BOS-OO2- )ii EVALUATION OF SATELLITE ADVANCED WASTEWATER TREATMENT FACILITIES t4 . I t4rr r REFERENCE Volume II BOSTON HARBOR SUPPLEMENTAL DRAFT ENVIRONMENTAL IMPACT STATEMENT U.S. ENViRONMENTAL PROTECTION AGENCY REGION I JOHN F. KENNEDY FEDERAL BUILDING BOSTON, MASSACHUSETTS 02203 ! EGI LIBRARY rr FEDERAL BLDG .cJON, MA 02203-2211 NOT FOR PUBLIC RELEASE DRAFT REPORT Prepared by: CE MAGUIRE, February 1984 0 Te. lW INC. ------- TABLE OF CONTENTS Section Title A HISTORICAL BACKGROUND A.1 EMMA CONCEPTS A.2 EMMA RECOMMENDED SATELLITE FACILITIES A.3 1978 DRAFT EIS CONCLUSIONS B DESCRIPTION OF SDEIS SATELLITE OPTIONS 8.1 EMMA RECOMMENDED SATELLITE FACILITIES UPDATE B.2 WETLANDS DISPOSAL OPTION — PROPOSAL BY QUINCY SHORES ASSOCIATION B.3 RELATIONSHIP OF SATELLITE OPTIONS OF ON-GOING MSD-SOUTH FACILITIES PLAN C EVALUATION OF SDEIS OPTIONS C.1 EMMA RECOMMENDED FACILITIES (i) Flow Augmentation (ii) Water Quality (iii) Water Supply C.2 WETLANDS DISPOSAL OPTION 0 CONCLUSIONS APPENDIX A WATER QUALITY MODELING CORRESPONDENCE APPENDIX B WETLANDS DISPOSAL BIBLIOGRAPHY APPENDIX C WETLANDS DISPOSAL-DEQE CORRESPONDENCE APPENDIX 0 I/I PRELIMINARY REPORT TO PROF. CHARLES M. HOAR ------- A. HISTORICAL BACKGROUND 1. EMMA Concepts Five broad-scale wastewater management concepts were developed for evaluation in the Eastern Massachusetts Metropolitan Area Wastewater Management (EMMA) Study. Although the concepts themselves were not necessarily formulated with the intention of any one being selected for implementation in its entirety, it was intended that the evaluation of these broad—scale concepts would establish the design criteria, system limits, and other conditions and considerations required of an imple- mentable, recommended plan. Brief general descriptions and important features relative to satellite facilities of the five original concepts are shown on Table 1. An extensive rating system was employed to evaluate and rank the concepts by the Technical Subcommittee. This evaluation led to the elimination of concepts 3 and 5 from further consideration. As stated in the EMMA Study Main Report (pg. 4-27): “Upon evaluation of all the factors affecting the plan selection process, and because of the closeness of the rankings for Concepts 1, 2 and 4, it was decided by the Technical Subcommittee that a moderately decentralized system would be the best overall solution considering river flows, increasing demand and decreasing oppor- tunities for water-oriented activities, and the difficulties associ- ated with extensive interceptor construction through urban areas and the filling of Boston Harbor.” Four satellite treatment alternatives were developed for further evaluation. The satellite systems and communities to be served under each alternative are summarized in Table 2. The wastewater flows from remaining communities tributary to the Nut Island Treatment Plant would continue to flow to Nut Island for treatment and discharge to Boston Harbor. The following excerpt from EMMA Study Main Report summarizes the evaluation of the four alternatives: 1 ------- TABLE 1 Satellite Facilities Design Communities Served Concept Description ( River Basin) ( Plant Location) Flow By Satellite Plants Upgrade existing facili- None ties, minor system expan- sion (addition of 7 com- munities), no satellite plants 2 Limited decentralization, Sudbury R. Framingham 19.0 IIGD Ashland, Framingham, creation of five regional Hopkinton, Southborough satellite systems Charles R. Dedham 29.0 HGD Brookline (25%), Dedham, Dover, Natick, Needham, Newton (8%), Sherborn, Wellesley, Boston (West Roxbury) Charles R. Watertown 45.0 MGD Lincoln, Newton (92%), Waltham, Watertown, Weston Neponset R. Canton 25.0 MCD Canton (70%), Norwood (90%), Sharon, Stoughton, Walpole Neponset R. Canton 5.5 ?IGD Canton (30%), Dedham (10%), Norwood (10%), Westwood 3 Maximum expansion of MSD None treatment of all flows at expanded harbor facili- ties ------- 4 Maximum decentralization of MSD, creation of six regional satellite sys- tem Sudbury R. Charles R. Framingham Dedham 19.0 HGD Same as Concept 2 22.0 MGD Dedham (40%), Dover, Natick, Needham, Sherborn, Welles ley Charles R. Neponset R. Watertown Canton 45.0 MGD Same as Concept 2 30 MGD Canton, Norwood, Sharon, Stoughton, Walpole, Wes twood 5 Land application of five of the six satellite facilities as proposed in Concept 4 - otherwise identical to Concept 4 Mystic R. Mystic R. Woburn Medford Same as Concept 4 (Sudbury River - Framiagham Facility would not employ land appli- cation) 31.0 MGD Burlington, Reading, Stoneham (85%), Wakefield (10%), Wilmington, Winchester (45%), Woburn 30.0 MGD Arlington, Bedford, Belmont (90%), Lexington, Medford (20%), Winchester (55%) ------- “Upon further analysis of the Neponet River, the Massachusetts Division of Water Pollution Control recommended that if a satellite treatment plant is located for discharge to the Neponset River, the plant should be located as far upstream as possible to provide maximum benefits to the river, particularly during the dry sunm er months. “A plant in the middle Charles area was considered vital to provide effluent for low-flow augmentation. As mentioned earlier, investigations (by the Corps of Engineers and the United States Geological Survey) for other means of flow augmentation in the Charles River were found not feasible and the need for conserving river flows was shown to be critical (by the United States Geologi- cal Survey). In terms of location, the lower middle Charles plant would be undesirable due to the flat, slow flowing river in that location. However, an upper middle Charles plant discharging at the Cochrane Dam near Charles River Village would be in a location where the discharge would benefit from the over one mile long rapids section. “In addition to these considerations, the plants will also serve to reduce flows to the Nut Island Treatment Plant and will reduce the need for relief lines along the Wellesley Extension Sewer, the New Neponset Valley Sewer, and the High Level Sewer. “Providing a 2 mgd wastewater treatment plant in the Aberjona River area would cost on the order of $9.7 million to construct and about $0.7 million per year to operate. These costs represent the complete treatment process shown in Figure 3-4. On the basis of operating costs alone, this would be in excess of three times the cost of using MDC water for augmentation (which would be an unaccept- able alternative). In addition to this, other alternatives of flow augmentation should be considered such as groundwater pumping during low flows and recharge during high flows. “A wastewater treatment plant discharging to the Sudbury River in the Framingham area was considered as not providing a significant improvement in flows due to the large storage potential in the flat swampy areas downstream.” Based on the evaluation of these alternatives, a modified Alterna- tive A was selected as the Recommended Plan. 2. EMMA Recommended Plan - Satellite Facilities The Recommended Plan included satellite treatment facilities dis- charging to the Middle Charles and Upper Neponset Rivers. The Middle Charles Treatment Plant would serve Ashland, Framingham, Hopkinton, 4 ------- TABLE 2 Satellite Facilities Design Alternative River Basin Plant Location Flow Communities Served by Satellite Plants A Charles R. Middle Charles 31 MCD Ashland, Dover (60%), Framingham, Area Hopkinton, Natick, Sherborn, South- borough, Wellesley (80%) Neponset R. Lower Neponset 31 MGD Canton, Norwood, Sharon, Stoughton, Area Walpole, Westwood B Charles R. Lower Middle 57 MGD Ashland, Brookline (15%), Dedham (40%), Charles Area Dover, Framingham, Hopkinton, Natick, Needham, Newton (54%), Sherborn, South- borough, Wellesley Neponset R. Lover Neponset 31 MCD (Same as Alternative A) Area C Charles R. Middle Charles 31 MGD (Same as Alternative A) Area Charles R. Lover Middle 27 MGD Brookline (15%), Dedham (40%), Dover (60%), Needham, Newton (54%), Wellesley (20%) Neponset R. Lover Neponset 31 MCD (Same as Alternative A) Area D Sudbury R. Upper Sudbury 19 MGD Ashland, Framingham, Hopkinton, South- Area borough Charles R. Lower Middle 39 MCD Brookline (15%), Dedham (40%), Dover, Charles Area Natick, Needham, Newton (54%), Sherborn, Wellesley Neponset R. Lower Neponset 31 MCD (Same as Alternative A) Area ------- Natick, Sherborn, Southborough and p 1 rtion of Dover and Wellesley and would have a design flow capacity o&31 MGp. The Upper Neponset Treat- ment Plant would serve Canton, Norwood., a’lpole, Sharon and Stoughton and would have a design flow capacity of 25 MGD. The anticipated benefits associated with these proposed facilities were summarized as follows: Neponset River: This facility would reduce the service area of the Nut Island Treatment Plant and keep reclaimed wastewater as far upstream in the Neponset River Basin as possible. The highly treated effluent should help the Neponset River by increasing flows in dry summer months. Restoration of clean water will also depend on the abatement of nonpoint and other sources of pollution. Charles River: This facility would treat 31 mgd in the year 2000, reduce flows to the Nut Island plant, and help retain reclaimed waste- water in its immediate basin. Adding these flows to the Charles River will be helpful to water quality in dry seasons. However, there can be no assurances of achieving intended water quality in the Charles River unless nonpoint and other sources of pollution are eliminated. The treatment facilities which are in various stages of implementation in the Medfield, Medway, and Milford areas should also benefit the river. It is worthwhile to note that, in recommending the implementation of both treatment facilities, it was recognized by the Technical Subcom- mittee and by those who participated in the public review process that water quality in both the Charles and Neponset Rivers might not be improved. There appears to have been, however, an implicit assumption that water quality problems would not worsen as a result of the dis- charges from these treatment facilities. The Middle Charles and Upper Neponset facilities were scheduled as sequence numbers 10 and 11 respectively in the Construction Staging Program for MDC Wastewater Management Projects. The total cost of both facilities was $90,700,000 based on January 1975 (ENR 2200) costs. 6 ------- The Construction Staging Program also listed interceptor relief in lieu of sequence numbers 10 and 11 as sequence numbers 1OA and hA if the satellite plants are not implemented. The total cost of additional interceptor relief for the Wellesley Extension, New Neponset Valley and High Level Sewers was listed as $64,700,000 (January 1975, ENR 2200). Finally, four optional treatment scenarios were presented in the EMMA Main Report which were intended to provide an economic perspective of the impacts of major changes from the Recommended Plan such as timing of implementation of major facilities (i.e. satellite plants); and policy changes such as primary treatment with deep ocean discharge versus secondary treatment. These “Other Treatment Options” and their assciated capital and O&M costs are summarized in Table 3. 3. Conclusions Regarding Satellite Facilities - Draft EIS, 1978 The Draft EIS concluded that neither the Charles nor Neponset River satellite plants should be constructed. This conclusion was based on negative water quality impacts projected to occur or to be maintained at the 7010 design flow condition. o. I Based on the application of a basic Streeter-Pheips dissolved oxygen analysis in the Neponset River, the draft EIS concluded that: “Any discharge to Neponset in the area proposed by the EMMA report would result in a significant detrimental impact on the Neponset River’s dissolved oxygen resources and overall water quality. In addition, all the discharge points analyzed are upstream of a major group of water supply wells (See Figure 2.5-18). It is very likely that these wells draw from the Neponset during low flows, given their proximity to the River and the nature of the aquifer. The potential for significant adverse health effects is created by utilizing any of these discharge point. In order to mitigate these impacts it would be necessary to move the discharge point downstream of point C. Such action reduces potential flow augmentation bene- fits considerably. 7 ------- TABLE 3 SUMMARY OF OTHER TREATMENT OPTIONS - MDC - EMMA STUDY Capital Cost( 1 ) Operation & Maintenanc?l)( 2 ) Option Description millions of $ cost, millions of $/yr Recommended plan 855.3 25.6 Total ocean discharge No satellite treatment plants. 737.9 16.9 All flows discharged in deep waters after receiving primary treatment at the Harbor plants. Ocean discharge in Satellite treatment plants con- 755.7 22.3 lieu of secondary structed. Primary treatment at treatment the Harbor plants with deep ocean discharge. Deletion of satel- No satellite treatment plants. 872.4 20.9 lite plants All flows receiving secondary treatment at the Harbor plants. Postponing of satel- Delayed construction of satel- 884.8 20.3 lite plants lite plants. Upgrade primary treatment at the Harbor plants. Extend treatment capabilities at the Harbor plants to secondary along with construction of satellite plants. 1. Costs shown are in millions of dollars based on January 1975 (ENR 2200) prices. 2. Costs on the basis of future flows (year 2000). 8 ------- “In light of the great potential negative impact upon water quality, implementation of a Neponset River Satellite Plant is not recom- mended.” A fairly rigorous analysis of the Charlesiiver was undertaken by Alan Ikalainen (at that time of EPA Region f’SYstems Analysis Branch staff) employing a computer model developed for the Massachusetts Division of Water Pollution Control (MDWPC) known as the STREAM model. Based on this analysis, the draft EIS concluded that: “A satellite plant represents a major new pollutant source for the Charles River, which will increase point source mass input the River of BOD 5 from 329 to 586 kg/d (725 to 1293 lbs/d) and nitrogenous oxygen demand from 311 to 535 kg/d (685 to 1181 lbs/d) (See Table 7, Appendix 3.2.2). In addition, the following table compares the proposed discharge with River quality just upstream of the dis- charge. Imposition of this additional load upon the already stressed river system may effectively preclude the Charles from recovering from its present stressed condition. If River conditions improve such that standards are met, the satellite discharge is indicated to cause violation of standards unless an extremely high level of treatment is achieved on a consistent basis. As the result of this analysis, a satellite plant discharge is seen as not improv- ing water quality in the Charles River and contributing to the maintenance of its present condition. The implementation of a satellite plant discharging to the Charles River is not recom- mended.” The conclusions and recommendations of Mr. Ikalainen’s report are as follows: CONCLIJS IONS 1. The physical characteristics of the Charles River are such that it has a very low assimilative capacity for oxygen demanding wastes at the seven-day, ten-year low flow. 2. This analysis reveals a very major likelihood that the Charles River, at the seven-day, ten-year low flow, when receiving year 2000 wasteloads (5 mg/i CBOD 5 and 1 mg/i N H 3 - N) from existing treatment plants in Miiford, Medfield, and Miliis and the Charles 9 ------- COMPARISON OF AWT EFFLUENT AND CHARLES RIVER QUALITY / Charles River’ Satellite Disch rge2 Flow, m 3 / 0.89 1.35 / (ft Is) ( 31.4)t ’ (47.7 ) Dissolved Oxygen, mg/i 3.1 6.0 BOB 5 mg/i 0.6 5.0 (kg/d (lbs/d) 67 (148) 478 (1494) Nitrogenous Oxygen Demand mg/i 0.005 1.0 kg/d (lbs/d) 17.5 (38.5) 535.8 (1181.5) Total Oxygen Demand mg/i 1.1 11.9 kg/d (ibs/d) 84.6 (186.5) 1231.4 (2675.5) ‘River conditions as modelled at river kilometer 80.3 (river mile 50), just upstream of Medfield State Hospital discharge point, during 7 day, 10 year low flow. All upstream point sources have effiuent quality of S mg/i BOD 5 and 1 mg/i NH 3 -N. recommended discharge and effluent quality. p M— ,LlL. J £0 10 ------- River Pollution Control District Plant, will not attain the D.O. level of 5.0 mg/i for long stretches. This condition will prevail with or without an MDC Satellite plant discharge at any of the locations considered in this analysis. 3. If future discharges at Milford, Medfieid and Nulls and the Charles River Pollution Control District can be reliably treated and the river can be reliably treated such that D.0. levels in the river upstream of an MDC satellite plant discharge are at 5.0 mg/i at the seven—day, ten-year low flow, then an MDC satellite plant discharge containing 5.0 mg/l of CBOD 5 would not lower D.O. levels below 5.0 mg/i if it is located upstream of the South Natick Dam. However, this condition would be true only if no other oxygen demanding phenomena such as algal die off and non-point source pollution occur during the low flow periods. 4. It is understood that the “STREAM” model does not simulate all of the physical and biochemical processes that occur in the Charles River and which determine part of its water quality and biotic condition. However, these processes, such as algal growth and death dynamics, land-surface runoff dynamics, septic and solid waste leaching——all of which are known to occur in the Charles River, can further worsen D.O. conditions at critical periods beyond those processes which are simulated by the “STEAM” model. Such critical conditions would probably be during periods of high temperature, low river flow and between periods of short duration, intense rainfall. The occurrence of base flow (groundwater flow) into the river has not been considered and its effect on water quality is not known. 5. An MDC satellite plant discharge under the anticipated year 2000 wasteloads (5.0 mg/l CBOD 5 andl.0 mg/i N B 3 - N at all upstream discharges) will significantly improve D.0. levels in the Charles River only if the discharge is located upstream of the South Natick Dam or near the Medfield Hospital. The improvement will be I to 2 mg/i increase in D.O. along several miles of river. However, the 11 ------- improved condition will be significantly below the desired level of 5.0 mg/i. 6. This analysis indicates that benthal oxygen demand is a significant oxygen loss to the Charles River. For example, at the seven-day, ten-year flow, without any sediment oxygen demand and without any treatment plant flow or wasteloads, the Charles would meet the D.O. level of 5.0 mg/i except for a short stretch upstream of Milford where background loads would cause 0.0. to fall to 2.5 mg/i. Current wasteloads (1978) added to the river under these same conditions cause D.0. levels to fail to zero below Milford and within the South Natick Dam and Cochrane Dam impoundments. If these wasteloads receive advanced treatment (5.0 mg/i CBOD 5 and 1.0 mg/i NH 3 - N) and the Charles River Pollution Control District Plant receives advanced wastewater treatment, at year 2000 wastewater flows, the zero D.0. levels are raised to greater than 5.0 mg/l below Milford and to about 2.5 mg/i in the South Natick Dam and Cochrane Dam impoundments. If an MDC Satellite plant discharge is added to the river at ?ledfield with year 2000 flows with advanced treatment, 0.0. levels are raised by 1-2 mg/i within the South Natick Dam impoundment and lowered by 1.0 mg/l to about 4.0 mg/i within the Silk Mill Dam impoundment. If the Satellite plant discharge is located below the . ‘Cochrane Dam, th will be no 0.0. increase within the South Natick Dam impoundment and there will be an additional decrease in 0.0. of QJ 1.0 mg/i to about 3.0 mg/l within the Silk Mill Dam impoundment. In comparison, with sediment oxygen demand at the levels used in this analysis, atthe volume of vastewater discharged, not including the proposed satellite plant, increases from no plant wastewater discharged to 1978 flows to 2000 flows, at the respective levels of treatment, the 0.0. levels of the river increase successively. The result is that the D.0. levels will be significantly better in the Charles at the year 2000 flows at Milford, CRPCD and Medfield- Millis, ret ivig advanced treatment, than at present flows and 12 ------- treatment levels. However, there will be long stretches with D.O. very much less than 5.0 mg/l within the South Natick Dam and Silk Mill dam impoundments. Adding the MDC Satellite plant flow at Medfield will further raise D.O. by 1-2.5 mg/l within these impound- ments, but it will remain 1-2.5 mg/i below the 5.0 mg/i level. Adding the MDC Satellite plant flow below the Cochrane Dam will raise D.O. about 1.5 mg/i at the discharge point and lover it about 1.0 mg/l within the Silk Mill Dam impoundment. d fu rt RECOMMENDATIONS 1. An MDC satellite plant should not be located on the Charles River unless: a. it can be shown through further data collection and analysis that those river processes not considered in this analysis will not increase D.O. deficits during low flow periods; b. it can be shown that treatment plant facilities can be reliably operated to provide the pollutant removals as are shown to be required by this analysis to maintain 5.0 mg/i D.O. in the Charles River at low flow; c. the public is willing to bear the economic and environmental impact costs of a satellite plant at the required location and level of treatment. I) P “% ‘ 2. (Treatment applied to wa ewater discharges not reduce levels of all pollutants below those occurring in runoff and other non- ) point pollution sources kf the Charles River unless it is proven J \ through detailed analysis that further treatment Iis,cost effective in terms of significantly improving in stream water quality. 3. The water pollution control planning process for the Charles River should include, as a possible control for future wastewater from Milford, CRPCD and Medfield-Millis, the limiting of sewer service 13 ------- area and wastewater loadings, such that wastewater loadings to the Charles River are minimized. NOTE: ,) &Q These recommendations are based upon the premise that the water quality standard for dissolved oxygen (5.0 mg/i) has to be met at the seven-day, ten-year low flow. Therefore, new discharges to the Charles must be such at D.O. levels of 5.0 mg/i will be met at low flow and they will be discharging to a river which is meeting standards at low flow. As a result of the conclusions stated regarding the negative water quality impacts associated with both the Charles and Neponset satellite facilities, the site selection process was abandoned for both facilities prior to the selection of a recommended location for each plant. Detailed evaluations of flow augmentation impacts of the satellite facilities were conducted for each river and reported in the draft EIS. The conclusions at these evaluations, which also reflect potential water quality impacts previously described are summarized as follows: Charles River “The future low flow hydrology of the Charles River will be influ- enced by a number of factors not previously considered. The most signi- ficant of these is the presence of point source discharges upstream of the MDC service area. Dischar e 3 from these sources is expecte o increase approximately 4 . x10 m /d (12.7 mgd) - from 19.68x10 m /d (5.2 mgd) in 1973 to 67.76x10 m /d (17.9 mgd) in 2000. These upstream com- munities draw groundwater from public wells scattered throughout the Upper Watershed (see Figure 2.5-13b) and many private wells. Groundwater withdrawals from wells distant from the river will adversely influence the Charles only after a significant time lag. Conversely, the water will rapidly reach the river via the sewer systems. The net effect can be considered as augmentation of river flow by pumping groundwater storage. These upstream sources roughly balance the export volume and the flow situation in the Charles can be anticipated to remain relatively constant. In addition, implementation of water conservation methods, reduction in I/I and more effective management of the Mother Brook diversion are techniques which can be utilized to ensure low flow prob- lems in the lower Charles watershed do not develop. 14 ------- “In summary, it is felt that the benefits of flow augmentation to the Charles River by an additional point source discharge, are not sufficient to warrant the degradation in water quality that such a discharge would cause. Given the option of Harbor discharge, the risks involved with a Charles River satellite discharge are not offset by the benefits to be derived. “While recycling of water within a basin is a worthy objective of a wastewater management plan, it should not be done at the expense of water quality considerations. Indeed, recycling is occurring in the Charles upstream of the study area. As a result of this, water is conserved during times of drought 3 a d water quality is frequently degraded. Adding an additional 120.24x10 m /d (31.77 mgd) point source to the river does not appear to be environmentally sound. The expenditure of resources on advanced waste treatment would be best applied to existing point sources in the river to maximize the water quality and quantity benefits of their operation. The water quantity/flow augmentation issue is extremely difficult to project and is by no means closed. However, it is felt that a system without satellite plants will best protect the overall environ- mental concerns within the study area.” Neponset River “The Neponset River is actively regulated for industrial water supply and this controls its low flow characteristics. In addition, the only upstream discharges are industrial cooling waters. Sources of water to make up for export to the Harbor are not readily available as in the Charles watershed. “Between 1970 and 2000, export of N p nset water to Boston Harbor would increase by approximately 45.42x10 m /d (12 mgd). The loss of this water is a negative impact associated with non—satellite alternatives. However, as previously discussed, significant water quality impacts will be caused by a Neponset discharge. Major water supply wells lie immedi- ately downstream of the most likely discharge points, creating public health concerns. The water quality related impacts are more severe than the water quantity impacts and, therefore, an all harbor alternative is preferable. “The potential to mitigate those impacts through an alternative augmentation system should be investigated. The active regulation of the Neponset for industrial water supply could be coordinated with flow needs such that both are satisfied during drought conditions. In addition, major I/I reductions and water conservation should be emphasized as methods to mitigate quantity related impacts. Such actions will have greater long term benefits for the Neponset River Watershed than aug- mentation with wastewater.” A comparison of the Recommended Plan which evolved as the result of the Draft EIS process and the EMMA Recommended Plan was presented in the Draft EIS in Section 3.5.9 which summarized the major impacts and costs. 15 ------- This section is reported here in its entirety as it represents an impor- tant link between the draft and supplemental EIS review process. “3.5.9 Conclusion (Draft EIS, 1978) “With respect to water quality considerations, the pn-satellite y em Deer Island Plan) is the only system alternative which will meet wate lTtyTti Tdi. This system will not affect water quality in inland streams and will greatly improve the quality of the existing effluent discharges. The EMMA Plan wi].1 similarly improve the quality of the harbor discharges and will reduce their volume somewhat. The EMMA Plan,_however, will cause degradation of water quality in the Charles and Ne15 ithet Ri ST A Nep nàet RiviIdIicharge will cause its dissolved oxygen standii d to be violated, while the Charles River discharge will significantly increase the magnitude of projected water quality viola- tions. The No Action alternative will result in the continued degrada- tion of harbor waters. Modified No Action will cause an improvement in ambient water quality conditions but degradation in the vicinity of the existing primary discharge will persist. Overall, the Deer Island Plan is the best of the four system alternatives with respect to water quality. “In terms of water quantity, the Deer Island Plan and both “No Action” alternatives will have a similar effect. That is, they will result in the export of water from the Charles and Neponset watersheds in the form of sewage. For the Charles River watershed, this loss will be approximately offset by additional point source dischar 9 to the river. For the Neponset River, an estimated export of 45.42x10 m /d (12 mgd) per day has been projected. The EMMA Plan, since it will result in the discharge of treated effluent to the rivers, will have a lesser impact on low river flows. In fact, the EMMA Plan will result in substantially higher dry weather river flows than have occurred in the past, but at the expense of water quality. “The effects of the No Action alternative on the area’s biotic communities will represent a continuation of present trends. That is, organisms associated with polluted waters will remain. Increased degradation of water quality as a result of increased pollutant loads will continue to damage the harbor’s flora and fauna as well as the public’s use of them. Modified No Action will improve the situation except in the vicinity of the existing primary outfalls. Both the EMMA Plan and the Deer Island Plan will further improve biotic conditions. “The EMMA Plan and the Deer Island Plan will further improve biotic conditions. “The EMMA Plan will require the use of two additional sites for facilities construction and specifies the filling of Quincy Bay to expand the Nut Island plant and the filling of Boston Harbor to expand the Deer Island plant. This is considered to be a major impact. The Deer Island Plan avoids filling the harbor but requires the complete use of Deer 16 ------- Island plus a major bay crossing. Also, additional interceptor relief is required for the Deer Island Plan. “In terms of construction-related impacts, both the Deer Island Plan and the EMMA Plan will cause more disturbance than either No Action alternative. While each of these systems will produce its own set of characteristic construction impacts, they cannot be easily separated on this basis in terms of a value judgment. “As far as air quality characteristics are concerned, the No Action alternative would result in the least air emissions followed by the Modified No Action alternative. The Modified No Action alternative represents an increase in emissions to the ambient air due to the incin- eration of the primary sludge, but it would not include the incineration of the secondary sludge. Comparisons of the emissions from primary to secondary sludge incineration at the Deer Island Plan and EMMA Plan sites, indicates the Deer Island Plan would have less air quality impact. This is based upon the lower quantities of emissions and the site loca- tion of the Deer Island Plan. This differential is offset, however, by the need to establish a landfill for disposal of digested sludge under the Deer Island Plan. “On the basis of the preceding comparison, the best of the four system alternatives can be selected. The No Action alternative, while it is economical and impacts upon air quality the least, is not considered feasible. Existing primary sludge di charges to the Harbor, poor opera- tion of existing facilities, gross and visible pollution from the Nut Island facility, and persistent bacterial contamination of the Harbor render this alternative untenable. “The modified No Action alternative will improve water quality conditions and benefit the harbor’s biota in a general sense, but the gross pollution from the existing primary outfalls and bypasses will persist. Pollution from sludge discharges will be abated, however. This plan is significantly less expensive than either the Deer Island plan or the EMMA plan and will be more favorable in terms of air quality impacts and primary construction-related impacts. The alternative is rejected, however, on the basis of permitting unacceptable water quality conditions to persist. “The EMMA plan and the Deer Island plan both further improve water quality conditions in the Harbor. As described previously, these alter- natives vary in terms of their specific impacts, but they can be sepa- rated on the basis of several significant parameters. These include: “1. The violation of water quality standards in the Neponset River and a further deterioration of the Charles under the EMMA plan. “2. The need for 42 acres of fill in the Harbor under the EMMA plan. “3. The need for a major harbor crossing, additional interceptor relief and drumlin removal under the Deer Island plan. 17 ------- “Beside these factors, the other levels of impact are generally similar with some trade-offs existing between the alternatives. Costs are approximately equal. While Item #3 above represents significant impacts, they can be justified in light of the magnitude of the problem and its solution. Except for drumlin removal, these effects are short term. Items #1 and #2, however, represent long term impacts which are considered unacceptable. The solution to a wastewater management problem should not be resolved by causing other water quality problems. The loss of 40 acres of the Harbor likewise represents an irreversible impact which should not be accepted if there exists any alternative. We therefore, select the Deer Island Plan as the best of the four system alternatives.” In its role as Technical Consultant to EPA Region I in the prepara- tion of the Supplemental Draft EIS, CE Maguire was asked to evaluate the technical basis which led to the conclusions previously discussed regard- ing satellite treatment facilities and to update the evaluations to reflect additional data, analytical procedures or changes in technology. In this regard, EIS documents and references from the Draft EIS were reviewed; meetings were held with EPA, MDC, MDWPC, DEQE, Division of Water Supply and other pertinent agencies; and data collected in inter- vening years (e.g. water quality) was assembled and incorporated into the review process. With respect to the draft EIS itself, the water quality analysis of the Charles River was found to be the major unresolved issue. This issue is identified in a package of correspondence between MDC, Metcalf & Eddy, EPA and MDWPC over the period of 5/18/77 to 7/25/79, culminating in a letter from Martin Weiss, then Chief Engineer of the MDC to Thomas C. Mcflahon, Director of the MDWPC dated 7/25/79. This letter established a scope of work expected to be conducted by the MDWPC to respond to con- cerns raised regarding the water quality modeling of the Charles River as presented by Mr. Ikalainen. With the exception of the water quality survey carried out by the MDWPC in 1978, no documentation was found to indicate that the MDWPC responded to Mr. Weiss’ letter on that the MDWPC has any plans to respond to these items at present. The complete text of the referenced correspondence is continued in Appendix I. The other issue left unresolved in the draft EIS is that of the siting of the satellite faclities. Although it is pointed out that the 18 ------- issue of siting was apparently considered moot following the presentation of findings regarding water quality impacts, it is unclear as to why a siting decision was preempted at that point in the EIS process. B. Description of SDEIS Satellite Options As a result of the joint NEPA/MEPA scoping process for this supple- mental draft EIS, EPA was required to reevaluate the original satellite facilities proposed in the EMMA Recommended Plan and a satellite facili- ties proposal submitted by the Quincy Shores Association incorporating wastewater reclamation/reuse via wetlands effluent disposal in critical water supply recharge areas in the metropolitan area. Both satellite options are described in the following sections incorporating wastewater flow projections reflecting revisions generated in the Nut Island Site Option Study; updated facilities design criteria and costs; and identi- fication of the benefits projected to be associated with each option. EMMA Satellite Facilities Wastewater flow projections for both the Middle Charles and Upper Neponset satellite facilities were updated using flow projections revised in the NI-SOS. The revised flow estimates are summarized in Table 4. Based on these projections, the Middle Charles facility would be designed to treat 15.27 MGD average flow and 37.13 MGD peak flow in the design year 2010. The Upper Neponset would be designed based on average and peak design flows of 9.00 MGD and 22.26 MGD, respectively, in the year 2010. Capital and operation and maintenance costs for the Charles and Neponset facilities were updated from 1978 (ENR 2654) to 1983 prices based on an ENR of 4200. As the differences in design flows relative to the overall size and complexity of each facility are small with respect to the updated vs. the original flow estimates used as the basis of design in the draft EIS, no adjustments in costs were made based on the updated flow projections for each facility. Further, it is important to note that the costs do not include sludge pumping, sludge processing 19 ------- (e.g. thickening, dewatering), incineration and ash disposal which are presented as the sludge processing and disposal operations in the draft EIS. (Draft EIS, pg. 3-232, “The sludge produced at the satellite plants would undergo incineration at each plant.”) Updated costs are presented Table 5. It was further determined that the level and type of treat- ment projected to be provided at each facility should remain as proposed in the EMMA Recommended Plan and as described in the draft EIS. Proposed effluent limits of 5.0 mg/i CBOD 5 and 1.0 mg/i NH 3 - N at the design year flows can be reliably expected to be achieved via the proposed treatment facility process configuration. As previously stated, from both the EMMA and draft EIS documents, the major benefits anticipated to be derived as the result of the imple- mentation of satellite facilities are summarized as follows: 1. Satellite facilities would maintain water in its basin of origin and thus provide reliable sources of low-flow augmenta- tion. 2. Satellite facilities would reduce treatment capacity and size requirements at Nut Island. 