ENVIRONMENTAL PROTECTION AGENCY
OFFICE OF ENFORCEMENT
E PA- 3 30/ 2-7 8-O15
Ei a Iu at ion of the
Treatment CapabiI/1y
of the
West T re at m en t Pi ant
Fit eh burv, M a s a a eh // 5 et is
o
NATIONAL ENFORCEMENT INVESTIGATIONS CENTER
DENVER.COLORADO
AND
REGION I. BOSTON. MASSACHUSETTS
ffc» STAfr.
DECEMBER 1978

-------
Environmental Protection Agency
Office of Enforcement
EPA-330/2-78-015
EVALUATION OF THE
TREATMENT CAPABILITY
OF THE WEST TREATMENT PLANT
Fitchburg, Massachusetts
Arthur N. Masse
December 1978
National Enforcement Investigations Center - Denver, CO
and
Region I - Boston, MA

-------
CONTENTS
I. INTRODUCTION 		1
II. SUMMARY AND CONCLUSIONS 		4
CHEMICAL COAGULATION AND SEDIMENTATION 		4
CARBON TREATMENT 		4
GENERATION OF HYDROGEN SULFIDE (H2S) 		5
INDUSTRIAL LOADING 		6
ABILITY TO MEET PERMIT LIMITATIONS 		6
PILOT PLANT DATA - POMONA, CALIFORNIA 		7
III. EVALUATION OF DESIGN AND OPERATION 		9
SELECTION OF PHYSICAL-CHEMICAL TREATMENT 		9
PLANT DESIGN		11
PLANT OPERATION		13
IV. PHYSICAL-CHEMICAL TREATMENT AT POMONA, CALIFORNIA ....	22
GENERATION OF HYDROGEN SULFIDE 		22
PRESSURE DROP AND BIOLOGICAL ACTIVITY AS
A RESULT OF NITRATE ADDITION 		24
APPLICABILITY OF POMONA FINDINGS TO
PROBLEMS AT FITCHBURG 		25
REFERENCES		27
TABLES
1.	Pilot Plant Data West Treatment Plant Fitchburg, MA . . . 10
2.	Summary of BOD Carbon Column Effluent Data, West Treatment
Plant, Fitchburg, MA 	 18
3.	Allowable & Actual Loads from Paper Mills, West Treatment
Plant, Fitchburg, MA 	 21
4.	Comparison of Physical Chemical Treatment Plant Designs at
Pomona and Fitchburg	23
5.	Summary of Performance of Physical-Chemical Treatment Plant
at Pomona, California 	 23
6.	Carbon Capacity at Physical-Chemical Treatment Plants . . 26
FIGURES
1.	Process Flow Diagram, Physical-Chemical Treatment Plant
Fitchburg, MA	 12
2.	Activated Carbon Tests, West Plant, Fitchburg, MA ... . 19

-------
I. INTRODUCTION
The City of Fitchburg, Massachusetts, with a population of about
43,000, is 64 km (40 mi) northwest of Boston on the North Branch of the
Nashua River. The industries in Fitchburg produce paper and allied pro-
ducts, cutting tools, plastics, cotton and yard goods, fabricated metals
and machinery. These industries, particularly the paper industry, use
all the river flow except during periods of high runoff.1
Fitchburg owns and operates two wastewater treatment plants. The
West Plant, the subject of this report, was designed to treat 0.67 m3/sec
(15.3 mgd) by 1990. The plant treats over 90% industrial wastes, mostly
from the paper mills, by a physical-chemical treatment system made up of
chemical clarification and granular activated carbon adsorption. The
East Plant, designed to treat 0.54 m3/sec (12.4 mgd) by 1990, is a two-
stage activated sludge plant which treats mostly domestic wastes. The
plant was designed to remove phosphorous by chemical precipitation and
to biologically oxidize ammonia and organic nitrogen compounds to the
nitrate ion.
The Massachusetts Department of Natural Resources has decreed that
the North Branch of the Nashua River, into which both plants discharge,
should be of the quality necessary for boating, fishing and general recre-
ational use.
The Massachusetts Division of Water Pollution Control issued an
NPDES* Permit (MA0101281) to the West Plant on December 27, 1974.
* National Pollutant Discharge Elimination System.

