14010 — 1O/70
  COST OF RECLAMATION /WD MINE DRAINAGE ABATEMENT -
            ELKINS DEMONSTRATION PROJECT
                        By

  Robert B. Scott, Ronald D. Hill & Roger C. Wilmoth
               WATER QUALITY OFFICE
          ENVIRONMENTAL PROTECTION AGENCY
        Robert A. Taft Water Research Center
              Cincinnati, Ohio  45226
This paper is a revision of the one presented at the
Society of Mining Engineers Meeting, St. Louis, Missouri,
        October 21-23, 1970. (Paper 70-AG-349)

-------
            Cost of Reclamation and Mine Drainage Abatement -
                      Blkins Demonstration Project
                                 by
            Robert B. Scott, Ronald D. Hill & Roger C. Wilmoth
      Acid mine drainage, discharging from coal beds, has polluted our

streams and rivers since early time.  These pollutants affect water

quality by lowering the pH, reducing natural alkalinity, increasing

total hardness, and adding undesirable amounts of iron, manganese, al-

uminum and sulfates.  The tangible damages are the costs involved in

replacing equipment corroded by the acid water, additional treatment

costs at municipal and industrial water treatment plants, and damages

resulting from corrosion of steel culverts, bridge piers, locks, boat

hulls, steel barges, pumps, and condensers.  Intangible damages, which

are real and important, include destruction of biological life of the

stream, reduced property values, and streams rendered undesirable for

recreational uses.

      The major problems of mine drainage occur in the anthracite and

bituminous coal regions in Appalachia.  However, many of the western

mining states have significant mine drainage problems in specific areas,

but the overall problem is not as great as in the eastern states.

      Pollution studies in Appalachia have revealed that inactive under-

ground mines contribute 52 percent of the acid, active underground mines

19 percent, inactive surface mines 11 percent, and active surface mines

1 percent.  Most of the remaining sources are in combination surface-
                  2
underground mines.

      A conclusive report on acid mine drainage was issued by the Com-

mittee of Public Works of the U. S. House of Representatives in 1962.

-------
The report pointed out the extent of the problem and stated that elim-


ination of this form of pollution would restore vast quantities of


water for municipal and industrial use, propagation of fish, aquatic


life, wildlife, and recreational purposes.  Previously, methods to


abate acid mine drainage had been abandoned because of high costs and


technical failure.  The committee concluded that mine sealing was the

                      3
most promising method.


      The report recommended:  (1) a sealing program directed at seal-


ing abandoned mine shafts and other drainage openings, (2) stepped-up


research programs by federal, state, and interstate organizations to


develop other abatement measures, and  (3) a stream and acid flow regu-


lation program employed where sealing or other methods are unable to


sufficiently reduce the acid content of the stream to meet water quality


requirements for all legitimate purposes.  Funds for a demonstration


program were authorized by Congress in 1964.


      In March 1964 the first demonstration project site was selected


in the Roaring Creek-Grassy Run watersheds near Elk ins, West Virginia.


The project was a cooperative effort between federal agencies and the


State of Nest Virginia.  The selected watersheds lie side by side.  One,


Roaring Creek, covers about 28 square miles and the other, Grassy Run,


about 4 square miles.  Both drain into the Tygart Valley River in the

                                        4
Upper Monongahela and Ohio River Basins.


      The site is roughly a rectangular area at elevations from 1,850


feet at the mouth of Grassy Run to 3,660 feet on the southeast rim of


the Roaring Creek Watershed.  The topography is hilly and rough.

-------
          The area contains a large, pillared drift mine  (3,OOO acres,

Kittanning seam), and a number of smaller underground nines  (Figure

1).  The outcrop had been extensively surfaced mined and  contained

over 1,000 acres of disturbed land.  The surface nines intercepted

the underground mine workings of the large mine and diverted water

into it.  Since the coal dipped from the Roaring Creek watershed tow-

ard the Grassy Run watershed, water was diverted from one watershed

to the other through the underground mine, resulting in a flushout of

pollutants.