3. Construction of satellite facilities would result in cost savings for interceptor relief in the southern MSD. 4. Satellite facilities would provide additional opportunities for feasibility on sludge treatment and management. 20 ------- TABLE 4 REVISED FLOW ESTIMATES - CHARLES & NEPONSET SATELLITE PLANTS Charles River Projected Flows Community Ave. 1980 1990 Peak Ave. Peak 2010 Ave. Peak 5.22 13.18 7.21 18.00 9.00 22.26 Source: MDC Nut Island Site Options Study, 1982, M&E. Ashland 0.39 1.12 0.55 1.56 0.93 2.49 Framinghain 5.72 13.32 6.86 15.97 7.72 18.00 Natick 2.67 6.64 2.98 7.36 3.34 8.19 Southborough 0.00 0.00 0.00 0.00 1.06 2.75 Wellesley 1.73 4.24 1.75 4.28 1.85 4.49 Dover 0.00 0.00 0.00 0.00 0.09 0.32 Hopkinton 0.00 0.00 0.00 0.00 0.22 0.65 Sherborn 0.00 0.00 0.00 0.00 0.06 0.24 10.51 25.32 12.14 29.17 Projected Flows Totals Neponset River Community Canton (30%) Norwood Sharon Stoughton Walpole Totals 1980 1990 Peak Ave. Peak 15.27 37.13 2010 Ave. Peak Ave. 0.49 3.03 0.00 0.78 0.92 1.26 7.35 0.00 2.08 2.47 0.62 4.21 0.00 1.15 1.23 1.59 10.29 0.00 2.91 3.21 0.79 4.78 0.26 1.62 1.55 1.98 11.65 0.78 3.92 3.93 21 ------- N TABLE 5 - COST UPDATE - EMMA SATELLITE FACILITIES Satellite AmountW Capital Cost 2 Annual O M Cost 2 Total Annual Cost 3 106) s x 106) s x Middle Charles 70.5 5.57 12.82 Upper Neponset 61.3 4.74 11.04 Cost of facilities based on wastewater treatment plant with diffused air aeration and post aeration. 2 Capital and O M costs updated from 1979 to present day based on ENR = $4,200. 3 Total annual costs computed based on 8 1/8% over 20 years (CRF = 0.1028). ------- 2. QUINCY SHORES ASSOCIATION STAELLITE FACILITIES PROPOSAL A detailed proposal recommending the implementation of three satellite facilities in three different river basins in the south MSD was prepared and submitted to EPA for evaluation in this EIS during the NEPA/MEPA scoping process. The specific facilities recommended in this proposal are presented as follows: THE WEYMOUTH FORE RIVER BASIN That a regional advanced wastewater treatment plant be constructed on the 42” MDC Braintree-Randoiph Extension Sewer on Section 128A down- stream of the Braintree Cranberry Brook trunk sewer. This plant could have an 8-10 million gallon per day (mgd) capacity. It would discharge into the Broad Meadow wetlands along the Cochato River where it could replenish critical water supply resources for the towns of Braintree, Randolph, and Holbrook. A plant located at that point could remove the following flows from the Nut Island plant: 1990 2010 Municipality Average Peak Average Peak* Braintree (15%) 0.42 0.97 0.44 1.01 Holbrook 0.14 0.46 0.38 1.12 Randolph 1.83 4.43 1.92 4.62 2.39 mgd 5.86 mgd 2.74 mgd 6.75 mg. Water Supply. Braintree, Holbrook, and Randolph all share a common surface water supply, Great Pond Reservoir and Richardi Reservoir. Surface waters of the Cochato and Farm Rivers are diverted during peak flow periods to supplement the reservoirs. There have been recent water shortages and the dry-year safe yield of this system is marginal to meet the current demands. All three communities are included in the current MDC water study as potential future connections to the MDC water system. *A11 flow values from June, 1982, Nut Island Wastewater Treatment Plant Facilities Planning Project (NI-SOS). THE NEPONSET RIVER BASIN That a regional advanced wastewater treatment plant be constructed on the 54” MDC New Neponset Valley Sewer on Section 113 downstream of Westwood, Walpole, and Stoughton extension sewers. This plant could have a 35 ingd capacity. It would discharge through a dis- persion pipe laid along 1-95 to the extensive Fowl Meadows, which is underlain by high and medium yield aquifers, which are critical to the area’s water supplies. ------- Such a plant could intercept the MDC New Neponset Valley Sewer at Section No. 113. That sewer is a brick interceptor 54” x 60”. Again, using Facilities Planning Report Data, it could recharge: Municipality 1990 Average Peak 2010 Average Peak Allowing for infiltration as was done in the Facilities Planning Study, the plant would have an average flow design capacity of approximately 35 mgd. If such a daily flow were to be recharged in the Fowl Meadow, say along Route 95 upstream of the proposed plant site, it would provide a dramatic increase in water resources in the Towns of Canton, Norwood, Westwood, and Dedham. The major well fields of the Dedhain Water Company are directly down- stream of the suggested plant location. The Dedham Water Company has had shortage in the past and has recently lost some capacity due to contamination; they are actively attempting to join the MDC water system. THE CHARLES RIVER BASIN That a regional advanced wastewater treatment plant be constructed by intercepting the Wellesley Extension Sewer and the Wellesley Relief Sewer at the Easterly Connection Chamber and pumping to the plant located at the edge of nearby City of Boston landfill on Gardner Street in West Roxbury. It would discharge to the Cow Island Meadows along the railroad and Route 128, where they are underlain by high and medium yield aquifers serving water supplies in Dedhain, Needhain, Wellesley, and Weston. Municipality 1990 Average 2010 Peak Average Peak 1.56 mgd 0.93 mgd 2.49 mgd 0.00 0.09 0.32 15.97 7.72 18.00 0.00 0.22 0.65 7.36 3.34 8.19 5.30 2.24 5.41 0.00 0.06 0.24 0.00 1.06 2.75 4.28 1.85 4.49 14.31 mgd 34.47 ingd 17.51 mgd 42.54 mgd Canton 2.08 mgd 5.30 mgd 2.62 mgd 6.60 mgd Norwood 4.21 10.29 4.78 11.65 Sharon 0.00 0.00 0.26 0.78 Stoughton 1.15 2.91 1.62 3.92 Walpole 1.23 3.21 1.55 3.93 Westwood 0.54 1.49 0.82 2.16 9.21 23.20 11.65 29.04 Ashland Dover Framingham Hopkinton Natick Needham Sherborn Southborough Wellesley 0.55 mgd 0.00 6.86 0.00 2 • 98 2.17 0.00 0.00 1.75 24 ------- The plant size would have an average daily capacity of approx- imately 50 mgd. Such a plant could recharge water to aquifers containing wells of the Dedharn Water Company and the towns of Needham, Wellesley, and Weston. Also, the recharge could take place in part upstream of the MDC diversion structure on Mother Brook. This would provide much greater dry-weather stream flows for management of water quality in the lower reaches of the Charles and Neponset Rivers. The following excerpt from the QSA proposal highlights the benefits perceived by the authors to be associated with the facilities described above: These facilities could: Reduce the size of the presently planned wastewater and sludge treatment facilities at Deer and Nut Islands; Allow for future growth and expansion in the western suburbs of the MDC district; Provide economic reduction in the I/I and CSO problems in the Harbor area by flow reduction in major conduits; and Enhance recreation and water supply resources in the Weymouth Fore River, Neponset River, and Charles River Basin. The recommendation that the satellite facilities recommended in the QSA proposal utilize natural wetlands for effluent renovation and groundwater recharge to existing and potential public water supply aquifers required a multi-level evaluation of effluent discharge criteria in order to develop a basis for conceptual design and costing of the proposed facilities. A review of available literature on wetlands discharge - wetlands treatment capabilities was performed to define suitable hydraulic, organic, and nutrient loading criteria for wetlands to serve as a basis for determining wetland acreage requirements, for various levels of treatment to be provided at the proposed satellite facilities. A complete bibliography of literature reviewed in this regard is included in Appendix B. Based on this literature review, it was decided to employ the organic and phosphorus loading criteria used to develop wetland area requirements in a feasibility study of wetland disposal of waste- water treatment plant effluent conducted by IEP, Inc., under a research grant for the MDWPC ( ). This report employed a BOD loading rate of two gallons per day per square foot (2 gpd/sf) which is based on a loading rate equivalent zs ------- TABLE 6 - WETLAND ACREAGE REQUIREMENTS - QSA SATELLITE FACILITIES PROPOSAL Wetland Area Phosphorus Wetland Area Phosphorus Wetland Area Flow Required Load-CAS(l) Required Load-ANT(2) Required ( MGD) ( Acres) ( #/Day) ( Acres) ( #/Day) ( Acres ) Charles River Average Daily Design Flow 20.0 230 2002.0 1335 167.0 ill Peak Design Flow 50.0 574 5004.0 3336 417.0 278 Neponset River Average Daily Design Flow 12.0 138 1200.0 800 101.0 67 Peak Design Flow 35.0 402 3502.0 2335 292.0 195 Weymouth Fore River Average Daily Flow 3.0 34 3000.0 200 25.0 17 Peak Design Flow 10.0 115 1000.0 667 83.0 55 N - Phosphorus loadings based on assumed effluent phosphorus concentration of 12.0 mg/i for typical conventional activated sludge treatment facilities in New England. - Phosphorus loadings based on assumed effluent phosphorus concentration of 1.0 mg/i from advanced waste treatment facility. ------- to a dual media filter and a phosphorus loading rate of 1.5 pounds per acre per day... “based both on preliminary review of the literature (108) and the desire not to hydraulically overload the wetland, resulting in adverse effects to the ecological and hydrogeological environment.” Applying these criteria to the proposed facilities assuming effluent BOD and phosphorus loadings for both secondary (conventional activated sludge) and advanced wastewater treatment processes yield the wetland acreage requirements presented in Table 6. In recognition of the proposed discharge locations relative to goundwater recharge areas in or near existing public water supply well fields, the Massachusetts DEQE, Divisions of Water Supply and Water Pollution Control, were contacted to ascertain effluent limits and discharge requirements in light of revised regulations promulgated by DEQE in late 1983. The response from the Division of Water Pollution Control, dated December 29, 1983, which is included in its entirety in Appendix C, included the following remarks: “On October 15, 1983, the Division of Water Pollution Control promulgated a set of comprehensive water pollution control regu- lations (Title 314 of the Code of Massachusetts Regulations) which included detailed groundwater quality standards. These standards define groundwater into these classes (1, 2, and 3); Class 1 being defined as: “fresh ground waters found in the saturated zone of unconsolidated deposits or consolidated rock and bed rock and are designated as a source of potable water supply.” Since all three proposed discharges will be tributary to groundwater currently being utilized as public water supplies (Class 1), all discharges to said groundwater will be required to meet very strict discharge limits; see Attachment 1 (in Appendix C.l). The discharge limits would basically require that the effluent entering onto the wetland meet or exceed the Primary and Secondary Drinking Water Parameters; see Attachment 2 (in Appendix C.l). In addition, the Division is concerned with the periodic “pass through” of materials such as oil, heavy metals, solvents, phenols, and other highly toxic or contaminating materials which are not sub- stantially removed with conventional wastewater treatment processes and which could cause severe impacts upon these aquifers. to continuously meet Class 1 effluent limitations and to protect these valuable public water supplies cannot be provided. jTh Division strongly discourages the continued review of such subregio facilities as proposed by the Quincy Shore ------- Similar conclusions and recommendations were stated in a memorandum from the DEQE Division of Water Supply to the DWPC dated December 16, 1983, including the following: “Aside from the problems associated with determining the assimilative capacity of wetlands for pollutants, this proposal does not address other potential water quality problems. For instance, the proposal does not address the fact that very little control exists over the nature and quality of sewage. Presently, the regulatory manpower does not exist for monitoring illegal or haphazard industrial waste disposal. Many industrial contaminants cannot be detected, let alone treated, in standard wastewater treatment facilities. As a result, it is very likely th t discharges from the proposed “satellite” plants would ultimately result in the degradation of existing water quality in the receiving wetlands/aquifer. All things considered, water quality degradation is likely to occur either over the short term through problems associated with seasonal flooding/freezing of the wetland and/or the undetected discharge of a hazardous substance or over the long term by the gradual saturation of the assimilative capacity of the wetland. Because of these uncertainties and the problems that may ensue, the DWS must conclude that the Citizens Plan proposal for wastewater discharge into wetlands is an unacceptable risk for potentially degrading these vital existing drinking water supplies.” The complete text of the DWS memorandum is included in Appendix C. Although the statements of the DWPC and DWS strongly suggest that the facilities proposal by QSA not be implemented, a preliminary conceptual facilities design was outlined for the purpose of providing a basis for cost comparisons between the two satellite options. The conceptual design shown on Figure incorporates advanced wastewater treatment operations including primary settling phosphorus removal via chemical additions, conventional activated sludge secondary treatment, nitrification-denitrification and final settling advanced waste treatment processing. Treatment beyond AWT levels theoretically leading to wastewater reclamation includes mixed media filtration, carbon absorption, chlorination-dechlorination and post-aeration prior to discharge. Grit, sludge and scum processing and disposal operations are also shown on the schematic. Cost for each facility were developed using costs per gallon oj waste- water as derived from the updated cost estimates prepared for the MMA satellites. Capital costs were escalated by 25 percent and O M costs were escalated by 40 percent to account for the increased level of treatment provided. These increases are not considered to include sludge processing and disposal. Generalized costs for each of these facilities are summarized ------- in Table 7. While it is recognized that the accuracy of these cost estimates is open to question, it is felt that the estimates reasonably reflect the level of treatment provided under the conditions stated above. .( 2 I ------- PAGE NOT AVAILABLE DIGITALLY ------- TABLE 7 - COST SUMMARY - QSA WETLANDS DISPOSAL SATELLITE FACILITIES Capital Cost Annual 0 M Total Annualized Cost Facility Flow x 10 ) Cs x 10 ) ( 5 x 10 ) Charles River 50 MGD 115.8 11.14 23.04 Wetlands Satellite Neponset River 35 MGD 81.1 7.80 16.14 Wetlands Satellite Weymouth Fore River 10 MGD 30.6 2.65 5.80 Wetlands Satellite 1 Total Annual Costs based on 8 1/8 percent over 20 years (CRF = 0.1028). ------- 3. RELATIONSHIP OFSD-EIS SATELLITE OPTIONS WITh ON-GOING FACILITIES PLANNING IN THE SOUThERN MSD As a result of the decision to delete the EMMA recommended satellite facilities from further consideration based on the conclusions of the draft EIS, facilities planning was initiated for relief of critically surcharged interceptors in the southern MSD including the following: Wellesley Extension Sewer (WES) Framingham Extension Sewer (FES) New Neponset Valley Sewer (NNVS) Braintree-Weymouth Extension Sewer (BWES) In addition to the interceptor relief plans, a major infiltration/inflow (I/I) analysis of the south MSD was conducted by Fay, Spofford and Thorndyke. I/I studies were also prepared for the MDC in the communities of Ashland, Natick, and Frainingham, and for the area tributary to the proposed Weylnouth Fore River Siphon. An evaluation of the hydraulic capacity of the High Level Sewer was conducted in conjunction with the Nut Island Site Options Study which incorporated the I/I reports mentioned above in addition to revised wastewater flow projections previously discussed. Additional studies and reports which must be taken into account include the preliminary report on I/I removal submitted to Professor Charles M. Haar, Court-Appointed Master in the suit brought by the City of Quincy vs. the MDC by the Executive Office of Environmental Affairs in response to Procedural Order, Item No. 5, entitled “Banking/Trading and Greater Than 2 for 1 Program.” An overview of MSD I/I is currently being conducted by Camp, Dresser and McKee for the MDWPC. Consideration of these reports in the evaluation of satellite facilities is of considerable importance relative to the following issues: • Implementation time framCrelative to on-going impacts of presently surcharged sewers. • Impacts of uncertainties in present I/I studies on flow projections, design capacity evaluations for interceptors and treatment facilities and the projected or assumed reduction in the required capacity of the harbor treatment facilities. Based on the current state of completion of Step 1 and Step 2 facilities planning for the major interceptor relief projects (e.g., WES, FES, NNVS, and BWES), it would appear reasonable to project that construction of recommended ------- relief components can be completed within the next three to five years, con- tingent upon available levels of State and Federal funding. It is estimated that the time frame from Step 1 facilities planning to start up c& operation for any of the satellite advanced waste treatment facilities proposed will range from ten to twelve years. If the elimination of overflows of untreated wastewater due to surcharging conditions and the water quality degradation presumed to result from such overflows is to be considered a primary objective of the wastewater management programs of MDC, DWPC, and EPA being evaluated in this SD-EIS, then it would appear prudent at this time to recommend that the relief projects proceed to construction regardless of a decision to reject or to proceed with the proposed satellite facilities. The issue of the relationship between projected reductions in the required capacity of harbor treatment facilities as a result of satellite facilities implementation and the effects of estimated and measured quantities of I/I on the capacity of the sewerage and treatment facilites has not yet been resolved. Several factors have contributed to the lack of consensus or understanding surrounding this issue. Both revised wastewater flow projections and the evaluation of the capacity of the High Level Sewer (HLS) presented in the Nut Island Site Options Study (SOS) state that the results of the I/I studies in the south MSD system prepared for the MDC and community-specific evaluations were taken into account in their development and analysis. Flow estimates project a peak flow of 305 MGD in the 2010 design year. Hydraulic evaluations of the HLS under previous conditions conclude that the HLS can adequately handle up to 310 MGD. Flow measurements taken by FST and reported in their I/I study included values up to 420 MGD. The conditions under which the extreme of 420 MGD were measured are not clearly defined. It is important to note that although the capacity of the HLS is 310 MGD, the available pumping capacity at Nut Island is only 280 MGD. This constriction, in combination with extreme high tide conditions (e.g., spring high tires), or othez factors such as extreme precipitation and/or seasonal high groundwater could produce a “stacking” effect in the HLS which may have introduced large errors in flow measurement in the system. Further, the manner and extent to which the I/I data were incorporated into the revised flow estimates developed in the SOS is not clear. As a result ------- of a meeting held at DWPC, Metcalf Eddy has agreed to provide more detailed explanation of the incorporation of the I/I report into the flow projections. The issues raised point to the need for additional information including systematic flow monitoring at several locations throughout the south MSD. Also, it would appear necessary to remove the constriction imposed by the pumping capacity at Nut Is land by increasing the pumping capacity to equal the design hydraulic capacity of the HLS. This in turn suggests that the peak design capacity of the treatment facility serving the south MSD should also be equal to the capacity of the HLS as recommended in the SOS. Although the implementation of satellite facilities would theoretically reduce flows to the harbor facilities equal to the design flows of these satellite plants, it does not appear to constitute a safe, reliable basis for re$ducing the design capacity of the harbor treatment facilities by an equivalent amount. This in turn suggests that the implementation of satellite facilities should be delayed until it can clearly and reliably be demonstrated that flows in the south MSD exceed the capacity of the HLS and treatment system and that these excess flows cannot otherwise be economically removed from the system. 34 ------- C. EVALUATION OF SATELLITE OPTIONS Both of the satellite options were evaluated with respect to the major environmental issues and perceived benefits which have been identified for both options. These include flow augmentation, water quality and water supply recharge. Issues and impacts relative to siting of any of the satellite facilities have not been addressed at this stage of the EIS process as the satellite issue has not progressed beyond the level of a conceptual component of the wastewater management program of the MDC. 1. EMMA Satellite Evaluation (1) Flow Augmentation : A detailed analysis of water quantity impacts of the EMMA satellite facilities was presented in Section 3.5.1 of the Draft-EIS. The analysis concluded that the satellite facilities would provide significant streamfiow augmentation to the water resources of both the Charles and Neponset Rivers. However, the analysis also evaluated the future low flow conditions of the Charles River without the additional future flows of the proposed middle Charles satellite facility. This analysis incorporated consideration of two major factors which had not previously been considered with respect to flow augmentation which are the net water quantity exported from the Charles River Basin to Boston Harbor relative to the projected flow of the satellite plant and the impacts of projected increases in flow volumes from existing wastewater treatment facilities on streamflów during low flow periods. As reported in the draft EIS, only 13.0 MGD of the projected design flow of the middle Charles satellite plant originates within the Charles River Basin. The remainder originates in the Sudbury River Watershed or is supplied to the contribut- ing communities from the MDC water supply system originating in the Quabbin Reser oir. The draft EIS analysis further indicates that the projected increases in discharge volumes from existing wastewater treatment plants in the Charles River Basin totalling approximately 12.7 MGD nearly equals the net projected exported flow of 13.0 MGD, thereby offsetting the effect of exporting that flow to Boston Harbor. Although we concur with the analyses with respect to projected streamfiow conditions without the implementation ------- of the Middle Charles Facility, it must still be recognized that the addition of this satellite plant will result in substantially improved streamflow conditions. Questions raised in the draft EIS with regard to water quality conditions and potential impacts on downstream water supply resources are discussed in subsequent sections of this report. The draft EIS acknowledges the potential streamflow benefit of the upper Neponset satellite facility on the Neponset River, but concludes that significant negative water quality impacts offset any potential benefits to streamflow and water supply resources. Based on our review of the water quality assessment of the Neponset River, we concur with the conclusions of the Draft EIS. (ii) Water Quality : The assessment of water quality impacts of the EMMA recommended satellite facilities on the Charles and Neponset Rivers consists of a review and analysis of previous modeling conducted for the 1978 Draft EIS and a review of water quality data collected during intervening years for both rivers. As previously described, an extensive water quality modeling effort was undertaken by EPA( ) to assess the impacts of the Middle Charles satellite facility discharge on the dissolved oxygen (D.0.) resources of the Charles River under the prescribed 1Q10 flow conditions. A low flow version of the MDWPC stream model was developed and calibrated using data generated by the MDWPC from surveys conducted in 1973 by Erdmann et al. The low flow model was then used to evaluate the dissolved oxygen response of the river to the projected waste flows and loads from the Middle Charles satellite and other wastewater treatment facilities projected to be discharging to the Charles River in the design year 2000. The effects of the discharge from the satellite facility were also examined with the discharge occurring at different locations in the Middle Charles. The conclusions drawn from these modeling analyses were presented in Section A.3 of this report. In general, although the modeling indicates that the Class B water quality criteria for dissolved oxygen of 5.0 mg/l may be violated over some river segments, overall dissolved oxygen conditions would ------- be improved at specific critical locations under certain specified conditions as a result of the discharge of a satellite facility as compared to projected conditions without the satellite facility. The facility would be required to provide advanced levels of waste treatment bordering on the limits of reliable technology. While it can be argued that the proposed satellite facility will not result in attainment of Class B, D.O. levels at projected low flow con- ditions, the analysis suggests that the proposed facility could represent a potential benefit to the Charles River as D.O. levels were observed to increase under certain conditions with the addi- tion of the satellite facility as opposed to without it, and as the modeling suggests that non-attainment conditions are beyond the ability of point source treatment measures alone to achieve. The analysis provides limited evaluation of the issue of other residual pollutants from a satellite effluent discharge. The concerns raised by Metcalf and Eddy and MDC in the correspondence found in Appendix A and the responses of EPA staff to these concerns were reviewed with respect to model formulation, coefficient selection- computation, use of data within the model framework, and the limits within which the available information was employed within the Stream model to project impacts of conditions for which no data is/was available. Model formulations were reviewed with respect to the model description contained in the “STREAM 7A USER’S MANUAL”, prepared for the MDWPC in 1978 by Resource Analysis, Inc. No major changes in model formulations were found between the version of the Stream model employed by Erdmann and Ikalainen and those described in the 1978 User’s Manual. Based on our review of the work that was done by EPA and reported in the Draft EIS, we conclude that the modeling reasonably and adequately reflects proper utilization of the available data within the model framework and within the range of sensitivity and variability tested. Other issues were raised in the text of the Draft EIS which played a substantial role in reaching the conclusion stated on page 3-155 that: “The implementation of a satellite plant discharging to the Charles River is not recommended.” These issues relate to the ability of the unit treatment processes envisioned to provide the advanced levels of treatment required to result in improved D.O. conditions reliably and consistently given the variability of influent flow and pollutant loading conditions and the limited degree of control obtainable over these conditions. These are 31 ------- still valid concerns, although there presently exists a significantly increased amount of experience in the operation of advanced waste treatment facilities than was available in 1978. Another issue with respect to the water quality modeling raised by both EPA and MDC/M&E concerned the parameters and in—stream processes not accounted for in the Stream Model. Phosphorus is a particular parameter of concerning this regard due to its potential impact on algae and aquatic weed production, which in turn would be expected to impact on the magnitude and severity of D.0. variablity. A satellite facility even providing phosphorus removal to maintain effluent phosphorus concentrations on the order of 1.0 mg/i represents a significant increase in phosphorus loading from point sources in the Charles River. Incorporating these concerns with the considerations offered by the water quality modeling (i.e., that under certain conditions, some degree of benefit may be derived), leads us to conclude that a satellite treatment facility discharging to the Middle Charles River will be of limited, if any, benefit to water quality in the Charles River. Based on available data, however, it is not expected that such a discharge will, in or of itself, contribute noticeably to degradation of water quality conditions beyond present conditions. A sumary of water quality data from DWPC surveys in 1973 and 1978 is presented in Table 7. Partial surveys of the Upper Charles (above the South Natick Dam) were also conducted in 1980 and 1981. The more recent surveys (1980 and 1981) reflect major upgrading of municipal treatment facilities, including the construction of the Charles River Pollution Control District AWl Facility serving the Franklin—Medway area and the Millis—Medfield facilities. Average DO levels for all but one survey period from all survey years are shown in Figure 2. Note the consistent improvement in DO recovery downstream of River Mile (RM) 60 with successive years of operation of recently—constructed facilities. Note also the generally unchanged conditions upstream of RM 60 reflecting the continuing problems observed in the Milford area with respect to the municipal sewer and treatment systems in addition to int sources in the head water areas of the river. Comparisons between the six survey periods (June’73; ------- TAsAc7 7. CHARLES RIVER WATER QUALITY SURVEY DATA SUMMARY - 1973/1978 Dissolved Oxygen (mg/i) SOD (mg i) NH -N (m /l) NO -Il ( g/l) 6/73 9/73 6/78 7/78 6/73 9/73 6/78 7/78 6/73 9/73 6/78 7/78 6/73 9/73 6/78 7/78 6/73 9/73 6/78 7/78 FLOW SUMMARIES DURING SURVEY PERIODS (FLOWS IN CPS) Gauge Station USGS Gauge. Dover USGS Gauge, Wellesley USGS Gauge. Waltham 6/73 9/73 6/78 Temperature (°F) CHO1 8.3 7.5 7.4 7.1 71.3 77.0 64 77 1.7 3.6 5.1 1.9 0.07 0.04 0.01 0.04 0.2 0.5 0.2 0.1 CHO2 3.9 4.7 8.0 7.9 74.2 78.0 67 77 3.1 1.6 4.9 3.1 0.29 0.09 0.02 0.04. 