6EPA
           United States
           Environmental Protection
           Agency
           Office of Water      July 1984
           Program Operations (WH-546)
           Washington DC 20460
Independent
Physical-Chemical (IPC)
Treatment of
Municipal Wastewater
           Design and Operations
           Feedback

-------
INDEPENDENT PHYSICAL-CHEMICAL (IPO TREATMENT
           OF MUNICIPAL MASTEWATER
        FEEDBACK TO DESIGN/OPERATIONS
                     BY
             ROY F, !''ESTON, INC,
                 HESTON !-'AY
      WEST CHESTER, PENNSYLVANIA  19380
               PROJECT MANAGER
               JOYCE E, LEMMON
           CONTRACT No, 68-01-6737
                  JULY 1984

    U,S, ENVIRONMENTAL PROTECTION AGENCY
       MUNICIPAL CONSTRUCTION DIVISION
            WASHINGTON, D,C,  20460

-------
                        TABLE OF CONTENTS


Section                      Title                          Page

         SUMMARY                                            S-l

 1.0     INTRODUCTION                                         1

 2.0     PROCESS DESCRIPTION                                  2

         2.1   Process Components                             2
         2.2   Problems with IPC Treatment Plants             2

 3.0     PROBLEMS AND REMEDIAL MEASURES ASSOCIATED WITH
         THE LIME HANDLING SYSTEM                             6

         3.1   Lime Loading and unloading                     6
               3.1.1   Problems                               6
               3.1.2   Remedial Measures                      7
         3.2   Lime Storage and Dry Feeders                   7
               3.2.1   Problems                               7
               3.2.2   Remedial Measures                      8
         3.3   Lime Slaking                                   8
               3.3.1   Problems                               8
               3.3.2   Remedial Measures                      9
         3.4   Lime Slurrying                                10
               3.4.1   Problems                              10
               3.4.2   Remedial Measures                     10
         3.5   Lime Slurry Transport                         11
               3.5.1   Problems                              11
               3.5.2   Remedial Measures                     12
         3.6   Lime Slurry peed                              13
               3.6.1   Problems                              13
               3.6.2   Remedial Measures                     14

 4.0     PROBLEMS AND REMEDIAL MEASURES ASSOCIATED WITH
         THE TERTIARY FILTRATION SYSTEM                      15

         4.1   Filtration Cycle                              15
               4.1.1   Problems                              15
               4.1.2   Remedial Measures                     16
         4.2   Backwash Cycle                                17
               4.2.1   Problems                              17
               4.2.2   Remedial Measures                     18
                                11

-------
                        TABLE OF CONTENTS
                           (continued)
Section                      Title                           Page

 5.0     PROBLEMS AND REMEDIAL MEASURES ASSOCIATED WITH
         GRANULAR ACTIVATED CARBON SYSTEM                     20

         5.1   Adsorption Process                             23
               5.1.1   Problems                               23
               5.1.2   Remedial Measures                      24
         5.2   Carbon Contactor                               26
               5.2.1   Problems                               26
               5.2.2   Remedial Measures                      27
         5.3   Carbon Transport System                        29
               5.3.1   Problems                               29
               5.3.2   Remedial Measures                      29
         5.4   Backwash System                                30
               5.4.1   problems                               30
               5.4.2   Remedial Measures                      30
         5.5   Regeneration System                            30
               5.5.1   Problems     •                          30
               5.5.2   Remedial Measures                      30
         5.6   Instrumentation and Control System             31
               5.6.1   Problems                               31
               5.6.2   Remedial Measures                      31

 6.0     SUMMARY OF FINDINGS AND CONCLUSIONS                  32

         REFERENCES                                           35

APPENDIX A     UNIT PROCESSES AND TREATMENT  PERFORMANCE
               OF IPC PLANTS                                 A-l-

APPENDIX B     LIME HANDLING SYSTEMS:  IDENTIFIED PROBLEMS
               AND SUGGESTED REMEDIAL MEASURES               B-l

APPENDIX C     FILTRATION SYSTEM: IDENTIFIED PROBLEMS
               AND SUGGESTED REMEDIAL MEASURES               C-l

APPENDIX D     GRANULAR ACTIVATED CARBON  SYSTEM:  IDENTI-
               FIED PROBLEMS AND SUGGESTED REMEDIAL
               MEASURES                                      D-l
                                iii

-------
                         LIST OF TABLES
Table No.                     Title

   1        Problem Summary of independent  Physical-
            Chemical (IPC)  Treatment Plants Visited
            During the AWT  Effectiveness  Project               4

   2        summary of IPC  Facility Performance               21
                         LIST OF FIGURES


Figure No.                   Title                          Page

   1        Typical Advanced IPC System Flow schematic        3
                                IV

-------
SUMMARY

This report presents the results of an investigation of 11  inde-
pendent Physical-Chemical  (IPC)  Treatment Plants,  conducted  as
part of a  nationwide advanced waste  treatment  (AWT)  effective-
ness evaluation sponsored  by  the U.S. Environmental  Protection
Agency  (U.S.  EPA).  The  results  of the  investigation  indicated
that virtually all of these plants are experiencing difficulties
with one or more of their treatment processes.

IPC treatment, as the name implies, involves the  utilization  of
only physical and chemical treatment processes  (e.g.,  clarifica-
tion, filtration, carbon adsorption, ion-exchange, etc.) for  the
treatment  of wastewater.  This  document briefly outlines  the
problems encountered at  IPC plants and provides  a  limited dis-
cussion of the impacts of these problems  on  the plant's perform-
ance.

Problems associated with  chemical  treatment  of wastewater, spe-
cifically with lime, are related to handling and feeding of this
material, and result  in  poor  process  performance  that adversely
affects the downstream processes.  The granular  activated carbon
(GAC) process,  commonly  used  in IPC  plants, has  been afflicted
with odor  and  corrosion problems associated with hydrogen sul-
fide formation, in  some  instances,  the process has not attained
the degree  of  soluble organic material  removal anticipated.  In
addition, the granular  tertiary filtration  process has  not  met
design  performance  criteria.  This  latter problem  has  occurred
due  to  the inability of this process to  cope  with inconsistent
effluent quality  from upstream  processes, and  the  lack  of ade-
quate flexibility in handling varying flow and  solids loadings.

Potential  remedies  to  the problems identified by this investi-
gation are also outlined in this document. These remedies should
be  applied  only after an  engineer experienced with  the design
and operation of IPC processes has thoroughly evaluated a facil-
ity  to  determine  which  solutions  are practical and cost-effec-
tive.
                               S-l

-------
EPA  has  identified  14   IPC  publicly  owned  treatment  plants
(POTW's) operating in the united states (22). This  report  exam-
ines the  performance  of  11  of these 14 IPC facilities,  and  ex-
plores the capabilities and  limitations of the IPC process.  Des-
criptions  of  the  unit processes,  discharge  requirements,  and
performance characteristics for  each  plant are included  in  Ap-
pendix A.

The goals of this report are to:

    •    Identify design deficiencies,  equipment performance  de-
         ficiencies, and operating problems relating to  the  IPC
         process based on information  from site  visits.

    •    Suggest methods  of  improvement  (as related to  design,
         equipment, and  plant operations)  so  that they may  be
         used as  feedback to  the operators of  existing  facili-
         ties.

Performance data  for  this feedback  report  were  collected during
an investigation of advanced waste treatment (AWT) technologies,
as part of a U.S. Environmental  Protection Agency (U.S.  EPA)  AWT
effectiveness evaluation.  Eleven of the 14 identified  IPC plants
in the  united states  were visited,  and their  treatment  process-
es, performance, deficiencies, and problems documented.  This  in-
formation, supplemented with  published data and other available
information, provided the basis  for this report.
                               S-2

-------
1.0  INTRODUCTION

Independent Physical-Chemical (IPC) wastewater treatment systems
typically  include  preliminary treatment  (such  as bar  screens,
comminutor, and/or grit  chamber),  chemical  precipitation,  clar-
ification, granular  media filtration, activated  carbon  adsorp-
tion,  and effluent  disinfection  (chlorination).  Not every  IPC
plant  contains  all of these  processes;  however,  these  are  the
most common components, and will usually be found  in some combi-
nation.

The IPC approach gained  widespread interest in  the  early 1970's
as an alternative  to  conventional  biological  treatment  process-
es.  At that  time  the  eutrophication of  receiving waters  was
identified as a serious  problem caused by  the presence  of  phos-
phorus in synthetic detergents commonly found in domestic waste-
waters. The IPC process  using lime precipitation  was considered
one of the methods  of wastewater treatment for phosphorus remov-
al. The perceived advantages of the IPC  process over biological
processes are summarized as follows:

   • •    More readily adaptable  to variations in wastewater flow
         and composition.

    •    Less susceptible to upsets from industrial  wastes.

    •    Efficient  removal of heavy metals  by  chemical  precipi-
         tation.

    •    Does not require treatment for stabilization of sludge.
         Sludge is dewatered easily and  can  be disposed  of  in
         landfills.

    •    Less space requirements.

    •    Removes phosphorus  from  the  effluent, thus mitigating
         the eutrophication problem.

Based on  the observation of  several IPC  plants, it  appears that
the plants  are  having problems meeting  effluent  discharge  re-
quirements (17)  and are also faced with the high cost of dispos-
ing of large quantities  of  chemical sludge (11).  It  is  evident
that some  of  the  process units  in IPC plants,  particularly  the
granular activated  carbon process,  are not performing as  expect-
ed due to design deficiencies and  improper operation and mainte-
nance.

-------
2.0  PROCESS DESCRIPTION

2.1  PROCESS COMPONENTS

IPC treatment plants are comprised of a combination of different
physical and chemical treatment processes, the selection and or-
der of  which  usually depends on wastewater  influent  character-
istics  and the  effluent discharge  requirements.   There  is  no
standard unit process sequence for IPC plants. However, based on
the information  from the plants  surveyed,  the typical  process
units used in IPC plants are the following:

         Screening.
         Comminuting.
         Grit chamber.
         Chemical precipitation.
         Clarification.
         Tertiary filtration.
         Granular activated carbon with carbon regeneration.
         Chlorination.

in addition,  dechlorination ion exchange and  post-aeration are
also used  in some  plants to  meet  the  site-specific  effluent re-
quirements. The  IPC  treatment process relies  to a  great  extent
on chemical  coagulation and  sedimentation  to remove  suspended
and colloidal solids. Filtration is commonly utilized  as a proc-
ess to  remove the  residual suspended  solids  in the  effluent af-
ter  the clarification  process.  The  granular activated  carbon
system  is  used in  place  of  a biological  process for the removal
of soluble organics.  When  exhausted, the  carbon  with its  ad-
sorbed organics is incinerated in a carbon regeneration furnace.
Of  the eleven  plants  evaluated  for  performance,  six  of  the
plants  have  filtration before carbon  adsorption;  three  do  not
have any filtration systems; one plant has filtration  after  car-
bon adsorption;  and one plant  has filtration both before  and
after carbon adsorption. A  typical  schematic  flow  diagram of an
IPC plant  is shown in Figure 1.