          Roaring Creek and Grassy Run were discharging over 12 tons

per day of acid into the Tygart River.  Chemical characteristics of

the two streams are presented in Table 1.
                           Table I
                Water Quality Characteristicsa

P^
Acidity, (Hot), CaCO3
Iron, Total
Iron, Ferrous
Sulfate
Hardness, CaCO^
Calcium, CaCQ^
Aluminum
Specific Conductance
Flowd
Grassy
mg/1
2.55
656.
110
4
992
446
293
38
1,723
6
Run
Tons/day
^
10.6
1.8
O.O6
16.0
7.2
4.7
0.6
_
-
Roaring
mg/1
3.3
110
5
1
168
99
76
12
530
40
Creek
Tons/day
„
1.8
0.08
0.01
2.7
1.6
1.2
0.2

-
a. Average values for period March 1965 to June 1966
b. Unit not mg/1, median value
c. Units  - Micromhos per cm
d. Units  - Cubic feet per second

-------
   Demonstration  Project
               No. I

Randolph County, Wett  Vlrglnlo

                1^2
              ^asss
               SCALE
FIGURE  1
                                     LEGEND
                          •    SUBWATCRSHED
                          C   ' Core drilling sit*

                          /\\   Psmnaneal streamgoq* R quality monitor

                          /\    Temporary ttrcomgag*

                                Stream quality sampling point

                                Strlpmln* ditturbonc*

                                Mtn* «r,Unnr»

-------
          Work on the demonstration project was carried out in  three




phases:  (1) site selection, preconstruction evaluation, and reclama-




tion planning, (2) construction of mine seals and regrading and re-




vegetation of surface mines, and (3) project evaluation.  Phase 1,




begun in March 1964 and completed in July 1966, was devoted to water




quality surveillance (FWQA); stream gaging (USGS); surface mapping,




investigation of mine conditions, and designing control measures and




reclamation planning (USBM); securing land permits (W. Va.); and a-




warding the construction contract (FWQA, USBM).  Sealing of the mines




and concurrent reclamation measures (Phase 2) were begun in July 1966




and terminated in September 1967.  Disturbed areas were revegetated




in the spring of 1968.  Phase 3, evaluation of the effectiveness of




mine sealing and reclamation measures, is continuing.






Control Measures




          During the period of Phase 1, control measures were planned



as follows:




          1. Air sealing of the underground mine was to be accomplished




by filling all boreholes, subsidence holes, and other passages into the




mine.  "Wet" mine seals, which allow water to leave the mine,  but pre-




vent air from entering, were to be constructed at all openings dis-




charging water.  Air sealing should prevent oxygen from entering the



mine, which would stop the oxidation of pyrite in the mine and reduce




the production of iron and acidity.




          2. Water is the transport media for carrying acid and iron




from the mining environment.  Therefore, water diversion would reduce

-------
the amount of water passing through a source or  underground mine,



thus reducing the amount of pollution.  This was to be accomplished



by filling subsidence holes, rechannelling streams to establish



drainage away from the mines, and constructing solid "dry"  seals in



portals through which water could not pass.



          3. Acid producing spoils and refuse were to be  buried when-



ever possible in surface mine pits to eliminate  a major contributor



to pollution.



          4. Surface mine reclamation was to be  performed by re-



grading strip mine areas to establish drainage away from  the mining



area and reduce the time the water would be in contact with acid pro-



ducing material.  During regrading, attempts were made to bury the



highly acid material.



          5. All disturbed areas were revegetated to prevent erosion



and stabilize the backfills.



          Both ^et" and "dry" seals were constructed from  two courses



of flyash blocks and coated with urethane -foam on both sides to pro-



tect the blocks from acid attack.  The mine opening was timbered on



both sides of the seal to keep the weight of the roof off the seal.



Dry seals consisted of one wall, while the wet seals had  two or three



walls.  For the wet seals, one wall was solid except that two blocks



were removed from the bottom, the outer wall was approximately 5 feet



from the seal, and 2% feet high.  Only two seals had an inner -wall



which was 12 feet from the seal and 2% feet high. The latter two walls

-------
formed a pool which prevented air from entering  the mine.  Clay seals




were used in areas where the highwall was badly  fractured  and  deep




mine workings lay behind the wall.  For  this  type of  seal, clay was




compacted against the highwall to a height well  above the  underground



mine workings.




       Three types of backfills were used on  the surface mines  —-




contour, pasture, and swallow-tail.  For a contour backfill, the




spoil was graded back as close as possible to the original contour




of the land.  Usually the top of the highwall was pushed down  to com-




plete the backfill.  in constructing the pasture backfill, the  spoil




was graded to form a small slope away from the highwall and the Mgh-




wall was left standing.  The pasture type backfill was used when the




highwall was sound.  The swallow-tail backfill was similar to the




pasture backfill except that a waterway was constructed parallel to




the highwall.  The waterway was located away from the highwall  and




final cut which allowed the water to drain over  the outer slope at




specified low points on the backfill,  when possible, soil low  in




acidity was hauled in and placed on top of the backfill to establish




revegetation and reduce acid production.  Most of the subsidence holes




within 100 feet of the highwall were filled with soil during the back-




filling operation.



