UNITED STATES ENVIRONMENTAL PROTECTION AGENCY

      '                      WASHiNGTON. D.C.  20460
                                                             Jl'i
                                            program Guidance Memorandum
                                            PG-53

Subject:  Interim Guidance - Consulting Engineering Agreements -
          Title II Construction Grant Program

From:     Alvin L. Aim, Assistant-Administrator  /
          for Planj^jag.and Management (PM-208)  '

          Jafrjes''W'?ffgVe1^^Tstant Administrator
          for Water and Hazardous Materials (WH-556)

To:       Regional Administrators

     Proposed subagreement regulations published in the Federal  Register
on May 9, 1975, included provisions applicable to consulting engineering
agreements under EPA construction grants (principally proposed 40 CFR
35.937 through 35.937-11, at 40 F.R. 20303 through 20305).  A notice was
published in the June 9, 1975 Federal Register to extend the comment
period upon these regulations to July 15, 1975.

     It is anticipated that final regulations concerning the subject
of the May 9, 1975 proposed regulations will be published in
September 1975, with an effective date somewhat later.  After promulga-
tion but prior to the effective date, a series of regional workshops
will be held.  The purpose of these workshops will  be to insure that
EPA personnel, consulting engineers, state and municipal personnel and
others will fully understand and properly apply the final subagreement
regulations and to assure minimum disruption to the program.

     The purpose of this memorandum is to define EPA policy and procedures
concerning consulting engineering subagreements in the interim until  	
final subagreement regulations become effective.  Program Guidance
Memorandum No. 42 dated October 23, 1974, and all other prior memos,
letters and guidance concerning this subject matter are superseded by
this memorandum.

-------
                         A,  ACCESS TO RECORDS


     (1)  Existing EPA regulations require applicants/grantees  and
their contractors including consulting engineers,  to maintain,  and
insure EPA access to, records pertinent to project performance.   See  40
CFR I 35.935-7 of the February 11, 1974, final Title II construction  grant
regulations and 40 CFR § I 30.605 and 30.805 of the final  EPA general  grant
regulations published at 40 F.R. 20242 and 20245 on May 8, 1975.

     This access to records requirement is applicable (subject  to the
policy and procedures set forth in Sec. B, below)  to all  Title  II
construction grants, but action need not be taken  to insert the
access to records clause in consulting engineering agreements under
Title II grants awarded prior to July 1, 1975.

     (2)  After June 30, 1975 a construction grant will not be  awarded
nor will initiation of Step 1 work be approved pursuant to 40 CFR
1 35.917(e) or 35.925-18(a)(3), unless an acceptable access clause as
follows is included in the consulting engineering  subagreement.   This
requirement also pertains to Step 2 and Step 3 grant awards.  This
requirement also pertains to completed Step 1 or Step 2 work not  covered
by a grant award, if payment therefor is requested as a part of a
Step 3 grant award.  Submission of consulting engineering subagreements
is required pursuant to 40 CFR § 35.920-3(a)(2) and 35.920-3{b)(7).

     The following clause is the acceptable access to records
clause for insertion in all consulting engineering subagreements  in
excess of $10,000:

          "1.  The (Contractor/Consulting Engineer) shall  maintain
     books, records, documents and other evidence  directly pertinent
     to performance on EPA grant work under this agreement in accordance
     with accepted professional practice, appropriate accounting  procedures
     and practices, and 40 CFR § § 30.605, 30.805, and 35.935-7.   The
     United States Environmental Protection Agency, the Comptroller
     General of the United States, the United States Department of Labor,
     (the grantee-owner), and (the state water pollution control  agency) or
     any of their duly authorized representatives  shall have access"to
     such books, records, documents and other evidence for the  purpose of
     inspection, audit and copying.  The (Contractor/Consulting Engineer)
     will provide proper facilities for such access and inspection.

           2.  The (Contractor/Consulting Engineer) agrees to include in
     all his contracts and all tier subcontracts directly related to
     project performance which are in excess of $10,000 the five  items
     of this clause.

-------
           3.  Audits conducted pursuant to this provision shall  be
     in accordance with generally accepted auditing standards and formally
     established audit regulations, procedures and guidelines of  the
     reviewing or audit agency(ies).

