TECHNICAL ASSISTANCE TO WATERVILLE/WINSLOW, MAINE IN RESOURCE RECOVERY PROCUREMENT PLANNING FINAL REPORT Work Assignment No. 8 Contract No. 68-01-4940 Prepared for: U.SC EnvitoYiaental Protection Agency Region I John Fo Kennedy Building Boston, Massachusetts 02203 by: G011DIAN ASSOCIATES INCORPORATED 1919 Pennsylvania Avenue, N.W. Suite 405 Washington,, J>CC. 20006 (202) 828-7300 and SCS Engineers 11800 Sunrise VeJ.ley Drive Restcn, Virginia 22091 November 19, 1980 Gordian Associates Incorporated ------- Public Law 94—580 — October 21, 1976 RESOURCE RECOVERY AND CONSERVATION PANELS SEC. 2003. The Administrator shall provide teams of personnel, including Federal, State, and local employees or contractors (herein- after referred to as “Resource Conservation and Recovery Panels”) to provide Federal, State and local governments upon request with technical assistance on solid waste management, resource recovery, and resource conservation. Such teams shall include technical, marketing, financial, and institutional specialists, and the services of such teams shall be provided without charge to States or local governments. This report has been reviewed by the Region I EPA Technical Assistance Project Officer, and approved for publication. Approval does not signify that the contents necessarily reflect the views and policies of the Environmental Protection Agency, nor does men— tion of trade names or co=ercial products constitute endorsement or recommendation for use. EPA Region I Project Manager: Susan Santos Gordian Associates Incorporated ------- ACKNOWLEDGEMENTS This report has been prepared by Bill Ranney and Dick Richards of Gordian Associates and by Mike McLaughlin and Tom Conrad of SCS En- gineers. We would like to acknowledge the valuable assistance provided by the EPA project manager, Susan Santos, Elery Keene and the staff of the North Kennebec Regional Planning Commission, representatives of Keyes Fibre, and the other people who gave their time and energy to this project. Gordian Associates Incorporated ------- TABLE OF CONTENTS I • INTRODUCTION . . • . . . . . . . . . . . . . . . S • 1 II. PRELIMINARY STEAM PURCHASE AGREEMENT . . . . . . . . . . III. RISKS AND STRATEGIES . . . . . . . . . . . . . . . . . • . S • S • • • S S • S S S • S • S S S S • . S S • • • IV. ECONOMIC ANALYSIS. . . . . . . . . • . . . . . . . . . • 5 26 26 30 32 33 35 Explanation of Systems and Assumptions Capital Costs. . . . • . . . . . . . . OperatLng Costs. . . . . . . . . . . . SensltLvlty Analyses . . . . . . . S S S S S S S S S S • S S S • S S • S S S S S S S S • S S • S • S S S S V. STRATEGIES FOR SYSTEM PROCUREMENT. . . . . . . . . . 54 Financing. . . . • . . . . . . . . Procurement. . . . . • . . . . . . Recoended Procurement Approach • . S S S S . S S S . S • S S S VI. CONCLUSIONS. . . . . . . . . . . . . . . . . . . . . . . 88 APPENDIX 1: APPENDIX 2: APPENDIX 3: APPENDIX 4: Waterville—Winslow Interlocal Solid Waste Agree- ment and Waterville—Winslow Joint Solid Waste Disposal Facility Corporation Certificate of Organization of a Corporation and By—Laws Major Resource Recovery Risk Areas and General Examples Price Support Loans for Municipal Waste Energy Projects 90 124 133 Preliminary Evaluations for Three Potential Sites 139 The Pricing Formula. • . . . . . . . . . The Contract Term. . . . . . . . . . • . . Operation, Steam Quality and Steam Quantity. Other Comments . . . . . . . . . . . . . 35 40 40 48 56 65 79 Gordiari Associates Incorporated ------- 1 I. INTRODUCTION Anticipating that the landfill would soon reach capacity, the City of Waterville and the Town of Winslow began investigating solid waste disposal alternatives available to them. In 1977, Edward C. Jordan Co., Inc. was retained to evaluate these regional solid waste manage- ment alternatives and its recoimnendation was that energy recovery by means of a starved—air modular combustion system be pursued. To assist them in the procurement of such a system, Waterville/Winslow contacted U.S. EPA Region I to request assistance under the Technical Assistance Panels Program. After meeting with local elected and appointed affiliates from the Waterville/Winelow area on February 20, 1980, EPA Region I and Gordian jointly determined that continued support through the Panels Program was justified. A scope of work consisting of the following tasks was developed: Task 1 — Market Analysis . The contractor shall interview management and staff level personnel associated with the identified market to determine technical and contractual specifications in sufficient detail to support the economic analysis in Task 2. The information will be used by the Waterville/Winslow Corporation (W/W Corp.) in preparing a final contract with the market and for use in any procurement documents. The contractor shall prepare a sample contract between the W/W Corp. and and the market which shall contain all provisions typically found in community—market agreements. The W/W Corp. will be responsible for finalizing and negotiating the contract with the irket. The contractor shall advise the W/W Corp. as to the pros and cons of positions taken on key contractual points. The contractor shall prepare a working paper describing the information prepared and the sample contract. Task 2 — Economic Analysis . The contractor shall perform a detailed analysis of the costs for a modular combustion unit facility with energy recovery at a size to be decided on by the Gordian Associates Incorporated ------- 2 WIW Corp. and the maximum amount of energy the market can use. Information from Task 1 shall be used to determine energy revenues. The contractor shall break Out all distinguishable costs for capital and operating. The contractor shall state all assumptions made in developing the costs and the reasoning for their use. Financing Costs and reserve funds shall also be included in the cost estimate. The contractor shall prepare a working paper presenting the system costs and the assumptions made. Task 3 — Develop Strategy for Procurement . The contractor shall analyze institutional issues relevant to the procurement of a resource recovery facility and appropriate for the by—laws and philosophy established by the W/W Corp. The contractor shall evaluate alternative procurement strategies and develop the most apropriate approach based on risk, institutional, and financial issues. The contractor shall map out the steps in the procurement process and include a cost estimate and schedule for a typical procurement using the above appropriate approach. The cost estimate shall include estimate for engineering, management, legal and financial consultants. The contractor shall meet with the W/W Corp. to present the results of this and previous tasks. The contractor shall prepare handout materials to be used for discussion purposes. Task 4 — Final Report . After receiving coiiments from the W/W Corp., North Kennebec RPC, State of Maine—DEP, and EPA Region I, the contractor shall finalize the working papers from the previous tasks and the presentation of Task 3 into a comprehensive summary report. It was decided to have Gordian’s subcontractor, SCS Engineers, perform Task 1 through its office in Augusta, Maine while the remaining tasks were to be performed by Gordian. Gordiari Associates Incorporated ------- 3 Several of the tasks had to be expanded to address the comments resulting from the presentation of the draft report. The new work focuses on the following issues: • revision of the steam agreement; • discussion of the specific risks associated with the project and possible negotiating strategies for the Corporation; • alteration of the economic—analysis to consider seven day per week operation at the original tonnage level and at a higher tonnage; • expansion of the sensitivity analysis to cover the potential use of wood chips as a fuel by Keyes Fibre; • evaluation of potential siting considerations at both Keyes and the Mid Maine Medical Center; • examination of the Btu content assumptions for the refuse and the potential need for sophisticated air pollution control equipment. • discussion of the viability of the Mid Maine Medical Center as an alternative energy market. With the exception of the last task, these issues are addressed in this report. A preliminary investigation of the Thayer Unit of the Medical Center by SCS Engineerings provided conflicting estimates of the steam demand, ranging from 3000 lb/hr to 15,000 lb/hr. It is generally agreed that demand is lower in the suer, which is when refuse generation is at its peak. By most estimates the steam demand would not be sufficient to use all the steam generated by a modular incinerator facility. The Medical Center has promised to provide detailed and accurate information on their energy requirements. Cogeneration of steam and electricity is a possibility to match steam production and consumption. Electrical power would serve the refuse—steam plant and the excess sold to Mid—Maine as well. However, based upon the relatively small quantity of electricity which would be generated, it is unlikely that even cogeneration would render the Mid—Maine alternative feasible. Gordian Associates Incorporated ------- 4 A more intensive investigation of the Medical Center is beyond the scope of this study. Based on the available information, every effort should be made to finalize an agreement with Keyes Fibre for the sale of steam. However, if these negotiations drag on, it may be worthwhile to look more closely at the Medical Center or other potential market. It should be stressed that significant delays will force people to find other energy sources and the present markets will disappear. Gordian Associates Incorporated ------- 5 II • PRELIMINARY STEAM PURCHASE AGREEMENT As subcontractor to Gordian Associates, SCS Engineers has developed a preliminary steam purchase agreement which would control the sale of steam by the Waterville—Winslow non—profit corporation to Keyes Fibre Co. The draft contract incorporates information gained through nt erous conversations with representatives of Keyes, including one face—to—face meeting held at Keyes in May 1980. Consequently, SCS feels that this agreement accurately reflects the conditions which Keyes will agree to at this preliminary point in time. However, it should be noted that the specific provisions which both parties may insist upon will undoubtedly change somewhat in the course of final negotiations. This document provides a comprehensive framework for opening discussions. In structure and wording, this agreement resembles the steam contract employed in Auburn, Maine, but there are some important differences reflecting the specific situations of the parties involved. Gordian Associates Incorporated ------- 6 STEAN PURCHASE AGREEMENT This Agreement is made this _________ day of _________, 19_, by and between the Waterville—Winslow Joint Solid Waste Disposal Facility Corporation, a quasi—municipal corporation organized un- der the laws of Maine (hereinafter referred to as “Corporation”) and Keyes Fibre, An Arcata Company (hereinafter referred to as “Keyes”) WITNES SETH Whereas, the Corporation is in the process of constructing a waste disposal system capable of disposing by incineration typical municipal waste (residential, commercial and industrial), and Whereas, the system to be constructed will be capable of sup- plying certain steam energy requirements for Keyes’ manufacturing facilities located near, Waterville, Maine; and Whereas, the Corporation has expressed an interest in selling and Keyes has expressed an interest in purchasing from the Corpor- ation, all steam produced by the refuse—steam plant up to Keyes’ steam requirements at its existing and future manufacturing fa- cilities located at College Avenue, Waterville, Maine; Gordian Associates Incorporated ------- 7 Now therefore, in consideration of the mutual convenants and conditions hereinafter set forth, and intending to be legally bound, Corporation and Keyes agree as follows: Section 1. Definitions . As used in this Agreement: 1.1 Steam . The word “steam” shall mean steam energy meet- ing the quality requirements specified in Paragraph 3.2 of this Agreement. 1.2 Pound of Steam . The words “pound of steam” shall mean steam weighing one pound at saturated conditions at a pressure base of 125 psig. 1.3 The term “psig” shall mean pounds per square inch gauge. 1.4 Refuse—Steam Plant . The words “refuse—steam plant” shall mean the facilities to be constructed and operated by the City pursuant to Section 2 of this Agreement. 1.5 Point of Connnection . The words “point of connection” shall mean a single interface between the Corporation’s steam pip- ing and condensate return make—up water system and Keyes’ steam piping and condensate return system, which interface shall be lo- cated at a point on Keyes’ property line nearest the energy con- version equipment and shown in Exhibit A attached hereto. 1.6 Boiler Efficiency . The words “boiler efficiency” shall mean the percentage of gross BTU input that is realized as useful BTU output; E = BTU output/BTU input. Gordian Associates Incorporated ------- 8 Section 2. Site and System Construction 2.1 Location of Plant . The Corporation will locate the refuse—steam plant adjacent to the existing Keyes manufacturing facility in Waterville, Maine as indicated on the plan attached to this Agreement as Exhibit A, and as more particularly bounded and described on Exhibit B to this Agreement (the “site”). Keyes will lease the site to the Corporation in accordance with the terms set forth in Exhibit C attached hereto. 2.2 Construction of Plant . • A. The Corporation agrees at its sole cost and ex- pense to purchase, construct, install, operate and maintain build- ings, waste disposal equipment, energy conversion equipment and associated facilities necessary to produce steam through incinera- tion of combustible waste, and to deliver such steam to the point of connection. B. Keyes will receive and transport steam from the point of connection into its manufacturing facility for use by Keyes. Keyes will furnish a steam line and condensate line prop- erly supported and insulated as required for transportation of steam and condensate from the point of connection to Keyes’ manu— facturi.ng facilities and return. Transmission losses between the steam generation equipment and the point of connection shall be borne by the Corporation; transmission losses between the point of connection and Keyes’ plant shall be borne by Keyes. Ownership of the Keyes—furnished steam and condensate lines shall remain Gordian Associates Incorporated ------- 9 with Keyes even after termination of this Agreement and regardless whether such lines are connected to the Corporation’s facilities. C. The Corporation may enter into contracts or sub— contracts with third parties or with Keyes for the construction and operation of the refuse—steam plant. If contracts or subcon— tracts are entered into with third parties, Keyes will continue to look to the Corporation for performance of the Corporation’s obli- gations pursuant to this Agreement, and the Corporation will guar- antee performance of this Agreement by such contractors or subcon- tractors. 2.3 Measurement of Steam and Condensate . A. The Corporation agrees to provide and maintain at its expense a recording steam flow meter which makes a continuous record of steam pressure and temperature. B. Keyes may install, maintain and operate at its own expense such check measuring equipment as it shall desire, provid- ed that such equipment shall be so installed so as not to inter- fere with the Corporation’s measuring equipment. The accuracy of Keyes’ cheek measuring equipment shall be verified by Keyes at reasonable intervals and, if so requested, in the presence of rep- resentatives of the Corporation. C. The accuracy of the Corporation’s measuring equip- ment shall be verified by the Corporation at reasonable intervals, and if so requested, in the presence of representatives of Keyes, but the Corporation shall not be required to verify the accuracy of such equipment more frequently than once in any thirty (30) day period. Keyes may at any time notify the Corporation that Keyes Gordiari Associates Incorporated ------- 10 desires that the Corporation undertake a special test of any mea- suring equipment. The expense of any such special test, if re- quested, shall be borne by Keyes if the measuring equipment tested is found to be in error by not more than two percent (2%), either fast or slow. Following such test, previous recordings of such equipment shall be considered accurate in computing deliveries of steam; but such equipment shall be adjusted at once to record ac- curately. If upon test, any measuring equipment shall be found to be inaccurate by an amount exceeding two percent (2%), either fast or slow, then the expense of such test shall be borne by the Cor- poration and any previous recordings of such equipment shall be corrected to a zero error for any period which is known definite- ly; but in case the period is not known or agreed upon, such cor- rection shall be for a period extending over one—half of the time elapsed since the date of last test. D. In the event a meter is out of service or is known to be registering inaccurately, the volume of steam delivered shall be determined as follows: (1) by using the registration of any check meter or meters, if installed and accurately registering, or in the absence of such check meters, (2) by correcting the error if the percentage of error is ascertainable by calibration, tests or mathe- matical calculation, or, if both Subparagraphs (1) and (2) are inapplicable, then, Gordian Associates Incorporated ------- 1.3. (3) by estimating on the basis of deliveries dur- ing period. under similar conditions when the meter was registering accurately. If the meters are located on Keyes’ property, Keyes will provide access to the Corporation at any time. Keyes may inspect the steam meter charts and condensate meter charts at any time upon reasonable notice to the Corporation, and will be entitled to have its representative present and observe the steam and/or condensate meter each month at the time the flows are read for billing pur- poses. 2.4 Due Diligence in Construction of the Plant . The Cor- poration will complete the purchase, construction, and installa- tion of the refuse—steam plant and place the same in operation with due diligence. Section 3. Terms of General Agreement, Purchase and Sale 3.1 Terms of Agreement . A. Keyes agrees to purchase from the Corporation all steam generated by the Corporation at its refuse—steam plant up to Keyes’ maximum low—pressure steam requirements at its Waterville, Maine, manufacturing facility. The steam so generated by the Cor- poration and delivered to the point of connection will be for the use of Keyes, and, so long as Keyes remains in business at its Wa— terville, Maine facility, may not be resold by Keyes without the express prior written consent of the Corporation. Gordiari Associates Incorporated ------- 12 B. Subject to the provisions of Sections 7 and 10, the term of this Agreement shall be ten (10) years, commencing on the date of the Corporation’s first delivery of steam to Keyes 1 with an automatic renewal period of ten (10) years upon the terms contained herein. 3.2 Quantity and Quality of Steam . The Corporation will make available to Keyes at the point of connection in accordance with the operating schedule set forth in Paragraph 5.1, at least 11,000 pounds per hour average of low—pressure saturated steam at 125 psig minimum. Subject to the provisions of Section 5.3, deli- very shall be, as a minimum, a total of 264,000 pounds of steam iithin each 24—hour period. 3.3 Keyes Boilers to Supplement Corporation Steam . Keyes will have the right to maintain, replace, enlarge and continuously operate at its plant its own boiler system to produce that portion of Keyes’ steam requirements which the Corporation does not pro- duce through the refuse—steam plant, and Keyes shalt have no obli- gation to pay the Corporation for the use of such Keyes—produced steam. 3.4 Excess Steam or Other Energy . In the event that the Corporation acquires the capacity to generate steam in excess of Keyes’ maximum low—pressure steam requirements or to generate electricity or other forms of energy at the refuse—steam plant, the Corporation shall have the right to sell such steam, electri- city or other forms of energy to third parties. Gordian Associates Incorporated ------- 13 Section 4. Payment Rates and Terms 4.1 Computation of Steam Rates . Steam will be sold by the Corporation to Keyes on the basis of a commodity charge only for each thousand pounds (“M ib”) of steam delivered to Keyes. The rate to be paid for such steam by Keyes to the Corporation will be adjusted quarterly. Keyes will provide the Corporation a State- ment of Rate Computation ‘which contains the following information, on or before the last working day of January, April, July, and Oc- tober each year: (1) average unit price for fuel consumed by Keyes to produce steam of a comparable type and function as that sup- plied by the Corporation during preceding calendar quarter ending March 31, June 30, September 30 and December 31 ($/unit). (2) description and average heating value of fuel con- sumed by Keyes to produce steam of a comparable type and function as that supplied by the Corporation during preceding calendar quarter (BUTa/unit). (3) Keyes’ boiler efficiency, computed in accordance with American Society of Mechanical Engineers Power Test Code. (4) Keyes’ thermal conversion constant, to equal ener- gy which must be added to Keyes’ average 125 psig steam con- densate return to produce steam of a comparable type and function as that supplied by the Corporation (BTUs/l,000 lbs ste am) Gorthan Associates Incorporated ------- 14 Upon request of the Corporation, Keyes shall substantiate the information provided. The Corporation shall use the most recent Statement for Rate Computation to determine the price to be paid for steam delivered during each billing period. The intent of the parties with respect to rate computation is to reflects Keyes’ costs for producing comparable steam, less the value of services rendered by Keyes (such as supplying make—up water and condensate return). The price to be paid for such steam by Keyes to the Corpora- tion will be computed as follows: (P x C) R K ______ (H x E) where R — commodity rate of payment for steam ($/1,000 lbs steam) P — average unit price of fuel consumed by Keyes during preceding calendar quarter ($/unit) C thermal conversion constant (BTUs/1,000 lbs steam) H = average heating value of fuel consumed by Keyes during preceding calendar quarter (BTUs/unit) E = Keyes’ boiler efficiency, computed in accordance with American Society of Mechanical Engineers Power Test Code K — discount value, computed as follows: Steam Quantity 1st and 2nd yr. Subsequent Delivered years Preceding Quarter (N ib) 0 — 45,900 0.900 0.950 more than 45,900 0.882 0.931 Gordian Associates Incorporated ------- 15 4.2 Billing Procedure . Except as provided in Paragraph 5.3 in connection with interruption of service, Keyes agrees to pay the Corporation for a minimum of 91,800,000 pounds of steam each year during the term of this Agreement, or for such lesser amount which the Corporation may deliver in accordance with Paragraph 3.2. The minimum annual charge shall be prorated in the event that initial deliveries and final deliveries occur on dates other than the first and last days of a calendar year, as the number of days of actual deliveries bears to the total number of days in such year. On or before the 15th day of each month following de- livery of steam, the Corporation shall bill Keyes for steam deli- vered to it during the preceding month. Any balance due the Cor— .poration as a result of Keyes’ failure to utilize the guaranteed minimum quantities (i.e., 91,800,000 pounds per year before prora- tion) will be billed annually. 4.3 Payment of Bill . All bills will be due from Keyes to the Corporation upon receipt. A service charge of 2 percent (2%) per month may be added to any balance outstanding thirty (30) days after invoice date. The Corporation may discontinue steam service for nonpayment of its bill upon not less than thirty (30) days written notice to Keyes. Suspension under this paragraph shall not affect the minimum purchase amount to be paid under Paragraph 4.2 above. Section 5. Operation of the Heat Recovery System 5.1 Minimum Weekly Operating Schedule . The Corporation agrees to operate the steam generation system at least five Gordian Associates Incorporated ------- 16 24—hour periods per week, 51 weeks per year. In addition, the Corporation further agrees to consider, without liability, operat- ing the system for additional periods of time, if suitable combus- tible waste is available to the Corporation and Keyes has a need for the steam produced. 5.2 Water Supply and Treatment . Keyes agrees to supply at its expense all make—up water which may be required by the refuse— steam plant in addition to condensate return for boiler use. All boiler feed water will be properly deaerated and chemically treat- ed so as to provide a non—corrosive, non—scaling steam. .5.3 Notice Requirements for Steam Service Interruption . he Corporation will make reasonable effort to give Keyes notice by the quickest means possible of any unplanned interruption of the steam supply and to give reasonable advance notice of all planned interruptions of the steam supply. The Corporation will make reasonable efforts to coordinate any planned, interruption of steam supply with Keyes so as to enable Keyes to take’appropriate protective measures. In the event of any such interruption of service resulting in supply of steam by the Corporation of the quality and quantity specified in Paragraph 3.2 on less than 255 days per year, the annual minimum payment required of Keyes under Paragraph 4.2 will be reduced by a fraction, the numerator of which shall be 255 less the actual number of operating days on which steam of the quality and quantity specified in Paragraph 3.2 is supplied, and the denominator of which shall be 255. No ha— bihity shall attach to the Corporation or its agents, servants, delegates, or other representatives for failure to deliver steam. Gordian Associates Incorporated ------- 17 5.4 Steam Plant Inspection . In the event that Keyes de- sires to obtain additional business interruption insurance for its manufacturing facilities, the Corporation agrees, upon reasonable notice from Keyes, to permit an initial inspection of its refuse— steam plant by representatives of the insurance company. The Cor- poration will not be liable to undertake any action which may be reco=ended as a consequence of said insurance company’s inspec- tion. 5.5 Steam Plant Operation and Maintenance . The Corporation will operate or cause to be operated the refuse—steam plant in a manner consistent with good plant management practice. Without limiting the generality of the foregoing, the Corporation will: A. Provide preventative maintenance, institute proper operating procedures, make all required repairs and replacements, and take other precautions to prevent interruptions and provide reliability of the steam supply. B. Operate the refuse—steam plant in compliance with all applicable local, state and Federal laws and regulations, and regularly remove and dispose of ash and any other waste products in accordance with all such laws and regulations. C. Store solid waste materials in a properly designed silo, building or pit while awaiting incineration. D. Maintain the buildings and land site consistently with good industrially zoned real property management practice, which shall include landscaping the site to make it attractive and compatible with Keyes’ property as a well—maintained industrial property. Gordian Associates Incorporated ------- 18 5.6 Responsibility . Nothing herein contained shall create or imply a relationship of principal and agent, or employer and employee, or any relationship other than independent seller and purchaser, as between the parties. Responsibility for complying with all regulatory and permit requirements of the refuse—steam operation shall be solely that of the Corporation. Section 6. Termination 6.1 Termination with Cause . Keyes may terminate this Agreement without any further liability under this Agreement: A. by giving written notice to the Corporation on or before ________________, in the event that the refuse—steam plant is not constructed; or B. by giving written notice to the Corporation on or before ________________, in the event that by ________________, the refuse—steam plant has not generated steam meeting the quantity and quality requirements of Paragraph 3.2 for at least five (5) consecutive business days. 6.2 Termination without Cause . Keyes may unilaterally ter- minate this Agreement upon not less than ninety (90) calendar days’ prior written notice to the Corporation. In the event of such termination, Keyes liability shall be as follows: (1) For the balance of the term of this Agreement, or any renewal thereof, Keyes shall compensate the Corporation for 91,800,000 pounds of steam per year, with price based Gordian Associates Incorporated ------- 19 upon the latest commodity rate billed to Keyes by the Corpor- ation before termination. In the event Keyes terminates without cause prior to the first bill having been issued by the Corporation, the coodity rate shall be $3/1,000 lbs. The price under this paragraph shall increase by 8 percent (8%) per year for the balance of the term of this Agreement, or any renewal thereof. (2) In the event that at any time following termina- tion of this Agreement, the Corporation commences the deli- very or distribution from the refuse—steam plant of steam ag- gregating 15,000 lbs or more per hour to one or more recipi- ents, then Keyes’ liability under this Paragraph 6.2 shall unconditionally terminate. Section 7. Amendments to Agreement This Agreement and its Exhibits supersede all prior negotia- tions and oral understandings, if any, and may not be amended or supplemented except in writing signed by both parties. Section 8. Notices Notices required under Paragraph 5.3 will be given to and by the respective local operating personnel of the Corporation and Keyes. Notices other than those required under Paragraph 5.3 will Gordian Associates Incorporated ------- 20 be deemed properly given when in writing Bent by certified mail, postage prepaid and addressed: if to Corporation if to Keyes Keyes Fibre Manager, Manufacturing Eastern Division College Avenue Waterville, Maine 04901; or to such other person as the respective parties may from time to time designate in a written notice to the other. Section 9. Renewal Upon the expiration of the initial ten (10) year term, this Agreement shall be automatically renewed upon the terms contained herein unless either party gives notice as provided below. The term of said renewal shall be ten (10) years. If either party wishes to renegotiate the Agreement terms, or if either party wishes to terminate this Agreement without a renewal, then the party shall give notice of its desire to renegotiate or terminate to the other party at least one (1) year prior to the expiration of the initial ten (10) year term. Upon receipt of such notice, the parties will negotiate in good faith to reach agreemen t on the terms and conditions of the renewal agreement, if any. Gordian Associates Incorporated ------- 21 Section 10. Force Majeure 10.1 Liability . Except as otherwise provided in this Agree- ment, neither party nor its agents and employees shall be liable in damages to the other party for any act, omission or circum- stance occasioned by or in consequence of any acts of God, strikes, lockouts, acts of the public enemy, wars, blockades, in- surrections, riots, epidemics, landslides, lightning, earthquakes, fires, storms, floods, washouts, arrests and restraints of rulers and peoples, civil, disturbances, explosions, breakage or accident to machinery or lines of pipe, the binding order of any court or overnmental authority which has been resisted in good faith by all reasonable legal means, and any other similar cause not rea- sonably within the control of the party claiming suspension and which by the exercise of due diligence such party is unable to prevent or overcome. 