0.1 0.0 0.1 0.0 CHQ3 4.4 4.2 6.1 4.9 70.8 75.0 64 73 6.3 2.7 4.8 2.4 0.20 0.32 0.03 0.10 0.3 0.3 0.4 0.3 CHO4 3.9 1.1 4.6 1.2 70.7 75.0 63 73 21.6 12.3 7.9 5.4 3.85 4.45 3.6 4.9 2.1 2.4 1.6 2.1 CHO5 1.8 1.4 3.0 0.9 71.0 76.0 63 73 4.8 7.8 5.4 4.6 3.45 6.2 3.6 4.3 1.4 2.0 1.4 0.6 CHO6 11.5 4.5 8.7 5.3 74.7 80.0 68 78 9.5 4.9 6.4 29.5 2.85 1.01 1.6 5.6 1.0 1.4 0.8 0.6 CHO7 3.3 1.9 5.3 2.6 70.8 76.0 66 75 5.0 4.9 5.1 6.6 2.00 0.92 0.88 0.89 1.1 0.7 1.4 1.2 CHO7B -—— ——— 7.5 5.2 -—- --- 66 78 --- ——- 3.1 3.3 --- --- 0.04 0.19 --- ——— 1.1 0.5 CHO7C —-- ——- 7.2 5.8 --- --- 65 74 --- -—— 1.9 2.5 --- --- 0.02 0.10 --- ——- 1.1 0.6 CHOB 6.7 5.5 7.4 6.3 71.1 77.0 64 75 2.6 1.8 2.7 1.6 0.13 0.13 0.04 0.08 0.4 0.7 0.8 0.5 CHO8A 7.3 5.5 6.7 6.0 71.9 77.0 64 79 4.4 2.4 2.5 2.4 0.13 0.36 0.10 0.38 0.6 0.4 0.7 0.8 CHO9 6.0 4.3 7.2 5.6 71.6 77.0 64 74 3.4 3.2 2.4 1.6 0.52 0.58 0.11 0.34 0.7 1.1 0.8 0.8 d uO 7.3 6.7 8.0 6.7 71.8 77.0 64 76 5.3 3.4 2.4 2.0 0.18 0.10 0.06 0.17 1.1 1.2 0.8 1.0 Cliii 7.0 7.4 7.2 10.7 73.7 79.0 65 70 4.0 3.6 5.0 3.6 0.07 0.25 0.03 0.01 0.8 0.5 0.6 0.0 CH I2 6.4 5.1 7.1 9.0 71.0 74.0 65 75 2.6 2.1 4.3 4.5 0.06 0.20 0.02 0.00 0.7 0.5 0.6 0.0 CH13 6.1 4.8 5.3 8.4 71.3 74.0 66 76 2.3 2.8 2.2 6.3 0.09 0.17 0.02 0.01 0.6 0.5 0.5 0.0 CH14 4.9 4.4 4.9 5.9 71.8 74.0 66 77 2.3 2.4 2.7 5.1 0.14 0.27 0.03 0.05 0.6 0.4 0.5 0.1 CH15 5.1 4.7 5.0 7.9 72.1 76.0 66 77 3.3 6.5 2.4 6.3 0.14 0.24 0.04 0.01 0.5 0.3 0.5 0.0 CH16 CH I7 6.2 7.0 5.7 5.9 5.4 6.5 8.1 7.6 72.4 72.7 76.0 76.0 67 68 77 74 4.1 5.4 6.0 4.6 2.5 2.4 5.5 4.0 0.07 0.06 0.16 0.14 0.04 0.02 0.01 0.05 0.5 0.5 0.3 0.1 0.6 0.4 0.0 0.0 CH17A --- --- 6.4 7.1 --- --- 67 78 --- —-- 2.1 4.0 --- --- 0:03 0.08 --- --- 0.4 0.0 CH18 ... CH19 7.2 6.9 7.0 7.0 7.4 6.9 6.6 7.3 72.4 72.6 76.0 76.0 67 67 77 77 4.1 4.2 4.6 6.0 2.7 Q.7 4.5 3.9 0.09 0.07 0.12 0.06 0.02 0.02 0.12 0.12 0.4 0.4 0.1 0.0 0.4 0.4 0.1 0.0 CH2O 7.3 8.4 8.4 12.3 72.8 76.0 68 80 4.8 6.3 3.1 6.6 0.25 0.05 0.05 0.59 0.4 0.0 0.4 0.1 CH21 CH22 6.9 7.4 7.8 6.8 8.3 8.3 11.2 7.8 72.2 72.6 76.0 75.0 68 67 79 78 6.6 4.4 8.0 7.1 3.9 4.0 7.2 . 6.1 0.25 0.28 0.05 0.07 0.02 0.04 0.30 0.38 0.4 0.4 0.0 0.1 0.4 0.4 0.1 0.2 CH22A --- --- 8.2 8.0 --- --- 67 77 --- —-- 3.9 6.3 --- --- 0.02 0.34 --- --- 0.4 0.2 CH23 7.1 7.8 8.3 10.2 73.5 76.0 67 79 5.9 7.2 4.0 7.0 0.24 0.06 0.01 0.09 0.4 0.0 0.3 0.2 CH24 7.4 6.6 7.8 8.0 72.1 74.0 67 73 4.1 5.1 3.7 5.8 0.27 0.08 0.01 0.08 0.4 0.1 0.3 0.3 7/78 149.2 105.2 199.8 73.3 134.0 111.2 198.2 79.4 170.8 141.6 257.4 98.6 ------- CHARLES RIVER WATER QUALITY SURVEY DATA SUMMARY — 1973/1978 Suspended Solids (mg/I) 6/73 9/73 6/78 7/78 Total Solids (mg/i) 6/73 9/73 6/78 Turbidity (NTU) 7/78 6/73 9/73 6/78 7/79 Total Kjeldahl Nitrogen (mg/l) Total Phosphorus (mg/i) 6/73 9/73 6/78 7/78 6/73 9/73 6/78 7/78 CR01 --- --- 0.29 0.97 0.03 0.02 0.04 0.73 1.0 18 5.5 1.0 --- --f. 125 68 --- --- 1.3 1.3 CR02 --- --- 0.34 1.2 0.06 0.04 0.05 1.0 1.0 19 1.8 1.0 --- --- 116 137 --- --- 2.0 1.9 CR03 --- --- 0.72 1.4 0.17 0.21 0.09 1.6 5 34 5.0 6.0 -—— --- 179 183 -—- —-- 2.3 3.9 CR04 -—- --- 4.3 5.8 3.55 4.60 2.1 4.3 4 22 16 1.5 —-— --- 241 256 -—- ——- 3.0 3.9 CR05 --- --— 4.3 4.4 3.10 4.00 1.3 4.2 1.0 37 5.8 5.2 -—— --- 271 220 --- —-- 2.9 3.6 CR06 --- --- 2.7 6.6 2.90 3.15 0.92 4.2 5 25 12 51 --— --- 216 305 --- ——- 2.5 5.7 CR07 --- --- 1.8 2.9 1.75 1.85 0.84 2.2 3 27 6.0 17 --— --- 190 202 --- --- 2.6 4.3 CR078 --- --- 1.4 1.2 --— —-- 0.60 1.5 --- --- 7.0 6.2 —-— --- 169 186 --- ——- 2.4 3.5 CHO7C --- --- 0.72 1.4 --— —-- 0.57 1.2 - -- -—- 6.0 4.2 -—— --- 169 262 --- —-- 1.7 3.6 CR08 --- --- 0.84 1.5 0.75 0.90 0.47 1.0 1.0 19 5.2 0.5 --- --- 170 157 --- —-- 2.0 3.1 CH O8A --- --- 0.45 1.6 0.48 0.35 0.59 1.0 6 32 6.0 2.2 --- --- 165 172 --- —-- 2.4 3.1 CR09 --- --- 0.89 1.4 0.93 0.93 0.68 1.0 1.0 17 4.5 2.5 --- --- 170 170 --- --- 2.4 2.7 CR10 --- --- 0.84 1.1 0.85 0.95 0.54 0.94 4 31 8.2 3.2 -—— --- 174 179 --- ——- 2.3 2.4 CHit —-- --- 0.72 1.6 0.88 0.63 0.40 0.44 5 22 10 28 ——— --— 149 129 --- ——- 2.1 5.0 CR12 --- --- 0.35 1.2 0.58 0.38 0.37 0.38 1.0 20 10 6.0 --— --- 274 113 --- —-- 2.0 5.1 CH 13 ——- --— 0.38 1.2 0.44 0.33 0.39 0.40 8 26 12 11 —-— --- 145 129 -—- ——- 1.4 4.7 CR14 —-- --- 098 1.5 0.45 0.35 0.34 0.44 6 33 10 18 —-— --- 177 130 --- ——- 1.9 4.9 CH15 -—- --- 0.88 1.4 0.45 0.35 0.34 0.41 3 25 8.2 7.5 --— --- 162 133 --- —-— 1.5 5.3 CR16 ——- --- 0.88 1.3 0.50 0.32 0.30 0.35 4 29 8.5 12 --— --- 160 171 -—— ——- 1.4 3.5 CHJ7 -—- --- 0.85 1.2 0.37 0.24 0.16 0.27 3 30 8.5 21 --— --- 141 150 —-— ——— 1.3 2.7 CH17A --- -—- 0.88 1.2 --- --- 0.18 0.26 --- -—- 6.2 8.7 --— -—- 140 146 --- ——— 1.4 2.7 CR18 ——- --- 0.83 1.3 0.36 0.23 0.21 0.29 4 27 6.7 8.2 --— --- 189 152 —-- ——— 1.5 2.2 CH19 ——- --- 0.91 1.4 0.36 0.20 0.17 0.28 5 36 8.5 16 --— --- 137 152 --- ——- 1.2 3.1 CH2O ——- --- 1.1 2.0 0.39 0.16 0.17 0.25 5 40 18 14 --— --- 153 156 --- ——— 1.4 6.1 CR21 —-- --- 1.0 2.0 0.33 0.18 0.17 0.22 4 42 11 17 --— --— 142 157 —-- ——- 1.6 6.7 CR22 —-- --- 0.95 1.9 0.28 0.17 0.16 1.2 3 31 20 22 —-— --- 171 184 --- ——— 1.5 5.3 CR22A ——- --- 0.90 2.3 --- --— 0.16 0.24 —-- --- 18 26 --- --- 156 180 -—- ——— 1.5 5.5 CR23 --- --- 0.88 2.4 0.26 0.16 0.20 0.20 7 28 16 14 --- --- 160 169 --- --- 1.6 12 CR24 ——- —-- 0.89 2.0 0.27 0.16 0.24 0.18 6 25 14 14 --— --- 176 168 —-- ——- 1.8 9.3 ------- CHARLES RIVER WATER QUALITY SURVEY DATA SWQ1ARY - 1973/1978 (Cont’d) pH (mg/i) Total Alkalinity (Std. Units) Total Coliform (#/lOOmi)(Geo. Mean) • Fecal Coliform (#100/ml )(Geo.Mean) CHO1 6/73 5.8 9/73 7.0 6/78 6.9 7/78 6.3 6/73 9/73 29 6/78 ‘11 7/78 9 6/73 740 9/73 19800 6/78 550 7/78 i50 6/73 --- 9/73 --- 6/78 17 7/78 5 CHO2 6.9 6.9 7.4 7.4 19 31 20 29 630 29900 220 80 --- - - - 7 7 CHO3 6.9 6.5 7.3 7.2 23 37 31 38 23000 52300 12000 12000 —-— --— 650 390 CHO4 CHO5 6.9 6.8 6.6 7.0 7.3 7.3 7.1 7.2 37 37 53 71 57 30 68 67 32000 16000 134000 56100 34000 9000 54000 1200 --— --- --- --- 3900 1100 6200 54 CHO6 7.4 7.0 7.5 7.1 37 45 38 58 630 13400 370 280 --- --- 16 5 CHO7 7.1 6.8 7.3 7.4 31 35 30 40 350 30000 2000 3300 —-- -- - 150 240 CH078 CHO7C --- —-- --- --- 7.3 7.3 7.3 7.6 --- --- --- --- 23 22 36 37 --- --- --- --- 610 1100 1600 320 --- --- --- --- 110 160 14 24 CHO8 7.1 7.0 7.2 7.4 19 30 19 32 2000 34600 1200 3400 --- --- 300 550 CHO8B 7.2 7.5 7.2 7.3 16 28 20 33 490 8500 730 1200 --- --- 130 150 CHO9 7.1 6.9 7.2 7.4 21 30 20 29 3000 40000 1600 1300 --- --- 270 53 CH IO 7.2 7.2 7.2 7.5 21 26 19 27 22000 29200 1400 1800 -—- -—- 380 240 CH11 7.2 7.3 7.1 8.4 18 27 19 25 1600 2400 1200 280 --- --- 100 24 CH I2 7.2 7.3 7.2 7.9 17 24 18 26 1700 25900 2400 420 --- --- 290 100 CH13 7.1 7.1 7.0 7.1 17 23 21 33 22000 16700 650 320 --- --— 89 23 CH I4 7.1 7.0 7.6 7.4 18 26 21 • 28 39000 52500 6920 84000 —-- --- 140 89 CH15 7.1 7.3 7.6 7.7 18 28 22 28 35000 77500 4700 7600 --- --- 56 28 CH I6 6.9 7.1 7.5 7.4 18 25 21 28 26000 13300 1900 740 --- - -- 75 14 CH17 7.1 7.0 7.6 7.5 18 27 24 28 3300 34500 650 • 170 --- -—- 51 20 CH17A —-- --- 7.7 7.3 --- --— 22 27 —-— --- 200 710 --- --- 20 20 CH18 7.1 7.3 7.6 7.4 19 27 23 28 2000 23100 720 710 --- --- 63 34 CH19 7.2 7.1 7.6 7.4 18 27 20 27 850 28800 690 600 --- --- 55 56 CH2O 7.1 7.4 7.5 —-— 21 29 23 35 1800 22000 940 240 --- -—- 130 60 CH21 7.2 7.6 7.7 8.7 22 29 24 33 5800 140000 1900 260 --- --— 180 74 CH22 7.3 7.6 7.5 7.7 21 31 25 31 1700 40600 8800 3700 --- -—— 220 1000 CH22A —-- --- 7.5 7.7 --- --- 24 31 --- --- 2200 4600 --- --— 400 460 CH23 7.4 7.3 7.4 7.7 24 32 22 31 5200 34600 1400 4800 --- -—— 80 400 CH24 7.3 7.0 7.5 7.6 25 32 23 32 20000 48600 9500 990 --- -—— 240 320 ------- CHARLES RIVER AVERAGE DISSOLVED OXYGEN MINE BK— HOPPING BK..— 1 fMILFORD SIP MILL BK NOT HER BK . DIVERSION rUWMILL BK. SUGAR BK — r— )GASTOW BK. r MEADOW BK. 1 —bIICKEN BK r—MEDFIELD STATE HOSP rST0NY BK. MILL STOP RIVER—I, RiVER— 1 rWA BAN BR. reEAVER 1 D é M aWPC. SURVEYS- 1973,1978,1980, & 1981 z w 0 0 (I) U) 0 RIVER MILES BK. ------- Sept. ‘73; June ‘78; July ‘78; July ‘80 and June ‘81) on a parametric basis are of limited value based on reported differences in stream flow conditions, water and air temperatures, rainfall and other climatic factors prior to and during each survey period. Generally, although average and minimum DO values have increased over the period covered by the data record, violations of the Class B criteria still occur. Violations of the Class B bacterial criteria of 200 colonies/100 ml continue to occur. Although the fecal coliform data for the June, 1981 survey period show a significant improvement over the portion of the river surveyed, the limited scope of the survey precludes assessment of improvement in downstream reaches. Nutrient loadings, particularly phosphorus, are of potential concern based on a review of chlorophyll—a data at stations comon to all surveys as presented below: ./J y CHLOROPHYLL-a (mg/rn 3 ) ,) iver 1973 1980 1981 () Mile Sta. Concentration Sta. Concentration Sta. Concentration ___ — ___________ — ___________ — ___________ J 76.5 CHO1 2.5 CHO1 0.81 72.0 CHO5 7.9 CHO5 3.32 CHO3 3.74 6O.1 CH1O 5.0 CH14 1.66 CHO9 1.08 44...6 CHI5_—__. 1L.8_. CH19 27.07 CH14 50.76 33.0 CH18 29.2 22.1 CH2O 92.2 18.3 CH22 90.0 9.8 CH24 60.8 Note: Chlor.—a data was not reported for the 1978 survey periods. Substantial increases are observed over the sampling periods covered at the sampling stations identified at RM 44.6. As chlorophi1l—a is indicative of the productivity occurring in a water body in response to available nutrient supplies, additional sampling over a wider area of stream coverage appears waryanted. As indicated in earlier discussions, the potential impacts of •increased nutrient loads from a satellite facility can be expected tobe reflected in increased productivity and chlorophyll-a levels. An area which has not been addressed with respect to a satellite facility is that of possible instream mitigation measures to reduce or ------- offset the potential impacts of the discharge, such as instream aeration, use of artificial wetlands for nutrient removal (and subsequent harvesting), or other alternative measures. /> ¶ The impacts of a satellite facility discharge to the Neponset River evaluated using a Streeter—Phelps analysis. The conclusions of this analysis were presented in Section A.3 of this report. Based on our review of the modeling discussion contained in the Draft EIS and Appendix 3.2.3—2, we concur with the conclusion that a satellite discharge would negatively impact the dissolved oxygen resources of the river. Again, although in—stream mitigation measures were not considered in the evaluation, the projected impacts are sufficiently severe on the Neponset River that any such measures may not be capable of providing a reliable degree of improvement. Water quality data for surveys conducted in 1973 and 1978 by the MDWPC are summarized in Table 8. Summaries of flow data during each survey period are also shown on Table 8, together with the 1Q10 low flows for each gauging station. As shown, the August, 1978 survey period flows are very close to the 7Q10 flows. Although DO levels generally appear to increase (both average and minimum values reported), periodic violations of the Class B criteria still occur. Much of the river is also in violation of the fecal coliform criteria, based on data reported in the 1978 survey. (Fecal coliform were not enumerated in the 1973 survey.) The imposition of a satellite facility to the upper Neponset River may be expected to reverse any trends toward the gradual improvement of water quality conditions in the river as are suggested to be occurring based on the available data. (iii) Water Supply : Potential impacts of the satellite facilities on water supply wells hydraulically connected to the main stem rivers downstream of the proposed discharges were identified as major concerns in the Draft ELS. The principal concerns relate to pollutants not removed by the treatment processes, and the inability to control influent quality to the treatment facilities. Under low stream flow conditions, when discharge volumes would comprise a significant proportion of total ------- ‘3 o’ 6 NEPONSET RIVER WATER QUALITY SURVEY DATA SUI’V4ARY - 1973/1978 Dissolved Temperature DOD 1*1 -N NO —N Total Phosphorus Oxygen (mg/i) (°F) (mg/i) (m /l) (in /l) (mg/i) 7/73 8/73 8/78 7/73 8/73 8/78 7/73 8/73 8/78 7/73 8/73 8/78 7/73 8/73 8/78 7/73 8/73 8/78 NEO1 8.9 5.4 7.5 79.5 76.2 2 6.15 4.20 4.0 0.00 0.270 0.02 0.00 0.00 0.0 0.085 0.125 0.10 NEO2 7.7 3.5 6.8 79.0 72.7 71 4.50 2.95 6.3 0.015 0.400 0.08 0.35 0.20 0.1 0.280 0.335 0.14 NEO3 7.4 6.1 7.0 76.8 71.9 71 3.70 4.05 5.0 0.020 0.265 0.09 0.40 0.40 0.2 0.170 0.205 0.12 NEO4 4.9 3.0 5.1 75.2 71.0 69 2.40 2.10 3.0 0.040 0.190 0.05 0.25 0.15 0.2 0.185 0.160 0.09 NEO5 6.7 6.5 7.8 74.8 71.8 69 3.20 2.60 5.0 0.030 0.150 0.01 0.30 0.30 0.2 0.165 0.135 0.08 NEO6 3.8 3.9 7.8 75.5 71.7 69 2.80 6.20 3.2 0.065 0.080 0.01 0.20 0.20 0.2 0.130 0.170 0.10 NEO7 4.8 4.5 6.7 82.5 78.0 77 3.50 1.80 3.3 0.085 0.190 0.02 0.25 0.30 0.1 0.100 0.105 0.06 NE08 6.7 6.8 8.1 79.8 76.6 74 3.20 2.50 3.8 0.040 0.200 0.03 0.25 0.25 0.1 0.105 0.100 0.05 NEO9 7.8 7.8 8.0 76.0 72.8 71 1.70 1.70 2.8 0.065 0.110 0.01 0.45 0.35 0.1 0.090 0.040 0.10 NEW 6.7 6.9 7.4 77.7 74.7 71 2.50 1.30 4.5 0.025 0.115 0.01 0.35 0.35 0.2 0.100 0.095 0.05 NEIl 5.6 5.7 6.5 76.2 73.1 70 2.00 2.20 2.7 0.090 0.175 0.07 0.35 0.65 0.4 0.105 0.085 0.06 NEI2 6.9 6.8 6.5 76.3 73.4 72 1.90 1.80 3.9 0.030 0.145 0.06 0.35 1.15 0.6 0.055 0.055 0.06 NE I3 5.0 5.2 5.8 75.6 72.6 70 3.00 1.80 2.8 0.080 0.110 0.06 0.35 0.45 0.2 0.095 0.090 0.05 NE14 5.6 5.6 6.7 77.0 73.2 70 3.15 2.50 2.4 0.135 0.175 0.08 0.45 0.35 0.2 0.170 0.135 0.06 NE15 6.5 6.6 6.9 76.5 73.3 70 3.45 2.00 3.2 0.120 0.120 0.19 0.45 0.45 0.4 0.180 0.085 0.12 NE I6 5.7 5.6 7.8 76.3 72.2 70 2.10 1.70 2.8 0.100 0.140 0.10 0.45 0.45 0.2 0.170 0.085 0.09 NEll 5.3 6.0 5.2 68.3 68.4 69 1.45 1.40 3.2 0.370 0.340 0.28 0.05 0.05 0.0 0.130 0.080 0.22 FLOW SUMMARIES DURING SURVEY PERIODS Average Flow (CPS) Average Flow 7/73 8/73 8/78 Gage Record 7Q10 fleponset River USGS Gauge at Non ood 36.0 46.8 11.08 51.8 4.9 East Branch USGS Gauge at Canton 45.8 47.8 12.08 50.6 3.4 ------- rIEPONSET RIVER WATER QUALITY SURVEY DATA SUI 1ARY - 1973/1978 (Cont’d) Total Alkalinity p H Total Coliform (mg/i) (Std. Units) (#/lOOmi)(Geo. Mean) 7/73 8/73 8/78 7/73 8/73 8/78 7/73 8/73 8/78 7/73 8/73 8/78 7/73 8/73 8/78 7/73 8/73 8/78 riLul 19.0 4.0 24 7.4 7.0 7.0 300 300 500 NE02 22.0 25.0 24 7.5 6.6 7.0 3000 2500 5000 NEO3 24.5 24.5 26 7.4 6.6 7.1 21000 26000 16000 NEO4 24.5 23.5 26 7.4 6.3 7.1 6500 5300 2400 PIEO5 23.0 23.5 26 7.4 6.6 7.1 24000 5000 6000 NEO6 21.0 25.5 28 7.5 6.8 7.2 34000 5000 15000 NEO7 21.0 28.0 29 7.3 6.9 7.3 11000 3500 3000 NEO8 21.0 27.0 30 7.4 6.6 7.2 9000 1900 1400 NEO9 20.5 22.5 23 7.4 6.8 7.3 35000 13000 4800 NElO 22.0 27.5 27 7.3 6.9 7.2 23000 11000 27000 NEll 23.5 29.0 30 7.4 6.7 7.3 12000 1000 9700 NE12 22.0 23.0 30 7.4 6.8 7.2 3700 15000 6000 NE13 22.5 24.5 30 7.6 6.6 7.2 7700 81000 1700 NE I4 24.5 26.0 30 7.6 6.6 7.2 29000 79000 21000 NE15 22.5 24.5 33 7.6 6.5 7.3 33000 62000 84000 NE16 23.5 25.0 33 7.5 6.8 7.3 12000 25000 50000 NE17 70.0 85.0 92 8.0 7.3 7.4 34000 12000 38000 ------- stream flow, it is possible that wells located near the mainstem of both rivers could result in drawing surface water in the river channels into the groundwater regime of the wells, resulting in potential health impacts to the populations served by those wells. While the concern for potential public health impacts is certainly a valid one, the assessment of risk associated with the proposed satellite facilities is difficult, given the long history of discharges of both treated and untreated wastewaters to both the Charles and Neponset Rivers. Given that there are no existing wastewater treatment facilities discharging to the Neponset River, it can reasonably be argued that the satellite facility proposed represents an unacceptable risk with respect to the protection of water supply resources. Given both the existing and projected wastewater flows from existing treatment facilities discharging to the Charles River, it cannot be clearly established that the discharge from the proposed satellite facility would represent an increase in the degree of risk of public health impacts, in addition to the risk that must be associated with existing facilities. Detailed hydrogeological investigations would be required to develop a reliable basis for defining the incremental risk associated with a satellite facility on the Charles River. 2. Wetlands Disposal Option An initial step in the evaluation of the QSA-Wetlands Disposal Satellite Option involved the determination of available wetlands within reasonable close proximity to the proposed sites for the three satellite facilities included in the proposal. Wetland maps for the Weymouth, Charles and Neponset River Basins prepared in 1976 by the Metropolitan Area Planning Council (MAPC) 208 water quality project were used to determine the acreage of inland wetlands located within 1000 feet radius and within a 1 mile radius of the proposed location of each facility. Table 9 sumarizes the estimated wetland acreage available within these two zones and compares the “available” wetland acreage with the previous estimate of wetland acreage required for each discharge as presented in Table 6. The estimated wetland acreage required is based on the phosphorus and BOD loading criteria as previously described. As can be seen, the extent of ------- TABLE 9 PRELIMINARY ESTIMATE OF WETLAND AVAILABILITY FOR WETLANDS DISPOSAL FACILITIES Treatment Wetland Acreage 1 Inland Wetland Area Inland Wetland Area Facility Required Within 1000’ (Acres) Within 1 mile (Acres ) P BOD Charles River 278 574 232.5 593.9 Neponset River 195 402 116.9 269.3 Weymou th Fore River 55 115 69.2 189.5 1 Based on phosphorus and BOD loading criteria as per Table 6. ------- “available” wetlands is dependent upon the selection of loading criteria used in the cases of the Charles and Weymouth Fore Rivers. The Neponset River does not appear to have a sufficient amount of available wetlands within 1000—foot radius to satisfy either criteria. The available wetlands within 6 miles of the Nepo js_etiacility would satisfy only. the phosphorus - - li Ing criteria . It is important to recognize that this estimate of “available” wetlands is based on available mapped information only and has not been confirmed by any level of field investigation of the wetlands identified. The estimate has not considered the ownership or other aspect of allowable or restricted uses which may affect the actual availability of a particular area. Finally, the costs which might reasonably be associated with an effluent pumping and distribution system which might be required under any of the treatment plant—wetland disposal area combinations possible. I L Based on the responses of the DEQE-DWPC and DWS to the subject proposal, which are presented in Appendix C and which reflect preliminary assessments of the proposal conducted by Maguire staff, additional evaluations were not conducted. The major areas of concern with regard to impacts are sumarized below. The development of the proposed satellite facilities present an unacceptable risk to public health and important water supply sources in the metropolitan region. As in the discussion of risk associated with the EMMA satellite facilities, the risks associated with placing a wastewater treatment plant discharge in intimate contact with existing clean sources of public water supply are unacceptable. Actual versus estimated wetland areas available and limits posed by the selection of loading criteria suggest that the scale of the wastewater facilities proposed is excessive for the safe application of wetlands disposal technology. Also, the use of wetlands for effluent disposal on a year—round basis could preclude the flow regulating function of natural wetlands which is an important aspect of flood storage hydrology in an urban area. This aspect may negate any potential benefits with respect to groundwater recharge. 11 ------- As pointed out by the DWPC and DWS, the renovation aspect of wetlands disposal is one of uptake and release. Experience with small—scale wetlands disposal projects relative to this aspect of facility operation and maintenance has led to the more prevalent practice of artificial wetland systems which can periodically be renovated by harvesting or dredging accumulated vegetation and decaying organic matter. D. CONCLUSIONS Based on the preceding evaluations, the following conclusions can be stated regarding satellite facilities in the South MSD: EMMA Recommended Satellite Facilities 1. Based on structural and hydrological analysis of the High Level Sewer (HIS) and revisions to wastewater flow projections (as reported in the Nut Island Site Options Study) , the HLS was found to be of adequate capacity and condition to accommodate flows up to 310 MGD without any relief requirement. Based on available I/I data, the HLS could see occasional peak flows higher than 310 MGD which have been estimated to reach up to 420 MGD. The development of the two proposed satellite AWT facilities to remove approximately 59 MGD from the south MSD system would not in and of themselves reduce these flows sufficiently to a level whereby harbor treatment facilities would be reduced in size. 2. Following the completion of necessary upstream interceptor relief projects, removal of limiting hydraulic factors in terms of pumping capacity at Nut Island, implementation of a flow monitoring program in the southern MSD, and a more realistic assessment of I/I reduction ( alternatives, the development of satellite treatment facilities in the south system versus other flow reduction/management options should be reevaluated as a priority in determing a cost effective and equitable solution to future system expansion needs. ------- 3. Based current updated facility plans of the MDC and their implementation time frame, it is our view that major interceptor relief projects currently proposed downstream of the sites investigated for AWT facilities would still be required to alleviate overflows and other surcharging conditions created by constrictions and other structural or hydraulic problems presently in the system, irrespective of a decision regarding satellite facilities. 4. The discharge of the AWl facility effluent to the Neponset River will have an adverse impact on water quality, particularly upon the dis- solved oxygen resources of the river. Additionally, during periods of low stream flow, potential public health/water supply impacts pose significant problems to public water supplies based on stream flow-groundwater relation- ships under low flow conditions and groundwater pumping close to the river. Potential public health/water supply impacts outweigh any potential benefit in terms of low—flow augmentation of the Neponset River. A satellite facility on the Neponset River is not recommended for further consideration. 5. The discharge of an AWl facility effluent to the Charles River may have a beneficial impact on the dissolved oxygen resources of the river even though water quality standards might be violated during certain periods. Increased phosphorus loads may exacerbate nuisance algae conditions in downstream reaches of the river. During periods of low stream flow)potential public health/water supply impacts may pose significant problems to public water supplies based on stream flow— groundwater relationships under low flow conditions and groundwater pumping close to the river. Potential public health/water supply impacts may outweigh any potential benefits in terms of low flow augmentation of either the Charles River or, via the Mother Brook diversion, the Neponset River. In accordance with Conclusion 2 above, at such time as satellite facilities are determined to be required to limit flows to the Harbor treatment system to the design limit of the HIS and treatment system, a satellite facility on the Charles River should be reconsidered incorporating consideration of possible in-stream and other impact mitigation measures as may be determined necessary. s I ------- Satellite AWT treatment facilities facilities proposed by Quincy Shores Associates, to be locate d on the Charles, Neponset and Weymouth Fore Rivers with discharge to adjacent wetlands, are not recomended for further consideration as part of the current facility siting analysis for the following reasons: 1. Development of these AWl facilities which would treat approxi- mately 97 MGD of wastewater would not provide sufficient flow relief or otherwise reduce the volume of flows in the MSD southern system in order to reduce the size of a harbor sited treatment facility. This is largely due to the existing adequate capacity of the High Level Sewer to handle all flows reaching it and sufficient excess volume wastewater flows to deliver a projected 310 MGD to a southern MSD harbor treatment plant. 2. All currently planned MDC interceptor relief projects are downstream of the proposed sites for these three AWl facilities and would, therefore, still be required offering no offsetting capital outlay savings. 3. The potential water supply/public health dangers associated with the impacts of discharge to a wetlands/watershed area are significant. The state has reviewed this proposal and has found sufficient elements of uncertainty and/or detrimental effect that they do not support this proposal’s feasibility. In particular, the issues raised about potential dangers from such a siting location include the expected pass—through of untreated organics and other potentially harmful materials, the more stringent groundwater/surface water standards that would be applied to such a facility’s effluent essentially resulting in drinking water standards, and concerns about such a facility’s operational limitations. These concerns outweigh any potential low flow augmentation benefits. 4. The limited availability of wetlands in close proximity to the proposed systems of sufficient size to accept effluent volumes of 10, 35, and 52 MGD as proposed, as well as limitations of the hydraulic and renovation capacities of the existing wetlands, suggests that facilities of such magnitude as proposed would be difficult to site. Required ------- hydrologic and wetland ecology evaluations are also expected to require a substantially longer implementation time frame. 5. The major capital costs of developing three AWT facilities, estimated to be considerably in excess of $238 million, coupled with major O&M costs annually, do not appear to be justified by the lack of potential benefits of such facilities relative to the need to site harbor treatment facilities. ------- APPENDIX A WATER QUALITY MODELING CORRESPONDENCE ------- .- /? (U /,.; (, ?-( .‘(..J ifl,,J,, I /ui,,’!. (J’Y{ O ’CE or -lE C - T . July 25, 1579 Mr. Thomas C. McMahon, Director Division of Water Pollution Control 110 Tren3nt Street Boston, MA 02108 Dear Mr. McMahon: Pursuant to our discussions of July 3, relative to the DWPC co,rnitr ent to do a Phase II Basin Plan for the Charles River, and in light of recent discussions between Mr. Al Ccoperman of your office and Mr. Jekabs Vittands of Metcalf & Eddy, we find that the following tasks remain to be carried out under the DWPC basin planning proc rm. 1. Cor.duct a detailed review of the Charles River model input values and develop their ranae of confidence . For example, theW jS modelling effort assumed_certain_values for_flofl flt source impacts and sediment deposit_impacts which e res 1ted in using up abàiiT 40 percent of the River’s oxyaen resources. Therefore, assumed values played the most significant role. 2. Conduct a detailed revie oL r od 1 parameters and develop _their rangeofcon:fidence. For example, the reaeration coefficients used by the EIS modelling effort in certain reaches .ere about ten percent of those used by the WPC E.asin Plan. Yet, both efforts reflect similar model calibration results. 3. Conduct sensitivity analyses on parameters and input data relative€ ir irnpact n satellite plant discharges. 4. Conduct field measurements to narrow the confidence ranges of those parameters and input data that impact water quality modelling based decisions on satellite plants. ------- .:r. Tr.cr3 5 C. Mc h o n , Director - 2 - July 25, 197 5. Make model runs and conduct analyses to provide the water quality modelling bases for determining the desirability of satellite plants addressing questions, such as: - Do dissolved oxygen violations occur with and without satellite plants? - If so, how often do they occur and how severe are they? - What water quality goals can be achieved with ar.d without satellite plants? Mr. Cooperman further indicated two additional relevant points. First, the modelling formulations for the Charles River have been carried out by the DWPC and have been verified. Secondly, OWPC plans to conduct the remaining tasks when new members of his staff have been sufficiently trained, but that results would not be available in the near future. Our interest is to insure that the necessary work will be reasonably scheduled so that future wastewater treatment decisions can properly be made. At such time that Mr. Cooperrian’s staff resume activities in tiis matter I suggest they contact and visit with Metcalf & Eddy personnel who have been involved with Charles River modelling review. I enclose for your staffs use a copy of some of this work as it relatI €ö EPA’s EIS n odelling on the Charles River. - - - If we have your concurrence the above tasks will be included in the Phase II Basin Planning, there will be no need for DC to do this work in the ut Island Facilities Planning. Please advise this office as soon as possible as to your concurrence so that we can finalize the scope of work for the Nut Island Facilities Planning contract. Yours truly, Martin Weiss Chief Engineer RG 3 : Enclosures (1 — 8, inclusive) cc: Al Cooperman w/o enclosures J b 2 1979 J .)iV 3 i r’r : ..T._-, Zi . - ,r.. ------- ?. Nl.m4R i€jic 3 / .., 2O eYJe1 S ree4 02’68 / i__ / /1 , J /I.; . 7/;7 -/2):;; April 26, 1979 Mr. Kenneth Johnson Special Assistant Environmental Protection Agency JFK Federal Building Boston, Mass. Re: Charles River Water Quality Analysis Dear Ken: I am writing because I believe some clarification of EPA and conducting the Charles River Water Analysis is needed. Attached is the Charles River Analysis section from scope of services, which outlines MDC’s work items. which we asked Metcalf Eddy to prepare, outlining EPA. We would appreciate your reviewing the rneinorandi.mi and scope to assure that we are in accord on our mutual responsibilities. Yours truly, Libby Blank Director of Environmental Planning LB/co cc: D.O’Brien, EPA J.Vittands, M E 1 MDC responsibilities in the Site Options Investigation Also enclosed is a rnemoran&rn, the tasks to be performed by Environmental Planning Office METCAI F & EDDY, I !C FILE...... :f;U 1 FD TO______ A PNS BY_ _____ Enc: 2 ------- — the b J r ’r .iLc sclcclicn nc]i. rj: — ‘CC ’1C! IC 3 — (‘IIV roimicntal irnp lct5, — ;ocia1. im ’acts, — t •‘c 1 Cal I , and — in Utution3l ii:ip cts. 13. . r ’ lvt c 1 inv’ i ption of Charles River l! Lcr C’ lity The pur ose of this invostiCation is to deterrn ne •;hether there is any opportunity for the discharge from an f• DC satellite treatment plant into the Charles River in conformance with The Clean l ater Act such that the pctential for reclar ation of wastewater, as well as the deployment of innovative technologies, can be considered. The investigation is intended as a continuation of the effort made byE?A during preparation of the EIS on the E!i •A study. Plthough the continuation Is to be a joint EPA—NDC effort, the major work is expected to be conducted by EPA wIth MDC participating in a program guidance, review and decision— making role. To this end, it is expected that EPA will carry out the following: — Update the EIS data base on the Charles River studies, especially with new information on wastewater discharges and recent field measurements. Prepare a file on that data base and provide a copy to MDC. — Review modeling formulations especially considering the results of such an effort carried out on behalf of the —12— ------- ;chi :-rt P vi i on or :, tcr Fo] ]ut :t’Cr:Y : i (“ ‘CI I tR !1l. i. ii ( %IC1 C!1 r{;c:; L — •icd i l’y Lhc i’oarnmu. ’dby EPI as nccc:;:.niy and ;r.. d 1 Lh f•DC, mci ud ii; c1 3ri cs nccd d to r rcptirc o it.rut In ncrc ii ab le Iormnt — u ce for and conduct a phy3ical i.n J)ccL ion (by boat, %:i crc a! Porz’ifltC) of the Charles River, a]so includir. pc r:;onncl selected by r 1DC. — Conduct a detailed evaluation of all para eters ein the modeling effort and jointly with MDC develop the range of confidence for each. - Arrange for free access for the project_participants to special experts where such are necessary for decision— making. — Conduct sensitivity analyses of parameters as necessary by supplementing computer runs made during the EIS and provide copies to MDC. — At locations where it is jointly agreed that further field Information is required for decision—making, conduct fIeld measurements. Such may include measurement of stream reaeration capacity. — Following development of ..a final agreed upon model of the Charles River, conduct model runs of jointly agreed upon conditions needed for decision—making and provide copies to MDC. — Prepare and print a jointly agreed upon report on study findings. Metcalf & Eddy’s function In this effort will be to assist ------- r:)C in this 1: r tiC .t ion s foJlo :s: — the Charle3 ivcr data baac fi]c t c:cic: ‘. .n(i ‘ dV1SC ‘.DC of pos tble ips needed to be fi] .d. — I rLicip tC in the phvsica]. jrirpection of the Charles lUvi ’r for nur;’oses of aiding in model prLrarflotcr selection. — A si ;L 1’iDC in evaluating the review of riodclthg • fot’ :nilat ions and of modeling done to date. — ;dvi c DC on model changes that are neccs ary or that will facilitate the review of results. — Assist MDC in the selection of a range of parameters for sehsltivity analysis. — Review results of sensitivity analyses and advise on final model adoption, including the conduct of discussions with special consultants and participation in the development of special field measurements. — Assist MDC in the development and evaluation of’ alternatives and in the development of’ recommendations . — Conduct reviews of reports and attend meetings as requested by MDC. 1 14. Assessment of Existing Nut Island Treatment Plant Conditions — Compile and review existing data and studies on the plant conditions and operations. — Make field investigations of physical features of the existing facilities including hydraulic and treatment capability, and equipment and structural work, as applicable. — Conduct detailed investigations and, If necessary, field testing of the condition and adequacy of’ major eau pment that is pertinent to the site selection process. —l 4— ------- os on jz o565 L /5/7a MEMORANDUM FOR THE RECORD The following presents a more detailed explanation of the work tasks expected to be conducted by the EPA as part of the analytical investigation of the Charles River water quality. — Update the EIS data base on the Charles River studies especially w .th new information on wastewater discharges and recent field measurements. Prepare a file on that data base and provide a copy to MDC. This task involves the collection and analysis of previous data and reports related to the Charles River. Included would be data from physical and water quality surveys conducted by the MDWPC and others; data from treatment plant discharges and industrial discharges; data on river flows; data from previous water quality modeling efforts; and any other pertinent information related to .the river’s water quality. The data should be analyzed to identify any treads, either beneficial or adverse, in the rivers water quality that may be evident upon review of the data. The history of the level of treatment and discharge location for all point sources should be investigated. The extent and frequency of low flow conditions on the river should be analyzed. — Review modeling formulations especially considering the results of such an effort carried out on behalf of the Massachusetts Division of Water Pollution Control (MDWPC) and identify model changes that may be necessary. This task involves a thorough analysis of modeling formulations used In the computer sImulation. An understanding of’ how the model uses the various input data should be developed. Recommendations would be made identifying model changes that may be necessary to properly represent the various processes occurring in the river. — Modify the program used by EPA as necessary and agreed upon with MDC, Including changes needed to prepare output In a more usable format. This task Involves the implementation of the needed changes identified in the previous task along with any format changes desired to enchance the readability of the computer output. ------- — Arrange for and conduct a physical nspecticn (by boat, where appropriate) of the Charles River, also including personnel selected by MDC. This task involves a physical inspection of sections of the river to develop a better understanding of the river’s characteristics. Possible limited spot checks might include cross— Ct1on measurements ,. velocity. measurements, depth measurements, extent. of sediment deposits, and the - collection of grab samples. A detailed field log would be maintaIned and any necessary changes to the various modeled river segments would be identified. — Conduct a detailed evaluation of all parameters used in the modeling effort and jointly with MDC develop the range of confidence for each. This task involves a review of the state—of—the—art r.ated to the various parameters used in water quality _ iodelIng. Included would be parameters related to such processes as BOD removal, nitriuication, reaeration, sediment demand, and photosynthesis. A range of confidence would be Identified for each parameter. — Arrange for free access for the project participants to special experts where such are necessary for decision-making. This task Involves making arrangements for the MDC to have free access to technical experts in areas where this Is needed, such as the areas of deoxygenation and reaeratlon in river systems. — Conduct sensitivIty analyses of parameters as necessary by supplementing computer runs made during the EIS and provide copies to MDC. This task Involves conducting computer sImulations to determine the sensitivity of the results to the range of values identified previously for critical parameters. In this manner tj e parameters most a.ffectlng the simulation results will be Identified. — At locations where it is joIntly agreed that further field informatioji Is required for decision-making, conduct field measurements. Such may include measurement of stream reaeration capacity. This task would involve making arrangements for the_conduct of special field measurements, where such have been identified as critical to the decision-making process due to the output from the previous tasks. METCALr & EDOY ------- — Following development of’ a final agreed upon model of the Charles River, conduct model runs of jointly agreed upon cond tions needed for decision—making and provide copies to MDC. This task would involve the conduct and analysis of computer simulations representative of conditions selected by the MDC. — Prepare and print a Jointly agreed upon report on study findings. This task would involve the preparation and printing of a report presenting the results of this investigation as agreed upon with the MDC. Throughout the conduct of the tasks described above, the MDC and Metcalf & Eddy would be involved In the investigation both directly in the technical analysis and functioning in a program guidance, review and decision—making role. Daniel W. Donahue DWD:dd METCALF & E OY ------- CS: :S: :- s_: E7 :, 93 Tt. • ‘p . a I • — . — - — — .. .. 