mineral recovery
from the noncombustible fraction
of municipal solid waste
i current^^^^H
jport a current re
•ent report a curr
t a current report
a current report /
I on solid waste management 3 C *
jnt report a currer
current report a c
urrent report a cu
report a current /
""t report
*>r

-------
An environmental protection publication in the solid waste management
series (SW-82d.l). Mention of commercial products does not constitute
endorsement by the U.S. Government. Editing and technical content of
this report are the responsibility of the Resource Recovery Division,
Office of Solid Waste Management Programs.
Single copies of this publication are available from Solid Waste
Information, U.S. Environmental Protection Agency, Cincinnati, Ohio 45268.

-------
MINERAL RECOVERY FROM THE NONCOMBUSTIBLE FRACTION
OF MUNICIPAL SOLID WASTE
A Proposed Project To Demonstrate
Incinerator Residue Recovery
This report (SW-82d.l) was written
by DAVID G. ARELLA and YVONNE M. GARBE
on work performed under Federal solid
waste management demonstration grant No. S-801535
that was awarded to the City of Lowell, Massachusetts,
in October 1972, and cancelled at the request of the
grantee in July 1975.
U.S. ENVIRONMENTAL PROTECTION AGENCY
1975

-------
FOREWORD
In July 1975, shortly after this report was written, steps were
initiated to cancel a grant that had been awarded to the City of Lowell,
Massachusetts, to demonstrate mineral recovery from incinerator residue.
The decision to cancel the grant resulted primarily from two unresolvable
problems, which did not include the technical or economic viability of
the recovery process itself.
First, the City of Lowell was obligated to upgrade its incinerator
in order to conform with Federal air pollution standards, as well as to
meet the requirements of the grant. These upgrading costs were esti-
mated at more than $5 million, far more than originally anticipated.
This amount exceeded both the original cost of the incinerator and the
cost of the resource recovery facility and, therefore, was considered
prohibitive.
Second, there was insufficient incinerator residue to process in
the resource recovery plant. Originally, the Lowell incinerator would
have provided half the volume of residue needed to operate the plant one
full 8-hour shift. Additional residue from incinerators operating in
nearby communities would have been brought in to supplement the volume.
Unfortunately, in 1973 and 1974, several of these communities closed
their incinerators because of noncompliance with Federal air pollution
standards, thus, creating the problem of insufficient residue volume.
There was another, less significant, cost increase in the project.
The estimated cost of the proposed resource recovery plant increased by
$2,034 million from 1972 to 1975, due to inflation and modifications of
the plant design. These increased costs are reflected in the economic
analysis of the project in this report, and it should be noted that, in
spite of these increases, the process remains economically attractive.
The grant cancellation should not be interpreted as a change in EPA
or Lowell attitude about the economic or technical feasibility of the
incinerator residue recovery system.
This report is published to document the valuable work completed on
this project before termination.
-SHELDON MEYERS
Deputy Assistant Administrator
for Solid Waste Management
iii

-------
MINERAL RECOVERY FROM THE NONCOMBUSTIBLE FRACTION
OF MUNICIPAL SOLID WASTES
Concern for environmental quality has grown dramatically in recent
years, and solid waste management has attracted particular attention for
three reasons.
First, we now realize that our discards contain significant quantities
of valuable materials. Reuse of these materials can make significant
contributions towards reducing the drain of our natural resources,
forestalling material shortages, and improving the Nation's material
trade balance.
Secondly, recent studies by the U.S. Environmental Protection
Agency (EPA) indicate that manufacturing processes which use recycled
materials, instead of virgin materials, generally produce less air and
water pollution and require less energy. With rising energy costs and
increasingly stringent environmental regulations, the use of recycled
materials may soon be cheaper in many cases than the use of virgin
materials.
Finally, we have begun to understand more clearly the necessity to
protect our lands and waterways from improper waste disposal techniques.
Evolving environmental regulations will improve the quality of our solid
waste disposal activities; the cheap, open burning dump will be outlawed,
but the costs of handling our wastes satisfactorily will increase
accordingly.
The concept of recovering resources from our wastes was spawned by
these factors and, in fact, offers a partial solution to all three.
Solid waste management systems which recover resources can reduce
material and energy shortages as well as offer a means of disposal which
is both cost competitive and environmentally satisfactory.
Therefore, the challenge is to develop technically and economically
viable systems for extracting resources from our wastes and reintroducing
them into the production cycle. The Solid Waste Disposal Act as amended
(Public Law 91-512) is evidence of this maturation in our materials use
policies. This act authorizes the Federal Government to aid in the
development and demonstration of systems which would recover material
and energy resources from solid wastes. Demonstrations of technology
are supported by Federal funds which absorb most of the risks in implementing
prototype plants. The payoff for the demonstration grant program is
a duplication of these concepts, once demonstrated to be technically
and economically feasible, in other locations without further Federal
financial participation. Demonstration grants have proven to be effective
tools for stimulating the implementation of new technologies. This
report describes one of the projects that had been selected for funding,
although under this Act it has since been cancelled (see Foreword): the
recovery of minerals from the noncombustible fraction of solid wastes.

