CONTRACT NO. 68-01-5034, AMENDMENT #4
 A HANDBOOK FOR STATES  ON THE USE OF
 COMPENSATION AND  INCENTIVES IN  THE
 SITING OF HAZARDOUS WASTE  MANAGEMENT
 FACILITIES
 September  30,  1980
  prepared for:

  U.  S.  Environmental Protection Agency
  401 M. Street,  S.W.
  Washington,  D.C.  20460
  prepared by:

  Urban Systems Research a Engineering,
  36 Boylston Street
  Cambridge, Massachusetts  02138

-------
                               TABLE OF CONTENTS

                                                                          Page

SECTION 1:  INTRODUCTION  .................... .....    1

        1.1 PURPOSE OF THIS HANDBOOK ..................    1

        1.2 HAZARDOUS WASTE FACILITY IMPACT ISSUES AND
            PUBLIC OPPOSITION  .....................    2

        1.3 RESPONSES TO HWMF IMPACT ISSUES:  DEFINITIONS
            AND EXAMPLES  ........................    4

        1.4 RATIONALE FOR THESE RESPONSES  ...... .........    5

        1.5 EXAMPLES FROM OTHER FACILITIY SITING EXPERIENCE  ......    8

        1.6 SCOPE OF THIS HANDBOOK ...................   12

SECTION 2:  INITIAL CONSIDERATIONS ...................   13

        2.1 STATE VERSUS PRIVATE SECTOR PROVISION  ...........   13

        2.2 GENERAL IMPLEMENTATION ISSUES IN PROVIDING MITIGATION,
            COMPENSATION AND INCENTIVES  ................   2i
SECTION 3:  MITIGATION TECHNIQUES  ...................   35

        3.1 INTRODUCTION ........................   35

        3.2 FACILITY DESIGN CHANGES  ..................   36

        3.3 FACILITY OPERATION CHANGES .................   39

        3.4 FACILITY LOCATION CHANGES  .................   44

SECTION 4:  COMPENSATION TECHNIQUES  ..................   47

        4.1 INTRODUCTION ........................   47

        4.2 MONETARY PAYMENTS  .....................   48

        4.3 IN-KIND REPLACEMENT/RESTORATION ACTIONS  ..........   59

        4.4 CONTINGENCY FUNDS:  UNEXPECTED EVENTS  ...........   63

        4.5 CONTINGENCY FUNDS:  PROPERTY VALUE IMPACTS .........   66

-------
                           TABLE OP CONTENTS (Cont'd)

                                                                          Page

   TION 5:   INCENTIVE TECHNIQUES	   72

        5.1 INTRODUCTION	   72

        5.2 SUITABILITY	   76

        5.3 STATE PROVISION VERSUS PRIVATE SECTOR REQUIREMENTS .....   77


APPENDIX A:  POWER TO IMPOSE IMPACT RESPONSE REQUIREMENTS ON
             A HWMF DEVELOPER	   79

APPENDIX B:  INTERSTATE ISSUES AND AGREEMENTS	   82

APPENDIX C:  POWER OP A STATE TO PROVIDE IMPACT RESPONSES	   84

APPENDIX D:  ALTERNATIVE LEGISLATIVE APPROACHES	   88

APPENDIX E:  MODEL BINDING AGREEMENTS	   89

APPENDIX F:  POTENTIAL FOR UNEXPECTED STATE LIABILITY	107

APPENDIX G:  PRESENT VALUE OF $1 DUE IN n PERIODS AT i INTEREST
             PER PERIOD	112

-------
                                   SECTION 1


                                 INTRODUCTION



1.1  PURPOSE OF THIS HANDBOOK


     Recent discoveries of abandoned hazardous waste sites across the country


have dramatized the need :for environmentally sound hazardous waste management


facilities (HWMFs).   Despite this  need.  States  and the private sector have  ex-


perienced considerable difficulty  in securing local acceptance of HWMFs.  Opposition  is


strong and is intensified each day by new "Love Canal" revelations  across the


country.



     There are techniques available to deal equitably and legitimately with


public opposition.  The purpose of this handbook is to supply State governments


with alternative techniques for  dealing  with the HWMF  issues  that stimulate

                          -v
community concern and public opposition.  "This handbook serves  as an intro-


duction to the concepts and possible uses of mitigation/ compensation and


incentives as tools in the siting of HWMFs.  In addition to  explaining


these techniques, this handbook explores some of the major issues and problems


associated with their application.  The handbook is written from two perspectives:


States may directly provide mitigation, compensation, and incentives to deal with


HWMF impact issues; or, States may require the private sector developers of HWMFs


to provide these techniques themselves.  In order for States to exercise either


option, they should have some information on different techniques and on the

-------
issues associated with these techniques.  This handbook is designed to provide




that information.





     A strong note of caution is appropriate at this point:  the impact




responses described in this handbook will have limited usefulness in many




hazardous waste siting situations.  HWMFs induce issues accompanied by highly




emotional feelings which, in many cases, belie the use of the techniques




described below.  While the reader's skepticism about these techniques is




justified, the handbook will attempt to show how these techniques can be




very valuable in dealing with HWMF impact issues.




      The handbook emphasizes compensation and incentives.   This emphasis is




 deliberate.   Mitigation techniques are much more familiar to States,  and,  in




 fact, are already required in the HWMF siting processes being developed by many




 States.   There is also no attempt in the handbook to prescribe a recommended




 blueprint for States to follow.  HWMF siting situations and the impacts associated




 with them  are very site-specific.  The handbook will not recommend a specific




 set of compensation and incentives for certain types of communities.   Rather,




 the handbook suggests types of techniques for different impact issues.  Most




 importantly, the handbook will provide States with  a framework for considering




 and  evaluating different techniques.






 1.2  HAZARDOUS WASTE FACILITY IMPACT ISSUES AND PUBLIC OPPOSITION




      Overcoming public opposition is a critical factor in the siting of HWMFs




 in the United States.  Public opposition to HWMFs stems from a number of potential




 impacts associated with these facilities.  These impacts concern environmental




 quality, health, quality of life, econonmic issues and public service burdens.




 Impact issues occur as a result of the construction, operation and long-term




 maintenance of a facility.

-------
 The principal impact issues associated with the construction! operation




long-term maintenance of a facility include:




 •  Traffic - Increased traffic from waste haulers and employees




    of the facility; increased possibility of traffic accidents and




    spills; wear on local roads





 0  Noise - Created by facility construction and operation,




    and by increased traffic




 •  Ground and Surface Water Pollution - At the site during operation and/




    or disposal and off-site from transport spills




 •  Air Pollution - Emissions from incinerators; fugitive dust from




    landfills




 •  Odors - From transport, processing, and storage of wastes




 •  Aesthetic__Changes - Particularly from incinerators




 •  Risks - Health and environmental risks associated with accidents,




    explosions, leaks, or spills during the operation of a HWMF or




    during transport of wastes to a facility; and during the post-closure period.




 •  Property Values - Decreased property values; of primary importance




    to landowners in the immediate vicinity of the HWMF or along routes




    heavily travelled by transport vehicles




 •  Public Services - Increased burdens for highway maintenance; for




    fire and emergency spill response; for facility inspections and




    monitoring




 •  Community Stigma - Resulting from the presence of a HWMF; this




    may have higher order impacts as well, such as quality of life




    losses and even effects on population movements.

-------
     While public opposition often centers-on  identifiable potential  impacts of




HWMFs, it is clearly not always a rational process.  The unknown risks associated




   .1 HWMFs often create an attitude of  fear  and mistrust.  The public emphasizes




the uncertainty of risks, and  questions the  ability of government, industry




officials or anyone to assure  long-term safety.






1.3  RESPONSES TO HWMF IMPACT  ISSUES:   DEFINITIONS AND EXAMPLES




     The construction of a IINMF involves costs and benefits  to individuals,




groups, the community and society as a  whole.  Some of the benefits associated




with a HWMF include acceptable disposal for  society and profits for the private sector.





If one views the facility impacts as economic  costs, mitigation, compensation




and incentives may be used as  responses  to these  costs.   In broad terms, these




impact response techniques are means for redistributing the costs and benefits




that result from a HWMF siting.  Because there are important differences in how




  •*:igation, compensation, and  incentives relate to HWMF impacts and costs, it is




—.eful to carefully define them.






     Mitigation is an action that prevents or reduces an impact.  It basically




represents the first line of defense in  dealing with impacts.  In terms of HWMFs,




it may mean, for example, redesigning a  facility to prevent groundwater pollution




or noise impacts.






     Compensation is generally a tool for dealing with unavoidable, intangible,




and unpredictable impacts.  It essentially is a means for dealing with impacts




that cannot or will not be mitigated.  Compensation attempts

-------
to make affected interests  as well off after the siting event as they were




before.  The developer or the State provides benefits equal to the value of




  3 impact or cost incurred.






     Incentives, on the other hand, provide benefits above and beyond the




costs associated with the HWMF.  Cost-benefit balance is not an issue in using




incentives to deal with HWMF impacts.  Incentives try to make people better off




than they were before the HWMF siting.  Generally, they provide a HWMF developer




or the State goodwill or strategic value in the siting process.  Exhibit 1




illustrates typical HWMF impacts and typical mitigation, compensation, and




incentives that may be appropriate in the siting of a HWMF.






     There is often a blurry line between mitigation, compensation, and incentives.




The reader should not assume that a clear distinction can always be made between




these techniques.  It is almost impossible, for example, to determine the precise




 nount of compensation to apply in a siting situation.   Therefore, the distinction




oetween incentives and compensation is not always possible to make.






1.4  RATIONALE FOR THESE RESPONSES




     In general, mitigation, compensation and incentives:




     •  Provide a more complete accounting of HWMF costs;




     9  Provide an opportunity for HWMF costs to be balanced by




        HWMF benefits or developer-provided benefits;




     •  May help to ensure the siting of environmentally sound




        HWMFs and, therefore, help to prevent illegal dumping.






     Due to the inherent differences between the three techniques, the rationales




for each one are considered separately.

-------
Why Mitigate?




     First of all, there may be requirements in other Federal, State, or local




   ulations to mitigate impacts.  These requirements may be specifically-outlined




in local zoning or state environmental impact regulations.  Secondly, it may be




more efficient or cost-effective to deal with impacts up front rather than paying




for them later.  For example, aesthetic and noise impacts of a proposed HWMF may




pose significant issues — ones that may eventually concern the community in




which the facility is sited.  In order to avoid potential complaints that residents




may voice after the facility is built, the developer or the State may buy




sufficient land as a buffer for the facility before construction of the facility.




The developer may also find it considerably more expensive to purchase additional




land later to deal with aesthetic and noise impacts.  Airports are prime examples




in which additional land purchases to deal with noise issues are very expensive.





Finally, it may be desirable to mitigate potential or projected impacts for




  rategic reasons.  A community and its residents will generally be more receptive




to a HWMF where the developer carefully anticipates impacts and takes actions to




prevent or reduce them.  By explicitly considering and proposing alternative




mitigation measures, developers or the State may establish credibility and trust




with a host community.






Why Compensate?




     While the developer will generally find it desirable to mitigate HWMF impacts,




it may be impossibTe to mitigate all costs associated with a facility.  This




difficulty may stem from technical problems, such as the inability of a site




location to be changed; planning problems, such as the difficulties associated with




predicting the type and magnitude of impacts; and economic reasons — it may

-------
 iply be cheaper to site  now and pay later.   Additionally, mitigation may  never




 complete for all possible  impacts of HWMF  siting because some risk will  always




    i.  Compensation  is useful in HWMF siting because it provides  a mechanism  for




 spending to the long-term impacts and risks associated with these facilities.






    Compensation is particularly useful for  resolving the problems of  economic




 equity associated with HWMFs.  Through compensation, the true costs and benefits




  a facility can be more  accurately figured  and evenly distributed, avoiding




 :cessive  localized costs.  In short, compensation can enable a more efficient




 id appropriate site  selection process.






 ny use incentives?




    Since incentives represent additional payments in the siting process,  they




re not easily  rationalized by a cost-benefit framework.  Incentives  are useful




n HWMF siting for goodwill and strategic purposes.  In using incentives a developer




.emonstrates to a host community, group, or an individual the willingness to




  -.r additional costs in order to  site a facility.




     The most important consideration in the use of incentives is their potential




to backfire,  i.e.,  to be counterproductive in dealing with public opposition in the




siting of HWMFs.  Incentives  that  are unrelated and non-responsive to impact issues




that remain unmitigated or uncompensated are especially vulnerable to backfiring.




There is considerably much  less backfire possibility if the community initially




suggests the use of incentives.






 1.5  EXAMPLES FROM OTHER FACILITY  SITING EXPERIENCE




     In considering a potential State role for compensation in the siting of HWMFs,




it is useful to briefly  consider other facilities  that  are perceived as objectionable.
                                        8

-------
The role of the States in compensating the impacts of these facilities provides




some perspective on HWMF compensation.






     There are a number of other nuisance type facilities that typically stimulate




objections in the siting process.  Some of the facilities include:




     •  Municipal wastewater treatment facilities




     •  Prisons




     •  Airports




     •  Energy facilities






     While incentives and compensation have been applied or considered in each




of these facility siting situations, the State role has varied considerably.  In




municipal wastewater facilities, for example, States provide an incentive to




communities to build the facility through a matching grant to an EPA construction




grant under the Clean Water Act,  The Federal government provides 75% of the




•"onstruction cost; States generally provide 15-20t;ancL the communities the rest.




.ne State portion is typically viewed as an incentive to the community to build




sewage treatment facilities.  The latter, like a HWMF, is perceived as providing




benefits beyond the local community — thus, the rationale for State subsidy of




the facility construction cost.  The combined funds — EPA, State, and local —




are also used for mitigating impacts that are likely to occur from the treatment




facility.  Thus, in the siting process, grant recipient communities raay be




required to change the design of a facility, alter operating plans, or even choose




a different location.

-------
     Prisons and airports offer two facility siting situations in which the State




   >ften the owner and operator of a nuisance facility.   This is in contrast to




the above example.   Airports have a relatively extensive experience in the




last 10-15 years with impact mitigation techniques.  For example, runway




location, buffer zones, and flight patterns have all been used to deal with noise.




More recently, airports have also used compensation techniques to offset property




value changes.  For example, the Logan Airport operation in Boston, MASSPORT,




purchased homes of nearby residents to compensate them for noise effects.  There




does not appear to be much evidence for the use of compensation or incentives




in the siting of State prisons.  These facilities generally, involve, at a




minimum, however, mitigation actions in the form of buffer zones.  In addition,




in-lieu of tax payments are fairly common with prisons.






     All of the above  situations involve the State in compensation in a facility




   .t is publicly owned.  While these are useful precedents for a State-owned HWMFs,




most States are initially involved in HWMF siting  as a regulator and not as




an owner.






     For privately-developed HWMFs, energy facility siting  experiences  offer useful




analogies  for State  HWMF compensation approaches.  In States where  there  has  been




considerable  energy  facility development, energy  facility siting laws  have been




developed.  These typically require the  energy developer to obtain a number of




permits in order  to  construct  a  facility.  States have used their  permit granting
                                         10

-------
 uthority to require developers/utilities to compensate local communities for




 ocioeconomic impacts associated with the construction of the facility.  This




 •onuirement may involve grants to the communities or developer-provided services




   ch as roads and sewers).  A good example is the Washington Public Power Supply




 jystem's (WPPSS)  $12 million compensation for public facility and public service




 Impacts projected to occur from its nuclear power plant construction activities.




 Che WPPSS negotiated agreements for this amount in the mid-1970's with 44




 iifferent taxing districts.   The State of Washington's Energy Facility Site




 Evaluation Council encouraged this compensation and served as a mediator during




the negotiations.






     Generally, in energy facility siting situations, the States expect or require




 the developer to deal direcly with the local community to mitigate or compensate




 impacts.  Actual State involvement with compensation may be limited to planning




 grants or planning assistance.  Because of the financial resources that an energy




 ^aveloper has, States have not felt compelled to subsidize the mitigation or




  .opensation effort.






     In summary, while States have had a role in nuisance facility compensation,




there are not extensive analogous situations in which States are directly providing




compensation for private facilities.  States have been fairly active in compensating




impacts when public facilities or projects are involved.  Energy facilities




provide the most extensive examples of compensation for private or semi-public




facilities.  And in these cases, States have generally required the developer to




directly provide the compensation.






     In considering the utility of mitigation, compensation, or incentives, the




 reader should also consider previous experience with HWMF siting.  How do you




prevent stalemate from occurring in the siting process?  How can you help to ensure
                                        11

-------
 hat costs are better distributed?  Certainly mitigation,  compensation and




 ncentives have drawbacks — and these are discussed, but their use may ensure




 be siting of an HWMF by recognizing HWMF impacts, not by facing-down objections.






  6  SCOPE OF THIS HANDBOOK




     This  handbook provides an examination of the techniques of mitigation,




 rompensation and incentives as responses to HWMF impacts.   Section 2 explores




 jiitial State considerations in using these responses, particularly State versus




 >rivate sector provision and basic implementation issues;   Section 3 examines




 oitigation; Section 4 looks at compensation; and Section 5 reviews incentives.









 Several appendices supplement the text:  Appendix A discusses the State's power




 to impose  impact response requirements on a HWMF developer; Appendix B looks




at some interstate issues arising out of state-provided impact response;




Appendix C examines the power of a state to provide impact responses; Appendix




D presents compensation language from selected state legislation.  Appendix £




   cains two model binding agreements—one between a HWMF developer and a




community  and one between a HWMF developer and a resident; Appendix F briefly




examines the liability issue associated with state-provided impact responses.



 appendix  G is  a present  value  table  used  in an  example  in the  text.
                                     12

-------
                                  SECTION 2




                            INITIAL CONSIDERATIONS
     The application of impact response techniques involves a number of con-




siderations.  This section will review some of the key evaluation issues for




States including:  the potential problems associated with State versus private




sector provision; and general implementation issues in providing mitigation,




compensation, and incentives.




2.1  STATE VERSUS PRIVATE SECTOR PROVISION




Issues



     State involvement in mitigation, compensation, and incentives may open




up the State to a number of potential problems.  These may occur depending




on whether the State directly provides the impact response or requires a res-




ponse from the HWMF developer.  Major issues include:




     •   Political Precedent — State involvement in these techniques may




         set a precedent for a similar State response in a future nuisance




         facility siting;




     •   Compromised State Regulatory Role — Direct State provision of these




         techniques may be viewed by the public as a compromise of the State's




         power to also regulate HWMFs;
                                   13

-------
     •   Legal Authority -~ Thexe are legitimate questions abput the




         legal authority1 of a State to provide compensation and incentives,




         There may also be legal opposition by the private sector to re-




         quirements imposed on them;




     •   Private Market Interference —  The HWMF private developer may view




         any requirements as interference in the community-private sector




         negotiation process;




     •   HWMF Costs — These techniques will redistribute and alter HWMF costs




         whether the State provides the techniques or requires them of the




         developer;




     •   Interstate HWMF Effects — The impact of the two previous issues




         may shift the development of HWMFs from one State to another




         and shift the transport and disposal between States.








