EPA-430/9-75-003
                   TECHNICAL REPORT
   COSTS OF WASTEWATE
      TREATMENT BY  LAND
             APPLICATIO

                   June 1975
           U.S. Environmental Protection Agency
           Office of Water Program Operations
                Washington, D.C. 20460

-------
                     NOTE
This Technical Report supplements the Technical
Bulletin, entitled, EVALUATION OF LAND APPLICATION
SYSTEMS, March 1975, No. EPA-430/9-75-001, and
should be used in conjunction with the EVALUATION
manual.
Methods of estimating costs and evaluating the cost-
effectiveness of conventional wastewater treatment
works are being developed in a separate document,
entitled, A Guide to the Selection of COST-EFFECTIVE
WASTEWATER TREATMENT SYSTEMS, NO. EPA-430/9-75-002,
which will become available later in 1975.

-------
EPA-430/9-75-003
                      TECHNICAL REPORT
     COSTS OF WASTEWATER TREATMENT  BY LAND APPLICATION
                              BY

                        CHARLES E. POUND
                        RONALD W. CRITES
                       DOUGLAS A. GRIFFES
                     CONTRACT NO. 68-01-0966
                       PROJECT OFFICER, P.E.
                       BELFORD L. SEABROOK
                 OFFICE OF WATER PROGRAM OPERATIONS
                 ENVIRONMENTAL PROTECTION AGENCY
                     WASHINGTON, D.C.   20460
                           JUNE, 1975
                          PREPARED FOR

            ENVIRONMENTAL PROTECTION  AGENCY
           OFFICE OF WATER PROGRAM OPERATIONS
                  WASHINGTON, D.C.  20460

-------
                          ABSTRACT
Cost information for two stages of planning is presented
for alternative land application systems:  (1) preliminary
cost screening and (2) detailed cost estimates.  Cost
categories include land, preapplication treatment, trans-
mission, storage, land application, and recovery of
renovated water.

For preliminary screening costs (Stage I), curves are
presented relating capital, amortized, and operation and
maintenance costs to average flowrates ranging from
0.1 to 100 mgd (4.38 to 4,380 I/sec).  Cost calculation
procedures and an illustrative example are included.

For detailed planning costs (Stage II), curves, tables,
and data are presented for 33 individual cost components
related to either flowrate or field area.  For capital
items, total construction costs are shown, and operation
and maintenance costs are divided into labor, materials,
and power where applicable.

This report is submitted in partial fulfillment of Contract
68-01-0966 by Metcalf § Eddy, Inc., Western Regional Office,
under the sponsorship of the Environmental Protection Agency.
Work was completed as of May 1975.
                              111

-------
                           CONTENTS
Section
   1
Appendixes
   A
   B
   C
   D
   F
   G
                                           Page
INTRODUCTION                                 1
Purpose                                      1
Scope                                        1
LAND APPLICATION SYSTEMS                     5
Types of Systems                             5
Design Components                           12
Factors Other Than Cost                     20
PRELIMINARY PLANNING COSTS (STAGE I)        23
Cost Components and Methodology             23
Cost Curves                                 29
Cost Calculations Procedures                52
Example                                     54
DETAILED PLANNING COSTS  (STAGE II)          59
Cost Components and Methodology             59
Cost Curves                                 65
Additional Costs                           120
Benefits                                   122
Cost Calculation Procedure                 123
Example                                    127
REVENUE-PRODUCING BENEFITS                 135
NONREVENUE-PRODUCING BENEFITS              137
REFERENCES                                 139
EPA SEWAGE TREATMENT PLANT AND
SEWER CONSTRUCTION COST INDEXES            145
PRESENT WORTH AND CAPITAL
RECOVERY FACTORS                           147
COST-EFFECTIVENESS ANALYSIS GUIDELINES     149
GLOSSARY OF TERMS, ABBREVIATIONS,
AND CONVERSION FACTORS                     151

-------
                          FIGURES
No.                                                     Page
 1   Methods of Land Application                          6
 2   Relationship of Stage I Cost Curves                 24
 3   Total Land Requirement                              26
     STAGE I COST CURVES
 4   Transmission - Conveyance                           33
 5   Transmission - Pumping                              35
 6   Storage                                             37
 7   Application Systems - Spray Irrigation,
     Solid Set (Buried), Crops                           39
 8   Application Systems - Spray Irrigation,
     Solid Set (Buried), Woodlands                       41
 9   Application Systems - Spray Irrigation,
     Center Pivot                                        43
10   Application Systems - Surface Irrigation            45
11   Application Systems - Overland Flow                 47
12   Application Systems - Infiltration-
     Percolation, Basins                                 49
13   Recovery of Renovated Water - Underdrains           51
14   Relationship of Stage II Cost Curves                61
15   Field Area Requirement                              63
     STAGE II COST CURVES
16   Preapplication Treatment - Aerated Lagoons          69
17   Preapplication Treatment - Chlorination             71
18   Transmission - Gravity Pipe                         73
19   Transmission - Open Channels                        75
20   Transmission - Force Mains                          77
21   Transmission - Effluent Pumping                     79
22   Storage (0.05-10 Million Gallons)                   81
23   Storage (10-5,000 Million Gallons)                  83
24   Field Preparation  - Site Clearing                   85
25   Field Preparation  - Land Leveling
     for Surface Irrigation                              87
                              VI

-------
                    FIGURES (Continued)
No.                                                      Page
26   Field Preparation - Overland Flow
     Terrace Construction                                 89
27   Distribution - Solid Set Spraying (Buried)           91
28   Distribution - Center Pivot Spraying                 93
29   Distribution - Surface Flooding
     Using Border Strips                                  95
30   Distribution - Ridge and Furrow Application          97
31   Distribution - Overland Flow                         99
32   Distribution - Infiltration Basins                   101
33   Distribution - Distribution Pumping                  103
34   Recovery of Renovated Water - Underdrains            105
35   Recovery of Renovated Water - Tailwater Return       107
36   Recovery of Renovated Water - Runoff Collection      109
37   Recovery of Renovated Water - Chlorination
     and Discharge                                        111
38   Recovery of Renovated Water - Recovery Wells         113
39   Additional Costs  - Administrative and
     Laboratory Facilities                                115
40   Additional Costs  - Monitoring Wells                  117
41   Additional Costs  - Service Roads  and Fencing         119
                              VII

-------
                            TABLES
No.                                                     Page
 1   Comparative Characteristics of Irrigation,
     Infiltration-Percolation, and Overland Flow
     Systems for Municipal Wastewater                     7
 2   List of Stage I Cost Components                     25
 3   Sample Stage I Cost Calculation Sheet               53
 4   Example of Completed Stage I Cost
     Calculation Sheet                                   58
 5   List of Stage II Cost Components                    60
 6   Sample Costs to Produce Crops in California        121
 7   Typical Yields and Prices for Crops in
     California for 1973                                123
 8   Sample Stage II Cost Calculation Sheet
     for Capital Costs                                  124
 9   Sample Stage II Cost Calculation Sheet
     for Operation and Maintenance Costs                125
10   Example of Completed Stage II Cost
     Calculation Sheet for Capital Costs                132
11   Example of Completed Stage II Cost Calculation
     Sheet for Operation and Maintenance Costs          133
D-l  Sewage Treatment Plant Construction Cost Index     145
D-2  Sewer Construction Cost Index                      146
E-l  Present Worth Factors                              147
E-2  Capital Recovery Factors                           148
                               Vlll

-------
                        PARTICIPANTS

EPA PROJECT OFFICER:   Mr.  Belford L. Seabrook

TECHNICAL REVIEW:   Inter-Agency Soil Treatment Systems
                   Work Group

EPA Members

  Richard E. Thomas,  OR§D  (Chairman), Robert S.  Kerr
    Environmental  Research Laboratory, Ada,  Oklahoma
  Belford L. Seabrook, Office of Water Program Operations,
    Washington, B.C.
  Darwin R. Wright, OR§D,  Municipal Pollution Control
    Division, Washington,  D.C.
  G. Kenneth Dotson,  National Environmental  Research
    Center, Cincinnati, Ohio
  Stuart C. Peterson, Region I, Boston
  Daniel J. Kraft, Region II, New York
  W. L. Carter, J. Potosnak, Region III, Philadelphia
  Russell Wright, Region IV, Atlanta
  Eugene I. Chaiken, Region V, Chicago
  Richard G. Hoppers, Region VI, Dallas
  Jay Zimmerman, Region VII, Kansas City
  Roger Dean,  Region VIII, Denver
  Lewis G.  Porteous, Region  IX, San Francisco
  Norman Sievertson, Region X, Seattle

Other Members

  Charles E. Pound               Eliot Epstein, USDA
  Metcalf § Eddy,  Inc.           Beltsville, Maryland
  Palo Alto, California

  Sherwood  C.  Reed, CRREL        George L. Braude, FDA
  U.S. Army Corps of Engineers   Washington, D.C.
  Hanover,  New Hampshire

  William E. Larson, USDA        Jack C. Taylor, FDA
  University of Minnesota        Rockville,  Maryland
  St. Paul, Minnesota

CONTRACTOR:  Metcalf $ Eddy,  Inc.,  Palo Alto, California

  Supervision:  Franklin L. Burton, Chief Engineer

  Authors:      Charles E. Pound, Project Manager
                Ronald W. Crites, Project Engineer
                Douglas A. Griffes

  Consultant:   Dr. George Tchobanoglous,
                University of California, Davis
                              IX

-------
                              Section 1

                             INTRODUCTION
PURPOSE

The purpose of this report is to aid the planner and engineer in
evaluating the monetary costs and benefits of alternative 1 and
application systems for municipal wastewater effluents so that they
may be compared in a cost-effectiveness analysis.  Procedures docu-
mented in the EPA Cost-Effectiveness Analysis Guidelines (40 CFR 35 -
Appendix A), which are presented as Appendix F of this report, include
requirements to evaluate project costs and benefits in monetary terms
where possible and to account for nonmonetary social and environmental
factors in descriptive terms.  The Technical Bulletin "Evaluation of
Land Application Systems",  [17] covers these important factors.  The
Guidelines state that "the most cost-effective alternative shall be
the waste treatment management system determined from the analysis to
have the lowert present worth and/or equivalent annual value without
overriding adverse nonmonetary costs."  The Guidelines further states
that the selected alternative shall "realize at least identifical
minimum benefits in terms of applicable Federal, State, and local
standards for effluent quality, water quality, water reuse and/or land
and subsurface disposal."

SCOPE

Cost curves, tables and other data are presented for estimating capital
and operation and maintenance costs for land application systems.  In-
formation is provided on revenue-producing benefits in Appendix A and
nonrevenue-producing benefits in Appendix B.  Cost information is pre-
sented for two stages of planning that require differing degrees of
detail and accuracy.  The two stages correspond to alternative evalua-
tion procedures identified  in Guidance for Preparing Facility Plans
[21], preliminary planning  cost  (Stage I) for screening of alternatives;
and detailed planning costs  (Stage II)  for detailed evaluation of the
most feasible alternatives.

Preliminary'Planning Costs  (Stage I)

Cost information for preliminary screening of alternatives to determine
which systems have cost-effective potential is presented in Section 3.
A minimum amount of site information is required to use this information.
It is expected that the information would be used for preliminary
evaluations, as indicated in paragraph c(3) of the Cost-Effectiveness
Analysis Guidelines, by planners and engineers

-------
when an  accuracy  of  approximately  30 percent  is sufficient.
It  should  be  noted,  however,  that  for  conditions unfavor-
able to  land  application,  Stage  I  cost estimates may vary
by  as much as 50  percent  from actual costs.

Detailed Planning Costs  [Stage II)

This stage of cost estimation corresponds to  paragraph f of
the Cost-Effectiveness Analysis  Guidelines.   Alternatives
that have  been screened  for cost-effective potential and
ability  to meet federal,  state,  and local criteria would
require  economic  evaluations  based on  preliminary designs.
Detailed planning costs  for this purpose are  included in
Section  4.  It is expected that  the accuracy  of Stage II
information would be within about  15 percent  of actual costs,
Because  of the uniqueness  of  land  application systems,
however, the  engineer making  the estimate will usually need
to  modify  the Stage  II  information to  reflect local
conditions in preparing  the cost-effectiveness analysis.

Limitations

The cost data cover  average plant  flowrates between 0.1 and
100 mgd  (4.38 to  4,380  I/sec), although they  are more
applicable for flowrates  between 0.5 and 50 mgd (21.9 to
2,190 I/sec).  Systems with flowrates  above or below these
ranges generally  require  special cost  considerations.  The
types of land application systems  identified  in Section 2
include  irrigation,  infiltration-percolation, and overland
flow.  Other  systems, such as subsurface leach fields or
deep well  disposal,  are  not included.

With the current  level of interest in  land application, it
is  expected that  new types of systems  and methods of
application will  be  developed and  will appear in use.  To
reflect  anticipated  changes and  improvements, the cost
data presented in this report should be revised and
updated  periodically.

Basis of Costs

All cost data given  are  for a base date of February 1973
and should be updated to  reflect current costs by means
of  cost  indexes.   Recommended methods  and cost indexes for
use in updating the  base  costs are given in both Sections 3
and 4.   Amortized capital  costs, which are given in Sec-
tions 3, are  based on an  interest  rate of 5-5/8 percent and
a period of 20 years.

The costs  given in this publication were derived from a
variety  of  sources.   Those in Section  3 (Stage I) were

-------
derived directly from those in Section 4 (Stage II), which
were, in turn, derived from a combination of:

     •  Previously published information

     •  Surveys of existing facilities

     •  Consultation with contractors

     •  Cost calculations based on typical preliminary
        designs

For the most part, however, the costs were predominantly
built up from typical preliminary designs since very few
actual construction cost data are available for existing
land application systems.  It is hoped that actual costs
can be used to a greater degree in future revisions of
this report as more data become available.

-------
                          SECTION 2

                  LAND APPLICATION SYSTEMS

To provide a background for the development of costs in
Sections 3 and 4, three basic concepts of land application
will be described:

     •  Types of systems

     •  Design components

     •  Factors other than cost

TYPES OF SYSTEMS

Although there is a wide variety of land application
systems, they can generally be classified as  (1) irrigation,
(2) infiltration-percolation, and (3) overland flow.  These
three methods are shown schematically in Figure 1, and com-
parative characteristics are given in Table 1.  In the text
that follows, each method will be discussed briefly, with
emphasis on  the ranges of site characteristics and typical
loading rates.

Irrigation

Irrigation involves applying wastewater to the land, by
spraying or  surface spreading, to support plant growth and
treat the wastewater.  This method is the most popular of
land application  techniques and  is generally  the most
reliable.

Treatment is accomplished by a combination of physical,
chemical, and biological means as the applied wastewater
seeps into the soil.  Systems may be designed for the
following purposes:  (1)  to avoid surface discharge of
nutrients; (2)  to obtain economic return from the use of
water and nutrients by producing marketable crops;  (3)  to
conserve water by exchange when  lawns, parks, or golf
courses are  irrigated; or (4)  to preserve and enlarge
greenbelts and open space.

Preapplication treatment is provided for most irrigation
systems, and a wide range of treatment requirements are
encountered.  The bacteriological quality of municipal
wastewater is usually limiting where food crops or land-
scape areas  are to be irrigated, or where aerosol generation
by sprinkling is  of  concern.   In other cases, reductions  in
BOD and suspended solids may be  necessary to  prevent clog-
ging of the  distribution system, or  to preclude odor problems

-------
                             EVAPORATION
SPRAY OR
SURFACE
APPLICATION
ROOT  ZONE
SUBSOIL
                                            CROP
                                (a)  IRRIGATION
                                                                    SLOPE
                                                                    VARIABLE
                                                                    DEEP
                                                                    PERCOLATION
                                  EVAPORATION
                                                 SPRAY OR
                                                 SURFACE APPLICATION
                                                 PERCOLATION  THROUGH
                                                 UNSATURATED  ZONE

                         (b)  INFILTRATION-PERCOLATION
ORIGINAL WATER
    TABLE
                                EVAPORATION
   SPRAY APPLICATION
   SLOPE 2-4%
                                          GRASS AND  VEGETATIVE  LITTER
                                 (c) OVERLAND FLOW
                                                                     RUNOFF
                                                                     COLLECTION
                FIGURE  1.  METHODS  OF  LAND APPLICATION

-------
              Table  1.   COMPARATIVE  CHARACTERISTICS OF
              IRRIGATION,  INFILTRATION-PERCOLATION, AND
          OVERLAND  FLOW  SYSTEMS  FOR MUNICIPAL  WASTEWATER
Irrigation
Factor
Liquid loading
rate, in./wk
Annual
application, ft/yr
Land required for
Low* rate
O.S to 1.5
2 to 4
280 to 560
High-rate
l.S to 4.0
4 to 18
62 to 280
Infiltration-percolation
4 to 120
18 to 500
2 to 62
Overland flow
2 to 9
8 to 40
28 to 140
1-ngd flowrate,
acres*

Application
techniques

Vegetation
required

Crop production

Soils
     Spray or surface


     Yes         Yes
 Excellent
            Good/fair
    Usually surface


         No


       Poor/none
    Usually spray


        Yes


      Fair/poor
 Moderately permeable
 soils with good produc-
 tivity when irrigated
Rapidly permeable soils.  Slowly permeable soils,
Climatic constraints  Storage often needed
such as sands,  loamy
sands, and sandy loans

  Reduce loadings in
  freezing weather
such as clay loams and
clays

Storage often needed
tfastewater lost to:
Expected treatment
performance
EOD and SS removal
.Nitrogen removal
Phosphorus removal
Evaporation and
percolation


98+*
85+ta
80 to 99*
Percolation


85 to 99*
0 to 501
60 to 95*
Surface runoff and
evaporation with some
percolation


92+*
70 to 90*
40 to 80t
a.  dependent on crop uptake

Metric conversion:
in. x 2.54 - cm
ft x 0.305 - m
acre x 0.405 - ha

-------
Site Characteristics.  The range of suitable site character-
istics for irrigation systems is also wide.  The major
criteria are as follows:

     •  Climate - Warm-to-arid climates permit longer
        season application, but more severe climates are
        acceptable if adequate storage is provided for wet
        or freezing conditions.

     •  Topography — Slopes up to 15 percent for crop
        irrigation are acceptable if runoff or erosion
        is controlled.

     •  Soil type — Loamy soils are preferable, but most
        soils from sandy loams to clay loams are suitable.

     •  Soil drainage - Well-drained soil is preferable;
        however, more poorly drained soils may be suitable
        if drainage features are included in the design.

     •  Soil depth -A uniform depth of 5 to 6 feet (1.52
        to 1.83 m) or more throughout sites is usually
        necessary for root development and wastewater
        renovation.

     •  Geologic formations — Lack of discontinuities that
        provide short circuits to the groundwater is
        necessary.

     •  Groundwater — A minimum depth of 5 feet (1.52m) to
        groundwater is normally necessary to maintain
        aerobic conditions, provide necessary renovation,
        and prevent surface waterlogging.  Control may be
        obtained by underdrains or groundwater pumping.

Loading Rates.  The liquid and nitrogen loading rates are
usually the most important for irrigation systems, and in
most cases, one of the two will prove to be limiting.
Occasionally, however, other loading rates, such as phos-
phorus and organic matter, or loadings of constituents of
abnormally high concentration, may be more critical.  To
determine the limiting loading rate, balances  should be
be conducted both for water and for constituents of concern,
as shown in Evaluation of Land Application Systems  [17].

In conducting the water balance, the following factors
are considered:

     •  Wastewater applied

     •  Precipitation

-------
     •  Evapotranspiration

     •  Percolation

     •  Runoff

The key is to balance, on a monthly or annual basis, the
water applied (effluent plus precipitation) with the water
losses (evaporation and percolation).  Runoff must usually
be controlled for irrigation systems.  Precipitation and
evaporation are determined from an analysis of weather
records.   Percolation rates used in the design should be
determined on the basis of a number of factors, including
soil characteristics, underlying geological conditions,
groundwater conditions, wastewater characteristics, degree
of renovation required, and crop tolerances.  In addition
to determining the liquid loading rate, the water balance
can be used to determine storage requirements.  As can be
seen in Table 1, the range of liquid loading rates differs
for low-rate and high-rate irrigation.  Low-rate irrigation
systems are normally operated to maximize crop yields, and
water is normally applied only during the growing season,
and only in quantities required to meet the growth needs
of plants.  Consequently, very little percolation occurs.
On the other hand, high-rate systems are normally operated
to optimize the economic treatment of applied wastewater.
In this case, the liquid loading is controlled by either
hydraulic limitations of the soil or by limiting loading
rates of constituents such as nitrogen.  With regard to
hydraulic limitations, deep sandy or loamy  soils usually
are not a problem while clayey soils or shallow soil
profiles may require application rates of  1.5 in./wk (3.6
cm/wk.) or less.

In conducting the mass balance for nitrogen,  the amount of
nitrogen applied in the wastewater per year is compared to
the amount taken up by a particular crop,  and the amount
that passes through to the groundwater.  Denitrification
may amount to 10 to 30 percent of the nitrogen remaining
after crop uptake.  The amount of nitrogen  taken up by crops
can be determined from a number of references, including
Reference 17.  Typical values are about 150 Ib/acre/yr
(168 kg/ha/yr) for corn and 230 to 400 Ib/acre/yr  (258 to
443 kg/ha/yr) for Reed canary grass.  Allowable amounts of
nitrogen passing through to the groundwater can be deter-
mined from applicable groundwater standards.  The amount of
nitrogen applied in the wastewater is a function of concen-
tration and liquid loading rate.

Once the limiting loading rate has been determined, weekly
application rates can be calculated over the  yearly

-------
 operating season.   Also, the land requirements  can  be
 calculated as shown in Sections 3 and 4.

 Infiltration-Pereolation

 In this method, wastewater is applied to  the  soil by
 spreading in basins or by spraying and is treated as  it
 travels through the soil matrix.   Vegetation  is  generally
 not used although grass is grown  in some  cases.  Preappli-
 cation treatment is generally provided to reduce the  sus-
 pended solids content and thereby allow the continuation
 of high application rates.  Biological treatment is often
 provided prior to spreading or ponding although  effluent
 with only primary treatment has also been used.

 Site Characteristics.  Because most of the applied  effluent
 percolates through the soil, soil drainage is usually  the
 limiting site characteristic.  Other site evaluation  cri-
 teria include:

      •  Climate — Infiltration-percolation is applicable
         in nearly all climates.  Loadings may need  to  be
         reduced for cold weather  conditions.

      •  Topography - Level terrain is  preferable, but
         rolling terrain is acceptable.

      •  Soil type — Acceptable soils include sand,  sandy
         loams, loamy sands,  and gravels.   Soils  that  are
         too coarse provide insufficient renovation.

      •  Soil drainage — Moderate-to-rapid drainage  is
         preferable.

      •  Soil depth - A uniform depth of 10 to 15 feet  (3.1
         to 4.6 m)  is preferred.

      •  Geologic formations  — Lack of  discontinuities  is
         necessary.

      •  Groundwater  —A minimum depth  of  15 feet (4.6  m)  to
         the existing water table  is  necessary; it is not
         allowed to  rise to less than 4 feet (1.2 m) from
         the ground  surface.   Control by underdrains may  be
         required.

Loading  Rates  and Land Requirements.   Depending  on waste -
water  characteristics  and  water quality objectives, loadings
of nitrogen, phosphorus, organic,  or trace elements may
be critical.  Although liquid or  nitrogen loading is most
                               10

-------
often limiting, loadings of salt as a result of weathering
and soil lime dissolution may be critical in some cases.
Loading schedules that include alternating loading and
resting periods are required to maintain the infiltration
capability of the soil surface and to promote optimum
nitrogen removal by nitrification-denitrification.

The water balance is similar to that for irrigation, except
that greater amounts of water are lost to percolation.
Again, runoff is usually not designed into these systems.
The limiting percolation rate should be estimated for
saturated soil and adverse climatic conditions.  Loading
rates of less than 12 in./wk (30.5 cm/wk) are generally
required for loams and sandy loams, while higher loading
rates usually require the soil to be predominantly sand
or gravel.

Where concentrations of nitrogen in either the groundwater
or recovered renovated water are limiting, the loading rates
and the loading schedule must be selected to maximize
denitrification.  Some guidance for the determination of
the proper loading rates for this purpose is provided in
Reference 17 and in papers by Lance  [26] and Bouwer  [5].