10.2 Suspension of Obligations . All obligations pursuant to this Agreement (other than the obligation to pay sums then ac- crued, due and payable) of the party claiming suspension pursuant to Paragraph 10.1 shall be suspended until the cause for such sus- pension has been removed, and both Keyes and the Corporation agree to use due diligence to remove or overcome the cause for such sus- pension. Gordian Associates Incorporated ------- 22 Section 11. Interpretation The paragraph captions are for convenience only and shall not affect the interpretation of this Agreement. This Agreement shall be construed and enforced in accordance with the laws of the State of Maine. Section 12. Assignment This Agreement may not be assigned by either party without the prior written consent of the other party; provided, however, .that Arcata may, without the consent of the Corporation, consoli- date with or merge into another corporation or permit one or more other corporations to consolidate with or merge into it, or trans- fer all or substantially all its assets to another corporation and thereafter dissolve, or sell, or transfer the Waterville, Maine fa- cilities to another corporation, and may, in connection with any such consolidation, merger, sale or transfer assign this Agreement to the surviving, resulting or transferee corporation without the consent of the Corporation, but only on the following conditions: A. that such surviving, successor or transferee corporation is a corporation organized and existing under the laws of the State of Maine or is duly qualified to do business in that State; B. that in connection with any such merger or consolidation in which Axcata is not the corporation resulting from or surviving Gordian Associates Incorporated ------- 23 such merger, the corporation resulting from or surviving such mer- ger shall (1) expressly assume and agree to perform all of Keyes’ obligations under this Agreement and (ii) shall file with the Cor- poration a letter by a firm of nationally known certified public accountants stating that after consummation of such consolidation or merger the corporation resulting from or surviving such merge will have an excess of consolidated assets over consolidated lia- bilities of at least $20,000,000; and C. that in connection with any such sale or transfer, the corporation to which such transfer is made shall (i) expressly as- sume and agree to perform all Keyes’ obligations under this Agree— inent and (ii) shall file with the Corporation a letter by a firm of nationally known certified public accountants stating that af- ter consun ation of such transfer the corporation to which such transfer is made has an excess of consolidated assets over con- solidated liabilities of at least $20,000,000. Section 13. Authority 13.1 Corporation’s Authority . The Corporation represents and warrants to Keyes that this Agreement and the transactions contemplated by this Agreement have been duly authorized by the Board of Directors of the Corporation and that no further action or authorization is necessary to make this Agreement a binding commitment of the Corporation. Gordian Associates Incorporated ------- 24 13.2 Keyes’ Authority . Keyes represents and warrants to the Corporation that this Agreement and the transactions contemplated by this Agreement have been duly authorized by the Board of Direc- tor of the Arcata Company, Inc. and that no further action or au- thorization is necessary to make this Agreement a binding commit- ment of Keyes. IN WITNESS WHEREOF, the parties hereto have caused this in— str ent to be signed and sealed by their duly authorized officers on the date first written above. WITNESS: WATERVILLE-WINSLOW JOINT SOLID WASTE DISPOSAL FACILITY CORPORATION: ________________________ By ( seal ) Name and title: _____________________ WITNESS: ARCATA COMPANY _______ By _______________ (seal) Name and title: — Gordian Associates Incorporated ------- 25 EXHIBITS Exhibit “A” — a preliminary master plan of the refuse—steam facil- ity, including potential expansion Exhibit “B” — a metes and bounds description of the ground lease site, including the right of way beneath railroad tracks Exhibit “C” — a ground lease for the site, containing provisions typical of ground leases 1) 20 year term 2) nominalrent 3) payment of taxes 4) ownership of fixtures 5) approval of improvements 6) reference to and approval of master plan 7) reference to metes and bounds description 8) right of way 9) utility easements Gordian Associates Incorporated ------- 26 III. RISKS AND STRATEGIES A number of comments were received concerning the Steam Pur- chase Agreement as originally proposed. Most have been incorpor- ated in the final version appearing in Section II. This section discusses specific risks associated with alternative positions on key contractural provisions, as well as negotiating strategies for each. Finally, a discussion of comments not incorported is provided. TRE PRICING FORNTJLA Most of the comments received on the draft Steam Purchase Agreement dealt with the proposed pricing mechanism. Basically, the formula involves computing Keyes actual cost for the genera- tion of its own steam, and applying a discount factor for steam purchased from the Corporation. Discount factors vary depending upon the quantity of steam consumed by Keyes (a 2 percent (2Z) volume discount is given for an average consumption of more than 30,000 lbs/hour) and the age of the refuse—steam plant. A larger discount is given Keyes during the first and second years of the Agreement to defray Keyes’ expense incurred to install steam sup- ply/condensate return piping to the point of connection. All of the figures used in Paragraph 4.1 of the Agreement are arbitrary, and are shown for illustration purposes only. The principal advantage of the pricing mechanism is its sim- plicity. In relatively straightforward fashion, the formula provides a realistic measure of steam value under changing condi- tions. As a profit—making corporation, Keyes is free to select the most economical fuel alternative for use in its boilers. The price for refuse—steam will always be lower than Keyes actual cost to generate its own steam. From the Waterville—Winslow stand— Gordian Associates Incorporated ------- 27 point, adjusting the formula on a quarterly basis based upon cur- rent energy cost will help assure that refuse—steam plant income does not decrease in real terms. The risks inherent in this approach are of net benefit to WatervilleWins low. Looking over the mid—term future (10—20 years) it is unlikely that energy costs for manufacturers such as Keyes will be reduced significantly. Although the formula shown puts the risks of lowered energy costs on Waterville—Winslow, the risk is comparatively remote. Some hard thinking will be necessary to determine the precise discount factors to be used in the pricing formula. Keyes only true saving will be in terms of fuel used; overhead, labor and ad- ministrative expenses will be unaffected by a refuse—steam meeting a small part of its steam requirements. Keyes savings in fuel costs (and perhaps boiler equipment depreciation) must be balanced against those services Keyes will provide the refuse—steam plant, including supply of make—up and boiler feedwater, nominal ground lease rent, and the supply/condensate return lines. Before suggesting a strategy for negotiating discount fac- tors, it would be helpful to review the price formula again: (P x C) RK _____ (H x E) where H commodity rate of payment for steam ($/1,000 lbs steam) P average unit price of fuel consumed by Keyes during preceding calendar quarter ($/unit) Gordian Associates Incorporated ------- 28 C — thermal conversion constant (BTUs/l,000 lbs steam) H — average heating value of fuel consumed by Keyes during preceding calendar quarter (BTU8/unit) E — Keyes’ boiler efficiency (dimensionless) K discount factor (dimensionless) For example, if during the preceding quarter Keyes used fuel oil to generate its low pressure steam, the computation might look like this: • average unit price — $26 per barrel • average heating value: 9.2 million BTU/barre]. • boiler efficiency 82 percent (82%) • thermal conversion contant assumes steam of 1,193,000 BTU/ 1,000 lbs and condensate return of 289,000 BTU/l,000 lbs): 904,000 BTU/l,000 lbs. Substituting, (26 x 904,000 R K __________ (9,200,000 x 0.82) R K ($3.11) If K, the discount factor, were 0.90, Keyes would pay Water— yule—Winslow $2.80 per 1,000 lbs steam. The first step in the negotiation process should be to esti- mate the value of the services rendered to Waterville—Wina low by Gordian Associates Incorporated ------- 29 Keyes. These services include (1) nominal ground rent, (2) boiler make—up water, and (3) some length of steam supply and condensate return lines. After these numbers have been estimated, the magni- tude of reduced maintenance and capital depreciation to Keyes should be estimated. Keyes’ inclination will naturally be to overstate the value of the ground lease, make—up water, and steam/condensate lines. Waterville—Winslow’s goal should be to equate ground lease and make—up water with reduced maintenance and reduce capital depreci- ation. A nominal discount (say 5 percent (5%)) should therefore be sufficient to serve as Keyes’ incentive. The final question would then be to determine any additional discount required to jnake the steam/condensate lines economically viable for Keyes. If necessary, Waterville—Winslow might even suggest its willingness to install the steam/condensate lines at its expense (with a cor- responding decrease in the discount given Keyes). A major financial consideration is the guaranteed minimum quantity of steam to be purchased by Keyes under Paragraph 4.2. The figure given (91,800,000 lbs steam/year) assumes the minimum operating schedule of Paragraph 5.1 (24 hours day, 5 days/week, 51 weeks/year) and a steam quantity of 15,000 lbs/hour at 125 psig. Keyes will pay for at least this minimum quantity, as adjusted by interuptions in service (Paragraph 5.3). The minimum given com- pares with the 94,248,000 lbs steam/year which would be delivered assuming a 24 hours/day, 7 days/week, 51 weeks/year and steam quantity of 11,000 lbs/hour at 125 psig. A guaranteed minimum quantity of steam to be purchased assures some stability of revenue over the term of the Agreement. A disadvantage to the minimum quantity language proposed is that an early termination by Keyes could result in a long—term, low cash price of the steam to be purchased. Language adding an 8 percent (8%) per year escala- tion has therefore been included. Gordian Associates Incorporated ------- 30 Other financial considerations shown by the sample Agreement include the actual billing mechanism and service charge for late payment. The language used is typical, but need not take precise- ly this form for the Steam Purchase Agreement. THE CONTRACT TERM A long—term commitment on the part of the purchaser to buy refuse—steam is an acknowledged requirement of every Steam Pur- chase Agreement. The difficulty in the present case is what con- stitutes “long—term”. Keyes has expressed resistance to any con- tract term longer than 10 years, with a 10 year renewal. Economic viability of the project probably requires a 15—20 year term. The sample contract establishes a 10 year initial term. As several coimnenters noted, amortization of Waterville— Winslow’s capital investment over a 10—year term will be diff 1— cult. In fact, a 10—year term may present an insurmountable ob- stacle to construction of the refuse—steam plant. Keyes should be advised of this fact at an early point in negotiations with two goals in mind. First, Keyes may agree to lengthen the contract term. More likely, however, is that Keyes will concede somewhat in negotiating other contract terms (for example the pricing dis- count factors) because Waterville—Winslow has “given up the store” on the critical question of contract length. As previously noted, amortizing the refuse—steam equipment over a 10 year period will be difficult. If Keyes is not willing to lengthen the term, perhaps it can otherwise assume some of this capital burden. Keyes may, of course, be making capital improve- ments in contemplation of receiving refuse—steam (e.g. steam sup- ply and condensate return lines). Keyes expressed tentative dis- approval of assuming a greater capital investment role in the pro- ject directly, but there may be other alternatives. One such al— Gordian Associates Incorporated ------- 31 ternative would be for Keyes to purchase revenue or general obli- gation bonds used to finance the refuse—steam plant. Other ar- rangements, such as limited suretyship, should be explored with Keyes to determine their acceptability. Given that the sample contract has only a 10—year basic term, there is nevertheless language included which provides for simple renewal for a similar 10 year period. The renewal is not certain, however. The renegotiation provisions can work to the benefit of either party; the refuse—steam will probably change in value to Keyes or to Waterville—Winslow or both after 10 years of opera- tion. The renegotiation feature makes it likely that the Agree- ment terms will be adjusted accordingly. A 20 year ground lease term has been suggested for Exhibit “C”. Such a provision would permit Waterville—Winslow to continue to incinerate solid waste for that period and seek other potential markets. Grounds for termination are clearly set Out jfl Paragraph 6.1. Keyes may terminate without liability should the refuse—steam fail to achieve satisfactory operation on or before a date certain. Keyes may unilaterally terminate the Agreement upon 90 days no- tice, but will remain liable for the guaranteed minimum quantity of steam as required under Paragraph 4.2 and 6.2. Keyes liability would end upon resumption of steam delivery to a third party. A question related to that of termination is a successor—in— interest to Keyes Fibre or Arcata Company. Waterville—Winslow’s concern in this regard is that Keyes’ obligations under the Agree- ment are assumed. The sample contract forbids assignment without the permission of Waterville—Winslow, unless assignment is made to a responsible firm which expressly assumes Keyes’ obligations un- der the Agreement. The Agreement is thought to give Waterville—Winslow suffi- cient protection from premature termination in all circumstances Gordian Associates Incorporated ------- 32 except bankruptcy. A bonding provision could be sought to provide even greater protection; the cost to Keyes of procurring such a bond would be reflected in the discount factor used to determine refuse—steam price. OPERATION, STEAM QUALITY AND STEAM QUANTITY Operations and interruptions to operations are often major points of contention during negotiation of Steam Purchase Agree- ments. In the present case, Keyes will be unable to reduce labor, overhead or administrative expenses of its own boiler operation because the refuse—steam plant will meet only a small portion of .Keyes low pressure steam needs. Since Keyes will maintain full steam generation capability on a full time basis, assurance of a constant steam supply from the refuse—steam plant is not as criti- cal to Keyes as might otherwise be the case. The Steam Purchase Agreement provides that the refuse—steam plant shall operate at least five 24—hour periods each week, 51 weeks per year. The language used is very flexible, and would allow the system to make up for working day interruptions by oper- ating on weekends. The language would also permit expansion to a 7—day—a—week operating schedule should sufficient combustible waste be available and should Keyes have a need for such addition- al steam. No liability would be imposed on Waterville—Winslow for fail- ure to maintain the minim*nn operating schedule; however, the mini— mum annual payment by Keyes will be adjusted if steam delivery is made on fewer than 255 days a year. Interruptions in Keyes’ ability to use refuse—steam will not result in an adjustment to the minimum annual payment, unless such interruptions are beyond the control of Keyes. Instead, the Gordian Associates Incorporated ------- 33 Agreement will stand suspended until the cause of the interruption has been removed. OTHER COMMENTS Some coimnents received were not incorporated in the “final” version of the Steam Purchase Agreement. The following discussion is intended to respond to the more significant of the coents not incorporated. Acceptable Waste Waterville—Winslow should probably not seek to limit the kinds of wastes to be burned at the site. Incineration of some kinds of hazardous wastes may prove to be economically attractive at some future date. In any case, there is no reason to unneces- sarily limit combustible -waste alternatives; any hazardous wastes disposed would be disposed of in accordance with applicable laws and regulations (Sections 5.5 and 5.6). Pricing Formula Several suggestions were made as to specific factors which should be included or changed within the formula. The earlier discussion of the pricing formula clarified most of these points; in spite of its apparent complexity, the formula is technically straightforward. Keyes will provide new values for all the varia- bles on a quarterly basis. Unit price and heat content for fuels will depend on the fuels used; boiler efficiency will depend on the fuel used and the capital equipment installed; and the thermal conversion constant will depend on the nature of condensate return and technology utilized. All of these values can change, depend- ing on the steam—generating technology which Keyes elects to in— Gordian Associates Incorporated ------- 34 stall. It would be inappropriate to establish constant values for any of these. One cominenter suggested including a capital investment factor in the formula. Such a change would be difficult to quantify, be- cause Keyes will not purchase any less capital equipment with the refuse—steam plant than without. Keyes capital investment will reflect the amount necessary to generate 100 percent (1002) of its steam requirements independent of the refuse—steam plant. A fac- tor which could be included is the capital depreciation and main- tenance factor, since Keyes will presumably operate its equipment less if the refuse—steam plant meets part of Keyes steam demand. Rather than include this factor in the formula, Waterville— Winslow should seek to equate this factor with the make—up water and nominal rent factors in determining Keyes’ discount. Guaranteed Minimum Payment The Steam Purchase Agreement requires Keyes to purchase a minimum quantity of steam, but is silent as to a minimum price. Technology changes at Keyes could affect annual revenues dramati- cally, as is shown in the economic analysis section of this re- port. With this in mind, several commenters suggested including a floor price for steam delivered. Such a floor price should be sought in negotiation, but realistically speaking, there is almost no chance Keyes would accept any floor price high enough to make a difference. The only value in seeking such a floor price is in concessions elsewhere during negotiations. Gordian Associates Incorporated ------- 35 IV. ECONOMIC ANALYSIS This section presents a brief but detailed discussion of the projected economics involved with building and operating a resource recovery system such as is being considered in Waterville/Winslow. The discussion is presented in four subsections: First, the system frameworks and basic assumptions required for the analysis are set forth; second, the capital costs are shown; third, the operating costs are projected; and finally, several sensitivity analyses are developed. In each of these subsections, material is presented in tabular or graphic form whenever possible in an effort to provide easy reference and to clarify the potentially confusing information. It is important to bear in mind that this data should still be considered preliminary at this point. The information is detailed and based upon reasonable assumptions. Nevertheless there are certain variables which cannot be determined with complete accuracy until final contracts are signed. Perhaps the most speculative element of a preliminary analysis of this kind is the projected revenues from sale of recovered energy. As noted in the previous section, the proposed steam contract provides for a great deal of uncertainty in that area. Cordian has attempted to present a feel for the range of uncertainty in the sensitivity analyses subsection. The point is that the numbers developed here are as realistic as is possible at this preliminary juncture but that a reasonable margin of variance should still be anticipated when final system bids are received from equipment vendors. If the Corporation proceeds to implement the system within the time frame assumed here, then this economic analysis should provide a reliable tool for decision making. EXPLANATION OF SYSTEMS AND ASSUMPTIONS The economic discussion presented in this section applies to several variations of the same basic system design. That design is based upon the following assumptions: Gordian Associates Incorporated ------- 36 • Technical Process: Modular incineration (based on Consumat type technology)* using the following combinations of combustion/boiler units: OPTION A: 4 units @ 25 TPD with 2 boilers OPTION 8: 3 units @ 25 TPD with 3 boilers OPTION C: 3 units @ 50 TPD with 2 boilers These units are assumed to operate continuously 24 hours a day, 7 days a week. The seven day/week operating schedule requires that these options contain a certain amount of spare capacity. Systems which operate five days per week can make up for downtime by running on weekends. However, with a continously operating facility this is not possible. Therefore, these alternative systems are sized to keep one unit in reserve to allow for continued operation during scheduled maintenance as well as during unscheduled downtime. Also, the addition of an extra incinerator increases the reliability of the system and allows the facility the option of accepting additional waste. This would be an especially advantageous arrangement if, in the future, the quantity of refuse from the member communities increases. All systems are assumed to be equipped with baghouse type air pollution control (APC) devices. This is the same technology implemented at the Auburn facility. The use of baghouses will assure compliance with Maine’s air pollution regulations. • Waste Quantities: Table 4.1 shows the waste tonnage assumptions that were included in the calculations for each system. These tonnages were derived from the December 1977 E.C. Jordan Study and the Waterville landfill survey conducted in June 1980. More reliance was placed on the * The use of Consumat’ s design is meant to be representative of modular incinerator systems and is not an endorsement of any particular system or manufacturer. Gordian Associates Incorporated ------- TABLE 4.1 Waste Processing Data for Alternative Systems 1 — Based on 90% system availability 2 — Accounts for possible system downtime when onsite waste storage is infeasible and for a one-week period when Keyes Fibre has no steam demand. 