FEDERAL ASSISTANCE PROJECT
METROPOLITAN DENVER SEWAGE
   DISPOSAL DISTRICT NO. 1
      October 1969 • FEBRUARY 1970
^
-> r I
| Westminst
^ r-j— | Thornton I
"LET
^1 J_
               Englewoed  ~\
                               ENVIRONMENTAL PROTECTION AGENCY

                               WATER QUALITY OFFICE - REGION VII

                                911 WALNUT, KANSAS CITY, MO. 64106

-------
    FEDERAL ASSISTANCE PROJECT
    METROPOLITAN DENVER SEWAGE
      DISPOSAL DISTRICT NO. 1
  OCTOBER 1969  -  FEBRUARY 1970
                By
            Bob A. Hegg
                And
         John R. Burgeson
  ENVIRONMENTAL PROTECTION AGENCY
WATER QUALITY OFFICE  -  REGION VII
911 WALNUT, KANSAS CITY, MO. 64106

-------
The Superintendent of Documents
classification number is:

      EP 2.2:  D43

-------
                                     TABLE OF CONTENTS

                                                                                  PAGE NO.

I.     Introduction	      1
II.     Purpose and Scope 	      2
III.    Description of Plant and Area	      3
IV.     Summary of Assistance Project 	      5
         A.  Control Testing  -  Procedures and Results	      5
         B.  Performance Evaluation  -  Procedures and Results 	      6
         C.  Data Analysis  -  Procedures and Results	      9
         D.  Control of Areas  -  Procedures and Results 	     11
         E.  Control of Sludge Characteristics  -  Procedures and Results.  ...     12
V.     Data Analysis	     15
         A.  Analysis of Sludge Production 	     15
         B.  Analysis of Secondary Clarifiers	     21
VI.     Summary and Conclusions	     29
VII.    Recommendations	     32
VIII.  Appendices	     33
         Appendix A  -  A Resolution:  "Concerning the Federal Government's
                        Responsibilities in Constructing and Operating Sewage
                        Disposal Facilities" 	     34
         Appendix B  -  References 	     36
         Appendix C  -  Determination of Substrate Removal Rate  (q) and
                        Net Growth Rate (l/ec)	     38

-------
                                      LIST OF TABLES
TABLE NO.                                  TITLE                                  PAGE NO.

    1        A Summary of Various Parameters Associated with the Selected
             "Steady State" Periods	     17
    2        Calculated Values of ec and quODs  ~  Selected Periods of
             Operation  -  Areas #2 and #3	•	     19
    3        Average Settled Sludge Volumes for "Steady State" Periods 	     22
    4        Zone Settling Rates (V$) and Equivalent Surface Overflow
             Rates (Or) for "Steady State" Periods 	     25
    5        Waste Sludge Flow Required to Remove an Equivalent Amount of
             Solids with Varying Underflow Concentrations	     28
                                             ii

-------
                                      LIST OF FIGURES
FIGURE NO.                                 TITLE                                  PAGE NO.
1
2
3
4
5
6
Plant Flow Schematic 	
Influent BODs Loadings and Seven Day Moving Average, Effluent
B005 and TSS Concentrations vs Time 	 ~ 	
Weekly Average Percentage Reduction of BOOs and TSS


Determination of Zone Settling Rate (Vs) - Height of Sludge
4
8
10
14
20
             Interface vs Time  -  Area #3 Period:  2/9 - 2/16/70 Average
             9:00 A.M	     24
                                             iii

-------
 I.   INTRODUCTION
     The Metropolitan Denver Sewage Disposal District #1 (Metro Denver) plant was designed mainly as a
secondary treatment facility  (activated sludge) to treat wastes from the cities and sanitary districts
in the Metropolitan Denver Area.  The plant is administered by a Board of Directors who represent the
various communities and districts that are served by the facility.  The largest source of flow to the
plant is the primary effluent from the City and County of Denver's North Side Sewage Treatment Plant.
     The Metro Denver plant began operation in 1966 and since that time has continually experienced
difficulties.  Odor problems, insufficient sludge handling facilities, air pollution from sludge
incineration; unavailability of land for sludge disposal sites, management, labor, and maintenance
problems are the more significant of the difficulties that the plant has encountered.  These problems
have served to further increase the public's awareness of the Metro Denver plant.
     In an effort to resolve this situation, the Board of Directors of the Metro Denver plant passed a
resolution (see Appendix A) entitled "Concerning the Federal Government's Responsibilities in Con-
structing and Operating Sewage Disposal Facilities."  In the resolution, Metro Denver petitioned the
Congress of the United States and the appropriate Federal  agencies to make available to the district
a special  team of scientists and engineers to serve as a task force to inspect the district's acti-
vated sludge treatment plant and make appropriate recommendations.  As a result of this resolution, a
three-man  team from what was then the Federal Water Quality Administration was assigned to the Metro
Denver treatment facility from October 1969 through February 1970.  The project officer was
Mr. Alfred West from the National Field Investigation Center (NFIC) in Cincinnati.   He was assisted
by Mr. Joseph Jos 1 in and Mr. Bob Hegg of the Kansas City Regional  Office.

-------
II.  PURPOSE AND SCOPE
    The most significant problem areas at the Metro Denver plant, leading to the request for assis-
tance, were the sludge handling and sludge disposal problems.   The major sludge handling problem was
processing the volume and type of waste activated sludge generated by the secondary treatment process
employed at the plant.  The sludge disposal problem occurred because of the plant's inability to
incinerate all of the sludge that was processed.  It was decided at the on-set of the Federal Assis-
tance Project to concentrate efforts on the sludge handling problem by attempting to effect the mass
                                t
and characteristics of the sludge produced by the secondary treatment process.
    Operational changes in the secondary treatment process, training in conducting various control
tests and data evaluation were the major tasks performed during the assistance project.  These
functions were coupled with various operational recommendations for both short term and long term
plant operation and control.
    This report documents the findings of the Federal team.  Also presented are the results of
additional analyses of the data conducted after the conclusion of the project.

-------
III.  DESCRIPTION OF PLANT AND AREA
    The Metro Denver activated sludge plant Is located north of Denver in  Commerce  City,  Colorado.
The effluent from the plant is discharged to the South Platte River,  an interstate  stream.   The  State
Water Quality Standards require a minimum of 8056 removal  of five-day  20°C  BOD by the  Metro  Denver
plant before discharge to the South Platte River.   Since  the plant began operation  in 1966, it has
generally achieved this required eighty percent reduction.
    The Metro Denver plant is comprised of primary and secondary sewage treatment facilities and
includes sludge processing facilities.   A flow schematic  is presented in Figure 1.
    The primary treatment facilities were designed to treat an average flow of 27 million gallons per
day (MGD) and a maximum flow of 50 MGD.  These facilities consist of  an inlet structure,  bar screens,
grit and grease removal units, sedimentation basins and a grease and  scum  incinerator.
    The secondary treatment facilities  were designed to treat an average flow of 117  MGD  with a
maximum flow of 234 MGD.  The design (8005) load is 166,350 pounds per day or an average  influent
concentration of 170 mg/1 8005.  The secondary treatment  facilities consist of aeration basins,  the
blower building, sedimentation basins and chlorine contact chambers.
    The sludge processing facilities were designed to treat 37,400 pounds  per day of  raw  primary
sludge and 131,000 pounds per day of secondary sludge from the Metro  Denver plant;  and 92,700 pounds
per day of digested primary sludge from the Denver North  Side plant.   These facilities consist of the
waste activated sludge concentrators, sludge holding tanks and the sludge  processing  building which
housed the vacuum filters and incinerators.
    Pertinent design information about types and sizes of equipment is discussed, as  necessary,  in
the following sections.

-------
NORTH SIDE EFFLUENT    GATE
  METERING FLUME    STRUCTURE
                                                               FEDERAL ASSISTANCE PROJECT
                                                      METROPOLITAN DENVER SEWAGE TREATMENT PLANT

                                                             OCTOBER 1969 - FEBRUARY 1970


                                                                  PLANT FLOW SCHEMATIC

-------
IV.  SUMMARY OF ASSISTANCE PROJECT
    The major emphasis during the Federal Assistance Project was  aimed at the biological  (secondary)
portion of the Metro Denver plant.  As shown in Figure 1, the secondary portion is comprised of
twelve aeration basins each of two million gallon capacity and twelve 1.16 million gallon  final
clarifiers.  These twenty-four structures were equally divided into four separate areas  by piping,
pumps and other control devices.  Throughout the project these four areas demonstrated characteris-
tics of four different plants possibly due to undetected loading  differences, flow characteristics,
etc.  For this reason, operational control of each of the areas was different and was based on the
individual characteristics exhibited.  Because excessive grease was contained in the influent to the
Metro Denver plant, aeration basins No. 1 and No. 2 (located in Areas #1 and #2) were used as grease
flotation units.  This required that Areas #1 and #2 be operated  using only two aeration basins in
combination with their respective three clarifiers.  Areas #3 and #4 were operated using all three
aeration basins and three clarifiers in each area.

