total of $9442.

 G-    Professional Certification

      1.   Number of person-hours required for inspections:  It is
 assumed that 80 hours are required  for periodically inspecting all as-
 pects of closure of the landfill.
      2.    Cost per person-hour:  In  this case, assume that a registered
 independent  professional engineer may be hired at a cost of $75  per  hour.
      3.    Total costs of independent professional engineer's  time (Line
 1 x Line 2) :   This yields a total cost of S6000  for the independent
 professional  engineer.
      4.   Number of  technical hours required for administrative  duties:
 Assume  that 8 hours  are required  from the owner/operator's  staff for
 administrative duties connected with employing an  independent professional
 engineer.
      5.   Person-hour costs  for technical administrative duties:  It  is
 assumed  that  the  total  fully-loaded costs for the  owner/operator's rtaff
 are  $30  per hour.
      6.   Total  administrative  costs for  technical labor (Line 4 x Line 5):
Given the above assumptions,  the  total  administrative costs for  technical
 labor are S240.
      7.  Number  of clerical  hours required for administrative  duties:
Assume  that 5  hours of  clerical time are  required  for the necessary  typing
 and  certifications.
     8.  Person-hour  costs for  clerical administrative duties:   Fully-
loaded costs of clerical time are assumed to  be $8.
     9.  Total administrative costs  for clerical labor (Line 7 x Line 8):
Given the above assumptions,  total  clerical costs are $40.

                                   9-64

-------
     10.   local administrative coses (Line 6 + Line 9):   Summing technical
 and  clerical  labor,  the  cocal administrative costs are  $280.
     11.   Total certification costs (Line 3 + Line 10; :   The total costs
 for  certification, including the engineer's fees  and  administrative costs
 1 a r lia,i  CfiOQn                                                             '
is  then


H*   T°tal Closure Costs  Including Adminisrration and Contingencies
     Lines 1 through  7 of  this Worksheet simply summarize  the  total  closure
costs, excluding administration and contingencies, from each of  the  prior
worksheets.

     8.   Total  of  Lines  1 through 7:   The  total costs for  the  activities
listed in Lines  1  through 7  are $130.020.
     9.   Administration:   For administrative  tasks,  including  taxes,
insurance, and administration and supervision not included elsewhere,
a total of 15 percent of  total costs  from  Line 8 is  used.
    10.   Contingencies:  A general provision  for contingencies of  15
percent of total costs has been included.
    11.  Total closure costs (Line 8 + Line 9 + Line 10):  The estimated
total closure costs are then $169,026.
                                  9-65

-------
                                 LANDFILLS
                     WORKSHEET A - DISPOSING OF INVENTORY
1.   Volume of waste when processed  for  disposal  '      800 cu. yds.
2.   Estimated volume  of  residue  and contaminated        600 cu. yds.
     soil to be disposed  through  on-site  landfill
     operation
3.   Total volume of waste  to be  landfilled on-site      1400 cu. yds.
     (Line 1 + Line 2)
4.   Estimated cost of constructing  trench               $18,000
5.   Estimated cost of placing waste in                  $ 6,000
     trench
6.   Total cost of disposing of inventory                $24 000
     (Line 4 + Line 5)
                                  9-66

-------
                                  LANDFILLS
                WORKSHEET B - DECONTAMINATING THE  FACILITY
 1.
 2.
 3.
 4.

 5.
 6.
 7.

 8.
 9.
10.
11.
12.
 Area of  facility  contaminated
 Depth of material removed
 Cost of  removal
 Quantity disposed on-site  (see Worksheet A
 to develop cost)
 Quantity disposed off-site
 Cost to decontaminate equipment
 Volume of waste resulting from decontaminating
 equipment
 Unit cost of off-site disposal ($/cu. yd.)
 Unit cost of hauling ($/cu. yd.)
Total cost of disposing off-site (Line 7 x Line 8)
Total cost of hauling (Line 7 x Line 9)
Total costs of decontaminating the facility
 (Line 3 + Line 6 + Line 10 + Line 11)
1800 sq. yds.
.33 yd. (1 ft.)
$840
600 cu. yds.

0
$1000
25 cu.  yds.
                                   9-67

-------
                                  LANDFILLS
                    WORKSHEET  C  - PLACING FINAL  CAP
      Area  Co be  capped  (include  sum of  all  portions
      of  Che  facility  remains  open and any portions of
      the facility  opened to dispose of  inventory and
      wastes  from- the  process  of  decontamination)
      Type  of material used for impermeable  layer
48,400 sq. yds.
(10 acres)
Clay with perm-
eability of 10~7
      Depth of material  of  impermeable  layer
      Volume of material to be  used  for impermeable
      layer (Line 1 x Line  3)
      Source of impermeable material
 6.   Cost of impermeable material
 7.   Depth of topsoil
 8.   Volume of topsoil  (Line 1 x Line 7)
 9.   Source of toosoil
10.   Cost of topsoil
11.   Cost per cu. yd. for hauling, spreading and
      compacting
12.   Cost of impermeable portion of cap
      (Line 4 x Line 11)
13.   Cost of placing topsoil  (Line 8 x Line 11)
14.   Total costs (Line 6 +• Line 10 4- Line 12 + Line 13)
.667 yds. (2 ft.)
32,428 cu. yds.

On-site from
previous exca-
vations
0
.667 yds. (2 ft.)
32,428 cu. yds.
On-site from
previous exca-
vations
0
$1.20

$38,914

$38,914
$77.828
                                    9-68

-------
                                 LANDFILLS
                  WORKSHEET  D  -  PLANTING  FINAL  VEGETATION
 1.   Area not yet vegetated  (should be approximately
      equivalent to area remaining open)
 2.   Area already closed but in need of some  replanting
      prior to final closure
 3.   Total area to be planted  (Line 1 + Line  2)
 4.   Type of vegetation to be  used
 5.   Quantity of seed per acre
 6.   Cost of seed per pound
 7.   Total cost of seed (Line  3 x Line 5 x Line 6)
 8.   Type of fertilizer to be used
 9.   Quantity of fertilizer per acre
10..   Cost of fertilizer per ton
11.   Total cost of fertilizer  (Line 3 x Line  9 x
      Line 10)
12.   Cost of soil preparation per acre
13.   Total cost of preparing soil (excluding
      materials)  (Line 3 x Line 12)
14.   Cost per acre of seeding  (less materials)
15.   Cost of seeding  (Line  3 x Line  14)
16.   Cost per acre of mulching
17.   Total mulching costs (Line 3 x Line 16)
18.   Total costs for vegetation
      (Line 7 + Line 11 -I- Line 13 + Line 15 + Line 17)
10 acres

5 acres

15 acres
Coarse grass
150 Ibs.
$.50
$1125
10/10/10
.25 tons
$200
$750

$100
$1500
                                    9-69

-------
                                LANDFILLS
                  WORKSHEET  E - GROUND-WATER MONITORING
 1.   Number of wells monitored                               8 wells
 2.   Number of samples per- well                              1 sample
 3.   Total number of samples  (Line 1 x Line 2)               8 samples
 4.   Number of hours required for collecting sample          2 hours
      (per sample)
 5.   Total number of hours required for collecting samples   16 hours
      (Line 3 x Line 4)
 6.   Number of hours required for preparing and delivering   3 hours
      samples
 7.   Person-hour costs for collecting samples                $15
 8.   Total sampling and collection costs                     $285
      ((Line 5 + Line 6) x Line 7)
 9.   Number of ground-water quality analyses                 8 analyses
10.   Number of ground-water contamination analyses           8 analyses
11.   Unit cost of ground-water quality analysis              S77
12.   Cost of ground-water contamination analysis        ,     S108
13.   Total ground-water quality analysis costs               $616
      (Line 9 x Line 11)
14.   Total ground-water contamination analysis costs         $864
      (Line 10 x Line 12)
15.   Total analyses costs  (Line 13 + Line 14)                $1480
16.   Number of technical hours for administration (e.g. ,     „
      reporting data to EPA)
17.   Person-hour technical costs                             S30
18.   Total technical costs for administration                S240
      (Line 16 x Line 17)
19.   Number of clerical hours                                5 hours
20.   Person-hour clerical costs                              $8
21.   Total clerical costs  (Line 19 x Line 20)                $40
22.   Total administrative costs (Line 18 + Line 21)          $280
                                    9-70

-------
WORKSHEET E - continued

23.  Monitoring equipment maintenance
24.  Total monitoring costs (Line 8 + Line 15
     Line 22 -I- Line 23)
                                  9-71

-------
                               LANDFILLS
                    WORKSHEET F -  FENCE MAINTENANCE
1.   Length of fence to be replaced                          723 feet
2.   Unit cost of replacing fence                            $13.067
                                                             linear ft.
3.   Total cost of replacing fence                           $9442
     (Line 1 x Line 2)
                                   9-72

-------
                                LANDFILLS
                  WORKSHEET G - PROFESSIONAL CERTIFICATION
 1.   Number of person-hours required for inspections
 2.   Cost per person-hour
 3.   Total costs of independent professional engineer
      certification (Line 1 x Line 2)
 4.   Number of technical hours required for administrative
      duties
 5.   Person-hour costs for technical administrative duties
 6.   Total administrative costs for technical labor
      (Line 4 x Line 5)
 7.   Number of clerical hours required for administrative
      duties
 8.   Person-hour costs for clerical administrative duties
 9.   Total administrative costs for clerical labor
      (Line 7 x Line 8)
10.   Total administrative costs (Line 6 + Line 9)
11.   Total certification costs (Line 3  + Line 10)
80 hrs,
$75
$6000

8 hrs.

$30
$240

5 hrs.

$8
$40
                                   9-73

-------
                                 LANDFILLS
              WORKSHEET  H  -  TOTAL COSTS OF  CLOSURE  INCLUDING
                    ADMINISTRATION AND CONTINGENCIES
 1.   Cost of disposing of  inventory  (From Worksheet A)       $ 24,000
 2.   Cost of decontaminating the surface and ancillary       $  2,850
      facilities  (From Worksheet B)
 3.   Cost of placing the final cap (From Worksheet C)        $ 77,828
 4.   Cost of planting final vegetation  (From Worksheet D)    $  7,425
 5.   Cost of ground-water  monitoring  (From Worksheet E)      $  2,195
 6.   Cost of fence maintenance (From Worksheet F)            $  9,442
 7.   Cost of professional  certification (From Worksheet G)   $  6,280
 8.   Total of Line 1 through Line 7                          $130,020
 9.   Administration                                          $ 19 f503
10.   Contingencies                                           $ 19,503
11.   Total costs of closure (Line 8 + Line 9 + Line 10)      $169,026
                                    9-74

-------
9.5                      EXAMPLE - INCINERATORS

     A 12-acre incinerator facility has bulk storage facilities for 120,000
gallons of slop oil, 120,000 gallons of phenolic wastewater, and 1,000,000
gallons of organic sludge.  Waste is also delivered in 55-gallon drums;  a
maximum of 600 drums may be stored at the facility.  In addition to these
delivered wastes, the facility normally contains an inventory of 50 drums
of non-combustible ash from the incinerator.
     The incinerator is designed to operate at 16 gpm with the following
feed mixture: 4 gallons of slop oil, 4 gallons of wastewater, and 8 gallons
of sludge (a 1/1/2 ratio).  The total operating horsepower of the incinerator
(including pollution control equipment in the form of a caustic scrubber
used to remove chlorinated compounds emitted from the slop oil) is 350 HP.
The following worksheets are based on this facility description.
                                   9-75

-------
         SAMPLE CLOSURE  COST  ESTIMATING WORKSHEETS:  INCINERATORS

A.   Characterizing the  Waste Inventory
     Worksheet A is used to describe  each waste accepted at  the site.  For
the example, worksheets  must  be  prepared for each of  the following wastes:
slop oil, phenolic wastewater, and biological  treatment sludges.  For each
vaste product accepted,  the following information is  required:
     1.  Describing the  waste:   Describing the origin and general nature
of the waste.
     2.  Chemical composition:   Chemical composition  should  be expressed
in weight percents for major  components and parts per million (ppm) for
trace components.  This  information should be  readily available to the
operator from the bill of  lading for  each waste shipment.
     3.  Physical state  of the waste:  This describes whether the waste is
a liquid, solid, or mixture.  This information is utilized in making estimates
of solid .residues requiring disposal  (Worksheet B).
     4.  Heat of combustion of the waste:  The heat content  (expressed in
BTU/lb., or BTU/gal.) of the waste products.  This information is used in
determining auxiliary fuel requirements (if any) on Worksheet C.
     5.  Specific gravity  of  the waste:  The specific gravity of the waste
at 60 F referenced to water at 60 F is used in the example problem.
     6.  Closure inventory:  For the  example, it has been assumed that the
operator has identified  from  experience that the maximum inventory he has
ever had stored on-site  was a 14-day  backlog.  We will assume that this
inventory is comprised of  the total components: 224 drums of slop oil
(12,320 gallons), 224 drums of phenolic wastewater (12,320 gallons) and
152 drums of sludges (8,360 gallons);  the bulk storage tanks contain 28,000
gallons of slop oil, 28,000 gallons of phenolic wastewater,  and 233,560
gallons of organic sludges.   Under these conditions,  the incinerator will
be able to treat its inventory through seven days of burning its optimum
feed mixture, and seven  days  of  burning sludges alone (through the addition
of auxiliary fuels) .
                                     9-76

-------
 B.   Treating the Inventory
      It is assumed that the inventory on-hand at the time of closure will
 be incinerated on-site.  All equipment necessary for the operation of the
 incinerator is assumed to be in complete working order.
      1.  Time required for treating the inventory:  It will require 336 hours
 (322,560 gallons of waste ^ 960 gallons throughput per hour).  If it is
 further assumed that the incinerator is on-stream 90% of the time, the total
 time required for treating on-site inventory is 373 hours.
      2.  Manpower requirements for treating the inventory:   The total number
                                                                       *
 of personnel required to operate this facility (including plant operators,
 equipment operators,  guards, maintenance persons, and laboratory personnel)
 is estimated as six.   Therefore, total man-hour requirement for treating
 the inventory is 2238 hours.
      3.  Cost of manpower:  The average hourly wage rate of a plant operator
 (including fringe benefits and labor burdens)  is assumed to be $20.
      4.  Total costs  of operating labor during inventory treatment (Line 2
 x Line  3):   Given the above assumptions, labor costs for this phase of
 closure are $44,760.
      5.  Fuel requirements for treating the inventory:   These represent both
 the cost of utilities consumed in order to treat the waste  inventory,  plus
 any auxiliary fuels which had to be purchased.   Each of these items is
.separately costed below.
      6.  Electricity  requirenents for treating the inventory:   The inciner-
 ator is actually in operation for 336 hours.   Electricity requirements for
                                        WTJ
 the example are equal to  350 HP x .746 ^- x 336  hours  = 87,730  Sewn.
      7.  Costs of electricity:   Electricity is assumed  to be  available at
 a  cost  of $.06/kwh.
                                                              i
      8.  Total costs  of electricity (Line  6 x  Line  7):   Total electricity
 costs for the  example are  $5264.
      9.  Auxiliary fuel requirements:   During  the  first 168 hours  of inven-
 tory treatment,  the incinerator will  be receiving an input  feed of 25% slop
 oil,  25% phenolic  wastewater,  and 50%  organic  sludges.   This  feed  has  a
 heat value  of  2900 BTU/lb.  and  will burn autogenously.   During  the remaining
 168  hours,  the feed will be  comprised  entirely of sludges, with a  heat
 value of 700 BTU/lb.;  this mixture  does  require  auxiliary fuel inputs.

