-------
ACID PICKLING SUBCATEGORY
SECTION V
WATER USE AND WASTE CHARACTERIZATION
Introduction
Process water usage within the steel industry is a major factor in
determining pollutant loads and estimating the cost of wastewater
treatment. The Agency used the data from the sampling inspections and
responses to the DCPs to evaluate process water usage within this
subcategory, and to obtain total wastewater volumes. The Agency
identified, for each line, existing control and treatment technology
and the method of wastewater disposal.
This section characterizes the wastewaters from acid pickling
operations and reviews the actual operation of the pickling process.
The waste characterization is based upon data obtained from two
sampling programs. During the first sampling program, the Agency
investigated the levels of the previously limited pollutants. During
the second program, additional monitoring was conducted for toxic
pollutants. When an operation was visited twice, only the more recent
data were used to characterize wastes from that operation.
Only process wastewaters are considered herein. Noncontact cooling or
nonprocess waters are not limited by the proposed regulation. Process
wastewater is that water which comes into contact with the process,
product, by-product, or raw materials, thus becoming contaminated with
various pollutants characteristic of the process. Noncontact cooling
water is defined as that water which does not directly contact
processes, products, raw materials, or by-products. Nonprocess
cooling water is defined as that water which is used for nonprocess
operations, i.e., utilities and maintenance.
Acid Pickling
As shown in Section III, acid pickling is performed either on a batch
or continuous basis. Wastewaters are discharged from three sources in
the acid pickling process: from the tanks containing the pickle
liquor, from the rinsing step(s) following the pickling tank, and from
the fume scrubber systems if wet scrubbers are used. Each of these
sources is described separately below.
1. Pickle Rinsewater - Batch and Continuous
The first wastewater source is the rinsing operation following
the pickling step. Depending upon whether or not the operation
is batch or continuous, varying amounts of water are used and
discharged. However, regardless of the type of operation, the
rinsewaters constitute higher flows than the other sources and
contribute much of the pollutant load to the treatment system.
225
-------
There can be one or more rinse steps depending upon the pickling
operation. A considerable number of lines include a single tank
in which the product is rinsed after pickling. However, many
lines include multi-step rinsing processes which consist of dip
tanks, spray chambers, or other rinsing components. The exact
arrangement of the rinses depends greatly upon the degree of
rinsing and cooling required.
Rinsewater discharge flows can be minimized with cascade or
countercurrent rinse systems. The water flow to the rinse tanks
is reduced and cascades from one tank to the next. The fresh
water makeup enters the final tank and then discharges from the
first rinse tank. The product to be pickled travels in the
opposite direction to the water flow and thus is rinsed with
successively cleaner water. These systems reduce water flow,
concentrate the pollutants in the last rinsing chamber, and
achieve more thorough rinsing. Although cascade rinsing is
ideally suited to continuous operations, it is also used for
batch operations.
The rinsewater flow and the wastewater characteristics can vary
considerably depending upon such factors as the number of rinsing
steps used and the type of rinsing (i.e., flow-through versus
standing; cascade versus conventional), and other factors. The
Agency considered these variations in developing these proposed
limitations.
Flow data and net concentrations for pollutants found in the
rinsewater at batch and continuous lines surveyed for this study
are summarized in Tables V-l, V-3, V-6, V-8, V-12, and V-15. Net
concentrations are presented to describe the actual levels of
pollutants contributed by acid pickling operations. Averages are
also listed to show a typical level of pollutants found in
discharges from batch and continuous operations.
B. Spent Pickle Liquor
The second source of wastewater in acid pickling operations is
spent pickle liquor (SPL) bath, which contains a pickling
solution composed of acids or various acid mixtures depending on
the type of steel being pickled (i.e., carbon versus specialty),
or, on the type of finish desired. Regardless of the type of
acid used, however, spent pickle liquors are highly contaminated.
The same pickling solution is generally used for several days or
weeks to process large tonnages of steel products. The contents
of the bath are replaced when the acid loses its strength to the
point, where extended pickling times are required or product
quality diminishes.
The quality of the SPL can vary greatly, depending on the age of
the solution. The wastewater characteristics for the sampled SPL
sources are summarized in Tables V-2, V-4, V-7, V-9, V-13, and
V-l6. If no flow data are presented in these tables for a
particular plant, there was no flow from the tanks when the
sampling was conducted. Because spent pickle liquor is highly
226
-------
contaminated and low in volume, contract hauling off-site is a
common disposal method. Lines that do not have SPL hauled,
gradually bleed the liquor into treatment systems for disposal,
or recover or regenerate it.
The solutions in the acid tanks are heated to increase the
chemical action of the pickling solutions. As a result, the
temperatures of the wastes being discharged from the bath can be
as high as 93.3°C (200°F).
C. Fume Scrubber Water
The third potential source of wastewater in the acid pickling
process is the wet fume scrubber. Wet systems are used to
collect and scrub fumes generated in the pickling process. Other
types of fume treatments that do not require water are in use at
several acid pickling operations. An example of this type of
system is the acid demi&ter used at one of the sampled sulfuric
acid pickling operations.
Considerable quantities of pollutants are discharged from the
fume scrubbing system, as the water scrubs the contaminants
carried from the process in the fumes. The concentrations of
pollutants discharged from the scrubbers vary considerably and
depend upon such factors as the amount of fumes generated in the
process, the water usage in the scrubber, and the degree of
recycle. The level of pollutants found at the 12 fume scrubber
systems sampled are summarized in Tables V-5, V-10, and V-14.
As discussed in later sections, the applied flow to the scrubber
system can, however, vary considerably. These flow rates can be
reduced significantly by recycling of the scrubber water. Many
of the lines with recycle systems on fume scrubbers discharge
less than 10 gal/ton. As noted earlier, these blowdowns may be
completely reused as rinsewater makeup at sulfuric and
hydrochloric acid lines.
D. Absorber Vent Scrubber Water
The regeneration mode of treating spent hydrochloric acid
pickling solutions can generate an additional wastewater source.
Wet absorber vent scrubbers are used to collect and scrub fumes
generated by the acid regeneration process. The concentrations
of pollutants discharged from the scrubbers vary considerably and
depend upon such factors as the amount of fumes generated in the
process, the water usage in the scrubber, and the degree of
recycle. Table V-ll summarizes analytical data from absorber
vent scrubbers.
The applied flow to the scrubber systems may vary. However,
these flow rates may be reduced through recycle. Absorber
scrubber recycle systems have demonstrated a discharge of 25
gal/ton. These blowdowns may be reused as rinsewater in
hydrochloric acid lines.
227
-------
tabu: v-i
SWWAHT OF AKALYTICAL UU FROM SMUD FLAHTS
BATCH SULFURIC ACID FICXLIHG
MET RAW RIHSE WASTEWATER - eOHCBHTEATIOH (¦g/1)
Raw Wastewater
Plant Code
Reference do.
Saaple Point*
Flow (gal/toil)
Parameters
090 091
0476A 061Z
C-(*H) F-A
91 122
092
00B8A
F-D-C-A
326
096
01121
D-A
604
I-ZA
0856F
7-6
207
1-2B
0856P
3-6
465
0-2
OS 90
1-2
18.0
R-2
0240B
2-7-6
30.8
S-2
02566
3-4-2
198
I
0240A
11-1
30
Average
164
NJ
tvj
CO
Diaaolved Iron
391
2350
51.7
97
2900
350
3.6
43,000
6500
3500
1850
596
8990
5430
Oil and Grease
22
15
42.8
12
-
4.3
8.4
12
11
0.6
4.5
21
1.3
11.9
Suspended Solids
-
-
361
126
19
70
21
18
749
20
370
159
1.3
147
P«
1.7-2.5
1.8
5.9-6.9
3.2-3.7
1.8
2.4-2.6
2.9-6.4
<1.0
1.3-1.6
1.9
2.0
2.2
1.6
<1.0-6.9
22
Parachl orcweta-
cresol
HD
0.020
HD
HD
HD
HA
HA
HA
HA
HA
HA
HA
HA
0.004
44
Methylene Chloride
HD
m>
0.040
HD
HD
ML
HA
HA
HA
HA
HA
HA
HA
0.008
51
Chi orodibroao-
aethane
HO
HD
0.070
HD
HD
HA
HA
HA
HA
HA
HA
HA
HA
0.014
57
2-Hitrophenol
0.022
m>
HD
HD
HD
HA
HA
HA
HA
HA
HA
HA
HA
0.004
60
4,6-Dini tro~o-
creaol
m
0.095
HD
HD
HD
HA
HA
m
HA
HA
HA
HA
M
0.019
66
Bi»(2-ethylhe*3rl)
phthalate
0.078
0.025
2.03
0.042
HD
HA
M
HA
HA
HA
HA
HA
HA
0.44
67
Butyl benqrl
0.011
0.034
HD
0.011
HD
HA
HA
HA
HA
HA
HA
HA
HA
0.011
ph thai ate
0.011
68
St-rhit}l
pbthalate
n>
n>
0.055
HD
HD
KA
M
HA
HA
HA
HA
HA
HA
70
Diethyl phthalate
0.065
HD
HD
HD
HD
HA
HA
HA
HA
HA
HA
HA
HA
0.013
71
Dinetbyl phthai ate
0.085
HD
HD
HD
HD
HA
HA
HA
HA
HA
HA
HA
HA
0.017
85
Ttetrachloroethylane
0.012
HO
HD
HD
HD
HA
HA
HA
HA
HA
HA
HA
HA
0.002
US
Arsenic
HA
m
0.08
HA
0.33
HA
HA
HA
HA
HA
HA
HA
HA
0.021
118
Cafeitaa
-
-
-
-
0.13
HA
M
HA
HA
HA
HA
HA
HA
0.026
119
Orosiai
0.36
3.8
16.3
0.090
2.4
HA
M
HA
HA
HA
HA
HA
HA
4.59
120
Copper
0.33
0.61
0.M
0.07
3.7
HA
HA
HA
HA
HA
HA
HA
HA
1.09
121
Cyanides
Wad
HO
HD
0.075
HD
HD
HA
HA
HA
HA
HA
HA
HA
HA
0.015
m
-
0.13
HD
0.18
1.89
HA
HA
HA
HA
HA
HA
HA
HA
0.44
124
nickel
0.42
0.79
1.4
0.080
3.7
HA
1M
HA
HA
HA
HA
HA
HA
1.30
126
Silver
m
HD
HD
HD
0.020
HA
HA
HA
HA
HA
HA
HA
HA
0.004
128
Zinc
59
27
1.14
15
-
HA
HA
HA
HA
HA
HA
HA
HA
20.6
HDi Hot detected (included in average).
Ms Mot analysed.
- I let calcalatiooa yielded negative values.
-------
TABLE V-2
SnOKKX OF AMLVTICAL DATA FK>M SMTU» PLAHTS
MICH. SULFURIC ACID PICKLMG
WET RAW SPEW OOMCEHrRATBS - CfCHBMn«l (»g/l)
Raw
Wastewater
Plant Code
091
092'
P-2
Q-2
R-2
Reference No.
0612
0088A
0312
0894
0240B
Aieragi
Sanple Points
R-A
C-A
3
1
6
Flow (gal/com)
3.5
14.6
17.6
24.3
10.5
14.1
Par aneter
Dissolved Iron
63,000
38,500
46,800
61,900
67,800
55,600
Oil and Grease
8
14
29
14
HA
16.25
Suspended Solids
2363
305
26
142
70
581.2
PH
<1.0
<1.0
1.4
<1
2.0
<1.0-2.
11
1,1,1,-Trichloroethane
0.010
HD
HA
NA
NA
0.005
23
Chi or of am
0.010
HD
MA
NA
NA
0.005
44
Methylene Chloride
ND
0.042
MA
NA
M
0.021
66
Bi»(2-ethylhexyl )ph thai ate
0.78
0.015
NA
NA
NA
0.40
68
Di-n-butyl phthalate
HD
0.045
HA
NA
HA
0.022
71
Dinethyl phthalate
m>
0.150
HA
NA
NA
0.075
85
Tet rachl oroethylene
0.010
HD
HA
NA
HA
0.005
86
Toluene
0.010
HD
HA
NA
HA
0.005
87
Trichloorethylene
0.010
HD
HA
NA
HA
0.005
118
Cadaiun
0.25
0.26
NA
NA
HA
0.026
119
Chroaiua
269
205
HA
NA
HA
237
120
Copper
2.6
4.7
HA
HA
HA
3.7
122
lead
1.5
-
HA
HA
HA
0.75
124
¦ickel
23
27
HA
HA
HA
25
126
Silwr
0.59
0.43
HA
NA
HA
0.52
128
Zinc
16
133
NA
NA
HA
75
Dt lot detected!.
Mi Hot analysed.
- I Met calculations jtilM negative result*.
-------
TABU V-3
SUMMARY OF ANALYTICAL DATA FROM SAMPLED PLANTS
CORTIHDODS SOLFtftIC ACID PICKLING
NET RINSE WASTEWATERS - COH CENT RATIONS (mg/l)
Raw Wastewater
Plant Code
094(Sheet)
094(Strip)
097
H-2
T-2
QQ-2
SS-2
TT-2
WW-2
Reference No.
0948C
094 8C
0760
0432A
0792 B
0584 E
0112A
0856D
0868A
Averaj
Sasple Point
C-A
D-A
(B+C)-A
3+4-1
1-2
5-1
2-10
1-2-3
1-3
Flow (gal/ton)
303
422
11.6
115
21.6
167
202
134
284
184
Partaeter
Dissolved Iron
40
98
36
28.7
1833
64.7
63
81.9
357
289
Oil aid Grease
9
7
3.3
6.2
5
-
2
2.4
1.6
4.1
Suspended Solids
38
29
334
-
49
34.5
76
7.0
6.1
63.7
pa
3.2-5.7
2.2-2.3
NA
1.9-6.4
1.6
2.7
2
1.8
1.7
1.6-6.
4
Benzene
*
ND
ND
NA
NA
NA
NA
NA
NA
*
44
Methylene
0.145
ND
ND
NA
NA
NA
NA
NA
NA
0.048
Chloride
70
Diethyl
ND
0.029
ND
NA
NA
NA
NA
NA
NA
0.010
phthalate
71
Din ethyl
ND
*
0.015
NA
NA
NA
NA
NA
NA
0.008
phthalate
115
Arsenic
-
-
1.0
NA
NA
NA
NA
NA
NA
0.33
118
Cathiua
-
0.080
0.1
NA
NA
NA
NA
NA
NA
0.060
119
Chtosiw
-
0.040
2.91
NA
NA
NA
NA
NA
NA
0.98
120
Copper
0.045
0.13
10.4
NA
NA
NA
NA
NA
NA
3.52
122
Lead
0.03
-
0.240
NA
n
NA
NA
NA
NA
0.090
124
Nickel
-
-
4.62
NA
NA
NA
NA
NA
NA
1.54
126
Silver
ND
ND
0.847
NA
NA
NA
NA
NA
NA
0.28
128
Zinc
-
0.040
0.20
NA
NA
NA
NA
NA
NA
0.080
* : Concentration leas than 0.010 mg/l.
NDt Hot detected.
11: Not analysed.
- : Net calculations yielded negative results.
-------
TABLE V-4
SUMMARY OF ANALYTICAL DATA FROM SAMPLED PLANTS
COHTIHUOUS SULFURIC ACID PICKLING
WET HAW SPENT CONCENTRATES - CONCENTRATION («g/l)
Raw Hastenater
Plant Code
097
B-2
T-2
QQ-2
SS-2
TT-2
WW-2
Reference No.
0760
0432A
0792B
0584 E
0112A
0856D
0868A
Average
Sanple Points
E-C
2
-
2
1
4
2
Flow (gal/ton)
7.2
14.7
14.6
23.6
10.9
23
44.7
19.8
Far as e£ era
Dissolved Iron
38,750
47,900
34,000
48,300
48,000
70,800
19,000
43,800
Oil and Crease
35
HA
18
8.5
9.5
18.5
10
16.6
Suspended Solid*
236
18,000
65
128
200
222
91
2706
1*
<1.0
<1.0
<1.0
<1.0
<1.0
<1.0
<1.0
<1.0
44 Methylene Chloride
0.055
NA
NA
NA
NA
NA
NA
0.055
115 Arsenic
0.20
HA
NA
NA
NA
NA
NA
0.20
118 Cadaias
0.41
NA
NA
NA
NA
NA
NA
0.41
119 Chrosiai
26
NA
NA
NA
NA
NA
NA
26
122 Lead
1.19
NA
NA
NA
NA
NA
NA
1.19
124 Nickel
14.4
NA
NA
NA
NA
NA
NA
14.4
126 Silver
0.?8
NA
NA
NA
HA
NA
NA
0.28
128 Zinc
2.5
NA
NA
NA
NA
NA
NA
2.5
Ml Rot analysed.
ID: Not delated.
- i No Maple at*
noaber designated.
-------
TABLE V-5
SUMMARY OF ANALYTICAL DATA FROM SAMPLED PLANTS
CONTINUOUS SULFURIC ACID PICKLING
NET RAW FDME HOOP SCRUBBER WASTEWATERS - CONCENTRATION (ag/1)
Row Wastewater
Plant Code
Reference No.
Saaple Points
Flow (gal/ton)
Parameters
QQ-2
0584 E
3
2
SS-2
0112 A
3*4+5
22.6
TT-2
0856D
2
2.3
Average
9.0
Dissolved Iron
Oil and Grease
Suspended Solids
PB
305
2.5
2.5
1.4
0.55
2.0
7.5
1.9
88.7
9.0
198
1.7
131.4
4.5
69
1.4-1.9
-------
TABLE V-6
SUMMARY OF ANALYTICAL MIA FROM SAMPLED PLANTS
BATCH HYDROCHLORIC ACID PICKLING
NET HAW RINSE WASTEWATERS - CONCENTRATION (mg/1)
Raw Wastewater
Plant Code
Reference Ho.
Saple Point
Flow (gal/ton
Par meters
V-2
0936
1+6-5
167.2
U-2
04 80 A
1-2
92.9
Average
130.0
KJ
U
w
Dissolved Iron
Saapended Solids
Oil and Grease
pH (Units)
270
0
1.5
2.5-3.4
190
0
3
1.8
230
0
2.3
1.8-3.4
-------
TABUS V-7
SUMMARY OF ANALYTICAL DATA FROM SAMPLED PLANTS
BATCH HYDROCHLORIC ACID PICKLING
NET RAW SPENT CONCENTRATES CONCENTRATION (mg/1)
Raw Wastewater
Plant Code
Reference No.
Saaple Point
Flow (gal/ton)
Parameters
V-2
0936
(7*8)
3.86
U-2
0480A
3
6.45
Average
5.16
KJ
Ul
Dissolved Iron
Suspended Solids
Oil and Grease
pH
107,000
140
HA
<1
77,000
40
NA
<1
92,000
90
NA
<1
-------
IAS LIE V-8
SUMMIT OF AHALTTICAL DATA FROM SAW LED P LASTS
OOKTIHOOUS HYDROCHLORIC ACID PICXLIHG
NET HAW MUSE WASTEWATERS - COBCE Iff RATIOS Oag/1)
Raw iMtwata
Plant Code
1-2
W-2
JE-2
1-2
Z-2
AA-2
BE-2
091
093
095
099
100(a)
100(b)
teCerocc Ho.
08S6F
M
00601
**
03960
0384 A
0060
0612
0396D
0584F
052 88
0384A
0384 A
Saaple Point*
4-6
7-3
3-7
5-4
1-4
2-1
5-2
B-G-F-A-L
B-A
G-A
C-F
C-A
B-A
Average
riw (gal/toa)
220
227.5
663
87.3
166
5.85
211
328
203
16.9
45.4
289
3.3
188
Puacten
.
Dissolved Iron
7
136
193
218
11,300
13,700
1100
_
2,530
2,325
1,379
35
2,185
2,700
Suspended Solids
96
17
-
1.5
72
8
37
-
206
-
16
34
0
37.5
Oil aid Grease
3.9
S
HA
-
9
28
59
-
147
0
9.1
3.0
0
20.3
pB, Units
4.5-5.0
2.9-3.8
2.2-2.6
1.7
1.1
1.1
1.5-1.7
2.9-3.8
1.0
1.4-1.7
1.9-2.8
4.2
2
<1.0-5.0
23
Chi or of oral
HA
HA
HA
HA
HA
HA
NA
-
*
0.020
HD
*
•
0.007
39
Fluoraathene
HA
HA
HA
HA
HA
HA
HA
*
0.060
HD
RD
*
HD
0.013
44
Methylene Chloride
HA
HA
HA
HA
HA
HA
HA
-
-
1.20
*
-
-
0.20
60
4,6-ftini tro-o-cresol
HA
HA
HA
NA
NA
HA
NA
0.013
m>
HD
HD
RD
HD
0.002
65
Phenol
HA
HA
HA
HA
HA
HA
HA
*
TO
•
HD
•
-
0.005
66
8is(2-ethylhexyl)
HA
n
NA
HA
NA
HA
HA
-
4.705
*
-
-
0.050
0.79
phthai ate
67
Butyl be nay 1 phthal ate
HA
HA
HA
HA
HA
HA
m
-
0.025
HD
HD
HD
*
0.006
68
Di-n-butyl phthal ate
HA
HA
HA
HA
HA
HA
HA
-
0.112
•
*
*
*
0.025
70
Diethyl phthalate
HA
HA
HA
HA
HA
HA
HA
-
HD
HD
HD
*
HD
0.002
71
Diaethyl phthalate
HA
HA
NA
HA
KA
M
MA
*
0.055
HD
HD
HD
HD
0.011
85
Tetrachloroethylene
HA
HA
HA
HA
HA
HA
HA
•
0.040
0.019
HD
HD
HD
0.012
87
Trichloroettaylene
HA
HA
HA
HA
HA
HA
NA
0.057
HD
HD
HD
HD
HD
0.010
114
AxMtinony
HA
HA
HA
HA
HA
HA
HA
HA
HA
0.181
HA
*
0.19
0.124
115
Arsenic
HA
HA
HA
HA
HA
MA
MA
M
-
0.225
0.25
HA
HA
0.23
118
Cadnin
HA
HA
HA
HA
HA
MA
MA
-
HD
HD
*
*
0.010
0.005
119
OrniiB Total
HA
MA
M
HA
HA
HA
HA
-
0.79
-
0.34
•
0.57
0.28
120
Copper
m
MA
HA
M
HA
MA
MA
-
0.67
0.68
0.61
0.06
1.6
0-60
122
toad
HA
HA
HA
HA
HA
MA
MA
-
0.43
HD
HD
*
0.14
0.10
124
Nickel
HA
HA
HA
HA
HA
HA
HA
-
0.48
0.733
0.63
*
1.28
0.52
128
Zinc
HA
HA
M
HA
HA
HA
HA
160
1.41
0.416
0.13
0.14
0.38
27.1
* t Calculation yielded values leas than 0.010 mfjl.
**! riant hu m refereace airtic.
(a) bndiiiii acid riaae
(k) Cascade riaae
nh Mot detected
¦i lot aul/nd
- > Calculation yielded a negative value
-------
TABLE \H
SUMMUtY Of AHALTTICAL DATA »»! SANPUD FLAHTS
OOHTIHODOS RMOCBLflUC ACID riGKLIHC
HBT U» WW CMamflB - OCBCEimMnOH <¦»/!)
>¦* Haatevater
Plant Code
1-2
W-2
2—2
AA-2
091
093
095
099
100
Reference Ho.
0856P
-
03960
03WA
0612
0396D
0584 F
0528B
0384A
Average
Staple Points
8-6
1-3
3-4
3-1
L-A
Kl)-A
B-A
B-A
K-A
Flow
Flow (gal/ton)
220
11.9
41.4
3.26
18.1
203
49.7
81.7
4.6
70.4
Par Meters
Dissolved Iron
7.1
137,700
44,300
116,000
56,000
3950
8,000
75,500
18,000
51,050
Suspended Sol ids
54
97
120
40
3,026
240
74.0
42.0
316
445
Oil and Grease
HA
S.l
0
0
4.0
237
4.0
11.0
5.0
33.3
pH, Units
4.5-5.0
0.6-0.7
<1
<1
<1
1.0
1.3-3.0
<1
<1
0.6-3.0
23
Chlorof oca
HA
M
HA
HA
*
•
0.101
*
O.OU
0.022
44
Methylene Chloride
HA
HA
HA
HA
*
RD
2.333
0.014
0.409
0.55
65
fhenol
HA
HA
M
HA
HD
RD
0.013
HD
ND
0.003
66
Bia(2 ethylheiyl)
M
HA
HA
HA
*
HO
0.017
1.550
0.155
0.344
phthalate
67
Butyl bensyl phthalate
HA
M
m
HA
ND
RD
HD
o.ou
0.045
O.OU
68
Di-n-bu tyl phthalate
HA
HA
HA
HA
RD
RD
HD
0.033
HD
0.007
85
Tetrachloroethylene
HA
HA
HA
HA
RD
RD
0.031
HD
HD
0.006
87
Triehl or ©ethylene
mk
HA
HA
HA
0.028
HD
HD
HD
HD
0.006
114
Antinomy
HA
HA
HA
HA
HA
HA
0.187
HA
4.1
2.14
115
Arsenic
HA
HA
HA
HA
HA
0.05
0.025
0.39
HA
0.155
118
CaifaiuB
HA
M
HA
HA
0.028
0.02
HD
0.26
0.28
0.12
119
Chroaiua Total
HA
MA
HA
HA
37.0
0.84
1.505
17.0
8.7
13.0
120
Copper
HA
HA
HA
HA
22.0
0.67
2.42
19.0
11.0
11.0
122
Lead
HA
m
HA
HA
1550
0.43
HD
*
2.1
311
124
Mickel
M
IM
HA
HA
22.0
0.48
2.505
13.0
13.0
10.2
128
Zinc
HA
HA
HA
HA
61.0
1.5
2.505
4.20
4.50
14.7
* : Calculation yielded nnlc* lees than 0.010 ag/1.
Ms Rot analyzed.
HDs Hot detected.
-------
TABLE V-10
SUMMARY OF ANALYTICAL DATA FROM SAMPLED PLAHTS
COHTIHOOUS HYDROCHLORIC ACID PICKLIHC
BCT BAH FPUS HOOD SCRUBBER WASTEWATERS - COHCBHTMTIOH fag/1)
Raw Wastewater
Plant Code W-2 7-2 093 095
Reference No. ** ** 03960 0584F
Swple Points 6-4 4-6 J-A GA2-G
Flow (gal/ton) 45.5 39.7 31.1 0.39
Parameters
880 662
2098
325 43.8
1.6 1.2
HD 0.017
* 0.332
HD HD
*
— ... 0.325 HD
U) 69 Di-n-octyl phthalate HA HA 0.358 0.055
o 114 Antisony HA HA HA 0.106
0 0.039
0.24
0.76 0.267
0.35
0.20
1.6 0.159
Dissolved Iron
23.9
3.7
Suspended Solids
3.0
1.7
Oil and Crease
5.3
-
pH (Units)
2.8-3.7
1.8-1.9
6
Carbon Tetrachloride
HA
MA
23
Chi orofocw
HA
HA
64
PeatMcbl orofbenol
M
HA
66
Bis(2 ethylhexyl)phthaiate
HA
HA
67
Butyl benayl phthalate
HA
NA
69
Di-n-octyl phthalate
HA
HA
114
Antisooy
Ift
MA
115
Arsenic
HA
HA
119
Qsoain
HA
HA
120
C°Pper
HA
MA
122
Lead
HA
HA
124
Hickel
HA
HA
128
Zinc
M
M
099
100
052 SB
0384 A
Average
F-A
J-H
6.1
3.4
21.0
45
1025
440
6
9
353
4
-
63.0
<1.0
1.0-1.2
<1.0-3.7
HD
HD
0.004
*
*
0.091
0.043
HD
0.011
0.320
-
0.083
0.026
*
0.090
0.01
*
0.109
MA
0.1
0.103
0.070
HA
0.036
0.09
0.15
0.12
0.10
0.1
0.31
-
-
0.009
o.oeo
0.1
0.095
0.009
0.07
0.460
* s Calculation yielded a value less than 0.010 mg/1.
Hs Hoc analysed.
- s Calculation yielded a negative result.
HD: Mot detected.
**:. Plants have no assigned reference mnber.
-------
TABLE V-ll
SUMMARY OF ANALYTICAL DATA FROM SAMPLED PLANTS
OMIIHUOUS HYDROCHLORIC ACID PICKLING
HKT HAW ABSOBBER VEWT SCRUBBER WASTEWATERS - COHCEOTRATIOH (mg/l)
R*w Wastewater
to
cj
CD
Plant Code
W-2
X-2
Reference No.
**
0060B
S««ple Points
5
2-1
Flew (gal/ton)
98.6
200
Pari
¦¦eters
Dissolved Iron
15
63.5
Suspended Solids
129
70
Oil and Grease
2.2
-
pH (Dnits)
3.7-7.6
6.9-7.1
30
1, 2-Transdichloroethylene
NA
NA
44
Methylene Chloride
NA
NA
66
Bis(2-ethylbexy 1)ph thalste
NA
NA
69
Di-n-octyl phthalate
NA
NA
71
Diaethyl phthalate
NA
NA
85
Tet rachloroethy1ene
NA
NA
114
Antimony
NA
NA
115
Arsenic
NA
NA
119
Chroaiua
NA
NA
120
Copper
NA
NA
122
Lead
NA
NA
124
Nickel
NA
NA
128
Zinc
NA
NA
T-?(a)
**
1-6
288
85
7.0-7.1
NA
na
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
T-2(b)
**
2-6
336
0.41
1.5
1.7
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
095
099
0584F
052 8B
Average
C-A
E-A
69
170
197
3658
150
650
65
51
67
-
-
0.4
1.7-2.1
<1.0-2.3
1.7-7.6
0.109
ND
0.055
1.070
0.031
0.55
0.046
0.012
0.029
0.021
ND
0.011
0.030
ND
0.015
0.011
ND
0.006
0.209
NA
0.209
0.017
*
0.014
-
0.98
0.49
1.27
0.436
0.85
-
0.10
0.05
0. 790
0.64
0.72
1.09
0.71
0.90
*: Calculation yielded a value less than 0.010 ag/1.
Calculation yielded a negative result.
(a) Acid regeneration unit with cyclone,
(b) Acid regeneration unit with electrostatic precipitator.
NA: Not analysed.
ND: Not detected.
**: Plant has no assigned reference awber.
-------
TABU V-12
SUMMARY OF ANALYTICAL DATA FBOM SA»LED PLANTS
BATCH COMBINATION ACID PICKLING
MET BAH RINSE WASTEWATERS - COHCKHTRATIOH (ng/1)
Raw Wastewater
Plant Code
C
F
L
D
123
124
125
Reference Mo.
0424-01
0856H
0440 A-01
0748
0088A
00 (USD
0S84B
S«aple Poiota
2 City
1-9
10-Hell
1-8
D-A
B-A
C-A
Average
Hater
Hater
Flow (gal/ton)
91
279
140
677
310
1,176
650
475
Parameters
Suspended Solids
404
—
165
_
35
1
1
86.6
Oil and Grease
-
0.1
0.9
2.2
2
9
3.0
2.5
Fluoride
635
173
0.33
500
MA
24.0
49.9
230.4
Dissolved Iron
717
60.3
133
1,080
46
10
5.0
293
pi, Units
0.4-0.8
2.6-2.9
2.8-3.0
1.9
2.6-2.7
2.7
3.5-3.6
0.4-3.6
23
Chloroform
MA
NA
NA
NA
-
-
0.047
0.016
44
Methylene Chloride
MA
NA
NA
MA
-
0.040
0.028
0.023
66
Bis(2 ethylhexyl)phthai ate MA
MA
NA
NA
0.266
0.138
0.135
0.048
67
Butyl benxyl phthai ate
MA
NA
NA
NA
*
•k
0.125
68
Di-n-butyl-ph thai ate
MA
NA
NA
NA
*
*
*
~
85
Tet r achl oroet hy 1 ene
DA
MA
NA
NA
—
*
0.01
115
Arsenic
MA
NA
NA
NA
0.01
0.01
0.01
119
Cbroaion
111
13.4
24.4
152
2.9
25.9
1.07
47.2
120
Copper
4.6
-
0.8
1.38
0.24
*
0.05
31.01
121
Cyanide
0.12
0.12
NA
NA
-
*
-
0.050
122
Lead
-
-
-
-
0.10
0.05
0.05
0.030
124
Mickel
156
9.4
12.5
70
7.4
27
0.54
40.4
128
Zinc
0.87
0.05
0.02
5.1
0.06
0.03
-
0.88
HD l Mot detected.
Unk: Unknown.
H : Mot analysed.
* t Concentration less than 0.010 ag/1.
- t Calculations yields a negative value.
-------
TABLE V-13
SDMNttT OF ANALYTICAL DATA FROM SAMPLED PLANTS
BATCH COMBINATION ACID PICKLING
met iaw sfgirr cobcbmtratk - ccwcEHrRATioii (ng/i)
Raw Wastewater
Plant Code
C(l)
C(2)
E
F
L
M
S
T
0
Reference Mo.
0424
0424
0201
0856H
0440A
0432J
00601
link
0748
Saaple Points
11
12
14
11
5
15
7
9
2
Flow (gal/ton)
-
-
-
-
-
-
-
-
-
Pari
¦seter
Dissolved
13,200
13,200
15,700
34,300
1.2
NA
8,240
34,500
30,400
18,693
Iron
Fluoride
1,700
7
18
7,000
232
17,000
380
MA
NA
3, 762
Nitrate
DA
MA
16,000
8,800
NA
1,481
NA
NA
NA
8,760
Oil and Grease 0.2
0.2
0.4
HA
NA
NA
NA
NA
NA
0.4
Suspended
224
44
114
100
123
60
236
NA
16
115
Solids
pH, Units
1.2
0.3
0.8
2.2
NA
1.2
0.8
0.9
2.3
0.3-2.3
118
Cadaiua
0.09
0.118
0.06
0.22
NA
0.32
0.17
0.3
0.35
0.20
119
Chroaiun
2,090
1360
2,426
6,800
NA
6,720
1,424
5,040
7,000
3,651
120
Copper
114
6.79
78
54
NA
640
52
632
144
19
122
Lead
*
*
5.7
2.64
NA
NA
1.28
7.1
1.2
2.56
124
Nickel
2,832
1786
2,123
4,200
NA
5,980
1,552
17,200
9,040
5,589
128
Zinc
0.97
2.15
1.6
85
MA
7.2
1.6
32
5.8
17.0
(1) Pickle line utilised HHO.-flF acid*.
(2) Pickle line utilised H^SO^ acid
RD : Rot detected.
HA : Hot analysed.
Onk: Unknown.
* : Concentration is less than 0.010 ag/1
-------
TABU V-14
SUMHARY OF ANALYTICAL DATA FROM SAMPLED PLAITS
BATCH row HAT ION ACID PICKLIHG
1 SAW PQjg aOOD SOtBWgK WASTEWATERS - CCHCBWTKATIOH (¦g/1)
Iw Wastewater
(o
ft
M
Plant Code
leference Ho.
Saiple Poiata
Flow (gal/ton)
Recycle Syatea It
Parameter
¦tailed
F
856H
2-9
50.4
Ho
125
884E
B-A
10.0
Tea
Average
30.2
Suspended Solida
-
23.0
11.5
Oil and Grease
0.2
23.0
11.6
Fluoride
1,802
5,500
3,650
Dinolwd Iron
45.7
503
274.4
pH, Units
1.5-2.0
2.9
1.5-2,
1
Aeenapthene
MA
0.017
0.017
21
2,4, 6-Trichl orophenol
HA
0.023
0.023
22
Parachloromtacresol
HA
RD
HD
31
2, 4-Dichl orophenol
MA
0.022
0.022
3*
2, 4-D methyl phenol
MA
0.045
0.045
39
Fluoranthene
HA
*
*
44
Methylene Chloride
HA
*
*
67
Butyl benzyl ph thai ate
HA
0.027
0.027
M
Di-o-butyl ph thai ate
HA
0.135
0.135
69
Di-n-octyl ph thai ate
HA
0.080
0.080
70
Diethyl phthalate
HA
*
*
71
Dinethyl phthalate
HA
0.076
0.076
115
Araenic
HA
0.57
0.57
119
Chroaion
2.42
69
35.7
120
Copper
0.07
1.8
0.94
121
Cyanide
*
0.10
0.088
122
Lead
MA
0.04
0.04
124
Michel
3.3
47
25.2
128
Zinc
0.30
1.5
0.90
At lot analysed.
IDs lot detected.
- t Calculation# yielded a negative result.
* l Calculations yielded a value leaa than 0.01 mgf\.
-------
TABLE V-15
SUMMARY OF ANALYTICAL DATA FROM SAMPLED PLANTS
CONTINUOUS COMBINATION ACID PICKLING
NET RAW RINSE WASTEWATERS - CONCENTRATION (mg/1)
Raw Wastewater
to
to
Reference No.
Plant Code
Sample Points
Flow (gal/ton)
Parameter
Suspended Solids
Oil and Grease
Fluoride
Dissolved Iron
pH, Units
Benzene
Chi oroform
Methylene Chloride
Bis(2 ethylhexyl)phthalate
Tet r achloroethylene
Antimony
4
23
44
66
85
114
115
119
120
124
128
Arsenic
Chromium
Copper
Nickel
Zinc
Nitrates
248B
D
4-1
1,016
10
76.5
103.5
3.8
HA
NA
NA
NA
NA
NA
NA
16.0
0.11
9.2
11.0
432K-02
I
4-1
1,814
553
0.6
31.4
59.2
3.2-7.2
NA
NA
NA
NA
NA
NA
NA
17.1
0.14
5.98
0.747
14.4
176-03
0
29-32
974
76
9.5
15.4
1.71
5.4-8.2
NA
NA
NA
NA
NA
NA
NA
0.48
0.040
2.14
0.070
20.3
0900
121
B-A
2, 754
2
169.0
148
2.4-2.7
0.028
0.184
0.501
0.017
0.030
0.060
0.012
32.2
0.528
19.4
0.317
NA
Average
1,640
160
3.0
73.1
78.1
2.4-8.2
0.028
0.184
0.501
0.017
0.030
0.060
0.012
16.4
0.205
9.18
0.284
15.1
NA: Not analyzed.
- : Calculations yielded a negative number.
-------
TABLE 7-16
SUMMARY OF ANALYTICAL DATA FROM SAMPLED PLANTS
COrrINITIOS COMBINATION ACID PICKLING
NET RAW SPEW COHCEOTEATIS - CONCENTRATION tmg/1)
Iwlaitmtit
Plant Cod*
A
0(1)
0(2)
I
0(1)
0(2)
llfnnct Ho.
0900
248B
2488
Q432K
0176
0176
Avaraga
Saapla Point
12
14
13
12
23
26
Flow (gal/ton)
NA
NA
NA
4.2
NA
NA
4.2
Paraaatara
Oil and Graaaa
2.6
2.2
2.0
7.1
NA
NA
3.5
Suapandad Solida
196
318
196
109
NA
KA
205
Diiaolvad Iron
989
74 , 700
36,900
20.6
16,200
6,960
22,595
Fluorida
15,000
2.5
6.4
26,000
NA
NA
10,253
pH, Onita
0.7
2.2
2.1
1.1
2.0
0.9
0.7-2.2
US Cadaiua
0.03
0.08
0.07
0.1
0.05
0.02
0.06
119 Chroaiua
2,400
6,242
3,481
4,284
2,361
1,248
3,336
120 Coppar
36
80
28
37
416
16
102
122 Uad
1.3
1.4
1.4
MA
1.2
0.6
1.2
124 Hickal
2,300
4,680
1,952
2,031
4,914
3,822
3,283
128 Zinc
1.4
6.4
4.0
1.1
10.8
0.76
4.1
Hitrata
463
NA
226
3,550
NA
NA
1,413
NAi Hot availabla
243
-------
ACID PICKLING SUBCATEGORY
SECTION VI
SELECTION OF POLLUTANTS
The final selection of pollutants for the acid pickling subcategory
was based on the analysis of wastewater samples collected during this
study. A number of pollutants originally limited by the 1976
regulation were selected, because they characterize the wastes from
the pickling operation. The pollutants limited by this proposed
regulation include those listed in the 1976 regulation plus certain
toxic pollutants found during extensive monitoring conducted for this
study. This section describes the pollutants considered for
regulation, presents the rationale for selecting those pollutants, and
the process sources of those pollutants.
Pollutant Selection
Conventional Pollutants
In the original regulation, three conventional pollutants were limited
for all types of acid pickling operations: total suspended solids,
oil and grease, and pH. However, the limitations for the oil and
grease were applicable only when pickling wastes were treated jointly
with cold roiling wastes. Wastewater characteristics for batch and
continuous operations are similar, such that the same limited
pollutants can apply to both types of operations in each acid
subdivision.
Based upon the information gathered during this study, the Agency
decided to retain oil and grease on the list of limited pollutants in
certain instances. Cold rolling wastes and pickling wastes are often
co-treated to take advantage of emulsion breaking properties of the
acid wastes. Since this is a common practice, and since the pickling
wastewaters can contain moderate amounts of oils, an allowance for oil
and grease is included in the proposed limitations.
High levels of suspended solids and low pH are also characteristic of
acid pickling operations. Solids are generated in the pickling
process and are carried away in either the rinse or fume scrubber
waters or in the spent pickle liquor bath. In addition, pH was also
limited in the original regulation for this subcategory and will
continue to be regulated by the proposed limitations. The pH of the
raw wastes from acid pickling lines is always acidic, with typical
values ranging from <1 to 4 standard units. Wastewaters with low pH
values can have detrimental effects if discharged without treatment.
Neutralization is required to bring the pH to within the regulated
levels of 6.0-9.0 standard units.
245
-------
Other Pollutants
In the original regulation, several nonconventional nontoxic
pollutants were limited. Dissolved iron was limited for all three
acid pickling operations. In addition, dissolved chromium, fluoride,
and dissolved nickel were all limited for combination acid pickling
operations. (The fluoride limitation applied only to those mills
using hydrofluoric acid). Limitations for these four pollutants are
being retained in the present regulation. However, chromium and
nickel are now limited on a total rather than a dissolved basis at
BAT, NSPS, PSES, and PSNS. The Agency made this change to more
accurately reflect the true pollutant load characteristics of these
wastewaters.
Toxic Pollutants
Besides the pollutants limited during the first phase of this study,
the Agency found that toxic pollutants are present at significant
levels in the discharges from acid pickling operations. During the
second phase of sampling, the Agency conducted additional monitoring
for the pollutants limited in the 1976 regulation, toxic pollutants,
and other pollutants. Based upon this sampling and responses provided
by the industry, the Agency developed a list which summarizes toxic
pollutants known to be present in the wastewater. (Table VI-1).
The Agency tabulated and calculated a composite concentration value
for each pollutant in the raw wastewater. A net value was used to
describe the contribution of pollutants from the pickling process. If
a pollutant was found in the raw wastewater at an average
concentration (net) of 0.010 mg/1 or greater, it was considered to be
characteristic of acid pickling wastewater and is addressed
accordingly throughout this report. Also shown in Table VI-2 are the
other pollutants for which limitations are being considered.
Several organic pollutants were detected at concentrations greater
than 0.010 mg/1 but are not listed in Table VI-2. These pollutants
were omitted because it is believed that their presence is not due to
acid pickling operations. Methylene chloride was omitted because it
is a solvent commonly used as a cleaning agent in the laboratory, and
its presence is ascribed to this practice and not to acid pickling
operations. Also, some phthalate compounds were detected at levels
greater than 0.010 mg/1, but they are not believed to be
representative of acid pickling wastes. Evidence developed during the
sampling inspections indicates that the presence of phthalates was
probably related to plasticizers in the tubing used in collecting the
samples. Only two toxic organic pollutants, namely, chloroform in
hydrochloric acid pickling and benzene in combination acid pickling,
are listed. These are common solvents that may occur in the pickling
process under certain operating circumstances, or may originate from
oils present on the steel product which is pickled.
As noted in Table VI-2, many toxic metal pollutants were detected at
concentrations greater than 0.010 mg/1. These pollutants, as with the
pollutants limited in the 1976 regulation, are present in the
wastewater because of the extreme chemical action that occurs during
246
-------
the pickling process. The acids remove the surface scale from the
steel products which contain the toxic metals. While these pollutants
may vary in concentration from line to line, they are characteristic
of the process. The Agency is proposing BAT, NSPS, PSES, and PSNS
limitations and standards for these toxic pollutants, together with
the previously limited pollutants.
247
-------
TABLE VI-1
PRIORITY POLLUTANTS KNOWN TO BE PRESENT
IN ACID PICKLING OPERATIONS
Sulfuric Hydrochloric Combination
Acid Pickling Acid Pickling Acid Pickling
004
Benzene
-
-
X
021
2,4,6-Trichlorophenol
-
-
X
023
Chloroform
- .
X
X
031
2 f4-Dichl orophenol
-
-
X
039
Fluoranthene
-
X
-
044
Methylene Chloride
X
X
X
051
Chi arodibromomethane
X
-
-
066
Bis(2-ethylhexyl)phthalate
X
X
X
067
Butyl benzyl phthaiate
X
X
X
068
Di-n-butyl phthalate
X
X
X
069
Di-n-octyl phthalate
-
X
X
070
Diethyl phthalate
X
-
071
Dimethyl phthalate
X
-
-
085
Tetrachloroethylene
-
X
X
087
Tri chl oroethylene
-
X
-
114
Antimony
-
X
X
115
Arsenic
X
X
X
118
Cadmium
X
X
X
119
Chromium
X
X
X
120
Copper
X
X
X
121
Cyanide, Total
X
-
X
122
Lead
X
X
X
124
Nickel
X
X
X
126
Silver
X
-
-
128
Zinc
X
X
X
Xt Parameter known to be present in at least one of the waste sources.
Parameter not found.
-------
TABLE VI-2
SELECTED POLLUTANTS - ACID PICKLING OPERATIONS
' Dissolved Itoo
Fluoride
Oil and Grease
Suspended Solids
PH.
4 Benzene
23 Chlorofom
114 Antiaony
115 Arsenic
118 Cadniua
119 Cbroniua
120 Copper
122 Lead
124 Nickel
126 Silver
128 Zinc
Sulfuric
Acid Pickling
X
X
X
X
X
X
X
X
X
X
X
Hydrochloric
Acid Pickling
X
X
X
X
X
X
X
X
X
X
X
X
X
X
Combination
Acid Pickling
X
X
X
X
X
X
X
X
X
X
X
X
X: Par meter selected.
Parameter not selected.
-------
ACID PICKLING SUBCATEGORY
SECTION VII
CONTROL AND TREATMENT TECHNOLOGY
Introduction
This section reviews existing wastewater treatment practices for the
acid pickling subcategory and lists those technologies which were
considered by the Agency in developing this proposed regulation. The
sampling data gathered at the acid pickling operations visited during
this study and a description of the treatment practiced at each are
also presented.
As a first step, it was necessary for the Agency to determine the
level of existing wastewater treatment in the acid pickling
subcategory. The Agency then developed BPT, BAT, BCT, PSES, and PSNS
alternative treatment systems in an "add-on" fashion to this base
level. The NSPS alternative treatment systems, however, were not
developed in this manner. Since NSPS applies to new acid pickling
operations, the Agency did not consider the "add-on" approach. The
alternative treatment systems (levels of treatment) and their
corresponding effluent characteristics are summarized in Sections IX
through XIII.
Summary of Treatment Practices Currently Employed
Because there is the potential for three different wastewater sources,
the treatment systems used on each source are discussed in detail
below, prior to a discusion of the general treatment scheme.
Treatment of Spent Pickle Liquor
Spent pickle liquor is presently classified as a hazardous waste under
the Resource Conservation and Recovery Act (RCRA). Special attention
must be given to this waste to insure that it is either properly
disposed of, or that it is treated sufficiently prior to discharge.
There are several different methods for handling spent acid
concentrates (spent pickle liquor). These methods include disposal,
treatment, or recovery/regeneration processes.
A. Disposal Methods
The disposal methods, which include contract hauling and deep
well injection, are not ideal solutions for handling the spent
acid concentrates. Hauling, and deep well injection move the
wastes from one place to another, and therefore, only relocate
the pollution. However, if properly performed any adverse
environmental effects can be minimized to levels comparable to
treatment of these wastes. Contract hauling is a commonly used
251
-------
method in the industry. Several plants dispose of their spent
pickle liquor by deep well injection.
B. Treatment Processes
Treatment processes include chemical neutralization and
precipitation. Detailed discussions of these processes follow.
Treatment may be performed separately or jointly with the other
wastewaters from the pickling operation. These methods are
commonly employed throughout the industry.
The ideal method for handling spent pickle liquor is to recycle
the wastes through recovery/regeneration processes. These
processes minimize handling costs and either reduce or eliminate
the discharge of pollutants. In addition, the pickling operation
itself may be made more efficient, since the acid bath can be
kept at a relatively constant, strength.
The Agency has identified the following recovery and regeneration
systems which are presently operated in this country. These
systems are available and have been proven effective at many
pickling operations.
1. Sulfuric Acid Recovery
The most common treatment method for recovering valuable
products from spent sulfuric acid is acid recovery by
removing ferrous sulfate through crystallization. Spent
pickle liquor, which is high in iron content, is pumped into
a crystallizer, where the iron is precipitated (under
refrigeration or vacuum) as ferrous sulfate heptahydrate
crystals. As the crystals are formed, water is removed and
the free acid content of the solution increases to a level
where it is reusable in the pickling operation. The
crystals are separated from solution, and the recovered acid
is pumped back to the pickling tank. The by-product ferrous
sulfate heptahydrate is commercially marketable. The
crystals are dried, bagged, and marketed, or sold in bulk
quantities. Ferrous sulfate, commonly referred to as
"copperas," is used in appreciable quantities in numerous
industries, including the manufacture of inks, dyes, paints,
and fertilizers. It is also used as a coagulant in water
and wastewater treatment. See Figures II1-5 and II1-6 for
the two types of available recovery operations. As an added
note, recovery processes, which produce ferrous sulfate
monohydrate crystals as a by-product are also available.
This process is usually carried out at elevated
temperatures.
2. Hydrochloric Acid Regeneration
The only commercially proven technology to regenerate spent
hydrochloric acid is through thermal decomposition. The
spent pickle liquor contains free hydrochloric acid, ferrous
chloride, and water. The liquor is heated to remove some of
252
-------
the water through evaporation and to concentrate the
solution. The concentrated solution is then further heated
to 925° to 1,050°C (l,700o to 1,920°F). At this
temperature, water is completely evaporated and the ferrous
chloride decomposes into iron oxide (ferric oxide, Fe203)
and hydrogen chloride (HC1) gas. The iron oxide is
separated and removed from the system. The hydrogen
chloride gas is reabsorbed in water (sometimes rinsewater or
scrubber water is used), to produce hydrochloric acid
solution (generally from 15% to 21% HC1) which is reused in
the pickling operation. There are several types of these
"roaster" processes in operation. The basic difference
between the processes is the design and operation of the
roaster/reactor and the recovery equipment. Each design,
however, has its own distinct advantages and disadvantages
(see Figures 111—7 through III-9).
Combination Acid Pickling
The Agency is unaware of any operating nitric or
hydrofluoric acid recovery process operating in this
country. It has been reported that such a system is
installed and successfully operating in the People's
Republic of China. However, due to the lack of operating
and performance data, the Agency is not basing any of its
proposed limitations or standards on this technology.
A summary of the treatment practices in each subdivision
disposal of spent pickle wastes is listed below;
for the
Acid
Subdivision
Sulfuric
Hydrochloric
Combination
Central
Treatment
38.3%
13.7%
46.0%
Acid
Recovery
2.6%
8.4%
0%
Contract
Hauling
44.5%
53.7%
44.0%
Deep
Well
5.2%
12.6%
0%
POTW
Discharge
9.4%
11.6%
10.0%
Treatment of Fume Scrubber Water
Many pickling lines include wet scrubber systems to control the
emission of fumes from the operation. Water is used to scrub the
fumes and thus becomes contaminated with the same type of pollutants
which are discharged from the other waste sources. The flow rates
from the scrubbers can be very large, and if not controlled, will
result in the discharge of large pollutant loads.
One means to control the amount of pollutants generated from this
source is to install recycle systems. Recycle rates of 100% have been
reported for many operations and many others have installed systems
which have recycle rates ranging between 90-95% of the total
wastewater flow.
High recycle rates are achievable, because corrosion does not present
a problem. The scrubbers are normally made of fiberglass, which is
not affected by the low pH of this waste source. Therefore, the
253
-------
degree of recycle is limited by the buildup of dissolved solids in the
recycle loop. Those operations that do not recycle this waste source
discharge these wastes to POTWs or to receiving streams after varying
degrees of treatment. The treatment components used by the lines that
discharge wastes from their scrubber systems are described below.
General Treatment Configuration for Pickle Rinsewaters
Most of the operations that treat pickle rinsewaters prior to
discharge do so in central treatment systems. Some of the wastewaters
that are often combined with the pickling wastes are cold rolling
wastewaters and wastewaters from alkaline cleaning or kolene and
hydride descaling operations. The pickling wastewaters are often
combined with cold rolling wastewaters, because the acid in the
pickling wastewaters helps break oil emulsions in cold rolling
wastewaters. Pickling wastewaters are often treated together with
alkaline wastewaters so that they neutralize each other. This can
greatly reduce the costs for chemicals necessary for neutralization.
In any event, most existing treatment systems have components which
accomplish the following: neutralize the acid in the wastes;
precipitate dissolved metals out of solution; promote flocculation of
solids and metals; and provide sufficient sedimentation for the solids
and precipitated metals. Also, some systems include a step which
dewaters any sludge generated in the treatment process.
Control and Treatment Technologies
Considered for Toxic Pollutant Removal
As the Agency found toxic metal pollutants in significant levels in
the discharges from acid pickling operations, it evaluated treatment
systems which are designed primarily to remove these pollutants.
The advanced alternative treatment systems considered by the Agency
for acid pickling operations are described below. These systems have
been demonstrated in varying degrees in the pickling subcategory and
in other industrial applications for wastes with characteristics
similar to those of acid pickling.
A. Lime Precipitation
Chemical treatment of acid pickling wastewaters is well
demonstrated at many plants with lime and polymer flocculation.
Lime precipitation is an effective method of removing toxic metal
pollutants from the wastewater. Lime precipitation involves the
addition of lime, either in the dry or hydrated slurry form, to
the wastewater in a mixing tank followed by sedimentation or
filtration. The metal precipitates are in the hydroxide form.