Overland Flow

In this method, wastewater is applied on the upper reaches
of sloped terraces of relatively impermeable soils and
allowed to flow across the vegetated surface to runoff
collection ditches.  Renovation is accomplished by physical,
chemical, and biological means as the wastewater flows in
a sheet through the vegetation and litter.  Preapplication
treatment should include removal of large solids, grit,
and grease which would hamper effective application by
sprinkling.  Where preapplication treatment includes
complete secondary treatment, overland flow can be used
for polishing of the effluent and removal of constituents
such as nitrogen.  The renovation noted in Table 1 has been
shown for domestic as well as food processing wastewaters.
For domestic wastewater that is not adequately disinfected
prior to overland flew treatment, disinfection of the
collected runoff may be necessary.

Site Characteristics.  Important site characteristics include

     •  Climate — Warm climates are preferable, but more
        severe climates are acceptable if adequate storage
        is provided for freezing conditions.
                              11

-------
     •  Topography — Rolling  terrain  is well suited;
        level  terrain  can  be  used  to  create uniform
        slopes of 2  to 6 percent,  and in  some cases
        as  high as 8 percent.

     •  Soil type —  Clays  and clay loams  are preferable.

     •  Soil drainage  — Poor  or  slow  drainage is necessary.

     •  Soil depth — Depth must  be sufficient to form
        slopes and maintain vegetative cover.

     •  Geologic formations — Lack of major discontinuities
        is  necessary.

     •  Groundwater  —  Groundwater  should  not interfere with
        plant  growth.

Loading Rates.  Typical loading  rates range from 0.25 to
0.75 in./day  (0.64 to  1.78 cm/day)  for systems applying
primary treated wastewater to  as high as  0.90 in./day
(2.30 cm/day)  for systems  applying  secondary effluent.
The water balance should be conducted mainly to determine
the amount  of  expected runoff.   The effluent applied plus
precipitation  should balance  the runoff plus evaporation,
with a 10 to 30 percent allowance  for percolation.

The loading rates mentioned apply  to  the  entire terraced
area, which may be composed of 50  to  100  feet (15.2 to
30.5 m) of  terrace under the  spray  diameter, plus 100 to
200 feet  (30.5 to 61.0 m)  of  runoff slope.  The required
length of runoff terrace will  depend  on the degree of
treatment required,  wastewater characteristics, amount of
slope, and  climate.

DESIGN COMPONENTS

Typically,  land application systems are composed of a
number of distinct components  from  the following list of
major component categories:

     •  Preapplication treatment

     •  Transmission

     •  Storage

     •  Distribution

     •  Recovery of  renovated  water
                               12

-------
The design of land application systems is highly variable
and is dependent on many factors relating to site charac-
teristics and project objectives.  Some of the major design
variables are discussed briefly in the following subsec-
tions.  Additional references [17, 40] should be consulted
for more detailed information.

Preapplication Treatment

The type and level of preapplication treatment will have a
significant effect on factors such as:

     •  The loading rate of various constituents

     •  The methods of  application to be used

     •  The type of crop or vegetative cover to be  grown

Many states have regulations  concerning  required levels  of
preapplication  treatment.  Regulations for  California are
included as an  example  in  an  appendix  in Reference  17,  and
range from requirements for primary treated wastewater  for
irrigation of fodder, fiber,  and seed  crops,  to  require-
ments for adequately disinfected, oxidized, coagulated,
and filtered wastewater for spray irrigation  of  food crops.

Transmission

Transmission  is the  conveyance  of wastewater  from  any one
portion  of the  system  to  another, and may  include  the con-
veyance  of:   (1) wastewater  from the  collection area to
preapplication  treatment  facilities,  (2) treated wastewater
from  treatment  facilities  to  the land application  site,
or (3)  recovered renovated water from the  land application
site  to  a discharge  point.  The three potential methods of
conveyance are:

      •   Gravity pipe

      •   Open  channels

      •   Force mains

 The primary  factor to  be  considered in the selection of
 the method  of conveyance  is  terrain.   Other factors must
 also be considered,  however,  particularly in the case  of
 open channels where the possibility of public contact  with
 the wastewater exists.   Standard design criteria for each
 method of conveyance should be used.
                               13

-------
Storage

Requirements for storage may range from 1 day of flow to
6 months of flow.  The primary considerations in determin-
ing storage capacity are the local climate and the design
period of operation for the type of system; however, system
backup and flow equalization should also be considered.

Storage reservoirs may be  required to have impervious
linings to eliminate percolation to the groundwater, and
asphaltic lining costs have been included in the cost
curves in both Sections 3  and 4.  Adjustment factors for
other types of linings are shown in Section 4.

Distribution

Wastewater may be applied  to the land by means of a variety
of distribution systems, the most basic of which are dis-
cussed in this subsection.  These include:

     •  Solid set spraying (buried)

     •  Center pivot spraying

     •  Surface flooding using border strips

     •  Ridge and furrow application

     •  Overland flow distribution

     •  Infiltration basins

Costs are given for each system in both Sections 3 and 4.
In Section 3, however, the costs of other basic components
have been added to the cost of each basic distribution
system, and "Surface Flooding Using Border Strips" and
"Ridge and Furrow Application" have been combined into the
more general "Surface Flooding."

Solid Set Spraying (Buried).  Solid set spraying using
buried pipe is used primarily for spray irrigation systems,
but it may also be used for infiltration-percolation and
overland flow systems.  The use of solid set spraying for
overland flow is discussed separately in a following sub-
section.   The major design variables include:  sprinkler
spacing,  application rate, nozzle size and pressure, depth
of buried pipe, pipe materials, and type of control system.
For more detailed information, additional references, such
as Sprinkler Irrigation [34], should be consulted.
                              14

-------
     •  Sprinkler spacing — May vary from 40 to 60 feet
        (12.2 by 18.3 m) to 100 by 100 feet  (30.5 by 30.5 m)
        and may be rectangular, square, or triangular.
        Typical spacings are 60 by 80 feet (18.3 by 24.4 m)
        and 80 by 100 feet (24.4 by 30.5 m).

     •  Application rate — May range from 0.10 to 1 in./hr
        (0.25 to 2.54 cm/hr) or more, with 0.16 to 0.25
        in./hr (0.42 to 0.64 cm/hr) being typical.  Weekly
        rates vary with the climate, soil type, and crop
        requirements over the ranges indicated in Table 1.

     •  Nozzles — Generally vary in size of openings from
        0.25 inch (0.64 cm) to 1 inch (2.54 cm).  The dis-
        charge per nozzle can vary from 4 to 100 gpm  (0.25
        to 6.3 I/sec), with a range from 8 to 25 gpm  (0.50
        to 1.58 I/sec) being typical.  Discharge pressures
        can vary from 30 to 100 psi (2.1 to 7.0 kg/sq cm);
        with 50 to 60 psi (3.5 to 4.2 kg/sq cm) being typical

     •  Depth of buried laterals and mainlines — Depends
        on the depth of freezing for cold climates.  Where
        the depth of freezing is not a factor, a depth of
        18 inches (46 cm) for laterals and 36 inches
        (91 cm) for mainlines is common [33].  Surface
        piping, usually of aluminum, may be 40 to 50 percent
        less costly than buried piping, but it is also
        less reliable.

     •  Pipe materials — May be any type used for standard
        pressure pipe; however, asbestos-cement and plastic
        (PVC) pipes are most common.  Factors that should
        be considered when selecting type of pipe materials
        include cost, strength, ease of installation, and
        reliability.

     •  Control systems —May be automatic, semiautomatic,
        or manual.  Automatic systems are the most popular
        for land application systems.  Automatic valves may
        be either hydraulically or electrically operated.

Center Pivot Spraying.  Center pivot systems are the most
widely used ,of the moving sprinkling systems.  Design
variables include size, method of propulsion, pressure,
and topography [33].

     •  Sizes — Systems consist of a lateral that may be
        600 to 1,400 feet (183 to 427 m) long.  The lateral
        is suspended by wheel supports and rotates about a
        point.  Areas of 35 to 135 acres (14 to 55 ha) can
        be irrigated per unit.
                              15

-------
     •  Propulsion — May be  by means of either hydraulic
        or  electric  drive.   One  rotation may take from
        8 hours  to as much as 1  week.

     •  Pressures -  Usually  50 to 60 psi  (3.5 to 4.2 kg/
        sq  cm) at the nozzle, which may require 80 to
        90  psi (5.6  to  6.3 kg/sq cm) at the pivot.  Stand-
        ard sprinkler nozzles or spray heads directed
        downward can be used.

     •  Topography — Systems can be used on rolling terrain
        with  slopes  up  to 15 to  20 percent.

 Surface Flooding Using  Border Strips.  The major design
 variables for surface flooding using border strips
 include strip dimensions, method of distribution, and
 application rates.

     •  Strip dimensions — Vary  with type of crop, type of
        soil, and slope.  Border widths may range from 20
        to  100 feet  (6.1 to  30.5 m); widths of 40 to 60
        feet  (12.2 to 18.3 m) are the most common.  Slopes
        may range from  0 to  0.4  percent.  The steeper
        slopes are required  for  relatively permeable soils.
        Strip length may vary from 600 to 1,400 feet (183
        to  427 m).

     •  Method of distribution — May generally be by means
        of  either a  concrete-lined ditch with slide gates
        at  the head  of  each  strip, or underground pipe
        with  risers  and alfalfa  valves.

     •  Application  rates —  At the head of each strip, rates
        will  vary primarily  with soil type and may range
        from  10  to 20 gpm per foot (2.1 to 4.1 I/sec per m)
        width of strip  for clay, to 50 to 70 gpm per foot
        (10.4 to 14.5 I/sec  per  m) width of strip for sand.
        The period of application for each strip will vary
        with  strip length and slope.

Additional  references,  such  as Irrigation [61], should be
consulted for more detailed  information.

Ridge and Furrow Application.  This method is very similar
in concept  to surface flooding using border strips, except
that the applied water  is conveyed down the slope by means
of furrows.   Row crops, such as  corn, are normally grown.
                               16

-------
The major design variables are application, topography, and
furrow dimensions.

     •  Application - Usually by gated aluminum pipe.   Short
        runs of pipe (80 to 100 feet) (24 to 30 m) are pre-
        ferred to minimize pipe diameter and headless  and
        to provide maximum flexibility.  Surface standpipes
        are used to provide the 3 to 4 feet (0.9 to 1.2 m)
        of head necessary for even distribution.

     •  Topography - Method can be used on relatively  flat
        land (less than 1 percent slope) with furrows
        running down the slope, or on moderately sloped
        land with furrows running along the contour.

     •  Dimensions — Furrow lengths usually range from 600
        to 1,400 feet (183 to 427 m).  Furrows are usually
        spaced between 20 and 40 inches (51 to 102 cm)
        apart, depending on the crop.

Overland Flow Distribution.  Sprinkling is the most common
technique in the United States; however, surface flooding
may be practical for effluents relatively low in suspended
solids.  General practice is as follows:

     •  Sprinkler application — May be by either fixed
        sprinklers or rotating boom-type sprays.  Moving or
        portable systems are not practical because a smooth
        surface must be maintained.  Sprinklers are spaced
        from 60 to 80 feet (18 to 24 m) apart on the laterals

     •  Slopes — May range from 2 to 8 percent with 2  to 4
        percent preferred for adequate detention time.
        Lengths of slope may range from 150 to 300 feet  (45
        to 90 m) with 175 to 250 feet  (53 to 76 m)
        being typical.

     •  Application cycles — Commonly 6 to 8 hours of
        wetting and 16 to 18 hours of drying to maintain the
        microorganisms on the soil surface active.

     •  Surface application — May be by flooding or by
        gated pipe.  Most suited to wastewater low in
        organic solids.

Infiltration Basins.  This method is the most common for
infiltration-percolation systems.  The major design variables
include:  application rate, basin size, height of dikes, and
maintenance of basin surfaces.
                               17

-------
     •  Application  rates — Can vary from 4 to 120 in./wk
         (10.2  to  305 cm/wk), with  the range of 12 to 24
         in./wk (30.5 to  61.0 cm/wk) being most common.
        Loading cycles generally vary from 9 hours to 2
        weeks  of  wetting and from  1 day to 3 weeks of drying.

     •  Basin  size — Generally a function of design flow and
        relationship of  wetting and drying periods.  Basins
        may range in size from less than 1 acre  (0.4 ha) to
         10  acres  (4  ha)  or  more.   It is usually  necessary
         to  include at least two separate basins  for even
         the smallest of  systems.

     •  Height of dikes  — Varies with depths of  water
         applied.  For depths of 1  to 2 feet (0.30 to 0.61 m),
         a height  of  approximately  4 feet (1.22 m) is common.

     •  Maintenance  of basin surface - May be a  significant
         operation and maintenance  expense.  Many systems
         require periodic tilling of surface, often annually,
        while  some high-rate systems may required periodic
         replacement  of sand or gravel.

 Recovery  of Renovated Water

 Systems  that may  be  used to recover renovated water include
 underdrains, runoff  collection followed by chlorination and
 discharge,  and recovery  wells.  Tailwater return is also
 included  in this  group,  even though the tailwater is usually
 not  completely renovated.

 Underdrains.  Underdrains may be required in poorly drained
 soils or  when  groundwater levels will affect renovation or
 crop growth.  The system normally  consists of a  network of
 drainage  pipe  buried 4 to 10 feet  (1.22 to 3.05  m) below the
 surface and intercepted  at  one end of the field  by a ditch.
 The  pipes normally range in diameter from 4 to 8 inches
 (10.2 to  20.4  cm).   The  distance between pipes can range
 from 100  feet  (30.5  m) for  clayey  soils to 400 feet (122 m)
 for  sandy soils.

 Cut-off ditches or open  drains can be used in place of
 buried drain pipes;  however, their use is declining and a
 cost curve  is  not provided.  Such  ditches can require from
 10 to 30  percent  of  the  field area and are usually not
 cost effective.

Tailwater Return.  A tailwater return system is  used with
surface irrigation to collect and  return excess  applied
water from  the bottom of the strip or furrow.  The system
normally consists of collection ditches, a small reservoir,
                              18

-------
a pump, and piping to the nearest distribution line.   The
system should normally be sized on the basis of the expected
amount of return flow, which can range from 10 to 40  percent
of the applied flow.

Runoff Collection.  The runoff collection systems referred
to in this publication are used primarily for overland
flow systems and can be followed by chlorination and
discharge.  The runoff collection ditches are most often
unlined and sized to handle the runoff from a specific
storm.  The chlorination and discharge facilities should
include a small reservoir, emergency overflow capabilities,
and also should be sized to handle the runoff from a
specific storm.

Recovery Wells.  Recovery well systems are used primarily
with infiltration-percolation systems, but may also be used
with high-rate irrigation systems.  They may be used for
reduction of groundwater levels to ensure treatment effect-
iveness, or they may be required for further reuse of
renovated water or to satisfy water rights considerations.
Design variables include well location and spacing, depth,
type of packing, and flowrate.  Each of these variables is
dependent on the geology, soil, and groundwater conditions
at the site, application rates, and the desired percentage
of the renovated water to be recovered.

Crops

Crops or vegetative cover are normally an integral part of
all land application systems, with the exception of most
infiltration-percolation systems.  Factors that affect the
selection of the type of crop to be grown include:

     •  Water requirement and tolerance

     •  Nutrient requirements, tolerances, and removal
        capabilities

     •  Sensitivity to inorganic ions

     •  Public health considerations relating to the use
        of the crop

     •  Ease of cultivation and harvesting

     •  Length of growing season

     •  Value of crop (marketability)

For a more detailed discussion of these factors, Reference 17
should be consulted.
                              19

-------
Water Rights

Water rights  considerations may be of importance in the
cost analysis, particularly in the western states [25].
The return  of certain quantities of water to a particular
water body  may be required.   In cases where a change is
contemplated  in  the method of disposal or point of discharge,
the state agency or other cognizant authority should be
contacted and the status of all existing water rights
should be thoroughly investigated.

FACTORS OTHER THAN COST

A number of factors other than direct cost must be consid-
ered in the analysis of wastewater alternatives.  Among
these are:

     •  Flexibility

     •  Reliability

     •  Environmental impact

     •  Public health considerations

     •  Social impact

     •  Economic impact

Each of these factors is briefly discussed with respect to
land application systems in the following text.  For a more
detailed discussion, Reference 17 should be consulted.

Flexibility

The abilities of each alternative wastewater system to
operate efficiently under changing conditions,  and to be
easily modified, should be assessed.   Factors related to
flexibility that should be considered are:

     •  Ability to meet changes in treatment requirements

     •  Ability to meet changes in wastewater characteristics

     •  Ease of expansion

     •   Ability to adapt to changing land uses

     •   Ability to be  upgraded as a result of technological
        advances
                              20

-------
Reliability

The reliability and dependability of the system are
critical, particularly if the adverse effects of an
operational breakdown or poorly operating system may be
great.  Characteristics relating to reliability that should
be considered include:

     •  Ability to meet or exceed discharge requirements

     •  Failure rate due to possible operational breakdowns
        of various components

     •  Vulnerability to natural disasters

     •  Adequacy of supplies of required resources

     •  Factors-of-safety

Environmental Impact

The environmental impact of the selected wastewater alter-
native will normally be considered in great depth in the
later stages of planning when a complete environmental
assessment is made.  Preliminary assessments should also
be made in the earlier stages, however, so that alterna-
tives can be compared on that basis.  Generally, the
environmental impact of factors unique  to land application
systems should be assessed with respect to:

     •  Soil and vegetation

     •  Groundwater

     •  Surface water

     •  Animal and insect life

Public Health Considerations

When evaluating the overall environmental impact of an
alternative, special consideration should be given to those
effects that relate directly to the public health.  Factors
that should be considered are:

     •  Groundwater quality

     •  Potential for breeding insects  and rodents

     •  Potential runoff from the site
                              21

-------
      •   Aerosols  from spray application

      •   Potential contamination of crops

 Social  Impact

 The  overall effects  of each alternative should be evaluated
 in light of their impact on the sociological  aspects of the
 community.   Factors  that should be considered are:

      •   Public acceptance

      •   Relocation of residents

      •   Aesthetic effects

      •   Community growth

      •   Agricultural marketing  competition with area farmers

 Economic Impact

 In many cases a wastewater  treatment facility will have
 indirect economic impacts on the community.   Some of the
 potential  impacts are:

      •   Change in the  value of  land used and  adjacent land

      •   Loss  of tax  revenues as a  result of governmental
         purchase  of  land

      •   Conservation of  resources  and energy

      •   Change in quality of ground or  surface waters

Resources Opportunity

The potential  benefits that can be derived from the addition
or reuse of various  resources should be assessed.   These
may include:

     •  Availability of  a source of water for irrigation

     •  Recycling.of nutrients

     •  Preservation of open space and greenbelts

     •  Recreational  activities
                               22

-------
                           Section 3

            PRELIMINARY PLANNING COSTS (STAGE I)

In this section cost data are presented that will enable
the user to quickly estimate the costs of treatment alter-
natives involving the land application of wastewater for
the purpose of preliminary screening.  Estimates developed
from these data should generally be within 30 percent of
actual costs; however, for conditions unfavorable to land
application the variance could be more than 50 percent.
Such conditions could include large site preparation costs
or the need for extensive stormwater control.  Consequently,
these curves should be used with caution.

COST COMPONENTS AND METHODOLOGY

The costs of land application as presented in this section
have been divided into 13 components which are grouped
under 7 major categories, as listed in Table 2.  Except for
land and preapplication treatment, cost curves are presented
for each component which relate the capital and operation
and maintenance costs to flow in million gallons per day.
The relationship among those components for which curves are
included is shown in Figure 2. Methods for determining the
cost of land and preapplication treatment are discussed in
the text.

Once the cost of each component has been computed, the
total cost of the system can be determined by adding the
component costs.  A cost calculation sheet  (Table 3) has
been included for this purpose at the end of this section.
A sample calculation is also included to illustrate the
step-by-step procedure  (page 54).

Land Costs

The cost of land is often a significant portion of the total
system cost.  Land may be acquired by an outright purchase,
lease, or other means as described in Evaluation of Land
Application Systems  [17] .   If the land is to be purchased
outright, the cpst should be determined by multiplying the
estimated total land requirement  (acres) by the prevailing
market price for land  (dollars per acre).  The prevailing
market price of land should be determined from a local
source such as the tax assessor.
                               23

-------
         ,PREAPPLICATION ,
            TREATMENT     '
                    TRANSMISSION
t-o
I  COST
  ESTIMATES
.  FROM OTHER
I  SOURCES
  	I
APPLICATION
  SYSTEMS
  RECOVERY  OF
RENOVATED WATER
                                                                              SPRAY
                                                                              IRRISATION
                                                                              SOLID  SET
                                                                              (BURIED)
                                                                              CROPS
                                                                              SPRAY
                                                                              IRRIQATIQN-
                                                                              CENTER PIVOT
                                                                              SURFACE
                                                                              IRRIGATION
                                                                                         UNDERDRAINS
                                                                              SPRAY
                                                                              IRRIGATION
                                                                              SOLID  SET
                                                                              (BURIED)
                                                                              •OODLANDS
                                                                               OVERLAND
                                                                               FLO!
                                                                              INFILTRATION
                                                                              PERCOLATION
                                                                              BASINS
                                 FIGURE  2.  RELATIONSHIP  OF  STAGE  I  COST CURVES

-------
           Table 2.   LIST OF  STAGE I  COST COMPONENTS

                                                 Figure No.
                                                 for curve   Page
          Category              Component            reference   No.

      1. Land           • Total area requirement            3a     26
      2. Preapplication   • Preapplication treatment"
        treatment
      3. Crop revenues    • Crop revenues0
      4. Transmission     • Conveyance                     4      33
                      • Pumping                       5      35
      5. Storage        • Storage                       6      37
      6. Application     • Spray irrigation, solid set        7      39
        systems          (buried),  crops
                      • Spray irrigation, solid set        8      41
                        (buried),  woodlands
                      • Spray irrigation, center pivot      9      43
                      • Surface irrigation              10      45
                      • Overland flow                 11      47
                      • Infiltration-percolation, basins    12      49
      7. Recovery of     • Underdrains                   13      51
        renovated water

      a.  This figure  is not a cost curve but a nomograph which relates total
         area requirement in acres to design flow in mgd, nonoperating time in
         weeks, and application rate in inches per week.
      b.  No cost data are provided.  See text, page 27.
      c.  No cost data are provided.  See text, page 29.


As  an aid  for  estimating the total  land requirement,  a
nomograph  (Figure  3) is included which relates total
area  in acres, with or without a buffer zone allowance, to
design flow  in mgd,  nonoperating time in weeks,  and appli-
cation rate  in inches per  week.  The nonoperating  time is
defined as the nubmer of weeks per  year during which
operation  is ceased because  of climatic factors.   For
systems in cold northern states, this would  be equal  to
the storage  period.   In more temperate climates,  the
nonoperating time  could be  considerably greater than  the
storage period because operation is possible for  periods
between unfavorable weather.

To  use the nomograph, first  draw a  line through appropriate
points on  the  design flow  and application  rate axes to the
pivot line.   Draw  a second line from the intersection of
the first  line with the pivot line  through  the appropriate
point on  the nonoperating  time axis.  The  calculated  total
area  is then noted at the  intersection of  that axis with
the second line.   This  total area  includes  land for appli-
cation, roads, storage, and  buildings.  The  total  area with
                                   25

-------

20 -=.
15 -=
^
;
to -;
8 —
\'\
- . -i
Ul 1
2 i-f
O j =
••* ™ «
tO U 5
ON — :
a. ;
~
2 -^
2
-
I __




too -
50 -
-
5 1° -
= !• =
It.
"• t
X"'^ -!
^ ~
/ 0.5 -
/ I
X
^^
O.I — '









X
xl
^^ ^B
0
a.







30,000 —
20,000 -
10,000 -

5,000 -
1.000 -
. 	 :
500 ~-

* too —
* Z
" 50 -
-
10 —

-
5 —
— 30,000
— 20,000
- 10,000
•
- 5,000
» 25 ™
*• 2 :
UJ «* 9fl —
at •• «D —
u I
J =" " 1
Iftl GAIIDI C 91 (IT ^" **
fl AAfl IL wHMrkC •< kUI «
-a *
- 500 Jz 2 5 _:
••« _
0 0.
_ o o
•
-too S
- *
»•
- 50 S
SAMPLE PLOT
DESIGN FLOW 3 M6D
APPL. RATE 1.5 1 N . /»
NONOPEP. TIME 10 WK
READ: goo ACRES W/BUFFER
*° 750 ACRES «f/0 BUFF















K
ER
FIGURE 3.  TOTAL LAND REQUIREMENT

-------
a 200-foot wide buffer zone allowance is read from the
right-hand side of the axis, while the total area without
a buffer zone allowance is read from the left-hand side.