                                    9-77

-------
      10.  Type of auxiliary fuel used:  It is assumed that i?6 fuel oil is
 used  as  the auxiliary fuel.
      11.  Quantity of fuel required:  Using engineering analysis,  and
 assuming  an average heat value of 154,000 BTU/gal.  for fuel oil,  total
 auxiliary fuel requirements  are estimated at 10,456 gallons.
      12.  Cost of auxiliary fuel:  It is assumed that #6 fuel oil  is available
 to  the operator at $.90 per  gallon.
      13.  Total cost of auxiliary fuels (Line 11 x Line 12):  The  total
 cost  of auxiliary fuel inputs is $9410.
      14.  Total fuel costs (Line 8 + Line 13):  Total fuel costs are $14,674.
      15.  Chemical requirements:  This category includes all chemicals,
 catalysts,  adsorbents, and other supplies consumed  during inventory treat-
 ment.  In the example, the only chemical required is the  caustic  consumed
 during flue gas scrubbing of chlorine entrained in  the incinerator waste
 stream.
      16.  Type of chemicals used:  It is assumed that the  caustic  will be
 purchased as  a 50% solution.
      17.  Quantity of chemicals required:  There are 40,320 gallons of sloo
 oil in the  waste inventory assumed to be present at the time of closure.
 This  is equivalent to 319,334 Ibs.  of slop oil (40,320 x  .95 specific
 gravity of  slop oil x 8.34 Ibs./gal. water).   Since the chlorine  content
 of  the slop oil is assumed to be no greater than 3  percent,  the maximum
 quantity  of chlorine to be scrubbed is 9,580 Ibs.  (270 moles).  Assuming
 that  1 mole of NaOH is required to neutralize 1 mole of chlorine,  270 moles
 x 40  Ibs. NaOH/mole = 10,800 Ibs.  NaOH-consumption.
      18.  Cost of chemicals required:  Caustic is assumed  to cost  $.08257
 dry Ib.
      19.  Total cost of chemicals (Line 17 x Line 18):   The total  cost of
 chemicals consumed during inventory treatment  is S891.
      20. Disposing or treating residues generated during inventory  treatment:
The residue generated during  inventory  treatment is  a  powdery solid,  inciner-
ator ash.   The  ash has  a  specific  gravity of  2.5.
     21. Amount of residue on-site  after treating the  inventory:  There
are 50 55-gallon drums  of  ash stored on-site  at  the  point of closure  (each
weighing  1150  Ibs.,  for a  total  of  57,500 Ibs.).  In addition,  residues
                                     9-78

-------
 are  generated by  processing  the  waste  inventory.   The  sludges  incinerated
 in  the  example are assumed  to  be 10  percent  solids;  one-third  of the solids
 are  assumed  to be non-combustible.   The  slop oil  and wastewaters processed
 by  the  incinerator produce no  ash.   Therefore,  the amount  of new residue
 generated  =  (total amount of sludge  in inventory  times specific gravity
 of  the  non-combustible por.tion of the  materials times  the  portion of the
 sludge  that  is non-combustible),  or:
         241,920 x (2.5 x 8.34)  x .0333  -  167,968 Ibs.
 Total residue to be disposed of  is equal to  167,968  Ibs. and 57,500  Ibs.  =
 225,468 Ibs.
     22. Method of disposing of  ash:   It is  assumed  that the incinerator
 ash  is  put into drums and transported  to a secure landfill.  The residue
 generated during inventory treatment can be  placed in  146  drums,  making
 the  total number of drums to be  disposed of  196.
     23. Unit costs of disposing  of residue:  The costs of disposing in
 a landfill are assumed to be $50/drum, according  to  industry specialists.
     24. Total costs of disposing of residue  (Line 21  x Line 23):  Total
 costs for the sample case are  $9800.
     25. Costs of hauling residue  to landfill for disposal:  In the  examole,
 it is assumed that the nearest landfill  that  will accept the drummed
 residue is 50 miles away, and  that trucks with a  carrying  capacity of  40
 drums are rented at an hourly  cost of  $60.  At a  speed of  40 mph, and
 assuming four hours for loading/unloading each trip, the total  hauling
 costs are estimated at $1950.
     26. Total cost of treating and disposing of  inventory (sum  of Lines
 4, 14,  19,  24, and 25):  Given the above assumptions,  the  total  cost of
 inventory disposal will be $72,075.

 C.   Decontaminating the Facility
     In order to completely decontaminate the incinerator facility,  the opera-
 tor  must see to it that all storage tanks and liquid waste feed  lines are
 cleaned, that wastewaters from the cleaning process are properly  disposed
or treated, that all equipment structures and containers left on-site are
decontaminated,  and that all contaminated soil is  removed properly.  These
various activities are individually costed below.
                                   9-79

-------
 Tank Cleaning
      1.   Storage tank cleaning:  The total volume of storage capacity to
 be cleaned is 1,240,000 gallons (120,000 gallons of slop oil storage,
 120,000 gallons of phenolic wastewater storage, and 1,000,000 gallons of
 organic sludge storage).
      2.  Method used:  The cleaning method selected for the sample case
 is steam-cleaning.
      3.  Unit cost of cleaning:  Renting equipment, labor,  and operating
 costs  for 1600 gal./hour of cleaning equipment are assumed  to be  approxi-
 mately $.02/gal.  of  capacity cleaned, based on information  from the Means
 construction  cost guide.
      4.  Total costs of storage tank cleaning (Line 1 x Line 2):   Total
 costs  of  steam-cleaning the storage facility are $24,800, given the above
 assumptions.
     5.   Cleaning residue generation:  According to closure  guidelines  for
waste  treatment sites issued by the Texas  Department of Water Resources,
 tne  amount of  contaminated washwaters produced by steam-cleaning  can  be
 assumed to be  equal  to .125 times  the volume of the tank being cleaned.
     6.   Quantity of cleaning residue generated (Line 1 x Line 5):
 155,000 gallons of contamined washwater  are generated in the example.
     7.   Method of disposing of residue:   In the sample case,  residues  are
assumed to be  transported by tank  truck  to  a surface impoundment  for
evaporation.
     8.   Unit costs  for disposing  of  residues:   Based on waste disposal
industry  estimates,  it  will cost $.05/gal.  to  dispose of residues in an
impoundment.
     9.   Total costs  for  disposing  of  residues  (Line  6  x Line 8):   Total
costs of  cleaning  residue  disposal, given these  assumptions, are $7750.
     10.   Hauling  costs  for residues:   In the example, hauling  cost esti-
mates are based on the  following assumptions - the  distance between the
incinerator and the  surface impoundment is  100  miles  one-way, a 7000-gallon
trailer is used,  the  average  trip  speed is  40  mph,  and  the hourly rental
cost of truck and  driver  is  $60.   The  cost  of  one round  trip is $300.
    11.   Number of trips  required:  The number  of trips required for the
case is 23.
                                   9-80

-------
      12. Total hauling costs for residues (Line 10 x Line 11):  The hauling
 costs for residue disposal are estimated at $6900.

 Decontaminating the Facility
      13. Flush out liquid waste feed lines:   The estimated cost of flush-
 ing out  all liquid residues from feed lines  on the facility (before the
 storage  areas  and incinerators are cleaned)  is assumed to be roughly one-
 eighth of the  costs of tank cleaning, or $3000.
      14. Pump  out and backfill sumps:  Sumps are to be decontaminated to
 prevent  the possibility of rain water accumulating and contaminating these
 portions of the facility.   The estimated costs of  this activity are
 $2000.
      15.  Removing contaminated soils:  Because of  spills  and other
 accidental releases,  certain areas  of the waste disposal  site such as
 the dikes in areas  around  storage  tanks may  be contaminated.   We have
 assumed  in this example problem that  2.5 percent of the area of the site
 (exclusive of  reservoirs,  ponds, and  basins)  is contaminated.
          Contaminated area = .025 x 12  acres  x 4840 sq. yd./acre
                            = 1452 sq. yds.
      16.  Depth  of soil removal:  For  this example,  the assumed depth  of
 soil  removal is  one  foot.
      17.  Total  amount of soil  removed (Line  15  x Line  16):   The total
 amount of soil  removed  in  this  example  is (1452  x  .333),  or  484 cu. yds.
      18.   Unit cost of  removing  soil:  Costs of  removing soil  (including
 equipment rental) are  estimated at  $1.60/cu. yd.
      19.   Total  cost of  soil  removal (Line 17 x Line  18):  Given the above
 assumptions, the cost  of removing the contaminated soil from  the inciner-
 ator  site  is $774.
      20.   Costs for disposing of contaminated soils:  The contaminated soil
 is assumed to be disposed in a sanitary landfill.  Based on current esti-
mates, the soil can be landfilled at a cost of $30/ton.
      21.  Total cost of disposing of soil (Line 17 x Line 20):  The cost
of disposing of the contaminated soil is 314,520.
      22.  Hauling costs for contaminated soil:  In this example, the
nearest landfill is assumed to be 50 miles away, the truck used for haulins

                                   9-81

-------
 has  a carrying capacity of 44,000 Ibs. ,  and is rented at a hourly cost
 of S60.
      23.  Number of trips required:  Assuming an average speed of 40 mph,
 22 trips  will be required.
      24.  Total hauling costs for contaminated soil (Line 22 x Line 23):
 Given the above assumptions, the total  costs for hauling the contaminated
 soil are  $3300.
      25.  Total costs of decontaminating  the facility (sum of Lines 4, 9,
 12,  13, 14,  19, 21,  and 24):  The total  costs of decontaminating the
 sample incinerator are $63,044.

 D.    Monitoring
      1.   Cost of air sampling during inventory treatment:   In order  to
 ensure that  the incinerator remains  in compliance with  Clean Air Act
 regulations  during the closure period, it  was assumed that  daily sampling
 cost  of $25  are incurred while the incinerator is operating.
      2.   Number of samples required:  The  inventory  treatment, phase  of
 closure is estimated to take 16  days  at  the sample site.
      3.   Total  costs of monitoring (Line 1 x Line 2):   Given  the  above
 assumptions,  monitoring costs  will be equal to $400.

 E.   Professional  Certification
      1.   Number of person-hours  required for inspections:   It  is  assumed
 that  20 hours are  required for periodically inspecting  all  aspects of
 incinerator  closure.
      2.   Cost per  person-hour:   In this case,  assume  that a registered
 independent  professional engineer  may be hired at  a cost of $75 per hour.
      3.   Total  costs  of  independent professional  engineer's time  (Line 1
 x Line 2)  :   This yields  a  total  cost  of $1500  for  the independent profes-
 sional engineer.
      4.  Number  of technical hours required  for administrative duties:
Assume that  eight  hours  are  required  from  the  owner's or operator's staff  for
administrative  duties  connected with  employing an  independent professional
engineer.
                                   9-82

-------
      5.  Person-hour coses for technical administrative duties:  It is
 assumed that the total fully-loaded costs for the owner's or operator's staff
 are $30 per hour.
      6.  Total administrative costs for technical labor (Line 4 x Line 5):
 Given the above assumptions,  the total administrative costs for technical
 labor are $240.
      7.  Number of clerical hours  required for administrative duties:
 Assume that five hours of clerical time are required for the necessary
 typing and certifications.
      8.  Person-hour costs  for clerical administrative  duties:   Fully-
 loaded costs of clerical  time are  assumed to be $8.
      9.   Total administrative costs for clerical labor  (Line 7  x Line  8):
 Given the above assumptions,  total clerical costs are $40.
     10.   Total administrative costs (Line 6 -I- Line 9):   Summing technical
 and  clerical labor,  the administrative  costs are $280.
     11.   Total certification  costs (Line  3  + Line 10):   The total costs for
 certification,  including  engineer's fees  and administrative costs,  are
 $1780.

