United States Environmental Protection Agency Office of the Inspector General Washington DC 20460 November 1991 Office of the Inspector General Semiannual Report to the Congress April 1,1991 Through September 30,1991 Printed on Recycled Paper ------- Foreword During this semiannual period, the Office of Inspector General identified improvements needed in several of EPA's major environmental programs, including pesticides, wetlands, and the cleanup of hazardous waste sites. We continued to find weaknesses in accounting for Superfund costs. Procurement and contract management remain a major concern. We continued our long-term commitment to improve contracting practices and contractor performance in EPA. We are focusing more resources on coordinated audits and investigations to ensure that the Agency is receiving quality work at reasonable prices and to pursue legal and administrative actions against unethical contractors. We also have initiated significant work toward implementing the Chief Financial Officers Act. We have become more involved in helping ensure that scientific data upon which the Agency bases its policies, programs, regulations, and enforcement actions are sound and credible. Our investigative work has found fraud and abuse in a surprisingly large percentage of laboratories participating in the Superfund Contract Laboratory Program. An audit found that the Agency had not identified and taken enforcement actions against laboratories that violated good laboratory practices regulations issued under the Federal Insecticide, Fungicide, and Rodenticide Act. We are using Total Quality Management (TQM) to improve our internal operations. Agency management has always shown a willingness to cooperate with us in improving program operations. However, through the use of TQM techniques we hope to work more closely with individual EPA program offices in the future, especially in improving their financial and contract management. John C. Martin Inspector General April 1, 1991 through September 30, 1991 ------- rj; - •1 ’ 2 - - - , r - -: 4, - I • ; f - - - c_ u• I • - - • • * — I-.’ :- . .1 ------- Contents Executive Summary I Overview of EPA’. Current Challenge. 3 Overview of Significant Trends In EPA of Concern to the OIG 4 Profile of Activities and Results 6 Establishment of the OIG in EPA—Its Role and Authority 7 Organization and Staffing 7 Purpose and Requirements of the OIG Semiannual Report 7 Section I—SIgnificant Problems, Abuses, and Recommendations Summary of Audit Activities and Results 10 Agency Management 11 Construction Grants 16 Superfund Program 20 Special and Early Warning Reviews 22 Section 2—AudIt Resolution Status Report on Perpetual Inventory of Audits in Resolution Process for the Semiannual Period Ending September 30, 1991 26 Audit Followup 27 Status of Management Decisions on IG Audit Reports 30 Resolution of Significant Audits 31 Section 3—Prosecutive Actions Summary of Investigative Activity 32 Description of Selected Prosecutive Actions 33 Description of Selected Prosecutive and Administrative Actions Concerning EPA Employees 35 Civil and Administrative Actions To Recover EPA Funds 35 Section 4—Fraud Prevention and Resource Management Improvements Review of Legislation and Regulations 36 Suspension and Debarment Activities 38 OIG Management Initiatives 40 Employee and Public Awareness 41 Personnel Security Program 41 President’s Council on Integrity and Efficiency 42 Committee on Integrity and Management Improvement 42 Hothne Activities 42 Professional and Organizational Development 4.3 Appendices Appendix 1—Audit Reports Issued 45 Appendix 2--Audits Without Management Decisions 60 A placid scene (photo by Steve Delaney, EPA) ------- Executive Summary Section 1— Significant Problems, Abuses, and Recommendations 1. Effects of Many Inert Ingredients in Pesticides Are Unknown. EPA had not promptly reviewed the potential toxicity of most inert ingredients in pesticides to ensure that human health and the environment are adequately protected (page 11). 2. Improvements Needed To Protect Wetlands. Protection of the nation’s wetlands from the discharge of dredged or fill material was undermined by EPA’s inconsistent program implementation (page 12). 3. EPA Region 8 Created A Personal Services Relationship With Support Contractor. Region 8 and EPA Headquarters did not follow EPA and Federal guidance and regulations in managing support contracts with Computer Sciences Corporation (CSC). As a result, contractor employees worked without clearly defined tasks or criteria for measuring their performance and created a personal services relationship between EPA and CSC (page 12). 4. Stronger Enforcement and Oversight Needed for Region 8 RCRA Program. EPA Region 8 had not provided adequate oversight of Resource Conservation and Recovery Act (RCRA) enforcement activities nor did states assess monetary penalties that considered the severity of the RCRA regulation violation or the economic benefit of noncompliance (page 13). 5. Problems Continued to Plague State Vehicle Inspection and Maintenance Programs. Over the years, EPA ’s Office of Mobile Sources has identified serious and continuing weaknesses in state vehicle inspection and maintenance (IIM) programs. Although EPA recommended corrective actions, in many instances, the states had not implemented them (page 14). 6. Greater Efforts Needed to Improve the Delaware and Inland Bays Estuaries. Region 3’s current efforts under the National Estuary Program are repetitious of past attempts to improve the Delaware and Inland Bays Estuaries, and the State of Delaware had not enforced the Clean Water Act against polluters that discharge into these estuaries (page 14). 7. Construction Grant Obligations Overstated by $49 Million. EPA regional offices did not take timely action to deobligate nearly $49 million of construction grant funds that could have been used for needed projects (page 15). 8. Los Angeles Claimed $90.3 Million in Questioned Costs. The City of Los Angeles, California, claimed $10,871,601 of ineligible construction, engineering, and force account costs. An additional $79,434,029 of unreasonable project costs were questioned for a facility not being used for its intended purpose (page 17). 9. Monterey, California, Claimed $58.6 Million of Ineligible and Unreasonable Costs. The Monterey Regional Water Pollution Control Agency, Monterey, California, claimed $7,491,007 of ineligible construction, engineering, administrative, and other costs. An additional $51,118,958 of unreasonable project costs were questioned (page 17). 10. Grantee’s $36.8 Million Project Claim Questioned After 12 Years of Violating Discharge Limitations. The Gary, Indiana, Sanitary District claimed $36,853,715 of costs for a wastewater treatment plant that has violated its National Pollutant Discharge Elimination System permit since 1978 (page 17). 11. Clark County, Nevada, Claimed $32.9 Million of Questioned Costs for Underutilized Facility. The Clark County Sanitation District, Nevada, claimed $6,851,921 of ineligible costs and about $26 million of unnecessary, unreasonable, or unsupported costs for a wastewater treatment plant used at only about half of its capacity (page 18). 12. Philadelphia Claimed Over $10.3 Million of Questioned Costs. The City of Philadelphia calmed $9,552,760 of ineligible force account, engineering, construction, indirect and Federal facility share costs. An additional $801,546 of unsupported, unnecessary and unreasonab!e costs were also questioned (page 18). 13. Nearly $7.7 Million of Questioned Costs Claimed by Indianapolis, indiana. The City of Indianapolis, Indiana, claimed $5,245,844 of ineligible engineering, project inspection, construction management, and other costs. An additional $2,424,093 of unsupported costs were questioned (page 19). 14. EPA Unnecessarily Delays Responsible Parties From Cleaning Up Hazardous Sites. Completions of Superfund cleanups were unnecessarily delayed by untimely review of responsible parties’ (RP) work products, failure to enforce stipulated penalties against RPs for noncompliance with voluntary agreements, and inadequate monitoring of contractors (page 21). 15. Problems With Superfund Accounting Continue. EPA’s accounting for Superfund costs has been improved, but as previously reported, financial reporting and accounting for disbursements, obligations, and receivables contain inaccuracies (page 21). 16. Inefficient Contracting Practices May Cost EPA An Extra $10.7 Million for Automatic Data Processing (ADP) Equipment and Services. EPA could pay up to $8.4 million over decreasing market prices for microcomputer workstations and other ADP equipment by not modifying an interim contract and delaying a competitive award. EPA could also pay the contractor $2.3 million more than actually incurred for operating expenses (page 22). 17. EPA Made Unnecessary and Improper Procurements Through Its Waterside Mall Lessor. EPA’s Facilities Management and Services Division circumvented Federal acquisition regulations and Agency procedures to make improper procurements through its Headquarters lessor, resulting in unnecessary costs in excess of $138,500 (page 23). 18. Laboratories Not Properly Targeted For inspections To Detect Violations. EPA failed to identify and take enforcement action against laboratories that violated good laboratory practices regulations issued under the Federal Insecticide, Fungicide, and Rodenticide Act (page 23). Apn 1, 1991 through September 30, 1991 ------- 19. Arizona And Nevada Had Not Matched $22 Million of EPA’s Construction Grant Funds. Arizona and Nevada had not provided required matching funds for implementing their State Revolving Fund programs, resulting in $22.2 million of Federal grant funds for construction of wastewater treatment plants remaining idle (page 24). 20. $1.5 Million Grant Prematurely Awarded For Indiana Project Requiring Modification EPA awarded a $1.5 million grant to construct sewers and a wastewaler treatment facility even though over one-third of the structures to be serviced are in a flood plain and will be moved or demolished (page 24). 21. $10.4 Million Grant To Florida County Should Be Annulled. Seven years after receiving a $10.4 million grant, Hillsborough County, Florida, still does not have a fully operable wastewater collection system (page 25). Section 2— Audit Resolution At the beginning of the semiannual period, there were 240 audit reports for which no management decision had been made. During the second half of fiscal 1991, the Office of Inspector General issued 942 new audit reports and closed 230. At the end of the reporting period, 309 audit reports remained in the Agency followup system for which no management decision had been made. Of the 309 audit reports, 68 reports remained in the Agency followup system for which no management decision was made within six months of issuance (page 26). In four followup audits, the Office of Inspector General found that some problems identified in previous audits continued to exist (page 27). However, we have nothing to report this period with respect to significant management decisions with which we disagree as required by the 1988 Inspector General Act Amendments. For the 230 audits closed, EPA management disallowed $45 million of questioned costs for recovery and agreed with our recommendations that $3.5 million be put to better use (page 26). In addition, cost recoveries in current and prior periods included $4.9 million in cash collections, and at least $19.2 million in offsets against billings (page 6). Section 3— Prosecutive Actions During this semiannual reporting period, our investigative efforts resulted in 11 convictions and 18 indictments. Also, this semiannual period our investigative work led to $4.5 million in fines and recoveries (page 32). A California testing company pled guilty to making false claims and false statements to EPA and was fined $500,000; a New Jersey testing company was fined $1 million for false statements; a New Jersey man pled guilty to charges that he sold mislabeled, unregistered pesticides overseas in violation of the Federal Insecticide, Fungicide, and Rodenticide Act; two employees of a Superfund cleanup contractor in Pennsylvania were charged with fraud; the Government and the remaining defendants in the Snapfingor Creek bidrigging case reached agreement on a final settlement of $880,000; and EPA received $350,000 back in a case involving contract lab fraud (page 33). Section 4— Fraud Prevention and Resource Management Review of Proposed Legislation and Regulations During this semiannual period, we reviewed 86 legislative and regulatory items. The most significant were an Anti-Fraud Enforcement Bill; a False Claims Act amendment; a bill on Federal government performance standards; special pay provisions for law enforcement personnel; and ethics regulations for Executive Branch personnel (page 36). Suspension and Debarment Activities We completed 148 cases during this reporting period, resulting in 36 debarments, 95 suspensions, 17 settlement agreements, and 52 cases closed after investigation. There were 171 active cases at the close of the reporting period (page 38). OIG Management Initiatives The OIG has two ongoing initiatives designed to promote management and financial improvements and integrity in EPA’s operations. These are major projects to expand the contr t audit program and assistance to the Agency in implementing the Chief Financial Officers Act (page 40). Personnel Security Program During this reporting period, the Personnel Security Staff reviewed 466 investigations. Among the actions taken, based on these reviews, were the resignation of two employees who had falsified their SF-171s, Application for Federal Employment, by not listing previous convictions for drug trafficking and writing worthless checks; oral reprimandsNerbal counseling of six employees regarding their failure to report delinquent taxes and debts and previous convictions for driving while intoxicated; and the decision not to make an employee a funds certifying officer and that employee receiving an oral admonishment for failure to disclose financial indebtedness (page 41). Hotline Activities The OIG toll-free Hotline opened 37 new cases and closed 27 cases during the reporting period. Eight of the closed cases resulted in environmental, prosecutive, or administrative corrective action (page 42). Professional and Organizational Development We approved 308 training enrollments for a total of 959 days of training and participation in professional development seminars and conferences. For all of FY 1991, we approved 595 enrollments for a total of 1739 days. The OlG-developed course, Detection and Prevention of Fraud, was substantially revised and presented twice during the reporting period. The Inspector General, Deputy Inspector General, and 26 managers completed the EPA Executive Course on Total Quality Management (page 43). 2 Office of the Inspector General Report to the Congress ------- An Overview Of EPA’s Current Challenges This section highlights some of EPA’s most significant challenges for restoring and protecting the quality of the air we breathe, the land where we live, and the water we depend on. Land The principal sources of land waste are: • Underground Storage Tanks. An estimated two million underground storage tanks in use in the United States contain petroleum products or hazardous chemicals. Approximately 400,000 of these tanks may be leaking and are a source of land contamination that can contribute to ground-water contamination. • Industrial Hazardous Wastes. The chemical, petroleum, metals, and transportation industries are major producers of hazardous industrial waste, such as dioxin and benzene which are known carcinogens. • Municipal Wastes. Municipal wastes include household and commercial wastes, demolition materials, and sewage sludge. Solvents and other harmful household and commercial wastes are generally so intermingled with other materials that specific control of each is virtually impossible. • Mining Wastes. A large volume of all waste generated in the United States is from mining coal, phosphates, copper, iron, uranium, and other minerals and from ore processing and milling. Runoff from these wastes increases the acidity of streams and pollutes them with toxic materials. Air The Clean Air Act Amendments of 1990 address three major threats to our nation’s environment and the health of Americans: urban air pollution, acid rain, and air toxics. The 1990 amendments also establish a national operating permits program and an improved enforcement program to foster better compliance with the requirements of the Act. • Urban Air Pollution. Under the 1970 Clean Air Act, EPA established National Ambient Air Quality Standards for pollutants posing the greatest overall threat to air quality. These “criteria pollutants” include ozone, carbon monoxide, airborne particulates, sulfur dioxide, lead, and nitrogen oxides. The 1990 amendments require a new classification of areas which are not in attainment with these standards and establish time frames for attainment based on the severity of current pollution levels. More stringent motor vehicle emission standards, use of alternative clean fuels, clean-fueled fleet vehicles, and additional controls on industrial facilities are required. Acid Rain. Emissions of sulfur dioxide (primarily from coal-burning power plants) and nitrogen oxides (primarily from motor vehicles and coal- burning power plants) interact with sunlight and water vapor in the upper atmosphere to form acidic compounds which can fall as acid rain. This is recognized as a serious long- term problem for many industrial nations. The 1990 amendments establish new requirements, primarily on coal-burning power plants, aimed at reducing emissions of sulfur dioxide and nitrogen oxides emissions. Also, these amendments provide for banking and trading of emission allowances among emission sources to facilitate reductions of acid rain. • Air Toxics. Before the 1990 amendments, EPA was required to establish national emission standards for hazardous air pollutants which would protect public health with an ample margin of safety. Because this margin was difficult to define and was the sublect of continued litigation, EPA promulgated regulations for only seven pollutants. The 1990 amendments shift from regulation of individual pollutants to categories of sources using technology- based standards. EPA must publish a list of industrial source categories for 189 chemicals specified in the 1990 amendments and regulate each categoty within 10 years to reduce air toxic emissions by over 75 percent. Water The job of cleaning and protecting the nation’s drinking water; oceans, coastal waters, and wetlands; and surface waters is made complex by the variety of sources of pollution that affect them. • Municipal Sources. Municipal wastewater (primarily from toilets, sinks, showers, and other uses) which runs through city sewers may be contaminated by organic materials, nutrients, sediment, bacteria, and viruses. Toxic substances used in the home also make their way into sewers. • Industrial Sources. The use of water in industrial processes, such as the manufacturing of steel or chemicals, produces billions of gallons of wastewater daily. Statut• Major Laws Administered by EPA Toxic Substances Control Act Provision, Federal Insecticide. Fungicide, and Rodénticide Act Requires that EPA be notified of any new chemical prior to its manufacture and authorizes EPA to regulate production, use, or dispose] of a chemical. Federal Food, Drug and Cosmetic Act Authorizes EPA to register all pesticides and specify the terms and conditions of their use, and remove unreasonably hazardous pesticides from the marketplace. Resource Conservation and Recovery Act Authorizes EPA in cooperation with FDA to establish tolerance levels for pesticide residues on food. Authorizes EPA to identify hazardous wastes and regulate their generation, transportation, treatment, storage, and disposal. comprehensive Environmental Response, Compensation, and Liability Act Clean Air Act Requires EPA to designate hazardous substances that can present substantial danger and authorizes the deanup of sites contaminated with such substances. Clean Water Act Authorizes EPA to set emission standards to limit the release of criteria pollutants and hazardous air pollutants. Safe Drinking Water Act Requires EPA to establish a list of toxic water pollutants and set standards. Marine Protection, Research and Sanctuaries Act Requires EPA to set drinking water standards to protect public health from hazardous substances. Asbestos School Hazard Abatement Act Regulates ocean dumping of toxic contaminants. Asbestos Hazard Emergency Response Act uthorizes EPA to provide loans and grants to schools with financial need for abatement of severe asbestos hazards. Emergency Planning and Community Right-to-know Act Requires EPA to establish a comprehensive regulatory framework for controlling asbestos hazards in schools. Requires States to develop programs for responding to hazardous chemical releases and requires industries to report on the presence and release of certain hazardous substances. April 1 1991 through September 30, 1991 3 ------- TOverview of Significant Trends In EPA of Concern to the OIG • Nonpoint Sources. Nonpoint sources of water pollution are multiple, diffuse sources of pollution as opposed to a single “point” source, such as a discharge pipe from a factory. For example, rainwater washing over farmlands and carrying top soil and chemical residues into nearby streams is a major nonpoint source of water pollution. Ocean Dumping. Dredged material, sewage sludge, and industrial wastes are a major source of ocean pollution. Sediments dredged from industrialized urban harbors are often highly contaminated with heavy metals and toxic synthetic organic chemicals, such as PCBs and petroleum hydrocarbons. Wetlands • More than half of the wetlands originally in the contiguous United States have been lost and others have been degraded by pollution and hydrological changes so thai they no longer perform many of their natural functions. To achieve its “no net loss” goal, EPA is increasing enforcement of Federal restrictions on activities which destroy or degrade wetlands. This section of our report presents the Office of Inspector General’s (OIG) perspective orr ignfflcant vulnerabilities facing EPA. These items serve to highlight the crosscutting problems the OIG believes must be addressed for the Agency to conduct its programs and operations in a more effective, efflcient and economical manner. These trends were derived from an overview of the common or recurring conditions identified by OIG audits, investigations, and evaluations over time. Scientific Data Integrity The accuracy and reliability of scientific data has always been crucial to EPA’s mission as a regulatory agency. Not only is sound scientific data essential to EPA’s credibility, it forms the basis for decisions that affect all major American industries and national policies to prevent hazards and risks to health and safety. However audit and investigative work shows that EPA is not always getting the research for which it pays, nor is it always accurate or objective. EPA is well aware of its role in ensuring that laboratories produce the type of data that can be relied upon. The pesticides program is particularly vulnerable since the pesticides manufacturers pay for studies that support their registration with EPA. EPA implemented the Good Laboratory Practices program to help ensure the integrity of the data that supports pesticides registration. The Agency recognized that this program had weaknesses, however, and asked the Office of Inspector General to look at alternatives for improving the program. A recent OlG special report found that the same 200 largest laboratories are inspected over and over, While another 600 smaller laboratories are not inspected at all. EPA has used independent laboratories under the Contract Laboratory Program to test samples from Superfund sites. We reported that EPA was not obtaining and safeguarding all original documentation generated by these contract laboratories. Also, a large percentage of contract laboratories were found to have serious problems with the integrity of their data and methods, resulting in criminal prosecutions, civil recoveries and debarments. Contract And Procurement Practices Procurement and contract management concerns continue to be the subject of Office of Inspector General audits, EPA internal control assessments, and General Accounting Office reviews. There is a dangerous tendency in EPA for the perceived urgency of program needs to prevail over sound contract management. EPA has a significant reliance on contractors to perform many of its functions while contractors may rely on limited scrutiny or liberal interpretation of their claims. Past OlG audits and investigations have identified instances of overcharging, including exorbitant markups on materials and services; award fees being given to contractors for less than satisfactory work; conflict of interest involving EPA employees; and schemes by contractors to defraud EPA. We recently reported that in Region 8s management of a computer support contract, a personal services relationship developed, in violation of Federal civil service laws and regulations, because the regional and national project officers prepared statements of work which broadly described the desired services and did not ensure the contractor could perform needed tasks and services. In its 1990 letter to the President, required by the Financial Managers’ Financial Integrity Act, the Agency reported a material weakness for Superfund because of the perception that contractors are assisting the program office with policy and regulatory development. Also, EPA’s Office of Research and Development reported that there is a growing inability to adequately manage extramural resources, which creates the potential for fraud, waste and abuse. GAO has identified weaknesses in EPA’s contract management, in such areas as cost controls and the quality of contractors’ performance. In recent testimony before Office of the Inspector General Report to the Congress ------- Congress, GAO stated that EPA has a large backlog of requests for audits of its contracts, with audits of funds paid to contractors being delayed for years. As GAO recommended, the Inspector General is developing a plan for auditing contracts and has requested resources to reduce the audit backlog and to keep abreast of future requirements. Financial Management: Chief Financial Officers Act The Chief Financial Officers (CFO) Act provides for improvements in financial management and internal controls to assure that agencies produce reliable financial information to deter fraud, waste and abuse. Recognizing the importance of financial management, the OlG has over the years performed a number of audits in the area. These audits have found that EPA’s accounting systems do not provide complete, consistent, reliable and timely information for Agency decision making and control of assets. In addition, 0MB considers the Agency’s accounting system a high risk area. In a recently completed review of fiscal 1990 Superfund obligations and disbursements, we found that weaknesses continued to exist in EPA’s new accounting system (the Integrated Financial Management System), property was not accurately recorded in the Agency’s property accounting system, and accounts receivable were not properly recorded and managed. Concerning Superfund, we found that 90 percent or $56.9 million of accounts receivable were classified as delinquent; $4.6 million were not recorded timely; and $181,000 of interest on overdue accounts receivable had not been assessed. Also, promised corrective actions on receivables were either not completed or were considerably delayed along with progress toward achieving accurate and complete accounts receivable records. In response to the CFO Act and as a result of these prior audits, we are continuing our emphasis on performing audits in the financial management area to ensure that necessary improvements are made in the Agency’s financial systems and internal controls. Superfund While progress has been made, OIG audits and investigations show that further significant improvements are needed to improve the cleanup of Superfund sites. EPA has emphasized implementing the needed improvements identified in the Administrator’s 1989 comprehensive review of the Superfund program. As a result, EPA has sought to focus its limited resources on addressing the worst problems at Superfund sites first. Due to continued problems with administration of the Superfund program, the Administrator directed two task forces to perform major studies in the summer of 1991. One of these focused on accelerating the program and improving risk assessment and management. The other focused on contracting problems. The OlG continues to find fraudulent analyses, falsified data, uncalibrated equipment, backdated analyses, and other serious problems with the contract laboratories used to analyze samples from Superfund sites. These problems could call into question cleanup decisions made on the basis of unreliable data analyses and hamper the recovery of EPA’s cleanup costs from those responsible for the contamination. Also, EPA has not adequately monitored the cleanup activities by responsible parties under voluntary agreements. The Agency is often not timely reviewing and approving project plans and other deliverables, assessing stipulated penalties for noncompliance with the cleanup agreements, or adequately monitoring Agency contractors to oversee the private cleanups. Further, EPA continued to be unable to prepare complete and accurate financial reports. The Agency’s Integrated Financial Management System (IFMS) lacked a reporting function and the Agency had not updated the Agency’s accounting procedures since the implementations of IFMS. In addition, we continue to find problems with the Agency’s remedial investigation! feasibility study (RIIFS) process. Rl/FS reports, which are key to Superfund site decision-making, are sometimes incomplete, inaccurate, delayed and not cost effective. Audit Followup The Agency’s system for tracking actions of audit findings is unreliable and the Agency’s Semiannual Reports to Congress on audit followup activity have been inaccurate. Since 1989 we have been assessing the effectiveness of the Agency’s efforts to carry out audit followup responsibilities. When we first began these reviews, there was no national system of audit followup in use. Now, there is the Management Audit Tracking System (MATS) being used by all regions. However, our more recent reviews point out that while there is a national automated system now in place, the information in that system is still not reliable. In our latest report on audit followup, issued in September 1991, we found in just three regions, almost as much in unreported recoveries ($7.4 million) as the Agency reported for all ten regions ($8.3 million) in its Reports to Congress for 1990. As a result of our early reviews, the Agency reported audit followup as a material weakness in its 1989 and 1990 Federal Managers’ Financial Integrity Act (FMFIA) Reports to Congress and the President. Based on information contained in our latest review, the Agency is again considering reporting the same material weaknesses in its 1991 report. While we have seen Headquarters program managers exert considerable effort to improve the national automated system and the audit followup program as a whole, these efforts were not uniformly effective in the regions we reviewed. April 1 1991 through September 30, 1991 5 ------- Profile Of Activities And Results Environmental Protection Agency Office of Inspector General April 1, 1991 to September 30, 1991 Fiscal 1991 (Dollars in Millions) Recommended Etficiencles(Funds be Put to Better Use) • Total Efficiencies $183.8 • Federal Share Etficiencies $178.6 - Cost Disallowed to be Recovered - Federal Share ineligible - Federal Share Unsupported - Federal Share Unnecessary/Unreasonable (costs which EPA management agrees are unallowable and is committed to recover or offset against future payments) - Cost Disallowed as Cost Efficiency • Federal Share Recommended Efficiencies (funds made available by EPA management’s commitment to implement recommendations in OIG performance or preaward audits) OTHER AUDITS: Audits Performed by another Federal Agency or Single Audit Act Audits - Questioned Costs • Total Ineligible • Federal Share Ineligible • Total Unsupported - Federal Share Unsupported* - Total Unnecessary/Unreasonable • Federal Share Unnecessary/Unreasonable - Recommended Efflciencles(Funds be Put to Better Use) • Total Efficiencies $202.7 - Federal Share Efficiencies $202.7 - Cost Disallowed to be Recovered • Federal Share Ineligible - Federal Share Unsupported • Federal Share Unnecessary/Unreasonable (costs which EPA management agrees are unallowable and is committed to recover or offset against future payments) Questioned Cost: Ineligible, Unsupported and Unnecessary/Unreasonable; and Recommended Efficiencies (Funds be Put to Better Use) are subject to change pending further review in the autht resolution process. • Cost Disallowed as Cost Efficiency - Federal Share Recommended Efficiencies (funds made available by EPA management’s commitment to implement recommendations in OIG performance or preaward audits) Agency Recoveries: • Recoveries from Audit Resolutions of $24. Current and Prior Periods (cash collections or offsets to future payments)** REPORTS ISSUED: - 016 MANAGED AUDITS: - EPA Audits Performed by the 016 - EPA Audits Peformed by Independent Public Accountants - EPA Audits Performed by State Auditors - OTHER AUDITS: - EPA Audits Performed by another Federal Agency - Single Audit Act Audits TOTAL REPORTS ISSUED - Audit Reports Resolved 230 (agreement by Agency officials to take satisfactory corrective action) investigative Operations • Fines and Recoveries (including civil) • Investigations Opened • Investigations Closed • Indictments of Persons or Firms • Convictions of Persons or Firms • Administrative Actions Taken Againsl EPA Employees Fraud Detection and Prevention Operations • Debarments, Suspensions, Voluntary Exclusions, and Settlement Agreements (actions to deny $207.4 persons or firms from participating in EPA $207.4 programs or operations because of misconduct or poor performance) • Hotline Complaints Received $4.1 • Hotline Complaints Processed and Closed $0.1 • Proposed Legislative and $0.0 Regulatory Items Reviewed • Personnel Security Investigations Adjudicated “Information on recoveries from audit resolution is provided from the EPA Financial Management Division and is unaudited. April 1, 1991 to September 30, 1991 Fiscal 1991 (Dollars in Millions) Audit Operations 016 MANAGED AUDITS: Audits Performed by EPA, Independent Public Accountants (IPA) and State Auditors • Questioned Costs - Total Ineligible $107.3 - Federal Share Ineligible $80.1 - Total Unsupported $29.0 - Federal Share Unsupported $22.6 • Total Unnecessary/Unreasonable $182.0 - Federal Share Unnecessary/Unreasonable $136.7 $1.2 $33.9 $86 $1.3 $2.3 $150.3 $110.3 $101.1 $76.4 $189.2 $142.1 $237.1 $221.0 $53.2 $14.0 $2.2 $60.9 $8.1 $8.1 $2.3 $2.3 $0.6 $0.6 52 97 16 241 536 942 $8.3 $80.3 100 156 28 366 1,038 1,688 517 $8,189,177 257 284 55 27 49 238 64 47 130 816 $5.4 $5.4 $1.3 $1.3 $0.4 $0.4 $4,541,615 147 153 18 11 38 $1.2 $0.1 $0.0 148 37 27 86 466 6 Office of f he Inspector General Report to the Congress ------- Establishment Of The OIG In EPA—Its Role And Authority The Inspector General Act of 1978 (Public Law 95-452), as amended, created Offices of Inspector General to consolidate existing investigative and audit resources in independent organizations headed by Inspectors General. EPA established its Office of Inspector General (OlG) in January 1980. As an agency with a massive public works budget, EPA is vulnerable to various kinds of financial abuses. The OIG’s role is to review EPA’s financial