A.  Control Testing Procedures and Results
    The initial phase of the project involved instigating process control testing, as outlined by
West (1), to monitor process performance.  The basic control tests are the centrifuge test, the
settleometer test, blanket depth measurements, turbidity measurements and dissolved oxygen concen-
tration determinations.  The main function of each of these procedures is:
    1.  Centrifuge tests were conducted on the effluent from the aeration basins and on the return
        sludge drawn from the final clarifiers.  This test indicates the relative concentrations (by
        percent volume) of solids needed for determining the solids distribution in the activated
        sludge process.  The results from the centrifuge test can also be used for other determina-
        tions.  For example, the secondary clarifiers at the Metro plant are the "vacuum" type with
        twelve draw-off tubes in each clarifier.  By using the centrifuge to determine the suspended
        solids concentrations, the height of each draw-off tube can be adjusted so that a uniform
        concentration of sludge can be drawn from the clarifier bottom.
        A  relationship between percent solids by centrifuge and by weight (milligrams per liter) of
        total and volatile suspended solids  (TSS & VSS) was obtained by comparing the results of a
        centrifuge test and a suspended solids analysis made on the same grab samples.  This compari-
        son was made on a daily basis throughout most of the project.
    2.  Settleometer testing was conducted on the effluent from the aeration basins to determine the
        settling rate and characteristics of the sludge.  Visual  observations of the sludge settling
        characteristics indicated the relative removals, flocculation properties, etc. of the sludges
        from  the four areas.  Analysis of the settleometer data coupled with centrifuge data also

-------
        allowed a determination of the dewatering or concentrating ability of the various mixed
        liquors.  Settleometer data were normally collected four times per day at 5:00 A.M., 9:00
        A.M., 1:00 P.M. and 9:00 P.M.  During the last portion of the project, settleometer tests
        were run every two hours.  Readings of the settled sludge volume (SSV), as indicated from the
        settleometer, were taken every five minutes for the first one-half hour and every ten minutes
        for the second one-half hour.
    3.  Blanket depth determinations (depth of sludge interface from surface) were taken on each of
        the final clarifiers to aid in determining the solids distribution and solids mass in the
        final clarifiers.  During the last portion of the project, blanket readings were taken every
        two hours, twenty-four hours per day.
    4.  Turbidity measurements were taken on samples of settled and skimmed effluent from the final
        clarifiers and were used to indicate the relative effectiveness of the activated sludge
        process in producing a clarified effluent.  The samples were settled and skimmed before
        turbidity measurements were made so that clarifier limitations could be eliminated from the
        analysis and only the relative effectiveness of the biological system could be judged.
    5.  Dissolved oxygen measurements were taken to assure that an adequate oxygen supply was avail-
        able to support the process.
    Plant operators were trained during the project to make the above control tests and to analyze
and interpret the obtained data.  Process control adjustments could then be made on a routine basis.
In addition to conducting the control tests, the operators were required to take readings of various
flow meters and to collect grab and composite samples so that the plant performance could be
monitored.

B.  Performance Evaluation-procedures and Results.
    The Metro plant laboratory conducted various analyses on the collected samples to provide addi-
tional data for the project.  Influent and effluent samples for the secondary treatment portion of
the plant were composited and determinations were made for 8005 and TSS.  In addition to overall
plant influent and effluent samples, Influent and effluent samples were collected and composited on
each of the individual areas.  Figure 2 illustrates the loading in pounds of BOD5 applied to the
secondary treatment (activated sludge) portion of the Metro Denver plant, as well as the seven day
moving average of the overall plant effluent concentrations of 6005 and TSS.
    The seven day moving average 8005 and TSS effluent concentrations are depicted on the lower por-
tion of Figure 2.  The BOD5 in the effluent is closely.related to the TSS concentration.  This
relationship emphasizes the effect of the difficulties encountered with final clarifiers at the Metro
Denver plant.  Without exception, each peak on the graph can be correlated with "bulking" problems in

-------
one or more of the areas.  A portion of the "bulking" problem was  due  to  a  poor-settling sludge
caused by process imbalance.  However, many times an apparent good-settling sludge  in  settleometer
testing was hydraulically "flushed" over the effluent weirs.
    It is believed that the peaks or poor effluent quality depicted in ,Figure  2,  prior to  and  during
the initial phases of the Federal project, were caused by the above-average flow  and BODg  loadings
(See upper portion of Figure 2) that were received at the plant during the  month  of October 1969.
The large peaks of effluent TSS and BODg experienced in the latter part of  November and in December
were caused by a loss of process balance in Areas #1, #2 and #4.  The  exact reasons for these  changes
are not known.  However, it may have been the type of loading being used, temperature  effects, meter
problems, etc.  When Areas #2 and #4 were subsequently converted so that  all the  sewage was applied
at the head of each aeration basin on December 12, 1969, the trend in  the effluent  concentrations of
BODjj and TSS decreased.  Area #1 was converted to this type of loading on January 5, 1970.
    The peaks depicted in the month of January were caused by loss of control  of  Area  #3.   Excessive
wasting of sludge and the breakdown of a clarifier were the main causes of  this failure.
    The peaks in February were caused by "bulking" problems in Areas #1 and #4.  Area  #1 was bulking
because an attempt was made to rapidly build up solids while Area #4 was  bulking  because excessive
solids had accumulated due to inaccurate flow meters on the waste sludge  stream.
    The effluent quality toward the end of the project (excluding the  peaks in late February)  was
definitely on an improving trend.  The only other period of corresponding quality was  experienced
during the first part of November 1969.
    The effluent quality depicted in Figure 2 represents a composite of all of the  areas  and,  there-
fore, the performance of the individual areas is not reflected directly.   Areas #1  and #4  generally
had the poorest quality effluents, while areas §2 and #3 gave the most consistent high quality
effluents.  The reasons for this may have been undetected differences  in  loading, the effects  of
different operational modes or undetected difficulties with flow meters.
    Also shown in Figure 2 is the loading to the secondary process in pounds of BODs per day.   The
dotted line represents the design average day loading (166,350 Ibs. BODg  per day) which was exceeded
on various days of all weeks during the project.  The average loading for the entire period of study
was 161,560 pounds BODs per day.  However, two aeration basins were not in  service  as activated
sludge basins but rather as grease removal units.  Thus, the aeration capacity to handle the design
load was reduced.
    The BOD5  load was high during the month of October because of the effects of runoff from early
snows that had occurred in the Denver area.  There is no apparent explanation for the higher load-
ings in the middle of January and especially the peak load on January 15, 1970.
    Another trend that is not as apparent is the relationship between loading and effluent quality.

-------
 i
     320

     280

     240-
 £  120-
 UJ

 3   80-
      90


  f  8°

-    20

     10
                                           FIGURE  2
                                    FEDERAL ASSISTANCE PROJECT
                            METROPOLITAN DENVER SEWER TREATMENT PLANT

                                  OCTOBER-1969 to FEBRUARY -1970

                                   INFLUENT BODS LOADINGS AND
                               7 DAY MOVING AVERAGE, EFFLUENT BOD5
                                      AND TSS CONCENTRATIONS
                                               VS
                                              TIME
   A
   I     *A   7 DAY MOVING. AVG. TSS
./                                            .A
  ,^*»'^%   7 DAY MOVING AVG. BOD5
s/               V^\v^/~*/
         1	KTOUI 1969
                                     1	HOVEMIEIt 1969
                                                                                                                                              AVERAGE DAY DESIGN
                                                                                                                                               LOADING 166,350 LBS. BOI
                                                                      TIME IN DAYS

-------
The low loading in December is reflected by a consistent high quality effluent during the first one-
half of the month.  The consistent steady loading during the last half of January and the month of
February is reflected by consistently improving effluent BODg and TSS concentrations.  The higher
loadings in October and in January demonstrate the adverse effect of decreasing effluent quality.
    Figure 3 illustrates the percentage reduction (weekly average) of BOD,- and TSS achieved by the
Metro Denver plant.  The percentage removal of BODg is a better indicator than effluent BODg concen-
trations of the benefits of process control.  This fact is shown by the gradual increase in percen-
tage removal throughout the project.  The percentage removal of TSS declined during the initial phase
of the project and then increased rapidly in December to a somewhat stable percentage reduction
during the final phases of the project.
    The increasing trend in percentage BODg reduction in conjunction with the fluctuating effluent
BOD5 concentrations can be explained by the variations in the incoming BODg load.  An increasing
BOD5 load was accompanied by increased effluent concentrations and thus a relatively constant rela-
tionship as far as percentage removal.
    The average reduction of BOD5 for the entire period was 85% and for TSS it was 60%.  These are
reductions by the secondary treatment portion of the plant only and do not include the reductions of
BOD5 and TSS that were achieved by primary treatment.  Therefore, the reduction of BODg for the pri-
mary and secondary processes averaged greater than for the secondary treatment process only and
adequately met the 80% minimum reduction of BOD5 required by Colorado's Water Quality Standards.

C.  Data Analysis  -  Procedures and Results
    Large volumes of data were obtained from the numerous control tests that were conducted and the
various monitoring or performance determinations that were made.  These data were analyzed daily to
determine trends which were indicative of process performance and from these various trends process
control decisions were made.  (i.e. increase or decrease return sludge flow, increase or decrease
wasting flow rate, etc.)  Metro Denver plant personnel were trained in analyzing the data and
deriving the various trend relationships.  Training was also provided in interpreting the various
trend curves so that control adjustments could be made.
    A large number of relationships were established to determine the best parameter or combination
of parameters to use for controlling the activated sludge process.  At the conclusion of the project
many of these relationships were abandoned and only those that appeared most beneficial were recom-
mended for continual use.
    A summary of the more pertinent analyses performed are presented below.
    The relationship between the settled sludge volume (settleometer readings) and time was plotted
to indicate the trends in settleability of the sludge.  Also established was the trend outlining the

-------
         100
          80-
          TO-
          GO-
        z
        o
           /\A
-      i so-
        li!
    .X
          40>
30<
          20-
                                                                                                               FIGURE 3

                                                                                                       FEDERAL ASSISTANCE PROJECT
                                                                                               METROPOLITAN DENVER SEWAGE TREATMENT PLANT

                                                                                                    OCTOBER - 1969 to FEBRUARY - 1970

                                                                                               WEEKLY AVERAGE PERCENTAGE REDUCTION OF BOD s
                                                                                                        AND TSS ( SECONDARY ONLY )
                                                                                                                   VS
                                                                                                                 TIME
          IO-
                                                                                                     26 I Z'l I 1 * • 2/16 I 2/23
       WEEK oF^joTToTTTaTjr^zoIiolTl 11 3 111 10 III i7«ll 24l .1 I • 12 8 112 IS! II 21112 291 I  S
                                                                                                                              END MARCH I. 1970

-------
ability of the sludge to concentrate or dewater.   Many of the relationships  were based on data from
the daily control test values.  Sludge blanket depths were determined as many'as twelve times per
twenty-four hour period as well as aeration tank concentrations, return sludge  concentrations and
flow measurements.  These values were averaged on a daily basis and such parameters as sludge age,
total sludge mass in the system, clarifier overflow rates, sludge detention  time in the clarifier,
mass of sludge returned per gallon of sewage, etc. were calculated.  Additional trends developed
were effluent quality versus time as described by BODg and TSS concentrations.
    All of the above-outlined analyses, as well as others, were conducted on each of the areas.

