SYNTHETIC FUELS PROJECTS
STATUS REPORT
NOVEMBER 1980
prepared by
ENERGY POLICY COORDINATION OFFICE
EPA, REGION VIII
DENVER, COLORADO

-------
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
REGION VIII
1860 LINCOLN STREET
DENVER, COLORADO 80295
Ref: 8EA
Dear Colleague:
There is a great deal of interest in the status of proposed commercial
synthetic fuels projects in Region VIII States. I am pleased to provide you
with a compilation of information on the projects of which we are aware. This
list is most certainly incomplete but may provide you with a perspective of
the magnitude of development which is planned in the Region. We have not
included any laboratory or small pilot plant synthetic fuels projects. Also,
this report does not include information on projects designed to convert
wastes to fuel. We plan to update this status report on a quarterly basis.
It can be seen from data in this report that the capacity of the 39 synthetic
fuels facilities being studied is about 1.4 million barrels per day of oil
equivalent. This represents a significant portion of the President's and
Congress' 1992 goal of 2 million barrels per day for the United States.
If you have comments, suggestions for improvement on the report, or other
remarks please direct them to Mr. Terry L. Thoem, Director, Energy Policy
Coordination Office.
Oak X


Sincere

-------
TABLE OF CONTENTS
PAGE
Forward	i
Executive Surrmary	ii
Oil Shale Projects 1
Coal Gasification Projects	17
Coal Liquefaction Projects	28
Tar Sands Projects	37
Glossary	40

-------
EXECUTIVE SUMMARY
On July 15, 1979, President Carter unveiled the Administration's plans to
produce the equivalent of 2.5 million barrels of oil per day of synthetic
fuel. Specific goals to achieve this 2.5 million BPD were as follows:
On July 20, 1979, the Western Governors' Policy Office (WESTPO) met and
adopted a four point affirmative action plan "to move America toward energy
self-sufficiency". This plan stressed: 1) a phased process of synfuels
development; 2) State-Federal partnerships to achieve short-term energy
conservation; 3) State-Federal partnerships to mitigate undesirable
socio-economic impacts; and, 4) improved intergovernmental consultation and
concurrence.
On June 30, 1980, President Carter signed into law the Energy Security
Act. This law provides for the establishment of the Synthetic Fuels
Corporation to provide financial assistance for commercial facilities. It
also calls for the production of synthetic fuels of 500,000 BPD by 1987 and
2,000,000 BPD by 1992. It is expected that the Western United States and
Region VIII states, in particular, will be called upon to provide the major
portion of these production goals.
Table 1 provides a summary listing of proposed commercial synthetic fuels
plants in the Region. Additional detail may be found on the one page fact
sheets developed on each project.
Synthetics from coal
Oil Shale
Biomass
Unconventional gas
1.0 to 1.5 million BPD
0.4 mi 1 lion BPD
0.1 million BPD
0.5 to 1.0 million BPD

-------
TABLE 1

Commercial
Synthetic Fuel
Activities

Oil
Shale Projects





Approximate


Page
Project
Size (BPD)
Status
State
1
White River
100,000
In courts
UT
2
Paraho
10,000
Demonstration design
UT
3
TOSCO
50,000
Feasibility study
UT
4
Geokinetics
20,000
Limited production
UT
5
Cathedral Bluffs
85,000
Module construction
CO
6
Colony
46,000
Construction
CO
7
Occidental
1,000
Construction
CO
8
Rio Blanco
76,000
Pilot construction
CO
9
Superior
12,000
Demonstration design
CO
10
Union
9,000
Construction
CO
11
Chevron
100,000
Planning
CO
12
Exxon
60,000
Planning
CO
13
NOSR
50,000-
Planning
CO


200,000

14
Mobil
50,000
Planning
CO
15
Cities Service
50,000
Planning
CO
16
Equity
1,000
Limited production
CO
TOTAL Oil Shale = 720,000 BPD
B.	Coal Gasification Projects
Approximate
Page	Project	Size (MMCFD) Status	State
17	Great Plains	125	Construction	ND
18	Panhandle Eastern	250	Planning	WY
19	Peoples Gas	250	Planning	ND
20	Lake DeSmet	250	Feasibility study	WY
21	Tenneco	250	Planning	MT
22	Mountain Fuel	275	Planning	UT
23	Washington Energy	?	Planning	MT
24	Rocky Mtn. Energy	250	Feasibility study	WY
25	Northern Res. Inc.	19	Prel. Feasibility study MT
26	Utah International	125	Planning	MT
TOTAL Coal Gasification = 350,000 BPD OE

