THE EFFECTIVENESS OF THE SUPEPFTIND PROGRAM
    CEROA SECTION 301(a)(l)(A) STtJDY
               Final Report
Office of Emergency and Remedial Jtesponse
   n.S. Environmental Protection Aaency
              December 19R4

-------
                            Table of Contents

                                                                Page
EXECUTIVE SUMMARY	   ES-1

INTRODUCTION	      i

CHAPTER 1.  REMEDIAL ACTIVITIES 	   1-01

   Discovery and Investigation	   1-16
   Reducing Bnroediate Hazards  	   1-19
   Understanding the Problem and Selecting Cleanup Action	   1-31

CHAPTER 2.  REMOVAL ACTIVITIES 	   2-01

   Notifying the Government "of Hazards Substance Releases ....   2-02
   Monitoring Non-Federal Cleanup Activities.	   2-07
   Short-Terra Responses to Hazardous Substance Releases 	   2-09

CHAPTER 3.  CHARACTERIZING REMOVAL ACTIONS 	   3-01

   Review of Past Removal Activities 	   3-01
   Removal Action Case Studies 	   3-01

CHAPTER 4.  ENFORCEMENT 	   4-01

   Coordination With Removal and Remedial Programs	   4-02
   Notification of Potentially Responsible Parties and
     Negotiation	   4-05
   Civil Litigation	'	   4-13
   Administrative Enforcement Actions 	   4-17
   Cost Recovery	   4-20
   Natural Resource Damage Enforcement 	   4-23
   Criminal Enforcement	   4-25

-------
                             EXECUTIVE SUMMARY

      The Comprehensive Environmental Response,  Compensation, and  Liability
 Act (CERCLA or the Superfund Act)  created a  broad and  complex system of
 response and enforcement authorities to address widespread  and  complex
 hazardous substance release problems throughout the country.  The Act was
 passed December 11, 1980,  and EPA undertook  the dual tasks  of setting up
 the administration of the Superfund program  and at the same time  initiating
 response actions to address known hazardous  release problems.  The Superfund
 program involves three major activity areas,  removal and  remedial cleanup
 actions undertaken by the Fund and enforcement  actions to secure  responsible
 party cleanups or to recover the  costs of Fund-financed actions.

      In its short existence, the  Superfund program has undergone  major
 policy changes which have significantly affected the implementation
 and accomplishments of the program.   Some of  these changes  have evolved
 with the Agency's growing  experience with the program  and our expanding
 knowledge of the problems  we have been charged  to address.  A number of
 policy changes resulted from a major analysis and reevaluation of the
 program undertaken in the  spring  and summer of  1983. .These policy
 changes resulted in significant shifts in approach and emphasis in
 the Superfund Program.

     The most significant  change  that occured in 1983  was a shift from a
 "negotiation first"  posture to more  prompt use  of Fund resources  and
 formal enforcement measures to provide response to hazardous substance
 releases.   At the outset of the program,  EPA  was faced with a huge number of
 existing and threatened hazardous  substance releases and  the need to
 conserve Fund resources and use them most efficiently.  EPA placed primary
 emphasis on enforcement negotiations to achieve cleanup.  Except  under
 emergency conditions,  the  Agency would attempt  to negotiate settlements
 before resorting to  administrative and civil  enforcement  authorities.
 This approach allowed  EPA  to conserve  Fund resources for  response at
 sites  with no potential responsible  parties or  where enforcement  efforts
 had failed.

     As  negotiations became prolonged,  this policy led to significant
 delays  in  achieving  cleanup at  sites.   Therefore,  EPA  has developed  a
more balanced approach  which includes:  initiating Fund-financed response
more promptly for both  removal  and remedial actions? targeting enforcement
 resources  on those sites where  there is a greater likelihood of successful
 action;  and participating  in a  formal  enforcement process which moves
 from negotiation to  civil or administrative enforcement in  a reasonable
 timeframe.

     Another cause for  delay in remedial  actions was the  timing requirement
 for States'  financial commitments  to remedial efforts.  States were
reguired to provide  assurances  for their  share  of the  cost  of Superfund
actions  at the beginning of  the remedial  investigation/feasibility study
stage.  This meant that States not only were  reguired  to  pay part of the
                                   E-l

-------
 planning costs, but also that the States had to provide  financial assurances
 at a very early stage in the remedial planning  process.  The policy
 changes in the spring of 1983 modified this requirement.   EPA waived  the
 requirement for States to finance part of the planning costs.   In addition,
 States do not have to make their financial ccmmitment for  a particular
 phase of remedial activity until immediately prior  to initiation of that
 phase, when they know what the action and the costs will be.

      Activity in the removal program stepped up significantly at this
 time as well.  In the first years-of the program, EPA took Fund-financed
 removal actions only in urgent situations.  There was a heavy stress  on
 encouraging States and responsible parties to undertake removal actions.
 In 1983, this policy changed to allow SPA Regions to interpret  the NCP
 criteria for taking removal action more liberally.   Consistent  with the
 NCP, removals could respond to significant potential hazards rather than
 only to currently existing threats.

      Also at this time,  there was a  shift in emphasis on the type of
 removal actions that should be taken at National Priorities List (NPL)
 sites.  Previously, removals at NPL  sites were  limited to  small-scale
 stabilization actions to reduce only the most imminent hazards, e.g.,
 of fire and explosion.   This policy  was expanded to encourage removals at
 NPL sites that involved  more extensive surface  cleanup.  The intention
 was to avoid the need to return to sites more than  once to undertake
 stabilization activities.

      Policy changes were also introduced that affected management of  the
 Superfund program.   Previously, decision-making and approval authority
 for Superfund actions had been very  centralized at  the Administrator  or
 Assistant Administrator  level (with  some very minor exceptions).  Since
 the spring of 1983, major portions of program decision-making and imple-
 mentation authority were delegated to the EPA Regional Offices.  The
 program has become  increasingly decentralized.  This decentralization has
 shortened the timeframe  for approval of most removal and some remedial
 actions and eliminated burdensome steps in the  process.

      An important program area in which EPA policy  has been evolving
 since the outset of the  program is community relations.  The safety and
 concerns of  the  community  surrounding  a hazardous release  site  are critical.
 Initially,  EPA encouraged  flexibility in tailoring  community relations
 activities  to the needs  of each site.   It became apparent  in late 1982
 that there was a need for  a more formal structure for community relations
 activities.  The structure that was  developed combines a minimum number
 of  requirements  with  flexibility in  how to implement the requirements.
 The  new structure also places greater emphasis  on the continuing involve-
ment of the community and  communication with EPA and State agencies
 throughout  the planning  and implementation phases of a cleanup  action.
                                   E-2

-------
                  ACCOMPLISHMENTS OF THE SHPRRFUMD PROGRAM
            the pace of the Superfund Program was slow at first, program
 activities and accomplishments have arown,  especially over  the  last 7
 years.   Throuqh FY R4, EPA and the Coast Ouard have started 472 removal
 actions, at a cost of more than $87 million, since the becjinninq of the
 program; 329 (78 percent)  of  these actions  were initiated in fiscal years
 1983 and 1984.  in addition,  under KPA administrative orders or consent
 aqreements, responsible parties have initiated another fi7 removal actions.
 The level of removal activity is particularly  important, because this is
 the mechanism throuqh which EPA can respond at sites which  pose a siqnif i-
 cant threat to human health,  welfare,  or the environment, but which do
 not qualify for remedial fundinq.

      In addition to undertaking direct removal actions, FPA monitors short-
 term cleanup actions by States or  private parties.  This monitoring, either
 by telephone or on-scene,  provides specific advice and assistance and
 ensures that appropriate cleanup action is taken.  EPA's approach encourages
 and assists response by responsible parties and non-Federal Government
 agencies.   At the same time,  EPA may step in and take over  the cleanup if
 the action under way at the site is inadequate.  The Agency provides such
 on-site monitoring at 300-500 sites per year.

      The pace of the remedial program  has accelerated significantly during
 1983 and 1984.   Dvhile construction has  been completed at only a few sites,
 we can  look to significant interim accomplishments which demonstrate that
 we are  on  track  to achieving  a larqe nunber of cleanup actions.  By the end
 of PV 84,  Fund-financed remedial investiqation/feasibility  studies had
 been started at  290 sites.  -Fund-financed remedial design has been initiated
 at 34 sites, and construction has  been initiated at 29 sites.  In addition,
 enforcement action through  the end of  FY 84 has resulted in responsible
 parties committing to undertake remedial investigation/feasibility studies
 at 25 NPL  sites  and cleanup actions  at  22 NPL sites.  In total, remedial
 investigation/feasibility  studies  have  been started at 315  NPL sites,
 design  at  56 NPL sites, and construction at 51 sites.

      A major area of accomplishment is  investigation of potential hazardous
 waste sites  and  expansion of  the NPL.  The EPRIR inventory has grown from
 13,392  sites in  late 1982 to  18,900  sites by the end of September 1984.
 F,PA has devoted  considerable  resources to investigating the potential
 sites that have  been identified.   As of September 1984, preliminary assess-
ments had  been completed at more than 10,700 sites, and site inspections
 had been completed at approximately  3,800 sites.  The Hazard Pankinq
 System has been  used  to score 1,732 sites.  In September 1983, a final
 NPL was  promulgated containing 40fi  sites, and the first update to the NPL
was proposed with 133 sites.   The first update was promulgated on September 12,
 1984, with 128 sites.  The second  NPL update was proposed on October 2,
 1984, with 244 sites.
                                   E-3

-------
      EPA has  developed  a  continuinq,  phased process  to  investigate sites
and  to  identify  those sites  that are  eligible for remedial cleanup.  This
process allows us to establish  sane priorities  for ("ore detailed and
intensive invest iqation at sites, based on the  likelihood that hazardous
substances are present, and  on  the potential threat  from those sites.

      FPA's Superfund enforcement efforts also reflect siqnificant
accomplishments, especially  in  the last 2 years.  Neqotiation with potential
responsible parties has resulted in 144 consent decrees and consent
administrative orders:  100 of these aqreements were  reached in Fiscal
Years 1983 and 1984.  The value of the 144 settlements, in remedial and
removal activities undertaken by responsible parties is more than S3]0
million.

      EPA  has  also issued  111 unilateral administrative orders, 107
of these  were issued in fiscal years  1983 and 1984.  Unilateral admini-
strative  orders  are used  to  compel responsible parties  to clean up
sites,  and EPA  may initiate precedent-settinq treble damage suits aqainst
some  of those parties who have not complied with the unilateral admini-
strative  orders.   In addition, the Department of Justice has filed 72
cases which have been referred by EPA for civil litiqation.  Forty-eight
of these  cases were filed in fiscal years 1983 and 1984.

      The  success of these enforcement efforts is very encouraginq for
conservation  and careful use of Fund monies.  EPA is demonstrating its
commitment to seek negotiated settlements as far as  possible, but to
proceed with  formal enforcement mechanisms when negotiations do not
result  in appropriate settlements.  Over the longer  term, these accomplish-
ments may prove  to be a strong incentive for more negotiated settlement
agreements in the  future.
           cost recovery efforts got off to a slow start because of the
time required to complete Fund-financed action and to secure adequate
documentation of expenditures, as well as to establish the procedures
which would be followed.  As of September 30, 1984, however, EPA has
recovered S6,94],196.

-------
                               INTRODUCTION

      The Comprehensive Environmental Response, Compensation,  and Liability
 Act (CERCLA or the "Superfund" Act), enacted on December 11,  1980,  provides
 the President with broad authority to undertake cleanup of hazardous
 substance releases to protect public health, welfare,  and the environment.
 In addition, the President has authority to order parties to  clean  up any
 releases or threatened releases for which they are responsible.   CERCLA
 also creates a strict system of strict responsible party liability  for any
 cleanup costs that are incurred when the Federal Government responds  to a
 release.  The Act creates a $1.6 billion Hazardous Substance  Response
 Trust Fund (the Trust Fund or the Fund)  to finance Federal cleanup  action.

      The President delegated .primary responsibility for implementing  the
 Superfund Act to -the 'EPA in-Executive Order 12316.   As required  by  CERCLA,
 EPA promulgated ;a -revised National Oil and Hazardous Substances  Contin-
 gency Plan (NGP')  on*Iu!y 16,  1982.   The Rational Contingency  Plan had
 originally been promulgated under section 311  of the Clean Water Act.
 The Act and tbe NGP pirovide the regulatory framework for the  cleanup  of
 hazardous substances;;by ;EPA .and other Federal  agencies.   Under this
 framework, EPA has established a Superfund program with three major
 program elements —renewal,  remedial, and enforcement actions — to  carry
 out the responsibilities in the Act.

   CERCLA's removal authority provides a powerful tool  for providing
 rapid effective response to threats to public  health,  welfare, and  the
 environment.   CERCLA defines removal as "the cleanup or removal  of  released
 hazardous substances from the-environment,  such actions  as may be necessary
 taken in the  event of the threat of release of hazardous substances into
 the environment,  ...such other actions as may  be necessary to prevent,
 minimize,  or  mitigafee damage to the public  health or welfare  or  to  the
 environment,  which jnay otherwise result  from a release or threat of
 release."

     Removal  actions are limited in scope by CERCLA section 104  (c)(l)  to
 $1 million of Fund -monies and  six months from  the date of  initial response.
 Removals may  be exempted from  the $1 million and 6 month limits  if  all
 of  the  following .conditions are satisfied:  (1)  continued response actions
 are required  to prevent,  limit,  or  mitigate an emergency;  (2)  there is  an
 immediate  risk to  public 'health or  welfare  or  the environment; and  (3)
 such assistance will not otherwise  be  provided on a timely basis.

     The NCP  establishes tswo categories  of  removal  actions.   Immediate
 removals are  to respond to situations of immediate  and significant  harm.
Planned  removals are to  respond  to  situations  which require an expedited,
but  not  an immediate response.  Under  EPA's general  grant  authority,  the
Agency also requires 'that a State must request a planned removal action
and must fund a 10 percent share of the  response  costs.

     The elements of  the emergency  response program are built  on  the same
program  elements previously established  and tested  under section  311 of
the CWa.  However, the CERCLA program  is much  broader  than the section

-------
 311 program.  The U.S. Coast Guard (USCG)  fulfills a vital and independent
 role in the Superfund program.  Under Executive Order 12316 and the
 NCP, the USCG has response authority for releases of hazardous substances
 into or threatening the coastal zone, U.S.  waters of the Great Lakes, and
 specified ports and harbors on inland rivers.   The USOG staff, aided by
 their Atlantic, Gulf, or Pacific Strike Team take immediate removal
 actions in response to these releases.

      The USOG also operates the National Response Center (NRC),  which is
 open around-the-clock to receive reports of hazardous substance spills
 and discharges.  The 10 EPA Regional Offices also have 24-hour hotlines
 to receive notifications.  CERCLA requires  that when a release exceeds
 certain reportable quantities for the substances involved,  it  must  be
 reported to the NRC.

      When the Federal Government is notified of a release of a hazardous
 substance from an accident or an uncontrolled waste site, EPA  or the USCG
 staff known as on-scene coordinators investigate the release.   In most
 cases responsible parties or state or local government agencies  respond
 to the release, and the on-scene coordinator monitors the cleanup action.

      Remedial activities are the second major element of the Superfund
 Program.   Remedial cleanup activities are directed to the most serious
 hazardous release problems and provide the  most extensive cleanup.  CERCLA
 CERCLA defines "remedy" or "remedial action" as "those actions consistent
 with permanent remedy taken instead of or in addition to removal actions
 in the event of a release or threatened release of a hazardous substance
 into the  environment, to prevent or minimize the release of hazardous
 substances so that they do not migrate to cause substantial danger  to
 present or future public health or welfare  or  the environment."   CERCLA
 also establishes a clear role for States in remedial response  actions.
 States must fund 10 percent of the cost of  remedial actions, unless the
 site was  owned by the State or a political  subdivision of the  State.  In
 that case,  the State must provide at least  50  percent of the cost of the
 remedial  action.

      States have the opportunity to undertake  the remedial  cleanup  activities,
 if  they choose,  or they may coordinate with EPA to take the lead.   The
 roles and responsibilities of the State and EPA are established  in  a
 cooperative agreement or Superfund State contract for State or Federal
 lead actions.

      EPA's  remedial  program has two distinct phases of activities.  The
 first  is  site  discovery and investigation.   During  this phase, EPA  identifies
 and investigates potential hazardous releases.  This involves  several
 steps  to  scope out the extent of the problem associated with the releases
 or  potential releases.   Finally the more serious  releases are  scored
 using  the Hazard Ranking System (HRS),  and  those  scoring 28.5  above or are
 entered on  the NPL after notice and opportunity for public  comment.  This
meets the requirement in CERCLA section 105  that  the President (EPA)
 establish a  national  list  of priorities among  known releases or  threatened
 releases, and  establish  criteria for determining  priorities among releases.
                                    11

-------
      The second phase of activity is planning and implementation of
 remedial cleanup activities.   The NCP limits remedial cleanup activities
 to those sites which are on the NPL.  This phase is very lengthy and
 expensive.  Before remedial planning can begin at a site,  EPA and  the
 State must sign a cooperative agreement or Superfund  State contract.  The
 activities during this phase  are preparation of a remedial investigation
 and feasibility study, choosing the remedial alternative,  and design and
 construction of the remedy.

      The third major element  of the Superfund program is enforcement.
 Both Congress and EPS recognize the limitations of the Fund in addressing
 the potentially thousands"of  hazardous substance releases  around the
 country.  The purpose of the  Superfund enforcement program is to ensure
 responsible party cleanup of  hazardous substance releases  and threatened
 releases whenever possible and to recover the costs of Fund-financed
 cleanup actions^

      Two sections of CERCLA form the basis of EPA's Superfund enforcement
 authority:
      o
        Section  106 authorizes  EPA to  issue administrative
        orders or to  pursue1 civil actions  in  the courts compelling
        responsible parties to  take appropriate cleanup action
        in  response to a  release that may  present an  imminent
        and substantial endangerment to public health or
        welfare  or the environment; and

      0  Section  107 makes responsible parties liable  for the
        costs incurred by Federal or State Government or private
        parties  in taking appropriate response to a release.
        This section  also makes responsible parties liable for
        up  to three times the cost of any  response made necessary
        by  the failure, without sufficient cause, of  the parties
        to  comply with an administrative order issued pursuant to
        section  106*  In  addition, responsible parties are responsible
        for the  costs of  natural resource  damages.

Negotiation with potential- responsible parties is an essential part of
the enforcement process.  Negotiations before a removal action are
kept to a  strictly limited time frame.  Negotiation  may take place at a
number  of  different  points during the remedial planning process to reach
agreement  on private party cleanup, as well  as after a Fund-financed
cleanup; is completed to  reach  agreement on cost recovery.  However,
agreements reached through negotiations are made formal through a consent
administrative  order or  a consent decree.  Where negotiations fail, EPA
may atftiempt t6  secure private  party cleanup  or cost  recovery through
unilateral adminstrative orders or civil  action.
                                   iii

-------
     The three major elements of the Superfund program are interrelated
in several ways.  Enforcement action may be pursued at specific points
during the remedial process, and may, in fact, be going on at the same
time as Fund-financed response.  When EPA identifies the need for a
removal action, timely enforcement efforts may secure private party
cleanup and eliminate the need for a Fund-financed response.  EPA and the
States must be careful in conducting Fund-financed response actions so
that adequate evidence and documentation are available for cost-recovery.

     Discovery and investigation activities during the initial phase of
the remedial program may lead to the identification of releases that
pose an immediate threat and should be subject to a removal action.  In
addition, sites which are listed on the NPL may pose an immediate threat
which EPA can repond to most effectively by taking a removal action.

     The following report discusses in detail how the Superfund program
operates and how it has changed over time.
                                    IV

-------
                           1.   REMEDIAL ACTIVITIES

                                 lOTROniiCTldN

      Cleanup of larqe,  abandoned or untended  hazardous waste sites  is the
 focus of remedial  response activities  in the  Superfund program.  EPA's
 remedial activities fall into two distinct  areas of effort.  The first is
 discovery and investiaation of potential hazardous releases and waste sites
 and identification of the more serious sites  where EPA will undertake
 long-term cleanup  actions. These activities  establish a systematic approach
 to set priorities  arriona thousands of sites.   Each successive phase of
 action involves a  more  intensive  resource commitment to expand our knowledqe
 of hazardous release problems at sites.  The  purpose is to progressively
 target attention and resources to those sites that pose potentially more
 serious problems.

      The second area of effort is accomplishing cleanup at those sites that
 have  been targeted f6r Remedial action.  This is a long-term intensive
 effort to determine precisely the extent of the problem at the site; choose
 a  preferred  cleanup alternative;  and implement the cleanup at the site.
 This  is in a sense a "pipeline" process, since each phase must be completed
 before proceeding  to the  next.  The number of sites in a particular
 phase is an  indication  of how many sites may  be expected to move into the
 next  phase.

      Exhibit 1-1 presents the progression of  RPA's remedial activities in
 the Superfund program.
                        DISCOVERY AND INVESTIGATION

Discovery

     This  initial 'phase of activity entails four specific steps, generally
performed seguentiaMy.  'These are site discovery, preliminary assessment,
site inspection, and listing on the National Priorities List.  The purpose
of site discovery is to identify all releases and potential releases of
hazardous substances to ensure that they are brought to the attention of
the appropriate authorities.  Some site discovery activities involve Federal,
State, and/or local iqoverrwents, while others are activities reguired of
private parties.  Different discovery methods are described below.

     CERCEA section 105(1) states that the National Contingency Plan shall
include Methods for discovering and investigating facilities where hazardous
substances  are located.  Section 300.63 of the National Contingency Plan
lists the following methods for site discovery:

                         notification.  Section !D3(a) of CEPCLA requires
         persons in 'charge of a facility to contact the National Response
         Center — a national emergency response clearinghouse operated
         by the Coast Guard — when a hazardous substance release eguals or
         exceeds its Federally specified reportable guantity.  This is an
         ongoing notification process.!
       Notification is discussed in detail in Chapter 9, "Removal Activities."

-------
                         EXHIBIT  1-1

               EPA's REMEDIAL  ACTIVITIES
                        Sites Discovered
                         (18,884 Sites)
                              I
                     Preliminary Assessment
                      < 10,76 7 Completed)
                        Site Inspection
                       ( 3,601 Completed)
                 Hazard Ranking System Scoring
                         (1,732 Sites)
                              I
                    Sites Listed on the NPL
                          (538 Sites)
                              I
             Remedial Investigation/Feasibility Study
                        (315 Started^)
                        Remedial Design
                         (56 Started)
                    Remedial Construction
                         (51 Started)
§/  Numbers Reflect Actual Program Data As Of September 30, 1984.

     Includes Responsible Party Actions.
Source:  Office of Emergency and Remedial Response, U.S. EPA.

-------
                       EXHIBIT 1-3
    BREAKDOWN OF PRELIMINARY ASSESSMENTS
  No  Further
    Action
 (3,751 Sites)
                   Preliminary Assessments
                      (10,767 Completed)
 Currently
  Pending ^
(3,415 Sites)
 Site Inspections
(3,601  Completed)
ay  "Currently Pending* Category Includes Sites That May Require Additional
     Information To Determine Whether A Site Inspection Is Necessary
Source: Office of Emergency and Remedial Response, U.S. EPA
        (September 30, 1984)

-------
                           EXHIBIT 1-2
            NUMBER OF SITES ON ERRIS BY QUARTER,
                FISCAL YEARS 1983 AND 1984
NUMBER
OF SITES

 19.000-


 18,000-


 17.000-


 16.000-


 16.000-


 14.000-
 13,000
                                   18.223,
                              17,534
                        16,703
                   18,397
       16.806
             18.028
15.410
                                            18,884
                 FY 1983
                                FY 1984
       Source: Office of Emergency and Remedial Response, U.S. EPA
              (September 30. 1984)

-------
                                     1-3


      o   Section 103(c)  required  owners or  operators, within
          180 days of CERQA's passage,  to notify EPA of  the
          existence of certain hazardous waste  treatment,
          storage, and disposal facilities and  any known,
          suspected, or likely releases  of substances from any
          facility, unless the facility  had  been  issued a
          permit or accorded  interim status  under the jtesource
          Conservation and Recovery Act, Subtitle C.  As discussed
          below, 4,nnn sites  were  identified  by this process.

      o   Investigation by government authorities. Section lD4(e)
          of CERCLA requires  persons who treat, store, or dispose
          of hazardous substances, to assist the  government in
          determining the need for response  to  a  release,
          Compliance may  involve furnishing  records of substances
          or permitting government access  to  a  facility for
          inspection or sampling purposes. The CERCLA section
          104
-------
                                     1-4
      EPA also used information contained in two other data bases.  The Site
 Tracking System operated by EPA's office of Enforcement added  3,200 potential
 sites.   Another major source for discovering sites  was the Hazardous Waste
 Data Management System.   Facilities  in  this data system that filed notifi-
 cations with EPA or the  states under the Pesource Conservation and Recovery
 Act, but later did not submit a Part A  application  for interim status, were
 added to the Emergency and Remedial  Response Information System data base.
 this added another 2,300 sites, after eliminating duplications.

      Ry the end of 1982, compilation of the various data bases was complete
 and the Emergency and Remedial Response Information System was ready for
 use as an inventory for  tracking hazardous  waste sites.  Exhibit 1-2 shows
 the expansion of the Emergency and Pemedial Pesponse  Information System.
 Other sources of discovery, such as  reports from citizens  and  state and
 local officials, were also added to  provide an  initial total of 13,392
 sites in the central data base.

      Additional sites have been added as they are reported to  EPA and a
 significant group of sites was added by the states  in 1983.  As of
 September 30, 1984 the Emergency and Pemedial Response Information System
 contained data on 18,884 sites.   Because site discovery efforts are con-
 tinuing, EPA anticipates that the number of discovered sites will reach
 approximately 22,000 by  1986.   Fbr example,  EPA continues  to receive
 citizens'  reports of suspected sites, as well as reports from  police, fire,
 health,  and other local  and State officials.  Reports of industrial and
 transportation accidents are potential  sources  for  supplementing the existing
 data  base.   Some states  are also using more systematic methods of discovery
 such as  industry waste stream tracking  or aerial photography.  Also, as
 resources allow, EPA may undertake more  targeted discovery efforts.  There
 are several types of sites that may  increase the current inventory of
 sites.   Briefly, these sites include the following:3

      Municipal Landfills;   An  investigation of municipal landfills could add
 significantly to the number of known hazardous  waste  sites.  Many municipal
 sites accepted both municipal  and industrial wastes that may have contained
 hazardous materials.   Although little attention  has been focused on these
 sites to date, many hazardous  waste  problems have already  been identified
 at municipal landfills.

      Facilities Permitted under the  Resource Conservation  and  Recovery Act;
 The number  of sites on ERRIS could increase if certain facilities regulated
 under the provisions of  the Resource Conservation and Recovery Act become
 Superfund sites.   The  likelihood  that a  facility regulated by  the Pesource
 Conservation and Recovery Act  will become eligible  for a Superfund response
will depend on the  probability that  (1)  a release will occur at the facility
 and (?)  that private or  other  sources of public  funds will be  available
 for remediation in  the absence of  a  Superfund response.
    3  For a more detailed discussion of the extent of the hazardous substance
release problem, see the CERCLA Section 301(a)(l)(C) study.

-------
                                    1-5
    Regulations promulgated under the Resource Conservation and Recovery
Act have minimum requirements for financial responsibility.  However, these
regulations cannot guarantee that releases will not occur or that all
owners or operators will have the financial strength  to cover  these costs.
Facilities with interim status under the Resource Conservation and Recovery
Act may go bankrupt or fail to comply with operational  standards and could
potentially become Superfund sites.  Furthermore, the regulations cannot
guarantee that a facility will not be abandoned or that funds will he
available after the end of the post-closure care period.  The number of
currently permitted facilities that may become Superfund sites will depend
largely on future EPA regulations inder both the Resource Conservation and
Recovery Act and Superftnd programs.

     Rites Involving Radioactive Wastes; The CERCLA section 101(22)(c)
definition of "release" specifically excludes some releases that are re-
gulated under the Atomic Rnergy Act and the draniut Mill Tailings Radiation
Control Act.4  Because of uncertainty over jurisdiction for these different
types of facilities, sites involving radioactive wastes may not have been
systematically reported to EPA.
   Excluded releases are:

   0  Release of source, byproduct, or  special nuclear material from a
      nuclear incident as defined in  the Atomic Fnergy Act of 1954
      (ABA, 42 U.S.C. 2011,  et seq.), if such release is subject to
      requirements with respect to financial protection under Section
      170 of the AEA.

   0  For the purposes of Section 104 of CERCLA or any other response
      action, any release of source, byproduct, or special nuclear material
      from any processing site designated under Section I02(a){l) or Section
      302(a) of the Uranium  Mill Tailings Radiation Control Act of 197R
      (WfTPCA).  There are approximately 25 sites designated under these
      sections of UMTRCA:  the Secretary of Ehergy may designate additional
      sites.

   0  In  addition, EPA has adopted the  policy that it will not use
      Superfund authorities  to respond  to releases from any facility with
      an  effective materials license from the Nuclear Regulatory Commission,
      because the Agency believes that  the Commission has the authority to
      control releases from  such facilities.  However, EPA will consider
      Superfund response to  a release formerly, but not currently, licensed
      by  the Nuclear Regulatory Commission.  EPA will also consider response
      to  releases from facilities which are licensed by Agreement States
      (States with authority to license the handling of radioactive materials
      under  agreement with the  Nuclear  Regulatory Commission).  Releases in
      which radicnuclides are  inseparable frcm other nonradioactive hazardous
      substances are also covered by CERCLA.  Radioactive releases from
      uraniun mining and processing sites which are not specifically
      designated by UMTRCA are  also covered by CERCLA.

-------
                                     1-7
      Federal Facilities;  Prior to  October 19RA,  no Federal  facilities were
 placed on the National Priorities List.   It is Generally  thought  that
 Department of Defense sites constitute about 85  percent of all  federal
 facility sites.  In this case,  F.PRIS already contains a larqe percentaqe
 of all potential federal sites.  However,  as a aroup, Federal facilities
 constitute only 3 percent of the total number of sites on EPRIS.  There may
 still  be a number of unlisted Federal facilities helonoinq to such aoeneies
 as the Department of Energy, the Department of floriculture, and the Depart-
 ment of the Interior.  The October 1984 proposed update to the National
 Priorities List includes 36 Federal facilities.

      agricultural Hse of Pesticides;  Several instances of around water
 contamination resulting, from the aciricultural use  of pesticides have been'
 reported in the past several years.  FPA is currently monitoring  wells and!
 qround water in areas where such contamination is  likely  to occur.  To
 date,  F.PA has found at least 15 different  pesticides in at least  20 States*
 It is, however, too soon to'1 estimate the size of this problem that may
 require Superfund response.  Sueh releases could conceivably  expand the:
 scope  of Superfund veil beyond  the number  of hazardous substance  problems
 envisioned when Superfund was created,

     Leaking Underground Storage Tanks;: nhtil recently,  reported- releases
 from underground tanks used to  store gasoline or hazardous substances wete
 United to random incidents that were handled by States and localities.  In
 the  past three to five years, EPA and State and  local governments- have been
 working to increase public awareness of the potential problems of underground1
 storaqe tanks.  This effort has  resulted in a growing number  of reports of
 leaking underground tanks,, and  it is expected that many additional cases
 will be discovered in the future.

