EVALUATION OF FIVE REGULATORY
DECISION-MAKING PROCESSES AFFECTING
PUGET SOUND'S WATER QUALITY
November 29, 1983
Submitted to:
Office of Analysis and Evaluation
and legion X
U.S. Environmental Protection Agency
401 M Street, S.W.
Washington, D.C. 20460
Project Officer; Robert Linett
Work Assignment Manager: Sara L. Neuber
In Response to:
EPA Contract No. 68-01-6348, Work Assignment No.
JRB Project No. 2-834-03-760-28
Submitted by;
Water Programs Division
JRB Associates
8400 Westpark Drive
McLean, V .A 22102

-------
JRB Associates 8400 Westpark Drive, McLean, Virginia 22102
A Company of Science Applications. Inc
(703) 821-4600
November 29, 1983
Mr. Robert Linett
Office of Analysis and Evaluation
U.S. Environmental Protection Agency
401 M Street, S.W.
Washington, D.C. 20460
Re: EPA Contract No. 68-01-6348, WA #28
JRB Project No. 2-834-03-760-28
Dear Bob:
Enclosed is JRB's final report entitled "Evaluation of Five Regulatory
Decision-Making Processes Affecting Puget Sound's Water Quality," prepared
in response to Work Assignment 28, "Approaches for Solving Water Quality
Problems in Estuaries." The final report incorporates the comments forwarded
to us.
Should you have any questions of a technical nature, please contact me
at (703) 821-4766. Questions of a contractural nature should be addressed
to our Contract Administrator, Ms. Nancy P. Wright, at (703) 734-4328. It
has been a pleasure working with you and Sally.
Sincerely,
0tttfU 100&4
Deborah K. Wood, J.D.
Acting Work Assignment
Manager
DKW/lls
Enclosure
cc: Elizabeth Southerland, JRB Work Assignment Manager
JRB Contracts
IHIli
RXQD00D20MT

-------
TABLE OF CONTENTS
PAGE
1.	EXECUTIVE SUMMARY/CONCLUSIONS		1-1
2.	INTRODUCTION		2-1
2.1	PROJECT APPROACH		2-1
2.1.1	Task I: Prepare a List of Water Quality
Regulatory Decisions for Puget Sound		2-1
2.1.2	Task II: Evaluate Decision Process for
Selected Water Quality Regulatory Decisions		2-3
2.2	ORGANIZATION OF THE REPORT		2-6
3.	CLEAN WATER ACT SECTION 301(h) WAIVERS		3-1
3.1	THE DECISION-MAKING PROCESS		3-4
3.1.1	The Agencies Involved		3-4
3.1.2	Procedures, Timing and Criteria		3-6
3.1.3	Coordination with Other Agencies				3-12
3.1.3.1	Washington Department of
Ecology (WDOE)		3-13
3.1.3.2	National Marine Fisheries
Service (NMFS) and U.S. Fish
and Wildlife Service (FWS)		3-15
3.1.3.3	Washington Departments of
Fisheries (WDF) and Game (WDG)		3-15
3.1.3.4	Washington Department of Natural
Resources (DNR)		3-16
3.1.3.5	U.S. Army Corps of Engineers.....		3-16
3.1.3.6	Local Shoreline Management Agencies		3-17
3.1.4	Public Input					3-17
3.1.5	Environmental Impact Statement (EIS)		3-18
3.2	OBSTACLES TO DECISION-MAKING		3-19
3.2.1	Technical Obstacles							3—19
3.2.2	Administrative Obstacles.						3-20
3.2.3	Statutory Obstacles				3-20
3.3	CONCLUSIONS				3-21
4.	CLEAN WATER ACT SECTION 404 PERMITS		4-1
4.1 THE DECISION-MAKING PROCESS				4-2

-------
TABLE OF CONTENTS (Continued)
PAGE
4.1.1	The Agencies Involved			4-2
4.1.2	Procedures, Timing and Criteria				4-3
4.1.3	Coordination with Other Agencies		4-9
4.1.3.1	EPA		4-9
4.1.3.2	National Marine Fisheries
Service (NMFS) and U.S. Fish
and Wildlife Service (FWS)		4-11
4.1.3.3	Washington Department of
Ecology (WDOE)		4-12
4.1.3.4	Washington Departments of
Fisheries (WDF) and Game (WDG)				4-13
4.1.3.5	Washington Department of
Natural Resources (DNR)		4-14
4.1.3.6	Local Shoreline Management
Agencies				4-15
4.1.4	Public Input		4-16
4.1.5	Environmental Impact Statement (EIS)		4-17
4.2	OBSTACLES TO DECISION-MAKING		4-18
4.2.1	Technical Obstacles		4-19
4.2.2	Administrative Obstacles						4-20
4.2.3	Statutory or Regulatory Obstacles				4-21
4.3	' CONCLUSIONS		4-23
5. THE EAST, WEST AND DUWAMISH WATERWAYS
NAVIGATION IMPROVEMENT PROPOSAL		5-1
5.1	BACKGROUND AND DESCRIPTION....		5-1
5.2	THE DECISION-MAKING PROCESS		5-6
5.2.1	The Agencies Involved......		5-6
5.2.2.1	The U.S. Army Corps of Engineers		5-6
5.2.2.2	The Port of Seattle		5-8
5.2.2.3	Other Agencies				5-8
5.2.2	Procedures, Timing and Criteria		5-11
5.2.3	Coordination With Other Agencies		5-19
5.2.3.1 Fish and Wildlife Agencies		5-20

-------
TABLE OF CONTENTS (Continued)
PAGE
5.3	DISCUSSION OF OBSTACLES TO DECISION MAKING		5-21
5.3.1	Technical Obstacles		5-21
5.3.2	Administrative Obstacles		5-22
5.3.3	Statutory or Regulatory Obstacles		5-24
5.4	CONCLUSIONS				5-25
6. DESIGNATION OF OPEN WATER DISPOSAL SITES		6-1
6.1	THE DECISION-MAKING PROCESS				6-1
6.1.1	The Agencies Involved........					6-1
6.1.2	Procedures, Timing and Criteria		6-2
6.1.2.1	Selection of Sites		6-2
6.1.2.2	Local Permit Application			6-5
6.1.2.3	Management of Sites		6-7
6.1.3	Coordination With Other Agencies		6-8
6.1.3.1	The Interagency Open Water Disposal
Site Evaluation Committee		6-9
6.1.3.2	Local Shoreline Management
Agencies						6-11
6.1.3.3	Washington Department of
Ecology (VTOOE)		6-13
6.1.3.4	Washington Departments of
Fisheries (WDF) and Game (WDG)		6-14
6.1.3.5	EPA and the Corps of Engineers..		6-15
6.1.4	Public Input.					6-15
6.1.5	Environmental Review Under SEPA.			6-16
6.2	DISCUSSION OF OBSTACLES TO DECISION-MAKING		6-17
6.2.1	Technical Obstacles.					6-17
6.2.1.1	Lack of Information		6-18
6.2.1.2	Lack of Coordination Between Site
Selection and Disposal, Activities		6-20
6.2.2	Administrative Obstacles		6-21
6.2.2.1	DNR Resources		6-21
6.2.2.2	DNR Management		6-22

-------
TABLE OF CONTENTS (Continued)
PAGE
6.2.2.3	Delays Due to Local Agency
Involvement				6-23
6.2.2.4	Complexity Due to Special Permit
Conditions..,,,.,,,...,,,		6—2.3
6.2.3	Statutory/Regulatory Obstacles		6-24
6.2.3.1	Five-Year Permit Limits		6-24
6.2.3.2	Shortage and High Co3t of
Upland Disposal Alternatives..			6-25
6.2.4	Public Input Considerations				6—27
6.3 CONCLUSIONS				6-27
7. REDESIGNATION OF THE FOURMILE ROCK
OPEN WATER DISPOSAL SITE				7-1
7.1	THE DECISION-MAKING PROCESS		7-3
7.1.1	DNTt and The Interagency Committee......			7—3
7.1.2	City of Seattle. 					7-4
7.1.2.1	The Seattle Shoreline Master
Program				7-4
7.1.2.2	SSMP Permit Procedures		7—7
7.1.2.3	Public Notice Requirements..		7-9
7.1.3	Environmental Review......				7-12
7.1.3.1	Lead Agency Status............			7-L2
7.1.3.2	Threshold Determination.				7-12
7.1.3.3	Lead Agency Disputes...				7-13
7.1.3.4	Environmental Impact Statement		7-14
7.1.3.5	Public Notice Requirements...			7-15
7.1.4	Review by WDOE and SHB				7-16
7.2	OBSTACLES TO DECISION-MAKING		7-17
7.2.1	Technical Obstacles				7-17
7.2.2	Administrative Obstacles		7-18
7.2.3	Funding Obstacles		7-18
7.3	CONCLUSIONS		7-13

-------
TABLE OF CONTENTS (Continued)
PAGE
APPENDICES
APPENDIX A - Puget Sound Water Quality Decision-Making Study Questionnaire
APPENDIX B - State of Washington Environmental Checklist Form
APPENDIX C - Bibliography

-------
LIST OF FIGURES AND TABLES
FIGURE	PAGE
2-1	Map of Puget Sound	2-2
3-1	Major 301(h) Applicants	3-5
3-2 301(h) Permit Processing	3-7
3-3 EPA Region X Basic Organization	3-10
3-4	Washington Department of Ecology Divisions Involved	3-14
4-1	404 Permit Processing	4-4
4-2	U.S. Army Corps of Engineers Seattle District,
Basic Organization	4-6
5-1	Proposed Navigation Improvement Project: from Reference 67	5-5
5-2 U.S. Army Corps of Engineers	5-9
5-3	Corps of Engineers Flow Chart for Feasibility Study and
Environmental Impact Statement on Duwamish Project	5-12
6-1	Decision-Making Process for Designation of Open Water
Disposal Sites	6-3
6-2	Washington Department of Natural Resources	6-4
7-1	Map of Seattle Area Showing Duwamish River, Elliot Bay
and Fourmile Rock Open Water Disposal Site	7-2
7-2 City of Seattle Department of Construction and Land Use	7-5
TABLES
2-1 Officials Contacted During Task I Interviews	2-4
2-2	Officials Contacted During Task II Interviews	2-7
3-1	Washington State 301(h) Applicants	3-3

-------
1. EXECUTIVE SUMMARY
Puget Sound is a fjord-like sea consisting of interconnected bays, inlets
and channels. Tidal water enters from the west and freshwater streams enter
at points throughout the system. This complex and productive estuary provides
a diversity of resources and uses including recreation, transportation, com-
merce, fishing, aquaculture, research, waste disposal, and aesthetic enjoy-
ment. It may be difficult to fully realize all of the Sound's potential be-
cause of inherent conflicts and competition between multiple uses. For exam-
ple, aquaculture and waste disposal uses in the same area may be undesirable.
As one official phrased it, "People and shellfish are incompatible."(65F)
Government agencies are charged with regulating both resources and uses.
Agencies' authorities sometimes coincide because their missions include regu-
lation of conflicting uses. This overlap of missions is apparent in Puget
Sound where water, land and people meet. For example, the U.S. Army Corps of
Engineers protects and enhances navigation, while the National Marine Fish-
eries Service protects and enhances fisheries. The State of Washington even
has two discrete agencies to regulate commercial and game fishing. Further,
some agencies have internally inconsistent missions. For instance, the
Washington Department of Natural Resources.both regulates and promotes the use
of natural resources. In addition, there is parallelism between Federal and
State authorities and responsibilities. As an example, the U.S. Environmental
Protection Agency and the Washington Department of Ecology both regulate waste
discharges.
In Governing Puget Sound. R. L. Bish suggests that the State of
Washington has an open government structure and that Federal, State and local
regulatory agencies share decision-making responsibilities.(4) In his view,
the overlap in the decision-making process is generally good in that it allows
agencies to evaluate each others' activities. Its accessibility also permits
public involvement in decision-making, allowing resource users to have a role
in resource management and regulation.
1-1

-------
This study has investigated five decision-making processes that affect
water quality in Puget Sound. They are:
•	Clean Water Act Section 301(h) waivers of secondary treatment
•	Clean Water Act Section 404 dredge and fill permits
•	The proposed Federal navigation improvement project in the Duwamish
River
•	Designation of open water disposal sites for dredged materials
•	Redesignation of the Fourmile Rock open water disposal site.
In each process, public accessibility and high levels of agency interaction
are evident. However, there are also areas where decision-making processes
and informational bases can be improved. Major conclusions intersect all five
decision—making processes and are summarized below.
•	Data - Inadequate data constrain regulatory agencies from making
completely informed decisions in specific cases and in general. As an
example, more sampling data and long-term monitoring are needed to
characterize dredged spoils and to determine their effects when dis-
charged in Puget Sound. Continued research will improve understanding
of the effects of individual discharges and the overall impacts of all
pollutant inputs to the Sound.
•	Resources - Inadequate resources constrain agencies from completely
fulfilling their missions. The Washington Department of Natural Re-
sources illustrates this well because it does not have the personnel
or funds to fulfill its current responsibilities vis-a-vis site moni-
toring much less to expand its regulatory activities in this area. In
this case and in general, increased resources could allow more data
collection and monitoring and enforcement of standards, faster pro-
cessing and review of applications, and improved interagency coordina-
tion.
•	Criteria and Standards - Lack of both specific criteria and general
guidelines impede sound decision-making. For example, numerical sedi-
ment criteria are needed to assess existing conditions and activities
at open water disposal sites and to evaluate dredged sediments pro-
posed for discharge. Also, guidelines for consistent, comprehensive
sampling and monitoring would increase the reliability and compara-
bility of information on dredging sites and disposal activities.
•	Statutory or Regulatory Action - Statutory or regulatory clarification
of agencies' responsibilities and authorities could improve decision-
making processes. The Clean Water Act Section 301(h) waiver process
1-2

-------
is a case where legislative action is needed to clarify the State's
authority to grant waivers from secondary treatment. Waivers are
currently considered inconsistent with State law. In the case of open
water disposal sites, the Washington Department of Natural Resources'
role can be expanded administratively to develop a stronger regulatory
program. Also, new regulatory programs may be needed to provide
additional landfill capacity in the Puget Sound area.
• Overall Management - A better overall management perspective is needed
to guide research, obtain resources, develop criteria, and clarify
responsibilities. Although there is overlap, agencies' separate mis-
sions and regulatory programs can limit their perspectives and their
consideration of other agencies' roles. For instance, Federal agen-
cies rarely consider the significance of local agencies' contributions
to decision-making, although localities are responsible for shoreline
management in the State of Washington. A broader perspective could
ensure that agencies' roles dovetail rather than overlap.
1-3

-------
2. INTRODUCTION
As economic and population growth continue in the coastal areas of the
Pacific Northwest, greater stress is being placed on the water quality of
Puget Sound (see Figure 2-1). Development activities in the area can be
linked to a variety of water quality problems, as evidenced by deteriorating
water quality, contaminated sediments and biota, and changes in estuarine
species composition. Control, prevention and mitigation of such adverse
effects may be accomplished through regulatory decisions made by Federal,
State and local environmental agencies.
Until recently, water quality management programs developed under the
Clean Water Act have focused on freshwater systems. Now, with the occurrence
of increasingly complex water quality problems in estuarine areas such as
Puget Sound, the U.S. Environmental Protection Agency is examining the re-
lationship between regulatory decision-making and estuarine water quality as
part of an effort to ensure that data gathering efforts support management
needs. Analysis of the relationship between decision-making and estuarine
water quality requires identification of regulated activities likely to have
an impact on water quality and evaluation of the processes through which
regulatory decisions are made. The purpose of this report is to present five
case studies of regulatory decision-making that affect Puget Sound's water
quality.
2.1 PROJECT APPROACH
The information used to prepare this report was gathered in two tasks.
2.1.1 Task I: Prepare a List of Water Quality Regulatory Decisions for Puget
Sound
In Task I, JRB gathered information to develop a list of major decisions
affecting Puget Sound's water quality that are likely to be made by Federal,
regional and/or State personnel during the next five to ten years. This was
accomplished in two phases. In Phase I, a literature review of JRB and EPA
data bases and reports was conducted to identify planned or potential activ-
ities that may require regulatory resolution. In Phase II, JRB analysts

-------
* / tverett
01
No F^oint
Ed monds
Point
efterio
adison
Seattle
WlOSI
Bremerton_>rfair
ni
Des Moi

o

** Inlet
Q) Steilacoom
)lympia
Figure 2.1 nap Qf Puget Sound
SOURCEi
A Summary of Knowledge of Puget Sound Related to Chemical Contaminants
NOAA Technical Memorandum OMPA-13. 1981.
2-2

-------
conducted interviews in Washington State to verify the importance of issues
identified in Phase I. Discussions with Federal, regional and State personnel
resulted in the following list of water quality-related regulatory decisions:
•	Clean Water Act Section 301(h) Waivers
•	Clean Water Act Section 404 Dredge and Fill Permits
•	Designation of Dredged Material Disposal Sites
•	Superfund Sites
•	Decertification of Commercial Shellfish Harvesting Areas
•	Air Emissions
•	Pretreatment
•	New Source NPDES Permits.
Two specific decisions were added to those listed above, based upon Interest
expressed by EPA Region X. They are:
•	Redesignation of the Fouraile Rock Dredged Material Disposal Site
•	Duwamish River Dredging Project.
Each of the issues listed above is discussed in a report entitled
"Preliminary List of Projected Water Quality-Related Regulatory Decisions For
Puget Sound," dated August 30, 1983. A list of officials contacted during
Task I is presented in Table 2-1•
2.1*2 Task II; Evaluate Decision Process for Selected Water Quality
Regulatory Decisions
In Task II, JRB evaluated the decision-making processes for five
regulatory decisions selected by the EPA Project Officer. Those regulatory
processes analyzed are:
•	Clean Water Act Section 301(h) Waivers
•	Clean Water Act Section 404 Dredge and Fill Permits
•	Duwamish River Dredging Project
•	Designation of Dredged Material Disposal Sites
•	Redesignation of the Fouraile Rock Dredged Material Disposal Site.
2-3

-------
TABLE 2-1
OFFICIALS CONTACTED DURING TASK I INTERVIEWS
U.S. Environmental Protection Agency, Region X, Seattle. Washington
John Armstrong, Biologist, Ocean Programs Team, Water Permits and Compliance
Branch, Water Division
Florence Carroll, NPDES Data Systems, Water Compliance Team, Water Permits and
Compliance Branch, Water Division
Jim Everts, Superfund Enforcement and Contracts Section, Toxic Substances
Control Branch, Air and Waste Management Division
Charles Findley, Deputy Director, Air and Waste Management Division
Carl Kassebaum, Environmental Engineer, Water Resources Assessment Team,
Environmental Evaluation Branch, Water Division
Marcia Lagerloaf, Leader, Ocean Programs Team, Water Permits and Compliance
Branch, Water Division
Joan McVamee, Environmental Engineer, Superfund Management Section, Toxic
Substances Control Branch, Air and Waste Management Division
Elbert Moore, NPS Specialist, Water Planning Section, Water Quality Branch,
Water Division
Gary O'Neal, Director, Environmental Services Division
Dan Petke, Environmental Engineer, IPA, Redmond
Robert Robichaud, Acting Pretreatment Coordinator, Water Permits Team, Water
Permits and Compliance Branch, Water Division
John Underwood, Chief, Water Quality Branch, Water Division
Richard White, Environmental Engineer, Air Program Development Section, Air
Programs Branch, Air and Waste Management Division
Thomas Wilson, Chief, Water Planning Section, Water Quality Branch, Water
Division
U.S. Army Corps of Engineers, Seattle District. Seattle. Washington
John Malek, Environmental Planner
Keith Phillips, Oceanographer, Environmental Resources Section, Planning
Branch, Engineering Division
2-4