-------
The original concepts were developed and pilot-tested by the U.S.
Bureau of Mines (USBM). This work was the basis for an application from
the City of Lowell, Massachusetts, to demonstrate a system for recovering
iron, aluminum, copper, and glass from the residues left after incineration
of municipal solid waste. The project included the design, construction,
and evaluation of a large system to handle 250 tons per 8 hours a
day of incinerator residue. The project was to be implemented in order
to hasten the advancement of resource recovery by shortening the gap
between research and full-scale implementation. Cost escalations and
the need to upgrade the incinerator to meet air pollution regulations
led to the cancellation of the project.
Project Objectives
The first objective of this project was to demonstrate the technical
and economic feasibility of a mechanical system for recovering metal and
glass from the noncombustible portion of solid wastes. Standard mineral
beneficiation techniques and off-the-shelf equipment were used in a novel
arrangement to separate and recover salable materials. The primary
products would be ferrous metal, aluminum, a copper-zinc composite,
sand, and a clean, mixed-color glass fraction suitable for recycling.
These materials can be recovered from incinerator residues, but the
system was also designed to handle noncombustible solid wastes that have
been separated from the combustible fraction by air classification or by
some other means. The ability to handle the noncombustible fraction
from both incinerated and non-incinerated solid wastes gives this system
wide application as one of the building blocks in future resource recovery
systems.
A second objective of this project was to evaluate the quality,
marketability, and potential uses for materials recovered from solid
waste. The project would attempt to identify the major constraints to
recycling and to demonstrate an effective marketing approach which
depends on maximum communication between the solid waste processor and
the secondary materials buyer.
A third objective was to demonstrate the value and viability of a
regional approach to resource recovery systems. Before the grant was
cancelled, the Lowell incinerator facility was processing solid waste
from two communities besides Lowell, and the resource recovery system
would rely on a supply of incinerator residue from several additional
communities. As a result, the State of Massachusetts, in developing
their statewide resource recovery program, intended to use this resource
recovery facility as one of its major processing points for noncombustibles
2

-------
Participants and Their Roles
This project involved a unique cooperative venture involving the
local, State, and Federal Governments. The U.S. Environmental Protection
Agency awarded approximately $2.4 million to the City of Lowell
to support 46 percent of the total estimated project cost of $4.4 million.
The State of Massachusetts agreed to provide $615,000, and the remainder
was to be provided by the City of Lowell.
The system designer for the project is the Raytheon Service Company
of Burlington, Mass. Significant consultation has also been provided by
the U.S. Bureau of Mines personnel who pioneered the early development
of the system. The USBM pilot plant at Edmonston, Md., has been used
under a cooperative agreement with Raytheon to perform additional pilot
plant testing that resulted in further system refinements.
At the time of cancellation, the design phase of the project had
been completed, and the construction phase had advanced to the point
where bids had been released for the construction of the resource
recovery facility. The reader should be aware that much of the information
presented here, especially that which concerns recovery rates and
economics, is preliminary and is subject to further verification. The numbers
used to describe recovery rates and percentages are based on studies at
the USBM pilot plant.
SYSTEM DESCRIPTION
Original Developmental Work by USBM
The original developmental efforts on this system were conducted by
the U.S. Bureau of Mines. USBM involvement stemmed from its work in the
mining industry. It was perceived that incinerator residues might be
viewed as a mineral-rich "urban ore" which could be subjected to and
separated by the same mineral separation and beneficiation techniques
which have been used in the mining industry for many years.
The USBM began the early development work on this concept in 1966.
This work culminated in the construction of a small pilot system at its
Edmonston, Md., facility. Completed in 1970, this pilot system has a
throughput capacity of 1,000 pounds per hour. Since then, the Bureau
has continued to perform numerous tests on incinerator residues from all
over the country. Results from these pilot tests were used to improve
the system design and operation.
3

