WATER POLLUTION CONTROL RESEARCH SERIES •  DAST-9
     Reduction of Infiltration
            by Zone Pumping
IPARTMENT OF THE INTERIOR • FEDERAL WATER POLLUTION CONTROL ADMINISTRATION

-------
               WATER POLLUTION CONTROL RESEARCH SERIES


The Water Pollution Control Research Reports describe the results and
progress in the control and abatement of pollution of our Nation's Waters.
They provide a central source of information on the research, develop-
ment and demonstration activities of the Federal Water Pollution Control
Administration, Department of the Interior, through inhouse research and
grants and contracts with Federal, State, and local agencies, research
institutions, and industrial organizations.

Triplicate tear-out abstract cards are placed inside the back cover to
facilitate information retrieval   Space is provided on the card for the
user's accession number and for additonal keywords.  The abstracts
utilize the WRSIC system:

Water Pollution Control Research Reports will be distributed to requesters
as supplies permit.  Requests should be sent to the Publications Office,
Department of the Interior, Federal Water Pollution Control Administration,
Washington, D.C. 202H2

Previously issued reports on the Storm and Combined Sewer Pollution Control
Program:

       WP-20-11    Problems of Combined Sewer Facilities and Overflows-
                   1967.

       WP-20-15    Water Pollution Aspects of Urban Runoff.

       WP-20 16    Strainer/Filter Treatment of Combined Sewer Overflows.

       WP-20-18    Improved Sealants for Infiltration Control.

       WP-20-21    Selected Urban Storm Water Runoff Abstracts.

       WP-20-22    Polymers for Sewer Flow Control.

-------
          REDUCTION OF GROUND-WATER

           INFILTRATION INTO SEWERS BY

        ZONE PUMPING AT MERIDIAN, IDAHO
FEDERAL WATER POLLUTION CONTROL ADMINISTRATION

                 GRANT  2 9-IDA-2
                HOFFMANN & FISKE
              CONSULTING ENGINEERS
          2500 Kootenai, Boise,  Idaho 83705
        917 Eighth Ave., Lewiston, Idaho 83501

                   June,  1969

-------
          FWPCA Review Notice

This report has been reviewed by the Federal
Water Pollution Control Administration and
approved for publication. Approval does not
signify that the contents necessarily reflect
the views and policies of the Federal Water
Pollution Control Administration.
                          ii

-------
                            ABSTRACT

    The purpose of this study was to determine if the lowering of the high
water table by pumping in a given area of the City of Meridian would
eliminate infiltration of ground water to the municipal sewers .  If the
infiltration could be eliminated,  the large volume of sewage flow that
occurs during the irrigation season would be greatly reduced.  Sewage
flows in excess of the capacity of the sewage treatment plant  are now
bypassed to a  small stream.
    It was contemplated that the test results  from this study could be
used to predict the lowering of water table in. ether areas in the City of
Meridian.  The topography, geology, precipitation, as well as local
irrigation programs are so irregular in character that no definite criteria
could be set up to predict what would occur in other areas.  It is concluded
that each area would have to be  studied independently to decide the depth cf
well, pump capacity and local affecting conditions.
    It is also  concluded that the cost of capital investment, cost of
operation of these pumping projects in the entire  Meridian area to lower the
water table would be too expensive to accomplish the purpose cf lowering
the water table below the sewers so  as to materially decrease the flow of
infiltration water to the sewage treatment plant.  It would be less expensive
to build holding lagoons  or a separate lagoon  system to treat the excess flow
to the sewage  treatment plant during the  irrigation period.  This report
was submitted in fulfillment  cf Grant 29-IDA-2 between the Federal Water
Pollution Control Administration  and  the City of Meridian, Idaho.
                                 iii

-------
                           TABLE OF CONTENTS               Page

    ABSTRACT	iii

I   INTRODUCTION

    1.  Nature of Project	   1
    2.  Findings	4
    3.  Conclusions	   6

II   DESCRIPTION OF PROTECT AREA

    1.  Location	7
    2.  Climate	   7
    3.  Irrigation	7
    4.  Sewage Collection, Treatment and Disposal at Meridian.   8
    5.  Problems in Operating the Combined Sewer System. ...   8

III  PROTECT CONSTRUCTION

    1.  Production Well.  . .	    9
    2.  Observation Wells	   11
    3.  Flow Measuring S ystems	    15

IV  PROTECT OPERATION

    1.  Initial Pumping Period	16
    2.  Intermediate Pumping Period	16
    3.  Final Pumping Period	   17
    4.  Presentation of Data	   21
        a.   Observation Wells	21
        b.   Flow in Manhole No. 5	:	21
        c .   Flow in Five Mile Creek	21
        d.   Flow thru Sewage Treatment Plant	25
        e.   Domestic Water Pumps	   25
        f.   Ground Water  Pumped	25
        g.   Irrigation Season	25
        h.   Precipitation	25
                                  IV

-------
V   ANALYSIS OF DATA

     1.   Observation Wells	   25
     2.   Flow in Manhole No.  5	26
     3.   Flow in Five Mile  Creek.	    27
     4.   Domestic Water Pumped	    27
     5.   Irrigation Season	27
     6.   Daily Precipitation	  28
                                     v