2.2  PROBLEMS WITH IPC TREATMENT PLANTS

The results  of  the AWT  effectiveness  evaluation  (18)  indicated
that there are  many problems associated  with  the  IPC  treatment
technology that adversely affect its  performance. Table 1 pres-
ents a  summary of  these problems as  they  relate   to  the major

-------
                                                  RAW SEWAGE
PLANT
SANITARY SEWER
         ENTRANCE
          MANHOLE
                          ENTRANCE  STRUCTURE
                        COMMINUTORS. BAR  SCREEN
    PLANT

    DRAINAGE
GRIT CHAMBER S PARSHALL FLUME
                                  CLARI
                               FLOCCULATOR
      RECARBONATION TANK
                                          PRE CHLORINATION  FEED
        BYPASS ANY
        OR ALL UNITS
                            MULTI  MEDIA FILTER
                              FILTER WET WELL
                              FILTER EFFLUENT
                                PUMPS
        BYPASS  ANY
        OR ALL UNITS
                                  CARBON
                                AOSOR6TION
                                 VESSELS
                                                     SODIUM HYDROXIDE FEED
                             CHLORINE BLENDER
                                                     BREAK POINT
                                                     CHLORINATION FEED
        BYPASS ANY
        OR ALL UNITS
                               OUTFALL SEWER
                  Source: Lozier Engineers, Rochester, New York

     Figure 1.   Typical advanced IPC system flow schematic.

-------
                             Table 1
     Problem  Summary of independent physical-Chemical (IPC)
Treatment Plants Visited During the AWT Effectiveness Project-1-



Unit
process Component
Lime feed system
Other chemical feed
system
GAC system
Filtration system
Process linkages2


Total
Number
of Plants
8
9

11
6
11
Number
of
Plants
with
Problems
5
3

10
3
5
Percent
of
Plants
with
Problems
63
33

91
50
45
 leased  on  11  operating IPC POTW's in the united states that
  were visited.
 2process linkages  refer  to the  interdependence of unit process-
  es  in  a treatment system.

-------
component process units  in  the system. As  illustrated  in  Table
1, almost  all  of the  plants had  problems  with their  granular
activated  carbon systems.  Three  major  problem  areas  at  IPC
plants have been identified, as follows:

    •    Lime handling system.
    •    Granular activated  carbon system (GAC).
    •    Tertiary filtration system.

in each of these systems, problems are identified,  and the  caus-
es of the problems and the impacts of these  problems  on  the per-
formance of the IPC plant are  discussed.  Remedies  are suggested
for mitigating the deficiencies noted. Special consideration has
been given  to  remedies  that facilitate improvement  of  existing
IPC treatment facilities.

-------
3.0  PROBLEMS AND REMEDIAL MEASURES ASSOCIATED WITH THE LIME
     HANDLING SYSTEM

This section  discusses  the  problems and remedial measures asso-
ciated  with  lime handling systems.  The specific  components  of
lime handling systems discussed are the following:

         Lime loading and unloading.
         Lime storage and dry feeders.
         Lime slaking.
         Lime slurrying.
         Lime slurry transport.
         Lime slurry feed.

A summary of the problems and remedies are given in Appendix B.

3.1  LIME LOADING AND UNLOADING

3.1.1  Problems

Problems  that  occur while  loading and  unloading lime are  the
following:

    •    One of the major problems  experienced  with  loading and
         unloading lime  is  the generation  of lime dust.  Manual
         handling of  bagged lime  is a  source  of  dust  in  the
         loading/unloading area,  in the  case  of  bulk  lime  handl-
         ing,  the  problem of  dust is  primarily attributed  to
         the malfunctioning  of baghouses  installed on  top  of
         lime  storage  bins.  If  the  baghouse  filters  are  not
         emptied  frequently,  they  are   unable  to  collect  the
         dust,  thereby causing dissipation of dust in  the  load-
         ing/unloading  area.

    •    Sharp elbows and bends in  lime  transport piping to  the
         storage bin  are subject  to severe  damage  caused  by
         abrasion,  depending on the type of lime  used  (hydrated
         lime  is generally less abrasive  than quicklime).

    •    Maintenance and repair of  lime  transport  piping is  dif-
         ficult  if the piping  is located at  high elevations  or
         is  otherwise  inaccessible.

-------
3.1.2  Remedial Measures

Remedial actions  that  may be taken to  alleviate  these  problems
are the following:

    •    An efficient  dust collection system  is  essential  for  a
         bulk lime storage bin.  A hood and baghouse installed on
         the top  of  the storage bin should be manually checked
         after every loading  operation  to ensure  that  the  con-
         tents of the  dust  collection  bag are  discharged  back
         into  the storage bin.  shaking the bag  helps  to  dis-
         charge the contents  easily. The  bag  should be  replaced
         periodically.

    •    A  safety valve should  be  provided on  the top of  the
         lime storage bin to  prevent rupture of  the  bin in  case
         of buildup of  excessive pressure due  to malfunctioning
         of the baghouse.

    •    sharp elbows  and bends in dry  lime transport  piping
         should be avoided. Piping  with sweep turns of a  mini-
         mum 3 to 4 foot radius is recommended to reduce mechan-
         ical  wear  and  decrease   resistance  to  flow.  Piping
         should be reinforced with additional  plates  at  bends
         to minimize excessive  wear by  abrasion,  use  of  mate-
         rials with  high abrasion  resistance should be consid-
         ered for bends.

    •    The top  of  the lime storage  bin and transport  piping
         should be easily accessible for maintenance purposes.

3.2  LIME STORAGE AND DRY FEEDERS

3.2.1  Problems

Problems involving lime  storage  and dry feeders  are the follow-
ing:

    •    in lime  storage bins,  the flow of lime  to  the feeders
         is  interrupted by  "arching"  or  "bridging" above  the
         hopper opening. Sudden  "flooding" of  the  feed  hopper
         occurs when the arch breaks.  This problem  is  particu-
         larly common  when  lime  in the form of  fine powder  is
         used. Granular and pebble lime are generally free-flow-
         ing materials.

-------
    •    Clogging of the feed hopper opening and feeder valve in
         the storage bin. This  problem occurs due to  the  entry
         of moisture into the storage  bin  which  causes the lime
         powder to  "cake,"  thereby  preventing free-flowing con-
         ditions.

3.2.2  Remedial Measures

Remedial measures to overcome these problems include  the follow-
ing:

    •    The lime storage bin should have  a conical  bottom with
         a 60°  slope to facilitate easy  flow of material into
         the feed hopper.

    •    A "live  bin"  system or  bin  vibrator at the  bottom of
         the storage bin will prevent  arching and  bridging  of
         lime above the feed hopper opening.

    •    A  volumetric   type of  feeder  is  preferred  over  the
         gravimetric type,  since  the  former  is more  reliable
         and easier to operate and maintain.

    •    A rotary valve  may be  installed between the feeder and
         lime slaker to  prevent  the entry of  moisture  into the
         feeder.

3.3  LIME SLAKING

3.3.1  Problems

The following problems can occur in the lime slaking  operation:

    •    Excessive  mechanical wear  of  grit  conveyors  in  deten-
         tion- and paste-type slakers.

    •    Maintaining airtight  conditions  in  a  slaking  system
         and operating  it under  negative  pressure is difficult.
         Thus, moisture from the slaker travels back  to the lime
         storage bin causing "caking"  of  lime and resulting in
         clogging of feed hoppers.

    •    Probes  used for  indicating  slurry  levels   in  slakers
         malfunction due to encrustation and scaling.

-------
    •    Cleaning of  slakers  for maintenance is a  labor-inten-
         sive operation;  encrustations  of lime  on  tank  walls,
         valves,  and  orifices   normally  have  to  be  manually
         chipped, scraped,  and  removed  from the  slaker.  This
         cleaning problem  is  further aggravated  if some  parts
         of the slaker are not easily accessible.

    •    instrumentation panels  located  on  or  adjacent to  the
         slaker are often covered with dust and grit. This  con-
         tributes  greatly  to  malfunctioning  of  lime   control
         systems.

3.3.2  Remedial Measures

Measures to resolve these problems include the following:

    •    The lime slaker should be sufficiently offset  from the
         lime storage  bin  and feeder to  prevent  the steam  and
         moist lime vapors from  the  slaking  operation traveling
         backwards to  the storage bin.  This measure will  help
         to avoid the problem of  "caking" of  lime in  the  feeder
         and storage bin.

    •    Maintaining the required slaking temperature is  essen-
         tial for complete  hydration of  quicklime.  The  optimum
         slaking temperature range is 175°F  to 185°F.

    •    Water-to-lime ratio  for  slaking should normally  range
         between  3:1  and 4:1  for detention-type  slakers.  How-
         ever,  recommendations  for  optimum  slaking  conditions
         for the  type  of lime used should be obtained  from the
         vendor supplying the  slaker.

    •    Lime slakers should be airtight  and  operate under  nega-
         tive pressure  in order  to  prevent  moisture and  dust
         from entering the work  area or  working backwards  into
         the lime feed  system or lime storage bin.  Aspirators,
         though often  used, have not always been successful  in
         maintaining a negative  pressure.  It is suggested  that
         a fan  be used to draw vapors from the slaker  and  help
         maintain a negative pressure in  the  slaker.

    •    Sonic-type level  sensor systems can be  used  to  avoid
         encrustation problems commonly experienced  with probes.

-------
    •    instrumentation panels and  electrical control  systems
         should be located away  from slakers and preferably  be
         housed separately to avoid  entry  of dust and  moisture
         from the slakers.