-------
During the detailed design of the Lowell facility, Raytheon Service
Company performed additional analysis on USBM historical data and, in
conjunction with USBM personnel, ran extensive additional pilot-plant
test runs on Lowell residue. As a result of this additional work, the
system design differs in some aspects from the data published by USBM on
the system. Raytheon Service Company has continued to seek consultation
from USBM staff, and due to this extensive pilot-level work, the project
staff has a high degree of confidence in the technical feasibility of
the final plant.
Overall Design Approach
Unlike EPA's other resource recovery projects, this process will
not handle the entire solid waste stream. It is, rather, a subsystem,
within a total resource recovery/disposal system, for extracting the
mineral values from the noncombustible fraction of the solid waste
stream.
The system was designed to accept a very heterogeneous input mate-
rial and produce a series of basic metal alloys and glass which are
suitable for recycling into existing material markets. High purity and
consistency of the output products have been important design objectives
in order to achieve maximum price and marketability.
In addition to the previous USBM pilot work, substantial preliminary
discussions with the expected buyers of the output materials were a
major factor in preparing the final design. Sample products from the
pilot tests were distributed to potential buyers for scrutiny, analysis,
and recommendations. Their responses were important in determining how
to maximize the marketability of the various products. These responses
were also used in preparing the final design to match as closely as
possible the material specifications of the probable buyers. EPA
recommends this approach to designing any resource recovery system. It
is worth emulating.
Finally, the design development was also supplemented by a large
number of tests performed on the anticipated full-scale equipment units
to verify the ability of large commercial-scale equipment to duplicate
the pilot plant results. In fact, nearly every processing step was
tested on full-scale units, on a piecemeal basis, using residue from the
Lowell incinerator. Proven equipment, available from the mineral bene-
ficiation field, is utilized in the process in order to reduce risks in
development. Evaluating the effectiveness of this equipment for processing
solid waste would have been a major objective of the demonstration
project.
4

-------
Description of Process Flow
The following is a functional description of the process operation
as presently conceived (Figure 1).
Primary sorting. Incinerator residue is pushed off a tipping floor
onto a vibrating conveyor by a front-end loader. The vibrating conveyor
evens out the flow of material and feeds in uniformly into the trommel
which is a rotating cylindrical screen with 1 1/4-inch holes. The
trommel separates the residue into a metal-rich fraction greater than
1 1/4 inch and a glass-rich fraction which is less than 1 1/4 inch.
Ferrous separation. The trommel oversize, which makes up about 20
percent of the incoming residue, is fed to the ferrous separation section
of the plant. It is first conveyed past a hand-picking station where
massive metals may be removed from the material along with some nonferrous
metals of particularly high value. This step protects the shredder from
damage. After the picking station, the trommel oversize stream is fed
to the primary shredder, and the ferrous metals are removed by a drum
magnet.
The recovered magnetic fraction, 80 percent of which is light
ferrous scrap, such as cans, has a density of about 22 pounds per cubic
foot and, on melting, has a metal yield of about 85 percent. Most steel
mills require densities of 75 pounds per cubic foot and a yield of 88
percent purity. Therefore, although not shown on the flow sheet, an
additional cleanup and densification step is required. A ring grinder
will be used for this densification step. This secondary shredding of
the metal fraction produces small dense particles, 3/4-inch in diameter.
This product is then separated from the slag and oxides knocked off in
the shredder by washing followed by a secondary magnetic separation
step.
The trommel undersize, which makes up about 80 percent of incoming
residue, consists mostly of glass, but contains some ferrous and non-
ferrous metals along with paper, unburned organics, and ash. A coarse
material washer is used to wash out much of the ash and unburned material.
Another drum magnet separates the smaller iron particles, which join the
balance of the ferrous product recovered from the trommel oversize.
Copper-zinc separation. The nonmagnetic material discharged from
the organic material separator is fed through a surge hopper/feeder into
a density separation device called a jig which performs two functions.
First, it performs a second-stage cleanup for removal of unburned
organics, ash, and other light waste. Second, it removes heavy nonferrous
metals, such as copper and zinc, from the residue. The remaining light
nonferrous metals (e.g., aluminum) and the glass fraction, which now have
been separated from the heavy nonferrous metals, iron, ash, and unburned
material, are conveyed into a large surge hopper.
5

