BOSTON HARBOR SUPPLEMENTAL DRAFT ENVIRONMENTAL IMPACT STATEMENT EVALUATION OF SATELLITE ADVANCED WASTE WATER TREATMENT FACILITIES APPENDIX B U.S. ENVIRONMENTAL PROTECTION AGENCY REGION I ENVIRONMENTAL EVALUATION SECTION JOHN F. KENNEDY FEDERAL BUILDING BOSTON, MASSACHUSETTS 02203 May 16, 1984 Prepared by: CE MAGUIRE, INC. ONE DAVOL SQUARE PROVIDENCE, Rl 02903 **. \m) THE MAGUIRE GROUP ------- BOSTON HARBOR SUPPLEMENTAL DRAFT ENVIRON IENTAL IMPACT STATEMENT Evaluation of Satellite Advanced Wastewater Treatment Facilities APPENDIX B U.S. Environmental Protection Agency Region I Environmental Evaluation Section John F. Kennedy Federal Building Boston, Massachusetts 02203 May 16, 1984 Prepared by: CE Maguire, Inc. One Davol Square Providence, Rhode Island 02903 ------- APPENDIX B FEASIBILITY OF SATELLITE TREATMENT FACILITIES TABLE OF CONTENTS SECTION TITLE PAGE NO . I. CONCLUSIONS AND SUMMARY B-i B1.1. Recommended Satellite Facilities B-i Bl.2. Satellite Facilities with Wetlands Discharge B-3 II. HISTORICAL BACKGROUND B-S B2.1. EMMA Concepts B-S B2.2. EMMA Recommended Satellite Facilities B—9 B2.3. 1978 Draft EIS Conclusions B-i2 III. DESCRIPTION OF SDEIS SATELLITE OPTIONS B-24 B3.l. EMMA Study Satellite Facilities Update B-24 B3.2. Quincy Shores Association Wetlands Disposal Option B-26 B3.2.i The Weymouth Fore River Basin B-28 B3.2.2 The Neponset River Basin B-30 B3.2.3 The Charles River Basin B-31 B3.3. Relationship of SDEIS Satellite Options with On-Going Facilities Plan in the Southern NSD B-38 IV. EVALUATION OF SATELLITE OPTIONS B-41 B4.i. EMMA Satellite Evaluation B-41 B4.1.i Flow Augmentation B-41 B4.i.2 Water Quality B-42 B4.1.3 Water Supply B-Si B4.2. Wetlands Disposal Option B-54 1. ------- ATTACHMENT A WATER QUALITY MODELING CORRESPONDENCE B-Si ATTACHMENT B WETLANDS DISPOSAL BIBLIOGRAPHY B-123 ATTACHMENT C WETLANDS DISPOSAL-DEQE CORRESPONDENCE B-126 ATTACHMENT D I/I PRELIMINARY REPORT TO PROF. CHARLES N. IIAAR B-140 11 ------- List of Tables Page Bi. Satellite Facilities General Description B-6-7 B2. Treatment Alternatives B-8 B3. Summary of Other Treatment Options B- 13 B4. Comparison of AWT Effluent and Charles River Quality B-15 B5. Revised Flow Estimates - Satellite Plants B-25 B6. Co t Update - ENMA Satellite Facilities B—27 B7. Wetland Acreage Requirements - Satellite Facilities B—34 B8. Cost Summary: Wetlands Disposal Satellite Facilities B—36 B9. Charles River Water Quality Survey Data Summary: 1973/1978 B—46—48 BlO. Neponset River Water Quality Survey Data Summary: 1973/1978 B—52—53 Bil. Preliminary Estimate of Wetland Availability for Wetlands Disposal Treatment Facilities B—55 List of Figures Bi. EMMA Recommended Plan B-b B2. Satellite Facilities with Wetlands Discharge B-29 B3. Conceptual Design of AWT - Wetlands Discharge Facility B—37 B4. Charles River Average Dissolved Oxygen DWPC Surveys: 1973, 1978, 1980 and 1981 B—49 111 ------- I. CONCLUSIONS AND SUMMARY Based on the enclosed detailed evaluations, the following conclusions can be stated regarding previous and new proposals to locate satellite facilities in the South MSD: Bi.i. Recommended Satellite Facilities on the Charles and Neponset Rivers a. Based on structural and hydrological analysis of the High Level Sewer (HIS) and revisions to wastewater flow projections as reported in the MDC Nut Island Site Options Study (MDC, June 1982, #4), the HIS was found to be of adequate capacity and condition to accommo- date flows up to 310 MCD without any relief requirement. Based on available I/I data, the HIS could see occasional peak flows higher than 310 MCD, which have been estimated to reach up to 420 HGD. The development of the two proposed satellite AWT facilities to remove approximately 59 MGD from the south MSD system would not, in and of themselves, reduce these HiS flows sufficiently to a level whereby harbor treatment facilities could be reduced in size. b. Following the completion of necessary upstream interceptor relief projects, removal of limiting hydraulic factors in terms of pumping capacity at Nut Island, implementation of a flow monitoring program in the southern MSD, and a more realistic assessment of I/I reduc- tion alternatives, the development of satellite treatment facilities in the south system versus other flow reduction/management options should be reevaluated as a priority in determining a cost effective and equitable solution to future system expansion needs. c. Based on current updated facility plans of the MDC and their imple- mentation time frame, it is our view that major interceptor relief projects currently proposed downstream of the sites investigated for AWT facilities would still be required to alleviate overflows and other surcharging conditions created by constrictions and other B-i ------- structural or hydraulic problems presented in the system, irrespec- tive of a decision regarding satellite facilities. d. The discharge of the AWT facility effluent to the Neponset River will have an adverse impact on water quality, particularly upon the dissolved oxygen resources of the river. Additionally, during periods of low stream flow, potential public health/water supply impacts pose significant problems to public water supplies, based on stream f1ow—ground ater relationships under low flow conditions and groundwater pumping close to the river. Potential public health/ water supply impacts outweigh any potential benefit in terms of low-flow augmentation of the Neponset River. A satellite facility on the Neponset River is not recommended for further consideration. e. The discharge of an AWT facility effluent to the Charles River may have a beneficial impact on the dissolved oxygen resources of the river, even though water quality standards might be violated during certain periods. Increased phosphorus loads may exacerbate nuisance algae conditions in downstream reaches of the river. During periods of low stream flow, potential public health/water supply impacts may pose significant problems to public water supplies based on stream flow-groundwater relationships under low flow conditions and ground- water pumping close to the river. Potential public health/water supply impacts may outweigh any potential benefits in terms of low-flow augmentation of either the Charles River or, via the Mother Brook diversion, the Neponset River. In accordance with Conclusion b. above, at such time as satellite facilities are determined to be a possible option to limit flows to the Harbor treatment system to the design limit of the HLS and treatment system, a satellite facility on the Charles River should be reconsidered, incorporating consideration of possible in-stream and other impact mitigation measures as may be determined necessary. B-2 ------- B1.2. Satellite Facilities with Wetlands Discharge Satellite AWT treatment facilities proposed by Quincy Shores Associates, to be located on the Charles, Neponset, and Weyinouth Fore Rivers with discharge to adjacent wetlands, are not recommended for further consid- eration as part of the current facility siting analysis for the following reasons: a. Development of these AWT facilities, which would treat approximately 97 MGD of wastewater, would not provide sufficient flow relief, or otherwise reduce the volume of flows in the MSD southern system in order to reduce the size of a harbor-sited treatment facility. This is largely due to the existing adequate capacity of the High Level Sewer to handle all flows reaching it, and sufficient excess volume wastewater flows to deliver a projected 310 11GB to a southern MSD harbor treatment plant. b. All currently planned MDC interceptor relief projects are downstream of the proposed sites for these three AWT facilities and would, therefore, still be required, offering no offsetting capital outlay savings. c. The potential water supply/public health dangers associated with the impacts of discharge to a wetlands/watershed area are significant. The state has reviewed this proposal and has found sufficient elements of uncertainty and/or detrimental effect that they do not support this proposal’s feasibility. In particular, the issues raised about potential dangers from such a siting location include the expected pass-through of untreated organics and other poten- tially harmful materials, the more stringent groundwater/surface water standards that would be applied to such a facility’s effluent essentially resulting in drinking water standards, and other related concerns outweigh any potential low-flow augmentation benefits. B-3 ------- d. The limited availability of wetlands in close proximity to the proposed systems of sufficient size to accept effluent volumes of 10, 35, and 52 !IGD as proposed, as well as limitations of the hydraulic and renovation capacities of the existing wetlands, suggests that facilities of such magnitude would be difficult to site. Required hydrologic and wetland ecology evaluations are also expected to require a substantially longer implementation time frame. e. The major capital costs of developing three AWT facilities, esti- mated to be considerably in excess of $238 million, coupled with major O&M costs annually, do not appear to be justified by the lack of potential benefits of such facilities relative to the need to site harbor treatment facilities. B-4 ------- II. HISTORICAL BACKGROUND B2.1. EMMA Concepts Five broad-scale wastewater management concepts were developed for evaluation in the Eastern Massachusetts Metropolitan Area Wastewater Management EHMA Study (MDC, Oct. 1975, #3). Although the concepts themselves were not necessarily formulated with the intention of any one being selected for implementation in its entirety, it was intended that the evaluation of these broad-scale concepts would establish the design criteria, system limits, and other conditions and considerations required of an implementable, recommended plan. Brief general descriptions and important features relative to satellite facilities of the five original concepts are shown on Table Bi. An extensive rating system was employed to evaluate and rank the concepts by the Technical Subcommittee. This evaluation led to the elimination of concepts 3 and 5 from further consideration. As stated in the EMMA Study Main Report (pg. 4—27): “Upon evaluation of all the factors affecting the plan selection process, and because of the closeness of the rankings for Concepts 1, 2 and 4, it was decided by the Technical Subcommittee that a moderately decentralized system would be the best overall solution considering river flows, increasing demand and decreasing oppor- tunities for water—oriented activities, and the difficulties associ- ated with extensive interceptor construction through urban areas and the filling of Boston Harbor.” Four satellite treatment alternatives were developed for further evalua- tion. The satellite systems and communities to be served under each alternative are summarized in Table B2. The wastewater flows from remaining communities tributary to the Nut Island Treatment Plant would continue to flow to Nut Island for treatment and discharge to Boston Harbor. The following excerpt from EMMA Study Main Report summarizes the evaluation of the four alternatives: B-5 ------- TABLE Bi SATELLITE FACILITIES GENERAL DESCRIPTION Satellite Facilities Design Communities Served Concept Description ( River Basin) ( Plant Location) Flow By Satellite Plants Upgrade existing facili- None ties, minor system expan- sion (addition of 7 com- munities), no satellite plants 2 Limited decentralization, Sudbury R. Framingham 19.0 MGD Ashland, Framingham, creation of five regional Hopkinton, Southborough satellite systems Charles R. Dedham 29.0 PIGD Brookline (25%), Dedham, Dover, Natick, Needham, Newton (8%), Sherborn, Wellesley, Boston (West Roxbury) Charles R. Watertown 45.0 1 1GD Lincoln, Newton (92%), Waltham, Watertown, Weston Neponset R. Canton 25.0 MGD Canton (70%), Norwood (90%), Sharon, Stoughton, Walpole Neponset R. Canton 5.5 ! 1GD Canton (30%), Dedham (10%), Norwood (10%), Westwood 3 Maximum expansion of MSD None treatment of all flows at expanded harbor facili- ties B-6 ------- 4 Maximum decentralization of MSD, creation of six regional satellite sys- tem Sudbury R. Charles R. Framingham Dedham 19.0 MGD Same as Concept 2 22.0 MGD Dedham (40%), Dover, Natick, Needham, Sherborn, Wellesley Charles R. Watertown 45.0 MGD Same as Concept 2 5 Land application of five of the six satellite facilities as proposed in Concept 4 - otherwise identical to Concept 4 30 MGD Canton, Norwood, Sharon, Stoughton, Walpole, Westwood 31.0 MGD Burlington, Reading, Stoneham (85%), Wakefield (10%), Wilmington, Winchester (45%), Woburn 30.0 MGD Arlington, Bedford, Belmont (90%), Lexington, Medford (20%), Winchester (55%) Neponset R. Canton Mystic R. Woburn Mystic R. Medford Same as Concept 4 (Sudbury River - Framingham Facility would not employ land appli- cation) B-i ------- TABLE B2 TREATMENT ALTERNATIVES Satellite Facilities Design Alternative River Basin Plant Location Flow Communities Served by Satellite Plants A Charles R. Middle Charles 31 MGD Ashland, Dover (60%), Framingham, Area Hopkinton, Natick, Sherborn, South- borough, Wellesley (80%) Neponset R. Lower Neponset 31 MGD Canton, Norwood, Sharon, Stoughton, Area Walpole, Westwood B Charles R. Lower Middle 57 IIGD Ashland, Brookline (15%), Dedham (40%), Charles Area Dover, Framingham, Hopkinton, Natick, Needham, Newton (54%), Sherborn, South- borough, Wellesley Neponset R. Lower Neponset 31 IIGD (Same as Alternative A) Area C Charles R. Middle Charles 31 MGD (Same as Alternative A) Area Charles R. Lower Middle 27 MGD Brookline (15%), Dedham (40%), Dover (60%), Needham, Newton (54%), Wellesley (20%) Neponset R. Lower Neponset 31 MGD (Same as Alternative A) Area 0 Sudbury R. Upper Sudbury 19 MGD Ashland, Framingham, Hopkinton, South- Area borough Charles R. Lower Middle 39 IIGD Brookline (15%), Dedham (40%), Dover, Charles Area Natick, Needham, Newton (54%), Sherborn, Wellesley Neponset R. Lower Neponset 31 MGD (Same as Alternative A) Area B-8 ------- “Upon further analysis of the Neponet River, the Massachusetts Division of Water Pollution Control recommended that if a satellite treatment plant is located for discharge to the Neponset River, the plant should be located as far upstream as possible to provide maximum benefits to the river, particularly during the dry summer months. “A plant in the middle Charles area was considered vital to provide effluent for low-flow augmentation. As mentioned earlier, investi- gations (by the Corps of Engineers and the United States Geological Survey) for other means of flow augmentation in the Charles River were found not feasible and the need for conserving river flows was shown to be critical (by the United States Geological Survey). In terms of location, the lower middle Charles plant would be undesir- able due to the flat, slow flowing river in that location. However, an upper middle Charles plant discharging at the Cochrane Dam near Charles River Village would be in a location where the discharge would benefit from the over one mile long rapids section. “In addition to these considerations, the plants will also serve to reduce flows to the Nut Island Treatment Plant and will reduce the need for relief lines along the Wellesley Extension Sewer, the New Neponset Valley Sewer, and the High Level Sewer. “Providing a 2 mgd wastewater treatment plant in the Aberjona River area would cost on the order of $9.7 million to construct and about $0.7 million per year to operate. These costs represent the com- plete treatment process shown [ in Figure 3-4]. On the basis of operating costs alone, this would be in excess of three times the cost of using MDC water for augmentation (which would be an un- acceptable alternative). In addition to this, other alternatives of flow augmentation should be considered such as groundwater pumping during low flows and recharge during high flows. “A wastewater treatment plant discharging to the Sudbury River in the Frainiugham area was considered as not providing a significant improvement in flows due to the large storage potential in the flat swampy areas downstream.” Based on the evaluation of these alternatives, a modified Alternative A was selected as the Recommended Plan. B2.2. EMMA Recommended Plan - Satellite Facilities The Recommended Plan included satellite treatment facilities discharging to the Middle Charles and Upper Neponset Rivers. Figure Bi portrays the system under this plan. The Middle Charles Treatment Plant would serve Ashland, Framingham, Hopkinton, Natick, Sherborn, Southborough and 8-9 ------- •‘ ‘ NUø OLI LI GINO I EXISTING FACILITIES NOT REQUIRING RUIEF OR UPGRADING AS PART OF THE RECOMMENDED PLAN A. EXISTING MSD SEWERS O EXISTING CITY OF SOSTON FACILITIES II MAJOR PROiECTS IN RECOMMENDED PLAN’• A EXISTING MSO SEWERS ___________ REQUIRIN3 RELIEF S. PROPOSEC EXTENSION SEWERS ___________ O TREATMENT PLANTS NEW) (INCLUOES CNGOING PROJECTS) III SERVICE ARIAS UNDER THE RECOMMENDED PLAN. A. DEER ISLAND PLANT S. NUT ISLAND PLANT C. MIDDLE C4A ILES PLANT 0. UPPER NIPONSET PLANT * 1 [ i FIG.Øt TREATMINT PLANT SFRV ICE ARE\S AM) M%JOR PROJECTS I S TIlL RECO 1 1FNIWD PLAN rt SSu v AIab*’ COWCOM pI* ODy MA SO NO UGH sUoSu N ’—- AOL LIS? 0$ M N.LJ1 1 ‘-S ) MON SOC ML AM 0 A 5 MCION our e EMMA &tudv, u sma y epM Mav i 1sii ,. eMULSION ------- portions of Dover and Wellesley and would have a design flow capacity of 31 MGD. The Upper Neponset Treatment Plant would serve Canton, Norwood, Walpole, Sharon and Stoughton and would have a design flow capacity of 25 IIGD. The anticipated benefits associated with these proposed facilities were summarized as follows: Neponset River -- This facility would reduce the service area of the Nut Island Treatment Plant and keep reclaimed wastewater as far upstream in the Neponset River Basin as possible. The highly treated effluent should help the Neponset River by increasing flows in dry summer months. Restoration of clean water will also depend on the abatement of nonpoint and other sources of pollution. Charles River -— This facility would treat 31 mgd in the year 2000, reduce flows to the Nut Island plant, and help retain reclaimed waste- water in its immediate basin. Adding these flows to the Charles River will be helpful to water quality in dry seasons. However, there can be no assurances of achieving intended water quality in the Charles River unless nonpoint and other sources of pollution are eliminated. The treatment facilities which are in various stages of implementation in the Medfield, Medway, and Milford areas should also benefit the river. It is worthwhile to note that, in recommending the implementation of both treatment facilities, it was recognized by the Technical Subcommittee and by those who participated in the public review process that water quality in both the Charles and Neponset Rivers might not be improved. There appears to have been, however, an implicit assumption that water quality problems would not worsen as a result of the discharges from these treatment facilities. The Middle Charles and Upper Neponset facilities were scheduled as sequence numbers 10 and ii respectively in the Construction Staging Program for MDC Wastewater Management Projects under the EMMA Study. The total cost of both facilities was $90,700,000 based on January 1975 (ENR 2200) costs. B-li ------- The Construction Staging Program also listed interceptor relief in lieu of sequence numbers 10 and 11 as sequence numbers 1OA and hA if the satellite plants are not implemented. The total cost of additional interceptor relief for the Wellesley Extension, New Neponset Valley and High Level Sewers was listed as $64,700,000 (January 1975, ENR 2200). Finally, four optional treatment scenarios were presented in the EMMA Main Report which were intended to provide an economic perspective of the impacts of major changes from the Recommended Plan such as timing of implementation of major facilities (i.e. satellite plants); and policy changes such as primary treatment with deep ocean discharge versus secondary treatment. These “Other Treatment Options” and their assciated capital and O&N costs are summarized in Table B3. B2.3. 1978 Draft EIS Conclusions and Recommendations The Draft EIS concluded that neither the Charles nor Neponset River satellite plants should be constructed. This conclusion was based on negative water quality impacts projected to occur or to be maintained at the 7Q10 design flow condition. Based on the application of a basic Streeter-Phelps dissolved oxygen analysis in the Neponset River, the Draft EIS concluded that: “Any discharge to Neponset in the area proposed by the EMMA report would result in a significant detrimental impact on the Neponset River’s dissolved oxygen resources and overall water quality. In addition, all the discharge points analyzed are upstream of a major group of water supply wells (See Figure 2.5-18). It is very likely that these wells draw from the Neponset during low flows, given their proximity to the River and the nature of the aquifer. The potential for significant adverse health effects is created by utilizing any of these discharge point. In order to mitigate these impacts it would be necessary to move the discharge point downstream of point C. Such action reduces potential flow augmentation bene- fits considerably. B- 12 ------- TABLE B3 SUMMARY OF OTHER TREATMENT OPTIONS: MDC - EMMA S1)Y 1113 Operation & Capital Cost, 1 ) Maintenance Cofl)( 2 ) Option Description millions of $‘ millions of $/yr Recommended plan 855.3 25.6 Total ocean discharge No satellite treatment plants. 737.9 16.9 All flows discharged in deep waters after receiving primary treatment at the Harbor plants. Ocean discharge in Satellite treatment plants con— 755.7 22.3 lieu of secondary structed. Primary treatment at treatment the Harbor plants with deep ocean discharge. Deletion of satel- No satellite treatment plants. 872.4 20.9 lite plants All flows receiving secondary treatment at the Harbor plants. Postponing of satel- Delayed construction of satel- 884.8 20.3 lite plants lite plants. Upgrade primary treatment at the Harbor plants. Extend treatment capabilities at the Harbor plants to secondary along with construction of satellite plants. 1. Costs shown are in millions of dollars based on January 1975 (ENR 2200) prices. 2. Costs on the basis of future flows (year 2000). (#13) See Bibliography, Appendix B. B- 13 ------- “In light of the great potential negative impact upon water quality, implementation of a Neponset River Satellite Plant is not recom- mended.” A fairly rigorous analysis of the Charles River was undertaken by Alan Ikalainen (at that time of EPA Region I Systems Analysis Branch staff) employing a computer model developed for the ?lassachusetts Division of Water Pollution Control (MDWPC) known as the STREAII model. Based on this analysis, the Draft EIS concluded that: “A satellite plant represents a major new pollutant source for the Charles River, which will increase point source mass input the River of BOD 5 from 329 to 586 kg/d (725 to 1293 ibs/d) and nitrogenous oxygen demand from 311 to 535 kg/d (685 to 1181 lbs/d) (See Table 7, Appendix 3.2.2). In addition, the following table compares the proposed discharge with River quality just upstream of the dis- charge. Impositionof this additional load upon the already stressed river system may effectively preclude the Charles from recovering from its present stressed condition. If River conditions improve such that standards are met, the satellite discharge is indicated to cause violation of standards unless an extremely high level of treatment is achieved on a consistent basis. As the result of this analysis, a satellite plant discharge is seen as not improv- ing water quality in the Charles River and contributing to the maintenance of its present condition. The implementation of a satellite plant discharging to the Charles River is not recom- mended.” The conclusions and recommendations of Mr. Ikalainen’s report are stated here as follows: “ Conclusions “1. The physical characteristics of the Charles River are such that it has a very low assimilative capacity for oxygen demanding wastes at the seven-day, ten-year low flow. “2. This analysis reveals a very major likelihood that the Charles River, at the seven-day, ten-year low flow, when receiving year 2000 wasteloads (5 mg/i CBOD 5 and 1 mg/l NR - N) from existing treatment plants in Milford, Medfield, and Millis and the Charles “River Pollution Control District Plant, will not attain the 0.0. level of 5.0 mg/i for long stretches. This condition will prevail with or without an MDC Satellite plant discharge at any of the locations considered in this analysis. B-14 ------- TABLE B4 COMPARISON OF AWT EFFLUENT AND CHARLES RIVER QUALITY* I . . 2 Charles River Satellite Discharge Flow, m 3 / 0.89 1.353 (ft /s) (31.4) (47.7) Dissolved Oxygen, mg/i 3.1 6.0 BOD 5 mg/i 0.6 5.0 (kg/d (lbs/d) 67 (148) 478 (1494) Nitrogenous Oxygen Demand mg/i 0.005 1.0 kg/d (lbs/d) 17.5 (38.5) 535.8 (1181.5) Total Oxygen Demand mg/i 1.1 11.9 kg/d (ibs/d) 84.6 (186.5) 1231.4 (2675.5) ‘River conditions as modelled at river kilometer 80.3 (river mile 50), just upstream of Medfieid State Hospital discharge point, during 7 day, 10 year low flow. All upstream point sources have effluent quality of 5 mg/i BaD 5 and 1 mg/i NH 3 -N. recommended discharge and effluent quality. 3 This represents an increase of 152% in the flow of the river at the point of discharge. *Froin Ikalainen as noted previously. B- 15 ------- “3. If future discharges at Milford, Medfieid and Millis and the Charles River Pollution Control District can be reliably treated and the river can be reliably treated such that D.0. levels in the river upstream of an MDC satellite plant dis- charge are at 5.0 mg/i at the seven-day, ten-year low flow, then an MDC satellite plant discharge containing 5.0 mg/i of CBODç would not lower D.0. levels below 5.0 mg/l if it is ioca ed upstream of the South Natick Dam. However, this condition would be true only if no other oxygen demanding phenomena such as algal die off and non-point source pollution occur during the low flow periods. “4. It is understood that the “STREAM” model does not simulate all of the physical and biochemical processes that occur in the Charles River and which determine part of its water quality and biotic condition. However, these processes, such as algal growth and death dynamics, land-surface runoff dynamics, septic and solid waste leaching-—all of which are known to occur in the Charles River, can further worsen D.O. conditions at critical periods beyond those processes which are simulated by the “STEAM” model. Such critical conditions would probably be during periods of high temperature, low river flow and between periods of short duration, intense rainfall. The occurrence of base flow (groundwater flow) into the river has not been considered and its effect on water quality is not known. “5. An MDC satellite plant discharge under the anticipated year 2000 wasteloads (5.0 mg/i CBOD 5 and 1.0 mg/i Nil 3 - N at all upstream discharges) will significantly improve D.O. levels in the Charles River only if the discharge is located upstream of the South Natick Dam or near the Medfield Hospital. The improvement will be 1 to 2 mg/i increase in D.0. along several miles of river. However, the improved condition will be significantly below the desired level of 5.0 mg/i. “6. This analysis indicates that benthal oxygen demand is a signi- ficant oxygen loss to the Charles River. For example, at the seven-day, ten-year flow, without sediment oxygen demand and without any treatment plant flow or wasteloads, the Charles would meet the D.0. level of 5.0 mg/i except for a short stretch upstream of Milford where background loads would cause D.0. to fall to 2.5 mg/l. Current wasteloads (1978) added to the river under these same conditions cause D.O. levels to fall to zero below Milford and within the South Natick Dam and Cochrane Dam impoundments. If these wasteloads receive ad- vanced treatment (5.0 mg/i CBOD 5 and 1.0 mg/i NH 3 - N) and the Charles River Pollution Control District Plant receives ad- vanced wastewater treatment, at year 2000 wastewater flows, the zero D.0. levels are raised to greater than 5.0 mg/i below Milford and to about 2.5 mg/i in the South Natick Dam and Cochrane Dam impoundments. B-16 ------- “If an MDC Satellite plant discharge is added to the river at Medfieid with year 2000 flows with advanced treatment, D.0. levels are raised by 1-2 mg/i within the South Natick Dam impoundment and lowered by 1.0 mg/i to about 4.0 mg/l within the Silk Miii Dam impoundment. If the Satellite plant dis- charge is located below the Cochrane Dam, thre will be no D.0. increase within the South Natick Dam impoundment and there will be an additional decrease in D.0. of 1.0 mg/i to about 3.0 mg/i within the Silk Mill Dam impoundment. “In comparison, with sediment oxygen demand at the levels used in this analysis, as the volume of wastewater discharged, not including the proposed satellite plant, increases from no plant wastewater discharged to 1978 flows to 2000 flows, at the respective levels of treatment, the D.0. levels of the river increase successively. The result is that the D.0. levels will be significantly better in the Charles at the year 2000 flows at Milford, CRPCD and Medfieid-Miliis, receiving advanced treatment, than at present flows and treatment levels. How- ever, there will be long stretches with D.0. very much less than 5.0 mg/i within the South Natick Dam and Silk Mill dam impoundments. Adding the MDC Satellite plant flow at Medfield will further raise D.0. by 1-2.5 mg/i within these impound- ments, but it will remain 1-2.5 mg/i below the 5.0 mg/l level. Adding the MDC Satellite plant flow below the Cochrane Dam will raise D.0. about 1.5 mg/i at the discharge point and lower it about 1.0 mg/i within the Silk Mill Dam impoundment. “ Recommendations “1. An MDC satellite plant should not be located on the Charles River unless: “a. it can be shown through further data collection and analysis that those river processes not considered in this analysis will not increase D.O. deficits during low flow periods; “b. it can be shown that treatment plant facilities can be reliably operated to provide the pollutant removals as are shown to be required by this analysis to maintain 5.0 mg/i D.0. in the Charles River at low flow; “c. the public is willing to bear the economic and environ- mental impact costs of a satellite plant at the required location and level of treatment. “2. Treatment applied to wastewater discharges should not reduce levels of all pollutants below those occurring in runoff and other non-point pollution sources of the Charles River unless it is proven through detailed analysis that further treatment is cost effective in terms of significantly improving in stream water quality. B-17 ------- “3. The water pollution control planning process for the Charles River should include, as a possible control for future waste- water from Milford, CRPCD and Medfield-Millis, the limiting of sewer service area and wastewater loadings, such that waste— water loadings to the Charles River are minimized. “ NOTE : “These recommendations are based upon the premise that the water quality standard for dissolved oxygen (5.0 mg/i) has to be met at the seven-day, ten-year low flow. Therefore, new discharges to the Charles must be such at D.O. levels of 5.0 mg/i will be met at low flow and they will be discharging to a river which is meeting standards at low flow. I As a result of the conclusions stated regarding the negative water quality impacts associated with both the Charles and Neponset satellite facilities, the site selection process was abandoned for both facilities prior to the selection of a recommended location for each plant. Detailed evaluations of flow augmentation impacts of the satellite facilities were conducted for each river and reported in the Draft EIS. The conclusions of these evaluations, which also reflect potential water quality impacts previously described, are summarized as follows: Charles River “The future low flow hydrology of the Charles River will be influ- enced by a number of factors not previously considered. The most significant of these is the presence of point source discharges upstream of the MDC service area. Dischar e 3 from these sources is expected 3 tg increase approximately 48.lxlO d (12.7 mgd) - from 19.68x10 in /d (5.2 mgd) in 1973 to 67.76x10 in /d (17.9 mgd) in 2000. These upstream communities draw groundwater from public wells scattered throughout the Upper Watershed (see Figure 2.5-13b) and many private wells. Groundwater withdrawals from wells distant from the river will adversely influence the Charles only after a signi- ficant time lag. Conversely, the water will rapidly reach the river via the sewer systems. The net effect can be considered as augmen- tation of river flow by pumping groundwater storage. These upstream sources roughly balance the export volume and the flow situation in the Charles can be anticipated to remain relatively constant. In addition, implementation of water conservation methods, reduction in I/I and more effective management of the Mother Brook diversion are techniques which can be utilized to ensure low flow problems in the lower Charles watershed do not develop. B- 18 ------- “In summary, it is felt that the benefits of flow augmentation to the Charles River by an additional point source discharge, are not sufficient to warrant the degradation in water quality that such a discharge would cause. Given the option of Harbor discharge, the risks involved with a Charles River satellite discharge are not offset by the benefits to be derived. “While recycling of water within a basin is a worthy objective of a wastewater management plan, it should not be done at the expense of water quality considerations. Indeed, recycling is occurring in the Charles upstream of the study area. As a result of this, water is conserved during times of drought and wat r 3 quality is frequently degraded. Adding an additional 120.24x10 m /d (31.77 mgd) point source to the river does not appear to be environmentally sound. The expenditure of resources on advanced waste treatment would be best applied to existing point sources in the river to maximize the water quality and quantity benefits of their operation. The water quantity/flow augmentation issue is extremely difficult to project and is by no means closed. However, it is felt that a system without satellite plants will best protect the overall environmental concerns within the study area.” Neponset River “The Neponset River is actively regulated for industrial water supply and this controls its low flow characteristics. In addition, the only upstream discharges are industrial cooling waters. Sources of water to make up for export to the Harbor are not readily avail- able as in the Charles watershed. “Between 1970 and 2000, export of Nepons t water to Boston Harbor would increase by approximately 45.42x10 m /d (12 mgd). The loss of this water is a negative impact associated with non—satellite alternatives. However, as previously discussed, significant water quality impacts will be caused by a Neponset discharge. Major water supply wells lie immediately downstream of the most likely discharge points, creating public health concerns. The water quality related impacts are more severe than the water quantity impacts and, there- fore, an all harbor alternative is preferable. “The potential to mitigate those impacts through an alternative augmentation system should be investigated. The active regulation of the Neponset for industrial water supply could be coordinated with flow needs such that both are satisfied during drought condi- tions. In addition, major I/I reductions and water conservation should be emphasized as methods to mitigate quantity related im- pacts. Such actions will have greater long term benefits for the Neponset River Watershed than augmentation with wastewater.” A comparison of the Recommended Plan which evolved as the result of the Draft EIS process based on the EMMA Recommended Plan was presented in the Draft EIS in Section 3.5.9 which summarized the major impacts and costs. B-19 ------- This section is reported here in its entirety as it represents an impor- tant link between the prior Draft and current