D.  Control of Areas  -  Procedures and Results
    Prior to this project, Metro Denver plant personnel were operating the secondary treatment
facilities as one large unit.  All four areas were using a two aeration basin,  three clarifier com-
bination and were step loading the sewage to the aeration basins.  Sewage could be introduced at four
gates along the aeration basin:  Gate A at the head end of the tank, Gate B  approximately one-fourth
of the length from the head of the basin, Gate C approximately one-half the  length from the head of
the basin and Gate D approximately two-thirds of the length of the tank from the head of the basin.
Metro Denver personnel were loading one-half of the sewage at Gate B and one-half at Gate C.  Return
sludge was introduced at Gate A.
    A short summary of the major operational changes made in each area will  be described below.  The
majority of the operational changes were made to determine the operational mode which would allow
maximum removal of TSS and BODg and would improve the sludge characteristics to facilitate sludge
handling.
    1.  Area #1 was operated using two aeration basins and three clarifiers  throughout the project,
        except for a short time (one week) when one of the final clarifiers  was inoperable.  Only two
        aeration basins were used since the third aeration basin was required to remove the excessive
        grease received at the plant.  This area was operated using step loading (one-half flow at
        Gate B and one-half at Gate C) from the start of the project until January 5, 1970, when
        loading was converted to introducing all the flow at the head of each aeration basin (Gate
        A).  This loading procedure was used until the end of the project.  All the return activated
        sludge was introduced at Gate A.
    2.  Area #2 was operated in a manner similar to Area #1.  However, Area #2 was converted to
        loading all sewage at Gate A on December 12, 1969.  Performance in Area #2 was generally
        superior to that of Area #1 throughout the project.  Although the meters didn't indicate a
        difference, it appeared as though Area #2 was  receiving less flow than Area #1.  It was
        attempted to equalize the flow to all of the areas throughout the project.  However, this was
                                                  11

-------
        difficult  to  achieve because of the  plant's hydraulics and, therefore, equal splitting of the
        flow to each  of the four areas  was not successful.
    3.   Area #3 was converted  to a  three  aeration basin, three clarifier basin operation within a
        week after the  project started.   All  sewage was loaded into the aeration basins at Gate A, as
        well as return  sludge.   Area #3 provided the best overall performance during the project, as
        measured by effluent BODg and TSS concentrations.
    4.   Area #4 was converted  to a  three  aeration basin, three clarifier basin operation within a
        week after the  project started.   However, a variety of methods of introducing loads was tried
        on Area #4.   Initially all  return sludge was introduced  at Gate A and the loading of one-half
        the sewage flow to Gate B and Gate  C was maintained.  However, this was changed to loading all
        the sewage at Gate D on November  12, 1969.   (Contact  stabilization)  This loading was main-
        tained until  December  12, 1969  when  all sewage was introduced at Gate A.  Area #4, at times,
        showed excellent reductions but the  area was generally sporadic in its performance because of
        difficulties  in retaining the sludge in the  final clarifiers.
    The major operational  changes above were affected  by a variety of operational problems.  Unreli-
able meter readings  on the waste sludge flow, uneven  flow distribution to the various areas, mechani-
cal failure of three  clarifiers during  the  project,  and a continual  problem with solids "flushing" out
of the final clarifiers are but a few of the operational problems that added to the complexity  of the
project.

E.  Control of Sludge Characteristics   -   Procedures  and Results
    The two major problems encountered  at Metro  Denver were  the  "flushing" of solids that occurred
out of the final clarifiers and the sludge  processing  and handling problem.  Since  the  initial
emphasis was to work in the secondary  treatment  portion of the  plant,  improving  removal efficiencies
and effluent quality became primary considerations  in  operating  the  facility.   However, a high
quality effluent representing increased removals  of BOD5  and TSS also  is  associated with  increased
sludge production, which served to magnify the sludge processing and handling  problems.   To  compensate
for the increased sludge production accompanying the increased  treatment  efficiencies an  attempt was
made to develop a sludge that would concentrate or dewater  better than  previous  sludges.  The end
result would be a lesser volume but increased mass  of sludge being removed  from the system.
    At Metro Denver, the waste activated sludge is  further  concentrated  by  the  use  of chemical
coagulants  in air flotation units.   Therefore, it was also  attempted to  develop a  sludge  more  amenable
to chemical coagulation.
    Figure 4 illustrates the concentration of sludge wasted  from the secondary treatment  process.  No
data on the waste sludge total suspended solids concentration are available  for the early phases of
                                                  12

-------
the project.  Consequently, no comparison Is  made of the overall  changes  In waste sludge concentra-
tions for the entire project period.   The trends  developed for the  period of  record are shown in
Figure 4.  A decrease in waste sludge concentration was  initially noted paralleling the operational
difficulties encountered with Areas #1, #2 and #4 in December (See  IV-D above).  Later in the project
(January and February) the waste sludge concentration increased steadily  to a weekly  average of
approximately 7,000 mg/1, representing a substantial increase over  the low weekly average of 4,500
mg/1 experienced during the last week of December.   Figure 4 indicates that one  of the goals in con-
trolling sludge characteristics, that of increased waste sludge concentration, was achieved.  However,
the benefits derived from increasing the waste sludge concentration were  partially overshadowed by the
increased sludge production resulting from increased removal efficiencies of  BODg.
                                                  13

-------
   Si
g
o

h-
111
U
z
o
3>
   2-
                             •  DAILY CONCENTRATION


                             O  WEEKLY AVG. CONCENTRATION
                                                                                                   FIGURE 4


                                                                                           FEDERAL ASSISTANCE PROJECT
                                                                                   METROPOLITAN DENVER SEWAGE TREATMENT PLANT
                                                                                        OCTOBER-I%9  to FEBRUARY - 1970


                                                                                    WASTE SLUDGE CONCENTRATION IN MG /L vs TIME
      17 NOV., '69-
                     1DEC.
                                                 T!
                                                       JAN.
                                                                                        1 FEB.
TT
                                                                                                                       1 MARCH.

-------
V.  DATA ANALYSIS
    Tlie objective of the assistance project was to operate the activated sludge process so that the
waste sludge characteristics could be controlled, thereby alleviating at least a portion of the
sludge handling problems.  While trying to achieve this goal a large amount of data were collected.
At the conclusion of the project portions of these data were analyzed to further evaluate the major
problems encountered at the Metro Denver plant, namely the sludge handling problem associated with
sludge produced in the activated sludge process and the problem of solids loss from the final
clarifiers.
    Certain portions of the data obtained during the project were selected so that smaller and more
workable portions could be investigated.  It was decided to evaluate only Areas n and #3, since
these two areas covered most of the operational modes investigated and demonstrated the best
response to operational controls.  Area #2 was operated with both step loading and conventional
loading and with two aeration basins in combination with the three clarifiers.  Area #3 was operated
with three aeration basins in combination with the three final clarifiers.  Both Areas #2 and #3
gave the most consistently good quality effluents and responded favorably to operational controls.
A.  Analysis of Sludge Production
    The sludge handling problems at the Metro Denver plant were affected by the amount of sludge
produced in the secondary unit.  To evaluate the sludge production per pound of 8005 removed, an
application of the kinetic model which has been used and frequently outlined in the literature to
describe biological treatment systems was used.  Papers by Lawrence and McCarty (2), Jenkins and
Garrison (3), Pearson (4) and McKinney (5) are a few that have discussed and presented the kinetic
model.  The assumptions made in relating the data collected during the project to the analysis made
using the kinetic model are outlined in a sample calculation presented In Appendix C.
    Since the kinetic model has been well documented in the literature, the following equations will
be used without a formal presentation of their theoretical basis.

                   Basic Kinetic Equations
                   q = F(S0 - ST)  =  Substrate removal rate                   Equation 1
                           X-|V
v -
                            F*2 * HX|r                                          Equation 2
                               vxl
                   v = Yq * Specific Growth Rate                               Equation 3
                           IIV.
                                    Mean cell residence time                   Equation 4
                        FX2
                   l/ec = Yq - Kd =   2   * r = Net growth rate                Equation 5
                                       v*l
                                                  15

-------
                  WHERE:
                        q = substrate removal rate, pounds of substrate removed per pounds of cells
                            in the system per day
                       S0 = influent substrate concentration
                       S-j = effluent substrate concentration
                        F = influent flow rate
                       X] = MLSS  or MLVSS concentration
                        V = volume of aeration plus secondary sedimentation basins
                        v = specific growth  rate, pounds of cells produced per pounds of cells in
                            the system  per day
                        Y = yield coefficient, pounds of cells produced per pounds of substrate
                            removed
                       Kd = endogenous  decay coefficient,  pounds of cells lost per pounds of cells
                            in system per day
                       X- = effluent TSS or  VSS  concentration
                        W = waste sludge flow
                       Xr =  return sludge and waste  sludge TSS or VSS  concentration
                        e  = mean  cell  residence  time (sludge age), days = pounds  of  cells in system
                             per  pounds  of cells  lost from  system per day