       The project was not completed as originally planned as no




reclamation took place in the Grassy Run watershed and north of




Coalton, West Virginia, in the Roaring Creek watershed (Figure  1).




Practically all the work was performed on the south half (up dip side) of




the major mine (3,000 acres) and dealt primarily with water diversion,

-------
                                 8
surface reclamation and air sealing.  This change in plans meant

that the major mine would not be air sealed.  However, a small is-

olated mine had been sealed and would be available for evaluation.

Thus, any inprovement in water quality would occur only in the south

portion of the Roaring Creek watershed and would give the effective-

ness of water diversion and surface mine reclamation and the effect-

iveness of air sealing and water diversion on a smaller mine.  Results

of reclamation on the project with respect to water quality have been

reported previously. ' ' * '

          A summary of the work perforated is presented in Table II.
                            Table II
                   Reclamation Work Performed
   Reclamation

   Surface Mines Reclaimed
   Backfill, Total
   Subsidence Holes Filled
   Mine Seals
   Grass Planted Only
   Grass Hydroseeded Only
   Trees Planted Only
   Hydroseeded Grass & Trees Planted
   Grass and Trees Planted
12.5 Miles
 3.6 Million Cu. Yds.
450
101
322  Acres
 16  Acres
 57  Acres
195  Acres
120  Acres
Cost Analysis Procedures

          The reclamation pontract was entered into on June 3O, 1966,

at an estimated cost of $1,640,382.  This contract did not include

revegetation nor  the filling of subsidence holes beyond 100 feet from

-------
the highwall.  Due to the many unknown conditions existing in  the



heavily mined-out areas, the contract was a cost plus fixed fee



type.




       It was apparent in late summer of 1967 that the entire pro-



ject would exceed the original estimates, therefore a modified plan



was adopted to restrict the first stage of work to the south portion



of the mine.



       Daily records of labor and equipment were kept by the con-



tractor for work performed on each work area in the project.  At-



tached is Exhibit 1 which shows cost analyses breakdown for (A)



Clearing and Grubbing, (B) Reclamation Operation, and (C) Underground



Operation.  These data were later transferred onto computer cards and



a computer program developed to obtain the desired cost breakdown.






Indirect Costs



       Indirect costs included everything not directly applied to



the work areas, such as office work, supplies, etc., and were dis-



tributed to the various work areas on a cost basis.  For example, if



ten percent of the direct costs were charged to Area 2, then ten per-



cent of the indirect costs would also be charged to that area.






Cubic Yards and Acres
       Approximately 650 acres of surface mine were reclaimed dur-




ing the reclamation contract.




       Aerial photographs were taken of the project area during the




planning stage and were used to develop contour maps showing the




finished grade, acreage, and cubic yards of earthen material to be

-------
                              10
                           Exhibit 1
                 Cost Analyses Breakdown Codes
A. CLEARING & GRUBBING
 1. Cutting & Clearing
 2. Grubbing & Clearing
 3. Cutting Landowners Timber
 4. Handling Landowners Timber
 5. Chipping & Hauling
 6. Fire Detail
 7. Root Rake Hauling

B. RECLAMATION OPERATION
 1. Cleaning Pit
 2. Cleaning Face of High wall
 3. Scraping SL from Soilbank
 4. Backfilling a. pasture  b.
 5. Ccapaction
 6. Subsidence  a. drilling & shooting
                b. hauling material
                c. dozing   d. shovel
 7. Moving Equipment to Area
 8. Drainage, Structure Grading
 9. Grading Work Sites
10. Drainage Grading
11. Down Time
12. Reporting Time
13. Maintenance
14. Grading Roads
15. Cleanup of Garbage
16. Ditching
17. Borrow Pit
18. Carbonaceous Material
          8. Access Road Grading
          9. Cleaning Pits & Pit
              Mouth Entry
         10. Drainage Grading
         11. Down Time
         12. Reporting Time
         13. Routine Maintenance
    contour  c. swallowing
a.
b,
c.
hauling
burying
dozing
C. UNDER GROUND OPERATION
 1. Cleaning & Temporary Timbering
 2. Removal Temp. Timber & Erecting Perm. Timber
 3. Concrete Footer Seal Location
 4. Provide hitches in roof & ribs at seal location
 5. Erect Seal
 6. Coat seal inbye side with bitumastic
 7. Seal perimeter with Ur ethane Foam
 8. Install rigid plastic tubing
 9. Pumping Operation
1O. Ventilation
11. Down Time
12. Reporting Time
13. Routine Maintenance
14. Hauling material & supplies to work sites
15. Dismantling & assembling equipment
16* Drilling, blasting, etc.

