PB-239 566 STREAM POLLUTION ABATEMENT BY SUPPLEMENTAL PUMPING Carl W . Reh , e t a 1 Richmond City Department o' Public Utilities \ 1-••'"»'-'"*-•''"*" Prepared fir: National Environmental Research Center February 1975 DISTRIBUTED BY: Tc^ls&J tsferos^osi Sc-rtlse U. S. SEP^TSQiT £-F CP^KEGCE ------- //'/< Jfi n VRINOn I.PA-b70/2-?5-035 | TECHNICAL REPORT DATA traJ Inilfitt »<•»< f»i fn riim< him i. J TltLt A\O SUUIITLE "Stream Pollution Abatement by Supplemental Pumping" PB 239 566 5 REPORT DATE iL?'5-issuing Pat 6 PtRFORMING ORGANIZATION CODE 8. PERFORMING ORGANIZATION REPORT r.O Carl W. Rch and liarren IV. Sadler 9 PERFORMING ORC-MZATION NAME AN ADDRESS City of Richmond, Virginia Department of Public Utilities Richmond, Virginia 25211) 10 PROr.RAM ELLMENT MO. 1HB054 11 Op^^A^.GRANT NO 11022 FLV G ACC.MCV NAMfc AND AODRLSS National Environmental Research Center Office of Research and Development U. S. T.nvironncntal Protection Agency Cincinnati, Ohio 15268 13 TVPC OF RCPORT AND PERIOD COVCPEC 14 SPONSORING AGENCY CODE 15 SUPPLLVII ttTAHV NOTES At the Riclimond, Virginia, h'astcuatcr Treatment Plant, a major structure, i.e., a Supplenenta-1 Pumping Station, and «;c\er:il ancillary structures were provided to achieve the project objective of no bypassing uhilc a ncv. grit chamber was being connected ahead of the existing Main Pumping Station, which station received and pumped all of the ran scha<-c. The Supplemental Pumping Station uas constructed by sinking a tuo-comp.irtmcnt, sheet steel cofferdam around an existing 72-inch concrete sewer and rearranging the* influent sewer flon pattern so that the sewage uas redirected to the site of the Supplemental Pumping Station. The redirection of scuagc tlow has achieved by the recon- struction of a junction chamber and by the insertion of a specially designed removable bulkhead, all without bypassing sewage. The time required for the design, construction and operation of the Supplemental Pumping Station uas about 36 months and the cost of this project uas approximately $900,000. KEY WORDS AND DOCUMENT ANALYSIS DESCRIPTORS hater quality liastc treatment I' IPENTIHCnS'OPEN tNOEO TCRMS Richmond,(Virginia) James River Wastehatcr treatment p 1 a n t Supplemental pumping On-line modification Sheet s>recl coffercla COSATI 15B l~ri-llsut ION STATLMI.NT Release lo Public 19 StCUKITY CLAbS (//IfI K,p,.rtl Unclassi fied 21 NO Ul CAGES 20 SECURITY CLASS r'/iM/wcr; Unclassified 32 PRICfc EPA Form 2220 1 (9-73) ------- 0 6r:i?5 i:PA-670/2-75-035 1'cbruary 197S STRLXM POLLUTION ABATEMENT BY SUPPLEMENTAL PUMP IXC By Carl K. Reh and harren E. Sadler City of Richmond, Virginia Department of Public Utilities Richmond, Virginia 23219 Grant Xo. 11022 FLV Program Element 1BB05-J Project Officer R. F. Roudabush U.S. Environmental Protection Agency Region III Philadelphia, Pennsylvania 19106 NATIONAL ENVIRONMENTAL RESI.ARCII CFNTPP oi-ncr oi- RI:SI.ARCM AND DEVI.LOPMINT •rl-Sivv-?"^"1^1' PROTICTIOX AGENCY CINCIXNAII , OHIO 45268 ------- REVIEW XOTICr. The National Envi ronmcnta 1 Rcscarcli Center-- Cincinnati has revicued this report and approved its publication. Approval does not signify that the contents necessarily reflect tl : vicus and policies of the U. S. Environmental Protection Agency, nor docs mention of tiade names or com- mercial p.oducts constitute endorsement or recom- mendation for use. ------- JOR I: t 0 RI) Man and his environment must be protected from the adverse effects of pesticides, radiation, noise and other forms of pollution, and the un ise management of solid waste. Efforts to protect the environment require a focus that recogni :Cs the in terplay het ecn the com- ponents of our physic:il envi roninent——air, t%atcr, and land. The National Invirotimental Research Centers provide this niultid.’ciplinary focus through programs engaged in • studies on the effects of environmental contaminants on man and the 1)1 osphe re , and o a search foi h3 S to prevent contamina- tion and to recycle valuable resources. This report describes the construction and operation of a Supp]ementa 1 I’unipi ng Station that as insrzi lIed at the Ri chnond { i rg in la) hastc atcr Treatment Plant . The use of this station made it possible to continue plant operation hi]e net plant units ;ere being installed. A. h. Rreidenbach, Ph.D. Director National Fnvironmcntal Research Center, Cincinnati ‘ i i ------- ABSTRACT In past times, the insertion of a major element into an existing sewage treatment plant was accomplished by taking the plant out of service and bypassing sewage during the cut-in period. It is possible to insert, new plant units in major sewage treatment works without bypassing; however, avoidance of bypassing may require the construction of other major facilities. At the Richrbond, Virginia Wastewater Treatment Plant, (Annual Average Capacity = 70 mgd) a major structure, i. e., a Supplemental Pumping Station, and several ancillary struc- tures were provided to achieve the project objective of no bypassing w1’ile a new grit chamber was being connected ahead of the existing Main Pumping Stition, t hich station received and pumped all of the raw sewage. The Supplemental Pumping Station was constructed by sinking a two—compartment, sheet steel cofferdam around an existing 72-inch concrete sewer and rearranging the influ- ent sewer flow pattern so that the sewage was redirected to th site of the Supplemental Pumping Station. The re- direction of sewage flow was achieved by the reconstruction of a junction chamber and by the insertion of a specially designed rem wable bulkhead, ;ill without bypassing sewage. The time required for the design, construction and operation of the Supplemental Pumping Station was about 36 iv ------- months. The cost of dcsign, construct.A..- and operation was about $900,000.00, of which $282,022.00 was provided by a E1’A Demonstration Grant. This report is submitted in fulfillment of Research, Development and Demonstration Grant 11O22FLV, Construction Grants 1 1PC—VA-246 and WPC-VA—273 from the Environmental Protection Ayency to the City of Richmond, Virginia. V ------- CONTENTS Page Abstract iv List of Figures vii List of Tables x Acknowledgments xi Secticns I Conclusions i II Recommendations 3 iii: Introduction 6 IV The Construction Design 30 V The Construction 62 VI The Operations 74 VII Discussion 87 VIII References 107 ‘Ti ------- FIGURES No. Page 1 General Location Map. . 7 2 Grit Removal Facilities View of New Grit Removal Facilities 8 3 Grit Removal Facilities View of Open Channels of the Grit Chamber • 9 4 Tributary Intercepting System and Treatment Plant Facilities 12—13 5 Existing Conditions Prior to Construction of Grit Removal Facilities 14—15 6 Flow Diagram Temporary Bypassing with Chlorination 16 7 Flow Diagram Alt. 3 with Supplemental Pumping Station. . . . 8 Work Done Under Alternate B to Avoid 3ypassing. . 20-21 9 Hydraulic Profiles 2 -23 10 South Junction Chamber Temporary Bulkhead. . . . . . . . . . . • • . • 26-27 11 Plan and Section 32-33 12 Sectio’ 343 13 Supplemental Pumping Station Grading for Site . . . . . • 36 14 Supplemental Pumping Station Erecting Working Platforri • . . . . • . 37 15 Supplemental Pumping Station Driving Sheet Steel Piling Cofferdam for Substructure . • . . . • • . 38 16 Supplemental Pumping Station Cross Lot Bracing of Substructure . . . . • . • 39 17 Supplemental Pumping Station Existing 72-Inch Lower Goodes Creek Intercepting Sewer • • . . • . • . 40 vii ------- FIGURES (Continued) No. Page 18 SupplementaL Pumping Station Partially Completed Pumping Station, Discharge Piping and Diversion Structure. . . . 41 19 Supplemental Pumping Station Interior View of Sewagt Pumping Units . . . . . 42 20 Supplemental Pumping Station Exterior View of Completed Pumping Station and Discharge Piping 43 21 Supplemental Pumping Station Pun ping Station Discharge Piping and Diversion Chamber . . . . . . . . . . . . . . . 44 22 Supplemental Pumping Station View of Open Wet Well and Enclosed PumpRoorn. . . . .45 23 Diversion Structure Breaking Out Openings for Discharge Pipe and Temporary Bulkhead. . . . . . . . . . . . . 46 24 Supplemental Pumping Station Electrical — One Line Diagram . . . . . . . . . 50-51 25 South Junction Chamber Transporting Prefabricated Special Bulkhead to Site . 55 26 South Junction Chamber Lowering Bulkhead into Place . 56 27 South Junction Chamber Scuth Face of Chamber Showing Bulkhead in Place. . . . . 57 28 South Junction Chamber Preparation for Construction of New Junction Chamber . . . . . . . . 58 29 South Junction Chamber Placing Reinforcing Steel for Conduit Between New Junction Chamber and Inlet Chamber . . . . . . . . . . . . . . . . . 59 vii i ------- FIGURES (Continued) No. Page 30 South Junction Chamber Removal of Prefabricated Bulkhead 60 31 Chronology 72-7" 32 Sewage Pumping Units Characteristic Curves 80-31 33 Calibration Curve Plant Effluent Weir vs Supplemental Pumping Station Flow 82 34 Wastewater Treatment Plant Plant Effluent Flow 84-8* 35 River Sampling Stations 88 36 James River, Dissolved Oxygen Level 91 37 James River, Biochemical Oxygen Demand 92 38 Wastewater Treatment Plant Influent and Effluent Loadings Suspended Solids 9fi-97 39 Wastewater Treatment Plant Influent and Effluent Loadings Biochemical Oxygen Demand 98-99 ix ------- TABLES Page No. - *— 1 Monthly Flow Summary .............. 86 2 River Sampling Data July, 1963-Junc, 1969 4 River Sampling Data February, 1972-Derember, 1972 90 Treatment Plant Loadings 93 5 James River Flow January, 1958-December, 1972 100 ------- Acknow ledge’ ’e nts This project was financially supported by the City of Richmond, Virginia, and by grants from the Environmental Protection Agency. Messrs. Harold J. Snyder, Jr. and Fenton Roudabush were the Project Officers for the Office of Water Programs of the Environmental Protection Agency. Mr. Snyder was in— struinental in assisting the City in securing the Research and Demonstraion Grant and Mr. Roudabush was most cooper- ative in assi5ting the City with the administration of this project. Staff personnel of both the Department of Health and the Water Control Board of the Commonwealth of Virginia were most helpful during the entire period that this Re- search and Demonstration Project was conducted. We wish to extend our sincere appreciation to both Contractors who worked on the project; Potter and Parsons, Inc., Baltimore, Maryland, who furnished the pumping equip- ment and the English Construction Company, Inc., Altavista, Virginia, who constr”cted the Supplemental. Pumping Station and installed the equipment. The English Construction Com- pany also constructed all the other appurtenant work necessary to make connections between existing facilities and the net’ Grit Chamber and also between the existing primary treatment plant and secondary treatment works. xi ------- Grecley and Hansen of Chicago, Illinois, were the Consulting Engineers responsible for the design of the Research ard Demonstration project and assisted in the supervision of th construction of these facilities. The project was under the direction of Mr. H. E. Lordley, Director of the Department of PubliC Utilities of the City of Richmond, who was abJy assisted by Mr. G. M. De’ano, Chief, Utility Plants, and Mr. L. H. Roden, 3r., Chief, Division of Wastewater Treatment. Mr. Roden was the City’s Project Coordinator for this project. xii ------- SECTION I CON CLUS I ONS 1. The project demonstrates that it is possible to cut in a major sewage treatment plant element without the need for bypassing raw sewage. 2. W ere no special provisions have been made either in the existing works or in the design of the new facili- ties for cutting ¶.n major plant ements without by- passing, special design will be required to achieve the “no bypassing” objective. In the case of this project, the special design required principally the supplemental pumping station and the construction of a unique bulk- head with a built-in sluice gate. 3. “umping units of standard design can be used. The pumping units which were selected were variable speed motor driven vertical centr fugal pumps. 4. A two compartment sheet steel cofferdam is a feasible means for constructing a pumping station substructure around an existing sewer. 5. The time for design and construction of so-called temp- orary facilities is likely to approach that required for conventional facilities. 