-------
                                FIGURES
                                                               Page
1.   Map of Meridian showing location of Sewage Treatment Plant,  Five
    Mile Creek, Meridian City and Project Area	2
2.   Ground-Water Program Meridian Pump Project	3
3.   Well Cross Section	10
4.   Plan of Pump Pit	12
5.   Section thru Pump Pit	13
6.   Diagram typical Observation Well	   14
7.   Time-Draw Down Curve Pumping Rate 200 g. p.m.  ...  ....  18
8.   Time-Draw Down Curve Pumping Rate 350 g.p.m	19
9.   Time-Draw Down Curve Pumping Rate 570-618 g.p.m	20
10. Distance Draw Down Diagram Section l(Pumped Well O.W.
      #6-O.W.#2)	22
11. Distance Draw-Down Diagram Section 2 (Pumped Well  O.W.
      #6-O.W. #3	23
12. Distance Draw Down Diagram Section 3 (Pumped Well O .W.
      #6-0.W. #4)	24
13. Chart Showing Field Recordings & Data for  City of Meridian
      Drainage Project	29
                                  vi

-------
                   REDUCTION OF GROUND-WATER
                   INFILTRATION INTO SEWERS BY
                ZONE PUMPING AT MERIDIAN,  IDAHO
1.   INTRODUCTION
        Nature of Project
        The sewer systems in several of the south central cities of Idaho
        have been troubled by the infiltration of irrigation water into the
        sewers. As a result the sewage treatment facilities are overtaxed
        during the irrigation season.  The situation at Meridian, Idaho, is
        unique in that the overtaxing of the sewage treatment plant comes
        during the dry summer months from the infiltration of irrigation water
        rather than in the winter during heavy rainfall period.

            The City of Meridian Sewage  System consists of several laterals
        throughout the City which connect to a 21 inch trunk sewer that leads
        to a secondary treatment plant Northwest of the City Center.  The
        effluent from the sewage plant flows into Five Mile  Creek  which runs
        Northwesterly through the area.  See Figure No. 1.

            The Sewage Treatment Plant is designed for a flow of  1500
        g.p.m. (2 ,160, 000 g.p.do).  The plant takes care of the sewage
        treatment during the winter months,  but during the summer months
        there are some flows over 2,160,000 gallons per day.  The extra flow
        is a result of infiltration of ground water during the  irrigation season.
        In some areas the ground water rises to within 18 inches cf the ground
        surface.  As  a result of this heavy infiltration a great deal of untreat-
        ed sewage bypasses the sewage treatment plant and flows into Five
        Mile Creek.  Five Mile Creek meanders westerly through a farming
        area to the Boise River which eventually flows into the Snake River
        near Parma, Idaho.

            One of the areas of high water table is in the southwest portion
        of the City.  It is a residential area bounded on the north by Bower
        Street; on the south by Cottonwood Avenue; on the west by Meridian
        Street and on the east by East 3rd Street,  See Figure  2.  The ground
        water in this area was  only 18 inches below ground surface at this
        point. This is probably the most critical area in the City of Meridian „

            The basic idea of this project was to install a shallow well
        pump  in the center of the above area, which is the approximate low
        point  of the area,. and study the lowering of the water table to
        determine the zone of influence of the well, If  the pumping were

-------
|oo
3°
a
SEWAGE

 TPEATMEMT
  PLANT
GENERAL LOCATION MA*

    CITY OF MERIDIAN

HOFFMANN-FISKE CONSULTING ENGINEER*
  •ZBOO KOOTENAJ ST.         BOISE, IDAHO
  917 8™ AVENUE       LEW1STON, IDAHO
A/of to Sco/e            Apr 24, 79g9
        Sewer- TrunK
               T. 3N., 1 W.,6.M.
                   PROJECT
                      AREA

-------
       GROUND   VSATGR

MERIDIAN  PUMP  PROJECT

4 TO TREATMENT                                   ft'0
II  PLA"T        I   |	1  ,|	|   |/**
  L_	_j£  I	__	|  ^ L	
T"                              	
     fx/'S/Vntf
  »V Ground Water
     Kfe// 41 Pump

         'ton **3
                  (0
                                               ~4  BOWER   AVB.
                                             8

^J?!!*

rronivoc
1
I
if
1
1
1
i!
>z>4i
\
\
XWG \

/•'*
WH.L/A.M&




k
2
€ " Temporary
Weil for «
Ground Water? \



\
\\
\
• — ' _^ I' — -
	 Z± 	 ^===
O
1, (•
Ju
If

Si
CM
\
•PROJECT *
Well 4 Pump

AVE.


AVE.


r
if

K.
V)
a-
X

o Manholes 
-------
    able to keep the ground water level below the sewers, the irrigation
    infiltration would  be reduced and the flow to the sewage plant during
    the irrigation period would be reduced.  The study was to determine
    if it would be economically feasible to install these pumps through-
    out the City and thus eliminate the sewage  bypassing the sewage
    treatment plant during the summer months.

        A 100 foot well was drilled as shown on Figure 2 at the alley
    between Ada & King Avenues on East 2nd.  This was completed on
    December 21,  1967.  A 500 g.p.m,  pump was installed on June 23,
    1968, and the City of Meridian construction crew completed construct-
    ion of the 8 inch transite line to the Nine Mile Drain as shown on
    Figure 2 at the same time.  The pump was started on June 26,  1968,
    at a capacity of 200 g.p.m. and pumped at  this capacity until July 17,
    1968.  On July 17, 1968, the pumping capacity was changed to
    350 g.p.m. and on August 7,  1968, the pump was  opened to its full
    capacity. Depending on the elevation of ground water this varied
    from 570 to 660 g.p.m.  The pump was left  at its maximum pumping
    capacity from August 7, 1968, until the wilting of this report and
    will continue to operate at full capacity until ground-water conditions
    warrant making a  change.