     The magnitude of each of these issues varies, depending on the technique,




 rfnership (State or private) of the facility, and the institutional arrange-




ment under consideration.  While the major issues of State versus private




sector provision will be discussed with respect to specific technique in




Section 3, 4 and 5, it is useful to introduce these issues initially with




respect to different institutional arrangements.








Institutional Arrangements




     The basic alternative insitutional arrangements for the provision of




impact response techniques include:




      -  Private sector provision, no State requirements




      -  Private sector provision. State requirements




      -  State provision




      -  Combination of State and private sector provision
                                     14

-------
          Private Sector Provision; No State Requirements




     This case is a free market situation.  Impact responses result from




  >luntary negotiations between the host community and the HWMF developer.




The above issues should be negligible in this situation; however, other




concerns warrant consideration.  Voluntary negotiations may not occur, or




they may be unsuccessful.  This may delay the siting process and hinder




site acceptance by failing to address public opposition.  The failure to




provide a contractual arrangement for compensation and incentives may also




discredit  the legitimacy of the siting process which may increase accusa-




tions of developer bribery.  Such accusations could also delay facility




siting.  These considerations have led some States to adopt compensation




legislation for HWMF siting.








          Private Sector Provision, State Requirements




     The precedent set by State legislation requiring private industry to




provide impact responses is not of major concern  to most of the  States.




States that have already passed such  legislation  do not feel that the prece-




dent will create problems in other regulatory areas.  The legal  authority




of States to  impose requirements on private industry is also not a major




issuet  In most  cases, conditions  that impose compensation  requirements on




private developers, communities or individuals, may be  included  in permit




applications  for the  siting of HWMFs  through a State authorized  agency or




board.  For more discussion of this subject see Appendix A.




     State requirements  on the private sector to  provide impact  response




is clearly within  the regulatory role of  the State.  The legal issues generally




revolve around  the extent of burden a State may impose  in the private sector.
                                      15

-------
     The type and form of impact response requirements placed in the private




sector by the State have major effects on the siting process.  There are two




schools of thought on this issue.  Some States and private sector developers




view State legislation with specific requirements — such as, type, amount,




.and recipients of impact response — as inflexible and constraining.  They




would prefer to see the developer and host community negotiate unbridled




by State requirements.  State requirements on compensation and incentives,




in particular, are -viewed as private market interference.  State requirements




take away a developer's bargaining chips.  Other States and private sector




developers view a reasonable amount of State requirements as facilitating the




siting process.  Legislated requirements, according to this school of thought,




provide a structure in which everybody can then negotiate site-specific




adjustments.  All developers start out on this basis; similarly, all communities




start out with a core level of required impact response techniques.




     The major effect of State requirements on the private sector to provide




impact responses involves costs.   A principal concern here is the economic




burden placed on the developer, and, in turn, the impact of this burden on




the developer's ability to obtain private financing and establish the facility.




Where legislation allows the community and developer to negotiate impact




responses, as is the case in Massachusetts, this flexibility may relieve




some of the economic burden.  Additionally, the true costs of HWMF siting




are reflected by the extra costs, which, ultimately will be paid by the




consumer.  The state of Connecticut adopted compensation legislation, how-




ever, and found industry very supportive of the requirements despite the




additional costs.
                                     16

-------
     State legislation may also have interstate effects.  Wastes may be




shipped to States where the cost- burden on hazardous waste generators,




and therefore the cost of disposal, is less.  This competitive advantage




also resides with facilities established before the legislation since they




do not have the extra costs of impact responses,  This will obviously not




be a problem for States with no facilities prior to legislation.  Since the




demand for HWMFs is so great, interstate differences in disposal costs may




not effect disposal patterns; it may still be cheaper because of transporta-




tion costs to use the in-state facilities.  Appendix B discusses alternative




arrangements for dealing with potential interstate disposal effects.








          State provision




     State provision of impact response may 'be favorable for a number of




reasons.  Exclusive State provision of impact responses may minimize the




possibility or perception of illegal payoffs between the private developer




and a community.  It may also help to resolve differences between communities




and the developer and thus help to shorten the siting process.  In general,




State provision of impact responses provides the State with additional




control over the entire impact response process.




     States should consider a number of issues before directly providing




impact responses.  Direct monetary payments from the State for mitigation,




compensation, or incentives may set a political precedent for other public




and private nuisance facilities,  A number of States voiced this concern




in a series of interviews with State hazardous waste officials.  One way to




diminimsh this possibility is through the use of special language in HWMF




impact response legislation that deals with the extraordinatry circumstances




surrounding HWMF siting.
                                      17

-------
     State provision of impact responses may also undermine the credibility




3f the State regulatory role.  This is  an important consideration  and one




   t is also of concern to many State hazardous waste agencies.  The public,




for example, may perceive the States as unable to adequately regulate a HWMF




in which they have provided a substantial investment for impact response,




The potential conflict of interest in State roles is minimized, however,




if States provide impact responses to communities rather than to developers.




There is also precedent for State aid to and regulation of a particular




party.  For example. States subsidize municipal wastewater treatment plants




and the same State agencies regulate them.  States also provide a number




of subsidies, such as economic development loans to private industry, and




also regulate their activities.  One precaution that States could implement




to minimize conflict of interest charges is to have a State agency, separate




from the regulatory agency, to be responsible for impact response activities.




     Legal Authority should not be a problem for State provision of impact




 -isponses.  States possess the power to tax and spend in the public interest,




and may determine what goods and services they will provide and how they will




be financed.  For a more complete discussion of this issue, see appendix C.




     State provision of impact responses effects the cost of HWMF siting by




reducing part of the economic burden on industry.  States, in effect, absorb




some of the HWMF costs in order to facilitate the siting process.  This




State role thus acts as an incentive to private developers in the siting of




HWMFs,  While this may be questioned as a subsidy to the private sector,




State subsidies to private industry already exist in a variety of forms




including the development of highways to industrial parks and low-cost




industrial development loans.
                                      18

-------
     Despite the incentive intentions of State-provided impact responses,




there may be impacts on the private market and interstate disposal costs.




If State involvement in HWMF impact response provides the private developer




with a competitive advantage over other HWMFs, cheaper waste disposal rates




may attract out-of-state wastes.  It may also affect disposal patterns at




existing facilities in the State.  A key issue for the interstate problem




involves the distribution of costs.  This is directly related to the




financing techniques and response method employed.  In the case of State




provision of compensation through the use of general funds, State residents




absorb the compensation costs, and in this way subsidize out-of-state waste




disposal.  There are two ways to deal with this issue:  develop agreements




with governments from out-of-state users; or legislate a surcharge on HWMF




disposal fees for out-of-state users.  See Appendix B.




     In general, the cost issues surrounding State provision of impact




responses concern basic political policies on economic efficiency and equity:




Who should bear the costs of HWMFs?  Users/ host  communities, society at large?




The type and provider of impact responses, influences  the  siting efficiencies




and the distribution of HWMF costs.  States will  have  to independently evaluate




their needs with respect to the use of these techniques, analyze how they may




ease siting difficulties, and distribute the costs and benefits of these facili-




ties.  The techniques in the sections below illustrate different cost and equity




effects for the States to consider.




          Combination of State & Private Sector Provision




     Mitigation, compensation, and incentives may be supplied in a number of




different combinations by the State and private sector.  The types of issues




for the State to consider here may be different than just  the aggregate of
                                       3.9

-------
 State provision and private sector provision issues.   State  provision  of




 compensation,  for example,  may offset the economic burden  imposed by a




 State requirement for mitigation.   Because there are  so  many different' com-




 binations  it is impossible  to discuss generic issues.  The following example




 shows how  one  combination of State and private sector provision  of  impact




 responses  may  affect issues previously discussed.




      In this example,  the State provides incentives to the host  community,




 such  as extraordinary road  improvements and additional emergency equipment




 to the community,  while requiring  the developer to provide compensation to




 the host community through  a tipping fee of 5C/gallon of disposal waste.




      A political precedent  is being set by the State  provision of incentives.




 However, the compensation provided by private industry may counter  balance the




 visibility,  and relative importance of the precedent  being set by the  State.




 The State  regulatory role is not compromised by the provision of incentives,




 although any direct monetary involvement may be criticized.   Many of the cost




 issues previously  discussed still  apply to this situation  depending on how the




 incentives are  financed by  the State.   Some of the issues  may be minimized




 by the combination  of  State and private sector provision of  impact  responses.




 For example, although  the incentives  provided by the  State may subsidize in-




 dustry, the private  sector  provision  of compensation  to  the  community will




 increase the developer's  disposal  costs to reflect the true  costs of HWMF




disposal.   Thus, the competitive advantage or disadvantage that would be




 induced by provision of impact responses  from just one of  these parties may




be negated by the combined  provision.   Clearly, various  provider combina-




tions will influence the  major issues  of  State  versus  private sector provision




of impact responses.
                                     20

-------
2.2  GENERAL IMPLEMENTATION ISSUES IN PROVIDING MITIGATION, COMPENSATION,
     AND INCENTIVES
     The basic implementation issues in providing mitigation, compensation,

and incentives include:

     •   Determining impact issues and local concerns,

     •   Identifying potential recipients.

     •   Selecting appropriate techniques,

     •   Determining amount of response.

     •   Determining timing of response.

     •   Selecting finance mechanisms.

     •   Developing binding agreements between provider and recipients.

     These issues characterize any effort to provide impact response whether

the response is supplied by the developer or the State.  This section

briefly introduces these issues so States can consider them before developing

impact response legislation,


Determining impact issues and local concerns

     The first step in implementing an impact response technique involves

identifying the impact issues and local concerns.  Four basic impact charac-

teristics will determine the range of impacts associated with a facility:

     •   Impact type.

     •   Impact magnitude.

     •   Impact incidence (who & where}

     •   Impact timing (when & duration)

     This impact discovery and characterization process for each site will

undoubtedly uncover a number of environmental and socioeconomic impacts such
                                     21

-------
as those listed in Section 1.  The State may formalize this process




through an environmental impact review process.




     Obviously, impact identification should carefully consider local




concerns.   Since impacts are perceived by the community differently than




by a developer. States should consider a formalized process for including




local concerns.




     Impacts occur when the characteristics of a specific HWMF interact with




the conditions existing at the site where the HWMF is located.  Thus,




a HWMF with a capacity of 200,000 gallons/day may stimulate 40 trucks




coming and going to the facility each day.  Site specific access condi-




tions and land use characteristics will affect the severity of this traffic




Impact, and the perception of its significance.  There may be minimal




impacts in a heavily industrialized community with existing good access to




the facility.  In a suburban location, on the other hand, traffic may be




a critical issue.




     Most State regulatory agencies are aware, of course, of the difficulty




of accurately predicting all of the impacts associated with any facility.




This handbook does not presume that this process is easy or that all impacts




will emerge in the impact discovery process.  At best, some issues may only




be red-flagged.  In these cases, impact response contingency arrangements




are appropriatet








Identifying potential recipients




     The impact characteristics will influence this process.  Property value




issues may be of interest to land owners, for example, in the immediate




vicinity of the HWMF or along transport routes.  Community water supply
                                     22

-------
 unpacts,  on the other hand,  affect the entire community,   Risk impacts,




 in many cases,  cannot be parceled out neatly to recipients.   Because




    antial recipients will vary by impact issue,  a mix of  impact responses




 is often  desirable.   For example, cash payments to the host  community  will




 not adequately  address impacts in neighboring communities.   These  communities




 may require mitigation measures or incentives.




      In fact, identification of the parties affected by each impact issue




 will aid  in the choice of response techniques,   A formalized process for




 this identification  will be  particularly useful in avoiding  accusations of




 unfair  and nonresponsive compensation and mitigation.   Again,  however, this




 handbook  recognizes  the complexity of impact incidence.   States and de-




 velopers  of HWMFs may simply not be able to define initially all those




 affected  by impacts.








   lecting Appropriate Techniques




      Selecting  the appropriate impact response technique  involves  a number



 of considerations, including;




      •    Impact Issue/Impact, Response Matching




      •    Legal  authority,




      •    Cost~effectiveness«




      •    Strategic value,




      •    Secondary impacts,
                 Issue/Impact Response Matching
     This issue may not be a major concern to some States.  Once the HWMF developer



has identified both impacts and impact incidence to the maximum extent possible,
                                    23

-------
the State may not  care what type  of  responses are actually applied,




The State may only be concerned that impacts are mitigated in or compen~




sated.  The handbook discusses State considerations for specific tech-




niques in Sections 3, 4  and 5,  As seen in  these sections, some techniques




are more appropriate for certain  impact issues.  In general, mitigation




is the first category of impact response  to consider.  In practice, however,



mitigation techniques are not totally suitable for all impact issues,  Some




impacts are unavoidable  and cannot be mitigated; others are difficult to



predict.  In these cases,  some type  of compensation is clearly warranted.




But developers and States obviously  should  not feel constrained by any "impact



issue/impact response matching" rules.  There simply is not a best or clear-




cut formula to apply.  Incentives, for example/ may or may not be directly



related to impact  issues.   Those  that are not related to specific HWMF




impacts, however,  may still have  an  important influence in siting the HWMF.
                Authority
     Pre-existing regulations or authority may constrain the implementation




feasibility of a particular impact response.  An example of this involves




alternative trucking routes as a response to traffic impacts.  In this case,




one of the alternatives may involve rerouting traffic along different high-




ways to avoid residential areas.  Existing Federal and local highway regula-




tions, however, may preclude the use of alternative routes.  In terms of




compensation, State constitutions may forbid the State to commit itself




to long term monetary arrangements.  Thus, the State may not be able to




agree to provide compensation funds to a community on an on-going basis,
                                     24

-------
          Cost-Effectiveness
     In most cases, mitigation, compensation and incentives will add costs
to the overall HWMF project.  As argued in Section 1, these are "legitimate"
costs that have often not been reflected in previous HWMF sitings.   The
magnitude of these costs will, of course, be dependent on the type  of
impact issue under consideration.  In some cases, however, a number of
techniques may adequately deal with a specific impact issue.  Refer to
Exhibit 1 in Section 1.  In these cases, cost-effectiveness can be  used as
a selection criteria.  For example, as a response to the aesthetic  impacts
of a HWMF, mitigation measures might include developing a buffer zone or
relocating the facility on the site.  Compensation would involve direct cash
payments to the affected parties.  It may be cheaper to provide the buffer
zone as well as administratively easier.
     Different techniques and financing methods will also clearly involve
different administrative costs.  A response involving ongoing payments from
the State to a community will require some type of a distribution program.
One-time up-front payments, or direct payments from industry to the community
will not add this expense to the State,  The administrative costs of different
techniques should be included in cost comparisons.
     Cost should also be determined in present value terms  in order to adequately
compare one-time costs with techniques that involve on-going costs.  See Exhibit 2
for an illustration of this concept.


     Strategic Value
     The choice of impact response techniques obviously involves strategic con-
siderations.  The political acceptability  of an  impact  response will be a
                                      25

-------
                                         EXHIBIT  2

                                   PRESENT VKLJJS ANALYSIS
  xition;  Present value analysis  is  a technique for comparing the costs of alternative iaaact
  anse schemes having different  time  streams of capital and recurring costs.  The present value
  uture cost represents the sum  that  would provide an equivalent income stream,  if held in a
   which yielded the current rate  of  interest.  In reality, there is no one current rate of
  rest.  The current rate at which one must borrow funds, however, is generally acceptable.

   The formula for determining present value if the HWMP impact response period is T years
 re
         C   • Capital costs at time n

         0   • Other costs at  time n
         PV  - I/O. + t)n. when  i -
           n
                                             1UQ
   Impact response capitol costs may involve new roads or buffer zone purchases; other costs
j be  tipping fees or other on-going payments.

mole:  Rather than use the present value formula, one can consult a present value table as
own in Appendix C and use the present value factor for a specific interest rate and tise period.
simplified example is shown below i

   Impact Response Alternative  1

       Project Start-up;

         •  New fire truck to  host community

         *  loop sum payment to property abutters

         •  Payment to host community to fix access road

       Continuing;

         •  Tipping fee to host community

         •  Tipping fee to neighboring communities

   Impact Response Alternative  2

       Project Start-up;

         •  Lump sum payment to property atwtters

       Continuing;

         •  Tipping fee to host conmunity

         •  Tipping fee to neighboring communities
$ 80,000

$ 45,000

$300,000
$425,000


$ 50.000/year

S 10,OOP/year

$ 60,000/year




$ 45.000



SlOO.OOO/year

S 10,OOP/year
5110,000/year
   Assumptionst  20 year planning period
   Interest Rate:  10%
   (Private sector)

   Alternative 1.-  PV - 542S,OOO(.1486) * * ($60.000X20 years) (.I486)

                     m $63,155 + $178,320

                     • $241,475

   Alternative 2i  pv • $45,000(.I486)  + ($110.000) (20) (.1486)

                     • $6,637 +  $326,920

                     - 5333,607
   *rrcm Appendix C
                                                26

-------
   \jor factor in HWMF siting.  For example, there is substantial mistrust




ay the public about the technological adequacy of HWMFs,  A well~conceived




mitigation and compensation strategy may be insufficient to overcome this  mistrust.




Without third-party monitoring above and beyond what is required, public




opposition may remain entrenched.  In general, host communities and other




sources of public opposition may not place much credibility in a HWMF




developer's operation promises, or promises of State enforcement.  These




mistrust and enforceability issues may well be addressed in many cases via




the incentive of third-party monitoring,








          Secondary Impacts




     An important consideration in selecting an impact response concerns




the indirect or secondary impacts that responses induce.  Simply put,




  solution to one problem may lead to another problem.  For example, one




solution to increased truck traffic to a proposed HWMF is to build one or




more transfer stations and ship the waste in fewer and larger vehicles,




This alternative essentially involves siting an additional HWMF to facilitate




the development of an already proposed HWMF.  The solution may require as




many complex negotiations and impact issues as the original facility.




     Each of these considerations are relevant to the selection of an appro-




priate impact response.   From the State perspective, the diversity of the




considerations implies that comprehensive HWMF impact response legislation may




be difficult to develop.   Massachusetts and Connecticut offer two contrasting




examples of States that have recently passed hazardous waste siting  legis-
                                      27

-------
   ion that includes  a provision mandating developers to provide compensation,




cue legislation, however,  merely requires the activity <~ it doesn't spell




jut precise requirements.   Site specific negotiations between the developer




and a host community  will  determine the appropriate techniques according to




the Massachusetts  approach,  though the State may also act as an arbitrator.




Connecticut, on the other  hand, recently passed legislation specifically




spelling out the type and  amount of developer compensation to a HWMF host




community,  Kentucky  has also recently passed similar legislation.  In




both cases, the developer  pays a tipping fee to the host community based




on the amount  of waste handled at the HWMF.  See Appendix D for these




alternative legislative  approaches.  The Connecticut and Kentucky legislators




do not pretend to  offer  comprehensive impact response approaches.  Rather,




they require a core starting point from which additional site-specific




   act responses could be  negotiated by the developer and affected com-




munities.  The Massachusetts approach assumed that the whole package of impact




response should be negotiated.