Supplemental Draft EIS review process. “3.5.9 Conclusion [ Draft EIS, 1978] “With respect to water quality considerations, the non-satellite system (the Deer Island Plan) is the only system alternative which will meet water quality standards. This system will not affect water quality in inland streams and will greatly improve the quality of the existing effluent discharges. The EMMA Plan will similarly improve the quality of the harbor discharges and will reduce their volume somewhat. The EMMA Plan, however, will cause degradation of water quality in the Charles and Neponset Rivers. A Neponset River discharge will cause its dissolved oxygen standard to be violated, while the Charles River discharge will significantly increase the magnitude of projected water quality violations. The No Action alternative will result in the continued degradation of harbor waters. Modified No Action will cause an improvement in ambient water quality conditions but degradation in the vicinity of the existing primary discharge will persist. Overall, the Deer Island Plan is the best of the four system alternatives with respect to water quality. “In terms of water quantity, the Deer Island Plan and both “No Action” alternatives will have a similar effect. That is, they will result in the export of water from the Charles and Neponset water- sheds in the form of sewage. For the Charles River watershed, this loss will be approximately offset by additional point source dis- charges to river. For the Neponset River, an estimated export of 45.42x10 m /d (12 mgd) per day has been projected. The EMMA Plan, since it will result in the discharge of treated effluent to the rivers, will have a lesser impact on low river flows. In fact, the EMMA Plan will result in substantially higher dry weather river flows than have occurred in the past, but at the expense of water quality. “The effects of the No Action alternative on the area’s biotic communities will represent a continuation of present trends. That is, organisms associated with polluted waters will remain. In- creased degradation of water quality as a result of increased pollutant loads will continue to damage the harbor’s flora and fauna as well as the public’s use of them. Modified No Action will improve the situation except in the vicinity of the existing primary outfa].].s. Both the EMMA Plan and the Deer Island Plan will further improve biotic conditions. “The EMMA Plan and the Deer Island Plan will further improve biotic conditions. B-20 ------- “The EMMA Plan will require the use of two additional sites for facilities construction and specifies the filling of Quincy Bay to expand the Nut Island plant and the filling of Boston Harbor to expand the Deer Island plant. This is considered to be a major impact. The Deer Island Plan avoids filling the harbor but requires the complete use of Deer Island plus a major bay crossing. Also, additional interceptor relief is required for the Deer Island Plan. “In terms of construction-related impacts, both the Deer Island Plan and the EMMA Plan will cause more disturbance than either No Action alternative. While each of these systems will produce its own set of characteristic construction impacts, they cannot be easily separated on this basis in terms of a value judgment. “As far as air quality characteristics are concerned, the No Action alternative would result in the least air emissions followed by the Modified No Action alternative. The Modified No Action alternative represents an increase in emissions to the ambient air due to the incineration of the primary sludge, but it would not include the incineration of the secondary sludge. Comparisons of the emissions from primary to secondary sludge incineration at the Deer Island Plan and EMMA Plan sites, indicates the Deer Island Plan would have less air quality impact. This is based upon the lower quantities of emissions and the site location of the Deer Island Plan. This differential is offset, however, by the need to establish a landfill for disposal of digested sludge under the Deer Island Plan. “On the basis of the preceding comparison, the best of the four system alternatives can be selected. The No Action alternative, while it is economical and impacts upon air quality the least, is not considered feasible. Existing primary sludge discharges to the Harbor, poor operation of existing facilities, gross and visible pollution from the Nut Island facility, and persistent bacterial contamination of the Harbor render this alternative untenable. “The modified No Action alternative will improve water quality conditions and benefit the harbor’s biota in a general sense, but the gross pollution from the existing primary outfalls and bypasses will persist. Pollution from sludge discharges will be abated, however. This plan is significantly less expensive than either the Deer Island plan or the EMMA plan and will be more favorable in terms of air quality impacts and primary construction—related impacts. The alternative is rejected, however, on the basis of permitting unacceptable water quality conditions to persist. “The EMMA plan and the Deer Island plan both further improve water quality conditions in the Harbor. As described previously, these alternatives vary in terms of their specific impacts, but they can be separated on the basis of several significant parameters. These include: “1. The violation of water quality standards in the Neponset River and a further deterioration of the Charles under the EMMA plan. B-21 ------- “2. The need for 42 acres of fill in the Harbor under the EMMA plan. “3. The need for a major harbor crossing, additional inter- ceptor relief and drumlin removal under the Deer Island plan. “Beside these factors, the other levels of impact are generally similar with some trade—offs existing between the alternatives. Costs are approximately equal. While Item #3 above represents significant impacts, they can be justified in light of the magnitude of the problem and its solution. Except for drumlin removal, these effects are short term. Items #1 and #2, however, represent long term impacts which are considered unacceptable. The solution to a wastewater management problem should not be resolved by causing other water quality problems. The loss of 40 acres of the Harbor likewise represents an irreversible impact which should not be accepted if there exists any alternative. We therefore, select the Deer Island Plan as the best of the four system alternatives.” In its role as Technical Consultant to EPA Region I in the preparation of the Supplemental Draft EIS, CE Maguire was asked to evaluate the techni- cal basis which led to the conclusions previously discussed regarding satellite treatment facilities and to update the evaluations to reflect additional data, analytical procedures or changes in technology. In this regard, EIS documents and references from the Draft EIS were reviewed; meetings were held with EPA, MDC, MDWPC, DEQE, Division of Water Supply and other pertinent agencies; and data collected in intervening years (e.g. water quality) was assembled and incorporated into the review process. With respect to the Draft EIS itself, the water quality analysis of the Charles River was found to be the major unresolved issue. This issue is identified in a package of correspondence between MDC, Metcalf & Eddy, EPA and MDWPC over the period of 5/18/77 to 7/25/79, culminating in a letter from Martin Weiss, then Chief Engineer of the MDC to Thomas C. McMahon, Director of the MDWPC dated 7/25/79. This letter established a scope of work expected to be conducted by the NDWPC to respond to con- cerns raised regarding the water quality modeling of the Charles River as presented by Mr. Ikalainen. With the exception of the water quality B- 22 ------- survey carried out by the MDWPC in 1978, no documentation was found to indicate that the MDWPC responded to Mr. Weiss’ letter or that the MDWPC has any plans to respond to these items at present. The complete text of the referenced correspondence is contained in Appendix A. The other issue left unresolved in the Draft EIS is that of the siting of the satellite faclities. Although it is pointed out that the issue of siting was apparently considered moot following the presentation of findings regarding water quality impacts, it is unclear as to why a siting decision was preempted at that point in the EIS process. B-23 ------- III. DESCRIPTION OF SDEIS SATELLITE OPTIONS As a result of the joint NEPA/MEPA scoping process for this supplemental draft EIS, EPA was required to reevaluate the original satellite facili- ties proposed in the EMMA Study Recommended Plan (MDC, Oct. 1975, #3), as well as a new satellite facilities proposal submitted by the Quincy Shores Association incorporating wastewater reclamation/reuse via wet- lands effluent disposal in critical water supply recharge areas in the metropolitan area. Both satellite options are described in the following sections incorporating wastewater flow projections reflecting revisions generated in the MDC Nut Island Site Option Study (MDC, June 1982, #4); updated facilities design criterit and costs, and identification of the benefits projected to be associated with each option. B3.l. EMMA Study Satellite Facilities Update Wastewater flow projections for both the Middle Charles and Upper Neponset 1 satellite facilities were updated using flow projections revised in the NI-SOS. The revised flow estimates are summarized in Table B5. Based on these projections, the Middle Charles facility would be designed to treat 15.27 MGD average flow and 37.13 MGD peak flow in the design year 2010. The Upper Neponset would be designed based on average and peak design flows of 9.00 MGD and 22.26 ?IGD, respectively, in the year 2010. Capital and operation and maintenance costs for the Charles and Neponset facilities were updated from 1978 (ENR 2654) to 1983 prices based on an ENR of 4200. As the differences in design flows relative to the overall size and complexity of each facility are small with respect to the updated vs. the original flow estimates used as the basis of design in the draft EIS, no adjustments in costs were made based on the updated flow projections for each facility. Further, it is important to note that the costs do not include sludge pumping, sludge processing (e.g. B- 24 ------- TABLE B5 REVISED FLOW ESTIMATES - CHARLES & NEPONSET SATELLITE PLANTS Charles River Projected Flows Source: MDC Nut Island Site Options Study, 1982, M&E. Community Ave. 1980 1990 2010 Peak Ave. Peak Ave. Peak Ashland 0.39 1.12 0.55 1.56 0.93 2.49 Framingham 5.72 13.32 6.86 15.97 7.72 18.00 Natick 2.67 6.64 2.98 7.36 3.34 8.19 Southborough 0.00 0.00 0.00 0.00 1.06 2.75 Wellesley 1.73 4.24 1.75 4.28 1.85 4.49 Dover 0.00 0.00 0.00 0.00 0.09 0.32 Hopkinton 0.00 0.00 0.00 0.00 0.22 0.65 Sherborn 0.00 0.00 0.00 0.00 0.06 0.24 Totals Neponset River 10.51 Ave. 1980 25.32 Peak 12.14 29.17 Projected Flows 15.27 2010 Ave. 37.13 Peak 1990 Ave. Peak Community Canton (30%) Norwood Sharon Stoughton Walpole 0.49 3.03 0.00 0.78 0.92 Totals 5.22 13.18 7.21 18.00 9.00 22.26 1.26 7.35 0.00 2.08 2.47 0.62 4.21 0.00 1.15 1 .23 1.59 10.29 0.00 2.91 3.21 0.79 4.78 0.26 1.62 1.55 1.98 11 .65 0.78 3.92 3.93 B-25 ------- thickening, dewatering), incineration and ash disposal which are pre- sented as the sludge processing and disposal operations in the draft EIS. (Draft EIS, pg. 3-232, “The sludge produced at the satellite plants would undergo incineration at each plant.”) Updated costs are presented in Table B6. It was further determined that the level and type of treatment projected to be provided at each facility should remain as proposed in the EMMA Recommended Plan and as described in the draft EIS. Proposed effluent limits of 5.0 mg/i CBOD 5 and 1.0 mg/i NH 3 - N at the design year flows can be reliably expected to be achieved via the proposed treatment facility process configuration which represents current state-of-the-art in wastewater treatment technology. As previously stated, from both the EMMA and Draft LIS documents, the major benefits anticipated to be derived as the result of the imple- mentation of satellite facilities are summarized as follows: 1. Satellite facilities would maintain water in its basin of origin and thus provide reliable sources of low-flow augmenta- tion. 2. Satellite facilities would reduce treatment capacity and size requirements at Nut Island. 3. Construction of satellite facilities would result in cost savings for interceptor relief in the southern MSD. 4. Satellite facilities would provide additional opportunities for feasibility on sludge treatment and management. B3.2. Quincy Shores Association (QSA) Wetlands Disposal Option A detailed proposal recommending the implementation of three satellite facilities in three different river basins in the south NSD was prepared and submitted to EPA for evaluation in this SDEIS during the NEPA/MEPA scoping process. (See the main report for a further discussion of the scoping process.) B-26 ------- TABLE B6 COST UPDATE - EMMA SATELLITE FACILITIES Annuat 2 9&rl Total f ual (1) Capital Cogt’ / Cost 6 Cost 6 Satellite Amount x 10 ) ( $ x 10 ) ( 5 x 10 ) Middle Charles 70.5 5.57 12.82 Upper Neponset 61.3 4.74 11.04 1 Cost of facilities based on wastewater treatment plant with diffused , 2 air aeration and post aeration. ‘Capital and O&N costs updated from 1979 to present day based on ENR = (3 $4 2OO. ‘ ‘Total annual costs computed based on 8-1/8% over 20 years Cct r = 0.1028). B-27 ------- The specific facilities recommended in this proposal are shown in the attached Figure B2 and are presented as described below. B3.2.1 The Weymouth Fore River Basin A regional advanced wastewater treatment plant is proposed to be built on the 42” ? C Braintree-Randoiph Extension Sewer on Section 128A downstream of the Braintree Cranberry Brook trunk sewer. This plant could have an 8—10 million gallon per day (mgd) capacity. It would discharge into the Broad Meadow wetlands along the Cochato River where it could replenish critical water supply resources for the Towns of Braintree, Randolph, and Holbrook. A plant located at that point could remove the following flows from the Nut Island plant: 1990 2010 Municipality Peak Peak* Braintree (15%) 0.42 0.97 0.44 1.01 Holbrook 0.14 0.46 0.38 1.12 Randolph 1.83 4.43 1.92 4.62 2.39 mgd 5.86 mgd 2.74 mgd 6.75 ingd *A].1 flow values from June, 1982, Nut Island Wastewater Treatment Plant Facilities Planning Project (NI-SOS). Braintree, Holbrook, and Randolph all share a common surface water supply, Great Pond Reservoir and Richardi Reservoir. Surface waters of the Cochato and Farm Rivers are diverted during peak flow periods to supplement the reservoirs. There have been recent water shortages and the dry-year safe yield of this system is marginal to meet the current demands. All three communities are included in the current MDC water study as potential future connections to the MDC water system. B-28 ------- PAGE NOT AVAILABLE DIGITALLY ------- B3.2.2 The Neponset River Basin A regional advanced wastewater treatment plant is proposed to be built on the 54” MDC New Neponset Valley Sewer on Section 113, downstream of Westwood, Walpole, and Stoughton extension sewers. This plant could have a 35 mgd capacity. It would discharge through a dispersion pipe laid along 1-95 to the extensive Fowl Meadows, which is underlain by high and medium yield aquifers, which are critical to the area’s water supplies. Such a plant could intercept the MDC New Neponset Valley Sewer at Section No. 113. That sewer is a brick interceptor 54” x 60”. Again, using Facilities Planning Report Data, it could recharge flows as follows: 1990 2010 Municipality Peak Average Peak Canton 2.08 5.30 2.62 6.60 Norwood 4.21 10.29 4.78 11.65 Sharon 0.00 0.00 0.26 0.78 Stoughton 1.15 2.91 1.62 3.92 Walpole 1.23 3.21 1.55 3.93 Westwood 0.54 1.49 0.82 2.16 9.21 mgd 23.20 mgd 11.65 mgd 29.04 mgd Allowing for infiltration, as was done in the Facilities Planning Study, the plant would have an average flow design capacity of approximately 35 mgd. If such a daily flow were to be recharged in the Fowl Meadow, say along Route 95 upstream of the proposed plant site, it would provide a dramatic increase in water resources in the Towns of Canton, Norwood, Westwood, and Dedham. The major well fields of the Dedham Water Company are directly downstream of the suggested plant location. The Dedham Water Company has had shortage in the past and has recently lost some capacity due to contamination; they are actively attempting to join the MDC water system. B- 30 ------- B3.2.3 The Charles River Basin A regional advanced wastewater treatment plant is proposed to be built by intercepting the Wellesley Extension Sewer and the Wellesley Relief Sewer at the Easterly Connection Chamber, and pumping to the plant located at the edge of the nearby City of Boston landfill on Gardner Street in West Roxbury. It would discharge to the Cow Island Meadows along the railroad and Route 128, where they are underlain by high and medium yield aquifers serving water supplies in Dedham, Needham, Wellesley, and Weston. Based on Facilities Planning Report Data, it could recharge: The plant size would have an average daily capacity of approximately 50 mgd. Such a plant could recharge water to aquifers containing wells of the Dedham Water Company, and the Towns of Needham, Wellesley, and Weston. Also, the recharge could take place in part upstream of the MDC diversion structure on Mother Brook. This would provide much greater dry-weather stream flows for management of water quality in the lower reaches of the Charles and Neponset Rivers. The following excerpt from the QSA proposal highlights the benefits perceived by the authors to be associated with the facilities described above. 1990 2010 Municipality Average 0.55 Peak 1.56 Average 0.93 Peak 2.49 Ashland Dover 0.00 0.00 0.09 0.32 Framingham Hopkinton Natick 6.86 0.00 2.98 15.97 0.00 7.36 7.72 0.22 3.34 18.00 0.65 8.19 Needham 2.17 5.30 2.24 5.41 Sherborn 0.00 0.00 0.06 0.24 Southborough Wellesley 0.00 1.75 0.00 4.28 1.06 1.85 2.75 4.49 14.31 mgd 34.47 mgd 17.51 mgd 42.54 mgd B-31 ------- These facilities could: • Reduce the size of the presently planned wastewater and sludge treatment facilities at Deer and Nut Islands; • Allow for future growth and expansion in the western suburbs of the !IDC district; • Provide economic reduction in the I/I and CSO problems in the Harbor area by flow reduction in major conduits; and • Enhance recreation and water supply resources in the Weymouth Fore River, Neponset River, and Charles River Basin. The recommendation that the satellite facilities, recommended in the QSA proposal, utilize natural wetlands for effluent renovation and ground- water recharge to existing and potential public water supply aquifers required a multi-level evaluation of effluent discharge criteria in order to develop a basis for conceptual design and costing of the proposed facilities. A review of available literature on wetlands discharge - wetlands treatment capabilities was performed to define suitable hydrau- lic, organic, and nutrient loading criteria for wetlands to serve as a basis for determining wetland acreage requirements, for various levels of treatment to be provided at the proposed satellite facilities. A com- plete bibliography of literature reviewed in this regard is included in Attachment B. Based on this literature review, it was decided to employ the organic and phosphorous loading criteria used to develop wetland area requirements in a feasibility study of wetland disposal of wastewater treatment plant effluent conducted by IEP, Inc., under a research grant for the MDWPC (Ref. #12). This report employed a BOD loading rate of two gallons per day per square foot (2 gpd/sf) which is based on a loading rate equi- valent to a dual media filter and a phosphorus loading rate of 1.5 pounds per acre per day • . • “based both on preliminary review of the litera- ture (108) and the desire not to hydraulically overload the wetland, B- 32 ------- resulting in adverse effects to ecological and hydrogeological environ- ment.” Applying these criteria to the proposed facilities, assuming effluent BOD and phosphorus loadings for both secondary (conventional activated sludge) and advanced wastewater treatment processes, yield the wetland acreage requirements presented in Table B7. In recognition of the proposed discharge locations relative to ground- water recharge areas in or near existing public water supply well fields, the Massachusetts DEQE, Divisions of Water Supply and Water Pollution Control, were contacted to ascertain effluent limits and discharge requirements in light of revised regulations promulgated by DEQE in late 1983. The response from the Division of Water Pollution Control, dated December 29, 1983, which is included in its entirety in Appendix C, included the following remarks: “On October 15, 1983, the Division of Water Pollution Control promulgated a set of comprehensive water pollution control regula- tions (Title 314 of the Code of Massachusetts Regulations) which included detailed groundwater quality standards. These standards define groundwater into these classes (1, 2, and 3); Class 1 being defined as: “fresh ground waters found in the saturated zone of unconsoli- dated deposits or consolidated rock and bed rock and are designated as a source of potable water supply.” “Since all three proposed discharges will be tributary to ground- water currently being utilized as public water supplies (Class 1), all discharges to said groundwater will be required to meet very strict discharge limits; see Attachment 1 (in Appendix C.1). “The discharge limits would basically require that the effluent entering onto the wetland meet or exceed the Primary or Secondary Drinking Water Parameters; see Attachment 2 (in Appendix C.1). In addition, the Division is concerned with the periodic “pass through” of materials such as oil, heavy metals, solvents, phenols, and other highly toxic or contaminating materials which are not substantially removed with conventional waste- water treatment processes and which could cause severe impacts upon these aquifers. B-33 ------- TABLE B7 WETLAND ACREAGE REQUIREMENTS - QSA SATELLITE FACLITIES PROPOSAL Wetland Area Phosphorus Wetland Area Phosphorus Wetland Area Flow Required(1) Load-CAS(2) Required Load-AWT(3) Required ( MGD) ( Acres) ( #/Day) ( Acres) ( 11/Day) ( Acres) Charles River Average Daily Design Flow 20.0 230 2002.0 1335 167.0 iii Peak Design Flow 50.0 574 5004.0 3336 417.0 278 Neponset River Average Daily Design Flow 12.0 138 1200.0 800 101.0 67 Peak Design Flow 35.0 402 3502.0 2335 292.0 195 Weymouth Fore River Average Daily Flow 3.0 34 3000.0 200 25.0 17 Peak Design Flow 10.0 115 1000.0 667 83.0 55 (1)Thls acreage represents the minimum requirements based on hydraulic loadings of wastewater effluent. The acreage shown under AWT would, therefore, have to be adjusted to be consistent with this minimum acreage shown. 2 CAS - Phosphorus loadings based on assumed effluent phosphorus concentration of 12.0 mg/i for typical conventional activated sludge treatment facilities in New England. 3 AWT - Phosphorus loadings based on assumed effluent phosphorus concentration of 1.0 mg/i from advanced waste treatment facility. B-34 ------- “ The Division is of the opinion that proper safeguards necessary to continuously meet Class 1 effluent limitations and to protect these valuable public water supplies cannot be provided. There- fore, the Division strongly discourages the continued review of such subregional facilities as proposed by the Quincy Shore Associates. ” [ Emphasis added.] Similar conclusions and recommendations were stated in a memorandum from the DEQE Division of Water Supply to the DWPC, dated December 16, 1983, including the following: “Aside from the problems associated with determining the assimilative capacity of wetlands for pollutants, this proposal does not address other potential water quality problems. For instance, the proposal does not address the fact that very little control exists over the nature and quality of sewage. Presently, the regulatory manpower does not exist for monitoring illegal or haphazard industrial waste disposal. Many industrial contaminants cannot be detected, let alone treated, in standard wastewater treat- ment facilities. As a result, it is very likely that discharges from the proposed ‘satellite’ plants would ultimately result in the degradation of existing water quality in the receiving wetlands/aquifer. All things considered, water quality degradation is likely to occur either over the short term through problems associated with seasonal flooding/freezing of the wetland, and/or the undetected discharge of a hazardous substance or over the long term by the gradual saturation of the assimilative capacity of the wetland. “Because of these uncertainties and the problems that may ensue, the DWS must conclude that the Citizens Plan proposal for wastewater discharge into wetlands is an unacceptable risk for potentially degrading these vital existing drinking water supplies.” The complete text of the DWS memorandum is included in Appendix C. There is also included in Appendix C a further letter from the Massachusetts Department of Environmental Quality Engineering (DEQE, April 23, 1984) which reviews the above issues and restates its support for the con- clusions made. Although the statements of the DWPC and DWS strongly suggest that the facilities proposal of QSA not be implemented, a preliminary conceptual facilities design was outlined for the purpose of providing a basis for cost comparisons between the two satellite options. The conceptual B-3 5 ------- design shown on Figure B3 incorporates advanced wastewater treatment operations, including primary settling phosphorus removal via chemical additions, conventional activated sludge secondary treatment, nitrifica- tion—denitrification and final settling advanced waste treatment pro- cessing. Treatment beyond AWT levels theoretically leading to wastewater reclamation includes mixed media filtration, carbon absorption, chlorina- tion-dechlorination and post-aeration prior to discharge. Grit, sludge and scum processing and disposal operations are also shown on the sche- matic. Costs for each facility were developed using costs per gallon of waste- water as derived from the updated cost estimates prepared for the EMMA satellites. Capital costs were escalated by 25 percent, and O&N costs were escalated by 40 percent to account for the increased level of treatment provided. These increases are not considered to include sludge processing and disposal. Generalized costs for each of these facilities are summarized in Table B8. While it is recognized that no accuracy can be assigned to these cost estimates due to their conceptual nature, it is felt that the estimates nonetheless reasonably reflect the level of treatment provided under the conditions stated above. TABLE B8 COST SUMMARY: QSA WETLANDS DISPOSAL SATELLITE FACILITIES Total Annua4 d Design Capital gost Annual 0 M Cost’ 6 ’ Flow ( $x lO) ( $xlO) ( $xlO ) Charles River Wetlands Satellite 50 NGD 115.8 11.14 23.04 Neponset River Wetlands Satellite 35 MGD 81.1 7.80 16.14 Weymouth Fore River Wetlands Satellite 10 MGD 30.6 2.65 5.80 (1)Total Annual Costs based on 8-1/8 percent over 20 years (CRF = 0.1028). Costs are ±25%. B-36 ------- PAGE NOT AVAILABLE DIGITALLY ------- B3.3. Relationship of SDEIS Satellite Options With On-Going Facilities Planning in the Southern MSD As a result of the decision to delete the EMMA recommended satellite facilities from further consideration, based on the conclusions of the draft EIS, facilities planning was initiated for relief of critically surcharged interceptors in the southern MSD including the following: Wellesley Extension Sewer (WES) Framingham Extension Sewer (FES) New Neponset Valley Sewer (NNVS) Braintree-Weyinouth Extension Sewer (BWES) In addition to the interceptor relief plans, a major infiltration/inflow (I/I) analysis of the south MSD was conducted by Fay, Spofford and Thorndyke. I/I studies were also prepared for the MDC in the communities of Ashland, Natick, and Framingham, and for the area tributary to the proposed Weymouth Fore River Siphon. An evaluation of the hydraulic capacity of the High Level Sewer was conducted in conjunction with the Nut Island Site Options Study which incorporated the I/I reports men- tioned above, in addition to revised wastewater flow projections pre- viously discussed. Additional studies and reports which must be taken into account include the preliminary report on I/I removal submitted to Professor Charles N. Haar, Court Appointed Master in the suit brought by the City of Quincy vs. the MDC, by the Executive Office of Environmental Affairs in response to Procedural Order, Item No. 5, entitled “Banking/Trading and Greater Than 2 for 1 Program.” An overview of MSD I/I is currently being con- ducted by Camp, Dresser and McXee for the MDW’PC. Consideration of these reports in the evaluation of satellite facilities is of considerable importance relative to the following issues: Implementation of time frame relative to on-going impacts of presently surcharged sewers. B-38 ------- Impacts of uncertainties in present I/I studies on flow pro- jections, design capacity evaluations for interceptors and treatment facilities, and the projected or assumed reduction in the required capacity of the harbor treatment facilities. Based on the current state of completion of Step 1 and Step 2 facilities planning for the major interceptor relief projects (e.g. WES, FES, NNVS, and BWES), it would appear reasonable to project that construction of recommended relief components can be completed within the next three to five years, contingent upon available levels of State and Federal fund- ing. It is estimated that the time frame from Step 1 facilities plan- ning, to start up of operation for any of the satellite advanced waste treatment facilities proposed, will range from ten to twelve years. If the elimination of overflows of untreated wastewater, due to surcharging conditions and the water quality degradation presumed to result from such overflows, is to be considered a primary objective of the wastewater management programs of MDC, DWPC, and EPA being evaluated in this SDEIS, then it would appear prudent at this time to recommend that the relief projects proceed to construction regardless of a decision to reject or to proceed with the proposed satellite facilities. The issue of the relationship between projected reductions in the re- quired capacity of harbor treatment facilities as a result of satellite facilities implementation, and the effects of estimated and measured quantities of I/I on the capacity of the sewerage and treatment facili- ties has not yet been resolved. Several factors have contributed to the lack of consensus or understanding surrounding this issue. Both revised wastewater flow projections and the evaluation of the capacity of the High Level Sewer (HLS) presented in the Nut Island Site Options Study (SOS) state that the results of the I/I studies in the south MSD system prepared for the MDC and community-specific evaluations were taken into account in their development and analysis. Flow esti- mates project a peak flow of 305 MGD in the year 2010 design year. Hydraulic evaluations of the HLS under previous conditions conclude that B-39 ------- the HLS can adequately handle up to 310 MGD. Flow measurements taken by FST and reported in their I/I study included values up to 420 MGD. The conditions under which the extreme of 420 MGD were measured are not clearly defined. It is important to note that, although the capacity of the I lLS is 310 MGD, the available pumping capacity at Nut Island is only 280 MGD. This constriction, in combination with extreme high tide conditions (e.g. spring high tides), or other factors such as extreme precipitation and/or seasonal high groundwater, could produce a “stack- ing” effect in the HLS which may have introduced large errors in flow measurement in the system. Further, the manner and extent to which the I/I data was incorporated into the revised flow estimates developed in the SOS is not clear. As a result of a meeting held at DWPC, Metcalf & Eddy has agreed to provide more detailed explanation of the incorporation of the I/I report into the flow projections. The issues raised point to the need for additional information, including systematic flow monitoring at several locations throughout the south MSD. Also, it would appear necessary to remove the constriction imposed by the pumping capacity at Nut Island by increasing the pumping capacity to equal the design hydraulic capacity of the IlLS. This, in turn, suggests that the peak design capacity of the treatment facility serving the south MSD should also be equal to the capacity of the IlLS as recommended in the SOS. Although the implementation of satellite facilities would theoreti- cally reduce flows to the harbor facilities equal to the design flows of these satellite plants, it does not appear to constitute a safe, reliable basis for reducing the design capacity of the harbor treatment facilities by an equivalent amount. This, in turn, suggests that the implementation of satellite faclities should be delayed until it can be clearly and reliably be demonstrated that flows in the south MSD exceed the capacity of the I lLS and treatment system, and that these excess flows cannot otherwise be economically removed from the system. B-40 ------- IV. EVALUATION OF SATELLITE OPTIONS Both of the satellite options were evaluated with respect to the major environmental issues and perceived benefits which have been identified for both options. These include flow augmentation, water quality and water supply recharge. Issues and impacts relative to siting of any of the satellite facilities have not been addressed at this stage of the EIS process, as the satellite issue has not progressed beyond the level of a conceptual component of the wastewater management program of the MDC. B4.1. EMMA Satellite Evaluation B4.l.1. Flow Augmentation : A detailed analysis of water quantity impacts of the EMMA satellite facilities was presented in Section 3.5.1 of the Draft EIS. The analysis concluded that the satellite facilities would provide significant stream- flow augmentation to the water resources of both the Charles and Neponset Rivers. However, the analysis also evaluated the future low flow condi- tions of the Charles River without the additional future flows of the proposed middle Charles satellite facility. This analysis incorporated consideration of two major factors, which had not previously been con- sidered with respect to flow augmentation, which are the net water quantity exported from the Charles River Basin to Boston Harbor, relative to the projected flow of the satellite plant and the impacts of projected increases in flow volumes from existing wastewater treatment facilities on streamflow during low flow periods. As reported in the Draft EIS, only 13.0 MGD of the projected design flow of the middle Charles satellite plant originates within the Charles River Basin. The remainder originates in the Sudbury River Watershed, or is supplied to the contributing communities from the MDC water supply system originating in the Quabbin Reservoir. The Draft EIS analysis further indicates that the projected increases in discharge volumes from existing wastewater treatment plants in the Charles River Basin, totalling ap- B-41 ------- proximately 12.7 MGD, nearly equals the net projected exported flow of 13.0 MGD, thereby offsetting the effect of exporting that flow to Boston Harbor. Although we concur with the analyses with respect to projected streamfiow conditions without the implementation of the Middle Charles Facility, it must still be recognized that the addition of this satellite plant will result in substantially improved streamflow conditions. Questions raised in the Draft EIS, with regard to water quality condi- tions and potential impacts on downstream water supply resources, are discussed in subsequent sections of this report. The Draft EIS acknowledges the potential streamflow benefit of the upper Neponset satellite facility on the Neponset River, but concludes that significant negative water quality impacts offset any potential benefits to streamflow