BOSTON HARBOR SUPPLEMENTAL DRAFT ENVIRONMENTAL IMPACT STATEMENT REPORT OF FINAL SCREENING RESULTS U.S. ENVIRONMENTAL PROTECTION AGENCY REGION I ENVIRONMENTAL EVALUATION SECTION JOHN F. KENNEDY FEDERAL BUILDING BOSTON, MASSACHUSETTS 02203 May 16, 1984 Prepared by: CE MAGUIRE, INC. ONE DAVOL SQUARE PROVIDENCE, Rl 02903 ------- THE GOAL OF THE EIS IS TO SELECT ONE PRIMARY TREATMENT AND ONE SECONDARY TREATMENT.OPTI ON FROM A LIST OF TWENTY ALTERNATIVES. BASED ON A PRELIMINARY COST-BENEFIT ANALYSIS, THE LIST OF TWENTY ALTERNATIVES WAS REDUCED TO A LIST OF SEVEN ALTERNATIVES. THE LIST OF SEVEN ALTERNATIVES SHALL BE REDUCED TO TWO BY EXAMINING EACH ALTERNATIVE AGAINST SIX OBJECTIVES PRESERVE AND PROMOTE HARBOR VISION BUILD AT LOWEST COST PRESERVE CULTURAL AND ENVIRONMENTAL RESOURCE* IMPLEMENT QUICKLY ASSURE FUTURE RELIABILITY MINIMIZE EFFECTS ON NEIGHBORS JW ALTERNATIVE WILL FULLY ACHIEVE ALL SIX OBJECTIVES. THEREFORE, CHAPTER IV WILL DISCUSS THE FACTORS WHICH WILL ENTER INTO THE CONSIDERATION OF EACH OBJECTIVE, AND WILL THEN SET FORTH HOW THE DECISION-MAKERS PROPOSE TO WEIGH THE OJECTIVES. ------- BOSTON HARBOR SUPPLEMENTAL DRAFT ENVIRONMENTAL IMPACT STATEMENT REPORT OF FINAL SCREENING RESULTS U.S. Environmental Protection Agency Region I Environmental Evaluation Section John F. Kennedy Federal Building Boston, Massachusetts 02203 May 16, 1984 Prepared by CE MAGUIRE, INC. One Davol Square Providence, RI 02903 ------- TABLE OF CONTENTS 1.0 SUMMARY OF CONCLUSIONS 1-1 2.0 BACKGROUND 2-1 2.1 Previous Wastewater Studies 2-1 2.2 Previous Sludge Studies 2-5 2.3 Legal and Institutional Background 2-6 3.0 REPORT OBJECTIVES 3-1 4.0 SCOPE OF THE ANALYSIS 4-1 5.0 FORMULATION OF INITIAL OPTIONS 5-1 5.1 Introduction 5-1 5.2 Secondary Treatment Alternatives 5-2 5.2.1 Deer Island-Nut Island Treatment Facilities 5-2 5.2.2 Nut Island-Deer Island-Long Island Treatment Facilities 5-3 5.2.3 New Island Option 5-4 5.3 Primary Treatment Alternatives 5-4 5.3.1 Deer Island-Nut Island Treatment Facilities 5-4 5.3.2 Deer Island-Nut Island-Long Island Treatment Facilities 5-4 6.0 EVALUATION OF THE OPTIONS 6-1 6.1 The Matrix of Findings 6-1 6.2 Screening Criteria 61 6.3 Findings of the Screening Process 6-7 6.3.1 Options Recommended for Further Study 6-8 6.3.2 Alternatives Eliminated 6-10 1. ------- 7.0 DETAILED DESCRIPTIONS OF FINDINGS 7-1 7.1 Summary of Analysis Results 7-1 7.2 Options Recommended for Further Study 7-2 7.2.1 Secondary Options 7-2 7.2.2 Primary Options 7-12 7.3 Options Not to be Studied Further 7-19 7.3.1 Secondary Options 7-19 7.3.2 Primary Options 7-26 8.0 REFERENCES 8-1 APPENDIX A. Public Participation Summary A-i B. Feasibility of Sub-Regional “Satellite” Treatment Facilities (under separate cover) ATTACHNENTS 1. Matrix of Findings 4-4 2. STEEPLI Impact Categories 6-2 3. Summary of Options and Their Impacts 7-2 4. Summary of Options and Costs 7-3 4a. Revised Cost Summary 7-4 5. Summary of Screening Results 7-6 12. ------- 1.0 SU1IMARY OF CONCLUSIONS This report defines the process followed in the first phase of the Supplemental Draft EIS (SDEIS) analysis by which eighteen siting options for wastewater treatment facilities to serve the Boston metropolitan area were screened to select the eight most feasible for further detailed study. These eight alternatives include four primary treatment and four secondary treatment options. Siting of major treatment facilities are proposed either at Deer Island (DI), Nut Island (NI) or Long Island (LI) in varying combinations as follows: Secondary Treatment (with harbor outfalls ) Option No . la .2 lb. 2 2b. 1. 2b .3. Secondary Treatment at DI, Headworks at NI. Secondary Treatment at DI, Primary Treatment at NI. Secondary Treatment at LI, Headworks at DI and NI. Secondary Treatment at LI, Primary Treatment at DI, Headworks at NI. 1—1 ------- Primary Treatment (with extended outfall)* Option No . 4a .2. 4b .2. 5a .2. 5b .2. Primary Treatment at DI, Headworks at NI. Primary Treatment at DI, Primary Treatment at NI. Primary Treatment at DI, Primary Treatment at LI, Headworks at NI. Primary Treatment at LI, Headworks at DI and NI. These alternatives were selected on the basis of an analysis of social, technical, economic, environmental, political, legal, and institutional impacts with input from those involved in the public participation process and comment by federal, state and local agencies. The most important criteria used in determining the feasibility and suitability of options were: 1. Engineering feasibility and economic cost. 2. Environmental impacts as they affect the people living and working in the communities impacted by the construction and operation of the proposed facilities. *Extended outfall with primary treatment is the stated preference of the Massachusetts Executive Office of Environmental Affairs and is the alternative submitted by the MDC under the federal review of a waiver from secondary treatment. 1—2 ------- 3. Site suitability, including size and accessibility, and the availability of buffer areas. 4. Potential for consolidation of treatment facilities to limit impacts, provide centralized construction and operations, and facilitate sludge disposal. 5. Opportunities for mitigation of adverse impacts. The following sections address the background studies leading to this SDEIS analysis, the objectives and scope of the analysis, formulation of the initial set of options, evaluation of the options, and detailed descriptions of the findings under each option. 1—3 ------- 2.0 BACKGROUND 2.1 Previous Wastewater Studies The SDEIS study now underway will supplement a prior EPA Draft EIS (DEIS) completed in 1978 and titled Draft Environmental Impact Statement on the Upgrading of the Boston Metropolitan Area Sewerage System . The DEIS examined a variety of wastewater management proposals presented by the Metropolitan District Commission (MDC) in the report, Wastewater Engineering and Management Plan for Boston Harbor - Eastern Massachusetts Metropolitan Area (EMMA Study) completed in 1976. The principal recommendations of the EMMA Study report were: 1. To upgrade the existing Deer Island and Nut Island treatment plants from primary to secondary treatment. 2. To dispose of sludge by means of incineration, as recommended in a separate report prepared for the MDC in 1973 entitled A Plan for Sludge Management . 3. To alleviate combined sewer overflows (CSO). 4. Construction of two advanced waste treatment plants on the Charles and Neponset Rivers. 2-1 ------- 5. Extension and improvement of the MDC’s interceptor system. After analysis and assessment of the impacts of the MDC’s proposals, the Draft EIS (1978) concluded that some elements of the EMMA Study (1976) were not suitable. The Recommended Draft EIS (1978) Plan included: 1. Centralized secondary treatment of all wastevater flows at a new facility on Deer Island with discharge to Boston Harbor. 2. Sludge disposal of primary sludge by incineration and ash land- filling at Deer Island (as recommended by EPA in a separate Final EIS on primary sludge disposal completed in 1979). 3. Sludge disposal of secondary sludge by a combination of incin- eration at Deer Island, landfilling at an unspecified MDC landfill, and composting at Squantuni in Quincy. 4. Upgrade of the existing interceptor sewer systems for the northern and southern Metropolitan Sewer District (MSD) areas to provide for expansion of the MDC system. 5. No construction of satellite advanced waste treatment plants discharging to tributary rivers at inland sites. 2-2 ------- 6. No specific proposals for alleviating CSO problems; separate CSO plans beyond the scope of the Draft EIS (1978) were being formulated and reviewed by the State and EPA. The recommendations of the Draft EIS (1978) were controversial and drew considerable public comment. Also, changes to the federal Clean Water Act occurred at that time which included provisions for waivers from secondary treatment levels ( 301(h) waiver). As a result of these events, EPA and the MDC reached agreement that detailed facilities planning should proceed on the upgrading of the wastewater treatment facilities in a flexible segmented fashion in order to accelerate actions needed to remedy the chronic problems and immediate upgrade needs of the MDC wastewater treatment plants and still provide for sequential decision making on an overall program for Harbor cleanup. Meanwhile, the MDC began work on a 301(h) waiver application for its proposed harbor treatment plant(s). This entailed an extensive analysis of water quality in Boston Harbor and designation of an extended effluent discharge location approximately seven miles into the ocean. An assessment of further wastewater treatment alternatives was also undertaken by the MDC in development of their facilities plans. First-phase recommendations were presented in the Nut Island Wastewater Treatment Plant Facilities Planning Project, Phase I 2-3 ------- Site Options Study , June 1982. This plan, referred to hereafter as the Site Options Study (1982), was prepared by Metcalf & Eddy, Inc. consultants to the MDC. It concluded that upgrading to primary treatment at both Deer Island and Nut Island with discharge via harbor outfalls was both environmentally sound and economically preferable. 2.2 Previous Sludge Studies EPA undertook a separate Draft and Final Sludge Management EIS which was concluded in 1979. This document provided an environmental evaluation of the MDC’s proposals for sludge disposal and concluded that incineration at Deer Island was the most cost-effective and environmentally acceptable sludge disposal method. EPA issued a Record of Decision on sludge management in 1980. The Record of Decision directed the MDC to continue environmental evaluation of incineration, as well as to examine further the feasibility of composting for the MDC system. This included EPA’s funding of a pilot composting facility located at Deer Island. MDC then issued a Sludge Management Update (1982) report to address these issues. Study of sludge management options continued by MDC and the State, focusing primarily on alternate disposal methods of composting, incineration, and ocean disposal. A state policy on sludge management has recently been formulated. It states that the preferred disposal method is composting, with ocean disposal and incineration as possible back-up methods. The 2—4 ------- SDEIS will review the three options under study to determine their influence on siting of harbor treatment facilities and any associated impacts resulting from sludge disposal facilities. EPA has not, as yet, reached a final decision on those issues remaining following the Record of Decision on sludge disposal and expects to conclude this review jointly with the State following development of sludge disposal facility plans. 2.3 Legal and Institutional Background While these studies were under way, a series of legal actions and State initiatives were instituted to improve water quality and coordinate State, Federal, and local facility planning efforts. The City of Quincy instituted a lawsuit against the MDC because of pollution of Quincy Bay by the Nut Island treatment plant. The Conservation Law Foundation instituted a separate lawsuit, also aimed at addressing the problems of pollution in Boston Harbor, against EPA, MDC and the Massachusetts Division of Water Pollution Control (DWPC) for alleged deficiencies in administrative and regu- latory reviews required of these agencies. This legal suit is still pending. The State court under the Quincy lawsuit appointed a Special Master to establish the facts in this suit. Following submission of his Findings of Fact in the case, the Court issued a ruling outlining a 10—year plan to clean up the harbor. The schedule for completion of the SDEIS conforms with this plan. 2—5 ------- Also, an independent advisory committee, known as the Boston Harbor Water Quality Committee (or Sargent Committee), was appointed by Governor Dukakis to examine programs and plans to improve water quality in Boston Harbor and to make recommendations to the Governor on the overall clean-up of the harbor. In further actions, on June 8, 1983, EPA issued a tentative decision denying the LIDC’s application for a waiver from secondary treatment requirements. This tentative finding was issued because of expected water quality and marine life impacts at the proposed outfall locations. The MDC has formally stated to EPA that it will reexamine those water quality impacts which led to a denial, and resubmit the application to EPA within one year. A final decision by EPA on the MDC Waiver Application will be made by March 1985. Concurrent with these events, the preparation of a SDEIS and Final EIS conforms with the overall schedule established by the Court. This schedule coordinates the various facilities planning elements which are being developed by federal, state and local parties. The SDEIS will be prepared and a draft copy reviewed during August of 1984. A final copy of the SDEIS will be distributed in October and a Public Hearing scheduled sometime that month or the next. Once all comments have been received following the close of the comment period, a Final EIS will be prepared and distributed in January of 1985. A Record of Decision by EPA on siting of wastewater treatment plants will consolidate the question of level of treatment and siting preference and is expected to be issued in March of 1985. 2-6 ------- 3.0 REPORT OBJECTIVES The SDEIS being prepared will enable EPA to provide funds for facilities proposed for the MDC System in Boston Harbor. The objectives of this report are to clearly define the first-phase screening process of the SDEIS by which the numerous siting options for wastewater treatment facilities to serve the Boston metropolitan area were narrowed to those judged to be most feasible. The report describes the steps followed in the analytical process leading to a determination of the most feasible options which will be subject to further detailed study. Supporting criteria and data utilized to reach these conclusions are presented. The results of this screening process are a final set of eight siting alternatives for further study, whose impacts will be analyzed in greater detail in the second phase of the SDEIS analysis. This set of eight options was derived from an initial listing of eighteen siting alternatives which were proposed at both coastal and inland sites. 3-1 ------- 4.0 SCOPE OF THE ANALYSIS Data from existing studies was used to perform the preliminary screening of all reasonable alternatives for the SDEIS. The principal sources used were: - EPA Draft Environmental Impact Statement on the Upgrading of the Boston Metropolitan Area Sewerage System (August 1978). - MDC Nut Island Wastewater Treatment Plant Facilities Planning Project, Phase 1, Site Options Study (Metcalf & Eddy, June, 1982) [ Site Options Study]. - MDC Wastewater Engineering and Management Plan for Boston Harbor — Eastern Massachusetts Metropolitan Area (Metcalf & Eddy, 1976 ) [ EMMA Study]. - MDC Application for Modification of Secondary Treatment Requirements for Its Deer Island and Nut Island Effluent Discharges into Marine Waters (Metcalf & Eddy, 1979 and 1983) [ reapplication due in June 19841. - MDC Wastewater Sludge Management Update (Havens & Emerson, 1982). - MDC Deer Island Facilities Plan, Vol. I, Fast-Track Improvements (Havens & Emerson/Parson Brinckerhoff, January 1984). 4-1 ------- Most of the data came from the MDC Site Options Study (1982). This data was updated and refined where applicable, and all previous cost figures were updated to an ENR of 4200. Meetings and discussions were also held with representatives of a variety of governmental and private organizations to obtain current information and copies of work in progress. These additional sources included: Metropolitan District Commission • Executive Office of Environmental Affairs • Department of Environmental Quality Engineering Division of Water Pollution Control Department of Environmental Management • Coastal Zone Management Office • Metcalf & Eddy, Inc. (Consultants to the MDC for Nut Island Facility Plan and 301(h) waiver application) Havens & Emerson/Parsons Brinkerhoff (Consultants to the MDC for Deer Island Facility Plan) In addition to the above named sources, further analysis, data manipulation, and collection of new data was carried out during this first phase of the SDEIS. This was done because in some cases existing information was out of date or inapplicable to the current evaluation of options; in other cases, new options not previously examined, such as man-made islands in Boston Harbor, satellite treatment facilities discharging to wetlands, and primary treatment on Long Island, were identifed for evaluation. The process was structured to use existing data where available and new data where 4-2 ------- necessary to select an optimal set of alternatives for further detailed study based on the application of defined screening criteria. The assessment undertaken was comparative in nature. The screening process enabled EPA to determine an optimal set of alternatives for further detailed study. The wastewater treatment facility options were examined for a determination of which options warranted further detailed study in the SDEIS. This was based on the application of the defined screening criteria, as noted above, and through the conduct of an evaluation of each option across several impact categories. The information that was compiled in this screening process has been summarized and presented in a condensed matrix shown in this report (Attachment 1). The matrix summarizes the options and their impacts with data reported in the matrix referenced by its source. Where data gaps or inconsistencies exist, this is noted in the matrix. A copy of the full matrix is available upon request from EPA. 4-3 ------- PAGE NOT AVAI LABLE DIGITALLY ------- 5.0 FORMULATION OF INITIAL OPTIONS 5.1 Introduction This Supplemental Draft EIS (SDEIS) in large part constitutes an environmental impact analysis of the facilities proposed in the MDC’s Site Options Study (1982). This facility plan evaluated eleven options for siting primary or secondary wastewater treatment facilities in Boston Harbor. The suing options evaluated in this facilities plan provided the initial definition and basis for options to be examined in the SDEIS. At the outset of the SDEIS analysis, a series of public scoping meetings was conducted to solicit input from citizens groups and the public at large, plus federal, state and local agencies. Comments were received on the various site options proposed and on the critical issues which should constitute the primary basis for an evaluation of impacts. As a result of those scoping meetings, the following additional options were considered for evaluation: 1. Primary or secondary wastewater treatment facilities con- structed on a new man-made island in Broad Sound (near the Brewsters or Lovells Island). 2. Consolidated primary and/or secondary wastewater treatment facilities sited on Long Island. 5-1 ------- 3. Separate primary wastewater treatment facilities sited on Long Island and Deer Island. 4. Sub—regional “satellite” facilities based upon recommendations previously presented in the MDC EMMA Study (1976) and the EPA Draft EIS (1978). 5. A proposal for satellite facilities, recently developed by the Quincy Shores Association Inc., with discharge into wetlands for effluent polishing and groundwater recharge. The complete list of prior and new alternatives determined to be most appropriate for analysis in this first phase screening process are described in the following section. 5.2 Secondary Treatment Alternatives 5.2.1 Deer Island - Nut Island Treatment Facilities a. Convert Nut Island to a headworks and construct secondary treatment facilities (either separate or combined system flows) at Deer Island; inter-island transport of effluent via tunnel. b. Construct upgraded primary treatment at Nut Island and construct secondary treatment facilities (either separate 5-2 ------- or combined system flows) at Deer Island; inter-island transport of effluent via tunnel. c. Separate secondary treatment facilities at Nut Island and Deer Island. d. Satellite AWT treatment facilities on the Neponset River, Charles River, or other locations in association with one of the above options. 5.2.2 Nut Island - Deer Island - Long Island Treatment Facilities a. Construct secondary treatment facilities (for north system flows) on Deer Island and secondary treatment facilities (for south system flows) on Long Island with preliminary treatment (either headworks or primary) facilities on Nut Island; inter-island transport of effluent via tunnel. b. Construct secondary treatment facilities on Long Island for combined system flows with preliminary treatment facilities (either headworks or primary) on Deer Island and Nut Island; inter—island transport of effluent via tunnels. c. Satellite AWT treatment facilities as noted above. 