    Finally,  the  consideration of each of these factors in selecting appro-




priate impact  response  techniques is obviously not a clear-cut  exercise.  A




hypothetical example  is  shown in Exhibit 3 to illustrate the difficulty in




selecting among impact  responses.  In this particular example,  the choice




is among different mitigation techniques to deal with truck traffic impacts.




Inqpleinentation feasibility encompasses, in this example, legal  authority and




political acceptability issues.  The example illustrates the tradeoffs  that




have to occur  in  selecting impact responses.  The most  effective  measure—the
                                        28

-------
                                                              CHIBIT 3
                                                     Mitigation Alternatives

                                For Dealing with HWMP Truck Traffic Impacts (Hypothetical Example)
           MITIGATION
          ALTERNATIVES
                    COST*
                   EFFECTIVENESS
                      IMPLEMENTATION
                       FEASIBILITY
                              SECONDARY
                               IMPACTS
          Reduce Size
          of HWMF
                $3,600,000
                (lost profits)
                   Will cut truck
                   traffic by 50% to
                   HWMF
                      No special problems
                      except for financial
                      feasibility of a
                      smaller facility
                              Will require another
                              facility in the metro-
                              politan area to meet
                              hazardous waste disposal
                              needs; higher disposal
                              costs t.o industry
     B.
vO
Reroute
traffic along
different
highway(s)
$  750,000
(cost of repair-
ing alternative
route)
Will eliminate
traffic in residen-
tial area; shift
traffic to rural  •
route; difficult
to enforce
May shift political
opposition to another
area; otherwise no
special problems
Fewer people affected by
rural route, hut op-
position may be en-
countered
          Construct
          transfer
          station in
          another area;
          use larger
          haul trucks
                $4,200,000
                   Will cut truck
                   traffic by 75%
                   to HWMF
                      Will be politically
                      difficult unless done
                      in local industrial
                      area
                              Will require the siting
                              of the transfer station
                              with all of its attendant
                              impacts; increased risk
                              due to extra handling;
                              roadways may deteriorate
                              more quickly	
     D.
          Limiting HWMF
          operatine
          hours  to
          strictly
          9:00 AM to
          5:00 PM
                $  500,000
                (lost profits)
                   Will eliminate
                   truck traffic dur-
                   ing sensitive
                   hours
                      No special problems
                              Will concentrate truck
                              traffic' in peak traffic
                              hours, thereby increasing
                              traffic accident risk
     *These are costs  (capital, 0 & M,  lost profits)  to the developer or to the State and are expressed in present worth
      terras on the basis of a 20 year design life for the 1IWMF.

-------
  •ansfer station alternative—is also the most explosive and is complicated by




  ie political problems of siting another facility.  The least expensive option—




    .imitations on operating  nouns—does not totally prevent the problem.




  gtennining Amount of Response




    •The amount of mitigation, compensation or incentives to be used is




 xjtentially the most negotiable aspect of impact response implementation.




 is mentioned above, the  States that have adopted compensation legislation for




 compensation in HWMF siting have chosen two basic approaches with respect




 to the amount of compensation:  an open model and a closed model,  Massachusetts,




 believing that the main  purpose of legislation is to legitimize the compensa-




 tion process, has an open model.  The Massachusetts legislation explicitly




 allows any conceivable type or amount of compensation to meet any conceivable




 adverse impact.  Communities  and operators are free to negotiate any agree-




 ment providing that it does not reduce environmental controls below the level




  •mired by the State.   Kentucky and Connecticut use a closed model.  In




 _ese States a specific  amount based on the waste volume or revenues of the




 HWMF developer is paid to the host community.  Even with closed model, legis-




 lated amounts, however,  can remain somewhat negotiable.  For example, in




 Kentucky the local governments are left with the decision of whether or not




 to tax the HWMF's revenue.




    These two methods have advantages and disadvantages.  When the amount of




 compensation is fixed, the  siting process is likely to proceed more quickly.




 Additionally, both sides know what to expect.  The developer knows the cost and




 can  factor it into his calculations while the community can determine if the re-




quired compensation is sufficient.  The disadvantage of the closed approach rests




with its inflexibility.  The  payment may be too low or high for a given situation,




and  it-may not allow for other types of responses.  Also if the required payment




  too high, HWMFs may not  be able to afford to provide other more effective or
                                    30

-------
 iesired compensation, or mitigation measures.   The  major problem associated with

 the open model is that it may lengthen the  negotiation process.

  ermine Timing of Response

    The implementation feasibility  of  a particular response is directly

 related to the timing of  an impact.   While some impacts, such as construction

 noise, occur for a limited  length of time,  others,  including those related to

 facility operation, occur continually over time,  The acceptability of a res-

 ponse is related to how adequately it deals with the timing of a potential

 impact.  A response offered on  an ongoing basis, such as direct monetary com-

 pensation based on HWMF waste tonnage,  can deal with impacts as they occur.

 It nay not, by itself, however, successfully provide for post-closure impacts.

 A one-time payment made up-front, or a  design-change mitigation technique does

 not address ongoing, operational impacts.  Obviously, some responses will be

 better suited for certain impacts than  others.  Incentives may be more appro-

 nriate for impacts relating to  the community image, while compensation, in

 ,e form of land value guarantees to property owners, may address property

 value impacts more completely.

 Selecting Financing Mechanisms

    One of the most difficult  issues facing States that provide HKKF impact

 responses, whether it be  monetary payments, in-kind replacements, or contingency

 arrangements, is the finance  issue.   There are three general approaches to

 financing State-provided  impact responses:

    1)   State general funds,

    2)   Fees or taxes on  private HWMF operators, disposers,
         or generators.

    3)   Some combination  of 1 & 2,

    A number of specific State statutory constraints will affect the finance

 'ecision, such as limits  on bonding.   In addition  to these considerations,

uowever, States should also consider the equity and hazardous waste disposal


                                     31

-------
market impacts, of their; financing decision.  Reliance solely on State

general funds potentially burdens all of  the State residents with HWMF

impact costs.  This financing method may  also result in a State subsidy

to new HWMFs allowing them to gain a competitive advantage in the HWMF

market over existing in-state and out-of-state HWMFs.  As alluded- to

earlier, this may alter transportation and disposal patterns of hazardous .

wastet  The use of HWMF disposal fees to  finance State-provided impact

response will distribute the disposal costs more equitably but may weaken the

competitive advantage of new HWMFs with respect to existing HWMFs,

     A summary of State finance options is presented in Exhibit 4 .



Binding Agreements

     When the State directly provides impact responses or if it requires the

private sector to do so, generally an agreement will be necessary to ensure

recipients that the provider will supply  the promised response,  In the

first case the State may have to enter into agreement itself with recipients;

in the latter case the State may want to  review impact response agreements

between a HKMF developer and a recipient.  Appendix E presents two model

agreements:  one between a developer and  a local government; and one

between a developer and a private citizen.  Appendix E also discusses the

issues associated with bringing agreements and for impact response techniques.

In general, these agreements face the following obstacles:

         Local governments cannot contractually bind the community to
         refrain from exercising its police powers in the future.  Thus,
         an agreement between a HWMF developer and a community will
         probably not have quid pro quo arrangements.  Rather, the
         agreement is more of a mechanism for developers to demonstrate
         their commitment
                                   32

-------
                                              At/TERWATIVE
                                                                          3  FOX  BTJVTB  FBOVH-gO MMMT
         METHOD
                                   DRFINITIOM
                                                                            USEe/EXAMrMSS
  General  Obligation
  Bonds
These bond* are backed by the "full
faith and credit" of the issuer and
are generally financed by taxes and/
or revenues from user charges.
Suitable for compensation that Involves
one-time capital expenditures.
These bonds typically carry lower Interest
rates than revenue bonds.  Amount of indebted-
ness capable of being Incurred might affect
the use of this mechanism.
   Revenue Bonds
In this type of bond, payments are
derived strictly from charges for
services provided.
These are also generally used for
capital costs, particularly in cases
where charges can be easily matched
with compensation provided.  They are
also attractive where statutory limi-
tations prohibit additional debt via
general obligation bonds.
These bonds typically carry higher interest
charges than general obligation bonds.
3. Grants/loans
These are cost sharing sources out-
side the jurisdiction.  They are
generally used to  finance a portion
of the capital costs of a project.
The State may be able to obtain grants/
loans from the Economic Development
Administration or regional conmlg-
sions.  In addition. Federal categorical
grants, such as highway money, could
be used to finance  in-kind compensation.
By subsidizing a portion of the capital costs,
grants and loans will, of course, reduce the
State's share of compensation costs.  This may
be critical to political acceptability of a com-
pensation measure.  Cost-sharing programs, how-
ever, may Impose conditions that may be unaccept-
able to the State.
4. General Operating
   Revenues
 These funds may  come  from a  variety
 of  State  sources,  such as miscella-
 neous fees',  fines,  and taxes.
These are suited to recurring
compensation costs or capital costs.
They can also be set aside money  for
sinking funds that can be used for
specific compensation projects.
The use of general operating revenues distri-
butes compensation costs to both users and non-
users.  Sinking funds, much like a private
savings account, use past revenues to fund
current projects.
 5. User Charges
 User charges are revenues  derived
 from a user of a project or service
 and are based on actual or surrogate
 measurements.
 The  State  may collect  these  from dis-
 posers  or  operators  of an IIWMF  to  finance
 capital and  recurring  compensation costs
User fees ami charges are designed to maximize
the "earned rewards" principle by charging users
for services received.  A consideration in setting
user fees Is the impact that it might have on the
user.  If States try to totally recover compensa-
tion costs through user fees, they may stimulate
non-use of on environmentally suitable IIWMF and
use of ill«V}
-------
Agreements with  local governments are, of course,
not binding on the residents of communities,  Thus,
for some impact  issues the developer will have to
develop agreements with  individual residents or
groups.
                                  34

-------
                                   SECTION 3

                             MITIGATION TECHNIQUES



3.1   INTRODUCTION

     Mitigation  generally involves an action that attempts to prevent  or  reduce

impacts from occurring.   The key aspect of mitigation is its preventative

nature.  As  discussed in Section 1, there are several reasons why mitigation

is appropriate in the HWMF siting processes:

     •  It may be legally required by federal, state, or local regulations;

     •  It may be cost-effective to avoid impacts rather than paying for
       them later;

     •  It may be strategically useful in demonstrating commitment and
       credibility in the siting process.

     Because mitigation measures are very site-specific in nature, the handbook

will not attempt to cover every mitigation technique that may be appropriate

in HWMF siting.   Rather, the subsections below discuss generic types of miti-

gation actions  that are appropriate in the HWMF siting.  HWMF mitigation actions

include the  following generic types.
                          •  Facility Design Changes

                          •  Facility Operation Changes

                          •  Facility Location Changes
                                        35

-------
    FACILITY  DESIGN CHANGES

  icription

    "his  technique  includes physical changes and adjustments to the HWMF design

   construction.  Changes may include both deletions, such as a change in the

 ze of  the  facility; modifications,  such as the change in height of an incin-

 ator stack;  or additions, such as the purchase of additional land to serve as

 buffer zone  between the facility and neighboring properties.  In addition to

 tese variations,  facility changes encompass, for the purpose of our definition,

 tianges  in the vehicle design used to haul hazardous waste to a HWMF.  For

 sample, the addition of a spill containment system on a waste haul vehicle

 institutes  a  design change.

 angles

    Mitigation techniques involving  design changes are probably the most

common mitigation measures appropriate to HWMFs.  The concern in this handbook

 ' 'ith  mitigation measures that are  generally not part of typical permit

tu^oirements.   The types of design changes beyond those required by the per-

aitting  authority include, for example, the following:

    •   Additional or thicker liners  for landfill facilities;

    •   The  addition of separate trenches in landfill facilities for
       segregating  wastes;

    9   Increasing stack heights to disperse incinerator particulates;

    •   The  incorporation of large buffer zones or earth berms in the
       HWMF to minimize aesthetic and noise impacts;

    •   Changes in the HWMF access road;

    •   Emergency spill containment systems provided on-site and on haul
       trucks.

uitability

    Mitigation techniques involving  design changes may be appropriate for a

-nber of  impact issues, including the following:
                                    36

-------
    •  Traffic  impacts

    •  Noise  impacts

    •  Air pollution

    •  Ground and  surface  water pollution

    •  Aesthetic impacts

    In many cases,  design  changes can prevent or significantly reduce the above

inpacts.  In general,  these impacts have one thing in common—they are fairly

tangible  in nature.  This,  in large part, explains the effectiveness of design

changes.  On the other hand, the following impacts are more intangible in

character:

    •  Risk

    •  Community stigma impacts

    •  Property value changes

These impact issues are highly interrelated.  Because these issues are

more intangible, they  are more difficult to predict, and therefore more diffi-

cult to mitigate.   For example, the mere presence of a HWMF in an area will

likely affect  abutting property values.  Design changes may reduce or eliminate

the impacts that in part stimulate property value impacts—noise, traffic, air

pollution.  But  these  mitigation measures are unlikely to fully eliminate the

risk issue.  The fear  associated with risk is likely to be an on-going factor

influencing property values.

General Issues

    Beyond the  fact that mitigation measures in the form of design changes

may be required  as  part of  the permitting process, other design changes are

useful for the following reasons:

    •  They give the  developer or the State credibility in negotiating
       with opposition groups.
                                        37

-------
      •  While  the State has broad discretionary powers over the private
         developer,  the economic burden placed  by  the  State in  the  form
         of  excessive design change requirements bears careful  considera-
         tion.   Judgements exercised by the  State  on these impacts
         responses require a balance between costs and impact management.
         It  may be just as adequate to  deal  with some  impacts via compen-
         sation techniques and at the same time maintain the financial
         feasibility of the site.

      •  While  State sharing of this type of mitigation would potentially
         relieve the economic burden on the  private sector, there are
         other  more appropriate State incentives that  could be  used to
         deal with the issues that this mitigation technique is intended
         to  resolve.  These include site banks  and facility development
         loans  to the private sector.

  3.3 FACILITY  OPERATION CHANGES

  Description

      This technique includes a number  of actions  that prevent  or reduce impacts.

  These actions  encompass changes in the on-site operation of the HWMF, such  as

  operating hour changes, waste handling procedures; changes in  off-site  operation;

  su«-K as waste  hauling routes; and changes  in the  types of wastes allowed  in the

  fw  -ity.

  Examples

      The  most  extensive examples in this mitigation category  encompass  precau-

  tionary techniques.  These techniques  generally try to reduce  the  risk  of an

  accident  from  occurring; to enhance the capability of the  operator or the host

  community to respond to an emergency situation; or to provide  an early  warning

  system.  Examples of these techniques  include:

      • Monitoring, including groundwater and surface water;

      • Agreement to independent site  and facility inspections;
         independent monitoring; or independent environmental  audits;

      •  Purchase and use of accident or clean-up equipment,  including
          fire trucks;

      •  Qnergency response procedures;

      o  Security plans and procedures;

       •  Employee training in  security and emergency response.

See also Exhibit 5.

                                         39

-------
                           Exhibit 5

                  MONITORING:  CASE EXAMPLES
The City of Indianapolis attempted in  1978 to develop a. waste-
water sludge plan that involved disposing its sludge from
existing lagoons into nearby farms.  In order to successfully
implement its plan, the city had to agree to subsidize the
Indiana State Board of Health to monitor potential ground-
water contamination and to inspect private wells nearby.


The IT Corporation of Los Angelest California directly pro-
vides groundwater monitoring at a HWMF in Benecia, California.
These monitoring wells were negotiated with the State and cost
the IT Corporation approximately $lSOtOOO/year.


An additional variation on monitoring  arrangements was agreed
to by the Boston Edison (BE) Company and the Massachusetts
Wildlife Federation (MWF) involving radiological monitoring
at the Pilgrim nuclear power plant in  Plymouth^ Massachusetts.
When attempting to build an additional facility at the exist-
ing power plant, BE was confronted by  the MWF about the
monitoring issue,  A settlement agreement was negotiated in
1976 which included^ in addition to BE's monitoring program,
an oversight advisory committee to administer the monitoring
program.  This committee was comprised of members from 3E3
     and State agencies.
                               40

-------
    Monitoring, in particular, is widely used  as  an attempt to provide an




     warning system for potential problems  as  seen in the examples in Exhibit 5




 jjese examples include non-HWMF experiences.



    an interesting example of an operations-related technique to deal with




 public opposition for a private HWMP  facility is the use of the State to actu-



 jlly operate the facility.  The rationale behind this approach is very simple:




 the State is viewed as more likely to protect the  public interest in operating




 aBHMF.  While most States view the ownership and  operation of HWMFs as private




 sector responsibility, States are not totally foreclosing the option of operating



 privately-owned and publicly-owned HWMFs.  The  Maryland Environmental Service




 (MES), for example, has legislative authority to operate a number of environ-



 aental 'facilities.  These include municipal  wastewater treatment facilities,




 wnicipal drinking water facilities,  solid waste landfills, and hazardous waste



 '••cilities.  In an attempt to site a  hazardous  waste landfill in Rossville, MD




 ,  dispose chromium waste from its Baltimore plant, Allied Chemical proposed



 the use of the MES to operate its facility.  The HWMF site was eventually re-




 jected by the county for a number of  reasons unrelated to MES' proposed opera-



 tion of the facility.  The only other State  that has shown much interest in




 operating facilities is New York.  There appears to be widespread support for State




 operation  (and ownership) of private  HWMFs  in  New  York because of the adverse



publicity associated with privately-operated HWMFs in New York.  The only public




body that is moving quickly towards public  operation of HWMFs is the Gulf Coast




 Authority in Houston, Texas.   This  is a special district arrangement in which




taste generators are cooperating with this special authority to jointly finance




   own a HWMF.GCA will operate  the  facility after it's built.
                                       41

-------
    Other common facility operation  examples  that potentially mitigate  impact




issues include:



    •  Operating hour limitations




    a  Changes in the wastes  allowed in the HWMF




    o  Waste haul route changes.




Suitability



    Operation techniques are  applicable to a  wide variety of impact  issues as




seen by the examples.  The precautionary techniques  are particularly  suitable




for the following issues:



    •  Ground and surface water pollution




    •  Odors




    •  Risks



    State-provided  operations may  potentially mitigate all of the impact issues.




(Derating hour changes are suitable for noise  impact,  traffic impacts, and, to




a less extent, property value  effects.  Changes in allowable wastes directly




deal with the risk issue; while waste haul route changes are best suited for




the noise, traffic,  highway  maintenance, and  risk issues.




General Issues



    The issues associated with mitigation design changes, cited in Section  3.2,




also generally apply to  the  use of  operational techniques.  In many cases,



however, operation changes,  such as truck rerouting  or operating hour changes,




will allow for cheaper mitigation techniques  than design changes.



    One issue associated with operation-oriented mitigation is the question




of enforceability.   Host communities and other sources of public opposition




Bay not place much credibility in an HWMF developer's operation promises.