Once the total capital cost of land has been calculated,
the amortized cost, including an allowance for salvage
value, can be determined by the following equation:


                ,    .   n n,c. total capital cost
       amortized cost = 0.0154   design flow -


where
       amortized cost  is  in  $/l, 000 gal.
       total capital cost is  in  $ (thousands)
       design  flow  is  in  mgd

or  in metric units

                ,     .   n .„, total  capital  cost
       amortized cost  = 0.173    design flow


where


       amortized cost  is  in  <£/l,000  1
       total capital cost is in  $ (thousands)
       design  flow  is  in  I/sec

Preapplication Treatment

For many systems  the cost of preapplication treatment must
be  included in the  total  cost of the system.   To obtain
these  costs, other  publications  that are devoted to the
cost of  conventional  treatment systems should be consulted.
A Guide  to the Selection  of  Cost-Effective Wastewater
Treatment Systems  [54],  and  Estimating Costs  and Manpower
Requirements for  Conventional Wastewater Treatment Systems
 [27] are suggested  as  useful references for this purpose.
 Special  consideration  is  given to preapplication treatment
by aerated lagoons  in  Stage  II because of their common
use in conjunction  with land application systems, and
because  of the limited amount of information concerning
 their  costs in other publications.  Consequently, a set of
 cost curves for aerated lagoons   (Figure 16) is included in
 Section 4, page 69 .
                               27

-------
The level  of  preapplication treatment  required  for  land
application is  dependent  on a number of  factors,  including

       •   Method  of  application

       •   Type  of crop  grown

       •   Intended use  of crop

       •   Loading rate  of certain  constituents

       •   Equipment  limitations

 In many states, regulations relating to  preapplication
 treatment  exist.  For further guidance, Reference  17
 should be  consulted.

To use preapplication treatment cost data from  other
 sources, the  costs should first be trended to the base
date  of February  1973,  using the cost  index specified in
 that  source.   If  a cost index is not specified, the EPA
Sewage Treatment  Plant  Construction Cost Index  should
be used.

Once  the total  capital  cost has been determined for
February 1973,  the amortized cost  can  be determined by
the following equation:


       amortized  cost = 0.0232  total  capital cost
                                   design flow
where
          amortized  cost  is  in  $/l,000 gal.
          total  capital cost is in $(thousands)
          design flow  is  in  mgd
or in metric units
where
       amortized cost =  0.268    total capital cost
                                  design flow
          amortized cost is in $/l,000 1
          total capital cost is in $(thousands)
          design flow is in I/sec
                              28

-------
The operation and maintenance cost per volume of treated
water may be determined from the annual operation and
maintenance cost by the following equation:


              0§M cost = 0.274  annual O^M cost
                                  design flow

where


              0§M cost is in f/1,000 gal.
              annual 0§M cost is in $(thousands)
              design flow is in mgd


or in metric units

              0$M cost = 3.17   annual 0§M cost
                                  design flow
where
              0§M cost is in 
-------
on the  left-hand pages.   Each of the  10  Stage  I  curves  given
in this  section was  derived directly  from the  Stage  II  cost
curves  of  Section  4.

Capital  Cost  Curves

Two  curves or groups of  curves are  presented in  each case
for  capital costs:   (1)  capital costs, expressed in  thou-
sands of dollars,  and (2)  amortized cost,  expressed  in
cents per  thousand gallons.   The capital  cost  is the cost
to the  owner  and includes allowances  of  25 to  35 percent
for  a service and  interest factor.  This  factor  includes
contingencies; engineering;  legal,  fiscal,  and administra-
tive costs; and interest during construction.

The  amortized cost is the total construction cost multiplied
by the  capital recovery  factor for  an interest rate of
5-5/8 percent and  a  period of 20 years (erf =  0.0845),  and
divided  by the design flow for 1 year.

Each of  the curves reflects  the costs for  the  base date of
February 1973.  It is suggested that  the costs be trended
to reflect current costs by  means of  the EPA Sewer Construc-
tion Cost  Index, as  explained on page 52.

Operation  and Maintenance  Cost Curves

An operation  and maintenance curve  is given for  each
component.  The curve gives  the total of all annual labor,
power, and materials  costs,  expressed in cents per thousand
gallons.   The curves  for irrigation systems include the cost
of planting and cultivating  the crop  grown.

The  costs  are based  on an  average staff labor  rate, includ-
ing  fringe benefits,  of  $5.00 per hour, and a  unit cost of
power of $0.02 per kilowatt-hour.  Although the  costs
cannot be  readily  adjusted for regional or  time  differences
in Stage I, it is  suggested  that the  total  operation and
maintenance cost be  trended  by means  of the EPA  Sewer Con-
struction  Cost Index  to  approximate current costs.

Average Versus Effective Flow

Costs for  transmission and storage  are related to average
flow, which is considered  to be the annual  average design
flow entering the system.  In the curves for pumping and
conveyance, an allowance for peaking  factors has been included,

Costs for application systems  and recovery  of  renovated
water are related to  effective  flow, which  is  the rate
                              30

-------
applied to the land during the operating season.  For sys-
tems operating year-round, the average and effective flows
are the same.  For systems that cease operation and store
incoming flow during a portion of the year, the effective
flow will be larger than the average flow in proportion to
the number of nonoperating days or weeks.  The effective
flow can be calculated using the following equation:
where


             Q  = effective flow in mgd or I/sec
             Q  = average flow in mgd or I/sec
             W  = number of operating weeks per year

Secondary Variables

A family of curves is included for many of the Stage I com-
ponents introducing secondary variables, such as storage
capacity or application rates.  Interpolation between these
curves is encouraged for storage capacities and application
rates other than those shown.  Selection of the proper
storage capacity and application rate is specific to the
site and application process chosen as indicated in Sec-
tion 2.  It is important to note that each application
system represents a separate process or management technique
with different site requirements to meet different project
objectives.  Consequently, the curves under "Application
Systems" should not be compared without taking into account
these differences.

Detailed Information Relating to Cost Curves

Base Date.  The base date for all costs given in this
section is February 1973

Costs Included.  A summary of the cost items included and
theimportant design assumptions is presented on the left-
hand page for each component.  The design assumptions gen-
erally reflect typical designs of each component with
average to moderately favorable conditions.

Metric Conversion.  Metric conversion factors are given for
those parameters which appear in the cost curves.  Addi-
tional metric conversion factors are given in Appendix G.
                               31

-------
                         TRANSMISSION

 CONVEYANCE

 Costs  per mile are given for the 3 basic methods  of
 conveyance:   (1)  gravity pipe, (2) open channels,  and
 (3)  force mains.

 BASE DATE -  FEBRUARY 1973

 Assumptions

 1.   Peaking  factor allowance ranges from 3  for  systems
     of 1 mgd (43.8 I/sec) and less average  flow,  to  2
     for systems with greater than 10 mgd (438 I/sec)
     average  flow.

 2.   Gravity  pipe:

     a.   9-ft (2.7  m) depth of cover over crown  of  pipe
     b.   Average slope of 0.002 to 0.005
     c.   Average velocity of approximately 3  to  5 fps
         (0.9 to 1.05 m/sec)
     d.   Repaving  of road surface required for 10%
         of distance

 3.   Open channels:

     a.   Concrete-lined,  trapezoidal-shaped ditch with
         1:1  side  slopes
     b.   Average slope of 0.004
     c.   Minimum average  velocity of approximately  2 fps
         (0.6 m/sec)
     d.   Normal  freeboard of 1.5  ft (0.5  m)

 4.   Force  mains:

     a.   5-ft (1.5 m)  depth of cover over  crown  of  pipe
     b.   Average velocity of 5 fps  (1.5 m/sec)
     c.   Repaying of  road surface  required for 10%
         of distance

Metric Conversion

1.  mgd x 43.8  = I/sec

2.   */l,000 gal. x 0.264  =  */l,000  1
                              32

-------
 18 IM
  1.000
<   1 00
      0. t
                                                             0. 1
                                                            0. 0 t
                                                        100
   0.01
   0. 002
                              OPERATION & MAINTENANCE COST
      t. i
               FIGURE 4. TRANSMISSION  - CONVEYANCE
                                 33

-------
                         TRANSMISSION

PUMPING

BASE DATE - FEBRUARY 1973

Costs Included

1.  Effluent pumping station with 150-ft (45.8 m)
    total head.

2.  Peaking factor allowance ranges from 3 for systems
    of 1 mgd (43.8 I/sec) and less average flow, to
    2 for systems with greater than 10 mgd (438 I/sec)
    average flow.

Note:  These curves should be used in conjunction
       with those in Figure 4, "Transmission-
       Conveyance," (see Assumption 4, Force Mains)
       on the preceding page.

Metric Conversion

1.  mgd x 43.8 = I/sec

2.  */l,000 gal. x 0.264 = */l,000 1
                               34

-------
 20,000
 10.000
i-' 1 . 0 01
    1 10
     ^ 0
       0. 1
                             -AMORTIZED
                                                            LL
                                                  CAPITAL COST
                                                CAPITAL
I                  10
    AVERABE FLOfl.HfiD
                                                                    200
                                                                    1 00
                                                                     0. 7
      tl
                                  OPERATION & MAINTENANCE COST]
      • !
                                   J	L
                                         I  I I I I
                           !                  10
                                AVEMABE FLOW.HBO
                                                               too
                  FIGURE  5.  TRANSMISSION -  PUMPING
                                     35

-------
                           STORAGE

Costs are given for various storage capacities as equivalent
average flows of 1-, 10-, and 20-week durations.

BASE DATE - FEBRUARY 1973

Costs Included

1.  Basic reservoir construction on level ground  with
    dikes formed from native excavated materials.

2.  Erosion protection using riprap.

Note:  For approximate costs of lined reservoirs, multiply
       basic cost by a factor of 2.2 for full lining, or
       1.6 for half lining.

Metric Conversion

1.  mgd x 43.8 = I/sec

2.  */l,000 gal. x 0.264 = */l,000 1
                              36

-------
,— 10.000
^  1,000.
     1 00
      11
        0. 1
                               20
                                                10
                                                       'CAPITAL
                                                 AMORTIZED^
                                                — 1
                                                                      400
                                                                       1 00
                                                                        I 0
                                      0. 1
                                      9.01
              1 0
AVERA8E FLOW. USD
                                                                  1 00
      0 . 1
     0.01
                                   OPERATION & MAINTEHANCE  COSJ
        a. i
                                                                  1 DO
                                 AVERAGE  FLOW. HOD
                              FIGURE  6.  STORAGE
                                        37

-------
                     APPLICATION  SYSTEMS

SPRAY  IRRIGATION,  SOLID  SET  (BURIED), CROPS

BASE DATE  -  FEBRUARY 1973

Costs  are  given  for a  typical  system, for application rates
of 1,2, and  4  in./wk.

Costs  Included

1.  Site clearing  of brush and few small trees.

2.  Distribution--buried solid-set spray system with
    automatic  controls,  80 x 100  ft  (24.4 x 30.5 m)
    sprinkler  spacing.

3.  Distribution pumping with  225-ft (68.6 m) total head.

4.  Administrative and laboratory facilities.

5.  Monitoring wells of  50-ft  (15.3 m) depth.

6.  Service  roads  and fencing.

7.  Cultivation  of corn.

Metric Conversion

1.  mgd x  43.8 = I/sec

2.  */l,000 gal. x 0.264 = */l,000 1
                             38

-------
 200,000
 100.000
  10,001
   1,000  -
    100
                                                               2
                                                                . 000
                                                                 1 00
                                                                  I 0
       0 . 1
                          10

            EFFECTIVE Fill. MID
                                                            100
    100

_)
•«
•

I


V


t-
JJ    to
u
—
I
               OPERATION & MAIHTENAHCE COST
APPLICATION RATES (Ili/VK)
                                     JLi
                                           it

                            EFFECTIVE FLOI, MB
                                                            100
        FIGURE  7.  APPLICATION SYSTEMS - SPRAY  IRRIGATION,
                       SOLID SET (BURIED),  CROPS
                                    39

-------
                     APPLICATION  SYSTEMS

SPRAY IRRIGATION, SOLID  SET  (BURIED), WOODLANDS

BASE DATE  - FEBRUARY 1973

Costs are  given for a typical system, for application
rates of 1, 2, and 4 in./wk.

Costs Included

1.  Site clearing--pathways  through wooded area
    for distribution.

2.  Distribution--buried solid-set spray system with
    automatic controls,  60 x 80 ft (18.3 x 24.4 m)
    sprinkler spacing.

3.  Distribution pumping with 150-ft (45.8 m) total head,

4.  Administrative and laboratory facilities.

5.  Monitoring wells of  50-ft (15.3 m) depth.

6.  Service roads and fencing.

Metric Conversion

1.  mgd x  43.8 = I/sec

2.  */l,000 gal. x 0.264 = */l,000 1
                             40

-------
200.000
100.000
 10,000
 1.000
   1 00
                                                             2.000
                                                             1 , 000
                                                              100 -
     0. t
                                                               • 0
                        i                 10
                         EFFECTIVE FLOW. H6D
                                                          1 00
   1 00
                              OPERATION i MAINTENANCE COSJ
                             APPLICATION
                            RATES (IN./IK)
                                         1 0

                         EFFECTIVE FLOf. MOD
                                                          1 00
     FIGURE 8.  APPLICATION SYSTEMS  - SPRAY  IRRIGATION,
               SOLID SET (BURIED), WOODLANDS
                                  41

-------
                     APPLICATION SYSTEMS

SPRAY IRRIGATION, CENTER PIVOT

BASE DATE - FEBRUARY 1973

Costs are given for a typical system, for application rates
of 1, 2, and 4 in./wk.

Costs Included

1.  Site clearing--brush with few small trees.

2.  Distribution--heavy-duty center pivot rigs with elec-
    tric drive.

3.  Distribution pumping with 150-ft (45.8 m) total head.

4.  Administrative and laboratory facilities.

5.  Monitoring wells of 50-ft (15.3 m) depth.

6.  Service roads and fencing.

7.  Cultivation of corn.

Metric Conversion

1.  mgd x 43.8 = I/sec

2.  */l,000 gal. x 0.264 = */l,000 1
                              42

-------
 1 00.DOB
  10.000
—  1,000
    1 00
      0 . 1
                                                               1 00
                                                                10 t-

                                                                   I
                                          10

                            EFFECTIVE FLOW.  H80
                                                           1 00
    200
_,   100
     I C
       0. 1
                               OPERATION A MAINTENANCE COST
\                 1 0

   EFFECTIVE FLOW. IID
                                                           1 00
        FIGURE  9. APPLICATION SYSTEMS -  SPRAY  IRRIGATION,
                             CENTER  PIVOT
                                   43

-------
                     APPLICATION SYSTEMS

SURFACE  IRRIGATION

Costs are  given  as  an  average  of costs  for  ridge and
furrow application,  and  surface  flooding using border
strips,  for  application  rates  of 1,  2,  and  4  in./wk.


BASE DATE  -  FEBRUARY 1973

Costs Included

1.  Site clearing--brush with  few small trees.

2.  Land leveling--500 cy/acfe (945  cu m/ha).

3.  Distribution--average  of ridge and furrow application,
    and  surface  flooding using border strips.

4.  Distribution pumping with  15-ft  (4.6 m) total head.

5.  Tailwater return--25%  of applied flow is returned.

6.  Administrative  and laboratory facilities.

7.  Monitoring wells of  50-ft  (15.3  m) depth.

8.  Service  roads and  fencing.

9.  Average  of cultivation of  corn and alfalfa.

Metric Conversion

1.  mgd x 43.8 = I/sec

2.  */l,000  gal. x 0.264 = */l,000 1
                              44

-------
  10,000
   10. 000
^  1 .000
     too
       0. 1
                                                                 100
                                                                 1 00
                          '                 10
                           EFFECTIVE FLOW, ISO
                                                            1 00
     210
     t 00
S
*
I
                                OPERATION & MAINTENANCE COST
        0. I
                            EFFECTIVE FLOI.  MGD
                                                            1 00
        FIGURE 10. APPLICATION SYSTEMS - SURFACE  IRRIGATION
                                   45

-------
                     APPLICATION SYSTEMS

OVERLAND FLOW

BASE DATE - FEBRUARY 1973

Costs are given for a typical system, for application
rates of 2, 4, and 8 in./wk.

Costs Included

1.  Site clearing--brush with few small trees.

2.  Overland flow terrace construction--!,400 cy/acre
    (2,650 cu m/ha).

3.  Distribution--terrace width of 250 ft (76.3 m).

4.  Distribution pumping with 225-ft (66.8 m) total  head.

5.  Runoff collection using open ditches.

6.  Chlorination and discharge--average flow of recovered
    water equal to 75% of applied flow.

7.  Administrative and laboratory facilities.

8.  Service roads and fencing.

9.  Planting of grass.

Metric Conversion

1.  mgd x 43.8 = I/sec

2.  */l,000 gal. x 0.264 =  */l,000 1
                              46

-------
200.000
ICO,000
 10.000
  1.000
   1 00
     0. t
                                                                2.000
                                                                I Ml
                                                                  1 00
                                           to
                            EFFECTIVE FLOW. MGD
                                                            1 00
                                                                   1 0 •-
                               OPERATION & MAIHTENAHCE COST
                   APPLICATION RATES (IN./WK)
                                          i 0
                          EFFECTIVE  FLOW.  MGD
                                                            1 00
        FIGURE  11.  APPLICATION SYSTEMS  - OVERLAND  FLOW
                                  47

-------
                      APPLICATION SYSTEMS
INFILTRATION-PERCOLATION, BASINS
BASE DATE - FEBRUARY 1973
Costs are given for a typical system, for application
rates of 6, 12, and 24 in./vrk.
Cost Included
1.  Site clearing--brush with few small trees.
2.  Distribution--multiple unit infiltration basins with
    4-ft (1.2 m) dikes.
3.  Distribution pumping with 15-ft  (4.6 m) total head.
4.  Recovery wells--50-ft (15.3 m) depth, flow of recovered
    water equal to 75% of applied flow.
5.  Monitoring wells of 50-ft (15.3 m) depth.
6.  Administrative and laboratory facilities.
7.  Service roads and fencing.
Metric Conversion
1.  mgd x 43.8 - I/sec
2.  */l,000 gal. x 0.264 = */l,000 1
                              48

-------
  31.0(8
^ 10,000
   1 , ODD
    100
      o. 1
                                                                 900

                                                                 0. 5
                                           1 0

                           EFFECTIVE FLOW, MID
                                                            1 00
     : o
     \ o
                                OPERATION & MAINTENANCE COST
                           APPLICATION
                           RATES  (!«./»»)
       0.1
1

 EFFECTIVE FLOW, MM
                                                            1 00
                   FIGURE  12.  APPLICATION  SYSTEMS-
                   IMF I LTRATION-PERCOLATI ON,   BASINS
                                    49

-------
                  RECOVERY OF RENOVATED WATER

UNDERDRAINS

BASE DATE - FEBRUARY 1973

Costs are given for typical underdrain system for
irrigation application rates of 1, 2, and 4 in./wk.

Cost Included

1.  Drain pipes buried 6 to 8 ft  (1.8 to 2.4 m), with a
    spacing of 200 ft (61 m).

2.  Interception ditch along one  side of the field.

3.  Weir for control of discharge.

Note:  These curves should be used in conjunction with
       those in Figures 7, 9, or  10, "Application Systems."

Metric Conversion

1.  mgd x 43.8 = I/sec

2.  */l,000 gal. x 0.264 = 
-------
  100.000
  1 0, 000
**  1 . 000
     1 00
                             -CAPITAL
                                             <~  ~7
                                                  CAPITAL  COSTl
                                                                  1 . tOO
                                             1 0
                            EFFECTIVE FLOW. ISO
                                                                    1 00
                                                                     : 0
                                                               1 00
       :
     0. 1
                                  OPE RAT I OH t MAINTENANCE COSTl
                            APPLICATION
                           RATES ( IN./IK)"3
       o. i
1                  10
  EFFECTIVE FLOW. HBO
                                                                DC
     FIGURE  13. RECOVERY OF RENOVATED WATER -  UNDERDRAWS
                                     51

-------
COST CALCULATION PROCEDURE

To facilitate the use of the cost data presented for Stage
I, a sample cost calculation sheet has been developed
(Table 3).  For each alternative to be analyzed, a similar
calculation sheet could be used.

The procedure for calculating Stage I costs is as follows:

     1.  Determine appropriate storage capacity and appli-
         cation rate (see discussion in Section 2).

     2.  Determine effective flow from number of operating
         weeks per year by method described on page 30.

     3.  Determine total capital cost, amortized capital
         cost, and operation and maintenance cost from
         cost curves for each applicable component.

     4.  Enter costs in appropriate columns on cost
         calculation sheet.

     5.  Add amortized capital cost and operations and
         maintenance cost to determine total cost for
         each component.

     6.  Add each column to determine subtotal for base
         date of February 1973.

     7.  Determine trend factor from EPA Sewer Construc-
         tion Cost Index for analysis date at appropri-
         ate location.

     8.  Multiply subtotal for base date by trend factor
         to determine subtotal for analysis date.

     9.  Determine total and amortized capital land costs
         by method described on page 27 and enter under
         appropriate columns.

    10.  Determine net revenue from sale of crops, if
         applicable, and enter under appropriate columns.

    11.  Subtract crop revenues from subtotal to determine
         total operation and maintenance cost.

    12.  Add land costs to subtotal to determine total
         capital cost.
                               52

-------
          Table  3.    SAMPLE STAGE  I COST  CALCULATION  SHEET
 Alternative No.
 Type of system_J
                                    Average flow
                                    Analysis date"
mgd
                            Total        Amortized
                         capital cost,  capital cost,   0§M cost,    Total cost,
                              $         */l,000 gal.   */l,000 gal.  t/1,000 gal.
Cost component
Preapplication treatment
Transmission -
  conveyance
                     mi
Transmission -  pumping

Storage period
                    wks
Application systems
                  in./wk
Underdrains

    SUBTOTAL,  BASE  DATE3

      Trend factorb

 SUBTOTAL,  ANALYSIS DATE

Crop revenues

Land cost

              TOTAL COST
                                                          J.   L
a.  February 1973.
b.  Trend factor =  EPA Sewer Construction Cost Index for  analysis date at
    appropriate location  *  194.2.
                                       53

-------
EXAMPLE

The use of the cost curves and cost calculation sheet is
illustrated in the following example.  A hypothetical 3-mgd
(131 I/sec) surface irrigation system, to be constructed
as part of a new wastewater treatment system in the San
Francisco area, is used in this example.  The analysis date
is July 1974, and the EPA Sewer Construction Cost Index
for that date for San Francisco is 242.0.  The example is
meant to illustrate all facets of the cost curves and cost
calculation sheet, and the total costs should not be com-
pared with other hypothetical cost estimates.

Assumptions

1.  Preapplication treatment is to consist of preliminary
    treatment  (screening, grit removal, and flow measure-
    ment) and aerated lagoons.

2.  The distance from the preapplication treatment plant
    to the potential land application site is approximately
    2 miles  (3.2 km) and is of sufficient slope as to allow
    transmission by gravity pipe.

3.  The storage requirement is approximately 10 weeks of
    detention.  Lining of reservoir is not required.

4.  The normal operating season is to be 42 wk/yr.

5.  The land is essentially flat and covered with brush
    and small trees.

6.  The application rate is to be approximately 1.5 in./wk
    (3.8 cm/wk).

7.  A buffer zone is not required.

Solution

The determination of costs is shown on a sample cost
calculation sheet (Table 4, page 58) and is discussed for
each item.  Total capital costs are given to the nearest
thousand dollars, while amortized capital costs, operation
and maintenance costs, and total costs are all given to
the nearest tenth of a cent per thousand gallons.

The total cost in cents per thousand gallons is the sum of
the amortized and operation and maintenance costs, and is
not included in the discussion.
                               54

-------
From the equation given on page 31, the effective flow is
determined to be 3.7 mgd (163 I/sec).

PreappZication Treatment - Includes prelimi-
nary treatment and aerated lagoon.