transactions, program operations, and administrative activities; investigate allegations or evidence of possible criminal and civil violations; and promote economic, efficient, and effective Agency operations. The QIG is also responsible for reviewing EPA regulations and legislation. The EPA Inspector General reports directly to the Administrator and the Congress and has the authority to: • Initiate and carry out independent and objective audits and investigations, • Issue subpoenas for evidence and information, • Obtain access to any materials in the Agency, • Report serious or flagrant problems to Congress, • Select and appoint OIG employees, • Fill Senior Executive Service positions, • Administer oaths, and • Enter into contracts. The Inspector General is appointed by, and can be removed only by, the President. This independence protects the OIG from interference by Agency management and allows it to function as the Agency’s fiscal and operational watchdog. Organization and Staffing The Office of Inspector General functions through three major offices, each headed by an Assistant Inspector General: Office of Audit, Office of Investigations, and Office of Management. Nationally, there are seven Divisional Inspectors General for Audit and five Divisional Inspectors General for Investigations who direct staffs of auditors and investigators and who report to the appropriate Assistant Inspector General in Headquarters. Purpose And Requirements Of The Office Of Inspector General Semiannual Report The Inspector General Act of 1978 (Public Law 95-452), as amended, requires the Inspector General to keep the Administrator and Congress fully and currently informed of problems and deficiencies in the Agency’s operations and to recommend corrective action. The IG Act further specifies that semiannual reports will be provided to the Administrator by each April 30 and October 31, and to Congress 30 days later. The Administrator may transmit comments to Congress along with the report, but may not change any part of the report. The specific reporting requirements prescribed in the Inspector General Act of 1978, as amended, are listed below. The Inspector General Act Amendments of 1988 require Inspector General Act, as amended more detailed statistics on the status of audit reports, their recommendations and monetary results. Source Section and Page Section 4(al(21, Rev ew of Leg slation and 4 36 Reg u a tions Section 5(a)(1), Significant Problems, Abuses, 1 10 and Deficiencies Section 5(a)12), Recommendations with Respect 1 10 to Significant Problems, Abuses and Deficiencies Section 5(a113), Prior Significant Appendix 2 60 Recommendations on Which Corrective Action Has Not Beefl Completed Section 5(al(4), Matters Referred to Prosecut ’ 3 32 Authorities Section 5(aii5l, Summary of Instances Where - Information Was Refused Section 51all61, List of Audit Reports Appendix 1 45 Section 5lall7), Summary of Significant Report 1 10 Sect on 5(ali8l, Statistical Table 1- Reports With 2 30 Costs Questioned Section 5lall9l, Statistical Table 2 - Reports With 2 30 Recommendations That Funds Be Put To Better Use Section OlalllOl, Summary of Previous Reports Appendix 2 60 No Management Decisions, an Explanation of the Reasons Sc Management Decision Has Nc’ Been Made, and a Statement Concerning the Desired T metabIe for Achieving a Management Decision on Eacn Such Report Section 5ialrl 1. Descripton And Explanation o Appendix 2 60 Reused Management Decisior Section 5la)il2i, Management Deois;ons With - Which The Inspector General is in Disagreement * There were no instances wt ere information or assistance requested by the Inspector General was refused during this reporting period. Accordingly, we have nothing to report under section 5(a)(5) of the Inspector General Act of 1978, as amended. There were no instances of management decisions with which the Inspector General was in disagreement Stai ,,, 9 Distribution__Fiscal 1991 CeilIng Office Staff & Support Operations & Field Total inspector General 5 — 5 Audit 31 212 243 investigations 7 64 71 Management 31 — 31 Total 74 276 350 April 1, 1991 through September 30, 1991 7 ------- Headquarters Office of Inspector General — Who’s Who Office of Audit Kenneth A. Konz Assistant Inspector General James 0. Rauch Deputy Operations Staff ElIssa R. Karpf Director Technical Assistance Staff Gordon Milbourn Director Inspector General John C. Martin Deputy Inspector General Anna Hopkins Virbick Office of Investigations Daniel S. Sweeney Assistant Inspector General Vacant Deputy Office of Management John C. Jones Assistant Inspector General Technical Assessment and Fraud Prevention Division Earline Broaden Director Administration and Management Services Division Michael Binder Director Planning and Resources Management Staff Kenneth Hockman Director Divisional Inspectors General RegIon 9 & 10 Truman R. Beeler, Audit H. Brooks Griffin Investigations Region 5 Anthony C. Carrollo, Audit RegIon 1 & 2 Paul McKechnie, Audit Robert M. Byrnes, Investigations Region 3 Paul R. Gandolfo, Audit Martin Squitieri Investigations Headquarters Edward Gekosky, Internal Audit Francis C. Kiley Washington Field Office Investigations Region 5, 7, & 8 Alex Falcon, Investigations Region 4 & 6 Mary Bayer, Audit James F. Johnson, Investigations 8 Office of the Inspector General Report to the Congress ------- r -ii ------- Section 1—Significant Problems, Abuses, And Recommendations As required by sections 5(a)(1) and (2) of the Inspector General Act of 1978, as amended, this section identifies significant problems, abuses, and deficiencies relating to the Agency’s programs and operations along with recommendations for the current period. The findings described in this section resulted from audits and reviews performed by or for the Office of Audit and reviews conducted by the Office of Investigations. Because these represent some of our most significant findings, they should not be considered representative of the overall adequacy of EPA management. Audit findings are open to further review but are the final position of the Office of Inspector General. This section is divided into five areas: Summary of Audit Activities and Results, Agency Management, Construction Grants, Superfund, and Special and Early Warning Reviews. Summary of Audit Activities and Results Questioned Costs And Recommended efficiencies By Type Of Audit 350 C ,, 0 0 150 100 50 Others Superfund Areas Of Effort By Staff Days (Total - 18,765 Days) Performance 5855 31% Sources Of Reports (Total Reports - 942) 300 250 200 0 Construction Federal Questioned Non-Federal Questioned Federal Share Recommended Efficiencies Non-Federal Share Recommended Efficiencies Superfund Performance 2543 14% Audits 57% Superfund-F & C 4082 22% 10 Office of the Inspector General Report to the Congress ------- Agency Management The Inspector Genera! Act requires the O!G to initiate reviews and other activities to promote economy and efficiency and to detect and prevent fraud, waste, and mismanagement in EPA programs and operations. Internal and management audits and reviews are conducted to accomplish these objectives largely by evaluating the economy, efficiency, and effectiveness of operations. The following are the most significant internal and management audit and review findings and recommendations. Eftects Of Many Inert Ingredients In Pesticides Are Unknown Problem EPA had not promptly reviewed the potential toxicity of most inert ingredients in pesticides to ensure that human health and the environment are adequately protected. Background Under the Federal Insecticide, Fungicide, and Rodenticide Act (FIFRA), EPA is authorized to regulate pesticides. Inert ingredients are added to pesticides to serve as a solvent, thickener, or propellant to make them more effective or usable. However, recognizing that some inert ingredients may be toxic, EPA issued an Inerts Strategy in 1987 classifying inerts into four categories: (1) those of unknown toxicity (1,300), (2) those known to be toxic (56), (3) those potentially toxic (68), and (4) those generally recognized as having no toxic effect (300). There may be an additional 600 products containing inert ingredients which EPA has not adequately identified. We Found That EPA had not reviewed about 1,300 inert ingredients in pesticides of unknown toxicity to determine whether they pose potential adverse effects to human health and the environment. The 1987 lnerts Strategy did not detail how EPA would address those inerts of unknown toxicity although they were the largest category. At the time of our review, EPA had started reviewing the publicly available information on 500 of these inerts. However, the Agency had not finalized plans to review over 800 remaining inerts in that category. As a resuft of EPA actions, the 56 toxic inert ingredients identified in the Inerts Strategy had been removed from most of the 1,228 products previously containing these inerts. However, EPA had not completed a compliance monitoring strategy to ensure that the registrants of the pesticides actually removed the toxic ingredients from their products. Also, EPA had not completed other actions intended to reduce the risk from pesticides containing toxic inert ingredients, such as: Requiring registrants to furnish data on exposure, ecological effects and environmental fate for 24 other pesticide products identified since 1987 as containing toxic inerts. • Acting on registrants’ requests for waivers of data requirements for 53 products under review since 1989. • Completing the review of 68 inerts identified as potentially toxic for roclassification as toxic or generally safe. (After 3 years, a work group had recommended that 19 of these inerts be reclassified as toxic.) We Recommended That The Assistant Administrator for Pesticides and Toxic Substances: • Establish action plans to review all inert ingredients in pesticides. • Develop and implement a compliance monitoring strategy for determining whether registrants have removed toxic ingredients from their products. What Action Was Taken The final audit report was issued to the Assistant Administrator for Pesticides and Toxic Substances on September 27, 1991. A response to the final report is due by December 26, 1991. In response to our draft report, the Assistant Administrator outlined corrective actions which, if properly implemented, should resolve the report’s findings. Harvesting lettuce in California (photo by Donald C. Schuhart). April 1, 1991 through September 30, 1991 11 ------- Improvements Needed To Protect Wetlands Problem Protection of the nation’s wetlands from the discharge of dredged or fill material was undermined by EPA’s inconsistent program Implementation. Background Section 404 of the Clean Water Act, as amended, was intended to reduce the destruction and degradation of the nation’s waters, including valuable wetlands, from the discharge of dredged or fill materials. Wetlands are a particularly valuable and vulnerable natural resource which provide many essential functions, such as maintaining groundwater quality, protecting shoreline from erosion, and serving as habitat for a large diversity of birds and fish. Only about 95 million acres of the original 215 million acres of wetlands in the contiguous United States remain today. We Found That Significant management improvements are needed in EPA’s wetlands protection program if legislative and Agency goals are to be achieved. EPA had not established measurable goals and commitments for regional wetlands activities. Regional implementation of the basic wetlands program elements-- enforcement, permitting, and strategic initiatives--varied in emphasis and results. Consequently, wetlands regulation was inconsistent and unpredictable and subject to public distrust and criticism. Specifically: Regions did not coordinate with the Army Corps of Engineers (COE) to consistently identify illegal discharges of dredged or fill material into regulated waters and take enforcement against those violators. Nor did the regions adequately address solid waste discharges as EPA had agreed with the COE to enforce under its CWA authority. Regions did not (1) maintain sufficient viable data on which to base regulatory decisions, (2) implement consistent, controlled public notice review processes, (3) properly exercise EPA’s statutory responsibilities concerning jurisdictional determinations and (4) use available authorities to resolve interagency disputes over permitting. Regions did not identify and prioritize wetlands as to value and vulnerability to target limited program resources and inform the public of most threatened wetlands. Nor did the region adequately plan wetlands initiatives, specifically the advanced identification of priority wetland areas as suitable or unsuitable for the discharge of dredged or fill material. We Recommended That: The Assistant Administrator for Water: • Develop and implement long- term guidance, plans, and meaningful measures of accomplishment to ensure better management accountability and achievement of the national wetlands program goals and objectives. • Establish procedures to monitor the COE enforcement program to identify major violations subject to EPA actions and take a consistent enforcement approach against those violators. • Develop a national approach for EPA’s public notice review process addressing compliance with and the use of existing authorities to foster a consistent, predictable regulatory response. • Establish a formal approach with COE to plan joint initiatives designed to maximize the long-term protection of designated priority wetlands. What Action Was Taken The final audit report (1100434) was issued to the Assistant Administrator for Water on September 30, 1991. A response to the final audit report is due by December 24, 1991. In responding to our draft report, the Assistant Administrator disagreed with some of our findings and recommendations. The Assistant Administrator stated that (1) EPA’S wetlands program encompassed more than the regulatory approaches emphasized in the audit report, (2) positions taken regarding program accountability were premised on a management philosophy that she believed was inconsistent with current Agency policy, and (3) the report reflects a misperception of EPA’S role in wetlands enforcement. However, these disagreements were generally not supported by facts, documentation, or sources. EPA Region 8 Created A Personal Services Relationship With Support Contractor Problem Region 8 and EPA Headquarters did not follow EPA and Federal guidance and regulations in managing support contracts with Computer Sciences Corporation (CSC). As a result, contractor employees worked without clearly defined tasks or criteria for measuring their performance and created a personal services relationship between EPA and CSC. We Found That EPA Region 8 and Headquarters did not implement and enforce sound contract management controls for administering CSC contract activities. CSC employees performed without approved, adequate statements of work. Region 8 personnel generally were not knowledgeable of Erecting wood duck nesting box on edge of deep water marsh in Minnesota (photo by Russ Jongewaad, USDA). 12 Office of the Inspector General Report to the Congress ------- contract terms and were not held accountable for performing contractor oversight. The regional and national delivery order project officers (DOPO) did not develop sufficient plans to monitor contract progress and time charges. Region 8’s administration of the CSC contracts created a personal services relationship between EPA and CSC contract employees, thereby violating federal civil service laws and Federal Acquisition Regulations. DOPOs prepared broad statements of work which were not adequate to ensure that CSC would perform needod tasks and services. Region 8 personnel extensively supervised CSC employees to ensure they performed tasks and services as intended. CSC employees were commingled with Region 8 employees, were furnished principal tools and equipment; and performed ongoing services which lasted more than 1 year and were expected to continue indefinitely. Region 8 regarded CSC employees as an integral part of the Region’s organization in carrying out EPA’s mission. The Region inappropriately paid CSC for more hours than its employees worked, including time spent attending EPA functions, basic computer training, and contractor meetings, ignoring Agency prohibition against paying for such charges. In addition, Region B helped CSC maximize profits by improperly upgrading labor categories and CSC employees. As a result, EPA incurred $110,354 in unnecessary charges in fiscal years 1990 and 1991. We Recommended That The Assistant Administrator for Administration and Resources Management: Require DOPOs to prepare statements of work which contain measurable performance criteria and develop and implement appropriate written plans to monitor contractor progress and associated costs. • Require the DOPOs to reevaluate Region 8’s labor categories for each CSC employee and reclassify positions to meet job skills required by the Region. • Ensure Region 8 has adequate EPA staff available to perform essential government services and eliminate even the appearance of contractor employees being improperly used for personal services. The Regional Administrator, Region 8: • Include contract administration duties in the performance standards of appropriate employees and require employees who provide contractor work assignments or monitor contract activities to attend the contract administration and project officer training courses. • Discontinue all practices which give the appearance of EPA employees supervising CSC employees. What Action Was Taken The final audit report (1100441) was issued to the Acting Assistant Administrator for Administration and Resources Management and the Regional Administrator, Region 8, on September 30, 1991. A response to the final audit report is duo by December 29, 1991. The Agency and the Region generally agreed with the findings and the recommendations in the report and have committed to take corrective actions. Stronger Enforcement And Oversight Needed For Region 8 RCRA Program Problem EPA Region B had not provided adequate oversight of Resource Conservation and Recovery Act (RCRA) enforcement activities nor did states assess monetary penalties that considered the severity of the RCRA regulation violation or the economic benefit of noncompliance. Background RCRA established the statutory framework for regulating solid and hazardous wastes. EPA may authorize States to develop and implement hazardous waste programs. The Agency administers RCRA functions in states which it has not authorized to administer RCRA programs. As of September 1990, Region 8 had authorized all States in the Region, except Wyoming, to administer RCRA programs. We Found That States had not implemented strong enforcement programs. EPA oversight was not adequate to disclose program deficiencies or to correct deficiencies. States had not imposed strong penalties in accordance with the requirements established in State/EPA agreements or always documented the basis for proposed penalties or negotiated adjustments. As a result, violators could gain financially from noncompliance with the statutory and regulatory RCRA requirements. In 11 instances, Utah and Colorado assessed penalties that were an estimated $233,720 less than justified and did not consider the economic benefit of noncompliance. Montana did not consider the severity of the violations in calculating the two penalties it assessed and later reduced and suspended the penalties by $1.5 million. As a result, violators did not correct problems and inspectors repeatedly found the same hazardous conditions. Region 8 had not provided sufficient oversight of State RCRA enforcement activities to ensure that States adhered to the Federal RCRA enforcement program. Reviewers did not always report program review results and did not establish foUowup systems to ensure corrective action. We Recommended That The Regional Administrator, Region 8: • Require comprehensive regional oversight to ensure States comply with RCRA enforcement and penalty regulations and policy. o Encourage States to develop a more aggressive policy for taking enforcement actions within established guidelines. What Action Was Taken The final audit report (1100428) was issued to the Regional Administrator, Region 8, on September 30, 1991. A response to the final report is due by December 19, 1991. The Regional Administrator disagreed with some individual findings and recommendations in the draft report, but agreed that the Region could improve its administration of the RCRA program and has committed to taking corrective actions. April 1, 1991 through September 30, 1991 ------- Problems Continued To Plague State Vehicle Inspection And Maintenance Programs Problem Over the years, EPA’. Office of Mobile Sources (OMS) has identified serious and continuing weaknesses in state vehicle inspection and maintenance (l/M) programs. Although EPA recommended corrective actions, in many instances, the states had not implemented them. Background Motor vehicles are major sources of carbon monoxide and ozone two pervasive air pollutants. Motor vehicles emit unburned hydrocarbons and oxides of nitrogen which react together in the presence of sunlight to form ozone. Carbon monoxide impairs the body’s ability to transport oxygen to the brain and body cells. Ozone, a severe irritant, damages lung tissue, aggravates respiratory disease, and makes people more susceptible to respiratory infections. Vehicle l/M programs are designed to ensure the effectiveness of emission control systems on motor vehicles. The IIM programs require periodic inspection of motor vehicles and emission related maintenance. Currently, 101 urban areas in 35 States and the District of Columbia have tIM programs. We Found That Fifty-two of 75 inspectors (69 percent) in four states inspected by the Office of Mobile Sources (OMS) improperly tested and passed vehicles that OMS had intentionally set to fail the emission test. • IIM programs in 2 of 6 states reviewed were not capturing necessary test data so that OMS could determine if programs were operating effectively. • Equipment used to test vehicles in 5 of 6 states inspected by OMS was often unreliable because of obsolescence or improper calibration. • Training of l/ 1 personnel (inspectors and auditors) in 5 of 6 states inspected by OMS was inadequate, resulting in improper testing and monitoring of l/M activities. • State enforcement action against noncomplying station owners and inspectors in 5 of 6 states inspected by OMS was ineffective and did not deter program violations. We Recommended That The Assistant Administrator for Air and Radiation improve the vehicle Ii? 1 programs by: • Strengthening controls over decentralized state l/M programs; • Improving quality assurance of state l/M programs; • Establishing minimum training requirements for inspectors and state auditors; and • Providing specific guidance to states on acceptable enforcement programs. What Action Was Taken In his response to the draft report, the Director, OMS, generally agreed with our findings and recommendations and indicated that OMS was in the process of revising the guidance on IIM programs in accordance with the Clean Air Act, as amended. The final audit report (1100359) was issued to the Assistant Administrator for Air and Radiation on August 16, 1991. A response to the final report is due by November 14, 1991. Testing for motor vehicle emission control system’s effectiveness. Greater Efforts Needed To Improve The Delaware And Inland Bays Estuaries Problem Region 3’s current efforts under the National Estuary Program (NEP) are repetitious of past attempts to improve the Delaware and Inland Bays Estuaries, and the State of Delaware had not enforced the Clean Water Act against polluters that discharge into these estuaries. Background The NEP was established by the 1987 amendments to the Clean Water Act (CWA) as a nationwide demonstration program that targets selected estuaries of national significance for protection and improvement. We Found That Region 3’s efforts to implement the NEP have restated the requirements of the relevant statutes and regulations that the Agency should already be enforcing against polluters and has not implemented many of the recommendations made in past studies because the desired solutions were either expensive or unpopular. Further, Region 3 did not always aggressively enforce the existing statutes and regulations against polluters. Also, the State of Delaware did not take adequate enforcement actions against facilities that violated their National Pollutant Discharge Elimination System perm ifs. Region 3 did not take enforcement action against those violators when the State failed to do so. 14 Office of the Inspector General Report to the Congress ------- We Recommended That The Regional Administrator, Region 3: Review previous studies that relate to the Delaware and Inland Bays estuaries to analyze impacts and reevaluate the feasibility of implementing their recommendations. Ensure that other Region 3 program offices more effectively support the NEP program to ensure that the two estuary programs are not required to complete tasks that are the responsibility of others. • Implement an agricultural initiative to address non-point source pollution that affect the Inland Bays estuary program. • Assure that more timely and aggressive enforcement is taken against polluters. • Ensure that the State of Delaware assesses penalties against violators which are significant enough to deter noncompliance and initiate direct Federal enforcement action when the state fails to pursue violators. What Action Was Taken The final report (1100422) was issued to the Regional Administrator, Region 3, on September26, 1991, anda response is due by December 26, 1991. in response to the draft report, the Regional Administrator generally did not agree with our audit report. He stated that many actions have been taken by EPA, states, and local agencies to better focus, accelerate, or supplement various programs to solve priority estuary problems and that the QIG report recommendations are part of the actions being implemented. Also, he suggested that we recognize their significant accomplishments over the years. Construction Grant Obligations Overstated By $49 Million Problem EPA regional offices did not take timely action to deobligate nearly $49 million of construction grant funds that could have been used for needed projects. Background Title Il of the Federal Water Pollution Control Act, as amended, authorized EPA to award grants to communities for constructing wastewater treatment projects. Since creation of the program in 1972, the Agency has provided over $50 billion to assist in constructing these projects. Although 1990 was the last year funds were authorized for Title II grants, more than 5,000 grants representing nearly $32 billion have not been closed out. In 1987, the program was revised to assist communities in constructing new and upgraded wastewater treatment facilities through grants to State Revolving Funds (SRF). We Found That Nearly $49 million of the $433 million of unliquidated construction grant obligations reviewed in eight regions were invalid and should have been deobligated. Also, part of approximately $82 million of additional unliquidated obligations should be deobligated when the grants are administratively complete or terminated. EPA has issued numerous policies and procedures encouraging timely construction of wastewater treatment facilities, administrative completion of construction grants, and timely deobligation of excess funds. For examp’e, when final payment requests are not submitted timely, the regions are required to inform grantees that their last payment request will be treated as the final one unless a final payment request is received within 90 days. However, regional officials did not always follow these policies and procedures. As a result, funds not needed to complete projects remained obligated when those funds could have been used to fund (1) grants to states to capitalize SRFs, (2) costs of states’ closing out their traditional construction grant programs, and (3) overruns on existing traditional construction grants. We Recommended That The Acting Assistant Administrator for Administration and Resources Management and the Assistant Administrator for Water have all regional administrators: (1) review their respective grants identified in our sample and deobligate unneeded funds, (2) notify the Assistant Administrators of the actions taken, and (3) confirm that funds are being deobligated in accordance with Agency policy as part of fiscal 1992 internal control reviews. What Action Was Taken The final audit report (1100426) was issued to the Acting Assistant Administrator for Administration and Resources Management and the Assistant Administrator for Water on September 30, 1991. A response to the final audit report is due by December 29, 1991. The Offices of Administration and Resources Management and Water told us that the regions have completed their reviews of the grants cited in the report and are taking the necessary action to deobligate the unliquidated obligations. 15 April 1, 1991 through September 30, 1991 ------- Construction Grants EPA’S waste water treatment works construction grants program is the largest single program the Agency administers. Under the provisions of Public Law 92-500, as amended, the Agency is authorized to make grants covering 55 percent and, in some instances, up to 85 percent of the eligible costs of constructing wastewater treatment facilities. During this semiannual period, $356 million was obligated on 105 new awards and 420 increases to existing grants. As of September 30, 1991, there were 997 active construction grants, representing $6 billion in Federal obligations. Amendments to the construction grants program are covered in Title I! of the Water Quality Act of 1987. Section 212 creates a new Title VI in the Clean Water Act, which addresses the process of phasing out the construction grants program by providing incentives for development of aftemative funding mechanisms by the States. The new Title VI charges EPA with developing and implementing a program to provide grants to capitalize State revolving funds for finandng wastewater projects. During this semiannual period, $1.4 billion was awarded for 38 continuation grants. As of September 30, 1991, EPA had obligated $4.8 billion to 50 States and Puerto Rico under the State Revolving Fund program. 16 Office of the Inspector General Report to the Congress ------- Los Angeles Claimed $90.3 Million In Questioned Costs ( iost ies Questioned 0 20 40 60 80 100 120 Mtlions of Dollars Federal Non-Federal Problem The City of Los Angeles, California, claimed $10,871,601 of Ineligible construction, engineering, and force account costs. An additional $79,434,029 of unreasonable project costs were questioned for a facility not being used for its intended purpose. We Found That EPA awarded nine grants totaling $101,520,254 to the City of Los Angeles for various projects, including the design and construction of a wet weather water reclamation plant; the planning, design and construction of a sludge processing and disposal system; portions of the Hyperion Energy Recovery System; and various tank modernization projects. We questioned $10,871,601 of the grantee’s final claim as ineligible, including: • $5,941,819 of engineering, force account and construction costs which were unapproved as outside the scope of the project or were inadequately documented; • $4,417,052 of grantee force account costs incurred without approval prior to the award of the grants; • $444,318 of force account costs allocable to the ineligible portions of the projects; and • $68,412 of excessive indirect costs based on provisional rates which were in excess of the approved indirect cost rates. I We also questioned $79,434,029 of project costs as unreasonable, $57,928,957 of which was claimed for the underutilized Tillman Reclamation Plant. Although the plant was designed and constructed as a reclamation plant, at an increased level of expenditure and funding, it was not being used to reclaim any wastewater. We Recommended That The Regional Administrator, Region 9, not participate in the Federal share of ineligible costs ($8,323,999); determine the eligibility of the federal share of the unreasonable costs ($60,076,899); and recover the applicable amount from the grantee. What Action Was Taken Three audit reports (1300112, 1300117, and 1300119) were issued to the Regional Administrator, Region 9, on September 25 and 30, 1991. Responses are due by December 29, 1991. Monterey, California, Claimed $58.6 Million Of Ineligible And Unreasonable Costs I Monterey Questioned 0 20 40 60 80 100 Milbons of Dollars roderal Non-Federal Problem The Monterey Regional Water Pollution Control Agency, Monterey, California, claimed $7,491,007 of ineligible construction, engineering, administrative, and other costs. An additional $51,118,958 of unreasonable project costs were questioned. We Found That EPA awarded five grants totaling $58,298,265 to the Monterey Regional Water Pollution Control Agency for the planning and design of the North Monterey County treatment facility and for constructing interceptors, pump stations, treatment plant modifications, an ocean outfall, and an agricultural irrigation demonstration project. We questioned $7,491,007 of the grantee’s claim as ineligible, including: • $3,776,328 of construction, engineering, administrative, and other costs in excess of approved amounts; • $1,558,787 of construction, engineering, and other costs which were questioned in a prior audit and either sustained or deferred by EPA, but which had not been deleted from the claim; • $901,481 of engineering and other costs for redesign work, in excess of actual amounts, due to grantee mathematical error; or not benefiting the project; • $370,357 of administrative, force account, and other costs allocable to the ineligible portion of construction; • $359,368 of administrative and force account costs incurred for facility operation and maintenance; • $342,362 of revenue generated from equipment sales, insurance proceeds, sublease of facilities and contributions from other Federal facilities which were not credited to the grant; and • $283,518 of engineering costs incurred after the construction completion date. Also, the grantee did not claim $101,194 of eligible engineering and administrative costs which we deducted from total ineligible costs. Further, we questioned $51,118,958 of project costs as unreasonable. The audit noted several matters, including flows received from Federal facilities and other municipalities, which indicated that EPA’s share of project costs may be significantly overstated. We Recommended That The Regional Administrator, Region 9, not participate in the Federal share of ineligible costs ($5,621,855); determine the eligibility of the Federal share of the unreasonable costs ($38,348,260); and recover the applicable amount from the grantee. What Action Was Taken The audit report (1300118) was issued to the Regional Administrator, Region 9, on September 30, 1991. A response is due by December 29, 1991. Grantee’s $36.8 Million Project Claim Questioned After 12 Years Of Violating Discharge Limitations Gary Audited Questioned 0 10 20 30 40 50 Millions of Dollars Federal Non-Federal L 1 Problem The Gary, Indiana, Sanitary District (GSD) claimed $36,853,715 of costs for a wastewater treatment plant that has violated its National Pollutant Discharge Elimination System (NPDES) permit sInce 1978. We Found That EPA awarded two grants to GSD for modification of an existing wastewater treatment plant and the training of facility April 1, 1991 through September 30, 1991 17 ------- operators. Because of its inability to properly operate and maintain the modified plant, GSD has consistently violated its NPDES permit since 1978. EPA obtained a final Consent Decree in 1983 requiring GSD