This distrust and enforceability issue may preclude the ability to use some of




these mitigation techniques as alternatives to design or location changes.
                                      42

-------
     Efforts by the developer to involve impartial, technically-competent,




third parties in the monitoring and oversight arrangements may be crucial in




overcoming this distrust.  This type of independent monitoring is likely to be




one of the most important impact responses in HWMF siting.  Ironically, its




popularity stems from a distrust of both private sector operation practices




and State regulation of these practices.  This contrasts with public support




in some States, notably New York, for State-operated HWMFs.  The Boston Edison/




Massachusetts Wildlife Federation example in Exhibit 5  is a good example of




third party monitoring.  The implementation requirements for third party moni-




toring, besides financing and a binding agreement, include:  determining moni-




toring issues  (e.g., groundwater, staff training, emergency containment systems);




choosing the third party  (private sector, environmental group, host community,




combination of these); and determining the frequency of monitoring.




State Provision Versus Private Developer Requirements




     When the State is both the owner and operator of a HWMF or, as in the case




of the Maryland Environmental Service  (MES), is potentially the operator of a




private facility, operational changes are clearly legitimate mitigation measures




for the State to provide-.  The more problematic case concerns the extent to




which the State should be involved in operational aspects of privately operated




HWMFs.  As in the case of the previous mitigation technique, the role of the




State as a regulator is a key issue.




     In serving its regulatory function, the State will require that certain




operating precautions be taken.  Some of these, such as groundwater monitoring,




will be mandated by RCRA requirements.  Even if the State imposes strict emer-




gency response and monitoring requirements on a private developer, the State,




as part of its regulatory function, will also serve in an oversight or monitor-




ing function.  To offset the costs associated with this function, the State
                                       43

-------
 nay require the  developer to pay inspection and monitoring fees.  Several States




 iupose a multi-purpose fee on HWMFs based on annual tonnage of waste handled




  at is used  to  support the State monitoring, inspection, and permitting program.




 As a means of stimulating further HWMF operating credibility, the State may also




 require the HWMF operator to fund third party participation in the' monitoring




 function.




     As in the previous mitigation technique, State operational requirements




 on private developers have to be exercised with some caution.  Operational




 changes can be a very effective and inexpensive way of mitigating impacts.  But




 some requirements,  such as increased security and monitoring, are not trivial.




 And unlike design changes, the costs of which may be paid once by the developer,




 operational requirements may pose recurring costs.




 3.4  FACILITY LOCATION CHANGES




 Description




     This mitigation technique is the most drastic since it deals with site




 specific impact  issues by attempting to use an alternative HWMF site.  A




variation of  this technique, when a large site is involved, is to alter the




location of the  facility within the original site.




Examples




     Until recently, careful consideration of alternative sites has not charac-




terized the HWMF siting process.  The recent passage of hazardous waste siting




legislation  in many States has altered this—increasingly the siting process




is starting with several sites.  The Delaware River Basin  Commission, New York




State, and the Now England Regional Commission have all actively supported




efforts to  identify areas suitable for HWMF development.
                                      44

-------
 Suitability




     In the face of considerable public opposition,  this  technique  may  be  the




   y feasible means for siting a new HWMF.   It may be  extremely difficult,  how-




 ever, to shift to another site for financial and  environmental  reasons.  In




 particular, if the developer or the State has not located other environmentally




 suitable sites, the process of determining these  may take several months.   Or,




 there simply may not be other sites as environmentally suitable. Environmental




 suitability will generally be the dominant criteria  when  the  facility type




 involves some type of land disposal, such as secure  landfills or deep well in-




 jection .




 General Issues




     This technique is a last resort type of approach  since it  basically in-




 volves starting the siting negotiation process over  again.  In  short, the




 shift to another location will merely raise  a whole  new set of  impact issues.




-Unless the developer or the State has developed suitable  alternative  sites,




 .5 mentioned above, this mitigation technique will also be very difficult  to




 implement.




     Facility location changes within a large site are obviously easier for




 an HHMF developer to accomodate.  Any location changes within a site, however,




 will undoubtedly involve tradeoffs among impact issues.   For  example, in order




 to respond to a larger buffer zone request,  soil  suitability  may be compromised.




 Alternatively, the facility size may have to be reduced in addition to  changing




 its location within a site.




 State Provision Versus Private Developer Requirements




     Some States require that private developers  present  alternative  sites




 to the State HWMF siting council.  This helps to  overcome the delay associated




 with the siting process, though it certainly may  not preclude public  opposition
                                        45

-------
from being generated at a new proposed site.  While  they  should  be  considered




tore in  terms of incentives to the developer rather  than  to  a  community,  such




<*ate activities as site banks are clearly methods to implement  this mitigation




 jhnique.
                                        46

-------
                                 SECTION 4




                          COMPENSATION TECHNIQUES






4.1  INTRODUCTION




     Mitigation techniques may address a number of HWMF impacts.  It's highly




unlikely/  however/  that all impacts will be (or in some cases should be)




addressed  by mitigation techniques only.  As seen in the discussion in




Section 3, there are practical and cost considerations that make mitigation




techniques difficult to apply.  This difficulty may be the result of technical




problemsr  such as the inability of a site location to be changed; planning




problems,  such as the difficulty associated with predicting the type and




magnitude  of impacts; economic reasons—it may simply be cheaper  to site now




and pay later; and uncertainty, since some risk will always remain—mitigation




is rarely  "complete" for all impact issues.




     Generally, there will be three major types of impacts that may emerge




from mitigation attempts that are potentially compensable impacts:
                             •   Unavoidable impacts




                             •   Intangible impacts



                             •   Uncertainty impacts
Unavoidable impacts may include, for example, increased traffic in the vicinity




of the HWMF or the destruction of valued open space.  Intangible impacts




refer to impacts that are difficult to measure, such as quality of life or



community stigma effects resulting from an HWMF.  Uncertainty impacts involve

-------
   tee impact issues where it is impossible to reliably predict whether an

   fact, will occur.  Rather than automatically mitigate these impacts  (which

    oe impossible to do anyway) two options are available:  contingency-

  •elated operation actions, such as monitoring and the development of emergency

  -tsponse techniques discussed in Section 3.3; or contingency funds to compen-

  sate for impacts when they do occur.

     There  are  several potential types of compensation techniques applicable

  9 HWMF siting  issues .


                         •   Monetary payments

                         •   In-kind replacement of affected
                             resources/services

                         •   Contingency funds


 ttniJbit 6 illustrates example techniques for each of these major types.  The

 eections below  describe the techniques and the issues associated with their
 4.2  MONETARY PAYMENTS

 Description

    This technique  involves  a cash payment to a potentially affected individual,

 group, or community.  Beyond  this basic definition, there are important dimen-

 sions that differentiate  the  techniques:  the method of the payment;  the timing

Of the payment;  the  recipient of the payment; , and, of course,  the provider.

Briefly, these dimensions define monetary payments as follows:


    •   Methods of  Payment

        This aspect refers to the form and basis for monetary payments.
        Payments may be  direct as in the case of a lump sum cash payment
        for impacts negotiated by a provider and recipient.  On the  other
                                      48

-------
                                  EXHIBIT   6

                       EXAMPLE COMPENSATION TECHNIQUES
            TECHNIQUE
APPROPRIATE FOR PRIVATE
    DEVELOPER USE
APPROPRIATE FOR
   STATE USE
        PAYMENTS TO COMMUNITIES:
IB property tax payments
-a payments in lieu of taxes
o gross receipt taxes on facility
    revenues
jo tipping fees
o tied impact payments
o special on-time lump sum payments
o adjustments to state-local  aid
    formulas
DIRECT MONETARY PAYMENTS:  TO
  AFFECTED INDIVIDUALS/GROUPS
o direct cash payments
o purchase of property at fair
    market value
IN-KIND REPLACEMENT/RESTORATION
  ACTIONS
Resources
o  replacement  or  restoration of
     property,  vegetation, wetlands,
     etc.
Services
o  repaving access roads to HWMF
o  provision of fixe truck for
     emergencies
o  replacement of municipal well
o  training of local police and fire
     departments
CONTINGENCY FUNDS
o  surety bond
o  liability insurance
o  emergency response fund
o  land value guarantees
o  tax base loss payments
          X
          X

          X
          X
          X
          X
           X

           X

           X

           X
           X
           X
       X
       X
                                 X

                                 X
        X

        X

        X

        X

-------
     hand,  they may be based on some surrogate measure  of  impact
     effects.   Tipping fees based on hazardous waste  amounts  and gross
     receipt taxes  both illustrate this type  of monetary payment.
     Payments,  particularly those from the States  to  a  recipient,  may
     also be attached to other monetary transfer mechanisms.   States,
     for example, may factor in payments for  HWMF  impacts  in  a
     community  into traditional State-provided local  aid mechanisms,
     such as road improvement funds.  These types  of  payments are
     commonly referred to as "earmarked" payments.

     •   Timing of  Payment

     This aspect addresses the "when" dimension of monetary payments.
     In  terms of monetary payments,  the key issue  is  often between
     one-time and continuous payments.  One-time payments  may occur
     upfront in anticipation of impact costs;  or they may  occur after
     the HWMF has been operating for a while  and its  impact costs
     are clearer.   Payments based on waste received at  a HWMF are
     examples of continuous payments.

     Because of the uncertainty of potential  HWMF  impact,  communities
     may want monetary payment schemes reviewed after a period of  time.
     A community may want a conversion provision included  in  the basic
     agreement  with the developer requiring a periodic  review to
     renegotiate the terms and conditions of  the monetary  payment
     scheme.  An example is contained in the  model binding agreement
     in  Appendix E.

     •   Recipient/Provider

     There  are  several combinations of providers and  recipients
     involving  the  State and the private developer as potential
     providers, and communities, individuals,  and  groups as recipients.
     The monetary payment transfer mechanism  will  vary  depending on
     the provider and recipient.  Exhibit 7 illustrates the appro-
     priateness of  particular mechanisms for  different  combinations
     of  provider and recipient.

Examples

     There  are  few  actual examples to date of monetary  compensation to either

communities or  individuals by States or by developers in the  siting of HWMFs.

In addition, some of the techniques listed in Exhibit 6 may  not be completely

familiar to the reader.  More detailed descriptions for some  of these terms

follow:
                                        50

-------
                        EXnJCBIT 7
        MONETARY PAYMENT TECHNIQUES APPROPRIATE FOR
DIFFERENT PROVIDERS AND RECIPIENTS INVOLVING PRIVATE HWMF3
^S. RECIPIENT
^>w
PROVIDElN^


STATE






PRIVATE
DEVELOPER





COMMUNITIES

HOST
• Tied impact
payments
• Lump sum
payments
• state-local aid
adjustments
• Property tax
payments
• Payments in
lieu of taxes
• Facility taxes

• Tipping fees
• Tied impact
payments
• Lump sum
payments
ABUTTING
• Tied impact
payments
• Lump sum
payments
• State-local aid
adjustments
• Tied impact
payments
• Lump sum
payments
• Tipping fees







INDIVIDUALS

• Tied impact
payments
• Lump sum
payments


• Tied impact
payments
• Lump sum
payments








GROUPS

• Tied impact
payments
• Lump sum
payments


• Tied impact
payments
• Lump sum
payments








-------
    •  Property  Tax Payments!  "In terms of compensation,  this technique
       means paying taxes above  that normally required for property of
       comparable  valueJor accelerating tax payments.

    •  Tipping Fees:   The.se are  fees that are levied on the facility
       based on  each unit of waste (truckload,  pound, cubic yard,
       gallon) accepted at the facility.   They provide an on-going
       source of compensation.

    •  Tied Impact Payments:  These compensation payments are tied to
       certain impact issues.  States may "earmark" funds to communi-
       ties so that they may only be used for certain activities.
       Private developers can  also earmark funds to communities through
       their agreements with communities.

    •  Adjustments to State-local Aid Formulas;   States have a variety
       of specific categorized assistance programs to funnel aid to
       communities.   These can be adjusted and-used as a transfer
       mechanism for monetary  payments.   In addition to these specific
       programs, many States also provide general revenues to localities
       based on  population,  local tax base assessments, etc.

    •  Purchase  of Property at Fair Market Value;  This is a pre-project
       payment to  a property owner for the pre-project fair market value
       of his property.   This  is a method for compensating property
       owners who  fear property  value impacts and wish to sell to  avoid
       losses.   This method contrasts with the  land value guarantee pay-
       ments listed in Exhibit 6  and discussed  below.

    While there  are few examples of the above techniques  to date,  two States

have passed legislation authorizing tipping fees  as compensation to host commu-

nities.  Kentucky and Connecticut require  the developer to pay the  host commu-

nity an amount based on the waste volume or revenues of the developer.   For

example, the Kentucky legislation requires that  HWMF developers pay 2% of their

gross receipts to the host county's General Fund.  Connecticut's formula is

as follows:
      •  $.OS/gallon  of  hazardous waste received on a quarterly basis;

      •  Payment  in accordance  with the following table,  whichever is
         greater:

                                                     Payment as % of
      Quarterly Gross Receipts                       Gross Receipts
       Over       Not  Exceeding
         0         $1,250,000                              10%

    $1,250,000     $2,500,000                               5%

    $2,500,000                                              2»j%
                                       52

-------
    Compensation in the  form of  monetary payments to communities to offset




the costs of specific impacts is  extensively used in the development of energy




 eilities.  These compensable impacts are primarily related to socioeconomic




inpacts.  A good example  is  the Washington Public Power Supply System's (WPPSS)




$12 million compensation  for public facility and public service impacts pro-




jected to occur from its  nuclear  power plant construction activities.  The




SPPSS negotiated agreements  for this amount in the mid 1970s with 44 different




taxing districts.  The  State of Washington's Energy Facility Site Evaluation




Council served as a mediator during the negotiations.




Suitability



    Monetary payments  are generally best suited to measurable impacts in which




costs are definable.  For example, if a community will need two additional




local health agents to  monitor the HWMF, these costs are easily calculated




and  can be compensated.  HWMF impacts on community image and risk are not as




easily costed and  less  suitable for specific monetary payments.  The Connecticut




jnd  Kentucky waste-based tipping fees, however, illustrate the suitability of




nonetary payments  for  dealing with these intangible impact issues.  Essentially




these approaches recognize the great difficulty in defining impacts and costs.




Thus, they simply  imply that impacts are related to the amount of waste being




handled at a HWMF  and  use a waste-based formula.  The host community then deals




trith the  issue  of  distributing these revenues to compensate tangible and intan-




gible impacts.



    On-going payments, such as tipping fees, will also obviously produce  less




revenue  for  a community in landfill situations  (which have a  limited lifespan)




than incinerators, processing, or  transfer facilities.  However,  if  one  assumes




that risk is related to years  of operation,  then  continuing payments do not




"overcompensate" as such.
                                        53

-------
aneral Issues

   There are  a  number  of general issues associated with the use  of  monetary

 ments  that States should consider whether they provide them directly or

require the  private  sector to use them:

   • Monetary  payments to an affected individual or community
      provide  the recipient with a great deal of flexibility.
      They allow the recipient to decide how to deal with the
      costs  suffered from the HWMF.  In this sense they are
      easier  to administer than other forms of compensation.

   • While giving the recipient flexibility, monetary payments
      are  also  more susceptible to accusations of buying off the
      recipient.  This is particularly possible if there is not
      a clear connection between the impact cost, the payment,
      and  the disbursement of the payment to offset the impact
      cost.

    In addition to these issues, there are important considerations in using

different types of monetary payments:

    v  One-time Versus  Continuing  Costs;   Certain  payments,  such
       as tied  impact payments  and lump  sum payments may be  one-
       time in  nature,  while  tipping fees  and  property  tax pay-
       ments  represent  recurring costs.  In looking at  the  economic
       burden placed on a private  sector developer, States  should
       examine  the present value of the  total  impact  response packages
       being  required  of a developer.   Similarly,  if  the State is
       providing a package of impact responses,  present value analysis
       as  illustrated  in Section 2 should  be  done. This will allow
       the economic  burden of packages to  be  compared between each
       other  and between providers.

     ,   Impact Responsiveness;  The tipping fee and other recurring
       payment  schemes are more responsive to unpredicted  impacts
        that may occur  after a HWMF is  sited than the one-time up-
        front  monetary  payments.

     •   Equity-   Monetary payments directly provided to a community
        n^y not  filter  down to residents affected most by HWMF impacts.
        In  that  sense,  tied impact payments are likely to be more
        equitable.   One-time, up-front payments tend to compensate
        existing residents rather than migrants.   Recurring payment
        schemes, particularly ones that are adjustable, are more
        equitable for existing residents and migrants to a community.

     •  Administrative Burden;   Tipping  fees and facility taxes are
        administratively the  easiest to negotiate,  calculate,  and
        collect of all the payment  schemes.  The other  schemes are
                                     54

-------
       likely to be more responsive to actual impact costs, but
       require often difficult calculations and distribution schemes.

    The above comments clearly indicate the tradeoffs between the difficult

jnetary approaches.  In order to deal with these issues, a combination or

a mix of monetary payments is a useful approach for States to consider in

developing compensation schemes.  See Exhibit  8 , for example.

State Provision Versus Private Developer Requirements

    1h& above considerations are useful in selecting the form and type of

Monetary compensation.  One of the  first and most important issues that a state

vill want to address, however, is the provider question.  Some general consid-

erations are provided below:
              Should  the  State  Be Involved  in  Directly

                    Providing  Monetary  Payments?
The  following  issues  are  relevant  to  this  questions

    •  In private  HWMF situations, exclusive  State provision
       of monetary payments  may minimize  the  possiblity  or
       perception  of illegal payoffs between  the  private
       developer and a community.  If the State supplements
       developer-provided  compensation with monetary  payments,
       it will probably  help to legitimize the concept of com-
       pensation.

    •  Exclusive State provision  of  monetary  payments may also
       be viewed either  as:

        - An  effective incentive  to  both  the  developer
          and the  community  to aid in the siting  of
          a HWMF;

        - An unnecessary or  undesirable subsidy of the private
          sector;

        - Interferring with  the competiveness among HWMFs.

       Obviously,  these  contrasting  viewpoints will have to be
       resolved  on a state-by-State  basis.
                                      55

-------
                                     OTC THE BiTJNU    A PRIVATE HWMP
                                           (Hypothetical Example)
       RECIPIENT/ISSUE
                                           DEVELOPER PROVIDED
STATE PROVIDED
TO HOST COMMUNITY
    o     quality of life impacts
                                      tipping fee of 5$/gallon of disposal
                                        waste—renegotiable every 2 years
o     facility monitoring
                                          annual tied impact payment based
                                            on actual costs incurred
          access road maintenance
                                                                               annual adjustment on State-local
                                                                                 highway aid formula
 TO NEIGHBORING COMMUNITY

    o     quality of life impacts
                                                                               annual  lump sum payment
 TO RESIDENTS ABUTTING FACILITY

    o     property value impacts
          quality of life
                                                                               one-time lump sum payment of
                                                                                 $5,000/propery owner

-------
   •  Supplementing  the  above,  any State  provision  of  compensation
      will help  to relieve some of the economic  burden on  the
      private  developer.   This  may be critical in the  successful
      siting of  a facility.