     Mining Wastes;   Although mining wastes are  not  specifically  designated
 as hazardous substances under CEPCLA,  they may contain constituents designated
 as hazardous substances under section 101(14)  of CEPCLA.   F.PA actions at
 sites  can be considered as  responses  to  threats  posed by hazardous substances
 (e.g.,  lead,  cadmium,  zinc)  contained in the mining wastes.   The  courts to
 date have supported  this position (See,  for example,  n.s.  v.  Metate Asbestos
 Corp.,  (D.Az.Ap.lO,  1984).

     In a survey of  abandoned mines,  the Office  of Surface Mines  identified
 450  abandoned  mines  that could present a potential hazardous  substance
problem.  After Pegional review  and further site investigation, EPA added
85 sites  to  the Fjnergency and Remedial Response  Information System.  Because
of the initial uncertainty over  the status of mining  wastes,  however, mining
waste sites may not  have been identified as  systematically as other sites.
Additional mining waste sites may be  reported to EPA  which could  increase
 the  current  inventory of hazardous  waste sites.

     Future  Discovery F.fforts;   Sites which a particular  state is aware of,
hut has not reported to EPA, have not been entered in the  data base.  For
example,  a State may wish to take enforcement actions at a site and not
involve EPA, and thus does not inform F.PA of  the existence of the site.
These  sites may be added to RRRIS  in  the future.

-------
      All levels of government are responsible for carryinq out  scne aspects
 of site discovery.  RPA has initiated  certain methods of discovery, such as
 the CFPCLA section 103(c)  notification process.   Because initial discovery
 efforts identified a larqe percentage  of  the  more severe and visible sites,
 additional efforts are likely to be more  resource-intensive.  Such efforts
 will involve record searches and creative approaches to identify sites.
 EPA is currently developing a method  to systematically evaluate various
 industries to determine categories of  waste generators which are more likely
 to involve hazardous release problems  that require Superfund action.

      Generally, FPA's approach has been to compile a broad inventory of
 sites that may present potential problems. As a result, the Agency's
 experience has been that up to two-thirds of  the sites in  ERRIS that have
 received further investigation do not  contain hazardous substance release
 problems.   As the Agency undertakes more  targeted discovery activities it
 is likely that a higher percentage of  sites entered into the inventory
 will actually have hazardous release problems.

 Preliminary Assessments

      After a site is discovered and entered into the Emergency  and Remedial
 Response Information System,  EPA or the State response agency conducts a
 preliminary assessment to  determine what  future  actions need to be taken.
 As of September 3fl,  1984, preliminary  assessments  have been completed at *n
 percent of the approximately 1ft,QOO sites in  the data base.  The order in
 which sites receive preliminary assessments is based upon  the sites' apparent
 hazard potential.

      A preliminary assessment is  an initial evaluation of  the potential risk
 posed by a hazardous  waste  site.   The  purpose of  the preliminary assessment
 is to:   (1)  eliminate those sites from consideration which pose no threat
 to public  health and  the environment;  (2)  determine if there is potential
 for  immediate danger to persons living or working near the facility; and
 (3)  establish the  priority  for  scheduling a site  inspection.  Initially,
 only EPA Regional  Offices,  with assistance from  contractors, conducted
 preliminary assessments.  Currently, the  majority of preliminary assessments
 are  scheduled to be  conducted by  States with  funds provided through one-time
 awards  under section  3012 of  the  Resource Conservation and Recovery Act and
 cooperative agreements with EPA.

      Federal,  State,  and local  government files,  reports,  and court documents
may be  reviewed  to gather data  for a preliminary assessment.  Sources such
 as State water resource offices,  local planning agencies,  the U.S. Geological
 Survey,  and private and public well logs may be used.  In  certain situations,
 a perimeter survey of the site  is a part  of the preliminary assessment.
 Preliminary assessments seek  to determine:

     o   Hazardous substances present.  Where specific hazardous
         substances have been identified,   the preliminary  assess-
         ment  seeks to identify known  hazard  characteristics such
         as toxicity,  flammability, infectiousness, water  solubility,
         volatility,  soil blending affinity, and persistence.

-------
     o   Pollutant dispersal pathways .  Identifying potential
         pathvrays involves considering the geologic,  hydrologic,
         and climatologic features of the  site  to determine
         possible routes of exposure to receptors, or searching
         for existing monitoring data that could identify a
         pollutant's movement.

     o   Population and resources .  'this involves examining
         target populations and resources  that  may he affected by
         a release.
     o   Facility meaFig^peftt practices.  Characterizing site
         management practices may inclirle describing site
         security practices and specific treatment, disposal, or
         containment procedures (e/g.,  incineration).  Past site
         operations can be evaluated through aerial overflight
         photographs .

     o   Responsible parties.  Data is  gathered on site owners
         and operators, including whether the site is publicly
         owned by the federal, state, or local government or
         whether it is privately owned.

     The output of the preliminary assessment is  intended to classify a
site's priority for further investigation.   The preliminary assessment also
helps to identify data gaps to he filled during site inspections.  Depending
on the findings of this report, the site may require an immediate removal
(see Chapter 2); otherwise it is classified  according to one of three
categories:

     o   Wo further action sites.  Such sites pose no threat to
         public health or the environment, and thus warrant no
         further investigation or remediation.  Such sites were
         initially identified as hazardous waste  sites, hut
         further investigation revealed that the  site posed no
         serious problems.

     o   Pending si tes .  These sites require additional
         information  to evaluate if a site inspection is necessary.
         For example,  sites that may be under the jurisdiction
         of the Ftesource Conservation and Rscovery Act may he
         categorized as "pending,"  Most of  the sites in this
         category will eventually undergo site inspections.

     o   Inspection sites.  These are sites  that  have undergone
         site inspection*

Exhibit 1-3 illustrates the nunher of sites  that  have been placed in these
three categories after completion of the preliminary assessment, as of
September 30, 19R4.

-------
                                     i-in
 Site Inspections

      The purpose of a site  inspection is  to further define the problem
 posed by a waste site, or to reduce  the uncertainty associated with a site.
 Kor those sites that may require RPA action, the site inspection supplements
 information collected during the preliminary assessment.  The order in
 which sites are inspected is determined by the results of the preliminary
 assessment.

      The objectives of a site  inspection are to:

      o   Determine  what, if any, further action is necessary;

      o   Determine  if there is any immediate danger to people
          living or  working near the facility;

      o   Provide a  sufficient  data base to determine whether a
          site should be  included on the National Priorities list;

      o   Confirm preliminary assessment data that are otherwise
          poorly substantiated; and

      o   Update knowledge of si be conditions, if there are
          indications that changes may have occurred at the site.

      A site inspection generally provides the data necessary for the FPA
 Hazard Ranking  System. The activities conducted for site inspections are
 considerably more extensive than for the preliminary assessment.  In par-
 ticular,  site inspections require environmental sampling to identify the
 presence  of particular hazardous materials and the degree of migration of
 the substances.  A  significant amount of time and money is required for the
 development of  work and site safety plans, legal considerations (e.g.,
 obtaining site  access), equipment preparation, and completion of laboratory
 analyses.  During sampling, quality assurance/quality control must also be
 carefully maintained and chain-of-custody procedures must be followed.
 Depending upon  the  time it takes to analyze samples and ensure quality of
 results,  it may  take from one  to six months to complete a site inspection .

      EPA  discourages conducting geophysical testing, groundwaber monitoring,
 well  installation,  studies to  identify the precise extent of contamination,
 and other activities  that require specialized techniques during the first
 site  inspection visit.  If these are necessary, they are referred for a
 follow-up si be  inspection.

     The  findings that result fron a site inspection are categorized in a
manner similar  to those resulting from a preliminary assessment.  Data
provided  in EPA's Potential Hazardous W&sbe Site Inspection Report, which
is completed for each inspected site, are used to classify the sibe in
one of four categories:

     o   Nb further action sites.  Such sites do not pose a
          threat to public health or the environment and do not.
         require remedial attention.  This decision is unccmtton

-------
                                     1-11
          for properly identified  hazardous  release sites.  The
          cateoory may contain sites for which data from the
          preliminary assessment were inconclusive, but that
          proved to he non-hazardous after inspection.

      o   Pending sites.   These sites inay only reouire monitoring,
          and can be examined at a later date  to see  if a
          significant threat  is posed.   Alternatively, pendinq
          sites may not he evaluated adequately  with  available
          information. The inspection may show  that  some hazard
          exists, but a follow-up  site inspection is  required to
          determine the potential  threat to  public health or the
          envirornent.

      o   Hazard Ranking System.   These  are  sites that pose a
          significant threat  and for which there  are  sufficient
          data to assiqn a hazard  rankinq score.   (The. Hazard
          Ranking System is discussed below.)

      o   Emergency Cleanup.   The  results of the site inspection
          may indicate that emerqency cleanup action  is needed at
          the site.   If this  is the  case,  the EPA reqional office
          or  the state then determines what  action may be
          warranted.   In some cases, the site may fall under the
          jurisdiction of  the Resource Conservation and Recovery
          Act or the Nuclear  Requlatory  Commission and the site
          will  be referred to the  appropriate persons for follow-up.

      Currently,  EPA Reqional Offices, throuqh the use of the Field Investi-
gation Team  contractors,  perform  the maiority of site inspection activities.
In some cases,  a follow-up site inspection may be necessary if more data
are needed to score the site using  the  Hazard Ranking System.  At this
staqe, more  sophisticated techniques may be applied  if appropriate.  Fbllow-
up site inspections may be several  times more expensive than the initial
site  inspection.

Listing on the  Mational Priorities  List

     The  Hazard Rankinq System was  desiqned to  fulfill the CERCLA requirement
that  the  President  identify  at least 400 facilities  in the nation warrantinq
the highest  priority for  remedial action.  The Hazard Ranking System provides
a systematic approach for  setting priorities among several thousand widely
varying hazardous waste sites.

     The  ranking system measures  the relative severity of the problems at
the site and the  likelihood  and potential magnitude of human and sensitive
environmental exposure to hazardous substances.  A score is developed for
each release or potential  release based on  its  impacts on (1) ground water,
(2) surface water, or (3)  air.  These three scores are then weighted and
combined to yield an estimated hazard ranking score.  The scores can range
from n (least hazardous)   to  100 (most hazardous).  The Hazard Ranking
System was not designed to distinguish accurately between the risks presented
by two sites whose scores  are  similar, but  it is a meaningful indicator of

-------
                                    1-12
 different levels of risk between sites with large differences. The  hazard
 ranking scores are weigh ted  to increase the scores given to sites that
 threaten densely populated areas, that have a greater likelihood  of  exposure
 to the affected population, or that contain large volumes of waste.

     The Hazard inking System was developed to give consistent results
 when used by a wide range of people, within and outside FPA.  The process
 for using the  Hazard Ranking System to score a site and determine which
 sites  are placed on the National Priorities List involves the following
 tasks:

     o   Data  assembly.  Generally, a review of the site
          inspection is sufficient for determining a hazard
          ranking score.  However, additional information may be
          collected in the field,  A standard form is used to
          docijnent the scoring.

     o   Regional quality control.  EPA Regional staff check
          each  score and prepare data to be submitted to EPA
          Headquarters.  Sites receiving scores of 25 or above
          are  to be forwarded to EPA Headquarters .5

     o   Quality assurance/quality control by FPA Headquarters.
          For the National Priorities List promulgated on
          September 8, 1983, SPA Headquarters staff reviewed the
          evaluations and conducted quality assurance airiits on a
          sample of sites to ensure accuracy and consistency in
          the scoring.  For the first and second updates of the
          National Priorities List, all sites were reviewed for
          quality assurance/quality control.  Where appropriate,
          hazard ranking scores for individual sites ware
          recalculated by EPA Headquarters.

     o    Proposed rule.  A proposed  rule is published in the
          Federal Register, listing sites proposed for the
          National Priorities List.

     o    Rulemaking requiremen ts .  After a 60-day public comment
         period, ccmments are received and considered, and a
          final rule is promulgated.

     The National Priorities List serves as an information tool for  EPA  to
identify sites  that appear to present a significant risk to public health or
the environment.  Inclusion of a site on the List does not mean that FPA
necessarily will undertake response  actions, nor  does it. determine the
liability of any party for the cost of cleanup at the site.
  5  Although the cutoff score for placing a site on  the National Priorities
List is 28.5, EPA Regional staff are asked to submit  sites  with  scores of
25 or above because in the quality assurance/quality  control process EPA
Headquarters may add points that would  increase a site's score to 28 .5.

-------
                                       1-13


        The National Priorities List: currently lists 538 sites.  s   .Section
   105(b) of CERCLA also requires "to the greatest extent practicable" that
   the List include at least one facility designated by each State within the
   100 highest priorities.  This designated facility is to pose  the greatest
   threat to public health, welfare, or the environment among known facilities
   in that State, and does not have to receive a Hazard Ranking  System score
  '! of 38.5.  Eight of the 56 designated sites currently on the List do not
   have a score of 28.5 (including one in Guam and one in the Commonwealth of
   the Marianas).

        In accordance with CKRCLA requirements, the National Priorities List is
   updated annually.  Sites may be placed in a deletion category if:

        o   EPA, in consultation with the State, has determined  that
            responsible parties have completed all appropriate
            response actions?

        o   All appropriate Fund-financed cleanup actions under
            CERCLA have been completed, and EPA has determined that
            no further cleanup by responsible parties is appropriate?  or

        o   EPA, has determined, based on the remedial
            investigation, that the site poses no significant threat
            to public health or welfare or the environment and,
            therefore no remedial action is appropriate.

  Goals and Related Policies of Site Discovery and Investigation

        While  the goal of site discovery and investigation — to identify all
  potential hazardous substance releases and ensure that they are  brought to
  the attention of the appropriate authorities — has remained  the same
  throughout  the  first three and one-half years of the Ruperfund program,  the
  emphasis on different phases in the process has changed significantly.
  These changes reflect EPA's belief that many of the sites posing more
  serious problems have been identified and EPA resources should increasingly
  focus on further assessment and inspection of these sites.

        One major  change is the priority assigned  to site discovery,   initially,
  the emphasis was on completing the CERCLA section 103(c)  notification
  process and on  merging Federal and State inventories and creating the
  Emergency and Remedial Response Information System.   In late  1982,  EPA
  received a  one-time appropriation to allocate funds to States to conduct
  site  surveys and inspection process,   tinder this program to implement
  section 3012 of the Resource Conservation and Recovery Act, EPA  identified
    6 48 PR 175, September 8, 19«3 (406 sites were placed on the final List);
and 49 FR 90, May 8, 1984 (4 sites proposed on September 8, 1983 were placed
on the final List).  Seven sites are listed as pending, and 128 additional
sites were placed on the final list in September 1984.  These sites were proposed
in the September 8, 1983 Federal Register.

-------
                                     1-14


 funded activities in  the  following order of priority:  preliminary assess-
 ments, site-inspections,  responsible party searches, discovery, and site
 inspection  follow-up.

      RPA's  targets,  set in  May 1983, are to:  (1) complete preliminary
 assessments for all  sites on  the Bnergency and Remedial Response System hy
 the end of  fiscal year 1986;  and (2) complete site inspections for sites
 that warrant inspection after the preliminary assessment by fiscal year
 1987.  Whereas EPA had been responsible for conducting most of the pre-
 liminary assessments  prior  to mid-1983, the States are now responsible for
 these activities with 3012  awards and funding provided in cooperative
 agreements.  EPA will conduct approximately 75 percent of the site inspections,
 with States conducting the  remainder.

      There  have been  no major policy changes related to the Hazard Ranking
 System.  The  one criterion  in the National Contingency Plan for listing
 sites en the National Priorities List is a sufficiently high hazard ranking
 score.  In  the first  update to  the National Priorities List, EPA proposed
 the addition  of the Ouail Run Mobile Manor site, Rray Suimitt, Missouri to
 the List, although the site's total score was below the 28 .5 cutoff.  In
 adding the  Ouail Pun  site to  the List, EPA stated its intent to "amend the.
 National Contingency  Plan to  authorize consideration of limited criteria
 other than  the total  hazard ranking score for purposes of including sites
 on  the National  Priorities  List."  In amending the National Contingency
 Plan,  EPA will consider using health assessments or advisories issued by
 other  Federal  agencies.

     EPA's  policies related to  the Hazard banking System and the National
 Priorities  List may be  altered by the Federal Courts as a result of a
 nunber of law suits that  have-been filed against EPA.  The major issues
 being  raised  in  the cases include:

     o   The  integrity and  accuracy of the Hazard Ranking .System;.

     o   EPA's authority  to respond and therefore to list sites with
          mining  wastes;

     o   Whether EPA  can properly list radiation sites that are regulated
          by Agreement states, but not list sites that are
          regulated by the Nuclear Regulatory Commission;  and

     o   Challenges that relate to the accurate  documentation of
          conditions at a site.

The decisions resulting from  the litigation over sites will affect not only
 the process for selecting priority  sites,  but could potentially affect the
 timeliness of responses at sites.

Major Accomplishments of Site Discovery and Investigation

     The Superfund program has a nunber of accomplishtients in site discovery
and investigation.  As of September 30,  1984,  major accomplishments inclirie:

-------
                                     1-15


      o   The probable discovery of the more serious  hazardous
          substance sites and releases in the country;

      o   Establishment of the Emergency and Remedial Response
          Information System as a storaae and retrieval system
          available to EPA headquarters, the reqions, the states
          and the public;

      o   Completion of over 10,700 preliminary assessments;

      o   Completion of approximately 3,600 site inspections;

      o   Scorinq of 1,732 hazardous waste sites;

      o   Listing of 410 sites on the final National  Priorities
          List in September 1983;

      o   Continued expansion of the National Priorities List,
          with 133 sites proposed for listinq in September 1983
          and 128 sites added to the Final List in September 19B4.

      o   Proposal of the second update  to the List with 244 sites
          in October 1984.

      These  accomplishments illustrate a major trend  with respect to this
initial phase of activities —  the  continued increase  in EPA's knowledge of
the extent  and nature of the problems at  hazardous waste sites nationwide.
This  trend  has characterized the Superfund program since its  inception and
continues to do  so more than three  years  later.  Althouqh no  comprehensive
site  discovery program is  underway,  the current inventory of  sites discovered
(18,900)  is expected to continue).   Notifications from Federal, State, and
community hotlines,  and aerial  photography continue  to  contribute to the
site  discovery inventory.   Random discoveries by EPA's  Remedial Planning
and Field Investigation Team contractor and  State agencies are other sources
for identifying  potential  hazardous release  sites.

      Future accomplishments  in  site discovery will depend not only on
the states' voluntary level  of  activity,  but also on EPA's policy regarding
an aggressive discovery program.  For example,  if EPA undertakes an active
review of municipal landfills or of certain  types of facilities under the
Resource  Conservation and  Recovery Act, site discoveries may  increase
significantly.

      Although the effects  of EPA's  shifts in emphasis on the  performance of
site discovery and  investigation are  not yet  fully known, some observations
relevant  to future  program accomplishments can be made.  First, EPA assumes
that; more preliminary assessments will be  conducted because an increased
emij>l|asis  has been placed on  these activities,  and the States  have been
      resources and  the authority to  conduct  them.
     EPA's decision to have States conduct site discovery and investigation
activities may affect the consistency with which sites are categorized.  No
formal criteria have been developed for placing sites as "no further action,"
"pending, " or as needing additional assessment.  There was less of a need for

-------
                                     1-16
 such  criteria when EPA or  its contractors made these determinations.  However,
 now that each State is placing sites within these categories, there may be a
 greater  need  to ensure consistency  in how sites are identified.


                         REDUCING IMMEDIATE HAZARDS
      In  the course of  investigating sites to determine the need for federally
 financed cleanup, EPA  and  the States also attempt to identify sites presenting
 an  immediate hazard that must be addressed quickly.  For example, a site
 may score  below  the 28.5 cutoff and therefore be ineligible for remedial
 action.  However, the  site may pose an immediate threat that requires some
 short-term action.  For sites that score above 28.5, there may be conditions
 at  the site which pose an  immediate threat and cannot wait for the more
 lengthy  processes of remedial planning or enforcement action.

     EPA  or the State may identify a situation that presents an immediate or
 imminent hazard  during a preliminary assessment or site inspection.  Also,
 EPA or the State may determine that there is an immediate hazard after
 scoring  the site under the Hazard Ranking System.  The ranking system
 contains two variables for "fire and explosion" and "direct contact" primarily
 for the  purpose  of "flagging" ranked sites that represent immediate or
 imminent hazards, to ensure that such sites receive expedited attention.

     There are two types of actions that may be taken to reduce or mitigate
 immediate  hazards at ranked sites.  The first of these actions, an immediate
 or  planned removal ,*?  may  be taken in response to a release notification or
 the identification of  an imminent threat through the site investigation
 process.   Immediate removals may also be initiated at sites on the National
 Priorities List.  In fact, many of EPA's removal actions are undertaken at
 sites that are identified  through the discovery and investigation process.

     The second  type of action is an initial remedial measure and may be
 taken only at sites on the National Priorities List.  Initial remedial
measures are actions that  can be taken quickly to limit exposure or the
 threat of exposure to a significant health or environmental hazard at
 ranked sites where planning for remedial actions is underway.  The category
of activity was created by the 1982 revisions to the National Contingency
Plan.  According to the NCP, criteria for determining whether an initial
remedial measure is appropriate are the following:^

     (1) Actual or potential direct contact with hazardous
         substances by a nearby population;
    See Chapter 2 for a full description of removal actions.

    National Oil'and Hazardous Substances Contingency Plan, Office of
    Emergency and Remedial Response, U.S. EPA  47 FR 31216 (See 40 CFR Section
    300.68(e)) (July 16, 1982}

-------
                                     1-17


      (?.)  absence of  an  effective drainage control system;

      (3)  Contaminated drinking water at  the  tap;

      (4)  Hazardous substances in drums, barrels, tanks, or other
          bulk storage containers,  that are known to pose a
          serious threat to public  health or  the environment;

      (5)  Highly contaminated soils largely at or near  the surface,
          posing a serious threat to  public health or the
          environment;

      (6)  Serious threat of fire or explosion; or

      (7)  Vfeather conditions that may cause substances  to migrate
          and  pose a  serious threat to public health or the
          environment.

      Originally, in  addition bo addressing imminent hazards, EPA's intention
was  to use  initial remedial measures as a mechanism to take relatively
simple measures at a si be while the  complex, long-tern) remedial planning
process was underway.  These were measures that could be easily identified,
where there were few or  no alternatives, and which were relatively low
.cost. The  procedures for initiating an initial remedial measure are similar
to,  but shorter than, those for conducting a full-scale remedial investigation
and  feasibility study (described in  the next section) .

      After  a  site is listed on the National Priorities List, the lead
agency (EPA or  the State) conducts an initial scoping of available information
to determine  the type or types of remedial response that may be needed for
the  site.  Based  on  this scoping,  the lead agency may determine that an
initial measure is feasible and necessary to limit exposure or threat of
exposure  to a significant health or environmental hazard.  In addition,
the  lead  agency assesses whether the measures are consistent with the
long-term remedy proposed for the site, and if such measures are cost-
effective .

      ("Vice the lead agency determines that an initial remedial measure is
appropriate,  the  lead agency undertakes a nunber of preliminary steps for
planning  and securing approval of  the proposed action.  Initial remedial
measures generally involve actions of two types:

     o    Simple actions  such as fencing, drum sealing,  or
         controlling run-off from  the site, that may be completed
          in a relatively short period of time.  To ensure that
          the proposed action is consistent with a permanent
         remedy,  a limited evaluation of the cost-effectiveness
         of the proposed action must be made.  In addition,
         either a public meeting cr a two-week public comment
         period on the planned action must be held.

-------
                                     1-18
      o   More ccreplex actions such as off-site transport  of
          wastes, storage of drums or substances not in con-
          tainers, or supplyina temporary water supplies.   Such
          actions may be components of the overall remedial action,
          but for which field work can be expedited.  These require
          a more extensive planning and approval process than
          simple actions, as well as a public meeting and  two-week
          comnent period on the planned action.

 Acccnplishments

      Until the spring of 1983, FPA'S policy was to undertake removal  actions
 only in the most urgent situations — situations of immediate and significant
 harm that reguired rapid response {see Chapter 2).   Since then,  EPA has expanded
 its initial interpretation of NCP criteria for taking a Fund-financed removal
 action, allowing EPA to address potential hazards as well as existing
 threats.  This has significantly expanded the Agency's actions at sites not
 on the National Priorities List which may pose an inrnediate and  significant
 risk of harm.  EPA took 9 removal actions at sites  not on the List  in
 FY81, and at 18 sites not on the List in FY82.  Tn  FV83,  the number went up
 to 67 removals at sites not on the National Priorities List.   In FYR4,
 the number of removals started by EPA at sites not  on the National  Priorities
 List was 148.  This is an important increase in activity,  since  removal
 actions are the primary mechanism for addressing sites not on the NPL.
 The U.S.  Ooast Guard started 37 removal  actions at  non-WPL sites through
 the end of FVfi4« ia of these were started in FV84 alone.

      At NPL sites, EPA has undertaken both removal  actions  and initial
 remedial measures.  Until the spring of 1983,  most  removal actions  at
 Priorities List sites were limited to small scale stabilizations to reduce
 only the most immediate hazards.   Altogether,  EPA has initiated  142 removal
 actions at NPL sites, as of September 30,  1984.   The U.S  Ooast Guard  has
 initiated a removal at one additional NPL site,   since the spring of  1983,
 the scope of removal actions at NPL sites  was  broadened to  encourage more
 extensive surface cleanups.

      At the same time,  initial remedial  measures have been undertaken at 39
 sites through FY84.   There have been relatively few initial remedial
 measures because there is little  distinction between the  type of on-site
 activities conducted for initial  remedial  measures  and removal actions.
 The criteria established in the National Contingency Plan for determinina
 whether to conduct an initial  remedial measure are  essentially the  same as
 the criteria for determining the  need for  removal actions.  However,  E^A
 policies  and guidance have reguired  substantially more documentation  for
 initial remedial measures to ensure conpliance with the cost-effectiveness
 reguirements of  the  NCP and  to enable EPA to demonstrate,  for cost-recovery
 purposes,  that  initial  actions are consistent  with  the NCP.   Because  of
 the additional administrative  requirements,  initial  remedial  measures are
more  time consuming  to conduct than  removals.

-------
      Initial remedial measures have had only limited success as a mechanism
 to take expedited action at NPI, sites.  However, removal actions are becoming
 an increasingly important and effective mechanism to provide guick response
 to immediate hazards at both NPL and non-NPL sites.  They are particularly
 important as a means of response at lower priority sites which have a small
 but serious, or potentially serious, hazardous substance problem.  In up-
 coming revisions to the National Contingency Plan, EPA is considering
 introducing the concept of "operable units" into the remedial planning and
 implementation process.  This would a'llow a phased approach to remedial
 action to replace initial remedial measures.


            UNDERSTANDING- THE PROBLEM AND SELECTING CLEANUP ACTION


      For all sites on the' rational Priorities List, a detailed study and
 evaluation must be conducted fco determine how to clean up the site.   This
 involves several stages of activity*  first, management planning to initiate
 activities at the site; then conducting a remedial investigation and feasibility
 study;  and finally, selecting the appropriate cleanup action.  Initial
 remedial measures or a removal atetion may be conducted at the site while
 these remedial planning activities are under way.  Exhibit 1-4 illustrates
 these activities.

 Initial Planning Activities

      Once sites are listed on the National Priorities List,  a number of
 factors determine when EPA will initiate remedial activities at a given site.
 These include:  the likelihood of securing responsible party cleanup through
 enforcement action;  the staters priorities and resources for undertaking
 action  at sites;  and management of Superfund resources among the sites
 awaiting action.

      To ensure that resources are available and  allocated effectively,  the
 EPA regions and States coordinate in scheduling  and planning remedial
 activities.   A comprehensive management plan provides a long range timetable
 for Superfund activities at ea'ch site.   In addition,  at the  beginning of
 each  guarter and  fiscal year, :EPA Regions submit a plan that identifies
activities  to be  conducted -a!t 'various sites in the Region and their  cost
during  the  time  period covered i'n the plan.   This Accomplishment Plan is
the official mechanism for r$PA :o i'deHti'f y demands on  the Trust Fund  for
Superfund activities.   It  indicates expected expenditures for removal and
remedial actions, enforcement,  community relations, contract laboratories,
and other program components.   The Assistant Administrator must approve the
Accomplishment  Plan  before  the  regions may obligate funds.

     After  a  site is scheduled for nanedial planning,  the regional community
relations coordinator or a state'dffieial prepares a  community relations
plan prior  to the start of  the remedial  investigation.   This plan, prepared
by the lead agency for the  site,  specifies  communications activities to be
conducted at  the  site to keep the community informed  of site activities and
to incorporate community concerns  in  the  remedial plans  for  the site.   In
preparing the community relations plan,  Regional and  State community relations

-------
                                     1-20
 staff participate in community discussions with  citizens and officials
 affected by the site to assess their concerns  about  the site.  The community
 relations activities must be  tailored to the specific concerns of the
 community and must be closely inteqrated with  the technical schedule for
 the site.

      The proposed activities  must also go throuejh intergovernmental review
 prior to starting the remedial investigation.  The procedures for this review
 are specified in 40 CFR Part  29,  and include notifying the State and local
 governments and other affected entities of a proposed remedial project.
 After notification,  a 60-day  Garment period is provided on the proposed
 project.9

      Hie EPA and State responsibilities for conducting a remedial
 investigation and feasibility study  at a site  are specified in a cooperative
 agreement or State letter of  reguest,  depending  on whether the State or EPA
 is  the lead agency.   These agreements are negotiated between the Regions
 and States as part of site planning  activities.!0

 Conducting a Remedial Investigation  and Feasibility  Study

      A remedial investigation involves a series  of detailed studies of a
 site  to characterize  the  site  and  identify the source and extent of contami-
 nation.   In particular, these studies  provide data in sufficient detail to
 develop and  evaluate  alternatives  for  cleaning up the site.  For EPA-.lead
 sites,  site work is  conducted by  the Remedial Planning and Field investigation
 Team  contractor,  under EPA's  supervision.  For State-lead sites, site work
 is  conducted or managed by the State agency.  EPA assigns a State project
 officer to oversee any contractor  work  at a State-lead site.

