SUPERFUND DESIGN and CONSTRUCTION From: Hazardous She Control Division To: EPA Regional Offices Update June 1988 - Vol. 2, No. 3 THE IMPACT OF LAND DISPOSAL RESTRICTIONS ON SUPERFUND RESPONSE ACTIONS The Hazardous and Solid Waste Amendments (HSWA) of 1984 place new requirements on dis- posal of hazardous wastes. Sec- tion 3004 generally prohibits land disposal of hazardous wastes, unless the waste or its residue has been treated to the level or by a method developed under Section 3004(m). Land Disposal Restrictions are being developed by the Office of Solid Waste to implement the requirements of Section 3004. In particular, treatment standards have been developed for solvents and dioxin-containing wastes under Section 3004(d) and for the Califor- nia-list wastes under Sectipn. £ •* 3004(e). Further standards are being developed for the scheduled wastes under Section 3004(g), which have been divided into "thirds" for development of regula- tions. These standards are being developed under the concept of the "framework rule" contained in the regulations on the solvents and dioxin wastes on November 7, 1986. The standards represent treatment by the "best demon- strated available technology" (BOAT) for the respective waste categories. Superfund actions which involve land disposal of restricted hazard- ous wastes may occur only after treatment to BOAT treatment standards after the standards go into effect between 1986 and 1990. However, Sections 3004(d) and (e) exempt contaminated soil and debris from the lan<} disposal prohibitions until November 8,1988. The Office of Solid Waste antici- pates developing treatment stan- dards for contaminated soil and debris as a separate waste cate- gory on the basis that contaminated soil and debris are different from bulk hazardous wastes. Until treatment standards for contami- nated soil and debris are devel- oped, treatability variances from BOAT standards may be available for contaminated soil and debris which cannot be treated to BOAT levels. These treatability variances will specify interim treatment goals for contaminated soil and debris. DO THE LAND DISPOSAL RE- STRICTIONS APPLY TO YOU? Under the Superfund Amendments and Reauthorization Act (SARA), Superfund response actions must comply with other regulations which are "applicable or relevant and appropriate" (ARAR). In order to determine whether the Land"1 - Disposal Restrictions are ARAR for a particular site, the two main questions are: Are you placing the waste? Is the waste you are placing a restricted hazardous waste? Placement does not occur when: (1) treatment occurs in situ, (2) the waste is capped in place, (3) the waste is moved within the area of contamination, or (4) the waste is removed for processing to improve its stability and returned to the same area of contamination. Placement does occur when: (1) wastes are consolidated from different areas of contamination into one area of contamination, (2) wastes are moved outside of an area of contamination for treatment and either returned to or deposited outside of the original area of con- tamination, or (3) wastes are moved within an area of contamination for treatment and redeposited into the original* area~of contarrtinatidnr" (Continued on page 4) Reaching the '175' RA Start Goal "Oct. 16,1989 -175 -100 •Status as of June 1988 ------- MIXED FUNDING AT MOTCO In June 1987, a consent decree was signed by EPA and 20 PRPs for a mixed funding settlement to cover the costs of remediation at the MOTCO site in La Marque, Texas. This is the first case settled using the mixed funding policy. The 11-acre MOTCO site is an old styrene tar reclamation facility and waste disposal site. The onsite wastes include 22 million gallons of contaminated water and organic liquids and 63,000 cubic yards of soil and sludges containing PCBs, vinyl chloride, mercury, and lead. Onsite incineration is the remedy selected for the site. Under the terms of the mixed funding settlement, the PRPs will be responsible for implementing the remedy. They will be reimbursed by EPA for 21 percent of the costs of the remedy provided that the cost of reimbursement does not exceed $9.324 million. The Agency’s liability for the remedy is capped at $9324 million. The Agency is still able to pursue cost recovery against the responsible parties not included in the settle- ment for the Government’s share of the mixed funding settlement. The policy for mixed funding settlements is summarized in an October 20, 1987, memorandum from J. Winston Porter and Thomas Adams to the EPA Regional Administrators. Under this policy, EPA has defined three types of settlements: 1. Preauthorization—The PRPs conduct the response action, and the Agency agrees to allow a claim against the Fund for a portion of the response costs. This is the type of settlement reached for the MOTCO site. 2. Cash-outs—The PRPs pay for a portion of the response costs upfront, and the Agency con- ducts the response action. 