2.  Findings
    The following are the findings of the study of the Meridian Drainage
    Project, Meridian, Idaho:

    a.  The ground-water level in the Meridian area is a factor in
    the infiltration of water into the sewer system.  The water table
    rises in the summer due tc irrigation water percolating into the
    ground.  In the winter excessive rainfall and snow melt also
    percolate into the ground.

    b.  The flew in the sewer lines is affected by the ground-water
    level.  The higher the ground-water level,  the greater the head
    on the sewers and therefore the greater the  rate of infiltration.
    There is no doubt  that the sewer lines constructed of vitrified
    clay pipe during the 19305s have defective joints and broken
    sections that contribute to this infiltration.

    c.  The flow through the sewage plant varys a great deal from
    summer to winter  months because of the infiltration of irrigation
    water into thn sewers. The records shew some 1,150,000 gallons
    per day byp?being the sewage in the peak summer flew.  This  is
    untreated water and sewage that flows into  Five Mile Creek.
                               - 4 -

-------
d.  The flow in Five Mile Creek varies from 10 c.f.s. in
winter to 45 c.f.s. in summer.  There is contamination of Five
Mile Creek from the sewage which bypasses the sewage plant
during the summer months.  Due to the greater flow of water in
summer months there is more oxygen available and a greater
flow for dilution of sewage.

e.  The ground water pumped from the drainage well into the
Nampa Meridian Drainage Canal has low bacteria  count and
B.O.D. demand indicating that  the waters are not contaminated
and can be used for irrigation purposes .

f.  The water levels in the different areas cf the  project area
were not lowered  uniformly with the pump operating 24 hrs. a
day.  The ground-water levels fluctuate due to the impact of
local irrigation, rain and snow  fall.

g.  The total cost cf the construction project was as fellows:

    Construction Costs
       a.   Contracts                   $11,745.67
       b.   Force Account                 4,227.85
       c.   Engineering                   6,265.00
       d.   Legal                          100.00
       e.   Administration                   450.00
       f.   O & M                        1,711.48
          Tctal Cost  Project            $24,500.00

h.  The cost of operating the pump 24 hours a day at full
capacity is  about $1.75 per day to pump an average 850,000
gallons of ground water.

i.  Pumping the  ground water lowered the water table below the
sewers for about  a two block square area.  This affected the
amount of flow into the sewers  and thus the, flew through the
sewage treatment plant.

j.   Pumping in the winter months lowered the water table as
it was affected by periodic rains ar^d snow melt.

k.  The results of this study did net result in any empirical
formula to predict the results of drainage pumping in other
areas of City of Meridian.  The subterranean geology as well
as the irrigaucr., topography and precipitation make this
                           - 5 -

-------
    impossible.

    1.   A drainage pump will lower the water table below the sewers,
    but each area will have to be studied independently to decide
    the depth of well, pump capacity and waste way for pumped
    water.  This area was an ideal area as far as costs are concerned.
    Elimination of waste water in other sections of City could present
    a problem.

    m.  All construction should be in the winter months so that the
    high water table will not present problems.

    n.  The City of Meridian consists of approximately 140 square
    blocks in area which ne ans about 70 units .  70 units  at an
    average cost of $40,000. per unit would mean a capital outlay
    of $2,800,000.  This would mean a power bill of $122.50 a
    day in addition.

        There  are other benefits derived from the pumping operations
    besides the lowering of the  infiltration into the sewer lines .
    Several basements in the area have been dry as a result of the
    drop in water table in the zone of influence of the pumping well.
    Actually the water pumped into the Nine Mile Draw could be
    used for irrigation and a benefit thus derived from the presently
    wasted flow.  Some people have shallow wells  used for irrigat-
    ing their own properties.  Some of these have gone dry as a
    result of lowering ground water.  If the water table could be
    lowered it  would make all types of construction, particularly
    utility construction, less expensive. At present utility
    construction is limited to the winter months when the  water
    table is down.

3.  Conclusions

    a.  There  is no doubt  that  the drainage project accomplished
    the purpose of lowering the  water table below the sewers
    within a two block area, but no definite criteria was established
    by the project so that formula  could be set  up for future projects.

    b.  The cost for installing pumping stations throughout the
    City of Meridian would be prohibitive in cost.  It would be
    cheaper to build a holding lagoon or separate lagoon system
    to take care of the surplus irrigation water that infiltrates
    into the sewer lines .
                               - 6 -

-------
II.  DESCRIPTION OF PROJECT AREA

    1.  Location
        The City of Meridian is located in Southwestern Idaho, 8 miles
    West of Boise,  Idaho.  See Figure 1.  It is the center of a farming
    area and known as the  "Heart of The Dairy-land" .   Meridian has a
    population of 2146 in accordance with the 1965 special census.
    The topography of the area slopes to the northwest draining towards
    the Boise  River which is four miles  north of Meridian.  The ground
    in the Boise Valley is somewhat  uniform in its  geological formation.
    There are generally  3 to 4 feet of rich top soil, then 6 to 18 inches
    of caliche hardpan; then gravel and sand strata to at least 50 feet.
    The project area is in the  southeastern part of Meridian.  Bounded by
    Bower Avenue on the north; Meridian Street on the west;  Cottonwood
    Avenue on the south; and East 3rd on the east.  This area is 3 blocks
    square. See Figure 2.

    2.  Climate
        The climate in general may be described as dry and temperate,
    with sufficient  variation to be stimulating.  Summer maximums
    generally are reached in late afternoon followed by rapidly falling
    temperatures after sunset.

        The normal precipitation pattern in  the Boise Area  shows a winter
    maximum  and a very pronounced  summer minimum. The greatest
    24 hour precipitation was  2.24 inches on June 11-12, 1958.  The
    average annual rainfall is 12 inches .  During the year June,  1967,
    to June,  1968,  the major periods  of rainfall were  1.0 inch in June,
    1967; 0.4 inch in October 1967;  4.0 inches snow and rainfall between Jan.
    1, 1968,  and April 1, 1968; and  the balance of 2.1 inches fell at odd
    times during the year for a total  of 7 „ 5 inches.