      The  scope of a  remedial  investigation is determined in part by existing
 information  on  the site.   The  study  may include  aerial photography and
mapping of  the  geology, geography, and hydrology of  the site.  Other tech-
 nigues  that  may be used to study the site include sampling, monitoring,
 tests to  determine permeability of the soil, etc.  Samples collected during
 the remedial  investigation are sent  to an approved laboratory for analysis.

     As additional data are collected  and analyzed,  studies of the site become
progressively more focused on  identifying possible methods for cleaning up
 the site.  For  example, if heavy eguip^ent is expected to be used during
clean up, tests will be conducted to determine where to locate the eguipment
or where  to  construct  roads so that  the stability of the site is not dis-
turbed.
     9  "State Participation in the Superfund Remedial Program," Office of
 Emergency and Remedial Response, n.s. EPA (February 1984), Appendix n —
 Procedures for Implementing Intergovernmental Review.

     in  por further information on remedial planning agreements, see "State
 Participation in the Superfund Remedial Program," Office of Emergency and
 Remedial Response, U.S. EPA (February 1984).

-------
     Rased on the results of the remedial investination, the contractor or
State agency develops specific alternatives for cleaning up the site.  Tt»e
remedial investigation and feasibility study report prepared during this
stage summarizes the findings of the site study, the alternatives developed
and evaluated, and the basis for eliminating some of the alternatives.  The
National Contingency Plan establishes the following steps conducted during
the feasibility study:

     1.  Develop Alternatives.  The contractor or State agency
         develops a limited number of alternatives either for
         source control (controlling the source of contamination
         at or near the area where the hazardous substances were
         originally located), or off-site remedial actions
         (actions necessary in cases where hazardous substances
         have migrated from the area of their original
         location).  The alternatives nay include a no-action
         alternative, when a response action would cause a
         greater environmental or health danger or where, after
         detailed analysis, the lead aqency concludes that the
         site does not present a potential danger to public
         health or welfare or the environment.

     2.  Initial Screen.  The contractor or State agency conducts
         an initial screening of each of the alternatives
         developed for the site.  Three broad criteria are used
         in the initial screening process:

         —  Costs, including the costs of installing or
             implementing the alternatives and the costs of
             operating and maintaining the site.

         —  Effects of the alternative, including any adverse
             environmental effects and whether the alternatives
             will adequately control the contamination and
             effectively mitigate and minimize the threat to
             public health or welfare or the environment.

         —  Acceptable engineering practices, including those
             practices that are feasible, applicable to the
             problem, and represent a reliable means of
             addressing the problem.

     3.   Detailed Analysis.  After the initial screening, the
         contractor or State agency analyzes in detail the
         alternatives that pass the initial screening.
         This detailed analysis includes:

         —  Rsfinement and detailed specification of
             alternatives, with emphasis on the use of
             established technology;

         —  Detailed cost estimation, including distribution of
             costs  over time;

-------
                                       1-22
            —  Evaluation of enqineerinq implementation, or
                construetability;

            —  Assessment of each alternative's ability to mitigate
                effectively and minimize damage to, and provide
                adequate protection of, public health and welfare
                and the environment, relative to the other
                alternatives analyzed; and

            —  Analysis of any adverse environmental impacts,
                methods for mitigating these impacts, and costs of
                mitigation.

   On the basis of this detailed analysis, the remedial alternative or
   combination of alternatives determined to be most cost-effective is
   recommended for implementation.   Examples of cleanup actions analyzed
   during a feasibility study include groundwater treatment, placing a cap on
   the site to reduce migration of  contaminants, or excavating  leaking drums
   and tanks and/or contaminated soil and removing them from the site.

        Throughout the remedial investigation and feasibility study, the
   Regional or State project officer is responsible for monitoring activities
   at the site and helping community relations officials to conduct activities
   as specified in the community relations plan.  Community relations  activities
   are conducted to ensure that the response agency informs affected citizens
   of site activities and elicits their input and concerns. Oomjnunity relations
   activities conducted for a site  include preparing fact sheets and/or  progress
   reports, establishing a location where all technical  documents and  infor-
   mation are available to the public, holding small group meetings, workshops,
   public hearings, and other activities.

   Selecting the Remedy

         The process for selecting  the appropriate remedy for a site beqins with
   the completion of the draft remedial investigation and feasibility  study
   report.   The draft report is reviewed by State,  EPA Regional,  and Head-
   quarters staff,  and other Federal agencies,  if appropriate.   For all  sites,
   a minimum three-week public comment period is provided to review the  remedial
   investigation and feasibility study.   A community relations  responsiveness
   summary is prepared following the comment period.   The responsiveness summary
   describes the comments received  and how FJPA or the State considered the
   comments prior to selecting the  cleanup option.

       After review and public comment on the  remedial  investigation  and
   feasibility study report,  Regional and State staff prepare a draft  decision
   document for either Ftmd-financed or responsible  party remedial  actions.H
    "Fbr further discussion of the process for developing and approving a
record of decision, see "Preparation of Decision Documents For Approving Fund
Financed and Responsible Party Remedial Actions," Memorandum from Lee Thomas,
Assistant Administrator for the Office of Solid Waste and Emergency Response.

-------
                                    1-23


     Fund-Financed Remedial Actions;  The draft Record of Decision and
supnortina documents, summarize the alternatives that were evaluated in the
detailed analysis conducted during the feasibility study.  The primary purpose
of the decision document and supporting information is to document the
decision process and denwnstrate that the remedial action is consistent
with CEPCLA and the National Contingency Plan.  The typical areas discussed
in the Record of Decision or supporting information include:

     o   Consistency with the National Contingency Plan sections
         330.68(g) through (i) for developing, screening, and
         evaluating alternatives.

     o   Documentation that a no-action alternative was evaluated
         and the reasons for eliminating the no-action
         alternative.

     o   Extent of remedy, including comparison with any EPA
         standards or criteria, or other environmental laws or
         regulations, or other approach used to establish level
         of cleanup.

     o   Cost estimates for all final alternatives evaluated in
         the feasibility study including remedial action cost,
         annual operation and maintenance cost,  and total present
         worth.

     o   Evaluation of the cost-effectiveness of the alternatives
         according to the factors in the National Contingency
         Plan sections 300.6fl(h)  and (i).

     o   Documentation that the reguirements of  CEPCLA section
         101(24)  have been met for any recommended remedy
         involving off-site transport,  storage,  destruction, or
         disposal of hazardous wastes.   The section 101(24)
         requirements specify that the  remedial  action, or
         component involving off-site transport, storage, disposal,
         etc.   activities,  must be shown to be more cost-effective
         than other remedial actions,  will create new capacity to
         manage hazardous substances in addition to those at the
         facility, or is necessary to protect public health or
         welfare  or environment from a  present or potential risk.

     o   The responsiveness summary details the  concerns of the
         community and potential  responsible party(ies) and how
         EPA or the state responded.

     o    Description of future  operation and maintenance
         activities needed for the site and how  the state expects
         to  fund  and conduct  activities.

-------
                                    1-24
     The Record of Decision package prepared by the Region and State is
 submitted to EPA  Headguarters  for review.  The EPA headguarters process for
 review.and approval of the package ensures that all appropriate offices are
 involved.  For instance, EPA's Office of General Counsel reviews each
 document to  ensure compliance with statutory reguirements.

     Based on comments from the reviews, revisions to the Record of Decision
 are made if  needed, and concurrences are obtained.  The final step in the
 process  is to brief the Assistant Administrator for the Office of Solid Waste
 and Bnergency Response, and obtain his approval of the recommended action.

     Responsible  Party Petnedial Actions;  The process for selecting the
 cleanup  action at enforcement-lead sites is similar to the process for
 Fund-financed remedial actions.  At the completion of the feasibility
 study, and following a public comment period, a Negotiation Decision Document
 is prepared  by the EPA Region in coordination with EPA Headguarters and the
 affected State.   This document identifies the alternative recommended by
 the Region and State to be used as a basis for negotiating with potentially
 responsible parties.  The criteria established in the National Contingency
 Plan for screening alternatives must be met and the alternative must
adeguately protect public health" and the environment.  Cnce approved by the
Assistant  Administrator, EPA uses the Negotiation Decision Document in
negotiating with potentially responsible parties.

     When  negotiations are successfully concluded, an Enforcement Decision
 Document is prepared for the site.  This document serves as the Record of
 Decision for  selecting the remedy and documents EPA's concurrence with the
terms of the settlement with private parties.  The Enforcement Decision
Document is a public document and is available for public review and comment.

Goals and Related Policies of Remedial Investigation and Feasibility Study

     The goals of the remedial investigation and feasibility study stage
     are to:

     o   Characterize the source and extent of contamination and
         the geography, geology, and hydrology of the site.

     o   Identify alternative cleanup measures, their
         reliability,  effectiveness at cleaning up the site, and
         associated impacts and cost.

     o   Select an alternative that provides adeguate cleanup and
         is cost-effective.

     o   Ensure state involvement and consultation in remedial
         alternatives.

     o   Ensure community involvement in remedial planning to
         address the needs  and concerns of the affected public
         and  to meet National Environmental Policy Act functional
         eguivalency reguirements.

-------
                                     1-25
 These goals have remained relatively constant throughout the history of  the
 Super fund program.  However, relevant EPA policies and guidance have changed
 during the first three and a half years of the program, and these changes have
 affected the way and extent to which these goals have been met.  The following
 sections discuss the specific policies related to the implementation of
 remedial investigation and feasibility studies.

      State Participation;  The National Contingency Plan encourages State
 participation in response actions.  Section 300.62, which outlines the
 specific reguirements for State participation, is intended to encouraoe
 States to undertake response action.   The reguirements are as follows:

      o   EPA will provide assistance  to the States pursuant to  a
          cooperative agreement or contract authorizing States to
          undertake most actions specified in the National
          Contingency
      o   States must enter a cooperative  agreement or. contract
          with  the Federal  Government before any Fund-f inanced
          action can be unQeiftakeft'i  The cooperative agreement or
          contract must include CKe' statutory assurances
          established in section  lf)4(c)  for State cost-sharing for
          remedial actions,  including State financing of their
          share of remedial planning costs, providing for  the
          costs of operation andt maintenance of  the site,  and
          providing a facility for the off-site  treatment  or
          disposal of hazardous substances  if necessary.

      o   EPA will consult  with the affected State before
          determining the appropriate remedial action.

      In  the spring of 191*3,  EPA  instituted a major shift  in emphasis  in  the
Superfund program to speed' up flund-f inanced remedial action.  As of April
19R3,  only 66  remedial investigation/feasibility studies  had been initiated.
From  EPA's experience,  a major cause for delay  was the reguirement that  States
pay for  10 percent of remedial planning costs,  and provide  their  statutory
assurances at  the  outset of the remedial planning  effort.   Many States
encountered administrative  and financial constraints in meeting this
reguirement.

    In May 1983,-  EPA implemented policy changes to expedite remedial  planning
activities.  These werer

     o   State cost-share for remedial  planning.   FPA waived  the
          regulatory  reguirement for cost-sharing for remedial
         planning activities (including remedial  investigation,
         feasibility study and remedial design activities)  at
         privately-owned sites (40 CPR  30.720(a)).

     o   Timing of assurances.  The statutory assurances  for
         state cost-sharing, off-site facilities,  and operation
         and maintenance costs, are not finalized  until
          immediately prior  to the initiation of remedial
         construction.  Ifcraft operation and maintenance plans,

-------
      Community Involvement!  The National Contingency Plan also states that
 response personnel should, to the extent practicable, "be sensitive to
 local cormnunity concerns (in accordance with applicable guidance)."12
 EPA understands the need to be sensitive to community concerns at  hazardous
 waste sites throuqhout the Superfund response process.  However, EPA has been
 developing more effective approaches to ensure community involvement as the
 Aqency gains experience with the program.  Early experience with hazardous
 waste sites indicated that the success of the Superfund program depended on
 EPA or the state developing and implementing an effective community relations
 program.  However, for such a program to be effective, the reguirements
 must be flexible enough to meet the community concerns and issues  at each
 site.  As a result, EPA did not consider it appropriate to issue strict
 reguirements for community relations at Superfund sites.  Instead, the Agency
 issued a policy memorandum in November 1981 that specified flexible program
 reguirements.13

      In November 198?, EPA initiated a review of the effectiveness of the
 community relations program.  The findings of the review indicated that the
 community relations program was not being implemented consistently in each
 Region.  The few community relations plans that were prepared  generally did
 not adeguately reflect site-specific community concerns and needs.

      As a result of these findings, EPA issued a community relations policy in
 May 19R3 and published CCnmunity Pelations in Superfund;  A Handbook,
 Interim version, September 1983.   EPA policy is intended to ensure that: fl)
 communication is established and maintained between EPA and state  officials
 and the community; (2)  communities are kept informed of site activities; and
 (3) community concerns are incorporated in the remedial plans  developed for
 the site.   The May 1983,  Community Pelations Policy established the following
 reguirements for community relations during remedial planning  activities:

      o   A community relations plan covering the remedial
          investigation and feasibility study must be prepared
         prior to the initiation  of the remedial investigation.
         The plan must he based on discussions with the local
         officials and  citizens of  their  concerns  about the
         site.   A revised plan must also be in place for the
         remedial  design  and construction phase.

      o  A  three-week public comment period must be provided on
         the  feasibility  study.   (This  also ensures "functional
         eguivalencv" with  the public participation reguirements
         of the National  Environmental  RxLicy Act.)
 12  National Oil and Hazardous Substances Contingency Plan, U.S. EPA
     47 FP 31?/4,  (July 16, 19«2) (See in CFR Section 300.fi!).


  13 "Superfund Community Pelations Policy and Guidance," Office of
Emergency and Pemedial Response, TJ.S. EPA (November 18, 1981).

-------
                                     1-27


      o   A community relations responsiveness summary must he
          submitted with the draft record of  decision.  The
          summary should describe  the comments received and how
          EPA or the State responded.

       In addition to the policy and  guidance, EPA has recently  initiated a
 community relations trainina workshop to be  conducted in every  region by
 October l^R^.   The trainina proaram  is designed to provide EPA  and state
 technical,  enforcement, and community relations staffs with additional
 ouidance on how to implement an effective community relations program.

      Delegation of Authority to the  Fegions:  EPA recoqnized that the
 Aciency's Headquarters approval process could cause delays in the proaress
 of  remedial actions as the number of remedial investiqations and feasibility
 studies increased.  Tn the sprinq of 1Q84, EPA delegated authority to the
 Regions for negotiating and siqninq  cooperative aqreements and  State Super-
 fund  contracts.   Tn addition, authority for  initiating and conducting
 remedial investigation,  feasibility  study, and remedial design  activities
 was delegated  to the Regions.  Previously, such activities reguired approval
 by  the Assistant Administrator for the Office of  Solid Waste and F)nergency
 Response.

 Major Accomplishments;

      In the first two and a half  years of the Superfund program, progress
 in  responding  to uncontrolled hazardous waste sites was was affected by a
 number of policy issues.   However, progress  has speeded up considerably in
 the last 2  years.   Exhibit 1-5 presents past and  projected annual numbers of
 remedial investigation and feasibility studies.   These annual numbers are
 also  broken down into the following  categories:

      0   PI/FS  actions financed by the Fund at Fund-lead sites;

      0   PI/FS  actions financed by the Fund at enforcement lead  sites; and

      0   RI/FS  actions undertaken  by  responsible parties.

 As  illustrated in Exhibit 1-5, 315 remedial  investigation and feasibility
 studies have been initiated as of September  30, 1984, of which  over «2
 percent  have been initiated  since the start of FYS3.  The number of remedial
 investigations/feasibility studies that are  under way is a predictor of the
 increased design and  construction activity that will occur in FY 1985, and
 in upcoming years.

     Cleanup T>ecisions;  Exhibit 1-R  located  at the end of this  chapter,
presents information  on  some of the  cleanup alternatives that have been
approved for Superfund  sites.  A  sample of 2fi records of decision were
reviewed for this  analysis.  This exhibit lists each of the decision documents
and provides a brief  description  of  the site problems, previous actions
taken, the remedial alternative recommended for the site, and the estimated
cost of  the  recommended  alternative.  In addition, analysis of  this sample
reveals that:

-------
      0   In almost every case, the remedial alternative included
          source control measures.  At six sites, off-site
          remedial action was included with source control
          measures, and at one site, an off-site action alone was
          recommended.

      0   The primary types of responses taken at the 26 sites were
          removal and off-site disposal of wastes, treatment of qround
          water, provision of alternative water supplies, capping
          contaminated areas, and construction of trenches.

      0   EPA is required to choose a cost-effective remedy.
          In 11 of the 19 cases in which cost ranoes for final
          alternatives were summarized,  the least-cost alternative
          was also the most cost-effective,  itie most costly alternative
          under consideration was the most cost-effective in 4 of these 19
          Records of Decision.

      0   Several decision documents cited public comments in
          modifying the selected alternative.  Seven documents
          explicitly stated that the public endorsed the remedial
          alternative selected.

      0   At approximately 60 percent of the sites reviewed,
          previous actions were taken at the site.   These
          actions include fencing the site, removing surface
          debris, and providing temporary drinking water supplies.
          In addition, in 11 of the 2P  Records of Decision,
          the approved alternative was an initial remedial measure
          or an interim phase .of cleanup.   Thirteen of the approved
          alternatives involve final cleanup measures.

      0   Three of the records of decision cited regulatory  standards
          or recommended concentration levels for contaminants to
          support the chosen remedy.  One document referred  to a  Centers
          for Disease Control judgement concerning polychlorinated
          biphenyl levels to justify the selection of an alternative.
          Environmental concentrations and other Quantitative factors were
          comnonly cited to identify the desired level of cleanup,  as well
          as to characterize  the environmental problem.

     These  findings  indicate that there are a number of issues that have
affected  cleanup decisions,  and that EPA is currently working to resolve.
EPA recognizes that  identifying and selecting the cleanup action has
been affected  by the  lack of adequate guidance on  determining the  appropriate
extent of remedy.  The National Contingency Plan criteria for selecting the
appropriate extent of remedy were designed to allow EPA flexibility in
selecting remedies to accommodate conditions at individual  sites.  However,
this lack of guidance may have  resulted in the Regions  and  States  placing
more emphasis  on the  components of  the criteria that are easiest to evaluate:
technical feasibility,  reliability,  and cost.   .Several  areas of  concern are
briefly discussed under "Outstanding Issues"  below.

-------
      Encouraging Community Involvement;  Over the  past  year, compliance with
 the community relations requirements has noticeably improved.   Every reqion
 has at least one designated Ruperfund community relations coordinator and
 community relations plans are now developed for many remedial  investinations/
 feasibility studies.  In addition, more  of  the  plans are based  on discussions
 with affected citizens and public officials.  Public coment periods are
 now routinely provided on the feasibility study.

      There are still some problems with  the proqram.   Coordination between
 technical and community relations activities  for  a  site needs  improvement.
 However,  some EPA Reqions have instituted a team  approach, reguirirta the
 community relations and technical staff  to  work closely together in  planning
 activities for the site.  Some regions lack adequate resources  to conduct
 active community relations for every site.   In  addition, some regions do not
 maintain  adequate oversiqht when a State has  the  lead  responsibility for
 community relations.

 Outstanding Issues

      There are still several outstanding issues that affect the decision-making
 process for choosinq cleanup alternatives.  Vhile EPA  has made  progress in
 resolving some of these issues,  they continue to  have  an impact on both the
 timeliness and the outcome of decision-snaking.  Some of these issues are
 discussed below.

 The  Extent of Cleanup;

      RPA  is finalizing a policy  to reouire  compliance  with "applicable or
 relevant"  environmental  and public health standards  in CEPCLA remedial
 actions unless certain specific  circumstances exist, and to document all
 analyses of  these  circumstances.   Other  regulations, advisories, and  ouidance
may  be considered  in developing  CERCIA remedies.  This policy should assist
decision-leaking on the extent  of cleanup,   necisions on the appropriate
 level  of  cleanup at remedial sites have  been  made on a site-by-site  basis.

     Capacity of RCRA Facilities;  There  is  a  concern about the  extent to
which  fully  permitted treatment, storage and  disposal  facilities will he
 available  to dispose  of  Superfund  wastes from remedial or removal actions.
 EPA's  experience over the past several years  has  shown that many of.  the
 facilities that have  interim status under the Resource Conservation
and  Recovery Act are in  violation  of  reguirements for  such facilities, and
therefore may be unacceptable  for  storage,  treatment or disposal of
Superfund wastes.

     Tn order to prevent future  problems resultina from disposal of  .Superfund
wastes, EPA  reguires  recent  inspection of disposal facilities.  In addition,
EPA  is considering a  requirement for  use of lined land disposal units for
Superfund waste arid establishing a preference for use  of treatment over
land disposal.  This may limit the number of  facilities which are immediately
available to accept Superfund waste.

-------
                                     1-30


      In addition, while there are many new and existing facilities scheduled
 for review to receive a final permit, many of these facilities are likely
 to be unable to receive final RCPA permits until the facilities take addi-
 tional action to meet regulatory reouirements.  Because of these problems,
 it is possible that there may be inadeouate treatment and disposal capacity
 under RCfA to meet Superfund needs.  The Agency is assessing this problem
 further.

      There are also serious concerns with the lonq-term impacts of continuinq
 land disposal of hazardous substances.  The Agency's ability to shift to
 treatment alternatives depends on the availability of proven treatment
 technoloqies.

      Alternative Technologies:  The rate at which the Federal and State.
 governments and private industry can develop and test more advanced
 treatment, recycling, and destruction technologies also affects available
 waste disposal capacity.   The range of technoloqies that are used most
 frequently at Superfund sites generally do not focus on advanced treatment,
 recycling or destruction.  Nbst of  the technoloqies that are used fit into
 the following general categories:

     —treatment technoloqies, such  as activated carbon units.  However,
 many of these still require destruction of highly concentrated/low volume
 wastes that result from the treatment process.  For example, expended
 activated carbon requires regeneration or the removal and further handling or
 disposal of residual substances.

     —containment technologies, such as slurry walls,  caps and barrier wells.
 The  program is gaining  experience with these technologies,  however,  there
 are tws important factors that affect their long term effectiveness.
 Most  of these reguire long  term maintenance to ensure adequate containment
 of hazardous wastes.  Also the long term effects of hazardous substances
 on the materials  used in  containment  structures are unclear and are  being
 carefully evaluated.

   —Storage technologies,  such as  covered waste piles are used generally
 as interim remedies until  a more permanent remedy can be implemented.

   —restriction  technologies,  such as incineration,  are very effective.
 However,  their application  has  been limited principally to liquids and sludges.

   —In situ stabilization, such as solidification or neutralization are
 effective.   Generally,  this treatment  is  only  applicable to certain  waste types.

 In summary,  there is still  a  qreat  need for technoloqies that will result
 in handlinq  the wastes only once, without long term operation and maintenance
 requirements,  and without the need  to  revisit  a potential threat of  release
 in the  future.  An  additional problem  related  to these long term needs
 is that CERCfA's  cost-effectiveness requirement was often interpreted as a
disincentive  for  the  use of newer, more costly treatment or destruction
 technoloqies.   However, EPA is  clarifyinq the  interpretation of cost-
effectiveness so  that alternative technoloqies may be  chosen when they
provide  additional  protection of human health  and welfare and the environment.

-------
                                     1-31
                       REMEDIAL DESIfW AND CONSTRrOTON

      After a site has been investinatert and evaluated and a method of cleanup
 has been selected, the recommended cleanup is initiated.   This  phase  is
 usually referred to as remedial desiqn and construction.

      The activities that take place during this phase are similar  in  concept
 to those that occur in any larqe desiqn and construction  project.   Detailed
 enqineering plans are developed,  site specifications  are  calculated,  and
 site-specific factors are incorporated in the planned desiqn.   Construction
 activities may include drillinq,  installation of supports and foundations,
 and earth moving.

      In most cases, the actual desiqn and construction are carried out by
 contractors.  However, EPA or the State continues to  have primary  responsi-
 bility for monitoring the activities.  For FPA lead sites, day-to-day
 supervision of site activities is handled by the Army Corps of  Engineers.
 The activity must still be defined in a State Superfund contract or a
 cooperative agreement, which  now contains the State assurances  required in
 CKRCLA section 104(c){3) for  cost sharing,  operation  and  maintenance  costs,
 and off-site treatment of hazardous substances.

      Prior to the initiation  of remedial desiqn activities, the Regional
 Superfund community relations coordinator or State  official must revise the
 community relations plan for  the  site.   This revised  plan must  account for
 the changing needs and concerns of  the  community related  to the selected
 cleanup option.

      After the contract or cooperative  agreement is final, a design contract
 is  procured.  At  federal-lead sites,  regional  staff oversee the Army  Corps
 of  Engineers,  who advertises'and  awards a contract  for desiqn.  The Corps
 ensures that all  bidders are  "responsive and responsible."  Both EPA  and
 the Corps review  the design at various  stages  of completion.  TTpon completion,
 the Corps advertises and awards a construction contract and manages its
 implementation.   This includes providing on-site Corps engineering services,
 implementing a safety plan, and ensuring that  the remedial action  is  com-
 pleted  in accordance with the plans and specifications.   Monthly progress
 reports are  submitted by the  construction contractor  to the EPA Regional
 Office  for evaluation.

     At State-lead sites,  the State either  retains  the contractor  that
 conducted the  remedial investigation  and feasibility  study, or  procures a
 new design firm.   The State's tasks are similar  to  those  of the Corps of
 Engineers  in a Federal-lead action.

      In addition  to monitoring site progress at  Federal-lead sites, EPA's
primary responsibilities are  to (1) work with  the State to obtain  access to
 the site and any  necessary local or State permits,  (2) maintain community
relations activities as specified in  the revised  community relations  plan,
 and (3)  proceed with enforcement activities  if there  is an opportunity for
cost recovery or responsible party action.   There may also be situations
where EPA works with other Federal  agencies  such as the Centers for Disease
Control or the Federal Siergency Management  Agency  during  design and  con-

-------
                                     1-3?


 struction.  In such cases,  a memorandum of understandino or  interaqency
 aqreement may he necessary to specify the scope of the project and detail
 each aqency's responsibilities.

      At State-lead sites,  the EPA Reoional office's role is  to monitor
 compliance with the cooperative  agreement.  EPA's TReqional proiect officer
 reviews all major decisons concerninq desiqn specifications.   The Regional
 proiect officer, in conjunction  with the State  project officer, addresses
 how desiqn and construction decisions affect future cooperative aqreement
 terms, and obtains necessary Regional approvals for the amendments.  At
 State-lead sites, the State aqency is responsible for  conductinq community
 relations activities as  specified in the revised community relations plan.

      EPA's current budget  estimates for a remedial planninq, desiqn and
 construction project are,  an averaqe, $SOO,000  for the PI/FS,  $440,000 for
 remedial desiqn, $7.2 million for construction, and $400,000 per year for
 operation and maintenance.   The  Fund-financed portion  of this  cost is $a.l
 million.  However,  as experience with this phase of activity increases, and
 as policies on the extent  of cleanup are clarified, it is likely that the
 estimated average cost for  construction may increase siqnificantly.

 Goals and Related Policies  of Design and Construction

      The qoal of the remedial desiqn and construction  staqe is to desiqn
 and implement a reliable and effective remedial alternative  in the most
 cost-effective manner (i.e.,  minimize cost overruns and delays).  This qoal
 has remained constant throughout the Superfund  program.  One recent program
 change  that  directly affects  desiqn  and  construction gives States the
 option of usinq the contractor that  conducted the remedial investiqation
 and feasibility study for desiqn and construction,  without additional
 procurement  .requirements.   Prior to  November 19R3,  separate procurement of
 desiqn  services was  often required.   This change is expected to expedite
 desiqn and construction  by  reducinq  the time taken to  solicit,  review, and
 negotiate a  new contract.

      Since EPA's experience implementing cleanup actions is somewhat limited,
 it  is too scon  to tell if there  are  specific problems  that cause delay during
 these phases of remedial action.  As the Aqency initiates more remedial
 cleanups,  we will evaluate  the effectiveness of our actions.   A major
 component of such an evaluation  is to determine how well the chosen tech-
 nologies  work.   This  is a lonqer-term question  which must be considered
 after the remedial measures have been in place  for some time.   In fact,
 this will be the "bottom line" in terms of  evaluating  the effectiveness of
 the program.

Major Accomplishments of Desiqn  and  Construction

     As illustrated  in Exhibit 1-fi,  by September 30, 1984, Fund-financed
 remedial  design activities  had been  initiated at 34 sites and  remedial
construction had  been initiated at 29  sites.  The  recent increase in the
number of remedial  investigations and  feasibility studies completed is
expected  to  result in a considerable  increase in the rate of sites entering

-------
                                    1-33
desiqn and construction, beqinninq in fiscal year 19RS.  In addition to
Fund-financed activities, responsible parties have initiated remedial
design and construction at 7.2 sites, as shewn in Exhibit 1-7.

     The  time required to complete plannina activities has impeded the pace
of remedial desiqn and construction; however, remedial desiqn and construction
have been facilitated by policy chanqes to speed up the planninq process.

     Accordingly, tarqets for program accomplishments have been developed
to reflect the ability of EPA and the States to desiqn and construct selected
alternatives at a more rapid rate.  Ihe increase in the number of remedial
planninq  projects undertaken since May, 19S3 will result in the initiation
of more remedial desiqn and construction projects in the near future.  By
fiscal year 1985, EPA staff expect Fund-financed remedial desiqn to be
initiated at 98 sites and Fund-financed remedial construction to be initiated
at 54 sites.

     Tn addition to Fund-financed remedial actions, responsible party
activity, resulting from EPA's enforcement mechanisms, have also siqnificantly
contributed to site cleanups.  Ttirough FYJU, responsible parties have
committed to remedial action at 22 NPL sites.  In FY«5, the Ajency anticipates
that responsible parties will commit to startinq remedial action at an
additional 17 sites.  Enforceemnt-lead activities are discussed in greater
detail in Chapter 4 of this report.