   •  Any state  provision of monetary payments may  help to
      resolve  differences between communities and the  developer
      and thus help  to shorten  the siting process.

   •  In those States with the  ability to override  local
      zoning in  HWMF siting, state provision of  monetary payments
      may be a political necessity to assuage community op-
      position and  to minimize  community  attempts to challenge
      the constitutionality of  the override provisions.

   o  Conversely, State  compensation payments may be the only
      way in those  States with  strong home rule  laws that  States
      can get  HWMFs  sited.

   Most of the above comments justify State provision of monetary payments.

ttere are, however, serious issues surrounding State  monetary  payments  and

these include:

    •  Do States have the  legal authority to provide monetary
       compensation in situations where the facility is privately
       owned?  We do not believe that this is a problem at all
       for States.   See Appendix C.

    9  State monetary payments may set a political precedent
       for State compensation payments for other public and
       private facilities.   This concern has been voiced by a
       number of States in a series of interviews with  State hazard-
       ous waste officials.  One way  to avoid this possibility
       is through the use  of special  language in compensation
       legislation that deals with the extraordinary circumstances
       surrounding 1IWMF siting.

    •  State monetary payments  raises the question of  state
       liability for problems that occur  later with the  facility.
       This appears to be  a  moot  issue with  respect to private
       HWMFs.  See Appendix  F.

    •  State compensation  monetary payments  may  undermine  the
       credibility of  the  State  regulating  role  in  the sitinq
       and operational review of  HWMFs.   This is a very compelling
       argument  and one  that is of  concern  to many  State hazardous
       waste agencies.  The  fact  that States would be  providing
       compensation  to the communities rather than  to  the  developers
       minimizes, however, potential  conflict of interest  in State
                                     57

-------
        roles.   There is also precedent for State  aid to and regula-
        tion of a particular party.   For example,  States subsidize
        municipal wastewater treatment plants and  the same State
        agencies regulate them.  States also provide a number of
        subsidies, such as economic development loans to private
        industry, and also regulate their activities.  One pre-
        caution that States could implement to minimize conflict of
        interest charges is to have a state agency separate from
        the regulating agency be responsible for the compensation'
        activities.

        State monetary payments, as well as those  required of private
        developers, may tend to promote the siting of HWMFs in
        poorer communities.  This in fact may occur but whether it
        represents a social inequity that is of concern to the
        State is for a particular State to decide.

        Many States are constitutionally prohibited in making long-
        term monetary or special privilege commitments.  Thus, annual
        payments would have to be legislatively enacted each year.

        State provision of monetary payment may affect the dis-
        tribution of hazardous waste disposal costs.  As discussed
        below, the method used by the State to finance compensation
        will affect the distribution of costs.  One of the concerns
        here is that State compensation funded out of general
        funds will act as a subsidy to out-of-state hazardous waste
        generators who dispose in the HWMF associated with the
        compensation.  See Appendix B.
                Should the State Require Private HWMF

               Developers to Provide Monetary Payments
     As mentioned,  both Connecticut and Kentucky have recently passed

legislation requiring private HWMF developers to provide compensation to

communities on a formularized basis.  Massachusetts has also passed legis-

lation requiring developer provided compensation, but has left the amount

to be negotiated between the developer and the community.  There are

several concerns with this issue that States should consider before

developing developer provided requirements.  First, on the positive side:

      »   State requirements for developer  monetary payments will
         tend to legitimize the compensation  concept.  Specific
         state requirements in the amount  of  the payments, such
         as those mandated in Connecticut  and Kentucky, would
         tend to mute the bribery and illegal payoff issues.
                                      58

-------
     0  Jtate  requirements are also  likely to standardize the
        negotiation process and therefore provide some "ground
        -.ales" to help speed up the  siting process.

     jevural States and some of the  private HWMF developers are concerned

  but Stdte requirements.   The principal .issues of concern are the following:

     •  Specific monetary payment requirements may prove to be
        an economic burden to developers.  This may make a site
        financially unfeasible or it may make a site more com-
        petitive with other sites.  This may further exacerbate
        illegal dumping practices or stimulate disposal to
        competing  firms.

     •  should monetary payment requirements also be made retro-
        active to existing HWMFs? This  may be difficult to
        legally do.  If they are not, however, existing sites
        will have a competitive advantage over new sites.

     •  Specific monetary payment requirements may make it dif-
        dicult for HWMFs to obtain private capital financing.
        Specific formula approaches  are, in effect, on-going
        liens on a developer's HWMF  revenues.  This may inhibit
        the developer's ability to obtain private financing.


     IN-KIND REPLACEMENT/KESTORATION ACTIONS

Description

     Instead of providing a monetary payment to a community or an affected

party,  the provider in this technique offsets impact costs by replacing the

affected  resource or service.

Examples

      This technique is  widely used in the  siting of energy facilities.  The

Tennessee Valley Authority  (TVA) uses this technique in the siting of its

nuclear and coal-fired  power plants.  For  example, in the mid 70's TVA nego-

tiated a very complex compensation agreement with several communities, the

State of Tennessee, and the Nuclear Regulatory Commission for the construction

of H nuclear  facility in  Hartsville, Tennessee.  Among the things agreed to
                                     .59

-------
   T/A was to construct necessary traffic improvements and education facilities.
                                    *
 n addition, they agreed to provide TVA expertise to supplement local officials

    ,-,al with housing and planning impact issues.

     Potential examples in HWMF siting include the following:

     Resources

     •  Replacement of restoration of property, vegetation, wetlands,
        valued open space affected by the HWMF


     Services

     •  Repaving of access roads to a HWMF

     •  Reconstruction of transportation route to a HWMF

     •  Replacement of municipal water supply wells

     •  Provision of fire truck to the host community for emergencies

     o  Training of local police and fire personnel in hazardous waste
        emergency response

Suitability

     This technique is most appropriate for those impact issues that a developer

or the State is able to directly provide an in-kind response.  For a private

developer, this ability may be limited.  The fire truck response is a good

example of what a developer can provide.  A variation on this technique is the

joint use of a service or facility, such as a fire truck.  Wes-Con, for example,

in Idaho has made available its fire truck to the host community for dealing

with off-site hazardous waste emergencies.

     In general, the HWMF developer will be most able to provide limited

nonconstruction-related items, such as fire trucks, training, and property.

The State, on the other hand is better able to provide items involving con-


struction.
                                         60

-------
      In-kind replacement actions are less able to deal with intangible issues,

      as quality of life and community stigma problems.  The mere presence of

 ,,e H'}JMF in a community may raise the community image problem.  There is very

little  a developer can do to directly compensate for this issue using in-kind

replacements.

General Issues

      The major advantage of using in-kind compensation techniques  is their

ability to directly deal with specific impact issues.  Unlike monetary pay-

ments to communities that may never reach impacted  individuals, these tech-

niques  directly offset costs and impacts associated with a HWMF.   Secondly,

they  are particularly appropriate in muting bribery or payoff criticisms

associated with the use of monetary compensation.   This is a major advantage

in overcoming public opposition to a HWMF.

      In terms of other issues, there are several:

      •   The developer or the State may not be able  to provide  some
         of the in-kind services and resources shown in the examples;
         it may be a lot easier to simply pay the host community money.

      •   The host community may not want the provider involved in re-
         placing resources or services} communities  may wish to handle
         these functions by-themselves.

      «   Similarly, an affected resident may also rather receive straight
         monetary payments rather than some comparably valued resource.

      •   A key concern is the issue of one-tiae replacement versus  on-going
         replacement.  Some of the in-kind services  and resources lend
         themselves to one-time compensation, such as the replacement of
         land needed for the HWMF.  Other service impacts of the HWMF may
         be recurring.  If the compensation agreement reached with
         the community covers these types of impacts, then the compen-
         sation provider may be involved in long-term on-going cost
         commitments.
                                       61

-------
  ate Pr -vision Versus Private Sector Requirement

     Sta^e-provided in-kind compensation measures are  appropriate obviously

     tat»-owned facilities.  The extent to which the State wants to provide

  hem in private sector HWMF situations will depend on  the following types of

  onside rations.

     •  Whether the State is interested in using State-provided
        compensation as a means of subsidizing the private HWMF
        developer;

     •  whether the State is in a better position to provide the
        in-kind compensation more cheaply or more quickly than the
        private sector;

     •  Whether the Stae provision will help to resolve stumbling
        blocks in the negotiation between the developing community
        and then speed up the siting process;

     •  whether the State in-kind compensation is viewed as a poli-
        tical precedent problem in terms of compensating other
        communities for nuisance facilities or in terms of subsi-
        dizing other private sector development activities;

     •  The extent to which out-of-state wastes are accepted at
        the HWMF and whether the State is willing to use compen-
        sation in light of its likely subsidy of out-of-state
        wastes.

     In terms of requiring the private sector to directly provide in-kind

services,  the concerns raised in the discussion of monetary payments apply

here as well.  The principal concern is the economic burden placed on the

developer  and, in turn, the impact of this burden on the developer's ability

to obtain  private financing for the facility.

     In general, the State requirements on developers  for in-kind services

should be  done with great care.  The developer is usually more able to provide

monetary  compensation rather than specific services.   One State, Massachusetts,

has  developed compensation legislation that allows the community and the

developer to negotiate which in-kind services the developer will provide.

The  state, through a hazardous waste siting council, reviews the developer-

•rom-vanity agreement and may recommend additional adjustments.
                                       62

-------
 4  CONTINGENCY FUNDS:  UNEXPECTED EVENTS
    Thi.;  technique involves a promise to pay for impact issues that cannot be
 liably predicted or that cannot be mitigated.  As discussed previously,  risk
 '11 -alv -iys remain in a HWMF area.
    Thi^  compensation technique is closely related to the mitigation activities,
 ch as monitoring and  emergency response activities , that attempt to prevent or
 educe  impacts from occurring.  Recognizing that operational activities are not
 ikely  ^o completely minimize risk, this technique ensures that contingency
 vments  would be forthcoming.  Contingency funds provide communities with the
issurance that should an adverse event occur,  the resources are available to
;ompensate for adverse  impacts.
     This section discusses techniques appropriate  for unexpected events.  For
the purposes  of  this handbook, contingency arrangements for property value im-
   ts are discussed separately in the next section because of  the paramount
importance of this issue in HWMF siting.
Examples  and  Suitability
     Contingency funds can vary along several parameters:   funding  procedures,
events covered,  and impacts covered.  Funding for contingency funds can come
from the  State or the private sector,  additionally, there is a time variation
-one-time,  as needed, continuing.  For example, the State can appropriate one
lump sum from its general  fund or appropriate an incremental amount annually.
Alternatively, States could have bond issues on a one-time only or periodic
basis.   Finally, they  could tax hazardous waste generators, transporters, or
 facility operators.
     The facility  owner could also make a lump sum payment prior to opening  the
 facility; purchase additional liability insurance beyond the  minimum permit
                                         63

-------
   icements; pay into a State-operated fund on a waste processed basis; reim-




   jf the fund on a dollar-for-dollar basis for expenditures related to the



   ?• or a combination of the above.




    Several States—Michigan, New Jersey, Wisconsin,  Delaware—require HWMFs




   pny  a certain amount per gallon of waste handled into contingency funds.




   sas, on the other hand, requires HWMFs to make one  lump  sum up-front payment.



   a.- requires a surety bond and a tonnage fee.  Other States, like New Jersey,




   rer the fee once the fund reaches a certain level, but requires any  HWMFs  that




  ise a problem to reimburse the fund.



    The funds can cover a range of possible events and incidents:




    •   transportation-related spills, or accidents



    •   incidents at the facility  (explosions, accidental releases)




    •   failure of mitigation measures  (lining ruptures)




    •   monitoring



    •   post closure accidents



    Finally, the funds can address a number of potential impacts to  either




 idividuals, corporations, or communities.  These could include




     •  property damages



     •  health  damages



     •  natural resource  damages



     •  economic  damages  (such as  loss  of work, loss of business)




     •  temporary or permanent relocation costs



     *  costs of incident management  and control




     •   costs of long-term monitoring



     New Jersey,  for example, uses this fund to provide compensation to individ-




aaJs,  communities,  and businesses for real  and personal property damages, clean-




up -osts,  health bills, lost income due to ill health, and loss of business.
                                        64

-------
 Other State generally authorize more limited use of the funds.



 General Issues




      The major advantage of contingency funds is that they deal with risk.




 It is impossible to accurately predict all possible adverse impacts in advance




 of HWMF operation.  Furthermore, no mitigation measure is 100% effective:




 accidents will occur and control technologies fail.  Contingency funds address




 these problems and provide a means to compensate for the impact and the long-




 term adverse effects of incidents.




      However, there are certain problems associated with the funds.  The most




 serious is, obviously, cost.  Tipping fees could affect the HWMF's continuing




 economic viability, while lump sum up-front payments could impact the feasi-




 bility of constructing the HWMF in the first place.   Furthermore,  there is the




 opportunity cost of tying  up money in a contingency fund.   If the fund is




 supported by State money, this money is lost to other State programs.   If the




 HWMF provides the contingency money,  its developer  is prevented from spending




 _he funds on other compensation measures or other economic  ventures.   Clearly,




 the more types of incidents and the more adverse impacts  the  fund  covers,  the




 greater the potential expenses and replenishment frequency.




      An additional issue related to the design  of such a  fund  is disbursement.




 Such funds require a mechanism for determining  when  the situation  warrants




 expenditures from the fund, and what those expenditures should  be.  This  is




 a potential area for State involvement.




 State Provision Versus Private Sector Requirement




      State requirement on the private sector  for surety bonds and  liability




 insurance  are  well-established and will be necessary for all HWMFs.  RCRA




mandates that  operators put up surety bonds and obtain liability insurance.
                                       65

-------
Surety  bonds,  to ensure coverage of closure costs, can be  canceled, however,




;and  liability  insurance mandated by the Federal government of  $1 million/



   urrence/firm and $2 million annual aggregate might be exceeded in the event



of a major catastrophe.   States, therefore, must  insure that cancellation




provisions in  a surety bond  contain a 90 day notice  provision.



     States can also supplement the private sector's contingency fund coverage



with its own emergency response fund as discussed above.   There is  some precedent




for  State and  public sector  participation in this area—catastrophic health in-



surance and crime victim  compensation are two  examples. The key dilemma faced




by States is the cost burden placed on the HWMF developer  versus incident and




impact  coverage desired.






4.5  CONTINGENCY FUNDS:   PROPERTY  VALUE IMPACTS




Description



     While empirical evidence is fragmentary and  often conflicting, a nuisance



 facility, such as a HWMF, is likely to stimulate  some degree of property value



loss in a certain area around a HWMF.  Such impacts  are also possible,  to a



lesser extent, along routes  heavily travelled  by  waste haul vehicles.   Changes



in property values reflect many of the other impacts raised in this handbook--




noise,  traffic, risk, odors. As these first order  impacts are unlikely to  be



completely mitigated, some types of contingency  fund is likely to  be a  common




compensation need in HWMF siting.



      A corollary impact  to property value  effects suffered by  individuals and



corporations is the tax  base loss  resulting in a  community.  Decreased  property




values mean lower tax receipts and revenues  for  a community.   This section



discusses alternative ways for compensating property value and tax base losses.
                                      66

-------
        Compensation Program Considerations^

     Before discussing alternatives, 'two important questions require some con-
                                   <
«•-
-------
price  figures provides perverse .incentives to local  homeowners:  the policy

might  contribute  to community disruption.

     Besides these  valuation considerations, there is the  key issue of eligi-

bility.   Is everyone in the host community eligible?  Certainly, this would

prove  to be an unmanageable compensation situation.   Property value compensa-

tion techniques require limits on eligibility—both  spatially and temporally.

Alternatives and  Issues

     There are two  basic means for dealing with property value losses:  purchase

of the affected property at a fair market value plus compensation price; or

some method of cash compensation to reflect the appraised  property value loss.

The first alternative involves either  the HWMF developer or the  State in the

property acquisition business.   This is  a major drawback and because of the

numerous issues involved in such an approach it is not considered in this hand-

book.

     There are several issues and variations associated with the second alter-

  ative:   percent of loss to be compensated; trigger  mechanism? time limit on

compensation period; eligibility of new  versus existing property owners.  Each

of these issues is  discussed:

     •  amount of compensation;   A full  100% compensation  suffers from
         economic efficiency problems.  In particular, if property owners
         were assured of 100% compensation, they would have no  incentive
         to search for the  highest-bidding customer for their home.  Some
         fixed percent, such as 80%, may  have to be considered.

     •  Trigger Mechanism; Should compensation be triggered by  a decision
         to sell? If a property  owner  in the eligible area decides  to sell
         his or her  home, the developer or the State  could  pay  a  fixed
         percent of  the difference between the pre-project  assessed  fair
         market value of the home, and  the subsequent sales price, adjusted
         for property inflation.   Should  the property owner decided  not to
         sell, compensation is still available.  In this case,  the provider
         would pay a fixed  percent of the difference  between the  pre-project
         appraised fair market value of the home,  and a second  adjusted
         appraised value taken after the  facility  is  in operation.
                                          68

-------
      •  Compensation Period;  Compensation should probably be paid only
         once, after the  facility is in operation, but before a certain
         _set  period has elapsed.  The single compensation payment re-
         duces administrative  load and avoids double-counting.  The
         requirement that compensation payments be delayed after the
         facility is in operation would avoid the payment of short-term'
         property value losses generated by construction impacts. Finally,
         a time  limit on  compensation claims (e.g., 5 years) would reduce
         administrative load and minimize problems of calculating land
         inflation over long periods.

      •  Eligible Property  Owners;  Che approach would compensate only
         those individuals  who owned impacted property prior to the
         introduction of  the HWMF.  Once a facility is introduced into
         an  area, property  values will adjust to reflect the impact of
         that facility; thus,  individuals who purchase homes in the
         impacted area after the facility is introduced will already
         have been implicitly  compensated by the .market through the
         reduction in the price they must pay for that home.  In short,
         if  an individual with full knowledge chooses to purchase a
         home next to a HWMF,  the State or a HWMF developer should
         probably not be  obligated to compensate that individual for
         having  made that choice.  Eligibility will also require
         definition  in terms of spatial considerations.  Alternative
         criteria, all imperfect in some respect,  would include:
         geography,  topography, arbitrary distance, transportation
         routes, or  some  negotiated test of "interest".

Tax  Base Loss Impacts

      Accompanying individual  property value losses are tax base losses to a

community.  The approach that is used to compensate a community for the loss

must be keyed to some of the  issues raised in property value  compensations,

namely:  impact area and compensation period.   Before a community can attri-

bute tax base losses to  a  HWMF, an eligible impact area and an  eligible period

for  compensation would require definition.  The tax base loss issue,  however,

is also complicated by offsetting tax base gains  in a community due to a HWMF.