3. Mixed Work—The PRPs and the Agency each agree to conduct discrete portions of the response activity. In evaluating a site for a mixed funding settlement, the two criteria to consider are the amount of responsibility the settling PRPs are willing to accept and the strength of the Government’s case against financially viable, nonsettling PRP5. If the settling PRPs are willing to undertake or finance a substantial portion of the work and it is likely that EPA will be able to recover its contribution to the settlement from nonsettling PRPs, the site may be a good candidate for a mixed funding settlement. DEALING WITH CHANGES AT UNITED CHROME A fast-track design has been completed and construction is near completion at the United Chrome site (Region X), a former industrial hard chrome electroplating shop. An aggressive project schedule has been successfully maintained despite a number of major changes in project scope during the con- struction phase. The remedial design included the cleanup and demolition of contami- nated structures; excavation and offsite disposal of contaminated soil; and construction of two infiltra- tion basins, a shallow groundwater extraction network, and a wastewa- ter treatment system. The attached table shows the bid tab for the project. The predesign report refined the cleanup concept and characterized the uncertainty of design assump- tions. Identified early were the possible deviations from design assumptions and what the resulting effects might be on performance. The uncertainties in design have played out as significant changes during construction. The challenge has been to maintain project control and momentum under the on- slaught of redesigns, negotiations, change orders, and work plan revisions. For example, EPA reconsidered the scope of building demobtion and decided for complete demolition of the 20,000-square-foot structure; this required interior decontamina- tion by spray washing and off site disposal of 400 tons of contami- nated debris. When the excavation and removal of the plating tanks re- vealed that adjacent soils and groundwater were heavily contami- nated with chromium, an additional 200 tons of heavily contaminated soils were excavated for off site disposal and the design was modified to incorporate three addi- tional extraction wells at this concentrated source. Also, discov- ery of different plume characteris- tics led to the installation of 11 additional exploratory wells— 5 for extraction and 6 for perimeter monitoring. It was possible to successfully accommodate and manage such scope changes by: (1) recognizing uncertainties—assumptions and re- sponsible deviations were identified in the predesign report, and every- one agreed to “buy into” these; (2) building flexibility, or “robustness,” into the design and construction contract documents; (3) streamlin- ing the change order and work plan revision process, and using a contingency in the work plan budget; and (4) preparing and following a construction man age- ment plan for processing and docu- menting changes. 2 ------- DIFFERING SITE CONDITIONS (AN INTRODUCTION) On Superfund fixed price (lump sum or unit price) construction contracts, the contracting party must include a “Differing Site Con- ditions” clause in the contract. The clause entitles the construction contractor to an equitable adjust- ment when it encounters unknown and unanticipated physical condi- tions delaying performance or increasing the cost of performance. The purpose of the clause is to shift the risk of unknown conditions to the contracting party and eliminate the need for the bidder to inflate the bid to cover the worst conditions that might be encountered. There are two types of changed conditions that can form the predicate for recovery under the differing site conditions clause of a construction contract. Type I requires that subsurface or latent physical conditions at the site differ materially from those “indicated” in the contract, and that these condi- tions be reasonably unforeseeable by the contractor. Examples of Type I claims include encountering unexpected quantities of under- ground water not revealed in the boring data and encountering more rock, larger rock, or rock that is harder to drill than indicated in the contract documents. Foster Construction Company vs. United States, 193 Ct. Cl. 587, 594, 435 F.2d 873, 876 (1970). To prevail on a Type I changed condition, the construction contrac- tor must prove that it encountered subsurface or latent physical conditions at the site materially different from site conditions “indicated” in the contract. The “indications” need not be explicit. They may be proven by inferences and implications in the contract documents. The contractor need not prove a deliberate or negligent misrepresentation made by the contracting party in the contract documents. The contractor’s burden of proof would be carried if it shows a material variation between the subsurface conditions stated in the contract and those encountered at the job site. Type II conditions consist of un- known and unusual physical conditions at the site, differing materially from those ordinarily encountered and generally recog- nized as inhering in the work provided for in the contract. A Type II claim does not require the existence of a contracting party representation or indication. To make a Type II claim the contractor must establish the existence of conditions of such an unusual nature that they could not reasona- bly have been anticipated by the contractor. The contractor has a rather heavy burden of proof to show that (1) it did not expect the encountered conditions and (2) the conditions would have been generally regarded as unexpected by others in the same type of operation. An issue that sometimes arises is whether the contractor