Lime is commonly used to neutralize acidic wastes because of
economic considerations. Other chemicals such as caustic are
considerably more expensive, but in certain applications offer
advantages over lime. Good removal efficiencies of metals with
lime precipitation have been found in this subcategory. Low
effluent levels have also been demonstrated in other steelmaking
subcategories that employ lime precipitation.
254
-------
A final consideration relating to lime precipitation systems is
the solid waste generation resulting from its use. The large
amounts of sludges which are generated due to the lime addition
are generally disposed of by landfilling. The disposal of
such sludges may pose an operating problem and result in
increased costs, depending on the availability of landfill sites.
The amount of sludge produced during treatment of pickling
wastewaters can be minimized by the design of the treatment
process. In conventional treatment processes the entire volume
of sludge produced is discharged for handling and disposal. In
the modified system a portion of the sludge is recycled to the
head of the treatment plant to act as seed for the treatment
process. The sludges produced in this modified approach are
considerably denser than the sludge produced by the conventional
process. The sludge volume can be reduced by a factor of 30.
B. Sulfide Precipitation
The addition of sulfide compounds to the wastewaters is capable
of reducing metals concentrations below the levels usually
achieved in lime precipitation reactions. Some of the metals
which can effectively be precipitated with sulfide are zinc,
copper, nickel, lead, and silver, which are all toxic metal
pollutants. The increased removal efficiencies can be attributed
to the comparative solubilities of metallic sulfides with
metallic hydroxides.
Iron sulfide is used to achieve precipitation, because this
compound has a solubility which exceeds that of the heavy metal
sulfides to be precipitated. Also, this compound does not form
excessive levels of sulfide ion concentrations, which could
contribute to the formation of hydrogen sulfide, an objectionable
gas. The typical sulfide precipitation system consists of
neutralization, precipitation, and filtration.
There are several problems associated with the sulfide
precipitation system which must be taken into consideration: (1)
high sludge production (unless the sulfide addition follows a
preliminary hydroxide precipitation step); and (2) higher costs
than for the standard hydroxide precipitation system, because
neutralization of the wastewater prior to sulfide treatment is
necessary.
C. Vapor Compression Distillation (Evaporation)
Vapor compression distillation is typically used to concentrate a
high dissolved solids waste stream (3,000 - 10,000 mg/1) to a
slurry consistency (approximately 100,000 mg/1). The slurry
discharge can be dried in a mechanical drier or allowed to
crystallize in a small solar or steam-heated pond prior to final
disposal. The distillate quality water generated by this system
can be recycled back to an acid pickling operation thereby
eliminating all discharges. _ One desirable feature of
this system is its relative freedom from scaling. Because of the
255
-------
unique design of the system, calcium sulfate and silicate
crystals grow in solution as opposed to depositing on heat
transfer surfaces. Economic operation of this system requires a
high calcium to sodium ratio (hard water).
The installation of this system may be the only possible way to
achieve a zero discharge of process water at all acid pickling
operations. However, the high cost and energy intensive nature
of this system precludes its widespread use.
Summary of Analytical Data
Raw wastewater and effluent analytical data for the acid pickling
operations which were visited are presented by subdivision in Tables
VII-2 through VII-14. Table VII-1 provides a key for the control and
treatment technology abbreviations used in the tables throughout this
report. The concentration values presented in the tables represent,
except where footnoted, averages of gross measured values. In some
cases these data were obtained from central treatment systems. Spent
concentrations, fume scrubber wastewaters, and absorber vent scrubber
wastewaters are listed in the raw form only; no effluent values are
given. In several instances, the effluent waste loads (lbs/1000 lbs)
for certain central treatment operations indicated on the analytical
data tables represent apportioned loads. In these central treatment
systems, the percentage contribution of an individual operation to the
total treatment system influent load is determined and subsequently
applied to the total effluent load. This procedure was repeated for
each pollutant. By using this procedure, the Agency assessed the
effects of treatment on the waste loads of an individual process which
discharges to a central treatment facility. Following the
determination of the raw and effluent waste loads, the pollutant load
reductions accomplished by each operation for each pollutant were then
determined.
Summary of Long-Term Analytical Data
As a supplement to the sampled plant analytical data, long-term
effluent analytical data from operations responding to the D-DCPs are
presented in Volume I.
Plant Visits
Brief descriptions of the visited plants follow. Treatment system
flow schematics are provided at the end of this section.
Plant A - See Plant 121
Plant C - Figure VII-1 (Combination)
This plant recently completed the installation of a new central
treatment facility. At the time of this sampling inspection, the
rinsewaters from bar and plate pickling lines were combined prior to
entering an equalization tank. From the equalization tank the wastes
were transferred to a mixing tank, where lime and coagulant aids were
added. The neutralized wastes then were settled in a sedimentation
256
-------
tank. The discharge was sent to a receiving stream. The spent pickle
liquors from the bar and plate lines are discharged to a holding tank,
and then are hauled away by a private contractor.
Plant D - Figure VII-2 (Combination)
At the time of the sampling trip, the acid rinses generated by this
continuous strip pickling process were discharged to a receiving
stream without treatment. However, a central treatment system that
treats the wastewaters from this combination acid pickling line was
completed in 1978 and is now in operation.
Plant F - Figure VII-3 (Combination)
This plant had two sources of wastes: pickle rinsewater and fume
scrubber water, that were combined prior to entering an equalization
tank. After equalization, lime is added and the pickling wastes are
combined with rolling mill wastes in a scale pit. From the scale pit,
the combined wastewater undergoes settling in a settling basin. The
spent pickle liquor at this operation is hauled away to a company
owned disposal site.
Plant H-2 z Figure VII-4 (Sulfuric)
Dunk rinses are cascaded to minimize flow; spray and other rinses
blended with other plant wastewaters for treatment by gas flotation,
neutralization with lime or caustic, flocculation with polymers,
clarifier, with thickening and vacuum filtration of clarifier
underflows. Concentrations are contract hauled off-site.
Plant Z. Figure VI1-5 (Combination)
This plant employs lime neutralization of the spent pickling
solutions,mixing with the acid rinses, and sedimentation in a lagoon
to treat this wastewater generated by the strip pickling process.
Plant 1-2 - Figure VII-6 (Sulfuric)
Waste pickle liquor is hauled away by a private contractor. All
rinses are combined with other plant wastes in a terminal lagoon and
discharged to a canal.
Plant 1-2 z Figure VII-6 (Hydrochloric)
This plant dilutes pickle liquor and rinses together with other plant
wastes in a terminal lagoon and then discharges to a canal.
Plant L - Figure VII-7 (Combination)
This plant employs municipal co-treatment to treat process rinsewaters
generated by the batch bar pickling operation. Waste pickle liquors
are treated at the plant employing lime neutralization.
257
-------
Plant 0 - Figure VII-8 (Combination)
This plant treats its pickle rinsewaters in a central treatment system
with wastes from other processes. The pickling wastes comprise 50% of
the total flow to the central treatment system. Central treatment
consists of equalization, sodium hydroxide neutralization, aeration,
and clarification. Sludges are dewatered in a sludge lagoon. Spent
pickle liquors at this operation are hauled off-site by a private
contractor.
Plant 0-2 - Figure VII-9 (Sulfuric)
This plant employs batch evaporative crystallization of spent sulfuric
acid. Acid is recovered by the production of ferrous sulfate
heptahydrate. Rinses are recycled to process as makeup to pickle
tank. Zero discharge is achieved.
Plant P-2 z Figures VII-10 and VII-11 (Sulfuric)
This plant employs batch pickle liquor regeneration by vacuum
crystallization. Rinses are metered to the sewer.
Plant Q-2 - Figure VII-12 (Sulfuric)
This plant practices batch pickle acid recovery through the cooling of
spent pickle liquor and crystallization of ferrous sulfate
heptahydrate. Rinses and mists from the filter are recycled back to
the pickle tank. Zero discharge is achieved.
Plant R - Figure VI1-13 (Sulfuric)
This plant uses lime neutralization and sludge lagooning to treat
spent concentrates and rinses from batch specialty steel pickling
operations. There is no discharge from the sludge lagoon.
Plant R-2 - Figure VII-14 (Sulfuric)
Pickle liquor and rinses are combined in an equalization tank; mixed
and treated with acetylene sludge; lagooned; and discharged to a
receiving stream.
Plant 5-2 - Figure VII-15 (Sulfuric)
Concentrated pickle liquor is contract hauled. Standing rinse is
reused as makeup to the pickle tank. Running rinse is treated with
lime and lagooned. The lagoon overflow is recycled, and the sludge is
contract hauled.
Plant T-2 - Figure VII-16 (Sulfuric)
Sulfuric acid is recovered from spent pickle liquor by evaporative
concentration. Rinses are cascaded and used as pickle tank makeup.
Steam condensate is used as a final product rinse.
258
-------
Plant U - Figure VII-17 (Combination)
This plant employs batch lime neutralization of the acid rinses after
combining the rinses with wastes from a degreasing line. This
operation also neutralizes its spent pickle liquor prior to
evaporating this waste stream to extinction. The effluent from the
batch treatment system is discharged to a receiving stream.
Plant U-2 - Figure VI1-18 (Hydrochloric)
The waste pickle liquors and rinsewaters from the batch pickling
operations are neutralized in a batch treatment tank by sodium
carbonate prior to discharge to a municipal sewerage system.
Plant V-2 - Figure VII-19 (Hydrochloric)
The spent pickle liquor from the batch pickling operations is contract
hauled. Rinses are neutralized with sodium hydroxide prior to
discharge to a municipal sewerage system.
Plant W-2 - Figure VI1-20 (Hydrochloric)
Waste pickle liquor is treated by pyrolytic regeneration of
hydrochloric acid. Rinses and fume hood scrubber wastes are diluted
and metered to a sewer. Absorber vent scrubber wastes are neutralized
with caustic solution prior to discharge to a receiving stream.
Plant X-2 - Figures VII-21 and VII-22 (Hydrochloric)
This plant practices spent acid recovery by hydrochloric acid
regeneration. Rinses are diluted and discharged to a receiving
stream. Absorber vent scrubber wastes are treated in a clarifier
along with other plant wastes.
Plant Y-2 z Figures VII-23 and VII-24 (Hydrochloric)
Spent pickle acid is recovered by pyrolytic regeneration of
hydrochloric acid. Rinses and absorber vent scrubber wastes are
diluted and discharged to a receiving stream.
Plant Z-2 - Figure VII-25 (Hydrochloric)
Refer to Plant 093.
Plant AA-2 - Figure VII-26 (Hydrochloric)
Refer to Plant 100
Plant BB-2 - Figure VII-27 (Hydrochloric)
Concentrated pickle liquor is disposed of by off-site contract hauling
to a regeneration system owned by the same company or in an on-site
deep well. Rinses are equalized; mixed with cold rolling wastewaters;
neutralized; aerated; treated with polymers; clarified; lagooned; and
259
-------
discharged to a receiving stream. Sludge from the clarifiers is
dewatered by vacuum filters prior to transport to a dump.
Plant QQ-2 - Figure VI1-28 (Sulfuric)
Spent concentrates and fume scrubber system blowdowns are partially
cascaded, blended with other plant wastewaters and treated by chromium
reduction; emulsion breaking; polymer addition; neutralization with
lime; clarification; and, discharge through a settling lagoon with
surface skimming for oil removal.
Plant SS-2 - Figure VII-29 (Sulfuric)
Spent concentrates are collected, equalized, and discharged to a deep
well. Fume hood scrubber blowdowns and rinsewaters are combined with
all other plant wastes; blended; skimmed; neutralized with lime;
aerated; flocculated with polymers; and, transferred to a settling
lagoon; from which sludges are treated by cyclones and thickeners.
Plant TT-2 - Figure VII-30 (Sulfuric)
Waste pickle liquors are collected, neutralized, and transferred to
off-site evaporation ponds. Rinses are cascaded, blended with fume
scrubber blowdowns, and discharged without treatment. A treatment
facility is under construction.
Plant WW-2 - Figure VII-31 (Sulfuric)
Spent concentrates are filtered and injected into deep wells.
Rinsewaters are blended with other plant wastewaters, flocculated with
polymers and alum, neutralized with lime, clarified, skimmed and
discharged through a terminal settling lagoon.
Plant 090 - Figure VII-32 (Sulfuric)
Plant treats rinses from batch pipe and tube pickling in a central
treatment facility that includes equalization, oil skimming, aeration,
neutralization with lime, polymer addition, clarification, and
finally, discahrge to a receiving stream. Spent concentrates are
recovered by a vacuum crystallization acid recovery system.
Plant 091 - Figure VI1-33 (Sulfuric)
Concentrates from a batch rod pickling operation are hauled off-site
for disposal. Rinses are blended and equalized with hydrochloric acid
pickling and galvanizing wastewaters; aerated; neutralized with lime;
clarified; and, filtered prior to discharge.
Plant 091 - Figure VII-33 (Hydrochloric)
Spent pickle liquor and rinses are neutralized with lime, oxidized,
clarified, and filtered through pressure sand filters prior to
discharge to a receiving stream. Clarifier sludge is dewatered by
vacuum filters prior to disposal.
260
-------
Plant 092 - Figure VI1-34 (Sulfuric and Hydrochloric)
Refer to Plant 123.
Plant 093 - Figure VI1-35 (Hydrochloric)
Spent pickle liquor and rinses are mixed with galvanizing and cold
rolling wastewaters, neutralized and clarified with polymer addition
prior to discharge to a municipal sewerage system. Sludges from the
clarifier are dewatered by vacuum filtration prior to transport to a
landfil1.
Plant 094 - Figure VI1-36 (Sulfuric)
Spent concentrates hauled off-site; rinses combined with all other
finishing mill wastewaters, equalized, skimmed, treated with lime and
polymer, clarified via thickener. Centrifugation of underflows and
discharge of treated effluents.
Plant 095 - Figures VI1-37 and VII-38 (Hydrochloric)
This plant practices spent acid recovery by hydrochloric acid
regeneration. Some rinsewater is recycled to fume hood scrubbers and
absorber vent scrubbers. Remaining rinsewater and scrubber wastes are
sent to waste lagoons.
Plant 096 - Figure VII-39 (Sulfuric)
Batch fastener pickler wastes are blended with galvanizing,
aluminizing, and electroplating wastes; aerated and neutralized with
lime; thickened; and, filtered. Filtrates are discharged to a holding
lagoon for plant-wide reuse or discharge.
Plant 097 - Figure VI1-40 (Sulfuric)
Spent concentrates are recovered by a two-stage evaporation and
crystallization recovery system designed to produce dry copperas.
Cold water rinses are used as pickle tank makeup, while hot rinses are
discharged to a POTW for further treatment.
Plant 098 - Figure VII-41 (Sulfuric)
Three lines pickle bar, wire, and special shapes. Rinses are
concentrated and dumped to pickle tanks as makeup. Acid vapors are
collected by a demister and recycled to pickle tanks. All sumps and
foundation drains are collected and transferred to storage. All
liquid wastes are contract hauled off-site.
Plant 099 - Figure-42 (Hydrochloric)
The spent pickle liquor is recovered by acid regeneration. Rinses and
fume scrubber wastes are mixed with other plant wastes, neutralized
and settled in ponds prior to discharge to a receiving stream.
261
-------
Plant 100 - Figure VII-43 (Hydrochloric)
This plant has cascade rinse systems with the rinsewater used as
makeup to a fume scrubber. Spent pickle liquor and fume scrubber
wastes are combined with cold rolling wastewaters and disposed of by
deep well injection.
Plant 121 and A - Figure VI1-44 (Combination)
This operation was visited on two occasions for this study. The first
time the operation was designated as Plant A, and for the second
sampling trip the operation was designated as Plant 121. The pickle
rinse and fume scrubber waters are combined with other small volume
waste flows before entering a central treatment system. The pickling
wastes comprise approximately 75% of the total wastewater flow
entering the central treatment system.
The combined wastes are treated by equalization, neutralizaton and
clarification. The underflow from the clarifiers goes to thickeners
and centrifuges. The overflow from the clarifiers goes to a polishing
tank from which approximately 50% of the treated water is discharged
to a receiving stream. The waste pickle liquor is hauled off-site by
private contractors.
Plant 122 (Combination)
Due to various technical difficulties not known during sampling, the
data from this plant are unacceptable. Therefore, they were
disregarded.
Plant 123 - Figure VII-34 (Combination)
The rinsewaters from this combination acid pickling operation (sample
point D) are combined with other pickling and hot mill wastes prior to
entering a central treatment system. The combined waste stream then
undergoes equalization, neutralization with lime, flocculation with
polymers, and clarification. Sludges produced are dewatered in vacuum
filters. Spent acid solutions are hauled off-site by private
contractors.
Plant 125 - Figure VII-45 (Combination)
This operation treats its pickle rinse and fume hood scrubber blowdown
water in a three-compartment lime neutralization pit prior to
discharging these wastes to a POTW.
262
-------
TABLE VII-1
OPERATING MODES, CONTROL AND TREATMENT
TECHNOLOGIES AND DISPOSAL METHODS
Symbols
Operating Modes
1. 0T
Once-Through
2. Rt,s,n
Recycle, where t
* type waste
s
* stream recycled
n
* Z recycled
t:
: U = Untreated
T ¦ Treated
s
n
P
Process Wastewater Z of
raw waste flow
F
Flume Only Z of
raw waste flow
S
Flume and Sprays Z of
raw waste flow
FC
Final Cooler Z of
FC flow
BC
Barometric Cond. Z of
BC flow
VS
Abs. Vent Scrub. ! of
VS flow
FH
Fume Hood Scrub. Z of
FH flow
3. REt,n
Reuse, where t ¦
type
n ¦
Z of raw waste flow
t:
U ¦ before treatment
T ¦ after treatment
4. BDn
Blowdown, where n ¦ discharge as % of
raw waste flow
Control Technology
10. DI
Deionization
11. SR
Spray/Fog Rinse
12. CC
Countercurrent Rinse
13. DR
Drag-out Recovery
Disposal Methods
20. H
21. DW
Haul Off-Site
Deep Well Injection
263
-------
TABLE VII-1
OPERATING MODES, CONTROL AND TREATMENT
TECHNOLOGIES AND DISPOSAL METHODS
PAGE 2
C. Disposal Methods (cont.)
22.
-------
TABLE VII-1
OPERATING MODES, CONTROL AND TREATMENT
TECHNOLOGIES AND DISPOSAL METHODS
PAGE 3
D. Treatment Technology (cont.)
43. FLt Flocculation, where t = type
t: L = Lime
A = Alum
P = Polymer
M * Magnetic
0 = Other, footnote
44. CY Cyclone/Centrifuge/Classifier
44a. DT Drag Tank
45. CL Clarifier
46. T Thickener
47. TP Tube/Plate Settler
48. SLn Settling Lagoon, where n = days of retention
time
49. BL Bottom Liner
50. VF Vacuum Filtration (of e.g., CL, T, or TP
underflows)
51. Ft,m,h Filtration, where t ¦ type
m * media
h ¦ head
t m h
D ¦ Deep Bed S ¦ Sand G ¦ Gravity
F ¦ Flat Bed 0 ¦ Other, P ¦ Pressure
footnote
52. CLt Chlorination, where t » type
t: A ¦ Alkaline
B ¦ Breakpoint
53. CO Chemical Oxidation (other than CLA or CLB)
265
-------
TABLE VII-1
OPERATING MODES, CONTROL AND TREATMENT
TECHNOLOGIES AND DISPOSAL METHODS
PAGE 4
D. Treatment Technology (cont.)
54. BOt Biological Oxidation, where t = type
t = type
t: An ¦
Activated Sludge
n =
No. of Stages
T -
Trickling Filter
B «
Biodisc
0 -
Other, footnote
55. CR Chemical Reduction (e.g., chromium)
56. DP Dephenolizer
57. ASt Ammonia Stripping, where t * type
t: F = Free
L * Lime
C * Caustic
58. APt Ammonia Product, where t ¦ type
t: S ¦ Sulfate
N ¦ Nitric Acid
A * Anhydrous
P * Phosphate
H ¦ Hydroxide
0 ¦ Other, footnote
59. DSt Desulfurization, where t ¦ type
t: Q = Qualifying
N ¦ Nonqualifying
60. CT Cooling Tower
61. AR Acid Regeneration
62. AU Acid Recovery and Reuse
63. ACt Activated Carbon, where t ¦ type
t: P * Powdered
G " Granular
64. IX Ion Exchange
65. RO Reverse Osmosis
66. D Distillation 266
-------
TABLE VII-1
OPERATING MODES, CONTROL AND TREATMENT
TECHNOLOGIES AND DISPOSAL METHODS
PAGE 5
D. Treatment Technology (cont.)
67. AA1 Activated Alumina
68. OZ Ozonation
69. UV Ultraviolet Radiation
70. CNTt,n Central Treatment, where t ¦ type
n ¦ process flow as
Z of total flow
t: 1 " Same Subcats.
2 ¦ Similar Subcats.
3 ¦ Synergistic Subcats.
4 ¦ Cooling Water
5 * Incompatible Subcats.
71. On Other, where n ¦ Footnote number
72. SB Settling Basin
73. AE Aeration
74. PS Precipitation with Sulfide
267
-------
TABLE VII-Z
SUMMARY OF ANALYTICAL DATA FROM SAMPLED PLANTS
SULFURIC ACID PICKLING - BATCH PROCESS
GROSS RAN AMD EFFLUENT WASTEWATERS - CONCENTRATIONS AND LOADS
Saw Waatewater
Plant
: Coda
I-2( 1)
I-2( 2)
0-2
P-2
0-2
Raferance No.
0856P
08S6P
0590
0312
0894
Sanpla Point a
7
3
1
1
3
Flow
(gal/ton)
207
465
18
16.9
8.0
Paraaatara
Iba/iuuu iba
all
lb*/1000 lbf
J!SZi
lt»/1000 lba
ag/1
lbs/1000 lba agjl"
lba/1000 lba
Dissolved
350
0.302
36
0.070
43,000 3.23
6,500 0.459
3,500 0.117
Iron
0.12
18
Suspended
113
0.0977
65
0.0014
749
0.0528
20
0.00067
Solida
0.028
Oil and
4.3
0.0037
14,4
12
0.00091
11
0.00078
0.6
0.00002
Crease
pH, Unica
2.4-2.
,6 -
2.9-6
.4 -
<1.0
-
1.J-!
L.6 -
1.9
-
11S
Arsenic
NA
NA
NA
NA
NA
MA
NA
MA
NA
NA
118
Cadaiua
NA
NA
NA
MA
MA
NA
NA
NA
NA
NA
119
Chroaiun
NA
MA
NA
NA
MA
MA
NA
NA
NA
NA
120
Copper
NA
NA
NA
NA
NA
KA
NA
NA
NA
NA
122
Lead
NA
NA.
NA
NA
MA
NA
NA
HA
NA
NA
124
Nickel
NA
NA
NA
NA
NA
MA
NA
MA
NA
NA
128
Zinc
NA
NA
NA
NA
MA
HA
NA
MA
NA
NA
Sffluenea
Treatment Tech.
SL
SL
AO
Nona
AD
Plant
: Coda
I—2< I)
1-2(2)
0-2
P-2
Q-2
Reference No.
0856P
085 6P
0590
0312
0894
Saapl
.a Points
7/(7+3 *2 <4) 5
3/<7+3*2-t4) 5
.
1
Streams Traatad
Rinses
Rinaaa
Rinaaa
i Concencraces
Rinaaa
Rinaaa
: & Concentrates
Flow (gal/ton)
207
465
0
16.9
0
Par an
latere
at/l
Iba/lUOO lba
V1
Ibe/1000 lba
¦ag/1
iwiKwr lba
qg/l
lba/iOOO
lba ag/l
lba/1000 lba'
Diaaolvad
0.03
0.0018
0.03
0.00041
Iron
Suapcndad
39
0.023
39
0.029
Zaro
Diract
Zaro
Solida
Oil and
Cresse
14
0.0068
14
0.0516
Diacharga
Diacharga
Diacharga
pB, Units
6.7
-
6.7
-
to
115
Arsanic
NA
NA
NA
NA
POTW
118
Cadaiua
NA
NA
NA
NA
119
Chroaiun
NA
NA
HA
NA
120
Coppar
NA
NA
NA
NA
122
Laad
HA
NA
MA
NA
124
Nickel
MA
NA
MA
MA
128
Zinc
NA
NA
NA
MA
268
-------
TABLE VII-2
SUMARY OF ANALYTICAL DATA FROM SAMPLED PLANTS
SULFURIC ACID PICKLING - BATCH PROCESS
GROSS SAW AND EFFLUENT WASTEWATER - CONCENTRATIONS AND LOADS
PACE 2
Raw tfaatevater
Plant Cod*
R-2
S-2
R
090
091
Reference No.
0240B
0256G
0240A
04 76A
0612
Sanple Pointa
2-7-6
3-4
11
C
r
Flov (gal/ton)
30.8
198
30
91
122
Parametera
¦§yi
lbe/1000 lba mgiI
Iba/iuoo lba
¦K/l lba/1000 lba
Si!!
lba/1000 lb*
a|/l
lba/1000 lba
Diaaolvad
1850
0.238
596
0.491
(990 1.126
393
0.150
2350
1.20
Iron
Suspended
3688
0.474
159
0.131
1.
3 0.00016
10
0.0038
96
0.0092
Solida
Oil and
665
0.0855
21
0.017
1.
3 0.00016
26
0.0099
It
0.049
Greaaa
pB, Onita
2.0
-
2.2
-
1.
6
1.7-2
.5 -
1.8
-
115 Araenic
NA
NA
NA
NA
NA
NA
MA
NA
M
NA
118 Cadmium
NA
NA
NA
NA
NA
NA
*
Neg
0.020
0.000010
119 Chromium
NA
NA
NA
NA
NA
NA
0.37
0.00014
3.8
0.0019
120 Copper
NA
1H
NA
NA
NA
1U
0.39
0.00015
0.63
0.00032
122 Lead
NA
NA
NA
NA
NA
NA
•
Neg
0.21
0.00011
124 Nickel
NA
NA
NA
NA
m
IU
0.44
0.00017
0.80
0.00041
128 Zinc
NA
na
NA
HA
NA
HA
59
0.022
27
0.014
Effluenta
Treatment Tach.
SL, E
None
SL,RL
E, AE, NLfCL, FLP
R, M., CL.m
Plant Code
R-2
S-2
R
090
091
Reference No.
0240B
0256G
0240A
0476A
0612
Saapl a Point a
(2-7-6)/(2«9) 3
-
-
(C/E)G
F/(#+C*D»B) H
Streama Treated
Kinaaa
Rioaea
Rlnaea t Concentrate*
Rin*e* Rin**a
t Concencrac*
Flo* (gal/ton)
30.8
o
0
9.1
122
Paraaetera
mg/1
lb*/100Q lba
¦g/l
lba/1000 lba
ac/1 lba/1000 lba
aii
lba/1000 lba
¦|/1
Ibe/IQOO lb*
Diaaolvad
0.04
Reg
Ccaplete
Ccaplete
0.050
0.00012
0.37
0.0086
Iron
Suapended
82
0.000057
Recycle
bfouokast
4
0.000066
11
0.00066
Soli da
Oil and
9
Reg
Operation
via
U
0.0040
4
0.0038
Graeae
pR, Onita
11.4
-
Lagoon*
6.6-9.
.0
8.3-8
.5
115 Araenic
NA
NA
NA
NA
NA
NA
113 Cadaiia
NA
NA
*
Reg
0.020 0.000085
119 ChroniuB
NA
NA
•
Reg
0.04
0.00059
120 Coppar
NA
NA
0.030
0.000030
0.03
0.00110
122 Laad
NA
NA
*
Meg
0.19
0.000010
124 Nickel
NA
MA
0.030
0.000034
0.03
0.00026
128 Zinc
NA
NA
0.060
0.00030
0.13
0.000070
269
-------
TABLE VII-2
SOIMAK? OF ANALYTICAL DATA FROM SAMPLED PLANTS
SULFURIC ACID PICKLING - BATCH PROCESS
GROSS RAH AMD EFFLUENT WASTEWATER - CONCENTRATIONS AND LOADS
PACE 3 ¦
Raw Wastewater
Plane Code
Reference No.
Saaple Poinea
092
0088A
F-D
326
096
01121
0
604
098
0684 D
I
12.2
Average
248
Par Meters
ag/1
"Ibe/1000"Iba
Wf/l
lbe/1000 Iba
¦t/r
-TE./1000"TT).
¦$/l
—ISsTTOM' Iba
Diaaolved
51.7
O.0704
97
0.24
2900
0.15
5432
0.603
Iron
Suapended
361
0.492
127
0.320
32
0.00020
418
0.131
Solida
Oil and
42.8
0.0582
16
0,040
4
0.0016
64.3
0.022
Grease
pH, Unite
5.9-6.9
-
3.2-3.7
-
1.8
-
1.0-6,
,4 -
115
Arsenic
0.39
0.00053
HA
HA
0.34
0.000017
0.37
0.00027
118
Cadaium
3.96
0.0054
*
Me(
0.14
Nag
0.83
0.0011
119
Chromium
16.3
0.022
0.100
0.00025
4.8
0.00024
5.07
0.0049
120
Copper
0.74
0.0010
0.200
0.00050
4.1
0.00021
1.21
0.00044
122
Lead
ND
HD
0.019
0.00048
2.06
0.00011
0.49
0.00014
124
Nickel
1.4
0.0019
0.090
0.00023
7.5
0.00038
2.05
0.00062
128
Zinc
3.9
0.0053
15
0.038
1.3
0.000066
21.2
0.016
Effluent!
Treatment Tech.
Plane Code
Reference No.
Saaple Poinea
Streaae Treated
EICR,NL,PLP,CL, T,VF
092
0O88A
(F-0)/(r*C*H) I
Rinaea
326
AE, NL.CL.F,
096
01121
D
-------
TABLE VII-2
SUM4ARY OF ANALYTICAL DATA FROM SAMPLED PLANTS
SULFURIC ACID PICKLING - BATCH PROCESS
GROSS RAW AND EFFLUENT WASTEWATER - CONCENTRATIONS AND LOADS
PAGE 4
FOOTNOTES
NA : Not analyzed.
ND : Not detected.
Neg: Calculated vaateload <0.000010 lba/1000 lb».
* : Concentration* <0.010 ag/1.
Negative reaulta were obtained when contributing acreama arc aubtracted frov the atream.
TreaOaent Tech. Code
AE : Aeration
AU I Acid recovery
CC : Countercurrent rinae
CR : Chemical reduction
E ¦ Equalisation
F i Filtration
FLP : Flocculation with polymer
FDBSi Filtration - Deep Bad Sand
NA Not analysed
NL : Neutralization with Lime
CL : Sedimentation via clarifier
SL : Sedimentation via lagoon
T : Sedimentation via thickener
VF : Vacutaa filtration
(1) No. 4 pickling operation
(2} No. 3 pickling operation
271
-------
TABLE VII-3
SUMMARY OF ANALYTICAL DATA FROM SAMPLED PLANTS
SULFURIC ACID PICKLING - BATCH PROCESS
GROSS RAH SPENT CONCENTRATES - CONCENTRATIONS AND LOADS
Raw Wastewater
P-2
R-2
091
092
Kj
to
Reference Ho.
0312
0894
0240 B
0612
0088A
Sanple Points
3
1
6
R
C
Average
Flow (gal/ton)
17.6
24.3
10.5
3.5
14.6
14.1
Paraieters
¦g/1
lbs/lOM lbs
¦g/1
lbs/1000 lbs
-g/1
^bs/1000 lbs
¦g/1
lbs/1000 lbs
¦g/ 1
lbs/1000 lbs
¦g/1
lbs/1600
Dissolved
46,800
2.93
61,900
6.27
67,800 2.97
63,000
0.921
38,500 2.38
55,600 3.09
Iron
Suspended
26.0
0.00016
1420
0.144
70
0.0031
2520
0.837
306
0.187
868
0.234
Solids
Oil & Grease
HA
0.00018
14
0.0014
NA
NA
11
0.00016
17
0.0010
15.3
0.00069
pH
1.4
-
<1
-
2.0
-
<1
-
<1
-
<1-2.
0
115
Arsenic
HA
NA
MA
MA
NA
NA
NA
NA
0.17
0.000010
0.17
0.000010
118
Cadtaiua
HA
MA
NA
HA
NA
NA
0.26
Neg.
0.28
0.000017
0.27
Neg.
119
ChroaiuB
!U
ha
MA
NA
NA
NA
269
0.00393
205
0.0725
237
0.0082
120
Copper
HA
MA
MA
HA
NA
NA
2.6
0.000038
4.7
0.00029
3.7
0.00016
122
Lead
NA
NA
MA
MA
NA
RA
1.6
0.000023
•
Neg.
0.81
0.000012
124
Mickel
DA
MA
NA
HA
NA
HA
23
0.00034
27.0
0.0016
25
0.00097
128
Zinc
NA
MA
HA
MA
RA
NA
16
0.00023
133
0.0087
74.5
0.0042
RA Mot analysed
Meg.: Hasteload leas than 0.000010 lha/1000 lbs
* : Concentration is less than 0.010 ag/l
-------
TABU WI-4
SOHMUY OP ANALYTICAL DATA FROM UWUD PLAHTS
SUtrOtlC ACID PICXLHG - OOHTIRUODS PBOCESS
qtOSS 1AH AMP EFFLBBHT WASTEVATgtS - COWCEHmTIOWS AND LOADS
taw Waetevater
Plant Code
Reference Bo.
Saaple Pointa
Floe ((al/taa)
H-2<»
0432A
3
103
H-2<»
0432A
4
11.5
T-2
0792 B
1
21.6
QQ-2
05848
5
167
SS-2
0112A
2
202
Para
act era
sll
Ibe/tOOO lba
5^1
lba/1000- lba
ad
lba/MHJU lba
a11
lba/1000 lba
3d
lba/1000 lba
Diaeolved
55
0.024
0.02
¦eg.
1833
0.165
83
0.058
63
0.053
Iron
Seapeaded
28
0.012
20
0.00096
49
0.0044
35
0.024
76
0.064
Solida
Oil aad
11
0.0047
11
0.00053
5.0
0.00045
2
0.0014
2
0.002
Creaae
pi, Oaite
1.9
-
6.4
-
1.6
-
2.7
-
2
-
115
Araeaic
HA
HA
HA
HA
HA
HA
HA
HA
HA
HA
US
Cadaliaa
HA
HA
HA
HA
HA
HA
HA
HA
HA
HA
119
Chroaiua
HA
HA
HA
HA
HA
HA
HA
HA
HA
HA
120
Copper
M
HA
HA
HA
HA
HA
HA
HA
HA
HA
122
Lead
H
HA
HA
HA
HA
M
HA
HA
HA
HA
124
Hckel
M
M
HA
HA
HA
HA
HA
HA
HA
HA
128
Ziac
HA
HA
HA
HA
HA
HA
HA
HA
HA
HA
to
CJ
Ifflnwti
Treitant Tech.
Plant Code
Reference Re.
8«apl e Points
Streaae Treated
Flo. (gal/toe)
Par act era
FLL, HL, riP.CL.T, VP
H-2
0432A
¦izr
tinaea
- 103
Ibe/IOM lba
FLL,N.,fLf^L,T,VF
M32A
tinaea
11.5
^71 lbe/lOW lba
T-2!
0792It
tinaea
C*,CC,n, M..CL, SL
W-2
0584 E
5/(6+2) 7
Concentrate! 1 tinaea
0 167
¦t/1 lbe/tOWTTEr ^7T—Ibe/IMO lb.
hl, a, ne, t, sl, ss
SS-2
0112A
1/(1*1*7) 9
Rinaea 4 Fiaae
Hood Scrubber
202
¦g/i iba/nnw~rtr
Diiiolved
0.04
Neg.
0.04
0.0003
Iroa
Suspended
Direct
Direct
Complete
1
0.00015
43
0.014
Sol Ida
Discharge
Discharge
Oil fc
to
to
Recycle
3
0.000056
6
0.00021
Grease
Teniae!
Tendnal
pB, Unit*
Treats ent
Treatment
System
7.5
-
7.7
-
115
Arsenic
Where
Where
NA
NA
NA
HA
118
Cadaitn
No Saiples
Ho S«ples
NA
NA
NA
NA
119
Chroaiusi
Were
Were
NA
NA
NA
NA
120
Copper
Taken
Taken
NA
NA
NA
NA
122
Lead
NA
NA
NA
NA
124
Nickel
NA
NA
NA
NA
128
Ziac
NA
NA
NA
NA
-------
TABLE VII-4
SUMMARY OF ANALYTICAL DATA FROM SAMPLED PLANTS
SULFURIC ACID PICKLING - CONTINUOUS PROCESS
GROSS RAU AND EFFLUENT WASTEWATERS - CONCENTRATIONS AND LOADS
PAGE 2
Raw Wastewater
Plant Code
TT-2
WW-2
o*<3>
094 <*>
097
Reference No.
0856D
0868A
0948C
0948C
0760
Saaple Points
1
1
C
D
E+B
Average
Flew (gal/ton)
134
284
303
422
11.1
166
Parameters
mg/i lbs/1 000 lbs
mg/1
lbs/1 WO lbs
¦g/1
lbs/1000 lbs
¦g/1
lbs/1000 lbs
¦8/1
lbs/1000 lbs
¦g/i
lbs/1000 lbs
Dissolved
81.9 0.0458
357
0.423
40
0.051
98
0.17
29, 780 1.38
6071
0.414
Iron
Suspended
7.0 0.003 9
6.1
0.0072
38
0.048
37
0.065
501
0.0232
118
0.029
Solids
Oil and
2.4 0.0013
1.6
0.0019
9
0.011
14
0.025
33.4
0.00155
12.1
0.0082
Grease
pHt Units
1.8
1.7
-
3.2-
-
2.2-
-
NA
-
1.7-
-
5.7
2.3
5.7
115 Arsenic
NA NA
NA
NA
*
0.000013
*
0.000018
0.17
Neg.
0.064
0.000010
118 Cadmium
NA NA
NA
NA
*
0.000013
*
0.000018
0.302
0.000014
0.107
0.000014
119 Chroaita
NA NA
NA
NA
*
0.000013
0.05
0.000088
2.0
0.000093
0.687
0.000005
120 Copper
NA NA
NA
NA
0.055
0.000070
0.14
0.00025
2.4
0.000111
0.865
0.00014
122 Lead
NA NA
NA
NA
0.04
0.000051
*
0.000018
1.0
0.000048
0.35
0.000039
124 Nickel
NA NA
NA
NA
0.06
0.000076
0.011
0.000019
13.8
0.00064
4.62
0.00025
128 Zinc
NA NA
NA
NA
0.04
0.000051
0.09
0.00010
1.8
0.000085
0.64
0.000099
Effluents
Treatment Tech.
Evaporation Pond
FLP, FLA, H,CL, SS, SL
E, S
!S,TI(Hf,NL
E, FLP, SS*\T, NL Evaporatiw
n,Crys talligation
Plant Code
T-2
WW-2
094137
094
097
Reference No.
0856D
0868A
0948C
0948C
0760
Sample Points
-
(1/4)5
(C/G)H
(D/G)H
F*G
Streams Treated
Rinses, 4 Ftme Rood
Rinses
Rinses
Rinses
Rinses
Scrubbers
Flow (gal/too)
134
28t
303
422
11.0
Parameters
wfj 1 lbs/1000 lbs
¦s/1
lbs/1000 lbs
¦g/1
lbs/1000 lbs
lbs/1000 lbs
«g/1
lbs/1000 lbs
Dissolved
Di rect
0.17
0.0007
0.050
0.000040
0.050
0.0003
465
0.0834
Iron
Discharge
Suspended
to
15
0.0006
6
0.00047
6
0.0013
7.5
0.00131
Solids
Receiving
Oil and
Stream
8.5
0.00007
6
0.00047
6
0.00091
9.3
0.0017
Grease
pR, Units
8.0
-
7.6-
-
7.6-
-
NA
-
7.8
7.8
115 Arsenic
NA
NA
*
0.000013
~
0.000018
0.010
Neg.
118 Cadtaium
NA
NA
*
0.000013
*
0.000018
0.012
Neg.
119 Chromiiai
NA
NA
0.020
0.000013
0.020
0.000053
ND
ND
120 Copper
NA
NA
*
ND
*
0.000018
0.139
0.000025
122 Lead
NA
HA
*
0.000051
*
0.000018
0.040
Neg.
124 Nickel
NA
NA
0.040
0.000051
0.040
0.000018
0.094
0.000017
128 Zinc
NA
NA
0.070
0.000020
0.070
0.000062
0.059
0.000011
-------
TABLE VII-4
SUMfAR OF ANALYTICAL DATA FROM SAMPLED PUNTS
SULFURIC ACID PICKLING - CONTINUOUS PROCESS
GROSS RAH AMD EFFUJBRT WASTEWATERS - CONCENTRATIONS AMD LOAD6
PAGE 3
FOOniOTES
(1) Spray tine
(2) Cascade tine
(3) Sheet Pickling Operation
(4) Strip Pickling Operation
Treatment Tech Code
AE t Aeration
CC t Counter cur rent rinse
CR : Cheaical reduction
E I Equalization
EB t Eaulaion breaking
FLA: Flocculation with ilia
FLL: Flocullation with lime
MD Rot detected
RA : Rot analysed
Reg.: Waateload is less than 0.000010 lbs/1000 lbs
* I Concentration is less than 0.010 mg/1.
FLPi Flocculation with polymer
Hi t Neutralization with liae
CL s Sedimentation via clarifier
SS: Skiaing
SL : Sedimentation via lagoon
T i Sedimentation via thickener
VF i Vacuum filtration
-------
TABLE VII-5
Raw Wastewater
SUMMARY OF ANALYTICAL DATA FROM SAMPLED PLANTS
SULFURIC ACID PICKLING - CONTINUOUS PROCESS
GROSS RAW SPENT CONCENTRATES * CONCENTRATIONS AND LOADS
Plant Code
H-2
T-2*
QQ-2
SS-2
TT-2
Reference No.
0432A
0792B
0584 E
0112A
0856D
Sampling Points
2
2
1
4
Flow
(gsl/ton)
14. 7
14.6
23.
,6
10.9
23
Paraaet ers
sig/1 lbs/1000 lbs
mg/l lb./1000 lbs
mg/l
lbs/1000 lbs
mg/ 1 lbs/1000 lb*
mg/l
lbs/1000 lbs
Dissolved
47,
900 2.93
34,
000 2.07,
48, 300
4.76
48,
000 2.18
70,800 6.8
Iron
Suspended
17,
000 1.04
65
0.0040
128
0.126
200
0. 0091
222
0.0213
Solids
Oil &
NA
NA
18
0.0011
8.5
0.008
9.5
0.00043
18.5
0.00178
Grease
pH
<1
-
<1
-
<1
-
<1
-
<1
-
115
Arsenic
MA
NA
NA
NA
NA
NA
NA
NA
NA
NA
116
Cadmium
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
119
Chroqium
HA
NA
NA
NA
NA
NA
NA
NA
NA
MA
120
Copper
NA
NA
MA
NA
NA
NA
NA
NA
NA
NA
122
Lead
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
124
Nickel
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
128
Zinc
NA
NA
HA
NA
NA
NA
NA
NA
NA
NA
Raw Wastewater
Plant Code
Reference No.
Sanpling Points
Flow (gal/ton)
WW-2
0868A
2
44. 7
097
0760
E
7.2
Average Flow
19.8
Parameters
mg/ 1
lbs/1000
lbs mg/l
lbs/1000 lbs
Average Average
mg/l lbs/1000 lbs
Dissolved
19,000
3.55
46,000
1.4
44,860
3.4
Iron
Suspended
91
0.0170
320
0.0096
2,575
0.175
Solids
Oil I
10
0.00187
46
0.0014
18
0.0012
Grease
pH
<1
-
<1
-
<1
-
115
Arsenic
NA
NA
0.18
Nag
0.18
Nag
118
Cadmium
NA
NA
0.46
0.000014
0.46
0.000014
119
Chromium
NA
NA
30.0
0.00090
30.0
0.00090
120
Copper
NA
NA
3.0
0.000090
3.0
0.000090
122
Lead
NA
NA
1.6
0.000048
1.6
0.000048
124
Nickel
NA
NA
21
0.00063
21
0.00067
128
Zinc
NA
NA
2.8
0.000084
2.8
0.000084
NA : Not analyzed.
Neg: Wasteload value is less than 0.000010 lbs/1000 lbs.
* : Acid Recovery plant with zero discharge.
276
-------
TABLE VII-6
SUMMARY OF ANALYTICAL DATA FROM SAMPLED PLANTS
SULFURIC ACID PICKLING - CONTINUOUS PROCESS
GROSS SAW FUME HOOD SCRUBBER WASTEWATER - CONCENTRATIONS AND LOADS
Raw Wastewater
Plant
Code
QQ-2
SS-2
TT-2
Reference No.
0584 E
0112A
856D
Staple Points
3
3-»4+5
2
Average Flow
Flow (gal/ton)
2
22.6
2.3
9.0
Average
Average
Par®
leter
¦g/1
lbs/1000 lbs
mg/1
lbs/1000 lbs
mg/1
lbs/1000 lbs
mg/1
lbs/1000 lbs
Dissolved Iron
305
0.00255
0.55
0.000052
88.7
0.000852
131
0.00115
Suspended
2.5
0.000021
7.5
0.0007)
198
0.00190
69.3
0.00088
Solids
Oil and Grease
2.5
0.000021
2
0.0019
9.0
0.000086
4.5
0.000099
pH, Units
1.4
-
1.9
-
1.7
-
1.4-1.9
-
US
Arsenic
NA
NA
NA
NA
NA
NA
NA
NA
118
CaAiiiza
NA
NA
NA
NA
NA
NA
NA
NA
119
Chroaiw
NA
NA
NA
NA
NA
NA
NA
NA
120
Copper
NA
NA
NA
NA
NA
NA
NA
NA
122
Lead
NA
NA
NA
NA
NA
NA
NA
NA
124
Nickel
NA
NA
NA
NA
NA
NA
NA
NA
128
Zinc
NA
NA
NA
NA
NA
NA
NA
NA
HA: Mot analyzed
-------
TABLE VII-7
SUMMARY OF ANALYTCIAL DATA FROM SAMPLED PLANTS
HYDROCHLORIC ACID PICKLING - BATCH PROCESS
CROSS RAW AND EFFLUENT WASTEWATERS - COR CENT RAT IONS AND LOADS
Raw Wastewater
Plant Code
Reference No.
Sanpling Points
Flow (gal/ton)
U-2
0480A
1
92.9
V-2
0936
1+6
167.2
Aver age
130,1
Parameters
¦g/1
lbs/1000 lbs
iag/1
lbs/I000 lbs
r j/1
lbs/lQOft lbs
Dissolved Iron
190
0.074
270
0.188
230
0.131
Suspended Solids
0
0
0
0
0
0
Oil and Grease
3
0.0012
1.5
0.0010
2.3
0.0011
pH, Units
1.8
-
2.5-3.4
-
l.fc-3.4
-
23
Chloroform
NA
NA
NA
NA
NA
NA
114
Antimony
NA
NA
NA
NA
HA
NA
115
Arsenic
NA
NA
NA
NA
NA
NA
118
Cadaiui
NA
NA'
NA
NA
NA
NA
119
Cfaroniun
NA
NA
NA
NA
NA
NA
120
Copper
NA
NA
NA
NA
NA
NA
122
Lead
NA
NA
NA
NA
NA
NA
124
Nickel
NA
NA
NA
NA
NA
NA
126
Silver
NA
NA
NA
NA
NA
NA
128
Zinc
RA
NA
HA
NA
NA
NA
-------
TABLE VII-7
SCMfARf OF AKALYTCIAL MTA FROM SAMPLED P LASTS
HTDBOCKjOKIC ACID PICKLING - BATCH PROCESS
GROSS RAW AND EFFLUBKT WASTEWATERS - COHCEKTRATIOSS AND LOADS
PAGE 2
fo
VD
Effluents
Treataent Technology
N.<»
Plant Code
0-2
Reference No.
04 80 A
Ssapling Points
-
Streaas Treated
Rinses
Flow (gal/too)
92.9
Parameters
¦g/1
lbs/1000 lbs
mg/1
Dissolved Iron
0.50
0.00020
261
Suspended Solids
385
0.149
195
Oil and Grease
5
0.00191
13
pH, Units
8.5
-
3.4*+. 5
23 Chi or of or*
NA
na
NA
114 Antiaooy
MA
NA
NA
115 Arsenic
NA
NA
NA
119 Chroaiua
NA
NA
NA
120 Copper
NA
NA
NA
122 Lead
NA
NA
NA
124 Nickel
NA
NA
NA
126 Silver
NA
NA
Mi
128 Zinc
MA
NA
NA
MA: Mot analysed.
(1) Neutralised with Soda Aah.
AB.NC
V-2
0936
4
Rinses
167.2
iWlOM
0.182
0.136
0.009
NA
NA
NA
NA
NA
NA
NA
NA
NA
-------
TABLE VII-8
SUMMARY OF ANALYTICAL DATA FROM SAMPLED PLANTS
HYDROCHLORIC ACID PICKLING - BATCH PROCESS
GROSS RAW SPENT CONCENTRATES - CONCENTRATIONS AND LOADS
Raw Wastewater
Plant Code
Reference No.
Sampling Points
Flow (gal/ton)
Parameters
ng/1
U-2
0480A
3
6.45
V-2
0936
7-m
3.86
lbs/1000 lbs
mg/1
lbs/1000 lbs
Average Flow
5.16
Average
mg/1
Average
lbs/1000 lbs
Dissolved Iron
77,000
2.06
107,000
1.72
92,000
1.89
Suspended Solids
40
0.0108
140
0.0022
90
0.0065
Oil and Grease
NA
NA
NA
NA
NA
NA
pH, Units
<1
-
<1
-
<1
-
23
Chlorofora
NA
NA
NA
NA
NA
NA
114
Antimony
NA
NA
NA
NA
NA
NA
115
Arsenic
NA
NA
NA
NA
NA
NA
118
Cadmium
NA
NA
NA
NA
NA
NA
119
Chromium
NA
NA
NA
NA
NA
NA
120
Copper
NA
NA
NA
NA
NA
NA
122
Lead
NA
NA
NA
NA
NA
NA
124
Nickel
NA
NA
NA
NA
NA
NA
126
Silver
NA
NA
NA
NA
NA
NA
128
Zinc
NA
NA
NA
NA
NA
NA
M: Not analyzed.
-------
TABLE VI1-9
SUMMARY OP ANALYTICAL DATA FROM SAMPLED PLANTS
HYDROCHLORIC ACID PICKLING - CONTINUOUS PROCESS
GROSS RAH i EFFLUENT WASTEWATERS - CONCENTRATIONS AND LOADS
Rao Wastewater
Plant Code
1-2
W-2
X-2
Y-2
Z-2
Reference Ho.
08S6P
**
006OB
**
0396D
S«plin| Points
4
7
3
5
1
Flow
(gal/ton)
220
228
663
87.3
166
«k/i
lbs/lOOOlbs
¦g/l
lbs/lOOOlbs
¦g/1
lbs/lOOOlbs
V1
lbs/lOOOlbs
¦g/1
Iba/lOOOlbs
Dia. Iron
7
0.0064
136
0.129
193
0.054
220
0.0802
11300
7.83
Sua. Solids
96
0.088
20
0.019
9
0.025
7
0.0026
72
0.050
Oil 4 Create
3.9
0.0036
14.8
0.014
ND
NO
3
0.0011
9
0.006
pH, Units
4.5-5.0
-
2.9-3.8
-
2.2-
¦2.6
1.7
-
1.1
-
023
Chloroform
HA
NA
NA
NA
NA
NA
HA
NA
NA
NA
114
Antiaoay
MA
NA
NA
NA
NA
NA
HA
NA
NA
NA
US
Arsenic
HA
HA
NA
MA
NA
NA
HA
NA
NA
NA
118
Cadniua
MA
NA
NA
NA
NA
NA
HA
NA
NA
NA
119
Chrosri.ua
¦A
NA
NA
NA
NA
NA
HA
HA
NA
NA
120
Copper
NA
NA
NA
MA
NA
NA
HA
NA
NA
NA
122
Lead
NA
NA
HA
NA
NA
NA
HA
NA
NA-
NA
124
Nickel
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
126
Silver
NA
NA
MA
NA
NA
NA
NA
NA
NA
NA
128
Zinc
NA
NA
NA
NA
NA
HA
NA
NA
NA
NA
**! Plant ha* ao reference auaber.
-------
TABLE VII-9
SUMMARY OF ANALYTICAL DATA FROM SAMPLED PLANTS
HYDROCHLORIC ACID PICKLING - CONTINUOUS PROCESS
GROSS RAW & EFFLUENT WASTEWATERS - CONCENTRATIONS AND LOADS
PAGE 2
Effluents
Treatment Tech.
SL
None
Plant Code
1-2
W-2
Reference No.
08S6P
-
Stapling Points
5
None
Streams Treated
Rinses
None
Flow
(gal/ton)
220
228
mg/1
lbs/lOOOlbs
mg/1 lbs/lOOOlbs
Dis. Iron
0.03
(1)
Sus. Solids
41
(1)
Discharge
Oil & Grease
14
(1)
to POTW
pH, Units
6.7
~
without
treatment
023
Chloroform
NA
NA
114
Antimony
NA
NA
115
Arsenic
NA
NA
118
Cadmium
NA
NA
119
Chromiua
KA
NA
120
Copper
NA
NA
122
Lead
NA
NA
124
Nickel
KA
NA
126
Silver
NA
NA
128
Zinc
NA
NA
None
None
X-2
Y-2
0060B
-
None
None
None
None
663
87.3
E, CL, NL, VF
Z-2
0396D
2
Rinses & Concentrates
166
lbs/10001ba mg/1 lbs/lOOOlbs mg/1 lbs/lOOOlbs
Direct
Discharge
wi thout
treatment
Discharge
to POTW
without
treatment
0.23
0.000162
36
0.0249
1
0.00069
8.1-8.6
-
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
-------
TABLE VII-9
SUMMIY OF ANALYTICAL DATA ttOH SAMPLED PLANTS
HTDCOCHLOK1C ACID PICKLING - COCTINUOOS PBOCESS
GKOSS IAW t EFFLDEKT RUSE WASTEWATERS - CONCBNTIATI0NS AND LOUS
PACE 3
Iw Waatevatar
to
09
CJ
Plaat Code
Kef are nee Bo.