 F-    Total  Costs Including  Administration and Contingencies
      Line  1  through  4:  These  lines  simply  require the  transfer of  the
 cost  information supplied in Worksheets 3 through  E.
      5.   Preliminary closure cost  estimate  (sum  of Lines  1  through  4):
 For  the sample  facility,  total worksheet  costs are qual  to  $137,299.
      6.  Administration:  The costs  for administration, which include
 insurance,  taxes, and  supervision  and administration not  included else-
where, are assumed to  be 15 percent of Line  5.
      7.  Contingencies:  A  provision for  contingencies of 15 percent of
Line  5 has been included.
      8.  Total costs of closure  (Line 5 +• Line 6 4- Line 7):  The  total
costs of closure, including administration and contingencies, for the
sample incinerator are $178,489.
                                   9-83

-------
                               INCINERATORS
                 WORKSHEET A - CHARACTERIZING THE WASTE (#2)

This worksheet should be used  to describe each waste accepted at the facility,

1.   Description of ths waste:
         Phenolic wastewater
2.   Chemical composition of the waste:
         1000 ppm phenols
3.   Physical state of the waste:
         Liquid
4.   Heat of combustion of Che waste:
         0
5.   Specific gravity of the waste:
         1.0
6.   Closure inventory:
         40,320 gal.
                                  9-84

-------
                               INCINERATORS
                WORKSHEET A  - CHARACTERIZING  THE  WASTE  (#3)

This worksheet should be used Co describe each waste  accepted  at  the  facility,

1.   Description of the waste:
         Waste activated sludge
2.   Chemical composition of  the waste:

3.   Physical state of the waste:
         Mixture (suspension) - 10% solids, 90% water
4.   Heat of combustion of the waste:
         700 BTU/lb.
5.   Specific gravity of the waste:
         1.06
6.   Closure inventory:
         241,920 gal.
                                     9-85

-------
                                 INCINERATORS
                    WORKSHEET  B  -  TREATING THE  INVENTORY
  1,
  2,
  3.
  4.

  5.
  6.
  7.
  8.
.  9.

 10.
 11.
 12.
 13.

 14.

 15.
 16.
 17.
 18.
 19.
 20.
 21.

 22.
 23.
 24.

25.
26.
 Time required for treating the inventory
 Manpower requirements for treating the inventory
 Unit cost of labor
 Total cost of labor - treating the inventory
 (Line 2 x Line 3)
-Fuel requirements
 Electricity requirements
 Unit cost of electricity
 Total costs of electricity (Line 6 x Line 7)
 Auxiliary fuel requirements

 Type of fuel used
 Quantity of fuel required
 Unit cost of fuel oil
 Total cost of auxiliary fuels
 (Line 11 x Line 12)
 Total fuel costs for treating inventory
 (Line 8 -S- Line 13)
 Chemical requirements
 Type of chemicals used
 Quantity of chemicals used
 Unit cost of chemicals
 Total cost of chemicals (Line 17  x Line 18)
 Residues generated  during inventory treatment
 Amount of residue generated

 Method of treatment
 Unit  cost of disposing of residue
 Total  costs  of  disposing  of residue
 (Line  21 x Line  23)
 Hauling  coses  for disposing of residue
 Total  costs  of  treatine and disposing of
 inventory (sum  of Lines 4,  14, 19,  24,  and 25)
                                9-86
 373  hours
 2238 man-hours
 S20/hr.
 $44,760

 Yes
 87,730 kwh
 $.06/kwh
 $5264
 Yes,  for input
 feed B
 #6 fuel oil
 10,456 gal.
 S.90/sal.
 $9410

 $14,674

 Yes
 Caustic, 50% solution
 10,800 Ibs.
 $.0825/lb.
 $891
 Incinerator ash
 225,468 Ibs.
 (196  drums)
 Landfill
 S50/drum
 $9800

$1950
$72,075

-------
                                INCINERATORS
                WORKSHEET C  - DECONTAMINATING THE  FACILITY
  1.
  2.
  3.
  4.
  5.
  6.
  7.
  8.
  9.

10.
11.
12.

13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
 Volume  to  be  cleaned
 Method  used
 Unit  costs of  cleaning
 Total costs of tank cleaning  (Line  1  x  Line  2)
 Cleaning residue  generation rate
 Amount  of  residue  generated (Line 1 x Line 5)
 Method  of  disposal
 Unit  cost  for  disposing of residue
 Total costs for disposing of residue
 (Line 6 x  Line 8)
 Unit  cost  for  hauling residues
 Number of  trips required
 Total costs of hauling residues
 (Line 10 x Line 11)
 Cost of flushing liquid waste feed lines
 Cost  to pump out and backfill sumps
 Amount of  contaminated soil area
 Depth of soil  removal
 Total amount of soil removed (Line 15 x Line 18)
Unit cost of removing soil
Total cost of removing soil (Line 17 x Line 18)
Costs for disposing of contaminated soils
Total cost of disposing of soil (Line 17 x Line 20)
Unit costs of hauling contaminated soils
Number of trips required
Total cost of hauling soils (Line 22 x Line 23)
Total costs of decontamination (sum of Lines
4, 9,  12,  13,  14,  19,  21, and  24)
 1,240,000 gal.
 S team-cleaning
 $.02/gal.  capacity
 $24,800
 .125  x volume of tank
 155,000  gal.
 Surface  impoundment
 $.05/gal.
 $7750

 $300/trip
 23
 $6900

 $3000
 $2000
 1452 sq. yds.
 1 ft.
 $774
 $1.60/cu. yd.
 $774
 $30/ton
 $14,520
 $150
 22
 $3300
$63,044
                                   9-87

-------
                              INCINERATORS
                        WORKSHEET D - MONITORING
1.   Cose of air sampling
2.   Number of samples required
3.   Total coses of air monitoring (Line 1 x Line 2)
                                     9-88

-------
                               INCINERATORS
                 WORKSHEET E - PROFESSIONAL CERTIFICATION
 1.   Number of person-hours required for inspecting the     20
      facility
 2.   Cost per person-hour                                   $75
 3.   Total costs of independent professional engineer       $1500
      certification (Line 1 x Line 2)
 4.   Technical hours required for administrative            8 hrs,
      duties
 5.   Person-hour costs for technical administrative duties  $30
 6.   Total administrative costs for technical labor         $240
      (Line 4 x Line 5)
 7.   Number of clerical hours required for administrative   5 hrs.
      duties
 8.   Person-hour costs for clerical administrative duties   $8
 9.   Total administrative costs for clerical labor          $40
      (Line 7 x Line 8)
10.   Total administrative costs (Line 6 + Line 9)
11.   Total certification costs (Line 3 + Line 10)
                                    9-89

-------
                              INCINERATORS
  WORKSHEET  F  -  TOTAL  COSTS  INCLUDING ADMINISTRATION AND  CERTIFICATION
1.   Costs of  creating  and  disposing  inventory  (From       $  72,075
     Worksheet B)
2.   Costs of decontaminating  the  facility  (From           $  63,044
     Worksheet C)
3.   Costs of monitoring  (From Worksheet D)                $    400
4.   Costs of professional  certification (From             $  1,780
     Worksheet E)
5.   Estimated basic costs  of  closure  (sum of Lines        $137,299
     1, 2, 3, and 4)
6.   Administration                                        $  20,595
7.   Contingencies                                         $  20,595
8.   Total costs of closure                                $178,489
                                   9-90

-------
9-6          EXAiMPLE - MULTIPLE PROCESS  FACILITY WITH TANKS
                         AND SURFACE  IMPOUNDMENTS-

     A 2-acre hazardous waste treatment  and storage  facility has storage
tanks for 60,000 gallons of waste solvents and  10,000 gallons of slop
oil.  Waste is received at. the facility  both from tank trucks and  in
55 gallon drums; the facility has a maximum storage  capacity of 200
drums.  There are two treatment processes undertaken at the facility.
There is a 30,000 gallon (50* x 20' x 4') concrete-lined surface
impoundment used for the gravity separation of  oily wastes into solvent,
slop oil, and sludge phases.  The normal composition of the oil wastes
accepted is 80 percent solvent, 15 percent oil, and 5 percent sludge.
There is a 30,000-gallon clay-lined surface impoundment (also 50* x 20'
x 4') for solidifying pickling liquor wastes.  A storage pile holds
up to 8,000 cu. ft.  of solidified pickling wastes; it is surrounded
by a clay-lined surface impoundment that collects drainage and run-off.
                                   9-91

-------
    SA.-1PLE  CLOSURE  COST ESTIMATING WORKSHEETS:  MULTIPLE PROCESS  FACILITY*

A.   Characterizing the Waste
     Worksheet  A  is used to describe each waste  accepted  at  the  facility.
For example,  separate worksheets must be prepared for  each of the following
wastes:  oily  wastes and pickling liquor wastes (the two types of  wastes
processed  at  the storage facility)  and the three  end products of  the  treat-
ment actions  performed (waste organic solvents, slop oil,  and solidified
pickling liquor wastes).   For each  waste product  specified, the following
information is  required:
     1.  Describing the waste:   Describe the origin and general nature
of  the waste.
     2.  Chemical  composition:   Chemical composition should be expressed
in  weight  percents for the various  Tajor components, and in parts  per million
(ppm) for  any trace components.   This information may  be readily  available
to  the operator from the  bill of lading for each  waste shiament.
     3.  Physical  state:   This describes whether  the waste  is a liquid,
solid, or  mixture.   This  information  is used in making estimates  of solid
residues requiring disposal (Worksheet  B).
     £.  Heat of comousticn of ;ne  vaste:   Represents  cne  neat content
(expressed in BTU/lb.  or  BTU/gal.)  of the waste products.  The information
is  used  to determine auxiliary fuel requirements  if the waste is  to be
disposed of through incineration.
     5.  Specific  gravity of the waste:   The specific  gravity of  the waste
at  60 F  referenced to water at 60°F.
     6.  Closure inventory:   The operator must identify  the maximum quan-
tity of each waste  that can  be present  at the  facility in storage  tanks,
drums, or  surface  impoundments,  during  any  point  in the  facility's active
life.  In  the example,  it is assumed  that  there are times  in which the stor-
age capacity  of  this facility is completely utilized.  This would  therefore
represent  the maximum inventory  for developing the closure cost estimate.
In  the sample case,  the  closure  inventory would consist of 65,500  gallons
of waste solvents,  10,000 gallons of  slop oil, 35,000  gallons of oily waste,
30,000 gallons  of  pickling liquor waste and 8,000  cu.  ft. of solidified
pickling wastes.
                                      9-92

-------
 3.   Treating  Inventory
     1.  Waste inventory:  As  noted  in  the waste  characterization  section
 of  this  example,  the sample  facility is  assumed to have  the  following  waste
 products on-site  at the  time of  disposal: 35,500  gallons of  oily waste,
 30,000 gallons of pickling liquor wastes, 65,500  gallons of  recovered  waste
 solvent, 10,000 gallons  of-recovered slop oils, and  8,000 cu.  ft.  of solidi-
 fied pickling  wastes.
     2.  Methods of treatment  or removal:  These  materials will be removed
 of  in a  variety of ways, as indicated below:
         a.  Solvents -  it is  assumed that the facility  can  find other manu-
 facturing/commercial establishments  that will use the waste  solvents (which
 have a BTU content of 135,000  BTU/gal.) as boiler fuel.
         b.  Slop Oils - pumped  out  of storage and hauled to an incinerator.
         c.  Oily Wastes - placed in surface impoundment for separation
 into its component parts.  Solvents  and slop oils recovered  from this  pro-
 cess are disposed of in  the same manner as (a) and (b) above.  Sludges left
 in  the basin are to be dredged,  stabilized and hauled to a landfill.
         d.  Pickling Liquor Wastes  - solidify with  cement and transfer
 the resulting  solid vasie co a lanafiii.
         e.  Solidified  Pickling Liquor Wastes -  transfer to a land-
 fill.
         Since  treatnsnt of inventory categories  (c)  and (d) will generate
 additional waste products in categories  (a), (b)  and (e), these preliminary
 processing phases will be discussed  first.

Disposing of Oily Waste
     3.  Composition of oily wastes:  It is assumed  that the normal compo-
 sition of the oily wastes is 80 percent solvent,  15 percent slop oil,  and
 5 percent sludge.
     4.  Amount of wastes produced after settling:  Using this percentage
mix, settling out the inventory of oily wastes will produce 28,400 gallons
of solvent, 5,325 gallons of slop oil, and 1,775  gallons of sludge.
     5.  Sorbent requirements:   It is assumed that the sludge will be mixed
withan equal volume of sorbent material, with a specific gravity of 1.8.
The specific gravity of the sludge is estimated at 1.2.
     6.  Cost of sorbent:  It is assumed that sorbent material is available
on-site for no cost.
                                   9-93

-------
      7.   Amount of residue generated:   After stabilization,  approximately
 22  tons  of  residue will need to be landfilled.
      8.   Unit cost of disposing of residue:  It is assumed that a land-
 fill  will charge $50/ton to dispose of the stabilized residues.
      9.   Total costs of disposing of residue (Line 7 x Line  8):   Given
 these assumptions, the total cost of disposing  of facility sludge resi-
 dues  will be  $1100.
    10.   Costs of hauling residue:   It is  assumed that the nearest land-
 fill  is  100 miles one-way from the site.   Trucks with a 44,000-lb.
 capacity  can  be rented at a cost of $60 per hour (including  driver);
 the average traveling speed of the truck is 40  mph.   For one round trip,
 the cost  of residue hauling is $300.
    11.   Number of hauls required:   With 22 tons of  waste (line  7), only
 one trip  by a 44,000 Ib.  capacity truck will be required.
    12.   Total cost of hauling residue (Line 10 x Line 11):   Given
 these assumptions,  the total cost of- hauling residue is $300.
    13.   Cost of disposing of oily waste (Line  6 + Line 9 +-Line  12):
 The total cost of disposing of oily waste  is then the sum of sorbent
 material  costs,  costs of disposal,  and costs of hauling for  a total of  S1400,

 Disposing of  Pickling Liquor Waste

    14.   In order to solidify the pickling liquor wastes  in  the closure
 inventory,  the waste must be mixed  with cement.   It  is estimated  that
 one sack  (94  Ibs/sack)  of cement will  solidify  10 gallons  of  waste.
    15.   Amount  of cement required:  To dispose of on-site inventory,
 3,000 sacks of cement (282,000 Ibs.) will  be required.
    16.   Cost  of  cement:   Cement is  estimated to cost  $2.50/sack.
    17.   Total cost of  materials (Line 15  x Line 16):   Given  the above
assumptions,  total material  costs  for solidifying the inventoried
pickling  liquor  waste are 37,500.
    18~.~  Total amount of  residues produced:   Given a  specific gravity
of pickling wastes  of 1.05,  and  the  proportions  of cement  co waste
assumed,  the  total  solid  residues produced  by inventory disposed is
272.4 tons.
                                  9-94