    To derive a kinetic description of  a particular waste source  requires  the  development  of a
series of steady state conditions.  In  other words, the  rate of change  of  substrate  removal  with
time is assumed to be zero.   Although  steady  state is never achieved  in a  large  dynamic  activated
sludge plant such as Metro  Denver's, certain  periods  of operation approach this  condition.   For
Areas #2 and #3 time periods were selected based on uniformity of aeration basin  solids  concentra-
tion and of sludge settling  and concentration characteristics.  The  uniformity of these  characteris-
tics best described a period of "steady state."   Table 1  summarizes  briefly  the  periods  selected  and
the average of selected parameters for each  period.
    The reciprocal of the mean cell residence time (ec)  is  the  net  growth  rate.   Equation  5, above,
outlines the relationship between the net growth rate (l/ec)  and  the substrate removal  rate  q.
These values are related by the yield coefficient (Y) and the  endogenous respiration coefficient
(Kd).  For normal domestic wastes, values for Y and Kd have been  determined.   Heukelekian, Oxford
and Manganelli  (6) have presented values of Y = 0.5 milligrams  volatile suspended solids produced
per milligram of waste (BODg) removed and values of Kd = -0.055 as  being representative, while
Middlebrooks and Garland (7) have presented values of Y = 0.67 milligrams volatile suspended solids
                                                  16

-------
                                              TABLE  1
                                    FEDERAL  ASSISTANCE  PROJECT
                            METROPOLITAN DENVER SEWAGE  TREATMENT  PLANT
                                  OCTOBER 1969   -   FEBRUARY  1970-
                            A Suirmary Of Various  Parameters  Associated
                             With  The Selected "Steady  State"  Periods
• Parameter-Average For Period
Influent Flow - MGD
Return Sludge Flow - MGD
Waste Sludge Flow - MGD
Aeration Tank Concentration (ATC)
% Volume Concentration by Centrifuge
Return Sludge Concentration (RSC)
% Volume Concentration by Centrifuge
Ratio TSS/ATC *
Ratio VSS/TSS *
Influent (To Secondary) 8005
Concentration - mg/1
Effluent BODs Concentration - mg/1
Effluent TSS Concentration - mg/1
AREA #2
1/5/70
to
1/11/70
25.62
13.85
.611
2.96
8.27
706
0.804
197
45
68
1/29/70
to
2/12/70
27.78
11.50
.262
4.46
14.89
585
0.811
197
24
36
AREA #3
12/15/69
to
1/5/70
29.64
14.41
.593
3.71
12.00
616
0.840
188
21
40
1/10/70
to
1/13/70
29.85
11.77
.490
1.36
4.61
817
0.846
194
36
44
1/20/70
to
1/25/70
26.30
23.00
.458
5.44
13.19
482
0.793
199
37
79
2/9/70
to
2/16/70
29.47
13.01
.445
3.92
14.05
684
0.782
207
13
26
* The relationship between % volume concentration by centrifuge and TSS and VSS was established
  by comparing results conducted on grab samples  -  normally daily grab samples.
                                                17

-------
produced per milligram of waste (BODg) removed and values of Kd = -0.048.
    The value of Y (slope) and Kd (intercept) can be graphically determined by determining the value
of ec (Equation 4) and q (Equation 1) and plotting 1/8C versus q.  Values  of the removal  rate (q)
and the mean cell residence time (ec) were calculated using the Metro Denver data for the selected
"steady state" periods.  (See Appendix C for example calculations)  These  data are presented in
Table 2.  Values derived for ec indicate a relatively low cell residence time.  Normal residence
times for conventional activated sludge are five to fifteen days, with a mean of ten days [See
Jenkins (3)].  When considering ec and normal values obtained for Y and q  during the period, Kd
values were not within the recognized range (i.e. -.05, -.06), which could reflect a lack of aera-
tion capacity, complete mixing, etc.
    The values of qBO|v and 1/flc determined from the project data have been plotted in Figure 5.
Also plotted is the line representing the relationship between l/ec and q  for a typical  domestic
sewage using an average of the values presented in the literature (6) (7).  (Y = 0.60 K
-------
                  TABLE 2

        FEDERAL ASSISTANCE PROJECT
METROPOLITAN DENVER SEWAGE TREATMENT PLANT
       OCTOBER 1969 - FEBRUARY 1970

     Calculated Values of ec and qBOD

       Selected Periods of Operation
              Areas #2 and #3
AREA #2
Day
Mon
Tues
Wed
Thurs
Fri
Sat
Sun

Thurs
Fri
Sat
Sun
Mon
Tues
Wed
Thurs
Fri
Sat
Sun
Mon
Tues
Wed


















Date
1/05/70
1/06/70
1/07/70
1/08/70
1/09/70
1/10/70
1/11/70

1/29/70
1/30/70
1/31/70
2/01/70
2/02/70
2/03/70
2/04/70
2/05/70
2/06/70
2/07/70
2/08/70
2/09/70
2/10/70
2/11/70


















1BOD5
Ib/lb
0.412
0.495
0.373
0.344
0.424
0.352
0.275

0.365
0.404
0.341
0.259
0.402
0.457
0.449
0.360
0.343
0.351
0.242
0.454
0.377
0.372


















6C
Days
2.533
2.160
2.510
4.263
2.736
3.128
3.947

6.514
6.250
6.714
6.750
6.706
7.586
5.409
5.261
5.311
5.273
4.818
4.952
5.561
6.053


















1/8C
Days-1
0.395
0.463
0.400
0.235
0.365
0.320
0.253

0.154
0.160
0.149
0.148
0.149
0.132
0.185
0.190
0.188
0.190
0.208
0.202
0.180
0.165


















AREA #3
Day
Mon
Tues
Wed
Thurs
Fri
Sat
Sun
Mon
Tues
Wed
Thurs
Fri
Sat
Sun
Mon
Tues
Wed
Thurs
Fri
Sat
Sun
Mon
Sat
Sun
Mon
Tues
Tues
Wed
Thurs
Fri
Sat
Sun
Mon
Tues
Wed
Thurs
Fri
Sat
Sun
Mon
Date
12/15/69
12/16/69
12/17/69
12/18/69
12/19/69
12/20/69
12/21/69
12/22/69
12/23/69
12/24/69
12/25/69
12/26/69
12/27/69
12/28/69
12/29/69
12/30/69
12/31/69
1/01/70
1/02/70
1/03/70
1/04/70
1/05/70
1/10/70
1/11/70
1/12/70
1/13/70
1/20/70
1/21/70
1/22/70
1/23/70
1/24/70
1/25/70
2/09/70
2/10/70
2/11/70
2/12/70
2/13/70
2/14/70
2/15/70
2/16/70
iBODs
Ib/lb
0.592
0.483
0.606
0.629
0.492
0.299
0.217
0.408
0.407
0.323
0.271
0.351
0.276
0.220
0.304
0.252
0.285
0.187
0.312
0.276
0.305
0.443
0.956
0.658
0.902
0.512
0.366
0.325
0.207
0.290
0.224
0.166
0.348
0.330
0.339
0.354
0.307
0.354
0.302
0.458
ec
Days
1.72
2.03
2.29
2.59
3.38
3.78
3.50
2.94
3.53
3.84
4.75
3.88
3.44
3.51
11.42
3.17
2.59
3.66
3.40
2.31
2.84
2.27
2.02
4.94
5.62
6.22
6.66
5.09
2.98
7.55
2.97
2.36
2.70
3.68
3.75
4.38
4.75
4.29
4.24
4.88
V8C
Days-1
0.581
0.493
0.437
0.386
0.296
0.265
0.286
0.340
0.283
0.260
0.211
0.258
0.290
0.285
0.088
0.315
0.387
0.273
0.294
0.433
0.352
0.441
0.495
0.202
0.178
0.161
0.150
0.196
0.336
0.132
0.338
0.424
0.370
0.272
0.267
0.228
0.211
0.233
0.236
0.205
                     19

-------
         0.9
   1
i
 s
         0.8-
         0.7-
0.6-
    e    0.5-
    = i  0.4-
         0.3-
         0.2-
0.1-
         .0. r'
                                                    0     /
                                                  •   S        .v*
                                                                                                           FIGURE 5
                                                                                                   FEDERAL ASSISTANCE PROJECT
                                                                                           METROPOLITAN DENVER SEWAGE TREATMENT PLANT
                                                                                                 OCTOBER 1969 TO FEBRUARY 1970
                                                                                                              NET GROWTH RATE (%c)
                                                                                                                      VS
                                                                                                          SUBSTRATE REMOVAL RATE (qBODs)
                                                                                                              • AREA-3
                                                                                                              O AREA - 2
            0.1
                              0.2       0.3
0.4      0.5       0.6       0.7


    SUBSTRATE  REMOVAL RATE   4BOD,
 •
0.9
0.8       0.9       1.0       1.1

  Ib. BOD5  REMOVED PER DAY
                                                                                          Ib. VSS IN SYSTEM

-------
sludge produced In the secondary would have been 82,800 pounds per day.   To maintain a specific cell
residence time (sludge age), this amount of sludge should have been wasted.  If the estimated yield
coefficient Y » 0.72 (See Figure 5) 1s used. 99.300 pounds per day would have been produced and
would have had to be wasted.  These values are dally average values and do not represent the peaks
in loading and sludge production that occur.  Both values are less than the 131,000 pounds per day
which was the design basis for the Metro Plant secondary sludge handling facilities.  Although  this
design loading was not exceeded on an average basis, problems did occur with the sludge handling
facilities (i.e. concentrators and incinerators).