and water supply resources. Based on our review of the water quality assessment of the Neponset River, we concur with the conclusions of the Draft EIS. B4.1.2 Water Quality : The assessment of water quality impacts of the EMMA recommended satellite facilities on the Charles and Neponset Rivers Consists of a review and analysis of previous modeling conducted for the 1978 Draft EIS, and a review of water quality data collected during intervening years for both rivers. As previously described, an extensive water quality modeling effort was undertaken by EPA (Ref. #14) to assess the impacts of the Middle Charles satellite facility discharge on the dissolved oxygen (D.0) resources of the Charles River under the prescribed 7Q10 flow conditions. A low flow version of the MDWPC from surveys was conducted in 1973 by Erdmann et al. The low flow model was then used to evaluate the dissolved oxygen res- ponse of the river to the projected waste flows, and loads from the Middle Charles satellite and other wastewater treatment facilities projected to be discharging to the Charles River in the design year 2000. The effects of the discharge from the satellite facility were also examined with the discharge occurring at different locations in the B-42 ------- Middle Charles. The conclusions drawn from these modeling analyses were presented in Section II. B2.3 of this report. In general, although the modeling indicates that the Class B water quality criteria for dissolved oxygen of 5.0 mg/I may be violated over some river segments, overall dissolved oxygen conditions would be im- proved at specific critical locations under certain specified conditions as a result of the discharge of a satellite facility as compared to project conditions it. The facility would be required to provide advanced levels of waste treatment bordering on the limits of reliable technology. While it can be argued that the proposed satellite facility will not result in attainment of Class B, D.O. levels at projected low flow conditions, the analysis suggests that the proposed facility could represent a potential benefit to the Charles River, as D.O. levels were observed to increase under certain conditions with the addition of the satellite facility as opposed to without it. The modeling suggests that non-attainment conditions are beyond the ability of point source treat- ment measures alone to achieve. The analysis provides limited evaluation of the issue of other residual pollutants from a satellite effluent discharge. The concerns raised by Metcalf & Eddy and the MDC in the correspondence found in Attachment A, and the responses of EPA staff to these concerns, were reviewed with respect to model formulation, coefficient selection- computation, use of data within the model framework, and the limits within which the available information was employed within the Stream model to project impacts of conditions for which no data is/was avail- able. Model formulations were reviewed with respect to the model des- cription contained in the “STREAII 7A USER’S MANUAL,” prepared for the MDWPC in 1978 by Resource Analysis, Inc. No major changes in model formulations were found between the version of the Stream model employed by Erdmann and Ikalainen, and those described in the 1978 User’s Manual. Based on our review of the work that was done B-43 ------- by EPA and reported in the Draft EIS, we conclude that the modeling reasonably and adequately reflects proper utilization of the available data within the model framework and within the range of sensitivity and variability tested. Other issues were raised in the text of the Draft EIS which played a substantial role in reaching the conclusion stated on page 3-155 that: “The implementation of a satellite plant discharging to the Charles River is not recommended.” These issues relate to the ability of the unit treatment processes envisioned to provide the advanced levels of treat- ment required to result in improved D.C. conditions reliably and consis- tently, given the variability of influent flow and pollutant loading conditions, and the limited degree of control obtainable over these conditions. These are still valid concerns, although there presently exists a significantly increased amount of experience in the operationof advanced waste treatment facilities than was available in 1978. Another issue, with respect to the water quality modeling raised by both EPA and MDC/M&E, concerned the parameters and in-stream processes not accounted for in the Stream Model. Phosphorus is a particular parameter of concern, in this regard, due to its potential impact on algae and aquatic weed production, which in turn would be expected to impact on the magnitude and severity of D.O. variability. A satellite facility even providing phosphorus removal to maintain effluent phosphorus concentra- tions on the order of 1.0 mg/i represents a significant increase in phosphorus loading from point sources in the Charles River. Incorporat- ing these concerns with the considerations offered by the water quality modeling (i.e., that under certain conditions, some degree of benefit may be derived), leads us to conclude that a satellite treatment facility discharging to the Middle Charles River will be of limited, if any, benefit to water quality in the Charles River. Based on available data, however, it is not expected that such a discharge will, in or of itself, contribute noticeably to degradation of water quality conditions beyond present conditions. B-44 ------- A summary of water quality data from DWPC surveys in 1973 and 1978 is presented in Table B9. Partial surveys of the Upper Charles (above the South Natick Dam) were also conducted in 1980 and 1981. The more recent surveys (1980 and 1981) reflect major upgrading of municipal treatment facilities, including the construction of the Charles River Pollution Control District AWT Facility serving the Franklin-Medway area and the Millis—Medfield facilities. Average DO levels for all but one survey period from all survey years are shown in Figure B4. Note the consistent improvement in DO recovery downstream of River Mile (RN) 60, with suc- cessive years of operation of recently constructed facilities. Note also the generally unchanged conditions upstream of RN 60, reflecting the con- tinuing problems observed in the Milford area with respect to the muni- cipal sever and treatment systems, in addition to nonpoint sources in the head water areas of the river. Comparisons between the six survey periods (June 1973; September 1973; June 1978; July 1978; July 1980, and June 1981) on a parametric basis are of limited value based on reported differences in stream flow conditions, water, and air temperatures, rainfall and other climatic factors prior to and during each survey period. Generally, although average and minimum D.O. values have increased over the period covered by the data record, violations of the Class B criteria still occur. Violations of the Class B bacterial criteria of 200 colonies/100 m l continue to occur. Although the fecal coliform data for the June, 1981 survey period show a signi- ficant improvement over the portion of the river surveyed, the limited scope of the survey precludes assessment of improvement in downstream reaches. Nutrient loadings, particularly phosphorus, are of potential B-45 ------- TABLE B9 CHARLES RIVER WATER QUALITY SURVEY DATA SUMMARY — 1973/1978 6/73 9/73 6/78 7/78 6/73 9/73 6/78 7/78 6/73 9/73 6/78 7/78 6/73 9/73 6/78 7/78 6/73 9/73 6/78 7/78 Gauge Station FLOW SUMMARIES DURING SURVEY PERIODS (FLOWS IN CPS) 7/78 USGS Gauge, Dover USGS Gauge, Wellesley USGS Gauge, Waltham 149.2 134.0 170.8 105.2 199.8 111.2 198.2 141.6 257.4 73.3 79.4 98.6 Dissolved Oxygen (mg/fl Temperature (°F) BOD (mg l) NH -N (m /1) NO -N ( g/l) CHO1 8.3 7.5 7.4 7.1 71.3 77.0 64 77 1.7 3.6 5.1 1.9 0.07 0.04 0.01 0.04 0.2 0.5 0.2 0.1 CR02 3.9 4.7 8.0 7.9 74.2 78.0 67 77 3.1 1.6 4.9 3.1 0.29 0.09 0.02 0.04 0.1 0.0 0.1 0.0 CHO3 4.4 4.2 6.1 4.9 70.8 75.0 64 73 6.3 2.7 4.8 2.4 0.20 0.32 0.03 0.10 0.3 0.3 0.4 0.3 CHO4 3.9 1.1 4.6 1.2 70.7 75.0 63 73 21.6 12.3 7.9 5.4 3.85 4.45 3.6 4.9 2.1 2.4 1.6 2.1 CHO5 1.8 1.4 3.0 0.9 71.0 76.0 63 73 4.8 7.8 5.4 4.6 3.45 6.2 3.6 4.3 1.4 2.0 1.4 0.6 CR06 11.5 4.5 8.7 5.3 74.7 80.0 68 78 9.5 4.9 6.4 29.5 2.85 1.01 1.6 5.6 1.0 1.4 0.8 0.6 CHO7 3.3 1.9 5.3 2.6 70.8 76.0 66 75 5.0 4.9 5.1 6.6 2.00 0.92 0.88 0.89 1.1 0.7 1.4 1.2 CR078 --- --- 7.5 5.2 --— --- 66 78 --- --- 3.1 3.3 --- --- 0.04 0.19 --- --- 1.1 0.5 CHO7C --- --- 7.2 5.8 --- --- 65 74 --- --- 1.9 2.5 -—— --- 0.02 0.10 --- --- 1.1 0.6 CR08 6.7 5.5 7.4 6.3 71.1 77.0 64 75 2.6 1.8 2.7 1.6 0.13 0.13 0.04 0.08 0.4 0.7 0.8 0.5 CRO8A 7.3 5.5 6.7 6.0 71.9 77.0 64 79 4.4 2.4 2.5 2.4 0.13 0.36 0.10 0.38 0.6 0.4 0.7 0.8 CHO9 6.0 4.3 7.2 5.6 71.6 77.0 64 74 3.4 3.2 2.4 1.6 0.52 0.58 0.11 0.34 0.7 1.1 0.8 0.8 CR10 7.3 6.7 8.0 6.7 71.8 77.0 64 76 5.3 3.4 2.4 - 2.0 0.18 0.10 0.06 0.17 1.1 1.2 0.8 1.0 CHI1 7.0 7.4 7.2 10.7 73.7 79.0 65 70 4.0 3.6 5.0 3.6 0.07 0.25 0.03 0.01 0.8 0.5 0.6 0.0 CR12 6.4 5.1 7.1 9.0 71.0 74.0 65 75 2.6 2.1 4.3 4.5 0.06 0.20 0.02 0.00 0.7 0.5 0.6 0.0 CR13 6.1 4.8 5.3 8.4 71.3 74.0 66 76 2.3 2.8 2.2 6.3 0.09 0.17 0.02 0.01 0.6 0.5 0.5 0.0 CH I4 4.9 4.4 4.9 5.9 71.8 74.0 66 77 2.3 2.4 2.7 5.1 0.14 0.27 0.03 0.05 0.6 0.4 0.5 0.1 CH I5 5.1 4.7 5.0 7.9 72.1 76.0 66 77 3.3 6.5 2.4 6.3 0.14 0.24 0.04 0.01 0.5 0.3 0.5 0.0 CR16 6.2 5.7 5.4 8.1 72.4 76.0 67 77 4.1 6.0 2.5 5.5 0.07 0.16 0.04 0.01 0.5 0.3 0.6 0.0 CR17 7.0 5.9 6.5 7.6 72.7 76.0 68 74 5.4 4.6 2.4 4.0 0.06 0.14 0.02 0.05 0.5 0.1 0.4 0.0 CHI7A --- --- 6.4 7.1 --- --- 67 78 --- --- 2.1 4.0 --- --- 0:03 0.08 --- --- 0.4 0.0 CR18 7.2 7.0 7.4 6.6 72.4 76.0 67 77 4.1 4.6 2.7 4.5 0.09 0.12 0.02 0.12 0.4 0.1 0.4 0.1 CR19 6.9 7.0 6.9 7.3 72.6 76.0 67 77 4.2 6.0 2.7 3.9 0.07 0.06 0.02 0.12 0.4 0.0 0.4 0.0 CR20 7.3 8.4 8.4 12.3 72.8 76.0 68 80 4.8 6.3 3.1 6.6 0.25 0.05 0.05 0.59 0.4 0.0 0.4 0.1 CH21 6.9 7.8 8.3 11.2 72.2 76.0 68 79 6.6 8.0 3.9 7.2 0.25 0.05 0.02 0.30 0.4 0.0 0.4 0.1 CR22 7.4 6.8 8.3 7.8 72.6 75.0 67 78 4.4 7.1 4.0 6.1 0.28 0.07 0.04 0.38 0.4 0.1 0.4 0.2 CH22A --- --- 8.2 8.0 --- -—- 67 77 --- --- 3.9 6.3 -—- --— 0.02 0.34 --— --- 0.4 0.2 CH23 7.1 7.8 8.3 10.2 73.5 76.0 67 79 5.9 7.2 4.0 7.0 0.24 0.06 0.01 0.09 0.4 0.0 0.3 0.2 CR24 7.4 6.6 7.8 8.0 72.1 74.0 67 73 4.1 5.1 3.7 5.8 0.27 0.08 0.01 0.08 0.4 0.1 0.3 0.3 6/73 9/73 6/78 ------- CHARLES RIVER WATER QUALITY SURVEY DATA SUMMARY - 1973/1978 Total Kjeldahl Nitrogen (mg/i) 6/73 9/73 6/78 7/78 Total Phosphorus (mg/i) 6/73 9/73 6/78 7/78 Suspended Solids (mg/i) 6/73 9/73 6178 7/78 Total Solids (mg/i) Turbidity (NTu) 6/73 9/73 6/78 7/78 6/73 9/73 6/78 7/78 CR01 --- --- 0.29 0.97 0.03 0.02 0.04 0.73 1.0 18 5.5 1.0 --- --- 125 68 --- --- 1.3 1.3 0102 --- --- 0.34 1.2 0.06 0.04 0.05 1.0 1.0 19 1.8 1.0 --- —-- 116 137 --- —-- 2.0 1.9 CR03 --- --- 0.72 1.4 0.17 0.21 0.09 1.6 5 34 5.0 6.0 --- —-- 179 183 --- —-— 2.3 3.9 CR04 --- --- 4.3 5.8 3.55 4.60 2.1 4.3 4 22 16 1.5 --- —-- 241 256 --- --— 3.0 3.9 CR05 --- --- 4.3 4.4 3.10 4.00 1.3 4.2 1.0 37 5.8 5.2 --- —-- 271 220 --- --- 2.9 3.6 CR06 --- --- 2.7 6.6 2.90 3.15 0.92 4.2 5 25 12 51 -—- —-- 216 305 -—- --- 2.5 5.7 CR07 --- --- 1.8 2.9 1.75 1.85 0.84 2.2 3 27 6.0 17 --- —-- 190 202 -—- -—- 2.6 4.3 CHO7B --- --- 1.4 1.2 --- -—- 0.60 1.5 --- --- 7.0 6.2 --- --- 169 186 --- —-- 2.4 3.5 CHO7C --- --- 0.72 1.4 --- -—- 0.57 1.2 --- -—- 6.0 4.2 --- --- 169 262 -—- —-- 1.7 3.6 CR08 --- --- 0.84 1.5 0.75 0.90 0.47 1.0 1.0 19 5.2 0.5 --- --- 170 157 --- ——- 2.0 3.1 CHO8A --- --- 0.45 1.6 0.48 0.35 0.59 1.0 6 32 6.0 2.2 --- --- 165 172 --- --- 2.4 3.1 CR09 --- --- 0.89 1.4 0.93 0.93 0.68 1.0 1.0 17 4.5 2.5 --- --- 170 170 --- --- 2.4 2.7 CR10 --- --- 0.84 1.1 0.85 0.95 0.54 0.94 4 31 8.2 3.2 --- --- 174 179 --- -—- 2.3 2.4 CR11 --- --- 0.72 1.6 0.88 0.63 0.40 0.44 5 22 10 28 --- --- 149 129 -—- --- 2.1 5.0 CR12 --- --- 0.35 1.2 0.58 0.38 0.37 0.38 1.0 20 10 6.0 --- --- 274 113 --- --- 2.0 5.1 CR13 -—- --- 0.38 1.2 0.44 0.33 0.39 0.40 8 26 12 11 --- --- 145 129 -—- —-- 1.4 4.7 CR14 --- --- 0.98 1.5 0.45 0.35 0.34 0.44 6 33 10 18 --- --- 177 130 --- -—- 1.9 4.9 CR15 --- --- 0.88 1.4 0.45 0.35 0.34 0.41 3 25 8.2 7.5 -—- --- 162 133 --- --- 1.5 5.3 CR16 --- --- 0.88 1.3 0.50 0.32 0.30 0.35 4 29 8.5 12 --- --- 160 171 --- --- 1.4 3.5 CR17 --- --- 0.85 1.2 0.37 0.24 0.16 0.27 3 30 8.5 21 --- --- 141 150 --- --- 1.3 2.7 CH17A --- --- 0.88 1.2 --- -—- 0.18 0.26 --- --- 6.2 8.7 --- --- 140 146 --- --- 1.4 2.7 CR18 --- --- 0.83 1.3 0.36 0.23 0.21 0.29 4 27 6.7 8.2 --- --- 189 152 -—- --- 1.5 2.2 CH19 -—- --- 0.91 1.4 0.36 0.20 0.17 0.28 5 36 8.5 16 --- ——- 137 152 -—- ——- 1.2 3.1 CR20 --- --- 1.1 2.0 0.39 0.16 0.17 0.25 5 40 -18 14 --- --- 153 156 --- --- 1.4 6.1 CR21 --- --- 1.0 2.0 0.33 0.18 0.17 0.22 4 42 11 17 --- --- 142 157 --- --- 1.6 6.7 CH22 --- --- 0.95 1.9 0.28 0.17 0.16 1.2 3 31 20 22 --- --- 171 184 --- --- 1.5 5.3 CH22A --- --- 0.90 2.3 --- --- 0.16 0.24 --- --- 18 26 --- --- 156 180 --- —-- 1.5 5.5 CR23 --- --- 0.88 2.4 0.26 0.16 0.20 0.20 7 28 16 14 --- --- 160 169 --- --- 1.6 12 CR24 --- --- 0.89 2.0 0.27 0.16 0.24 0.18 6 25 14 14 --- --- 176 168 --- --- 1.8 9.3 ------- CHARLES RIVER WATER QUALITY SURVEY DATA SUMMARY - 1973/1978 (Cont’d) pH (mg/i) . (Std. Units) (#/lOOmi)(Geo. Mean) (#100/mi)(Geo.Mean) 6/73 9/73 6/78 7/78 6/73 9/73 6/78 7/78 6/73 9/73 6/78 7/78 6/73 9/73 6/78 7/78 CHO 1 6.8 7.0 6.9 6.3 9 29 11 9 740 19800 550 350 --- --- 17 5 CH O2 6.9 6.9 7.4 7.4 19 31 20 29 630 29900 220 80 --- -—- 7 7 CHO3 6.9 6.5 7.3 7.2 23 37 31 38 23000 52300 12000 12000 --- ——- 650 390 CHO4 6.9 6.6 7.3 7.1 37 53 57 68 32000 134000 34000 54000 --- —-— 3900 6200 CH O5 6.8 7.0 7.3 7.2 37 71 30 67 16000 56100 9000 1200 --- --- 1100 54 CHO6 7.4 7.0 7.5 7.1 37 45 38 58 630 13400 370 280 --- -—— 16 5 CHO7 7.1 6.8 7.3 7.4 31 35 30 40 350 30000 2000 3300 --- --- 150 240 CH O7B --- --- 7.3 7.3 --- --— 23 36 --- --- 610 1600 --- -—- 110 14 CHD7C --— --- 7.3 7.6 --- —-— 22 37 --- --- 1100 320 -—- --- 160 24 CH O8 7.1 7.0 7.2 7.4 19 30 19 32 2000 34600 1200 3400 --- -—— 300 550 CHO8B 7.2 7.5 7.2 7.3 16 28 20 33 490 8500 730 1200 --- --— 130 150 CH O9 7.1 6.9 7.2 7.4 21 30 20 29 3000 40000 1600 1300 --- --- 270 63 CH1 O 7.2 7.2 7.2 7.5 21 26 19 27 22000 29200 1400 1800 --- --- 380 240 CH 1 1 7.2 7.3 7.1 8.4 18 27 19 25 1600 2400 1200 280 —-- --- 100 24 CH12 7.2 7.3 7.2 7.9 17 24 18 26 1700 25900 2400 420 --- --- 290 100 CH13 7.1 7.1 7.0 7.1 17 23 21 33 22000 16700 650 320 --- -—— 89 23 CH14 7.1 7.0 7.6 7.4 18 26 21 28 39000 52500 6920 84000 —-- --— 140 89 CH15 7.1 7.3 7.6 7.7 18 28 22 28 35000 77500 4700 7600 —-- --- 56 28 CH16 6.9 7.1 7.5 7.4 18 25 21 28 26000 13300 1900 740 --- -—- 75 14 C1117 7.1 7.0 7.6 7.5 18 27 24 28 3300 34500 650 170 —-- -—— 51 20 CH17A --- --- 7.7 7.3 --- --— 22 27 --- -—- 200 710 --- -—- 20 20 CH18 7.1 7.3 7.6 7.4 19 27 23 28 2000 23100 720 710 -—- -—— 63 34 CH19 7.2 7.1 7.6 7.4 18 27 20 27 850 28800 690 600 —-- -—— 55 56 CH2O 7.1 7.4 7.5 --- 21 29 23 35 1800 22000 940 240 --- -—— - 130 60 CH21 7.2 7.6 7.7 8.7 22 29 24 33 5800 140000 1900 260 --- -—- 180 74 CH22 7.3 7.6 7.5 7.7 21 31 25 31 1700 40600 8800 3700 --- --- 220 1000 CH22A --- --- 7.5 7.7 --- --- 24 31 --- --- 2200 4600 ——- -—- 400 460 CH23 7.4 7.3 7.4 7.7 24 32 22 31 5200 34600 1400 4800 --- --- 80 400 CH24 7.3 7.0 7.5 7.6 25 32 23 32 20000 48600 9500 990 --- --- 240 320 ------- FIGURE B4 CHARLES RIVER AVERAGE DISSOLVED OXYGEN UW. PC. SURVEYS -1973,1978,1980, & 1981 0 ’ z Ui x 0 0 U i 0 (I , C l) 0 RIVER MILES ------- concern based on a review of chlorophyll-a data at stations common to all surveys as presented below: CHLOROPHYLL- a (mg/rn 3 ) River 1973 1980 1981 Mile Sta. Concentration Sta. Concentration Sta. Concentration 76.5 CHO1 2.5 CHO1 0.81 72.0 CHO5 7.9 CHO5 3.32 CR03 3.74 60.1 CR10 5.0 CH14 1.66 CHO9 1.08 44.6 CH15 19.8 CR19 27.07 CH14 50.76 33.0 CR18 29.2 22.1 CR20 92.2 18..3 CH22 90.0 9.8 CR24 60.8 Note: Chior. -a data was not reported for the 1978 survey periods. Substantial increases are observed over the sampling periods covered at the sampling stations identified at RN 44.6. As chlorophyll-a is indi- cative of the productivity occurring in a water body in response to available nutrient supplies, additional sampling over a wider area of stream coverage appears warranted. As indicated in earlier discussions, the potential impacts of increased nutrient loads from a satellite facility can be expected to be reflected in increased productivity and chlorophyll-a levels. An area which has not been addressed, with respect to a satellite facility, is that of possible instream mitigation measures to reduce or offset the potential impacts of the discharge, such as instreain aeration, use of artificial wetlands for nutrient removal (and subsequent harvesting), or other alternative measures. The impacts of a satellite facility discharge to the Neponset River were evaluated using a Streeter-Phelps analysis. The conclusions of this analysis were presented in Section A.3 of this report. Based on our review of the modeling discussion contained in the Draft EIS and Appendix 3.2.3-2, we concur with the conclusion that a satellite discharge would negatively impact the dissolved oxygen resources of the river. Further, based on discussions with DWPC and TSB staff, it was determined that more sophisticated modeling was not warranted due to the severity and magni- B-SO ------- tude of the projected inpacts. Again, although instream mitigation measures were not considered in the evaluation, the projected impacts are sufficiently severe on the Neponset River that any such measures may not be capable of providing a reliable degree of improvement. Water quality data for surveys conducted in 1973 and 1978 by the MDWPC are summarized in Table BlO. Summaries of flow data during each survey period are also shown on Table BlO, together with the 7Q10 low flows for each gauging station. As shown, the August, 1978 survey period flows are very close to the 7Q10 flows. Although D.O. levels generally appear to increase (both average and minimum values reported), periodic violations of the Class B criteria still occur. Much of the river is also in violation of the fecal coliform criteria, based on data reported in the 1978 survey. (Fecal coliforni were not enumerated in the 1973 survey.) The imposition of a satellite facility to the upper Neponset River may be expected to reverse any trends toward the gradual improvement of water quality conditions in the river as are suggested to be occurring based on the available data. B4.1.3 Water Supply : Potential impacts of the satellite facilities on water supply wells hydraulically connected to the main stem rivers, downstream of the proposed discharges, were identified as major concerns in the Draft EIS. The principal concerns relate to pollutants not removed by the treatment processes, and the inability to control influent quality to the treatment facilities. Under low stream flow conditions, when discharge volumes would comprise a significant proportion of total stream flow, it is possible that wells located near the mainstem of both rivers could result in drawing surface water in the river channels into the groundwater regime of the wells, resulting in potential health impacts to the popu- lations served by those wells. B-5 1 ------- TABLE BlO NEPONSET RIVER WATER QUALITY SURVEY DATA SUMMARY — 1973/1978 Dissolved Temperature ROD NH —N NO -N Total Phosphorus Oxygen (mg/i) (°F) (mg/i) (m4/ l) (m4/l) (mg/i) 7/73 8/73 8/78 7/73 8/73 8/78 7/73 8/73 8/78 7/73 8/73 8/78 7/73 8/73 8/78 7/73 8/73 8/78 r oi 8.9 5.4 7.5 79.5 76.2 72 6.15 4.20 4.0 0.00 0.270 0.02 0.00 0.00 0.0 0.085 0.125 0.10 NEO2 7.7 3.5 6.8 79.0 72.7 71 4.50 2.95 6.3 0.015 0.400 0.08 0.35 0.20 0.1 0.280 0.335 0.14 NEO3 7.4 6.1 7.0 76.8 71.9 71 3.70 4.05 5.0 0.020 0.265 0.09 0.40 0.40 0.2 0.170 0.205 0.12 NEO4 4.9 3.0 5.1 75.2 71.0 69 2.40 2.10 3.0 0.040 0.190 0.05 0.25 0.15 0.2 0.185 0.160 0.09 NEO5 6.7 6.5 7.8 74.8 71.8 69 3.20 2.60 5.0 0.030 0.150 0.01 0.30 0.30 0.2 0.165 0.135 0.08 NEO6 3.8 3.9 7.8 75.5 71.7 69 2.80 6.20 3.2 0.065 0.080 0.01 0.20 0.20 0.2 0.130 0.170 0.10 NEO7 4.8 4.5 6.7 82.5 78.0 77 3.50 1.80 3.3 0.085 0.190 0.02 0.25 0.30 0.1 0.100 0.105 0.06 NEO8 6.7 6.8 8.1 79.8 76.6 74 3.20 2.50 3.8 0.040 0.200 0.03 0.25 0.25 0.1 0.105 0.100 0.05 NEO9 7.8 7.8 8.0 76.0 72.8 71 1.70 1.70 2.8 0.065 0.110 0.01 0.45 0.35 0.1 0.090 0.040 0.10 NE1O 6.7 6.9 7.4 77.7 74.1 71 2.50 1.30 4.5 0.025 0.115 0.01 0.35 0.35 0.2 0.100 0.095 0.05 NEll 5.6 5.7 6.5 76.2 73.1 70 2.00 2.20 2.7 0.090 0.175 0.07 0.35 0.65 0.4 0.105 0.085 0.06 NEI2 6.9 6.8 6.5 76.3 73.4 72 1.90 1.80 3.9 0.030 0.145 0.06 0.35 1.15 0.6 0.055 0.055 0.06 NE13 5.0 5.2 5.8 75.6 72.6 70 3.00 1.80 2.8 0.080 0.110 0.06 0.35 0.45 0.2 0.095 0.090 0.05 NE14 5.6 5.6 6.7 77.0 73.2 70 3.15 2.50 2.4 0.135 0.175 0.08 0.45 0.35 0.2 0.170 0.135 0.06 NE15 6.5 6.6 6.9 76.5 73.3 70 3.45 2.00 3.2 0.120 0.120 0.19 0.45 0.45 0.4 0.180 0.085 0.12 NE16 5.7 5.6 7.8 76.3 72.2 70 2.10 1.70 2.8 0.100 0.140 0.10 0.45 0.45 0.2 0.170 0.085 0.09 NE17 5.3 6.0 5.2 68.3 68.4 69 1.45 1.40 3.2 0.370 0.340 0.28 0.05 0.05 0.0 0.130 0.080 0.22 FLOW SUMMARIES DURING SURVEY PERIODS Average Fiow (CPS) Average Fiow 7/73 8/73 8/78 Gage Record 7Q10 Neponset River USGS Gauge at Norwood 36.0 46.8 11.08 51.8 4.9 East Branch USGS Gauge at Canton 45.8 47.8 12.08 50.6 3.4 ------- NEPONSET RIVER WATER QUALITY SURVEY DATA SUMMARY - 1973/1978 (Cont’d) Total Alkalinity pH Total Coliform (mg/fl (Std. Units) (#/lOOml)(Geo. Mean) 7/73 8/73 8/78 7/73 8/73 8/78 7/73 8/73 8/78 7/73 8/73 8/78 7/73 8/73 8/78 7/73 8/73 8/78 NEUl 19.0 24.0 24 7.4 7.0 7.0 300 300 500 NEO2 22.0 25.0 24 7.5 6.6 7.0 3000 2500 5000 NED3 24.5 24.5 26 7.4 6.6 7.1 21000 26000 16000 NEO4 24.5 23.5 26 7.4 6.3 7.1 6500 5300 2400 NEO5 23.0 23.5 26 7.4 6.6 7.1 24000 5000 6000 NEO6 21.0 25.5 28 7.5 6.8 7.2 34000 5000 15000 NEO7 21.0 28.0 29 7.3 6.9 7.3 11000 3500 3000 NEO8 21.0 27.0 30 7.4 6.6 7.2 9000 1900 1400 NE O9 20.5 22.5 23 7.4 6.8 7.3 35000 13000 4800 NE1O 22.0 27.5 27 7.3 6.9 7.2 23000 11000 27000 NEll 23.5 29.0 30 7.4 6.7 7.3 12000 1000 9700 NE12 22.0 23.0 30 7.4 6.8 7.2 3700 15000 6000 NE13 22.5 24.5 30 7.6 6.6 7.2 7700 81000 1700 NE14 24.5 26.0 30 7.6 6.6 7.2 29000 79000 21000 NE15 22.5 24.5 33 7.6 6.5 7.3 33000 62000 84000 NE16 23.5 25.0 33 7.5 6.8 7.3 12000 25000 50000 NE17 70.0 85.0 92 8.0 7.3 7.4 34000 12000 38000 ------- While the concern for potential public health impacts is certainly a valid one, the assessment of risk associated with the proposed satellite facilities is difficult, given the long history of discharges of both treated and untreated wastewaters to both the Charles and Neponset Rivers. Given that there are no existing wastewater treatment facilities discharging to the Neponset River, it can reasonably be argued that the satellite facility proposed represents an unacceptable risk with respect to the protection of water supply resources. Given both the existing and projected wastewater flows from existing treatment facilities discharging to the Charles River, it cannot be clearly established that the discharge from the proposed satellite facility would represent an increase in the degree of risk of public health impacts, in addition to the risk that must be associated with existing facilities. Detailed hydrogeological investigations would be required to develop a reliable basis for defining the incremental risk associated with a satellite facility on the Charles River. B4.2. Wetlands Disposal Option An initial step in the evaluation of the QSA—Wetlands Disposal Satellite Option involved in the determination of available wetlands within rea- sonable close proximity to the proposed sites for the three satellite facilities included in the proposal. Wetland maps for the Weymouth, Charles, and Neponset River Basins prepared in 1976 by the Metropolitan Area Planning Council (MAPC) “208” water quality project were used to determine the acreage of inland wetlands located within 1000 feet radius and within a 1 mile radius of the proposed location of each facility. Table Bli summarizes the estimated wetland acreage available within these two zones, and compares the “available” wetland acreage with the previous estimate of wetland acreage required for each discharge, as presented in Table B7. The estimated wetland acreage required is based on the phos- phorus and BOD loading criteria as previously described. B-54 ------- TABLE Bil PRELIMINARY ESTIMATE OF WETLA1 DS AVAILABILITY FOR WETLANDS DISPOSAL TREATMENT FACILITIES Inland Wetland Inland Wetland Treatment Wetland Acreage Area Within Area Within Facility Required 1,000’ (Acres) 1 Mile (Acres ) P BOB Charles River 278 574 232.5 593.9 Neponset River 195 402 116.9 269.3 Weymouth Fore River 55 115 69.2 189.5 ‘Based on phosphorus and BOB loading criteria as per Table 6. As can be seen, the extent of “available” wetlands is dependent upon the selection of loading criteria used in the cases of the Charles and Weymouth Fore Rivers. The Neponset River does not appear to have a sufficient amount of available wetlands within 1,000-foot radius to satisfy either criteria. The available wetlands within 6 miles of the Neponset facility would satisfy only the phosphorus loading criteria. It is important to recognize that this estimate of “available” wetlands is based on available mapped information only and has not been confirmed by any level of field investigation of the wetlands identified. Nor has the estimate considered the ownership or other aspect of allowable or re- stricted uses which may affect the actual availability of a particular area. Finally, the costs which might reasonably be associated with an effluent pumping and distribution system which might be required under any of the treatment plant-wetland disposal area combinations possible are not developed beyond those figures presented in Table B8. Based on the responses of the DEQE-DWPC and DWS to the subject proposal, which are presented in Appendix C and which reflect preliminary assess- ments of the proposal conducted by Maguire staff, additional evaluations were not conducted. The major areas of concern with regard to impacts are summarized below. B-55 ------- The development of the proposed wetlands discharge satellite facilities presents an unacceptable risk to public health and important water supply sources in the metropolitan region. As in the discussion of risk asso- ciated with the ENMA satellite facilities, the risks associated with placing a wastewater treatment plant discharge in intimate contact with existing clean sources of public water supply are unacceptable from a State regulatory perspective. Actual versus estimated wetland areas available and limits posed by the selection of loading criteria suggest that the scale of the wastewater facilities proposed is excessive for the safe application of wetlands disposal technology. Also, the use of wetlands for effluent disposal on a year-round basis could preclude the flow regulating function of natural wetlands which is an important aspect of flood storage hydrology in an urbanized area. This aspect may further negate any potential benefits with respect to groundwater recharge. As pointed out by the DWPC and DWS, the renovation aspect of wetlands disposal is one of uptake and release. Experience with small-scale wetlands disposal projects, relative to this aspect of facility operation and maintenance, has led to the more prevalent practice of artificial wetland systems which can periodically be renovated by harvesting or dredging accumulated vegetation and decaying organic matter. B-56 ------- ATTACHMENT A WATER QUALITY MODELING CORRESPONDENCE INDEX 7/25/79 Martin Weiss, Chief Engineer, MDC, to Thomas C. McMahon, Director Mass. DWPC, re: tasks remaining to be carried out under DWPC basin planning. 4/26/79 Libby Blank, Director of Environmental Planning, MDC, to Kenneth Johnson, U.S. EPA, re: EPA and MDC responsibilities in conducting Charles River Watershed Analysis. 3/29/78 Jekabs P. Vitt nds, Vice President, Metcalf & Eddy, Inc., to Libby Blank, Director of Environmental Planning, MDC, re: comments on Dissolved Oxygen Modeling, Charles River, Massachusetts . 4/28/78 Daniel W. Donahue, Project Engineer, Metcalf & Eddy, Inc., to John Elwood, Environmental Planning Division, MDC, re: review comments on Mr. Polese’s memorandum on Charles River 1978 survey (attached). 3/1/78 Wallace E. Stickney, Director, Environmental and Economic Impact Office, U.S. EPA, to Libby Blank, Director of Envi- ronmental Planning, MDC, re: Allen Ikalainen’s “Comment on Memorandum on the Review of Dissolved Oxygen Modeling , Charles River, Massachusetts” (both attached). 7/27/77 Mary E.Shaughnessy, Environmental Impact Analyst, U.S. EPA. to Libby Blank, Director of Environmental Planning, MDC, re: Charles River water quality modeling. B- 57 ------- 8/5/77 Allen J. Ikalainen, Acting Chief, Systems Analysis Branch, U.S. EPA, to Libby Blank, Director of Environmental Planning, MDC, re: Charles River water quality modeling, responses to Metcalf & Eddy questions. 7/6/77 Jekabs P. Vitlands, Metcalf & Eddy, Inc., to Libby Blank, Director of Environmental Planning, MDC, re: questions on Charles River water quality modeling. 7/18/77 Libby Blank, Director of Environmental Planning, MDC, to Mary Shaughuessy, U.S. EPA, re: comments on Charles River water quality modeling. 5/18/77 R.W. Chapin, Environmental Assessment Council, Inc., memoran- dum to Mary Shaughnessy, Project Officer, U.S. EPA, re: location of Mid-Charles River satellite plant discharge. B- 57a ------- /( , - // ‘ /,.; ,‘,?i ( J h’, /.‘,‘/ jj/f.// 1” I’ /1 ...‘C.J’rrm,rj,f Jt,”i’/. -7)’ .Jn ( .. ‘(J C:FICE or - E Cr \C T L - -. July 25, 1979 Mr. Thomas C. Mc!ahon, Director Division of Water PoUution Ccntrol 110 Tren3nt Street Boston, MA 02108 Dear Mr. McMahon: Pursuant to our discussions of July 3, relative to the DWPC co 1rnitr,ent to do a Phase II Basin Plan for the Charles River, and in l•ight of recent discussions between Mr. Al Cooper an of your office and Mr. Jekabs Vittands of Metcalf & Eddy, we find that the following tasks remain to be carried out under the D PC basin planning proc rain. 1. Coi.duct a detailed review of the Charles River model input values and develop their ranae of confj ence . For example, the. )S modelling effort assume4certain_values for_non 9 nt source impacts and sediment deposit_impact ich each resuT in using up abouT 40 p T of the River’s oxygen resources. Therefore, assumed values played the most significant role. 2. Conduct a detailed revie _oL mod j parameters anj_d€ve p their range of confidence. For example, the reaeration coefficients used by the E]S modelling effort in certain reoc es .ere about ten percent of those used by the DWPC Easin Plan. Yet, both efforts reflect similar model calibration results. 3. Conduct on parameters and input data relative to their impact on satellite plant discharges. 4. Conduct field measurements to narrow the confidence ranges of those parameters and input data that impact ater quality modelling based decisions on satellite plants. ------- •: -. r.:r C. Mc ahci , Director - 2 - July 25, 157 5. Make model runs and conduct analyses to provide the water quality modeilina bases for determining the desirability of satellite plants addressing questions 1 such as: - Do dissolved oxygen violations occur with and without satellite plants? - If so, how often do they Occur and how severe are they? - What water quality goals can be achieved with and w tho t satellite plants? Mr. Cooperrnan further indFcated two additional relevaflt points. First, the modelling formulations for the Charles River have been carried out by the DWPC and have been verified. Secondly, DWPC plans to conduct the remaining tasks when new members of his staff have been sufficiently trained, but that results would not be available in the near future. Our interest is to insure that the necessary work will be reasonably scheduled so that future wastewater treatment . decisions can properly be made. At such time that Mr. Cooper-nan’s staff resun e activities in tns matter I suggest they contact and visit with Metcalf & Eddy personnel who have been involved with Cha es River modelling revie . I enclose for your staffs use a copy of some of this w3rk as it rela t i ô EPA’s EIS i odelling on the Charles River. - If we have your concurrence the above tasks will be included in the Phase II Basin Planning, there will be no need for DC to do this work in the ut Island Facilities Planning. Please advise this office as soon as possible as to your concurrence so that we can finalize the scope of work for the Nut Island Facilities Planning contract. Yours truly, 2 & Martin Weiss Chief Engineer RGJ : mmw Enclosures (1 — 8, inclusive) cc: Al Coooerrrianw/o enclosures it3’ö 2 1979 J,V :: T. :. ------- - -‘ •-‘ /1/ /—1 /, ,2 i2 /7 j: : :: j -Ji2e 6mm&n,leea/Z/i 6’ 1 .h / ‘ : ‘ 20 ,ierje S’Zree4 £ e z, 0& 8 / 7/7ç/ Environmental Planning Office ______________________ r 0 rr r i i ,’ MLTCALr ô LULl!, Ii: .; . FILE...... D IC April 26, 1979 Mr. Kenneth Johnson Special Assistant Environmental Protection Agency JFK Federal Building Roston, Mass. Re: Charles River Water Quality Analysis Dear Ken: I am Titing because I believe some clarification of EPA and C responsibilities in conducting the Charles River Water Analysis is needed. Attached is the Charles River Analysis section from the Site Options Investigation scope of services, which outlines MDC’s work items. Also enclosed is a rnemora.ndirq, which we asked Metcalf Eddy to prepare, outlining the tasks to be performed by EPA. We would appreciate your reviewing the meinoranthnn and scope to assure that we are in accord on our mutual responsibilities. Yours truly, Libby Blank Director of Environmental Planning LB/co cc: D.O’Brien, EPA J.Vittands, M E 1 Enc: 2 ------- — $ . • :i . e the b .i r tLe selection — t’C ’:1er: C i!”flflCtS, — CflV i’oniicntal impncts, — .;ocial im icts, — •‘ l 1 C:)l ii flct: , and — institutional inpacts. 23. . l ,t!1c l inv ti ption of Charles River U .tcr uaUty The purpose of’ this investiCation is to determine .hcther there is any opportunity for the discharge from an EDC satellite treatment plant into the Charles River in conformance with The Clean Water Act such that the potential for reclar ation of wastewater, as well as the deployment of innovative technologies, can be considered. The investigation is intended as a continuation of the effort made by EPA during preparation of the EIS on the E A study. lthough the continuation is to be a joint EPA—F DC effort, the major work is expected to be conducted by EPA wIth MDC participating in a program guidance, review and decision— making role. To this end, it is expected that EPA will carry out the following: — Update the EIS data base on the Charles River studies, especially with new information on wastewater discharges and recent field measurements. Prepare a file on that data base and provide a copy to MDC. — Review modeling formulations especially considering the results of such an effort carried out on behalf of the 1 ’ ------- cc’tt P vi oi of U Lcr roll ut o: ’Cc: :‘. i (“ ‘d I tient. t i lCl c!n C ; tj L :-:‘be i cCr — ;odi ‘y the ‘oa1mLI.’d y EPA as nccc: .nIv and ; ‘e ’d tij’oii with !