5-3 ------- 5.2.3 New Island Option a. Construct a new island site for secondary treatment facilities in an appropriate outer harbor location. 5.3 Primary Treatment Alternatives 5.3.1 Deer Island - Nut Island TreatmentFacjljties a. Construct combined primary treatment facilities at Deer Island with a headworks at Nut Island (and either a harbor or extended outfall); inter-island transport of effluent via tunnel. b. Construct separate primary treatment facilities on Deer Island and Nut Island (and either separate harbor outfall or combined extended outfall). 5.3.2 Deer Island - Nut Island — Long Island Treatment Facilities a. Construct separate primary treatment facilities at Deer Island (for north system flows) and Long Island (for south system flows) with headworks on Nut Island. b. Construct combined primary treatment facilities on Long Island (with extended outfall) with pump station on Deer 5-4 ------- Island and Headworks on Nut Island; inter-island transport of effluent via tunnels. 5-5 ------- 6.0 EVALUATION OF THE OPTIONS 6.1 The Matrix of Findings A matrix was developed to compare all options on the basis of a specified list of impacts*. The impacts were defined in seven cate- gories-—social, technical, environmental, economic, political, legal, and institutional (“STEEPLI”). These formed the matrix rows while the options formed the columns. Within each impact category, several sub-categories were defined (see Attachment 2). The expected impact of each alternative was then noted in the appro- priate cell of the matrix. For each impact and option, data was displayed either numerically or entered as a written description. The configurations of the various levels of treatment are displayed graphically in the matrix to show either headworks, primary or secondary treatment facilities. 6.2 Screening Criteria The next step in the screening process was to develop a basis for elimination and/or consolidation of the options. A set of screening criteria was developed with input from both the CAC (Citizens Advisory Committee) and the TAG (Technical Advisory Group) partici- pating on the project. *Satellite treatment facilities are an adjunct to harbor treatment sites and are evaluated in a separate technical report (Appendix B) to this report. 6—1 ------- ATTACHMENT 2 Impact Categories and Sub-Categories (STEEPLI) Social/Community Construction impacts Traffic and safety Noise/air quality/odor Property value Land use Social consequence Technical Level of treatment and acres required: Nut, Deer, Long, and other islands Average and peak daily flows and level of treatment in design year: north, south and combined systems Construction period System operation during Construction Energy requirements Long-term viability and opportunity for expansion/upgrade Relationship to other facilities’ plans (including immediate upgrade of system) Sub-regional systems and their relationship to harbor treatment facilities Economic Capital cost Operation and maintenance costs Present worth/annualized costs Local share (by town) User charges (per capita/family) Affordability Employment and wages Secondary economic benefits 6—2 ------- Environmental Water quality standards Recreational resources and visual quality (regional) Fisheries Habitats Air quality/health Other natural resources Political Federal: EPA EIS EPA 301(h) Army Corps of Engineers Other agencies State: MEPA MDC DEQE/DWPC CzM Other agencies Legislature Governor Boston Harbor Water Quality Committee (Sargent Comm.) Local: City of Boston/Suffolk County City of Winthrop Town of Quincy Other MDC member communities Other: CACs Houghs Neck and other Quincy residents Point Shirley and other Winthrop residents Quincy Shores Association Legal Permits required Statutory requirements/limits Compliance with court actions Institutional Institutions involved/affected Policies Management of facilities Other planning elements Site ownership and acquisition 6-3 ------- The CAC was asked to comment on the importance and relative weight of each of the “STEEPLI” impacts. They ranked the categories in the following order of importance: social, environmental, technical, institutional, economic, political, and legal. Within each category, the sub—categories considered significant to the siting process were identified as follows: • Social - construction activities, odor, property values, and land use; • Environmental — water quality, marine life, air quality, fisheries, and wildlife; • Technical - engineering feasibility, land availability, infil- tration/inflow impacts; and • Institutional — future planning, and growth/expansion of system. A Public Workshop was also held to solicit comment from the general public. The workshop audience placed a greater relative importance on economic impacts (cost of alternatives) than did the CAC, but in other areas expressed priorities and concerns comparable to those of the CAC. The TAG was also consulted for agency views on the alternatives. A questionnaire was used to identify TAG preferences for final 6-4 ------- alternatives. The majority of responses indicated a clear preference of TAG members for use of the Deer and Nut Island sites with various combinations of wastewater treatment. A minority of responses indicated that Long Island options should be studied further. No support was received for the outer harbor options. The factors most cited in support of these conclusions were costs, continuation of established land uses, environmental impacts, and management advantages of consolidating facilities. Upon review of the data developed, as arrayed in the matrix, and with consideration of comments from those participating in the EIS process, EPA and its consultants then determined which of the impact categories in the “STEEPLI t ’ matrix were most critical to the screening process. These impacts, along with three other factors mentioned below, became the basis for the final screening. The principal impact categories that were applied to the screening process which distinguished the more feasible options were: 1. Technical : site suitability, including adequate land area and appropriate buffer; access; and engineering feasibility. 2. eer.in: consolidation of major treatment facilities in the harbor to take advantage of centralized construction and operation activities; reduced operation and maintenance requirements; and consolidation of sludge handling and disposal. 6-5 ------- 3. Social : reducing construction and operations impacts on abutting residential neighborhoods, primarily as a result of increased traffic, duration of construction, and associated disruption; opportunities to apply mitigation measures to reduce adverse impacts. 4. Environmental : environmental effects of large-scale dredge and fill activities; recreational resources and visual quality impacts. Economic impacts are also an important criteria in selection of a final recommended plan, but were shown during the screening process to be secondary to the above criteria. This was based on estimated annualized costs for all of the various site options within their respective treatment levels which were within 10% of each other (with the exception of the new island alternatives)*. Thus cost could not be used to select between alternatives at this stage of review. In addition to the impact categories of the “STEEPLI” matrix, three other elements were factored into the screening criteria. These included: *This narrow cost range is reflected in a comparison of the acceptable primary and secondary options, respectively. The range for primary treatment options with a harbor outfall (no longer considered acceptable) reflect a 25% cost range. 6-6 ------- 1. ?IDC’s preferred primary and secondary options, as identified in the Site Options Study (1982), and the proposed option in the 301(h) waiver application included to address the recommenda- tions of the grantee. 2. State policy regarding the location of the primary treatment outfalls which led to exclusion from further study of alter- natives involving primary treatment with harbor outfalls. 3. Public comment on the preliminary screening recommendations circulated for review at meetings in Quincy and Winthrop. Analysis of these options during this phase of the SDEIS was based on a comparison of the screening criteria, preliminary analysis of impacts, outfall policy considerations, and public comment to develop a discreet set of options for further study in the following phase of the SDEIS analysis. 6.3 Findings of the Screening Process In screening the numerous options being considered for wastewater treatment facilities in Boston Harbor, several important elements associated with review of siting alternatives became clear. First, it was found that no alternative siting or treatment option is without potentially significant adverse impacts. Such impacts are associated with the effects of construction and operation activities upon nearby residential areas and the adjacent community at large, 6-7 ------- the effects upon the natural environment, cost of the proposed actions, and the potential incompatibility of wastewater treatment facilities with surrounding land uses. It must be noted also that none of the options satisfied all of the screening evaluation criteria. The combination of the size and complexity of the proposed project, the difficulty of siting such facilities in an urban area such as Boston, and the past poor performance of existing facilities has limited the acceptability of every option to one or another constituent group and neighboring community. Nonetheless, the alternatives selected best represent viable and realistic choices for further study of the siting feasibility of major wastewater treatment facilities in Boston Harbor. 6.3.1 Options Recommended for Further Study Options recommended for more detailed study were those which best met the established criteria, when compared to other alternatives recognizing that no alternatives could fully meet all the critieria. Options lacked sufficient analysis at this stage to determine their full impacts and were carried to allow such a more detailed analysis to be conducted in the next phase. Briefly summarized, the eight alternatives to be studied will examine both primary and secondary treatment options located at either Deer Island, Nut Island, or Long Island. Under secondary 6—8 ------- treatment levels, two options Cia and ib) consider secondary treatment at Deer Island with either headworks or primary treatment at Nut Island; one option (2b.l)proposes either headworks or pumping facilities at both Deer Island and Nut Island with consolidated treatment at Long Island; and one option (2b.3) would site primary treatment at Deer Island, secondary treatment at Long Island and headworks at Nut Island. For primary treatment levels, two options (4a.2 and 4b.2) consider primary treatment at Deer Island with either headworks or primary treatment at Nut Island; one option (5a.2) would site primary treatment at both Deer Island and Long Island and headworks at Nut Island, and one option (5b.2) proposes either headworks or pumping facilities at both Deer Island and Nut Island with consolidated treatment at Long Island. Two of these options noted above (lb and 4b.2) involving expansion at Nut Island were also retained because they were the preferred plans of the MDC. Section 7.0 discusses these options in detail. In order to reach a final recommendation in the SDEIS, subsequent detailed analysis in the second phase of the work plan will examine in greater detail the benefits and adverse effects of facilities at each of the three sites: Deer Island (DI), Nut Island (NI) and Long Island (LI). Each siting option will also be evaluated with analysis of mitigation measures to eliminate or limit potential adverse impacts. 6—9 ------- 6.3.2 Alternatives Eliminated This section sets forth the options that have been dropped and the major reasons for their elimination from further consideration (as specified by Federal CEQ guidelines S1502.14(a)). The following section of the report also discusses these options in detail. Four options (4a.l, 4b.l, 5a.1 and 5b.l) which included primary treatment and harbor outfalls were eliminated because of likely adverse impacts on water quality and the stated policy of the Commonwealth of Massachusetts that the harbor outfalls will not be considered further under primary treatment levels. Two options (3a and 3b) which provided for creation of man-made islands seaward of Boston Harbor were eliminated because of excessively high costs, and limited engineering and operational feasibility. Three options (ic, la.2 and 2b.2) which provided for expansion of the Nut Island wastewater treatment facility to secondary level were dropped because of lack of land availability and general absence of buffer space between the site and nearby residential neighborhoods. These plans would also require the greatest degree of decentralized plant operations and maintenance and would have resulted in adverse impacts across the broadest area of the harbor and land based areas. 6-10 ------- One option (2a.1) involving separate secondary treatment facilities on Deer Island and Long Island was also eliminated because it too resulted in scattered, multiple impacts and decentralized plant operations and maintenance. Subregional treatment or “satellite” facilities have been dropped from further study at this stage of analysis, because the anticipated benefits of such facilities are insufficient to offset their significant costs, questionable benefits and uncertain environmental impacts. Negligible system flow reduction would result from such plants. This conclusion is further documented in Appendix B issued as a separate volume to this screening report. 6—11 ------- 7.0 DETAILED DESCRIPTION OF OPTIONS 7.1 Summary of Analysis Results The following tables (Attachments 3 and 4) summarize the key impact findings and costs for the options considered. The impact categories listed reflect those identified as having the greatest significance, based on analysis and public comment, for the comparative screening phase. These results show those impact categories by option which are projected to have the greatest impacts and, in some cases, unacceptable impacts in comparison to other options available. The final eight options selected for further study cover a range of possible alternatives for treatment plant siting among those alternatives which appear must suitable based on the established criteria and impact comparisons. In addition, Attachment 4a presents a summary of recently revised costs for the eight preferred options to be studied in detail. These revisions reflect more recent reviews of the facility costs and 0&li costs for the preferred options carried out as part of the impact assessment analysis. This was carried out following selection of the preferred options and was based in part on further analysis and verification of the data developed in both the MDC Site Options Study (1982) and EPA Draft EIS (1978). As a result of these further reviews, the costs shown in Table 4a update those in Table 4. It should be noted, however, that these updated costs do not alter the prior screening conclusions since the relationship of 7—1 ------- PAGE NOT AVAILABLE DIGITALLY ------- ATTAC1I1 NT 4 BC TJ H RW)R SI IS: SUI ’1M7½RY OF OPTIONS ND THEIR INITEAT, (TjS1 + + Option No . SECONDARY + 1* fi 2 ) + b ( 2)$ ic 2a .1 2a .2 2b 4 1 2b • 2 2b.3 3a/b** PRIMARY 4a.l + _4•4 4b. 1* + 5a • 1 5a.z 5b.l + 5b.2 Nut Island a ( 2) • _ (;e) • — (36 ) • ( 2) • (18) a(2) • (18) • (2) • ( 2) • ( 2) a t 2 ) • (18) • •(•18) •(2) ,.... (3).... (2) Doer Island • — (115) • — ( US) • — (104) • — (104 ) • — (104) • ( 2) • ( 52) •(52) • C 2) • (62) • ( 52) (52J • ( 52) • ( 2) U ( 2) • ( 18) • ( 18) • (62 ) • (62) KEY: headworks only primary treatment secondary treatment D deep ocean outfall * MDC’s preferred options **a alongside Lovells Island b alongside Brewster Islands Assumes 8-1/8% interest rate over 20 years. + = preferred options 1 or detailed study 1 Assurn s all sts as developed initially in MDC Site Options Study (1982) yt--. (P M rnjjr, .. Tnr (M ’i 1A.1 R4 Sites, Level of Treatment, and (Acreaae Reauirad Long Zaland Other Ialand** Costs in Cuill •— — C 36) C 21) (115) C 68) 1 01) • (154) 9$ 1. O&M Annualized Costs*a* (SMilljons 131.3 8526 43.7 8874 45.2 136.4 884.4 43.4 134.3 897.9 46.0 138.3 915.5 46.1 140.2 998.5 43 7 i .45 .4 1001.8 48.9 151.9 49.5 1496 1515.9/2037.6 42.9+ 198.7/252.3 390.5 22.7 62.9 D 21.1 374.0 22.6 61.1 D 22.0 101.7 • 436.2 22.3 67.2 792.5 D 21.9 103 2 • 536.5 22.1 77.3 861.4 13 20.5 109.1 4 ------- ATTACHMENT 4a BOSTON HARBOR SDEIS: SUMMARY OF OPTIONS AND THEIR REVISED COSTS 1 Sites, Level of Treatment, and Coats in ( Acreage Required) SMillions _____ Annualized Other Coats 1 5 Option No. Nut Island Deer Island Long Island Island’ Capital O&M ( $14illions ) Secondary Opt.i.ons is • ( 2) (115) 869.68 43.7 133.1 lb * • (18) (115) 966.88 45.2 144.6 2b.i I ( 2) • ( 2) • (115) 1022.97 42.7 147.9 2b.3 • ( 2) • ( 52) • ( 81) 1061.48 48.5 157.6 Pr.un try Options 4a.2 D • C 2) • ( 62) 799.47 21.1 103.3 4b.2*D. S (18) 5 ( 52) 879.59 22.0 112.4 Sa.2 0 • ( 2) 5 ( 52) • ( 18) 875.77 21.7 111.7 5b.2 D • ( 2) • ( 2) 5 ( 62) 961.38 20.5 119.3 KEY: — headworks only 5 = primary treatment = secondary treatment D — deep ocean outfall * MDC’S preferred options AssUmes 8—1/8% interest rate over 20 years. 1. Revised costs reflect baseline construction factors with reduction in previously estimated secondary treatment costs and deletion (for the time being) of incineration coetøj see discussion in section 7.0. These revised Costs will increase upon addition of costs for sludge disposal facilities, as well as Costs for mitigation measures such as construction barging or reduced work schedules. These total costs will be presented in the SDEIS. Source: CE Maguire, Inc. (June17, 1984) ------- Costs between options has not significantly changed, and, as stated previously, costs were not a primary determinant in screening. The following discussion describes in greater detail each of the options considered and explains the basis for its inclusion or exclusion in further SDEIS analysis. The preferred eight options are listed first, followed by the remaining options considered. For each option, the information is summarized by the major impact categories analyzed — technical, social/community, engineering and economic, and environmental - with specific data presented by subcategories determined to be most significant. Attachment 5 further summarize these findings and conclusions for all options. For the category of impacts dealing with traffic and construction activities, no assumptions regarding barging of materials or workers have been factored into the analysis at this stage. This will be addressed in the detailed impact analysis for the SDEIS. 7.2 Options Recommended for Further Study 7.2.1. Secondary Alternatives la.2. Secondary Treatment (Separate Waste Flows) at DI, Headworks at NI. Technical : This option would convert the 17-acre Nut Island (NI) site owned by the MDC to a 2-acre headworks to screen and pump waste flows of the southern MSD to a consolidated secondary treatment 7—5 ------- Attachment 5 SUMMARY OF COMPARATIVE SCREENING RESULTS Facility Siting Option NI DI LI Other Screening Comments SECONDARY TREATMENT la (1 & 2) H P/S Recommended for further study ; 1978 Draft EIS preferred option; improvements at NI; community benefits in Quincy; consolida- tion of facilities; increased impacts of DI; lowest cost. lb (1 & 2) P P/S Recommended for further study ; preferred by MDC for secondary treatment; increased impacts at NI and in Quincy; higher costs; greater impacts at DI and in Winthrop. ic P/S P/S Major construction and opera- tions impacts at NI and DI; legal and environmental impacts to filling of Quincy Bay; higher costs; major separate plants at both sites; no apparent advan- tages. 2a.1 H P/S P/S Major construction and opera- tions impacts at DI and LI; possible preclusion of other uses at both sites; conflict with prison and hospital; higher costs; dispersed facili- ties at three sites; does im- prove conditions at NI, but not to any greater degree than other less costly more advan- tageous options such as la, ib, or 2b. 2a.2 P P/s S Increased construction and operations impacts at NI with no appreciable advantages at DI or LI compared to prior choice; higher cost; major facilities at all sites; Op- tions la, ib, and 2b appear preferable. 