6. fleliable operation can be achieved through the design of simple mechanical configurations. Thr total control was: ?ump-on, pump-off. and pump-speech Suction or discharge valves were not operated as a part of the 1 ------- start-stop sequence. 7. Variable speed pump operation is feasible without a wet well. The close control of pumping levels, however, is difficult to achieve and requires more than ordinary attention. 8. Provisions should be included for large debris from finding its way into the pump suction through unantic- ipated water levels. Large garbage cans and tires suc- ceeded in finding their way behind the coarse bar racks and interfered briefly with pumping operations. 9. The degree of treatment of sewage was maintained through- out the construction period. 10. o deterioration in th water cuality in the James River was experienced throughout the construction period. 11. The scheduled bypassing time for the construction of the grit chamber was 110 calendar days. The time re- quired to design, construct and operate the supple- mental pumping station was 36 months. The total sewage pumped was 13,125 mg. 12. The ccst of the new grit chamber was approximately $1.8 million. The cost of the supplemental pumping station and appurtenant work was $900,000. This amount in- cluded the cost of design, construction and operation. If all costs of the supplemental pumping station are applied to the cost of pumping sewage 1 the amount would be $65.! 4 per million gallons. 2 ------- SECTION XI RECOMMENDATIONS 1. This demonstration was necessary because of a change in Federal guidelines. At the time a new grit chamber was scheduled to be connected to the sewage treatment works, the Federal guidelines were revised to prohibit any bypassing of raw sewage to receiving waterways As a result, the use of the new grit chamber was delayed about 36 months until a suppleme-rtary pumping station could be designed and constructed and the necessary connecting works completed. It .is recom- mended, therefore, that, to the maxii ’um extent possible, any project approved under one set of gtidelines, and for which the major construction has been accomplished, be allowed to be completed under those guidelines rather than be conformed to a new set of criteria. 2. The project demonstrated that new plant facilities can be cut into an existing plant without the need for bypassiriçj. The delays in the completion of the new works cemonstrated the need to include those facilitics for the avoidance of bypassing among the provisions for cut-in included as part of the original design. Such facilities should not be made a separate element of work. 3 ------- 3. If supplemental pumping is required, the facilities for such supplemental pumping should be included as a part of the general plant construction. A greater selection of pumping equipment will thereby be made available and the time for construction and for pumping will be coincident with the general plant construction and will not be made a sequential itei of work. The cost for such supplemental facilities will be reduced by this procedure. 4. Pump control is basic to the operation of the supplemental pumping station. Usual automatic controls are not adeauate for a pumping facility which has no wet well. It is necessary that a single level he defined for the control of all pumps at all speeds. Such a set point controller will facilitate automatic operation and will avoid problems in ump speed setting. 5. If a supp emental pumping statirn is to be strictly a one-time temporary pumping station, simpler config- urations for the substructure should be explored to reduce both the tine and the cost. Multiple smaller circular cofferc]ams may be feasible and if the time for the exploration of pump types is available, some form of a vertical wet pit type dredge pump might be 4 ------- suspended within the cofferdam. These elements may tend to reduce time and cost. 6. The supplemental pumpinq station was planned to function about 110 days whi’e the new grit char ber was being cut into the system. It was to be main- tained on a standby basis should some future contin- gency require its reactivation. If a supplemental or a standby pumping tation is to be maintained for the total life of the treatment works, the substruc- ture should be large enough to accommodate equipment for all the future sewage quantities to be expected. The design concept r ight be different from the one which has been constructed. The function of a proposed supplemental pumping station shculd be fully explored and developed prior to the start of design. S ------- SECTION III INTRODUCTION A. The Problem The Richmond Sewage Treatment Plant was designed during the early l9SO’s and placed in operation in 1958. ost p1 ints of this age had no means of routing sewage around its main pumping station without bypassing raw sewage. The practice of bypassing has always been permitted in th? past throughout the country. The City of Richmo’ d is engaged in making certain ad- ditions to, and improvements in, its sewage treatment works. rigure 1 shows the relationship of the Wastewater Treatment Plant to the City of Richmond. Specifically, a new grit re- moval chamber now completed had to be connected to the plant’s main pumping station wtiich lifts all sewage into the plant. The grit removal charther was constructed at a cost of $1.3 million, including a 30 percent EPA grant. Photographs of the new Grit Facilities are shown in Figur 2 and 3. The City also has secondary treatment facilities under construc- tion which had to be connected to the present primary treat- ment plant at several locations. These secondary treatment facilities had also been approved for EPA grant participation. In addition, due to the severe flood in August, 1969, which inundated much of the treatment works, certain cleaning and 6 ------- ii 1 I / ‘\ i.___ _ _1 •’ --- 4 • 4)00 4.000 00O0 e .oe > ‘IA -4 1 1: 4.4, ._ 4 S 4. 4. Q , — - \ I. \ P .-.-- ! / ‘L I / ,1 •> -, (1 • 4 ‘ - !__—-—- - -- s:. 1 ‘% ‘- f : .4i/ ...t%’ - .. - . -l— ,’ - . - N- 4 s’ ; f /j/ 14. 4 01\ - \ S \ 4 • V. S. • SUPPLE NTAL Pt g STITIO !‘ “ 0 / I ... •. 0/ tfS £ S 4.5 •AsrfTco’TREA;Mcpdr FL 4 44 r 3 1 ., ‘4 Figure 1 General Location Ma t.. -- --- I • l S i I’ 57t / I I) 4 • S 4 b ( 7 ------- 4. ‘ I V. - LI - .‘. —+ - -.— —• - • r - — : - n / ‘ •-.- - -,- -- / • -• I Figure 2 Grit Removal Facilities View of New Grit Removal Facilities A ------- I. / ___._rt — / I t f i , iJ v L — - v \ _____ - __ _____ *1 / —---. Figure 3 Grit Peroval Facilities View of C’pen Channels of thi (rit Charnher .) . ‘ I 9 . I / / / 0 I . I I I I I /1 I I I I I I \I I ------- maintenance operations had to be performed. The grit chamber was projected to be completed by November 1, 1969, irtd it was planned to cut in the new facilities during a 110—day period beginning on that date. During this 110-day period, the normal dry weather sewage flow of approximately 30 million gallons per day would be chlorinated and discharged directly into the James River, thereby bypassing the plant. The Virginia Water Control Board had approved the proposed plan. Prior approval had also been obtained from the IJ.S. t:nvironrnetital I’rotection Agency in 1967 as part of its review of the City’s plans for the construction of the grit removal facility and the initiation of construction of the secondary treatment works. The Regional Director of the Federal Water Pollution Control Agency announced in September, 1969, that his Agency was opposed to the bypass. lie stated that he would initiate action to prohibit the City from bypassing sewage into the James River and would oppose further Federal funding of i ichrnond’s sewage treatment works if this were done. This new public policy prohibiting plant shutdown and bypassing provided a complete departure frcm the procedure previously approved by the Regulatory Agencies, and created a new problem for the City in that no provision had been made in the design for the connection of the new plant elements without a plant shutdown. The City accepted the new policy and directed its engineers, Greeley and Hansen, to dcve3 p schemes whereby the necessary work could be 10 ------- accomplished without bypassing sewage into the James River. 13. The System Figure 1 shows a general location map of the Richmond area. Figure 4 shows the major sewers entering the Waste- water Treatment Plant. rigure 5 shows the arrangement of the sewers and plant structures in the vicinity of the l ain Pumping Station prior to tl.e construction of the new g..it removal facilities. Figure 6 illustrateF a flow diagram to accomplish temporary bypassing of plant facilities during the construction of the connecting conduits for the new grit chambers. Two alter atjve methods were devised which would permit the connection of the new grit removal facilities without plant shutdown and without bypassing the raw sewage into the James River. 1. Alternate A comprised the installation of a 60-inch temporary bypass around the inlet conduit to the pumping station from the new diversion chamber to the inlet of the Main Pumping Station. A temporary bulkhead would be required to be in- stalled at the outlet of the south junction chamber. Temporary bulkheads were also required at the entrance to the Main Pumping Station. If this arrangement could be provided, the plant could be kept in operation, using the existing Main Pumping St .ion, while the new grit ::emova]. , 11 ------- / A 4 3h..d 17# &1réfiv .t4l( t, , ‘pmp ‘.f on (flo wkr .M4e D’ ’esf on k*& $LII,ICNlP ’\ 100 0 tOO 400 ‘I DIVISION £ 4 SEWER / ,i1PCITY ,1 DIVISION A LOCK kIVER CROSSING / / / DIVISION B CREEK INTERCEPTING / SEWER 0 DIVISION C HULL ST’FT N T(RCEPTING SEWE C, I,’ / /,/ I,. ) “I,, RICHMOND -PETLNSBURS .1 1t - J ti 1 0 ,ILt _t \ GORDON AVCNUL COWBIN(O • ZOO’ 12 ------- DIV ION Z PART I G000ES CREEK TERCEPTING SEWER 1. ii I Sludqe ôsds - ______ TURNPIKE ___-- —.------—-. FIGURE 4 TRIBUTARY INTERCEPTING YSTEM AND TREATMENT PLANT FACILITIES 13 S.drn,sn cAi. 7o vk ------- V 7, #7, / DIVISION - A LOCK RIVER CROSSING / ‘ - ‘ .‘GORDON AVENUE COMBINED SEWER CHLORIt ,- — DIVISION C L STREET INTERCEPTING SEWER 1/ 1 / ‘‘ / / 7 MAIN PU PI $TATION 1 0 ----7- “I “ ‘I’ 44 / / 14 ------- DIVISsON Z PART I LOWEft 000DES CREEK INTERCEPTING SEWER - - --——-----—-—----——----——— : 5 10N S T RUC T URET:::: SCREEN AND GRIT BUILDING umet P*!11 N STAT$O FIGURE 5 EXISTING CONDITIONS PRIOR TO CONSTRUCTION OF GRIT REMOVAL FACILITIES I- V p. V 2 w 0 p. CD ICALE $0 0 $0 100 Pt. - - - —J 1.G0’ ‘I 15 ------- FiGURE 6 FLOW DIAGRAM TEMPORARY BYPASSING WITH CHLORINATIOt 16 ------- chamber was connected to the plant. 2. Alternate B visualized the construction of a Supplemental Pumping Station. Sewage could be diverted to the Supplemental Pumping Station by reversing the flow through the 72-inch Lower Goodes Creek Intercepting Sewer which ultimately would carry sewage to a junction chamber adjacer.t to th. Main Pumping Station, and thereby divert the sewage around the main pumping station and force main to the treatment facilities. A temp- orary bulkhead would be required to be installed at the outlet of the south junction chamber and in the diversion chamber where the new supple- mental pumps would discharge. This would permit the new grit removal chamber to be connected and the cleaning and maintenance of the Main Pumping Station and force main to take place without the necessity of bypassing ur.treated seuage into the James River. A Supplemental Pumping Station could solve the immediate problem, and could be used in the future should an emergency arise requiring a shutdown of the Main Pumping Station and force main. The arrangement for a Supplemental Pumping Station and ancillary facilities is shown on Figure 7. 