B.  Analysis of Secondary Clarlfiers
    Eckenf elder and O'Connor (8) have stated that the size of secondary clarlfiers In biological
systems Is.related to three design factors.  These factors are:  (1) The permissible retention of the
settled sludge 1n the basin as dictated by Its biological properties, (2) The area required fo'r
clarification over the operating mixed liquor suspended solids range, and (3) The area and volume
requirements to produce by thickening an underflow of a desired concentration.
    At Metro Denver sludge retention In the final claHfiers should be minimized; possibly to one
hour or less.  The value of the sludge detention time, SDT, 1n the final clarifiers was determined
during the project on a daily average basis and normally was easily controlled by adjusting-the
return sludge pumping rates.  This fact Implies that the volume of the clarifiers and the .return
sludge pumping capacity was generally satisfactory to allow rapid removal of the' sludge.
    The clarification and thickening capacities for a secondary clarlfler can be estimated from
                                                                                        ,1 •
batch settling tests.  A great number of batch settling tests were conducted during the project, and
these results were used to evaluate the clarification and thickening capacities of the Metro Denver
plant.
    The limitation of this  type of analysis 1s in the determination of a representative batch
settling  test.  The previously selected "steady state" periods for Areas #2 and #3 were selected for
analysis.  These  periods were Initially selected based on uniformity of sludge settling and sludge
concentration  characteristics, as  well as  uniformity of solids concentration.  In addition, these
periods were generally the  best  periods of control and operation and therefore were representative
of sludge settling characteristics that were experienced during the project.
    During most of the project four batch  settling tests were  conducted on  a dally  basis  at 5:00 A.M.,
9:00  A.M., 1:00 P.M. and 9:00 P.M.  Values for settled sludge  volume for each hourly  test were
averaged  for the  various  "steady state" periods.  These  values are presented 1n Table 3.   Table 1
gives the associated average parameters and average  flow  values for these  same periods.   The period
January  10,  1970  to January 13,  1970  for  Area #3 was omitted  from  this  analysis because of the  low
mixed liquor solids concentration  and  resulting  rapid settling.
                                                   21

-------
                  TABLE 3
        FEDERAL ASSISTANCE PROJECT
METROPOLITAN DENVER SEWAGE TREATMENT PLANT
      OCTOBER 1969  -  FEBRUARY 1970
    Average Settled Sludge Volumes For
          "Steady State" Periods
Area and "Steady
State" Period

n

January 5, 1970
to
January 11 , 1970
#2

January 29, 1970
to
February 12, 1970
#3

December 15, 1969
to
January 5, 1970
#3

January 20, 1970
to
January 25, 1970
#3

February 9, 1970
to
February 16, 1970
Settling
Time (Min)

5
10
20
30
60
5
10
20
30
60
5
10
20
30
60
5
10
20
30
60
5
10
20
30
60
Average Settled Sludge Volumes for
"Steady State" Period - cc/1
5:00 A.M.
496
346
261
224
171
666
489
403
343
276
805
660
510
431
320
922
870
742
642
480
541
413
334
294
238
9:00 A.M.
523
383
279
239
184
737
545
433
376
301
855
725
585
495
360
953
914
828
717
542
604
476
382
335
264
1:00 P.M.
424
286
211
179
144
453
332
261
228
184 '
650
521
408
347
260
903
752
582
482
367
470
368
294
259
207
9:00 P.M.
517
332
246
213
161
.617
452
362
320
249
677
523
401
. 348
265
936
829
598
489
381
539
421
337
308
237
                     22

-------
    The clarification capacity required In a clarlfler can be estimated from the Initial  rate at
                        /
which the solIds liquid Interface subsides as outlined by Eckenfelder (8), Rich (9)  and Smith and
Loveless (10).  The zone settling rate (Vs) can be calculated by determining the slope of the Initial
straight line portion of the sludge settling curve.  This settling rate-can then be  expressed as the
equivalent surface overflow rate since solids will be lost 1n the plant effluent 1f  the settling rate
is exceeded by the clarlfler overflow rate.

                   Or • V  x 7.5 gallons per cubic foot x 24 hours per day
                    r    s                                                     Equation 6
                      = Vs x 180
                   WHERE:
                        Or = Equivalent Surface Overflow Rate (gal/sq ft/day)
                        Vs = Zone Settling Rate (ft/hr)
    Curves were drawn from each set of average settled sludge volume values for the  selected periods.
The slope of the Initial straight line portion of the curve was determined and thus  the zone settling
rate (V.) was established.  An example determination of V, Is shown In Figure 6.  The values of the
       d                                                 9
zone settling rates (V$), as well as the associated equivalent overflow rates (Or),  are shown 1n
Table 4.
    The zone settling rate (V$) varied throughout the "average" day for the selected periods.  This
Is to be expected since the zone settling rate Is a function of the Initial MLSS concentration and of
the loading rate, I.e. pounds of BOD per pounds of MLSS.  [Smith and Loveless (10)].  Flow variations
throughout the day caused the MLSS and the loading rates to fluctuate, causing the observed varia-
tions In the values of Vs.  No attempt was made to distinguish between the portion of the change 1n
Vs due to changing load and that due to change of Initial MLSS concentration or 1n response to any
possible variances 1n growth rates.  In addition, as mentioned earlier, cell residence time seldom
exceeded five to six days.  Associated effects on settleabillty were also not separable.
    It 1s shown 1n Table 4 that the maximum zone settling rate normally occurred at the 1:00 P.M.
test.  However, It was observed that this was also the time of the day when most of the solids
flushing occurred.  Table 4 shows the calculated overflow rates based on the dally average flow for
each area during the periods.  Each area at Metro Denver had three 130 foot diameter secondary
clarlflers which gave a total surface overflow area of 39,900 square feet.  Generally the 1:00 P.M.
equivalent surface overflow rates exceeded the average clarlfler overflow rates for the periods
Investigated.  However, this 1s based on maximum zone settling rates compared with average clarlfler
overflow  rates.   If the maximum flow Is assumed to occur at 1:00 P.M. and the design ratio of
l"averagehday1raSte a 2 ^See Hennlngson, Durham and Richardson (11)] Is applied to the clarlfler
overflow  rates, then In every case the equivalent surface overflow rate derived from Vs values at
                                                  23

-------
                    FIGURE 6

           FEDERAL ASSISTANCE PROJECT
   METROPOLITAN DENVER SEWAGE TREATMENT PLANT
          OCTOBER. 1969 - FEBRUARY. 1970

     DETERMINATION OF ZONE SETTLING RATE ( Vs )

        HEIGHT OF SLUDGE INTERFACE vi TIME

     AREA #3  PERIOD: 2/9-2/16/70  AVG.9:OOAM
15         20
  SETTLING TIME
  25         10
( MINUTES )
           24

-------
                                        TABLE 4
                              FEDERAL ASSISTANCE PROJECT
                      METROPOLITAN DENVER SEWAGE TREATMENT PLANT
                            OCTOBER 1969  -  FEBRUARY 1970
                    Zone Settling Rates  (Vs) And Equivalent Surface
                    Overflow  Rates  (Or)  For "Steady State" Periods
Area and "Steady
State" Period
n
January 5, 1970
to
January 11, 1970
#2
January 29, 1970
to
February 12, 1970
#3
December 15, 1969
to
January 5, 1970
#3
January 20, 1970
to
January 25, 1970
#3
February 9, 1970
to
February 16, 1970
Zone Settling Rates (Vs)
- ft/hr and Equivalent Surface Overflow Rates (Or) -
gpsfd for "Steady State" Periods *
5:00 A.M.
3.43
620
1.72
310
1.13
204
<1
<180
3.00
544
9:00 A.M.
6.80
595
1.45
262
0.88
159
<1
<180
2.70
488
1:00 P.M.
3. '30
1,225
4.93
890
2.72
490
<1
<180
6.00
1,080
9:00 P.M.
3.83
690
3.03
546
2.53
456
<1
<180
3.24
585
Daily Average
Overflow Rate
For "Period"
gpsfd
644

698

744

660

740

Vs values are given on top and Or values on bottom.
                                            25

-------
1:00 P.M. is exceeded by the clarifier overflow rate and flushing of solids  could be  expected to
occur.  Additionally, a portion of this flushing may be attributable to the  normal  high  return sludge
pumping rates that were utilized in the operational controls.
    This problem was further aggravated by locating the effluent weirs for the 130 foot  diameter
clarifiers at the outer edge of the clarifiers.  This allowed  localized high upflow velocities to
occur in the final clarifiers.  These localized high velocity  currents could have been avoided if
weir placement had been such that more of the surface area in  the final clarifiers was developed  to
provide a more uniform upflow velocity.  However, even if the  additional weirs were located to
develop more of the surface area of the final clarifiers, the  data shown in  Table 4 indicates that
problems with flushing of solids still could occur.
    Therefore, either more surface area must be provided or the settling characteristics must be
altered such that the zone settling rate is increased (i.e. a  faster settling sludge}.  The zone
settling rate is dependent upon the initial MLSS concentration and the loading rate (which directly
affect the sludge flocculation characteristics).  [See Eckenfelder (8) and Smith and  Loveless (10)]
These factors are dependent upon the influent flow rate, which is highly variable and therefore makes
a positive control of the zone settling rate difficult to achieve.  For ease of operation it appears
that more effective surface area, which is better developed by weir placement, is required at Metro
Denver to provide adequate clarification capacity.
    The thickening capacity required in a final clarifier can  also be estimated from  a batch settling
test (8) (9).  The average 1:00 P.M. settling test (See Table  3) was selected for analysis since  this
time was assumed to coincide with normal daily peak flows which are approximated by twice the average
daily flow (11).  The most rapid 1:00 P.M. zone settling rate  (See Table 4)  was selected to determine
a desired thickening capacity since the value determined would represent a minimum thickening area
required,  (i.e. any settling rate with a lesser value would require more thickening  area.)  The  peak
zone settling rate for Area #2 at 1:00 P.M. was 4.93 feet per hour and for Area #3 it was 6.00 feet
per hour.  (See Table 4)
    Rich (9) outlines an equation for determining the thickening area required:
                       1TU
                   A = yi-ii                                                     Equation  7
                       * o
                   WHERE:
                          A = cross section required to obtain a layer of a  desired concentration
                              -- ft2
                          q = flow rate of the mixed liquor entering the final clarifier -- ftVsec.
                                                   26