7-6 ------- Facility Siting Option NI DI LI Other Screening Comments 2b.1 H H P/S Recommended for further study ; significant potential benefits at NI and DI; consolidation advantages; among the highest cost; greatest impacts at LI with possible preclusion of other present and future uses; adverse impacts likely to occur in Squantum/Quincy with Pos- sible mitigation opportunities to minimize traffic or other effects. 2b.2 P P S Additional impacts at DI; from expanded facility size; in- creased NI and LI impacts; higher costs; no advantage over Option 2b.3. 2b.3 H P P/S Recommended for further study ; improved at NI; DI increase in facility size and potential impacts in nearby community; major new impacts at LI with possible preclusion of other uses and likely conflict with the hopsital; higher cost; most removed from nearby residential areas. 3 H H P/S Highest potential impacts; highest costs; difficult and long construction; greatest operational difficulties; envi- ronmental impacts high; im- provements at NI and DI not suf- ficient to offset impacts/costs; other options afford better bal- ance and likely acceptable cost effectiveness. 7—7 ------- Facility Siting Option NI DI LI Other Screening Comments PRIMARY TREATMENT 4a.1 H P (Harbor Out- Harbor outfalls not recommended falls) based on State 301(h) reapplica- tion preference; independence of outfall from siting decision. 4a.2 H P (Extended Recommended for further study ; Outfall) improved conditions at NI with reduced impacts in Quincy; im- pact at DI in Winthrop; consoli- dated facilities; comparable costs considering long outfall. 4b.1 P P (Harbor Out- Not considered as noted above; falls) MBC’s Site Options Study pre- ferred option. 4b.2 P P (Extended Recommended for further study ; Outfall) NBC ’s 301(h) preferred option; increased impacts at NI; in- creased impacts at DI; separate facilities with associated con- struction effects and staffing/ maintenance requirements; higher costs; maintins present facility siting; no consolida- tion. 5a.1 H P P (Harbor Not considered as noted above. Outfalls) 5a.2 H P P (Extended Recommended for further study ; Outfall) improved conditions at NI and on Houghs Neck; community im- pacts in Quincy and in Point Shirley/Winthrop area; impacts introduced to LI, however, mini- mal (18 acre) area required; possible conflict with recrea- tional plans; higher costs; separate treatment facilities with potential for mitigation of adverse impacts. 5b.1 H H P (Harbor Not considered as noted above. Outfalls) 7—8 ------- Facility Siting Option NI DI LI Other Screening Comments 5b.2 H H P (Extended Recommended for further study ; Outfall) reduced impacts at NI and DI with major facilities removed from proximity to residential areas; greatest impacts at LI with preclusion of some land uses, and possible conflict with hospital; adverse impacts likely in Squantum/Quincy with possible mitigation opportuni- ties for the optins; higher costs potential benefits at NI and DI. 7—9 ------- facility on Deer Island (DI). In this option, some buffer area would be available on NI to better separate the proposed facility from abutting residences. The headworks facility would be located on the site of the present treatment plant in the vicinity of the existing administration building. On DI, the 210-acre site under multiple ownership could accommodate a proposed secondary treatment plant encompassing about 115 acres. The present primary treatment plant covers about 26 acres. Most of the expanded facility construction on DI would occur towards the southern portion of the site which is vacant. Additional buffer areas on DI would be limited due to the short causeway leading to the site from nearby residential areas, and the close proximity of the Suffolk County/City of Boston prison just to the north of the existing treatment plant. Some encroachment of an expanded treat- ment plant on the prison could occur, although future consolidation of the prison would make available additional land for siting of treatment facilities. Social/Community : During construction, impacts would occur at both Deer and Nut Islands and in the adjoining communities of Winthrop and Quincy. At NI, an average of about 13 workers and 35 trucks daily would travel to the site. Construction activities would last 3 to 4 years, and impacts would be limited to the site, with moderate additional traffic in Quincy and through Houghs Neck. During future operations of the headworks, a total staff of 20 would be maintained over three daily shifts. This option would improve 7—10 ------- conditions on the site through a reduced facility use and minimize impacts upon abutting residential uses in Hough’s Neck and in Quincy. At DI, the construction period would last about 7 years. Major impacts would result from the daily transportation of an average of 415 construction workers, and up to a peak of 940 truck trips per day through Winthrop (as well as through Boston and other neighboring communities). This estimate and those for all options assumes (at this stage of the preliminary analysis) that no barging activity or other mitigation to reduce the truck or auto traffic is employed. Operations staff at DI would increase to 230 persons from the 160 presently employed at the plant. Engineering and Economic : This option would consolidate treatment at a single facility on DI, thereby affording benefits of centralized operations and maintenance. Sludge disposal would likewise be consolidated at a single site. Treatment facilities proposed in this option would be located at the site of an existing treatment plant, allowing possible reuse of certain components at the site. Preliminary cost estimates for this option are among the lowest of the secondary treatment options. Construction costs are estimated to be $852.6 million with operations and maintenance (0&Z1) costs at $43.7 million. The annualized costs for debt service (20 years at 8-1/8%) and O&N are $131.3 million. 7—11 ------- Environmental : This option would impose no additional adverse impacts upon the use, water quality, or recreational resources of the Harbor beyond the limited, controlled period of its construc- tion. Visual quality at DI would be impacted due to the expansion in the size and number of treatment works there. Access to and use of the site would remain limited by the security requirements of the prison on the island. Buffer zones and screening could be established at DI, however, the expanded size of the facility would nmke it visible from numerous locations on land and from water. At NI, a reduction in the size of the facility to a headworks would allow the introduction of plantings or earthwork which may improve present visual intrusion upon nearby residences. Noise and odor problems emanating from the present plant would be lessened. However, the small size of the island limits its potential as a site for new recreational areas or other uses of benefit to the community. This option is recommended for further study based on its having sufficient area on DI to accommodate expanded treatment facilities, its utilization of existing treatment sites and the advantages of consolidation as noted above, and the improvements to the NI site. lb.2. Secondary Treatment (Separate Waste Flows) at DI, Primary at NI Technical : This option expands the present treatment facilities at both NI and DI. It is the preferred choice of the MDC for secondary 7-12 ------- treatment. The 17 acre NI site would be converted to a larger primary treatment plant requiring a total of approximately 18 acres, of which 1 to 3 acres would be filled land added to Quincy Bay. Expansion at NI would necessitate utilizing the full extent of the site for expanded facilities, reducing the already limited separation between the treatment plant and abutting residences. The 210-acre DI site could accommodate a secondary treatment plant of 115 acres. While there is sufficient area on DI to accommodate the expanded plant, there may be some encroachment onto the site of the existing prison facility. Expansion on DI would utilize most of the presently vacant land on the island. Social/Community : During construction, major impacts would result at both DI and NI and in the adjacent communities of Winthrop and Quincy. At DI, construction would last 7 years with an average of 412 workers and up to 880 truck trips daily passing through Winthrop during peak activity. Operational staff required at DI would be 215 persons. At NI, construction would last for 5 years and would be significant with 36 workers and 40 truck trips daily at peak. Operations staff at NI would be 83 persons. Engineering and Economic : This option maintains separate primary treatment facilities and consolidates secondary facilities at two locations in the harbor. As such, it does not fully consolidate operations or maintenance and sludge disposal requirements, although savings are achieved at the secondary level from centralization at 7—13 ------- DI. Preliminary costs of this option are $887.4 million for construction, $45.2 million for O&N, and $136.4 million annualized cost. Environmental : This option would pose added environmental and water quality impacts as a result of harbor filling needed to expand the present site at NI. Constraints would exist due to the state prohibitions against harbor filling. Visual quality would be altered significantly at NI from the enlarged and expanded facilities and total utilization of the site with closer proximity and greater scale of treatment works to abutting residences. No buffer zones or screening would be possible. At DI, this option would be comparable to option la.2. As one of the MDC’s preferred facility plan options, this option is recommended for further study. 2b.1. Secondary Treatment at LI, Headworks at DI and NI Technical : This option would convert the existing 26-acre DI treatment plant to a pump station (2—acre) and the 17-acre NI treatment plant to a headworks (2-acre) to respectively pump and screen waste flows to a new consolidated secondary treatment plant of 115 acres on Long Island (LI). The total area of LI, which is owned by the City of Boston, is 213 acres. 7-14 ------- A treatment plant could be accommodated on LI; however not without encroachment upon existing and proposed future uses there. The LI Hospital currently occupies about 26 acres in the central portion of the island, with the remaining areas of the island vacant. An abandoned Nike missle base is also situated in the central part of the site with a former U.S. defense installation, Fort Strong, and a lighthouse located at the northern head of the island. There is a ‘causeway and bridge connecting LI to Moon Island and Quincy. The condition of the bridge will have to be investigated relative to its use by heavy construction traffic. Social/Community : Impacts of this option during construction would be significant, involving an estimated total peak level of 428 workers and 975 truck trips daily traveling through Quincy to both LI and NI. The construction period at these sites would be 3 to 4 years at NI and 9 years at LI. These levels of construction activity would impose major adverse impacts upon the Squantum community and moderate impacts upon nearby residential areas of Houghs Neck. Conditions on-site at NI would be improved with improvements for abutting residences. During operations, total daily staffing levels over these shifts would be 20 persons at NI and 215 persons at LI. At DI, construction activities would require 28 workers and 35 truck trips per day over a 4 to 5-year period. This would impose moderate traffic impacts on the community while it improved conditions 7-15 ------- on-site and for abutting residential areas. Operational staff at DI would be 40 persons over three daily shifts. Engineering and Economics : This option consolidates all treatment at a new site on LI with smaller headworks and pumping facilities at NI and DI, respectively. This would afford benefits of centralized operations, maintenance and sludge disposal. Preliminary costs of this option entail $998.5 million for construction, $42.7 O&H, and $145.4 million annualized cost. Environmental : Improvements and potential benefits would result on both DI and NI from reduction to pump station and headworks respectively of the present treatment facilities located there. On NI, this would be most beneficial to abutting residences in Houghs Neck (as noted in option la.2), while on DI the reduction of the present treatment plant to a pump station would lessen the visual impacts and odor and noise problems currently experienced by residents of Point Shirley in Winthrop. However, the continued operation of the prison on DI and size of the pump station would limit access to and use of the site. Buffer areas and screening could be established on both DI and NI. On LI, there would be major impacts due to the potential conflict of treatment facilities with the existing hospital and proposed recreational use under the Boston Harbor Islands State Park plan. In addition, known historical and archaeological resources, including a cemetary, would be impacted by siting of a treatment 7-16 ------- facility. Visual impacts on LI and of views from Boston Harbor would be significant with a large facility as proposed. This option is recommended for further study based on its potential for benefits at DI and NI from reduction of treatment facilities and the improvements to abutting residential areas in both communities. It would site major treatment facilities furthest away from residential areas. Impacts on LI involving the hospital use, recreation plans and open space, visual quality, and preclusion of other use potential on the island will be analyzed in greater detail. 2b.3 Secondary Treatment at LI, Primary Treatment at DI, Headworks at NI Technical : This option would construct new primary treatment facilities for southern IISD flows and consolidated secondary treatment facilities at LI. The size of the treatment facilities at LI would be about 80 acres of the 213-acre island. NI would be converted to a headworks (2-acre). At DI, the present primary treatment plant of 26 acres would be expanded to double its size (52 acres) to accommodate an upgraded primary treatment plant for northern MSD flows as presently is treated. Land area is available at all three sites to accommodate the proposed facilities. At all three sites, also, sufficient area 7—17 ------- exists to allow for buffer zones with possible screening provided although NI affords the least opportunity for buffer. On DI, expanded facility construction would occur on the vacant portion of the site to the south; on LI, construction would be in the central portion of the island in the area of the abandoned Nike installation. Social/Community : During construction, the average number of construction workers at peak would be 360 at LI, 13 at NI and 80 at DI. Truck traffic would involve about 535 vehicle trips through Quincy, mostly through the Squantum community, and 335 vehicle trips through Winthrop. Construction would last about three to four years on NI, four to five years at DI, and eight years at LI. Operational staff for these facilities would number 130 persons at LI, 12 persons at NI and 41 persons at DI over the three daily shifts. Impacts from traffic would be greatest in this option on LI and in Squantum and through parts of Quincy leading to LI. Access over the LI bridge would require further investigation. Impact on DI would be significant from an expanded and larger sized primary treatment facility with traffic impacts through the neighboring community. On LI, there would also be potential for impacts on historical and archaeological resources, like in option 2b.1, and encroachment upon the hospital site is possible. At DI, the treatment plant would require additional area which presently is unused open space although encroachment on the prison grounds may occur. At NI, 7-18 ------- reduced facilities to a headworks would improve site conditions and minimize impacts upon abutting residences. Engineering and Economics : Separate primary treatment facilities on LI and DI with consolidated secondary treatment on LI would afford lessor consolidation advantages at the primary treatment level than other options noted above. Some reuse advantages could result on DI from siting at an existing facility. Preliminary costs for this option are estimated at $983.5 million for construction and $48.5 million for O&M, with $149.6 million in annualized costs. Environmental : This option’s environmental impacts are similar at LI to those described for option 2b.1. The acreage requirements would be slightly less; however, the extent of land area disturbed to accommodate treatment facilities and a relocated roadway would approach the disruption under the larger sized option. At NI, the impacts would be comparable to those under option la.2. At DI, impacts would result from the expansion of treatment works to double the present size. Encroachment upon the prison may occur. Under this option reuse potential of remaining open space areas to the south would be limited by the continued security restrictions of the prison. Visual intrusion of the treatment plant (and the prison) would continue and be increased by the expanded facility size. 7—19 ------- 7.2.2 Primary Alternatives 4a.2 Primary Treatment at DI, Headworks at NI (Extended Outfall) Technical : This option would site an expanded consolidated primary treatment plant (62 acres) on DI with a headworks (2 acres) on NI. Present treatment facilities on DI encompass 26 acres of the total 210 acre site, while at NI they cover most of the 17-acre site. Both sites can readily accommodate a facility of the type proposed. Sufficient buffer area exists with screening possible to limit views from nearby residential areas and improve views from points in Boston Harbor. Social/Community Impacts : Construction activities under this option would last between three and four years at NI and five to six years at DI. An estimated 414 workers and 480 truck trips per day would travel through Winthrop. In Quincy, there would be 13 workers and 39 truck trips daily. At NI, construction impacts due to traffic would be moderate with limited on-site disruption. Reduction of facilities on-site would improve conditions relative to abutting residences. At DI, site impacts would be significant from the expansion of the present facility. Traffic impacts on local roads are likely to cause disruption of normal traffic patterns and access through Winthrop and neighboring communities. Point Shirley residents would experience the greatest disruption from both increased heavy vehicle traffic and on-site activities. Operations 7-20 ------- staff at DI would require 136 persons over three daily shifts, while at NI the figure would 20 persons. Engineering and Economics : This option maximizes consolidation advantages associated with operations, maintenance and sludge disposal at a single treatment plant on DI. Preliminary costs under this option are $759.6 million for construction, $21.1 million O&H, and $99.1 million annualized cost. Environmental : Impacts under this option for DI and NI are comparable to those in option 2b.3. The slightly larger consolidated facility under this option (62 acres) would still be readily accommodated at DI with open space areas remaining to the south. However, the securi.ty requirements of the prison would limit, if not preclude, new recreational or other uses on DI. There would be construction impacts as noted on-site and in Winthrop. At NI, the reduced facilities would improve conditions on-site and lessen impacts to abutting residences, but the small ara of the site limits its future reuse potential. This Option is recommended for further study based on its consolidation advantages, the partial improvements expected at the NI site and benefits to nearby residences at Houghs Neck. 7-21 ------- 4b.2 Separate Primary Treatment at DI and NI (Extended Outfall) Technical : This option would maintain and expand primary treatment facilities at both DI and NI. It is the preferred primary treatment choice of the MDC in their 301(h) waiver application. At DI, the present 26-acre treatment facility would be expanded to a 52—acre facility, while at NI the entire 17-acre site would be utilized for treatment works, plus new landfill would be required of one to three acres in Quincy Bay to accommodate an expanded treatment facility. Sufficient area exists at DI to accommodate new facilities, including buffer areas and screening opportunities. However, there may be some encroachment on the nearby prison grounds. At NI the present site is inadequate for expansion, and