4 .._ -— ._ — . .a . —. Consulting Engineers March 29, 1978 J— 5250 Ms. Libby Blank Director of Environmental Planning Metropolitan District Coriniss on 20 Somerset Street Boston, Massachusetts 02108 Dear Ms. Blank: Following our brief review of the mater a1s submitted to you by Mr. Wallace Stickney, EPA, dated March 1, 1978, on Dissolved 0xy en Modeling, Charles River, Massachusetts , and our attendance with you at a meeting with EPA on i•iarch 21, 1978, on the same subject, we felt it necessary to summarize our comments herewith. In general, the above—mentioned materials and meeting do not change the coniments made in our Memorandum on the Review of Dissolved Oxygen Mode1in , Charles River, Massachusetts , sub- mItted to you on January 10, 1975. In order to be brief, we will only touch on the more important points to provide further clarification. Model Formulation Accuracy As mentioned before, we have not checked the correctness of the program. However, we do suggest checking, for example, the temperature correction formu1at on for the upstream reach iflflOW. AWT Performance Reliability and Deoxygenation Rates We suggest checking the performance capability of the Marlboro Easterly plant to achieve the 5 rng/L BOD 5 and 1 mg/L NH 3 —N. NEWYORK PALQAL O C’ ICAGO ------- Y . L ..bby Ela.nk March 29, 1978 S .n±1ar1y, we suggest checking th±s plant’s effluent cha’acte’— Istics to determine the appropriate deoxygenatlon rates for AW? effluents. For further references on the change in deoxygenation rates with increasing levels of treatment for plant effluents and receiving streams, we suggest reading Professor Schroepfer’s pIoneering work on the Mississippi River*, as well as recent wcrk by the Geological Survey on the Willainette River in Oregonhl*. DocumentatIon of Assumptions and Hand1in of Dan Reaeration, T e of Flow, etc . - Againj we suggest that the sources of information be documented. For example, the sources of the data in Table 5 of’ the EPA Report need to be shown, to identify where such are from the BasIn Plan and where such are from other references. In our earlier memorandum we commented on some of the formulatIon used. Our concern was with the correct use of these and not with the answers they may produce. PhotosynthesIs and RespiratIon In developing the photosynthesis and respiration terms for water quality modeling, a set of selected K rates was used for the purpose of oxygen budgeting in the DICURV2 Program. Then a dIf- ferent set of K 2 values was used in the actual water quality modeling. This cannot be considered as a process leadIng to model calibration. Further, the photosynthesis/respiration information derived from the above calibration process was not used in the low flow sImulations. The input reflecting photosynthetic oxygen production was greatly reduced while the oxygen consumption due to respiration was held constant. FIgure 6 of the EPA Report shows a curve labeled ALGPO = ALGRA. This represents a conditIon where photosynthesis and repiratlon are modeled to In effect zero each other. Such a condition is more favorable to the oxygen resources of a stream than can be expected at night, when the respiration load is not canceled. However, the curve as shown falls below the range of measured DO values over most of the Charles River. Since these measurements G. J. Schroepfer, M. L. Robins and R. H. Susag, “Reaopralsal of Deoxygenation Rates of Raw Sewage, Effluents and Receiving Waters”, Journal WPCF, Vol. 32, No. 11, November 1960. **R. A. Rickert, W. G. HInes and S. W. McKenzie, “Methodology for River — Quality Assessment with ApplicatIon to the Willamette River Basin”, Oregon, Geological Survey Circular 7l5—M, 1976. ------- Libby Slank :arch 29, 1973 include nIghttime readings WhiCh are representatIve of river con- ditIons where there is a respiratlon load but no photosynthesls addition, calIbration should be adjusted to allow the curve to fall wIthin the range of field measurements; Reaeration Coefficients Undoubtedly the whole reaeration approach is a most important factor in thIs modeling effort. Again, one cannot use a different basis of reaeration in the development of photosynthesis and respiratIon budgeting the.n one would use in modeling the same data In the River. One cannot Use the wrong formulation to represent dam reaeration irrespectIve of the results. Wtth respect to selecting a formulation for stream reaeratlon, as stated In EPA’s latest submittal, there is no one formula capable of adequately predicting reaeration capacity in any stream. Thls includes the Tsivouglu—Neal formulation as well as the O’Connor— Dobbins formulation. The Tsivouglu—Neal formulation is am attempt at this. Covar’s paper (see EPA Memorandum, March 1, 1978 for reference) recommends a set of three equations, including the O’Connor—Dobblns formulation, for three conditions but does not recommend the use of the Tsivouglu—Nea]. formulatIon due to a considerable scatter in the data.” As an objection to the use of the O’Connor—Dobbins formulation (used by DWPC in the Charles River BasIn Plan), the EPA Memorandum, apparently using Covar’s paper as a basis, cites that the data used for its development were under conditions where velocities were greater than 0.1 feet per second —— a condition not occurring in the Charles River during low flows. Perusal of the Tsivouglu— 1eal data base, as It is published, did not show any data points with velocities less than 0.1 feet per second either. It should be pointed out that we do not necessarily subscribe to any of these formulas as being the most appropriate for the Charles River. Our feeling is that the impact of this parameter is sufficiently significant to warrant a sound basis for its determination. Impacts on Oxygen Resources Again, as modeled, the most significant impacts result from as- sumed data. On the basis of a limited review of the available data and without the ability to obtaIn computer runs we would have liked to see as input to our review, the following numbers can be only consIdered as crude approximations of impacts. ------- ::s. Li b:.’ Blank ?:arch 29, 1978 Cause Impact on DO in m /L Basis Sedinent oxygen demand 3 Rept. FIg. 15. El ]. and Gil. Cases Phctosynthes ls/ respiration 6 Rept. Fig. 16. D2 and E2. Cases Upstream plants Unknown i• DC satellite plant 1.5 Rept. Fig. 12. B]. and 311. Cases Nonpolnt sources Unknown Following the March 21st meeting, at which the last paragraph on Page 11 of EPA ’s March 1st memorandum was discussed, we reviewed the EPA computer run No. 368 which had been submitted as the basIs for the conclusions in that paragraph. As stated 2 the purpose o ’ the run was to test the significance of the oxygen demand from all of the treatment plants by reducing CBOD 5 to 1 mg/L and NBOD to 0. The run showed DO values significantly lower than those quoted in the paragraph. A spot check of the input data showed that the NEOD values had not been set to zero. A further check showed that the Input data had been further changed by raIsing upstream background water quality, by increasing K 2 in five segments, by decreasing K 2 In three segments, and by elImInatIng a small point source. Very truly yours, ekabs P. Vittands VIce PresIdent JPV:jfj ------- Metcalf & Eddyjnc . SC S:ai’torC S e : Sos:0 Massa: e S C 1 617 523. 9OOT VX 71C 321 635 Ca ,eAOOreSS M TEOD Boston Apr11 28, 1976 - ‘.‘ —1 Ir. Jonn Elwood E v1rozi- enta1 P1ann1r Dlvislon etropo11tan District Cor IssIon 20 Somerset Street 3t ston, assachusetts 02108 Dear ] r. Ciwood: As you requested, we have reviewed r. Folese’s ne-iorandu on the Charles River 1978 Survey. The memorandum implIes that this year’s survey will resolve some of the problems encountered in the co puter modeling of the river. AssumIng this to be one cf thc- goals of the sampJ.ing program, the following cor ents are made. 1. The sampling program should be conducted under conditions similar to those used In the modeling effort. That is, since the river modeling Is for \ /7 low flow conditions, the measurement program \ / should be conducted during dry weather under low flow conditions. Also, the timing should be flexible so that the program can be rescheduled If signIficant rainfall occurs prior to p1anned program. 2. In order to obtain dependable results from the modeling effort, it is essential to have all com- ponents sampled at the same time. Therefore, when the main stem is sampled, the point sources and at least the major tributaries, such as fine Brook, Stop River 2 and Sugar Brook, should also be a&’ipled. Net’ Yo,A Palo Alto Chicago rc— —0 ------- -. John lwood 2 ,_._ 1 . dI 3. i1th regard to additional sampling stations, it would be desirable to establish a station somewhere between river mile 70.3 and 66.1, where rnodelin o ’ the 1973 data indicates no dissolved oxygen. Stations should also be established above and below ajor point source discharges to aid in assessing their impact on the river’s water quality. (Eince no advanced plants are operating on the river, Perhaps monitoring an existing advanced plant, such as Marlborough, would provide valuable data in deter in1ng tile effects these plants will have on river water quality.) . Time of travel studies should be conducted in con- junction with the samplir.g program. 5. upplenenta1 flow gages should be installed and oper- ated before and during the sampling program. 6. Dam reaeratjon should be measured by measuring dis- solved oxygen concentrations immediately above and below the dams. 7. Sediment samples should be taken and analyzed to determine benthic demands. It is not necess y, however, that these samples be taken during the sampling program. For convenience, they could be taken either before or after the program. 6. Measurements should be taken from which determinations can be made of instream carbonaceous decay rates, nitrogenous decay rates, and reaeration rates. 9. The sampling program should include both daytime and nighttime measurements to aid in assessing the diurnal variation in dissolved oxygen concentrations and to ascertain the level of algal photosynthesis and respiration. 10. Groundwater samples should be analyzed to aid in determining the water quality characteristics of base flow under extreme low flow conditions. ------- ‘• jo F.wood Apr11 23, 1978 In sur unary 1 we believe that a considerable effort is requIred to re olie all the probleris that have been encountered in the ! ?A ater quality modeling effort. U recom end that tha sampling proGra! be caref 1ly designed and carrIed out so that the data collected will be useful in further studie3 of the Charles iver water quality. It you should have any queztions regardIng these co en:s, please do not hesitate to contact us. Vc ry truly yours, /1, )• , .1 ‘ .• — ona. ue Projec: : ineer WD: ob ------- N:EnORANDU 1 FOR THE RECORD BY: A. Lawrence Polese DATE: April 14, 1978 SUBJECT: Charles River 1978 Survey The Charles River 1978 Water Quality Survey has been scheduled by the Division for the week of July 17 — 21. The last intensive survey was conducted in 1973 in which both main stem and major tributaries to the Charles were included in the sampling runs. During March and April of this year personnel from the Division cdnducted two preliminary spring surveys, one on the main stem and one on the tributaries. The purpose of these was to collect background data and to investigate possible pollutant loads carried in runoff from snovmelc, and leechate resulting from high water tables. Results from chemical and bacteriological analysis are not yet available. This year’s survey will differ somewhat from the 1973 study. For modeling p . poses the entire main stem (minus tributaries) will be sampled in one run, whereas in 1973 the run was divided into Upper and Lower Charles runs. This was done in order to keep the runs from being too time consuming i.e., seven hours. By postponing the tributary stations a few days one complete run on the Charles can be accomplished. This was not possible in 1973 with the Upper and Lower Charles arrange- ment. Again complete runs should make modeling both easier and more representative of actual river conditions. The sampling stations for the current year are identical to those used in 1973 (see The Charles River Part A, MDWPC 1973). Since tributaries are being sampled separately, a more comprehensive survey is allowed. A list of tributaries to be sampled is attached along with a list of main stem stations. The selection of sampling stations and time of survey is not yet final. Addition/deletion of stations will be considered to make modeling as accurate as possible. This memorandum is to provide interested parties with an idea of how the Division is handling this year’s survey. Coiwnents and questions should be directed to Larry Polese at the Division’s Water Quality and Research Section, Westborough, MA (617—727—6983 Boston) or (366—9181, 9182 Jestborough). ALP / ro Attachment cc: A. Akalainen L. Blank Ii. Shaughnessy .1. Vittands ------- CHARLES RIVER ?t .IN STEM STATIONF CHO1 Dilla St., Milford CHO2 Cedar Swamp Pond Darn, Milford CR03 Howard St., Milford CR04 Mellen St., Hopedale CR05 Hartford Ave., Bellingham cR06 Box Pond Darn, Bellingham CR07 Rte. 126, Bellingham CR08 Pond St., Franklin—Hedway CR09 Elm St., (Shaw St.), Franklin—Medway CR10 Bent St. (Walker St.), Medway CR11 River Rd., Norfolk CR12 Forest Rd. — Orchard St., Millis—Medfield CR13 Dover Rd. — West St., Millis—Medfield CH14 Rte. 27, Sherborn—Medfield CR15 Bridge St., Sherborn—Dover CR16 South Natick Dam, Natick CR17 Central Ave. — Centre St., Needham—Dover CRIB Chestnut St., Needham—Dover CR19 Ames St., Dedham CR20 Kendrick St., Needham—Newton CR21 Elliot St., Needham—Newton CR22 Walnut St. (Wales St.), Wellesley—Newton CR23 Moody St., Waltham CR24 Watertown Dam, Watertown CHARLES RIVER TRIBUTARY STATIONS 1 Godfrey Brook — Depot Rd., Milford 2 Beaver Brook — Taunton St., Bellingham 3 Hopping Brook — Rte. 109, Bellingharn 4 Chicken Brook — Rte. 109, Nedway 5 Sheppards Brook — Elm St., Franklin 6 Mine Brook a) Rte. 140, Franklin b) Near Rte. 495, Franklin c) Pond St., Franklin 7 Miii River — River Rd., Norfolk (CR11) 8 Stop River a) Pond St., Norfolk b) Winter St., Norfolk—Walpole c) Campbell St., Norfolk c) South St., Medfield 9 Sugar Brook — Of f Dover Rd., Millis 10 Vine Brook — Rt. 109, Medfield 11 Bogastow Brook — Rte. 115, Nulls 12 Fuller Brook — Dover Rd., Wellesley 13 Waban Brook — Rte. 16, Wellesley 14 South Meadow Brook — At Charles River, Newton 15 Beaver Brook — River St., Waltham TOTAL STATIONS 19 ------- -- UN iTED STATES ENViPONMENTAL ? OTECTION A3E.; CY pEGIO .: j F KE DY FEDERAL BUILDING, aosro . chUS T S c:: 3 flarch 1, 1973 Ms. Libby Blank Director of Environmental Planning ::e r politan District Coc’.mission 20 Somerset Street Boston, MA 02108 Dear Ms. Blank: Upon receipt of your January 11, 1978 letter containing your corm ants prepared by Metcalf and Eddy on the Draft Report —— “Dissolved Oxygen Modeling — Charles River, Massachusetts”, Mr. Allen Ikalainen reviewed the comments closely. He has prepared remarks concerning each point addressed by Metcalf and Eddy. I have enclosed a copy of Hr. Ikalainen’s remarks. It is evident that there are some misunderstandings of what the report says. In particular, your comments concerning temperature correction for reaction rate con— stants which are temperature corrected, photosynthetic oxygen production 3nd respiration rates used in the model calibration, rtitrification rate constants in simulations at low flow and the discussion of dam reaeration reflect these misunderstandings. The attached remarks explain these points in detail. In addition to the specific misunderstandings mentioned above there are several items in your comments which deserve further attention. For instance, your comments on variations in river flow during the time of travel survey in 1973 and differences in river flow between the September 1973 calibration and projected flows in the year 2000 are discussed in the attached remarks. Also, your comments on sediment oxygen demand and the magnitude of their effect are considered in some detail. Your comment on in—stream reaeration raises Tsivoglou and Neal’s caution, concerning use of their method in impoundments. However, they raise the note of caution because the procedure may predict reaeration rates in excess of what they may actually be impoundments. The opposite is iridi— c..ited by the language of your comment. Again, the attached remarks explain these points in detail. ------- Your reco .- endationS raise an important consideration in understanding and interpreting modeling results. Sensitivity analyses should be done to determine which modeling parameters most greatly affect the results, in this case, predicted river dissolved oxygen levels. As mentioned in the attached remarks concerning your conclusions and recommendations, sensitivity tests on sediment oxygen demand, photosynthetic oxygen production and in—scream nitrificaciori rates are included within the report. We also point out subsequent to the modeling report and receipt of your con encs, sensi— ti ’içy tests have been done on deoxygenacion rates of plant discharges, bioche ical oxygen demand loads in runoff, treatment plant loadings and in—stream reacration. These sensitivity tests are not rigorous and have not been done to determine the effect on results from varying percent changes in model input, but have been done over wide ranges to determine the most sensitive input parameters in terms of their effect on results. It is evident that in order in—stream reaeration, treatment plant loadin , and sediment oxygen demand Although not yet tested, time of flow is undoubtedly an important para ecer also. In your recommendations, you have suggested confidence testing of each “factor”. In this case this cannot be done because the field data collected by the Division of Water Pollution Control in 1973, 1972, and other data developed by EPA does not contain any duplicate samples or replicate analyses or is not available in its original form. We agree that further investigation of assumed values or field sampling could provide more information to us. However, we question if the time and expense involved in time of travel measurement, sediment oxygen de:. nd measurement and tracer measurement of reaeration will provide information which will change our understanding of the river’s dissolved oxygen resources. We still believe there is a major doubt that the Charles River can assimilate the projected waste loads for the year 2000, after advanced treatment, and main- tain D.0. levels of 5.0. mg/i consistently during the surer_ g ;j Therefore, we question the advisability of discharging any more waste— loads_to the river than is absolutely necessar . r. Alan Cooperman of the Division of Water Pollution Control informed us that he is planning a water quality survey of the Charles River next summer and that he would like all parties involved in this modeling to decide upon any specific field measurements which we need to further calibrate and verify the model. I suggest that once you review the attached remarks we meet with Mr. Cooperman to discuss the need for additional field measurements. ------- Lastly, at several points in r. Ikalainen’s remarks h . . ha n i :ed t’r. t he tould review and consider any information that you or N tcali and Eddy might have to further elaborate on the points of discussion concerning deo ygenation rates of wastewatcr after advanced treatment, in—stream reaeration predictive methods and in—stream deoxygenation rates for strear s receiving effluents after advanced treatment. In this regard please contact Mr. Ikalainen directly. Sincerely, . Wallace E. Stickney, PE. Director Environmental and Economic Impact Office Enclosures cc: Mr. Alan Cooperman (MDWPC) ------- Ca=e n: on “ cmorandum on the Revicw of Dissolved ( ‘ cer. ? :adelin • Charles Rivet, fl3 sachus c ts ” (Co-z ents refer to paragraphs in sequence—first to last of the above 1emorandu:n) Paragraph 1. On February 9 and 11, 1977 I met with Mr. Alan Coopernan, ? t.TC at Wes:boro, MA. We discussed modeling of the Charles River for purposes of analyzing the effects of a proposed MDC Satellite treatment plant discharge on dissolved oxygen. The EPA — Environmental Iipact Office and their consultants were interested in the effects of the proposed discharge if the discharge points were located at points other than just downstream of the Cochrane Dam. This interest developed because of difficulty in finding a site for the satellite plant near the E> LA recommended location. Mr. Cooperman explained that Mr. John Erdmann had modeled the June and September, 1973 water quality conditions with the STREAM and DICURV2 models, but h d not developed a low flow simulation with the STREAM model prior to his leaving the MDWPC. Mr. Cooperman and I agreed that low flow conditions should be simulated with the STR.EAN model to analyze the effect of alternative satellite plant discharge locations. The Division did not have the resources at that time to develop the low flow model. However, r. Cooperman provided to me card decks of Mr. Erdmann’s September 1973 simulation, the DICURV2 program and its input data for June and September 1973, a memorandum on the use and development of DICURV2 and computer printout of the September 1973 simulation of the Charles River with the STREAM model. He provided this information so that I might develop a low flow simulation. Mr. Erdmann and Mr. Cooperman were planning on using the STREAM model and DICURV2 to determine wasteload allocations under drought flow conditions for inclusion in the Charles River 1976 Water Quality Management Plan. (Ref: Part C, Water Quality Analysis, the Charles River and Charles River Basin 1973, 1976 Page 65.) However, Mr. Erdmann’s leaving precluded this. In my report I have referenced this prior work by Mr. Erdrann in the ACKO LEDGE NT and on page 17 — last paragraph. Also in the model calibration procedures discussed on pages 18—32 of my report, Mr. Erdmann’s and thus the Division’s work is referenced repeatedly although each parameter is not specifically indicated as being developed by Mr. Erdmann. I have modified Mr. Erdmann’s model calibration input data for the September 1973 simulation in two major areas, in—scream reaeration and sediment oxv en demand. Reasons for and the details of these modifications will be discussed under com ents on paragraphs relating to those subjects, specifically. ------- 2. Th ‘.TC has reviewed the report in dctoil. rr .flLr ro rh s: - Office ( azcr Quality Section) has scheduled a water quality sur ey for t: Ch::les River Basin for the sunmer of 1978. The purpose of the survey is to u 3ta the past water quality information and to provide current infor o: or for development of a Phase 2—Water Quality Mar.a enent Plan. The Phace 2 Plan is intended to review and update wasteload allocations for point so :c ar.d to develop wasceload allocations for new point sources and non—point sources. The Plan is scheduled for completion in early C.Y. 1979 and .s being developed in coordination with NAPC and EPA. Paragraph 2. The impetus for this modeling did come from the EIS preparation. However, under the requirements of the Federal Water Pollution Control Act facilities planning cannot be funded by EPA unless there is an EPA a,proved basin plan among other require ants. Basin plans which apply to streams and rivers which are designated as water qu_ .zy ii .: cannot be approved by EPA unless vasteload allocations for point source discharges will meet water quality standards as set by the states and approved by EPA. Therefore, this modeling of the Charles which is considering the current approved wasteload allocations is part of the continuing water quality management process including facilities planning and wasteload allocation. It is also part of the EIS preparation which reviews the water quality impact of facilities planned to meet wasteload allocations. Paragraph 3. Recommendation 1 c. is based uoon the pure logic that treatment plants which would provide effluanc quality as seems necessary accorfing to this analysis would be very costly to construct, operate and maintain. Also, it is my understanding that there are very few large municipal treatment plants operating at levels producing effluents of 5 ng/i CBOD 5 and zero NH 3 —N and therefore one can only question the reliability of a plant to do so. One of the reasons that an EIS is in preparation is because a satellite plant will have a significant environmental imo.a t. Recommendation 3 does not recotr.mend that sewer service areas be limiced. It recommends in fact that “the water pollution planning process for the Charles River should include, as a possible control for future wascewater from MILFORD,..., the limiting of sewer service area and wastewacer loadings,...” Conclusion 4 says leaching from solid waste is known to occur in the Charles River. This statement is based upon Part D, Water Quality Management Plan — WPC 1976 — Charles River Basin, pages 17, 24. Paragraph 4. If the DC and Metcalf and Eddy will recall the meeting at which they were present in Westboro, MA at the Division Offices on May 27, 1977. ------- At t i : reetin; Mr. Coope an explained to all present that their cons ..i:. ’:, ?csour:c Analysis, Inc., wa reviewin; the nodel f u1 tion. As oi :h:s writing I has not cc ’lc:cd their a alvsis, but recent conversntion i: them indicates that the model is correct in the steady—stare form. Ai l, constants input to the model in this analysis are tenperature corrected by the model as explained on page 16. Reaeracion rates have been adjusre Thpward outside of the model by the temperature correction factor specified by Tsivo 1ou and Neal and have also been temperature corrected (an upward adjustment) within the model. This is explained in footnote (1) on page 30 of the report. In the year 2000 low flow simulations the Mother Brook diversion was inadvertently located at the downstream end of Reach 26 when it should be located at the head end of the reach. A low flow simulation has been run with the diversion located at the head end of Reach 26. The difference in downstream D.0. conditions as a result of this error is less than 0.1 mg/i for the case tested. Paragraph 5. The assumptions icade in the model calibration and the low flow .ode1 development are stated in the report. Also, many of the assumptions are the sa ne as those in the modeling portion of the approved Water Quality Management Plan for the Charles — Part D — WPC 1976. Paragraph 6. If one looks closely at the time of travel study data from April — May 1973 it is seen that river reaches between river mile 76.5—75.5 and 72.0-70.3 were surveyed on May 8. All of the remaining main stem reaches were surveyed between April 30 and May 4, inclusive. Flow variations at the Charles River Village, Wellesley and Waltham USGS gaging stations were 22 , ll and l3 of the minimum daily flow, respectively for the period April 30 to Nay 4, inclusive. Again, if one looks closely, the 2000 projected low flow with an ! WC satellite plant is seen to be about 7 times less than the average flows during the time of travel study. This is based upon the projected and measured flows at the three USGS gaging stations. The tine of travel—flow relationships used in the September 1973 and low—flow simulations are the same as those used in tha modeling of Part D— Water Quality Management Plan, Charles River, 1976 C Table VI—3 and are essentially the same as those in Appendix E of Charles River Water Ou 1jtv Study EPA—Region I, September 1971, except as noted in Table Vt—3. As explained in the Report on page 18 the work of Leopold and Maddock is the basis for determining the time of travel—flow relationships. This is a widely accepted procedure for predicting river velocity at varying flows. ------- 4. A rD:ed in the co:-ients Leopold and laddock d ve]oped the procedure fran data collected on “freely—flowin; streams witheut dams”. If this s in fact the case, then it is very possible that the relationship may predict velocities that are too high in the impounded reacnes. The relationshap somewhat underpredicts time of travel as measured in April— y 1973. (See Attached Table 1) Additional testing of the relationship at flows approaching those of the projected low flow with a satellite plant would be useful. However it will require a great deal of luck to schedule a tiie of travel survey to coincide with low flows being stead:: throughau the river and approaching the projected lowflows. I presume Netcaif and Eddy’s reference to “hydraulic efficiency” of impoundments is an attempt to explain that large, recent man—made impound- ments may retain the original river cross section along the bottom surface profile and that at extremely low flows the river will flow within its original channel causing lower times of flow. I don’t believe this is the case in the Charles River because I observed the river on August 16, 1977 when the daily average flow at the Charles River Village Gaging station was 58cfs or 28% less than the projected seven—day 10 year low flow as shown in Table 8 of my report. On that day the impoundments behind the So. Natick Dam and Cochrane Dam were fully impounded and velocity of flow was extremely slow. Floating algae were barely distinguishable as moving downstream. Further, I don’t believe the concept of “hydraulic efficiency” is applicable to rivers flowing through wetlands and lowlands, as does the Charles, with impoundments formed by run of the river darns. Paragraph 7. The September 1973 calibration includes pollutant loadings from Sugar Brook as measured on 9/4/73. The ?Iillis wastewater treatment plant discharges to Sugar Brook. In this particular case the model includes the loading from Sugar Brook which carries the loads frou’ Millis and Coct Corp. via the Millis treatment plant. I have not reviewed and compared the operating procedures in 1973 and 1974. Perhaps Mr. Erdmann did in preparing the model for calibration. 