17 ------- 4 FIGURE 7 FLOW DIAGRAM ALT. B WITH SUPPLEMENTAL PUMPING STA. RIVER CROSSING LJAM(5 RIVER HULL STREET INTERCEPTING GORDON AVENUE COMBINED SEWER ‘p . ’, St e ‘s- GORDON AVENUE OVERFLOW REL F CHAMBER GORDON AVENUE COMBINED SEWER p 1 ., 4’ Sri, - LOWER G000ES CREEK INTERCEPTING SEWER MAIN PU*(JPING STATION GORDON AVENUE INTERCEPT ING CHAMBER GORDON AVENUE COMBINED SEWER- - T PIQ,?f PUMPING STATION 18 ------- C. Physical Requirements for Constructing Supplemental Pumping Station 1. Location of Supplemental Pumpinq Station The preferred location of the Supplemental Pumping Station on the Lower Goodes Creek Inter- cepting Sewer was such that the pumping station would not be excessively deep, the water levels in the wet well would not be too high so as to surcharge the sewers and cause overflow into the James River, and that relatively inexpensive modifications would be required to the existing structures. As shown on Figure 8, a suitable location for the Supplemental Pumping Station would be close to the existina 96-inch force main. Figure 9 shows the hydraulic profiles extending from the river crossing through the Lower Goodes Creek Intercepting Sewer, through the Supplemental Pumping Station and to the diversion structure. The profile also shows the con- nection from the south junction chamber through the new Grit Chamber to the Main Pumping Station. The flow from the pumping station would be discharged to the existing diversion chamber at which point pre— chlorination normally occurs. The location had to be such that at any’ time in the future should it become necessary to provide ad- ditional pumping capacity at the Main Pumping Station 19 ------- d V — —I • _ __— Z __ ;— ,--.— - ‘ J -- DVERS ON CHAP 3EN AND OYPASS L1? E I’ C.nsfr. cl.d tO r*rf F/ow tr m S vM .A,nc , Chombir ffvowgh I * I ? - t ‘& r,fv Uvi( 20 $CALI •0 0 $0 100 $‘ S. • a. 4 I F, 4’, / 7/’ C, p £:.. i5iJ:. to - : pa-’ / • r’ : _____J - / , ,-, -- SOV1N JUP CTIt Spctt l Ad inoo’ h?s omd u i tlfoaI ov Vl in ?1ra i ,, ivvi ro Me S/u/ion .4.. ?‘ d 4 /er ‘:‘, . Fish . f•ec/ 1, ‘- ‘- t•,’- ‘u ’ , 5eve 41.,” ‘ , , i, ,_ - ADDITIONAL WORK UND DIVISIONS X , XII AND XIII A. Main Pumping Stotios - moo’, /,Ce /,on /0 mel we/I S. Fa c• Main — c/coning ol 96-,Ach ore• main. 0 ------- SIWPLEMCNTA4. PUMPING STATION 1 R se g. d,,rled Lippimerdol Pvmpin9 Stof,o. ty r .e,swç . P2-mic* ‘Qvsfr se.’ea Iherefo’ permimn Me new Gril Chamber 1 01 conr,C 1d ood be dose a, Mo 4 rn Aimpsn Sloho , and force meet wiVhc.d b poua ,c w rso *d Se.09 10 M i .b’we River 1 w SLUICE GATE CHANGER I .‘ms go * s of Me flOw Gil fOciblies, Mo ,, Ptiwpw ,q Stohon end force mem IL o r necessofy inomiene e or eipons,o, ork - - - — — , - 7 (n FIGURE 8 WORK DONE UNDER ALTERNATE B TO AVOID BYPASSING - I DIVERSION CHAM3ER Modd d oeccirimodaf thscho,qs frøm S pbmeMolRarp$g loe’ Lend a convey f/ar ic lb. nt o, irsoimeni. I 5 Crie17I I 3rif &iii.v’.g-’ ‘ ¼ t ‘p PLAPITCOP IECTIOP4S FOM SECO WARY T ATt? HT FACILITr S During lbs rrg of Me &&rpplemonic( Pumping $,. ,, Ibe f / .o p nr i g were mode Fe Secon#.v; rr,o ir,.nl fec ’ mg aic’ido P/oaF sftyldo.rn end typos row uwoge 10 Me domes River (a) Conneclios bi/ween me mflv#sf cf.en,eF ond be Pr.hM ery Se iwenFolio. TonOs. (1) Ce nec/ian t1w•ei , fl affluent of lh P ,Mw4 Se#i ealefim Ten*so Seccndery Treolment Focs/n’ni. (ci Co ’nscF ,Os a, CAiffo// Chon,ber flo. 3.op•i W a ,ifo 7 i rs ! , , for Me pr ii , ,Or, - seconday Freolm af woOs. } ‘ I I I 4J’v’r; 15 f,a lion 8g .i I, II I Iii’r’i/’’ , .,“ 21 ------- eti • O vrf,o,. QsI,gf CA.,r ep ki l ii a — ‘ii _______—__________ 7 7 P7? - - ,-5ez // “arnter Ajenue Co ’r&ôir,ed.5ewer Z ) Lor e- Ge cdes C e1c /P #ercepteng 3e er- ________ (72PC.PSe*er) -J PROFILE FROM SOUTH JUNCTION CHAMB(R TO D:VERSION CHAMBER PROFILE FROM SOUTH JUNCTION CHAI(R TO MANS PU eSIG STATIOM 22 40 30 20 tO 44 ‘4 0 -w -20 - 40 30 20 (0 -4 ‘4 -I0 -20 -50 -40 ------- I, 0 SOuTs JJP4(TION MA JB(R TO D v(RSION CHAMB(R ‘00 rt ____ I..s0• FIGURE 9 HYDRAULIC PROFILES 5u cpIemenFa.’ Pu v p 9 ,5I’jI’, n I 40 30 20 I- 1 0 PROF ILE 23 ------- or make any repairs to equipment, all of which would require a shutdown, the Supplemental Pumping Station could be reactivated thereby permitting continuous operations without bypassing to the James River. 2. Gordon Avenue Overflow Relief Chamber Prior to the directive from the Federal Water Pollution Control Agency to accomplish the plant im- provements without bypassing, the Gordon Avenue Over- f low Relief Chamber was designed to take the flow from the Lower Goodes Creek Intercepting Sewer and also to serve as the point of chlorination of all the sewage bcing bypassed to the James River. with the construction of the Supplemental Pumping Station, this structure no longer serves any purpose. 3. Plant Connections for Secondary Treatment Facilities Connections of the secondary treatment facilities which were originally planned to be made during the 110 days of plant shutdown were redesigned, based on the new concept of the Federal Water Pollution Control Administration that no bypassing to the river is per- mitted. The three connections which were made while the plant was kept in operation are as follows: (a) Connection between the infiuent channel and the preliminary sedimentation tanks. 24 ------- (b) Connection between the effluent of the preliminary sedimentation tanks and the secondary treatment facilities. Cc) Connection at Outfall Chan’ber No. 3, which is part of the outfall system for the primary-secondary treatment works. 4. Bulkheading the Inlet to the Main PuTTiping Station Figure 10 shows the existing south junction chamber and the temporary bulkhead which must be installed in the 8—foot square outlet. This bulkhead must be in- stalled in this junction chair ber to divert the flow to the Supplemental Pumping Station. 3-foot by 4-foot sluice gate was installed on the bulkhead to permit its installation. B. The Design Problem The average tributary dry weather flow to the Wastewater Treatment Plant is approximate]y 30 mgd with minimum flows in the range of 15 to 17 mgd and maximum dry weather flows approximating 50 mgd. In the design of the Supplemental Pumping Station, it as planned to provide two or three pumping units with an installed capacity ranging between 90 and 100 mgd. Therefore, operating these units simultaneously, capacity would be available for approximately three times the average 25 ------- PLAN . h iit ,o:ke A: Sea ”, A C,Fy Lock P , ,Cr.si ’g (ôô o ACP) : “ jj P’:• A’S.’; - ;S SECTION A-A A _ ‘ , Co:’ P•,. - gCg 1 , 3 c: A.- 1 S.’ -I , R ,:.,.#.‘ ‘,.:,..r.i5eAs_ : ., 5 ,,,1 Q&i’i 59ev” ( .rde b’ o RCP, ’ (44 ’ ., , Pumping 5I 9,o,, -- - 26 ca t 4 5 5 .— ------- A SUGCEST(O SEOIJENCF OF ROU TO BE PERFORMED INSTILLATION OF BUUI4!AI STRUCTURE 1110(511 (00 0115 ( 0i 111110 00i ( 4 (0 the loitil Nil OlIN d or 410 lOcated at (I —i I • 55 001111114 44 (0101 01 100$ 4 1141 111 55 (.00101 1010s.i 101100 to Us 10101 Nil 01011 CI 1 ad ilcited II Ii -4 O ad (11 ‘I0 14 100 1lI40 WI 114 II riot it Ii . 2 I 3 144’ 015 15110111011 lul fl4 0001 111(5 55 (hadel 411 lit It list t Or$rily S I till 64101510 001 I I (I 4-0 4 (. r Its 00110510 lllactur. assadi quito 01.16 1 ph In 0 i p0 111141 Nited in 0 110. 410 I I I tidl6cl 011114 1 1 1 1c 140) 41 10 1ng It c1:sfuii ad fio.uog tIll lids 00001500 1101 0111111 llttr51Id 111 1 , 1 till SottisOl IN 4JI5 30 11 1 1 1,0 3 3 Of till bout of tile 11 sr 1111 the lace Of tile , 1tt.c.l *jl od lois limps ‘0 t, trio la, of the ClOth Nil listili ..J. plates W I IN 101112440 4ii 0 5 Jilts 1010 ChIld till tu1001k lu l l1 to ge. ’.o heist 611119110,114 ildIl till (4000001101000 I II. 001111 1511 Ti41ton 11* 1 105611 C I. 55 hIll 411111 IjIllol ottactur. 1 in fuii 1111010 dWIt lCl 411 ii 0107 101 till 14411114 IA 91 16 . 001100100 L r till 00112410 ItlactulS a1l t (0101114 it COISI.iI’f lull Ninth ‘114 1 6 1 4 , 1 4 K. 0010341 014 .eItiCli 101112441 1041 1141405 0110 tIll 1361 0! tIll 1111 itltii II I 00000100 tIll lljllIIOed II 11111111 I Ii Ill 1111010 Cl I I I ItadIl This 091101101 I jl I II I Carl? hi i COOrdinated 101 1151 it XIII ilOi Itiflg CableS in 0100, tO 01iOt ain 00 $1541015117 OSItiC lI 5511,410l 0110 51110430 Itr01turl IlilOtiliiotld 010001 16. gt thllS I till CI0 I liii 10gm 0000010 a C00t515ltip •uKlouing oressur. ai till 15,111410 ItfOOt ur s hid . ,ii 10 1.110110 Op Ins 51il 41 tIll 0105061 CaSio The u 00d Ito. liii 64410 0 11011 tO 1110 410 1.01(01117 1i 40 till Iluic. gIll PC I ? ,O1 it ii I SO 00006001 tO 1151001(1 lOli01lOl l I I —0 0 II 44 10 1 100..If 44 lOOt 50101 tIll Cliadol I10I 115011141 114 001121540 Otfactuli ii 140 15107 OCt 510 1010111 111111114001(111011 7 0110111 g114.01I 1f th i S 1,011061 coOls 410 011411 11111 0 1 503u 1 1 to 15 ,5 lii . 11,111010 11101 lull 05iIl ?d dliii still 01111011114 its 1 0 1 0 1 1 1 bhp 00111611 01011 1041000.114 0311.111 tIll? (i S suds 1500104 scsi I I I i 1 510 pr55u i 111000 141 tisIrd I 611514101 05t I 114 etltmchi 001121001 5001 114165$ 411 I I I 1061 CI 114 Clii I I 1110,000 10631 tIll 11&tUsdl ,t,act ,g. till t mn.ng 01511040 Di 1.. p015mfting II to rest 01 liii 111,0 ,1 of 1113 di I 0 1 (601116° hIll 01 n islot cdli. InSt all few 14111411.1 0041 111015 106110311 II .0 4 01115351101303 ltriKtu IO to ill lin l .011,611 1iu4 lt Op edJdltIIig 4 53 ( 1 If loisi jeclulig lot 161010 located wi Ills strut 91 1100 a? II .1 0 ad 4 6.00 01 103131 gcl03o loCated ai till neltiCli 5303 110065$ 00106601 to (Is south Nil Of SIt S s r at El -G 1 111 1001.11 oi lf c53tos 1(1031 SIll 115 014141 of 114 01110134. It01tull at Ci • 2 0 1 .30100 hIs gosrcd 110111 COols O iislali 1131,041151 0116141004101 5510 101410$ ItOd 41 till 640 a Id 0311 e llis a? 55 6fl 3l It El -0 IS ad boll It tO l .i 00111041 00 of Ills bil 10010 1 1 15 6t0 10 1151011 0610101 0003 10101000110100 551411710311 0? 1113 dt l 1113(511 4 (5 ‘is (ii 110$ 01111 lull10i l0I t71114 till 11116101 5303 to 11100111100 0141101 5101 Ti4 1 (bi 55 lii 155 dliii Ill 1011 0100 ii tc. tel 1C 000 lOcoted 11% IllS ,trh.,t 5s lio os at El . 4 iI 010 10110.60 0 111011 11,1111 lied C10i 111 11411 115100101.1 WaCO 00(6300 44 110 100$ 1010 111 Isles in IllS nort 4111 of till o (501111 11411 hIll 0300 041C 1 501,041 tIll 0015540 ot ’01turo 1010 Us 00j0641 1 WlCrltI ll ad5ad ’etEi-4 0 1141111 IluIc. ( 010 IitWI3lC 0t03 0001 (0100 aid till Worshtog 01031 staId (0(0000 ’ antis itS 6631 1151 00111.114 IndiCt 5415100 004111 It El . 12 -0 II C e o. Ills SiutcO 40(0 101065 10101 liii liii Ill till 005501 NtlIClWItiy 11141 (0 . .l ( 5 till 1101 tlrstJI 1115 OfOTlSt$I ! 010 1 1000 00$5 651011101 lOcated in till 0001 Nil 01 015 Ch 1 It IS I S O 11036100 tO II I’ 5500 Walolliotli, El 0 0 REKOVAL Of BULKHEAD STRUCTURE Cusliiallp (sue 111.11 folio. t ie ot s 00 II I iIiStSliIlINl P110 I t i0 iSiorel 0101, I 00io the IluiCi pIe SN 0,0, lull drop 0010011* 0041’ 1441 $101 4- 2 ‘e slush gale 00 1101.114 110Cr 11410 cast ir s gituig nra,.i st ( 0. .10 till 111511101 0101 TI 1(1011 414101 1061100 1(0101 tIe top 1( I 01 55 $tl itt . it C L .2 4 3 l his lids ad Its 0015500 #4151 044 ad 551111.14 5101131$ io lum .51011114 sill?? 41411$ 1111 lIp It t 0i alIip $110051114 It El 4 0 4 T,4lt00 55 porN 110151 chili vi 0411 141:01111 5341 struts 15114010 El . CWIldt 00000111 14111 CIlia 44 (141141 It diIO 1114 5ii5 30 lt.gtWIS l 01I itI 1111114 liii 5 Ti4stso (n 11iiy tIll 1100161 cable #1015,1 It S 01i5 $ini4IIj10 51 O dliii $ • 01144 1 I I 001.1140 50t till 001 11631 0011244 fiw 44 55 ta,of I —I, S 00’,, I I I 101011010 1(IaCtu Il *111,1 II I 011 1410 ? US 1511544 ii 3 3 55 ‘II I of Ire cis i This 111111 00 da I s Op a GaneluiIp , 0ordi 10160 t -e3 01 iSts 113,111 £00111 ‘ 5 (1100 (hateS f, Us 01111410 pids 11 111$ 10601400% Ci — I • DitcaIslec : tic 1100161 II 104 I Ibis. 15 00111430 101010015 essadIp mit of 114 01 , ,o 55 00i 41101 WIlts 1101100 at El — I S • ii till lulCIia 5001 010 li v 1s rhui14 list? 10410$ 11141 iJ14 0041 t isiip ii 11101 01 55 511411 at Ci 4 0 • , Ills 1101011 1(45,1 001100 tO till 141(11 c lii #11 tIll 435140 531St t40 41 510 th . riot at Cl • 2 0 FIGURE 10 SOUTH JUNCTION CHAMBER TEMPORARY BULKHEAD 27 ------- dry weather flow or twice the maximum dry weather flow. In addition,the outlet from each pump was designed with a siphon to prevent backf low from the point of discharge (existing diversion chamber) while the Main Pumping Station is in operation and the Supplemental Pumping Station is in a standby condition. In considering the above,it :as important to find equipr tent which was readily available and easily in- stalled. The various motive powers considered to drive the pumps were gas engines, diesel engines and electric motors. Sludge gas or natural gas were not available at the plant site during the time of design or construction. Therefore, gas engine drives were not considered. Diesel engines would be required to operate for extended periods of time at very slow speeds due to the minimum sewage flows which could be encountered at the pumping station. This type of operation, with economical high speed enqines, would require excessive maintenance to keep the injectors and the ports clean; thus the re- liability of the station would be reduced. Therefore, diesel engine drives were not used. Electric motors require a minimL.m amount of main- tenance with very good reliabilicy. In addition, re- liable power was available a short distance from the 28 ------- Supplemental Pumping Station. Therefore, variable speed electric motors were selected as the pump drives. The control of the pump speed is important so that the wet well will not rise to such a level that the sewers surcharge and discharge raw sewage into the James River. The depth of the pumping station was set so that the pumps would not operate dry at minimum ‘ peed when the level in the wet well was at a minimum. The bulkhead required to be installed in the existing south junction chamber presented a difficult problem. Although this was the best possible location for the bulkhead, no standard device would work, including in- flatable plugs, flat plates, stop logs, etc. Whatever type of bulkhead was to be used would rc quire instal- lation while the sewage was flowing through the existing structure. The structure, however, r:as not designed for the head which would be imposed on it with the in- stallation of a bulkhead. An involved and costly procedure was necessary to solve this problem. 