filling of the harbor would pose additional constraints to construction (particularly in light of the local and state legal prohibitions against such action). Limited buffer area would be available at NI, and abutting residences would be even closer to treatment facilities which would be larger and more extensive than the presently in operation. Social/Community Impacts : Construction activities at DI would involve and average of 340 workers and 355 daily truck trips through Winthrop. Impacts of traffic on local roads and of construction activities on site and to adjacent residential areas would be significant. The duration of construction activities would be six years. At NI, the number of average daily construction workers and trucks are 38 and 95, respectively, over the projected five-year 7-22 ------- construction period. Impacts on residents of Houghs Neck and in Quincy during construction from traffic and on-site activities would likewise be significant. Operations staffing at DI would be 80 persons and at NI 55 persons over three daily shifts. Engineering and Economics : This option would expand and maintain separate primary treatment facilities at two locations in Boston Harbor. No advantages of consolidation would be achieved in this option compared to other choices noted above. The preliminary costs of this option are estimated to be $774.8 million for construction, $22 million for O&}1 and $101.7 annualized cost. Environmental : The impacts under this option are comparable for NI with option lb.2 and for DI with option 2b.3. The impacts on the environmental and water quality resources of Quincy Bay from filling would be significant. On DI, the impacts of construction traffic on local roads in Winthrop and the effects of construction activities on the residents of Point Shirley would be significant. This option is recommended for further study based on its recom- mendation by the MDC in their 301(h) waiver application, and the question of its possible operational advantages versus siting impacts at the NI site. 7-23 ------- 5a.2 Separate Primary Treatment at DI and LI, Headworks at NI ( Extended Outfall) Technical : This option would build a new 18-acre treatment plant on LI for southern MSD flows, a 52-acre treatment plant on DI for northern ?ISD flows, and a headworks at NI to screen flows prior to conveyance to LI. Sufficient area exists at all three sites to I accommodate the proposed facilities. Buffer areas would be available and screening could be provided to minimize or enhance views of the facility. Some encroachment of proposed facilities with other site uses could result at DI with the prison and at LI with the hospital and recreational plans for the island. Social/Community Impacts : Construction activities under this option are dispersed over three separate sites over a period of three to four years for the headworks at NI and six years each for treatment facilities at DI and LI. Daily average construction workers would number 77 at LI, 13 at NI, and 340 at DI. Truck trips during construction would number a total of [ 17 vehicles in Quincy at both NI and LI and 335 vehicles in Winthrop at DI. These impacts would be significant, disrupting local traffic and access in both Quincy and Winthrop and in their respective neighborhoods closest to the sites. On-site impacts at NI would be moderate affecting Houghs Neck in Quincy, while they would be greater at LI affecting Squantum also in Quincy. At DI impacts would be greatest impacting most upon Point Shiny in Winthrop and upon the on-site use of DI and the prison. 7-24 ------- Engineering and Economics : Consolidation would not be achieved under this option. Separate primary treatment plants at DI and LI with further remote headworks at NI are proposed. Additional operations, maintenance and sludge disposal requirements and higher costs would result. Preliminary costs under this option are estimated to be $792.5 million for construction and $21.7 million 0&M with $103.2 million annualized cost. Environmental : Impacts at NI and DI under this option are comparable to those described under option 2b.3. In addition, at LI there would be significant impacts from siting of a 18-acre facility adjacent to an existing hospital. Further significant impacts are likely from on-site archaeological and historical resources on LI and from possible incompatibility with the state’s plans for recreational uses on the island. This option is recommended for further study based on its potential benefits at NI and limited expansion at DI. Its limited siting on LI, although accommodated, requires further analysis to determine the extent of potentially significant impacts there and in Quincy. 5b.2 Primary Treatment at LI, Headworks at DI and NI (Extended Outfall) Technical : This option would convert DI to a pumping facility and NI to a headworks (2 acres each), and would consolidate all treatment on LI (62 acres). All three sites can accommodate the 7-25 ------- proposed facilities with available buffer areas based on their existing acreages of 210 acres at DI, 213 acres at LI, and 17 acres at NI. Screening could further limit views of the facilities at all three sites from nearby residential areas or from Boston Harbor. Possible encroachment of proposed facilities may occur at LI with the hospital use there or with recreation plans for the island. Social/Community Impacts : Construction activities would be moderate at DI and NI and greater at LI. At DI, an average of 28 construc- tion workers and 39 truck trips occur over a five—year period. At NI, an average of 13 workers and 35 truck trips would occur over a three to four-year period. On LI, an average of 340 workers and 355 truck trips would last over a seven-year construction period. Disruption and impacts at DI and NI under this option would be moderate due to a reduction of facilities and are comparable to those under option 2b.1. At LI, traffic impacts in Quincy and to residents of Squantum would be major. The greater distance of the LI site from the nearest residences would minimize the influence of on—site construction impacts such as noise and dust. Engineering and Economics : Consolidation under this option would be maximized with all treatment at LI, comparable to advantages under option 2b.1. Preliminary costs would be $861.4 million for construction, $20.9 million O&M and $109.1 million annualized cost. Environmental : Impacts of this option at DI and NI are comparable to option 2b.1. At LI, the proposed facility (62 acres) could be 7—26 ------- accommodated, but not without impacts on the hospital and potential archaeological and historical resources in the vicinity of the site. Recreational plans for LI would possibly also be in conflict with the proposed treatment plant. This option is recommended for further study in order to analyze issues such as that of access to LI via the bridge and the extent of improvements on—site at DI and NI, as well as to the neighboring communities of Winthrop and Quincy adjoining the two sites. 7.3 OPTIONS NOT TO BE STUDIED FURTHER 7.3.1 Secondary Options la.1 Secondary Treatment (Combined Waste Flows) at DI, Headworks at NI This option was similar to la.2 as described in the previous section with only its internal piping of treatment flows configured differently. It was dropped from further consideration, since it was not appreciably different than Option la.2 and it did not appear to offer any significant advantages. 7-27 ------- lb.1 Secondary Treatment (Combined Waste Flows) at DI, Primary Treatment at NI This option is not considered further, since it is essentially the same as option lb.2 described in a previous section as noted above. ic. Secondary Treatment at DI and NI Technical : This option would expand both existing treatment plants to separate secondary plants. At DI, this would entail a 104-acre facility; at NI, the proposed facility would require 36 acres. At NI, the existing 17—acre site would require about 20 acres of fill to Quincy Bay in order to accommodate the proposed larger facility. Buffer zones or screening would be limited at the NI site under this option. Proximity to nearby residential areas at NI would be greater. At DI, land is available to accommodate the larger facilities; however, encroachment on the prison area would likely occur. Other uses at DI would be limited under this option. Social/Community : Impacts at DI would be comparable to those described under option lb.2 as described in the previous section, with the modification of a longer nine-year construction period. There would be somewhat reduced traffic levels under this option with an average of 225 workers and 690 truck trips daily. Impacts on-site and in Winthrop would be significant. At NI, the impacts of such an expanded and larger facility at the site would pose severe adverse impacts and disruption to residents of Houghs Neck and 7-28 ------- Quincy. Traffic during construction at NI would entail a daily average of 110 workers and 230 truck trips. Construction duration at NI would be for nine years also. Operating staff at DI would be 150 persons and at NI would be 80 persons over three daily shifts. Engineering and Economics : This option offers no consolidation advantages. Its preliminary costs are estimated at $884.4 million for construction, $43.4 million 0&Z1, and $134.3 million annualized cost. These costs are comparable to other options due to the elimination of a need for inter-island conduits to convey flows even though separate major treatment facilities would be built. Environmental : This option impacts environmental parameters and particularly water quality in Quincy Bay, on-site land uses on DI and NI, and adjoining residential areas and communities to a greater degree than other options. It would preclude any On-site mixed uses and limits establishment of buffer zones. It also advisely impacts visual quality in the harbor by establishing separate major facilities of such large scale and visual intrusion. This option is not recommended for further study based on its major on-site and neighborhood impacts and its clear unsuitability of siting a secondary treatment plant on NI. 7-29 ------- 2a.1 Secondary Treatment at DI and LI, Headworks at NI Technical : This option would place separate secondary treatment plants at two harbor locations, while reducing one present site to a headworks. DI would be the site of a major 104-acre facility, while LI would be the site of a major 36—acre facility. Both sites can accommodate such facilities based on their 210 acre and 213 acres respective areas; however, at DI encroachment on the prison would result with limited buffer areas available, while at LI encroachment on potential archaeological and historical resources, proposed recreational plans and on the hospital are likely. NI would show improved site accommodation from location of a proposed 2-acre headworks. Social/Community Impacts : Impacts at NI are moderate and comparable to those described under option la.2; DI impacts are significant and comparable to those described under option lc. At LI, there would be an average of 150 construction workers and 340 truck trips daily. The duration of construction activities would be three to four years at NI and seven years at LI. At DI, construction is estimated to last eight years. Construction traffic, involving an average 250 workers and 690 truck trips at DI, and 163 workers with 375 truck trips at NI and LI, would pose significant impacts on the local roads in Winthrop and Quincy and would result in major disruption to the communities of Point Shirley and Squantum with lesser impacts at Houghs Neck. Operations staff at these sites would involve 12 7-30 ------- persons at NI, 75 persons at LI and 140 persons at DI over three daily shifts. Engineering and Economics : This option offers no consolidation advantages with major facilities sited at two separate island locations. Its preliminary costs are estimated at $897.9 million for construction, $46 million for O&I1, and $138.3 million annualized cost. Environmental : At DI and NI this option’s impacts are comparable to those under option la. Under this option, some uses at LI would be precluded with significant impacts resulting. There exists at LI a potential for adverse impacts upon archaeological and historical resources, and encroachment on the hospital site is possible. Recreational uses may likewise be impacted under this plan. This option does not meet sufficient criteria relative to other choices to warrant its further study. 2a.2 Secondary Treatment at DI and LI, Primary at NI Technical : This option would locate secondary treatment facilities of 104 acres at DI and 21 acres at LI, while siting a primary treatment plant of 18 acres at NI. There is adequate land area at both DI and LI to site such uses, although at DI a facility would encroach upon the adjoining prison site, while at LI encroachment may occur with regard to historical or archeological resources. Buffer areas are available at both locations with opportunities for 7-31 ------- screening of the facility from view. At NI, the present 17-acre site would require one to three acres of fill to Quincy Bay to accommodate a primary treatment plant. Social/Community : Impacts of this option are major and wide ranging, given the distribution of traffic and construction impacts over three sites and two adjoining communities. These impacts are comparable for DI and LI to those described in option 2a.1 above. At NI, impacts would be comparable to those described in option lb.2 described in the previous section. Engineering and Economic : No consolidation advantages are attendant with this option to site three major separate treatment facilities at separate sites in Boston Harbor. Preliminary costs are estimated at $915.5 million for construction, $46.1 million 0&I1, and $140.2 million annualized cost. Environmental : This option would impose major impacts at all three sites with filling of Quincy Bay a principal concern. Land use impacts and those on adjoining communities would be comparable at NI to those described under option lb.2 and at DI and LI to those described under option 2a.1. This option is not recommended for further study based on the extent of impacts and lack of compliance with the established criteria relative to other options. 7-32 ------- 2b.2 Secondary Treatment at LI, Primary Treatment at DI and NI Technical : This option would maintain and expand primary treatment facilities at DI (52 acres) and NI (18 acres) with a new consolidated secondary treatment facility on LI (68 acres). These facilities can be accommodated at both DI and LI with unavoidable encroachment on abutting land uses and resources at both sites. At NI, the proposed facility could not be teadily accommodated requiring fill to Quincy Bay. Social/Community : Construction impacts under this option from workers and trucking activities would pose major disruption to both adjoining communities and at each of the three sites. Impacts at NI are comparable to those described under option lb.2 in the previous section. At DI and LI, impacts would be comparable to those described under option 2b.3, although the size of the LI facility is slightly smaller. Engineering and Economic : This option affords no consolidation advantages with major treatment facilities at three separate locations in Boston Harbor. Preliminary costs are estimated to be among the highest at $1001.8 million for construction, $48.9 O&?1, and $151.9 annualized cost. Environmental : Impacts under this option would be major and wide ranging across all three sites and in both adjoining communities of Winthrop and Quincy. Filling of Quincy Bay would pose environmental 7-33 ------- and water quality impacts. Impacts are comparable at NI to those described under option lb.2 described in the previous section; DI and LI impacts are comparable to those described under option 2b.3. This option is not recommended for further study based on its greater impacts and lack of compliance with the criteria. 3a/b. Man—Made Island Adjacent to Lovells Island or The Brewsters Technical : This option introduces unique construction solutions in order to locate treatment facilities in the outer harbor furthest away from residential areas. DI and NI would be converted to pumping and headworks facilities respectively. It would require major dredging, filling and stabilizing of the island’s shallow water areas; all—weather barging with no land backup would be the sole access; construction of additional storm barriers and protective jettys are needed; and the existing islands would be physically altered. This option would create a filled area of 154 acres adjacent to the existing island sites. Social/Community : Construction impacts, in addition to the unique engineering and special construction practices necessary, would involve 400 to 500 construction workers at the outer harbor locations, plus another 13 workers at NI and 28 workers at DI. More than 900 truck trips daily would be required and converted to barge transport. These requirements alone make this option highly speculative. Operations staff would be 140 persons over three daily shifts to be barged to the treatment plant. 7-34 ------- The only advantage of such a plan would be the removal of major treatment facilities furthest away from residential areas. However, the limitations of such an approach appear to outweigh its advantages. Engineering and Economics : While this plan consolidates treatment at a single site, this is not as feasible a solution to achieve that goal as other options. Preliminary costs for this option are significantly higher than all others at $1515.9 to $2037.6 million for construction, $43 million plus for 0&M, and $198.7 to $252.3 million annualized costs. Enviromental : The considerable consequences for marine habitat and water quality during construction, plus the major additional costs associated with transport of staff and materials to the site during construction and operations are of such magnitude and uncertainty that the potential for adverse impacts far outweighs any of the possible benefits. In fact, other options offer far greater benefits at lower costs and with fewer likely adverse impacts. This option is therefore not recommended for further study. 7.3.2 Primary Options 41.2 Primary Treatment at DI, Headworks at NI (Harbor Outfall ) 7—35 ------- 4b.1 Separate Primary Treatment at DI and NI (Harbor Outfall) 5a.1 Separate Primary Treatment at DI and LI, Headworks at NI ( Harbor Outfall) 5b.1 Primary Treatment at LI, Headworks at DI and NI (Harbor Outfall ) All of the above primary treatment options with harbor outfalls into Boston Harbor are not Consistent with the recently stated policy of the Commonwealth of Massachusetts Executive Office of Environmental Affairs and the MDC Commissioner, which favor an extended outfall with primary treatment. These options are not, moreover, among those proposed by the MDC under their 301(h) waiver application. Therefore, primary treatment options with harbor outfalls are not recommended for further study. Since this conclusion only deals with the length and location of an outfall conduit and does not affect the siting of treatment facilities, any future change in policy regarding outfall locations could readily be accommodated to the EIS process at a later date. 7-36 ------- 8.0 REFERENCES 1. EPA Draft Environmental Impact Statement on the Upgrading of the Boston Metropolitan Area Sewerage System (August 1978). 2. MDC Nut Island Wastewater Treatment Plant Facilities Planning Project, Phase 1, Site Options Study (Metcalf & Eddy, June, 1982) [ Site Options Study]. 3. MDC Wastewater Engineering and Management Plan for Boston Harbor - Eastern Massachusetts Metropolitan Area (Metcalf & Eddy, 1976 ) [ EMMA Study]. 4. MDC Application for Modification of Secondary Treatment Requirements for Its Deer Island and Nut Island Effluent Discharges into Marine Waters (Metcalf & Eddy, 1979 and 1983) [ reapplication due in June 1984]. 5. MDC Wastewater Sludge Management Update (Havens & Emerson, 1982). 6. MDC Deer Island Facilities Plan, Vol. I, Fast-Track Improvements (Havens & Emerson/Parsons Brickerhoff, January 1984). 7. MDC, Discharges from Moon Island . Camp, Dresser & McKee, Inc. - Draft Report March 28, 1984. 8-1 ------- 8. MDC, Report on Combined Sewer Overflows in the Dorchester Bay Area . Camp, Dresser & Mckee, Inc. - October 1980. 