-------
C. Coal Liquefaction Projects
Size
Page
Project
(BPD methanol)
Status
State
27
Exxon
?
Planning
WY
28
Circle West
15,588
Feasibility study
MT
29
W.R. Grace
35,833
Feasibility study
CO
30
Wentworth Bros.
178,571
Planning
ND
31
Dunn Nokota
83,262
Feasibility study
ND
32
Mobil
40,000 (gasoline)
Planning
WY
33
American Methyl
178,571
PI anni ng
WY
34
Northern Natural Gas
20-25,000
Planning
ND
35
Hampshire Energy
20,000 (gasoline)
PI anning
WY
TOTAL
Coal liquefaction = 250,
,000 BPD OE


D.
Tar Sands Projects



Page
Project
Size (BPD)
Status
State
36
Asphalt Ridge
25,000
Pilot design
UT
37
Great National Corp.
8-25,000
Pilot planning
UT
38
Standard Oil of
T r» rl i js n a
50,000
Feasibility study
UT
Indiana
TOTAL Tar Sands = 100,000 BPD
TOTAL Synfuels = 1,420,000 BPD OE

-------
A. OIL SHALE PROJECTS

-------
Project Type: Oil Shale		
Project Name: White River Shale Project	
Company(s): White River Shale Oil Corp. (Phillips Petroleum, Sunoco Energy
Development Co. and Sohio Natural Resources Co.)	
Project Location: Utah - Federal lease tracts U-a and U-b near Bonanza
Process Technology: Underground room and pillar, surface retort (Paraho,
Union B, and Tosco)	
EPA Permit Status: Expect PSD application by late 1980	
Other Approvals, Dates: Detailed Development Plan submitted, Utah funding
(about $8 million) for reservoir and dam on White River; BLM preparing EIS
(Draft due in December 1980)		
Construction Beginning Date: as early as late 1981
Production Amounts, Dates: 100,000 BPD by 1993
Present Status: Leases were suspended pending resolution of injunction
related to land ownership. June, 1980 - U.S. Supreme Court ruled against
Utah
Remarks:

-------
Project Type: Oil Shale
Project Name: Paraho 		¦	
Company(s): Paraho Development Corp. and others (12 companies to date)
Project Location: Utah-Uinta Basin near Bonanza; NE of Uallb (R25E, TIPS)
Process Technology: Underground room and pillar, surface retort (Paraho)
EPA Permit Status: Preliminary discussions
Other Approvals, Dates: DOE grant for design work on demonstration plant,
DOE grant of $3.1 million (7/9/80) for feasibility study for 30,000 BPD retort
Construction Beginning Date: June 1982
Production Amounts, Dates: Operation to begin 1984; 11,000 BPD by 1990
Present Status: Demonstration plant design work
Remarks: This project has moved from Anvil Points, Colorado. Limited research
may continue at Anvil Points. 		
-2-

-------
Project Type: Oil Shale	
Project Name: TOSCO Sand Wash	
Company(s): The Oil Shale Company (TOSCO)
Project Location: Utah-Uinta Basin - Sand Wash (R21E, T9S)	
Process Technology: Underground room and pillar, TOSCO II surface retort
EPA Permit Status: PSD non applicability determination for exploratory
underground mining activity		
Other Approvals, Dates:	
Construction Beginning Date: 1978
Production Amounts, Dates: 43,000-50,000 BPD beginning 1988
Present Status: Environmental assessment and engineering work underway; test
mine begun		
Remarks:

-------
Project Type: Oil Shale	
Project Name: Geokinetics-LOFRECO
Company(s): Geokinetics,Inc.	
Project Location: Utah-Uinta Basin (R22E, T14S)
Process Technology: Horizontal in-situ	
EPA Permit Status: PSD permit issued (10/80)
Other Approvals, Dates: DOE grant for feasibility study, (7/9/80) for
$1.9 mil 1 ion			
Construction Beginning Date: About 30 BPD production at the present time
Production Amounts, Dates: 200 BPD in 1983, 20,000 BPD in 1990
Present Status: Active production
Remarks: DOE PON for $9.1 million