to comply with the effluent limitations specIfied in Its permit. In 1984, the United States filed a Motion to Enforce the Consent Decree because the grantee was not complying. EPA filed an additional complaint in 1986 against the grantee for violations of the Toxic Substances Control Act (TSCA), charging that excessive concentrations of PCBs were found in the plant’s sludge. To settle the Motion to Enforce and the TSCA complaint, EPA entered into a modified Consent Decree in 1987 requiring several actions by GSD, including the hiring of qualified employees to operate and maintain the plant. At the completion of our review, GSD still had not complied with the modified Consent Decree. Therefore, we questioned as ineligible the grantee’s total claimed costs of $36,853,715. Should the grantee eventually comply with the Consent Decree, we still questioned $2,492,223 of that claim as ineligible, including: • $956,522 of unjustified costs associated with rescheduling work under a change order; • $687,927 of project inspection and architectural engineering fees, overhead, profit, taxes, and bond premium costs allocable to other ineligible costs; • $571,594 of additional construction costs and engineering fees outside the scope of the project, claimed but not incurred, or exceeding allowable amounts; and • $276,180 of costs billed twice and depreciation on fully depreciated equipment. We also questioned $1,421,332 of unsupported project inspection and architectural engineering fees. We Recommended That The Chief, Financial Management Branch, Region 5: Ensure the grantee operates and maintains the plant property and meets its NPDES permit limitation. If the grantee does not take the necessary action, the grants should be annulled. • If the grantee properly operates and maintains its plant, not participate in the Federal share of ineligible costs ($1,869,167); determine the eligibility of the Federal share of unsupported costs ($1,066,000); and recover the applicable amount from the grantee. What Action Was Taken The final audit reports (1400037 and 1400038) were issued to the Chief, Financial Management Branch, Region 5, on September 9, 1991. Responses are due by December 9, 1991. Clark County, Nevada, Claimed $32.9 Million Of Questioned Costs For Underutilized Facility Millions 01 Dollars — Federal Problem Non-Federal The Clark County Sanitation District (District), Nevada, claimed $6,851,921 of ineligible costs and about $26 million of unnecessary, unreasonable, or unsupported costs for a wastewater treatment plant used at only about half of its capacity. We Found That EPA awarded a grant, as amended, totaling $62,454,745 to the District for constructing a wastewater treatment plant for the greater Las Vegas area. We questioned $6,851,921 of the grantee’s claim as ineligible, including: • $5,335,437 of legal fees to defend a claim by the construction contractor which resulted from grantee caused delays; • $806,789 of project costs paid by the United States Air Force as its share of the project for treatment of flows from Nellis Air Force Base; • $263,318 of costs for constructing an electrical substation that were refunded by the Nevada Power Company and miscellaneous income that were not credited to the grant; • $207,687 of administrative costs incurred for operation and maintenance, excessive indirect costs and costs related to a contractor’s failure to perform; • $152,708 resulting from the grantee’s mathematical error; and • $85,982 of construction and engineering costs in excess of approved amounts or ineligible per grantee records. We also questioned $688,395 of inadequately supported engineering, equipment, and administrative costs. The grantee also claimed $25,390,310 of unnecessary/unreasonable costs related to the underutilized and unused portions of the wastewater treatment plant. Only 56 percent of the plant capacity was in use and significant segments of the facility, such as the filtration system, were totally unused. We Recommended That The Regional Administrator, Region 9, not participate in the Federal share of ineligible costs ($5,138,940); determine the eligibility of the Federal share of unsupported and unnecessary/unreasonable costs ($19,559,029); and recover the applicable amount from the grantee. What Action Was Taken The audit report (1100436) was issued to the Regional Administrator, Region 9, on September 30, 1991. A final response is due by December 31, 1991. Philadelphia Claimed Over $10.3 Million Of Questioned Costs Audited Questioned 0 20 40 60 80 100 120 140 160 Millions 0 f Dollars — Federal Problem Non-Federal The City of Philadelphia claimed $9,552,760 of ineligible force account, engineering, construction, indirect and Federal facility share costs. An additional $801546 of unsupported, unnecessary and unreasonable costs were also questioned. We Found That EPA awarded eleven grants totaling $142,829,885 to the City of Philadelphia to upgrade the Southeast Water Pollution Control Plant to meet National Pollutant Discharge Elimination System permit requirements. We questioned $9,552,760 of the grantee’s claimed costs as ineligible, including: • $3,645,288 of costs which exceeded the grant ceiling; I Office of the Inspector Genera) Report to the Congress ------- • $1,831,188 of consulting and force account engineering costs incurred after the construction completion date or outside the project’s scope; • $1,796,394 of Federal facility share costs which should be paid by the U.S. Navy; • $1,721,811 of ineligible construction change orders and costs previously disallowed by the State; • $332,968 of contractor and City indirect cost rates applied incorrectly; and • $225,111 of consulting and force account engineering services allocable to the ineligible portion of the project. We also questioned $357,094 for force account, engineering services, and indirect costs that lacked adequate documentation. In addition, we questioned as unnecessary $342,213 of construction costs because the City did not aggressively pursue a potential civil claim for damages from contractors previously implicated in a bid rigging scheme. Engineering costs of $102,239 were determined to be unreasonable because they exceeded generally accepted guidelines. Nearly $7.7 Million Of Questioned Costs Claimed By Indianapolis, Indiana Problem The City of Indianapolis, Indiana, (City) claimed $5,245,844 of ineligible engineering, project inspection, construction management, and other costs. An additional $2,424,093 of unsupported costs were questioned. We Found That EPA awarded nine grants for a project the City claimed costs totaling $222,273,857. The grants provided funds to plan and modify the Southport and Belmont wastewater treatment plants. The grantee claimed ineligible costs of $5,245,844, including: We Recommended That The Chief, Financial Management Branch, Region 5, not participate in the Federal share of ineligible costs ($3,565,238); determine the eligibility of the Federal share of the unsupported costs ($1,589,503); and recover the applicable amount from the grantee. What Action Was Taken The audit report (1400047) was issued to the Chief, Financial Management Branch, Region 5, on September 24, 1991. A response is due by December 24, 1991. We Recommend That The Regional Administrator, Region 3, not participate in the Federal share of ineligible costs ($7,164,570) and determine the eligibility of unsupported, unnecessary and unreasonable costs ($601,160). What Action Was Taken The final report (1300116) was issued on September 26, 199 1, to the Regional Administrator, Region 3. A response is due by December 26, 1991. • $3,193,548 of project inspection and construction management costs incurred after the latest EPA-approved construction completion date; • $1,707,539 of engineering, force account, and administrative costs claimed in excess of incurred amounts; • $303,105 of engineering, administrative, and project inspection costs applicable to ineligible construction; and • $41,652 of equipment costs for car and truck purchases which are ordinary operating expenses. We also questioned $2,424,093 of unsupported project inspection and engineering costs. Indianapolis Audited 1] Questioned 0 50 100 150 200 250 Millions of Dollars FederaJ Non-Federal [ April 1, 1991 through September 30, 1991 19 ------- The Superfund program was created by the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA). The Act provided a $1.6 billion trust fund to pay for the costs associated with the cleanup of sites contaminated with hazardous waste. Taxing authority for the trust fund expired on September 30, 1985. For more than a year, the Superfund program operated at a reduced level from carryover funds and temporary funds provided by Congress. On October 17, 1986, the Superfund Amendments and Reauthorization Act of 1986 (SARA) was enacted. It provides $8.5 billion to continue the program for 5 more years and makes many programmatic changes. On November 5, 1990, the Omnibus Budget Reconciliation Act of 1990 was enacted, authorizing appropriations for 3 additional years and extension of the taxing authority for 4 additional years. The parties responsible for the hazardous substances are liable for cleaning up the site themselves or reimbursing the Government for doing so. States in which there is a release of hazardous materials are required to pay 10 percent of the costs of Fund-financed remedial actions, or 50 percent if the source of the hazard was operated by the State or local government. The enactment of SARA increased the audit requirements for the Inspector General. In addition to providing a much larger and more complex program for which the OIG needs to provide audit coverage, SARA gave the Inspector General a number of specific responsibilities. Mandatory annual audit areas include: • Audit of all payments, obligations, reimbursements, or other uses of the Fund; • Audit of Superfund claims; • Examination of a sample of agreements with States carrying out response actions; and • Examination of remedial investigations and feasibility studies. The Inspector General is required to submit an annual report to the Congress regarding the required Superfund audit work, containing such recommendations as the Inspector General deems appropriate. The fourth annual report, covering fiscal 1990, was issued on September 25, 1991. In addition, the EPA Administrator is required to submit a detailed annual report to the Congress on January 1 of each year on the progress achieved in implementing CERCLA during the preceding fiscal year. The OIG is required to review this report for reasonableness and accuracy, and the Agency is required to attach the result of the OIG review to the Agency’s annual report. As of September 30, 1991, the OIG had not received a final version of the Agency’s report for fiscal 1990 for review. 1 ,::-1 tc1 : ‘V. Superfund Program 20 Office of the Inspector General Report to the Congress ------- EPA Unnecessarily Delays Responsible Parties From Cleaning Up Hazardous Sites Problem Completions of Superfund cleanups were unnecessarily delayed by untimely review of responsible parties’ (RP) work products, failure to enforce stipulated penalties against RPs for noncompliance with voluntary agreements, and inadequate monitoring of contractors. Background EPA may negotiate an agreement with responsible parties (RP) that are wilhng and financially able to clean up a site. EPA oversees the RPs’ activities. RPs are required to submit certain products to EPA, such as project site plans, quality assurance plans and test results prior to site cleanup. EPA uses Technical Enforcement Support (TES) contractors If technical assistance is needed in performing oversight. We Found That Superfund cleanups in 3 of 4 EPA regions were unnecessarily delayed after EPA reached settlement with RPs, possibly further degrading the environment. At 24 of 39 sites reviewed, EPA’s review and approval of RP documents and plans took up to 36 months due to lack of guidelines for completing reviews; unauthorized extensions; multiple revisions of documents; lack of a milestone tracking system; personnel turnover; and RPs not being responsive. Also, EPA regions were not assessing stipulated penalties for RPs noncompliance with post-settlement milestone dates. For 15 sites in noncompliance, the regions assessed penalties against BPs in only three cases totaling $45,000, failing to assess potential penalties of $4,855,500 against RPs in seven other cases. In two other cases, potential judicial sanctions against the RPs could have totaled $8,125,000, if EPA had referred t em for enforcement action. Instead, the regions generally limited their enforcement actions to verbal negotiations or warning letters, seeking penalties only in extreme cases because they believed such actions might inhibit cleanup progress at the sites. Also, EPA was not adequately monitoring its TES contractors hired to oversee RP cleanups by conducting quality assurance audits, contractor office reviews, and field oversight reviews. As a result, EPA had limited assurance that the TES contractors were performing required work and that their tests and records were reliable and accurate. We Recommended That The Assistant Administrator for Solid Waste and Emergency Response: • Develop and ensure compliance with guidance, including time frames for reviewing and approving RPs’ submissions. • Develop and implement a standard post-settlement automated tracking system. • Aggressively monitor TES contractors’ performance by establishing guidelines for scheduling, performing, and documenting periodic quality assurance audits, contractor office reviews, and field oversight visits. The Assistant Administrator for Enforcement: • Issue guidance for aggressive pursuit of stipulated penalties when RPs are generally in noncompliance with settlement document requirements. What Action Was Taken The final audit report (1100431) was issued to the Assistant Administrator for Solid Waste and Emergency Response and the Acting Assistant Administrator for Enforcement on September 30, 1991. A response to the audit report is due by December29, 1991. EPA generally agreed with the findings and recommendations in the draft report and had initiated corrective actions. Problems With Superfund Accounting Continue Problem EPA’s accounting for Superfund costs has been improved, but as previously reported, financial reporting and accounting for disbursements, obligations, and receivables contain inaccuracies, Background The Comprehensive Environmental Response, Compensation, and Liability Act of 1980, as amended, requires an annual audit of all payments, obligations, reimbursements, or other uses of the Hazardous Substance Superfund (Superfund). For fiscal 1990, EPA reported $1.6 billion of obligations and $1.1 billion of disbursements under the Superfund. We Found That The Integrated Financial Management System (IFMS), implemented in March 1989, has not produced adequate, reliable financial management reports, a condition previously reported. EPA continues to rely on its previous accounting system to provide financial reports to EPA management. In addition, the Agency’s accounting procedures have not been updated since IFMS was implemented in March 1989. While EPA’s Schedule of Obligations and Disbursements were generally fairly presented, disbursements for salaries were understated by $11.3 million. In addition $13.8 million of nonpayroll obligations and $8 million of nonpayroll disbursements were not adequately supported or resulted from accounting errors. Accounting deficiencies also led to inaccuracies in EPA accounts receivable records. There was an unreconciled difference of $18.7 million between the general ledger control account and the subsidiary ledger. Further, of the receivables, $4.6 million were not recorded timely; $562,288 were not recorded in the correct fiscal year; thirteen were delinquent but not assessed interest of $181,468; and $2.3 million of collections were not recorded against the correct receivables. Without accurate records, EPA cannot effectively manage or pursue accounts receivable. We Recommended That The Acting Assistant Administrator for Administration and Resources Management: • Continue corrective actions underway for improving EPA’s accounting system, including the effective management of accounts receivable. • Ensure that all financial policy and procedures guidance for recording and supporting transactions in IFMS and for reconciling data in internal and external records and reports are updated. • Review and resolve all questioned obligations and disbursement transactions and make appropriate adjustments. What Action Was Taken The final audit report (1100385) was issued to the Acting Assistant Administrator for Administration and Resources Management on September 16, 1991. A response to the final report is due by December 15, 1991. In response to our draft report, the former Assistant Administrator either agreed with our recommendations or proposed acceptable alternative actions. 2t ------- Special And Early Warning Reviews This section In our semiannual report describes significant and potential findings, deficiencies, and recommendations which have been Identified through evaluations, analyses, projects, and audits. These reviews are intended to help Agency managers correct problems and recognize the potential for savings before resources are fully committed. Special Reviews Special reviews are narrowly focused studies of programs or activities providing management a timely, in formative, independent picture of operations. Special reviews are not statistical research studies or detailed audits. Rather, they are information gathering studies that Identify Issue areas for management attention. Inefficient Contracting Practices May Cost EPA An Extra $10.7 Million For Automatic Data Processing (ADP) Equipment And Services Problem EPA could pay up to $8.4 million over decreasing market prices for microcomputer workstations and other ADP equipment by not modifying an interim contract and delaying a competitive award. EPA could also pay the contractor $2.3 million more than actually incurred for operating expenses. Background In April 1989, EPA planned to award two competitive contracts for 18,000 workstations and other ADP equipment and services at an estimated cost of $285 million. Because of delays in the procurement and an increased demand for workstations, EPA altered its procurement strategy by splitting the requirement equally between a small and disadvantaged firm under the Small Business Administration’s (SBA) 8(a) program and another firm to be selected competitively. The 8(a) procurement was subsequently reduced to 5,640 workstations estimated to cost $67.5 million, and a negotiated firm-fixed price, indefinite delivery/indefinite quantity contract was awarded in July 1990. Also, the value of the requirement to be made competitively was reduced to $206 million. We Found That EPA was delayed in competitively awarding a contract to procure workstations and other ADP equipment having an estimated value of $206 million. (Even if awarded in December 1991, as planned at the completion of our review in July 1 991, the competitive award would be 19 months overdue.) As a result, assuming full contract performance, EPA could incur excess costs of as much as $8.4 million over the life of an interim contract awarded to a small and disadvantaged firm for such equipment. EPA did not use all available means to modify the contract to take advantage of decreasing market prices after the interim contract’s award. Also, EPA did not perform a sufficiently thorough analysis of cost data provided by the contractor during negotiations and could pay $2.3 million more than the contractor actually incurs for certain expenses, such as freight, rent, and insurance. Further, although no regulations were violated,, the $67.5 million award to one firm deprived EPA of the opportunity of allowing other qualified 8(a) firms to participate in the acquisition, thereby better advancing the 8(a) program objectives. We Recommend That The Acting Assistant Administrator for Administration and Resources Management: • Issue the competitive contract for the workstations and other ADP equipment as soon as possible, but not later than December 1991. • Monitor ADP equipment market prices, renegotiate individual contract prices for items that have decreased significantly, and not buy individual items of ADP equipment if the interim contractor does not make equitable price adjustments. • Strengthen procedures to ensure that costs agreed to during negotiations are based on current cost and pricing data. • Improve the Federal Managers’ Financial Integrity Act process by establishing an event cycle specific to the 8(a) pre.award process and contract management. What Action Was Taken The final special review report (1400060) was issued to the Acting Assistant Administrator for Administration and Resources Management on September 30, 1991. In response to the draft report, the Acting Assistant Administrator agreed with some of our recommendations. We requested that he reconsider the remaining recommendations. A response to the final report is due by December 29, 1991. -I W r 1 22 Office of the Inspector General Report to the Congress ------- EPA Made Unnecessary And Improper Procurements Through Its Waterside Mall Lessor Problem EPA’s Facilities Management and Services Division (FMSD) circumvented Federal acquisition regulations and Agency procedures to make improper procurements through its Headquarters lessor, resulting in unnecessary costs in excess of $138,500. We Found That FMSD used the Agency’s Waterside Mall lessor to improperly obtain commercial goods and services, ignoring Federal acquisition regulations requirements for sole-source justification, competition and determinations of price reasonableness. Unnecessary “middleman” (profit and overhead) payments of $132,900 were made to the lessor that could have been avoided by procuring directly from commercial vendors. For example: • $100,000 paid to the lessor for end of fiscal year carpet purchases; • $31,600 paid to the lessor for systems furniture installation and poster framing; and • $1,300 paid to the lessor for towels and laundry service, planters and a microwave oven. The lessor was also paid $5,600 for carpet cleaning services that had already been paid to the Internal Revenue Service in response to a Notice of Levy against the vendor. Convenience and speed took precedence over regulatory requirements. FMSD used the lessor to make many of those purchases when the Agency’s Procurement and Contracts Management Division (PCMD) refused. However, the Agency had not clearly defined or limited the use of FMSD’s purchase authority, nor implemented adequate internal controls over it. We Recommended That The Assistant Administrator for Administration and Resources Management: • Assign responsibility for all FMSD procurements to the Director, PCMD. • Instruct the Director, PCMD, to review and ratify or deny all past purchases made by FMSD, and take appropriate action for those purchases that cannot be ratified. • Recover the $5,600 duplicate payment for carpet cleaning services. What Action Was Taken The special review report (14 00024) was issued to the Assistant Administrator for Administration and Resources Management on June 20, 1991. In his September 25, 1991, response, the Acting Assistant Administrator indicated that significant changes will be made to their procurement procedures. Laboratories Not Properly Targeted For Inspections To Detect Violations Problem EPA failed to identify and take enforcement action against laboratories that violated good laboratory practices (GLP) regulations issued under the Federal Insecticide, Fungicide, and Rodenticide Act (FIFRA). We Found That EPA did not assess any civil or criminal penalties for any FIFRA GLP violations during the first 7 years of the program. This sent a message to the industry that a GLP violation results in little or no penalty for non-compliance. Reasons for the lack of enforcement against violators of the regulations included a general emphasis on outreach and the GLP program’s lack of: (1) a strong enforcement authority under FIFRA, (2) a specific GLP enforcement policy for specific violations ol the GLP regulations, including a detailed penalty policy, and (3) standards necessary to accept or reject laboratory studies for specific GLP violations. Due to ineffective targeting, the same 200 laboratories have been inspected repeatedly although they are not necessarily the laboratories with the majority of problems. We Recommended That The Assistant Administrator for Pesticides and Toxic Substances: • Seek legislation that specifies a violation of the GLP regulations is a FIFRA violation and provides stronger penalties for FIFRA violators. • Require the completion of a GLP enforcement policy that prioritizes specific GLP violations and provides for penalties to be determined based on the severity of the violation. • Develop standards for accepting or rejecting laboratory studies based on violations of GLP regulations. • Target for inspection medium- and small-sized laboratories that have not been previously inspected. In addition, examine the feasibility of extending the inspection cycle for laboratories that have consistently passed GLP inspections. What Action Was Taken The special review report (1400064) was issued to the Assistant Administrator for Pesticides and Toxic Substances on September 30, 1991. A response to the final report is due by December 29, 1991. In responding to the draft report, the Assistant Administrator generally agreed with our findings and recommendations. AprU 1 1991 through Seplember 30, 1991 23 ------- Construction Grant Early Warning System This program is designed to identify potential problem construction projects early in their life cycle so that EPA management can take appropriate corrective action. The long-range goal of the construction grants program is to reduce the discharge of municipal wastewater pollutants to improve water quality and protect public health. EPA provides grants to municipal agencies to assist in financing the construction of waste water treatment works, a process which takes 2 to 10 years to complete. Because audits are generally performed after the project is complete, problems which affect the efficient design, construction, management; or operation of a treatment plant are not disclosed until thousands or millions of dollars have been spenL The OlG early warning system reviews projects before construction begins to identify problems and preclude the ineffective expenditure of funds. Our reviews focus on certain indicators and attributes that can suggest the likelihood of a potential problem. Arizona And Nevada Had Not Matched $22 Million Of EPA’s Construction Grant Funds Problem Arizona and Nevada had not provided required matching funds for implementing their State Revolving Fund (SRF) programs, resulting in $22.2 million of Federal grant funds for construction of wastewater treatment plants remaining idle. We Found That Region 9 awarded SRF capitalization grants to Nevada and Arizona before those states were financially capable of operating SRF programs. As a result, $10,912,200 of fiscal 1989 and $11,294,300 of fiscal 1990 Federal grant funds were not available for loans to state and local governments for constructing wastewater treatment plants because Arizona and Nevada had not passed legislation to provide the necessary matching funds to operate their SRF programs. If Nevada does not meet its September 30, 1991, deadline for funding its state match for fiscal 1989, $4,577,200 of fiscal 1989 grant funds will be available for reallocation to other states. If Arizona fails to meet its November 5, 1991, deadline, an additional $6,335,000 will be available for reallocation. In addition, Nevada did not have written policies and procedures for approving the eligibility of loan recipients or for monitoring loan repayments; had not established a cash management policy; and did not have effective controls to record the time charges of employees working on SRF activities. We That The Regional Administrator, Region 9: Reallocate the fiscal 1989 SRF grant funds aulhonzed for Nevada and Arizona if they miss the state match funding deadlines of September 30, 1991, and November 5, 1991, respectively; • Require Nevada to document its SRF policies and procedures and improve its timekeeping system; and • Perform proaward reviews of the states’ capability to operate a SRF program before providing additional grant funds. What Action Was Taken The final special review report (1400051) was issued to the Regional Administrator, Region 9, on September 26, 1991. A response to the special report is due by December26, 1991. The Region did not agree that its preaward reviews needed improvement or that SRF grant funds should be reallocated because state match funding deadlines expire. $1.5 Million Grant Prematurely Awarded For Indiana Project Requiring Modification Problem EPA awarded a $1.5 million grant to construct seWers and a wastewater treatment facility even though over one-third of the structures to be serviced are in a flood plain and will be moved or demolished. We Found That On September 29, 1990, EPA awarded the town of English, Indiana, a grant to design and construct new conventional gravity sewers, lift stations with force mains, and a wastewater treatment facility. The project’s service area included 117 structures in a flood plain. On September 13, 1990, or about 2 weeks before the grant was approved, the English Town Council condemned about 85 parcels of land located within the flood plain and announced plans to relocate the residents to a safer area. On June 11, 1991, the Town Council annexed about 200 acres of land outside the approved service area for the relocation. The condemnation ordinance was the Council’s first step toward a major 3- to 5-year redevelopment project which includes: • Relocating its central business district and residences out of a flood prone area, • Developing a new town center boulevard and industrial park, • Building low-income housing, a courthouse, library, town hall and fire station, and • Developing recreational facilities, including a man- made reservoir, in the flood prone area. As a result, the project which was described and supported by a September 28, 1990, Facility Plan and authorized by the grant probably cannot be built as conceived. Over one- third of the structures will either be relocated or rebuilt in another location, likely on land originally outside the planned service area. Also, there is no assurance that the original reason for a new wastewater treatment system, failing on- site septic systems, is any longer valid. Many of the old failing undersized systems will be abandoned when residents are relocated. In addition, the grantee will not be able to meet the project completion dates specified in the grant. We Recommended That The Regional Administrator, Region 5, suspend, terminate or annul the grant awarded to the town. What Action Was Taken The special review report (1400048) was issued to the Regional Administrator, Region 5, on September 25, 1991. A response is due by December 25, 1991. 