9. MDC, Combined Sever Overflow Report, MDC, Inner Harbor Area Facilities Plan . O’Brien & Gere Engineers, Inc. - January 1981 8-2 ------- APPENDIX A PUBLIC PARTICIPATION STJMNARY Barry Lawson Associates, Inc. Public Participation Coordinator ------- INTRODUCTION Two Public Information Meetings were held during January 198 I to obtain public reaction to the Environmental Protection Agency’s (EPA) recommendations that the eighteen major wastewater facilities siting options be narrowed down to six for further study. The meetings were sponsored jointly by the EPA and the Commonwealth of Massachusetts’ Executive Office of Environmental Affairs (EOEA) as part of their joint environmental review of alternative sites for wastewater treatment facilities for the Metropolitan Sewerage District (MSD). In order to obtain comments from residents most directly affected by the present (and possibly future) plants, one meeting was held in Quincy and one in Winthrop. The meetings were advertised in the local press and announced on local radio. A news release was sent to about 25 media outlets. State and local elected officials, members of the Citizens Advisory Committee and Technical Advisory Group members were personally invited to attend and/or submit written testimony. Approximately 100 people attended each meeting. A comment period followed the meetings, during which written comments were received and reviewed. Michael Deland, EPA’s Regional Administrator, welcomed those attending the public meetings. He stated that a Boston Harbor clean—up would benefit more communities and individuals than any other project in the region. He stressed the commitment of both EPA and the Commonwealth to the selection of an alternative which will mimimize adverse community impacts. He also emphasized his agency’s commitment to reviewing the widest possible range of options and analyzing thoroughly the impacts of options recommended for further study. Secretary Hoyte of EOEA reiterated Mr. Deland’s comments on the importance of the siting project. He then described the steps the state is taking to obtain immediate improvements in the wastewater system: o EOEA has sought increased staffing and resources for the Deer and Nut Island wastewater treatment plants. o EOEA is working with William Geary of MDC and Amy Anthony of the Executive Office of Communities and Development to develop a long—term water and sewer management plan. o DEQE is developing a comprehensive Infiltration/ Inflow (I/I) relief plan and legislation will be filed shortly for a $100 million I/I removal grant program. o EOEA is working actively with the Massachusetts congressional delegation to obtain federal long—term funding sources. o EOEA is committed to immediately improving the Deer and Nut Island treatment plants. William Geary, Commissioner of the MDC, acknowledged the problems associated with the MDC’S role in wastewater treatment. He stated that it is important to determine how to repair these facilities. He stressed that the MDC serves inland communities A—i ------- from Framingham to Reading. Wastewater treatment facilities siting is not solely a problem faced by Winthrop, Quincy or Boston but is also a regional problem. Each MSD community must take responsibility for absorbing environmental and financial costs associated with adequate wastewater treatment. If we fail to act in a concerted fashion, he said, the judiciary will take from our hands the means by which we can rectify our own problems. This could result in grave consequences, such as sewer moratoria, which could impair growth. He mentioned that he was encouraged by the improved lines of communication with the EPA evidenced by this SDEIS process. EPA’s David Fierra (in Quincy) and Robert Mendoza (in Winthrop) briefly reviewed past studies conducted on wastewater treatment facilities siting, and described the timetable for the development of the SDEIS. They also described the 301(h) process whereby the MDC is applying for a waiver of ehe req 4rement to provide secondary treatment at its plants. The EIS will be finalized in December 198k, and will contain a preferred primary and preferred secondary alternative site. The decision on which option is selected will be made concurrently with the decision on the 301(h) secondary treatment waiver process, expected by about March 1985. Daniel Carson of C.E. Maguire, Inc., EPA’S consulting engineers, described his firm’s preliminary screening analysis and conclusions. He presented a handout showing a site comparison, principal screening criteria used to select alternatives, preliminary recommendations of which options would be recommended for further study, and possible mitigation measures to minimize or eliminate potential adverse impacts resulting from the construction and operations of proposed harbor treatment facilities. At the Quincy meeting, Mr. Carson also detailed the reasons for recommending that sub—regional (satellite) treatment plants be dropped from further consideration at this time. He emphasized, however, that the consultants will be recommending consideration of satellites as part of future wastewater planning beyond the scope of this work. The remainder of the meeting was moderated by Barry Lawson of Lawson Associates, Inc. The comments which are summarized in Part I of this documuent were those made orally at the meeting, on the participation sheets which were distributed, or those sent to EPA as part of the screening process. Comments have been grouped together by issue or topic and restated for clarity. Responses follow each issue and were either those given at the meeting or those formulated by EPA following agency review and deliberation. Part II of this document contains EPA responses to specific questions listed on the participation sheets or posed at the meetings. Part III is a summary of all formal written statements received and EPA responses where appropriate. Part IV is a tabulation of responses to the Participation Sheets which were distributed at the public meetings. PART I — SUMMARY OF IMPORTANT ISSUES/EPA RESPONSES Use of Long Island as a Site for Wastewater Treatment Facilities Opposition : Many people at the Quincy meeting expressed opposition to the use of Long Island as a site for a wastewater treatment facility. Its potential as a regional recreational facility was stressed as was a desire to avoid simply transferring all the negative impacts of wastewater treatment from one harbor island to another. The attorney who reviewed the screening results on behalf of the Squantum Community Association stated that the consultants’ recommendations imply A—2 ------- that siting a wastewater treatment plant at Long Island will have virtually no residential impact. However, she and several others expressed their strong concerns about traffic and other impacts on the Squantum neighborhood and, indeed, all of North Quincy. The costs associated with repairing and maintaining the bridge to Long Island were seen as factors which would limit the site’s availability, as was assumed opposition from the City of Boston. While opposition in Quincy to use of Long Island was strong, a minority felt that it was a suitable site for a wastewater treatment facility. A representative of the City of Boston Department of Health and Hospitals strenuously opposed the use of Long Island, stating that a wastewater treatment facility is inconsistent with the Island’s present use as a chronic disease hospital and with the possible development of non—hospital related activities. In his view, Deer Island has been dedicated by the City of Boston for such uses as the Deer Island House of Correction and neither the present wastewater treatment facility, nor any of the recommended Deer Island options, would impair these uses. By contrast, the construction of a primary or secondary wastewater treatment facility on Long Island would forever eliminate opportunities for non—hospital related uses. Support : Attendees at the Winthrop meeting overwhelmingly supported placing all primary and secondary treatment at a new facility to be constructed on Long Island. Many people felt that the City of Boston (owner of Long Island) has an obligation to share some of the burden of wastewater treatment because a large percentage of the region’s waste is produced by Boston and because Boston has been encouraging a building boom with little concern about the problems of treating the resulting increased wastewater. Others stressed the isolated nature of the Island and the fact that it was far away from dense residential areas, which, they felt, would result in the fewest adverse impacts. It was also stated that sufficient land would remain for recreational purposes. EPA Response : The options of siting MDC wastewater treatment facilities on Long Island received significant support from some parties and raised serious opposition from other groups. EPA will evaluate various wastewater treatment scenarios for Long Island in the Supplemental Draft EIS and appreciates the level of public involvement expressed at the Quincy and Winthrop Public Information Meetings. The agency wishes to emphasize that the purpose of the preliminary screening process is to identify which alternatives warrant further study in the SDEIS. The benefits and impacts of siting a treatment facility on Long Island will be fully evaluated during the development of the SDEIS. These alternatives will be compared to similar environmental impact analyses of the Deer and Nut Island site options. Final recommendations will then be put forth for a preferred primary site and a preferred secondary site based on a thorough impact analysis. Mitigation (and compensatory) measures necessary to make the siting decision acceptable will be included as part of the final recommended plan. Use of Deer Island as a Site for Wastewater Treatment Facilities Opposition : The majority of those attending the meeting in Winthrop were opposed to the use of Deer Island as a site for wastewater treatment facilities. They favored using Deer Island as a headworks facility, an option not recommended for further study by the consultants. Many people spoke of the adverse impacts from the present A—3 ------- facility, particularly noise, odor and traffic impacts. They felt that ill effects caused by poor maintenance, poor operational policies, lack of proper personnel and misplacement of the plant have been borne by the Town of Winthrop and this could only be remedied if Deer Island were no longer used as a treatment facility. Many were angry that Winthrop has had to host or be adversely affected by a disproportionate number of regional facilities, including the Deer Island House of Correction, Logan Airport, and the Deer Island Wastewater Treatment Plant. They felt that this burden should be shared more equitably. Another reason for opposition to use of Deer Island as a site was fear that the plant would need to be expanded in the future. According to this view, if the plant were relocated (to Long Island) now, residents of Winthrop would never be faced with the issue again. Many of those present felt that the options presented by the consultants did not represent a balance between impacts and benefits. They pointed out that even the so—called “status quo” option, consisting of primary treatment at Deer Island, would involve many years of construction impacts associated with the rebuilding of the plant. Finally, mention was made of the recreational potential of Deer Island if the wastewater treatment facilities were removed. Support : Limited support was expressed in Winthrop for options 14b2 and 5a2, which would involve separate facilities with Deer Island taking no more flow than it already receives. Support for alternatives Ia or a2 (combined primary or secondary treatment at Deer Island) was expressed by several Quincy meeting attendees. They stated that consolidated treatment at one site would be best for Boston Harbor as a whole and would lead to centralized, consolidated and accountable management of the sewerage system. Deer Island was said to be a more suitable site because of its large area. Several mitigation and compensation measures were suggested, such as barging and busing of construction workers and supplies to Deer Island; opening of Shirley Gut with passenger vehicle access to the prison maintained by a drawbridge manned by prison personnel; sewage assessment exemption; odor/noise control; visual shielding; and improvement of future plant operations by changing the governing structure of the Metropolitan District Coismission. EPA Response : Several Deer Island alternatives will be evaluated as part of the SDEIS, including: the use of Deer Island as a headworks facility, primary and secondary treatment of North System flows, and primary and secondary treatment of consolidated System flows. The use of Deer Island as a site for wastewater treatment raised serious community concerns in Winthrop, but received considerable endorsement from other groups. EPA would like to emphasize that no decisions have been made at this point in the SDEIS other than the recommendation to narrow the range of sites to Deer, Long and Nut Islands. The environmental impact analysis will fully evaluate the serious community concerns raised at the public information meetings in Winthrop and Quincy. Deer Island alternatives will be studied on an equal basis with other alternatives to determine the most environmentally sound, cost—effective site for MDC wastewater treatment facilities. Use of Nut Island as a Site for Wastewater Treatment Facilities Opposition : Opposition to the use of Nut Island was not so vocal as opposition to Long and Deer Islands, due to the fact that the consultant’s preliminary report listed Nut Island as the least suitable of the sites for a major wastewater treatment ------- facility. Four of the six options recommended converting Nut Island into a headworks. Opponents noted neighborhood impacts in the Hough’s Neck area and objected to the filling of the Harbor needed to construct new facilities at Nut Island. Some pointed out that current state law prohibits any filling of Quincy Bay. The problems of constructing on filled land were emphasized. Several people noted that the present Nut Island facility’s primary sedimentation tanks had settled, causing disruption to the treatment process. There were claims that landfill negatively affected the Harbor’s flushing action and that further filling would damage the area’s fish resources. Support : There was very little support for the location of a treatment plant on Nut Island. Written comments from the Boston Harbor CAC expressed disappointment that the MDC preferred option consisting of upgraded primary treatment at Deer and Nut Islands with a local outfall, had been dropped from consideration. This group felt this option to be a good first step which could be immediately implemented. State Representative Saggese (Winthrop) expressed support for option qb2, which consists of primary treatment at Deer and Nut Islands with a deep ocean outfall. EPA Response : Use of Nut Island as a site for treatment of South System flows and for a headworks facility will be evaluated in the SDEIS. As with the other two sites under consideration, Nut Island was recommended for further study, but no final decision can be made until the environmental impact analysis is completed. Need for Sub—regional (“Satellite”) Treatment Facilities Considerable support was expressed for decentralization of the MDC treatment system and reduction of flows to the MSD. Many of those attending the Quincy meeting wanted to retain consideration of sub—regional, or satellite, treatment facilities to attain these goals. State Representative Brownell stated that such facilities should have been adopted many years ago. In his view, this would have avoided the present situation in which Quinoy and Winthrop must continue to be host communities simply because wastewater facilities are already located in these communities. The Charles River Watershed Association asserted that satellite treatment facilities are needed now to correct serious deficiencies, not simply for the unspecified future. The issue of the equitable distribution of wastewater facilities was raised frequently, with many stating that “upstream” communities are insensitive to wastewater treatment problems because of an “out of sight, out of mind” mentality. It was the view of several meeting attendees that all communities should share the problems along with the benefits of wastewater treatment. Many called for a moratorium on expansion of the Metropolitan Sewerage District. One Quincy resident specifically asked that all information upon which the decision to eliminate satellite treatment plants was based be made public. It was also recommended that an in—depth study on the feasibility of satellite wastewater treatment facilities be initiated soon, since planning for new facilities can take years. One person suggested that every community (in the MSD) have a mini—plant to screen and treat sewage before it reaches the main treatment plant. EPA Response : As part of the documentation of the screening of alternatives for further study, A—5 ------- EPA is issuing a separate evaluation of the need for satellite treatment facilities for the Metropolitan Sewerage District (MSD). This document, entitled “Evaluation of Satellite Advanced Wastewater Treatment Facilities”, is attached as Appendix B of this Final Screening Report. The report documents the factors which led to a judgment that proposed satellite treatment options are not a feasible alternative at the present time. It was determined that these options do not influence the sizing or siting of Harbor wastewater treatment plants, and pose potential water quality and public health problems. In particular, the State strongly opposes wetlands disposal of treated effluent. As a follow—up to this conclusion, and as part of the EIS, EPA will be outlining the long range options and benefits associated with satellite treatment plants for the MSD. Other causes of pollution in Boston Harbor: Combined sewer overflows (especially Moon Island); Infiltration/Inflow; Sludge Considerable attention was focused on other components of the wastewater collection and disposal system which many felt contributed as much, if not more, to the overall Harbor pollution problem as faulty or overloaded treatment plants. The Boston Harbor CAC cautioned that the total cost of a Harbor cleanup must be factored into the treatment plant siting decision or it is likely that the price will be considered too high. Combined sewer overflows (CSO’s) were frequently mentioned as prime causes of pollution leading to periodic beach closures. Several people faulted the EPA for not giving consideration to repairing and upgrading the Boston Water and Sewer Con nission’s Moon Island facility which, it was charged, periodically discharges untreated waste into the waters off Squantum. The cumulative effect of all sewage discharges must be considered when evaluating the water quality impact. The Boston Harbor CAC suggested that water quality in Boston Harbor could be significantly improved if funds which would be needed to construct a deep ocean outfall were instead used to address the Harbor CSO problem. Another concern was the tremendous amounts of Infiltration/Inflow (I/I) entering the MDC system through cracked or leaky pipes and illegal connections of storm drains into the sanitary sewer system. Millions of gallons of extra flow enters the system in this way and leads to wastewater treatment plant overloads and discharge of sewage through CSO’s. One person stated that significant flow reductions are a necessary part of’ a long—term solution to wastewater problems and another advocated progressive user fees, with metering if necessary, to place the financial burden of’ treatment at its source. A third concern was the issue of sludge disposal. One person expressed opposition to the use of incineration as a method of disposal, while another asked whether ocean incineration was under consideration. Concern was expressed that the analysis of the options presented by the consultants didn’t take into account the impacts of the probable location of a sludge incinerator on the same site as the wastewater treatment plant. Finally, one person cited the tide gates in the system as a source of’ pollution and suggested their elimination and the re—routing of sewage into the system. A—6 ------- EPA Response : The MDC prepared a CSO Facilities Plan in 1980 which inventoried the 108 CSO’s in the Boston Harbor area and suggested ways of controlling them. To date, three CSO projects are moving into the construction phase. The state is setting up an interagency group to review the status of the remaining CSO’s and develop a master plan for their correction. EPA reviews the environmental impacts of the correction programs and participates in funding the projects as they develop on the state’s priority list. In addition, EPA has directed its