           4.  The (Contractor/Consulting Engineer) agrees to the
     disclosure of all information and reports resulting from access
     to records pursuant to paragraphs 1 and 2, above, to any of  the
     agencies referred to in paragraph 1, above.  In those cases  where
     the audit concerns the (contractor/consulting engineer), the auditing
     •agency will afford the (contractor/consulting engineer) an opportunity
     for an audit exit conference, and an opportunity to comment  on the
     pertinent portions of the draft audit report.  The (contractor/
     consulting engineer) will be provided copies of the formal draft
     audit report at the time of its transmission.  Such transmission
     will include the written comments, if any, of the audited firm.

           5.  Records under paragraphs 1 and 2 above shall  be maintained
     and made available during performance on EPA grant work under this
     agreement and until three years from date of final EPA grant payment
     for the project.  In addition, those records which relate to any "Dispute"
     appeal under an EPA grant agreement, or litigation, or the settlement
     of claims arising out of such performance, or costs or items to which
     an audit exception has been taken, shall be maintained and made available
     until  three years after the date of resolution of such appeal,
     litigation, claim or exception".
     An alternate clause may be approved only if it has been found  acceptable
by the Regional Counsel.
     (3)  Exception for  Step 3 Grant Awards.   If amendment of an  existing
consulting engineering agreement is not feasible prior to the'award of a
Step 3 grant, but amendment is assured in writing by a letter from the
consulting engineer, grant award may be made prior to such amendment.
In such .case, the grant agreement must include the following special
condition:

          "This grant is awarded subject to compliance, within 90  	
     days after the grant award or such additional  extension of tinie~
     as may be allowed in writing by the EPA Project Officer, with the
     access to records requirements of 40 CFR  30.605, 30.805, and
     35.935-7, in reliance upon the written assurance dated (     }
     by (consulting engineer or firm).   Consulting engineering work
     performed under an agreement which does not include an acceptable
     access to records clause will  be ineligible.  Accordingly, grant
     payments will not be made for consulting  engineering work until
     the agreement under which such work has been or is being performed
     includes an acceptable access to records  clause."

-------
     This exception should be utilized chiefly as an interim measure
to avoid unnecessary disruption of Step 3 grant awards for applications
presently filed in the EPA Regional Office.

              B.  EXERCISE OF RIGHT OF ACCESS TO RECORDS

     (1)  EPA has a broad right of access to the grantees' consulting engineers'
records pertinent to performance of EPA project work.  The extent
to which EPA will exercise this right of access will depend upon
the nature of the records and upon the type of agreement.  In referring
to these records, it is important to bear in mind the following three
categories of records —

          Category A:  records pertaining directly to the professional,
                       technical and other services performed, excluding
                       any type of financial records of the consulting
                       engineer.

          Category B:  Financial records of the consulting engineer pertaining
                       to the direct costs of professional, technical and
                       other services performed, excluding financial records
                       pertaining to profit and overhead or other indirect costs,

          Category C:  Financial records of the consulting engineer excluded
                       from Category B.

     (2)  In all cases, EPA will exercise its right of access to Category A
records.  Also, where there is an indication that fraud, gross abuse,
or corrupt practices may be involved, EPA will exercise its right of
access to records in all categories.  Access to consulting engineers'
financial records (Category B and C)  will depend principally upon the
method(s) of compensation stipulated in the agreement:

          (a)  Agreements Based Upon a Percentage of Construction Cost.
Category B and C records will not be audited.  However, terms of the
agreement including the total amount of compensation will be evaluated
for fairness and reasonableness and consistency with historical and
advisory guidelines in general use and acceptable locally such as ASCE
Manual 45 or other analyses or data relied upon or utilized by the
contracting parties in negotiation of the agreement.  Such evaluation
shall  also consider comparable contracts for which EPA grants have been
awarded.  Payment under a contract based upon a percentage of construction
cost must be based upon the consulting engineer's construction cost estimate
provided at the time of completion of plans and specs plus a reasonable
compensation for updating plans and specs, revising cost estimate, or
similar services.  Where the low bid for construction is higher than
this estimate, payment for consulting engineering services may not be
increased, except for those services performed in the interim between
completion of plans and specs or award of the grant, and receipt of
the engineer's estimate, over and above those services contemplated
in the original  consulting engineering agreement.