-------
                                               EXHIBIT  1-4

                         REMEDIAL INVESTIGATION/FEASIBILITY STUDY

                                               ACTIVITIES
        Action
     Memorandum
     ft Community
     Relations Plan
       Approved
 RI/F3
for site
Included
onSCAP
   Notify state & local
  agencies of expected
   prefect.  Allow  for
 80-day comment period.
RA approves
cooperative
agreement or
state letter
of request
finalized
\
Conduct RI/FS site work.
prepare RI/F3 report
-develop alternatives
-Initial screen
-detailed analysis

•;
Review of
draft RI/FS
report by
region,
state ft
HO staff
••
\
Provide 2
wk. public
comment period.
Prepare respon-
siveness
summary.
1
Prepare
decision
document
i submit to
EPA HQ
for
approval
                                Decision
                                document
                                approved
                                              Community relations
                                              activities conducted
                                              as specified In CRP
Intergovernmental
 review of F8-
 60 day comment
 period required
 CRP—Community Relations Plan
   PS—Feasibility Study
   RA—Regional Administrator
   Rl—Remedial Investigation
SCAP—Superfund Comprehensive Accomplishment Plan

-------
    500-1
NUMBER
  OF
 SITES
    400-
    300-
    800-
    100
                    EXHIBIT 1-5
              SUPERFUND PROGRAM:

REMEDIAL INVESTIGATIONS AND FEASIBILITY STUDIES
                                                           465
                                                              Total RI/FS
                                                               ERCLA-Flnanced
                                                               RI/FS Actions
                                                  Enforcement-Lead
                                                  RI/F3 Actions
                                                            26 _.--——
                                                             ^Responsible Party
                                                               RI/FS Actions
              FY 81
          FY 82

      Actual

      Projected
                                        FY 83
                                                     FY 84
FY 85
                                              Source: Office of Emergency and Remedial
                                              Response, U.S. EPA. (September 30, 1984)

-------
       40 -


       35 *~
NUMBER

 SITES  30 ^

       25 -


       20 -


       15 -


       10 -


         5 -
                                     EXHIBIT 1-6
                       SUPERFUND PROGRAM:  FUND-FINANCED
               REMEDIAL DESIGN AND REMEDIAL CONSTRUCTION ACTIVITIES
         10
                                       34 Remedial
                                       ,*  Design
                                      t
                                     / 29 Remedial
                                    '      Construction
                          16
                 FY 81
FY 82
FY 83
FY 84
                    Remedial Design Activities
                    Remedial Construction Activities
           Source: Office of Emergency and Remedial Response, U.S. EPA (September 30, 1984)

-------
 NUMBER
OF SITES

     25-n
    20-
    15H
    10-
                                EXHIBIT 1-7

             SUPERFUND PROGRAM:  RESPONSIBLE PARTY REMEDIAL
               DESIGN AND REMEDIAL CONSTRUCTION ACTIVITIES
                                                     11
                                         , Remedial Design
                                         And Remedial
                                         Construction
              FY 81
FY 82
FY 83
FY 84
        Source: Office of Emergency and Remedial Response, U.S. EPA (September 30, 1984)

-------
                         2.  REMOVAL ACTIVITIES
                                INTRODUCTION

     Removal activities constitute the emergency response portion of the
 Superfund proqram.  There are three major elements  of  the removal program.
 These are:  ensuring that the government is notified of hazardous substance
 releases; monitoring non-Pederal  cleanup efforts; and  conducting short-term
 cleanup activities.  Through its  removal activities, EPA ensures that  there  is
 appropriate response to emergencies involving hazardous substance releaises.
 EPA can also use removals to address many releases  or  potential  releases
 that pose an immediate hazard but that are not eligible for  remedial
 cleanup,  ttiree sections of CERCLA provide the statutory authority  for
 most Superfund emergency response activities:

          0  Section 102, which authorizes the EPA Administrator
             to designate hazardous substances and establish
             reportable guantities, and which sets the  reportable
             guantity for hazardous substances at one pound unless
             the Administrator has set a different reportable
             guantity or a different reportable guantity was  set  for
             the substance under CWA section 311(b)(4);

          0  Section 103,  which requires any person  in  charge of  a
             vessel or facility to notify the NRC as soon as  he or she  has
             knowledge of a release of a hazardous substance  in an amount
             eoual to or greater than the reportable guantity of  the
             substance; and

          0  Section 104,  which gives the government broad
             authority to take any response measure  (including
             removal and remedial  action)  consistent with the
             NCP that it finds necessary to protect  public health or
             welfare or the environment from a release  or threatened
             release of a  hazardous substance or a pollutant  or contaminant
             that may present an imminent and substantial danger.  Such
             measures may be taken unless  it is determined that the  owner
             or operator of the releasing facility or vessel, or  some
             other  responsible party,  will perform the  heeded response
             properly.

     Section 104 places some limits on the extent of a removal action.  A
Fund-financed  removal  may not continue  beyond 6 months  or $1 million,  unless
EPA finds  that a continued response is immediately  reguired  to prevent,
limit, or mitigate  any emergency,  an  immediate risk  to  public health or
welfare or the environment exists,  and an appropriate  response will not
otherwise be provided  on a  timely basis.

-------
                                     2-2
           NOTIFYING THE GOVERNMENT OF HAZARDOUS SUBSTANCE RELEASES

      Notification concerning hazardous  substance  releases and threatened
  releases  is the  first  step in  the Superfund emergency response process.
  Notification is  a prerequisite for  determining (1) the need for a response,
  (2)  the adequacy of any cleanup efforts, and  (3) the degree to which
  post-release monitoring may be required.

      EPA learns of releases of  hazardous substances in several different
  ways:  through notifications to the  National Response Center pursuant to
  CERCLA section 103(a); through direct  notifications to the regions;
  through government investigations conducted in accordance with CERCLA
  sections  lf)4(b)  or 104(e)  or other  statutory authorities; through notifi-
  cations frcn Federal or State  permit holders  in accordance with their
  permits;  through inventory efforts; and through incidental observations,
  reports,  and referrals from Federal and State agencies, the public, or
  other  sources.

      The National Response  Center, operated by the Coast Guard, has 2
  24-hour toll-free telephone lines to receive notifications.  Notifications
  may  be made by responsible parties, witnesses, or other parties with
  knowledge of a release or  potential release.  When the Center receives a
  call,  the duty officer asks for:

           0   The name, address, and telephone number of the
              reporting individual;

           0   The identity,  location, and nature of the release,
              including its  source, cause, guantity, and duration;

           0   The identity  of the transporter or owner of the
              facility or vessel;

           0   The nature of  iniuries and property damage, if any;

           0   A description of any corrective actions taken; and

           0   Information concerning other relevant circumstances,
              such as weather conditions.

 The duty officer enters this information on a computer terminal as it is
 received.   The officer then forwards the information to the relevant EPA
 Regional Office or OSCG district office and to the appropriate agency
 of the affected State.

   .  Individual EPA Regional Offices also receive notifications from
 responsible parties and witnesses.  In a few Regions, States forward
 release reports to the Regional Office.  Each Region has its own notifi-
 cation hotline,  originally established under section 311 of the CWA, to
' receive notifications of x>il and hazardous substance releases.  When a
 call  comes in, the on-scene coordinator or other staff person on duty
 will  record the relevant information and later transfer it to a logbook
 or, in some Regions, to a  computer file.  After hours calls are relayed
 to the on-scene coordinator on duty by a commercial answering service.

-------
                                    2-3

          a Federal on-scene coordinator receives a release report from
 anyone other than the responsible party, including reports from the NPC,
 the coordinator will attenpt to verify the notification information by
 contacting the responsible party or State or local authorities, to verify
 release information,  On the basis of the information gleaned from
 screening the notification, the on-scene coordinator determines whether
 further action is warranted, such as a search of Regional  files for
 additional relevant site information, an on-scene investigation, or
 monitoring of the situation by telephone.

 Goals and Related Policies of Notification

     The goal of notification is to alert the Federal Government to releases
 of hazardous substances that may reguire rapid response to protect public
 health and welfare and the environment.   The purpose of the CEPCIA section
 103(a) reguirement that persons in charge inform the NRC of a release  is
 to ensure that the notification is relayed to the appropriate on-scene
 coordinator and to the affected State.

     EPA policy as expressed in the NCP is consistent with  CERCLA
 notification goals.  Section 300.fi3(b)  of the NCP provides that Tilf  not
 reported previously,  a release should be promptly reported to the NRC,"
 and the section also repeats the statutory reguirements.   In  practice,
 however, EPA has placed a  low priority on enforcement of the  reguirement
 that releasers notify the  NRC.  This lack of emphasis resulted from EPA's
 pressing obligations  concerning the other elements of the  Superfund
 program, as well as EPA's  belief that even if notifications are not
 provided to the NRG,  ttaey  are generally  provided either to the States or
 to EPA,  thus ensuring an appropriate response.

     Since the start of the Superfund program, compliance with the CEPCLA
 reguirement that releasers notify the NRC has been relatively limited.
 EPA Regional  staff  estimate  that  the Center  receives  notification of only
 5-20 percent of all the releases  reguired to be reported under CERCLA.1
 The  remaining 80-95 percent  are reported either to EPA Regional Offices,
 to States,  or to local emergency  services (e.g.,  fire or police departments,
 rescue sguads,  etc.),  or are unreported.   For example,  33  States  reported
 responding to a total of more than 16,000 hazardous  substance spills over
 the  two  fiscal years  19fll  and 1982.   Although many of these state responses
may not  have  involved CERCLA hazardous substances, the National Response
 Center received fewer  than 4,000  hazardous substance  release  reports
 over the same two-year period.?

      Several  reasons  exist for the lack  of compliance with the statutory
notification  reguirement.   First, CERCLA section 103(b) penalizes  only a
 failure  to  notify "the appropriate  agency of the United States Government
 .  .  .," even  though the  National  Response Center  is discussed  in  section
     1 Source:  Interviews with EPA on-scene coordinators carried out
by EPA's Emergency Response Division during FY84.

     2 Association of State and Territorial Solid W&ste Management Officials,
State Cleanup Programs for Hazardous Substance Sites and Spills, Report to
U.S. EPA under Special Agreement X-901453, December 21, 1983.

-------
                                    2-4

 103{a).   Thus, releasers may believe  that notifying the EPA Peqion or
 Coast Guard District Office is sufficient to avoid the statutory penalty.

      Reports also frequently fail  to  reach the National Response Center
 or other Federal authorities because  the Superfund enforcement program
 has provided few incentives for compliance with CERCLA section 103(a) and
 
-------
                                    2-5

 governments  have  responded effectively to certain hazardous substance
 releases.  Generally,  all States  contact EPA Peqional Offices when
 necessary  responses  to releases are beyond their capabilities.

      Even  without explicit EPA efforts to improve compliance with
 notification requirements, reports  to the National Response Center pursuant
 to CERCLA  have steadily increased over time.  As Exhibit 2-1 shows,
 reports  to the Center  concerning  releases of CERCLA hazardous substances
 increased  by about 33  percent  from  pvfil to FY82 and by about 16 percent
 from  FM82  to FY83.   In addition,  the National Response Center received
 234?  reports concerning releases  of CEPCLA hazardous substances in FY 84,
 as conpared  with  2240  reports  during FY 83 — a 5 percent increase.4
 These increases may  be due to  a growing number of hazardous substance
 releases each year,  greater awareness of CERCLA requirements on the part
 of responsible parties and the public, or other factors.

      The number of reports being made directly to the ten EPA Regions also
 has increased  substantially over tine.  As Exhibit 2-2 shows, the Regions
 received a total  of  more than  3,000 notifications under CERCLA in fiscal
 years 1981 and 1982  and more than 5,000 notifications in FY83, including
 reports  forwarded by the National Response Center, reports forwarded by
 -States either  individually or  in monthly summaries, and some other other
 rtuplicative  reports.^   Even excluding the reports forwarded to the Regions
 by the National Response Center6 and other instances of duplication, the
 total number of CEPCLA notifications received by the Regions appears
 substantially greater  than the number of such notifications received by
 the National Response  Center.

    A major  accomplishment with respect to notification will be the
 promulgation in PY85 of a final rule adjusting the reportable quantities
 of  341 hazardous  substances under CEPCLA section 102(a).  Of the 341
 substances, approximately 50 percent will have their reportable quantities
 raised from  the levels originally established by CERCEA or under the Clean
 Wfeter Act, another nine percent will have their reportable quantities lowered,
 and the  remainder will retain  their original reportable guantities.7  These
 reportable quantity adjustments are intended to enable EPA to focus its
 resources on the inost  serious  releases and thereby to protect public health
and welfare and the environment more effectively.  Ry reducing the potential
 4 Source:  National Response Center.

 5 These totals are based on figures collected quarterly from the regions
   by the Emergency Response Division.  Differences in Regional accounting
   practices affect the accuracy of the totals.

 6 Approximately 75 percent of the CERCLA reports received by the National
   Response Center in 1983 were forwarded to the EPA Regions.  Source:
   National Response Center.

 7 Eor example, acetic acid was assigned a reportable guantity of 1000
   pounds under the Clean Water Act.  The final rule under CERCLA
   section 102(a)  will raise the reportable quantity of acetic acid
   to 50on pounds.

-------
                                    2-6

                                EXHIBIT 2-1

             NOTIFICATIONS TO THE NATIONAL PPSPONSR CKNTRP POP
                  RELEASES OF CEPCLA HAZARDOUS SUBSTANCES

                               FY81        FV82      FY83      FYP4

 Hazardous substance
 release reports               1450*      1934      2240      2342

 Percentaqe increase over       N/A        33%       Ifi*       5*
   previous year
 b  First quarter of PY81 estimated based on weighted  average of
    subsequent three months;  actual figures  unavailable.

    Source:   National Response Genter.


                                EXHIBIT 3-2

                 COMPARISON OF NPrriFICATIOFS TO EPA REGIONS
               WITH NOTIFICATIONS TO NATIONAL RESPONSE CFNTEP
                FOR RELEASES  OF CERCIA  HAZARDOUS SUBSTANCES

                                FVR1       FYR2      FVR3     FY84

 Hazardous substance release     3000       3300      5200     5000
  reports to FPA Jteqions—
  all sources3

 Hazardous substance release  •   1450b      1934      2240     2342
  reports to NRC

 Estimated hazardous substance  1910       1850      3520     3240
  release reports  to EPA
  regions from sources
  other than NRCC
a   EPA estimates based on workload projections.  Totals include CPT
    notifications forwarded to F,PA Regions by National Response Center and
    other possible duplication.  Approximately 75 percent of the CEPCLA
    reports received by the National Pesponse Center in calendar year 1Q83
    were forwarded to the EPA Pegions.

b   First guarter of FY81 estimated based on weighted average of subsequent
    three months? actual figures unavailable.

c   Rased on assumption that 75 percent of CFPCLA reports to National
    Pesponse Center forwarded to EPA Regions.

    Sources:  Emergency Response Division and National Response Center.

-------
                                    2-7
 burden of reporting snail-Quantity releases,  the adjustments may also
 increase compliance with CERCLA notification requirements.   In addition,
 the preamble to the final rule will clarify CERCLA notification provisions.
 Publication of these clarifications may increase responsible party and
 public awareness of CERCLA notification requirements  and thus increase
 compliance.
                 MONITORING NON-FEDERAL CLEANUP ACTIVITIES


      A major portion of the releases  reported  to EPA or the National
 Response Center which require cleanup are taken care of by responsible
 parties.  Most others are cleaned up  by State  or local  government  agencies.
 EPA monitors these cleanup activities to ensure that they are adequate  to
 protect public health and welfare and the environment from the dangers  of
 hazardous substance releases.  Monitoring by a Federal  on-scene  coordinator
 may be at the site or by telephone, to verify  that  responses are proceeding
 as planned and to provide technical assistance and  expertise to  the
 response team.  On-scene monitoring usually  is reserved for more complex
 responses.   Telephone monitoring tends to be used for response actions
 that an on-scene coordinator believes are well within the capacity of the
 respondinq party or agency.

      In cases where on-scene monitoring is performed, EPA Regions  provide
 a  representative (an on-scene coordinator or Technical  Assistance  Team
 member)  at the site of the release to ensure proper response by  the
 responsible party or by another agency.   If  the responsible party  fails
 to respond to a release adequately, the on-scene coordinator may seek to
 initiate a Fund-financed removal  and  will collect enforcement evidence
 for later cost recovery.  Other on-scene monitorinq functions may  include
 rapidly mobilizing and coordinating communications  and  resources among
 the various Federal,  State,  and local agencies,  providing information to
 the public,  ensuring that appropriate safety eguipment  is available, and
 checking that proper safety equipment training is provided.

     Off-scene monitoring involves providing  direction and assistance by
 telephone.   In these cases,  the on-scene coordinator has determined that
 another  agency,  such  as a state or local  response authority,  will  be present
 at  the scene or that  the releaser has formulated an appropriate  response  plan
 and has  a record of cleaning up  releases  adequately.  The coordinator makes
 follow-up telephone calls to check the progress of  response activity at a
 release  site.   Off-scene monitoring can  include  providing advice on
 cleanup  procedures,  safety precautions,  sources of  equipment,  and  similar
 specialized assistance.   The on-scene coordinator may also decide,  based
 on  information received over the  telephone,  that a  Federal representative
 is  needed at a site.

    Monitoring practices differ among the Regions.  Variations in monitoring
practices may be attributed to differences in geographic,  demographic,  and
 industrial characteristics, states' capabilities to respond,  and Regional
resources and workloads.  On-scene coordinators  within each Region  decide
on  an incident-by-incident basis whether  to monitor a particular release

-------
                                    2-8

 on-scene.  Similarly, once removal work is underway/  on-scene  coordinators
 rely on their own judgment of proper monitoring procedures.

 Goals and Related Policies of Monitoring

     The primary goal of monitoring is to ensure that  removal actions
 carried out by private parties or non-Federal authorities  adequately
 protect public health and welfare and the environment from the threats
 posed by hazardous substance  releases,   ffonitorinq  also provides other
 benefits.  Adequate cleanup by private parties and  States  preserves Fund
 resources for use at sites where  no financially capable responsible
 parties are identified.  In addition,  by providing  specialized knowledge,
 technical assistance, and training to the responsible parties  or States
 carrying out the removals, monitoring may increase  their participation in
 the  future in responding to hazardous  substance releases.

     Neither the National Contingency Plan nor the removal  guidance8 prepared
 by EPA establishes an explicit role for monitoring, and no national policies
 or guidelines exist for determining when or how to monitor.  Even without
 explicit guidance, monitoring has evolved into a major EPA activity,
 because it enables the Regions to achieve the CERCLA  goals of  protecting
 health and the environment while  relying  in large part on  private party
 resources.

 Major Accomplishments of Monitoring

      EPA estimates that the Regional Offices  conduct  on-scene  monitoring
 at approximately 300 to 500 non-Pederal removal actions each year.
 Approximately 10 to 14 percent of all hazardous substance  notifications
 to the Regions were addressed through on-scene monitoring.*'  The vast
majority of all notifications were addressed  through  off-scene monitoring.
 EPA estimates that during the first two years of the  removal program,  up
 to 20 percent of all federally-directed removals (approximately 20 out of
 103 actions during that period) may have  resulted from monitored removals
where the  on-scene coordinator declared that  the responsible parties were
 incapable  of  taking appropriate action.1°   itius, monitoring seems to be
effective  in  ensuring proper  cleanup of hazardous substance spills.
        Emergency Response Division, n.R. EPA, Superfund Removal Guidance —
        Revision *1 (December 2, 1982).

        Quarterly data on total notifications to the regions and regional
        on-scene monitoring collected from the regions by the Emergency Response
        Division.

         Estimates provided by EPA Regional on-scene coordinators.

-------
                                    2-9

     When conducting on-scene monitoring, Federal on-scene coordinators
 are able to pass  on to States,  localities, and responsible parties some
 of  their specialized knowledge  concerning proper emergency response and
 removal procedures,  in  addition  to such ad hoc forms of training, EPA
 has provided more than 200 safety and technical training courses since
 the start of the  Superfund program  in various areas of the country.
 Approximately  2,760 State and local response personnel, representing
 roughly 50  percent of  all participants, have attended these courses.  The
 courses has  included both emergency response procedures and the use of
 protective  and safety  eguipment.  Several EPA Regional Offices are also
 conducting or  sponsoring such training courses to address the needs of
 State and local first  responders.
           SHORT-TERM RESPONSES TO HAZARDOUS SUBSTANCE RELEASES
    In addition to monitoring private party or State cleanup efforts, SPA
may choose to respond to a hazardous substance release with a removal
action.  EPA may also undertake removals at hazardous waste sites identi-
fied through the site discovery and investicration process.  The steps
leading to the perfornance of a removal may include the following:

         0   Determining whether a health or environmental risk
             exists from the release;

         0   Evaluating the release to determine if it meets CERCLA
             and National Contingency Plan criteria for a removal;

         0   Recommending the release for a removal action (or
             approval of the removal action by the on-scene
             coordinator, if the coordinator has been delegated such
             authority, the release of threatened release constitutes
             an emergency and the action is expected to cost less than
             $50,000);

         0   Approving the removal by the Regional Administrator
             or, if expected to cost more than $1 million, by the
             Assistant Administrator of the Office of Solid Waste and
             Emergency Response.  For  planned removals, executing the
             appropriate contractual relationship with the state;

         0   Procuring contractors and coordinating with other
             Federal and State agencies;

         0   Preparing necessary plans, including response plans,
             site safety plans, and community relations profiles or
             plans; and

         0   Performing the removal, including monitoring of
             contractor work, and proper disposal of the removal
             material.

-------
                                    2-10

 These steps are discussed in further detail below.

      After receiving notification of a release or identifying a site  that nay
 pose an imminent hazard, the on-scene coordinator performs  an off-scene
 preliminary assessment to determine whether a response action may be
 necessary.  The preliminary assessment typically includes:   (1)  evaluation of
 the magnitude of the hazard; (2)  identification, if possible, of the  source
 and nature of the release; (3)  determination of whether any non-Pederal party
 is ready, willing, and able to undertake the necessary response;  and  (4)
 evaluation of the urgency of the  problem.   Vhen assessing releases  from
 hazardous waste management facilities, the on-scene coordinator may review
 past and present site management  practices,  photographs, and any background
 literature that may assist in the selection of appropriate  removal  activities.

      In the case of hazardous substance spills,  which  freguently reguire  some
 sort of emergency response and for which background information is  usually
 lacking, the on-scene coordinator performs an abbreviated screening of the
 notification.  The screening is ordinarily performed over the telephone to
 determine the extent of the spill,  what actions  are being taken  at  the spill,
 and whether EPA or Coast Guard assistance  is needed.

      If the preliminary assessment  or screening  indicates that the  release does
 not constitute a tline-critical emergency,  EPA conducts a more detailed
 investigation to identify the health or environmental  threats posed by the
 release.  The investigation may be performed by  an  on-scene coordinator or by
 a Technical Assistance Team member  and may include:

          0   A site survey
          0   Soil sampling
          0   W&ter sampling
          0   Drum sampling
          0   Air monitoring
          0   Visual characterization
          0   Interviews with local  residents.

     The on-scene coordinator uses  all  available  information in determining
 whether to recommend a Fund-financed removal action.   Factors used  to
 determine  whether a health or environmental  risk  exists include:  actual  or
 potential  direct human contact  with hazardous substances; contamination of
drinking water supplies or drinking water  at the  tap;  hazardous substances
 stored  in  bulk containers that  pose a serious threat to public health or  the
environment; serious  threat of  fire  or explosion; highly contaminated soils at
 or near the surface;  and weather conditions  that may cause  substances to
migrate  and pose  a serious  threat to public  health or  the environment.

     The immediacy of the threat  is evaluated to  determine  whether  an
 immediate or planned  removal  is more appropriate.   Also, the  on-scene
coordinator must  consider whether timely action by  a potentially  responsible
party is expected,  and whether  a State  or  local agency is financially and
 technically capable of  responding.   If the site  is  a candidate for  a
planned removal,  EPA initiates  coordination  with  the State  during the
evaluation process.

-------
                                    2-11

      If the on-scene coordinator determines that a Fund-financed removal  is
 necessary, the coordinator identifies and evaluates particular response
 options to mitigate the threats posed by the release.   This evaluation
 considers the reliability, effectiveness, and technical feasibility of the
 options, and their timeliness and cost.  An action memorandum describing  the
 recommended response is then submitted to the Regional  Administrator or to EPA
 headquarters, as appropriate, for approval.  For a planned removal, the State
 must also submit a request for the action and an assurance of intent to
 provide the reguired cost share.

      After an immediate removal or an EPA lead planned  removal is approved,
 the on-scene coordinator obtains  a cleanup contractor through EPA's
 Emergency Response Cleanup Services system.  The Emergency Response
 Cleanup Services system groups EPA Regions into four zones and establishes
 a single cleanup contractor in each zone through a prenegotiated contract.
 The contractor supplies cleanup services, including the control and
 disposal of released hazardous substances.  The on-scene coordinator
 signs delivery orders and supervises performance.

      The on-scene coordinator is  assisted by Technical  Assistance Team members
 and the Emergency Response Cleanup Services contractor  in determining  specific
 methods for addressing the release.   In addition,  on-scene coordinators may
 seek assistance from various  groups  established by the  National Contingency
 Plan, such as EPA's Environmental Response Team,  the National Response Team,
 or  the  Regional Response Team.  The  Environmental  Response Team is a fully
 eguipped group of technical experts  who are available to respond to releases
 that are beyond Regional capabilities.   The National Response Team and ten
 Regional Response Teams are interagency advisory and planning groups that deal
 with response issues of national  or  regional scope.  In some instances,
 on-scene coordinators will seek assistance from other Federal agencies.   For
 example,  the Centers for Disease  Control  assist with health effects analyses,
 and the Federal Emergency Management Agency aids  in temporary relocation  of
 any local  residents who must  be moved for safety reasons.

     The on-scene coordinator  works with EPA Regional public affairs staff to
 prepare a  community relations profile for a removal  action expected to last
 longer  than five days and a conrunity relations plan for a removal action
 lasting longer  than 45 days.   In  addition,  the  on-scene coordinator must
 prepare a  site  safety plan before work may begin  at a release site.  Among
 other things, this  plan sets  forth the  level of protection reguired at the
 site; delineates the site's contaminated zone,  decontamination areas,  and
 entry and  escape routes; and  identifies  key personnel.

     Once an immediate removal has been approved,  the time needed to
mobilize and  start  work  at the  scene  of  the release  varies according to
 the nature of the work reguired.   Under emergency circumstances,  partic-
 ularly  where  the  nature of the  removal activity is clear,  work may begin
within  a matter of  hours,  and several of  the above steps may be performed
simultaneously.   On  the other hand, where the specific  nature of  the
 threat  and the  steps needed to  address  the threat  are less obvious,
several days may be  reguired  to develop an  appropriate  plan of response
and  to  begin  work at the site.

-------
                                    2-12

      For planned removals, some additional administrative work must be
 completed.  The Region works with the State to execute a Superfund State
 Contract or cooperative agreement outlining EPA's and the State's
 responsibilities and the State's payment schedule for its cost-share.
 For EPA lead removals, the on-scene coordinator begins the process of
 procuring cleanup services, in most cases through the Emergency Response
 Cleanup Services System.  In a State lead action, the State must procure
 a cleanup contractor.  However, there has been only one State lead planned
 removal.

      Vfttile a removal action is underway, the on-scene coordinator is
 responsible for managing the cleanup action and coordinating the involve-
 ment of any other Federal, state, or local agencies.  When the removal is
 completed, the coordinator prepares a report summarizing actions taken at
 the release site.

 Goals and Related Policies of the Sunerfund Removal Program

      The primary goal of the Superfund removal program is to prevent,
 minimize, or mitigate acute threats to human life or health or the environ-
 ment from hazardous substance releases.  At the inception of the program,
 senior EPA management defined additional goals, including to;

          0  Provide a maximum opportunity to potentially
             responsible parties and states to assume the burden of
             performing removal actions;

          *  Ensure that all removal actions financed by the
             Hazardous Substance Response Trust Fund are absolutely
             warranted under the circumstances;

          0  Prevent infringement by removal actions on the scope
             of the remedial action program; and

          0   Maintain consistency in program implementation through
              centralized Headoruarters control of removal program
              decisions.

     Many of these goals,  and the policiesdeveloped to implement these
goals, changed significantly in 1983.   The  following discussion of five
major EPA policy  areas illustrates the broad changes that have occurred.
The policies discussed are:

          0    Criteria for obtaining approval for an inimediate
             removal action;
         0
             Creation of the category of planned removals;

             Restrictions placed on performing removals at
             sites on the National Priorities List;

             Delegation of authority outside the Office of the
             Administrator; and

-------
                                    2-13

          0   The requirement  to conduct a  contmunity relations
              program for immediate removals.

 Criteria for an Immediate Removal

     The National Contingency  Plan provides criteria for determining when
 an immediate removal is appropriate.   Section  300.65(a) states that an
 immediate removal action may  be appropriate when it will prevent or
 mitigate an immediate and significant  risk of  harm to human life or
 health or to the environment  from such situations as:  exposure to acutely
 toxic substances; contamination of a drinking  water supply; fire and/or
 explosion; or similarly acute situations.   A removal guidance document11
 developed by EPA's Emergency  Response  Division repeats these criteria and
 also emphasizes the need to evaluate the imminence and magnitude of the
 health or environmental threat  and the availability of a responsible
 party or non-Federal authority  to respond.

     During the first two years  of  the  removal  program, EPA Headquarters
 staff followed a very narrow  interpretation of the National Contingency
 Plan criteria for approval of immediate removal actions.  In particular,
 only removals that would prevent or mitigate immediate and significant
 risks of harm were considered appropriate  for  Fund financing as immediate
 removals.   Removals oriented  toward prevention of potential rather than
 presently existing threats lacked  the  marked "sense of urgency" that was
 at that time reguired for approval.

     The policy of strict interpretation of the National Contingency Plan
 criteria was modified in 1983.   The new policy did not restrict immediate
 removal actions to acute emergencies presenting major and presently
 existing threats.   Instead, immediate  removals were allowed to address
 significant threatened hazards,  i.e.,  risks that  did not necessarily
 involve  acute  emergencies.  As  the changes  discussed in the Accomplish-
ments Section illustrate, the pace of  immediate removal activity increased
markedly during the  last two  guarters  of FY83.  EPA is currently considering
 revising the National Contingency  Plan to expand  further the situations
where  removal  actions  are appropriate.

       Creation of  the  Category of Planned Pemoyals! Under CERCLA, a
removal  is any authorized Federal response action which reguires less
 than SI million and  six months  to  complete.  The  statute does
not contain the concepts of immediate and planned removals.  These
categories were created 'by the  19P2 revision of the National Contingency
Plan.  12
    11 Emergency Response Division, U.S. EPA, Superfund Removal Guidance
       Pevision »1 (December 2, 1982).

    12 47 FR 31180; see 40 CFR sections 300.65 and 300.67.

-------
                                    2-14

     In the preamble to the final NCP,  EPA stated  that  iirnrediate  removals
 were restricted to "situations of immediate and siqnificant harm to human
 life or health or the environment;  ... emergency  situations which require
 rapid immediate response."  Planned removals were for  "situations ...
 which require an expedited response, but  not an immediate one.   In these
 situations, more deliberation can be qiven to planning the
 response action.13

     One objective of distinguishing between an "immediate"  and an
 "expedited" response was  to achieve better manaqement  of the Fund.14  By
 classifyinq a release as  appropriate for  a planned rather than an immediate
 removal, EPA could use the state cost-share,  planninq,  and  cost-evaluation
 requirements of planned removals  to maintain strict control  over  potentially
 larqe Fund expenditures.

     A number of policies  were developed to implement the goals of planned
 removal  actions.  Ihese policies, which are set forth  in the Superfund
 Removal  Guidance,  require that:

          0    On-scene coordinators  analyze removal alternatives,
              including some  evaluation of costs, before proceeding
              with a planned  removal request;

          0    Planned  removal requests  undergo an extensive approval
              process in the  Regions and headguarters (this
              reguirement  was later modified by  the April 1,  1984
              redelegation of authority to the Regions); and

          0    States  share in the cost  of  carrying out  planned
              removals.  Even at privately-owned sites,  states must
             pay 10 percent  of planned removal  costs.