‘ DC, i nclud inc ch ri c nc d d to n ’crare c !’uL iii ncrc ii ablc f’ormnt — ; pp in roz’ rind conduct a phy iica1 in pcct ion (by boat, :hcze ! i’o; riaLc) of’ the Charles River, a]so inclwnr. pei onncl selected by 1DC. - Conduct a detailed evaluation of all pa tersue n the modeling effort and jointly with MDC develop the range of confidence for each. - Arrange for free access for the project participants to special experts where such are necessary for decision— making. — Conduct sensit .vity analyses of parameters as necessary by supplementing computer runs made during the EIS and provide copies to MDC. — At locations where it is jointly agreed that further field information Is required for decision—making, conduct field measurements. Such may include measurement of stream reaeration capacity. — Following development of...a final agreed upon model of the Charles River, conduct model runs of jointly agreed upon conditions needed for decision—making and provide copies to MDC. - Prepare and print a jointly agreed upon report on study findings. Metcalf & Eddy’s function in this effort will be to assist 2. ------- 1. .)C in this thy LiC tion s fo] lo.:s - 1 i’viC : the Charic ivcr d:ta ba5e filc cve1C and advi c flDC of’ os U)le needed o be fi) d. — 1 1L2c pJ tC in the physical jnapectjOfl cf the Charics ]Uvcr icr nurposes of aiding jn model p rarncter electiOi. — Anstht 1’ DC in evaluating the review of modcUng Cor; ntLitions and of modeling done to date. — . dvise DC on model changes that are neccs arY or that •:ill facilitate the review of’ results. — Assist MDC in the selection of’ a range of parameters for sehsitivity analysis. — Review results of sensitivity analyses and advise on final model adoption, including the conduct of’ discussiOr 5 with special consultants and participation in the development of special field measurements. — Assist MDC in the development and evaluation of alternatives and in the development of recommendations . — Conduct reviews of reports and attend meetings as requested by MDC. 114. Assessment of Existing Nut Island Treatment Plant Conditions — Compile and review existing data and studies on the plant conditions and operations. — Make field Investigations of physical features of the existing facilities including hydraulic and treatr ent capability, and equipment and structural work, as applicable. — Conduct detailed Investigations and, If necessary, field testing of the condition and adequacy of major equipment that is pertinent to the site selection process. ‘3 ------- cs•:on Jz_o868 L /5/7 9 MEMORANDUM FOR THE RECORD The following presents a more detailed explanation of the work tasks expected to be conducted by the EPA as part of the analytical investigation of the Charles River water quality. — Update the EIS data base on the Charles River studies especially w .th new information on wastewater discharges and recent field measurements. Prepare a file on that data base and provide a copy to MDC. This task involves the collection and analysis of previous data and reports related to the Charles River. Included would be data from physical and water quality surveys conducted 6y the MDWPC and others; data from treatment plant discharges and industrial discharges; data on river flows; data from previous water quality modeling efforts; and any other pertinent information related to .the river’s water quality. The data should be analyzed to identify any treads, either beneficial or adverse, in the rivers water quality that may be evident upon review of the data. The history of the level of treatment and discharge location for all point sources should be investigated. The extent and frequency of low flow conditions on the river should be analyzed. — Review modeling formulations especially considering the results of such an effort carried out on behalf of the Massachusetts Division of Water Pollution Control (MDWPC) and identify model changes that may be necessary. This task involves a thorough analysis of modeling formulations used in the computer simulation. An understanding of how the model uses the various input data should be developed. Recommendations would be made identifying model changes that may be necessary to properly represent the various processes occurring in the river. — Modify the program used by EPA as necessary and agreed upon with MDC, including changes needed to prepare output in a more usable format. This task involves the implementation of the needed changes identified in the previous task along with any format changes desired to enchance the readability of the computer output. ------- — Arrange for and conduct a physical Inspecticn (by bcat, where appropriate) of the Charles R!ver, also Including personnel selected by MDC. This task involves a physical inspectIon of sections of the river to develop a better understanding of the river’s characteristics. Possible limited spot checks might include cros , . , ctIon measurements,, velocity, measurements, depth jni urements, extent. of sediment deposits, and the collection of grab samples. A detailed field log would be maintaIned and any necessary changes to the various modeled river segments would be identified. — Conduct a detailed evaluation of all pararnèters used in the mode l ng effort and Jointly with MDC develop the range of confidence for each. This task involves a review of the state—of—the—art r lated to the various paramëtèrs used in water quality modeling. Included would be parameters related to such processes as BOD removal, nitrification, reaeration, sediment demand, and photosynthesis. Ar g _p,ç, confidence would be Identified for each parameter. — Arrange for free access for the project participants to special experts where such are necessary for decision-makIng. This task involves making arrangements for the MDC to have free access to technical experts in areas where this is needed, such as the areas of deoxygeriatlon and reaeration in river systems. — Conduct sensitivIty analyses of parameters as necessary by supplementing computer runs made during the EIS and provide copies to MDC. This task involves conducting computer simulations to determine the sensitivity of the results to the range of values identified previously for critical parameters. In this manner tj e parameters most a,ffecting the simulation results will be Identified. — At locations where it is JoIntly agreed that further field information Is required for decision-making, conduct field measurements. Such may include measurement of stream reaeratlon capacity. This task would involve making arrangements for the_conduct of special field measurements, where such have been identified as critical to the decision—making process due to the output from the previous tasks. MCTCA .F & CODY ------- — Following development of a final agreed upon model of the Charles IUver, conduct model runs of joIntly agreed upon cor.d tions needed for decision—making and provide copies to MDC. This task would Involve the conduct and analysis of computer simulations representative of conditions selected by the MDC. — Prepare and print a jointly agreed upon report on study findings. • This task would involve the preparation and printing of a report presenting the results of this Investigation as agreed upon with the MDC. Throughout the conduct of the tasks described above, the MDC and Metcalf & Eddy would be involved In the Investigation both directly In the technical analysis and functioning in a program guidance, review and decision—making role. Daniel W. Donahue DWD:dd 6 METCALF & EDO ------- Sa-.::’e : : _5 _: 3’T . :2 e: Z : a . a a a _ — • — a — •——. — 2 ._ — _. —‘ Consulting Engineers March 29, 1978 J—5 50 Ms. Libby Blank Director of Env ronmenta1 Planning Metropolitan District CommissIon 20 Somerset Street Boston, Massachusetts 02108 Dear Ms. Blank: Following our brief review of the materials submitted to you by Mr. Wallace Stickney, EPA, dated March 1, 1978, on Dissolved Oxygen Modeling, Charles RIver, Massachusetts , and our attendance with you at a meeting with EPA on Z arch 21, 1978, on the same subject, we felt it necessary to summarize our comments herew th. In general, the above—mentioned materials and meeting do not change the comments made in our Memorandum on the Review of Dissolved Oxygen Mode1in , Charles River, Massachusetts , sub- mItted to you on January 10, 1978. In order to be brief, we will only touch on the more important points to provide further clarification. Model Formulation Accuracy As mentioned before, we have not checked the correctness of the program. However, we do suggest checking, for example, the temperature correction formulation for the upstream reach inflow. AWT Performance Reliability and Deoxygenation Rates We suggest checking the performance capability of the Marlboro Easterly plant to achieve the S mg/L BOD 5 and 1 mg/L NH 3 —N. NEWYORK PALOALTO CHICAGO ------- xE. Libby 3 lank March 29, 1978 S n larly, we suggest checkIng thIs plant’s effluent character- istics to determine the approprIate deoxygenatlon rates for A effluents. For further references on the change in deoxygena Ion rates with increasing levels of treatment fcr plant effluents and receiving streams, we suggest reading Professor Schroepf r’s pIoneering work on the Mississippi River*, as well as recent wcrk by the Geological Survey on the Willamette River in Oregon**. Documentation of Assumptions and Handling of Dam Reaeration, Tine of Flow, etc . - Again we suggest that the sources of nfor nation be documented. For example, the sources of the data in Table 5 of the EPA Report need to be shown, to identify where such are from the BasIn Plan and where such are from other references. In our earlier memorandum we commented on some of the formulatior. used. Our concern was with the correct use of these and not with the answers they may produce. PhotosynthesIs and RespiratIon In developing the photosynthesis and respiration terms for water quality modeling, a set of selected K rates was used for the purpose of oxygen budgeting in the DItURV2 Program. Then a dIf- ferent set of K 2 values was used in the actual water quality modeling. This cannot be considered as a process leadIng to model calibration. Further, the photosynthesis/respiration information derived from the above calibration process was not used in the low flow sImulations. The input reflecting photosynthetic oxygen production was greatly reduced while the oxygen consumption due to respiration was held constant. Figure 6 of the EPA Report shows a curve labeled ALGPO = ALGRA. This represents a conditlon where photosynthesis and repiratlon are modeled to in effect zero each other. Such a condition is more favorable to the oxygen resources of a stream than can be expected at night, when the respiration load is not canceled. However, the curve as shown falls below the range of measured DO values over most of the Charles River. Since these measurements *G J. Schroepfer, N. L. Robins and R. H. Susag, “ReappraIsal of Deoxygenation Rates of Raw Sewage, Effluents and Receiving Waters”, Journal WPCF, Vol. 32, No. 11, November 1960. * R. A. Rickert, W. G. HInes and S. W. McKenzie, “Methodology for River — Quality Assessment with ApplicatIon to the Willamette River Basin”, Oregon, Geological Survey Circular 715—N, 1976. ------- Libby 3 lank Narch 29, 1978 Include nIghttime readings WhiCh are representatIve of river con- ditIons where there Is a respiratIon load but no photosynthesIs addition, calIbration should be adjusted to allow the curve to fall wIthin the range of field measurements; Reaeratlon Coefficients Undoubtedly the whole reaeration approach is a most thportant factor In thIs modeling effort. Again, one cannot use a different basis of reaeration in the development of photosynthesis and respiratIon budgeting then one would use In modeling the same data In the River. One cannot use the wrong formulation to represent darn reaeration IrrespectIve of the results. WIth respect to selecting a formulation for stream reaeratlon, as stated In EPA’s latest submittal, there is no one formula capable of adequately predicting reaeration capacity in any stream. Thls includes the Tsivouglu—Neal formulation as well as the O’Connor Dobbins formulation. The Tsivouglu—Neal formulation is an attempt at this. Covar’s paper (see EPA Memorandum, March 1, 1978 for reference) recommends a set of three equatIons, including the O’Connor—Dobblns formulation, for three conditions but does not recommend the use of the Tsivouglu—Neal formulation due to a ??conslderable scatter ifl the data.TT As an objectIon to the use of the O’Connor—Dobbins formulation (used by DWPC In the Charles River BasIn Plan), the EPA Memorandum, apparently using Covar’s paper as a basis, cites that the data used for its development were under conditions where velocities were greater than 0.1 feet per second —— a condition not occurring in the Charles River during low flows. Perusal of the Tsivouglu—NeaJ. data base, as It is published, did not show any data points with velocities less than 0.1 feet per second either. It should be pointed out that we do not necessarily subscribe to any of these formulas as being the most appropriate for the Charles River. Our feeling is that the impact of this parameter is sufficiently significant to warrant a sound basis for its determination. Impacts on Oxygen Resources Again, as modeled, the most significant impacts result from as- sumed data. On the basis of a limited review of the available data and without the ability to obtaIn computer runs we would have liked to see as input to our revlew, the following numbers can be only consIdered as crude approximations of impacts. ------- :•: . Li b:’ Blank :arch 29, 1975 Cause Impact on DO in rn /L Basis Sed nent oxygen demand 3 Rept. Fig. 15. Eli and Gil. Cases Phctosynthes s/ resp rat on 6 Rept. Fig. 16. D2 and E2. Cases Upstream plants Unknown MDC satellite plant 1.5 Rept. Fig. 12. El and B].].. Cases Nor.po nt sources Unknown Following the March 21st meeting, at which the last paragraph on Page 11 of EPA ’s March 1st memorandum was discussed, we reviewed the EPA computer run No. 368 which had been submitted as the basis for the conclusions in that paragraph. As stated, the purpose of the run was to test the significance of the oxygen demand from all of the treatment plants by reducing CBOD 5 to 1 mg/L and NEOD to 0. The run showed DO values significantly lower than those quoted n the paragraph. A spot check of the input data showed that the NBOD values had not been set to zero. A further check showed that the input data had been further changed by raising upstrean background water quality, by increasing K 2 In five segments, by decreasing K 2 in three segments, and by elImInating a small point source. Very truly yours, y f ekabs P. Vittands VIce Presldent JPV:jfj ------- Metcalf & Edd ,Inc . S aiiforC S ’ee Sos c assa: e’;s C1 i 617 523. 19O TWX 71 C 321 6355 Ca e Aoore s METE OD Boston / pr11 28, 1975 .r. John Elwood ._ J) E vIronnenta1 P1annir D1vis on Netropolitan District Cor IssIon 20 So erset Street Boston, ;Iassachusetts 02108 Dear r. Elwood: As you requested, we have reviewed fr. Polese’s nenorandu on the Charles River 1978 Survey. The memorandum Inplles that this year’s survey will resolve some of’ the problems encountered ir. the computer modeling of the river. AssumIng this to be one of r the goals of the sampling program, the fol1owIn com ents are made. 1• The sampling program should be conducted under conditions similar to those used In the modeling effort. That is, since the river modeling is for \ fi low flow conditions, the measurement program ‘ should be conducted during dry weather under low flow conuitlons. Also, the timing should be flexible so that the program can be rescheduled If sIgnIficant rainfall occurs prior to..planned program. 2. In order to obtain dependable results from the modeling effort, it Is essential to have all com- ponents sampled at the same time. Therefore, when the main stem is sampled, the point sources and at least the major tributaries, such as lane Brook, Stop River, and Sugar Brook, should also be sampled. Ne YOrA Palo Alto Chicago rC 5 . ------- r. John 1wood 2 r—-. i -‘ “2_ d1 3. Ulth regard to additional sampling stations, it could be desirable to establish a station somewhere between river mIle 70.3 and 66.1, where rnode1In of the 1973 data indicates no dissolved oxygen. Stations should also be established above and below jor point source discharges to aid in assessing their impact on the river’s water quality. (Eince no advanced plants are operating on the river, perhaps monitoring an existing advanced plant, such as liarlborough, would provide valuable data in determining the effects these plants will have on river water quality.) 4 Time of travel studies should be conducted in con— junction with the sampling program. 5. Supplemental flow gases should be installed and oper- ated before and during the sampling program. 6. Dam reaeration should be measured by measuring dis- solved oxygen concentrations immediately above and below the darns. 7. Sediment samples should be taken and analyzed to determine benthic demands. It is not necess y, however, that these samples be taken during the sampling program. For convenience, they could be taken either before or after the pro ran. 8. Ileasu.rements should be taken from which determinations can be made of instrearn carbonaceous decay rates, nitrogenous decay rates, and reaeration rates. 9. The sampling program should include both daytime and nighttime measurements to aid in assessing the diurnal variation in dissolved oxygen concentrations and to ascertain the level of alga]. photosynthesIs and respIration. 10. Groundwater samples should be analyzed to aid in determining the water quality characteristics of base flow under extreme low flow conditions. ------- :r. Job; ulwood April 28, 1978 In suzunary, we believe that a considerable effort is required to re3olve all the probleris that have been encountered in the PA :ater quality mocic-ling effort. Ue recorn end that the sai,ling pro rar be caref z1ly desIgned and carrIed out so that the data collected will be useful in further studies of the Charles I iver water quality. If you should have any questions regardIng these co en;s, please do not hesitate to contact us. Very truly yours, )•‘ , a: iel :. ona ue ? ojec: - 1 n er .‘ r . -, .Y j. 0 :t3 ------- O DU FOR THE RECORD BY: A. Lawrence Polese DATE: April 14, 1978 SUBJECT: Charles River 1978 Survey The Charles River 1978 Water Quality Survey has been scheduled by the Division for the week of July 17 — 21. The last intensive survey was conducted in 1973 in which both main stem and major tributaries to the Charles were included in the sampling runs. During March and April of this year personnel from the Division conducted two preliminary spring surveys, one on the main stein and one on the tributaries. The purpose of these was to collect background data and to investigate possible pollutant loads carried in runoff from snowmelc, and leechate resulting from high water tables. Results from chemical and bacteriological analysis are not yet available. This year’s survey will differ somewhat from the 1973 study. For modeling p o g the entire main stein (minus tributaries) will be sampled in one run, whereas in 1973 the run was divided into Upper and Lower Charles runs. This was done in order to keep the runs from being too time consuming i.e., seven hours. By postponing the tributary stations a few days one complete run on the Charles can be accomplished. This was not possible in 1973 with the Upper and Lower Charles arrange- ment. Again complete runs should make modeling both easier and more representative of actual river conditions. The sampling stations for the current year are identical to those used in 1973 (see The Charles River Part A, ! WPC 1973). Since tributaries are being sampled separately, a more comprehensive survey is allowed. A list of tributaries to be sapled is attached along with a list of main stem stations. The selection of sampling stations and time of survey is not yet final. Addition/deletion of stations will be considered to make modeling as accurate as possible. This memorandum is to provide interested parties with an idea of how the Division is handling this year’s survey. Coimnents and questions should be directed to Larry Polese at the Division’s Water Quality and Research Section, Westborough, MA (617—727—6983 Boston) or (366—9181, 9182 Westborough). ALP / ro Attachment cc: A. Akalainen L. Blank H. Shaughnessy J. Vittands 74 ------- CHARLES RIVER NAIN STEN STATIO CHO1 Dilla St., M.ilford CHO2 Cedar Swamp Pond Dam, Milford CHO3 Howard St., Milford CHO4 Mellen St., Hopedale CHO5 Hartford Ave., Bellingham CHOÔ Box Pond Darn, Bellingham CHO7 Rte. 126, Bellingham CHO8 Pond St., Franklin—Medway CHO9 Elm St., (Shaw St.), Franklin—Medway CH1O Bent St. (Walker St.), Medway CH11 River Rd., Norfolk CH12 Forest Rd. — Orchard St., Millis—Medfield CH13 Dover Rd. — West St., Millis—Medfield CH14 Rte. 27, Sherborn—Medfield CH15 Bridge St., Sherborn—Dover CHI6 South Natick Dam, Natick CH17 Central Ave. — Centre St., Needham—Dover CHI8 Chestnut St., Needharn—Dover CH19 Ames St., Dedham CH2O Kendrick St., Needham—Newton CH2 1 Elliot St., Needham—Newton CH22 Walnut St. (Wales St.), Wellesley—Newton CH23 Moody St., Waltham CH24 Watertown Dam, Watertown CHARLES RIVER TRIBUTARY STATIONS 1 Godfrey Brook — Depot Rd., Milford 2 Beaver Brook — Taunton St., Bellingham 3 Hopping Brook — Rte. 109, Bellingham 4 Chicken Brook — Rte. 109, Iledway 5 Sheppards Brook — Elm St., Franklin 6 Mine Brook a) Rte. 140, Franklin b) Near Rte. 495, Franklin c) Pond St., Franklin 7 Mill River — River Rd., Norfolk (CH11) 8 Stop River a) Pond St., Norfolk b) Winter St., Norfolk—Walpole c) Campbell St., Norfolk c) South St., Medfield 9 Sugar Brook — Of f Dover Rd., Millis 10 Vine Brook — Rt. 109, Medfield 11 Bogastow Brook — Rte. 115, Millis 12 Fuller Brook — Dover Rd., Wellesley 13 Waban Brook — Rte. 16, Wellesley 14 South Meadow Brook — At Charles River, Newton 15 Beaver Brook — River St., Waltham TOTAL STATIONS 19 74 ------- UN ED STATES ENV PONMENTAL PROTECTION A3E CY REGIC’ J F E’ NEDY FEDERAL BUILC!NG, BOS O . P.iAS .Cr USETTS c:: flarch 1, 1973 !s. Libby Blank Director of Environmental Planning ::etrapolitan District Commission 20 Somerset Street Boston, MA 02108 Dear Ms. Blank: Upon receipt of your January 11, 1978 letter containing your comments prepared by Metcalf and Eddy on the Draft Report —— “Dissolved Oxygen !ode1ing — Charles River, Massachusetts”, Mr. Allen Ikalainen reviewed the comments closely. He has prepared remarks concerning each point addressed by Metcalf and Eddy. I have enclosed a copy of Mr. Ikalainen’s remarks. It is evident that there are soie misunderstandings of what the report says. In particular, your comments concerning temperature correction for reaction rate con- stants which are temperature corrected, photosynthetic oxygen production and respiration rates used in the model calibration, nitrification rate constants in simulations at low flow and the discussion of dam reaeration reflect these misunderstandings. The attached remarks explain these points in detail. In addition to the specific misunderstandings mentioned above there are several items in your comments which deserve further attention. For instance, your comments on variations in river flow during the time of travel survey in 1973 and differences in river flow between the September 1973 calibration and projected flows in the year 2000 are discussed in the attached remarks. Also, your comments on sediment oxygen demand and the magnitude of their effect are considered in some detail. Your comment on in—stream reaeration raises Tsivoglou and Neal’s caution, concerning use of their method in impoundments. However, they raise the r.ote of caution because the procedure may predict reaeration rates in e4cess of what they may actually be impoundments. The opposite is mdi— c ited by the language of your comment. Again, the attached remarks explain these points in detail. 1 ------- Your reco .endatiCflS raise an important consideration in understanding arid interpreting mode1in results. Sensitivity analyses should be done_to detertirie which modeling parameters most greatly affect the results, in this case, predicted river dissolved oxygen levels. As mentioned in the attached renarks concerning your conclusions and recommendations, sensitivity tests on sediment oxygen demand, photosynthetic oxygen production and in—stream nitrification rates are included within the report. We also point out subsequent to the modeling report and receipt of your comments, sensi- tivity tests have been done on deoxygenation rates of plant discharges, bioche ical oxygen deriand loads in runoff, treatment plant loadings and in—stream reaeration. These sensitivity tests are not rigorous and have not been done to determine the effect on results from varying percent changes in model input, but have been done over wide ranges to determine the most sensitive input parameters in terms of their effect on results. It is evident that in order in—stream reaeration, treatment plant loadin s, and sediment oxygen demand Although not yet tested, time of flow is undoubtedly an important para ecer also. -. Ii-. your recommendations, you have suggested confidence testing of each “factor”. In this case this cannot be done because the field data collected by the Division of Water Pollution Control in 1973, 1972, and other data developed by EPA does not contain any duplicate samples or replicate analyses or is not available in its original form. We agree that further investigation of assumed values or field sampling could provide more information to us. However, we question if the time and expense involved in time of travel measurement, sediment oxygen de: nd measurement and tracer measurement of reaeration will provide information which will change our understanding of the river’s dissolved oxygen resources. We still believe there is a major doubt that the Charles River can assimilate the projected waste loads for the year 2000, after advanced treatment, and main- rain D.0. levels of 5.0. mg/i consistently during the suter_ g Therefore, we question the advisability of discharging any more waste— loads_to the river than is absolutely necessar . I:r. Alan Cooperman of the Division of Water Pollution Control informed us that he is planning a water quality survey of the Charles River next sumner and that he would like all parties involved in this modeling to decide upon any specific field measurements which we need to further calibrate and verify the model. I suggest that once you review the attached remarks we meet with Mr. Cooperman to discuss the need for additional field measurements. ------- Las:ly, t several points in r. Ikalainen’s renar .s h h 1n i n:ed t - :t he would review and consider any information th3t you or Netcaif ar 1 d Eddy might have to further elaborate on the points of discussion concerning deo ygenation rates of wastewatcr after advanced treatment, in—scream reaeration predictive methods and in—stream deoxygenation rates for streams receiving effluents after advanced treatment. In this regard please contact Mr. Ikalainen directly. Sincerely, wallace E. Stickney, P.E. Director Environmental and Economic Impact Office Enclosures cc: Mr. Alan Cooperman (MDWPC) ------- Car en: on ‘cmorandum on the Revicw of Dissolved O vce Ddeli . Charles River, 1 ssacrws cts ” (Co— -.ents refer to paragraphs in sequence—first to last of the above lenorandum) Paragraph 1. - On February 9 and 11, 1977 I met with Mr. Alan Cooper an, TC at Wes:boro, MA. We discussed modeling of the Charles River for purposes of analyzing the effect of a proposed C Satellite treatrent plant d charge on dissolved oxygen. The EPA — Environmental Impact Office and their consultants were interested in the effects of the proposed discharge if the discharge points were located at points other than just downstream of the Cochrane Darn. This interest developed because of difficulty in finding a site for the satellite plant near the E - 1A recomz’ ended location. Mr. CooperTnan explained that Mr. John Erdmann had modeled the June and September, 1973 water quality conditions with the STREAM and DICL’RV2 models, but h4d not developed a low flow simulation with the STREA.M model prior to his leaving the ? mWPC. Mr. Cooperman and I agreed that low flow conditions should be simulated with the STREAM model to analyze the effect of alternative satellite plant discharge locations. The Division did not have the resources at that time to develop the low flow model. However, r. Cooper an provided to me card decks of Mr. Erdmann’s September 1973 simulation, the DICURV2 program and its input data for June and Septenber 1c73, a memorandum on the use and development of DICURV2 and computer printout of the September 1973 simulation of the Charles River with the STREAM model. He provided this information so that I might develop a low flow simulation. Mr. Erdrnann and Mr. Coope an were planning on using the STREAM model and DICURV2 to determine wasteload allocations under drought flow conditions for inclusion in the Charles River 1976 Water Quality Management Plan. (Ref: Part C, Water Quality Analysis, the Charles River and Charles River Basin 1973, 1976 Page 65.) However, Mr. Erdmann’s leaving precluded this. In my report I have referenced this prior work by Mr. Erd ann in the ACK C LEDGENI? T and on page 17 — last paragraph. Also in the model calibration procedures discussed on pages 13—32 of my report, Mr. Erdmann’s and thus the Division’s work is referenced repeatedly although each parameter is not specifically indicated as being developed by Mr. Erdmann. I have modified Mr. Erdmann’s model calibration input data for the September 1973 simulation in two major areas, in—stream reaeration and sediment oxygen demand. Reasons for and the details of these modifications will be discussed under co ents on paragraphs relating to those subjects, specifically. ------- 2. Th D ’C has reviewed the report in dotail. Frt L r re tr ;: s: - cff (War r Quallcy Section) has scheduled a water qual:tv sLr ey for t. Ch rlcs River Basin for the su -rier of 1976. The purpose of the survey is to e 3te the past water quality info ation and to provide current infor a: fcr development of a Phase 2—Water Quality Iana emenc Plan. The Phaze 2 Plan is intended to review and update wasteload allocations for point sourc and to develop wasceload allocations for new point sources and non—point sources. The Plan is scheduled for completion in early C.Y. 1979 and s being developed in coordination with MAPC and EPA. paragraph 2. The i pecus for this modeling did come from the EIS preparation. 1 o aver, under the requirements of the Federal Water Pollution Control Act facilities planning cannot be funded by EPA unless there is an EPA approved basin plan among other require ts. 3asin plans which apply to streams and rivers which are designated as water qulity lir.i cannot be approved by EPA unless wasteload allocations for point source discharges will meet water quality standards as set by the states and approved by EPA. Therefore, this modeling of the Charles which is considering the current approved wasteload allocations is part of the continuing water quality managenent process including facilities planning and wasteload allocation. It is also part of the EIS preparation which reviews the water quality impact of facilities planned to meet waseeload alloca: ions. Paragraph 3. Recommendation 1 c. is based upon the pure logic that treatment plants which would provide effluent quality as seems necessary according to this analysis would be very costly to construct, operate and maintain. Also, it is y understanding that there are very few large municipal treatment plants operating at levels producing effluents of S r’g/i CBOD 5 and zero Wd 3 —N and therefore one can only question the reliability of a plant to do so. One of the reasons that an EIS is in preparation is because a satellite plant will have a significant environmental im3art. Recommendation 3 does not recommend that sewer service areas be limited. It recommends in fact that “the water pollution planning process for the Charles River should include, as a possible control for future wastewater from MILFORD,..., the limiting of sewer service area and wastewater loadings,...” Conclusion 4 says leaching from solid waste is known to occur in the Charles River. This statement is based upon Part D, Water Quality Management Plan — WPC 1976 — Charles River Basin, pages 17, 24. Paragraph 4. If the MDC and Metcalf and Eddy will recall the meeting at which they w are present in Westboro, MA at the Division Offices on May 27, 1977. ------- t t : reetin; Mr. Cooper an exrlained to all present that t ir con :. —:, cs :r:c . r.alysis, Inc., wa revie in; the nodel f rru1a:ior.. As of t writing F_Al has not co lc:ed their a a1vsis, but recent conversa:ion chem indica:es that the model is corrcct in the stead :—state form. constants input to the model in this analysis are tcrperature corrected by the model as e: plained on page 16. Reaeration rates have beer’. adjusce upward outside of the model by the temperature correcclon factor specified by Tsivog!ou and aa1 and have also been temperature corrected (an upward adjus:men:) within the model. This is explained in footnote (1) on page 30 of the report. - - — In the year 2000 low flow simulations the Mother Brook diversior. was inadvertently located at the downstream end of Reach 26 when it shou1 be located at the head end of the reach. A low flow simulation has been run with the diversion located at the head end of Reach 26. The difference in downstream D.0. conditions as a result of this error is less than 0.1 mg/i for the case tested. Paragraph 5. The assumptions made in the model calibration and the low flow —odel development are stated in the report. Also, many of the assumptions are the sate as those in the modeling portion of the approved Water Quality Management Plan for the Charles — Part D — WPC 1976. Paragraph 6. If one looks closely at the time of travel study data from April — May 1973 it is seen that river reaches between river mile 76.5—75.5 and 72.0—70.3 were surveyed on May 8. All of the remaining main stem reaches were surveyed between April 30 and May 4, inclusive. Flow variations at the Charles River Village, Wellesley and Waltham USGS gaging stations were 22 , ll and l3 of the minimum daily flow, respectively for the period April 30 to Nay 4, inclusive. Again, if one looks closely, the 2000 projected low flow with an C satellite plant is seen to be about 7 times less than the average flows during the time of travel study. This is based upon the projected and measured flows at the three USGS gaging stations. The time of travel—flow relationships used in the Septerrber 1973 and low—flow simulations are the same as those used in the modeling of Part D— Water Quality Management Plan, Charles River, 1976 C Table VI—3 and are essentially the sane as those in Appendix E of Charles River Water Ou 1itv Study EPA—? egion I, September 1971, except as noted in Table VI—3. As explained in the Report on page 18 the work of Leopold and Haddock is the basis for determining the tine of travel—flow relationships. This is a widely accepted procedure for predicting river velocity at varying flows. ------- 4. A roze in the co: ents Leopold arid 1addock d ve1oped the proced’jre fron d :a collected on “freely—flowing streams withcut da-s’. If this s in fact the case, then it is very possible that the relationship may predict v 1ocities chat are too high in the inpounded reacnes. The relationship sonawhat underpredicts time of travel as reasured in April— :!av 1973. (See Attached Table 1) Additional testing of the relationship at flows approaching those of the projected low flow with a satellite plant would be us fu1. However it will require a great deal of luck to schedui.e a tine of travel survey to coincide with low flows bing stead:: throughaut the river and approaching the projected lowflows. - .1 presune Metcalf and Eddy’s reference to “hydraulic efficiency” of impoundments is an attempt to explain that large, recent man—made impound— ments nay retain the original river cross section along the bottom surface profile and that at extremely low flows the river will flow within its original channel causing lower times of flow. I don’t believe this is the case in the Charles River because I observed the river on August 16, 1977 when the daily average flow at the Charles River Village Gaging station was 58cfs or 28 less than the projected seven—day 10 year low flow as shown in Table 8 of my report. On that day the impoundments behind the So. Natick Dan and Cc hrane Dam were fully impounded and velocity of flow was extremely slow. Floating algae were barely distinguishable as moving downstream. Further, I don’t believe the concept of “hydraulic efficiency” is applicable to rivers flowing through wetlands and lowlands, as does the Charles, with impoundments formed by run of the river dams. Paragraph 7. The September 1973 calibration includes pollutant loadings from Sugar Brook as measured on 9/4/73. The ?Iillis wastewacer treatment plant discharges to Sugar Brook. In this particular case the model includes the loading from Sugar Brook which carries the loads from Millis and Cott Corp. via the Millis treatment plant. I have not reviewed and compared the operating procedures in 1973 and 1974. Perhaps Mr. Erdmann did in preparing the model for calibration. Mr. Erdmann’s