    •    Slakers should be located so that they are easily ac-
         cessible for  maintenance.

    •    Spare screw conveyor parts  should be  stored or readily
         available as  replacements because screw conveyors for
         grit removal  are  prone  to  abrasive mechanical  wear.

3.4  LIME SLURRYING

3.4.1  Problems

in most treatment  process applications, lime is  introduced as  a
slurry. In the slurrying operation, slaked  quicklime  or  hydrated
lime is mixed with water and agitated in a covered tank to form
a slurry of  a  concentration  suitable for  feeding (usually 5  to
10 percent by  weight).  Problems associated with lime  slurrying
operations are as follows:

    •    Probes used for level  control in slurry  tanks  are  coat-
         ed with scale and rendered ineffective.

    •    Maintenance of agitator motors, level  controllers, etc.
         in elevated slurry  tanks  is a  problem due to  poor ac-
         cessibility.

    •    severe  abrasion  of  the tank  can  occur if  fiber-rein-
         forced  plastic  (FRP)   tanks  are  used  for  lime slurry
         preparation,  especially when quicklime is  used; hydrat-
         ed lime tends to  be  less abrasive.

3.4.2  Remedial Measures

Measures to  alleviate  problems  in  the lime  slurrying  operation
include the following:

    •    Sonic-type slurry level  sensor  systems are preferable
         to conventional probes that become  encrusted  frequent-
         ly.
                                10

-------
    •    Lime slurry tanks should be covered  to  prevent  splash-
         ing of slurry.  For  the slurrying of powdered hydrated
         lime,  a vent with a dust collection  bag  is  required  to
         trap the dust  generated.  The bag should  be  located  away
         from the  point  where  the lime  enters  the slurry  tank
         and should be  checked  and cleaned regularly.

    •    Lime slurry tanks  should be constructed of  corrosion-
         resistant  metal  and  not of  fiber-reinforced  plastic
         (FRP)   to  prevent  abrasion  problems,  particularly  if
         quicklime is used.

    •    Access should be provided  for  the maintenance  of  agi-
         tators, level controllers, and  other equipment in  the
         slurry tank.

    •    Water  used for preparing  lime slurry  should not  contain
         excessive levels of carbonates, sulfates, or  any other
         ingredients that  could react  with   the  lime to cause
         precipitation  and scaling.

3.5  LIME SLURRY TRANSPORT

3.5.1  Problems

Transportation of lime  slurry presents one of  the most difficult
problems in a lime handling system,  as noted below:

    •    Scaling of  pipes is  a severe  problem  common  in  most
         lime slurry transport systems.  Scaling  may  be  due  to
         the following:

              Leakage  of  air  into pipes  around  the  pump seals
              or through other appurtenances,  carbon  dioxide  in
              the  air  reacts  with lime  to precipitate  calcium
              carbonate as scale on the  inner  walls  of pipes.

              Settling of  solids  from  the lime slurry during
              off cycles.

    •    Scaling and deposition of solids in sharp bends  and el-
         bows  is  very common  in  lime  slurry transport lines.
         Right angle bends  at  the bottom of  vertical  pipes  are
         extremely prone to the deposition of  lime solids.
                                11

-------
    •    Small diameter piping is reported to be one of  the  maj-
         or causes of frequent clogging of lime slurry transport
         pipes in many wastewater treatment plants.

    •    Cleaning of scale  accumulated in lime  transport lines
         is  extremely  difficult and  labor-intensive,   partic-
         ularly when long lengths of metal pipes are  used with-
         out cleanouts.

3.5.2  Remedial Measures

Measures that may be employed  to overcome  these problems are  as
follows:

    •    Lime transport piping should be at least 1-1/2  to 2 in-
         ches in diameter to avoid frequent clogging problems.

    •    Flexible hoses should be used for lime slurry transport
         piping wherever possible. Long straight lengths can  be
         of rigid piping.  Flexible  hoses  have  the  major advan-
         tage of being easier  to  maintain  when  clogging  occurs.
         Agitation of  a  flexible hose can release  plugs caused
         by an air lock or solids deposition in a lime transport
         line. Scale accumulated on  the inner  walls  of  a flex-
         ible lime transport pipe can be removed by  flexing the
         hose, which  is  not possible with rigid pipe.  Flexible
         hoses  are  also  easier   to  replace  than  rigid pipes.
         Transparent/translucent   type  flexible hoses  help  to
         locate  plugs   in  the line   faster.  However,  flexible
         hoses require more supports than  rigid piping.

    •    Lime transport  lines  should be installed  with  minimum
         bends. Sharp  elbows and vertical  runs  should be avoid-
         ed,  "cleanouts"  should be  provided  in  lime slurry
         transport lines  as often as  possible,  particularly  at
         the bottom of vertical  runs to facilitate  cleaning  of
         lime deposits.

    •    Periodic cleaning  of lime  slurry pipelines using  de-
         vices  called  "pigs"  would  help  to maintain  a clean
         slurry  transport  system.   "Pigs"  are  plastic-rubber
         products with  abrasives spirally embedded  in the  sur-
         face.  It  is  moved by water pressure  through the  pipe
         and removes the scale by a scouring or augering  action.
                                12

-------
    •    It is recommended that lime transport lines be operated
         continuously.  Deposition  of solids  and scaling  occur
         when the line is out of service for  only a  few hours.  A
         recycling loop is one of  the methods  used  successfully
         to maintain  continuous operation of  a lime  transport
         system during off cycles.

    •    Provision for flushing  lime slurry transport  lines  is
         essential to  prevent  excessive  build-up  of  scale  in
         pipes, valves, and other parts  of the conveying system.
         If the lime transport  system  does not have a recircu-
         lating loop,  automatic  devices should be  installed  to
         flush the line with water  immediately after each opera-
         tional cycle. If  a loop system  is  not  used,  provision
         should be made  to manually flush  the loop with  water
         after  each  lime feed  operation.  Periodic  flushing  of
         the lines with  corrosion  inhibited  dilute  hydrochloric
         acid to  clean the  residual  scale is desirable to main-
         tain a trouble-free lime transport system.

3.6  LIME SLURRY FEED

3.6.1  Problems

The controlled addition of lime slurry  to a treatment process  is
generally carried out using feed pumps  and control valves.  Prob-
lems experienced with lime slurry feed  systems are as follows:

    •    Scaling  and  clogging  of   pumps  and  metering  valves.
         Clogging  is  particularly  common  when the  feed  system
         is used intermittently.

    •    in pH-controlled  lime  slurry  feed systems,  encrusta-
         tion of the  pH probe (with lime solids and  calcium car-
         bonate  scales)  results  in erroneous  pH  readings  and
         thus improper dosage of lime to the process.

    •    Progressive  cavity-type metering pumps have high  main-
         tenance requirements due to stator wear.

    •    slurry  feed  metering  valves  with  variable  flow  rate
         control are easily clogged  due to lime deposits  in the
         constricted  areas of the valves.
                                13

-------
3.6.2  Remedial Measures

Measures to  alleviate  problems in  the  lime slurry  feed  system
are as follows:

    •    Take-off points for lime slurry  feed  should be located
         on the vertical portion of  transport loops and as close
         as  possible  to  the  point of  application.  Provision
         should be made  for  backflushing  the  take-off  assembly
         for cleaning purposes.

    •    Feed  control  valves  should  be  operated  in  a  fully
         opened or fully-closed mode.  Pinch valves  are  prefer-
         able  for  this  operation.  Constricted  valve  openings
         tend  to clog  due to  scaling  and deposition with  lime
         solids.

    •    The problem of malfunctioning pH probes  due to scaling
         can be solved by alternate use of  two  pH  probes.  One
         probe can be  cleaned  and calibrated while the  other  is
         being  used.  pH  probes  are  to  be  cleaned  frequently
         with dilute  acid and rinsed with-water.

    •    Diaphragm-type metering  pumps provide  better  control
         of  feed  than progressive  cavity   or  other  types  of
         pumps, and are less  expensive  to  maintain.

    •    Rotary cup-type  feeder  or  similar  slurry  feed  systems
         are preferable,  wherever  possible, over  chemical  feed
         pumps  because the latter  are  susceptible  to  clogging
         problems.
                               14

-------
4.0  PROBLEMS AND REMEDIAL MEASURES ASSOCIATED WITH THE TERTI-
     ARY FILTRATION SYSTEM

This section discusses  the  problems  and remedial measures asso-
ciated with the tertiary  filtration system  in  an IPC  wastewater
treatment plant. The filtration system is divided into two oper-
ations, namely, the filtration cycle and  the  backwash  cycle,  in
order  to  separately  address the problems and  remedies  for  each
operation. A summary  of the problems  and remedies is  given  in
Appendix C.

4.1  FILTRATION CYCLE

4.1.1  Problems

Problems that occur during the filtration cycle are as follows:

    •    Media clogging is  a widespread filtration problem  that
         results  in   increased  head  loss  through  the bed  and
         thus  decreases  the  length  of  the  filter  run.  Media
         clogging can result from the following:

              Microbial growth in the filter bed.

              Solids  carryover  from prior  treatment  processes,
              especially when process upsets occur.

              Oil  and  grease   carryover  from  prior  treatment
              processes.

              Precipitation of  calcium carbonate,  calcium  sul-
              fate, calcium hydroxide, etc.  on the  filter  bed
              due  to  malfunctioning of  a  prior  unit  treatment
              process.

    •    Hydraulic surges in influent  flow  to filters caused by
         a  lack  of  flow  equalization  facilities  result  in
         operating difficulties and poor effluent quality.

    •    Uneven spacing of  wash water  troughs  on the  filter bed
         creates differential velocity gradients, causing carry-
         over of sand media during backwashing.

    •    improper design  of the filter underdrain system causes
         migration of filter media to  the underdrains  and clog-
         ging of backwash nozzles.
                                15

-------
    •    Many operators have little or no  training  in  the  oper-
         ation of filtration systems.  This  lack  of  knowledge  and
         training can  cause ineffective  filtration and  inhibit
         operators from making the alterations  necessary to  im-
         prove  filtration   operations.  This  inflexibility  can
         compound problems  during periods of process upsets.