24 Office of the Inspector General Report to the Congress ------- $10.4 Million Grant To Florida County Should Be Annulled Problem Seven years after receiving a $10.4 million grant, Hillsborough County, Florida, still does not have a fully operable wastewater collection system. We Found That Region 4 awarded Hillsborough County, Florida, grants totaling $10,393,809 for the design and construction of a wastewater treatment facility. The project is 3 years past its scheduled completion, $2.7 million over the original project cost estimate, and only 65 percent complete. The project has been suspended and completion is questionable. Also, because of delays and cost overruns, the anticipated capacity and user charge fees are projected to almost triple by 1996. The grant award was based on the County’s claim that a hepatitis outbreak was caused by faulty septic tanks and field lines that contaminated groundwater. Tests were never conducted to determine if the hepatitis cases were linked to groundwater contamination. Although the County cited health problems at 27 properties, it planned to connect only 14 of the properties to the sewage collection system and not correct all the health problems used to justify the grant. Also, the County improperly certified that it had obtained all property needed to construct the project in its April 1984 grant application, since it did not even begin to obtain easements until January 1989. Failure to address and resolve the issue of access to residents’ property contributed to the engineer’s inability to complete project design, and caused construction delays, cost overruns, and contract disputes. The County did not design fiberglass tanks before award of the construction contract. Responsibility for final design passed from the County’s engineer to the tank installation contractor to a subcontractor who designed and manufactured the tanks. An independent testing laboratory concluded the tanks were improperly designed, manufactured, and inspected, arid could not be refitted to meet design specifications. The County was faced with not only abandoning further installation of the tanks, but also replacing 480 tanks that had already been installed. The County did not properly acquire easements required by Federal law as the residents did not receive fair treatment or just compensation for their property. Specifically, the grantee did not (1) inform property owners of their rights; (2) furnish appraisals to property owners; and (3) acquire easements by negotiation. The grantee proceeded with construction based on incomplete design, causing significant construction delays and higher costs than anticipated. We Recommended That The Regional Administrator, Region 4, annul the grant and recover the Federal share expended ($5,245,731). What Action Was Tak.n The special review report (1400054) was Issued to the Regional Administrator, Region 4, on September 26, 1991. A response to the final report is due by December 26, 1991. In responding to the draft report, the Regional Administrator agreed that the grantee had not followed site certification and Uniform Relocation Act procedures. However, he disagreed that the grant award was not justified, the project was poorly planned, and the grantee failed to make substantial progress without good cause. Fiberglass tanks (photo by EPA O1G stall) April 1, 1991 through September 30, 1991 25 ------- Section 2—Audit Resolution As required by the Inspector General Act, as amended, this section contains a status report on audits in the resolution process for the semiannual period. This section also summaries OIG reviews of the Agency’s followup actions on selected audits completed in prior periods. Statistical information is also presented on reports issued during the semiannual period with questioned costs and recommendations that funds be put to better use. In addition, information is presented on the resolution of significant audits reports issued by the OIG involving monetary recommendations. Appendix 2 summaries the status of each audit report issued before the commencement of the reporting period for which no management decision had been made by the end of the reporting period. A. For which no management decision has been made by the commencement of the reporting period B. Which were issued during the reporting period C. Which were issued during the reporting period that required no resolution Subtotals (A + B- C) D. For which a management decision was made during the reporting period E. For which no management decision has been made by the end of the reporting period F. Reports for which no management decision was made within six months of issuance Any d ference n number of reports and amounts of questonec costs or recommended ef c enc es between this report and our prev:ous semannua [ report resu tS from correct ons made to data n our audo tracbng system EPA Office Of Inspector General Status Report On Perpetual Inventory Of Audits In Resolution Process For The Semiannual Period Ending September 30, 1991 Dollar Values (in thousands) Report Issuance Audit Resolution Costs Sustained Number Questioned Recommended To Be As Costs Efficiencies Recovered Efficiencies 240 258,990 942 246,479 643 11 539 505,458 230 155,969 309 349,488 68 111,552 58,181 381,344 2,038 437,487 36,571 45,010 3,534 400,917 23,936 26 Office of the Inspector General Report to the Congress ------- Audit Followup The Inspector General Act Amendments of 1988 have focused increased attention on Agency responses to the findings of the Inspectors General. Agency management is now required to report semiannually, in a separate report to Congress, the corrective actions taken in response to the lG’s audits. The Office of Inspector General reviews the Agency’s followup actions on selected audits. Below are summaries of four of these reviews. Significant Problems Render EPA’s Audit Followup System Unreliable Previous Problems and Findings Our September 1989 special review found that there was no Agency audit followup system. Despite a stated Agency commitment to audit followup, our second special review, in August 1990, identified numerous, significant weaknesses in the newly-developed Management Audit Tracking System (MATS). Our third review, completed in February 1991, identified inconsistencies in the way regions tracked nonmonetary single audit corrective actions in the system. Followup Findings Our September 1991 report (1400050), the fourth in a series assessing the Agency’s audit followup program, found that EPA’s MATS continues to contain incorrect and incomplete information about dollars recovered as a result of Office of Inspector General audit findings. Further, reports to Congress and Agency management produced from the system were unreliable, severely underreporting Agency corrective actions, recoveries, and writeoffs. As in 1990, data in MATS was incomplete and incorrect due to problems such as (1) an incomplete universe of external reports in the system; (2) inconsistent and uncertain reporting of writeoffs, offsets, and recoveries by Agency Audit Followup Coordinators (AFC); and (3) regional MATS data not reconciling with Headquarters MATS data. EPA Management’s Semiannual Reports to the Congress on Audits for fiscal 1990 were seriously flawed. There were inaccuracies in the reported number of audits on which final corrective actions had been taken. Also, reported recoveries as a result of audit findings were grossly understated. Our review of three EPA regions found unreported recoveries ($7.4 million) were almost as much as the Agency reported ($8.3 million) for all 10 regions. Also, an additional $7.4 million of disallowed costs that were reduced through the appeals process in those three EPA regions were not reported as writeoffs in either of the 1990 semiannual reports to Congress. Region 9 alone failed to report as writeoffs almost $6 million in reductions through appeal. Followup Recommendations We recommended that the Acting Assistant Administrator for Administration and Resources Management correct the identified reporting deficiencies, issue written guidance to AFCs to eliminate future reporting problems, and institute a program of quality assurance. What Action Was Taken In his September 25, 1991, response to the draft special review report, the Acting Assistant Administrator generally agreed with our recommendations and cited several steps already taken to correct the noted weaknesses. A response to the final report is due by December 30, 1991. Region Recoveries Writeoffs Reported II Actual I Reported II Actual 1 $1,794,876 $ 2,531,354 $3,974 -0- 4 $1,534,275 $ 4,761,578 -0- $1,399,433 9 Total $5,556 $3,334,707 $ 3,441,589 $10,734,521 -0- $ 3,974 $5,973,607 $7,373,040 includes the $3.3 million in recoveries reported by the Agency, plus $7.4 million which we identified that was not reported. AprU 1, 1991 through September 30, 1991 27 ------- improvements Still Needed In The Asbestos School Hazard Abatement Act (ASHAA) Loans And Grants Program Previous Problems and Findings Our September 1987 report showed that EPA awarded $11 million in loans and grants for asbestos abatement during fiscal 1985 and 1986 to schools that were not the most financially needy or with the greatest health risks. Our September 1989 report showed during fiscal years 1987 and 1988, EPA funded applications on hand which were not significant enough to receive funding in the prior year because the Agency did not solicit new applications. Approximately two million additional asbestos exposure hours could have been abated on projects with major damage if EPA had funded new applications. Followup Findings Our followup report (1400039) found that the Office of Pesticides and Toxic Substances (OPTS) had taken significant steps to implement most recommendations from our prior reports, such as (1) revising award procedures for State minimum requirements and private Local Education Agencies (LEAs), (2) improving the determination of an LEA’s financial need, 3) soliciting new applications for the 1989, 1990, and 1991 ASHAA award cycles, and (4) revising loan repayment terms for projects on which work was already completed. However, we found other actions taken by the Agency were inadequate. Foflowup Recommendations We recommended that OPTS (1) revise its definition of “qualified projects” to include only projects involving significantly damaged asbestos, (2) require States to participate more in identifying needy applicants with the most hazardous projects, and (3) develop bonding requirements for public schools that are recipients of ASHAA loans, requiring their contractors to use Treasury-rated bonding companies. Also, we recommended that the Office of Administration and Resources Management: (1) document the particular reasons why any grant applicant is unable to undertake and complete its abatement program with loan funds, (2) modify the work-in- progress loan promissory note for schools that complete their asbestos abatement within one year of the award date to begin repayment more promptly, and (3) recover $20,243 in excess grant funds from the Bureau of Indian Affairs. What Action Was Taken The Agency had either completed recommended actions or agreed to take the recommended actions for most of our findings. However, (ho Agency disagreed with our recommendations that it document why a grant applicant cannot complete a project th a loan, develop bonding requirements for loan recipients, and require states participate more in identifying the neediest applicants,. The final special report was issued to the Assistant Administrator for Pesticides and Toxic Substances and the Acting Assistant Administrator for Administration and Resources Management on September 12, 1991. We will reevaluate the recommendations vvith which the Agency disagreed after the Agency submits its response which is due by December 11, 1991. Region 9’s Air Grants Program Deficiencies Not Corrected Initial Problem and Findings In March 1987 we reported that Region 9’s air grants program was hindered by inadequate controls. Air grants totaling $2.6 million for fiscal 1983 through fiscal 1985 were identified as ineligible. Followup Findings Our followup report (1400049) found that although Region 9 had taken adequate corrective actions on two of the prior findings, it had not developed effective procedures to (1) ensure that grant recipients meet the statutory maintenance of effort (MOE) requirements and (2) monitor grant performance. Four of the grantees discussed in our prior audit still had not met their required MOE requirements for all grants awarded from fiscal 1983 to fiscal 1985, nor had $1.5 million of the $2.6 million of ineligible grants made during the period been recovered. The Region encouraged and subsequently approved the grantees’ reclassification of some nonrecurrent costs as recurrent costs so that MOE requirements were met. Further, the Region had not implemented recommended procedures to prevent the supplanting of Federal funds and continued to allow air pollution grantees to improperly claim nonrecurrerit costs as recurrent costs in order to meet their MOE. As a result, grantees received about $1.9 million of ineligible grants. Also, the Region did not require year-end performance evaluations to be completed within 120 days, as agreed, or use its data base tracking system to monitor grant performance. As a result, grants were awarded without assessing whether the grantees accomplished the prior year’s program objectives. Followup Recommendations We recommended that the Regional Administrator, Region 9, (1) advise the grantees that they were not eligible for air pollution control grants totaling $3.4 million for fiscal years 1983 through 1990, (2) establish effective procedures to prevent the supplanting of local funds with grant funds, (3) closely review grantee determinations on nonrecurrent costs to assure that they are consistent with the intent of the Act and (4) require year-end performance evaluations and retention of workpaper documentation. What Action Was Taken In responding to the draft followup report, the Regional Administrator, Region 9, agreed with some recommendations, disagreed with others, and asked for clarification of several others. He stated that Region 9 had tried to implement corrective actions recommended in the 1987 report and that current programmatic, administrative, and financial efforts meet the intent of Section 105 of the Clean Air Act. Because previously agreed to corrective actions had not been implemented or were not effective, we will continue to track the prior report’s recommendations. 28 Office of the Inspector General Report to the Congress ------- Agency Accounts Receivable Not Accurate And Complete; Significant Improvements Still Needed Initial Problem and Findings In March 1988, we reported that the Agency Financial Management System (FMS) did not have accurate or complete records of accounts receivable, nor were Financial Management Officers (FMO) aggressively collecting debts. In March 1 987, of the Agency’s reported $99 million in accounts receivable, we estimated that 25 percent were understated by more than $5 million and 14 percent were overstated by nearly $3 million. Followup Findings A special followup review (1100433) reported that while the Agency had implemented or initiated action on most of the recommendations from the 1988 report, many corrective actions were completed substantially later than originally scheduled. As a result, the Agency still did not have accurate or complete accounts receivable records. However, the Agency recently initiated additional corrective actions that, if properly completed, should result in substantially more reliable and accurate accounts receivable. For example, an Agency-wide accounts receivable reconciliation was scheduled for completion by September 30, 1991, and an Accounts Receivable Task Force was established to review current status and make necessary recommendations to ensure compliance with current guidance. Followup Recommendations We recommended that EPA adhere to the requirements of Resources Management Directive System 2540, Chapter 9, for monthly reconciliations and add guidance requiring FMOs to verify and document the accuracy of reconciliations; provide training in accounts receivable policy and procedures; develop specific followup and resolution procedures for all findings and recommendations of the Accounts Receivable Task Force; and require periodic evaluations of FMOs’ success in promptly recording new accounts receivable. What Action Was Taken The special foiowup final review report was issued to the Acting Assistant Administrator for Administration and Resources Management on Soptember 30, 1991. A response to the final report is due by December 29, 1991. In responding to the draft report, the Acting Assistant Administrator generally agreed with our recommendations. April 1, 1991 through September 30, 1991 29 ------- Status Of Table 1 Management Inspector General Issued Reports With Questioned Costs Decisions On IG Audit Repoers Semiannual Period Ending: September 30, 1991 Dollar_Values jthousand This section presents statistical Questioned Unsupported information as required by the _______— . _..._P !L_ _P2 c2sJ Inspector General Act A. For which no management decision has 149 258,990 92,642 Amendments of 1988 on the been made by the commencement of the status of EPA management reporting period decisions on audit reports issued by the OIG involving B. New Reports issued during period 126 246,467 23,901 monetary recommendations. In order to provide uniformity Subtotais (A + B) 275 505,457 116,542 in reporting between the various agencies, the C. For which a management decision was 116 155,969 60,773 President’s Council on Integrity made during the reporting period and Efficiency issued guidance (i) Dollar value of disallowed costs 97 45,01 D 8,670 on reporting the costs under required statistical tables of (ii) Dollar value of costs not disallowed 76** 110,959 52,102 sections 5(a)(8) and (9) of the Act, as amended. 0. For which no management decision has 159 349,488 55,769 As presented, information been made by the end of the reporting contained in Tables I and II period can not be used to assess results of audits performed or Reports for which no management 48 111,552 37,376 decision was made within six months controlled by this office. Many of issuance of the reports counted were performed by other Federal Ouestloned costs include the unsupported costs. auditors or independent public “On 19 audits management did not sustain any of the $43,623,700 questioned costs. Fitly.stx audits are also accountants under the Single included In C(il) because they were only partially sustained. Only the costs questioned that were riot sustained in C(i) Audit Act. EPA OIG staff does are Included in this category. not manage or control such assignments. In addition, amounts shown as costs Table 2 questioned or recommended to inspector Generai issued Reports With Recommendations That Funds Be Put To Better Use be put to better use contain amounts which were at the . Semiannual Pcriod Ending: September 30, 1991 time of the audit unsupported by adequate documentation or Number Dollar Vaiue records. Since auditees ( in thousands frequently provide additional A. For which no management decision has been made 25 58,181 documentation to support the by the commencement of the reporting period allowability of such costs subsequent to the audit, we B. Which were issued during the reporting period 69 379,306 expect that a high proportion of unsupported costs will not Subtotals (A + B) 94 437,488 be sustained. EPA OlG controlled audits C. For which a management decision was made during 23 36,571 resolved during this period the reporting period resulted in $52.8 million being (i) Dollar value of recommendations that were 10 3,534 sustained out of $65.9 million agreed to by management considered ineligible in reports under OIG control. This is an - based on proposed management action n/a n/a 80 percent sustained rate. - based on proposed legislative action n/a n/a (ii) Dollar value of costs not disallowed 10 18,190 (iii) Dollar value of non-awards or unsuccessful bidders 8 14,847” D. For which no management decision has been made 71 400,917 by the end of the reporting period Reports for which rio management decision was 10 23,936 made within six months of issuance Five of the audits were the same audits in items C(i) and C(iI). Only the related dollars disallowed were included in C(i). whereas the dollars which were not disallowed were included in C(ii). “ThIs amount represents the dollar value of recommendations that funds be put to better use. Office of the Inspector General Report to the Congress ------- Resolution of Significant Audits Resolution of Significant Audits Report Numb.r/ Grwt.& Report Date Contractor Report Issuanc$ FS Questioned/ Recommended Efficiency Report Resolution Federal Share to be Recovered! Sustained Efficiency Report Number/ Grante.I Report Date Contractor Report Issuance FS Question.d/ Recommended Efficiency Report Resolution Federal Share to be Recovered! Sustained Efficiency D8AML1-O1 -0045 ABB ENV. SERVICES, INEL 0 INC. ME INEL 0 P2CWN8-05-0142 ST PAUL MWCC MN 1300015 INEL 675550 INEL 675,550 UNSP 46463 UNSP 46463 1100048 UNSP 0 UNSP 0 REPORT DATE UNUR 0 UNUR 0 REPORT DATE UNUR 0 UNUR 0 10/31/90 SCOM 0 SUST 0 10/29/90 RCOM 416,728 SUSI 416,728 S2CWL9-01 -01 75 MWRA MA INEL 904,555 1100107 UNSP 534,226 REPORT DATE UNUR 0 INEL UNSP UNUR P2CWN8-05-0214 MUSKEGON CO 692,150 DPW MI 0 1300014 0 REPORT DATE INEL 76511 INEL 76,511 UNSP 1,213,469 UNSP 1,123,051 UNUR 0 UNUR C 1/22/91 RCOM 0 SUST 0 10/31/90 RCOM 0 SUST 0 P2CWL9-02-0050 NASSAU COUNTY NY INEL 533,556 INEL 477,063 P9AHN1-05-0135 OHM REM INEL 0 INEL 0 0100481 UNSP 127,363 REPORT DATE UNUR 0 UNSP UNUR 0 ERCS3 R4 OH 0 1300040 UNSP 0 UNSP 0 9/17/90 RCOM 0 SUST 0 REPORT DATE UNUR 0 UNUR 0 P2CWL9-02-0312 NASSAU COUNTY NY INEL 129,408 NEL 2/28/91 129,165 RCOM 4,447,864 SUST 1,365,392 1100177 UNSP 128,389 REPORT DATE UNUR 674,684 4/15/91 RCOM 0 UNSP UNUR SUST 25,419 P2CWN9-07-0081 METRO ST LOUIS 674,684 SEWER 01ST, MO 0 1300038 INEL 1,239,757 INEL 1,239,757 UNSP 677,531 UNSP 0 P2CW8-03-0178 GREENBRIER NEL 882,455 CO PSD #2 WV 0100536 UNSP 416,213 REPORT DATE UNUR 162,449 9/28/90 RCOM 0 P2CWL9-03-0017 WSSC & FAIRFAX INEL 1,064,863 CITY & DC DC 1100157 UNSP 525,183 REPORT DATE UNUR 0 3/29/91 RCOM 0 P2CWL9-03-0308 HAMPTON ROADS INEL 813,134 SANI DISTRICT v 1100045 UNSP 0 REPORT DATE UNUR 0 10/23/90 RCOM 0 P2CWN9-04-0294 ATLANTA GA INEL 637.366 1300012 UNSP 2.558,305 REPORT DATE UNUR 0 10/24/90 RCOM 0 P9AHP1-04-0100 WESTINGHOUSE- INEL 0 INEL UNSP UNUR SUST INEL UNSP UNUR SUST INEL UNSP UNUR SUST INEL UNSP UNUR SUST INEL REPORT DATE 688,397 2/28/91 3,562 0 S2BWNO-09-0171 SAN FRANCISCO, 0 C&C WST CA 1300055 1,013,373 REPORT DATE 3/29/91 184,358 0 S2CW6-09-0175 OXNARD, 0 CITY OF CA 1300045 787,041 REPORT DATE 3/25/91 0 0 S2CW*7.09 0116 SAN DIEGO, 0 CITY OF CA 0300038 635.011 REPORT DATE 2.558.305 3\30\90 0 0 0 UNUR 0 UNUR 0 RCOM 0 SUST 0 INEL 1,596,249 INEL 1,190,967 UNSP 0 UNSP 0 UNUR 2.662,422 UNUR 0 RCOM 0 SUST 0 INEL 6.485,975 INEL 5,883,960 UNSP 0 UNSP 0 UNUR 0 UNUR 0 RCOM 0 SUST 0 INEL 10,420,275 INEL 10,420,275 UNSP 0 UNSP 0 UNUR1 7,598,897 IJNUR 0 RCOM 0 SUST 0 HAZTECH GA 1400008 UNSP 0 REPORT DATE UNUR 0 3/6/91 RCOM 1,650.090 UNSP UNUR SUST 0 0 919.131 S2CWN8-04-0051 TULLAHOMA TN INEL 249,900 1300026 UNSP 608,164 REPORT DATE UNUR 281,833 1(8/91 RCOM 0 INEL UNSP UNUR SUST 249,900 266,324 281,833 0 P2CWL8-05-0282 SUMMIT CO OH NEL 3.553,409 0100490 UNSP 2,467,655 REPORT DATE UNUR 0 9/24/90 RCOM 0 INEL UNSP UNUR SUST 3,553,409 2,026.997 0 0 P2CWL9-05-0324 SUMMIT & INEL 233,040 PORTAGE CO’S OH 0100464 UNSP 4,813,935 REPORT DATE UNUR 78,124 8/29/90 RCOM 0 INEL UNSP UNUR SUST 233,040 1,055.527 78,124 0 P2CWN6-05-0377 CHICAGO INEL 236,306 MWRDGC IL 1300051 UNSP 240,323 REPORT DATE UNUR 17,410 3/29/91 RCOM 0 INEL UNSP UNUR SUST 235,057 240.323 17,410 0 P2CWN7-05-0498 CHICAGO INEL 675,462 MWRDGC IL 1300050 UNSP 356,998 REPORT DATE UNUR 9,309 3/29/91 RCOM 0 INEL UNSP UNUR SUST 524,847 356,998 9,309 0 NOTE: INEL = INELIGIBLE COST UNSP = UNSUPPORTED COST UNUR = UNNECESSARY/UNREASONABLE COST RCOM = RECOMMENDED EFFICIENCIES SUST RECOMMENDED EFFICIENCIES SUSTAINED April 1, 1991 through September 30, 1991 31 ------- Section 3—Prosecutive Actions The following Is a summary of investigative activities during this reporting period. These include Investigations of alleged criminal violations which may result in prosecution and conviction, investigations of alleged violations of Agency regulations and policies, and OIG personnel security investigations. The Office of Investigations tracks investigations In the following categories: preliminary Inquiries and investigations, joint Investigations with other agencies, and OIG background investigations. Summary Of Investigative Activities Summary Of Investigative Activities Pending Investigations as of April 1, 1991 198 New Investigations Opened This Period 147 Investigations Closed This Period Pending Investigations as of September 30, 1991 192 Prosecutive and Administrative Actions In this period, investigative efforts resulted in 11 convictions and 18 indictments. Fines and recoveries, including those associated with civil actions, amounted to $4.5 million. One settlement agreement resulted in a cost avoidance of $3 million. Thirty-eight administrative actions were taken as a result of investigations: Suspensions 2 Reprimands 19 153 Resignations/Terminations 3 Other 14 * Does not include suspensions and debarments resulting from Office of Investigations activities or actions resulting from reviews of personnel security investigations. Profile Of Pending Investigation By Type (Total -192) Superfund 49 2904 EPA Program Area Waste 32% Construction 34 18% Employee 29 15% Administration 22 11% Profiles Of Pending InvestIgatIons By (Total-192) Water 50 26% Program Fraud/Other 59 31% Personnel Security 8 4% 32 Office of the Inspector General Report to the Congress ------- Description Of Selected Prosecutive Actions Below is a brief description of some of the prosecutive actions which occurred during the reporting period. Some of these actions resulted from investigations initiated before April 1, 1991. Superfund Contract Laboratory Program Investigation The Office of Investigations has a major investigative initiative underway within the Superlund program, directed at fraud in the Contract Laboratory Program (CLP). Laboratory analyses under the CLP are the empirical basis for the entire Superfund program. Based on testing for the presence of hazardous chemicals by these laboratories, the Superfund program decides which cleanups to initiate and how to carry them out. Fraudulent analyses could result in a danger to the public health and safety as well as the unnecessary expenditure of cleanup funds. In addition, fraudulent analyses could hinder the Department of Justice’s efforts to collect the cost of cleanups from the responsible parties. Several actions resulting from the contract lab investigations are described below. California Lab Pleads Guilty, Fined $500,000, Agrees to Pay $805,000 More in Civil Action In a case involving fraud and abuse within EPA’s Contract Laboratory Program, the Science Applications International Corporation (SAIC), La Jolla, California, pled guilty to charges of making false statements to EPA and making false claims for payment to the Government. Six of SAIC’s employees had previously pled guilty for their roles in the case. EPA contracted with SAIC to perform analyses on samples taken from Superfund toxic waste sites. The purpose of these analyses were to (1) determine the amount and identity of the toxic chemicals, (2) establish priorities among sites so that the most dangerous sites could be cleaned up first, and (3) help in identifying the parties responsible so that EPA could obtain reimbursement for the cleanup costs. In the contract between SAIC and EPA, EPA required that volatile organic analyses be performed within ten days, so that certain chemicals would not dissipate. Penalties were assessed for lateness. In addition the contract required that sample analysis equipment be tuned and calibrated every twelve hours to ensure accuracy. The joint investigation by the EPA OIG and the FBI uncovered that backdating of sample test results occurred in order to avoid the penalty. Also, SAIC manipulated the sample analysis equipment test data to fraudulently reflect the accuracy of analysis equipment. The company agreed to pay a criminal fine of $500,000. The company’s guilty plea was a part of the overall settlement agreement between SAIC and the Government, in which SAIC agreed to pay $805,000 (EPA $745,000 and the Air Force $60,000) for the civil claims arising for the same conduct, making the total settlement (both civil and criminal) over $1.3 million. Major Testing Firm Fined $1 Million United States Testing Company of Hoboken, New Jersey, a subsidiary of SGS North America, Inc., (a part of the SGS Group, the world’s largest inspection and testing company with over 21,000 employees in 140 companies), pled guilty in April to making false statements to EPA. The company was ordered to pay a $100,000 criminal fine and to repay the entire contract price of $869,486.90 as restitution to the United States. U.S. Testing admitted to backdating tests of water and soil samples at Superfund sites. U.S. Testing, by speak shaving” (manual manipulation of calibration), which violated the required testing sequence, sought to disguise its failure to conduct timely tests. Missouri Lab Sentenced MetaTrace, lnc., Earth City, Missouri, and two of its former officers were sentenced after previously pleading guilty to submitting false statements to EPA under the CLP program. Dr. Carol Byington, former executive vice president, was sentenced to five years imprisonment and a $20,000 fine, Kenneth Baughman, a vice president, was given live years probation and was fined $10,000. The corporation was put on probation for five years and was fined $400,000. Laboratory personnel had manipulated results for calibration and check standards during GC/MS analysis in order to show that a group of environmental sample results were fully compliant with protocol criteria when, in fact, they were not. Unregistered Pesticides Shipped Abroad A New Jersey man has pled guilty to charges that he sold mislabeled, unregistered pesticides to overseas companies in violation of the Federal Insecticide, Fungicide, and Rodenticide Act (FIFRA), which is administered by EPA. The case involves Kamal Salieb Gabra, whose three businesses -- Liberty International Agricultural Products, Nevacide Ltd, and Hercules Chemicals USA -- were charged with the sale and shipment of the chemicals to firms in several Middle Eastern countries, including the United Arab Emirates. Bribes Alleged in Indiana Sewer Work An Illinois businessman, Ronald Randich, has been indicted for allegedly bribing a Hammond, Indiana, Sanitary District (HSD) superintendent. Randich was indicted under the provisions of Title 18, U.S.C., Section 666, for Apr I 1, 1991 through September 30. 1991 33 ------- allegedly bribing an agent of an organization or agency which receives, in any one year period, benefits in excess of $10,000 under a federal program involving a grant, contract, subsidy, loan, guarantee, insurance, or other form of federal assistance. During the one year period in which the alleged bribe was made, HSD received over $350,000 in EPA grant monies. The EPA has awarded HSD over $17 million in grant money over the three year period from 1 984 through 1987. The federal grand jury indictment charging Randich with the bribe is a result of an investigation by the Indiana State Police in cooperation with the EPA OiG and the Indiana Department of Environmental Management. A superseding indictment has added another defendant to a Pennsylvania pollution case. Louis Maslow, the chief executive officer and majority owner of two former Trainer, Pennsylvania, firms, Metro Container Corporation and Metro-Enterprise Container Corporation, was indicted on June 4, 1991. Sidney S. Levy, President, and one of the owners of Metro, and Steven Zubrin, a Metro maintenance supervisor, were indicted in August 1990, and charged with criminal violations of two Federal environmental statutes, the Resource Conservation and Recovery Act and the Clean Water Act, and with conspiracy to violate these two Federal environmental statutes. A joint investigation by the EPA 010, the EPA Office of Enforcement, and the Federal Bureau of Investigation was initiated after a criminal investigation by thd EPA 010 of another allegation involving the Superfund program found evidence of serious environmental violations. As part of the joint investigation, a search was executed at the site by members of the EPA’s National Enforcement Investigations Center (NEIC). NEIC personnel excavated portions of the site where Metro conducted a drum recycling business. Using heavy equipment, NEIC personnel excavated portions of the site where the hazardous waste was believed to have been buried. Buried drums were uncovered, and numerous samples taken from the site revealed the presence of hazardous waste in the yard and in the building. In addition, the presence of contaminants was detected in a pipe leading from the Metro facility to Stoney Creek, a tributary of the Delaware River. Terry Lee Tebben and Daniel Workman, employees of Gee- Con, Inc., a Pennsylvania company, have been charged with fraud in connection with the cleanup of a Superfund site at Bruin Lagoon, Butler County, Pennsylvania. EPA funded a $4 million contr t with Geo-Con to clean up the lagoon, which was contaminated with, among other things, sulfuric and hydrochloric acid. The adjacent Bruin Oil Company had used the lagoon for disposal of wastes since the 1930’s. It was anticipated that the cleanup work would cause the emission of hazardous gases, including sulfur dioxide, creating a potential hazard not only to the Geo-Con employees but also to nearby residents. The indictment alleges that Tebben used the finger of a rubber glove and grease to cover up the air monitors required by the contract, causing them to give false readings on the amount of hazardous gases being released, and thereby endangering public health and safety. Another provision of the contract required Geo-Con to treat any water which became contaminated as a result of the cleanup. The company was to be reimbursed at a rate of $.30 per gallon of water treated. Workman allegedly pumped air through the water metering system, leading to $62,000 in false claims for reimbursement for water treated. Minority Business Claim Faulted As the result of a joint investigative effort by the EPA OlG, the DOT DIG, the GSA OIG, and the FBI, a Massachusetts firm and its president were charged with conspiracy to defraud the government in connection with the Minority Business Enterprise (MBE) program. The firm and its president allegedly used a Rhode Island MBE firm as a “front company” so that expenditures on some federal and federally assisted construction projects would be credited towards MBE goals, when they were, in fact, for the benefit of the firm. EPA suspended the firm, which distributes reinforcing bars (“rebars”) used to reinforce concrete for the construction of roads, bridges, and treatment plants, and its president from all government contracts and assistance, loan, and benefit programs. In September 1991, the U.S. District Court, District of Massachusetts, dismissed the criminal charges filed against the firm and its president. The U.S. Attorney’s Office is appealing the dismissal of the charges. In 1989, the MBE firm and its president were convicted of making false statements on a minority business certification application filed with the Commonwealth of Massachusetts. This firm and its president were each fined $1 0,000. The president was also placed on 3 years probation and ordered to perform 100 hours of community service to the minority community. Duo Admits Guilt in Timesheet Fraud Jay Lehr and Keith Leiux, employees of the National Water Well Association (NWWA), Dublin, Ohio, pied guilty to falsifying timesheets as part of a claim for payment under an EPA cooperative agreement. NWWA’s task was to develop a national mapping system of ground water supplies to be used by EPA in the control of ground water contamination from waste disposal sites, by State and by region. Lehr and Lelux were each sentenced to 6 months imprisonment and 2 years probation upon release. Lehr was also fined $25,000 and Lelux $5,000. NWWA subsequently entered into a settlement agreement with the Government, under which it paid the United States $203,273.50, double the actual amount of damages to EPA. Fraud Alleged at Company CEO Added Superfund Cleanup to Indictment For Site Environmental Violations 34 Office of the aspector General Report to the Congress ------- Description Of Selected Prosecutive And Administrative Actions Concerning EPA Employees The OIG investigates and reports information, allegations, and indications of possible wrongdoing or misconduct by EPA employees and persons or firms acting in an official capacity directly with EPA or through its grantees. In addition, the Senate Report of the Supplemental Appropriations and Rescission Act of 1980 states that appropriate administrative action is expected to be taken in cases where employees have acted improperly. EPA Environmental Engineer Sentenced for Perjury An EPA environmental engineer who pled guilty to one count of perjury was sentenced in May to 6 months of home detention, 5 years of probation, and a $50 fine. While appearing in Federal court as an expert witness for EPA in May 1990, the employee testified that she had received a Ph.D. in civil engineering from a state university when, in fact, she had not. Civil And Administrative Actions To Recover EPA Funds Investigations and audits conducted by the Office of Inspector General provide the basis for civil and administrative actions to recover funds fraudulently obtained from EPA. Through the Inspector General Division of the Office of General Counsel, the OIG uses a variety of tools to obtain restitution. These include cooperative efforts with the Department of Justice in ffiing civil suits under the False Claims Act, the Program Fraud Civil Remedies Act, and other authorities; working with grantees using their own civil litigation authorities; invoking the restitution provisions of the Wctim and Witness Protection Act during criminal sentencing; using the Agency’s authority to administratively offset future payments and to collect debts; and negotiating voluntary settlements providing for restitution in the context of suspension and debarment actions. Civil and administrative actions to recover funds usually extend over several semiannual reporting periods. Final Settlement Reached on Snapfinger Creek Case In May 1991 the Government and the remaining two defendants in the Snapfinger Creek False Claims Act (FCA) litigation agreed to a final settlement. In exchange for a cash payment of $880,000 from Dynalectric Inc., the Government agreed, with respect to Dynalectric and G.W. Waither Ewalt, to dismiss any and all claims that it might have arising out of the Snapfinger Creek bidrigging conspiracy. Prior to the settlement with Dynalectric and Ewalt, the government had recovered $440,000 from the Paxson defendants and $660,000 from Fischbach and Moore (F&M). The settlement with Dynalectric and Ewalt brought to a close the Government’s attempts to be made whole for the economic harm that EPA suffered in funding the construction of the Snapfinger Creek wastewater treatment plant. The construction costs of that facility were inflated by the bidrigging conspiracy of the prospective electrical subcontractors, the defendants in the Government’s FCA action. Three quarters of the amount of inflation was paid for by EPA, which funded 75% of the project’s construction costs. The escalating recoveries, first $440,000 from the Paxson defendants, then $660,000 from F&M, and finally $880,000 from Dynalectric reflect the Government’s assessment of (1) the relative culpabilities of and (2) the extent of economic gain realized by the defendants. Dynalectric, for example, did virtually no work on the Snapfinger project, yet realized an $880,000 profit. Overall, the Government has recovered $1,980,000 from the Snapfinger defendants, $1.3 million of which has been returned to the EPA appropriation. This $1.3 million represents the amount by which the Federal Government’s monetary contribution to the Snapfinger project was inflated as a consequence of the electrical contractors’ bidrigging conspiracy. Lab Fraud Case Settled The Government and Science Applications International Corporation (SAIC) reached a civil fraud settlement in August 1991. The Government’s case against SAIC arose out of that laboratory’s willful failure to comply with the terms of four of