    3.  Irrigation
        The irrigation season in the Meridian Area starts in the middle
    of April and runs to the middle of October. Generally the water is
    distributed to the area  in a main canal „  From the main canal
    laterals lead out to the various areas, usually  in the street right-
    of-way or alleys.  The property owners  take their water out of the
    laterals for their particular property.  Generally it is done on a
    local weekly distribution plan, depending on the  property area.  By
    mutual agreement, days of the week may be exchanged or if it rains
    for a few  days  seme people  may  not irrigate. Thus the surcharge of
    ground water has no particular predictable pattern. This was in
    evidence  at the cbservation wells which would have the local water
    table rise during the days of irrigation and then gradually subside
                                    - 7 -

-------
until the next irrigation rotation.

4.  Sewage Collection, Treatment and Disposal at Meridian
    Most of the sewers in the residential areas were constructed
during the W.P.A. days and were not well constructed„  The sewers
are mainly vitrified clay tile.  Over the years since 1930"s the
ground water has raised and lowered several times in the gravel
and sand formations, leaching out the fines from the gravel causing
voids; n the strata which resulted in unequal settlement of the pipe,
causing some of the joints to open. Whenever the water table rose,
the water infiltrated into the sewers.

    The City of Meridian Sewage System consists cf several 8 inch lat-
erals  feeding into  12 & 15 inch collector sewers, which eventually
empty ito a 21 inch trunk sewer that runs Northwest into a secondary
treatment plant Northwest of the City Center.  The effluent from the
sewage plant flows into Five Mile Creek which runs northwesterly
thru the area to the Boise River. The Sewage Plant is designed for
a flow of 2,160,000 gallons per day.  The treatment plant takes
care of the sewage treatment during the winter months, but during the
summer months there are some flows of 3,620,000 gallons per day.
The extra flow is a result of the infiltration of ground water during
the irrigation season.  As a result cf this heavy infiltration, a
great  deal of untreated sewage has to bypass the  treatment plant
and flow into Five Mile Creek. Five Mile Creek meanders north-
westerly through farming area to the Boise River,  which  eventually
empties into the Snake River near Parma,- Idahc .  On August 24,
1968, as much as  1,460,000 gallons per day bypassed the sewage
treatment plant.

5.  Problems in Operating The Combined Sewer System
    The sewage plant is designed for a-maximum  flow of 1500
gallons per  minute (2 ,160,000 gallons  per da/),  During the
irrigation period between April 15 and October 15  each year the
infiltration into sewer commences to build up until a peak of
almost 3,620,000 gallons per day  flows to the plant.  The
sewers are not designed as a combined sewer, but due to poor
original construction, there are open joints and poor house
connections, as well as,  pieces of vitrified clay  pipe broken out
of the pipe line. As the townspeople start their irrigation, the
arounr'-vater leva! builds up and is soon under a  head which forces
the water into  sewer pipes making a combined sewer cf the lines.
In some .. f the 8 inch lines that have a normal flow of 1 to 2 inches
during winter mortiis the pipe is entirely full in the middle of the
irrigation period.
                                - 8 -

-------
        The sewage plant, of course, is not designed to take a flow cf
    nearly 3,620,000 gallons per day; so the excess of 1,460,000
    gallons is bypassed into Five Mile Creek which has a flow of
    20-30 c.f.s. during the summer months. This stream flows north-
    west to the Boise River and adds to its pollution.

        It can readily be seen that if some method could be devised to
    prevent the irrigation water from infiltrating into the sewers, the
    load on the sewage plant would be substantially reduced.  One
    method would be to dig up the sewers and relay them or lay a
    parallel line.  This cost would be prohibitive in the paved streets.
    Another method to reduce the infiltration would be  to lower the
    water table below the  sewers by the operation of a pumped well.

III. PROJECT  CONSTRUCTION

    1.  Production Well
        Bids were advertised on the drilling of a 24-inch diameter well
    to 100 feet as shown on Figure 3 and bids were open on October 26,  1967.
    The Contract was awarded to Witt & Sons Drilling  of Caldwell, Idaho.  The
    final well was 80 feet and cased 81.6  feet. The casing was perforated from
    9 to 72 feet.  The perforations were 1/4 x 5 inches spaced 9 inches
    horizontally and 5 inches apart  vertically.   The well was developed and
    gravel packed from November 30,  1967, until December 21, 1967.  The
    well was tested for a period of 16 hours.  The first day the well was
    tested at a flow of 300 g.p.mto 1,000 g.p.m. with an 8 inch turbine
    pump with 60 feet of column. The static water level was 5 feet below
    the top of casing.  The pumping level was 31 to 34 feet below the top of
    casing which corresponds  to a draw down cf 26 to  29 feet. At the end
    of the 16 hour test the pumping rate was 913 g.p.m. with a draw down
    of 29  feet. The static water level was  6.5 feet below casing at termin-
    ation of pumping. The log of the well  is shown on Figure 3.

        Bids were advertised and opened on April 9 , 1968 , for a vertical
    turbine pump to pump 500 g.p.m.  This was the type of pump and
    the capacity specified after a study of the test well data.

        The  specifications for the operating conditions of the well were
    as follows:

         1.   Inside diameter of well - 24 inches .
        2.   Depth of Well - 80 feet.
        3 .   Static water level below topwell - 5 feet.
        4.   Pumping level below topwell - 40 feet.
        5 .   Pumping head above top of well - 10 feet.
                                   - 9 -

-------




Q
n














t
IT





$
^
t
o
1
in
§>
vL
V
I.
1
I.
^
(9
»i
*i




«!