-------
          (b)  AgreementsBased Upon SalaryCostTimes a Multiplier,
Including Profit.  Category B records wi11 be audited^Category C  records
will not be audited.  However, terms of the agreement, including the
multiplier, will be evaluated in accordance with appropriate portions  of
paragraph 8(2)(a) above.  Items of overhead or other indirect costs will  only
be audited to the extent necessary to assure that types of costs found.
both in overhead and reimbursable direct costs, if any, are prdperly
charged.

          (c)  Per Diem Agreements.  Category B records will be audited.
Category C records will not be audited.  Audit will be performed to
the extent necessary to determine that hours claimed and classes
of personnel used were properly supported.  The per diem rates
will be evaluated in accordance with appropriate portions of (2){a)
and (b) above.

          (d)  Cost Plus a Fixed Fee Payment (Compensation).  All  direct
costs and overhead and other indirect costs claimed will be audited
to determine that they are reasonable, allowable, and properly supported
by the consulting engineer's records.  The amount of fixed fee will not be
questioned unless the total compensation appears unreasonable when
evaluated in accordance with (2)(a) and (b) above.

          (e)  Fixed Lump-Sum Contracts.  Category B and C records
will not be audited.  The contract amount will not be questioned unless
the total compensation appears unreasonable when evaluated in accordance
with appropriate portions of (2)(a) and (b) above.

     (3)  Under agreements covering both grant-eligible and ineligible
work, access to records will be exercised to the extent necessary to allocate
contract, work or costs between work grant-eligible for Title II construction
grant assistance and work or costs which are ineligible.

     (4)  Under agreements utilizing two or more methods of compensation,
each part of the agreement will be separately audited in accordance with
the appropriate subparagraph of (2) above.

     (5)  Any audited firm and the grantee will be afforded opportunity
for an audit exit conference and an opportunity to comment upon the
pertinent portions of the draft audit report.  The audited firm and the
grantee will also be provided copies-of the formal draft audit report
at the time of its transmission.  Such transmission will include the
written comments, if any, of the audited firms and the grantee in addition
to those of the appropriate state and/or Federal agency(ies).

-------
                    C.  TRANSITION:  CONTRACT TYPE

     (1)  The percentage of construction cost type of contract,  and the
multiplier contract, where profit is included in the multiplier, may
not be utilized for Step 1 or Step 2 work initiated after July  1, 1975,
when the Step 1 or Step 2 grant is awarded subsequent to June 30, 1975.

     (2)  Step 1 and Step 2 work performed under the percentage  of
construction cost type of contract and the multiplier contract,  where
profit is included in the multiplier, will be reimbursed and such
contracts will not be questioned where such costs are reimbursed in
conjunction with a Step 3 grant award where Step 2 work has been initiated
prior to July 1, 1975 and the Step 3 grant is awarded before July 1, 1976.

     (3)  Where Step 2 work is initiated after July 1, 1975, under
contracts described in (1) and (2) .above, EPA approval may not  be given  or
grant assistance awarded until the -terms of compensation under  the contract
have been renegotiated.  It is recommended that the terms of compensation
under the contract be renegotiated as a lump-sum agreement where
the extent of work to be performed is reasonably ascertainable,  (or as a
cost plus fixed fee payment type agreement where the extent of  work to be
performed is not reasonably ascertainable).

     (4)  Establishing an "upset" figure (an upper limit which  cannot
be exceeded without a formal amendment to the agreement) under  a
multiplier contract, where profit is included in the multiplier, is
not acceptable where renegotiation. of such contracts is required. In
such renegotiation, the amount of profit must be specifically identified.

     (5)  Per diem agreements should be utilized only to a limited
extent, such as where the first task under a Step 1 grant involves
establishing the scope and cost of succeeding Step 1 tasks, for Step 3
services during construction, or for incidental services.

     (6)  Appendix A to this memorandum contains examples to serve as
guidance in the application of the foregoing requirements.

                      D.  COST OR PRICE ANALYSIS

     (1)  EPA requirements concerning cost or price analysis are
contained in 40 CFR § 30.725.  Guidance is being prepared concerning
such formal analysis for consulting engineering agreements.  Until
such guidance has been distributed, no such formal analysis should
be undertaken.