its sample analyses contracts and its manipulation and misrepresentation of data to reflect otherwise. SAIC defrauded EPA on the four contracts by filing claims for complete payment even though the laboratory knew of its failure to comply with certain contractual requirements and of its intentional misrepresentation of relevant information to reflect that it had complied. Had EPA been aware of SAIC’s contract noncompliance, the Agency would have taken monetary deductions authorized by the contracts and would have reviewed the SAIC data more critically, rather than relying on it at face value. Under the terms of the settlement, SAIC paid the government $805,000 ($745,000 for EPA, and $60,000 for the Air Force) for the fraud that the laboratory practiced against EPA. Of this recovery, $350,000 has been returned to the Agency appropriation. This amount represented the full payment that EPA had made to SAIC under the tainted contracts. Suspension Lifted After $1.1 Million Settlement In August 1991, Enseco Incorporated, Corning Lab Services, Inc., and Corning Incorporated (the Corning entities) paid the Government $1.1 million. The payment was part of a settlement under which EPA agreed to terminate its June 25, 1991 government- wide suspension and proposed debarment of the Corning entities. The Corning entities made the payment to settle allegations that Enseco and its predecessor, Rocky Mountain Analytical Laboratory, Inc., had submitted false claims under 6 EPA Contract Laboratory Program contracts. The payment has been returned to EPA’s Superfund program. In addition, Enseco agreed to give up its contract claim against EPA, which amounted to approximately $3 million, including accrued interest. Finally, the Corning entities agreed to implement a contract compliance plan and an ethics policy to assure EPA that the Corning entities are presently responsible to do business with the Federal Government. April 1, 1991 through September 30, 1991 35 ------- Section 4 —Fraud Prevention and Resource Management improvements This section describes several activities of the Office of Inspector General to promote economy and efficiency and to prevent and detect fraud, waste, and abuse in the administration of EPA programs and operations. This section includes information required by statute, recommended by Senate report, or deemed appropriate by the Inspector General. Review Of — And Regt ations Section 4(a)(2) of the Inspector General Act of 1978, as amended, dtrects the Office of Inspector General to review existing and proposed legislation and regulations relating to Agency programs and operations to determine their effect on economy and efficiency and the prevention and detection of fraud and abuse. This semiannual reporting period, we reviewed 5 legislative and 81 regulatory items. The most significant items reviewed are summarized below. Department of Justice Draft Anti- fraud Enforcement Act of 1991 The provisions of this bill would assure a more comprehensive assessment of damages and evidence in connection with civil actions resulting from OlG investigations. We strongly supported this draft bill because we believed it would provide easier and quicker access to grand jury material in the pursuit of civil remedies that follow criminal prosecutive actions. Considering the large number of civil actions that are brought as a result of OIG work in EPA, we believe that this draft bill would have significant impact on EPA and the rest of the Federal Government by improving the Agency’s ability to more efficiently and effectively pursue and obtain civil recoveries. Government Energy Efficiency Act of 1991, S1040 The bill would require each Inspector General to conduct a review to determine agency compliance with Section 543 of the National Energy Conservation Policy Act. We believe this requirement is unnecessary, and that it negatively affects our ability to prioritize our work. The OlG has an annual audit planning process that attempts, with limited resources, to provide balanced coverage of all Agency programs. Our process recognizes the existence of new requirements (such as those in the bill), and we consider these factors when selecting audit assignments. We believe that identifying significant areas for auditing and directing our resources to the most productive efforts should remain our prerogative. False Claims Act Amendment of 1991 We agree with the Department of Justice that it was not the intent of Congress to allow government employees to benefit financially from the False Claims Act Amendments of 1986. We believe that the proposed amendment to revise the qui tam provisions of that statute is absolutely essential to avoid substantial losses to the Treasury and significant impairment of anti-fraud efforts. Federal Government Performance Standards We generally supported the draft bill regarding Federal Government Performance Standards (sponsored by Senator Graham) and Senate Bill S.20 (sponsored by Senator Roth). The establishment of such standards and goals would increase accountability and ensure that funds are being spent to effectively accomplish the desired results. However, even though no new audits are mandated for Inspectors General (lGs), we oppose certain provisions of Senator Graham’s bill (Senator Roth’s bill does not identify the role of lOs regarding these standards and goals). Our first concern relates to the requirements of Senator Graham’s bill for lOs to determine in each audit conducted, supervised, or coordinated, whether any material weaknesses exist. This requirement goes beyond what is required by Government Auditing Standards and would be extremely resource Intensive and would drastically reduce the number of audits that we could perform. Secondly, the bill would require IGs to investigate any allegation of fraud or misrepresentation that occurs related to any interim or final report or statement required by the Federal 36 Office of the Inspector General Report to the Congress ------- Managers’ Financial Integrity Act. IGs would also be required to submit a report of investigation to Congress within 60 days after receipt of the allegation in writing. Reports of investigation regarding Federal employee fraud are generally referred to the Department of Justice for prosecutive consideration, and we do not believe it is appropriate to send them to Congress on a routine basis. The bill is also too restrictive in its requirement for these investigations because it does not provide IGs with the latitude to prioritize their own work. We also disagree with the provisions which would require that lGs report under the “Seven Day Letter Notice”, the failure to meet established policy objectives and performance standards. We believe this is unnecessary since it duplicates the requirement for agency managers to report on their achievement of performance standards and goals. This requirement would only appear to be appropriate if an IG had reason to believe that there was an attempt to deny, obstruct, or withhold this type of information. Proposed Special Occupational Pay System for Law Enforcement Officers and Protective Occupations We generally support the proposed development of special pay systems covering law enforcement officers and protective occupations. We recommended that the Office of Personnel Management review the findings and recommendations of the National Advisory Commission on Law Enforcement, which were published in April 1990 by the Office of the Comptroller General (OCG-90- 2). The information and analysis obtained through the work of this Commission should be considered and incorporated where possible into any studies that OPM conducts on these pay and classification systems. Currently there are on- going discussions between OPM and the Congress regarding whether Senior Executive Service employees should be included under Title IV, Section 404, of the Federal Law Enforcement Pay Reform Act of 1990. We suggest that any special pay system developed under the provision which provides for locality pay increases for law enforcement officers be specific on this issue. GSA Interim Rule on Ethics We have reviewed and recommended revisions to the GSA Interim Rule implementing 31 U.S.C. section 1353. It was not clear who would be the “authorized agency official” for the purpose of determining the propriety of accepting payments. Although this decision may be left up to the individual agency to decide, we believe that it is important that this official (or officials) have a legal background and experience in ethics determinations. In addition, our Office of Investigations would be called upon to address and resolve any complaints and allegations that might arise from any actual or apparent improprieties pertaining to this interim rule. Therefore, we believe that the initial reviews and determinations made in connection with this rule be conducted by a competent and knowledgeable agency official to ensure consistency. We recommended that the Designated Agency Ethics Official, or similarly qualified person be the only ‘authorized agency official” to make these determinations. We also believe that should an employee’s attendance at an event outweigh any concern with regard to an appearance of a conflict, then the agency should seriously consider paying the expenses necessary for the employee to attend, and disregard any offer of payment from a non-Federal source. This would protect the agency and employee from any problems that could arise in connection with an actual, or an appearance of, conflict of interest. Proposed Office of Government Ethics Regulations for Employees of the Executive Branch We commented on the proposed revision to 5 CFR 2635.803, Prior Approval for Outside Employment and Activities. We believe that EPA should publish regulations that require prior approval of outside employment for certain categories of employees. The OlG will submit a request that would require such prior approval for our auditors and investigators, should the regulations become final. Under certain circumstances the proposed regulations would permit an employee to use his or her official title or position in connection with teaching, speaking, or writing activity. We suggested that supplemental regulations include language which would require an agency employee to sign (for agency records) and have published (for public review) a disclaimer of official endorsement by the employee’s agency. We believe this should be done whenever official titles or positions are used that could express or imply official EPA support or approval of the work or opinions expressed by the employee. Proposed Section 2635.502, Personal and Business Relationships, describes one category of covered relationships as a person who is a member of the employee’s household or who is a relative with whom the employee has a close personal relationship. We believe that it makes more sense to say that the employee has covered relationships with any person with whom he or she has a close personal relationship and not limit this to a relative. The existing proposed wording will create a serious problem for the enforcement of conflict regulations where persons outside of a traditional family relationship are involved. Chief Financial Officer Delegation We recommended revisions to Delegation 1-16, Agency Chief Financial OfficerfAccounting Budgeting, and other Financial Management Activities. Specifically we suggested that language be incorporated which specified that none of these delegations should be interpreted to infringe on the Inspector General’s independence or authority to conduct, supervise and coordinate audits and investigations relating to EPA programs. We also indicated that, according to the Integrated Financial Management System Charter, September 14, 1990, two management groups (the Executive Management Group and the System Management Group) are responsible for the effective management of IFMS, not the Director of the Financial Management Division. The Charter further states that, overall, the functional divisions (Financial Management Division and Budget Division) are responsible for all functional aspects of IFMS life cycle management. In addition, the Administrative Systems Division is responsible for software management; therefore, we do not believe this authority can be redelegated to the Director of Financial Management Division. In addition, we recommended that the authorities regarding audit findings and the Federal Managers’ Financial Integrity Act should be rodelegated to the Resource Management Division and not the Financial Management Division. April 1 1991 through September 30, 1991 37 ------- Final EPAAR Rule on Oral Purchase Orders Suspension And Debarment We recognized that the Agency’s proposed change increasing the oral ordering limit of $25,000 will permit more oral orders to be placed, thereby reducing procurement lead time and costs associated with processing purchase orders. However, the increased dollar limit also increases the Agency’s vulnerability to abuse or mismanagement. The OlG believes that the Procurement and Contracts Management Division (PCMD) should carefully review its internal controls to ensure that they are adequate to prevent misuse of this authority. The OlG also believes that individuals placing oral purchase orders should be specifically authorized to do so by their respective Assistant Administrators, Regional Administrators, or equivalent, and certified through training by the PCMD. Additionally, we believe that any Contracting Officer with this authority should have (at a minimum) a limited background investigation for a moderate risk position to ensure his or her suitability for a position of public trust. Activities EPA’s policy is to do business only with contractors and grantees who are honest and responsible. EPA enforces this policy by suspending or debarring contractors or grantees from further EPA contracts or assistance if there has been a conviction of, or civil Judgment for: • commission of a fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public contract or subcontract; • violation of Federal or State antitrust statutes relating to the submission of offers; • commission of embezzlement, theft, forgery, bribery, falsification or destruction of records, making a false statement, or receiving stolen property; or • commission of any other offense indicating a lack of business integrity or business honesty that seriously and directly affects the present responsibility of a Government contractor or subcontractor. A contractor may also be debarred for violating the terms of a Government contract or subcontract, such as willful failure to perform in accordance with the terms of one or more contracts, or a history of failure to perform, or of unsatisfactory performance on one or more contracts. A contractor may also be debarred for any other cause of so serious or compelling a nature that it affects the present responsibility of the contractor. Thus, a contract or need not have committed fraud or been convicted of an offense to warrant being debarred. Debarments are to be for a period commensurate with the seriousness of the cause, but are generally not to exceed 3 years. The effectiveness of the suspension and debarment (S&D) program has been enhanced by regulations that provide all Federal agencies a uniform system for debarring contractors from receiving work funded by Federal grants, loans, or cooperative agreements. The system, required by Executive Order 12549, provides that a nonprocurement debarment or suspension by one agency is effective in all aaencies and requires the General Services Administration (GSA) to publish monthly a ‘List of Parties Excluded from Federal Procurement or Nonprocurement Programs.’ Formerly, a nonprocurement debarment was effective only in the programs administered by the debarring agency, and each agency maintained Its own list The EPA Grants Administration Division operates the S&D program at EPA. The OIG supports the EPA S&D program by conducting audits, investigations, and engineering studies; obtaining documents; and providing information and evidence used in determining whether there is a cause for suspension or debarment. The OlG’s Suspension and Debarment Unit works with the Grants Administration Division to further educate and inform State and local governments and environmental interest groups about the effective use of suspensions and debarments. Suspension/Debarment Activities FY89 - FY91 r250 200 •i50 -100 -50 0 Summary of Suspension and Debarment Activities The following is a summary of S&D actions taken during this reporting period: April 1, 1991 to September 30, 1991 FY 1991 Cases opened during period 190 Cases completed • Suspensions • Debarments • Settlements 276 95 120 36 79 17 39 Subtotal — S&D action 148 238 Closed after investigation 52 102 Total cases completed 200 340 Active cases as of September 30, 1991 • Under OIG investigation • Under program review • Under OGC review • Proposed for debarment Total open cases 22 59 16 74 171 FY89 FY90 FY91 Includes suspensions. debarmen ts, and voluntary settlements 38 Office of the Inspector General Report to the Congress ------- EPA’s continuing concern to protect the public has led to an even greater expansion of its traditional suspension and debarment efforts. Environmental polluters are beginning to realize the hard way that it just doesn’t pay to spoil the environment. The day of stiff jail sentences, fines, and suspensions and debarments for environmental violations is here. The Agency’s aggressive pursuit of environmental crimes has resulted in a dramatic increase of suspension and debarment actions. The following are examples of suspension and debarment actions resulting from direct OIG involvement: An OIG proactive investigation which reviewed documents concerning effluent monitoring reports required under the National Pollutant Discharge Elimination System (NPDES) revealed that fraudulent documents were being submitted to the State of North Carolina. John G. Mason, a contract wastewater treatment operator, was found guilty as charged and was sentenced to jail and fined. Mason was also debarred from all Federal procurement and non-procurement programs for three years. • Dr. Vinh Iran, an employee of an EPA Superfund contractor, Western Analytic Laboratory, was convicted for filing false statements with the Agency on soil and water tests at Superfund sites throughout EPA’s Region Ill. Based on the conviction, EPA debarred her for six months. • Chem-TLE Environmental Services, Inc. (Chem-TLE), the EPA Emergency Response Cleanup Services Zone Contractor responsible for cleaning up a dioxin site in Lexington, Kentucky, was charged with submitting false claims to the EPA. EPA suspended and subsequently debarred Chem-TLE from all future assistance, loan and benefit programs and direct Federal procurement for three years. EPA also debarred B.F. Rippy Jr., Chem-TLE’s operations manager, and Thomas L. Ewing, the President of Chem-TLE. • Dominic Nicassio, Inc. (DNI), Dominic Nicassio, Western Pennsylvania Minority Enterprises Inc. (WPME), and Eugene Minard all allegedly participated in a scheme to fraudulently obtain EPA-funded sewer construction contracts totaling millions of dollars by misrepresenting that WPME was a legitimate minority business enterprise. EPA has suspended WPME, Minard, DNI and Dominic Nicassio. • Russell Taylor, an employee of Kansas Tunneling and Boring, Inc., (Kansas Tunneling), transported and handled explosives while Kansas Tunneling was a subcontractor on an EPA construction grant to Olathe, Kansas. Taylor pled guilty to improperly handling explosives, was convicted, fined $900, and debarred by EPA from Federal procurement and non-procurement programs for three years. These cases reflect OIG assistance in obtaining necessary documents to support a S&D action for the Agency: EPA debarred Martha C. Rose Chemicals, Inc., Kansas City, Missouri, and several Rose Chemicals officials (Sharon Hayes, Dwight E. Thomas, Jr., James B. Carolan, and Christopher Grosch) on June 18, 1991, for three years, following their convictions on charges of conspiracy to defraud EPA, and making false statements pertaining to the level of PCB’s in the retention pond at Rose Chemicals, Holden, Missouri. The court also ordered the defendants to comply with EPA regulations and pay a $74,200 balance due on an EPA Consent Decree. William Windham, the former superintendent of utilities at the wastewater treatment facility in Big Springs, Texas, was found guilty of violating the Clean Water Act by fraudulently altering effluent data reports which exceeded the plant’s National Pollutant Discharge Elimination Systems permit. Windham was sentenced to five months in prison and fined. EPA subsequently debarred Windham for three years from participating in Federal procurement and non- procurement programs. Mark lrby, former plant manager for the Lower Reedy Wastewater Treatment Plant in Greenville County, South Carolina, was convicted of violating the Clean Water Act and tampering with representative samples required to be submitted under the facility’s National Pollutant Discharge Elimination System permit. Irby was the first individual in South Carolina to be tried on charges of violating Federal environmental laws. EPA debarred Irby for three years based on his conviction. Thomas Cappozziel and his company, Bridgeport Wrecking Company, Inc., Bridgeport, Connecticut, were convicted for violating the Clean Air Act regarding the removal and handling of asbestos from buildings being demolished. EPA debarred both the company and the owner from Federal procurement and non- procurement programs for three years, based on these convictions. • Angelo Paccione, Anthony Vulpis, John McDonald, and W&W Properties were convicted under the Racketeer Influenced and Corrupt Organizations Act (RICO) for operating an illegal 70 acre landfill on Staten Island, New York, and sentenced to prison for twelve years, seven months. Based on these convictions, EPA debarred them until July 18, 2006. Apri’ 1 1991 through September 30, 1991 39 ------- OIG Management Initiatives This section discusses two initIatives by the Office of Inspector General to promote management and financial improvements and integrity in EPA’S operations. OIG Expands Its Contract Audit Program During this semiannual period, the OIG continued the long- term efforts to expand its contract audit program, while strengthening its relationship with DCAA. The efforts consisted of assuming audit cognizance of major EPA contractors, conducting contract audits, and developing plans and policies for timely, comprehensive, and aggressive audit and investigative coverage. The OlG issued formal policy guidance describing how the Offices of Audit and Investigations should coordinate their efforts with other EPA and Federal agencies. Oversight responsibility for major EPA contractors was assigned to OlG field divisions to: monitor and track the status of all audits and investigations of their assigned contractors; identify and refer indicators of fraud, and abuse to the Office of Investigations; and, use those results to help plan future audits or investigations of a particular contractor, other contractors, or an internal and management audit of EPA programs. The OlG continued to work closely with DCAA to transfer audit cognizance of major EPA contractors from DCAA to EPA. The OIG and DCAA are revising a Memorandum of Understanding for audit services and preparing guidance for DCAA auditors auditing Superfund contracts. The Office of Audit initiated a comprehensive analysis of all contractors with EPA contracts not administratively closed to identify (1) the contractors for which the OIG could assume audit cognizance, (2) the contractors for which the cognizant agency should provide more comprehensive or expedient coverage of EPA contracts, and (3) contracts whose age and low dollar amounts warrant closing without audit. The Office of Audit also began developing a detailed implementation plan for contract audit efforts. The plan, to be issued during the first quarter of fiscal 1992, will address the EPA contractor analysis, resource-related activities, training, the development of policy in various contract audit areas, and the assumption of audit cognizance for additional contractors. By September 30, 1991, the OIG had assumed audit cognizance for 12 firms, including six major Superfund contractors. Examples of significant contract audit reports performed and issued under the OlG’s direction during this period follow: A contractor who submitted a $73 million proposal for an emergency response cleanup contract was financially weak, could not support its indirect cost calculations, proposed labor rates exceeding actual costs, and could not properly account for equipment use. We recommended that the contracting officer not award a contract to this firm. Of the $627,150 of other direct costs claimed by O&R Management Corporation, $300,164 were ineligible and $228,506 were not adequately supported. The ineligible costs consisted of vehicle lease costs reimbursed by EPA but never paid to the leasing company; labor costs exceeding those actually incurred; and other costs incurred before the contract, covered by other portions of the contract, or not allowable per contract terms. An interim audit of the $5.7 million of costs claimed by Guardian Environmental Services, Inc. under two Superfund contracts concluded that $406,443 was ineligible and $1,181,840 was not supported. The unallowable costs involved equipment, materials, and personnel costs not authorized by EPA; unallowable items included in overhead rates; labor costs calculated through incorrect rates; and duplicate costs. The unsupported costs included equipment, personnel, and material charges without supporting documentation. In addition, the audit identified contractor internal control weaknesses such as inadequate segregation of duties, lack of written accounting procedures, and the failure to maintain an accounting system which identified and segregated unallowable costs. OIG Continues To Work with Agency to Implement the Chief Financial Officers Act The Chief Financial Officers (CFO) Act was enacted to bring about much needed improvements in Federal financial management. The Act provides another mechanism for the OlG and EPA management to promote improvements in financial systems and internal controls that deter fraud, waste and abuse, and to develop useful financial information for evaluating programs and making management decisions. To accomplish these objectives, the OIG’s Office of Audit is co-chairing with the Agency’s Financial Management Division an Agency-wide CEO implementation task force. The task force has met several times to explain to Agency personnel the requirements of the Act; to discuss the proposed delegation of authority for the CFO; and to request performance data related to the Agency’s trust and revolving funds. Working with the Financial Management Division, we have also established four Agency-level CEO task force workgroups to address areas Office of the Inspector General Report to the Congress ------- critical to the successful implementation of the CFO Act. The four work groups and their objectives are: (1) financial reporting - to develop a format for the annual report, including identification of performance indicators to be reported; (2) financial systems -to identify new systems or enhancements to existing systems that will be needed to meet the requirements of the CFO Act; (3) personnel issues - to assist the CFO in ensuring high quality in financial management personnel and organizations; and (4) user fees - to address the CEO requirement to perform biennial reviews of fees and charges. Employee And Public Awareness A continuing priority of the Office of Inspector General is to enhance awareness of its presence among EPA employees, grantees, firms participating in EPA programs, and the public. In this process, we are trying to make these groups aware of their responsibility to prevent, detect, and report instances of fraud, waste, and abuse. We have found that while most EPA employees, grantees, and contractors are conscientious about the economy, efficiency, and effectiveness of their work, they have little knowledge about the Office of Inspector General. We have also found that while many Agency employees and managers are concerned about the possibility of fraud and abuse in EPA and sincerely want to learn how to detect or prevent it, several others appear naive to its existence or even reject the possibility of it happening. Although they may not be in violation of law, employees who maintain anything but a strictly arm’s-length relationship with any contractor, and any contractor that performs with anything less than good faith, represent a risk to the integrity of the competitive procurement process and what EPA gets for its money. Also any contractor, grantee, or employee who claims funds in excess of or for other than the approved purpose is in violation of the law. We believe that EPA employees are in the best position to detect, prevent, and report fraud, waste, and abuse if they can recognize it. We have used a variety of media to provide information and encourage specific segments of the concerned population to recognize and report conditions or actions that threaten EPA’s resources or mission. OlG-developed publications, videotapes, presentations, and training help prepare EPA project or program managers and employees to identify and report suspected indicators of fraud that otherwise may have gone unnoticed. Semiannual Report Over 1,800 copies of each semiannual report to Congress are distributed to members of Congress on EPA-related committees, top EPA managers, news media (including wire services), State agencies administering EPA programs, State attorneys general, citizens, EPA libraries, and selected environmental groups. Personnel Security Program The personnel security program is one of the Agency’s first-line defenses against fraud. The program uses background investigations and National Agency Checks and Inquiries to review the integrity of EPA employees and contractors. During this semiannual reporting period, the Personnel Security Staff reviewed 466 investigations. The following conditions were identified and administrative actions taken: • 2 employees resigned prior to administrative removal for falsifying their SF-i 71 s, Applications for Federal Employment, by not listing previous convictions for drug trafficking and writing worthless checks. • 6 employees received oral reprimands/verbal counseling regarding failure to report delinquent taxes, delinquent debts, and previous convictions for driving while intoxicated (DWI). • 1 employee was not placed in a position as a funds certifying officer and received oral admonishment for failure to disclose financial indebtedness. • 1 employee was removed as an imprest fund cashier and received a letter of warning for failure to list previous felony charges. • 2 employees received written reprimands for falsifying their SF-i 71 s by not listing previous terminations and convictions. • 1 employee was terminated for failing to list a previous conviction for theft on the SF- 171 used to gain employment with EPA. • 1 employee received a 14- day suspension for not listing prior convictions for numerous DWI charges. April 1, 1991 through September 30, 1991 41 ------- • 1 employee was placed on a “last chance agreement” by his supervisor in lieu of being terminated for failure to list a previous termination. Under the agreement, the employee’s conduct will be closely monitored. • 11 employees had to submit corrected SF1 71s for failure to list minor offenses. • 1 contractor employee was denied access to Confidential Business Information because of failure to list a previous conviction for embezzlement. President’s Council On Integrity And Efficiency The Office of Inspector General participates in the activities of the President’s Council on Integrity and Efficiency (PCIE), which was established by Executive Order in March 1981 to attack fraud and waste, and to improve management in the Federal Government The PCIE coordinates interagency activities involving common issues, and develops approaches and techniques to strengthen the effectiveness of the entire Inspector General community. The PCIE is headed by the Deputy Director, Office of Management and Budget, and includes the statutory Inspectors General and other key Federal officials. Committee On Integrity And Management Improvement The Committee on Integrity and Management Improvement (ClMl) was established in 1984 by EPA Order 1130.1. The purpose of CIMI is to coordinate the Agency’s effort to minimize the opportunities for fraud, waste, and mismanagement in EPA programs and to advise the Administrator on policies to improve the efficiency and effectiveness of EPA programs and activities. The Committee is composed of senior EPA program and regional officials and is chaired by the Inspector General. Public Service Recognition Week To communicate support and appreciation to EPA employees at all levels, CIMI sought an opportunity for the Agency to speak out and show its commitment to human resources. As a result, ClMl developed and coordinated a series of special events during Public Service Recognition Week. The program, hosted by EPA’s Administrator, William Reilly, was highlighted by speeches from Brigadier General Evelyn Foote, former commanding general of Fort Belvoir, Virginia, and District of Columbia Mayor Sharon Pratt Dixon. Hotline Activities The OIG Hothne Center opened 37 new cases and completed and closed 27 cases during the reporting period. Of the cases closed 8 resulted in environmental, prosecutive, or administrative corrective action, while 19 did not require action. Cases that did not have immediate validity due to insufficient information may be used to identify trends or patterns of potentially vulnerable areas for Future review. The Hotline also referred 2,836 telephone callers to the appropriate program office, State agency, or other Federal agency for assistance. The following are examples of corrective action taken as a result of information provided to the OIG Hothne Center. • A complainant alleged that a manufacturing company had dumped chemical wastes In or near water supplies. A review of the complaint disclosed illegal activity which resulted in a joint investigation by EPA’s Chicago Criminal Investigations Division, the Federal Bureau of Investigations, and the U.S. Army Criminal Investigation Division. As a result, a federal grand jury in Michigan indicted six individuals for conspiracy: unlawful treatment, storage and disposal under RCRA; and failure to report a release under CERCLA. • A complainant alleged continuing contamination of residential soil and a nearby harbor from gasoline leaks. A review of the complaint disclosed that an underground gasoline storage tank had leaked, and that some contaminated soil had been removed by the responsible party. As a result of the complaint, ground water samples were collected and a device to detect gasoline vapors was provided. Two State agencies are collecting information to determine the 42 Office of the Inspector General Report to the Congress ------- impact of past underground storage tank releases on the residential area. New Hotline Poster During this semiannual reporting period, we designed and began distribution of 300 new OIG Hothne posters to all EPA facilities. An example of this new design is printed on the back cover of this report. We hope that by periodically updating the look and distribution of the Hotline poster, EPA employees and on-site contractors will be encouraged to call the OlG Hotline when they suspect any possible fraud, waste, or abuse. Professional And Organizational Development For the semiannual period ending September 30, 1991, we approved 308 traIning enrollments for a total of 959 days of training and participation in professional development seminars and conferences. For all of fiscal 1991, we approved 595 enrollments and a total of 1739 days. Contract and in-house courses conducted by the OIG are summarized below. OIG-Developed Courses • Detection and Prevention of Fraud. Although this course was developed to prepare independent public accountants doing work for the EPA OlG to detect and refer possible instances of fraud to the OlG for criminal investigation, it also increases the awareness of EPA managers and supervisors. During this reporting period, the course was substantially revised and was presented twice, to the majority of new OIG auditors. • Superfund and the Role of the 01G. This course was developed to provide OlG staffers with an understanding of the Superfund program and the role of the OlG in the program. The development of this course, coordinated by the OIG employee development specialist, was a combined effort of all three primary components of the 01G. The course consists of six units: (1) history of Superfund, (2) major concepts of the Superfund program, (3) Superfund program organizations and resources, (4) auditing cooperative agreements, (5) auditing Superfund contracts, and (6) internal (management) audits. • Effective Briefing Techniques. This course was designed to prepare auditors, investigators, and managers to give effective and persuasive presentations, deal with confrontational situations, and improve OlG relations with affected organizations or individuals. The course includes sections on effective oral communication, visual imagery, confrontational management, and a video workshop. It stresses the importance of teamwork between OIG employees and Agency management. The course was presented twice during this reporting period to mid-level and senior staff. OIG Contracted Courses • Introduction to Government Auditing. This course was designed to enhance the new auditor’s ability to understand the requirements of Federal Government auditing and to provide the individual with the skills necessary to meet these requirements. • Behavioral Aspects of Government Auditing. This course was designed for auditors, audit field supervisors, and audit managers who have contacts with personnel in organizations being audited; have contacts with affected organizations or individuals; or manage audit organizations. The course contains the basics of communication methods that are intended to make the audit work more productive for both auditor and auditee. • Contract Auditing. This course was designed for auditors and audit supervisors who are responsible for the performance and review of contract audits. • Compliance Auditing/Questioned Costs. The course analyzes policies, standards, and practices to enhance the auditor’s ability to identify, document, and report questioned costs in a governmental audit and to participate in their resolution. Total Quality Management The Office of Inspector General fully supports and participates in EPA’s commitment to Total Quality Management (TQM). As a first step toward implementing TQM as the way of life within the OIG, the Inspector General, the Deputy Inspector General and 26 managers participated in the EPA Executive Course on Quality during this reporting period. GAO “Yellow Book” Standards The OIG fully complies with the General Accounting Office “yellow book” requirements for training. These standards require anyone performing or managing Government audits to receive at least 80 hours of continuing professional training every 2 years, including at least 24 hours directly related to Government auditing. Management Development in OIG EPA has implemented an annual management development program that requires 40 hours of management development training for each supervisor and manager. The goals of the management development program are to build leadership and management skills, highlight their importance in the way we select, develop, appraise and reward managers, and provide the required resources. OlG supervisors have received training in developing individual development plans that will ensure this training is received. A workshop for the OlG Support Staff was held in Arlington, Virginia, May 14-16. The objective of the workshop was to enhance secretaries’ job performance by developing strategies for them to use to more effectively assist supervisors. Apri 1, 1991 through September 30. 