1.  Preliminary treatment - Based on maximum
    flow of 6 mgd (263 I/sec) .  Costs deter-
    mined from reference [37] are:

    Total capital cost                         $ 94,000

    Amortized capital cost (*/l,000 gal.) -
    0 0232 x $94 (thousand)                     Q ?
    u.u^z x      3 nigd                          ' *

    Operation and maintenance cost -
    Annual cost is found to be $9,500.
    The cost in */l,000 gal. is then
    0.274 x $9'5                                0.8*
2.  Aerated lagoon - Costs determined from
    Stage II cost curve  (Figure 16) are:

    Total capital cost                         $140,000

    Amortized capital cost (*/l,000 gal.) -
    n n?^2 x $140 (thousand)
    °-0232 x — - T¥P                         1.1*

    Operation and maintenance cost - Annual
    cost is found to be  $8,240/ingd.  The
    cost in */l,000 gal.  is  then
    0.274 x $8.24 (thousand) /mgd                2.3*

Transmission - Conveyance -  From Figure 4,
the costs for gravity pipe are :

    Total capital cost -  2 mi x $140,000       $280,000

    Amortized capital cost (*/l,000 gal.) -
    2 mi x 1.0*                                 2.0*

    Operation and maintenance cost (*/l,000
    gal.) - 2 mi x 0.04*                        0.1*
                               55

-------
 Storage  -  From Figure 6,  the costs for
 storage  for  10 weeks  detention are:

     Total  capital cost -                        $   350,000

     Amortized capital cost (*/l,000 gal.)  -       2.6*

     Operation and maintenance cost
     U/1,000 gal.) -                              0.3*

 Application  System -  Surface Irrigation  -
 From Figure  10, the costs for surface
 irrigation for an effective flow of
 3.7  mgd  are:

     Total  capital cost -                        $1,300,000

     Amortized capital cost (*/l,000 gal.)  -       8.0*

     Operation and maintenance cost  (*/l,000
     gal.)  -                                     14.0*

 Subtotal^  Base Date - The subtotals of costs
 for  each column for the base date of February
 1973  are:

    Total  capital cost -                        $2,164,000

    Amortized capital cost (*/l,000 gal.)  -     14.4*

    Operation and maintenance cost  (*/l,000
    gal-)  -                                     17.5*

 Trend Factor -  The EPA Sewer Construction
 Cost  Index for  the analysis  date of 242.0
 divided by the  index  for  the  base date of
 194.2 is:                                        1.25

 Subtotal, Analysis  Date -  The  subtotals of
 costs for each  column  for  the  analysis date
of July 1974  are:

    Total capital  cost  - 1.25 x $2,164,000     $2,700,000

    Amortized capital  cost  (*/l,000 gal.)
    1.25  x  14.4*                                18.0*

    Operation and maintenance costs  (*/l,000
    gal.) 1.25 x 17.5*                          21.9*
                              56

-------
Crop Revenues - A conservative yield of corn
silage of 20 tons per acre and a price of
$15 per ton are determined from Table 7
in Section 4.  Corn is assumed to be grown
on 500 acres of the total area.  The estimated
negative cost from the sale of corn is:

    Operation and maintenance cost - Annual
    revenue is determined to be $5C,000/mgd.
    The revenue in */l,000 gal. is then
    0.274 x $50.0 (thousand)/mgd.              (13.7*)

Land Cost - From Figure 3, the total land
requirement is determined to be 750 acres.
The cost of land, determined from local
sources, is approximately $1,000 per acre.
Land costs are then:

    Total capital cost -
    750 acres x $l,000/acre                    $  750,000

    Amortized capital cost  (*/l,000 gal.)

    0.0154 x $75°

Total Cost - The subtotals for the analysis
date plus land costs are:

    Total capital cost                         $3,450,000

    Amortized capital cost  (*/l,000 gal.)       21.9*

    Operation and maintenance cost  (*/l,000
    gal.)                                        8.2*
                               57

-------
                 Table 4.   EXAMPLE  OF  COMPLETED STAGE  I
                           COST CALCULATION  SHEET
Alternative No.	/	   Average flow	3	mgd
Type of system    SURFACE IRRIGATION       Analysis date        JUL  '74

                            Total         Amortized
                         capital cost,   capital cost,  0§M cost,     Total  cost
    Cost component            $         */l,000 gal.  {/I,000 gal.  f/1,000 gal.


Preapplication treatment
   PRELIMINARY	      94.0OO         0.7           0.8            1.5
   AERATED  LAGOON	     I40.0OO         /./           2.3           3.4
Transmission -
  conveyance
   GRAVITY PIPE,     2  "i     280.OOP .        2.O           O.I            2,1

Transmission - pumping    	—      	I_I__       —        	—
Storage period
        JO	 wks     350.0OO    	2.6           0.3           2.9
Application systems
SURFACE IRRIGATION
8 1.5 in./wk
Underdrains
SUBTOTAL, BASE DATE3
Trend factor1*
SUBTOTAL, ANALYSIS DATE
Crop revenues
Land cost
TOTAL COST
1 ',3OO,OOO
_ _
2.164.000
1.25
2,700,000
750.000
3.450.000

8.0
_ _
14.4
1.25
18. 0
3.9
21.9

14.0
_ m^
17.5
1.25
21.9
( 13.7 )

8.2

22.O
- —
31.9
1.25
39.9
C 13.7 )
3.9
30. /

a.  February 1973.
b.  Trend factor =  EPA Sewer Construction Cost Index for analysis  date  at
    appropriate location *  194.2.
                                        58

-------
                          Section 4

              DETAILED PLANNING COSTS  (STAGE  II)

In this section cost data of a more detailed nature are
presented that will enable the user to estimate the cost
of a land application system more accurately than in
Stage I.  It is anticipated that these estimates will be
used in the evaluation of selected wastewater treatment
alternatives that are considered to be feasible.

The major differences between Stage I and Stage II are that
in Stage II:  (1) costs are developed for more individual
system components,  (2) costs are presented for each partic-
ular component in relation to the most applicable parameter,
and  (3) costs can be more easily adjusted to reflect local
and current conditions.  To utilize Stage II cost data
properly, a greater amount of specific information, includ-
ing a preliminary design layout, will usually be required.

Stage II cost estimates developed from the data in this
section should be within about 15 percent of  actual costs.
It is anticipated that the engineer will build on the cost
curves presented here and modify the numbers  to arrive at
his final cost-effectiveness analysis and cost estimate.

COST COMPONENTS AND METHODOLOGY

The costs of land application systems have been divided
into 33 components which are grouped under 8  major cate-
gories as listed in Table 5.  For 26 components, cost
curves are presented which relate the capital and operation
and maintenance costs of the component to the most appli-
cable parameter, such as storage volume, flowrate, or field
area.  The relationship between those components for which
cost curves are included is shown in Figure  14.  The figure
shows only a typical relationship;  in actual  practice,
combinations of components other than  those  shown are
possible.

Once the cost of each component has been estimated,  the
total cost of the  system can be determined by adding the
component costs.   Cost calculation  sheets for both capital
costs  (Table 8, page  124) and operation and  maintenance
costs  (Table 9, page  125) have been included for this pur-
pose at  the end of  this  section.  They are arranged  so  that
each component and  its cost can be  written under the appro-
priate  component category.  A column for computing amortized
cost from the capital  cost  is provided in Table 8.   A sample
calculation is also included  to illustrate the  step-by-step
procedure  (page  127).
                               59

-------
             Table  5.    LIST OF  STAGE  II  COST COMPONENTS
           Category
Component
                                                            Figure number for
                                                             curve reference
                                        Page
                                       number
1.
2.
3.



4.

5.




6.









7.






8.









Land a .
Preapplication treatment a.
b.
Transmission a.
b.
c.
d.
Storage a.
b.
Field preparation a.
b.

c.

Distribution a.

b.
c.

d.

e.
£.
g-
Recovery of renovated water a.
b.
c.

d.

e.
Additional costs a.

b.
c.
d.

e.
f.
g-
h.
Field area requirement
Aerated lagoons
Chlorination
Gravity pipe
Open channels
Force main
Effluent pumping
0.05-10 million gallons
10-5,000 million gallons
Site clearing
Land leveling for
surface irrigation
Overland flow terrace
construction
Solid set spraying
(buried)
Center pivot spraying
Surface flooding using
border strips
Ridge and furrow
application
Overland flow
Infiltration basins
Distribution pumping
Underdrains
Tailwater return
Runoff collection
for overland flow
Chlorination and discharge
for overland flow
Recovery wells
Administrative and laboratory
facilities
Monitoring wells
Service roads and fencing
Planting, cultivation, and
harvesting
Yardwork
Relocation of residents
Purchase of water rights
Service and interest factor
15
16
17
18
19
20
21
22
23
24

25

26

27
28

29

30
31
32
33
34
35

36

37
38

39
40
41

c
--
--
--

63
69
71
73
75
77
79
81
83
85

87

89

91
93

95

97
99
101
103
IDS
107

109

111
113

115
117
119

120
120
120
122
122
a.  This figure is not a cost curve but a nomograph which relates field area in acres to
    design flow in Bgd, nonoperating time in weeks, and  application  rate in inches per
    week.

b.  See text, page 64 for other methods.

c.  No cost curves are provided; see discussion on referenced pages.
                                           60

-------
I   MEAPPLICATIOM
'     TREATMENT
 RECOVERY OF
RENOVATED WATER
                         FIGURE  14, RELATIONSHIP OF  STAGE  II  COST CURVES

-------
Land

In many cases, the cost of land, either as an outright pur-
chase or a lease, will be a significant portion of the
total cost of the system.  In Stage II this cost should be
determined for a specific plot of land, based on a prelim-
inary layout.  An important first step in this process is
the determination of the field area requirement.  This is
the area of land in which the actual treatment process
takes place.  The field area requirement is also an import-
ant design parameter to which the costs of many of the com-
ponents in Stage II are related.

Field Area Requirements.  As an aid to the determination of
field area requirements, a nomograph (Figure 15) is includ-
ed which relates field area in acres to design flow in mgd,
nonoperating time in weeks, and application rate in inches
per week.  To use the nomograph, first draw a line between
appropriate points on the design flow and nonoperating time
axes.  Draw a second line from the intersection of the first
line with the pivot line and the appropriate point on the
application rate axis.  The calculated field area is then
noted at the intersection of that axis with the second line.
In some cases it may be necessary to increase this figure
by a use factor to account for inefficiencies of land utili-
zation.  The use of the nomograph is further illustrated
by means of a sample plot.

Land Costs.  Once the field area has been calculated, the
total land requirements can be determined.  This should be
done by means of a preliminary layout for a specific site.
Included in the layout should be an adequate amount of land
for each of the following items, if they are required:

     •  Field area

     •  Buffer zones

     •  Storage

     •  Buildings, roads, and ditches

     •  Future expansion or emergencies

The land costs should then be determined by multiplying the
estimated total land requirement (acres) by the prevailing
market price for land (dollars per acre).  The prevailing
market price for land should be determined from a local
source such as the tax assessor.
                              62

-------
(^
1UU —
50 -



10 —
i s -
ik
CB
vt -
111
1.0 —
0.5 -

0.1 —











25
10,000 -,
5.000 :
'
1,000 —
2 50° "
IMM u
z «
1- UJ
e BE
» •* ^,
^ J* ~
^^,^ "" 50 :
10 —
5 -
1 —
r i punr i c


20
v> ^^,-
111
^^*" "*" u>
^^*** h-
** CB
*
^ 10
«
a.
o
e
SAMLPE PLOT °
DESI GN FLOW 1 . 0 MGO
APPL. RATE 2.4 IN./WK
NONOPER.TIME 5 W K
READ: 120 ACRES
ririn ADCA ocnii i DCIICMT
                                                                                                                                       I  -1
                                                                                                                                       2   -
                                                                                                                                       3  -
                                                                                                                                      10  -
                                                                                                                                      15  -
                                                                                                                                      20  —'

-------
In accordance with the Federal Regulations on Cost Effect-
iveness Analysis [40 CFR 35), land shall be assumed to have
a salvage value at the end of the planning period equal to
its prevailing market value at the time of the analysis.
This fact is reflected in the format for calculating the
amortized cost of land as described on page 126.

Preapplication Treatment

For many systems the cost of preapplication treatment must
be included in the total cost of the system.  To obtain
these costs, other publications that are devoted to the
cost of conventional treatment systems should be consulted.
A Guide to the Selection of Cost-Effective Wastewater
Treatment Systems [54], and Estimating Costs and Manpower
Requirements for Conventional fiastewater Treatment Systems
[37] are suggested as useful references for this purpose.
Special consideration is given to preapplication treatment
by aerated lagoons because of their common use in conjunc-
tion with land application systems, and because of the
limited amount of information concerning their costs in
other publications.  In addition, the cost of chlorination
for preapplication treatment is given in Figure 17.

The level of preapplication treatment required for land
application is dependent on a number of factors, including:

     •  Method of application

     •  Type of crop grown

     •  Intended use of crop

     •  Loading rate of certain constituents

     •  Equipment limitations

In many states, regulations relating to preapplication
treatment exist.  For further guidance, the technical
bulletin, Evaluation of Land Application Systems [17]
should be consulted.

Additional Costs

The category of "Additional Costs" consists of 8 components,
and cost curves are presented for 3 of these.  The costs
for the remaining components are not readily presented by
means of curves; therefore, other methods of cost computa-
tion are described in the text that follows the curves.
                              64

-------
COST CURVES

The 26 cost curves, which are presented following this
discussion, are composed of two-page sets (Figures 16
through 41):   the capital and operation and maintenance
cost curves are shown on the right-hand pages, and detailed
information relating to the curves is summarized on left-
hand pages.

Capital Cost Curves

A curve or group of curves is presented for each component
which represents the total capital cost to the owner, in-
cluding the contractor's overhead and profit.  The curves
do not include allowances for contingencies, administration,
or engineering, however.

Each of the costs is related to either the "EPA Sewer Con-
struction Cost Index" or the "EPA Sewage Treatment Plant
Construction Cost Index" for February 1973.  For many com-
ponents, neither of these indexes directly applies, in
which case the index used is the one which is considered to
be the most applicable. Capital costs read from the curves
should be trended by means of the specified index or other
method to reflect current costs for a particular locality.
Current values for both indexes are published monthly in
the Journal of the Water Pollution Control Federation, and
quarterly in the Engineering News Record.

For some components, a group of curves is presented that
shows a range of costs for some secondary parameter.  For
example, a group of curves corresponding to a range of
depths of cover is included for "Gravity Pipe"  (Figure 18).
In several other cases, additional curves are included for
significant subcomponents or auxiliary costs, as in the
case of "Force Mains"  (Figure 20), where an additional
curve is included for  the cost of repaving.

Operation and Maintenance Cost Curves

Operation and maintenance costs are divided, where appli-
cable, into three curves or groups of curves: labor, power,
and materials.  They are each expressed in terms of dollars
per unit per year.

The labor cost is the estimated annual cost for operating
and maintaining that component by members of the staff,
and includes administration and supervision.  It is based
on an average staff labor rate, including fringe benefits,
                               65

-------
of $5.00 per hour and may be adjusted to reflect actual
average rates when significant differences exist.

The power cost  is the estimated annual cost for electrical
power required  to operate the particular component based on
a unit cost of  $0.02 per kilowatt-hour.  It may be adjusted
to reflect actual unit costs when significant differences
exist.  For several components a group of power cost curves
are shown for a range of pumping heads.

The materials cost is the estimated annual cost for normal
supplies, repair parts, and contracted repair or mainten-
ance services.  An equivalent annual cost based on the
sinking fund factor for an interest rate of 5-5/8 percent
is included for those materials costs which are not incur-
red annually.

Wholesale Price Index.   The Wholesale Price Index for
Industrial Comodities,  which may be used for trending
the materials cost,  was 120.0 for February 1973.

Detailed Information Relating to Cost Curves

Basis of Costs.  A summary of the bases of costs for which
the curves were derived is included on the upper portion of
the left-hand page for each component.  These bases normal-
ly include: (1) the selected construction cost index for
February 1973,  (2) the average labor rate, and  (3) the
power cost.

Assumptions.  A list of assumptions concerning basic design
features, and items included and not included in the cost
curves, is presented on the left-hand page for each compo-
nent.  Generally it reflects typical designs of each
component with  average conditions.  In many cases adjust-
ment factors are included for assumptions involving impor-
tant design parameters that are highly variable.

Adjustment Factors.   Adjustment factors are included for
many components to account for significant variations in
designs.  These factors should be multiplied by the cost
from the indicated curve to obtain the adjusted cost.  For
example, if the adjustment factor for labor costs were 1.1,
and the labor cost for a given field area were $1,000 per
acre per year,  then adjusted labor cost would be $1,100 per
acre per year.

Metric Conversion.  Metric conversion factors are given for
those parameters which appear in the cost curves.  Addition-
al metric conversion factors are given in Appendix G.
                              66

-------
Sources.   The various sources of information from which
thecurves were derived are listed along with reference
numbers (in brackets).  References are presented in
Appendix C.
                              67

-------
                  PREAPPLICATION TREATMENT
AERATED LAGOONS
Basis of Costs
1.  EPA Sewage Treatment Plant Construction  Cost  Index
    = 177.5.
2.  Labor rate including fringe benefits  - $5.00/hr.
3.  Electrical power cost = $0.02/kwh.

Assumptions
1.  Average detention time 7 days.
2.  15-ft (4.6 m) water depth.
3.  Horsepower requirement based on meeting  oxygen  demand.
4.  Small impeller floating aerators.
5.  Capital cost includes:
    a.  Excavation, embankment, and seeding  of  lagoons
    b.  Service road and fencing
    c.  Riprap embankment protection
    d.  Hydraulic control works
    e.  Aeration equipment and electrical equipment
Metric Conversion
1.  mgd x 43.8 = I/sec
Sources
Derived from previously published information  [37].
                                68

-------
  10.000
c/>  1,008
     too
       0 I
                                                CAPITAL COST
                          1                 10

                                 FLOW.  MGD
                                                            III
  30.000
  10,000
i-  1 . 000
M
     100
                           LABOR
                                OPERATION & MAINTENANCE COST
                                             POWER
                                              MATERIALS-
                                                           —
       0. 1
1                 H

      FLOW. MGD
                                                             100
     FIGURE 16.  PREAPPLICATION  TREATMENT -  AERATED  LAGOONS
                                   69

-------
               PREAPPLICATION  TREATMENT
CHLORINATION
Basis of Costs
1.  EPA Sewage Treatment Plant Construction Cost
    Index = 177.5.
2.  Labor rate including fringe benefits  = $5.00/hr.
3.  Chlorine cost = $0.05/lb ($0.023/kg).
Assumptions
1.  Capital cost includes:
    a.  Chlorination facilities with  flash mixing  and
        contact basin
    b.  Chlorine storage
    c.  Flow measuring device
2.  Maximum dosage capacity, 10 mg/1.  Average  dosage,
    5 mg/1.
3.  Chlorination contact time, 30 min for average  flows.
Metric Conversion
1.  mgd x 43.8 = I/sec
Sources
Derived from previously published information  [37].
                             70

-------
  1,000
    1 00
      :
       0. I
                                             CAPITAL  COST]
1                 10
     FLOW, MGD
                                                           1 00
  10,000
co  1 . 000
     1 00
                               OPERAT I OH & MAINTENANCE COST
            •ATERIALS OTHER THAN CHLORINE
        0 1
                                                           1 00
      FIGURE 17.  PREAPPLICATION TREATMENT  - CHLORINATION
                                 71

-------
                        TRANSMISSION
GRAVITY PIPE

Cost curves are given for gravity pipe that may be of use for
any applicable segment of the system, such as for conveying
(1) wastewater from the collection area to preapplication
treatment facilities, (2) treated water from existing treat-
ment facilities to the land application site, or (3) recovered
renovated water from the land application site to a discharge
point.

Basis of Costs

1.  EPA Sewer Construction Cost Index = 194.2.

2.  Labor rate including fringe benefits = $5.00/hr.

Assumptions

1.  Curves given for various depths of cover over crown of
    pipe in feet.

2.  Moderately wet soil  conditions.

3.  All'excavation in earth.

4.  Capital cost includes:

    a.  Pipe  and fittings
    b.  Excavation
    c.  Laying and jointing                    ,,-.,,
    d.  Select imported  bedding and  initial  backfill
    e.  Subsequent backfill  of native material
    f.  Manholes
    g.  Testing and  cleanup
5.  Labor  cost includes  periodic  inspection  of  line.

6.  Materials cost includes  periodic cleaning by contractor.

Note:   For cost of repaying  see Figure  20,  "Force  Mains."

Adjustment Factor

 1.  Soil conditions  (capital cost):   From  approximately
    0.80 for  dry to  approximately 1.20  for wet  conditions.

Metric Conversion

 1.   in.  x  2.54 =  cm

 2.   ft x 0.305 =  m

 Sources
 Derived from previously-published information [6]
                               72

-------
     500
 J   100
     I 00
u.
<
                DEPTHS OF  COVER  IN FEET
                                   • D
                                                              1 00
                            PIPE SIZE.  INCHES
                                OPERATION & MAINTENANCE COSJ
                                                             I 00
                            PIPE SIZE. INCHES
             FIGURE 18.  TRANSMISSION -  GRAVITY PIPE
                                  73

-------
                        TRANSMISSION
OPEN CHANNELS

Cost curves are given for open channels that may be of use
for any applicable segment of the system, such as tor con-
veying (1) wastewater from the collection area to preappli-
cation treatment facilities, (2)  treated water from existing
treatment facilities to the land  application site,  or
(3) recovered renovated water from the land application site
to a discharge point.

Basis of Costs

1.  EPA Sewer Construction Cost Index = 194.2.

2.  Labor rate including fringe benefits = $5.00/hr.
Assumptions

1.   Stable soil, predominantly flat terrain.

2.   Capital cost includes:
     a.   Slip-formed concrete-lined trapezoidal ditches with
          1:1  side slopes
     b.   Earth  berm
     c.   Simple drop structure every 1/2 mile  (805 mj

 3.   Labor cost includes periodic  inspection,  cleaning, and
     minor repair work.
 4.   Materials  cost'includes major repair or ditch relining
     after 10 yr by contractor.

 Adjustment  Factor

 1.   Irregular  terrain (capital  cost):  1.10  to 1.40.

 Metric Conversion

 1.   ft x 0.305 = m

 Sources

 Derived from cost  calculations  based on"a  series of typical
 designs.  Unit costs based on price quotes from an irriga-
 tion contractor.
                                 74

-------
     1 00
M
o
u
0
     1 00
      I
                                                        COS7
                                            z
                                   I :
                                                              I 00
                           CHANNEL PERIIETER.  FT
                   MATERIALS
                           \
                                OPERATION & MAIHTEHANCE COST]
                                       LAID*
                                                             100
                          CHANNEL PERIMETER. FT
             FIGURE  19.  TRANSMISSION -  OPEN  CHANNELS
                                  75

-------
                        TRANSMISSION
 FORCE MAINS
 Cost curves are given for force mains that may be of use for
 any applicable segment of the system, such as for conveying
 (1) wastewater from the collection area to preapplication
 treatment facilities, (2) treated water from existing treat-
 ment facilities to the land application site, or (3)  recovered
 renovated water from the land application site to a discharge
 point.

 Basis of Costs

 1.  EPA Sewer Construction Cost Index = 194.2.

 2.  Labor rate including fringe benefits  = $5.00/hr.
 Assumptions

 1.  Depth of cover over  crown  of pipe,  4  to  S  ft (1.2 to
     1.5 m).

 2.  Moderately wet soil  conditions.
 3.  All excavation in earth.

 4.  Capital cost  includes:

     a.   Pipe and  fittings
     b.   Excavation
     c.   Laying and jointing
     d.   Select imported  bedding and  initial  backfill
     e.   Subsequent backfill of native material
     f.   Testing and cleanup
 5.  Repaving cost included as  separate curve.

 6.  Materials cost includes periodic cleaning by contractor.

•Note:  These curves should be  used in conjunction with  those
        in Figure  21, "Transmission-Effluent  Pumping."

 Adjustment  Factor

 1.  Soil conditions (capital cost):  From approximately
     0.80 for dry  to approximately 1.20 for wet conditions.

 Metric  Conversion

 1.  in.  x 2.54 -  cm

 2.  ft.  x 0.305 = m

 Sources

 Derived  from previously  published information [6] .
                               76

-------
1 . 000
  1 00
  1 0 0
    :
                                                           1 00
                          PIPE SIZE, INCHES
                             OPERAT I OH & MAINTENANCE
                                      MATERIALS
                                 I c
                                                           100
                           PIPE SIZE,  INCHES
           FIGURE 20.  TRANSMISSION -  FORCE  MAINS
                               77

-------
                       TRANSMISSION
EFFLUENT PUMPING

Basis of Costs

1.  EPA Sewage Treatment Plant Construction Cost Index
    = 177.5.
2.  Labor rate including fringe benefits = $5.00/hr.

3.  Electrical power cost = $0.02/kwh.



Assumptions

1.  Capital and power cost curves given for various total
    heads in feet.

2.  Capital costs are related to peak flow in mgd.
    Operation and maintenance costs are related to
    average flow.

3<  Capital cost includes:
    a.  Fully enclosed wet well/dry well type structure
    b.  Pumping equipment with standby facilities
    c.  Piping and valves within structure
    d.  Controls and electrical work
4.  Labor cost includes operation, preventive maintenance,
    and minor repairs.
5.  Materials cost includes repair work performed by out-
    side contractor and replacement of parts.