Sapling Point*
AA-2
0384A
2
S.8S
M-2
0060
5
211
091
0612
K-F
328
093
0396D
UJ
234
095(2)
0584F
G+GA2+GA3
Iba/lOOOlba
¦g/1
Iba/lOOOlba
¦»/!
Iba/lOOOlba
Ibs/lOOOlbs
¦R/l
Ibs/lOOOlbs
Dia. Icon
14000
0.342
1100
0.969
~
+
3539
3.46
1591
0.164
Sua. Solida
21
0.00051
37
0.033
120
0.102
491
0.480
46.7
0.048
Oil 4 Grease
40
0.00098
59
0.052
~
+
249
0.243
2.8
0.00029
pi, Units
1.1
-
1.5-1.7
-
2.9-3.9
-
1.0
-
1.4-1.7
-
023
Chlorofora
HA
NA
NA
NA
~
+
*
NeS
0.03
Neg
114
Antiaony
NA
HA
NA
NA
ND
ND
NA
NA
0.13
0.000014
115
Arsenic
HA
HA
NA
NA
HO
ND
0.045
0.000044
0.16
0.000016
118
Cadaiiai
NA
NA
NA
NA
*
Neg
*
NeS
0.14
0.000014
119
Chroaiua
NA
NA
NA
NA
-
-
0.79
0.00075
0.035
Neg
120
Copper
NA
NA
NA
NA
0.20
0.00017
0.69
0.00067
0.633
0.000065
122
Lead
NA
NA
NA
HA
23.7
0.020
0.43
0.00041
0.42
0.000052
124
Nickel
HA
NA
NA
NA
0.126
0.00011
0.48
0.00043
0.035
Neg
126
Silver
NA
NA
NA
NA
NA
NA
0.027
0.000026
0.17
0.000018
128
Zinc
NA
NA
NA
NA
162
0.137
1.52
0.00149
0.42
0.000043
-------
TABLE VII-9
SUMMARY OF ANALYTICAL DATA FROM SAMPLED PLANTS
HYDROCHLORIC ACID PICKLING - CONTINUOUS PROCESS
GROSS SAW & EFFLUENT WASTEWATERS CONCENTRATIONS AND LOADS
PAGE 4
Effluent
NJ
03
Treatment Tech.
None
AE,FLP,CL,VF,SL,E
NL,
,FDS,VF,CL
NL, CL, VF, E
None
Plant Code
AA-2
BB-2
091
093
095
Reference No.
0384A
0060
0612
396D
0584F
Sampling Points
None
6(3)
(B-G-F) „
(J+B)
(B+E+C+D)
(D+B+F+J+E)
None
Streams Treated
None
Rinses
Rinses &
Rinses & Fume
Concentrations
Hood
Scrubber
None
Flow
(gal/ton)
5.85
211
328
234
24.7
¦g/1 lbs/lOOOlbs
mg/1 lbs/lOOOlbs
mg/1
lbs/10001bs
mg/1
lbs/lOOOlbs
mg/1 lbs/lOOOlbs
Dis. Iron
Disposed
0.004 (1)
0.365
0.00030
5.1
0.00073
Sus. Solids
via deep
2 (1)
11
0.0111
43.0
0.0156
Discharge to
Oil & Grease
wel 1
3 (1)
4
0.00076
5.5
0.0085
waste lagoons
pH, Units
injection
8.3-8.9
8.4
-
9.1
-
with no
treatment
023
Chlorofora
NA NA
*
+
~
Neg
114
Antimony
NA NA
NA
NA
NA
NA
115
Arsenic
NA NA
NA
NA
*
0.000011
118
Cadmium
NA NA
0.02
0.000055
0.02
0.000053
119
Chromium
NA NA
0.04
Neg
0.075
0.0010
120
Copper
NA NA
0.03
0.000075
0.17
0.000092
122
Lead
NA NA
0.19
0.0016
0.58
0.000030
124
Nickel
NA NA
0.03
0.000066
0.27
0.00017
126
Silver
NA NA
0.03
0.000080
0.09
0.000071
128
Zinc
NA NA
0.03
0.00041
0.25
0.000023
-------
TABLE VII-9
SUMMARY OF ANALYTICAL DATA FROM SAMPLED PLANTS
HYDROCHLORIC ACID PICKLING - CONTINUOUS PROCESS
GROSS RAH & EFFLUENT WASTEWATERS CONCENTRATIONS AND LOADS
PACE 5
Raw Wastewater
Plant Code
099
100
Reference No.
0528B
0384F
Saapling Points
C+E
C
Flow
(gal/ton)
215.6
37.6
mg/1
lbs/lOOOlbs
mg/1
lbs/lOOOlbs
Dis. Iron
409
0.37
35.0
0.0055
Sus. Solids
56.8
0.051
54.0
0.0085
Oil & Grease
7.8
0.0070
8.0
0.0013
pH, Units
NA
-
4.2
-
023
Chloroform
*
Neg
0.011
Neg
114
Antimony
NA
NA
0.10
0.000016
115
Arsenic
0.063
0.000056
NA
NA
118
Cadmium
*
Neg
*
Neg
119
Chromium
0.85
0.00076
0.030
Neg
120
Copper
0.47
0.00043
0.060
Neg
122
Lead
0.10
0.000090
0.050
Neg
124
Nickel
0.64
0.00057
0.020
Neg
126
Silver
0.02
0.000018
0.020
Neg
128
Zinc
0.60
0.00054
0.14
0.000016
Average
mg/1 lbs/lOOOlbs
2710
1.15
92.8
0.078
33.1
0.0274
1.1-5.0
-
0.012
Neg
0.076
0.000010
0.067
0.000029
0.034
0.000003
0.341
0.00030
0.41
0.000267
4.94
0.0041
0.26
0.00022
0.059
0.000016
32.9
0.028
-------
TABLE VII-9
SWMARY OF ANALYTICAL DATA FBOM SAMPLED PLANTS
HYDROCHLORIC ACID PICKLING - CONTINUOUS TROCESS
GROSS RAW & EFFLUENT WASTEWATERS CONCENTRATIONS AND LOADS
PACE 6
Effluent*
K)
CO
Treatment Tech
Plant Code
Reference No.
Sampling Points
Streams Treated
Flow (gal/ton)
Di». Iron
Sua. Solids
Oil i Grease
pB, Units
023 Chlorofoza
114 Antiaony
US Arsenic
118 Cadaius
119 Cbroaiua
120 Copper
122 Lead
124 Nickel
126 Silver
128 Zinc
AR.NL.SL
099
0528B
«>E> G
(C+E+D+N) "
Rinses, Fiae Hood
Scrubber & Adsorber
Vent Scrubber
215.6
¦k/1 ¦ lbs/lOOOlbs ag/1
0.19
11.0
15.5
7.0
¦D
HA
*
*
0.03
0.025
0.10
0.03
0.02
0.02
0.00024
0.0128
0.0144
ND
HA
0.000013
0.000013
0.000015
0.000071
Reg
Reg
0.000023
0.000011
CL
100
0384A
(C/G) I
Rinses
37.6
15.7
20.0
3.0
8.2
0.024
0.10
HA
*
0.03
0.02
0.05
0.035
0.02
0.47
lb»/10001bs
0.0177
0.0021
0.000077
Neg
Neg
MA
Neg
Neg
Neg
Neg
Neg
Neg
0.000013
-------
TABLE VII-9
SIMIARY OF ANALYTICAL DATA FROM SAMPLED PLANTS
HYDROCHLORIC ACID PICKLING - CONTINUOUS PROCESS
GROSS BAH & EFFLUENT WASTEWATERS CONCENTRATIONS AND LOADS
PAGE 7
FOOTNOTES
(1) No wasteload calculations possible due to contribution froa unknown streaaa.
(2) Untreated wastewater to waste lagoon not included in average.
(3) Includes tandea cold aill waste.
HA : Not analyzed
ND : Not detected
+ : Quantities determined by subtracting other atreaas yields negative values.
* : Concentration is less than 0.010 ag/1.
Neg: Wasteload is less than 0.000010 lb/1000 lbs.
Treatment Tech. Code
AE : Aeration
AR : Acid regeneration
E Equalization
FDS: Filtration deep bed sand
Flf: Flocculatioa with polyaer
ML: Neutralization with liae
CI: Sedimentation via clarifier
SL: Sedimentation via lagoon
VF: Vacuua filtration
to
00
-------
TABU VII-10
SUMMIT or ANALYTICAL DATA FUN 8AWLKD PLAKTS
HTDtOC&LOMC ACID PICKLIHC - OMTHODOS PROCESS
CROSS RAW SPCIfT CCHC8 ITT RATES - COHCK WIATIOWS AUD LOADS
Km Haitevttir
Pint Code -
Reference Ho.
Sampling Points
Plow (gal/ton)
~^rr
1-2
0856P
220
Iba/lOOOlba
"mHT
W-2
**
1
11.9
lbs/lOMlbs
"57T"
z-i
0396D
DNK
41.4
1 bt/100011m
SE7T"
AA-2
0384A
3
3.26
Iba/lMOlba
091
0612
L
18.1
¦gA lbg/lOOOlbg
Dissolved
7.1
0.0065
137700
13.7
44300
15.3
116000
3.14
56000
4.24
Iron
Suspended
54
0.049
97
0.0096
120
0.0414
40
0.0011
3026
0.229
Solids
Oil & Grease
HA
HA
5.1
0.00050
1
0.00035
20
0.00055
4.0
0.00030
pH, Doits
4.5-5.0
-
0. 6-0.7
-
<1
-
<1
-
<1
-
23
Chi or of on
NA
NA
NA
NA
NA
NA
NA
NA
*
Neg
114
Antiaooy
M
HA
NA
NA
HA
NA
NA
NA
NA
NA
115
Arsenic
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
118
Csdaita
NA
NA
NA
NA
NA
NA
NA
NA
0.28
0.000021
119
Cfaroain
HA
NA
NA
NA
NA
NA
NA
NA
37
0.0028
120
Copper
LMd
na
NA
NA
NA
NA
NA
NA
NA
22
0.0017
122
Hk
NA
HA
NA
HA
NA
NA
NA
1550
1.17
124
Nickel
HA
HA
NA
NA
NA
NA
NA
NA
22
0.0017
126
8ilver
HA
HA
NA
NA
NA
NA
NA
NA
0. 30
0.000023
12$
Zinc
M
NA
HA
NA
HA
NA
NA
NA
61
0.0046
-------
TABLE VII-10
BOMAHT or ANALTT1GAL DATA FBOM SAMPLED FLAWS
HTMOC&OUC ACID FICKLOK - COMTINDOUS P BO CESS
GROSS IAW SFUT OMICSHriATES
PAGE 2
law lutenater
Flat Cod*
093
095
hftrnct Bo.
0396D
0584T
Sampling Mat)
Ml)
>
Flan
' (*«l/too)
203
49.7
mt/l
llM/lOO01b*
¦f/1 .
lIX/lOOUltM
•f*
Diaiolwd
3950
3.35
8000
1.66
75,500
Iran
Suap*ad*d
240
0.203
74
0.015
42
Solid*
Oil 8 Gran*
237
0.201
4
0.00083
11
pa, Ooita
1.0
-
1.3-3.0
-
<1
23
Chi or of oca
*
0.101
0.000021
•
114
Aatiaony
m.
m.
0.187
0.000039
HA
IIS
Ananic
0.05
0.000042
0.025
—s
0.40
118
Cateiw
0.02
0.000017
¦D
ID
0.31
119
Oraia
0.84
0.00071
1.50
0.000031
18
120
Cofp*r
0.67
0.00057
2.42
0.00050
28
122
L**d
0.43
0.00036
¦D
K>
*
124
¦ickal
0.48
0.00041
2.50
0.00052
13
126
Silver
0.03
0.000025
n>
ID
0.31
128
Xiae
l.S
0.0013
2.50
0.00052
4.2
(1)> CaUal rimm k coraatrttM
¦D I lot datcctad
RA t lot
¦a«i latdori is laa¦ that 0.000010 lba/10001kw
* I Coacatritia 1* 1*m than 0.010 ag/1
~ t C«oaot b* ml«it«d
** i pint r*f*r*nc* cod* not uaifMl,
049
05281
*
81.7
lWlMOlhi
^7T
100
0384 A
k
4.65
"TGTTWBIK"
~ML
iu/lfl001b«-
15.8
18000 0.349
56723
7.50
0.014
316
0.00613
445
0.0631
0.0038
5
0.000097
35.9
0.0259
-
<1.0
-
<1-5.0
-
«•!
0.011
"*S
0.028
m
4.2
0.000082
2.19
0.00006)
0.00014
m.
¦A
0.158
0.000061
0.00011
0.28
¦ec
0.178
0.000030
0.0061
8.7
0.00017
13.2
0.00202
0.0096
11
0.00021
12.8
0.0025
"«
2.1
0.000041
310.5
0.234
0.0044
13
0.00025
10.2
0.0015
0.00011
0.39
He*
0.21
0.000032
0.0014
4.6
0.000089
14.8
0.00158
-------
TABU VII-U
SUMMARY OF ANALYTICAL DATA FROM SAMPLED PLANTS
HYDROCHLORIC ACID FICKLIHC - CONTINUOUS PROCESS
GROSS RAH FUME HOOD SOtUBBLER WASTEWATERS - CONCENTRATIONS AMD LOADS
Ran Wastewater
Plant Code
M
M
0396D
0584F
0528B
Reference Code
W-2
Y-2
093
095
099
Saspling Points
6
4
J
GA
F
Flow
(gal/ton)
45.5
39.7
31.1
0.386
6.1
mgj 1
lbs/lOOOlbs
¦8/1
lbs/lOOOlbs
¦g/1
lbs/10001 bs
¦8/1
lbs/10001bs
¦8/1
lbs/10001bs
Dissolved
23.9
0.0045
3.8
0.00063
880
3.55
733
0.00118
45
0.00115
Iron
Suspended
3.0
0.00055
6.7
0.00111
2132
8.61
21
0.000034
22
0.00056
Solids
Oil 1 Creese
5.3
0.0010
2
0.00033
330
1.33
46
0.000074
14
0.00036
pH, Units
2.8-3.7
-
1.8-1.
9
1.6
-
1.2
-
<1
-
23
Chi or of on
HA
NA
NA
NA
*
0.000040
0.369
Reg
*
Neg
114
Antimony
NA
NA
NA
NA
NA
NA
0.117
Heg
NA
NA
115
Arsenic
HA
NA
NA
NA
*
0.000040:
0.047
Neg
0.08
Neg
118
Cedkiia
NA
NA
MA
NA
*
0.000040
0.20
Meg
*
Heg
119
Chrflaiia
NA
NA
NA
NA
0.29
0.00117
0.35
Neg
0.09
Keg
120
Copper
NA
NA
NA
NA
0. 76
0.0031
0.503
Neg
0.10
Heg
122
Lead
NA
NA
NA
NA
0.35
0.0014
0.60
Neg
0.10
Heg
124
Nickel
NA
NA
NA
NA
0.20
0.00081
0.50
Heg
0.08
Heg
126
Silver
NA
NA
NA
NA
*
0.000040
0.25
Neg
0.02
Neg
128
Zinc
NA
NA
NA
NA
1.7
0.0069
0.35
Heg
0.11
Heg
-------
TABLE VII-11
SUMIARY OF ANALYTICAL DATA FROM SAMPLED PLANTS
HYDROCHLORIC ACID PICKLING - CONTINUOUS PROCESS
GROSS RAH FUME HOOD SCRUBBER WASTEWATERS - CONCENTRATIONS AND LOADS
PAGE 2
Raw Wastewater
Plant Code
Reference Code
Sampling Points
Flow (gal/ton):
ag/ 1
0384 A
100
J
3.37
lbs/lOOOlbs
mg/ 1
Average
21.0
lbs/1000lbs
to
¦JD
Dissolved
3210
0 . 0452
816
0. 600
I ron
Suspended
29
0. 00041
369
1.44
Solids
Oil & Grease
3
0.000042
66
0. 222
pH, Units
1.0-1.2
-
<1-3. 7
-
23
Chioroform
~
Neg
0. 100
0.000010
114
Antimony
0. 6
Neg
0.359
Neg
115
Arsenic
NA
NA
0.046
0.000020
118
Cadmium
0. 015
Neg
0.059
0.00010
119
Chromium
0. 72
0.000010
0.36
0.00030
120
Copper
1.7
0.000024
0. 77
0.00078
122
Lead
0.08
Neg
0.28
0.00035
124
Nickel
1.4
0.000020
0.55
0.00021
126
Silver
0.20
Neg
0. 12
0.000010
128
Zinc
0.45
Neg
0.65
0. 001 7
+ : Value determined by subtracting other contributing streams yielded a negative value.
NA : Not analyzed.
* : Concentration is less than 0.010 mg/1.
Neg: Wasteload is less than 0.000010 lbs/lOOOlbs.
** : Plant has no assigned reference number.
-------
TABLE VII-12
SUMMARY OF ANALYTICAL DATA FROM SAMPLED PLANTS
HYDROCHLORIC ACID PICKLING - CONTINUOUS PROCESS
GROSS RAW ABSORBER VENT SCRUBBER WASTEWATERS - CPU CERT RATIOKS AND LOADS
fo
id
NJ
Raw Wastewater
Plant Code
W-2
X-2
Y-2( 1)
Y-2( 2)
095
Reference No.
**
0060B
**
**
0584 F
Saapling Points
2
2
1
2
C
Flow
(gal/ton)
98.6
220
288
336
69
¦g/l
lbs/lOOOlbs
ng/ 1
lbs/lOOOlbs
®g/l
lbs/lOOOlbs
mg/ 1
lbs/lOOOlbs
®g / 1
lbs/10001bs
Dissolved
15
0.0062
63.5
0.072
+
+
0.41
0.00058
3670
1.06
Iron
Suspended
129
0.053
70
0.079
85
0.102
1.5
0.0021
194
0.0559
Solids
Oil & Grease
2.2
0.0009
+
+
~
+
•f
+
3
0.00086
pH, Units
3.7-7.6
-
6.9-7.1
-
7.0-7.1
-
1.7
-
1.7-2.1
-
23
Chi orof on
NA
NA
NA
NA
NA
NA
NA
NA
0.026
Neg
114
Antimony
KA
NA
NA
NA
NA
NA
NA
NA
0.22
0.000063
US
Arsenic
NA
NA
NA
NA
NA
NA
NA
NA
0.025
Neg
118
Cadaiut
NA
NA
NA
NA
NA
NA
NA
NA
0.02
Neg
119
Chroaita
NA
NA
NA
NA
NA
NA
NA
NA
0.58
0.000167
120
Copper
NA
NA
NA
NA
NA
NA
NA
NA
1.503
0.000423
122
Lead
NA
HA
NA
NA
NA
NA
NA
NA
0.60
0.00017
124
Nickel
NA
NA
NA
NA
NA
NA
NA
NA
0.790
0.00023
126
Silver
NA
NA
NA
NA
NA
NA
NA
NA
0.25
0.000072
128
Zinc
NA
NA
NA
NA
NA
NA
NA
NA
1.277
0.000368
-------
TABLE V11-12
SUMARY OF ANALYTICAL DATA FROM SAMPLED PLANTS
HYDROCHLORIC ACID PICKLING - CONTINUOUS PROCESS
GROSS RAH ABSORBER VENT SCRUBBER WASTEWATERS
PAGE 2
Raw Wastewater
Plant Code
Reference No.
Sampling Points
Flow (gal/ton)
099
0582B
F+E
176
Average
465
N>
ID
W
mg/1
lbs/lOOOlbs
mg/1
lbs/lMdlbs
Dissolved
150
0.11
650
0.207
Iron
Suspended
67
0.0492
91
0.0566
Solids
Oil & Grease
7
0.0051
2
0.0011
pH, Units
<1.0-2.3
-
<1.0-7.6
-
23
Chloroform
*
Neg
0.018
Neg
114
Antimony
NA
NA
0.22
0.000063
115
Arsenic
*
Neg
0.018
Neg
118
Cadmiua
*
Neg
0.015
Neg
119
Chromium
0.98
0.00072
0.78
0.00043
120
Copper
0.436
0.00032
0.97
0.00037
122
Lead
0.10
0.000073
0.35
0.00012
124
Nickel
0.64
0.00047
0.72
0.00034
126
Silver
*
Neg
0.13
0.000036
128
Zinc
0.73
0.00054
1.00
0.00044
(1): Acid regeneration unit with cyclone.
(2): Acid regeneration unit with electrostatic precipator.
Neg: Wasteload is less than 0.000010 lbs/1000 lbs.
NA : Not analyzed.
* : Concentration is less than 0.010 mg/1.
+ : Value obtained by substracting other contributing streams yielded a negative value.
** : Plant has no assigned reference number
-------
TABLE VII-13
SUMMAM OF ANALYTICAL DATA FROM SAMPLED PLANTS
COMBINATION ACID PICKLING - BATCH PROCESS
GROSS RAW AMD EFFLUENT WASTEWATERS - CCMCEOTRATIOHS AND LOADS
Raw Wastewater
Reference No.
0748
0424
0836H
0440A
Plant Cod*
U
C
F
L
Sample Point
1
2
1
10
Plow (gal/too)
677
91
279
140
Parameter*
¦gA
lbe/1000 lbs
Bg/1
lbs/1000 lba
all
1be/1000 lbs
lbs/1000 lbs
Suspended
4
0.0113
106
0.0402
8
0.0093
179
0.105
Solida
Oil and Create
3
0.0085
5
0.0019
0.7
0.0008
1.9
0.0011
Fluoride
soo
1.41
1,725
0.655
174
0.203
1.4
0.00082
Diaaolved Iron
1,080
3.05
216
0.082
61
0.07
135
0.0788
pH, Uniti
1.9
-
0.4-0.
8 -
2.6-2.
,9 -
2.8-3
.8 -
US Arsenic
NA
NA
NA
HA
NA
NA
NA
NA
119 Chroaim
132
0.429
137
0.032
13.4
0.0156
24.4
0.0142
120 Copper
1.38
0.0038
9.3
0.0036
0.06
0.000070
0.8
0.0005
122 Lead
*
Nag
NA
NA
*
Nag
*
Nag
124 Nickel
70
0.198
241
0.0915
9.4
0.0109
12.5
0.0073
128 Zinc
5.6
0.0158
0.87
0.003
0.07
0.000081
0.08
0.000047
Effluent
Plane Code
0
C
r(l>
L
Reference No.
-
0424
0856H
0440A
Sasple Point•
4
4
4
1
stream! Treated
Kins**
i Concentrates
linees
Kinses 6 Fuae Hood Scrub.
Xinaea
Treatment Tech.
KL, SL
(, NL, PSP
1,NL, SL
NW
Flew (gal/ton)
677
91
279
140
Par Meters
¦g/i
' TGs/IMO lbs
ail
lbs/1000 lb*
a/1
lba/1000 lba
lbt/1000 lb*
Suspended
12
0.0339
31
0.0118
430
0.50
119
0.0695
Solida
Oil and Graaae
1.0
0.0028
0.3
0.0001
1.6
0.0019
3.0
0.00175
Fluoride
12
0.0339
133
0.0303
68.7
0.0799
1.4
0.000817
Dissolved Iron
0.02
0.000037
8.3
0.0032
41.1
0.0478
0.1
0.000058
pH, Units
10.4
-
3.0
-
3.8
-
5.8
-
113 Arsenic
NA
NA
NA
HA
NA
NA
NA
NA
119 Chroaiua
0.04
0.0001
1.3
0.0003
7.3
0.0085
0.61
0.000356
120 Copper
0.03
0.00008)
0.0«
0.000030
0.07
0.000081
0.01
0.0000058
122 Lead
NA
NA
NA
HA
NA
NA
NA
NA
124 Nickel
0.02
0.000037
2.3
0.0093
6.7
0.0078
0.16
0.000356
128 Zinc
0.03
0.000085
0.033
0.000013
0.14
0.0016
0.01
Nag
294
-------
TABLE VII-13
SUMMARY OF ANALYTICAL DATA FROM SAMPLED PUNTS
COMBINATION ACID PICKLING - BATCH PROCESS
GROSS WASTEWATER - CONCENTRATIONS AND LOADS
PACE 2
Raw Haacevater
Reference No.
0088A
0088D
0884 E
Plant Code
123
124
125
Sample Point
D
B
C
Average
Fltw (gal/ton)
310
1176
650
475
Parameters
mg/ 1
lba/1000 lba
tag) 1
lba/1000 lba
lba/1000 lba
mg/ 1
lba/1000 lba
Suspended
36
0.0459
2
0.0098
3
0.0081
48.3
0.0319
Solid!
Oil and Graaae
5
0.00646
11
0.054
6
0.0163
4.6
0.0124
Fluoride
NA
NA
25
0.12
32
0.141
428
0.439
Diaaolved Iron
46
0. 0595
10
0.049
5
0.0136
222
0.486
pH, Units
2.6-2.7
-
2.7
-
3.5-3.
.6 -
1.9-3.
6 -
11S Araenic
0.01
0.000013
0.01
0.000049
0.01
0.000027
119 Chromitan
3.21
0.0042
6.2
0.0304
1.1
0.00298
48.1
0.078
120 Copper
0.26
0.000336
0.02
0.000098
0.08
0.000230
1.28
0.0011
122 Lead
0.10
0.000129
0.05
0.000245
0.05
0.000135
0.067
0.00017
124 Nickel
7.6
0.0099
27
0.132
0.56
0.00153
52.5
0.064
128 Zinc
0.08
0.000110
0.05
0.000245
0.02
0.000054
0.97
0.0024
Effluent
Plane Code
Reference No.
Sample Point a
Streama TreaCed
Treatment Tech.
Flow (gal/too)
123
0088A
(D/F+OH)xI
Rinaea 4 Concentrates
E| M«| FLPtCL
310
124
0088D
C
Rinaea
E,NC,FtsP
1176
125
0884 E
(C/C+F»D)*E
Rinaea i Fuse Rood
Scrubbera & Concen.
E, NL, FLP, PSP
650
Par meters
¦g/1
lba/1000 lba
mg/ 1
lba/1000 lba
¦J/J.
lba/1000 lba'
Suapended
28.5
0.00646
65
0.314
527
0.694
Solida
Oil and Creaae
8.50
0.00
5
0.0245
24
0.0434
Fluoride
NA
NA
10
0.0490
94.J
0.260
Diaaolved Iron
0.445
0.00129
ND
KD
0.04
0.00
pH, Units
7.9
-
11.9
-
11.9
-
115 Araenic
*
0.00
*
0.000049
*
0.000027
119 Chromiim
0.355
Neg
1.9
0.00932
10.6
0.0352
120 Copper
0.030
0.000026
0.03
0.000147
0.185
0.000542
122 Lead
0.100
+
0.050
0.000245
0.125
+
124 Nickel
0.325
0.000776
8
0.0392
6.79
0.0217
128 Zinc
0.115
Neg
0.495
0.00243
0.140
~
295
-------
TABU VXI-13
8CMUKY OF ANALYTICAL DATA FROM SAMPLED PLANTS
COMBINATION ACID PICKLING - BATCH PROCESS
RINSE WASTEWATER - CONCENTRATIONS AND LOADS
PAGE 3
FOOTNOTES
(1) Sample taken prior Co final tattling.
NA : Not analyzed.
ND : Not datectad.
Neg: Waateload is leaa than 0.000010 lba/1000 lbe
+ : Unable to calculate.
* : Concentration ia leaa Chan 0.010 Bg/1.
Treatment Tech. Code
E Equalization
FDSP: Deep bed eand preaaure filtration
FLT : Flocculation with polyner
NC t Neutralisation with cauatic
NL I Neutraliiation with live
MW I Neutrelixation with waste*
FSF s Friaarjr scale pit
SC I Sedimentation via clarifier
SL < Sediaeat ation via lagoon
296
-------
TABLE VII-14
Saw Waat.load
SUMMARY OF ANALYTICAL DATA FROM SAMPLED PUNTS
COMBINATION ACID PICKLING - CONTINUOUS PROCESS
GROSS RAW AMD EFFLUENT WASTEWATERS - CONCENTRATIONS AND LOADS
Plant Co
-------
TABLE VII-14
SUMMARY OF ANALYTICAL DATA FROM SAMPLED PLANTS
COMBINATION ACID PICKLING - CONTINUOUS PROCESS
RINSE WASTEWATER - CONCENTRATIONS AND LOADS
PACE 2 ___
Raw Wastewater
Flint Code
121
Reference No.
0900
Sanple Point*
B
Average
Flow (gal/ton)
2754
Pnaetert
mg/1
lbs/1000 lbs
mg/1
lbs/1000 lbs
Dissolved Iron
148
1.70
152.9
0. 968
Suspended Solids
14.3
0.164
180.8
1.26
Oil and Grease
6.3
0.0724
8.3
0.055
Fluoride
180
2.07
69.2
0.647
pH, Unit.
2.4-2.7
-
2.4-8.0
-
4 Benzene
0.049
0.00567
0.049
0.000567
119 Chromium
33.4
0. 383
24.9
0.264
120 Copper
0.59
0.00678
0.27
0.0027
124 Nickel
20
0.230
14.9
0.104
128 Zinc
0. 33
0.0038
0.39
0.0033
Effluent*
Plant Code
Reference No.
Sample Point*
Systens Treated
Treatment Technology
Flow (gal/ton)
Par am et era
Dissolved Iron
Suspended Solids
Oil and Grease
Fluoride
pH, Units
4 Benzene
119 Copper
120 Chromium
124 Nickel
126 Zinc
121
0900
4
Rinses, FHS and Concentrates
E, CLyCR
1338
¦K/*
-lbsTTOBff lb.
0.26
0.00145
8
0.0446
4.3
0.0247
9.5
0.0544
7.9
NA
0.033
0.000186
0.074
0.000413
0. 90
0.00503
0.37
0.00205
0.07
0.000391
NA: Not analysed.
NDi Not detected.
Treatment Tech* Code
CR : Chemical reduction
E : Equalisation
FLP: Flocculation with polymer
NL : Neutalisation with liae
CL : Sedimentation via clarifier
SL : Sedimentation via lagoons
T : Sedimentation via thickener
298
-------
K)
VO
C
BAR MILL
PICKLING
0.19 Itoc
(3 gpm)
PLATE MILL
PICKLING
EQUALIZ-
ATION
TANK
—
0.378 l/»ec
(6 gpm)
0.19 l/*ec
(3 gpm)
W. P. L.
HOLDING TANK
-v Z&H2S04
J A
hno3-hf
oo
rfoi
A
SAMPLING POINTS
DISPOSAL BY PRIVATE
CONTRACTOR
PROCESS: COMBINATION ACIO PICKLING -
BATCH
PLANT: C
PROOUCTION: plate: 79.4 METRIC TONS/TURN
87.5 TONS/TURN
BAR: 6.6 METRIC TONS/TURN
7.3 TONS/TURN
LIME
SLURRY
TANK
MIXING
TANK
SEDIMENTATION
TANK
0.378 1/sftC
(6 gpm)
SLUDGE
REMOVAL
DISCHARGE
COAGULANT
AIDS
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
COMBINATION ACID PICKLING - BATCH
WASTEWATER TREATMENT SYSTEM
WATER FLOW DIAGRAM
Dwn. 4/9T9
FIGURE 1ZII-
-------
PICKLING
LINES
PROCESS
WATER
WASTE PICKLING
LldUOR TANKS
PROCESS: COMBINATION ACID PICKLING -
CONTINUOUS
PLANT: 0
PRODUCTION:
A__
42 30 l/sec
(1016 gal/ton)
DISCHARGE
TO RIVER
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
COMBINATION ACID PICKLING'CONTINUOUS
WASTEWATER TREATMENT SYSTEM
WATER FLOW DIAGRAM
Own. 4/9/79
FIGURE 3ZH-2
-------
PROCESS'
COMBINATION ACID PICKLING
BATCH
PLANT:
PRODUCTION: 43.5 METRIC TONS STEEL/TURN
(48 TONS STEEL/TURN)
FEED
(9.3 gpm)
PLATE MILL
PICKLING
SCALE
LI ME
NEUTRALIZATION
EQUALIZATION
.0.6 l/sac
(8.6 gpm)
NITRIC-HYDROFLUORIC
ACID WASTE PICKLE
LIQUOR
SULFURIC
ACID
WASTE
PICKLE
LIQUOR
SETTLING
BASIN
oo o=^
HAULED TO COMPANY
DISPOSAL SITE
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
COMBINATION ACID PICKLING - BATCH
WASTEWATER TREATMENT SYSTEM
WATER FLOW DIAGRAM
Dwn. 4/9/79
-------
INDUSTRIAL
SUPPLY WATER
PROCESS: PICKLING-H2S04-CONTINUOUS STRIP
CONCENTRATES 6. RINSES
PLANT:h-2
PRODUCTION^
625 METRIC TONS/TURN
(689 TONS/TURN)
-10.4 l/sec
1165 gpm)
FRESH
ACID
PRODUCTION FLOW
k k A
-------
process: combination acid pickling-
CONTINUOUS
PLANT: I
PRODUCTION: 257.3 METRIC TONS STEEL/TURN
1283 TONS STEEL/TURN)
OTHER
PROCESS RINSES
31 gpm
PICKLING RINSES
1070 gpm
SPENT
PICKLING
LIQUOR
69.4 I/sec
(1100 gpm)
FEED PUMP
2.5 gpm
TRANSFER
PUMP
HOLDING
TANK
BATCH
NEUTRALIZATION
TANKS
(2)
DISCHARGE
TO RIVER
SETTLING LAGOONS 12)
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
COMBINATION ACID PICK LING - CONTINUOUS
WASTEWATER TREATMENT SYSTEM
WATER FLOW DIAGRAM
LIME
SLURRY
STORAGE
CONTINUOUS
STRIP
PICKLING
PROCESS
-------
w
o
it.
MILL SERVICE
WATER
A
— 353 l/SEC
(5600 6PM)
*4 PICKLE LINE -
3.97 l/SEC
(63 6PM)
FRESH t^S04
-337 l/SEC
IU5347 6PM)
SCALE
PICKLE
TANKS
(*4 a
PR0CESS: hot forming-section
PICKLING H2S04-HCL
HOT COATING GALVANIZING
PLANT1 l"2
PR0DUCTI0N;464 METRIC TONS(5l2 T0N3/TURN ROD
278 METRIC TONS(306T0NS)/TURN
H2S04 PICKLING
22 METRIC TONS (24 TONS)/TURN
HCL PICKLING S GALVANIZING
¦5 PICKLE LINE
9.84 l/SEC
(136 GPM)
FUME HOOD
I NO SCRUBBING)
P. 9
SPRAY
RINSE
OEEP
RINSE
337 l/SEC,
(5347 6PM)
SPENT ACID
TO CONTRACTED
DISPOSAL
WATER SPRAYS
l/SEC
GPM)
HCL
RUNNING
HOT
HOT
PICKLE
RINSE
STANDING
DIP
TANK
RINSE
GALV.
13.8 l/SEC
(219 GPM)
0.7 t/SEC
'(II GPM)
TERMINAL SETTLING LAGOON
46,2000,000 I
(12,200,000 GAL.)
¦~ 350 l/SEC (5556 GPM)
TO RECEIVING STREAM
/V SAMPLING POINTS
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
COMBINED WRE, ROO, PICKLING 8 WERE GALVANIZING LINES
WASTEWATER TREATMENT SYSTEM
WATER FLOW DIAGRAM
DWG.6-24-''dfte#.2 2S&76
RDM 110
1
FIGURE 3ZE-6
-------
PROCESS: COMBINATION ACID PICKLING'BATCH
PLANT:
PRODUCTION: 39.1 METRIC TONS STEEL/TURN
(43.1 TONS STEEL/TURN)
1.56 IA«C
(25 gpm)
WASTE PICKLING
SOLUTION TO LIME
NEUTRALIZATION
PLANT
26.8 l/tec
(423 gpm)
i
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
COMBINATION ACID PICKLING-BATCH
WASTEWATER TREATMENT SYSTEM
WATER FLOW DIAGRAM
SAMPLING POINTS
Dwn. 4/9/79
BAR MILL
BATCH
PICKLING
SANITARY
WASTEWATER
OTHER PROCESS
WASTEWATER
MUNICIPAL
SEWAGE
PLANT
-------
i/sec
C (763 gpm)
48.1 l/sec.
(763 gpm)
OO CH
OTHER PROCESS
WASTEWATER
EQUALIZATION
AND
AERATION
CONTINUOUS
STRIP
PICKLING
WASTE PICKLING
LIQUOR
PROCESS"- COMBINATION ACID PICKLIN6-
CONTINUOUS
PLANT'- 0
PRODUCTION: 40.5 METRIC TONS STEEL/TURN
(44.6 TONS STEEL/TURN)
COAGULANT
AID
OTHER PROCESS
WASTEWATER
SODIUM
HYDROXIDE
NEUTRALIZATION
c
DUAL
RECTANGULAR
'J
CLARIFIER
a.
^-2.2 l/sec
c (35 gpm )
,11.8 l/sec
< ' (IB7 gpm)
74.9 l/sec
(1187 gpm)
1
TO RIVER
A SAMPLING POINTS
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
COMBINATION ACID PICKLING'CONTINUOUS
WASTEWATER TREATMENT SYSTEM
WATER FLOW DIAGRAM
3wn. 4/9/79
FlfilJRF "VTT-fl
-------
h2o vapor
CRYSTALLIZED
TANK
20«C I
FRESH H,SO. ACID
PICKLE TANK
TO* C 060* F)
18% ACID
18,900 LITERS
(SlOOO GALLONS)
SEPARATOR
TANK
FERROUS
SULFATE
HEPTAHYDRATE
CRYSTALS
RECOVERY
ACID
13%
PROCESS: PICKLING H2SO4-BATCH-CONCENTRATED
a RINSE; PK3KLIN6-SULFURIC ACID
RECOVERY
plant: 0-2
PRODUCTION: 60 METRIC TONS STEEL/TURN
(67 TONS STEEL/TURN)
CITY WATER
LIME
DIP
SPRAY
RINSE
STANDING
RINSE
ENVIRONMENTAL PROTECTION AGENCY
STEEL INOUSTRY STUDY
SULFURIC ACID PICKLING AND ACID
RECOVERY OPERATION
WASTEWATER TREATMENT SYSTEM
WATER FLOW DIAGRAM
Own.6/5/75 |Rev. 2/26/76
FIGURE 3ZH-9
Re*6/20'76l 1
-------
PROCESS: PICKLING H^O^-BATCH-CONCENTRATEE
a RINSE,PICKLING SULFURIC ACID
RECOVERY
plant: P-2
production: 43 METRIC tons of steel/turn
(47 TONS OF STEEL/TURN)
recovery and
FRESH ACID VSfy.
batch charge
(SEE FIS. an-II)
SULFURIC
ACID PICKLE
TANK
processing sequence:
(T) product to rinse
(4) TO ROD DRAWING
(?) PRODUCT TO DRAINAGE
(2) PRODUCT TO LIME COAT
WATER
HOSE
fc-.
1, r
»-
RINSE
AND
DRAINAGE
TANK
MILK OF LIME
TANK
/\0.I6 l/SEC
(2.5 GPM)
BATCH DUMP
208,200 l/MO.
(55,000 GAL/MOJ
SPENT
PICKLE
LIQUOR
STORAGE
-A-
TO SEWER
TO REGENERATION
PLANT (SEE FIG. 3EI-II)
A
SAMPLING POINTS
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
BATCH H2S04 PICKLING AND ACID RECOVERY
WASTEWATER TREATMENT SYSTEM
WATER FLOW DIAGRAM
|Pwn.7/l6/lgg
FIGURE 3ZII-I0
-------
u>
o
vo
COOLING
WATBQ
-&r
5A5EC.
(a&QPM)
5T&AM
Z7^
PRE
COOLER
£3
a
tp
Z
£
—*
ORYSTALUieR
-£Q&, 200l./MO-
(5S.OOQ &AL. /MO.)
BATCH DUMPS
FRO M P1CK.LS TANK'S
(SEE H&TTT-IO
\g/
or
Hi
s
J,
\v
PROC&SS i PICl^LI NG - SULPUGIC
ACID RKCOV6C.Y
Pl/^nt : P--Z
PRODUCTION : q,5G& LIT&CS OP
SPENT PICULL& LiOi
/TU£N{.Z.,£ZQ &AU?.
5P&NT P1CU.L& HQlN
ITU&N
k-VACUUM JfcTS (TYPl
-TO ATMOSF'U &R&
WWW
WET WELL
I
SPENT ACID
5TORAS&
)
¦5.4-£/5&C
(as &pm)
A
±Q£
TH1CU.EN&R
-C&MTBI FU&Er
crystal
5TORA&&
P &2
IHtO
TO F>ICLZLE:«
TANi^e>
{see R&. szn-io
P&COVEgErD
ACID
COOLINS WAT&E
TO &E-VVEQ
A-
5AHPU M6 POI NT^
ENVIRONMENTAL PROTECTION AGE A/CV
STEEL INOUSTffV STUDY
SU l—F-U R I C ACID R&COVERY
W^TEWAT&R. TCtATMEiNT SYST&M
VVATC-K PLOW DIA&RAM
UV(. I fr.-7'j
Rl-V.l VH Hr
Pl V'/ 'L U- Tte
Pi&uRE 2E-II
-------
PROCESS' PlCKLIMG. SO A - BM"CLW
C0K1CEKSTR/WE.S £ RIWSES;
PICkLIKJG SULFURIC ACID
RECOVERY
PLAUT ' Q-?_
PKODUtTlOW : 36 METRIC TOU&/TUC,\i
(40 TOM s/TURN)
ACID M 1ST
,-SPEUT PIC.K.LE LIQUOR
COOL TO IO*~ C (^50°F^
ACID RETURN
UUE.
CRYSTALL'.ZER
MAK.6.-UP WATER
(CITY WATEf*-)
PURCHASED
FRESH AC.IO
ACIDIFIED RlWSE.
WATER ,
AVG, FLOW
0.03S X/SEC.
(O.SCi &PM1)
COLLECTOR
AIR
///////,' /
PUSH/PULL
" ~ ~ FUMt CONTROL
HEAT TO GS.5°C
(l500F)
Alft AaiTATIOto
W
PICK.LIKJCj takji^
RE-COVERED
5ULFUR\C ACID
FHP,RO'JS SULFATE
HE.PTAHY PRATE. /
CAPACITY: ZCmSOO jC
(T.060GAL.)
SPRAY WH5£t
DIP TANK.
RECOVERED ACtO
A SNMPLIWO POIMTS
EUVIB.ONMEMTNL PtaoTI^CTlQ>J ft6£KlLY
Steel ihpustrv stu&v
SULFURIC ACID ptCK-LWIG ^RE-COVG-RV
BATCH OP6RAT IOK)
W#V6TEWATEB. TREATMF.NT SYSTEM
WATER FLOW DIAGRAM
owe. t-<-75
R.EV.2 Hi-fi
figure m-i
Vt0-7<
-------
PROCESS: BATCH PICKLING (SULFURIC ACID)
PLANT: R
PRODUCTION:301 METRIC TONS STEEL/TURN
(332 TONS STEEL/TURN)
RIVER A
WATER
SLUDGE LAGOON
/{^SUPERNATE
A SAMPLING POINTS
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
SULFURIC ACID BATCH PICKLING
WASTEWATER TREATMENT SYSTEM
WATER FLOW DIAGRAM
Own. 3/28/79
FIGURE 331-13
WASTE
PICKLE
LIQUOR
BATCH
PICKLING
¦1.3 l/sec.
(21 gpm)
LIME
NEUTRALIZATION
-------
ACID Rl NSE. WATE.R
O.SS &/SEC.. 04-GPM)
ALKALI ME RIKJSE WATER
OA2. -£/SE0.£G,.G> GPM)
SPE.MT PIC.K.LE. LIQUOR.
0^4 JL! SE.C. C3.& GPM)
-A:—¦
SPEtsIT ALK.A.HKJE CLEAKJERS
IKIT6RMITTEWT FLOW
O.OZ^/SEC.fO.SGPM)
¦A-—*
PROCESS- PICKLIWG HjSO^.-BATCH
CONCENTRATES K Rll-JSES
PLAMT : P.- Z.
PRODUCTION: 300 METRIC TOWS OF STEEL/
TUjeA/(33l TONS OF STEEL/
TU&N)
EQUAL.IXATIOM TAKJK.
ACETYLENE SLUDGE
STORAGE
I.Gl/SEC
(25 4PM)
(a) SETTLIKJG
LAGOONS
f
I.G,i»/SEC.
(tESPM)
TO RECEIVING STREAM
Ml V ING TAK1VC
^/N^SAMPLIKJG POIWTS
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY .
H^SO* PICK.LIWG LIKJE
WASTEWATER TRE AT ME, KIT SYSTEM
WATER PLOW DIAGRAM
DWG 6-C.-7S
Rtv t iv>m
FIGURE 3ZH-I4
-------
PROCESS: PICKLING-H2504-BATCH RINjSE
PLANT t 5-2
PRODUCTION: 77 METRIC TONS OF STEEI/TJCM
(as tonsofsteel/t^aO
Z.-Zizl SEC
(35GPM)
MAKE-UP WATER
tr DlCHROMATE SPlLL/VGE
^ FROM HOT DIP
BATCH
MAKE-UP
ADDITIONS
HzSQ4
batch
pch
TREATMENT
PRE-HOTDIP
GALVANIZING
STANDING
RUNNING
RINSE
RlMSfc
PlCKLE
TANK
SUMP
PUMP
2/ZlijSEC
(356PM)
ACID PROOF BRICK
ALLTANKS
CONTRACT DISPOSAL.
LIME
STORAGE
MfXER
LAGOON
SLUDGE TO
ENVIRONMENTAL PROTECTION AGENCY
CONTRACT DISPOSAL
(WEEKLY)
STEEL INDUSTRY STUDY
batch HzSOij pickling,
wastewater treatment system
WATER FLrVv DIAGRAM
A = SAMPLING POINTS
k» /? i yt if
figure xn-15
t Jt If
-------
PROCESS : PIOO.IN6K, SO4 CONTINUOUS-
CONCENTRATED AND RINSES
PICKUNG-5ULPUQIC ACID PtCOVERY
TO ATMOSPWEQEr
PLANT:
O. 2a.iL/5EC. M?P VAPQg-
C 4.5 &PM W2O VAPOa)
ITMO'aPH&R
PPODUCTIOn- "/ METBlC 'QMS c3P
6T&E-L- /TUZN
HOP TON'S? OP eTE:fc"L_/
TUEN )
KJOoi
(&OOOGAL.)
=P»CKLIN& TAN Id.
RIN&E TANK.
TAMK
COMPENSATE- BIN5E WAT Eg
o/2a£/s&c. ( spm-mot)
SPENT P1CU.L& LIPUOC
Q.2&1/SEC. (4.5 6 PM)
METEBeD PLOW
RlNSt
/2\ CITY WAT&CZ.
(USED TO &&N£Q A.TE.
TAKlId
Q£.covee£.o acid
STOQA&& TAN IC
STEAM
CONOE.NS&T&
2e>£/S6C
PROM
CON OH ION I NIG
~ NIT
TAN 16
2-2 TOO X.
CA S 6PM MOT)
(&OOOSAL.)
NEW AC I O
TAMI^.
NON -CONTACT
COOLiM T TO
ENVIRONMENTAL PROTECTION AGENCY
^ TO CBVaTALLl^&g. TAN U. OF ACID BECOVEPY LI Ml
ACID COMC. iS-^O^ BY
STEEl INDUSTRY STUDY
CONTINUOUS STRIP* PI C KL.I W6
WASTE: rt&TErR TREATMENT SYSTEM
WAT£R P-LOW QI6&0AM
ErVAPORATI V
COKiC&KjTCATlOM
A=samplins points
W6.3/6-74.
m.i m-x
FIOUftB Sir 16
IfiY, I 2 201k
-------
OJ
H*
Ln
PROCESS". COMBINATION ACID PICKLING BATCH
PLANT: U
PRODUCTION: 10.4 METRIC TONS STEEL/TURN
(11.5 TONS STEEL/TURN)
EMERGENCY RECIRCULATION
LIME
L ME
LIME
(AS NEEDED
(AS NEEDED)
(MANUALLY)
rt?
PICKLING
PROCESS
(PIPE AND
TUBE)
DISCHARGE
TO CREEK
BATCH DUMPED
PICKLING
RINSES
BATCH NEUTRALIZATION SYSTEM
LIME
DEGREASER
RINSE
WATER
SPENT PICKLE
LIQUOR
MIXING
PUMP
SOLIDS TO LANDFILL
NEUTRALIZATION
TANK
ENVIRONMENTAL PROTECTION AGENCY
VACUUM DRUM
FILTER
STEEL INDUSTRY STUDY
COMBINATION ACID PICKLING - BATCH
WASTEWATER TREATMENT SYSTEM
WATER FLOW DIAGRAM
STEAM
F
Dwn. 4/5/79
IGURE 3ZTE-I7
EVAPORATION TANK
-------
WIRE PICKLE OPERATION
CITY WATER
process: pickling-hcl-batch
CONCENTRATED a RINSE
PLANT: U-2
PRODUCTION: 9 METRIC TONS OF STEEL/TURN
(10 TONS OF STEEL/TURN)
757 l/DAY
1200 GAL./DAY)
z
z
o
UJ 9
UJ
c*>
©
UJ
©
*-
t- *-
1-
©
z
z
Z
uj
Z>
<5 <
<
UJ
J
v>
CO
<
UJ
a:
©
UJ
o
<
I
I
JL
SODIUM CARBONATE
NEUTRALIZATION
BATCH
TREATMENT TANK
SAMPLING POINT
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
HCI PICKLING LINE
WASTEWATER TREATMENT SYSTEM
WATER FLOW DIAGRAM
pwn. 6/6/75 Rev. 2* 2/26/7S
Rw. 1-2/21
FIGURE 3ZXT-18
-------
process: pickling hci-batch
CONCENTRATED 8 RINSE
PLANT: V-2
PRODUCTION: 72 METRIC TONS OF STEEL/TURN
I79 TONS OF STEEL/TURN)
FIXED
SPRAYS
ACCUMULATOR
1.64 l/SEC,
(26 6PM)
CITY WATER
ACCUMULATOR
HOSE
HOSE
EAST
BATCH PICKLE
CAR 3
RINSE
DRAIN
AREA
LIME B BORAX
SPARE
LIME
LIME
BORAX
BIN
CONTRACT OISPOSAL
OFF-SITE
0.82 l/SEC
(13 6PM)
FIXED SPRAYS
CENTRAL
BATCH PICKLE]
CAR 2
(NOT IN USE)
RINSE
WEST
BATCH PICKLE
CAR 4
NaOH
STORAGE
0.82 l/SEC.
(13 GPM)
"X
0.82 l/SEC.
/ (13 GPM)
CONTRACT
OFF-SITE
DISPOSAL
METROPOLITANS*
SANITARY DISTRICT
4.73 l/SEC
(75 GPM)
OTHER FLOOR DRAINS
rNON CONTACT COOLING
FROM HOT COATING LINE
NEUTRALIZATION TANK
BATCH TREATMENT
A SAMPLING POINT
ENVIRONMENTAL PROTECTION AGENCY
Own. 6/6/75
STEEL INDUSTRY STUDY
HCI PICKLING LINE
WASTEWATER TREATMENT SYSTEM
WATER FLOW DIAGRAM
Rev. 2/27/76'
R«». 2/20/76
FIGURE 301-19
-------
process:
PICKLING-HCrCONCENTRATED AND
RINSE, PICKLING-HCI REGENERATION
TYPE: PYROLYTIC HCI REGENERATION
PLANT*. W-2
PRODUCTION: |,I48 METRIC TONS/TURN
(1,266 TONS/TURN)
HCI PICKLING AREA
FUMES
EXHAUST
37.9 l/SEC
1600 GPM)R|NSE water
MAKE-UP
(SERVICE WATER
SUPPLY)
PICKLED
STRIP STEEL
7.57 l/SEC.
(120 GPM) SCRUBBER
SPRAY WATER
PICKLE LINE FUME COLLECTION HOOD
STRIP
STEEL
RINSING
SECTION
PICKLING SECTION
(POTABLE SUPPLY)
FRESH
PICKLE
LIQUOR
STORAGE
ACID
MAKE-UP
WATER
RINSE
FUME
SCRUBBER
TO SEWER
EFFLUENT
37.9 l/SEC
(600 GPM)
SPENT
PICKLE
LIQUOR
STORAGE
FUME SCRUBBER
EFFLUENT
SPENT
PICKLE LIQUOR
SCRUBBER
SPRAY WATER
FRESH WATER MAKE-
UP TO VENTURI
(POTABLE SUPPLY)
HCI-HoO VAPORS
7.57 l/SEC
I (120 GPM)
(SERVICE WATER SUPPLY)
HCI-HaQ VAPOR
FRESH MAKE-UP
WATER TO ABSORBER
(POTABLE SUPPLY)
SCRUBBER
GASES
HCI-H-0 VAPORS
CARRYOVER
/k 16.4 l/SEC
^<260 GPM)
2.0 l/SEC
(31.5 GPM)
CYCLONE
DUST
COLLECTOR
ABSORBER
EXHAUST
SCRUBBER
HCI
ABSORBER
PYROLYTIC
REACTOR
HCrHgO
VAPORS
INLINE CAUSTIC
SOLUTION FEED
IRON OXIDE
DUST
AI6.4 l/SEC
(260 GPM)
NEUTRALIZED
SCRUBBER EFFLUENT
VENTURI \/
NATURAL GAS
AIR
PREHEATED
SPENT
PICKLE
LIQUOR
RON OXIDE PELLETS
REGENERATED
2.0 l/SEC.
(31.5 GPM)
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
CONTINOUS HCI PICKLING AND RECOVERY
WASTEWATER TREATMENT SYSTEM
WATER FLOW DIAGRAM
A SAMPLING POINT
Dwn.6/6/75
JZH-20
FIGURE
R«v. 2/24/76
-------
LaJ
H
lO
PROCESS: COVC ROLUNG ¦ RE.C\RCULM\ON
HCU- CONTINUOUS CONCENTRATED
PlCKLINt,- VACL- fvOD RtiE-NtSKTvON
PLANT: X-Z
PRODUCTION: (COLD RQL\.ED^
.B5 'AE.TWCTONS OY <5\EEX \ ru£\'
(75
(P^CKLlNtS)
4GO NSETR.\CTON^ OF "STE-tL \TJ^r\
ISD1 TONS C>* mZl.\_jTU£V^
C\AR\F\EK5
H UNITS)
TO VA.CV)\)W
RE^ERVOtR
(lAUVIW EC ?,OPPlV)
F\CTE^-,tL<>.VJOCVU.