-------
TABLE 2-1 (Continued)
OFFICIALS CONTACTED DURING TASK I INTERVIEWS
James Towle, Project Manager
Fred Weinmann, Biologist, Environmental Resources Section, Planning Branch,
Engineering Division
Washington State
Eric Hurlburt, Fisheries Biologist, Washington Department of Fisheries,
Olympia, Washington
David Jamison, Director, Marine Research and Development, Marine Land
Management Division, Department of Natural Resources, Olympia, Washington
Phil Kauzloric, Marine Habitat Manager, Environmental Planning and Permits
Section, Habitat Management Division, Washington Department of Fisheries
Ken Merry, Chief, Office of Environmental Health Programs, Department of
Social and Health Services, Olympia, Washington
Bob Monn, Section Head, Water Quality Management and Planning Section, Office
of Water Quality Management, Water Quality Management Division, Department of
Ecology, Olympia, Washington
2-5

-------
To gather the information required for this task, JRB analysts returned to
Washington State to conduct in-depth interviews with Federal, regional and
State personnel. To facilitate the interview process, a questionnaire was
developed and distributed to individuals with expertise in each decision-
making process. A copy of the questionnaire is provided in Appendix A. A
list of officials interviewed in Task II is presented in Table 2-2.
2.2 ORGANIZATION OF THE REPORT
The report contains seven sections. In addition to the executive
summary/conclusions and this introduction, a section is devoted to each of the
five selected regulatory decision-making processes. Included in each section
is a discussion of the agencies involved, the decision process, the timing of
the process and the decision criteria, coordination between agencies and ob-
stacles to decision-making. Flow diagrams for the overall decision process
indicating key participants, intermediate determinations and processes leading
to the final decision are presented. Organizational charts for the key
agencies are included.
2-6

-------
TABLE 2-2
OFFICIALS CONTACTED DURING TASK II INTERVIEWS
U.S. Army Corps of Engineers, Seattle District, Seattle, Washington
Gall Arnold, Biologist, Environmental Resources Section, Planning Branch,
Engineering Division
Warren Baxter, Permits Section, Regulatory Functions Branch, Operations
Division
Stephen Martin, Biologist, Environmental Resources Section, Planning Branch,
Engineering Division
Fred Weinmann, Biologist, Environmental Resources Section, Planning Branch,
Engineering Division
U.S. Environmental Protection Agency, Region X, Seattle, Washington
John Armstrong, Biologist, Ocean Programs Team, Water Permits and Compliance
Branch, Water Division
Carl Kassebaum, Environmental Engineer, Water Resources Assessment Team,
Environmental Evaluation Branch, Water Division
Gary Voerman, Life Scientist, Water Resources Assessment Team, Environmental
Evaluation Branch, Water Division
National Marine Fisheries Service, Seattle', Washington
Laurie Boch, Attorney, Office of General Counsel
A1 Groves, Biologist
National Oceanographlc and Atmospheric Administration, Seattle, Washington
Edward Long, Marine Biologist, Ocean Assessment Division
Washington Department of Ecology, Olympia, Washington
Carol Fleskes, Sanitary Engineer, Water Quality Management and Planning
Section, Water Quality Management Division, Office of Water Quality Management
Ed Hammersmith, Sanitary Engineer, Shorelands Management Section, Shorelands
Division, Office of Land and Water Resources
William Obert, Environmental Planner, Shorelands Planning Section, Shorelands
Division, Office of Land and Water Resources
Joan Thomas, Division Supervisor, Water Quality Management Division, Office of
Water Quality Management
2-7

-------
TABLE 2-2 (Continued)
OFFICIALS CONTACTED DURING TASK II INTERVIEWS
Jim Thornton, Environmental Planner, Environmental Quality Section, Operations
Management Division, Office of Operations and Enforcement
Washington Department of Fisheries, Olympia, Washington
Curtis Dahlgren, Marine Habitat Manager, Environmental Planning and Permits
Branch, Habitat Management Division
Washington Department of Natural Resources
David Jamison, Director, Marine Research and Development, Marine Land
Management Division
Seattle Department of Conservation and Land Use
Elsie Hulsizer, Senior Land Use Specialist, Land Use Division
2-8

-------
3. CLEAN WATER ACT SECTION 301(h) WAIVERS
Section 301(h) of the Clean Water Act (CWA), 33 U.S.C. 1251 et. seq.,
allows a variance from the secondary treatment requirements of CWA Section
301(b)(1)(B) for POTWs discharging into marine and estuarine waters if certain
criteria are met. The variance is equivalent to a waiver of secondary
treatment requirements for the five-year life of a NPDES permit.
The Section 301(h) waiver program was created in a 1977 amendment to the
CWA. Applications for this waiver were submitted by POTWs in 1979 and in
1982. The following discussion of regulatory history explains why there were
two application periods and why applications submitted in 1979 are subject to
different procedures than those submitted in 1982.
Proposed regulations for the Section 301(h) waiver program were published
by EPA on April 25, 1978 (A3 FR 17484) and became final on June 15, 1979 (44
FR 34784). To be eligible to apply, a POTW had to have an existing discharge
to marine or estuarine waters as of December 27, 1977. A preliminary applica-
tion had to be submitted to EPA by September 25, 1978, and a final application
by September 13, 1979. Seventy applications were received, nationwide.
The' 1979 regulations were challenged in the U.S. Court of Appeals and
three provisions were invalidated (Natural Resources Defense Council, Inc. V.
EPA. 656 F.2d 768 (D.C. Cir. 1981). The court struck down provisions pro-
hibiting the issuance of waivers if the applicant was currently achieving
secondary treatment, for discharges receiving less than primary treatment and
for the discharge of sludge.
Later in 1981, Congress amended Section 301(h) in several respects. The
amendments extended eligibility to apply to all POTWs discharging Into marine
or estuarine waters, and set the submission deadline at December 29, 1982.
POTWs achieving secondary treatment could apply to discharge wastewater at
less than secondary treatment levels, but waivers for sludge discharge were
prohibited. Applications to discharge at less than primary treatment were not
addressed and, thus, not prohibited.
3-1

-------
Subsequently, EPA promulgated final and Immediately effective amendments
to the 1979 regulations to implement the statutory changes (47 FR 24918; June
8, 1982). At the same time, EPA published proposed amendments to the regula-
tions (47 FR 24921). Those amendments became final on November 26, 1982 (47
FR 53666). EPA received 137 applications under the 1982 regulations (40 CFR
125).
As a result of this regulatory history, there remain certain procedural
distinctions between 1979 and 1982 applications. Headquarters retains
decision-making authority for the 30 larger 1979 applications under the 1982
regulations (large applicants are defined as those discharging at least five
million gallons per day or serving a population of at least 50,000). The 40
smaller 1979 applications and all 1982 applications are assigned to the
Regions for decision. In addition, all 1979 applications that are revised by
the applicants as a result of the statutory changes are delegated to the
Regions although concurrence by Headquarters on the decision is required. The
301(h) program is not delegable to states.
All 30 of Washington's 301(h) applicants discharge into Puget Sound or
one of its tributaries. These applicants are listed in Table 3-1. All are
currently achieving at least primary treatment and none propose to drop below
this level of treatment. Of the 30 applications, 17 are pending from 1979,
and 13 from 1982. Of these, the following seven discharge over five million
gallons per day and are thus considered major applicants:
•	1979 applicants
-	Seattle Metro (West Point)
-	Tacoma (North End, Central)
•	1982 applicants
-	Bellingham (Post Point)
-	Edmonds
-	Everett
-	Seattle Metro (Alki).
3-2

-------
TABLE 3-1
WASHINGTON STATE 301(h) APPLICANTS
•	1979 Applicants
Anacortes (Main Point, Skyline)
Clallam County (Clallam Bay, Sekiu)
Coupeville
Hartstene Point
Langley
Lynnwood
Mukilteo
Penn Cove Sewer District
Port Angeles
Seattle Metro (Duwamish, Richmond Beach, West Point)
Steilacoom
Tacoma (Central, North End, Western Slopes)
Westside Water District
•	1982 Applicants
Bellingham (Post Point)
Des Moines Sewer District
Edmonds
Everett
Kitsap County (Manchester)
Lakehaven Sewer District (Lakota, Redondo)
Port Townsend
Seattle Metro (Alki, Carkeek)
Skagit County Sewer District #1 (La Conner)
Southwest Suburban Sewer District (Miller Creek, Salmon Creek)
3-3

-------
The location of the major applicants is indicated in Figure 3-1. Originally,
there were 19 1979 applications, bat Coupeville withdrew its application and
Seattle Metro Duwamish was denied.
The following sections describe the Regional decision-making process and
obstacles to that process.
3.1 THE DECISION-MAKING PROCESS
This section identifies the Federal, State and local agencies involved in
301(h) decisions for Puget Sound POTWs, and describes the nature of their
involvement. It outlines the decision-making process, the timing of the pro-
cess and the criteria that must be met. Coordination among agencies and pub-
lic input are also discussed.
3.1.1 The Agencies Involved
Federal agencies involved in the 301(h) permitting process include EPA
Region X, and the regional offices of the National Marine Fisheries Service
(NMFS) and the U.S. Fish and Wildlife Service (FWS). EPA is the permitting
authority. NMFS and FWS review applications for compliance with the En-
dangered Species Act, 16 U.S.C. 1531 et_. seq.
On the State level, the Washington Department of Ecology (WDOE) is
responsible for determining whether a 301(h) proposal complies with State law,
including water quality standards and the coastal zone management plan, and
whether any other discharger would be required to increase treatment if the
proposal were granted. WDOE may absolutely veto any application on those
grounds.
If an applicant proposes changes to its outfall location and diffuser
design, necessitating construction, the Washington Departments of Fisheries, '
Game, and Natural Resources and the local shoreline management agency will
also be involved, as may the U.S. Army Corps of Engineers.
3-4

-------
A. BELLINGHAM
A
EVERETT
r fiverett
01
No Point
Edmonds
Point
efferso
EDMO
adison
EATTLE WEST POtN
Seattle
WlQSi
Bremen oruwaif
EATTLE
V? ALKI
Des Moines
TAKOM
<_ END
TACOMA CENTRAL

o
I

Steilacoom
APPI! CANTS
OlvmDia
FIGURE 3-1
MAJOR 301(h) APPLICANTS
DAPTED FROM! A Summary of Knowledge of Puget Sound Related to Chemical Contaminants
NOAA Technical Memorandum OMPA-13. 1981.
3-5

-------
The next section describes EPA Region X's decision-making process. The
roles of other agencies are discussed in Section 3.1.3.
3.1.2 Procedures, Timing and Criteria
As the simplified flow chart in Figure 3-2 indicates, the current
decision-making process at Region X is Initiated by receipt of an application.
A complete 1979 application from a small discharger, forwarded from EPA head-
quarters, proceeds directly to technical review. Major 1979 applications re-
viewed by EPA headquarters that receive favorable tentative decisions are for-
warded to the Region for draft permit preparation. A 1982 application does
not receive a technical review until a plan of study is authorized and com-
pleted (if required), and WDOE issues a favorable tentative determination on
compliance with State law and impact on other dischargers.
A 1979 application receives a State determination at the final permit
stage, after Region X or EPA headquarters has reached a favorable tentative
decision. The 1982 regulations require a tentative State determination before
the Region will evaluate the application. If WDOE's tentative determination
is negative, the application will be denied unless revisions that satisfy
State concerns are possible.(65A) After a favorable tentative decision by
Region X, the final State determination on 1982 applications occurs.
The plan of study is also an innovation of the 1982 regulations. Where
time did not permit an applicant to supply all information required by the
submission deadline, the Region may require or authorize submission of addi-
tional information following receipt of an application. If the missing in-
formation concerns discharge characteristics, water quality, biological con-
ditions or oceanographic characteristics, the applicant will be required to
submit a plan of study for collection of the data. A plan of study is re-
quired only when an applicant seeks to submit information after it has sub-
mitted its application. Completion of a plan of study may take up to one
year. Where the data engendered by a plan of study supports changes in pro-
posed treatment levels and/or outfall location and dlffuser design, a revised
application may be submitted with the data collection results.
3-6

-------
~ -
o-
nam 3-2
301(h) mom processing

-------
The technical review involves analysis of the data submitted to determine
whether the criteria are met. Section 301(h) requires the applicant to
demonstrate that:
(1)	there is an applicable water quality standard specific to the
pollutant for which the modification is requested, which has been
identified under section 304(a)(6) of this act;
(2)	such modified requirements will not interfere with the attainment or
maintenance of that water quality which assures protection of public
water supplies and the protection and propagation of a balanced, indige-
nous population of shellfish, fish and wildlife, and allows recreational
activities, in and on the water;
(3)	the applicant has established a system for monitoring the impact of
such discharge on a representative sample of aquatic biota, to the extent
practicable;
(4)	such modified requirements will not result in any additional re-
quirements on any other point or nonpoint source;
(5)'all	applicable pretreatment requirements for sources introducing
waste into such treatment works will be enforced;
(6)	to the extent practicable, the applicant has established a schedule
of activities designed to eliminate the entrance of toxic pollutants from
nonindustrial sources into such treatment works;
(7)	there will be no new or substantially increased discharges from the
point source of the pollutant to which the modification applies above
that volume specified in the permit.
The information necessary to determine if the criteria are met is required to
be furnished with the application.
3-8

-------
The technical evaluation of the application may be conducted by Region X,
or by a contractor. In either case, the evaluation is reviewed within the
Region by the Water and Environmental Services Divisions. The Technical
Support Team of the Environmental Services Division's Field Operations and
Technical Support Branch provides input on receiving water circulation and
quality. The Ocean Programs Team of the Water Division's Permits and Com-
pliance Branch conducts the remainder of the review. The Water Team in the
Office of Regional Counsel reviews permit terms and conditions. An organi-
zational chart of Region X is contained in Figure 3-3. An evaluation
generally takes from one to two months to complete, although there is no
formal time limit for completion.(66A)
Following the technical review and tentative decision, 1979 applicants
may revise their applications to propose changes to treatment levels and/or
outfall and diffuser location and design. A letter of intent to revise must
be sent to EPA within 45 days of EPA's tentative decision on the original
application or within 45 days of promulgation of the 1982 regulations, which-
ever is later. A revised 1979 application must be submitted within one year
of EPA's tentative decision on the original application or within one year of
promulgation of the 1982 regulations, whichever is later.
Revised 1979 applications are treated as new or 1982 applications. Thus,
State determination is required prior to technical review of the revised ap-
plication, and a plan of study may be authorized or requested. If a plan of
study is authorized, an additional revision is possible if the study data sup-
ports changes in proposed treatment leveils and/or outfall location and diffu-
ser design.
A 1982 applicant may also revise its application following the tentative
decision to propose changes to treatment levels $nd/or outfall anj) diffuser
location and design. Revisions which increase pollutant loads (i.e., downward
revisions) must be justified by substantial changes in circumstances beyond
the applicant's control since submission, because 1982 applicants could have
proposed any level of treatment in their submission.
3-9

-------
ricute 3-3
EPA RECION X
¦ASIC ORGANIZATION
OFFICE OF
lint t SAfEIt
OFFICE OF
CIVIL RICHIS
COVLIARCE MARCH
MRItR KRHIIS
DRINKING UAflEA
PROGRAMS MARCH
AHBIENI
HMITORIRG
ARALfSIS MM
ERVIRORCRIAL
EVALUATION
MMICH
JMMCH
KRSOMFL AND
ORGANIZATION/
SUTPORT SERVICES
MARCH
F1EIB OPERATIORS
MO TECHNICAL
SWHII RRAMCR
nnic SURSIAHCES
MSTE
MTA
STSIEHS
MARCH
ASSISTMI FOR
CORGRESSIORAL
IKTERRATIORAL
RELAIIORS
ASSISTMI
FOR STATE
ARO LOCAL
RELAIIORS
CRIMINAL
ERFONCEJUT
DIVISION
REGIONAL COUNSEL
HATER
OIVISIOR
AIR
ERVIRORMJITAL
SERVICES
' DIVISION
OEMITT
RECIORAL AOHINISIRAIOR
KCIORAl
AOHINISIRAIOR

-------
Thus, if a tentative decision is unfavorable, any applicant may make
revisions which reduce pollutant discharges (i.e., upward revisions). If a
tentative decision is favorable, 1979 applicants may revise downward. Down-
ward revision for 1982 applicants is possible only if substantial changes in
circumstances are demonstrated. A revised application is treated as a new
application.
Following a favorable tentative decision, a draft permit, fact sheet and
administrative record are prepared by Region X, as required by the NPDES
procedural regulations at 40 CFR 124. The draft permit contains effluent
limitations, biological, water quality and effluent monitoring requirements
and, if required, a pretreatment program schedule. A pretreatment program is
required if an applicant has known or suspected industrial sources of toxic
pollutants. A program is not required of applicants that certify no known or
suspected industrial sources of toxic pollutants or pesticides.
The fact sheet describes the facility that is the subject of the draft
permit and the type and quantity of pollutants proposed to be discharged. The
basis for permit conditions is summarized, including the calculation of efflu-
ent limitations, and the reasons justifying the waiver are set forth. The
procedures for reaching a final decision are described, including the begin-
ning and' end of the public comment period, and procedures for requesting a
hearing. The fact sheet also provides the name and telephone number of a
person to contact for additional information.
The administrative record for a draft permit includes the application and
any supporting data furnished by the applicant, the draft permit, the fact
sheet, and all documents cited in the fact sheet (unless such material is
readily available at the Region or is published material generally available).
If a tentative decision is unfavorable, the administrative record in-
cludes a notice of intent to deny the application rather than a draft permit.
If the Region's final decision is that the tentative decision to deny was
incorrect, the notice of intent to deny is withdrawn and a draft permit is
prepared.
3-11

-------
Public notice of a draft permit or of intent to deny an application must
be given, and at least 30 days for public comment must be allowed. Notice
requirements are described in Section 3.1.4.
Following public notice, WDOE must concur if a favorable final determina-
tion is to ensue. For 1979 applicants that do not revise their applications,
the first and only State determination occurs at this point. For 1982 appli-
cants and 1979 applicants that revise their applications, this is the second
and final State concurrence.
A final decision to issue or deny a waiver is made after the close of the
public comment period. Notice is sent to the applicant and to everyone who
submitted written comments or requested notice of the final permit decision.
The notice must make reference to procedures for contesting the decision. The
decision becomes effective 30 days after service of notice unless a later date
is specified. If no changes in the draft permit were requested in comments,
the permit becomes effective immediately upon issuance.
A response to public comments must be issued with the final decision.
Any provisions of the draft permit that have been changed must be specified as
well as the reasons for the change. All significant comments must be de-
scribed and responded to. Any documents cited in the response must be in-
cluded in the administrative record for the final decision. The response is
available to the public.
The administrative record for the final decision consists of the record
for the draft permit, all public comments, the tape or transcript of any
hearing and any wTitten material submitted at a hearing. As noted, the
response to comments and any new material must be Included. The final permit
is also included.
3.1.3 Coordination With Other Agencies
This section describes the roles of agencies other than Region X in the
301(h) decision-making process. The responsibilities of those agencies that
3-12