conclusion number 2 from Part C Water Quality Analysis, 1973—1976, Charles River and Charles River Basin points out that non—point sources ‘undoubtedly degrade the quality of many more miles of stream than do the waste discharges and the sewer overflows, but in more moderate degree”. Paragraph 8. The second sentence in this paragraph partially reiterates a point discussed at length in the report on page 36 and 38. Non—point sources contribute much more CBOD 5 to the river than do point sources. The calibration simulation under predicts CBOD 5 loads in the river. For example, the total river CBOD 5 mass loading in pounds per day for the surface runoff, as assumed, is 83 percent of the total CBOD 5 mass loading from tributaries and point sources. Yet the CBOD 5 profile as simulated and shown in Figure 8 is consistently lower than the rreasured CBOD 5 in 82 ------- 5. : e r:ve: for th river reaches below river rulc 70. Figure 9 further C ?USiZCS t C magnitude of non—point source 1oad ngs to the river as cCn? aQ to point source loadings. The last sentence of paragraph S is not very meaningful and grossly misrepresents the benthal oxygen demand used in the calibration. If one looks clo e1y at Table 5 and computes the sediment demand values in te s of mg/i—day it is seen that the maximum demand rate is 3.28 mg/i—day only in Reach 2. Further ’ore, of the remaining reaches, three have sed nent d ands of 1.66 to 1.0 and the last 18 have sediment de ands of 0.80 to 0.15. m /l—day. The discussion of sediment oxygen demand on page 29 of the report explains and justifies the sediment demand inclusion in the calibration modeling. The D.0. simulation of September 4, 1973 conditions as shown in Figure IV—5, Part C, Water Quality Analysis, Charles River and Charles River Basin apparently includes a sediment oxygen demand of 2.5 gm/m 2 /day. This rate seems much too high, but may result in a predicted profile close t3 the mean of measured values if reacration rates are also too high. Paragraph 9. The photosynthesis discussion in this paragraph is totally rong . The calibration simulations as shown in Figures 6 and 7 represent average photosynthetic oxygen production and respiration and average photosynthetic oxygen production set equal to average photosynthetic respiration. This is e:.:plainad in detail on page 32 of the report and is indicated on Figure 6. Thus photosynthesis is represented only as having a net D.C. production over a day or having no net D.O. production. No simulations are presented in the report with “zero respiration”. The discussion presented in Paragraph 9 of weather conditions :s no: a complete representation of river flow conditions on September 4, 5 and 6, 1973. The river system car.not be viewed as simplisticly as in the comments. For example, the streanflow data presented in Table 1 of the ccm ents indicates that daily average river flows at Charles River V llaga were higher by 31 percent on September 4, 1973 than on September 6, 1973. However, if we look at USGS recorded river flows on those days at :el1esley and Waltham we find that river flows were 15 percent higher and l7 lower, respectively on September 4 and September 6. The cor.Irents fail to present this further information which indicates that higher river flows resulting from rainfall in the upper Charles Basin cannot necessarily be associated with higher D.O. conditions during daylight hours. In addition, the comment fails to point out or rccogni:e that the higher DO’s referred to on page 36 of the report occurred predominantly during daylight hours. Looking at the data further in Appendix B the higher DO’s on September 4 occurred as peaks in diurnal D.0. variations ------- 6. cn.th r day, while diu al variations wore significantly lower on Se zcmber 6. This bears out the conclusion in p3ra;raph 5 of page 36 in the re art that photos T.:hetic D.C. pro ucticn on Septenber 4 exceeded that on September 6. This conclusion is also supported by the observation that at all but one location peak photosynthetic oxygen production rates, as determined by the DICIRV2 analysis of John Erdnann, occurred on September 4, 1973. Lastly, as shown in Figure 8 and as discussed in the second and third paragraphs on page 38 runoff in the lower reaches of the Charles may contain si nifjcant CBOD 5 which would offset its dilution potential, even though the mpjority of D.O. demand effect of the runoff BOD would not be exerted until some days later. Table 1 of the comments contains two errors. First, there is no rainfall recorded on September 7, 1973 at the Boston WSO location. The Table indicates .44 inches as being recorded on that day. Second, the Data Sourac 1 as listed should be dated September 1973, not January 1973. Paragraph 10 — “Biochemical Deoxygenation Rates” The background loadings as input to the September 1973 calibration siulation and the 2000 low flow simulation are about 5 pounds per day of CBOD . The concentrations of ultimate and 5—day carbonaceous biochemical oxygen emand, respectively are 10.6 and 4.2 mg/i. This total mass loading is input to the river only at r.m.76.5 and is based upon the CBOD 5 loadings measured at r.m.76.5 in September, 1973. This is a natural background loading and there is no information or implementation plan to indicate this loading will change by 2000. As stated on page 43 of the report the deoxygenation rate for the treatment plant loadings is a normal rate for biochemical oxidation. If Metcalf and Eddy and/or the C has data available on deoxygenation rates for advanced treatment plants I would like to review the data for further consideration of the rate constants. It should be noted, however, that the rate constant within the range of .1 to .4 will not affect the results of the modeling analysis to a significant degree. Copies of simulations pointing this Out are attached. I see no justification for decreasing K 2 rates in the river between 1973 and 2000. In 1973 the river’s water’ bality was predominantly affected by non—point sources, in particular below r.m.40. As stated in Mr. Erdmann’s conclusions as referenced on pages 11—12 and as discussed on page 38 of the report non—point sources affect the D.0. balance in the Charles River over many more miles of river than do point sources but to a zore moderate degree and BOD loads in the river are attributable to algal mass and or ROD in runoff with D.O. increasing as BOD increases. ------- 7. dso. ac they are indicated on page 43 in Tab1 7 th trca i rates (5ioc ie ical reaction rates) range between .09—.23. These ar not high races ior streams of low to moderate pollution _I have seen and c:: erienced. Furthermore, if one does sore simple calcula:ions, it car. b seen from the data in Table 8 that the Charles River at low flow in 2000 would consist of between 50 and 80 percent treatment plant effluent with the effluent containing 5.0 mg/i CBOD 5 . This level of CBOD 5 is not analgous with high quality water or clear rivers, in my mind. Therefore, lower deo: .:ygenacion rates in the river are not justifiable. Par graph 11 — Nitrogenous Oxidation Rate The discussion in this paragraph is not meaningful to the analysis of the report because the discussion in item 4 on page 56 under Cases A, B, E, C and H simulations and the D.0. profiles of figure 15 indicate that the simulation results are not very sensitive to nitrification rate constants of 0.6—0.2. With regard to the com:nenc concerning “certain forms of algae” aking “great inroads upon the aimnonia supply”. Such a phenomenon has not be.en studied in the Charles River and is beyond the scope of this analysis. Also, as will be considered under the discussion of Paragraph 12 it is probably not sound thinking from a water qu3lity protection standpoint to count on highly variable algal populations, which are one of the Charles’ water quality problems, to mitigate the effects of oxidation of amnonia. Lastly, I don’t believe water quality simulation has advanced far enough in the understanding of algal and plant growth and death dynamics so that anyone could definitively quantify algal consumption of ammonia. Paragraph 12 The discussion in this paragraph has not mentioned at all the material presented in the report on page 28 which considers both the Quirk and Eder and Mastropietro dam reaeration prediction procedures. To reiterate that material, a comparative analysis of D.O. values downstream of each dam on the Charles as predicted by the two procedures and cor pared to measured values indicated little difference. At low flQw, with an MDC Satellite plant located downstream of the Cochrane Dam, the Mastropietro procedure gave significantly higher ( 1.0 mg/i), DO’s due to dam reaeration at three dams, slightly higher DO’s (.2—.6 mg.i) at six dams, equal DO’s at one dam, and lower DO’s (up to 0.6 mg/i) at four dams. Here again there appears to be less than significant difference between the two procedures as applied in this B5 ------- S. analV5iS. Fbwever, the r.odel will he odified to pr d:cr P.O. by as:rop1etro procedure and the impact of the change evaluated ca se thc NaszropietrO procedure is more logical and was developed from mp .: ca1 analysis of measured dam reaeratiori. Paragraph 13 — Stream Rcaeration K, The first paragraph of this comment has taken the work of Tsivoglou and Neal out of context giving the authors’ reco ’a endations an incorrect interpretation. Conclusion number 15 in the article referenced in the re;ort says in full: “15. Certain limitations of the foregoing predictive trodels should be emphasized, notably those that relate to scream segments in which rnixiria is poor. Thus, although the pools that occur as the result of natural topography are incorporated in the results sut _ arized here, the predictive models have not. been derived for, and do not apply to, major man—made impoundments. In general, very small slopes and small rates of energy dissipation imply less turbulence and poor mixing and, consequently, relatively low values for the escape coefficient C.” As can be seen by observing the relationship as given on page 28 of the report, a low escape coefficient results in a low K, value. Thus the relationship may be predicting K2 values which are too high for the long impounded reaches of the Charles. With regard to the second comment on stream reaeration it is useful to look at the facts of how and when K 2 s were predicted by the WPC in Part D — Water Quality Management Plan — 1976 and Part C — Water Quality Analysis — the Charles River and Charles River Basin. Page 71, Part D, indicates that the equation of O’Connor and Dobbirts developed for channels having isotropic turbulence was used with the relationship (referenced to EPA) for a minimum These were applied such that the higher K 2 yielded by either method was used in the modeling in this Basin Plan. Tables VI—5 and VI—6 indicate which K values were adjusted upward to a minimum value of 2.0/depth. If we first look at the O’Connor Dobbins relationship as described by Covar (1976) and Rinard (1976) we see that it was developed and tested on streams in which velocities ranged from 0.2 to 4.0 feet/sec and depths from 2 to over 30 feet. Table VI—6 showsthat velocities in 25 of the 33 reaches are between .17 and .001 ft/sec and 18 of those 25 have velocities less than 0.1 ft/see. Also, if we look at the depths in Table VI—6 we see that most are near the lower limit of the range of depths over which the O’Connor—Dobbins relationship was developed and tested. a’ ------- 0 xe:::, 1oo ing at the EPA relationship (dev 1oped by Hydro;ci nce unier con:ract to Mitre Corp. and EPA) in Appendix A of S fiuied ‘ath > :ndelinz , 1971, we see that the reference says chat the reacraciori race :<7 is equal to a transfer,coefficient K 2 divided by the average dep:h. “In the lover range, a minimum value in the order of 2 feet per day is an appr ximace limit” for the transfer coefficient. Thus = 2.0 ft/day is the minimum reaerat ion coefficient predictable by this method. h There are two major deficiencies in this relationship. First, it is not logical that all streams of the same depth have the same reaeration chracter stics. Second, the more recent work of Tsivoglou in icaces ch3t reacration is not directly related to depth, but is only influenced by depth as it is related to crcss—sectional area and time of flow for a particular scream geometry. Now, if we look at reaeration rate coefficients as developed.iri Part C — Water Quality Analysis Charles River 1973, 1976, we see on page 25 that the estimated values of 2 on 9/4 and 9/6 are considerably lower than those of Table VI—6, Part D in sixteen of the 33 model reaches. As computed in Part D the 2 values in sixteen river reaches are higher when river flows are lower, when velocities are lower and when depths are lower than in September 1973. This emphasizes inconsistencies of the O’Connor— Dobbins relationship and the EPA relationship in reaeration prediction. The last part of the Stream Reaeration comment suggests that “alternative methods of computing 2 which have been developed for conditions more similar to the Charles River should be investigated as part of a sensitivity analysis.” I agree that methods of computing ½ which have been developed for depths, velocities and flows similar to those of the Charles River should be used in modeling the Charles. This is precisely why the Tsivoglou—Neal relationship was used. Covar (1976) and Rinard (1976) have examined the conditions under which relationships by O’Connor—Dobbins, Churchhill, Owens Thackston and Krankel, and Tsivoglou and a1lace were developed. Their work reveals that none of these more prominent relationships were developed for velocities less than about .2 feet/sec. Tsivoglou and Neal have tested, in their Energy Dissipation ?Iodel paper, the accuracy of the predictive r.odels of O’Connor—Dobbins, Churchhi].l, Langbein—Durum, Thackston—Krenkel and Owens by comparing predicted K 2 ’s with K 2 ’s measured by tracer studies. “None of the models tested proved capable of predicting reaeration capacity within acceptable limits of error.” B’?- ------- 10. I would be happy to review any predictive procedures for uh ,ch e: alr an Eddy and the ‘DC have information describir.g the r develop— nenc under velocity conditions sinilar to those of the Charles River and based U O actual tr3cer ne3sur_:. :f r 3eration. Para;raph 14 — Photosynthetic 0>:ygen Production and Respiration As described in the report on pages 31 and 3 photosynthetic oxygen production and respiration rates used in the September 1973 calibration simu1at on are those developed by John Erdmann utilizing his DICURV2 model. Thus, the K 2 1 s used in deterrtining the gross rate of photosynthetic ox; gen production via DICURV2 are those estimated by Mr. Erdnann and reported by the Division in Part C. r— K 2 1 s as predicted by the Tsivoglou—Neal relationship were not used ‘with DICURV2 to give new photosynthetic oxygen production rates for incorporation in the calibration simulations of the report because there was no purpose to do so. It would have the effect of giving higher oxYgen roduction rates which would raise the entire solid line profile in Figures 6 and 7 of the report. This would indicate that the STREAN model with these higher photosynthetic oxygen production rates more closely predicts axiium D.0. as measured on September 4—6, 1973 than it does mean or minimum D.O. as measured. ;ith regard to the comment concerning “future projected conditior.s”, there again is evident an incomplete review of the report. Page 57 last paragraph describes a low flow simulation in which the peak photosynthetic oxygen production rates are incorporated. This sinulation as shown in Figure 16 indicates that photosynthesis can cause near saturation D.O. conditions throughout the river. However, the discussion points out that this source of oxygen “occurs only during periods of sunlight, is not reliable and requires abundant algal populations to sustain it”. In this case, as in the case of algae utilizing ammonia thereby lessening oxygen consumption in oxidation of ammonia in the river, a water quality problem (high algal populations) should not be considered as a reliable oxygen resource to the river. Paragraph 15 — Conclusions and Recor nendacions As explained in the previous comments the major differences between John Erdnann’s September 1973 simulations and those of this report are in reaeracion rates and sediment oxygen demand rates. D.0. simulation results in the report show a somewhat higher D.0. profile for the September conditions than do Mr. Erdmann’s (See Attached Figure IV—5 from Part C— I PC, as modified) I believe that the work in the report properly represents the oxygen resources of the Charles River whether or not it is “unfavorable” to planning for utilization of the river for wastewater assimilation after advanced treatment such that some eighty percent of the river will be wascewacer during low flow conditions. ------- 1 —MOTIIER UK. OIVEflSIOfl 1 —SJW.MILL 01<. I r t .ICIIDQ’.’, L I 5IOPJY L J 1 —UCAVFfl T (‘2) (? i( t) •‘) ‘ ) DISSOLVED OXYGEN on SEPTEMEi [ R 1, V . CHARLES RIVER C rn CM z w (9 >- >< 0 0 IL l > -J 0 (I) U) a RIVER MILES sampling itations ------- 11. ? :es 55—57 of zh rc?3rt ex:i3ifl why alternative st ac r 1oa :- : an aiter iacive river c dt:ions were si:iulated. If ercalf a Ed nd : e :- jc will recall a :ing with the PC and EPA at as:b r:’, . c .;u; sz 10. 1977, it was c;reed at that time that year 2000 low flo : sinulations would include alternative wascewacer 1oad n and r:ver co d z:c-. -. slmula :iOns. The scor:ng systern was developed to evaluate the relative differencc between alternative simulations and was applied uniformly to all low flow simulations. The following comments relate specifically to the four reco iendations onthe last page of the iemorandum. The low flow simulations have been tested for their sensitivity both within the work which is described in the draft modeling report and in continuing modeling subsequent to completion of the draft report. First , within the report simulation Cases A B, and E demonstrate the effects of varying the nitrification rate constant from 0.6 to 0.2 day —1. Figure 15 on page 61 and Table 12 indicate that the simulated D.O. profile is not vety sensitive to varying the nitri.Eication race constant from 0.6 to 0.2 day . (Cases All and Eli). Simulation Cases G and H demonstrate the effects of the sediment oxygen demand. Figure 15 and Table 12 point out that even with zero sediment oxygen demand a D.O. level of 5.0 mg/i cannot be maintained throughout the river. Simulation Case D demonstrates the effect of having a net D.0. production due to photosynthesis at the rates of September 4, 1973. This is discussed on page 57, last paragr: -. Second , since completion of the draft report additional sensitivity test simulations have been run. Deoxygenation rates of treatment plant discharges (Kjp) were set at 0.4 in the report; rates of 0.2 and 0.1 have been tested with conditions of Case E simulations as defined in the re ort. These lower deo: ygenation rates yield a higher ultimate or initial CRUD •thus producing significantly lower D.0. profiles than with a rate of 0.4. This is sho in the attached printouts of the low flow simulations. The sensitivity of the simulated D.0. profile to CBOD 5 loads in the uniform distributed flow was tested under Case E conditions by reducing the CBOD 5 loads to 1.0 mg/i in all reaches. This resulted in no appreciable change in the D.O. profile as indicated in the attached printout. In order to test the significance of the oxygen demand of the treatment plant loadings a simulation was run with CBOD 5 loadings at 1.0 mg/i and with N3OD loadings at zer This resulted in a D.0. profile which reached minimum values for D.O. of 3.5 mg/i behind the So. Natick Dam, 3.7 mg/i behind the Cochrane Dam and 4.9 mg/i behind the Silk Mill Dam. (See enclosed printout). This points out chat the plant loads are a significant oxygen denianding source. ------- 1, :: 1t:Dn rates were duubled as input to E s 1it1c ns t3 test th :r se sitivi:y. D.0. profiles resultinS fron this reveal :ha: reaerati is a major deteri inant of D.O. levels in the Charles River. H ’wever. even with doublthg of the rates predicted by tr.e Ts voglou— ai -ethod, there re 3ins long stretches of river with D.0. levels very mUL below 5.0 r ;/l. (See enclosed printout). Comi ent Prepared By Allen J. Ikalainen ------- TA5LE I Tthe of Travel C 1ibratiort Char1 s River April 30 to May 4, 1973 FL0 ME?.SLR 1ENT RIVER FLO J MEASUR.ED2J SI 1ULATED2J LOCATION cfs TI 1E OF TIME OF •(USGS GAGE) TRAVEL, hours TRAVEL, hours C . LES RIVER VILLAGE—r.z . 34.3 545 129 113 :.aT:- I—r.m. 18.3 463 164 145 E..LESLEY—r.i. 12.0 453 184 163 it Average of mean daily flows for 4/30 through 5/4, 1973. Tioe of travel between r.m. 76.5 and gaging stations. ------- R f e r en cc S Cov r, A.?.; “Se1ectin the Proper Reaeration Coefficient for Use in 1 ter Ou 1ity Models’; Proceedir.;s of the Conference on Envircn en:al del g and Sit u1ation — April 19—20, 1976, Cincinnati, Ohio; EPA 603/9—76—016. Rinard, I.H.; HCT DOSAC. River Oualitv Simulation Model, User’s Manual ; Falcon Computer Technologies, Inc., New York; Janua:y, 1976. 13 ------- L TIC CF S SITIVITY TEST SL iL TIO S The besic si J. tton upcn ..hlch the tcsts ere made is Identical to :L t of Case E conditions as described in the report (page 5l-Ta ie io) Inthis case all plants era disc rgin at 5.0 /i CBOD 5 and 1.0 r..;/1 Sedizent oxy;cn de nd is included as in the Sept. 1973 calibratlcn sir. .atIoo and in-stream nltrification rates are 0.20 day 1 (bese e). JC ;o. SSITI Tf TEST 05 CLOD loacinj in ifcr 21. .flCf Is 1.0 n;/l. 356 K 1 of plant wastes is 0.20 day (base e). of plant wastes is 0.10 day 1 (base e). 3 J 1l plant loadin&s to the river are 1.0 ii only. 353 In-stream reaeretjcn rates are doubled in all reaches. ------- • ‘ ‘• r ’ —— .— . __fl I. DIS LVED o:i GEN iODELING C: A LES RIVER, r .A SACH JSETTS A significant part of the matertal presented in the report was developed by the Commonwealth or Massachusetts DivIsion of Water Pollution Control (DW?C) as part of Its Charles River Eas n Water uality ianagement Plan. Some of It was acknowledged explIcItly an some was not. It would serve the Commonwealth and the readers if he material that was taken from the DWPC work were referenced ex- plicitly. On the other han , the departures’ from the 3asln Plan and the basis for them should also be Identified because the asIn Plan is presently the approved document for pollutIon contrcl and waste load allocations in the Charles River BasIn. Therefore, any changes ust be explicitly shown so that the Plan can be amended accordIngly where such changes are adopted. The report Preface identifIes the purpose of the report as beIng “part of the wasteload allocatIon, facilItIes plannIng and en- vironmental impact assessment procedures underway” in the Eastern : :assachusetts MetropolItan Area (ET &k). However, wasteload alloca— tlcn Is the responsIbIlity of the DWPC through Its basin plannIng process for which a resulting approved basin plan exists for the Charles River Basin. FacilItIes plannIng wIth its envlronnental impact assessment, on the other hand, Is the responslblllty of the C and the E! 1A municipalities. In the case of TWC, thIs process is not beIng carried out at this tIme due to the prerequIsIte EIS being prepared by the EPA. The document under review here Is a part of the EIS and not any of the above. The report Conclusions and Recommendation do not follow the data base reported upon ln dIscussIng treatment relIabIlity and economic and environmental impact costs. These are not addressed In the report itself. As an example, a recommendaticn is made to llmit future service areas without an analysIs of alternatives or ccnsequences, yet a conclusion is also made that septIc leaching oc- curs Into the Charles RIver. The following review has not included a check of the model- ling formulation and the input data base whIch should be made. As examples, some of the rate constants used In the mcdel are tempera- ture corrected while others are not, and the Mother 3rook DIversion Is Incorrectly located in the runs representing projected conditIons whereas It is correctly located for callbratlon runs. In evaluating the calibratIon effcr:s and flnd!rigs, it nust be understood that hydrologIc condItions were quite varIable durIng t .e calIbration erIod, that data fcr discharges used In calibration are for conditions one year later than the stream water qualIty survey ------- sed, and : -.at a si car.; component of the input da:a baze used ‘or cal!bra:±cn Is assumed. During the water qualIty survey period used for calibration, stream flows were ten times those of the low flow period. During this time, the average daily flows varIed by more than thIrty percent as a result of signIficant upstream raInfall that occurred just prlcr to the survey period. The time of flow in various parts of the river Is a significant modelIng parameter and, in thIs case, it was devel- oped from relatIonships formulated for freely flowIng streams wi:hcut dams. The constants for this relationship were developed under flow conditions that were about three to four times those during cal bra— zIon, but about thirty times those later used for modeling of prc— jected future conditions. DurIng the extremely low flow regIme In an area with impoundments the time of flow must also incorporate the hydraulIc efficiency of the impounded areas. WIthout such an analy- 515, a larger time of flow may result. With respect to the waste discharges used, the dIfferences in operating procedures between 1973 and 19714 must be revIewed. For example, ifl 1973 Cott Corporation discharged its wastes to the MIl— lis wastewater treatment plant. In 19714, however, It dIscharged dIrectly to Sugar Brook. A number of values Incorporated in the callbratlon process were assumed. Assumed values for nonpoint sources total to 140 percent of the total wastewater point source discharges. SimIlarly assumed are sludge deposIts which are formulated to take up as much as 3 mg/1 of dissolved oxygen, or nearly 40 percent of the river T s oxygen re- sources. Another sIgnificant factor in the calibration is the photo- synthetic oxygen production and algal respiratlon phenomena. As modeled, In some locations of the Charles River, this, combined with sludge deposits mentioned above, can take up as much as the entire riverTs oxygen resources. The basic fcrmulatIon assumptions of this and other parameters are dIscussed later. Here the dIscussion cen- ters around theIr use in the calIbration process as presented on pages 32 through 36 of the report. Figure 6 (page 314) presents the sImulatIon of zero photosynthesis and zero respiratIon (dashed lIne) superimposed on the range of four measurements (two night tIme and twc day time). WIth zero respiration, the simulatIon should show a favorable DO conditIon as compared to DO measurements at night time which Include resolration. As shown on FIgure 6, the sImulatIon generally falls below the measurement range IndIcating the need for a review of the modelIng parameters used. A further need Is to re- view weather conditIons surroundIng the 1973 survey period to insure that all factors are consIdered In the evaluation of the photosyn- thesis and algal respiratIon phenomena. For example, the weather conditIons discussed on page 36 of the report do not fully cover the survey condItIons as shown in Table 1. For example, the favorable water cuality In the Charles River on September 14 can also be at- tributed to its Increased lcw resulting from the September 1 rain- fall as well as favorable sunlIght condItions on that day. ------- TABLE 1 AVERAOE DAILY RAINFALL AND RIVER FLOWS IN TIlE ChARLES RIVER BASIN AREA, SEPTEMBER 1 TO SEPTEMBER 10, 1973 Location Boston WSO Blue hills Fram Ingham Walpole West Medway Franklin Milford Charles River at. Charles River Village 98 115 120 TIme 1 days in - IF__ T(2) ‘r 1.30 — — .18 — .08 103 • 39 .78 .80 — 1.80 .68 99 125 (1) no ratnfall (2) trace 3ource i: 1. United tate3 Department or Commerce, U.S. Weather Bureau Cilinatological Data: Iluw 1!.ng)an(1 , Vol. 85, No. 1, Asheville, N.C. , January, 1973. 2. Un I Led St.at;e Department or the Tnterloi’ , Geol ogica) Survey, Wa Ler Resource flaL;i rni• Manrmchuaetts , New hlaiiipshi re Rhode 1 ;]amid 1 Vermont , Uo ;toii , Maas . , 1 9(3 I. - Item Rainfall (inches) River Flow (cfs) September. 1973 .111 1 .1 11 1 • i i — 2 3 _(1) .01 .02 — — .07 .27 .60 1.311 • 36 - - 13 9 i eT 116 88 ‘I 1311 — I ‘‘• ------- : h&—:cal :x nation sates In the co putcr modelIng effcrt, deo: nation rate :cn— stants, K 1 , are input in associatIon with the wastelcad chara::eris— tics of t e fol1cw ng fIve areas: 1. background K, 2. stream K 1 3. treatment plant dlscharge K 1 L • tributary K 1 5. uniformly distributed flow K 1 W th n the model, all of these K 1 rates, except the stream K 1 , are used only to compute the ultimate BOD. All decay occurs at The stream K 1 rate. ThIs results In the following ultimate 30D concen— trations entering the Charles River in the year 2000: Source tilt. SOD m /1 background 10.7 treatment plant 5.8 tributary flow 5.1 uniform flow above r.m. 6.0 below r.m. 111.1 9.0 The background conditions reflected above were used in bc:h the 1973 calIbratIon run and the 2000 low flow runs. These loadings seem exceedingly high, particularly for year 2000 condItIons. In regard to treatment plants, in the year 2000 simulatIons the report used a decay coefficient of 0. 1 0/day. SInce these plants would be advanced, the organic material remaInIng wIll be resIstant to decomposItion and therefore a lower K, rate can be justIfied. As mentioned previously, all deoxygenation is carried out at the stream K 1 rate. In the computer simulations, the same K 1 rates used 1 n the yea 2000 runs as In the 1973 calibratIon run. I; nas oeen shown that as water quallty cor.c t1cns imprcve, tne ae x — genation rates decrease. Therefore, with the anticipated upgrading of the Charles River water quality, K 1 rates should decrease under 2000 condltlons. ------- : :i:o:encus O:.:i a:icr. sate In the modeling effort, the report assumed the :r:n:us decay rate to be .6 day l (or .2 day —1 in some cases). The 0.6 value is extremely high. All treatment lants consIdered in the Investigation discharge dlslnfected effluents to the river. Chic— rination effectively kIlls all nltrifylng bacteria in the discharge. Effluents not carrying theIr own seed of nitrlfylng organisms are sutject solely to the natural seed occurrIng In the rIver water or ifl attached growths on the bottom and on submerged objects. In addition, ammonia is a prime nutrIent for certaIn fords of algae. ; iI:h chlorinatIon of effluents, these algae will possibly make great inroads upon the ammonIa supply and thereby reduce the amount of ai= onia avaIlable for oxidation by nitrlfylng bacteria. Also, the range of oxIdation rates found In the reference cIted by the report is actually .1 to .6 day —J.. Dan Reaeratlon The report chose to represent this Dhenomenon by arela:i ship developed by Quirk and Eder. This relationship was develcped to represent reae ation through a vented turbine and not for free fall over a dam. Due to the lack of data, the authors used a linear relatIon between Fd(Q) and Q which passes through the origIn. This assumption results in low reaeration rates under low flow condItIons, which is not correct for a free fall over a darn when more cf the overflowing water mass is exposed to the air and subject to reacra— tion. A representation of darn reaeration WhiCh relates reacratlcri to the height of fall over the dam, such as that developed by Mastropietro or Foree, would give a better representation of actua:. darn reaeration under low flow condItIons. Such a formulation was also used by the DWPC in their Basin Plan. Stream eaerat!on K 2 In—stream reaeration was computed using a relationship deve.— oped by Tsivoglou and Neal. The relatIonship states that the reacratlon rate in a reach Is a functIon of the chanze In water sur- face elevation along the reach and of the time of travel :hrcugh the reach. The authors caution users of their formulatIon In applying It to rivers whose physical characteristIcs are predc•mInantly con- trolled by dams. As an example, for the projected future condItIons, the K;’s computed under thIs method are on the order of ten percent of those used by the DW?C In a number of reaches. Therefore, alternati;e methods of computing K 2 which have been developed for condItIons more similar to the Charles River should be InvestIgated as part of a sensItIvIty analysis. ------- Ph:::Zi ::y e ?‘ uc:ion a d :irati r The e:hod of accountIng for pho:o yr ;hes s ar .d re ; ra: .:r. used in the report modeling was based on work perfcr ed by : p: using the systematic diurnal curve analysis. The basic fcaticri is: = K 2 (C 5 —C) ÷ P — ir. whIch: DC = the tlme rate of change of DO concentration, = the rate of atmospheric reaerat on, K 2 = the atmospheric reaeration constant, = the DO .saturatlon concentration, C = the DO concentration, P = the gross rate of photosynthesis by the community of algae and plants in the rIver locale, = the gross rate of deoxygenation, includIng res- piration and nitrification, by the entire community of organisms In the river locale. In 1973, the IWWPC conducted DO measurements on the Charles iver. These measurements, together with the determination of K 2 , resulted in a relationship from which P and R could be determIned. As can be seen, the value of R — P is dependent on the value of K 2 used i.n the analysis. The value of R, so determined, is a total deoxygenatlon rate which Includes C3OD, NBOD, and sedIment demand. Therefore, in going from the total deoxygenatlon rate to that rep— resentati h of algal respiration, all other oxygen demands must be subtracted. This process Is in turn a function of the CBOD and OD decay rates and the sediment demand. In the model calibration process used in the report, the values of photosynthetIc oxygen production and oxygen consumption due tc algal respiration appear to be those as determined by the D PC using their estimation of K 2 t s. Rowever, when the photosynthesis value5 were Incorporated into the rIver basin model for callbratlcn and ftr sImulatIng future projected conditions, the report used the lower values as dIscussed earlier. ifl addItion, under the future prc ec:ed conditIons, the input values of algal respIratIon are the same a f:r the 1973 calIbratIon runs, but the values representlng phozosyntbe:I oxygen production have been greatly reduced. If anythIng, it would seem that the photosynthetic oxygen production would Increase under the culescent low flow conditions. The basIs for the manipulatIon of D PC’s data In the 1973 calIbratIon run, and the basis for the ras— :10 reduction in :ho:csynthetlc oxygen production while cxy en sun:tIcn by algal respiration is not reduced in the pro ec;ed cbndi:ion simula:ior.s; need to be determIned. (00 ------- ._J__ The iS epcr: has resen:ed res’ it of cde ca:ra: : forts for the Charles River DO resources which are s lar :c res : of a lIke effort by the DWPC 3as±n Plan; however it uses f .ca :— ly dlfferir.g factors. In the EIS Report, these factors are selec:e on the sIde of an unfavorable oxygen resources represenatlcn In zne river. The calIbration effort also includes a number of assumed val- ues whIch have a sIgnIfIcant impact on results. Several alternative projected future condItIons, as well as some changes in factors, have been simulated. The basis for their selection is not exDlalned. A scoring system was used to measure :ne alternatives whIch appears to be rather arbitrary. We recommend that: •a thorough evaluatIon be made of each factor and each assumed value, •;he range of confidence for each factor be developed on the basis of present data, •a sensitIvIty analysIs be conducted to identify those values havIng a sIgnifIcant impact on decIsions and requiring a narrowIng of their confIdence range, and .Investlgatlons, IncludIng, if necessary, fIeld mea- surements, be conducted to achIeve the necessary narrowIng of that confIdence range. t°I ------- I UN TED STATES ENVIRONME 4TAL PROTECTiON A r .1 J F E EW FE E &L eUILONG. BOSTON. July 22, 1977 I’s. Libby Blank Director of Environ enta1 Planning etro o1itafl District Corr nission 20 Somerset Street 3oston, 02108 Dear Ms. Blank: Thank you for your letter and comments of July 18, 1977 with regard to the Charles River water quality rodeling. e will respond in detail to each question raised by Metcalf and Eddy by August 10, 1977. Please understand, ho :ever, that the computer modeling of the Charles River which we are performing is based upon our understanding of the Charles River and our determinations of proper mathematical representazicnS of river processes affecting water uality. Thus, our final model simulations il1 incorporate any necessary corrections to the model input revealed by 1etca1f and Eddy after considering each of their com ents. I have attached for your information a copy of the letter which we sent to Dover, Framingham, riedfield, Natick, eed- ham, Sherborn and ‘Te11esley requesting their participation in an expanded site selection committee. We would welcome your participation with us and the cor unities in the site selection process. We will notify you as soon as we re- ceive responses from the communities and set tho first meeting date. Sincerely yours, £ Y k\CAL L kA\&p Mary E. Shaughnessy Environmental Impact Analyst ------- S. I ; UNITED STATES ENVIRONMENTAL PROTECTION AGENCY REGION I J.F. KENNEDY FEDERAL BUILDING, BOSTON. MASSACkUSETTS 02203 Au unt 5, 1977 t... r ibby Blank !)lr’ctOt oC invironi ental Planning iLr( 1 iO1Lt .)fl t)iSttiCt Cc . issiOn •‘,) ,u,ILtSCt Stre?t I ;t gut, i\ i2li 8 t) L M . i3lank: This is in response to your letter of July 18, 1977 to tis. ;•iary Shaugnnessy of tie viri,j .nr ntal and Economic Ir act OLLic’ concerniny tn? water ‘ uslity r ode1ing of the Charles River and effects of tn o: ; 3 — i ries aste ater treatment plant. I ritin; tc you directly because I am the person doing the modeling. 