CITY
^\NS>E 3i.5(/ser
NC COOLING
¦=*.5 l/SE-C
C\5a 4PM)
WM CR
(50O&PN\)
U£KTINS VIEAtA
3.2 ft/SEC.
(bOSPM)
CONTINOOO&
HC>- PlCKUN
KMLLWMER
•>, SETTLED WfftK
TOERED VJME.R
T/VNDE^
COLD
NULL
PlCKUER
NON-CONTKCT
Cool\nG
5 rinse
WATERS
4&T S| "SEC
f^oo gpia)
S.hAP. UNfc
TO V\\\-L
44.ZIISUS3
(loo 6PC'
C LAiRI F>ER
•5£TT\.CR
i5i" lac
AWoc,PtA)j
EFFUOtW
rbv - Q.LT£R
*OD
Rt&EHEW'.TVCiN
PL&.MT
VVAVTE 0\L
(f LOTMlON TANK)
\REtaV\ENT
Ofe3 points
«.v.t 1Z.S7G>
tSVOCk (o- <© 13
F\GOfcfc 3ZEE-2I
Rfcvt ?2oTfe
-------
process; pickling-hydrochloric
ACID REGENERATION
plant:
X - 2
production: 4I METRIC tons of HCt/TURN
(46 TONS OF HCl/TURN)
WASTE ACID (FROM 3 LINES)
1.56 l/SEC (25 GPM)
CYCLONE
WATER
VAPOR
STORAGE
TANKS
STORAGE
TANKS
STACK
ACID
COOLER
PACKING
EXHAUST
FANS
47.3 l/SEC'1
(750 GPM)
ACID WASTE
ROASTER
"''A'.
/,////////,
CRUSHER
PUMP
RECUPERATOR
FUME
SCRUBBER
~
Tor
OXIDE BIN
BLOWER
,2 47.3 l/SEC.
T'(750 GPM)
TO CLARIFIER
REGENERATED ACID
REGENERATED
ACID
A SAMPLING POINT
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
HCI REGENERATION
WASTEWATER TREATMENT SYSTEM
WATER FLOW DIAGRAM
3wn.6/V74
RW. 2/28/76
FIGURE VE-ZZ
fl»v. 2/20/76
-------
PROCESS! PICKUN6-HCI-PINS&
TYPE: CONTINUOUS
PLANT-
PRODUCTION: WETRICTONSOFSTEEL/>Z*W
(<£,OCc TONS OF STEEL/ TUEM)
SERVICE WATER
3.I//SEC
(SOQPM)
HEATED BAYWATEP
3.8 II SEC 1
(£0 GPMN, f
DIRECTION OF STRIP TRAVEL
RINSE TANK
n«z rinse tank
KJ03 RINSE TANK
OVERFLOW
OVERFLOW
TO SEWER
¦TO BE DIVERTED TOHCl PLANT
AND USED IN ABSORBER TO
GENERATE ACID, ELIMINATING
RINSE WATER DISCHARGE FROM
K|S 3 PICKLE LINE
ENVIRONMENTAL PROTECTION AGENCY
A- SAMPLING, POINTS
STEEL INDUSTRY STUDY
HCI PICKLE LINE
"WASTEWATER TREATMEMT SYSTEM
WATER FLOW DIAGRAM
FIGURE 301-23
TOWER FUME
SCRUBBER
N«3
CONTINUOUS
PlCKLER
-------
OJ
to
to
PROCESS: HCI RELGCUE-RATIOkJ
TYPE. '• SPW./VV R.O\STEP.
PLO.MT ' Y* H.
PRODUCTION : /3<£/ METRIC TOKSS/TU£M
(ISOO TOVOS/T U£M)
(SERVES 3P>CK.unG OPERATIONS)
RE.GEKgttATE.tt
AciD
STORAGE TANK
PIC.VCLE-
LIQOOF^
S TO RAG E_ TAVUC
REGENERATED
A. dp
STORAGE TAHK.
P'C-*t-E.
LIQUO R
STORAGE TM^K.
< 1.3 21/SEC. FEED
(aiGPM)E-ACH *
3Z.-l/see feed
•
BAOV.WASH WMER^
COKJCEKJTRATED RltJSE WATER
TO BE. UsE-OikJIOEW*. FUTURE
WATER
ACID
AC-ID
COOLER.
> »
CI CUOMt
WATER
ABSORRW
AtSORBte
PRECIPITATOR.
A - B
ROASTERS
(iDEkmCM-)
tlA/SEC.
Asogpm}
(I UNIT)
FUME.
FUME.
CLEANER.
{eOOGPM)
(2 UNITS)
OXIDE.
VlBRATIMG
HPPPEB
VI BRAT IMG
HoPPEia.
TANK. CAR
OXIDE. COMvE-tOR
Ox\OE. CONVE.YOR
EXHAUST FAWS
E.KHAUST FAMS
EWVIKOME.IOTAL PRQTEC.TIOW A,C,EtOC^
STEEL IkJCSUSTRY STUDY
WCL RE&EMER.ATIOM
WASTEWATER TR.H.AT NvE_>OT SYSTEM
WATER Flow DIAGRAM
«se ^/sec
I /i4oo GPM)
* INCLUDES NOM-CONiAC
WM£V)
' ' / IN'.
^SAMPClUG POIklTS
REV? ixi-n
DWG 5-1 ITU
FIGURE HH-24
REV. I Z-T-^U
-------
WATER
ACID (HCl)-
5TEEL STRIP-
K:
PICKLERS
7t
WASTE PICKLE7 i.
LIQUOR ^
TANK
lO.lllSEC.
\ (l&OSPM)
2.511 SEC ¦
(40GPM)
r*Kl9 17
AIR
g-*
/\-- SAMPLING POINTS
CLARIFIER
VACUUM
FILTER
SERVICE
WATER
PROCESS: PICKLING HCI CONTINUOUS
COVENTRATED 4 RINSE
PLANT: 2-Z
PRODUCTION! 453 TONS OF5TEEL/TU/Su)
MM/iVr a>
RINSETANKS
'^RINSES
tj-K 2/SEC
(I20GPM)
UPCOILER
POLYELECTROLVTE
- lO.tfi/SELC
(IfcOGPM)
TO
SANITARY
SEWER
ENVIRONMENTAL PROTECTION AGENCY
STEtL INDUSTRY STUDY
HCI PICKLING LINE
WASTEWATER TREATMENT SYSTEM
WATER FLOW DIAGRAM
DWa 75
REV-1 2-lc5
P£.v ? 1-71 K
FIGURE. EH- 25
-------
PROCESS: PICKLING-HCI CONTINUOUS
CONCENTRATED < PlNSE
PLANT: AA 2
PRODUCTION- Bit METRIC TONS OF STEEL/""!'.
( 1C.O TOWS OF STEEL/ TURn)
ZZH.OL
CfeOOGMS}
1981.11
(5Z5GAL5)
1197.8 1
(415 GALS )
1892.51
(50OGALS.)
2116.41
(575 GALS)
2081.81
(550 GALS)
HCI PICKLING
0.14 C./5EC
(l 1.1 6PM)
STEEL STRIP
MAKE-UP WATER
0.73-0.1fci|5EC.
(l 1.5- IZGPM)
SPENT —
PICKLE
LIQUOR
0.4IAISEC
(&-5GPM)
T0
DEEP WELL
DISPOSAL
A-
SAMPLING points
ENVIRON mental protection A6E.NCV
STEEL industry study
HCI PICKLING LIME
WASTEWATER TREATMENT SYSTEM
WATER FLOW OlAtaBAM
Xi <- 6 1 S
Rtv i 2 20 ~/i
Rtv 1 2 nv.
FIGURE 3ZE-26
-------
4&jG/S£C. (ia>o gpm)
WfcLL WAT&g
3.6^/seC.
(ao 6pw)
CONTINUOUS STRIP
,i i 4J1 —
PICl^L&K.t) UN£5)
AOD RlMSfc WTO
5UK6ETAW5(2)
5 STD TANDEM
COLD MILL.
COLD MILL BINSc
SPENT EMULSION
WTC.SUH6ETAKJTO
TANK& t COLD COLLINJ&
B&CI BCULATlOKl;
PICI^LI NI&-UC.I —CONTl NUOUS
RlNSEr
RLANJT : BB-Z
PRODUCTION : (.COLD COLL I Kltj) :
!&>33 METRIC TOnI'sOF STL /T. C'J
QeOI TOK>^> OP STfcfcV..T_ C
(PICtUNO) :
ZZZS METCICTOHSQEgTL -
( Z4£3 TONS OF ST&£L/rtC )
¦TO MCI gfcCOVEB.V AT AN OPP-SlT^ LOCATION.
~OR DISPOSAL-AT AN ON-SlTfc DEEP YV6-LL.
n3.feOO.QOO I ( 30,000,000 tiUSV)DIA
vi&KM'iatt-wF
TO gfcCEIVING
STEEAM
Kbfth)C65,)DIA.
VACUUM PI CT ErE-bC*)
RECIRCULATED SLUDGE:
4 ,T 'O1
VACUUM El LTErCb (Z)
/\= SAMPLING pqimts
ENVIRoriM EbJTAL PROTECTION A&EMCV
©Tee-L industry study
COLO ROLLINC> £ HC( PICKL.ING,
WASTE HVATBP TREATMENT SYSTEM
watec. plow diaqcam
m Qr
-------
PROCESS1 PICKLING H 2S04 "CONT I NUOUS
CONCENTRATES & RINSES
PLANT:QQ-2
PRODUCTION- 922 METRIC TONS/TURN
(1016 TONS/TURN)
FUME HOOD
PRODUCTION
FLOW
r* FRESH H2SO4
rorpio
Ul
to
-------
ROLLIMG> SOl-UTIOM
CO l_D
ROLLING
PROCESS
PROCESS. PICKLING-H-j SO* COKJT
C-OMCEWTRATES AND
RIW5ES
PLAUT SS-2.
PRODUCT iokj
7<7a METRIC TOUS/7"6'-£'A'
800 TOWSITUSN
-za. i/SEC
\ (itGRMV
COLD
HOT
WATER
WATER
RECOIL
T-l
T-Z
T-3
T- A
T-S
RINSE
RINSE
STATION
-3&9«/SEC"5a8i/SEC
(4000 GPM" 3,0OO
gpm)
OTHER PLAK1T
•WASTE PICKLE. LIQUOR
I. 2C. -fi/SEC..
(fcO GPM)
WASTE WATER
Z3-a^/SEC
(37 7 5 GPM)
2E to receiving stream
-DISCHARGE to
R.E.CE-IVIK1G STREAM
307 o-e/sec.
(^sso&pm)
A'
SAMPLING POINT
EkJVIROUMEMTAL PROTECTION AGENCY
STEEL IkJDUSTKY STUDY
COMTIUUOUS N;SO+ PICKLIU&
AUD COLD ROLLING
WASTE WATER TREATMENT SYSTEM
water flow diagram
DWG H-II-7S
R6.V.1 ?-t87<
figure HI-29
-------
INDUSTRIAL
WATER SUPPLY
FUME SCRUBBER HOODING
PROCESS^ PICKLING-H2S04-CONTINUOUS
CONCENTRATES -RINSES
PL ANT: TT-2
PRODUCTION 947 METRIC TONS/TURN
(1044 TONS/TURN)
FRESH
h2so4
COLD RINSE WATER
HOT RINSE WATER
Q
V
PRODUCTION _ FLOW
f 1 *
PRE-PICKLING
COOLING WATER
STATION
h2so4
1
COLD WATER 1 HOT WATER
RINSE 1 RINSE
1
1
RECOIL
STATION
Q
rr
Looping car
>-3.16 I/tec I
(50 gpm) I
A
3.16 lAec-
(50 gpm)
- 0.316 l/sec
(5 gpm)
FUME SCRUBBER
EFFLUENT
y\.
-17.6 t/sec (279 gpm)
COMBINED RINSE WATER
-21.1 l/sec(334 gpm)
-Transfer by tank car
To-
other
ACID WASTE"
WASTE PICKLE LIQUOR
NEUTRALIZATION
SYSTEM
EVAPORATION PONDS
COMBINED WITH OTHER
PLANT WASTEWATER AND
DISCHARGED DIRECTLY TO
RIVER
SAMPLING POINT
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
CONTINUOUS SULFURIC PICKLING
WASTEWATER TREATMENT SYSTEM
WATER FLOW DIAGRAM
Dwn. 3/29/79
FIGURE 3ZH-30
-------
PROCESS: PICKLING H2S04 CONTINUOUS
CONCENTRATES 8 RINSES
PLANT: WW"2
PRODUCTION^ 584 METRIC TONS/TURN
(644 TONS/TURN)
INDUSTRIAL WATER SUPPLY
PRODUCTION
FLOW
3.79 l/sec
60 gpm
24.0 l/sec
(380 gpm)
OTHER PLANT
WASTEWATER
A SAMPLING POINT
I 75 l/sec—
(2778 gpm)
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
CONTINUOUS SULFURIC PICKLING
WASTEWATER TREATMENT SYSTEM
WATER FLOW DIAGRAM
DISCHARGE TO
RECEIVING STREAM
Dwn. 3/29/79
FIGURE 2TT-3I
FILTRATION
SYSTEM
DEEP WELL
INJECTION
TERMINAL
TREATMENT
PLANT
LOOPING
PIT
COLD WATER
RINSE
HOT WATER
RINSE
RECOIL
STATION
-------
SULFURIC ACID PICKLIN6
BATCH PIPE AND TUBE
090
PROCESS1
TUBE MILL
PLANT-.
production: 37 metric tons/turn
(41 TONS/TURN)
O.oez 9/SEC
1.3
O.OZS f/SEC
< >—o.^t q pm
RINSE
TANK
CROWN
SYSTEM RINSE
RINSE
TANK
RINSE
TANK
0.6 V/SEC
9 G,PM
EQUALIZATION
AND OIL
SKIMMINQ .
RINSE AREA
SUMP
EMERQENCV
IMPOUNDMENT
TO LAGOON
AERATION
COOLING
BOSH
CHEMICAL
addition 4
MIXING
1ARI FIERI
PAR5HALL
FLUME
OTHER PLANT SOURCES
/37 i/SEC
2.170 qPM
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
SULFURIC ACID PICKLING-BATCH GALVANIZING
WASTEWATER TREATMENT
WATER FLOW DIAGRAM
/\SAMPLING POINT
OWN. 11/16/78
FIGURE m-32
-------
NON-CONTACT CDOUNC- h70
ChilLER CInOEnSaTE
Discharge jnlv OPERA1ES
At 60°p>
PROCESS Uj-SULFURIC ACID PICKLING
BATCH - ROD
plant: 091
PRODUCTION: Q-250 METRIC TONS/TURN
<284 TONS/TURN)
MAKE-UP
Zinc ammonia
CRvStalS
MA Hi
uHTOMATE
RINSE
TANK
•VA X
F L U*
REEIERS
K'NSt
TANK
TANK
TANK
bath
ROD Mi:
1-NK
UN*
RECiCiE 4
TO MILL
CiVEk
4 PICKLING ( GALVANIZING LINE
CiN BASEMENT)
Kj atmosphere
MAKE-Uf
k
X
amPER water
Lift STATION
U*4 Of T
MECVCIE I RivER WATER
PUMP HOUSE
DISCHARGE TO
RiVf R
FLU* I
k doling
galv
2inC
BATH
RINSE
rinse
MAX
reelers
RINSE
ALIU
TANK
TANK
TANK
"GO MILL
TANK
CCnTiNuOUS
&LEE3
no 3 picklingigalvanizing line
(uRQUNO FLOOR)
make-up
rS
PRESSURE
SANO FILTERS
CPE RATING
I STANDbV
30*%l
124 t Of**
FROM LEAD
ANfCALING
CL ARIFIERS
iPRAt #11
furnace
LIME FEEO
slurrv
galv
riNC
BATH
ChnQMATE
RINSE
TANK
LOOLIN^
RINSE
TANK
flu*
fANK
RINSE
TANK
REELERS
f
0 r^Tt
VACUUM DRUM
FttTER
1555<^«
CAM
2 GPM
(GftOUNO FLOOR)
WATER TREATMENT PtANI
SPHtfcfc
MAKE-UP
REACTION
TANK
iOXlOATlON
TANKS
BOILER
LFT STATION
IBLCMOOWN)
0 2a
5ALV
ZINC
Bath
IUU.ING
RINSE
TANK
chrcmaje
RINSE
TANK
RINSE
TANK
RtNSE
TANK
WAX
TANK
h?SC4
RtNSE
A TA*K
4 VS l?2 * GPW
n*i picklingi galvanizing line
(G#?0U*0 FtOOP)
VANI2ING
(NO ACID)
lORAuE
I
SAMPLING POINT
bBlS i
10 H GPM
A
LIFT STATION
ENVIRONMENTAL PROTECTION AGENCY
MARSHALL
i )96//V«c i24"4 cpm
0 b CPM
Hy.1 TANKS OUMPEb
EVEttV FRlOAV NI^Hf
~%C ME1ERE0 'MO
TREATMENT SYSTEM
(¦ »N«SwEO MCNOAT
MORNING
MAIN LIF T blAllON
STEEL INDUSTRY STUDT
HQ-NEUTRALIZATION— CONTINUOUS GALVANIZING
WASTEWATER TREATMENT SYSTEM
WATER FLOW DIAGRAM
E2Kyj£]
I
FIGURE 3ZH-33
-------
RINSE.
COLO
RINSE
RINSE
J/&£C
0.16JI/SIC
[if.fSPM)
HOT
RINSE
NON-CONMCT
COOLING V/ATEX
RINSE
^2-S7 A/S£C
(GrPM^ i
HOT MILL
WASTEWATER
W.-*-
(2-2-
J/SEc.
C,PM)
¦its—~
UPSETTER
i
1
t
HOT
MILL
SUMP
m zinc.
(312 G,PK\)
-£-~fcx—>1
I'ROCt ss: SULFURIC ACID PICKLING-BATCH
HYDROCHLORIC ACID PICKLING-BATCH TUBE
COMBINATION ACID PICKLING-BATCH
plant: 092 a 123
PRODUCTION:COMBINATION ACID PICKLING
20 METRIC TONS/TURN (22 TONS/TURN)
SULFURIC ACID PICKLING
157 METRIC T0NS/TURNII73 TONS/TURN)
HYDROCHLORIC ACID PICKLING
154 METRIC TONS/TURN (173 TONS/TURN)
SPENT PICKLE
LIQUOR
EXTRUSION
BLDQ.
EXTRUSION
AREA
SUMP
EXTRUSION
&L0<*.
EXTRUSION
BLDG,.
Id-lJ/sec.
(Z97 GfM)
A
MAKE UP WATER (CITY WATER) GOES TO VARIOUS LINES
COLO
FINISHING,
area
L
SUMP
CENTRAL
TREATMENT
PLANT
46.Z. Jt/se-C.
(732- OjPM)
——~
A;
SAMPLING POINT
(IZS G,PfA)
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
SULFURIC ACID-COMBINATION ACID PICKLING
WASTEWATER TREATMENT SYSTEM
WATER FLOW DIAGRAM
DWN.il/2l/7E
FIGURE 3ZH-34
-------
PROCESS: i< tickling iici neutralization
093
PRODUCTION; R- 34 3 METRIC TONS/TURN
(378 TONS/TURN)
RIVER
WATER
1.55 l/SEC.
(24.5 6PM)
11.64
l/SEC
(184.5
GPM)
STEAM
CONTINUOUS
HCL
PICKLING LINES
^ 10.1 l/SEC.
(160 GPM) i "
0 l/SEC.
(0 GPM) <'
(5 LINES)
SPENT
MILK OF LIME
PICKLE
REACTOR
STORAGE
LIQUOR
PURCHASED
TANK
TANK
HOLOING
H2S04 TUB
PICKLER LIQUOR
TRUCKED FROM
ANOTHER PLANT
MILK OF LIME
TANK
NO TRUCK LOADS
DURING SAMPLING
0. 41 l/SEC.
O l/SEC.
(0 GPM>-
17.42 l/sec
(276 GPM)
SUMP
DISTRICT
RUN
CLA RIFIER
ENVIRONMENTAL PROTECTION AGENCY
-------
PROCESS' CONTINUOUS H2S04 PICKLING
PLANT: 094
SERVICE WATER
MIL LS
LIME FEED
PRODUCTION: 955 METRIC TONS/TURN
(1053 TONS/TURN)
POLYMER
L I M t
FEED
FEED
PRIMARY
TANK # I
263.5 l/SEC
4176 GPM)
00
PRIMARY
SCALPING
TANK #
LIME FEED
PRIMARY
MIX
TANK # 2
PARSHALL
TANK
FLUME
PRIMARY
SCALPING
TANK «2
SCUM
BOX
TANK
FLOCCUL
24.29 l/SEC
(385 GPM)
CL ARIF
OIL
SKIM
TANK
Sludge
A LIFT
STATION
WEL L
THICKENER
SLUDGE
PUMPS
0.947 l/SEC
(15 GPM)
u> tc
116
l/SEC
(1847 GPMI
Filtrate
OIL
SEPARATION
TANK
OIL
STORAGE
TANK
ELECTROLYTIC
PLATING LINES
LIFT
STATION
CENTRIFUGES
SLUDGE
CONVEYOR
CONTRACT
HAULER TO
LANDFILL
N" I TIN MILL
3 STAND C.R.S.M
CONTRACT
HAULER
UO
LIFT
STATION
ENVIRONMENTAL PROTECTION AGENCY
N " 2
PICKLER
LIFT
STATION
STEEL
NOUSTRY
STUDY
CONTINUOUS H2S04- CONTINUOUS GALVANIZING
WASTEWATER TREATMENT SYSTEM
WATER FLOW DIAGRAM
25.75
(406
l/SEC
GPM)
N I
PICKLER
DWN 8/3/78
SAMPLING POINT
FIGURE 3ZH-36
-------
FILJERED
MAKEUP
WATER
// 1 :! . \>A'/ A'. /. )us ;,^i P/'KL/Htj-
PLANT'.
PRODUCT /ON: /5.-90ZMETK/C TCWS S.T££jrj.kLM
(ViS TONS STE£l/TU£K>)
FRESH ACID
MAKEup
RI NSE
section
PICKLING
SECTION
PRODUCT
EMERGENCY
overflow
PRODUCT
TO HC/
REGENERATION
PLANT *
SpENT ACID
TANK
cj>-(iaGPM)
i. i tysEc.
AC ID
INSTRUMENT-
ATION
spm>(D
L/SEC.
TWO
FUME
SCRUBBERS
SCRUBBER
MAKEUP
NOT IN USE
<0.50 G PM)(1)
0.05 '-/SEC.
-SCRUBBER
BLOWDOWN
*r\-
(O.G6GPMJ0)
O.04 L/SEC-
A-
-#|8ASEMEAIT/\
SUMP
AREA
DRAINS
-(52.25 GpMjO)
3,30 l/SEC.
ARB A
DKAINS
NOTE (DMEaSUREO FLOW
VALUES.
TO WASTE
LAGOONS
A
SAMPLING POINT
environmental protection ASENCY
STEEL INDUSTRY STUDY
CONTINUOUS HCt PICKL.INQ-RINSES
WASTEWATER TREATMENT SYSTEM
Water Flow t>iAC*RArv\
DWN:fr2l-77
FIGURE MT-37
-------
L-HC! PICkLZ LIQUOR
vt-^EHt/cATioN (meat PROCESS)
PiMT' oisa
f 'H'ODUC TlON: 8-&Z0 METZIC TONS ST£Ll/TIMN
i.G9S TDHS STEELL/tu£N)
HOT GASES
4.5 ^/?6C.
(11 6PM.)
WASTE PICKLE
FROM SJ0RA6E
7ANKS
MOT SASES
LIQUOR
HOT GASES
FUEL OIL
PZE-E-VAPORAJOZ
AIR
-SOME RINSE
WATER FROM
PICKUNQ LINES.
BALANCE TO
LAG>OOHS ^
FILTERED
MAKEUP WATER
IRON OXIDE
FRESH PICKLE
LIQUOR TO
STORAGE TANKS
WASfE S
ENVIRONMENTAL PROTECTION AQENCY
SCRUBBER WASTES FROM
OTHER THREE TRAINS
STEEL INDUSTRY STUDY
CONTINUOUS HCI PICKLING AND RECOVERY
WASTEWATER TREATMENT SYS TEW
WATER plow diaqrana
FIGURE 3ZH-38
(Si
-------
PROCESS-. CrSIILFUKIC ACID PICKLING
BATCH FASTENERS
SOUTH Dt^REASLR
A L HAL INC RINSES
096
PLANT:
PRODUCTION: Q-42 METRIC TONS/TURN
(46 TONS/TURN)
NORTH AND SOUTH
qALVAhllZER rinses
EL EC. TKOLYTIC
RINSES
RAMSOHOrr WASHER, j.
furnaces, £rc.
IO MILL,
HOT FORMING)
ETC.
C T.
COIL ORAWIN$, £ TC-
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
ACID PICKLING, GALVANIZING, ALKALINE CLEANING
WASTEWATER TREATMENT SYSTEM
WATER FLOW DIAGRAM
TO STREAM ANo/oR
RECYCLE
DWN.11/27/78
FIGURE3ZII-3S
LACfOON
DEEP
BED
FILTERS
-------
No I TANK 10,SOO gal A /0 H2S04
No. 2. TANK 10,500 gal 7-l2°,fc h^SQ,
No. 3 TANK 10,500 gal \b-Z\% H2S04
OPERATING TEMPERATURE flO*
PROCESS: o-sulfuric ACID PICKLING
CONTINUOUS STRIP
FROM WELL WATER SUPPLY
PLANT".
0.22 S/SEC
(3.7
-------
CJ
u>
KD
PROCESS-
Q BATCH SULFURIC ACID PICKLING
BAR, WIRE a SPECIAL SHAPES
recovered
AClOJMkSH
AC 10 VAPOR DE MISTER
PLANT:
PRODUCTION:
VAPOR
EXHAUST
188 METRIC TONS/TURN
(207 TONS/TURN)
steam
I heating
ACID
VAPOR
DEMISTER
VAPOR
PICKLE
TANK
H2S04
3000 GAl
PlCKlt
TANK
H2SO4
3000 GAl.
RINSE
TANK
PICKLE
TANK
H2S04
J000 GAL
LJMt
TANK
4000 GAL
WATER
STORAGE
3800 GAL
STEAM HEAI
FOUNDATION DRAINS
TANK
MAKEUP WATER
W PICKLING
INOlRECT
HEAT
EXCHANGERS
"-fe
RINSE WATER
TRANSFER PUMP
MAKEUP WATER
BOOSTER PUMP
FEED WATER
SUMP PUMPS
AC 10 VAPOR OEMISTCR
AIR SPARGING
BLOWERS
T*T77
AIR CURTAIN
FAN
PLANT BAR PICKLING
RECOVERED AC»D WASH
S-tMiaKft IuWn
t—i SPENT ACiO PUMP
STEAM
HEAT
C0N0FN5«t
RtTlUN
OCfcNSA'E
RETURN
pickle
TANK
H2SO4
PICKLE j
TANK I
HgSO^ I
WPOR EXHAUST FAN
STEAM HCAI
PICKLE
TANK
H7SO4
PCKLE
TANK
H2SQ!
BONDER
LUBE
TANK
RINSE
TANK
3HOSPHAIE
TANK
FOMWa
CRAWS
INOlRECT
aJR
SPARGING i»
BLOWER
RINSE WATER
TRANSFER pump
x^aiR SPARGING rv
[jg BlOWERSCTVP)
Alio VAr'iN OE MISTER
AlR CURIAM
FAN
RECOVERED AC©
SPENT AC»0
PUMP
PLANT N® I WIRE COIL PICKLING
TSjOOO GALLON
STORAGE TANK
SPENT ACID
LIQUORS
MWE-lP ViAIER
STEAM
CONTRACT*
HAULER
effluent
SUMP
A IK CUXTAIN
FANS
PICKLE
TANK
LIME
TANK
RINSE
TANK
PCKLE
TANK
^HjSO,
A-SAMPL1NG POINT
PLANT N»l
SPECIAL
LL ,h2so4 r*
SHAPE j
iTFAM 10 f€Al ~' '**¦%. Z! J- = W~~
FOUNDATION DRAINS
ENVIRONMENTAL PROTECTION AGENCY
Pickling steam 10 ^cai
kJCHANGER Atft
curtain
FAN
STEEL INDUSTRY STUDY
BATCH SULFURIC ACID PICKLING
WASTEWATER TREATMENT SYSTEM
WATER FLOW DIAGRAM
^ RINSE water
TRANSFER PUMP
^»AIR SPARGING
a eiowERs---s
SPENT ACIO
PUMP
DWNB/ll/78
FIGURE "VTT-41
-------
u>
O
HCI Continuous Strip
Pickling Line
PICKLE
LINE
/C\RINSE
WATER
Non- Contact
Cooling Waters
from Mills
FUME
DISCHARGE
HCI
SPENT
PICKLE
L
LIQUOR
-Recovered HCI
-A-
HCI REGENERATION
PLANT
PROCESS: R-CONTINUCUS IICI PICKLING/
ACID REGENERATION
PLANT 099
PRODUCTION : R-384METRIC TONS/TURN
(423 TONS/TURN)
-FeCI j
(Sold)
BOI LER
a HOUSE
/h\sump
CENTRAL MIXING
MANHOLE
PARSHALL
FLUME
DRAIN
N* 4
SETTLING
POND AND/OR
EMERGENCY
POND
Ns I POND
PUMP
STATION
SETTLING
POND
SECONDARY
NEUTRAL
SUMP
N? 3
Ns 2
SETTLING
SETTLING
POND
POND
To Mills-^-
-Z^s
RAW RIVER
WATER
PRIMARY
NEUTRAL
SUMP
,CONDENSER
^RUBBER
DISCHARGE
TANDEM
MILL
POND
PUMP
DISCH.
,
k
TANDEM
MILL
SETTLING
POND
SAMPLING POINT
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDf
CONTINUOUS HCL PICKLING/ACID REGENERATION
WASTEWATER TREATMENT Sn'STEM
WATER FLOW DIAGRAM
DWN.7/26/78
FIGURE 2EM2
-------
PNOCLSS: l< IIt I Al io PICKLING
PLANT: 100
production:
*1 Normalizing Line- 362 Metric Tons/Turn
(399 Tons/Turn)
6.82 l/sec
(108 gpm) PICKLE ACID
RAW WATER 20% HCl
0.375 lAec
(5.94 gpm)
*4 Pickling Line
2761 Metric Tons/Turn
(3066 Tons/Turn
A RAW WATER
(23.8 gpm)
1.5 l/fcec
I NORMALIZING
LINE
ACID RINSE
WET
LOOPING
PIT
UJIu
A PICKLING LINE
HCl CASCAOE RINSE
TANDEM
(21.5 gpm
36
lAec
CASCAOE
RINSE
1.87 l/sec
(29.7 gpm)
FUME
SCRUBBER
!
(4) FLOCCULATING
(21,129 gpm)
1,333 l/sec
CL/vRIFtERS
CLAR F ER
DISTRIBUTION
SOT HSM
SCALE
PIT 4-B
BOX
1,310 l/sec
e(X767gpnd
STRIP
DISTRIBUTION
BOX
B MIXING
CHAMBER
ACID
SUMP
OUTFALL
TO LAKE
"3 COLD
STRIP MILL
PRETREATMENT
FACILITIES
(SCALPING PITS)
D.I.W.
WET WELL
3 CSM
EAST
—rhr*
(362 gpm)
22.84 l/sec
362 gpm)
22B4 Ifoc
•5 PICKLE
LINE
2
COLDMILL
SPENT ACID
*3
COLDMILL
SPENT ACID
/\ SAMPLING POINT
> PRODUCT FLOW
ONLY
AC D
*3 COLDMILlI A(82.6 qpmtj
ACID WASTES) 521 l/sec
80 TANDEM
PUMP
ENVIRONMENTAL PROTECTION AGENCY
HOUSE
SPENT ACID STORAGE TANKS
STEEL INDUSTRY STUDY
COLO ROLLING - ACID PICKLING
WASTEWATER TREATMENT SYSTEM
WATER FLOW DIAGRAM
*3 COLD ROLLED STRIP MILL
DEEP WELL
ACID INJECTION
"4 S ^5 PICKLING LINES
56" a 80" TANDEM MILLS
DWN.6/27/78
FIGURE 2)1-431
-------
OJ
to
City water
Make-up
Recycle
(I80gpm)'''
11.'4 l/sec
RECYCLE
SURGE
TANK /!t\
KOLENE
RINSE
TANK
JN
• »
o£
w
WASTE
PICKLE
LIQUOR
TANK
BRIGHT
ANNEAL
LINE
1*1
(90 gpm)
5.7 l/»ec."
(240 gpm)
15.1 I/sec."
ANNEAL
AND
PICK LING
LIQUORS
—Watte pickling
liquor
PICKLE TANK
FUME
SCRUBBERS
Slowdown
to creek
COOLING
TOWER
COLD
REDUCTION
MILL
"A
N» 3 STRIP
GRINDER
DECREASE
2
22.1 lAec.
(350 gpm)
SOLIDS
REMOVAL
FILTERS
PROCESS- COMBINATION ACID PICKLING-CONTINUOUS
PLANT= 121 a A
PRODUCTION1 55 METRIC TONS STEEL PICKLED/TURN
(61 TONS STEEL/TURN)
To creek
(170 gpm)
10.7 l/»ec. avg.
POLISHING
TANK
T
A
-~ Oil removal
(Contract disposal)
COOLING
TOWER
:r*
¦600 gpd
BOILERS
Sodium metabisulfate
feed (not in use)
-Btowdown
ACID
WASTES
SUMP
Overflow-
EQUALIZATION
TANK
NEUTRALIZA" ION
] TANK
Oil removal
(To contract
disposal)
Underflow—^
TWO
REACTOR/
CLARIFIERS
AIR
COMPRESSOR
COOLING
WATER
THICKENER
(20 gpm)"'
1.3 l/eec.
Disposal by
private contractor
TOWER
COOLING
TOWERS
i
k
i
>
COLD
REDUCTION
MILLS
Underflow-
Underflow
TWO
CENTRIFUGES
-^Slowdown
to creek
NOTES: (I) Company supplied
design flow data
(2) Weir measurements
I
Centrifugate -
SOLIDS
REMOVAL
FILTERS
A
SAMPLING POINT
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
COMBINATION ACID PICKLING'CONTINUOUS
WASTEWATER TREATMENT SYSTEM
WATER FLOW DIAGRAM
Dwn.6/21/77
FIGURE 3ZH-44
-------
PROCESS: COMB. ACID PICKLING - BATCH
PLANT:
PRODUCTION -3.6 METRIC TONS/TURN
(4 TONS/TURN)
81,800 l/DAY
(21,600 GPD)
/lai l/DAT
(40 GPD)
LIME
9840 l/DAY
(2600 GPD)
v 12,100 l/DAY
(3,200 GPD)
2,120 l/DAY
(360 GPD)
12100 l/DAY
(3200 GPD)
151 l/DAY
(40 GPD)
DISCHARGE
TO POTW
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
COMB. ACID PICKLING - BATCH
WASTEWATER TREATMENT SYSTEM
WATER FLOW DIAGRAM
FIGURE 521-45
SCRUBBER
BAR WASH
WATER
TUBE WASH
WATER
PICKLING OPERATION
THREE STAGE OVERFLOW
NEUTRALIZATION PIT
-------
ACID PICKLING SUBCATEGORY
SECTION VIII
COST, ENERGY, AND NONWATER QUALITY IMPACTS
Introduction
This section addresses the cost, energy, and nonwater quality impacts
of applying the different levels of pollution control to acid pickling
operations. Topics of discussion include actual treatment costs
incurred by plants sampled, the alternative treatment systems
considered for use in the pickling subcategory, and the cost, energy,
and other nonwater quality impacts associated with the application of
the BPT, BAT, BCT, NSPS, and Pretreatment alternative treatment
systems. In addition, the BCT cost comparison and the consumptive use
of water are addressed.
Actual Costs Incurred by Plants Sampled for This Study
The water pollution control costs for the acid pickling operations
sampled during this study are presented in Tables VI11—1 through
VI11-12. The costs were derived from data supplied by the industry at
the time of sampling or from data submitted in response to the D-DCPs.
The costs have been adjusted to July 1978 dollars. Where central
treatment systems are present, the industry often supplied total cost
data for the entire treatment system. These costs were analyzed and
apportioned to determine costs attributable to acid pickling wastes.
In some instances, standard cost of capital and depreciation factors
were applied to the reported costs to determine those portions of the
annual costs of operation. In the remaining instances, those costs
were provided by the plants.
Control and Treatment Technologies
Recommended for Use in Acid Pickling
The treatment components and systems incorporated in the BPT and BAT
alternative treatment systems are presented in Tables VIII-13 through
VIII-16. The following items are described for each treatment step.
1. Treatment and/or control methods employed
2. Status and reliability
3. Problems and limitations
4. Implementation time
5. Land requirements
6. Environmental impacts other than water
7. Solid waste generation and primary constituents
It should be noted that the use of these control and treatment
technology components will not be required by the final regulation.
Any treatment system which achieves the proposed effluent limitations
is adequate.
345
-------
Cost, Energy, and Nonwater Quality Impacts
General Introduction
The Agency estimated cost and energy requirements on the basis of the
alternative treatment systems developed in Sections IX through XIII of
this report.
Estimated Costs for the
Installation of Pollution Control Technologies
A. Costs Required to Achieve the Proposed BPT Limitations
The Agency has made estimates of the expenditures needed to bring
acid pickling facilities from current treatment levels to a level
from which BAT technology can be installed. This level is
referred to as the "BAT Feed Level." These costs were considered
as "BPT Required" costs for purposes of the economic impact
analysis of the industry. To develop the costs required to
achieve this level, a cost summary based upon a treatment model
concept has been established. As explained above, this model
concept recognizes the types of treatment systems presently
installed and includes the types of components that the plants
will install in the future.
In order to develop BPT compliance costs, it was necessary to
develop BPT models sized to represent the average pickling plants
in the United States. Separate model sizes were developed for
batch and continuous operations in each acid pickling
subdivision. The model sizes (tons/day) were developed on the
bases of the average production capacities of each type of acid
pickling operation. The components incorporated in the various
treatment models are also representative of actual acid pickling
operations.
Using the rationale explained above, a plant by plant inventory
was conducted for each acid pickling segment to determine the
number of plants in each model configuration. Using updated flow
rates (see Section X) and the model sizes described previously,
unit costs for each treatment component were developed. Total
costs were then calculated by applying the treatment component
model costs, adjusted for size, to each acid pickling site. BPT
Capital Cost Tabulations are presented for all acid pickling
lines in Tables VIII-27 through VIII-35 . The estimated capital
costs of BPT technology in this subcategory are $309 million
{July 1978 dollars). Of this total, equipment valued at $138.5
million is currently in place at various pickling facilities as
of January 1978. The remaining $170.5 million remains to be
expended for additional treatment equipment. The estimated
annual operating costs for all acid pickling operations are
approximately $68 million. Tables VIII-17 through VIII-26
present BPT model capital and annual costs and effluent flows and
concentrations for each acid pickling subdivision. Table VIII-58
details the capital and operating costs at BPT for all segments
of the acid pickling subcategory.
346
-------
B. Costs Required to Achieve the BAT Limitations
The Agency considered three BAT alternative treatment systems for
all acid pickling segments except for sulfuric acid recovery.
These operations achieve zero discharge at BPT. Therefore, no
additional treatment components are necessary at the BAT level.
For all other segments of the acid pickling subcategory, BAT
Alternative No. 1 consists of a cascade rinse system. BAT
Alternative No. 2 adds sulfide precipitation and a filtration
system to the BAT 1 component. BAT Alternative No. 3 achieves
zero discharge through a cascade rinse system, evaporation, and
100% recycle. Additional details and rationale for these
alternatives are provided in Section X. The additional capital
and operating costs at BAT for operations in the various acid
pickling segments appear in Tables VIII-36 through VIII-42.
Table VIII-59 details the capital and operating costs for the
three BAT alternatives for all segments of the acid pickling
subcategory.
C. Costs Required to Achieve BCT Limitations
The BCT cost analyses for the various acid pickling segments are
presented in Tables VIII-43 through Vlll-46, while additional
information regarding BCT is provided in Section XI.
D. Costs Required to Achieve NSPS
Two different NSPS alternatives are being considered for
hydrochloric and combination acid pickling operations and one for
sulfuric acid pickling. New facilities constructed after the
proposal of this regulation will be required to meet NSPS. Model
costs have been developed for the NSPS alternative treatment
systems. These costs are shown in Tables VII1-47 through VII1-53
for pickling operations.
E. Costs Required to Achieve Pretreatment Standards
Pretreatment Standards apply to those existing (PSES) and new
{PSNS) sources which continue or elect to discharge to POTW
systems. Tables VII1-54 through VII1-57 present the costs of the
pretreatment alternative systems developed for each segment of
the acid pickling subcategory.
Energy Impacts
Moderate amounts of energy are required for the various levels of
treatment in the acid pickling subcategory. Major energy expenditures
for the subcategory occur at the BPT treatment level. BAT
Alternatives No. 1 and 2 require little or no additional energy.
However, BAT Alternative No. 3 is extremely energy intensive. The
hydrochloric acid regeneration segment is the only one where BAT No. 3
energy costs are not greater than BPT energy costs. This is due to
the acid regeneration system which requires additional energy. The
sulfuric acid recovery models only incur energy costs at BPT, since
the system achieves zero discharge at this level of treatment.
347
-------
A. Energy Impacts at BPT
The estimated energy requirements are based upon the assumption
that all acid pickling operations will install treatment systems
similar to the alternative treatment systems which have flows
similar to those of the models discussed in Section IX. On this
basis, the estimated annual energy usage at the "BAT Feed Level"
for all pickling operations is 423 million kilowatt hours of
electricity. This estimate represents about 0.7 percent of the
57 billion kilowatt hours used by the steel industry in 1978.
Refer to Table VI11-60 for a detailed analysis of the BPT energy
requirements for the acid pickling segments.
B. Energy Impacts at BAT
The estimated energy requirements for the BAT treatment
alternatives are based upon the same assumptions noted above for
BPT. The estimated energy requirements needed to upgrade
facilities to the three BAT alternatives appear in Table VIIl-60
for the segments of the acid pickling subcategory.
C. Energy Impacts at BCT
The estimated energy requirements for the BCT level of treatment
in the acid pickling subcategory appear in Table VIII-60.
D. Energy Impacts at NSPS, PSES, and PSNS
The energy requirements for the NSPS, PSES, and PSNS treatment
models appear in Table VIII-60. Only model-based estimates are
presented for NSPS and PSNS as estimates of future additions of
capacity were not made as part of this study. The energy
consumption associated with PSES is included in the totals for
BPT and BAT.
Nonwater Quality Impacts
In general, there are minimal nonwater quality impacts associated with
the alternative treatment systems. Air pollution, solid waste
disposal, and water consumption impacts were considered.
A. Air Pollution
Sulfide addition is incorporated in the BAT, NSPS, PSES
alternative treatment systems and PSNS Alternative No. 2. In the
event of treatment process control upsets, the atmospheric
discharge of sulfides could occur. However, the use of FeS
rather than H2S is recommended to avoid this problem. No other
air pollution impacts will result from the installation of any of
the treatment components considered. Sulfide addition is not the
selected alternative.
348
-------
B. Solid Waste Disposal
Considerable amounts of solid wastes will be generated at the BPT
level of treatment, consisting primarily of metal hydroxide
sludges that result from the lime neutralization step. Very
little additional sludge will be generated as a result of
installation of the BAT components. The amounts of dry solids
that can be expected for operations in the various pickling
segments appear in Table VII1-61.
C. Water Consumption
The Agency does not expect that a significant amount of water
will be consumed as a result of the installation of BPT
technology in the acid pickling subcategory. The model treatment
system includes recycle for fume scrubber streams. Some water
may be consumed in these systems; however, the amount is expected
to be minimal. No cooling devices are envisioned for these
recycle systems, so evaporation will not be a problem. Hence, no
significant water consumption is expected for this subcategory at
the BPT level. No appreciable amounts of water are expected to
be consumed at any other treatment level in the acid pickling
subcategory.
Summary of Impacts
In summary, the Agency concludes that the pollutant reduction benefits
described below for the acid pickling subcategory justify any adverse
energy and nonwater quality environmental impacts.
Effluent Discharges (Tons/Year)
Pollutant
Raw Waste
Proposed BPT Proposed BAT
Flow (MGD)
TSS
Oil & Grease
Fluoride
Toxic Metals
Toxic Organics
Dissolved Iron
172.7
69. 2
15.0
551
36,211
5,003
29,345
31,918
3,819
850
257
141
80.8
15.5
0.3
18.3
4.6
544,989
86. 1
1 .7
85.0
NOTE: PSES discharges are included in those for BPT and BAT.
349
-------
TABLE VIII-1
EFFLUENT TREATMJNT COST
SULFURIC ACID PICKLING - BATCH SPENT OONCEOT RATES
(All costs are expressed in July 1978 dollars)
Plant Code
1-2
0-2
P-2
Q-2
R-2
R
Reference No
0856P
0590
0312
0894
0240 B
0240A
Initial Investment
1,203,800
413,800
322,490
512,960
469, 360
280,000
Annual Cost
Cost of Capital
51,760
17,790
13,870
22,060
20,180
12,040
Depreciation
120,380
41,380
32,250
51,300
46,940
28,000
Operation & maintenance
49, 910
2,320
-
19,910
27,820
-
Energy and Power
25,710
-
101, 730
24,880
61,030
59,660
co Other
CT1
484,000
-39,230
-34,170
-102,110
35,120
-
TOTAL
731,760
22,260
113,680
16,040
191,090
99,700
$/Ton
2.81
0.56
3.11
0.51
0.58
0.38
Plant Code
090
091
096
098
Reference No
0476A
0612
01121
0684D
Initial Investment
448,550
394,800
817,600
NR
AnnualCost
Hauling
Cost of Capital
19,290
16,980
35,160
C08tS
Depreciation
44,860
39,480
81,760
estimated
Operation & Maintenance
34,940
34,380
34,230
at
Energy and Power
6,860
22,800
2,900
210,000/yr
Other
-11,830
3,600
3,730
—
TOTAL
94,120
106,440
157,780
210,000
$/Ton
4.92
0.52
17.46
1.41
NR: Ho response
-------
TABLE VIII-2
EFFLUENT TREATMENT COST
SULFURIC ACID PICKLING-BATCH RINSEWATER
(All costs are expressed in July 1978 dollars)
Plant Code
1-2 (1)
1-2 (2)
R-2
S-2
Reference No.
0856P
0856P
0240 B
0256G
Initial Investment
83,920
20 9,800
64,000
16,730
Annual Cost
Cost of Capital
3,610
9,020
2, 750
720
Depreciation
8,390
20,980
6,400
1,670
Operation and
Maintenance
820
2,060
3,790
4,380
Energy and Power
10
30
8,320
3,100
Other
780
1,990
4,790
90,060
TOTAL
13,610
34,080
26, 050
99,930
$/Ton 0.19 0.18 0.079 1.06
Plant Code R
Reference No 0240A
Initial Investment 144,240
Annual Cost
Cost of Capital 6,200
Depreciation 14,420
Operation and
Maintenance
Energy and Power 29,830
Other
TOTAL 50,450
$/Ton 0.19
090 0 91 096
0476A 0612 01121
178,080 794,540
7,660 34,179 70,700
17,810 79,450 164,410
7,420 69,200 68,450
5 , 380 45 , 890 5 , 800
1,160 7,250 7,450
39,410 235,960 316,810
2.06 1.15 35.06
(1) Spray rinse
(2) Cascade rinse
351
-------
TABLE VIII-3
EFFLUENT TREATICNT COST
SULFURIC ACID PICKLING - CONTINUOUS SPENT CONCENTRATES
(All costs are expressed in July 1978 dollars)
Plant Code
H-2
T-2
QQ-2
TT-2
WW-2
Reference No
0432A
0792B
0584 E
0856D
0868A
Initial Investment
Hauling
679,000
1,534,500
3,017,400
3,650,000
Annual Cost
costs
Cost of Capital
estimated at
29, 200
65,980
129, 750
156,950
Depreciation
$264,000/yr
67,900
153,450
301,750
365,000
Operation & Maintenance
-
65 , 940
464 , 050
313,260
Energy and Power
30,350
12,410
888 , 840
4,000
Other
-31,930
28,860
767,320
1,677,630
TOTAL
264,000
95,520
326,640
2,551,700
1,677,630
§/Ton
0.43
1.41
0.23
1.53
1.63
-------
TABU VIII-4
EFFLUENT TKIAXWNT COST
sulfuric AcxDria^no-OMTimniiB uisnun
(All
eoata ara axpreaaed in July 1978 dollara)
Plat Cod*
H-2
QQ-2
88-2
WW-2
Refaranc* No.
0432A
05848
0112A
0868A
Initial Imitant
297,630
2,087,240
144,450
716,170
Annual Coat
Coat of Capital
12,800
89,7S0
6,210
30,800
Depreciation
29,760
208,720
14,430
71,620
Oparation and
Maintenance
14,9*0
163,160
13,570
55,990
Energy and Paver
9,370
1S4,300
10,790
7,670
Othar
1,330
-
3,290
34,460
TOTAL
68,400
613,930
48,310
200,540
~ /Ton
0.11
0.43
0.078
0.29
353
-------
TABLE VIII-5
EFFLUENT TREATMENT COST
SULFURIC ACID PICKLING-CONTINUOUS FUME HOOD SCRUBBERS
(All costs are expressed in July 1978 dollars)
Plant Code
QQ-2
SS-2
WW-2
Reference No.
0584 E
0112 A
0868A
Initial Investment
25,350
14,310
71,620
Annual Cost
Cost of Capital
1,090
615
3,080
Depreciation
2,540
1,430
7,160
Operation and
Maintenance
1,980
1,350
5,600
Energy and Power
1,710
1,070
770
Other
-
330
3,450
TOTAL
7,320
4,795
20,060
$/Ton
0.0052
0.0078
0.029
354
-------
TABLE VIII-6
EFFLUENT TREATMENT COST
SULFURIC ACID PICKLING-BATCH AND
CONTINUOUS ACID RECOVERY PLANT WASTEWATER
(All costs are expressed in July 1978 dollars)
Plant Code 090
Reference No. 0476A
Initial Investment 1,630
Annual Cost
Cost of Capital 70
Depreciation . 160
Operation and Maintenance 70
Energy and Power 50
Other 10
TOTAL 360
$/Ton 0.019
355
-------
TABLE VIII-7
EFFLUENT TREATMENT COST
HYDROCHLORIC ACID PICKLING-BATCH SPENT CONCENTRATES
(All costs are expressed in July 1978 dollars)
Plant Code
Reference No
U-2
0480A
V-2
0936
Initial Investment
Annual Cost
Cost of Capital
Depreciation
Operation and Maintenance
Energy and Power -
Other 5860 7848
TOTAL
5860
7848
$/Ton
0.675
0.112
356
-------
TABLE VIII-S
EFFLUENT TREATMENT COST
HYDROCHLORIC ACID PICKLING-BATCH RINSEWATER
(All costs are expressed in July 1978 dollars)
Plant Code U-2
Reference No. 0480A
Initial Investment
Annual Cost
Cost of Capital
Depreciation
Operation and Maintenance
Energy and Power
Other 27311
TOTAL 27311
$/Ton 3.143
2180
1591
3771
0.054
357
-------
TABLE VIII-9
EFFLUENT TREATMENT COST
HYDROCHLORIC ACID PICKLING-CONTINOOUS SPENT CONCENTRATES
(All costs are expressed in July 1978)
Plant Code
Reference No.
Initial Investment
Annual Cost
Cost of Capital
Depreciation
Operation and
Maintenance
Energy and Power
Other
TOTAL
$/Ton
X-2
0060B
2,928,397
122 , 992
292 , 840
387,555
-1,397 , 605
-594 , 217
-1.046
Z-2
0396D
1,645,754
69,122
164,576
679, 595
913,292
2.021
BB-2
0060
1,717,169
72,120
171,718
101,850
33,333
379,021
0.166
091
0612
56,101
2,412
5,610
4,470
1,936
14,428
0.164
Plant Code
Reference No
Initial Investment
Annual Cost
Cost of Capital
Depreciation
Operation and
Maintenance
Energy and Power
Other
TOTAL
$/Ton
093
03 96A
1,645,754
69,122
164,576
679,595
913,292
2.021
095
0584 F
10,632,692
1,249,341
106,327
1,357,196
958,643
349,193
4,020, 700
099(1)
0528B
44,090
1,896
4,409
9,952
-24
437
16,670
0.030
(1) Includes only the costs of treating fune hood scrubbers.
358
-------
TABLE VIII-10
EFFLIKRT TREAT«KT COST
HYDRO CHLORIC ACID PICKLIHC - COHTIHUOUS RIHSEHATER
(All coats are expressed in July 1978 dollars)
Plant Code
1-2
Z-2
AA-2( 1)
BB-2
091
093
099
Reference Ho.
0856P
0396D
0384 A
0060
0612
0396D
0528B
Initial Investment
14,951
86,619
394 , 950
5,647,341
399,528
86,619
815,271
Annual Cost
Cost of Capital
628
3,638
16,589
237,189
39,953
8,661
81,527
Depreciation
1,495
8,661
39,495
564,733
19,300
-
21,493
Operation & Maintenance
145
-
120,966
366,104
13,786
35,768
-455
Energy and Power
-
35,768
4,543
304,612
12,532
-
162,543
Other
143
-
-
17,180
3,638
35,057
TOTAL
2,411
48,067
181,593
1,442,638
102,751
48,067
308,236
Sfton
0.560
0.106
0.215
0.633
1.166
0.106
0.556
(1) Applies to plant 100 in toxic pollutant study.
-------
TABU VIII-11
EFFLUENT TREATWNT COST
COMBINATION ACID PICTLINC-BATCH OPIBATICHS
(All costs are expressed in July 1978 dollars)
Plant Code
D
C
F
L
124
125
**
/ 1 \
Reference No.