     CERCLA does not itself  reguire any sort  of cost-sharing for  removal
actions.  The cost-share  requirement was  imposed under the authority of
EPA's general grant  regulations and the Agency's discretionary authority
under CERCIA.l5  EPA justified cost-sharing on  a programmatic basis
because:
    13  4? PR 31193.

    14  ibid.

    15  47 FR 31186, 31193.

-------
                                    2-15

          0   Cost-sharing provides  evidence  that the  State
              considers the site in  question  a threat  and  is  comnitted
              to removal action at the site;

          0   Cost-sharing encourages an active State  role in the
              selection of releases  that require response, which is
              consistent with statutory  goalsj  and

          0   Sufficient time will generally  be available  for doing
              a planned removal to arranqe for cost-sharinq without
              causinq  a delay in response (47 FR 31193).

      I7ie recent redelegation of authority to the Reqional Administrators
 to  approve all removals up to $1  million,  ihcludinq planned  removals
 (discussed below)  will reduce somewhat  the time and effort required to
 obtain approval of planned removals.  However,  fewer  than 20 planned
 removals have been completed since  the  start of the program, and EPA is
 considerinq eliminating the oateqory of planned removals  in  the next set
 of  revisions  to the NCP.  It is likely  that  the state cost-share and the
 multiple approvals and justifications required for planned removals may
 have  discouraqed many States from applying.   The proposed revisions would
 be  designed to streamline response  procedures  while preserving the dis-
 tinction between removal and remedial response actions.

      Restricting Removals at Sites  on the NPL:  Prior  to May  19R3, EPA
 sharply  limited the extent of removal activities at inactive or abandoned
 sites that were on the National Priorities List to conserve  Fund resources
 for remedial  actions  and to avoid duplication  of effort.  Instead, EPA
 targeted sites  on  the List  for  remedial  actions, to ensure that the
 actions  would be subject to greater planning,  cost-effectiveness analysis,
 competitive bidding,  and State  cost-sharinq.  1**

    As noted  in Chapter 2 of this report, EPA's initial restrictions on
 removals at National  Priorities List sites were manifested in the most part
 detail in Chapter  2 of this  report,  not through the  number  of removals
 performed at  such  sites in 1981 and 1982, but  through the limitations
 placed on the scope of the removals that were  performed.  Most of the
 removal  activities that occurred  at National Priorities List sites were
 small-scale "stabilization"  actions  intended to reduce only  the most
 imnediate hazards  present, e.g.,  by removing obvious  fire and explosion
hazards,  pumping down overflowing evaporation  ponds or shoring up diking,
 erecting signs  and fences to keep people off the property, and other
relatively  superficial actions.   Illustrating  the effects of  the initial
policy,  EPA has undertaken 47 removal "restarts" — additional removal
action at sites where a  removal had been performed — 40 of which were at NPL
sites.
    Removal actions and initial remedial measures to address acute
    hazards at both NPL sites and non-NPL waste sites are discussed in
    further detail in Chapter 1 of this report.

-------
                                    2-16

      In May of 1983, EPA began to place much greater emphasis  on  removal
 activities at National Priorities List sites.  First, because  these sites
 represent the roost significant known threats to public health  and the
 environment from hazardous substance releases, they were qiven top
 priority for evaluation for immediate removal actions.  Second, the scope
 of stabilization activities at National Priorities List sites  was broadened
 considerably.  Instead of restricting immediate removals to the avoidance
 of imminent disasters and prevention of public access, EPA encouraged
 more extensive stabilization and surface cleanup actions,  to avoid the
 need to return to the sites time and time again and to ensure  that the
 sites would be stabilized until remedial actions could be started.

      Limited Delegation of Authority; Until January fi, 1982, all  EPA
 removal actions had to be approved by the Administrator.  On that date,
 the Administrator redelegated a small portion of this authority to the
 Assistant Administrator and the Regional Administrators.  Regional Admini-
 strators were empowered to authorize immediate removals only at the
 following:

         (1)  Releases from transportation accidents,  active or
             operating facilities,  or deliberate illegal dumps  of
             hazardous materials; or

         (2)  Inactive or abandoned  facilities or sites "when there is
             a risk of death,  injury, or catastrophic environmental
             damage from releases." *?

      The power to initiate removals at inactive or abandoned facilities
 or  sites without prior headguarters approval was to  be viewed  as  "extremely
 limited." Regional authority to commit funds without Headouarters'
 approval was in any case limited to $50,000 per incident.

      A  substantial shift in the delegation policy begain in the spring of
 1983.   In May 1983,  the Administrator delegated to the Assistant  Admini-
 strator of the Office of Solid Waste and Emergency Response the authority
 to  approve responses up to the six month and $1 million limits cited in
 CERCLA.   Shortly thereafter,  the Assistant Administrator redelegated to
 the Regional Administrators the authority to approve immediate removals
 up  to $250,000.   The purpose  of the redelegation of  authority  to  the
 Regions  was  not  only to reduce approval  times for inmediate removals, but
 to  place the authority for approving particular response actions  with the
 parties most knowledgeable  concerning the relevant facts and circumstances.

    Approximately one year after the Regional Administrators gained the
authority to approve  immediate  removals  up to $250,000, a new redelegation
 of  authority took place.   In  April. 1984,  the Administrator  signed two
delegations  that  accomplished  the  following:

          9    Regional  Administrators may approve any removal action
             up to $1 million, and may also grant  exemptions from the
              six-^nonth time limit, when  the applicable CERCLA
   Superfund Removal Guidance — Revision #1.

-------
                                    2-17

              criteria are satisfied.   In addition,  Regional
              Administrators may delegate to their Division Directors
              the authority to approve  expenditures  up  to SI million
              for projects lasting up to six months, and  may
              redelegate to on-scene coordinators  the authority to
              approve immediate removal actions up to S50,flOO  for
              classic releases from transportation accidents,  active
              facilities, or deliberate dumps,  or  imminent ha2ards at
              inactive or abandoned facilities  or  sites.

          0    The Assistant Administrator of the Office of Solid
              Waste  and B^ergency Response has  the authority to
              approve immediate removal actions that will initially or
              eventually reguire  obligation  of  more  than  $1 million.

      The April 1984,  redelegation of authority reversed  the highly
centralized approval  structure adopted during  the first  two years of the
program. It  placed the entire removal program in the  hands of the people
most  closely  connected with day  to day removal activities.  EPA. intends
to  assess the effectiveness of this delegation of response authority to
determine the extent  to which more or  less  delegation  of authority will
be  appropriate in the future.

      Community Relations Policies:  In November 1981,  EPA issued  a policy
and guidance  memorandum on  the implementation  of  a  community  relations
program  for Superfund actions.  The guidance specified that community
relations plans had to be developed for remedial  sites and for planned
removals expected to  last longer than  two weeks.

      As  EPA acguired  experience  with the removal  program, it  found that
community relations activities were also essential  at  emergency response
actions.  Citizens living near the  release  wanted information about the
release,  as well as about the effects  of the removal action.  They also
wanted to have the opportunity to  interact  with response officials.

    Therefore,  in May 1983, EPA  revised its community  relations policy to
require  that  a community relations  plan had to be submitted to Headquarters
for any  immediate removal action reguiring  Headguarters  approval.  The
September 1983 Interim Community Relations  Handbook clarified this requirement
further.  It  stated that for  any immediate  removal  action lasting longer than
five days, a  community relations profile — an abbreviated form of community
relations plan —must be prepared.  If an  action is anticipated  to last
longer than 45 days,  a community relations  plan must be  prepared.  In
addition, for planned removal  actions,  officials  must  conduct discussions with
members of the community before  preparing community relations plans and must
submit responsiveness summaries  to  EPA Headquarters when the  actions are
completed.

-------
                                    2-18
 Major Accomplishments of the Superfund Removal Program

      The CF.RCLA removal program has evolved into an active emergency  response
 and protection program.  Exhibit 2-3 summarizes all removal activity  from the
 start of the Superfund program through September 30,  1984.  In  that span of
 time, EPA completed 336 immediate removals (out of 367 started) and
 14 planned removals (out of 17 approved),  and obligated approxinnately $86
 million.  In the same period, the Coast Guard completed another 38 immediate
 removals at a cost of about SI.7 million.

      Removal costs have ranged from under  51,000 to more than $2 million. I8
 Although in the latter case an exemption from CERCLA's $1 million limitation
 on removals was necessary,  EPA granted only three exemptions from this limit
 in each of the first three  years of the program,  as Exhibit 3-5 shows.  Nine
 exemptions from the $1 million limit were  granted in FY84.  EPA has
 granted a greater number of exemptions from the 6 month time limitation:
 18 in FY81, 4 in FY82, 13 in FY83,  and 20  in FY84.   For purposes of the $1
 million and six month limitations,  EPA treats the money and time spent at
 a particular site cumulatively, aggregating the initial removal action
 with any restarts that are  subseguently approved  for  the same site.19

     Because 35 removal actions  in fiscal years 1981-83 lasted longer  than six
 months, the average duration of a removal  was skewed  upwards; the average
 duration has been about 23  days,  while the median duration  has been only
 14 days.20

      The policy changes in  the  spring of 1983 substantially affected  the level
 of Superfund removal  activity.   For example,  from December  1980 to February
 1983,  EPA conducted 119 removal actions.   From March  1983 through September
 1983,  however,  102 additional removals were conducted,  almost matching in
 those six months the  total  removal  activity of the  previous two years. 21
 Removal actions during FY 84  increased more than  60 percent over the  FY
 83 level.
18  Emergency Response Division, "Superfund Removal Actions December 11,
    19PO-September 30, 1983 — A Presentation to the National Response Team,"
    January 5, 1984, p. 10.

19  Interview with Emergency Response Division staff, July 10, 1984.

20  Emergency Response Division, "Superfund Removal Actions December 11,
    1980-September 30, 1983 — A Presentation to the National Response Team,"
    January 5, 1984, p. 11.

21  Statement of Lee M. Thomas before the Senate Committee on Environment
    and Public Works, April 25, 1984.

-------
                                    2-19
                               EXHIBIT 2-3
               SUMMARY OF CERCLA REMOVAL ACTIVITV
                              12/11/RO-9/30/R4
 ACTIVITIFS
 EPA
     Immediate Removals
        Non-NPL
        NPL
              TOTAL

     Planned Removals
        Non-NPL
        NPL
              TOTAL
USCG
        Nbn-NPL
        NPL
             TOTAL
                              Actions
                              Started
Actions
Completed
Percentage
of. Funded
Actions
Completed
22R
139
367^
14
3
17
37
1
38
204
132
336
11
3
14
37
1
3*
89
&
92
79
M
R?
100
ion
100
TOTAL
   38RC
FUNDING
    Estimated Obliqations as of 9/30/84 (in thousands of dollars)
        EPA
        — Immediate Removals                      S79,fi44.7
        — Planned Removals            •              6,210.6
        liSOG                                         1,698.6
             TOTAL                                 $87,753.9
a  Includes 22 CERCLA removals initially funded under Clean Water Act
   section 311 during period monies from CFRCLA Fund were not yet available.

k  includes 32 removal actions in West Pacific Trust Territories, 40
   restarts at National Priorities List (NPL) sites, and 7 restarts at
   non-NPL sites.

c  includes 37 restarts at NPL sites and 5 restarts at non-NPL sites.

    Source:  Removal Tracking System, Emergency Response Division.

-------
                                    2-20


                                EXHIBIT 2-4

                 APPROVED EXEMPTIONS PROM STATUTORY LIMITS

                            FY81      FY82      FY83     FY84     Total
                                                   (throuqh
                                                    8/15/R4)

 SI  Million  Exeirption         33        3        9      18

 Six Month Exemption         18       4       13       20      55
 Sources:  Emergency Response Division
     Exhibits 2-5, 2-6, 2-1, and 2-8 illustrate the rapid growth of the
removal program.  Exhibit 2-6 indicates that the number of removals
initiated each year rose 58 percent from FY81 to FY82 (36 to 57) and
again by 119 percent from FY82 to FY83 (57 to 125). 22  in FY84, EPA and the
Coast Guard together initiated 204 removals, a 63 percent increase over the
previous year.

     The redelegations of authority to approve removals substantially reduced
the time needed to process immediate removal requests.  Prior to February 8,
1983, 50 percent of all immediate removal requests were processed in eight
days or less and 90 percent of the requests were processed in 19 days or
less.23  Between February 8, 1QR3 and June 30, 1983, fin percent of all
immediate removal requests were processed within one day, including requests
which Regional &3ministrators decided; EPA Headquarters processed 50 percent
of the immediate removal reguests submitted to it in four days or less; and 90
percent of all requests were processed in nine days or less. 24  rxaring this
latter time period, 58 percent of all removal decision were made at the
22  These figures include (a) 47 restarts and (b) 22 CERCLA removals
    funded under Clean Water Act section 311 during the period the CERCLA Fund was
    unavailable.

23  Headquarters Technical Assistance Team, Analysis of ERD Removal
    Recyuest Processing, Phase II, February 8-June 30, 1983 (TDD No. 138302-01-A),
    pp. 2 and 7.
24  ibid.

-------
                                    2-21
 Regional level.  Between July 1,  1983  and September  30,  1983, overall
 processing times decreased even further,  as 70 percent of all immediate
 removal requests were processed within one day. 25   -phe  Regional
 Administrators decided 81 percent of these cases.

      Planned removals were not included in the 1983  redelegation of approval
 authority to the Regions.  Because of  the additional documentation and
 approvals required for planned removal requests, processing time remained
 lengthy.   In FY82, three of the 10 planned removal requests were processed
 within four working days.  Five of the 10, however,  required 22 or more days
 to process, and three of these required more than 50 days to process. 26
 During the first three quarters of FY83,  five of the six planned removal
 requests  submitted required more  than  25  working days to process. 2?

      An additional institutional  change in 1984 was  EPA's adoption of the
 Emergency Response Cleanup Services program, initiated February 1, 1984.  This
 program replaced a lengthy and cumbersome procurement procedure that relied on
 case-by-case negotiation of services,  hours, material, and costs and that
 frequently precluded competitive  bidding  in emergency situations.  Under the
 Emergency Response Cleanup Services system, the on-scene coordinator need only
 prepare a Delivery Order to obtain guaranteed cleanup services for a
 particular site at a prenegotiated and competitive price.  Response time
 limits in the contract vary from  1.5 hours, for incidents within a 50-mile
 radius of New York City, to 24 hours,  for incidents  in the State of
 Alaska. 28  The on-scene coordinator may  still resort to the old procurement
 system when the Emergency Response Cleanup Services  contractor cannot respond
 in a  timely fashion,  when a conflict of interest may exist, or when a unique
 situation warrants another contractor.

      In the area of community  relations,  no formal tracking system exists that
 allows EPA Headquarters to determine whether the Regions are complying with
 current ccranunity relations policies for  immediate and planned removals.
 Vfaile there has  been  increased emphasis on strengthening the community
 relations program for removals, it appears that compliance with program
 requirements is  still  sporadic.  Only  4 out of the 10 Regions, for example,
 have  consistently prepared community relations profiles.  However, continuing
 emphasis  on community  relations is likely to increase community involvement in
 removal activities.
25  Headquarters Technical Assistance Team, Analysis of ERD Removal
    Request Processing, Phase III, July 1-September 30, 1983 (TDD No. 138302-11)

26  Headquarters Technical Assistance Team, Analysis of ERD Removal
    Request Processing and Program Guidance (TDD No. 138302-1), March 25, 1983.

27  Ibid; Headquarters Technical Assistance Team, Analysis of ERD
    Removal Request Procession, Phase II, Februrary 8 - June 30, 1983 (TDD No.
    138302-01-A) , p. 4.f

2^  Emergency Response Division.

-------
                                    2-22
      In sum, immediate removals appear to constitute a successful and rapidly
 expanding element of the Superfund emergency response proqram.   Planned
 removals, on the other hand, because so few have been performed, have not
 achieved to any significant extent the qoal of providing an expedited response
 in situations where a removal (as opposed to a remedial) action is necessary.
 EPA is considering revising the National Contingency Plan to eliminate the
 category of planned removals.  Similar institutional adjustments are being
 made on a continuing basis to improve the effectiveness of removals in meeting
 CERCLA goals.

                                       2-S
       SriPERFTTKTn REMOVALS INITIATED BY FISCAL YEARS a/
       FPA
           Immediate

               Non-NPL
                   MPL

           Total Immediate

           Planned

               Non-NPL
                   NPL

           Total Planned

           Total EPA

      USCG

               Non-NPL
                   KFPL

           TOTAL USCG

      TOTAL
                                     FY81
 q b/
27 C/
          FY82
        FY83
          FY84  Total
36
18
28

46
           9
           1
          10

          57
 63
 47

110
       10


       10

      125
138
 37
        18


        IB

       204
228
139

367
1
1
47
4
1
5
115
10
1
11
186
14
3
17
384
        37
         1

        38

       42?
a   Where applicable, figures  include approved restarts of  removal  activity
    at existing sites.

b   Includes 3 removals funded under Clean Water Act  section  311.

c   Includes 19 removals funded under Clean Water Act section 311.

^   Includes total of 47 restarts.

-------
                               EXHIBIT 2-6
           SUPERFUND REMOVALS STARTED BY FISCAL YEAR
NUMBER OF
 STARTS

       200

       180 -

       180 -

       140

       120

       100 -

       80 -

       60 -

       40

       20 H

        0
                                           (204)
                             (129)
               (57)
(38)
              1981
               1982
1983
1984
                                 FISCAL YEAR
   _§_/ These Totals Include 47 Approved Restarts And 38 Coast Guard Removals.
      The FYS1 Total Also Includes 22 Removals Initially Funded By The CWA Section
      311 Program Because The CERCLA Fund Had Not Yet Accumulated Sufficient Monies.
    Source:  Emergency Response Division, U.S. EPA (September 30, 1984)

-------
                                   2-23


                              EXHIBIT 2-7

             SUPERFUND REMOVAL OBLIGATIONS BY FISCAL YEAR
                      (Contract OOTmitments) ($00ns)


                              FY81        FYR2       FY83       FY84  a/    Ttotal
      EPA
          Inrediate          9922.6    11,924.3   20,804.9    37,192.9   79,R44.7
          Planned              —          74.8    3,174.0     2,961.8    6,210.6

      USCG

          Dnmediate              -        637.3     270.3     791.0     1,698.6

      TOTAL                 9,922.6    12,636.4  24,249.2  40,9*5.7    87,753.9
Sources: U.S. EPA Financial Management System

-------
                      EXHIBIT 2-8
     SUPERFUND REMOVAL OBLIGATIONS BY FISCAL YEAR
MILLIONS
   OF
DOLLARS
     42-t
     40-
     38-
     36-
     34-
     32-
     30-
     28-
     26-
     24-
     22 -
     20 -
     18 -
     16 -
     14 -
     12 -
     10-
     8 -
     6 -
     4 -
     2 -
     0 -
                                       (40.9)
                          (24.2)
            (12.6)
(9.9)
          1981
             1982          1983
                FISCAL YEAR
1984
       Source:  U.S. EPA Financial Management System.

-------
                                                                        RXHMMT 1-fi

                                                                      CLEANflP ACTIONS APPROVED
      Site Name

AfcF Materials, TL
Berlin and Farro, Ml
Bruin Laooon,  PA
Burnt Fly Boa, NJ
Celtor Chemical Works,
CA
   Problem at the Site

Rite contains contaminated
linuid wastes, oil-, sludne, awl
soil, as well as drums of un-
known contents.  Contamination
is movina toward river used for
drinkinn water.

Rite consists of ? contaminated
laooons, a landfill with hurled
drums, a paint sludoe trench,
and numerous pockets of liquids,
slurtnes, and solvents.

Contamination of surface water
and arounduater threatened hy
leachinci from open lagoon con-
tainina asphaltic slurtoe and
acidic linuid supernatant.  Site
also contains effluent overflow
pond, covered lanoon sludne
nixed with soil, and contaminated
soils.

Rite consists of * lancons con-
tain inn contaminated shrine,
drummed materials, a tar patch,
and an asphalt pile with oroanic
pollutants.
nrininally operated as sulf ide
ore procession plant, site con-
tains exposed ore piles, open
ore bins, contaminated soils,
and partially filled extraction
vats.  Heavy metals such as cad-
mium, zinc, and copper found
at site.
                                  r»ate of
                                  Cleanup
                                  Decision

                                  11/23/R3
                                   Ofi/ft?/"?
         Previous
     Cleanup Actions

Immediate removal conducted to
lower waste levels; install dike
and trench; remove wastes; and
install temporary cap over por-
tions of site.
                                               Various state and EPA-funrted
                                               actions undertaken to remove
                                               sludne  in  lanoon; fence the
                                               site; and excavate drums.
None
                                   11/1S/R3
Rite has been fenced and a sec-
tion of dike has been repaired
to prevent lanoon spillape.
                                                None
Cleanup Action Approved

Initial remedial measure approved
involves removal and off-site
disposal of contaminated wastes
and oils and removal of drums
(RPA lead).
Remedial action approved involves
excavation of drums in landfill,
construction trench; off-site
disposal of wastesl and incineration
of PCBs (state lead).

Remedial action approved involves
removal and off-site disposal of
supernatant; physical stabilization
of lanoonj cleanup of effluent
pondl diversion of oroundwater;
and stabilization of lanoon dike
(EPA lead).
Two phases to remedial cleanup
(RPA lead):
1.  Demoval and off-site disposal
    of some contaminated materials.
2.  Removal and off-site disposal
    of remainina hazardous materials
    and  restoration and revenatatlon
    of the area.
    nroundwater monitorinn  included
    in a second phase.

Initial  remedial measure approved
for the  site involves removal and
off-site disposal of contaminated
materials  (RPA lead.)
Costs of
Approved
 Action

sill,nno
                                                                                                                         S9 million
                                                                                                                          S1.S million
                                                                                                                                                     Phase  I-S2.3
                                                                                                                                                         million
                                                                                                                                                     Phase  ?-SS.1
                                                                                                                                                         million
                                                                                                                                                     S340,000

-------
                                                                           I-H (
cleanup site.  Rxact nature of
previous actions not specified.
                      Both wells taken out of service.
                      iisino CFRCLA enenjency funds,
                      RPA repaired damaged drws and
                      started approximately «,nrm other
                      drums.  EPA subsequently re-
                      moved and disposed off-site sere
                      of the hazardous materials.

                      Fence installed and eciuipoent
                      and debris were reroved fron>
                      site.
None
Cleanup Action Approved

Initial rwedial measure approved
ho extend a nearby water sunply
svsten to affected residents.
Initial remedial n«asur« approved
to remve and dispose of qas cy-
linders of unknown contents, to
clean and reconstruct storm sewer
systen, and deoontar'i rwte th
the site and re-oval vehicles on the
site (RPA lead).

Interim twnedial cleanup approved
to remove contanination of one
well through aeration. Further
work is underway to determine
source of contamination (RPA lead).

Interim remedial cleanup involves
off-site disposal of  the liouid,
slutVie, liner,  and contaminated
soil frow  larjoon  (state Inad).
 Remedial cleanup approved for the
 site involves removal and off-
 site disposal  of soil with PCR
 concentrations over 10 pr».  Addi-
 tional excavation will he under-
 taken where cost-effective (P.PA
 lead).

 Remedial cleanup approved involves
 constructing a wall around Ifi
                                        Costs of,
                                        Approved
                                         Action
                                                                                                                                                                  million
                                                                            sson,nnn
                                                                               .d milli
                                                                                                                                                                 Rl.« milli

-------
                                                                  RXHIRIT 1-B (continued)

                                                             REMEDIAL CLEANUP ACTIONS APPROVED
      Site Name

Matthews Electroplating,
McColl Site,  CA
Mcf in Company, MR
 Milltovm Reservoir
 Sediments, MT
 Hinker, Stout, Cashel,
 Pull ins, ouail Run,  and
 Sontaq Road Sites, MD
 New Briqhton/Arden
 Hills,  MN
  New Briqhton/Arden
  Hills, MN
   Problem at the Site

nroundwater is contaminated with
chromium from electroplatinq
operations at the site,  Oround-
water is used for drinkinq
water.

Site used for disposal of acid
sludqe wastes and drilllnq muds.
Soil is hiohly acidic, with hiqh
sulfur and orqanic content.

site is located  in abandoned
sand and nravel  pit and contains
tanks and a  laaoon containina
various oil and  liquid chemical
wastes and volatile omanics.
Potential contamination of
qroundwater.

nroundwater  is contaminated with
arsenic and  other heavy metals
 affectinq drinkina water for
area.

 Soil at six residential sites
 contaminated with dioxin.
 PIune of contaninated qround-
 water, spread over approximately
 18 square miles, has affected
 drinkinq water supplies of
 48,100 residents.

  (See above)
Date of
Cleanup
Decision

06/0?/R3
                                                              04/U/fl4
                                                              tn/15/«3
                                                                                   Previous
                                                                               Cleanup Actions
None
                                                                           None
             State  supervised  removal of oil
             and  liquid chemical wastes.
                                                              04/14/R4    None
 1984        Permanent relocation offered to
            11 families in Minker/F.tout area,
            temporary relocation offers made
            to 7. other families in Minker/
            Stout area and 100 residents of
            Ouail Run area.

 06/24/P3   Several municipal and private
            wells have been closed.
                                                               09/19/R3   (See above)
Cleanup Action Approved

Ceroedial action approved to extend
nearby nuninipal water supply to
residents affected by qroundwater
contamination (EPA lead)

Approved cleanup action includes
excavation and off-site disposal
of wastes with monitorinq and
control of emissions (state lead).

Initial remedial measures approved
for site consists of off-site
disposal of liquids and studqes,
on-site cleaninq of tanks,  and
Off-site transport of enoty tanks
(state lead).
                                       Remedial action approved involves
                                       replacinq existinq water supply
                                       and distribution system and flush-
                                       ino each house's pipe system
                                       (state lead).

                                       Remedial cleanup of sites includes
                                       excavation of contaminated soil
                                       and transport of the soil to an
                                       interim storage facility (a con-
                                       crete vault with a flexible cover)
                                       at Times Beach, MO  (FPA lead)

                                       Initial rwiedial measure approved
                                       to treat the municiple water
                                       supply for city of New Rriqhton
                                       (RPA lead).
                                                    Additional inital remedial mea-
                                                    sure approved to extend a nearby
                                                    water supply to fi residents
                                                    (state lead)
                                                                                                                               Cbsts of
                                                                                                                               Approved
                                                                                                                               _Action
                                                                                                                                                          million
                                                                                                                                                        S<«7,onn
                                       sis.7
                                        million
                                                                                                                                                        siRn,nnn

-------
                                                                          l-« (continued)
                                                             REWEP.1AL CLEANUP ACTIONS APPROVED
      Site name

Xjthoard Marine Cor-
x>ration, IL
"rice Landfill, NJ
Re-Solve, Inc., MA
Ran Gabriel Area 1,  CA
Stringfellow Acid Pits,
CA
   Problem at the Site

Rite consists of VbuKenan Harbor
and adiacent property of the
Outboard Marine Corporation and
is contaminated with PCRs.
Oroundwater contamination has
resulted from leachina from land-
fill.  Contamination has affected
local drinkino water wells and
threatens water supply for
Atlantic City.
Surface water and nroundwater
are contaminated with PCFte,
volatile oroanics, and heavy
metals as a  result of operations
at former solvent reclamation
facility.  Site contains A
unlined lagoons, oil spreading
area, and coolino pond filled
with sand and contaminated soil.

Plume of ciroundwater contaminated
with chlorinated hydrocarbons
(including PCB and TCE) has
affected an  area 4 miles lonn and
1-1/2 miles  wide.

As a result  of dumpinq of  toxic
wastes, surface water is con-
taminated and drinkina water
supply is threatened.
Date of
Cleanup
Decision

05/15/ft4
n<»/20/R3
         Previous
     Cleanup Actions
None
Local residents have been re-
quired to use bottled water.  EPA
and the state of Hi have imple-
mented several measures at a
nearby water treatment plant in
the event the plume reaches the
wellfield for Atlantic City.

None
 OS/11/M
                                                                           None
              Intensive  remedial cleanup
              actions have been conducted.
Cleanup Action Approved

Remedial cleanup approved for the
site includes extensive dredging,
excavation, dewatering, fixation,
off-site disposal, and cappinn
operations (EPA lead).

Remedial action approved involves
relocatinn the Atlantic City well-
field and conducting treatment
studies to manage contaminated
plume (state lead).

Approved cleanup action involves
excavation and off-site disposal
of approximately 7,000 eobic yards
of contaminated wastes and soils
(EPA lead).
                                           Initial remedial measure approved
                                           for the site involves treatino
                                           well discharge with an air-
                                           stripping system to lower PCE
                                           contaminlation (F.PA lead).

                                           Initital remedial'measure approved
                                           for the site will augment remedial
                                           actionns currently underway.
                                           Approved actions include fencinn
                                           and erosion control, off-site
                                           disposal and various interim
                                           actions to mitigate contaminated
                                           groundwater.
Cost of
Approved
 Action
                                                                                              million
                                                                                                                                                          S24.7
                                                                                                                                                            million
                                                                                                                                 3.a million
                                         speci-
                                     fied

-------
                                                                   FXHIBIT 1-ft (continued)

                                                                       CLFANIIP ACTIONS APPROVED
      Site  Name

Sylvester,  NH
Sylvester,
Taputimu  Farm,  American
Samoa
   Problem at the Site

Illenal dinning of toxic wastes
has resulted in contamination
qroundwater that potentially
threatens to contaminate drinkina
water supply.
(See above)
Date of.
Cleanun
necision

07/29/82
                                                              09/27/K3
         Previous
     Cleanup Actions

Under Clean Water Act section
311, drums were removed and dis-
posed of off-site.  CRPCIA emer-
tjencv funds used to install
qroundwater inception and recir-
culation system to retard miqra-
tion.

(see above)
Site used Cor storage of aciri-
cultural chemicals and pesti-
cides.  Approximately 4,nnn
pounds of. liouid and solid chemi-
cals are stored in a warehouse
and are affectino warehouse
workers.
1V27/P3
Mone
 Cleanup Action Approved

Penedial cleanup action approved
involves installation of a
wall and surface cap of site
(state lead).
Costs of
Approved
 Action

 Not spec-
   fied
Further remedial actions approved   S4.7 mi Dion
for the site involves construc-
tion of water treabnent plant to
extract and treat contaminated
arounowater (state lead).

Remedial actions approved for the   $lfiO,non
site  involve decontaminating the
warehouse and transportinq the
decontaminated  and stored wastes
to the CI.S. mainland  (EPA lead).