-------
                        Z'0 = initial height of the interface in the settling column - feet (The
                              settleometers used at Metro Denver for the batch settling tests had a
                              0.5 feet depth.)
                         TU = settling time required to attain a desired underflow concentration -
                              sec. [This value is obtained from a graphical  analysis of a sludge
                              settling curve as outlined by Eckenfelder (8)  and Rich (9).]
    To complete the analysis of thickening capacity a desired underflow concentration must be
selected.  At Metro Denver the design values for underflow concentration expected ranged between
5,000 to 15,000 mg/1.  Therefore, a desired underflow concentration of 10,000 mg/1 was selected.
    The settling time (Tu) required to obtain a 10,000 mg/1 underflow concentration for Area #2 for
the selected period January 29 to February 12, 1970 (Vs = 4.93) was determined by a graphical
analysis of the sludge settling curve.  This value was used with the average flow for the period to
determine by Equation 7 the area required for thickening.  For average flows 42,500 ft2 would be
required for thickening while for peak flows 85,450 ft2 would be required.  A similar analysis con-
ducted on Area #3 for the selected period (February 9 to February 16, 1970)  showed required areas of
114,000 ft2 and 57,000 ft2 at peak and average flow rates respectively.
    The available surface area in Areas #2 and #3 is 39,900 ft2.  This is not adequate to provide the
thickening area required to achieve a 10,000 mg/1 underflow concentration with the type of sludge
obtained during the project.  The above analysis also indicates the implications of limited thicken-
ing capacity on sludge handling problems.  Without sufficient thickening capacity a more dilute waste
sludge flow concentration is realized.  The effect of the dilute concentrations is shown by the
relative differences in total sludge volumes to waste 100,000 Ibs. of solids as summarized in Table
5.
    The preceding materials were developed to compare actual performance results with the batch
settling data.  Most importantly, Rich (9) describes the numerous departures of actual sedimentation
basin performance from that of ideal basins.  "The net effect of all the factors that contribute
toward reducing the efficiency of sedimentation in an actual basin is to decrease the clarification
rate and to increase the detention time over that derived from a batch analysis.  For the sedimenta-
tion of flocculent particles from dilute suspensions the overflow rate generally will be decreased by
a factor of 1.25 to 1.75 and the detention time will be increased by a factor of 1.50 to 2.00.  In
scaling-up thickening operations, a factor of 1.0 to 2.0 is applied to the area required for clarifi-
cation (hindered settling) and a factor of 1.0 to 1.5 to that required for thickening."
    Results of the Metro Denver settleability testing should be judged in this light and with the
reported values of loading, residence times, etc. obtained during the period.
                                                  27

-------
                  TABLE 5
        FEDERAL ASSISTANCE PROJECT
METROPOLITAN DENVER SEWAGE TREATMENT PLANT
      OCTOBER 1969  -  FEBRUARY 1970
   Waste Sludge Flow Required To Remove
    An Equivalent Amount Of Solids With
     Varying Underflow Concentrations
Underflow Concentrations ~ mg/1
Waste Volume to Remove
100,000 Lbs. of Solids - Gal.
5,000
2,400,000
10,000
1,200,000
15,000
800,000
                     28

-------
VI.  SUMMARY AND CONCLUSIONS
    One of the objectives of the project was to Instigate additional  process  control  testing  for  the
secondary treatment (activated sludge) portion of the Metro Denver plant.   Plant  personnel were
trained to conduct process control  tests on a routine basis, to evaluate  and  graph  various selected
parameters, and to interpret these data so that adequate daily operational  changes  could be made.
The full beneficial effect of these process controls was not realized because of  various problems
encountered with plant operation, as outlined below:
    1.  Adjustment of flow to each aeration basin was difficult because each  basin  was  fed by a gate
        opening from a common channel.  Balancing the hydraulic effects of ten gates  to achieve equal
        flow to each of the four areas required a great deal of attention.  After the gates were
        adjusted, determination of actual flow to each aeration basin was  questionable  because of
        occurrences of unreliable instrument readings.
    2.  Two of the twelve aeration basins provided in the secondary portion of the  plant were used as
        grease flotation units to remove grease from the influent waste stream and  were thus  unavail-
        able for use as a portion of the activated sludge process.  This  becomes  important since  the
        average loading to the secondary during this investigation was 161,560 pounds of BOD   per day,
        which is approaching the design loading of 166,350 pounds of BOD   per day.
                                                                       *)
    3.  The rate of wasting sludge was difficult to control on a continuous basis because the meters
        and control instruments frequently gave erroneous readings.  Several  times  it was discovered
        that actual flow and meter readings differed by as much as 100 percent.  This definitely
        effected the ability to establish a process balance.
    4.  No reserve capacity was available for final clarification.  When  a clarifier broke down
        (three clarifiers broke down during the project) solids were carried  over in the plant
        effluent, the effluent quality was degraded, and the process balance  in the affected  area was
        impaired.
    Other difficulties encountered were the sludge production in the secondary treatment process  and
the flushing of solids from the final clarifiers into the effluent.
    The initial emphasis in dealing with the problems at Metro was to control the secondary  treatment
portion of the plant.  Therefore, removal efficiencies and effluent quality became  important  consider-
ations in operating the facility.  Unfortunately, a high quality effluent representing  increased
removals of BOD5 and TSS is associated with increased sludge production,  which served to antagonize
                                                                          •
the sludge processing and handling problem.  To compensate for the increased  sludge production that
accompanied the slightly increased removals achieved during the project and to relieve  the existing
sludge problem, an attempt was made to develop a sludge that would concentrate or dewater better  than
                                                   29

-------
 previously.   This would  have  allowed  a  lesser volume of a more dense sludge to be wasted.  Average
.concentrations  of 6,900  to  7,000 mg/1 were obtained in the waste sludge flow toward the end of the
 project.   However,  the benefits derived  from increasing the waste sludge concentration were not
 realized because of the  increased  removal efficiencies and the resulting increase in the amount of
 sludge  produced.
     Although  slightly greater BOD  and suspended solids removal efficiencies were realized through
 operational controls, little  was accomplished to alleviate the sludge handling problems at the plant.
 It is hoped that the increased removal efficiencies will be maintained and the sludge handling proce-
 dures modified  to alleviate these  difficulties.  An investigation of the sludge production character-
 istics  at  the Metro plant to  compare them with presently available sludge handling facilities was
made.
     A kinetic model was  applied to the collected data to determine the microbiological character of
the  waste  stream.   At Metro Denver the results of this analysis indicate that the characteristics of
the  waste  received  at the Metro Denver plant do not deviate significantly from those expected from a
typical domestic waste.  An attempt was made to determine the amount of sludge production and to com-
pare these results  with  the sludge handling capacities at the plant.  The results indicate that the
design  sludge handling capacity (131,000 pounds per day of secondary sludge) could be exceeded during
peak loading periods.  It is  important when sludge handling procedures or facilities are modified at
Metro Denver that the sludge  production during peak loading periods be considered in the design
criteria.
     The second major operating difficulty evaluated was the flushing of solids that occurred from the
final clarifiers.   Representative zone settling rates were determined for the sludge at Metro Denver
based on the numerous batch settling test data obtained.   From this analysis it was determined that
the  clarification capacity of the final clarifiers at the Metro Denver plant was not adequate for
the  selected periods of  investigation.  The type of sludge developed proved to have a zone settling
rate (Vs) that was  too slow to be held in the final  clarifiers.  A portion of the flushing problem
was  also attributed to the large diameter (130 feet) final clarifiers which had effluent weirs
located at or near  the outer periphery.   This weir placement allowed excessive velocity currents to
develop further aggravating the solids "flushing" problem.  This  problem can be alleviated by a
different weir placement arrangement that allows a more uniform use of the surface area on the final
clarifiers.  (i.e.  another launder of weirs located nearer the center of the tank.)
     It was also determined that the thickening area requirements  of the final  clarifiers were not
adequate to obtain a 10,000 mg/1  underflow concentration  with the type of sludge developed during the
project.
    Two alternatives can be used to change the effects  of the slow zone settling rates of the sludge.
                                                  30

-------
The first is to increase the clarifier surface area to reduce overflow rates to less than the settling
velocity established by the zone settling rate.  This would provide additional  thickening area at the
same time.  The second approach would be to increase the zone settling rate of the sludge at the Metro
Denver plant.  The zone settling rate is a function of the MLSS concentration and the loading rate.
Because of the constantly changing load (flow) and its effect on the MLSS concentration, it is a con-
tinuous problem to maintain a proper process balance and achieve a desired zone settling rate.
                                                   31

-------
VII.   RECOMMENDATIONS
    The following recommendations are made:
    1.   It is recommended that control testing established during the Federal  Assistance  Project  be
        continued.
    2.   An effort should be made at the Metro Denver plant to assure  the  accuracy  of all  metered
        values in order to adequately use control  testing procedures.
    3.   It is recommended that Metro Denver  be considered for demonstrating various  comparisons.
        Because of the unique arrangement of facilities at the Metro  plant, four areas  with  an  iden-
        tical influent waste are available for evaluation.  This arrangement is  ideal  for conducting
        comparisons of various types of equipment (i.e. provide various  types  of aeration equipment,
        evaluate effects of different skimmer arrangements on final  clarifiers,  evaluate  different
        weir placement patterns on final clarifiers, etc.).
    4.   The Metro Denver plant should be operated to achieve the maximum possible  reduction  of  waste
        pollutants.  To operate and achieve  these high removal efficiencies, modifications to the
        sludge handling procedures or facilities must be made.  Any  modification of  the Metro Denver
        sludge handling facilities should take into account the sludge production  characteristics at
        the Metro Denver plant which are apparently similar to those  of typical  domestic  sewage and
        the clarification-thickening capacity requirements of the secondary clarifiers.
    5.   Properly located additional weirs are recommended on the secondary clarifiers to  develop  a
        more uniform distribution of flow over the surface area provided in the  relatively large
        diameter final clarifiers.  Surface  skimmers are also recommended.
    6.   Additional  clarifier surface area with proper weir placement is  recommended  or the sludge
        settling characteristics must be altered by operational control  in order to  assure that
        solids will not be flushed into the  final  effluent.   Additionally, increased area would
        appear to improve sl.udge thickening, thereby reducing waste  sludge volumes.   More reliable
        control would also be obtained by increased clarifier surface area.
                                                  32