-------
           Liquor = 30,000 gal x 1.05 S.G.  x 8.34 (water weight) =
                    262,800 Ib.
           Cement = 3,000 sacks  x 94 Ibs/sack = 282,000 Ibs.
                    262,000 Ibs  + 282,000 Ibs = 544,800 Ibs =
                    272.4 tons
      19.   Other  on-site residues:   Waste category (e)  represents
 previously solidified  pickling  wastes stored on-site.   It is assumed
 that  there is  8,000 cu.  ft.  of  this material currently in storage,  and
 that  the material weighs approximately 135 Ib/cu. ft (similar to a
 mortar-like cement).   Therefore,  the total weight of this residue
 would be 1,080,000 Ibs.  (540 tons).
      20.   Total  amount of pickling  residue (Line 18  +  Line 19):   Total
 solid residues from treatment of  the pickling wastes are 812.4  tons.
      21.   unit cost  of disposing  of  residue:   As in  Line 8 above, it is
 assumed that a landfill will charge  $50/ton to dispose of such  residues.
      22.   Total  cost of  disposing of residue  (Line 20  x Line 21):   Total
 disposal costs are estimated to be  340,620.
      23.   Costs  of  hauling residues:   The  costs and  method of hauling
 residues are the  same  as  Line 10  above.
      24.   Number  of  hauls required:   Given truck capacity of 44,000 Ibs.
 (22 tons),  it will  take  37 round  trips  to  haul the solidified pickling
 wastes.
     25.   Total  cost of  hauling residues:   Given the above assumptions,
 the total  hauling  costs  will  be $11,100.
     26.  Cost of disposing of pickling liquor waste (Line 17 -H Line  22
+ Line 25):  The total cost of disposing of pickling liquor waste is
 then the sum of costs of  materials,  residue disposal and hauling, for a
 total of $59,220.
     27.  Amount of solvent on-site:   Including  the  solvents  recovered
during the settling of inventoried oily waste,  the total  inventory  of
waste solvents at  the sample  facility are  60,000  gal.  (storage tank)  +
5,500 gal.  (drums) + 28,400 gal. (surface impoundment)  = 93,900 gal.
     28.  Method of disposal:  It is assumed  that the waste  solvents  can
be provided to manufacturers as a boiler fuel.
                                 9-95

-------
      29.   Cost of disposal:  It is assumed that the users of the solvents
 will pay  the costs of pumping and hauling the solvents to their facilities,
 No additional credit is awarded to the owner/operator of the tank facility.

 Treating  Slop Oil

      30.   Amount of slop oil on-site:  Including the slop oils recovered
 during  the settling of inventoried oily waste, the total inventory of
 slop oils are 10,000 gal.  (storage tank)  + 5,325 gal.  (surface impound-
 ment) = 15,325 gal.
      31.   Method of treatment:   It is assumed that the slop  oils will he
 trucked to an incinerator.
      32.   Coat of treatment:  The  estimated  fee  paid to the  incinerator
 for  treating  the wastes  is  $0.60/gallon.
      33.   Total costs  of treatment (Line  30  x Line 32):   Given the  above
 assumptions,  it will cost $9,195 to  treat the slop oil inventory.
      34.   Costs of hauling:   It is assumed that  the nearest  incinerator
 is  50 miles  away,  that the  wastes  will be transported  in a  7,000-gallon
 capacity  truck, at an average speed  of 40 mph.   The hourly  rental  cost
 for  truck and driver is  S60.
      35.   Number of hauls required:   Given trailer capacity,  it will
 require three trips to haul  the slop  oils to  the incinerators.
      36.   Total costs  of hauling:  Given  the  above assumptions, hauling
 costs are estimated at $450.
      37.  Total costs  of treating  slop  oil (Line 33 +  Line 36):  The  total
costs of  treating  slop oil are  then the sum of the  costs  of disposal  and
hauling,  for  a  total of  $9,645.
     38.  Total  costs  of disposing of  inventory  (sum of Lines 6, 9, 12,
17, 22,  25, 29,  33, and  36):  The  total costs of the above activities
are estimated  to be  $70,265.
                                 9-96

-------
 C.   Decontaminating che Facility

 Tank Cleaning

      1.  Cleaning method:  In this example,  the storage tanks are
 steam cleaned.
      2.  Volume:  In the sample case, there are 60,000 gallons of
 solvent storage capacity and 10,000 gallons of oil storage capacity
 to be cleaned, for a total of 70,000 gallons.
      3.  Unit cleaning costs:  For a 2,000 gallon-per-hour steam cleaning
 unit (capable of washing a 16,000-gallon area of storage capacity/hour),
 costs of equipment rental, labor, and operation are equal to $.02/gallon
 of capacity cleaned.
      4.  Total costs of steam cleaning (Line 2 x Line 3):   Total cleaning
 costs for the storage tanks is $1400.
      5.  Type and quantity of residues generated:  Steam cleaning
 generates residues in the form of contaminated washwaters.  The rate of
 residue generation is 1 gallon of waste/8 gallons of tank volume.  In
                                         *
 the example, total residues are 70,000 * 8, or 8750 gal.
      6.  Method of disposal:   It is assumed that the residues are hauled
 to a surface impoundment and evaporated.
      7.  Cost of-disposal:   Impoundment disposal of washwaters is
 estimated to cost $.OS/gallon.
      8.  Total cost of disposal (Line 5 x Line 7):   Costs  of disposing
 of these cleaning residues will be $438.
      9.  Cost of hauling cleaning residues:  For one round trip,  the
.cost of hauling residues is $600.  The cleaning residues will be hauled
 in a 7,000-gallon tank truck, with an average truck speed  of 40 mph.
 The hourly rental cost for truck and driver is $60; the nearest
 available surface impoundment is assumed to be 200  miles away.
     10.   Number of hauls required:   Given the assumption on residue
 generation and truck capacity, two trips will be required, at $600/trip.
     11.   Total costs of hauling:   Total hauling costs  are  $1200.
     12.   Total costs:   The  sum of the  costs of  steam cleaning,  disposal
 and hauling  yields  a total  of $3038.
                                  9-97

-------
Decontaminating  the  Impoundment

     13.  Cleaning method  for  Impoundment  1:   It  is assumed  that  the
concrete-lined impoundment will  be  sandblasted.
     14.  Area of concrete impoundment  to  be cleaned:  The area requiring
sandblasting, based  on  the sample facility description, is equal  to the
base area  (50* x 20', or 100  sq.  ft.)  plus the area of the site
walls (2* x 50'  x 4' +2'  x 20'  x 4',  or 560 sq.  ft.), for a total of
1560 sq. ft.
     15.  Costs  of sandblasting:  A  6  cu.  ft.  capacity compressor will
be used in the sample estimate.  The unit  rents for a $100/week, and
costs $1.75/hour to  operate; labor  costs are estimated at $20/hour.
The unit can clean 40 sq.  ft.  of concrete/hour.   Consequently, sand-
blasting costs are estimated at  $.60/sq. ft.
     16.  Total  costs of sandblasting  (Line 14 x  Line 15):  Sandblasting
costs are estimated  to  be  S936.
     17.  Type and quantity of residue  generated:  The residues will
consist of contaminated sands.   It  was  assumed  that 4000 Ibs. (2  tons)
of sand residue  will be generated.
     18.  Unit costs of disposal:   The  sands will be landfilled at a
disposal cost of $507ton.
     19.  Total  costs of disposal (Line 17 x Line 18):  Total disposal
costs will be equal  to  S100.
     20.  Cleaning method  for  Impoundment  2:  All contaminated clays
from the clay-lined  impoundment will-be removed and hauled to a landfill.
     21.  Area of clay  impoundment  to be decontaminated:  Since the dimen-
sions of this impoundment  are  the same  as  those of the concrete-lined
impoundment discussed above, the surface area  to be contaminated is the
same as that estimated  in  Line 14 of this  worksheet, or 1560 sq.  ft.
     22.  Amount of  clay removed:   It  is assumed  that the clay in the
pickling liquor  impoundment has been contaminated to a depth of one
foot.  Therefore, 1560  cu. ft. of clay, or 57.8 cu. yds.,  must be
removed.
                                 9-98

-------
      23.   Unit  cost  of  removing  clay:   Clay  removal  will  be performed
 with  a  backhoe.   Including  costs of  equipment  rental and  labor,  the
 costs of  removing  the clay  is  estimated to be  $1.60/cu. yd.
      24.   Total  costs of  removing clay  (Line 22  x Line  23):   Given the
 above assumptions, the  costs of  removing the soil are S92.
      25.   Disposing  of  contaminated  clays:   Clays will  be hauled  to a
 landfill  for disposal.  The costs of disposal  are estimated to be
 $30/cu. yd.
      26.   Total  costs of  disposal (Line 22 x Line 25):  The total costs
 of disposal are  S1734.

 Removing  Soil and >Iiscellaneous  Activities

      27.   Removing contaminated  soils:   Because  of spills and other
 accidental releases, certain areas of the waste  disposal  facility,  such
 as diked-in areas around  storage  tanks will  be contaminated.  It  is
 assumed for the  sample  facility  that 2.5 percent of  the total site area
 is contaminated.
           Contaminated  area =•  2  acres x  4840 sq. yd./acre x  .025
             rate of contamination - 242 sq.  yd.
      28.   Amount of  soil  removed:  The depth of  soil  removal required
 to remove  all hazardous contaminants is  assumed  to be 1 foot.  Thus,
 the total  amount of  soil  removed  - 242 sq. yd.  x .33  yd. = 80.7 cu.  yds.
      29.   Unit cost of  removing soil:  As in Line 23, removing soil  can
be accomplished at a cost of $1.60/cu.  yd.
      30.   Total cost of removing soil (Line 28  x Line 29):  Total cost
of removing soil is $129.
      31.  Disposing of contaminated soils:  Contaminated soils are also
hauled to  a landfill, where they may be disposed at a cost of S30/
cu.  yd.
      32.  Total costs of disposal (Line 28 x  Line 31):  Given the above
assumptions,  disposing of soils will cost $2421.
                                9-99

-------
      33.   Hauling costs for decontamination wastes:   The wastes  described
 in  Lines  17,  22,  and 28 of this Worksheet will be hauled to the  landfill
 in  a  44,000-lb.  truck.  The landfill is assumed to be 100 miles  away;  the
 hourly  cost of  truck and driver is $60 and the average trip speed  is
 40  mph.   Adequate dividers will be supplied so that  mixed loads  can be
 carried.
      34.   Number  of trips required:   If it is assumed that a cu. yd. of
 earth weighs  approximately 2000 Ibs.,  the hauling of these waste residues
^will  require  seven trips.
      35.   Costs of hauling decontamination residues  (Line 33 x Line 34):
 At  $300 per round trip, total hauling  costs would be $2100.
      36.   Flush pumps and transfer lines:  All pumps and piping used to
 transfer  hazardous waste are flushed to remove contaminants. This
 process is  assumed to cost $2000.
      37.   Decontaminate equipment:   All materials handling equipment
 used  on-site  must be decontaminated.  This is assumed to cost $500.
      38.   Decontaminate containers:   In the example, it  is assumed that
 all drums  kept on-site will be crushed and buried in a landfill, at a
 total cost  of $1000.
      39.   Total costs of decontaminating facility (sum of Lines 4, 8,
 11, 16, 19,  24, 26,  30, 32, 35-38):  Total costs  of  decontaminating the
 facility,  based on the above assumptions, are estimated  to be $14,070.

 D.    Professional Certification

      1.    Number  of  person-hours required for inspections:   It is assumed
 that  16 hours are required for periodically inspecting all aspects of
 closing the  tanks and impoundments.
      2.    Cost per person-hour:  In  this case,  assume that a registered
 independent professional engineer  may  be hired  at a  cost of  $75 per hour.
      3.    Total costs of independent professional engineer's  time (Line  1
 x Line 2) :  This  yields a total cost of $1200 for the independent pro-
 fessional  engineer.
                                   9-100

-------
     4.   Number of  technical hours required  for  administrative  duties:
Assume  that 8 hours  are  required from the owner's or operator's  staff  for
administrative duties connected with employing an independent  professional
engineer.
     5.   Person-hour costs for technical administrative duties:   It  is
assumed that the total fully-loaded costs for the owner's or operator's
staff are $30 per hour.
     6.   Total administrative costs for technical labor (Line 4 x Line  5):
Given the above assumptions, the total administrative costs for  technical
labor are $240.
     7.   Number of  clerical hours required for administrative duties:
Assume that 5 hours  of clerical time are required for the necessary
typing and certifications.
     8.   Person-hour costs for clerical administrative duties:  Fully-
loaded costs of clerical  time are assumed to be $8 per hour.
     9.   Total administrative costs for clerical labor (Line  7 x  Line 8):
Given the above assumptions, total clerical costs are $40.
    10.   Total administrative costs (Line 6 + Line 9):  Summing technical
and clerical labor,  the administrative costs are $280.
    11.   Total certification costs (Line 3 + Line 10):  The total costs
for certification,  including engineer's fees and administrative costs, are
$1480.

E-   Total Costs Including Administration and Contingencies

     Items 1 through 3 give the costs of all activities on each of the
preceding worksheets.  Line 4 is the total of Lines 1 through  3,  $85,815.
     5.    Contingencies:   A general provision for contingencies of 15
percent of Line 4 has been included.
     6.    Administrative  and supervisory cost:  For administrative tasks,
including taxes, insurance, and administration and supervision not included
elsewhere, a total  of 15  percent of total costs  from Line 4 is used.
     7.    Total costs of  closure (Line 4 + Line  5 + Line 6):   The
total costs  for closing the tanks, and  impoundments are  estimated  for
the sample case to  be $111,559.