     (2)  Until guidance has been distributed, the total contract
amount under any form of contract may be questioned in accordance with
     (3)  On all consulting engineering contracts in excess of $100,000
a certification may be required (see Appendix B).

-------
                              E.  PAYMENT

     Full and prompt payment should be made by EPA and by grantees
for eligible costs as work is completed under consulting engineering
contracts in accordance with 40 CFR § 35.945 (second sentence).
Grantees or their contractors should not withhold payment for professional
services unless it is determined that the professional service contractor
has failed to comply with contract objectives, terms, conditions, or
reporting requirements.  Any withholding should be limited to only
that amount necessary to assure contract compliance.

                            F.  ENFORCEMENT

     Refusal by a consulting engineer to allow access to its records,
or to renegotiate a consulting engineering contract in accordance
with the foregoing requirements, will render costs incurred under such
contract ineligible.  Accordingly, all such costs will be questioned
and disallowed pending access to records.
cc:  Mr. Stringer, Director of Audit

-------
                               TRANSITION
         CONSULTANT FEE BASED ON PERCENTAGE OF CONSTRUCTION COST
                                   or
           COST MULTIPLIER  (WITH PROFIT AS PART OF MULTIPLIER)
A.  GRANT OFFER MADE AND ACCEPTED
                CASE
                                             EPA POSITION
Case  I
1.  Step  1 Contract only.
2.  Step  1 Work Underway or
      being completed.
3.  Progress or Final Payment
      is Requested.

Case  II
1.  Step  2 Contract only.
2.  Step  1 Complete.
3.  Step  2 Underway or
      being completed.
4.  Progress or Final Payment  is
      Requested on  Step  2.

Case  III
.1.  Combination Step 1, 2, &
      "Supervision" 3 (or 1/2 or
      2/3).
2.  Work  has not yet started on
      2  (or 3).
3.  Anticipate continued payment
      requests.
                                        Pay Requests thru  Compl.  Step  1
Case  IV
1.
2.
3.
Previously Completed Step 2 Work.
Step 2 P&S "Shelved"
Step 2 Reactivated and only add'l
 work by A/E is "updating" P&S etc.
 (to allow Step 3 Grant request or
 bidding) thereby resulting in
 increased Constr. Cost and
 increased  (windfall) A/E
 compensation.
                                        Pay Requests thru Compl.  Step  2
                                        Pay requests for work on Step
                                        currently underway.   Advise
                                        Grantee Fed. share will apply
                                        only to Steps not underway  where
                                        compensation is not  determined
                                        as % of construction cost,  or
                                        cost multiplier.
Pay only compensation as determined
by Constr. Cost estimate at completion
of original work plus a "reasonable"
compensation for "updating" the
plans and specs, etc.
                              Appendix A (1)

-------
B.  GRANT OFFER PENDING -- GRANTEE ALREADY HAS AS>E UNDER CONTRACT WITH
    COMPENSATION BASED ON PERCENTAGE CONSTRUCTION COST OR COST MULTIPLIER
                CASE
            EPA POSITION
Ca.se I
1.  No work started on Step 1,
     or 2.
2.  Grant Request Made
No grant until Grantee/Consultant
 renegotiate Contract with compensation
 based on other than % Constr. Cost,
 or Cost Multiplier.
Case II
1.  Work Started (or Compl.)
     on Step 1

Case III
1.  Work Started (or Compl.)
     on Step 2

Case IV
1.  Combination Step 1 and 2
     (or 1, 2 & 3, etc.).
Award grant, continue current
 contract and pay that basis.
Same as B. II above.
Same as A. Ill above.
                             Appendix A  (2)

-------
CONTRACT PRICIMG PROPOSAL - EPA Grant Subagreement
EPA Grant Number: -«,.o. j ,,o.o, ,.*,.,*
*r»Mr Ol Ol * 1 MO*«


»ut'p|_iC » *.Ni>'on M.W v*c t* TO AC rvi«Ni*nto
,o,.,A-ov.ro,,.o,o», Step(S)
DETAIL DESCRIPTION OP COST ELEMENTS
>. DI'RECT MAT t BIAI.
.. pi,nCM.trnr-»..T>.