-------
Project Type; Oil Shale		
Project Name: Cathedral Bluffs	
Company(s): Occidental Oil Shale, Inc. and Tenneco
Project Location: Colorado - Federal lease tract C-b (R96W, T3S)
Process Technology: Modified in-situ and Lurgi surface retorting
EPA Permit Status: Conditional PSD for 5000 BPD, 12/15/77; Anticipated PSD
application for 85,000 BPD by late 1980, NPDES permit under review	
Other Approvals, Dates: Detailed Development Plan approved by DPI August 1977
Construction Beginning Date: 12/77
Production Amounts, Dates: 85,000 BPD (57,000 in-situ and 28,000 surface)
by 1986	
Present Status: Construction - 3 shafts are being sunk
Remarks: Need State SOp emission standard modification

-------
Project Type: Oil Shale		
Project Name; Colony	
Company(s): Colony Development Operation (Exxon and TOSCO)
Project Location: Colorado - North of Parachute (R95W, T5S)	
Process Technology: Underground room and pillar, surface retort (TOSCO II)
EPA Permit Status: Conditional PSD issued on 7/11/79 for commercial plant
Other Approvals, Dates: Final EIS issued, 404 permit approved
Construction Beginning Date: Summer, 1980
Production Amounts, Dates: 46,000 BPD in 1985
Present Status: First construction phase
Remarks:

-------
Project Type: Oil Shale	
Project Name: Occidental Logan Wash
Company(s): Occidental Oil Shale, Inc.
Project Location: Colorado - De Beque - Logan Wash (R97W, T7S)
Process Technology: Modified in-situ	
EPA Permit Status: PSD for retort 7 and 8 (11/1/79; modified 6/27/80)
Other Approvals, Dates:
Construction Beginning Date:
Production Amounts, Dates: 1000 BPD - "Burn" scheduled for November 1981
to June 1982
Present Status: Under construction
Remarks: DOE PON

-------
Project Type:. Oil Shale			
Project Name: Rio Blanco Oil Shale	
Company(s): Rio Blanco Oil Shale Inc. (Gulf and Standard of Indiana)
Project Location: Colorado - Federal lease tract C-a (R99W, T2S)	
Process Technology: Combination of modified in-situ and surface retorts;
demonstration plant will use Lurgi process	
EPA Permit Status: PSD for 1000 BPD - 12/15/77; modification application
anticipated late 1980; NPDES permit under review	
Other Approvals, Dates: Detailed Development Plan approved 9/22/77; Colorado
Joint Review Process for surface retort (2000 BPD) initiated 9/80	
Construction Beginning Date: 1977
Production Amounts, Dates: Development and ignition of two retorts by 1981;
76 , 000 BPD coimiercial facility by 1987	
Present Status: Rubbling began on demonstration project May 1980; Retort "0"
burn ignited on October 13, 1980. Retort 1 scheduled for ignition in Spring
1981.
Remarks:
-8-

-------
Project Type: Oil Shale
Project Name; Superior	
Company(s): Superior Oil Co.
Project Location: Colorado - Piceance Creek/White River (R97W, TIN)
Process Technology: Underground mining, above-ground processing Superior
process	
EPA Permit Status: preliminary discussions	
Other Approvals, Dates: Draft EIS 7/17/79 (BLM), final 7/80; DOE grant for
demonstration plant design	
Construction Beginning Date:
Production Amounts, Dates: Eventually three modules of 11,586 BPD
Present Status: Anticipate BLM negative decision on land exchange; Superior
may utilize private lands near R98W, T6S for module	
Remarks:

-------
Project Type: Oil Shale
Project Name: Union Long Ridge Project
Company(s): Union Oil of California
Project Location: Colorado - Parachute Creek (R96W, T5S)	
Process Technology: Underground room and pillar, Union B retorting
EPA Permit Status: Conditional PSD for module (7/31/79) PSD application sub-
mitted for 10,000 BPD (9/29/80)		
Other Approvals, Dates: Colorado Mined Land Reclamation Board permit for
prototype	 '	
Construction Beginning Date: Prototype - Summer 1980	
Production Amounts, Dates: Prototype - 9000 BPD by 1983. Complete facility
50,000 BPD by 1990	
Present Status: Construction on prototype
Remarks: Received $4 million DOE feasibility grant for upgrading unit
-10-

-------
Project Type: Oil Shale	
Project Name: Chevron	
Company(s): Chevron Shale Oil Co.
Project Location: Colorado - Roan Creek (R99W, T5S) or Parachute Creek
(R97W, T6S)	
Process Technology: Surface mining (?) and surface retort	
EPA Permit Status: Preliminary discussions on PSD
Other Approvals, Dates:
Construction Beginning Date:
Production Amounts, Dates: Initial demonstration plant by 1982; 50,000 BPD fay
1988; 100,000 BPD by early 1990's		-
Present Status: Planning, environmental monitoring
Remarks:

-------
Project Type: Oil Shale
Project Name: Exxon
Company(s): Exxon	
Project Location: Colorado - Hunter Creek (R98W, T3S)	
Process Technology: Underground room and pillar, surface retort - TOSCO II,
Superior - TOSCO II	
EPA Permit Status: PSD application to be submitted mid-1981	
Other Approvals, Dates: Requested BLM to initiate land exchange (Fall 1979)
Construction Beginning Date:_		
Production Amounts, Dates: 30,000 BPD 1987; 60,000 BPD 1990
Present Status: Awaiting BLM decision on land exchange
Remarks:
-12-

-------
Project Type: Oil Shale	
Project Name: Naval Oil Shale Reserves - NOSR	
Ccmpany(s): National Petroleum and Oil Shale Reserves - Department of Energy
Project Location: Colorado - near Rifle (R95W, T5S)
Process Technology: Investigating many options	
EPA Permit Status: Preliminary PSD discussions; EIS scoping meetings
Other Approvals, Dates:
Construction Beginning Date:
Production Amounts, Dates: 50,000-200,000 BPD
Present Status: Planning, environmental monitoring
Remarks:

-------
Project Type: Oil Shale
Project Name: Mobil
Company(s): Mobil	
Project Location: Colorado - Parachute Creek (R95W, T6S)
Process Technology:_?	
EPA Permit Status:, Preliminary discussions; submitted air monitoring plan
Other Approvals, Dates:
Construction Beginning Date:
Production Amounts, Dates: 50,000 BPD
Present Status: Planning, environmental monitoring proposed
Remarks:
-14-

-------
Project Type: Oil Shale	
Project Name: Cities Service
Company(s): Cities Service
Project Location: Colorado - Parachute Creek (R97W, T6S)	
Process Technology: modified in-situ	
EPA Permit Status: Preliminary discussions on permit requirements and monitor-
ing plans		
Other Approvals, Dates:	
Construction Beginning Date:
Production Amounts, Dates: 50,000 BPD
Present Status: Planning
Remarks:

-------
Project Type: Oil Shale
Project Name: Equity
Company(s): Equity
Project Location: Colorado - Black Sulphur Creek (R99W, T3S)
Process Technology: in-situ steam injection		
EPA Permit Status: Nonapplicability PSD determination for present phase
Other Approvals, Dates:
Construction Beginning Date: 1979
Production Amounts, Dates: 1000 BPD
Present Status: Limited operation
Remarks: DOE PON - leach zone operation

-------
B. COAL GASIFICATION PROJECTS

-------
Project Type: Coal Gasification	
Project Name: Great Plains	
Company(s): Great Plains Gasification Associates
Project Location: North Dakota - Mercer County near Beulah
Process Technology: Lurgi	
EPA Permit Status:
Other Approvals, Dates: North Dakota PSD permit November 1978; FERC
Certificate of Public Convenience and Necessity 11/15/79	
Construction Beginning Date: 8/80		
Production Amounts, Dates: 125 MMCFD high BTU SNG
Present Status: Under construction; DOE provided $250 million loan guarantee;
consumers groups including General Motors in Midwest have challenged cost of
gas	
Remarks:
-17-