                                 9-101

-------
                     MULTIPLE  PROCESS  FACILITY
          WORKSHEET  A - CHARACTERIZING  THE WASTE  (#1)
Description of the waste
    Organic solvent
Chemical composition
    (Not given)
Physical state of the waste
    Liquid
Heat of combustion of the waste
    18,000 BTU/lb.(135,000 BTU/gal.)
Specific gravity of the waste
    .9
Maximum inventory of the waste
    60,000 gallons bulk storage
     5,500 gallons in drums
ID numbers for areas holding these wastes
    Tanks T-l to T-4
                                9-102

-------
                    MULTIPLE PROCESS FACILITY
          WORKSHEET A  - CHARACTERIZING  THE  WASTE  (#2)
Description of Che waste
    Slop oil
Chemical composition
    (Not given)
Physical state of the waste
    Liquid
Heat of combustion of the waste
    16,000 BTU/lb (126,720 BTU/gal.)
Specific gravity of the waste
    .95
Maximum inventory of the waste
    10,000 gallons bulk storage
ID numbers for areas holding these wastes
    Tank T-5
                              9-103

-------
                  MULTIPLE  PROCESS  FACILITY
          WORKSHEET A - CHARACTERIZING THE WASTE (#3)
Description of the waste
    Oily wastes
Chenical composition
    (Not given)
Physical state of the waste
    Mixture (95% liquids, 57, sludge)
Heat of combustion of the waste
    (Not given)
Specific gravity of the waste
    (Not given)         ,
Maximum inventory of the waste
    30,000 gallons in holding basin
     5,500 gallons in drums
ID numbers for areas holding these wastes
    Impoundment S-l
                               9-104

-------
                       MULTIPLE PROCESS FACILITY
                WORKSHEET A -  CHARACTERIZING THE  WASTE  (#4)
1.   Description of  the waste
         Pickling liquor waste
2.   Chemical composition
         (Not given)
3.   Physical state of the waste
         Liquid
4.   Heat of combustion of the waste
         0
5.   Specific gravity of the waste
         1.05
6.   Maximum inventory of the waste
         30,000 gallons in holding basin
7.   ID numbers for areas holding these wastes
         Impoundment B-l
                                     9-105

-------
                        MULTIPLE  PROCESS  FACILITY
               WORKSHEET A  - CHARACTERIZING THE WASTE (#5)
1.   Description of the waste
         Solidified pickling liquor wastes
2.   Chemical composition
         (Not given)
3.   Physical state of the waste
         Solid
4.   Heat of combustion of the waste
         (Not given)
5.   Specific gravity of the waste
         2.2
6.   Maximum inventory of the waste
         8,000 cu. ft. in storage pile
7.   ID numbers for areas holding these wastes
         None
                                    9-106

-------
                         MULTIPLE PROCESS FACILITY
                    WORKSHEET 3 - TREATING THE INVENTORY
       Waste  inventory  at  time of closure
           Waste  solvents
           Slop oil
           Oily wastes
           Pickling  liquor  wastes
           Solidifed pickling  wastes
      Methods of treatment or removal
           Waste  solvents
           Slop oil
           Oily wastes
          Pickling liquor wastes
          Solidified pickling wastes
 Disposing of Oily Waste
                                      65,500 gal.
                                      10,000 gal.
                                      35,500 gal.
                                      30,000 gal.
                                       8,000 cu.  ft.

                                      Reuse  as  boiler fuel
                                      Incinerate
                                      Separate; recover  solvents,
                                      incinerate slop oils,  landfill
                                      sludges
                                      Solidify, landfill
                                      Landfill
 7.
 8.
 9.

10.
11.
12.
13.
Composition of waste
    80% solvent, 15% slop oil, 57, sludge
Amount of waste produced
    28,400 gal. solvent, 5,325 gal. slop oil,
Amount of sorbent used in sludge treatment
Cost of sorbent used
a.  Cost of materials
Amount of residue generated
Unit cost of disposing or removing residue
Total cost of disposing or removing residue
   (Line 7 x Line 8)
Costs of hauling residue
Number of trips required
Total cost of hauling residue (Line 7  x  Line 10)
Costs of disposing or removing oily waste
   (Line 6 + Line 9 + Line 11)
1,775 gal. sludge
1:1 ratio with oils
0
0
22 tons
$50/ton
$1100

5300/trip
1
$300
S1400
                                   9-107

-------
WORKSHEET  B  (continued)
Treating or  Removing  Pickling  Liquor  Waste
14.  Amount  of cement required for  solidification
15.  Total amount  of  cement  required
     Cost of cement
     Cost of materials (Line 15 x Line  16)
     Amount  of residues  produced by treating  inventory
     Amount  of other  residues  already on-site
16
17
18
19
20
     Total amount of  pickling  residues
        (Line 18 + Line  19)
21.  Unit cost of disposing or removing residue
22.  Total cost of disposing or removing residue
        (Line 20 x Line  21)
23.  Costs of hauling residues
24.  Number of trips  required
25.  Total costs of hauling (Line 23 x Line  24)
26.  Costs of disposing  or removing pickling liquor
        waste (Line 17 + Line  22 + Line 25)
Removing Waste Solvent
27.  Amount of waste  solvent
     a.
     b.
28.
         Amount of solvent in inventory
         Amount of solvent obtained from oily
            waste inventory treatment
     Method of removal
29.  Cost of removal
Treating Slop Oil
30.  Amount of slop oil on-site
     a.  Amount in inventory
31.
32.
     b.   Amount generated from disposing or
            treating oil waste inventory
     Method of  treatment
     Unit cost  of treatment
33.  Total cost of treatment (Line 30 x Line 32)
34.  Unit costs of hauling residues
1 sack/10 gal.
3000 sacks
$2.50/sack
$7,500
272.4 tons
540 tons
812.4 tons

$50/ton
$40,620

$300/trip
37
$11,100
$59,220
93,900 gal.
65,500 gal.
28,400 gal.
Recovery and reuse
as boiler fuel
0
15,325 gal.
10,000 gal.
5,325 gal.

Incinerate
$0.60/gal.
$9,195
$150/trip
                                  9-108

-------
WORKSHEET B (continued)


35.  Number of trips required                    -         3

36.  Total costs of hauling (Line 34 x Line 35)           $450

37.  Costs of treating slop oil                           $9,645

38.  Total costs of treating inventory                    $70,265
        (Sum of Lines 6, 9, 12, 17, 22, 25, 29,
         33 and 36)
                                  9-109

-------
                         MULTIPLE  PROCESS  FACILITY
                 WORKSHEET C - DECONTAMINATING THE FACILITY
  Tank Cleaning
  1.    Cleaning method used  .
       Capacity to be cleaned
       Unit cleaning coses
       Total costs of steam cleaning
       (Line 2 x Line 3)
       Quantity and type of residues generated
  2.
  3.
  4.

  5.
  6.    Method of disposal
  7.    Cost  of disposal
  8.    Total cost of disposal
       (Line 5 x Line 7)
  9.    Cost  of hauling residues
10.    Number of trips required
II.    Total costs of hauling (Line 9  x Line 10)
12.    Total costs of tank cleaning
Decontaminating the Impoundment
13,
14,
15.    Unit  costs of sandblasting
16.    Total costs of sandblasting
       (Line 14  x Line 15)
       Quantity  of .residues  generated
       Unit  costs  of  disposing  of residue
      Cleaning method used  -  Surface  Impound-
      Area to be cleaned
17
18
19
20,

21.
22.
23.
24.
Total costs of disposing of residue
(Line 17 x Line  18)
Cleaning method  used -  Surface  Impound-
                        ment 2
Area to be cleaned
Amount of clay removed
Unit cost of removing clay
Total cost of removing  clay
(Line 22 x Line  23)
 Steam cleaning
 70,000 gallons
 5.02/gallon

 $1,400
 8,750  gallons of  contaminated
 washwaters
 Surface  impoundment
 $.05/gallon

 $438
 $600/trip
 2
 $1200
 $3038

 Sandblasting
 1560 sq. ft.
 $.60/sq. ft.

 $936
 2 tons of contaminated sand
 $50/ton
 S100

Clay removal  and landfill
  disposal
1560 sq. fc.
57.8 cu. yds.
31.60/cu. yd.
$92
                                   9-110

-------
 WORKSHEET C (continued)
 25.  Unit  cost of disposing  of  residue  (clay)
 26.  Total costs of  disposal
      (Line 22 x Line 25)
 Soil Removal and Miscellaneous  Site  Cleanup
 27.  Soil  area contaminated

 28.
 29.
 30.

 31.

 32.

 33.
35.
36.

37.
38.
39.
Amount  of  soil removed
Unit cost  of removing soil
Total cost of removing soil
(Line 28 x Line 29)
Unit costs of contaminated soil
disposal
Total costs of disposing of soil
(Line 28 x Line 31)
Hauling costs for decontamination
wastes  (including impoundment cleanup)
Number of  trips required
Total costs of hauling
Costs of flushing pump and transfer
lines
Decontaminate equipment
Decontaminate containers
Total costs of decontaminating the
facility
                                           530/cu.  yd.
                                           $1734
2.5% of site area
(242 sq. yd.)
80.7 cu. yd.
$1.60/cu. yd.
$129

$30/cu. yd.

$2421

S300/trip

7
S2100
$2000

$500
$1000
314,070
                                   9-111

-------
                        MULTIPLE PROCESS  FACILITY
                  WORKSHEET  D -  PROFESSIONAL  CERTIFICATION
 1.   Number of person hours  required  for  inspections
 2.   Cost per person-hour: engineer
 3.   Total costs of independent professional engineer's
      time (Line 1 x Line 2)
 4.   Number of technical hours required for
      administration
 5.   Cost per person-hour: technical
 6.   Total administrative costs for technical
      labor (Line 4 x Line 5)
 7.   Number of clerical hours required for
      administration
 8.   Costs per person-hour:  clerical
 9.   Total administrative costs for clerical labor
      (Line 7 x Line 8)
10.   Total administrative costs (Line 6 - Line 9)
11.   local certification costs >,Line 3 T Line 10)
16 hours
S75
$1200

8 hours

$30
$240

5 hours

$8
$40
                                 9-112

-------
                       MULTIPLE PROCESS FACILITY
                  WORKSHEET E  - TOTAL  COSTS INCLUDING
                   ADMINISTRATION AND  CONTINGENCIES
1.   Costs of disposing of- inventory                       $  70,265
     (From Worksheet B)
2.   Costs of decontaminating the facility (From           $  14,070
     Worksheet C)
3.   Costs of professional certification (From             $   1,480
     Worksheet D)
4.   Subtotal                                              $  85,815
5.   Contingencies                                         $  12,872
6.   Administration                                        $  12,872
7.   Total closure costs                                   $111,559
     (Line 4 + Line 5 + Line 6)
                                  9-113

-------
9.7                EXAMPLE - POST-CLOSURE COST ESTIMATES

     A  large  flat  landfill of  200 acres  has been closed  in  accordance
with the EPA  interim status regulations.  This landfill  consists
of rather closely  spaced narrow trenches that are protected by  clay
covers  and  cover vegetation.  The facility soil is a  soil which is
mostly  clay in  content.   All of the  facility is planted  with  grass to
resist  erosion.
     The post-closure operations  at  this facility have been planned to
carry out the requirements of  the interim status  regulations.   The ac-
tivities planned are as  follows:
     •  periodically inspecting the  facility
     •  mowing
     •  routine erosion  repairs
     •  replacing  security fences  (as  needed)
     •  fertilizing
     •  leachate pumping and disposal
     •  ground-water monitoring
     •  monitoring well  replacement  (as  needed)
     •  repair of  severe erosion  caused  by storms
     •  post-closure  administrative  services
These activities are  costed in  the attached annotated worksheets.   All of
these activities are  costed based on the assumption that the facility is
completely  closed  and that  no  "free" assistance is available from an
active portion of  the facility.  This means  that  some of the supporting
facilities  such as office space  that are available during closure are
not automatically  available during the post-closure period.
                                   9-114

-------
               SAMPLE POST-CLOSURE COST ESTIMATING WORKSHEETS

 A.    Periodically Inspecting the Facility
      1.   Number of technical management person-hours required for each
 inspection:   Each inspection at this closed hazardous waste facility
 will be  conducted by two people in a rented vehicle.  We are of the
 opinion  that  two people are needed to conduct the inspection of the
 large closed  waste disposal area (200 acres)  and that an extra measure
 of  safety is  afforded by having two inspectors.   Each inspection takes
 a full day of work by two technically trained managers.
      2.   Annual number of routine inspections:   Six routine inspections
 will be  conducted during each year of the post-closure period.   These
 will be  conducted on a bimonthly  basis.
      3.   Person-hour costs  for technical  management labor:   The fully-
 loaded labor  rate for this  technically  trained labor is  $30 per hour.
      4.   Technical labor costs  for annual routine inspections  (Line 1 x
 Line 2 x  Line  3):   The technical  labor  cost  for  these annual routine
 inspections is  the  product  of  the person-hours required  for each  inspec-
 tion,  the  number  of  inspections planned,  ar.d  che  technical  labor  rate.
      5.   Annual  numoer of engineer-supported  inspections:   In addition
 to  the routine  inspections  described  above,  two annual engineer-supported
 inspections are  planned.  These inspections use a team of professional
 engineers  and one  of  our technical managers.  The engineer  is a state-
 certified  professional engineer from  an independent  firm  that is  contracted
 to supply  professional services to the-hazardous  waste disposal facility.
      6.  Number of  independent state-certified engineering  hours  for each
 engineer-supported  inspection:  For each  inspection,  eight  hours  of  the
 engineer's time is  required.
      7.  Number of  technical management hours for each engineer-supported
 inspection:  For each  inspection, eight hours of  technical  labor  is
 required.  This requirement is in addition to the engineering labor  that
 is required.
     8.  Person-hour cost for a professional engineer:  The quoted cost
of engineering services is $75 per hour.  These services will be obtained
 from an independent engineering firm.