-------
will be Involved in every 301(h) decision are described first. This section
then outlines the roles of agencies that will be involved only if construction
is proposed in a 301(h) application.
3.1.3.1 Washington Department of Ecology (WDOE)
WDOE, located in Olympia, is the State equivalent of EPA. A 301(h)
waiver cannot be granted by EPA unless WDOE certifies that the proposal:
•	Complies with State law, including water quality standards and the
coastal zone management plan, and
•	Will not result in additional pollution control requirements on any
other point or nonpoint sources.
The Water Quality Management and Planning Section of WDOE's Water Quality
Management Division in the Office of Water is responsible for 301(h) policy
development and coordinates the review process. It also conducts an overall
technical review in conjunction with the Regional Offices. The monitoring
component of the application is reviewed by the Water Quality Investigations
Section of the Water Quality Management Division. The Environmental Quality
Section of the Operations Management Division in the Office of Operations and
Enforcement reviews water quality aspects o'f the application. Consistency
with the State's coastal zone management plan is determined by the Shorelands
Management Section of the Shorelands Division in the Office of Land and Water
Resources.(66F) Normally, 90 days are allotted for review, although exten-
sions may be granted by Region X upon request. Figure 3-4 is an organiza-
tional chart of WDOE divisions and the sections Involved.
As evaluation criteria, WDOE uses the State water quality standards, WAC
173-201, and criteria for sewage works design, WAC 173-240, and EPA's 301(h)
regulations, 40 CFR 125. The State must specify any conditions required by
State law in the certification. The final permit must incorporate such
conditions. For 1979 applications, WDOE relies on EPA's technical review
documents and administrative record to reach its determination.(66F) Such
reliance will not be possible for the early determination required on 1982
applications and revised 1979 applications.
3-13

-------
FICUIE 1-4
UASBINCTON DEPARTMENT Of ECOLOGY
DIVISIONS INVOLVED
OFFICE OF
MMAGEIENT
MB RUDSET
to
I
OFFICE OF HUMMUS
SHNSIARCES ANN AIR
POLLUTION CONTROL
HATER QUALITT
MUUGENERr ARB
FLAMING SECTION
NAIER QUALITY
INVESTIGATIONS
SECTION
(10 CHEN
INVESTIGATIONS
	SECTION
SHORE LAMK
NUUGEKNI
SECTION
ENVIRONMENTAL
REVIEW/PERMIT
NANA6EHRI SECTIOR
SAIL IT
SECTION
ENVIRONMENTAL
qUALITT
SECTION
NATEI QUALITY
MMAGEHENI
DIVISION
OPERATIONS
MUAGEIENI
DIVISION
OFFICE OF
RATER QUALITY
HANACHCNI
0LPV1T DIRECTOR
DIRECTOR
OFFICE OF
OPERATIONS AN
ERFORCEKRT
LAND

-------
3.1.3.2	National Marine Fisheries Service (NMFS) and U.S. Fish and Wildlife
Service (FWS)
In its technical review, Region X must determine whether a 301(h) pro-
posal complies with Endangered Species Act 16 U.S.C. 1531 et. seq. A proposal
must comply for a favorable tentative decision to be reached.
The Region sends its tentative decision to the local offices of NMFS and
FWS as part of the public notice process. An explanation of the finding of no
threat to endangered species or their critical habitats is included. At least
30 days are available for review. NMFS and FWS must concur in the determina-
tion for the decision-making process to proceed. Otherwise, the process halts
while further studies are conducted.(66A)
In addition to their endangered species review, NMFS and FWS may propose
that special conditions be included in a permit to avoid substantial impair-
ment of fish, shellfish or wildlife resources. The Region has discretion on
the inclusion of such recommended conditions.(15)
3.1.3.3	Washington Departments of Fisheries (WDF) and Game (WDG)
If an application proposes changes to the outfall and diffuser location
or design necessitating construction, WDF and WDG are sure to be involved.
They could comment in any case, and propose permit conditions to protect fish
and wildlife, but if an application proposes construction, the construction
cannot take place without an hydraulic project approval (HPA) (WAC 220-110).
However, according to WDOE, the HPA process is not part of the 301(h) certifi-
cation and concurrence process. The HPA process might occur simultaneously
with the certification and concurrence process or later, even after a waiver
is granted. WDOE would also have to approve any construction. Thus, the
State distinguishes waiver approval from construction approval.(66F)
Hydraulic projects are defined as'any construction or other work that
will use, divert, obstruct or change the natural flow or bed of any river or
stream, or that will utilize any of the waters of the State, or materials from
3-15

-------
the stream beds. Hydraulic projects may not take place unless an HPA is
granted.(55)
The purpose of the HPA is to protect fish. The program is jointly
administered by WDF and WDG. WDF has jurisdiction over non-game fish and WDG
has jurisidiction over game fish.(65H)
Processing time is generally less than 30 days unless a site visit or
further information is required. The HPA may contain such general, technical
and special provisions as are necessary to protect fishery resources. An HPA
will be denied only if the proposal is determined to be directly or indirectly
harmful to fish life and adequate protection, mitigation or restoration cannot
be assured.(55)
3.1.3.4	Washington Department of Natural Resources (DNR)
DNR manages State lands, including certain aquatic submerged lands. It
requires a lease for the land involved in operation of waste outfalls. Under
WAC 332-30-125(7), the rent is based on the fair market value of land used
plus the actual value of quantifiable public resource elements being with-
drawn. The amount of land used by an outfall depends on the type and volume
of waste discharged, the type of treatment the waste receives and the type of
outfall. The value of resources withdrawn depends on the size of the area
affected, and the number and economic value of natural resources affected. If
a 301(h) application proposes outfall construction, that alteration may be
reflected in an adjustment of the current annual rental.(54)
3.1.3.5	U.S. Army Corps of Engineers
Although the Corps may review and comment upon any 301(h) application,
and always receives notice of draft permits, it is most likely to take an
active role if an application proposes construction because of its respon-
sibilities in the areas of navigation and anchorage. If the Corps Seattle
district engineer determines that navigation or anchorage would be substan-
tially impaired if the permit is granted, the permit must be denied. If the
Seattle district engineer advises the Region that certain conditions in the
3-16

-------
permit are necessary to avoid substantial impairment of navigation or anchor-
age, the Region must include the conditions in the permit (40 CFR 124).
3.1.3.6 Local Shoreline Management Agencies
The State Shoreline Management Act (SMA), RCW 90.58, grants 23 cities and
15 counties the authority to regulate activities within their jurisdiction
that take place on State submerged lands. Such activities must conform to
local master plans that contain goals, policies, environmental zoning designa-
tions and specific use regulations. SMA is the basis for the State's coastal
zone management plan.(59)
Any alteration of an outfall's location or design is an activity that
might require a local SMA permit. The issuance of local permits is governed
by the locally developed master plan. An outfall alteration may require a
substantial development or conditional use permit or a variance, depending
upon the specific use regulations of the local plan.
An environmental checklist must be submitted with the permit application.
On the basis of that checklist, the local agency will decide whether an en-
vironmental impact statement (E1S) is required under the State Environmental
Policy Act (SEPA), RCW 43.21C. This process is discussed further in Section
3.1.5.
The applicant must publish notice in the local newspaper twice, a week
apart, upon filing for a permit. No action may be taken by the local agency
for 30 days. When final action is taken, the applicant, WDOE and the State
attorney general must be notified. The applicant and all interested parties
in disagreement with the final action have 30 days to request certification of
review from WDOE. If a permit is approved without appeal, the applicant may
proceed 45 days after WDOE receives notice of final action.(57,59)
3.1.4 Public Input
Region X must issue public notice of a draft 301(h) permit or of Intent
to deny an application. Under 40 CFR 124, at least 30 days for public
3-17

-------
comments must be allowed. Notice must be mailed to all Interested parties,
including other agencies with jurisdiction over some aspect of the applica-
tion. Notice is sent to the applicant, WDOE, WDF, WDG, NMFS, FWS, the Corps,
DNR, the Advisory Council on Historic Preservation, any other appropriate
government authorities and other interested parties. For major permits,
notice must be published in a daily or weekly newspaper within the affected
area. Press releases may also be utilized.
A public notice must identify the applicant and its location, the office
processing the permit and someone from whom additional information may be
obtained. The nature of the waiver must be described and the times when the
administrative record is available for public inspection. Comment procedures
and procedures to request a hearing must be described. A copy of the fact
sheet, application and draft permit must be sent along with the notice to the
parties named in the previous paragraph. The Regional Administrator may hold
a public hearing at her discretion.
Public notice must also be given by WDOE of receipt of applications for
water quality certification. Notice is mailed to all interested and appro-
priate persons and organizations. The comment period is 20 days. Public
hearings are not mandatory.(56)
3.1.5 Environmental Impact Statement (EIS)
Although an EIS under the National Environmental Policy Act (NEPA), 42
U.S.C. 4321 et. seq., is not required for 301(h) applications, an EIS under
the State Environmental Policy Act (SEPA), RCW 43.21C, may be required if the
application proposes changes to the outfall location and diffuser design re-
quiring construction. An EIS under SEPA would not be required if construction
is not proposed because, in the case of Puget Sound, 301(h) waivers have the
effect of maintaining the status quo.
An EIS under SEPA is required if a proposed activity may have a
substantial adverse effect on the quality of the environment. The need for
an EIS is determined by the lead agency on the basis of a standard State-wide
3-18

-------
environmental checklist (included in Appendix B) completed by the applicant
when applying for a State or local permit. The lead agency in this case would
be the local shoreline management agency if a permit is required under the
local shoreline master plan. Cities and counties are always the lead agency
unless the applicant is an agency, in which case the applicant is the lead
agency.(13)
If an EIS is required, it may be prepared by the agency or by the
applicant, depending on local regulations. The EIS must be issued for review
to all State and Federal agencies with jurisdiction over the proposed action.
Reviewing agencies have 35 days to respond.(13)
According to WDOE, the results of an EIS would not affect the State's
water quality certification or its concurrence on a 301(h) application. Like
the hydraulic project approval required for outfall construction (discussed in
Section 3.1.3.3), the EIS on construction, if required, would be considered a
separate process from certification and concurrence.(66F)
3.2 OBSTACLES TO DECISION-MAKING
This section describes the technical, 'administrative and statutory or
regulatory obstacles to the 301(h) decision process.
3.2.1 Technical Obstacles
WDOE and Region X agree that lack of data on which to base decisions is
the primary technical obstacle to decision-making. Although enough is known
that the agencies feel comfortable granting waivers, particularly because a
waiver decision generally maintains the status quo and may improve it via the
monitoring programs, a better understanding of the limits of the Sound's
assimilative capacity for various pollutants and the cumulative Impact of
discharges is necessary. Further data on circulation and exposure fields in
water columns would be useful, as would benthic testing standards that link
loadings with biological availability and toxicity. Further research to
define the contaminants of concern in an estuarine ecosystem is also needed.
Overall, criteria that specify how much impact is too much are necessary for
3-19

-------
informed and consistent decision-making. Information generated by the plans
of study will be useful, but water quality standards for priority pollutants
and sediment criteria are still needed for informed decision-making.
3.2.2	Administrative Obstacles
Incomplete applications that cause delay and lack of sufficient pro-
cessing personnel are cited as administrative obstacles by Region X. The
major problem in this area, however, is considered to be lack of sufficiently
trained professionals to conduct the technical reviews.(66A)
An administrative problem with technical overtones anticipated by WDOE
pertains to the early State determination required for 1982 and revised 1979
applications. For 1979 applications, WDOE may rely on the information and
determinations of EPA's technical review,.but such reliance will not be
possible for the early State determinations on 1982 and revised 1979 applica-
tions. Delays are foreseen while further information is sought and the exper-
tise of additional personnel is drawn upon.(66F)
Another possible problem has to do with major and revised 1979 applica-
tions. Because EPA headquarters was originally responsible for all 1979
applications, it must concur on the final permit. Concurrence may be a
problem for Region X because all the terms and conditions of the permit have
been negotiated at that stage. If headquarters insists on changes in the
terms and conditions, Region X's position may be hampered by applicants'
knowledge that it does not have the last word.(66A) Thus far, headquarters'
Office of Marine Discharge Evaluation has always concurred.
3.2.3	Statutory Obstacles
There has been great uncertainty at present about whether there will be a
301(h) program in Washington. State law requires best practicable treatment;
all known, available and reasonable treatment technology must be utilized.
That provision has been interpreted to require secondary treatment, thus
foreclosing the availability of 301(h) waivers. The issue arose in December
3-20

-------
1982 when the first proposed final permit was sent to WDOE for certification
and concurrence.(66A)
Legislation authorizing the State to participate in the 301(h) program
was introduced in the last session of the legislature but was not reported
out of committee. The Senate Parks and Ecology Committee is conducting an
informal study of the issues involved. The bill will still be alive when the
legislature reconvenes in January, 1984. However, WDOE has now adopted a
position of nonadvocacy in the belief that lobbying efforts should be led by
the communities that will be forced to finance secondary treatment should the
bill fail. At this point, the bill is opposed by certain legislators rep-
resenting districts that border the Sound on water quality grounds, and
supported by POTWs like Seattle Metro on economic and environmental
grounds.(66F)
An attorney general's opinion on the issue indicates that whether the
State has authority to participate in the program depends on WDOE's interpre-
tation of the phrase "all known, available and reasonable methods" in relation
to treatment technology and the circumstances surrounding each applicant.
Water quality would not be a factor in such an interpretation because the
requirements are technology-based. As State law does not expressly require
secondary treatment, WDOE may have to determine on a case-by-case basis
whether secondary treatment is "available and reasonable" under the particular
circumstances.
3.3 CONCLUSIONS
In theory, the key agencies in the 301(h) decision-making process are
Region X and WDOE, and the key decisions are the Region's tentative decision
and WDOE's certification and concurrence. Due to uncertainty about the
State's authority to participate in the program, however, the key actors at
this time are WDOE, the legislators and affected communities.
Because the process in Washington State has not progressed beyond the
first 1979 application being sent by Region X to WDOE for certification,
3-21

-------
overall conclusions on coordination of the decision-making process are not
possible. Although WDOE has not reviewed an application, review responsibili-
ties have been defined and a 301(h) permit coordinator appointed. Processing
within the Region is well defined and understood, although constrained by lack
of resources. Region X is acknowledged to be a leader in 301(h) program
development and is consulted by other Regions on various issues. For the time
being, limited Regional resources have shifted away from review of Washington
applications, toward review of Alaska applications.
Even with the uncertainty about the 301(h) program, 1982 Washington
applicants are proceeding with their plans of study. The Region expects to
receive all completed applications within the next year.(66A) Whether there
will be a 301(h) program in Washington at that time is unknown.
3-22

-------
4. CLEAN WATER ACT SECTION 404 PERMITS
The Clean Water Act (CWA), 33 U.S.C. 1251 et seq., prohibits disposal of
dredged or fill material in waters of the United States except in compliance
with Section 404. Section 404(a) authorizes the Secretary of the Army, acting
through the Corps of Engineers, to issue permits for the discharge of dredged
or fill material into waters of the United States at specified disposal sites.
Disposal sites are specified through application by the Corps of EPA guide-
lines.
The guidelines, authorized by Section 404(b)(1), and developed by EPA in
conjunction with the Secretary of the Army, are contained in 40 CFR 230. The
guidelines apply to discharges of dredged or fill material to waters inside
the baseline from which the territorial sea is measured, and to fill dis-
charges (including dredged material disposed of for the purpose of fill) into
the territorial sea. Puget Sound is located inside the baseline from which
the territorial sea is measured. Discharges of dredged material into the
territorial sea are regulated under the Marine Protection, Research, and
Sanctuaries Act, 33 U.S.C. 1401 et seq.
The guidelines establish a presumption' against discharge to waters unless
it can be demonstrated that a discharge will not have an unacceptable adverse
impact on the aquatic ecosystem either individually or in combination with
impacts of other activities that affect ecosystems of concern. If a proposed
discharge does not comply with the 404(b)(1) guidelines, the Corps may still
issue a permit if it decides under Section 404(b)(2) that the economic impact
on navigation and anchorage warrant issuance. The authority to issue permits
for dredged or fill material discharge Is delegated to 36 district engineers.
Corps procedures for permit issuance are contained in 33 CFR 320 £t seq.
In addition to individual permits under Section 404(a), the Corps is
authorized to issue general permits under Section 404(e) on a state, regional
or nationwide basis. General permits cover categories of activities involving
dredged or fill material disposal that are similar in nature, cause minimal
adverse environmental effects when performed separately and have only minimal
4-1

-------
cumulative adverse effects on the environment. The activities specified in a
general permit may take place without an individual permit. General permits
may be issued for more than a five year term.
If certain conditions are met, Section 404 does not govern the discharge
of dredged or fill material as part of the construction of a Federal project
specifically authorized by Congress. Under Section 404(r), if an environmen-
tal impact statement containing informat'ion on the effects of the discharge is
submitted to Congress prior to the discharge and prior to authorization of the
project or appropriation of funds, then Section 404 does not apply. Still, an
evaluation under the Section 404(b)(1) guidelines is included in the submit-
tal. Section 5 of this report describes the regulatory decision-making pro-
cess for a specific Section 404(r) project.
The sections immediately following describe the decision process for
individual Section 404(a) permits to discharge dredged or fill material and
the obstacles encountered in that process.
4.1 THE DECISION-MAKING PROCESS
This section discusses the procedures .and criteria used by the Corps to
process and evaluate 404 permit applications, and the timing of the process.
This section also outlines the roles of other Federal, State and local agen-
cies involved in decision-making and the opportunities for public input. The
situations requiring environmental impact statements are described, obstacles
to the decision process are discussed and conclusions are drawn.
4.1.1 The Agencies Involved
As noted, the U.S. Army Corps of Engineers is the issuing authority for
permittee dispose of dredged or fill material in waters of the United States.
In the Puget Sound area, this authority has been delegated to the Seattle
District of the Corps. In conjunction with the Army, EPA develops the guide-
lines for specification of disposal sites and oversees delegation of State 404
programs. EPA Region X reviews permit applications, among other responsibil-
ities. Other Federal reviewers include the National Marine Fisheries Service
and the U.S. Fish and Wildlife Service.
4-2

-------
On the State level, the Washington Department of Ecology (WDOE) reviews
each application for water quality certification and coastal zone plan con-
currence. It also coordinates the State review process and provides the
formal State response. WDOE routinely sends 404 applications to seven agen-
cies for review. These agencies are the Departments of Fisheries, Game,
Natural Resources, Social and Health Services, and Transportation, the Parks
and Recreation Commission and the Office of Archeology and Historic Preserva-
tion.
The appropriate local shoreline management agency also reviews 404 permit
applications for consistency with the local shoreline master program. The
local shoreline management agency may be a city or a county agency.
The next section describes the procedures, timing and criteria involved
in the Corps' decision-making process. The roles of other agencies are dis-
cussed in Section 4.1.3.
4.1.2 Procedpres, Timing and Criteria
The following discussion is based on Cprps procedures contained in 33 CFR
320 eit. seq. As the simplified flow chart in Figure 4-1 indicates, the formal
process begins with the submission of an application for a permit to the
Seattle District Corps office. If a major project is proposed, applicants are
encouraged to consult with the Corps prior to submission of an application for
advice on the type and quantity of information that may be required.
All activities reasonably related to the same project are included in a
single permit application. For example, a single application may propose non-
navigational dredging, which is permitted by the Corps under Section 10 of the
Rivers and Harbors Act, as well as disposal of the dredged material, which
may be governed by CWA Section 404 or Section 103 of the Marine Protection,
Research and Sanctuaries Act. The same general procedures govern all Army
permitting processes.
4-3