1991 43 ------- Gary Chin Award Presented Janet Kasper, second from the left, and Donna Witherspoon, second from the nght, were presented the Gary C. Chin Award during OIG Week ceremonies in May. Also present were (left to right), Anthony Carrollo, Division Inspector General for Audit, Northem Division, Kasper’s supervisor; Dr. Allan Chin and Elaine Twiner, uncle and sister of Gary Chin; Letha Roache, mother of Mrs. Witherspoon; and John C. Martin, Inspector General The award will be given annually to those OlG employees who best exemplify the qualities of the late Gary C. Chin—perseverance and dedication. (photo by Tom Maloney). 44 Office of the Inspector General Report to the Congress ------- Appendix 1 Audit Reports Issued THE INSPECTOR GENERAL ACT REQUIRES A LISTING, SUBDIVIDED ACCORDING TO SUBJECT MATTER, OF EACH AUDIT REPOIRT ISSUED BY THE OFFICE DURING THE REPORTING PERIOD AND FOR EACH AUDIT REPORT, WHERE APPLICABLE, THE DOLLAR VALUE OF QUESTIONED COSTS AND THE DOLLAR VALUE OF RECOMMENDATIONS THAT FUNDS BE PUT TO BETTER USE. Questioned Costs Recommended Audit Control Auditee Final Report Ineligible Unsupported Unnecessary/ Efficiencies Number Issued Costs Costs Unreasonable (Funds Be Put Costs To Better Use) Assistant Administrator for Air and Radiation E1KAFO-03-0269-1100359 VEHICLE INSPECTION/MAINTENANCE 8/16/91 Assistant Administrator for Administration and Resources Management P1SFFO-11-0032-1100385 SUPERFUND TRUST FUND AUDIT - 9/16/91 FISCAL 1990 E1XMG1-13-0036-1400050 AUDIT FOLLOWIJP - EXTERNAL AUDITS 9/26/91 E1SFG1-05-0018-1400046 CONTRACTOR PROPERTY OVERSIGHT 9/27/91 E1AME9-11-0041-1100426 UWLIQUIDATED OBLIGATIONS IN 9/30/91 CONSTRUCTION GRANTS E1AMG1-11 -6000-1100433 ACCOUNTS RECEIVABLE FOLLOWUP 9/30/91 E1XMF1-O8-OO33-1100441 REGION 8 MANAGEMENT OF COMPUTER 9/30/91 SCIENCES CORPORATION CONTRACT ACTIVITIES E6EMPO-15-0O39-140006O MANAGEMENT OF THE INTERIM COMPUTER 9/30/91 WORKSTATION CONTRACT E6AMG1-13-0035-1400024 FACILITIES MANAGEMENT PROCUREMENTS 6/20/91 Assistant Administrator for Pesticides and Toxic Substances E1EPG1-O3-6000-1400039 ASHAA FOLLOWUP AUDIT 9/10/91 20,243 E1EPF1-05-0117-1100378 PESTICIDES INERTS 9/27/91 E1EPG1-11-OO21-1400064 QA/QC PROCEDURES UNDER THE GOOD 9/30/91 LAB PRACTICE PROGRAM E6APGO-15-0034-1400026 PESTICIDES SYSTEMS 6/28/91 Assistant Administrator for Solid Waste and Emergency Response E1SHGO-O4-0103-1400028 EMERGENCY WAIVER CRITERIA 8/14/91 E1SKE9-11-OO47-1100411 CONTROLS OVER THE SUPERFUND 9/24/91 CONTRACT LAB PROGRAM E1SJEO-O2-0157-1100431 SUPERFUND POST-SETTLEMENT 9/30/91 ACTIVITIES CDNSC DATED AUDIT Assistant Administrator for Water E1HWEO-D4-0291-1100434 CWA SECTION 404 (WETLANDS) 9/30/91 CONSOLIDATED AUDIT Financial Management 0ffice Las Vegas E1AMA1-O9-0134-1100439 REVIEW OF DISBURSEMENT FUNCTION 9/30/91 AT LAS VEGAS Office of Information and Resources Management E1RMG1-15-OO41-1400061 REVIEW OF EPA’S MAJOR INFORMATION 9/30/91 SYSTEMS Region 1 E1SGG1-O1-0184-1400025 SUPERFUND-DEOBLIGATIONS 6/18/91 Region 2 E1HWG1-02-6000-1400041 WPDES FOLLOWUP 9/12/91 Region 3 E1HWAO-O3-O4O8-1100422 DELAWARE BAY & INLAND BAYS 9/26/91 ESTUARY PROGRAM E1SHT1-O3-O396-1400059 SPECIAL REVIEW OF SUPERFUND SITE 9/27/91 CLEANUP DOCUMENTS E1SGG9-14-O012-1400053 SUPERFUWD RI/FS REVIEW OF 9/26/91 SOUTHERN MARYLAND WOOD TREATING April 1 1991 through September 30, 1991 45 ------- Audit Control Number Audit.. Questioned Costs Final Report Ineligible Unsupported Unnecessary/ Issued Costs Costs Unreasonable Costs Recommended Efficiencies (Funds Be Put To Better U ..) Region 1 E1AMG1-04-0388-1400023 IMPREST FUND - REGION 4 6/ 7/91 Region 8 E1DSC1-08-0049-1100428 REGIONAL ADMINISTRATION OF GRANTS Region 9 E1KAG1-09-6094-1400049 FOLLOWIJP REVIEW - REGION 9 AIR PROGRAM E1HTG1-D9-0156-1400051 REGION 9 IMPLEMENTATION OF STATE REVOLVING FUND TOTAL INTERNAL & MANAGEMENT AUDITS 2. CONSTRUCTION GRANT AUDITS TOTAL OF REGION 01 = 8 TOTAL OF REGION 02 = 11 E2CWLO-03-0108-1 100259 E2CWM9-03-0209- 1200020 E2CWMO-03-0145- 1200021 E2CWT- 03-0269-1200026 P2CW*7 03 0282 1200014 P2CW*7 O3 0342 1200030 P2CW*B 03 0299. 1200017 P2CW*8 03 0282 1200018 P2C l9-03-0175- 1200019 P2CWMO-03-01 15-1200022 P2C 49-03-0176- 1200023 P2C 49-03-0259- 1200024 P2CW*8 03-0049-1200028 P2CWMO-03-0231 -1200032 P2CWMO-03-0034- 1200034 P2CWM9-03-0238- 1200037 P2CWMO- 03-0232-1200038 P2CWN9-03-0244- 1300061 P2DW*8 03 O174 1300105 P2CWN9-03-0383 1300109 P2CWW O-03-0322-1300 116 TOTAL OF REGION 03 = 21 PITTSVILLE TOWN OF GARRETT CTY SANITARY CONM ANNE ARUNDEL COUNTY SALTSBURG BOROUGH OF SHICKSHINNY SANITARY LEONARDTOWN TOWN BALTIMORE COUNTY BALTIMORE COUNTY BOTETOURT COUNTY ELMHURST TOWNSHIP BATH COUNTY SERVICE AUTH HERMITAGE MUNI AUTH WASHINGTON CTY SANI DIST OF BEL AIR TOWN OF PEPPER’S FERRY TRMT AUTH GARRETT COUNTY SANI DIST BERRYVILLE TOWN OF ANNE ARUNDEL COUNTY PHILADELPHIA CITY OF WHEELING PHILADELPHIA CITY OF 668,695 1,900,486 4,351,005 9,170,238 0 2,366,711 5,245,731 E2AWT1 -01-0047- 1400021 P2CW*7 O1 -0179- 1100271 S2CWLO-O1 -0106-1100234 S2CWLO-O1 -0074-1100274 S2CWLO-01 -0071-1100277 S2CW*8 O1 -0365-1100280 S2C WLO-O1-O1O8-1100281 S2CWL9-O1 -0112-1100360 NANTTUCKET EWS EAST WINDSOR LOWELL NORTHAMPTON SOUTHBR lOGE LOWELL LOWELL MANSFIELD 0 108,991 438,336 0 0 13,499 71, 243 36,626 0 0 664,172 0 0 449,581 150,127 636,606 0 0 0 0 0 0 0 0 P2CWL9-O2-0209- 1100161 P2CWL9-O2-O312- 1100177 P2CWL9-O2-O321 -1100178 P2CWLO-O2-0O98- 1100228 P2CWL9-O2-O164- 1100270 P2CWL9-O2-O267- 1100275 P2CWL9- 02-0266-1100276 P2CWLO-O2-OO38- 1100278 P2CWL9-O2-O235-1 100304 P2CWLO-O2-OO32-1100424 P2CWL9-O2-OO36- 1100425 WESTCHESTER COUNTY NASSAU COUNTY WESTCHESTER COUNTY NASSAU COUNTY SAND LAKE PRASA PRASA ROCKLAND ROCKLAND COUNTY SD NO. 1 CAMDEN COUNTY MUA CAMDEN CNTY 1,083,074 4,508,544 0 129,408 128,389 674,684 45,547 859,711 0 1,339,316 2,864,704 1,636,565 580,617 0 0 4,292 0 0 8,651 0 0 33,615 0 0 777,066 134,044 0 75,155 551,531 0 274,264 123,315 55,462 RCRA 9/30/91 9/25/91 9/26/91 = 28 MA 5/22/91 CT 6/27/91 MA 5/30/91 MA 7/ 1/91 MA 7/ 1/91 MA 7/ 1/91 MA 7/ 1/91 MA 8/21/91 NY 4/ 2/91 NY 4/15/91 NY 4/15/91 NY 5/22/91 NY 6/27/91 PR 7/ 1/91 PR 7/ 1/91 NY 7/ 1/91 NY 7/ 9/91 NJ 9/27/91 NJ 9/27/91 MD 6/19/91 MD 6/ 7/91 MD 6/11/91 PA 6/27/91 PA 4/11/91 MD 8/22/91 MD 5/31/91 MD 6/ 3/91 VA 6/ 4/91 PA 6/17/91 VA 6/20/91 PA 6/24/91 MD 7/ 2/91 MD 8/22/91 MD 9/11/91 VA 9/12/91 MD 9/30/91 VA 9/30/91 MD 4/19/91 PA 9/12/91 WV 9/23/91 PA 9/26/91 NC 4/19/91 NC 4/29/91 SC 6/25/91 SC 7/ 1/91 GA 7/25/91 NC 4/29/91 FL 7/17/91 FL 9/26/91 100,600 61,733 59,441 135,426 136, 303 42”, 6 5 73,594 47,679 236,349 92,662 66,390 216,858 49,379 427,655 104, 174 164,571 165,060 37,317 54,810 196,729 7,164,570 9,591,302 108,292 19,962 162,867 9,454 6,873 44,113 0 206,119 6,900 0 3,000 0 177,964 0 47,402 0 6,083 52,925 56,104 0 177,964 2,985 0 17,238 0 78,647 789 267,929 924,085 4,562 0 0 0 0 0 0 0 0 0 0 0 163,504 0 0 0 0 0 0 0 163,504 0 3,159 0 0 0 0 333,339 500,002 0 0 0 0 0 0 5,052,880 E2CWM8-04-O243- 1200015 E2C I1 -04-0069-1200016 E2CWMO-04-O353- 1200025 E2CWM1-04-0415-1200027 E2CWM1 -04-0445-1200029 E2CWN8-O4-O122- 1300062 E2CWN1 -04-0052-1300086 E2AWP1-04-O11O- 1400054 AULANDER KENLY BERKELEY CO WSA EDGE F I ELD LYONS LEXINGTON HILLSBOROUGH CTY HILLSBOROUGH COUNTY 46 Office of the inspector General Report to the Congress ------- Questioned Costs Audit Control Number Auditee Final Report Ineligible Unsupported Unnecessary/ Issued Costs Costs Unreasonable Costs Recommended Efficiencies (Funds Be Put To Better Use) TOTAL OF REGION 04 = 17 TOTAL OF REGION 05 = 13 TOTAL OF REGION 06 = 4 TOTAL OF REGION 07 = 4 P2CW*8 08 009O 12D0035 SARATOGA, CITY OF P2CW*8 08 01O9 12OO036 BISMARCK, CITY OF TOTAL OF REGION 08 = 2 TOTAL OF REGION 09 = 8 P2CW*8 10 D057 11OO419 P2CW*8 10-0022-1100420 P2CW*7 10-0095-1200033 P2CW*7 10-0046-1200039 P2EWPO- 10-0086-1400058 RAYMOND, CITY OF SITKA, CITY OF CLALLAM, COUNTY OF BRISTOL BAY, BOROUGH WASHINGTON ST REVOLVING FUND TOTAL OF REGION 10 = 5 3,887,615 1,324,816 32,583.860 1,848,869 282,872 79,128 49,324 0 5,289,851 5,245,731 21,951,937 2,000,464 120,736,373 0 1,831,225 4,272,877 4,272,877 TOTAL CONSTRUCTION GRANT AUDITS 3. OTHER GRANT AUDITS = 93 75,230,750 17,553,927 136,661,107 11,349,833 P2CWNO-O4-OO18- 1300064 P2CWND-04-0048- 1300065 P2CWNO-04-0020- 1300091 P2CWN9-D4-0391 -1300102 S2CWN9-04-0195- 1300073 S2CWNO-04-0O40- 1300092 S2CWN8-O4-03D9- 1300093 S2CWN9-04-0123- 1300099 S2CWN8-O4-0425- 1300104 MAYODAN ATLANTA WILL ISTON ST. PETERSBURG JONESBORO, MT JULIET MEMPHIS LA VERGNE MURFREESBORO 41,347 149,403 10,921 83,858 364,450 440,284 2,192,930 40,653 212,208 0 0 292,689 0 0 0 1,016,314 11,251 0 0 0 0 0 0 0 236,971 0 0 E2AWT1-05-01 16-1400048 E2AWT1 -05-0391-1400063 P2CWN8-05-D509- 1300059 P2CWW9-05-D064- 1300076 P2CWN9-05-O037- 1300084 P2CWN8-05-0273- 1300090 P2CWND-05-0086- 1300115 P2CWP9-05-0O75- 1400037 P2CWP8-05-0D26- 1400038 P2CWPO-O5 -0346-1400042 P2CWP8- 05- 0594-1400043 P2CWP9-D5-007O- 1400047 P2CWPO-05-0420- 1400057 ENGLISH EWS LOOGOTEE EWS COLUMBUS MIAMI CD STRONGSVI LLE LAKE CD DPW GAL ION GARY SD GARY SD CASS CD DUPAGE CO INDIANAPOLIS LAKEW000 1,472,130 359, 095 NC 5/ 7/91 GA 5/ 7/91 SC 8/ 2/91 FL 9/ 4/91 TN 6/ 4/91 TN 8/ 2/91 TN 8/ 2/91 TN 8/14/91 TN 9/12/91 IN 9/25/91 IN 9/30/91 OH 4/ 2/91 OH 6/10/91 OH 7/ 8/91 IL 7/30/91 OH 9/26/91 IN 9/ 9/91 IN 9/ 9/91 MI 9/19/91 IL 9/20/91 IN 9/24/91 OH 9/27/91 TX 9/23/91 LA 5/10/91 NM 6/ 4/91 LA 6/19/91 MO 4/11/91 IA 6/ 4/91 IA 6/19/91 MO 7/17/91 WY 9/25/91 ND 9/27/91 188,636 0 0 227,584 0 0 79,719 132,515 0 314,854 31,937 0 95,620 49,948 0 2,833,075 0 0 24,807,211 0 0 2D7,485 42,866 D 144,463 2,100 0 3,565,238 1,589,503 0 119,975 0 0 E2CWN9-06-OO34- 13D01O8 P2CWN8-06- 0094-1300067 P2CWN9-06-0145- 1300073 P2CWN9-06-0081- 1300079 AUSTIN VINTON CLOVIS NEW IBERIA P2CWN8-07-0D52- 1300060 P2CWN8-D7-0130- 1300074 P2CWN9-D7-01 15-1300078 P2CWN8-07- 0207-1300087 INDEPENDENCE NEWTON DES MOINES POLK CO. 0’ FALLON E2AWP1 -09-0184-1400062 P2CW*8 09-0026-1100421 P2BWLO-09-D175- 1100436 S2CW*8 09 D157 13DO1 12 S2CWN9-09-OO39-13001 17 SZCWN9-O9-O032- 1300118 S2CW*8 O9 0156 13OO1 19 S2CWN9-O9-0171-130012O D 49,324 652,941 18,717 0 45,670 60,115 10,993 5,172 0 7,239,343 0 0 0 717,328 76,280 7,239,343 12,639 9,275 237,614 23,344 0 0 0 79,128 0 0 0 0 0 0 0 0 0 5,138,940 542,720 6,098,282 5,621,855 1,862,904 2,687,236 0 516,296 1,484,168 0 0 0 0 611,722 19,042,733 0 7,460,741 38,348,260 51,135,450 4,137,467 D 0 WATSONVILLE, CITY OF GLOBE, CITY OF CLARK COUNTY SD LOS ANGELES, CITY OF LOS ANGELES, CITY OF MONTEREY REG WATER POLL LOS ANGELES, CITY OF TRACY, CITY OF CA AZ NV CA CA CON CA CA CA 9/30/91 9/25/91 9/30/91 9/25/9 1 9/30/9 1 9/30/9 1 9/30/9 1 9/30/9 1 9/25 /9 1 9/25 /9 1 9/11/91 9/30/91 9/27/91 WA AK WA AK 34,891 211,666 403,577 226,764 0 0 0 0 0 885,157 17,895 125,250 0 0 0 1,146,812 229,561 528,827 C3HVK1 -01-0180-1500694 C3HVK1-D1-0181-1500695 C3HVK1 -01-0179-1500696 C3HVK1-01-D193-150 08D1 C3HVK1-O1-O243-1501039 G3HVK1 -01-0127-1500522 G3HVK1-O1-0122-1500523 MERIDEN MERIDEN MERIDEN PITTSFIELD CHICOPEE HATFIELD RYE CT 5/22/91 CT 5/22/91 CT 5/22/91 MA 6/27/91 MA 9/27/91 MA 4/ 3/91 NH 4/ 3/91 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 April 1 1991 through September 30, 1991 47 ------- Audit Control Number Auditee Questioned Costs Final Report Ineligible Unsupported Unnecessary/ Issued Costs Costs Unreasonable Costs Recommended Efficiencies (Funds Be Put To Bettor Use) G3HVK1 -01 -0121 -1500524 G3HVK1-O1- 0112-1500536 G3HVK1 -01 -0132-1500687 G3HVK1 -01-0130-1500688 G3HVK1 -01 -0147-1500690 G3HVK1-01 -0148-1500691 G3HVK1 -01-0149-1500702 G3HVK1 -01 -01 76-1500703 G3HVK1-01-0175-1500704 G3HVK1 -01 -0174-1500705 G3HVK1 -01 -0177-1500706 G3HVK1 -01 -0183-1500714 G3HVK1 -01 -0182-1500775 G3HVK1-01-0172-1500776 G3HVK1 -01-0173-1500777 G3HVK1 -01-0189-1500800 G3HVK1-01 -0190-1500802 G3HVK1 -01 -0195-1500900 G3HVK1 -01-0196-1500901 G3HVK1 -01 -0197-1500903 G3HVK1 -01 -0220-1500945 G3HVK1 -01-0222-1500948 G3HVK1 -01-0223-1500949 G3HVK1 -01 -0221 -1500951 N3HVK1-01 -0077-1500521 N3HVK1 -01 -0087-1500535 N3HVK1-01-0108-1500537 N3HVK1-01 -0107-1500540 N3HVK1-01 -0078-1500634 N3HVK1 -01 -0126-1500635 N3HVK1 -01 -0086-1500686 N3HVK1 -01-0109-1500689 N3HVK1-01-0167-1500715 N3HVK1 -01 -0163-1500723 N3HVK1 -01 -0188-1500724 W3HVK1 -01-0106-1500771 N3HVK1 -01-0198-1500904 N3HVK1 -01 -0217-1500905 N3HVK1 -01-0144-1501018 W3HVK1 -01-0186-1501019 N3HVKO-01 -0270-1501040 SANDWICH DOVER CONCORD BRISTOL CHARLES RIVER POLL. DIST. ORLEANS, BREWSTER, EASTHAM HART FORD NARRAGANSETT BAY COMM NARRAGANSETT BAY COMM NARRAGANSETT RAY COMM NARRAGANSETT BAY COMM WI NCHESTER MA WATER RESOURCES AUTHOR. MA WATER RESOURCES AUTHORITYMA MA WATER RESOURCE AUTHORITY MA WEBSTER MA MAINE MUNICIPA; BOND BANK ME CHELMSFORD MA EXETER NH SOUTH ESSEX SEWAGE DIST. SPENCER MA FAIRHAVEN MA WARREN MA BRIDGEWATER MA NASHUA NH HARTFORD CT METRO AREA PLNG. COUNCIL MA ROCKINGHAM PLNG. COMM. NH BERKSHIRE CNTY. REG. PLMG. MA MONTACHUSETT REG. PLNG. COMMMA DANBURY CT MANCHESTER NH BARNSTABLE COUNTY MA BROCKTON , MA BARNSTABLE COUNTY MA NEW HAMPSHIRE, STATE OF NH PIONEER VALLEY PLANNING CON MA NORTHERN MIDDLESEX COUNCIL MA INDIAN TOWNSHIP TRIBAL GOVTME SACO ME SOUTHEASTERN REG PLANNING MA 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 TOTAL OF REGION 01 = 48 3,828,912 0 0 G3HVK1 - 02-0091-1500546 G3HVK1 -02-0103-1500656 G3HVK1 -02-0105-1500679 G3HVK1 -02-0107-1500758 G3HVK1 -02-0108-1500759 G3HVK1 -02-0116-1500778 G3HVK1 -02-0140-1500975 N3HVK1 -02-0077-1500605 N3HVK1 -02-0098-1500614 N3HVK1 -02-0099-1500615 N3HVK1 -02-0100-1500654 N3HUK1 -02-0101-1500655 N3HVK1 -02-0102-1500678 N3HVK1 -02-0081 -1500757 N3HVKO-O2- 0207-1500976 N3HVKO-O2-O289- 1500977 N3HVK1 -02-0063-1500978 N3HVK1 -02-0141-1500979 N3HVK1 -02-0142-1500984 N3HVK1 -02-0106-1501001 N3HVK1 -02-0143-1501002 N3HVK1 -02-0137-1501037 BYRON LANDIS SA GREAT NECK WPCD GLOVERSVILLE-JOHNSTOWN JT CAPE MAY COUNTY HUA INTERSTATE SANITATION COMM LANCASTER NASSAU COUNTY CHAUTAUQUA COUNTY MI LLVI LLE CHAUTAUQUA COUNTY RESEARCH FOUNDATION OF SUNY R IVERHEAO WASHINGTON COUNTY GOUVERNEUR LOGAN ROCKLAND YORKTOWN DEXTER WEST SENECA SCHUYLERVI LLE KINGSTON NY 4/ 8/91 NJ 5/ 7/91 NY 5/13/91 NY 6/17/91 NJ 6/17/91 NY 6/25/91 NY 8/14/91 NY 4/23/91 NY 4/29/91 NJ 4/29/91 NY 5/ 7/91 NY 5/ 7/91 NY 5/13/91 NY 6/17/91 NY 8/14/91 NJ 8/14/91 NY 8/14/91 NY 8/14/91 NY 8/16/91 NY 8/26/91 NY 8/26/91 NY 9/17/91 0 0 0 0 0 0 0 0 0 0 0 0 0 184,250 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 TOTAL OF REGION 02 = 22 0 184,250 0 0 0 0 0 0 0 0 0 0 NH 4/ 3/91 NH 4/ 4/91 MA 5/20/91 CT 5/20/91 MA 5/21/91 MA 5/21/91 VT 5/30/91 RI 5/31/91 RI 5/31/91 RI 5/31/91 RI 5/31/91 NH 6/ 5/91 MA 6/24/91 6/24/91 6/24/91 6/27/91 6/27/91 7/19/91 7/19/9 1 7/23/91 8/ 6/91 8/ 6/91 8/ 6/91 8/ 6/91 4/ 3/91 4/ 4/91 4/ 4/91 4/ 4/91 5/ 1/91 5/ 1/91 5/20/91 5/21/91 6/ 5/91 6/11/91 6/20/91 6/19/91 7/23/91 7/23/91 9/ 4/91 9/ 4/91 9/ 27/9 1 0 0 0 0 0 0 0 0 0 0 0 0 3,828,912 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 C3HVK1-O3-O067-150055O CARROLL COUNTY 6/90 MD 4/ 9/91 0 0 C3HVK1-O3-0183-1500603 FAIRFAX COUNTY VA 4/22/91 0 0 C3HVK1-O3-O271-1500794 WASHINGTON COUNTY 6/90 M D 6/26/91 0 0 C3HVJ1-O3-O315-1500952 VA AIR POLLUTION CONTROL VA 8/ 6/91 0 4,847 G3HVK1-O3-O152-1500552 OAKLAND TOWN OF MD 4/ 9/91 42,020 0 G3HVK1-O3-0153-1500553 OAKLAND TOWN OF MD 4/ 9/91 0 0 G3HVK1-O3-O154-1500554 OAKLAND TOWN OF M D 4/ 9/91 332,955 0 G3HVK1-O3-O18O-1500563 INTERSTATE CON POTOMAC RIVERMD 4/11/91 0 0 G3HVK1-03-O190-1500598 BUCKINGHAN TOWNSHIP PA 4/22/91 0 0 48 Office of the Inspector General Report to the Congress ------- Questioned Costs Audit Control Number Auditee Recommended Final Report Ineligible Unsupported Unnecessary/ Efficiencies Issued Costs Costs Unreasonable (Funds Be Put Costs To Better Use) TOTAL OF REGION 03 = 43 489,899 868,847 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 G3HVK1-O3-0189-1500599 LAKE CITY MUNICIPAL SEWER PA 4/22/91 0 0 G3HVK1-O3-0188-1500600 LAKE CITY MUNICIPAL SEWER PA 4/22/91 0 0 G3HVK1-O3-O187-15006O1 LAKE CITY MUNICIPAL SEWER PA 4/22/91 0 0 G3HVK1-O3-O186-15006O2 LAKE CITY MUNICIPAL SEWER PA 4/22/91 0 0 G3HVK1-03-O240-1500712 LANESBORO PA 6/ 4/91 0 0 G3HVK1-03-O239-1500713 LEE COUNTY VA 6/ 4/91 0 0 G3HVK1-O3-O276-1500815 BEAR CREEK WATER SHED AUTHO PA 7/ 1/91 0 864,000 G3HVK1-O3-O277-1500817 GREEN VALLEY GLENW000 Wv 7/ 1/91 0 0 G3HVK1-O3-O279-1500818 NEW HOLLAND BOROUGH AUTHORITPA 7/ 1/91 0 0 G3HVK1-03-O28O-1500872 MILFORD CITY OF DE 7/11/91 0 0 G3HVK1-03-O281-1500873 BELLEFONTE BOROUGH AUTH PA 7/11/91 0 0 G3HVK1-03-O292-1500874 GARRETT COUNTY MD 7/11/91 0 0 G3HVK1-03-0293-1500875 ST. MARY’S COUNTY MD 7/11/91 0 0 G3HVK1-O3-0317-1500946 WAYNESBURG BOROUGH OF 12/90 PA 8/ 6/91 0 0 G3HVK1-03-0319-1500950 PLUM BOROUGH SEWER AUTH PA 8/ 6/91 114,924 0 G3HVK1-03-0320-1500953 ALTOONA CITY AUTHORITY PA 8/ 6/91 0 0 G3HVK1-O3-0323-1500954 SAINT THOMAS TOWNSHIP PA 8/ 6/91 0 0 G3HVK1-03-0316-1500958 WAYNESBURG BOROUGH OF 12/88 PA 8/ 6/91 0 0 N3HVJ1-O3-O108-1500551 WYOMING COUNTY WV 4/ 9/91 0 0 N3HVK1-03-0O78-1500584 WASHINGTON COUNCIL OF GOVT DC 4/18/91 0 0 N3HVK1-O3-0185-1500585 FREDERICK CITY OF MD 4/18/91 0 0 N3HVK1-O3-OO79-1500586 ALLEGHENY COUNTY PA 4/18/91 0 0 N3HVKO-O3-O417-1500597 DC DEPT OF PUBLIC WORKS DC 4/22/91 0 0 N3HUJ1-03-O142-1500816 UNIVERSITY OF VIRGINIA VA 7/ 1/91 0 0 N3HVK1-03-0151-1500819 NATIONAL COUNCIL OF SENIOR DC 7/ 1/91 0 0 N3HUJ1-03-O147-150082O VA COMMONWEALTH UNIVERSITY VA 7/ 1/91 0 0 N3HVKO-03-0355-1500821 BALTIMORE CITY OF MD 7/ 1/91 0 0 N3HVJ1-03-0184-1500829 VIRGINIA POLYTECHIC INSTIT VA 7/ 1/91 0 0 N3HVJ1-03-O018-150083O VA DEPT OF ARGICULTURE & CO VA 7/ 1/91 0 0 N3HVK1-03-0135-1500871 ERIE COUNTY PA 7/11/91 0 0 N3HUK1-03-O318-1500947 UNIVERSITY OF PITTSBURGH PA 8/ 6/91 0 0 N3HVK1-03-0314-1500955 HOWARD COUNTY MARYLAND MD 8/ 6/91 0 0 N3HVK1-O3-0326-1500956 EMMITSBURG TOWN OF MD 8/ 6/91 0 0 N3HVJ1-03-O236-1500957 VA DEPT OF HEALTH VA 8/ 6/91 0 0 C3HVK1-O4-0142-15005O8 NASHVILLE & DAVIDSON COUNTY TN 4/ 5/91 0 C3HVK1-O4-O228-1500526 AL DEPT ENVIRONMENTAL MGMT AL 4/ 3/91 11,880 C3HVJ1-O4-0157-1500621 JEFFERSON COUNTY COMMISSION AL 4/29/91 0 C3HVJ1-04-O16O-1500622 JEFFERSON COUNTY COMMISSION AL 4/26/91 0 C3HVK1-04-0158-1500651 FT. LAUDERDALE FL 5/ 6/91 0 C3HVK1-04-0269-1500766 JEFFERSON COUNTY FISCAL COURKY 6/18/91 0 C3HVK1-04-O27O-1500767 TALLAHASSEE FL 6/18/91 0 C3HVK1-04-0281-1500797 LEXINGTON-FAYETTE COUNTY KY 6/27/91 0 C3HVJ1-O4-0276-1500798 MONTGOMERY COUNTY AL 6/27/91 0 C3HVK1-04-0391-15O1O34 JACKSONVILLE FL 9/11/91 0 C3HVK1-O4-04O3-15O1035 PENSACOLA FL 9/11/91 0 G3HVK1-O4-0229-1500525 MOUNT CARMEL TN 4/ 3/91 0 G3HVK1-O4-O145-1500544 ASHFORD AL 4/ 8/91 0 G3HVK1-O4-O146-1500545 ASHFORD AL 4/ 8/91 0 G3HVK1-O4-0143-1500559 BAILEY NC 4/11/91 0 G3HVK1-O4-0144-1500561 BAILEY NC 4/11/91 0 G3HVK1-O4-0148-15006O9 CHOCOWINITY NC 4/29/91 0 G3HVK1-04-0152-150061O BOILING SPRINGS NC 4/29/91 0 G3HVK1-04-0151-1500611 CLAYTON AL 4/29/91 0 G3HVK1-04-0150-1500612 CHICKAMAUGA GA 4/29/91 0 G3HVK1-O4-0149-1500613 CHICKAMAUGA GA 4/29/91 0 G3HVK1-O4-0174-1500643 LEIGHTON AL 5/ 3/91 0 G3HVK1-O4-0165-1500644 JONESVILLE NC 5/ 3/91 0 G3HVK1-04-O161-1500646 HOPE MILLS NC 5/ 3/91 0 G3HVK1-O4-0162-1500647 HOPE MILLS NC 5/ 3/91 0 G3HVK1-04-O164-1500648 CONYERS GA 5/ 3/91 0 G3HVK1-04-O181-1500658 ROBERSONVILLE NC 5/ 7/91 0 G3HVK1-04-0180-1500659 ROBERSONVILLE NC 5/ 7/91 0 G3HVK1-O4-0182-150066O ROBERSONVILLE NC 5/ 7/91 0 G3HVK1-O4-0183-1500661 PHIL CAMPBELL AL 5/ 7/91 0 G3HVK1-O4-0184-1500662 PHIL CAMPBELL AL 5/ 7/91 0 G3HVK1-04-O188-1500665 STALLINGS NC 5/ 9/91 0 G3HVK1-O4-O196-1500667 SPARTA NC 5/ 8/91 0 G3HVK1-04-O198-1500668 SPARKS GA 5/ 8/91 0 G3HVK1-04-O197-1500669 SPARTA NC 5/ 8/91 0 G3HVK1-04-0199-1500670 SALEMBURG NC 5/ 8/91 0 G3HVK1-04-0191-1500674 WHITE LAKE NC 5/10/91 0 G3I4VK1-04-019O-1500675 WHITE LAKE NC 5/10/91 0 G3HVK1-04-0168-1500676 HANCEVILLE AL 5/10/91 0 G3HVK1-04-0189-1500677 WHITE LAKE NC 5/10/91 0 G3HVK1-04-0237-1500716 BLOWING ROCK NC 6/ 5/91 0 0 April 1 1991 through September 30, 1991 49 ------- Audit Control Number Audite. Questioned Costs Final Report Ineligible Unsupported Issued Costs Costs Unnecessary/ Unreasonable Costs Recommended Efficiencies (Funds B. Put To Better Use G3HVK1 -04-0240-1500717 G3HVK1 -04-0241 -1500718 G3HVK1 -04-0179-1500725 G3HVK1 -04-0244-1500726 G3HVK1 -04-0396-1500727 G3HVK1 -04-0266-1500728 G3HVK1 -04-0254-1500729 G3HVK1 -04-0247-1500730 G3HVK1 -04-0243-1500731 G3HVKI -04-0245-1500732 G3HVK1 -04-0242-1500733 G3HVK1 -04-0262-1500736 G3HVK1 -04-0204-1500745 G3HVK1 -04-0203-1500746 G3HVK1 -04-0337-1500747 G3HVK1 -04-0194-1500748 G3HVK1 -04-0202-1500749 G3HVK1 -04-0275-1500765 G3HVK1 -04-0215-1500780 G3HVK1 -04-0214-1500781 G3HVK1 -04-0218-1500782 G3HVK1 -04-0217-1500783 G3HVK1 -04-0280-1500786 G3HVK1 -04-0282-1500786 G3HVK1 -04-0284-1500787 G3HVK1 -04-0219-1500795 G3HVK1 -04-021!- 1500796 G3HVK1 -04-0298-1500822 G3HVK1 -04-0297-1500823 G3HVK1 -04-0301-1500824 G3HVK1 -04-0302-1500825 G3HVK1 -04-0300-1500826 G3HVK1 -04-0304-1500827 G3HVK1 -04-0306-1500844 G3HVK1 -04-0293-1500848 G3HVK1 -04-0308-1500849 G3HVK1 -04-0294-1500850 G3HVK1 -04-0327-1500863 G3HVK1 -04-0325-1500864 G3HVK1 -04-0326-1500865 G3HVK1 -04-0324-1500866 G3HVK1 - 04-0329-1500887 G3HVKI -04-0328-1500888 G3HVK1 -04-0331-1500890 G3HVK1 -04-0239-1500891 G3HVK1 -04-0238-1500895 G3HVK1 -04-0335-1500896 G3HVK1 -04-0234-1500897 G3HVK1 -04-0232-1500899 G3HVK1 - 04-0261-1500906 G3HVKI -04-0285-1500907 G3HVK1-04-0286-1500908 G3HVK1 -04-0260-1500912 G3HVK1 -04-0271-1500916 G3HVK1 -04-0279-1500917 G3NVK1 -04-0344-1500918 G3HVK1 -04-0346-1500919 G3HVK1 -04-0251-1500980 G3HVK1 -04-0250-1500981 G3HVK1-04-0384-1500988 G3HVK1 -04-0364-1500990 G3HVK1 -04-0363-1500991 G3HVKI -04-0255-1500992 G3HVK1 -04-0235-1500994 G3HVK1 -04-0303-1500995 G3HVK1 -04-0305-1500996 G3HVKI -04-0372-1500997 G3HVK1 -04-0336-1500998 G3HVK1 -04-0371-1500999 G3HVK1-04-0375-150’006 G3HVK1 -04-0376-1501007 G3HVK1 -04-0369-1501008 G3HVK1 -04-0252-1501020 G3HVK1 -04-0390-1501021 G3HVK1 -04-0389-1501022 G3HVK1 -04-0358-1501023 G3HVK1 -04-0394-1501024 G3HVK1 -04-0368-1501027 ELKTON KY ELKTON KY NAHUNTA GA FREEPORT FL ABBEVILLE AL ABBEVILLE AL HIGH SHOALS NC FLEMINGSBURG KY CORINTH MS FRANKLIN WATER & SEWER AUTH NC CORINTH MS LEXINGTON NC BARNWELL SC BARNWELL SC LAKE LURE NC ASHEBORO NC BARNWELL SC LAKELAND FL FORT DEPOSIT AL FORT DEPOSIT AL HALEYVILLE AL HALIFAX NC MOUWDVILLE AL QUITMAN GA ROWLAND NC LENOIR NC EDENTO$I NC HUNTSVILLE TN LOUISVILLE & JEFFERSON CO SDKY MS MS KY KY MS GA MS MS #KY NC NC MS AL AL SC NC NC FL KOSCIUSKO KOSCIUSKO I NEZ VINE GROVE LAUREL WARRENTON HARRISON COUNTY WASTEWATER liT! CA BOYD & GREENUP COUNTIES SD MICRO MICRO PEARL CHATAM UTILITIES BOARD CHATAI4 UTILITIES BOARD NEWBERRY CTY WATER & SEWER STAR STAR WEST MELBOURNE PRICHARD WATER WORKS & SEWERAL SPENCER NC LYONS GA LAKE LORMAN UTILITY 01ST MS LAKE LORMAN UTILITY DISTRICTMS LYONS GA PLANT CITY FL PUCKETT MS SANFORD FL SALTILLO MS FULTON KY FULTON KY COLLIER COUNTY FL CLAYTON AL REIDSVILLE GA HAINES CITY FL OLD FORT NC VINE GROVE KY VINE GROVE KY ATMORE AL LOUISVILLE MS ARCADIA FL WAVELAND REGIONAL WUMO MS RINCON GA SACREMENTO KY FULTON KY HICKORY NC HICKORY NC DOTHAN AL DALTON WATER LIGHT & SINKINGGA JASPER WATERWORKS & SEWER SDAL 6/5/91 0 0 0 6/5/91 0 0 0 616/91 0 0 0 6/10/91 0 0 0 6/11/91 0 0 0 6/10/91 0 0 0 6/10/91 0 0 0 6/10/91 0 0 0 6/7/91 0 0 0 6/10/91 0 0 0 6/7/91 0 0 0 6/12/91 0 0 0 6/12/91 0 0 0 6/12/91 0 0 0 6/12/91 0 0 0 6/12/91 0 0 0 6/12/91 0 0 0 6/18/91 0 0 0 6/25/91 0 0 0 6/25/91 0 0 0 6/25/91 0 0 0 6/25/91 0 0 0 6/25/91 0 0 0 6/25/91 0 0 0 6/25/91 0 0 0 6/27/91 0 0 0 6/27/91 0 24,351 0 7/1/91 0 0 0 7/1/91 0 0 0 7/1/91 0 0 0 7/1/91 0 0 0 7/1/91 0 0 0 7/1/91 0 0 0 7/2/91 0 0 0 7/3/91 0 0 0 7/3/91 0 0 0 7/3/91 0 0 0 7/10/91 0 0 0 7/10/91 0 0 0 7/10/91 0 0 0 7/10/91 0 0 0 7/17/91 0 0 0 7/17/91 0 0 0 7/17/91 0 0 0 7/17/91 0 0 0 7/18/91 0 0 0 7/18/91 0 0 0 7/18/91 0 0 0 7/18/91 0 0 0 7/23/91 0 0 0 7/23/91 0 0 0 7/23/91 0 0 0 7/24/91 0 0 0 7/24/91 0 0 0 7/24/91 0 0 0 7/24/91 0 0 0 7/24/91 0 0 0 8/14/91 0 0 0 8/14/91 0 0 0 8/22/91 0 0 0 8/22/91 0 0 0 8/22/91 0 0 0 8/22/91 0 0 0 8/22/91 0 0 0 8/22/91 0 0 0 8/22/91 0 0 0 8/22/91 0 0 0 8/22/91 0 0 0 8/22/91 0 0 0 8/27/91 0 0 0 8/27/91 0 0 0 8/27/91 0 0 0 9/5/91 0 0 0 9/5/91 0 0 0 9/5/91 0 0 0 9/5/91 0 0 0 9/6/91 0 0 0 9/6/91 0 0 0 50 Ottice ot the Inspector General Report to the Congress ------- Questioned Costs G3HVK1-04-0530- 1501029 N3HVK1-04-0113- 1500558 N3HVJO-04-0391 -1500560 N3HVK1 -04-0103-1500623 N3HvK1-04-0166- 1500636 N3HVK1 -04-0167-1500637 N3HVK1-04-0175- 1500652 N3HVK1 -04-0176- 1500653 N3HVK1 -04-0084-1500657 N3HVK1-04-0195- 1500666 N3HVK1-04-0045- 1500671 N3HVK1-04-0171-150 0711 N3HVK1 -04-0192-1500743 N3HVK1-04-0193- 1500744 N3HVK1 -04-0295-1500779 N3HVK1-04-0283- 1500785 N3HVK1-04-0292- 1500799 N3HVJ1 -04-0256-1500828 N3HVJ1 -04-0257-1500837 N3HVJ1 -04-0287-1500839 N3HVK1-04-0107- 1500841 N3HVK1 -04-0177-1500843 N3HVK1 -04-0312-1500846 N3HVK1 -04-0313-1500847 N3HVKO-04-0245- 1500854 N3HVK1-04-0085- 1500855 N3HUK1 -04-0342-1500861 N3HVK1-04-0101-15 0 0862 N3HUK1-O4-0087- 1500867 N3HVK1-04-0330- 1500889 N3HUK1 -04-0334-1500898 N3HVJ1 -04-0453-1500909 N3HVK1-04-0178- 1500910 N3HVK1 -04-0430-1500911 N3HVK1 -04-0170-1500913 N3HUK1 -04-0366-1500989 N3HVK1-04-0264- 1500993 N3HVK1 -04-0382- 1501000 N3HUK1-04-0370- 1501025 N3HVK1 -04-0406-1501026 NICEVILLE FL BUNCOMBE COUNTY NC AL GEOLOGICAL SURVEY AL RALEIGH NC HYDE COUNTY NC HYDE COUNTY NC PAMLICO COUNTY NC PAMLICO COUNTY NC SALISBURY NC STALLINGS NC WASHINGTON NC NAHUNTA GA ASHEBORO NC ASHEBORO NC ORLANDO FL QUITMAN GA WARRENTON GA GA DEPT. OF EDUCATION GA GA DEPT. OF AGRICULTURE GA GA DEPT NATURAL RESOURCES GA LANCASTER KY PAMLICO COUNTY NC OWENTON KY OWENTON KY MEMPHIS TN WINSTON-SALEM NC RESEARCH TRIANGLE PARK NC VALDOSTA GA CLEMSON UNIVERSITY SC OAKGROVE KY GEORGIA, UNIVERSITY OF GA GEORGIA FORESTRY COMMISSION GA NEW HANOVER COUNTY NC BRISTOL TN NEW HANOVER COUNTY NC WEST GEORGIA COLLEGE GA UNION COUNTY NC HUNTSVILLE AL LOUISVILLE UNIVERSITY OF KY NORTHERN KENTUCKY UNIVERSITYKY TOTAL OF REGION 04 = 159 9/10/91 4/11/91 4/11/91 4/25/91 5/ 1/91 5/ 1/91 5/ 6/91 5/ 6/91 5/ 7/91 5/ 9/91 5/ 9/91 6/ 4/91 6/12/9 1 6/12/91 6/25/91 6/25/91 6/27/91 7/ 1/91 7/ 2/91 7/ 2/91 7/ 2/91 7/ 2/91 7/ 3/91 7/ 3/91 7/ 9/91 7/ 9/91 7/10/91 7/10/91 7/10/91 7/17/91 7/18/91 7/23/91 7/24/91 7/24/91 7/24/91 8/22/91 8/22/91 8/22/91 9/ 6/91 9/ 6/91 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2.928 0 0 14,808 24,351 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 C 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Audit Control Number Auditee Final Report Ineligible Unsupported Issued Costs Costs Unnecessary/ Unreasonable Costs Recommended Efficiencies (Funds Be Put To Better Use) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 C3HVJ1-05-O374 -15009O2 CANTON FY 88 OH 7/22/91 0 0 C3HVJ1-05-O396-1500983 ILLINOIS EPA FY 89/90 IL 8/15/91 0 0 C3HVK1-05-O432-1501O17 GRAND RAPIDS FY 90 MI 9/ 3/91 0 0 C3HVK1-05-O423-15O1O45 LANSING FY 90 MI 9/30/91 0 G3HVJ1-05-O227-1500541 MARKLEVILLE FY 88/89 IN 4/ 5/91 0 6,681 0 G3HVK1-O5-0226-1500542 LE SUEUR FY 89 MN 4/ 5/91 0 0 G3HVK1-05-0230-1500543 STEWARTVILLE FY 90 MN 4/ 5/91 0 0 G3HVK1-05-O233-1500562 MANTORVILLE FY 90 MN 4/11/91 0 0 G3HVK1-O5-0252-1500573 W CHICAGO FY 90 IL 4/17/91 0 0 G3HVK1-O5-O249-1500574 CAMPBELLSPORT FY 90 WI 4/17/91 0 0 G3HVJ1-O5-0250-1500575 FT BRANCH FY 90 IN 4/17/91 0 0 G3HVJ1-O5-O251-1500576 SHIRLEY FY 88/89 IN 4/17/91 0 0 G3HVJ1-05-0248-1500578 WILMINGTON FY 89 OH 4/17/91 0 0 G3HVK1-O5-O254-1500588 HEWITT FY 90 MM 4/19/91 0 0 G3HVJt-O5-O258-150063O WAUSEON FY 89 OH 4/29/91 0 0 G3HVK1-O5-O269-1500631 G3HVK1-O5-O268-1500632 ROYALTON FY 89 ULEN FY 89/90 MN MN 4/29/91 4/29/91 0 0 0 0 G3HVK1-05-0266-1500633 G3HVJ1-05-O293-1500698 HUBBARD SD FY 90 CYNTHIANA FY88/89 WI IN 4/29/91 5/29/91 0 0 0 0 G3HVK1-05-0299-1500699 G3HVK1-O5-0300-15007O1 BROWNTON FY 90 SILVER LAKE FY 90 MM MN 5/29/91 5/29/91 0 0 0 0 G3HVK1-O5-O3O1-15007O9 G3HVJ1-05-O294-150071O G3HVJ1-05-O311-1500734 G3HVK1-O5-0312-1500735 G3HVK1-05-O318-1500805 G3HVJ1-05-O330-1500806 G3HVK1-05-0370-1500883 G3HVK1-05-O362-1500884 G3HVJ1-05-O314-1500886 G3HVJ1-05-O336-1500914 G3HVK1-O5-O371-1500933 G3HVK1-O5-O337-1500934 G3HVK1-05-O372-1500935 G3HVK1-05-O376-1500936 MAYNARD FY 90 CHANDLER FY 88/89 SHARPSVILLE FY 88/89 MONROE CITY FY 90 PIPESTONE FY 90 PETERSBURB FY 90 BARTLETT FY 90 NAPPANEE FY 90 NILES FY 89 MARIETTA FY 86 SPRINGFIELD FY 90 DODGE CENTER FY 90 LONG PRAIRIE LOWELL FY 90 MM IN IN MI MM IN IL IN OH OH MN MN MN MI 6/ 3/91 6/ 3/91 6/11/91 6/11/91 6/28/91 6/28/91 7/15/91 7/15/91 7/15/91 7/19/91 8/ 1/91 8/ 1/91 8/ 1/91 8/ 1/91 0 0 0 0 0 0 0 0 0 0 0 1,200 0 0 0 0 0 0 0 0 0 0 0 0 0 192,805 0 0 April 1 1991 through September 30, 1991 51 ------- Questioned Costs Audit Control Number Auditee Recommended Final Report Ineligible Unsupported Unnecessary! Efficiencies Issued Costs Costs Unreasonable (Funds Be Put Costs To Better Use) TOTAL OF REGION 05 = 53 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 199,486 0 C3HVKI -07-0183-1500969 G3HVK1 -07-0107-1500527 G3HVK1 -07-0108-1500528 G3HVK1 -07-0109-1500529 G3HVK1 -07-0110-1500530 G3HVK1 -07-0112-1500531 G3HVKI -07-0113-1500532 G3HVK1 -07-0114-1500533 G3HVK1 -07-0115-1500534 G3HVK1 -07-0116-1500538 G3HVK1 -07-0117-1500539 G3HVK1 -07-0122-1500572 G3HVK1-07 -O11 1-1500595 G3HVK1 -07-0130-1500719 G3HVK1 -07-0147-1500737 G3HVK1 -07-0146-1500738 G3HVK1-07-0145-1500739 G3HVK1 -07-0132-1500741 G3HVK1 -07-0131-1500742 G3HVK1 -07-0133-1500753 CEDAR RAPIDS MARYVI LIE STORY CITY ST. PETERS SALEM KIMBERLING CITY DIAMOND VALENT INE ALLIANCE ALL lANCE WEBB CITY LAJ4OWTE, CITY OF SALEM MENLO NORTHEAST PUBLIC SEWER DIST CITY OF OSAWATCi4IE MACOW CITY OF VILLAGE OF I4ORRILL DUCKETT CREEK SEWER DIST CITY OF LIBERTY CO 8/12/91 MO 4/ 3/91 IA 4/ 3/91 NO 4/ 3/91 MO 4/ 2/91 MO 4/ 3/91 MO 4/ 3/91 NE 4/ 4/91 NE 4/ 4/91 NE 4/ 4/91 MO 4/ 4/91 MO 4/16/91 MO 4/19/91 IA 6/ 6/91 M C 6/12/91 KS 6/12/91 6/12/91 NE 6/12/91 MO 6/12/91 MO 6/13/91 G3HvK1-O5-O375-1500937 PARK RAPIDS FY 90 MM 8/ 1/91 0 G3HvK1-O5-04O4-1500940 PINCKNEY FY 91 MI 8/ 1/91 11,414 G3HVK1-O5-O4O5-1500941 S ST PAUL FT 90 MN 8/ 1/91 0 G3HVK1-05-O398-1500942 N HOUGHTON CUS MI 8/ 1/91 0 G3HVK1-05-0406-1500965 NEORSD FY 90 OH 3/ 8/91 0 G3HVJ1-05-O413-1500971 U LEBANON FT 88/89 IN 8/12/91 2,947 G3HVK1-05-0418-1500985 RUSSELL FY 90 MN 8/16/91 0 G3HVK1-05-O417-1500986 LA CRESCENT FY 90 MM 8/16/91 0 G3HUJ1-05-042O-1500987 NEW LONDON LSD FY 90 OH 8/16/91 0 N3HVKI-05-0273-1500684 WHITE EARTH RESERVE Fl 89 MN 5/16/91 0 N3HVJ1-05-0196-1500685 LANCASTER FT 88 OH 5/16/91 0 N3HVJ1-05-0255-1500722 MICHIGAN DPH FT 88/89 MI 6/ 7/91 0 N3HVJ1-05-O199-1500751 CUYAHOGA CO FY 89 OK 6/13/91 0 N3HVJ1-05-0333-1500807 LANCASTER FT 90 OH 6/28/91 0 N3HUK1-D5-O331-15008O8 LOYOLA U FY 89/90 IL 6/28/91 0 N3HVJI-O5-0332-1500885 OHIO ST U Fl 88 OH 7/15/91 0 N3HVK1-O5-0231-1500938 MENOMINEE IT FY 90 WI 8/ 1/91 0 N3HVK1-05-0270-1500939 ONEIDA TRIBE FY 90 WI 8/ 1/91 0 15,561 C3HVJ1-O6-O094-1500583 ARKANSAS DEPT OF P01. CONTR.AR 4/18/91 0 0 0 C3HVK1-O6-0095-1500624 SAN ANTONIO TX 4/29/91 0 0 0 C3HVK1-O6-O102-1500664 SHREVEPORT LA 5/ 9/91 0 0 0 C3HVK1-O6-O14O-1500880 ARKANSAS DEPT. OF POLLUTION AR 7/12/91 0 0 0 C3HVK1-06-O145-1501028 WICHITA FALLS TX 9/ 9/91 0 0 0 G3HVK1-06-OO89-1500548 CLUTE TX 4/ 9/91 0 0 0 G3HVK1-O6-0O90-1500549 CLUTE TX 4/ 9/91 0 0 0 G3HVK1-06-O092-1500555 TEXARKANA TX 4/11/91 0 0 0 G3HVK1-06-0O93-1500582 DERIDDER LA 4/18/91 0 0 0 G3HVK1-O6-DO98-1500596 KINGFISHER OK 4/19/91 0 0 0 G3HVK1-06-O100 -1 500645 CLEBURNE TX 5/ 3/91 0 0 0 G3HVK1-06-O101-1500663 TEXARKAP4A TX 5/ 8/91 0 950 0 G3HVK1-06-O128-1501O13 SLATON TX 8/30/91 0 0 0 G3HVK1-06-O125 1501014 NEW DEAL TX 8/30/91 0 0 0 G3HVK1-06-O126-1501015 NEW DEAL TX 8/30/91 0 0 0 G3HVKI-06-0127-15O1O16 MAGNOLIA SEWER SYSTEM AR 8/30/91 0 0 0 G3HVK1-06-0148-1501O32 TEXHOMA PUBLIC WORKS AUTH. OK 9/11/91 0 0 0 N3HVK1-06-OO85-1500514 ST. MARY PARISH OF LA 4/ 2/91 0 0 0 N3HVK1-06-0080-1500515 TAOS NM 4/ 1/91 0 0 0 N3HVK1-06-0O84-1500516 ORANGE TX 4/ 2/91 0 0 0 N3HVK1-06-0083-1500517 ESPANOLA NM 4/ 2/91 0 0 0 N3HVK1-06-O082-1500519 PECOS MM 4/ 2/91 0 0 0 