3 — 40% of the processed waste by weight plus unprocessed waste SYSTEM DESIGN CAPACITY (TPD) YEARLY SYSTEM DESIGN 1 CAPACITY (TPY) Y Days of Operation E A R I Available Waste (TPD) 1980 otal Waste Per Year rotal Waste Proce 9 ed/ Year Residue Disposal 3 Per Year A 100.8 $33,113 7 days/wk. operation 63 for 42 weeks 70 fr. summe 23,380 22,211 10,053 B 75.6 24,835 7 days/vk. operation 52 for 42 weeks 59 fr.summer 19,470 18,302 8,489 C 147.6 48,487 7 days/wk. operation 88 for 42 weeks 98 fr.summer 32,730 31,094 14,074 -J ------- 38 latter data since it is so current and was obtained directly through sampling. That survey indicated that during the week of sampling Waterville/Winslow generated 345.6 tone of landfillable waste plus 212 tons of waste that was not landfilled. Since the sampling took place in early June it is difficult to estimate how much of the non—landfillable waste would be generated annually. Gordian reviewed the composition of the non—landfillable waste sample and determined that the proceseible (i.e. combustible in a modular incinerator) portion of these wastes would amount to approximately 2,360 tons annually with most of this waste accumulated over ten weeks during the ser. This figure, coupled with the 17,113 tons of landfillable waste that the survey projected annually, totals to approximately 19,470 tons per year for Waterville/Winslow alone. As shown in Table 4.1, that quantity was applied to the calculations for System B. System B therefore represents a minimum sized facility with capacity for the wastes from Waterville and Winslow only. System A is sized to include the waste streams from the towns of Clinton—Benton and Fairfield in addition to Waterfield/Winslow. The waste quantities for these communities were taken from the estimates presented in the E.C. Jordan report. However, those quantities have been adjusted downward by 9% to account for reduced amounts of glass caused by the introduction of the “bottle bill.” The resulting annual total waste tonnage is 23,380 as shown in Table 4.1. The tonnage estimate shown for System C in Table 4.1 is based on the assumption that additional waste will be available to maintain operation at close to 100 TPD on a seven day/week basis • In view of the approximate nature of these waste estimates and in the absence of reliable populat-ion projections, the waste quantities developed here were assumed to be constant throughout the 20 year life span used in the economic analyses. Gordian Associates Incorporated ------- 39 • System Operation: The following assumptions were employed to calculate system operating costs. Since the economics are projected over the life of the systems, various escalation rates were aes ed as indicated. Baseline data were developed for 1983 as the initial year of system operation. Whenever possible, costs were based on actual figures quoted by Keyes. MSW heating value (HHV): 4,500 Btu/lb* Incinerator/boiler efficiency: 60% Steam generation: 5,800 lb steam/ton of MSW 125 PSIG SAT and condensate return of 300°F In plant energy usage: Electricity — at 5$/kwh for 1980 escalated @ 9% annually 25 kwh/ton of waste processed Air pollution equipment O6M — 10% of initial APC capital cost in 1983 escalated at 10%/year Auxiliary fuel — $3.75/MMBtu in 1980 escalated @ 12% 250,000 Stu/ton processed waste Rolling stock: $.99/gal (diesel) in 1980 escalated at 12%, 0.3 gallons/ton waste input Maintenance, parts and supplies: $1.75/ton processed waste Residue characteristics: weight: 40% of incoming plant waste (includes water) water: 35% of total residue weight Equipment replacement: 1% of base capital (for Last 15 years) * This figure is based upon national averages of municipal refuse. In the judgment of Gordian Associates it represents a safe and reliable estimate. To arrive at a more exact figure the communities should undertake an analysis of their refuse to determine its actual Btu content. Gordian Associates Incorporated ------- 40 Insurance: @ 0.5% of base capital Downtime assumptions: one week for Keyes downtime Energy prices for revenue calculations — No. 6 Fuel Oil (high sulfur): $38/Bbl in 1983 escalated at 12% year Wood chips: $20/ton delivered in 1980 4500 Btu/lb for wood chips Discount factor: 302 Other escalation factors: Labor — @ 8% Materials — @ 10% Maintenance — @ 102 Residue Disposal — @ 10% CAPITAL COSTS Estimated capital costs for each of the three systems are presented in Table 4.2. These costs are based on a start—construction date of August 1981. The data used was derived from conversations with numerous system vendors and review of cost information for similar existing or planned facilities. OPERATING COSTS Tables 4.3, 4.4, and 4.5 present annual operating budgets for each system for 1983, 1993, and 2003 respectively. The system life span is here considered to be 20 years, although the fact that potential investors might be reluctant to purchase bonds for more than a 15 year period is recognized in the Debt Service line item. Thus, in Table 4.5 (2003) the Debt Service is zero although the Equipment Replacement line item is increased significantly to account for accelerated machinery breakdown. Labor costs are developed from the detailed labor requirements for each system presented in Tables 4.6 through 4.8. The Outside Services line item includes such necessary costs as telephones, periodic vector control, laundry, janitorial, and other miscellaneous professional and upkeep services. Residue Disposal is assumed to be handled by contract rather than by in—house equipment. The baseline costs used for this item are Gordian Associates Incorporated ------- t . System TABLE 4.2 CAPITAL COSTS Potential Modular Incinerator System Waterville /Wins low Installed Capacity 1. Land 4xZ5TPD 2 Boilers 0 3x25TPD 3 Boilers 0 3 SOTPD 2 Boilers 0 2. General construction (a) Site Preparation (b) Incinerator Facility $ 130,000 650,000 $ 110,000 540,000 $ 150,000 840,000 3. Refuse Processing (a) Incinerator Modules (b) Air Pollution Control Cc) Piping (stea m and condensate return) 2,000,000 360,000 60,000 1,600,000 340,000 50,000 2,300,000 390,000 60,000 4. Other Equipment (a) Weigh Scale (b) Front—end Loader (c) Fuel tank (d) Spare Parts, Tools, etc. PROJECT SUBTOTAL 5. Relief Factors (a) Omissions & Contingency (10%) (b) Escalate to 8/81 (10%) PROJECT SUBTOTAL $3,290,000 329,000 329,000 $3,948,000 $2,730,000 273, 000 273, 000 $3,276,000 $3,830,000 383,000 383,000 $4,596,000 6. Fees and Construction Costs (a) Engineering and Con- struction Mgmt (10%) (b) Organization, Mgmt, Legal (52) (c) Finance costs and interest during const.(lO%) (d) Start—up Costs(3%) TOTAL CAPITAL COSTS A B C 50,000 50,000 50,000 20,000 20,000 20,000 10,000 10,000 10,000 10,000 10,000 10,000 395,000 328,000 460,000 198,000 164,000 230,000 395,000 328,000 460,000 118,000 98,000 138,000 $5,054,000 $4,194,000 $5,884,000 Gordian Associates Incorporated ------- 42 TABLE 4.3 ANNUAL COSTS (1983 DOLLARS) Modular Incineration System Options Waterville /Winslow 4x25TPD 2 Boilers lOO.8TPD 3x25TPD 3 Boilers 75.6TPD 3x5OTPD 2 Boilers 147. 6TPD 1. Debt Service (15 years @ 7%) 2. Labor 3. Air pollution equipment O&M 4. Utilities (a) Electricity* (b) Fuel (c) Water/sewer $ 555,000 451,000 36,000 34,000 37,000 13,000 $ 460,000 395,000 34,000 28,000 30,000 13,000 $ 646,000 480,000 39,000 47,000 51,000 13,000 5. Maintenance, parts and supplies 6. Outside Services 7. Equipment Replacement 8. Insurance 9. Disposal of Residue Contract Hauling TOTAL COST Energy Revenues Net Cost Net Cost Per Ton $1,299,000 686,000 $ 613.000 $ 27.60 $1,105,000 566,000 $ 539,000 $ 29.45 $1,493,000 891,000 $ 602,000 $ 19.36 * Does not include electricity for APC devices System Installed Capacity Daily Tonnage Capacity A B C 49,000 41,000 69,000 15,000 15,000 15,000 51,000 42,000 59,000 27,000 21,000 30,000 31,000 26,000 44,000 Gordian Associates Incorporated ------- 43 TABLE 4.4 ANNUAL COSTS (1993 DOLLARS) Modular Incinerator System Options Watervi lle/ Winslow 4x25TPD 2 Boilers 100.8TPD 3x25TPD 3 Boilers 75. 6TPD 3x5OTPD 2 Boilers 147.6TPD 1. Debt Service (15 years @ 7%) 2. Labor 3. Air pollution equipment O&M 4. Utilities (a) Electricity (b) Fuel (c) Water/Sewer 5. Maintenance, parts and supplies 6. Outside Services 7. Equipment Replacement 8. Insurance 9. Disposal of Residue Contract Hauling TOTAL COST Energy Revenues Net Cost Net Cost Per Ton $ 555,000 974,000 93,000 80,000 115,000 34,000 127,000 32,000 132,000 27,000 80,000 $2,249,000 2,131,000 $ 118,000 $ 5.31 $ 460,000 853,000 88,000 66,000 93,000 34,000 106,000 32,000 109,000 21,000 67,000 $1,929,000 1,758,000 $ 171,000 $ 9.34 $ 646,000 1,036.000 101,000 111,000 158,000 34,000 179,000 32,000 153,000 30,000 114,000 $2,594,000 2,767,000 —$ 173,000 —$ 5.56 System Installed Capacity Daily Tonnage Capacity A B C Gordian Associates Incorporated ------- 44 TABLE 4.5 ANNUAL COSTS (2003 DOLLARS) Modular Incinerator System Options Waterville/Wins low System A B C Installed Capacity 4x25TPD 3x25TPD 3x5OTPD 2 Boilers 3 Boilers 2 Boilers Daily Tonnage Capacity l O O.8TPD 75.6TPD l47.6TPD 1. Debt Service* (15 years @ 7%) 0 0 0 2. Labor $2,103,000 $1,842,000 $2,237,000 3. Air pollution equipment O&M 241,000 228,000 262,000 4. Utilities (a) Electricity 189,000 156,000 263,000 (b) Fuel 357,000 289,000 314,000 (c) Water/Sewer 88,000 88,000 88,000 5. Maintenance, parts and supplies 329,000 275,000 464,000 6. Outside Services 69,000 69,000 69,000 7. Equipment Replacement 555,000 460,000 646,000 8. Insurance 27,000 21,000 30,000 9. Disposal of Residue Contract Hauling 208,000 174,000 296,000 TOTAL COST $4,166,000 $3,602,000 $4,669,000 Energy Revenues $6,619,000 $5,460,000 $8,594,000 Net Cost —$2,453,000 —$1,858,000 —$3,925,000 Net Cost Per Ton —$ 110.44 —$ 101.52 —$ 126.23 * Debt is retired after 15 years. For the remainder of the project life equipment replacement costs are increased to assure continuous facility operation. Gordian Associates Incorporated ------- 45 TABLE 4.6 LABOR COST ESTIMATES 100 TPD Modular System —— 4 Units (Candidate System A) Job Title No. of Workers Pay Rate Annual Cost Plant Manager 1 $25,000/yr $ 25,000 Weigh Clerk/Clerical 1 $5.00/hr 10,400 Shift Foreman 4 $11.00/hr 91,520 Front—end Loader Operator 5 $9.00/hr 93,600 Mechanic, Maintenance 1 $8.00/hr 16,640 Laborer 2 $7.00/hr 29,120 SUBTOTAL 14 $266,280 Forced Overtime 10% 26,600 Fringe Benefits 30% 78,900 TOTAL ESTIMATED ANNUAL PAYROLL $371,780 Gordian Associates Incorporated ------- 46 TABLE 4.7 LABOR COST ESTIMATES - 75TPD Modular System — 3 Units (Candidate System B) Job Title No. of Workers Pay Rate Annual Cost Plant Manager 1 $25,000/yr $ 25,000 Weigh Clerk/Clerical 1 $5.00/hr 10,400 Shift Foreman 4 $11.00/hr 91,520 Front—end Loader Operator 4 $9.00/hr 74,880 Mechanic, Maintenance 1 $8.00/hr 16,640 Laborer 1 $7.00/hr 14,560 SUBTOTAL 12 $233,000 Forced Overtime 10% 23,300 Fringe Benefits @ 30% 69,900 TOTAL ESTIMATED ANNUAL PAYROLL $326,200 Gordian Associates Incorporated ------- 47 TABLE 4.8 LABOR COST ESTIMATES 15OTPD Modular System — 3 Units (Candidate System C) Job Title No. of Workers Pay Rate Annual Cost Plant Manager 1 $25,000/yr $25,000 Weigh Clerk/Clerical 1 $5.00/hr $10,400 Shift Foreman 4 $11.00/hr $91,520 Front—end Loader Operator 5 $9.00/hr $93,600 Mechanic, Maintenance 2 $8.00/hr $33,280 Laborer 2 $7.00/hr $29,120 SUBTOTAL 15 $282,920 Forced Overtime 10% 28,292 Fringe Benefits 30% 84,876 TOTAL ESTIMATED ANNUAL PAYROLL $396,088 Gordian Associates Incorporated ------- 48 derived from conversations with the Central Maine Disposal Company which identified a 1980 cost of $45 per 18 ton truckload. Energy revenues for all systems are based on oil as Keyes’ alternative fuel, escalated at 12% and discounted 302. This yields a 1983 baseline steam price of $5.33/1,000 lbs. Net cost per ton figures are based on total waste processed (see Table 4.1) for each system. SENSITIVITY ANALYSES Because of the inherent uncertainty involved with projecting into the future and the relatively large number of unresolved elements related to this project, Gordian has developed a series of curves to show the sensitivity of net system* costs to changes in several of the more sigzi ificant variables. The first analysis, shown in Figure 4.1, develops the effects of varying the length of the bonding period from 10 to 15 years. This variance is important because investors may not be willing to purchase bonds for periods longer than 10 years if the steam purchase agreement with Keyes is only for an initial 10 year commitment. Even if Keyes would agree to commit to a longer than 15 year steam contract it is unlikely that investors would purchase bonds with longer than 15 year paybacks given the relatively unproven track records of modular incinerators. The different bond payback periods would affect the debt service and net system costs as shown in Figure 4.1. Initially, there is approximately a $7/ton difference between the two scenarios, which jumps to $24/ton when the 10 year bond is repaid. Between 1993 and 1998 the 10 year bond option is less expensive because there is no debt service. However, after 1998 the debts for both alternatives are paid, so the savings are equal. The advantages of the 10 year debt are that the bond issue may be easier to sell and that between 1993 and 1998 it will produce a greater saving. However, during the early years of the project the 15 year debt option is less expensive. Since the project is likely to experience high front end costs, the 15 year debt service option is probably more attractive. * All sensitivity curves in this subsection are based on system option A as described earlier. Gordian Associates Incorporated ------- 49 FIGURE 41 SENSITIVITY ANALYSIS ON DEBT SERVICE LENGTH 1 — (baseline case) 15 year debt service with 7% intereat rate and given assumptions 2 — 10 year debt service with 7% interest rate and given assumptions $27.60 $35.03 I 1 2 1 2 1 2 $5.31 [ 1 $19.67 1983 1993 2003 Key: $110.44 $110.44 Cost Tipping Fee ($/ton MSW) Profit Gordian Associates Incorporated ------- 50 The second Ben8itiVity analysis presented here involves the effect upon steam revenues of varying energy price escalation rates which directly affect net system costs. In Figure 4.2, the net per ton costs of System A over 20 years are compared for energy prices escalated at 9%, 12% and 15%. Recall that a 12% escalation rate was used for the baseline system costs presented earlier. Additionally, the effect of ending revenues completely as a result of Keyes’ failing to renew its steam contract is dramatically demonstrated. From this graphic representation, it can be seen that even if energy prices escalate at only 9% the net system costs will decline after ten years. The 12% scenario, which currently looks very reasonable for oil related revenues, begins to realize a profit per ton around 1995. Note that if profits begin to climb too rapidly, Keyes would probably demand some form of revenue sharing or additional steam price discount, so the net profits shown for later years are probably unrealistic. Bear in mind also that the costs/profits shown are not in constant dollars, consequently dollars in the future are worth considerably less than current dollars. Nevertheless, profits and/or lowered costs remain relative. The final sensitivity curve (Figure 4.3) is similar to Figure 4.2 except that in this scenario, Keyes converts to a wood fired system which considerably reduces steam revenues. As noted earlier, in conversations with Keyes, they expressed a desire to implement a wood fired system as soon as possible. This system would consist of one or two 60,000 lb/hr boilers burning wood chips. The wood chips would be burned as is (roughly 50 — 60% moisture). These boilers operate at efficiencies of 65 — 70%, and the two boiler system would cost $3,600,000 to $4,000,000 to install. Gordian assumes that Keyes could not implement such a system prior to 1985, therefore the wood based revenues do not coence until that year. Wood chip prices are currently far below oil prices. The current price is approximately $20/ton delivered. The revenues are based on a 30% discount of this price. While it would be attractive for the Corporation to receive credit for a portion of Keyes’ capital investment, Keyes is unlikely to agree to this, as discussed in Section 3. Gordian Associates Incorporated ------- 1983 1993 2003 Key: FIGUR.E 4.2 SENSITIVITY ANALYSIS ON OIL BASED ENERGY REVENUES 1 2 3 4 1 2 3 4 1 2 3 4 1 — 9% escalation of energy revenues, steam sales agreement not renewed after 10 years, and given assumptions 2 — 9% annual escalation of revenues, steam agreement extended for 20 years, and given assumptions 3 — (baseline case) 12% annual escalation of revenues, renewed agreement, and given assumptions 4 — 15% annual escalation of revenues, renewed agreement, and given assumptions $29.62 $29.62 $27.60 $25.48 $32.96 $5.31 $32.24 $25.89 Cost Tipping Fee ($/ton 14 5W) Profit Gordian Associates Incorporated ------- 52 FIGURE 4.3 SENSITIVITY ANALYSIS ON WOOD BASED ENERGY REVENUES 1983 1 _____ 2 ______ 3 _____ 4 _____ 1993 1 ____________ 2 _________ 3 ______ 4 2003 1 — 9% annual escalation of steam revenues, aeam sales agreement not renewed after 10 years, and given assumptions 2 — 9% annual escalation of revenues, steam agreement extended for 20 years, and given assumptions 3 — 12% annual escalation of revenues, renewed agreement, and given assumptions 4 — 15% annual escalation of rev’dnues, renewed agreement and given assumptions $41.24 _____ $41.24 _____ $40.07 ____ $38.81 ____ I $101.26 1560.42 $44.08 I $21.66 L $187.56 I $90.90 $10.00 I S134.48 I Cost Key: •• Profit Tipping Fee (S/ton MSW) Gordiari Associates Incorporated ------- 53 The effects of a switch to wood could actually cause net system costs to increase if wood chip prices only escalate at 92. At a 12% rate system costs hold relatively steady until the debt service ends at which time costs decline. Gordian Associates Incorporated ------- 54 V • STRATEGIES FOR SYSTEM PROCUREMENT The Waterville—Winslow Joint Solid Waste Disposal Facility Corporation (hereafter referred to as the Corporation) has several critical steps to complete before a resource recovery system can be constructed. Among these steps are: • negotiation of waste supply contracts; • negotiation of steam sale contract with Keyes Fiber Co. or another market; • selection of procurement approach; • selection of financing approach; and • the sale of bonds. This chapter will discuss the issues that must be addressed in completing these steps and will outline alternative implementation strategies for Waterville—Winslow. First, the Corporation must gain control of the quantity of waste for which the facility is to be designed through the negotiation of waste supply contracts with surrounding communities. The economic evaluation in Chapter III will assist the Corporation in developing a price structure for tipping fees (user charges) to be assessed these communities for using the proposed facility. A steam contract with the Keyes Fiber Corporation must be negoti- ated and signed before design or construction begins. In Chapter II, Gordian has discussed the terms of the steam agreement being considered by the Corporation and Keyes Fiber Company and recommendations are made for adjustments along with possible negotiating strategies. The Corporation must also select procurement and financing ap- proaches consistent with its goals as stated in the “Waterville—Winslow Interlocal Solid Waste Agreement and Waterville—Winslow Joint Disposal Facility Corporation Certificate of Organization of a Corporation and By—Laws.” This document is included in Appendix 1. There is an element of risk involved in any resource recovery pro- ject and a general discussion of this issue is included in Section 3 and in Appendix 2. It is important, when considering the procurement strategy for a resource recovery project, to allocate the risks among Gordian Associates Incorporated ------- 55 the project participants in a fair and equitable manner. Those en- tities that accept these risks should also share the benefits that result from the project. The project proposed by Waterville—Winslow has two major areas of risk associated with the contracts for waste supply and the energy market. These risks have been discussed in previous Sections and will not be addressed further here, except to emphasize that the Corporation must be aware of them and the contracts negotiated (and the project management framework adopted) must take into account these and other risks. Gordian Associates Incorporated ------- 56 FINANCING Resource recovery aye tern development involves many complex de- cisions regarding appropriate financing mechanisms. One of the biggest problems in financing capital intensive resource recovery systems is that resource recovery systems cannot yet be generally sold as “of f—the— shelf” facilities; they involve certain risks. Thus, regardless of the financing mechanism(s), investor concerns associated with the risks must be minimized. The major concerns in the financial community center on whether the municipal and private sectors can be brought together in workable contracts; whether the processes selected are technically feas- ible and reliable and the participating parties in the project under- stand the risks and have divided the risks according to which ones they are best able to manage; whether the waste stream(s) intended for the projeTct(s) can be committed and controlled over a Long term period; and whether there are reliable long term markets for recovered products, particularly energy, since bondholders tend to dieregard the reliability of other product markets. Obviously, there are other concerns such as credit backing and in- surance, contractor expertise in design, construction and operation, emergency alternatives for waste disposal, and adequate “coverage” ratios in the project revenue structure. While there are several public and private financing arrangements available for resource recovery system development, most projects being developed today involve some combination of the two and the application, at least in—part, of tax—exempt debt instruments. Straight private equity financing of a total project is unlikely. A private company expects a return on its investment which is consistent with the risks (and at least equal to the return) from a similar investment of capital. Too, most companies want to keep the financing of resource recovery projects “off—the—balance—sheet” since the debt would be too large for them to absorb. Most resource recovery projects could not withstand the profit payout required from a total private financing nor could most private companies secure the amount of funds needed for a large scale facility. Gordian Associates Incorporated ------- 57 Private equity can, however, be successfully combined with public financing (i.e., revenue bonds) in the development of such projects. Such financing still involves risks but it can reduce total project capital costs since the private investor(s) may be able to take advan- tage of the Federal tax benefits such as accelerated depreciation, in- vestment tax credits, and interest deductions. These benefits can afford substantial cash flow advantages to the private sector partici- pant(s) in the early years of the project and such savings can be passed on to the participating municipalities in the form of lower tipping fees. It is important to briefly examine the relative benefits of public ownership and operation versus private ownership and operation when dis- cussing financing alternatives. Most advocates of public ownership and operation point to the lower costs of capital and the retention of muni- cipal control over the facility. Too, the profit factor is obviated and the public body retains ownership after the debt is paid back. Public bodies may also believe they have greater leverage to negotiate with the proposed energy customer(s) in their jurisdictions. On the other hand; private industry may be better equipped to oper- ate and manage a technically complex facility and market the products successfully. It also has the profit motive as an incentive for eff 1— cient operation and can usually offer higher salaries to attract the necessary skills to operate the facilities. While the cost of capital to a private developer may be higher than for a public entity, a properly structured financing could afford the private firm Federal tax benefits — otherwise lost to a public body — that could enhance the overall eco- nomics of a project. Regardless of the financing arrangements, a private system company that would design and/or build a plant should have a major stake, if not through ownership and/or operation, at least through strong performance guarantees to the owner/operator. The choice of public versus private facility ownership should be made by the local public officials based on local conditions and objectives. The following review of financing alternatives is provided as a guide to the current status of financing for resource recovery projects. Gordian Associates Incorporated ------- 58 Although some of the more intricate financing approaches, such as lever- aged leasing, are perhaps more appropriate where large—scale facilities are concerned, Waterville—Winslow should be aware of the full—range of financing alternatives available before final decision financing is made. • Public Financing Local governments typically purchase equipment and facilities from current revenues or borrowings. It is common to find municipalities financing solid waste collection equipment, landfills and landfill equip- ment, and certain other facilities through current revenues (i.e., “pay as you go”). For more capital intensive projects, municipalities must often obtain bank loans, lease the facilities or else pursue long—term financing alternatives involving issuance of bonds. The bonds may in- clude general obligation issues or municipal revenue bonds, and they are usually exempt from Federal income tax, which makes them attractive to investors. Section 103(a) of the Internal Revenue Code of 1954 provides that gross income does not include interest on obligations of a state or political subdivision of a state. This same tax exempt treatment is extended to interest on industrial development bonds used to finance solid waste disposal facilities under section 103(b) of the code. Pollu— tion control revenue bonds, which are issued by a public entity on behalf of a private enterprise to enable it to obtain low cost financing for pollution control, are also covered under the code. They carry tax ex- empt status and are similar in form to municipal revenue bonds; however, the credit rating of the corporation and its guarantee of revenues are key to the marketability of such bonds. The major approaches to long—term financing for capital intensive facilities and/or equipment are presented as follows: General Obligation Bonds Usually the easiest financing approach in resource recovery develop- ment involves the issuance of general obligation bonds. Such bonds are backed by the full faith and credit of the municipality (could be more Gordian Associates Incorporated ------- 59 than one municipality) issuing them. In other words, the municipality pledges its taxing power without limit as to rate or amount to ensure payment of the debt rather than relying only on project revenues. For a community with a very good bond rating, the financial community does not examine G.O. bonds as closely as other financing instruments and thus, some projects could be developed without certain key project elements in place, i.e., lack of long—term market agreements. In general obligation bond financing the municipality is normally required by law to secure voter approval for the bond issuance. Thus, the project may come under close public scrutiny if not close examination from the investors. There are some recent examples of resource recovery facilities being financed with G.O. bonds. Among these are an RDF pro- ject in Ames, Iowa, the Crawford RDF plant in Chicago, and RDF/dedicated boiler projects in Dade County Florida and Columbus, Ohio. Most of these projects involve a strong public works department and/or a municipal utility as the energy market. It is important to note that many municipalities may be near their legal debt limit or have poor credit ratings and thus, not find general obligation bond issuance a viable option for resource recovery project financing. Revenue Bonds Revenue bond financing typically involves the issuance of municipal bonds or industrial development authority bonds secured by the revenues of the project and not the taxing authority of the issuing entity. The revenues include the “tipping fees” or payments for service made by the users of the project facilities, and, in a resource recovery project, would also include revenues received from the sale of products such as steam, electricity, ferrous metals, or other energy and materials. These bonds usually require an interest rate ranging .5% — 1.5% higher than for general obligation bond financing. Further, they will come under very close scrutiny by the investment community since they are not secured by “full faith and credit” of a municipality. For such bonds to be marketable in financing a resource recovery project, there typi- cally have to be several security features in the project. The issuing Gordian Associates Incorporated ------- 60 agency must be able to set rates and charges sufficient to cover debt service and all operation and maintenance on the project over its life. Bond underwriters will typically look for contractually coiitted fees and revenues minus operating and maintenance costs sufficient to provide “coverage” of 1.25 — 2 times the capital charges. Additional require- ments in the bond resolution may include the establishment of various reserve and contingency funds. The issuing entity, whether a municipality or municipal authority or other authority arrangement, must have the ability to “control” the waste stream and to control private collectors to ensure sufficient waste quantities and, thus, revenues to the project. In addition, firm, long— term contracts of a “put or pay” nature whereby one or more energy mar- kets agree to purchase a minimum quantity of energy and pay a minimum amount for it whether they use it or not must be secured before the financing can be completed. Revenue bond financed projects need not be strictly municipal. They may include private operation and, in certain cases, private ownership where the tax benefits to a private entity or the lower “effective” cost of capital would be attractive to a private company capable of owning and operating a facility. While the interest rate on a revenue bond may ex- ceed that of a general obligation bond by as much as 1.5% the tax bene- fits of ownership that would accrue to a private entity could total 2 or 3%. In this