-------
                                    3-1


                     3. CHARACTERIZING REMOVAL ACTIONS


                                INTRODUCTION
      This chapter provides additional information concerninq the threats
 found and response  actions taken at release incidents and sites addressed
 by  the removal program.  The discussion delineates the diverse situations
 faced by the  removal program and the wide range of options available for
 responding to actual and potential hazardous substance releases.  The
 chapter also  presents  three case studies that illustrate how EPA makes
 decisions and how various removal activities are typically carried out.
                    REVIEW OF PAST REMOVAL ACTIVITIES
     EPA recently undertook a study of removal actions approved between
October 1, 1983 and May 16, 1984, to characterize the actions and assess
consistency in the removal program. 1 During that time period, a total of
142 removals were approved, with 129 approved by EPA and the rest by the
Coast Guard.  When the study was initiated, CERCLA-funded on-site work
had begun at 105 of the EPA approved projects, and private party response
negotiations or actions were under way at 13 of the remaining 24 sites.
In general, these 129 removal actions are representative of the type of
removal actions EPA is likely to undertake.  However, due to the major
policy changes in the spring of 1983, these actions may not represent
removals occurring in fiscal years 19R1 and 1982.

     The threats that these removal actions responded to were divided
into two major categories, health and environment.  Health threats include
direct contact, fire and/or explosion, drinking water contamination, food
chain contamination, and air contamination/inhalation.  Environmental
threats include surface water contamination, ground water contamination,
soil contamination, and ecological damage.  The threats from the
129 sites were as follows:

    0 Health threats were present at 87 percent of the sites.

    0 Environmental threats occured at 83 percent of the sites

    0 Combined health and environmental threats were present at
      76 percent of the sites.

    0 Environmental threats alone occured at eight percent of
      the sites
   Booze, Allen and Hamilton, "Consistency of Regional Removal Decisions",
   Final Report, August 30, 1984.

-------
                                    3-2
     *  The most frequently occurino health threat was direct
       contact at approximately  79 percent of all sites.
       other threats occured  far less often, from food chain
       contamination at fewer than one percent of the sites to
       drinking water contamination at 21 percent of the
       sites.

     0  The most frequently occurinq environmental threat was soil
       contamination at 43 percent of the sites; surface water
       and qround water contamination were present at 27 and 23
       percent of the sites respectively.

     As  presented in Exhibit 3-1 removals were taken in response to a
variety  of  different incidents or problems.  However, more than 60 percent
of  the incidents involved abandoned cotainers or abandoned waste facilities.
More than 127 different types of hazardous substances were found at the
sites.  The 13 most commonly found substances or classes of substances
are presented in Exhibit  3-2.

     A number of different types of activities may be undertaken in the
course of a  removal action.  Exhibit 3-3 presents 13 categories of actions
and examples of  each.   At any given site, the combination of response
activities may result  in  a stabilization or cleanup of the site.  The
most commonly occurinq types of response actions were removaKe.q.,
removing soil or other contaminated materials from the site), disposal,
and source control, and most incidents required some combination of these
activities.   Ihe decision on the type of activities to undertake may be
influenced by such factors as the type of site (non-NPL vs NPL sites,
where  there  is the potential for more extensive cleanup later); the
type of  incident;  the  substances released; and the extent of the threat.

     The scope of response at a site may range from limiting access by
fencing or temporary relocation to substantial cleanup through removal
and off-site disposal of  some or all of the contaminants.  Approximately
two-thirds of the completed  removal actions were cleanups, i.e., mitigation
of  the threat to the extent  that, barring unforseen circumstances, EPA
has no plans  to  treat  the site again.  The rest of the completed sites
were characterized as  "stabilizations", alleviating exposure sufficiently
to  allow for more orderly planning for further action.  However, all the
actions at NPL sites were stabilizations, and 90 percent of the completed
actions at non-NfPL sites  were cleanups.  The length of time it took to
complete these actions ranged from one day to 69 days, with an average
length of 27 days.

-------
                                   3-3
                               RXHIBIT 3-1
                        National Incident Profile
                            Approved Removals
                            10/1/P3 - 5/16/84
All Removals
Incident Type
Abandoned Container
Abandoned Waste Site
Active Facility
Contaminated Fill
Fire
Former Facility
Radiation
Transportation
Uncontrolled Release
Well Contamination
National
SumjT\ary
No.
23
64
6
7.
3
• 20
3
2
12
7
142
%
16.2%
45.1
04.2
01.4
02.1
14.1
02.1
01.4
08.4
04.9
99.9%
EPA Removals
. No
1R
64
6.
7
3
IP
3
1
7
7
129
%
13.9%
49.6
4.6
1.6
2.3
13.9
2.3
O.R
5.4
5.4
99. «%
* Error due to rounding
                                  111-8

-------
                                   3-4
                               EXHIBIT 3-2
                             National Profile
                        of Most Common Substances
Substance                 Number of             Percent of
                          Approvals*          Ttotal Removals
PCBs                        30                     33.?
Pesticides/DDT              18                     13.9
Heavy Metals**              18                     13.9
Orqanics                    12                     9.3
Toluene                     11                     8.5
Cyanide                     9                      6.9
Benzene                     7                      5.4
Paints                      7                      5.4
Caustic Solda               6                      4.7
Acids                       5                      4.7
Ethylbenzene                5                      3.9
Trichloroethylene           5                      3.9
Xylene                      5                      3.9
NA                          8                      6.2%
*  Wumbers are non-additive since more than one substance may be found
   at a removal.

** Includes lead (7) and chronium{6}
                                  III-9

-------
                                   3-5

                                EXHIBIT  3-3
                        Removal Action  Categories
 1.    Site Security


 2.    Source Control



 3.    Sampling

 4.    Migration Control

 5.    Relocation

 6.    Measuring



 7.    Water Supply



 8.    Damage Control

 9.    Excavation

 10.   Removal



 11.  Salvage Operations

 12.  Disposal
 Installed fence, maintained security guard,
 secured buildings

 Overpacked drums, pumped down overflowing lagoon
 staged drums, capped landfill, fought fire,
 controlled release, solidified materials

 Sampled containers, soil, air, water, etc.

 Installed sorbent booms, dug ditches

 Evacuated on temporary or permanent basis

 Conducted environmental,-assessment, conducted,
 ground water supply, conducted magnoneter study,
 installed monitoring wells

 Provided temporary supply, provided permanent
 supply, provided bottles,  provided tanks,
 installed hook ups, installed pipline

 Stabilized stream

 Dug pits

.Decontaminated buildings,  removed soil,  aqueous,
 material, sludge, containers, contaminated
 debris

 Recycled wastes/materials

 Landfilled wastes, incinerated wastes, transported
 wastes for disposal
13.  Site Restoration
Graded,  seeded,  restored,  applied hay

-------
                                    3-6

                        REMOVAL ACTION CASE STUDIES
      This section presents three examples of removal  actions  taken pursuant
 to section 104 of CERCIA.   All three site actions were  taken  under EPA's
 immediate removal program and were conducted during fiscal year  1983.
 These specific examples were chosen because  they differ significantly
 with respect to the nature and immediacy of  the  threat  existing  at the
 site as well as the scope  of action taken to abate  or minimize the site
 hazard.

      The first removal example (Western Processing) was conducted at a site
 listed on the NPL targeted for future remedial action.  This  example
 illustrates that a removal action to stabilize an immediate threat may be
 conducted concurrently with remedial activities.  It  also illustrates
 conditions and manner in which a removal action may be  conducted at an
 NPL site.

      The second removal example (Brown's Field) was conducted at a non-NPL
 abandoned hazardous waste  site.  This example illustrates that a removal
 action may be conducted at a site which poses a significant threat to
 public health and the environment, but which does not score high enough
 on EPA's hazardous ranking system to be listed on the NPL for remedial
 action.

      The third removal example (Hampton Cylinder) was also conducted at a
 non-WPL site.   Similar to  Brown's Field,  this example illustrates that a
 removal action may be conducted at a non-NPL site which poses a  significant
 threat to public health and the environment.  This situation, however,
 differs from Brown's Field with respect to the immediacy of the  threat
 and the response action taken  to abate that  threat.
                    WESTERN PROCESSING SITE  (NPL Site)

Site Background

     This site is a 13 acre chemical recycling and reclamation facility in
Kent, Washington owned by the Western Processing Company.  It received
and stored chemical and industrial wastes from 1961 to 1983.  The area
surrounding the site is predominately commercial, light industrial,
agricultural, and residential.  Two residences and a number of commercial
and industrial buildings are located within one-half mile of the site.
Adjacent to the site is a frequently used bicycle and jogging path.  A
stream known as Mill Creek flows along the western boundary of the site,
eventually entering the Duwamish River and Puget Sound.

     This site contained approximately 4000 to 6000 drums, 70 bulk storage
tanks, several piles of unconfined chemical and industrial wastes, 10
surface impoundments, 5 PCB transformers, and various other structures
containing a variety of hazardous substances.  These substances included
acids, caustics, wastes containing cyanide, heavy metals, ignitables, oils,
PCBs, and other hazardous substances.  The site contained a total of
eighty-seven priority pollutants, including forty-eight known or suspected
carcinogens.

-------
                                    3-7
 NPL Listing and Remedial Planning Activities

      Western Processinq had interim status to store hazardous wastes
 under the Resource Conservation and Recovery Act (RCRA).   In March of
 19R1, EPA discovered that the operator was in violation of various RCRA
 hazardous waste management regulations.  In early 19&2, a Compliance
 Order was issued requiring the operator to undertake various actions to
 meet existing regulations.  The operator failed  to comply with this
 order.  In July of 1982 the site was listed on EPA's National Priorities
 List (NPL) for CERCLA remedial action.   In July  of 19P3 EPA ordered the
 operator of this facility to cease operations.

      Tb date, a variety of remedial response activities and an immediate
 removal action have been conducted at this site.   Remedial response
 activities include the completion of a  remedial  action master plan as
 well as the initiation of the remedial  investigation and  feasibility
 study.  This remedial project is expected to be  completed by the end of
 fiscal year 1986.   Because the site posed an immediate threat to public
 health and the environment,  EPA determined that  an immediate removal
 action should be conducted concurrent with on-going remedial activities.

      On April 11,  19R3,  EPA issued an administrative order under section
 106 of CERCLA requiring the site operator to undertake specific actions
 necessary to eliminate the immediate hazards at  the site.   After the
 site operator indicated an inability to take action,  EPA  authorized an
 immediate removal  on April 15,  19R3.  The general  goal of the removal was
 to  stabilize the hazardous nature of the site, and to mitigate the immediate
 threat to public health  and  the environment.

 Nature of Immediate  Threat

      EPA determined  that the site posed an imminent and substantial
 threat to human health and the  environment.   The nature of the threat was
 direct contact of  hazardous  substances  to humans,  a fire  and explosion
 hazard, as well as both  on and  off-site  contamination of  soil,  surface
 and  ground water.  These threats existed due to  the following site
 conditions.

      First,  containment  structures were in various stages of deterioration
and otherwise poorly managed.   These  containments  were releasing hazardous
 substances  into the  environment in significant quantities.   The release of
 these  substances resulted  in  both on  and off-site  contamination of soil,
 surface and  ground water.

     One major  route of  off-site contamination was Mill Creek which runs
through the site, eventually  flowing  into  the Duwamish River  and Puget
Sound.  Sampling and analysis of Mill Creek  identified hazardous substances
downstream from the  site,  including a number of carcinogens.   These
bodies  of water are  used extensively  for fishing and recreational purposes.
Hazardous substances have also been detected  in an  underground  aquifer,
potentially contaminating  a  local supply of drinking water.

-------
                                    3-8

      Second,  drums containing flammable hazardous  substances were  releasing
 toxic fumes into the environment.   This situation  created a serious  fire
 and explosion hazard.

      Third, the fence surrounding  the site was  in  various stages of
 disrepair,  petmiting uninhibited access to the  site.  Fourth, on-site
 vehicles had been observed tracking contaminated material onto the adjacent
 roadways and neighborhoods.

 Response Options

      To stabilize conditions  on-site  and to prevent further off-site
 contamination,  EPA determined that an immediate removal action was warranted.
 Three options were considered to eliminate the  immediate threat at this site:


      Option 1:  Stabilize  Substances and Store On-site

        o  overpack drums;
        0 Supply new tanks; and
        0 Stabilize fertilizer, flue ash and battery
           chip piles on-site.
     Option 2; Partial Clean-up and Disposal

       0 Stabilize all bulk materials on-site
           (e.g. battery chips and fly ash);

       0 Treat surface ponds on-site or dispose
           off-site;
       0 Decant ink bottoms and treat effluent;
       0 Stabilize and cover the fertilizer pit
           to prevent run-off or leaching; and
       0 Dispose of 1500 to 2000 drums off-site.
     Option 3; Complete Surface Clean-up and Disposal

       0 Remove all containments, flue ash,
          zinc bottoms, and fertilizer pit;
       0 Clean surface pits; and
       0 Bnpty all tanks.
     Evaluation of Options;

     EPA determined that the Partial Clean-up Option (Option 2 )
was the most cost-effective removal action.  The following matrix
summarizes the criteria EPA used to determine the appropriate
action for this site:

-------
Task
Technically
Feasibile
Estimated
Cost
Option 1
yes
$1,095,000
3-9
Option 2
yes
$ 750,000
Option 3
yes
$2,709,000
  Effectiveness
   in eliminat-
   ing immediate
   threat on and
   off-site
partially
yes
yes, but
beyond scope
of emergency
action
Consistency
with yes
remedial
activities
overlap with
yes remedial
activities
 Removal  Action

      An  immediate removal  action was approved for the site on April 15,
 1983.  EPA directed  the overall clean-up effort with the assistance
 of  Federal,  State, and local governmental authorities including: the U.S.
 Coast Guard,  the  U.S. Public Health Service, the Centers for Disease
 Control, the Washington Department of Ecology, and the City of Kent Fire
 and Police Departments.  The Coast Guard generally assisted EPA in overseeing
 the clean-up contractor, directing site activities, providing site safety
 monitoring,  as well  as administrative and cost control functions.  The
 Public Health Service and  Centers for Disease Control provided public
 health information and assistance.  The Kent Fire and Police Departments
 provided fire and security assistance.  The removal action was actually
 carried  out as follows.

     On  April 15, 1983, EPA held a meeting to discuss cleanup capabilities
 and to prepare a general contract for site response activities.  On April
 18, 1983,  EPA began  staging equipment for on-site work.

     On  April 19, 1983, EPA began the iitmediate removal action at the
 site.  Response activities included the following.  EPA installed a
security fence, established a communication command post, and briefed
on-site  personnel of the site safety plan.  EPA began staging, overpacking,
sampling, and identifying contents of drums, testing tanks and surveying
surface  impoundments for leaks or deterioration,, controlling surface
 runoff,  and conducting other site stabilization as well as air and soil
monitoring activities,  EPA also began investigating options and developing
proposals  for off-site disposal and/or recycling the site's hazardous
wastes.

-------
                                    3-10

      On May 6, 1983, the Partial Removal Option (Option 2) was selected
 as the most cost-effective alternative for completing  this removal action.
 This option included removal and off-site  disposal of  drum and tank
 wastes, paint sludges, as well as acid waste and other waste water from
 lagoons.  All other materials were stabilized on-site.  Stabilization
 activities included transferring contents  from  deteriorated containers to
 lined tankers or suitable drums, constructing a contairment pit for
 fertilizers, and constructing a berm to prevent off-site drainage of
 substances remaining on site.

      Project costs escalated dramatically  due to high  disposal costs.  An
 exemption to the $1 million limit imposed  by CERCLA was approved on May
 7, 1983, and the project ceiling was raised to  $1.6 million.  Actual
 clean-up costs were approximately $1.4 million.  The action was completed
 on July 1, 1983.

 Enforcement

      EPA has initiated a variety of  actions (e.g. administrative compliance
 orders under both CERCLA and RCRA) over the past few years to compel the
 responsible party to conduct appropriate hazardous waste management and
 clean-up actions.   As indicated,  the responsible party failed to comply
 with EPA's order to conduct the inwediate  removal action.  EPA plans to
 initiate cost recovery action to recover any CERCLA funds (for both
 removal and remedial costs)  that have been used  to finance site clean-up
 actions.

                             BROWN'S  FIELD  SITE
Site Background

     This site is an abandoned hazardous waste site located near the
Brown's Field Airport in Chula Vista, California.  The site contained 265
drums of hazardous materials that were deposited on site in September
1982.  These drums contained a variety of hazardous substancs including
acetic acid, hydrogen cyanide, and styrene.  A truck enroute to a chemical
recycling facility in Tijuana, Mexico deposited the material at the site
after failing to clear customs at the United States/ Mexican border.
After failing to gain private party cooperation in cleaning-up this site,
State officials contacted EPA for assistance on June 23, 1983.  EPA
initiated an immediate removal action on July 22, 1983.

Nature of the Threat

     The 265 druns deposited at the site were in various stages of deteri-
oration, threatening to release hazardous substances into the environment.
Many of the substances contained in these drums are designated hazardous
substances which pose a significant threat to human health and the
environment.

-------
                                   3-11
     The nature of the threat at this site was direct contact of hazardous
substances to humans, a fire and explosion hazard, as well as soil and
air contamination.  These threats existed due to the deteriorated condition
and improper storage of hazardous substances at the site.

     The most significant threat to human health was from fire, explosion,
and/or the release of toxic gases and vapors.  Industry and airport
personnel as well as approximately lOOO people who resided within three
miles of the site were potentially threatened by this situation;.  The
most significant environmental threat resulted from the potential con-
tanination of area plant and animal life as well as nearby irrigation
wells.

Response Options

     EPA determined that aij ptoediate removal action was necessary to
eliminate the threat at tns site.  The following summarizes three options
considered to mitigate or stabilize the threat at the site:

     Option 1; Limited Stabilization' On-site

       0 Provide 24 hour site security;
       0 Pence site to prevent direct contact;
       0 Provide berms to prevent runoff; and
       0 Stage and segregate drums for on-site
         storage.

     Option 2: Stabilization On-site

       0 Provide 24 hour site security;
       0 Pence site to prevent direct contact;
       0 Provide berms to prevent runoff;
       0 Overpack leaking and deteriorated
           drums; and
       0 Stage and segregate drums for on-site
           storage.


    Option 3; Off-site Disposal

       0  Provide 24 hour site security;
       0  Fence site to prevent direct contact;
       0  Provide berms to prevent runoff;
       0  Overpack leaking and deteriorated
           drums;
       0  Stage and segregate drums for
           off-site disposal;
       0  Remove and dispose of hazardous
           substances; and
       0  Remove and restore contaminated soil.

-------
                                    3-12

      Evaluation of Options;

      EPA determined  that the Off-site Disposal Option (Option
 3)  was the most cost-effective  removal action for this site.
 The following matrix summarizes the criteria EPA used to
 determine the appropriate action at this site:
Task
Technically
feasibile
Estimated
cost
Time frame
Maintenance
after action
Other

Option 1

yes

$47,000
15 days

yes
local
concern
Option 2

yes

$57,000
15 days

yes
local
concern
Option 3

yes

$141,000
30 days

no
none

Removal Action

     EPA managed the overall removal action with the assistance of the
U.S.  Coast Guard, and the County of San Diego and the California Depart-
ment of Health Services.  The Coast Guard generally assisted EPA in
overseeing site activities.  State and local Health Services Departments
provided public health and environmental information.  The following
summarizes how the removal action was actually carried out.

     The County of San Diego and the State of California had inspected
and sampled site contents over a one year period beginning shortly after
the hazardous substances were deposited at the site.  State and local
officials were unable to gain private party cooperation in cleaning up
this site.  In addition, the State had insufficient funds to finance the
clean-up.  As a result, the State notified EPA and requested Federal
assistance to clean-up the site on June 23, 1983.

     EPA conducted a preliminary assessment of the site on June 25, 1983.
After concluding that the site presented an unacceptable threat to hunan
health and the environment, SPA notified the responsible party of the
site problem and requested private clean-up on June 28, 1983.  After
failing to obtain a positive response from the responsible party, EPA
initiated an immediate removal action on July 22, 1983.

-------
                                    3-13

      EPA conducted the following activities in initiating this  removal
 action.  EPA established 24 hour site security and constructed  a security
 fence to prevent direct contact by unauthorized persons;  collected and
 analyzed drum contents to determine the substances and their quantities;
 sprayed a fire retardant and constructed a sand berm around  the drum area
 to prevent the spread of a potential fire; and initiated  an  investigation
 for determining alternative plean.-up and disposal  options.

      To carry out actual clean-up activities,  EPA  overpacked, removed,
 transported,  and disposed of the 256 drums. EPA also conducted both on
 and off-site soil and air sampling and monitorina  to determine  the extent
 of environmental contamination.  Soil samples  indicated that hazardous
 substances had contaminated some site areas, and EPA removed and disposed
 of the soil accordingly.

      This removal action «^s Cjqfnpleted August  17r  19P3.  EPA oblioated
 5164,273 for the action.

 Enforcement

      As indicated,  the State qf California and EPA attempted but failed
 to obtain  responsible  party clean~up of this site.   The State of California
 filed a suit against  the responsible parties for removal  of  the drums and
 civil penalties  for violation of various California health and  safety as
 well as business and  professional codes.   SPA  has  initiated  action to
 recover costs of the removal  action  conducted  at the site.   This case
 has been referred to  the Department  of Justice for court  action.
                          HAMPTON CYLINTER SITE
Site Background
     This site  is a vacant lot in Hampton, Virginia that contained over
4500 improperly stored, le^ino;, and, deteriorated cylinders and drums.
The lot was improperly used as a storage site for a cylinder testing
facility.  These cylinders, an$ drums contained a variety of hazardous
substances including acstv^fsftgr flouromethane, propane, and trichloro-
ethylene.  The situation ^BJSI tf?£& brought to the attention of Hampton
City officials on June ft, 1983.  BPA initiated an immediate removal
action on June, 16, 1983.

Natureof Threat

     The improper storage. ajKl deteriorated condition of the cylinders
and drums posed a direct and immediate threat to human health and the
environment.  The substances identified above as well as others in the
containers are flammable, explosive, or acutely toxic when inhaled.  A
threat to human health and the environment existed via the potential for
fire, explosion, and inhalation from cylinder releases.

-------
                                   3-14

      The existence of flammable and  toxic materials at this site posed an
 imminent threat to approximately 1000 people who  lived or worked within
 1/4 mile of the site.  Included within  this 1/4 mile  radius was a State
 run school.  The threat of  this situation was  intensified by high temperatures
 which caused vapor releases from many of the cylinders.  These releases
 increased the potential for direct contact, fire  or explosion.

 Response Options

      EPA determined that an immediate removal  of  all  cylinders and drums
 from the site was the only  feasible  option.  This option was as follows:

        0 Evacuate all persons within 1000 feet of
            the site;
        0 Arrange for 24 hour site security to
          prevent direct contact by unauthorized
          persons;
        0 Sample cylinders and drums  to  identify con-
            tents,  determine extent of hazard,  and
            proper disposal  options;
        0 Overpack and stage cylinders and drums
            according  to hazard;
        0 Segregate cylinders and drums  by DOT
            hazard class;
        0 Destroy cylinders  or drums  if  contents
            cannot  be  identified;
        0 Arrange for  removal and off-site disposal;
            and

        0 Sample soil  for contamination.

 Removal  Action

      EPA managed the  overall clean-up effort with the assistance of the
 Federal  Emergency  Management Agency  (FEMA), the U.S. Coast Guard, the
Virginia Office of Emergency and Energy Services  (OES), the Virginia
 Department  of  Health,  the State  Police, the State Fire Marshalls Office,
 the Cities  of  Hampton and Newport News Police  and Fire Departments and
Offices  of  Civil Preparedness, as well as the  Merican Red Cross.  FEMA
and the  American Red Cross managed and carried out the temporary relocation
of nearby residents.  The Coast Guard generally assisted EPA in overseeing
site  activities.  The various State  and local  entities assisted EPA in
matters  pertaining to public health, as well as fire protection and
site  security.

     On June 9,  1983,  the Hampton Fire Marshalls Office responded to a
complaint that  cylinders were improperly stored on the site.  The Fire
Marshalls Office issued a clean-up order to the site owner to clean-up
the site within  15 days.  On June 13, 1983, the Fire Marshalls Office re-
sponded  to another complaint that gas was being released from the cylinders
on this site.  The Fire Marshall  subsequently contacted an industrial
expert who expressed concern about the hazardous nature of the site.

-------
                                   3-15

      On June 15,  1983, specially trained personnel from the Fire Marshalls
 Office conducted  an investigation and subsequently contacted the State
 Office of Emergency and Energy Services for assistance in determining the
 nature of the threat created by this situation.  OES conducted another
 investigation that afternoon.  On June 16,  1983, OES contacted EPA for
 assistance.

      EPA's Region III coordinator conducted a preliminary assessement on
 June 16, 1983, and determined that Federal  action  under the Superfund
 program was  necessary to protect hunan health and  the environment.  The
 State of Virginia was unable to initiate and maintain the appropriate
 action but agreed to participate by providing technical assistance.  The
 responsible  party was unavailable and had failed to comply with a  previous
 clean-up order.   EPA then initiated an immediate removal of all cylinders
 and drums.

      The removal  action was initiated on June 17,  1983.   The Hampton
 Police and Fire Departments secured the site to prevent entry  by unauthorized
 persons.  EPA assisted in on-scene safety coordination.   The Virginia
 Office of Emergency Services began monitoring the  site to determine the
 public health impact.   Representatives from the Coast Guard moved  on-scene
 to  aid EPA.   EPA's coordinator worked with  City Emergency Services officials
 to  expedite  telephone and electrical hookups to establish a site command
 post.

      EPA informed FEMA of the site situation and requested that they
 undertake temporary relocation of approximately 75 people for  a period of
 5 to 7 days  while work at the site took place.  FEMA carried out the
 evacuation with the assistance of the American Red Cross who provided
 temporary housing facilities.  The City of Hampton Fire  Department provided
 water for decontamination and cooling of cylinders,  briefed the local
 trauma center on  potential health hazards,  and arranged  for emergency
 transport of persons to medical  facilities.

     On June 18,  1983,  EPA fully assessed the site to determine the extent
 of  the threat and contamination at this site.  In  addition, personnel were
 briefed on general site clean-up procedures  and the  site safety plan was
 drafted.

     Between June 19 and  June 2.5 the cylinders and drums were  inspected and
 their  contents were analyzed.  Once the contents were identified,  they were
 overpacked and staged  acpordi-ng  to the degree of hazard .they posed to human
health  and the environment.   Finally,  the cylinders  and  drums were transported
 to a  temporary hazardous  waste storage facility in North Carolina.

      On June 25,  1983, the site was  inspected to  ensure that  it no longer posed
 a threat  to  human health  and  the environment,  and  the community evacuation
was suspended.  All  cylinders  were deposited  in the  temporary storage
 facility by June 27, 1983.

-------
                                   3-16

      After disposal in the temporary facility, EPA began developing cost-
effective disposal or recycling options for the cylinders.  The cylinders
were relocated to a RCRA approved pecmanant facility for disposal and
recycling on September 21, 1983.  The removal action was officially
completed on January 25, 1984.  EPA obligated 297,100 for this removal
action.
Enforcement

     EPA is pursuing cost-recovery action to recover CEPCLA funds used to
finance this removal action.  EPA has referred this case to the Department
of Justice, which has filed an action under CERCLA section 107 to recover
these funds.

-------
                               4 .
     The purpose of  the  .Superfund enforcement program is  to secure responsible
party cleanup of releases and  threatened releases wherever possible and to
recover the  costs of Fund-financed response actions,  Hnlike enforcement
programs under other statutes administered by EPA, CEFCLA enforcement does
not focus on compliance  with a complex regulatory system based on standards
of  environmental quality and human health.  Instead, CERCLA establishes a
civil enforcement program to hold responsible parties liable for releases
or  threatened releases of hazardous substances that may present substantial
danger  to public health  or welfare or the environment.

     In  addition to KPA's authority to order responsible party response
actions and  to recover costs under sections 10 fi and 107 of CRPCLA,
EPA may  also use its authority under the Resource Conservation and
Recovery Act to  address  releases of hazardous wastes: 1

           0  For example, under section 3013, EPA can order owners
             and opera tors of a site to conduct a remedial
             investigation whenever the release of waste may present
             a "substantial hazard to human health or the
             environment."  In an action taken under section 3013,
             therefore,  EPA is not required to establish "imminent
             and substantial endangermen t ."

           0  Section 7003 authorizes EPA to bring suit or take
             other action as may be necessary to prevent endangermen t
             from the "handling, storage, treatment, transportation
             or disposal of any solid waste or hazardous waste."
             Because this section is not tied to Subtitle C of the
             Resource Conservation and Recovery Act, which defines
             hazardous wastes to exclude petroleum and mining waste
             releases, the CERCLA enforcement program may use section
             7003 or civil action orders to abate threats from releases
             of petroleum and mining wastes and other wastes not listed
             as  hazardous wastes under CFPCLA at Superfund sites.

firders under sections 3013 may only be issued to ovners and operators
of  hazardous waste treatment, storage, or disposal facilities, however, and
thus are not appropriate in  cases where EPA takes enforcement action against
other types of responsible parties.
   Many of the early Superfund enforcement, cases dealt with violations of
   the Resource Conservation and Recovery Act that occurred before CKRCLA's
   passage.

-------
                                     4-1
     To indicate the broad  enforcement authorities for addressing hazardous
substance  releases,  Exhibit 4-1 presents a 5-year summary of enforcement
settlements  achieved under  an  administrative consent order, a consent
decree, or a consent aqreement.  These settlements are categorized accordinq
to the laws  and  sections under which  they were siqned.  As the data indicate,
a  larqe proportion of early enforcement settlements were under the authority
of the Resource  Conservation and Recovery Act.  As the Superfund program
evolved, however, an increasing number of settlements have been the result
of CERCLA  section 106 and 107  actions.

                                EXHIBIT 4-1

       STATUTORY AUTHORITY  OF  S17PERFUNP ENFORCEMENT SETTLEMENTS3
Statute Section      1980

RCRA    113013          0
RCRA    IIVOOS13         4
CERCLA  1I106C          o
CERCLA  11107           0
CERCLA  1(106/107^      0
1981

 0
 9
 0
 0
 0
 FISCAL YEAR
1982     1983
  5
 15
  3
  0
  2
 9
 4
11
 2
 8
198-db

  10
   6
  39
   8
   5
Total

   24
   38
   53
   10'
   15
    SOURCE:  Enforcement Case Manaqement System, Office of Solid Waste and
             Emerqency Response
    a   This table does not enumerate all settlements achieved, because a
small number of settlements at Superfund sites have been reached under the
authorities of other environmental statutes, such as the Toxic Substances
Control Act and the Safe Drinkinq Water Act.

    b   Includes those cases taken under authorities of Sections 7003/3013.

    c   Includes those cases taken under authorities of Sections 106/7003 and
Sections 106/3013 settlements.

    d   Includes those cases taken under authorities of Sections 106/107/7003
and Sections 106/107/3013 settlements.