C. OTMI II .

ror/L r>!RKCr MATERIAL
2, U*T 1 Ml AL OVtRHt'AOJ «?»(» 1, A }&•••-)
3. DIRTCT LABOR (5t~tl!r)

f
/
£
jf\
* \
rorx^ DiKrcr L*KOK \
4. LARO1I OVtP.h£AO (Sptftly tfrr*r'n«nf or cofef ttgrrt)
j
/ I
\^f
TOTAL LA(i?S^i»l'rf:IICxn
nouns HOUR






;.::.•:::::::::;:::::"::::::::::•::::::••

O.H. RATC X BASE s



:•:.:•::::;::::•:.:. :::.|::::-;u::::::
s.»»rc»At partners bunng Kate:fHartnership Unly^
.... ..-^ 	 	
\ /^
EST COJTW




":::-i»=ll:!:;!»:;-
EST
COST (1)






::r:::::::::::::.::::.
tST COST (1)




EST Cp&T f»


S*. V TOTAL fPl.CIAt. TES77WC r::::::::::::::-:-::::
*. SPfCIAl. rOUIPMCHT (Hd,,«l cWir.A \
7. TRAVIL (11 rfl.rcl .h.rf.J I 1 i
.. ».M,r.nT.i.»N < //
t. fC« OIIU OH tUBtllTCHCi: ^f"^
«. COHSULTAIITS f/dcnHI)- . r/£0, . -~\.I,J
/ !
4 /
X /
\/
. ror^L covsvi.rA.vTj
EST COST f*>


CST COST (*>





». OTHI'll dinliCT COSTS
w. TOTAL ntKi:cT co.tr AND offKiiFA.fi
II. CCHLItAL A«D ACIUINlSTHATIVE rX"CNSC (Ktlt 1* fl tuft rlrmrnl Nu-
ll. noyAi.Tirs
»• ror>tt cir/HATco cosr
u. ret on pnot'iT
i». Torxt rsriiuTii>cosTjurnrKr.onrHorir
TOTAL
£*T COST'






::::;;::!::;;::•:;::


;::::::iii:iv::i::

F:i:::i;;i;i:;;;::;



:::;:::::•:.•. :..


=:•=::=!:!!!;•••••:



:::::•••::::•;;•:••




':::::::'::'::'::•:•!
i;:::f.::':-ji.—


	 * 	 •










HLLdQIiimt
teference







































(Attach certification of current cost or pricing data)

M«.N*w»i (Contractor)
*•*'"• or '""* o»»ec» io»Mi»«on
i.trnricate of Kevit-w (Grantoo)

-------
                CERTIFICATE  OF  CURRENT  COST OR  PRICING DATA****
      This is to certify that,  to  the  best of my  knowledge and belief,
 cost or pricing data as defined in  (                            ) submitted,
 either actually or by specific identification in writing to the
 Contracting Officer of the Grantee  or his representative in support of
 	* are accurate, complete, and
 current as of	**.
                 day         month        year
                                      Firm_

                                      Name
                                      Title
                          ***
 Date of Execution
   *Describe the proposal,  quotation,  request for price  adjustment or
      other submission involved,  giving appropriate  identifying  number
      (e.g., RFP No.	).
  **This date shall  be the  date when the price negotiations were
      concluded and  the contract  price was  agreed to.  The respon-
      sibility of the contractor  is  not limited by the personal
      knowledge of the contractor's  negotiator if the contractor
      had information reasonably  available  at the time of agreement,
      showing that the negotiated price is  not based on  accurate,
      complete, and  current data.
 ***This date should  be as  close  as  practicable to the date when the
      price negotiations were concluded and the contract price was
      agreed to.
****The contractor acknowledges the  certification data is available
      for EPA audit  verification  where such verification is deemed
      appropriate.                       ^   „-•''
                                 Appendix B (2)

-------
                                       FY  1904 OWOGAS
                           CONSTRUCTION GRANTS ACTIVITIES  4,  6-9  BACKUP
                                    COMPLCTIOriS/CLOSEOUTS
Step 1 Physical Completions and
Terminations

      Completions
      Terminations

Step 2 Physical Cortpletions and
Terminations

      Ccrrpletions
      Terminations

Step 3, Step 2+3, PL 84-660,
Physical Completions, and
Terminations
      Cctnpletions
      Terminations