manner, some of those savings could then be passed on to the communities in the form of lower tipping fees. It is important in structuring any resource recovery project financ- ing that the goal of municipal control in protecting the public interest while still providing for the opportunity for private operation (and possibly ownership to the extent it would qualify the private firm(s) for tax benefits) is fully considered. The participating communities must have strong guarantees from an experienced company with a proven track record and an incentive to make the project work in conformance with local conditions. Yet, both public and private groups must be willing to assume certain risks they can best assume and share others that they can- not fully absorb. Gordian Associates Incorporated ------- 61 A more complex method of financing involving a mix of public and private investment is discussed in the next section. Leveraged Leasing This form of financing involves the participation of a private entity investor(s) in 20% — 40% of the project costs and the leveraging of that investor’s funds with the tax—exempt financing of the remainder of the project costs and the benefits of tax ownership the private investor can claim. The private investor becomes the owner/lessor of the project and would in turn, lease the facilities to another private entity termed the user/lessee. En the case where the user/lessee is able to take full advantage of the tax benefits of ownership, it may not be economically viable to pursue leveraged leasing. The equity investor must finance at least 20% of the cost of the project and maintain that throughout the lease term. The remainder could be financed with industrial development bonds or the long—term obliga- tions (GOB or revenue bond) of a municipality or trust. The equity in- vestors, typically one or more individuals in a very high tax bracket, are able to shelter part of their other income through the tax benefits of ownership. In this manner and along with the cash flow from lease rental and the residual value of the project, the investors earn a suffi- cient return on investment and the community is able to reduce its amount of capital required as well as the effective interest cost of the capital for a resource recovery project (although leveraged leasing is not re- stricted to resource recovery projects). It is appropriate to obtain an IRS advance ruling on a leveraged lease financing to ensure that the arrangement is, in fact, a true lease and the equity investors qualify as the project owners for Federal income tax purposes. In addition, the IRS has set forth several rules and con- ditions relative to this type of financing which may make it difficult for certain contemplated arrangements to qualify and which must be care- fully evaluated in structuring this rather complicated form of financing. Gordian Associates Incorporated ------- 62 Recently, leveraged lease financing for resource recovery projects has received interest from commercial banks and at least one is pursuing this approach rather aggressively. Under this approach, the bank would become the paper owner of the project and arrange a lease with a silent partner who would put up 25% — 40% of the equity and accrue the ownership tax benefits. The lessee, either a private operator or a municipality, enters into a construction contract with a builder who would construct, test, and deliver a project meeting required specifications. It would also enter into waste disposal contract(s), energy sales contract(s), and perhaps materials sales contract(s). Payments received under these contracts are designed to cover lease rental and operator fees. At the end of the lease, the lessee would typically have the option to purchase the project at fair market value. In the optimum case when 40% private equity is provided, the differ— ence in effective interest rates on total capital requirements between this financing approach and other forms of debt could be as much as five percentage points. Gordian Associates Incorporated ------- 63 Other Financing Programs and Incentives for Resource Recovery Projects There are several Federal grants, loan and loan guarantee programs that afford assistance to resource recovery project financing and serve as incentives to develop projects that might not otherwise be finance— able. This is not to say that if a project is not economically sound it should be pursued using one or more forms of Federal financial assistance. Included in recently developed financing incentives are several modifications of current law and addition of new programs for resource recovery, primarily energy recovery projects, under the Crude Oil Wind- fall Profits Tax Act signed into law in April 1980. Other programs are described below. Current Federal Programs for Capital Funding of Resource Recovery Projects (1) Co—Disposal of Sewage Sludge and Solid Waste Resource recovery projects that include the co—disposal of sewage sludge and municipal solid waste may qualify for direct grants under Section 201 of the Clean Water Act. This program has been used to fund other co—disposal projects to date and may be used to fund part of the costs of the equipment to pro- cess and combust sewage sludge. (2) Department of Energy Programs The U.S. Department of Energy provides several programs for re- source recovery financing assistance. Among these programs are a $15 million demonstration grant program for new technology, a recently announced program for alternative fuel production projects which is not yet defined for municipal waste resource recovery type projects, a loan guarantee program to provide Federal guarantees to finance was te—to— energy projects that may not otherwise be financeable such as in com- munities with low credit ratings, and a limited price support program which provides cash subsidies to energy recovery projects during the first several years of operation (usually when cash flows are lower), Gordian Associates Incorporated ------- 64 which are repaid during the later years of a project when cash flows are greater. This program is described in more detail in Appendix 3. The Department of Energy also has an “entitlements” program which provides direct s Ibsidies to municipal solid waste—to—energy produced; however, this program expires in 1981, well before any facilities could be implemented in Waterville/Winslow. SBA Loans The Small Business Administration maintains an Energy Loan program and a Pollution Loan program, which provide lower interest loans to qualifying small businesses for the development of various energy sav- ings and pollution control projects or the purchase of related equipment. These loans are limited to a maximum of $5 million each at present. Recoended Financing Approach Gordian recommends that the City of Waterville and the Town of Winslow each fund its respective share of the initial capital costs through the issuance of general obligation (G.o.) bonds, provided that: • its bond rating is sufficient to ensure an attractive interest rate; and • its debt ceiling will not be surpassed. Under optimal circumstances, G.O. bonds provide the lowest interest rate and ensure the ownership of the facility by the Corporation. Gordian Associates Incorporated ------- 65 i1tU .ULtLLILL’ L Alternative Procurement Approaches* There exist several methods for procuring resource recovery facil- ities and for their operation. These methods have been discussed in detail in a report previously issued to the City. Resource recovery procurement is a process by which decisions made in the selection phase regarding syst type are systematically trans- lated into an operational facility. This process involves contractor selection, contract negotiation, facility construction, and operational testing. Because the process tends to be both legally and administra- tively complex, a carefully considered procurement strategy is essential for successful implementation. There are three basic strategies, or procurement options, that can be followed, as shown in Figure 5.1. The first is the traditional architect—engineer approach (ME); the second is the turnkey approach and the third is a full service approach. There are, however, potential modification to each approach. The choice of one strategy over the other depends largely upon the issues of ultimate facility ownership, the allocation of risks between the City and private contractors, legal restrictions, and the availability of financing. A&E Approach The A&E approach is the strategy cities have traditionally used to procure sewer systems, roads, schools, land other public works. It nor- mally involves two separate procurements — one for engineering services and another for facility construction. Initially, an ME firm is se- lected on the basis of its past experience and present capabilities in the general type of resource recovery system desired by the City. The firm draws up the final enginering designs and helps the City to prepare an invitation for bids (IFB). The City then reviews the bids submitted by contractors and awards a contract for the construction of the facil- ity on the basis of lowest cost. In the A&E approach, the consulting * This discussion was derived mainly from “Procurement Strategies, Choices, and Contractual Methods Explored” by P. Aarne Vesilind and Dennis Warner, Solid Waste Management , April 1978. Gordian Associates Incorporated ------- 66 FIGURE 5.1 RESOURCE RECOVERY PROCUREMENT RESPONSIBILITIES UNDER THREE DIFFERENT ACQUISITION STRATEGIES ME Turnkey Full service Procurement Steps Option Option Option 1. Review City City City Qualifications 4 4 2. Design ME Facility Firm 3. Review Bids City 4. Construct Facility Contractor 5. Supervise ME Facility Construction Firm Contractor System 6. Equipment Vendors Contractor and Materials 7. Start Up Plant Operator —- Operator Operator 8. Operation and - Maintenance System Contractor or City 9. Facility Ovnership City City Source: Ibid,A. Vesilind 1 D. Warmer ------- 67 engineers often provide continuing services to the City in the form of construction supervision and monitoring of final plant shakedown. Turnkey Approach An alternative procurement option is the turnkey approach, in which he City contracts with a single contractor for a complete package of facility design, construction equipment supply, and start—up. The con- tractor is required to satisfy various acceptance criteria in turning over to the City a fully operating facility. A modification of this option is to have the contractor also operate the facility for the City. Turnkey contracts usually are awarded on the basis of a request for pro- posals (RIP) issued by the City. An RIP states in general terms the type of system wanted by the City and allows interested contractors the opportunity to propose comprehensive, and possibly unique, solutions for which they have special capabilities. Gordian Associates Incorporated ------- 68 Full—Service Approach The third option is the full service approach involving total im— plementation, operation, and possible ownership by a private firm. As in the case of the turnkey option, the City issues an RIP, but the contract is for a resource recovery service instead of a plant. The selected contractor is responsible for project financing, design, con- struction, equipment supply, start—up, and subsequent operation of the facility. The full—service contractor may own the facility and be solely responsible to the bondholders for repayment of the financing loan. The owner in this case would seek to back up his responsibility to the bondholders with long term contracts for assured waste supply and tipping fees from municipalities and for sale of by—products, energy and materials. In this case the owner would receive all tax benefits. tf the municipality or solid waste authority owns the facility, the operator may lease the plant and repay the bondholders via the plant owner in equal payments for the term of the lease. Under this arrange— inent the plant operator may be entitled to all profits or may be re- quired to share revenues in excess of a predetermined return on in- vestment with the plant owner. Under such a financing mechanism the lessee (plant operator) is, for tax purposes, considered owner of the plant, although title still resides with the municipality or authority. As such, the lessee (operator) of the plant is entitled to the full investment tax credit of between 20 to 30% and the accelerated tax de— prec iat ion. Alternatively, the contractor or operator may act solely as the plant operator without leasing under contract to the owner (municipal- ity). Successful cases of all three types of contracting strategies can be found. One of the first to use the A&E approach was Ames, Iowa, which since 1975 has had a fully operational 200 TPD system producing refuse derived fuel, baled paper, and metals. On the other hand, Auburn, Maine adopted the modified turnkey approach and expects to have a 200 TPD plant producing steam in 1980. The full service approach is well illustrated in Bridgeport, where an 1800 TPD plant producing refuse derived fuel, metals, and glass expects to be operational in 1981. Gordiari Associates Incorporated ------- 69 Within the context of the three procurement options, there are two basic methods for reaching contractual agreements between the City and the suppliers of services, facilities, and equipment. The first method can be termed competitive procurement, because it utilizes formal ad- vertising and the selection of the lowest responsive bid according to well—defined specifications. Since it is the traditional method used in the A&E approach, competitive procurement is a widely used procedure in public works implementation and is well understood by city personnel. The competitive procurement method begins with an examination of the qualifications of ME consulting firma by the city. The selected firm normally is chosen on the basis of its relevant resource recovery experience, the type of recovery system desired by the City, and the results of negotiations between the City and the firm. This portion of the cbmpetitive procurement method is not price competitive, although the remainder of the process is. The consultant then carries Out final system designs and helps to prepare an IPB containing detailed speci- fications of the type of system desired. The resulting bids from poten- tial contractors are price competitive, since they are evaluated on the basis of both technical merits and cost. The second method for arriving at contracts is termed negotiated procurement, and it applies primarily to the turnkey and full service procurement approaches. Negotiated procurement has not been widely used in the acquisition of public works, and it occasionally runs into restrictions from state laws requiring competitive bidding on the basis of price. Although competitive procurement is well suited to systems which can be clearly specified in advance, a growing number of state and local governments are coming to realize that negotiated procurement is far more effective in the acquisition of systems whose technology, markets and operations contain many uncertainties at the time of con- tract negotiations. The heart of the negotiated procurement method is the R7P, which generally solicits bids on the basis of specifications more broadly drawn than those in an IFB. In general, an RPP for a turnkey approach will contain more technical detail than one for a full service option. Nevertheless, the use of an R!P shifts much of the design responsibility Gordian Associates Incorporated ------- 70 to the contractor and, hopefully, provides the city with a wide range of proposed technical solutions. Following proposal evaluation, a winning contractor (or set of finalists) is selected and the City then enters into contract negotiations with this firm. Any necessary deviations from the iF? must be considered at this point. Furthermore, the con- tract should contain sufficient flexibility to allow the contractor to adjust to unanticipated technical and financial changes in the systems. Without this flexibility, the increased risks borne by the contractor will be reflected in higher contract costs to the city. Implementing Agency’ s Philosophical Posture The implementing agency’s philosophical posture is very important to consider in determining which procurement approach will be under- taken. Remembering that the primary purpose for undertaking a resource recovery project is to provide for the sound disposal of solid waste without creating a public health hazard or an environmental pollution problem, municipal officials are faced with deciding between traditional and nontraditional approaches. Resource recovery companies exist which are willing to provide equipment and/or services to address municipal needs under any conceiv- able project structure that can be effectively applied. Various pro- jects have been implemented under very different structures reflecting the posture of the local officials as well as the availability of alter- natives that are believed to exist. Municipal officials will need to decide what degree of control they wish to have in maintaining the public health aspects of solid waste disposal, either directly or through contracts for service. Similar decisions will need to be made regarding which capital financing vehi- cle can be used. The availability of financing approaches and mecha— nieme does affect the procurement decision. Siinilarily, decisions must be made with regard to the degree of support it will commit over the life of the project for the operations — either through commitment of certain minimum quantities of solid waste or through a guaranteed pay- ment for receiving the service of disposal through recovery. Gordian Associates Incorporated ------- 71 Basic to these decisions is the degree of control that the City of Waterville and the Town of Winslow would like to maintain over the facil- ities’ operations. For greatest control, the municipalities should main- tain ownership through the Waterville—Winslow Joint Solid Water Disposal Facility. The control is lees direct if ownership does not lie with an entity which is accountable to the participating municipalities. If ade- quate capacity for sanitary landfill exists in the future and at a rea- sonable cost — less than projected at this time for resource recovery — then it may be advisable to allow others to own the facilities. If prob- lems arise, disposal could be provided by sanitary landfilling directly. As discussed earlier, even if publicly owned, the facility can be privately operated as well as designed and constructed by the same en- tity. As public agencies usually have less flexibility to hire/fire staffresources, consideration of this posture may become a necessity for the operation of resource recovery equipment. Small System Procurement Experience A growing number of small resource recovery systems are being planned and implemented. The experiences of the projects that have moved forward into construction and operation phases are reviewed briefly here to provide perspective. Presented in Table 5.1 is a listing of twelve localities that are either operating or constructing small modular units. The procurement methods followed by these localities are summarized as follows: As can be seen, the A&E approach has most often been used in the procurement of small systems. However, two recent procurements — Auburn, Maine and Pittsfield, Massachusetts — and North Little Rock’s recent award of the operating contract to Consumat Systems Inc. indicate a new trend in municipal procurement of small systems as well. A review of the decision—making process in these locations is pre- sented here for background purposes. North Little Rock In 1971, North Little Rock purchased two small incinerators (12.5 tons per day per uu t) without energy recovery capability to handle their growing volume of solid waste. However, the units were never Gordian Associates Incorporated ------- 72 TABLE 5.1 MODULAR COMBUSTION PROJECTS Th• following localities ar• either operating or constructing small modular combustion units to pro- duce sf.am horn mass combustion of municipal solid waste: SEPOITED CRP*CITT WIT*L 00STS (EPO) lLU0MSW 8) £* iI . UI. 3.2 Dingil inairaU . leaded by DOt Bibri Iii , aigned enrgp sin slid .ws’w Pubic W inntrscts sqn.d inledluCtisli 90buTh Cdt Mall began Aug 1971. davtup lsnned 45 Srung St 1w No. 1930 *ubuin, Maine 04210 76 N/A Ts,nwardy SMut d n 1w uastillatea Tam Ldtle Mayw be Mt med S I addstam& unitS Cdv Mall IlfiIeadle. Ark 72315 60 3 11 be SMMJama . uadw sing Nelson C Malir I .it i s st i sn$ Gin Mg tawinnsontul3am i nCam P.O Boa 765 Ciaseall Tens 33555 _____ 100 2 Under amnd,udwn. Alderman Bob mrs Ma’tup idheduled is swIg 1980 CIornal Rubbr Dysvsbw( Tim. 33024 300 2.0 Begin speisthens in feb 3980 Ninumsiltkaqa Mann. P1 Tsu,nsti’D Engines’ 7244 North Rd Canine . Nd 41437 NiL £ _ bel 24 N/A Opratioal ames 1976 Rd Caudle Cs.ssl P,ud ts Crinetan Pasv Mill. Inc Gmueton.RN 03512 93 N/A Under amedvuctisil: be be is sperabun *1Mm 0 Iambert beisly 3930 DtyManagr 105 EIbngton P 5 w 7.. R I! Ln.iburg Teas 37091 1.45 Operational 19761979. , inU , uk Botasi sndsigsing modifications. Cdy Pruidenl anarded be Consumat U.S. Iu Je CIP Systems Inc.. 1w nmdilicatisns and P .O Boa 7561 Iu ng4evm operation. inisduled be lithe Rack. *,k 72217 NipetaMsIob 1980 SO 1.3 Iqan operations us Mn. 1980 U Preudi. Mayer City Mall Bocusfe . *15.72370 240 12 slobs ul . ,1V.d i o mob i Bomas. Jr. k 1180 P emodenl VmanRacmert c P.O Boa 100 S I . Censu Butler, NJ 07405 t —t 1.1 Operational. 1979 Wdham P a. Jr. Coy Mgr P.O. B. 069 S.lsm.Ya.2*153 36 A Ope r etaia lsina ss,t lm *1 Vrw . Our. inenUp bmnj used as Ssmtatusn Bopt moly) 430 North $ilsom Spus k 72763 Source: NCRR Bulletin, Voluwe 10, Number 1, Xarch 1980 ------- 73 installed because of political problems relating to siting. In 1974, U.S. Recycle Corporation, a franchised dealer of Consumat Systems, Inc. proposed that the City operate a modular incineration system with energy recovery and that it sell the steam produced from the system to a poten- tial market — Koppers Company. After favorably receiving a U.S. Recycle study which included a discussion of potential project economics, along with positive discussions with Koppers regarding the apparent feasibil- ity of a Consumat System meeting steam requirements, the City decided in 1975 to pursue the energy recovery system. From 1976 to mid—1977 con- tracts were negotiated and the facility was constructed. In September 1977, the City began operating its own modular incineration system that was contractor-designed and constructed. The turnkey approach was not operating to the City’s satisfaction, however, and in March of 1980, the City turned over the operations of the facility to Consumat (Figure 5.2). The City had determined that it would own and operate the facility from its start. However, Consumat assumed responsibility for the daily operation of the facility when it was determined that City personnel were not properly carrying out required tasks. Under the new arrangement, the City receives all revenue from steam sales and pays Consumat a flat fee for facility operation. Consumat assumes all risk for the quantity of materials required for daily operations. The operating contract is limited to one year due to state law, but it appears that Consumat’s direction of operations will continue at least until the steam contract with Koppers terminates. In selecting the contractor, the City was required by state law to carry out competitive bid processes except in “exceptional situations where such procedure is deemed not feasible or practicable.” The RIP was very detailed in that it included proposer qualifications criteria in the bid package for the design, construction, and equipping of the facility. Proposers had to have had at least two years of demonstrated experience providing similar systems for processing municipal refuse and with at least two projects involving municipal solid waste processing and in pro- viding steam to a user which required a uniform and uninterrupted supply of steam. The RIP was released in November 1975 and contract negotia- tions were culminated in April 1976. U.S. Recycle/Consumat, the selected Gordian Associates Incorporated ------- 74 FIGURE 5.2 NORTH LITTLE ROCK CONTRACTS ModificatiOfl8 Steast Purchaser ------- 75 contractor proposed a fixed price for the equipment, supervision of in- stallation, training of City employees during the first year of opera- tion, and equipment testing at the end of one year to determine perfor- mance quantities. Project costs were financed from a special revenue bond issue and from available city funds. - The City retained a local engineering firm to prepare plans and specifications for plant building construction and equipment installa- tion. U.S. Recycle also provided assistance in the preparation of spec- ifications and offered to meet with each prospective bidder to describe the Conaumat equipment installation requirements in order to aid in the bidder’s cost estimates and guarantee proper installation. Bids were opened in early June 1976 and a contract was awarded to the lowest bidder two weeks later. ln June 1976, the City and Koppers signed contracts for the purchase of steam, including a provision for the project to utilize Koppers’ wood wastes, and for a site lease. The steam purchase agreement provides that Koppers will purchase steam requirements of Koppers’ Forest Products plant. The price of steam was pegged to the lowest cost fuel available to the Forest Products plant. Koppers must approve the City’s plans and specifications for the modular incineration units. The steam purchase contract did not include a guarantee by Koppers to purchase a specific amount of steam, only that it purchase the amount required for current operations. The wood waste agreement is for one year with an annual renewal option. It was felt that woodwaste would serve as an auxiliary fuel source for weekend operations, if operations were expanded, but nothing has happened to date. Koppers will provide voodwaste to the City at no cost. The site lease contract covers a 20—year period, where the City is obligated to pay a rental of $1 per year and all property tax assessments and improvement charges. Pittsfield, Massachusetts The Pittsfield plant will be designed, constructed and operated by Vicon Recovery Associates, a subsidiary of Vicon Construction Co. The steam will be sold to a nearby paper company, Crane & Co. Project shake- down is expected to begin in November 1980 and last for four to six months. Gordian Associates Incorporated ------- 76 The financing for the project was provided through tax—exempt p0 l— lution control revenue bonds sponsored by a local industrial development authority.