1r. Erdmann’s conclusion number 2 from Part C ‘ater Quality Analysis, 1973—1976, Charles River and Charles River Basin points out that non—point sources “undoubtedly degrade the quality of many more miles of stream than do the waste discharges and the sewer overflows, but in more moderate degree”. Paragraph 8. The second sentence in this paragraph partially reiterates a point discussed at length in the report on page 36 and 38. Non—point sources contribute much more CBOD 5 to the river than do point sources. The calibration simulation under predicts CBOD 5 loads in the river. For example, the total river CBOD 5 mass loading in pounds per day for the surface runoff, as assumed, is 83 percent of the total CBOD 5 mass loading from tributaries and point sources. Yet the CBOD 5 profile as simulated and shown in Figure 8 is consistently lower than the measured CBOD 5 in ------- 5. the r:ver for the river reaches below river mile 70. Figure 9 further en h .as :es the iagnitude of non—point source loadings to the river as ccnpared to point source loadings. The last sentence of paragraph S is not very meaningful and grOSSlY misrepresents the benthal oxygen demand used in the calibration. If one looks cio ely at Table 5 and computes the sediment denand values in te s of m;/l—dav it is seen that the naximum denand rate is 3.28 mg/i—day only in Reach 2. Furthernore, of the remaining reaches, three have sedir.enc d ands of 1.66 to 1.0 and the last 18 have sediment demands of 0.80 to 0.13. g/l—day. The discussion of sediment oxygen demand on page 29 of the report explains and justifies the sediment demand inclusion in the calibration modeling. The D.O. simulation of September 4, 1973 conditions as shown in Figure IV—5, Part C, Water Quality Analysis, Charles River and Charles River Basin apparently includes a sediment oxygen demand of 2.5 gm/m 2 /dav. This rate seems much too high, but nay result in a predicted profile close to the mean of measured values if reacration rates are also too high. Paragraph 9. The photosynthesis discussion in this paragraph is totally wrong . The calibration simulations as shown in Figures 6 and 7 represent average photosynthetic oxygen production and respiration and average photosynthetic oxygen production set equal to average photosynthetic respiration. This is e: :plainad in detail on page 32 of the report and is indicated on Figure 6. Thus photosynthesis is represented only as having a net D.0. production over a day or having no net D.O. production. No simulations are presented in the report with “zero respiration”. The discussion presented in Paragraph 9 of weather conditions is no: a complete representation of river flow conditions on September 4, 5 and 6, 1973. The river system cannot be viewed as simplisticly as in the cc=ents. For example, the streanflow data presented in Table 1 of the ceants indicates that daily average river flows at Charles River Village were higher by 31 percent on September 4, 1973 than on September 6, 1973. However, if we look at USGS recorded river flows on those days at e1lesley and Waltham we find that river flows were 15 percent higher and l7 lower, respectively on September 4 and September 6. The conrents fail to present this further information which indicates that higher river flows resulting from rainfall in the upper Charles Basin cannot necessarily be associated with higher 0.0. conditions during daylight hours. In addition, the comment fails to point Out or recognire that the higher DO’s referred to on page 36 of the report occurred predominantly during daylight hours. Looking at the data further in Appendix B the higher DO’s on September 4 occurred as peaks in diurnal D.O. variations ------- 6. cn that day, while diurnal variations were significantly lower on September 6. This bears out the conclusion in paragraph 5 of page 36 in the report that photosyn:hecic D.C. producticn on September A exceeded chat on September 6. This conclusion is also supported by the observation that at al’l but one location peak photosynthetic oxygen production rates, as determined by the DICURV2 analysis of John Erdmann, occurred on September 4, 1973. Lastly, as shown in Figure 8 and as discussed in the second and third paragraphs on page 38 runoff in the lower reaches of the Charles may contain si nificant CBOD 5 which would offset its dilution potential, even though the m joricy of D.C. demand effect of the runoff SOD would not be exerted until some days later. Table 1 of the comments contains two errors. First, there is no rainfall recorded on September 7, 1973 at the Boston WSO location. The Table indicates .44 inches as being recorded on that day. Second, the Data Sourae 1 as listed should be dated September 1973, not January 1973. Paragraph 10 — “Biochemical Deoxygenacion Rates” The background loadings as input to the September 1973 calibration simulation and the 2000 low flow simulation are about 5 pounds per day of CBOD . The concentrations of ultimate and 5—day carbonaceous biochemical oxygen emand, respectively are 10.6 and 4.2 mg/i. This total mass loading is input to the river only at r.m.76.5 and is based upon the CBOD 5 loadings measured at r.m.76.5 in September, 1973. This is a natural background loading and there is no infor iation or implementation plan to indicate this loading will change by 2000. As stated on page 43 of the report the deoxygenacion rate for the treatment plant loadings is a normal rate for biochemical oxidation. If Metcalf and Eddy and/or the C has data available on deoxygenacion rates for advanced treatment plants I would like to review the data for further consideration of the rate constants. It should be noted, however, that the rate constant within the range of .1 to .4 will not affect the results of the modeling analysis to a significant degree. Copies of simulations pointing this out are attached. I see no justification for decreasing K., rates in the river between 1973 and 2000. In 1973 the river’s water’ uality was predominantly affected by non—point sources, in particular below r.m.40. As stated in Mr. Erdmann’s conclusions as referenced on pages 11—12 and as discussed on page 38 of the report non—point sources affect the D.0. balance in the Charles River over many more miles of river than do point sources but to a more moderate degree and BOD loads in the river are attributable to algal mass and or SOD in runoff with D.O. incre3sing as BOD increases. ------- I. Also, as they are indicated on page 43 in Tahi 7 the t ca K 1 rates (hiocher ical reaction rates) range between .09—. 23. These are not high races jar streams of low to moderate pollution asl have seen and C::?erienced. Furthermore, if one does some simple calculazions, it can b seen from the data in Table 8 that the Charles River at low flow in 2000 w uid consist of between 50 and 80 percent treatment plant effluent with the effluent containing 5.0 mg/i CBOD 5 . This level of CBOD 5 is not analgous with high quality water or clear rivers, in my mind. Therefore, lower deox:’genation races in the river are not justifiable. Par graph 11 — Nitrogenous Oxidation Rate The discussion in this paragraph is not meaningful to the analysis of the report because the discussion in item 4 on page 56 under Cases A, B, E, C and H simulations and the D.0. profiles of figure 15 indicate that the simulation results are not very sensitive to nitrificacion rate constants of 0.6—0.2. With regard to the comment concerning “certain fot-ms of algae” caking “great inroads upon the ammonia supply”. Such a phenomenon has not bRen studied in the Charles River and is beyond the scope of this analysis. AJ.so, as will be considered under the discussion of Paragraph 12 it is probably not sound thinking from a water quality protection standpoint to count on highly variable algal populations, which are one of the Charles’ water quality problems, to mitigate the effects of oxidation of ammonia. Lastly, I don’t believe water quality simulation has advanced far enough in the understanding of algal and plant growth and death dynamics so that anyone could definitively quantify algal consumption of ammonia. Paragraph 12 The discussion in this paragraph has not mentioned at all the material. presented in the report on page 28 which considers both the Quirk and Eder and !astropietro dam reaeration prediction procedures. To reiterate that material, a comparative analysis of D.0. values downstream of each dam on the Charles as predicted by the two procedures and compared to measured values indicated little difference. At low floy, with an ! DC Satellite plant located downstream of the Cochrane Datii the Mastropietro procedure gave significantly higher 1.0 mg/i), DO’s due to dam reaeratiori at three dams, slightly higher DO’s (.2—.6 mg.l) at six dams, equal DO’s at one dam, and lower DO’s (up to 0.6 mg/l) at four dams. Here again there appears to be less than significant difference between the two procedures as applied in this ------- S. analysiS. Hawever, the rodel will he ‘od fi d to pred cr P.O. by th : astropietro procedure and the impact of the change evaluated b ca se the : !as:ropietro procedure is more logical and was developed frc’rn enpir cal analysis of measured darn reaeracion. Paragraph 13 — Stream Reaeration 1(7 The first paragraph of this comment has taken the work of Tsivoglou and Neal out of context giving the authors’ recommendations an incorrect in:erprecacion. Conclusion number 15 in the article referenced in the resort says in full: “15. Certain limitations of the foregoing predictive tro als should be emphasized, notably those that relate to scream segments in which tnixin is poor. Thus, although the pools that occur as the result of natural topography are incorporated in the results suc _- arized here, the predictive models have not. been derived for, and do not apply to, major man—made impoundments. In general, very small slopes and small rates of energy dissipation imply less turbulence and poor mixing and, consequently, relatively low values for the escape coefficient C.” As can be seen by observing the relationship as given on page 28 of the report, a low escape coefficient results in a low 1(7 value. Thus the relationship may be predicting 2 values which are too high for the long ir pounded reaches of the Charles. With regard to the second comment on stream reaeration it is useful to look at the facts of how and when “K 2 ’s” were predicted by the MDWPC in Part D — Water Quality Management Plan — 1976 and Part C — Water Quality Analysis — the Charles River and Charles River Basin. Page 71, Part D, indicates that the equation of O’Connor and Dobbins developed for channels having isotropic turbulence was used with the relationship (referenced to EPA) for a minimum These were applied such that the higher 2 yielded by either method was used in the modeling in this Basin Plan. Tables VI—5 and VI—6 indicate which 1(7 values were adjusted upward to a minimum value of 2.0/depth. If we first look at the O’Connor Dobbins relationship as described by Covar (1976) and Rinard (1976) we see that it was developed and tested on streams in which velocities ranged from 0.2 to 4.0 feet/sec and depths from 2 to over 30 feet. Table VI—6 showsthat velocities in 25 of the 33 reaches are between .17 and .001 ft/sec and 18 of those 25 have velocities less than 0.1 ft/sec. Also, if we look at the depths in Table VI—6 we see that most are near the lower limit of the range of depths over which the O’Connor—Dobbins relationship was developed and tested. ------- a :e:.:t, looking at the EPA relationship (developed by Hydroscicrice under con: act to Mitre Corp. arid EPA) in Appendix A of Sin lified ath > :ode1ir. , 1971, we see that the reference says that the reaeration rate X2 is equal to a transfer coefficient K, divided by the average deoth. “In the lover range, a minimum value in the order of 2 feet per day is an apprr’ximate limit” for the transfer coefficient. Thus Ka 2.0 ft/day is the minimum reaeration.coefficient predictable by this method. h There are two major deficiencies in this relationship. First, it is not logical that all streams of the same depth have the same reaeration ch racteristics. Second, the more recent work of Tsivoglou indicates that reaeration is not directly related to depth, but is only influenced by depth as it is related to crcss—sectional area and time of flow for a particular stream geometry. Now, if we look at reaeration rate coefficients as developed.in Part C — Water Quality Analysis Charles River 1973, 1976, we see on page 25 that the estimated values of K 2 on 9/4 and 9/6 are considerably lower than those of Table VI—6, Part D in sixteen of the 33 model reaches. As computed in Part D the 2 values in sixteen river reaches are higher when river flows are lower, when velocities are lower and when depths are lower than in September 1973. This emphasizes inconsistencies of the O’Connor— Dobbins relationship and the EPA relationship in reaeration prediction. The last part of the Stream Reaaration comment suggests that “alternative methods of computing K 2 which have been developed for conditions more similar to the Charles River should be investigated as part of a sensitivity analysis.” I agree that methods of computing K 2 which have been developed for depths, velocities and flows similar to those of the Charles River should be used in modeling the Charles. This is precisely why the Tsivoglou—Neal relationship was used. Covar (1976) and Rinard (1976) have examined the conditions under which relationships by O’Connor—Dobbins, Chufchhill, Owens Thackston and Krenkel, and Tsivoglou and a1lace were developed. Their work reveals that none of these more prominent relationships were developed for velocities less than about .2 feet/sec. Tsivoglou and Neal have tested, in their Energy Dissipation Model paper, the accuracy of the predictive models of O’Connor—Dobbins, Churchhill, Langbein—Durum, Thackston—Krenkel and Owens by comparing predicted K 2 ’s with K 2 1 s measured by tracer studies. “None of the models tested proved capable of predicting reaeration capacity within acceptable limits of error.” ------- 10. I would bc happy to review any predictive procedures fcr which : aif an E. dy and the C have inforitation describir.g their develop- e c under veloci:y conditions sicilar to those of the Charles River and based U O actual tracer measur_:.c- : f :eaeration. Para r2Dh l1 — Photosynthetic O :ygen Production and Respiration As described in the report on pages 31 and 3 photosynthetic oxygen p-oduc:ion and respiration rates used in the Septe:nber 1973 calibration siculat on are those developed by John Erdnann utilizing his DICURV2 model. Thus, the K 2 ’s used in determining the gross rate of photosynthetic ox gen production via DICIJRV2 are those estimated by Mr. Erdcann and repozted by the Division in Part C. , — Kfs as predicted by the Tsivoglou—Neal relationship were not used ‘with DICLR ’2 to give new photosynthetic oxygen production rates for incorporation in the calibration simulations of the report because there ‘was no purpose to do so. It would have the effect of giving higher oxygen production rates which would raise the entire solid line profile in Figures 6 and 7 of the report. This would indicate that the STRL 1 codel with these higher photosynthetic oxygen production rates more closely pred cts naxicum D.0. as measured on September 4—6, 1973 than it does mean or rninimum D.O. as measured. With regard to the comment concerning “future projected conditions” there again is evident an incomplete review of :- e report. Page 57. . . .. las: paragraph describes a low flow simulation in which the peak photosynthetic oxygen production rates are incorporated. This sinulation as shown in Figure 16 indicates that photosynthesis can cause near saturation D.O. conditions throughout the river. However, the discussion points out that this source of oxygen “occurs only during periods of sunlight, is not reliable and requires abundant algal populations to sustain it”. In this case, as in the case of algae utilizing ammonia thereby lessening oxygen consump:ion in oxidation of ammonia in the river, a water quality problem (high algal populations) should not be considered as a reliable oxygen resource to the river. Paragraph 15 — Conclusions and Recommendations As explair.ed in the previous comments the major differences between John Erd-ann’s September 1973 simulations and those of this report are in reaeraciori rates and sediment oxygen demand races. D.0. simulation results in the report show a somewhat higher D.0. profile for the September conditions than do Mr. Erdmann’s (See Attached Figure IV—5 from Part C— MD PC, as modified) I believe that the work in the report. properly represents the oxygen resources of the Charles River whether or not it is “unfavorable” to planning for utilization of the river for wastewater assimilation after advanced treatment such that some eighty percent of the river will be wastewaccr during low flow conditions. ------- z w (-9 >- >< 0 a Lii > -J 0 (I) (1) C) d sampling IloliOni ( (.i) (s ) —MOTIIEI1 UK. DIVEfl5IO?l L UK. I r 50 IJEI DO .’l OK I I _LLI J • : : @‘( :! .) ( ) ) ‘! DISSOLVED OXYGEN on SEPTI MF3ER CHARLES RIVER 1 C.’ C P1 U ’ RIVER MILES MUlE UK. — hOPPING BK.— ’ —CHICKEN BK. STOP —SUGAR 13K. —MILL OK. —BOGASTOW BK. — MEOFIELD STATE UOSR —WABAN DU. a” ------- 11. ? :es 55—57 of the rc?3rt e: 1ain why alternative tsc at r lo ::- an a1te ative river c nd::ions were simulated. If ?:eccalf a Ed nd the :•ijC will recall a : ng with the PC and EP.A at es:bort’, . u; s: 10, 1977, it was c;reed at that time that year 2000 icw fio : si ulacions would include alternative waszewdter loading and river co di: c- simulations. The scoring system waS developed to evaluate the relative differenccs betveen alternative simulations and was applied uniformly to all low flow simulations. The following comments relate specifically to the four recoriendatio s or: the last page of the Memorandum. The low flow simulations have been tested for their sensitivity both within the work which is described in the draft modeling report and in continuing modeling subsequent to completion of the draft report. - First , within the report simulation Cases A, B, and E demonstrate the effects of varying the nitrification rate constant from 0.6 to 0.2 day —1. Figure 15 on page 61 and Table 12 indicate that the simulated D.0. profile is not vety sensitive to varying the nicrification rate constant from 0.6 to 0.2 day . (Cases All and Ell). Simulation Cases G and H demonstrate the effects of the sediment oxygen demand. Figure 15 and Table 12 point out that even with zero sediment oxygen demand a D.C. level of 5.0 mg/i cannot be maintained throughout the river. Simulation Case D demonstrates the effect of having a net D.C. production due to photosynthesis at the rates of September 4, 1973. This is discussed on page 57, last paragr: h. Second , since completion of the draft report additional sensitivity test simulations have been run. Deoxygenation rates of treatment plant discharges (K 1 p) were set at 0.4 in the report; rates of 0.2 and 0.1 have been tested with conditions of Case E simulations as deEmed in the re,ort. These lower deo ygenacion rates yield a higher ultimate or initial CBOD thus producing significantly lower D.C. profiles than with a rate of 0.4. This is shown in the attached printouts of the low flow simulations. The sensitivity of the simulated D.0. profile to C30D 5 loads in the uniform distributed flow was tested under Case E conditions by reducing the CBOD 5 loads to 1.0 mgfl in all reaches. This resulted in no appreciable change in the D.0. profile as indicated in the attached printout. In order to test the significance of the oxygen demand of the treatment plant loadings a simulation was run with CBOD 5 loadings at 1.0 mg/l and with 30D loadings at ze This resulted in a D.C. profile which reached minimum values for D.C. of 3.5 mg/l behind the So. Natick Dam, 3.7 mg/i behind the Cochrane Dam and 4.9 mg/i behind the Silk Mill Dam. (See enclosed printout). This points out that the plant loads are a significant oxygen derranding sourcc. ------- 12. F.:rJt 3n rates were d%.mbl d as input to Ca E si ulat or s to test their se .sitivity. D.O. profiles resulting from this reveal : a: reaeraci is a najor determinant of D.O. levels in the Charles River. H :ever. even with doub1in of the rates predicted by the Tsivoglou— eai thod, there re ains long stretches of river with D.O. levels very mu r below 5.0 r;/l. (See enclosed printout). Comment Pre?ared By Allen J. Ikalainen ------- TA5LE I Ti a of Travel C2libration Char1 s River April 30 to ay 4, 1973 FLOW !E SLR 1EI T RIVER FLOWJ MEASU? ED2J SIMULATED J LOCATION cfs TI 1E OF TD!E OF (USGS GAGE) TP WEL, hours TP VEL, hours C RLES RIVER VILLAGE—r.t . 34.3 545 129 113 aT: N—r.m. 18.3 463 164 145 LESLEY—r. . 12.0 483 184 163 i Average of mean daily flows for 4/30 through 5/4, 1973. jJ Tine of travel between r.m. 76.5 and gaging stations. ------- R fererices Covar, A.P.; “Se1ecci ig th Proper Reaeratior Coefficient for Use in ter Quality Models”; Proceedir. s of the Conference on Envircnnen:al Mode1i g and Simulation — April 19—20, 1976, Cincinnati, Ohio; EP. . 600/9—76—016. i ard, I.E.; HCT DOSAC. River Oualitv Sirrulation Model, User’s Manual ; Halcon Computer Technologies, Inc., ew York; January, 1976. ------- 7L IC C SZ. SITIVI t ’f ZST SDIL’.TIo:;S The sic si :. 1 tIon upcn hIc the tcsts are ade is iden.ticel to th t of Case E con.ditions as described in. the Report (page 51-Ta5le 10) In.this case all plants era diEch rging at 5.0 /i CBOD 5 and 1.0 r /1 L 3 -N. Sedizent oxygen densnd is included as in the Sept. 1973 ca libratlcn sir.ulatlcn and In-stream nltrification rates are 0.20 day (base e). JC ;o. s :sITIvIrf TEST C QD 1OEd].n ifl unifcr r ncff Is 1.0 ! /1. 356 K 1 of plant wastes is 0.20 day (base e). 3 2 K 1 of plant wastes is 0.10 day (base e), J ll plant loadmn.&s to the river ar 1.0 z;/l only. 3 3 mn.-strea reaeraticn r tes are doubled in all reeches. ------- rr-i*redcp Er4rh , m r R ;CLLCSLI ¼r.. I& I. .. ;-mr - : .1 ‘, i:73 ‘ ‘ec mr n t’ - ?1 :m-ilz.— c. ‘c- t..ltt flctr- ct Cc—r.lss!on —- —‘ ; ., : —r’ --’ , - C .V CC .2/:1CtL :- -- : r :r:st :- - - - - — - - - -•_ — — — - ‘ S 1 - -. I ‘b L - _: : : - - . : --: : ‘o:. - ‘ rt__ 1 t:-v ::-vi- -:;.t-. ::_.t-i :-::t. :--; ,. c-r tl. :. - - •‘ • s--:;.: F. :ttz-n -i .L- ....? •w L i I ” - - - I - — - - Affit 5 -h. : ------- • ‘.—‘.... f_,. —.— — ..L DI 3LVED O:•YGEN NODELING C EARLES RIVER. ! 4ESACHUSETTS A signIfIcant part of the materIal presented in the report was developed by the Commonwealth of Massachusetts DivIsion cf Water ?cilution Control (DWPC) as part of Its Charles River BasIn Water ual!ty. Management Plan. Some of it was acknowledged ex lIcI:ly an some was not. It would serve the Commonwealth and the readers If the material that was taken from the DWPC work were referenced cx- plic±tly. On the other hand, the departures from the 3asln Plan and the basis for them should also be identified because the 3asln Plan Is resently the approved document for pollutIon control and waste load allocations in the Charles River BasIn. Therefore, any changes must be explicitly shown so that the Plan can be amended accordingly where such changes are adopted. The report Preface IdentifIes the purpose of the report as being “part of the wasteload allocatIon, facilIties planning and en- vironmental im act assessment procedures underway” In the as:ern : :assachusetts Metro olItan Area (Er !A). However 1 wasteload alloca— tICfl Is the responsibIlity of the DWPC through its basin planning process for which a resulting approved basin plan exists for the Charles River Basin. FacilItIes plannIng with itS envIronmental i ;act assessment, on the other hand, is the responsIbIlIty of the !DC a.id the municipalities. In the case of ?WC, thIs process is not being carried out at this tIme due to the prerecuislte EIS being prepared by the EPA. The document under review here Is a part of the EIS and not any of the above. The report Conclusions and Recommendation do not follow the data base reported upon in discussing treatment relIabIlity and economic and environmental impact costs. These are not addressed in the report itself. As an example, a recorr endaticn is made to lImit future service areas without an analysIs of alternatives or ccr.secuences, yet a conclusion is also made that septIc leaching cc— curs into the Charles RIver. The following review has not included a check of the model- ling formulation and the input data base whIch should be made. As examples, some of the rate constants used In the mcdel are tempera- ture corrected while others are not, and the Mother Brook Diversion is Incorrectly located in the runs representIng projected conditIons whereas it Is correctly located for calIbratIon runs. In evaluatIng the calibratIon effcr:s and fIndIngs, it must be understood that hydrologic condItIons were quite varlabl C durIng the calibration erIod, that data fcr d!schar es used In calibratl:n are for conditions one year later than the stream water qualIty survey ------- an : -.at a siznificar.: com:cnent cf the Inout da:a a e usa f r caii ra:±cn Is assumed. DurIng the water qualIty survey period used for calIbration, stream flows were ten times those of the low flow period. During this time, the average daily flows varIed by more than thIrty percent as a result of signIficant upstream raInfall that occurred just pricr to the survey period. The time of flow n various parts of the river Is a signIfIcant modeling parameter and, In thIs case, it was devel- oped from relatIonships formulated for freely flowIng streams wi:hcut dams. The constants for this relationship were developed under flow conditions that were about three to four times those during calibra— tion; but about thirty times those later used for modeling of prc— jected future condItions. DurIng the extremely low flow regIme In an area with im oundments the time of flow must also lncorporate the hydraulIc efficiency of the impounded areas. WIthout such an analy- SiS, a larger time of flow may result. With respect to the waste discharges used, the dlfferences In operating procedures between 1973 and 19714 must be revIewed. For example, in 1973 Cott Corporation discharged its wastes to the 1111— 115 wastewater treatment plant. In 19714, however, It dIscharged directly to Sugar Brook. A number of values Incorporated in the calIbratIon process were assumed. Assumed values for nonpoint sources total to 140 percent cf the total wastewater point source discharges. Simliarly assumed are sludge deposIts which are formulated to take up as much as 3 ng/1 of dIssolved oxygen, or nearly 140 percent of the river’s oxygen re- sources. Another sIgnificant factor in the calibratIon Is the photo- synthetic oxygen production and algal respIratIon phenomena. As modeled, ifl some locations of the Charles River, this, combined with sludge deposits mentioned above, can take up as much as the entire river’s oxygen resources. The basic formulation assumptions of this and other parameters are dIscussed later. Here the dIscussion cen- ters around their use in the calIbration process as presented on pages 32 through 35 of the report. Figure 6 (page 3 ) presents the sImulation of zero photosynthesis and zero respiratIon (dashed line) su eri pcsed on the range of four measurements (two night time and twc day time). With zero respIratIon, the simulation should show a favorable DO condltion as compared to DO measurements at night zinc which Include respIration. As shown on Figure 6, the simulatIon generally falls below the measurement range indIcating the need for a revIew of the modeling oarameters used. A further need Is to re- view weather condItIons surroundIng the 1973 survey period to insure that all factors are consIdered in the evaluation of the photosyn- thesis and algal respiration phenomena. For example, the weather condItIons discussed on page 36 of the report do not fully cover the survey condItIons as shown in Table 1. For example, the favcrable water ouail:y in the Charles RIver on September 14 can also be ac— :ri5 ted to ItS increased flcw resulting from the September 1 rai .— f 1l as well as favcrabie sunlIght condltions on that day. ------- TABLE 1 AVI I1A0E DAILY RAINFALL AND RIVER FLOWS iN TIlE ChARLES RIVER BASIN AREA, SEPTEMBER 1 TO SEPTEMBER 10, 1973 Location Boston WSO Blue hills Frami ngham Wa] po le West Medway Fran Ic 11 n Milford Char)es River at; Charles River Village 1.3 11 1.01 .36 98 115 120 116 103 88 99 125 (1) no rainfall (2) ti’acc :ia1Irce 1. UniLed 3taLes Department of Commerce, U.S. Weather Bureau Climatological D La: hew I•:n 1an(1 , Vol. 85, No. 1, Asheville, N.C. , January, 1973. 2. tIn I t.ed SI;aLc Department of the Tnter br’ , (leol optca) Si rvey , WUer__He ;oi I ni fin r.achiu;cL L3 , New Ilnmpsh Ire, Rhode inland 1 Vermont , Ilonton , finns . , ] 973 1 2 _(1) .01 3 02 .07 It eiri Rainfall (inches) Iliver Flow (cfs) Time, days in September , 1973 T(2) ‘F .1111 .1 11. 1 1.30 — — U 9 T1 .27 .18 .39 .60 .08 .78 — 80 1.80 .68 1 311 ------- : : €r— ca1 xv enat n Rates In the computer modelIng effcrt, deoxy nation rate :cn— sta:-its, K,, are input In associatIon with the wastelcad charac:eris— tics of tfle fol1ow ng fIve areas: 1. background K, 2. stream K 1 3. treatment plant dIscharge K, 14 tributary K 1 5. unIformly distrIbuted flow WithIn the model, all of these K 1 rates, except the stre -n K, , are usec only to compute the ultimate BOD. All decay occurs at The stre K, rate. ThIs results In the followIng ultimate 30D concen— ;rati.ons entering the Charles River in the year 2000: Source Ult. 30D m /l background 10.7 treatment plant 5.8 trIbutary flow 5.1 unIform flow above r.m. 141.1 6.0 below r.m. 141.1 9.0 The background conditions reflected above were used in bc:h the 1973 calIbratIon run and the 2000 low flow runs. These loadings seem ex eeding1y high, particularly for year 2000 condItIons. In regard to treatment plants, in the year 2000 simulatIons the report used a decay coefficient of 0.140/day. SInce these plants would be advanced, the organic material remaInIng will be resistant to decompositIon and therefore a lower K, rate can be justIfIed. As mentioned previously, all deoxygenation Is carried out at the stream K rate. In the computer simulatIons, the same K 1 rates were used in the year 2000 runs as In the 1973 calIbration run. I; has been shown that as water cual ty conaIt ons im rcve, tne ceoxy— genation rates decrease. Therefore, with the anticIpated u zradThg of the Charles River water quality, K 1 rates should decrease under 2000 condItIons. ------- : : :‘o:encus Oxida:ior. a:e In the modelir.g effort, the report a umed the : : s decay rate to be .6 day 1 (or 2 day ‘ n sore casec) 0 6 value is extremely high. All treatment plants considered in the investigation d scherge dis nfected effluents to the rIver. Chlo— rination effectively kIlls all n1tr fy1ng bacteria in the discharge. ffluents not carrying theIr own seed of nltrlfylng organIsms are subject solely to the natural seed occurrIng In the river water Cr in attached growths on the bottom and on submerged cbjects. In addition, ammonia is a prime nutrient for certain for s of algae. With’chlorination of effluents, these algae will pcssibly make zreat inroads upon the ammonla supply and thereby reduce the amour.: of ammonia avaIlable for oxidation by nitrlfylng bacteria. Also, the range of oxIdation rates found in the reference cited by the report is actually .i to .6 day —1. Da Reaeration The report chose to represent this phenomenon by a reia:i:r.— Ship developed by Quirk and Eder. This relationship was developed to represent reaekation through a vented turbine and not for free fall over a dam. Due to the lack of data, the authors used a linear relation between Fd(Q) and Q which passes through the origin. This assumption results in low reaeration rates under low flow con :icms, which is not correct for a free fall over a darn when more cf the overflcwlng water mass is exposed to the air and subject to reaera— ticn. A representation of darn reaeration which relates reaerat cn to the height of fall over the dam, such as that developed by Mastropietro or Foree, would give a better representation of actual darn reaeration under low flow conditions. Such a formulation was also used by the DWPC in their Basin Plan. Stream eaeratIon • 2 In—stream reaeration was computed usIng a relationship deve— oped by Tsivoglou and Neal. The relatIonship states that the reacratlon rate in a reach is a functIon of the change in water sur- face elevation along the reach and of the time of travel :hrc gh the reach. The authors caution users of their formulation in applying it to rivers whose physlcal characteristics are predcmir.anzly con- trolled by dams. As an example, for the projected future conditions, the ‘s computed under thIs method are on the order of ten :ercent of those used by the DWPC in a number of reaches. Therefore, alternative methods of computing K 2 which have been developed for conditions more similar to the Charles River should be ±nvest!gated as part of a sensitivity analysis. ------- Fs:: e:io C’xy en ?rdu::ion and The e:hod of acccunt ng for pflOoEynhe5 E and reEra: .: Lsed in the report modeling was based on work perfcr ed by the :.?: using the systematic diurnal curve analysis. The baslc fc aticn Is: = K 2 (C 5 —C) + — R, in whIch: DC = the tIme rate of change of DO concentratIon, = the rate of atmospheric reaeraticn, K 2 = the atmospheric reaeration constant, Cs • = the DO .saturatlon concentration, C = the DO concentration, P = the gross rate of photosynthesis by the cc unIty of algae and plants in the rIver locale, = the gross rate of deoxygenatlon, including res- piration and nitrification, by the entIre cc r.munI:y of organisms In the river locale. In 1973, the !VDWPC conducted DO measurements on the Charles iver. These measurements, together With the determination of resulted in a relationship from which P and could be determined. As can be seen, the value of H — P is dependent on the value of K 2 used in the analysis. The value of R, so determined, is a total deoxygenation rate which includes CEOD, NBOD, and sediment dei and. Therefore, in goiflg from the total deoxygenatlon rate to that rep— resentati th of algal respiratIon, all other oxygen demands must be subtracted. This process is in turn a function of the C3CD and N3cD decay rates and the sediment demand. In the model calibration pràcess used ifl the report, the values of phctosynthetic oxygen production and oxygen consumption due tc algal resciration aDoear to be those as determined by the D •ZFC usI z theIr estImatIon of K 2 tS. However, when the photosynthesis values were Incorporated into the river basin model for callbrat!cn and for simulatIng future projected conditions, the report used the lower K 2 values as dIscussed earlIer. In addItion, under the future rcjec:ed conditions, the input values of algal respIratIon are the saie as the 1973 calIbratIon runs, but the values representIng photosyn:he:Ic oxygen production have been greatly reduced. If anything, i.t would seem that the photosynthetic oxygen production would increase under the culescent low flow conditions. The basIs for the manipulatIon of D ?C’s data In the 1973 calibratIon run, and the basis for the dras- :ic reduction in ho:csynthetIc oxygen productior. w!:ile cxy en c:n— sur ::icn by algal respiration is not reduced in the pro ec:ed cbndl:ion simulations, need to be determIned. ------- — r — —. • c — — — — — —— — — — _ — The EIS ?.epcr; has çresented res it cf cdel c :: c i forts for the Charles River DO resources which are si .lar :c re : of a lIke effort by the DWPC 3asln Plan; however it uses si .car:— ly dIffering factors. In the EIS eport, these factors are selected on the side of an unfavorable oxygen resources representatIon In the river. The calibration effort also includes a number of assumed val- ues which have a significant impact on results. Several alternative projected future condItIons, as well as scne crianges in factors, have been simulated. The basis for their selectIon is not ex laIned. A scoring system was used to measure the alternatives which appears to be rather arbitrary. We recommend that: •a thorough evaluation be made of each factor and each assumed value, • the range of confidence for each factor be developed on the basis of present data, •a sensItIvIty analysis be conducted to Identify those values havIng a sIgnifIcant impact on decIsions and requiring a narrowIng of their confidence range, and •Investlgatlons, includIng, if necessary, field mea- surements, be conducted to achieve the necessary narrowing of that confldence range. ------- f UN TE STATES ENVIRONMENTAL F OTECT;O: REGI3N I .tc F FE EP L PUILD:NG. B0 TON. 3 July 22, 1977 :s. Libb” Blank Director of Environmental Planning 4etro olitan District Commission 20 Scmsrset Street Boston, !