Adrdnistrative Corpletions
fStep 3, Step 2+3 and PL 84-660}

  -Will not be sent to DIG
     (TN N8 coded NS)

  -Awaiting Completion of Another
    Segncnt of phase  (TN N8 coded AP)

  =Stcp 3, Step 2+3 and  PL 84-660
    Audit Requests

  +Stcp 1 and/or Step 2  Audit Requests
    over $250,000

  •f Step 1 and or Step 2  Audit Requests
    under $250,000

  =Total Final Audit Requests

Project Closcouts  (Stop  3, Step 2+3
  iind PL 84-660)
1st 2nd 3rd 4-ch
Quarter Quarter Quarter Quejrter
af 40 tro bo
(A<} ( W ) ( 5* ) ( 5* )
( C ) ( /••))( 6 ) ( JL )
V // ^o a 7
( ^) ( // ) ( /? ) ( .^^}
( 0 ) ( r/ ) ( / ) ( o2 )
J? o ^
( / -? ) ( -3c% ) ( -Jj--) ( -?') )
( a 3s' qt
( 0 ) ( o ) ( / } ( / )
?! of Active"
Projects at
Beginning c:
FY-84
(27 Slvp 1  or r.l..>» ? :.•.•.:•':-. -•• !•• .-.:-.«• :
     ilal.vi c-L.iu -jn. [\';j.
                 '.-*«'

-------
                                      FY 1984 OWOGAS
                           CONSTRUCTION GRAI1TS ACTIVITIES 4, 6-9 BACKUP
                                    COMPLUTIOHS/CLOSEOUTS
Step 1 Physical Completions and
Terminations

      Completions *
      Terminations

Step 2 Physical Corrpletions and
Terminations

      Ccnpletions
      Terminations

Step 3, Step 2+3, PL 84-660,
Physical Ccnpletions, and
Terminations
      Conpletions
      Terminations

Administrative Conpletions
 (Step 3, Step 2+3 and PL 84-660)

  -Will not be sent to OIG
     (TN N8 coded NS)

  -Awaiting Completion of Another
    Segmsnt of phase (TN N8 coded AP)

  =Stsp 3, Step 2+3 and PL 84-660
    Audit Requests

  +Step 1 and/or Step 2 Audit Requests
    over $250,000

  +Stcp 1 and or Step 2 Audit Requests
    under $250,000

  =Total Final Audit Requests

 Project Closcouts  (Step 3, Step 2+3
  and PL 84-660)
  1st
Quarter
    6
    7
   3  )
         2nd       3rd
       Quarter   Quarter


         31      31
          ( o  /  )   (  3?  )
          (  O   )   (   •
                                                                           4th
                              {   CD  )
          (  g  )   (  la  )   (   /<   )
          (  o  )   (  o  )   (   o   )
                  23
       )   (  SL )   ( v^  )   (  v.
                 (  IB )   (  /?
                 	)   {  100 )

                  103      122.
IB
        ? of Active
        Projects at
        Spinning o:
        FY-84
                                          (   Z )
                                              **

-------
                                                      1C-6)
                          FY 1984 OWOGAS
         CONSTRUCTION GRANTS ACTIVITY £5 IN ATTACHMENT B
          CONSTRUCTION MANAGEMENT EVALUATION COMMITMENT


Region   V -

                   Full/Extended CHE's*
States                  FY
                            Z-

                            2,
Total (Commitment) ___ ___ f^2L
*  Projection does not  include instructional CME's which are
expected to be performed on virtually all new construction
starts.

** Although the commitment is for the Regional fiscal year total
progress will be monitored quarterly.    State estimates are
requested  as backup  information.

-------
                                                       (C-7)

                           FY  1984  OWOGAS
         CONSTRUCTION  GRANTS  ACTIVITY #11 IN ATTACHMENT B
          DELEGATION OVERVIEW IMPLEMENTATION COMMITMENT
Objective:    Complete  delegation to the States

Activity:     Implement the Agency Policy on Delegation and
              Overview  for  the- Construction Grants Program.


Date Regional Overview  Policy Completed?