4.1.2  Remedial Measures

Measures that  may be employed to  alleviate these  problems  are
as follows:

    •    The problem of  frequent clogging  of media and  buildup
         of head loss can be reduced by considering the  follow-
         ing measures:

              Judicious selection  of  the  type  of  filter media.
              Multimedia filters  normally   perform  better   than
              conventional  single media sand filters in tertiary
              wastewatef applications.

              Applying a disinfectant, usually  chlorine, to  the
              filter influent to  control microbial  growth in  the
              filter bed. The disinfectant  should  be applied on
              a periodic basis or  whenever microbial  growth  is
              detected.

              The treatment processes  ahead of the  filter should
              be designed to provide better removal of  suspended
              solids. Removal of high concentrations  of carry-
              over solids by filtration systems is  not  cost  ef-
              fective.  The  preceding  treatment process should
              also remove oil and grease prior to  the filtration
              system. Once  coated  on  the  filter media,  oil  and
              grease  cannot  be   removed   by  normal   backwash
              methods.

    •    The problem of  poor  effluent quality  due  to  hydraulic
         surges in  the  influent  to the filter  can  be  mitigated
         by incorporating the following measures:

              influent flow to filters should be recorded and an
              automatic controller should  be  provided  to ensure
              an even flow  distribution among  filters,  in  cases
              where  flow exceeds the design  hydraulic  capacity
              of  the  filters, diverting  the additional  flow to
              a surge  tank should  be  considered  in the design
              of the system.

                               16

-------
              Designing the  filter  system  with  the  option  to
              operate filters in  a  parallel or series mode,  in
              case of increased suspended solids  loading  to  the
              filter due to sudden process  upsets, series  opera-
              tion could help to  meet the requirements for  ef-
              fluent quality. However, additional  filters  would
              have to be provided  to enable operating  filters in
              series.

    •    wash water  troughs  should  be  spaced  uniformly over  the
         filter bed. Leveling of the troughs is critical to fil-
         ter operation and troughs should be checked and adjust-
         ed regularly.

    •    Clogging of backwashing  nozzles due  to  media migration
         can be  minimized by  utilizing  nozzles  fitted  with  a
         protective plate on top.

    •    All operator(s)  who work  with  the  filtration process
         must  be  familiar  with  filtration  technology  and  the
         operation of their  system,  pull knowledge of the sys-
         tem will permit the operator  to make operational  modi-
         fications necessary to improve  the performance of  the
         system. This technical  skill will  be especially helpful
         during periods of  upsets in preceding  treatment  proc-
         esses. The  operator(s) must be  able  to  assess the sit-
         uation, modify  the  filtration system operating  proto-
         col, and,  if necessary,  decide when and what part  of
         the flow should bypass  the filtration system.

4.2  BACKWASH CYCLE

4.2.1  Problems

Problems associated with the backwash cycle are the following:

    •    Backwash systems designed to operate on  the  basis of  a
         single criterion,  either  a  fixed time  interval  or  a
         predetermined head  loss, sometimes result in  improper
         frequency of backwash. For  example,  the backwash  cycle
         may not  be  initiated  until  the  preset  time  interval
         although  the  filter  may  require backwashing  due  to
         high head loss that may have built up.
                               17

-------
    •    if the backwash  rate and/or  duration  is  not  sufficient,
         the bed will not be  thoroughly  cleaned,  conversely,  too
         high a backwash  rate because of an  incorrect setting on
         a backwash system with  no rate-limiting  control  can  re-
         sult  in  media  loss, gravel mounding,  or  gravel dis-
         placement.

    •    incorrect operation  of  the  auxiliary backwashing sys-
         tems, such as surface-water  wash, air  scour, or  subsur-
         face agitation,  can  cause the following  problems:

              incomplete  backwashing  resulting  in reduced filter
              run times.  This problem could occur if the auxil-
              iary backwash system is not  operative  during  the
              initial  fluidization  stage of  backwashing, thus
              causing insufficient removal  of foreign material
              from the bed.

              Loss of filter  media.  If  the  auxiliary air  scour
              is   operated   during   the   second    stage   of
              backwashing when  the wash water  is flowing into
              the  troughs,  the   filter  media   would  be  carried
              over with 'the wash water.

    •    Upstream process upsets can occur because of excessive
         hydraulic loading on treatment  units  that receive back-
         wash wastewater  from tertiary filters.

    •    improper selection of the material of construction  for
         backwash  nozzles  results in corrosion  and  dislodging
         from their support structures  causing inadequate  back-
         washing.

4.2.2  Remedial Measures

Measures that  may  be taken to alleviate these problems  include
the following:

    •    Backwash frequency should be controlled  on  the basis of
         both head loss  and a fixed  time interval, whichever is
         needed first. Effluent  quality  should be monitored  and
         a provision for  manual  override for  backwashing should
         be available to  overcome upset  conditions in the filter
         operation.
                                18

-------
•    Maintaining the  correct  operational sequencing is  im-
     portant  for  effective  backwashing.   The   operator(s)
     should observe  the  filter instrumentation  during  each
     backwashing cycle to ensure that the correct operation-
     al  sequence occurs.  At   a  minimum,  a monthly visual
     check should be made of each filter  cell  for a complete
     backwash cycle to ascertain  that all  systems  are  oper-
     ating correctly.

•    The correct rate and duration of backwashing are essen-
     tial for good filter  system  operation. The  operator(s)
     should frequently check all of the  settings  of the rate
     and timer controls to ensure that they are  appropriate.
     The controls and instrumentation should be  recalibrated
     as  required to ensure that  the system  is  functioning
     properly. The operator(s) should adjust the  rate of the
     backwash flow  to compensate  for the  change  in  water
     viscosity  because  of  changing  temperatures.   The  rate
     should be decreased during the  cooler  part  of the year
     and increased during  periods  of warmer weather so that
     a  comparable  degree  of  bed  expansion  is  achieved
     throughout the year  during backwash.

•    Timer  systems   used  for  controlling   the  duration  of
     backwash should be  adjustable  for  the  total duration
     as well as  the  duration  of  high and low  rate  cycles  in
     backwashing. This design feature builds an additional
     flexibility into the  operation  of the  filter, which  is
     often very helpful in mitigating problems.

•    An  interlock  control system  is recommended  to  ensure
     that  the  designed  maximum  number  of  filters  to  be
     backwashed at any given time is not exceeded.

•    It  is recommended that backwash wastewater  be collected
     in  a surge  tank  and  recycled to other  process units  at
     a controlled rate.  This  will help  to minimize problems
     created  by significant  hydraulic   surges  due  to  dis-
     charge  of  backwash  wastewater  from the tertiary fil-
     ters.

•    Materials  of construction  used for  backwash nozzles,
     underdrains and  their support structure,  and the filter
     walls must  be  compatible with each  other to avoid cor-
     rosion problems  caused by galvanic action and electrol-
     ysis.  Backwash  nozzles  should  be   securely  mounted  on
     the supporting structure.
                            19

-------
5.0  PROBLEMS AND REMEDIAL MEASURES  ASSOCIATED  WITH  THE  GRANU-
     LAR ACTIVATED CARBON SYSTEM

IPC treatment plants  were designed  and built to provide a  sec-
ondary or higher  level  of treatment of wastewaters without  the
use of biological  treatment processes,  secondary treatment  typ-
ically required  not less  than  85 percent  removal  of  BODs  and
total  suspended  solids  (TSS)   and  monthly  average  effluent
BODs  and TSS  concentrations  not  to  exceed  30  and  30 mg/L,
respectively (2).  GAG  systems were  intended to provide suffi-
cient  soluble  BOD  removal to  meet  these  secondary  treatment
requirements.  Some engineers  and  researchers  have  expressed
doubt  over   the  ability  of  GAC  systems  to  remove  sufficient
soluble BOD  to  meet these secondary effluent  requirements,  and
the more stringent  advanced effluent  requirements that  some  IPC
treatment plants must  meet (6).

Appendix A  provides a  summary  of the  effluent  BOD and SS  re-
quirements  and  treatment  plant  performance of  the IPC plants
visited. An  evaluation  of the  information  given  in Appendix  A
is  presented in Table  2.  It should  be noted  that out of  the
eleven IPC  plants visited, five  plants had taken   the  GAC  unit
off-line, in order  to make a realistic assessment  of  the  per-
formance of the  IPC  plants,  this  evaluation  is based on  the
information  from the  six fully  operational plants.  Based on
Table  2,  the following observations  on the performance of  IPC
plants are made:

    •    Only 33  percent  of the  plants met all BOD and SS  re-
         quirements.

    •    80 percent of  the plants met  the BOD  concentration  re-
         quirements, but only 33 percent could meet the percent
         removal criterion for BOD.

    •    80 percent of  the  plants met the  SS  concentration  re-
         quirements, and 83 percent  met the  percent  removal  cri-
         terion for SS.

It  was  observed that  only two  out  of the  four plants  designed
for secondary treatment  met  the effluent  requirements. The  two
plants designed  for tertiary  effluent  requirements  did  not  meet
the effluent standards.

It  is evident that  a  large fraction of  the  plants are  unable to
meet  the  percent removal criterion  for BOD although most  meet
the effluent concentration limits.  One  possible  explanation  for


                               20

-------
                             Table  2
              Summary of IPC Facility Performance1




Effluent Requirement
All BODs and SS effluent
requirements
BODs limit
Percent BODs removal
requirement
Suspended solids limit
Total
Number
of
Plants
with
Requirement
6
5
6
5
Percent SS removal requirement 6
Number
of
Plants
Not
Meeting
Requirement
4
1
4
1
1

Percent
of Plants
Not
Meeting
Requirement
67
20
67
20
17
iflased on operating data from six  fully  operational IPC facil-
 ities; five of the 11  plants visited  had  taken  their GAG units
 off-line.
                               21

-------
the failure to  meet  the percent removal  criterion  could relate
to influent  strength.  A weak  influent  (BOD  and SS <160  mg/L)
makes it more difficult to achieve  a  given  percent  removal cri-
terion since  relatively lower absolute  effluent concentrations
must be produced. Of the plants  that  failed to  meet the percent
removal criterion, all  but one  had influent  BOD concentrations
of 160 mg/L or less.

Although 80  percent  of the  fully operational  plants  satisfied
effluent  BOD  concentration   requirements,  two  facts  must  be
noted.  First,  all of   the  plants  meeting  this criterion were
operating well below design flow capacity.  Secondly,  in all but
one case,  the  influent strength was  relatively weak  (BOD and
SS <160 mg/L).  It is impossible  to  project  performance for full
strength, design  flow  conditions given  the available  operating
data.