-------
2
The permit requires the effluent from the West Plant to meet limits of 8
mg/1 biochemical oxygen demand (BOD) and 8 mg/1 total suspended solids
(TSS) as a monthly average, 12 mg/1 BOD and 12 mg/1 TSS as a weekly aver-
age, and 15 mg/1 BOD and 15 mg/1 TSS as a daily maximum.* The West Plant
has not been able to meet these limitations. From March to September
1977, the BOD of the plant effluent ranged from 40 to 71 mg/1 and the
TSS ranged from 20 to 35 mg/1.
Because the plant is unable to meet the permit limitations, EPA
Region I requested the National Enforcement Investigations Center (NEIC)
to conduct a technical evaluation of the West Treatment Plant. Specifi-
cally, NEIC was requested to evaluate the design and operation of:
1.	the chemical coagulation and sedimentation systems (primary
treatment)
2.	the carbon columns, including the column lining and backwash
system
3.	the carbon transfer system.
NEIC was also requested to evaluate potential and existing problems
i ncludi ng:
1.	the generation of hydrogen sulfide in the carbon columns,
2.	the effect of excessive loadings from industrial contributors
on: a) the ability of the plant to meet the permit limitations,
b) the carbon regeneration frequency, and c) the ability of
the carbon regeneration system to meet the resultant demands,
and,
3.	the potential for excessive carbon loss during regeneration.
Based on the plant evaluation, NEIC was asked to appraise the capa-
bility of the system to meet the prescribed limitations and, as necessary,
recommend changes in operation or design to achieve compliance.
* Settleable solids, dissolved oxygen and total and fecal coliform
are limited also, but these limits are not pertinent to this study.

-------
3
The West Fitchburg Plant was inspected on May 4 and 5, 1978 by
EPA personnel from NEIC, from the Office of Research and Development
in Cincinnati and from the Regional Office. The EPA visitors met with
Mr. George Chretien, Plant Operator, and Mr. Jim Taylor, Chief Engineer.
The information obtained through discussions with the Plant representa-
tives and their timely response to a follow-up letter was used in the
preparation of this report.

-------
II. SUMMARY AND CONCLUSIONS
The West Plant of the City of Fitchburg, Massachusetts, which
receives more than 90% of its influent load from paper mills in the
area, has been unable to meet the 8 mg/1 BOD and 8 mg/1 TSS limita-
tions prescribed in its NPDES permit. The treatment sequence at the
plant consists of chemical addition, flocculation, sedimentation and
adsorption on columns of granular activated carbon.
NEIC conducted an inspection of the plant to evaluate its design,
operations and treatment capability. The following summarizes the
inspection findings and conclusions reached.
CHEMICAL COAGULATION AND SEDIMENTATION
The pumps originally installed on the primary sedimentation tanks
could not remove the sludge as fast as it was being produced. These
pumps have been replaced and the coagulation-sedimentation system is
producing an effluent with an average TSS concentration of less than
35 mg/1. If the final effluent is to meet the 8 mg/1 limitation,
more rigorously controlled operation of the system is needed to re-
duce the average TSS concentration of the clarified wastewater.
CARBON TREATMENT
The protective lining applied to the carbon columns has proven
defective. In many places, the lining has split and corrosion of the
base metal is occurring. The cause of this problem has not been deter-
mined nor has any corrective action been taken.

-------
5
The suface wash mechanisms on all columns have been sheared off,
probably by incorrect backwashing procedures. Repair or replacement
of these mechanisms is awaiting recommendations of the City's consul-
tants, Camp, Dresser & McKee (CDM).
When a column of carbon is being regenerated, the carbon is moved
hydraulically in some locations and pumped mechanically in other loca-
tions. The hydraulic transport systems are working satisfactorily
but the pumps used to move the carbon mechanically have experienced
severe wear of the impeller linings and require expensive downtime
and maintenance. Another type of pump has been recommended but is
not yet in service.
Insufficient data are available to support any determination of
the carbon losses	during regeneration. Similar systems have experi-
enced losses of 5	to 10%, and the losses at Fitchburg should be in
this range.
GENERATION OF HYDROGEN SULFIDE (H9S)
Because the wastewater entering the carbon columns has a high
(~60 mg/1) contentration of BOD, bacterial growth occurs on the carbon
granules. In the absence of dissolved oxygen, sulfate-reducing bacteria
proliferate, resulting in the production of hydrogen sulfide, which
is released to the atmosphere when the effluent from the columns is
discharged, thus causing a serious odor problem in the area. The
City of Fitchburg alleviates this problem by shutting down the columns
periodically and adding enough caustic to raise the pH to 10.5. The
carbon is allowed to soak for several hours at this high pH, thus
killing the sulfate-reducing bacteria. In the winter, this procedure
must be carried out every 4 to 8 weeks. In the summer, however, the
bacteria reappear within a week after a column resumes operation, and
the treatment must be repeated weekly.