M3HVK1-06-0081-1500520 EL PASO TX 4/ 2/91 0 0 0 N3HVK1-06-OO91-1500556 OKLAHOMA CITY OK 4/11/91 0 0 0 N3HVKO-O6-O200-1500557 LAREDO TX 4/11/91 0 0 0 N3HVJO-06-014O-1500692 N3HVJO-06-O237-1500697 N3HVK1-06-0117-1500707 OKLAHOMA, STATE OK OKLAHOMA, STATE OF OK TARRANT COUNTY TX 5/21/91 5/22/91 6/ 3/91 4 0 0 0 0 0 0 0 0 N3HVKO-06-O236-15007O8 NM DEPT OF HEALTH & ENVIRONNMM 6/ 3/91 0 0 0 N3HVK1-06-0149-1501O3O NEW MEXICO HEALTH & ENVIRONMNM 9/11/91 0 0 0 N3HVK1-06-0147-1501031 OSAGE NATIONS OF OKLAHOMA OK 9/11/91 0 0 0 N3HVK1-06-0146-1501033 GALVESTON COUNTY HEALTH DEPTTX 9/11/91 0 0 0 N3I4VK1-06-O152-1501O36 POJOAQUE PUEBLO NM 9/16/91 0 0 0 N3HVJ1-06-0156-1501038 LOUISIANA STATE OF LA 9/24/91 0 0 0 TOTAL OF REGION 06 = 34 4 950 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 52 Office of the Inspector General Report to the Congress ------- Questioned Costs Audit Control Number Auditee Final Report Ineligible Unsupported Unnecessaryl Issued Costs Costs Unreasonable Costs Recommended Efficiencies (Funds Be Put To Better Use) G3HVK1-O7-0150- 1500754 G3HVK1 -07-0151-1500756 G3HVK1 -07-0156-1500760 G3HVK1 -07-0134-1500768 G3HVK1-O7- 0157-1500770 G3HVK1 -07-0168-1500814 G3HVK1 -07-0169- 1500852 G3HVJ1 -07-0172-1500925 G3HVK1 -07-0171-1500927 G3HVK1-07-0174- 1500928 G3HVK1 -07-0175-1500929 G3HVK1 -07-0181-1500961 G3HVK1 -07-0180-1500962 G3HVK1 -07-0179-1500967 N3HVK1 -07-0106- 1500511 W3HVK1 -07-0104-1500512 N3HVK1 -07-0105-1500513 M3HVJ1-O7-01 19-1500547 N3HVK1 -07-0123-1500566 H3HVKO-07-0182- 1500587 N3HVKO-07-0195- 1500589 N3HVKO-07- 0257-1500590 N3HVKO-07-0258- 1500591 N3HVJO-07-0283- 1500592 N3HVK1 -07-0124-1500593 N3HVK1 -07-0125-1500594 P43HVK1 -07-0126-1500672 N3HVK1 -07-0127-1500673 N3HVJO-07-O228- 1500700 N3HVJ1 -07-0129-1500720 N3HVK1 -07-0148-1500752 N3HVK1 -07-0149-1500755 N3HVK1 -07-0154-1500761 N3HVJ1-07-0155- 1500762 N3HVK1 -07-0152-1500763 N3HVK1 -07-0153-1500764 N3HVJ1 -07-0158-1500769 N3HVJ1 -07-0128-1500845 N3HVK1 -07-0137-1500930 W3HVJ1 -07-0176-1500931 N3HVK1 -07-0182-1500960 N3HVK1 -07-0187-1500982 ORRICK CITY OF CITY OF JACKSON CITY OF RIDGEWAY ROCK CREEK PUBLIC SEWER EMPORIA FULTON CHELSEA, CITY OF LINEVILLE DAKOTA CITY OLATHE ANNAPOLIS KEARNEY DODGE CITY LA WEREN CE COLUMBIA LIBERAL AMES IOWA DEPT. OF DOUGLAS COUNTY TOPEKA LIWN COUNTY JOHNSON COUNTY OF SEDGWICK, COUNTY OF NEBRASKA DEPT OF HEALTH LII4N COUNTY CROWDER COLLEGE OMAHA OMAHA KANSAS, STATE OF IOWA DEPT OF PUBLIC HELATH MARYVILLE R-II SCHOOL 01ST SIOUX CITY CITY OF NEOSHO IOWA DEPT OF PUBLIC HEALTH STATE OF KANSAS SEDGWICK COUNTY KNOXVILLE KIRKW000 COMMUNITY COLLEGE SUMNER IOWA, STATE OF TOPEKA JOHNSON COUNTY TOTAL OF REGION 07 = 62 G3HVK1 -08-0068-1500639 G3HVKI -08-0069-1500640 G3HVK1 -08-0070-1500641 G3HVK1 -08-0071-1500649 G3HVK1 -08-0078-1500693 G3HVK1 -08-0080-1500740 G3HVK1 -08-0028-1500831 G3HVK1 -08-0092-1500920 G3HVJ1 -08-0091 -1500921 G3HVJ1 -08-0090-1500922 G3HVK1 -08-0089-1500923 G3HVJ1 -08-0088-1500924 G3HVK1 -08-0093-1500926 G3HVK1 -08-0084-1500932 N3HVK1 -08-0066-1500604 N3HVK1 -08-0067-1500616 N3HVK1 -08-0073-1500617 N3HVJ1 -08-0074-1500627 143HUK1 -08-0075-1500642 N3HUJ1 -08-0072-1500650 W3HVK1 -08-0081-1500750 N3HVJ1 -08-0029-1500832 N3HVJO- 08-0082-1500833 W3HVKO-08-O079- 1500834 N3HVJO-08-01 11-1500835 N3HVJO-O8-O1 12-1500836 N3HVKO-O8-O 62- 1500838 N3HVK1 -08-0062-1500840 N3HVKO-O8-0054- 1500842 N3HUK1 -08-0104-1500959 N3HVK1 -08-0096-1500966 N3HVJ1 -08-0100-1500968 DIST. WY MT WY MT MT MT WY CO SD BAGGS WY COLORADO WATER & POWER ATHORCO TEN SLEEP WY LONGMONT CO EUREKA SD UTE INDIAN TRIBE UT ROSEBUD SIOUX TRIBE SD CASPER COLLEGE WY NORTH DAKOTA DEPT. OF AGRC. ND WYOMING, UNIV. RESEARCH CORPWY WEST FARGO PUB. SCH. DIS #6 ND ASSINIBOINE AND SIOUX TRIBESMT BURLINGTON TOWN OF WY CASS COUNTY ND ND DENVER REG COUNCIL OF GOVTS CO COLORADO STATE OF CO MONTANA STATE OF MT MISSOULA COUNTY MT TURTLE MT BAND CHIPPEWA ND MISSOULA COUNTY MT WY UNIV RESEARCH CORP WY PUEBLO CITY OF CO ND DEPT OF HEALTH & LABS ND ASPENS WATER & SEWER MISSOULA, CITY OF CASPER, CITY OF BEARCREEK,TOWN OF LAKESIDE COUNTY SEWER TOWN OF BEARCREEK CASPER, CITY OF METRO WASTEWATER 01ST BURKE SCHOOL DIST 26-2 MO 6/13/91 MO 6/13/91 MO 6/17/91 MO 6/18/91 KS 6/18/91 MO 71 1/91 IA 7/ 8/91 IA 7/25/91 IA 7/29/91 KS 7/29/91 MO 7/29/91 MO 8/ 7/91 KS 8/ 7/91 KS 8/12/91 MO 4/ 2/91 KS 4/ 2/91 IA 4/ 2/91 IA 4/ 9/91 NE 4/15/91 KS 4/19/91 IA 4/19/91 KS 4/19/91 KS 4/19/91 NE 4/19/91 IA 4/19/91 MO 4/19/91 NE 5/ 9/91 NE 5/ 9/91 KS 5/29/91 IA 6/ 6/91 MO 6/13/91 IA 6/13/91 MO 6/17/91 IA 6/17/91 KS 6/17/91 KS 6/17/91 IA 6/18/91 IA 7/ 2/91 MO 7/29/91 IA 7/29/91 KS 8/ 7/91 KS 8/14/91 5/ 2/91 5/ 2/91 5/ 2/91 5/ 3/91 5/21/91 6/12/91 7/ 2/91 7/25/91 7/ 25/9 1 7/25/91 7/25/91 7/25/91 7/29/91 7/29/91 4/23/91 4/29/91 4/29/91 4/29/91 5/ 2/91 5/ 3/91 6/13/91 7/ 2/91 7/ 2/91 7/ 2/91 7/ 2/91 7/ 2/91 7/ 2/91 7/ 2/91 7/ 2/91 8/ 7/91 8/12/91 8/12/91 NATURAL RESC. 0 0 0 0 0 0 0 0 0 0 0 0 0 C 0 0 0 0 0 0 0 ) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 a 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 O 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 01ST. TOTAL OF REGION 08 = 32 April 1, 1991 through September 30, 1991 53 ------- Questioned Costs Audit Control Number G3HVK1 -09-0166-1500721 G3HVJ1 -09-0179-1500793 G3HVK1 -09-0201 -1500915 N3HVK1 -09-0116-1500509 N3IIVK1 -09-0118-1500510 N3HVK1 -09-0121-1500565 N3HVK1 -09-0124-1500568 N3IIVK1 -09-0125-1500569 N3HVK1 -09-0126-1500570 N3IIVK1 -09-0127-1500571 N3HVK1 -09-0128-1500577 N3HVK1 -09-0129-1500579 N3HVK1 -09-0130-1500580 N3HVK1 -09-0131-1500581 N3HVK1 -09-0135-1500606 N3HVK1 -09-0136-1500607 N3HVK1 -09-0137-1500608 N3HVK1 -09-0140-1500618 N3HVK1 -09-0141 -1500619 N3HVK1 -09-0142-1500620 N3HVK1 -09-0143-1500625 N3HVK1 -09-0144-1500626 N3HVK1 -09-0146-1500628 N3HVK1 -09-0147-1500629 N3HVK1 -09-0151-1500680 N3HVK1 -09-0152-1500681 N3HVK1 -09-0153-1500682 N3HVK1 -09-0172-1500772 N3HVK1 -09-0173-1500773 N3HVK1 -09-0050-1500788 N3HVK1 -09-0065-1500789 N3HVK1 -09-0176-1500790 N3HVK1 -09-0177-1500791 N3HVK1 -09-0178-1500792 N3HvK1 -09-0181-1500803 N3HVK1 -09-0182-1500804 N3HVKO-09-0228- 1500813 N3HVK1 -09-0186-1500851 N3HuK1 -09-0187-1500856 N3HVK1 -09-0188-1500857 N3HVKO-09- 0280-1500860 N3HVK1 -09-0190-1500868 N3HVK1 -09-0189-1500869 N3HVKO-09-0275- 1500876 N3HVK1 -09-0049-1500877 N3HVK1 -09-0192-1500878 N3HVK1 -09-0191 -1500879 N3HVK1 -09-0194-1500881 N3HvK1 -09-0195-1500882 N3HVK1 -09-0197-1500892 N3HUK1 -09-0196-1500893 N3HVK1 -09-0198-1500894 N3HVK1 -09-0205-1500944 N3HVK1 -09-0207-1500963 N3HVK1 -09-0208-1500964 N3HVK1 -09-0213-1500970 N3HVK1 -09-0214-1500972 N3HVK1 -09-0215-1500974 N3HVK1 -09-0202-1501003 N3HVK1 -09-0221-1501005 N3HVK1 -09-0222-1501009 W3HVK1-09-0224-15O1010 N3HVK1 -09-0225-1501011 N3HVK1 -09-0234-1501041 N3HVK1 -09-0235-1501042 N3HVK1 -09-0236-1501043 CARSON CITY MONTESANO, CITY OF MAUI, COUNTY OF FERNDALE, CITY OF WASHO€ COUNTY NEVADA MONTEREY REGNL WATER AMADOR, COUNTY OF SHASTA COUNTY OF EAST BAY MIJNI UTIL 01ST SONOMA, COUNTY OF FRESNO, CITY OF LIVE OAK, CITY OF STANISLAUS, COUNTY OF TULARE, COUNTY OF MANTECA, CITY OF MERCED, COUNTY OF NV 6/ 6/91 WA 6/26/91 HI 7/24/91 CA 4/ 1/91 NV 4/ 1/91 POLL CTCA 4/12/91 CA 4/15/91 CA 4/15/91 CA 4/15/91 CA 4/15/91 CA 4/17/91 CA 4/17/91 CA 4/17/91 CA 4/17/91 CA 4/23/91 CA 4/23/91 4/23/91 CA 4/29/91 CA 4/29/91 CA 4/29/91 CA 4/29/91 CA 4/29/91 CA 4/29/91 CA 4/29/91 CA 5/15/91 CA 5/15/91 CA 5/15/91 CA 6/21/91 CA 6/21/91 CA 6/26/91 CA 6/26/91 FEDERATED STATES MICRONESIA FM WOODLAND, CITY OF GRASS VALLEY, CITY OF SAN JOAQUIN, COUNTY OF LOS ANGELES CTY. SAN. DIS SOUTH COAST AIR QUAL. MGMT. SAN DIEGO ASSN. OF GOVT. TRACY, CITY OF PETALUMA, CITY OF SANTA BARBARA, COUNTY OF VALLEJO SAN AND FLOOD CTRL KINGS, COUNTY OF SAN JUAN BAUTISTA, CITY OF FORT MOJAVE INDIAN TRIBE ASSOCIATION OF BAY AREA GVT 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Recommended Efficiencies (Funds Be Put To Better Use) TOTAL OF REGION 09 = 66 G3HVKO- 10-0029-1500518 G3HVK1 - 10-0052-1500564 G3HVK1 - 10-0054-1500638 G3HVK1 - 10-0057-1500683 G3HVK1 - 10-0067-1500943 G3HVK1 -10-0068-1500973 G3HVK1 - 10-0074-1501012 N3HVKO- 10-0040-1500774 N3HVJ1-10-0O11-1500809 FAIRBANKS NORTH STAR BOB. AK COEUR D’ALENE, CITY OF ID NEWBERG, CITY OF OR TROY, CITY OF ID METRO WASTEWATER MONT COMM OR HOMER, CITY OF AK SPRINGFIELD, CITY OF OR ANCHORAGE, MUNICIPALITY OF AK CHEHALIS, CITY OF WA 4/ 2/91 4/11/91 5/ 2/91 5/15/91 8/ 2/91 8/13/91 8/29/91 6/21/91 6/28/91 356,565 0 Audit.. Final Report Ineligible Unsupported Unnecessary/ Issued Costs Costs Unreasonable Costs 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 D 0 0 0 D 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 355,763 0 0 0 0 802 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 CA 6/26/91 CA 6/26/91 CA 6/26/91 CA 6/27/91 CA 6/27/91 CA 6/28/91 CA 7/ 8/91 CA 7/ 9/91 CA 7/ 9/91 CA 7/ 9/91 CA 7/11/91 CA 7/11/91 MODESTO, CITY OF SANTA MONICA, CITY OF SANTA CRUZ, CITY OF ORANGE COUNTY OF SAN MATEO, COUNTY OF INDIO, CITY OF LA DEPT. OF WATER & POWER UNIV OF CALIFORNIA SF FRESNO, COUNTY OF LOS ANGELES, CITY OF CORNING, CITY OF BOLINAS COMMUNITY P.U.D. CLARK COUNTY HEALTH DISTRICTNV GILA RIVER INDIAN COMMUNITY AZ SOUTH TAHOE PUD CA ASSN OF MONTEREY BAY AREA CA RURAL COMMUNITY ASSIST CORP CA WASHOE COUNTY NV BOULDER CITY, CITY DF NV PIMA COUNTY COMM COLLEGE DI AZ YAP STATE GOVERNMENTS FM EASTERN MUM. WATER DISTRICT CA SAN DIEGO, COUNTY OF CA SAN FRANCISCO, CITY & COUNTYCA WEOTT COMMUNITY SVCS. 0 1ST. CA POHNPEI, STATE OF FM CLARK COUNTY HEALTH DISTRICTNV L.A. DEPT OF WATER & POWER CA SAN DIEGO, CITY OF CA PLACER, COUNTY OF CA GERBER-LAS FLORES CON SVCS CA BAY AREA AIR QTY MONT 01ST CA INTERTRIBAL COUNCIL OF AZ AZ WHITE MOUNTAIN APACHE TRIBE AZ SAN JOAQUIN VLYWIDE AIR POLLCA 7/11/91 7/11/9 1 7/11/9 1 7/11/9 1 7/12/9 1 7/12/91 7/17/9 1 7/17/91 7/17/91 8/ 2/91 8/ 7/91 8/ 7/91 8/12/91 8/13/91 8/13/91 8/27/91 8/27/91 8/29/91 8/29/91 8/29/91 9/27/91 9/27/9 1 9/27/91 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 54 Office of the Inspector General Report to the Congress ------- Questioned Costs Audit Control Number N3HVK1 - 10-0027-1500810 N3HVJ1 -10-0008-1500811 N3HVKO- 10-0074-1500812 N3HVK1 -10-0065-1500858 N3HvK1 - 10-0066-1500859 N3HVJ I - 10-0003-1500870 N3HVJ1-10-0071-1501004 N3HVK1 - 10-0082-1501044 EUGENE, CITY OF CAMAS, CITY OF MULTNOMAH COUNTY ANCHORAGE, MUNICIPALITY OF POCATELLO, CITY OF LYNNW000, CITY OF SPOKANE COUNTY SHOSHONE-BANWOCK TRIBES TOTAL OF REGION 10 = 17 TOTAL OTHER GRANT AUDITS 5. SUPERFUND GRANTS E5FGL1-O1-O083-1100313 RI COOP. REVIEW RI E5FGL1-O1-O114-110043O NEW HAMPSHIRE COOP AGREEMENTNH P5BGLO-O1-O155-1100383 MADEP-PSC RESOURCES MA P5BGLO-O1-0154-1100384 MADEP-I4ULTISITE COOP MGMNT MA TOTAL OF REGION 01 = 4 P5BGLO-02-O196-1100423 NYS LOVE CANAL REMEDIAL PROJNY TOTAL OF REGION 02 = 1 E5CGL1-04-O055-1100175 SF DAVIE LANDFILL E5BFN1-O4-O224-1300113 SUPERFUND COOP AGREEMENTS TOTAL OF REGION 04 = 2 = 536 7/11/91 9/30/91 9/13/91 9/16/91 4,705,749 1,277,884 13,017 162,842 9/27/91 1,389 921,394 1,389 921,394 4/10/91 304,323 9/26/ 91 304,323 0 0 P5GFNO-O6-O116-1300069 LA DEPT OF ENV QUALITY P5BFNO-O6-021O-130008O TX WATER COMMISSION LA 5/20/91 524 TX 6/19/91 3,022,423 O 0 O 0 TOTAL OF REGION 06 = 2 3,022,947 0 0 H5BFL1- .1-0034-1100393 I I5BFL1-11-O037-1 100429 M5BFL1 -11-0032-1100387 M5BFL1-11-0O33-1100392 M5BFL1-11-0038-1100427 M5BFL1-11-0O18-1100438 FY87-89 HHS ATSDR DC FY87-89 HHS NAT INST OF HLTH FY89 001-OF OF SECRETARY FEMA AD.PERM/TEMP RELOC. DC FY 89 IRS REIN. SF COSTS DC SF IAG-DOJ FY 89 9/16/91 9/30/91 9/16/91 9/16/91 9/30/91 9/30/91 TOTAL OF REGION 11 = 6 TOTAL SUPERFLJND GRANTS 8. OTHER CONTRACT AUDITS = 16 3,472,439 3,571,480 0 D8AML1-01-O110-1100162 D8CML1-O1-0125-1100179 DBAML1-O1-O162-1100232 D8CML1-O1-O165-1100233 D8AML1-O1-O169-1100238 D8AML1-O1-O17O-1100239 DBAML1 -01-0168-1100243 D8AML1 -01-0207-1100326 D8AML1 -01-0208-1100327 D8AML1-O1-0210-1100337 D8AML1 -01-0209-1100338 INDUSTRIAL ECONOMICS INC. CAMP DRESSER AND MCGEE EASTERN RESEARCH GROUP MITRE CORPORATION ANEPTEK CORP ABB ENVIRON. SERV. ERC FIELD SERVICES CORP SYNETICS CORP EASTERN RESEARCH GROUP CADMUS GROUP METCALF & EDDY INC. MA 4/ 3/91 MA 4/18/91 MA 5/30/91 MA 5/30/91 MA 5/31/91 ME 5/31/91 MA 6/ 5/91 MA 7/23/91 MA 7/23/91 8/ 6/91 8/ 6/91 *The dollar value of contract audits have not been shown. Public disclosure of the dollar value of financial recom- rnendations could prematureLy reveal the Goverrsnent’s negotiating positions or release of this information is not routinely avaiLable under the Freedom of Information Act. The nuTl er of these reports and dollar value of the findings have been included in the aggregate data displayed below. Such data individualLy excluded in this listing will be provided to the Congress. The transmitted data will contain appropriate cautions regarding disclosure. TOTAL OF REGION 01 = 11 D8AML1-02-O136-1100335 D8AAL1 -02-0139-1100341 DBBML1 -02-0148-1100369 P8AXL1-O2-0133-1100432 ECOLSCIENCES INC MATHTECH INC LEONARD G. BIRNBAUM ECOLOGY & ENVIRONMENT NJ 7/29/91 NJ 8/ 8/91 NJ 9/ 3/91 NY 9/30/91 TOTAL OF REGION 02 = 4 D8AML1-03-O161-1100163 D8AML1-O3-O162-1 100164 D B OML1-O3-0163-1100165 D8AML1-03-O164-1100167 DEOML1 -03-0165-1100171 GANNETT FLEMING INC TECHNICAL RESOURCES INC ROY F. WESTON DYNAMAC CORPORTAT ION UNISYS CORPORATION PA 4/ 4/91 MD 4/ 4/91 PA 4/ 4/91 MD 4/ 4/91 VA 4/ 9/91 Auditee Final Report Issued Ineligible Costs Unsupported Costs Unnecessary/ Unreasonable Costs Recommended Efficiencies (Funds Be Put To Better Use) OR 6/28/91 0 0 0 WA 6/28/91 0 0 0 OR 6/28/91 0 0 0 AK 7/9/91 0 0 0 ID 7/9/91 0 0 0 WA 7/11/91 0 0 0 WA 8/27/91 0 0 0 ID 9/27/91 0 0 0 0 13,017 162,842 0 FL SC 0 0 0 0 0 0 0 0 P5CGNO-1O-OO11-1300066 WASHINGTON DEPT OF ECOLOGY WA 5/ 7/91 130,763 2,487,244 0 TOTAL OF REGION 10 = 1 130,763 2.487,244 0 Apri 1, 1991 through September 30, 1991 55 ------- Questioned Costs Audit Control Number Auditee Final Report Ineligible Unsupported Unnecessaryl Issued Costs Costs Unreasonable Costs Recommended Efficiencies (Funds Be Put To Better Use) D8AML 1- 03-0166- 1100172 D8EML1 -03-0167-1100173 D8AML1-03- 0168-110 0174 D8AML1 -03-0203-1100182 D8AML1 -03-0202-1100183 DBAML1-03-0201-1100184 D8AML1 -03-0200-1100185 D8AML1 -03-0199-1100186 D8AI4L1 -03-0198-1100187 D8AML1 -03-0197-1100188 D8A 14L1-03-0196-1100189 D8AML1-03-0195-1100190 D8AML1-03-O194-1100191 D8AIIL1 -03-0193-1100192 DBAML1 -03-0192-1100193 D8AML1-03-0191-1100195 D8AML1 -03-0209-1100196 D8AML1 -03-0208-1100197 D8AML1 -03-0207-1100198 D8AML1 -03-0206-1100199 D8AML1 -03-0205-1100203 D8AML1-03-02041 100204 D8EML1 -03-0210-1100205 D8AML1-03-02t1-11002O6 08*1411-03-0212-1100207 D8AML1-03-0213-11002 09 D8AML1 -03-0214-1100210 D8A14L1 -03-0215-1100211 D8AML1-03-0216-1100212 D8AML1-03-0217-1100213 D8AML1-03-0218-1100215 D8ANL1 -03-0219-1100216 D8EML1 -03-0220-1100217 D8AI4L1-O3-0221- 1100218 D8DML1 -03-0222-1100219 D8AML1 -03-0223-1100220 DM1411 -03-0245-1100260 D8CML1 -03-0248-1100261 D8CI4L1 -03-0250-1100262 D8AML1 -03-0255-1100263 D8EML1 -03-0261-1100264 D8AI4L1 -03-0266-1100265 D8AML1 -03-0265-1100266 D8AML1-03-0251-1100267 D8AML1 -03-0243-1100268 08*1411-03-0263-1100269 08*1411-03-0267-1100287 D8AML1-03-0268-1100288 DBAML1 -03-0269-1100289 D8AIIL1-03-0272-1100290 DM1411 -03-0273-1100291 D8A14L1 -03-0264-1100296 D8AML1-03-0262-110 0297 D8CML1 -03-0260-1100298 08*1411-03-0291- 1100299 08*1411 -03-0287-1100300 DM1411 -03-0288-1100301 D8AML1 -03-0289-1100302 D8AIIL1 -03-0290-1100303 D8AML1 -03-0286-1100305 D8OML1 -03-0259-1100306 D8CML 1-03-0258-1100307 DM1411 -03-0274-1100308 DM1411 -03-0270-1100309 D8DMLI -03-0257-1100316 0801411-03-0256-1100317 D881411 -03-0246-1100318 08*1411-03-0247-1100319 D8AI4LI -03-0244- 1100320 DM1111 -03-0254-1100321 D&ML1 -03-0249-1100322 DM1411 -03-0285-1100323 08*1411 -03-0284-1100324 D8A14L1 -03-0283-1100325 D804L1 -03-0301-1100331 D8DML1 -03-0331-1100355 DM1411 -03-0330-1100356 D8EML1 -03-0332-1100357 SCIENCE POLICY ASSOCIATES SCIENCE POLICY ASSOCIATES RI I VIAR & COMPANY SRA TECHNOLOGIES INC GENERAL SCIENCES CORP WORLD WILDLIFE FUND VIAR & COMPANY MARASCO NEWTON GROUP JACA CORPORATOW SOFTWARE AG FEDERAL JAMES MARTIN GOVERNMENT CON GREENHORNE & O’MARA INC VIGYAN INC SOLUTIONS BY DESIGN INC TECHNOLOGY APPLICATION INC WALCOFF & ASSOCIATES ICF INC LABAT ANDERSON INC ROY F. WESTON UNISYS CORPORATION COMPUTER SCIENCES CORP. ANALYSIS CORPORATION ANALYSAS CORPORATION C.C. JOHNSON & MALHOTRA C C. JOHNSON & MALNOTRA RESOURCE APPLICATIONS INC SYCOM INC PRC INC INFORMATION MANAGE ROW SCIENCES INC 8DM INTERNATIONAL INC AEPCO INC CSC APPLIED TECHNOLOGY DIV HEALTH SYSTEMS MRKT & 0EV UNI SYS CORPORATION 8DM INTERNATIONAL RESOURCE APPLICATIONS INC MAR INC DYNAMAC CORPORATION NYMA INC BOOZ ALLEN & HAMILTON INC NMI SYSTEMS INC RAY COMMUNICATIONS PACIFIC ENVIRONMENTAL SERV ASCI CORPORATION T. HEAD AND COMPANY ZONE 2 NMI SYSTEMS INC PRC INC CENTEL FEDERAL SYSTEMS INC GENERAL SCIENCES CORP (GSC) CONTEL FEDERAL SYSTEMS INC COMPUTER DATA SYSTEMS INC MD T.HEAD AND COMPANY ZONE 1 VA DYNAMAC CORPORAT ION IRIS CORP M D GANNET FLEMING INC PA JACK FAUCETT ASSOC INC MD JACK FAUCETT ASSOC INC MD SOBOTKA AND CO INC DC SYSTEMS RESEARCH & APPLICA VA PENNSYLVANIA STATE UNIVERS PA ROY F. WESTON INC PA ELECTRONIC DATA SYSTEMS CORPVA I-NET INC MD VIAR AND COMPANY VA RAVEN SERVICES CORPORATION VA NUS CORPORATION MD S. COHEN VA ROY F. WESTON INC PA UNISYS GOVERNMENT SYSTEMS VA WORLD WILDLIFE FUND DC COMPUTER BASED SYSTEMS INC VA DYNAMAC CORPORATION MD DYNAMAC CORPORATION MD ARC PROFESSIONAL SERVICES GRMD DYNCORP/PRI PROGRAM RESOJRCEMD VIAR AND COMPANY VA CDM- FEDERAL PROGRAMS 14* DC 4/ 9/91 DC 4/ 9/91 MD 4/ 9/91 VA 4/24/91 VA 4/24/91 MD 4/24/91 DC 4/24/91 VA 4/24/91 VA 4/24/91 PA 4/24/91 VA 4/29/91 VA 4/29/91 MD 4/29/91 VA 4/29/91 VA 4/29/91 VA 5/ 1/91 VA 5/ 1/91 VA 5/ 1/91 VA 5/ 1/91 PA 5/ 1/91 VA 5/ 2/91 VA 5/ 2/91 DC 5/ 2/91 DC 5/ 2/91 MD 5/ 2/91 MD 5/ 7/91 VA 5/ 7/91 VA 5/ 7/91 VA 5/ 7/91 MD 5/ 7/91 VA 5/ 8/91 MD 5/ 8/91 VA 5/ 8/91 DC 5/ 8/91 VA 5/ 8/91 VA 5/ 8/91 VA 6/25/91 MD 6/25/91 MD 6/25/91 MD 6/25/91 MD 6/25/91 VA 6/26/91 PA 6/26/91 VA 6/26/91 VA 6/26/91 6/26/91 7/ 3/91 7/ 3/91 7/ 3/91 7/ 3/91 7/ 3/91 7/ 3/91 7/ 3/91 7/ 3/91 7/ 8/91 7/ 8/91 7/ 8/91 7/ 8/91 7/ 8/91 7/ 9/91 7/10/91 7/10/91 7/10/91 7/10/91 7/19/91 7/19/91 7/19/91 7/19/91 7/19/91 7/22/91 7/22/91 7/22/91 7/22/91 7/22/91 7/25/91 8/15/91 8/15/91 8/15/91 VA VA VA VA MD VA 56 Office of the Inspector General Report to the Congress ------- Questioned Costs Audit Control Number Auditee Final Report Ineligible Unsupported Issued Costs Costs Recommended Unnecessary/ Efficiencies Unreasonable (Funds Be Put Costs To Better Use) DBBML1 -03-0353-1100386 D8AML1-03-0352-1 100388 D8AML1-03-0351-1100389 D8EML1 -03-0345- 1100390 DSEML1 -03-0341-1100391 DB OML1-03-0344-1100395 DSCML1 -03-0346-1100396 DBBNL 1-03-0349-1100397 D8AIIL1 -03-0354-1100398 D8DML1 -03-0359-1100399 DBOML 1-03-0360-1100400 D8AML1 -03-0363-1100401 DBAML1 -03-0364-1100402 D8AML1 -03-0365-1100403 DBAML1 -03-0366-1100404 D8BML1 -03-0342-1100405 DSAML1-03-0371-1100406 D8AML1 -03-0370-1100407 D8AML1 -03-0369-1100408 DBAML1 -03-0367-1100409 D8EML1 -03-0362-1100412 DBEML1 -03-0361-1100413 D8EML1-03-O348- 1100414 D8AML1 -03-0350-1100416 D8AML1 -03-0368-1100417 P8BMN1-03-0125-1300100 SRA TECHNOLOGIES VA COMPUTER BASED SYSTEMS VA JUK INTERNATIONAL VA COMPUTER SCIENCES CORPORAT VA COMPUTER SCIENCES CORP VA UNISYS GOVERNMENT SYSTEM VA ARC PROFESSIONAL SERVICES GRMD UNISYS DEFENSE SYSTEMS DIVERSIFIED TECHNOLOGY COMPUTER SCIENCE CORP COMPUTER SCIENCE CORP WESTAT INC INFORMATION SYS & NETWORK VERSAR KEYDATA SYSTEMS INC CONSOLIDATION COAL DYNAMAC CORPORATION ETS INTERNATIONAL JACK FAUCETT ASSOCIATES COMSIS CORPORATION COMPUTER SCIENCE CORP COMPUTER SCIENCE CSC APPLIED TECHNOLOGY DIV NMI SYSTEMS INC RI! 0 & R MANAGEMENT CORP 9/16/91 9/16/91 9/16/91 9/16/91 9/16/91 9/17/91 9/17/91 VA 9/17/91 VA 9/17/91 VA 9/17/91 VA 9/18/91 MD 9/18/91 M D 9/18/91 VA 9/18/91 MD 9/18/91 PA 9/20/91 MD 9/20/91 VA 9/20/91 MD 9/20/91 MD 9/20/91 VA 9/24/91 VA 9/24/91 VA 9/24/91 VA 9/24/91 MD 9/24/91 MD 8/23/91 TOTAL OF REGION 03 109 D8CML1 -04-0289-1100200 D8AML1 -04-0288-1100201 D8ANL 1-04-0387-1100244 D8AML1 -04-0354-1100245 D8AML1 -04-0352-1100246 D8AML1 -04-0386-1100248 D8AML1 -04-0355-1100249 DBAML1 -04-0353-1100250 DBAML1 -04-0402-1100257 DBAML1 -04-0444-1100310 DBCML1-O4-O442- 1100311 DBAML1-O4-O443-1100312 D8DML1 -04-0487-1100336 DSAML1-04-O51 1-1100351 D8CML1 -04-0513-1100352 D8AML1-04-O512-1100353 D8AML1 -04-0519-1100354 DBAMLO- 04-0403-1100358 D8AML1 -04-0526-1100363 D8AML1 -04-0525-1100364 D8BML1 -04-0524-1100365 DBDML1-04-0541 -1100377 D8EML1-O4-O549-1100418 HBAML1 -04-0385-1100247 H8AML1 -04-0508-1100350 H8AML1 -04-0527-1100366 H8AAL1-O4-0542- 1100376 P8ABN1-O4-O483-1300111 BUILDING SVCS UNLIMITED ENTROPY ENVIRONMENTALISTS EC/R INC EDWARD AUL & ASSOC, INC. EDWARD AUL & ASSOC., INC. RESEARCH & EVAL ASOC ENVIRONMENTAL INVESTIGATION NC EC/R INCORPORATED NC RESEARCH & EVALUATION ASSOC NC INTEGRITY PRIVATE SECURITY TN MANTECH ENVIRONMENTAL NC S JTHERN RESEARCH INST ITUT AL MANTECH ENVIRONMENTAL TECH NC RESEARCH & EVALUATION ASSOC NC CONTINENTAL SHELF ASSOCIATESFL RESEARCH & EVALUATION ASSOC NC ZEDEK CORPORATION NC KBN ENGINEERING & APPLIED SCFL TRANSCONT I NENTAL ENTERPR I SESNC RESEARCH & EVALUATION ASSOC NC CONTINENTAL SHELF ASSOC FL MANTECH ENVIRONMENTAL TECH NC ADVANCED SYSTEMS TECHNOLOGY GA RESEARCH TRIANGLE INST NC RESEARCH TRIANGLE INSTITUTE NC UNIVERSITY OF NC AT CHAPEL NC RESEARCH TRIANGLE INSTITUTE NC EHRT-LEXINGTON KY FL 5/ 1/91 NC 5/ 1/91 NC 6/ 5/91 NC 6/ 5/91 NC 6/ 5/91 NC 6/ 5/91 6/ 5/91 6/ 5/91 6/18/91 7/10/91 7/10/91 7/10/91 8/ 2/91 8/14/91 8/14/ 91 8/14/91 8/15/91 8/15/91 8/29/91 8/29/91 8/29/91 9/11/91 9/25/91 6/ 5/91 8/13/9 1 8/29/91 9/11/91 9/23/91 TOTAL OF REGION 04 28 D8DML1 -05-0235-1100169 DBOML1-O5-O236-110017O D8AML1-05-031O-1100254 D8CML1 -05-0309-1100255 D8CML1 -05-0308-1100256 D8AML1 -05-0368-1100328 D8CML1 -05-0369-1100329 DBCML1 -05-0377-1100330 D8DML1-O5-0388-1 100332 D8GML1 -05-0389-1100333 D8GML1-05-0382-1100334 D8CML1-O5-0414-1 100347 DBGML1-05-O424-1100348 D8GML1-05-O425-1100349 D8AML1- 05-0445-1100379 DBAML1-05-O439-1 100380 E8AXN1 -05-0279-1300072 P8AAP1 -05-0280-1400027 AUTO TESTING LAB FY 89 AUTO TESTING LAB FY 89 ANDERSEN CONSULTING CHEMICAL ABSTRACTS SERVICE BATTELLE EXPERIENCE INC BATTELLE BATTELLE AUTO TESTING LAB BATTELLE VECTOR RESEARCH INC BATTELLE BATTELLE BATTELLE LIFE SYSTEMS INC COLEJON MECH PRC EM! EOM (AIR) OH 4/ 5/91 OH 4/ 5/91 IL 6/12/91 OH 6/12/91 OH 6/12/91 MN 7/18/91 OH 7/18/91 OH 7/20/91 OH 7/25/91 OH 7/25/91 MI 7/25/91 OH 8/ 9/91 OH 8/12/91 OH 8/12/91 OH 9/12/91 OH 9/12/91 IL 6/ 3/91 OH 8/ 2/91 ApnI 1. 1991 through September 30, 1991 57 ------- Au C=. I Numbsr Qu on.d Coets Final Rsport Inaligible Unsupported su ed Coets Cost Unnec e c*sry/ Unrs.sonable Coets Recommended (Funds B. Put To Better U..) P8AAP1-05-0295-1400029 EON P8AXP1-05-0354-1400033 OHM REM INTERIOR TOTAL OF REGION 05 = 20 OH 8/13/91 OH 9/ 5/91 D8AML1 -06-0096-1100180 D8&AL1 -06-0097- 1100181 D8AHL1 -06-0099-1100194 D8AML1-06-0107-1100214 D8AML1-06-011O-1100224 D8ANL1-06-0111-1100225 D8AML1-06-0112-1100226 D8AAL1-06-0114-1100227 D8AAL1-06-0115-1100231 D8AAL1-06-0118-1100242 DSCAL1 -06-0129-1100292 D8CAL1 -06-0130- 1100293 D8CAL1 -06-0131-1100294 D8CAL1 -06-0132- 1100295 D8CML1 -06-0143-1100362 D8BML1 -06-0150-1100381 D8BML1-06-0151-1100382 D8BML1-06-0153- 1100394 SOUTHWEST RESEARCH IMSTITUTETX RADIAN CORPORATION TX GEO-MARINE INCORPORATED TX INTERA INC. TX SOUTHWEST RESEARCH INST ITUTETX ENTERPRISE ADVISORY SERVICESTX ETC ENGINEERS INC. AR EG&G AUTOMOTIVE RESEARCH TX SOUTHWEST RESEARCH INSTITUTETX RADIAN CORPORATION TX EG&G AUTOMOTIVE RESEARCH INCTX EG&G AUTOMOTIVE RESEARCH TX EG&G AUTOMOTIVE RESEARCH TX EG&G AUTOMOTIVE RESEARCH INCTX RADIAN CORPORATION TX RADIAN CORPORATION TX RADIAN CORPORATION TX RADIAN CORPORATION TX 4/18/91 4/18/91 4/30/91 5/ 7/91 5/20/91 5/20/91 5/20/9 1 5/21/91 5/29/91 6/ 4/91 7/ 3/91 7/ 3/91 7/ 3/91 7/ 3/91 8/29/91 9/13/91 9/13/91 9/16/91 TOTAL OF REGION 06 = 18 D8AML1-O7-0161-1100284 D8DML1 -07-0163-1100285 D8ABL1-O7-O164-1100286 D8FWL1-O7-0185-1100340 D8ABN1 -07-0160-1300081 D8ABN1 -07-0159-1300082 DBABN1 -07-0162-1300083 D8ABN1-07-O173- 1300088 D8ABN1-07-0177- 1300089 D8DMN1 -07-0184-1300095 D8ABN1 -07-0186-1300096 D8ABN1-07-O178- 1300097 MRI MO DEVELOP PLAN & RESEARCH ASOCKS WILSON LABS KS SVERDUP & CORP MO MRI MO MRI MO PSI/HALL KIMBRELL MO DEVELOP PLANNING & RESEARCH KS UNIVERSITY OF IOWA HYGIENIC IA BLACK & VEATCH MO MRI MO MRI MO 7/ 2/91 7/ 2/91 7/ 2/91 8/ 7/91 7/ 2/91 7/ 2/91 7/ 2/91 7/25/91 7/29/91 8/ 7/91 8/ 7/91 8/12/91 TOTAL OF REGION 07 = 12 D8AMW1-O8-0O77-1300070 NFT INC., GOLDEN TOTAL OF REGION 08 = 1 Co 5/21/91 D8DML1-09-0117- 1100160 D8DML1 -09-0138- 1100222 D8CML1 -09-0139-1100223 DBAAL 1-09-0158-1100235 D8CML1- 09-O16O-1100236 D8CML1 -09-0161-1100237 D8CAL1 -09-0162-1100240 D8CAL1 -09-0163-1100241 D8OML1-09-O164-1100251 D8DML I-09-0165-1100252 D8ANL1 -09-0170-1100258 D BAML1-09-O180-1100272 D8ANL1-O9-O183-1100273 D8BML1 -09-0193-1100314 DBAI4L1- 09-0206-1100342 D8CML1-09-021O-1100343 D8CML1 -09-0211-1100344 D8AML1-09-02 09-1100345 D8AI4L1-09-O212-1100346 D8BML1 -09-0220-1100361 D8DML1 -09-0227-1100368 D8AML1 -09-0230-1100372 D8AML1-09-0229-1100373 D8AML1-09-0231-1100375 D8CAL1-09-O233-110041O DBAML1-O9 U237-1100435 D8AML1-09-0238-1 100437 D8CML1-09-0240-1 100440 D8CML1-09-0241-1100442 D8CML1 -09-0242-1100443 D8AMN1 -09-0145-1300068 D8DMN1 -09-0159-1300071 DBAI4N1 -09-0169-1300077 GEO/RESOURCES CONSULTANTS CA ROCKWELL/ROCKETDYNE, CANOGA CA AEROSPACE CORP., EL SEGUNDO CA ENERGY ENVIR RESEARCH CORP CA SCIENCE APPLICATIONS INTL CA ACUREX CORP CA ENERGY & ENVIRN. RES. CORP CA ACUREX CORP ENGINEERING SCIENCE, INC CA ENGINEERING SCIENCE,INC CA GENERAL ATOMICS CA URIBE & ASSOCIATES CA STERLING FEDERAL SYSTEMS CA IT CORP CA S-CUBED CA ACRUEX CORP CA ACUREX CORP CA SIERRA TECH SERVICES INC CA SIERRA TECH SERVICES INC CA IT CORP CA ENGINEERING-SCIENCE, INC. CA SCIENCE APPLICATIONS INTL CA LEE ASSOCIATES CA STEINHOFF AND SADLER, INC CA ENERGY & ENVIR. RES. CORP. CA VISTA RESEARCH, INC CA IT CORP CA ACUREX CORPORATION CA ACUREX CORP CA ENERGY & ENVIRON REAEARCH JACOBS ENG GRP. PASADENA CA SCS ENGINEERS GENERAL ATOMICS CA 4/ 1/91 5/16/91 5/16/91 5/30/91 5/30/9 1 5/30/91 5/31/91 5/31/91 6/ 6/91 6/ 6/91 6/19/ 91 6/27/91 6/27/91 7/12/91 8/ 8/91 8/ 8/91 8/ 8/91 8/ 8/91 8/ 8/91 8/26/91 8/29/91 9/ 6/91 9/ 6/91 9/ 9/91 9/20/91 9/30/91 9/30/91 9/30/91 9/30/91 9/30/91 5/16/9 1 5/30/91 6/19/91 TOTAL OF REGION 09 = 33 58 Office of the Inspector General Report to the Congress ------- Questioned Costs Audit Control Number D8AAL1 -10-0078-1100371 D8AMN1 -10-0079-1300103 P8AXL1-10-0034-1100168 P8AXL1 -10-0037- 1100202 PBAXL1-10-0050-1100315 P8AXN1 -10-0036-1300098 OMNI ENVIRONMENTAL SERVICES OR 0MW! ENVIRONMENTAL SERVICES OR RES-ROCKY FLATS DOE PREAWARDOR CH2M HILL DOE/MTN MAR PREAW OR CH2M HILL DOE RFP 9xS1-Q42570R RES NAVY PRE-AWARD 9/ 6/91 9/ 6/91 4/ 4/91 5/ 1/91 7/18/91 8/13/91 TOTAL OF REGION 10 = 6 TOTAL OTHER CONTRACT AUDITS 9. SUPERFUND CONTRACTS P9AHL1-O2-O11O-110037O S&D ENGINEERING SERVICES NJ TOTAL OF E9BGP1 -03-0333-1400055 P9AKN1 -03-0327-1300094 P9BHNO- 03-0382-1300101 P9AKW1 -03-0355-1300106 P9AKN1 -03-0356-1300107 P9DXN1-03-O387-1300114 TOTAL OF D9AHL1 -04-0309-1100208 P9BHNI -04-0317-1300110 REGION 02 = 1 CDM FEDERAL PROGRAMS CORP CLEMENT INTERNATIONAL INC GUARDIAN ENVIRONMENTAL SVC CLEMENT INTERNATIONAL ICF INC ICF INFORMATION TECHNOLOGY REGION 03 = 6 GEOPHEX LTD. ENVIRONMENTAL HEALTH TOTAL OF REGION 04 = 2 E9AKN 1-05-0206-1300063 E9FFP1 -05-0442-1400056 P9DGLO-O5-O265-1100166 P9AHt41 -05-0191-1300085 P9DHPO-O5-O378- 1400030 P9BHPO-05-0292- 1400031 P9BHPO-05-0293- 1400032 P9AHP1 -05-0281-1400034 P9AHP1 -05-0313-1400035 P9AHP1 -05-0313-1400036 P9DHP1 -05-0285-1400040 P9AHP1 -05-0297-1400044 P9AHP1 -05-0296-1400045 P9FGP1-O5-0411-1400052 PRC EMI ENG FMR tM ENG FY 89 OHM REM ERCS3 Ri OHM REM FY 89 OHM REM ERCS2 Z1 FY 89 OHM REM ERCS2 Z2 FY 89 OHM REM ERCS3 R5 OHM REM ERCS3 R2 OHM REM ERCS3 R2 OHM REM FCOM Fl 89 MAECORP ERCS3 R5 MAECORP ERCS3 R5 DONOHUE ARCS R5 FMR TOTAL OF REGION 05 = 14 D9AKL1-O6-O124-1100279 LOCKHEED ENGINEERING & SCIENTX TOTAL OF REGION 06 = 1 URIBE & ASSOC D9AHL1-O8-0O83-1100282 D9AKL1 -08-0082-1100283 GREYSTOWE ENVIRONMENTAL SERVCO TOTAL OF REGION 08 = 2 P9EGL1-10-0040-1100367 CH2M HILL CAS DIS ADEQUACY OR = 242 1,002,451 9/ 6/91 NC 5/ 3/91 KY 9/23/91 IL 5/ 1/91 MI 9/27/91 MI 4/ 4/91 OH 7/ 9/91 OH 8/19/91 OH 8/19/91 OH 8/19/91 OH 9/ 6/91 OH 9/ 6/91 OH 9/ 6/91 OH 9/11/91 IL 9/20/91 IL 9/23/91 WI 9/26/91 7/ 1/91 CO 7/ 2/91 7/ 2/91 8/29/91 425,122 203,689,419 HDQ 771 - - REPORTS ISSUED BY TYPE AUDIT AND REGION SEMI-ANNUAL PERIOD ENDING 9/30/91 Audltss Final Report Issued Inoligibi. Costs Unsupported Costs Unnecsss .ry/ Unrssson.bl. Costs Rscommond.d Efficiencies (Funds 8. Put To Better Us.) OR VA VA DE VA VA VA 9/27/ 91 8/ 7/91 8/29/91 9/13/91 9/16/91 9/26/91 228,506 0 0 0 0 1,080,621 1,268,752 0 166,284,436 85,492,010 23,900,549 137,086,229 381,323,688 TOTAL OF REGION 10 = TOTAL SUPERFUND CONTRACTS TOTAL AUDITS = 942 = 27 AprU 1 1 991 through September 30, 1 991 59 ------- Appendix—2 Audits Without Management Decision D8AML1-04-0030-1100011 RESEARCH & EVALUATION ASSOC NC 10/12/90 Summay CONTRACTOR WiLL NOT INCUR MAJORI1Y OF OPTION PERIOD ONE COSTS PROPOSED. • EXPlANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: PROBLEMS HAVE BEEN ENCOUNTERED IN REDUC11ON OF SCOPE OF WORK IN ORDER TO DECREASE THE COST OF PERFORMANCE. - DES IRED TiMETABLE FOR ACHIEViNG A MANAGEMENT DECISION: RESOLUTION IS EXPECTED BY 11J3C 91. 16 FOLLOWUP STATUS AS OF 9/30/91: [ 1J PROCUREMENTS CONTRACTS MANAGEMENT DIViSION Financial Analysis Section P9AHN9-05-0347 .0300036 OH MATERIALS (PR EQ RATES) OH 3/27/90 Summary: WE HAVE RECOMMENDED REDUCTIONS OF $670,000 TO PROPOSED F iXED HATES FOR EQUIPMENT PRIMARILY BECAUSE OF ERRORS IN UT1UZATION METHODS, ADJUSTMENTS FOR FULLY DEPRECIATED EQUIPMENT, AND UNSUPPORTED ESTIMATES AND ASSUMPTIONS BY THE CONTRACTOR. - EXPLANATION OF ThE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: CONTRACT HAS NOT BEEN AWARDED YET. NEGOTIATIONS ARE STILL PENDING - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: IG FOILOWUP STATUS AS OF 9/30/91: 1j P9AHNO .05-0260-0300047 OH MATERIALS (PR EQ RATES) OH 4/27/90 Summary: WE RECOMMENDED $182,049 IN EFFICIENCIES DUE TO PROPOSED EQUIPMENT RATES 1) EXCEEDING CONTRACT CEIUNG RESTRICTIONS, 2) BEING DEVELOPED USING ESTIMATED COSTS, AND 3) BEING DEVELOPED USING INFORMATION OTHER THAN COST DATA - EXPLANATION OF THE REASONS MANAGEMENT DECISiON HAS NOT BEEN MADE CONTRACT HAS NOT BEEN AWARDED YET. NEGOTIATIONS ARE STILL PENDING. - DESiRED TiMETABLE Foil ACHIEVING A MANAGEMENT DECISiON: (6 FOLLOWUP STATUS AS OF 9/30/91: (1) AsSIgnment Control Title Number PROCUREMENTS CONTRACTS MANAGEMENT DIVISION Washington Cost Advisory Branch P9AHNI•10-0022-1300052 RES-ERCS REGION IV PREAWARD OR 3/27/91 Summary PROPOSED LABOR AND EQUIPMENT RATES ACCEPTED. DEFICIENCIES IN ACCOUNTING SYSTEM WITH PREPARATION OF INVOICES, RECORDING EQUIPMENT COSTS, ACCOUNTING FOR BID AND PROPOSAL COSTS AND PREPARATION OF PROPOSALS. - EXPLANATION OF ThE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: FINAL RESOLUTION WAS COMPLETED ON 9/2/91. 6 FOLLOWUP STATUS AS OF 9/30/91: 111 DIG RECEIVED THE ABOVE EPA STATUS ON 10/29/91. HOWEVER, WE HAVE NOT RECEIVED THE SUMMARY OF NEGOTIATION AS OF 10/3 91. REGIONAL ADMINISTRATOR, REGION 5 E2AWTO-05-0223 .0400020 SELLERSBURG EWS IN 6/14/90 Summary: REGION 5 AWARDED A $5.5 MI WON STEP 2+3 GRANT TO SELLERSBURG,IN FOR A PROJECT WHICH DID NOT MEET THE EUGIBIUTY REQUIREMENTS FOR A STEP 2+3 GRANT. - EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: FINAL DETERMINATION LETTER HAS BEEN SENT TO 0(0, AND THE DIG IS REViEWING CONTESTED ISSUES FOR POSSIBLE SUBMISSION TO THE AUDIT RESOLUTION BOARD. 16 FOILOWUP STATUS AS OF 9/30/91: 16] E2AWTO-05-0224-0400045 W TERRE HAUTE EWS IN 9/28/90 Summary REGION 5 AWARDED A STEP 2+3 GRANT OF $5,275,325 TO WEST TERRE HAUTE, IN FOR A PROJECT WHICH DID NOT MEET THE EUGIBIUTY REQUIREMENTS FOR A STEP 2+3 GRANT. - EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: FINAL DETERMINATION LETTER HAS BEEN SENT TO 01G. AND THE DIG IS REVIEWING CONTESTED ISSUES. 16 FOLLOWIJP STATUS AS OF 9/30/91: 161 E2AWT1-05 -0134-1400007 S HENRY RSD EWS IN 2/25/91 Summary: REGION 5 AWARDED A STEP 2+3 GRANT OF $4,461,060 TO SOUTH HENRY REGIONAL WASTE DISTRICT, IN FOR A PROJECT WHICH DID NOT MEET THE EUGIBIUTY REQUIREMENTS FOR A STEP 2+3 GRANT. • EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: FINAL DETERMINATION LETTER HAS BEEN SENT TO DIG, AND THE OIG IS REViEWING CONTESTED ISSUES. 16 FO(.LOWIJP STATUS AS OF 9/30/91: 161 THE INSPECTOR GENERAL ACT REQUIRES A SUMMARY OF EACH AUDIT REPORT ISSUED BEFORE THE COMMENCEMENT OF THE REPORTING PERIOD FOR WHICH NO MANAGEMENT DECISION HAS BEEN MADE BY THE END OF THE REPORTING PERIOD (INCLUDING THE DATE AND TITLE OF EACH SUCH REPOR1), AN EXPLANATION OF THE REASONS SUCH MANAGEMENT DECISION HAS NOT BEEN MADE, AND A STATEMENT CONCERNING THE DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION ON EACH SUCH REPORT. (The IG provides the summary, the date and title of each such report. The Agency provides the explanation of the reasons such management decision has not been made, and a statement concerning the desired timetable for achieving a management decision on each such report.) 10 Followup Status Codes of Agency’s Response at 9/30/90: 1. No Response 2. Incomplete Response Received 3. Proposed Response Received Awaiting Final Determination 4. Proposed Response Received in Review Process 5. Final Response Received ii Review Process 6. In Pre-ARB Referral Process Assignment Control Title Final Report Final Report Number Issued Issued PROCUREMENT CONTRACTS MANAGEMENT DIVISION Cost Policy and Rate Negotiation Section P9DHLS1O -0110-1100108 RES FY86 INDIRECT COSTS OR 1/24/91 Summary: - EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: THE DIG ASKED THAT NEGOTIATIONS BE SUSPENDED PENDING THE RESOLUTION OF OTHER ISSUES THAT MAY IMPACT THE OUTCOME OF THIS AUDIT. - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: 16 FOLLOWUP STATUS AS OF 9(30(91: [ 1] PROCUREMENTS CONTRACTS MANAGEMENT DIVISION Durham Cost Advisory Branch DBAPLOO2-0340-1100007 SYRACUSE RESEARCH CORP NY 19/12/90 Summary: WE RECOMMENDED FUNDS TO BE RECOVERED AS EFFICIENCIES BASED ON REDUCTION OF THE ESTIMATED COST INCLUDED IN THE PROPOSAL • EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: FINAL DECISION WAS MADE ON 9/39/91. 016 IS AWAITING NOTIFICATION TO CLOSE AUDIT. IG FOLLOWUP STATUS AS OF 9(30(91: (lj (NO CHANGE IN FO(IOWUP STATUS AT 10/25/91. 