29 ------- SECTION IV ThE CONSTRUCTION DESIGN A. Descripticn of the Pumping Station Design 1. Structural : The supplemental pumping station was to be designed as a simple economical structure con- sisting of a sheet steel piling cofferdam to be built around the existing 72-inch ID Lower Goodes Creek Intercepting Sewer and to act as the substructure for the pumping station. A dividing wall of sheet steel piling set on a short concrete wall divides the sub- structure into the wet well and the pump room in the dry well. The scheme of sheeting was with wales and cross-lot bracing located ir, such a manner as to form a structurally sound substructure and to permit reason- able location of the required equipment. The design was such that the shceting was to be driven to rock and then the concrete base placed and keyed into the rock. The loads for a structure as deep as this were very substantial necessitating very large walers and struts. After the structure was completed, the upper portion of the existing 72-inch reinforced concrete Lower Goodes Creek Intercepting Sewer pipe was removed, thus forming part of the wet well. Figures 11 and 12 illustrate the type of construction. 30 ------- Figures 13 to 23, inclusive, illustrate a general sequence of construction of the Supplemental Pumping Station and the modifications to the diversion structure. 2. Architectural : A superstructure of economical materials was constructed over the pump room in the dry well (See Figure 12), and constructed of a structural steel frame with insulated metal siding. The siding was made up of an exterior steel panel with a paint finish and an interior steel panel with a baked-on finish and 1-1/2 inch thick fiber glass insulation betwee i the panels. Hollow metal doors and frames and aluminum louvers were provided in the walls. The roof was constructed of four sections made up of 1-1/2 inch deep, formed steel decking. The outer two sections were spot welded to the steel roof framing and the inner two sections were bolted to the steel framework to provide for the removal of the pumping units. A vapor barrier, 1—1/2 inches of rigid insulation, a four—ply tar and gravel roofing was applied over the metal deck. A metal facia and water dam was installed around the perim- eter of the roof. Sheet metal downspouts were provided. Steel stairs were provided for access to the pump room floor. The wet well was not covered, but was protected with a railing around the entire perimeter. Aluminum stairs were provided in the wet well for access to the bar racks. 31 ------- I A PLAN AT EL+28.5 ------- - - - ____ I -- D’o Stiel 2 . t/’3133 4 FIGURE II PLAN AND SECTION 33 ------- f-,: ,j t. D,.q,, _.s Z Le *rr GcIvs CPv’. l. fr/er ep9ifl9 5 t*fP (F -, ’ ‘ P9 7V 4’ CP .5ew’r) — — - — - --. - — — - - - 4 - - — - I T - .51i, ’:e ‘ - — i— --—- — - 5fee’ S. f, - j - .JtC C* ••fJ Pe V i I T 1.’ E L L P P H- I POD r ’ c) ( rn c .df. • f $u:0’. K; --:9! SECT ION 34 ------- 4 (1 I.; L / = JP.;cs ---u EXISTING DIVERSION CHAMBER SC AL C 4 1 0 4 SF1. _________________________ I /4 • I•- C R-D. a---; 4.9•-4• v.,2 .5 - B-B FIGURE 12 SECTION 35 ------- ‘A, —a ‘ S— - S . . .; S S . .. S ‘S. S. —: S. i . . ’. • SS - . - S. . *.—S- *S . :e . ’. “S - 5- _ S S S — - • * S . . 5 5 S -.5.. ’ . . S. • S • 0% S 5 - SS. - •T •• ‘ ‘• 5’ -; -S .5 S - - • • • • -. ,. . S S - ••: flS 5I 1’bbS. t... . • . . - S• 5 • •S • .•• - . • - 5 4• . 5— •-• • -0 — • - 5 - 5 5 .tba,;; .j ‘ • - S • Figure 13 supplemental Pumpinçi Station, Grading for Site ------- “ ‘‘ / F. / . / / , / . . t._. — / iij ‘F / / / p - - - gi 4 ’ . .. .. . ‘‘ . “ “ I r • y _ ’c— — — — - — I I Ii \ - J I ____ Supplemental Pumping Station / Erecting Work m i Platform I ____________ ________ ------- r r Figure l5 Supplemental Pumping Station Driving Sheet Steel ?iling Coffcrdarn , for Substructure —I• • : I 1 r .1 •1 (T 1 r’1 I ------- - — -- . 5. N N. . . — - _______S5__ - - \, 0 , - S • _ 5__ - ‘V • •• • _ . 5__ • 5. f 4 t ‘ . .. -‘ r i ’ . ‘•• • - ‘ ? — 5 •_ ’_ _•_ .5 p — 5’ -. . 5-.— .-.- / ‘ t L , Figure 16 Supplemental Pumping Station Cross Lot Bracing of I’ .5 . It .: - • • • . ‘ - .4 ‘ • iP W I (45 . . 5 .• uit J • . . .. - . . . • -4 -. • I A f Th ; • -I 5 ’ 5— Ii ‘ ._f - ‘5--. 5 / ‘I, I. ‘ 5 - 5555 _ 5 . S.. ‘5- 5. ------- 0 .J Figure 17 Supplemental Pumping Statiofl Existing 72-Inch Lower GoodeS Creek ntcrceptiflg Sewer ------- : -. b- I - -J — f ,1’ -- r 1 ’. S1è MJ X -?( Figure 18 Supplemental Pumping Station Partially Coii pletcd ‘urnpir g Station, Discharge Piping and Diver3ion Structur 1 ’ - I - 4 - 1- -•. : . - .- S -- — • ? s L ‘ 4 ‘ I - r ------- jL: I r. ----- 1’_ Figure 19 :1 Supplemental Pumping Station _______ nterior View of Sewage Pumping Units I.- 1; \ \ / / : . I, 42 ------- \ /:‘ . __________________ - _ i _ - - Z(__ 1 - “ ‘ ,, - — r — t 4 — — — .4 ., — — . ,— # % ‘p — - .-, — — . ,- .—.- - T I Figure2O - - -. Supplemental Pumping Station Exterior View of Completed Pumping St ition and Oischarga Piping _____________ ------- -S..—— - — - - S_. . S . S [ - - 1 — __- ___ - — - ... .. i: -. 5 ____ ‘ ‘ — -- 4 - -S. :‘ - - — - - A - - -4 — .. . 1 .h a; — — T r I - - - -. ‘ - - : - - -- - - - - - - -. - - - - - • -. t - s-S.. i.b.. - -. - - . . . • -., - - •--. 4 . . i. ..-. —- -U -d • . 5 ’ i ..• .- - -. - - - S - - ‘ -a -- - - • • 4 - .. S .’_’•c_S ‘.•• ‘. - - .. _ 5• .•.• S • S ‘ - 5 5_Si - -S • - •• b - - - I . ___ — ‘ • III• ”4I• _ - - Supplemental Pumping Station • ‘•“ - ‘ - - Pumping Station Discharae Pipinci , . and Diversion Chamber i- ., -• - . - . - _-. ------- ‘J.t 1 V ç ’ / :.. : — a -•-,y - - -. - ‘-.1 - Figure 22 -: - • ‘-: Supplemental Pumping Station ’ .; -; View of Open Wet Well and Enclosed Pump Room ... .‘. ‘. • p••. - - I ------- ,? r- - r • _______ Figure 23 Diversion Structure Breaking Out Opcninas for Discharge Pipe and Ternpor ry Bulkhead 1’ /1 41 • r - - - J’; ‘2 - - - •1 • - ‘;: -, - I - k J I L ------- 3. Piping and Equipment : Two vertical nonclog raw sewage pumps with close-coupled wound motor drives, supported directly on the pump, were installed, Each pumping unit is capable of variable speed operation. Each unit is capable of puin?ing 50 mgd t maximum speed and 15 mgd at minimum speed. The pumps are provided with grease seals. The suction of each pump is a 42-inch steel pipe with a 42-inch sluicq gate at the end in the wet well for shutoff. A 36-inch steel discharge pipe with sleeve type couplings is provided from each pump forming a siphon at the top where it leaves the pump- i-q station and discharges down into the nearby existing diversion structure. Bar racks which may he cleaned manually are pro- vided in the wet well ahead of the suction sluice gates. Figure ] 2 illustrates the arrangement of the piping and equipment. The chlorination piping in the exist Lng diversion structure was modified to provide facilities for the addition of chlorine downstream of the pump discharges. Valving is provided in the new chlorine piping so that the chlorine may be applied at the entrance of the 96—inch force main wnen the Main Pumping Station is in operation, or downstream of the Supplemental 47 ------- Pumping Station pump discharges when the Supplemental Pumping Station is in operation. Metering equipment include meters and registers for each pump suction and discharge pressure and the pump speed. With this information and the head-caoacity curves for each pump, the approximate pumping rate for each pump may be determined. The meters and registers are located on an instrument panel inside the building at the ground floor level. Provision for manual or automatic control of the pumps is provided in the pump control system. The variable speed control system for both pumping units consists of autow tic speed ontrol arranged to sense the liquid level in the wet well. The wet well level as sensed by the liquid level control adjusts the liquid rheostat connected in the secondary of the wound rotor motor for pump speed control. External heat exchangers are provided, for Lhe liquid rheostat, consisting f a radiator and fan mounted outside the pumping station structure. The speed control is designed to start the lead pump, naintain a constant wet well level until the lead pump is at maximum speed then start the second pump and both pumps then operate at reduced speed maintaining a pre-set wet wel]. level. An alarm system includes an annunciator on the pump control center and an outside horn and a flashing 48 ------- light to give an alarm in the event of equipment failure. 4. Electrical System : The electrical system for the Supplemental Pumping Station consists of a sub- station near the pumping station which is supplied from a 13.2 kv VEPCO overhead line and supplies power to the Supplemental Pumping Station at 2,400 volts. An auxiliary station transformer located outside the pumping station structure is provided to supply station pcwer at 480/277 volts for heating, ventilating, lighting and other auxiliaries. The switch gear, primary control and secondary controls are mounted on a concrete slab at ground floor level inside the superstructure of the pumping station. Figure 24 shows a simple one—line diagram for the station’s electrical arrangement. i. Heating and Ventilating : An exhaust fan with a capacity of 1,000 cfm mounted on the roof provides continuous ventilation of the Pump Room and dry well. The roof exhaust fan’s duct carries down into the Pump Room or dry well to just above the pump suction ccnnection providing an exhaust of about 6 char ’ies per hour for an effective operating height of 10 feet. A 3-foot by 1-foot 4—inch high manually operated 49 ------- 5. t e — — • r — 8 ,k (m et’,on j YE o f € • Lçfl/ ,.,,g 4:,rste, “ —__- 4 t O no’ng’—— r——I .Z’(V1’ e’ (a po d) rviCC - Pl)ñ I’ i - 4—- (1, n(,Q - 1 - —-— - -- - - - —— —- —- I . — I!?’ p;-! — .—. - - ;/- •) • A / A 2t 4 : x - L__ Spc-es — A 1’) - - To8fz ) • ! ‘ - -- + L i -- 2- ” •-- . - ?O V -ed M 3 (2 ‘(3 ci ONE LINE DIAGRAM 240(N. 3P’-i 60Hz Uni - fl,’e s - — 41 v’ (&- “II• C ) - 3115- ——------- -.-- - - - To .‘SO 2)? & _;; Th t.f -s- — o. ’rn; -—— --—-—----- — 7 An, . ‘ co’ r / 7 / $ V’ CI’ Po,e/ -- 3 $clHz. J-333 nYA /3. ?Z 4% -V Pjt ptv I ______ 50 ------- p7- 1 p7-. - - —4--—--.--’—- —— -t - - 3O 5Q(. _ _. — — , , — t _ U’ / / ‘cI 5w ,ch “2- L ?J P / I - ’ L_.f12_J L _. Nel No? Pi5 — —-—----- Q /d U ’Oi5 — ---———— C 7 _L. - :1 (uP - “---I A’ urnp Dc” , O ,r ’or • f; .:-‘. • ‘ ‘.!- .Yi’ , . “. t’ ’ar • , “ ‘c! &‘;c “ s - &rc - 5-Mci / ;4 ‘.., . t — P1 .‘,i (:3 :—1, - 5c- ’e’ . O.f ’ ’d I c ,jr,’—er .“(. r. -o’ t -:- .. ) : ‘ ‘ “ -: -—---4 T tc,? ’o ’ 1 F ,ir’o. ’ .. fl ci:. L - rta’ -’e F x ’ 5*c D Dc’ zt Oxc r !?:i e C. ,,ç o b ,. :e- ‘. .