Tax  base gains?  It is not improbable that the presence of a  HWMF would stim-

ulate industry  to locate in a community; or minimize the loss of some existing

industries.  Attributing tax  base losses to HWMFs appears to  be highly question-

able.  Consequently,  contingency arrangements do  not seem to  be a high priority.

Rather, such impacts if  they  do occur, would probably be best handled in a lump

sum  type of cash payment.
                                        69

-------
 State Provision Versus Private Sector Requirement




      There is considerable experience with after-the-fact land value compensa-



 tion in  facility siting,  particularly transportation facilities.  In these




 situations,  the Federal and State governments have provided compensation without




 resorting  to owner-initiated court suits.  There is also a substantial body of



 case law for property value compensation due to nuisances. (See, for example,




 D.  Hagman  and D.  Miscyznski, Windfalls for Wipeouts, American Society of Plan-



 ning Officials, 1978)   The research for this handbook,  however,  has  uncovered



 very limited experience with property value compensation in the  fora of pre-



 project  contingency arrangements.  During considerations for moving  the capital



 of  Alaska  from Juneau, legislation was passed in the Alaska legislature authori-



 zing the State to purchase property at a fixed percentage of present value if




 property owners were not  able  to sell their houses within a certain  period of



 time.  In  Montgomery County, Maryland, the developer of the White  Flint Mall




 offered to abutting property owners a property value compensation  guarantee.



 The developer hired an appraiser to appraise the pre-Mall values of  the ap-




 proximately  ten properties.  According to the agreement signed by  the developer



 and the land owners,  if property owners wnated to sell  their property within 5




 years,  and the price offered fell below the pre-project appraised  value, then



 the developer would:  1) pay the difference;  or 2)  buy the property.  It is un-



 likely that  the compensation guarantee will have to be  exercised.  Property



values have,  in fact,  increased due to the popularity of the Mall.




      While the Mall example  is not entirely analogous to HWMT siting, one



lesson learned from the Mall experience is useful:  property value compensa-




tion guarantees are import*nt chips in facility siting negotiations.   Proper-



ty  value concerns  are  likely to be paramount issues  in HWMF siting.  Some pro-




visions  appear justifiable.  While States can and have resorted to after-the-fact
                                        70

-------
property value compensation, the constitutional difficulties faced in many States




co? earning long-term commitments appears to preclude a lead role for the States




in  directly providing through State financing a contingency fund.  Consequently,




the private developer, at least from a logistical viewpoint, is best suited




to  provide for contingency arrangements.  The economic burden is likely to be



minimal, particularly if the compensation period is defined as a short-term




period as suggested above.  State or host community involvement, however, is



warranted for defining impact areas and providing oversight in the appraisal




process.
                                        71

-------
                                    SECTION 5




                              INCENTIVE TECHNIQUES








  .1   INTRODUCTION




      Unlike mitigation or compensation techniques which attempt to address




 losts or impacts incurred in the siting of a HWMF, incentives may not be




 specifically directed at HWMF impacts.  Incentives represent additional pay-




 tents in the siting process.  They attempt to provide benefits above and beyond




 the  impacts associated with a HWMF.  As mentioned in Section 1, the rationale




 Eor  incentives is primarily goodwill and strategic in nature.  There is obvi-




 ously a fine definitional line between compensation and incentives.  Impact-




 related techniques refer to measure that address specific HWMF impact issues,




 Put  are in addition to whatever compensation or mitigation techniques used to




 address the impact issues.  The ability to define incentives as impact-related




 techniques depends on site specific impacts as seen in Exhibit 9 .   The




 examples shown in Exhibit 9 are representative examples.  There are undoubtedly




 additional variations on donation recipients or on the types of additional




public services/amenities that could be provided in a particular community.




      There has been a moderate number of examples involving the use or offering




of incentives in the siting of HWMFs.  For example, Wes-Con, Inc. used several




incentives in the siting and operation of a hazardous waste disposal facility




 in an abandoned missile silo complex in Grandview, Idaho.  The site is over




I0v>  acres in size.  Wes-Con offered several incentives to the local area, including:
                                        72

-------
     EXHIBIT 9




EXAMPLE INCENTIVES
TYPE
Provision of jobs
to local area
residents
Free Disposal or
preferential rates
to local business
and the community
Additional public
services and
amenities
o fire truck
•3 ambulance
parks ,
recreation areas
o road improvements
o etc.
Additional risk manage-
ment activities:
o independent
monitoring and
inspections
o emergency res-
ponse procedure
Additional monetary
payments to the host
community
o additional taxes
o additional tipping
fees
GENERALLY
UNRELATED
TO
HWMF
X

'
X












.












MAY BE
RELATED OR.
UNRELATED TO
HWMF IMPACTS







X









X











APPROPRIATE
FOR PRIVATE
PROVISION
X


X



X









X





x





APPROPRIATE
FOR
STATE PROVISION







X









X





x





            73

-------
EXHIBIT 9  (Cont'd)




EXAMPLE INCENTIVES
TYPE
inup of existing
iandonad hazardous
ste facility
tions to local
ari table organi-
tions
an tees or backing
municipal bonds
jhase 3f municipal
l>nds at rates more
>"orable to the
, Lity than pre-
.ing market rates
GENERALLY
UNRELATED
TO
HWMF


X









MAY BE
BELATED OK
UNRELATED TO
HWMF IMPACTS
X











APPROPRIATE
FOR PRIVATE
PROVISION
X

X


X

X




APPROPRIATE
FOR
STATE PROVISION
X




X

X




              74

-------
use of  Wes-Con's firefighting equipment, (the area is rural and has no existing
equipment);  the use of its first aid equipment; and the use of its well water
   local cattlemen.  The county and the area cattlemen, however, have not used
any cf  these offers since the Grandview site began, operations in 1973.
      We s-Con also received permission to site  a hazardous waste disposal faci-
lity  in 1977 in a nearby missile silo complex  in Bruneau, Idaho.  It has not
yet developed this site as a HWMF and is contemplating alternative uses for
the site.  The success in getting approval for the Bruneau site, however, is
attributable, in part, to Wes-Con's successful use of incentives at its Grand-
view  site.  During the operation of its Grandview site, Wes-Con has made dona-
tions to  local charities and recreation events (total * $15,000) and has pro-
vided free pesticide disposal service to area  farmers.  The free dispoal service
is estimated to be equivalent to $5,000/year.  In addition, Wes-Con has made an
effort to hire its employees locally; provided emergency disposal  service during
  atural disasters; and volunteered the use of  its heavy equipment  to local resi-
dents .
      The  use of  incentives  to promote goodwill has also been  evident in other
HWMF  sites.  Chemical Waste Management, Inc.,  which  operates  a  disposal facility
in  Livingston, Alabama,  donated an ambulance to  the  community.  Kansas Industrial
Environmental  Services  (KIES) which operates a land  disposal  facility  for haz-
ardous wastes  in Furley, Kansas, supplements local snow plowing efforts with
its own  equipment.
      There  have  also been offers of  incentives in unsuccessful  HWMF siting
situations.   Allied Chemical,  Inc.  for example,  sought to locate  a secure land-
fill in  nearby Rossville, Maryland to dispose chromium waste  from its manufac-
turing  operations in Baltimore.  The siting attempt, which generated consider-
able opposition and eventual rejection, was marked by Allied's offer to donate
                                        75

-------
0 acres  of its 60 acre site for use as a local park.

5.2  SUITABILITY

     l.i  HWMF siting situations when the provider has  responsively addressed

impact, issues, incentives nay be.appropriate given the following considerations:

     «   As a means for showing commitment in addressing Impact  issues,
         the use of incentives may be appropriate.  Thus,  if the loss
         of open space for the HKMP is an issue, then  providing  parkland
         above and beyond what was lost would be an incentive that might
         help to overcome opposition.

     9   The use of incentives that are unrelated to impact issues has
         to be done carefully. These types of incentives should be
         based on a careful assessment of needs in a community.  An
         offer to donate  land  for a park may have no strategic or good-
         will clout if the area has adeguate recreation resources.  An
         offer to accept  local industry wastes for free, however, may
         be done for little cost to the developer and  have tremendous
         political and economic value in a community where local indus-
         try is having a  difficult or expensive tine disposing of its
         hazardous waste. Similarly, a rural area with few public
         amenities or  services is more apt to positively respond to
         such incentives  as donated ambulances, fire trucks, or  recrea-
         tion facilities.

     •   The Wes-Con,  Inc. example also illustrates the value of using
         incentives during the operation of a facility.  The goodwill
         that accounts to these incentives is an important factor in
         keeping a HWMF  in business.
      The most  important consideration  in the use of incentives  is  their poten-

tial  to backfire, i.e., to be counterproductive in addressing public  concerns

in  the siting  of HWMFs.  Research conducted for this handbook with HWMF firms

revealed a  sensitivity to this issue.  Some State hazardous waste  officials

also  view incentives that are totally  unrelated to HWMF impact  issues as  border-

ing on bribery.   In short, incentives  that are non-responsive to impact issues

that  remain unaddressed can be potentially dangerous.  They can jeopardize or

nullify well-intentioned efforts to deal with public concerns.  There is  a

grea-er likelihood that incentives will be accepted if the community  or poten-

tial  recipient raises the notion first.
                                        76

-------
     While the backfiring issue is  a clear-cut risk associated with the use

of incentives, incentive costs are-variable.  Unlike mitigation or compensation,

  ere  Htate or local regulations or the severity of the impact may dictate the

amount and form of compensation, the use of incentives operates more on a free

auurket basis.  The HWMF developer or the State has considerable flexibility

in using incentives.  A provider must essentially make a judgement on what the

siting market requires in terms of  the type and amount of incentive.  How much

should the provider pay in incentives?  It is not possible to answer that ques-

tion here, but two factors should be considered:

     •  Long term monetary payments to the community (tied to the amount
         of waste  being disposed) that are above and beyond compensation
         requirements are relatively more expensive than one-time or ad-
         hoc incentives such as the  donation of public amenities.

     •  In-kind services will generally be the least expensive incen-
         tives  (and may have just as much strategic value).  These
         include free disposal service to local industries and the
         sharing of HWMF facilities  and equipment (e.g.,  fire trucks).

5.3  STATE PROVISION VERSUS PRIVATE SECTOR REQUIREMENTS

     It is generally inappropriate  for the State to require a private developer

to provide benefits above and beyond what is required to deal with actual im-

pacts.  While the State has wide latitude in what it can require of a private
                             »
developer (see Appendix A) incentive requirements are not likely to be favor-

ably received by  a developer who has carefully provided an adequate compensation

package.  Surveys with private developers conducted for this handbook indicate

that they do not  see incentive requirements as an appropriate State role.  They

feel that incentives are basically  a concern of the developer and the community.

The private sector is not opposed to State use of incentives to supplement the

private developers incentives.  As  seen in Exhibit 9 , there are a number of

opportunities for the State to potentially use in HWMF siting.  State provision

should be done with caution since these are more discretionary actions than
                                      77

-------
mitigation or compensation activities.  Thus, the public nay not view them



as beinr;  legitimate State activities.
                                        78

-------
APPENDIX  A: POWER TO IMPOSE IMPACT RESPONSE REQUIREMENTS ON A HWMP DEVELOPER




      In the absence of a statutory provision expressly limiting

 such power, an agency or board,  authorized by  State law  to issue

 permits for siting hazardous waste management  facilities  (HWMF),

 may impose certain conditions on its approval  of applications  for

 such permits.  Among these nay be a requirement to  compensate

 the community or individual property owners for the losses they

 will suffer as a result of the facility's location.

      Nearly every type of governmental action  relating to land

 use regulation or facility siting approval has been made  subject

 to conditions at one tim^ or another, and such conditions have
                                         1
 generally been sanctioned in the courts.  Typically,  such con-

 ditions are imposed in order to  protect  those  interests  that

 have been placed within the anfcit of the permitting agency or

 board.  The board may determine  that such conditions  are  needed

 in order to protect the interests it has been  charged with pre-
                   V
 serving.  It will thus work out with the developer  the specific

 measures that must be undertaken or promised prior  to permit

 issuance.  Only after the conditions have been met  will  the


 authority issue the permit.

      Conditional permits are likely to be issued -  and to be

 judicially approved - whenever the permitting  authority  is given

 discretion as to whether to approve or disapprove a particular
                    2
 permit application.  In general,  the rule that has  been  applied

 in the courts to evaluate the propriety  of particular conditions on

 site approvals has been that the condition imposed  must  bear a
                                   79

-------
"reasonable relation" to the purposes and intent of the enabling
          3
enactment.  There does not appear to be any generic limitation on

the types of conditions that may be imposed, as long as this

reasonableness criterion is met.  Thus, for example, if one pur-

pose of HWMF siting legislation is to protect the interests of

communities in which a facility is ot be located or those of

abutting property owners, any  condition reasonably designed to

serve such purposes will likely be sanctioned.  A condition requir-

ing that compensation be paid  appears to fall within this rule.

     Indeed, courts have approved  "required dedications" of land

and money  to compensate for  the adverse consequences of a. devel-
                                                         4
opment when they were made conditions of permit issuance.  The

only limits that have been placed  on such  requirements is that the

funds or other property demanded must be intended for a purpose

related to the use  to which  the property will be put, and must

not be so  great as  to be regarded  as unreasonably onerous, in

light of that use.  Thus, as long  as compensation requirements

are limited to payments that approximate the  likely damages that

will be caused by the  facility,  they should be  legally permitted.

      In  formulating compensation requirements as conditions  for

 site  approval,  permitting authorities should take care to

 measure  the required compensation according to the magnitude

 of the harm.  This may be extremely difficult, if not arbitrary,

 however,  in dealing with the  intangible impacts.

      The fact that permitting authorities have considerable lati-

 tude in formulating compensation requirements does not mean that
                                 80

-------
their discretion is unfettered, however.  Rather, their powers




are limited by principles of due process and equal protection,




as well as by the provisions of any state administrative proced-




ure act that applies.  A board's actions may thus be subject




to challenge, for example, if compensation conditions are imposed




in some instances and not in others, unless there is some rational




explanation of this difference.




     In the absence of discrimination or specific arbitrary and




capricious conditions that, violate constitutional or administrative



law principles, however, a HWMF permitting authority may feel




free to impose conditions requiring payment of compensation in




proportion to the damages expected actually to be imposed by




the facility.
                                 81

-------
APPENDIX B:   INTERSTATE ISSUES AND AGREEMENTS



     Variations in compensation policies  among neighboring  States can have

undesired impacts on a HWMF's economic viability,  and  the flow of hazardous

wastes into the State.  Because of these  potential problems, States may want

to develop interstate agreements on compensation  strategies.  There are poten-

tial adverse effects whether the State, or  the facility  bears the cost of

compensation.  In instances where the facility pays  compensation, these ex-

penses will incrase the facility's operating costs.  Therefore, any HV7MF that

provides compensation is  likely to either charge  higher  rates or be less profit-

able than a facility that does not face these expenses.  If a Hwr-iF charges

higher rates, generators  will pre*fer to  use other facilities in the area.

If a HWMF is less profitable, it is  a less  viable investment.  These factors

could either keep facilities from being built in  the first  place, or ultimately

force compensation-providing facilities out of business.

     If, on the other hand, the  State bears the cost of  compensation while

another nearby State requires the  facility to bear this  burden,  the situation

is reversed.  Here, the  rates at the HWMF in the  State that provides the

compensation will be lower  which nay attract wastes into  the  State.   This  has

the undesirable side effect of  increasing the  risk of transportation related

accidents, wear and tear on the  transportation  routes, and may be  bad  public

relations for the State.  Furthermore,  the more wastes handled at  the  facility,

the greater the expense  to  the  State of providing compensation.

      Because of these potential problems.  States may  want  to resolve policy

differences through formal or informal interstate agreements.  They would have

two main options:

      e   jointly agree on compensation requirements; or

      •   agree on locations for common facilities and  jointly provide
         compensation.
                                      82

-------
     Jointly agreeing on compensation requirements might be difficult.  Given

the site specific nature of compensation needs, given regulatory differences

amoving States and given differing political contexts, identifying an appropriate

common level of compensation, and implementing it might be complicated.  But

even some minimum agreement,  for example,  requiring  HWMFs in the States involved

to provide some minimum compensation, or simply agreeing that the States will

provide the compensation themselves  would  alleviate  some of the potential pro-

blem.  Furthermore,  these  could be agreed  upon informally without establishing

official institutions  or memoranda of understanding.

     Should States agree to have common HWMFs and provide the compensation

jointly, they would  face endless options.   For example,  tne States could

pay lump sums into a common fund,  or pay  on a tonnage shipped basis,  or they

could develop common generation taxes and pool these in a compensation fund.

They also  could  agree  to provide various  mitigation measures  such as:

     •  shared maintenance of transportation routes;
     •  shared emergency preparedness/response;

     •  shared monitoring;

     •  shared laboratory facilities/technology transfer;

     •  transfer stations.
     These arrangements could be made through separate memoranda of understand-

 ing  among  State  agencies,  through established regional commissions  such  as

 the  New England  Regional  Commission or the Delaware River Valley Planning

 Commission, or  through special newly developed hazardous waste commissions.

 The  Resource Recovery and Conservation Act expressly allows for interstate

 agreements and  organizations for hazardous waste management.  While a detailed

 description of potential interstate arrangements is beyond the scope of this

 handbook,  Appendix F of Arthur D. Little's report to the Hazardous Waste

 Management Program of the New England  Regional Commission, "A Plan for Develop-

 nent of Hazardous Waste Management  Facilities in the New England Region",

 includes such a discussion.
                                     83

-------
APPENDIX C:  POWER OF A STATE TO PROVIDE IMPACT RESPONSES






      The power to tax and spend in the public interest is a

                                        6
 fundamental "attribute of sovereignty"  possessed by every


 state.  Under this power, states are free to determine what


 goods and services they will provide and how they will be


 financed.


      An incentive or compensation payment may take: either of


 two forms:  (1) It may be an explicit grant of funds or other


 value to  those who are affected or are  expected to be affected


 adversely by a hazardous waste management facility; or (2) it


 may, in effect, be a contractual purchase of a "package" of goods


 and services from the parties who receive the payment.  The. pack-


 age may include affirmative cooperation in siting a hazardous


 waste management facility  (HWMF); it may include promises to


 forego legal avenues to challenge the  siting; or it may include


 other similar elements.


      The effects of either type of payment are likely to be the


 same.  In both cases, the availability of compensation or similar


 cash payment may serve to reduce opposition to a HWMF.  If opposi-


 tion is reduced, the public may benefit because a needed facility


 can  be developed more  readily, keeping disposal and product prices down.


 A  State is  free to make  the  judgment  that the  public  interest is


 thereby served.


      Onca  it  is determined that the public will benefit from


 such community cooperation in the HWMF siting  process, or prom-


 ises to  forego legal  rights  to intervene in opposition to the
                                 84

-------
exercise their police powers in certain ways in the future.  If




such a promise is the only quid pro quo for a State's payment




of compensation, the state has received nothing in return for




its expenditures, and it is possible to assert that the payment




is therefore not in the public interest.