-------
6
INDUSTRIAL LOADING
Design conditions for this plant included a total BOD load in
the raw wastes of 4,400 kg (9,700 lb)/day. The actual BOD load to
the plant in recent months has been about 6,350 kg (14,000 lb)/day,
45% over design conditions. About 99% of the BOD is from the indus-
trial sources. Increases in production and revised operating proce-
dures at the paper mills were reported as the causes of the increased
loads.
These high loads have undoubtedly contributed to the inability
of the plant to meet the permit limitations, but the extent of this
contribution cannot be determined from the data available. The heav-
ier loads may necessitate a higher regeneration frequency than was
originally anticipated but, again, data are not available to support
this. Until the regeneration frequency necessary to meet the permit
limits is determined, the ability of the existing regeneration system
to meet the regeneration demands cannot be ascertained.
ABILITY TO MEET PERMIT LIMITATIONS
When the carbon columns were on stream, they were not effective
in reducing the BOD to the degree necessary to meet the limitation.
The wastewater leaving the coagulation-sedimentation system had a BOD
concentration of about 60 mg/1, of which the carbon columns removed
only 50%, leaving a final effluent BOD concentration of 30 mg/1. The
carbon column effluent has seldom, if ever, met the permit limitation
of 8 mg/1. These data, plus carbon adsorption studies of Fitchburg
wastewater conducted in NEIC laboratories, indicate that the wastewater
contains a high percentage of non-adsorbable organic materials. An
evaluation of the raw materials used by one of the paper mills indicates
that many of the materials used are relatively low in molecular weight
and would be biodegradable but not adsorbable.

-------
7
The data available make it apparent that, with the high loads of
non-adsorbable materials being contributed to the West Plant by the
paper mills, coagulation, sedimentation and carbon adsorption will
not reduce the BOD to 8 mg/1. It will be necessary to provide biolo-
gical treatment to degrade the low-molecular-weight materials prior
to, or in conjunction with, carbon adsorption.
PILOT PLANT DATA - POMONA, CALIFORNIA
The physical-chemical treatment of wastes at Pomona, California
was evaluated because of the many simi1iarities between the design
characteristics of the Pomona and Fitchburg Plants. The Pomona Plant
treats municipal rather than industrial wastes, but both provide chemi-
cal coagulation and sedimentation followed by adsorption on granular
carbon.
Because the Pomona Plant, like Fitchburg, experienced sulfide
generation problems, it conducted an extensive study of procedures to
solve this problem. Most successful was the addition of the nitrate
ion to the carbon column influent. Nitrate addition not only reduced
sulfide concentration of the column effluent to less than the detec-
table level, but also promoted biological growth on the carbon granules.
These organisms degraded the organic materials that were concentrated
on the carbon and, in effect, partially regenerated the carbon and
decreased the frequency of regeneration necessary to maintain effluent
quality. Both the elimination of the sulfide problem and the bio-
degradation of organic materials provided by the addition of the nitrate
ion would improve the quality of the effluent at Fitchburg. The nitrate
ion is reduced to nitrogen gas so nitrogen is not added to the effluent
in any form.
The addition of the nitrate ion does increase the pressure drop
through the carbon columns, but at Pomona this was satisfactorily
handled by proper backwashing techniques. The effect of the increased

-------
8
pressure drop resulting from nitrate addition cannot be determined
for Fitchburg; but the procedure has enough potential benefits that
it should be evaluated.

-------
III. EVALUATION OF PLANT DESIGN AND OPERATION
SELECTION OF PHYSICAL-CHEMICAL TREATMENT
After an initial evaluation of the characteristics of the waste-
water at Fitchburg, the City consultants (CDM) recommended physical-
chemical treatment (coagulation, sedimentation, carbon adsorption)
rather than conventional biological treatment. CDM indicated that
biological treatment: a) could not operate effectively with the wide
variability in flows and concentrations experienced at Fitchburg (the
paper mills shut down on weekends); b) would not remove the color
bodies present in the raw wastes; and c) would require the addition
of nutrients to support biological growth.
To determine if adsorption on activated carbon was suitable for
this application, CDM conducted pilot-scale adsorption studies. Waste-
water collected from several of the contributing mills was composited
in a tank trailer to simulate the feed to the municipal plant. The
feed to the pilot-scale columns was supernatant from the tank trailer.
During the six weeks of pilot plant operation [Table 1], the settled
waste BOD ranged from 1 to 34 mg/1 (avg = 14 mg/1) and the carbon
column effluent BOD (after 23 minutes' empty bed contact time) ranged
from 0 to 6.3 mg/1 (avg = 2 mg/1).
On the basis of the pilot plant results, the West Plant was de-
signed to provide chemical coagulation and sedimentation followed by
34 minutes' contact (empty bed basis) in downflow granular activated
carbon columns.