0060D
0424
0856H
0440A
0088D
0884E
112H
Initial Investment
169,387
140,462
508,760
None
40,574
18,310
283,611
Annual Cost
Coat of Capital
7,284
6,077
21,877
-
1,745
' 787
12,195
Depreciation
16,938
14,135
50 , 876
-
4,057
1,831
28, 361
Operation and,.
Maintenance
Energy and Power
11,613
4,081
33
21,014
20,830
11,279
24,711
—
-
-
-
-
-
-
Other
1,006
9,335
5,088
-
-
TOTAL
33,836
33,042
82,140
26,102
26,632
13,897
65,267
$/too
19.91
0.95
4.69
0.83
6.40
2.89
1.22
(1): Cost data was received in the response to the detailed questionnaire.
(2)i Energy and power costs are included in operation and maintenance.
** : No plant code assigned.
-------
TABU VIII-12
EFFLIKNT TREATMENT COST
OOHBimTIOH ACID PICKLIHG-COHTINUOUS OPERATICHS
(All coats are expressed in July 1978 dollars)
Plant Code
D
I
0
121
Reference No.
0248 A & B
0432K
0176
0900
Initial Investment
_
546,051
674,735
1,100,683
Annual Coat
Cost of Capital
-
23,259
29,014
47,329
Depreciation
-
54,605
67,474
110,068
Operation & Maintenance (1)
-
17,696
39, 741
49, 986
Energy and Power (1)
-
-
-
-
Other
-
90,692
49,686
29,212
TOTAL
-
186,474
187,974
239,265
$/Ton
0.35
0.54
3.68
2.56
(1) Energy & power costs are included in operation and maintenance
-------
TABLE VIII-13
CONTROL AND TREATMENT TECHNOLOGIES
ACID PICKLING SUBCATEGORY
Sulfuric Acid - Batch and Continuous Acid Recovery
Treatment and/or
Control Methods Employed
A. Spent acid storage
B. Acid recovery syste
Status and
Reliability
Widely practiced.
Excellent, yielding no
aqueous discharge. Currently
in use at several pickling
plants.
Probl ess
and Limitations
None if storage tank
is constructed
properly.
High initial capital
cost is eventually
balanced by recovery
of usable products.
High energy requirement.
Impl men-
tation Land
Time Requirements
6 months 20* x 20'
24 months 200'x200'
Envi ronment al
Impact Other
Than Water
None
Ferrous sulfate
heptahydrate
Solid Haste
Generation and
Primary
Consti tuents
None
Generates large
amounts of
is highly soluble FeSO.^H^O
so it cannot be crystals,
landfilled.
-------
TABLE V1II-14
CONTROL AMD TREAT«lfT TECHNOLOGIES
ACID PICKLIHG SUBCATEGORY
Sulfuric Acid - Batch and Continuous Neutralization
Treatment and/or
Control Met ho da Employed
A. Spent acid equalization
B. FHS recycle blowdown
goes to further treataent.
C. Equalisation
D. neutralization
with liae to raise pH to 6-9.
E. Flocculation with
polyaer to aid flocculation.
P. Aerati<
G. Settling Basin
(last step of BPT).
Stat us and
Reliability
Widely practiced.
Practiced at aany
operations in the
subcategory.
Practiced at aany operations.
Oil separator not needed
unless cold aill wastes are
jointly treated.
Practiced at a aajority of
operations.
Widely practiced.
Reliable when attention is
given to operation and
aai ntenance.
Practiced at aany
operations in the
subcategory.
Problems
and Liaitations
Hone if storage tank
is constructed
properly.
Requires sufficient
blowdown to reduce
possibility of dissolved
solids build up and
plugging.
Basin aust be sized
sufficiently to
accoaaodate batch
duap and other
irregular flows.
Increased cheaical
cost. Considerable
amounts of solids are
generated which aust
be recovered.
Iapleaen-
t at ion Land
Tiae Requireaents
6 aonths 20' x 20'
Increased che
costs.
lical
HigJ) capital costs.
Sludges hard to
dewater.
Accuaulated solids
aust be periodically
reaoved.
2 aonths 25* x 251
3 aonths 50'x50'
3 aonths 50'x50'
6 aonths 2S'x2S'
9-12
months
6 aonths
200' x 200'
Envi ron ent al
Impact Other
Than Water
None
None
None
See solid waste
impacts.
None
Potential for
fine generation
Solid Waste
Generation and
Primary
Constituents
None
None
Any oils collected
aust be landfilled
or incinerated.
Lime addition
increases the aaount
of sludge which aust
be landfilled.
No significant
aaount of sludge
generated.
Increased metallic
precipitates.
Accuaulated solids Sludges aust be
must be disposed landfilled.
of properly.
-------
TABLE VIII-14
CONTROL AND TREATMENT TECHNOLOGIES
ACID PICKLING SUBCATEGORY
PACK 2
Treatment and/ or
Control Methods Employed
BAT Alternatives
H. Cascade rinse iy»t« to
reduce riiaewater discharge
(end of BAT Alternative 1).
I. To H, add sulfide
precipitation to fon
^ Metallic precipitates.
J. Filtration of overflew
(end of BAT Alternative 2)
K. To H, add an evaporation
system.
Status and
Reliability
Practiced at niaerous
operations in other
subcategories.
Used in various industrial
wastewater treatment
operations for toxic metal
removal.
Practiced at ninerous
operations.
Demonstrated in the power
generation industry.
L. Recycle distillate quality Demonstrated in the power
effluent back to process (end generation industry,
of BAT Alternative 3).
Problems
and Limitations
Implemen-
tation Land
Time Requi regents
Envi ronmental
Impact Other
Than Hater
Sol id Waste
Generation and
Primary
Constituents
Requires coordination
with rinsewater flow
ratios.
Care must be exercised
in the handling of the
feed solution. The
treatment process
control is required to
prevent odor problems.
Hydraulic overloads
must be controlled.
Reeds maintenance.
Economics depend on
integration of this
system into the water
cycle.
6-12
months
50'x100'
6 months 20'x20*
15-18
months
25' x 25*
6 months 60 'x60 '
None
Precipitates need
proper disposal.
9ulfide odors
can resul t from
improper control.
Backwash solids
must be properly
disposed.
None
Precipi tates
be filtered.
¦us t
The backwash solids
are removed by
vacuum filtration.
Uses approximately Slurry generated
90 kwh/100 must be dewatered.
gallons of feed- Sludge generated
water. is decreased.
None
2 months 25'x25'
None
None
-------
TABLE VIII-15
CONTROL AND TREATICMT TECHNOLOGIES
ACID PICKLING SUBCATEGORY
Hydrochloric Acid - Batch and Continuous
Treatnent and/or
Control Methods Employed
A. Spent acid storage
B. Install acid regeneration
systea (this step is applicable
only to continuous acid
regeneration process).
C. FHS Recycle - blowdown
goes to futher treatment.
D. Equalization
E. Add line to raise the pfl
to 6-9 in mixing tank.
Status and
Reliability
Practiced at many
operations in the
subcategory.
Good with proper attention
to operation.
Practiced at many operations
in the subcategory.
Practiced at many operations
in the subcategory.
Problems
and Limitations
None, if storage
tank is constructed
properly.
Requires coordination. 6-12
months
Implesen-
tation Land
Time Re qui rement s
6 months 20' x 20'
Requires sufficient
blowdown to reduce
possibility of dissolved
solids buildup and
plugging.
Equalization basin
must be sufficiently
large to accommodate
batch dusp or other
irregular flow.
Practiced at a majority of Increased chemical
operations in this subcategory, costs. Considerable
amounts of solids are
generated which must
be treated.
200'xAOO'
2 months 25'x25'
3 months S0'x50'
3 months 50'x50'
Environmental
Impact Other
Than Water
None
Energy intensive
None
None
See sol id was te
impacts.
Solid Uaste
Generation and
Primary
Constituents
None
Sludges must be
disposed of in
a landfill.
None
If any oils are
collected, they
must be incinerated
or landfilled.
Addition of lime
increases amount
of sludges generated
Sludges must be
landfilled.
-------
TABLE VIII-15
CONTROL AND TREATMENT TECHNOLOGIES
ACID PICKLING SUBCATEGORY
PAGE 2
Treatment and/or
Control Methods Employed
F. Polymer addition
to aid f locculation.
G. Aeration
H. Thickener
^ I. Vacum Filter to thickener
CT underflow (last step in BPT).
BAT Alternatives
J. Cascade rinse systea to
reduce rinsevater discharge
(end of BAT Alternative 1).
K. To J, add sulfide
precipitation systea.
L. Filtration of overflow
(end of BAT Alternative 2).
H. To Jv install vapor
compression/ evaporation
systea.
Status and
Reliability
Widely practiced.
Reliable method of
promoting settling.
Good when given attention to
operation and maintenance*
Practiced by many operations
Practiced at many operations
Practiced at numerous
operations.
Used in various industry
treatment opertions for
purpose of toxic metals
removal •
Practiced at maerous
operations
Demonstrated in power
generation industry.
Problems
and Limitations
Increased chemical
costs.
Implemen-
tation Land
Time Requirements
6 months 20'x20'
Environmental
Impact Other
Than Water
None
Solid Waste
Generation and
Primary
Cons ti tuents
No significant
amounts generated.
High capital costs. 9-12
Sludges hard to months
dewater •
200 'x200'
Potential for Increased metallic
fuse generation. precipitates.
Needs considerable
maintenance.
6 months 150'xl25'
Produces sludge.
Sludges must be
landfilled.
Increased capital and 15-18 25'x25'
operating costs. months
Dewatered sludge Solids produced
requires disposal, must be landfilled.
Requires coordination 6-12
with rinsewater flow months
ratios.
50*xl00*
None
None
Care is to be exer-
cised in handling of
feed solution. Careful
treatment process
control required to
prevent odor problems.
Hydraulic overloads 15-18
must be controlled. months
6 months 20'x20'
Needs maintenance.
Economics dependent
on integration of this
system into water cycle.
25 * x 25'
6 months 60*x60'
Precipitates
requires proper
disposal. Odors
can result if
treatment process
is not controlled,
Backwash solids
must be properly
disposed.
Precipitates must
be filtered.
Backwash solids are
removed by vacuus
filtration.
Uses approximately Slurry generated
90 kwh/1000 must be dewatered.
gallons of feed-
water•
-------
TABLE VIII-15
CONTROL AND TREATMENT TECHNOLOGIES
ACID PICKLING SUBCATEGORY
PAGE 3
Treatment and/or
Control Methods Employed
N. Recycle distillate
to process (end of BAT
Alternative 3).
Status and
Reliability
Widely practiced in the
power generation industry.
Solid Haste
Implemen- Environmental Generation and
Problems tat ion Land Impact Other Primary
and Limitations Time Requirements Than Water Constituents
Hone 12-14 25'x25' None None
months
-------
TABU VIII-16
CONTROL AMD TREAT WITT TECHNOLOGIES
ACID PICKLING SUPCATEGORY
Combination Acid - Batch and Continuous
U)
o>
00
Treatment and/or
Control Methods Employed
A* Recycle FHS vaateiiter
with a blowdown
going to further treatment.
B. Equalisation with oil
separation.
C. Neutralisation with lime
to raise pH to 6-9.
D. Plocculaticn with polymer
to aid flocculationa.
E. Clarifier
F. Vacuus Piltration
of clarifier underflow
(last step of BPT) .
BAT Alternatives
G. Cascade rinse tyatcs
to reduce rinsewattr discharge
(end of BAT Alterntivn 1).
Status and
Reliability
Practiced at many
of the operations in the
subcategory.
Practiced at mmy operations.
Oil separator not needed
unless cold mill wastes are
jointly treated.
Practiced at a majority
of operations.
Widely practiced.
Practiced at nany operatic
Practiced at nany operatic
Practiced at msserous
operations in other
subcategories.
Probl ena
and Lisa tat ions
Requires sufficient
blowdown to reduce
to possibility of
dissolved solids buildup
and plugging.
Bssin aust be sized
sufficiently large
to accomodate batch
diap and other
irregular flows.
Increased cheaical
coat. Considerable
aaounts of solids are
generated which aust
be trested.
Implemeo-
tation Land
Tiae Requirements
2 months 25'*25'
3 months 50'xSO1
Increased cheaical
coats.
Need considersble
aai ntenance.
Increased capital
and operating costs.
Requires coordination
with rinsewater flow
ratios.
3 months 50'xSO1
6 months 25,x25*
6 months 150axl25'
6 aonths 25'x25*
Environmental
Impact Other
Than Water
None
None
See solid
waste iapacts.
Solid Waste
Generation and
Primary
Constituents
None
Produces
sludge.
Dewatered sludge
will require
disposal •
6-12
aonths
50'xl00'
None
Any oils collected
must be landfilled
or incinerated.
Lime addition
increases the
amount of sludge
which must be
landfilled.
No significant
mount of sludges
generated.
Sludges must
be landfilled.
Solids oust be
disposed via
landfill.
None
-------
TABLE VIII-16
COHTBOL AMD THEATMEKT TECHNOLOGIES
ACID PICKLWC SCBCATEGC*?
PAGE 2
Treataent and/ or
Control Method* Employed
H. To G, add sulfide
precipitation to font Metallic
precipitates.
Status and
Reliability
Used in various industrial
wastewater treatment
operations for toxic aetal
reaoval.
1. Filtration of overflow Practiced at nu
(end of BAT Alternative 2). operations.
J. To G, install vapor Deaonat rated in the power
compression/evaporation generation industry,
¦ystaa.
K. Recycle distillate
quality effluent back to
process (end of BAT Alternate
3).
Widely practiced
in the power generation
industry.
Probl ail
and Limitations
Care Bust be exercised
in the handling of the
feed solution. The
treatsient process
control is required to
prevent odor problea.
Hydraulic overloads
¦ust be controlled.
Needa maintenance.
Economics depend on
integration of this
systea in the water
cycle.
lapl Caen-
tat ion Land
Tiae Requirement»
6 aontha 20 '*201
Environmental
Impact Other
Than Hater
Precipitates
need proper dis-
posal. Sulfide
odors can result
frow improper
control.
Solid Haste
Generation and
Primary
Constituents
Precipitates Bust
be filtered.
15-18 25' x 25'
aonths
6 aonths 60'x60'
Backwash solids
Bust be properly
disposed.
Uses approxi-
aately 90 kwh/
1000 gallona of
f eedwater.
The backwash solids
are removed by vacua
filtration.
Slurry generated
must be dewatered.
Sludge generated
is decreased.
None
2 aonths Z5'x25'
Hone
None
-------
TABLE VIII-17
BPT MODEL COST PATAs BASIS 7/1/78 POPLARS
Subcategory: Pickling-Sulfwic Acid Models Size-TPD: 500
: Batch Oper. Days/Year : T5ff
: Neutralization Turns/Day : 3
C&TT Step
A
B
C
D
E
Total
-3
Investment $ * 10 ,
119
128
381
99
60
787
Annual Cost $ x 10
Capi tal
5.1
5.5
16.4
4.3
2.6
33.8
Depreciation
11.9
12.8
38.1
9.9
6.0
78.7
Operation & Maintenance
4.2
4.5
13.3
3.5
2.1
27.5
Sludge Disposal..
Energy & Power
~
0. 9
-------
TA11X VIII-18
BPT HO DEL COST DATA I BASIS 7/1/76 DOLLARS
Subcategoryi
rickllnt-Sulfurie Acid
Batch
Acid Recovery
Carbon I Specialty
Hodeli SiM'TPDr $00
Opar. Daya/Keer t JOT
Turna/Day I J
ClrTT Stop
-3
,-3
Inveatment 5 * 10
Annual Coat $ x 10
Capital
Depreciation
Operation & Maintenance
Cryatal Diapoaal
Energy i Power
TOTAL
US
S.l
11.»
4.3
11.1
3430
147.}
343.0
120.1
St.2
114.3
781.1
Total
3549
152.6
334.9
124.2
56.2
114.3
802.3
Leaa Credit
Net Total
(1)
21.1
4$. 3
735.6
45. J
756.8
f 2)
Effluent Quality
Flow, gal/ton
Total Suapendad Solida
Oil and Greaae
Diaaolved Iron
pHr Unit*
115 Ananic
U8 Cadaiua
11 9 Chroaitaa
120 Copper
122 Lead
124 Nickel
128 Zinc
BPT
Iffluent
Laval
(1) Credit for acid recovery.
(2) All values are in «g/l unla«» otharviia noted.
nx TO C*TT I TIP I
Ai Spaat Acid Storage Syateei
>l Acid Recovery SyaCea
371
-------
TABLE VIII-19
BPT MODEL COST PATAi BASIS 7/1/78 DOLLARS
Subcategory:
Fickling-Sulfuric Acid
Continuous
Heutraliution
Carbon & Specialty
Model: Size-TPD:
Oper, Day*/Year :
Turns/Day :
1980
"555
C&TT Step
-3
„-3
Investment $ i 10
Annual Coat $ x 10
Capital
Depreciation
Operation & Maintenance
Sludge Disposal
Energy & Power
Chemical Coat*
TOTAL
228
9.8
22.8
8.0
40.6
171
7.3
17.1
6.0
2.4
2.0
32.4
(2)
I
(2)
c
D
E
Total
757
149
116
1421
32.5
6.4
5.0
61.0
75.7
14.9
11.6
142.1
26.5
5.2
4.1
49.8
-
-
15.5
15.5
19.2
0.5
-
19.7
97.8
9.8
-
109.6
251.7
36.8
36.2
397.7
u>
K> BPT
... Effluent
Effluent Quality Level
Flow, gal/ton 250
Total Suspended Solids 50
Oil and Grease 10
Dissolved Iron 1.0
pH, Units 6-9
IIS Arsenic 0.10
118 Cadaiw 0.10
119 ChroisiuB 0.10
120 Copper 0.10
122 Lead 0.10
124 Nickel 0.20
128 Zinc 0.10
(1) Costs are all power unless otherwise noted.
(2) Total cost does not include power, because a credit is supplied for existing process water requirements.
(3) All values are in »g/l unless otherwise noted.
KEY TO C&TT STEPS
A: Spent Acid Equalization D: Polymer Addition, Aeration
B: FHS Recycle E: Setting Basin
C: Equalization and Lime Addition
-------
TABLE VIII-20
BPT H)DEL COST DATA: BASIS 7/1/78 DOLLARS
Subcategory:
Pickling-Sulfuric Acid
Continuous
Acid Recovery
Carbon & Specialty
Model: Size-TPD: 1980
Oper. Days/Tear : 260
Turns/Day : J
C&TT Step
.-3
Imeataeat $ * 10
Annual Coat $ z 10 J
Capital
Depreciation
Operation & Maintenance
Cryatal Disposal
Energy & Power
OJ
TOTAL
Less Credits
Ret Total
(1)
Total
264
11.3
26.4
9.2
46.9
46.9
4034
173.5
403.4
141.2
128.7
123.B
970.6
260.6
710.0
4298
184.8
429.8
150.4
128.7
123.8
1017.5
260.6
756.9
BPT
i.t Effluent
Effluent Quality Level
Plow, gal/ton 0
Total Suspended Solids
Oil and Crease
Dissolved Iroa
pB, Units
115 Arsenic
118 Cadaiuai
119 Chroaiui
120 Copper
122 Lead
124 Bickel
128 Zinc
(1) Credit for acid recovery.
(2) All values are in «g/l unless otherwise noted.
KEY TO C&TT STEPS
A: Spent Acid Storage Systeu
It Acid Recovery Systea
-------
TABLE VII1-21
CtTT Step
Inwataent $ x 10-'
Annual Cost 9 x 10
Capital
Depreciation
Operation & Maintenance
Sludge Diapoaal
Energy k Power
Cheaical Coat a
TOTAL
u>
Efflweat Quality*4*
Flo*, gal/too
Total Suapended Solid*
Oil and Cimm
Dissolved Iron
|«, Oaita
23 CU«nC«m
114 Antimony
115 Annie
lit CaAaioa
119 Cknaia
120 Copper
122 Lead
124 Hickal
126 Silver
128 Zinc
BPTHDDBLC06TDAIA: BASIS 7/I/?8 DOLLARS
Subcategory! Pickling-Hydrochloric Acid
» Batch-Heutralieation
( Carbon & Specialty
Model Sise-IFD I 190
Oper. Days/Tear: 260
Turns/Day I 2
n<3>
.(3)
Total
55
76
186
47
26
51
123
138
702
2.4
3.3
8.0
2.0
1.1
2.2
5.3
5.9
30.2
5.5
7.6
18.6
4.7
2.6
5.1
12.3
13.8
70.2
1.9
2.7
6.5
1.6
0.9
1.8
4.3
4.8
24.6
_
-
-
-
-
-
7.6
7.6
-
0.6
1.9
0.3
0.2
0.5
0. 1
1.3
4.5
-
-
-
11.0
2.1
-
-
-
13.1
9.8
13.6<»
35.0
19.6
6.9
9.6
22.2
33.4
150.2
BPT
Effluent
Level
280
50
10
1.0
6-9
0.01
0.10
0.10
0.10
0.10
0.10
0.10
0.20
0.10
0.10
-------
TABU VtII-21
BPT IODE1, OOST DATA: BASIS 7/1/78 DOLLARS
PICKLHG-HYDBOCHXKIC ACID
BJSrCBHKDTBALn«riai
MBS 2
(1) Coats are all power unless otherwise noted.
(2) Total cost does not inelode power, because a credit is applied for existing process water requirements.
(3) Treatment components are used in tandem.
(4) All values are in sg/1 unless otherwise noted.
KIT TO C4TT STEPS
CJ
-J
Ln
At Spent Acid Equalisation
B: FHS Recycle
C: Equalization
D: List Addition
B: Polymer Addition
F* Aeration
6: Thickener
Hi Vacuum Filter
-------
TABU VII1-22
HPT MODEL COST DATA: BASIS 7/1/78 DOLLARS
Subcategory: Pickling-Hydrochloric Acid Model Size-TPD :
: Continuous-Neutralisation Oper. Days/Tear:
i Carbon t>' Specialty Turns/Day :
C4TT Step
A -
B
C
D
K
F
g(3>
_H("
Investment $ x 10 ' ,
198
191
885
185
59
150
416
506
Annual Coat $ x 10
Capital
8.5
8.2
38.1
8.0
2.6
6.4
17.9
21.8
Depreciation
19.8
19.1
88.5
18.5
5.9
15.0
41.6
50.6
Operation fc Maintenance
6.9
6.7
31.0
6.5
2.1
5.2
14.6
17.7
Sludge Disposal
-
(?)
-
-
-
-
-
159.1
Energy i Power
-
10.5IZ'
2.0
0.6
2.1
1.4
15.6
15.6
Cheaical Coats
-
-
-
126.8
21.3
—
—
-
TOTAL
35.2
34.0<»
159.6
160.4
34.0
28.0
89.7
264.8
-------
U1U *111-22
BFT MOOS I. COST DATA: BASIS 7/1/78 DOLLARS
ncKLiaG-irn»ocax«ic acid
OOKTIBUOUS-WUTtALIZATIC*
PACE 2
(1) Coat* are all power unless otherwise noted.
(2) Total coat doea not include power, because a credit i» applied for exiating process water requirements.
(3) Treatment ctspoanti are wed is twta.
(*) All ssloes are in ag/1 m las a otherwise noted.
KEY TO CATT CTKFS
W
-J
At Spent Acid Equalisation
Bt M Icejcle
Ci Bfoalisatioa
Di Lis* Additioo
K: Poljaer Addition
Ft Aeration
Ci Thickener
H< Vacnoa Filter
-------
TABLE VIII-23
BPT MODKL COST DATA; BASIS 7fl /?8 POfclARS
Subcategory: Pickling-Hydrocfcloric Acid
Model Sixe-TPD ;
2760
: Continuoos-Acid Regeneration
Oper. Days/Year:
"317
: Carbon & Specialty
Turns/Day
•
—
C&TT Step
A
¦¦ » ¦¦
C
D
E
F ¦¦¦
G
h<3)
_i(3>
Total
Investment J r 10
198
4420
191
963
98
59
182
494
241
6846
Annual Cost $ * 10
Capital
8.5
190.0
8.2
41.4
4.2
2.5
7.8
21.2
10.4
294 .2
Depreciation
19.8
442.0
19.1
96.3
9.8
5.9
18.2
49.4
24.1
684.6
Operation 6 Maintenance
6.9
154.7
6.7
33.7^
3.4
2.1
6.4
17.3
8.4
239.6
Sludge Disposal. .
-
-
" (2)
-
-
-
-
-
18.1
18.1
Energy fc Power11'
-
307.3
10.5
41.9
1.0
0.6
2.8
1.4
4.9
359.9
Chemical Costs
-
-
-
-
27.4
29.2
-
-
-
56.6
TOTAL
35.2
1094.0
34.0*2>
213.3
45.8
40.3
35.2
89.3
65.9
1653.0
Less Credits
Acid Recover;
2304.6
2304.6
Iron Oxide Recovery
1543.6
1543.6
Ret Annual Coat
35.2
-2754.2
34.0(2)
213.3
45.8
40.3
35.2
89.3
65.9
-2195.2
BPT
... Effluent
Effluent Quality Level
Flow, gal/ton 450
Total Suspended Solid* 50
Oil and Grease 10
Dissolved Iron 1.0
pB, Knits 6-9
23 Chi or of or* 0.01
114 Antinoay 0.10
115 Arsenic 0.10
118 Cadkiw 0.10
119 Chroaiua 0.10
120 Copper 0.10
122 Lead 0.10
124 Rickel 0.20
126 Silver 0.10
128 Zinc 0.10
-------
TABLE VIII-ZJ
¦FT MDKL COST DATA! BASIS 7/1/79 DOLLARS
FICKLnC-flTMOCHARIC ACID
cohtiwoos-acid bgbkmxioh
PACK 2
(1) Coats are all power unless otherwise noted.
(2) Total cott does we include power, because a credit is applied for existing process water requirements.
(3) Treatment coaponents are used in tandea.
(4) All values are in ag/I unless otherwise noted.
KIT TO C4TT STEPS
A: Speat Acid Storage System
It Acid Regeneration
C: FHS Recycle
D: Equalisation
I! Line Addition
Fl Polyaer Addition
Gi Aeration
Hi Thickener
11 Vacuus Filter
-------
TABUS VIII-24
BPT MODEL COST DATA: BASIS 7/1/78 DOLLARS
Subcategory: Pickling - Combination Acid
; Batch-Other
: Carbon-Speciality
Model Size-TPD : 200
Oper. Days/Year: IftO
Turn*/Day : 2
C&TT Step
.-3
Investment $ x 10 ,
Annual Cost $ x 10
Capital
Depreciation
Operation & Maintenance
Sludge Disposal,.
Energy 4 Power
Chemical Costs
TOTAL
A
B
C
D
E( 3)
F( 3)
Total
52
88
92
40
85
162
519
2.2
3.8
3.9
1.7
3.7
7.0
22.3
5.2
8.8
9.2
4.0
8.5
16.2
51.9
1.8
3.1
3.2
1.4
3.0
5.7
18.2
0.6(2)
0.2
0.3
0.2
0.2
2.1
1.3
2.1
2.2
-
7.5
0.8
—
-
8.3
92(2)
15.9
24.1
8.1
15.4
32.3
105.0
Effluent,.
Quality
Fl
B: Equalization and oil separation E:
Cj Neutralisation with lime PJ
Flocculation with polymer
Clarifier
Vacuus Filter
380
-------
TABLE VIII-25
BPT MODEL COST DATA: BASIS 7/1/78 DOT.t.abs
Subcategory: Pickling - Combination Acid Model Size-TPD s 200
: Batch-Pip# & Tube Oper. Daya/Year: 260
s Carbon-Speciality Turn*/Day i —2
C&TT Steo
A
B
C
D
E(3)
F( 3)
Total
Investment ? x 10 .
52
208
109
56
154
192
771
Annual Coat $ x 10
Capi tal
2.2
8.9
4.7
2.4
6.6
8.2
33.0
77.1
26.9
4.9
2.6
Depreciation
5.2
20.8
10.9
5.6
15.4
19.2
Operation & Maintenance
1.8
7.3
3.8
1.9
5.4
6.7
Sludge Disposal,.
Energy & Power
0.6(2)
0.1
0.4
0.2
0.2
4.9
1.7
Chemical Coats
-
••
9.3
2.7
-
12.0
TOTAL
92(2)
37.1
29.1
12.8
27.6
40.7
156.5
Effluent
Level
700
Flow, gal/ton
Total Suspended Solids
Oil 4 Grease "
Fluoride «
Disaolved Iron ,
PH, Unit*
11S Arsenic
119 Chromium ®*J®
120 Copper J*»
122 Lead ®-J®
124 Nickel ®*J®
128 Zinc ®'"
0.10
(1) Coats are all power unleaa otherwise noted.
(2) raquiranantf0' iBCUd* b*C*U" * Cr,dU U «»FPUM for existing process water
(3) Treatment components are used in tandem.
(4) All values are in og/1 unleaa otherwise noted.
U1 TO C4TT STEPS
As FHS Recycle
B: Equalisation and Oil Separation
C> Neutralisation with Lime
D» Flocculation with Polymer
*« Clarifier
Pi Vacuum Pilter
381
-------
Subcategory
TABLE VIII-26
BPT MODEL COST DATA: BASIS 7/1/78 DOLLARS
Pickling - Combination Acid
Continuous
Carbon-Speciality
Modal Size-TPD : 500
Oper. Days/Year: 320
Turns/Day : 3
C&TT Step
A
B
C
D
E(3)
F( 3)
Total
_3
Investment $ x 10 ,
83
239
166
77
245
216
1116
Annual Cost $ x 10
Capital
3.6
14.1
7.1
3.3
10.5
9.3
47.9
Depreciation
8.3
32.9
16.6
7.7
24.5
21.6
111.6
Operation & Maintenance
2.9
11.5
5.8
2.7
8.6
7.6
39.1
Sludge Disposal.v
Energy & Power
Ji'2'
0.3
1.0
0.9
1.4
6.2
6.3
6.2
9.9
Chemical Costs
-
-
32.0
12.1
—
—
8.3
TOTAL
u.»(2)
58.8
62.5
26.7
45.0
51.0
258.8
BPT
Effluent,v Effluent
Quality Level
Flow, gal/ton 1000
Total Suspended Solids 25
Oil & Grease 10
Fluoride 15
Dissolved Iron 1<0
pH, Units 6-9
4 Benzene 0.05
115 Arsenic 0.10
119 Chromium 0.50
120 Copper 0.10
122 Lead 0.10
124 Nickel 0.25'
128 Zinc 0.10
(1) Costs are all power unless otherwise noted.
(2) Total does not include power, because a credit is supplied for existing process water
requirements.
(3) Treatment components are uaed in tandem.
(4) All values are in mg/1 unless otherwise noted.
KEY TO C&TT STEPS
A: FHS Recycle Ds
B: Equalization and oil separation E:
Ci Neutralization with lime Ft
Floceulation with polymer
Clarifier
Vacuum Filter
382
-------
TABLE VI1I-27
BPT CAPITAL COST TABULATION
BASIS)
7/1/78 DOLLAKS x 10
FACILITIES IN PLACE AS OF 1/1/78
9ubcat«goryi Pickling-Sulfuric Acid
i Batch Mautraliiatioo
i Carbon 4 Speciality
CfcTT 8 tap
Plant
Code
TPD
A
0048?
117
50
0060H
816
160
0088A
1594
535
0088D
769
154
0112
560
157
0112A
1029
183
0112C
2886
340
0112?
827
161
0112G
44
w
01121
287
83
0240A
58)
131
0240B
687
144
0256?
90
42
02560
471
TT5
0432A
1805
257
0460A
1281
209
0460C
105
47
04600
239
TP
0460E
180
64
0460?
28
21
0460C
225
74
0476A
250
78
0492A
474
115
0612
1137
195
Id
B
c
p
B
Plica
Required
Total
53
159
41
25
237
91
328
T7l
5TT
133
w
922
133
1055
m
m
198
TTo
238
1338
1576
166
493
106-22
78
997
22
1019
TT7
5OT
106
u
0
842
842
197
587
153
93
1030
183
1213
366
IT371
m
Tfi
1629
623
2252
T7T
5T5~
134
TT
334
730
1064
to-
89
23
14
30
154
184
st
273
71
43
408
156
564
TO)
m
109
U
625
240
865
T5F
m
120
71
689
264
953
sr
T35
35
2T
280
0
280
113
3OT
W
W
664
96
760
m
8!?
214
TTo
1700
0
1700
in
57ff
m
106
1175
209
1384
vr
IT?
J5T
25"
270
39
309
52
25*
64
3*
430
76
506
vs
JBlf
W
IS
69
357
426
TS
68
18
u
23
118
141
7?
2-36
61
37
352
135
487
m
25T
65
55
440
78
518
154
m
W
vs
551
211
762
¦m
162
W
1093
195
1288
383
-------
TABU VIII-27
1PT CAPITAL COST TABULATION .
BASISt 7/1/78 DOLUM *10
t facii.itus iii rues as or 1/1/78
PACE 2
C4TT8t«p
Plant
In
Coda
TPD
A -
B ¦
¦ c ¦
D
Placo
Inquired
Total
0640
758
153
164
489
127
77
730
280
1010
0684G
1143
1»
m
626
163
w
1098
195
1293
0684Q
372
100
VST
m
5T
3ff
659
0
659
0728
75
3r
JfT
lib
31
to
220
32
252
0SS6P
378
TBI
1BS
3IT
84
3T
481
185
666
0856S
222
73
7T
33*
61
17
151
332
483
08360
is*
ff
rt
110
55
33
71
364
435
0860F
1083
189
TOs
606
137
99
904
346
1230
0860C
733
150
ttt
m
123
7S
842
150
992
08648
651
139
IOT
440
TIT
7ff
782
139
921
0868A
373
129
TVS
517
VST
BT
617
236
853
0884C
18
16
ir
5r
13
r
17
89
106
0884D
18
16
17
52
13
8
17
89
106
08846
8
10
IT
32
8
5
43
18
61
0948A
189
66
7T
3T3
35
35
438
0
438
2*, 185* 10,334* 34,738*
•Total inclodaa confidential pianta.
HOTBl
Underlined coat* repreeent fecil Itiee in-plece, where two fijuree eppeer in tin column,
the underlined portion it it>-plaea( the now non-underlined portion rnaeioe to be inetailed.
BY T0-C6TT STIPS
At Spent Acid equalisation
Bi FBI lacjrcle
Ct Iqualiaation and Liaa Addition
Di Poljnanr Addition, Aeration
It Settling Baain
384
-------
TABLE VIII-28
BPT CAPITAL COST TABULATION
_3
Subcategory: Pickling - Sulfuric Acid Basiss 7/1/78 Dollars x 10
: Batch Acid Recovery : Facilities In Place as of 1/1/78
: Carbon & Specialty
C&TT Step
Code
TPD
A
B
In Place
Requi red
Total
0048B
450
112
2499
0
2,611
2, 611
0060C
63
34
768
34
768
802
0068
94
5ZT
977
44
977
1,021
0112B
240
77
1714
0
1,791
1,791
01121
282
84
1888
188 8
84
1,972
0240C
102
46
H5K
0
1,026
1,026
0384A
501
119
2665
0
2,784
2,784
0432E
30
22
492
22
492
514
0432 L
323
5T
2048
91
2,048
2,139
0460H
94
Vi
977
0
1,021
1,021
0584C
462
113
2539
113
2,539
2,652
0684 D
1400
m
4937
221
4,937
5,158
0684 E
1650
557
5449
243
5,449
5,692
0684 H
636
157
3075
137
3,075
3,212
0684 P
603
151
2979
133
2, 979
3,112
0684 V
150
"3*
1293
0
1,351
1,351
0856N
846
163
3650
163
3,650
3,813
0856P
1599
m
5347
239
5,347
5,586
0856Q
15
15
325
15
325
340
0856R
351
W
2153
96
2,153
2,249
085 6 T
258
w
1790
80
1,790
1,870
0916A
612
13*
3005
134
3,005
3,139
0920D
267
SI
1827
82
1,827
1,909
0948B
306
1983
89
1,983
2,072
3824*
60,969*
64,793*
NOTE! Underlined costs represent facilities in place. Where two figures appear in the
same column, the underlined portion is in place; the non-underlined portion remains
to be installed.
*: Totals include confidential plants.
KEY TO C&TT STEPS
A: Spent Acid Storage System
B: Acid Recovery System
385
-------
TABU VIII-29
BPT CAPITAL COST TABULATION
Subcategoryt Pickling - Sulfuric Acid B««ia:
S Continuou* Neutralisation :
; Carbon 6 Specialty
7/1/78 Dollar* x lO-3
Facilities In Place aa of 1/1/78
Plant Code
TPD
C4TT Stepa
A
B
C
D
E
0012 A
11,031
638
479
2121
418
326
0020B
801
132
"9?
"TOT
"87
"58
0060D
1,194
157
iir
490
97
75
0112D
1,156
165
T25
558
108
8?
0176
60
28
TT
"W
"15
T3T
0256A
414
8*
87
2 98
58
55
0256B
423
9T
88
300
59
46
0432A
2,088
235
m
781
154
120
0432B
1,686
TOT
rsr
687
T3T
106
0476A
127
~3J
146
29 ,
22
0528A
2, 577
266
2ro
187
17*
lis
058OC
45
~7T
18
78
12
15
0584 E
4,458
37IT
m
1232
243
189
0684 C
1,014
152
m
~!5T
TOT
^8
0792C
486
Tff
.326
64
50
08560
9,650
588
427
1957
38?
3or
0856r
2,560
265
199
883
174
136
0856V
339
"57
262
52
0846B
2,166
240
1ST
799
158
123
0868A
3,525
322
m
15TO
ITT
TO
0948C
5,844
436
337
1449
387
222
In Place
3,344
826
676
864
174
1S6
68
1,466
362
230
266
41
1,942
266
514
0
1,483
59
1,260
1,686
2,284
17,967
Eeqiilted
638
0
244
163
0
399
495
0
929
44
1,397
105
370
685
98
3,674
174
433
240
322
436
10,848
Total
3,982
826
920
1,029
174
555
563
1,466
1,291
274
1,663
146
2,312
951
612
3, 674
1,657
492
1,500
2,008
2,720
28,815
SOTEl Underlined catta repreaent facilitiea in place, tfhere two figure* appear in the aaae column, the underlined
portion i* in place; the non-underlined portion meina to be inatalled.
KEY TO C&TT STEPS
Ai Spent Acid Equalization
Br FHS Racyclt
Ct equalisation & Lis* Addition
Dj polya«r Addition, Atratioa
It Settling Bttin
386
-------
TABLE VIII-30
BPT CAPITAL COST TABULATION
Subcategory: Pickling - Sulfuric Acid
: Continuous Acid Recovery
: Carbon & Specialty
Basis: 7/1/78 Dollars x lO-3
: Facilities In Place as of 1/1/78
Plant
C&TT Step
Code
TPD
A
B
In Place
Required
Total
0384A
84
40
794
0
834
834
0432M
307
86
1727
86
1727
1813
0580
4
128
0
134
134
0760
482
113
2264
0
2377
2377
0792 B
480
113
2258
2258
113
2371
0856E
297
84
T55T
0
1777
1777
2344
6962
9306
MOTE: Underlined costs represent facilities in place. Where two figures appear in the
same column, the underlined portion is in place; the non-underlined portion remains
to be installed.
KEY TO C&TT STEPS
A: Spent Acid Storage System
B: Acid Recovery System
387
-------
TABLE VIII-31
BPT CAPITAL COST TABULATION
_3
Subcategory: Pickling - Hydrochloric Acid Basis: 7/1/78 Dollars x 10
: Batch Neutralization : Facilities In Place as of 1/1/78
: Carbon i Specialty
Plant C&TT Step
Code
TPD
A
B
C .
D
E
F
G
H
In Place
Required
Total
0060L
0.4
1
2
9
2
I
2
5
7
2
27
29
0176
16
12
17
85
19
12
19
50
63
98
179
277
0384A
768
127
176
865
197
118
199
506
640
506
2322
2828
0580A
4
5
7
37
8
5
8
22
27
42
77
119
0864B
273
68
94
465
106
63
107
272
344
642
877
1519
1290* 3482* 4772*
*: Totals do not include confidential plants.
NOTE: Underlined costs represent facilities in place. Where two figures appear in the same column, the underlined
portion is in place; the non-underlined portion remains to be installed.
KEY TO C&TT STEPS
A: Spent Acid Equalization
B: FHS Recycle
C: Equalization
D: Lime Addition
E: Polymer Addition
F: Aeration
G: Thickener
H: Vacuum Filter
-------
TABIE VlII-32
BPT CAPITAL COST TABULATION
Subcategory: Pickling - Hydrochloric Acid B fit: 7/1/78 Dollar* x 10~*
! Continuoua : Facilities In Place aa of 1/1/78
: Neutralixation
I Carbon & Specialty
Plant
Coda
TPD
A
& "
• - ¦
¦
_
0020C
582
78
75
0060
8107
378
355
0060D
207
42
~~us
0112B
5592
302
297
01120
8517
389
375
0112H
40
16
15
0320
7075
348
337
0384A
3708
236
TTJ
0396D
1134
116
112
0432C
4452
264
75X
0432D
3678
235
277
0448A
2797
200
T5I
0580 A
4
4
4
0580C
18
10
9
0S80D
105
28
27
0580 E
90
25
25
0580 F
90
25
24
0584A
9948
427
412
0612
234
45
43
0684 F
4824
277
2S7
0856F
2388
182
175
0856S
24
11
IT
0860F
69
22
21
0864B
3492
228
ITS
0868A
1590
142
T37
09Z0A
3399
224
717
0920C
2446
184
178
092 0G
2133
170
T55
094 SA
2637
193
w
C&TT Step
C D E F 0 H In Place Required Total
348 73 23 59 163 1 99 940 78 1,018
lW9 353 lTT iBS 7BT 955 4,566 378 4,944
TIT TT H TI 1 1JT 2U 281 547
1357 287 90 22 9 635 773 2,279 1,676 3,955
TTOJ 364 116 295 SI* 995 1,298 3,795 5,093
70 ~T5 5 12 "3T 40 150 56 206
1557 325 10? 255 737 890 3,318 1,238 4,536
tots m nr m m 604 497 2^94 3091
519 108 35 88 357 297 998 521 1,519
1177 244 2 2 2 67A 2>512 93a 3,450
TP5T 720 70 178 594 601 2,020 1,056 3,076
"S5I 186 W T5T ST5 510 186 2,424 2,610
18 T 1 3 8 10 34 18 52
53 9 3 7 2ff 25 9 117 126
124 2j 8 21 59 71 265 99 364
TTJ 3T ff 17 53 65 24 307 331
113 25 8 19 53 65 24 307 331
1910 399 127 324 898 1092 1,424 4,165 5,589
201 H ^ 115 160 588
1377 259 37 2TC 587 707 2,637 984 3,621
® ^ HE 464 1)729 646 1,375
TT Tt "J -» TJC 29 11 138 149
97 6 16 45 55 238 44 282
i22 52 SBT 2,172 811 2«983
125 rrr ® w 363 1,355 505 1,860
lBBJ TVS 67 TTff V7T 373 1,321 1,613 2,934
2|2 In 2 |li H HI 2,225 184 2,409
12 15 £ 12 S *3* 1.616 604 2,220
861 ISO 57 146 405 492 1,835 193 2,028
36,377 25,930 62,307
NOTE) Underlined coat* repreaent tacllitiea in place. Vhiti two Ilgurea appear in the aaae coliaan, the underlined
portion ia in place) the now-underlined portion raaaina to be inatalled.
KEY TO CtTt STOPS
Ai Spent Acid Equalization
B: FH8 Recycle
Ci Equalixation
Di Line Addition
E: Polymer Addition
Fi Aeration
Gi Thickener
Hi Vacuua Filter
389
-------
TABLE VII1-33
BPT CAPITAL COST TABULATIOH
Subcategory: Pickling - Hydrochloric Acid Basia: 7/1/78 Dollars x 10
: Continuous : Facilities In Place as of 1/1/78
t Regeneration
: Carbon 6 Specialty
Plant ¦ ¦ CtrrStcpa
Code
TPD
A
B
t
D
E
F-
6
H
V
In Place
Required
Total
0068
193
40
896
39
195
20
12
37
100
49
0
1,388
1,388
0384A
2808
200
4466
193
973
99
60
184
500
244
500
6,419
6,919
05288
2196
173
3854
167
839
85
51
159
5JT
210
4,370
1,599
5,969
0580
125
31
30
150
15
9
28
17
38
0
1,068
1,068
0580B
105
28
622
27
135
14
8
26
69
34
0
963
963
0584C
3066
211
4708
203
1026
104
63
194
526
257
526
6,766
7,292
0584 F
8325
384
8572
370
1868
190
114
353
955
467
9,530
3,746
13,276
0684B
2733
197
5155"
190
957
97
59
181
m
240
491
6,315
6,806
06841
1377
130
2912
126
635
65
39
120
355
159
3,302
1,209
4, 511
0856P
17
9
209
9
45
~5
3
9
~T5
11
0
323
323
18,719* 29,796* 48,515*
*: Totals do not include confidential plants.
ROTE: Underlined costs represent facilities in place. Where two figures appear in the awe col tain, the underlined
portion is in place; the non-underlined portion mains to be installed.
EET TO CtIT STEPS
At Spent Acid Storage
8: Acid Regeneration Systea
Ct FKS Recycle
D: Equalisation
E: Lime Addition
Ft Polyaer Addition
Ct Aeration
H: Thickener
It Vacuus Filter
-------
TABLE VtII-34
EPT CAPITAL COST TABULATION
BASIS: 7/1/78 DOLLARS x 10~3
: FACILITIES IN PUCE AS OF 1/1/78
Subcategory: Combination Acid Pickling
; Batch
: Carbon & Speciality
C&TT Step
Plant
In
Coda
TPD
A
B
-C-
D ~
8
P
Place
Requi red
Total
0020B
99
-
113
70
35
89
103
410
0
419
00601
117
-
TOT
W
ro
176
T55
259
322
581
0060 S
10
-
rr
TS
9
22
26
46
57
103
0060P
26
-
w
3T
16
40
46
121
62
183
0068
381
~
253
T57
79
T?9
232
0
920
920
0088A
72
-
93
58
29
73
85
338
0
338
0088C
546
-
m
TO
m
257
258
0
1142
1142
0088 D
52
-
77
48
24
60
70
125
154
279
0112A
1044
-
153
2SS
145
364
425
1685
0
1685
0112C
882
.
5T?
25ff
T3T
32?
335
1007
515
1522
0112H
552
-
m
TS5
99
259
290
761
389
1150
0176
728
113
m
231
117
235
342
1471
0
1471
0176C
23
vr
T9~
rr
rr
53"
0
171
171
01760
9
8
27
17
8
21
25
0
106
106
0248C
260
61
201
125
63
158
184
0
792
792
0248D
37
19
62
39
20
49
57
88
158
246
0248E
5
6
19
T7
6
13
17
0
75
75
0248?
1
2
7
4
2
6
7
10
18
28
0256P
30
17
55
%
17
53
50
166
50
216
0256H
0.3
r
T"
r
r
3
5
7
12
0256L
84
31
102
32
Bb
176
%
T75
127
VSl
0284A
177
48
160
95
35
146
275
354
629
0424
211
-
177
TTo
35
TO
163
343
303
646
0432E
15
11
vr
23"
IT
29
33
0
143
143
0440A
237
-
190
118
60
150
174
0
692
692
0476A
386
-
235
158
80
201
234
928
0
928
0496
411
80
m
165
53
20?
253
718
326
1044
0548A
63
-
86
17
33"
27
58"
79
207
106
313
05488
42
-
51
21
33
62
42
203
245
0580
45
-
70
55
22
55
64
0
255
255
0636
-
-
-
-
-
-
-
_
-
-
0684 P
96
19
145
90
46
115
133
0
548
548
0684 0
194
-
169
105
53
133
155
0
615
615
0684 V
194
51
169
105
53
133
155
0
666
666
391
-------
TABLE VIII-34
BPT CAPITAL 038T TABULATION ,
BASIS: 7 /I /7B DOLLARS * 10
: FACILITIES IS PLACE AS OP 1/1/78
PACE 2
C1TT Stap
Plant
In
Coda
IPC
A
¦ B ¦¦
0
D —
F
Placa
Kaqui rad
Total
0728
75
-
93
39
30
73
88
0
347
347
0776F
26
-
30
31
16
40
46
97
86
183
07760
3
-
T9
17
r
15
17
52
17
69
0776H
13
-
3J
JT
TO
TX
31
47
74
121
0776J
8
-
25
TS
8
OT
23
40
51
91
0792A
34
•
7f
V9
23
62
72
0
286
2S6
0856E
78
-
98
61
31
77
90
159
198
357
0856H
123
39
no
*r
41
102
119
313
199
512
0884 E
24
13
SB"
w
15
W-
44
45
145
190
0884 F
5
-
19
17
6
13
17
0
69
69
*ruTO~
~TOE"
•21586
*Total includes confidential plant*.
HOTS:
Underlined coat* represent facilities in-pi oca, what* two figures appesr in the saae colutn,
the underlined portion i» itr-placst tha new non-underlined portion raaaint to b* installed.
m to ott saps
At FH8 Xaeyela D: Poljner Addition
Bt Equalisation with oil separation It Clarifier
Ci Lisa Addition Pi Vacuus Filter
392
-------
TABLE VIII-35
BPT CAPITAL COST TABDLAIIOII
„-3
BASIS)
I
7/1/78 DOLLARS X 10
FACILITIES IN PLACE AS OP 1/1/78
Subcategory: Combination Acid Pickling
: Batch
< Carbon A Speciality
C6TT Stap
Plant
Coda
002 OB
0020C
0020L
0060
0060D
0060E
0112A
0112C
0176
0248B
02560
0284A
0432K
0432L
0648
0684 D
0860B
0860F
0948F
In
WD
534
906
386
308
1,833
100
96
131
128
1,877
577
161
739
34
129
1,083
390
45
82
• A"
B
C
. P
E
F
Placa
Raquired
Total
69
508
228
108
357
312
1,513
69
1,582
95
597
3T7
T59
5W
5T9
2, 078
95
2,173
57
517
TOT
8r
I9T
537
1,245
57
1,302
49
353"
m
n
T%
235
1,087
49
1,136
145
T7564
577
577
757
535
2,433
881
3,314
T5~
TBS
HI-
40
nr
114
254
325
579
25
181
ST
3?
157
111
543
25
568
29
OT
w
57
T35
T35
316
364
680
29
in
95
46
151
132
669
0
669
157
TvT79
270
TVS
663
3,362
0
3,362
rr
3*r-
m
TT3
375
317
798
859
1,657
35
247
ITT
33"
T75
152
585
186
771
85
vn
m
m
441
385
722
1,231
1,953
13
97
53"
21
sr
60
0
302
302
29
216
97
46
152
133
97
576
673
105
776
358
165
54
477
545
1,871
2,416
57
420
189
89
295
258
0
1,308
1,308
16
115
52
25
81
71
319
41
360
22
1ST
75
35
TO
TO
22
491
513
IP.M8 17735"
25,318
NOTE!
Underlined coat* repreaent faeilitiaa in-place, where two figurea appaar in tha aaaa colunn,
tha undarlinad portion 1* in-plac«| tha new non-underlined portion raaaina to ba inatalled.
KEY TO Oil STEP 8
Al FIB Recycle oi Polymer Addition
Bt Equalisation with oil aaparation Et Clarifier
Cs Lisa Addition ft Vacuus Viltar
393
-------
TABLE VIII-36
BAT MODEL COST DATA! BASH 7/1/78 DOLLARS
Subcategory: Picklinf-Sulfuric Acid
: Batch
i Neutralisation
Modal Siae-TPD I 500
Oper. Days/Year t IOT
Turns/Day i 3
Alternete 1
C&TT Step
G
Total
T
j
ToEat
" J" ' ~
—r~
Total
1 1
Investment $ x 10 -
114
114
34
lit
226
1256
66
1436
Annual Coat $ x 10
Capital
4.9
4.9
1.5
5.1
11.4
54.0
2.8
61.7
Depreciation
11.4
11.4
3.4
11.8
26.6
125.6
6.6
143.6
Operation & Maintenance
4.0
4.0
1.2
4.1
7.3
44.0
2.3
50.3
Sludge Ditpoaal
•
-
-
-
-
1.8
-
1.8
Energy & Power
-
-
0.2
1.8
2.0
23.8
0.2
24.0
Replacement Parta
15.2
15.2
-
-
15.2
-
-
15.2
Chemical Coata
-
-
0.7
-
0.7
-
-
-
TOTAL
35.5
35.5
7.0
22.8
65.3
249.2
11.9
296.6
Effluent Quality'1}
BAT
Feed
Level
Flow, gal/ton
360
Suspended Solids
30
Oil & Graaae
10
Dissolved Iron
1.0
pK, Units
6-9
115
Arsenic
0.10
118
Cadmium
0.10
119
Chromium
0.10
120
Copper
0.10
122
Lead
0.10
124
Hiclcel
0.20
128
Zinc
0.10
(1)
All values are in ng/1 unless
70
30
10
1.0
6-9
0.10
0.10
0.10
0.10
0.10
0.20
0.10
70
15
s.o
1.0
6-9
0.10
0.10
0.10
0.10
0.10
0.10
0.10
KEY TO C4TT STEPS
Gi Caacada tin**
H. Sulfide Precipitation
Is Filtration
JI Evaporation Sy«ta
Ki Recycle 1001
394
-------
TABU VIII-37
BAT HODP. COST PAIAl BASIS 7/1/78 DOLLARS
Subcategory:
Pickling-Sulfuric Acid
Continuoua
Heutralixatiaa
Carbon & Specialty
Modal Siw-TPD i 1980
Opar. Daya/Yaar i "TOT
Turna/Day J 3
Alternate 1
3-Alternate 1
C&TT Stap
"'33
InvifCaaat 9 x 10
Annual Coat $ x 10
Capital
Dapraci eti on
Operation i Maintenance
Sludga DUpo«al.,
Energy & fewar
Replacement Pacta
Chemical Coat
TOTAL
Effluent Quality'^
BAT
Feed
Laval
Vlou, gal/ton
250
Sua pe tided Soli da
30
Oil £ Graaae
10
Diaaolved Iron
1.0
PH
6-9
115
Araanic
0.10
118
Cedntiun
0.10
119
Chroniun
0.10
120
Coppar
0.10
122
Lead
0.10
124
Hickal
0.20
128
Zinc
0.10
""c
Total
x—
. ^ .