-------
l.VClNb.RArOR Ri SlDlJt
o o o o o o
o o o o o
o o o o o o
o o o o o
1
f

MATERIAL
WASHER

PAPER . 01RT AND ORGANICS
MASSIVI. Ml FAL.
FERROUS METALS

JIG

CHINDtR
SCREEN
OO
OO
^^MAGNET^^
HEAVY NON-FERROUS METALS
OPAOUE GLASS
CLEAN GLASS
Figure 1. This simplified flowsheet indicates the seven basic
operations used for processing the incinerator residue: primary sorting,
ferrous separation, copper-zinc separation, buffer storage, aluminum
separation, glass separation and cleaning, and water treatment.
6

-------
Buffer storage. A large surge hopper (not shown on the flow
sheet) is provided in the center of the system to allow uniform feeding
of the second half of the plant and to permit production of output
products during short shutdown periods occurring in the first half of
the processing plant. The first part of the plant processes an extremely
heterogeneous random material; it will require considerable maintenance
during operation. To compensate for this, this section of the plant has
been designed to handle approximately twice the average processing
capacity. The second half of the plant which treats a fairly uniform
type of material is designed with closer tolerances and is expected to
run smoothly with few breakdowns and maintenance problems.
Aluminum separation. Material discharged from the large surge
hopper consists primarily of glass and aluminum. This material is
processed in a series of crushing and screening steps. The theory of
operations in this section is that glass and other friable materials
will be crushed to very small particle sizes while the pieces of aluminum
which are malleable will instead be flattened out by the crushing action.
Subsequent screening can then perform an easy size-separation for
recovering the aluminum.
Glass separation and cleanup. The glass-rich fraction leaving the
crushers has very small particle sizes. This fraction is fed to a froth
flotation cell which removes slag, brick, ceramic, and stone and produces
a clean glass product. The flotation rejects are dewatered and recovered
as a sand product. The recovered glass is dried and then separated into
two fractions by a high intensity magnetic separator. One fraction is a
clean mixed-color glass product suitable for making bottles. The other
fraction is basically glass which has been contaminated by iron during
incineration. This material is not suitable for making new bottles and
will probably be included in the sand product.
Water treatment. Most of the processing is carried out in the
presence of water. Water is collected from several sumps throughout the
process. Suspended solids are removed by means of sedimentation. These
solids are pumped to a vacuum drum filter and make up the filter cake
material which is planned for land disposal. Clean water is recycled.
The quantity of water used for processing incinerator residue is
about 2200 gallons per ton of residue on a dry weight basis. By recycling
most of this water about 6 times through the plant, the make-up water
required is only about 360 gallons per ton of residue.
7

-------
PRODUCT DESCRIPTION-MARKETING
Ferrous Metals
Physical description. This product, called incinerated ferrous
scrap, consists mostly of light ferrous metals such as tin cans, nails,
and bottle caps along with some smaller pieces of ferrous metal.
Particles are generally spherical in shape and range in size from 1/4 to
1 inch. This material, packed loosely in a container, has a density of
about 75 pounds per cubic foot.
Quality discussion. The material is somewhat rusted. Most of the
food matter, labels, and coatings have been burned off during incineration.
This product is generally not suitable for detinning because a substantial
part of the tin coating on the cans has been removed or diffused into
the iron during incineration, thus making detinning uneconomical. This
material should have about a 93 percent ferrous metal yield.
Market potential. This ferrous scrap can be used by small steel
mills (mini-milIs), ferrosilicon producers, and by scrap export dealers.
If the ferrous scrap were prepared differently, it would also be suitable
for the precipitation of copper from low-grade copper ores. "Nuggetizing"
the metal makes it unsuitable for copper precipitation, but enhances its
value for steel production. Usually, mini-mills and ferrosilicon
producers will dilute this material with other ferrous scrap in order to
reduce the copper and tin contaminations to acceptable levels for their
use. Mill prices for incinerated ferrous scrap varied from $10 to $45
per ton in the 1972 to 1974 period. If the scrap is channeled through a
scrap dealer, the seller would receive a somewhat lower price.
Preliminary buyer response. In March 1975, the incinerated ferrous
scrap was valued at $22.50 per ton for use in a steel mill.
Aluminum
Physical description. The aluminum scrap product is a nugget-like
mixture of aluminum alloys. This material is screened to recover nuggets
ranging from .14 to 4 inches. As a result of incineration, the aluminum
melts into a dense globular form which has a density of 91 pounds per
cubic foot.
Quality description. This is a very high-quality aluminum product.
The coarse nuggets are fairly pure aluminum alloys that contain very
little, if any, paint, labels, or other contaminants. Furthermore, the
product is not heavily oxidized and has a yield on melting of over 72
percent. Actual yields from residue processed in the pilot plant very
often have exceeded 85 percent. The 72 percent yield is acceptable to
aluminum processors and should be readily obtained by the plant.
8