-------
Project Type: Coal Gasification	
Project Name: Wycoal Gas Inc.	
Ccmpany(s): Panhandle Eastern and Peabody Coal Co.
Project Location: Wyoming - Douglas	
Process Technology: Lurgi gasification and methanation	
EPA Permit Status: Preliminary discussions on PSD application
Other Approvals, Dates: State permit for reservoir issued, DOE cooperative
agreement (7/9/80) for $13.2 million	
Construction Beginning Date:
Production Amounts, Dates: 250 MMCFD high BTU SNG beginning in 1987,
Present Status: Planning
Remarks:
-18-

-------
Project Type: Coal Gasification	
Project Name: Peoples Gas Dunn County Project	
Company(s): Natural Gas Pipeline Co. of America (subsidiary of Peoples Gas)
Project Location: North Dakota - Dunn County
Process Technology: Lurgi		
EPA Permit Status:
Other Approvals, Dates:
Construction Beginning Date:
Production Amounts, Dates: 250 MMCFD high BTU SNG
Present Status: Awaiting North Dakota decision on PSD permit
Remarks:

-------
Project Type: Coal Gasification
Project Name: Lake DeSmet	
Company(s): Texaco and Transwestern Pipeline Co. (subsidiary of Texas
Eastern Corp.)	
Project Location: Wyoming - Lake DeSmet
Process Technology: Lurgi or Texaco
EPA Permit Status: Permits to be applied for in 1982
Other Approvals, Dates:
Construction Beginning Date: 1984
Production Amounts, Dates: 250 MMCFD high BTU SNG beginning in 1988
Present Status: Feasibility study (to be completed by 1981)
Remarks:
-20-

-------
Project Type: Coal Gasification
Project Name: Tenneco
Company(s): Tenneco
Project Location: State line between Wibaux, Montana and Beach, N.D.
Process Technology: Lurgi		
EPA Permit Status: Preliminary contact
Other Approvals, Dates: Tenneco has applied to Montana DNR for Dam and	
Reservoir on Beaver Creek (7/80); Tenneco has requested that Federal coal in
the area be ccfr.petiti vely leased (7/80)	
Construction Beginning Date: 1986	
	f	
Production Amounts, Dates: 250 MMCFD high BTU SNG beginning in 1990; plant
and mine cost = $2.05 billion (1980 $)		
Present Status: Environmental baseline studies since 1974; Monitoring to
begin Fall 1980; Long Range Plan submitted to Montana DNR in April 1980.
Remarks: Have applied to DOE for $20 million in matching funds for engineering
design.			
-21-

-------
Project Type: Coal Gasification	
Project Name: Mountain Fuel Supply	
Company(s): Mountain Fuel Supply Co. and Conoco
Project Location: Utah - Emery
Process Technology: Lurgi	
EPA Permit Status: Preliminary discussions on permit application and
environmental monitoring	
Other Approvals, Dates: Site approval from Utah Interagency Task Force on
Plant Siting	
Construction Beginning Date: 1985
Production Amounts, Dates: 125 MMCFD high BTU SN6 increasing to 275 MMCFD
high BTU SNG	
Present Status: Planning
Remarks:
-22-

-------
Project Type: Coal Gasification
Project Name: Washington Energy
Company(s): Washington Energy Co.
Project Location: Montana - McCone County - Circle
Process Technology:	
EPA Permit Status:
Other Approvals, Dates:
Construction Beginning Date:
Production Amounts, Dates:
Present Status: Planning - Awaiting DOE decision on feasibility study grant
Remarks:

-------
Project Type: Coal Gasification	. 	
Project Name: Cherokee	
Ccnipany(s): Rocky Mountain Energy Company Consortium
Project Location: Wyoming - near Rawlins	
Process Technology: Lurgi and Koppers Totzek combination
EPA Permit Status: Permits will be applied for in early 1982
Other Approvals, Dates:
Construction Beginning Date: Early 1984
Production Amounts, Dates: 125 MMCFD beginning in 1986, increasing to 250
MMCFD by 1989	
Present Status: Feasibility study (to be completed by January 1982); site
selection late 1980
Remarks:
-24-