consultant, C.E. Maguire, to investigate in the SDEIS possible inclusion of the Moon Island overflows or other CSO sources to a new treatment facility on either Deer Island or Long Island. On the issue of Infiltration/Inflow (I/I), EPA agrees that flow reductions are a necessary part of the long—term rehabilitation of the MDC infrastructure. The Massachusetts Department of Environmental Quality Engineering (DEQE) is pursuing I/I reduction and rehabilitation in member communities. DEQE has filed legislation to provide $100 million for a grants program to fund up to 90% of the cost of I/I reduction. On the issue of sludge management, the SDEIS will integrate the EOEA sludge management policy into the siting evaluation. EOEA has reviewed three sludge management techniques: composting, incineration and ocean disposal, and has formulated a sludge management policy for the MDC. Composting has been recommended as the preferred solution for handling MDC sludge. The SDEIS will evaluate the siting impacts of these three sludge management options in conjunction with its review of siting impacts of wastewater treatment facilities. Support for Deep Ocean Outfall At both meetings there was considerable support for selecting an option containing a deep ocean outfall. The basic argument put forward is that disposal of treated wastewater should not take place in areas close to residential neighborhoods and beaches. It was stated that a deep ocean outfall would provide the lowest potential for irreparable environmental harm. Several people requested assurances that, if approved, EPA would enforce construction of the deep ocean outfall. Others supported the concept of deep ocean outfall, but asked how EPA would safeguard the Harbor to ensure that raw sewerage would not be pumped far out to sea. Some opposition to a deep ocean outfall was expressed. The Boston Harbor CAC stated that it is easier to monitor water discharged in the Harbor than water discharged beyond the Harbor. The group did not want a Harbor cleanup at the expense of the water quality in the outer Harbor. EPA Response : At the Quincy public information meeting, MDC Commissioner William Geary stated his agency’s support for pursuing a deep ocean outfall in its 301(h) secondary treatment waiver reapplication to EPA. Based on EOEA’s commitment to a deep ocean primary outfall, EPA has retained only those primary options which propose a deep ocean outfall. The SDEIS will not make a water quality determination on these primary alternatives because the 301(h) waiver application will evaluate the acceptability of a primary effluent at the deep ocean site. The SDEIS will evaluate A—? ------- the water quality impacts of secondary effluent within the Harbor. Regional Administrator Michael De].and pledged to use EPA’s enforcement powers to ensure that federal requirements are carried out. Level of Treatment: Primary vs. Secondary The majority of the comments on this issue centered on the impacts on communities, rather than the environmental merits of construction and operation of secondary treatment plants. A great deal of support was expressed for granting of the MDC’S request to EPA for a waiver of the requirement to provide secondary treatment (the “301(h) waiver”) because construction of a primary treatment plant would necessitate far less land than a secondary plant. Others supported secondary treatment at specific sites. EPA Response : The level of treatment required will be determined as part of EPA’s review of the revised MDC 301(h) waiver application. A revised application is expected to be submitted to EPA by June of 19811 and a final decision on the waiver will be made by March of 1985. Mitigation and Compensation The possibility of devising ways of reducing the effects of adverse construction and operating impacts of awastewater treatment facility was widely discussed. Opinions varied considerably. Many of those who felt mitigation was feasible said every possible measure should be taken to protect the safety and convenience of neighborhood residents, regardless of potential inconvenience to contractors, construction workers or suppliers, and increased operation and maintenance costs. Many proposed water—based transportation (barging) of construction workers and material; noise and odor control methods; visual screening; modified construction scheduling; reduction/elimination of sewer assessments; and financial compensation for the burdens of hosting such a facility, among other methods. Others felt that no mitigation measures are possible. Several Winthrop residents said that there would be limited opportunities for mitigation in Winthrop at the scale of construction proposed. EPA Response : EPA views mitigation of adverse impacts as an essential step in determining an environmentally acceptable solution for siting of wastewater facilities in Boston Harbor and will include mitigation measures in the evaluation of each alternative. Investigation of Other Sites One person proposed that EPA should erect a sewage treatment plant on land underneath the “Northeast” Expressway, Route 93, using a high technology laser beam method of treatment. EPA Response : This proposal offers some unique state—of—the—art concepts which are as yet A—8 ------- unproven. The likely high cost of such a technologically sophisticated system would be expected to be prohibitive. Annual energy and operational costs would likewise be very high compared to conventional treatment systems. Also the technical sophistication and newness of laser treatment is likely to make such a system susceptible to malfunctions beyond the norm for sewage treatment plants. As for the suggestion of a treatment plant location on land underneath Route 93. the relocation of these facilities to other inland sites appears infeasible for the following reasons: the limited availability of 50 to 100 acres suitable to accommodate treatment plants; the likely prohibitive costs of renovating existing sewers, interceptors and pumping stations; the problem of locating suitable effluent discharge lines from the treatment plants; and as yet uncertain requirements for sludge handling and disposd’l. Modified No Action Option Many people expressed opposition to keeping this option under consideration. Since the current situation is in violation of the Clean Water Act, it was stated that the “modified no action” option is illegal and should not be pursued further. It was clear that most of those attending the meetings felt that action must be taken to upgrade and improve harbor treatment facilities. EPA Response : EPA will not be studying “modified no action” as an option for Boston Harbor; however, as part of the National Environmental Policy Act (NEPA), a description of the existing and future environment without the proposed overall improvements must be documented. The agency will use existing information to document the environment in Boston Harbor and will briefly describe what the immediate improvement programs in the treatment plants will achieve for short—term water quality improvements. These descriptions will serve as a baseline against which to compare the various “action” options under study. Management of the MDC System Many comments focused on MDC’s ability to operate and maintain a wastewater treatment system efficiently and effectively. Many said that poor management by MDC has led to the current controversy over siting of improved wastewater treatment facilities. They doubted that MDC could maintain newly constructed facilities. Several expressed the view that an independent water and sewer authority is the only way to guarantee proper management of the system in the future. EPA Response : EPA Administrator Michael Deland has stated his support for an independent authority to guarantee proper management of the Metropolitan Sewerage District. A—9 ------- PART II — QUESTIONS AND ANSWERS ON SPECIFIC CONCERNS ’ (‘Taken from Participation Sheets distributed at meetings) Q: What safeguards will EPA impose to insure that raw sewerage is not being pumped out to sea? A: EPA has an influence over treatment plant performance in two basic ways: first, since EPA will be granting money to the MDC to build proposed treatment plants under the Clean Water Act, the MDC facilities must be designed using specific approved and accepted design standards intended to maximize plant performance and reliability in order to meet the applicable water quality standards. Such standards include the inclusion of redundant or back up systems and machinery (such as pumps). Lack of back up equipment and poor maintenance has been a major cause of raw sewage bypassing at both Nut and Deer Island facilities in recent years. The second major influence EPA has over treatment plant performance is through effluent discharge monitoring and permitting. By monitoring the quality and quantity of MDC’s discharges, corrective action can be enforced if plant performance falls below the level specified by the discharge permit issued by EPA. Q: Will present treatment plant options be large enough for future growth and expansion needs? A: The harbor facilities options under study in the SDEIS are being sized to handle all the flow which may physically reach the plant or plants through existing sewer interceptors (which currently convey sewage to the facilities at Nut and Deer Islands). Population and usage forecasts presented in the Nut Island Site Options Study suggest that these main interceptors are large enough to handle all the flow which is likely to be generated in the existing service area over the 20 year planning period. However, at some future time, population growth in the existing service area, and/or service area expansion may cause future flows to exceed interceptor capacity. Future plans should evaluate the use of inland (satellite) treatment plants as one possible alternative to interceptor enlargement and harbor facility expansion. It must be pointed out, however, that even with present “average” sewage flows less than the peak capacity of the interceptors leading into the Nut and Deer Island treatment plants, wet weather conditions quickly result in peak hydraulic flows. In fact, a portion of the system’s sewage flows never reach the treatment plants because of leaks, combined sewer overflows (CSO’s), “bottle necks”, and other hydraulic limitations and problems upstream in the sewer system. These leaks and overflows contribute significant amounts of raw sewage to the Harbor from sources in addition to the plants themselves. Finding and implementing remedies for these hydraulic problems is an ongoing effort of the state and federal governments — efforts which are consistent with, but separate from, the actions under study in the SDEIS. A—iD ------- Q: Why is the water in Quincy Bay brown? A: Although the SDEIS water quality evaluations are still underway and no conclusive determination is possible at this time, there appear to be several possible sources for the “brown” color of Quincy Bay’s water: o sewage effluent o stormwater and urban runoff o salt marsh detritus o resuspension of bottom muds by tide/wave action o brown algae It is likely that all of these sources contribute to the water’s color. As with other water quality criteria, color is expected to fluctuate daily, as environmental conditions vary. Q: Have satellites been ruled out as an option? A: See response to comments made at public meetings. Q: Why was the water quality so poor in the ser of 1982 and 1983 when it was not so consistently poor before that? A: Yearly changes in water quality are difficult to doc ent, and vary by location, activities and background water quality parameters. It is assumed that the question refers to water quality in shoreline areas around the treatment plants, in which case one possible answer is that equipment failures at the treatment plants and wet weather conditions caused an unusually high amount of raw sewage bypassing the plant during 1981, 1982 and 1983. However other pollution sources, such as CSO discharges and urban runoff also contributed to this problem. Q: Would new primary treatment plants at Nut Island and Long Island require further filling of Quincy Bay? A: If a new primary treatment plant were built on Nut Island to treat south system flows only (SDEIS options lb and 14b.2), the MDC estimates that 1 to 3 acres of Quincy Bay would need to be filled. This estimate may be reduced if buffer areas are not included in the design criteria for such a facility. No filling of Quincy Bay would be required to build any of the primary treatment facilities under study for Long Island. Under secondary treatment options (Option ic) it was proposed that upwards of 20 acres be filled in Quincy Bay. Due to the potentially severe environmental impacts and other unacceptable consequences of this option, it was eliminated from further study. Q: Has filling over the years to build up beaches (especially Wollaston Beach) changed the flushing ability of the tides? A: Filling to build up beaches does not, per se, significantly restrict tidal flushing actions. However, where tidal channels are restricted, for example by bridge abutments or causeways, tidal flushing behind or upstream of the restriction will be limited and more brackish or freshwater species may replace saltwater fauna and flora. In general, tidal action continually alters shoreline A—li ------- areas moving sand and soil particles from one location to another. Q: Wouldn’t proper primary treatment at Nut Island necessitate 23 additional acres rather than one additional acre? A: No. According to the Nut Island Site Options Study , between one and three additional acres of land, depending on the size of buffer areas, would be needed at Nut Island to site a primary treatment facility built to current standards. Secondary treatment facilities at Nut Island, an option judged to be unacceptable and not recommended for further study, would require about 20 acres be filled. Q: C.E. Maguire estimates that only one acre of fill would be required to construct a primary treatment facility at Nut Island without a buffer. Does this take into consideration where construction—related materials would be stored? Does it take into consideration roadways and employee parking? A: C.E. Maguire’s preliminary evaluations related to plant size and layout at Nut Island are based on tIDC’s engineering estimates presented in the Nut Island Site Options Study . The range of fill estimated is 1 to 3 acres, reflecting differences in amount of buffer areas and the like. The plant layout shown in Volume I, Figure 5—10 of that study suggests that adequate lay down areas, roads and parking areas are provided. Q: What is the status of the Boston Harbor Water Quality Committee and the Master appointed by the courts? A: The Boston Harbor Water Quality Committee, also known as the Sargent Committee, was established by Governor Dukakis to examine, coordinate and make recommendations on the problems and needs of Boston Harbor in order to begin to address the pollution problems in the harbor. The Committee is examining such diverse and related issues as treatment plant siting, sludge disposal, a new water and sewer authority to replace the present structure at the MDC, water quality and environmental resource issues and other associated elements. The Committee expects to make its final recommendations to the Governor in April. Their findings and conclusions will be incorporated into the analysis for the SDEIS. Q: What is the status of sludge management planning? A: The most recent plans concerning sludge management include engineering studies done for the MDC in 1973 and updated in 1983 which recommended incineration of primary sludge at a facility to be built on Deer Island. A Draft and Final Environmental Impact Statement (EIS) prepared by EPA (concluded in 1979) supported the HDC’s recommended disposal plan but also directed the MDC to investigate composting of sludge as an additional method. In addition, a separate Draft ElS prepared by EPA in 1978 concluded that in addition to incineration of primary and some secondary sludge, composting of some remaining secondary sludge should be done at a site on Squantum in Quincy, while the remaining secondary sludge should be landfilled at an unspecified MDC—owned site. Since those studies and decisions, the Commonwealth of Massachusetts has undertaken a comprehensive study to determine the most acceptable method of sludge disposal/management. The Commonwealth evaluated three alternatives: A—i 2 ------- incineration, composting, and ocean disposal (barging). The Commonwealth has decided that composting is the preferred method of sludge handling. They also plan to explore the feasibility of ocean disposal as a back up disposal method. The preferred Commonwealth sludge handling and disposal methods will be incorporated into the eight treatment plant alternatives which remain for detailed analysis. Q: Why hasn’t a study been conducted on the effects of treatment plants on the health of area residents? A: The question of the effects of treatment plants on the health of area residents is a critical one which affects people’s daily lives. Public health threats along shoreline areas involving beaches and shellfish resources are more frequent than is acceptable and efforts to address these problems are currently underway. These efforts include the current work to site new, improved treatment plants for the MSD and the State and EPA’s work to eliminate the present sludge discharges to the harbor. Other pollution sources, of perhaps even greater impact upon public health, such as CSO discharges and urban runoff, add to the complexity and seriousness of this problem. No one pollution source is solely responsible for public health threats. Therefore, any solution to these problems must be a coordinated response involving a variety of projects beyond the scope t the SDEIS. Public health issues are more appropriately considered by the state and local authorities. The Massachusetts Division of Public Health and Division of Water Pollution Control (DWPC) are involved in monitoring these issues in Boston Harbor, as is the MDC, while local health departments in Winthrop, Quincy and other shoreline and inland communities likewise are monitoring water quality at beaches and other recreational areas. Q: Has EPA considered a “natural” facility for waste treatment, such as a California facility detailed in a recent Boston Globe article? A: Wastewater treatment using “aquaoulture” has not been given any consideration as an alternative for Boston Harbor facilities for three reasons: 1. New England’s cold winters would prevent adequate growth of aquatic plants which remove chemicals (nutrients) in the wastewater. Such a system could not provide adequate treatment in the winter, unless facilities could be built enclosed, dramatically increasing their costs and affecting their viability. 2. Such systems in general require much more land than conventional mechanical secondary treatment facilities. The land requirement would make such a facility much more expensive and more difficult to site than those options now under study. 