Although  the  evaluation  just  discussed considers  performance
data  only  from  the  six fully  operational  plants,  the reasons
for the other five plants  not  being fully operational  must also
be considered. The GAG  units in  these plants had severe problems
and had to  be  taken  out of service.  Some of  these  problems re-
lated to operational difficulties  (e.g.,  plugging  of the-  carbon
bed,  odor  generation,  corrosion of contactors,  excessive  costs
due to frequent regeneration of  the carbon, etc.).  In other cas-
es, the  GAG unit simply could not  achieve  the  treatment  levels
required, and the expense  of  keeping  the unit on-line  could not
be justified. In all five cases  the GAG unit, which is primarily
responsible for soluble BOD removal,  did not function as intend-
ed. This raises a question as to the capability of the GAG proc-
ess to meet the appropriate effluent  requirements for BOD  remov-
al.

The  following  discussion  of  problems  and  suggested  remedial
measures  for  GAG systems  has  been subdivided  according to the
different components of a,typical GAG system. A specific section
is included on  the carbon  adsorption  process itself. The  effec-
tiveness, or  ineffectiveness,  of the carbon  adsorption process
in removing soluble organics is  a key issue. The process compon-
ents discussed include  the following:

              Adsorption process.
              Carbon contactor.
              Backwash  system.
              Carbon regeneration system.
              Instrumentation and control system.
                                22

-------
Appendix D includes a summary of problems and suggested remedies
for the different components of the GAC system.

5.1  ADSORPTION PROCESS

5.1.1  Problems

The major operational process problem with the GAC system is the
inadequate  removal of  soluble  BODs  in  the treated  effluent.
This single  problem  significantly affects the  overall  perform-
ance of  IPC  plants and is considered a  major deficiency  of the
IPC  process.  The  following discussion  focuses  on  the  carbon
adsorption process itself and its ability to  remove soluble BOD.

According to  theory,  activated carbon removes  soluble  organics
from solution in three steps. The first step  is  the transport of
the solute through a surface film to the interior of the carbon.
The next step is the diffusion of the solute  within the pores of
the activated  carbon.  The third step  is the adsorption  of the
solute on the  interior  surfaces  bounding the pore and  capillary
spaces of the  activated carbon.  Several factors  can affect the
effectiveness of soluble  organic matter  adsorption by  activated
carbon. These factors include the following (21, 22):

    •    The characteristics of  the  material to be adsorbed in-
         cluding molecular weight, molecular  size, and  polarity.
         Activated carbon is not  effective  for  the removal  of
         low  molecular  weight  soluble  organic  compounds.   A
         wastewater with a high percentage of these compounds is
         a poor candidate for activated carbon treatment.

    •    The nature  of the carbon  itself  (adsorptive  capacity,
         regeneration  characteristics,  structural  properties,
         and physical  condition).  All activated  carbons  do not
         have the same properties; these properties vary depend-
         ing on  the  type of carbon, utilizing  an inappropriate
         activated carbon can significantly reduce GAC  system
         performance.

    •    Wastewater characteristics such as temperature and pH.

    •    Performance  of prior treatment  processes and the  BOD
         and suspended solids loadings to the GAC system.
                                23

-------
         Biological activity  within a GAG  system may  signifi-
         cantly enhance the removal of soluble organics  and non-
         adsorbable (e.g.,  nonpolar and  low molecular  weight)
         compounds, but can also cause physical  fouling  and re-
         duction in active  surface of the carbon bed.  The most
         prevalent  explanation  is  that  adsorption  causes  in-
         creased biological removal through  a  substrate  concen-
         tration effect on  the  reaction  rate (1, 8). This bio-
         logical activity  has  been postulated as the mechanism
         responsible  for   the   constant,    long-term   removals
         observed in activated  carbon  systems  (8, 16).  However,
         some  researchers  have  hypothesized  that   slow  mass
         transfer  into  micropore  regions accounts for  the con-
         stant removal of organic  substances  over extended time
         periods (10,  13, 14, 15). At  this time,  it  is  not pos-
         sible  to  conclude which  mechanism  is responsible  for
         the constant, long-term soluble  organic removals. It is
         important  to  recognize that  this   mechanism,  although
         not  well  understood,  has  the  potential  to   enhance
              removal  in IPC systems(4).
5.1.2  Remedial Measures

Remedial measures  to  improve the  efficiency  of the GAG  system
for soluble BOD removal are discussed in this  section.

    •    Plant modifications to improve  BOD removal  include  the
         following:

              Possible changes  to  the chemical precipitation  and
              clarification  systems   including  improvements   to
              upgrade the current  system and switching  from lime
              to a different chemical that may prove  more  effec-
              tive.

              Revising the  order  of the  treatment processes  to
              decrease the pollutant loading  to the  GAG system,
              such as placing the  filtration system ahead  of  the
              carbon  contactors,  may  improve  the  BOD removal
              performance of the  GAG system,  thus enabling  the
              plant to meet its BOD discharge  objective.
                                24

-------
Chemical additions  to  enhance soluble BOD  removal  (3,
4, 5).  Peroxide,  oxygen,  ozone,  or sodium  nitrate  can
potentially improve  carbon  system performance by  con-
trolling microbial  growth  in  GAC systems.  The  control
of microbial  growth includes  both the enhancement  and
elimination  of microbial  activity.  Anaerobic  micro-
organisms,  when established in a carbon  contactor,  can
cause the generation of hydrogen sulfides.  Addition  of
sodium  nitrate  has been  very effective   in  preventing
microbial  reduction  of sulfates  to hydrogen  sulfides
under   anaerobic   conditions   (4).  Aerobic  microbial
growth  can  have either a  positive  or negative  effect
on the  GAC  system  effluent. Aerobic microbial activity
can lead to the biological assimilation  of  organics  by
microorganisms  in   the  contactor and  prevent  sulfide
formation.   This biological  assimilation can  help  to
reduce  the  BODs in  the  GAC  system effluent.  However,
aerobic microbial  growth can  interfere with adsorption
capability of the carbon bed  and  increase backwash  and/
or regeneration requirements.

An aerobic  condition can be created in the  carbon  con-
tactor by adding air, oxygen,  etc. to  the carbon  system
influent which, in  turn,  can  ensure   the  growth  of
aerobic microorganisms  in the  contactors  (3, 5).  Chemi-
cals have  also been added  to decrease  the  wastewater
pH to slightly below neutral  levels  to increase  the  ad-
sorptive characteristics of the activated carbon  (21).
                      25

-------
    •    The carbon should be regenerated at required  intervals
         to ensure  a  fresh,  readily  adsorbing  carbon.  It  is
         important that any  carbon  lost during regeneration  be
         replaced. The type  of  activated  carbon installed  with
         the system  should  also be  studied.  Carbon structural
         properties,  performance, and  cost  are not necessarily
         related.  Sometimes  a structurally sound and inexpensive
         carbon is selected  at the sacrifice of performance. The
         plant operators may  have to change the specific acti-
         vated carbon  type,  at  possibly greater  cost, to  meet
         effluent  requirements.

    •    Pretreatment  of  selected wastewater  sources  for  the
         removal or alteration of nonadsorbable compounds.  This
         procedure may require an industrial or combined waste-
         water testing program to:

              Determine by isotherm  testing if activated carbon
              can   still  effectively treat  the  wastewater  as
              originally designed,  and to determine if  the  non-
              adsorbable compounds  are entering  the   treatment
              plant.

              Determine by gas  chromatography/mass spectrometry
              testing which  compound(s) are not adsorbed by the
              activated carbon system.

              Determine  industrial   source(s)   of   nonadsorbable
              compound(s).

              Develop a treatment or  pretreatment  program to re-
              move or  alter  the nonadsorbable compound(s). Ap-
              propriate regulations must be  available or enacted
              to enforce the pretreatment program.

5.2  CARBON CONTACTOR

5.2.1  Problems

The following problems are associated with  the  carbon contactor:

    •    Corrosion of  carbon  contactors has  been  observed  in  a
         number of POTW's. Dry carbon is not corrosive.  However,
         partially dewatered  carbon  is  extremely  corrosive, un-
         der conditions  of  continuous exposure, it may produce
         pitting in unprotected mild  steel  plate by electrolytic
         corrosion at a rate as high  as 250  mils per year.


                                26

-------
         Corrosion can also be  caused by hydrogen sulfide.  Hy-
         drogen sulfide  gas  develops when  sulfates  present  in
         the influent  wastewater  are  biochemically  reduced  by
         sulfate-reducing bacteria,  conditions promoting or  ac-
         celerating hydrogen sulfide  production  in GAC  contac-
         tors include (17,  21):

              Anaerobic conditions,  i.e., the absence of oxygen
              in the GAC  system  influent.

              High concentrations  of BOD and sulfates  in  the  GAC
              system influent.

              Long detention  times.

    •    Media clogging occurs  in  GAC systems in  the IPC  plants.
         It  is primarily  caused by development  of  microbial
         growth in the carbon bed. Media clogging  increases  the
         head loss through  the  carbon bed and thus  decreases  the
         length of  the operating  cycle. Some clogging problems
         are the result of  backwashing deficiencies, including:

              Lack of backwashing  facilities.

              Design of an ineffective  backwash  system (no aux-
              iliary wash or  scour systems  provided).

              Backwash rate and/or  duration are not  sufficient
              to thoroughly clean  the bed.

5.2.2  Remedial Measures

Measures that  may be employed  to alleviate  problems  associated
with the carbon contactor are as follows:

    •    Carbon  contactors,  when constructed  of  mild  steel,
         should be  covered with  protective  coatings  of suffi-
         cient thickness, such  as  coal-tar  epoxy  paint. The con-
         tactor surface should  be  prepared  prior  to applying  any
         coating, to ensure that  the  coating will  adhere to  the
         contactor surface. This  preparation should include  re-
         pairing  any defects found  on  the contactor surface,
         cleaning the  contactor  interior,  and surface prepara-
         tion appropriate  for the coating  to be applied. Dewa-
         tering bins, wash tanks, and quench tanks should also
         receive  a  protective  coating.  Fiberglass tankage  may
         also be acceptable from a design standpoint.
                               27

-------
Potential  remedies  for  controlling  hydrogen  sulfide
generation can be made by  either  chemical  additions or
operating modifications.  Chemical additions  have  been
used with  limited  success to control  anaerobic micro-
bial growth/ which  is  the principal cause  of hydrogen
sulfide  generation.  A better  approach is  to maintain
aerobic  conditions  in  the column,  thus limiting  the
growth of hydrogen  sulfide-producing  bacteria  (because
they require anaerobic conditions to grow).