-------
                               11
moved for specified types of backfill on  the work areas.  Upon com-

pletion of the contract, a land survey was made of each work area

to determine the total acreage and cubic  yards of material moved.

       Accuracy of the backfilling quantities is somewhat limited

because of the necessity of moving backfill material  two or three

times in an attempt to separate the toxic spoil from  the non-toxic

fill material and burying it in the strip pit.


Revege tati on

       A contract in the amount of $205,911 was awarded to the

Tygarts Valley Soil Conservation District on a cost reimbursable

basis in September 1967 to revegetate the reclaimed work areas on

the project.  In the spring of 1968 approximately 71O* acres of

land distrubed during reclamation were revegetated.   Soil samples

were taken and analyzed as a guide to the fertilizer  and lime require-

ments and for choosing the best type of vegetation.   The District com-

pleted the revegetation of the project in one growing season instead

of two as originally planned, reducing the contract cost for revege-

tation to $177,727.

       The contractor was required to make a cost analysis at the

completion of the contract, therefore accurate and complete records

were kept on all phases of work as it progressed.  Actual labor and

equipment hours expended each day were recorded by work areas.  In

addition, a daily record was kept of all  lime and fertilizer applied

and all grass seed and tree seedlings plan ted in each  work area.  This

  Increased revegetation acreage due to revegetation of certain disturbed
  areas which did not require prior reclamation.

-------
                               12
was further broken down as to method of application, for example,
truck spreading or box spreading of fertilizer and conventional
method or hydroseeding of grass seed.  In addition, a record was
kept of the species of grass seed and tree seedlings planted in each
work area.
       Each month a summary was made of all data compiled during that
month and a cumulative total made of labor and equipment hours and
material applied to each work area.  Foremen's time and overhead costs
were distributed to the different work areas on a basis of direct
labor hours worked in each area during the month.  Vehicle rental
distribution was based on actual hours equipment was used on each
work area during the month.

-------
                                 13




                         DISCUSSION & RESULTS








        Cost of surface mine reclamation,  mine sealing, and revege-




 tation is presented in various ways in this report for purposes




 of estimating cost of future reclamation work.  An average overall




 cost, including both direct and indirect charges, is calculated for




 surface reclamation and mine sealing.  Dataafr« presented in Tables




 III - IX.  Since direct cost (labor,  equipment useage, and material)




 will vary on different reclamation projects depending on the condition




 and location of unreclaimed area, certain work areas on the project




 with a variety of working conditions and different types of backfill




 and seals, were selected for a special study.  Data from this study




are presented in Tables X and XI.  All data from the selected work




 areas will be designated (SWA).




        Costs on these selected areas are shown two ways:  (1) without




 clearing and grubbing to give cost of reclaiming recently mined, un-




 revegetated areas which would require no clearing and grubbing prior




 to reclamation and which would reclaim the land to satisfy most exist-




 ing state mine laws, and (2) including clearing and grubbing to give a




 cost picture of reclaiming old abandoned strip mine areas which are




 overgrown with vegetation and would require clearing and grubbing




 prior to reclamation.



        Since equipment rental was a main item of expense (40 percent




 of the total cost) on the reclamation work, equipment costs were ana-




 lyzed to determine the best and most economical equipment utilization




 for each type of work.

-------
                               14
Equipment Summary




       During the period of the reclamation contract, twenty-six




pieces of equipment were leased by the contractor on a monthly basis




to perform the reclamation work on the project.  The lessor was to be




notified by letter thirty days prior to terminating the lease on any




of the equipment.




       Table III lists the equipment that was utilized during recla-




mation and shows the work hours, cost per hour, and range of cost




per hour for each particular type of unit used.




       Range of cost varied considerably for the D-9 dozers due to




the necessity for keeping certain dozers on rental during periods of




adverse weather.  For example, the dozer which showed the highest cost




per hour ($79.86) was on rental during four winter months and, because




of bad weather, was utilized only 144 hours during the rental period.




If this equipment had not been kept on rental, the lessor would have




moved it from the project making it unavailable for spring operation.




       The LeRoi air corapressor was rented for one month but after




only sixteen hours of use, it was found to be insufficient for the job;




therefore the average cost was extremely high at $10O.OO per hour.




       The 977 traxcavators were used as a combination hi-lift to ex-



plore the strip pits for buried deep mine openings and as a root rake




to clear areas prior to backfilling.  Utilizing this equipment during




the winter months was difficult which resulted in considerable vari-




ation in the cost per hour as shown on Table III.