* The bonds are guaranteed directly by Vicon Construction and indirectly by Pittsfield’s guarantee to deliver waste or pay tipping fees. The initial tipping fee is set at $11.59 per ton. However, pro- jections indicate profits to the operation which are to be shared 50/50 between Vicon and Pittsfield, thus reducing Pittsfield’s upfront tipping fee. The RFP was prepared by the City engineering and investment con- sultants. It stated that the City was willing to enter into a put—or— pay contract for delivery of solid waste, to provide a site for the facility as well as a residue and emergency landfill site, and to aid the contractor in obtaining tax—exempt financing. The RFP also identi- fied Crane & Co. as the steam customer. The RFP was advertised in March 1978 and two months later Vicon Recovery Associates was selected. The steam purchase contract becomes effective in December 1981, or at an earlier date agreed upon by the company and Crane. The project has been set up for a 15 year period. The company must construct the facility and ass e all costs relating to steam producing facilities as well as lines and equipment for steam delivery. The company is required to sell and deliver, and Crane to accept and purchase, at least 700,000 lb of steam per day at a rate of at least 20,000 lb per hour for 240 Crane work—days. Steam prices will be based on Crane’s cost for No. 6 fuel oil discounted by a negotiated rate. Pittsfield has shifted the project’s technical and performance risk to a private company which guarantees the design and its ability to process waste and generate steam. In return, Pittsfield accepted the responsibility to assure waste stream supply quantity and quality and to pay tipping fees if waste is not available for some reason. * Robert H. Aldrich, “Small Resource Recovery Project Gets Disposal Revenue Bond Pinancing,” in Solid Waste Management , January 1980. Gordian Associates Incorporated ------- 77 Auburn, Maine Recognizing a disposal problem in 1974, a planning process was initiated to identify alternatives. In 1975, an energy recovery scenario was identified. Efforts began to crystallize in 1977 when the City prepared an implementation report which highlighted the problem and provided direction. Between 1977 and 1979, the City went through a decision—making process that led to a City—owned, contractor—designed, constructed and operated (over an initial 3 year basis) project. See Appendix C for more detail on the project. The contract arrangements are depicted in Figure 5.3. The City decided early on to own the facility and eventually to operate it as well. However, current operating experience in other municipally-owned and operated systems convinced Auburn officials to modify their approach. They decided to give responsibility of design, construction and opera- tion to one contractor. The initial operating phase was set at three years and allows for two five—year extensions. The City guarantees waste quantity and quality and, in the event of waste shortfall, an operating fee to the operation. Provisions for processing additional waste and sludge are provided. The City maintains control over additional waste through contractual arrangements with other municipalities and with the sewer authority for sludge supply. In selecting the contractor, the City solicited a very detailed Re- quest for Proposals describing the project and the contractual terms it was interested in offering. The RFP was released in December 1977, a contractor was selected in July 1978, and contract negotiations with the contractor and steam customer were concluded in October 1979. The project is backed substantially by the steam sales contract. The revenue generation will be substantial. More importantly, the steam purchaser — a major U.S. corporation — guarantees to “take or pay” for steam. In the event that the steam user closes its facility in Auburn, the agreement also provides for continued payments equivalent to the principal and interest on the City’s long—term debt for the project. The project technology and performance risks are completely shifted to the contractor as long as it remains the operator of the facility. Gordian Associates Incorporated ------- 78 FIGURE 5.3 MDE ConstEti S fl Obligat L1ie t r t bn F —E 1 ill Sa1e Su 1y Division of cons t t Libby O.mxi FwxI Operate T si I r i t Irac./Global ve1u 1 ut II ------- 79 Performance incentive and penalty provisions are included in the opera- ting specifications. The City has the right to take over the facility in the case of non—performance by the contractor over an extended period of t line. The Auburn project is an example of strong desire to both own and operate a resource recovery facility being tempered by recent experience elsewhere and recognition of the fact that the project has to be run as a business — the need to overcome City constraints in personnel and mainte- nance. It is also worth noting that the influence and participation of the energy user throughout the planning and contractor selection process was important to the project’s success and significantly influenced pro- ject structure. RECOMMENDED PROCUREMENT APPROACH The by—laws of the Waterville—WinslOw Joint Solid Waste Disposal Facility Corporation (hereafter referred to as the Corporation) permit it considerable latitude in the procurement which it may adopt. Article 3.3a would even allow the ownership of the facility to be assigned to a full—service contractor, provided the unanimous consent of the Joint Board was obtained. Gordian recommends that the advantages of the full—service procure- ment approach should be examined carefully by the Joint Board. The oper- ation and maintenance of a modular combustion facility require skills which a public corporation may find difficult to attract (as was shown by the experience of North Little Rock). In addition, the contractor is responsible for the construction and the performance of the system pro- cured, and thus, shares some of the technical risks associated with implementing the project. (This latter advantage is also shared by the turnkey approach.) The ultimate control of operations would be retained by the Corporation through its ownership of the facility and its role in approving the annual operating budget for the facility. Gordian Associates Incorporated ------- 80 Alternative Procurement Strategies Overview of Strategies The alternative procurement strategies available to the Corpora- tion are displayed in Figure 5.4. The first priorities of any strategy are to secure contracts for waste supply and the energy market and to select the financing and procurement approaches to be taken (Step 1). The A&E approach would then require that the Corporation advertise for and select an ME firm to design the proposed facility (Step 2). This would include the development of specifications for the facility which would be used by the construction contractor. Depending on the requirement of the Maine Department of Environ- mental Protection, an environmental assessment of the proposed project may be required at this stage (Step 3). Also in Step 3 (Preconstruc— tion Planning) the financing and any required preconstruction permits should be secured. The sale of G.O. bonds may require voter approval and preparation for a referendum should be started well in advance. Once the financing is secured, an invitation to bid (In) is issued for a contractor to construct the facility (Step 4). (Ill’s for hardware vendors may also be issued.) Following selection of the con- struction contractor, construction can proceed. Although the services being procured under the turnkey and full— service approaches are different, the procurement strategies used are essentially the same. As with the ME approach, the Corporation must secure contracts for waste supply and the energy market as well as select the financing approach (Step 1). Following this in Step 2, an RIP for the turnkey or full-service contractor/system vendor is pre- pared and issued. The proposals submitted are evaluated and a con- tractor selected. A contract with the vendor must be negotiated and finalized. It is important that this agreement clearly define the roles and responsibilities of the contractor and the Corporation. Generally, the contractor will prepare a preliminary design to facilitate the financing process and obtaining preconstruction permits in Step 3. This source will be provided one of the contractor’s fee and this will be included as a capital cost. As with the A&E approach, some kind of environmental assessment of the project may be required. Gordian Associates Incorporated ------- 81 FIGURE 5.4: ALTERNATIVE PROCUREMENT STRATEGIES STEP 1.. ProcureLlent P1anni g SECURE WASTE and Contracts SUPPLY CONTRACTS SECUR MARXET CONTRACT SELECT NAZ1CINC APPROACH SELECT P CUREMENT APPROACH 1,JRNUY/FULL-SERVICE STEP 2. ContractOr SelectiO PREPARE AND ISSUE RFP (Advertise for and Select ME Contractor) EVALUATE PROPOSALS AND sELECT 1 coNTRAcToR NEGOTiATE AND FINALIZE CONTRACT WITH SELECTED VENDOR __ ‘I , STEP 3. PreconStrUCt1 9 PERFORM ENVIRORMENTAL PERFORM ENVIRONNENTAL __________________ £SSESS IT (as Required) - - ASSESSMENT (as Required) SECURE NANCINC SECURE FINANCING SECURE PiNSTRUCTION PER 1 ITS CONS TRUCTION STEP 4. ConatTUCtiOR ISSU , ivs Contractor Selection ___________ SELECT CONSTIUJCTION co CTOR (CON CTION) (CONSTRUCTION) ------- 82 Gordian strongly recoends that the Corporation employ a third— party engineering firm in Step 4 to supervise the contractor’s planning, design and construction of the facility to ensure that the contractor meets the terms of the contract. Procurement Schedule An approximate schedule for procurement under the alternative strategies is shown in Figure 5.5. Gordian estimates that all alterna- tive procurement strategies can result in ground—breaking within twelve months. This could be achieved over a shorter period for the turnkey/ full—service approach depending on the time that elapses between issuing the RFP and finalization of the contract with the syst vendor. The ME approach will probably require the full twelve months since the design and preparation of specifications for the IFB by the A&E firm will be time consuming. In contrast, the full—service turnkey contrac- tor will have this design information on hand. However, it should be emphasized that unforeseen difficulties 1 such as the inability to finalize contracts, could delay project imple- mentation considerably. Procurement Costs Estimates for the cost to complete the alternative procurement strategies, including both the cost of consulting and in kind services, are shown in Table 5.2. Gordian estimates that full—service/turnkey approach would cost $120,000 compared to $90,000 for the A&E appraoch. Although the estimated cost for the ME approach is less than for the turnkey/full—service approaches, the overall cost may be greater due to a higher engineering fee which will result from the greater role the ME firm takes in overseeing construction. Project Management The interlocal agreement that created the Corporation specifies the management structure to be adopted for the proposed facility. The only major option available to the Corporation is whether to operate the facility itself or hire a contractor. Project management for the former Gordian Associates Incorporated ------- FIGURE 5.5 Approximate Schedule for Alternative Procurement Strategiea A6 E Step 1 Turnkey! Full—Service 1 1 1 1 [ I —. 1 —. —. — — J 2 3 4 Step 1 2 3 4 I I — — I 1 I 0 1 2 3 4 5 6 7 8 9 10 11 12 N ------- Step 2 Contractor Selection Step 4 Construction Contractor Selection TABLE 5.2 Cost Esti.atss for Alternative Procure.snt Strategies 84 Step I Procureweot Planning and Contracts Tasks a. Scure b. Secure c. Select d. Select Cost Estinete Is bOO) waits supply contracts arket contract finsnc ing procurewent approach Step Total -g Step 3 Reconstruct son Planning A & E PROCURLI r Tasks Cost Sst i ste $ z 1OO0 Tasks Cost Situate (5 z 1000) a. Advertise for AU fire b. Evaluate qualuficalions and select firn Step Total T5 a. Prepare and issue UP b. Evaluate proposals and aslect contractor c. Negotiate end finalize con- tract with selected vendor Step Total a. Perfor. enviroewental aesesent (as required) b. Sscure financing c. Secure prsconstruction per. its Step Total 40 a. P.rfor. enviroewsatal assess— ewnt (as required) b. Secure financing Step Total s. Issue I FIs b. Select construction contrector (and hardware vendors) Step Total TOTALS 16 90 a. Construction .anagewent Step Total 120 ------- 85 case is illustrated in Figure 5.6 by means of a cash flow diagram. The system operating costs will be paid by the Corporation from revenues from tipping fees, and energy revenues. Excess revenues would be re- turned to the participants (Waterville and Winslow) according to their share of the operating costs (levied on the basis of MSW processed by a tipping fee). The excess revenues would be used by the participants for debt retirement. The project management would be only slightly altered if the facility operation were to be contracted privately, as is illustrated by a cash flow diagram in Figure 5.7. En this case, the system oper- ating costs would be paid though by the operator who would receive an operating fee from the Corporation which would include a profit for the operator. The operator would also receive a percentage of the energy revenues. This would provide an incentive for the operator to maximize energy production and thus increase its profit. Gordian Associates Incorporated ------- 86 FIGURE 5.6: CASH FLOW FOR FACILITY OPERATED BY THE CORPORATION Service FEES Service Tipping Fees Energy Revenues ------- 87 FIGURE 5.7: CASH FLOW FOR FACILITY OPERATED BY A PRIVATE CONTRACTOR Debt Service FEES Tipping Fees Service I a — — J ------- 88 VI. CONCLUSION This study is designed to move Waterville/Winslow closer to actual implementation of a resource recovery facility. However, completion of -this report is only part of the resource recovery planning and procurement process. That process is generally divided into three phases: • Phase I — Feasibility Analysis; • Phase II — Procurement Planning; and • Phase III — System Procurement. The report by E.C. Jordan essentially completed Phase I, establishing the feasibility of energy recovery with Keyes Fibre Co. as the market for steam. The purpose in providing assistance through the Panels Program was to assist Waterville/Winslow in completing or making progress on the tasks in Phase II which include: • define project; • update project economics; • secure waste supply; • allocate risks; • select procurement approach; and • select financing approach. This report has provided Waterville/Winslow with more detailed analysis of three important areas of the proposed project: the energy market and steam agreement, project economics and alternative procurement strategies. From these analyses, Cordian can make the following observations: • the project under consideration is basically sound; • the creation of the Corporation provides a vehicle for procurement and project management; • an interested market for energy has been identified although there is considerable interest in seeking a new, possibly more secure, market; and Gordian Associates Incorporated ------- 89 • the economics of the proposed project are promising — although the present landfill is inexpensive, it will reach capacity in the near future and means of developing a new landfill are foreseen — thus, resource recovery must be considered a viable alternative. However, despite these promising factors, Gordian must caution Waterville/Winslow that some important elements of the project need to be addressed. These are: • finalizing a contract for an energy market; • securing contracts for waste supply; and • a commitment from the community to raise the money for procurement. In conclusion, Gordian recommends that Waterville/Winslow proceed with the steps outlined above and in Section V as quickly as possible. Any delay will result in increased costs for the system due to inflation as well as the loss of the momentum and commitments already gained. Gordian Associates Incorporated ------- 90 APPENDIX 1 WATERVILLE-WIN SLOW INTERLOCAL SOLID WASTE AGREEMENT WATERVILLE-WINSLOW JOINT SOLID WASTE DISPOSAL FACILITY CORPORATION CERTIFICATE OF ORGANIZATION OF A CORPORATION AND BY-LAWS Gordian Associates Incorporated ------- 91 WATERV I LLE-WINSLOW INT):RLOCAL, SOLI r) W1’! TE 1 GREENflNT ANI) WATERVILLE—WINSLOt ’ JOINT SOLID WAST1 flTSPOs1 T, r, CILITY COPPOPJ TIOI 1 CERTIFICATE OF ORGANTZ?TION OF A CORPORATION A! D BY-LAWS This AGREEMENT, mac ic this clay of 1980, by and between the City oC Watorvillo and the Town of Winslow, the participatinq niunicipctlities hereinafter referred to as the “Parties,” all bcinq bodies politic and corporate located in the Couriy of Konnebec, and State of Maine. WHEREAS th Partj s to this Agr cment hiwo the duty to provide solid waste disposal fncilities for domosLic and commercial, solid wastes qc’ner. r’cI within thcir respective territorics,pursuant to Tit l 3K M.fl.S.i ., ncction 1305(1); an ci WHEREAS the Parties are authorized to contract pursuant to the Maine Interloca]. Cooperation Act, pursuant to Title 30, Chapter 203. M.R.S.A.; and WHEREAS the Parties arc d s;irnus t other throucjh an intcrlocal atlrcc’ment. to such powers, privilenes, or authority as by law to exercise individually in order a cooperative program for the manaqement generated within their boundaries and to in an Energy Recovery Facility; anti cooporato with each exercise jointly they are permitted to participate in o ’f solid waste thereby participate WHEREAS that it will their mutual the Parties to this Agreement have determined be a more effici nt use of their powers and to advantage to entc•r into this Agreement; and ------- 92 WIIEREAS the Parties to this Ac1rc meni are further desirous of setting forth herein the terms and conditions of their Agreement to cooperate in a program for the management of solid waste qencrated within their boundaries and an Energy Recovery Facility, and an addition to orqanize the Waterville—Winslow Joint Solid waste Disposal Facility Corporation, hereinafter referred to as thc “Corporation,” to carry out such management dulics and responsibilitics and to set forth herein the Certificate of Orqanizat o and By—Laws of such Corporation; anti WHEREJ S this Corporation shall be a quasi—municipal corporation, jointly owned by the City of Watcrville and the Town of Winslow, and sup!)ortod by public funds of the municipal Parties and by revenues produced and/or received from other users by contract with the Corporation. NOW, THEREFORE, the municipalities of Watervil].e and Winslow, for and in consjdcration of the mutual promises and agreements hereinafter stated and the performance thereof do hereby promise anti aqrec as follows: PART 1. PURI’OSF. 1. 1 That the purpose of this / qrcemenL and the Cor- poration is to include but not be limited to providincy for the disposal of solid wastes cwric ratec1 within the territor- ies of the Parties, or within I.hi territoric of other individuals, corporations, or municipalities which may in the future become parties to this Agreement or which may contract with these Parties to this Aqrecmont for the use of such participating municipal Parties’ Solid Waste Disposal Facilities; and to orq.intze, operate, and maintain thereby a joint Energy Pecovcry Facility; and for all purposes permitted under Title 13, Chzwter 81,M.R.S.A.. Corporations Without Capital Stock. 1.2 That the purpose of this Agreement is to provide for the acquisition bf real anti personal property necessary to the management of solid astc and to establish and carry out a program of solid waste manoqemont and an Energy Recovery Facility for solid w;iste: 2 ------- 93 a. ‘Fhe managemcnl oC 5weh solid wzistc as may be generated within the boundaries of the Parties at rate schedules and proportions established pursuint to this Acyrecmnent; or b. As may be generatci elsewhere when the management of such solid wast’ is accepted by a majority vote of the Waterville-wins]ow Joint Solid Waste L ispos 1 r cility Corpora- tion, hereinafter ‘fc rrcd to as the “Coiporation,” at T Lc’S established by the Board of Directovra ci thc’ Corporation, here- inafter rcfcrrc’d to 1 ,s tho “.!ajnt. T oarc1,” PART 2. 1 Fl’INTT1ON 2.1 Definitions as usedl in this Agreement: a. “Solid Waste” mc nns solid materials with insufficient lic uid content to be free flowing, jflCludlnci without limitation rubbish, gnrhagc’, scr.,p materials, junk, refuse, inert material and landscape refuse, b. “Solid Waste Disposal Facility” means any land area or structure or combination of land ar”a and st ruc urc s, iuc d for storing, salvaijinq, proccs i;icj, reducing, incinerat- inq, or disposiiic of solid w 1 ist-es, including an Fnergy Rc ciwry F ici I i y for thr incin- eration of solid waste and gc’neration of steam for sale and rc venue. PART 3. APMJN1STRATION 3.1 Joint Board. The Certificate of Organization and By—Laws of the Waterville—Ijinslow Joint Solid Waste Disposal Facility Corporation, attached to this Aqrocment as Appendix A and Appendix B respectively, arc hereby incorporated into and made a part of this Aqrec’mi’nt. The Joint Board of the ------- 94 Corporation shall be two (2) iiiembers of each of the -Parties’ respective City and Town Councils duly appointed pursuant to each of the Parties’ municipal charter5 and Maine law regard- inq appointments, plus each of thc Pi rties’ City Administrator and Town Manager, plus one (1) citizen—at-large for each ten thousand (10,000) in population for cach of the respective Parties. Therefore, at. thc com uenccmcnt of this Agreement and of this Corporation, and ai. according to each of the respective Parties’ populations, the Municipality of Waterville shall have four (4) Joint Boar l members, and the Municipality of Winslow shall have three (3) mint Board members. All terms of Joint Board members who are City or Town Council members and the City Administrator and Town Manager shall be co-terrninous with municipal office and shall hold such position as a Joint Board member only durinq each of their present terms of office. Each and every iLizcn—at—]arqi duly. appoinLeci by each of the respective City or Town Counci I ; of each of th• Parties to this Agreement, shall be so appointci.] for alternating staggered three (3) year and two (2) year tc rm . Upon the effective dat of this Agreement and of the Corporation, or as soon thcrc’aiter as possible, the Joint Board shall hold an orcjanization;iI r u I.inq tn c lcct. Officers of th Joint Board including a Chairman and Vice-Chairman, who shall perform the duties of the Ch. i rintn in his nb.sonc , along with such other Officers as may h d cmcc1 necessary or convenient, including but not limited ti a ftcrctary and a Treasurer, and perform all actions necessary t inenrporation Pursuant to Title 13, Chautor 81, M.R.S.A., including the adoption of ruics for the conduct of its meotinq €and its affairs. Officers of the Joint Board shall serve for a term of one (1) year. The Joint Board is hereby established and created to con- duct the cooperative unclertakinc! contenmiatod by this Agreement, and to exercise on behalf of the participating municipalities the powers delegated to it. Vacancies in the office of aiiy of the members of the Joint Uoard shall be filled by appointment as according to the re- spective municipal charters of p,ch of the Parties. 4 ------- 95 3.2 Mcetincjs. a. Joint hoard Mcc’tinqs sha]l he called as rsu nt to the P.’— l.a ’s ol the W it rvj1]c— Winslow Joint Sol’ Waste Disrosal Facility Corporation, which Ity—Law5 are ;itt-;ichc .d horcto as ppc.mcl x II and r’i dc a T)art hcrc’f. b. quorum f r any nh’et- i n j ha] 1 COfl j ! C) f at least tun—third . (2/3’s) of c ch of the Parties’ reprcsen tives, nd in order for a valid vote to ho taken in order to do business, all actions must pass by a two— thirds (2/3’s) vote of all members present; and if at any meeting there is only a minimum quorum present, then any vote taken on any action must he unanimous in order for such vote to be valid and for such action to pass and for the .loint Board to do business. 3.3 Powers. The Joint Hoard shall have a]l necessary, incidental, or convenient now ’r. qrant.c’d to l)irector.s of non—capital stock corpora L i ‘ns inc1”r Ti I 13, Chapter 81, M.R.S.A., subject to such lirnit.aLions as ar required by law and this . grcoment, and incluclinq hut, not limited to th: fo] lc)wi nij J)(Iwcr ; at I u ‘eli; il i I I I i ‘ ; , I n orcic r to accomplish the purposes stated herein and which are per— mit.tQrl by l;uw to b oxcrcist ’tl hv the Part:ic ; r pcctivcly: a. On behalf of the mrticinatinq municina] Parties, to purchase, 3eai ;e as lc see, rent, hold, niain— tam, operate, 1 ’ase as lessor, or convey any and all real and personal property or any easement or int.ere e therein a]1 as may be necessary, incic1i’iut 1, or convenient for its purposes. Owner. hjp of any ricjht, title, or interest therein shall be held by the Corr ora- tion unless some other nrranqcmcnt is determined by the unanimous conSent of the Joint Board to be more appropriate. b. To contract with any person, firm, corporation, or partnership, or other entity, private, public, governmental, or otherwise, for scrvices, management, work, matcr a1, or property in the name of time Corporation.- ‘S ------- 96 c. To adopt c r alter ru).es and regulations iind terms and conditions for the manage— mcnt of solid wasf.” and for the aclminis . tration, nd opc’ration and maintenance of the Corporation and its facilities. d. To cmp]oy or nrr n.;r1 for thu employment oC such persons as re required for the pur- poses stated h”r In! e. To receive and accept from, or contiact with, the Fk’ral, StaLe, and Municipal governments, and oLhcr public or private agc’ncies, for donations, loans, grants, or other assistance for solid waste management, and in any such ct ntract ;a’jrco to ho bound by all app1icablt provisions or Federal, State, and Municip.il statutes, ordinances, and regulations as the case may be. f. To make expcndit- irc for and contract with rospeet to capit 1 ñ items from funch provided to the Corpoi-at ic n Ur u nt to this %recment as stated herein. g. To contract with rnrsons, corporiit.ions, districts, other inunicipaliti , or other ] ccjal entities, Ii L Ii inside anil out. 1idc the boundaries of the Participatinj municipal Parties, and with the State of Maine, United St tcs Covcrnmont, and any agency of either, to provide for the ni .inagemenl. of 5Olid wante cit rates established by t e Joint Boards h. ‘ro receive and duthurse, on behalf of the participating municipal Parties, funct for any purpose contc!nlplat.ed by thi A IICCI O t. i. To license or qrant permits to users of the Corporation’s f3cilities on such termn as it deems proper. I’ ------- 97 • . To adopt or alter rules and rccjulations, and terms and conditions reqarding the types and nnounts of vtrioiin c1as ifjcatjons of solid waste which may he c1ispo c1 at. the (‘ rporat. ion’ 1a i Ii Lit :; k . L’o plan, cons ii net , equip, opc’ratc tn’J in.• i III i%ifl a SC)1 iii W 1 I V I1I.1I sI’J1 IIItII1 (IIUqJ Hfl for the benefit of 1h’ nuiniripal Parties, and any other p.i r t ‘ by iont r act. 1. To serve as a nuutu. 1 forum 10 identify, discuss, study, and brincj into focus the municipal Partir ’ solid w 4 :;tc I roblcm and needs. m. To serve as a vehicle for the collection and exchange of solid waste information ofcon— cern and interest to the municipal Parties to this Agreement. n. To provide continuing organizational ma— chinc ry to insur ” effc ctivc solid waste system operation. communication, dnd coor- dination, and c0’•cr;ition among thc’ munic- ipal Parties to this grecrnent. 0. To foster, dcvc’lo;. and review policies, pian , and priori L ; for the Corporation PAR’I’ 4. 11N NCE 4.1 Costs of Capital and Operation Expenses, and Appor— tionnient. Costs of acquisi U ons, improvements, and operations, and i lernz incidental thereto, sh t ll be paid for by fees collected from municipal commercial, anti/or private users, grants, donations, and appropriations and the sale of steam and any salvacjable maU?riLiln Irom such so3id waste disposal facility. Appropriations shall be allocated between the Partier in accordance with the following: ------- Adjustment to paqe 8, item a. a. Initial Capital Costs. Each municipality shall furnish their respective dollar share of initial capital con- struction costs upon reasonable and timely demand by the Joint Board. Half of the initial capital cost will be shared by the two municipalities in proportion to their population and half in proportion to their respective municipal valuation. ------- 99 a. Initlul Capital Cc’-ts . I ac1i Inunicipa]4ty shall furnish their re pccti doijar share of initial capital c’nnstructjon costs upon reasonable and t.im:ly dcnjthcl by the Joint floard accordinc, tc the r tit- of onc’—h 1f State municip 4 1 v.,1u ,i’ion and ori —half popu] a tion to i —h C :t ate nmnic:i pi 1 valuit ion and on ’—h 1 1 C p pn1 i tion. b. Subsequent Capit ii ;::pcnsc ;. n the event that a capital (:.pc’nIjturo ir requcstc.d to b made, the co f which in the Opinion of the Joint Roard i too great to he met from annual rcv ntu’.c clurinq the fisc;i] year in which such capital cxpcnditure is requested, the Joint Board sh.iU notify the participatjnq municipal Partios of the propn d capit j expendIture. ]n it not.ic tr th ’ participatjncj municipal ‘ rt ics , the Jc)I nt I.u. ri1 ;h; ii CICscrjb the project. for which I lii ’ eapi tal cxpcncjj turn is r tJu i red, the e:: I. I ui ted cw; t thereof , the term over which thr COSt shall be funded, the proportjonatc 5hnrc of the estimated co5t to be contributed by each earticipating municipal Party re jucstcd to provide such funds and the dat.c or dates upon which such funds arc to ho made available to the Joint J3o . rd. Such captt;ii funds may be provided by each participalj.nc 1 municipal Party in such manner as it shall determine, from available revenue funds, by tc xation, by borrowing, or othei-wisc. Each Participating municipal Party 1hifl promptly take such action as nc cens:i1-v to provide nch C IT,I ta] fundz and shal] notify the Joint Uoard as soon as such funds arc’ avatlabjo. Thc. notice to the Joint Board shall be accompanied by an opinion of coun c1 stating that the funds ha o b cn duly authorized and may properly be paid to the 3 iiit floarci or, if the funds L) re to J)t. ra I $;l’c I by lion owi nq , the notice to the 3oint floard ha11 he accompanied by ------- 100 preliminary Opinion of r( coqni oc1 Rond Cnun c’l indie ii inc1 that hy mieli n (lL3atj— fled opinion provnc the leqality of bonds or not ‘s 1 o he i :‘;iied for ‘ .i Id r’ lrposo can reasonably be c pcc:Led at time such bonds or notes are issued and that the net pro— ceecis may he ly paid to the 1 Thint Board. The funds so prnvich’d by th p irti ciIJatinrj municipal Partic shal] be used by the 7oint Board for the purposes for which the request was made. i ny surplu. funds not SO used shall be retuLned to the participatinq municipal Parties in the s mc proportion in which such Parties ‘riqinall’, Contributcd such funds. The proportionate !. harc of the capital expenditures to bc contributed by c’ach participating muiiirtpal Party shall be dctcj-rnin d by t.ht’ .J’’int I3odrd on thc• 1)flSjS of the per entflq(? of solid waste processed from such participatjnr 1 municipal Party on thQ nv . i iqc dun ncj thi’ Past pre— C( cl I f b i I r) %IX .CI four (4 ) years C. Apportionment of Dcht Retirement. The City of Watorvilic and ihe Town of Winslow, being the municipal Parties to this Aqrccmen , shall both raise their I rbportionate share of the initial capital invo tment for the construc- tion of a Solid W. stc Disposal Facility, and for any subscquent c nital investment pursuant to the above sectIon 4. 