Operating modifications can also be used to control hy-
drogen sulfide production in GAC systems, such as:

     Increase the frequency of backwash, as needed.

     Backwash GAC  columns  more  thoroughly  by  use  of
     surface wash,  if available.  The  plant  should con-
     sider installing this  equipment  if not already in
     place.

     Reduce  the  GAC system detention  time  by removing
     certain carbon contactors  from  service if the de-
     tention time is too long.

     Preaerate the  influent wastewater  to  the GAC sys-
     tem utilizing a mechanical system.

     Addition  of  sodium  nitrate  (NaNO3)   to  the  in-
     fluent  of the GAC system.

These  measures  will aid in maintaining aerobic condi-
tions  in the GAC  contactor,  which,  in  turn, will  de-
crease hydrogen sulfide generation (4, 21,  22).

Media  clogging  can be limited  by the proper operation
of  the  backwash  system.  Processing  the correct  rate
and  duration of  backwashing  is  mandatory  for good GAC
system  operation.   Considerations  should  be given  to
modifying the system  to  include an auxiliary wash sys-
tem  if none  is provided.  Microbial growth  can be con-
trolled  by applying the  above methods for hydrogen sul-
fide control.
                       28

-------
5.3  CARBON TRANSPORT SYSTEM

5.3.1  Problems

Problems that  occur  in  the carbon transport system are as  fol-
lows:

    •    Clogging of  the carbon  transport  system pipes  occurs
         with  GAC  systems at  many  plants.  The  causes  of  this
         problem are  primarily design  related  and include  the
         following:

              Undersizing of carbon  slurry lines.

              Poor  carbon transport system design, i.e.,  use  of
              short  radius  and  90°   elbows   or   insufficient
              fluid velocity.

              Lack  of cleanouts in the carbon transport  system.

    •    Clogging of  the carbon slurry pumps  used in GAC  sys-
         tems. The  use  of the  wrong  type of pump and/or  small
         diameter influent and effluent piping causes  pump clog-
         ging problems.

    •    Abrasion wear  of carbon slurry  pipes.  The  use  of  un-
         lined mild  steel pipe and  short  radius, right  angle
         bends in the slurry transport system result in  exces-
         sive wear.

5.3.2  Remedial Measures

Measures that  may  be taken  to alleviate  these problems  are  as
follows:

    •    coated cast  iron steel pipe or  glass-lined  or  rubber-
         lined steel  pipe  are preferred  for  carbon  transport
         systems. Mild  steel or FRP  pipe should never be  uti-
         lized as a carbon transport  pipe. Abrasion is  greatest
         at bends. Long  radius  fittings at  changes in direction
         of  flow,  along with  extra  heavy elbows  and tees  are
         recommended. Rubber or ceramic-lined impellers  are also
         recommended for carbon slurry pumps (21).
                                29

-------
    •    Several improvements can be made  to  alleviate  clogging
         of the carbon transport pipes,  increasing the  transport
         line size (a minimum pipe diameter of 2  inches  is  rec-
         ommended)  and decreasing the carbon-to-water slurry ra-
         tio can help to prevent clogging in carbon slurry pipe-
         lines.

5.4  BACKWASH SYSTEM

5.4.1  Problems

Clogging of the backwash and/or  surface  wash  nozzles is  a prob-
lem  in  the carbon contactor.  Carbon media  and/or solids  that
leave  the  contactor   are  responsible for  clogging nozzles  and
wash  mechanisms.  The carbon  migrates  to  the contactor  under-
drains due  to  structural  failures in the  media support  system,
where it is picked up by the  incoming backwash water and causes
clogging of the distribution nozzles.

5.4.2  Remedial Measures

Preventing carbon loss  can  remedy the clogging of backwash  and/
or surface wash nozzles  that  is caused  by solids  and media  mi-
gration  through  the   underdrain  and into  the backwash  system.
Screens can be added  to critical  locations  to prevent media and
solids migration. Cleanouts should be placed  in order  to permit
the screens to be cleaned.  Frequent  backwashing  (especially af-
ter  loading  the carbon) will remove carbon fines from  the  bed
and  decrease  carbon  clogs. These preventative  measures  should
also  decrease  carbon  losses within  a GAC  system,  thus  reducing
operating costs.

5.5  REGENERATION SYSTEM

5.5.1  Problems

The regeneration system is a source  of carbon loss during opera-
tion.  Some  carbon  loss is  expected  during regeneration  opera-
tions, but  incorrect  furnace  operating conditions can  result in
excessive carbon loss.

5.5.2  Remedial Measures

Preventing excess furnace operating  temperatures,  timely removal
of the regenerated carbon from  the furnace, and proper  handling
of the regenerated carbon  can keep  carbon  loss during  regenera-
tion  to a minimum.
                                30

-------
5.6  INSTRUMENTATION AND CONTROL SYSTEM

5 .6 .1  Problems

Maintenance operations at many treatment plants are not adequate
to keep  the system  functioning  properly,  insufficient  mainte-
nance can  result  in nonfunctioning or  ineffective instrumenta-
tion systems,  inoperable valves, pumps  that  do not work,  etc.
These systems  can  impact on operations and cause  the  system  to
discharge a poor quality effluent.

5.6.2  Remedial Measures

An adequate maintenance  program  should be  established  to ensure
that the instrumentation and control systems  function  properly.
It is especially important that these systems  function  properly.
These systems allow the plant operator(s) to  control and monitor
the GAC process.
                               31

-------
6.0  SUMMARY OF FINDINGS AND CONCLUSIONS

Based on the  previous  discussion, the  following  conclusions on
the overall performance of IPC treatment systems may be made:

    •    The performance evaluation of IPC plants indicates that
         most of  the  plants have numerous operational problems
         with various process units.  Chemical feed systems, par-
         ticularly lime  handling  systems,  have been  especially
         difficult to  operate and maintain.  The operation  and
         maintenance costs of the IPC plants  have been very high
         due to the high costs of chemicals,  and excessive main-
         tenance requirements. The survey  showed that  6  out of
         the eleven IPC  plants evaluated  had  decommissioned one
         or more of their process units due to severe operation-
         al problems or excessively high costs of operation.

    •    From the  standpoint  of  effluent quality, only two out
         of  the six  fully  operational  IPC  plants meet  their
         specified  effluent  discharge   limitations.   Both  of
         these  plants   were  designed   for  secondary   treatment
         levels.  The  two operational  plants  designed  for  ter-
         tiary  treatment • levels  did   not  meet  the  discharge
         standards. Many IPC plants have problems attaining per-
         cent  removal  requirements,  while meeting  the effluent
         concentration  requirements  for 8005  and SS.  This  may
         be attributed  to weak  influent  strength (BOD5  of  160
         mg/L  or  less),  which   was   observed  at  most  plants
         visited.

    •    One  possible  explanation for  the lower than expected
         BOD  removals  in many IPC plants  appears to  be because
         carbon adsorption  may not be effective  for  removal of
         low  molecular  weight soluble  organics which  exist in
         domestic,  as  well  as  industrial  wastewaters.  Air  or
         oxygen-containing  compounds  may  be  fed to  the carbon
         adsorbers  to  enhance aerobic  biological activity  and
         consequent  removal  of  low molecular  weight biodegrad-
         able  organic  material.   However, increased   levels  of
         biological  growth  within the  carbon  bed can  also re-
         quire  more  frequent carbon  regeneration requirements.
                                32

-------
    •    The operation of IPC plants  requires  qualified  operat-
         ing  personnel  trained  specifically  for  dealing  with
         physical-chemical processes. This  type of training  is
         significantly different  from the training and  experi-
         ence commonly received from operating  biological treat-
         ment processes.  This  deficiency has  been observed  in
         several of the IPC  plants visited.

    •    it  is  recommended  that the  performance  of IPC  plants
         should  be  evaluated   by  an  engineer  experienced  in
         physical/chemical treatment technology, and appropriate
         remedial measures taken accordingly.

The following conclusions and  recommendations  are made  for  the
design  and  operation  of specific  unit  processes in  the  IPC
plants:

    •    Frequent backwashing and maintaining aerobic  conditions
         in  GAG  contactors   can minimize  the  hydrogen  sulfide
         generation problem.

    •    Lime handling systems  are  prone to problems of equip-
         ment  malfunction  and,   in  general,  require  frequent
         maintenance and operator attention  due  to the  inherent
         nature of  the  chemical and  its limited  solubility  in
         water.  Lime slurry  transport and feed systems  are  the
         major problem areas in the lime handling  system,  scal-
         ing and  clogging of pipes is a  chronic problem in  the
         lime handling system,  problems  of lime slurry transport
         systems could be minimized by the following:

              Maintaining continuous  operation  of  the  system
              utilizing recirculation loops.

              Using flexible hoses.

              Periodically flushing the lines with water.
                                33

-------
              Providing a minimum number  of  bends.

              Using piping at least 2  inches in  diameter.

    •    The design of  a filtration system in  IPC  applications
         should be  based on  the  consideration  that  wastewater
         filters require provisions for flexibility  in operation
         to handle  process  upsets  and meet effluent  discharge
         criteria.

    •    The filtration system, if  used at  an IPC plant,  should
         be placed  prior to the GAG system  to decrease  the  pol-
         lutant loading to the GAC system.

    •    incorrect  backwashing  protocol  can  cause  media  clog-
         ging, media loss, gravel mounding  and displacement,  and
         mudball formation  in the  tertiary filtration  system.
         In order to ensure that the filter  is backwashed at  the
         appropriate time intervals, the frequency  of backwash-
         ing should be controlled on the  basis of both head  loss
         and a  fixed  time  interval,  whichever  occurs  earlier.
         Settings of the rate and timer controls for backwashing
         should be  checked regularly for  correctness.