-------
turn
ZZ7-
O-
o-
TICUU 4-1
4OA PERMIT FROCESSINC

-------
An application to discharge under 404 is reviewed for completeness within
15 days of receipt. The applicant must, among other things, describe the
source of the material proposed to be discharged; its type, composition and
quantity; the proposed method of transportation and disposal; and the location
of the proposed disposal site. If the application is incomplete, additional
information will be requested.
Within 15 days of receipt of all required information, public notice is
issued. Thirty days are generally allowed for comment, although as few as
15 may be allowed. An additional 30 days for comment may be provided upon
request. Comments must be considered and made part of the administrative
record.
During the public comment period, the application is reviewed by the
Corps. Complex cases are reviewed by the Environmental Resources Section of
the Engineering Division's Planning Branch. Other cases are reviewed by the
Permit Section of the Operations Division's Regulatory Functions Branch, which
also coordinates the overall process and issues permits.(66Q) Figure 4-2 is
an organizational chart of the Seattle District office.
The Corps conducts what is known as a .public interest review. The public
interest review balances favorable impacts against detrimental impacts, in-
cluding cumulative impacts, to reflect national concerns for both the pro-
tection and utilization of important resources. Corps review also includes
consideration of the 404(b)(1) guidelines developed by EPA. A permit must be
denied if the proposed activity is not in the public interest or does not
comply with the 404(b)(1) guidelines.
In the public interest review, the relative need for the proposed
activity is considered. If there are unresolved conflicts about resource use,
reasonable alternative discharge locations and methods are evaluated for
practicability. In addition, the Corps considers the extent and permanence of
beneficial or detrimental effects on public and private uses of Che area.
4-5

-------
SAftU
OFFICE
comsn
OFFICE
PUBLIC
AFFAIRS
OFFICE
OFFICE OF
AOHIMSIMIITC
SERVICES
NEST SIATILE
HIOGE
ICSIOHT
OFFICE
LINT DW
HSIOEII
OFFICE
CHIEF JOSEPH
DM (ESIOEIT
OFFICE
SPECIAL
ASSISTANTS
EKCUIire OFFICE
FIGURE 4-2
D.S. ARMY CORPS OF ENGINEERS
SEATTLE DISTRICT, BASIC ORGANIZATION

-------
Any impacts of dredged or fill material disposal in the following areas
are balanced in the public interest review:
•	Wetlands
•	Fish and wildlife
•	Water quality
•	Historic, cultural, scenic and recreational values
•	Interference with adjacent properties or water resource projects
t Coastal zone
•	Marine sanctuaries
•	Navigation
•	Other Federal, State or local requirements.
The 404(b)(1) guidelines (40 CFR 230) establish certain conditions that
must be met for a permit to issue. Under Section 230.10, a discharge must not
be permitted if there is a practicable alternative that would have less impact
on the aquatic ecosystem and that would not cause other significant environ-
mental consequences. A proposed discharge must not cause or contribute to
violations of applicable State water quality standards, violate applicable
toxic effluent standards or prohibitions under CWA Section 307, jeopardize
endangered or threatened species or their critical habitat, or violate any
requirement imposed to protect a designated marine sanctuary. In addition, a
discharge must not be permitted if it would cause or contribute to significant
degradation of waters of the United States. All appropriate and practicable
steps to minimize adverse impacts on the aquatic ecosystem must be taken.
To ensure compliance with the above conditions, the 404(b)(1) guidelines
require consideration of the potential impact of the discharge on the physi-
cal, chemical and biological characteristics of the aquatic ecosystem, and on
special aquatic sites and human use characteristics. The guidelines require a
written factual determination on potential short- and long-term effects in the
following areas:
•	Physical substrate
•	Water circulation, fluctuation and salinity
4-7

-------
•	Suspended particulate/turbidity
•	Contaminants
•	Aquatic ecosystem and organisms
•	Proposed disposal site
•	Cumulative effects
•	Secondary effects.
These determinations are included by the Corps in a statement of findings
(SOF) or record of decision (ROD), prepared after an environmental assessment.
The SOF is prepared in cases where an environmental impact statement under the
National Environmental Policy Act, 42 U.S.C. 4321 et seq., is not required.
The ROD is prepared if an environmental impact statement is required. An SOF
or ROD contains the district's public interest review and 404(b)(1) findings
and conclusions. It is included in the administrative record prior to final
action on the application. Final action is not taken until the public comment
period has closed and the responses of other agencies and the public are
received.
At the earliest possible time, the Corps provides the applicant with an
opportunity to propose resolutions or rebuttals to any substantive negative
comments from concerned parties. A final decision will not be made until
objections are resolved. However, the Corps may issue a permit over objec-
tions that it deems insignificant, if no concerned Federal agency objects.
Under CWA Section 404(q), Federal agencies that review 404 permit applications
may request that a Corps decision to issue a permit over objections be re-
viewed by a higher authority. This review process is known as elevation.
A State water quality certification must be obtained from or waived by
WDOE before a permit will be granted. The Corps assumes that the State has
waived certification if no action is taken on a certification request within a
period of 60 days. The district; engineer may, as appropriate, extend or
shorten this allowed time. Still, no extension may exceed one year.
WDOE must also concur that an application is consistent with the State
coastal zone management plan before a permit will be Issued. If the State
objects or indicates that further review is necessary, a permit will not be
4-8

-------
issued until concurrence is given by WDOE or the Secretary of Commerce deter-
mines that the application is consistent with the Coastal Zone Management Act.
If the State fails to concur or object within six months, concurrence is
presumed.
Once the water quality certification and coastal zone concurrence are
obtained, and a permit is deemed warranted on the basis of the administrative
record, objections are resolved or rebutted. The district will determine the
special permit conditions, if any, and permit duration. At this stage, prior
to final action, the Corps staff may forward the application and administra-
tive record to a higher Corps authority for decision. Such an elevation by
Corps staff is most likely to occur in highly controversial cases.
If the district decides to deny the permit, the applicant is notified in
writing of the dispositive reasons for the decision. If the final decision is
to issue the permit, the Corps sends two copies of a draft permit to the ap-
plicant for signature. Signature indicates acceptance of permit conditions.
Both copies of the draft permit must be returned to the district for signature
by the issuing official. One copy is returned to the permittee. Final action
is the signature of the issuing official on the permit or the signature on the
letter notifying the applicant of denial.
The fee for a 404 permit is $100 if the ultimate purpose of the project
is commercial or industrial in nature, and $10 if the project is non-commer-
cial in nature. The fee is payable to the U.S. Treasury and due when the
permit is Issued.
4.1.3 Coordination with Other Agencies
This section describes the roles of other agencies in the 404 process,
and how their evaluations are coordinated with the overall process. Federal,
State and local agencies involved will be discussed in that order.
4.1.3.1 EPA
EPA has several roles to play In the 404 program. As administrator of
the Clean Water Act, EPA establishes the scope and jurisdiction of the 404
4-9

-------
program. As noted, the agency is responsible, in conjunction with the
Secretary of the Army, for developing the 404(b)(1) guidelines for specifi-
cation of disposal sites. EPA reviews individual permit applications, general
permits and environmental impact statements, and has authority to restrict or
prohibit use of a discharge site under CWA Section 404(c). In addition, EPA
is responsible for approving and overseeing the delegation of State 404 pro-
grams under 404(g) and (h). States may apply for authority to issue dredged
or fill material discharge permits for their "non-navigable" waters. "Non-
navigable" waters are those waters which are not used for interstate or
foreign commerce and which are not susceptible to such use. The State of
Washington has reviewed its authority and determined that existing legislation
is not sufficient to meet EPA requirements for establishment of a State 404
program. There are no plans at present to enact the required authorities.(39)
Acting through its regional offices, EPA reviews 404 applications
forwarded by the Corps for comment as part of the Corps' public notice proce-
dure. The Corps may issue a 404 permit even if EPA's determination of com-
pliance with the guidelines is negative, after consultation on the objections.
However, as noted, the statute establishes a procedure in Section 404(q)
whereby EPA may elevate review of a permit if it objects to Issuance of the
permit as proposed. In addition, EPA'is authorized by CWA Section 404(c) to
prohibit or restrict specification of any area as a sice if it determines that
disposal will have an unacceptable adverse effect on shellfish beds and fish-
ery areas, wildlife, municipal water supplies or recreational areas. This
authority may be exercised in advance of a planned discharge, while a permit
application is pending or even after Issuance of a permit. Exercise of
Section 404(c) authority is governed by procedures contained in 40 CFR 231.
The decision is made by the Regional Administrator and reviewed by the
Administrator prior to site restriction or prohibition.
Thus, EPA may block issuance of a discharge permit	only by using CWA
Section 404(c). The Corps may not override such action with the economics of
navigation and anchorage determination of 404(b)(2) but	may request a waiver
from EPA on that basis. Region X haa not yet exercised	Section 404(c)
authority.
4-10

-------
Region X's evaluation of the consistency of 404 applications with the
404(b)(1) guidelines is conducted by the Water Division's Environmental Evalu-
ation Branch, with support from the Environmental Services Division and the
Air and Waste Management Division (see Figure 3-3). Most evaluations take
less than a day to conduct, and in those cases all of the information needed
for review is supplied in the public notice. In more complex cases, addi-
tional information and review time are likely to be required. The Region
often coordinates requests for additional information with other reviewing
agencies.(66J) There is a 30-day time limit on review. The Corps extends
this review period for an additional 30 days upon request.
The primary concerns of the Region in the review of applications to dis-
charge dredged material is the degree of contamination of the material and the
nature of the proposed discharge site. The primary concern about fill dis-
posal is loss of wetlands. Besides recommending denial, the Region can
propose location or operation modifications to reduce environmental impacts.
Mitigation to offset unavoidable impacts is coordinated with the applicant
and, when appropriate, is required for permit approval.(66J) Although loss of
wetlands due to permitted fill disposal is considered a serious issue, Federal
and State personnel expressed more concern about dredged material disposal.
A.1.3.2 National Marine Fisheries Service (NMFS) and U.S. Fish and Wildlife
Service (FWS)
Under the Fish and Wildlife Coordination Act, 16 U.S.C. 661, et seq., any
Federal agency that proposes to modify or control any body of water must first
consult with NMFS, FSW and the head of the appropriate state agency. NMFS and
FWS review 404 applications for compliance with the Endangered Species Act, 16
U.S.C. 1531 et seq. Applications are routinely routed to these agencies as
part of Corps' public notice procedures. NMFS and FWS have the right to
elevate proposed permits under Section 404(q).
In its initial review of an application, the Corps makes a finding about
the proposed activity's impact on endangered species and their critical habi-
tat. If it is determined that there will be no impact, a statement to that
4-11

-------
effect is included in the public notice. The notice sent to NMFS and FWS
serves as a request for information on whether any listed species or any
species proposed to be listed may be present in the area of the discharge.
If the Corps finds that the proposed activity may jeopardize an endan-
gered species or adversely affect a critical habitat, formal consultation
procedures with NMFS or FWS are initiated by including a statement to that
effect in the public notice. An application must be denied if it cannot be
modified so as to eliminate any threat to endangered species on their critical
habitat.(66D)
4.1.3.3 Washington Department of Ecology (WDOE)
WDOE is the lead agency for the State on 404 applications. WDOE coordi-
nates review by seven agencies, issues the State response and reviews applica-
tions for water quality certification and coastal zone concurrence. In addi-
tion to WDOE, 404 applications are reviewed by the Departments of Fisheries,
Game, Natural Resources, Social and Health Services, and Transportation, the
Parks and Recreation Commission and the Office of Archeology and Historic
Preservation for issues within their various areas of jurisdiction. Any of
these agencies may offer comments and objections, but only WDOE, WDF and WDG
can stop a project.
WDOE can stop a project by denying water quality certification or coastal
zone concurrence. WDF and WDG can stop a project by denying issuance of an
hydraulic project approval (see Section 4.1.3.4). If other State reviewers
voice objections that cannot be reconciled, WDOE must base the State response
on its best judgment. Occasionally, projects are approved over objection. If
agencies fail to comment within the allotted time without a legitimate reason,
their right to comment is waived. The State response will recommend denial if
HPA, water quality certification or coastal zone concurrence is denied.
Denial is generally based on water quality grounds.(660)
The WDOE 404 permit coordinator in the Operations Management Division of
the Office of Operations and Enforcement routes an application to reviewers
4-12

-------
and coordinates responses. Within WDOE, applications are reviewed by the
Environmental Quality Section of the Operations Management Division in the
Office of Operations and Enforcement, the Shorelands Management Section of the
Shorelands Division in the Office of Land and Water Resources; and the Water
Quality Management and Planning Section of the Water Quality Management Divi-
sion in the Office of Water Quality Management (see Figure 3-4). In certain
cases, WDOE regional personnel take part in the reviews. As review criteria,
WDOE uses State water quality standards (WAC 173-201), Federal 404(b)(1)
guidelines and other case-specific policies.(66M,0)
In. some cases, the State requires more information than the applicant
must furnish the Corps. Unless there is reason to believe contamination is
present, the Corps does not require any analysis of sediment proposed to be
dredged and discharged; the Corps only requires that the type and composition
of sediment be specified. WDOE requires chemical analysis of sediment to be
dredged when discharge is proposed whenever contamination is suspected. The
State will specify how many core samples to take, at what depth each sample
should be taken, and what substances should be analyzed in each sample. WDOE
can require operation modifications and monitoring on projects where problems
are suspected.(660)
Conditions to the water quality certification or coastal zone concurrence
required by WDOE are included in a 404 permit only if deemed essential by the
Corps. The Corps encourages negotiation and execution of separate applicant/
agency agreements containing all conditions thought necessary by those agen-
cies. Although the Corps permit references separate agreements which bind an
applicant, these agreements must be enforced by the signatory agencies.(660)
4.1.3.4 Washington Departments of Fisheries (WDF) and Game (WDG)
WDF and WDG review 404 applications for conformance with hydraulic proj-
ect rules, WAC 75.20.100, designed to protect fish life. WDF has jurisdiction
over non-game fish, while WDG has jurisdiction over game fish. The agencies
jointly administer the hydraulic project approval (HPA) program.
4-13

-------
Hydraulic projects are defined as construction or other work that will
use, divert, obstruct or change the natural flow or bed of any river or
stream, or that will utilize any waters of the State, or materials from the
stream beds. Every hydraulic project must have an hydraulic project approval.
The Corps public notice is deemed an application for a HPA. Processing
time is generally within 30 days of receipt of an application, unless more
information or a field evaluation is necessary. The HPA may contain such
general, technical and special provisions as are deemed necessary to protect
fishery resources. A HPA will be denied if a project is determined to be
directly or indirectly harmful to fish life unless adequate protection, miti-
gation or restoration can be assured.(55) If the HPA is denied, WDOE will
issue a negative State response and the 404 application must be denied.(660)
Whether a HPA is required for the discharge of dredged material as dis-
tinguished from the dredging is a matter of interpretation that has not yet
been clarified. Due to the fact that Corps procedure requires one application
to include both dredging and the disposal of the dredged material, dredged
material disposal is reviewed for HPA purposes along with dredging.(66E)
4.1.3.5 Washington Department of Natural Resources (DNR)
Among other responsibilities, DNR manages 1,300 miles of tidelands, 6,700
acres of constitutionally established harbor areas, and 2,000 square miles of
marine beds of navigable waters. Tidelands, shorelands and beds of navigable
waters may be leased by DNR to the general public.
The open water dredged material disposal sites in Puget Sound are managed
and leased by DNR. DNR requires notice of an intended use five days prior to
the use, if it is a first use, to allow an on-site visit with the discharger
to confirm site location. Otherwise, notice is required 24 hours prior to
use. There is a $300 minimum fee for use of a disposal site and an additional
charge of ten cents per cubic yard if over 3,000 cubic yards are discharged.
The Corps is not charged and other public agencies pay only the minimum fee.
DNR will not lease use of a dredged material disposal site unless all required
4-14

-------
Federal, State and local permits and authorizations have been granted to the
discharger.(54)
DNR also charges a fee for dredging in State-owned beds of navigable
waters, tidelands and shorelands. The removal of rock, gravel, sand and silt
is considered a resource withdrawal. The fee is based on the fair market
value of the land used plus the actual value of quantifiable public resource
elements withdrawn. Public agencies are not charged.(54)
4.1.3.6 Local Shoreline Management Agencies
The Shoreline Management Act, RCW 90.58, is the basis for the State's
coastal zone management plan. Among other things, it grants cities and coun-
ties the authority to regulate activities within their jurisdiction such as
dredging, and discharge of dredged or fill material, that take place on State
submerged lands within Puget Sound. As a result, applicants for 404 permits
must obtain a local shoreline management permit from the city or county with
jurisdiction over the area in which the proposed activity is to take place.
It is important to note, however, that a local permit is issued for dredging
or filling but not for open water disposal of dredged material. Local permits
for dredged material disposal sites are sought and held by the State Depart-
ment of Natural Resources. Recently, in the first case of its kind, the Mason
County shoreline agency Issued DNR a permit for an open water dredged disposal
site that attempted to control the quality of material discharged to the site.
The permit contained a condition that DNR notify the County of scheduled dis-
charges so that the County could decide on a case-by-case basis whether dis-
charge of the material would be allowed. Although the permit was vacated for
other reasons, the State Shorelines Hearing Board found that the County has
the right to attach special conditions to a disposal site permit to control
the quality of the site.(58) The selection, authorization and management of
open water dredged disposal sites are discussed at length in Section 6 of this
report.
The local permitting process for approval of dredging or filling activi-
ties generally takes more time than the 404 process; the Corps advises appli-
cants to begin the local process well in advance of the date the proposed
4-15

-------
activity is tentatively scheduled to begin.(66Q) The local permitting pro-
cess takes place apart from the 404 process, but WDOE will take the local
process into account when reviewing a 404 application for coastal zone con-
sistency.(66U)
The local permitting process begins with an application and an environ-
mental checklist. The environmental checklist is used to determine whether an
environmental impact statement (EIS) is required under the State Environmental
Policy Act, RCW 43.21C. Environmental impact statements are discussed in
Section 4.1.5.
Upon submitting an application, the applicant must publish public notice
in the local newspaper twice, with the notices appearing a week apart. During
this time, within 15 days of submission of the application and checklist, the
local agency determines whether an EIS under SEPA is required. If not, the
local agency sends notice to that effect to other State or local agencies with
jurisdiction over some aspect of the proposed activity. Those agencies have
15 days to review the finding.(59)
If an EIS under SEPA is not required, final action may be taken by the
local agency 30 days after submission of the application, although there is no
set time within which it must act. The applicant, WDOE and the State attorney
general must be notified of final action. The applicant and all interested
parties in disagreement with the final action have 30 days to seek certifi-
cation of review from WDOE to appeal to the Shorelines Hearing Board. The
Shorelines Hearing Board is an administrative appeal body created by the
Shoreline Management Act. A Board decision may be appealed to Superior Court,
as may any request for review not certified. If a permit is approved without
appeal, the applicant may proceed with the proposed activity 45 days after
WDOE receives notice of final action.(59)
4.1.4 Public Input
Public notice of a 404 application is issued by the Corps within 15 days
after receipt from the applicant of all necessary information. Copies are
4-16

-------
posted in post offices or other public places in the vicinity of the site of
the proposed activity and are sent to appropriate city and county officials,
State and Federal agencies, adjoining property owners, concerned business
and conservation organizations, the local news media and other interested
parties.(16)
The notice must identify the applicant and where additional information
may be obtained, and describe the nature and location of the proposed activ-
ity. A list of other government authorizations obtained or requested by the
applicant must be included. The notice must state that any person may request
that a public hearing be held. A description of the factors on which deci-
sions are based is also included.(16)
Thirty days are generally allowed for public comment. At least 15, and
as many as 60, days from the date of mailing may be allowed. Public hearings
are held at the discretion of the district engineer. He may attempt to re-
solve informally any material issues raised in a hearing request, or set a
time and place for a hearing. Requests for a hearing must be granted unless
the district engineer determines that the issues raised are insubstantial. In
cases of doubt, the presumption is in favor of a hearing.(16)
The notice required for State water quality certification is transmitted
with the Corps notice. A standard WDOE form entitled "Notice of Application
for Water Quality Certification" is included by the Corps in its public
notice. Written comments received within 20 days of publication of notice are
accepted.(56) Public notice is not required for a WDF/WDG hydraulic project
approval or a DNR public lands lease.
4.1.5 Environmental Impact Statement (EIS)
An EIS under the National Environmental Policy Act (NEPA) or the State
Environmental Policy Act (SEPA) may be required. An EIS under NEPA is re-
quired for major Federal actions that may significantly affect the quality of
the environment. As discussed in Section 5 of this report, the 404(r) exemp-
tion for a Federal project authorized by Congress is available only if an EIS
is prepared that discusses the requirements of the 404(b)(1) guidelines.
4-17