Total
J
K
Total
323
323
64
137
544
234.6
83
2752
13.9
13.9
2.8
6.7
23.4
100.9
3.6
118.4
32.3
32.3
6.4
15.7
54.4
234.6
8.3
275.2
11.3
11.3
2.2
5.5
19.0
82.1
2.9
96.3
-
-
-
-
-
4.3
-
4.3
-
-
0.3
2.2
2.5
58.2
0.3
58.5
42.8
42.8
-
-
42.8
-
-
42.8
-
—
1.4
-
1.4
-
-
-
100.3
100.3
13.1
30.1
143.5
480.1
15.1
595.5
55
55
0
30
15
.
10
5.0
-
1.0
1.0
-
6-9
6-9
-
0.10
0.10
-
0.10
0.10
.
0.10
0.10
-
0.10
0.10
-
0.10
0.10
_
0.20
0.10
.
0.10
0.10
-
(1) All valuaa ara in mg/1 unleae otherwiae noted.
«Y TO CtTT STEPS
as Caacade Rinae j; Evaporation Syat«
Bt Sulfide Precipitation K: Recycle 100%
It 1 titration
395
-------
TABLE VIII-38
BAT HODEL COST DATA! BASIS 7/1/78 DOLLARS
Subcategory! Pickling-Hydrochloric Acid Modal Size-TPD I 190
t Batch Neutralisation Oper. Days/Yaar : TTO
I Carbon t Specialty Turin/Day i 2
2 Alternate 1 plua:
3 Alternate 1 pluai
CftTT Step
Inveataant $ x 10
-3
,-3
Annual Coat $ x 10
Capital
Depreciation
Operation t Maintenance
Sludge Diapoaal.t
Energy * Power11'
keplacaent Parta
Cheaical Coeta
TOTAL
Effluent Quality*4'
BAT
feed
Level
flow, gal/ton
560
Suapended Solida
30
Oil t Creeae
10
Diaaolved Iron
1.0
pB, Onita
6-9
23
Chlorofon
0.01
114
Antiaony
0.10
115
Araenic
0.10
US
Cadaiua
0.10
119
Chroaiua
0.10
120
Copper
0.10
122
Lead
0.10
124
Nickel
0.20
126
Silvar
0.10
128
Zinc
0.10
I
Total
K(1>
Total
iiii
M(l>
local
"
63
63
29
72
164
1292
58
U13
2.7
2.7
1.2
3.1
7.1
55.6
2.5
60.7
6.3
6.3
2.9
7.2
16.4
129.2
5.8
141.3
2.2
2.2
1.0
2.5
5.7
45.2
2.0
49.5
_
0.1
0.2
0.3
12.1
0.2<2>
12.1
8.3
8.3
-
-
8.3
-
-
S.3
-
-
0.2
-
0.2
-
-
19.5
19.5
5.4
13.0
38.0
242.1
10.3(2)
271.9
90
90
0
30
15
«•
10
5.0
_
1.0
1.0
•
6-9
6-9
•
0.01
0.01
.
0.10
0.10
_
0.10
0.10
0.10
0.10
0.10
0.10
•
0.10
0.10
•
0.10
0.10
0.20
0.10
•
0.10
0.10
0.10
0.10
•
(1) Treatment componenta are uaed in tandea.
(2) Total coat doea not include power, because a credit ia applied tor exiating proceaa water requirement!.
(3) All valuta are in a(/l ualeaa otherwiaa noted.
KIT TO C4TT STEPS
II Caacade tinea J> Sulfide Precipitation
Ki Filtration Li Evaporation Syatan
Ki tecyele
396
-------
TABU VIII-39
BAT MODEL COST BAKU BASIS 7/1/78 DOLLARS
Subcategory! Pickling-Hydrochloric Acid Modal Size-TPD I 2760
1 Continuoua Neutralization Oper. Daya/Year I 312
» Carbon & Specialty Turna/Day t 3
2 Alternate 1 pluai
3 Altarnata 1 pluai
C&TT Step
I
Total
£1
Total
slii
Total
Inveataant, $ x 10~?
293
293
24
153
470
2003
33
2329
Annual Coat t * 10~
Capital
12.6
12.6
1.0
6.6
20.2
86.1
1.4
100.1
Depreciation
29.3
29.3
2.4
15.3
47.0
200.3
3.3
232.9
Operation i Maintenance
10.3
10.3
0.8
5.4
16.3
70.1
1.2
81.5
Sludge Diapoaal,.
Energy t Power
.
0.1
0.6
0.7
122.6
1>>
123.6
Replacement Parti
38.9
38.9
-
-
38.9
-
-
38.9
Cheaical Coata
**
*"
1.0
-
1.0
-
•
-
TOTAL
91.1
91.1
5.3
27.9
124.3 •
479.1
6.9<2)
577.0
Effluent Quality'4^
BAT
Peed
Lave!
Plow, gal/ton
320
Suapended Sot Ida
30
Oil & Creaaa
10
Diaaolved Iron
1.0
pHi Oniti
6-9
23
Chi orof on
0.01
114
Antiaony
0.10
115
Araenic
0.10
118
Cadaiua
0.10
119
Chroaiiai
0.10
120
Copper
0.10
122
Lead
0.10
124
Hickel
0.20
126
Silver
0.10
128
Zinc
0.10
35
30
10
1.0
6-9
0.01
0.10
0.10
0.10
0.10
0.10
0.10
0.20
0.10
0.10
35
13
5.0
1.0
«-»
0.01
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
(1) Treataant coaponanta are uaed in tandea.
(2) Total coat doea not include povtr, becauaa a credit i« applied for (xiating procaaa water requiraaenta.
(3) All valuaa are in ag/1 unle»» otherviae noted.
til TO CtTT STEP8
Ii Caacade tinaa Jt Sulfide Precipitation
K: Filtration Li Evaporation
Ml Recycle
397
-------
TABLE VIII-40
BAT MP DEL COST DATA! BA8I3 7/1/78 DOLLARS
Subcategory! Pickling-Hydrochloric Acid Model Siie-TPD : 2760
i Continuoua-Acid Neutralization Oper, Daya/Year : 312
I Carbon & Specialty Turns/Day i 3
2 Alternate 1 pluai
3 Alternate 1 pluai
-3
-3
C&TT Step
Inveatment, | i 10
Annual Coat j i 10
Capital
Depreciation
Operation 6 Maintenance
Sludge Diapoaal.s
Energy & power
Replacement Parte
Chemical Coeta
TOTAL
(4)
Effluent Quality
BAT
Feed
Level
Flow, gal/ton
430
Suapended Solid*
30
Oil fc Greaae
10
Diaaolved Iron
1.0
pB, Unit*
6-9
23
Chloroform
0.01
114
Antimony
0.10
US
Araenic
0.10
118
Cadmium
0.10
119
Chromiia
0.10
120
Coppar
0.10
122
Lead
0.10
124
Wickal
0.20
126
Silver
0.10
128
Zinc
0.10
I
Total
Jlii
Total
Mu>
Total
339
339
31
192
562
2398
40
2877
14.6
14.6
1.3
8.3
24.2
115.7
1.7
123.7
33.9
33.9
3.1
19.2
56.2
249.8
4.0
287.7
11.9
11.9
1.1
6.7
19.7
87.4
1.4
100.7
_
_
0.2
1.0
1.2
191.3
1.8<2)
191.3
45.0
43.0
-
-
45.0
-
-
45*0
-
-
1.3
-
l.S
-
-
-
105.4
105.4
7.2
35.2
147.8
644.2
7.1
748.4
70
70
0
30
15
•
10
5.0
-
1.0
1.0
•
6-9
6-9
-
0.01
0.01
•
0.10
0.10
•
0.10
0.10
-
0.10
0.10
-
0.10
0.10
-
0.10
0.10
-
0.10
0.10
•
0.20
0.10
-
0.10
0.10
•
0.10
0.10
-
(1) Treatment component* are uaed in tandem.
(2) Total coat do** not include power, becauae a credit ia applied for axiating procaaa water requirementa.
(3) All value* are in ag/1 unleia otherwiie noted.
PT TO C&TT STEPS
Ii Caacade Rinae
K> Filtration
Hi Recycle
Ji Sulfide Precipitation
Lt Evaporation
398
-------
TABU VIII-41
IAI HODEL COST DATA; BASH 7/1/76 DOLLARS
Subcategory! Combination Acid Pickling Modal Siae-TPD : 200
I Batch Oper. Days/Year : 260
I Carbon A Specialty Turn»/Day i 2
CATT Stap
-3
-3
Inveataent, $ x 10
Annual Coit 9 x 10
Capital
Depreciation
Oparation A Maintenance
Sludge Diapoaal,.
Enargy A Power
Chemical Coata
Replaceable Coata
TOTAL
1
2-Altarnate 1
plua:
3-Alternate 1
plus:
c
Total
H
1
Total
J
K
To tal
69
69
23
97
191
1467
24
1559
3.0
3.0
1.1
4.2
8.2
63.1
1.0
67.0
6.9
6.9
2.5
9.7
19.1
146.7
2.4
155.9
2. A
2.*
0.9
3.4
6.7
51.3
0.8
54.6
-
-
0.1
0.2
0.3
13.7
0.2<2)
13.8
9.1
9.1
0.1
-
9.1
-
-
-
-
-
-
1.5
-
9.1
21 .A
21.A
A.7
17.5
43.5
274.8
4.2<2>
300.4
BAT
Effluent Quality'3'
Feed
Laval
Flow, gal/ton
545
10}
105
0
Suapended Solida
30
10
15
-
Oil A Create
2.0
2.0
2.0
-
Fluoride
15
15
15
-
Diaaolvad Iron
1.0
1.0
1.0
-
pH, Unite
4-9
6-9
6-9
-
120 Coppe r
0.10
0.10
0.10
-
119 Chroaiiia
0.10
0.10
0.10
-
124 Nickel
0.20
0.20
0.10
-
115 Araenic
0.10
0.10
0.10
-
122 Lead
0.10
0.10
0.10
-
128 Zinc
0.10
0.10
0.10
-
(1) Coata are all power unleea otherviaa notad.
(2) Total coat doea not include power, bacauae a credit ia applied for exiating proceea water requireaenta.
(3) All valuaa are in ag/1 unlaaa otherwiaa noted.
REV TO art STEPS
Gi Caacade kinaa Jj Evaporation
Hi Sulfide Precipitation Ri Recycle
li filtration
399
-------
TABLE VIII-42
BAT MODEL COST DATA: BASIS 7/1/78 DOLLARS
Subcategory: Combination Acid Pickling Model Size-TPD : 500
: Continuous Oper. Days/Year : 320
: Carbon & Specialty Turns/Day : 3
1
2-Alternate 1
plus:
3-Alternate 1
plus:
C&TT Step
G
Total
H
t
Total
J
K
To tal
-3
Investment, $ x iO -
142
142
41
191
374
2473
38
2653
Annual Cox $ x 10
Capital
6.
.1
6.1
1.8
8.2
16.1
106.3
1.6
1K.0
Depreciation
14,
.2
14.2
4.1
19.1
37.4
247.3
3.8
265.3
Operation 6 Maintenance
5.
,0
5.0
1.4
6.7
13.1
86.6
1.3
92.9
Sludge Disposal.,
-
-
-
-
-
-
(?)
-
Energy i Power
-
-
0.2
0.9
1.1
122.3
0.7UJ
122.3
Chemical Coat*
-
-
0.9
-
0.9
-
-
-
Replacement Parts
18.
8
18.8
-
-
18.8
-
-
18.8
TOTAL
44,
.1
44.1
8.4
34.9
87.4
562 5
6.7<2>
613.3
BAT
Effluent Quality''*'
Peed
Level
Flow, gal/ton
1865
335
335
0
Suspended Solids
30
30
15
-
Oil & Grease
2.0
2.0
2.0
-
Fluoride
15
15
15
-
Dissolved Iron
1.0
1.0
1.0
-
pH, Units
6-9
6-9
6-9
-
4 Benzene
0.05
0.05
0.025
-
115 Arsenic
0.10
o. «¦
0.10
-
119 Chromium
0.10
0.10
0.10
-
120 Copper
0.10
0.10
0.10
-
122 Lead
0.10
0.10
0.10
-
124 Nickel
0.20
0.20
0.10
128 Zinc
0.10
0.10
0.10
(1) Coats are all power unless otherwise noted.
(2) Total coat does not include power, because a credit is applied for existing process water requirements*
(3) All values are in ng/l unless otherwise noted.
KEY TO C&TT STEPS
G: Cascade Rinse J: Evaporation
Us Sulfide Precipitation K: Recycle
It Filtration
400
-------
TABLE VIII-43
RESULTS OF BCT COST TEST
SULFURIC ACID PICKLING SUBCATEGORY
(Neutralization Systems Only)
A. Batch Type
BCT-1: lbs/year removed ¦ 29,383
Cost of BCT-1* » $35,500 $/lb -1.74 FAIL
*Include8 the cost of all BAT components
BCT-2: lbs/year removed ¦ 21,901
Cost of BCT-2* - $58,300 $/lb » 2.66 FAIL
*Includes the cost of all BAT components except ———
sulfide precipitation.
B. Conti nuous Type
BCT-1s lbs/year removed » 48,485
Cost of BCT-1* ¦ $100,300 $/lb - 2.07 FAIL
~Includes the cost of all BAT components. '
BCT-2 lbs/year removed ¦ 53,256
Cost of BCT-2* - $130,400 $/lb - 2.45 FAIL
~Includes the cost of all BAT components except ——
sulfide precipitation.
401
-------
TABLE VIII-44
RESULTS OP BCT COST TEST
HYDROCHLORIC ACID PICKLING SUBCATEGORY
(Neutralization Systems)
A. Batch Type
BCT-1: lbs/year removed =5,420
Cost of BCT-1* » $19,500 $/lb =3.60 FAIL
~Includes the cost of all BAT components
BCT-2S lbs/year removed ¦ 6,160
Cost of BCT-2* - $32,500 $/lb ¦ 5.28 FAIL
~Includes the cost of all BAT components except
the sulfide precipitation.
B. Continuous Type
BCT-1: lbs/year removed » 126,460
Cost of BCT-1* - $ 91,100 $/lb - 0.72 PASS
~Includes the cost of all BAT components
BCT-2 lbs/year removed » 134,268
Cost of BCT-2* - $119,000 $/lb -0.88 PASS
~Includes the cost of all BAT components except
the sulfide precipitation.
402
-------
TABLE VII1-45
RESULTS OF BCT COST TEST
HYDROCHLORIC ACID PICKLING SUBCATEGORY
(Acid Regeneration System Continuous Pickling Lines Only)
A. Bat ch Type
BCT-1: lbs/year removed ¦ 173,819
Cost of BCT-1* - $105,400 $/lb -0.61 PASS
~Includes the cost of all BAT components
BCF-2 lbs/year removed » 183 , 707
Cost of BCT-2* - $140,600 $/lb -0.76 PASS
~Includes the cost of all BAT components except
the sulfide precipitation.
403
-------
TABLE VIII-46
RESULTS OF BCT COST TEST
SULFURIC ACID PICKLING SUBDIVISION
A. Batch Type
BCT-1: lbs/year removed = 8,804
Cost of BCT-1* - $21,400 $/lb « 2.43 FAIL
~Includes the cost of all BAT components
BCT-2: lbs/year removed * 9,714
Cost of BCT-2* - $38,900 $/lb - 4.00 FAIL
*Include8 the cost of all BAT components except
sulfide precipitation.
B. Conti nuous Type
BCT-1: lbs/year removed » 28,556
Cost of BCT-1* - $44,100 $/lb - 1.54 FAIL
*Include8 the cost of all BAT components.
BCT-2 lbs/year removed ¦ 37,630
Cost of BCT-2* - $79,000 $/lb - 2.10 FAIL
~Includes the cost of all BAT components except
sulfide precipitation.
404
-------
TABLE VIII-47
USPS MODEL COST DATA: BASIS 7/1/78 DOLLARS
Subcategory: Pickling-Sulfuric Acid Model Size-TPD : 500
: Batch Oper. Days/Year: 260
: Carbon & Specialty Turns/Day : 3
cvrr step
A
B
Total
Investment $ x 10 -
119
1457
1576
Annual Cose $ x 10
Capital
5.1
62.7
67.8
Depreciation
11 .9
145.7
157.6
Operation & Maintenance
4.2
51.0
55.2
Crystal Disposal
-
27.8
23.8
Energy & Power
-
48.5
48.5
TOTAL
21.2
331.7
352.9
Less Credit
Acid Recovery
-
19.3
19.3
NET ANNUAL COST
21.2
312.4
333.6
Raw Waste Levels
NSPS
Effluent Quality^
Cone
Rinse
FHS
Total'
Total
Effluent
Level
Flow, gal/ton
20
330
710
1060
70
0
Suspended Solids
870
420
70
195
2940
-
Oil & Grease
150
65
4.5
26
395
-
Dissolved Iron
56,000
54,000
130
2800
42,800
-
pK, Units
<1-2
1-&
1.4-1.9
<1-6
<1-6
-
115 Arsenic
0.20
0.40
-
0.40
2.5
-
118 Cadniun
0.80
0.80
-
0.80
4.0
-
119 Chromiisn
240
5.1
-
18.5
95
•
120 Copper
3.7
1.2
-
1.3
6.7
-
122 Lead
0.80
0.30
-
0.50
1.4
-
124 Nickel
25
2.0
-
3.3
17
-
128 Zinc
75
21
-
24
120
-
(1) Step A costs and loada attributable to apent concentrates only.
(2) All values are in ag/1 unless otherwise noted.
(3) Concentrationa and flow values represent cosiposite averages of concentrates, rinses, end FHS streams.
(4) Concentrations and Clow values represent composite averages of concentrates, rinses after cascade
rinse, and FHS blovdown streets.
KEY TO C4TT STEPS
A: Spent Acid Storage Systsn B: Acid Recovery System
405
-------
TABLE VIII-48
USPS MODEL COST DAIAi BASIS 7/1/78 DOLLARS
Subcategory:
Pickling-Sulfuric Acid
Continuous
Carbon & Specialty
Model Si»e-TPD
Oper. Daya/Year
Turns/Day
1980
260
3
C&TT step
A<»
B
Total
-3
Investment $ * 10 ,
264
4034
4298
Annual Cost $ x 10
Capital
11.3
173.5
184.8
Depreciation
26.4
403.4
429.8
Operation i Maintenance
9.2
141.2
150.4
Crystal Disposal
-
128.7
128.7
Energy & Power
-
123.8
123.8
TOTAL
46.9
970.6
1017.5
Less Credit
Acid Recovery
-
260.6
260.6
NET ANNUAL COST
46.9
710.0
756.9
Raw Waste Levels
NSPS
Effluent Quality'2'
Cone
Rinse
FHS
Total(3)
Total(4)
Ef£lu«ut
Ltvel
Flow, gal/ton
20
220
130
370
55
0
Suspended Solids
2600
120
70
236
1590
-
Oil & Greaae
18
12
4.5
10
65
-
Diseolved Iron
45,000
6100
130
6100
41,100
-
pH, Units
<1
2-6
1.4-1.9
<1-6
<1-6
-
US Arsenic
0.20
0.07
-
0.10
0.35
-
118 Cadmium
0.50
0.10
-
0.10
0.60
-
119 Chromium
30
0.70
-
3.1
14
-
120 Copper
3.0
0.90
-
l.l
4.7
-
122 Lead
1.6
0.35
-
0.45
2.0
-
124 Nickel
21
4.6
-
6.0
26
-
128 Zinc
3.0
0.65
-
0.85
3.7
-
CI) Step A costs and loads attributable to spent concentrates only.
(2) All values are in mg/1 unless otherwise noted.
(3) Concentrations and flow values represent composite averages of concentratea, rinses, and FHS strea
(4) Concentrations and flow values represent composite averages of concentrates, rinses after cascade
rinse, end FHS blovdown stream.
KEY TO CiTT STEPS
Ai Spent Acid Storage System B: Acid Recovery System
406
-------
TABLE VII1-49
MSPS, PSES AMD PSNS MODEL COST DATA: BASIS 7/1/78 DOLLARS
Subcategory: Hydrochloric Acid Pickling Model Site-TPD : 190
: Batch Neutralization Oper. Days/Year: 260
: Carbon and Specialty Turns/Day : 2
O
TOTAL
Alternative No. 1
Alternative No. 2
9.8
13.6
(2)
24.6
10.7
30.2
10.8 4.9
12.9 18.0
136.1
H(l)
ill!
Total
C6TT Steps
A
B
C
D
E
F
G
Total
Unci. A-J)
Investment $ x 10 ^
55
76
79
60
116
57
26
72
91
63 2
29
72
733
Annual Cost $ x 10
Capital
2.4
3.3
3.4
2.6
5.0
2.5
1.1
3.1
3.9
27.2
1.2
3.1
31.5
Depreciation
5.5
7.6
7.9
6.0
11.6
5.7
2.6
7.2
9.1
63.2
2.9
7.2
73.3
Operation and Maintenance
1.9
2.7
2.8
2.1
4.1
2.0
0.9
2.5
3.2
22.1
1.0
2.5
25.6
Sludge Disposal
-
(?\
-
-
-
-
-
-
1.7
1 7
-
-
17
Energy and Power
-
0.6
-
-
0.4
0.3
0.3
0.1
0.1
1.2
0.1
0.2
1.5
Cheaical Costs
-
-
-
-
9.1
0.3
-
-
-
10.2
0.2
-
L0.4
Replacement Parts
-
-
10.5
-
-
-
-
-
-
10.5
-
-
10.5
5.4 13.0 1154.5
-------
TABLE V1I1-49
NSPS, PSES AND PSNS MODEL COST DATA: BASIS 7/1/78 DOLLARS
hydrochloric acid pickling
PAGE 2
Effluent Quality
(3)
Cone
Raw Haste Level
Rinse FHS
Total
(4)
Total
(5)
Alt. Ho. 1
Effluent Level
PSES No. 1
Effluent Level
O
CD
Flow, gal/ton
10
540
150
700
90
90
90
Total Suspended Solids
450
90
370
155
1200
30
15
Oil & Grease
44
33
66
40
310
10
5.0
Dissolved Iron
57,000
2700
820
3100
24,000
1.0
1.0
pH (Units)
<1-5
1-5
<1-3.7
<1-5
<1-5
6-9
6-9
23
Chloroform
0.03
0.01
0.10
0.03
0.25
0.01
0.01
114
Antimony
2.2
0.01
0.40
0.10
1.0
0.10
0.10
115
Arsenic
0.20
0.09
0.05
0.10
0.65
0.10
0.10
118
Cadnium
0.20
0.04
0.06
0.10
0.35
0.10
0.10
119
Chromium
13
0.35
0.35
0.50
4.1
0.10
0.10
120
Copper
13
0.60
0.80
0.80
6.4
0.10
0.10
122
Lead
310
18
0.30
18.35
145
0.10
0.10
124
Nickel
10
0.50
0.55
0.60
5.0
0.20
0.10
126
Silver
0.20
0.06
0.10
0.10
0.55
0.10
0.10
128
Zinc
15
146
0.65
113
880
0.10
0.10
(1) Treatment components are used in tandem.
(2) Total cost does not include power, because a credit is applied for existing process water requirements.
(3) All values are in ng/1 unless otherwise noted.
(4) All values are once-through concentrations.
(5> Concentrations and flow values represent composite averages of concentrates, rinses after cascade
rinse, and FHS blowdown stream.
KEY TO C&TT STEPS
A: Spent Acid Equalization System
B: FHS Recycle
C: Cascade Rinse
D: Equalization
E: Lime Addition
F: Polymer Addition
G: Aeration
H: Clarifier
I: Vacuum Filter
J: Sulfide Precipitation
K: Filtration
-------
TABU VIII-50
USPS, PSES AHD P3NS MODEL COST DATA: BASIS 7/1/78 DOLLARS
Subcategory: Hydrochloric Acid Pickling Model Sise-TPD : 2760
: Continuous-Neutraliration Oper. Days/Tear: 312
t Carbon and Specialty Turns/Day : 3
Alternative No. l Alternative No. 2
C&TT Steps
A
B
C
D
E
F
<5
HW
I<3)
Total
k(3>
Total
(Incl. A-l)
_3
Investment $ * 10
154
191
394
349
86
47
81
204
258
1764
24
153
1941
Annual Coat $ x 10
Capital
6.6
8.2
16.9
15.0
3.7
2.0
3.5
8.8
11.1
75.8
1.0
6.6
83.4
Depreciation
15.4
19.1
39.4
34.9
8.6
4.7
8.1
20.4
25.8
176.4
2.4
15.3
194.1
Operation and Maintenance
5.4
6.7
13.8
12.2
3.0
1.6
2.8
7.1
9.0
61.6
0.8
5.4
67.8
Sludge Disposal ...
Energy and Power
-
" (2)
-
-
-
-
-
-
94.2
94.2
-
-
94.2
-
10.5* Z'
-
0.9
5.8
1.1
0.7
7.6
7.6
23.7
0.1
0.6
24.4
Qieaical Coat*
-
-
-
-
77.0
12.6
-
-
-
89.6
1.0
-
90.6
Replacement Part a
-
~ {2}
52.3
-
-
-
-
-
-
52.3
-
-
52.3
TOTAL
27.4
34.0
122.4
63.0
98.1
22.0
15.1
43.9
147.7
573.6
5.3
27.9
606.8
4*
O
U>
-------
TABLE VIII-50
NSPS, PSES AND PSNS MODEL QOST DATA: BASIS 7/1/78 DOLLARS
HYDROCHLORIC ACID PICKLING
PAGE 2
Raw Waste level
O
(4)
Effluent Quality
Cone
Rinse
FHSU)
Total
Total
Flow, gal/ton
10
300
180
490
55
Total Suspended Solids
450
90
370
200
1780
Oil & Grease
44
33
66
45
400
Dissolved Iron
57,000
2700
870
3100
28,000
pH, Units
<1-5
1-5
<1-3.7
<1-5
<1-5
23
Chi or of orm
0.03
0.01
0.10
0.04
0.40
114
Antimony
2.2
0.01
0.40
0.20
1.8
115
Arsenic
0.20
0.09
0.05
0.10
0.70
118
Cadmium
0.20
0.04
0.06
0.10
0.45
119
Chromium
13
0.35
0.35
0.60
5.4
120
Copper
13
0.60
0.80
1.0
8.3
122
Lead
310
18
0.30
17.5
155
124
Nickel
10
0.50
0.55
0.70
6.4
126
Silver
0.20
0.06
0.10
0.10
0.70
128
Zinc
15
146
0.65
90
800
Alt. Ho. 1
Effluent Level
55
30
10
1.0
6-9
0.01
0.10
0.10
0.10
0.10
0.10
0.10
0.20
0.10
0.10
(1) Treatment components are used in tandem.
(2) Total cost does not include power, because a credit is applied for existing process water needs.
(3) All values are in mg/1 unless otherwise noted.
(4) All values are once-through concentrations.
(5) Concentrations and flow values represent coaposite averages of concentrates, rinses after cascade
rinse, and fuse hood scrubber blow down stream.
Alt. No. 2
Effluent Level
55
15
5.0
1.0
6-9
0.01
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
1ST TO C6TT STEPS
A: Spent Acid Equalization System
B: FHS Recycle
C: Caacade Rinse
Dt Equalisation
E: Lime Addition
F: Polymer Addition
G: Aeration
H: Clarifier
I: Vacuum Filter
J: Sulfide Precipitation
Ks Filtration
-------
TABLE VIII-51
USPS, PSES AHD P3HS MODEL COST OAIA: BASIS 7/1/76 DOLLARS
Subcategory: Hydrochloric Acid Pickling Model Sire-TPD :
: Continuous-Acid Regeneration Oper. Days/Tear;
: Carbon and Specialty Turns/Day :
Alternative Not 1
Alternative No. 2
C4TT Step
A
B
C
D
E
r
G
H<1)
i—
Total
Investment $ * 10 'j
198
4814
191
406
77
46
94
237
300
6363
Annual Cost $ * 10
Capital
8.5
207.0
8.2
17.5
3.3
2.0
4.0
10.2
12.9
273.6
Depreciation
19.8
481.4
19.1
40.6
7.7
4.6
9.4
23.7
30.0
636.3
Operation and Maintenance
6.9
168.5
6.7
14.2
2.7
1.6
3.3
8.3
10.5
227.7
Sludge Disposal ...
Energy and Power
-
-
" M)
-
-
-
-
-
109.5
109.5
-
307.3
10.5"'
1.0
5.5
1.0
0.9
8.8
8.9
333.4
Cbeaical Costs
-
-
-
-
72.0
12.0
-
-
-
84.0
Replacement Parts
-
52.3
-
-
-
-
-
-
-
52.3
TOTAL
35.2
1216.5
34.0<2)
73.3
91.2
21.2
17.6
51.0
171.8
1716.8
Less Credits
Acid Recovery
2304.6
2304.6
Iron Oxide Recovery
1543.6
73.3
91.2
21.2
17.6
51.0
171.8
1543.6
Met Annual Cost
35.2
-2631.7
34.0
-2131.4
(l) ^U)
192
J
31
1.3
3.1
1.1
0.2
1.5
7.2
8.3
19.2
6.7
1.0
Total
(Incl. A-I)
6586
283.2
658.6
230.5
109.5
334.6
85.5
52.3
7.2 35.2 1754.2
2304.6
35.2 1543.6
-2094.0
-------
TABLE VIII-51
USPS, PSES AMD PSNS MODEL COST DATA: BASIS 7/1/78 DOLLARS
HYDROCHLORIC ACID PICKLING
PAGE 2
Waste Level
... Alt. No. 1 Alt. »o. 2
Effluent Quality
Cone
Rinse
FHS
AVS
Total -
Total
Effluent Level
Effluent Level
Flow, gal/ton
10
300
180
120
610
70
70
70
Total Suspended Solids
450
90
370
90
180
1560
30
15
Oil & Grease
44
33
66
2
37
320
10
5.0
Dissolved Iron
57,000
2700
820
650
2630
23,000
1.0
1.0
pH (Units)
<1-5
1-5
<1-3.7
<1-7.6
<1-7.6
<1-7.6
6-9
6-9
23
Chi orof on
0.03
0.01
0.10
0.02
0.04
0.35
0.01
0.01
114
Antiaony
2.2
0.01
0.40
0.20
0.20
1.7
0.10
0.10
115
Arsenic
0.20
0.09
0.05
0.02
0.10
0.60
0.10
0.10
118
CaAaiun
0.20
0.04
0.06
-
0.10
0.35
0.10
0.10
119
Chroai.ua
13
0.35
0. 35
0.02
0.50
4.3
0.10
0.10
120
Copper
13
0.60
0.80
0.80
0.90
7.9
0.10
0.10
122
Lead
310
18
0.30
1.0
14
125
0.10
0.10
1Z4
Nickel
10
0.50
0.55
0.35
0.65
5.6
0.20
0.10
126
Silver
0.20
0.06
0.10
0.10
0.10
0.70
0.10
0.10
128
Zinc
15
146
0.65
1.0
73
630
0.10
0.10
(1) Treat*ent coaponents are used in tandem.
(2) Total coat does not include power, because a credit is applied for existing process water needs.
(3) All values are in ag/1 unless otherwise noted.
(4) All values are once-through concentrations.
(5) Concentrations and flow values represent composite averages of concentrates, rinses after cascade
rinse, and f we hood scrubber blow down streams.
KEY TO C6TT STEPS
A:
Spent Acid Equalisation Systea
F:
Polyaer Addition
B:
Acid Regeneration Systea
G:
Aeration
C:
FHS Recycle, Cascade Rinse
H:
Clarifier
D:
Equalisation
I:
Vacuus Filter
E:
Liae Addition
J:
Sulfide Precipitation
Ks
Filtration
-------
TABLE VIII-52
USPS Ir fSH3 Maoa. CQST DAIAiBASIS 7/1/78 DOLLARS
Subcategory: Combination Acid Pickling Model Sise-TPD : 200
: Batch Oper. Days/Tear: 260
: Carbon-Specialty Turns/Day : 2
Alternative Ho. 1 Alternative Ho. 2
CSTT Steps
A
B
C-
D
E
•J?
Total
H
I
Total (Includes A-G)
Invests ant $ x 10
63
82
41
79
39
49
62
415
34
84
533
Annual Coat $ x 10
Capital
2.7
3.5
1.8
3.4
1.7
2.1
2.7
17.8
1.5
3.6
22.9
Depreciation
6.3
8.2
4.1
7.9
3.9
4.9
6.2
41.5
3.4
8.4
53.3
Operation and Maintenance
2.2
2.9
1.4
2.8
1.4
1.7
2.2
14.5
1.2
2.9
18.7
Sludge Disposal ...
Energy and Power
~ (2)
-
-
-
-
-
1.2
1.2
-
-
1.2
0. 7
-
-
0.3
0.2
0.1
0.1
0.7
0.1
0.1
0.9
Chenical Costs
-
-
-
6.2
0.2
-
-
6.4
0.1
-
6.5
Kepiacenent Parts
-
10.8
-
-
-
-
-
10.8
-
-
10.8
TOTAL
11.2(2)
25.4
7.3
20.6
7.4
8.8
12.4
92.9
6.3
15.0
114.3
-------
TABUS VIII-52
USPS 4 PSNS MODEL COST DATA: BASIS 7/1/78 DOLLARS
ODMBIMATIOH ACID PICKLING
PAGE 2
Raw Haste Level
4*
Effluent Quality**-
Cone
Rinse
FHS(*>
Flow, gal/ton
15
200
1140
Suspended Solids
130
50
25
Oil ( Grease
0.40
4.6
0.30
Dissolved Iron
19,000
230
50
Fluoride
3900
430
1800
pH, Units
<1-2.3
2-4
1.5-2.0
115 Arsenic
-
0.10
-
119 Chroaitas
4300
48
2.4
120 Copper
230
1.3
-
122 Lead
2.7
0.07
-
124 Nickel
5800
53
3.3
128 Zinc
1.7
1.0
0.30
Total(5) Total(6>
1355
30
1.0
290
1620
<1—4
0.10
55
17
0.25
75
0.60
45
900
28
8620
48,800
<1-4
0.10
1700
82
1.2
2250
18
Alt. Ho. 1
Effluent Level
45
30
10
1.0
15
6-9
0.10
0.10
0.10
0.10
0.20
0.10
(1) Treatment components are used in tandesu
(2) Total cost does not include power, because a credit is applied for existing process water needs.
(3) All values are in «g/l unless otherwise noted.
(4) All values are once-through concentrations.
(5) All values are once-through concentrations.
(6) Concentrations and flow values represent concentrates, rinses after cascade
rinse, and foe hood acrubber blow down streaas.
Alt. No. 2
Effluent Level
45
15
5.0
1.0
45
6-9
0.10
0.10
0.10
0.10
0.10
0.10
KEY TO C4TT STEPS
A: FIB Recycle
Bt Cascade Rinse
C: Equalization Tank
Ds lis* Addi ti on
E: Polyner Addition
F: Clarifier
G: Vacuus Filter
H: Sulfide Precipitation
I: Filtration
-------
TABLE VIII-53
NSPSVPSNS MODEL COST DATA: BASIS 7/1/78 DOLLARS
CATT Steps
Investment $ x
Annual Cost $ x
10
10
3
-3
Replacement Parts
TOTAL
Subcategory
Combination Acid Pickling
Continuous
Carbon-Specialty
Model Siee-TPD : 500
Oper. Days/Year: 320
Turns/Day : ?
Alternative No. 1
Alternative No. 2
A
59
B
142
C
96
D
102
E
52
F_
84
(3)
G_
81
(3)
Total
616
H
34
I
107
18.8
10.5(2) 44.1
17.1
26.9
10.7
18.8
15.2 16.3 140.9 6.6
19.3
Total (Includes A-G)
757
Capital
2.5
6.1
4.1
4.4
2.2
3.6
3.5
26.5
1.5
4.6
32.6
Depreciation
5.9
14.2
9.6
10.2
5.2
8.4
8.1
61.6
3.4
10.7
75.7
Operation and Maintenance
2.1
5.0
3.4
3.6
1.8
2.9
2.8
21.6
1.2
3.7
26.5
Sludge Disposal ...
Energy and Power
l.I(2)
-
-
-
-
-
1.3
1.3
-
1.3
-
-
0.5
0.3
0.3
0.6
1.7
0.2
0.3
2.2
Cheaical Costs
-
-
-
8.2
1.2
-
-
9.4
0.3
-
9.7
18.8
166.8
-------
TABLE VtlI-53
USPS 4 PSNS HODKL COST DATA: BASIS 7/1/78 DOLLAKS
OOMBIMXIOR ACID PICKLIHG
PAGE 2
Raw Waste Level*
Alt. Ho. 1 Alt. Mo. 2
Effluent Quality^ Cone Rimt FHS^^ Total^ Total^Effluent Level Effluent Level
Flow, gal/ton 15 500 720 1235 90 90 90
Suspended Solids 200 180 25 90 1230 30 15
Oil & Grease 3.5 3.3 0.30 1.6 21 10 5.0
Dissolved Iron 23,000 155 2.4 345 4700 1.0 1.0
Fluoride 10,000 69 50 180 2450 15 15
pH (Onits) 1.5 2.5-8 1.5-2.0 1.5-8 1.5-8 6-9 6-9
4 Benzene - 0.05 ** 0.05 0.05 0.05 0.025
115 Arsenic - 0.01 - 0.01 0.01 0.01 0.01
119 Chroaiua 3300 25 8.3 55 755 0.10 0.10
120 Copper 100 0.27 0.07 1.4 19 0.10 0.10
122 Lead 1.2 - - 1.2 1.2 0.10 0.10
124 Bickel 3300 15 1800 1100 15,000 0.20 0.10
128 Zinc 4.1 0.40 0.30 0.40 5.3 0.10 0.10
** Value is less than 0.010 ag/1.
(1) Costs are all power unless otherwise noted.
(2) Total does not include power, because a credit is supplied for existing process water requirements.
(3) Treatment components are used in tandes.
(4) All values are are in ag/1 unless otherwise noted.
(5) All values are once-through concentrations.
(6) Concentrations and flow values represent composite averages of concentrates, rinses after cascade
rinse, and fuse hood scrubber blow down strew.
KEY TO C6TT STEPS
A: FBS Recycle
Bt Cascade Rinse
Cl Equalisation Tank
D: Liae Addition
E: Polyaer Addition
F: Clarifier
G: Vacuus Filter
H: Sulfide Precipitation
I: Filter
-------
TABLE VIII-54
tSBS MODEL COST DATA; BASIS 7/t/7B DOLLARS
Subcategory:
Pickling-Sulfuric Acid
Batch
Neutralization
Model Size-TPD :
Oper. Days/Year:
Turns/Day :
500
m
Alternative No. 1
Alternative Ho. 2
CSTT Steps
A
B
C
D
E
r
<£1
Total
11
Total
(Incl. A-B)
Investment $ x 10 '-
119
128
114
41
36
74
90
60
662
34
118
814
Annual Cost 9 x 10
Capi tal
5.1
5.5
4.9
1.8
1.5
3.2
3.9
2.6
28.5
1.5
5.1
35.0
Depreciation
11.9
12.8
11.4
4.1
3.6
7.4
9.0
6.0
66.2
3.4
11.8
81.4
Operation and Maintenance
4.2
4.5
4.0
1.4
1.3
2.6
3.2
2.1
23.2
1.2
4.1
28.5
Sludge Disposal , .
Energy and Power
-
"(7>
-
-
-
-
-
4.1
4.1
-
-
4.1
-
0.9 '
-
0.2
0.4
0.2
0.2
1.1
2.1
0.2
1.8
4.1
Cheaical Costs
-
1.2
-
-
16.2
2.6
-
-
20.0
0.7
-
20.7
Replaceaeot Parts
-
-
15.2
-
-
-
-
-
15.2
-
-
15.2
TOTAL
21.2
24.0(2)
35.5
7.5
23.0
16.0
16.3
15.9
159.3
7.0
22.8
189.0
-------
TABLE VIII-54
PSES MODEL COST DATA: BASIS 7/1/78 DOLLARS
PICKLING-SULFORIC ACID
PAGE 2
Raw Waste Level
Effluent Quality*
Cone
Rinse
FHS
Total
Total(
Flow, gal/ton
20
330
710
1060
70
Suspended Solids
870
420
70
195
2940
Oil & Grease
150
65
4.5
26
400
Dissolved Iron
56,000
5400
130
2800
42,800
pH, Units
<1
1-6
1.4-1.9
<1-6
1-6
115
Arsenic
0.20
0.40
-
0.40
1.9
118
Cadaiua
0.80
0.80
-
0.80
4.0
119
Chromium
240
5.1
-
18.5
93
120
Copper
3.7
1.2
-
1.3
6.7
122
Lead
0.80
0.30
-
0. 50
1.6
124
Nickel
25
2.0
-
3.3
16.5
128
Zinc
75
21
-
24
120
PSES No. 1
Effluent Level
70
30
10
1.0
6-9
0.10
0.10
0.10
0.10
0.10
0.20
0.10
PSES No. 2
Effluent Level
70
15
5.0
1.0
6-9
0.10
0.10
0.10
0.10
0.10
0.10
0.10
(1) Treatment components are used in tandem.
CO (2) Total cost does not include power, because a credit is supplied for existing process water needs.
(3) All values are in mg/1 unless otherwise noted.
(4) All values are once-through concentrations.
(5) Concentrations and flow values represent concentrates, rinses after cascade
rinse, and fuse hood scrubber blcwdovn streams.
KE* TO C&TT STEPS
A: Spent Acid Equalization Systc
B: FHS Recycle
C: Cascade Rinse
D: Equalization
E: Line Addition
F: Polymer Addition, Aeration
G: Clarifier
H: Vacuum Pilter
I: Sulfide Precipitation
J: Filter
-------
TABLE VIII-55
PSES MODEL COST DATA: BASIS 7/1/78 DOLLARS
yo
Subcategory: Pickling-Sulfuric Acid
: Continuous
: Neutralization
: Carbon & Speciality
Model Size-TPD :
Oper. Days/Year:
Turns/Day s
C4TT Stepa
Iineilaeat $ i 10 ^
Annual Cost $ * 10
Capital
Depreciation
Operation and Maintenance
Sludge Disposal
Energy and Power1
Cheaical Coats
Replacement Parts
TOTAL
.(1)
Alternative Ho. 1
A
264
11.3
26.4
9.2
B
171
7.3
17.1
6.0
2.4
2.0
(2)
46.9 32.4
(2)
C
323
13.9
32.3
11.3
42.8
100.3
D
287
12.3
28.7
10.0
0.3
E
68
2.9
6.8
2.4
1.6
104.4
P
105
4.5
10.5
3.7
0.4
10.4
51.3 118.1
(1)
C
167
7.2
16.7
5.8
1.0
29.5 30.7
213
9.2
21.3
7.5
15.3
5.1
58.4
1980
—J
Total
1598
68.6
159.8
55.9
15.3
8.4
116.8
42.8
I
64
(1)
2.8
6.4
2.2
0.3
1.4
467.6 13.1
Alternative
j(P
157
6.7
15.7
5.5
2.2
30.1
Ho. 2
Total
(Incl. A-H)
1819
78.1
181.9
63.6
15.3
10.9
118.2
42.8
510.8
-------
TABU VIII-55
PS8S MODEL COST MTA: KASIS 7/1/78 DOLLARS
flCKLIKC-SOLFOSIC ACID
PAGE 2
Itr Vntc Level
Effluent Quality'3'
Cone
time
res
Total
Flow, gal/too
20
220
130
370
Suspended Solids
2600
120
70
236
Oil 4 Grease
18
12
4.5
10
Diaaolved Iron
45,000
6100
130
6100
pH, Unit*
<1
2-6
1.4-1.7
<1-6
US
Araenic
0.20
0.07
-
0.10
118
Cadaiua
0.50
0.10
-
0.10
119
Chroaiw
30
0.70
-
3.1
120
Copper
3.0
0.90
-
1.1
122
Lead
1.6
0.35
-
0.45
124
Rickel
21
4.6
-
6.0
128
Zinc
3.0
0.65
-
0.85
/C\
FSES Mo. 1
FSES Ho. 2
Total '
Effluent Level
Effluent Level
55
55
55
1590
30
15
65
10
5.0
41,000
1.0
1.0
<1-6
6-3
6-9
0.35
0.10
0.10
0.60
0.10
0.10
14
0.10
0.10
4.7
0.10
0.10
2.0
0.10
0.10
26
0.20
0.10
3.7
0.10
0.10
O
(1) Treataent coaponenta are used in tandea.
(2) Total coat does not include power, becauae a credit ia supplied for exiating process water needs.
(3) All value* are in ag/1 unless otherwise noted.
(4) All value* are once-through concentration*.
(5) Concentration* and flow value* represent concentrate*, rinses after cascade
rinse, and fuse hood scrubber blowdovn itreaa*.
EET TO CMT STEPS
Ai Spent Acid Equalisation Syatea
Bi ns ftecycle
Ci Caacade Kinae
D: Bqual isation
Et Liae Addition
F: Foljnaer Addition, Aeration
G: Clarifier
Bt Vacuus Filter
It Sulfide Precipitation
Jt Filter
-------
TABLE VIII-56
PSES HP DEL POST DATA: BASIS 7/1/76 DOLLARS
Subcategory: Combination Acid Pickling Model Size-TPD : 200
: Batch Oper. Days/Year: 260
: Carbon and Specialty Turns/Day : 2
Alternative Ho. 1 2-Steps A to E of Alt. 1 plus:
C4TT Step*
A
B
C
D
E
£1
Total
H
Total
_3
Investment $ x 10 ^
63
69
68
85
39
69
79
472
23
25
97
469
Annual Coat $ s 10
Capital
2.7
3.0
2.9
3.7
1.7
3.0
3.4
20.3
1.0
1.1
4.2
20.2
Depreciation
6.3
6.9
6.8
8.5
3.9
6.9
7.9
47.2
2.3
2.5
9.7
46.9
Operation and Maintenance
2.2
2.4
2.4
3.0
1.4
2.4
2.8
16.5
0.8
0.9
3.4
16.4
Sludge Disposal ,
Energy and Power
-
-
-
-
-
1.7
1.7
1.7
-
-
1.7
0. 7
-
0.2
0.3
0.1
0.2
0.3
1.8
-
0.1
0.2
1.6
Cheaical Coats
-
-
-
6.1
0.5
-
-
6.6
-
0.1
-
6.6
Keplaeeaent Parts
-
9.1
-
-
-
-
-
9.1
-
-
-
9.1
TOTAL
11.2<2>
21.4
12.3
21.6
7.6
12.5
16.1
103.2
4.1
4.7
17.5
102.5
-------
TABU VIII-56
PSES MODEL COST DATA: BASIS 7/1/78 DOLLARS
OOHBIKATIOH ACID PICKLIHG
PAGE 2 - ¦¦
lw Waste Level
Effluent Quality*3*
Cone
Rinae
FHS
Total
Total((
Flow, gal/ton
15
520
1140
1675
105
Total Suspended Solida
130
50
25
34
540
Oil 6 Greaae
0.40
4.6
0.30
1.6
26
Dissolved Iron
19,000
230
50
275
4400
Fluoride
3900
430
1800
1400
22,200
pH (Units)
<1-2.3
2-4
1.5-2.0
<1-4
<1-4
115 Arsenic
-
0.10
-
0.10
0.10
119 Chroaiia
4300
48
2.4
55
880
120 Copper
230
1.3
-
7.7
39
122 Lead
2.7
0.07
-
0.10
0.75
124 Rickel
5800
53
3.3
71
1130
128 Zinc
17
1.0
0.30
0.70
U
PSES Ho. 1
Effluent Level
105
30
10
1.0
15
6-9
0.10
0.10
0.10
0.10
0.20
0.10
PSES No. 2
Effluent Level
105
15
5.0
1.0
15
6-9
0.10
0.10
0.10
0.10
0.10
0.10
'
to
10 (1) All coats are power unleaa otherwise noted.
(2) Total coat doea not include power, becauae a credit ia applied for exiating proceaa water requirenenta.
(3) Treatment components are used in tandea.
(4) All valuea are in ag/1 unlea a otherwiae noted.
(5) Valuea are ooce-through concentrations.
(6) Concentration and flow values represent composite averages of concentrate, rinse after cascade rinse,
and fuse hood acrubber blowdown atreaaa.
KET T0C4TT STEPS
At
FHS Recycle
Ft
Clarifier
Bl
C as cade Rime
Cs
Vacuua Filter
CI
Equalisation
H:
Settling Baain
Dt
Liae Addition
It
Sulfide Precipitation
Ei
Polyaer Addition
J:
Fil ter
-------
TABLE VII1-5 7
PSES MODEL COST DATA; BASIS 7/1/78 DOLLARS
Subcategory: Combination Acid Pickling Model Sire-TPD : 506
: Continuous Oper. Days/Tear: 320
: Carbon and Specialty Turns/Day : 3
N)
OJ
C&TT Steps
_3
Investment $ x 10
Annual Coat $ * 10
Capi tal
Depreciation
Operation and Maintenance
Sludge Disposal
Energy and Powerx
Cheaical Coata
Replacement Parta
TOTAL
.CD
Alternative Ho.
1
2-Steps A to E
of Ait. :
I plus:
A
B
C
D
E
f(3)
Total
H
l(3)
j(3)
Total
69
142
225
160
SB
135
203
982
105
41
191
981
2.5
6.1
9.7
6.9
2.5
5.8
8.7
42.2
4.5
1.8
8.2
42.2
5.9
14.2
22.5
16.0
5.8
13.5
20.3
98.2
10.5
4.1
19.1
98.1
2.1
5.0
7.9
5.6
2.0
4.7
7.1
34.4 ,
3.7
1.4
6.7
34.4
-
-
-
-
-
-
4.4
4.4
-
-
-
-
1.4(2)
-
0.3
1.0
0.7
0.4
4.2
6.6
-
0.2
0.9
3.1
-
-
-
27.2
4.1
-
-
31.3
-
0.9
-
32.2
-
18.8
-
-
-
-
-
18.8
-
-
-
18.8
10.5(2)
44.1
40.4
56.7
15.1
24.4
44.7
235.9
18.7
8.4
34.9
228.8
-------
TABLE VIII-57
PSES MODEL 00ST DATA: BASIS 7/1/78 DOLLARS
OOMBItUXlOH ACID PICKLING
PAGE 2
Raw Waste Level
Effluent Quality*4'
Cone
Rinse
fhs(4)
Total(5)
Flow, gal/ton
15
1800
720
2535
Total Suspended Solids
200
180
25
135
Oil & Grease
3.5
3.3
0.30
2.4
Dissolved Iron
23,000
155
2.4
250
Fluoride
10,000
69
50
122
pH, Units
1-5
2.5-8
1.5-2.0
1.5-8
004 Benzene
-
0.05
**
0.05
115 Arsenic
-
0.01
-
0.01
119 Chroaiua
3300
25
8.3
40
120 Copper
100
0.27
0.07
0.80
122 Lead
1.2
-
-
1.2
124 Nickel
3300
15
1800
540
128 Zinc
4.1
0.40
0.30
0.40
PSES No. 1 PSES No. 2
Total Effluent Level Effluent Level
335
335
335
1030
30
15
18.5
10
5.0
1870
1.0
1.0
930
15
15
1.5-8
6-9
6-9
0.05
0.05
0.025
0.01
0.01
0.01
300
0.10
0.10
6.1
0.10
0.10
1.2
0.10
0.10
4100
0.20
0.10
3.0
0.10
0.10
(1) Costs are all power unless otherwise noted.
(2) Total coat doe* not include power, because a credit ia applied for existing process water needs.
(3) Treataent components are used in tandaa.
(4) All values are in ag/1 unless otherwise noted.
(5) All values are once-through concentrations.
(6) Concentrations and flow values represent coaposite averages of concentrates, rinses after cascade
rinse, and fiae hood scrubber blowdown streaas.
KEY TO CSTT STEPS
A: FHS Recycle F:
B: Cascade Rinse G:
Ci Equalisation H:
D: Liae Addition I:
El Poljraer Addition J:
Clarifier
Vacuua Filter
Settling Basin
Sulfide Precipitation
Filter
-------
TABLE VIII-58
BPT INVESTMENT AND ANNUAL COSTS FOR THE
ACID PICKLING SUBCATEGORY
Subdivision
Sulfuric
Segment
Batch Neutralization
Batch Acid Recovery
Continuous Neutralization
Continuous Acid Recovery
24.18
3.82
17.97
2.34
48.31
BPT Costs ($ x 10"6)
Investment
In Place Required Total
10.55
60.97
10.85
6.96
89.33
34.73
64.79
28.82
9.30
137.64
Total
Annual
10.32
17.63
7.56
12.70
48.21
Hydrochloric
Batch Neutralization*
Continuous Neutralization
Continuous Acid Regeneration*
1.29
36.38
18.72
63.47
3.48
25.98
29.80
60.94
4.77
62.31
48.52
124.41
1.75
25.11
-19.80
7.06
Combination
Batch
Continuous
10.10
16.59
26.69
11.48
8.73
20.21
21.58
25.32
46.90
7.00
5.89
12.89
Total of Subcategory
138.47
170.48
308.95
68.16
* : The costs of confidential plants are not included in the investment cost totals for this
segment.
Note: All investment cost totals presented in this table include the costs of confidential
plants unless otherwise noted.
425
-------
TABLE VIII-59
BAT INVESTMENT AND ANNUAL COSTS FOR THE
ACID PICKLING SUBCATEGORY
BAT Cos ts ($ x 10
Total Investment
Subdivision 5tg»tiit
Sulfuric
Hydrochloric
Combination
BAT^I BAFI BAT1?
BAT-1
Total Annual
BAT-2
ife.
to
BAT-3
Batch Neutralization
6.73
15.69
84. 72
2.09
3.84
17.50
Continuous Neutralization
6.14
10.34
52.29
1.91
2.73
11.31
17787
ism
137.61
4. 00
6.51
28.81
Batch Neutralization
0.44
1.15
9.89
0.14
0.27
1.90
Continuous Neutralization
9.08
14.57
72.20
2.82
3.85
17.89
Continuous Acid Neutralization
3.05
5.06
25.89
0.95
1.33
6. 74
12.57
20.78
107.56
TT5T
TT5F
26.53
Batch
3.45
9.55
77.95
1.07
2.18
15.02
Continuous
2.70
7^11
50.41
0.84
1.66
11.65
6.15
16.66
128.36
rrsr
"JT85"
26.67
Total of Subcategory
31.59
63.47
373.35
9.82
15.86
82.01
Hotel Sulfuric acid recovery operations achieve zero discharge at BPT, therefore no additional
cost* are incurred at BAT.