_
0)
0
*
J3
J>
^
X
10
£
lo;
S
*
Perforated
2G" Hole
24' Caeins _•


*'*>?',*?•• '-'•.'***.
r+'^V9-- *" "• ^-r
%*&,*. *#
9 ~*> -JSvr" ?. ^ ^*?-i
->V-:"'"^-"V^>^V?%"\-::
^jS
•_'.*." v * * ' . * -
,**''*•* >
,*. * * **,*". -," -\. * t'\* **
J


V >


y— Ground Surface











wen. CROSS SKCT/OI
-"
-
          REV. 4/Z4/C9
HOFFMANN £ FIBKE  CONSULTING ENQINEB
 SSOO KOOTCNAI STREET     BOISE, IDAHt
 9/7 Om AVENUE        LEWI9TON,
Not fo Soate                SEPT. Aft
                       -10-

-------
    6.   Total pump head - 50 feet.
    7.   Capacity of well - 500 g.p.m.
    8.   Power characteristics - 220 V.,  3 phase,  60 cycles.
    9.   Normal rotative speed -  1760 R.P.M. maximum.

A venturi type,  direct acting controller, water level indicator and
appurtenances were included in the bid.  A recording meter to
indicate the depth of water in the well, with a shut off control  at
40 feet was also specified.  It was desired to control the flow  from the
pump, if required, so that the water table would be kept just below the
level of the lowest sewer in the study area.   Mayne Pump  Co., of
Boise, Idaho, was awarded the Contract.  See Figures 4 & 5.

    The construction  of 812 feet of 8 inch Transite pipe  and a pump pit
were constructed by force account by the City of Meridian forces.
All construction work  was completed on June 23rd,  1968.

    The pump was started on June 26th,  1968, at 200 g.p.m.

2.  Observation Wells
    Four observation  wells were constructed prior to the starting
of the pump on June 26, 1968 ,  as shown on Figure  6.  These wells
were constructed by digging holes approximately 14 to 16 feet deep,
installing a 6 inch corrugated pipe and back filling with  gravel.  Except
for the top 2 to 3 feet, the 6 inch observation well  pipes were in gravel.
The wells used finally are Nos. 2,3,4 and 6.  Well No.  53s  shown
on Figure  2 is a drainage well owned by the Nampa Meridian Irrigation
Company that is next  to Nine Mile Draw and pumps directly into it.
It was mutually intended to use this well as  an observation well, but
it was inconvenient to obtain access to measuring the water depth
because of the construction of the unit, thus  this observation well was
abandoned.  Wells Nos. 2, 3 and 4  were constructed Sept. 18, 1967.
Well No.  6 was constructed June  20, 1968.  The depth of water in wells
Nos. 2,3  and 4 were measured by means  of electrical resistance
measuring device. Depths to water were measured weekly prior to use
of recording meters .   Recording meters  were  the Belfort Co. Catalogue
No. 5-FW-4*and were installed June  1, 1969.

    The location of the  observation wells from the  pumped well is
as follows:

*  Use of product and company names is  for identification  only and
   does not constitute endorsement by the U.S. Department of  the
   Interior or the Federal Water Pollution Control Administration.
                               - 11 -

-------
Existing
         Of  PUMP   PIT
                                    FIGURE A
      HOFFMANN- P/SKE CONSULTING ENGINEER
      2SOO KOOTENAI STJfffT    BOISE. IDAHO
      9f7  «™ AVENUE         LEWI9TON,
           Sco/« * 9&'- t'-O'        Apr.

            -12-

-------
3ECTIOM    THRU    PUMP   PIT
C< ?j*'/ «r
T,jt>ing-~-
                        -"*'?• 'o
                               Dt-ot/n  to dispose of eur-fy/uo
                                  in pit 09 w+//<*9 f~
                                              m/ in
                                                     FIGURE 5
                      HOFFMANN ~ FtSffE   CONSUL TING £HG/fffSKS
                      SSOO KOOT&NAI 3Tf?££T      DO>3E,I&A.HO
                      7/7 OTH AVENUE     _  /  ^LfWISTON, IDAHO
                                Sc&te • •*/< '*l'-O"    Apr

                             -13-

-------
                       BZLFORT RECORDING METER
Ground Surface
WS&Xf/////fi&yW//A






X
vL



y///
Vsi
^


5
C9
10
i
0*


c*JiVjL
1

•„*' * *
* ' " •*
* H*




^ * . t >J
n
LJ

- ; :

V
;.' •


5
/
/
/
*** >
4-1
. LJ .^ 	 Z4'X?4'XG~ Concrete Base
[ . ^^:>:-^^^^//A^^^
.'^•'"i *..'.'«
;-."•-". --...«•;
/-/
-------
See Figure 2.

      Observation Well No.        Distance From Pumped Well (feet)
            2                                688
            3                                630
            4                                769
            6                                 98

Other data on the Observation Wells is as follows:
                                             Elevation Water Level
                                               6/28/68 and
  Observation                   Elevation    Zero Elevation
   Well No.      G D Elevation  Bottom Well    on Guage	
     2               2610.83      2598.08          2600.98
     3               2605.59      2593.79          2600.09
     4               2606.01      2596.16          2603.66
     6               2601.96      2590.51          2598.76

All data is on U.S. Coast & Geodetic Control.

The level of water in each well was plotted  weekly so that a study
could be made when the water table was below the grade of the
sewers in the vicinity of  the wells.