‘ -‘;‘ 5c ! , i $ ,, FIGURE 24 SUPPLEMENTAL PUMPING STATION ELECTRICAL-ONE LINE DIAGRAM 51 ------- - - louver is provided in the superstructure wall to provide for the continuous air intake. Another exhaust fan with a capacity of 6,000 cfm is mounted in the Pump Room about 10 feet above tne lower floor. This fan is thermostatically con- trolled to provide heat removal and discharges throuc,h a gooseneck on the roof of the superstructure. Inter- locked with this exhaust fan is a 4-foot y 8—foot high motor—operated louver located in the super- structure wall, which provides the intake to the superstructure of the required amount of outside air. Three 20-kw thermostatically controlled electric unit heaters are provic ed for heating the Pump Room and superstructure. B. Description of the ‘z3ulkhead ’ The installation of the bulkhead in the existing South Junction Chamber required design because of the unusual structural aspects. The walls of the existing South Junction Chamber were not designed structurally to restrain the greater loads imposed on them by the increase in internal hydrostatic pressure; an 8-foot by 8-fot opening in the south wall lGading to the Main Pumping Station was to be bulkheaded. The entire structure, including the north (back) wall and the side walls, was engaged,structurally, to carry the loads 52 ------- imposed by the severe hydraulic conditions after the installation of a bulkhead. The bulkhead had to be installed while the sewage was flowing through the junction chamber. The bulkhead was prefabricated of welded steel plates, beams and angles with a 3-fcot by 4-foot sluice gate mounted at the center near the bottom and rubber seals on both sides and the bottom. The bottom of the 8-foot by 8-foot opening was flat with no sill for bottom support of the bulkhead. It was necessary to design the bulkhead for very small deflections to prevent leakage. The bulkhead was designed by a stiffness method using an IBN 360 computer. A program was developed which deter- mined all reactions, shears and moments of all points considering the effects of the various deflections. The bulkhead was structurally tied to the back wall with the use of tie rods and an anchor beam placed outside of the structure against the back wall. This permitted the hydraulic loads imposed on the bulkhead to be trans- mitted into the entire structure, even utilizing the side walls, and preventing the south wall from receiving the bulkhead loads for which it was not designed. Figure 10 illustrates the bulkhead as installed. It was necessary to remove a portion of the top of the concrete structure to permit the installation of the bulkhead. 53 ------- Figures 25 to 30, inclusive, illustrate the installation and removal of the temporary prefabricated bulkhead placed in the inside south face of the special structure to divert raw sewage to the Supplemental Pumping Station thile making con- nections to the new Grit Removal Facilities. C. Method of Accomplishment and Costs To obtain pumping equipment as quickly as possible, the pumping - uipw nt was purchased with a separate contract prior to thr ..esign of the structure.. To obtain the most readily available equipment, the .iecifications permitted the furnishing of new or reconditioned pumping units consisting of two or three vertical or horizontal electric motor driven units. The type of controls permitted were squirrel-cage motors with adjustable speed magnetic drives, wound rotor motors with liquid rheostat variable speed controls in the secondaries of the motors. Two bid proposals were received for the above pumping equipment and controls. Both proposals were for new equipment. One pro- posal offered two vertical wound rotor motor drive units each with a maximum capacity of 50 mgd; the other proposal offered three horizontal units with wound rotor motor drives each having a maximum capacity of 30 mgd. Each proposal in- cluded liquid rheostat variable speed controls. Although the bid prices of the three horizontal unit proposal was slightly less than that offered with the two unit vertical proposal, the two vertical units were selected 54 ------- I 1I U’ Is . —.. - .r .,(_•. — S Figure 25 South Junction Chaiiibcr Transporting Prefabricated Special Bulkhead to Sitc -ì I I r AJ . E. Is - r If —.- ------- r * I ‘._ J L I — I i L 1 .. I I _______ I t Figure 2b I Lowe ring Dulkhea into piaceL t _ L i ___________ ii _ 1 L_i ------- 411• •: “ - 4 4 -! .4. I .. I. 4i • 1 f - ¶• .. • ‘ ‘• I ’.” . p N U, -4 1 - A . . ,,I- • 1 Figure 27 ‘I. S South Junction Chamber - South Face of Chairber . - Showing Bulkhead in Place - . ------- J ‘1 . .. 4 J . ’ •.. . . UV ‘1’ : . tq’ “ — ‘ ‘ •‘ I . ,. . - e • 11 ‘ _ ; ! 4’ L ?;, .; V 44 7 L .1 • .-. I - . . -- .- . •4 . - -,, .‘V Ø I - - , •1’•’ . ,. - . - .i! 7 4 4 . 1 1 i - It .-. . . I / - -. — I r 4’ / .- . i • • : , , , - - ‘- ; . ‘ , .4 ‘L.è i ... •- - .:• d • - . -#•_ • - ‘‘v -1 . .’. - I ‘ . ,: b.-. . / ¼ .$ - A. — . - .. _ ,1— • - -. • ._‘_5_ ,. -. ._, , . —, V •‘ , .. . .. 6 ., - ‘7/ - 4 . •— ‘ “ ., !‘, . - .. . - -. :.: • : r -’ - . . - - • . -. . .rn ,1 ‘ • - .- . __c - , -S • . - • -.5. •• •••_•• ‘ . . .: ‘. .. .- . • • • .• . . _ ‘• — • Z • .• -5 - . ____ .5 , ,• . •, • • _I .h• 5 . Figure 4 -. - South Junction Chamber Preparation for ‘ .,‘ .ç ) ‘ e ’ Constructio!L .pf New Junction U’ ------- N •_\ H -se. 4 aa 4 ’ gure l9 .rs I $ r South Junction Chanter t ,‘. _— ‘ -- — - • Placing Reinforcing Steel for Condui* C’ - - ‘ - --- Between New Junction Chamber - - a - ’ and Inlet Chainbe r tIJ • . -•.•--.•— , —.-- —-‘- -—- -- -- —“ - ra ‘ H ‘. ; ,. . ‘* e rM r . I — , - •, [ , •• “ I t O . 1 k ‘N ’ ) ‘ 1 I I’ - 4’ - - ‘ 1’ - : “ 7 ’ 4” ‘ . 1 ------- I •1 ii ‘ ‘ : I J i Jr ,‘ . bq .i’• •. 1 ç ,L - - Lr ! - ____ — •.-.-‘• - —•-,, South Junction Chamber Removal of Prefabricated Bu1kheadL 60 ------- because a much smaller pumping station structure could be built and the savings in cost of the smaller structure would more than offset the small additional cost of the equipment. The total amount of the bid for the two vertical pumping units and all specified controls was $149,900.00. D. Design Time The design of the Supplemental Pumping Station and Appurtenances began in January, 1970. Bidding documents for the pumping equipment and controls were prepared and bids were received on May 14, 1970. The Contract was awarded on June 23, 1970, and the design of the Supple- mental Pumping Station was begun to accommodate the specific equipment to be provided. On July 20, 1970, the preliminary Plans were reviewed with representatives of the Federal Water Quality Administration, the Virginia State Health Department and the Virginia State Water Control Board. The design con- cept was approved at that meeting, and at the end of July, 1970, the FWQA approved the Plans for the Supplemental Pumping Station. All design work was completed and negotiations with Contractors were begun for the accomplishment of the Contract work. Contracts and change orders to existing contracts were signed in December, 1970, and on—site construction was begun February 19, 1971. 61 ------- SECTION V ‘ IIIE CONcTRUCTION The design of the facilities necessary to avoid bypassing was initiated following acceptance of the Grant Offer on January 26, 1970. The work was to be developed in two parts; pumping equipment and the Supplemental Pumping Station structure itself. On April 21, 1970, the Federal Wacer Quality Adninistration approved the Plans and specifications for the pumping equipment. The contract was advertised on April 24, 1970, with bids to be received on May 14, 1970. The award of the contract was approved by t e FWQA and the contract was subsequently executed on June 24, 1970. Pump tests were witnes3ed on January 25 and 26, 1971. All equipment under the contract was received by the end of May, 1971. The preliminary design of the “Supplemental P nping Station - Structures” and the design of the temporary bulkhead for the existing junction chamber were substantially complete by June ii, 1970. A meeting was helu on July 20, 1970, to review the cost estimates for the pumping station and bulkhead. Present at this meeting were representatiVes of the Federal Water Quality Administration, the State Health D2partnent, the State Water Control Board and the consuita its of the City of Richniond. At the meeting, the plans for the pumping station structures were submitted for approval. As a result of 62 ------- that meeting, it was agreed to redesign the electrical service to realize a savings of approximately $7,000 and to eliminate the Dahl flow tubes. These changes were to be incorporated in a change order to the work presently underway at the Wastewater Treatment Plant. The Federal Water Quality Administration notified the City on July 29, 1970, that they approved the design of the Supplemental Pumping Station - Structures, incorporating the changes discussed in the July 20, 1970 meeting. Actual construction of the Supplemental Pumping Station — Structures was begun on February 19, 1971, with the driving of sheet piling completed on April 7, 1971. Excavation ‘as essentially complete by September 4, and concrete work was accomplished between September 10 and November 23, 1971. The assembly of the superstructure, electrical work and the installation of equipment and coritros were all undertakEn during th period from November 23, 1971 to February 1, 1972. In addition to the two main parts of this project, (pumping equipment and pumping station structure) numerous smalJer projects were necessary to allow the Supplemental Pumping Station to function properly. These various projects were achieved through change orders and various contracts. The various Contract Divisions for work at the Wastewater Treatment Plant, the change orders, 63 ------- separate contracts, dates of issue and a brief description of the work covered by each change order or contract are summarized below: Change Order Contract Number Date Description Div. x 7 4-17—70 For furnishing all labor, material and equipment for the construction of the following items (see projosal by Contractor dated April 13, 1970, and proposed Construction procedure): 1. Outfall Chamber No. 3, as illustrated on Supplementary Sheets 4 to 6, inclusive revised !‘ arch 19, 1S70. 2. New Diversion Chamber and Sewer as illustrated on Supplementary Sheets 1 and 2, dated October, 1968. Div. X 9 10-10—70 Change Order No. 9, “Modi- fication of Junction at River Crossing” per letter of January 9, 1970, from the City Manager addressed to the State water Control Board, including Attachment “A”. Part D of Attachment “A”, Modification of Junction at River Crossing — Construction Grant. (See English Construction Company, Inc. proposal dated September 25, 1970, and Plan Sheets Nos. 1, 2 nd 3 with Specifications. 64 ------- Change Order Contract Number Date Description Divs. XII and XIII 2 9—2—70 For furnishing all labor, materials and equipment for construction of a sluice gate chamber in the existing raw sewage conduit adjacent to the e:cisting prixrary tanks (See Sipplemental Sheet No. 2 and English Construction Company proposal). Divs. XII and XIII 3 10—10—70 Research and Development on a Supplemental Pumping Station and on the Modi- fication of Junction at River Crossing p r letter of January 9, 1970, fi ,m the City Manager addressed to the State Water Control Board including Attachment “A” Part A of Attachment “A” - Pumping Facilities Research and Development Grant. (See Part A of English Construction Company, Inc. proposal dated September 23, 1970 and Plan Sheets Nos. 1 through 13, with Specifications). Part D of Attachment “A” — Modification of Junction at River Crossing — ? search and Development Grant (See English Construction Company Inc. proposal dated September 23, 1970, and Plan Sheets Nos. 1, 2 and 3 with Specifications). 