3. Such facilities typically are feasible in small—scale uses of less than 50 million gallons per day (MGD). The MDC system would require capacity to treat at least 50 MCD. Note also that all secondary treatment options under study employ biological (microbial) treatment of wastewater and are, therefore, as equally “natural” a system as the aquaculture facility referred to, except they are housed in associated mechanical facilities. A—i 3 ------- Q: If infiltration and inflow to the high level sewer were eliminated, would this lessen the load sufficiently to make satellite treatment plants feasible? A: Any reductions to infiltration and inflow (I/I), while necessary to improve overall sewage system operations, would not significantly reduce flows to the Harbor treatment plants. This is an issue that was specifically examined for the Southern MSD system and Nut Island treatment plant in the Nut Island Site Options Study and it was concluded that regardless of likely I/I removals upstream, 310 MGD of wastewater flows would still be delivered to a harbor treatment plant. The sizing of the facilities, therefore, reflects this realistic capacity flow. Since satellite advanced wastewater treatment plants were determined to be infeasible even if I/I were reduced, consultants then considered whether they could be used to reduce and treat the I/I and overflow problems upstream. It was determined that, for this planning period, satellites are still not warranted. A full report detailing these evaluations and conclusions regarding satellites, I/I, and associated water quality issues has been prepared by C.E. Maguire and will be released shortly. A further consideration of this question will be included in the SDEIS as a long—term planning issue to address wastewater management solutions. Q: Would the primary options presented entail construction of an entirely new facility or rehabilitation of the present facility? A: At Deer Island and Nut Island, existing treatment facilities are in need of replacement now and these improvements have been undertaken by the state with funding assistance from EPA. These so—called “fast—track” improvements do not upgrade the present facilities nor do they alleviate the capacity problems of the treatment plants. To be conservative in developing cost estimates for new facilities proposed, it has been assumed that implementation of any of the options involving Deer or Nut Islands would require the construction of entirely new facilities. Since the fast—track improvements are being implemented currently and new treatment plants would not be completed for at least 10 to 15 years, it is reasonable to expect that any new equipment installed now would have reached the end of its depreciation value by the time of subsequent financial coimmitment for new facilities. Q: How will data on social impacts be evaluated? A: The kinds of social impacts to be examined include the numbers, ages, and distribution of people throughout the communities affected by the construction and operation of a proposed treatment facility, the impacts on businesses, local institutions and public facilities that may be affected, local tax base and provision of public services such as police and fire protection, questions of family affordability of possible higher sewer costs, issues of local real estate values, and overall MDC system—wide distribution of the costs and benefits of new treatment facilities located in the Harbor. Another important aspect will examine the traffic and other construction—related impacts of each option. Once this data is compiled the basic question to be analyzed is the effects of each of the eight options on the communities adjacent to the three proposed A—i ’ 4 ------- sites, primarily Winthrop, Quincy and Boston, and upon the other user communities of the Metropolitan Sewerage District. For example, the traffic analysis will determine what the impacts of proposed auto and truck traffic associated with each option will be. This will identify bottlenecks, congestion, travel delays, safety issues, noise, and other disruption to normal local activities in the vicinity of the projects. Likewise, the established social/cultural patterns of the communities in terms of residential activities will also be evaluated to determine disruptions and other problems. Finally the identified impacts will be analyzed to establish whether any mitigation measures are available to lessen or eliminate their effects. One such mitigation technique might involve barging as a substitute for some truck delivery, or pooling of construction workers to cut back on the auto traffic in a community. Q: How can you mitigate a secondary facility at Deer Island when you’re discussing removing the drumlin and levelling he site? A: Clearly, the construction of secondary treatment facilities requiring over one hundred acres would be difficult to mitigate to a degree that no serious impacts result. Construction of these facilities would result in significant and unavoidable adverse impacts ranging from traffic and noise to preclusion of other uses at the sites where such facilities are proposed. Given that fact, however, there remain several viable opportunities to apply mitigation measures that reduce some of the serious impacts expected to result. In the case of siting at Deer Island or Long Island, possible mitigation measures could include analysis of methods to reduce truck and auto traffic, establishment of staging areas off—site, alternate layout of treatment facilities to take advantage of natural screening elements such as the drumlin (still a possibility even with secondary treatment), or alternate locations for the prison (at Deer Island) or hospital (at Long Island). In any case, mitigation would not be assumed to remedy all of the expected adverse impacts. Rather, this approach would seek to lessen and control, to more acceptable levels, the impacts that would result in order to achieve the ultimate goal and benefits of modern and adequate treatment facilities. Q: With regard to balance, not one of the proposed options benefits Winthrop, yet four have a positive benefit to Quincy. Where is the balance in this? A: The SDEIS screening process evaluated all the options in terms of the criteria established to limit the options for detailed study. These criteria included: availability of required acreage at each site, engineering feasibility, minimizing adverse environmental impacts, minimizing adverse community impacts, consolidation of treatment facilities, and opportunities for mitigation. It was determined from the outset that no one option could satisfy all the criteria established. Therefore, all the options initially recommended for further study entail some impacts. Initially, C.E. Maguire recommended to EPA that only the options that utilized Deer Island for at least a primary treatment site be carried forth for further study, because these options met many of the established criteria. However, due to the input of the Winthrop community at the public information meeting, options A—i 5 ------- involving less than primary treatment at Deer Island and consolidation of all treatment at Long Island were included for further study. The options involving a headworks at Deer Island would clearly provide benefits to Winthrop and will be examined to the same level of detail as the other six alternatives. Q: What is the population along the pathway to Long Island compared to the percentage of Winthrop residents who are affected by the Deer Island facility? A: There are approximately 19,000 residents in Winthrop and 811,000 residents in Quincy. The Hough’s Neck neighborhood has approximately 111100 residents, Squantum has about 3000 residents and the Point Shirley and Cottage Hill neighborhoods have about 3000 residents. These figures are only estimates at this stage of the analysis. The impact assessements which will be conducted during the next stage of the SDEIS process will review the 1980 U.S. Census data and refine these figures based upon field observation. These numbers alone do not reflect the potential impacts of proximity to proposed treatment plants. Additional information on numbers of elderly and children, traffic levels and routing through a community, existing roadway conditions and deficiencies, construction schedules and practices, and opportunities for mitigation are some of the specific details that will investigated during the detailed environmental impact analysis that will follow the screening results. A—i 6 ------- PART III — WRITTEN COMMENTS RECEIVED/EPA RESPONSES The comments below summarize letters received during the process of screening alternatives for wastewater facilities siting. The Final Screening Document addresses the concerns reflected in these comments. EPA has prepared responses only to specific points which need clarification or further explanation. COMMENTS FROM QUINCY OFFICIALS AND RESIDENTS City of Quincy, Mayor Francis X. McCauley : o Supports decision of MDC to limit 301(h) waiver to deep ocean outfall. o Supports single consolidated primary treatment facility w/deep ocean outfall. o Supports effective mitigation for unavoidable adverse construction and operation impacts (residential streets and communities shouldn’t be used as routine thoroughfares; visual shielding, odor control and noise abatement should be provided) o Supports retaining consideration of sub—regional treatment facilities. o Suggests rejection of modified no action option. o Concerned about new treatment facility on Long Island: fears that sludge management facility would be placed there; sees Long Island as unmatched recreational resource; has seen no situations in which recreational/waste disposal activities shown to be compatible; feels facility would downgrade Long Island’s recreational potential. • Response : There are several examples nationwide of the concept of mixed use wastewater treatment facilities/recreation. One specific example is the Taliman’s Island wastewater treatment plant in New York City which provides for a waterfront park adjacent to the treatment plant. o Those who share in benefits of sewage treatment must share the burden of costs and facilities. o 301(h) waiver process would benefit from continuing public information discussion and impact. o Cost of repairing bridge to Long Island must be assessed. o Moon Island causes periodic discharges of untreated waste into the waters off Squantum. State Representative Thomas Brownell : o Subregional facilities should have been adopted many years ago. Quincy and A—i 7 ------- Winthrop are the communities that. must be hosts because they already have facilities. o If harbor facilities are required, the following conditions must be met: 1) Moratorium on expansion of district; 2) Host communities must be exempted from assessments related to sewage treatment and paid compensation for the burden; 3) Separate Metropolitan Water and Sewer Authority must be established. o A long—term solution must include significant waste flow reductions (including I/I, CSO, general water resource wastefulness) o Progressive user fees (including meterin if necessary) should be used to place financial burden of treatment at the source. o Deep—ocean outfalls necessary. o Rejects options ib, tb.2, since they will require landfill at Nut Island and increase in level of activity (state law prohibits filling of Quincy Bay). o Cannot accept facility at Long Island (transferring and imposing impacts on another Quincy neighborhood). Shouldn’t forego future economic and aesthetic benefits in iiaintaining Long Island. o Plant consolidation is best alternative — Option la and I$a.2 provide greatest overall benefit/cost ratio (personally feels i is best since it calls for secondary treatment.) o Change in structure governing Metropolitan District Commission will improve future operations of treatment plant. Adequate mitigation measures will help in construction process. o Reject modified no—action proposal. State Representative Michael Morrissey : o Supports options la.2 and 4a.2 o Suggests payments in lieu of taxes/reduced assessments as mitigation measures. o Regarding Long Island, consider Mayor Flynn’s plans for revitalizing hospital and development of land, cost of reconstruction and repair to bridge, traffic impact on Squantum and North Quincy. o Little thought has gone Into repairing/upgrading Moon Island which Is a constant source of problems to Quincy residents.” “ Response• On the contrary, the Noon Island holding tanks and associated Calf Pasture pumping station which serve as overflow diversions and storage for the Deer Island treatment plant are actively being studied. The MDC will soon complete an hydraulic assesanent of the Moon Island facilities and their condition while EPA’s consultants are examining the feasibility of connecting these flows to a proposed primary treatment plant that will serve the southern MSD flows. If A— 18 ------- such a connection proves viable, this major CSO discharge point could be eliminated and the existing facilities on Noon Island dismantled. Squantum Community Association, Rona Goodman, Attorney : o Thinks problems with Long Island site seriously underestimated. o Disagrees with implication of CEM study (Dec. 10) that siting a wastewater treatment plant at Long Island will have virtually no residential impact. Thinks construction work will have adverse impact since only land access is through Squan um “ Response : It is true that there will probably be adverse impacts during construction involving traffic associated with a facility on Long Island. These impacts are acknowledged in previous studies and will be reexamined in greater detail during the upcoming phase of the EIS analysis. The reference to “no residential impacts” was intended to apply specifically to the absence of in residential uses at Long Island, unlike the current conditions at both Hough’s Neck in Quincy and Point Shirley in Winthrop where residences are as close as several hundred feet from the plants. This so—called “benefit” would apply more to the operational period than to construction when impacts would be more widespread. o If land access planned, Long Island bridge will have to be upgraded. If not planned, equipment barging expenses would be similar to those found to be infeasible at Lovel].s and Great Brewster Islands.” • Response : The quality of the Long Island bridge is an important consideration in judging the cost effectiveness and viability of any Long Island options. At a minimum, the roadway surface will require resurfacing; however, the structural steel supports and integrity of the bridge may prove sound and adequate to support construction equipment of the type required in such a project. At this time, any judgment on the bridge’s adequacy is speculative. A careful engineering assessment will be made to determine exactly the condition of the bridge and any limitations relative to the proposed truck traffic. The costs for any upgrading will be added to those options. Alternatively, barging will also be a more costly undertaking involving greater contingencies of construction and operations. However, it is incorrect to assume that barging activities at Long Island are similar to those required for an outer harbor site. First, Long Island would still have land access allowing a possible combination of land and water borne transport; secondly, much of the infeasibility of the outer harbor sites was associated with their greater construction problems resulting from the need to build a so—called “man—made” island rather than constructing on solid ground as is available at Long Island. Moreover, the barging uncertainties were due to the harsher weather conditions (waves and winds) experienced in the outer harbor area which is less protected and at a greater distance from staging terminal areas. While it is likely that barging activities would experience some effects from weather and adverse A—i 9 ------- conditions in winter months resulting in higher costs, these would not be expected to preclude such activities at a close—in site such as Long Island or Deer Island. o After construction, the effect of a wastewater treatment plant at Long Island will be similar to that at Deer Island. Sees no reason why another community should be spoiled by wastewater treatment plant. o Valuable recreation site lost (past experience indicates that MDC sewage treatment facilities never appropriate for recreational use). o Moon Island problem not solved or taken into account when considering cumulative effect of sewage discharge.” • Response : The water quality impacts of the Moon Island raw discharge to Quincy Bay and of other CSO discharges elsewhere in the Harbor will be described in this EIS in a general discussion of the existing pollutant sources to Boston Harbor. Control of CSO’s is the objective of separate state and federal projects and their existence does not alter the need to site treatment plants in the Harbor which will accommodate the current MSD flows. That is not to say, however, that the issue of Moon Island’s relationship to treatment facilities is not being considered. On the contrary, careful consideration is being given to this question. See response to comment of State Representative Michael Morrissey. o Deep ooean outfall is dependent on state policy and water quality conditions which are subject to change. o Supports options la.2 or 4a.2. Consolidated treatment at one site will be best for Boston Harbor as a whole. Will lead to centralized, consolidated and accountable management of system. o Favors long outfall approach (assuming such an outfall will be used in overflow situations). Secondary treatment alone is unsatisfactory because it leaves raw sewage in our backyards in an overflow situation. Save Our Shores, Inc. : o Concerned about amount of time devoted to exploration of primary treatment options when doubt exists concerning waiver application and decision. o Disagrees with theory that putting waste in ocean is best alternative. o Satellite options should be explored more effectively. All communities should share the problems of wastewater treatment along with the benefits.’ • 1 Response : The question of satellite advanced wastewater treatment options at several sites inland has been reevaluated during the screening process. See EPA response to this issue detailed in the summary of comments made at the public information meetings. A—20 ------- o Sees no benefits in destroying Long Island as Deer and Nut Islands have been destroyed. Cites impacts on Squantum and North Quincy (and possibly Montclair). o Opposed to any local outfall proposal. o Emphasis should be on quality of the system and its ability to minimize adverse impacts on the environment rather than on the cost. Andrea Sault, Quincy resident o Regrets that satellite options eliminated. o Wants to see information upon which C.E. Magurie based decisons to eliminate satellites made public.” • Response A report fully documenting the analysis and conclusions of EPA’s consultants is being released concurrently with the final screening document. See response above. o Recommends that an in—depth study of satellites take place soon, because planning for a new facility can take years. o Any primary option should have a deep ocean outfall. Funds and time limitations for its construction should be instituted. o Site chosen must have enough land area to allow for design error, technical upgrade and expansion. Filled land, as on Nut Island, is not suitable for primary holding tanks. In addition, filling has an adverse impact on the already hampered natural flushing action of the Bay. o Before Long Island can be considered as a site, there must be relative certainty that it is available for use as a treatment plant, or delays in constructing a facility will occur. Janet Burgei meister. Quincy resident o Erect a sewage treatment plant on land underneath the Northeast Expressway, Route 93. The plant should use laser beams to treat and purify sewage before it reaches Boston Harbor.” See response detailed in Part I of this document. o Each community should have its own plant to screen out and treat sewage before it reaches main plant in Boston. I o EPA’s proposed sites are not suitable. Two sites need a great deal of modernization and renovation to bring them to appropriate level. The third site, Long Island, would destroy a beautiful island in Quincy Bay. Proposed sites would pose environmental and other problems to Winthrop and Quincy. In addition, A—2 1 ------- filling of Quincy Bay would have a negative effect on fishing.” “ Response : It is clear that the siting of new wastewater treatment facilities is not an easy task. There are unavoidable problems and adverse impacts that accompany a construction project of the scale and magnitude required in this case. However, the MDC treatment system is in need of major renovation. The public health of Communities and the natural and recreational resources of the Harbor would be threatened if renovation of the system were not undertaken. The eight options to be examined in detail involving Deer Island, Long Island, and Nut Island have been developed after careful study and examination of more than eighteen alternatives. For some options this analysis has been conducted over the past eight years, while other proposed options have had only recent examination. In all cases, however, the solutions proposed represent the best possible choices given the multitude of constraints inherent in such an undertaking. Other sites around Boston Harbor offer less opportunities to accommodate major treatment facilities of 50 to 100 plus acres in size. In addition, the SDEIS will explore mitigation of many of the adverse impacts associated with siting. John Murphy, Quincy resident : o Outflow from the Nut Island wastewater treatment plant is a large source of pollution in Quincy Bay and is increased due to breakdowns, plant malfunctions, and deficiency of supervision. Corrective measures include routine servicing, preventive maintenance and construction of deep ocean outfall. o With regard to the Deer Island wastewater treatment plant, outflow must also be piped or tunnelled to deeper water.” “ Response : The so—called long outfall associated with any primary treatment options would