3 .   Flow-Measuring Systems
     Several flow measurements were made in the study.  A
Leopold-Stevens type "F" recorder  * was installed at M.H. #5 to
indicate the depth of flow in this manhole which was indicative of
the flow of sewage in the area under study.  Some troubles were
encountered in the function of the unit and as a result there were
some blank periods of recording.

     The existing recording meter at the sewage plant was used to
record the amount of  sewage flowing through the sewage plant.
Since the  pumps to the primary clarifier could only handle 1500
g.p.m.  (2,160,000 gallons per day) any flow in excess would
bypass the sewage plant  and discharge into Five Mile Creek.

     The flow on Five Mile Creek was measured by means of a staff
gage a hundred yards below the sewer  out fall.  The flow in the

*  Use of product and company names  is for indentification only and
   does not constitute endorsement by the U.S. Department of the
   Interior or the Federal  Water Pollution Control Administration.
                               - 15  -

-------
    creek was calibrated by a current meter and flow curve established.
    The minimum measured flow was about 10 c.f.s. and the maximum
    flow about 45 c.f.s.  The B.O.D. was found to be about 55 p.p.m.
    during the low winter flows and 200 p.p.m. in the high summer flows.
    Suspended solids were 32 p.p.m.; total solids about 627 p.p.m.; and
    the bacteria count was 20 m.p.n.  in March, 1968.  The floating
    materials consist of grass , twigs , paper, and other debris . There
    is a healthy growth of water crest, lillies and grass along Five Mile
    Creek at waters edge.

IV.  PROJECT OPERATION

    1.   Initial Pumping Period
         The initial pumping started on June 26th, 1968, and the pump
    was set at 200 g.p.m. and run until July 17, 1968. The water in
    the well would drop until the people in the immediate area would
    start irrigating.  This flood irrigating would cause the level in the
    wells to rise and then subside after irrigating.  Actually there was
    no true  pattern as to how the neighborhood irrigation would affect
    the water level in the wells.  To try and use the formula developed
    by Theis, Wenzel and Jacob produced such erratic results due to
    the surcharging of ground water by surface irrigation,  the idea was
    abandoned.  The curves indicating the lowering of water table
    were plotted on logarithmic scale, but no data could be obtained
    from them that was of any  value except that over a long period
    of time  the ground water was dropping. The cost for pumping
    200 g.p.m.  was $1.33 per day of 24 hours.  See Figure 7.

    2.   Intermediate Pumping  Period
         On July 17th, 1968, the pumping capacity was changed from
    200 g.p.m.  to 350 g.p.m.  This was continued until August 7,  1968.
    The same trouble was encountered at this pumping capacity because
    the water in observation well would fluctuate, but at the end of the
    period there was a definite decline in the water level.  There really
    was no  definite period when the ground-water level would stabilize;
    so it was decided on August 7th to increase the pumping capacity to
    the maximum, which at the existing water table elevation was
    665 gallons  per minute. The cost for pumping 350 g.p.m. was
    $ 1.54 per day of 24 hours. See Figure 8.

    3.   Final Pumping Period
         On August 7th,  1968,  the control valve was opened to maximum
    capacity and was kept at this maximum until March 11, 1969, when
                                   - 16 -

-------
it had to be turned off for a ten day period so the Nampa Meridian
Irrigation District could clean the Canal into which the pumped
ground water was discharged.  During this pumping period the ground
water level varied due to irrigation, rain, and snow fall.  Each of
these would recharge the ground water temporarily. After a few days
of pumping the ground water level would return to the level prior to
the temporary distrubance.  The cost for pumping maximum capacity
570-660 g.p. m. was $1.75 per day of 24 hours.  See Figure 9.

    From the performance curve of the Johnson Pump * the following
is a table which shows the amount pumped and the level of water in
the well casing:

    Pumping Capacity for Given Ground Water Depth Below Pump
                                                           GPM
Lift in Well   Head Loss Above Ground  Total Dynamic Head   Pumping

    50                10                  60
    40                10                  50              570
    39                10                  49              580
    38                10                  48              585
    37                10                  47              590
    36                10                  46              600
    35                10                  45              605
    34                10                  44              610
    33                10                  43              615
    32                10                  42              620
    31                10                  41              625
    30                10                  40              630
    29                10                  39              635
    28                10                  38              640
    27                10                  37              645
    26                10                  36              650
    25                10                  35              655
    24                10                  34              660
    23                10                  33              665
   Use of product and company names is for identification only and
   does not constitute endorsement by the U.S. Department of the
   Interior or the Federal Water Pollution Control Administration.
                               - 17 -

-------
1000
IQOOO

-------
       (000
TIME SINCE
PUMP  STARTED
   10,000
IN  MINUTE'S
FIGURE 8

-------
too
1000

-------
    During the months of January, February and March the well
capacity was varying due to recharge from rain and snow fall.

    At the date of shutting off the pump for ditch cleaning, the
water table was below each of the observation wells, just being
at the bottom of Well No. 4.

    The following is a table showing the zone of influence of the
well in line with the observation wells .  See Figures  10,11 & 12.