In  the  course  of  this  study many design-,  operational-,  and
equipment-related  problems  have  been  observed at  independent
physical-chemical  treatment facilities,  implementation of  the
remedial measures recommended in this  report should  significant-
ly improve  the  performance  and  operational  reliability of these
facilities. However, there is some question concerning the abil-
ity of IPC  processes  (specifically, the  granular activated  car-
bon process) to remove  low  molecular weight soluble  organics  to
the extent  necessary  to achieve advanced treatment  design  cri-
teria. It is recommended that this question be addressed in  fur-
ther studies (i.e., pilot-scale studies and field studies).
                               34

-------
REFERENCES

 1. Basik, F.  High  Rate Adsorption - Bio-Oxidation  of  Domestic
    Sewage. Water & Sewage Works 120(6):  68-71, 1973.

 2. Code of Federal Regulations, Title  40,  Part 35,  Appendix  A,
    10 September 1973.

 3. Culp,  R.L.  and S.P.  Hansen.  Carbon Adsorption  Enhancement
    with  Ozone.  Journal  water  Pollution  control  Federation,
    52(2):  270-281, 1980.

 4. pirecto, L.S., C.L. Chen,  and  R.P.  Miele.  Independent  Phys-
    ical-Chemical Treatment  of Raw Sewage, wastewater  Research
    Division,  Contract  No.  14-12-150,  Report No.  EPA-600/2-77-
    137, Cincinnati, Ohio 45268.

 5. Guirguis,  W. et al. improved Performance of  Activated Carbon
    by Pre-Ozonation.  Journal water Pollution control Federation
    50(2):  303-320, 1978.

 6. James M. Montgomery, inc. Wastewater Treatment Plant Evalua-
    tion - Vallejo,  April 1981.

 7. Lier, W.C. van, E. Van de  Berg, and  G.  Lettinga. The Appli-
    cation of  Carbon for wastewater Treatment. Progress  in  Water
    Technology 10(1-2), 517-536,  1978.

 8. Lowry, J.D. and C.E. Burkhead.  The  Role of Adsorption in Bi-
    ologically Extended Activated Carbon Columns.  Journal  Water
    Pollution  Control  Federation  52(2):   389-397, 1980.

 9. Lynch, W.O. and L.R. Potter.  Start-up of a Physical-Chemical
    Treatment  Plant. Journal Water Pollution Control Federation
    53(3):  318-324, 1981.

10. Maqsood, R. and A.  Benedek. Low Temperature Organic Removal
    and Denitrification in Activated Carbon columns.  Journal wa-
    ter Pollution Control  Federation 49(1):   2107-2117,  1977.

11. Metcalf &  Eddy,  inc. wastewater Engineering,  2nd   Edition,
    McGraw-Hill, New York, 1979.

12. Moss, W.H.  and R.E. Schade. Full-scale  use of Physical-Chem-
    ical Treatment of  Domestic Wastewater at Rocky River,  Ohio.
    Journal Water  Pollution  Control Federation 49(11):   2249-
    2254, 1977.
                               35

-------
13.  Narbaitz,  R.M.  and A.  Benedek.  Least  Cost Process  Design  for
    Granular Activated carbon Adsorbers.  Journal  Water Pollution
    Control Federation, 55(10)  1244-1251,  1983.

14.  Peel,  R.G. and A. Benedek. Dual Rate Kinetic Model of  Fixed
    Bed Adsorber.  Journal  Environmental  Engineering Division
    ASCE 106(4):   797-813, 1980.

15.  Peel,   R.G.  and  A.  Benedek. Biodegradation  and  Adsorption
    within Activated  carbon  Adsorbers.  Journal Water Pollution
    Control Federation, 55(9):   1168-1173,  1983.

16.  Roberts, P.V. and R.S. Summers. Performance of Granular  Ac-
    tivated Carbon  for Total  Organic Carbon  Removal.   Journal
    American Water  Works Association 74(2):  113-118,  1982.

17.  Roy  F. Weston,   inc.  Summary  Report  Advanced   wastewater
    Treatment  Effectiveness  Evaluation. Advanced  Treatment  (AWT)
    Task 5. U.S.  EPA, October 1983, Draft Report.

18.  Roy F. Weston,  Inc. Feedback  to Design/Operation - Lime Han-
    dling. Advanced Wastewater Treatment  (AWT)  Task 5, U.S. EPA,
    December 1983,  Draft Report.

19.  Roy F. Weston,  Inc.  Feedback to Design/Operation -  Filtra-
    tion.  Advanced Wastewater  Treatment  (AWT)  Task 5, December
    1983,  Draft Report.

20.  Roy F. Weston, inc. Feedback to Design/Operation  - Granular
    Activated  Carbon Advanced wastewater  Treatment  (AWT)  Task  5,
    December 1983,  Draft Report.

21.  U.S. EPA Process  Design  Manual for Carbon  Adsorption.  Tech-
    nology Transfer 1973.

22.  U.S. EPA,  Municipal  Technology Branch, personal  communica-
    tion,  January 1984.

23.  Weber, W.J., Jr.  Physiochemical Processes  for Water  Quality
    Control. John Wiley and  Sons, inc., New York,  1972.
                               36

-------
                      APPENDIX A






UNIT PROCESSES AND TREATMENT PERFORMANCE OF IPC PLANTS

-------
                           Unit  processes and  Treatment  Performance of  IPC Plants
            present/
Treatment   Design
  Plant      Plow
            (mgd)
unit Process in Treatment Order
                                      Parameter
influent
 (rag/L)
                       Compliance with
           Permit     Effluent Requirements
Effluent   Limit                    Percent2
 (mg/L)    (mg/L)    concentration   Removal
            10/12.5    Preliminary treatment                       BOD5        211
                      cnemical (lime) precipitation               SS          263
                      Kecarbonation-clarification (upflow)
                      Activated carbon adsorption
                      Cnlorination
                      Dual-media filtration

            10.0/15.3  Preliminary treatment  (municipal flow)      BODj        135
                      Chlorination (municipal  flow)               SS          450
                      Primary sedimentation  (municipal flow)
                      Cnemical (lime, alum,  and polymer)
                       precipitation-clarification
                       (industrial and municipal flows)
                      Activated carbon adsorption (industrial
                       and municipal flows - downflow)
                      Post-aeration (industrial and municipal
                       flows)

            3.75/6.0   Preliminary treatment                       BODs        160
                      Cnemical (ferric chloride and polymer)      SS          220
                       precipitation-clarification
                      Horizontal pressure filtration
                      First  stage activated  carbon adsorption
                        (upflow)
                      Breakpoint Chlorination
                      Dechlorination (second stage activated
                       carcon adsorption upflow)
                      pH  adjustment
                                                               50
                                                               30
                                                               40
                                                               20
                        30
                        30
                         8
                         8
                         No
                         yes
                         No
                         No
No
Yes
No
yes
                                                                la
                                                                10
                        10
                        20
                         No
                         Yes
NO
yes
^Activated carbon system  not utilized.
2A11 plants are assumed to have a requirement to meet  a minimum  of  85 percent removal of BOD5  and  SS  unless specified otherwise.

-------
                               Unit Processes  and  Treatment Performance  of IPC  Plants
                                                               (continued)
                present/
    Treatment   Design
      Plant      Plow
                (mgd)
              Unit Process in Treatment  Order
                                                   Parameter
                                  Compliance with
                      Permit    Effluent Requirements
influent   Effluent    Limit                    Percent2
 (mg/L)     (mg/L)     (mg/L)   Concentration   Removal
 I
ro
0.31/0.60   Preliminary treatment                      BOD5
           Chemical  (lime and ferric chloride)         SS
            precipitation-clarification
           Dual-media filtration
           Activated carbon adsorption (downflow)
           Dual-media filtration
           Ion exchange columns
           Cnlorination

0.05/0.05   Hydrosieve
           Chemical  (FeCla and polymer)               BODg
            precipitation-clarification               SS
           Activated carbon adsorption (upflow)
           Chlorination

6.5/10.0    Preliminary treatment                      BOD5
           Chemical  (alum, PeCla, and polymer)         SS
            precipitation-clarification
           Microstraining
           Activated carbon adsorption (downflow)
           Breakpoint chlonnation
           Dechlorination
           Post-aeration

0.5/1.0    Preliminary treatment                      BOD5
           Chemical  precipitation-clarification        SS
           Multimedia filtration
           Activated carbon adsorption (downflow}
           Breakpoint chlorination
           Dechlorination
           Post-aeration

8.1/13.0    Preliminary treatment                      BOD5
           Chemical  (alum, FeCl3, and polymer)         SS
            pieci Citation-clarification
           Sand filtration
           Activated carbon adsorption (upflow)
           Chlorination
                                                                                 168
                                                                                 239
             16
              2
                                                                                  216
                                                                                  346
                                                                                  131
                                                                                  160
             20
             13
             70
             21
                                                                                  250
                                                                                  200
             75
             30
                                                                                  155
                                                                                  130
             30
             20
25
30
Ves
Yes
Yes
yes
95 percent  	
95 percent  	
30
30
No
Yes
             No
             Yes
No
Yes
10
10
No
No
No
Yes
30
30
Yes
Yes
NO
Yes
     Activated carbon system not utilized.
     2A11  plants are assumed to have a requirement  to meet a minimum of 85 percent  removal  of  BOD5 and SS unless specified otherwise.

-------
                       Unit  Processes and Treatment Performance  of  IPC Plants
                                                  (continued)
n
Treatment
Plant
9




10





II1




Present/ Compliance witn
Design Permit Effluent Requirements
Flow Unit Process in Treatment Order Parameter Influent Effluent Limit Percent2
(mgd) (mg/L) (mg/L) (mg/L) Concentration Removal
0.35/0.5 Preliminary treatment BOD5 120 25 30 Yes No
Chemical (PeCl3 and lime) precipita- SS 150 75 30 No No -
tion-clarif ication
Activated carbon adsorption (downflow)
Chlorination
0.5/2.0 Preliminary treatment BOD5 137 11 30 Yes Yes
cnemical (Pecl3 and polymer) precipi- SS 145 7 30 Yes Yes
tat ion-clan ficat ion
Granular media filtration
Activated carbon adsorption (upflow)
Chlorination
11.0/16.0 Preliminary treatment BOU5 130 52 20 No No
Chemical (FeCla) precipitation- SS 121 33 20 No No
clarification
Activated carbon adsorption (downflow)
Chlorination
1 Activated carbon system not utilized.
2A11 plants are assumed to have a requirement to meet a minimum of 85 percent removal of BODs and SS unless specified otherwise.
AD-
                    D-0
                                                                                             BK-

-------
                        APPENDIX B
LIME HANDLING SYSTEMS:  IDENTIFIED PROBLEMS AND SUGGESTED
                    REMEDIAL MEASURES

-------
       Lime  Handling  System:    Identified problems  and  Suggested
                                   Remedial  Measures
        Identified Problem
              Suggested Remedial Measures
Lime Loading and Unloading

  Dust.