performed an adequate investigation of the bidding documents, data, and site prior to bidding. As a rule, contrac- tors are not required to inspect documents that are not a part of the contract. For a Type I condition, the contractor is held to what a relatively simple viewing of the site would have revealed. Warren Beaves, DOTCAB 1160,84-1 BCA ¶1 7,198 (1984). Where a Type II claim is made and the contracting party provided no indication of site conditions, the contractor may be held to a requirement to perform a more detailed site investigation. In the next issue of this newsletter we will discuss (1) variations (2) exculpatory language, and (3) notice requirements. J. Kent Holland, Jr. Wickwire, Gavin & Gibbs, P.C. TABULATION OF BIDS FOR THE UNITED CHROME SITE Riedel Loughney Crowley Rollins Environmental Dewatenng Environmental Environmental Desctiption Services’ Inc. Services Services Bonds and Insurance $12,500 $ 68,095 $ 13,760 $ 32,032 Move.ln and Site Preparation 42,679 318,334 83,000 136,464 Asbestos Removal 7,594 6,960 10,000 65,035 Demolition and Structural Reinforcements 124,601 130,105 267,113 148.1 69 Deep Monitonng well Installation 27,594 18.647 17,923 37,817 Extraction Well System Installation 16,328 59,088 228,309 118,955 Infiltration Basin Construction 53.580 80,122 85,000 78,531 Wastewater Treatment Fadllty Construction 279,437 203,445 263,000 215,568 Packaged Treatment System Installation 14,345 7.807 11200 52,621 Contaminated Soil 86,450 135,550 95,850 119,633 Extraction Well, Wefl Footage, Piezometer, Well Abandonment 68,382 45,991 44,205 44,047 Levels of Protection 6,100 16,947 35,000 24,000 Dust Control 12,000 12,000 0 0 TOTAL BID AMOUNT $751,590 $1,101,091 $1,154,380 $1,071,172 ‘Contract award Engineers Estimate for total amount (Sept 1987) $805,000. 3 ------- (Continued from page 1) A waste is a hazardous waste: (1) if it is listed in Subpart D of 40 CFR 261 as a waste from non-specific source (F waste), waste from specific source (K waste), acutely hazardous commercial product (P waste), or toxic commercial chemi- cal product (U waste), or (2) if it demonstrates one of the following characteristics: ignitability, corro- sivity, reactivity, or extraction procedure toxicity. Restrictions apply to a particular Superfund site, including how to obtain a treatability variance for soil or debris. Contact your Regional Coordinator or Carolyn K. Offutt (FTS 8- or 202-475-9760) for further information. Carolyn K. Of futt Site Policy and Guidance Branch SITE DELETIONS The Agency has recently issued draft guidance for Regional review on completion of Superfund sites and deleting sites from the NPL. As part of this process, EPA has developed criteria and procedures for determining the completion of a Superfund site. Completion criteria focus on site protectiveness and compliance with the Record of Decision. A Close-Out Report has been developed to document the satisfaction of technical require- ments for site completion. This report will be prepared by the Regional Project Manager and signed by the Regional Administra- tor. Close-Out Reports will be required of all Superfund sites before a site gains completion status. Deletion of sites will occur following completion. A notice will be placed in the Federal Register announcing the Agency’s intent to delete the site from the NPL and requesting public comment on the deletion. Responses to comments will be prepared and a final notice of deletion published. Administrative steps have been started that will delegate virtually all of the deletion process directly to the Regions. A new category of sites, known as long-term response actions (LTRAs), has also been created and will be listed separately on the NPL. LTRAs are sites where all remedial facilities have been implemented but continued activity is required for a period of time before the levels of protection specified in the ROD can be achieved for one or more pathways of exposure. Following achievement of protec- tion, the site will be classified as a completion. A Close-Out Report will be required before a site gains LTRA status and will be amended to signify site completion. The site can then be deleted from the NPL. Douglas Sarno Design & Construction Management Branch Training in 1988 Personnel Protection and Safety/EPA Contact: Regional Superfund Training Coordinator (513) 569-7539 or FTS 8-684-7537 July 11-15 July 18-22 July 25-29 August 1-5 August 8-12 August 22-26 Region VI New York, NY Region Ill Region V Region IV Region IX Requirements for Hazardous Waste Landfill Design, Construction, and Closure Contact: Orville Macomber/EPA (513) 569-7347 or FIS 8-684-7347 Management of Construction in the Superfund Program Contact: Jim Felix, Bureau of Reclamation (303) 236-8330 or FTS 8-176-8330 July 19-21 July 12-13 July 14-15 August 23-24 August 25-26 August 30-31 September 1-2 September 13-14 September 15-16 San Francisco, CA Dallas, TX Chicago, IL Denver, CO Kansas City, KS Philadelphia, PA Atlanta, GA New York, NY Boston, MA ABOUT THE UPDATE As more sites move into the design and construction stage, many of you will face similar technical and management issues. This Update is designed to assist you in managing these complex projects. Contact Karen Locke at EPA with comments, FTS or (202) 382-7997. For copies, contact EPA’s Public Information Center, FTS or (202) 382-2080. 4 ------- |