-------
Where Federal agencies are not involved, an EIS may be required under
SEPA if a proposal will have significant adverse environmental effects.
Significance is determined on the basis of a standard State-wide environmental
checklist (see Appendix B), completed by an applicant in conjunction with a
State or local permit application.
If an agency, such as a port authority, is the applicant, it is the lead
agency for the EIS. In cases involving private applicants, the lead agency is
the city or county from which a permit must be acquired. If a city or county
is not involved, and permits must be obtained from more than one State agency,
WDOE is the most likely lead agency. In a 404 situation, the local shoreline
management agency is almost certainly the lead agency because activities
taking place within and along the Sound are governed by and must comply with
local coastal zone master plans.(13)
The lead agency reviews the environmental checklist and determines the
significance of the proposed activity within 15 days. If a declaration of
nonsignificance is issued, other agencies with jurisdiction over the proposed
activity have 15 days to respond. Another agency with jurisdiction may assume
lead status by issuing a notice to that effect with a declaration of signifi-
cance.^^)
If the proposed activity is deemed significant, a declaration of signifi-
cance is issued and an EIS is required unless the proposal can be modified to
eliminate significant adverse effects. Each State and local agency has
adopted its own rules, consistent with the State guidelines, to implement
SEPA, WAC 197-10. If the rules of the lead agency allow it, an EIS may be
prepared by the applicant under the direction of the lead agency. Otherwise,
the EIS is prepared by the lead agency.(13)
The focus of an ElS is upon assessment of Che adverse impacts that may
result from the proposed activity or its alternatives, and analysis of
measures that may be taken to mitigate or eliminate those adverse Impacts. A
draft EIS must be issued to State and Federal agencies with jurisdiction over
4-18

-------
the proposed activity, and to cities and counties where adverse effects may
occur. Reviewing agencies have 35 days to respond. Notice to the general
public is encouraged but not required, and a hearing may be held.(WAC 197-10-
450)
If no critical comments are received, the draft EIS becomes the final
EIS. Otherwise, the lead agency must prepare a final EIS within 75 days of
issuance of the draft. The final EIS or an accompanying document must sum-
marize and respond to critical comments, and be circulated to the agencies
that received the draft.(13)
Where an EIS is prepared under NEPA and an EIS is also required under
SEPA, the SEPA EIS will not be required if the NEPA EIS is considered adequate
by the lead agency. If a NEPA EIS is considered inadequate by the lead
agency, the lead agency may modify or supplement it, or prepare an independent
draft EIS under SEPA.(13)
4.2 OBSTACLES TO DECISION-MAKING
This section describes the technical, administrative and statutory or
regulatory obstacles to the 404 decision-making process. Section 4.3 contains
conclusions.
4.2.1 Technical Obstacles
Two separate but closely related technical obstacles affect 404 decision-
making. One obstacle is lack of data on some materials proposed to be
discharged. The other is lack of criteria on which to judge the environmental
significance of discharges.
Acceptability of material, for water disposal is determined by application
of the 404(b)(1) guidelines to information submitted by the applicant. The
guidelines do not expressly require applicants to submit sampling information
on materials proposed to be discharged unless the Corps has reason to believe
the materials are contaminated. As a result, whether contaminants are present
in discharged material is unknown in the majority of cases, and decisions to
allow discharges are based on "best professional judgment (BPJ).
4-19

-------
In cases where problems are suspected, WDOE and EPA have taken the lead
in requesting sampling information. However, there are no State water quality
standards for priority pollutants and no sediment criteria for use in the 404
decision-making process. In short, there is a lack of criteria with which to
determine sampling needs; there is no sampling rationale. Thus, even when
sampling is required, decisions on what to sample for and what the samples
mean are based solely on best professional judgment.
The absence of a sampling requirement in the majority of cases and the
reliance on BPJ allow greater flexibility in application of the guidelines.
Still, such flexibility has drawbacks; it creates a potential for arbitrary,
inconsistent application of the guidelines. Also, the effectiveness of BPJ
depends substantially on the technical competence of the personnel determining
acceptability.
To understand the significance of environmental impacts of dredged or
fill material discharged into Puget Sound, the relationship between con-
taminants in discharged material and the availability of those contaminants to
aquatic organisms must be more clearly established. The link between con-
taminant loading rates, exposure fields in the water column, partition rates
from the water column to the sediment and rates of resuspension must be better
understood and translated to toxicity thresholds for Informed, consistent 404
decision-making.
4.2.2 Administrative Obstacles
Two administrative obstacles to the 404 decision-making process were
cited. The most universally cited obstacle Is lack of personnel, both
secretarial and professional, to process applications.
The other administrative obstacle cited by the Corps is delay in the
permitting process. The Corps is concerned about delays because it is con-
strained by 404(q) to process applications within 90 days, to the extent
practicable. Delay is most likely to be caused by local permit processing and
4-20

-------
is also caused by requests for further information on materials proposed for
discharge.
The Corps is criticized for requiring insufficient information, but there
seems to be a tacit agreement between the Corps, Region X and WDOE that review
of most 404 applications requires no further information than is requested.
The Corps maintains that it requests all the information that is required
under 404 and the guidelines. While Corps personnel grant that some cases
require further information and are too complex to be processed within 90
days, the Corps' basic orientation may lean more toward facilitating anchorage
and navigation than preventing undesirable environmental impacts.
As for delays caused by the local shoreline management permitting
process, a recent report for WDOE recommends that some streamlining of pro-
cedures is in order. The report suggests that WDOE should take the lead in
setting up an interagency working group to clarify responsibilities in cases
of overlapping Federal, State and local jurisdiction, and develop streamlined
permit processes.(18)
Waiver of State water quality certification after 60 days is a potential
obstacle to 404 decision-making, especially because WDOE seems to conduct the
most in-depth reviews. However, the Corps' Seattle district has never con-
sidered a water quality certification waived. WDOE routinely notifies the
district within 60 days of any delay in its review or in the reviews of the
seven other State agencies that are coordinated by WDOE. The district has
always granted the extensions required. Generally, WDOE personnel find the
Corps' Seattle district to be responsive to their concerns.
4.2.3 Statutory or Regulatory Obstacles
The 404(b)(1) guidelines on acceptability of material for discharge are
currently undergoing review at EPA headquarters in an effort to simplify them.
While simplicity may provide desired flexibility, the lack of an attendant
sampling rationale is considered an obstacle to informed 404 decision-making.
For example, there are no standard tests for sediment that establish the link
4-21

-------
between material deposited and its availability and toxicity to aquatic
organisms. Similarly, monitoring of dredging and of dredged or fill material
discharges is rarely requested because there are no standards to determine
monitoring needs. Sediment criteria and State water quality standards for
priority pollutants should be addressed in the guidelines or associated
guidance.
The guidelines do not require monitoring of the effects of dredging or of
dredged or fill material disposal. Although WDOE occasionally requires
monitoring of discharges, neither it nor any other State, Federal or local
agency has taken a strong role in overseeing discharges and site monitoring.
As discussed in Section 6, disposal sites are managed by DNR under locally
issued shoreline management permits. DNR leases sites for use but monitors
only on a spot-check basis. The monitoring gap may be overcome by an expan-
sion of DNR's site management role, currently under consideration.
Increased site monitoring could also be required of DNR or its leasee by
local shoreline management agencies through conditions pieced in the disposal
site permit. As discussed in Section 4.1.3.6, the recent attempt by Mason
County to condition a disposal site permit so as to control the quality of
material discharged may be a step in the direction of site monitoring. In the
extreme, however, local control could lead to allowance of local dumping only.
A stronger State or Federal role may be in order.
In addition, the absence of a Federal, State or local program to ensure
adequate upland disposal sites for materials that are not acceptable for water
disposal establishes a de facto presumption favoring discharge. JRB did not
evaluate the availability of upland disposal sites, but Federal and State
personnel agree that unless a material proposed to be discharged is known to
be highly contaminated, it is likely to be discharged to the Sound simply
because there is nowhere else to put lt.(66J, 0) Establishment of a program
to ensure adequate upland disposal capacity should be a high regulatory
priority.
4-22

-------
4.3 CONCLUSIONS
Overall, the 404 process is fairly well streamlined in its operation, but
decisions may be based on inadequate standards and data. Water quality stan-
dards for priority pollutants and sediment criteria should be addressed in the
404(b)(1) guidelines or associated guidance. A sampling rationale must be
developed.
In addition, no agency has taken a strong role in overseeing discharges
and site monitoring. This gap should be addressed by the guidelines or by
State and local agencies.
Finally, the absence of any program to ensure adequate upland disposal
sites establishes a de facto presumption in favor of water disposal. Rectify-
ing this imbalance should be a high regulatory priority.
4-23

-------
5. THE EAST, WEST AND DUWAMISH WATERWAYS
NAVIGATION IMPROVEMENT PROPOSAL
The East, West and Duwamish Waterways navigation improvement project
refers to the proposed deepening of the Federal navigation channels of the
lower Duwamish River waterways in Seattle to allow deep-draft vessels better
access and improved safety. This proposed dredging project will not follow
the typical 404 permit process described in Section 4 of this report because
it is exempted under Section 404(r) of the CWA.
The Duwamish Navigation Improvement Study was specifically authorized by
Congress. As such, any resulting discharge of dredged material does not
require a permit under Section 404 of the CWA as long as an environmental
impact statement (EIS) under the National Environmental Policy Act is sub-
mitted to Congress before the commencement of construction-related discharges
and prior to authorization of the project or appropriation of funds for it.
Environmental analysis according to the 404(b)(1) guidelines is still required
as part of the EIS process. An EIS is required for a 404(r) dredging proposal
even before it actually becomes a Congressionally authorized project.
This section outlines the decision-making process on this navigation
improvement proposal, including (1) the steps that have been taken to get from
the stage of a "study" to the stage of a "proposed project," and (2) the steps
needed to get the proposed project to the stage of a real construction
project.
To provide background on the proposed project, the following material
draws extensively from the "Final Feasibility Report and Final Environmental
Impact Statement" (January 1983) prepared by the U.S. Army Corps of Engineers,
Seattle District.(67)
5.1 BACKGROUND AND DESCRIPTION
As stated in the EIS and Feasibility Report, the Duwamish project had its
genesis in a study resolution sponsored by Senator Warren G. Magnuson and
adopted by the Senate Public Works Committee on May 18, 1956. The resolution
5-1

-------
directed the Corps of Engineers to review previously prepared reports on
Seattle Harbor development, with particular reference to the advisability of
improving the Duwamish Waterway.
In September 1978, the Port of Seattle and City of Seattle requested that
the Corps of Engineers study the feasibility of enlarging and extending the
Federal navigation channels for Seattle Harbor. The existing authorized
channel dimensions were approved by Congress in 1935. However, with the in-
crease in vessel size since then, the waterways have become too narrow and too
shallow for safe passage by many of the larger, more cost-effective vessels
now in use. Also, the EIS indicates that more vessels are using the Harbor
area. It found that the Seattle Harbor total commodity tonnage increased 9.5
percent from 1975 to 1977 and 36 percent from 1977 to 1978. Between 1969 and
1978, the tonnage of commodities shipped through the East, West, and Duwamish
Waterways grew at an average annual rate of 3.7 percent. This growth is pro-
jected to continue at an average annual rate of 2.8 percent to the year 2000,
whether or not the existing channel is enlarged. According to the EIS (67),
the Port has accommodated this growth through major redevelopment of existing
outer harbor terminals for more intensive use.
With the outer harbor facilities nearing full capacity, the existing
Federal navigation channel is the main area available for more intensive use.
However, inadequate depths in the channel have resulted in such inefficient
shipping practices as loading only partially, waiting for favorable tides, and
using smaller, less cost-efficient ships. Restricted channel widths, particu-
larly in the lower Duwamish Waterway, are also a navigation and safety prob-
lem. In June 1978, the dry-bulk carrier ANTONIO CHAVEZ collided with a sup-
porting pier of the Spokane Street Bridge, causing permanent disablement of
the drawspan mechanism and disruption of land traffic. The Port desires im-
provement of the channel so that the current and projected growth can be
handled more safely and cost-effectively.
In response to the Congressional resolution and the Port of Seattle's
request, the Seattle District, U.S. Army Corps of Engineers prepared the
Feasibility Study (67), herein excerpted, to report to Congress on the need
5-2

-------
for, and feasibility of, improving and extending the existing Federal navi-
gation channels. The Feasibility Report determined that there was a need for
improvement of the navigation channels in the Duwamish and that the project
was feasible.
During the study of navigation needs and problems, a number of possible
solutions were considered. Alternatives considered in detail were no action
and improvement of the Federal navigation channel. The no-action plan would
result in continuation of present growth trends in the area. The non-
structural plan would increase navigation safety but not improve navigation
efficiency.
Technical studies and agency and public input indicated that the public
interest would best be served by a plan involving a moderate enlargement of
the existing channels on the East, West, and lower Duwamish Waterways and
replacement of the Burlington Northern railroad bridge. The recommended plan,
as outlined in the Feasibility Report (67), includes the following specific
actions:
•	Deepening the authorized channel on the East and West Waterways from
34 to 39 feet
•	Narrowing the authorized channel on the East and West Waterways from
750 to 500 feet (to permit ship berthing outside of the Federal
channel)
•	Enlarging the authorized lower Duwamish Waterway (downstream of First
Avenue South Bridge) from 200 feet wide by 30 feet deep to 250 feet
wide by 39 feet deep
•	Replacing the Burlington Northern railroad bridge over the lower
Duwamish Waterway to provide a minimum channel clearance of 250 feet
•	Deepening of Turning Basin No. 1 at the head of Harbor Island
•	Deauthorizing of the unneeded Turning Basin No. 2 upstream of the
First Avenue South Bridge
•	Filling the area between Piers 90 and 91 at South Cove in Elliott Bay
with all dredged materials found to be contaminated (assumed for plan-
ning purposes to be the upper three feet of sediment or 1.1 million
cubic yards)
5-3

-------
•	Disposing of dredged material that is found suitable for open water
disposal (approximately 1.4 million cubic yards) at the Fourmile Rock
Site just outside of Elliott Bay. Suitability will be determined by
WDOE, EPA, and the Corps after considering water quality standards and
the 404(b)(1) criteria
•	Mitigating 2 acres of shallow-water/intertidal habitat that would
otherwise be lost due to channel enlargement on the lower Duwamish
•	Mitigating 2 acres of shallow-water habitat that would otherwise be
lost through disposal of dredged material at Piers 90 and 91
•	Mitigating lost deepwater habitat at Piers 90 and 91 via artificial
reef construction comparable to fish productivity lost
•	Increasing public access to the navigation channel and river
environment through provision of a small boat ramp
•	Increasing salmon rearing/reeding habitat by constructing an addi-
tional 2 acres of shallow-water/intertidal habitat as enhancement.
Federal responsibilities include initial and maintenance dredging of the
improved navigation channel as well as sharing costs with local sponsors
according to cost sharing authorities. The Port of Seattle will be local
sponsor for the entire project, including channel enlargement, some mitiga-
tion features, and for a public access boat ramp added in response to
expressed public interest. The local sponsor also provides lands required for
channel enlargement, dredged material disposal sites, and utility relocations.
The Port will also share in bulkheading and public access costs and would
dredge their vessel berthing areas to depths commensurate with the enlarged
channel. The Muckleshoot Indian Tribe, which has treaty fishing rights in the
Duwamish River, will sponsor and share the cost of fishery enhancement
features. The replacement cost of the Burlington Northern railroad bridge
would be shared between the bridge owner and the Federal Government. A
diagram of the project area is shown in Figure 5-1.
The EIS places the total cost of the plan at $50,400,000 (October 1981
price level). This includes approximately $20,550,000 for channel enlarge-
ment, $1,219,000 for berth dredging by local interests, $23,761,000 for rail-
road bridge replacement, $3,420,000 for mitigation, $300,000 for increased
public access, and $1,150,000 for salmon fishery enhancement.
5-4

-------
DREDGE
WDE. 31 FT.
*12—«
l_n
i
Ul
ELLIOTT
BAY
INSET
BELOW
I

watch**!
R»»c
K(D>|i

Avi S BrH«e
DEAUTHORQE
TURNING BASM
UPSTREAM UMIT OF
EXISTM6 FEDERAL PROJECT-
DREDGE TO 250 FT. WIDE, 39 FT. DEEP
-1st Avi S
\
_ REMAMM6 SOUTH
£ SPAN (TO BE
REMOVED BY
OTHERS)
WATERWAY
RELOCATE
RA1ROAD BRD6E
SCALE IN FEET
too o	5oo
DREDGE TO 39 FT. DEEP
PKEON POMT REACH
INSET
ADD NEW
PUBLIC ACCESS
Autfcarize4 Settling Basin
Head of Navigation
CONSTRUCT SHALLOW WATER
HABITAT FOR FISHERY
MITIGATION AND ENHANCEMENT-
LEGEND
PROPOSED CHANNEL ENLARGEMENT
BULKHEADS
RIPRAP SLOPE PROTECTION
SCALE IN FEET
EAST. WEST AND DUWAMISH WATERWAYS
NAVIGATION IMPROVEMENT STUDY
PROPOSED NAVIGATION IMPROVEMENTS
SEATTLE	WASHINGTON
PLATE 2
Figure 5-1. PROPOSED NAVIGATION IMPROVEMENT PROJECT: from Reference 67

-------
Average annual costs over the project life, Including average annual
increased maintenance costs and interest during construction, are estimated in
the EIS at $4,275,000 and the average annual benefits would be $10,078,000,
resulting in a benefit-to-cost ratio of 2.4 to 1.
5.2 THE DECISION-MAKING PROCESS
This section outlines the agencies involved and their roles. It also
presents relevant procedures, timing and criteria. Obstacles are discussed in
Section 5.3.
5.2.1 The Agencies Involved
This subsection describes the main agencies and their responsibilities in
the process of developing this proposal.
5.2.2.1 The U.S. Army Corps of Engineers
The Corps of Engineers is responsible for water resources development as
part of the Federal Civil Works Program. The Corp undertakes survey investi-
gation and other feasibility studies authorized by specific legislation or by
resolution of the House Public Works and Transportation Committee or the
Senate Environment and Public Works Committee.
The Corps of Engineers first received responsibility for civil works with
an Act of Congress in 1824 for the improvement of rivers and harbors for navi-
gation. Later legislation expanding Corps responsibilities Includes:
•	Establishment of the Board of Engineers for Rivers and Harbors, 1902
•	The River and Harbor Act of 1899 (33 USC 401 e£. seq.) established
regulatory control over waters
•	The National Environmental Policy Act of 1969 (Public Law 91-190)
required preparation of an environmental impact statement to accompany
every recommendation or report on legislative proposals or other major
Federal actions that significantly affect the quality of the environ-
ment
•	The River and Harbor and Flood Control Act of 1970 (P.L.-91-611)
directed the Secretary of the Army to promulgate guidelines for
5-6