              Policy  Title:
Date Regional  Overview Pol.icy Implemented* with the States  (and
the Corps) :

               States                        Date

               1 y.-lTLu/AiP/'S _____    ____ jj '^|£c/ ____

               2.    ~
               3 .   yff ^H.^J _______    ____ LUL/.&/

               4 • -J3lL±±l.Cl£l^t ________    _____ ' J-L5 JW.
               5 . __pHj_q _____________        3  |. IS" 1.83
               7.

               8.
               C o ^P£_o£_§.n gineer s	    	Uj_1L/JLl_
 *"Implomented with the States" is  defined  as:  (1)  delegation
  agreements revised to reflect Policy,  (2)  Regional  delegation
  management procedures revised to  reflect  the  Policy,  and (3)
  overview program developed and  in  opprntion with  tlio  St^te in
  (.yj-?:ti or..  For tin' T-c.-rr1.., "iwpl ••";. »•> <>  v-lif
  i ii;.: :;i" J L \ on ol Co:(:i j^')-i urni,ir,<  i-  i n-.0  t?:^  ovi-r v • Ov/  jM'.-'.j ra::is .

-------
                       FY 1984-1906 Workload Projections
                          Requested From The Regions
                                For Each State
FY
1984
TOTAL
FY
1985
TOTAL
FY
1986
TOTAL
                 Data
Step 1 Terminations.                               	/

Step 1 Completions.

Step 2 Completions.

Step 2+3 Awards.

Step 2+3, Design Portion  Completions.

Step 3 Awards.
Step 2+3 Construction  Portion  Completions.           5"         Q      l&
   *                               *                *•• •iiiin«fc.in«3nf-iii»ii-     ••. •». -•-. »•.• J. *mm   *~* .in	,i|l	,	.„„.

Step 3 Construction  Completions.                  	LjL_     	U—

Adinin. Completions  (Step  3  &  2 + 3).                 £jl~f        ?)~~~f

Final Constr  Audit  Completions(Step 3  & 2 + 3)      	L&2-     	/IZ1

Construction  Project Closeouts  (Step 3 & 2+3)

AT Reviews.
Corp_s_-Spe_£i f i c_Data

On-Site Presence  Corps  Workyears                   Q	     	^._.

Total Di_r_e_c_t  Corps  Workyears                     JS~5L_

Total Corps Expendi tures (jTh^^^^^^J        ^l^tSO

Corps Workyear for  Special  Assignments

                                                             .33..     3.?-

-------
                      FY 1984-193b Workload Projections
                         Requested From The Regions
                               For Each State
                                                          State
                                                          Region
project Workload Data
Step 1 Terminations.
Step 1 Completions.
Step 2 Completions.
Step 2+3 Awards.
Step 2+3, Design Portion Completions.
Step 3 Awards.
Step 2+3 Construction Portion Completions.
Step 3 Construction Completions.
Ad:nin. Completions  (Step 3 & 2+3).
Final Constr Audit  Completions(Step 3 & 2 + 3)
Construction Project Closeouts  (Step 3 5 2+3)
AT  Reviews.
Corns- Speci f_i c  Da^ta^
On-Site  Presence Corps  Workyears
Total  Direct Corps  Workyears
FY
1984
TOTAL
FY
1985
TOTAL
FY
1986
TOTAL
                                                  zo
Total  Corps Expend! tures
Corps  Workyear for Special  Assignments
JL=L.
 /
                                                              9
22.
 /s
                                                                      J

-------
                      FY 1984-1906  Workload Projections
                         Requested  From The Regions
                               For  Each State
Project  Workload Data
Step 1 Terminations.
Step 1 Completions.
Step 2 Completions.
Step 2+3 Awards.
Step 2+3, Design Portion Completions.
Step 3 Awards.
Step 2+3 Construction Portion Completions.
Step 3 Construction  Completions.
Admin. Completions  {Step 3 & 2+3).
Final Constr Audit  Completions(Step 3  & 2+3)
Construction Project Closeouts (Step 3 & 2+3)
AT  Re.views.
Corps-Speci f i c_Da_ta_
On-Site  Presence  Corps  Workyears
Total £ir_e_ct Corps  Workyears
Total Corps Expend i ture s CTKo^-SO-'naS^)
Corps Workyoar for  Special Assignments
FY
1984
TOTAL
'.~33~-
FY
1985
TOTAL
~L<2-
-3£L
_.££_
FY
1986
TOTAL
15"
3&
___L     _JL
  .£_
JL5L
                                                ..SSL
           _3^
           -32.
                      3
15..
                     SO