-------
VIII.  APPENDICES
       Appendix A  -  A Resolution:  "Concerning the Federal Government's Responsibilities in
                      Constructing and Operating Sewage Disposal Facilities."
       Appendix B  -  References
       Appendix C  -  Determination of Substrate Removal Rate (q) and Net Growth Rate  (l/ec)

-------
              APPENDIX A
 A RESOLUTION ADOPTED BY METROPOLITAN
DENVER SEWAGE DISPOSAL DISTRICT NO.  1'S
          BOARD OF DIRECTORS

               ENTITLED

 "Concerning the Federal Government's
 Responsibilities in Constructing and
 Operating Sewage Disposal  Facilities"

             July 11, 1969

-------
                                            A RESOLUTION
                      (CONCERNING THE FEDERAL GOVERNMENT'S RESPONSIBILITIES IN
                       CONSTRUCTING AND OPERATING SEWAGE DISPOSAL FACILITIES)
    WHEREAS, the federal government has enacted water pollution control  legislation which  makes  it
incumbent upon states to establish stream quality limits, or to be subjected to stream quality stan-
dards as dictated by the federal government itself, and
    WHEREAS, the water pollution legislation adopted by the State of Colorado is not  consistent  but
rather relates to stream classification, based upon an evaluation of each stream's individual
characteristics, and
    WHEREAS, the evaluation process for stream classification relates to a multitude  of factors
other than the consideration of protection to health and the abatement of nuisance, and
    WHEREAS, sewage treatment to the extent of providing for the development of streams and  adjacent
properties into recreational areas does require an additional capital investment for  treatment
facilities, as well as substantially increasing operating and maintenance expenses thereof,  and
    WHEREAS, the arid and semi-arid regions of the western United States have additional burdens for
capital investments and operational and maintenance expenses, due to the lack of dilution  water  to
the same degree as do the other regions of the United States, and
    WHEREAS, the high degree of sewage treatment required to effect water pollution control  does
generate additions to solid wastes to be disposed of in the form of sludge, and
    WHEREAS, cities, counties and independent samitation districts in the Metropolitan Denver area
recognized in the early 1960's their financial inability as separate political  subdivisions  to meet
the strict standards being forced upon them by the national Congress and the State Legislature,  and
    WHEREAS, these independent political subdivisions banded together and created the Metropolitan
Denver Sanitation District No. 1, prevailing upon the Colorado General Assembly to adopt Colorado
Revised Statute 89-15-5 giving them authority so to do, and
    WHEREAS, property owning electorate, demonstrating their concern over the pollution threat to
the health and welfare of the total community, by a vote of 25,099 to 2,756, agreed to mortgage
their property so that bonds in the amount of $32.5 million could be issued for the construction of
a modern primary and secondary sewage treatment plant at the confluence  of Clear and  Sand  Creeks
with the Platte River, and
    WHEREAS, this plant has been constructed following review and approval  of engineering  and con-
struction plans by all required federal, state and regional agencies with these bond  moneys, supple-
mented by some federal but no state funds, to take care of residential,  commercial and industrial
                                                 34

-------
wastes with each participating political subdivision, by means of billings to users  within  their
subdivisions, paying their proportionate shares of all  operating costs, and
    WHEREAS, this multi-million-dollar plant does bring effluent dumped into the Platte River up to
water pollution control standards it does not dispose of the solid wastes resulting  from such treat-
ment for a variety of reasons not the least of which is the fact that our technology has developed a
multitude of consumer goods, paper products, garbage disposal systems and detergents, handle human
waste, and
    WHEREAS, resident property owners of Metropolitan Denver recognized their responsibilities to
take the initiative and act to abate practices which contributed to the pollution of Clear Creek,
Bear Creek, Sand Creek and other watercourses that flowed into the Platte River as well as  the
Platte River itself, and
    WHEREAS, residents and taxpayers of the various political subdivisions that are  now participating
in this metropolitan effort to eliminate a pollution problem are being taxed the maximum they can
afford to pay for sewage disposal and do not have the financial capability to pay imminent additional
operating and maintenance costs or to effect the engineering, design and capital construction
necessary to increase the efficiency of this plant so as to halt continuing pollution of our
environment;
    NOW, THEREFORE, be it resolved, that the Board of Directors of the Metropolitan  Denver Sanitation
District No. 1 hereby does petition the Congress of the United States and the appropriate federal
agencies to:
    1.  Conduct and finance extensive research to discover new techniques of handling the variety of
        waste products now being dumped into the sanitary sewers of America and being carried to
        traditional plants that do not have the capabilities of handling them.
    2.  Make available to this district a special team of scientists and engineers assembled from
        appropriate federal departments to serve as a task force to inspect the District's sewage
        disposal plant and make appropriate recommendations.
    3.  Appropriate sufficient funds so that these recommendations can be implemented, since the
        Federal government has set up the standards the District is required to meet.
    4.  Recognize that antipollution standards adopted by the  Congress and enforced by federal and
        state as well  as  local government agencies are placing unprecedented and unbearable  financial
        responsibilities on local governments  and their constituents, thus making it mandatory that
        the  Federal government assist local communities in meeting costs  involved not only in con-
        structing adequate sewage facilities but of operating  them as well.
                                                   35

-------
APPENDIX B
REFERENCES

-------
 1.  WEST, A. W.
         Case Histories:   Improved Activated Sludge Plant Performance by Operations Control  -
         Proceedings  8th  Annual  Environmental and Hater Resources Engineering Conference,
         Vanderbilt University.   1969.
 2.  LAWRENCE, A. W. and McCARTY, P.  L.
         "Unified  Basis for  Biological Treatment Design and Operation."  Journal of the Sanitary
         Engineering  Division. ASCE, Volume 96, No. SA 3, Proc. Paper 7365, 1970, pp. 757-778.
 3.  JENKINS, D.  and GARRISON, W. E.
         "Control  of  Activated Sludge by Mean Cell  Residence Time," Journal Mater Pollution Control
         Federation,  Volume  40,  No.  11, Part 1, 1968, pp. 1905-1919.
 4.  PEARSON, E.  A.
         Kinetics  of  Biological  Treatment.  Paper presented at:  Special Lecture Series  -
         Advances  in  Water Quality  Improvement, University of  Texas, Austin.  1966.
 5.  McKINNEY, R.  E.
         "Mathematics of  Complete-Mixing Activated  Sludge."  Journal of the Sanitary  Engineering
         Division, ASCE,  Volume  88,  No. SA  3, Proc. Paper 4362, 1965, pp. 45-61.
 6.  HEUKELEKIAN, H.,  OXFORD, H.  E.  and MANGENELLI,  R.
         "Factors  Affecting  the  Quantity of Sludge  Production  in the Activated  Sludge Process."
         Sewage  and  Industrial Wastes. Volume 23, No. 8, 1951, pp. 945-958.
 7.  MIDDLEBROOKS,  E.  J.  and  GARLAND, C.  F.
         "Kinetics of Model  and  Field Extended-Aeration Wastewater Treatment  Units,"  Journal Water
         Pollution Control Federation, Volume 40, No. 4, 1968, pp. 586-612.
 8.  ECKENFELDER, W. W. and O'CONNOR, D.  J.
         Biological Waste Treatment. Pergamon Press,  New York. 1961.
 9.  RICH,  L. G.
         Unit Operations  of Sanitary Engineering. John Wiley  and Sons,  Incorporated,  Publishers,
         New York, London.  1961.
10.  SMITH  and  LOVELESS
         Notes  on Activated Sludge, Lenexa.   1969.
11.  HENNINGSON,  DURHAM and RICHARDSON
         Consulting  Engineers Report. Metropolitan Denver  Sewage  Disposal  District  No.  1   -   Metro
         Plant  Expansion  Study,  Part 1   -   Immediate  Requirements.   1969.

-------
12.   WEST, A.  W.
          Listing of Abbreviations Used to Describe Activated Sludge Systems.   Lecture Presentation
          to Consulting Engineers and Plant Operators Concerning Control  Testing for Activated
          Sludge Plants Sponsored by Water Pollution Control  Division, Colorado Department of
          Public Health.   1970.
                                                 37

-------
            APPENDIX C
DETERMINATION OF SUBSTRATE REMOVAL



RATE (q) AND NET GROWTH  RATE  (1/eJ
                                 C

-------
    It is the purpose of this appendix to present a sample calculation of the determinations made of
the substrate removal rate (q) and the net growth rate (l/ec).  Throughout the sample calculation the
assumptions made in relating the data collected and analyzed during the assistance project to the
analysis made using the kinetic model will be stated.  Data obtained for Area #3 on December 15, 1969,
will be used for the presentation of the sample calculation.
A.  Determination of the Substrate Removal Rate (q)
    q = F(S° " S1J       [See Jenkins (3)]
           V)tj
    1.  Determination of F(SQ - 5j)
        WHERE:
            SQ = influent substrate concentration  -  For Metro Denver a BOD5 value based on a
                 composite sample was used to represent SQ (12/15/69 for Area #3, S  = 198 mg/1).
            S. = effluent substrate concentration  -  For Metro Denver a BOD,, value based on a
                 composite sample was used to represent S  (12/15/69 for Area #3, S. = 16 mg/1).
             F = influent flow rate (12/15/69 for Area #3, F = 34.8 MGD)  -  This value was obtained
                 from flow meters at the Metro Denver plant.
        THEREFORE:
            F = 34.8 MGD     SQ = 198 mg/1     S] = 16 mg/1
            34.8 (198-16) (8.33 Ibs/gal) = 52.760 Ibs. BOD5 removed/day
    2.  Determination of VX,
        WHERE:
             V = volume of aeration plus secondary sedimentation basins
            X  = MLSS or MLVSS concentration
        NOTE:
            VX-| is a number representing the total pounds of cells in the system.  Normally in
            determining this value mixed liquor suspended solids concentrations by weight are used
            (Xj).  Instead of MLSS concentrations, sludge concentrations were obtained on a percent
            volume basis by using the centrifuge.  During most of the project, however, daily rela-
            tionships between percent concentration of sludge by volume and concentration by weight
            were determined on the basis of a grab sample.  These comparisons varied from 1% =
            500 mg/1 TSS to 1% = 1,000 mg/1 TSS.  However, during "steady state" conditions, the
            relationship between spin concentrations and mg/1 remained fairly constant.  Therefore,
            the average of the relationship between spin concentrations and mg/1 for each "steady
            state" period selected was determined and used to convert the spin concentration to
                                                  38