44’ r .iit 5 re used by the cnvironn ntal an cor o ic Impact Office and their consultants in oerfor i j . . ‘i. .. - t: i zsessment of the pro7os d tr tn n . alternatives for the i• C system. First, I will revie4 ou j.1 i ” ent in tne C.arl F .ver i odelin’j and tn n res?c. i to the rjuestions by i etcalf and Eddy, Inc. In June an Se te ber, 1973, the assachusetts Division of eter ?ollution Control, ( D C) , conducted water i 1it 2 ’ surveys of the Charles River between ilfori aterto4n, assachus’ tts. .)ata fro,i these surveys was used to set u2 trie stream model of the ;: .•;pC Lor simulation of water qpalitj ; t•. i .•:i )urin the June an E cpte: .ber surveys. The strea i ocie1 is that :.escriied in Syst :i5 \ n 1ys s for ater Poll .iticn Control b uirk, Lawler a 1atus y, June 1911. iir. John Erdmann, fornerly of the .1D. PC cerfor.r i the model set u2 ai.I i!1’J1ation of the June and Se te ber survey conditions, a procesa tcr. ed model ca1i L tion. At tne request of our -:n ,ir ntal an3 Economic I. pact Office and with the cooperation of ;•ir. Alan Cooper ar. of the ID.S?C, I obtained tne Charles Riv2r m .]’:l s calibrated by Mr. Erdmann and d. ve1op d a sirrulatiOn of the Charle. RLv2r unoer 7—day, l i—year recurring low f 104 CI)I1LIIL1OflS for with dater quality standards. This si 1 ulatiori was done using the PA version of the stream model progra’ which is analaQous to the i . D. PC ctrea:n model pro rarn. At the ore5 nL ti r.2, the modelin j is being done with the steady—state option of the model and we are si. ulating (03 ------- aitcrr. t ve tre t ?nt plant locatior. ar.d io :n cr criL1C L’ r cju. lity condlticnz. The .ty—St.e : is be1r u3e5 because tne port Ion of tnc 1rOU i pr re . L• oiurr. 1 Ji. s )lved oxygen v riat on due to oLo. ynt 1OS15 Was found to be incorrect. Ti5_nOJ Jj snould be cu,n.:ilcted by the end of tne month and the final results will b rejorteJ in detai —t afl concerne p3rtie . Now, fl respondin to th rjuestions by Metcalf and Eddy, inc., I will comment on each as presented by them. QuestiOn 1: Projected Upstream water Qua1it ConditiOr.S Water quality conditionS upstrea of the iouth Natick Dam, .5 ;i ulated, are tho5e resulting from stream conditions as we predict them to be and e5tim e wtc4ut’ r loadings from th’ various treatment plants discharging to the rjv’ r in the year 2033. me wastewater loadings for ijitord, the proposed Charles River Pollution District, rer tham State School., NorfOlk—. alpOle i CI and :edf eld—:1illiS are tfl.p j estimated to be disc’ ar’jed with the respective treat! ’1er r . )l nt configurations producing their highest quality effluent achievaole. Loa 1r Js ani f!o. were deterrnine.i by c e 6nvironment3l .: essment Council, Inc. and Greeley and Hansen, Inc. after revie ;ing information on tne Eacil ties currently being planned for the various co nmunities. Results of rnodeli’g ur. cr tnese conditicns indicate that it will be very likc-ly that certain stream reaches upstream of the South Natick Darn will not meet water . ality standards for dissolved oxygen under year 2000 conditions. riere— fore, it is erroneous to assu:ne t &c water quality standards for dissolve I o y;9n will be met under critical low flow conditions in .ll upper river reaches. - Question 2: Projected astew ter Flows The anticipated Medfield— illiS facility was initially simulated witn a waste .zat!r flow rate of 1.5 million gallons per d y (ngi) beraj e that is the desi;n flow capacity of t e existinj ?ie.ifi li treatnent plant. The proj ecte 3 t ter flow for b t.i co.n uriities c3rb1ne in the year 20C is estimated to be 3.0 nyd. Tne model has been •:. ivjed to reflect t ’ etfects of the entire 3.0 mgd. Question 3: Stream Reaer t1on In reviewing the calibrated nodel by Mr. Erdmann and t04 ------- triO s 1ifie : i’: re c’te i t e 1976 C:ie River ter n:’ r• nt ?1 r’. it seen ti at tne re.crt tion cocffic . r.t as co tec the O’Connor—Dcbt :ns 1sotrc ic T -h ii- ce relation .-.i . Tnis relationenip is most valid for use witn strea s having aeptns of 7.3 to 12.3 feet 1L) : l ’cit es of ø.5 to 2.5 feet p r second. Under con i ons of 10—year recurring low flow the water c3eo .hs iQny t.- e entire river are co; 1 puted by the model to be between 1.0 and 10.5 feet 4ith velocities of C.C5 to ci.55 feet per second. Thercfore, the Tsivoglou—:eal ner Dissipation re1at on hip was used to cc pute the re eration coefficient. The re3.stionship is valid for str f.low and ss ci t d ie tns and velocities in ran je of 1.0 to cubic f t per sscond, which icludes th’ ran’Je of flows along the entire har1es River duriny 1o flow conditions. The Tsivoglou—Neal relationship includes the change in water surface eie iation along the 1on; tu ina1 stre profile, the time of flow within the s re r and a coefficient tern related to flow rate. Reaeration rates itIiin each river reacn ere co te using the proper coefficient for stream flow, the cnanye in water surface elevation as taken from Coros f n.iieers profiles of the river at low flc and tne tir e of flo as co.nputed by the r odel. These and o:i r terms for river reaches 17 tnrough 22 are snown n tne attacne5 table. Regar’iin’j etca1f and Eddy’s cor ent on the “choice” of reaeration coefficient values and ass tions of sediment oxygen der.and rates; the reasration rates are co puteJ ac by reach as pr vi us1y explained ‘. hil sediment oxygen dend rates zere ass ei cori i3er n; available data. 3. :j a Cflt demand is assu eä to present in the ri’. er within reacnes upstrea o the da!as and where strea r. bo to material analysis indicates organic sediment is present. As sho..:i in i C attached table, sedi 1 i ent oxygen demand s ioc t behind the Soutn tick and Coczrarie a s and in lo er velocity reaches. In the table, note that the reaeration coefficients for reaches 20, 21 and 22 as lnjUt in the si:nulations reviewed by i’ietcalf an i Eddy were in error as computed and ha ie since been corrected. Question 4: Dam Receration The value of the model input variable for dam ------- rcacratlon ( ) c.t the Sc t . iatick D wc-r. rj ifl3llj L J into the model as O. i6’-. Tne Va1 e shOUld fl3VO en 1 .UG88. odel input has beer correCt2 t value. The discrepancY CC’’J e fa the 1 r’j difference in dam rearation between tne Sout NatiCk and Cachrarv. Question 5: DeoxY enatiOn Coefuiciertt or witrogenous qen Denafld The modeling described in the Charles River 3t r Qu.311tY 4anage eflt Plan is a sinplifie l roceauro wr.icn considerS car )3flaC )U hiocncnical oxygen deina:;i ni nitrO flOuS Oxy cfl aemand a one proc’ uccurrin a one rate and t ref.orc both rate constants must be tn same. stream model co z 1icrs the’5e )roccc:c5 separately as they actually occur in nature. The deoxy.3cnation coefficient for nitrificatiOn of .6O at 2(°C is a hign value which results in the ammonia concentration simulation cor pariflg e11 with the Septe’ ber 1973 a. imonia concentratiOns as rneasurei in the river. Also, the higi v U’? iS logical asc’i;nptiOfl consider in tnat when the four major treatment plants on t e river ar operating as advanced biological syst .r s the river should continue to have a well estabiisfled population of nitrif n J organiSmS. Because the r.adel is well calibrated for ar. on1a and high po7ulatiCnS of nitrityir.’3 organi3• S can be expected in t e river in the future, the assuied rate of 0.6 is valid. In summary, the modeling is conticing as explained herein. when final results are availa)le, tney will be sent to all involved parties for review. I hope this explains my position with regard to the ode1ing and s ou1d you have any further uesti0flS please do not hesitate to Co!ltCCt me. Sincerely, Allen .3. Ikalainen Acting Chief Systems Analysis Branch cc: h. ShaughneSSY EPA A. Cooperfl fl. 1) PC A . Gitto, EPA ij . Vittands, iietcalf and Eddy, Inc. L. Polese, MD PC R. Chapin, EAC ------- c; RL’S RIvr.R ‘TDEI, YSTE S VM.YSIS !3RA.CiI CP,\ - RZGIO:; I RIVFR RC1 CIIES 17 TIIRU 22 Low Sediment Flow Time of ! Change in clan Reacration ” Oxygen Demand Velocity / Depth Flow of water Surface Rate Reach ’ Grams /m /dav Ft/Sec Ft. Hours Ft. — Day 17 3.46 .07 4.8 10.6 0.5 0.06 18 3.46 .08 5.1 53.6 2.0 0.05 19 0 .19 2.5 12.5 0.25 0.03 20 1.38 .12 7.5 56.2 1.45 0.04 21 0 .45 2.8 5.2 1.0 0.27 22 1.38 .32 7.0 14.9 2.0 0.19 a/ Reach 17,— flogastow Brook to Medfielcl hospital — 0.5 miles Reach 18 ‘ ec1fie1d hospital to South Natick Darn — 6.7 miles Reach 19 — South Natick Darn to Waban Brook — 1.7 miles Reach 20 — Waban Brook to Cochrane Dam - 4.8 miles Reach 21 — Cochrane Dam to Chestnut Street, Nccdham — 1.6 miles Reach 22 — Chestnut Street, Needham to Long Ditch Inlet — 3.2 miles h/ Proposed MDC plant located at head of Reach 18 c/ Coefficient for Tsivoglou relationship — 0.060 @ 25.5°C ------- :, —: i — irector of vironnerital ?ann!ng : •:e:rcpcli:an District C.ission 20 So erse: Street cs: n, : .: o2loS — ‘—. . .•.s. Lan . : res:cnse to the recuest by ! DC we have ccnduc;e a brief ‘eview of EPA’s ZIS Consultant’s Charles iver odelin efforts associated with the location of the Middle Charles Satellite ; •:ast •;at r Treatnent Plan:. Spec fical1y, we have reviewed the f:llc :in dccu en:s: a. A andu fr r. r. F. i. Thapir. of the Environ- en:al : ess en; Cou’.cil, IflC. (::s Ccr.sul:anz) c Mary Sha hnessy of EPA, describing six ode:.irg cases and reccending that the discharge Cf : e sut ect tlan:be located as far u s:rea:- of the cu n as tcss: e. :. Cc zuter ou::u; frc the cdeling of Case 3A described :i the I Consultant : :e cran um. r ana:.ysis has focused on the assumptions and parar.eters used in :ne cc ;uter mcde.ing effort. :n :h s review, we have assumed :na: the :ara e;ers used in Case 3A are the same as those used in :he ctner five :ases described in the EIS Consultant e orandtu ma: ftr the :asis fcr tneir reccru endation. cwever, ins ec:i:n :c :_c: :— : Cc’ s .l:a ’ t LercranC -‘a’ es :-_s as— s::icn : stimable s:ecifically because of the peculiar :lc:s for Cases and 3 between river •iles 39.1 and puter runs for other than Case 3A were not supplied for review. ase our initial review, we raise ques:i n in the fcllc ing areas: 1. Prciec:ed cs:rea a:er ality cnditicns . in a six of me cases considered oy me E5 C:nsultant, seri:._s violations of Class :a:er cuali:y standards are :rc i f:r several of the se;nen:s u:strea cf the South ::a:i: _a i: ng me rea:nes :nne::ate y upstream c: : e da :bere a 20 of :er is rc , ec;ed as a result of s:rean effluent loads, i.e. • cxci’ ing the i •:ia :e Cha:’ss :lan:. :t is iroor;ant to know the extent to w ic :s c:nsu:tanz’s reccru endaticns relative to the ±dde Cnarles :an: are inf e- ei t ::-is cde l ed u:rear vo c . ‘•- (os) - - - ------- _:::y z_a r: .... .. :, —; ; a:er Quality. In ncdeling the River under the year 2000 conditions, snoud it not be ex ec;ed that ut— stream. dIscharges will be treated to the point wnere water quality standards wlll be met? 2. ? ro, ected Wastewater ?lcws . In the EIS Consultant’s modeling, the Charles River i assumed to receive 1.5 mIllion gallons per day (:ngd) of wastewater from a combined Medfie1d— i11isfacility in the year 2000. However, the DW?C in its basin planning has reported flow projections of 1.0 mgd for each cor iun1ty in 19E5. ?rojectlons in the £Y!I’ A study also show larger values for the year 2000. Ir. the £13 Consultant’s mcdeling work, were changes made In the sewerage service con- cepts In that location to warrant the reduced effuen; dis charges? 3. Stream Reacration . The values of the coeffIcient cf reaeration (K 2 ) used ifl the model are consideraoj .7 less than reported in the 1976 Water uality 1ana ement PIan cf the £ !assachusetts Division of Water Po lluticn Control (JW?C). The attached table comoares these values for the clever. reaches on the Charles RIver of interest to the MIddle Charles plant analysis. In the nine reaches no; considered to be “rapids”, the values of :<, used in the model are i to 96 tercent less than those re- ported by DW?. Reach 21, ir_ ediately below the Cochrane Dam, value of •<2 was Increased to reflect the higher reaeration rate exDected In this so—called “rapIds” section. The value, however, is only aoout or.e—half that used by the DW?C. However, in the other “ra Ids” sectIon (Reach 19, just below the South Natlck Dam), a K 2 value was used that is among the lo:.:est as- sumed by the EIS Consultant anywhere. This choice Cf K 2 is lnconsIstent with the assumptions on ber.:hic oxygen demand made in the £13 Consultant’s Memorandum. On :ne other hand, in the long flat reach between the Sou:n Natick and Cochrane dams (Reach 20), a K value was used almost ecual to that used at the Co hrane Dam “rapids”. What is the basis for significantly changing the DW?C parameters? 1 . Dam Reaeration . The DW?C used fIeld samoling data to conclude :na; the South Natick and Cochrane dams have e:ual va ..es c’ tre reaera::cr cef:o.t ra: o -e £5 Consultant used a similar para ze;er, the reaera:Icn f n :ion. Thus, one would expect the two dams to oe (oq ------- cnaracterized by equal values of P’d ( ). c JeVer, the IS Consultant modeling won.: is based cn in u: parameters that give the South Natick Dam a reaaticn capability nearly nine times that cf the Ccchrane am. What is the basis for this significant change? . Dec.x:::ena:icn Coefficient for i:ro enCUS CXIZen Demand . The mcdel outputs prodUcedDY t. e S Ccnsultant are based on a value cf 0.67 for the oge ous d oxyg ra on coeff 1 e t in all reaches. S s ma kedly h 1 ghe t a the 0. value used by DW?C. Again, the basis for this change neeos tO DC determined. t this time, we have identifIed fi e areas .•:here the séecti;r of parameters are expected to impact Si !fi:antly the ccncl — sicns cf the ElS Consultant’s Memorandum. It is a parent that an item by item review of the mcdeling data, and possibly the program fcrmulation is needed as tne ne::: step. cr the siznificant model parameters, the range cf confidence sncud be identified and theIr sensitivity should be de:er .ined. Scne :aranc:ers can be field checked easily. An example cf s cn is the reaenaticn capability at the critical d ns. Due to the recent attention given to possible discharge locations, it .s reco ended that MDC review with DW?C the following prcpose next steps. 1. Detailed review of all input oarameters. s;ablishment of a pcssible range for each signifi- cant parameter. 3. ?.eview of the program formulation. . Sensitiiity analysIs of parameter ranges wIth respect to a decision fcr the desired locaticri and requIred effluent quality for a Middle Charles plan:. At a minimum, modeling runs should be made wIth the above—noted changes, to determine the impact on the EIS Consultant’s ccncl sion relative to the discharge location. ?e y trul ’ veurs, ekabs P. Vittands (%0 ------- COM PAI I ;ON 01 ” fl i•:n EU A’l’ I Oil ( < ) VA I A I i•: ; iJ lI) 1,0. ‘r(8 I I l . .1 39. II 3,’. 6 33.0 29.8 C. 2 11 . 2 71.2 L S • C. I C ) 1? 18 19 20 21 22 23 .) I 2 ‘ 26 0.056 0.1115 0.056 0.033 0.5111 0.569 0.089 0.033 0.011 0. 022 0.1311 0 .311 0.35 0.33 Q.82 0.25 1..i 0.29 0.22 0.30 0 . 27 o . 2 l vcr —— :;La I l.on in lie No . Ei ; (1) F)WPC (2) 119.9 110 Ic i ’ Ih’o(JIc Hece] ve llac ha rge I ’ioiii MedFieliJ-MI 1J I:i Ii )j-’_,a LOW Drook Med I I 01(1 110 api Lal (Ia I. Ic k Dani “Rapids” (Mole low E1 K 2 ) Wa han Ilibooll ( Hole hi l i :i S K ) Cueluane l)arii “Rapids” CItc ;I.iiiiL 3tr ct l. ( ii ’ 1)1 Ich fiilet. f •luLliei ’ I)i ’ook Diversion 10 Neponsel RI v i :; Will Ii .I_ Ut I1.;_ , ,Iow I rc )c l( ;I 1k (II ii flaiii 1 . II:;e ,1 h y El Cona i I I.anl. fui’ Iwo.)ecled Veat’ 700(1 condl I; lona hy l)WPC iii Clia ii eu H 1 vet’ Waler Qua] I I;y Ma iiageiiierit. Plan t ’or’ proj ec Lcd Year 1 9U (:1)1 111 I I; I oii:; ------- S. •. — -I. F f /1 -_,‘/ie (,t’_i’) )nc/e(?e’a((n /‘ .. f (7 . C(C ’i .” ’ .‘t: ; ( .JflC/ July 18, 1977 TEL. 7Z7-e eQ .Dear Ms. Shaughnessy: Re: EIS - Charles River Water Quality At quality plant. our request, Metcalf Eddy, Inc. has reviewed the Charles River water modeling data relative to the proposed Mid-Charles wa tewater treatiient The following are counents provided to us by Metcalf and Eddy. “Specifically, we have reviewed the following doci.m ents: a. A memorandum from Mr. R.W. Chapin of the Environmental Assessr ent Council, Inc. (EIS Consultant) to Mary Shaughnessy of EPA, describing six modeling cases and recoimnending that the discharge of the subject plant be located as far upstream of the South Natick Dam as possible. b. Computer output from the modeling of Case 3A described in the EIS Consultant Memorandum. Our analysis has focused on the assumption and parameters used in the computer modeling effort. In this review, we have assumed that the oarazneters used in Case 3A are the same as those used in the other five cases described in the EIS Consultant Memorandum that fonn.the basis for their reco endation. However, inspection of the DO plots in the EIS Consultant Memorandum makes this assumption questionable specifically because of the peculiar plot for Cases 1 and 3 between river miles 39.7 and 40.5. Computer runs for other than Case 3A were not supplied for review. Based on our initial review, we raise questions in the follotdng areas: 1. Projected stream Water Quality Conditions . In all six of the cases considered by the EIS Consultant, serious violations of Class B water quality standards are projected for several of the segmer.ts upstream of the South Nat±ck Da. in uding the rea hes i r’.edia e1y tr a i c’f the SN VI RO ‘4 M ENT AL PLA.NING 0FICS 2t9 ‘rne, / c. 9 ceee j ’. 4n O &IO8 1977 T .LF & ED DY I. .’ 1 FC10. Ms. Mary Shaughnessy Environmental Section Environmental Protection Agency J.F.K.Federa]. Building Boston, Mass. 1 1i2.. ------- dam \%here a DJ of :ero is projected as a result of :pstr cff1u nt loads, i.e., excluding the .Liddle Charles plant. it is important to 1 iow the extent to ..hich the EIS Consultant’s recorrrnendations relative to the Middle Charles plant are influenced by this modeled upstream water quality. In modeling the Rive under the year 2000 conditions, should it not be expected that upstream discharges will be treated to the point where water quality standards will be met? 2. Projected Wastewater Flows . In the EIS Consultant’s modeling, the Charles River is assi. ed to receive 1.5 million gallons per d.ay (mgd) of wastewater from a combined Medfield-Millis facility in the year 2000. However, the DWPC in its basin planning has reported flow projections of 1.0 mgd for each conununity in 1985. Projections in the E’Mk study also show larger values for the year 2000. In the EIS Consultant’s modeling work, were changes made in the sewerage service concepts in that location to warrant the reduced effluent discharges? 3. Stream Reaeration . The values of the coefficient of reacration (K 2 ) used in the model are considerably less than reported in the 1976 Water Quality Management Plan of the Massachusetts Division of Water Pollution Control (D PC). The attached table compares these values for the eleven reaches on the Charles River of interest to the Middle Charles plant analysis. In the nine reaches not considered to be “rapids”, the values of K, used in the model are 44 to 96 percent less than those reported y DWPC. In Reach 21, inrnediately below the Cochrane Darn, the value of K, was increased to reflect the higher reaeration rate expected in this so-called “rapids” section. Tne value, however, is only about one-half that used by the DWPC. Ho ever, in the other “rapids” section (Reach 19, just below the South Natick Dam), a K., value was used that is among the lowest assi ned by the FIS Consultant anywhere. This choice of K 2 is inconsistent with the assumptions on benthic oxygen demand made in the EIS Consultant’s Memoran&zn. On the other hand, in the long flat reach between the South Natick and Cochrane darns (Reach 20), a K, value was used almost equal to that used at the Cochrane Darn t1rapidsr . What is the basis for significantly changing the D PC parameters? 4. Dam Reaeration . The DWPC used field sampling data to conclude that the South .atick and Cochrane dams have equal values of the reaeratiori deficit ratio. The EIS Consultant used a similar parameter, the reaerat ion function. Thus, one would expect the two darns to be characterized by equal values of Fd (Q). However, the EIS Consultant modeling work is based on input parameters that give the South Natici: Da r n a reaeration capability nearly nine times that of the Cz :hr tie Dam. l nat is the basis for this significant change? ir ------- 5. De xv2enation Coefficient for Nitrogenous 0xv en D and . T - model outputs produced by the EIS Consultant are based on a value of 0.67 for the nitrogenous deoxygenation coefficient in all reaches. This is markedly higher than the 0.2 value used by DWPC. Again, the basis for this change needs to be detemined.” We have discussed the modeling data with Messrs. Coopman and Polese of the Division of Water Pollution Control and they concur with Metcalf and Eddy’s corrments. At this time the C and the DWPC request that you rerun the model with the changes indicated by Metcalf Eddy. If you have any questions regarding these changes, please contact Jekabs Vittands of Metcalf G Eddy at 523-1900 ext. 456. When these model rerwis have been made, the MDC and DWPC staff would appreciate the opportunity to discuss the outputs with you and determ.ine whether additional analyses are required. Yours truly, Libby Blank Director of Environnental Plannng LB/co cc: A.Coopman, DWPC J.Vittands, M EV A. Ekalainen, EPA ------- H £ H C . P A TO: Y.ary Shatchr.essv - — E.P.A., Project Officer (j.i C 4 IP A CC: I. Klein; C. Koch; D. Suler; D. Bartlett FROM: R. . Chapin — DATE: May 18, 1977 P IF: Location cf M d—Charlas S ver satellite :lant dischar2e The DflA study recorrends dis:harti o the effluent frcr the rid—Charles River satelli:e plant a: the Cochrane dr.. Our use of the Charles River a:er çuality nodel has been ai ed at dece iniz: if this is the “best” location for the dischsree. ?re’ ious nenoranda. 15 .t::il and 26 April, sur ri:e Tcdell:nc activities. This nercrzndtr etlua:es the effects of the varicus cases ucon the orvcen balar.ce :n the Ch:rles RIver. (Rasults are evaluated relative to Class 3 dissolved or:zen standards. See rerorand z of 10 Y.ay 1977.) The ECA reDcrt rezrnended a dischane of 31 rad containin: 5 rz’l 30D; and 1 nz/. at the Cocnrane dan. arly nodellir.: runs indicated this to violate -;ater :tzlitv stzndards for dissolved oxvzan and. :nerefcre, the dischar2e effE.:zs of an “advanced” level of trea:nent, no a EC; of 5 g/1 and Z of 0 n;/l, -;ere investizated. :n addition, tvo a :erranve discharge locations were rodelled: a: the S. atick dan: anc 6.7 :les uo— strean of the S. ::a:i:k dan a: the he of n:de11iz rsach IS ( areaf:er called Reach 12). Fisures 1 an: 2 :resen:, res;ec:ivCv, :lc:s st.-rari:ir.z these treatrent levels and dischar:e Locations and :he r affects uoor dis- solved oxygen levels in the Charles. The E’2A recornended dis:harse resulted in a lar:e D.C. sn below the Cochrar e dan, which violates the Class B standcrd of never less than 5 ng/l at an: ti—e. Dischar!e at the S. Nanck dan res 1ted in two sa;s below the 5 ra.’l level, howaver, these were n:t as severe as the Cochrane dai discharge sag. C.n’.’ersely, d:scharne at Reach 1S caused no “ blanc;: of the 5 r!/1 standard below the S. Nat ck dan. Dissolved o::vgen levCs above the dar are well below this class 3 lbic, althcu:h dischar2e a: Reach .S generally ir:rcves ccndi:ions over ch:se predicted to ex:st out a -TC disoharge. tThen dischPr3ing the advanced effluont at the Cochrane darn a sag below the Class B 5 r;/l ilni: occurs. This level of trea:nent does not violate t :s standard whcn disc ar:ed at the S. ::ick dan, hcwe”er. the 16 hour class B standard is vio1.a:ed by a S. azick dr d:s:harce. Reach IS dischzrze a.s: does not violate the 5 n:!t stand:r .! bel:w the S. atick dan, while cissclved oxygen levels above tne can fall below chat level. However, a discharse here i—proves conditicr.s in this reach over the discharge condition. ACdi— tionally the 16 hour stanc:r ::es n:t ao:ea: to be viclated the IS dis:harcc. I’g ------- w—J- ‘ ‘ — rake .ay 1E, 157 ThIs analysis indicates the greatest benefit to the oxygen ba1a e cf the river occurs vhen the 1d—Charles satellite plant sch rces . a- vanced effluent placed above the S. Natick dan at river ile 47.8. The political reality of placing such a discharge at that location is beyond the scope of this discussion. Nevertheless, it is the position of EAC that any discharge from a id—Charies satellite plant be placed as far upstrean of the S. Natick dam as possible. Such a discharge appears to provide the most benefit to the oxygen balance of the Charles River. ‘lip ------- Char es F iv : ::e ::e-: _s _o& t Mode].llng Waste Waste C .arac .eris ::s Plant Reach -. r1o ( ) 30D ( g/1) - (: j ) Yi1for i CHO3 6 5 1.1 CRPCD CH13 8.4 5 1.0 Wrenthe: State spOl 0.1 5 1 Scnoc]. Norfolk W 1po!e SPO5 0.4 5 1 MCI Medfie1d— i11is C 1E 1.5 9 2 v!RO .F” TA.. E! T CL CiL ------- ‘ ‘•— — case cr c- ?. .z5 eccr.-.er ed z:.: d.5::-arce a l i- at the Cochre .e dan. :ss:1-:e oxycen SacS to 1.5 c/2. he : the .11 da..-’ (:: . e ie C.) vio].atir ’.g C .ass 2 s:ada:ds (see at:ac -ed Fic re 1). 3 Recor er.de Z A discharce and ica i-.:s at t .e S. atick sag to 4. r ,’1 de’.-elc s eh .r.d : -e :cc a dan (at r ;’er ie while a secc d aac :o 4.1 .c/l e:ec:s : e £ k :: 11 . This io1ates Cas3 3 D.O. cr ter a (see F c re 1). 4 Advanced disc :cea d lcad:ng at the Ccchrane . . . sac at 4.1 mg/i hind s :c :: il an which v:o lates Ciass 3 standards. 4E Advanced d:scharce and load:ncs at the 3. Natick da . 5 a.n. d scnar e causes sa to : i —., wh ;: dces n z te Class 2 1o e: 1 : ::er a. A :.:le of for a -r :er.cd thdica:es s:an±ard :s v c1a:ed (see a.zle 1 and Fic- re 2). A:an:ed ::a:a:: an: lcadin;s : ::ee— cf S. atick — a: :i er 1e 47.5 (the : a: f t:- s. ..— reac:-). his :—:roves d .s— solved a a:h : - r these c::r.—c ho : :ne dis:ha: e :.c. :e’.e:s do no: : ae anove :ne 5 lc er 1 : for Class 2 e:s. A sac to 5.7 c.’i de’:e:os s : ::i1 or—. A cycle cf r a f:: a 4 hc r ;er::d :ndi:a:es tne :: s 2 i standard .s : a: no: v1 :ed see a 1e 1 and : - e 2). 3A ?.ecc ended z::-a.: and 1:ao._ncs strea— cf S. :n: dan at river i1e his also :oves .O. leve.s h:nd 3. Natic dam. :: : : as ‘ ch as ase 4 . A sag to 5.4 /1 de’.’elc s behir.d 3i :: d -, hc ever a 4 hour cycle has r.c: heen for this case. s;.f.e:, a1. _s at S a.r. ENVIRONM!’T4L AS f.SS. E 7 COL.2U. !1C ------- Charles River Be thic Demand Reach /m 2 fd Z Bottom Coverage Co=e:its 19 — S. Natick Dam to Waban Brook 0 0 rapids 20 — aban Brook to - Cochrane Dam 1.38 25 21 — Cochrane Dam to Chestnut St. Needham 0 0 rapids 22 — Chestnut St. to Long Ditch Inlet 1.38 75 23 — Long Ditch Inlet to Mother Brook 1.38 75 24 — Mother Brook to Long Ditch Outlet 1.38 75 25 — Long Ditch Outlet to S. Meadow Brook 1.38 75 26 — S. Meadow Brook to Sick Mill Dam 1.38 90 (ii EPJVIRONMEF .TAL A !Z S’. E?.T CL CIL ------- S. 3 :c ::c. . e Tin e Low D.O., “i 3am 5.7 5am 5.1 9am 5.5 12 pi’ 7.7 6pm 9.9 12 am 6.7 Reach 1! DiE: r;cs Case 4 3am 6.2 5am 5.6 9am 6.0 12 8.2 12 am 7.2 Note: All low .O. . 3i es are dc s:: cf Cochrar.e -. a: :i rer 1e ::.: the Silk : i1. i . (2.0 ENVIRO’ .iET. .t. .SS SS .1 NT CCU :CI. ir .C ------- I : :i Ff .r. i . [ TT ‘ :. : ISCthRG’F i 4 Lt3O IiGtLj .: .NH TT TTTT i m- I . .. . .‘ i I — I I • 11L$ . . . .UkT.LC. i + 4’ £AC4i1 [ : TTflT.. !i CttL . ! uI:Z. ? ..t.H I flH:.: • • : I ’ :i :1 • •I . .. I:...I.. •1. -I I ‘±t i L i THfL 4J I 1LLt 51L I’ ; H Ii ’ : •. :. • : ;. AL:.’ !;ii :; j. ! : ‘ . - i . : .. i ; ! • I • : • :. ::.:... 1_ - . 1.• •• , ri •4 I-! • .$ ,• . .1 1 (J . ..H_ • : I iii • : ; ,: iiI • I: . !1! I,i I ,, 1 .1 1 ! ! I . i 1— • I. :‘ I. -;--.-- H .4— :: :. I.. • • • . 1 i::: I • I — — —. :1..:. I. :_ I.: __L .:i . -- :.i Me (1.1. 13 IF. I.. 11 J :]’LI; 1I LIL.H II I , I I L: L :Z L.LIL. —I ••_ __ ,_•• I I — . I I —t Ii - JI I j.._ ‘ I A. AT .5AJ !._ I— I—I— I .::: :::I.::. : I •.. . :. :. t..TtTTj ... :J:: :1..: . : :i’ ‘ H..I . . F i’ -I, 1T I: ‘a i :. .qjp L T TT:T :. :•. 97 T1 •.. : I : . 1. • 1••• ____________ i i II I I ifj,:. 1 __ 1I :...j —. •.• .— • I — I, I’ :. . 1: I • : • : •_ I • . ‘ I ! - •• I : : :1 i• (LI I I I 1. I_I . . .. .1 ‘j’ I . :, • I • • . — ! ....LiLLL f-I. . :. IT .: — f l . 1 : j .1... . I::j:!T ... . . . .! , •... -1 — ___.tu •.• — I ‘ i J 1 tTTT± T rDI tH;i — I -, _. LL r • Hy ::::: :3 1 T ::3/ I I ‘ I I I - R Lt::LJLL . -:H [ t-iI , \ DI CIt 1 RGE . I . --I I ‘.. ___ J ..J ._.___. . -.L. .J......j . ... • 1•.— — ------- :.j..!.’ l 1 i ___________ — =. ._. .....-:......, - — - - - - : 1:: : - :i. -: .— ::.. I_ - 1- .. .. 1 “. I . . I - — - — l - .1 . : : : 1 i . :: I. . ) - - — -1 -. I ——:::.: - 1.1 :-. -- : - I.- - — - •- “1: ‘ .1• -I : ot : ::I:’: ‘ i-—I ..—... :! 1 L I -. I - - . -J - I- r .r :: . - - 1 2 1 1 L - . :... -.. - . I.- i —. .:_ . JIVL1 f IL . . -. I - . — _lt::l11 4 1 UI I— - -... : - :, . : ,.‘:;: I ..I..: ....t. : f : I = ! V J - -— ---.. ::::I () . .: . . I. 1 —H £ 11 ;. jT 1: I I . ..• ii I :•.;.: - I I - 1 Ti T .iT1TTT T . : • 1 .1 .1.. :.. . ! . I— I a _ _i I I.’ : I I I - -I HI; r Ii I j a - : _ SC RGE . .P .01111 1 _ . . i 1 _L_ 1 I 4 LC i i1i [ I :: - .::: .:1::il .1 i _ i:i:!iLi Li:” J4 j____ I .. - i: ..I . I, —I - .# p II . I. (. C- r V C. I.; I. — r : 1:. P L L’tJN. I T -I :‘... — : - - . i: — I _.I • I i - —-I —I-i • I L i :: till a 4e L . L. :: [ : -( -, :J:. 5. I i1lL . .. 1 O ) iL l. —. 1. •. . I t 1 t II I_ r — — -— — — - l I L [ I L L__ /,I I: :—i I 1 — I — T1r —;•— .%• . .uJ — — — — I — i (L ILi J IJJ L J — .— . — -I — — . . — — — ______________________ _________________ — — II I I — F — L4- .‘ —I—— —— 1- -• f: I I a _ .,— 1 at 4 IuI I -I I I — — r—- ——-- — — — — I. ( I I , . . . . . ..! : :- I. II ___ I i I jII::i Ii _ifj ’.i -I .—. I i . - . - : “ :: I — I — — — — :—• — •— ,. I: H: H H - :.r..:. I - : IE::T; I .jL;::; I. : 1 :1.. LL Lt I - I .. .1 a I.. — 1::. a: CIJ - I I I, .-. .—4• ._*I .__ ‘ i_ .’_t”_’_•— . . U’d Q hMIl I - ±1 i - — - I 1’ yr 1 .T’- -. - J. t lI —I Ii . 12 1.1 - ------- ATTACHMENT B WETLANDS DISPOSAL BIBLIOGRAPHY B-123 ------- BIBLIOGRAPHY 1. Gersberg, R.M., Elkins, B.V., and Goldman, C.R., The Use of Artifi- cial Wetlands to Remove Nitrogen from Wastewater , Ecological Re- search Associates, Davis, California. 2. Kadlec, Robert H., Wetlands for Tertiary Treatment , University of Michigan, 1978. 3. MDC, Wastewater Engineering and Management Plan for Boston Harbor- Eastern Massachusetts Metropolitan Area, EMMA Study , October 1975 (Metcalf & Eddy, Inc.). 4. MDC, Nut Island Wastewater Treatment Plant Facilities Planning Pro- ject, Phase I, Site Options Study, Vol. I , June 1982 (Metcalf & Eddy, Inc.) 5. Mudroch, A. and Capobianco, J.A., Effects of Treated Effluent on a Natural Marsh , Canada Centre for Inland Waters, Burlington, Ontario, J.W.P.C.F., September, 1979. 6. Odum, H.T., Ewel, K.C., Mitsch, W.J. and Ordway, J.W., Recycling Treated Sewage Through Cypress Wetlands in Florida , Center for Wetlands, University of Florida, 1975. 7. Reed, Sherwood C. and Bastian, Robert K., Aguaculture Systems for Wastewater Treatment: An Engineering Assessment , U.S. E.P.A., Washington, D.C., June, 1980. 8. Spangler, Fred I., Fetter, C.W. and Sloey, William E., Phosphorus Accumulation - Discharge Cycles in Marshes , American Water Resources Association, 1977. 9. Tuschall, John R., Brezonik, Patrick L., and Ewel, Katherine C., Tertiary Treatment of Wastewater Using Flow-Through Wetlands Sys- tems , Department of Environmental Engineering Sciences and Center for Wetlands, University of Florida, Gainsville. 10. U.S. EPA, Draft Environmental Impact Statement on the Upgrading of the Boston Metropolitan Area Sewerage System (August 1978). 11. Valielu, Ivan; Vince, Susan and Teal, John M., Assimilation of Sewage by Wetlands , Woods Hole Oceanographic Institution, Woods Hole, MA. 12. Valk, A.G. van der, Baker, James L., Davis, Craig, B., Beer, Craig, E., Natural Freshwater Wetlands as Nitrogen and Phosphorus Traps , Iowa Agriculture and Home Economics Experiment Station, Ames, Iowa. 13. Weber, A. Scott, Tchobanaglous, George, Colt, John E., Aquatic Systems for Secondary and Advanced Treatment of Wastewater , Depart- ment of Civil Engineers, University of California, Davis. B-124 ------- 14. Whigham, Dennis F. and Bayley, Suzanne E., Nutrient Dynamics in Freshwater Wetlands , Chesapeake Bay Center for Environmental Studies and Maryland Coastal Zone Management, Department of Natural Re- sources. 15. Yonika, Donald and Lowry, Dennis, Feasibility Study of Wetland Dis- posal of Wastewater Treatment Plant Effluent , Massachusetts Division of Water Pollution Control, 1979. B—125 ------- ATTACHMENT C WETLANDS DISPOSAL - DEQE CORRESPONDENCE INDEX 4/23/84 Thomas F. McLoughlin, Deputy Commissioner, Mass. DEQE, to Ron Manfredonia, Environmental Evaluation Section, U.S. EPA, re: DEQE review of “Evaluation of Satellite Advanced Wastewater Treatment Facilities Volume II, Boston Harbor (SDEIS)” by CE Maguire, February 1984. 12/29/83 Thomas C. HcMahon, Director, Division of Water Pollution Control Mass. to Walter Newman, Acting Chief, Environmental Evaluation Section, U.S. EPA, re: DWPC review of Quincy Shores Association proposal for satellite treatment plant disposal to wetlands. 