65 ------- Change Order Contract Number Date Description Divs. XII and XIII 4 10—10—70 Construction of a Supplemental Pumping Station and Modifications of Diversion Structure per letter of January 9, 1970 from the City Manager addressed to the State Water Control Board including Attachment “A”. Part A of Attachment “7 ”, Pumping Facilities - Construction Grant. (See Part A of English Construc- tion Company, Inc. proposal dated September 23, 1970 and Plan Sheets Nos. 1 through 13 with Specifica- tions). Part B of Attachment “A”, Modification of Diversion Chamber — Construction Grant. (See Part B of English Construction Company, Inc. proposal dated September 23, 1970 and Plan Sheets Nos. 1 through 13). Divs. XII and XIII 5 10-21-70 For furnishing materials and labor for construction of and installation of a steel bulkhead in the ef f— luent channel of the existing Preliminary Sedimentation Tanks per Supplemental Sheet No. 3 and the English Construction Company proposal of October 19, 1970. This work is to be accomplished with the existing plant in operation. 66 ------- Change Order Contract Number Date Description Supplemental 6—24-70 Furnishing and delivering Pumping complete, the new or Station - reconditioned used pumping Furnishing equipment consisting of Pumping two or three vertical or Equipment horizontal, electric motor— driven pumping units and all equipment to provide a complete pump control system. Supplemental 5—19-71 For furnishing a ground Pumping detection alarm system, Station — fused switch and additional Furnishing motor starters, and the Pumping deletion of the window—type Equipment current transformers and ground fault relays. No extension of time is required. Electrical 3—22-71 Furnishing and installing Substation the transformers, poles, fence, and related equipment to completely construct the substation. The existing diversion structure was altered during the period September through November, 1971, with the installation of a wooden bulkhead. Work on the connection of the grit removal facilities continued until the Wastewater Treatment Plant was flooded in June, 1972. At the time of that flood, work was essen- tially : p1etc on construction required for connection of the grit channels. Following the emergency repair work was begun on the Grit RE:iioval Facilities. This period OC r pair required approximately three months. By August, 6 ------- 1972, it was anticipated that connections could be made and the Supplemental Pumping Station could be shut down about the beginning of October. The flood in the early part of October forced the station out of service frcm October 6 through October 9, 1972. Once again, the grit channels were flooded and repairs were completed by the beginning of December. Attempts to reactivate the Main Pumping Station were hampered by damage caused by the flooding and idleness, but undetected during repair work. Complete repair work on the Supplemental Pumping Station made necessary by the June, 1972 flood could not be acccinplished until the Main Pumping Station was reactivated. The floods of June and October, 1972, caused a delay of approximately seven months in the corrpletion of the supplemental pumping operations. The flood of 1 ugust, 1969, while not occuring during the construction of the Supplemental Pumping Station and appurtenances did contribut’ to delays in the construction schedule for the Grit Removal Facilities. The irtended period of plant shutdown had to be delayed from September 15, 1969, unt5l November 1, 1969. Before the plant shutdown was to begin, howEver, bypassing was ruled out and circumstances led to the filing of the grant application on November 14, 1969. 68 ------- Initiating Construction The connection bet.;een the South Junction Chamber and the Main Pumping Station was closed by the installation of the specially designed bulkhead. Modifications to the South Junction Chamber and preparatory work for the instal- lation of the temporary bulkhead was begun on October 12, 1971, and was completed by January 31, 1972. At that time art attempt was made to install the bulkhead in accordance with the suggested procedure outlined in Figure 8. The attempt to install the temporary bulkhead wa unsuccessful because the Contractor failed to ascertain a dimension in the field as stipulated in the design Plans. The bulk- head was removed, tered and reinstalled on February 1, 1972. Final adjustments on equipment and controls in the SupplerLental Pumpinq Stat.On were made between February 2 and February 9, 1972, when the sluice gate was closed on the temporary bulkhead in the south Junction Chamber arid the Supplemental Pumping Station went into full operation. The temporary bulkhead sealed the opening excellently, allcwing very littic leakage. Termination of C’MmtructiOfl In December, 1972, the sluice gate in the temporary bulkhead was opened at various time. to test the operation of the grit channe s and the Main Pumping Station. These tests were run on an interr. ittent basis until January 3, 69 ------- 1973. By FebrUarY 14, 1973, preparationS were being made to restore the stiucture and equipment to preflood conditions. The chronology of principal events bearing on the development and .Logress of the work associated with the Supplemental Pumping Station is shown graphically on Figure 31- The construction costs are summarized as follows: DivS. XII and XIII Electrical Subtotal - Outfall Chamber No. 3 and New Diversion Chamber 81,467.00 Modification of South Junction Chamber __________ Sluice Gate Chamber at Primary Tanks Mech. & elec. work P.S. & Diver. Structure Bulk. in Primary Tanks Substation (original Contract) Structures and Appurtenances Cost 24,900.00 $106,367 .00 12,800.00 145,100.00 317,400.00 7,495.00 $482,795.00 10,470.00 $599,632.00 Supplemental Pumping Station, rurnishing (original Pumping Equipme’ t Contract) Electrical controls Subtotal — Furnishing Pumping Equipment Cost Total Construction Cost 149,900.00 2,139.30 $152,039.30 $751,671.30 Contract Div. X Co St 70 ------- The total cost for pumping equipNeflt is $152,039.30 and the cost of the Supplemental Pumping Station and appurtenant structures is $599,632.00, including thn cost of the Virginia Electric and Power Company work on the electrical substation. The total of all construction costs associated with the Supplertental Pumping Station and Appurtenances is $751,671.30. Sumxnar The total cost of the Supplemental Pumping Station and appurtenant work has been defrayed in part by Research and Development Grants and in part by local funds. The allocation of costs is as follows: Const. R & D Grant Grant Total Encjir.eeriflg 36,095.34 1,576.61 37,671.95 ConstructiOn 454,532.00 297,139.30 751,671.30 Operation — 99,734.93 99,734.93 Administration — 6,47 .7 8 6,479.78 Total $490,627.34 $404,930.62 $895,557.96 71 ------- Review of Shop Drawings - Pumpmg Equipment I 1t IU, I ATSTO 14 Construction - Oivlsion I Flood Delays - Division I — — I Restudy U N2 Administrative Review RE R.tl.sign 1 D!J F A1ML Ltk l ?O A ii S —. -.‘-.-.t * -Is 1 1• ;_• t I__ iiiiiri1ir. -4- $ — T ‘I I 4 — — ——— — .h - -J__ !]‘ _‘L_!!._ Construction — Supplamental Pumping Station Operation - Supplemental Pumping_Station 1 IH1 Ii : i ,. J -: 1 , ‘ ‘ \ I I 1 t 1 . .H i i I • k4 I ; — i i 1 il * ¶ ‘ ‘I t , ‘ : 1 L ’ \1 \ \ $ ‘4 I ti ’L Ut k t’it I I’ i 1Ih 72 ------- S97 1 972 973 o N ________ 4• - 4 —- I- 4 II -, f -1 - 4 —--t---4 -4 •-• --.-- •--- -. -. ,•.-. •..--.- -. i . . - . . . “. . 4 - — ..-. -, . . --.—. . .--.- .... . —.- -—..--—— --- :: :: :1 I , I 1 I t C ( ‘ ‘ I l 1 I I i i - I i . ‘ i ( t FIGURE 31 CHRONOLOGY 73 ------- SECTION VI THE OPERATIONS A. Operation Phase The Supplemental Pumping Station was tested on February 3, 1972, for a period of 7 hours. On February 9, 1972, the station began full-time operation at 9:10 A.M. The first full day of operation was February 10, 1972, and the station continued to operate until the flood caused a shutdown at 12:00 P.M. on June 22, 1972. The station was restarted at 11:30 P.M. on July 3, 1972. Another flood required the station to be shut down from 6:00 A.M. October 6, 1972, to approximately 8:00 P.M. October 9, 1972. The Suppleriental Pumpirg Station was shut down on Janu iry 21, 1973, and the Main Pumping Station was restored to service. At the time of the initial start—up of the Supplemental Pumping Station, it was anticipated that the connection to the New Grit ChaNber could be made during the month of June, 1972. The flood of June, 1972, damaged motors, controls and othe’ equipment in the Supplemental Pumping Station and the Lransformers at the VEPCO substation. The two 500-horse- power motors were removed with a crane through a hole cut in the roof of the station and sent to the General Electric service facility in Richmond. One of the motors was returned and remounted on July 3, 1972. This installation was used to pump and chlorinate a portion of the sewage flow. The 74 ------- second motor was returned and installed on July 4. The station was operated rianually, since the automatic controls were still damaged. The transformers in the VEPCO substation were also repaired by the local General Electric service facility. By August, 1972, repairs on flood damage to the new grit tanks had progressed sufficiently to expect that con- nection could be made at the beginning of October. The flood in October or.ce again flooded the grit tanks and caused damage. The Supplemental Pumping Station had been stripped of readily removable equipment and required only that it be pumped out and w ’shed down before the electrical equipment could be reinstalled. Repairs to the grit tanks were essentially completed in November and connection was scheduled for December. During Deceivber, 1972, and January, 1973, repeated atterL tr were made to reac tivate the Main Pumping Station with new grit tanks on line. Operational problems were a . Luted to the flooding of equipment and to the long period which the equipment remained idle. The problems werL finally resolved and the Supplemental Pumping Station was secured on January 21, 1973. B. Operation and Maintonance Staff The staff required for the operation and maintenance of the Supp emental Pumping Station has been drawn fron 75 ------- the personnel regularly employed at thu Wastewater Treatment Plant. Overall daily supervision was provided by the plant superintendent and this required approximately ten percent of his tji; e. Five shift supervisors provided immediate supervision of operating personnel and this required ten percent of their total time. The total of eight shift operators spent approximately 100 per cent of their time attending the equipment. These eight operators comprised four gas engine operators and four gas engine attendants. These men were normally employed in the Main Pumping Station and are familiar with large pumping equipment and drives. Control System The Supplemental Pumping Station operated in response to an increase or decrease in the wet well level. The primary control sensor for automatic pump operation was an air bubbler tube suspended in the wet well. The pressure changes on the bubbler system caused by fluctuations in the sewage level in the wet well were converted to an electric signal which controlled pump motor speed and pumping sequence. The “start” and “Stop” sequence of the infinitely variable speed pump motors could be 3elected and the wet well eleva- tion at which the pumps start and stop was adjustable. The approximate elevations were as follows: Start Stop Lead pump El.-5.5 El.-5.6 Second pump El.-4.75 El.-4.85 76 ------- The sequence of operation used with this control system is described as follows: 1. Jhen the wet well evel reaches the “start’ t elevation for the “lead” pump, the motor shall start at minimum speed. 2. The “lead” t’ it shall increase in speed as the wet well level te.ids to rise. It shall increase in speed to the maximum pump speed maintaining a constant level. 3. When tl “lead” unit has reached its maxir um speed and the wet well level has risen to the corresponding level for the “start” of the second unit, the “second” pumping unit shall r ,tart. The “lead” unit arid “second” unit shall adjust to the same speed. 4. The “lead” unit and “second” unit shall increase in speed as the wet well level tends to rise. They shall increase in speed to their maximum pump speed with the rising level. 5. ? the wet well level tends to drop, the “lead” unit and “second” unit shall decrease in speed until their total capacity is less than the capacity of the “lead” unit running at maximum speed. The “lead” unit shall immediately in— crease in speed so its capacity equals the total before the “second” unit stopped. 