Note:  These curves should be used in conjunction with those
       in Figure 20. "Transmission-Force Mains."

Metric Conversion

1.  ft x 0.305 = m

2.  mgd x 43.8 = I/sec

Sources

Derived from various sources  [6, 37],
                               78

-------
  5, 000
 1 . 000
   1 00
                                                        1 00
too.ooo
 10.000
  1 . 000
   1 00
                              OPERATIOH & MAINTENANCE COST
      0. 1
                                                        1 00
      FIGURE  21.  TRANSMISSION  - EFFLUENT  PUMPING
                             79

-------
                           STORAGE


STORAGE (0.05-10 MILLION GALLONS)

Basis of Costs

1.  EPA Sewer Construction Cost Index = 194.2.
2.  Labor rate including fringe benefits = $5.00/hr.

Assumptions

1.  Dikes formed from native excavated material.

2.  Inside slope of dike, 3:1; outside slope, 2:1.
    12-ft (3.7 m) wide dike crest.
3.  5-ft (1.5 m) depth of reservoirs less than 1 mil  gal.
    (3,790 cu m), increasing to 12-ft (3.7 m) depth of
    reservoirs greater than 10 mil  gal.  (37,900 cu m).

4.  3-ft (0.9 m) freeboard.
5.  Rectangular reservoir on level  ground.

6.  Cost of lining given for asphaltic lining of entire
    inside area of reservoir.  Must be added to reservoir
    construction curve to obtain cost of a lined reservoir.
    For other types of lining see adjustment factors.
7.  Cost of embankment protection given for 9 in. (22.8  cm)
    of riprap on inside slope of dike.

8.  Labor cost includes maintenance of dike.
9.  Materials cost includes bottom scraping and patching
    of lining by contractor after 10 yr.

Note:  The design and cost of storage reservoirs may be
       highly variable and will depend on the type of
       terrain, type of earth material encountered, and
       other factors.  If the expected design differs
       significantly from the one summarized above, a
       cost estimate should be arrived at independently.

Adjustment Factor

1.  For linings other than asphaltic membrane:

    a.  Bentqnite - 0.86
    b.  PVC  (10 mil) with soil blanket - 1.21
    c.  Soil cement - 1.21
    d.  Petromat  - 1.24
    e.  Butyl neoprene  (30 mil) - 1.97

Metric Conversion

1.  mil  gal.  x  3,790  =  cu m

Sources

Derived  from cost calculations  based on  a  series  of  typical
designs.
                               80

-------
1.000
  1 00
  1 -
    0.4
    8. 01
                        EMBANKMENT PROTECTION
       RESERVOIR CONSTRUCTION
   0.1                  1
STORAGE VOLUME, MILLION GALLONS
 4. 010
 I .in
                                OPERATION & MAIHTENANCE COS
                         o.t
                      STORAGE VOLUME,  MILLION GALLONS
        FIGURE 22.  STORAGE  (0.05-10 MILLION GALLONS)
                                    81

-------
                          STORAGE

STORAGE (10-5,000 MILLION GALLONS)

Basis of Costs

1.  EPA Sewer Construction Cost Index = 194.2.

2.  Labor rate including fringe benefits = $5.00/hr.

Assumptions

1.  Dikes formed from native excavated material.

2.  Inside slope of dike, 3:1; outside slope, 2:1.
    12-ft (3.7 m) wide dike crest.

3.  12-ft (3.7 m) depth of reservoir with 3-ft  (0.9 m)
    freeboard.
4.  Rectangular reservoir on level ground.

5.  Reservoirs greater than 50 acres (20 ha) divided into
    multiple cells.
6.  Cost of lining given for asphaltic lining of entire
    inside area of reservoir.  Must be added to reservoir
    construction curve to obtain cost of a lined reservoir.
    For other types of lining see adjustment factors.

7.  Cost of embankment protection given for 9 in. (22.8 cm)
    of riprap on inside slope of dike.

8.  Labor cost includes maintenance of dike.

9.  Materials cost includes bottom scraping and patching
    of lining by contractor after 10 yr.

Note:  The design and cost of storage reservoirs may be
       highly variable and will depend on the type of
       terrain, type of earth material encountered, and
       other  factors.  If the expected design differs
       significantly from the one summarized  above, a
       cost estimate must normally be arrived at  independ-
       ently.

Adjustment Factor

1.   For  linings other than asphaltic membrane:

     a.   Bentonite  - 0.86
     b.   PVC  (10 mil) with soil blanket  -  1.21
     c.   Soil  cement - 1.21
     d.   Petromat  - 1.24
     e.   Butyl neoprene  (30 mil) - 1.97

Metric Conversion

1.   mil  gal.  x  3,790  =  cu m

Sources^

Derived from cost calculations  based on a series  of  typical
designs.
                               82

-------
 40.000
 10.BOO
  1,000
    100
                                          EMBANKMENT PROTECTION
       ' I
 110                >.080
STORAGE VOLUME.  MILLION  8ALLONS
                                                              10, Ota
    100
                                 OPERATION & MAINTENANCE COSJ
v»    10
    0 . 4
        ! -
                                              LABOR
  too               i.ooo
STORAGE VOLUME. MILLION GALLONS
                                                              10.000
           FIGURE  23.  STORAGE  (10-5,000  MILLIONS  GALLONS)
                                      83

-------
                  FIELD PREPARATION
SITE CLEARING

Basis of Costs

1.  EPA Sewer Construction Cost Index = 194.2.
Assumptions

1.  Heavily wooded--fields cleared and grubbed.
2.  Brush and trees--mostly brush with few trees.   Cleared
    using bulldozer-type equipment.
3.  Grass only--abandoned farmland requiring disking only.

4.  No capital return included for value of wood removed
    from site.
5.  All debris disposed of onsite.


Note:  In actual practice site conditions will be  quite
       variable, and  interpolation between curves  may be
       required.

Adjustment Factor

1.  Debris disposed offsite:  1.8 to 2.2.

Metric Conversion

1.  acre x 0.405 = ha

Sources

Based on a survey of  actual construction costs for existing
systems.
                             84

-------
IM. 090
 10.DfcO
  1 , 000
    I 3D
          X
     1 3
         X
    0. I
              HEAVILY WOODED:
                      -UU
^At
                      TOT

                            z

                                    TOTAL
                                    BRUSH AND TREES:
                                                CAPITAL  COST
                                              X
                                         iRASS ONL
        I
  110                '••»
      FIELD AREA, ACRES
                                                            10.Oil
          FIGURE 24.  FIELD PREPARATION  - SITE CLEARING
                                   85

-------
                   FIELD  PREPARATION



LAND LEVELING FOR SURFACE  IRRIGATION

Basis of Costs

1.  EPA Sewer Construction Cost Index  =  194.2.



Assumption^

1.  Land previously cleared and rough  leveled.

2.  Curves given for volumes of cut of 500 and  750 cy/acre
    (945 and 1,418 cu m/ha) .

3.  Costs include:

    a.  Surveying
    b.  Earthmoving
    c.  Finish grading
    d.  Ripping two ways
    e.  Disking
    f.  Landplaning
    g.  Equipment mobilization

4.  Clay loam soil.

Note:  In many cases, 500  cy/acre is sufficient, while the
       curve for 750 represents conditions requiring con-
       siderable earthmoving.  The curves should generally
       be used in conjunction with those in Figure 24,
       "Field Preparation-Site Clearing," and either
       Figure 29, "Distribution-Surface Flooding Using
       Border Strips," or Figure 30, "Distribution-Ridge
       and Furrow Application."

Adjustment Factor

1.  Volumes of cut:  0.2 + 0.0016C  where C = volume of cut,
    cy/acre.  Cost based on 500 cy/acre curve.

Metric Conversion

1.  acre x 0.405 = ha

2.  cy/acre x 1.89 = cu m/ha

Sources

Derived from cost calculations based on a series of typical
designs and consultation with the California Agricultural
Extension Service.
                              86

-------
18,000
 I 000
  1 00
   I 0
     > :
           :z:
               tx
                        Z
                     1 00              I.000
                        FIELD AREA. ACRES
10.000
                 FIGURE  25.  FIELD  PREPARATION -
             LAND LEVELING FOR SURFACE IRRIGATION
                               87

-------
                   FIELD PREPARATION



OVERLAND FLOW TERRACE CONSTRUCTION

Basis of Costs

1.  EPA Sewer Construction Cost Index = 194.2.



Assumptions

1.  Land previously cleared and rough leveled.
2.  Curves given for volumes of cut of 1,000 and 1,400
    cy/acre (1,890 and 2,646 cu m/ha).

3.  Costs include:
    a.  Surveying
    b.  Earthmoving
    c.  Finish grading
    d.  Ripping two ways
    e.  Disking
    f.  Landplaning
    g.  Equipment mobilization
4.  Clay soil with only nominal amount of hardpan.

5.  Final slopes of 2.5*.

Note:  A cut of 1,000 cy/acre would correspond to terraces
       of approximately 175-foot (53.4 m) width with a slope
       of 2.5% from initially level ground, while a cut of
       1,400 cy/acre would correspond to terraces of approxi-
       mately 250-foot (76.2 m) width and 2.51 slope.  The
       curves should generally be used in conjunction with
       those in Figure 24, "Field Preparation-Site Clearing,"
       and Figure 31, "Distribution-Overland Flow."

Adjustment Factor

1.  Volumes of cut:  0.2 + 0.0008C where C  = volume of cut,
    cy/acre.  Cost based on 1,000 cy/acre'curve.

Metric Conversion

1.  acre x 0.405  = ha

2.  cy/acre x  1.89 = cu m/ha

Sources

Derived  from  cost calculations based  on  a series  of typical
designs.
                             88

-------
40.BOO
10.ODD
 I . ODD
  1 DO
   i ;•
     i :
                                             i   i  i i  i r
                               VOLUMES OF
                               CUT CY/URE
                                                7
                     100               1000

                         FIELD AREA, ACRES
                                                      to.ooo
               FIGURE 26.  FIELD PREPARATION -
             OVERLAND FLOW TERRACE  CONSTRUCTION
                               89

-------
                           DISTRIBUTION
 SOLID  SET  SPRAYING (BURIED)
 Basis of Costs
 1.  EPA Sewer Construc'tion Cost Index = 194.2.
 2.  Labor rate including  fringe benefits = $5.00/hr.

 Assumptions
 1.  Lateral spacing, 100  ft  (30.5 m).  Sprinkler spacing,
     80 ft  (24.4 m) along  laterals.  5.4 sprinklers/acre
     (2.2 sprinklers/ha).
 2.  Application rate 0.20 in./hr (0.51 cm/hr).

 3.  16.5 gpm (1.04 I/sec) flow to sprinklers at 70 psi
     (4.9 kg/sq cm).
 4.  Flow to laterals controlled by hydraulically operated
     automatic valves.
 5.  Laterals buried 18  in.  (46 cm).  Mainlines buried 36 in.
     (91 cm).
 6.  All pipe 4 in. (10  cm) diam and smaller is PVC.  All
     larger pipe is asbestos  cement.
 7.  Materials cost includes  replacement of sprinklers and
     air compressors for valve controls after 10 yr.
 Adjustment Factors

        Item            Capital cost        Labor       Materials
1.  Irregular-shaped fields  1.15 to 1.30
2.  Sprinkler spacing       0.68 + 0.06S    0.6S + 0.06SS    0.1 + 0.17S
Note: S » sprinklers/acre.
 Metric Conversion
 1.  acre  x 0.405 = ha
 2.  in. x  2.54 = cm
 Sources
 Derived from a survey of  existing systems and cost calcula-
 tions based on a series of typical designs.
                                  90

-------
100,000
 10.009
.  1 . 000
    100
     t:
       i:
                        100              1.000
                           FIELD AREA, ACRES
                                                         10,000
    .100
    too
                               OPERATION & MAINTENANCE COST
                        100               1.000
                           FIELD AREA. ACRES
                                                         10.000
      FIGURE 27.  DISTRIBUTION - SOLID SET  SPRAYING (BURIED)
                                  91

-------
                         DISTRIBUTION
CENTER PIVOT SPRAYING
Basis of Costs
1.  EPA Sewer Construction Cost  Index =  194.2.
2.  Labor rate including fringe  benefits = $5.00/hr.
3.  Electrical power cost = $0.02/kwh.

Assumptions
1.  Heavy-duty center pivot rig  with electric drive.
2.  Multiple units for field areas  over  40 acres (16.2 ha).
    Maximum area per unit, 132 acres (53.4 ha).
3.  Distribution pipe buried 36  in.  (91  cm).
4.  Materials cost includes minor repair parts and major
    overhaul of center pivot rigs after  10 yr.
5.  Power cost based on 3.5 days/wk operation of each rig.
Metric Conversion
1.  acre x 0.405 = ha

Sources
Derived from a survey of existing systems and cost calcula-
tions based on a series of typical designs.
                               92

-------
   .eos
  IB.956
   I . 000
    1 00
     ;
       i :
                        111               1.000

                           FIELD AREA. ACRES
10. 001
    900
    1 00

M
B
U
                                OPERATION il MAINTENANCE COST
                         too              1,000
                            FIELD AREA, ACRES
                                                           II.Oil
        FIGURE  28. DISTRIBUTION - CENTER PIVOT SPRAYING
                                    93

-------
                         DISTRIBUTION


SURFACE FLOODING USING BORDER STRIPS
Basis of Costs
1.  EPA Sewer Construction  Cost  Index = 194.2.
2.  Labor rate including fringe  benefits = $5.00/hr.

Assumptions
1.  Border strips 40 ft  (12 m) wide and 1,150 ft  (350 m)
    long.
2.  Concrete-lined trapezoidal distribution ditches with  2
    slide gates per strip.
3.  Rectangular-shaped fields previously leveled  to a slope
    of approximately 0.4%.
4.  Clay loam soil.
5.  Continuous operation for large systems and  5  days/wk  for
    systems smaller than 50 acres (20 ha) .
6.  Materials cost includes rebordering every 2 yr and major
    relining of ditches  after 10 yr.
Note:  A flatter slope or more permeable soil condition would
       require a reduction  in strip length.
Adjustment Factors

                                     Labor and
        Item            Capital cost    materials
1.  Irregular-shaped fields  1.15 to 1.30    1.10 to 1.20
2.  Strip length          2.4 - 0.0012L   1.8 - 0.0007L

Note:  L - length of border strip, ft.
Metric Conversion
1.  acre  x  0.405  =  ha
2.  ft x  0.305  = m
Sources
Derived  from cost  calculations based on a  series  of  typical
designs .
                               94

-------
   10.000
    1 . 000
      100
      10
        i :
                                               CAPITAL
                                          >
                                             X
                                                ;"
                         100              1,000
                            FIELD AREA. ACRES
10.000
     600
     1 00
                                OPERATION & MAINTENANCE COST
                        100               I,000
                            FIELD AREA.  ACRES
10.000
FIGURE  29. DISTRIBUTION - SURFACE FLOODING USING BORDER  STRIPS
                                  95

-------
                          DISTRIBUTION
 RIDGE AND FURROW APPLICATION
 Basis of Costs
 1.   EPA Sewer Construction Cost Index =  194.2.
 2.   Labor rate including fringe benefits  =  $5.00/hr.

 Assumptions
 1.   Gated aluminum pipe distribution with outlets  on  40-in.
     (102 cm)  centers.
 2.   Gated pipe spacing based on 1,200-ft  (366 m)  long furrows
 3.   Rectangular-shaped fields previously  leveled  to a slope
     of approximately 0.34.
 4•   Loam soil.
 5.   Continuous  operation for large systems  and partial  oper-
     ation for  systems  smaller than 50 acres  (20 ha).
 6.   Materials  cost  includes  replacement of  gated pipe after
     10 yr.
 7.   Cost of furrows  included in planting  and harvesting.
 Note:   A flatter  slope or more permeable  soil condition would
        require  a  reduction  in furrow length.
 Adjustment Factors
                                      Labor and
       Iten              Capital cost     aaterials
1.  Irregular-shaped fields   1.10 to 1.25   1.10 to 1.20
2.  Furrow length           2.2 - 0.001L   2.44 - 0.0012L

Note:  L - length of furrow, ft.

Metric Conversion
1.   acre  x  0.405 =  ha
2.   ft x  0.305  = m
Sources
Derived from cost calculations based on a series of  typical
designs.
                                96

-------
10.000
 1 . 000
   100
    i :•
      ti
101               I.Ml
   FIELD AREA, ACRES
                                                         10.111
 1 .000
                              OPERATION & MAINTENANCE COSJ
                       too               '.o°°
                          FIELD AREA. ACRES
                                                         I 0.000
   FIGURE 30.  DISTRIBUTION -  RIDGE AND FURROW APPLICATION
                                  97

-------
                         DISTRIBUTION
OVERLAND FLOW
Basis  of Costs
1.   EPA Sewer Construction Cost Index = 194.2.
2.   Labor rate  including fringe benefits = $5.00/hr.

Assumptions
1.   Terraces  250  ft  (760 m)  wide and previously leveled
     to  2.5% slope.
2.   Application rate  over field area 0.064 in./hr
     (0.16  cm/hr).
3.   13-gpm (0.83  I/sec)  flow to sprinklers at 50 psi
     (3.5  kg/sq  cm).
4.   Laterals  70 ft  (21.3 m)  from top of terrace.
5.   Flow  to laterals  controlled by hydraulically operated
     automatic valves.
6.   Laterals buried  18  in.  (46 cm).  Mainlines buried  36 in.
     (91 cm).
7.  All pipe  4-in.  (10  cm)  diam and smaller is PVC.  All
     larger pipe is asbestos  cement.
8.  Materials cost includes  replacement of sprinklers  and
     air compressors for  valve controls after 10 yr.
Adjustment Factors
        Item             Capital cost       Labor       Materials
1.  Irregular-shaped fields   1.15 to 1.30
2.  Terrace width          1.5 - 0.002T    1.75 - 0.003T    2.5 - 0.006T

Note: T • terrace width, ft.

Metric Conversion
1.  acre  x 0.405 = ha
2.  ft x 0.305 = m
Sources

Derived from  a survey of  existing  systems and cost calcula-
tions based on a series of  typical designs.
                                98

-------
1D«.000
 19.000
•  1.000
    100

       II
                                                 '   '   I I  I I
100                1.000
    FIELD  AREA.  ACRES
                                                            10.000
  1,000
    100
     i :
       i :
            T—I I I  I I I
                                                       I  I I IT
                                OPERATION & MAINTENANCE COST
1>t               1 . 000
    FIELD'AREA.  ACRES
                                                            10.000
              FIGURE  31.  DISTRIBUTION -  OVERLAND FLOW
                                   99

-------
                           DISTRIBUTION
INFILTRATION BASINS
Basis of Costs
1.  EPA Sewer Construction Cost Index = 194.2.
2.  Labor rate including fringe benefits = $5.00/hr.

Assumptions
1.  Multiple unit infiltration basins with 4-ft (1.22 m) dike.
2.  Dikes formed from native excavated material.
3.  Inside slope of dike.3:1; outside slope, 2:1.
    6-ft (1.83 m) wide dike crest.
4.  Deep sandy soil.
5.  Materials cost includes annual  rototilling of infiltration
    surface and major repair of dikes after 10 yr.
Metric Conversion
1.  acre x 0.405 = \a
Sources
Derived from cost calculations  based  on a series of typical
designs.
                                100

-------
  7,000
ta  1,000
M
c=
CJ
    100
     i :
                                                i   i  i  i~rr
                         10                100

                            FIELD AREA. ACRES
                                                           1 . OSO
   1.000
     1 00
                                OPERATION & MAINTENANCE COS
                         10
                            FIELD AREA. ACRES
                                                           1.110
           FIGURE 32.  DISTRIBUTION  - INFILTRATION  BASINS
                                    101

-------
                       DISTRIBUTION
DISTRIBUTION PUMPING

Basis of Costs

1.  EPA Sewage Treatment Plant Construction Cost Index
    = 177.S."
2.  Labor rate including fringe benefits = $5.00/hr.

3.  Electrical power cost = $0.02/kwh.



Assumption^

1.  Capital and power cost curves given for various total
    heads in feet.
2.  Capital costs arc related  to peak flow in mgd.  Opera-
    tion  and raani tenance costs are related average flow.

3.  Capital cost  includes:

    a.  Structure built into dike of storage reservoir
    b.  Continuously cleaned water screens
    c.  Pumping equipment with norn>al standby •facilities
    d.  Piping and valves within structure
    e.  Controls  and electrical work
4,  Labor cost includes operation, preventive maintenance,
    and minor repairs.
5.  Materials cost includes repair work performed by out-
    side  contractor and replacement of parts.

Note:  The curves should generally be used in conjunction
       with curves for a particular method of distribution,

Metric Conversion

1.  ft x  0.305 = m

2.  mgd x 43.8 =  I/sec

Sources

Derived from a series of typical designs and various cost
data  [6,  37].
                              102

-------
  4 , 008
  1.000
    «I
      0. 1
                                                         1 DO
100.000
 10.000
  I.000  =
   1 00
                              OPE RAT I OH & MAINTENANCE COST
      0. 1
                                                         1 00
                            AVEftABE FLOW, MOD
      FIGURE 33.  DISTRIBUTION - DISTRIBUTION PUMPING
                             103

-------
               RECOVERY OF  RENOVATED WATER
UNDERDRAINS

Basis of Costs

1.  EPA Sewer Construction Cost Index  =  194.2.

2.  Labor rate including fringe benefits =  $5.00/hr.



Assumptions

1.  Costs given for spacings of 100  and  400 ft  (30  and
    122 m)  between drain pipes.

2.  Capital cost includes:

    a.  Drain pipes buried 6 to 8 ft (1-8 to 2.4  m).
    b.  Interception ditch along length  of  field
    c.  Weir for control of discharge

3.  Labor cost includes inspection and unclogging of  drain
    pipes at outlets.

4.  Materials cost includes high pressure jet cleaning  of
    drain pipes every 5 yr, annual cleaning of  interceptor
    ditch,  and major repair of ditches after 10 yr.

Note-:  Spacings as small as 100 ft may be required  for  clayey
       soils; a 400-ft spacing is typical for sandy soil
       conditions [23].

Metric Conversion

1.  ft x 0.305 = m

2.  mgd x 43.8 = I/sec

Sources

Derived from cost calculations based on  a series  of typical
designs.
                            104

-------
ZD, DOO
11.000
CAPITAL COST. $(THOUSANOS)
— O
M • •
j. 0 0 0




















4
	 2






















x

























































SPACING BETWEEN
UNDERDRAINS IN FEET,












X

X













j/


s












^


x1
















^











^




X











•^



f














^r
s>r
\r










X

jr,













X1






















x


X
















-*-*


2


















— i —
s^ *>
^M
rX^^>




^*










i iii
WP/HL COST





^100
L^
f 	






400
f














X


^
^s^
*
















f

— -^
_^*


















/


X
-


















J/~





















j**-




x








































        :
100               1.000
   FIELD AREA, ACRES
                                                          10.000
    200
    t 00
     •: r
V,

t-:
                               OPERATION & MAINTENANCE COST
       1!
100               '••••
    FIELD AREA, AtRES
                                                          it,oeo
    FIGURE 34.  RECOVERY OF  RENOVATED WATER  - UNDERDRAINS
                              105

-------
                 RECOVERY  OF RENOVATED WATER
TAILWATER RETURN

Basis of Costs

1.  EPA Sewer Construction Cost  Index  =  194.2.

2.  Labor rate including fringe  benefits ••=  $5.00/hr.

3.  Electrical power cost = $0.02/kwh.



Assumptions

1.  Costs are given versus flow  of recovered water.

2.  Capital cost includes:

    a.  Drainage collection ditches
    b.  Pumping station forebay, 1/3 acre (0.14 ha).
    c.  Pumping station with shelter and multiple pumps
    d.  Piping to nearest point  of distribution mainline
          (200 ft or 61 m)
3.  Materials cost includes major repair of pumping  station
    after 10 yr.

Note:  Generally, the flow of recovered water can be ex-
       pected to be 10 to 40 percent (an average would be
       20 percent) of the flow of applied water, depending
       on soil conditions, application rate, slope,  and
       type of crop or vegetation.  This range is based on
       irrigation practice where water is plentiful  and
       soil-water quality conditions may dictate excess
       water application.  Should return piping lengths be
       significantly more than 200 ft (61 m), to the nearest
       distribution main, the additional costs could be
       obtained from Figure 20,  "Transmission-Force  Mains."