     The short answer to this objection is that the State's spend-




ing power is not limited to situations where the state itself




receives a benefit in return.  Countless public expenditures




are made more or less as pure grants, without evan a semblance




of quid pro quo.  The true test of State power is not whether




the State will benefit from the expenditure, but whether the




public interest is served.




     This short answer however, ignores the fact that, if the




state has secured only an unenforceable promise in exchange for




its expenditure, the public has also received no benefit from




the transaction.  Moreover, unlike welfare payments where the




simple transfer of funds is regarded as a public benefit be-




cause it serves the objective of  equitable wealth distribution,




payments to local governments where HWMF are proposed do not by




themselves serve the public interest.  The only way to assure




that the public interest is served by incentive payments to




local government—and thereby to remove all doubt as  to  their




validity — is to structure such arrangements so that, the; payments




are not made until after the bargained-for action is complete.




     Nevertheless, the determination of where the public interest




lies is normally left to the executive  and legislative branches
                                    86

-------
of government.  Courts will normally not interfere with a determin-




ation that a public purpose is served by an expenditure.   Thus




while it may be impossible to assure that every compensation or




incentive payment in  fact advances the public interest, a State




determination that it will is all that is required in order to




bring the payment within the scope of the state's power.
                                  87

-------
-APPENDIX D:   ALTERNATIVE LEGISLATIVE  APPROACHES
                        ( Available  in final handbook)
                                        88

-------
                          APPENDIX E-l
                          APPENDIX E-l
            Model Compensation Agreement Between the
                      Town of Riverdale
                  •and Waste Management, Inc.
 Introduction

     The model agreement sets forth a number of provisions  for

 mitigation,  compensation,  and incentives to the "Town of  River-

 dale" for the  potential and certain impacts of a hazardous

 waste management  facility  (HWMF)  to be constructed and operated

 by  "Waste Management,  Inc."

     The major legal problem associated with agreements of  this

 type is securing  proper "consideration" from the governmental

 signatory so that the  agreement is  binding  and enforceable.  Con-

 sideration is  what each party to a  contract does,  promises, or

 forgoes in exchange for the actions,  promises,  or forbearance

 of  the other party.  A contract is  not enforceable unless con-

 sideration has been given by each party for the obligations

 undertaken by  the other.  In the  model agreement,  many promises

 are aade by  Waste Management,  Inc.   Therefore,  care must be taken

 that the Town  of  Riverdale  gives  consideration for all of these

promises.
                                 89

-------
     In a contract such as the model agreement, the necessary




consideration might conceivably take the form of a promise to




accept the HWMF or not to oppose it.  Note that no such promise




appears in this agreement.  Even if one did appear, it might be




null and void because it exceeded  the Town's power, since a




Town ordinarily may not contract away its right and duty to




serve the public interest.




     Alternatively, the contract might  include a promise to




forego any legal remedies that may be available against the




owner to obtain damages for  the adverse impacts of the HV7MF.




That promise  is also  not made in  the model  agreement  (and




indeed is explicitly  rejected in  the proviso  of paragraph




I.V.A., since few  towns would likely be willing to agree to




it.



     Another alternative would be for  the agreement  to  recite




all of the harms possibly to be suffered by the  Town and  to




state  that the site owner's promises are to compensate  for




those  harms.   This approach was not taken for two reasons:




 (1) In reality,  it would be merely another form of a promise




of forbearance such as is rejected in paragraph I.V.A.   (2)




Since  many of the impacts recited would not be actionable in




 court (for example, because  they  would not render the facility




 a nuisance), a promise to forego  legal action might be




 "illusory" and thus not proper consideration.
                                  90

-------
     A fourth alternative is to  tie  certain promises to certain




harms and thereby to  trade  forbearance  from action for those




harms only for the  compensation  agreed  to.  This approach is




escplicitly taken in paragraph  IA.  However, this is only a




partial solution, and the model  agreement emphasizes this




fact by reciting a  list of  harms in  the preamble much longer




than those to be compensated  under paragraph  IA.




     The alternative  selected, therefore, was to make the en-




tire agreement contingent upon some  action by the  Town, rather




than any promise.   That action is the passage of a resolution




supporting the site owner's application, but it could  as well




be  a resolution  approving the site,  if such  a resolution were




part of the  necessary regulatory procedure.   Thus, paragraph




V.A. makes the compensation agreement a "unilateral"  contract




which  does not go into effect until one side—the  Town—has




 completed its obligation under it.  If the Town does not pass




 the necessary resolution, the contract is not effective.   If




 it does,  that action is adequate  consideration for all the




 promises made by Waste Management,  Inc.



      Sections I, II, and III  of the model agreement contain a




 few examples of compensation, mitigation, and incentives that




 can be included in the  agreement.  Many  more examples, of




 course, could be devised.
                                 91

-------
  •I- Cash  Compensation and Fees






     Paragraph  A.  of this  section contains  conventional  tied-




impact payments for the capital expenses and start-up  costs




of servicing the HWMF.   Paragraph B.  sets up a  tipping fee and




allows it  to be renegotiated from time  to time.






 II- Provision  of  Services and  Other  Compensation






     As an incentive, paragraph A.  promises free disposal ser-




vices to the Town  or its designee.  Paragraph B. promises to




dedicate a recreational facility to the Town.   This promise




may be regarded as a compensation device, if there will be some




loss of recreation in the  Town  as a result  of the HWMF, or it




may be regarded as an incentive  otherwise.   Note that  the pre-




amble says nothing about lost public  facilities as an  impact of




the HWMF.  Such a  reference  could,  of course, be incorporated




if it were needed.






III. Conditions of Construction  and Operation






     Paragraph  A.  provides for  liability insurance, in the event




of third party  damage.   Paragraph B.  includes some mitigation




measures that will alter the operation  of the HWMF.






 IV. Additional Compensation in  the Event of Breach






     This provision could be completely removed from the agree-




ment without affecting  the substantive  obligations under it.
                              92

-------
    section is purely procedural and establishes a mediation and

arbitration procedure for handling breaches of contract conditions.

If this provision were omitted, such breaches would have to be

litigated in court:.  In either event, however, the same sub-

stantive rights would be at issue.


  V. Effective Date


     As noted above, this section transforms the model agreement

into a unilateral contract and solves the problem of considera-

tion.  Paragraph A. also states that the agreement is not ef-

fective unless the site is approved.

     Paragraph B. is designed to protect the site owner in the

situation that the Board passes the required resolution but then

either it or its members or other community representatives take

action to undermine the effectivess of  the resolution.  In such
                    *
a case, the site owner may terminate the agreement if it alerts

the Siting Board of the fact  in time for it to delay its decision

on the application until it has had time to consider the effect

of the lack of an agreement.  The same  paragraph also protects

either party in the event that anything else occurs to make the

agreement unsatisfactory during the possibly long period of time

between the filing of the application  for  site approval and the

ruling on it.
                                  93

-------
               Model Compensation Agreement

                        Between
    The Town of Riverdale
    Town Hall
    Room 101
    Riverdale,  U.S.A.
                          and
    Waste Management, Inc.
    101 Main Street
    Riverdale, U.S.A.

WHEREAS Waste Management, Inc. plans to build a hazardous
waste management facility  (HWMF) on a site which it owns
in the Town of Riverdale, and which is located at 	
	; and

WHEREAS the construction and operation of the said HWMF will
result in increased traffic in the Town of Riverdale, re-
quiring additional expenditures by the Town of Riverdale
for traffic control and road maintenance; and

WHEREAS the construction and operation of the said HWMF may
result in odors,  noise and/or air pollution and thereby
cause damage to the residents of Riverdale and to public
facilities owned by the Town of Riverdale; and

WHEREAS the construction and operation of the said HWMF may
result in adverse impacts on the- beauty and quality of the'
environment of Riverdale and thereby lower property values
and reduce  the property tax base of the Town of Riverdale;
and

WHEREAS the construction and operation of the said HWMF may
result in ground and/or surface water pollution and  thereby
cause damage  to the public water supply owned and operated
by the Town of Riverdale;  and

WHEREAS "the construction and operation of the HWMF will result
in the need for additional expenditures by the Town  of  River-
dale for public services,  including  fire  and emergency  spill
response services, facility inspections and ground and  surface
                                94

-------
                          -2-
water monitoring ;  and
WHEREAS  the  construction and operation of the HWyj  -ay  increase
the  risk, of  other damages to residents of Riverdale and/ or  to
the  Town of  Riverdale; and

WHEREAS  Waste Management/ Inc. has agreed to undertake the  mitigation
measures specified in this agreement; and

WHEREAS  Waste Management,, inc. has agreed to compensate the residents
 of Riverdale and the Town of Riverdale   for such costs as are
 specified in this agreement;

 The parties  have agreed as follows :

 I.  Cash Compensation and Fees

     A. Waste Management, Inc. shall  pay  the  following amounts
 to the Town of Riverdale as  compensation for  the costs which
 will be imposed on it by the construction and operation of
 the HWMF:

           (1) Upon approval  of  the site  by the State Facility
 Siting Board: $ _ /  as  capital  for  extensions of local
 services ;

           C2) Upon commencement  of operation  of the HWMF:
               as compensation for  start-up expenses connected
 with extension of  local  services.

     B. Waste Management,  Inc.  shall  also  pay  the following
 amounts to the Town  of Riverdale:

            (JL). During the two years commencing on the  first
 date of operation  of the HWMF,  a  fee of five  cents  ($.05) per
 kilogram of waste  delivered to the HWMF.

            (2) Thereafter,  a fee as mutually agreed  by the
 parties from time  to time;  provided  that, if  the parties are
 mutually unable  to agree on a  fee at any  time,  the  fee shall
 be set at  an amount  equal to three cents  ($.03) per kilogram
 times the  number of  whole years that the  HWMF has been in
 operation.
                               95

-------
                           -3-
II. Provision of Services and Other Compensation

    A. Waste Management/ Inc. shall provide, without charge,
disposal services for up to	 kilograms per month of ha2ar-
dous wastes, as defined by the Resource Conservation and Re-
covery Act, 42 U.S.C. §6903(5), generated by any party or
parties designated by the Town of Riverdale.

    B. Waste Management, Inc. shall purchase the site located
at 	_, or an equivalent alternative site
mutually agreed upon by the parties, and construct thereon
a recreational facility to be dedicated to the Town of River-
dale, as further specified in Appendix I to this agreement.

IIL Conditions of Construction and Operation

    A. Prior to commencement of construction, Waste Management,
Inc. shall purchase and maintain insurance coverage for liabili-
ty to third parties for personal injury and property damage in
an amount not less than $	__ per occurance.

    B. Waste shall be transported to the HWMF only along the
route specified in Appendix II to this agreement.  No wastes
shall be transported to the HWMF except during the hours of
9:00 a.m. to 5:00 p.m. Mondays through Fridays.  No more than
	 truck loads of wastes shall be delivered to the
HWMF per day.

IV. Additional Compensation in the Event of Breach

    A. In the event that any one or more of the conditions
stipulated in this agreement shall not be met, the Town of
Riverdale shall be entitled to further compensation for the
damage caused by breach of the said condition.  The compensa-
tion shall be determined according to the procedure described
in paragraphs B,C and D below; provided that the Town of
Riverdale1s right to such  further compensation shall not
derogate from any right to other remedies which may be avail-
able to it under law.

    B. In the event that a dispute shall arise over whether
any one or more of the conditions  stipulated in this agreement
have been^met, the question  shall be  decided by a  committee
of'three experts,  appointed  according  to paragraph C below.
The decision of the said committee shall be final  and binding
on  those parties.
                              96

-------
    C. The committee of experts shall be appointed as follows:

        .  (1) In the event that Waste Management/ Inc. rejects
a claim by the Town of Riverdale that any one or more of the
conditions in this agreement have not been met, the Town of
Riverdale may demand that the claim be resolved by the commitee.

          (2) Within fifteen  (15) days of written demand to
this effect by the Town of Riverdale, each party shall appoint
one member of the committee.

          (3) The third member, who shall act as chairperson,
shall be chosen by the two members appointed by the parties,
and failing agreement between them, by 	.

    D. In the event that the committee of experts shall decide
that one or more of the conditions stipulated in this agreement
have not been met, the additional  compensation to which the
Town of Riverdale  is entitled under paragraph A above shall
be determined as follows:

          (1) The  Town of  Riverdale shall submit a claim to
Waste Management,  Inc., who  shall  respond to  that claim within
ninety  (90)  days.

          (2) If Waste Management,  Inc.  rejects the  claim,
representatives of both parties  shall meet, together with  a
mediator who shall be named  by  the chairperson of the committee
of experts which determined  that the  condition had not been
met.

          (.3) With the help  of "the said  mediator the parties
shall negotiate  in good  faith and shall  attempt  to evaluate
the further  costs  imposed  on Riverdale by breach of  the relevant
condition.

           04) Should the parties fail to reach agreement on this
matter, the' question shall be submitted  to  arbitration  before
an arbitrator who  shall  be appointed by  the mediator.

           (5) The  arbitrator's decision, which will  be  final
and binding  on  both parties, will stipulate the  sum of  compen-
sation  to be paid, or services to be provided and  the time when
such  compensation will be paid or services provided.

           t6)  The arbitrator shall determine which of the
parties shall  pay the costs of the arbitration.
                                 97

-------
                            -5-
V.  Effective Dates

    A. This agreement shall become  effective and binding on
the parties when  the  application of Waste Management-, Inc.
for approval of the site is approved  by  the State Facility
Siting Board if,  within one month of  the signing of this
agreement, the Governing Board of the Town of Riverdale
shall have passed the resolution, contained in Appendix III
of this agreement, in support of the  said application.

    B. This agreement may be terminated  by either party if
both of the following conditions are  met:

           (1) Written notice .of the termination, together with
a request  for a  stay  of the proceedings  on the application of
Waste Management, Inc. for approval of the site by  the State
Facility Siting  Board is received by  the Board prior  to its
ruling on  the  application.

           C2) Written notice of the termination  is  delivered
by hand  to the  other  party at the office address provided  in
the heading  of  this  agreement, above.
                                  98

-------
                         APPENDIX E-2

             Model Compensation Agreement: Between
            Waste Management, Inc. and John F. Kane
Introduction

     The model agreement sets forth a number of provisions for

mitigation, compensation, and incentives to "John F. Kane"

for the potential and certain impacts of a hazardous waste

management facility  (HWMF) to be constructed and operated by

"Waste Management, Inc."

     The problem of  securing proper "consideration" is not as

difficult in private compensation agreements as it is in agree-

ments with local governments since private parties may freely

agree to support a HWMF in the future, regardless of the pub-

lic interests affected.  Nevertheless, the best structure for

a private compensation contact is the same as for an agreement

with the government: a unilateral contract.  Such an agreement

does not go into effect unless one of the parties  (here, John

F. Kane) completes the action that constitutes the consideration

for the other party's promises.
                                 99

-------
     Sections  I,  II,  and  III of  the model agreement contain a




 few examples of compensation, mitigation, and incentives that




 can be  included in  the agreement.  They differ, of course,




 from the items contained  in the  model agreement with the Town




 of  Riverdale.  Some of the provisions, however, are similar.






  I. Cash Compensation and Fees






     Paragraph A. of  this section contains a single lump sum




 fee stated to be  compensation for the major construction impacts




 of  the HWMF.  Paragraph B. sets  up a monthly fee in exchange




 for continued forebearance from bringing an action for damages.




 This fee may be renegotiated from time to time.






 II. Provision of Services and Other Compensation






     As an incentive, paragraph A. promises free disposal




 services to John  F. .Kane.  Paragraph B. promises to create a




buffer strip between the HWMF and the abutting site.   This




promise is a mitigation device, peculiarly suited for dealing




with abutters.   Another mitigation device appears in para-




 graph C., which provides that Waste Management, Inc.  will pay




the costs of ground and surface water monitoring on the abut-




ting site.
                               100

-------
III. Conditions of Construction and Operation






     Paragraph A. provides for setbacks and sideyards,  to miti-




gate the impact of the HWMF further.  Paragraph B.  includes




additional mitigation measures in the form of spill prevention




practices.






 IV. Additional Compensation in the Event of Breach






     This provision, unlike the similar one in the public com-




pensation agreement, could not be completely removed without




affecting the substantive obligations of the parties.  The sec-




tion does establish a procedure for handling damage claims




arising out of the operation of the HWMF and creates a fund to




compensate those claims.  However, the section permits compen-




sation in instances where the harms caused are not actionable in




a court proceeding either as a breach of contract or as a tort.




Note that John P. Kane may pursue a claim under this procedure




without disturbing his right to a monthly fee under paragraph




I.E.  Once the compensation fund is depleted, however, he




cannot pursue a remedy without forfeiting his monthly fee.






  V. Effective Date






     As noted above, this section transforms the model agreement




into a unilateral contract and solves the problem of considera-




tion.  Paragraph A. also states that the agreement is not  ef-
                                  101

-------
fective unless the site is approved.  Paragraph B.  is designed -




to protect the site owner in the same manner as the comparable




paragraph in the public compensation agreement.  In addition,




this paragraph diminishes the ambiguity of the word "cooperated"




in paragraph A.  A court would normally interpret "cooperate"




to mean "reasonably cooperate" if the issue were raised before




it.  However, Paragraph B. allows Waste Management, Inc. to




terminate the agreement if it believes that the quality of the




cooperation it is receiving is inadequate.  Paragraph B. also




allows John F. Kane to terminate the agreement if it believes




that the cooperation being demanded is too burdensome.  The




practical impact of Paragraph B., if neither party terminates




the agreement, is that this fact alone is strong evidence that




the cooperation given was "reasonable,"
                                  102

-------
                 Model Compensation Agreement
                          Between
                 Waste Management, Inc.
                 101 Main Street
                 Riverdale, U.S.A.

                            and

                 John F. Kane
                 1 Rosebud Lane
                 Riverdale, U.S.A.


WHEREAS Waste Management, Inc. plans to build a hazardous
waste management facility  (HWMF) on a site which it owns,
located at 	 adjacent to property located
at	 which is owned by John F. Kane (the
"abutting site").

WHEREAS the construction and operation of the said HWMF will
result in increased traffic on Rosebud Lane in front of the
abutting site; and

WHEREAS the construction and operation of the said HWMF may
resuit in odors, noise and/or air pollution and thereby
cause damage to John F. Kane and to the abutting site; and
                   »
WHEREAS the construction and operation of the said HWMF may
result in adverse impacts on the beauty'and quality of the
environment of Riverdale and thereby lower the property
value of the abutting site; and

WHEREAS the construction and. operation of the said HWMF may
result in ground and/or surface water pollution and thereby
cause damage to the well water presently used to supply the
abutting site; and

WHEREAS the construction and operation of the HWMF will result
in  the need for ground  and surface water monitoring on the
abutting site; and
                              103

-------
                           -2-
WHEREAS the construction and operation of the HWMF may
increase the risk of other damages to John F. Kane-and/or
to the abutting site; and

WHEREAS Waste Management/ Inc. has agreed to undertake the
mitigation measures specified in this agreement; and

WHEREAS Waste:'Management, Inc. has agreed to compensate
John F. Kane for such costs as are specified in this agreement;

The parties have agreed as follows:

I.   Cash Compensation and Fees

     A. Waste Management, Inc. shall pay John F. Kane, upon
approval of the site by the State Facility Siting Board, the
amount of $	, as compensation for the annoy-
ance, noise, odor and other temporary impacts on the abutting
site from construction of the HWMF.