77 ------- 6. As the wet well level tends to drop, the “lead” unit shall decrease in speed to maintain a con- stant level until its capacit)’ is that of the unit running at minimum speed. At this time the “lead” unit shall stop. The characteristic curves of the two pumping units installed in t!ie Supplemental Pumping Station are presented as Figure 32. c. Data Collected Data collected on a regular basis during operation of the Supplertental Pumping Station include: James River water quality data, pumping unit suction and discharge pressure, uinping unit rotational speed, operating logs, a di.ary maintained by the resident engineer at the treat- ment plant, and the treatment plant operating records. The river water qualit.y data is based on weekly samples taken by the Richmond Department of Public Utilities at six stations on the James River. Samples are analyzed for ter.Dorature, pH, dissolved oxygen, 5-day mOD, total bacteria and coliforms. Pumping unit suction and discharge pressure and rota— tiondl speed were recorded on 24—hour recording charts. Each unit has, therefore, three separate operational charts for each 24-hour period. 7n ------- - .., . . .C- .fl •. -ta. . r,- .. - . -. -. - -. . — — -. - — .• — - Operating logs were maintained by the treatment plant personnel on a 24—hour basis. The information regularly recorded on these logs was: Wet well level Pump hour meters Watt hour meters Suction and discharge pressure In addition, operator’s comments were recorded. The resident engineer’s diary provides a record of con- struction and oper-ition sequences and describes activities and problems encountered during the project. D. r valuation of Data The available data on pump speed, st.ction and discharge head and the pump characteristic curves can be used to estimate the axrount of sewage handled by the Supplemental Pumoing Station. The developirent of the complete pumping record from their data would involve extensive data logging and computations. The treatment plant records, theretore, have been studied to establish an alternate record of pumpage. The treatment plant flow record is obtained from an effluent weir. Comparison of the flow data from the two sources for selected periods of operation indicate good correlation. The flow data reported herein, therefore, is that obtained from the effluent weir at the treatment plant. An estimated curve showing comparison of the two sources of flow data is included as Figure 33. 79 ------- I- taJ I d •-- 60 z a I d 5O C., z .40 -J d 0 I- 20 80 ------- - - URE 32 ES 81 ------- Pdoto: Supplomentol Pumping Station flow vaIue were computod from chart recordo. 80 60 Ii : 00T 20 40 80 100 120 SUPPLEMENTAL PUMPiNG STATION FLOW — MCD FIGURE 5 CAUBRATION CURVE PLANT EFFLUENT WE R VS SUPF P. STA. FLOW 82 ------- Complete flow records are available for the period beginning with the start-up of the Supplemental Pumping Station and ending with the facilities shutdown caused by flooding. A record of daily flow averages for that period is presented on Figure 34. During this period of record, the maximum daily average flow was 61.3 mgd on February 20, 1972. The minimum daily average flow of 36.6 ingd was handled on May 3, 1972. The estimated average dai .j flow handled by the Supplemental Pumping Station during the period when the weir was out of service was 42.6 mgd, based on the previous 418 days of plant operation. The monthly averages of flow received and pumped for the period covering the operation of the Suppler ental Pumping Station and nine r onths previous are shown in Table 1. These figures are presented to indicate the periods for which flows had to be estimated. The total flow pumped prior to after the floods is 13,125 mg. The estimated aiqount bypassed due to the floods is 680 mg, which is approximately 4.5 percent of the total flow tributary to the treatment plant during the project. 83 ------- 80 70 C) 0 I- z w -J Ii U i 30 I.- z d -J a. 20 I0 0 IIillIttlIItIIIllIlIIIIIttI 1111111111111111111111111111 0 0 0 01 C) (%J - cg Fsbruary March 972 MONTH 84 ------- I I III I 1 I I II 1 [ 1 1 1 111 11 II I i I I I 1 1 1 1 0 c,J April IiiiIiIII IIiIIi IIIIIIIiIIIiI1IlI11Ii_1_ I__I _ I_ I May 972 0 oJ MO NT H ol In— 0 01 June FIGURE 34 WASTEWATER TREATMENT PLANT EFFLUENT PLANT FLOW ) 0 85 ------- TABLE 1 Supplemental P. 5. Flood — SP.S. out Flood — S.P.S. out Through January 3, RICHMOND, VIRGINIA MONTHLY FLOW SUMMARY OF FLOW MONTH DAYS MCD NUMBER AVERAGE MAIN P.s. sup.r.s. FLOW DIFFERENCE MC MC FLOW MC f Tho 1,380 1,170 1,260 1,220 1,450 1,170 1,090 1,230 390 TOTAL FLOW MC 1971. 1 ay ( June 31 30 41.183 46.132 1,280 1,380 PRIOR TO C July 31 37.714 1,170 OPERATION C Aug. C sept. ( Oct. ( Nov. C Dec. 31 30 31 30 31 40.672 40.638 46.932 39.017 35.204 1,260 1,220 1,450 1,170 1, 90 1972 C Jan. 31 — Feb. (* ] .) — 29 — 39.703 — 9.822 — — — T,5s5 1,20 1,440 March 31 April 30 May 31 June(*2) 30 Ju ly(*2) 31 Aug. 31 Sept. 30 Oct.(*3) 3]. Nov. 30 Dec. 31 1973 Jan. (*4) 31 TOTALS DURING OPE RAT ION 44.497 43.390 46.406 47.95P 42.6 42.6 42.6 42.6 42.6 42.6 42.6 660 65 1,380 1,300 1,440 1,000 1,180 1,320 1,280 1,170 1,280 660 65 390 140 150 1,380 1,300 1,440 1,390 1,320 1,320 1,280 1,320 1,280 1,320 130 (*1) (*2) (*3) (*4) began operations at 9:00 A. M., robruary 9. of operation 10 days and 23 1/2 hours between June 22 and July 3. of operaticii 3 days and 14 hours between October 6 and 9. when the Supplemental Station was put on Rtandby. ------- SECTION VII DISCUSSION A. General The purpose of providing a Supplemental Pumping Station was to protect the water quality of the James River. Avail- able water quality data is based or. weekly sair.ples taken by the r ichinond Department of Public Utilities. The sampling points along the river are shown on Figure 35. River san pling data ace summarized in Tables 2 and 3 for a period of record preceding operation of the Supplemental Pumping Station -nd for the period of operation, respectively. A comparison of maximum and minimun’ concentrations of dissolved oxygen and BOD 5 in the river by months is pre- sented as Figures 36 and 37, respectively. These data indicate that dissolved oxygen levels were maintained at or above those for the period of record for stations down- stream of the Wastewater Treatment Plant. Likewise, the concentration of 5-day biochemical oxygen demand during the period of operation is lower than that during the period of record downstream of the plant. A record of the loadings on the Wastew.. ter Treatment Plant is presented in Table 4. This table covers not or’y the period of operation of the Supplemental Pumping Station, but the nine-month period immediately preceding. The tabu— lation shows that during that nine-month period, the Waste— 87 ------- FIGURE 35 RIVER SAMPLING STATIONS I S.T.P SCALE 048 2 6 io,cEOFT. LEGEND Boulevard Bridge Intermediate Terminal Light 68 / Dupont Intake / Light 166 88 ------- TABL ; 2 RICHMOND, VIRCINIA River Sampling Data July, 1963—June, 1969 Station 2 Station 3 Station 4 Station 5 Station 6 DO BOD CO BOD DO BOD DO BOD DO BOD Month % Sat mg/i % Sat mg/r % Sat mg/i 5 % Sat mg/i5 %Sat mg/i5 Jan. 99 3.2 99 3.5 98 4.7 97 4.8 96 5.1 Feb. 97 2.5 90 3.6 99 4.9 99 4.1 98 3.7 March 96 2.5 97 2.5 99 3.5 98 3.6 97 3.6 ‘0 April 96 3.1 93 3.7 89 3.7 84 3.9 83 4.3 May 93 2.7 91 2.9 83 4.3 75 4.4 75 3.9 . T une 94 1.9 84 3.4 62 4.6 54 4.2 51 4.( July 91 2.2 63 3.5 32 5.3 22 5.6 27 6.1 Aug. 89 2.6 65 3.7 27 6.6 18 6.4 27 8.1 Sept. 87 2.1 65 3.5 19 8.2 14 7.2 15 7.5 Oc!. 91 2.3 87 3.5 59 .7 61 5.4 56 5.5 Nov. 96 2.5 92 3.4 76 6.9 60 6.0 61 4.8 Dec. 97 2.3 98 3.6 97 5.2 96 5 ,4 93 5.2 Aver. 94 2.5 8o 3.4 70 5.3 65 5.1 65 5.2 ------- TABLE 3 RICHMOND, VIRGINIA River Sampling Data Fcbruary, 1972— December, 1972 Station 2 DO BOD % Sat mgi 56 1.8 93 1.7 69 1.3 78 1.2 Station 3 DO DOD % Sat mgi 97 1.3 97 0.4 87 1.7 88 2.1 station a DO DOD % Sat mg / 94 1.9 98 2.0 90 2.3 90 2.2 Station 5 DO DOD °o Sat m9/ 94 1.9 93 2.1 84 2.8 92 3.0 Station 6 DO BODç % Sat mg/i 95 3.1 98 0.9 94 2.0 89 2.2 MO nth Feb. March April 0 !.lay June July 75 3.2 100 1.0 100 3.0 92 2.4 88 3.4 Aug. 73 5.7 98 1.7 95 0.9 98 2.0 94 2.4 Sept. 76 3.7 97 4.8 80 4.6 74 4.1 80 3.2 Oct. 88 5.1 71 2.7 96 1.0 91 2.6 81 6.6 Nov. 78 1.2 84 1.6 83 1.0 83 2.4 83 2.6 Dec. 58 1.4 85 0.9 88 1.1 91 1.0 85 1.4 Aver. 74 2.6 90 1.8 91 2.0 89 2.4 89 2.8 ------- 100— Ataitimum Moniti az rnMont Month I I I I 2 3 4 1 STATION NUMGER LEGEND — — — — Period of record July, 1963 through Period of operation February, 1972 FIGURE 36 June, 1969. through December, 1972. JAMES RIVER, DI3SOLVED OXYGEN LEVEL 80— 60— z 0 U) 0 I- z Lu C) Lu a. 40— 20— 0 91 ------- . • • ?-n . —. -. — w — — s-. —- — tcfl.4, — *fl Minimum Mo?ith — Minin um 2 3 4 5 6 STATION NUMBER LEGEND Parlod of record July, 1963 thro h June, 1969. Period of operation February, 1972 through December, 1972. FIGURE 37 JAMES RIVER, BIOCHEMICAL OXYGEN DEMAND --I Month -O / •%. / I / I / 10 9 8 7 6 5 4 3 2 0 I / / -j 0 I ’ ) / / a, ., — ------- TABL}: 4 RICILMO I1), VIRGItZIA TREATMrNT PLANT WADINGS Month Flow-MGD Suspended Solids 5-Day SOD Suspended Solids Load 50D5 Load Ave. 1ax. Mm. Average-mg/i vcraçc-nq/1 1000 lbs/day 1000 lbn/mo 1000 lbs/day 100C Ibsftto Influer.t Effluent Influont Effluent mi. Eff. mi. Lff. In!. Eu. Inf. Elf. 1971 May 41.18 56.24 28.24 161 80 154 95 55.3 27.5 1713 852 52.C 32.6 1635 1010 June 46.13 61.06 37.76 141 72 101 70 54.3 27.7 1630 831 38.8 27.0 1164 810 July 37.71 44.60 23.16 136 67 137 97 42.7 21.1 1323 654 43.0 30.5 1331 944 Aug. 40.67 48.70 35.08 154 76 129 100 52.2 25.8 1620 800 43.8 33.9 1357 1CSO Sept. 40.64 47.18 27.52 146 76 144 113 49.5 25.8 1485 774 48.8 38.3 1464 1150 Oct. 46.93 59.46 27.68 136 80 104 83 53.2 31.3 1650 971 40.7 32.5 1260 1007 ;ov. 39.0 49.00 23.76 140 79 116 87 45.6 2 .7 1368 771 37.7 28.3 1130 849 Dec. 35.20 47.80 25.38 154 84 124 96 45.2 24.7 1400 765 36.4 28.1 1129 871 1972 Jan. 39.70 46.30 28.40 144 88 140 118 42.6 29.1 1477 902 46.3 39.0 1435 1209 Ave. 40.CO 146 78 128 95 49.5 26.5 1518 813 43.1 32.2 1323 989 Feb. 49.32 61.32 32.40 122 87 102 109 50.7 36.2 1470 1 .050 42.4 45.3 1229 1312 Mar. 44.50 57.50 39.14 128 72 117 96 47.5 26.8 1471 831 43.4 35.6 1345 1103 Apr. 43.39 55.36 38.80 150 81 149 100 54.3 29.3 1630 879 53.9 36.2 1618 1086 May 46.40 58.80 36.60 13]. 72 135 .103 50.6 27.9 1570 865 52.2 39.9 1619 1238 .munel’)49.96 60.50 40.24 133 65 130 91 53.2 26.0 1118 546 52.0 36. 4 1091 764 Ju lyO .)42.6* — — 162 72 198 131 57.6 25.6 1210 537 70.6 46.5 1482 976 Aug. 42.6* — — 135 66 150 109 48.0 23.4 1488 775 53.3 38.7 1651 1200 Sept. 42.6* — — 144 74 215 162 51.2 26.3 1536 790 76.5 57.5 2290 1726 Oct.(2)42.6* — — 115 71 159 112 40.9 25.2 1105 650 56.5 39.8 1525 1075 Nov. 42.6* — — 125 73 140 104 44.4 25.9 1332 777 49.7 37.0 1490 1110 Dec. 42.6* — — 101 61 116 83 35.9 21.7 1112 672 41 2 29.5 1275 915 Ave. 44.33 - 131 72 146 109 48.6 26.8 1367 759 53.8 40.2 1510 1137 (1) Figures do not include estimated loadings during the flood of June 23 — J’ily 4 (2) Figures do not include estimated icadings during the flood of October 6-9 * Flow based on average of the previous 418 days ------- a. water Treatment Plant received an averaae monthly flow of 40.80 mad, 1,518,000 pounds of suspended solids monthly and 1,323,300 pounds of DOD 5 monthly. fluring the operation of the Supplemental Pumpirg Station, and not including the periods of shutdown caused by flooding, the plant rcceived an average monthly flow of 44.33 mcd, l,367,00 I pounds of suspended solids n onthly and l,ilO,)00 pounds of DOD 5 monthly. The effluent for the nine months prior to operation of the Supplemental Puripinq station average 813,000 pounds per month of suspended solids and 989,000 pounds of DOD 5 per month. During operation, not including shutdowns, the ef- fluent averaged 759,000 pounds of suspended solids per rionth and 1 ,l37, 00 pounds of DOD 5 per month. The thfluent and efflut.it loadings of flow handled by the treatment plant are shown on Figure 8 (Suspended Solids) and 7 igure 39 (BOD 5 ). Prior to the operation of the Supple nental Purping Sta- tion, the Wastowater Treatment Plant renoved approximately 46 percent of the suspended solids and 25 percent of the BOD 5 . During operation of the Supplemental Pumping Station, the plant removed approximately 45 pcrc nt of the suspended so1id and 25 percent of the DOD 5 , which indicates the plant continued to function at the same level of efficiency. The floods which caused shutdowns of the Supplemental Pumping Station allowed the following estimated suspended solids and DOD loads to enter the river: 94 ------- Est. Load—1000’s of Is . S ispended Flood Solids BODE June—July, 1972 1,000 1,107 October, 1972 164 226 Total 1,164 1,333 The operation of the Supplemental zuruping Station re- duced the load on the James River, over the entire period of operation, a total of 6,630,000 pounds of suspended solids and 4,110,000 pounds of 30D 5 . The James River flows, average, maximum and minimum, are tabulated for the period January, 1958 through December, 1972 and are shown in Table 5. The average monthly flows for 1972, based on preliminary data from the Virginia State Water Con- trol Board are as follows: Average Monthly Flow Month ( CFS ) January 6,180 February 18,295 March 10,180 April 9,492 May 13,036 June 30,906 July 11,302 August 7,859 September 2,486 95 ------- 80 70 0 o 60 0 0 U I C, > do -J 40 -J 30 0 U I 0 z20 UI U) C l ) I0 0 MONTH 96 ------- Flood Jw 9 21 to July 4 Flood _____ Oct.6 to Oct.9 ______r’ ’ I I I I I I____ I I I Doc. ear. r. Jw c July . Sept. Oct Nc . 