      The Koehring shovel was operated at an average cost per hour of




$24.21 and was used for stream channeling and establishing drainage from

-------
           15
        Table III

   RECLAMATION PROJECT
     Cost Breakdown

Summary of Equipment Time
Type Equipment
6OO Motor Grader
TD-25 Dozer
D-7 Dozer
D-8 Dozer
D-9 Dozer
Koehring Shovel
Compac tor
977 Traxcavator
DW-21 Pan
Scraper Pan
John Deere Crawler
Air Tract Carrier &
Attachments
Compressor
105 LeRoi Air Compressor
Totals
No. of
PCS.
1
2
1
2
6
1
1
3
2
2
1
1
2
1
26
Work
Hours
481
2,678
2,492
2,851
10,859
951
560
5,615
3,818
1,048
1,892
396
2,294
16
35,951
Total
Cost
$ 10,385
29,636
28,259
28,358
237,360
23,024
16,100
63,315
55,883
25,195
4,162
10,363
17,478
1,600
$551,118
Avg. Cost
Per Hour
$21.59
11.06
11.34
9.94
21.86
24.21
28.75
11.27
14.64
24.04
2.20
26.17
7.61
100.00
Range in Cost
Per Hour
0
$ 7.47 - $17.14
0
8.50 - 1O.31
12.63 - 79.86
0
0
7.71 - 16.97
14.30 - 14.99
11.81 - 30.55
0
0
6.27 - 8.94
0

-------
                                16
work areas.  In February 1967 the shovel was damaged by a highwall



fall and was down for repairs for the remainder of the project.



       The scraper pans were used mostly in work areas requiring



compacted backfill and thus had limited use.



       The grader was used exclusively to maintain haulage roads



to and from the work areas at an average cost of $21.59 per hour.



The compressor, air tract, and crawler were used mostly for under-



ground work pertaining to masonry seals.






Clearing and Grubbing



       The first work actually performed on the project was the



clearing of certain areas which were covered with volunteer trees



and other vegetation established over the 25 years since stripping.



This was done  to prepare the land for the backfilling and sealing




operations and was designated as Clearing and Grubbing.



       The following work was performed during this operation:



       1. All  trees with a diameter less than four inches, measuring



12 inches from the ground, were uprooted, cut, and burned.



       2. All  trees with a diameter greater than four inches were



cut, trimmed to saw log lengths, and stockpiled at a convenient lo-



cation for the property owner.



       3. All  stumps and brush were uprooted and burned.



       4. Boulders and rocks large enough to impede revegetation were



buried in  the  spoil near the outer slope.



       Average overall cost for clearing and grubbing was $330/acre



or  16.6 percent of the total cost for surface mine reclamation  (excluding

-------
                               17
revegetation).  An average of 32 labor hours/acre was required  to


clear and grub (Table IV).  These costs were higher  than originally


estimated, partially due to the dense forest in some areas and  the


extra handling to cut pulpwood for the landowners.  Average direct


cost (SWA) varied considerably with respect to type of backfill per-


formed on the work areas.  For example (see Table X), the average


cost/acre for clearing and grubbing prior to contour backfilling on


Areas 27, 2P, and 44 was quite high and ranged from $127/acre to


$367/acre.  High costs were incurred in areas containing a fractured


highwall.  A portion of the highwall was unsafe and had to be cleared


so it could be pulled down.  Also the material was needed for fill.


Generally, low costs were noticed in pasture and swallowtail backfill


operations and in stripped areas where toxic spoil had prevented


dense foilage and where it was not necessary to disturb vegetation


on the highwall.




Surface Mine Reclamation
       The average cost for surface mine reclamation was $l,658/acre.


Cost of moving earth was $0.35/cubic yard (Table V).  These costs arc


higher than those reported by the U. S. Bureau of Mines for surface

                                                       (6)
mine reclamation at Moraine State Park in Pennsylvania.     In their


report, the cost/acre for two areas was $780 and $1,402.  The average


earth moving cost was $0.16/cubic yard.  Labor hours (39/acre) were


the same for both projects.


       The average direct cost  (SWA) for surface mine reclamation varied


from a low of $472/acre on contour backfill to a high of $l,130/acrc


for a combination of pasture-contour backfill (Table X).

-------
                               18
       Average direct cost  (SWA) per acre for pasture backfill




reclamation was higher than contour backfill costs, an unexpected




result.  Further studies showed that, in general, the spoil was




more highly toxic in the pasture backfill areas than in the contour




areas.  Because of its toxic nature, the spoil had to be moved




several times, thus increasing the cost.




       Swallowtail backfill, because of additional earth work, was




slightly more costly than pasture backfill.




       High costs for all phases of reclamation for a combination




of pasture and contour are due to complex problems that existed in




the work areas including the six conditions given below:




       1. Unknown interrelated conditions between the strip and under-




ground mines which made it necessary to spend considerable time open-




ing up the pit to locate fractures and openings into the underground




mine.