1(h). J ach such municipal Party sh;ilL be responsib o for the ret i rrnent- of I ti.; d.’hL. On an annual ba I ;, however, thcr shall be a proportionate adjustment of capital debt to one of the municipal. Parties, b scd UDOn the percentage of the previous year’s actual usage by each municipal Party. The basis 9 ------- 101 for comput.inq the annual debt. retjrem yj cost of each munir pal Party shall be the original cost of Jie facility, and the cost of any subsequent capital investments, to- gether with al] debt retirement expenses, with equal annu . 1 1ueLion amounts over a twenty (20) year p rioc1 to each municipal Party. When a rnunicip.il rarty’s usaqr increases or decrc’az;c,s from the oriqinal proportionate share, based upon the per- centage of the previous year’s actual usage by each munieip 1 Party, the differ- ence shall be paid to the Corporation with the other municipal Party’s proportionate annual contributing shire of operating cost to the Corporation tncreasing or decreasing in accordance with the adjusted amount. d. Short Term Borrowing. The Corporation shall only have the power to borrow by executing notes on a short Lerni temporary basis and for cash—flow purposes only, and the term for which such notes shall become fully due and payable shall not execc ci one (1) year, and which notes cumulatively in any one (1) fiscal year shall not exceed eighty percent (BOt) of the previous year’s operating budget, and which notes shall be paid out of income revenues during the fiscal year in which they were made. e. Mlocatjon of Costs of Operation. Allocation of all costs of operation of the solid waste management procjram to the participating municipal Parties Jiall ho accomplished on the basis of thc percentage of solid waste generated by the Parties and as otherwise herein provided, by charging each of the participating municipal Parties a uniform unit cost per ton of solid waste, which shall be so established each year by the Joint Board as, to the extont possible, will assure sufficient income to meet the cost of solid waste management. for the ensuing year. Such l 0 ------- annual opcratiriq xpenscs shall Also .iriclude unfunded capita] outlay, if any, insurance, taxes, rentals, and necessary reserves for COntincjcncjes as Lerminoci by the Joint Board but not t cxcccd in any yeai- five percc nt (5? ) of thr! total. opr’ratinci hud et. After thc? firsi Iisc,tl y ir of opc’r,-ltion hc n compi c Lc 1 • ;ai ci uni orrn uni t cc) t5 shall be compuLc’d on Lhc ba5is oC thoso amounts of sol iii Wastes 0c(’!5’cl hy each Party during th precedinq year with ad- justments mac1 , ii. any, t:() each Party for the next cstimawcl year of uniform unit costs. rol.]ot. ing the f r’l fufl fisr:iI y’ nr of npcratioi , said tInhfc)rm unil costs shall be computed based upon actual amounts of solid wastes processed from each Participating municipal Party in the precedinq year as ch t:c rmjncd from •1 int flo ircI rt.cords with and including adjustmcnr to each municipal Party for actual waste disposed in thc pro— ceding year. Th Joint l3oarrl may require advance nayment of such op rating costs for the first fiscal year of operation. 4.2 Di rilnit. ion of UrV-’IiIiC’S. Any ‘xcer s cv ’nn at the end of any Cisc il y’d r C,VI’i ,,ntl abovi wh i t i ucuduci to onorate the I’aci ii ty .shal 1 h’ di :thiirsc’cl back to each municipal Party as ctccorciinc7 to cdch Party’s actual waste disposed at the Facility in th preceding year. 4.3 In—Kind Contributions. Subject to approval by the Joint Board, credit shall. h• qiven to the Parties for in—kind contributions to time L’c’rporation. 4.4 Financial Procedures. a. Budget. The 1 in1. Hcard shall prepare a budqot, establish uner tc cs, determine rccornmr’ncled shares o costs, and transmit the S C to the Parties at least 90 days 1. 1 ------- 103 prior to the bcqinninq of each Party’s- fiscal year; and which C ]Cu1atjons shall also include an iternizec.1 C’StjTn U. of the expenditures and thri anticipated revenues for the fo11ow1n yc ar, all of which cal— cu]afion , 051 inmt , mid rc’porlF; shall be Submitted upon eomplc’tion to t-hc r sri cf-jve City and Town Coun i]s of Ihi: Participating municipal Parties. Such itc mizcd estimates of exp ndj tures and anti ipa t c1 revenues for the followinq yr ar shall include the following: 1. ltnticinatod Revenues. An itcinjz c1 estimate of ant icipatncl revenues during the ensuing fiscal year from each source. 2. 1 stimato of Exp nditurc. An itemized c stjrnatc of c’xpc’nclj Lures for each classification for such ensuincl fiscal year. Expend I t I1L CS will i ncliidc’ esti- mated Opcratjn j c’xymndjti,rcs and the actual amount of debt retirement, principal and interest, scbcdujcd for each municipal Party to this Agreement for money they have borrowed for Lhe joint Solid Waste Disposal Facility in accordance with sections 4 .l(a) or 4.1(b). 3. Actual Receipts. After the first year of operation, an itemized statement of all actual receipts from all sources to and I nc3 wi i nq .Tiim’ 30 ol (‘ach pr:v i n t is fiscal year. 4. Actual Expenditures. After the first year of operaL,nn, an it’mi cd statement of all actual Qxpcnditures to and includ- ing June 30 of each previous fiscal year. ------- 104 . F.stimated Cost. Pcr Ton. ‘hE’ estimated uniform unit c-o t per ton of solid-waste to be charqe ,.1 for the c iir.uinq fisCdl year. On or before Mnrr)i 1 nC c’m-h yc’;ir, the 3oin floarci nhall adr,,i .i j nal budqcL br t.hc up— comincj fiscal yc.ir wh icli ;h 1 l1 he i Lcmi ?.ed in the same manner ts th’ àstimat.c of cxpendjtures anti rt• ’eI1I1e . ‘Ihc. htidqot shall include the amount: of any doficit or antici— pateci deficit foi- the current. Year’s orcratior . Such budget shal] 1)0 submitted forthwith to the respective articipatjn municipt l Party’s City and Town Councils and shall include an allocation of (ho annual costs of operation, the determination ol which shall be pursuant to the section herein at 4 .1(c) regarding Costs of Operation. Jach partici- pating municip 1 - 1 Party shall nay not later than the fifteenth (15th) Jay of July of each year an amount of money which shall equal the ostiniatoci unit cost per ton set forth in said budget nmlt.ip] led Lw the number of tons of waste material dt 1iv rec1 by and on behalf of nuc h part i c i p.i t i nq imin i ti p 1 P.irt y to thc’ Corporation’s oiid waste disposal f cj1jtj s in the prccc’d inq n;nnth nr lelcrminccl by the Joint Board, but in no event shall such monthly payment be less than one—twelfth (1/12th) of the allocated ;harc ol such Participating municipal Party for said en— suinq fiscal yeai - b. Fiscal Year. The fiscal year shall be from July 1 to June 30 each year. The Parties shall make twelve (12) pnymentn to the Corporation, with the first payment due on July 15 of each year. c. Audit. The Joint floard shal] OnJaqe a qualified public accountant to conduct an annual audit of the Corporation’s accounts. The audit shall be conducted on the basis of auditing standards and procedures proscribed by the State Auditor for municipalities. LI ------- iOS I’A, r 5 . r’uoI’I :I TV 5.1 Title. The Corporation shall hold title to all real and pcrsonal property and any leasehold interests acquired pursuant to the purpo ’s for which it is formed, subject to the foliowincj: a. In the ovcnt a site for any facility is acrjuircd throu h cx r tse of thc power oC t minent. domain h u y one of the Parties. then the I’arty so L tking shall retain title to the property taken and shall lcn e or donate the use of such property to the Corpor ntion. The terN of any such lease shall be the term of this itqrccmcnt or the use u1 life of the site as a solid waste disposal facility, whichever shall first occurs The L,essor Party may elect to receive in-kind contribution credit for the costs of acquisition. IC th l.( ssor Party does not. sc elc’ct , the oLh Party may pay amounts which in num equa L the cost of the taking less the hes ot- Party ‘ ; proportionate share, p yrnc n t ;ha ri t I i n a io rcl.i nCc’ vi lit the l4ipo r Li e iuien L sec L Lons hereinabove • or such other method as th Parties shall agree to. 5.2 ImDrovemeflts. The Corporation shall develop and construct all imorovements, kc’c’p the same in good repair, and shall insure all properties ztcquirocl by or leased to it. . 3 Disl.ri hut i n 01 As!;c’t S and l.i.ihi lilies. Any Assets and/or Liabilities of the CorpoLation rcrnaininq at the time of termination of this Aqreeiiii nt shall be divided among the Parties accorriinq to ii ir proport ionate payments or contri- butions to the Corporation durinq the final five (5) years of this Agreement, subject to the followincj: a. Upon termination of this Aqreemen all property, real and personal , acquired by the corporation shall 1)0 offered for sale to the Parties at the market value of such property. Property not purchased by the Parties shall he sold at public auction. 111 ------- 106 b. Upon termjn -itjo, 01 any ]c’ se under seEtjon 5.1(a) h( rc1inahov ., thr other I’arty shall retain a claim the O n r municipal Party for a sh n- ’ of thc’ Proc cds of any resale of such 1tncl or, should the owner municipal Parts’ elect to retain the land for other pub] jc, n s, it. shall hriv two (2) years to pay th .’ other Party for its interests in the land. C. Thc right, ti.t1 4 and intr re st. of the par- ticipating munir:ip l Parties in solid waste disposa’ sites whcin exhausted of their capacity and of no urthcr u e in tho accompljshm , t of ‘h purposes set forth herein shall be cnnvc yed at no charge to that particjpz tjnc, municipal Party Within whose boundaries satd site is located unless such particjpatjncc ;nunicipa] Party does not dosire same. Piu ’r C. ITRSONJ41:T 6.1 Employment Status. ‘The Joint Board may employ such persons as it deems necessai’• t ’ accomplish the Purposes of this Aqrocmcn . ny such emplny( os sha’l be cmp]oycos of the Corporation and shall not b deemed to be employees or subject to procedures, sIIpc’rvir nn, or rules of any Party. The Corporatio 1 shall be solely liable to any such employees for any liability for cotnpcnsaij. on or indemnity for injur ’ or sickness arising out of or Jr the course of their emoloy— mont. a. Staff t imc may I)(’ c. nt ri1)IILc (j to thc Corporation by the Partien. Persons p rformi ng work under such con Lribution arrangements shall be under the Supervision of Lhc Joint Board .r its dcsiJnatc d super- visory porsonnc], but sliaJi otherwise retain the st 3tus of an uni;Joyee of the Contributing Party. jr ------- 107 6.2 Salaries and Benefits. 9’he .loint Board shall have the power to fix comncnn.-it inn and to determine any benefits for its crnp1oyo s, rnvi Ic..1, howevcjr, that such compensation and/or benefits ar not substnntially at variance with the comnonsation and/or benefi.t.r of cmploy cc of the Partic who perform similal- dutics. 6.3 Rules. The Joint floard shall establish rules ar 1 d regulations to govern its eInplofC cS in Lhc pt’rformance of their duties, which rules and rcqulations m iy include job descriptions and grievance procedures. 6.4 Hirinci and Termination Procedures. a. The Joint Board h t1 1 c.ni r ndvcrtj s( m nts to ho placed in theal publications for a period not loss than rirtoc -i (15) days prior to application dc 1 icllines-for any position created or opened. Applicants shall provide such references and other information as the Joint Board may require. Applications shall be considered without regard to race, color, creed, national origin, political affiliation, sex or aqe over 18. Applicants shall possess such qu ilifications as ioint [ bard shall os tab ii s h. b. Tcrminatjc n of t’inplnyment ;h i1 1 he for good cause and shall follow nn ice and opportunity for hearing. PART 7. R1:IiEn71 5 7.1 Breac-h. A Party shall hi’ (1OC’TfloCl to be in broach of this Agreement if it fail to appronriate or make timely payment of its share of costs, or if it fails to ucrform or comply with any of the terms, provisions, or conditions of this Agreement or of the By—Laws of the Corporation. The Joint Board shall cjivc a Party written notice of specific arts or omissions which const tuto broach. The Party so 16 ------- 108 notified shall have thirty (30) days to conform. if the Party fails to conform within the aI)c)vc’—mcnhionecl time period, or if the Party waives :hc time pr riocl, then this Agreement shall be decmc c1 rc cindt d, rrvokcd, or otherwise discharqed and disso).vecl ari 1 t.he abovi’—ment. iflflc.,C1 Section regarding Distribution of 7 ssc t$. rh ]1 app’y c lOnq with eetrh section or (his Part 7. 7.2 Withdrawal and/or i3rr’ach. 1 ny Party which breaches this Agreement or which m. y withdraw from this Agreement shall be subject to the following: a. A participating municipal Party may withdraw from this Agreernont at the end of any fiscal year of the Corpor ttion provided that it has qaven the Joint Hoard at least one (1) year’s written notice of its intention to do so. The wjthdrawjnq Party shall make any payments due during such period. b. in I_ho c1vi nt I h wi thih- 1 wi n’j Party fails to comply with subsection a. aboVe, it shall pay to the Corporat ion an amount equal to i ts share of co t- ; du throttqh the followincj Corporation ti c a year. c. The withdrawinq auci/or breachinci Party shall convey to the Cnrpur tic,n sufficient riqht, title, or intei-t- t in the property held by the Corporation to insure unfettered use for the purposes stated herein by the re- maining municipa] I iirty until the solid waste disposal site’s or SiLOS’ capacity(ies) is exhausted and of no further use in the ac- complishment of the purposes set forth herein, and after ich time the assets of th• Corporation at sucI site or sites formerly shared by the Part-ie 3 ,ur ;tIant to this Agreement shall be distributed Pursuant to the above—section rcgarcIinq t)istrihutjon of Assets at section 5.3. Furthermore, the I.? ------- 109 withclrnwinq and/’i hrc 1 whirtty Party shall — have no vested riqht to continuc to make use of any existji q solid waste disposal site or sites or fiu i]itics of thc Corporation, ci. The withdrnwjnc; and/or breaching Party shall pay to thc Corpor it.ion the entire amount of its share of any outstanding debts of the Corporation and of any lease payments due to any person, firm, corporation, or other legal entity leasing a solid waste disposal facility sitc to the Corporation, or any payments due under any other lc’asr’. 7.4 Corporation is ‘third—P.it-1 ’ flcneCi iary. The Corporation is hc’roby declared to be a third—party bone— ficiary.of this Agreement and shall be entitled to seek enforcement of any term, orovision, or condition of this Agreement. 7.5 Inc]emnjrjcatjon in C r of Liability to Third Parties, The Parties nqrcc to inth’innit:y each other for any liability which a Party or Parties may incur as a result of a suit against the Corporation arisinq ‘ut of activities Derformed by it for the benefit of the Parties, Any such indemnifica- tion shall be shared in accorc1an-r with the apDortjonment provisions as above-stated, or such other method as the Parties shall agree to. PART 8, ADOPT]QPI, ? MENflMEN 8.1 !)uraljon. This Aqic •cnwnt shall remain in full force and effect until either of the following occurs: a. One of the Parties withdraws from this Aqrecmcnt or is in substantial breach thereof, or the Corporation is dissolved; b. For a term of forty (40) years from its Of fective date. This Agreement may be ext.onc]ccl b .’ mutual aqrecment of the participating municip 1 1 ParLies, evidenced by a duly executed instrument in writing attached hi rc’to. 18 ------- 8.2 Adoption. This qrci m fl shall not take effect with respect to parties siqn 1to2.y un]css the following occurs: a. it has been approvc d by the legisla- tive bodies or the respcctivc City and Pown Councils of the Parties pursuant to their r spc ctivc municipal charters, and a n iority of the municipal of fic’i- thcrc of have affixed their sitjnauiros below; and b. It has been approved by the Attorney r,eneral and the M inc flepartmcnt of: Environmental Prott c:tion; and a. It has been filed with the clerk of each of the Parties, and with the Secretary of Stnt(’. 8.3 Review by Regional Pl nninq Commission. This Agreement shall be filed for review with the North Kennebec Regional Planning Commission at least thirty (30) days prior to the date of legislative or City or 9 ’own Council action by any of the Parties. 8.4 Amendment. This Aqreenw’nt may be modified or amended by the Parties in the .samc manner as that provided in section 8.2 hereinabove. Othc•r muniripalitios not original signatories hereof which wish to become partici- pating municipalities as parties to this Agreement may be admitted to this Agreement if thc 3oint Poard votes to admit such additional party, and the ]cqislativo body or the respective City and Town Conncils of the Parties signa- tory hereof accepts by approp)-iatc’ action such an additional municipality, upon that additional municipality’s legislative body’s or its municiDa]. off iet . r’s duly approved acceptance by appropriate action under anti pursuant to its municipal charter. and upon the terms and conditions placed upon such entry pursuant to this Agreement and any such further or other terms, conditions, as the Joint Board and/or the Parties hereto may require. 19 ------- 111 IN WITNESS WhEREOF, the various municipaljtjes, Parties to this Agreement, have causc d this Aqrc’crncnt to be executed and signed in their corporate n ni ’s by their respective and duly authorized OfZicers, the day nnd year first above written. - CITY OF W7 Tr.RVT1,1. TOWN OF WINSLOW BY _________ fly Approved: ALtorney ( ener. l Maine Department of 1nvironmcnjal J’rotectjon - - - - - Regional Planning _____ Commission 20 ------- i12 APPENDIX A ------- ‘Xatt’ t1 i±tuiiir APPENDIX A Certificate of Organization of Coiporatioii, tindci TitIc 13, Chapter 8! of thc, Revised Star uics, iud Aincndiiicnts thereto. r1 1 e i.isdcrs ,stiI. i.u ‘ ‘I put iiu i ii .i in pin .i ls ’si i iIiii . u. iiiii .,i ‘ 1.1: !V I .1!. C L Ly HaJ Buf Id i n m die tuwn ii i . !!. !Y !.!f I;iIt iii M.utw. i,ii i h’ . iI.iv ni ——. .. %. I). III . liii. Ii u -i Iii .s huh i i The nuise of asd tu 1 wii.st,. ,,i W. ! ‘rviI l —! ii Iow •! ‘ iii W .i: 1 ti l) ;’iis il •Faci I itv Cnrporatioi id o!pabra I !‘..•‘T.”. 1t t• 1 ” r J 1 ! • hut :uri Ls’prnim ‘ ..V.. tj L. gcn rai social wel (ari of the p.iri Ic 1p.,L in munir 1p. l’.irI. I u . , and ror :i Ii Jlrpi ’n•?. I’t•rm I ttt .•d by law, inn uJJi bitt n t 1 imi t i d in hirilvid ill,: liii iii- iii !;IH :;:I I • ‘ I s il iii wast • ; t ad within the turIl ° the part liip i mutt iiijml it to Lls Wit trw tile—Winslow Interloca] &ilid W stc Agreement, which ngrec ’menL Is ;ittarhed htritn mid m;ud part hereof; and fo providing for the disposal of solid wasts’s gi•nvr.itid within tIu. territories of oUter indi- vidual , ci rpnra t lone; • or mon ic tpa lit I i ; wit jilt may ht ’enhuIL• part I v . to such Agrcemen t or which may contract with the participaiiiig municipal Part ics Lu such Agreement for the use of such Corporation’s solid waste dispi’ ;u1 f.ieii i i (is; and to organize, operate and main- tain thereby a joint Energy Recovery F.ii’iIlty; :ind fir : 11 I Purposes permitted under Title 13, Chapter H I • l. K . S .A. , Co rpiira e ions; Wit unit t Ca1i I at Stiei k ; and to dii all t ii itigs whti c i i are r ca ’ onahk to carry out and perpctu:ILC all ol nun, purpo. es, Including but not limited to hold in); or a qui ring, impriw tug, opi’.-at Ln#, el ii op. rnnv v infl, assigning, mi rtgaglng, or leasing :iny real or Pt’rsnn.i I propert v • and borrow iii money :ind ing suck evidence of Indebtedness and Buchi ron(racts, .igrevini’nt ;, and In:4trumeiiLs as authorized by such Ibtervi] l —Wins low .loint Solid Waste A 1 ;rc’i’mi ’iii ;iuid C ’rp4 ’raI Inn Ry—J.aws attaclit d hereto and s de a part hereof, and to t ’ ecute and d ’l iver any imlrtgagt ’, dt’cd of trust, assignment of income, or other security Inst ritment in eoiii io tinit I hcri.wiLh. hiring personnel • contract— I n ; wit Ii 1)1 her lcg.i I tnt II I en • :iiiii all of :is ,h, iii I I. i piur;’mn.,: • (‘i’wirn , anti I ii i nu; ; iwc:wu;ary or apprupr tate or cunven I wit (or car r I ug Oti :md s’xori Is I its’. :t ii of such fnrc n I ng put r— poses anti powers a; sta I i ’d huirt’hy, or si .s i’d or ant hi r I .vd or imp 1 ir iL Lii the W a L ervi lie— Winslow interiocal Solid W.ist Agrt ’imi ’ii anti Liii’ Corporat lout 8y—law . at Larlued hereto ;incl made a part hereof. Tb Is Corporat ion shall he a quasi —mimi r Ipal inrpnr.i L Ion, jul nr 1 y m’nt•d by the C l ty of Wa t cry I I I c and the Town of Winslow, aitti support cii by ituihi ir lurid:; of t hi’ inuni ci pal Par tics and by revenues produced and/or rt ’ciiv ’4 fr .,m cither users by contract with the Corporation. The regulation of the intcrnal QffalT!: of the Q’rpnrntitun, rnd ihastribution of assets on dissolution or final liquidation shall hi as aci-ordin;; to thti, Watirvi l1c—Wjn 1ø Interloca] . Solid Waste Agreement, and the Watervilli ’—Wjns l ,tw .loint Solid Waste flispw i1 Facility Corporat. ion h y—Jjiw , both of vii li-h art’ as I .irlu ’ul Iu’rt’t 0 auth mwhe a t rL hi•reuf The na and place of address sif each of liii’ luws ’rporators ilFi! ns follows: Paul R. LnVerdlcrc, TLuynr fluvici Ilt:utr City hail Building Ch.ilrmnn of Wln iow Town Council Common StTCCt . Coosiridgo Lane Waterville, Maine 04901 hlnstow, Maine 06902 Robert V. Palmer, Jr. Edw.srd A. C.1 1 ;non Vaterville City AcIwliulstr itor WInsitiw Towit ftiua ;vr City thai ] Building Nis.uic1p ?kuildtiig common Street UaLnpvijle Pit. 0490t ((II Itiitti,n Avesus, — Winslow, Ph’ 04902 ------- 114 A P PE N D I X B ------- APPCNDIX B or WATCRV1LLC —t’JIN5LO ,J JCIIT OLI UASTE DISPOSAL FACILITy CORPORMIOr j ARTICLE I Off ic Section 1.01. Principal Offjcc’. The principal Office of the Corporation in the State of Iflaine shall be located at W corvi1le, County of Kennebec. Section 1.02. Rngistcrt’i-J ufric’ and Itqcint. The Corporation shall havr anti Continuously maintain in the State of M3ine a rer)iste.LI d office and a registered agent whose Offj e is idontjco l with such registered office. ARTICLE TI Board of Directors . Section 2.01. Cencral Powers. The affairs of the Corpor3tjofl shall be managed by its Board of Directors known as the “Joint Board,” Section 2.02. Number, Tenure, and Oualificatjona. The Board of Directors of the Corporation, known as the Joint Board, shall be tu,o (2) members of eAch of the Watervj1le...Wjns1o Interlocal Solid Waste Agreement party municipality’s respective City and Town Councils duly appointed pursuant to each of Such party municipality’s charters regarding appointments, plus each of Such party municipality’s City Administrator and Town mano ar, plun one (1) citizen—at—large for each ton thousand (10,000) in population for each of the rosppctjve party municipalities and wl ch citizen—st..1arq to I r 1 uly arpuintrrl by the re’ptctivo City or Town Council. Therc,fore, at thc corn— noncement of this Corporatien, and as according to acIi of the respective Party municipeljt ’9 populations, the munjcj... palitv of t’latorvjUc shall have four (4)mombcrs of the Joint !oard and the municipality of Wins1 w shall have thrari (3)membersoftheJoj,. 8oa! All terms of members of the Joint eoard who are City or Town Council members and the City Adminictrator and Town rnanager shall be co-torminous with municipnl office and shall hold such position as nambor of the Joint Board oniy (luring each of their preannt tc’rm! of office. Each end every citi7en .at...]arge duly apl)ointrci by each of the respective City or Town Councils of c’uch of the Party municj.. pa1itje shall be so appointed for alternating staggered three (3) year end two ( ) yenr tirms. ------- 116 Section 2.!’)3. C1 flj itj i, ’j1 tin n’• flc u1ar rneetjr s. Upon the effectjvp ctate of this Corpor tjon. o ns oor thpre.. after LiS i’os ib1p, ttir. Board of b’ ini the Joint Boarrl. ehall hold an Drgani?atjon r’nr’tino, e1 -r.t ri Chnirn ri and Vice— Chairman who st-all rprforrn the “utic’s nf the Ch rman in his ahsc nce, elonn with Such othi r off1coi may L.r’ iJ, ”rnr r1 flPc’•nscry or convenient, inc1u ing but not limited to 3 ! ‘crct iry rod Tr a urt r, and pc!rforn all actions ner.c sSory to lncorpor..tion pur L,rr;f. to litle 13—B, rn.R.S .i ., jncludjno the adoption of zules for the c:ond’ict of it mectjn and its affairs. ti rugular ;*ruit,nl L tjnr (pf hr Joint Eoard shnll be hold, with- out other notice than the ;e By—Lows, on tic ________- day of at thc’ City of Watervilic Council Ch rnbprn. The Joint Ooard iiy pro- vide by resolution and without other notir.o than u h resolution, the time and placf.’ for hu1djui , rictiljtju,;zjj rf. qul.’r I”P tirfl of the ’ Joint Board. Section 2,04. Sp cj 1 mr’tin,•-. Special meutinos of tht’ Joint 3oarri may b called by or at thu request .of the Chairman, or .h ll be callr,t by tho Secretory at the rctque5t of any two (2) mernbert o t.hi’ Joint Oonrd , Th authorized per’;or. or persons c;sllin; a sp cia1 meetinq of thp Joint Board may fj> th timr 1t1i the pl;icr’ of ruch S oci ’1 f eeting Unless by resolu— t ori t o .‘ojnt Board has deemed nthprijj -p. Section 2.flS. Notlr.n, Iotir., of ;sny Spor.j: 1 F cetjun of thi Joint 9o riJ ! ho1l h qivon ot 1ea t two (2) days Prc!viousiy theroto by t’irittc’n notice delivered pl r on 11y, or four (4) days noti ’.r Sient by tmil or tr’legrom, to each mc’ bI r of the Joint. oarii at l’j ’. showr, P,y ttit’ recorth of the orporation , If mailed, such nutic shall b doomed to be delivcred whan dr )nr jte ; in the t!nttcd 5t tus ‘lail in a SPF,lcd onvelooc so addressed, with u’o!;tncjn tiwri•rn rnpoirI , IF notir.c be qivon by telc’ r;.m, such notice shall be rienmud to be rteljvnre,d when the tele- gram io cIu1ivL rr’d to the tulonr;u’h (IP t :fly, tiny mcntt,er of the Joint Board may waive noti:e of any ru ‘tin . Th tti’n.j; n of a me bar of the Joint Board at any meetin:; ! h;1l1 con!;tjtUtp a I’.aju r of nutiw of r.%.’ctt meeting, cxce t “ihern ; rncm’ ’r uf thu Joint Ooaz -d attends a meoting for the expruss purpose of objc r.t.jnt to thc’ tr ansactjon of any busint’o ; becau’;o the mentjnq j.: not: l;ii”fully or “ropcrly called or c nvenpd, The business to hc’ trnn: nct,ut at the n.eetinq need not be specifind in the notice or waiver of notice of Such meeting, unless specifically required by law or thrr r fly—Laws, ectjon 2.06. Quorum. A Quorum for tiny m c tinq sh ill coimist of at least two—thirds (2/3 ’s) of each of the dolnr);I tjn,1 or ri rsrr aentntjye members to the Joint Board of each of the municipajjtj , Tti PCctivr ly, Which am Parties to the “Iatnrvj11o_’ Jjns1o ,,, Intnrlocal Solid “Ja!;te Agreuman , — ------- i17 Sectiofl 2.07. I ’3nncr of Ar.tiriq. In ord . r rot s tn!lid vote to br tnk,?n in orrf.r to do bu’31n05S all oction must i t i by a tu.ci—thjj 1 (7/3’s) votf• of_all mom Jc rs of the Joint oar’I Prc ent; anI if at any nnr tin thr ’rn is only minimum uorum prnsnnt. then any vote t kcn On any mat r must be unz n!mou5 in order for Such vritra to hr.’ v ’1ic’ flr for Such action to pass on’s for tho Joint L oard to b hu1iinr .:r.. Section 2.fl . Vacanejec. Vocanciac in the Dffjcr cif any of thr r”, t ‘ “ . c the Joint boorci Is3l1 b€’ filicri by ar1pojnt.m t nr ;ccordjnr 2 t thç rP’;i1r.ctjvr municipal charters of each of the rsIunjCinnljt i? , t’ hich are porti 3 to the t iat rviUp— inslo ’, lnt rhmal Solid “J3’ t’ t grr ment. A mem- ber of’ the Joint oard appoiriter: t r l] ‘Jr cflflcy Oh jll be so opg ojn ci fot the unexpjreij ter’ Qf hio prr’k r e or in offjc . Section 2.09. Co’ ’ien tjon. Pembers or the Joint roard h l1 nol !er oiw’ any compen: tjon for their iervirna n dirnctorr . Section 2.10. Absence from Meetings. Any member of the Joint Conri “io i b’ r nt from three (3) con- ccutjv rneetin s without GXCLISI’ utisfoctorv to tti” Joint Loard shall be dnnmc i to h vr, iurrc’n(hI’r,fd hj’ offlt:r’ ;i ; a member of the Joint Board. Section 7.11. Residuary Poworn. Th Joint Eo ’rd hr:lI hiyr the rc”tcrs and t utir s n r.r . ary or a epprorrj tr for the administration or the off j of’ the Corporation. and including but not limited to the poi’icir’; qrr.ntcd to the Joint Board by the W3ter ,i1Je ’jjns1n ; Intririncal Snlid inntn Agreement, oxcept these pecifico11y grantuth or it ;r rus ci by law, the Certificate of 0raanjzatior those By—Laws, or the Watervills—Wjnslow Interlocal Solid Waste Agreement. Section 2. ’. Removal From Office. A member of the Joint 0oz r’I m: y be remounci from Office., for cause, by vota of not le:;s than th:ec—fourth (3/4’s) of the members of the. Joint rioarrl prnsent, unlr”r. th,r ’rr ’ i fl minimum •luorum nr. ent ‘ horeby a unanirnouc vote sh; 1l be roquirnrt as acr.erdinc) to Section 2.07 abouc, and proviclud in nny co that noticn of such Proposed action shall have been duly qive.n in th! notice of the mectinr and provided the mombor of thi.’ Joint OoarrJ hoc been inforrie.d in writing of the charges preferred against hin !t lra!.t ten (1(i) days before such meeting; Such charocs pri’fnrre.d aqain!t any such member of’ the Joint Board may be brought by any mnmhc r or members of the Joint 803rd. The n.v mber of’ the Joint Board InvoJ ’jr ’iI ;Iin1l be niven an opportunity to hc . Pi : d at such r.ioctinr 1 . —3- ------- 11t’ III . 2fficer . Section 3, 1J• The Officc.,r5 of thc’ Cori’nr tjon I 1l hi- rn rnl n -r of th Joint Soard und h ll iriciu e Ch iriii n, zi Vir.’ —Ch jrrtmn t’iho .hnlI rrr?cjrm th2 dutio of tt.t Chnl rr in iii l•i -. ib -i’nr:”, ;i c crc.1t ry, onri ; - Trsc urr r, olony with such other Cffic:c’ ;i in y b rrrncrJ necc scry or conv .nient; Such 0ffirnr ; tLp h.uvr’ thr tiithcirity of :‘r.cI r,’rform thr ‘futir irc— crit.ed, from timn tn ti, iri, by t.I.. Joini. lnrul. Th Cffir.rr . of Socrt2tury and Tr t!.urIer m:iy hr rn ;’ ’ i rL’ii ;inri hr I by onr p r on. Section 3,fl’ . lr’ct.jon n ‘ Torni of Ufftrn. Tho Off r’ro of th- Cor ’iorntjnri ri.cifiritI in :;r tjon ,Ol h31l be nlei to(I from thr u’ .ihr r ;hfp of tl’t’ Joint oarcJ by th Joint. aonrd at itc 0fl0u3) mr. ntjni, or a soon thrrnaftpr n po ible. i ew 0ff!crr may be crnatnc and fjtlr’,J it any mrntin of th Joint P o ’rd. Cacli Officer shall hold offir.r until t.hr nr:’t annu:,l meeting antI untfl hj ! ucccaso shull havi’ Iwpn duly lrct :tnci shall have qualifjn , A Chairman of the Joint Board shall not serve more than three (3) consecutive termL of office, Election -of t fficc’:r, shall bri by v ritt-,n L ’ i1r-t c 15;t by qu lifjcc1 mcribnr . of tho Joint ‘onrri nr! n ‘cr.orrfjn. to tb n numbr r of votes necessary _y Snctior 1 :‘nd fl7 r.cCtjOfl Reriov;’l, Any Officcr elnt;trtl by thr- Joint 1o?lrri r ow.’t! by the Joint ocrd by vote of not lrn than thr —?oiirLh (3/4’s) of the msmb r of the Joint Conrd prn rnt, unlr thr’rn i a rljnjfl:um ‘)uorurn present whereby a un nimoua votr ‘;hnll be r quircr as acr.ortlinri to Section 2.07 abovr, wherwvor in jL juclqrnrnt th bn t. ir ternsta of the Corporation i iould br rv iI thu rr1by; but L;uch removal sh il be without prejudice to such jicrr.on in hin or hor r.a’acity a! a m m or of thr Joint board . !.nctjon Z.” . Vacnncjns, A vscancy in any Office b c itrn’ of th’ th, r’ .i n tjon, r?oot l, cliraualjfjcatjon. or c.U.nrwi ..., --z y hn fillr’tI by tlv Joint Board for thc unnxpirnd portion of the tnrm by th rune procI dure u! ed to elect the oririin tl Officer. -. Soction 3.P5. Chairman, The Chairman oh ]1 be thri princi” l rxr’cutjvc’ officer of the Corporation and shall in ‘ien raj control the business and ffeirs of thr Cor ’nr;’tjon , P’e ah; ll nresjdp at all meetings of the mc ibc’rs end a? the Joint roarrt. He mey sic n, with ------- 119 attoctation of or nlonr t’ijth- t.hru ‘ nr.ri’t;iry or nny othrr proper Orficor of the Corporation authori/eti by thc! Joint flonrd, o without any such attestation or co—’ iqnaturc’ r r c directed by the Joint Board, any deeds, mortgaqes, bonds, contracts, or ott c r in tru,rpnta which the Joint Board authori7es to be oxecutni , nxcept in c cs whcrb th irjninq an execution thcrnof shall be exrirosnly dcilrgaterl by the Joint Board or these By-Laws or statute to nm- otl-’er Dfficrr or agent of the Corpora- tion; and in qonerel he shall nrlrfnrni li dutin:. in:irlp.nt to th O??j of Chairman and such othi r rJuti’: a m y by’ prescribed by the Joint oard fron time to timr • - Section 3.06. Vicr Chairman. In the bsnncu of the Ch:jirman t ’ in thn cvr’nt of hi inz.hility o refu z l to act, the Vice Chnirman nha]1 perform t.hr ciutic of thu Chairmen, and, when so acting, sh ifl ha’j nil cowers of and be subject to all the restrjctjor.a upon the Chuirnnn, Any Vir.o Chairman shall perform such other duties as from tinin to tSm may be ac igned to him by the Chairman or the Joint floarrt. Scction 3.07. TTU L,TflT. Thp Treasurer shall j r i bonn for th fnitliful di charoe of his dutic•s in ruct, sum and with nuch surt ty or sureties as the Joint Goerd shall determine. Un shil’ hr u crv!r end custody of and be rucponeible for all funds and sr curitir” of the Corcoratjon; rscc’ive and give rnceipts for moneys due ir.ri r syz blr to the Cor’,oration from any rource w.’latsonvcr; deposit or in ,c t all such moneys in the name of the Careoratjon in such henks, t.rust ccnnar;ie s, or ether depositaries, or in such notes or bonds i s sh ll be ! e1 cted in accordance with the proviEjons of Artir.le VI of thr By—Levis; and in c,nn ral perform all duties incident to the office of Treasurer end such other duties as from time to time ; ssignod to him by the Chairman or the Joint Board. Section 3.00. Secrcitary. The Secretary shall keep thr minutr. s of th mentings of the Joint Doord in one or marc books provided for that purpose; see that all nctiees are duly niven in accordance with the provision3 of theer Ey Laris or as roquirud by law; be custorhien of ann ne that the Seal of the orporation, if any, i . fixed to eli ciocunents the execution of which on behalf of the Corporation unr r its seal is duly author- ized nd roquirnnl, if at nil, in ncr.orrfnncn with the provisjon of those 0y—Lnt’i , by law, or by the Joint Board; anti, in gencral, perform all duties incidient to the office of 5t’crctary onif such other duties esfrori tLliaL’ to tir.it mey be assinned by the Chairman or the Joint Board. • Section 3,09. Executive mananer If at any time the Joint ! oartI n!c”mr it flecr nary or convenient, it may appoint an Executive manager as the day-to—r’EIy upcrvi or and eOninistrator of the Corporation, end who shall bce responsibis to the ------- 120 Joint Board, and whor o rJutin ‘Thnll t r thcr,, e’ prescriborj by the Joint Board, ecu who shall b r.hoscn and nf’r’nir tnd by the Joint Board on the be is of hi executju and arfministratjue qua1jrj j 0 5 with special rRfcrencr to his actuni rlxpcrionce in, or his knowledge of, the duties and purposna o 5uch Corporation. Any_Person a2pojntfld to fill the position of Cxc cutivo Director, or any vacancy therein, shall have such term as the Joint Boarri fixr , but nO embcr of the Joint Board shall bri c’lic’jb1 tt, Lhj! pozjtion of Oxecutjve director exc as a temporary appointee. Section 3.10. Additional Pcrsonno l. The Joint 2oerd may from time to timc cmploy such personnt l as it deems necessary or convenient to ndmini ;tcr or as i t in dmjnjster in 9 the Corporation, The 5fl1nr.t.j n r nr1 compensatjon nd duties of such personnel shall be as dCtnrmjn fJ by the Joint Board, ARTICLE I V Order of Busint,s , Section 4,fl l. Order of usjness , The order of busjnes ; at eny re u1ar ; nnt. a1 or pocia1 fleeting of the Joint Eoord shall be: (a) floadinq and anprova]. of any uflapprovr!d minutes. (b) Rcpo t of Dffjc and Commjttc s, (c) Unfinj ht,d busjnrss, Cd) Now businosc• (3) Arljournnnnt, Section 4.02. Parli; ms ntary Procr,rlurc. On qucstioir of Parlinmtintary pror.ndtjrr, not covnred in those a rulinn by the Chairman shall rrevail. ARTICLE V Comr,jtte s . Section 4.01. ommjttoes. Committees not having and clxcrcJ inq the authority of the Joint Board as SPecifically prcscrited to the Joint L’o rd by the ‘Iatorvj11e Jjn 1øw Interlocal Solid Jostr Ac ronm”nL, by law, or by those By—Laws, may be designated by a resolution adopterl by the Joint Board, Except as otherwise provided in such resolution, members of each such Committee shall be members of the Joint Obarci, and/or Citi en .at_1arne who arc residents of either munici aljty which is a party to the ‘iatorvjlle— _‘,_ ------- 121 Winslow Interlocal Solid asto , ijrcnmr nt, and/or municipa’ officers of ofriciolo of any nuch party munh ip;i1ity t ouch Intorlocal Agree— mont. Any member of any ouch Commjttpc mny be reno sod by the Joint Board whenever in it jurJr mcnt thn hc ’ t int rooto of-the Corporation shall be sorvor by ouch removal, hut any such rr mov of any Committee membor who is aloo a member or thc Joint goard shall bb Itjjthout prejudice to such peroon in his or h r capacity as a member of the Joint Joard. Section 5.02. Term of Officn. - Each menber of a Cor:,mjttcp ohn ll continue as Such until the next regular annual rn etiriq of the Joint flo:rci ann until his successor is z Dpo iited, uninos the Commjtte :;hnll be Sooner termjnat, d by the Joint 9oard, or wsleoz thn Corsimittn ‘ xtendpd f r a longer period of time by rc olutjon of thn Joint ‘oarr , er unlcoo Such mc ’ i5cr of a Co!nrijttCf, io r.ernovccj f o. ouch ConmittL ’’, or unlcoo Ouch member shall cease to qualify a ; a membclr of any SUCh Committec . Section 5. 3. Chairman. Dne member of each Coz,imjtj.n i h;ill br ;‘ppojntc rj Chojrenn by the Joint !3bard Scctjoi, 5.!’4. Vacencjr’r ,. Vacnncjo in the m r bt’ r,hj• of nny Coi,imjttni may be filled by oppointmcntz made in thc S mc nannrr ,a erovjnJc cj in the’ eo o of the Ori jin l 3p7ojntmunt of to :;uch Commjt (’.c!, by the Joint Board for the uncx jrP i portion or ti• octinn 5.05. Unleas otherwise provided in thr’ rPcolutj n :f the Joint EoarcJ designzitin’ a Committee, a majorjt.y of th ‘“hole Corn jtf r shall constitute a Quorum and the act of majority of the members prosont at a meeting st which a quorum i prr’ic nt shall b the act of the Committe’. !oction 5.0G. Rules. Each co.ii.ii ti o r. ay adopt ruli for it!; arm jovnrnmon not incon— aiztcnt uith t ’ r.3 !3y—L,’ i or with rulr’ ; :)(lfl:It (I by thc Joint floaird. ARTICLE VI Contracts, Chocks Dr’aozito, and Fundz . Section 6.g l. Contracts. The Joint oard r1 y auth! rj•.c my Officr’r or OffLcc ’rs, agent or agents of the Corporation, in addition to th Officers !3O authorized by these y —Lawe, to ntor into nny contriict or nxecute and deliver any instrunsent in the name of and on b Imlf of th CorporatIon; and such Quthority r.ay be gcn ral or confined to i inicific instance. -p — I — ------- 122 6•I • Chr’ck’ , Dr3rt’,, rtc, IU1 check:;, rlrnfts, ordr’rr for thri r y ’rnt r nancy, bori s, or other ovjcjcncric of ind ’b..’ dn or invc t,, t i i .j the norno of thc Corrior tjnn i ll ba, ;j )nPrf by such Cffjccr or Cf jcpr , eont or cnt of the Corporo jon, and in uch mannóras shell ft ’ time to time b ci trr .ini,cJ by r olutjon of the Joint Eoarci or a SPocificully Prc cribccJ y th. otrrvjll _ jn.,1oLP Intorlocal 3olid : astc Agreement, by low, or by th r r niy_Lm . In the Obsence OP such dctorminotjon by the Joint 2oz,rLJ, such in:tru -cnts shall he si nod by th TrCDSUr’r an J COUflt ! jqnr’ri by thi’ Chairman of the Joint oard. Sc tj n 6.0 . DCposjt . All funda of the Cornorotjon rhall b rIr’rn: jted to the credit of the Cor’ oratjon ira such Lnn:;r;, tru t cu. rmnj , or other deposita j s, Or in Such notes or bt ri a:; the Joint 9o; rd m y Select. Any invest- ments in any notes and/or bonds of corro -; ti’ mon y5 may be made, from time to time, only with such corporoth mon ys as arc not immediately fleCoSSory to ocerate or maintain the Cornoration, ann any such moneys invc sted may only b ’ inuesteci in rnnsnnz jn and prudent notes and/or 5on j In zi fiducIc vmanner. 5 ct1on 6.fl’ 1 Thc Joint flo rri r.;; y or.rrpt nn hr’hilf of the Corporatjon any contribution, rjift, bequest, or devise for the general purposes or for any ;pocjal Iurpo o5 of tii’ Corpr3r 1 )1.jt)n A :TICLF: 9oo!:s and . ccordz . The Corporatj n shall keep correct and conpiete books cnrJ records of account and shall also keep ninuti s of the Proceedings of the Joint • oard and any or it Co,,1mittrm and auIi —Com itte , anl shall keep 3t the re•Ji tc;cd or princj’m]. office record givinr the names and addresses of all mcmbc’rs or the Joint oard and of its committees and cub—Commjtto an.l nqc’ntr anil rmfJ1oy. e’; . All. books and records of the Corpozotj n may be in pc ’ctnrf by n” :t” iIj r of the general public or his agent or attorney, for any proper purposes at any reasonable time. Th Joint Doard : hal1 c une an audit of the records of the Corporetion to be made each yn r by coiipetpnt auditor. At TlCLf VIlT ri ca1 Yo r , The fi cal your of the Corr,oratjon 5h3 11 begin on the first ( 1 St) day of July and end on the last day of June in each year, unless cheng ’d or mnndcd by resolution of ths Joint oarc1. ------- 123 Se j1 . The Joint 3orr j tiny ;rov.( je Cnr inr.,tt’ St’n’• •‘.hi’h !;‘ll bf in for,, of n zinrJ h ilJ hn j,• jn’crj’)c’ ,I thr the n ri of tI CorOor:3Lj3r. :.ntl tIi! ‘,orr$ , “Cor- )r—tn ;ri , n iVer or ctjc. . !nnnov!’r nny iiutj .’ 1: rr Ii J:I,. : h ’ ‘, ivr’n un’-’ r ‘.1 provjjor of thc L u of thc’ t ,tr’ of ‘jtir ,r Lhr’ Ci’rtjfjcitc of O tIir y—Lr •’ of the Cor’ini-;,t!,,n r’ ivr:r th•r”or in VJrjt.LrII i noc by th:’ pnr!;ipri or “) u)fl: i’Iu 1t1ri ! tIi rt’to, IJhethc r h forc or after the tirno tat therein, h li rr m a cr1u.tv 1cnt (:o th’ givinq of such notjc0. m Z tt nd ric , of :ny fler:.on dt L! mectjn , or P1OCI. t it 1 ,1 in any ouch n:ticr’. or th r’uinq of any act a notjfjcd In jfly uch notice hn1l con’;t.jtutu a ‘jvt r of notice cxcnpt where 3 riy 3uch p r on attornt :i rnr”tjn-) or th !‘rr .rnt nt an ct fnr I:! :,r,! . pur o:; of obj ctj,iq to any such ‘nrL’tjnr , act, or d ir ; of b Sjn bc!cauoc Such wcc not ;‘ro;iflrly c :1l.r’uI or convened or tim nr ,, nt of The: ‘y—Ln•: may, from timi to tInt ,, bc, nlt ”r ri, orneflrir.cj, or ro—macj nnü :;rJo tu cI by Lh’ rneniher of thc Joint ‘3o ird at ny renu3 r influ l meetjn 1 , or at ny apnc ’) r.u’r,tjn, of the Joint Soard called for such urno , erovL.- e f, ho”ev , that no c’,ch action ohz,ll cr ge the tIrpo n of the Corporation .o ;r; to i,lpajr it o riohtr and Po” r ur.tli’r the Lr’, ; of the of ‘.nini’, or to waive Ony roquiromene of bone or any provinjon for th3 s:futy and Oc’curity of the PrO! erty ond fur 1 cf ; of the Cor! orfl j t, or to r!rs%rjv: rn” mc rnbcr of ti Joint eony j or any municjr,oljtw !hjCI, i a narty to the J3t_I r loij Intr rl , ;. 1 olid t !zi ;tr !%r rPrr n , 9’lthOut their Oxpre a oent, of ri mt-, rivi1Pn’, , or iu.1rnun.!.tjr’ th-n exF tirig. ot1ce of Ony maiCir 1 r), CrfQpt1flr , iltrrin’ 7 , :lrI’nPfr.uuint, or repc’ l of thc e y—Lr ”!c to be offt rn,; t. :in., ;.u r.tjnc 1 Of thu Jnint. . o;ird ‘ ,rifl b r,jvon not 1c than zc’ r n (7) n r.wr,’ than thj Ly (30) tiayo before ouch meotinc en ziell set forth : u i1 alt.’ration, 3rlr.ndnjnt, or rnpe l of cuch 3 y—Lawz icr c :j ALL ‘lEI.! D V THEcE SCNTS: that th undor:;jrpned S cretcry of the Corporation £i t’ntjfj ri in the foranoin y—Lai’io doo heresy cortify that the foreuoin 0 3y—Lni’ ,uer riuly adopterl by the Incor — porators and Joint oarri of ‘;nid Co?porr tjnn a fly—Lot of oauid Corporation, on th ______ day of ________, 19(11), ot a duly c;’llerJ and cOnOtjtutrd’m1etjn nd that they rio n i’s conotj .jjc the y—Lawo of sairi Corpor tjon. — — n’crf!t Jry (Corp&k nte 5n 1 ------- 124 APPENDIX 2 MAJOR REOURCE RECOVERY RISK AREAS AND GENERAL EXAMPLES Gordian Associates Incorporated ------- 125 The following section has been excerpted froiii the publi— c tion, Resource Recovery Plant IpIe entation Guides for Municipal Officials Risks and Contracts , compiled for the U.S. Environmental Protection Agency, Office of Solid Waste, by Robert E. Randol in 1976. It has been modified by Gordian to further clarify examples of risks. It serves as a useful guide in understanding the relevant areas of risk in resource recovery project implementation. Gordian Associates Incorporated ------- 126 1. Risk Areas Affecting Waste Supply Risk Area Examples Waste Composition New laws or consumer behavior can alter the compo- sition of the waste. Changes in the compo *tion of the waste stream, in turn, can: (1) lower the frac- tion or quality of combustibles or recoverab)e ma— - terials and thereby reduce the revenue potential per ton of input; or (2) increase the unprocessable wastes to be landfilled and, thus, increase the net cost of operations. Waste Quantity New laws affecting consumer behavior can cause sea- sonal or permanent reductions in the quantity, which, in turn, will result in: (1) increased costs to process each ton of waste (because of fixed cost associated with facilities and equipment); and (2) decreased total annual revenues and, therefore, re- turn on fixed investment. Jurisdiction If a jurisdiction decides to discontinue delivery Withdrawal of waste to a recovery facility, all the conse- quences of a waste quantity change, plus the possi- bility of discontinuing recovery operations, are felt by other participants in recovery operations. Generally, no public legislative body may bind fu- ture legislative bodies to continue to participate in a project (i.e., regional system). Competition from Resource recovery is undergoing significant tech— Processing nological change. If a new competing processing Alternative alternative is implemented and attracts some of the waste that could have been processed by the recov- ery facility, then the consequences are the same as those for a waste quantity change. Gorthan Associates Incorporated ------- 2. Risk Areas Affecting Markets Risk Area Examples Competing Reductions in the price of primary fuels and/or Materials Prices secondary materials may drive down the pricet for the recovered fuels and materials, thus, rethicing project revenues. If these reductions forces the project into a period of economic frustration, operations may have to be discontinued. Substitutability Due to changes in production processes, recovered of Recovered fuels and/or materials may in the future be less Product substitutable for primary fuels and materials. Al- though most trends are toward recovered materials, some are not (notably power generation where the overall trend is toward nuclear plants). The more likely event is that the specifications required of recovered fuels and materials by buyers could ex- ceed a recovery facility’s ability to produce. In either event, the revenues of the recovery project could be reduced and some of the- output may have to be landfilled. User Incremental Buyers of recovered materials or fuels may have to Costs make unanticipated investments in order to use them, or their operating costs may increase as a result of their use. These cost impacts may be re- flected in the price that the user is willing to pay for the products — or in demands on the recov- ery project for user—based investment — thus affecting the recovery project’s cost and/or reve- nues. Shipment Size Most producers require that raw material shipments and Frequency be scheduled over regular intervals and sized Requirements according to their production schedules. Devia- tions from these requirements by suppliers can cause production problems. If a recovery project cannot consistently meet the delivery requirements of its buyers, then its marketing contracts may be cancelled. This would affect project revenues and could put the project in jeopardy. User Requirements by users of recovered fuels or mater— Specifications isis for consistent quality could affect: (1) the operating cost of the recovery project; (2) the price paid by buyers per unit of output; or (3) the duration of the contract between the project and the buyer. In the extreme case of inability to meet specificktionB, the project may find its mar- keting contracts cancelled. Gordian Associates Incorporated ------- 128 Risk Area Examples User Location A change in the locations of one or more buyers of recovered materials or fuel could affect the net price (net of transportation costs) per unit of output and, in the extreme case, the ability-of the recovery project to service the buyer. In either event, the revenues of the project would be affected. User’s Financial If the buyer of recovered fuel or materials goes Condition Out of business or is unable to pay for deliveries, the project’s revenues will be correspondingly d 1mm £ shed. Legislation and Changes in freight rates and rate structures could Regulations result in higher transportation costs (and, possib- ly, lower net revenues) or in cost discrimination against a recovered fuel or material. Either event could affect both the demand for and the price of recovered materials and fuel. Contract Duration Marketing contracts may elapse before the invest— ment in the recovery facilities is recovered. This could place the project in a precarious position should the operator be unable to renew the contract or find new buyers. Gordian Assoc3ates Incorporated ------- 29 3. Risk Areas Affecting Facility Construction Risk Area Examples Delays Delays in the completion of construction aM in the start—up date can cause cost overruns in the pro- ject and necessitate the continued use of obsolete or undesirable disposal methods. Delays also re— - suit in an inability to deliver the anticipated output of the recovery plant to customers. Contract Suspension of a construction contract has the same Suspension consequences as construction delays. Increased Capital Increases in the coat of equipment or materials Costs during the facility construction phase can cause the cost to process each ton of waste to increase as a result of the increased fixed cost. If these increases are large enough, the entire project may be jeopardized if additional financing cannot be secured. Site Availability If it proves difficult to find and acquire a facil- ity Bite that is environmentally suited to recovery operations: (1) the project may be delayed; (2) the cost of operating may be increased, especially if the site is distant from the source of waste and/or the buyers of output; or (3) the project may be jeopardized. Gordian Associates Incorporated ------- 130 4. Risk Areas Affecting Facility Operation Risk Area Examples System Reliability Since solid waste cannot be stored for more çhan a short period, excessive downtime for the recovery system may result in foregone revenues from hater— ial or fuels tht otherwise would have been r cov— ered and sold. Likewise, inferior quality of re- covered materials could result in lower prices per unit and, therefore, reduce revenues. Either event could lead to cancellation of contracts for pur- chase of outputs. Either event also could require temporary use of a less desirable means of waste disposal which would add to the total system cost. (NOTE: The solid waste must be disposed whether the system is operational or not.) Economic Should the participants in the resource recovery Frustrations project find it impossible to operate at a reason- able cost, the project may be jeopardized with the consequences of: (1) having to find alternative means for disposing of the waste; (2) discontinuing or revising whatever services relied upon the Out- put of the recovery facility; and (3) satisfying debts to project financers. Inflation Inflationary forces may increase operating costs faster than revenues are increasing, thus causing the project’s net cost to increase. In addition, if allowable cost increases are tied to a national or state cost index and the index changes faster or slower than the actual costs, then one or more par- ticipants in the project may suffer economically. Labor Productivity Reductions in the productivity of labor may cause the operating cost of the project to increase or could result in an inability to process the target— ed tonnage per day. The latter consequence would result in lower output of materials end reduced revenues. Razardous Wastes Should explosive, radioactive, or chemically dan- gerous wastes find their way to the recovery facil- ity, the health and safety of the project’s labor force and the safety of the facility itself may be jeopardized. This could result in unscheduled downtime or even cancellation of operations. The consequences could include lost revenues, increased costs, interz upted production, and temporary use of alternative disposal methods. Gordian Associates Incorporated ------- 131 Risk Area Examples Legislation and Certain legislation, especially that which could Regulations affect waste quality (e.g.. mandatory source separ- ation), or facility design (e.g.. pollution control standards), could result in decreased revenues or increased costs per ton of waste processed. In the extreme case of removing a large portion of the in— - put to an individual subsystem of a resource #recov cry plant (such as the possible effect of beverage container deposit legislation on an aluminum recov- ery subsystem), the econo nic viability of that sub- system may be jeopardized. Waste Stream Discussed under “Waste Supply” risks. Quantity and Composition Storage Capacity If the storage capacity for incoming waste or out- going materials is not sufficient to handle emer- gencies (such as shut—downs, storms, etc.), then waste may have to be diverted to alternative dis- posal. This could affect project costs and revenues. Gorchan Associates Incorporated ------- 132 5. Risk Areas Affecting Disposal Risk Area Examples Site Capacity The capacity of the disposal site for resi dusls from the recovery operation, and f or unprocessable wastes, may run Out before the end of facility Op- erations, thus causing a need to find an emefjency disposal site (probably at extra cost). Legislation and Regulations may be implemented which require design Regulations changes for landfills (e.g., liners to prevent ground water pollution). This would increase the cost of recovery system operations. Site Location A change in the location of the site for land— filling residuals could increase operating costs by requiring a longer haul from the recovery facility to the landfill. Gordian Associates Incorporated ------- 133 APPENDIX 3 PRICE SUPPORT LOANS FOR MUNICIPAL WASTE ENERGY PROJECTS Gordian Associates Incorporated ------- 134 Price Support Loans for Municipal Waste Energy Projects Introduction The Energy Security Act (ESA), which was signed by President Carter on July 2, 1980, contains several significant incentives for resource recovery projects including price support loans. The objective of this program is to encourage the development of alternate energy sources which will displace fossil fuels, particularly oil and natural gas. Through the price support loan program, the sale of energy from a resource recovery facility will be subsidized during the early years of the project when its economics might normally require a tipping fee which would make it unattractive in comparison to landfill disposal. In later years, when increased revenues from energy sales improve project economics, the price support loans are repaid. Price Support Loan Program The amount of the price support to be disbursed to a resource recovery project will be determined as the standard support price (ssP) reduced by the cost of fuel displaced by waste derived energy, with a mazimum allowable support of $2.00 per MMZTUs. The SSP is defined as the world price of oil at the time of enactment of ESA, and will remain unchanged throughout the life of the program. For a new resource recovery facility, price supports will be provided over a seven year period. The full price support will be provided for the first year, six—sevenths for the second year, five— sevenths for the third year, and so on until, in the seventh year, one—seventh of the price support is paid. (For existing projects, price supports loans will be provided for five years, with a similar reduction in support amount over that time period.) In the year following the final disbursement (the eighth year for new facilities), the price supports will be repaid over the remaining planned life of the project (but not to exceed 15 years). The interest rate for the loan repayment will be determined following the final loan disbursement and will be based on the current average market yield Gordiari Associates Incorporated ------- 135 on outstanding marketable obligations of the United States plus not to exceed one per cent. Standard Support Price The standard support price (ssP) has been set at $5.37 per ) fBTUs .in rules proposed by DOE ( Federal Register , 9/25/80). If the fuel being displaced is No. 6 fuel oil or a higher grade petrolet product (as is the case with Keyes), the price support will be increased by 25% (to $6.71 per MMBTUa). Cost of Fuel Displaced The amount of fuel displaced can be determined by the following equation: Amount of fuel displaced — ( quantity of working fluid ) — (quantity of fossil fuel used) .85 The working fluid is steam or hot water and when multiplied by the enthalpy of the steam, h (in BTU per lb) gives the energy contained in a given quantity of steam or hot water. Using a representative effici- ency for a fossil fuel boiler (.85), an estimate of the fossil fuel energy that would have been needed to produce that quantity of steam/ hot water is obtained. From this is subtracted the energy used as auxiliary fuel in the secondary combustion chamber. The cost of this displaced fuel will be determined on a case—by— case basis from actual costs incurred during a base period of any 12 consecutive months during the 18 month period preceding any commitment on the part of DOE to make a price support loan to the project. Effect on Project Economics In order to illustrate the effect of price support loans on the economics of the Waterville/Wiuslow project, the probable amount of the Gordian Associates Incorporated ------- 136 price support loans for Alternative A have been calculated. These cal- culations use the following assumptions: MSW accepted by facility: 23,380 TPY MSW processed by facility: 22,211 TPY Steam produced per ton MSW: 5,800 lbs Steam conditions: 125 psig, saturated Enthalpy, h: 1,191 BTUI1b Cost of displaced fuel: $4.96 per )INBTUs (based on $30.29 per barrel in 1981, at 6.11 )OIBTIJs/bbl) Auxiliary fuel use per ton MSW: 0.3 BTUs The energy produced annually by the facility can be calculated: 22,211 TV! x 5,800 lb/ton x 1,191 BTTJ/lb 153,429 MMBTU Since the fuel displaced would be No. 6 fuel oil, the SSP can be cal- culated using $6.71 per !4MBTUs: 6.71 x 153,429 = $1,029,510 The amount of displaced fuel can be obtained using the following equation: ( 22,211 x 5,800 x 1191 ) — (300,000 x 22,211) .85 = (180,500 — 6,663)(106) 173,837 )OthTUs Assuming that the cost of the displaced fuel is determined in 1981 at $4.96 per MN3TUs, the cost of the displaced fuel is estimated at: Gordian Associates Incorporated ------- 137 173,837 x 4.96 — $862,231 thus, the maximum amount of price support loan is found by subtraction — SSP — displaced fuel cost — 1,029,510 — 862,231 $167,270 If the facility accepts 23,380 TPY of MSW, the price support loan amounts to $7.15 per ton in the first year of the project. The probable effect of price support loans on the proposed Water— yule—Winslow project (Alternative A) is shown in Table 111—1. A total of $669,112 in price supports would be provided in the first year of the jroject (1983). The loan payback would begin in 1990 and continue for the remaining 13 year planned life. The interest rate assumed for this projection is 13%, based on an average 12% rate for treasure notes over the disbursement period plus one per cent. The debt service for this would be $109,300 per year which repre- sents an additional cost of $4.67 per ton in the remaining 13 years of the project. The effect of price support loans on the disposal cost or effec- tive tipping fee for Alternative A is shown in Figure Ill— I. This cost is significantly lower in the early years of the project with price support loans, but it does not decrease as rapidly in the middle years. However, due to the effect of increasing energy revenues on project economics, the facility would become profitable only one year later with price supports than without. Gordian Associates Incorporated ------- S - 1 00 I ’ I —1 1O I 1983 . . V • 1988 V V V 1993 . p p p J 1998 p p p p 2003 I.