• 02108 Dear Ms. Blank: Thank you for your letter and comments of July 18, 1977 with regard to the Charles River water quality ode!in . We will respond in detail to each question raised by I etcalf and Eddy by August 10, 1977. Please understand, ho :ever, that the computer odeling of the Charles River which we are performing is based u on our understanding of the Charles River and oui deteri inations of proper mathematical representations of river processes affecting water cuality. Thus, our final model simulations zi11 incorporate any necessary corrections to the model input revealed by ietcalf and Eddy after considering each of their comments. I have attached for your information a copy of the letter which we sent to Dover, Framincham, fledfield, N tick, eed- ham, Sherborn and Te1les1ey reciuestinc their artic ation in an expanded site selection committee. We would welcome your participation with us and the communities in the site selection process. e will notify you as soon as we re- ceive responses from the communities and set the first meetinc7 date. Sincerely yours, £ Y OLLL ! ary E. Shaughnessy Environmental Impact Analyst ------- f “ ‘ UNITD STATES ENVIRCNMENTAL PROTECTION AGENCY REGION I J F. KENNEDY FEDERAL BUILDING, BOSTON YASSA iUSET1S 02203 ,\utjunl 5, 1977 . Libby Blank !)Ir’ ctOr of Environi enta1 Planning c 1 O1It )n 1 )jstrlCt Cc ission ..‘ I ,oia.rsCt 5tre t I);t’)rt, u21 3 I) ’ t M . clank: This is in response to your letter of July 18, 1977 to t1S. ; . i .y Shaugnnessy of t)’! vLruILIIental and conornic I act OLLic’ concerniny tne dater ‘quality modelinc of the Charles uver and effects of tne ?ro D;:fl — i ries aste ater treatment plant. I itin; te you directly because I am the person doing the odc1ing. 44’ C. ’Lt arc- used by the Cnvironn ntal ani Ecorao ic Irn?act Office and their consultants in er for i j : .. •‘1.:: .: t: i ssessn ent of the pro7osed tr . atrt nt lt rri tives for the system. First, I will revie4 ou: in tne C. arle ver iaodelin’j and Ln n res c. to the juetions by etcalf and Eddy, Inc. In June an Se te ber, 1973, the assac u etts Division of beater ?o1l tion C itrol, ( D C), conducted water u li j surveys of the Charles River etween ilfori ai isssachus’ tt ;. ata fro.i these surveys was used to set u the streai ode1 of the ;.: •; c Lor simulation of water qual it ; ., i..; )urin, the .June a’ J c ,te: ber sur’ evs. The stream model is t iat : escrihe in Syst .i5 \ n 1ysis for iater Po11 ticn Control 5 . uirk, Lawler ani T3tus y, June 19 _Il. iir. John Erdr ann, formerly of the D. PC perfor.nei the model set u i;1 i! ’Jl tion of the June and Septe r.5er survey conditions, a process tcr. ed rnodel cal br . tion. At tne request of our n iironr.ental an) Economic I. pact Office an with the cooLeration of ; ir. Alan Cooperrar. of the ND. 1 ?C, I obtained tne Charles Riv r c,]’ l . s calibrated by 4r. Erdmann a nd developed a simulation of the Char1e Riv2r unoer 7—day, lu—year recurring low f 104 c’)nditionS for COI 9aLiS ).1 with dater quality standards. Tnis si 1 ulation was done usinj the ?A v. rs•ion of the stream model progra’n which is analacous to the i D.cPC stream model program. At the pres- nt time, the rr.o elirkj is being done with the steady—state option of the model and we are si,ru1atir ------- I tcrr t Ve trectT flt plant locatior.z ar.. ± r criL C ) r i1ty COr d1tlC .Z. T: : —s •: o :::- is bein J u30d bccE.use tno port cn Of tne r oue1 ?o-:r: .u;- L• - o urn l Ls )lV ’J ox en v riat:on due to noio ynt iCSiS was found to be incorrect. Tl is_•no _i ; snoulc3 be co.n ’lcted by the end of tne month and the fine! results will be reporteJ in aetaii—k sU concerne3 -)art1e . NOW, in responding to th questions by •1etcalf and Eddy, Inc., I will comment on each as presented by them. QuestiOn 1: Projected Upstream water Qualit Conditions Water quality conditions upstrea: of the .outh Natick Dam, .; ;i ulated, are those resulting from stream conditions as we preJict thei to be and ei ted wtC4Jt L loadings horn th various treatment plants discharging to the river in the year 2033. irie waatewater loadings for •lilford, the proposed Charles River Pollution District, • rentham State School, Norfolk—. elpole £• CI and !•:edfield—’4illis are.thg estimated to be disc ar’jed with the respective treat!! e’ t • l nt configurations producing their hignest quality effluent achievable. Loa incjs ani flo. were determine.5 by t ie Environment3l . ; essment Council, Inc. and Greeley and Hansen, Inc. after revie : ng information on tne facilities currently being planned for the various communities. Results of modeling under tnese cond!ticns indicat- that it will be v rv ikeav that certain stream reaches u3stream of the South Natick Dam will not meet water uality standards for dissolved oxygen under year 2CO 3 conditions. :nere— fore, it is erroneous to assu: e th water quality standards for dissolve 1 o y; n will be met under critical low flow conditions in ll upper river — reaches. Question 2: Prcjected astew ter Flows The anticipated edfield— illis facility was initially simulated witn a wasteJat2r flow rate of 1.5 million gallons per ciy (ngd) her e.ise that is the desi;n flo’ capacity of t e exjstin.3 Me’5fi i treat;nent plant. T e projecte t’ t r flow for b tn co,ni .mities cotbir: d in the year 20C3 is estimated to be 3.0 ngd. T.- e modal has beei c. nrjed to reflect effects of the entire 3.0 mgd. Question 3: Stream Rer tion In reviewing the calibrated model by Mr. Erdmann and ------- tne sl d : i’: re:c.:t.2: i t 1976 C .::1 River .ater ; t zn wa seen that the rc cr tion coc i:i r. as co ted theC Connor—Dcb is isotro i T -h - -’.c’ rel t:or.z :. Tnis relotionship is !nost valid for use with streams having ocptns of 7. 3 to 12. feet ‘ icit1es of 0.5 to 2.5 feet r second. Under conditoiis of 7—n. ., 1( —year recurring low flow the water depths aior J t e entire river are co : 1 puted by the model to be between 1.0 and 10.5 feet 4ith velocities of C.C5 to 0.55 feet per secoi d. Thcrcfore, the Tsivoglou—:9a1 ner.;J Diasipation relot on hip was used to compute the reaerat.ion coefficient. The reIationsn p is valid for str .i f.low and asso iated deDtns and velocities in t e range of 1.0 to cqbic f€at per s2cond, which icludes th’ range of flows along the entire Charles River durin j lo flow conditions. The Tsivoglou—Neal relationship includes the change in water surface elevation along the longit dina1 strea. profile, the ti e of flow within the stream and a coefficient terrn related to flow rate. Receration rates within each river reacn ere co— it 3 using the proper coefficient for stream flow, the ciange in water surface elevaticn as taken fro Corps n i,eers profiles of the river at low fic;; and tne time of f1o as co:nputed by the ode1. These and o: r ter s for river reaches 17 tnrough 22 are sndwn n tne attached table. Regardin’j ietca1f and Eddy’s co :ent on the “choice” of reaeration coefficient values and ass tions of sedirr ent oxygen de .and rates; the reac-ration rates are co itout J L âCh by reach as oravio sly exDlair.ed h1J sedi 1 nent oxygen de and rates were assu ei cOi rLn available data. 3 j. ent de ar.d is ass ed to e present in the river within reacnes upstres o the da s and where stream bo to ateria1 analysis indicates or;ani: sediment is rese it. As sho n in ti C attaciieo table, seoi 1 nent oxygen ce ano is ioc t behind the Soutfl tick and Cocnrane Dams and in loAer velocity reaches. In the table, note that the receration coefficients for reaches 20, 21 and 22 as input in the sinulations reviewed by £•ietcalf and Eddy were in error as computed and ha ie since been corrected. Question 4: Dam Reaeration The value of the model input variable for dam ------- rcaer3t Q .1) .t the Sc jt iat Ck D w origlfl3llj iflto tne model as Tn’ val’ e shauld n :e n U.{J088. :odel in ut h s been correct t :iic value. The discrepancy CC’)’J C f th larL3 difference in dam rearation between tne Souti Natick and Ca hran : )..ns. Question 5: Deoxy enatiofl Coefficient or Nitrogenous 1 qcn Denand The modeling described in the Charles Rivet t r Qu.ulity 1anage ent Plan is sii lifi. I rocedurc which considers car onaceou hiocnc ical oxygen den njtro nous oxven cemand a . one proc’ -; uccurrin; r. one rate and tnercf.ore both rate constants must be tne sami . T: u3 stream nodcl colisilers thc’;’ •)tOCC CS separatc y as they actually occur in nature. The deoxyjenation coefficient for nitrification of at 2G°C is a hign value which results in the a inonia concentration simulation comparing sell with the Septe’ bet 1973 a rnonia concentrations as measur. d in the river. Also, th higi v hie is a logical ascui ption consid?rinj t at when the four major treatment plants on t ie river are operating as advanced biological syst .ns the river should continue to have a well est.ablisned population of nitrifyin j or is S. Because tha jdel is well calibrated for an on a a d high po;ul3tic .s of nitrifyir. j organi3. S can be expected in t’.e rivur in the future, the assi ed rate of O.G is valid. In summary, the modeling is contiuing as explained he eir.. When final results are available, tney will be sent to all involved parties for review. I hope this explains my position with regard to the r 1 odeli g and should you have ny further • uestions please do not hesitate to contact me. Sincerely, Allen J. Ikalainen Acting Chief Systems Analysis Branch cc: i. Shaughnessy , EPA A. Coopern n , l ?c ,L. Gitto, EPA “j. Vittan )s, Metcalf and Eddy, Inc. I. Polese, MD ;PC R. Chapin, EAC ------- c ; s:.:S RIVF.R ‘.:zo r. vsTE;S \::,\I.v I i,v;c i — nzcio:; I RIVER RflJ CIIITS 17 TIIRU 22 Sediment Oxygen Demand ( ranis /irt /dav Ve1ocity / Ft/Sec — .07 .08 • 19 .12 .45 .32 Low F low Depth Ft. 4.8 5.1 2.5 7.5 2.8 7.0 Time of ’ Flow Hours 10.6 53.6 12.5 56.2 5.2 14.9 Change in Elan of Water Surface Ft. 0.5 2.0 0.25 1.45 1.0 2.0 Reacra tionE’ Rate Day 0.06 0.05 0.03 0.04 0 .27 0 . 19 a/ Reach — Reach Reach Reach Re a c h Re a cit 17,— flogastow Brook to Medfielcl hospital — 0.5 miles 18 Medfie1d Hospital to South Natick Dam — 6.7 miles 19 — South Natick Darn to Waban Brook — 1.7 miles 20 — Waban Brook to Cochrane Dam - 4.8 miles 21 — Cochranc Dam to Che5tnut Street, Nccdham — 1.6 miles 22 - Chestnut Lreet, Needham to Long Ditch Inlet — 3.2 miles b/ Proposed MDC plant located at head of Reach 18 H each 17 3.46 18 3.46 19 0 20 1.38 21 0 22 1.38 C, Coefficient for Tsivoglou relationship 0.060 @ 25.5°C ------- :i :: a:-k irec:or of vironne.r tal ? .anning : :e:rcpcli:an istrict Ccr.zission So erse: Street .— —— — . ., ...t J . . .VLi arNs. Plank: :— re cnse to the recuest by NDC we have ccnduc:e a brief ‘ E:s Consuitantts Charles iver odeli g effcr :s assccia;ed with the location of the 1iddIe Charles azellite :as:e ater Trea: ent Plan:. S ec1fically, we have reviewed the f:Li :in dccuren:s: a. . eri:rar.dw :or. r.?. :hap of the virori- en:al essnent c incil, Inc. (IS Ccns l:ant) :c :ary Sha gnnessy cf EPA, descri : six eJn cases and reccn e in that the scharge of the subject plan: be Thcated as far u :rean of the cuth azic : Daz as ;cssib.e. Cc :uter ou::u; from the odelir.g of Case 3A described in the P15 Consultant : er crandum. r ana.ysis has focused on the assumptions and pa’a eters used in :ne c:n:u:er mcdelir. effort. : :h s review, we have assuned :he :ara e;ers used i . Case 3 are the same as those used in the cther fi :e :ases described in the E S Ccnsultant :• eno’ana that f.r- : e :as:s fcr tneir reccr. endation. ! cwever, in :-e 0 :.c:s : e E3 Cc s :a t e cra o ’ —a’ es ::s as— s n:::cn : stionabie s:ecifically because of he peculiar :ic:s for Cases and 3 between river r.iles 35.7 and Conp :er runs for other than Case 3A were not supplied for review. o initial review, we raise aues:icns in the fcllowin areas: I. Prciected a:er a.i:: cnditicns . In a1. six of tne cases considered :y tne 1 Ctnsuitant, sent_s viclat ons of Class P :ater cuali:y standards are nc ec:ei f:r severa cf the sez en:s u:szrean cf the Scu:h ::a:i: the rea:hes i . dia;ely upszrean cf ; e da :here a C of :eno is :rc ec:ed as a result of :reat effluent beds, i.e., excluding the i iddbe Chan.es is ioocr:ant to :now the extent to which E5 Ccnsu:tan: t s reccr endaticns relative to the i de — __ . __ . .. __ . — - .._.. -...:—.—: :—.- ------- ; a:er c ua.i:y. In ncdeling the River under the :.ear 2000 conditions, shoud it not be expected that ut— stream discharges w ll be treated to the point wnere wate:’ ua1ity standards wIll be met? 2. ? z’o ected Wastewater F].cws . In the EIS Consultant’s modeling, ;ne Charles River i assumed to receive 1.5 mlll!on gallons Der day (:n d) of wastewater from a cc b ec ecf:el — 1lisfac:1.:y in tne year 2C00 : cwever, the DW?C ifl its basin planning has repcr:ed flow projections of 1.0 mgd for each commun Ity in 19E . ProjectIons in the study also show larger values for the year 2000. In the EIS Consultant’s mcdeling work, were changes made n the sewerage servIce con- cepts In that location to warrant the reduced effluent d s charges? 3. Stream Reacration . The values of the coefficient cf reaeration ( ‘. 2 ) used ifl the model are consideraoly less than re crted in the 1976 Water uality ?lanagemen; P:.an c.f the Massachusetts Division of Water Po.lluticn Control (DW?C). The attached table comoares these values for the eleven reaches on the Charles RIver of interest :0 the ±ddle Charles plant analysis. ifl the nine reaches not considered to be “rapids”, the values cf used in the model are L1 to 96 percent less than those re- ported by DWPC. Reach 21, immediately below tne Cochrane Da . •:alue of • 2 as increased to reflect the higher reaeration rate expected in this so—called “rapids” section. The value, however, is only acout one—half that used by the DW?C. Eowever, In the other “rapids” section (Reach 19, just below the Scuth a:ick Dam), a K 2 value was used that is amcng the lowest as- sumed by the EIS Ccnsulzant anywhere. This choice of K is inconsistent with the assumptions on benthic oxygen demand made in the EIS Consu.tant’s :emcrandum. On the other hand, ifl the lcng flat reach between the Sou:n Natick and Cochrane dams (Reach 20), a : value was used almost ecual to that used at the Cc hrane Dam “rapids”. What is the basis fcr significantly cnanging the DW?C parameters? Da- eae at o . The DW?C used f 4 eld sam 1ing data to conclude that :ne South Natlck and Cochrane d s have equal values of the reaeraticn deficit ratio. he :: Consultant used a similar parameter, the reaera:icn f nc:ion. Thus, one would expect the two dams to be ------- cnarac:eri:ed by ecual values of P’d ( ). Ecwever, the EIS Consultant modeling work is based cn in u: parameters that give the South atick Dam a reaera i:n ca ability nearly nine times that cf the Cochrane :am. What is the basis for this significant change? • Deox:: enaticn Coefficjent for encus Ox1zer’. Demand . The model ou: uts :roducedby tne ES Ccnsuj.tant are based on a value cf 0.67 for the nitrogenous deoxyger.ation coefficient n all reaches. This is markedly hIgher than the 0.2 value used by DW?C. Again, the basis for this change needs to be det errnlned. A: this time, we have identifIed five areas •.:here the sé:.ec:icr. o: parameters are expected to impact s:gnl ant .y :ne con:_u— sicns cf the EIS Consultant’s Memorar.duzn. It is apparent that an item by item review of the mcdeiing da:a, and cssibly the Program formulatIon is needed as tne next step. cr the significant model parameters, the range cf confidence cu be identified and their sensitivity should be de:ermine . acme :arame:ers can be fiei.d checked easily. An exam;.e cf s cn is the reaeraticn capabIlity at the critical dams. Due to the recent attention given to possIble discharge lcca:icns, 1: is recormended that MDC review with DWPC the following prc::se ne:•:: ste:s. 1. Detailed review of all input parameters. 2. s:a:lishment of a cssIble range fcr each siznifi— cant parameter. 3. eview of the Program formulation. i. Senslti7ity analysIs of parameter ranges wIth res:ec: to a decisIon for the desired locaticn and required effluent cuality for a Middle Charles lant. A; a minimwn, modeling runs should be made wIth the above—noted changes, to determine the Impact on tne S Consultant’s ccnc -. sion relative to the discharge location. 7 j t” veu s, ‘I —i’ .’s b.:. : zs ------- C0MI AI I :;oi i 0i•’ Ui .:AI•:UA’i’i oil (Ic 2 ) VAI. IE IJ:;l•:I) ;ii r,a i. Urook 119 . 9 ‘10 . 3 ‘I [ . I 39 . 1 3” . 6 33.0 29.1 1 2I 1 . 2 21.2 20. 2 16 0.056 0311 Ilecel ve 1 I :r.harge Iiouii Medf Ie]d—MllJ I:i I1ui ,u:; Low Urook Mud 1 I e id Ito Lp1 La 1 HaL. tc k Daiii t’Jn L tii Ui’oolc ( ucIirane Darn Clic : Liiii L SILeC I; l.nii ç Ditch f i ii eL 1•lu 1.1 iu i fli’ook :;; w I I .1. I r()c)k Ii •;iilow fli’nc.’Ic I I Ic 11 i :i i i)ani Il:;ci l by 111 Cons i I LniiI. roi’ iro.Iec Led Yeat 2000 cond It; Ionn J:;uI by I1Wl in CIi ir Ieu l I vc %dat.ur Quit] I ty Man igemerit. Plan For p ojec Lcd Yeai 1 9t1 i: 01 v i i I I cii i :; H lver :‘ .LZL I I on nil 1 e No Ileach . Vjlue:; oF -- Fl 9(1) 1(2 (h H;e e) — 2) lb ie ; nwpc ( 17 0.1115 0.35 0.056 0.33 19 0.033 0.82 20 0.5117 0.25 21 0.569 1.1 22 0.089 0.29 23 0.033 0.22 2 I 0.011 0.30 2’i 0.022 0.27 26 0.13 11 0.2 11 “Rapids” (hole low E [ 1 K 2 ) ( hole high ETS K 2 ) “flapid:i Diversion to Neponsel I(Ivt i ------- • _•__ :. ‘. •__ ENVIRO’ M NTAL PLA .NING OFFICE rt 10. Ms. Mary Shaughnessy Environmental Section Enviroriniental Protection Agency J.F.K. Federal Building Boston, Mass. July 18, 1977 .L c i 11? 1? Re: E NA EIS - Charles River Water Quality TEL.. 7z7-eae .Dear Ms. Shaughnessy: At quality plant. our request, Metcalf Eddy, Inc. has reviewed the Charles River water modeling data relative to the proposed Mid-Charles wastewater treati ent The following are comments provided to us by Metcalf and Eddy. “Specifically, we have reviewed the following documents: a. A memorandiun from Mr. R.W. Chapin of the Enviroriniental Assess”ent Council, Inc. (EIS Consultant) to Mary Shaughnessy of EPA, describing six modeling cases and recommending that the discharge of the subject plant be located as far upstream of the South Natick Dan as possible. b. Computer output from the modeling of Case 3A described in the EIS Consultant Memorandum. Our analysis has focused on the assumption and parameters used in the computer modeling effort. In this review, we have assumed that the parameters used in Case 3A are the same as those used in the other five cases described in the EIS Consultant Memorandum that form the basis for their reco endation. However, inspection of the DO plots in the EIS Consultant Memorandum makes this assumption questionable specifically because of the peculiar plot for Cases 1 and 3 between river miles 39.7 and 40.5. Computer runs for other than Case 5 were not supplied for review. Based on our initial review, vC raise questions in the following areas: 1. Projected stream Water Qua1i r Conditions . In all six of the cases considered by the EIS Consultant, serious violations of Class B water quality standards are projected for several of the segments upstream of the South Xat±ck Ds. in:1uding the rea:hes ir .edia e1v trea - ‘f t-.e /_• ....,/he C,’ I , a . .. aC/’!’ ‘ 2i2 i ’me,. .°/ S4 ee t zd .n O&1O8 ------- dim here a DJ of :ero is projected as a result of pstr a. cffluont loads, i.e., excluding the idJle Charles plant. It is i iportant to ow the extent to which the E1S Consultant’s reconr endations relative to the Middle Charles plant are influenced by this modeled uvstre3zn water quality. In modeling the Rive under the year 2000 conditions, should it not be expected that upstream discharges will be treated to the point where water quality standards will be met? 2. Projected Wastewater Flows . In the EIS Consultant’s modeling, the Charles River is assumed to receive 1.5 million gallons per day (mgd) of wastewater from a combined Medfield-Millis facility in the year 2000. However, the DIcPC in its basin planning has reported flow projections of 1.0 mgd for each community in 1985. Projections in the E’Mk study also show larger values for the year 2000. In the EIS Consultant’s modeling work, were changes made in the sewerage service concepts in that location to warrant the reduced effluent discharges? 3. Stream Reaeration . The values of the coefficient of reaeration (K 2 ) used in the model are considerably less than reported in the 1976 Water Quality Management Plan of the Massachusetts Division of Water Pollution Control (DWPC). The attached table compares these values for the eleven reache.s on the Charles River of interest to the Middle Charles plant analysis. In the nine reaches not considered to be “rapids”, the values of K, used in the model are 44 to 96 percent less than those reported y DWPC. In Reach 21, iii nediate1y below the Cochrane Dam, the value of K, was increased to reflect the higher reaeration rate ex-pected in this so-called “rapids” section. Tne value, however, is only about one-half that used by the DWPC. Ho ever, in the other “rapids” section (Reach 19, just below the South Natick Dam), a K, value was used that is among the lowest assumed by the EIS Consultant anywhere. This choice of K 2 is inconsistent with the assumptions on benthic oxygen demand made in the EIS Consultant’s Memorandum. On the other hand, in the long flat reach bet een the South Natick and Cochrane danis (Reach 20), a K, value was used almost equal to that used at the Cochrane Dam “rapids . What is the basis for significantly changing the DWPC parameters? 4. Dam Reaeration . The DWPC used field sampling data to conclude that the South Natick and Cochrane dams have equal values of the reaeration deficit ratio. The EIS Consultant used a similar parameter, the reaeration function. Thus, one would expect the two dams .to be characterized by equal values of Fd (Q). However, the EIS Consultant modeling work is based on input parameters that give the South Natici: Dam a reaeration capability nearly nine times that of the C zhra.ie Dam. What is the basis for this significant change? ------- 5. De xv enation Coefficient for Nitrogenous Oxvcen Demand . Th model outputs produced by the EIS Consultant are based on a value of 0.67 for the nitrogenous deoxygenation coefficient in all reaches. This is markedly higher than the 0.2 value used by DWPC. Again, the basis for this change needs to be determined.” We have discussed the modeling data with Messrs. Cooprnari and Polese of the Division of Water Pollution Control and they concur with Metcalf and Eddy’s comments. At this time the MDC and the DWPC request that you rerun the model with the changes indicated by Metcalf Eddy. If you have any questions regarding these changes, please contact Jekabs Vittands of Metcalf Eddy at 523-1900 ext. 456. When these model reruns have been made, the MDC and DWPC staff would appreciate the opportunity to discuss the outputs with you and determine whether additional analyses are required. Yours truly, Libby Blank Director of Environnental Plann.ng LB/co r:: A.Coopman, Dl PC J . Vittands, M E V A. Ekalainen, EPA ------- ‘ -S. - • — - - - . 1 ) - - .. - / TO: Mary Shnchness’: - — E.P.A., Project Officer j..i (P A ( CC: I. Klein; C. Koch; 0. Suler; 0. Bartlett FR0 : R. ! ’. Chapin - . DATE: May 18, 1977 RET: Location oE Mid—Charles River satellite ;lant dischar2e The ECA study recorends dischartinc the effluent frcn the nid—Charles River satellite olant a: the Cochrane dan. Our use of the Char les River water çLall:v model has beer. aiTed at dete inin: if this is the “best” location for the discharse. ?re’-ious renoranda. 15 .t.:ril and 25 April, srrarize n:delflnz activities. This nenorand e clua:es the effects of the t-aricus cases uton the ox-.-cen balar.ce in the Ch:rles RIver. (Results are evaluated relative to Class 3 dissolved o:c en standards. See nerorancun cf 10 May 1977.) The E 2:s. re crt recorzended a dischar e of 31 rad containir.: 5 t-z’l SOD: and 1 r.zfl a: the Ccchrar.e d an. Early nodellint runs indicated :: : to violate - azer :tali:v st:ndards for dissolved oxvzan and. :nerefcre, the discharge effects of an “advanced” evel of treatTent, to a 502; of 5 ngtl and .n 0 : 0 were Lnvest:tatec. :r. adn:Ion, two a tcrattve discharge locations were rodelled: at the S. :;atick dan: anc 6.7 nies to— strean of : e S. ::a:ick dan a: the he=± of —.:dellirs roach IS ( areafter called Reach 13). Figures 1 and 2 :resent. res:ec:iva:v, :lc:s s -ari:izz these treatrent levels and dischar e Thcazicns and their affects u:or dis- solved oxygen levels ir. the Charles. The E’2 A reconnended discharge resulted in a larte 0.0. sag below the Cochrane fan, which violates the Class 5 standard of never less than 5 ngIl a: an:.-ti e. Discharge at the S. Nat:ck dar resulted in two sa;s below the 5 rz1 level, howr:er, thace ware no: as severe as the Cocnrane dan discharge sag. Conversely, d:schar e at each IS caused no ‘iclaticn of the 5 e /l standard below the S. at:ck fan. Dissolved o::v en levCs above the far are well below this class 3 lint, althou:h dischar2e at Reach :s ger.erallv in;rcves ccnditions over those predicted to exist v:th- out a C discharge. When dischsr;ing the ad-.anced efflucr.t at the Cochrane darn a sag below the Class 3 5 n/l lint occurs. This level of treatnent does not violate standard wher. dischar;ef at the S. Sotick dan, hcwe”er. the 16 hour class S standard is violated by a S. ‘azick dr disoharce. Reach IS dischzrce as: does not violate the 5 z:!l standzr below the S. Satick fan, while d:sscved oxygen levels above the dan fall below that level. However, a discharge here i—.prcves conditions in this reach ever the discharge conoition. ;Cdi— tionally the 16 hour stancord toes ntt aopear to be v:clatef b-- the aaoh .S dis:harcc. ------- Paze —2- .ay iS, 1977 ThIs ar.aiysis indicates the greatest benefit to the oxygen ba1 n e cf the river occurs when the .Id—Cha:ies satellIte plant d±sh rçes a.- a- vanced effluent placed above the S. Natick da at river iie 7.8. The political reality of placing such a discharge at that location is beyond the scope of this discussion. Nevertheless, it is the position of EAC that any discharge from a id—Charies satellite iant be placed as far upstrean of the S. Natick da as possible. Such a discharge appears to provide the osc benefit to the cxygen balance of the Charles River. ------- cha :es F. vc: :e-::e—z .—...s Modellir.g waste ¶aste C arac:eri!: :s P1a t Reach - F1c ( ) 30D ( /1) ( j ) M.ilford CHO3 6 5 1.1 CRPCD CH].3 8.4 5 1.0 reithe State spol 3.1 5 1 • Schocl Norfolk 31po1e SPO5 0.4 5 1 MCI Medfie1d— iiiis CHiC 1.5 9 2 ENVISO .E’..TA. r. .Er 7 C L: L ------- - - Case escr:i . ec: - -.er e ar. 1ca i :s at the C r3 c dan. oxvcen sacs t3 1. :/l heh: :-.e s :< ].i -. (::.-e: - .le 0.) violating Cass 2 s:ardads (see at:athed Pic re 1) 3 accn er.de disc arce and lcadjn s s: the S. atick ear. : : :a1 sac to .a rc,’l a elc:s enin ::- C:cn:ar.e den (at ::ver -.ie E.4 while a seccnd sac : 4.1 nc /i evelo:s e .ind the £.i•: ‘:ll a-. This icla :es Ca53 2 D.O. cr.teria (see F:ci.re 1) 4 Advanced disth2r:e and icadi at the Ccch:ane den. .. sag at 4.1 g/l be:-.ind s.i:.: :::1J. an which v::lates Cass 3 standards. 4E Acvanced scharce e.c 1cad.n s at che 3. at.ck dan. 5 a. . d .scnar:e ca .ises sa: t 5.L :- .‘ “:11 a-. i:h d:es nc: Class 3 1c er :.:e :a. A : 1e cf ns icr 3 — c r er : :s s:ndar :s v:cla:ed (see ale 1 an F1c re 2). Advan:ed a:a: a - lcadinzs : a.- ci S. a ::: s ..— a: r:er cile 47.5 (che f : e S. ::: z — :eac.-). T: is :;rcves d s— solved c:.: :ez _- :ns a:- :v : these c:: :: -; : -:.: :ne dis:ha::e : : . . eveis d nc: ::se e.cve : e 5 :-: l .er 1_—:: for Class 3 wa:e: . A sac : 5.7 nc/ eveLc :s he. -. nd :::1 A cycle cf r a i:r a 24 hc z• :::± :n !ca:es tne :mss 2 1 h::r standard is ;:::ez.y nc: :ic1 :e see a ie 1 ani F: re 2) d::-arce and 1: i nrs .cs:rean cf S. a::c den at river n .1e his al_c::-— ves .O. levels :na S. Na:ic d in. -:: as ch as ase 4 . A sag :o 5.4 c/1 deveic;s behir.i d , hcwever a : r cycle has r.c: heen n icr this case. ‘Unless s:.±.e:, all : ns at S a.n. ENVON?. 5’ TAL AS! S5.’E T C3U .IL 1C ------- Charles River enthic Demand Reach ______ Z Bottom Coverage Co=e :s 19 — S. Natick Darn to Waban Brook 0 0 rapids 20 — Waban Brook to Cochrane Dam 1.38 25 21 — Cochrane Dam to Chestnut St. Needharn 0 0 rapids 22 — Chestnut St. to Long Ditch Inlet 1.38 75 23 — Long Ditch Inlet to Mother Brook 1.38 75 24 — Mother Brook to Long Ditch Outlet 1.38 75 25 — Long Ditch Outlet to S. Meadow Brook 1.38 75 26 — S. Meadow Brook to Sick Mill Dam 1.38 90 ENvIqop4M r rAL A SE S E T L CIL C ------- S. 2 :: —c. . e - Time Low D.O., /i _ . 3am 5.7 5ai 5.1 9am 5.5 12 pm 7.7 6pm 9.9 12 am 6.7 Reach 13 Di!: zr;es Case 3am 6.2 5 5.6 9 a 6.0 12 8.2 12 7.2 Note: A 1 1o .C. es are dcs:: : cf Cochrar.e a: ri:er .iie the Silk : i1. ENVIRO. .T . .L .SSES5. ENT CCU C L ‘.C ------- :!1 [ TI.:1::: DISC 1hRGE L—.--- P GD.I. f.•x. JLL E OI /4GtLL.t’JH .J____ i . I .:. .1...!.. :::5 L .:J LLInIT ociththL :1 i1iTL ‘_-_ ‘_J._L • _______________ I I I F:. I--•- — :.;: ::: ; ..: : .:j::E .: :j:: .. • ::sj. TP ‘f-” - - i”L 1 444 I. ‘.. • :•• L - I L. I i L I T:T1TIT. : I . .. !: N1 I_ i i iL Ii U. C 1. Li ( I, C 3—... TT - -- I- -÷: :. :t :Ii - E: ‘I:: I I ‘Ii: 1 i - .4 .2 (I . •1• Iii T TTTT :T iT T 1 T 5::: :I:: . :. : ;:: • :5 I I • : • . . ::: :: : 1:. I I ii I: I .. I !. . . EL I_ L.-J_ .L ._i .._l — _. _L i _ - i A1T Lk.. r rr - tt .:! i;J l’ .i :: :: •ri._..i_ : Fl ‘ • I ;Ii . .l: . , •. : I !. . - : — : —• l ...l... I — — — : ::L 1H •. ...u...! :: I :..J I — (_•_ — I— I i •I.I I .. • , II I j • : j. II — l_ — • . . r .• “I • - 7 ’. . 5 — :1:1. I j I 2 . . J .1:!. I . ; I •. I .. : —;— •‘ ....i_ • L 1 •• .•.—-.- .__———— 1... ‘I’ . . I .._I—.. . 1:4. ,.—— :d :.;:I .:. I • I: ..:- ..—— 1: 1. •I :: .:::.:.:;..:1: . .j i.: : .::_ii :I : 1:.::. .1 ...!.! :1 Ii :: ill_IL 1 TI .1 -1 • • — :1 ‘lIT T ’ I_I I j . ..._._!__j.... ; I s J I I I :; ‘; —I I s: :.O :&j ::;i “—-rD .. •.. . 1 $ . .: I •__ ! —I 1.11 I I . t 5:.. I . : i : • .1.1 1 ;I .1 s::. ! i I i TL• 1 j 1 t a •I_ •1 Lf) 5 :5: . — ..., ::s. ,,H jj -iH . 1:_s f::.: .I:;.:I.::.I:: 4 i -ti- I: ::LLL : 5 ::.I : 5. Lii:: I!I . : (.) :5 - It L I. •1 • . •I .J .j :. ::::I TT,T I T T .; I: •l: . .:; ETT:• i i. I i’ E•il_iIi i .. 1 1i. .1 ...I I I .L . FI UI? [ 1 LJtfC11i RGEi . - j 1 1 J L± _L ------- r It j kTT1 r 1 H . L 1:1; :1. - . H— -- H-±HH-}- i--, c ) : - I,E — I-1 Ij +‘4 H T d t, . ‘1 I C C ( . I. I. I I ; —I— - -. I :: ! I 1 , ,.I4I! ’I’LL . 1.:. _øii # V1 I . . 4I 1j ih! I i : !.: . T + ,I #I._ lJ’a I ‘ I .... ’ i i — T [ - ___ I — L.,tU : 4L . 1 — .J ,‘ JIkLL 111 I’ . -:I.: .. I . : , ..; _ . • •. ___________ . : : i:. i ’.: !ii i . ‘!“ H —i -I H -A ± .1.. . I -. . - _.:._ . I .1 ‘‘ 1. I . - 0 1 • :! _ . : : 1: • ; ii - !. .. .11 • •• I • . 1 . • •l. • • - . : :- - I — _ :.! ..: . . . .! • 1 ;H]’H I •. I • I I- I. I IIt •ThI . iL p t Jii I xI .1 +z -:- .1:.:’. : 1 L J Q -.1 Ihj T: . I :: :: 1. -. . : 1 L t :j • .. • L - I::.., ..-:- ::;: :;:‘: . .i-: , • • — - . .—. I. — — L ii ________ I ; L - _L !_L’- :-!. .4.. - XL::. •: I I ..— $ — ! .:::I.::: f. !. _:I •1 1’ T fJ ;: r i.’ :L : .: •1.- • .. ... ‘ !:I u 1.:::.- “I. I V -l - _________ III ••_I_________ _____1. — — — — — —— I. : L::. tH. . • ‘• .i:I:1II:.I.. ;Ln • :.:r ( . •j: :c .’ •: •• ‘; f.t.:. 1 •.j. • — I •i ::‘ • ______ F’ ________ i i : .. I ..: . j I ’f •‘j 1 I . . r I ‘2 7 I 2 —I—I :i I — — I IVL1 [ ilLt 1 . — I — — I : !. :. . - . I.’. AD 1 ./, ‘...!U ISCIIb ’ E . .1 I •ji ., ._. .j:.: I .L I- ‘II I; : - I I . • ::I y I .1 :—- )•---- T--:; —:1 • ::::! D : -I I - I -IJ• :.:;i • --.! - ..: 1: I ------- APPENDIX B BIBLIOGRAPHY - WETLANDS TREAThIENT ------- BIBLIOGRAPHY 1. Gersberg, R.M., Elkins, B.V., and Goldman, C.R., The Use of Artificial Wetlands to Remove Nitrogen from Wastewater , Ecological Research Associates, Davis, California. 2. Kadlec, Robert H., Wetlands for Tertiary Treatment , University of Michigan, 1978. 3. Mudroch, A. and Capobianco, J.A., Effects of Treated Effluent on a Natural Marsh , Canada Centre for Inland Waters, Burlington, Ontario, J.W.P.C.F., September, 1979. 4. Oduin, H.T.., Ewel, K.C., Mitsch, W.J. and Ordway, J.W., Recycling Treated Sewage Through Cypress Wetlands in Florida , Center for Wetlands, Univer- sity of Florida, 1975. 5. Reed, Sherwood C and Bastian, Robert K., Aguaculture Systems for Waste- water Treatment: An Engineering Assessment , U.S. E.P.A., Washington, DC, June, 1980. 