-------
TABLE VIII-60
g«R0Y mqPIREHBWTS IK THE ACID PICKLIH6 3UBCATBC0RT
Subdj-riai oo Seynit
Sulfuric
A
KJ
vj
Hydrochloric
Combination
Batch neutralisation
Batch Acid Recovery
Continuous Neutralization
Continuous Acid Recovery
Batch Neutralization '
Continuous neutralisation
Continuous Acid Regeneration
Batch
Continuous
TPT
16.99
117.65
14.97
84; 34
233.95
2.44
46.25
129^56
178.25
4.60
-6i08
-nrw
Subcategory Basis
BAT-1
6AT-2 BAT-3
Energy Requirements (kw-hr/year) x 10
Treatment Model Basis
4.72
1.90
6.62
0.08
0.87
0.43
T73JS
0.60
0.84
T7W
56.64
44.46
101.10
3.39
153.26
68;87
775751
27.60
92i95
150.55
ET
0.02
0.04
H5PS-1
MSPS-2 PSES-i PSES-2 PSNS-i
1.94
4.95
0.05
0.95
13.34
0.03
0iO7
(1)
(2)
R/A
N/A
0.06
0.98
13.38
0.04
0i«9
0.08
0.43
0.05
0.95
13.34
0.16
0.53
0.06
0.98
13.38
0.06
0.12
1.94
4.95
0.05
0.95
13.34
0.03
0i07
(1)
(2)
PSH5-1
H/A
N/A
0.06
0.98
13.38
0.04
0.09
Total Cor Subcategory
422.88
9.44
447.17
1 J The energy requiresents listed refers to all batch sulfuric operations.
2 < The energy requirements listed refers to all continuous sulfuric operations.
¦/At Hot applicable.
Bote: .BAT and BCT energy rcqnirenentf listed represent those energy units required in addition to BPT.
-------
TABLE VIII-61
SOLID HASTE GENERATION SUMMARY(1)
ACID PICKLING SUBCATEGORY
Subdivision lb«/ ton^ lbs/day^
Sulfuric Acid
Batch Acid ftecovary
BPT 4 9..54 24,770
Batch Neutralisation
BPT 40.02 20,010
BAT 1* 0.206 103.2
BAT 2* 0.220 109.9
BAT 3 * 0.234 116.8
Continuous Acid Raeovary
BPT 36.611 72,490
Continuous Neutralisation
BPT 29.252 5 7 , 919
BAT 1* 0.141 278.9
BAT 2* 0.151 299.5
BAX 3* 0.162 321.2
Hydrochloric Acid
Batch Neutralisation
BPT 28.196 5 35 .7
BAT 1* 0.330 62.62
BAT 2* 0.347 65.87
BAT 3* 0.365 69.30
Continuous Neutralisation
BPT 20.245 55,875
BAT 1* 0.187 51 5 .9
BAT 2* 0.197 544.8
BAX 3* 0.208 575.2
Continuous Acid Rscovmry
BPT 12.357 34,106
BAT 1* 0.253 697.5
BAT 2 * 0.266 734.2
BAT 3 * 0.280 773.0
428
-------
TABLE VIII-61 m
SOLID HASTE GENERATION SUMMARY
ACID PICKLING SUBCATEGORY
PAGE 2
Subdivision lbe/ton^ lb*/day^
Cq»binatiot> Acid
Batch
BPT 7.419 1,484
BAT 1* 0.147 29.33
BAT 2* 0.160 31.99
BAT 3 * 0.182 36.33
Continuou*
BPT 8.671 4335
BAT 1* 0.510 255.0
BAT 2 * 0.552 276.2
BAT 3* 0.622 310.8
(1) Include* tolidi and octal calculated on a dry baaia.
(2) Pound* of *olid watt* par ton of production baaad on traataant modal.
(3) Pound* of solid vaatt par day baaad on traataant nodal,
*i Load* ovar and above BPT level*.
429
-------
ACID PICKLING SUBCATEGORY
SECTION IX
EFFLUENT QUALITY ATTAINABLE THROUGH
THE APPLICATION OF THE BEST PRACTICABLE
CONTROL TECHNOLOGY CURRENTLY AVAILABLE
Introduction
The Agency is proposing BPT limitations which are the same as those
originally promulgated in 1976. Additional limitations are being
proposed in the sulfuric acid subdivision for batch neutralization
operations. The 1976 regulation limited all batch sulfuric operations
at zero discharge. However, reanalysis of the data for this segment
indicates batch neutralization and batch acid recovery operations
should be limited separately. A review of the treatment processes and
effluent limitations associated with the acid pickling subcategory
follows.
Identification of BPT
The BPT model treatment systems described in this section are
identical to the systems used to develop the originally promulgated
BPT limitations. There are three basic modes of treatment in use in
the acid pickling subcategory. A description of each treatment mode
follows.
1. Neutralization
Neutralization of acid pickling wastewaters is currently carried
out for sulfuric, hydrochloric, and combination acid pickling
operations. The basic treatment system combines spent pickle
liquor (which has been equalized), rinsewater, and fume scrubber
blowdown in a second equalization basin. An oil separator is
included in the combination acid pickling model. Lime and
polymer are then added to the wastewaters in a mixing tank. The
lime neutralizes the acidic waste, while the polymer serves as a
flocculant. In the sulfuric and hydrochloric acid pickling BPT
model treatment systems, aeration is also provided at this point.
The pollutants which have been separated out must be removed.
The sulfuric acid pickling model includes a settling basin to
accomplish this. Separation is achieved with a thickener and
vacuum filter in the hydrochloric acid pickling subdivision,
while a clarifier and a vacuum filter are used in the combination
acid pickling subdivision. The filtrates from the vacuum filters
are returned to the respective thickener and clarifier inlets.
2. Acid Recovery
Acid recovery is practiced in the sulfuric acid pickling
subdivision. A spent acid storage system and the acid recovery
system, including storage for the recovered acid and by-product,
431
-------
are the only components necessary for acid recovery. This method
crystallizes the iron salts out of the pickling wastewater. The
sulfuric acid which remains is then strengthened to its original
concentration, so that it may be reused. This treatment model
achieves zero discharge.
3. Acid Regeneration
Acid regeneration is practiced in the hydrochloric acid pickling
subdivision as an alternative to neutralizing the spent pickle
liquor. In this method, the spent pickle liquor is regenerated.
Ferrous chloride is hydrolyzed to an iron oxide by-product and
HC1 gas. The gas is then absorbed to reform hydrochloric acid.
This process can generate absorber vent scrubber wastewater,
which is combined with the rinsewater and fume scrubber blowdown.
The three sources of wastewater are then neutralized as described
previously.
The BPT model treatment systems described above are illustrated
in Figures IX-1 through IX-5. As noted in Section VII, each
component included in the model treatment systems is in use at a
number of acid pickling operations.
The proposed BPT limitations do not require the use of the model
treatment systems presented in this section. Any systems which
achieve the limitations are acceptable. The proposed BPT
effluent limitations, which represent 30-day average values are
presented in Table IX-1. The proposed maximum daily effluent
limitations are three times the average values.
Justification of BPT
Tables IX-2 through IX-4 present the justification of the BPT effluent
limitations originally promulgated in March 1976. All of these
limitations are being reproposed. In addition, new limitations are
proposed in the sulfuric acid subdivision for batch neutralization
operations. The 1976 BPT limitation for all batch sulfuric operations
was zero discharge. However, only acid recovery operations achieve
zero discharge. Therefore, a neutralization model treatment system
was developed reflecting treatment components, flows, and pollutant
concentrations of those sulfuric batch neutralization plants currently
in operation. Refer to Tables X-l and X-2 for the derivations of the
flow values used to specify the sulfuric acid batch neutralization
model.
Tables IX-2 through IX-4 present sampled plant effluent data which
support the proposed BPT limitations. All of the plants listed
achieve one or more of the effluent limitations, except for Plant
AA-2, in the hydrochloric subdivision. No specific chemical treatment
is practiced at this plant, because all effluents are disposed of by
deep well injection. Data from the other sampled plants demonstrate
that the proposed BPT effluent limitations are achievable.
432
-------
Total Metals
In the combination acid pickling subdivision, limitations for chromium
and nickel were promulgated on a dissolved basis in 1976. The Agency
is presently proposing limitations for these toxic metal pollutants on
a total metal basis. The total metal more accurately reflects the
true pollutant load characteristics of this waste source. In
addition, total chromium and total nickel are included in the toxic
pollutant list. No change in the limitations for these.metals is
being proposed, since the proposed limitations for the total metals
are justified in this subcategory. Fluoride is also limited at BPT in
the combination acid pickling subdivision. However, these limitations
only apply when hydrofluoric acid is used in the pickling process.
433
-------
TABLE IX-1
BPT EPFLOENT LIMITATIONS - ACID PICKLING SUBCATEGORY
Operation
SULFURIC ACID
Batch Neutralizacion
Batch Acid Recovery
Continuous Neutralization
(with spent pickle liquor)
Continuous Neutralization
(without spent pickle liquor)
Continuous Acid Recovery
Discherge
Flow
Basis (GPT)
360
250
225
OU anf j
TSS Grease
Dissolved
Iron
Chromitxn
Fluoride'2' Nickel
0.0751 0.0150 0.00150
No discharge of process wastewater pollutants
0.0521
0.0104
0.00104
0.0469 0.00938 0.000938
No discharge of process wastewater pollutants
BYDROCH.ORIC ACID
Batch Neutralization
with scrubber
280
0.0584
0.0117
0.00117
-
-
Batch Neutralization
without scrubber
230
0.0480
0.00960
0.000960
-
-
Continuous Neutralization
vith scrubber
280
0.0584
0.0117
0.00117
-
-
Continuous Neutralization
without scrubber
230
0.0480
0.00960
0.000960
-
-
Continuous Acid Regeneration
vith scrubber
450
0.0938
0.0187
0.00187
-
-
Continuous Acid Regeneration
without scrubber
400
0.0834
0.0166
0.00166
-
-
COMBINATION ACID
Batch Pipe and Tube
700
0 . 0730
0.0292
0.00292
0.00146
0.0438
Batch Otber
200
0.0209
0.00834
0. 000834
0.000417
0.0125
Continuous
1000
0.104
0.0417
0.00417
0.00209
0.0626
0.000730
0.000209
0.00104
(1) Thia load is allowed only when theae wastes are treeted in combination with
cold rolling Bill wastes.
(2) Thia loed is allowed only when hydrofluoric acid is used.
434
-------
TABLE IX-2
JUSTIFICATION OF BPT EFFLUENT LIMITATIONS
SULFURIC ACID PICKLING SUBDIVISION
Effluent Limitations (kg/kkg)
Proposed BPT Effluent Limitation!
Batch-All Operations
Continuous-Neutralization
(with (pent pickle liquor)
(without spent pickle liquor)
Continuous-Acid Recovery
TSS
0.0521
0.0469
04C
(1)
0.0104
0.00938
Dissolved
Iron
0.00104
0.000938
pH (Units)
6-9
6-9
C4TT
Actual Effluent Loads
Batch-Neutralization
I-2a (08560)
I-2b (08560)
R-2 (0240B)
S-2 (0256C)
090 (0476A)
091 (0612)
096 (01121)
(4)
0.023
0.029
0.000057
0
0.000066
0.00066
0.0028
0.0068
*
Meg
0
0.00400
0.00060
0.0026
0.0018
0.00041
Neg
0
0.00012
0.00093
0.003
6.7
6.7
6.6-9.0
7.5-8.3
7.3
SL,NL
SL.NL
SL,E
100X Recycle
E,A,NL,SC,Ski,FLP
E,CRCC,NL,FLP,T,VF
A,NL,F,T
Batch-Acid Recovery
0-2 (0590)
Q-2 (0894)
Continuous-Neutralization
QQ-2 (0584E)J?
SS-2 (0112A)
TT-2 (0856D)},;1
WW-2 (0868A)
094 (0948C) Strip
094 (0948C) Sheet
097 (0760)
Continuous-Acid Recovery
T-2 (0792B)
0.00015
0.014
0.0039
0.00060
0.00047
0.0013
0.00131
0.000056
0.00022
0.00130
0.000070
0.0004
0.00091
0.0017
Neg
0.00034
*
0.00070
0.000040
0.00013
7.5
7.7
*
8.0
7.6-7.8
7.6-7.8
AR
CRCC,EB,NL,SC,SL
NL,A,T,SL,Ski,FLP
Evaporation Pood
FLP,NL,SC,SL,FLA,Ski
e,NL,Ski,FU>,T
E,NL,FLP,T,Ski
Evaporation and
Crystallization
435
-------
TABLE IX-2
JUSTIFICATION OF BPT EFFLUENT LIMITATIONS
SULFURIC ACID PICKLING SUBDIVISION
PAGE 2
FOOTNOTES
(1) Load permitted only for joint treatment with cold rolling wastewaters.
(2) Plants with scrubbers
(3) Plant uses evaporation pond with no discharge. Quality shown is feed to pond.
(4) Plant neutralizes rinses, settles out solids in a lagoon, and recycles all treated wastewaters.
(5) Plant neutralizes rinses and spent concentrates, and impounds the sludges, with no discharge.
* : Limitation not supported
Neg: Load less than 0.000010 lb/1000 lbs
c&rr codes
A : Aeration
CRCCt Chemical reduction chromium conversion
E : Equalization
EB : Emulsion breaking
F : Filtration
FLA : Flocculation with alum
FLPi Flocculation with polymer
NL ; Neutralization with lime
SC : Sedimentation via clarifier
SKi: Skimming
SL ; Settling lagoon
T : Sedimentation via thickener
436
-------
TABLE IX-3
JUSTIFICATION OF BPT EFFLUENT LIMITATIONS
HYDROCHLORIC ACID PICKLING SUBDIVISION
Effluent Limitation* (kg/Wkg)
TSS
O&G
(1)
Dissolved
Iron
pH (Units)
C&TT
BPT Effluent Limitations (3/76)
B*tch and Continuous Neutralization
with scrubbers 0.0584
without scrubbers 0.0480
Continuous Acid Regeneration
with scrubbers 0.0938
without scrubbers 0.0834
0.0117
0.00960
0.0187
0.0166
0.00117
0.000960
0.00187
0.00166
6-9
6-9
6-9
6-9
Actual Effluent Loada
Batch Neutralization
U-2 (0480AK>
V-2 (0936)
0.136
0.00194
0.009
0.00020
*
8.5
NL
NC
Continuous Neutralization
z-2 (0396D)1;'!;,;
AA-2 (0384A)1*"-"
091 (0612)
093 (0396D)^?
100 ( 0384A)
Continuous Acid Regeneration
x-2 (oo^gyr ;
V-2 (-) . .
95 (0584F)
99 (0S28B)
(2)
0.024
*
0.0111
0.0156
0.0021
0.025
0.0026
0.0048
0.0128
0.00069
*
0.00076
0.0088
0.000077
ND
0.0011
0.00029
0.0144
0.000162
*
0.00030
0.00073
*
*
*
0.00024
8.1-8.6
*
8.4
9.1
8.Z
*
*
*
7.0
E,NL,VF,SC
None
NL,FDS,VF,SC
NL,VF,E,SC
SC
AR
Alt
AR, NL, SL
(1) Load permitted only for joint treatment with cold rolling wastes.
(2) Plants with scrubbers.
(3) Plants discharged to deep well. Later visit (see Plant 100) gives current data on
present treatnene syscsn.
(4) Plant discharges to a P0TW.
NA: Not applicable.
* ! Limitation not supported.
C4TT CODE
AH
E
FDS
NC
Acid regeneration
Equalization
Filtration-deep bed send
Neutralization with cauatic
NL I Neutralization with line
SC : Sedimentation via clarifier
SL : Sedimentation via lagoon
VT ¦ Vacuus filtration
437
-------
TABLE IX-4
Actual BPT Loads
Proposed
BPT Effluent
Limitations
Proposed
BPT Effluent
Limitations
JUSTIFICATION OF BPT EFFLUENT LIMITATIONS
COMBINATION ACID PICKLING SUBDIVISION
Proposed
BPT Effluent
Limitations
TSS
O&C
(I)
Dissolved
Iron
Effluent Limitations (kg/kkg)
Chromium
(2)
Fluoride Nickel
C&TT
Batch-Pipe & Tube
0.0730
0.0292
0.00292
0.00146
0.0438
0.0007 30
U (Unk)
123 (088A)
0.0339
0.00646
0.0028
ND
0.000057
0.00128
0.0001
ND
0.0339
NR
0.00005 NL.SL
0.000776 E,NL,FLP,CL
Batch-Other
Actual BPT Loads
C (0424)
0.0209
0.0118
0.00834
0.00010
0.000834
0.000417
0.0125
0.000209
E, NL,PSP
Continuous
0. L04
0.00417
0.00209
0.0626
0.00104
Actual BPT Loads
O (0176)
121 (Unk)
0.0824
0.0446
0.00196
0.0247
0.00785
0.00145
0.0544
E,NL,FLP,SC,T
E,SC,CR
U) Load pexmitted only when joint treatment vith cold rolling wastewaters it practiced.
(2) Load permitted only when hydrofluoric acid is used.
* t Limitation not supported. Where inadequate treatment was denonstratad within the subcategory,
limitations will be justified by transfer of technology.
NR: Not repotted.
ND; Not detected.
c&rr code
E : Equalization
CR ; Chemical reduction
FLP: Flocculation with polymer
NL : Neutralization with lime
PSP: Primary scale pit
SC : Sedimentation via clarifier
T : Sedimentation via thickener
438
-------
W
VO
Spent
Pickle
Liquor
FUME HOOD
SCRUBBER
BLOWDOWNS
CASCADE
RINSE
PICKLE
TANK(S)
-Cool to
I0#C(50»F)
CRYSTA
LLIZER
c>o
CRYSTAL
COLLECTOR
RECOVERED
ACID TANK
Recovered Acid
FERROUS SULFATE
HEPTAHYORATE CRYSTALS
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
SULFURIC ACID PICKLING
CONTINUOUS B BATCH ACID RECOVERY
8PT MODEL
D*m.6/l2/80
FIGURE IX" I
-------
EQUALIZATION
TANK
LIME
PICKLE
RINSE
WATER
SPENT PICKLE
LIQUOR
EQUALIZATION
TANK
FUME HOOD
SCRUBBER
SLOWDOWN
POLYMER
-t
•TO DISCHARGE
SETTLING
BASIN
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
SULFURIC ACID PICKLING
BATCH a CONTINUOUS NEUTRALIZATION
BPT MODEL
Dwn.6/13/80
FIGURE JK-2
-------
EQUALIZATION
TANK
.ACID TO
REUSE
ABSORBER
VENT SCRUBBER
(ONCE-THROUGH)
ACID
REGENERATION
UNIT(S)
PICKLE
RINSE
WATER
SPENT PICKLE
LIQUOR
EQUALIZATION
TANK
FUME HOOD
SCRUBBER
SLOWDOWN
THICKENER
AIR
LIME
POLYMER
VACUUM
FILTER
•TO DISCHARGE
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
HYDROCHLORIC ACID PICKLING
CONTINUOUS ACID REGENERATION
BPT MODEL
Dwn. 6/17/80
FIGURE IX-3
-------
lp»
NJ
To
Discharge
THICKENER
EQUALIZATION
TANK
AIR
LIME
POLYMER
VACUUM
FILTER
SPENT PICKLE
LIQUOR
EQUALIZATION
TANK
PICKLE
RINSE
WATER
FUME HOOD
SCRUBBER
SLOWDOWN
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
HYDROCHLORIC ACID PICKLING
BATCH 8 CONTINUOUS NEUTRALIZATION
BPT MODEL
Dwn.6/16/80
FIGURE I£-4
-------
OIL
^•TO DISCHARGE
CLARIFIER
EQUALIZATION
TANK
LIME
POLYMER
VACUUM
FILTER
SPENT PICKLE
LIQUOR
EQUALIZATION
TANK
FUME HOOD
SCRUBBER
BLOWDCMN
PICKLE
RINSE
WATER
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
COMBINATION ACID PICKLING
BATCH 8 CONTINUOUS NEUTRALIZATION
BPT MODEL
Own.&'ie/BO
FIGURE IX-5
-------
ACID PICKLING SUBCATEGORY
SECTION X
EFFLUENT QUALITY ATTAINABLE THROUGH THE APPLICATION
OF THE BEST AVAILABLE TECHNOLOGY ECONOMICALLY ACHIEVABLE
Introduction
The Best Available Technology Economically Achievable (BAT) effluent
limitations are to be attained by July 1, 1984. BAT is determined by
reviewing subcategory practices and identifying the best economically
achievable control and treatment technologies employed within the
subcategory. In addition, where a technology is readily transferable
from one subcategory or industry, such technology may be identified as
BAT.
This section identifies the model BAT flow rates, three BAT
alternative treatment systems, and the resulting effluent levels
considered for the acid pickling subcategory. In addition, the
rationale for the Agency's selection of the alternative treatment
systems, applied and discharge flow rates, and effluent pollutant
concentrations are presented. Finally, this section addresses the
Agency's selection of a BAT model treatment system to serve as the
basis for the proposed BAT limitations.
Identification of BAT
Based upon information contained in Sections III through VIII of this
report, the Agency developed the following three alternative treatment
systems (as add-ons to the BPT treatment system models) for the acid
pickling subcategory. These three alternatives are applicable to all
pickling operations except for those practicing sulfuric acid
recovery. The acid recovery operations attain zero discharge at BPT.
Therefore, no further treatment is necessary beyond BPT.
BAT Alternative No. 1_
The first BAT alternative treatment system reduces the flow being
discharged from the rinse operations through the application of a
cascade or countercurrent rinse system. The fume scrubber blowdown
may be eliminated by feeding it to the cascade rinse system. Zero
discharge of fume scrubber wastewaters could also be achieved by 100%
recycle. At the present time, plants in the sulfuric and hydrochloric
acid subdivisions have demonstrated zero discharge of fume scrubber
waters through blowdown to the cascade rinse system. Other plants
have achieved zero discharge by using mist filters in lieu of wet
scrubbers.
BAT Alternative No. 2
The second BAT alternative treatment system employs the same cascade
rinse system presented in the description of Alternative No. 1. In
445
-------
addition, toxic metals removals are improved by the installation of a
sulfide precipitation system followed by a filter. The filter removes
suspended solids in the wastewater and the toxic metals entrained in
the suspended solids,
BAT Alternative No. 3
The third BAT alternative treatment system also employs the cascade
rinse system described in Alternative No. 1. In addition, this
alternative achieves zero discharge of the entire wastewater flow.
Evaporation, with the use of a multi-stage evaporator, a condenser,
and a centrifuge to dewater the slurries generated, are included to
achieve zero discharge. The distillate quality water, which is
produced by this system, is recycled back to the acid pickling
operation.
Figures X-l through X-4 illustrate the BAT alternative treatment
systems described previously for the acid pickling subcategory. The
treatment technologies shown represent those technologies in use at
one or more plants, or demonstrated in other wastewater treatment
applications, and considered to be capable of attaining the respective
BAT effluent levels.
Pollutants Limited at BAT
The BAT effluent limitations for each alternative treatment system are
presented in Table X-l6. The pollutants listed in this table
represent a condensation of the list of selected pollutants presented
in Section VI. The Agency selected pollutants for limitation based
upon the following factors: treatability using the technologies
presented in the alternative treatment systems, and the ability to
serve as indicators of both the presence and the removal of other
pollutants.
Analytical data indicate that chromium, lead, and zinc predominate in
sulfuric and hydrochloric acid pickling wastewaters. Chromium,
copper, and nickel are found at much higher levels and in much greater
quantities than other toxic pollutants in combination acid pickling
wastewaters. Based upon these observations, the Agency has selected
chromium, lead, and zinc for sulfuric and hydrochloric operations and
chromium, copper, and nickel for combination operations, as the toxic
pollutants to be limited at BAT. Other toxic metals could be found in
acid pickling wastewaters; however, control of the toxic metals listed
in Table X- 16 will also result in comparable control of the other
toxic metals. Toxic organics have also been found in acid pickling
wastewaters at very low levels. However, the cascade rinse system,
which is part of all three BAT alternative treatment systems, will
provide significant reductions in toxic organic pollutant loads, as
well as in toxic metal pollutant loads, by reducing the discharge
volume.
In addition to the toxic metals listed above, fluoride is also limited
at BAT in the combination acid subdivision. However, these
limitations only apply when hydrofluoric acid is used in the pickling
process.
446
-------
Rationale for BAT
The following discussion presents the rationale for the selection of
the BAT model treatment systems and for the determination of the flow
rates and effluent concentrations of the critical pollutants.
Treatment Scheme
The cascade rinse system included in the first BAT alternative
treatment system is commonly used by plants in the acid pickling
subcategory. The 85% recycle rate used to develop BAT model flows has
been demonstrated by two acid pickling plants. In addition, zero
discharge from the fume scrubber recycle system has been demonstrated
by plants in the sulfuric and hydrochloric acid pickling subdivisions.
Zero discharge is being achieved by reuse of the fume scrubber
blowdown in the rinsing operation, and by total recycle (100%) of the
fume scrubber wastewater system.
The sulfide precipitation system incorporated in the second BAT
alternative treatment system is not presently demonstrated in this
subcategory. However, its effectiveness in removing toxic metals from
wastewaters has been demonstrated in studies involving wastewaters
from other metals manufacturing operations. Filtration, used to
remove solids and metals precipitated with sulfide, has also been
proven in other subcategories.
The evaporation technology included in the third BAT alternative
treatment system is extremely costly and energy intensive in
comparison to the other BAT alternative treatment systems.
BAT Flow Rates
The best applied flows were averaged for each acid pickling segment
for the purposes of sizing and costing treatment systems and
establishing effluent limitations. These averages of concentrate,
rinse, fume scrubber, and absorber vent scrubber (if applicable)
streams for the various acid pickling segments appear in Tables X-l
through X-l4. The flow rates for this subcategory were developed as
explained below.
Raw Wastewater Flow Values
The BAT raw flow rates were determined by summing the appropriate
concentrate, rinse, fume scrubber, and absorber vent scrubber (if
applicable) flows.
Bat Feed Flow Values
The BAT feed flow rates were determined by summing the appropriate
concentrate, rinse, fume scrubber blowdown, and absorber vent scrubber
(if applicable) flows. The best discharge fume scrubber values were
averaged to determine fume scrubber blowdowns. All acid pickling
segments, except for combination continuous, demonstrated 10 gal/ton
of fume scrubber blowdown. Combination continuous operations
demonstrated 50 gal/ton of fume scrubber blowdown.
447
-------
BAT Model Flow Values
The model BAT flows were determined by summing the appropriate
concentrate, cascade rinse blowdown, fume scrubber blowdown, and
absorber vent scrubber blowdown (if applicable) flows. Data from two
pickling operations (0584F and 0384A) demonstrate rinse flow
reductions with cascade rinse systems in excess of 85%.
Based on these data, model BAT feed rinse flows were reduced by 85% at
the BAT level. Several hydrochloric acid regeneration operations have
demonstrated 80% recycle of absorber vent scrubber (AVS) streams.
Based on these data, BAT feed AVS flows were reduced to 20% of the
original value, at the BAT level. In addition, the fume scrubber flow
was reduced to zero at BAT for sulfuric and hydrochloric operations.
This reduction was based upon the sulfuric and hydrochloric operations
which have demonstrated the ability to blow down any remaining fume
scrubber flow to the cascade rinse system. This type of reduction has
not been demonstrated at combination acid plants. The fume scrubber
flow could also be reduced by 100% recycle of the fume scrubber
wastewaters as reported for many plants.
Refer to Table X-15 for the development of model BAT flow rates.
Wastewater Quality
The average effluent concentrations incorporated in each BAT
alternative treatment system follow (the maximum values are enclosed
in parentheses):
Pollutant, mq/1 BAT-1 BAT-2 BAT-3
Fluoride1 15 (45) 15 (45)
Chromium2 0.10(0.30) 0.10(0.30)
Copper3 0.10(0.30) 0.10(0.30)
Lead4 0.10(0.30) 0.10(0.30)
Nickel3 0.20(0.45) 0.10(0.30)
Zinc4 0.10(0.30) 0.10(0.30)
IFluoride is limited in the combination acid subdivision only when
hydrofluoric acid is used.
2Chromium is limited in all three acid pickling subdivisions.
3Copper and nickel are limited in the combination acid pickling
subdivision only.
4Lead and zinc are limited in the sulfuric acid and hydrochloric acid
pickling subdivisions only.
Toxic Metal Pollutants
A. BAT Alternative No. 1
The cascade rinse system in this alternative achieves a
substantial flow reduction which results in a comparable
pollutant load reduction. The pollutant concentrations in the
remaining flow are dependent upon the preceding treatment
components. Thickeners, clarifiers, or settling basins with
448
-------
chemical addition are incorporated at the BPT level of treatment.
Short-term data involving these treatment components, in pickling
and other related subcategories, were reviewed to determine the
toxic metal removal capabilities of these wastewater treatment
components. Reference is made to Volume I, Appendix A, for the
derivation of 30-day average and daily maximum performance
standards for Alternative No. 1.
B. BAT Alternative No. 2
As noted previously in this section, BAT Alternative No. 2
incorporates a sulfide precipitation and filtration system in
addition to the cascade rinse system in Alternative No. 1. As
sulfide precipitation technology has not been demonstrated in
this subcategory, the capabilities of this technology have been
transferred from other metals manufacturing wastewater treatment
applications. The toxic metals effluent levels which can be
achieved with this treatment technology were developed on the
basis of the data review presented in Volume I. The data
indicate that average toxic metals effluent concentrations of
0.10 mg/1 can be attained with this treatment technology.
C. BAT Alternative No. 3
The evaporation system incorporated in BAT Alternative No. 3
achieves zero discharge of process wastewater pollutants.
Effluent Limitations for Alternative Treatment Systems
The effluent limitations for the BAT alternative treatment systems
were calculated by multiplying the model effluent flow incorporated in
each alternative treatment system and the corresponding concentration
of metals with appropriate conversion factors. Table X-16 presents
the effluent limitations developed for each alternative treatment
system in each segment of the subcategory.
Selection of a BAT Alternative
The Agency has selected BAT Alternative No. 1 as the model treatment
system upon which the proposed BAT limitations are based. Cascade
rinse systems are well demonstrated in the acid pickling subcategory,
while sulfide precipitation and evaporation techniques are not. For
this reason, the first alternative was selected as the BAT model
treatment system. The proposed BAT effluent limitations are presented
in Table X-16 under the Alternative No. 1 heading.
449
-------
TABLE X-l
ANALYSIS OF FLOW DATA
SULFURIC ACID PICKLING-BATCH
APPLIED FLOW RATE (GPT)
Plant Code
Concentrates
Rinses
Basis
0088A-1
8.1
<1
DCP
0946A-3
5.4
3.5
DCP
0088D-1
14.2
4.7
DCP
0248A-2
8.1
6.0
DCP
0946A-1
10.4
6.4
DCP
0894
24.3
8.0
Sampled
0684D-2
8.9
8.3
DCP
0946A-2
18.8
8.6
DCP
0112-1
11.9
9.7
DCP
0248A-3
10.0
10.0
DCP
0048D-2
10.4
10.4
DCP
0684P-1
9.9
11.2
DCP
0048B
5.5
15 .
DCP
0684E-1
17.5
15.7
DCP
0312
17.6
16.9
Sampled
0060M
2.2
17.3
DCP
0684P-3
10.0
17.4
DCP
0590
Unk
18.0
Sampled
0048D-1
27.0
27.0
DCP
0048F
13
37
DCP
0684P-2
10.0
40.3
DCP
0684E-4
17.5
41
DCP
0916A-2
18.0
42
DCP
0088A-2
22.6
49.2
DCP
0684G-1
3.5
54.3
DCP
0856T
5.6
55.8
DCP
0048B
20.0
58.3
DCP
0856U
23.7
62
DCP
0584C
9.7
62.3
DCP
0240B
10.5
62.9
DCP
0684G-2
11.9
74.5
DCP
0884G
11.0
77.0
DCP
0684D-3
8.9
77.4
DCP
0248A-1
9.4
84.4
DCP
0240A
Unk
85.4
DCP
047 6A
Unk
91
Sampled
0492A
3.5
91
Sampled
0256G
18.3
107
DCP
0088A-4
16.3
117
DCP
0612
14.6
122
Sampled
450
-------
TABLE X-l
ANALYSIS OF FLOW DATA
SULFURIC ACID PICKLING-BATCH
APPLIED FLOW RATE (GPT)
PAGE TWO
Plant Code Concentrates Rinses Basis
0088A-5
42.1
132
DCP
0856S
2.76
134
DCP
0240C
3.8
141
DCP
0856N-3
11.7
160
DCP
0684V
21.0
164
DCP
0916A-7
15.0
165
DCP
0384A-2
2.5
180
DCP
0460D
28.9
181
DCP
0856N-2
21.7
209
DCP
0684Q
24.6
215
DCP
0460G
22.7
224
DCP
0112-2
22.5
231
DCP
0460F
32.6
261
DCP
0088A-3
14.6
272
DCP
0460B
13.3
280
DCP
0728
7.8
288
DCP
0684E-3
17.5
297
DCP
0856F-3
7.7
346
DCP
0868A-1
5.0
349
DCP
0264
17.1
382
DCP
0864B-1
9.2
398
DCP
0884C
25.0
400
DCP
0460C
12.5
410
DCP
0856N-1
20
432
DCP
0264D
13.6
446
DCP
0860F
16.6
465
DCP
0856Q
15
480
DCP
0460H
27.7
535
DCP
0264C
11.8
589
DCP
0548B
27.0
649
DCP
0856P-2
13.5
696
DCP
0068
70 **
769
DCP
0684E-2
17.5
820
DCP
0460A-1
25.8
824
DCP
0548-1
8.9
853
DCP
0860G
22.4
o52
DCP
0640-1
27.6
898
DCP
0684H-1
25.3
913
DCP
0256F
4
960
DCP
0548-3
9.0
960
DCP
0548-2
9.0
961
DCP
451
-------
TABLE X-l
ANALYSIS OF FLOW DATA
SULFURIC ACID PICKLING-BATCH
APPLIED FLOW RATE (GPT)
PAGE THREE
Plant Code
Concentrates
Rinses
Basis
0548-4
0460A-3
0920D
0948B
0856F-2
0884D
0384A-1
0088D-2
0948A
0460A-2
0640-2
0060C
0112A-2
0112C-1
0112C-2
0112C-3
0112F-1
0112F-2
01121-1
01121-2
01121-3
01121-4
01121-5
01121-6
01121-7
0432A-2
0432A-3
0432A-4
0856R
9.1
27.0
33.7
Unk
4.1
16.7
14.3
Unk
48.9**
47.8**
7.6
8
4.5
22.1
8.9
9.9
5.1
3.8
10.5
20.5
14.8
25.9
33.7
110 **
22.3
26
25.1
19.2
8.5
965
973
1079
1081
1126
1200
1379
2775**
3810**
4174**
8291**
Unk
Unk
Unk
Unk
Unk
Unk
Unk
Unk
Unk
Unk
Unk
Unk
Unk
Unk
Unk
Unk
Unk
Unk
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
Unk: Unknown
- : Not present
** : Not used in "Average of the Best" Calculation
APPLIED FLOW RATE AVERAGES
Concentrates
Average of all sources 17.4 GPT
"Average of the best" 15.6 GPT
Rinses
Average of all sources 537 GPT
"Average of the best" 327 GPT
Note: The above averages include confidential data
452
-------
TABLE X-2
ANALYSIS OF FLOW DATA
SULFURIC ACID PICKLING-BATCH
Plant
Code
Applied Flow Rate (GPT)
Scrubbers
Discharge Flow Rate (GPT)
Scrubbers
Basis
0460H
306
0
DCP
0856N-3
534
133**
DCP
0548-2
846
0
DCP
0856N-1
960
240**
DCP
0240C
1000
41
DCP
0384A-2
1200
156**
DCP
0856F-3
2677**
185**
DCP
0856F-2
7518**
162**
DCP
** » Not
used in "Average of the best
" calculation
APPLIED
FLOW RATE AVERAGES
Scrubbers
Average of all sources 1684 GPT
"Average of the best" 708 GPT
DISCHARGE FLOW RATE AVERAGES (Of those plants practicing flow reduction)
Scrubbers
Average of all sources 102 GPT
"Average of the best" 10.3 GPT
Note: The above averages include confidential data.
453
-------
TABLE X-3
ANALYSIS OF FLOW DATA
SULFURIC ACID PICKLING-CONTINUOUS
Applied Flow Rate (GPT)
Plant Code
Concentrates
Rinses
0856P
27.5
1.95
0760
7.2
11.1
0112A-6
29.2
11.5
0528A-2
14.7
19.6
0256C-1
11.0
29.4
0256C-2
11.0
29.4
0856F
18.0
54
0112A-12
34.7
80
0112A-13
34.7
80
0112A-10
34.7
86
0868A-3
36.8
96
0432A-1
14.4
115
0122A-7
8.4
127
0792C
39.0
127
0856D-3
13.0
129
0868A-4
45.6
133
0112A-4
14.4
136
0112A-5
18
143
0856D-2
11.5
143
0112A-3
17
149
0948C-4
11.3
161
0868A-2
40.5
162
0112A-11
11.7
170
0864B-2
24.8
170
0864B-4
27.7
190
0256A
9.7
209
0856D-4
10.2
225
0864B-3
37.4
257
0684C
21.3
284
0584E
15.8
300
0948C-1
21.4
303
0856D-1
15.9
310
0396E-1
Unk
328
0112A-8
27.9
338
0868A-5
23.9
345
0948C-2
21.4
422
0112A-9
30.9
423
0256B
15
425
0432B
17
427
0856U-2
12.7
467
Basis
DCP
Sampled Data
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
Sampled Data
DCP
DCP
DCP
DCP
Sampled Data
DCP
DCP
DCP
DCP
454
-------
TABLE X-3
ANALYSIS OF FLOW DATA
SULFURIC ACID PICKLING-CONTINUOUS
PAGE TWO
Applied Flow Rate
(GPT)
Plant Code
Concentrates
Rinses
Basis
0432M
7.8
469
DCP
0948C-3
13.6
532
DCP
0020B
6.4
539
DCP
0856E
21.4
758**
DCP
0176
Unk
847**
DCP
0580C
10.4
1184**
DCP
0432L
3.3
1200**
DCP
0580-2
31.3
1800**
DCP
0580-1
16.7
4000**
DCP
0384A-3
51.4**
4141**
DCP
0580-3
20.0
10,000**
DCP
0060D-2
5.0
Unk
DCP
0112D
Unk
Unk
DCP
0528A-1
Unk
Unk
DCP
**: Not used in "Average of the best" calculation
APPLIED FLOW RATE AVERAGES
Concentrates
Average of all sources 20.5 GPT
"Average of best" 19.9 GPT
Rinses
Average of all sources 649 GPT
"Average of best" 213 GPT
455
-------
TABLE X-4
ANALYSIS OF FLOW DATA
SULFURIC ACID PICKLING-CONTINUOUS
Plant Applied Flow Rate(GPT)
Code Scrubbers
Discharge Flow Rate(GPT)
Scrubbers
Basis
0112A-11
16.7
16.7
DCP
0856D-4
20.5
20.5
DCP
0112A-4
23
23
DCP
0856D-1
44
44
DCP
0528A-2
55.9
55.9
DCP
0856F
62
11.3**
DCP
0020B
90
90
DCP
0856D-3
97
97
DCP
0256A
104
104
DCP
856D-2
143
143
DCP
0856P
232
232
DCP
0432M
234
234
DCP
0792C
237
0
DCP
0856E
253
253
DCP
0684C
284
284
DCP
0256B
425**
425
DCP
0868A-3
448**
0
DCP
0868A-4
597**
0
DCP
0176
750**
750
DCP
0868A-2
908**
0
DCP
0060D-2
Unk
Unk
DCP
0112A-3
Unk
Unk
DCP
0112A-5
Unk
Unk
DCP
0112A-6
Unk
Unk
DCP
0112A-7
Unk
Unk
DCP
0112A-8
Unk
Unk
DCP
0112A-9
Unk
Unk
DCP
0112D
Unk
Unk
DCP
0432B
Unk
Unk
DCP
0528A-1
Unk
Unk
DCP
0584E
Unk
Unk
DCP
0868A-5
Unk
Unk
DCP
Unk: Unknown
**: Not used in
"Average of best"
calculation
APPLIED FLOW RATE
AVERAGE
Scrubbers
Average of all sources 251 GPT
"Average of best" 126 GPT
DISCHARGE FLOW RATE AVERAGE (all plants practicing flow reduction)
Scrubbers
Average of all sources 2.3 GPT
"Average of best" 0 GPT
456
-------
TABLE X-5
ANALYSIS OF FLOW DATA
HYDROCHLORIC ACID PICKLING-BATCH
Applied Flow Rate (GPT)
Plant Code
Concentrates
Rinses
Bas is
048OA
6.5
92.9
Sampled
0936
3.9
167
Sampled
0384A-6
4.4
469
DCP
0864B
6.6
1319
DCP
0176
Unk
1811**
DCP
0580A-3
38.0**
1950**
DCP
0060L
4.0
13,400**
DCP
Unk: Unknown
**: Not used in "Average of best" calculation
APPLIED FLOW RATE AVERAGES
Concentrates
Average of all sources 11.6 GPT
"Average of best" 7.2 GPT
Rinses
Average of all sources 2481 GPT
"Average of best" 538 GPT
457
-------
TABLE X-6
ANALYSIS OF FLOW DATA
HYDROCHLORIC ACID PICKLING-RATCH
Plant
Code
Applied Flow Rate (GPT) Discharge Flow Rate (GPT)
Scrubbers
Scrubbers
Basis
0864B
0384A-6
132
169
0
169
DCP
DCP
Unk: Unknown
Not present
**: Not used in "Average of best" calculation
APPLIED FLOW RATE AVERAGES
Scrubbers
Average of all sources 399 GPT
"Average of best" 150 GPT
DISCHARGE FLOW RATE AVERAGES (of those plants practicing flow reduction)
Scrubbers
Average of all sources 0 GPT
Note: The above averages inlcude confidential data.
458
-------
TABLE X-7
ANALYSIS OF FLOW DATA
HYDROCHLORIC-ACID PICKLING-COHTINUOUS
Applied- Flow Rate
«JPT>
Plant € ode
Concentrates
Rinses
Baai«
0612-5
<1
0
DCP
03 84-4
7.2
7.7
DCP
085 6 F
9.6
60
DCP
0948A-1
3.7
61
DCP
0948A-2
4.4
71
DCP
0724A-4
7.3
84
DCP
Y-2
Unk
87.3
Sampled Data
0684 B-2
12.3
102
DCP
0684B-l
8.7
109
DCP
0724A-3
Unk
137
DCP
0584 A-3
4.1
191
DCP
0528B
81.7**
216
Sampled Data
0584 A-1
4.6
217
DCP
0584 A-2
4.8
224
DCP
0584 C
4. 7
225
DCP
0920G
7.0
225
DCP
W-2
11.9
228
Sampled' Data
03 96D
203**
234
Sampled Data
0432C-2
15.3
239
DCP
0580-4
1.5
240
DCP
0580B-2
1.5
240
DCP
0580D-3
1.5
240
DCP
0580E-2
1.5
240
DCP
0580F-2
1.5
240
DCP
0584 A-A
5.2
243
DCP
0920C
7.4
258
DCP
0920A-1
18.7
270
DCP
0060-2
13. 7
274
DCP
0580-3
3.0
288
DCP
0580B-l
3.0
288
DCP
0580D-2
3.0
288
DCP
0920A-2
19.3
290
DCP
0060-1
14.8
295
DCP
0868A
25.4
299
DCP
0684 F-2
8.2
305
DCP
0612
18.1
328
Sampled Data
0864 B-4
8.8
330
DCP
0580-2
1.8
360
DCP
0580-6
3.8
360
DCP
0580B-3
1.8
360
DCP
0580 D-l
1.8
360
DCP
459
-------
TABLE X-7
ANALYSIS OF FLOW DATA
HYDROCHLORIC ACID PICKLING-CONTINUOUS
PAGE TWO
Applied Flow Rate- (OPT)
Plant Code
Concentrates
Rinses
Basi
0580E-1
1.8
360
DCP
0580F-l
1.8
360
DCP
0068-2
8.0
367
DCP
0384 -2
8.3
372
DCP
0864 B-3
12.0
400
DCP
0384-3
7.7
450
DCP
0864B-l
2.5
487
DCP
0684 F-l
7.3
500
DCP
0684 F-3
8.1
503
DCP
0856S-1
0.8
589
DCP
0432D
8.5
596
DCP
0384-1
13.6
763
DCP
0864B-2
5.3
766
DCP
0020C
35
958
DCP
0580 C-3
4.4
1152**
DCP
0724A-2
Unk
1200**
DCP
0856S-2
2.4
1309**
DCP
0580-5
33.3
1333**
DCP
0580-1
10.0
1440**
DCP
0580C-l
17.5
1440**
DCP
0068-1
13.2
2087**
DCP
0860F-1
7.0
3130**
DCP
0724A-1
Unk
4160**
DCP
0860F-2
12.8
5760**
DCP
0860F-3
12.8
5760**
DCP
0580C-2
13.0
6034**
DCP
0580 A-1
5.9
6240**
DCP
0580 A-2
117.5**
9333**
DCP
085 6 P
5.9
15,540**
DCP
0112B-1
Unk
Unk
DCP
0112 B-2
Unk
Unk
DCP
0112 B-3
Unk
Unk
DCP
0112D-1
Unk
Unk
DCP
0112D-2
Unk
Unk
DCP
0112H
20.9
Unk
DCP
0320-1
6.6
Unk
DCP
0320-2
5.1
Unk
DCP
0320-3
6.5
Unk
DCP
0320-4
6.1
Unk
DCP
0448A-1
9.8
Unk
DCP
0448A-2
7.0
Unk
DCP
460
-------
TABLE X-7
ANALYSIS OF FLOW DATA
HYDROCHLORIC ACID PICKLING-CONTINUODS
PAGE TIBIEE
Unk: Unknown
**! Data not included in "Average of the best" calculati
APPLIED FLOW RATE AVERAGES
Concentrates
Average of all sources 14.0 GPT
"Average of best" 8.4 GPT
Note: The above averages include confidential dta.
Rinses
Average of all sources
"Average of best"
1150 GPT
295 GPT
461
-------
TABLE X-8
ANALYSIS OF FLOW DATA
HYDROCHLORIC ACID PICKLING-CONTINUOUS
Plant
Applied Flow Rate (GPT)
Discharge Flow Rate (GPT)
Code
Scrubbers
Scrubbers
Basis
0020C
7.4
7.4
DCP
0384-4
7.7
7.7
DCP
0920A-1
16
16
DCP
0724A-4
17
17
DCP
0864B-4
18
0
DCP
0920A-2
18
18
DCP
0920C
24
24
DCP
0864B-3
25
0
DCP
0112D-2
45
Unk
DCP
0868A
45
0
DCP
0432C-2
47.8
47.8
DCP
0432C-1
49.2
49.2
DCP
0112D-1
58
Unk
DCP
0856F
66
12
DCP
0580-2
72
72
DCP
0432D
78.3
78.3
DCP
0528B
78.7
6.1
Sampled Data
0060-2
80.4
12.0
DCP
0724A-2
86
86
DCP
0060-1
86.8
12.9
DCP
0724A-3
88
78**
DCP
0684F-2
93
12
DCP
0684B-2
102
0
DCP
0112B-2
111
Unk
DCP
0580B-3
120
120
DCP
0580D-1
120
120
DCP
0580F-1
120
120
DCP
0584A-3
127
127
DCP
0584C
141
0.8
DCP
0580D-3
144
0
DCP
0580F-2
144
0
DCP
0320-4
144
144
DCP
0584A-1
145
145
DCP
0584A-2
149
149
DCP
0584A-4
162
162
DCP
0684F-1
166
21
DCP
0112B-3
183
Unk
DCP
0112B-1
202
Unk
DCP
0320-3
210
210
DCP
0320-1
214
214
DCP
462
-------
TABLE X-8
ANALYSIS OF FLOW DATA
HYDROCHLORIC ACID PICKLING-CONTINUOUS
PAGE TWO
Plant
Applied Flow Rate (GPT)
Discharge Flow Rate (GPT)
Code
Scrubbers
Scrubbers
Basis
0684B-1
217
217
DCP
0684F-3
251
251
DCP
0320-2
277
277
DCP
0580D-2
288
288
DCP
0580-3
288
288
DCP
0580B-1
288
288
DCP
0384-2
298
298
DCP
0724A-1
300
240**
DCP
0112H
358
Unk
DCP
0580-6
360
360
DCP
0948A-1
454
10
DCP
0384-3
463
463
DCP
0948A-2
536
12
DCP
0384-1
611
611
DCP
0060D
696
696
DCP
0856P
15,125**
0
DCP
0396D
Unk
31.1
Sampled Data
0448A-1
Unk
Unk
DCP
0448A-2
Unk
Unk
DCP
W-2
Unk
45.5
Sampled Data
Y-2
Unk
39.7
Sampled Data
**: Data not included in "Average of the best" calculation
APPLIED FLOW RATE AVERAGES
Scrubbers
Average of all data 430 GPT
"Average of the best" 176 GPT
DISCHARGE FLOW RATE AVERAGES (includes only those plants which recycle)
Scrubbers
Average of all data 29.0 GPT
"Average of the best" 6.2 GPT
Note: The above averages include confidential data.
463
-------
TABLE X-9
ANALYSIS OF FLOW DATA
COMBINATION ACID PICKLING-BATCH
Applied Flow Rate
(GPT)
Plant Code
Concentrates
Rinses
Basis
0884F
<1
<1
DCP
0684P-1
12.0
38
DCP
0424-1
10.8
93
DCP
0060N
46.9
109
DCP
0684P-2
14.0
133.6
DCP
0684P-3
14.0
135.5
DCP
0580G
1.3
143
DCP
0068
27.6
162
DCP
0776F
1.2
169
DCP
0440A-1
6.9
178
DCP
0088A
4.1
310
Sampled
0256N-2
11
320
DCP
0284A
3.0
325
DCP
0856H
13.4
338
DCP
0776J
11.6
360
DCP
0440A-2
11
384
DCP
0796A
12.0
386
DCP
0684V
5.8
409
DCP
0424-2
45.7
463
DCP
00601
Unk
611
DCP
0176-1
Unk
633
DCP
0580
1.0
640
DCP
0884E
6.3
650
Sampled
0748
Unk
677
Sampled
0176-7
Unk
711
DCP
0496
9.0
736
DCP
0088-1
6.6
791
DCP
0088-2
6.6
791
DCP
0176-6
Unk
805
DCP
0856E
12.3
922
DCP
0476A
31
932
DCP
0256F
9.5
960
DCP
0248C-1
2.4
1015
DCP
0176-2
Unk
1043
DCP
0776G
18.7
1050
DCP
0088D
Unk
1176
Sampled
0176C
41.3
1617**
DCP
0020B-3
52.1
2182**
DCP
0248C-3
2.7
2310**
DCP
0792A
4.0
2667**
DCP
0548A
0.6
2743**
DCP
464
-------
TABLE X-9
ANALYSIS OF FLOW DATA
COMBINATION ACID PICKLING-BATCH
PAGE TWO
Applied Flow Rate
(GPT)
Plant Code
Concentrates
Rinses*
0176D
35
3200**
0776H
42.7
3303**
0548B
16.1
3871**
0248C-2
20.8
8889**
0060P
8.2
Unk
0112A-1
3.9
Unk
0112C
16.3
Unk
0112H
6.5
Unk
Basis
DCP
DCP
DCP
DCP
DCP
DCP
DCP
DCP
Unk: Unknown
Not Present
**: Not used in "Average of the best" calculation
APPLIED FLOW RATE AVERAGES
Concentrates
Average of all sources 14.1 GPT
"Average of best" 14.1 GPT
Rinses
Average of all sources 1169 GPT
"Average of best" 517 GPT
Note: The above averages include confidential data.
465
-------
TABLE X-10
ANALYSIS OF FLOW DATA
COMBINATION ACID PICKLING-BATCH
Plant
Code
Applied Flow Rate (GPT) Discharge Flow Rate (GPT)
Scrubbers
Scrubbers
Basis
0856H
0284A
0432E
0176D
0176-2
0884E
0176-1
0176-7
0176-6
0256F
39.4
163
864
960
2087
2700
417**
6.3
330**
284**
242**
0
39.4
163
864
960
DCP
DCP
DCP
DCP
DCP
Sampled Data
3550**
5689**
6443**
7200**
DCP
DCP
DCP
DCP
- = Not present
** = Not used in "Average of the best" calculation
APPLIED FLOW RATE AVERAGES
Scrubbers
Average of all sources 3344 GPT
"Average of the best" 1136 GPT
DISCHARGE FLOW RATE AVERAGES (Of those plants practicing flow reduction)
Scrubbers
Average of all sources 160 GPT
"Average of the best" 2.0 GPT
Note: The above averages include confidential data.