       2. The contractor was required to separate the toxic spoil




from  the nontoxic backfill material where feasible and bury the toxic




material in the strip pit.  This required moving the material two or




three  times in some areas.  As a result, the amount of earthen mater-




ial actuall}' moved greatly exceeded the 3,060,000 cubic yards deter-




mined  from before and after cross sections.



       3. Approximately 17 percent of the total backfill material moved




was used for excavation material to fill subsidence holes on top of




the highwall and as clay compacted material for seals.




       4. It was necessary  in many work areas to establish drainage by




rechanneling streams from strip mines prior to reclamation.

-------
                               19


       5. Adverse weather conditions during the winter months hampered

the reclamation work on the project and necessitated payment of rent

on equipment which could not be utilized.

       6. The highwall, in many instances, was fractured to the extent

that it could not be left standing.  In such cases, the wall was pullec'

down and the material used to complete the backfill.

                             Table IV
            Clearing and Grubbing Costs for 651 Acres

Direct Labor, Total
Direct Labo ', Average/Acre
Equipment, ~otal
Equipmen t , .We rage/ Ac re
Direct Cost, Total
Indirect Cost, Total
Total Cost
Average Cost Per Acre
Cost
$ 72,662
$ 112
$ 38,329
$ 59
$110,991
$103,518
$214,509
$ 330
Hours
21,468
32
3,461
53




                             Table V
           Surface Mine Reclamation Costs for 651 Acres
                  -3,060,000 Cubic Yards Moved -

Direct Labor, Total
Direct Labor, Average/Acre
Equipment, ^otal
Equipment, aver age/Ac re
Direct Cost, Total
Direct Cost, Average/Acre
Direct Cost. Average/Cubic Yard
Indirect Cost, Total
Total Cost
Average Cos". Per Acre
Average Cost Per Cubic Yard
Cost
$ 96,884
$ 149
$ 457,706
$ 703
$ 554,590
$ 852
$ 0.18
$ 524,984
$1,079,574
$ 1,658
$ 0.35
Hours
25,558
39
26,028
40








-------
                               20
Revegetation Costs




       The overall cost for revegetating the reclaimed work areas




is summarized in Table VI.  Average direct cost was  $2OO/acre and




total cost  ?248/acre.




       Cost varied considerably depending on the  type revegetation




work perforned.  Higher rovegetation costs were incurred  (Table  VII)




in steep ar ?as where it was necessary to use a hydroseeder.  This also




increased cost (SWA) in contour backfill areas (Table X).  The more




level areas on which conventional equipment could be used were re-




vegetated a': a much lower cost.






Masonry Sea'.s




       Forty-three dry masonry seals and 12 wet seals were constructed




in the entries to abandoned drift mines at an average cost of $4138/




seal (Table VIII).




       High equipment cost was attributed to the exploration of  the




strip pit tr> locate mine openings and to clearing debris from openings




at the face of the highwall.  Preparation of seal sites, such as timber-




ing and clearing debris from  the seal sites in the mine, was performed




manually.



       The  r.verage direct cost (SWA) for dry seals and -vet seals is




presented on Table XI and shows that wet seals cost  about twice  as much




as dry seals.  Cost of dry seal on Work Area 8 was considerably higher




than cost of other seals due  to high labor cost involved in opening and




timbering the portal prior to constructing seal.

-------
                               21
Clay Seals




       In t reas where the highwall was badly fractured  and  the




stripping operation had intercepted  the deep mine workings,  openings




were sealec" by compacting clay against the openings  and the  highwall




with a vibrating sheeps foot compactor.  Although 41 openings xvere




sealed this way, data were recorded  only for Work Areas 1-9  and  1O.




These data are summarized in Table IX.  The cost/seal in Work Area  10




was higher than in Areas 1-9 due  to  haulage distance from  the borrow




pit to the seal site.






                            Table VI




                 Revegetation Cost for 709 Acres

Direct Labor, Total
Direct Labor, Average/Acre
Equipment, Total
Equipment, Aver age/ Ac re
Material Cost
Hydroseeding Contract Cost
Direct Cos*, Total
Direct Cos'., Average/Acre
Indirect Cost, Total
Total Cost
Total Aver.-.ge Cost/Acre
Cost
$ 31,860
$ 45
$ 17,493
$ 25
$ 45,190
$ 47,475
$142,018
$ 200
$ 3.3,709
$175,727
$ 248
Hours
9 , 5 39
14
4,365
6








-------
                                22
                             Table VII

                   Cost Breakdown of Revegetation'^'
                           DoIlars/Acre
                             Labor   Equipment  Material
                   Indirect
                b   Cost0
         Total

Conventional
Hydroseediny
Trees Only
Hydroseedimi
Conventional
Trees"
d
Grass
Onlye

Plus Trees
Grass Plus


32
19
39
54

68

.65
.23
.51
.47

,53

36
227
4
238

23

.51
,32a
.20
.74a

.29

63
61
18
76

64

.39
.44
.37
.78

.80

32.
71.
21,
84.