-------
10
Table 1
PILOT PLANT DATA3
WEST TREATMENT PLANT
FITCHBURG, MASSACHUSETTS
Date	TSS (mg/1)	 	BOD (mq/1)	
1970 Carbon Feed	Carbon Effluent Carbon Feed Carbon Effluent
MAY
12
1.5
-
26.2
6.3
13
18.5
12.7
22.5
5.1
14
29
17.3
18.2
4.9
18
16
-
10.0
5.3
19
2.0
4.0
13.5
5.0
20
18
4
6.2
3.9
21
8
0
12.0
4.8
22
23
-
-
-
26
2
0
1.0
0.03
28
18
7.2
4.2
0.3
JUNE




1
12.4
1.4
8.1
0.4
2
147
3.8
-
-
3
-
-
34.3
7
4
10.8
0
4.8
0.9
5
15.0
5.4
10.0
0.5
8
10.8
0.2
4.8
1.0
9
15
0
5.6
0.2
10
25.6
-
27.6
1.4
11
59.0
0.2
30.2
0
12
12.4
0
17.4
1.0
15
49.2
0
15.3
0.8
16
34.0
0
15.9
0
17
52.8
0
12.3
0.7
18
4.4
0
11.0
0
19
10.4
0
10.0
0.75
22
14.8
2.0
10.3
0.8
23
-
0
14.2
0.6
24
21.6
0
15.0
1.7
25
1.6
0
17.5
2.6
26
9.6
0
4.5
0
29
9.6
0
4.8
0
30
45
0.4
21.3
1.3
a Table taken from "Supplement C, Proposed Process Revisions, West
Fitchburg Wastewater Treatment Facility, August, 1970." Prepared
by Camp, Dresser and McKee.

-------
11
PLANT DESIGN
The West Plant receives municipal and industrial wastewaters in
separate conduits [Figure 1]. The sanitary wastewaters are settled
in two 9.1 m (30 ft) diameter clarifiers operating in parallel. At
the 1990 design flow of 0.08 m3/sec (1.8 mgd), the overflow rate would
be 30 1/min/m2 (1,060 gpd/ft2). This primary effluent is then chlori-
nated and joins the industrial wastewater. This combined flow of
0.67 m3/sec (15.3 mgd) is then dosed with alum and sent through two
rapid-mix tanks in parallel (6-minute residence time). Polymer is
then added, and the water flows to two 2-stage flocculation basins in
parallel (40-minute total detention time).
After flocculation, the wastewater is settled in two 40 m (130
ft) diameter clarifiers. At 0.62 m3/sec (15.3 mgd), the clarifier
overflow rate is 16.4 1/min/m2 (580 gpd/ft2). The chemical clarifi-
cation system is well designed and is capable of providing the quality
of effluent necessary for carbon adsorption.
Following clarification, the wastewater is pumped to the carbon
adsorption system which consists of twelve carbon columns containing
beds of granular (8 x 30 mesh) activated carbon. The carbon columns
are 6 m (20 ft) in diameter and have an overall height of 10 m (33
ft). Each column contains a carbon depth of 4.7 m (15.5 ft) (57,000
kg-126,000 lb). The carbon is supported on a perforated stainless
steel plate underlain by 30 cm (12 in) of graded gravel. The gravel
is supported by a Sybron-Leopold* glazed clay filter underdrain system.
A 5.8 m (19 ft) diameter Sybron-Leopold rotary filter agitator (surface
wash mechanism) is installed 5 cm (2 in) above the top of the carbon.
This is a horizontal pipe rotating on a vertical axis with spray nozzles
* Mention of commercial products does not imply endorsement by
the Environmental Protection Agency.

-------
Domestic
Wastes
Filter Backwash
Polymer
A1 urn
Industrial
Wastes
to
Process Flow Diagram - Physical-Chemical
Treatment Plant - Fitchburg, Massachusetts
Figure
Lagoon
Chlorination
Flocculation
Carbon
Regeneration
Clarification
Primary
Treatment
Post
Aeration
Rapid Mix
Carbon
Adsorption
hO

-------
13
directed at the carbon surface. Its function is to agitate the bed
during backwash and to separate the carbon granules from the waste-
water solids filtered out and from the biological solids generated.
Design conditions called for ten columns to be on stream (in
parallel) at any one time while one is being regenerated and one is
being backwashed. When the capacity of the carbon in one column is
exhausted and regeneration is necessary, the carbon is moved hydrau-
lically, using water-driven eductors, from the carbon column to the
spent carbon storage tank. The carbon is then mechanically pumped to
a screw conveyor feeding a 3.3 m (10.75 ft) diameter six-hearth furnace
for regeneration. The carbon is moved down from hearth to hearth,
reaching a maximum temperature of about 870°C (1,600°F). Following
this step, the carbon flows by gravity, without contact with air, to
a quench tank and is then mechanically pumped to a regenerated carbon
storage tank. From here, the carbon is educted hydraulically back to
a column.
PLANT OPERATION
Data available for the West Treatment Plant indicate that the
carbon columns have treated less than 10% of the clarified wastewater
since startup. From November 16, 1976 to May 31, 1978 (the first and
last dates for which information is obtainable), data are available
for only 429 column days.* If only 6 of the 12 columns had been opera-
ting continuously during this time, there would have been 3,360 column
days of operation. For treating 0.67 m3/sec (15.3 mgd) (the design
flow) at the design column flow rate, ten columns would have to be
operating at the same time.
* One column day = one column in operation for one day.