12/16/83 Ilyas Bhatti, Director, Division of Water Supply, Mass. DEQE, memorandum to Steve Lipman, Boston Harbor Coordinator, DEQE, re: Division of Water Supply review of satellite treatment plans. B— 126 ------- - elk € ?wQuvea/€ Cf ( 7 of m nmentaI J fzc 1Øa n( of cfn rn.nta aah &y eee 2L 1 of 7V €o d D. sse /4reet .qBoo&* 02108 April 23, 1984 Mr. Ron Manfredonia Re: MDC Environmental Evaluation Section SDEIS, Siting of Wastewater Environmental Protection Agency Treatment Facilities J.F. Kennedy Building Boston, Massachusetts 02203 Dear Mr. Manfredonia: In response to a request from your agency, representatives from the Department of Environmental Quality Engineering (DEQE) have reviewed a report titled: Evaluation of Satellite Advanced Wastewater Treatment Facilities Volume II Boston Harbor Supplemental Draft Environmental Impact Statement Prepared by C.E. Maguire, Inc. February, 1984 C.E. Maguire evaluated two specific satellite options; EMMA recom- mended facilities and Quincy Shore Associates proposal. The report pre- sents a number of specific conclusions and reconmiendations for each option; which are sumarized below: 1) the construction of the proposed satellite facilities for both options will not reduce the size or complexity of necessary harbor treatment facilities; 2) the use of satellite facilties should be reevaluated as a priority in determining a cost effective and equitable solution to future system expansion needs; 3) construction of the satellite facilities would not alleviate the need for planned downstream interceptor relief; 4) direct discharge of AWl effluent to the Neponset River would adver- sely impact water quality, particularly dissolved oxygen; ------- Ron Manfredonia April 23, 1984 Page 2 5) direct discharge of AWl effluent to the Charles River could have potential beneficial impact upon dissolved oxygen but could cause violations of water quality standards at certain times of the year, would exacerbate nuissance algae conditions in downstream reaches and could lead to significant public health impacts upon existing and proposed public water supplies due to the interrelationship of the surface and groundwater within this basin; 6) the discharge of AWl effluent to wetlands which are hydraulicly connected to groundwater aquifers currently utilized as major sour- ces of drinking water poses significant potential public health risks; 7) there are only limited wetlands areas in close proximity to the proposed AWT facilities of sufficient size to accept AWl effluent; and 8) the high’ capital and O/M costs for these AWT facilities are excessive and unjustifiable since there are very few benefits with regard to siting of the harbor facilities. DEQE concurs with these conclusions. Appendix C of this report also contains two policy documents issued by the Department’s Divisions of Water Pollution Control and Water Supply which present detailed analyses of the Quincy Shores Associates proposal. The Department is also in receipt of correspondence from David Standley to EPA dated April 3, 1984, which takes exception to many of the C.E. Maguire conclusions. In particular, Mr. Standley states, “It is therefore, our opinion that ways will have to be found to render the sub- regional approach feasible and acceptable. It appears on first blush that the constraints suggested by DEQE are excessively stringent, and wholly inconsistent with practices elsewhere in the state and nationally. It also appears that aggressive control of non—point sources may be a requisite to off—setting any otherwise unavoidable reductions in in-stream water quality. One step which must be taken and which has been discussed by me with the Massachusetts Division of Water Supply, is the re-evaluation of the need for severely stringent limitations on the discharges from such f ac lii ties • The Department’s Division of Water Pollution Control (DWPC) strongly disagrees with Mr. Standley’s statement that DEQE’s position is excessively stringent and inconsistent with actions in other parts of the Comonwealth. The DWPC’s December 28, 1983, letter (referenced previously) explains that on October 15, 1983, DWPC promugulated a set of comprehensive water pollu- tion control regulations (Title 314 of the Code of Massachusetts Regulations) which includes detailed groundwater quality standards. The Division’s regulatory strategy and requirements are very clear and expli- cit as to how it must relate to the Quincy Shores Associates proposal. (2 ------- Ron Manfredonia April 23, 1984 Page 3 The Division is in the process of permitting all existing and proposed ground- water dischargers and every applicant must comply with the same regulatory requirements no matter where their discharge is located within the Commonwealth. Mr. Standley stated that he has discussed the possible re—evaluation of the “severely stringent limitations on the quality of discharges from such facilities” with the Division of Water Supply. It should be stressed that the only State agency empowered to relax or modify the level of treat- ment for a groundwater discharge is the Division of Water Pollution Control and not the Division of Water Supply. The DWPC’s position has been very clearly delineated in its December 29 correspondence — “The discharge limits would basicly require that the effluent entering onto the wetland meet or e ceed the Primary and Secondary Drinking Water Parameters...”. If you have any questions concerning this correspondence, please con- tact Steven Lipman of my staff at 292-5698. Very truly yours, - Thomas F. McLoughl Deputy Comissioner TFM/SGL/bd cc: David Fierra, EPA Sam Mygatt, MEPA Noel Baratta, MDC Dan O’Brien, MDC Marjorie O’Malley, CZM William Gaughan, DWPC Steven Lipman, DEQE ------- ecu4 CJ C 8 of £ o (a/ J c s Ø ment of &vz o qne zAI c aah 9 AGI ANTHONY D. CORTESE, Sc. D. / ‘ 02108 December 29, 1983 Walter Newman, Acting Chief Re: MDC Environmental Evaluation Section SOEIS, Siting of Environmental Protection Agency Wastewater Treatment J.F.K. Kennedy Building Facilities Boston, MA 02203 Dear Mr. Newman: In response to a request from your agency, the Division of Water Pollution Control, Permits Section has reviewed the proposal by the Quincy Shore Association for subregional wetland application satellite wastewater treatment plants. The proposal calls for the construction of three facifl— ties, one each to be located in the Weymouth Fore River Basin, Neponset River Basin and the Charles River Basin. All three plants would include advanced wastewater treatment processes with discharge of their effluent to major wetland areas which are hydraulicly connected to groundwater aquifers currently being utilized by various municipalities as major sources of drinking water. Information presented to the Division indicates that during recharge periods up to 80% of the effluent discharged to the marshes would enter the groundwater regime and recharçe the subject aquifers. On October 15, 1983 the Division of Water Pollution Control pro- mulgated a set of comprehensive water pollution control regulations (Title 314 of the Code of Massachusetts Regulations) which included detailed groundwater quality standards. These standards define groundwater into these classes (1,2,and 3); Class 1 being defined as “fresh ground waters found in the saturated zone of uncon- solidated deposits or consolidated rock and bed rock and are designated as a source of potable water supply 11 . Since all three proposed discharges will be tributary to groundwater currently being utilized as public water supplies (Class 1), all discharges to said groundwater will be required to meet very strict discharge limits, see attachment #1. The discharge limits would basiclyrequire that the effluent entering onto the wetland meet or exceed the Primary &nd Secondary Drinking Water (30 ------- Walter Newman December 29, 1983 Page 2 Parameters, see attachment #2. In addition, the Division is concerned with the periodic “pass throughH of materials such as oil, heavy metals, solvents, phenols and other highly toxic or contaminating materials which are not substantially removed with conventional wastewater treatment pro- cesses and which could cause severe impacts upon these aquifers. The Division is of the opinion that proper safeguards necessary to continuously meet Class I effluent limitations and to protect these valuable public water suppltes can not be provided. Therefore, the Division strongly discourages the continued review of such subregional facilities as proposed by the Quincy Shore Associates. Ver truly yours, Thomas C. McMahon Director TCM/MP/pnim cc: Sam Mygatt, MEPA David Fierra; EPA Steven Lipman, DEQE William GaughaW, DWPC Marjorie O’Malley, EOEA Noel Baratta, MDC Robert Daylor,Quincy Shores Associates ------- ATTACH! ENT 1 !82 314 CMR: DIVISION OF WATER POLLUTtO; COt TROL 6.07: Application of Standards (1) Ground Water Discharge Permits . No person shall make or permit an outlet for the discharge of sewage or industrial waste or other wastes or the effluent therefrom, into any ground water of the Ccjnmonwealth without first obtaining a permit from the Director of the Division of Water Pollution Control pursuant to 314 CMR 5.00. Said permit shall be issued subject to such conditions as the Director may deem necessary to insure compliance with the standards established in 314 CMR 6.05. Applications for ground- water discharge permits shall be submitted Within times and on forms prescribed by the Director and shall contain such information as he may require. (2) Establishment of Discharge Limits . In regu—. lating discharges of pollutants to ground waters of the Commonwealth, the Division shall limit or prohi- bit such discharges to insure that the quality stan- dards of the receiving waters will be maintained or attained. The determination by the Division of the applicable level of treatment for an individual discharger will be made in the establishment of discharge limits in the individual ground water discharge permit. In establishing effluent limita- tions in the individual permits, the Division must consider natural background conditions, must protect existing adjacent and downgradient uses and must not interfere with the maintenance and attainment of beneficial uses in adjacent and downgradient waters. Toward this end, the Division may provide a reaso- nable margin of safety to account for any lack of knowledge concerning the relationship between the pollutants being discharged and their impact on the quality of the ground waters. (3) For purposes of determining compliance with 314 CMR 6.06(1)aa for toxic pollutants in Class I and Class II ground waters,’ the Division shall use Health Advisories which have been adopted by the Department or EPA. Generally, the level of a toxic pollutant which may result in one additional incident of cancer in 100,000 given a lifetime expo- sure (1O Excess Lifetime Cancer Risk) will be used in determining compliance ñth that secticn of the regu1at on . 1g.. ------- Attachnient ##2 liE; 314 CMR: DIVISION OF WATER POLLUTION CONTROL Parameter Limit 1. Coliform ShaH not be Bacteria discharged in amounts sufficient to render ground waters detrimental to public health, safety or welfare, or impair the ground water for use as a source of potable water. 2. Arsenic Shall not exceed 0.05 mg/i 3. Barium Shall not exceed 1.0 mg/i - 4. Cadmium Shall not exceed 0.01 mg/i 5. Chromium Shall not exceed 0.05 mg/i 6. Fluoride Shall not exceed 2.4 mg/i 7. Lead Shall not exceed 0.05 mg/i (33 ------- I ‘ I 314 CMR: DIVISION OF WATER POLLUTION CONTROL 8. Mercury Shall not exceed 0.002 mg/i 9. Total TrihalamethaneS Shall not exceed 0.1 mg/i 10. Selenium Shall not exceed 0.01 mg/i 11. Silver Shall not exceed 0.05 mg/i 12. Endrin (1,2,3,4,10, Shall not exceed 1O_hexachlOrO_1,7 -eP0xY 1 , 0.0002 mg/i 4,4a,5,6,7,8,9a OCtahYdr0— 1 ,4_endo,efldO_5,8 -dimethaflo naphthal ene) 13. Lindane (1,2,3,4,5, Shall not exceed 6_hexachlorOCYClOhexafle, 0.004 mg/i gamma isomer) 14. MethoxychiOr (1,1,1— Shall not exceed Trichloro—2, 2—bis 0.1 mg/i (p -methoxyphenYl) ethane) 15. Toxaphene (C 1 OH1OC18, Shall not exceed Technical Chlorinated 0.005 mg/i Camphene, 67—69 percent chlorine) 16. ChlorophenoxyS 2,4_D,(2,4 —DiCh1Or0 Shall not exceed phenoxyacetic acid) 0.1 mg/i 2,4,5-TP Silvex (2,4, Shall not exceed 5_TrichlOrOPheflOXY— 0.01 mg/i propionic acid) 17. Radioactivity Shall not exceed the maximum radionuclide con- taminant levels as stated in the National Interim Pr ary Drinking Water Standards. I 3&f ------- 314 CMR: DIVISION OF WATER POLLUTION COr TROL 18. Toxic pollutants Shall not exceed (other than those “Health Advisories .’ listed above) which have been adopted by the Department and/or EPA. A toxic pol- lutant for which there is no avail- able .‘Health Advisory” and for which there is not sufficient data available to the Department for the establishment of a “Health Advisory” will be prohibited from discharge. (b) Secondary effluent limitations for Class I and Class II ground waters . In addition to the effluent limitations in 314 CMR 5.10(3)(a) , the following limitations shall also apply to any discharge from a point source or outlet which enters the saturated zone of, or the unsa- turated zone above, Class I and Class II ground waters. Parameter Limit 1. Copper Shall not exceed 1.0 mg/I 2. Foaming Agents Shall not exceed 1.0 mg/ I 3. Iron Shall not exceed 0.3 mg/l 4. Manganese Shall not exceed 0.05 mg/i 5. Oil and Grease Shall not exceed 15 mgIl 6. pH Shall be in the range of 6.5 to 8.5 standard units 7. Su1f e Sh l1 not exceed 250 mg/i ‘U ------- .1.19 314 CNR: DIVISION OF WATER POLLUTION CONTROL 8. Zinc Shall not exceed 5.0 mg/i 9. All other None in such pollutants concentrations which in the opin- ion of the Director would, impair the ground water for use as a source of potable water or cause or contribute to a condition in contravention of standards for other classified waters of the Commonwealth. Cc) Additional effluent limitations for Class I and Class II ground waters . In addition to the effluent limitations listed in 314 CMR 5.10(3)(a) and (b), the following limitations shall apply to treatment works designed to treat wastewater at flows in excess of 150,000 gallons per day: Parameter Limit 1. Nitrate Nitrogen Shall not exceed (as Nitrogen) 10.0 mg/i 2. Total Nitrogen Shall not exceed (as Nitrogen) 10.0 mg/I Cd) Additional effluent limitations for Class I ground waters . In addition to the effluent limitations in 314 CMR 5.1O(3)(a)(b) and (C) the following limitations shall apply to treat- ment works discharging to Class I ground waters: Parameter Limit 1. Chlorides Shall not exceed 250 mg/I 2. Total Dissolved Shall not exceed Solids 1000 rag/i ------- n Jhe Uom ,ieo,z, 4 eeaJ1/i e / h ,lJJ17c// ,ae(/J ’ c e 0/ lV(2’C71fld(fl( lI iç e/ ailrnent 0/ s uôeonnzentd aat 4 ’ 4Ze9zee2f( 7 .92 3eo 0/ /t te, e. Ji O, . W u’e M, ee t 91a 4n. diLL 02/08 ME MORAN DUM TO: Steve Lipman, Boston Harbor Coordinator FROM: Ilyas Bhatti, Director, Division of Water Supply DATE: December 16, 1983 SUBJECT: Metropolitan District Comission, Southern Sewerage District Wastewater Treatment Facilities Planning Project: The Citizens Plan. The Division of Water Supply (DWS) has reviewed the proposed plan for subregional “satellite” wastewater treatment facilities as part of the general plan for rehabilitating the MDC wastewater treatment system. As the agency responsible for ensuring safe drinking water supplies, we are particularly concerned with the impact these treatment plants could poten- tially have on the water quality of nearby aquifers and wetlands which serve as public water supplies for many communities. Specifically, these areas are: 1. Weymouth Fore River Basin — proposed 8—10 mgd discharge into Broad Meadow, a wetlands of the Cochato River; Cochato and Farm Rivers are diverted to reservoirs for use by Braintree, Randolph, and Holbrook. - 2. Neponset River Basin - proposed discharge of 35 mgd to Fowl Meadows which supplies Canton, Westwood and Dedham. 3. Charles River Basin - proposed 50 mgd discharge into Cow Island Meadows, a wetland in an aquifer area which supplies Dedham, Needham, Wellesley, and Weston. With regard to these sites, the sponsors of the Citizens Plan cla rn that there are several advantages to these projects as compared to the current MDC proposal. The following comments reflect the Division’s con- cern with claims in the proposal that the development of the sateflite ANTHONY 0. GORTESE Sc. 0. COMM,SI, ONER In ------- Memorandum December 16, 1983 Page 2 plants will increase the water quantity and improve the water quality of the water supplies in the 10 affected communities (Brairitree, Randoplh, Holbrook, Canton, Norwood, Westwood, Dedham, Wellesley, Needham, and Weston). Although the Citizens Plan is an innovative proposal for solving the extremely complex problem of dealing with wastewater treatment in the Metropolitan Area and the associated water quality problems in Boston Harbor, its claim with regard to increasing the water quality/quantity j the aformentioned wetlands and aquifers is based on questionable assumptions. As noted in the proposal, wetlands have been studied by many agencies, including DEQE, and are known to have significant capacities to attenuate various types of pollution such as nitrates, phosphates, and heavy metals. Although this feature of wetlands is well documented, the present proposal assumes that wetlands have a limitless capacity to act as “sinks” for con- taminants and that all discharges from the proposed wastewater treatment plants will be “polished” by the assimilative capacity of wetlands. In fact, wetlands have limited capacities to assimilate wastes; unlike treat- ment plants which accelerate the process of waste removal , wetlands recycle and absorb pollutants over a long period. It is difficult o generalize about the capability of wetlands to function as water purification systems. Ultimately, the diversity of the many wetland charateristics will determine their net efficiency to assimi- late sewage contaminants. The vegetative type, rate of flooding, and the area of a wetland will determine: the rate at which pollutants are recycled, the BOO loading tolerance, the sedimentation rate, and the level of bioche- mical degradation. The geographical location of a particular wetland will also markedly affect the seasonal capacity of wetlands to. assimilate wastes. For instance, It is quite possible that the wetlands proposed for discharge in the Citizen’s Plan would freeze during certain periods of the year which would inhibit even the mechanical, primary treatment function of plant screening and particulate sedimentation. Aside from the problems associated with determining the assimilative capacity of wetlands for pollutants, this proposal does not address other potential water quality problems. For instance, the proposal does not address the fact that very little control exists over the nature and quality of sewage. Presently, the regulatory manpower does not exist for monitoring illegal or haphazard industrial waste disposal. Many industrial contaminants cannot be detected, let alone treated, in standard wastewater treatment facilities. As a result it is very likely that discharges from the proposed “satellite” plants would ultimately result in the degradation of existing water quality in the receiving wetlands/aquifer. All things considered, water qualit.y degradation is likely to occur either over the ------- Memorandum December 16, 1983 Page 3 short term through problems associated with seasonal flooding/freezing of the wetland and/or the undetected discharge of a harzardous substance, or over the long—term by the gradual saturation of the assimilative capacity of the wetland. Because of these uncertainties, and the problems that may ensue, the DWS must conclude that the Citizens Plan proposal for wastewater discharge into wetlands is an unacceptable risk for potentially degrading these vital existing drinking water supplies. ------- ATTACHMENT D INFLOW/INFILTRATION PRELIMINARY REPORT TO PROF. CHARLES M. HAAR (submitted by Massachusetts Executive Office of Environmental Affairs) B-140 ------- 5Ae imcnc áa&/i c/c cicAa et’ i I ? .1 9 cec(a i . (. i/cce C 7 (3ii i C) .GiI11ZC1lt ((t . ;i! , ) (_12 / (j1 ?j Y;ii 100 ‘l2’(VE Y((/9C J/i’ 1 cd CONE g c :t ,fl, .,ac%u t6 02202 . GE’ ENT Dec ber 2, 1983 ?rc essor Charles . Haar 3C0 Griswald Hall arvard Law School C bridge, 02138 Re: Quiicv v MDC . Schedule Item: Pro:ess r Haa:: closed is the prel inary report on 1/I r oval. Sincerely, Wiliia.. Lahevt Counsel f — ,- ‘- ! :: — L: be r. cc: Peter L. Koff L ’t Ralph A. Child E. :iichael Slo an Steien C. Horowitz — Jeiferv Fo 1ev L#s’” -— .ls. Laura St irberg - , . . .. — Willia C. Golden t 1 Stephen C. Karnas SteDhen P. Eur av - .- Stev L an . ,N1 CC uL EL 141 ------- December 2. 1983 Procedural Order — Item #5. BANKING/TRADING AND GREATER THAN 2 FOR 1 PR0 RAM Item #5 of the Procedural Order requires that DEQE assess the feasibi- lity of a Banking and Trading System and a greater than 2 for 1 sewer extension permit program. This document not only provides the Court with those feasibility assessments but attempts to develop a basis for an expanded discussion of the need for an integrated approach to all iir related items contained in the Procedural Order. It is our intention to use this expanded discussion document to hopefully stimulate fresh approaches to these technically and politically complex issues. This document should not be viewed as a DEQE position paper but as a discussion document and comments are not only welcomed but strongly requested. In order to assess either of these programs adequately one must con- duct such an assessment in the context of DEQE and MDC’s overall efforts to deal with the entire sewerage system and its myraidof prQblems.. Within the MDC regional sewer system there currently exists 5,430 miles of municipal sewers, 228 miles of MDC sewers, approximately 3,000 miles of privately owned house laterals, over 70,000 manholes, 10 MDC pumping stations and numerous municipal and privately owned pumping sta- tions. Large sections of the North System have combined sewer/drain faci- lities and literally thbusands of cross connections or interconnections exist within the sewers and drains tributary to both the F orth and South Systems. Also various exfiltrating sewers are underdrained with small diameter perforated pipe which discharge to adjacent watercourses. Extensive gauging or flow monitoring facilities currently do not exist within eithe ’ the MDC or municipal sewerage systems and therefore tliire is very little historical data concerning the distribution of wastewater within this maze of pipes, pumping stations, diversion structures, treat- ment plants and overflow facilities. Due to the nature of the segmented ownership of these facilities, management of flows into the system is extremely difficult to control and monitor. Infiltration and inflow (I/I) within this system is a very signi- ficant flow component (estimated to be over 50% of the average monthly flow). It must be e iiphasized that I/I is not peculiar to the 1DC system but also exists in large amounts in all sewer systems particularly older systems. Others have statea that if I/I could be significantly reduced, many of the system problems could be solved without the construction of new relief sewers, pumping stations or expanded treatment plants. There is no question that I/I reduction could aid in these efforts, particularly with regard to localized surcharging and overflows, but it is ot a panacea to the problems of the MDC system or pollution of Boston Harbor. Iq 2 ------- I/I within the MDC system has been extensively investigated with millions of dollars expended to date in •this effort. Due to the length of time needed to complete the study and design phases of the I/I program, very few communities within the MDC have actually begun the physical reconstruction phase of the I/I program. Therefore, relatively little I/I removal has been achieved to date even though a great deal of effort and money has been expanded by local and federal agencies on this program. Rehabilitation projects have been completed, are under construction or soon to be initiated within seven (7) MDC municipalities and are expected to remove 30 MGD of I/I from the sewerage systems (3.6 MGD within the South System and 26.5 MGO within the North System). Unfortunately I/I studies and rehabilitation programs are more of an art than a science and this program is receiving extensive national reex— mination by the EPA, consulting engineering firms, I/I gauging and rehabi- litation firms,, major municipal sewer authorities, and state agencies. This review is in large measure due to the demonstrated inability of com- munities to reduce lit rates to those originally assumed to be realistic (and often mandated). During 1979 and 1980 EPA funded a major study to examine the level of success of it Construction Grants I/I Rehabilitation Program. The results showed that of the nineteen (19) con nunities studied, none had attained the assumed levels of I/I reduction and many had not reduced 1,/I at all despite extensive reconstruction efforts. The study concluded that current I/I determination and rehabilitation techniques generally will not result in substantial system I/I flow reductions: This study further recommended nine (9) major revisions to the EPA I/I program (See attachment #1). — During the past seven years numerous I/I studies have been performed within the overall MDC system by various consulting fir as. It is very dif- ficult to compare the results of the varoius studies to each other and often impossible to even correlate the results of Phase I and Phase II I/I studies within a single community conducted during consecutive years by the same consultant. The MDC has performed 2 system—wide I/I studies, (North System performed during 1978 by Camp, Dresser & McKee and the South System performed during 1979 by Fay, Spofford, and Thorndike), plus 7 system component I/I studies by 6 different firms for individual projects such as the Framingham Interceptor, Fore River Siphon, etc. Of the 43 member municipalities, 25 have already performed additional 1/I studies utilizing 11 different consulting firms. All these studies were required to comply with the EPA cost-effectiveness guidelines which resulted in significant amounts of I/I not being cost-effective for removal due to comparatively low transporation and treatment costs for the MDC system. Therefore, projects which have progressed into the Phase II — Sewer System Evaluation Survey Phase, Design Phase or construction Phase are skewed towards removal of I/I to the point where the EPA regulations deem the I/I com7onent of total flow to a treatment facility This approach does not emphasize significant elimination or reduction of I/I through continued and routine maintenance of a sewer system, but rather one- time repairs or replacement of sewers which may or may not have a lasting effect in reducing I/I system—wide. ------- —3— Problems in the MDC Sewer System can be classified as: 1) ACUTE — Conditions which can lead to direct public health impacts such as sewage overflows into recreational areas, shellfish areas, and public water supplies and back—ups into homes; and 2) CHRONIC — Conditions such as sewer surcharging leading to flow restrictions, reduced pollutant removal efficiencies at treatment facilities, and overflows to watercourses in non—critical areas. DEQE believes that there is room for improvement fri the treatment of both acute and chronic problems, but the appropriate remedies are not necessarily the same. Past practice : A) DEQE has utilized enforcement action (sewer bans, monitoring, two for one, holding tanks, etc.) to address ACUTE problems. It is our opinion that a degree of success has been reached but still more can be done to identify problem areas and initiate enforcement action which would utilize the existing array of possible remedies and tailor specific remedies to particular situations. B) DEQE has utilized a format of developing a Memorandum of Understanding (orginally signed on April 13, 1982) between its Division of Water Pollution Control and the MDC to prioritize major water pollution abatement projects, develop compliance schedules and allo- cate federal/state grdnts as a primary remedy for the CHRONIC problems of the MDC system. We now recognize that an effective remedy to the CHROIfiC problems must also include other elements beyond the construction grants project list. The remedy f r the CHRONIC problems must include an organized, structured, long term approach to reducing extraneous flow of “clean water into the entire MDC system. During August and September the Division of Water Pollution Control (DWPC) developed interim maximum I/I removal rates for each MDC member corn— munityas required by the Court. Since these rates had to be developed during a very short period of time, DWPC had to assume across—the—board— removal rates (30% and 50% reduction in infiltration and inflow respec- tively were chosen) for each corrmunity based upon the flow studies available at the time. This analysis indicated that 110 - G0 and 80 MGI) could possibly be removed from the South and North System respectively if 30% and 50% reduction could be obtained in each community along with a source of monies to fund this extensive work (estimated at 5100 million)., It was never the Department’s intent to indicate that this level of I/I reduction was easily obtainable, cost effective, or could be instituted within a short period of time. The following are some of the major problems and uncertaintieswhich we believe stand in the way of instituting any program to deal with the Chronic problems within the South System (similar problems exist within the Uorth System): ! ‘!‘1 ------- -4 - 1) It has been estimated that total flows in excess of 450 MGD enter various sections of the South System at any one time; 2) The theoretical maximum flow reduction within the system has •been estimated at 110 MGD assuming across—the—board reduc- tions of Infiltration by 30% and Inflow by 50%; 3) The major constriction within the conveyance and treatment facilities are the High Level Sewer with a peak capacity of 310 MGO and the Nut Island Treatment Plant with a peak capa- city of 250 MGD. Flows cannot be reduced to these levels even if the theoretical maximum I/I reduction rates were attained; 4) The estimated cost for removal of 110 MGO is $60 million, if 30% & 50% reductions could be obtained in afl con nunities; 5) Current state—of—the—art hI reduction practices indicate a significantly lower I/I removal capability (15% total I/I reduction); 6) It is uncertain whether current I/I reduction techniques withstand the passage of time. Rehabilitated sewer lines rr.ay quickly revert to prior conditions and other currently nan— leaking sewer segments may begin to leak as the lines detertGrate with age; 7) Current information indicates that as much as 50% ofall infiltration within a sewer system originates from privately owned 3 or 4 inch house connections (pipe connecting the building to the street sewer); 8) Various Iii experts now belive that “allowable” non—cost— effective I/I rates for a community may be as high as 10,000 gallons per day/inch/mile of pipe (gpd-.in—mi) instead of 6,000 gpd-in—mi currently being used by EPA and 1,500 gpd—in— mi which was originally used by EPA. If the 10,000 gpd—in—rrii figure is used as a cut—off point for further I/I work, a review of the existing I/I rates for Southern System Comnunities (attachment 2) indicates that only Boston, Dedham, and Hingham would require I/I reduction. 9) Since all prior I/I studies were performed utilizing the EPA cost-effectiveness program;many if not all the prior studies will need to be revised. This may also require additional flow monitoring to supplement prior monitoring data. This monitoring work can only be performed during high groundwater (“hunting”) periods and such revision to any of the existing studies could add approximately two years to their completion times; and ------- —5— 10) We currently have• no methods of monitoring total system flows, flows from each municipality, loss of flow due to localized overflows, etc. Any attempt to develop maximum I/I rates for each municipality in order to Hsolve all of the many problems experienced in the MDC and local sewer systems (i.e. surcharging and overflows, downstrean constrictions in MDC trunk sewers, overloading of pumping stations, hydraulic overloading of the treatment plant and pollution abatement within Boston Harbor) with the existing information is like trying to fine-tune a piano when half the keys are missing. In order to resolve some of these uncertainties and to begin the deve- lopment of an effective system-wide approach to the chronic problems of the MDC, the Department is undertaking the following: 1) The DEQE sent two staff engineers to New Jersey during August to attend a nationi EPA—sponsored seminar titled ANew Concepts fl I/I Evaluation and Sewer Syste m Rehabilitation”; 2) DEQE has formed an internal task force to devise a consistent statewide policy on I/I, specifically to address the recent development of and revision to state—of—the—art rehabilita- tion techniques as enumerated at the above discussed EPA seminar; 3) DEQE is in the process of developing a Technical Advisory Group to work with us to develo an acceptable and implemen— table 1!rprogram for the MDC system. Our preliminary idea for membership of this group is to have one representative from the following: DEQE, MDC, BWSC, EPA, Quincy , a North System Community, a South System Community, engineering con- sultant, sewer rehabilitation company and developer/home builder. This would provide for a workable 10 member tech- nical committee. We would also be requestino that each member representing a larger grouping develop an extended corm ittee to whom they could report in order to ensure a wide dissemination of data. 4) DEQE recently held an interagency seminar on I/I at which Gerald Conklin, a well known expert on state—of—the—art Iii rehabilitation techniques, explained the results of a study the firm Dufresne — Henry performed for the EPA; 5) DEQE has sent letters to Region 1 and Washington EPA strongly requesting that EPA hold the New Jersey seminar in Boston so that a thorough discussion could be held with all parties to the court suit. EPA recently indicated to DEQE that they could probably fund this seminar; 6) DEQE has contacted Michael Bonk from the Washington South Suburban Sanitary District requesting permission for members of cur I/I Task Force to visit their facility and discuss their extensive experience in I/-I rehabilitation programs. This meeting has been tentatively sheduled for December 6 and 7. ------- -6’ 7) DEQE filed legislation seeking $100 million in state funding for I/I rehabilitation programs which includes a section which would allow DEQE to fund a system—wide flow gauging and monitoring system for the MDC; 8) DEQE is in the process of entering into a S39,000 contract with a well known consulting firm to review all I/I data within the MDC’S South System and to recommend an action plan with regard to I/I reduction for the MDC. 9) DEQE plans to send correspondence to many of the MDC’s member communities (letters already sent to Hingharn, Stoughton, Westwood, Needham, Randolph, Quincy, Framingham, Natick, Ashland, and Brookline) requesting their attendance at indi- vidual meetings to discuss the additional I/I work that they- will be required to perform. DEQE believes that there must be a system—wide commitment for the development and implementation of an integrated MDC sewer management program. This program must include the provision for adequately sized transmission and treatment facilities; a realistic I/I program; on—going municipal sewer maintenance, effective sewer permit program and system—wide flow monitoring. These five items will be discussed in greater detail in a later section of this document. - . These actions the Department has taken and plans to undertake are based on our conclus4ons that the first priority in developing a new and effective approach to solving the system—wide problems of the MDC is an educational process for all concerned parties. The need for this educa— tional process is a result of our review of our efforts, and those of EPA and other major metropolitan sewer systems in dealing with I/I. By recognizing past successes and failures, becoming familiar with new state— of-the-art methods for dealing with I/I, and reviewing this information and obtaining the advice of the Technical Advisory Group, we will have the opportunity for the first time to devise an effective and workable system— wide solution to the MDC’S problems. Because we haven’t yet completed that educational process, or formed of the Technical Advisory Group, which we feel is essential in deve- loping a program which has the support and endorsement of all concerned in the operation of the MDC system, we cannot now recommend a detailed approach to solving the I/I problems, or what the mix of technical, funding and administrative or enforcement mechanisms should be in such a program. However, we have developed some basic concepts about what an effective system must include and have reviewed the concepts of banking and trading and expanded 2 for 1 program as they might be part of this overall solu- tion. We offer our conTnents on banking/trading and 2 for 1 and our thoughts on the minimal components of an integrated MDC system management program for the consideration and use af the Technical Advisory Group, the Court and all parties as a first step in devising an effective program. ------- -.7— Banking and Trading DEQE has closely reviewed the feasibility of various types of banking/trading systems, the two major catorgories being TM private capital systems” and a “central bank”. A workable banking/trading system must meet the following minimum criteria: 1) Access to the system must be readily available to all who want or need to participate; 2) I/I reductions for which credits are granted should be verifiable; 3) I/I reductions should be permanent and enforceable; and 4) I/I reductions should be exchangeable in a way that is meaningful in terms of system-wide conditions. An examination of the MDC I/I situation indicates that a private capital banking/trading system is unli- kely to be successful in meeting these criteria. A “private capital” system is one in which private developers wishing to obtain sewer connection permits would either directly produce reductions in I/I or purchase reductions from other private or public enti- ties who had performed work necessary to remove I/I. Credits could be “stored” in a bank or privately held under such a system. A “central bank” system is one in which reduction credits are created by the bank (an existing or new public entity or quasi—public entity) only, then sold to developers who need connection permits. A. Access to system . Perhaps the most fundamental barrier to a private capital system is that access to that system is constricted and complex. The sewerage system is made up of several layers of ownership: MDC sewers; municipal sewers; and private laterals. Obtaining necessary permission to perform work within such a system requires several steps: site selection, ownership determination, and securing necessary approvals from several sources. Municipalities may be unable or unwilling to grant access under the terms of their easements; individuals may deny access necessary to disconnect unauthorized laterals or remove sumnp pumps. Apportioning potential tort liability will complicate the system further. Finally, all of these barriers may be compounded by interjurisdictional problems. In some municipalities reductions may be difficult or impossible to achieve, causing developers to seek credits through reductions in other jurisdictions. Some municipalities may be reluctant to encourage develop- ment outside of their boundaries by allowing such work. Lack of technical expertise may be another significant barrier. - In brief, access to the reduction credit system would be con- siderably constrained and many potential entrants may be excluded. The same set of barriers makes it unlikely that their will be many “speculators” who will produce credits for sale to developers. By contrast, a central bank system does not necessarily pose such barriers to access. To some extent, the same impediments to the creation of I/I reduction credits exist; however, they are less severe because the process could be centralized in a public or quasi-public entity which might be able to secure necessar ’ access rights through specific enabling legislation. More importantly, these barriers would not bar access into the system by those iishing to purchase credits, as the purchase of credits from the central bank requires only a cash exchange. 