involve a single outfall from either a Deer Island or Long Island facility with wastef]ows consolidated from any other treatment facilities at another site. For secondary treatment options, no such long outfalls are required since the effluent quality would meet established state water quality standards in the Harbor. o Long Island should not be considered as a site for wastewater treatment plant because the area has so much potential for recreation. o Steps should be taken to remove other sources of pollution to Boston Harbor, including periodic discharges from Calf Pasture pumping station 1 CSO’s, storm drain water run—offs and industrial outflows. o Tidegates should be eliminated from the sewerage system by rerouting sewerage into the system.” “ Response : A—22 ------- This comment appears to refer to the existence of tidegates at the plants used to control the inflow of seawater into the treatment facilities. Such gates are necessary to control flows during incoming tides both to prevent the increases to treatment flows and capacity at the plant by seawater and to minimize exposure of the plant’s pumps and other equipment to the corrosive effects of seawater. Current problems associated with these tidegates result from their breakdown and improper operation. These problems can be remedied in the design of new facilities. In addition, the Boston Water and Sewer Commission has undertaken a major rehabilitation program of tidegates in the Boston system that have caused untreated sewage discharge into the Harbor. o With regard to sludge, incineration should never be adopted as a means of disposing of the sludge. COMMENTS FROM WINTHROP OFFICIALS AND RESIDENTS Town of Winthrop, Beard of Selectmen, Robert Noonan : o Only option favored by Winthrop is full primary and secondary treatment at Long Island. o Long Island is only site which features fewest adverse impacts, acceptable operating conditions, affordable cost to public.” While the preference of the Winthrop Board of Selectmen has been clearly stated, it must be remembered that Long Island options are but one set of alternatives that were judged to merit further detailed study. Other options involve siting at Deer Island and Nut Island, as well as combination of these three sites. To conclude at this early stage that one option or site is the least impacting and most acceptable does not consider the facts which are as yet incompletely assembled. Only upon a careful review and comparison of the facts for all remaining options and sites, equally, can a fair judgment be made on a recommended option/site. This is the task of the EIS and will be achieved by the conclusion of the study. o Sufficient area would still remain for recreational and hospital uses.” “ Response : The question of available area and compatibility of mixed uses on Long Island is an important one with regard to any proposed treatment plant siting there. This will be analyzed in detail in the upcoming phase of the analysis, including the opportunities for mitigation of potential adverse impacts or incompatible uses. o (There are a range of] studies and lawsuits underway and all the separate agencies (involved] should be working together to solve problem. o Option 2b, or amended 2b.3 (to include headworks at Deer Island) would fulfill purpose of EPA — fewest adverse impacts, acceptable operating conditions, and affordable cost. A—23 ------- Board of Selectmen, Mr. Vecchia : o Eastern edge of Deer Island is an area of natural beauty (Original Boston Harbor Islands Comprehensive Plan issued by MAPC called for relocating prison and using south end of Deer Island as a large informal park). o Long Island is good site for expansion of wastewater treatment. City of Boston promulgated building boom (high—rise apartments, condos, office buildings, hotels) and must share responsibility and burden of cleaning up harbor and maintenance. Board of Selectmen, Mr. DeLeo : o Federal and State govenments are responsible for closing Shirley Gut and constructing a roadway to Deer Island, which in turn, led, to the location of the wastewater treatment plant. o Winthrop has suffered adverse impacts from Logan International Airport, Deer Island House of Correction and MDC wastewater treatment plant. o City of Boston, Commonwealth of Massachusetts and federal government have each contributed to the problems on Deer Island and should show consideration for the residents of Winthrop by finding a permanent long range solution to the wastewater treatment problem. Winthrop Board of Health : o None of the six options is acceptable to Winthrop. o Board of Health concerned with sewage in waters and has had to bear the expense of water tests twice a month. o All adverse effects of poor maintenance, poor operational policies, lack of proper personnel, misplacement of plant are borne by Town of Winthrop. o Demands placement of primary/secondary treatment facilities at Long Island. Winthrop Conservation Commission : o None of six options benefit Winthrop. o Once a site chosen, there can be minimal reduction of impacts. o Asserts that 5b.2 and 2b.1 were dropped because of higher cost. Supports these two options. State Representative Alfred Saggese: o Opposed to secondary treatment at Deer Island. o Opposed to any expansion of Deer Island facility. o Granting of waiver is most desirable option — Urges EPA support. A—2 ------- o Unique location forced Winthrop to bear regional problems (prison, Logan Airport) o Supports options 1 b.2, 5a.2, consisting of separate primary facilities with Deer Island doing no more than it does now. o Favors prohibition of expansion of MSD. OTHER WRITTEN COMMENTS Boston Harbor CAC o Pleased that options reduced. May not agree with options selected for further study, but sees why EPA still evaluating them. o Disappointed that MDC preferred option (Upgraded primary at Deer Island & Nut Island w/local outfall) was dropped. Either data compiled during site options study are erroneous (that local outfall could meet with water quality standards) or other factors have changed of which the BHCAC is not aware. o Under a waiver application, it could be proved or disproved whether water quality standards could be met with no waiver. If not, option for long outfalls could then be built. o If effluent from upgraded primary plants will not meet water qualtiy standards at local level, will it meet standards by extension of outfall? o If water quality standards can be met with local outfall, a deep ocean outfall is a waste of money and an unnecessary disruption. Easier to monitor water discharge in close than waters beyond Harbor. Does not want harbor clean up at expense of outer harbor. o Believe upgraded primary at Deer and Nut Islands with local outfalls is a first step and can be started inmediately. o Long outfall or secondary treatment can be added if necessary, but CSO problem could be addressed with funds needed for deep ocean outfall tunnels and pipes. o Sludge and CSO’s responsible for more pollution than treatment plants. o Total cost of Harbor cleanup must be factored into wastewater treatment plant siting. *IResponse : EPA has based its exclusion of local outfall options on the Executive Office of Environmental Affairs’ clear indication to EPA that the MDC 301(h) revised application will evaluate a deep ocean outfall site. The conclusions reached in the Nut Island Site Options Study alone do not constitute a sufficient basis for pursuing local outfalls. The 301(h) waiver process is an extensive biological and water quality evaluation of the impacts of primary effluent at a proposed site. Since the first round waiver application was tentatively denied for the deep ocean site, EOEA has determined that the most prudent course of action would be for MDC to reapply for a deep ocean site. EPA would like to emphasize that the siting issue is not affected by the length of the outfall A—25 ------- and that if the 301(h) waiver process comes to a different conclusion, EPA’s siting evaluations will not be .ompromised. o Opposed to No Action concept. o Oppose use of Long Island for treatment facility. o Do not want consolidation of treatment at one plant: (a) disaster if system breaks is too great (b) concentration of effluent may cause water quality problems; Cc) how would Southern System overflows be handled? (have provisions for overflows been considered in this option?)” A consolidation of all treatment (either primary or secondary) at one plant and site can be viewed as a positive benefit due to the associated advantages from centralized construction and operation activities, staffing, and sludge disposal measures. There are, likewise, potential disadvantages from this option in terms of land area needed and greater expansion of treatment works. These opposing factors will be evaluated in detail in the EIS to determine an acceptable solution. The SDEIS does not plan to evaluate consolidated options solely on the potential problems of system breakdowns. If there are breakdowns in a consolidated treatment plant, as might reasonably be expected for some limited period of time, these problems would not shut down an entire treatment process or result in total plant bypass of raw sewage. Modern treatment facilities on—line today do not operate in that fashion. A more reasonable “worst case” expectation would be breakdowns of some equipment, such as pumps or valves etc., with resultant lessening of the treatment processes for only a limited period of time. Such reduced treatment capacity, moreover, would only last as long as it would take to repair or replace the broken equipment. Given the back—up pumps and other redundancy required to be built into a modern plant design, such repairs would be expected to occur immediately. There may be water quality problems of a short duration, but not of the extent which would warrant dropping consolidated options from further study. With regard to effluent concentration, proper location of effluent discharge pipes, diffuser design, and the controlling state and federal water quality discharge standards and permit requirements will insure that any effluent, including that from a combined facility, will not violate water quality standards. On the issue of overflows, the SDEIS will finalize the siting of a South System treatment plant that will be designed to handle the peak flows carried by the High Level Sewer, thus significantly reducing overflows at the plant. Upstream overflows will not be addressed directly in the SDEIS. Some relief of these overflows will be realized when the Frainingham and We].lesley Extension projects are completed. The issue of excess flow in the Southern System is also being addressed in the current I/I planning being undertaken by DEQE. Finally, the SDEIS will consider the feasibility of connecting the Moon Island A—26 ------- CSO facility (currently associated with overflows at Deer Island) to a proposed primary treatment plant which handles southern MSD system flows. This option, it is expected, will contribute to significant water quality improvements to the Harbor. o Supports waiver of requirement for secondary treatment. o Supports requirement that large upstream projects provide own treatment and cease reliance on MDC. Innovative wastewater treatment on site should be actively sought; community or regional sewage treatment plants in outer reaches of present MDC should be part of long range planning. 55 ‘ 5 Response : This comment is an important statement of planning and policy considerations which, although not directly related to the siting questions in the SDEIS, merit further consideration and analysis. The question of satellite advanced wastewater treatment facilities was evaluated and judged not viable at this time. However, this option along with other possible solutions to wastewater management as noted in the cosinent will be considered in the £13 as a long—term planning element. City of Boston Department of Health and Hospitals o Recommends elimination of all primary or secondary treatment alternatives proposing use of Long Island because this is inconsistent with both the Island’s present use as a chronic disease hospital and with the possible development of non—hospital related activities. o Option 4b.2 should be rejected in favor of a.2. o Option lb.1 should be dropped from further consideration. There would be no significant additional burden on Winthrop due to elimination of Nut Island primary in favor of headworks but significant benefits would be gained by Quincy. o Boston has little to lose and may benefit from siting of a well designed, maintained and operated primary or secondary treatment facility on Deer Island, but would sustain a substantial and irretrievable loss of opportunity if a facility were constructed on Long Island.” The preference of the Department for consolidated treatment (either primary or secondary) on Deer Island is noted. However, it must be pointed out, that a conclusion that such a solution would not impact residents of Winthrop appears premature at this time. There appear to be serious impacts to Winthrop from the construction and operations of a secondary plant at Deer Island; while a primary plant siting also appears to generate some adverse impacts. What is not as yet established is the extent of such impacts, their severity and duration, and the comparison of adverse impacts to potential benefits among all of the remaining options. o All reasonable mitigating measures should be taken to safeguard health, comfort and convenience of residents of Quincy, Winthrop and Boston. A—27 ------- o Favors barging and busing of construction workers and supplies to Deer Island and opening of Shirley Gut, with passenger vehicle access to the prison maintained by a drawbridge manned by prison personnel. o Favors deep water outfall. Charles River Watershed Association o Supports the proper operation and upgrading of the MSD’s treatment plant and system. o Believes flows to the plants should be reduced, especially in the Southern System. o Supports satellite treatment plant as means of reducing flows, and disagrees with screening decision to remove them from consideration. o Advocates a plant in a commercial area, away from river bank, with aerated discharge to the river. o Concerned with MSD overflows to the Charles River as a recurring source of wet weather pollution. o Loss of groundwater from Quabbin and Charles watersheds to Boston Harbor is unnecessary, especially since it is needed to replenish stream flow and groundwater. o Three treatment plants now discharge into the Charles River. A quality effluent from a satellite plant would not degrade the river and could augment stream flow. o Proposes a treatment plant in the Framingham—Ashland area where much of the growth affecting the Southern System is taking place. **Response : See response to this issue detailed in Part I of this document. A—28 ------- PART IV — COMPILATION OF PUBLIC MEETING PARTICIPATION SHEETS WINTHROP PARTICIPATION SHEETS 1. Views on the suitability of the site shown for the location of primary and secondary wastewater treatment facilities. Deer Island Nut Island Long Island Most Least Most Least Most Least Primary 0 13 0 19 0 Secondary 0 i1 1 5 18 0 Reasons for choices (sample of responses): o Winthrop destroyed by present treatment plant; can’t swim at beaches. o People will be least affected with plant at Long Island. o Nut Island doesn’t have acreage; use of Deer Island would severely impact quality of life in Winthrop (air, noise; overcrowding); streets of Winthrop cannot handle daily traffic of trucking workers and supplies for 8 — 10 years; Long Island is located further away from communities of Winthrop and Quincy. o Recommended options would present a severe adverse impact on an already congested town; construction required would cause severe damage to roads, homes, environment. Cost of 2b1 outweighed by improved quality of life for citizens of Winthrop and Quincy. o Long Island not nearly as populated and therefore it will not have adverse effects on residents; Long Island is more centralized and near the heaviest sewerage spiller (Boston). o Boston should accept impact of its building boom and provide for most effective treatment of increased sewerage at a plant cited within City (Long Island). o Long Island would be centralized facility most isolated from a population; if waterborne traffic used, there would be no impact on any community including Quincy. o Long Island is only logical technical site for sewerage treatment facilities for Boston; Winthrop has done more than its share for Boston, including donating land to Massport for Logan Airport. 2. Additions/Eliminations to consultants’ recommendations o Open up Shirley Gut so water can clean up beaches o Add 2b1, 5b2; eliminate la, lb , 4a2, 1 b2, 5a2 (many responses). o Delete all 6 options as they have no relevance from an engineering standpoint. 3. Preferences among options o 2b1 (10 responses) o This option will save the town. o Any other option will decimate community. o If people of Winthrop trusted MDC we might accept improved primary treatment A—29 ------- at Deer Island for existing flow with no secondary treatment. However we do not trust MDC. o 5b2 (3 responses) o 2b3 (U responses) o Would not increase present capacity of Deer Island. o Would prefer no further expansion at Deer Island, but this seems most intelligent evil if 2b1 eliminated. o Provides least impact to the communities, maximum treatment and room for further expansion. o Least offensive (but not preferred). o 5a2 (2 responses) o Only acceptable option — no increased impact on Winthrop; facilitates future expansion on Long Island when required. o Least offensive (but not preferred). U. Mitigation measures which could be taken (sample of responses) o Practice of allowing large trucks along Winthrop Shore Drive (to Beacon, Shirley Streets) should be stopped. o Barge construction equipment. o Payment in lieu of taxes; barging of construction workers and materials; no land traffic. o Never remove the drumlin at Deer Island. o Construct primary/secondary facilities at Long Island. o Proper and efficient plant operation; odor and chlorine emission control through proper technology, use and operation. o Not possible to mitigate. Traffic is already congested; impact of thousands of construction workers by barge or otherwise would be devastating. o You can’t buy the community; no mitigating circumstance, no compromise possible. QUINCY PARTICIPATION SHEETS 1. Views on the suitability of the site shown for the location of primary and secondary wastewater treatment facilities. Deer Island Nut Island Long Island Most Least Most Least Most Least Primary 6 0 0 8 3 2 Secondary 5 0 0 7 3 3 Reasons for choices (sample of responses): Long (Most) o Closest to deep ocean/separated from neighborhoods. o Poor health effects diminish with distance from population areas. A—30 ------- Deer (Most) o Outer/larger; no need of landfill; less neighborhood problems o Has no alternative uses due to prison. Nut (Least) o Not enough land; close to neighborhood; congestion of access road; impact of construction noise on community. o Access road too narrow; site limitations severe; filling in Quincy Bay would be disastrous to all fishing. 2. Additions/Eliminations to consultants’ recommendations o Site plant using land under Route 93. o Add satellite plants so waste is treated before arriving. o Eliminate 4b2 — too close to poulation; eyesore to Quincy Bay area. o Eliminate lb and 4b2 — not enough land available at Nut Island; plant has adverse neighborhood impacts; headworks would add to recreational use of Nut Island. o Eliminate lb — due to filling of 18 acres at Nut Island o Use “no action” for comparison purposes only. o Safeguards to ensure construction of deep ocean outfall. 3. Preferences among options o Modernize Nut and Deer Island sites (no expansion or landfill). o Site facility at Long Island (closest to deep ocean and separated from neighborhoods). o 2b3 — Most advantageous to environment (improves Hough’s Neck and relocation of outfall improves Winthrop). o la, 4a2 (4 responses) o causes less problems and costs less. o puts effluent nearer mouth of Harbor. o Deer Island has prison, so other uses limited. 4. Mitigation measures which could be taken (sample of responses) o Barging of contruction materials. o Construction of athletic facilities. o Work with community to schedule construction. o Design facilities to be more in keeping with surrounding communities (e.g. like forifications) o I/I reduction incentives. o Busing of workers. o Noise abatement. o Development of viable evacuation plan in the event of a chlorine or gas accident. o Moratorium on system expansion A—3 1 ------- |