-------
14
Operating Problems
Continuous operation of the carbon columns has been prevented
because of the many design and operating problems. These problems
are itemized below and discussed in the text following:
1.	The pumps installed to remove sludge from the clarifiers
could not handle the load being produced; thus excess sludge
built up in the clarifiers.
2.	Piping system breaks in the carbon column feed system oc-
curred and required major revisions.
3.	The pumps that move the activated carbon to and from the
regeneration furnace have been a high maintenance problem
because of excessive wear of the impeller linings.
4.	The lining applied to the contactors has failed and severe
corrosion of the base metal has occurred and is still occurring.
5.	The surface wash mechanisms on all carbon columns have been
broken and are no longer effective. Improper backwashing
procedures have been reported as the cause.
6.	The automatic rate controllers designed to balance the flow
among the active carbon columns do not work properly.
7.	The growth of sulfate-reducing bacteria on the carbon gran-
ules has resulted in hydrogen sulfide concentrations up to
5 mg/1 in the column effluent, causing serious local odor
problems.

-------
15
Clarifiers
Since the clarifier sludge pumps were replaced with pumps that
can handle the sludge, the clarifiers have operated satisfactorily.
Between March and September 1977, the TSS contentration of the clari-
fier overflow ranged from 20 to 38 mg/1 and averaged 32 mg/1. This
resulted in a carbon column effluent that, with few exceptions, exceeded
the 8 mg/1 TSS limitation [Table 2]. Improved operation of the clarifier
to reduce the TSS concentration of the feed to the carbon column will
be necessary if the carbon column effluent limitation of 8 mg/1 TSS
is to obtained.
At the same time, the BOD of the clarifier overflow ranged from
4 to 71 mg/1 and averaged 61 mg/1. A reduction in the TSS of this
stream should result in a BOD reduction as well.
Carbon Treatment System
Piping system breaks caused start-up delays, but these problems
have been solved. The pumps that move the carbon to and from the
regeneration furnace, however, remain a high maintenance problem. It
is necessary to replace the impellers frequently. Replacement pumps
have been suggested by the contractor but have not yet been installed.
Several studies have been made to determine the cause of the
column lining failure. The study reports have not been made available
and, to date, no action has been taken to repair or replace the lining.
Severe corrosion has occurred and is still occurring where the base
metal has been exposed. For successful long-term operation, it will
be necessary to patch the linings or to replace them completely.

-------
16
Because of improper backwashing procedures, the surface wash
mechanisms were torn loose from their mountings during operation.
None of the mechanisms have yet been replaced although replacement is
necessary for successful plant operation.
Automatic rate controllers were installed in the influent lines
to balance the flows to each column. These have not worked satisfac-
torily, and the flow rate to the operating columns is now controlled
manually while the automatic system is being redesigned.
Generation of Hydrogen Sulfide
In metabolizing biodegradable organic material, bacteria will
use oxygen from, in the order of preference, dissolved oxygen, the
nitrate ion and the sulfate ion. The feed to the carbon columns is
high in BOD (avg = 61 mg/1) and has little, if any, dissolved oxygen
or nitrate ion. The organisms, therefore, use oxygen from the sulfate
ion, thus producing hydrogen sulfide (H2S). The odorous hydrogen
sulfide is released into the atmosphere when the effluent is dis-
charged from the columns; H2S concentrations as high as 5 mg/1 have
been measured in the column effluent. The odor is so strong and per-
vasive that it is necessary to shut the columns down when this problem
occurs.
The City officials have elected to solve the odor problem by
shutting down a column when the H2S odor from that column becomes
objectionable and adding caustic to the column feed until the effluent
reaches pH 10.5 to 11. The carbon is soaked in this high pH water
for 24 to 36 hours. During this period, the sulfate-reducing bacteria
are killed and the column can be started up again free of H2S production.
This procedures controls sulfide generation from 4 to 8 weeks in the
winter. In the summer, however, the sulfate-reducing bacteria grow
so rapidly that it is necessary to repeat the procedure every week.