1972 MONTH FIGU E 3a WASTE 1ATER TREATMENT PLANT INFLUENT AND EFFLUENT LOADINGS SUSPENDED SOLGDS 97 ------- 80 70 6O 0 0 0 50 w 40 l-J 00 >- 20 I ’ ) to 0 MONTH 96 ------- to July 4 I I I I I I I I I Mar. Apr. t oy June July 1972 Aug. Sopt. Oct. Nov. Doe. MONTH FI U E 39 WASTE WAT ER INFLUENT AND BIOCHEMICAL T’ E’ 1 TMENT PLANT EFFLUENT LOADINGS OXYGEN DEMAND 6 to Oct. 9 99 ------- TABLE 5 RICHMOND, VIRGINIA James River Flow January, 1958 through December, 1972 Average Minimum Maximum Range: Monthly Monthly Mon hly Max. Minus Month Flow-CFS Flow-Cr’S Flow-CFS Mm. — CFS Jan. 7,301 2,903 22,803 19,900 Feb. 10,511 2,957 28,672 25,715 Mar. 12,383 5,117 40,145 35,028 Apr. 9,490 4,466 25,323 20,857 May 7,159 2,887 18,905 16,018 June 5,752 1,184 30,906 29,722 July 2,402 648 11,302 10,654 Aug. 3,413 405 21,710 21,305 Sept. 1,416 202 4,960 4,758 Oct. 4,171 330 18,700 18,370 Nov. 4,507 1,084 19,710 18,626 Dec. 6,455 2,029 20,132 18,103 100 ------- October 18,700 November 19,710 December 20,132 Comparison of the 14-year average in Table 5 with the above figures for 1972 shows that all months in 1972, except January and March, :ere greater than the average, most being significantly greater. The combination of higher than normal river flows and continuation of normal treatment processes resulted in an improved water quality of the James River, even with load- ings occasioned by the two floods during the project. B. The Design The provision of a steel sheeted structure for the Supplemental Purnpinc, Station proved to be a practical r ethod of construction. Steel sheeting was driven to rock and area inside the sheeting was excavated while the walers were being driven down. Difficulty was experienced in placing the lower walers because the sheeting had drifted in toward the center. Another method of construction which might have lessened the difficulties would be one in which the sheeting and walers were driven together and in which the excavation proceeded with the driving. The construction could then proceed by the sequence of driving, excavating, and placing walers. 101 ------- While the ground water conditions encountered at the Treatment Plant site are relatively high, it was not necessary to weld the joints of the steel sheeting, however leakage proved objectionable in the steel sheeting separating the wet well and dry well. The Contractor welded the seams of this separation wall between El. -2.5 and El. 6.0. After the June, 1972 flood, the City, under their Annual Welding Contract, completed welding the joints in this separation wall to ground level. Unfortunately, this additional welding work was not completed prior to the October, 1972 flood and consequently, the dry well again flooded. Construction of this type has also indicated the need for a sump pump of greater capacity than that which would be normally provided. The variable speed control of the pumps appeared to be a good system, but not without difficulties. The system req iired a time delay circuit to allow the lead and lag pumps to change speeds more smoothly, and adjustments proved very difficult except under low flow conditions. At low speeds the pump controls tended to “hunt” over a 20-30 rpm range. The air hose to the bubbler control tube was not strong enough and ruptured after about one month of operation. The pumps and motors operated satisfactorily throughout the project and appeared to be suitable for this type of service. 102 ------- The electrical system was revised to eliminate the danger from 50 feet of 2400 volt conduit inside the struc- ture ahead of the breaker. The transformers at the sub- station had trouble with overheating and plugging of the vents in the oil system. The bar screen platform in the wet well had openings in the north and south ends which allowed large objects to get into the pumps during high flow periods. The apparent solution, which was undertaken, was to provide a “screen” at these openings. The temporary bulkhead at the South Junction Chamber was a successful design. The bulkheading of a chamber which was not originally designed for the loads appears feasible. The novelty of this bulkhead is also apparent in that it can be installed, operated and removed. Should plant operations require, the bulkhead could be reinstalled. The removable roof panels as designed are probably acceptable for relatively continuous operation, but are not suitable for emergency equipment removal. For emergency equipment removal, the panels should be designed to be readily removable. C. The Construction Due to the restricted area, the Contractor elected to drive the sheet piling for the Supplemental Pumping Station without excavating. This method was successful, but did prove to be time—consumlling. The elevation of rock was 103 ------- found to be lower than estimated and this caused some problems since the Contractor had ordered sheeting in “exact” lengths. Additional sheeting had to be ordered and welded on to the driven sheeting. The method of driving without excavation probably contributed to the sheeting drift toward the center and caused difficulty in setting the bottom waler. The existing 72—inch sewer and concrete cradle was found to have been built differently from the Plans. There was a misalignment of the sewer, probably due to a ledge of rock. The sewer was built around the rock ledge and the concrete cradle was incomplete. Construction was generally delayed by slow progress on the pile driving and excavation, the availability of corner sheeting, structural steel, control circuitry, and re rking of controls. The modifications of the South Junction Chmniber proceeded slowly and intermittently with small crews, but was ready to receive the bulkhead when the Pumping Station was ready for operation. Only one day was required to make the necessary modifications to the bulkhead to accommodate the different size opening. The installation went smoothly and the bulkhead required no further modifications. The final completion of the new Grit Removal Facilities was delayed twice by flooding. The floods of both June and October, 1972, occured at approximately the time when 104 ------- construction was complete and connection was to be made. When the grit facilities were finally brought on line, the Supplemental Pumping Station was on standby service and adjustments were made both at the gut chamber and the Main Pumping Station. When fina] adjustments were completed the temporary bulkhead was removed and the Supplemental Pumping Station deactivated. The Supplemental Pumping Station can be reactivated should conditions at the Wastewater Treatment Plant require. D. Operations The operation of the Supplen ental Pumping Station demonstrated that a constant wet well level was very difficult to achieve and the fluctuations caused the lead and lag pump operation to be generally troublesome. Manual adjustment and operation of the station were often required. If a pump were shut off without bringing down the speed, the sewage in the discharge line would rush back and quickly raise the wet well. Cleaning of the bar screen was difficult because of the large fluctuations in the wet well and especially difficult during periods of high flows when the sidewalk platform was submerged. During flood conditions, the bar screen became clogged with debris and caused the pumps to “hunt” for an operating range, caused debris to flow over the platform and down through the openings. 105 ------- The pump control electrolyte reservoir level required regular attention and when the level became too low, the pump speeds would vary erratically over a range of 40—50 rpm. Also, it was necessary to enclose the electrolyte controls to protect them from freezing during cold weather periods. The operation f the temporary bulkhead in the South Junction Chamber demonstrates that with careful preparation, design and rabrication a device can be provided which can divert flow without shutdown. Provision of such a device should also consider the greater expense required to insure a workable solution. The Supplemental Pumping Station was a generally reliable facility, despite operational r.,oblezns associated with full automatic operation. Adjustments of the station controls proved difficult under “on-line” conditions and the system was often operated manually. The speed of constructthn, closely followed by operation probably did not allow an adequate period of training and orientation for the operating personnel. Consequently, problems did develop due to inappropriate action or faultly adjustments. The Supplemental Pumping Station is now expected to remain available for standby service. During the near future, repairs to flood damage will be made and the station restored to pre-flood condition with modifications to the superstructure roof. The present plan is to operate the station weekly to insure its continued reliability. 106 ------- SECTION VIII REFERENCES 1. City of Richmond, Virginia. Agreement between City and Virginia Electric and Power Company, dated March 22, 1971, to cc.nstruct Supplemental Pumping Station Electrical Substation. 2. City of Richmond, Virginia. Division X — Grit Removal Facilities. Change Order No. 7, dated April 17, 1970; change Order No. 9, dated October 10, 1970. 3. City of Richmond, Virginia. Divisions XII and XIII — Secondary Treatment Facilities - Phase 3. Change Order No. 2, dated September 2, 1970; Change Orders Nos. 3 and 4, dated October 10, 1970; Change Order No. Sr dated October 21, 1970. 4. City of Richmond, Virginia. Supplemental Pumping Station — Furnishing Pumping Equipment. Change Order No. 1, dated May 19, 1971. 5. City of Richmond, Virginia. Supplemental Pumping Station. Daily Operating Records and Operators’ Logs. 6. City of Richmond, Virginia. Supplemental Pumping Station. Operating Charts for Discharge Pressure — Pumping Unit o. 1. 7. City of Richmond, Virginia. Supplemental Pumping Station. Operating Charts for Discharge Pressure — Pumping Unit No. 2. 8. City of Richmond, Virginia. Supplemental Pumping Station. Operating Charts — RPM — Pumping Unit No. 1. 9. City of Richmond, Virginia. Supplemental Pumping Station. Operating Charts - RPM - Pumping Unit No. 2. 10. City of Richmond, Virginia. Supplemental Pumping Station. Operating Charts — Suction Pressure — Pumping Unit No. 1. 11. City of Richmond, Virginia. Supplemental Pumping Station. Operating Charts - Suction Pressure — Pumping Unit No. 2. 107 ------- 12. City of Richmond, Vira nia. Wastewater Treatment Plant. Daily Operating Records. 13. City of Richmond, Virginia. ‘leekly Jar es River Analysis Report. (six sampling points in James River) 14. Greeley and Hansen, Engineers, Chicago, Illinois. Plans and Specifications dated April, 1970, entitled “Supplemental Pumping Station — Furnishing Pumping Equipment.” 15. Greeley and Hansen, Engineers, Chicago, Illinois. Plans and Specifications dated August, 1970, entitled “Supplenc .ital Pumping Station and Appurtenances — Structures.” 16. Jordan, C. L., Resident Construction Engineer. Notes on Construction and Operation of the Supplemental Pumping Station. 17. U. S. Department of Commerce, National Oceanic and Atmospheric Administration, Environmcntal Data Service. Climatological Data for Byrd Fiel Station, Richmond, Virginia. 108 ------- |