466
-------
TABLE X-ll
ANALYSIS OF FLOW DATA
COMBINATION ACID PICKLING-CONTINOOUS
Applied Flow Rate
(GPT)
Plant Code
Concentrates
Rinses
Basis
0948F
Unk
176
DCP
0284A-3
1.9
313
DCP
0284A-2
1.7
358
DCP
0432K-1
1.6
457
DCP
0176-3
Unk
558
DCP
0020L-2
7.2
1011
DCP
0020B-2
24.7
1029
DCP
02560-3
7.5
1064
DCP
0020L-1
7.8
1087
DCP
0684D-7
11.2
1255
DCP
0020B-1
15.5
1333
DCP
0684D-14
12.8
1383
DCP
0684D-6
16.8
1387
DCP
0060E-1
8.2
1690
DCP
0684D-12
18.8
1714
DCP
0724A-1
Unk
1846
DCP
0684D-2
Unk
1867
DCP
0176-5
Unk
2000
DCP
0684D-3
23.4
2044
DCP
0648
15
2097
DCP
0684D-5
24.9
2100
DCP
0176-4
Unk
2182
DCP
0684D-11
22.4
2222
DCP
0248B-9
8.1
2237
DCP
0020C-6
Unk
2271
DCP
0684D-1
22.2
2291
DCP
0684D-10
7.6
2713
DCP
0248B-1
13.4
2721
DCP
0900
Unk
2754
Sampled Data
0020C-8
Unk
2900
DCP
0248B-5
10.6
2923
DCP
0684D-9
25.7
3120
DCP
0248B-3
13.9
3162
DCP
0248B-10
11.7
3230
DCP
0020C-1
Unk
4127**
DCP
0684D-4
Unk
4246**
DCP
0248B-4
13.4
4255**
DCP
0684D-8
18.4
4457**
DCP
0248B-6
21.1
4688**
DCP
0724A-2
Unk
4966**
DCP
0020C-5
Unk
5509**
DCP
467
-------
TABLE X-ll
ANALYSIS OF FLOW DATA
COMBINATION ACID PICKLING-CONTINUOUS
PAGE TWO
Applied Flow Rate
(GPT)
Plant Code
Concentrates
Rinses
Bas:
0432L
18
5571**
DCP
02560-1
11.5
5729**
DCP
02560-4
17.0
6051**
DCP
0020C-2
Unk
6288**
DCP
0020C-3
Unk
6288**
DCP
02560-2
15.3
6588**
DCP
0248B-8
13.1
7317**
DCP
0248B-2
40.2
7668**
DCP
0112G-2
6.0
7706**
DCP
0248B-7
16.5
9195**
DCP
0020C-4
Unk
9388**
DCP
0860F
Unk
22,400**
DCP
0060
23.4
Unk
DCP
0060D-1
Unk
Unk
DCP
0060D-2
Unk
Unk
DCP
0060D-3
Unk
Unk
DCP
0060D-4
Unk
Unk
DCP
0060D-5
Unk
Unk
DCP
0060D-6
Unk
Unk
DCP
0060E-2
2.5
Unk
DCP
0112A-2
18.8
Unk
DCP
0112C-3
6.0
Unk
DCP
0112C-4
6.0
Unk
DCP
0432K-2
Unk
Unk
DCP
0432K-3
Unk
Unk
DCP
0432K-4
Unk
Unk
DCP
Unk: Unknown
**s Not used in "Average of the best" calculation
APPLIED FLOW RATE AVERAGES
Concentrates
Average of all sources 14.2 GPT
"Average of best" 14.2 GPT
Rinses
Average of all sources 3677 GPT
"Average of best" 1809 GPT
463
-------
TABLE X-12
ANALYSIS OF FLOW DATA
COMBINATION ACID PICKLING-CONTINUOUS
Plant
Code
Applied Flow Rate (GPT)
Scrubbers
Discharge Flow Rate (GPT)
Scrubbers
Bas:
0020C-1
20.8
20.8
DCP
0060D-5
50.4
Unk
DCP
0432K-3
63
63
DCP
02 84A-2
89
89
DCP
0432K-2
94
94
DCP
0060D-3
100
Unk
DCP
0020C-6
102
102
DCP
0284A-3
104
104
DCP
0432K-4
115
115
DCP
0020B-1
102
102
DCP
0020L-2
253
253
DCP
02560-3
268
0
DCP
0020L-1
272
272
DCP
0248B-9
309
40
DCP
0020C-5
329
329
DCP
072 4A-2
331
331
DCP
0020B-2
343
343
DCP
0248B-1
376
49
DCP
0648
400
0
DCP
0248B-5
403
53
DCP
0248B-10
446
58
DCP
0060D-6
511
Unk
DCP
0020C-4
561
561
DCP
02560-1
697
0
DCP
0248B-3
703
95
DCP
0112A-2
750
750
DCP
0248B-4
766
0
DCP
0060E-1
777
777
DCP
0948F
882
0
DCP
02560-2
941
0
DCP
0020C-8
1096
1096
DCP
0060D-2
1200
48
DCP
0176-4
1273
364**
DCP
0020C-2
1380
1380
DCP
0020C-3
1380
1380
DCP
0060E-2
1381
1381
DCP
02560-4
1532
0
DCP
0060D-1
1579
63
DCP
0248B-2
1702
230**
DCP
0248B-6
2344
188**
DCP
0176-3
3189
80
DCP
0176-5
7000**
400**
DCP
469
-------
TABLE X-12
ANALYSIS OF FLOW DATA
COMBINATION ACID PICKLING-CONTINUOUS
PAGE TWO
Plant Applied Flow Rate (GPT) Discharge Flow Rate (GPT)
Code Scrubbers Scrubbers Basis
0860F 11,520** 640** DCP
0060 Unk Unk DCP
0060D-4 Unk Unk DCP
0724A-1 Unk Unk DCP
**: Not used in "Average of the best" calculation
APPLIED FLOW RATE AVERAGES
Concentrates
Average of all sources 1113 GPT
"Average of best" 716 GPT
DISCHARGE FLOW RATE AVERAGES (All plants practicing flow reduction)
Scrubbers
Average of all sources 115 GPT
"Average of best" 47.8 GPT
470
-------
TABLE X-13
vj
I—1
Subdivision
Sulfuric Acid
-Batch
Sulfuric Acid
-Cont inuous
Hydrochloric Acid
-Batch
Hydrochloric Acid
-Continuous
Combination Acid
-Batch
Combination Acid
-Continuous
RAW WASTE LEVEL FLOW JUSTIFICATION
ACID PICKLING
Actual Applied Flow Rate (GPT)
Concentrates Rinses Scrubbers
15.6
19.9
7.2
8.4
14.1
14.2
327
213
538
295
517
1809
708
126
150
176
1136
716
Listed Values (GPT)
Concentrates
20
20
10
10
15
15
Rinses
330
200
540
300
520
1800
Scrubbers
710
130
150
180
1140
720
-------
TABLE X-14
ANALYSIS OF FLOW DATA
ABSORBER VENT SCRUBBER
Plant
Flow Rate (GPT)
Code
Scrubber
Basis
0584F
69
Sampled
W-2
98.6
Sampled
0528B
176
Samp led
0684F
376**
DCP
Y-2
624**
Sampled
**: Not used in "Average of the best" calculations.
SCRUBBER FLOW RATE AVERAGES
Average of all sources 269 GPT
"Average of the best" 115 GPT
472
-------
TABLE X-15
DEVELOPMENT OF BAT FLOW RATES
Treatment
Flow
(GPT)
Process
Level
Cone.
Rinse
FHS
AVS
Total
Sulfuric Acid
1. Batch
Raw
20
330
710
1060
Neutralization
BAT
Feed
20
330
10
360
BAT
20
50
0
70
2. Batch Acid
Raw
20
330
710
1060
Recovery
BAT
Feed
-
-
-
0
BAT
—
0
3. Continuous
Raw
20
220
130
370
Neutralization
BAT
Feed
20
220
10
250
BAT
20
35
0
55
4. Continuous Acid
Raw
20
220
130
370
Recovery
BAT
Feed
-
-
-
0
BAT
—
—
—
0
Hydrochloric Acid
1. Batch
Raw
10
540
150
700
Neutralization
BAT
Feed
10
540
10
560
BAT
10
80
0
90
2. Continuous
Raw
10
300
180
490
Neutralization
BAT
Feed
10
300
10
320
BAT
10
45
0
55
3. Continuous Acid
RAW
10
300
180
120
610
Regeneration
BAT
Feed
0
300
10
120
430
BAT
0
45
0
25
70
Combination Acid
1. Batch
Raw
15
520
1140
1675
BAT
Feed
15
520
10
545
BAT
15
80
10
105
2. Continuous
Raw
15
1800
720
2535
BAT
Feed
15
1800
50
1865
BAT
15
270
50
335
Cone: Concentrate
FHSs Fume Hood Scrubber
AVS: Absorber Vent Scrubber
473
-------
TABLE X-16
BAT EFFLUENT LIMITATIONS
ACID PICKLING SUBCATEGORY
Subdivision
Sulfuric
Process
BAT
Alternative
1 Batch -
Neutralization 1*
Discharge
Flow (GPT)
70
70
2. Batch Acid
Recovery
3. Continuous -
Neutralization
BPT
1*
55
55
Pollutants
Concentration
Basis (mg/1)
Effluent
Limitations (lbs/1000 lbs)
AVE.
MAX.
AVE
MAX
Chromium
0.10
0.30
0.0000292
0.0000876
Lead
0.10
0.30
0.0000292
0.0000876
Zinc
0.10
0.30
0.0000292
0.0000876
Chromium
0.10
0.30
0.0000292
0.0000876
Lead
0.10
0.30
0.0000292
0.0000876
Zinc
0.10
0.30
0.0000292
0.0000876
Chromium
_
_
-
_
Lead
-
-
-
Zinc
-
-
-
-
Chromium
0.10
0.30
0.0000230
0.0000690
Lead
0.10
0.30
0.0000230
0.0000690
Zinc
0.10
0.30
0.0000230
0.0000690
Chrom iura
0.10
0.30
0.0000230
0.0000690
Lead
0.10
0.30
0.0000230
0.0000690
Zinc
0.10
0.30
0.0000230
0.0000690
Chromium
-
-
-
-
Lead
-
-
-
-
Zinc
-
-
-
-
4. Continuous Acid BPT
Recovery
0
-------
TABLE X-16
BAT EFFLUENT LIMITATIONS
ACID PICKLING SUBCATEGORY
PAGE 2
BAT
Subdivision Process Alternative
Hydrochloric 1. Batch
Neutralization 1*
2
J) 2. Continuous 1*
Neutralisation
1
3. Continuous
Regeneration 1*
2
3
Discharge
Flow (CPT)
90
90
0
55
55
0
70
70
0
Concentration Effluent
Pollutants Basis (ag/1) Liaitations (lbs/1000 lba)
AVE. MAX. AVE MAX
Chroaiun 0.10 0.30
Lead 0.10 0.30
Zinc 0.10 0.30
Chroaiua 0.10 0.30
Lead 0.10 0.30
Zinc 0.10 0.30
0.0000375 0.000113
0.0000375 0.000113
0.0000375 0.000113
0.0000375 0.000113
0.0000375 0.000113
0.0000375 0.000113
Chroaiua
Lead
Zinc
Chroaiua
0.10
0.30
0.0000229
0.0000688
Lead
0.10
0.30
0.0000229
0.0000688
Zinc
0.10
0.30
0.0000229
0.0000688
Chroaiua
0.10
0.30
0.0600229
0.0000688
Lead
0.10
0.30
0.0000229
0.0000688
Zinc
0.10
0.30
0.0000229
0.0000688
Chroaiua
-
_
-
_
Lead
-
-
-
Zinc
-
-
-
Chroaiua 0.10 0.30 0.0000292 0.0000876
Lead 0.10 0.30 0.0000292 0.0000876
Zinc 0.10 0.30 0.0000292 0.0000876
Chroaiua
Lead
Zinc
0.10
0.10
0.10
0.30
0.30
0.30
0.0000292
0.0000292
0.0000292
0.0000876
0.0000876
0.0000876
Chroaiua
Lead
Zinc
-------
TABLE X-16
BAT EFFLUENT LIMITATIONS
ACID PICKLING SUBCATEGORY
PAGE 3
BAT Di acharge
Subdivision Procen Alternative Flow (GPT)
Combination 1. Batch 1* 105
2 105
3 0
2. Continuous 1* 345
2 345
3 0
Concentration Effluent
Pollutants Basis (¦»/!) Limitations (lbs/1000 lbs)
AVE. MAX. AVE MAX
Fluoride
15
45
0.00657
0.0197
Chroaiua
0.10
0.30
0.0000438
0.000131
Copper
0.10
0.30
0.0000438
0.000131
Nickel
0.20
0.45
0.0000876
0.000197
Fluoride
15
45
0.006571
0.0197
Chroaiua
0.10
0.30
0.0000438
0.000131
Copper
0.10
0.30
0.0000438
0.000131
Nickel
0.10
0.30
0.0000438
0.000131
Fluoride
-
-
-
Chroniua
-
-
-
-
Copper
-
-
-
-
Nickel
-
-
-
-
Fluoride
15
45
0.0216
0.0647
Chroaiua
0.10
0.30
0.000144
0.000432
Copper
0.10
0«30
0.000144
0.000432
Nickel
0.20
0.45
0.000288
0.000648
Fluoride
15
45
0.0216
0.0647
Chromium
0.10
0.30
0.000144
0.000432
Copper
0.10
0.30
0.000144
0.000432
Nickel
0.10
0.30
0.000144
0.000432
Fluoride
-
-
-
-
Chroaiua
-
-
-
-
Copper
-
-
-
-
Nickel
-
-
-
-
* : BAT Alternative selected.
Note: The fluoride load in codbination acid pickling is allotted only when hydrofluoric acid is used.
-------
rSPENT PICKLE1
I LIQUOR L_.
i EQUALIZATION i
1 TANK |
[" FUME HOOO~1
SCRUBBER
' SLOWDOWN 1
u ,
CASCADE
RINSE
L-«J-
LLIMEri r-, !
" i '''J
rPOLYMElTj
s^;
EQUALIZATION
TANK
T
I
aIr
BAT-I
BAT "2
SETTLING
SULFIDE
BAS N
FILTER
BAT" 3
EVAPORATION
100% RECYCLE
TO PROCESS
ENTRIFUGE
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
SULFURIC ACID PICKLING
BATCH 8 CONTINUOUS NEUTRALIZATION
BAT TREATMENT ALTERNATIVES
[Vm. 6/16/80
FIGURE X-l
-------
BAT-I
-J
CO
CASCADE
RINSE
SYSTEM
I
FUME HOOD
SCRUBBER
BLOWDOWN
ISPENT PiCKLEl
I LIQUOR I
EQUALIZATION
I TANK
1
r
±
ACID
EQUALIZATION
TANK
rJ-
ABSORBER
¦^—^^REGENERATION I »|VENT SCRUBBER)
UNIT(S)
|_ SLOWDOWN |
r
i
L
» POLYMER
V
"T
r-i
L THICKENER
BAT-2
SULFIDE
J , I
VACUUM f
•^FILTER |
AIR
FILTER
REACTION TANK
BAT-3
EVAPORATION
100% RECYCLE
TO PROCESS
CENTRIFUGE
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
HYDROCHLORIC ACID PICKLING
CONTINUOUS ACID REGENERATION
BAT TREATMENT ALTERNATIVES
Dwn.6/17/80
FIGURE X-2
-------
[spent pickle]
LIQUOR | »,
I EQUALIZATION I ,
I TANK J I
r FUME HOOD |
SCRUBBER I
; SLOWDOWN |
"X"
CASCADE
RINSE
EQUALIZATION
TANK
BAT-1
POLYMER |
1
in
I
I
I
r-l 1
j VACUUM ^
| FILTER |
I THICKENER
V
J
BAT-2
SULFIDE
REACTION TANK
BAT-3
100%
^RECYCLE
TO PROCESS
¦^•CENTRIFUGE
FILTER
EVAPORATION
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
HYDROCHLORIC ACID PICKLING
BATCH a CONTINUOUS NEUTRALIZATION
BAT TREATMENT ALTERNATIVES
Own. 6/16/80
FIGURE X-3
-------
J" FUME HOOD ~1
SCRUBBER
I BLOWDOWH J
[spent-pickTe"]
I LIQUOR I
I EQUALIZATION I
L TANK j
-i
I
I
[oip
i
oo
o
EQUALIZATION
TANK
BAT-I
LIMEJ J" p0LYMER 1
"T L. J
CLARIFIER
BAT-2
SULFIDE
1
VACUUM I
FILTER J
FILTER
REACTION TANK
BAT-3
EVAPORATION
100% RECYCLE
TO PROCESS
•"CENTRIFUGE
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
COMBINATION ACID PICKLING
BATCH 8 CONTINUOUS NEUTALIZATION
BAT TREATMENT ALTERNATIVES
Dwa 6/18/80
FIGURE x-4
-------
ACID PICKLING SUBCATEGORY
SECTION XI
BEST CONVENTIONAL POLLUTANT CONTROL TECHNOLOGY
Introduction
The 1977 Amendments added Section 301(b)(4)(E) to the Act,
establishing "best conventional pollutant control technology" (BCT)
for discharges of conventional pollutants from existing industrial
point sources. Conventional pollutants are those defined in Section
304(b)(4) - BOD, TSS, fecal coliform and pH - and any additional
pollutants defined by the Administrator as "conventional." On July
28, 1978, EPA proposed that COD, oil and grease, and phosphorus be
added to the conventional pollutant list (43 Fed. Reg. 32857). Only
oil and grease was added.
BCT is not an additional limitation, but replaces BAT for the control
of conventional pollutants. BCT requires that limitations for
conventional pollutants be assessed in light of a new
"cost-reasonableness" test, which involves a comparison of the cost
and level of reduction of conventional pollutants from the discharge
of POTWs to the cost and level of reduction of such pollutants from a
class or category of industrial sources. As part of its review of BAT
for certain "secondary" industries, EPA proposed methodology for this
cost test. (See 43 Fed. Reg. 37570, August 23, 1978).
Methodology
Reference is made to Volume I for a review of the BCT methodology.
BCT Treatment Alternatives
BCT treatment has not been considered for those sulfuric acid plants
practicing acid recovery. Zero discharge is attained at BPT by this
model. Therefore, further reduction of conventional pollutants is not
necessary. The proposed BCT limitations for sulfuric acid recovery
plants are the same as the proposed BPT limitations.
BCT Alternative No. T_
The BCT alternative treatment systems developed for the other
operations in the acid pickling subcategory are add-ons to the
respective BPT model treatment systems. The first BCT alternative is
identical to the BAT-1 developed in each subdivision. A cascade rinse
system is incorporated in this alternative to reduce the rinse flow
entering the treatment system. In the hydrochloric and sulfuric acid
subdivisions, the fume scrubber blowdown is fed to the cascade rinse
system. However, zero discharge from fume scrubbers at combination
acid pickling operations has not been demonstrated. Therefore, in the
combination acid pickling model, fume scrubber blowdown is not fed to
the cascade rinse system at the BCT level of treatment.
481
-------
BCT Alternative No. 2
The second BCT alternative treatment system passes the discharge flow
from the BCT-1 treatment system through a filter. Filtration
technology provides for additional removal of conventional pollutants
than that accomplished by sedimentation. The BCT alternative
treatment systems are depicted in Figures XI — 1 through XI-4.
Development of BCT Limitations
The reference POTW treatment cost for the conventional pollutants is
$1.34/lb (July 1, 1978). (See Section X of Volume I). The BCT cost
test is detailed in Section VIII with the results listed in Tables
VIII-43 through VIII-46 . A pass/fail summary of the BCT cost test
for the acid pickling subcategory follows:
BCT Cost Test
Results for the
BCT Alternatives
Subdivision 1 2
Sulfuric Acid - Batch Fail Fail
Neutralization
- Continuous Fail Fail
Neutralization
Hydrochloric Acid
- Acid Regneration Pass Pass*
- Batch Fail Fail
Neutralization
- Continuous Pass Pass*
Neutralization
Combination Acid
- Batch Fail Fail
- Continuous Fail Fail
~Selected as the BCT Alternative
The Agency is proposing BCT limitations for suspended solids, oil and
grease, and pH. However, the oil and grease limitations are
applicable only when acid pickling wastewaters are treated in
combination with cold rolling wastewaters. Reference is made to
Appendix A of Volume I for the derivation of performance standards for
suspended solids and oil and grease.
Proposed BCT Limitations
The proposed BCT limitations are presented in Table XI-1. Proposed
BCT limitations for those segments of the acid pickling subcategory
which did not pass the BCT Cost Test are the same as the proposed BPT
limitations. The proposed BCT limitations were calculated by
multiplying the effluent flow incorporated in the chosen treatment
model and the corresponding concentrations of suspended solids and oil
and grease, with appropriate conversion factors.
482
-------
TABLE XI-1
03
GO
BCT EFFLUENT LIMITATIONS GUIDELINES
ACID PICKLING SUBCATEGORY
Subdivision
Sulfuric Acid Pickling
1. Batch Neutralization
Total Suspended Solids
(lbs/1000 lbs)
Ave.
0.0751
2. Continuous Neutralization
(with spent pickle liquor) 0.0521
(without spent pickle liquor)0.0469
Hydrochloric Acid Pickling
1.
Batch Neutralization
(with scrubber)
(without scrubber)
0.0584
0.0480
2. Continuous Neutralization 0.00344
3. Continuous Acid Regeneration 0.00438
Combination Acid Pickling
1. Batch (Pipe and Tube) 0.0730
2. Batch (Other) 0.0209
3. Continuous 0.104
Max.
0.225
0.156
0.141
0.175
0.144
0.00917
0.0117
0.219
0.0627
0.312
Oil and Grease
(1)
(lbs/1000 lbs)
Ave.
0.0150
0.0104
0.00933
0.0117
0.00960
0.0292
0.00834
0.0417
Max.
0.0450
0.0312
0.0282
0.0351
0.0288
0.00229
0.00292
0.0876
0.0249
0.125
Model
Selected
BPT
BPT
BPT
BPT
BPT
BCT-2
BCT-2
BPT
BPT
BPT
(1) This load is allowed only when these wastes are treated in combination with
cold rolling mill wastes.
Note: pH is also limited in this subcategory at BCT to the range 6.0 to 9.0 standard units.
-------
["spent PICKLE 1
1 LIQUOR 1
I
I
L .
EQUALIZATION
TANK
I FUME HOOO I
SCRUBBER I
BLOWDOWN I
I
I
I
["lime! ["polymer")
*— 1 1 ' T 1
I
I
RINSE
1
EQUALIZATION
TANK j
Jll.
i
I C»kO
f"""
i
I
AIR
I
I
_ J
BCT-I
\. ;
SETTLING BASIN
BCT" 2
FILTER
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
SULFURIC ACID PICKLING
BATCH S CONTINUOUS NEUTRALIZATION
BCT TREATMENT ALTERNATIVES
Own. 11/25/80
FIGURE XI-
-------
4*-
00
Ul
BCT"
CASCAOE
RINSE
SYSTEM
FUME HOOD 1
SCRUBBER I
SLOWDOWN j
TSPENT PICKLE 1
I LIQUOR 1
, EQUALIZATION |
L TANK j
[lime1.
T
I
. POLYMER
1
EQUALIZATION
TANK J
+ -+4
I I
I
V
i-u,~
T
THICKENER J
I
I
AIR
T
i
ACID
TO +
REUSE
^ ACID ^
•H REGENERATION t- •
^ UNIT(S> J
| ¦* 1
'ABSORBER VENT1
H SCRUBBER |
BLOWDOWN j
I , VACUUM
U -1 ^
^FILTER
V
I
I
BCT- 2
FILTER
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
HYDROCHLORIC ACID PICKLING
CONTINUOUS ACID REGENERATION
BCT TREATMENT ALTERNATIVES
0wn.il/25/80
FIGURE XT-2
-------
00
-------
T FUME HOOO 1
l SCRUBBER
BLOWDOWN I
rsPent~pickle 1
LIQUOR I
EQUALIZATION
I
I
I
TANK
CASCADE
RINSE
OIL
T
t
l
jlime;
i
i
^polymer]
I
r
l-T ^
I EQUALIZATION
i TANK
BCT- I
I '
I -Je->
i zrL" i
! I
CLARIFIER s*
VACUUM ~j |
L FILTER J*
r
i
i
BCT "2
FILTER
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
COMBINATION ACID PICKLING
BATCH a CONTINUOUS NEUTRALIZATION
BCT TREATMENT ALTERNATIVES
Dwn.M/26/80
FIGURE 21-4
-------
ACID PICKLING SUBCATEGORY
SECTION XII
EFFLUENT QUALITY ATTAINABLE THROUGH
THE APPLICATION OF NEW SOURCE PERFORMANCE STANDARDS
Introduction
A new source is defined as any source constructed after the proposal
of New Source Performance Standards (NSPS). The effluent standards,
which must be achieved by new sources, are to specify the degree of
effluent reduction achievable through the application of the Best
Available Demonstrated Control Technology (BADCT), including, where
applicable, a standard permitting no discharge of pollutants. This
section identifies the treatment alternatives considered by the Agency
for NSPS and the resulting effluent standards for acid pickling
operations. In addition, the rationale for selecting the NSPS
treatment models, flow values, and proposed effluent standards are
discussed.
Identification of NSPS
Acid Recovery
NSPS for continuous and batch sulfuric acid pickling operations are
proposed at zero discharge. The alternative treatment systems which
achieve this level of reduction are identical to the continuous and
batch acid recovery BPT model treatment systems for sulfuric acid
pickling operations. Refer to Figure XII-1.
Two NSPS alternative treatment systems have been developed for
hydrochloric and combination acid pickling operations. Descriptions
of these alternatives follow. Refer to Figures XII-2 through XII-4
for illustrations of these model treatment systems.
NSPS Alternative No. ]_
The first NSPS alternative treatment systems are similar to the BPT
and BAT-1 treatment systems developed for the hydrochloric and
combination acid pickling subdivisions. For the batch and continuous
neutralization models in the hydrochloric acid subdivision, the NSPS-1
treatment system consists of spent acid equalization; fume scrubber
recycle with subsequent blowdown to the cascade rinse system;
equalization of spent pickle liquor and cascade rinsewaters;
neutralization with lime; flocculation with polymer; aeration;
clarification; and vacuum filtration of the clarifier underflow. The
batch and continuous neutralization model in the combination acid
pickling subdivision is identical to the corresponding model for
hydrochloric operations, except that aeration is not a treatment
system component. The NSPS-1 treatment system developed for
continuous hydrochloric acid regeneration operations incorporates all
of the treatment components just discussed. In addition, an acid
489
-------
regeneration unit and absorber vent scrubber recycle system are
included in the treatment system prior to the equalization unit.
NSPS Alternative No. 2
The second NSPS alternative treatment systems are similar to the
corresponding BPT and BAT-2 treatment systems developed for the
hydrochloric and combination acid pickling subdivisions. For the
batch and continuous neutralization models, in both subdivisions,
NSPS-2 treats the NSPS-1 system discharge by sulfide precipitation and
filtration. The NSPS-2 model developed for continuous hydrochloric
acid regeneration operations incorporates the NSPS-1 treatment systems
developed for these operations. In addition, the discharges from the
NSPS-1 systems are treated with sulfide and then filtered.
Rationale for NSPS
Alternative Treatment Systems
The NSPS alternative treatment systems developed for the acid pickling
subcategory are similar to the BPT, BAT-1, and BAT-2 treatment systems
described in Sections IX and X. Therefore, the rationale presented in
those sections is applicable to NSPS.
Flows
The applied and discharge flows developed for the zero discharge
sulfuric acid recovery model at NSPS are identical to the correspondng
model BPT flow values. Refer to Section IX. The applied and
discharge flows developed for the other NSPS treatment systems are
identical to the BAT-1 and BAT-2 raw and effluent flows developed for
operations in the hydrochloric acid subdivision. Refer to Section X
for the development of these flow values. In the combination acid
pickling subdivision, the raw concentrate and fume hood scrubber flows
are identical to those developed at BAT (see Section X). However, the
raw rinse flows have been lowered from those used in the BAT model.
In the batch NSPS system, the raw rinse flow is 200 GPT as compared to
520 GPT at BAT. In the continuous NSPS system, the raw rinse flow is
500 GPT in comparison with the value of 1800 GPT incorporated in the
BAT system. Applied flows for combination acid pickling operations
were lowered to the Best Demonstrated Flows for NSPS. Flows for
sulfuric and hydrochloric acid plants were not lowered at NSPS.
However, the Agency is soliciting comments on the use of best
demonstrated flows for NSPS in these subdivisions.
Selection of NSPS Alternative
The acid recovery model, which achieves zero discharge, has been
chosen for batch and continuous sulfuric acid pickling operations.
NSPS Alternative No. 1 has been selected as the model treatment system
upon which the proposed NSPS effluent standards are based for all
hydrochloric and combination acid pickling operations. The Agency
selected the first alternative rather than the second, because the
sulfide precipitation technology included in the second alternative
has not been demostrated in this subcategory.
490
-------
The proposed NSPS effluent standards are presented in Table XII-1.
The NSPS model treatment systems are designated by asterisks.
491
-------
TABLE XI1-1
NEW 90URCE PERFORMANCE STANDARDS
ACID PICKLING SUBCATEGORY
Subdivision
Sulfuric
Hydrochloric
ID
K>
Concentration Basis
Effluent Standards
Discharge
lmg/1)
(lb/1000 lb
Process
NSPS Alternative
Flow (GPT)
Pollutant
Ave.
Max.
Ave.
Max.
Batch
1*
0
Continuous
1*
0
Batch
1*
90
TSS
30
60
0.0113
0.0225
Neutralization
O&G
10
20
0.00375
0.00750
Chromium
0.10
0.30
0.0000375
0.000113
Lead
0.10
0.30
0.0000375
0.000113
Zinc
0.10
0.30
0.0000375
0.000113
pH, Units
6.0 to
9.0
2
90
TSS
15
40
0.00563
0.0150
OSG
-
10
-
0.00375
Chr onion
0.10
0.30
0.0000375
0.000113
Lead
0.10
0.30
0.0000375
0.000113
Zinc
0.1O
0.30
0.0000375
0.000113
pH, Units
6.0 to
9.0
Continuous
1*
55
TSS
30
60
0.00688
0.0138
Neutral!xation
OtrG
10
20
0.00229
0.00458
Chromium
0.10
0.30
0.0000229
0.00006B7
Lead
0.10
0.30
0.0000229
0.0000687
Zinc
0.10
0.30
0.0000229
0.0000687
pH, Units
6.0 to
9.0
2
55
TSS
15
40
0.00344
0.00917
O&G
-
10
-
0.00229
Chroaiian
0.10
0.30
0.0000229
0.0000687
Lead
0.10
0.30
0.0000229
0.0000687
Zinc
0.10
0.30
0.0000229
0.0000687
pH, Units
6.0 to
9.0
Continuous
1*
70
TSS
30
60
0.00876
0.0175
Acid
OtG
10
20
0.00292
0.00584
Regeneration
Chrcmlum
0.10
0.30
0.0000292
0.0000876
Lead
0.10
0.30
0.0000292
0.0000876
Zinc
0.10
0.30
0.0000292
0.0000876
pH, Units
6.0 to
9.0
-------
TABLE XII-1
NEW SOURCE PERFORMANCE STANDARDS
ACID PICKLING SUBCATEGORY
PAGE TWO
Concentration Basis Effluent Standards
Subdivision
Process
USPS Alternative
Discharge
Flow (GPT)
70
Combination
Batch
45
10
u>
45
Continuous
1«
90
90
Pollutant
Ave.
Max.
Ave.
Max.
TSS
15
40
0.00438
0.0117
OtG
-
10
-
0.00292
Chroaiua
0.10
0.30
0.0000292
0.0000876
Lead
0.10
0.30
0.0000292
0.0000876
Zinc
0.10
0.30
0.0000292
0.0000876
pH, Units
6.0 to
9.0
TSS
30
60
0.00563
0.0113
OtG
10
20
0.00188
0.00376
Fluoride
15
45
0.00281
0.00844
ChroHiia*
0.10
0.30
0.0000188
0.0000564
Copper
0.10
0.30
0.0000188
0.0000564
Nickel
0.20
0.45
0.0000375
0.0000844
pH, Units
6.0 to
9.0
TSS
15
40
0.00281
0.00751
OtG
-
10
-
0.00188
Fluoride
15
45
0.00281
0.00844
Chroaiua
0.10
0.30
0.0000188
0.0000564
Copper
0.10
0.30
0.0000188
0.0000564
Nickel
0.10
0.30
0.0000188
0.0000564
pH, Units
6.0 to
9.0
TSS
30
60
0.0113
0.0225
OtG
10
20
0.00375
0.00750
Fluoride
15
45
0.00563
0.0169
Chroaiua
0.10
0.30
0.0000375
0.000113
Copper
0.10
0.30
0.0000375
0.000113
Nickel
0.20
0.45
0.0000751
0.000169
pH, Units
6.0 to
9.0
TSS
15
40
0.00563
0.0150
OtG
-
10
-
0.00375
Fluoride
15
45
0.00563
0.0169
Chroaiua
0.10
0.30
0.0000375
0.000113
Copper
0.10
0.30
0.0000375
0.000113
Nickel
0.10
0.30
0.0000375
0.000113
pH, Units
6.0 to
9.0
*t Alternative selected.
Hotei The fluoride load Is allowed only when hydrofluoric acid is used.
-------
Spent
Pfckle
Liquor
CRYSTA LLIZER
FUME HOOD
SCRUBBER
BLOWDOWNS
CRYSTAL
COLLECTOR
CASCADE
RINSE
PICKLE
TANK(S)
RECOVERED
ACID TANK
FERROUS SULFATE
HEPTAHYDRATE CRYSTALS
Recovered Acid
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
SULFURIC ACID PICKLING
CONTINUOUS 8 BATCH OPERATIONS
NSPS TREATMENT MODEL
Dwn.6/12/80
FIGIJRF "XTT-I
-------
CASCADE
RINSE
SYSTEM
FUME HOOD
SCRUBBER
BLOWDOWN
SPENT PICKLE
LIQUOR
EQUALIZATION
TANK
REUSE
ACID
REGENERATION
UNIT(S)
POLYMER
NSPS- I
CLARIFIER
NSPS"2
EQUALIZATION
TANK
SULFIDE
VACUUM
FILTER
REACTION TANK
FILTER
ABSORBER
VENT
SCRUBBER
BLOWDOWN
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
HYDROCHLORIC ACID PICKLING
CONTINUOUS ACID REGENERATION
NSPS TREATMENT ALTERNATIVES
Dwn.6/18/80
FIGURE 211-2
-------
EQUALIZATION
TANK
FUME HOOD
SCRUBBER
SLOWDOWN
SPENT PICKLE
LIQUOR
EQUALIZATION
TANK
CASCADE
RINSE
SYSTEM
LIME
NSPS ~I
NSPS-2
CLARIFIER
SULFIDE
AIR
REACTION TANK
POLYMER
VACUUM
FILTER
FILTER
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
HYDROCHLORIC ACID PICKLING
BATCH S CONTINUOUS NEUTRALIZATION
NSPS TREATMENT ALTERNATIVES
Dwn. 6/18/80
FIGURE XK-3
-------
|LIMEl | POLYMER
EQUALIZATION
TANK
SPENT PICKLE
LIQUOR
EQUALIZATION
TANK
CASCADE
RINSE
FUME HOOD
SCRUBBER
SLOWDOWN
NSPS"I
CLARIFIER
NSPS"2
SULFIDE
VACUUM
FILTER
REACTION TANK
FILTER
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
COMBINATION ACID PICKLING
BATCH a CONTINUOUS NEUTRALIZATION
NSPS TREATMENT ALTERNATIVES
Own, 11/21/80
FIGURE UL-4
-------
ACID PICKLING SUBCATEGORY
SECTION XIII
PRETREATMENT STANDARDS FOR DISCHARGES
TO PUBLICLY OWNED TREATMENT WORKS
Introduction
This section discusses the alternative control and treatment systems
available for acid pickling operations which discharge wastewaters to
publicly owned treatment works (POTWs). The main factors considered
in the pretreatment standards are: (1) the need to ensure that the
acid pickling wastewaters are treated sufficiently to avoid
overloading POTW systems, and (2) that provisions for toxic pollutant
removal are incorporated such that these pollutants do not interfere
with or pass through the POTW, or are not otherwise incompatible with
POTW operations.
The Agency developed separate pretreatment systems for existing (PSES)
and new (PSNS) operations in the sulfuric and combination acid
pickling subdivisions. However, in the hydrochloric acid pickling
subdivision, PSES and PSNS systems are identical.
General Pretreatment Regulations, 40 CFR Part 403, are applicable to
all acid pickling sources. A discussion of the general pretreatment
and categorical pretreatment standards applying to acid pickling
operations follow.
General Pretreatment Standards
For detailed information concerning Pretreatment Standards, refer to
43 FR 27736-27773, "General Pretreatment Regulations for Existing and
New Sources of Pollution," (June 26, 1978). In particular, 40 CFR
Part 403 describes national standards (prohibited discharges and
categorical standards), revision of categorical standards through
removal allowances, and POTW pretreatment programs.
The General Pretreatment Regulations set forth general discharge
prohibitions that apply to all non-domestic users of POTWs to prevent
pass through of pollutants, interference with the operation of POTWs,
and municipal sludge contamination. The regulations also establish
administrative mechanisms to ensure application and enforcement of
prohibited discharge limits and categorical pretreatment standards.
In addition, the Regulations contain provisions relating directly to
the determination of and reporting on Pretreatment Standards.
Categorical Pretreatment Standards
In establishing pretreatment standards for acid pickling operations,
the Agency gave primary consideration to the objectives and
requirements of the General Pretreatment Regulations. In addition,
499
-------
the Agency considered other factors specifically appl icable to acid
pickling operations.
Although wastewaters from a significant number of pickling operations
are discharged to POTWs, the POTWs are not designed to treat toxic
metal pollutants present in pickling wastewaters. Instead, POTWs are
designed to treat biochemical oxygen demand (BOD) / total suspended solids
(TSS), fecal coliform bacteria,"and pH. Toxic metal removal by POTWs
is incidental to the POTW's main function of treating conventional
pollutants. POTWs have historically accepted many pollutants in
amounts well above their capacity to treat them adequately. The
problems of municipal sludge disposal are becoming increasingly
difficult to resolve. Pretreatment standards must address toxic
pollutant removal. This will greatly reduce the transfer of these
pollutants to POTWs where they concentrate in the sludges.
Due to the presence of toxic metal pollutants in pickling wastewaters,
extensive pretreatment must be provided to ensure that these
pollutants do not interfere with or pass through the POTWs, or are not
otherwise incompatible with POTW operations or cause harm to the
treatment plant. In general, the alternative treatment systems are
comparable to the BAT alternative treatment systems. Pretreatment
standards for suspended solids and oil and grease are not proposed.
These pollutants, in the amounts present in acid pickling BPT
effluents, are compatible with POTW operations and can be effectively
treated at POTWs.
Various studies1 have demonstrated that the toxic metal pollutants
found in wastewaters at levels comparable to those present in pickling
wastewaters inhibit the biological treatment process. The
pretreatment systems ensure that the toxic metal pollutants present in
the pickling wastewater discharges of these segments will not
adversely affect the treatment process.
Other studies2 involving the electroplating industry (with similar
levels of the same toxic metals) indicated that from fifty percent to
ninety percent of the toxic metal pollutants entering a POTW will pass
through the system. The possiblity therefore exists that a POTW could
discharge undesirable levels of toxic metal pollutants when accepting
industrial process wastewaters.
The toxic metal pollutants which do not pass through a POTW are
concentrated in the POTW sludges. Generally, land application is the
most advantageous, yet least expensive, method of POTW sludge disposal
as the sludge can be used to replace soil nutrients. However,
excessive amounts of toxic metal pollutants in the sludges could
lEPA-430/9-76-017a, Construction Grants Program Information; Federal
Guidelines, State and Local Pretreatment Programs
2Federal Register; Friday, September 7, 1979; Part IV, Environmental
Protection Agency; Effluent Guidelines and Standards; Electroplating
Point Source Category; ' Pretreatment Standards for Existing
Sources-Pages 52597-52601.
500
-------
inhibit plant growth, thus rendering the sludge unfit for use as a
soil nutrient supplement. In addition, these metals could enter
either the plant or animal food chain or could leach into the
groundwater. For the above reasons, the Agency believes that the
control of toxic metal pollutant discharges to POTWs is essential.
Rationale for Selection of Pretreatment Systems
Treatment Models
The PSES and PSNS systems developed for the acid pickling subcategory
are similar to BPT, BAT-1, and BAT-2 treatment systems described in
Sections IX and X. Therefore, the rationale presented in those
sections is applicable to PSES and PSNS.
Flows
The applied and discharge flows developed for the PSES and PSNS
systems are identical to the BAT-1 and BAT-2 raw and effluent flows
for hydrochloric neutralization operations and hydrochloric acid
regeneration operations. The applied and discharge flows developed
for sulfuric acid recovery operations at PSES and PSNS are identical
to the corresponding BPT flows, as are the PSNS flows for sulfuric
neutralization operations. PSES flows for sulfuric neutralization
operations refect BAT flow values. Refer to Sections IX and X for the
development of these flow values.
In the combination acid pickling subdivision, the applied and
discharge flow values developed for the PSES alternatives are
identical to the corresponding BAT-1 and BAT-2 applied and discharge
flow values. Refer to Section X. However, the flow values developed
for the PSNS alternative system are identical to the corresponding
NSPS applied and discharge flow values. Refer to Section XII for the
development of these flow values.
Alternative Pretreatment Systems
A. Sulfuric Acid Pickling
1. PSES
The PSES system developed for sulfuric acid recovery
operations is identical to the model BPT treatment system.
Refer to Figure XIII-1. The two PSES systems developed for
sulfuric acid neutralization operations are similar to the
corresponding BPT, BAT-1, and BAT-2 treatment systems. PSES
Alternative No. 1 consists of spent acid equalization; fume
scrubber recycle with subsequent blowdown to the cascade
rinse system; equalization of spent pickle liquor and
cascade rinsewaters; neutralization with lime; flocculation
with polymer; aeration; clarification; and, vacuum
filtration of the clarifier underflow. The filtrate from
the vacuum filters is returned to the clarifier inlet. The
clarifier overflow is then discharged to the POTW. PSES
Alternative No. 2 incorporates all of the Alternative No. 1
501
-------
treatment components just discussed. In addition, the
clarifier overflow is treated with sulfide in a reaction
tank. The solids precipitated by the sulfide are removed by
filters and the filter effluent is then discharged to a
POTW. Figure XIII-2 depicts the treatment models just
described.
2. PSNS
The PSNS treatment model developed for all sulfuric acid
pickling operations is identical to the NSPS model treatment
system for sulfuric operations. This treatment system
achieves zero discharge. Refer to Figure X111 — 1.
B. Hydrochloric Acid Pickling
1. Acid Regeneration
The PSES/PSNS systems developed for hydrochloric acid
regeneration operations include all of the PSES-1 and PSES-2
system components developed for sulfuric acid neutralization
operations. In addition, an acid regeneration unit and
absorber vent scrubber recycle system are included prior to
the equalization unit in each treatment system. Refer to
Figure XIII-3.
2. Neutralization
The PSES/PSNS treatment systems developed for hydrochloric
acid neutralization operations are identical to the
corresponding PSES Alternatives No. 1 and 2 developed for
sulfuric acid neutralization operations. Refer to Figure
XII1-4.
C. Combination Acid Pickling
1. PSES
The two PSES systems developed for combination acid
neutralization operations both include fume hood scrubber
recycle; cascade rinse; equalization of spent pickle liquor,
fume hood scrubber blowdown, and cascade rinse system;
neutralization with lime, and flocculation with polymer. At
this point, the PSES Alternative No. 1 treatment system flow
passes through a clarifier. The clarifier underflow is
vacuum filtered with the filtrate returned to the clarifier
inlet. The clarifier overflow then enters the POTW. In the
PSES Alternative No. 2 treatment system, the wastewater
which has been neutralized with lime and flocculated with
polymer then passes to a settling basin. Sludge is removed
periodically, and after sufficient retention time, the
wastewater is treated with sulfide in a reaction tank. The
solids which have been precipitated are removed by filters.
The filter effluent then passes to the POTW. Figure XIII-5
depicts the treatment systems just described.
502
-------
2. PSNS
The PSNS systems developed for combination acid
neutralization operations incorporate all of the PSES-1 and
PSES-2 treatment components developed for sulfuric aci4
neutralization operations, with the exception of aeration.
Refer to Figure XIII-6.
Selection for Pretreatment Alternatives
The acid recovery system, which achieves zero discharge, has been
developed for new batch and continuous sulfuric acid pickling
operations (PSNS). This system also applies to existing batch and
continuous sulfuric acid recovery operations.
The PSES-1 alternative has been selected as the model treatment systen
upon which the proposed PSES effluent standards are based for sulfuric
and hydrochloric neutralization operations and hydrochloric aci4
regeneration operations. The PSNS models for the two types of
hydrochloric acid pickling operations are identical to the
corresponding PSES models.
The first PSES and PSNS alternatives have also been selected as the
model treatment systems upon which the proposed PSES and PSNS effluent
standards are based for combination neutralization operations. The
Agency selected the first alternatives for operations in all three
subdivisions, because the sulfide precipitation technology
incorporated in the second alternatives has not been demonstrated in
this subcategory.
The proposed PSES and PSNS effluent standards are presented in Table
XIII—1. The selected PSES and PSNS alternatives are designated by
asterisks. No effluent standards are proposed for suspended solids
and oil and grease, as these are conventional pollutants which can be
effectively treated in a POTW.
503
-------
TABLE XIII-1
PRBIHEMMENT OTLDENT STANDARDS (EXISTING AND NEW SOURCES)
ACID PICKLING SUBCATEGORY
Subdivision Process
Sulfuric
Batch
Pretreataent
Alternative
PSES-1*
Flow
Baaia (GPT) Pollutants
Concentration
Basis (nq/1)
Ave. Max.
Effluent Standards
(lbs/1000 lbs)
Ave.
PSES-2
70
70
U1
o
Hydrochloric
Batch
Neutralization
Chroaiua
Lead
Zinc
pa (Units)
Chroaiua
Lead
0.10
0.10
0.10
0.10
0.10
0.30 0.0000292
0.30 0.0000292
0.30 0.0000292
6.0 to 9.0
0.30
0.30
0.0000292
0.0000292
Zinc
pH (Units)
0.10
0.30
6.0 -
9.0
0.0000292
PSNS*
0
-
-
-
PSES-1*
55
Chroaiua
Lead
Zinc
pH (Units)
0.10
0.10
0.10
0.30
0.30
0.30
6.0 -
9.0
0.0000229
0.0000229
0.0000229
PSES-2
55
Chroniua
Lead
Zinc
pB (Units)
0.10
0.10
0.10
0.30
0.30
0.30
6.0 -
9.0
0.0000229
0.0000229
0.0000229
PSNS*
0
-
-
-
PSES/PSNS-1*
90
Chroaiua
Lead
Zinc
pH (Units)
0.10
0.10
0.10
0.30
0.30
0.30
6.0 -
9.0
0.0000375
0.0000375
0.0000375
PSES/PSNS-2
90
Chroaiua
Lead
Zinc
pB (Units)
0.10
0.10
0.10
0.30
0.30
0.30
6.0 -
9.0
0.0000375
0.0000375
0.0000375
Max.
0.0000876
0.0000676
0.0000876
0.0000876
0.0000876
0.0000876
0.0000688
0.0000688
0.0000688
0.0000688
0.0000686
0.0000686
0.000113
0.000113
0.000113
0.000113
0.000113
0.000113
-------
TABLE XIII-1
PRE TREATMENT EFFLUEHT STANDARDS (EXISTING AND NEW SOURCES)
ACID PICKLING SUBCATEGORY
PAGE TWO
Subdivision Process
Pretreataent
A1 tentative
Flow
Basis (GPT)
Conti nuoui
Neutralization
PSES/PSNS-1*
55
PSES/PSNS-2
55
Coati ntious
Acid
Regeneration
PSES/PSNS-1*
70
m
O
cn
PSES/PSNS-2
70
Cfiabination
Batch
PSES-1*
105
PSKS-2
105
PSNS-1*
45
PSNS-2
45
Concentration
Basis (mg/1)
Effluent Standards
(lbs/1000 lbs)
Pollutants
Ave;
Max.
Ave.
Max.
Chroaita
Lead
Zinc
pH (Units)
0.10
0.10
0.10
0.30
0.30
0.30
6.0 -
9.0
0.0000229
0.0000229
0.0000229
0.0000687
0.0000687
0.0000687
Chroaiua
Lead
Zinc
pH (Units)
0.10
0.10
0.10
0.30
0.30
0.30
6.0 -
9.0
0.0000229
0.0000229
0.0000229
0.0000687
0.0000687
0.0000687
Chroaiua
Lead
Zinc
pH (Units)
0.10
0.10
0.10
0.30
0.30
0.30
6.0 -
9.0
0.0000292
0.0000292
0.0000292
0.0000876
0.0000876
0.0000876
Chroaiua
Lead
Zinc
pR (Units)
0.10
0.10
0.10
0.30
0.30
0.30
6.0 -
9.0
0.0000292
0.0000292
0.0000292
0.0000876
0.0000876
0.0000876
Chroaiua
Copper
Nickel
p>H (Units)
0.10
0.10
0.20
0.30
0.30
0.45
6.0 -
9.0
0.0000438
0.0000438
0.0000876
0.000131
0.000131
0.000197
Chroaiua
Copper
Nickel
pH (Units)
0.10
0.10
0.10
0.30
0.30
0.30
6.0 -
9.0
0.0000438
0.0000438
0.0000438
0.000131
0.000131
0.000131
Chroaiua
Copper
Nickel
pH (Units)
0.10
0.10
0.20
0.30
0.30
0.45
6.0 -
9.0
0.0000188
0.0000188
0.0000375
0.0000563
0.0000563
0.0000844
Chroaiua
Copper
Nickel
pH (Units)
0.10
0.10
0.10
0.30
0.30
0.30
6.0 -
9.0
0.0000188
0.0000188
0.0000188
0.0000563
0.0000563
0.0000563
-------
TABLE XIII-1
PRETREATMENT EFFLUENT STANDARDS (EXISTING AND NEW SOURCES)
ACID PICKLING SUBCATEGORY
PAGE THREE
Pretreatnent Flow
Subdivision Process Alternative Baals (GPT)
Continuous PSES-1* 345
PSES-2 345
PSNS-1* 90
Ul
o
PSNS-2 90
*i Alternative selected
Concentration
Basis
to/1).
Pollutants
Ave.
Max.
Chroaiua
0.10
0.30
Copper
0.10
0.30
Nickel
0.20
0.45
pa (Units)
6.0 -
Chroalua
0.10
0.30
Copper
0.10
0.30
Nickel
0.10
0.30
pfl (Units)
6.0 -
Chroaiua
0.10
0.30
Copper
0.10
0.30
Nickel
0.20
0.45
pH (Units)
6.0 -
Chroaiua
0.10
0.30
Copper
0.10
0.30
Nickel
0.10
0.30
pB (Units)
6.0 -
Effluent Standards
(lbs/1000 lbs)
9.0
9.0
Ave.
0.000144
0.000144
0.000288
0.000144
0.000144
0.000144
0.0000375
0.0000375
0.0000751
0.0000375
0.0000375
0.0000375
Max.
0.000431
0.000431
0.000647
0.000431
0.000431
0.000431
0.000113
0.000113
0.000169
0.000113
0.000113
0.000113
-------
FUME HOOD
SCRUBBER
SLOWDOWNS
CASCADE
RINSE
PICKLE
TANK(S>
-Cool to I0"C(50° F)
CRYSTA LLIZER
o»o
CRYSTAL
COLLECTOR
tfMtlWIftlfil.
RtCOVERED
ACID TANK
—/ FERROUS SULFATE
/ MEPTAHYDRATE CRYSTALS
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
SULFURIC ACID PICKLING
CONTINUOUS 8 BATCH OPERATIONS
PSNS TREATMENT MODEL
Dwa II/22/BO
FIGURE 2DI-
-------
U1
o
oo
PSES-)
PSES-2
CLARIFIER
SULFIDE
EQUALIZATION
TANK
AIR
REACTION TANK
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
SULFURIC ACID PICKLING
BATCH ft CONTINUOUS NEUTRALIZATION
PSES TREATMENT ALTERNATIVES
LIME
POLYMER
VACUUM
FILTER
FILTER
FUME HOOD
SCRUBBER
BLOWDOWN
SPENT PICKLE
LIQUOR
EQUALIZATION
TANK
CASCADE
RINSE
-------
EQUALIZATION
TANK
ACID TO
REUSE
CASCADE
RINSE
SYSTEM
SPENT PICKLE
LIQUOR
EQUALIZATION
TANK
FUME HOOD
SCRUBBER
SLOWDOWN
ACID
REGENERATION
ABSORBER
VENT SCRUBBER
SLOWDOWN
LIME
POLYMER
PSES/PSNS - I
PSES/PSNS-2
CLARIFIER
SULFIDE
FILTER
AIR
VACUUM
FILTER
REACTION TANK
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
HYDROCHLORIC ACID PICKLING
CONTINUOUS ACID REGENERATION
PSES/PSNS TREATMENT ALTERNATIVES
Dwn.6/20/8C
FIGURE Xm-3
-------
-^HJYTiCKOT
LIQUOR
EQUALIZATION
TANK
I LIMEl | POLYMER
FUME HOOD
\1
SCRUBBER
SLOWDOWN
CASCADE
RINSE
EQUALIZAT ON
TANK
AIR
CLARIFIER
VACUUM
FILTER
PSES/PSNS ~ I
PSES/PSNS'2
SULFIDE
FILTER
REACTION TANK
ENVIRONMENTAL PROTECTION A6ENCY
STEEL INDUSTRY STUDY
HYOROCHLORIC ACID PICKLING
BATCH a CONTINUOUS NEUTRALIZATION
PSES/PSNS TREATMENT ALTERNATIVES
On* II/22/8C
FIGURE 201-4
-------
SPENT PICKLE
LIQUOR
EQUALIZATION
TANK
FUME HOOD
SCRUBBER
BLOWDOWN
| POLYMER
1
EQUALIZATION
TANK
CASCADE
RINSE
PSES- I
CLARIFIER
VACUUM
FILTER
PSES * 2
SULFIDE
FILTER
SETTLING BASIN
REACTION TANK
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
COMBINATION ACID PICKLING
BATCH a CONTINUOUS NEUTRALIZATION
PSES TREATMENT ALTERNATIVES
Dwn. 11/24/80
FIGURE 2m-5
-------
LIME] 1 POLYMER
EQUALIZATION
TANK
SPENT PICKLE
LIQUOR
EQUALIZATION
TANK
FUME HOOD
SCRUBBER
BLOW DOWN
CASCADE
RINSE
PSNS " I
CLARIFIER
VACUUM
FILTER
PSNS ~ 2
SULFIDE
FILTER
REACTION TANK
ENVIRONMENTAL PROTECTION AGENCY
STEEL INDUSTRY STUDY
COMBINATION ACID PICKLING
BATCH 8 CONTINUOUS NEUTRALIZATION
PSNS TREATMENT ALTERNATIVES
Dwn.il/25/60
FIGURE ZEI-6
-------