-------
    mg/1 of total suspended solids.  The relationship between total  suspended solids (TSS)
    and volatile suspended solids (VSS) was also obtained from the analysis of daily grab
    samples.   The average ratio of VSS/TSS for each "steady state" period was determined.
    For December 15, 1969, and the associated "steady state" period the average relationship
    between volume or spin concentrations and mg/1 was 1% = 616 mg/1 TSS for Area #3 and the
    average VSS/TSS ratio was 0.840.   Another refinement was also used in obtaining VX ,
    which will be outlined below.                                 •      ..'..'
APPROACH:
    A value comparable to VX, called total sludge units (TSU) was determined using the Metro
    Denver data.  Total sludge units are equivalent to the summation of the aerator sludge
    units (ASU) and the clarifier sludge units (CSU).  A sludge unit is defined as one
    gallon of sludge at 100% concentration, based on sludge concentrations obtained by cen-
    trifuge testing.  One of the differences between TSU and VX-| lies in the fact that a
    modification is made in determining the clarifier sludge units.
a.  Determination of Clarifier Sludge Units (CSU)
                                         Final Clarifier
                                                                   CONC = RSC
WHERE:  [West's Symbols (12)]
    CWD = clarifier water depth (mean depth if bottom is sloped)  -  At Metro Denver the
          mean depth was 11.7 feet.
    DOB = depth of sludge blanket  -  At Metro Denver blanket depth determinations were made
          every two hours on each of the three clarifiers in the respective areas.  These
          values were averaged on a daily basis to obtain DOB (12/15/69 for Area #3, DOB =
          9.7 feet).
                                          39

-------
    BLT =  sludge  blanket  thickness  -  This value is equivalent to CWD - DOB (11.7 - 9.7 =
          2.0  feet  (BLT)  for  Area #3 on  12/15/69).
    ATC =  aeration  tank concentration  - This is the concentration of sludge by percent
          volume  in the aeration basin.  This value was obtained by centrifuging samples of
          the  effluent from the aeration basins.  A daily average of ATC values was obtained
          for  use in calculations.   (12/15/69 for Area #3, ATC = 2.75X)
    RSC =  return  sludge concentration  - This is the concentration of sludge by percent
          volume  drawn off the bottom  of the secondary clarifiers.  This value was obtained
          by centrifuging samples taken  from the return sludge wet well.  A daily average of
          RSC  values was  obtained for  use in calculations.   (12/15/69 for Area #3, RSC =
          11.25%)
    CMC =  clarifier mean  sludge concentration  -  This value is obtained by the equation
          ATC  + RSC   ^is equation assumes a sludge concentration at the top of the blanket
          equal to ATC and that at  the bottom equal to RSC and a uniform distribution of
          concentration.   (2-75 + 11.25  = 7.0%  (CMc) for Area #3 on 12/15/69)
OTHER FACTORS:
    CVG =  clarifier volume in gallons  per clarifier multiplied by  the number of clarifiers in
          operation.  At  Metro Denver  the volume of each clarifier was  1.165 million gallons
          and  three clarifiers were in operation.   (1.165 x  3 =  3.495 MG  (CVG) for Area #3
          on 12/15/69)
    CSP =  clarifier sludge percentage  or the  portion of the  clarifier occupied by sludge
          which is determined by  the ratio  of *£. (2.0 = n.171  (CSP) for Area #3 on
                                             CWD   11.7
          12/15/69).
    From the above the clarifier  sludge  units can  be determined  by the  equation:  CSU =
CMC X CSP  X CVG.
    A modification was made in the  equation for this  analysis  in  that the CMC was multiplied
by the factor representing the conversion between  percent  concentration by  volume and mg/1
(616 mg/1  TSS = 1% for Area #3 for 12/15/69 and the  related  "steady state"  period).
    Therefore the modified clarifier sludge mass  can  be  determined by CSU (modified) =
CMC x 616 x CSP x CVG x 8.33 Ibs/gal.
    C = 7.0 x 616 x 0.171 x 3.495 x 8.33
      = 21.550 IDS, of total  suspended solids or sludge  in clarifier
b.  Determination of Aerator Sludge Units  (ASU)
    ASU = AVG x ATC
                                         40

-------
        WHERE:
            AVG = aeration basin volume in gallons per aeration basin times the number of basins
                  in service.  At Metro Denver the volume of each aeration basin was 2.0 MG and
                  three basins were in operation in Area #3 (2.0 x 3.0 = 6 MG (AVG) for Area #3
                  on 12/15/69).
            ATC = 2.75% for 'Area #3 on 12/15/69 (See a. above).
            From the above the aeration basin sludge units can be determined.  However, the per-
        centage sludge concentration by volume must again be converted to mg/1 (616 mg/1 TSS =
        ITfor Area #3 for 12/15/69 and the related "steady state" period).
            Therefore the modified aeration basin sludge mass can be determined by:
            ASU (modified) = AVG x ATC x 616 x 8.33 Ibs/gal.
                           = 6 x 2.75 x 616 x 8.33
                           = 84.670 Ibs. of total  suspended solids or sludge in aeration basin
    c.  Determination of TSU
            Using the modifications outlined above the value of TSU is assumed to be equivalent
        to the value VX-j.
        THEREFORE:
            TSU (modified) = VX-, = ASU (modified)  + CSU (modified)
                           = 21,550 (From a. above) + 84,670 (From b. above)
                           = 106,220 Ibs.  of total suspended solids or sludge in system
        NOTE:
            The value of TSU, as determined above, was obtained on a TSS basis.   Normally in
        determining a substrate removal 'rate (q) a VSS basis is used.  (VSS/TSS = 0.840 for
        Area #3 for 12/15/69 and the related "steady state" period)
        THEREFORE:
            TSU (modified) x VSS/TSS = VX1  in Ibs. of VSS
                                     = 106,220 x 0.840
                                     = 89.220 Ibs. of volatile suspended solids  in system
3.  Example Determination of q
           VX-|
    For Area #3 on 12/15/69:
    F(S0 - S-j) = 52,760 Ibs. BOD5 removed/day (1.  above)
           VX1 = 89,220 Ibs. of volatile suspended solids  in system (2.  above)
                                             41

-------
                  q = 52.760
                  H   89,220
                    = 0.592 Ib.  of BODs removed per day
                               Ib.  of VSS in system
        [q for conventional activated sludge normally has  a value of 0.2  to 0.5,  see  Jenkins  (3)]

B.  Determination of the Net Growth Rate l/ec
    1.   _ FX2 + WXr          [Sefi jenk^s (3)]
       c      VX]
    1.   Determination of VX-)
            VX, or its assumed equivalent was determined in Part A-2 above.  This was determined for
        Area #3 for the date of 12/15/69.
            VX. = 106.220 Ibs. of total suspended solids in system (A-2 above)
        NOTE:
            In the determination of l/ec it is not necessary to convert from a TSS basis to a VSS
        basis since both the numerator (FX2 + WXr) and denominator (VX])  in the calculation can be
        determined on a total suspended solids basis.  Therefore, VX] on  a total  suspended solids
        basis is given above and WXr and FX2 will be calculated on a total suspended solids basis
        below.
    2.  Determination of UXr
            WXr represents  the mass of sludge wasted from the system per day.
        WHERE:
              W = waste sludge flow rate  (12/15/69 for Area #3, U = 0.89 MGD)  -  This value was
                  obtained  from flow meters at the Metro Denver plant.
             Xr = return sludge TSS or VSS concentration  -  This value was not determined at Metro
                  Denver on mg/1 basis but rather the return sludge concentration (RSC) was deter-
                  mined as  a percent volume using the centrifuge.  This value  (RSC) can be related
                  to  Xr using the  relationship established between mg/1 and percent concentration by
                  volume based on  daily  grab samples.   (616 mg/1 TSS = IX  for  Area #3 and the
                  related  "steady  state"  period)  For Area #3 the daily average  RSC concentration on
                  12/15/69 was 11.25%.
             Xr  = 11.25 x  616 = 6,930 mg/1
        THEREFORE:
            WXr  = 0.89 x 6,930 x 8.33  Ibs/gal. = 51.310 Ibs. wasted  per dav
                                                  42

-------
3.  Determination of FX2
        FX2 represents the cells lost from the system per day in the plant effluent.
    WHERE:
         X2 = effluent TSS or VSS concentration  -  At Metro Denver the effluent TSS  concentra-
              tion was determined for each area based on the analysis of a composite  sample
              (12/15/69 for Area #3 effluent TSS = 36 mg/1).
          F = influent flow rate (F = 33.9 MGD for Area #3 on 12/15/69).
    THEREFORE:
        FX2 = 33.9 x 36 x 8.33 Ibs/gal.
            = 10.180 Ibs. of total suspended solids lost in the effluent per dav
4.  Example Determination of Net Growth Rate (l/ec)
           FX2 + WX»
    •I / gt  _   fc.	 I

    For AreaJ3 on 12/15/69:
        FX2.= 10,180 Ibs/day (3. above)
        WXr = 51,310 Ibs/day (2. above)
        VX1 = 106,220 Ibs. (1.  above)
    THEREFORE:
        1/0  „ 10.180 + 51.310

             =  61.490
               106,220
             = 0.581 Ibs. TSS wasted or lost per day
                           Ibs.  TSS in system
        The reciprocal 'of l/ec is equal  to ec or the mean cell residence time (sludge age).  For
    Area #3 on December 15, 1969, ec = 1.72 days.
        Similar calculations we're made for the other days included in the selected "steady state"
    periods for Areas #2 and #3.  The results of these analyses are presented in Table 2 in text.
                                              43

-------