Metric Conversion

1.  mgd x 43.8 = I/sec

Sources

Derived from cost calculations based on  a series of  typical
designs.
                                106

-------
      18
       a.01
                         0.1                 ,
                        FLOW OF RECOVERED WATER. MGD
  30 . IK
  10.000
~

*
  I .000
    too
     e:
       0.01
                                OPERAT I OH & MAINTENANCE COST
                                 LABOR
                           MATER ALS
                                             POWER
 1.1                 f
FLOW OF RECOVERED WATER, MGD
                                                             i :
             FIGURE 35.  RECOVERY  OF RENOVATED WATER-
                          TAILWATER RETURN
                                   107

-------
              RECOVERY OF  RENOVATED WATER
RUNOFF COLLECTION FOR OVERLAND FLOW

Costs are given for overland flow runoff collection by
both open ditch and gravity pipe.  The curves may be used
in conjunction with those in Figure 37, "Recovery of
Renovated Water-Chlorination and Discharge for Overland
Flow."

Basis of Costs

1.  EPA Sewer Construction Cost Index = 194.2.

2.  Labor rate including fringe benefits  = $5.00/hr.

Assumptions

1.  Cost of lateral collection ditches along bottom of
    terrace in included in Figure 26 - "Field Preparation-
    Overland Flow Terrace Construction".
2.  Open Ditches:

    a.  Network of unlined interception ditches sized
        for a 2-in./hr storm
    b.  Culverts under service roads
    c.  Concrete drop structures at 1,000-ft (305 m)
        intervals
    d.  Materials cost includes biannual  cleaning of
        ditches with major repair after 10 yr
3.  Gravity Pipe:

    a.  Network of gravity pipe interceptors with inlet/
        manholes every 250 ft (76.3 m) along submains
    b.  Storm runoff is allowed to pond at inlets
    c.  Each inlet/manhole serves 1,000 (305 ra) of
        collection ditch
    d.  Manholes every 500 ft along interceptor mains.
    e.   Operation  and  maintenance cost includes periodic
        cleaning of  inlets and  normal  maintenance of
        gravity  pipe

Note:  Open  ditches should be  used where  possible.   Gravity
       pipe  systems may  be required when  unstable  soil
       conditions are  encountered, or when  flow  velocities
       are erosive.

Metric Conversion

1.  acre x 0.405 = ha

Sources

Derived from cost calculations based on a series of typical
designs.
                            108

-------
 20.000
 10.000
   , 000
    1 00
     1 0
       • :
             GRAVITY PIPE SYSTEM^
                                                I   I—I MIL
                                               CAPITAL COST
                                      OPEN DITCH SYSTEM
                        1 00
                                         1 .000
                                                           10.000
                           FIELD AREA. ACRES
    1 00
u
I
                                OPERAT I OH & MAINTENANCE COST
           BRAVITY PIPE SYSTEM
    0. 4
                         100               1.000
                            FIELD AREA.  ACRES
                                                           1 0. 000
         FIGURE 36.  RECOVERY OF  RENOVATED  WATER  -
           RUNOFF COLLECTION FOR OVERLAND  FLOW
                              109

-------
           RECOVERY OF  RENOVATED WATER




CHLORINATION AND DISCHARGE FOR OVERLAND FLOW

Basis of Costs

1.  EPA Sewage Treatment Plant Construction Cost  Index
    = 177.5.

2.  Labor rate including fringe benefits = $5.00/hr.
3.  Chlorine cost = $0.05/lb ($0.023/kg).


Assumptions

1.  Capital cost includes:

    a.  Chlorination facilities with flash mixing  and
          contact basin
    b.  Chlorine storage
    c.  Flow measuring device
    d.  Stormwater overflow structure

2.  Maximum dosage capability,  10 mg/1.  Average dosage,
    5 mg/1.

3.  Chlorination contact time,  30 rain.

Note:  The curves should be used in conjunction with  those
       in Figure 36, "Recovery of Renovated Water-Runoff
       Collection for Overland Flow."

Metric Conversion

1.  mgd x 43.8 = I/sec

Sources

Derived from previously published information [27], and
cost calculations based on a series of  typical designs.
                          110

-------
   1 . BOO
    too
     t 0
       0. I
                                               CAPITAL  COST
                                           I 0
                        FLOI OF RECOVERED IATER.  H6D
                                                             100
  10.000
«•»
i-"  1.000
    109
              X
                                OPERATION & MAINTENANCE  COST]
                              LABOR
                         5 j^Z
                            S
           MATERIALS OTHER THAN CHLORINE
                     CHLORINE-
                               i.
       0. I
  i                 10
FLOW OF RECOVERED WATER,  M6D
                                                             1 00
          FIGURE  37.  RECOVERY OF  RENOVATED WATER
       CHLORINATION  AND DISCHARGE FOR  OVERLAND FLOW
                                ill

-------
              RECOVERY OF  RENOVATED WATER


RECOVERY WELLS

Basis of Costs

1.  EPA Sewage Treatment Plant Construction Cost  Index
    = 177.5.
2.  Labor rate including fringe benefits  = $5.00/hr.

3.  Electrical power cost =•$().02/kwh.
Assumptions

1.  Capital and power cost curves given for well  depths  of
    50 and 100 ft (15 and 30 m).
2.  Total head equal to well depth.

3.  Capital cost includes:
    a.  Gravel-packed wells
    b.  Vertical turbine pumps
    c.  Simple shelter over each well
    d.  Controls and electrical work
4.  Labor cost includes operation, preventive maintenance,
    and minor repairs.
5.  Materials cost includes repair work performed by outside
    contractor and replacement of parts.

Note:  The costs do not include any piping away from the
       well.  The cost of discharge piping can be obtained
       from Figure 20, "Transmission-Force Mains."

Metric Conversion

1.  ft x 0.305 = m

2.  mgd x 43.8 = I/sec

Sources

Derived from previously published information [8].
                              112

-------
   I .080
~   100
       0. I
 1.0                 10


FLOW OF RECOVERED VATER. MGO
                                                              100
  60. DM
>• 10.000

o
•

«
   t.ooo
     too
       0. 1
                          I    I    III
                                 OPERATION & MAINTENANCE COST
                           MATERIALS
                                              LABOR
                                                    50':=- =
                                             i o
                                                               too
                         FLOW OF RECOVERED WATER, MGO
              FIGURE 38.  RECOVERY  OF  RENOVATED WATER -
                            RECOVERY WELLS
                                     113

-------
                   ADDITIONAL COSTS



ADMINISTRATIVE AND LABORATORY FACILITIES

Basis of Costs

1.  EPA Sewage Treatment Plant Construction Cost Index
    = 177.5.
2.  Labor rate including fringe benefits = $5.00/hr.



Assumptions

1.  Capital cost includes:
    a.  Administration and laboratory building
    b.  Laboratory equipment
    c.  Garage and shop facilities

2.  Labor cost includes:
    a.  Laboratory analyses and reporting
    b.  Collection of samples
    c.  Maintenance of buildings
3.  Labor cost does not include administrative supervision.
    Labor for supervision included under individual components

4.  Materials cost includes:
    a.  Chemicals and laboratory supplies
    b.  General administrative supply items

Note:  When the land application system is to be an addition
       to an already existing conventional treatment system,
       complete facilities (as described here) are not re-
       quired, and the costs given should be reduced
       accordingly.

Metric Conversion

1.  mgd x 43.8 = I/sec

Sources

Derived from previously published cost information [37].
                             114

-------
  ID.000
  I . 000
1   100
     ! S
      0. 1
                        1                10

                             FLOW.  MGD
1 00
 JO.000
 It.100
  1.000
   300
      0. I

^V
•*^_
"^*









^v

*-.
"»*.

HAT






v


"l

•Rl










"V
u










•"s.








•>,


-N
_-







^x.


*N.
^ *







' V_
^^


^^









nrr


| |
OPERATION & MAINTENAHCE COS]



^

•^









v.










^










•s.

Tfc,








f
*v
•s








••
s.
s.








— —
N










s

•^







LABOR
\

•*^mlM
^*- 	



















^














— •«







*-,


•»•»










- .











s

»*
                                        ! 0
                                                        100
                             FLOW.  MGD
                  FIGURE 39.  ADDITIONAL COSTS-
           ADMINISTRATIVE  AND LABORATORY FACILITIES
                                115

-------
                   ADDITIONAL COSTS


MONITORING WELLS

Basis of Costs

1.  EPA Sewer Construction Cost Index = 194.2.
2.  Labor rate including fringe benefits = $5.00/hr.



Assumptions

1.  Capital cost includes:

    a.  4-in. (10 cm) diam drilled wells
    b.  Vertical turbine pump, 10 gpm (0.63 I/sec)
    c.  Controls and electrical work
2.  Labor cost includes preventive maintenance and minor
    repairs by staff.  Labor costs for sampling included
    in Figure 39, "Additional Costs-Administrative and
    Laboratory Facilities."
3.  Materials cost includes repair work performed by outside
    contractor and replacement of parts.

Metric Conversion

1.  ft x 0.305 = m

Sources

Derived from previously published cost information [8].
                            116

-------
 100.ODD
-* 1 0. 000
S  1,000
    200
        1 C
                                  1 00
                             WELL  DEPTH. FT
                                                          1.000
   1 . 0 00
                                          I     I   I   I  I I  I
                               OPERATION A MAINTENANCE GOSJ
                                 1 00
                             WELL DEPTH. FT
1 . 000
       FIGURE  40. ADDITIONAL COSTS  - MONITORING  WELLS
                             117

-------
                  ADDITIONAL COSTS
SERVICE ROADS AND FENCING

Basis of Costs

1.  EPA Sewer Construction Cost Index =  194.2.



Assumptions

1.  Costs of service roads and fencing given versus  field
    area based on typical system layouts.

2.  12-ft (3.67 m) service roads,  with gravel surface,
    around perimeter of area and within  larger fields.

3.  4-ft (1.22 m) stock fence around perimeter of  area.

4.  Materials costs includes major repair  after 10 yr.

Metric Conversion

1.  acre x 0.405 = ha

Sources

Derived from cost calculations based on  a  series of  typical
designs.
                           118

-------
4.000
1 , HI
  III
     11
                           SERVICE ROADS

                                    i
                                          'FENCING
                      111                1.800
                          FIELD AREA. ACRES
                                                         II.Ill
  II
  0. 2
                              OPERAT I OH & HAIHTEHAHCE COST
     \ •
III               I.000
   FIELD AREA. ACRES
                                                         10.011
 FIGURE 41.  ADDITIONAL  COSTS - SERVICE  ROADS  AND  FENCING
                                119

-------
ADDITIONAL COSTS

The following components are not readily presented by means
of curves.  Alternative means of cost estimation are there-
fore discussed.

Planting, Cultivation, and Harvesting

Annual agricultural costs will generally be quite variable,
depending on the type of crop or vegetation grown and
various local conditions.  Costs should normally be deter-
mined from local sources; however, as an aid, sample costs
to produce crops in California are given in Table 6 [42].
Similar cost information is available in most states
through cooperative extension services at land grant uni-
versities .

Yardwork

Yardwork  includes a variety of miscellaneous items.  For
conventional treatment systems, these items would generally
include:  general site clearing and grading, intercomponent
piping, wiring,  lighting, control structures, conduits,
manholes, parking, sidewalk and road paving, landscaping,
and  local fencing.  The  suggested costs for these items  are
 [37]:  (1) capital cost,  14 percent of total construction
cost; and  (2) annual  operation and maintenance cost, $1,500
to $4,000 per mgd for labor and $80 to $400 per mgd for
materials.  These cost allowances are suggested for land
application systems if applied only to the cost of pre-
application treatment components.

When applied to  the cost of a land application system as  a
whole, the proportion of costs for yardwork would be con-
siderably less because the costs of many of the items are
included  in the  cost  of  other components.

Relocation of Residents

The  purchases of large quantities of land will often
require that some residents be relocated.  If the project
is to be  federally funded, this must be conducted in
accordance with  the Uniform Relocation Assistance and
Land Acquisition Policies Act of 1970.  The cost of reloca-
tion, which can  be significant, should be estimated on the
basis of  local conditions.  Assistence in estimating this
cost can  often be obtained from agencies which must fre-
quently deal with this problem, such as the U.S. Army,
Corps of  Engineers, and  state highway agencies.
                              120

-------
  Table  6.    SAMPLE  COSTS  TO  PRODUCE CROPS  IN CALIFORNIA  [42]
                                                     Cost, $/acre
                                 Cultural  cost
    Crop
Expected         Fuel                                  Cash
 yield,          and                Equipment           over-
per acre  Labor  repairs  Materials   overhead   Harvest   head
	 Cost
                     per
                     unit
                      of
      Manage-        yield,
 Rent   ment    Total    $
Perennials
Alfalfa.
green chop
Alfalfa
hay
Alfafa,
seed
Clover,
seed
Pasture
Annuals
Barley
Corn,
silage
Cotton

Grain
sorghum


36 tons

8 tons

310 Ib

4 cwtc
12 aumd

2.5 tons

25 tons
8 cwt
Clint)

65 cwt


42

26

5

18
5

9

32
46


26


9

2
V
19b

3
1

23b

10
24


IS


69

70

51

90
46

34

43
87


58


106a

39a

--

40a
6

--

31
25


23


55

63

17

47
--

19

57
115


10


18

7

20

6
4

19

10
20


10


125

100

50

50
94

60

98
115


65


26

23

8

12
4

12

80
24


13


450

330

170

266
160

176

361
370


220


12.50

41.40

0.55

66.50
13.33

3.52

14.44
46.00


3.38
Note:   Expected yield - Yields  attainable under good management.  Usually  above average for  the major
                       producing area.
       Labor  cost - Includes wages, transportation,  housing, and fringe benefits for farm workers.
       Fuel and repairs - Includes fuel, oil, lubrication plus repairs (parts  and labor) of  farm  equipment.
       Material - Includes seed, fertilizer, water or power, spray, machine  work hired, and  other costs
                 not included  in labor or fuel and repairs.
       Equipment overhead - Depreciation, interest,  property taxes.
       Harvest  - Total cost of  harvest up to receiving payment for product.
       Cash overhead - Office,  accounting, legal, interest on operating capital, and other costs  of
                      management.
       Rent  - Actual rent or cost of  taxes, interest on investment, and depreciation of fixed facilities
             if land is owned.
       Management - Usually calculated at 5 percent of the gross income.

a.  Includes  crop stand.
b.  Custom operations.
c.  cwt - 100 Ib.
d.  aua - animal unit months or forage eaten by one 1,000-lb cow in one month.

Metric conversion:  Ib x 2.2 -  kg
                   acres x 0.40S - ha
                                               121

-------
Purchase of Water Rights

In many cases, particularly in the western states, the
consumptive use of water may require the purchase of water
rights.  This may be either a capital or annual cost and
should generally be determined on the basis of prevailing
local practices.

Service and Interest Factor

A service and interest factor must be applied to the capital
cost of the system to account for the additional cost of
items  such as:

     •  Contingencies

     •  Engineering

     •  Legal,  fiscal,  and  administrative

     •   Interest  during  construction

Generally, the  cost  for  these  items  ranges  from  about 35
percent  of the  nonland  total construction  cost for  $50,000
projects, to  about  25 percent  for  $100  million projects.

BENEFITS  (NEGATIVE  COSTS)

Benefits  that may apply  to  land  application systems  range
from the  sale of  crops  grown or  renovated  water  recovered
to  the leasing  of land  for  secondary uses  such as recrea-
tion.   Monetary or  revenue-producing  benefits  are discussed
more fully in Appendix  A, and  possible  nonrevenue producing
benefits  (social  or  environmental  factors)  are described  in
Appendix  B.

Typically, an irrigation or overland flow  treatment system
would  have an economic  benefit from  the sale of  the crop
grown.

Prices and yields will  vary with the locality and should  be
determined from local  sources.   As  an aid,  however, typical
yields and prices for  some  feed  and  fiber  crops  grown in
California for  1973 are given  in Table  7 [42].   Similar
 information  is  available in most states through  cooperative
extension services  at  land  grand universities.   The data  for
Reed canary  grass are  from  a University of Missouri publica-
 tion [2]  where  the  Missouri price range is $15 to $30 per
 ton.
                               122

-------
Table 7.   TYPICAL YIELDS AND  PRICES FOR CROPS  IN  CALIFORNIA
                            FOR 1973 [42]
                                   Price,         Yield,
              Crop         Unit   $ per unit    units per acre
        Perennials

        Alfalfa, hay       ton      49.00          8.0

        Alfalfa, seeda     cwtb     42.00          3.1

        Clover, seed3      cwt      62.50          4.0

        Reed canary grass
          hay,c            ton      20.00          4.5

        Annuals
Barley
Corn, silaged
Cotton, lint
Grain hay
Grain sorghum
cwt
ton
cwt
ton
cwt
4.58
15.00
47.00
--
5.11
50.0
25.0
8.0
1.8
65
        Note:   Prices reflect seasonal averages received by
               farmers at  the first delivery point.
        a.  For 1972.
        b.  cwt = 100 Ib.
        c.  For Missouri,  reference [2].
        d.  From reference  [10].
        Metric  conversion:  Ib x  2.2 = kg
                          acres x 0.405 = ha


COST CALCULATION  PROCEDURE

To facilitate  the use of the  cost  data presented  for Stage
II sample  cost calculation  sheets  have been developed and
are shown  as  Tables 8 and 9.   For  each alternative  to be
analyzed,  a  similar calculation  sheet could be  used.

The procedure  for calculating State  II costs  is as  follows:

     1.  Enter the cost  curve or  table for the  applicable
         cost  components and  read  off the cost.

     2.  For  operation and  maintenance costs, multiply the
         resultant annual costs per  unit by the appropriate
         units to yield  the cost  in  dollars per year.
                               123

-------
Table 8.   STAGE  II  CALCULATION  SHEET  FOR CAPITAL COSTS
  Alternative No.
  Type of system
                Average flow 	
                Analysis date
            mgd
        Cost component
          Total cost,  Amortized cost,
               $            $/yr
  Preapplication treatment
  Transmission
  Storage
  Field preparation
  Distribution
  Recovery
  Additional costs
  Service and
  interest factor §
  Land @
mil gal.
                       SUBTOTAL
       I
SUBTOTAL
   /acre
                         TOTAL
  Amortization:
  i = 	I,  n
     yr,  CRF =
,   PWF
                              124

-------
       Table  9.   STAGE  II CALCULATION  SHEET
        FOR OPERATION AND MAINTENANCE  COSTS
Alternative  No. 	      Average flow 	mgd
Type of system 	      Analysis date 	


                                   Annual cost, $/yr
                              Labor  Power  Material  Total
Preapplication treatment



Transmission



Storage 	 mil gal.

Distribution



Recovery



Additional costs
Benefits
                     TOTALS
                            125

-------
     3.  Adjust the costs for different cost indexes or
         wage or power rates.

     4.  Multiply the costs by an appropriate adjustment
         factor, if necessary.

     5.  Enter the resultant costs on the calculation sheet
         for that cost component.

For operation and maintenance costs, the total annual costs
in dollars per year for labor, power, and materials, can
now be found by summing the appropriate columns.  For
capital costs and amortized capital costs, however, several
additional steps are necessary before totals can be deter-
mined.  To obtain the total capital cost in dollars:

     1.  Increase the nonland subtotal of the costs of all
         components by the appropriate service and interest
         factor.

     2.  Add to this subtotal the cost of land.

To obtain the amortized cost in dollars per year:

     1.  Determine the capital recovery and present worth
         factors for the appropriate interest rate and
         period from Appendix E.

     2.  Multiply the nonland subtotal cost including the
         service and interest factor by the capital recov-
         ery factor to obtain the amortized nonland sub-
         total .

     3.  Determine the present worth of the salvage value
         of land by multiplying the initial cost of land
         by the appropriate present worth factor.

     4.  Subtract this value from the initial cost of land
         and multiply by the appropriate capital recovery
         factor to obtain the amortized cost of land.

     5.  Add the amortized nonland subtotal and the amor-
         tized cost of land.
                              126

-------
EXAMPLE

The use of the cost curves, adjustment factors, and cost
calculation sheets is illustrated in the following example.
A hypothetical 1-mgd (43.8 I/sec) spray irrigation system
to be constructed as part of a new wastewater treatment
system in the Baltimore area, is used in this example.  The
example is meant to illustrate all facets of the cost
curves, adjustment factors, and calculation sheets, and the
total costs should not be compared with other hypothetical
cost estimates.

Basis of Costs

1.  The analysis date is July 1974.  The EPA Construction
    Cost Indexes for that date are 204.7 for sewage treat-
    ment plants and 226.0 for sewers.

2.  The labor rate including fringe benefits is $7.50/hr.

3.  The electrical power cost is $0.02/kwh.

4.  The materials cost is assumed to be equal to February
    1973 cost.

5.  Amortization at 7% is for 20 yr (capital recovery
    factor = 0.0944, present worth factor = 0.2584).

Assumptions

1.  Preapplication treatment is to consist of preliminary
    treatment (screening, grit removal, and flow measure-
    ment), aerated lagoons, and chlorination.

2.  The distance from the preapplication treatment plant
    to the land application site is 2 miles (3.2 km).

3.  From a water balance calculation, the storage require-
    ment is 35 days of detention.

4.  The land terrain is essentially flat and covered with
    brush and trees.  Debris can be disposed of onsite.

5.  The application rate is to be 2.4 in./wk (6.1 cm/wk).

6.  The soil is a loam underlain by clay.

7.  Perennial grass is to be harvested by the staff twice
    a year, with a yield of 5 tons/acre/yr (11.2 metric
    ton/ha/yr).
                              127

-------
8.  The buffer zone requirement is 150 feet (45 m) around
    the irrigated area.

Solution (Total Capital Cost)

The determination of total capital cost is shown on a
sample cost calculation sheet (Table 10, page 132), and is
discussed for each line item.  Additional minor assumption
and adjustments are included to illustrate the range of
applicability of the cost curves.  All costs are given to
the nearest thousand dollars.

Each of the costs determined from cost curves is updated,
or trended to the analysis date by means of the indicated
EPA Construction Cost Index, as follows:

    1.  For costs keyed to EPA Sewer Construction Cost
        Index


                updated cost = cost x
                                        y

    2.  For costs keyed to EPA Sewage Treatment Plant
        Construction Cost Index

                                      226.0
                updated cost = cost x 194. 2

Land - From Figure 15, for a flow of 1 mgd (43.8 I/sec),
a nonoperating time of 5 weeks, and an application rate of
2.4 in./wk (6.1 cm/wk) .

        field area requirement = 120 acres (48.6 ha)

Total land requirements  based on a preliminary layout are:

                                       acres     ha

        Field area                      120     48.6
        Buffer zone                      33     13.4
        Roads                             3      1.2
        Storage                           9      3.6
        Preapplication treatment         10      4 . 1

                           Total        175     70.9
                             128

-------
Preapplieation Treatment - Includes
preliminary treatment, aerated lagoon,
and chlorination.

1.  Preliminary treatment - Based on maximum
    flow of 2.5 mgd (109 I/sec), updated cost
    from reference [37]

2.  Aerated lagoon - Updated cost from
    Figure 16

    Chlorination - Updated cost from Figure 17
Transmission - Includes force main, repaying,
right-or-way and easement acquisition, special
crossings, and effluent pumping station.

1.  Force main - From Figure 19, updated cost
    for 10-in. (25.4 cm) pipe is $14.50/lf

    Repaying - 1,000 ft (305 m).  From Figure
    19, updated cost of repaying for 10-in.
    pipe is $2.80/lf

    Right-of-way and easement acquisition-
    4,000 ft (1,220 m).  From local sources,
    cost is determined to be $2.00/lf

    Special crossings - 2 streets.  Cost
    determined from local sources
2.  Effluent pumping - From Figure 21,
    for total head of 150 ft (45.7 m)

Storage - From Figure 23, updated storage
costs fpr required storage volume of 35 mil
gal.  (133,000 cu m) are:

                      reservoir construction
                                      lining
                                      riprap
$ 63,000*


$ 80,000

$ 40,000

$120,000*
$153,000



$  3,000



$  8,000


$ 12,000

$176,000*


$133,000*
$ 46,000
$103,000
$ 50,000

$199,000*
*  Number entered on Table 10, page 132.
                              129

-------
Field Preparation - From Figure  24, updated
cost  or  clearing site of brush  and few  trees

Distribution - Includes solid set spraying
(buried)  distribution system and distri-
bution pumping.

1.  Solid set spraying (buried)  - Updated
    cost  from Figure 27

    Adjustment factor for 80 ft by 80 ft
    (24.4 m by 24.4 m) sprinkler spacing,
    or 6.8 sprinklers/acre
2.  Distribution pumping - From Figure 33,
    for total head of 150 ft  (45.7 m)

Recovery of Renovated Water - 50 acres of
underdrains with spacing of 100 ft. Updated
cost from Figure 34

Additional Costs - Includes administrative
and laboratory facilities, monitoring wells,
and service roads and fencing.