-------
consideration of economic, environmental, and social effects of
proposed projects
•	The Water Resources Development Act of 1974 (P.L.-93-251) established
a two-phase authorization procedure for major projects
•	The Federal Water Pollution Control Act of 1972 and the Clean Water
Act amending it in 1977 give the Corps primary responsibility for
permits for discharges of dredged or fill material into waters of the
United States under Section 404. Section 404(r) allows Congressional-
ly authorized projects to be exempted from permitting requirements, if
an EIS and 404(b)(1) evaluation are prepared before the project is
authorized.
These and other acts have made the Corps' participation in areas of water
resource management more comprehensive and changed public policy toward con-
sideration of environmental and social objectives in resource planning and
development activities.(48)
The Assistant Secretary of the Army for Civil Works works with the Chief
of Engineers in planning, directing and controlling the Corp of Engineers.
Civil works functions of the Corps are supervised by the Director of Civil
Works within the Office of the Chief of Engineers. Other Boards and Commis-
sions advise and support the Chief of Engineers directly.(48)
The bulk of the civil works program assigned to the Chief of Engineers is
delegated to field offices. U.S. Army Engineer Divisions have jurisidiction
over specified geographical areas and responsibility for administering the
Corps mission involving civil works planning, engineering, construction, oper-
ation, and maintenance. Divisions also supervise U.S. Army Engineer Districts
by reviewing major plans and programs. Districts in turn are the principal
planning and Implementation offices responsible for preparing water resource
needs and development studies in response to Congressional resolutions. Dis-
tricts also prepare engineering and design studies and construct, operate and
maintain civil works facilities.(48)
Within this legislative and organizational framework,- the Seattle
District of the Corps of Engineers is reponsible for the Duwamlsh Navigation
5-7

-------
Improvement project. The basic organization of the Seattle District is shown
in Figure 5-2 in relation to other organizational groups.
5.2.2.2	The Port of Seattle
The Port of Seattle is a port district authorized to acquire, construct,
maintain, and operate all forms of transfer and terminal facilities for land
and water transportation. Port commissions are elected, have taxing author-
ity, and may issue bonds to support industrial development districts estab-
lished within their boundaries. Port districts are politically and finan-
cially independent of other local governments and they can have a substantial
impact on development of a region's shoreline.(3)
As the local sponsor for the Duwamish Project, the Port will have
responsibility for acquiring land to provide dredged material disposal area
and sharing other costs. The Port will have financial decisions to make later
in the process. However, it is not a regulator and is not discussed in great
detail in this report.
5.2.2.3	Other Agencies
Through the NEPA review and public notice process, the Corps must consult
with a variety of agencies. The statutes and agencies that are relevant to
this project are introduced briefly below. The agencies' comments and con-
cerns about this project are presented in Section 5.2.3.
t Clean Water Act of 1977, (Federal Water Pollution Control Act Amend-
ments of 1972) 33 U.S.C. 1251 et_. seq. Evaluation of the effects of
the discharge of dredged or fill material Into waters of the United
States, including consideration of the Section 404(b)(1) Guidelines
must be included in an EIS prepared for all Corps actions where the
recommended plan or approved project involves the discharge of dredged
or fill material into waters of the United States. This procedure
will satisfy Section 404(r) of the Act, upon submittal of the EIS to
Congress, in lieu of issuing a public notice and obtaining a State
water quality certificate.
• Coastal Zone Management Act of 1972, as Amended, 16 U".S.C. 1451 et.
seq. Proposed Corps projects and activities significantly affecting
land or water uses in the coastal zone of a State must be coordinated
5-8

-------
(OTHER OFFICES NOT SHOWN)
(OTHER DIRECTORATES NOT
SHOWN)
(OTHER DIVISIONS
NOT SHOWN)
(OTHER DISTRICTS
NOT SHOWN)
SEATTLE
DISTRICT
CONSTRUCTION
DIVISION
(OTHER
BRANCHES
NOT
SHOWN)
(OTHER
SECTIONS
NOT
SHOWN)
OPERATIONS
DIVISION
DIRECTORATE
OF
CIVIL WORKS
DEPUTY CHIEF
OF ENGINEERS
PLANNING
BRANCB
PERMITS
UNIT
NAVIGATION AND
COASTAL PLAN-
HING SECTIOH
REGULATORY
FUNCTIONS
BRANCH
ENVIRONMENTAL
RESOURCES
	SECTION
ENGINEERING
DIVISION
BOARD OF ENGINEERS
FOR
RIVERS AND HARBORS
NORTH PACIFIC
DIVISION
(PORTLAND, OREGON)
CHIEF
OF
ENGINEERS
FIGURE 5-2
U.S. ARMY CORPS OF ENGINEERS
ABRIDGED ORGANIZATION
5-9

-------
with the WDOE and determined to be consistent with the State's Shore-
line Program.
•	The Fish and Wildlife Coordination Act, 16 U. S.C. 661 ejt. seq.
requires coordination with the appropriate Regional Director of the
Fish and Wildlife Service (FWS), the appropriate Regional Director of
the National Marine Fisheries Service (NMFS) and the head of the agen-
cies responsible for fish and wildlife for the state.
•	The Estuary Protection Act (16 U.S.C. 1221 et. seq.) requires EISs for
projects affecting estuaries and their natural resources to be circu-
lated to the Department of the Interior for review and comment.
•	The Federal Water Project Recreation Act (16 U.S.C. 460-1-12 e£. seq.)
requires consideration of opportunities for outdoor recreation an<3
fish and wildlife enhancement by the Department of the Interior.
•	The Endangered Species Act of 1973, as Amended, 16 U.S.C. 1531 et.
seq., requires coordination with the appropriate Regional Director of
the Fish and Wildlife Service (FWS) and/or National Marine Fisheries
Service (NfMFS) to determine if any listed endangered or threatened
species or species proposed for listing or their critical habitat may
be present in the area of the proposed action.
•	Clean Air Act, as amended, (42 U.S.C. 7609). The Regional Adminis-
trator of EPA must review EISs from the standpoint of public health or
welfare or environmental quality under Section 309 of the Act and the
determinations and findings required by Section 176(c) of the Act to
assure conformity with the State implementation plan (SIP).
•	The Preservation of Historical Archeological Data Act of 1974 (16
U.S.C. 469 e£. seq.) requires coordination with appropriate State his-
toric preservation officers, the Heritage Conservation and Recreation
Service, the Advisory Council on Historic Preservation, and other
groups with cultural resources expertise.
•	Two local agencies, the City of Seattle and King County, will also be
involved during the final stages of the project. In Washington,
shoreline management permits must be obtained from local governments
before construction of projects in the coastal zone. The State Shore-
line Management, which authorized the shoreline permit program, is
explained in detail in Section 6. Specific local permitting pro-
cedures for the City of Seattle are explained In Section 7.
The general public and Indian Tribes also become involved in the EIS
review process and can have an impact. The Duwamish project as described in
Section 5.1 includes some features designed to mitigate the concerns of the
Indian Tribes, the public, and the Fish and Wildlife Agencies.
5-10

-------
5.2.2 Procedures, Timing and Criteria
The Duwamish Navigation Improvement Project is well along in the deci-
sion-making process. This section outlines the entire process so that present
and future events can be understood in light of past decisions. Figure 5-3 is
a flow chart of this process.
This decision-making process was initiated partially because Congress
passed a resolution in 1956 allowing the Corps to study and provide recommen-
dations for the Seattle Harbor Area. Studies were undertaken and proposals to
widen and deepen the Duwamish Waterways were made early in the 1970s. These
early proposals languished because the perceived benefits of the project were
counter-balanced by the high cost of bridges and related structures, which
would have to be replaced at the expense of local agencies. In 1978 the
cost-to-benefit ratio improved because Federal emergency relief funds became
available to replace the damaged Spokane Street Bridge. By letters in
September 1978, the Port and City of Seattle requested reactivation of the
study with the Port acting as local sponsor.(67)
When the Seattle District Office of the Corps began the most recent study
of navigation improvement in the Duwamish Waterways, a "Study Manager" from
the Navigation and Coastal Planning Section was assigned to coordinate all
aspects of the study. For a study of this type both a Feasibility Report and
an Environmental Impact Statement are required.
Feasibility Studies are required for Congressional authorizations as the
initial step in the planning process and are conducted in accordance with the
Engineering Regulations in the Corps of Engineers' Planning Guidance Notebook.
They are detailed studies concerning the need for and desirability of proposed
projects. These implementation studies focus on formulating a recommended
plan of action to meet long-term needs and alleviate problems. Studies
resulting in recommendations are documented in Feasibility Reports. In the
planning process, a Feasibility Study would be followed by advanced engineer-
ing and design and, finally, detailed plans and specifications, if the
proposed project were authorized.(48)
5-11

-------
FIGURE 5-3
CORPS OF ENGINEERS FLOW CHART FOR FEASIBILITY STUDT AND ENVIRONMENTAL
IMPACT STATEMENT ON MJWAMISH PROJECT
5-12

-------
Studies of this type are also governed by NEPA (42 U.S.C. 4371 seq.),
which establishes procedures to ensure that environmental information is
available to public officials and citizens before decisions are made. The CEQ
regulations for implementing NEPA (40 CFR 1500 e_t. seq.), are designed to
integrate environmental considerations early in the planning process and to
emphasize cooperative consultation among agencies. Normally, under the NEPA
process, an environmental assessment is done to determine whether an EIS is
necessary, but this is not done if the agency has already decided to prepare
an EIS. The Corps normally prepares an EIS for Feasibility Studies, operation
and maintenance activities, regulatory permits, and real estate actions.
Also, an EIS is necessary for a study of a proposal for a Congressionally
authorized 404(r) project. As the Corps is lead agency for EIS purposes, the
Corps' regulations found at 33 CFR 230 govern. The Feasibility Report and
EIS process are discussed together in this section.
Before initiating the study, the CEQ regulations require scoping to
determine the range of issues to be evaluated during the Feasibility Study and
EIS. A notice of intent to prepare an EIS was published in the Federal Regis-
ter and EPA's Regional Office was notified. In connection with civil works
planning activities, public meetings are required at various stages to advise
on the nature and scope of a proposed study, to present the results of prelim-
inary studies, and to present detailed findings and tentative recommendations
at later stages. The Corps held formally organized, announced, and recorded
public meetings and workshops in June 1980, July 1981, and July 1982. A
formal scoping meeting was also held.
After scoping, preparation of the draft EIS and Feasibility Report began.
Both reports are integrated into one document but are kept self-contained so
that they can be read and understood separately. An EIS is meant to serve as
an action-forcing device for decision-making, not just a disclosure'document.
To this end, a number of things must be considered during preparation of an
EIS. Corps regulations state that:
5-13

-------
•	Federal projects involving disposal of dredged material in navigable
waters at a specified disposal site must be evaluated by applying
404(b)(1) guidelines
•	If the 404(b)(1) guidelines alone would prohibit the disposal, the
Corps would also consider the effect that not disposing would have on
maintenance of navigation, including economic impacts
•	If the project involves periodic maintenance dredging, the 404(b)(1)
determination must also consider these future disposal needs
•	Dredged material will not be disposed of in wetlands unless the
benefits of disposal outweigh the damage to the wetlands
•	Disposal activities that affect the coastal zone must be evaluated to
ensure that they are consistent with the State Shoreline Master
Program "to the maximum extent practicable"
•	Federal projects under 404(r) do not need a Section 401 water quality
certification from the State if an EIS is submitted to Congress before
the actual discharge of dredged material
•	Related work in the same area must also be considered during planning
and review of the Federal project.
Other agencies' perceptions of how well the Corps addressed these considera-
tions are discussed in Section 5.2.3.
The' NEPA guidelines at 40 CFR 1500 specify the format and content of an
EIS, which must include among other things, discussions of the need for and
objectives of the action, alternatives, affected environment, environmental
effects, and a summary of major conclusions and findings, areas of contro-
versy, and unresolved Issues. Also, when information is lacking or uncer-
tainty exists, that must be clearly stated. After the draft report was pre-
pared, the District Engineer filed it with the EPA and sent public notices
to all parties who requested notices, to the U.S. Senators and Representa-
tives for the area, the Field Representative of the Secretary of the Interior,
the Regional Director of the Bureau of Sport Fisheries and Wildlife, the Re-
gional Director of the National Park Service, the Regional Administrator of
the Environmental Protection Agency, the Regional Director of the National
Marine Fisheries Service of the National Oceanic and Atmospheric Administra-
tion (NOAA), the head of the State agency responsible for fish and wildlife
5-14

-------
resources (WDF and WDG), the District Commander, U.S. Coast Guard, and the
Office of the Chief of Engineers. The EPA also publishes a weekly notice in
the Federal Register announcing all EISs filed during the week. The draft EIS
and Feasibility Report were distributed for a 45-day comment period in June of
1982.(67)
Federal agencies are required to respond as specifically as possible and,
if any object, they should describe alternative methodologies, additional
information needs, and mitigation measures they consider necessary to allow
granting of any applicable permit or license. At this point, agencies may
refer objections to the Council on Environmental Quality (CEQ) within 25 days
or people may request a public hearing. Neither of these happened in the
Duwamish project. If an agency does not respond, the Corps assumes there is
no objection. The Fish and Wildlife Coordination Act Report was also prepared
during this time and finalized in September 1982.(49)
After receiving this input, the District Engineer prepared a final EIS
that responded to all comments. Responses at this stage may include:
(1)	Modifying alternatives including the proposed action.
(2)	Developing and evaluating alternatives not previously given serious
consideration.
(3)	Supplementing, improving, or modifying the analyses.
(4)	Making factual corrections.
(5)	Explaining why the comments do not warrant further
response.(33 CFR 230)
The District Engineer's final EIS and Feasibility Report was dated
January 1983, and included the general plan outlined in Section 5.1. The
"final" document, which included both the EIS and Feasibility report, was sub-
mitted to the Division Engineer for review, approval, and transmittal to the
Board of Engineers for Rivers and Harbors. Following the normal NEPA process,
there would be a public notice at this stage. Although at this point the doc-
ument was available for public review and the EIS was identified as "final,"
5-15

-------
the Feasibility Report was still an interim document under COE review and
subject to revision because several levels of internal review remained.(66B)
The Brigadier General for the North Pacific Division in Portland con-
curred with the conclusions and recommendations of the Seattle District
Engineer in March of 1983. As the document goes up the chain of command, the
"reporting officer" prepares a report at each level. Reports of this type are
usually in letter form and are supposed to discuss:
•	Views of State and local authorities
•	Corps views concerning probable effects on:
-	Navigation
-	Marine life
-	Wildlife
Water quality
-	Coastal zone management plans
-	Persistence and permanence of the effects of pollutants on the
waterbody
-	Effect of volumes and concentrations of pollutants
-	Alternate disposal methods or pollutant recycling measures
•	Conclusions
•	Recommendations.(33 CFR 230)
These reports are usually prepared with substantial input from the Seattle
District, which started the process.(66B)
At this point, the Division Engineer sent the report to the Board of
Engineers for Rivers and Harbors and issued a public notice indicating that
comments could be sent to the Board. If the Board of Engineers' review and
action had resulted in major revisions to the proposed plan, an addendum for
alternatives described in the draft EIS or a supplement to the EIS for new
alternatives not previously considered would be prepared with the assistance
of the Seattle District.
5-16

-------
When the Board completed its review it made recommendations to the Chief
of Engineers. These recommendations were made public and the Board began
preparation of the proposed report of the Chief of Engineers. The Board of
Engineers concurred with the need for all points of the proposed plan but
recommended that the Federal government not participate in funding the pro-
posed mitigation measures.(66Q) This is consistent with the Corps' policy as
stated in the Digest of Water Resources Policies and Authorities.(48) The
policy on mitigation states that the Federal government is not normally
responsible for damages incidental to civil works activities within areas
subject to navigation servitude. Usually local interests are required to hold
the United States free from damages due to construction operation or mainte-
nance as a condition of project authorization. The Corps tries to prevent
damages to fish and wildlife resources through good planning. Measures to
offset unavoidable damages to fish and wildlife are included in projects only
when the costs are justified. Acquisition of lands or waters for this purpose
requires specific Congressional legislation. After construction, responsibil-
ity for operation and maintenance of mitigation features is usually designated
to the most effective agency through the authorizing legislation. Responsi-
bility for funding operation and maintenance rests with the responsible
agency.
At the beginning of September, the proposed Chief's report, together with
all previous reports, was submitted to the Governor of Washington and to all
Federal agencies at the headquarters level and filed with EPA for public
notice. The public notice period for the Feasibility Report is 90 days long
for all Federal agencies and the Governor. The public notice on the final
EIS, which was published October 7, 1983, is only 30 days long, per NEPA
guidelines, for all other groups and individuals with interest. Comments on
the EIS are due by November 7, 1983.
After the 90-day period, the proposed report of the Chief of Engineers
will be made final and a draft Record of Decision will be prepared with
assistance from the Seattle District. The Record of Decision will:
5-17

-------
•	State what the decision was
•	Identify all alternatives considered
•	State whether all practicable means to avoid or minimize environmental
harm have been adopted.(40 CFR 1505.2)
The Chief of Engineers will sign the final Feasibility report and EIS and
transmit it and all accompanying documents, including the draft Record of
Decision, to the Assistant Secretary of the Army for Civil Works. The
Assistant Secretary will send the package to the Office of Management and
Budget for review. A proposed letter to Congress will be included, but not
the draft Record of Decision. The Water Resources Council is supposed to have
a review at this point also, but funds were never provided for this func-
tion.(33 CFR 230)
After 0MB provides its findings to the Assistant Secretary of the Army,
the Assistant Secretary will sign the Record of Decision and transmit the
entire package to Congress. At the same time, the final Record of Decision
will be filed with EPA for public notice and copies will be available for
public review. This constitutes the final step in processing of Feasibility
Reports.
The local districts' study period ended when the report was sent to the
division, in January of this year. The next phase the proposed project would
enter is Continuation of Planning and Engineering (CP&E), or detailed design
studies. Under general authorities and the resolution, the District Office
can initiate some studies for this phase without specific Congressional
authorization. Congressional authorization and appropriation are needed be-
fore entering the plans and specifications stage.(66Q)
The Feasibility Study considered possibilities and made plans based on
assumptions. It was not meant to provide concrete answers and fixed project
activities. For example, sites for mitigation cannot be acquired for a
Feasibility Study. Nevertheless, some commentators felt that the Corps left
too many unanswered questions in this report.(66G,0,E) The Continued Planning
5-18

-------
and Engineering phase is meant to answer some of these questions. CP&E phase
studies include analyses to either reaffirm the basic planning decisions or to
reformulate the project to be responsive to changed needs. Initiation and
scheduling of these types of studies depend on the relative importance of the
project, local interest and cooperation, and availability of funds. Some
District funds have been obtained for fiscal year 1985.(66Q) Some of the
types of activities planned for CP&E for the Duwamish Project are:
•	Sampling and analysis of sediment cores to determine the depth of
contamination and the volume of spoil that must be accommodated
a Evaluating use of substrate that enhances benthic life along the
waterway
•	Selecting a location and design of the proposed artificial reef
•	Evaluating methods of containing contaminated materials at Pier 90/91
•	Planning and coodinating a monitoring program of chemical and biologi-
cal testing of the type and extent of contamination.(67)
Any reports developed during the next phase must go through an approval
process similar to that described for the Feasibility Study. If there is a
significant difference between the final project plans and the project evalu-
ated in the EIS, supplements or entire new statements may be needed, each re-
quiring a lengthy approval process. The average time for a Federal project to
move from initiation to construction is about 19 years. Construction for the
Duwamish project is not expected until the 1990s.(66Q)
5.2.3 Coordination With Other Agencies
Coordination of this proposed project has taken place through all
appropriate regulatory channels. In addition to Federal agencies, State and
local agencies were consulted, including:
•	WDOE
•	WDF
•	WDG
•	DNR
5-19