Line of Observation Well   Distance From Well to Zero Influence (feet)

         6-2                                  1000
         6-3                                  3500
         6-4                                  1500

4.  Presentation of Data

    Figure 13 indicates graphically the results of ail the field data
accumulated.  Some  area data is missing due to malfunction of the
recording device or recorder missed collecting data on schedule.

    a.   Observation Wells
         The  first series of 4 plottings indicates the rise and decline
    of the water levels in  each of the four observation wells over
    the period of study from June 26,  1968, to March 11, 1969.
    The vertical scale indicates the drop in feet from the water
    level in each observation well from the initial pumping start
    of June 26, 1968. The bottom of each well is plotted as the
    lowest point in  each well.  It was calculated that when  the
    water table in the wells reached the bottom, the  sewers  in the
    area would be above the water table.  The horizontal ordinate
    represents the date of the recording.

    b.   Flow in Manhole No. 1
         This  chart records the flow in Manhole #5  which is
    indicative of the total flow in the sewers from the project area.
    Due to malfunction of  the recording equipment some data is
    missing.  The vertical scale represents flow in gallons per
    minute .  Horizontal scale shows date.

    c.   Flow in Five Mile Creek
         A staff gauge was placed below the  sewage plant to record
    the depth of water in Five Mile Creek. The creek flow had
                                - 21 -

-------

-------
     10
DISTANCE  FROM  PUMPED
       100
WELL IN FEET
                                                                          1000
FIGURE  fl

-------

-------
        been calibrated for various depth by flow meter and curve plotted
        for the station.  The vertical scale indicates the flow in Five
        Mile Creek in cubic feet per second and the horizontal scale the
        date.

        d.  Flow thru Sewage Treatment Plant
            This  graph is  a record of flow in sewage treatment plant from
        June 1, 1967, to March 11, 1969. The  vertical scale shows
        flow in gallons per day.  The maximum flow through the treatment
        plant is 2,160,000 gallons per day and  any flow larger than this
        means the surplus has to be bypassed.

        e.  Domestic Water Pumped
            This  is a daily record of domestic water pumped from the
        four wells. The vertical scale is in hundreds of thousands of
        gallons per day.  The horizontal scale represents the date.

        f.  Ground Water Pumped
            This  graph indicates the periods of pumping the drain well
        pump for 200 g.p.m.; 350 g.p.m. and maximum capacity of pump.

        g.  Irrigation Season
            This  plot represents the irrigation period for the time of
        the project study.

        h.  Precipitation
            This  graph represents the precipitation daily for the period
        of the study.  The vertical ordinate is inches of precipitation.

V.  ANALYSIS OF DATA

    1.  Observation Wells
        A general observation of each of the curves for the wells shows
    that the water in each  dropped from the initial day of start of the
    pump June 26,  1968, until the date of ending the test March 11, 1969.
    It can be readily seen that the local irrigation program effects the water
    table to such an extent that no real correlation by formula (Theis,
    Wenzel, Jacob) could be obtained from the available data, but all
    cases the water table receded to the bottom  of the observation wells.
    Well No.  2 reached the bottom on August 25th, 1968; Well No.  3 on
    June 4, 1969;  Well No. 4 on Nov. 28, 1968; Well No. 6 as early as
    August 13, 1968.  Well No. 6 was affected by rainfall and snow
    melting period in January and February 1969. Well No.  3 was affected
    by the rainfall and snow in January and February.  When the water  level
                                    - 25 -

-------
reached bottom of wells No. 2 and No.  4 there was a rise above the
bottom.  It can be  seen that the pumps must continue all winter to keep
the water table below the sewers or when they are shut off in winter the
water table would rise because of rainwater and snow melt penetrating the
gravel strata raising the water table.

    The  water table at any time is not the same on all observation
wells which indicates that due to the variable impervious hard pan
strata, probable clay barriers, the water table is not the same
throughout the project area. From this study it would not  be possible
to predict what would happen in other areas of the City as there is no
correlation between the effects of pumping on each of the observation
wells, except that eventually if pumped long enough the  water would
be lowered below the invert of sewers.  The pumping capacity of the
well should be, ideally, that it could be set so that it would keep the
water table below the sewers in the area under study.  I  would
recommend a variable speed motor with controls to keep the water
table just below the deepest sewer.  In our study a constant speed
Motor of 1750 R.P.M.  was used to produce 500 g.p.m. under total
pump head of 50 feet.  The pump was set wide open on August 7, 1968,
and was  still pumping at full capacity on March 11, 1969. The flow varied
from 620 g.p.m. to 665 withatotal head varying from 43  feet to 33 feet.

    The  water was discharged into a drain ditch by agreement with
the Nampa Meridian Irrigation District.  This water was  put to
useful irrigation use as the bacteria count was low.

2.  Flow in Manhole f 5

    The  records on flow in Manhole No. 5 were poor at certain times
during the test period. The recorder was found to be rubbing against
some supports; so that the recordings were not correct.

    The  maximum water table is generally reached during September each
year and remains practically static until through December when it
starts to recede.

    The  graph shows that the flow went from 200 g.p.m. in the
end of March,  1968, to a high of 790 g.p.m.  in first of July, 1968.
After the pumping started on June 26, 1968, the flow in the sewer at
Manhole No. 5 receded to 400 g.p.m. in first part of September and
diminished to around 220 g.p.m. in October.  Thus the pumping
did have some effect.
                               - 26 -

-------
    During the winter months of December,  1968  - January, 1969,
the flow increased again, but this was affected by rainfall and
melted snow entering the gravel strata and infiltrating into the
sewers.

3.  Flow in Five Mile Creek
    The chart on flow in Five Mile Creek  shows that during the
winter months and early spring  the flow is down to 10 c . f .s .  and
gradually rises as the area enters the irrigation season and
irrigation is started. It acts as a drain for the area and surplus
water flows into the Creek.  It  reached a high of 45 c.f.s.  in
September and receded to 20 c.f.s. in December, 1968, rising
and falling during the winter from rain and snow melt.  During
the summer months  there is  enough flow to dilute  the treated  sewage
and give some dilution to the 1,150,000 g.p. d. of untreated
sewage  bypassed from June  to September when this untreated
sewage  is added to Five  Mile Creek.