     B. Waste Management, Inc. shall also pay John F. Kane
the following additional amounts for so long as John F. Kane
refrains from bringing suit for any property damage to the
abutting site arising out of the operation of the HWHF:

           (1) During the two years commencing on the first
date of operation,of the HWMF, a fee of $	 per
month.

           (2) Thereafter, a fee as mutually agreed by the
parties from time to time; provided that, if the parties are
mutually unable to agree on a fee at any time,  the fee shall
be set at $            per month.

II.  Provision of Services and Other Compensation

     A. Waste Management, Inc.  shall provide,  without charge,
disposal services for up to '      kilograms per month of hazar-
dous wastes,  as defined by the Resource Conservation and Re-
covery Act, 42 U.S.C. §6903(5), generated by John F. Kane.

     B. Waste Management, Inc. shall purchase from John F. Kane
for $_._.. ^	___, a buffer strip designated  as lot A on
the plan attached as Appendix I to this agreement and shall
plant thereon a hedge, acceptable  to John F. Kane, and  sufficient
to form a visual screen between the HWMF and the abutting site.
                               104

-------
                          -3-
     C. Waste Management, Inc. shall reimburse John F. Kane
for the purchase and installation of ground and surface water
monitoring devices, as specified in Appendix II to this agree-
ment, and shall further reimburse John F. Kane for monitoring
services and maintenance of the said devices in an amount not
to exceed $_	 per year.

III. Conditions of Construction and Operation

     A. No wastes will be stored or disposed of on the HWMF
at locations less than ______  yards from the abutting site
or 	 yards from Rosebud ILane.

     B. Waste Management, Inc. shall.institute the practices
specified in Appendix III to this agreement for the prevention
of hazardous waste spills at the HWMF.

IV.  Compensation for Damages

     A. Waste Management, Inc. shall establish a fund of
           which will be used to mitigate any effects of the
HWMF on individual residents: of Riverdale, with whom Waste
Management, Inc. enters into agreements substantially similar
to this agreement, and to compensate such residents for those
decreases in property values which result directly from con-
struction and/or operation of the HWMF.

     B. Claims for mitigating measures and/or compensation by
John F. Kane                   shall be decided by an assessment
board of three people who shall be appointed in the manner
specified in paragraph C below.
                 .*
     C. The assessment board shall be appointed as follows:

           CD Within fifteen CIS) days of submission of a
claim to Waste Management, Inc. each party to this agreement
shall appoint one member of  the board.

           (.2) The third member, who shall act as chairperson,
shall be chosen by the two members appointed by the parties,
and failing agreement between them, by	.

     D.--A-fter affording John F. Kane and a representative of
Waste Management,.Inc. the opportunity to be heard on the
claim, the assessment board  shall determine John F. Kane's
entitlement;.to compensation  and/or mitigating measures.  The
board may attach whatever conditions it deems appropriate to
the award of such compensation and/or mitigating measures.
                                105

-------
     E. The liability of Waste Management, Inc. under this
agreement  for all claims submitted by  John F. Kane shall be
limited to the sum of the fund established under paragraph
A;    provided that  this fund shall  in no way restrict the:
legal liability of Waste Management, Inc. for claims not submitted
to the assessment board, or for claims that  cannot be met
due to depletion of  the fund.

V.   Effective Dates

     A. This agreement shall become  effective and binding on
the parties when the application of  Waste Management, Inc. for
approval of the site is approved by  the State Facility Siting
Board if John F. Kane shall have coop.erated with Waste Management,
Inc. in any hearings before the said Board.

     B. This agreement may be terminated by  either party if
both of the following conditions are met:

           (1) Written notice of the  termination, together with
a request  for a stay of the proceedings on the application of
Waste Management, Inc. for approval  of the site by the State
Facility Siting Board is received by the Board prior to its
ruling on  the application.

           (2) Written notice of the  termination is delivered
by hand to the other party at the office address provided in
the heading of this agreement, above.
                             106

-------
APPENDIX F:  POTENTIAL FOR UNEXPECTED STATE LIABILITY








      The decision of a State to provide compensation or  an



 incentive to facilitate the siting of a hazardous waste  manage-


                                       12
 raent facility (HWMF) will not normally  subject the  state to



 liability for damages if that decision proves  to have untoward



 consequences for the community or neighboring  property owners.



 This conclusion is not altered even when the state has been



 negligent in deciding to provide the incentive or compensation.



      Of course, a State may voluntarily take on responsibility



 for the HWMF, by contractually guaranteeing its safety.  In



 such a circumstance, the State may be held liable according to



 the terms of its contract.  Such liability, however, is  not



 "unexpected" and can readily be avoided simply by refraining  to



 enter into any agreements containing such guarantees.



      The more difficult issue for State agencies is



 whether the mere fact of providing incentives  or compensation
                   .»            •


 can give rise to tort or similar forms of liability  for State



 negligence or violation of federally protected rights.  Such



 liability is generally precluded under principles of law that



 provide immunity from tort liability for certain governmental



 acts.
                                     107

-------
     One rationale for sovereign immunity is that nearly every

act of government he.s adverse impacts on some individuals.  Such

impacts cannot be the basis for tort liability, however, if

government is to function.  As U.S. Supreme Court Justice

Jackson once observed, "It is not a tort for government to
         13
govern."

     However, sovereign immunity means more than that govern-

ments are not liable for every adverse impact of their actions.

Where sovereign immunity applies, governments will not be held

liable for any adverse inputs of their actions, even if those

actions were negligent and the impacts were directly caused by

them.

     Until 1957, sovereign immunity shielded every state from

tort liability for every governmental activity.  In that year,

Florida became the first state to abolish sovereign immunity
                 14
in some contexts.   At least 26 states have now abolished or
                           15
modified the immunity rule.    Nevertheless/ most jurisdictions

have retained immunity in some contexts so as to avoid the spectre

of one branch of government reviewing the reasonableness of a

co-equal branch.  The California Supreme Court has explained:

          "(There must be) an assurance of judicial ab-
          stention in areas in which the responsibility
          for basic policy decisions has been committed
          to coordinate branches of government.  Any wider
          judicial review, we believe, would place the
          court in the unseemly position of determining the
          propriety of decisions expressly entrusted to a
          coordinate branch of government.'

     In order to assure that courts will not review the reason-

ableness of "basic policy decisions," most jurisdictions have
                               108

-------
adopted a "discretionary function" rule of immunity.  Under that

rule a state is immune from liability for its acts if the act

involves high level policy decisions which have been entrusted

to the executive branch of government, and are thus inappropri-

ate for judicial review.

     The discretionary function rule originated with the Federal

Tort Claims Act of 1946, which abolished federal soverign immunity

and allowed tort claims to be brought against the United States

government for the first time.  The Act, however, retained immunity

for:

          "(a)ny claim...based upon the exercise or
           performance or the failure to exercise or
           perform a discretionary function or duty
           on the part of a federal agency or an em-
           ployee of the Government, whether or7not
           the discretion involved is abused."

Several states have enacted legislation patterned after the
            18
Federal act.    Even where State statutes are totally different,

however, the courts have essentially carved out the same area of

governmental discretion to which immunity applies.  For example,

the New York Court of Appeals has interpreted that state's tort

claims act, which contains no express immunity whatever, as retain-

ing immunity for discretionary actions.  As the court explained:

          "To accept a jury's verdict as to the reason-
          ableness and safety of a plan of governmental
          body which originally considered and passed on
          the matter would be to obstruct normal govern-
          mental operations and to place in inexpert
          hands what the Legislature has seen fit to en-
          trust to experts."19

     ftie decision to provide compensation or incentives to a

community to facilitate the siting of a HWMF clearly appears to
                                   109

-------
be just the sort of discretionary activity that tort immunity


rules were designed to protect.  Such a decision appears to


involve the judgment of state officials entrusted with power to


make the decision.  Nevertheless, this conclusion cannot be


reached automatically.  Even "ministerial" actions - the term


used to describe acts which are not discretionary and for which


there is consequently no immunity - may involve some degree of


judgment.


     Ministerial actions are sometimes contrasted with dis-


cretionary acts on the basis that they involve execution rather


than formulation of policy.    Using such a distinction, a de-


cision to provide compensation or incentives in all cases that


meet certain criteria would be discretionary, while a decision


as to whether a particular objective criterion had been met


would be ministerial.  Theoretically, then, a decision to provide


compensation or incentives might turn on a purely ministerial ap-


plication of policy, and thus might be the subject of a tort suit.


In practice, however, the decision to provide compensation or in-


centives will not be based on such objective criteria, but rather


on policy determinations concerning such factors as the urgency of


the need for additional facilities.  These determinations are


more clearly matters of discretion.


     The issue of immunity is somewhat different if the allegation


is that the decision to provide compensation or incentives has


interfered with a right secured by federal law.  Such an allegation

                                                            22
may conceivably be made under Federal civil rights statutes,

-------
using the Resource Conservation and Recovery Act  (RCRA) as the


source of the Federal right.  However, while the civil rights


statutes have been applied to allow money damages to be assessed


against other levels of government. States are granted absolute


immunity by the eleventh amendment from suits for damages in

              23
federal court.    While this immunity has not. been extended to


actions for equitable relief such as injunctions, this fact will


be of little use to a litigant whose sole basis for relief is a


decision to provide incentives or compensation since the decision


and its implementation would likely be complete at the time the


action is brought.


     Thus, it may be concluded that the decision to provide in-


centives or compensation to a community to induce or facilitate


its acceptance of a HWMF will not open the State to unexpected


liability.  Unless the State expressly binds itself to guarantee


the safety of such a facility,  it will be immune from suit for


even a negligently made decision to provide such compensation or


incentives.
                                   Ill

-------
                             APPENDIX G:   PRESENT VALUE OF 9**DUE IN « PERIODS AT i INTEREST PER PERIOD
H
M
N)
                               Rate of interest, %
                       1.0      1.5      2.0
2.5
3.0
4.0
5.0
6.0
    Rate of interest, %
8.0        10.0      15.0
20.0
25.0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
25)
30
35
40
45
50
.9950
.9901
.9851
.9802
.9754
.9705
.9657
.9609
.9561
.9513
.9466
.9419
.9372
.9328
.9279
.9233
.9187
.9141
.905)6
.9l>5»
.9006
.85)01
.85)10
.8872
.8828
.87H4
.H740
.8(55)7
.8053
.Kf.HI
.8.15J8
.815)1
.7?)5X)
.775)3
.9901
.9803
.9700
.9610
.9515
.9420
.9-327
.9235
.9143
.9053
.8963
.8874
.8787
.8700
.8613
.8528
.8444
,8300
.8277
.811)5
.8114
.8034
.7954
.7876
.77S)«
.7720
.7644
.7568
.74(.)3
.74 H)
.705!)
.0717
.035)1
.6080
.9852
.9707
.9563
.9422
.92S3
.9145
.90)0
.8877
.8748
.8617
.8489
.8364
.8240
.8118
.7999
.7880
.7764
.7649
.7538
.7425
.7315
.7207
.7100
.695)5
.685)2
.675X1
.605)0
.055)1
.045)4
.G35JK
.55)35)
.5513
.5117
.4750
.9804
.9612
.9423
.9238
.9057
.8880
.8706-
.8535
.8368
.8203
.8043
.7885
.7730
.7579
.7430
.7284
.7142
.7002
.6864
.6730
.6598
.6468
.6342
.6217
.0095
.55)70
.5855)
.5744
.5031
.r>r>2i
.SOW
.4525)
.4102
.3715
.9758
.9518
.9286
.9060
.8839
.8623
.84 J3
.8207
.8007
.7812
.7621
.7436
.7254
.7077
.0905
.6736
.0572
.6412
.6255
.6103
,5954
.5809
.5067
.5529
.535)4
.5202
.5134
.5005)
.4«ftt
.4707
.4214
.3724
.325)2
.25)05)
.9709
.9426
.9151
.8885
.8626
.8375
.813J
.785)4
.7664
.7441
.7224
.7014
.0810
.6011
.6419
.6232
.6050
.5874
.5703
.5537
.5375
.5219
.5007
.45)15)
.4776
.4037
.4502
.4371
.4243
.4120
.3554
.3000
.2644
.22RI
.9815
.9240
.885)0
.8548
.8219
.7903
.7599
.7307
.7020
.6756
.645X5
.6246
.6006
.5775
.5553
.5339
.5134
.45)30
.4740
.4564
.4388
.4220
.4057
.3!K)1
.3751
.3007
.3408
.3335
.3207
,10H3
.2534
.2oai
.1712
.M»7
.9524
.9070
.8638
.8227
.7835
.7482
.7107
.6768
.6448
.6139
.5847
.5508
.5303
.5051
.4810
.4581
.4303
.4155
.3957
.3769
.3589
.3418
.3256
.3101
.2<)53
.2812
.2078
.2551
.2429
.2314
.1813
.M20
.1113
,0872
.9434
.8900
.8390
.7921
.7473
.7050
.6051
.6274
.5919
.5584
.5208
.4970
.4688
.442.3
.4173
.3930
.3714
.3503
.3305
.31 18
.2942
.2775
.2018
.2-170
.2330
.2U)8
.2074
.15)50
.1840
.1741
.1301
.05)72
.0727
.05-13
.9259
.8573
.7938
.7350
.6806
.6302
.5835
.5403
.5002
.4032
.4289
.3971
.3077
.3405
.3152
.2919
.2703
.2502
.2317
.2145 >
.1987
.1839
.1703
.1577
.1400
.1352
.1252
.1155)
.1073
.05)5)4
.0076
.0100
.0313
.0213
.9091
.8264
.7513
.6830
.6209
.5645
.5132
.4605
.4241
.3855
.3505
.3180
.2897
.2033
.2394
.2170
.1978
,1799
.1035
.1480
.1351
.1228
.1117
.1015
.0923
.0839
.0703
.005)3
.0030
.0573
.0356
.0221
.0137
.0085
.8696
.7501
.6575
.5718
.4972
.4323
.3759
.3209
.2843
.2472
.2149
.1869
.1625
.1413
.1229
.1009
.05)29
.0808
.0703
.0011
.0531
.0462
.0402
.03-1!)
.0304
.0264
.0230
.0200
.0174
.015!
.0075
.0037
.0019
.0005)
.8333
.65)44
.5787
.4823
.4019
.3349
.2791
.2326
.1938
.1615
.1346
.1122
.0935
.0779
.0649
.0541
.0451
.0376
.0313
.0201
.0217
.0181
,0151
.0126
.0105
.0087
.0073
.00(51
.0051
.0042
.0017
.0007
.0003
.0001
.8000
.6400
.5120
.4096
.3277
.2821
.2097
.1678
.1342
.1074
•.0859
.0087
.0550
.0440
.0352
.0281
.0225
.0180
.0144
.0115
.0092
.0074
.0059
.00-17
.0038
.0030
.0024
.001!)
.0015
.0012
.0004
.0001
0.0000
0.0000

-------
                        Appendix Footnotes
 1,  See Freilich & 0_uinnf  "Effectiveness of  Flexible  and  Conditional
    Zoning Techniques—What They Can and What They Can  Not Do for  Our
    Cities,"  1979 Proceedings of the Institute on  Planning,  Zoning and
    Eminent Domain 167, 193 (.Southwestern Legal Foundation)

 2.  In the unusual circumstances where no such discretion exists,  how-
    ever,  a permit must be issued whenever the statuatory criteria are
    met,  and  no additional conditions can be imposed.   Statutes  that
    confer authority on a  particular board to issue HWMF  permits,  however,
    appear always to vest  some discretion in the board,

 3.  See,  e.g. r  Bringle vv  Board of Supervisors,  54 Cal, 2d 86, 351
    P.2d 765  (I960)  (zoning variance),

 4,  See,  Pioneer Trust Savings Bank v.  Village of  Mt, Prospect,  22 111,
    2d 373, 176 N.E,2d 799 (1961).

 5.  For example, some courts have been reluctant to approve mandatory
    dedications for schools.  Id.

 6.  Maryland  v. Environmental Protection Agency, 530  F.2d 215,
    225 (4th  Cir. 1975), vacated and remanded, per curiam, on
    other grounds, sub nom. Environmental Protection  Agency
    v. Brown,  431 U.S. 99  (1977).

 7.  Linde & Bunn, Administrative Law 832 (1976)

 8.  Perkins v.  Lukens Steel Co., 310 U.S. 113, 127 (1940)

 9.  Kretzmer,  "Binding Communities to Compensation Agreements
    for Facilities" Document No. 16, Energy  Impacts Project,
    Laboratory of Architecture and Planning, Massachusetts
    Institute of Technology, Report to the U.S. Department of
    Energy (1979)

10.  Research  revealed no instance where the  validity  of a
    public expenditure was challenged on the basis that the
    bargained-for promise  was illusory.  Exhaustive research,
    however,  was not undertaken.

11.  Courts sometimes state that decisions of this  type  are
    entitled  to a presumption of validity.  See, e.g._,  Caleb
    Pierce, Inc. v Commonwealth, 453 Mass. 306, 237 N.E.  2d 63
    (1968).
                                  113

-------
12. This issue discussion does not address peculiar provisions
    of state law that might conceivably alter its  conclusions
    in certain circumstnaces in a single jurisdiction.   While no
    such provisions were identified in the course  of research,
    an exhaustive search was not undertaken.

13. Dalehite v. United States, 346 U.S. 15,57 (dissenting)(1953).

14. Hargrove v. Town of Coca Beach, 96 So.2d 130 (Fla.  1957).

15. See cases collected in Comment, "The Discretionary  Exception
    to Government Tort Liability," 61 Marquette L. Rev. 163,  n.2
    (1977)

16. Johnson v. State, 69 Cal.2d 782, 248 P.2d 352  (1968)(emphasis
    in original).

17. 28 U.S.C. p2608  (a).

18. s*»e, e.g., Alaska Stat. p9.50.250(1); Cal. Gov't Code p820.02;
    Iowa Code Ann. p25A.14.1; Minn. Stat. Ann. p466.03(6).

19 • Weiss v. Fote, 7 N.Y.2d 579, 167 N.E.2d 63  (1960) .

20. See, e.g., Elgin v. District of Columbia, 337 F.2d 152, 155
    (D.C.Cir. 1964).

21. The problems of proof in such a suit would be astronomical,
    however.  At a minimum, it would be necessary to prove that
    the decision to provide, compensation or incentives was the
    proximate cause of the harm alleged.  If there was any interven-
    ing superceding cause such as negligent design or operation of
    the facility the causal link would be broken and the suit would
    fail.

22. 42 U.S.C. p!983.

23. See Sketianv. Board of Trustees, 538 F.2d 53, cert, denied,
    429 U.S. 979  (1979).

-------