6. Spangler, Fred I., Fetter, C.W. and Sloey, William E., Phosphorus Accuiiiulation - Discharge Cycles in Marshes , American Water Resources Association, 1977. 7. Tuschall, John R., Brezonik, Patrick L., and Ewel, Katherine C., Tertiary Treatment of Wastewater Using Flow-Through Wetlands Systems , Department of Environmental Engineering Sciences and Center for Wetlands, University of Florida, Gainsville. 8. Valielu, Ivan; Vince, Susan and Teal, John M., Assimilation of Sewage by Wetlands , Woods Hole Oceanographic Institution, Woods Hole, MA. 9. Valk, A.G. van der, Baker, James L., Davis, Craig B., Beer, Craig E., Natural Freshwater Wetlands as Nitrogen and Phosphorus Traps , Iowa Agriculture and Home Economics Experiment Station, Ames, Iowa. 10. Weber, A. Scott, Tchobanaglous, George, Colt, John E., Aquatic Systems for Secondary and Advanced Treatment of Wastewater , Department of Civil Engineers, University of California, Davis. 11. Whighain, Dennis F and Bayley, Suzanne E., Nutrient Dynamics in Freshwater Wetlands , Chesapeake Bay Center for Environmental Studies and Maryland Coastal Zone Management, Department of Natural Resources. 12. Yonika, Donald and Lowry, Dennis, Feasibility Study of Wetland Disposal of Wastewater Treatment Plant Effluent , Massachusetts Division of Water Pollution Control, 1979. ------- APPENDIX C CORRESPONDENCE RE: QSA WETLANDS DISCHARGE SATELLITE PROPOSAL - MASSACHUSETTS DEQE - DIVISION OF WATER POLLUTION CONTROL AND DIVISION OF WATER SUPPLY ------- •1 ez? 1 e w zwea # a t 1 xecu4 e Cjfl e naI4f a nent of o e zI Qiia4 £ee# uj of 7i e 6 ‘ e i d ANThONY D. CORTESE. Sc. D e 7f nte e Aeee . && 02108 December 29, 1983 Walter Newman, Acting Chief Re: MDC Environmental Evaluation Section SDEIS, Siting of Environmental Protection Agency Wastewater Treatment J.F.K. Kennedy Building Facilities Boston, MA 02203 Dear Mr. Newman: In response to a request from your agency, the Division of Water Pollution Control, Permits Section has reviewed the proposal by the Quincy Shore Association for subregional wetland application satellite wastewater treatment plants. The proposal calls for the construction of three facili- ties, one each to be located in the Weymouth Fore River Basin, Neponset River Basin and the Charles River Basin. All three plants would include advanced wastewater treatment processes with discharge of their effluent to major wetland areas which are hydraulicly connected to groundwater aquifers currently being utilized by various municipalities as major sources of drinking water. Information presented to the Division indicates that during recharge periods up to 80% of the effluent discharged to the marshes would enter the groundwater regime and recharçe the subject aquifers. On October 15, 1983 the Division of Water Pollution Control pro- mulgated a set of comprehensive water pollution control regulations (Title 314 of the Code of Massachusetts Regulations) which included detailed groundwater quality standards. These standards define groundwater into these classes (1,2,and 3); Class 1 being defined as “fresh ground waters found in the saturated zone of uncon- solidated deposits or consolidated rock and bed rock and are designated as a source of potable water supply”. Since all three proposed discharges will be tributary to groundwater currently being utilized as public water supplies (Class 1), all discharges to said groundwater will be required to meet very strict discharge limits, see attachment #1. The discharge limits would basicly require that the effluent entering onto the wetland meet or exceed the Primary &nd Secondary Drinking Water ------- Walter Newman December 29, 1983 Page 2 Parameters, see attachment #2. In addition, the Division is concerned with the periodic “pass through” of materials such as oil, heavy metals, solvents, phenols and other highly toxic or contaminating materials which are not substantially removed with conventional wastewater treatment pro- cesses and which could cause severe impacts upon these aquifers. The Division is of the opinion that proper safeguards necessary to continuously meet Class I effluent limitations and to protect these va1uable public water suppites can not be provided. Therefore, the Division strongly discourages the continued review of such subregional facilities as proposed by the Quincy Shore Associates. Ver, truly yours, Thomas C. McMahon Director TCM/MP/pmm cc: Sam Mygatt, MEPA David Fierra, EPA Steven Lipman, DEQE William Gaughah, DWPC Marjorie O’Malley, EOEA Noel Baratta, MDC Robert Daylor,Quincy Shores Associates ------- ATTACHflENT 1 !82 314 CMR: DIVISION OF WATER POLLUTIO 1 COr TRDL 6.07: Application of Standards (1) Ground Water Discharge Permits . r o person shall make or permit an outlet for the discharge of sewage or industrial waste or other wastes or the effluent therefrom, into any ground water of the CciTunonwealth without first obtaining a permit from the Director of the Division of Water Pollution Control pursuant to 314 CMR 5.00. Said permit shall be issued subject to such conditions as the Director may deem necessary to insure compliance with the standards established in 314 CMR 6.06. Applications for ground- water discharge permits shall be submitted within times and on forms prescribed by the Director and shall contain such information as he may require. (2) Establishment of Discharge Limits . In regu—. lating discharges of pollutants to ground waters of the Commonwealth, the Division shall limit or prohi- bit such discharges to insure that the quality stan- dards of the receiving waters will be maintained or attained. The determination by the Division of the applicable level of treatment for an individual discharger will be made in the establishment of discharge limits in the individual ground water discharge permit. In establishing effluent limita- tions in the individual permits, the Division must consider natural background conditions, must protect existing adjacent and downgradient uses and must not interfere with the maintenance and attainznent of beneficial uses in adjacent and downgradient waters. Toward this end, the Division may provide a reaso- nable margin of safety to account for any lack of knowledge concerning the relationship between the pollutants being discharged and their impact on the quality of the ground waters. (3) For purposes of determining compliance with 314 CMR 6.06(1)aa for toxic pollutants in Class I and Class II ground waters, the Division shall use Health Advisories which have been adopted by the Department or EPA. Generally, the level of a toxic pollutant which may result in one additional incident of cancer in 100,000 given a lifetime expo- sure (iO Excess Lifetit e Cancer Risk) will be used in determining compliance with that section of the regulatiori . — 17 — ------- Attachment # 2 .11 (; 314 CMR: DIVISION OF WATER POLLUTION CONTROL Parameter Limit 1. Coliforni Shall not be Bacteria discharged in amounts sufficient to render ground waters detrimental to public health, safety or welfare) or impair the ground water for use as a source of potable water. 2. Arsenic Shall not exceed 0.05 mg/i 3. Barium Shall not exceed 1.0 mg/i 4. Cadmium Shall not exceed 0.01 mg/i 5. Chromium Shall not exceed 0.05 mg/I 6. Fluoride Shall not exceed 2.4 mg/i 7. Lead Shall not exceed 0.05 mg/i — 17 — ------- — - f 314 CMR: DIVISION OF WATER POLLUTION CO 1TROL 8. Mercury Shall not exceed 0.002 mg/i 9. Total Trihalomethanes Shall not exceed 0.1 mg/i 10. Selenium Shall not exceed 0.01. mg/i 11. Silver Shall not exceed 0.05 mg/i 12. Endrin (1,2,3,4,10, Shall not exceed 10-hexachloro—1,7-epoxy-1, 0.0002 mg/i 4,4a,5,6,7,8,9a—octahydro— 1 ,4—endo,endo—5,8—dimethano naphthalene) 13. Lindane (1,2,3,4,5, Shall not exceed 6-hexachlorocyclohexane, 0.004 mg/i gamma isomer) 14. Methoxychlor (1,1,1— Shall not exceed Trichloro—2, 2-bis 0.1 mg/i (p—methoxyphenyl) ethane) 15. Toxaphene (C 1 OH1OC18, Shall not exceed Technical Chlorinated 0.005 mg/i Camphene, 67—69 percent chlorine) 16. Chiarophenoxys: 2,4-D,(2,4—Oichloro— Shall not exceed phenoxyacetic acid) 0.1 mg/i 2,4,5-TP Silvex (2,4, Shall not exceed 5-Trichlorophenoxy- 0.01 mg/i propionic acid) 17. Radioactivity Shall not exceed the maximum radionuclide con— taminant levels as stated in the uationai Interim Pr r ary Drinking Water Standards. - - ------- 314 CMR: DIVISION OF WATER POLLUTION COt TROL 18. Toxic pollutants Shall not exceed (other than those “Health Advisories” listed above) which have been adopted by the Department and/or EPA. A toxic pol- lutant for which there is no avail- able 11 Heaith Advisory” and for which there is not sufficient data available to the Department for the establishment of a Health Advisory” will be prohibited from discharge. (b) Secondary effluent limitations for Class I and Class II ground waters . In addition to the effluent limitations in 314 CMR S.lO(3)(a), the following limitations shall also apply to any discharge from a point source or outlet which enters the saturated zone of, or the ünsa— turated zone above, Class I and Class II ground waters. Parameter Limit 1. Copper Shall not exceed 1.0 mgIl 2. Foaming Agents Shall not exceed 1.0 mg/i 3. Iron Shall not exceed 0.3 mg/i 4. Manganese Shall not exceed 0.05 mg/i 5. Oil and Grease Shall not exceed 15 mg/i 6. pH Shall be in the range of 6.5 to 8.5 standard units 7. Sulfute Shall not exceed 250 r g,’i - 19 - ------- .1 . 9 314 CMR: DIVISION OF WATER POLLUTION CONTROL 8. Zinc Shall not exceed 5.0 mg/i 9. All other None in such poll utants concentrations which in the opfn— ion of the Director would. impair the ground water for use as a source of potable water or cause or -contribute to a condition in contravention of standards for other classified waters of the Com.monwealth. Cc) Additional effluent limitations for Class I and Class II ground waters . In addition to the effluent limitations listed in 314 CMR 5.10(3)(a) and (b), the following limitations shall apply to treatment works designed to treat wastewater at flows in excess of 150)000 gallons per day: Parameter Limit 1. Nitrate Nitrogen Shall not exceed (as Nitrogen) 10.0 mg/I 2. Total Nitrogen Shall not exceed (as Nitrogen) 10.0 mg/I Cd) Additional effluent limitations for Class I ground waters . In addition to the effluent limitations in 314 CNR 5.1O(3)(a)(b) and (c) the following limitations shall apply to treat- ment works discharging to Class I ground waters: Parameter Limit 1. Chlorides Shall not exceed 250 mg/i 2. Total Dissolved Shall not exceed Solids 1000 cig/l - 20 - ------- _____ Yom’mm zrn €zf (€y ecid ve O//e o/ é ?2:à cfl,flCflg / Q ( g ,c.s /ta trnent 0/ iv wonment, / ea6i ( i,e ’zee bi, ANTHONY 0. CORTESE SC. 0. . VL Wfl €j/ # te, COMMIUION R O#&e ) K U $ ee .Ji i 02/08 MEMORANDUM TO: Steve Lipman, Boston Harbor Coordinator FROM: Ilyas Bhatti, Director, Division of Water Supply DATE: December 16, 1983 SUBJECT: Metropolitan District Commission, Southern Sewerage District Wastewater Treatment Facilities Planning Project: The Citizens Plan. The Division of Water Supply COWS) has reviewed the proposed plan for subregional “satellite” wastewater treatment facilities as part of the general plan for rehabilitating the MDC wastewater treatment system. As the agency responsible for ensuring safe drinking water supplies, we are particularly concerned with the impact these treatment plants could poten- tially have on the water quality of nearby aquifers and wetlands which serve as public water supplies for many communities. Specifically, these areas are: 1. Weymouth Fore River Basin — proposed 8—10 mgd discharge into Broad Meadow, a wetlands of the Cochato River; Cochato and Farm Rivers are diverted to reservoirs for use by Braintree, Randolph, and Holbrook. - 2. Neponset River Basin — proposed discharge of 35 mgd to Fowl Meadows which supplies Canton, Westwood and Dedham. 3. Charles River Basin - proposed 50 mgd discharge into Cow Island Meadows, a wetland in an aquifer area which supplies Dedham, Needham, Wellesley, and Weston. With regard to these sites, the sponsors of the Citizens Plan claim that there are several advantages to these projects as compared to the current MDC proposal. The following comments reflect the Division’s con- cern with claims in the proposal that the development of the satellite ------- Mernor an dum December 16, 1983 Page 2 plants will increase the water quantity and improve the water quality of the water supplies in the 10 affected cornunities (Braintree, Randoplh, Holbrook, Canton, Norwood, Westwood, Dedham, Wellesley, Needham, and Weston). Although the Citizens Plan is an innovative proposal for solving the extremely complex problem of dealing with wastewater treatment in the Metropolitan Area and the associated water quality problems in Boston Harbor, its claim with regard to increasing the water quality/quantity in the aformentioned wetlands and aquifers is based on questionable assumptions. As noted in the proposal, wetlands have been studied by many agencies, including DEQE, and are known to have significant capacities to attenuate various types of pollution such as nitrates, phosphates, and heavy metals. Although this feature of wetlands is well documented, the present proposal assumes that wetlands have a limitless capacity to act as “sinks’ for con- taminants and that all discharges from the proposed wastewater treatment plants will be “polished” by the assimilative capacity of wetlands. In fact, wetlands have limited capacities to assimilate wastes; unlike treat- ment plants which accelerate the process of waste removal , wetlands recycle and absorb pollutants over a long period. It is difficult to generalize about the capability of wetlands to function as water purification systems. Ultimately, the diversity of the many wetland charateristics will determine their net efficiency to assimi- late sewage contaminants. The vegetative type, rate of flooding, and the area of a wetland will determine: the rate at which pollutants are recycled, the BOO loading tolerance, the sedimentation rate, and the level of bioche- mical degradation. The geographical location of a particular wetland will also markedly affect the seasonal capacity of wetlands to. assimilate wastes. For instance, It is quite possible that the wetlands proposed for discharge in the Citizen’s Plan would freeze during certain periods of the year which would inhibit even the mechanical, primary treatment function of plant screening and particulate sedimentation. Aside from the problems associated with determining the assimilative capacity of wetlands for pollutants, this proposal does not address other potential water quality problems. For instance, the proposal does not address the fact that very little control exists over the nature and quality of sewage. Presently, the regulatory manpower does not exist for monitoring illegal or haphazard industrial waste disposal. Many industrial contaminants cannot be detected, let alone treated, in standard wastewater treatment facilities. As a result it is very likely that discharges from the proposed “satellite” plants would ultimately result in the degradation of existing water quality in the receiving wetlands/aquifer. All things considered, water quality degraiation is likely to occur either over the ------- Memorandum December 16, 1983 Page 3 short term through problems associated with seasonal flooding/freezing of the wetland and/or the undetected discharge of a harzardous substance, or over the long-term by the gradual saturation of the assimilative capacity of the wetland. Because of these uncertainties, and the problems that may ensue, the OWS must conclude that the Citizens Plan proposal for wastewater discharge into wetlands is an unacceptable risk for potentially degrading these vital existing drinking water supplies. ------- APPENDIX D INFLOW! INF I LTRATION TRADING/BANKING PROPOSAL ------- Y e inicnccea&% c/cacAaaee 1? f q c3.ceac( c £ 1 ) 1 2az eye’ &n z:e”. nmcn(a/ 100 dZ’.cct Jfaiack dt i 02202 C3-.!TAL ZONE Frc essor Charles M. Haar 3C0 Gris ald } all arvard La School C br1dge, L4 02138 Re: Q i cv v >!DC , Schedule lte : Dec ber 2, 1983 e r ?rofess r Haa:: ! c1osed is he p e1i inary report on I/I r oval. Sincerely, L: b enc 1: cc: ?ecer L. Koif Raiph A. Child E. lichael Slo an Sce ie C. Horo tcz Jeffery Fo iey 1s. Laura Sceirberg Wjlli3 C. -o1dcn Scephen C. Karn s S:erhen P. turgay Stev ’. Li: r— ‘ ‘— - 0 fC , I- -‘ ,._.._ ._ . . 2EL . ._. V = .. —3 I. — 1:E: 7 ‘.1 £ rr i Jç’..I’ .‘.. Counsel ------- December 2. 1983 Procedural Order — Item #5. BANKING/TRADING AND GREATER THAN 2 FOR 1 PROGRAM Item #5 of the Procedural Order requires that DEQE assess the feasibi- lity of a Banking and Trading System and a greater than 2 for 1 sewer extension permit program. This document not only provides the Court with those feasibility assessments but attempts to develop a basis for an expanded discussion of the need for an integrated approach to all I/i related items contained in the Procedural Order. It is our intention to use this expanded discussion document to hopefully stimulate fresh approaches to these technicafly and politically complex issues. This document should not be viewed as a DEQE position paper but as a discussion document and comments are not only welcomed but strongly requested. In order to assess either of these programs adequately one must con- duct such an assessment in the context of DEQE and MDC’s overall efforts to deal with the entire sewerage system and its myraidof problems. Within the MDC regional sewer system there currently exists 5,400 miles of municipal sewers, 228 miles of MDC sewers, approximately 3,000 miles of privately owned house laterals, over 70,000 manholes, 10 MDC pumping stations and numerous municipal and privately owned pumping sta- tions. Large sections of the North System have combined sewer/drain faci- lities and literally thbusands of cross connections or interconnecticns exist within the sewers and drains tributary to both the North and South Systems. Also various exfiltrating sewers are underdrained with small diameter perforated pipe which discharge to adjacent watercourses. Extensive gauging or flow monitoring facilities currently do not exist within eithe the MDC or municipal sewerage systems and therefore there is very little historical data concerning the distribution of wastewater within this maze of pipes, pumping stations, diversion structures, treat- ment plants and overflow facilities. Due to the nature of the segmented ownership of these facilities, management of flows into the system is extremely difficult to control and monitor. Infiltration and inflow (I/I) within this system is a very signi- ficant flow component (estimated to be over 50% of the average monthly flow). It must be emphasized that I/I is not peculiar to the MDC system but also exists in large amounts in all sewer systems particularly older systems. Others have statea that if I/I could be significantly reduced, many of the system problems could be solved without the construction of new relief sewers, pumping stations or expanded treatment plants. There is no question that I/I reduction could aid in these efforts, particularly with reaard to localized surcharging and overflows, but it is ot a panacea to the problems of the MDC system or pollution of Boston Harbor. ------- I/I within the MDC system has been extensively investigated with millions of dollars expended to date in •this effort. Due to the length of time needed to complete the study and design phases of the I/I program, very few communities within the MDC have actually begun the physical reconstruction phase of the I/I program. Therefore, relatively little I/I removal has been achieved to date even though a great deal of effort and money has been expanded by local and federal agencies on this program. Rehabilitation projects have been completed, are under construction or soon to be initiated within seven (7) MDC municipalities and are expected to remove 30 MGD of 1/I from the sewerage systems (3.6 MGD within the South System and 26.5 MGD within the North System). Unfortunately I/I studies and rehabilitation programs are more of an art than a science and this program is receiving extensive national reex— mination by the EPA, consulting engineering firms, I/I gauging and rehabi — litation firms,, major municipal sewer authorities, and state agencies. This review is in large measure due to the demonstrated inability of coin— munities to reduce I/I rates to those originally assumed to be realistic (and often mandated). During 1979 and 1980 EPA funded a major study to examine the level of success of it Construction Grants I/I Rehabilitation Program. The results showed that of the nineteen (19) communities studied, none had attained the assumed levels of I/I reduction and many had not reduced I/I at all despite extensive reconstruction efforts. The study concluded that current I/I determination and rehabilitation techniques generally will not result in substantial system I/I flow reductions. This study further recommended nine (9) major revisions to the EPA I/I program (See attachment #1). — During the past seven years numerous I/I studies have been performed within the overall MDC system by various consulting firms. It is very dif- ficult to compare the results of the varoius studies to each other and often impossible to even correlate the results of Phase I and Phase II I/I studies within a single community conducted during consecutive years by the same consultant. The MDC has performed 2 system—wide I/I studies, (North System performed during 1978 by Camp, Dresser & McKee and the South System performed during 1979 by Fay, Spofford, and Thorndike), plus 7 system component I/I studies by 6 different firms for individual projects such as the Framingham Interceptor, Fore River Siphon, etc. Of the 43 member municipalities, 25 have already performed additional I/I studies utilizing 11 different consulting firms. All these studies were required to comply with the EPA cost-effectiveness guidelines which resulted in significant amounts of I/i not being cost-effective for removal due to ccmparatively low transporation and treatment costs for the MDC system. Therefore, projects which have progressed into the Phase II — Sewer System Evaluation Survey Phase, Design Phase or construction Phase are skewed towards removal of I/I to the point where the EPA regulations deem the I/I component of total flow to a treatment facility anon—excessive”. This approach does not emphasize significant elimination or reduction of I/I through continued and routine maintenance of a sewer system, but rather one- time repairs or replacement of sewers which may or may not have a lasting effect in reducing I/I system—wide. ------- —3— Problems in the MDC Sewer System can be classified as: 1) ACUTE — Conditions which can lead to direct public health impacts such as sewage overflows into recreational areas, shellfish areas, and public water supplies and back—ups into homes; and 2) CHRONIC — Conditions such as sewer surcharging leading to flow restrictions, reduced pollutant removal efficiencies at treatment facilities, •and overflows to watercourses in non—critical areas. DEQE believes that there is room for improvement in the treatment of both acute and chronic problems, but the appropriate remedies are not necessarily the same. Past practice : A) DEQE has utilized enforcement action (sewer bans, monitoring, two for one, holding tanks, etc.) to address ACUTE problems. It is our opinion that a degree of success has been reached but still more can be done to identify problem areas and initiate enforcement action which would utilize the existing array of possible remedies and tailor specific remedies to particular situations. B) DEQE has utilized a format of developing a Memorandum of Understanding (orginally signed on April 13, 1982) between its Division of Water Pollution Control and the MDC to prioritize major water pollution abatement projects, develop compliance schedules and allo- cate federal/state grdnts as a primary remedy for the CHRONIC problems of the MDC system. We now recognize that an effective remedy to the CHRO?UC problems must also include other elements beyond the construction grants project list. The remedy fDr the CHRONIC problems must include an organized, structured, long term approach to reducing extraneous flow of “clean wat2ru into the entire MDC system. During August and September the Division of Water Pollution Control (DWPC) developed interim maximum I/I removal rates for each MDC member corn— munityas required by the Court. Since these rates had to be developed during a very short period of time, DWPC had to assume across—the—board— removal rates (30% and 50% reduction in infiltration and inflow respec- tively were chosen) for each community based upon the flow studies available at the time. This analysis indicated that 110 £- GD and 80 MGD could possibly be removed from the South and North System respectively if 30% and 50% reduction could be obtained in each community along with a source of monies to fund this extensive work (estimated at $100 million). It was never the Department’s intent to indicate that this level of I/I reduction was easily obtainable, cost effective, or could be instituted within a short period of time. The following are some of the major problems and uncertainties which we believe stand in the way of instituting any program to deal with the Chronic problems within the South System (similar problems exist within the FJorth System): ------- -4- 1) It has been estimated that total flows in excess of 450 MGD enter various sections of the South System at any one time; 2) The theoretical maximum flow reduction within the system has been estimated at 110 MGD assuming across—the—board reduc- tions of Infiltration by 30% and Inflow by 50%; 3) The major constriction within the conveyance and treatment facilities are the High Level Sewer with a peak caPacity of 310 MGD and the Nut Island Treatment Plant with a peak capa- city of 250 MGO. Flows cannot be reduced to these levels even if the theoretical maximum I/I reduction rates were attained; 4) The estimated cost for removal of 110 MGD is $60 million, if 30% & 50% reductions could be obtained in all cornunities; 5) Current state—of—the—art hi reduction practices indicate a significantly lower I/I removal capability (15% total I/I reduction); 6) It is uncertain whether current I/I reduction techniques withstand the passage of time. Rehabilitated sewer lines may quickly revert to prior conditions and other currently non— leaking sewer segments may begin to leak as the lines detert rate with age; 7) Current information indicates that as much as 50% ofall infiltration within a sewer system originates from privately owned 3 or 4 inch house connections (pipe connecting the building to the street sewer); 8) Various I/I experts now belive that “allowable” non—cost— effective I/I rates for a community may be as high as 10,000 gallons per day/inch/mile of pipe (gpd—in—mi) instead of 6,000 gpd-in—mi currently being used by EPA and 1,500 gpd—in— mi which was originally used by EPA. if the 10,000 gpd—in—mi figure is used as a cut-off point for further I/I work, a review of the existing I/I rates for Southern System Cornunities (attachment 2) indicates that only Boston, Dedham, and Hingham would require I/I reduction. 9) Since all prior I/I studies were performed utilizing the EPA cost—effectiveness program, many if not all the prior studies will need to be revised. This may also require additional flow monitoring to supplement prior monitoring data. This monitoring work can only be performed during high groundwater (“hunting”) periods and such revision to any of the existing studies could add approximately two years to their completion times; and ------- —5— 10) We currently have• no methods of monitoring total system flows, flows from each municipality, loss of flow due to localized overflows, etc. Any attempt to develop maximum I/I rates for each municipality in order to ‘solve” all of the many problems experienced in the MDC and local sewer systems (i.e. surcharging and overflows, downstream constrictions in MDC trunk sewers, overloading of pumping stations, hydraulic overloading of the treatment plant and pollution abatement within Boston Harbor) with the existing information is likeS trying to fine—tune a piano when half the keys are missing. In order to resolve some of these uncertainties and to begin the deve- lopment of an effective system-wide approach to the chronic problems of the MDC, the Department is undertaking the following: 1) The DEQE sent two staff engineers to New Jersey during August to attend a nationl EPA—sponsored seminar titled “New Concepts in I/I Evaluation and Sewer System Rehabilitation”; 2) DEQE has formed an internal task force to devise a consistent statewide policy on I/I, specifically to address the recent development of and revision to state—of—the—art rehabilita- tion techniques as enumerated at the above discussed EPA seminar; 3) DEQE is in the process of developing a Technical Advisory Group to work with us to develop an acceptable and implemen— table I/i program for the MDC system. Our preliminary idea for membership of this group is to have one representative from the following: DEQE, MDC, BWSC, EPA, Quincy , a North System Community, a South System Community, engineering con- sultant, sewer rehabilitation company and developer/home builder. This would provide for a workable 10 member tech- nical committee. We would also be requestina that each member representing a larger grouping develop an extended committee to whom they could report in order to ensure a wide dissemination of data. 4) DEQE recently held an interagency seminar on I/I at which Gerald Conklin, a well known expert on state—of—the—art I/I rehabilitation techniques, explained the results of a study the firm Dufresne — Henry performed for the EPA; 5) DEQE has sent letters to Region 1 and Washington EPA strongly requesting that EPA hold the New Jersey seminar in Boston so that a thorough discussion could be held with all parties to the court suit. EPA recently indicated to DEQE that they could probably fund this seminar; 6) DEQE has contacted Michael Bank from the Washington South Suburban Sanitary District requesting permission for members of cur I/I Task Force to visit their facility and discuss their extensive experience in I/-I rehabilitation programs. This macting has been tentatively sheduled for December 6 and 7. ------- 7) DEQE filed legislation seeking $100 infl lion in state funding for I/I rehabilitation programs which includes a section which would allow DEQE to fund a system—wide flow gauging and monitoring system for the MDC; 8) DEQE is in the process of entering into a $39,000 contract with a well known consulting firm to review all I/I data within the MDC’s South System and to recommend an action plan with regard to I/I reduction for the MOC. 9) DEQE plans to send correspondence to many of the MDC’s member communities (letters already sent to Hingharri, Stoughton, Westwood, Needham, Randolph, Quincy, Framingham, Natick, Ashland, and Brookline) requesting their attendance at indi- vidual meetings to discuss the additional I/-i work that they will be required to perform. DEQE believes that there must be a system-wide commitment for the development and implementation of an integrated MDC sewer management program. This program must include the provision for adequately sized transmission and treatment facilities; a realistic I/I program; on—going municipal sewer maintenance, effective sewer permit program and system—wide flow monitoring. These five items will be discussed in greater detail in a later section of this document. These actions the Department has taken and plans to undertake are based on our conclusions that the first priority in developing a new and effective approach to solving the system-wide problems of the MDC is an educational process for all concerned parties. The need for this educa— tional process is a result of our review of our efforts, and those of EPA and other major metropolitan sewer systems in dealing with I/I. By recognizing past successes and failures, becoming familiar with new state— of-the-art methods for dealing with I/I, and reviewing this information and obtaining the advice of the Technical Advisory Group, we will have the opportunity for the first time to devise an effective and workable system— wide solution to the MDC’s problems. Because we haven’t yet completed that educational process, or formed of the Technical Advisory Group, which we feel is essential in deve- loping a program which has the support and endorsement of all concerned in the operation of the MDC system, we cannot now recommend a detailed approach to solving the I/I problems, or what the mix of technical, funding and administrative or enforcement mechanisms should be in such a program. However, we have developed some basic concepts about what an effective system must include and have reviewed the concepts of banking and trading and expanded 2 for 1 program as they might be part of this overall solu- tion. We offer our comments on banking/trading and 2 for 1 and our thoughts on the minimal components of an integrated MDC system management program for the consideration and use of the Technical Advisory Group, the Court and all parties as a first step in devising an effective program. ------- —7— Banking and Trading DEQE has closely reviewed the feasibility of various types of banking/trading systems, the two major catorgories being “private capital systems” and a “central bank”. A %4orkable banking/trading system must meet the following minimum criteria: 1) Access to the system must be readily available to all who want or need to participate; 2) I/I reductions for which credits are granted should be verifiable; 3) I/I reductions should be permanent and enforceable; and 4) I/I reductions should be exchangeable in a way that is meaningful in terms of system—wide conditions. An examination of the MDC I/I situation indicates that a private capital banking/trading system is unli- kely to be successful in meeting these criteria. A “private capital” system is one in which private developers wishing to obtain sewer connection permits would either directly produce reductions in I/I or purchase reductions from other private or public enti- ties who had performed work necessary to remove I/I. Credits could be “stored” in a bank or privately held under such a system. A “central bank” system is one in which reduction credits are created by the bank (an existing or new public entity or quasi—public entity) only, then sold to developers who need connection permits. A. Access to system . Perhaps the most fundamental barrier to a private capital system is that access to that system is constricted and complex. The sewerage system is made up of several layers of ownership: MDC sewers; municipal sewers; and private laterals. Obtaining necessary permission to perform work within such a system requires several steps: site selection, ownership determination, and securing necessary approvals from several sources. Municipalities may be unable or unwilling to grant access under the terms of their easements; individuals may deny access necessary to disconnect unauthorized laterals or remove sump pumps. Apportioning potential tort liability will complicate the system further. Finally, all ol? these barriers may be compounded by interjurisdictional problems. In some municipalities reductions may be difficult or impossible to achieve, causing developers to seek credits through reductions in other jurisdictions. Some municipalities may be reluctant to encourage develop- ment outside of their boundaries by allowing such work. Lack of technical expertise may be another significant barrier. In brief, access to the reduction credit system would be con- siderably constrained and many potential entrants may be excluded. The same set of barriers makes it unlikely that their will be many ‘ 1 speculators ” who will produce credits for sale to developers. By contrast, a central bank system does not necessarily pose such barriers to access. To some extent, the same impediments to the creation of I/I reduction credits exist; however, they are less severe because the process could be centralized in a public or quasi-public entity which might be able to secure necessar ’ access rights through specific enabling legislation. More importantly, these barriers would not bar access into the system by those wishing to purchase credits, as the purchase of credits from the central bank requires only a cash exchange. ------- -8— B.