-------
                                    4-2
      Recent enforcement policy emphasizes the use of administrative orders
 and civil  actions pursuant  to CERCLA section 106 to secure "up front"
 private party response  as well as the recovery under section 107 of previously
 expended Federal funds  to maximize environmental results.  The appropriate
 use of section 106 authorities to compel private party action is preferable
 to an exclusive reliance on cost recovery for the following reasons:2

           0   It is consistent with the intent of Congress that
              responsible parties should be compelled to clean up the
              hazards  they create, whenever feasible;

           0   It provides the only mechanism for cleaning up sites
              when use of the Fund is prohibited (e.g.,  when states
              cannot meet their statutory cost-share obligations);

           0   It may provide for additional protection of the public
              health or environment at specific sites since
              enforcement remedies can be more extensive than Fund-
              financed ones since enforcement remedies are exempt
              from the Fund-balancing requirement of CERCLA section
              104(c)(4).

           0   Successful "up front" enforcement actions  encourage
              additional settlements; and

           0   Successful "up front" enforcement preserves Fund
             monies for use at other sites where no financially
              capable responsible parties are identified.


              COORDINATION WCTH REOTVAL AND REMEDIAL PROGRAMS
     At each hazardous waste site, EPA must initially decide whether
to exercise its enforcement authority bo compel  cleanup,  or  to conduct a
Fund-financed remedial or removal action.  Conditions at  the site and the
likelihood of securing responsible party cleanup are the  two important
factors in determining how to proceed at a site.  EPA must ensure  that its
decisions are consistent with the overall objective of protecting public
health and welfare and the environment.  Coordination of  enforcement and
Fund-financed action involves:

          8  Identifying sites that are appropriate for enforcement
             actions;

          0  Determining the point at which enforcement efforts
             should cease and a Fund-financed  action should  be
             initiated; and
    2 "CERCLA Enforcement and Compliance Strategy"  (rraft), Office of Waste
      Programs Enforcement, January 12,  1984.

-------
                                     4-3
           0  Minimizing the overlap of enforcement and program
              activities at a site.

 Qoals and Related Policies;

      Initially, EPA implemented a system whereby sites with financially
 capable potentially responsible parties were managed first  by  the enforcement
 program.  Because most sites have at least one identifiable potentially
 responsible party with some ability to pay for cleanup, most sites beqan as
 enforcement sites.  "tie removal and remedial offices would  address sites only
 if  they were emergencies or if  no financially viable potentially responsible
 parties could be found.  Otherwise, the signature of the  Assistant Admini-
 strator of the (now reorganized)  Office of Legal and Enforcement Counsel
 was reguired for a site to be referred to the program offices.

      In 1982,  EPA experimented  with a "dual-track" system whereby
 Fund-financed remedial planning activities could be conducted  at the same
 time that enforcement staff negotiated with responsible parties for  financing
 of  subseguent phases of work at the site.   Ttie dual-track system too often
 resulted in duplication of efforts  between program and enforcement staff.

      The Site Classification System which went into effect  in  June 1983,
 replaced the dual-track system  for  remedial response sites.3  This system
 divides sites  into categories depending upon such factors as the strength and
 likelihood of success of the enforcement case,  the need for prompt response
 at  the  site, and the ability of states to  provide the necessary statutory
 assurances for Fund-financed activity to begin.   Specifically:

           0 Category I sites are sites where,  in general,  only
              Fund-financed response will be conducted.  Most of the
             sites in this category are sites where no financially
             capable potentially responsible parties have been
             identified.   As of September 30,  1984, 79 sites were
             classified as Fund-lead sites.

           °  Category II  sites  are  enforcement-lead sites.   Sites
             are placed in this category if the  case against respon-
             sible parties is strong and there is no immediate need
             to begin remedial  activity at the site.   Negotiations
             are held with responsible parties and,  if  no settlement
             is reached,  RPA must use civil or administrative
             authorities  under  CEPCLA section 106{a).   The  remedial
             investigation and  feasibility study may be conducted by
             EPA using  Fund monies,  or by  the potentially responsible
             party if the party agrees to  follow EPA's  scope of
    3 See "Guidance for Selecting Enforcement Action on Fund-financed
Response at Sites Under the Superfund Law", (Draft) Office of Emergency and
Remedial Response, June 8, 1983.

-------
             work.  Generally, no Fund monies should f"*e expended for
             response activities after these studies are completed
             for Category II sites.  In September 19R4, 175 sites were
             cateqorized  as Federal-lead enforcement sites.

           0  Category III sites are sites where there is only
             limited time available for neqotiations before response
             actions must benin.  Neaotiations are limited to 60-120
             days after EPA (or the potentially responsible party, in
             some cases)  conducts the remedial investiqation and
             feasibility  study.  If no aoreenent is reached durincr
             neqotiations, EPA may attempt to compel the potentially
             responsible  party to clean up the site by issuina a
             unilateral administrative order.  If the party refuses
             to  comply with the order, EPA proceeds with a
             Fund-financed remedial action and seeks to recover
             response costs and treble damaqes, if appropriate.
             Accordinq to September 19R4 data, ISO sites were listed as
             Cateqory III sites.

           0  Category IV  sites are State-lead enforcement sites
             where EPA's  role is limited to oversight and technical
             assistance.  State-lead enforcement sites numbered 136
             in  September 1984.4

EPA routinely monitors activities at sites included in the first three
categories.  Because EPA's role is limited for Category IV sites, less is
known about the  enforcement progress at these sites.

     Ihe role of enforcement in removal actions depends prunarily on the
time available before site actions must begin.  In emergencies, enforcement
efforts, if conducted at  all, are aimed at securing immediate, voluntary
action by responsible parties, usually the owner or operator of the site.
In most emergency situations, however, enforcement is limited to cost
recovery.

     At many removal sites, there may be a week or less between the time EPA
decides to undertake removal actions and the time site work must begin.  In
such cases, enforcement activities are to be conducted under strict time
schedules.  If private parties do not undertake response, EPA proceeds with
a Fund-financed  removal.
   In addition to sites classified in the four categories, there were 6
   unclassified sites as of September 19R4.

-------
                                     4-5


 Major Accomplishments

      The primary effect of the Site  Classification System has been to ensure
 that the enforcement and the Superfund program offices have clearly defined
 responsibilities for a large number  of separate sites.  Coordination problems
 still arise when responsible parties at Fund-lead remedial sites decide
 suddenly that they wish to settle, or when enforcement efforts fail
 unexpectedly.

      For the most part,  however, coordination seems bo be improved under the
 Rite Classification System and under the new removal coordination procedures.
 Further examination of specific cases, especially Category III sites which
 require the greatest coordination, might be valuable in assessing the need for
 refinements to the system,  in addition, since FPA's oversight of State-
 lead enforcement sites is  very limited, progress at those sites is unclear.


       NOTIFICATION OF POTENTIALLY RESPONSIBLE PARTIES AND NEGOTIATION


      Notification

      Notification  in  the enforcement program refers to the procedures used
 by EPA to inform parties of  their potential liabilities for the costs of
 responding  to releases of  hazardous substances and for natural resource
 damages.   Notification  in essence sets the stage for negotiations to secure
 agreement with responsible parties or to initiate unilateral administrative
 or civil action.

      EPA policy  requires notification of potentially responsible parties on the
 basis of CERCLA  section  104(a-)(l), which authorizes the President to conduct
 response actions ...  "unless  the President determines that such removal and
 remedial  action  will be done properly by the owner and operator of the
 vessel  or facility  fron which  the release or threat of release emanates,  or
 by any  other responsible party."  Written or verbal notice is the first
 step in determining whether a potentially responsible party is willing and
 financially capable of undertaking proper response.

      The first enforcement activity undertaken at hazardous substance release
 sites is  the attempt  to  identify potentially responsible parties.  Regional
 EPA staff usually examine Federal, State,  and local government and private
 party records  to identify past and present owners and operators of facilities
 at the  site and generators and  transporters of substances discovered at the
 site,  states also conduct responsible  party searches as part of the site
 investigation activities.

     Once the Regional staff identify parties who may be potentially liable
 under CERCLA for response costs and damages to natural  resources,  they then
 inform  them of their potential liabilities and of opportunities for partici-
pating  in planned response actions.  Where a remedial  response is  required,
 this  initial contact  takes the form of  a "notice letter."  For immediate
removals where more prompt response is  necessary,  EPA may contact potentially

-------
                                     4-6


 responsible parties by telephone.  In emergencies, such as a fire or potential
 explosion,  EPA may not have  time  to  notify potentially responsible parties
 at all.  In general,  EPA staff notifies potentially responsible parties
 well enough in advance of  planned  site actions  to allow recipients to
 contact EPA to discuss their participation in such actions or in future
 cleanup negotiations.  Since  the beginning of the Superfund program, however,
 the timing, content,  and objectives  of notice letters have varied in response
 to policy shifts regarding the participation of potentially responsible
 parties in  response actions.

 Goals and Related Policies

      The goal  of the  notification  process is to establish communications
 between EPA and potentially responsible parties.  Therefore, EPA's approach
 to notification has paralleled the Agency's approach to negotiating over
 reponse actions.  Initially, the Agency was willing to negotiate separately
 for the planning and  implementation  phases of remedial- action, and notice
 was sent at each phase. Notice letters were essentially "open ended" with
 no set time limits for response.   In February 1982, EPA identified potentially
 responsible parties for all 115 sites on the interim priorities list and  .
 issued a mass  mailing of 707 form  letters to those parties.  Two months
 later, only seven companies had responded with a willingness to negotiate .5
 Most of the respondents asked EPA  to demonstrate their responsibility for
 the release in question.

      In May 1983,  the Agency adopted a modified approach, setting out
 stricter  terms for  responsible party participation in response activities.
 Notice was  generally  sent  concurrently with Fund-financed planning efforts.
 In  addition, EPA increasingly used notice letters to request information
 under the authorities of CEPCLA section 104(e)  and PCRA section 3007(a) />
 There were  two drawbacks to this approach.  Some responsible parties wanted
 an  opportunity to conduct  or participate in the remedial investigation and
 feasibility study.  Also, parties were reluctant to accept the conclusions
 in  the feasibility stiriy and assime responsibility for the cleanup because
 their  views were not reflected in  the study.

      In  the spring  of 1984, EPA further modified its approach to notification.
 EPA will make  available a list of sites which are scheduled for remedial
 investigations/feasibility stulies and invite potentially responsible parties
 to participate in or conduct the remedial planning.  EPA will then send
notice  letters to potentially responsible parties for sites on the list and
5 "Hazardous Vfeste Enforcement," Report for the Subcommittee on Oversight
   and Investigation, Committee on Energy and Comerce, U.S House of
   Rspresentatives, December 1982.

fi  Notice letters were sent under section 104(e) of CEPCLA and section
   30(l7(a) of the Resource Conservation and Recovery Act.  These provisions
   authorize the Administrator to require handlers of hazardous wastes
   and substances to provide certain information about the origin and
   disposition of substances at the site.  EPA then uses this information
   to identify additional responsible parties and to prepare for negotiations
   or litigation.

-------
                                    4-7
 inform them  of  planned response actions, their potential liabilities, and
 opportunities t-o discuss  their participation in or conduct of those activities.
 These letters are sent at least fin days before the start of a remedial
 investigation or as early as possible before a removal to allow time for
 negotiation,  before the action gets under way.  Parties may conduct
 the activities  if they agree to follow  the requirements laid out by EPA.7

      As  of September 30,  19R4, EPA had issued approximately 5,900 notice
 letters  involving 227 sites.

 Negotiation

      Throughout the history of Superfund, KPA has acknowledged the importance
 of  negotiations  in securing responsible party cleanup of hazardous waste
 sites.  However,  EPA has  increasingly recognized the potency of its other
 enforcement  tools, such as the authority to issue unilateral administrative
 orders or  to initiate legal action.               .   .

      As  part of  its enforcement program, EPA will undertake negotiations with
 parties  identified to be potentially responsible for the release of hazardous
 substances.   These negotiations provide an opportunity for potentially
 responsible  parties to come to a settlement with EPA concerning their role
 in  the investigation, selection, design, and implementation of site cleanup.
 Negotiations, as discussed here are generally conducted only for remedial
 response sites.   EPA and potentially responsible parties may follow a
 similar  but  much  shorter course of negotiations before certain removal
 actions  when there is time before site work must begin.

      Ordinarily, before negotiations are initiated,  a case development  team
 of  Regional  and Headquarters technical and legal enforcement staff draws up
a draft enforcement document.  For remedial  negotiations conducted after
remedial planning, this draft incorporates the technical information and
suggested remedy of the remedial  investigation  and feasibility study.  This
draft document,  generally in the form of an  administrative order or consent
decree, is not final, but details the specific  technical  issues and proposed
 terms of settlement that then become the substance of the negotiations.

     In cases where there  are multiple parties  potentially responsible for
a site, EPA will not conduct individual negotiations, hut instead expects
the parties  to organize into a negotiating team,  which will  confer with EPA
as a single entity.  For all cases, there is a limit en the number of days
   "Participation of Potentially Responsible Parties  in  Development of
    Remedial Investigations and Feasibility Studies under CEPCLA," Memo-
    randum from lee Thomas, Assistant Administrator for  Solid frfeste and
    Emergency Response, and Courtney Price,  Assistant Administrator for
    Enforcement and Compliance Monitoring,  to  Regional Administrators
    (March 20, 19R4) .  This is referred to as  the  "March 19R4 Thomas/Price
    RI/FS Memo," in the remainder of this report.  "CERCLA Notice letters,"
    JVaf t Guidance, Office of  Waste Programs Enforcement and Office of
    Enforcement Counsel-Waste, U.S. EPA (April 1984) .

-------
                                     4-8

 allowed for discussion.  If negotiations will reouire more  than 60 days,
 the approval of EPA Headquarters is necessary.  As a matter of current
 policy/ negotiations should not exceed 120 days;  furthermore, EPA can end
 negotiations at any point between 60-120 days, if it judges that  appropriate
 progress is not being made.

      Negotiations in which EPA and the potentially responsible parties agree
 to the scope and terms of the remedy have generally resulted in a negotiated
 agreement, a consent administrative order, or a consent  decree.   A negotiated
 agreement, the eguivalent of a written "handshake",  is the  least  binding of
 the three settlements and, therefore, difficult to enforce  in court, EPA
 has not used this agreement since 1982.   A consent administrative order
 issued pursuant to CERCLA section 106 is a written agreement signed by EPA
 and potentially responsible parties specifying the actions  to be  taken by
 the parties.  A party who fails without sufficient cause to comply with a
 consent administrative order may be sued by EPA under CERCLA section 107
 for up to three times the costs of response made  necessary  by such non-
 compliance.   CERCLA does  not authorize treble damage penalties for failure
 to comply with consent decrees.

      A consent decree filed by the Department of  Justice is the most formal of
 the three types of settlements.  The Department must first  file a complaint in
 Federal district court and the consent decree must be signed by a judge.  The
 issuance of  a consent decree does not necessarily mean that the relationship
 between EPA  and the responsible parties during negotiations has been hostile.
 EPA encourages settlement by consent decree as opposed to consent order
 because a consent decree  is enforceable by the Federal district court.
 Consent decrees are especially encouraged when the number of responsible
 parties is large or the terms of settlement complex.

      EPA is  developing a  policy on public participation  in  enforcement
 actions that will provide for public comment on consent  administrative
 orders.  In  the case of judicial action  (i.e.,  consent decrees),  the Depart-
 ment of Justice usually conducts a 30-day public  comment period after the
 decree  is signed.   Consent administrative orders  or consent decrees may be
 amended or modified on the basis of comments received.   However,  the public
 is  not  allowed to participate directly in the negotiations.  While the
 discussions  between EPA and potentially  responsible parties are in progress,
 only a  limited amount of  "generic" information about the negotiating process
 may be  released.   EPA is  currently developing a policy that would reguire
 public  comment and a responsiveness summary on the remedial investigation/
 feasibility  study,  before  negotiations get under  way.  EPA  may involve
 public  representatives in meetings with  responsible parties under carefully
 defined circumstances.

     When negotiations are unsuccessful,  and no settlement  is reached, EPA may
 issue a unilateral  administrative order,  initiate (or continue) civil action
 under CERCLA section 106,  or undertake a Fund-financed cleanup followed by
 cost recovery efforts.

     Since the passage of  CERCLA,  EPA has developed guidelines for the
 negotiating process  to  make  the  discussions as  productive and conclusive as
 possible.  EPA generally will not conduct discussions with  parties who
offer to settle for  less than 80 percent  of the cleanup  costs.  All offers
 to settle  for less  than 100  percent of the costs  of cleanup must  be approved

-------
                                     4-9


 by EPA Headquarter s.R  Because of site-specific issues, RPA cannot standardize
 the format followed in  negotiations, hut must allow each discussion with
 potentially responsible parties  to follow its own course within the broad
 parameters defined  by RPA.

 Goals and  Pelated Policies

      Since the beginning of  the  Superfund program, the goal of negotiations has
 been  to secure privately managed or financed cleanup of hazardous substance
 releases.   Negotiations further  seek to docunent  the terms of settlement
 with  responsible parties in a written agreement (e.g., a consent order or
 decree) .

      Though the goals of negotiation have not changed during the history of
 CEFCLA,  the way negotiations have been implemented and their role in the
 overall enforcement program have gone through several distinct phases.

      Initially, EPA's approach was to seek an agreement with responsible
 parties prior  to recourse to the Fund or litigation.9   Under this initial
 policy,  RPA was willing to segment negotiations.  Each phase of a site
 response was discussed  separately, before the remedial investigation and
 feasibility study and again later before remedial design,  and later still
 before implementation.  As long as there was a possibility that action by a
 potentially responsible party might forestall or prevent the need for
 drawing  upon the Fund,  RPA was willing to negotiate.

     There  were several problems with this approach.  Negotiations before
 remedial planning were  often protracted and ill-defined, because neither party
 to  the discussions could be certain about the nature and costs of the remedy.
 Negotiations over the remedial investigation and feasibility study were
 often splintered into issues of specific detail:  where and how to sample
 for contamination,  the methods of detection, thresholds of detection, etc.
 Remedial investigations and feasibility studies that were  undertaken by
 responsible parties were often inadequate, in part because guidelines for
 the studies  had not yet been developed.  Finally, as a result of these
 problems, necessary response actions were delayed.

     The "dual-track" strategy of concurrent enforcement and Fund-lead
 action,  introduced  in 1982, was intended to deal with sane of these problems.
The advantage of this strategy — a more promptly initiated Fund response
 — was more  than offset by the same disadvantages associated with the
   "Interim Hazardous Waste Case Settlement Policy/1 Memorandum from Lee
    Thomas and Courtney Price to Regional Administrators, Regional
    Counsels, and Regional Iteste Division Directors (undated) .

   "Huidelines for Using the Imminent Hazard,  Enforcement and  Emergency
    Response Authorities of Superfund and Other Statutes" (47  Federal
    Ftegister 20664) .

-------
                                     4-10

 with the earlier policy.   The dual-track strategy also introduced a new
 problem: duplication of effort at the same site by the program  and enforcement
 personnel.

      A third,  and current, phase in the evolution of enforcement negotiations
 began in early 1983, when the EPA adopted the Site Classification System.
 Sites are assigned a provisional classification prior to remedial planning,
 and then a final classification once the feasibility study has  been completed.
 EPA intended that the Site Classification Sytem would clarify the role  of
 enforcement actions and negotiations in the overall response  process.

      By determining whether a site meets the  criteria necessary for a
 Category II site, EPA identifies in advance whether or not the  remedy for a
 site could be  negotiated  successfully or,  failing that, enforced successfully
 using section  106 authorities.   The classification procedure  represents a
 distinct change from an earlier period when negotiations were often initiated
 with inadequate case information,  and few clear expectations  as to where
 the talks might lead.

      Another policy change in the  role of negotiations concerns EPA's
 willingness to bargain with potentially responsible parties about their
 role during remedial planning.   In the first  years of Superfund, EPA met
 with potentially responsible parties to negotiate a privately managed
 remedial investigation and feasibility study.   Subseguently,  EPA allowed
 private party  participation in  remedial planning only if they were willing
 to  make a prior commitment to conduct the remedy selected by  EPA.  Current
 EPA policy permits potentially  responsible parties to conduct the remedial
 investigation  and feasibility study if they agree to follow certain
 reguirements established  by EPA.1°  However,  EPA will not permit significant
 negotiations over the  scope of  work.

      As discussed above,  responsible parties  will have an opportunity to
 conduct the remedial investigation for those NPL sites slated for remedial
 investigations and feasibility  studies in the current fiscal  year.  However,
 agreement must be reached by the scheduled start date for Fund-financed
 planning.   Furthermore, potentially responsible parties must  agree to
 organize themselves  to  conduct  the remedial investigation and feasibility
 study,  and must follow the technical procedures for the study that EPA  is
 currently preparing.   The procedures should be documented in  some type  of
 administrative order or consent dcree.   This prospective policy becomes
 effective when the  remedial  investigation  and feasibility study guidance
manuals are issued.

      For any NPL site  not on the Remedial  Accomplishments Plan, potentially
 responsible  parties may conduct the  remedial planning studies only if they
 further agree  to design and  conduct  the remedy  stipulated by  EPA.  Under
 this policy, EPA hopes  to eliminate  the  need for further negotiations at
 such  sites  over the  remedial design and implementation.   Resources thus
freed will be  used  instead to supervise  the privately conducted remedial
 investigation  and feasibility study.
10
Thomas/Price Remedial Investigation and Feasibility Study Memorandum.

-------
                                     4-11


 Major Accctnplishnents

      Negotiations have been increasinqly successful  over the past two years  in
 promtinq settlements with responsible parties.   Forty-six settlements were
 achieved under administrative consent orders in FY 84;  this  compares to  20
 administrative consent orders in FY 83,  and  nine in  FY  82.   Settlements
 reached under consent decrees have increased somewhat.   In FY84,  IP consent
 decrees were signed; in FY83 and FY82, the number was 15 and 20 respectively.
 Exhibit 4-2 depicts the number of administrative consent orders and consent
 decrees siqned during each of the past four  fiscal years.

      EPA has begun to increase enforcement actions at removal sites and  is
 attempting to increase the number of negotiated orders  issued for removal
 actions.  This policy was initiated in the autumn of 1^83, and was recently
 formalized.I1  The data on settlements indicate that the policy is taking hold:
 for FY 84, 17 consent orders and one consent decree  were siqned for removal
 actions.  This number corrpares with a total  of  four  negotiated settlements
 for removal actions in FY 83,  four in FY 82, and two in FY 81.

      In the  case  of privately-conducted  remedial  investigations and
 feasibility studies, the settlement data also reflect the recent  policy
 decision to  permit the involvement of responsible parties in resnedial
 planning.  Exhibit 4-3 shows the number  of negotiated settlements which
 stipulated remedial planning by responsible  parties  during the four-year
 history or Superfund.

     The dollar-value of negotiated remedies has also increased markedly
 since  FY 81.   From, FY 81 to FY 82,  the value of  settlements  declined from
 $53  to $16 million.   In FY 83,  however,  settlements  values increased to
 over $95 million.   Over 50 percent  of this amount was accounted for by two
 settlements  achieved under consent decrees:  $24 million for  a total remedial
 cleanup of the Olin Triana site,  and $24.5 million for  a total reinedial
 cleanup of the Velsicol site.   .Settlement amounts for FY 84  increased $50.3
 million over  amounts  for FY83:  again,  two settlements in particular were
 responsible  for a large proportion of FY 84's dollar total (settlement at
 the  Hooker Chemical site  resulted  in a $45 million cleanup, while  a reinedial
 action undertaken by consent decree at Petro Processors in Baton  Rouge was
 valued  at $50 million).   Exhibit 4-4 tabulates  the dollar amounts  of
 negotiated settlements over the past four fiscal  years.

     In  general, negotiating activity has incrased considerably over the
 past two years, and recent policy changes are having a  positive impact in
 terms of  the  number and kinds of settlements achieved.   The  success of
 negotiations  is partially related  to the perceptions responsible  parties
have that EPA will use  its strong civil and  administrative enfrocement
authorities if negotiations are not proceeding  toward a desirable  settlement.
As discussed  in the following sections,  EPA  increasingly has demonstrated
a willingness to  use these authorities and this may  account  to some degree,
for the rise  in negotiated settlements.  EPA has also recently issued an interim
    "Issuance of Administrative Orders for Immediate Removal Actions,"
     Memorandum from Lee Thcmas, Assistant Administrator for Solid Waste
     and Emergency Response, to Regional Administrators, Regional Counsels,
     and Regional Division Directors, February 21, 1984.

-------
                                    4-12


                                EXHIBIT 4-3

             REMEDIAL INVTEPTIGATIONS/FEASIRILITV STUDIES  (RI/FS
                       CQNpncTED BY RESPONSIBLE PARTIES


                                          FISCAL VEAR

                          19fll        1982          1983          1984

         RI/PS              2          2            4            17
        SOURCE:  Enforcement Case Management System, Office of Waste Programs
                 Enforcement.
                              EXHIBIT 4-4
               VALUE OF SETTLEMEMTs (in thousands of dollars)
                       (COST RECOVERIES MCTF INCUTPED)
                                          FISCAL YEAR

                    1980     1981      1982    1983      1984     Ibtal

&3ministrat ive
Consent Orders               $500     $9,650   $27,200   $23,670  $ 60,020

Consent Decrees     $800   52,784      6,208    67,965   122,835  $250,592

    TOTAL           $800  $53,284    $15,858   $95,165  $145,505  $310,612
    ROfTRCE:  Enforcement Case Management System, Office of Solid Waste and
             Emergency Response.

-------
                                     4-13

 case settlement policy 12 wich seeks to define more precisely the goals of
 negotiation,  acceptable negotiatina terms, and the circumstances in which
 litigation is the  preferred alternative.  While these definitions may limit
 the role of neqotiations within  the overall  context of enforcement activity,
 they may also serve to focus  the negotiating process, making it a more
 powerful enforcement tool.
                              CIVIL LITIGATION

 Description of Activity

      Under certain circumstances, EPA may decide to initiate civil action
 against potentially responsible parties under CERCLA section 106.  Fuch
 action may be appropriate when parties have demonstrated during negotiations
 that  they  are unwilling to accept their liability for necessary cleanup.
 Negotiations  may or may not precede the decision to initiate a section lOfi
 action, however.   Further grounds for civil action might be the failure of
 parties to cease voluntarily from conducting activities that may endanger
 public health or welfare or the environment.

      Litigation  reguires that the Department of Justice file a complaint in
 Federal District Court.  In order to file and successfully prosecute a
 complaint, EPA and the  Department of Justice must, at a minimum, have
 evidence to show the following:

         0  There  must  be an actual or threatened release of a
            "hazardous substance" as defined in section 101(14) of CERCLA;

         0  EPA must establish that the actual or threatened release may
            present "an imminent or substantial endangerment to public
            health or welfare or the environment-"13

         0  The actual or threatened release must be from a "facility"
            as defined  in CERCLA section 101(9); and

         0  The liability of responsible parties for the release
            must be clearly documented.

Additionally, EPA must thoroughly document the nature of the contamination
problems at the site as justification for the reguired remedy and respond
to issues raised by the defendant.
12  "Interim Hazardous Waste Case Settlement Policy, "Memorandum from Lee
    Thomas and Courtney Price to Regional Administrators, Regional Counsels,
    and Regional Waste Division Directors.

13  EPA conducts an endangerment assessment to establish the existence and
    nature of the "imninent and substantial endangerment."  See EPA's draft
    "Endangerment Assessment Guidance",  Memorandum from Lee Thomas, Assistant
    Administrator for Solid Waste and Emergency Response, to Regional
    Administrators, April 1984.

-------
                                     4-14

      Before decidinq whether to refer a case  to the Department of Justice for
 filing,  EPA must  also determine if  the specified site response is needed
 shortly, or can be safely delayed without  aggravating the  "imminent and
 substantial endanqerment" to public health or welfare or the environment.
 When site response must be undertaken promptly,  FPA will choose first to
 initiate a Fund response, and then  later to sue  the responsible parties to
 recover  Fund expenditures,

      The Department of Justice, as  attorney for the Federal novernment, usually
 conducts the trial and related litiqation.  EPA provides technical support to
 the Department during the litioation process.  EPA will also participate in
 negotiations with responsible parties after a complaint has been filed by
 the Department.  Often,  f ilinq a complaint may prompt responsible parties
 to  negotiate a settlement before or even during the trial  itself.  Settlement
 agreements reached after a complaint has been filed by the Department of
 Justice  are formalized in a  consent decree signed by EPA,  the Department,
 the responsible parties,  and a judge. 14

      Litigated cases,  however,  may  proceed to a  iudicial decision because
 no  negotiated settlement  between EPA and responsible parties can be reached.
 In  evaluating whether  to  accept settlement offers, EPA may consider whether
 the case would establish  an  important legal precedent.

                                 EXHIBIT  4-S

                     MENTS POT? REMEDIAL AND PKMOVAL ACTIONS a
                                       FISCAL YFAR

                              19P1        1982          19R3          19R4
Remedial Actions
  All Settlements              9           23            27             S2
  Settlements at NPL Sites     a           12            22             3*
Removal Actions
  All Settlements              2            4             4             18
  Settlements at NPL Sites     0            2             3             10
    a  Some settlements were reached which stipulated the performance of
both a removal and remedial action, and are therefore counted in both
categories.  There was one such settlement in FYfll;  two in FYR2;  none in
FYR3; and 11 in FYR4.

    Source:  Enforcement Case Management System, office of Solid Waste and
             Emergency Response.
    A consent decree, however, does not automatically indicate that the
    case is a litigated case.  As noted in the text, EPA and/or responsible parties
    may choose to formalize a negotiated settlement in a consent decree before
    a case is filed by, or even referred to, the Department of Justice.  In
    such instances, consent decrees are lodged concurrently with the filing of
    the complaint itself.

-------
                                     4-15


          decision to litigate is influenced by a number of pragmatic
 considerations.  Civil action is generally an expensive activity, both in
 terms of tine and resources; therefore, even a well-documented, clear-cut case
 of responsible party liability may not be worth the expense,  if the issue in
 dispute is relatively insignificant,  resource limitations will also mean that
 cases of potential value as precedents may be given higher priority.

      Goals and Related Policies

      Civil litigation under CERCIA section 106(a)  may serve one or more of the
 following objectives:

           0  To seek and obtain a judicial decision,  or to induce
              responsible parties to sign a consent decree, corrpellinq
              responsible parties to conduct site cleanup;

           0  Ib provide incentives for responsible
              parties in other cases to settle with'EPA;  and

           0  To establish important legal precedents  for ongoing
              and future cases.

    The goals of litigation have remained essentially the  same  throughout the
 history of Superfund, though EPA's ability and willingness to use litigation
 to acccnplish these goals have  changed over time.   EPA policies during  the
 past  1ft months have reflected a willingness to litigate  as a means of
 securing responsible party cleanup or  to establish important legal precedents.