-------
•	Office of Archaeology and Historic Preservation
•	Washington Parks and Recreation Commission
•	City of Seattle
•	King County
•	Port of Seattle
•	Muckleshoot Indian Tribe.
Concerns over maintaining critical salmon habitat were addressed by replacing
habitat otherwise lost to the project. Increased public access was included
in the selected plan in response to community interest. Further coordination
with resource agencies and the public will occur during the Continuation of
Planning and Engineering phase of the project.(67)
The Feasibility Report states that "no major areas of controversy or
outstanding issues are known to remain." Although major issues have been
addressed, some agencies still expressed reservations about the project.
5.2.3.1 Fish and Wildlife Agencies
The Fish and Wildlife Coordination Act Report on the Duwamish Project,
dated September 1982, was prepared by the Olympia Office of the U.S. Fish and
Wildlife- Service. State and Federal fisheries agencies and the Muckleshoot
Indian Tribe are concerned that the Corps' final report addresses all con-
cerns but does not completely resolve them. Also, there is concern over the
Board of Engineers' failure to endorse funding of mitigation measures.
(66G,0,E) WDOE has recently prepared the State response on the Duwamish
Project. There will be opportunities to resolve remaining concerns during the
next phase of the project, CP&E.
The fisheries concern arises because juvenile salmonids currently feed In
shallow/intertidal habitat along the entire length of the Duwamish during
their weeks-long outmigration to the sea. Since shallow water habitat will be
destroyed all along the deepened channel, proposed mitigation plans include
construction of new isolated feeding habitat sites. The proposed sites have
similar total area to that destroyed but do not have a similar habitat regime
5-20

-------
because fish may rot be able Co manage feeding discortinuously at sites miles
apart along the river.(660) The Fish and Wildlife Coordination Act Report
proposed creating additional habitat along the deepened channel by grading the
slopes of the channel and using light riprap as substrate to enhance growth of
benthic and epibenthic invertebrates used as food by salmonids. The Corps
agreed to study this habitat mitigation issue during Continuation of Planning
and Engineering.
The Muckleshoot Indian Tribe shares this concern about mitigation and
expressed another, that increased commercial shipping would displace Indian
fishermen to less desirable locations. This concern was addressed by pro-
posing that the Tribe sponsor and share the cost of fisheries enhancement
measures, with the Federal government sharing costs.(67)
Thus, the Corps addressed agency concerns by incorporating specific
proposals and activities into the Feasibility Report and by agreeing to study
certain issues during CP&E.
5.3 DISCUSSION OF OBSTACLES TO DECISION-MAKING
The planning horizon for this project is almost a decade. The potential
obstacles discussed in this section may not become apparent for several years,
but acknowledging them now may help to alleviate difficulties later.
5.3.1 Technical Obstacles
In addition to the need for better technical information, logistical
problems, or lack of knowledge about the future, are important technical
obstacles in this case.
Many alternative sites were investigated during the Feasibility Study.
For planning purposes, the Corps has assumed that some of the dredged material
will be deposited between Piers 90 and 91 and the rest will go to the Fourmile
Rock site. Logistical problems could arise because both sites could be
unavailable by 1990 when construction is expected to begin. The Fourmile Rock
site requires local shoreline permit renewal at least every five years, as
5-21

-------
discussed in Section 7 of the report. The City of Seattle has the option of
not renewing the permit for dredge disposal or prohibiting certain types of
materials at Fourmile Rock. The Corps feels that this may not be a realistic
option in that many public and private entities, other than the Corps, also
use the site.
The Pier 90 and 91 site owned by the Port of Seattle is being considered
for several uses, including a Naval Facility. If the site is developed for
other purposes, it could be unavailable for filling by the Corps in 10 years.
Also, other upland disposal sites may not be more viable in the future,
considering the existing shortage of such areas. These logistical obstacles
may make the proposed dredging more difficult or necessitate additional
related studies. On the other hand, it must be noted that the Corps can
consider different disposal sites than other users, because of its regulatory
powers and its ability to pay. Still, close coordination with the City and
the Port, as well as active planning for upland disposal, can help prevent
logistical problems in the future.
5.3.2 Administrative Obstacles
The City of Seattle, the Port of Seattle, King County and the public are
aware that the navigation improvement proje-ct will facilitate industrial and
commercial growth. Local planning agencies foresee demand on surrounding
areas for backup space, warehouses, and other facilities to support the
expanded terminal facilities.(67) A logical extension of the project will be
dredging of berthing and terminal areas to facilitate the larger ships that
will be using the deepened waterways. Although these privately owned areas
are not the Corps' responsibility, dredging activities and, therefore, 404
permitting activities will increase as a result of the overall navigation
improvement. These developments will also necessitate increases in the level
of activity in Seattle's and King County's Shoreline Master use permitting
programs. Furthermore, a representative from Metro suggested at the recent
Interagency Open Water Site Evaluation Committee meeting that near-shore
berthing and docking areas may be more contaminated than the central channel
(24), due to run-off, spills, and leaks associated with industrial activity.
5-22

-------
Thus, the number and complexity of requests for shoreline and 404 permits
would be increasing together, making individual decisions more difficult and
time-consuming. Although local agencies and the Federal government have
overlapping permitting responsibilities in shoreline areas, like the lower
Duwamish, local governments perceive that their role is not considered
seriously by Federal decision-makers. Rather than participating together in
related permitting activities, there is often a local perception of disregard
and lack of desire for coordination.
The Coastal Zone Management Act of 1972 (CZMA) requires Federal agencies
conducting activities directly affecting the coastal zone to ensure that
projects are consistent with approved State management programs to the maximum
extent practicable. Washington's Shorelines Management Act, which implements
the CZMA, gives primary regulatory responsibility to local governments through
shoreline master programs, which are part of the approved State management
program and State law. The Corps must use the local shoreline master program
requirements for guidance when making consistency determinations for Federal
activities in the coastal zone. Both the City of Seattle and King County have
jurisdiction over shorelines where the Duwamish Project is planned. WDOE
reviews consistency determination prepared by the Corps. The Corps is not
required to delay or abandon proposed activities based on State concerns, but
the State encourages reassessment, especially if it disagrees and suggests
alternatives. The State also urges consultation and informal discussion to
resolve concerns and develop a proposal that is consistent with the State's
program, to the maximum extent practicable.
The Hydraulic Project Approval (HPA) process is administered by the
Washington Departments of Fisheries and Game as described in Section 6. As
mentioned, the Board of Engineers' recent report endorsed the idea of habitat
mitigation and fisheries enhancement but not the funding for it. This is
certain to raise the level of concern among the fisheries agencies and Indian
tribes who agreed to the proposal only after specific mitigation measures were
included. WDF brokers the concerns of all the State agencies when deciding on
a HPA. This approval may not be necessary for a Federal project of this type.
5-23

-------
However, if habitat mitigation concerns are not resolved, this could become an
issue when the proposed project is nearer to implementation.
5.3.3 Statutory or Regulatory Obstacles
Before this proposal to deepen the Duwamish Waterways can become a
project, Congress must review the documents and act. Congressional action
may:
•	Authorize the project
•	Authorize and appropriate funds for ths project
•	Request additional studies
•	Terminate the proposal.
It should be noted that a Federal project of this type has not been authorized
since 1976. There is a backlog of authorized projects that have not yet been
funded. Thus, even if all Corps approvals go smoothly and Congress acts
quickly, timely commencement of construction is not guaranteed.
Extensive review and coordination at each stage of Che project can cause
unexpected delays. Futhermore, the NEPA guidelines at 40 CFR 1505.3 allow
agencies' to provide for monitoring to assure that their decisions are carried
out. Mitigation and other conditions established in the EIS and committed as
part of the decision must be implemented by the COE. In implementing a
decision, the COE must also:
•	Include appropriate conditions in grants, permits or other approvals
•	Condition funding of actions on mitigation
•	Inform other agencies of progress in implementation.(AO CFR 1500)
Additional conditions or restrictions on site use, mitigation measures, etc.,
could be placed by a Federal agency with jurisdiction, or a State or local
agency whose approval is required.
5-24

-------
5.4 CONCLUSIONS
Actual construction and dredging on the Duwamish are not expected until
at least 1990. Even this schedule may be unachievable, considering logistical
obstacles and the need for Congressional action and State and local approvals.
The Continuation of Planning and Engineering phase of the proposed
project provides a means of collecting more information about the extent and
effect of contamination in the project area, through sampling and monitoring.
Several issues that were not completely resolved in the Feasibility Report
should be studied further before construction begins.
•	Data indicates that the most contaminated areas of the Duwamish are
berthing areas and docks, which will most likely be dredged by private
applicants after the proposed channel deepening. The extent and
nature of this related dredging should be investigated so that
disposal capacity can be left available or planned at other locations.
•	The Feasibility Study considered various disposal sites but not the
environmental effects of using them. The impacts of disposing of the
Duwamish sediments at the Fourmile Rock open water disposal site
should be Investigated.
•	The methods and extent of mitigation for loss of fish habitat should
be investigated. The approval of Federal and State fish and wildlife
agencies depends on resolution of this issue.
Enhanced understanding of these issues and responsiveness to State and
local viewpoints will facilitate consistency determinations or other approvals
that may be necessary.
5-25

-------
6. DESIGNATION OF OPEN WATER DISPOSAL SITES
There are ten sites in Puget Sound used "for open water disposal of
dredged material. There are other designated sites in the Strait of Juan de
Fuca and along the Pacific Coast. Dredged spoil disposal sites are necessary
to support maintenance and special dredging projects throughout the Puget
Sound region for economic reasons and because of a severe scarcity of upland
disposal areas, or landfills.
The need for designation of an open water disposal site may be realized
by a local port authority maintaining navigation channels, a developer con-
structing a marina, or a regulatory agency with jurisdiction over dredging
activities, such as the Corps of Engineers or the Washington Department of
Natural Resources (DNR).
Redesignation of an existing site necessitated by expiration of its local
shoreline permit is a far more common procedure than designation of new sites.
Because it initiates the decision-making process of designating or redesignat-
ing a site, DNR is treated as the key agency in the following discussion.
6.1 THE DECISION-MAKING PROCESS
This section describes how dredged material disposal sites in open water
are selected, designated and managed. The agencies involved and their
decision-making responsibilities are introduced. The public input process and
the environmental review process are also outlined.
6.1.1 The Agencies Involved
In Washington, the Department of Natural Resources (DNR) regulates beds
of navigable waters and manages the standards and procedures used in lease
management, land use allocation and development activities, Including open
water disposal sites. DNR selects, establishes, and manages sites with the
advice of the Interagency Open Water Disposal Site Evaluation Committee, which
was created by DNR regulation. In addition to DNR, Washington's Departments
of Ecology, Fisheries, and Game are represented on this Committee. Federal
6-1

-------
representatives on the Committee include EPA Region X, the U.S. Army Corps of
Engineers, the National Marine Fisheries Service, and the U.S. Fish and
Wildlife Service.
Although not represented on the Committee, local governments are also
involved in this decision-making process. Local governments have the re-
sponsibility for implementing shoreline management programs under State law.
A dredged material disposal site cannot be operated unless a local shoreline
management permit is granted.
The next section describes DNR's procedures and criteria for site selec-
tion and management. Local permit procedures are discussed as a separate pro-
cess. The roles of other agencies are discussed in Section 6.L.3.
6.1.2 Procedures, Timing and Criteria
This section focuses on the role of the Department of Natural Resources
in the site designation decision-making process. Figure 6-1 is a flow diagram
of the decision process. The Marine Lands Management Division of DNR, shown
in Figure 6-2, plays the major role in designating open water disposal sites.
DNR regulations (WAC- 332-30-166) outline site designation criteria, site
management procedures, and composition of the Interagency Open Water Disposal
Site Committee.
6.1.2.1 Selection of Sites
As chair of the Interagency Committee, DNR schedules meetings and
determines the agenda. The need for sites, approaching expirations of local
permits for existing sites, and previous Committee discussions are factors in
deciding the priority of items on the agenda.
The Interagency Committee meets irregularly at the request of DNR to
provide scientific and regulatory advice on designation of open water disposal
sites. The Committee's role is to evaluate sites, discuss alternatives and
make recommendations to DNR. DNR reviews the Committee's recommendations and
decides whether to pursue establishment of a site. For a more detailed
6-2

-------
I eicAiu
«m« or
irtiMtxi
cmiittu »
nymi ilTl
twrni
«tun omiio.
*r«iu«u
tWMMKQi
'c&mitni
^WfWl
imiana.
vcicctt.in
FICURI t-1
decision-making process for designation of open water disposal sites

-------
o*
SAUS
FIIMCMl
SftVICCS
SMI IBM.
urn
sreci«. swics
mmamni
MMT5IS MS
HlWtt
HIS
IS
mimmiiAum
COWttSSIONER
IC LMDS
IC AFFAIRS
rm coaiMi
AULA
CERTRAL
SOUIHEASI
AREA
oiviric
tiASHINCTOM DKPAATNENT
or NATURAL RBSOURCBS

-------
discussion of the Interagency Committee activities and the criteria used for
site selection, see Section 6.1.3.
DNR considers the discussions and informal recommendations of the Commit-
tee, along with the comments of other agency representatives and individuals
invited to the Committee meetings. Available scientific studies and data are
also reviewed. DNR'a procedures at this point are not well documented. In a
few weeks, depending on the workload, Marine Lands Management Division of DNR
then may decide to:
•	Discontinue use of an existing site
•	Relocate an existing site
•	Seek renewal of an existing site
•	Designate a new site.
6.1.2.2 Local Permit Application
For any of the latter three options, which are the most common alterna-
tives, DNR must initiate the local permitting process by applying for a
shoreline permit from the city or county government that has jurisdiction over
the proposed site under the Shoreline Management Act, described in more detail
in Section 6.1.3.2.
The application process includes completion of a standard State-wide
application and an Environmental Checklist for activities like this one that
require "environmental review" under SEFA. The permit application used for
all types of shoreline permits requests the following information:
•	Applicant's name
•	Location of proposed activity
•	Name of water area
•	Current use
•	Proposed use
•	Nature of water or shoreline area
6-5

-------
•	Shoreline designation, according to the applicable Shoreline Manage-
ment Plan (SMP)
•	Site characteristics
•	Source, composition, and volume of dredged or fill material.
The environmental checklist appears in Appendix B. Some of the important
additional information it requires about environmental impacts is listed here:
•	Deposition, siltation or erosion effects
•	Discharges into surface waters
•	Alteration of water quality
•	Changes in diversity or numbers of species including microflora and
aquatic plants
•	Deterioration of habitat
•	Release of hazardous substances
•	Human health hazards or potential hazards
Completing the checklist requires more detailed evaluation and analysis than
the permit application. There is no time constraint on the application
process, which may take weeks to months.
The time element is important only in that local permits can be issued
for a maximum period of five years. When reapplying for a local permit for an
existing site, DNR must initiate Committee discussions and the reapplication
process well in advance of the expiration date, where continuous use of the
site is desired.
Upon completion of the environmental checklist, DNR, the local agency and
other interested parties review the checklist to determine whether an environ-
mental impact statement (EIS) will be required in accordance with the State
Environmental Policy Act (SEPA). (See Section 6.1.5 for more explanation.)
If an EIS Is not required, a declaration of non-significance (DNS) is issued.
If an EIS is required, a statement of significance is issued and an EIS is
6-6

-------
prepared. For purposes of this discussion, DNR's final application for a
local shoreline permit, accompanied by completed environmental review docu-
ments, represents the end of the site selection process and the beginning of
the local permitting process. Local permitting procedures, timing and
criteria are discussed in greater detail in Section 6.1.3.2.
6.1.2.3 Management of Sites
After the local permit is obtained, DNR operates the designated site in
accordance with its own regulations and any supplemental conditions that may
be imposed by the local shoreline management permit. DNR has significant site
management responsibilities, which Include leasing the use of a designated
site to dump operators, collecting lease fees, monitoring disposal activities,
and penalizing unauthorized activities. Nevertheless, DNR relies on EPA
Region X and the Washington Department of Ecology (WDOE) to determine which
dredged materials are acceptable for open water disposal. This determination
is usually made as part of the dredged or fill material disposal permit
process under Section 404 of the Clean Water Act, which is discussed in
Section 4 of this report.
DNR1s current management role may change in the near future. On
September 28, 1983, DNR proposed four alternative management strategies for
consideration by the Interagency Committee. The strategies range from greatly
increased DNR involvement in site management to decreased DNR involvement with
greater exercise of local authority through the shoreline management permit.
Highlights of each of the proposed management strategies are listed below.
(1) Maximum DNR Involvement: Under this option, DNR would still obtain a
local shoreline management permit for each site, but would also:
•	Review the characteristics of the material to be disposed of before
issuing leases
•	Monitor most disposal activities for compliance
•	Fund research for impacts of disposal
•	Raise lease fees significantly to support increased responsibilities.
6-7

-------
(2) Increased DNR Involvement: This option Is similar to (1) except that DNR
would:
•	Rely on EPA, WDOE and Corps review and approval of dredged material
characteristics
•	Cooperate with other agencies in funding research
•	Raise lease fees less significantly.
(3)	Current DNR Involvement: This option describes current management prac-
tices which differ from the above in that DNR only:
•	Monitors for compliance on a spot-check basis
•	Depends on research funded by others.
(4)	Decreased DNR Involvement: Under this option, DNR's role in site manage-
ment is substantially diminished. Procedures would be as follows:
•	Disposal sites would be established by regulation, rather than by
local permit
•	Each use would require an individual-local shoreline permit
•	Monitoring would be done only by the permit issuing agency (Corps
and/or local government)
•	Disposal fees would be discontinued.
DNR has asked the Interagency Committee to evaluate these options and recom-
mend a management approach at the next Committee meeting.
6.1.3 Coordination With Other Agencies
DNR is aided in the disposal site decision-making process by the Inter-
agency Site Evaluation Committee. The local shoreline management agencies are
also integral to the process. The following sections discuss their respective
roles. In addition, the roles of several other agencies represented on the
Committee are described at greater length.
6-8

-------
6.1.3.1 The Interagency Open Water Disposal Site Evaluation Committee
The Interagency Committee was created by DNR regulations (WAC 332-30-
166). It consists of representatives from the following eight agencies:
•	U.S. Army Corps of Engineers - Seattle District
•	U.S. Environmental Protection Agency - Region X
•	National Marine Fisheries Service
•	U.S. Fish and Wildlife Service
•	Washington Department of Game
•	Washington Department of Ecology
•	Washington Department of Fisheries
•	Washington Department of Natural Resources.
Committee members are chosen by the agencies they represent. Although
specific individuals are the designated agency representatives, it is not
uncommon for more than one person or an alternate to attend meetings in place
of the designated representative.
The Interagency Committee's main role is providing scientific and
regulatory advice to DNR. The Committee is a forum for discussing site
characteristics, sharing scientific information, considering opinions of
agencies not represented on the Committee, and recommending alternatives.
Other regulators, local government officials, Indian tribal representatives
and private citizens may be invited to attend meetings to present data,
viewpoints, or background. After reviewing all information presented, the
Committee makes informal recommendations to DNR. The following criteria from
WAC 332-30-166 are used in preparing the recommendations:
(a)	Select areas of common or usual natural characteristics. Avoid
areas with uncommon or unusual characteristics.
(b)	Select areas, where possible, of minimal dispersal of material
rather than maximum widespread dispersal.
(c)	Sites subject to high velocity currents will be limited to sandy or
coarse material whenever feasible.
6-9