-------
Project Type: Coal Gasification	
Project Name: Northern Resources, Inc.
Company(s): Northern Resources, Inc.
Project Location: Montana - Billings
Process Technology: Lurgi	
EPA Permit Status:
Other Approvals, Dates:
Construction Beginning Date: Begin in 1981 (?)
Production Amounts, Dates: 19 MMCFD to be supplied to Exxon refinery
Present Status: Planning
Remarks: Would also purchase 3 million CFD of sour gas from Exxon, purify, and
return along with produced gas			
-25-

-------
Project Type: Coal Gasification		
Project Name: Crow Tribe	
Company(s): Utah International, Pacific Lighting Corp. and Crow Tribe
Project Location: Montana - Big Horn County
Process Technology:	
EPA Permit Status:
Other Approvals, Dates: Received $2.8 million DOE grant for feasibility study
Construction Beginning Date:
Production Amounts, Dates: 125 MMCFD by 1989
Present Status: Planning
Remarks:
-26-

-------
Project Type: Coal Gasification		
Project Name: Northern Resources	
Ccmpany(s): Northern Resources, Inc. (subsidiary of Burlington Northern)
Project Location: Montana - Billings
Process Technology:	
EPA Permit Status:
Other Approvals, Dates:
Construction Beginning Date: Late 1981 - early 1982
Production Amounts, Dates: 19MMCFD
Present Status: Preliminary feasibility study
Remarks:

-------
C. COAL LIQUEFACTION PROJECTS

-------
Project Type: Coal Liquefaction
Project Name: Exxon	
Company(s): Exxon	
Project Location: Wyoming - Campbell County
Process Technology:	
EPA Permit Status:
Other Approvals, Dates:
Construction Beginning Date:
Production Amounts, Dates: mid 1990's
Present Status: Planning
Remarks: Long range planning

-------
Project Type: Coal Liquefaction			
Project Name: Circle West Project
i
Company(s): Burlington Northern, Dreyer Bros., Inc., Basin Electric, and
Resources Sciences Corp.	
Project Location: Montana - McCone County - Circle
Process Technology:	
EPA Permit Status: Preliminary discussions
Other Approvals, Dates: DOE feasibility grant received; discussions with
Montana DNR on siting	
Construction Beginning Date:
Production Amounts, Dates: 2175 TPD (15,588 BPD) Fuel grade methanol
Present Status: Feasibility study, environmental monitoring
Remarks:
-29-

-------
Project Type: Coal Liquefaction
Project Name; W.R. Grace	
Company(s): W.R. Grace and Co.
Project Location: Colorado - near Axial	
Process Technology; Koppers - Totzek - will produce a slurry of methanol and
COq for pipeline transport with pulverized coal	
EPA Permit Status: Preliminary discussions	
Other Approvals, Dates: Awarded DOE feasibility study grant (7/9/80) for
$786 , 477	
Construction Beginning Date:
Production Amounts, Dates: 5000 TPD (35,833 BPD) of methanol beginning in
1986
Present Status: Planning, beginning feasibility study
Remarks:
-30-

-------
Project Type: Coal Liquefaction	
Project Name: Wentworth Brothers	
Company(s): Wentworth Bros., Inc. for 19 utilities and industries
Project Location: North Dakota
Process Technology:	
EPA Permit Status:
Other Approvals, Dates:
• Construction Beginning Date:
Production Amounts, Dates: 178,571 BPD methanol
Present Status: Planning
Remarks:
-31-

-------
Project Type: Coal Liquefaction		
Project Name: Dunn Nokota Methanol Project
Company(s): Nokota	
Project Location: North Dakota - Dunn County	
Process Technology: Lurgi gasifiers and methanol synthesis units
EPA Permit Status:
Other Approvals, Dates: DOE grant for feasibility study 7/9/80
Construction Beginning Date: Spring 1983
Production Amounts, Dates: 11,618 short tons per stream day (83,262 BPD) of
fuel grade methanol plus 3,050 BPD of "gasoline blending stock" beginning in
1986	
Present Status: Feasibility study	
Remarks:
-32-