60 Office of the Inspector General Report to the Congress ------- AssIgnment Control TILIG Final Report Plumber Issued Grants Financial Management RegIon 5 P2CWN9 O5-O336-O300076 WELLSVILLE OH 8/6/90 Summary: OVER $1.9 MILLION QUESTIONED BECAUSE OF THE GRANTEE’S FAILURE TO REHABIUTATE ITS SEWERS. - EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: FINAL DETERMINATION CANNOT BE MADE UNTIL SOURCE SYSTEM EVALUATION SURVEY IS COMPLETE. GRANTEE HAS SIGNED A CONSENT DECREE. - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: THE SOURCE SYSTEM EVALUATION SURVEY WILL BE SUBMITTED ON 7(1(92. IG FOLLOWUP STATUS AS OF 9/30/91: [ 1) N3HMKOO5-0143-0500671 WAYNE CO FY 88 MI 3/20/90 Summary: COUNTY MAY HAVE EARNED AND RETAINED $12,060 IN INTEREST ON EXCESSIVE FEDERAL FUNDING OF $186,000. • EXPLANATiON OF ThE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: A FINAL DETERMINATION LETTER WAS ISSUED TO THE GRANTEE DURING SEPTEMBER 1990. IN A RECENT MEETING, THE LOCAL OIG AGREED TO INVESTIGATE WHY THIS SINGLE AUDIT HAS NOT BEEN CLOSED IN THE IG TRACKING SYSTEM. IG FOLLOWUP STATUS AS OF 9/30/91: [ 2) P2C WN7-05-0492-1 300049 CHICAGO MWRDGC IL 3 /29(91 Summary: MWRDGC, IL CLAIMED $1,233,148 OF INELIGIBLE CONSTRUCTION AND ENGINEERING COSTS. AN ADDITIONAL $146,862 OF UNSUPPORTED FORCE ACCOUNT ENGINEERING COSTS WERE CLAIMED. • EXPLANATiON Of THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: SINCE INTERCHANGEABLE COSTS EXIST BETWEEN THIS GRANT AND ANOTHER GRANT, RESOLUTION OF THE QUESTIONED COSTS IS DEPENDED UPON AUDIT OF GRANT NUMBER C175321-01. - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: THE FINAL DETERMINATION LETTER IS CURRENTLY BEING COORDINATED BETWEEN THE REGION AND THE 01G. ISSUES SHOULD BE RESOLVED IN THE FIRST QUARTER OF FY 1992. IG FOLLOWUP STATUS AS OF 9/30/91: [ 2) G3HVKI-05-0081-1500189 CINCINNATI MSD FY 89 OH 12/12/90 Summary: GRANTEE CLAIMED $383,000 IN INEliGIBLE CHARGE ORDER COSTS. ALSO THE GRANTEE DID NOT HAVE APPROVED COST ALLOCATION PLANS AVAILABLE TO SUPPORT $383,000 IN OVERHEAD COSTS CLAIMED FOR THE YEARS APPUCABLE TO THE GRANT PERIODS. • EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: FINAL DETERMINATION LETTER WAS SENT ON 7/17/91. IG FOLLOWUP STATUS AS OF 9/30/91: [ 1) NO CHANGE IN FOLLOWUP STATUS ON 10/25/91. P2CWN4-06-0183-5100159 EUCLID OH 7/12/85 Summary: WE QUESTIONED THE ENTIRE GRANT AWARD OF ALMOST $14.3 MIWON. THE GRANTEE FAILED TO MEET GRANT CONDITION NO. 3 AND OPERATE THE PLANT SUFFICIENTLY TO MEET IT NPDES PERMIT. - EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: AS A RESULT OF LITIGATION, A CONSENT DECREE WAS SIGNED GIVING THE GRANTEE UNTIL 1996 TO COMPLETE CORRECTIVE ACTIONS. IG FOLLOWUP STATUS AS OF 9/30/91: 131 P3DWL1-05-0360-5100559 PRC ENG CT FY 80/81 IL 9/25/85 Summary: WE RECOMMENDED OVERHEAD RATES OF 145.36 PERCENT AND 131.73 PERCENT FOR FISCAL YEARS 1981 AND 1980, RESPECTIVELY. - EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: PREUMINARY DETERMINATION HAS BEEN ISSUED. THE REGION IS AWAITING LEGAL ADViCE FROM REGIONAL COUNSEL - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: TARGETED FINAl. DETERMINATION DATE IS SECOND QUARTER FY 1992. IS FOL.LOWUP STATUS AS OF 9/30/91: [ 2) AsSignment Control TItle Final Report Number Issued P2C WN4-05-0357-61 00389 DETROIT WSD MI 8/25/86 Summary: THE CITY OF DETROIT, MI CLAIMED OVER $169,000 OF UNREASONABLE ENGINEERING COSTS. • EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: REGIONAL COUNSEL IS CURRENTLY PREPARING A LEGAL OPINION ON THE ALLOWABIUTY OF TIME EXTENSIONS RETROACTIVELY APPROVED BY THE WATER DIVISION FOR THE VARIOUS CONTRACTS FUNDED BY EPA UNDER THE SEVERAL GRANTS. UPON RECEIPT OF THE LEGAL OPINION, REGION WILL ISSUE A PRELIMINARY DETERMINATION TO 01G. IG FOLLOWUP STATUS AS OF 9/30/91: [ 2) P2G WN4 -05-0264-61 00390 DETROIT WSD MI 8125/86 Summary: WE QUESTIONED INEUGIBLE FORCE ACCOUNT COSTS OF $20,872 INCURRED PRIOR TO THE GRANT AWARD. IN ADDITION, UNSUPPORTED FORCE ACCOUNT COSTS OF $36,370 INCURRED AFTER THE APPROVED CONSTRUCTION COMPLETION DATE WERE QUESTIONED. • EXPLANATION OF ThE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: • DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: REGIONAL COUNSEL IS CURRENTLY PREPARING A LEGAL OPINION ON THE ALLOWABIUTY OF TIME EXTENSIONS RETROACTIVELY APPROVED BY THE WATER DIVISION FOR THE VARIOUS CONTRACTS FUNDED BY EPA UNDER THE SEVERAL GRANTS. UPON RECEIPT OF THE LEGAL OPINION, REGION WILL ISSUE A PRELIMINARY DETERMINATION TO 01G. IG FOLLOWUP STATUS AS OF 9/30191: P2CWN4-05-02636100391 DETROIT WSD MI 8125/86 Summary: THE GRANTEE CLAIMED UNREASONABLE FORCE ACCOUNT COSTS OF $286,000. THE GRANTEE ALSO CLAIMED INEUGIBLE COSTS OF $15,000. - EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: REGIONAL COUNSEL IS CURRENTLY PREPARING A LEGAL OPINION ON THE ALLOWABIUTY OF TIME EXTENSIONS RETROACTIVELY APPROVED BY THE WATER DIVISION FOR THE VARIOUS CONTRACTS FUNDED BY EPA UNDER THE SEVERAL GRANTS. UPON RECEIPT OF THE LEGAL OPINION, REGION WILL ISSUE A PRELIMINARY DETERMINATION TO 01G. IG FOLLOWUP STATUS AS OF 9/30/91: 121 P2CWN4-05-0280-6100574 DETROIT WSD MI 9/30/86 Summary: WE QUESTIONED INELIGIBLE COST OF $293,000 MOSTLY FOR CHANGE ORDERS. WE ALSO QUESTIONED UNNECESSARY COST OF $399,000 FOR FORCE ACCOUNT AND GRANTEE DELAYS. CHANGE ORDER COSTS OF $14800 WERE UNSUPPORTED. - EXPLANATiON OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: REGIONAL COUNSEL IS CURRENTLY PREPARING A LEGAL OPINION ON THE ALLOWABIUTY OF TIME EXTENSIONS RETROACTIVELY APPROVED BY THE WATER DIVISION FOR THE VARIOUS CONTRACTS FUNDED BY EPA UNDER THE SEVERAL GRANTS. UPON RECEIPT OF THE LEGAL OPINION, REGION WILL ISSUE A PRELIMINARY DETERMINATION TO 01G. IG FOLLOWUP STATUS AS OF 9(30/91: 121 P2CWN4 -05-0265-6100575 DETROIT WSD WI 9/30/86 Summary: THE GRANTEE CLAIMED INEUGIBLE AND UNSUPPORTED CONSTRUCTION COSTS OF $559,000. THE GRANTEE ALSO CLAIMED UNREASONABLE ENGINEERING COSTS OF $374,000. • EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: REGIONAL COUNSEL IS CURRENTLY PREPARING A LEGAL OPINION ON THE ALLOWABIUTY OF TIME EXTENSIONS RETROACTIVELY APPROVED BY THE WATER DIVISION FOR THE VARIOUS CONTRACTS FUNDED BY EPA UNDER THE SEVERAL GRANTS. UPON RECEIPT OF THE LEGAL OPINION, REGION WILL ISSUE A PRELIMINARY DETERMINATION TO 01G. IG FOLLOWUP STATUS AS OF 9(30(91: (21 April 1, 1991 through Seplember 30, 1991 61 ------- Assignment Control Title Final Report Number Issued P2CWNS-05-0242-7000034 DETROIT WSD MI 10 / 6/86 Summaty WE QUESTIONED INEUGIBLE CONSTRUCTION AND ENGINEERING COSTS OF $20006. IN ADDITION, WE QUESTIONED UNSUPPORTED ENGINEERING COSTS OF $40,495 INCURRED AFTER THE APPROVED CONSTRUCTION COMPt.ETION DATE. • EXPLANA11ON OF ThE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: - DESIRED TIMETABLE FOR ACHIEViNG A MANAGEMENT DECISION: REGIONAL COUNSEL IS CURRENTLY PREPARING A LEGAL OPiNION ON THE ALLOWAB1UTY OF TIME EXTENSIONS RETROACTIVELY APPROVED BY THE WATER OMSION FOR THE VARIOUS CONTRACTS FUNDED BY EPA UNDER THE SEVERAL GRANTS. UPON RECEIPT OF THE LEGAL OPINION, REGION WiLL ISSUE A PRELJMINARY DETERMINATION TO 0(3. IG FOILOWUP STATUS AS OF 9/30/91: (2) P2CWN5O5-0246-7000044 DETROIT WSD MI 10/ 7/86 Summary THE GRANTEE CLAIMED UNREASONABLE FORCE ACCOUNT COSTS OF $330,000. - EXPLANATION OF ThE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: • DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: REGIONAL COUNSEL IS CURRENTLY PREPARING A LEGAL OPINION ON THE ALLOWABILITY OF TIME EXTENSIONS RETROACTIVELY APPROVED BY THE WATER DMSION FOR THE VARIOUS CONTRACTS FUNDED BY EPA UNDER THE SEVERAL GRANTS. UPON RECEIPT OF THE LEGAL OPINION, REGION WILL ISSUE A PREUMINARY DETERMINATION TO 01G. IG FOLLOWIJP STATUS AS OF 9/30/91: (2) P2GWN5 .05-0275-7000045 DETROIT WSD MI 10/ 7/86 Summaly: WE QUESTIONED $80,000 OF INEUGIBLE ENGINEERING AND CONSTRUCTION COSTS. ENGINEERING COSTS OF $112,000 INCURRED AFTER THE APPROVED CONSTRUCTION COMPLETION DATE WERE NOT SUPPORTED. - EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: - DESIRED TiMETABLE FOR ACHIEVING A MANAGEMENT DECISION: REGIONAL COUNSEL IS CURRENTLY PREPARING A LEGAL OPINION ON THE ALLOWABILITY OF TIME EXTENSIONS RETROACTIVELY APPROVED BY THE WATER DMSION FOR THE VARIOUS CONTRACTS FUNDED BY EPA UNDER THE SEVERAL GRANTS. UPON RECEIPT OF THE LEGAL OPINION, REGION WiLL ISSUE A PREUMINARY DETERMINATION TO 0(3. IG FOLLOWUP STATUS AS OF 9/30/91: (2) P2CWN5-05-0247-7000049 DETROIT WSD MI 10/ 8186 Summary: WE QUESTIONED UNREASONABLE TECHNICAL SERVICES AND CONSTRUCTION COSTS OF $559,000. - EXPLANATION OF ThE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: 13 FOLLOWUP STATUS AS OF 9/30/91: (2) P2CWN5 .05 .0276-7000050 DETROIT WSD MI 19/8186 Summary: WE QUESTIONED $59,000 OF INEUGIBLE ENGINEERING COSTS. ENGINEERING COSTS OF $433,600 INCURRED AFTER THE APPROVED CONSTRUCTION COMPLETION DATE WERE NOT SUPPORTED. - EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: REGIONAL COUNSEL IS CURRENTLY PREPARING A LEGAl. OPINION ON THE ALLOWABIUTY OF TIME EXTENSIONS RETROACTIVELY APPROVED BY THE WATER DMSION FOR THE VARIOUS CONTRACTS FUNDED BY EPA UNDER THE SEVERAL GRANTS. UPON RECEIPT OF THE LEGAL OPINION, REGION WILL ISSUE A PREUMINARY DETERMINATION TO 01G. 43 FOLLOWUP STATUS AS OF 9/39/91: (2) E2BWL5-05-0136-7000980 SAUGET IL 3/31/87 summary: SAUGET, IL WAS AWARDED FEDERAL FUNDS IN EXCESS OF $7 MI WON FOR INELIGIBLE AND UNNECESSARY PROJECT COSTS. - EXPLANATION OF THE PEASONS MANAGEMENT DECISION HAS NOT BEEN MADE: AUDIT REPORT HAS COMPLEX ISSUES WITH TOTAL QUESTIONED AND UNSUPPORTED COSTS OF $15,323,316. THE REGION IS SEEKING GUIDANCE FROM REGIONAL COUNSEL AND WATER DMSION. A DEVIATION REQUEST IS PENDING IN EPA HEADQUARTERS. - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: IG FOLLOWUP STATUS AS OF 9/30/91: (2) Assignment Control Title Final Report Number Issued P2GWN5-05-0132-8000464 DETROIT WSD MI 1/20/88 Summary: DETROIT CLAJMED INEUGIBLE COSTS OF ALMOST $2.6 MIWON RESULTING FROM ITS FAILURE TO HONOR A CONTRACT. WE ALSO QUESTIONED UNSUPPORTED COSTS OF ALMOST $2.1 MIWON. • EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: REGIONAL 3 COUNSEL IS CURRENTLY PREPARING A LEGAL OPINION ON THE ALLOWABIUT’( OF TIME EXTENSIONS RETROACTIVELY APPROVED BY THE WATER DIVISION FOR THE VARIOUS CONTRACTS FUNDED BY EPA UNDER THE SEVERAL GRANTS. UPON RECEIPT OF THE LEGAL OPINION, REGION WILL ISSUE A PRELIMINARY DETERMINATION TO 0 (3. IG FOLLOWUP STATUS AS OF 9/30/91: (2] P2C WN7.05-0237-81 00724 DETROIT WSD MI 8129/88 Summary: DETROIT, MI CLAIMED OVER $274,000 OF INELIGIBLE CONSTRUCTION COSTS. WE ALSO QUESTIONED UNSUPPORTED ENGINEERING AND FORCE ACCOUNT COSTS OF $662,000. • EXPLANATiON OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: REGIONAL COUNSEL IS CURRENTLY PREPARING A LEGAL OPINION ON THE ALLOWABIUTY OF TIME EXTENSIONS RETROACTIVELY APPROVED BY THE WATER DIVISION FOR THE VARIOUS CONTRACTS FUNDED BY EPA UNDER THE SEVERAL GRANTS. UPON RECEIPT OF THE LEGAL OPINION, REGION WILL ISSUE A PRELIMINARY DETERMINATION TO 0(3. IG FOLLOWUP STATUS AS OF 9/30/91: (2) P2GWN5-05-0169-8100774 DETROIT WSD MI 9/1/88 Summary: WE QUESTIONED INELIGIBLE CONSTRUCTION AND ENGINEERING COSTS OF $96,520. ENGINEERING COSTS OF $992,430 INCURRED AFTER THE APPROVED CONSTRUCTION COMPLETION DATE WERE NOT SUPPORTED. - EXPLANATION OF ThE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: • DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: REGIONAL COUNSEL IS CURRENTLY PREPARING A LEGAL OPINION ON THE AIIOWABIUTY OF TIME EXTENSIONS RETROACTIVELY APPROVED BY THE WATER DIVISION FOR THE VARIOUS CONTRACTS FUNDED BY EPA UNDER THE SEVERAL GRANTS. UPON RECEIPT OF THE LEGAL OPINION, REGION WILL ISSUE A PRELIMINARY DETERMINATION TO 0(3. 13 FOLLOWUP STATUS AS OF 9/30/91: (2) OFFICE OF INFORMATION RESOURCES MANAGEMENT E1NMBO-15-0021-1100152 IBM 3090 OPERATIONS AT NCC 3/29/91 Summary: EPA DID NOT FORECAST ITS COMPUTER REQUIREMENT, OR MATCH ITS NEEDS TO AVAILABLE RESOURCES. ALSO, AN ESTIMATED $ 5.3MIL WAS UNNECESSARILY SPENT ANNUALLY DUE TO COMPUTER OPERATIONS/USE, SOFTWARE APPUCATIONIDESIGN AND DATA STORAGE/RETRIEVAL • EXPLANATiON OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: OARM RESPONDED TO THIS AUDIT ON 6/14/91. AFTER RECEIPT OF THAT RESPONSE, THE OIG REQUESTED ADDITIONAL INFORMATION. THIS INFORMATION WAS FURNISHED 10/1/91. • DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: FINAL DETERMINATION SHOULD BE ISSUED BY THE END OF NOVEMBER 1991. IG FOLLOWUP STATUS AS OF 9/30/91: (2) REGIONAL ADMINISTRATOR, REGION 3 P2CW8-03-0152-1100147 YORK COuNTY OF VA 26/91 Summary: RECOMMENDED COST RECOVERY INCLUDES INEUGIBLE ($1,109,034) AE BASIC OTHER AE AND PROJECT INSPECTION FEES, ADMINISTRATIVE EXPENSES. AND CONSTRUCTION COSTS; AND UNSUPPORTED ($1,136,703) OF AE BASIC, OTHER AE AND PROJECT INSPECTION FEES, ADMIN EXP, AND CONSTRUCTION COSTS. • EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: DUE TO THE COMPLEXITIES OF THE ISSUES INVOLVED, SEVERAL CONSULTATIONS WITH VARIOUS PARTIES WERE REQUIRED. A DRAFT FINAL DETERMINATION LETTER HAS BEEN SENT TO THE 04G. ADDITIONAL MEETINGS ARE NOW BEING HELD WITH THE ENGINEERING SCIENCE UNIT OF THE OIG TO DISCUSS THESE ISSUES. - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: PROPOSED COMPLETION DATE IS DECEMBER 15, 1991. IG FOIIOWUP STATUS AS OF 9/30/91: (4) 62 Office of the Inspector General Report to the Congress ------- Assignment Control Title Final Report Number Issued REGIONAL ADMINISTRATOR, REGION 4 E2CWN7-04-0302-0300054 SYLACAUGA UTILITIES BD AL 5/10/90 Summary: THE GRANTEE TERMINATED THE ORIGINAL CONTRACTOR FOR CONVENIENCE AND DID NOT HOLD THE CONTRACTOR AND/OR THE BONDING COMPANY RESPONSIBLE FOR CHANGED SITE CONDITIONS AND INCREASED COSTS OF $1.6 MILLION. • EXPLANATiON OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: REGION AND THE LOCAL OIG CANNOT REACH AN AGREEMENT ON A MANAGEMENT DECISION. CIG MAY REFER THIS AUDIT TO EPA’S AUDIT RESOLUTION BOARD. - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: 10 FOLLOWUP STATUS AS OF 9/30/91: [ 2] NO CHANGE IN FOLLOWUP STATUS AS OF 10/25/91. THE ACTION OFFICIAL HAS NOT ADDRESSED AU. THE ISSUES OF THE AUDIT REPORT. E2CWNO-04-0176-1300034 JEFFERSON COUNTY AL 2/12191 Summary: THE GRANTEE CLAIMED $663,971 OF INEUGIBLE CONSTRUCTION, AND ENGINEERING EXPENSES AND $1,730 OF UNSUPPORTED ADMINISTRATIVE EXPENSES. - EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: THE REGION PROViDED THE FINAL DETERMINATION LETTER TO THE 040 ON 9/30/91. APPROVAL BY THE 016 IS EXPECTED BY 10/31/91. IG FO1.LOWUP STATUS AS OF 9/30/91: [ 31 S2CWN8-04-0251-1300043 LEBANON TN 3/13/91 Summary: COSTS QUESTIONED REPRESENTS ENGINEERING FEES ADJUSTED FOR OVERHEAD RATES, DUPLICATION OF FRINGE BENEFITS, CONTRACTS EXCEEDED AND INSPECTION INCURRED AFTER SCHEDULED COMPLETION. ALSO, CONSTRUCTION COSTS QUESTIONED FOR FAILURE TO RETAIN BID BOND OF LOW BIDDER. • EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: (NO REASONS WERE GIVEN WHY NO RESPONSE WAS MADE TO THE AUDIT UNTIL IT WAS OVER 6 MONTHS PAST THE REPORT ISSUE DATE) - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: FINAL DETERMINATION LETTER WAS ISSUED 9/30/91, AND THE 040 CLOSED THE AUDIT ON 10/9/91. 10 FOLLOWUP STATUS AS OF 9/30/91: 151 G3HWKI-04-0078-1500307 CAVELAND SANITATION AUTHOR. KY 1/29/91 Summary: • EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: (NO REASONS WERE GIVEN WHY NO RESPONSE WAS MADE TO THE AUDIT UNTIL IT WAS OVER 6 MONTHS PAST THE REPORT ISSUE DATE) - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: FINAL DETERMINATION LETTER WAS ISSUED ON W27/91, AND OIG CLOSED AUDIT ON 10/8/91. IG FOLLOWUP STATUS AS OF 9/30/91: [ 5J REGIONAL ADMINISTRATOR, REGION 2 P2CW8 -02-0028.0100129 NYC - SPRING CREEK NY 1(29(90 Summary: THE GRANTEE CLAIMED TOTAL UNALLOWABLE COSTS OF $2,944,029 FOR THE DESIGN AND CONSTRUCTION OF A RETENTION BASIN. - EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: THE NEW YORK STATE DEPARTMENT OF ENVIRONMENTAL CONSERVATION PREPARED A FINAL DETERMINATION WHICH WAS NOT ACCEPTED BY THE 04G. THE 010 HAS REQUESTED ADDITIONAL INFORMATION TO SUPPORT THE ALLOWABLE COSTS. - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: A FINAL DETERMINATION SHOULD BE ISSUED DURING THE FIRST QUARTER OF FY 1992. IG FOIIOWUP STATUS AS OF 9/30/91: [ 21 P2CW*7.02.0228 0100139 WESTCHESTER CO NY 2/ 1/90 Summary: THE GRANTEE CLAIMED TOTAL UNALLOWABLE COSTS OF $6,404,317 TO UPGRADE A WASTEWATER TREATMENT PLANT. • EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: THE AUDIT RESOLUTION PREPARED BY NEW YORK STATE DEPARTMENT OF ENViRONMENTAL CONSERVATION HAD BEEN PENDING A DECISION ON THE GRANTEE’S NON-COMPLIANCE WITH THE USER CHARGE REQUIREMENTS OF THE CLEAN WATER ACT. - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: FINAL DETERMINATION IS PLANNED DURING THE FIRST QUARTER OF FY 1992. PG FOLLOWUP STATUS AS OF 9/30191: [ 3j Assignment Control Title Final Report Number Issued P2CWL9-02-0246-1100136 WESTCHESTER CO - PEEKSKILL NY 3 /4/91 Summary: GRANTEE CLAIMED $4,111,482 UNSUPPORTED COSTS AND $52,012 OF INELIGIBlE COSTS. THE GRANTEE HAS NOT IMPLEMENTED THEIR USER CHANGE SYSTEM. - EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: THE AUDIT RESOLUTION PREPARED BY NEW YORK STATE DEPARTMENT OF ENVIRONMENTAL CONSERVATION HAD BEEN PENDING A DECISION ON THE GRANTEE’S NON-COMPLIANCE WITh THE USER CHARGE REQUIREMENTS OF THE CLEAN WATER ACT. - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: FINAL DETERMINATION IS PLANNED DURING THE FIRST QUARTER OF FY 1992. 13 FOLLOWUP STATUS AS OF 9/30/91: 131 C3HMK1-02.0070-1500306 EQB PR 1/29/91 Summary: THE ENVIRONMENTAL QUALITY BOARD OF PUERTO RICO CLAIMED $101,263 IN INEUGIBLE COSTS INCLUDING $1,413 OF INELIGIBLE PAYROLL COSTS AND $99,850 OF UNSUPPORTED COSTS DUE TO LACK OF DOCUMENTATION FO VARIOUS EPA PROGRAMS. • EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: THE GRANTEE SUBMITTED AN EXTENSIVE FORMAL RESPONSE WHICH WAS RECEIVED ON 9/15/91. - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: THE REGION PLANS TO ISSUE FINAL DETERMINATION DURING THE FIRST QUARTER OF FY 1992. 13 FOLLOWUP STATUS AS OF 9(30/91: [ 11 E2C WL9-02-0063-91 00508 NYSDEC 205 G NY 9/29/89 Summary: NYSDEC’S ADMINISTRATION OF THE CONSTRUCTION MANAGEMENT ASSISTANCE PROGRAM (205 (G)1 WAS NOT ADEQUATE TO ENSURE THE PROPER CONTROWNG AND REPORTING OF PROGRAM EXPENDITURES. - EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: THE REGION’S REVIEW OF THE LATEST NYSDEC DOCUMENTATION DISCLOSED UNALLOWABLE LABOR COSTS. 043 REQUESTED MORE DOCUMENTATION TO EXPLAIN LABOR COSTS DISTRIBUTIONS. NYSDEC HAS AGREED TO SUBMIT ALL REQUIRED DOCUMENTATION. - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: FINAL DETERMINATION IS EXPECTED DURING THE FIRST QUARTER OF FY 1992. 0 FOLLOWUP STATUS AS OF 9/30/91: [ 21 REGIONAL ADMINISTRATOR, REGION 9 S5BG8-09-O202-0300037 CA DEPT OF HEALTH CA 3/30/90 Summary: COSTS OF $2,419,415 QUESTIONED AS INELIGIBLE AND $1,639,629 AS UNREASONABLE INEUGIBLES RELATED TO FORCE ACCOUNT AND CONTRACT COSTS UNREASONABLE RELATED TO CONTRACT COSTS. GRANTEE’S FINANCIAL MANAGEMENT SYSTEM DETERMINED INADEQUATE. MOST INEUGIBLE COST WERE THE RESULT OF THIS. - EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: ALTHOUGH INITIALLY DELAYED BY SEVERAL COMPLEX ISSUES, THE FINAL DETERMINATION LETTER WAS APPROVED BY THE 010 ON 6/17/91 AND SENT TO THE STATE ON 7/29/91. DUE TO REORGANIZATION OF THE STATE’S ENVIRONMENTAL DEPARTMENT, THE STATE HAS REQUESTED AN ADDITIONAL OPPORTUNITY TO REVIEW THE FINAL DETERMINATION LETTER. - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: PG FOLLOWUP STATUS AS OF 9/30/91: [ 21 (THE REGION’S FINAL DETERMINATION LETTER DEFERS ISSUES WITHIN THE AUDIT REPORT AND IS NOT CONSIDERED A COMPLETE RESPONSE.) S2CW8-09-01 17-0300077 SCOTtS VALLEY, CITY OF CA 8/7/90 Summary: INELIGIBLE COSTS OF $533,500 REPRESENT NE FEES OF $123,960 INCURRED PRIOR TO APPROVAL $389,804 IN EXCESS OF APPROVAL $1,445 AFTER COMPLETION $28,561 OF INEUGIBLE COSTS, ($10,275) ADDITIONAL CONSTRUCTION AND $44,975 OF UNREASONABLE IN EXCESS OF GRANT AMOUNT. - EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: THE PROPOSED FINAL DETERMINATION LETTER WAS APPROVED BY THE 010 ON 3/29/91. DEVIATION REQUESTS ON SEVERAL DETERMINATIONS WERE SUBMITTED AND APPROVED ON 9/24/91. - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: A FINAL DETERMINATION LETTER IS EXPECTED BY THE END OF THE FIRST QUARTER FY 1992. 10 FOLLOWUP STATUS AS OF 9/30191: [ 21 ApnI 1 1 991 through September 30, 1991 63 ------- Assignment Control Title Final Report Number Issued E2CW ’8-0900240300090 HONOLULU CITY & COUNTY OF HI 9/19/90 Sunwnwy INELIGIBLE COST QUESTiONED OF $279208 CONSISTED OF $247,009 OF UNALLOWABLE FORCE ACCOUNT/ADMINISTION COSTS AND $31,649 FOR INEliGIBLE CONSTRUCTION COST. $3,786,208 OF UNREASONABLE COSTS RELATED TO INCOMPLETE STEP I GRANT AND UNDERUTILIZED FACILITY. - EXPLANATION OF THE REASONS MANAGEMENT DEC1S 1ON HAS NOT BEEN MADE: THE REGION HAS RECEIVED A DRAFT FINAL DETERMINATION LETTER FROM THE STATE. SOME OF THE DETERMINATIONS WERE UNACCEPTABLE TO THE REGION. THE TOPICS WERE DISCUSSED BETWEEN THE STATE AND EPA SENIOR MANAGERS. • DESIRED tiMETABLE FOR ACHIEVING A MANAGEMENT DECISION: THE FiNAL DETERMINATION LETTER IS EXPECTED BY MID FY 199Z IG FOILOWUP STATUS AS OF 9/30 (91: [ 1) E2CWN9 .09-0033-0300091 HONOLULU, CITY & COUNTY OF HI 9/19(90 Summy INELIGIBLE COST QUESTIONED OF $1,106,980 CONSISTS OF $446,176 OF UNDOCUMENTED ADMINISTRATION COST AND $660,744 FOR CONSTRUCTION COSTS RELATED TO PERMITS. UNREASONABLE COSTS OF $5,298,871 RELATED TO UNDERUTILIZED FACILITIES. - EXPLANATION OF ThE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: THE REGION HAS RECEIVED A DRAFT FINAL DETERMINATION LETTER FROM THE STATE. SOME OF THE DETERMINATIONS WERE UNACCEPTABLE TO THE REGION. THE TOPICS WERE DISCUSSED BETWEEN THE STATE AND EPA SENIOR MANAGERS. - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: THE FINAL DETERMINATION LETTER IS EXPECTED BY MID FY 199a 13 FOILOWUP STATUS AS OF 9f30 91: 1J E2CWB-09-0037 .0300092 HONOLULU, CITY & COUNTY OF HI 9/ 19/90 Summaly: INELIGIBLE COSTS QUESTIONED OF $16,269,686 CONSISTED OF $552,471 OF UNAllOWABLE ADMIN/FORCE ACCOUNT COSTS, $734,663 FOR UNALLOWABLE NE FEE $14,982,872 FOR INEUGIBLE CONSTRUCTION COSTS; ADDITIONALLY $2,493,500 FOR UNNECESSARY COSTS FOR EQUIPMENT NOT IN USE BY GRANTEE. - EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: THE REGION HAS RECEIVED A DRAFT ANAL DETERMINATION LETTER FROM THE STATE. SOME CF THE DETERMINATIONS WERE UNACCEPTABLE TO THE REGION. THE TOPICS WERE DISCUSSED BETWEEN THE STATE AND EPA SENIOR MANAGERS. - DESIRED TIMETABLE FOR ACHIEViNG A MANAGEMENT DECISION: THE FINAL RESOLUTION OF THIS AUDIT IS NOT EXPECTED UNTIL THE END OF FY 1992. IG FOILOWUP STATUS AS OF 9/39/91: 1J 558KN9-09-0267-0300098 SOUTH BAY MULTI-SITE CA 9/28/90 Summary: COSTS OF $2,903,899 WERE QUESTIONED AS UNSUPPORTED BY ADEQUATE SOURCE DOCUMENTATION. • EXPLANATION OF ThE REASONS MANAGEMENT DEC1S 1ON HAS NOT BEEN MADE: THE O4G APPROVED A PROPOSED ANAL DETERMINATION LETTER IN A MEMORANDUM DATED 9/19/91. THE LETTER WAS ISSUED TO THE STATE WATER RESOURCES CONTROL BOARD ON 9/27/91. THE REGION IS WAITING FOR ITS RESPONSE. - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: THE AUDIT SHOULD BE CLOSED BY THE END OF THE FIRST QUARTER FY 1992. 13 FOLLOWUP STATUS AS OF 9/39/91: 121 (THE REGION’S ‘FiNAL DETERMINATION LETTER’ DEFERS ISSUES WITHIN THE AUDIT REPORT AND IS NOT CONSIDERED A COMPLETE RESPONSE.) E2CW ’7-09O1 92-1 300053 SUN VALLEY WATER & SAN DIST NV 3/29/91 Summwy INELIGIBLE COST QUESTIONED OF $6 ,221,120 CONSISTS OF 1152 FOR NOT MEETING / 3 RULE $995,653 FOR UNALLOWABLE NE; $116,120 FOR UNALLOWABLE ADMINISTRATION AND $4,300 OF l/E CO’S ALSO $2,437,748 QUESTiONED FOR UNDERUTILIZATION OF FACILITIES. - EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: THE REGION WORKED WITH THE STATE TO DRAFT A PROPOSED DETERMINATION LETTER. FT WAS SENT TO THE OIG PRIOR TO 9/30. - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: FINAL DETERMINATION SHOULD BE ISSUED IN THE FIRST HALF OF FY 1992 16 FOILOWUP STATUS AS OF 9/39/91: ill EPA SUBMITTED THE STATE’S RESPONSE. HOWEVER, 043 DID NOT CONSIDER THIS TO BE ACCEPTABLE AS EPA’S POSITION. Assignment Control Title Final Report Number Issued E2AWP9-09-0189-1400006 EARLY WARNING - MONTEREY CA 2/11/91 Summary: REGION 9 AWARDED $6.1 MIWON GRANT AMENDMENT WHICH DID NOT MEET THE REQUIREMENTS OF THE CLEAN WATER ACT OR THE EPA REGULATIONS. IN ADDITION THE U.S. ARMY OVERPAID $6.2 MI WON FOR ITS SHARE OF THE CONSTRUCTION PROJECT. - EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: ThIS AUDIT IS LINKED TO THE MARINA EARLY WARNING AUDIT (9400043). THE REGION HAS BEEN TRYING TO RESOLVE ISSUES COMMON TO BOTH AUDITS WITH THE 04G. WATER DIViSION MET WITH 046 ON 9/16/91. • DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: FINAL RESOLUTiON IS EXPECTED BY SECOND QUARTER OF FY 1992. 13 FOLLOWUP STATUS AS OF 9/30/91: flJ E2AWPI .09.0059-1400018 GUALALA COMM SER 01ST. IEWR CA 3128 /91 Summary: REGION 9 CIRCUMVENTED EPA REGULATIONS IN AWARDING A $8.7 MI WON YEAR-END GRANT TO THE GUALALA COMMUNITY SERVICES DISTRICT FURTHER POTENTIAL COST SAVINGS OF AT LEAST $162 MIWON NEED TO BE CONSIDERED BY THE REGION. -EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: DRAFT DETERMINATION LETTER WAS SUBMITTED TO 016 ON 6(14/91, BUT WAS NOT APPROVED. AS A RESULT, TWO DEVIATION REQUESTS WERE FORWARDED TO HEADQUARTERS. - DESIRED TiMETABLE FOR ACHIEVING A MANAGEMENT DECISION: IG FOLLOWUP STATUS AS OF 9/30/91: 121 (THE REGION’S ‘FINAL DETERMINATION LE1TER DEFERS ISSUES WITHIN THE AUDIT REPORT AND IS NOT CONSIDERED A COMPLETE RESPONSE.) N3HMK1-09-0108-1500445 SANTA CLARA VALLEY WTR 01ST CA 3112/91 Summary: - EXPLANATION OF ThE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: REGION HAS BEEN WORKING WITH THE STATE TO CHANGE THE PRACTICE CONTESTED BY AUDIT. 043 HAS RECEIVED THE STAFFS PROPOSALS TO REViSE THE PROCESS FOR SUBMITTAL OF FEDERAL CASH TRANSACTION REPORTS. REGION IS NOW AWAITING DIG RESPONSE. - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: 13 FOLLOWUP STATUS AS OF 9/30/91: 111 DIG RECEIVED RESPONSE ON 10/21/91 AND CLOSED OUT THE AUDIT ON 19/21/91. E2AWP9-09-0065-9400025 HOMELAND EARLY WARNING CA 3/31/89 Sunvnary SPECIAL REVIEW OF CONSTRUCTION GRANT OF WASTEWATEA TREATMENT PLANT FOUND $3,737,139 IN FEDERAL SHARE COSTS QUESTIONED. AN EARLY WARNING LETTER ADVISED THAT COSTS FOR THE COLLECTION SYSTEM PORTION OF THE PROJECT DID NOT QUALIFY FOR FUNDING BECAUSE OF THE ‘2/3 RULE. - EXPLANATION OF ThE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: RESOLUTION OF THIS AUDIT HAS BEEN REFERRED TO THE AUDIT RESOLUTION BOARD. A CLARIFICATION OF NATIONAL POLICY IS BEING PAEPARED BY THE OFFiCE OF WATER THAT IS EXPECTED TO HELP IN RESOLVING THE AUDIT. • DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: 13 FOLLOWUP STATUS AS OF 9/30/91: [ 51 E2AWP9-09-0230-9400043 EARLY WARNING-MARINA CWD CA 9/26(89 Summary: SPECIAL REVIEW OF GRANT TO BUY CAPACITY RIGHTS FROM REGIONAL WASTEWATER TREATMENT PLANT RESULTED IN AN EARLY WARNING LETTER TO EPA MANAGEMENT THAT THE AWARD VIOLATED 40 CFR3S 2250 AND THAT TOTAL COSTS QUESTIONED OF $1,694,000 (F.S. $931,700) WOULD CAUSE ‘WINDFALL’. - EXPLANATION OF ThE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: THIS AUDIT IS LINKED TO MONTEREY EARLY WARNING AUDIT (1400006). REGIONAL PROGRAM STAFF HAVE BEEN TRYING TO RESOLVE ISSUES COMMON TO BOTH AUDITS WITH THE 04G. REGION’S WATER DIVISION MET WITH 016 ON 9/16(91. - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: BASED ON THAT MEETING, FINAL RESOLUTION IS EXPECTED BY THE SECOND QUARTER OF FY1992. 13 FOLLOWUP STATUS AS OF 9/30/91: 161 Office of the Inspector General Report to the Congress ------- Assignment Control Title Final Report — Issued REGIONAL ADMINISTRATOR, REGION 6 E2CWN8-06-00370300055 BARTLESVILLE OK 5111/90 Summary: AUDIT OF CONSTRUCTION GRANTS C-400690-O1,02,03,12,13 & 14 QUESTIONED COSTS OF $10,974,785 (FEDERAL SHARE $8,189,026). THE GRANTEE FAILED TO UPDATE FACIUTY PLANS AND COST EFFECTIVE ANALYSIS EVEN ThOUGH DESIGN INCREASED CONSTRUCTION COSTS FROM $3.1 N TO $9.8 N. • EXPLANA11ON OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: A REQUEST FOR A DEViATION FOR THE CITY OF BARTLESVILLE ON PROJECT PERFORMANCE WAS SUBMITTED TO EPA HEADQUARTERS ON 5131/91. FURThER ACTION IS PENDING THE OUTCOME OF THE DEVIATION REQUEST. - DESIRED 11METABLE FOR ACHIEViNG A MANAGEMENT DECISION: 16 FOWY,VUP STATUS AS OF 9/30/91: 131 P5BFNO-06-0117-1300041 OKLA DEPT OF HEALTH OK 3/9/91 1ummar - EXPLANATION OF ThE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: OIG DISAGREED WiTH PROPOSED FINAL DETERMINATION LETIER. IT WAS REVISED AS OF 9/30/91 AND IS CURRENTLY BEING REViEWED BY THE OFFICE OF REGIONAL COUNSEL - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: APPROVAL IS ANTICIPATED DURING THE FIRST QUARTER FY 1992. 16 FOILOWUP STATUS AS OF 9(30/91: (21 P5BGNO-06-0118-1 300042 OKLA DEPT OF HEALTh OK 3/9(91 Summary: • EXPLANATiON OF ThE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: OIG DISAGREED WITH PROPOSED FINAL DETERMINATION LETTER. IT WAS REVISED AS OF 9(30/91 AND IS CURRENTLY BEING REVIEWED BY THE OFFICE OF REGIONAL COUNSEL - DESIRED TIME1 ABLE FOR ACHIEVING A MANAGEMENT DECISION: APPROVAL IS ANTICIPATED DURING THE FIRST QUARTER FY 1992. 16 FOU.OWUP STATUS AS OF 9(30/91: 121 G3HWKI-06-0079-1 500502 KOUNTZE TX 3/28/91 Summarr - EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: GRANTEE DID NOT COMPLY WITH GRANT CONDITIONS AND HAD NO PROPERTY MANAGEMENT SYSTEM AS REQUIRED BY EPA REGULATIONS. EViDENCE OF CI1YS CORRECTIVE ACTION IN PROGRESS HAS BEEN VERIFIED BY TEXAS WATER DEVELOPMENT BOARD. FINAL DETERMINATION TO BE ISSUED WHEN CORRECTIVE ACTIONS COMPLETED. • DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: 16 FOLLOWUP STATUS AS OF 9/30/91: (11 REGIONAL ADMINISTRATOR, REGION 7 G3HWK1-07-0058-1500384 CHILLICOTHE MO 2/25/91 Summary: • EXPLANATiON OF ThE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: THIS AUDIT IS CLOSED. - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: A Final etenalnation Letter was received and the audit was closed out on October 21, 1991. IGFOLLOWUPSTATUSASOF 9/30/91: [ 11 REGIONAL ADMINISTRATOR, REGION S E2CW7 -08-0036-0100418 THREE LAKES WATER & SANIT CO 7/31/90 Summary: THREE LAKES WATER AND SANITATION DISTRICT, GRAND LAKE, CO DID NOT PROCURE CONSTRUCTION SERVICES FOR THE BUILDING OF THEIR NEW $14 MIWON WASTEWATER TREATMENT WORKS BASED ON THE LOW COMPETITIVE BID. IN ADDITION, THE CLAIMS FILED WITH EPA COULD NOT BE SUPPORTED. - EXPI.ANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: EPA REGION 8 OFFICE PREPARED A MANAGEMENT DECISION LETTER ON 10/24/90 TO THE 0 16. oN 11/21/90 A DEVIATION REQUEST WAS SENT TO EPA /HO FOR REVIEW. IT WAS APPROVED ON 8/21/91. - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: THE FINAL DETERMINATION LETTER IS EXPECTED BY THE END OF THE FIRST QUARTER OF FY1992. 6 FOUOWUP STATUS AS OF 9/30/91: 1 1J Assignment Control Title Final Report Number Issued PSBHN9O8-0092-0300096 SO. ADAMS COUNTY WSD CO 9/27/90 Summary: SOUTH ADAMS COUNTY’ WATER & SANITATION DISTRICT (SACWSD) DID NOT PROVIDE CONTRACTS FOR ITS WATER TREATMENT FACIUTY IN A MANNER THAT ASSURES A REASONABLE PRICE OR THAT THE BEST OFFERORS ARE AWARDED CONTRACTS. SACWSD ALSO APPROVED UNNECESSARY CHANGE ORDERS. • EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: THE REGIONAL OFFICE PREPARED A MANAGEMENT DECISION 1.ETrER ON 12/20/90. ON 1/23/91, A DEViATION REQUEST WAS SENT TO EPNHQ FOR REVIEW. IT WAS APPROVED ON 6/3/91. A PROPOSED FINAL DETERMINATION WAS SENT TO THE OIG ON 10/3/91 AND SHOULD BE ISSUED DURING THE FIRST QUARTER FY 1992. - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: THE FIRST QUARTER FY 1992. 16 FOLLOWUP STATUS AS OF 9/30/91: 141 REGIONAL ADMINISTRATOR, REGION 10 P5CHN9 10-0151-0300095 OREGON DEQ OR 9/27/90 Summary: - EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: THE PROJECT OFFICER SENT A RESPONSE TO THE OIG ON 2/14/91. OIG ASKED FOR ADDITIONAL INFORMATION ON 3/18/91. PROGRAM OFFiCE IS PREPARING THE FINAL DETERMINATION LETTER. - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: AUDIT SHOULD BE CLOSED BY THE END OF THE FIRST QUAATER FY 1992. IG FOLLOWUP STATUS AS OF 9/30191: (11 E2AWPO -1O-00174400012 ELBE WATER DIST EARLY WARN WA 3/30/90 Summary: THE ELSE WATER & SEWER DIST PROPOSED TO CONSTRUCT A $2.2 MILLION MODIFICATION OR REPLACEMENT TO SERVE 39 HOUSES (ABOUT $60,000 PER HOUSE). HOWEVER, THE PROJECT WAS NEITHER COST EFFECTIVE NOR DID IT QUALIFY AS A MODIFICATION OR REPLACEMENT PROJECT. • EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: A TECHNICAL REVIEW TO DETERMINE IF THE ISSUES RAISED IN THE AUDIT WERE CAUSED BY A FAILURE IN DESIGN IS STILL IN PROCESS. THE REGION’S WATER DIVISION AND THE OIG ARE WORKING TO GET THE REVIEW COMPLETED. - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: FINAL DETERMINATION IS EXPECTED BY THE END OF NOVEMBER 1991. IG FOIIOWtJP STATUS AS OF 9/30/91: Ii ) P5CG8-10-0076-1100146 WASHINGTON DEPT OF ECOLOGY WA 3/20/91 Summary: COSTS QUESTIONED FOR IMPROPER PROCUREMENT, PERSONNEL SERVICES AND INDIRECT COSTS. - EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: AUDIT HAS BEEN SENT TO THE GRANTEE AND THE PROJECT OFFICER FOR COMMENT. - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: THE FINAL DETERMINATION LETTER IS EXPECTED TO BE ISSUED BY THE END OF THE FIRST QUARTER F? 1992. IG FOLLOWUP STATUS AS OF 9(30 /91: (ii P5CG*8.10.0084 1100156 ALASKA DEPT OF ENV CONSER AK 3/29/91 Summary: COSTS QUESTIONED AS INEUGIBLE FOR SUBCONTRACTOR SERVICES NOT PERFORMED, EXCESS PROFIT AND ENGINEERING SERVICES PERFORMED ON SITES OUTSIDE THE SCOPE OF THE COOPERATIVE AGREEMENT. • EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: DUE TO TURNOVER OF KEY PERSONNEL FINAL ACTION HAS BEEN DELAYED. - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: THE FINAL DETERMINATION LETTER IS ANTICIPATED BY THE END OF THE FIRST QUARTER F? 1992. 16 FOILOWUP STATUS AS OF 9/30(91: (11 P5CHN9-10-0155-1300047 WASHINGTON DEPT OF ECOLOGY WA 3/26/91 Summary: • EXPLANATION OF THE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: THIS AUDIT HAS BEEN SENT TO THE PROJECT OFFICER AND TO THE GRANTEE. THE ISSUANCE OF THE FINAL DETERMINATION LETTER WAS DELAYED BY THE LOSS OF KEY PERSONNEL IT IS EXPECTED TO BE ISSUED BY 11/30/91. - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: FINAL DETERMINATION LETTER IS EXPECTED TO BE ISSUED BY 11/30/91. IG FOLLOWIJP STATUS AS OF 9(30/91: (11 April 1,1991 through September 30, 1991 65 ------- Co fill. A I Repo E3BGI-10-0066-8100761 MOSES LAKE IAR & REHAB DIST WA 8(31/88 Sumniwy INTERIM AUDIT OF DEMONSTRATION GRANT TO RESTORE MOSES LAKE AND TO CONTROL NON-POINT POLLUTION SOURCES FOUND TOTAL COSTS QUESTIONED CF $2,439,103 (F.S. $1,205,039). GRANTEE USED STANDARD METHOLOGY INSTEAD OF DEVELOPING NEW INNOVATIVE TECHNIQUES. - EXPLANATiON OF ThE REASONS MANAGEMENT DECISION HAS NOT BEEN MADE: ThIS AUDIT IS CURRENTLY BEING CONSIDERED BY ThE AUDIT RESOLUTION BOARD. - DESIRED TIMETABLE FOR ACHIEVING A MANAGEMENT DECISION: IG FOILOWUP STATUS AS OF 9/3 91: (6J TOTAL AUDITS ISSUED BEFORE REPORTING PERIOD FOR WHICH NO MANAGEMENT DECISION WAS MADE DURING THE REPORTING PERIOD: 65 - Agency procedixes do nd requwe the IGs apixoval on Agencys Management Decision on an auc t (other than a preaward an internal and management i ) with the Federal share o( queedoned coats nt less than $100,000. Theretore, we have not provided a summary ot the aude. Office of the Inspector General Report to the Congress ------- Mailing Address and Telephone Numbers • OlG HOTLINE (800) 424-4000 or (202) 260-4977 Headquarters Office of Inspector General 401 M Street, S.W. (A109) Washington, DC 20460 (FTS or 202) 260-3137 Atlanta Office of Inspector General 1375 Peachtree Street, NE Suite 276 Atlanta, GA 30309 Audit (404)347-3623 FTS 257-3623 Investigations: (404) 347-2398 FTS 257-2398 Boston Office of Inspector General JFK Federal Building OIG 521 Boston, MA 02203 Audit (617) 565-3160 FTS 835-3160 lnvestigations:(61 7) 565-3928 FTS 565-3928 Chicago Office of Inspector General 77 West Jackson Boulevard 13th Floor Chicago, IL 60604 Audit (FTS or 312) 353-2486 Investigations: (FTS or 312) 353-2507 Dallas Office of Inspector General 1445 Ross Avenue, Suite 1200 Dallas, Texas 75202-2733 AUdit (214) 655-6621 FTS 255-6621 Investigations: (214) 655-6610 FTS 255-6610 Denver Office of Inspector General 999 18th Street, Suite 500 Denver, CO 80205-2405 Audit (303) 294-7520 FTS 330-7520 Investigations: (303) 293-1650 FTS 330-1650 Kansas City Office of Inspector General 726 Minnesota Avenue Kansas City, KS 66101 Audit (913) 551-7824 FTS 276-7824 New York Office of Inspector General 90 Church Street, Room 802 NewYork,NY 10007 Audit (FFS or 212) 264-5730 Investigations: (FTS or 212) 264-0399 Philadelphia Office of Inspector General 841 Chestnut Street 13th Floor Philadelphia, PA 19107 Audit (FTS or 215) 597-0497 Investigations: (FTS or 215) 597-9421 Research Triangle Park, NC Office of Inspector General EPA Administration Building Alexander Drive, Room 113 Research Triangle Park, NC 27711 Audit (919) 541-1028 FTS 629-1028 Investigations: (919) 541-1027 FTS 629-1027 Sacramento Office of Inspector General 8011 Street, Room 466 Sacramento, CA 95814 Audit (916) 551-1076 FTS 460-1076 San Francisco Office of Inspector General 75 Hawthorne St (1-4) 19th Floor San Francisco, CA 94105 Audit (415) 744-2445 FTS 484-2445 Investigations: (415) 744-2465 FTS 484-2465 Seattle Office of Inspector General 1111 3rd Avenue, Suite 350 Seattle, WA 98101 Investigations: (206) 442-1273 FTS 399-1273 ------- IGNORING FRAUD WON’T MAKE IT ABUSE AWAY! REPORT IT TO THE INSPECTOR GENERAL HOTLINE • INFORMATION IS CONFIDENTIAL 800-424-4000 or 202-260-4977 WASTE OR JJ;.I GO U.S. ENVIRONMENTAL PROTECTiON AGENCY • OFFICE OF ThE INSPECTOR GENERAL • 401 N STREET S.W. WASHINGTON, D.C. 20460 0 ------- |