-------
17
Adsorption-Resistant Materials in Column Feed
During the time the carbon columns were on stream, the 8 mg/1
BOD limitation was not met. The limited BOD data available [Table 2]
indicate that the columns removed only about 50% of the influent BOD,
producing an effluent with about 30 mg/1 BOD. The influent, then,
must contain a high concentration of organic materials that are not
adsorbable on activated carbon.
A sample of the carbon column influent was collected during the
plant inspection and carbon adsorption studies were conducted at the
NEIC laboratory. The results show that the wastewater contains a
high concentration of materials that are resistant to adsorption on
carbon. In the NEIC test, 500 mg/1 of activated carbon lowered the
total organic carbon (TOC) content of the column feed from 27 to 13
mg/1 (52%). The addition of 1,000 mg/1 of activated carbon removed
only 3 mg/1 TOC more. The low additional TOC removal obtained with
double the carbon dosage is due to the high percentage of non-adsorb-
able organic compounds present. The NEIC study results [Figure 2]
indicate that carbon adsorption alone will not remove all the organic
material.
It is well known that activated carbon is not effective in ad-
sorbing low-molecular-weight materials such as alcohol and formalde-
hyde. An evaluation of the data supplied by one of the paper mills2'3
shows that their wastewaters contain both of these materials, and
several other organic materials that would not be adsorbable on acti-
vated carbon. Because these non-adsorbable organic materials have
low molecular weights, it is likely that they are readily biodegrad-
able. Therefore, to meet the BOD limitation required, it will be
necessary to combine both carbon adsorption and biological treatment.

-------
18
Table 2
SUMMARY OF CARBON COLUMN EFFLUENT DATA
WEST TREATMENT PLANT
FITCHBURG, MASSACHUSETTS
Column	Number of 	BOD (mg/1)	 	TSS (mq/1)
No.	Data Points Range	Average Range Average
1
3
23-34
29
7-13
9
5
9
12-44
30
6-20
9
6
7
12-32
22
2-15
6
7
14
19-64
35
2.5-43
15
8
8
26-29
28
3-10
6
9
8
14-49
28
1-34
19
10
7
16-49
34
0.5-44
18
12
9
18-40
27
2.4-19
10

-------








-



















-







-
-
















































































-






-

_
-

-
-





































-



























-
-
¦
-




































-










-




-
-







-

-





































































































































































































































































































































-


v










































































































































































































































-





























k
-


































































































¦









































































"




























-

—









































































































































































































































































-






















-


























































































































































































-

¦











-










1 ! 1
...
















































































































































-







-


-
-






-





-














re
vat
cTT&Tj
PI
29
Car
jOQ-'Te >js-
;$adhusetts
2$
9
ant
0
TOO
200
300
400	500	600
Activated Carbon Dosage, mg/1
700
800
"900~
T000

-------
20
Carbon Regeneration
Between June 1977 and June 1978, the carbon from seven of the
West Plant columns was regenerated. The data provided indicate that
the regeneration restored the carbon to near virgin conditions. Re-
peated adsorption and regeneration cycles are necessary, however, to
determine the effectiveness of the regeneration procedures.
No data are available on the amount of carbon lost during the
carbon transfer and regeneration processes. However, carbon has been
transferred and regenerated in similar processes with losses ranging
between 5 and 10%, and it should be possible to limit losses to these
levels at Fitchburg.
Effect of Industrial Load on Treatment Capability
During the CDM pilot-scale studies, the BOD content of the input
to the pilot carbon columns ranged from 1 to 34 mg/1 [Table 1] and
the carbon treatment successfully reduced this to less than 8 mg/1.
The average BOD input to the carbon columns under present operating
conditions is 61 mg/1. The industries have increased their load several-
fold over the design conditions [Table 3]. Although the City has
requested that the industries reduce the load to the plant, a signifi-
cant load reduction does not seem probable. The change in quantity,
and probably in nature, of this load between the time of the pilot-
plant study and the present time has undoubtedly affected the ability
of the plant to meet the permit limitations. Further plant-scale
studies combining biological oxidation and carbon adsorption will be
necessary to determine if the plant has the capability to meet the
limitations under the increased industrial load.

-------
Table 3
ALLOWABLE AND ACTUAL LOADS FROM PAPER MILLS
WEST TREATMENT PLANT
FITCHBURG, MASSACHUSETTS
	Flow	 	BOD	 	TSS	
Plant	Allowed	Actual	Allowed	Actual	Allowed	Actual
Name	m3/sec mgd m3/sec mgd kg/day lb/day kg/day lb/day kg/day lb/day kg/day lb/day
James River,
Massachusetts
0.23
5. 3
0.15
3.5
993
2,190
2,650
5,840
8,527
18,800
6,577
14,500
Fi tchburg
Paper Co.
0.21
4.8
0.15
3.5
1,770
3,900
2,780
6,130
9,980
22,000
13,150
29,000
Crocker Technical
Papers
0.11
2.6
0.05
1.1
363
800
250
550
770
1 ,700
624
1 ,375
James River,
Fitchburg
0.05
1.1
0. 06
1.3
458
1,010
615
1,355
1,590
3,500
787
1 ,735
Sanitary
0.07
1.5
0.01
0.15
816
1 ,800
68
150
910
2,000
56
125
Total
0.67
15.3
0.42
9.55
4,400
9,700
6,300
14,025
21,770
48,000
21,200
46,735