                                   9-115

-------
       9.  Engineering labor coses for che engineer-supported inspections
 (Line 5 x Line 6 x Line 8):  The cost of the engineering labor is the
 product of the number of engineer-supported inspections, the number of
 engineering hours needed for each inspection, and the person-hour cost
 of  engineering services.
      10.  Technical labor costs for the engineer-supported inspections
 (Line 3 x Line 5 x Line 7) :  The technical managerial labor costs for
 the engineer-supported inspections is the product of the labor rate for
 technical labor, the number of inspections required, and the technical
                                                          •
 labor hours required for each inspection.
      11.  Labor costs for the engineer-supported inspections (Line 9 +
 Line  10) :   The total labor costs for the engineer-supported inspections
 is  the sum of  the engineering labor and technical labor costs.
      12.  Cost  of renting the truck for each inspection:   A rented pick-
 up  truck  is used for transporting the inspectors  throughout the hazardous
waste  disposal facility.   The quoted rate for the truck is  $25  per day and
 $.14  per  mile.   In addition,  the renter must supply  gasoline.   The mileage
 for each  inspection is  50 miles including the trips  between the facility
and  the rental agency.   This  results in a total cost for the truck of
$36 per day ($25 rental,  $7  mileage,  and $4 gasoline).   The gasoline   '
value  is  estimated based  on  a truck mileage of  15 mpg and a gasoline
price  of  SI.20 per gallon.
      13.  Annual cost of  renting the truck for inspections (Line 2 - Line
5 x Line  12) :   The total  annual truck rental cost is the product  of  the
 total  number of inspections  needed  (both routine  and engineer-supported)
and the daily  truck rental cost.
     14. Total  annual inspection  cost  (Line 4 -!• Line 11  + Line  13):  The
total  cost  of  conducting  this post-closure  inspection program is  the sum
of the annual  total  labor  costs  for  the  routine inspections, the  annual
labor  costs for  the  engineer-supported  inspections,  and  the  annual rental
costs  for  the  truck.
                                   9-116

-------
 B-    Routine  Monicoring  and Maintenance Activities
 Mowing Operations
      1.   Facility  acreage:   The waste disposal area of this  hazardous
 waste facility  is  200  acres.  This  area includes  the cover of the waste
 disposal  trenches  and  land  close  to the trenches.
      2.   Mowing labor:   The waste disposal  area is to be mowed periodically
 to promote  the  growth  of cover vegetation and  to  inhibit the growth of
 large deep-rooted  vegetation such as  young  trees.   This  mowing is to be
 carried out on  a contract basis by  a  mowing service.   The quoted  labor
 rate  for  this service  is $14.28 per acre mowed.
     3.   Mowing equipment:   The quoted  rate for the mowing equipment is
 $5.37 per acre  mowed.  This  rate includes fuel and all equipment  costs.
     4.   Unit mowing cost (Line 2 + Line 3):   Adding the labor rate and
 the equipment rate yields the total contracted mowing rate (unit  cost)  for
each acre mowed.   Cheaper agricultural  methods cannot be used  because of
 the impact of the heavier equipment on.the  cover.
     5.  Annual frequency of mowing:  Mowing of the waste  disposal  area
is required once a year  during the  post-closure period.  This  frequency
of mowing will encourage the growth of  cover vegetation  and will  suppress
the growth of trees and  other deep-rooted vegetation.
     6.   Annual cost of mowing (Line  1 x Line  4 x  Line 5):  The annual
cost of mowing is the product of the  facility  acreage, the unit mowing
cost,  and the annual frequency of mowing.

Routine Erosion Damage Repair
     7.   Annual routine erosion rate:  The annual  routine  loss of soil
from the facility is computed using the Universal  Soil Loss Equation
(USLE).
             A = RKLSCP
         A = Average soil loss,  tons/acre
         R = Rainfall and run-off  erosivity  index
         K = Soil erodibility factor
                               »
         L = Slope  - length  factor
         S = Slope  - steepness  factor
         C = Cover/management factor (type of vegetative  cover)
                                  9-117

-------
          P = Practice factor (terracing, contour plowing)
 This equation computed for the sample facility's location yields an
 annual soil loss of 0.12 tons per acre.  With a soil density of approxi-
 mately 100 Ibs. per cu. ft., 0.089 cu. yds. are lost from each acre.   In
 our subsequent computations, we make the very conservative assumption
 that all of the lost soil will have to be replaced and reseeded.
      8.   Total annual routine erosive loss (Line 1 x Line 7):   The total
 annual routine soil loss is the product of the acreage times the annual
 soil loss per acre.
      9.   Unit cost for land excavation of soil:  Replacement soil will be
 obtained on-site at the facility.   Since the amount of soil required  is
 very small compared to the daily capacity of earth-moving machinery,
 hand labor will be used to excavate the soil.   The rate stated here is
 a  fully-loaded rate for union labor working for an independent contractor.
 This unit cost is based on contractor quotes.
     10.   Unit cost for on-site  transportation  of soil:  The excavated
 soil is  transported by truck on-site to the location where the erosion
 repair is to  be made.   This service will be provided by an independent
 contractor.
     11.   Unit cost for compacting  the soil by  hand:   The unit  cost of
 hand compacting the new soil as a  repair for erosion damage is estimated
 to  be the same as for hand excavation of the soil.   This service will
 be  provided by an independent contractor.
     12.   Unit cost of  seeding:   The cost of seeding  is a function of
 the  surface area of the  new bare soil.   In our estimates,  we assume
 that  a small  gully (or gullies)  have formed.   The  ratio  of surface area
 to  soil  volume is  small.   This  new soil is seeded with the same  type  of
 grass  as  is used for  the  original  cover vegetation.
     13.   Aggregate unit  cost of  repairing  routine soil erosion damage
 (Line  9 + Line 10  +• Line  11 + Line 12):  The aggregate unit cost  of
 repairing the routine  soil  erosion is  the  sum  of  the  excavation  unit
 cose,  the on-site  trucking,  the  hand compacting of  the soil, and  hand
 seeding of  the bare soil.
     14.   Total annual  cost  for  repairing erosive damage  of a routine
nature (Line  8 x Line  13) :   The  total  annual cost of  such  routine  erosive

                                    9-118

-------
repairs under average  rainfall conditions  is  the  product  of  the amount
of soil lost and  the unit aggregate  cost  for  erosion  damage  repairs.
     15. Adjustment factor  to account  for  unusually wet seasons:   The
above cost  (Line  14) is computed  for average  rainfall conditions  at  the
facility location.  A  safety factor  of  2  is applied which  is  the  equiva-
lent of increasing the rainfall and  runoff erosivity  index (within the
Universal Soil Loss Equation) from 150  to  300.  This  changes  the  facility's
rainfall from its actual mid-Atlantic  level to  the high southern  levels.
This conservative assumption is required  to allow for the  annual  variation
in routine  rainfall-caused  erosion.
     16. Adjusted annual cost for repairing routine erosion damage (Line
14 x Line 15):   The adjusted annual cost  for erosion repair  of a routine
nature is the product  of the average annual cost  and  the adjustment  fac-
tor.

Replacing the Fence
     17. Frequency of  replacing the  fence:  Security  at the facility  is
provided by a 6-ft. high chain link  fence  that  has been established along
                                                                         *
the encore  perimeter of the facility (11,808  ft.  in length).  This fence
is made of  galvanized  #9 wire.  Operating experience  at this  hazardous
waste facility indicates that the fence must  be replaced every  15  years.
Thus, during the anticipated 30-year duration of-the  closure  period,  the
fence will have to be  replaced once.
     18. Facility perimeter:  The length of the security fence  is  the
length of che facility oerimeter (11,808 ft.).
     19. Unit cost of replacing the  fence:  Quotes were obtained  from
fencing suppliers for a new fence of equal specifications.  The value
given here is a unit cost per linear foot for an installed fence.
     20. Total cost of fence replacement (Line  18 x Line 19):  The cost
of replacing the perimeter security  fence is  the product of the perimeter
footage and the unit cost of the installed fencing.
     21. Pro-rated annual cost of fence replacement:  The  total cost  of
replacing the security fence is pro-rated to each year by dividing the
total cost  (Line 20) by the number of years in  the post-closure period
(30 years).

                                   9-119

-------
 Fertilizing
      22.  Unit cost of fertilizing:  The hazardous waste disposal facility
 has  relatively poor soil resulting in the experienced necessity of annual
 fertilizer applications until che vegetation has become established,  & periodic
 applications thereafter.  Type 10/6/4 fertilizer costing $0.12 per Ib.  (in
 50-lb.  bags) is applied at'a rate of 500 Ibs. per acre.  This corresponds
 to a nitrogen application rate of 50 Ibs. per acre.   The unit cost of ferti-
 lization  is the sume of the labor, materials and equipment costs.
          Labor                      $69.10/acre
          Materials                  $60.00/acre
          Equipment                  $ 5 .00/acre
 Previous  experience at this facility has shown that  this application
 rate for  fertilizer is satisfactory to maintain the  vegetation.
      23.   Number of applications of fertilizer for the first  3 years:   One
 application of fertilizer is needed each year for a  total of  3 applications.
      24.   Number of applications of fertilizer for remaining  years of  post-
 closure  (Years 4 through 30):   One application of fertilizer  is  needed  every
 5 years,  or a total of 5 applications for the remainder of post-closure.
      25.   Total costs  of fertilizing for the first 3  years  of  post-
closure (Line 1 x Line 22 x Line 23):   The cost of fertilizing for the
first 3 years is  the product of  the acreage fertilized,  the unit cost of
fertilization and the  frequency  of application during  the  first  3  years.
The  costs  of  fertilizing for the first  3  years are then  $80,460.
      26. Total costs of  fertilization  for years 4  through  30 of  post-
closure (Line 1 x Line 22 x Line 24):   The cost of fertilizing is  the
product of  the acreage fertilized,  the  unit  cost of fertilizing, and
the  frequency of  application during the years  4 through  30.  The costs
for  fertilizing for  the  remainder of post-closure  is  then 3134,100.
     27. Total costs of  fertilizing during post-closure  (Line  25 + Line
26):   The  total  fertilization costs are  the  sum of the costs for ferti-
lizing during the first  3 years  and the  5  applications required during
the  remainder  of  post-closure.   The  total  costs  for fertilizing  for
the  entire 30-year period  are then  $214,560.
     28. Total  annual  costs  of fertilizing  (Line 27 4- 30):  The
total costs  for fertilizing  for  the 30-year  period is divided by the

                                   9-120

-------
 30
years of the post-closure period to yield an annual cost of $7152.
 Ground-Water Monitoring Well Replacement^
      29.  Unit cost for well replacement:  The lowest observed depth of
 the water table has been closer to the surface than 50 ft. throughout the
 active operation of the facility.   A replacement well to a depth of
 aprpoximately 50 ft.  will cost $425 when installed by an independent
 contractor ($8.50 per vertical linear ft.).   This quoted price includes
 a suitable casing.
      30.  Number of  wells needing replacement:  The monitoring wells have
 a relatively long useful lifetime  as do residential wells.  It is antici-
 pated that two  wells  will have to  be replaced during the post-closure
 period.
      31.  Total  cost of  monitoring  well replacement (Line 29  x Line 30):
 The total post-closure  period cost of well replacement is the unit cost
 of  each well multiplied by the number of wells  required in the post-
 closure period.

 Leachate  Pumping  and  Disposal
      32.  Frequency  of removing the leachate:  Leachate is removed perio-
 dically from the  hazardous waste facility risers  by  means of  a vacuum truck.
 Every month,  the  truck  circulates  to  each riser  pumping out  the collected
 leachate.  This service is performed  by an independent contractor.
      33.  Average  total  monthly leachate withdrawal:   Since the facility's
 cover system is quite effective  in reducing infiltration,  only 2000  gals.
 of  leachate  (average  value) will have  to be removed  each  month.   This
 leachate  is  removed to  an  off-site disposal area.
      34.  Unit cost of removing  the  leachate to an  active  off-site disposal
 area:  The unit cost  of  removing the  leachate includes  driving the vacuum
 truck to  each riser at  the facility and  removing  the  leachate  and deliver-
 ing  the truckload of  leachate  to the off-site disposal  area.   A relatively
high  per-gallon removal  cost  is quoted because of  the  necessity  of collec-
 ting  a small amount of  leachate from each of  the widely dispersed risers
 throughout the large  facility.  This cost includes transportation to  the
TSDF.
                                   9-121

-------
     35. Total  annual cost of  removing  the leachate  (Line  32  x Line  33 x
Line 34 x  12):   The  annual leachace  removal cost  is  the  product of the
monthly leachate volume removed,  the number of  months  in a year, and  the
unit cost  per gallon removed.
     36. Unit cost  for removing  leachates  to an off-site TSDF:  The unit
cost for off-site disposal of  the leachate material  is $.05/gal.  This
material is disposed of in a surface impoundment.
     37. Annual costs for  off-site disposal (Line  32 x Line 33 x Line 36
x 12) :  The cost of  disposing  of  the material in  the off-site surface
impoundment is  the product of  the amount of leachate disposed and the
unit cost  for the disposal.
     38. Total  annual cost for removing and disposing of leachates (Line
35 + Line  37) :   The  total  cost for leachate removal and  disposal is the
sum of the removal' cost and the disposal cost.