1*? ------- -8- B.•Verification : Verification issues, though chiefly technical, have significant structural ramifications. The technical problem posed by the preseiit condition of the sewerage syste n are multifold, but for purpose of this discussion can be sum- marized as follows. Because there is no effective flow moni- toring facilities within either the MDC or its tributary member system, it is extremely difficult to measure accurately either a baseline for I/I removal in specific locations or the amount removed. In addition, a gallon of Ill removed from one point does not necessarily represent a gallon removed from the system as a whole. The impact of this situation on a private capital banking/trading system is that realistic verification of I/I removal is virtually unob- tainable and reductiop would be ephemeral. Realistic verification would - require Department monitoring before and after each reduction, at all sites selected by those attempting removal. The Department does not currently have the staff or equipment to perform such monitoring tasks and the required resources would be excessive compared to the potential benefits. Even rough calculations based on total flow would be of little use because it would be necessary to apportion specific amounts of reduction credit to individual projects which would be occuring continually throughout the sewerage system if the banking/trading system were to function properly. A workable system with unverifiable reduction credits would be difficult if not impossible to establish and certainly impossible to administer equitably. The same fechnical problems confront a central bank system, but the structure of a central system offers the possibility that they-might be manageable. Because credits would only be created through projects coor- dinated centrally, baseline and post-project monitoring are more feasible. Rather than isolated projects chosen by developers scattered throughout the system, target areas can be selected for ru removal and some determination made of the effects of the work on the system. Because afl credits created go into the central bank, it is not necessary to apportion system—wide (or sub—system—wide) credits among different projects. Credit allowances, though not completely quantifiable would at least be more consistent; making the system more equitable and more likely to obtain the desired results. C. Enforceability . The technical and structural issues con- cerning the enforceability of I/I reduction are inextricably linked to those of verification. Thus, the same problems outlined above affect this criterion as well. Adding to these problems is the need for some sort of permanence to the reductions obtained; i.e. removal of I/I must be effec- tive for some specified period of time, or credits would be meaningless. This concern requires the maintenance of that work, throughout the life of the credit. A private capital system poses serious enforcement problems from this standpoint. Quality assurance would require constant Departmental presence at all projects. Requiring de elopers to return to removal sites to perform maintenance work would be extremely difficult in practical terms. The Department currently lacis the resources to perform either of these functions. ------- -9— Again, a central bank system might be able to minimize some of these difficulties. Both quality control and maintenance could be assured more effectively by centralizing remova work. There is less likelihood of either fraud or inadequate performance and as a result, such a system would be more equitable and reliable. 0.. Credit exchange . The premise of the banking/trading systerri is that I/I removal credits are both fungible and adequate to allow for added new flow; in other words removal credits should be interchangeable both with other removals and with added new flows elsewhere in the sewerage system, regardless of time. A private capital banking/trading system assu- mes that these units are interchangeable and in terms of the banking/trading system only , this assumption is not unreasonable. However, in terms of the sewerage system the assumption is false, and a system based on it would be ineffective for solving the underlying problems of the sewerage system. Equal volume removal credits are not fungible for several reasons, including timing of flow concentrationS, location within the system or sub—system and likelihood that I/I removed from one point will enter (in some proportion) at another or cause flooding. If the effectiveness of removal measures deteriorates over time, I/I reduction credits in the bank must also be devalued in the same ratio.. The wider the system and the more variation in conditions the greater the likelihood of incompatibility of removal credits. Moreover, some of the MDC component systems are fairly “tight”, while others offer good oppor- tunities for I/I removal and still others may present flow problems that should be solved in other ways . I/I removal actions also differ in cost— effectiveness (in real terms, as opposed to EPA’s grant-related criteria for cost—effectiveness). The implications of the technical sewerage issues for the banking/trading system strongly suggest that the only type of implementable system is a central bank. A central bank system would focus I/I removal efforts on target areas where I/I removal is most useful from a system—wide viewpoint. The compatibility of removal credits with each other or with proposed additional flows could be judged technically and adjustments in the amount of credit allowed or needed for a particular project could be made. It should be easier to establish sub—systems in which trading of credits could occur. For example, credits neededfor North System connec- tions should be based on North System removal. It may also be necessary to further restrict the transfer area to sub—system levels. Conclusions . Considering the four criteria of market access, verification of removal credits, enforceability, and exchangeability of removal credits from the standpoint of the sewerage system as a whole, a central bank system seems to offer considerable advantages over a private capital system of banking and trading I/I removal. The apparent advantage of mobilizing private capital to address the I/I problem suggested by a private capital banking/trading system is minimal, particularly since the same amount of capital could be generated through the sale of removal cre- dits created by a central bank and the resources could be directed more effectivly with a centralized structure. ,s b ------- -10- Nevertheless, adoption of a centralized banking and trading structure would not solve the underlying technica] problems. In particular, the absence of effective flow monitoring capability within the system, and the practical difficulties inherent in effectively removing I/I (see d scus io below), seriously weakens any banking and trading system. The central bank alternative would obviously require enabling legisla- tion. This legislation would both establish the bank and the basic trading rules and provide an initial funding resource. One major policy issue that should be addressed if establishment of such a system is proposed is the extent to which both start-up and future costs should be borne by the public at large and what portion should be borne by those seeking to purchase credits. Should the entire burden be placed on “new development” or should some portion of the burden be shared by existing system users. Greater Than 2 For 1 Program There appears to be some confusion by the Court as to the intent of the DWPC’s existing 2 for 1 program and whether that program could be used to jjgnificantly reduce I/I in the MDC system. The program was never intended to replace the Commonwealth’s Construction Grants Program which has been providing large amounts of money to communities for work such as sewer rehabilitation and I/I projects. The sewer ban and resultant 2 for 1 program was devised as an enforcement tool to get the particular community’s “attention”. Some people have used the following analogy to describe the program: “it is like hitting the community in the face with a two-by—four to get their attention and then once their attention is assured, develop a rasonably implementable method for reviewing, revising and approving sewer extensions while not exacerbating flow problems within the localized sewer system”. To date there are 9 communities on the 2 for 1 program and several others are under review. Since the implementation of the program in 1980 approximately 5.5 million gallons of flow have been listed as possibly being removed from the sewer system. In affidavits presented to the Court, DWPC stated that even if all I/I specified as being removed from the system was in fact removed, it would take over thirty (30) years to reduce the South System flows by 60 MGD using the same 2 for 1 format and assuming similar numbers of yearly permit applications. The 2 for 1 program is even less likely to significantly reduce flows to the sewer system as the town— wide I/I rehabilitation programs previously attempted by the EPA. In fact the “hunt and seek method” used by developers to find and repair isolated sources of I/I to justify connection of a new building is precisely the type of I/I rehabilitation procedure that all experts have denounced as unworkable. Professor Haar stated in his Masters Report the following with regard to the current 2 for 1 program: “The 2:1 reduction program is an interim remedy. Although it will not result in the sane kind of significant flow reductions as will the planned system- iide infiltration/inflow reduction program it will provide relief since, without it, new additions will exacerbate the current /5/ ------- —11— failures of the system. While hot bringing about large improvements, it will prevent the situation from deteriorating further in the near future. It can be initiated immediately and can maintain the status quo or even slightly lesson the frequency and/or the level of treatment bypasses while the longer—term remedy of a planned system-wide infiltration/inflow program can be increased by changing the present ratio 2:1 to require a removal of three or even four units of infiltration/inflow for every new unit of flow added to the system. It is thus possible to design the program in an equitable and effi- cient manner. The DWPC has the authority to impose such a program on MDC member communities. Experience with jndividual communities has shown that development typically does not stop and that infiltration/inflow is removed as a result of the imposition of such programs. Therefore, the 2:1 reduction program is an appropriate interlocutory remedy to be imposed by the Court.” - DEQE believes that just increasing the percentage removals of I/I from the current 2 for 1 to 3 or 4 for 1 will have no measurable impact on bypassing and overflows into Boston Harbor. We do believe that the sewer ban and 2 for 1 program is effective in forcing a corrniunity to deal with its sewage problems and provides a framework for closer coordination be- tween DEQE, the municipality and the development community. Therefore, DEQE proposes to continue with the current 2 for 1 reduc- tion percentage as part of its enforcement actions in cornnunities with acute problems. However, the continued use and effectiveness of this enforcement mechanism iill be closely reviewed in conjunction with the development of a system—wide approach for dealing with I/I in the MDC system, which is discussed below. If the system-wide approach offers more effective alternatives to permanent removal of I/I, the use of the 2 for 1 program as an enforcement tool may be altered or discontinued. Integrated Sewer Management Program There must be a system-wide commitment for the develapment and imple- mentation of an integrated MDC sewer management program. This program must include at a minimum: 1) Provision of transmission, pumping and treatment facilities with adequate capacity for the MDC system; 2) A realistic on-going I/I reduction program; 3) An effective sewer extension and permitting program; 4) An on—going municipal sewer maintenance/rehabilitation program for all communities within the MDC system; and 5) A system-wide flow monitoring network. We further believe that these five program elements can be implemented and that much of it is currently on—going as specified below: ici ------- —12— 1) Capacity : The MDC. and many of its member communities are .already implementing this program with such projects as the Nut Island and Deer Island Primary Upgradings, East Boston Pumping Station, Framingham Interceptor, Charlestown Pumping Station, etc. The Procedural Order Item #23 tracks the compliance for most of these ongoing projects. 2) I/I Reduction : The Departement plans to utilize the $100 million grants program (if enacted) to develop a state—of—the— art I/I rehabilitation program which could remove DEQE from the artificial cost effectiveness regulations required for the expenditure of EPA grant monies. We would like to be able to define major problem neighborhoods and rehabilitate all sewers and associated facilities within the entire area with pre— and post— flow gauging. Based upon the effectiveness of those projects we would develop a priority rating system for the entire MDC system and begin funding neighborhood reduction projects. 3) Permits : DEQE has developed an interim program to ensure ade- quate reviews of all permits within the MDC service area. DWPC has sent requests to all South System municipalities requesting copies of all building permits issued by them from January 1982 to the present. This data will be cross—checked against Sewer Extension Permit Applications to determine the extent of compliance with our regulations. An extensive educ— tional program has also been initiated by DWPC to help ensure compliance with our permitting program. 4) Ongoing Municipal Rehabilitation : This is the most difficult aspect to control and enforce since it is strictly a local function with no state or federal regulations mandating the nature and extent of such work and no outside funding sources available to the municipality to offset the costs. A thorough sewer maintenance program would require the expenditure of significant amounts of local monies. Due to the current financial constraints imposed upon the municipal governments and the constraints upon new state regulations that increase costs imposed by the Proposition 2 tax cap legislation, it can almost be guaranteed that any type of elective expen- ditures (preventive maintenance) will not take place. DEQE believes that this type of work will become much more attrac- tive to the municipalities if a method of assessment versus flows is devised and implemented by MDC. Also under existing regulations (MDC regulations and most local sewer ordinances) it is presently illegal to discharge clean water (vooling water, storm water, or groundwater) to the sanitary sewer systems. However these regulations are not strictly or actively enforced in most cases. Any preventive manintenance program should be “supported” by a strong enfor— cent program conducted at the local, district (MDC) and state (DEQE) levels aimed at eliminating to the maxir in extent feasible illegal connec- tions of clean water into the 1 .100 and member communities sewer systems. ------- -13— Enforcernent activities would be cohducted by parties such as the MDC Industrial Section; local public works departments, building and plumbing inspection personnel; with general oversight by the DEQE — DWPC. The system—wide monitoring capability would be used to target priority areas for enforcement and investigations; to evaluate results and to monitor the possibility or reconnection. Available penalties would be examined and modifications proposed where appropriate. 5) Systenwide Flow Monitoring Network : The capability to monitor and evaluate flow continuously throughout the MDC system and at strategic locations within its member municipal systems is essential to the proposed program of minimizing extraneous flow in the system. The information gained through this capa- bility could be utilized: a) in both the Federal and State Grants Program for setting priorities for funding and eva- luation of construction and rehabilitation work; b) in the Enforcement Program to identify prime areas for investigation of illegal connections; and c) on the Incentive Program in establishing the flow upon which sewer charges will be based. Continuous system-wide flow monitoring capability is a prere- quisite for implementation of the proposed flow based sewer charge system and for a realistic banking and trading system.. In summary we wish to again stress our belief that an intergrated approach to the regional sewerage system difficulties is needed. The only way to develop such an approach is to jointly educate all participants (State Agencies, Municipal Officials, Area Legislators, etc.) in the various facets of th. process. We do not want to blindly grab onto one or a combination of quick—fix alternatives. Our own experiences with the 2 for 1 program is a perfect example . Our agency saw the program as a readily enforceable and implementable method of reducing flows in the local and MDC sewerage system to mitigate sewer overflows and surcharging while allowing for reasonable continued growth to occur. DEQE, like EPA, assumed that I/I reduction techniques used in the late 70’s and early 80’s actually removed a significant percentage of I/I. We have recently learned that such an assumption was incorrect to a large extent. The development of our proposed Technical Advisory Group, can be used as a spring board to begin this eductional process. ------- ,‘ tzacnment £ :v u ticm o? Infjltratjo:i/Infiow ina2 , ?c ort July 1960 U.S. Erwiron enta1 Protection Age cv C iAPTER 4 RECO &MENDATIONS C N Z’ AL The findings’of this.study indicate that Sewer Syste 4 -a Evalua- tion and Rehabilitation generally does not result in sub—- st r.tia1 system I/I flow reductions. The consecuence of tnis s that returning I/I has used u all or substa a1 port onscz tne reserve capacity of new and u graded. treat jtent facil tjes and thus, shortened the plants’ desjcn lives.. I/I is not going to ‘be removed., by i ’gnori it ’;-- Thus;—it. is -— essantLal that it be evaluated in order that sewerage works can b designed and operated effectively. The following reconmandations are offered as possible courses of action that EPA can undertake in order to ensure that /: is effectively addressed in design and o era ions of s : rage works. These recommendations ozzer a variety of choices that could be implemented. Some recommendations id be imole ented together while others could not_ A dLscu sion is presented with each reco mend tion. :2C -:Z DATION l REVISE THE I/I PROGRP METHODOLOGY, —k’ - i J.. The existing 1/1 ?rogra methodology simply has not achieved ex?ected results. It has become evident that successful r ilitation is more of an exception than a general case; ju3t the opposite of what was assumed when the I/I Pi’cgram ;.: s initiated. If the I/I Program is to be continues. the th dology must be revised. The follo :ing arc some of the possible changes to Ser System Evaluations that would provide more realistic initial. data, thus, resulting in more successful projects.—- - Star,!ardize cuantificazion of system-vide I/I .. Cr :1y, a :idc variety o para ctE .:s are uS2d in design a cost ef ctiv€ czs analyses : or t- :7 1 flo.; c c t: i.e. wc-t on !/I, ak de..; I/I, I/I at 10:2 v r - This c’..’ t cc’ tllv C5 ifl- t-C . :stc . E nd. tO DrOV1(F . e 1t . ‘ di c T c.o z effr. :iv- : a1”:.: : ,:r .. . r’ cr I,’i ‘ :c. 1t : ‘.-l”.. - ------- I/I flow monitoring and televisicn ins ectioa use be rformed during wet weather and/or high ground- water condItj n (I/I Hunting Season). This study h z found that in many instances t l vjsjo inspec- tion was not performed during peak high groundwater conditions. Any leaks observed froni manholes, sewers and house service connections were factored up to re- flect. oeak flows. This practice has resulted in er- roneous flow estimates from oinz Sources. It is imperative that flow monitoring and television inspec- tion be performed during a specific “hunting season”. - This can be defined by using a specific systen total flow parameter: for exa ple, three (3) tin .es -base flow, or a system I/I rate greater than 6,000 gallons per day per in-mile. Establish a realistic system ItT rate to be used as a cut-off for projects to proceed to Sewer System Evaluation Surveys, ie., 6,000 gallons per day per i nôh mile - - s??. established an infiltration rate of 1,500 pd/i mile including service connections in its P?2 i7 —lO - Any rate be1o ; this value was considered non—excessive This study has fo md that most of the projects had pr -rehabilitatL n high week I/I rates exceeding 6,000 g dfin-rnile. Post rehabilitazjon high week I/ rates were reduced from above to below 6,000 c /in-rnjje in only one (1) project. t may be pos— sibi that cost-effective rehabilitation work can be a hi ved in sewer syStems with ore—rehabilitation ii : :z be2.ow 6,000 gpd/ n-znile, uz cnancas 0: SUCCeSS be rninL- al. Establjshi ent of a cut—off-I/I rate of, say, 6,000 cpd/in-mjle could sosed uo many projects, and result in more successful rehabilita- tion. I c’ude lir it d t levjsjon insoaction and rain al1 sL - u1aticn work in the I/I Analysis Phase. - In the I/I Analysis Phase, estirn3tes of I/I to be rcmo;ed are made, rehabilita ion progr s projected and cost—effectjvene s estimated. All this is done withctut firm documantation of where the I/I is coming fom. This stu:y has rour.a that a major source 01 - i/I is house service connections, and the flow frotn Is.’, ------- this •sourco is not detectable i e:- x/z Ana1y is Phase. In most instances, the :10w easured or estimated during this Phase erronecuslv assu ries that most of tha I/I .s fron manholes or sewer l saes, and the resulting recoxr ended I/I. remcvals via sewer line rehabilitation looks attractive: If limited television insoection identit d s ecific sot rces, a more rea1 .st .ce rehabiJ. tation pro;ra could e out— lined. Performing limited television insoection of say , 2 to 5% of the system,and possibly limited rainfall simulation where inficu is suspeoted . during the I/I Analysis Phase would result in more realistic conclusions of this Phase of work. Consider the impact of ±/1 from house sevice connec— tion and groundwater migrationafte sewer line rehabilitation. This study h s found that estimates of I/I to be re- duced by rehabilitation generally have been in the 60 to 90% range, while actual reductions have generally been in the 0 to 30% range. In addition, during cost effectiveness analysis no consideration is given for m grat on oz groundwater to non-:ena 1 za ted sources. The percent I/I reduction achievable by r.ain barrel sewer line rehabilitation, including test and seal programs, is dependent on one (1) par— ameter more so than any other: the percentage of 1/I coming fran rain barrel defects versus the pecentage coming from house service connections. etelevisina curing th .s stucy found tnat I/I aces c2grate to nOn— rehabilitated sources, and that rehabilitated sewers wi ere le ss than 60% of the pre-rehabilitetion I/I was documented coming from sewer joint leaks (versus :r ouse service connections) achieved reductions less than 25%. A rough estimate of this important parameter should be ascertained as early as possible. Under the pre- sent methodology, this parameter is not defined until at least the SEES televising phase. In certain cases, where S5ES televising was forecorie in lieu of ro— posed test anc seal program, or en SS S televLslng was done during low groundwatc:, the se :er line joint lca percentage was not ascertained at all I . order to more realistically oredict I/I ercentage ro a1 , we have d velooed the curves oresanted in r1 u e 4—1. sti: ating I/I c uczions. These curves w :e dev lc ad fro- . actual re.ul: and :e 1i tically corpc ra rctu:ning I/Z fror house s r-:ice connec— and r r 1 tcr igr t1 . is? ------- CURVE A U) F— 0 ‘jJ Ii. l U C) -J -j lii ii: ‘C (n z 0 LL Li. 0 • TEST a SEAL WITH LlMIT o SERVICE CONNECTIoj REP !fl C l ) t&I C-, > a: Lu U) 0 a: I L. CURVE B • REPLACEMENT • SLIP LINE • TEST Q SEAL WITH EXTENSIVE WORK ON SERVICES. LI. 0 . 0 25 50 75 100 % INFILTRATION REDUCTION ESTIMATING I/I REDUCTION FIGURE 4-I ------- Standardize television inspection flow estir ating technique. Visual flo : estir ation of leaks bserved during tele- vision inspection can vary by as much as +5O .- This data is.a significant element of any cost effective— ncss analysis and resultant rehabilitatiofl pro r A standardized technique should be developed_ . . ZNr .;TION 2 REQUIRE THAT REHABILITATION BE PERFOR ON A “PATCH” BASIS., SUCH THAT NO PIPE IS LEFT UNREHABILITATED 111 AU AREA CHOSEN FOR REHABILITATION. THIS WILL MINIMIZE THE OPPORTU II1Y FOR I/I TO MIGRATE FROM REHABiLITATED SEVIER SECTIONS TO ! ON— PEHABILITATED SECTIONS. sC:j3SION T:.. notion of I/I mIgration from rehabilitated sewer sec— ti.n to non—rehabilitated sections is widesoread. Rehabili— t ticn ‘ ork can Lometnes take on a “little bit here, little bit there” appearance; thus maximizing the opportunity for I/I t igrate upstrea n or downstream of rehabilitated sources. j.’ acceptance of test and seal grouting over specified ja i ;rcuting wa based on resolving the I/I migration ef— I - ::c e e :tensiVe test end seal, as well as other rehabilitation t c u s ay be required to minimize the I/I migration .— S,, —S• ’ DECREJ SE THE STANDARD DESIGN LIFE OF TRE TNENT PLANTS FRO1 20 YEARS TO 10-20 YEARS.. DEPENDING ON THE ABILITY OF LONG RA E REUABILITATION TO REDUCE i/I. r - ‘ -‘ — _l_..1 T. :e rtt oitu tion, in part due to th failure be the I/I P D:: . ’. iS new or racec t:e tr2 t pl n s are at or d : gn c p oity afrer only on (1) or t o (2) years of o:. zi’ . ‘i : CC.Z1 ar f c 3 ‘,ith planning now or ------- ti c r.ear future for either substantial sewer line-rehab—- ilitation id/or plant expansion. These corr unjtjes were, ii fact, cxp ct.tng tO atcain 20 years of useful Life from th e treat ient plants. way around the present dileiiina is to be realistic and nOt- ov rlv oPtimistic about the effectiveness of sewer-line re— habi1it tion and tr atnent plant desig-i l e Th ol ow g :o: a ion s ou!d s co si.de:ed during the planning and/or o erat on of new sewerage works. - - Recognize that generally a sewer system rehabilita— tion program will reduce I/I from 10 to 3O . There, of course, wifl be exceptions to this general r-Eile.. • “One shot” sewer systen evaluation and r habi1itatioa will not identify and/or eliminate all the sewer system I/I problems. n on—going operat on ax a a n— tenanc program nust be L- p1ernented to include in— vestigating new and old I/I sources and perfor aing on-going rehabilitation. • The actual effectiveness of rehabilitation in red c— in; I/I flows in the system should be deteriüned, afte rehabiLit €ion is coi tp1ete. T: s, the approach to sizing treatment plants would be to in iuc a larcer I/ flow co onent (than would be est s ated a: - : rehabilitation under the present nethodology, which t s to e::pact large reductions in I/I) a d a smaller re— z ve capacity f. r base flow expansion. This would tend to ee th a ;eraga treat ent plant size and cost about the s e a under the present I/I methodology- By designing new tlants to handle not-so—drastically reduced I/I flows. and plyLna ror tn2s oy l mizing future reserve capac1ty the actual changes in I/I and base flow can be monitored, and thus, facilitate decisions on additional rehabilitation andf 0: ?l t expansion as the 10 year or more design lifeis app :cached - R C ’ ATICN 4 E FO CE SEWER LiNE OPERATION A D MALMTE A CE PROGRPS S. r ir Cp r tiOn tr d mai tenanc (0 i -i) proç ans on sewer syst s are rc qui: td p r PR i78—1C.- This study -as fou that this ------- is no being i pl nzeci. An.on—goinc 0 M rocra - t. will djsco’ r n w I/I sources and often these will be easily re— crcd- It is .in the best interest of the counity, fror t a cozt effective perspective to continually evaluate arid re— ve I/I th t.is less expensive to elirainate than to treat. C0 4Z DATI0N 5 A RESS THE PRO3LE:1 OF I/I FROM PRIVATE SOURCES; SPECIFICALLY THE DEIECT1ONJ DISCOW ECTION AND REP,41R OF PRIVATE I/I SOURCES SUCH AS SUi ? PWIPSJ DRAINS, ROOF LEADERS A LEA}(— ING SERVICE LATERALS, DTSCC5SION I/I contributed from rivate sources generally constitutes o ar Q% of the system I/I. Thus, treatment plants will c nti e to have hich I/I flows durinc wet eather and hi i c:o : ater conditions if orivate I/I sources are ot re— In orcer to reduce treatment plant sizes a! d main— çcod treatment plant operation, corr unities shc ld ad— c!:ess these private 1/ sources. Thcse co unitias that ig c.re this major problem should be penalized ? DATI0 : 6 c; ;cTirAT . pr TT?*Ir A cIIt .InT .’r TD ;’TIl •rUAT J1 r nT. Li r’ r..J J. i iI u r i iwihu .. IIJLsL,R . It iL L J;I F?R ?::ASED REHA JLJTATiON WITH GO/NO-GO DECiSION POINTS !: ,•,1-L! - 1 IL.. L LF Sc . i0N T e /I reduction achieved by rehabilitating a collection svzte cannot be ascertained finally until after the work iz cc lete and th system experiences design—level pre— cipit ion/s ie1t conditior.s. o 7 atter how veil-documented the pre-re- abilitatiorL I/I so rc :s, it at .a s that ccuntin on an estii ted reduction t cosr ef zive is anala’ ous to counting on a cood be t c zhro gh. A phased proçra or rena 1 tat n. oul the ctua2. re ction achieved by rehabilitating part a collecticn sy ze to be used in datcr injnc t e ost eff c i ;nss of :th r rehabilitation - I,,’ ------- p a ed rch bilitation could be integra ed with service .pop u1at d e: p ion; i.e. phased reduction of the i/I design cc. one t co’ 1d f ee up treaLi ent plant design capacity for bcse flow e:pansion re arc probler s w .th .such an approach. Tb.e variability o rainfall and snowrnelt from year to year could lead to f e co c1usions about achieved reductions. A r di g - ctur3 that allc s so/No-Co decisions after each pbase cc :ld cc an adm n1strat3.ve nightrnare.. The problems i volved ;it ’ fu d g, i particular, would require detailed e-jalua— af ore adopting any form of phased rehabilitation.. RECOXME DATION 7 WSTLTUTE A STUDY TO DETEP.J’UNE THE ACTUAL EFFECTS OF I/I LO JiNG ON TR TMENT PL HT PERFORMANCE. USE THE RESULTS TO ESTABLiSH GUIDELINES FOR DESIGNING FOR If I DT SSION T-e:c is currently no standard design practice for handling £11 ot: : than the use of standard design hydraulic loading r s dcveloped for raw s age A rational basis for treat— i: j dii .:ted se :age is ç arly needed, based on the docuz entcd. of I/I loading on plant perfor ar ce. The capacity c t: ent plants to weather both short-term “inf1o ” ar:d long—term “infiltration” should be deternined. as : y p:esc t a significant “source” of I/I capacity in— in standard treatrnent plant design practice a I :sflTUTE DISCHARGE PEPJ ’HT REQUIREIIENT VARtPJ CES DURING P ODS OF HIGH I/I FLO ISJ TAKING ADVAUTAGE OF THE INCREASD S!J1lL4TiVE CAPACITY OF RECEIVING iIATERS THAT GENERALLY C3: ?A iES HIGH I/I FLOWS. ‘ .- —.— - S. r .iL ’2 I/I loadings r v cause treatnant o iant efficiencies t- r c d well bclcw the rec.iired 85% re iovais for Bio— c iC Oxygen Demand 1 OD) and Suspended Solids (SS) - cc . yina d ’uticn effect of the I/ ge e ’’v en bl s : c :luent ch r ctc:ist1cs to re7r .ai.n e .cw 3 r .gra s c. lite The toz:.l of these eff1ue t r etcrs b i: as c3, ‘: t higher recc iv! g te: flc z z ay v: the a ;i7’ilatiVC capac .tY. ------- • CC : N .;TION 9 !: TITL’TE A (1O TORIUH ON ALL I/I ANALYSES AND SE 1ER SYSTEM EVALUATiON SURVEY REPORiS THAT ARE UND WAY OR RECE LILY C0i PLETEDI THESE PROJECTS SHOULD BE REVIEWED P D 3IJIFIED ACCORDING TO THE FINDINGS OF THE STUDY, DISCUSSION I/I Analyses and Sewer System Evaluation Surveys are still i g based on unreelistièally high expected red ictio s. One (1) or two (2) years from now these projects wifl. be con— szructed and the same findjnqs of effectiveness will be made as in this study Thus, in the long run it would ba beneficial to delay these projects for a short period now, aid obtain more realistic results when sewer line re! bj1jta— tion is Completed. /1.3 ------- PEAK 1/I P ED C ICN SO YI - O OL X DISTP IC _________ t ated Exis ing I/I’ Proccse I/I — VGD 2 -?DIM 3 .:GD G? IM A hia d 0.63 3330 0.36 1900 125.0 20830 .66.0 11000 ! , ai. tree 16.2 10750 9.05 6000 3 1ine* 8.8 9150 5.30 5500 aritor 5.1 7800 2.85 4330 10-3 i250 5.9 7150 7.1 3180 4.2 1900 .6.0 26500 1.0 4400 c1 rcok N/A N/A N/A 500 3.1 3500 2.2 2450 tick 3.45 3230 2.0 1350 4.]. 3100 2.65 2000 11.3 5530 6.5 3200 9.2 8310 6.0 5400 cy 22.4 9150 12.9 5250 2.6 3660 1.5 2150 St. -2tc 1.8 3860 1.2 2550 3.3 8350 1.2 31 0 i1es1ey 3.7 2370. 2.5 1600 1.2 2900 0.7 13 0 ¶•: c th 8.1 5550 5.1 35 3 _, —-..— £.._. -‘ • _l U . —— r ,: -: s2d u : ir’r r t.t c: of c rr .-t icr t DE’E 2 . . - . ; Y. = G:.1!c” :• - —.-. - ., , .: . . ii J ------- |