-------
IV. PHYSICAL-CHEMICAL TREATMENT
AT POMONA, CALIFORNIA
Between 1973 and 1975, the Environmental Protection Agency spon-
sored a 27-month study of physical-chemical treatment at Pomona, Cal-
ifornia. The feed to the system at Pomona was principally municipal
wastes, as opposed to the 90+% industrial wastes in the feed to the
Fitchburg plant. Nevertheless, the designs of the two systems are
similar [Table 4] and the problem of hydrogen sulfide generation being
experienced at Fitchburg, was encountered and solved at the Pomona
Plant. For this reason, the results of the Pomona study4 were eval-
uated and are discussed below.
Table 5 shows the results of the Pomona study. An overall per-
centage removal for BOD cannot be determined because the BOD of the
raw wastewater was not given, but the carbon system alone reduced the
average BOD from 36.2 to 7.8 mg/1, an average removal of 78.5%. It
is probable that the overall BOD removal (clarification and adsorp-
tion) is greater than 90%.
GENERATION OF HYDROGEN SULFIDE
The Pomona plant experienced difficulties with hydrogen sulfide
generation in the carbon column, and total sulfides in the effluent
exceeded 5 mg/1 at times, a situation almost identical to the problems
experienced at Fitchburg. Backwashing alone was not adequate to solve
the problem, so the addition of pure oxygen to the feed was evaluated.
The sulfide content of the effluent decreased slightly as a result of
oxgen addition, but this procedure was abandoned because of excessively
high pressure drops which occurred in the column as a result of the
increased biological activity.

-------
23
Table 4
COMPARISON OF PHYSICAL-CHEMICAL TREATMENT PLANT DESIGNS AT
POMONA AND FITCHBURG
Parameter
Fitchburg
Pomona
Contact Time in Rapid Mix Tank, min
6
2.8
Contact Time in Flocculation Basin, min
40
42.5
Clarifier Overflow Rate, 1/min/m2 (gpd/ft2)
16 (580)
33 (1,180)
TSS in Clarifier Overflow, mg/1
<35
28
BOD in Clarifier Overflow, mg/1
61
36
Column Feed Rate, 1/sec/m2 (gpm/ft2)
2.1 (3.2)
2.7 (4)
Carbon Contact Time, Empty Bed, min.
34
30
BOD in Column Effluent, mg/1
30
7.8
Table 5
SUMMARY OF PERFORMANCE OF PHYSICAL-CHEMICAL
TREATMENT PLANT AT POMONA, CALIFORNIA
Parameter	Raw	Clarified	Carbon	Overall
Sewage	Effluent Effluent Removal (%)
TSS, mg/1	199	28.3	6.7	96.6
Total COD, mg/1	321	95.8	19.3	94.0
Dissolved COD, mg/1	49.0	48.6	13.5	72.7
BOD, mg/1	-	36.2	7.8	78.5a
a Does not include BOD removal by clarification.

-------
24
Continuous chlorine addition, at doses ranging from 20 to 50
mg/1, was then evaluated. It was hoped that the chlorine would kill
the sulfate-reducing bacteria. Because chlorine is rapidly removed
by activated carbon, this procedure was not effective and the sulfide
concentration of the column effluent reached 2.6 mg/1.
The addition of sodium nitrate to the column feed was then evalua-
ted. At a dosage of 5.4 mg/1 of sodium nitrate (as nitrogen), this
procedure was completely successful and the sulfide levels were reduced
consistently to below detectable levels.
PRESSURE DROP AND BIOLOGICAL ACTIVITY AS A RESULT OF NITRATE ADDITION
The addition of sodium nitrate at Pomona was accompanied by an
increase in the rate of pressure drop build-up during operation. On
several occasions, pressure losses exceeding 3.5 kg/cm2 (50 psi) were
experienced before the daily backwash. By proper backwashing proce-
dures, however, the backwashing frequency was kept at about once-per-day.
About 6-8% of the product water was used to backwash the column.
Offsetting the headloss problems caused by the nitrate addition
was the significant increase in carbon capacity, also apparently result-
ing from the addition of the nitrate ion. The column, containing
2360 kg (5,200 lb) of 8 x 30 mesh activated carbon, treated 113,500
m3 (30 million gal) of wastewater during the first cycle (before regen-
eration). The first cycle was ended so that experience could be gained
in regenerating the carbon. The carbon was not exhausted and appeared
to have leveled out at about 70% dissolved COD removal, and regeneration
was not necessary to maintain product quality. It was theorized that
the organisms generated by the nitrate addition metabolized some of
the organic material from the feed as it proceeded down the column
and, at the same time, partially regenerated the carbon by attacking
the organic materials concentrated on it.