-------
                                                                 (D-2)
                                                                _
                                                            Region
                       FY 1984-1906 Workload  Projections
                          Requested From The  Regions
                                For Each State
FY
1984
TOTAL
FY
1985
TOTAL
FY
1986
TOTAL
Project Workload Data
Step 1 Terminations.
Step 1 Conpletions.                                QC)
Step 2 Completions.
Step 2+3 Awards.
Step 2+3, Design Portion  Completions.
Step 3 Awards.                                        ~~/      	HZ-
Step 2+3 Construction  Portion  Completions.          /c3.,-     	/uL-   __sL/
Step 3 Construction  Completions.                  	^2T_       J*0
Adsnin. Completions  (Step  3  &  2+3).                __j£Q     --2-Q
Final Constr  Audit  CompletionsfStep 3 & 2+3)     	f/_     	(J_
Construction  Project Closeouts (Step 3 & 2+3)    __L3_     	J?^T_
AT  Reviews.                                         ^3         3
 Corp^-S P_££i_£i.c_p_ a t a
 On-Site  Presence Corps Workyears                 __s2.	
 Total  Direct Corps Workyears                      ^7       tfjTl    <3~~f
       fm_ ^_ tl_ n	_1f__^__    '       •*                          m_ii- ^ji _- - vJ^vl^     LIJ , 11 ff •"	iT~ -m m   •—.M
-------
                      FY  1984-198£i Workload Projections
                         Requested From  The Regions
                              For Each  State
                                                            (D-2)
                D at a
Step  1  Terminations.
Step  1  Completions.
Step  2  Completions.
Step  2-1-3 Awards.
Step  2+3,  Design Portion  Completions.
Step  3  Awards.
Step  2+3 Construction Portion  Completions.
Step  3  Construction  Completions.
Admin.  Completions (Step  3  & 2+3).
Final  Constr  Audit Compl etions( Step 3 & 2+3)
Construction  Project Closeouts (Step 3 & 2+3)
AT Reviews.
Corps-Speci f i c  Data
On-Site Presence Corps Workyears
Total  Di re_c_t  Corps Workyears
Total  Corps Expendi ture ^(T^OU^a^d^)
Corps Workyear  for Special  Assignments
                                               FY
                                              1984
                                              TOTAL
  UL
-30.
	jL
JL.
 FY
1985
TOTAL
_9L
IP.
 J3S.
                    FY
                   1986
                   TOTAL
         . 30
            to
            n
           30
          J3A.
 l^co   fezo

-------
                                                               (0-2)
                                                          m*jofao/g3
                                                          c *.. * ;f~virrv-*—r—^—*—
                                                                YI/X^^^OTT.S/ZZ
                                                          P\egion f~_i\/&.,___  _
                       FY  1984-1986 Workload Projections
                          Requested From The Regions
                                For Each State
                                                 FY        FY        FY
                                                1984      1985      1986
                                                TOTAL     TOTAL     TOTAL
Project W o r ic 1 oaid D a t a
Step 1 Terminations.                            -^"lC3—;_      ~~Q-~~L    ~—Q —
Step 1 Completions.                               ^4 I
Step 2 Completions.
Step 2+3 Awards.
Step 2+3, Design Portion Completions.
Step 3 Awards.
Step 2+3 Construction Portion Completions.
Step 3 Construction Completions.
Admin. Completions  (Step 3 & 2+3).
Final Constr Audit Compl etions ( Step 3 & 2+3)      __/j6__     	/5~_
Construction Project Closeouts (Step 3 & 2+3)     	/_^__     	/..?_
AT  Reviews.                                         /         Q     _ jQ
Corps^Speci fi c_Data
On-Site Presence Corps  Workyears
Total OIL6.0! Corps Workyears
 Total  Corps  Expendi ture^(^TnO(Ji&(3t^\^J           £inQ.     £J2_,   J^Z.2.
 Corps  Workycar  for  Special Assignments
                                                 J53.     .1^7-    1^7-

-------