- . FIGURE 111.1 EFFECT OF PRICE SUPPORT LOANS ON DISPOSAL COSTS FOR ALTERNATIVE A -p z 0 I-i 0 U 0 p4 ‘-4 — — — — — — = without price support loans with price support loans ------- 139 APPENDIX 4 PRELIMINARY EVALUATIONS FOR THREE POTENTIAL SITES I , Gordian Associates Incorporated ------- ROBERT P STEARNS. PB £ 1. CONRAD. PE r CURTIS J. SCHMIDT. PB STEARNS. CONRAD * 1 10 SCHMIDT MARK L BRECH R IISULTINC EN0INEE . INC. RODERICK A. CARR i ISODSLP E VAU.EYO VE MILES J. HAVEN PBSTOPI V 0 A22OO GARY I.. MITCHELL PB RONALD B. PERKINS. PB DAVID B. ROSS. PB DONALD U. SHILESKY. ScD JOHN P. WOODYARD. PB November 17, 1980 File No. A0280-1 Mr. William H. Ranney Gordian Associates, Inc. 1919 Pennsylvania Avenue, NW Washington, D.C. 20006 Subject: Waterville—Winslow, Maine, Phase II, Site Investiga- tions, Prime Contract No. 68-01-4940 (68—01-60001) Dear Bill: This letter and attachments constitute our output for Task 3, Site Investigations, Amendment No. 6 to the Agreement between SCS and Gordian. Under this scope of work, SCS was to perform an Investigation of three potential sites for the proposed re- source recovery facility and to determine on a preliminary bas- is the differences between the sites. The scope of this effort was as follows: • Preparatory work such as reviewing the files and previ- ous reports and developing a data form for collecting information. • A one day site visit to see the sites and to collect the information that could be obtained within the time avail able. • Limited follow—up telephone calls to obtain additional information. • Compilation of the data and preparation of this submit- tal. This report submittal consists of the following: • A data form for each site. Most of the Information that was obtained during the site visit is noted on it. • A budgetary order-of-magnitude cost estimate for site development for each of the sites. OFFICES IN RES1ON. VIRGINIA; LONG BEACH. CALIFORNIA. AUGUSTA. MAINE. REDMOND. WASHINGTON. AND COVINGTON. KENTUCKY ------- 141 Mr. William H. Ranney Page two It should be emphasized that these cost estimates are primarily for comparison and are intended only as a starting point. Ad- ditional effort is needed In order to more precisely define the work required in order to develop any of these sites. Also, these estimates reflect a conservative approach; i.e., some of these costs could likely be reduced by detailed Investigation and engineering analysis. For example, we assumed at the Keyes No. 1 site that water would be brought in some 800 feet from College Avenue, including crossing of the railroad tracks, rather than estimating lower costs for unconventional means of providing water. Further investigations and engineer1n should be authorized if this cost information is Intended for more than comparative analysis between the sites. For example, If the costs would be used for contract negotiations with the user, more definitive data Is needed. Furthermore, we recommend that further engi- neering Input be provided to the Northern Kennebec Regional Planning Commission to help this project to proceed forward. Historically, this project has had a lack of engineering in comparison to the amount of planning and meeting etc. I pre- ceive that if the project is allowed to continue to be drug out, the primary potential steam user will likely become impa- tient and develop alternative strategies for reducing their en- ergy costs. We welcomed this opportunity to provide these additional ser- vices to you and EPA and look forward to continuing to serve you all. Very truly yours, E. 1. Conrad, PE Principal SCS ENGINEERS ETC/sib End osure cc: 1 n Perkins ------- 142 PR Dm RY SI ISSN XE DP FORM, 1 YES #1 SI’IE WCA.TI( .• See vicinity maps, USGS 15 Minute Quadrangle, Waterville, 1959, Figure 1 City zoning nap, Figure 2 • Distance to user - 300’ to Keyes plant — Keyes to install steam line, incl x3ing constructing it ixider railroad tracks TEANSPO TI P? 4 CIO • Vehicles hauling refuse to site - Esti.nated 25 packer loads per day • Loads of residue - less than 6 per day • Distance to major road and condition of major road - 0.55 miles to College Avenue, which is a 4-lane arterial road. - Exit of f College Avenue is 0.5 north of Keyes’ plant - When traveling north on College Avenue, an 160° turn mist be made off of College Avenue. - When traveling south on College Avenue, a left turn of about 20° is required. - Trucks delivering refuse f cin WinslcI 7 can reach the turn off the College Avenue about as fast as by traveling north to the bridge at Fairfield and then traveling south on College Avenue, as they could by driving through Watexville and north on College Avenue. Thus, not all packer trucks delivering refuse ould have to nake the 1600 turn off College Avenue. — If Fafrfi ld and other to s to the north start delivering refuse to the facility, they will have an easy turn off College Avenue. • Trucks (packers delivering refuse and trucks hauling residue can often exit by crossing railroad tracks 0.1 mile south of the site and travelling through Keyes’ yard to College Avenue 0 • 4 miles away, when there are no railroad cars parked at the crossing. The railroad will not agree to keeping the tracks clear of trains. • ess road to site ------- 143 - 0.45 miles of 10’ wide a1l- ather road exists. It should be widened/ unproved to 24’ width and it ould be desirable to pave the road. This road passes within 60’ of 2 residences. - 0.10 miles of paved, 20’ to 35’ wide public road exists. AlthoWh paved, it appears to have been paved and patched. I suspect that the base c es not c 1y with cwrent road building standards. This road passes 7 or B residences. SITE DESCRIPTICI9 • cisting land uses — Industrial zoning and use. Keyes plant was built in 1903 at s location. — No )ax n change is apparent. The proposed site is currently mused. it is separated £ u the plant by t tracks of the Nairie Central Railroad. • Size of potent 1 site 260’ x120’ + • ner of site: Keyes Fibres, Inc. land to be leased Assessed Land Value $15,000 to $17,000/acre of raw land (Assessed Value = 0.93 x narket value) • Ttçogra y — Gentle slope (less than 2%) £ u the plant to the bank of Kennebec River • £S pole lines pass through the site. I think both lines have telepI ne and poker cables. They will both prrJ ab1y have to be relocated. • appearance of site. — Unused and kept industrial land cx,vered with wild grass. — No planting required as screening. • Drainage Requir Tents — Existing conditions and problans. Generally drains to the river and the la area to the north. — Required inpzov tents — ndnixnal. ------- 144 • Soil Conditions — Sandy loam , 2,500 psf al1o ble bearing pressure - Use spread foundations — Water table is probably ll below the site — river is 30’ below the site • Site grading requirertents - grade to provide drainage • Potential for vandalian - miniiiel - Keyes tries to operate 24 Ix urs per day, 365 days per year - Keyes has caretaker/guazd to watch their facilities -: No fencing required = Water • Purveyor - Kennebec Water District Waterville, E bd haan 872—2763 • Location of nearest public lines - 12” line and private (Keyes) fire hydrants on College Aven - ctension required - 800’ + incl ing passing tmder t railroad tracks (a casing xsuld have to be jacked under the tracks arid the pipeline jacked through the casing). — Connection charge — none • Alternate water s plies - Fire protection line - connect to Keyes’ fire protection line, which obtains its water £r. u the river. — Ash qj enching (procass) water —Install an intake in the river and p izp, or —Connect to the cooling water (for vacu in punps) system that Keyes has if sufficient capacity exists. Install a neter. Crossing of the railroad tracks uld prr l ly be required. U ------- 145 - Potable water, nnect to Keyes’ potable water syst n in the plant and install a neter. Jack a casing irider the railroad tracks. • Keyes will provide treated neke- water for the boilers. • Ca nection charge — no charge by Kennebec Water District. Se r • Q ner - Kennebec Sanitary Watexvii.le Sewerage District Treat iwit District Waterville, Bill Cu11€ rt I w Bl i r 873—06U 872—2763 • Nearest line and size — 24” or 30” industrial interceptor, 100’ west of site. It has adequate vol etric capacity. - Keyes also has a 24” RCP Industrial waste line, about 70’ south of the site. — KS D applies its sludge to land. Thus, it has stringent limitations on heavy netals. Pre-treatnent would be required to ove heavy netals £i xu ash qusnching. - A vol ite neasuring tructure would be required. - A site sanpier would probably have to be installed. — Sanitary wastes can be discharged to the industrial interceptor • Connection charge - none. Electric Line • Utility c tpany - Central Maine P zer Co. Watexville, ?‘E Gordon M P1’ l 1 873—4201 • Nearest line — Site is 150’ fx C PC substation which reduces voltage to 12,470v. This substation serves Keyes. CWC or resource recovery facility could build a line to the resource recovery facility and install a transforner at the facility to provide pager. This would involve a significant capital cost which can probably be avoided. — The 1 t cost extension would probably consist of extending a new line £ College Avenus arotz d the Keyes plant to the railroad fat i1ity, which would be about 800’ long. ------- 146 • Special proble!ns in neking connection. £‘ pole lines exist across the site. They nay require relocation. This site needs further study; it is rather 1 1icated. • Connection charge - No extension charge anticipated. A pole line re- location charge of about $3,000 might be required. Telep!X)ne Line • Utility Caiçany - New Digland Telepkxne and Telegraph Co. Waterville, NE Peter Go an 947—9911 (Bangor office for new non- - services) • Nearest line - There are two lines across the site which nay be usable. - Alternately a new line will have to be extended f u College Avenue. - ?A tionally, Maine Central Railroad has a pole line on south side of tracks which might be us hle for this purpose. • Connection charge - $3,000 estimated for extension and relocating pole lines. O1 R V 1M L FACV /PO1 TThL PIGB1 M5 Noise - Sbould not be a probl n, except trucks passing by 10 residences on the haul road north of Keyes. E missions - Ccxnply with State standards. Keyes would insist upon that too to ensure that DEP would not blaite Keyes for probl ts that the resource recoi exy facility might cause. — Refuse-contaminated drainage cannot drain to river. Containnent facilities would be m edpd. Nearby Residents/ andc ’iners — Trucks delivering refuse to the resource recovery facility n st pass close by about 10 residences. That could be a imajor prthlest. Wind Consideration - No problEn. ------- Ot} r - Special exception pemnit required to locate within 250’ of river. - The line separating t1 n of Fairfield and the City of Waterville passes through the Keyes plant, just north of the site. This is also t1 line that separates SaTnerset and Kennebec Q,unties. 147 ------- 148 / ‘ m è5; - ---S,, •11) •. ‘ ( , / . L j A1 - - I - -:! /• j S - ,4 ,, , - ‘r 4 Wth.w’.” :- 1 Ls .__ t.-) 4” t % ’ L i r 3 b t - . i..n.w - 1 , q - / 4 W R i . • ¶ / ¶ - 1* / ::,,y’ J 4 I) ‘ ,L ‘,i !i- ‘4 c f2 ? ‘ q 5 & 1n : 1 2OOO’ SQirce: US 15 mm. Quad., Tt tetviUe, ? , 1957 Figure 1. VICflII?i MPIP ------- Kt a 1 Loc Uon Locat on Scale: 1N=l000 S irce: City of WaterviUe Zoning Ilap, 1979 I 0 0 0 Fiqure 2. OC1 TIC MAP PI JPCS ]) RFSWR E REOCYtFERY FACILITf ------- 150 P RY a E FOR SITE PEEpJ RAI’Ia , KE #1 Land a uisition, Keyes to lease C1 ring and gr 4 ’ g - Clearing $ 500 Grading 500 Siltation C ntxc1 500 2 coass road Grading to wi i road to 24’, 2400’ length 3,000 Drainage culverts, , 150’ @ $14/LF 2,100 incinding end sections and daylighting 6” crushed stone base @ $5/ ton, 24’ wide x 2400’ long = 6,400 sy @ $1.60/sy 10,200 3” asphalt paving @ $16/ton, 12’ wide x 2400’ long = 3,200 sy @ $4.10/sy 13,100 Site Preparation Finished grading and 9” crushed stone base @ $5/ton = 4000 sy @ $2.30 9,200 3” asphalt paving @ $16/ton = 2,500 @ $4.10 10,300 Utilities ter 6” pipe, 800’ @ $16 F 12,800 nnection to existing Line 2,000 Jack pipe zider railroad tracks 8,000 Fire hydrant 1,000 S er 6” lateral, 200’ @ $l5/ F 3,000 1 nanhole @ $1,000 1,000 c xtçosite sarr ler 2,000 tering struct me 5,000 Electric Service No charge for ocnnection Pole line relocation 3,000 Telephone Service No charge for connection Pole line relocat ie 3,000 ------- Subtotal $ 90,400 ntingencies and engineering, 25 percent 22,600 $113,000 151 ------- 152 PR JD ARY SITE ISSA DATA FO 4, ITIES #2 SITE IOC7 iTIC1 -. See vicinity maps, USGS Quaxx3rangle, Waterville, Figure 1 ‘in Zoning Map, Figure 2 • Distance to user (s) - 3000 feet to main user - Keyes s.xuld bui]d a steam line ar r&uc!e cost of steam acoordinjly SPOP2ATI FACIORS • Vehicles hauling refuse to site - Estimated 25 packer 1o per day. • Loads of residue - Less than six truck lo is per day. • Distance to major road ard conittions of major road - 250 feet to College Avenue which is a four-lane arterial road. • access road to site — Perbie Street. — Patched up pavenent witlxxit good definition of width. — For p cposed truck traffic, repave with 1½ inch surface course. • Lard uses adjacent to access road — iinercia]. ard irxlustrial. SITE DESCRIPrI(1 • Size of potential site — Gross size of parcel is 280’x215’, bit creek throuqh it reduces useable acreaqe ard fill for parkir* lot to tbe west appears to be on the parcel. I , ------- 153 • cist rg laid uses — anercial (CC) zoning. - Used car dealer be zeen site aid Collee Avenue with partially paved aid paritally gravel-surfaced parking. - Was foimerly the site of the gas plant where gas was manu.facbired fran coal . - A large gas storage plant exists at the eastern edge of the site. It is currently used to store aid distribite gas. - It is assumed that the gas storage aid distribition f”-ilities will rBna.in in service as is, aid the p 1 o csed resource facility will use the r naurder of the site. Maine gas will likely not agree to this “sharing” of the site. Also, sharing of the site will cause the site layout to be difficult aid not as efficient as other sites. — Laid south of the site (across the creek) is l ,-1evel ccmnercial davelopnent. irther south, 1/4 + mile fran the site, is residenI-i l. The residences are gradn l Ty being replaced with irxlustrial/camiercial developnent. • ¶Lbpography - Gently sloping, 3 percent +, except parking lot fill to the west which appears to be partially on this operty. Pai]xoad tracks to east are higher. — 250 feet to piblic road. - Cordition of nearest t*iblic road: excellent - improve roadway to Coll e Avenue, 250 feet long by 28 feet wide. • Appearance of site — Site is grass covered. ees are on south side along the creek. — Planting re jiired as screening - ne. • Drainage Ra jiirenents - cisting coiditions aid probl ns - A drainage ditch is at the east side of the site adjacent to aid at the toe of the fill for the railroad tracks. A creek is on the south side of site. Ii . — Reu.i.red improvanents — t ne. ------- 154 • Soil conditions - up to 5 feet of fill on site. — probably sandy loam, like at Keyes, with 2500 psf ali. ,ab1e bearing pressure. — use spread footings. • Site grading r 1irGnents — Ratove uncxznpacted fill and recciripact. — Parove fill on west side of parcel if itional space is ne d . • Poten - 4 1 for vandalisu - I ccessible frau Ollege Avenue. — Install a 6 foot chainlink fence with barbad-wire guard. ILITIES Water • Purveyor - Kennebic Water District Waterville, Maine Tad hnan 872—2673 • Location of nearest lines and sizes (map) — 20 inch line crosses site, 20 feet east of west property line. - Fire hydrants cist on Coll e Avenue, 300 feet ± fran site. — 100+ psi static pressure. • ctension r uirenents - ninal • Connection charge - b charge Sanitary S r • CX.Jner - Waterville S ierage District Waterville, Maine Dave BThir 873—5191 • Nearest lines aid sizes — 30 inch industrial interc ptQr on riverside of C4RR tracks. It xsu1d be cpensive to jack a s ,er under the tracks. It could be possibly rcutad on the surface thra.igh the culvert under the railroad tracks. A 200-300 foot lateral uld be r frad. ------- 155 - 10 ix h sa ier on the south bank of the brook south of the site. A p p station aid force main or an invert sipl n would be reguir to connect to this line. A 200-300 foot lateral would be requir 1. • Special r jiirenents - Same as for Keyes #1 site. • Connection charge - None Electric Line • Utility iipany - Central Maine Power Cat pany Waterville, Maine Gordon McPhail 873—4201 • Nearest line — Transformers are on a pole on north side of site. Power lines are also on College Drive. • ny special problans in makin3 connection - none anticipat • Connection charge - none e cpected Tel ne Line • Utility ca pany - New Englaxd Te1epI ne aid Telegraph C npany Waterville, Maine Peter Gorman 947—9911 (Baxvor office for new non_residen i 1l services) • Nearest line - On College Avenue; also appears to be a telepl ne line on the north side of the site. • Connection charge - Less than $100 OTHER VI MENTAL F CTORS/POrENTIAL P OBL 4S Noise - No apparent probl ns. flnissions - Must ouqly with State starx3ards Nearby Residents/Landowners - None within ]J4 mile of site. ,1 ------- 156 Wire Cbnsideration - West wir s are prevelant — CXzxinercial laid uses are ininediately to the south arx residei ces are about 1/4 mile to the south of the site. - the east is the river; on other side of river (1/4 mile away) is ithustrial property. Other - A special exception peimit is r ured for facilities located within 250 feet of the river. 1usion — I d.i r t see any re n why there u1d be any serious objections to use of this site for an incinerator ar steam generation facility. ------- 157 PPELD a r ES TE FOR SITE Pi EPI BPTICI , KF #1 Land a uisition, 1 acres @ $25,000 (if available at all) $ 25,000 rlaingas storage and distribution facility to reirain where it -is Clearing and gradi.ng Clearing 500 avation of loose fill and reccaupaction. 8,000 Additional grading I taining wall on west side of property 6,000 Siltation control 500 Acoess/I ad Drainage devices 1,800 1½” asphalt resurfacing @ $16/ton, 28’ wide x 250’ 2,400 lông = 800 sy @ $3. 00/sy Site Preparation Finished grading and 9” crushed stone base @ $5/ton 9,200 = 4000 sy @ $2.30/sy 3” asphalt paving @ $16/ton 10,300 = 2,500 sy @ $4.lO/sy Grade and pay area for Maingas facility 15, 000 6’ chainlink fence with guard, 800’ @ $9.00/LF 7,200 Utilities Water - nnecticn and fire hydrant 4,000 Se r 4’ force train, 200’ @ $20,tF 4,000 P Station and u tering device 15,300 Qxr osite san 1er 2,000 Electric Service NC 1ephone Sexy os NC subtotal $111,200 Qxitingencies and engineers, 25 percent 27 800 $139,000 a , ------- 158 P .D INM ( SITE I ISSA E DATA OR4 — TIUiYER C US MD— fl E DI L II’ER SITE -LC TIC.V • See vicinity maps, USGS 15 Minute Quandrangle, Waterville, 1959, Figure 1 City zoning map, Figure 3 • Distance to user Cs) - 700 feet + to Thayer boiler - !.kil jn to other users; iore than 1/4 mile TRA SPO ATI F IO • Vehicles hauling refuse to site - esthnated 25 packer loads per day • Loads of residue - less than six per day • Distance to major road arid condition of ro - The Thayer campis is on North Avenue, a major ti o-lane arterial that is in good condition. It is heavily traveled. Packer use of this road sbould be no problaa. — reach site, thrn north off North Street onto Quarry ad arid travel about 0.15 miles. Quarry &ad is a residenii 1 type street that is in good condition; Quarry I ad is lightly traveled. - At corner of North Avenue aid Quarry 1 ed is a 3nall scbool. Beyond that are woods to the turnoff of the site. Another 0.1 miles beyond the turnoff is a lune for the mentally retarded, aid 0.1 to 0.2 miles beyond that is an apar nent cauplex. The truck traffic to the facility sluild not be a major problen. — The Mid—Maine staff arid their architect stated that the 25 to 30 trucks traveling to the facility would not be a problen for the bospital. — The access road to the resource recovery facility could be located on an undeveloped right-of-way for about 500 feet; another 200 feet of road on Mid-Maine property uld have to be built. All of this road ‘xuld be in heavily ooded laid that is undulating. — It is doubtful that Mid-Maine would al1 z packer trucks to gain access to the resource recovery facility through its parking lot, altbough that ild be less costly to construct. ------- 159 SITE D IP I(X4 • cisting ].and use — Institutional zoning where the resource r rery facility uid be located. - A ixderate to high ircane residenF 1 area exists alxxit 1/4 + mile to the west. — - A slxpping center exists to the ncrtl ,est. • ithre land uses — Not expected to change significantly in the general area. - This area appears to be growing slowly. • Size of poten -ia1 site - several acres. This is nc probl n • ner of site - Mid-Name M ica1 Center • Land value - Assessed value is $700 per acre, undeveloped Assessed value is reportedly 93 percent of market value • pography - Site, variable slopes up to 10 percent. - access road - Variab t e up to 20 percent, including crossizx snail swales. • 1 ad - 700 feet to Quarry 1 ad • Appearance of site — Heavily oded deciduous trees. bu]d provide excellent screenm . • Drainage B jiiraments — No foreseeable problGns. - Drain to the swale. — Minimal downstream prob]ans. — Culverts required for access road where it would cross swales. ‘I ------- • Soil O rx1itions per SCS nap — ( i sification is silt and claycy. — 8—15 percent slopes. — We] ]. dra.inBI. • Foundation Problans — Use spread foundations. • Site grading reqjiiranents — Q,nsiderable clearing. - Fair ano mt of grading. • Poten’ l for vandalisn - Tbought to be relatively low. - Apart2nents to the northwest and hi4h to nv derate in ne l isirx to the east, both 1/4 ± mile away. • Fencing Re jiiretentS — Six foot chainlink fencing around site. t7r1T S Water • Purveyor - Kennebec Water District Waterville, Maine Tad hnan, Superint xIent 87 2—27 63 • Location of nearest lines and sizes — 20 inch line on Quarry I ad. • ctension r ijiiranents - 700 foot extension plus a fire hydrant at site. • Connection Charge — N ne Sanitary S • Owner - Waterville Sewer District Waterville, Maine 1 ve iTh iy 827—2763 ------- • Nearest line and sizes - 8 inch or 10 inch sewer in Quarry ad (700 feet away via the c posed a ess ro or thineitately adjacent to the Thayer parking lot). - 15 inch interceptor between North Street and the river (1000 feet away via a route ixElnEliately afjacent to the mayer parking lot). • Special r pfrenents — Sane as for Keyes #1 site. • Connection change — None. Electric Line • Utility ca çany - Central Maine P .ier Canpany Watervifle, Maine Gordon McP111 4l 873—4201 • Nearest line - Three Phase line on North Street, near Eustis Parkway. — No special problans in making cxnnection. ctend an overh line along North Street to beyond Thayer Unit and north outside parking lot to the res irce recovery facility. • Connection charge - Probably no charge. Dmarxl sluild warrant no-c st extension. Teleplcne Line • Utility Canpany - New ig1and Te1ept ne and Telegraph Canpany Waterville, Maine Peter Gonnan 947-9911 (Bangor office for new non-residential services) • Nearest line — North Avenue and. on Quarry I ad. • Connection charge — Less than $500. ------- an VI L ThC1ORS/PcYL NrIAL P BTB4S Noise - far er ugh fran the I spita1 to be rc ob1an. flnissions - must cunply with State starx1ards. - Nearby residents/1ar ownerS - ncne within 0.1 miles accept mayer Unit. Mid-Maine M&ical Center supports the concept of construction of resource recovery facility on their property. I ------- INST. Figure 3. WCATIW MAP PIU C6 ]) RFS(XJFCE REOCWER! F ILtT S irco: City of Jatervi1e zoniiij Map, 1979 L) ------- . 164 PBEZ m ST ESTD TE FOR S3 TE DP fl’ - THPJYER T1411’ Land a uisition, 2 acres @ $1,000 per acre plus $2,000 closing $ 4,000 Clearj.ng and grading CLearing, 1½ acres @ $2,000 per acre 3,000 ading 6,000 Siltation itxol (during nstruction) 1,000 1 ccess/1 ad, 24’ wide, 700’ long Clearing 2,000 ading, 700’ @ $15/LF 10,500 airiage culuerts, P, 150’ @ $144? 2,100 inc1 x1ing end sections Siltation control (during nstruction) 1,000 9” crushed stone base @ $15/ton 24’ wide x 700’ long = 2,000 sy @ $2.30/sy 4,600 3” asphalt paving @ $16/ton, 12’ wide x 00’ long = 1,000 sy @ $4.10/sy 4,100 Site Preparation Finished grading and 9” crushed stone base @ $5/ton = 4,000 sy @ $2.30/sy 9,200 2” asphalt paving @ $16/ton = 2,500 sy @ $4.10/ton 10,300 6’ high chain].ink fence with barbed wire guard, 900’ @ $9.00/LF 8,100 Utilities ter 6” pipe, 700’ @ $14/LF 9,000 nnection to e dsting 20” line 2,000 Valves (2) 800 Fire hydrant 1,000 S r 6” lateral, 1,000’ @ $13/LF 12,000 3 uen1 les @ $1,000 3,000 Q. . osite sampler 2,000 tering str’.rture 5,000 Electric service Tel xme service 500 ------- Subtotal $102,000 ntthgencies and engineers, 25 per zit 25, 000 $127,000 165 ------- |