4.  Domestic Water Pumped
    The domestic water supply for Meridian varies from minimum
200,000 g.p.d. during the winter months to 700,000 maximum
g.p.d. during summer months.  It can be noted during rainfall
period in the  summer the water  use drops on days of precipitation.
The amount of water entering sewers from  domestic use rises  during
summer  months.  Thus during summer months there are major
contributions to sewers  from both irrigation and domestic water waste.

Records  The area of influence is on an average about 1000 feet
from pump location. This would mean many wells in the entire City
area to lower the water table entirely below sewers. This area is about
3 city blocks square. The initial capital cost of the project was
about $15,000.  The pumps  should last 20 years before replacement
or this would be at  a cost of $750. a year, per unit. The power
cost per day of $1.75 per day is negligible for benefit derived.

5.  Irrigation Season
    The irrigation season runs  from April  15 to the first week in
October. The flow  through the  sewage plant shows the influence of
the irrigation water. A general schedule for each area is set  up  for
irrigation, but it is greatly affected by the whims  of the users,
precipitation,  and other factors.  Due to these variable factors,  the
actual surcharge of ground water is difficult to predict with so many
variables.  Actually if the City of Meridian decides to install pumps
in the balance of the City to lower the water table I do not believe
that any data was obtained from this  study to formulate a definite
                                - 27 -

-------
 pattern of action in other areas. The zone of influence varied in
 a line from the pump to each of the observation wells.  The geology
 of each area would have to be studied, as well as the irrigation
 program, drain ditches in the area.   There is no doubt that pumping
 will lower the water table, but each  area would have its own
 peculiarities  and I would recommend a study of each area  with a
 variable speed motor pump to determine what capacity pump would
 best suit the  local conditions.

 6.  Daily Precipitation
     The daily precipitation chart indicates the rainfall for the full
 period of the  study.  The records indicate that the year 1967 was
 a dry year with 7.68 inches; the year 1968 was a relatively wet year
 with 13.08 inches  rainfall.  Actually the month of August  1968 was a
 wet month. Also there was quite a bit of precipitation during November
 and December, 1968, and January and February, 1969, were real
 wet months.

     During the winter months  of December, 1968, and January-
«. February, 1969, the heavy rainfall and snow melt affected the level
 in the observation wells as well as the total daily flow through the
 sewage plant.  In  addition to irrigation water, rain water  and snow
 melt penetrates the ground water strata.
                                 -28 -

-------
 PAGE NOT
AVAILABLE
DIGITALLY

-------
I BIBLIOGRAPHIC:  City of Meridian, Idaho
j Sewer Infiltration Reduction by Zone Pumping - Hoffmann anc
 Fiske-FWPCA Publication DAST 9-1969.                       1

 ABSTRACT:  The intent of  this project was to demonstrate
| the reduction of ground-water infiltration into sanitary
 sewers by pump down of the water table in the sewer area
| assuming the geology, precipitation and local irrigation
; practices were ameanable  to rapid and wide zones of influ-
| ence.  The water table was lowered below the sewer and re-
' duced the volume of flow  to the treatment plant.  The
| water table was not lowered uniformly.  For 1^0 square
 blocks 70 pump units would be required at an average cost
| of $UO,000 per unit with  a total power bill of $122-50 per
; day.  This is not economically favorable when compared
Jwith other corrective measures.  This report was submitted
1 in fulfillment of Grant No. 29-3DA-2.

; KEBirrOCna^iircf~Crby~ol1~Meridian,"Idaho"       " "      ~ ~"
| Sewer Infiltration Reduction by Zone Pumping - Hoffmann and
', Fiske-FWPCA Publication DAST 9-1969.

 ABSTRACT:  The intent of  this project was to demonstrate
|, the reduction of ground-water infiltration into sanitary
 sewers by pump down of the water table in the sewer area
(.assuming the geology, precipitation and local irrigation
;practices were ameanable  to rapid and wide zones of influ-
I ence.  The water table was lowered below the sewer and re-
 duced the volume of flow  to the treatment plant.  The
| water table was not lowered uniformly.  For ikO square
 blocks 70 pump units would be required at an average cost
| of $^0,000 per unit with  a total power bill of $122.50 per
 day   This is not economically favorable when compared
|;with other corrective measures.  This report was submitted
;in fulfillment of Grant No. 29-IDA-2

•BIBLfoGRAFHIC: -~Ci-ty~of"lferidlan7 Idaho
|,Sewer Infiltration Reduction by Zone Pumping - Hoffmann an<3
 Fiske-FWPCA Publication DAST 9-1969.
I
 ABSTRACT:  The intent of  this project was to demonstrate
| the reduction of ground-water infiltration into sanitary
 sewers by pump down of the water table in the sewer area
| assuming the geology, precipitation and local irrigation
 practices were ameanable  to rapid and wide zones of influ-
|ence.  The water table was lowered below the sewer and re-
 duced the volume of flow  to the treatment plant.  The
(water table was not lowered uniformly.  For lUo square
 blocks 70 pump units would be required at an average cost
|of $UO,000 per unit with  a total power bill of $122.50 per
 day.  This is not economically favorable when compared
(with other corrective measures.  This report was submitted
 in fulfillment of Grant No. 29-IDA-2.
"ACCESSION NO.'

KEY WORDS
              I
  Infiltra-
   tion       j

  Volume Re-  1
   duction

  Surcharging

  Zone-pump-
   ing        |
ACCESSION No.
              i
KEY WORDS

  Infiltra-   :
   tion       I

  Volume Re-  I
   duction

  Surcharging

  Zone-pump-
   ing        I
ACCESSION No.

KEY WORDS

  Infiltra-
   tion

  Volume Re-
   duction

  Surcharging

  Zone-pump-
   ing
                                                                        GPO 882-989

-------