•Verification : Verification issues, though chiefly technical, have significant structural ramifications. The technical problem posed by the preselit conditidn of the sewerage system are multifold, but for purpose of this discussion can be sum- marized as follows. Because there is no effective flow moni- toring facilities within either the MDC or its tributary member system, it is extremely difficult to measure accurately either a baseline for I/I removal in specific locations or the amount removed. In addition, a gallon of I/I removed from one point does not necessarily represent a gallon removed from the system as a whole. The impact of this situation on a private capital banking/trading system is that realistic verification of I/I removal is virtually unob- tainable and reduction would be ephemeral. Realistic verification would require Department monitoring before and after each reduction, at all sites selected by those attempting removal. The Department does not currently have the staff or equipment to perform such monitoring tasks and the required resources would be excessive compared to the potential benefits. Even rough calculations based on total flow would be of little use because it would be necessary to apportion specific amounts of reduction credit to individual projects which would be occuring continually throughout the sewerage system if the banking/trading system were to function properly. A workable system with unverifiable reduction credits would be difficult if not impossible to establish and certainly impossible to administer equitably. The same technical problems confront a central bank system, but the structure of a central system offers the possibility that they-might be manageable. Because credits would only be created through projects coor- dinated centrally, baseline and post—project monitoring are more feasible. Rather than isolated projects chosen by developers scattered throughout the system, target areas can be selected for I/I removal and some determination made of the effects of the work on the system. Because all credits created go into the central bank, it is not necessary to apportion system—wide (or sub—system—wide) credits among different projects. Credit allowances, though not completely quantifiable would at least be more consistent; making the system more equitable and more likely to obtain the desired results. - C. Enforceability . The technical and structural issues con- cerning the enforceability of I/I reduction are inextricably linked to those of verification. Thus, the same problems outlined above affect this criterion as well. Adding to these problems is the need for some sort of permanence to the reductions obtained; i.e. removal of I/I must be effec- tive for some specified period of time, or credits would be meaningless. This concern requires the maintenance of that work, throughout the life of the credit. A private capital system poses serious enforcement problems from this standpoint. Quality assurance would require constant Departmental presence at all projects. Requiring developers to return to removal sites to perform maintenance work would be extremely difficult in practical terms. The Department currently laciçs the resources to perform either of these functions. ------- —9— Again, a central bank system might be able to minimize some of these difficulties. Both quality control and maintenance could be assured more effectively by centralizing removal work. There is less likelihood of either fraud or inadequate performance and as a result, such a system would be more equitable and reliable. 0. . Credit exchange . The premise of the banking/trading system is that I/I removal credits are both fungible and adequate to allow for added new flow; in other words removal credits should be interchangeable both with other removals and with added new flows elsewhere in the sewerage system, regardless of time. A private capital banking/trading system assu- mes that these units are interchangeable and in terms of the banking/trading system only , this assumption is not unreasonable. However, in terms of the sewerage system the assumption is false, and a system based on it would be ineffective for solving the underlying problems of the sewerage system. Equal volume removal credits are not fungible for several reasons, including timing of flow concentration•, location within the system or sub—system and likelihood that I/I removed from one point will enter (in some propoi tion) at another or cause flooding. If the effectiveness of removal measures deteriorates over time, I/I reduction credits in the bank must also be devalued in the same ratio_ The wider the system and the more variation in conditions the greater the likelihood of incompatibility of removal credits. Moreover, some of the MDC component systems are fairly “tight”, while others offer good oppor- tunities for I/I removal and still others may present flow problems that should be solved in other ways . I/I removal actions also differ in cost— effectiveness (in real terms, as opposed to EPA’s grant—related criteria for cost—effectiveness). The implications of the technical sewerage issues for the banking/trading system strongly suggest that the only type of implementable system is a central bank. A central bank system would focus I/I removal efforts on target areas where I/I removal is most useful from a system—wide viewpoint. The compatibility of removal credits with each other or with proposed additional flows could be judged technically and adjustments in the amount of credit allowed or needed for a particular project could be made. It should be easier to establish sub—systems in which trading of credits could occur. For example, credits neededfor North System connec- tions should be based on North System removal. It may also be necessary to further restrict the transfer area to sub—system levels. Conclusions . Considering the four criteria of market access, verification of removal credits, enforceability, and exchangeability of rem3val credits from the standpoint of the sewerage system as a whole, a central bank system seems to offer considerable advantages over a private capital system of banking and trading I/I removal. The apparent advantage of mobilizing private capital to address the I/I problem suggested by a pri’:ate capital banking/trading system is minimal, particularly since the same amount of capital could be generated through the sale of removal cre- dits created by a central bank and the resources could be directed more effectivly with a centralized structure. ------- -10- Nevertheless, adoption of a centralized banking and trading structure would not solve the underlying technical problems.. In particular, the absence of effective flow monitoring capability within the system, and the practical difficulties inherent in effectively removing I/I (see discuss o below), seriously weakens any banking and trading system. The central bank alternative would obviously require enabling legisla- tion. This legislation would both establish the bank and the basic trading rules and provide an initial funding resource. One major policy issue that should be addressed if establishment of such a system is proposed is the extent to which both start-up and futtire costs should be borne by the public at large and what portion should be borne by those seeking to purchase credits. Should the entire burden be placed on “new development” or should some portion of the burden be shared by existing system users. Greater Than 2 For 1 Program There appears to be some confusion by the Court as to the intent of the DWPC’s existing 2 for 1 program and whether that program could be used to Jjnificantly reduce I/I in the MDC system. The program was never intended to replace the Commonwealth’s Construction Grants Program which has been providing large amounts of money to communities for work such as sewer rehabilitation and I/I projects. The sewer ban and resultant 2 for I program was devised as an enforcement tool to get the particular -- community’s “attention”. Some people have used the following analogy to describe the program: “it is like hitting the community in the face with a two—by—four to get t•heir attention and then once their attention is assured, develop a rasonably implementable method for reviewing, revising and approving sewer extensions while not exacerbating flow problems within the localized sewer system”. To date there are 9 comunities on the 2 for 1 program and several others are under review. Since the implementation of the program in 1980 approximately 5.5 million gallons of flow have been listed as possibly being removed from the sewer system. In affidavits presented to the Court, DWPC stated that even if all I/I specified as being removed from the system was in fact removed, it would take over thirty (30) years to reduce the South System flows by 60 MGD using the same 2 for 1 format and assuming similar numbers of yearly permit applications. The 2 for 1 program is even less likely to significantly reduce flows to the sewer system as the town— wide I/I rehabilitation programs previously attempted by the EPA. In fact the “hunt and seek method” used by developers to find and repair isolated sources of I/I to justify connection of a new building is precisely the type of 1/I rehabilitation procedure that all experts have denounced as unworkable. Professor Haar stated in his Masters Report the following with regard to the current 2 for 1 program: “The 2:1 reduction program is an interim remedy. Although it will not result in the sane kind of significant flow reductions as will the planned system-wide infiltration/inflow reduct.ion program it will provide relief since, without it, new additions will exacerbate the current ------- —11— failures of the system. While hot bringing about large improvements, it will prevent the situation from deteriorating further in the near future. It can be initiated immediately and can maintain the status quo or even slightly lesson the frequency and/or the level of treatment bypasses while the longer—term remedy of a p1anned system—wide infiltration/inflow program can be increased by changing the present ratio 2:1 to require a removal of three or even four units of infiltration/inflow for every new unit of flow added to the system. It is thus possible to design the program in an equitable and effi- cient manner. The DWPC has the authority to impose such a program on MDC member communities. Experience with jndividual communities has shown that development typically does not stop and that infiltration/inflow is removed as a result of the imposition of such programs. Therefore, the 2:1 reduction program is an appropriate interlocutory remedy to be imposed by the Court.” DEQE believes that just increasing the percentage removals of ru from the current 2 for 1 to 3 or 4 for 1 will have no measurable impact on bypassing and overflows into Boston Harbor. We do believe that the sewer ban and 2 for 1 program is effective in forcing a community to deal with its sewage problems and provides a framework for closer coordination be- tween DEQE, the municipality and the development cori nunity. Therefore, DEQE proposes to continue with the current 2 for 1 reduc- tion percentage as part of its enforcement actions in comnunities with acute problems. However, the continued use and effectiveness of this enforcement mechanism will be closely reviewed in conjunction with the development of a system—wide approach for dealing with I/I in the MDC system, which is discussed below. If the system-wide approach offers more effective alternatives to permanent removal of hr. the use of the 2 for 1 program as an enforcement tool may be altered or discontinued. Intearated Sewer Management Program There must be a system-wide commitment for the develapment and imple- mentation of an integrated MDC sewer management program. This program must include at a minimum: 1) Provision of transmission, pumping and treatment facilities with adequate capacity for the MDC system; 2) A realistic on-going I/I reduction program; 3) An effective sewer extension and permitting program; 4) An on-going municipal sewer maintenance/rehabilitation program for all communities within the MDC system; and 5) A system-wide flow monitoring network. We further believe that these five program elements can be implemented and that much of it is currently on-going as specified below: ------- —12— 1) Capacity : The MDC. and many of its member communities are already implementing this program with such projects as the Nut Island and Deer Island Primary Upgradings, East Boston Pumping Station, Framingham Interceptor, Charlestown Pumping Station, etc. The Procedural Order Item #23 tracks the compliance for most of these ongoing projects. 2) I/I Reduction : The Departement plans to utilize the $100 million grants program (if enacted) to develop a state—of—the— art I/I rehabilitation program which could remove DEQE from the artificial cost effectiveness regulations required for the expenditure of EPA grant monies. We would like to be able to define major problem neighborhoods and rehabilitate all sewers and associated facilities within the entire area wit1 pre— and post— flow gauging. Based upon the effectiveness of those projects we would develop a priority rating system for the entire MDC system and begin funding neighborhood reduction projects. 3) Permits : DEQE has developed an interim program to ensure ade- quate reviews of all permits within the MDC service area. DWPC has sent requests to all South System municipalities requesting copies of all building permits issued by them from January 1982 to the present. This data will be cross—checked against Sewer Extension Permit Applications to determine the extent of compliance with our regulations. An extensive educ— tional program has also been initiated by OW?C to help ensure compliance with our permitting program. 4) Ongoinq Municipal Rehabilitation : This is the most difficult aspect to control and enforce since it is strictly a local function with no state or federal regulations mandating the nature and extent of such work and no outside funding sources available to the municipality to offset the costs. A thorough sewer maintenance program would require the expenditure of significant amounts of local monies. Due to the current financial constraints imposed upon the municipal governments and the constraints upon new state regulations that increase costs imposed by the Proposition 21 tax cap legislation, it can almost be guaranteed that any type of elective expen- ditures (preventive maintenance) will not take place. DEQE believes that this type of work will become much more attrac- tive to the municipalities if a method of assessment versus flows is devised and implemented by MDC. Also under existing regulations (MDC regulations and most local sewer ordinances) it is presently illegal to discharge clean water (vooling water, storm water, or groundwater) to the sanitary sewer systems. However these regulations are not strictly or actively enforced in most cases. Any preventive rnanintenance program should be “supported” by a strong enfor— cenent program conducted at the local, district (MDC) and state (DEQE) levels aimed at eliminating to the maxii in extent feasible illegal conner— tions of clean water into the MDC and mem5er communities sewer systems. ------- Enforcement activities would be cohducted by parties such as the MDC Industrial Section; local public works departments, building and plumbing inspection personnel; with general oversight by the DEQE — DWPC. The system—wide monitoring capability would be used to target priority areas for enforcement and investigations; to evaluate results and to monitor the possibility or reconnection. Available penalties would be examined and modifications proposed where appropriate. 5) Systemwide Flow Monitoring Network : The capability to monitor and evaluate flow continuously throughout the MDC system and at strategic locations within its member municipal systems is essential to the proposed program of minimizing extraneous flow in the system. The information gained through this capa- bility could be utilized: a) in both the Federal and State Grants Program for setting priorities for funding and eva- luation of construction and rehabilitation work; b) in the Enforcement Program to identify prime areas for investigation of illegal connections; and c) on the Incentive Program in establishing the flow upon which sewer charges will be based., Continuous system—wide flow monitoring capability is a prere- quisite for implementation of the proposed flow based sewer charge system and for a realistic banking and trading systerrr_ In summary we wish to again stress our belief that an intergrated approach to the regional sewerage system difficulties is needed. The only way to develop such an approach is to jointly educate all participants (State Agencies, Municipal Officials, Area Legislators, etc.) in the various facets of th process. We do not want to blindly grab onto one or a combination of quick—fix alternatives. Our own experiences with the 2 for 1 program is a perfect example . Our agency saw the program as a readily enforceable and implementable method of reducing flows in the local and MDC sewerage system to mitigate sewer overflows and surcharging while allowing for reasonable continued growth to occur. DEQE, like EPA, assumed that I/I reduction techniques used in the late 70’s and early 80’s actually removed a significant percentage of I/I. We have recently learned that such an assumption was incorrect to a large extent. The development of our proposed Technical Advisory Group, can be used as a spring board to begin this eductional process. ------- . ttacvnent .j. - • ““ :valu3tjc,r o1 Irfi1eratjo /In:iow .o _ ..., ... Rc ort July 1980 U.S. Environ nta1 Protection ?.ge c’, CHAPTER 4 The findingsof this.study indicate that Sewer Svste Evalua- tion and Rehabilitation generally does not result in sub—- s r.tial systen I/I flow reductions. The conse uence of .thizis that returning I/I has used up all or substa ja1 port onsc the reserve capacity of new and u graded, treat— zac .l .t es and thus, shortened the plants’ design lives. I/I is not going to be removed by ignori git -—.Thus;—j 5 -— eer aJ. that it be evaluated in order that sewerage works ca b esigned and operatec effectively. The follcwin recom mendations are offered as possible courses of action that EPA can undertake in order to ensi e ti at I,: is effectively addressed in design and operations of s- : rage works. These recommendations offer a variety of : - ic that could be im?leTnented. Some recodatic s c 2.d be implemented together while others could not A dizcu sicn is presented with each reco endation. C> E DATIO ’1 l REuSE THE I/I PROGR ’i f ETHODOLOGYI Is — — ‘— ‘- — . _, -. The existing i/I Progren methodology simply has not achie red expacted results. It has become evident that successful r& ebilitation is more of an e>:ce?tion than a gemexal case; just the opposite of ‘ hat was assumed when the I/I Picgraza w s initiated. If the I/I Program is to be continued., the th ology be revised. The following arc o a of the possible changes to Sewe: S7stem Evaluations that would provide more realistic initial data, thus, resulting in i ore successful projects : - St r.!ardi:e cuantificaticn of system—wide I/I_ Cu:: n:1y, a wi c variety Of para ct :s are used in design ar. cost e cctiv cz analyses for the f1c : c c :: 1.2. w t ce o I/I, - at: da-.; v : -’ ...-¼:1 I/I, I/I at 1OQ v..:: - This c. . .,r,’:r t j :n :?1lv C5t t C d tO D OV1( e 1t . ‘. cr.: . n cost er:: v: : . al. 7 .:r. . :cr I,’ r. ‘1—1 ------- i/i flow monitoring and televis.icn inspection 111.Lst be rformed during wet weather and/or high ground- water conditions (I/I Hunting Season) - This study hz z found that in many instances television i .spec— tion was not perfo ed during peak high groundwater conditions. Any leaks observed from manholes, sewers and house service connections were factored u to re- flect. peak flows. This practice has resulted in er— ronsous flow estimates from point sources. It is L perative that flow monitorthg and television inspec— tion be performed during a specific “hunting season” • This can be defined by using a specific syster . total flow parameter: for example, three (3) times base flow, or a system I/I rate greater than 6,000 gallons per day per in-mile. Establish a realistic system I/I rate to be used as a cut-off for projects to proceed to Sewer System Zva1uatio Surveys, ie, 6,000 gallons per day er inch mile. EPA established an infiltration rate of 1,500 pd/irL mile including service connections in its PR i7 —lO Any rate balo ; this value was considered non—excessive.. This study has fo nd that most of the projects had -rabilitat n high week I/I rates exceeding 6,000 gpd/in—mile. Post rehabilitation high week I/I rates ware reduced from above to belo 7 6,000 ctd/in—mile in only one (1) project. It may be pos— that cost-e:rective rehabll2.tatlon work can be a:hi ved in sewer systems with pre-rehabilitation I/I : zt below 6,0CC god/in-mile, but chances of success would be minL al. Establishment of a cut-of f I/I rate of, say, 6,000 gpd/in-mile could speed u any rojects, and result in more successful rehabilita— Include limited television inspection and rainfall sL ulaticn work in the I/I Analysis ?hase. In the I/I Analysis Phase, estimates of I/I to be r no;ed are made, rehabilitation programs projected and cost—effectivenezs estimated. All this is done wjth ut firm documentation of There the I/I is coming from. This study has found that ‘a major source of i/I is house service connections, and the flow iroa 4—2 ------- this sourco is not detectable in the I/i Analy is Phase. In most instances, the flow measured or estimated during this Phase erroneously ass nas that most of th. I/I is from manholes or sewer lines, and the resulting reco r ended I/I. removals via sewer line rehabilitation looks attracti ie. If limited television inspection identi d s ecific sources, a more realistice rehabilitation program could be out- lined. Pa:foming limited television inspection of, say, 2 to 5% of the system, and possibly limited rainfall sii ulation where inflow is suspected, during the I/I Analysis Phase would result in ore realistic ccnclusions of this Phase of work. Consider the impact of ±/1 from house set-vice connec— tion and groundwater migration aftef sewer line rehabUitation. This study has found that estimates cf I/I to be re— duced by rehabilitation generally have been in the 60 to 0% range, while actual reductions have generally been n tne 0 to 30% range. In acc t on, curing cost effectiveness analysis no consideration is given fo: migration of groundwater to non-rehabilitated sources. The oercent I/I reduction achievable by main barrel sewer line renabilizat on, nclu 1flg test and seal prog:ams, is dependent on one (1) par- ameter more so than any other: the percentage of I/I coming from main barrel defects versus the pecentage co: ing from house service connections. eteievising curing zh .s stucy found tnat I/I coes ig:ate to non— rehabiljta ted sources, and that rehabilitated sewers where less than 60% of the pre-rehabilitation I/I was docum2nted coming from sewer joint leaks (versus house service connections) achieved reducticns less than 25%. A rough estimate of this important parameter should be ascertained as early as possible. Under the pre- sent methodology, t:iis parameter is not defined until at least the SEES televising phase. In certair. cases, where SSES televising was foregone in lieu of pro— - posed test and seal program, or when SSES televising as done during low groundwat :, the se ;er line jOint leak percentage was not asce:zained at eli. In order to re listica1ly predict I/I percentage ro;al , we have daveloped the cu: e3 presented in Tig re 4—i. Zsti:r atir g I/I Reductions. These curvcs . d ‘elo e fro -r actual rc :ul:z a’d :e:liztically i: cDrpor e retu:ning I/i from h se s r ice connec— 2.Ofl5 ar f mig:at n. 1 .8 ------- 0 25 50 75 tOO % INFILTRATION REDUCTION I/I REDUCTION FIGURE 4—I ESTIMATING CURVE A • TEST a SEAL WITH LIMITED SERVICE CONNECTION flEP !fl CURVE B REPLACEMENT SLIP LINE • TEST a SEAL WITH EXTENSIVE WORK ON SERVICES 1/ ) I— 0 U i ti— (U -J ‘Ii c i: C r ) 0 LL IL 0 U) U i L) > a: Ui U) 0 a: Li I I— 0 ------- Stanciardjz television inspection flow. estir at ng techniqt e. Visual flow estimation of leaks bserved •during tele- vision inspection can vary by as much as +5O .. This data is .a significant element of any cost effective— nass analysis and resultant rehabilitation procr _ A standardized technique should be developed_ - 2 REQUIRE THAT REHABILITATION BE PERFORMD ON A “PATCW’ BASIS.. SUC 1 THAT NO PIPE IS LEFT UNREHABILITATED IN AN AREA CHOSEN FOR REHABILITATION, THIS WILL MINIMIZE THE OPPORTUIilTY FOR I/I TO MIGRATE FROM REHABILITATED SEWER SECTIO’NS TO f ON— REHABrLITATED SECTIONS 1 T::.. notion of I/I migration from rehabilitated sewer sac— t n to non-rehabilitated sections is widespread. Reha.bili— t :ticn work can zc eeimas take on a “little bit here, little bit there” appearance; thus maximizing the opportunity for I/I tc igrata upstream or downstream of rehabilitated sotircas acceptance of test and sea]. grouting over specified j in g:o ting wa based on resolving the I/I migration ef— :: e x ensive .test and seal, as well as other rehabilitation t: u may be reçuired to minimize the I/I migration p:oblam. — ‘“ I -. re. m 1 . —. .. .i i. 1. DECREL SE THE STANDARD DESIGN LIFE OF iR ATI iENL. PLANiS FRON 20 Ya RS TO 10—20 YEARS., DEPENDING ON THE ABILITY OF LONG RA; GE RE} ABiLiTATiOU TO REDUCE I/I. T. : : ; nt ituatior., in part d to the failure df the I/I is eh t n w C: u? racec t:e tr nt plants are at or r. r a: n c c .tv afzc: only cn (1) or t o• (2) years of c: z .-n. ccr u-ities ar f c with planning now or 4—5 ------- in thc r.car future for either substantial sewer line.rehab—. iiitation tnd/cr pia t ex ansion. These communi .es were, in face, cxp Ctiflg to attain 20 years of useful life from — ‘ A way around the present dilemna is to be realistic and not OV i optimistic about the effectiveness of sewer-line re— habilitation and trsatment plant design life. The following • infor a ion hou!d be considered du ing the planning and/or operation of new sewe age works. Recognize that generally a sewer system rehabilita- tion program will reduce 1/I from 10 to 30 . There, of course, will be exceptions to this general rule.. “One shot” sewer system evaluation and r habLritaeion will not identify and/or eliminate all th& sewer system I/I problems. - on-going operation a d main— tcnanc program must be L ip1emented to include in— vestigatir.g new and old I/I sources and performing on-going rehabilitation. The actual effectiveness of rehabilitation in red ic— ing I/I flows in the system should be determined, after rehabilit €ion is complete. Thus, the approach to sizing treatment plants would be to i l c e a lercer i/ flow com onent (than would be esti ated a±: : rehabilitation under the present methodology, which to e::pect large reductions in I/I) and a smaller re— z r e capac ty f r base flow expansion. This would tend to ; ? th average treat ent plant size and cost about the - s a a under the present I/I methodOlogy. By designing r e lants to handle not—so—drastically reduced I/I flows, and p yin for this by limiting future reserve capacity the actual changes in I/I nd base flow can be monitored, and thus, facilitate decisions on additional rehabilitation andf or plant c x nsion as the 10 yea: or more design. life-is apprcached. REC 1 -: YO.;TION 4 E FO CE SE’dER LINE OPERATION AND MAINTENANCE PROGRPJIS. O tr2tion d maintenance (0 & i -i) progr s on sewer systcms are r q f: d p:r PR i7!—lC- This study has fou d that this I —6 ------- is nc t being ir 1e Gnted. .on—go ; 0 ! orogra will disco er fl’2w I/I Sources and often these will be easily re— t.tir d It is .in the best interest of the co unity, from a co t effective pe soactive to cont r’a1 v ava 1 ua e ar d re— /! that s less ex?enslve to elii nate than to treat C0 Z DATI0N S AJDRESS THE PROSLEM OF I/I FROM PRIVATE SOURCES SPECIFICALLY THE DETECTION., DISCONNECTION A D REPAIR OF PRIVATE I/I SOURCES SUCH AS SUN? PUMPS.. DRAINS, ROOF LEADERS A LEAK— U G SERVICE L TEP 4LSI DIScUSSION I/I con thuted from orivate sources generally constitutes o er 5Q of the system I/I. Thus, treatr ent plants will ct to have high I/I flows during wet weathe and high g:o’ ;ater conditions if private I/I sources are not re— In order to reduce treatrnent plant sizes ai airi— good treatment plant operation, cor. unities should ad— c r ss these private l/T sources. Thcse co unities that ig’c:e this major problem should be penalized. ? DATI0 c• . ‘CcTirAT t-IDTPI A IINr1T !r 7Dlv-TIfD: TL!, T J 1 t Li r irL I l u ri unu hu iLiw U riL .- ..LLJ;I F R ?: ASED RE;-L43ILITAT1ON WITH GO/NO-ED DECiSION POIf’ TS • Ci,f U DL..”C - 1. IL.. LtLI1 riu- ..., ( \T T; e 1/ 1 reduction aohieved by rehabilitating a collection s t cannot be ascertained finally until after the work iz cc plete and the system e>:periences design—level pre— ci iticn/sn . elt conditions. n atter ho ::e1l-docu anted the pre-rehabilitatioi . I/I so rc s, it at:aars that counzin on an timated reductiort. cosr. ef czive is analaoous to counting on a cood be t core zhro gh. A phased program o: r ao2 .l .tat fl ouJ the actual reduction achieved by rehabilitating part C: a coll2ct:cn sysze to be used in dat2r ining the èost cti’.n ss of f :zher rehabilitaticn. 4—7 ------- Ped rch i1itation could be integra ed with seivice.pop— ulat d e: :PaI’s1on; i.e. phased reduction of the I/I design cc: 2ona1t could kee up treat ene plant design capacity base flow expansion. There are p:obler s with .such an approach. The variability of rainfall and snowme lt from year to year could lead to fft’.se conclusions about achieved reductions. f ndi g - ct re znat a1lcc s Go/No—Go dec .sions after each ohase cc .d e an ad inis rative n ghtnare.. The problens i vo1ved funding, in particular, would rec’ ire detailed evalua— ti before adopting any forrn of phased rehabilitation. 7 W 1ITUTE A STUD? TO DETEP UNE THE ACTUAL EFFECTS OF 111 LO Ji G O TREATMENT PL4NT PERFORMANCE. USE THE RESULTS TO ESTABLISH GUiDELINES FOR DESIGNING FOR I/I, Thera is currently no standard design practice for ha d1ing i/I ot: : than the use of standard design hydraulic loading r t s dcveloped for rew savage. A rational basis for treat— i:: diluted se :age is ç arly needed, based on the docunented e t of I/I loading on plant performance. The capacity t: - ent plants to weather both short-term “inflo a:d long—term “i’ ltrat on ’ should b determined, as i : :v :eo:esent a significant “source’ of I/I capacity in— t in standard treat ent plant design practice. Z D..TION 8 I T TUTE DISCHARGE PERMIT REQUIREMENT VARIANCES DUR1N5 P .:• oDS OF HIGH I/I FLOWSJ TAKING PIDVAUTAGE OF Th:E INCREASE [ i!L TiVE CAPACITY OF RECEIVING WATERS THAT GENERALLY II It jLU 1 r i :S rilGn I/I •% •• _•1c —,.s I L .1 _.‘.. . - . nil I/I loadings r y cause treat ent plant efficiencies r c d well b lcw the recuired 85% re iovals for Bio— c ic l Oxygen Demand (3CD) and Suspended Solids (55) acc p ying dilut!on effect of the 1/! generally enab].es ::i c e±!].uent ch r ctc:is ic5 to rer ain elc ; 3D iliigrans !itc . The to::;l of these effluent ;a: etcrs b i: c: asec3, :,‘: the high : receiving te: flc rs may - . s .ly ;e the az ;i; .iletivc capacity. 4—8 ------- cc: : ? T!O 9 i: STLTUTE A (1O ATOR1UM ON ALL I/I ANALYSES AND SE 1ER SYSTEM EVALUATION SURVEY REPORIS THAT ARE UND: WAY OR RECEi iLY COr PLETED 1 THESE PROJECTS SHOULD BE REVIEW AND 1• 3D [ FIED ACCORDING TO THE FINDINGS OF THE STUDY, DISCUSSION I/I f_ alysas and Sewer System Evaluation Surveys are still being based on unrealistically high expected reduCtions. One (1) or two (2) years from now these projects will be con— structed and the same findings of effectiveness will be m. de as in this study. Thus, in the long run it woiild be beneficial to delay these projects for a short period now, and obtain more realistic results when sewer line reb bilita— tion is completed. 4—9 ------- Estir ated M D 2 0.63 125.0 16.2 8.8 5.1 10.3 7.1 .6.0 N/A 3.1 - 4.1 11.3 9.2 22.4 2.6 1.2 3.3 3.7 1.2 2.1 •) ‘ ., • -, PE.K 1/.1 ? .EDUCi’ICN SOUT.- ! TROPOLI AN DIS ICr Existing I/I’ Procsed C-PDIM 3 3330 0.36 20830 66.0 10750 9.05 9150 5.30 7800 2.85 12500 5.9 3180 4.2 26500 1.0 N/A N/s. 3500 2.2 3250 2.0 3100 2.65 5530 6.5 8310 6.0 9150 12.9 3660 1.5 3860 6350 1.2 2370 2.5 2900 0.7 5550 5.1 139.11 I/I G?DI 1 -a 11000 6000 5500 4350 7150 1900 4400 500 1850 2000 3200 5400 5250 2150 2550 3130 1600 1300 3500 cC : : NIFL S ston* Car.tort De rn : r 1 r. .ngh m Hc1 :cok N i:k N 1 .’ — i—. . & __.e_ — O incy s tc• . tcn - .: as d .rc: j r- c rr :-t - icn . c :r c :, - = G-.1! ’ r :... ‘ : ------- |