1.  Administrative and laboratory facilities
    Updated cost from Figure  39

2.  Monitoring wells - Four wells of 20-ft
    depth.  Updated cost from Figure 40

3.  Service roads and fencing - Updated
    cost from Figure 41

First Subtotal - Total of numbers*

Service and Interest Factor^ - 30 percent
of first subtotal

Second Subtotal - First subtotal plus
service and interest factors

Land - Cost of $l,000/acre ($2,470/ha)
determined from local sources

Total - The total capital cost is
determined to be
$   62,000*
$  201,000



    x 1.09

$  219,000*


$   93,000*



$  58,000*
$   58,000*


$    3,000*


$   58,000*

$1,242,000*


$  372,000*


$1,615,000*


$  175,000*


$1,790.000*
   Number entered on Table 10, page 132.
                              130

-------
Solution (Amortized Capital Cost)

The determination of the amortized capital cost is shown in
the right-hand column of Table 10.  First the nonland sub-
total is amortized by multiplying it by the capital
recovery factor of 0.0944.  The resulting amortized cost of
$152,000 per year is entered in the appropriate space.

A salvage value of zero at the end of the 20-year planning
period is assumed for all components except land.  For land,
the salvage value after 20 years is assumed to be the
present market value of $175,000.  The present worth of the
salvage value at 7 percent interest is $45,000, which is
determined by multiplying the present market value by the
present worth factor of 0.2584.  The difference between the
two values of $130,000 is multiplied by the capital recov-
ery factor 0.0944 to obtain the amortized cost of land of
$12,300 per year.

Solution (Operation and Maintenance Cost)

The determination of annual operation and maintenance costs
is shown on a sample cost caluclation sheet  (Table 11).
The method for determining the costs of each individual
component from cost curves is similar to that used for
total capital costs; consequently, a discussion of that
method for each line item is not  included.  Two items which
are discussed because of their unique nature are cultiva-
tion and harvesting costs, and the benefits from crop sale.

Cultivation and Harvesting - From Table 6,
the estimated labor and materials costs for
alfalfa hay are:

1.  Labor - Total total from labor and harvest
    columns of $89/acre  ($36/ha)               $ 10,700

2.  Materials - The total from the materials
    column less the estimated costs of water
    and fertilizer, or $60/acre  ($24.3/ha)     $   7,200

Benefits - From Table  7,  the estimated nega-
tive materials cost from  the sale of alfalfa
hay, assuming a conservative yield of 5 tons/
acre  (11.2 metric tons/ha) and a  price of
$40/ton  ($44/metric ton),  is $200/acre
 ($494/ha).                                     ($  24,000)
                               131

-------
     Table 10.  EXAMPLE OF COMPLETED  STAGE II
     COST CALCULATION SHEET FOR CAPITAL COSTS
Alternative No. /
Type of system SPRAY IRR.

Cost component
Preapplication treatment
PRELIMINARY TREATMENT
AERATED LAGOON AND CHLORINATION
Transmission
FORCE MAIN
EFFLUENT PUMPING
Storage 35 mil gal.
Field preparation
SITE CLEARING
Average flow / mgd
Analysis date JUL '74

Total cost, Amortized cost,
$ $/yr
63.000
/20rOOO
176 . 000
/33,000
/99. 000
62.000

Distribution
SOL/0 SET SPRAYING (BURIED)
DISTRIBUTION PUMPING
Recovery
UNDERDRAINS
2/9 , 000
93, 000
58. OOO

Additional costs
ADMIN B LAB FACILITIES
MONITORING WELLS
SERVICE ROADS a FENCING
58.000
3. OOO
58. OOO

SUBTOTAL
Service and
interest factor § 30 %
SUBTOTAL
Land § $1.000 /acre
TOTAL
1.242. 000
372, OOO
1.615, OOO I52.5OO
I75,OOO I2.30O
1, 790, OOO 164, BOO

Amortization:
i *    7  %.  n
20
CRF
0.0944 ,   PWF = Q.2584
                          132

-------
     Table 11.   EXAMPLE OF  COMPLETED  STAGE II
              COST  CALCULATION SHEET FOR
            OPERATION AND MAINTENANCE  COSTS
Alternative No.
Average  flow
                                                     mgd
Type of system SPRAY IRR.
Analysis date JUL '74

Annual cost, $/yr

Preapplication treatment
PRELIMINARY TREATMENT
AERATED LAGOON AND CHLORINATION
Transmission
FORCE MAIN
EFFLUENT PUMPING
Storage 35 mil gal.
Distribution
SOLID SET SPRAYING (BURIED)
DISTRIBUTION PUMPING
Recovery
UNDERDRAINS

Additional costs
ADMIN a LAB FACILITIES
MONITORING WELLS
SERVICE ROADS & FENCING
CULTIVATION a HARVESTING

Labor
8 ',600
2,900
800
12.300
8,600
500
10.700
Power Material
1.500
6,OOO 2,000
500
6.5OO 300
60O

6.500 300


/,900
100
1.400
7.200

Total
6.600
16,600
500
1,400
I3,80O
9.700
10.500
600
1.400
17.900
Benefits
  SALE OF CROP
        (24.000)  (24.PC
                     TOTALS  56,200  /9.0OO
                7/./00
                           133

-------
                         APPENDIX A

                 REVENUE-PRODUCING BENEFITS

Revenue-producing benefits should be incorporated into the cost-
effectiveness analysis procedure as negative operation and
maintenance costs.  Possible monetary benefits include (1) sale
of crop grown, (2) sale of renovated water recovered, (3) sale
of surplus effluent to adjacent farmers or industries,
(4) lease of purchased land back to farmers for the purpose
of land application, and (5) lease of purchased lands to
groups or individuals for secondary purposes, such as seasonal
recreation.  Additional benefits may arise in a specific
locality if secondary uses of the water or land are practical.
If recreational or other social or environmental benefits
can be quantified, they should be incorporated into the monetary
portion of the cost-effectiveness analysis.

SALE OF CROP GROWN

Data on cash returns from crops grown using effluents for
irrigation are relatively scarce.  Some information is in-
cluded in Sullivan [50] and Pound and Crites [40]..  Generally,
the return from the sale of crops will offset only a portion of
the total operation and maintenance cost.  The cost of planting,
cultivation, soil amendments (if necessary), and harvesting
should be offset by the crop sale for a well-operated system.
The relative costs and benefits of crop production will depend
on local farming practice, the local economy, and the type
of irrigation system.  Referring back to Table 7, the returns
from the sale of annual crops, especially where two or more
crops can be raised in a year, are generally higher than for
perennials.  On the other hand, operating costs are usually
higher and the needed degree of farming expertise may also
be greater.

For overland flow systems, the economic returns generally
amount to a small fraction of the operating costs [52, 18].

SALE OF RENOVATED WATER RECOVERED

This benefit is most applicable to overland flow and
infiltration-percolation systems.  The return will depend on
the economic value of water in the area and the restrictions,
if any, placed on the use of the water.  This type of benefit
has been incorporated into management plans for Bakersfield,
California, and Phoenix, Arizona.
                             135

-------
SALE OF SURPLUS EFFLUENT

This has been practiced at many existing land application sites
in Texas and California to reduce storage costs, raise revenue,
or, in one case, to satisfy a lawsuit.  In Pomona, California,
effluent is purchased from the Los Angeles County Sanitation
Districts at $7 per acre-foot ($0.006 per cu m)  and sold to
various users at $5 to $22 per acre-foot ($0.004 to 0.018
per cu m) [40].

LEASE OF LAND FOR IRRIGATION.

As an alternative to the conduct of farming operations by
cities or sanitary districts, the land owned by the city or
sanitary district is leased to a local farmer.  Such leases
are prevalent in the western states.  Variations exist on the
length of the lease, the requirements for storing or applying
effluent, and the responsibility for maintenance of distribution
facilities.

LEASE OF LAND FOR RECREATION

This type of benefit has been realized at Woodland, California,
where land that is leased to a farmer for $23 per acre ($57 per
ha) for irrigation in the summer is leased to a duck club for
$6 per acre  ($15 per ha) during the late fall for hunting
privileges [40] .  Other recreational benefits may be feasible
at other locations.
                              136

-------
                          APPENDIX B

                NONREVENUE-PRODUCING BENEFITS

Nonrevenue-producing benefits including social and environmental
benefits must be accounted for descriptively in the cost-
effectiveness analysis to determine their significance and
impact.  Social benefits may include recreational activities,
creation of greenbelts, or preservation of open space.  Environ-
mental factors may include reclamation of sterile soils or
repulsion of saline water intrusion into aquifers by groundwater
recharge.

SOCIAL BENEFITS

Recreational benefits should be included in the descriptive
analysis, especially where parks or golf courses are to be
irrigated.  The creation of greenbelts and the preservation
of open space are planning concepts specifically encouraged
in P.L. 92-500 for wastewater management systems.

Where the social benefits identified can also be quantified,
they should be incorporated into the monetary portion of the
cost-effectiveness analysis.

ENVIRONMENTAL BENEFITS

Claims of environmental benefit for recycling of nutrients
should be scrutinized closely to determine whether nutrients
are being recycled, or whether nutrient problems are only
being transferred from one area to another.  Energy savings
resulting from use of fertilizing agents in effluents in
lieu of commercial fertilizer should be evaluated on the basis
of actual fertilizer value of the effluent and local fertilizing
practice.

Reclamation of sterile or strip-mined soil by applications of
wastewater is an environmental benefit that is difficult to
quantify.  Similarly, groundwater recharge to reduce salinity
intrusion is a qualitative benefit.  The environmental benefits
that can be achieved through a specific wastewater management
alternative should be enumerated and evaluated to determine
their significance.
                               137

-------
                         APPENDIX C

                         REFERENCES
1.    Ackerman, W.C.   Cost of Municipal Sewage Treatment.
     Technical Letter 12, Illinois State Water Survey.
     June 1969.

2.    A Guide to Planning and Designing Effluent Irrigation
     Disposal Systems in Missouri.  University of Missouri
     Extension Division.  March 1973.

3.    Allender, G.C.   The Cost of a Spray Irrigation System
     for the Renovation of Treated Municipal Wastewater.
     Master's Thesis, University Park, The Pennsylvania State
     University.  September 1972.

4.    Bauer,  W.J. and D.E. Matsche.  Large Wastewater Irri-
     gation Systems:  Muskegon County, Michigan and Chicago
     Metropolitan Region.  In:  Recycling Treated Municipal
     Wastewater and Sludge through Forest and Cropland,
     SoppeTjW.E. and L.T. Kardos, (ed.).  University Park,
     The Pennsylvania State University Press.  1973.  pp 345-
     365.

5.    Bouwer, H., R.C. Rice, and E.D. Escarcega.  Renovating
     Secondary Sewage by Ground Water Recharge with Infil-
     tration Basins.  U.S. Water Conservation Laboratory,
     Office of Research and Monitoring.  Project No. 16060
     DRV.  Environmental Protection Agency.  March 1972.

6.    Brown and Caldwell/Dewante and Stowell.  Feasibility
     Study for the Northeast-Central Sewerage Service Area,
     County of Sacramento, California.  November 1972.

7.    Buxton, J.L.  Determination of a Cost for Reclaiming
     Sewage Effluent by Ground Water Recharge in Phoenix,
     Arizona.  Master's Thesis, Arizona State University.
     June 1969.

8.    Campbell, M.D.  and J.H. Lehr.  Water Well Technology.
     McGraw-Hill Book Co. New York.  1973.

9.    Consulting Engineering - A Guide for the Engagement of
     Engineering Services.  ASCE - Manuals and Reports on
     Engineering Practice - No. 45.  New York, ASCE.  1972.
                             139

-------
 10.  Cantrell, R.P.,  et  al.  A Technical  and Economic Feasi-
     bility  Study of  the Use of Municipal  Sewage Effluent
     for  Irrigation.   In:  Proceedings of  the  Symposium on
     Municipal Sewage Effluent for  Irrigation, Wilson, C.W.
     and  F.  E. Beckett (ed.).  Louisiana  Polytechnic Insti-
     tution.  July  30,  1968.  pp  135-157.

 11.  Crites, R.W.   Irrigation with Wastewater  at Bakersfield,
     California.  In:  Wastewater Use in  the Production of
     Food and Fiber--Proceedings.  EPA-660/2-74-041.  June
     1974.

 12.  Crites, R.W.,  C.E. Pound, and R.G. Smith.  Experience
     with Land Treatment of Food Processing Wastewater.
     In:  Proceedings  of the Fifth National Symposium on Food
     Processing Wastes, Monterey, California.  EPA-660/2-
     74-058.   June  1974.

 13.  Cunningham, H.   Environmental Protection  Criteria for
     Disposal of Treated Sewage on Forest  Lands.  Eastern
     Region,  U.S. Forest Service.  Milwaukee, Wisconsin.
     July 1971.

 14.  Davis, W.K.  Land Disposal III:  Land Use Planning.
     Journal  WPCF,  45, No. 7, pp 1485-1488.  1973.


 15.  Drainage of Agricultural Land.  Soil  Conservation
     Service, U.S.  Department of Agriculture.  Water infor-
     mation Center, Inc.  1973.

 16.  Estimating Staffing for Municipal Wastewater Treatment
     Facilities.   Operation and Maintenance Program.  Office
     of Water Program Operations, Environmental Protection
     Agency.   March 1973.

17.  Evaluation of Land Application Systems.   Office of Water
     Program  Operations, Environmental Protection Agency.
     Technical Bulletin, EPA-430/9-75-001.  March 1975.

18.  Gilde, L.C. , et al.  A Spray Irrigation System for
     Treatment of Cannery Wastes.   Journal WPCF, 43, No.  8,
     pp 2011-2025.   1971.

19.  Gray, J.F.   Practical Irrigation with Sewage Effluent.
     In:  Proceedings  of the Symposium on Municipal Sewage
     Effluent for Irrigation,  Wilson,  C.W. and  F.E.  Beckett
     (ed.).   Louisiana Polytechnic Institution.  July  30,
     1968. pp 49-59.
                             140

-------
20.   Green, R.L., G.L.  Page, Jr., and W.M.  Johnson.   Con-
     siderations for Preparation of Operation and Maintenance
     Manuals.   Office of Water Program Operations, Environ-
     mental Protection Agency.

21.   Guidance  for Facilities Planning.  Office of Air and
     Water Programs, Environmental Protection Agency.
     January 1974.

22.   Hill, R.D., T.W. Bendixen, and G.G. Robeck.  Status
     of Land Treatment for Liquid Waste-Functional Design.
     Presented at the Water Pollution Control Federation
     Conference.  Bal Harbour.  October 1964.

23.   Houston,  C.E.   Drainage of Irrigated Land.  California
     Agricultural Extension Service Circular 504.  December
     1967.

24.   Houston,  C.E.  and R.O. Schade.  Irrigation Return-
     Water Systems.   California Agricultural Extension
     Service Circular 542.  November 1966.

25.   Hutchins, W.A.   Water Rights Laws in the Nineteen Western
     States, Volumes I, II, and III.  Miscellaneous Publica-
     tion No.  1206.   U.S. Department of Agriculture.  1971.

26.   Lance, J.C.  Nitrogen Removal by Soil  Mechanisms.
     Journal WPCF,  44, No. 7, pp 1352-1361.  1972.

27.   Land Application of Sewage Effluents and Sludges:
     Selected Abstracts.  Office of Research and Development,
     Environmental  Protection Agency.  EPA 660/2-74-042. June
     1974.

28.   McGauhey, P.H.  and R.B. Krone.  Soil Mantle as a
     Wastewater Treatment System.  SERL Report No. 67-11.
     Berkeley, University of California.  December 1967.

29.   Merz, R.C.  Continued Study of Waste Water Reclamation
     and Utilization.  California State Water Pollution
     Control Board,  Sacramento, California.  Publication
     No. 15.  1956.

30.   Merz, R.C.  Third Report on the Study of Waste Water
     Reclamation and Utilization.  California State Water
     Pollution Control Board, Sacramento, California.
     Publication No. 18.  1957.
                              141

-------
31.  National Canners Association.  Liquid Wastes from
     Canning and Freezing Fruits and Vegetables.  Office of
     Research and Monitoring, Environmental Protection Agency.
     Program No. 12060 EDK.  August 1971.

32.  Nesbitt, J.B.  Cost of Spray Irrigation for Waste-
     water Renovation.  In:  Recycling Treated Municipal
     Wastewater and Sludge through Forest and Cropland,
     Sopper, W.E. and L.T. Kardos, (ed.).  University Park,
     The Pennsylvania State University Press.  1973.
     pp 334-338.

33.  Pair, C.H., (ed.).  Sprinkler Irrigation.  Supplement
     to the 3rd edition.  Silver Spring, Sprinkler
     Irrigation Association.  1973.

34.  Pair, C.H., (ed.).  Sprinkler Irrigation, 3rd edition.
     Washington, B.C., Sprinkler Irrigation Association.  1969

35.  Parker, R.P.  Disposal of Tannery Wastes.  Proceedings
     of the 22nd Industrial Waste Conference, Part I.
     Lafayette, Purdue University.  1967.  pp 36-43.

36.  Parson, W.C.  Spray Irrigation of Wastes from the
     Manufacture of Hardboard.  Proceedings of the 22nd
     Industrial Waste Conference.  Lafayette, Purdue
     University.  1967.  pp 602-607.

37.  Patterson, W.L. and R.F. Banker.  Estimating Costs
     and Manpower Requirements for Conventional Wastewater
     Treatment Facilities. Office of Research and Monitoring,
     Environmental Protection Agency.  October 1971.

38.  Philipp, A.H.  Disposal of Insulation Board Mill
     Effluent by Land Irrigation.  Journal WPCF, 43, No. 8,
     pp 1749-1754.  1971.

39.  Postlewait, J.C. and H. J. Knudsen.  Some Experiences in
     Land Acquisition for a Land Disposal System for Sewage
     Effluent.  Proceedings of the Joint Conference of Recycl-
     ing Municipal Sludges and Effluents on Land, Champaign,
     University of Illinois.  July 1973.  pp 25-38.

40.  Pound, C.E. and R.W.  Crites.  Wastewater Treatment and
     Reuse by Land Application, Volumes I and II.  Office
     of Research and Development, Environmental Protection
     Agency.  EPA-660/2-73-006a,b.  August 1873.

41.  Powell, G.M. and G.L. Culp.  AWT vs. Land Treatment:
     Montgomery County, Maryland.  Water § Sewage Works, 120,
     No. 4, pp 58-67.  1973.


                             142

-------
42.   Reed, A.D.   Sample Costs to Produce Crops.   University
     of California Cooperative Extension Circular MA-4.
     July 1974.

43.   Reed, S.C.  and T.D. Buzzell. Land Treatment of Waste-
     waters for Rural Communities.  In:  Water Pollution
     Control in Low Density Areas, Jewell, W.J.  and R.  Swan,
     (ed.).  University Press of New England, Hanover,  New
     Hampshire.  1975.  pp 23-40.

44.   Rowan, P.P., K.L. Jenkins, and D.W. Butler.  Sewage
     Treatment Construction Costs.  Journal WPCF, 32, No.  6,
     pp 594-604.  1960.

45.   Rowan, P.P., K.L. Jenkins, and D.H. Howells.  Estimating
     Sewage Treatment Plant Operations and Maintenance
     Costs.  Journal WPCF, 33, No. 2, pp 111-121.  1961.

46.   Schraufnagel, F.H.  Ridge-and-Furrow Irrigation for
     Industrial Wastes Disposal.  Journal WPCF, 34, No. 11,
     pp 1117-1132.  1962.

47.   SCS Engineers. Demonstrated Technology and Research
     Needs for Reuse of Municipal Wastewater.  Environmental
     Protection Agency.  EPA-670/2-75-038.  1975.

48.   Smith, R.  Cost of Conventional and Advanced Treatment
     of Wastewater.  Journal WPCF, 40, No. 9, pp 1546-
     1574.  1968.

49.   Stevens, R.M.  Green Land-Clean Streams:  The Beneficial
     Use  of Waste Water through  Land Treatment.  Center for
     the  Study of Federalism.   Philadelphia,  Temple University,
     1972.

50.  Sullivan, R.H., et al.   Survey of  Facilities using Land
     Application  of Wastewater.   Office of Water Program
     Operations.  Environmental  Protection Agency.  EPA-
     430/9-73-006.  July  1973.

51.  Tchobanoglous, G.  Wastewater Treatment  for Small Com-
     munities.   In:  Water Pollution Control  in Los Density
     Areas, Jewell, W.J.  and R.  Swan,  (ed.).  University
     Press of New Englend, Hanover, New Hampshire. 197b.
     pp  389-428.

     C   W Thornthwaite Associates.  An Evaluation of Cannery
     Waste Disposal  by Overland Flow  Spray  Irrigation.
     Publications in  Climatology,  22,  No.  2.  September 1969.
                              143

-------
53.  Tihansky, D.P.  Cost Analysis of Water Pollution Con-
     trol:  An Annotated Bibliography.  Office of Research
     and Monitoring.  Environmental Protection Agency.
     Washington, B.C.  April 1973.

54.  Van Note, R.H., P.V. Hebert, and R.M. Patel.  A Guide
     to the Selection of Cost-Effective Wastewater Treatment
     Systems.  Municipal Wastewater Systems Division,
     Engineering and Design Branch.  Environmental Pro-
     tection Agency.  EPA-430/9-75-002.  1975.

55.  Waste into Wealth.  Melbourne and Metropolitan Board
     of Works.  Melbourne, Australia.  1971.

56.  Waste Water Reclamation.  California State Department
     of Public Health, Bureau of Sanitary Engineering.
     California State Water Quality Control Board.  November
     1967.

57.  Williams, T.C.  Utilization of Spray Irrigation for
     Wastewater Disposal in Small Residential Developments.
     In:  Recycling Treated Municipal Wastewater and Sludge
     through Forest and Cropland, Sopper, W.E. and L.T.
     Kardos, (ed.).  University Park, The Pennsylvania
     State University Press.  1973.  pp 385-395.

58.  Wilson, C.W.  The Feasibility of Irrigating Softwood
     and Hardwood for Disposal of Papermill Effluent.
     Paper No.  71-245, Annual Meeting, American Society of
     Agricultural Engineers, Pullman, Washington.  June 1971.

59.  Woodley, R.A.   Spray Irrigation of Fermentation Wastes.
     Water and Wastes Engineering, 6, B14-B18.  March 1969.

60.  Woodley, R.A.   Spray Irrigation of Organic Chemical
     Wastes.   Proceedings of the 23rd Industrial Waste
     Conference.   Lafayette, Purdue University.  1968.
     pp 251-261.

61.  Zimmerman, J.P.  Irrigation.  New York, John Wiley
     § Sons,  Inc.  1966.
                             144

-------
                                      APPENDIX D
           EPA SEWAGE TREATMENT PLANT AND SEWER  CONSTRUCTION COST  INDEXES
                                   (1957-1959=100)

             Table D-l.   SEWAGE TREATMENT PLANT  CONSTRUCTION COST  INDEX
Years
1957
195S
1959
1960
1961
1962
1963
1964
1965
1966
1967
1968
1969
1970
1971
1972
1973
1974
Jan


106
109
110
114
117
121
128
137
150
167
176
188


.80
.64
.82
.05
.76
.10
.68
.63
.60
.73
.14
.13
Feb


107
109
111
114
118
121
129
137
150
168
177
190


.05
.45
.04.
.60
.08
.20
.50
.87
.89
.66
.49
.21
Mar


107
109
111
114
118
121
129
138
153
169
180
190


.08
.53
.07
.77
.11
.21
.84
.15
.34
.16
.38
.97
Apr


107.11
109.57
111.12
115.08
118.22
121.55
130.03
138.49
155.41
169.88
181.62
196.10
May


107
109
111
115
118
121
130
141
157
171
182
197


.22
.70
.15
.34
.34
.71
.03
.18
.29
.41
.56
.76
Jun


107
109
111
116
119
122
131
143
158
172
182
202


.78
.99
.83
.05
.11
.49
.11
.03
.62
.18
.86
.53
Jul


108
110
112
116
119
123
132
146
160
172
183
212


.07
.24
.31
.82
.63
.39
.44
.25
.58
.31
.68
.15
Aug


108.
110.
112.
116.
120.
123.
135.
146.
165.
173.
183.