-------
Project Type; Coal Liquefaction
Project Name: Mobil	
Company(s): Mobil Oil Co.	
Project Location: Wyoming - Buffalo	
Process Technology: Lurgi gasification and Mobil's M process for conversion
to gasoline	
EPA Permit Status:
Other Approvals, Dates:
Construction Beginning Date: 1986	
Production Amounts, Dates: 40,000 BPD gasoline beginning in 1990
Present Status: Planning - Awaiting DOE decision on feasibility grant
Remarks:
-33-

-------
Project Type: Coal Liquefaction	
Project Name: American Methyl	
Company(s): American Methyl Fuel Corp.
Project Location: Wyoming - near Gillette
Process Technology:	
EPA Permit Status:
Other Approvals, Dates:
Construction Beginning Date:
Production Amounts, Dates: 178,571 BPD methanol
Present Status:
Remarks:

-------
Project Type: Coal Liquefaction	
Project Name: Northern Natural Gas	
Company(s): Northern Natural Gas of Omaha
Project Location: North Dakota
Process Technology:	
EPA Permit Status:
Other Approvals, Dates:
Construction Beginning Date:
Production Amounts, Dates: 20,000-25,000 BPD methanol
Present Status: Planning - Awaiting DOE decision on feasibility grant
Remarks:

-------
Project Type: Coal Liquefaction
Project Name: Hampshire Energy
Company(s): Hampshire Energy, Inc.
Project Location: Wyoming - near Gillette	
Process Technology: indirect gasification plus Mobil M
EPA Permit Status:
Other Approvals, Dates: DOE award of $4 million for feasibility study
Construction Beginning Date:
Production Amounts, Dates: 20,000 BPD of gasoline by 1985
Present Status:
Remarks:

-------
D. TAR SANDS PROJECTS

-------
Project Type: Tar Sands	
Project Name: Asphalt Ridge	
Company(s): Sohio Natural Resources Co.
Project Location: Utah - Uintah County - Asphalt Ridge (R21E, T4S)	
Process Technology: Surface strip mining, surface solvent/water extraction
EPA Permit Status:
Other Approvals, Dates:
Construction Beginning Date: Pilot - 1982; Full plant - 1988
Production Amounts, Dates: Pilot - 5000 BPD by 1983; Full plant - 25,000
BPD by 1990	
Present Status: Design and permits application for pilot
Remarks:

-------
Project Type: Tar Sands		
Project Name: Great National Corporation Project	
Company(s): Great National Corp. and Ford, Bacon and Davis Utah, Inc.
Project Location: Utah - Carbon County - Sunnyside Deposit	
Process Technology: Surface strip mining, surface hot water/thermal
extraction (hybrid)	
EPA Permit Status:
Other Approvals, Dates:
Construction Beginning Date:
Production Amounts, Dates: Pilot -? Full plant - 8,000-25,000 BPD by 1989
Present Status: Pilot planning
Remarks:
-38-

-------
Project Type: Tar Sands	
Project Name: Standard Oil	
Company(s): Standard Oil of Indiana
Project Location: Utah - Carbon County - Sunnyside
Process Technology: Surface mining, solvent extraction
EPA Permit Status:
Other Approvals, Dates:
Construction Beginning Date:
Production Amounts, Dates: 50,000 BPD
Present Status: Feasibility study
Remarks:

-------
GLOSSARY
BPD	barrels per day - a measure of daily oil production
BPDOE	barrels per day, oil equivalent - a measure of production for
synthetic fuels expressed in terms of an equivalent amount of
natural crude oil
MMCFD	million standard cubic feet per day - a measure of synthetic or
natural gas production
DOE	Department of Energy
PON	Program Opportunity Notice - a contractual arrangement between
DOE and industry
NPDES	National Pollutant Discharge Elimination System - permit to
discharge wastewater into the waters of the U.S.
EIS	Environmental Impact Statement
PSD	Prevention of Significant Deterioration of Air Quality - permit
to emit air pollutants into the atmosphere; required for major
new facilities
BLM	Bureau of Land Management
DOI	Department of Interior
FERC	Federal Energy Regulatory Commission
SNG	Synthetic Natural Gas
BTU	British Thermal Unit - a unit of measure of heat required to
raise the temperature of one pound of water one degree Farenheit
DNR	Department of Natural Resources
TPD	Tons per day