37.

07
49
63
93

22

164
37F
84
454

19?

.62
.48
.2]
.92

.84
a. Hydroseeding work was subcontracted for $225 per acre? which included
   mulch at one ton per acre.
b. Includes lime, fertilizer, seed, and trees.  In some "trees only" areas
   no fertilizer and/or lime were used.
c. Indirect cost distributed on basis of direct cost.
d. Fertilizc-r (0.5 ton/acre of 1O-1O-1O) , lime (2-4 tons/acre) applied
   from truck, grass planted by seeder box.
e. Lime (2-4 tons/acre) spread from truck or from farm type fertilizer
   spreader, hydraulic application of grass seed, fertilizer  (0.5 ton/
   acre of JO-1O-1O)
f. Hand plat-tod (OOO-IOOO/acre).
g, Hydros ceding plus hand planted trees (9OO-lOOO/acrf>) ,
h. Conventional grass as in d, plus hand planted trees (90O-lOOO/acre).
                            Table VIII

                     Cost of 55 Masonry Seals
                                          Cost
                     Hours
Direct Labor, Total
Direct Labor, Average/Seal
Equipment, Total
Equipment, Average/Seal
Direct Cost; Total
Direct Cost  Ppr Seal
Indirect Cost, Total
Total Cost
Average Cost Per Seal
$ 65,949
$  1,199
$ 50,729
$    922
$116,678
$  2,121
$110,913
$227,591
$  4,138
17,932
   326
 5,602
   301

-------
                                 23






                            Table IX




                      Clay Compacted  Seals

Work
Area
1-0
3O

No. nf
Se.il-.
10
6
Cu. Yds.
Compacted
Backfill
10,490
1 1 , 670

Total
Cost
$ 9,500
$14,16O

Cost per
Seal
$ 950
$2,360
Avg.
Cu. Yd/
Seal
1,049
1,045

Cost/
Cu. Yd.
$0.91
$1.21
Summary




       An a<:id mine drainage  reclamation  project was established in




the Roaring Creek-Grassy Run  watershed  near Elkins,  We«t Virginia.




During the reclamation, 651 acres  of surface mines were reclaimed,




709 acres rrvegetated,  55 masonry  seals constructed, and 41 clay s




instal1ed.




       The average overall  surface mine reclamation  cost was $2236/acr?




including $ V3O/acre for clearing and grubbing,  $165ft/acre for reclama-




tion, and $'M8/acre for revegetation.   Overall  co?t  for masonry seals




was $4,138  -?ach and clay seals  $1,47°-.




       The liigh costs  were  due  primarily  to unknown  rorditions o^ the




abandoned nrlr>es,  exploration  which was  necessary to  locate the high-




wall  fractures and openings intercepting  the deep mine, and multiple




moving of spoil to bury toxic material .




       Indirect costs  on the  reclamation  contract appear high due to




the inclusion of  vehicle rental and foremen's salaries.  Because of




the data collection system, it  was necessary to include these charges,




normally coisidered direct, in  indirect costs.   A more comprehensive




report, to  'ie published at  a  later date,  will present cost data in




greater detiil.

-------
                               24
       StaHlity cf the reclaimed area has been exceptional as on^y




eight small subsidence holes have occurred since 1967.  Total main-




tenance cc«'S have been less than $?,OOO in the past three years or




less than <",O3 percent per year of the construction coiit.

-------
                                               Table X

                                   Direct Cost of Surface Reclamation
                             by Various Methods on Selected Work Areas (SWA)
                               on Demonstration Project #1, Norton,  W. Va.
Work
Area No.
3
4
5
8
9
37
MEAN
23 & 24
28
27
29 & 3O
44
MEAN
1
2
MEAN
10
11
MEAN
Acres
11
4
4
7
11
13
53
77
11
63
37
26
221
18
40
59
140
47
187
.9
.7
.3
.9
.7
.0
.5
.9
.0
.0
.7
.7
.3
.7
.3
.0
.3
.0
.3
Type of Cost/Acre
Backfill Reclamation
Pasture $
It
tt
if
it
it
$
Con to ur $
It
tt
f
ti
$
Swallowtail $
ti
$
Pasture ?• Contour $1
1
$1

383.
56.
995.
740.
437.
708.
568.
429.
265.
540.
542.
41O.
472.
315.
706.
582.
,06O.
,341.
,131.