Sep


52
54
57
92
28
69
34
70
07
11
87


107
108
110
112
117
120
124
135
147
166
173
184


.19
.58
.63
.70
.11
.59
.53
.46
.45
.30
.78
.51

Oct

107
109
110
112
117
120
126
135
148
166
174
184


.20
.54
.69
.82
.51
.89
.80
.85
.07
.25
.45
.97

Nov

107
109
110
112
117
120
127
136
149
166
175
185


.03
.51
.73
.87
.46
.91
.24
.61
.28
.44
.47
.79

Dec

106
109
110
113
117
121
127
136
149
167
175
187


.84
.60
.68
.09
.48
.01
.71
.86
.63
.19
.68
.51

Annual
index
98.04
101.50
103.65
104.96
105.85
106.99
108.52
110.11
111.95
116.10
119.41
123.55
132.65
143.64
159.83
171.98
182.62

a. Source:  EPA, Office of Water Program Operations

-------
                       Table D-2.   SEWER  CONSTRUCTION COST  INDEX
Years
1957
1958
1959
1960
1961
1962
1963
1964
1965
1966
1967
1968
1969
1970
1971
1972
1973
1974
Jan








115.32
118.19
122.72
126.31
135.01
143.29
157.39
179.56
192.83
206.68
Feb








115.60
118.68
122.98
126.94
135.73
144.00
157.78
180.42
194.22
208.40
Mar








115.
119.
122.
127.
136.
144.
159.
181.
195.
210.









65
02
83
04
10
60
17
50
78
49
Apr







114.50
115.72
119.68
123.01
127.40
136.57
145.74
161.01
181.99
196.54
214.20
May







114.42
115.72
119.97
123.36
127.90
136.36
146.81
164.25
184.79
198.93
217.48
Jun







114.69
116.50
120.40
124.23
128.80
137.00
149.15
166.76
185.67
199.63
224.62
Jul







115.19
117.03
121.39
124.74
129.90
139.32
152.57
168.38
186.23
200.97
229.68
Aug







115.10
117.31
121.18
125.36
130.31
141.48
152.62
169.89
187.53
201.34

Sep







115.26
117.32
121.44
125.71
131.12
141.24
153.48
172.00
188.73
202.02

Oct







115.20
117.57
121.93
126.00
132.39
141.49
154.38
173.25
189.27
202.83

Nov







115.03
117.61
122.20
126.17
133.33
141.98
154.82
177.29
190.44
203.69

Dec







115.01
117.93
122.16
126.24
133.44
142.61
155.94
178.99
191.06
206.01

Annual
index
96.80
100.42
104.78
106.22
108.19
109.72
113.07
114.72
116.61
120.52
124.45
129.57
138.74
149.78
167.18
185.60
199.57

a.  Source:  EPA, Office of Water Program Operation.

-------
                   Appendix E

               PRESENT WORTH AND
            CAPITAL RECOVERY FACTORS
Table E-l.  PRESENT WORTH FACTOR, PWF =
                                        (1
i = interest
rate, 1
5.000
5.125
5.250
5.375
5.500
5.625
5.750
5.875
6.000
6.125
6.250
6.375
6.500
6.625
6.750
6.875
7.000
7.125
7.250
7.375
7.500
7.625
7.750
7.875
8.000

10
0.6139
0.6067
0.5995
0.5924
0.5854
0.5785
0.5717
0.5650
0.5584
0.5519
0.5454
0.5390
0.5327
0.5265
0.5204
0.5143
0.5083
0.5024
0.4966
0.4909
0.4852
0.4796
0.4741
0.4686
0.4632
N
15
0.4810
0.4725
0.4642
0.4560
0.4479
0.4400
0.4323
0.4247
0.4172
0.4100
0.4028
0.3957
0.3888
0.3280
0.3754
0.3689
0.3624
0.3562
0.3500
0.3439
0.3380
0.3321
0.3264
0.3208
0.3152
= period,
20
0.3769
0.3680
0.3594
0.3510
0.3427
0.3347
0.3269
0.3193
0.3118
0.3045
0.2975
0.2905
0.2838
0.2772
0.2708
0.2645
0.2584
0.2525
0.2466
0.2410
0.2354
0.2300
0.2247
0.2196
0.2145
yr
25
0.2953
0.2866
0.2783
0.2701
0.2622
0.2546
0.2477
0.2400
0.2330
0.2262
0.2197
0.2153
0.2071
0.2012
0.1953
0.1897
0.1842
0.1789
0.1738
0.1688
0.1640
0.1593
0.1547
0.1503
0.1460

30
0.2313
0.2233
0.2154
0.2079
0.2006
0.1936
0.1869
0.1804
0.1741
0.1681
0.1622
0.1566
0.1512
0.1460
0.1409
0.1361
0.1314
0.1268
0.1225
0.1183
0.1142
0.1103
0.1065
0.1029
0.0994
                       147

-------
ble E 2 CAPITAL RFCOVFRY
i/ -i- t* Xi< £* • \_jjA X j. j. ,/A. xj ivXwO vy v J_iix x
i = interest
rate, 1
5.000
5.125
5.250
5.375
5.500
5.625
5.750
5.875
6.000
6.125
6.250
6.375
6.500
6.625
6.750
6.875
7.000
7.125
7.250
7.375
7.500
7.625
7.750
7.875
8.000

10
0.1295
0.1303
0.1310
0.1319
0.1326
0.1335
0.1343
0.1351
0.1359
0.1367
0.1375
0.1383
0.1391
0.1399
0.1407
0.1416
0.1424
0.1432
0.1440
0.1449
0.1457
0.1465
0.1474
0.1482
0.1490
N
15
0.0963
0.0972
0.0980
0.0988
0.0996
0.1005
0.1013
0.1021
0.1030
0.1038
0.1047
0.1055
0.1064
0.1072
0.1081
0.1089
0.1098
0.1107
0.1115
0.1124
0.1133
0.1142
0.1151
0.1159
O.)168
FACTOR
-TJA.W A Wl\ f
= period,
20
0.0802
0.0811
0.0820
0.0828
0.0837
0.0845
0.0854
0.0863
0.0872
0.0881
0.0890
0.0899
0.0908
0.0917
0.0926
0.0935
0.0944
0.0953
0.0962
0.0972
0.0981
0.0990
0.1000
0.1009
0.1019
TRF =
l_il\..T —
years
25
0.0709
0.0718
0.0727
0.0736
0.0745
0.0755
0.0764
0.0773
0.0782
0.0792
0.0801
0.0810
0.0820
0.0829
0.0839
0.0848
0.0858
0.0868
0.0878
.0.0887
0.0897
0.0907
0.0917
1.0927
0.0937
1(1 + i)n
(1 + i)n - i

30
0.0650
0.0660
0.0670
0.0679
0.0688
0.0698
0.0707
0.0717
0.0726
0.0736
0.0746
0.0756
0.0766
0.0776
0.0786
0.0796
0.0806
0.0816
0.0826
0.0836
0.0847
0.0857
0.0867
0.0878
0.0888
148

-------
                                     APPENDIX  F

             COST-EFFECTIVENESS  ANALYSIS  GUIDELINES
               APPENDIX A

  COST EFFECTIVENESS ANALYSIS GUIDELINES

  a.  Purpose.—These  guidelines provide  a
basic methodology for  determining the most
cost-effective waste  treatment management
system or the most cost-effective component
part of any waste  treatment management
system.
  b.  Authority.—The  guidelines contained
herein are provided  pursuant to section 212
(2) (C) of the Federal  Water Pollution Con-
trol Act Amendments of 1972  (the Act).
  c.  Applicability.—These guidelines  apply
to the development of plans for  and the
selection of component  parts  of  a  waste
treatment management system  for which a
Federal grant is awarded  under  40 CFR,
Part 35.
  d.  Definitions.—Definitions  of terms used
In these guidelines  are as follows:
  (1)  Waste treatment  management  sys-
tem.—A system used to restore the integrity
of the Nation's waters. Waste treatment
management system Is used synonymously
with  "treatment works" as  defined  in 40
CFR, Part 35.905-15.
  (2) Cost-effectiveness analysis.—An analy-
sis  performed  to  determine  which  waste
treatment management  system  or compo-
nent part thereof will result In the minimum
total resources costs over time  to meet the
Federal,  State or local requirements.
  (3)  Planning period.—The  period  over
which  a waste treatment management sys-
tem Is evaluated for cost-effectiveness. The
planning period commences with the initial
operation of the system.
  (4) Service li/e.—The period of time dur-
ing which a component of a waste  treat-
ment management system will be capable of
performing  a function.
  (5) Useful li/e.—The period of time dur-
ing which a component of a waste  treat-
ment management system will be required to
perform  a function which Is necessary to
the system's operation.
                           Title 4O—Protection of the Environment
                                CHAPTER I—ENVIRONMENTAL
                                    PROTECTION AGENCY
                                    SUBCHAPTER D—GRANTS
                                PART 35—STATE AND LOCAL
                                         ASSISTANCE
                            Appendix A—Cost-Effectiveness Analysis
                             On July  3,  1973, notice was published
                           in the FEDERAL REGISTER  that the En-
                           vironmental Protection Agency was pro-
                           posing  guidelines  on cost-effectiveness
                           analysis pursuant to section 212(2) (c) of
                           the Federal Water Pollution Act Amend-
                           ments of 1972 (the  Act)  to be published
                           as' appendix A to 40 CFR part 35.
                             Written  comments  on  the proposed
                           rulemaking were invited  and received
                           from  interested  parties.  The Environ-
                           mental Protection Agency has carefully
                           considered  all comments  received.  No
                           changes were  made in the guidelines as'
                           earlier proposed. All  written comments
                           are on file with the agency.
                             Effective date.—These regulations shall
                           become  effective October 10, 1973.
                             Dated September 4, 1973.

                                                JOHN QUARJ.ES,
                                           Acting Administrator.
  e.  Identification, selection and  screening
of alternatives—(1) Identification of alter-
natives.—All feasible alternative waste man-
agement systems shall be initially identified.
These  alternatives should Include systems
discharging  to receiving  waters,  systems
using land or subsurface disposal techniques,
and  systems employing the reuse  of waste-
water.  In identifying  alternatives, the possi-
bility of  staged development of the system
shall be  considered.
  (2) Screening of alternatives.—The iden-
tified  alternatives shall be systematically
screened  to define those capable of meeting
the  applicable Federal, State,  and  local
criteria.
  (3)   Selection   of   alternatives.—The
screened  alternatives shall be initially ana-
lyzed to determine which systems have cost-
effective potential and which should be fully
evaluated according to the cost-effectiveness
analysis  procedures  established  in  these
guidelines.
  (4) Extent of effort.—The extent of effort
and  the level of sophistication used In the
cost-effectiveness  analysis should reflect the
size  and Importance of the project.
  f.  Cost-Effective, analysis  procedures—(1)
Method of  Analysis.—The  resources costs
shall be evaluated through the use of oppor-
tunity costs. For those resources that can be
expressed  in  monetary  terms,  the interest
(discount) rate established in section (f) (5)
will  be used. Monetary costs shall be calcu-
lated in  terms of present worth  values or
equivalent annual values over the planning
period  as defined in  section (f)(2). Non-
monetary factors  (e.g., social and environ-
mental) "shall be accounted for descriptively
In the analysis in order to determine their
significance  and  Impact.
                                            149

-------
   The most cost-effective alternative shall be
 the  waste treatment management  system
 determined  from  the analysis  to  have the
 lowest present worth and/or equivalent an-
 nual value v/ithout overriding adverse non-
 monetary -costs and to realize at least Identi-
 cal minimum benefits In terms of applicable
 Federal,  State, and local standards  for ef-
 fluent  quality, water quality,  water reuse
 and/or land and subsurface disposal.
   (2) Planning period.—The planning period
 Tor the cost-effectiveness analysis shall be 20
 years.
   (0) Elements  of cost.—The  costs to  be
 considered shall include the total  values of
 the resources attributable to the waste treat-
 raent management system or to one of Its
 component parts. To determine these values,
 nil monies necessary for capital construction
 costs and operation and maintenance costs
 shall be Identified.
   Capital construction costs used In  a cost-
 effectiveness analysis shall Include all con-
 tractors' costs ol construction Including over-
 head and profit; costs of land, relocation, and
 right-of-way   and  casement   acquisition;
 design engineering, field exploration, and en-
 gineering  services during construction;  ad-
 ministrative  and legal  services  Including
 costs of bond sales; startup costs such as op-
 erator training;  and  interest  during  con-
 struction. Contingency allowances consistent
 with the level of complexity and detail of the
 cost estimates shall be Included.
   Annual  costs for operation and mainte-
 nance  (Including routine  replacement  of
 equipment and equipment parts)  shall be
 Included  in the  cost-effectiveness analysis.
 These costs shall  be adequate to ensure ef-
 fective and dependable operation during the
 planning period for the system. Annual costs
 shall be divided between fixed annual costs
 and costs which would be dependent on the
 annual quantity of wastewater collected and
 treated.
   (4)  Prices.—The various components of
 cost shall be calculated on the basis of mar-
 ket prices prevailing at the time  of  the cost-
 effectiveness analysis.  Inflation of wages and
 prices shall not be considered in the analysis.
 The Implied  assumption is that  all prices
 Involved will  tend to  change over time by
 approximately the same percentage. Thus,
 the results of the cost effectiveness analysis
 will not  be affected by changes  in  the gen-
 eral level of prices.
   Exceptions to the foregoing can  be made
 If their Is Justification for expecting signifi-
 cant changes In the relative prices of certain
 Items during  the  planning  period. If such
 cases are Identified, the expected change in
 these prices should be made to reflect their
 future relative deviation from the general
 price level.
   (5) Interest (discount) rate.—A rate of 7
 percent per year  will  be used for the cost-
 effectiveness analysis until the promulgation
 of the Water  Resources Council's "Proposed
 Principles and Standards for Planning Water
 and Related Land  Resources." After promul-
 gation of the  above  regulation, the rate
established for water resource projects shall
 toe used for the cost-effectiveness analysis.
   (6) Interest during construction.—In cases
•where capital expenditures can be  expected
to be fairly uniform during the construction
period. Interest during construction may be
 calculated as IX V4 PXC where:
 I=the  Interest  (discount)  rate  in  Section
   f(5).
 P=the construction period In years.
 C—the total capital expenditures.

   In cases  when expenditures will not  be
 uniform, or when the construction period
 will be greater than three years. Interest dur-
 ing construction shall  be calculated  on  a
 year-by-year basis.

   (7) Service life.—The service life of treat-
 ment works for  a cost-effectiveness  analysis
 shall be as follows:

 Land 	Permanent
 Structures	30-60  years
     (Includes  plant  buildings,
     concrete  process  tankage,
     basins,  etc.; sewage collec-
     tion  and conveyance pipe-
     lines;  lift   station  struc-
     tures; tunnels; outfalls)
 Process equipment	15-30  years
     (Includes   major  process
     equipment such as clartner
     mechanism,  vacuum filters,
     etc.;  steel process  tankage
     and chemical storage facili-
     ties;  electrical  generating
     facilities on  standby service
     only).
 Auxiliary equipment	10-15  years
     (Includes instruments and
     control  facilities;  sewage
     pumps  and electric motors;
     mechanical equipment sucb
     as compressors, aeration sys-
     tems,  centrifuges, chlori-
     nators,  etc.;  electrical gen-
     erating facilities on regular
     service).
   Other service life periods will be acceptable
 when sufficient Justification can be provided.
   Where  a  system  or a  component is for
 Interim  service  and  the anticipated useful
 life is less  than  the service life,  the useful
 life shall  be substituted for the service life of
 the facility in the analysis.
   (8)  Salvage value.—Land for  treatment
 Works, including land used as part of the
 treatment process or for ultimate disposal of
 residues, shall be assumed to have a salvage
 value at the end of the planning period equal
 to its prevailing  market value  at the time of
 the analysis. Right-of-way easements  shall
 be considered to have  a  salvage value not
 greater  than the prevailing market value at
 the time of the analysis.
  Structures  will  be   assumed  to  have  a
salvage value If there Is a use for such struc-
tures at the end of the planning period.  In
 this case, salvage value shall be estimated
using straightline depreciation during the
 service life of the treatment works.
  For phased additions of process  equipment
and auxiliary equipment, salvage value at the
end of the planning period may be estimated
under the same conditions and on the same
basis as  described above for structures.
  When the anticipated useful life of a facil-
ity is less than 20 years (for analysis of in-
terim facilities). salvage value can be  claimed
 for equipment where it can  be clearly  dem-
 onstrated that  a specific market or  reuse
 opportunity will exist.

   [FR Doc.73-19104 Piled 9-7-73;8:45 am]
                                              150

-------
                         Appendix G

             GLOSSARY OF TERMS, ABBREVIATIONS,
                   AND CONVERSION FACTORS
TERMS
Aerosol - A suspension of fine solid or liquid particles in
air or gas.

Application rate - The rate at which a liquid is dosed to the
land (in./hr, ft/yr, etc.).

Aquifer - A geologic formation or stratum that contains
water and transmits it from one point to another in quan-
tities sufficient to permit economic development.

Border strip method - Application of water over the surface
of the soil.Water is applied at the upper end of the long,
relatively narrow strip.

Contour check method - Surface application by flooding.
Dikes constructed at contour intervals to hold the water.

Cost-effectiveness analysis - The procedure for economic
evaluation of wastewater treatment alternatives given in the
guidelines as 40 CFR 35-Appendix A.

Conventional wastewater treatment - Reduction of pollutant
concentrations in wastewater by physical, chemical, or
biological means.

Drainability - Ability of the soil system to accept and
transmit water by infiltration and percolation.

Evapotranspiration - The unit amount of water used on a
given area in transpiration, building of plant tissue, and
evaporation from adjacent soil, snow, or intercepted
precipitation in any specified time.

Field area - Total area of treatment for a land-application
system including the wetted area.

Flooding - A method of surface application of water which
includes border strip, contour check, and spreading methods.
                             151

-------
Grass filtration - See overland flow.

Groundwater - The body of water that is retained in the satu-
rated zone which tends to move by hydraulic gradient to lower
levels.

Groundwater table - The free surface elevation of the
groundwater; this level will rise and fall with additions
or withdrawals.

Infiltration - The entrance of applied water into the soil
through the soil-water interface.

Infiltration-percolation - An approach to land application
in which large volumes of wastewater are applied to the
land, infiltrate the surface, and percolate through the soil
pores.

Irrigation  - Application of water to the land to meet the
growth needs of plants.

Land  application - The discharge of wastewater onto the soil
for treatment or reuse.

Loading rate - The average amount of liquid or solids applied
to the land over a fixed time period, taking into account
periodic resting.

Overland flow - Wastewater treatment by spray-runoff (also
known as "grass filtration" and "spray runoff") in which
wastewater  is sprayed  onto gently sloping, relatively imper-
meable soil that has been planted to vegetation.  Biological
oxidation occurs as the wastewater flows over the ground
and contacts the biota in the vegetative litter.

Pathogenic  organisms - Microorganisms that can transmit
diseases.

Percolation - The movement of water beneath the ground
surface both vertically and horizontally, but above the
groundwater table.

Permeability - The ability of a substance  (soil) to allow
appreciable movement of water through it when saturated
and actuated by a hydrostatic pressure.

Primary effluent  - Wastewater that has been treated by
screening and sedimentation.
                              152

-------
Ridge and furrow method - The surface application of water
to thelandthrough formed furrows;  wastewater flows down
the furrows and plants may be grown on the ridges.

Secondary treatment - Treatment of wastewater which meets the
standards set forth in 40 CFR 133.

Sewage farming - Originally involved the transporting of
sewage to rural areas for land disposal.  Later practice
included reusing the water for irrigation and fertilization
of crops.

Soil texture - The relative proportions of the various soil
separates--sand, silt, and clay.

Soil water - That water present in the soil pores in an
unsaturated zone above the groundwater table.

Spraying - Application of water to the land by means of
stationary or moving sprinklers.

Spray-runoff - See overland flow.

Transpiration - The net quantity  of water absorbed through
plant roots that is used directly in building plant tissue,
or given off to the atmosphere.

Viruses  - Submicroscopic biological structures containing
all  the  information necessary for their own reproduction.

Wetted area - Area within the spray diameter  of  the
sprinklers.
                              153

-------
ABBREVIATIONS
acre-ft   -  acre-foot
ASCE      -  American Society of Civil Engineers

BPT       -  best practicable treatment technology

erf       -  capital recovery factor
cm        -  centimeter
cu m      -  cubic meter
cy        -  cubic yard

diam      -  diameter

EPA       -  Environmental Protection Agency
ENRCC     -  Engineering News-Record construction cost (index)

fps       -  feet per second
ft        -  foot

gal.      -  gallon
gpm       -  gallons per minute

ha        -  hectare
hr        -  hour

in.       -  inch

kg        -  kilogram
kg/sq cm  -  kilograms per square centimeter
km        -  kilometer
kwh       -  kilowatt-hour

1         -  liter
Ib        -  pound
If        -  linear feet
m
mil gal
mgd
mg/1
ml
mm
meter
million gallons
million gallons per day
milligrams per liter
milliliter
millimeter

operations and maintenance
                               154

-------
ppm       -  parts per million
perim     -  perimeter
psi       -  pounds per square inch
PVC       -  polyvinylchloride
pwf       -  present worth factor

Q         -  flow
Qe        -  effective flow

SCS       -  Soil Conservation Service
sec       -  second
sff       -  sinking fund factor
sq cm     -  square centimeter
sq ft     -  square foot
STPCC     -  sewage treatment plant construction cost (index)

wk        -  week

yr        -  year
CONVERSION FACTORS

million gallons x 3.06 = acre-feet
acre-inch x 27,154 = gallons
mg/1 x ft/yr x 2.7 = Ib/acre/yr
                               155

-------
                            CONVERSION FACTORS
                            English to Metric
English unit
•ere
•c re-foot
cents per thousand gallons
cubic foot
cubic feet per second
cubic inch
cubic yard
cubic yards per acre
degree Fahrenheit
feet per second
feet per year
foot (feet)
gallon(s)
gallons per acre per day
gallons per capita per day
gallons per day
gallons per day per
square foot
(•lions per Minute
gallons per Minute per
square foot
horsepower
inch(es)
inches per day
inches per hour
inches per week
•ill ion gallons
million gallons per
acre per day
million gallons per day
mile
parts per million
pound (s)
pounds per acre
pounds per day per acre
pounds per million gallons
pounds per square inch
square foot
square inch
square mile
square yard
torn (short)
ton* per acre
yard
Abbreviation
acre
acre-ft
4/1,000 gal.
cf
cfs
cu in.
ey
cy/acre
deg F
fps
ft/yr
ft
gal.
gad
gcd
gpd
gpd/sq ft
gpm
gpm/sq ft
hp
in.
in./day
in./hr
in./wk
mil gal.
mgad
mgd
mi
PP«
Ib
Ib/acre
Ib/day/acre
lb/mil gal.
psi
sq ft
sq in.
iq mi
sq yd
ton
tons/acre
ya
Multiplier
0.40S
1,233.5
0.264
28.32
28.32
16.19
0.0164
0.76S
764.6
1.89
0.555 (*F-32)
O.JOS
0.305
0.305
3.785
9.353
3.785
4.381 x 10"S
1.698 X 10"5
0.283
0.0631
2.445
0.679
0.746
2.54
2.54
2.54
2.54
S.785
3,785.0
0.039
43.108
0.0438
1.609
1.609
1.0
0.454
453.6
1.121
1.121
0.120
0.0703
0.0929
6.452
2.590
0.836
907.2
0.907
0.3674
0.914
Abhrcviut ion
ha
cu m
«/l,000 1
1
I/sec
cu ca
1
cu m
1
cu m/ha
deg C
m/sec
m/yr
m
1
1/day/ha
1/ctpita/day
I/sec
cu B/hr/sq m
cu B/min/ha
I/sec
cu m/hr/sq m
1/sec/sq •
kw
cm
cm/day
cm/hr
ca/vk
Ml
cu m
cu B/hr/sq B
I/sec
cu B/sec
km
B
mg/1
kg
(
kg/ha
kg/day/ha
mg/1
kg/sq cm
sq m
sq CB
sq km
sq m
kS
metric ton
metric tons/ha
B
Metric unit
hectare
cubic Bctcr
cents per thousand liters
liter
liters per second
cubic centimeter
liter
cubic meter
liter
cubic meters per hectare
degree Celsius
Beters per second
Beters per year
meter(s)
liter(s)
liters per day per hectare
liters per second
cubic meters per hour
cubic Beters per ninute
per hectare
liters per second
cubic Beters per hour
per square Beter
square meter
kilowatts
centimeter
centimeters per day
centimeters per hour
megaliters (liters x 105)
cubic meters
cubic meters per hour per
square Beter
liters per second
cubic aeters per second
kilometer
Beter
milligrams per liter
kilogram
grams
kilograms per hectare
kilograms per day per
hectare
milligrams per liter
kilograms per square
square Beter
square centimeter
square kilometer
square meter
kilogram
metric ton
Bctric tons per hectare
meter
                                     156
•ft U. S. GOVERNMENT PRINTING OFFICE 197S • «8Oft43/237 R*>g. 8

-------