Ground-Water Monitoring

     39. Number  of wells monitored:   This  hazardous waste  facility has
12 ground^water  monitoring wells.  One well is  upgradient  and 11 wells
are downgradient from the  disposal area.
     40. Number  of samples taken  per well  (annual):  Two "cycles" of
ground-water sampling will be  conducted annually.  One ground-water
quality analysis  and  two ground-water contamination analyses are to be
carried out.  One sample may be used for both the  ground-water quality
and ground-water contamination analyses.   Therefore, two samples are
taken from each  well  annually.
     41. Total number of samples  (annual)  (Line 39 x Line  40):  The total
number of ground-water samples taken annually is the product of the
number of monitoring  wells and the number  of  samples taken annually from
each well.
     42. Number  of hours for collecting the sample (per  sample):   Each
sample requires  two hours  of collection time.  The well must be pumped
dry and allowed  to refill.  Then  a sample  is  taken.  The facility ex-
perience is that approximately two hours are  required for each well
sampling (including some time  for  moving about  the fields).
                                   9-122

-------
     43.  Total number of hours for collecting the sample (Line 41 x
Line 42):  Annually, 24 samples will have to be collected, requiring
48 hours of labor.
     44.  Total number of hours for preparing and delivering the sample:
The total number of hours required for packaging and delivering the
samples is six hours per year.
     45.  Total sample handling hours (Line 43 + Line 44):  The annual
total time for collecting and delivering the ground-water samples is
54 hours.
     46.  Person-hour costs for handling ground-water samples:  The
person-hour costs for handling the samples is based on the facility ex-
perience of $15 per hour fully-loaded.
     47.  Total sample handling costs (Line 45 x Line 46):  The total
labor cost for handling the samples is the product of the hours required
and the unit labor costs.
     48.  Unit cost of ground-water quality analysis:  The unit cost
of an analysis for the following parameters is $77 per analysis:
          Chloride                  $ 6/sample
          Iron                      $12/sample
          Manganese                 $12/sample
          Phenols                   $25/sample
          Sodium                    $12/sample
          Sulfate                   $10/sample
     49.  Unit cost of ground-water contamination analysis:   The unit
cost of an analysis for the following parameters is $108 per analysis:
          pH                        $ 4/sample
          Specific Conductance      $ 4/sample
          Total Organic Carbon      $25/sample
          Total Organic Halogen     $75/sample
     50.  Total cost of ground-water quality analysis (annual)  (Line  39
x Line 48):   The annual cost for analysis of water quality is the product
of the number of wells and the unit cost of the analysis.
     51.  Total cost for ground-water contamination analysis (annual)
(Line 41 x Line 49):  The annual cost for analysis for ground-water
contamination is the product of the number of sample sets to be analyzed
and the unit cost of the analysis.
                                  9-123

-------
     52.  Total annual  ground-water nonitoring coses  (Line 49 + Line 50 +
Line 51) :  The total annual cost  for ground-water analysis is the sum of
the ground-water quality analysis cost,  Che ground-water contamination
analysis cost, and the  sample handling cost.

Routine Maintenance Summation

     53-60.  The annual cost for each of the routine maintenance and
monitoring operations are added together to yield the total cost (annual).
This cost does not include administrative costs which are computed on a
separate worksheet (Line 53 + Line 54 + Line 55 + Line 56 + Line 57 +
Line 58 + Line 59).
                                    9-124

-------
 c-    Erosion Damage Contingency Scenario
      1.  Percentage of vegetation removed:  Some unplanned events that
 will create additional demands for care will occur during the duration of
 the post-closure period.   This worksheet computes the additional cost
 that would result from such an unplanned event that removes 30% of the
 vegetative cover from the hazardous waste facility.  After the vegetation
 is  removed, the soil remains bare for one month exposed to normal rainfall.
 Resulting erosive damage  is repaired and the bare acreage is revegetated.
 The one month lapse between the damaging event and the revegetation allows
 for delays in the discovery of the damage and the time required for the
 revegetation steps.
      2.   Facility acreage:   The entire facility is impacted by the event.
      3.   Acreage reduced  to bare soil (Line 1 x Line 2):   The acreage
 stripped of vegetation is  the product of the percentage of vegetation
 removed and the total  acreage of the facility.
      4.   Annual per acre  soil loss rate (without vegetative  cover):   The
 annual  soil loss  for each  acre of  bare soil is  computed using the Univer-
 sal  Soil Loss  Equation (USLE).
             A =  RKSLCP
          A = Average soil  loss,  tons/acre
          R = Rainfall  and  run-off  erosivity index
          K = Soil erodibility  factor
          L = Slope  - length  factor
          S => Slope  - steepness  factor
          C = Cover/management  factor  (type  of vegetative cover)
          P = Practice  factor  (terracing, contour  plowing)
This  equation  is  for erosion resulting  from rainfall subsequent  to the
event that  removed  the vegetation.
      5.   Monthly  bare ground soil  loss  rate:  The annual loss  rate
computed  in Line  A  is converted  to a one month  loss rate.   This  conver-
sion  is  accomplished by dividing the annual  loss  rate by 12.
      6.   Amount of soil lost before repairs  are instituted:  The amount
of soil  lost from the bared ground is the product of the monthly loss
rate per  acre and the acreage of the facility that is exposed.  This
product  is  then multiplied by two  to allow for soil lost during  the

                                   9-125

-------
 removal of the vegetation.  The ground is assumed to be bare for about
 one month before the repairs and replanting are completed.  The conversion
 to volume of soil lost is carried out assuming a soil density of 100 Ibs.
 per cu. ft.
      7.  Unit cost for excavating and loading soil:   The unit cost for
 excavating and loading replacement soil is computed  using a 2 cu.  yd.
 front end loader.  This operation will be performed  under contract.
      8.  On-site haul of excavated soil to the area  needing repair:   The
 excavated soil is transported on-site over a 2000 ft.  distance  by  trucks
 operating under contract.
      9.  Filling and compacting eroded areas of the  facility:   The replace-
 ment  soil is  filled and compacted into the eroded areas  using a dozer
 operating under contract.
    10.  Total unit cost for replacing soil (Line 7  + Line 8  +•  Line  9):
 The total unit cost of replacing soil is  the sum of  the  excavation-
 loading,  hauling and filling unit costs.   These unit costs were obtained
 from  estimates made by a local contractor.
    11.  Cost of replacing the lost  soil  (Line 6 x Line  10):  The  total
 cost  for  replacing  the lost soil is  the product of the amount of soil
 lost  times  the unit cost for soil replacement.
    12.   Unit cost  for seeding the bare soil:   The unit  cost  for seeding
 the bare  acreage is computed from the sum of the labor,  materials  and
 equipment  costs.
              Labor                   $69.10/acre
              Materials              $13.90/acre
              Equipment              $ 5.00/acre
 The grass .planted is  Kentucky  bluegrass available  from a  local  supplier
 at $0.32 per  Ib.  in 50-lb.  bags.  The application  rate for  this  seed is
 1  Ib. per  1000  sq.  ft.  (or  43.56  Ibs.  per  acre).   This is  less  than one-
 third of  the  seed application  rate used for  home  lawns.   Experience has
 shown this  seeding  rate  to  be  satisfactory.
    13.  Unit  cost  for fertilizing:   Since  the  soil at this hazardous
waste facility  is quite  poor,  fertilization  is  necessary.  Type  10/6/4
 fertilizer  costing  $0.12  per Ib.  (in  50-lb.  bags)  is  applied at a rate
of 500  Ibs. per  acre.  This  corresponds to a nitrogen application rate

                                    9-126

-------
 of  50-lbs.  per  acre.   The unit  cost of fertilization is the sum of the
 labor,  materials  and  equipment  costs.
          Labor                       $69.10/acre .
          Materials                   S60.00/acre
          Equipment                   $  5.00/acre
 Previous  experience at this  facility has  shown that  this application
 rate  for  fertilizer is satisfactory.
      14.  Unit cost for mulching with.straw:   Since  the soil is bare, pro-
 tection from erosion  must be provided  while  the grass  starts to grow.
                                        •
 This  is achieved  by using straw mulch  at  an  application rate of 1 ton
 per acre.   The  unit cost  of  mulching is the  sum of  the labor,  materials
 and equipment costs.
          Labor                       $34.50/acre
          Materials                   $85.00/acre
          Equipment                   $  5.00/acre
      15.  Total  unit replanting  cost  (Line 12  + Line  13 + Line  14):   The
 total unit  replanting  cost is the sum  of  the  seeding,  fertilizing,  and
 mulching  costs.   Lime  is  not  applied at this  facility  because  it is not
 recommended by  the Agricultural Extension Service (USDA).
      16.  Total  replanting  costs (Line  3 x Line  15):  The  total replanting
 cost  for  the facility  is  the  product of the acreage  to be replanted and
 the unit  cost of  replanting  each acre.
      17.  Number of erosive incidents expected  in the post-closure period:
 It is anticipated that such  highly erosive incidents will occur twice
 during  the post-closure period.  These- will be  either  major  storms  or
 floods.
      18. Total cost for repairing damage from erosive  incidents  (Line 11
+ Line  16 x Line 17):   The total post-closure cost for  repairing  the  damage
 from such incidents is the sum of the  repair costs for  each  incident
 (soil and vegetation)  multiplied by the number  of incidents  expected  in
 the 30-year post-closure period.
     19. Total annual cost for repairs required by erosive incidents
 (Line 18  r 30 years):   The total cost of repairing the  damage  from  the
 two incidents is divided by  the 30 years of the post-closure period  to
yield the annual cost  for contingency repairs.

                                  9-127

-------
D.   Initial  Replanting Co Establish Vegecation
     1.  Percentage  failure of vegetation per year:   It  is  estimated
that in  this  climate,  10 percent of the vegetation will  fail  per  year  due
to inadequate initial  establishment.
     2.  Number  of years required for full vegetation:   It  is estimated
that three years will  be necessary for full establishment of  vegetation
to the point  replanting will no longer be necessary.
     3.  Facility acreage:   Facility acreage is 200 acres.
     4.  Total acres to be  replanted due to initial failure of vegetation
(Line 1  x Line 2 x Line 3) :  Total acres to be replanted are  then 60
acres.
     5.  Annual  per  acre soil loss:  The annual soil  loss for each acre
of bare  soil  is  computed using the Universal Soil  Loss Equation (USLE).
              A - RKLSCP
         A =>  Average soil loss,  tons/acre
         R =  Rainfall  and run-off erosivity index
         K =  Soil erodibility factor
         L =  Slope - length factor
         S =  Slope - steepness factor
         C =  Cover/management factor (type of vegetative cover)
         P =  Practice  factor (terracing,  contour plowing)
This equation is for erosion resulting from rainfall  subsequent to the
event that removed the  vegetation.
     6.  Monthly bare  ground soil loss rate:   The  annual loss  rate com-
puted in Step 4  is converted to  a one-month loss rate.  This  conversion
is accomplished  by dividing the  annual loss rate by 12.
     7.  Amount  of soil lost before repairs are instituted  (Line  4 x
Line 6) :  The amount of soil lost from the bared ground  is  the product
of the monthly loss rate per acre and the acreage  of  the facility  that
is exposed.   This product is then multiplied  by two to allow  for  soil
lost during the  removal of  the vegetation.   The ground is assumed  to be
bare for about one month before  the repairs and replanting are completed.
The conversion to volume of soil lost is  carried out  assuming a soil
density  of 100 Ibs. per cu.  ft.
                                   9-128

-------
      8.   Unit  cost  for  excavating  and  loading soil:   The unit  cost  for
 excavating and loading  replacement soil is computed using a 2  cu.  yd.
 front end loader.   This operation  will be performed under contract.
      9.   On-site  Haul of excavated soil to area needing repair:   The
 excavated soil is  transported on-site  over a 2000 ft. distance by trucks
 operating under contract.
     10.   Filling  and  compacting eroded areas of the facility:  The  replace-
 ment soil is  filled and compacted  into the eroded areas using  a  dozer
 operating under contract.
     11.   Total unit cost for  soil  replacement (Line  8 + Line 9 + Line 10):
 The  total unit cost of  soil replacement is the sum of the excavation-
 loading,  hauling and  filling  unit  costs.   These unit costs  were  obtained
 from estimates made by  a local  contractor.
     12.   Cost  of soil replacement  (Line 7  x Line 11):  The  total cost for
 replacing the  lost  soil is the  product of  the amount of soil lost times
 the  unit  cost  for soil  replacement.
     13.   Unit  cost  for  seeding  bare soil:   The unit  cost  for seeding  the
 bare  acreage is computed  from the  sum  of  the  labor,  materials  and equip-
 ment  costs.
             Labor                  $69.10/acre
             Materials              $13.90/acre
             Equipment              $  5.00/acre
 The grass planted is  Kentucky bluegrass available  from  a  local supplier
 at $0.32  per Ib. in 50-lb. bags.  The  application  rate  for  this seed  is
 1 Ib. per 1000 sq.  ft.  (or about 40 Ibs. per acre).  This is less than one-
 third of  the seed application rate used for home lawns.  Experience has
 shown this seeding  rate  to be satisfactory.
    14.  Unit cost  for  fertilizing:  Since  the soil at  this hazardous
waste facility is  quite poor,  fertilization is necessary.  Type 10/6/4
 fertilizer costing  $0.12 per Ib. (in 50-lb. bags) is applied at a rate
of 500 Ibs. per acre.   This corresponds to a nitrogen application rate
of 50 Ibs. per acre.  The unit cost of  fertilizing is the sum of  the
labor, materials and equipment costs.
         Labor                      $69.10/acre
         Materials                  $60.00/acre

                                  9-129

-------
          Equipment                  $ 5.00/acre
 Previous experience at  this facility has shown that this application
 rate for fertilizer is  satisfactory.
      15. Unit cost for  mulching with straw:  Since the soil is bare,
 protection from erosion must be provided while the grass starts to grow.
 This is achieved by using straw mulch at an application rate of 1 ton
 per acre.  The unit cost of mulching is the sum of the labor, materials
 and equipment cos ts.
          Labor                      $34.50/acre
          Materials                  $85.00/acre
          Equipment                  $ 5.00/acre
      16. Total unit replanting cost (Line 13 + Line 14 +• Line 15) :   The
 total unit  replanting cost is  the sum of the seeding,  fertilizing,  and
 mulching costs.   Lime is not applied at this facility  because it is  not
 recommended by the Agricultural Extension Service (USDA).
      17.  Total replanting costs (Line 4 x Line  16): The  total replanting
 costs  for the entire  30-year period are then $20,796.
      18.  Total costs  for initial replanting  to  establish  vegetation  (Line
 12  + Line 17) :   The total costs for the initial replanting  to establish
 vegetation  are then $20,847.
      19.  Total annual cost (Line 18 4- 30):   The total  cost  for the initial
 replanting  to  establish  vegetation is  divided by  the 30 years  of  the  post-
 closure  period to  yield  the  total  annual cost,  for  a total  of  $695.