Type
Seeding
C
C
C
C
C
C

C
C
C
C
C

C
C

C
r

8, H




ft H

,H, & T
,H, & T
9 YT
,H & T
,11 & T

,H & T
,H & T

, H . & T


Cost/Acre
Reclamation
+ Seeding
$

1



$
$




$
$

$
$1
1
$1

533.
14O.
,126.
840.
5r>^.
012.
582.
669.
612.
907.
744.
684.
754.
546.
815.
730.
Q36
, - j J .
,49R.
,302.

Cost/Aero
Reclamation + Seeding
+ Clearing ?• Grubbinn
$

1
1

1
$
$

1


$
$

$
$1
1
$1

576.
174.
,137.
,035.
55°.
,028.
760.
704.
882.
,275. '^
804.
812.
918.
566.
843.
755.
,435.
,548.
,456.

Type Seeding:  C = Conventional, H = Hydroseeding,  and T = Trees

-------
                   r?6
               Table  XI

               t Compari son
           Seal Construction
Demonstration Project #1,  Norton,  W. Va,
Work Area
No.
2
7
3
14
27
3O
101
24
53
No. of TyPe
Seals S al
.? Di y
3
1
1
12
6
1 We. t
1
1
Direct
Cost
$4,000.
5, 298.
6,376.
1,358.
.?3 , 706 .
14,574.
$5,031 .
4,068.
3,128.
Cost per
Seal Maximum
$2,000. )
1,766. )
6,376. ) $6,376,
1,358. )
1,Q75. )
2,479. )
$5,031. )
4,068. ) $5,O37.
3,128. )
Mi n imum Ave rage


$ 1,358. $2,212.




$3,1?8. $4,076.


-------
                                 27

                             REFEPENCES

1.  Committee of Public  '-'T-ks,  U,  3.  House of representatives,  1962,
    "Acid Mine Oral mot-, "  House Committee Piinr No. 18, 87th Congress,
    Second Session, U. S.  Government  Printing Office,  '.vUshinrj+on,  D.  C.

2.  Stream Pollution  by  Coal Mine  Drainage in Appalachi.i, Federal  V.'alcr
    Pollution Control  Admin i s t ruli on ,  Ci ncinnati ,  Ohi o :  Revi bed  1 06° .

3.  Hill, Re nald D.,  Silting  Minn Drainage Pollution Con "rol Demonstration
    Project, Third Symposium on Coal  Mino Drainage Research, Pittsburgh,
    Pennsyl \ ania:   May  1^7n.   Copies available from Environmental  Pro-
    tection Agency,  Cincinnati,  Ohio 45226.

4.  Porges, Ralph.  Lowell  A  Van ncn Berg, and Dwigh^ G, Bal linger,  Re-
    Assessirg an Old Probl cm- -Aci d Mine Drainage, Journal of  the Sanitary
    Engin^ei Ing Division,  Proc^ed-f nn<; of the '\me~nVan Society of Civil
    Engineers, Vol.  Q2 ,  Sa 1, February 1066.

S.  Bui lard  W. H.,  Acid Minr- Drainage Pollution Control Demonstration
    Program U'ses of Experimental Watershed?;, International Association
    of Scientific Hydrology,  Symposium of Budapest, Extract of  Publi-
    cation ! of 66,  Budapest,  Hungary:  1Q65.

6.  McNay, !-ewis M. ,  Surface  Mine Reclamation , Moraine 3tn to  Park, Penr-
    sylvani a, Burea-j of  Minos Tnfnrmation Circular 8^S6, U.  S.  Department
    of the "nterior,  Pittsburgh, Pennsylvania.  1Q7O,

7<.  Hill, Ronald D.,  Reclamation and Rovegctation of 64O Acres  of  Surface
    Mines - Elk ins,  '.'.'cst Virginia.  Proceedings International Symposium
    on Ecol'igy and  ^evenetati on  of Drastically Distvirbrd Areas, Pennsyl-
    vania State Hniversity,  August 1960 (to be releasee 1971).  Copies
    availab e from  Environmental Protection Agency, Cincinnati, Ohio 45226.
                             ACKXOK'LnnGEMFiNTS

This proj^r "i  was  -\  cooperative effort between the Federal Water Quality
Administration  (FWQA*),  the State of West Virginia, am'  the following
Poderal  \geicies:   TJ.  S,  Bureau of Mine^ (USBM) , U. S. Geological  Survey
(USGS) ,  and  rh
-------