-------
Market potential. The aluminum scrap can be used for remelting by
secondary aluminum ingot suppliers and by primary producers who process
scrap into higher grade ingots for foundries and other specialty users.
Prices for scrap, similar to this, varied from $160 to $360 per ton in
the 1972 to 1974 period.
Preliminary buyer response. Samples of the expected aluminum scrap
product were circulated to three or four secondary aluminum processors.
In March 197b, their quotes for this product ranged from $250 per ton
delivered to the processor.
Heavy Nonferrous Metals (Copper-Zinc Composite)
Physical description. The copper-zinc scrap product is a mixture
of nugget-like nonmagnetic metal alloys consisting mostly of copper-base
and zinc-base alloys. Samples may also contain some nonmagnetic stain-
less steel and very small quantities of precious metals. The particles
are between .14 and 4 inches. The material has a density of 180 pounds
per cubic foot.
Quality discussion. This product is roughly 60 percent copper
base, 30 percent zinc base, and 10 percent other nonmagnetic metals.
This material has no nonmetallic contaminants, and the various components
can be readily separated and recovered through conventional processes in
the secondary metals industry.
Market potential. Mixed copper and zinc-base alloys can be used by
major copper refiners who extract the copper value. Prices for this
product varied from $300 to $867 per ton between 1972 and 1975.
Preliminary buyer response. The price quoted by one of the copper
smelters in New Jersey in March 1975, was $330 per ton delivered.
Mixed-Color Glass
Physical description. This product is a finely ground, carefully
cleaned mixture of non-color-sorted glass, resembling yellow-white beach
sand. When melted in a 100-percent mix, this material has a light amber
or emerald green color. The material is dry and has a density of
75 pounds per cubic foot.
Quality discussion. This product has been froth-floated to remove
ceramics and stones. STass test melts are transparent and have been
free of stones, seeds, or similar defects.
9

-------
Consideration was given to color-sorting, which would increase the
market value. However, currently available color-sorting equipment
requires much larger particle sizes (1/4 in. to 3/'4 in.), and since
local markets exist for the mixed-color glass product, color-sorting was
not selected.
Market potential. The market potential for a non-color-sorted
glass product is significantly limited vis-\-vis color-sorted cullet.
However, clean mixed-color glass can apparently be used with virgin
materials (silica sand and soda ash) at proportions of 5 to 15 percent
in making flint bottles and perhaps as high as 50 percent in making
green or amber bottles without causing significant changes in the color
of the bottle. Prices for this product varied from $10 to $25 per ton
during 1972 to 1975.
Preliminary buyer response. The Glass Container Corporation plant
in Dayville, Conn., and/or the new Owens-Illinois plant in
Mansfield, Mass., quoted a price of $22.50 per ton for mixed-color
glass in March 1975.
"Sand"
Physical description. The "sand" product resembles dark beach
sand. It is composed of fine ceramic, brick, stone, slag, and other
friable materials including glass. This product may also contain some
metals too fine to be recovered. The density of this material is 70
pounds per cubic foot.
Quality discussion. Work is in progress to evaluate this product
as a road-surfacing material to be mixed with coarse aggregate and to be
used in asphalt or concrete-paving mixtures. As a fine aggregate, this
product might have a value of about $2 per ton.
ECONOMICS
In Proper Perspective
The economic information that follows is based on significant pilot
plant experience and engineering estimates. The economics are sensitive
to capital costs, operating costs, product yields, and prices for the
recovered materials. An attempt has been made here to present current
expectations which are neither optimistic nor pessimistic. An evaluation
of the economics of this plant would have been a major objective of the
demonstration plant. Finally, the economic analysis presented here
reflects numerous conditions specific to the Lowell area, and, therefore,
costs or revenues could vary significantly if the plant were located
elsewhere.
10