 Major Accomplishments

      A  number of factors have influenced EPA'S efforts to  litigate Superfund cases.
 Preparation of evidence necessary to prove Superfund  cases has  been both
 costly  and time consuming and EPA has  been hesitant to refer cases to the
 Department of Justice without such documentation.   For many cases,  EPA's
 documentation procedures have been insufficient to support prompt referral
 to the  Department of Justice.   A major element of  this documentation is the
 endangerment  assessment of the  site and the technical justification for the
 appropriate remedy.   EPA's positon  is  that  cases cannot  be effectively
 litigated  unless a  remedial  investigation and feasibility  study have been
 performed.  Fund monies  for enforcement-lead  remedial  planning  were  first
 allocated  at  the end of FY83.  Twenty-three remedial  investigations and
 feasibility studies were  initiated  at enforcement-lead sites during  that
 year.   Tn  FY  ft4, 3*>  remedial  investigations and feasibility studies were
 initiated.  For FY 85,  46 remedial  investigations  and  feasibility studies
 are targeted  (35 for NPL sites,  and 11  for non-NPL dioxin  sites).

     Because  remedial investigations and  feasibility studies may  take up  to
 IB months  to  complete,  there will be some  lag time before  the results of
 these actions are reflected in litigation.   Once the studies now  underway
 have been  concluded,  EPA expects the pace  of litigation  activity to
accelerate.

-------
                                     4-16
      The level of civil litigation activity has generally increased  in the
 past two years.  Of the 106 cases referred to the Department of Justice
 over the history of Superfund, 61 (or 58 percent)  were  referred in fiscal
 years 1983 and 1984.  A total of 72 cases have so far been filed  in  Federal
 district court; of these, 48 cases (or 67 percent) have been filed in the
 past two years.  Exhibit 4-6 summarizes civil litigation  activity from FYSl
 through FY84.

                                 EXRHIRIT 4-6

                CERCLA FNPOPCFMENT CASE REFERRALS AND FILINGS3
                                           FISCAL YEAR
                           1979-
                           1981b    1982       1983       1984     Total

 Referrals to noj          24        21          28         33       106

 Filings                   21        3          27         21       72
 a  Referrals are cases that EPA has  sent  to the Department of Justice to be
    considered for legal action.   Pilings  are those referred cases for which
    DOJ has  initiated  formal  legal action.

 b  Cumulative through FY81;  cases prior to  1981 were  initially filed under
    the Resource Conservation and  Recovery Act or the  Clean Water Act, and
    then  amended to include CERCLA authority.

     Source:   OECM Consolidated  Docket Tracking System

     Given  this delay,  coupled with  the fact that case referrals and filings
 have only recently accelerated, the  effectiveness of  EPA's current litiga-
 tion policies should  become more apparent in the next two years.  EPA is
 confident that litigation can be  pursued more vigorously in the future, now
 that pre-litigation policies  and procedures have been better defined.

     Moreover,  a number of judicial  decisions have recently been handed down
 that clarify  important  liability issues left unclear  by the statute.  These
 precedent-setting decisions should allow future litigation to proceed more
 smoothly and may induce potentially  responsible parties to settle cases that
 otherwise may have gone to trial.

     For example,  courts have in several cases upheld FPA's assertion that
 responsible parties are strictly and jointly and severally liable for response
 costs and natural  resource damages,  (see n.R. v. Price (July, 1983), O.S. v.
 Ghent-Dyne (October, 1983), and U.S.  v. A&F Materials  (January, 1984))  These
 issues of strict and  joint and several liability had, until these decisions,
been a major  impediment to productive negotiations and expeditious litigation.

-------
                                    4-17

      In addition to strict and -joint and several liability, EPA's
 interpretation of  the  statute has been upheld on several other key issues.
 (see  e.g., U.S. v. Northeastern Pharmaceutical and Chemical Company  (January
 1984)).  The  courts have also held that the Government need not prove a
 causal link between costs incurred for cleanup and a qiven generator's
 waste,   (see  U.S.  v. Wade (December, 1983) and U.S. v. South Carolina^
 Recycling and Disposal, Inc. (February 1984)).


                     ADMINISTRATIVE ENFORCEMENT ACTIONS

      Section  106(a) of CERCLA authorizes the President, after notice to the
 affected state, to issue "such orders as may be necessary to protect public
 health and welfare and the environment" whenever the President determines that
 "there may be an imminent and substantial endangerment" because of an actual
 or threatened release  of a hazardous substance from a facility.

      Willful  violation, failure, or refusal to comply with an administrative
 order issued pursuant  to section 10fi(a) is punishable by a fine not exceeding
 S5,000 for each day of the violation, failure, or refusal to comply.  In
 addition, recipients of an order that fail, without sufficient cause, to
 provide proper response action pursuant to such an order may be sued by EPA
 under the authority of CERCLA section 107(c)(3) for up to three times the
 costs of response made necessary by such nonccmpliance.  This broad admini-
 strative authority granted by CERCLA section lOfi and the treble damages
 provision of  section 107(c)(3) make administrative orders one of the most
 potent enforcement tools available to EPA under any environmental statute.
      Regional Administrators may issue unilateral administrative orders if the
 following conditions are met:

          0  EPA must  conduct an endangerment assessment to show
             that an imminent and substantial endangerment may exist;

          0  The release or threat of release must meet the CERCLA
             definition of "release" (section 101(22)) and of
             "hazardous substance" (section 101(14));

          0  The release or threat of release must be from a
             "facility" as defined in CERCLA section 101(9); and

          0  EPA must provide prior notice to the affected State or
             States that an administrative order will be issued.

    Administrative orders are usually drafted and issued by the EPA Regional
Offices.  Current policy reguires prior RPA Headguarters concurrence for
consent orders, but not for unilateral orders,  rmilateral orders generally
contain the following provisions:

         0   A statement of the imminent and substantial danger
             pursuant to CERCLA section 106;

         0   For removal actions, a statement of the risk of harm
             under section 300.65 of the National Oil and Hazardous
             Substances Contingency Plan;

-------
                                     4-1R
          0   A statement explaining the liability of: the recipient
             under CERCLA  section  107 and  the  steps that must be
             taken to comply with  the order;

          0   A mandatory timetable for performing and completing
             the response, including the effective date of the order
             (e.g., 72 hours for removals);

          0   The recipient may contact EPA to  reguest a conference on the
             order.

          0   EPA reserves  the right to take action if site conditions
             dictate such action and that  such action in no way relieves.
             the responsible parties of liability for the costs of such
             action; and

          0   A provision reguiring accurate record-keeping and
             chain-of-custody procedures on the part of the recipient
             and cooperation from  any contractor hired by the
             recipient to perform  site work.

     If the recipients agree to implement  the  order, the On-scene Coordinator
oversees compliance.  In some cases, RPA and the potentially responsible
parities may agree to redraft a unilateral order and sign it as a consent
order.  If the  recipient does not  agree to implement the order, EPA may,
in a remedial case, go to court to enforce the order or perform a Fund-
financed response  and seek treble  damages  during cost recovery, if appro-
priate.  For immediate removals, current policy provides for Fund-financed
response in the event of non-compliance.

Goals and Pelated  Policies

     Initial policy de-emphasized  the use  of unilateral administrative orders.
However, EPA issued guidance in September, 1983, urging Regional staff to
consider the use of administrative orders  "in  every case where compelling
enforcement authority is necessary."!5  This guidance establishes specific
criteria for Regional staff to consider in deciding whether to issue an
administrative  order.  Regional staff should issue administrative orders
if potentially responsible parties are likely to comply with the order, or
if EPA has a strong case for enforcing the order or for successfully suing
responsible parties for treble damages if the parties fail without sufficient
cause to comply with the order.
15  "Guidance Memorandum on the Use and Issuance of Administrative
    Orders under Section 106{a) of CERCLA" (September », 1983).

-------
                                     4-19
      Additional  quidance  issued  in  February 19R4 further specifies the
 criteria and procedures for issuincr unilateral  administrative orders  in
 immediate removal  actions.  16 The  outdance memorandum emphasized that
 one of EPA's primary enforcement qoals  is  to increase the  use of administra-
 tive orders  for  immediate removals:  "Orders are particularly useful in
 immediate removal  situations, since they can be issued guickly, can require
 discrete segments  of work (e.g., surface cleanup) and carry the threat of
 additional damages and penalties in the event on non-compliance." EPA
 estimates that administrative orders may be appropriate for a "significant
 percentage"  of immediate  removal situations.

      After identifying responsible  parties  and  notifying them of their
 potential liabilities, reqional  enforcement staff may consider issuinq a
 unilateral order if there is  at  least a week before site work must begin, to
 allow the recipients of the order to confer with RPA on the terms of  the
 order.   In addition,  unilateral  orders  for  removal actions are generally
 issued only  if the number of  potential  hired by the recipient to perform
 site work.

      To speed up the issuance of administrative orders, EPA has redelegated
 the  reguired concurrence  authority.  Initially, Regional Administrators
 were required to confer with  the Assistant  Administrator for Legal and
 Enforcement  Counsel and receive  concurrence from the Assistant .administrator
 for  Solid Waste  and Emergency Response  before issuing an administrative
 order.   Delegations of authority approved in April 1984, however, allow
 Reqional Administrators to  authorize the issuance of unilateral administra-
 tive  orders  in removal actions without prior  concurrence from FPA headguarters,
 Consent administrative orders still  reguire advance concurrence fron  the
 Assistant Administrator for Solid Waste and Bnergency Response before
 signing.

 Major Accomplishments

      Since EPA issued the September  19P3 guidance memorandum, the use of
 administrative orders  has risen sharply.  In  FY8<1, regions issued
 R5 unilateral orders  under  CERCLA section 106.  in FY83, 27 unilateral
orders were  issued.

      EPA has particularly stepped up the issuance of unilateral orders for
removal actions.   Exhibit 4-7 shows  the number of unilateral orders issued for
 remedial and removal  actions  during  FYR1 and  FY82 and during each guarter of
 FY83 and FY84.  As  the data indicate, a dramatic increase in the use  of
unilateral orders  for removals occurred  in  the  second guarter of FY84,
corresponding to policy changes  in the September and February guidance
documents.
    gee "Issuance of Administrative Orders for Immediate Pemoval Actions,"
    supra note 5.

-------
                                     4-20
     Of  the 26  unilateral administrative orders  issued before FY84,
 responsible parties did  not  comply with eight.   In FY84, potential
 responsible parties have not complied with 32 of the 85 unilateral orders
 issued,  making  a  Fund-financed  response necessary in each case.  Twenty-five
 of  these 32 cases have involved non-compliance with an order for a removal
 action.  In some  of these recent cases, EPA did  not expect the responsible
 parties  to  comply with an order; EPA nonetheless issued the unilateral
 orders so that  precedent-setting treble damage suits might be initiated.


                              EXHIBIT 4-7

                  UNILATERAL  ADMINISTRATIVE ORDERS

                  FDR REMEDIAL AND REMOVAL ACTIONS
Fiscal Year            1981     1982          1983                 1984
       Quarter                         I   II   III   IV      I   II   III IV

    Remedial Actions    0       3      0044      3    10   64
    Removal Actions     0       0      0063      4   23   16  10
    Remedial/Removal    0_       1^      !    £     1    2_      1    _!•>   _JL   1
        Actions

        TOTAL           0       4      1    0    12    9      8   38   24  15
    Source: Enforcement Case -Management System, Office of Solid Waste and
            Emergency Response
                              COST RECOVERY 17

    EPA currently defines cost recoveries to include all payments or reim-
bursements to the Fund by responsible parties.  A cost recovery therefore
includes both payments by responsible parties to the Fund to conduct a
cleanup response before the work is undertaken, as well as collections from
responsible parties for Fund monies already expended.

    There are three elements to cost recovery efforts:

          °  Documentation.  In addition to documenting all costs
             incurred in a response action, EPA must demonstrate:
             (a) that a release or threat of release of a hazardous
             substance (as defined in CBRCLA sections 101(22) and
   The 301(a)(l)(D) Study presents a record of EPA's cost-recovery for
   expenditures from the Fund.

-------
                                     4-21
              101(14)  existed;  (b)  the liability of  the defendant  for
              the release or threat of release;  and  (c) the  Federal
              or State response actions taken were not inconsistent
              with the National Contingency Plan.

           °  Issuance of a Demand  Letter.  EPA  routinely  issues a
              letter to parties liable for  response  costs  sunroarizing
              the costs incurred and demanding payment for those costs.

           0  Settlement with Responsible Parties.   Responsible parties
              may seek to negotiate a settlement with the  EPA for  cost
              recovery or, failing  that, EPA  refers  the case to the
              Department of Justice for filing and subsequent litigation.
              Negotiated settlements of filed cases  are embodied in a
              consent  decree.

Goals  and  Related Policies

     The objective of cost-recovery efforts  has remained  the same since the
passage  of CERCLA:  To documentand recover the  maximum practicable amount
of money due  to the Fund from  responsible  parties.  EPA's May 1982 enforcement
guidelines stated:

           When  decision is made to employ  the Fund  for site
           cleanup,  every effort will  be made. .  . to recover
           the Government funds expended, including  referral
           to  the  Department of Justice for collection action
           where necessary.18

     Although not an  explicit  policy,  cost-recovery efforts during the
initial years of  the  program were  considered part of negotiations for a
remedy.  Cost-recovery agreements,  if pursued,  were generally embodied as
one part of broader settlement agreements or consent decrees.

     Cost-recovery  efforts  have only  in the  last year received EPA's priority
attention.  The major reason for this delay  is  that initial program policies
resulted in a slow  rate of  expenditure of Fund monies for non-emergency
releases.   Rather than seeking cost-recovery  for each segment of  a Fund-
financed response,  EPA in most instances chose  to wait until the  response
was entirely or substantially  complete before contacting responsible parties
about cost recovery.   Because  remedial actions generally require as many as
three to four years to complete, EPA has only recently begun to initiate
cost-recovery action  for the first Superfund-financed remedial actions.
Fund-financed removal  actions  druing  the initial years of the Superfund
program were generally limited to  emergency actions that required
relatively low expenditures from the Fund, so cost-recovery was not
emphasized.
18  49 FR 20666.

-------
                                     4-22
      In 1983,  revised EPA policies  increased  the  level of  Fund-financed
 removal and remedial activity.   Under the Site Classification System,
 necrotiations at certain remedial sites (Category  III) are  conducted under
 strict time limits.   If a settlement is not reached, remedial desiqn and
 construction are conducted using Rind monies  and  enforcement efforts shift
 to cost recovery.  In addition,  increased removal activity placed growing
 demands on the Fund  and provided greater impetus  to cost recovery efforts.

      EPA policy encourages responsible parties to negotiate a settlement
 for cost recovery to avoid costly litigation.   In such cases, agency
 neootiation and settlement policy applies.

 Major Accomplishments

      Funds Recovered;  As of September 1984,  the  Fund has  been reimbursed
 whollyor in part for CERCLA costs  incurred in 33 cases for a total of
 $6,fi41,196.  During  FY81,  EPA recovered response  costs at  one site for
 $30,000.  In FY82, EPA made three cost recovery collections for a total of
 $2,409,688.  During  FY83,  EPA recovered response  costs in  13 cases for a
 total of $2,155,133.  During F¥R4,  EPA took 16 cost recovery actions for
 a  total of $2,046,375.

      Documentation;  During the second half  of  FY83, EPA formed a cost
 recovery task group  to  establish more thorough documentation procedures and
 to manage the  rapidly increasing number of  removal cases for which cost
 recovery could be sought.   In August 1983,  EPA issued guidance on cost
 recovery that describes:

           0  Essential  elements  that the government may be called
             upon to  prove  in a  cost recovery  action;

           0  Hie assembly and maintenance of a file;

           0  Examples of appropriate documentation for each element
             of  the  cause of action;

           0  Procedures for processing and negotiating cost
             recovery claims; and

           0  The mechanics of repayment  of any recovery to the
             Flind. 19
In addition to this document, EPA is currently developing more detailed
guidance on cost documentation procedures.
   "Cost Recovery Actions Under the Comprehensive Environmental Response,
    Compensation, and Liability Act of 1980 (CEFCLA)", Office of Solid
    Waste and Emergency Response and Office of Enforcement and Compliance
    Monitoring, August 26, 1983.

-------
                                     4-23


      EPA is currently focusino its efforts on assembling and packaqinq  the
 necessary documentation for a priority list of sites made up mostly of
 completed removal actions.  This process has involved workinq with  reqions
 to identify priority sites, acquiring necessary supportinq documentation,
 and assembling and totalling site-specific costs.

      Although this work has improved the management of cost recovery actions,
 some gaps remain in the quality of EPA's documentation process.   The task
 group has focused only on direct Fund expenditures.  Recovery of indirect
 (e.g., administrative, oversight, overhead) costs  is more difficult and
 will take additional time.  EPA'S financial management office is currently
 working on a system for tracking and documenting indirect costs.

      Damand Letters; EPA routinely issues demand letters on cost recovery
 actions.  There has been, one case to date,  where responsible parties have
 agreed to reimburse the Fund after receipt of a demand letter.

      Cost Recovery Litigation;  As indicated,  EPA  has successfully  recovered
 CERCLA funds from responsible parties in 33 cases  for a total of $6,641,196.
 A significant number of additional cases are either currently in litigation
 or are being developed for future litigation.   The Department of Justice
 (DOJ)  has filed 77 CEPCLA section 107 cases with an approximate  value of
 $117,688,300.  EPA has additionally referred 26 cases to DOJ which  have
 not yet been filed.  The approximate value  of  these cases is $13,006,300.
 Finally, EPA is in the process of developing 19 additional section  107
 actions.  The approximate value of these cases is  $7,049,200.  in total,
 there are 155 section 107 actions pending with a total of $144,384,996.
                    NATURAL RESOURCE DAMAGE ENFORCEMENT

     CEPCLA section 107(a) makes certain  responsible parties  liable for

        damages for injury to, destruction of, or loss of natural
        resources,  including  the reasonable costs of assessing such
        injury, destruction,  or loss resulting from ... a release.

EPA's ability to  use  this provision of the Act is limited because EPA does
not gualify as a  "trustee" for natural resources,  rmder Executive Order
12316, President  Reagan delegated his authority as trustee under CEPCLA to the
Secretaries of Defense, the Interior, Commerce, and Agriculture for resources
under their statutorily mandated protection.  In addition, State governments
have an independent Federal cause of action under CERCLA for  resources within
the State or belonging to, managed by, controlled by, or appertaining to such
State, and  therefore also constitute trustees of natural resources under
CERCLA.

     Despite the  fact that EPA is not a designated trustee for natural
resources,  potentially responsible parties negotiating with EPA over Superfund
cleanups have at  times requested releases from liability for  natural resource
damages.  Because it is not a trustee, EPA is not authorized  to grant such
releases and so must confer in those instances with the appropriate

-------
                                     4-24
 trustee(s).  This section describes EPA's efforts to facilitate  settlements by
 resolving natural resource damaae liability issues while upholding CFPCLA's
 objectives.

      EPA also has potential enforcement authority for natural resource damages
 under the claims provisions of CEJRCLA section 112.   rmder section  112,
 trustees may present claims against the Fund for costs incurred  in restoring,
 replacing, rehabilitating, or acquiring the eguivalent of natural  resources
 damaged by releases of hazardous substances (including assessment  costs).
 EPA, as Fund manager, may subseguently pursue enforcement actions  against
 potentially responsible parties to recover Fund monies paid out  as a result of
 the claim.  This authority has not been used,  however, because no  claims have
 yet been paid out of the Fund.20

      F,PA has only recently encountered the need to resolve natural resource
 damage liability issues to facilitate settlements with responsible parties
 at Ruperfund sites.  In September 1983, EPA entered into a Memorandum
 of Understanding with the Department of the Interior to provide  for prelimi-
 nary surveys of Superfund enforcement sites.   Under the memorandum, EPA
 may reguest that the Department of the Interior perform a preliminary survey
 at any site to determine whether there may be a potential cause  of action
 for damages to natural resources for which the Department is  a trustee.
 lt»e Department then reports its findings to EPA and indicates whether a
 release from liability may be incorporated into any settlements  with poten-
 tially responsible parties regarding the site,   These preliminary  surveys
 do not assess the damages to natural resources.   Rather,  they identify
 whether potential damages may exist that may not be restored  as  a  result
 of response actions.

 Goals and Related Policies

      The goal of the  activity described above is to facilitate settlements
 without compromising  the  intent  of CERCLA to ensure protection of  the
 environment.   Initially,  EPA developed no formal policy regarding  natural
 resources  liability,  primarily because  no claims had been filed.   As
 trustees,  (especially States)  began to seek damages for injury to  natural
 resources, potentially responsible  parties increasingly reguested  releases
 from liability as part of settlements with EPA.   This development  prompted F.PA
 to develop the Memorandum  of Understanding with  the Department of  the
 Interior.  Current EPA plans call  for a preliminary natural resource damage
 survey to  be done at  every enforcement-lead Superfund site.
    20 EPA is currently developing regulations to implement CERCLA section
112.  EPA's claims policy reguires potential claimants  to receive
pre-authorization for any response action for which a third party plans to
present a claim against the Fund (see section 300.25(d) of the National Oil
and Hazardous Substances Contingency Plan).  In December 1983, EPA received 57
claims fron four states for natural resource damages totalling $2.7 billion.
EPA returned the claims because they did not meet filing reguirements.  In
response to EPA's action, the state of New Jersey filed suit against EPA and
the Department of the Interior in April 1984, seeking promulgation of natural
resource damage assessment and claims regulations.

-------
                                     4-25
 Major Acccmplishments

      Since EPA entered into the Memorandum of Understanding, the Agency has
 provided the Cepartnent of Interior with a list of 6? sites  (as of September
 1984} in order of priority.  The Department has conducted preliminary
 surveys at 58 of these sites  but, because  findings are confidential,
 no conclusions can be drawn about the number of sites for which a release
 from liability has facilitated  settlement.

      EPA has not yet pursued similar  arrangements with other Federal trustees
 (e.g./ Defense, Commerce,  Agriculture).21
                             CRIMINAL ENFORCEMENT
      EPA's criminal enforcement  program  began  two years ago.  It is constrained
 by limited resources that must be applied to all of the environmental statutes
 which EPA administers.

      CRPCLA imposes criminal  sanctions only for failure to comply with
 notification requirements under  section  103, a relatively minor infraction in
 comparison to  criminal provisions of other environmental statutes.  Generally,
 any criminal case  involving a violation  of CERCLA will also involve a
 violation of the Resource Conservation and Recovery act because this statute
 has felony violations, whereas violations of CERCLA section 103 are
 misdemeanors.

      The  primary authority of EPA's criminal enforcement program at Ruperfund
 sites arises from  sections 300.8(d) and (e) of the Resource Conservation and
 Recovery  Act.  Section 3008(d) subjects  to fines and/or imprisonment any
 person who:

      0  Knowingly  treats, stores, or disposes of any hazardous
        waste without having, or in violation of, a permit
        under  the  Resource Conservation  and Recovery Act or
        under the  Marine Protection, Research, and Sanctuaries
        Act, or knowingly transports hazardous waste to such a
        facility;  or

      0  Knowingly  makes a false  statement or knowingly alters,
        destroys,  or conceals records on any document reguired
        by the Resource Conservation and Recovery Act.

 Section 3008(e) of the Jtesource Conservation and Recovery Act establishes
even  stronger criminal penalties for any person who knowingly endangers
another person and manifests an unjustified and inexcusable disregard for,
or an extreme indifference to, human life as a result of:
    21 The National Oceanic and Atmospheric Administration is the only
federal trustee thus far to pursue natural resource damages at a Superfund
site (New Bedford Harbor).

-------
                                     4-26
      0  Knowingly transporting wastes to an  unpermitted facility?

      0  Knowlingly operating a facility without,  or in violation
         of, a permit;

      0  Withholding reouired information in a permit application; or

      0  Failure to comply with applicable interim status regulations
         and standards.

      In addition to these criminal provisions under the Resource Conservation
 and Recovery Act, EPA has sought criminal penalties for violators of CERCLA's
 notification requirements.  Section 103(a)  reguires persons  that have
 knowledge of a release of a hazardous substance egualing or  exceeding the
 reportable quantity for that substance to report  such a release  to  the
 National Response Center.  Violators of section 103(a)  are subject  to a
 fine of $10,000 or impriosonment for one year, or both.  Similar penalties
 may be sought against persons who failed within 180 days of  CERCLA's passage
 to notify EPA of certain treatment, storage,  or disposal facilities which
 they owned or operated at the time of disposal, or to which  they transported
 hazardous substances.

      In certain circumstances, criminal penalties may also be sought in
 Superfund cases for violation of Title Ifi of  the  U.S.  Code.  Department of
 Justice attorneys in charge of an existing  case may add Title 1R counts for
 actions including,  but not limited to:

      0  Submitting  fase statements to the Federal Government;

      0  Mail Fraud;

      0  Obstruction of justice;

      0  Defrauding  the U.S.  Government; or

      0  Conspiracy.

      EPA's efforts  in a criminal enforcement  case begin when EPA receives
 allegations that  a criminal provision of  the  law  has been violated.  These
 allegations may be  submitted  by  citizens  or local law enforcement or fire
 officials,  or  by  EPA staff involved with  the  site for other  reasons.

      The allegations are forwarded to the criminal investigative staff at
 EPA's National Enforcement investigations Center  in Denver.  Staff at the
 Center review  the allegations and determine whetehr they warranted opening
 an investigation.   If an  investigation is not warranted, the case may be
 referred to the FPA  Headguarters for  civil  or administrative action  or it
may be set  aside  indefinitely.   If  an investigation is  warranted, however,
 the case is given a  number and agents may use the full  range of  criminal
 investigative  techniques  (e.g., wire tapping, interviews, search warrants)
 to collect  the evidence needed to prosecute the violator.

-------
                                     4-27

      vfaen the investiqation is  complete  and  the necessary evidence has been
 accumulated,  a final report is  prepared  and  the case is referred  to  the
 Department of Justice for prosecution.   To prosecute a  case, the  Department
 must impanel  and seek an indictment from a Grand Jury.   If an  indictment is
 handed down,  the next major step  in the  process is the  arraignment, where
 defendants enter pleas and bail is set.   Arraiqnment is usually followed
 by entering pre-trial motions,  through which the defense ray attempt to
 have the case dismissed.   Barring such an occurence,  a  jury trial follows.

      Pursuant to the Speedy Trial Act, trials must be held .within 70 days of an
 indictment.  Continuances or delays requested by the defense may  be, and
 usually are,  granted, however.

      In criminal trials,  the jury decision must be unanimous for  conviction.
 Moreover, a higher  burden of proof rests on  the prosecution in a  criminal case
 than in a civil  case.  For civil  actions, the prosecution roust prove only that
 "the preponderance  of evidence" establishes  the liability of the defendant.
 In criminal cases,  however,  the prosecution  must prove  the guilt  of  the
 defendant "beyond any reasonable  doubt."  Thus, EPA must be sure  it has a
 solid case before it initiates  a  criminal action.

 Goals and Related Policies

      The goals of EPA's criminal  enforcement program are:

           0  To  investigate,  prepare, and follow through to
              prosecution,  criminal enforcement of environmental laws;

           0  To  convict violators and thereby deter potential
              future violations; and

           0  To  provide a criminal enforcement perspective to EPA's
              development of policy and guidance.

      Because  the resources available to  the  criminal  enforcement  program are so
 limited,  EPA  has  consistently pursued a policy emphasizing investigation and
 referral  of only the most severe  violations  of environmental law.  In
 determining the  severity of a violation,  the two significant criteria are:
 (a)  the extent of environmental contamination or human  health hazard resulting
 from, or  threatened  by, the prohibited conduct; and  (b) the real or potential
 impact of the violation on EPA's  regulatory  functions.

      EPA  guidance 22 specifies that the determination of health or environmental
 threat should rely on considerations such as:

           0   The  duration of  the conduct;

           0   The toxicity of  the  pollutants  involved;

           0   The  proximity of population centers;
    22 "Criminal Enforcement Priorities for the Environmental Protection
Agency," Memorandum from Robert Perry, Associate Administrator for Legal and
Enforcement Counsel to Regional Counsels (October 12, 19ft2).

-------
                                     4-28
           0  The quality of the receiving land,  air,  or water;

           0  The amount of Federal,  State, or local cleanup
              expenditures? and

           0  Public sentiment supporting strong  enforcement action
              in response to a specific situation.

 The need for criminal sanctions should also be considered when  the prohibited
 conduct may have caused EPA to make  a  regulatory decision that  could have
 serious impacts on health and the environment.

 Major Accomplishments

      Initially, the lack of resources  allocated  to the  criminal enforcement
 program limited its effectiveness.   Before 1982, EPA  employed only one person
 with experience in criminal investigation and prosecution.   Most of that
 person's time was taken up with administrative duties,   Ihe lack of criminal
 investigative experience in the regions meant that cases referred to EPA
 headquarters often contained insufficient substantiation to meet the
 stringent scienter23 and burden-of-proof  standards reguired for criminal
 conviction.    Oily one criminal conviction was achieved in  1981, for
 Clean Wbter Act violations.

      In October 1982,  however,  EPA hired  23 experienced criminal investigators
 and assigned them to EPA headquarters,  the National Enforcement investigations
 Center in Denver,  and six of the ten EPA  Regions.

      Nevertheless,  EPA priorities, limited  the use of CERCLA criminal sanctions
 and the use of other sanctions  at Superfund sites.  Tn  1982, only one of
 five criminal convictions  included a CERCLA count.

     In FY83,  the number of indictments  including CERCLA counts  increased to
 three,  all of which also included other statutory  counts.   In FY84, CERCLA
 counts have  so far been handed  down  in  two cases.   In one,  the  CERCLA charge
 was dismissed during the trial.   In  the other, the defendant pleaded guilty
 to  the CERCLA and Hazardous  Materials Transportation  Act counts with which
 he  was  charged.   According to the National  Enforcement  investigations
 Center,  one  current case involves only  a  CERCLA count.   The data available
 are insufficient  to determine the number  of CERCLA cases or the number of
 cases pursued under the Resource Conservation and  Recovery  Act  at sites or
 releases at which Superfund  response was  conducted.
    22 "Criminal Enforcement Priorities for the Environmental Protection
Agency," Memorandum from Robert Perry, Associate Administrator for Legal and
Enforcement Counsel to Regional Counsels (October 12, 1982).

    23 "Scienter" refers to the need to show "knowing violation," which is a
requirement for criminal convictions under the Resource Conservation and
Recovery Act, but not for convictions under CERCLA.

-------
                                    4-29
    The criminal enforcement program should continue to increase its activity
in the coming years.  As more resources are devoted to it and investigators
beccFie more familiar with the range of criminal sanctions available, greater
enforcement of criminal provisions under CERCLA and the Resource Conservation
and Recovery Act at Runerfund sites should result.  Moreover, current EPA
plans involve the addition of criminal investigators to cover all ten EPA
regions by the end of FY85.

-------