  Mechanical weac of transport piping.


  Delay  in  repair and maintenance of  line
  transport piping.

Lime Storage and Dry Feeders

  Arching over hopper openings.

  Clogging  of  feed hopper, valves, and
  screw  feeders.


Lime Slaking

  Unreliable slaked lime delivery.
  Mechanical  wear of grit conveyors
  and other moving parts.
  Malfunctioning  of  probes used for
  indicating levels  of slurry.

  Instrumentation for control systems
  coated with lime dust.

Lime Slurryxng

  Malfunctioning  of  liquid level control
  systems in slurry  tanks.


  Inaccessibility of agitator drives and
  other equipment located on slirry tanks.

  Mechanical wear of FRP slurry tank
  walls.
Install and  maintain a dust collection baghouse system
on lime storage  silo/bin.

Avoid sharp  elbows and bends in piping.  Install addi-
tional plates at bends for reinforcement.

Install ladders,  catwalks, and platforms for  quick ac-
cess during  maintenance work.
Install vibrating hoppers or 'live bin* systems.

Prevent entry of moisture into feeder by installing
rotary valve between feeder and slaker, or  offset-
ting location of slaker  from feeder.
Maintain proper  temperature and water-to-lime ratio  in
slaker. Operate  slakers under negative pressure to
prevent entry  of moisture into feeders.  Periodic  clean-
ing of slakers.

Use better quality  lime with lower grit  content:,  if
possible. Spare  screw  conveyor should be available for
replacement.

Clean probes regularly. Consider use of sonic-type
level sensors.

Locate instrumentation panels away from high dust
areas. Enclose panels  in housing.
Clean probes regularly. Consider use of sonic-type
level sensors.  Provide  overflow piping to handle
emergency conditions.

Install ladders,  catwalks, and platforms to facilitate
access for maintenance.

Construct erosion-resistant steel slurry tanks to pre-
vent aorasion problems.
                                              B-l

-------
    Lime  Handling  System:    Identified  Problems and Suggested

                                 Remedial Measures

                                      (continued)


       Identified  Proolem                              Suggested Remedial Measures


Lime  Slurry Transport

  Clogging of lime  slurry transport lines.   Operate transport  lines continuously. Install  re-
                                         circulation loops. Use flexible hoses for transport
                                         piping. Minimize length of slurry transport  lines.
                                         Avoid sharp bends  and elbows to prevent accumula-
                                         tion. Provide cleanouts in piping. Use large diam-
                                         eter piping to prevent frequent clogging. Plush
                                         transport piping after each  use with water,  consid-
                                         er  use of covered  troughs for lime slurry transport.

Lime  Slurry Feed

  Clogging of lime  slurry feed piping,      Locate take-off points for slurry feed as close  to
  pumps, and valves.                       point of application as possible. Use open/close-
                                         type feed control  valves —  avoid variable flow
                                         control valves. 'Rotodip' or similar type feed sys-
                                         tems are preferable to progressive cavity-type feed
                                         pumps.

  Malfunctioning  of pH meters used for      Use two pH probes  in cyclic order.
  lime feed control.
                                            B-2

-------
                      APPENDIX  C
FILTRATION SYSTEM:  IDENTIFIED PROBLEMS AND SUGGESTED
                  REMEDIAL MEASURES

-------
         Filtration  System:    Identified  Problems  and  Suggested
                                   Remedial Measures
        Identified Problem
              Suggested Remedial Measures
Design Aspects

  Frequent  clogging of media and buildup
  of excessive  head loss.
  Hydraulic  surges in influent flow to
  filters.

  Improper frequency of backwashing.
  Loss of  media during backwashing.
  Clogging  of  backwash nozzles due to
  migration of media.

  Corrosion of backwash nozzles.
Operating Aspects

A.  Filtration Cycle

    Media Clogging.
    Excessive filtration system
    downtime due to equipment
    problems.

    Incorrect operation of the filtration
    system.
Multimedia  filters should be considered.  Design  filters
to operate  either  in parallel or series.  Improve qual-
ity of influent  to filter by incorporating modifica-
tions to processes ahead of filter.

Provide equalization facilities ahead of  filter.
Backwash frequency should be controlled on the  basis  of
predetermined head loss and a fixed time interval,
whichever is necessary earlier.

Wash water  troughs should be uniformly distributed
over the entire area of the filter bed. A backwash  rate
controller  should be provided.

Use of nozzles fitted with a protective plate on top  is
recommended.

Use of compatible materials of construction for noz-
zles, underdrain support structure, and filter  bed  to
avoid electrolysis and galvanic corrosion is recommend-
ed.
Microbial growth  in  filter bed ~ Add a disinfectant,
usually chlorine, to the  filter influent periodical-
ly. Backwash to remove  residual chlorine.

Solids carryover  —  The prior treatment process
should be modified to improve its performance. Removal
of these solids by filters is not effective.

Oil and grease carryover  — The prior treatment proc-
esses should remove  these constituents.

Chemical precipitation  on filter — The chemical con-
ditions of the precipitation system should be adjust-
ed to ensure that all precipitation occurs in the pre-
cipitation system.

An adequate maintenance program should be established
and followed.
The operator(s)  should  receive training in filtration
theory and system operation. The operator(s) should be
aware of the system's capabilities so they can modify
it, especially during periods of prior treatment proc-
ess upsets, and in response to a change in conditions.
                                              C-l

-------
         Filtration System:  'Identified_Problems  and  Suggested
                                  Remedial  Measures
                                        (continued)
        Identified Problem
                                                       Suggested Remedial Measures
B.  Backwashing Cycle

    Incorrect operational sequencing
    during filter bacfcwasning.
    Incorrect rate and duration of
    backwashing.
    Incorrect operation of  backwash
    system.
    Excessive backwash system downtime
    due to  equipment problems.
The operator(s) should observe the instrumentation dur-
ing backwashing to ensure that the correct operational
sequence occurs. A monthly visual check should also be
made of each filter cell for a complete backwash cycle
to ascertain that all systems are operating correctly.
A pole that rises above the media should be attached to
the arm of a submerged auxiliary wash or scour system
to aid in observing its operation.

Operators should be aware of correct backwashing rates
and duration. The settings of the rate and timer con-
trols should be checked regularly to ensure they are
correct. Operators should change backwash rates as
temperatures fluctuate to compensate for the change in
water viscosity with temperature.

Operators should be trained in the operation of the
backwash. They should be made aware of the system's
capabilities and how to modify its operation in re-
sponse to a change in conditions.

An adequate maintenance program should be established
and followed.
                                              C-2

-------
                      APPENDIX D
GRANULAR ACTIVATED CARBON SYSTEM:  IDENTIFIED PROBLEMS
            AND  SUGGESTED REMEDIAL MEASURES

-------
        Granular  Activated  Carbon  System:    Identified  Problems
                          and  Suggested  Remedial  Measures
        Identified Problem
              Suggested Remedial Measures
Carbon Contactor

  BOD removal goal not achieved.
  Hydrogen sulCide generation in the
  carbon contactor.
  Corrosion of the carbon contactor.
  Accumulation of solids in the carbon
  contactor  (media clogging).

  Structural  failure of the carbon
  contactor  underdrain and influent
  piping.
Carbon Slurry  Transport System

  Clogging  of  the carbon slurry transport
  pipeline.
  Abrasion  of  the carbon slurry pipeline.
  Clogging  of  the carbon slurry pumps.
The activated carbon should be tested  for adsorptive
capacity;  more  frequent regeneration of  the  carbon; add
oxygen to  the GAC  influent.

Maintain aerobic conditions in the carbon contactor by
addition of  oxygen, air, or peroxide to  the  GAC system
influent;  add sodium nitrate to the influent to prevent
sulfide formation; increase the frequency of backwash-
ing; backwash GAC contactor more thoroughly  by the use
of a surface wash; reduce the GAC system detention
time.

Spark test to determine defects in the contactor coat-
ing; patch defects in the contactor coating; reseal the
contactor  with  better coating material;  use  synthetic
connectors within  the contactor; eliminate the poten-
tial for hydrogen  sulfide generation.

Use surface  washers and increase backwash frequency.
Modify underdrain and air grid system,  redesign and re-
construct underdrain supports; replace  defective piping
with pipe of  increased wall thickness;  specify a struc-
turally stronger grade of pipe; add additional pipe
supports.
Increase  transport line size (minimum suggested
diameter  is  2  inches); decrease carbon slurry concen-
tration;  avoid the use of short radius right-angle
bonds.

Use black steel or lined steel pipe;  long radius fit-
tings should be used at changes in direction of flow,
along with extra-heavy elbows and tees.

Decrease  the carbon slurry concentration; modify the
carbon slurry  pump (i.e., change the  impeller or uti-
lize larger  size intake or discharge  piping); replace
the pump if  the original cannot be modified to improve
its performanoe.
                                              D-l

-------
         Granular Activated Carbon  System:    Identified  Problems
                         and Suggested Remedial  Measures
                                      (continued)
        Identified pcoolem
             Suggested Remedial Measures
Backwash System

  Clogging of backwash and/or surface
  wash  nozzles.
  Incorrect rate and/or duration of
  backwasning.
Regeneration System

  Excessive carbon loss.



Instrumentation and  Control Systems

  Nonfunctioning instrumentation and
  control systems.
Prevent the carbon from leaving the  contactor; add
screens to remove solids from the backwasn and surface
wash influent; provide cleanouts to  permit cleaning of
the screens.

Operators should check rate and timer controls fre-
quently to ensure they are accurate; backwash controls
and instrumentation should be periodically recalibrat-
ed.
Operate the carbon regeneration furnace at the speci-
fied conditions; store  enough spent carbon to permit
more continuous operation of the regeneration furnace.
An adequate maintenance program should be established
and followed.
                                             L>-2

-------