-------
Projected Economics
The economic data indicate that the capital cost for this
particular recovery plant is estimated to be $4.12 million (Table l).
TABLE 1
CAPITAL COSTS*
Design, Construction
Management, Shakedown	$798,000
Equipment & Construction	$3,321,000
TOTAL	$4,119,000
~Capital costs are based on 1975 estimates
and quotes at Lowell, Massachusetts, and do not
include cost for land.
The projected operating costs and revenues show that for a 1-shift-
per-day operation the plant will cost $36,000 per year, or about $0.55
per ton of input residue (Tables 2 and 3). If the plant were operated
on 3 shifts, the projected profit would be about $990,000 per year, or
$5.05 per ton of input residue.
Discussion of Economics
The economic viability of an incinerator residue recovery system is
a function of recovery rates, throughput capacity, economic life span of
the hardware, operating costs, and market prices for the products. The
revenues derived from the sale of the recovered products are expected to
almost equal the costs of construction and operation. An increase in
revenue would result in additional profit which can be used to reduce
overall disposal or resource recovery system costs. Since incinerator
residues normally require landfilling, which is becoming increasingly
expensive, this resource recovery system may reduce the landfill volume
requirements by 70 percent or more and thereby provide the overall solid
waste management system with additional savings.
11

-------
TABLE 2
ESTIMATED REVENUES*

Percent
Recovery
(dry weight basis)
Value
$/Ton
Revenue
$/Ton Input
Residue
Aluminum
1.25
250
$3.12
Copper/Zinc
.63
330
2.08
Ferrous
14.6
32.90
4.80
Clean Glass
30.0
22.50
6.75
Sand
24.17
2.00
.50
Filter Cake
15.6
0
0
Organics
13.75
0
0
TOTALS
100.00

$17.25
*Based on material values quoted by interested secondary materials
buyers in March 1975. Aluminum and copper-zinc values are F.O.B.
the resource recovery plant. Haul costs for the remaining materials are
not included in the above quoted values. However, hauling costs have
been included in the operating cost estimates presented 1n Table 3.
12

-------
TABLE 3
PROJECTED OPERATING ECONOMICS

1 Shift/Day
(250 tons of residue
per 8-hour-day,
260 days-per-year,
65,000 tons processed per year)
3 Shifts/Day
(750 tons of residue
per 24-hour-day,
260 days-per-year,
195,000 tons processed per year)

Cost (Income)
per year
Cost (Profit)
per ton input
Cost (Income)
per year
Cost (Profit)
per ton input
Capital Cost*
$424,000
$6.50
424,000
$2.20
Operation and
Maintenance**
$734,000
O
CO
$1 ,950 ,000
$10.00
TOTAL COST
$1 ,158,000
$17.80
$2,374,000
$12.20
Revenue***
($1 ,1 22 ,000)
($17.25)
($3,364,000)
($17.25)
Net Cost (Profit)
$36,000
$0.55
($990,000)
($5.05)
*Capital Costs are amortized using an economic life span of 15 years and a 6 percent interest rate.
~~Operating and maintenance costs are based on 11 to 12 persons/shift at an average salary of $10,000 per year.
*** Revenue estimates are based on March 1975 material values.

-------
ENVIRONMENTAL CONSIDERATIONS
An environmental impact appraisal was prepared for this project.
The appraisal concluded that the potential environmental impact of this
project is not considered to be significant. The areas of possible
detriment can be monitored and controlled adequately to eliminate any
environmental pollution. However, the anticipated benefits are significant.
Pollution resulting from improper land disposal will be reduced, while
natural resources are conserved.
Land
This system will reduce the landfill volume requirements for in-
cinerator residues by over 70 percent. Initially, the unburned organic
material in the residue and the filter cake will be disposed of in
Lowell's sanitary landfill. At a later time, the organic fraction will
be reintroduced into the incinerator for disposal, and the landfill
volume requirements will thereby be reduced by over 85 percent.
The filter cake has the appearance of fly ash from an incinerator.
It consists of suspended solids removed from the processing water and is
mostly ash and dirt contained in the incoming residue and some fine
glass produced during crushing and grinding. Initially, this material
will be landfilled; however, alternative uses for this product as a fill
material replacing soil are currently under investigation.
Air
The process employs primarily wet-processing techniques; therefore,
there will be a minimum dust problem. However, a dryer is used in the
glass cleanup section and the exhaust gases from the drier will be
cleaned in a small bag house.
Water
The plant would require about 50,000 to 100,000 gallons per day of
make-up water. About 270,000 gallons per day would be treated and reused
in the plant. A water treatment system would be incorporated at the
plant to treat 885,000 gallons of process water per day. The plant would
use a 10 to 1 recycle ratio and would discharge approximately 100,000
gallons per day of properly pre-treated and fully acceptable effluent to
a municipal sewer system. This effluent can be readily handled by a
city's waste water treatment plant.
vict!182
14

-------