 E.   Administrative Services
     1.   Number  of  technical hours required  for administrative  duties
 (annual) :   Since  the  facility  is closed,  all of the required administration
 is an extra cost  that  must be  carefully  accounted for.  This  facility esti-
mates that  an  average  of three  weeks of  labor by a  manager  is  required  to
administer  the complete  set of  specified  post-closure  activities.  This
average administrative requirement includes  the administration  of the
occasional  contingent  events described in Worksheet C.
 •
     2.   Person-hour cost  for  technical administrative duties:  The labor
rate for  facility technical labor  is $30 per hour fully-loaded.
     3.  Total administrative costs for  technical labor (Line 1 x Line  2):

                                   9-130

-------
 The total cost for administrative technical labor is the product of the
 hours  required and the labor rate.
      4.   Number of clerical hours required for administrative duties:
 Three  weeks of clerical work is  required to support the technical adminis-
 trator.
      5.   Person-hour costs.for clerical administrative duties:  The fully-
 loaded labor rate for clerical labor at the facility is $8 per hour.
      6.   Total administrative  costs  for clerical labor (Line 4 x Line 5):
 The total cost for administrative clerical labor is the product of the
 hours  required and the labor rate.
      7.   Office or trailer  rental:   The total  annual administrative cose
 also includes  the rental of office space during the busier times of each
 post-closure year.   This includes typewriter,  telephone and supplies.
     8.   Total annual administrative costs for post-closure activities
 (Line  3 + Line 6  + Line 7):  The  total  cost of administration is the
 sum of  the costs  of  technical  labor,  clerical  labor,  and office rental.

 F-   Total Costs  Including  Administration  and  Contingencies
     Items  1 through  5  summarize  the  total annual costs  of  the  post-
 closure functions  taken from the  cost worksheets.   The  erosion  contingency
 repair cost  (Line  3)  used is the  annual  cost of  the  two  major erosion
 events expected in  the  post-closure  period (30 years).
     6.  Total of Lines  1 through 5:  The  total  costs of the activities
 listed in  Lines 1  through 5  are $40,206.
     7.  Contingencies:  Fifteen percent of  the  sum of  the above costs is
 taken as an  allowance for contingencies.   This contingency allowance is
made in addition  to the  costs expected from  the  two major post-closure
erosion events.
     8.  Administration:  An additional 10 percent of Line 6 is included
 for fees,   insurance and  related needs.
     9.  Total annual costs of post-closure  (Line 6 + Line 7 + Line 8):
The total  sum of the annual post-closure costs is $50,258.
                                  9-131

-------
                                POST-CLOSURE
                 WORKSHEET A - PERIODIC FACILITY INSPECTION
 1.   Number  of  technical management person-hours               16  hours
      required for  each  routine  inspection of  the
      closed  facility
 2.   Annual  number of routine inspections                     6
 3.   Person-hour costs  for technical management labor          $30
 4.   Technical  labor costs for  annual routine inspections      $2880
      (Line 1 x  Line 2 x Line 3)
 5.   Annual  number of engineer-supported  inspections           2
 6.   Number  of  independent state-certified engineering         8 hours
      hours for  each engineer-supported inspection
 7.   Number  of  technical management hours for each             8 hours
      engineer-supported inspection
 8.   Person-hour cost for a professional  engineer              $75
 9.   Engineering labor  costs for  the engineer-supported        $1200
      inspections (Line  5 x Line 6 x Line  8)
10.   Technical  labor costs for  the  engineer-supported          $480
      inspections (Line  3 x Line 5 x Line  7)
11.   Labor costs for the engineer-supported inspections        $1680
      (Line 9 +  Line 10)
12.   Truck rental  cost  for each inspection                    $36
13.   Annual  truck  rental cost for inspections                  $288
      (Line 2 +  Line 5 x Line 12)
14.   Total annual  inspection cost (Line 4 + Line 11 +          $4848
      Line 13)
                                   9-132

-------
                                POST-CLOSURE
         WORKSHEET B  - ROUTINE MONITORING AND MAINTENANCE ACTIVITIES
 Mowing  Operations
 1.    Facility  acreage
       Mowing  labor  (per  acre)
       Mowing  equipment  (per  acre)
       Unit mowing cost  (Line 2 + Line  3)
       Annual  frequency of mowing
       Annual  cost of mowing  (Line  1  x  Line  4  x  Line  5)
 Routine Erosion Damage  Repair
 7.    Annual  routine erosion rate
 8.
 9.
10.
11.
      Total annual routine erosive  loss   (Line  1  x  Line  7)
      Unit cost for hand excavation of soil
      Unit cost for transporting of soil  on-site
      Unit cost for hand compacting soil  (repairing
      erosive damage)
      Unit cost of seeding
      Aggregate unit cost of repairing routine  soil
      erosion damage (Line 9 +• Line  10 +  Line 11 -f- Line  12)
      Total annual cost for repairing erosive damage of
      a routine nature (Line 8 x Line 13)
      Adjustment factor to account  for unusually wet seasons
      Annual cost for repairing routine erosive damage
      (Line 14 x Line 15)
 Fence Replacement
17.   Frequency of replacing fence
12.
13.

14.

15.
16.
19.
      Facility perimeter
      Unit cost of replacing fence
 200 acres
 $14.28
 $5.37
 $19.65
 Once a year
 $3930

 0.12 tons
 per acre
 (.089 cu.
 yds./acre)
 17.8 cu.  yds.
 $21.21/cu.  yd.
 $2.13/cu. yd.
 $21.21/cu.  yd.

 $l/cu. yd.
 345.55/cu.  yd.

 $810.79
                                                               S1621.58
Once during
post-closure
period
11,808 ft.
$13.06/linear
ft. (installed)
                                   9-133

-------
WORKSHEET  B  (continued)
20.  Total  cost  of  fence replacement  (Line 18 x  Line 19)
21.  Pro-rated annual cost of  fence replacement
Fertilizing
22.  Unit cost for  fertilizing
23.  Number of fertilizer  applications for  first 3 years
24.  Number of fertilizer  applications during  remainder
     of post-closure  (Years 4-30)
25.  Total  costs of fertilizing  for first  3 years
     (Line  1 x Line 22  x Line  23)
26.  Total  costs of fertilizing  for post-closure
     years  4-30  (Line 1 x  Line 22 x Line 24)
27.  Total  fertilizing  costs (Line 25 + Line  26)
28.  Annual cost of facility fertilization  (Line 27 T 30)
Ground-water Monitoring Well Replacement
29.  Unit cost for replacing well
30.  Number of wells  needing replacement during  the
     pose-closure period
31.  Total cost of monitoring  well replacement during
     the entire post-closure period (Line 29 x Line 30)
Leachate Pumping and  Disposal
32.  Frequency of removing the leachates
33.  Average monthly  total leachate withdrawal
34.  Unit cost of removing the leachate to an active
     off-site TSDF
35.  Total annual cost  of removing leachate
     (Line 32 x Line  33  x Line 34 x 12)
36.  Unit cost for disposing of leachate off-site (at
     a surface impoundment)
37.  Annual costs for disposing off-site (Line 32 x
     Line 33 x Line 36  x 12)
38.  Total annual costs  for removing and disposing of
     leachates (Line  35 4- Line 37)
 $154,212.48
 S  5,140.41

 $134.10/acre
     3
     5

 $ 80,460

 $134,100

 $214,560
 $  7,152

 $425/well
 2

 $850


 Once/month
 2000 gals.
 50.18/gal.

'$4320

 $.05/gal.

 $1200

 $5520
                                   9-134

-------
 WORKSHEET B (continued)
 42.

 43.

 44.

 45.
 46.
 47.
 48.
 49.
 Ground-Water Monitoring
 39.   Number of  wells monitored
 40.   Number of  samples  taken per well (annual)
 41.   Total  number  of samples per well (annual)
      (Line  39 x Line 40)
      Number of  hours for  collecting the  samples (per
      sample)
      Total  number  of hours  for collecting  samples
      (Line  41 x Line 42)
      Total  number  of hours  for preparing and  delivering
      samples
      Total  sample  handling  hours  (Line 43  + Line 44)
      Person-hour costs  for  handling  ground-water samples
      Total  sample  handling  co.sts  (Line 45  x Line 46)
      Unit cost  of  ground-water quality analysis
      Unit cost  of  ground-water contamination  analysis
50.   Total  cost for  ground-water quality analysis
      (annual) (Line  39  x Line  48)
51.  Total  cost for  ground-water contamination analysis
      (annual) (Line  41  x Line  48)
52.  Total annual ground-water monitoring cost  (Line 49
     + Line 50 + Line 51)
Routine Maintenance Summation
53.  Annual mowing cost (Line 6)
     Annual cost for repairing routine erosive
     damage (Line 16)
     Annual cost for replacing fence (Line  21)
     Annual cost for fertilizing (Line 28)
     Annual cost for replacing well (Line 21 4- 30)
     Annual cost for removing leachates  (Line  38)
     Annual cost for ground-water monitoring (Line  52)
     Total annual cost for routine activities
54.

55.
56.
57.
58.
59.
60.
 12 wells
 2 samples
 24 samples

 2 hours

 48 hours

 6 hours

 54 hours
 $15
 $810
 $77
 $108
 $924

 $2592

 S4326
$3930
$1621.58

$5140.41
$7152
$28
$5520
$4326
S27.717.99
                                   9-135

-------
                                 POST-CLOSURE
              WORKSHEET C - EROSION DAMAGE CONTINGENCY SCENARIO
  1.
  2.
  3.
  4.
10,

11.
12.
13.
14.
15.
16.
17.

18.

19.
 Percentage of vegetation removed
 Facility acreage
 Acreage  reduced to bare soil (Line 1 x Line 2)
 Annual per acre soil loss rate (without
 vegatative cover)
 llonthly  bare  ground soil loss  rate
Amount of  soil  lost before  repairs  are  instituted
(Line 3 x  Line  5x2)  'The  factor of  2  adjusts  for
immediate  soil  losses)
Unit cost  for excavating  and  loading  soil  (on-site
operations using  a  2-cu.  yd.  front  end  loader)
On-site haul of excavated soil  to area  needing
repair
Filling and compacting  the  eroded areas  (using
a dozer)
Total unit cost for soil  replacement
(Line 7 + Line 8  +  Line 9)
Cost of replacing lost soil (Line 6 x Line 10)
Unit cost for seeding the bare  soil
Unit cost for fertilizing
Unit cost for mulching with straw
Total unit replanting cost  (Line  12 + Line 13 + Line
Total replanting  cost (Line 3 x Line 15)
Number of erosive incidents expected in the post-
closure period
Total cost for repairing  damage from erosive
incidents (Line 11  + Line 16 x Line 17
Total annual cost for repairs required by erosive
incidents (Line 18  4- 30)
     30%
     200 acres
     60 acres
     12 tons
     per acre
     1 ton per
     acre
     (.741 cu.
     yds./acre)
     120 tons
     (89 cu. yds.)

     50.21 per
     cu. yd.
     SO.85 per
     cu. yd.
     $1.25 per
    cu. yd.
     32.31 per
    cu. yd.
    $205.59
    $88/acre
    $134/acre
    $124.50/acre
14)  S346.50/acre
    $20,790
    2

  .$41,580
                                    9-136

-------
                                 POST-CLOSURE
          WORKSHEET D - INITIAL REPLANTING TO ESTABLISH VEGETATION
  1.
  2.
  3.
  4.

  5.

  6.

  7.

  8.

  9.

10.

11.

12.
13.
14.
15.
16.
17.
18.

19.
 Percentage failure of vegetation per year
 Number of years required for full vegetation
 Facility acreage
 Total acres to be replanted due to initial
 failure of vegetation (Line 1 x Line 2 x Line 3)
 Annual per acre soil loss rate (for areas with
 inadequate vegetative cover)
 Monthly bare  ground soil loss rate

 Amount of soil lost before  repairs are
 instituted (Line 4 x Line 6)
 Unit  cost for soil excavation and loading
 (on-site operations using a 2-cu.  yd.  front  end loader)
 On-site  haul  of  excavated soil to  area needing
 repair
 Filling- and compacting eroded  areas  (-usinc a
 dozer)
 Total  unit cost  for soil replacement
 (Line  8  -I- Line  9 -r Line  10)
 Cost of  soil  replacement  (Line  7 x Line  11)
 Unit cost  for seeding bare  soil
 Unit cost  for fertilizing
 Unit cost  for mulching with straw
 Total  unit replanting cost  (Line 13 + Line 14 + Line 15)
 Total  replanting costs (Line 4 x Line 16)
 Total  costs for  initial replanting to establish
vegetation (Line 12 + Line 17)
Total annual cost  (Line 18 4- 30)
 10 percent
 3
 200 acres
 60

 6 tons/acre

 .5 tons
 (.3706 cu.
 yd./acre)
 30 tons
 (22  cu.  yds.)
 $0.21 per
 cu.  yd.
 SO.85 per
 cu.  yd.
 SI.25 per
 cu.  yd.
 $2.31 per
 cu.  yd.
 $50.82
 $88/acre
 $134.10/acre
 $124.50/acre
$346.60/acre
$20,796
$20,847
                                   9-137

-------
                                POST-CLOSURE
                   WORKSHEET E  - ADMINISTRATIVE  SERVICES
1.   Number of  technical  hours  required  for  administrative
     duties (annual)
2.   Person-hour cost  for technical  administrative duties
3.   Total administrative costs  for  technical labor
     (Line 1 x  Line 2)
4.   Number of  clerical hours required for administrative
     duties
5.   Person-hour costs for clerical  administrative duties
6.   Total administrative costs  for  clerical labor
     (Line 4 x  Line 5)
7.   Office or  trailer rental (includes equipment and
     supplies)
8.   Total annual administrative costs for the post-closure
     activities (Line 3 +• Line 6 + Line 7)
120 hours

§30
$3600

120 hours

$8
$960
                                   9-138

-------