-------
25
Table 6 compares experience at Pomona with data at other physi-
cal-chemical treatment plants where the nitrate ion had not been added
to the columns. The carbon capacity at Pomona was over five times as
high as the average obtained at the other plants. The economic bene-
fits of nitrate addition at the West Treatment Plant would have to be
balanced against the cost of the nitrate added and the effect of the
increased pressure drop.
APPLICABILITY OF POMONA FINDINGS TO PROBLEMS AT FITCHBURG
The findings at Pomona appear relevant to the problems being
experienced at the Fitchburg West Plant. Adding the nitration ion to
the carbon column feed should reduce, or possibly eliminate, the pro-
duction of hydrogen sulfide. In addition, the organisms whose growth
will be promoted by the addition of the nitrate ion will metabolize
some of the low-molecular-weight materials that are resisting adsorp-
tion on carbon. This would result in reduced BOD in the effluent
from the carbon columns, but the degree of reduction is not predict-
able.
The rate of pressure drop increase at the West Plant resulting
from the addition of nitrate ion to the carbon column influent cannot
be predicted. Every effort should be made to backwash the columns
properly so that both sulfide reduction (or elimination) and biological
degradation can be achieved at the plant.

-------
26
Table 6
CARBON CAPACITY AT PHYSICAL-CHEMICAL TREATMENT PLANTS4
Plant	Total COD, mg/1
Influent Effluent
Carbon Capacity
Total COD kg total COD Removed
Removal %	kg carbon
Lebanon, OH 67
Washington,
D.C	55
27
15
59.7
72.7
0.5
0.7
Ewi nq-Lawrence,
N.J.	75
Pomona, CA
98.4
20
23.6
73.3
76
0.8
3.5

-------
27
REFERENCES
1.	Callahan, W.F. and A.B. Pincence, Physical-Chemical Treatment
System at Fitchburg, Massachusetts. TAPPI Environmental Conference
Proceedings. April 1977.
2.	Memo of September 8, 1978 from Frank J. Early (EPA, NEIC) to John
F. Hackler (EPA, Region I), titled Carbon Adsorption Resistance of
Chemicals Found in Untreated Effluent from Fitchburg Paper Company,
Fitchburg, Massachusetts.
3.	Independent Physical-Chemical Treatment of Raw Sewage. EPA-600/2-77-137,
August 1977. Environmental Protection Technology Series.
4.	Letter of July 10, 1978 from F.E. Pendleton, Jr., of Fitchburg
Paper to John F. Hackler, EPA Region 1.

-------
RECOMMENDATIONS FOR IMPROVING EFFLUENT QUALITY
AT THE FITCHBURG WEST TREATMENT PLANT
1.	Addition of the nitrate ion to the feed to a full-scale carbon con-
tactor should be evaluated. To prepare for this evaluation, a
surface wash mechanism should be installed on one of the carbon
columns. The carbon should then be filled with virgin or freshly-
regenerated activated carbon and backwashed as recommended by the
supplier of the surface wash mechanism.
2.	Clarified wastewater, to which 5 mg/1 of sodium nitrate (as nitro-
gen) has been added, should be passed downflow through the column
at the design rate. The nitrate ion should be added far enough
upstream to assure adequate mixing. If hydrogen sulfide is detect-
able in the effluent under these conditions, the nitrate addition
rate should be increased. If H2S is not detectable, the nitrate
ion addition rate may be decreased.
3.	Backwashing should be initiated when required by pressure drop
through the'column. The backwashing procedure recommended by the
supplier of the surface wash mechanism should be followed closely.
Samples of the backwash water should be taken frequently and back-
washing stopped when a predetermined turbidity of the backwash water
is reached. Shutdown of the backwashing procedure should also be
done as recommended by the supplier of the surface wash mechanism.
4.	During this evaluation of nitrate addition, complete records of
influent BOD and TSS, influent flow, and column pressure drop
should be maintained.
5.	The caustic wash procedures should not be used during this evaluation.

-------
6. If this treatment procedure does not reduce the BOD to the desired
level or if the rate of pressure drop increase prevents satisfac-
tory operation, one of the following procedures must be followed to
enable the plant to meet the prescribed limitations:
a. Reduce the amount of non-adsorbable organic materials enter-
ing the plant by process revisions or pretreatment at the paper
mills.
b. Provide a separate biological system at the treatment plant
to remove non-adsorbable materials prior to carbon adsorption.

-------