-------
(d)	When possible, use disposal sites that have substrate similar to the
material being dumped.
(e)	Select areas close to dredge sources to ensure use of the sites.
(f)	Protect known fish nurseries, fishery harvest areas, fish migration
routes, and aquaculture installations.
(g)	Areas proposed for dredged material disposal may require an inves-
tigation of the biological and physical systems which exist in the
area.
(h)	Current velocity, particle size, bottom slope and method of disposal
must be considered.
(i)	Projects transporting dredged material by pipeline will require
individual review.
(j) Placement of temporary site marking buoys may be required.
(k) Special consideration should be given to placing material at a site
where it will enhance the habitat for living resources.
(1) Locate sites where surveillance is effective and can easily be found
by tugboat operators.
Additional factors that may be considered beyond the regulatory guidelines
include:
•	Cost and feasibility of dredged material disposal
•	Proximity of the site to pipeline, cable, or anchorage areas and
transportation routes.
The Interagency Committee's recommendations may cover the same range of
options as DNR's decision, including:
•	Discontinue use of an existing site
•	Relocate an existing site
•	Seek renewal of an existing site
•	Designate a new site.
The Committee also provides informal advice on political considerations,
research needs, and site management issues.
6-10

-------
6.1.3.2 Local Shoreline Management Agencies
In 1971 the StaCe of Washington passed the Shoreline Management Act
(SMA), RCW 90:58, to promote planning of shoreline uses, to promote develop-
ments dependent on shoreline use, to protect the environment, and to improve
public access to shorelines. The Act established a cooperative management
program between local governments and the State. Cities and counties in the
coastal zone developed Shoreline Master Programs (SMPs) to guide shoreline
uses and activities. These programs are implemented through a permit system
that applies to marine waters, lakes greater Chan 20 acres, streams with a
flow of 20 cubic feet per second, associated wetlands, and upland areas 200
feet from the ordinary high water mark. Local master programs for all cities
and counties bordering Puget Sound have been reviewed and approved by WD0E and
the State attorney general, and are now State regulations. Although locali-
ties have primary responsibility for the administration of the shoreline
regulatory program, WDOE supports and reviews local actions to ensure compli-
ance with State and local rules.
The SMA defines four types of land use designations for use in developing
local SMPs: urban, rural, conservancy and natural. Some local governments
have established additional designations (e.g., urban-residential) to further
describe- use availability. "Natural" areas are not available for disposal of
dredged spoils.
SMPs also establish regulations concerning developments or activities
on shorelines, and implement permitting programs to enforce these regulations.
There are three types of permits:
•	Substantial development permit - This permit is required for all
developments that Interfere with normal public use of waters or
shorelines, or that are valued at more than $1,000.
•	Conditional use permit - This permit is used to limit or condition
ongoing activities at a development, and to allow flexibility In
applying SMP rules.
•	Variance use permit - This is used for developments or activities that
require an exception from the SMP rules.
6-11

-------
By definition, all areas of Puget Sound are under same local jurisdic-
tion's Shoreline Master Program. Open water disposal is considered a "devel-
opment" for the purpose of applying a SMP. Any site selected for open water
disposal requires both a substantial development permit due to the size of the
operation, and a conditional use permit because of the ongoing nature of
dumping activities (as opposed to a finite period of construction). Local
agency actions and permit decisions are reviewed by the Shorelines Division of
WDOE (see Section 6.1.3.3).
When a local agency receives a completed application for a shoreline
permit from DNR, public notice is given and a comment period follows. During
the 30-day public comment period, the local agency reviews the application
and accompanying environmental checklist in accordance with WAC 173-14-100,
"Review Criteria for Substantial Development Permits," and WAC 173-14-140,
"Review Criteria for Conditional Use Permits." Shoreline uses classified as
"conditional" in the SMP may be allowed if the proposed activity meets the
following criteria:
•	Will be consistent with the Shoreline Management Act and the Shoreline
Master Plan
•	Will not Interfere with normal use of public shorelines
•	Will be compatible with other permitted uses in the area
•	Will cause no unreasonable adverse effects on the shoreline environ-
ment
•	Will have no substantial detrimental effect on the public interest.
Other uses not specified in the SMP may be authorized if extraordinary
circumstances preclude reasonable use in a manner consistent with the SMP.
WDOE guidelines for development and approval of SMPs (WAC 173-16-060-16)
require that local plans address open water disposal of dredged material,
which is allowed only for habitat improvement, to correct problems of material
distribution that adversely affect fish and shellfish, or where the land
disposal alternatives are more detrimental to shoreline resources. There is
6-12

-------
no limit in practice on the amount of time allowed for this review by the
local agency.
After reviewing the application and public comments, the local agency
may:
•	Deny the permit
•	Approve the permit without restrictions
•	Approve the permit with conditions such as time limits, volume limits,
monitoring requirements, or individual dump approvals, depending on
the local SMP.
The local agency must file its ruling with WDOE and the State Attorney General
within eight days of the decision. The State's review is discussed next.
6.1.3.3 Washington Department of Ecology (WDOE)
The Management Section of the Shorelines Division of WDOE has 30 days
from the date of receipt to review the local permit decision (WAC 173—1A—130).
Normally, only approvals are reviewed. Local denials are considered final at
this stage. WDOE reviews the application and accompanying documents to ensure
that the" permit was issued properly and that the decision is consistent with
the local Shoreline Master Program. The Attorney General also reviews the
decision for consistency.
Due to limited resources, the Shorelines Division concentrates its
efforts on the review of Conditional Use Permits and Variance Permits. Less
time is spent on the review of Substantial Development Permits unless the
proposal is controversial. WDOE's final review decision can take one of three
forms:
•	Approval
•	Approval with conditions (with the concurrence of the local agency)
•	Appeal to the Shorelines Hearing Board.
6-13

-------
This decision is returned to the local government, which is in turn responsi-
ble for notifying interested parties.
The applicant, or any other person or agency in disagreement with the
final decision, may seek WDOE certification for review by the Shorelines
Hearing Board. A request must be filed within 30 days of receipt of the final
decision. The Shorelines Hearing Board consists of State government officials
and representatives from the Washington Association of Cities and the
Washington Association of Counties. The Board can make decisions based on
both SEPA and SMA issues. Reviews are conducted on a case-by-case basis,
without reference to prior decisions. Appeals beyond the Board may be taken
to the Washington State Superior Court.
6.1.3.4 Washington Departments of Fisheries (WDF) and Game (WDG)
WDF and WDG administer the Hydraulic Project Act, RCW 75.20.100, through
regulations contained in at WAC 220-110. A "hydraulic project" means con-
struction or other work that will use, divert, obstruct, or change the natural
flow or bed or utilize any waters of the State. All hydraulic projects,
including open water disposal sites, require a Hydraulic Project Approval
(HPA). A HPA is a written, signed approval from both departments that
provides conditions for the protection of fish life. It is valid for twelve
months unless reauthorized. The departments use a standard HPA application
which includes plans and specifications. If the application is complete and
SEPA requirements have been met, the permit can be processed within 30 days.
Each approval is specific to a location. The departments may place general,
technical, and special conditions in a HPA. Examples include:
•	Timing restrictions to protect fish during periods of migration or
spawning
•	Operational or technological restrictions to minimize siltatlon or
impacts to biota
•	Area restrictions to protect fish habitat or spawning areas.
6-14

-------
Violation of HPA conditions is a gross misdemeanor punishable by fine or
imprisonment.
WDF and WDG are both members of the Interagency Committee and are in-
formed of site designation decisions. Since there is extensive coordination,
the approval of an open water disposal site as a hydraulic project, may be im-
plicit in the Departments' sanctioning of and participation in the Committee's
recommendation to DNR. If this is true, the written HPA, with any conditions,
is a formality which should not impede the decision-making process.
6.1.3.5 EPA and the Corps of.Engineers
Under the dredge and fill permit regulations, 40 CFR 230.80, EPA and the
Corps of Engineers may identify areas that will be considered as possible
future disposal sites or that are unsuitable for such designation. The
agencies or another party may initiate this procedure, which must be done in
consultation with the State. This "advance identification" does not allow or
prohibit discharge of dredged material at these sites but only facilitates 404
permit application and processing. This activity which may be conducted by
EPA and the Corps is consistent with their roles on the Interagency Committee.
Further, the Corps uses DNR designated sites when Issuing 404 permits and for
most of its own dredging activities. However, the Corps participates in this
process by policy, not by mandate, and may use other sites in certain situa-
tions. Corps' dredging activities must comply with Sections 404 and 401 of
the CWA and the CZMA, to the maximum extent practicable. Corps projects do
not require site use permits or lease fees.
6.1.4 Public Input
During the Interagency Committee meetings overseen by DNR, public input
is provided only informally. City and county officials, representatives of
interested agencies or Indian Tribal governments, or members of the public are
often invited to meetings for Informal discussion or for advance notice of an
impending action.
6-15

-------
No formal public notice of site designation is required until DNR applies
for a local shoreline permit. At that time, DNR must publish notice in a
newspaper of general circulation within the geographical area of the proposed
development at least once a week for two consecutive weeks on the same day of
the week. Reasonable notice must be given to adjacent property owners by
mailing or posting near the site. Individual SMPs may require more frequent
notices.
The notice must state that interested persons may submit written comments
within 30 days of the final newspaper notice, and may request individual
notice of the final decision. WDOE procedural regulations (WAC 173-14-080)
provide for optional public hearings at the local level as part of the
shoreline permit process. A hearing may be required under an approved local
SMP if a request is made during the comment period. The hearing would be held
prior to the final local permit decision.
After a decision on a local permit is issued, WDOE reviews the decision.
During this period, a review by the Shorelines Hearing Board may be requested
by any interested party. The request must be filed with WDOE within 30 days
of WDOE's receipt of the local decision. WDOE will certify the request for
review within 30 days if it appears to have merit. If WDOE does not certify
the request, the requestor may seek certification from the Attorney General or
review by the Superior Court. The rules of practice of the SHB are estab-
lished by law in RCW 90.58.180, and by regulation in WAC 461-08.
6.1.5 Envlronoental Review Under SEPA
The State Environmental Policy Act (SEPA), RCW 43.21C, requires local
governments to assess the environmental impacts of proposed developments,
including the designation of an open water disposal site. To fulfill the
requirements of this environmental review, the applicant for a proposed
project completes an environmental checklist (included as Appendix B) along
with a shoreline permit application. Although any regulatory agency involved
in a development can request a checklist, a "lead agency" is normally estab-
lished to oversee the entire environmental review process. In this case, the
6-16

-------
lead agency is DNR because it is a government applicant and it has jurisdic-
tion over open water disposal sites. The completed checklist provides State
and local reviewers with a preliminary determination of the environmental
impact of the proposed activity. Based on the review of the checklist and
SEPA procedures, an environmental impact statement (EIS) may be required.
The environmental review begins during the 30-day public comment period.
If an EIS is not warranted, based on this review, a Declaration of Nonsignifi-
cance (DNS) is issued by the lead agency, and circulated among parties of
record, other agencies with jurisdiction, public interest groups, and the
general public. Fourteen days are then allowed for public comment, at which
time the DNS may be challenged.
If an EIS is required based on the checklist, a Declaration of Sig-
nificance is prepared and circulated. This decision cannot be appealed. In
the case of open water disposal site designation, DNR will prepare the EIS and
serve as the lead agency. The draft EIS may take from several months to years
to prepare. Upon completion, it is distributed to interested parties for a
35-day comment period. All comments regarding environmental effects and
alternatives to the proposed activity must then be addressed in a final EIS.
After consideration of the final EIS, the local agency begins the final permit
decision process described earlier.
6.2 DISCUSSION OF OBSTACLES TO DECISION-MAKING
This section discusses the technical, administrative and statutory or
regulatory obstacles to the site selection, designation and management pro-
cess. Conclusions are presented in Section 6.3.
6.2.1 Technical Obstacles
Two types of concerns are discussed as "technical obstacles:" lack of
information and lack of coordination. However, it should be clear that these
are related to the Issues raised in other sections, too.
6-17

-------
6.2.1.1 Lack of Information
Lack of data is cited as the main obstacle to informed selection and
management of open water disposal sites. Although information concerning
bioassays, toxicity, and impacts of disposal of dredged spoils has been
collected by the Corps and others, complete data are lacking for specific
sites in Puget Sound. Ongoing research programs conducted by NOAA, EPA, and
WDOE are producing information about pollutants locations, concentrations
and toxicity. However, to make wholly informed decisions about specific
sites, regulatory agencies must know more about:
•	The physical/chemical behavior and dynamics of the site, and materials
dumped there, including the rate of settling and resuspension of sedi-
ments, rate of exchange between the dissolved and suspended form of
pollutants in the water column, synergistic effects of pollutant
combinations, and degradation rates of contaminants
•	The ecological characteristics of the site, including exposure path-
ways in the water column and sediment, bioaccumulation pathways, and
biological uses of the site
•	The characteristics and discharge rates of materials to be disposed of
at the site including volumes, concentrations and availability of
pollutants of concern.
A major concern is the possible link between dredge spoil discharges and
deleterious effects on the biota. An understanding of the relationship of
this disposal activity to all other pollutant sources and their interaction in
the overall transport and persistence of contaminants within Puget Sound is
also needed. The many unknowns make decisions on acceptability of materials
for open water disposal difficult and subject to professional judgements In
many cases.
New, changing information can also be an obstacle when environmental
studies show that problems previously considered significant are less impor-
tant in relation to newly discovered problems. Ongoing research programs
designed to study one problem often uncover evidence of new, poorly understood
problems. For example, in various environmental programs, including the site
designation process, attention has shifted from conventional pollutants to
6-18

-------
toxic metals, toxic organics, and synergistic effects of contaminants. Also,
in the Sound water quality concerns have expanded to include sediment qual-
ity. Overall, research efforts often lag behind regulatory needs and deci-
sions are made with incomplete information.
A historical perspective on "informed selection" must also be noted. DNR
established the Interagency Committee and the review criteria by regulation in
1980. However, most of the existing open water disposal sites have been in
use for a decade or more. Before ten years ago, open water dumping occurred
wherever it was convenient. Fishing grounds and feeding habitat were being
destroyed. An advisory group was set up to consolidate dumping activities to
a few sites. The group established some general selection criteria, discussed
the issues, and then compromised. Proximity of sites to dredging activities
and experience were important considerations.
Although the historical decision-making process relied on similar
interagency discussions and guidelines, it was less formal and rigorous than
today's process. More is now known about sites and impacts and criteria are
more formal since codification. However, this historical process still has a
direct effect on today's decisions, which usually involve redesignation of an
old site, rather than selection of new sites based on new criteria.
Although it is not necessarily done In a rigorous fashion for each site,
the environmental checklist prepared during application for a local shoreline
permit requires evaluation of data on water quality, sediments, benthos,
pelagic life, and long-term effects of dredged spoil discharges. These topics
can be investigated in greater detail during preparation of an EIS. Practices
for newly designated sites should include even more baseline monitoring to
document existing conditions, and follow-up monitoring to determine whether
sediments are moving or spreading. Although the regulations governing ocean
dumping (40 CFR 227, 228) do not apply in Puget Sound, they could be used as
guidance in designing monitoring programs. Because the application process
must be repeated every five years, the shoreline permit also provides a
mechanism for acquiring and considering new information. This periodic review
allows local governments to evaluate new information which support
6-19

-------
establishment of conditions on site use or termination. This local permit
provides a tool for reevaluating past decisions and guiding efforts toward
better decisions in the future.
Two of DNR's recently proposed management alternatives would generate
increased fees to fund monitoring and research. Either approach will improve
DNR's ability to collect information necessary for informed decision-making.
6.2.1.2 Lack, of Coordination Between Site Selection and Disposal Activities
Existing technical problems are exacerbated by the lack of regulatory
coordination between the site designation process, administered by DNR, and
the dredge and fill permitting program, administered by the Corps, EPA and
WDOE. During its designated life a site may be used for disposal of materials
from a variety of locations. The existing criteria used by DNR to select
sites do not require detailed information on the quantity and quality of
materials to be discharged at a site.
As part of the dredge and fill program, the Corps, EPA and WDOE decide,
independently of the site selection process, which dredged materials can be
disposed of in open water using the 404(b)(1) and 401 .criteria of the CWA.
DNR pres-umes that all material determined to be "suitable" for open water
disposal is reasonably uncontaminated, and will not degrade the marine
environment.
With chemical analysis however, it has become clear that some materials
classified as suitable are more contaminated than others. For example,
dredged spoils from urban or Industrialized river and harbor areas are
typically contaminated with heavy metals or organic pollutants. Thus,
disposal sites located near urban areas may be concentrating these contami-
nants. Uncontaminated dredge dumped at sites in undeveloped areas may simply
reflect redistribution of naturally occurring materials.
At a recent Interagency Committee meeting in September 1983, members were
asked to comment on a proposal to designate different disposal sites for
6-20

-------
different types of materials. Recognition of the need for this distinction
may be a step toward a solution. To answer this question properly, effort
must be put into determining whether relatively contaminated materials can be
dumped in the Sound in some location where they are relatively contained and
adverse effects are minimized perhaps by capping of the site by natural
sedimentation processes or man-made means. A decision to designate different
types of sites would probably be accompanied by development of criteria to
distinguish between materials that are "suitable" and those that are "contami-
nated, but acceptable." Consideration of upland alternatives to open water
disposal could also tie into this process.
6.2.2 Administrative Obstacles
Four issues are discussed in this section as examples of problems or
potential concerns related to administration of the open water disposal site
program. They are:
•	Resources
•	Management
•	Delays
•	Complexity.
6.2.2.1 DNR Resources
DNR's Marine Lands Management Division lacks the staff and resources to
manage rigorously the site selection and leasing program. Activities neces-
sary for an effective management program include:
•	Monitoring site use for compliance with Federal or State conditions
•	Monitoring for compliance with restrictions imposed by local agencies
•	Encouraging complementary actions by other agencies
•	Monitoring the activities of other agencies
•	Monitoring long-term effects at the site and relating this data to
other monitoring efforts in the Sound
6-21

-------
•	Funding studies of transport and impact of materials at the site and
linkages to other discharges
•	Developing innovative approaches to site management.
There is a perception that DNR could be more aggressive in its regulatory
approach, for example, by monitoring site use and permit compliance.
DNR's current lease fees for disposal activities do not provide suffi-
cient resources to fund operation of sites, let alone monitoring and research
or encouragement of alternatives. There is intermittent spot checking of dump
operations but no long term monitoring at the disposal sites. Two of DNR's
proposed management alternatives provide increased fees which could increase
long-term monitoring at sites and enforcement, which is not conducted by any
agency now, even those involved in permitting. Another of the management
alternatives would eliminate lease fees altogether, thus exacerbating an
existing problem.
6.2.2.2 DNR Management
DNR has proposed alternative management strategies ranging from increased
involvement in site management to virtual withdrawal from it. Only two of
these wauld result in a stronger regulatory program. One of the proposed
alternatives would substantially remove DNR from the process and substitute
local control through the shoreline permit program. This approach could
result in a more fragmented regulatory program and greater risk of environ-
mental damage. Even under this alternative, however, an effective program
could still evolve. As oversight agency for the shoreline permit program,
WDOE could impose a coordinated site management program through revisions to
SMP guidelines and review of.individual permit decisions. This approach is
not envisioned at this time.
Two of the proposed strategies would result in a stronger regulatory
program for managing open water disposal sites. An expanded role for DNR in
coordinating the review of individual dredge disposal permits, as proposed,
would integrate regulation of disposal activities with the site designation
6-22

-------
process. It would enhance compliance monitoring and promote research, too.
This stronger central presence has the advantage of preventing proliferation
of local conditions designed to counterbalance a weak regulatory program.
However, DNR's participation in evaluating other agencies' determinations of
acceptability has disadvantages, too. An additional review would not increase
knowledge of the unknown or long term fate and effects of contaminants at
disposal sites; it would merely add delays and redundancy. DNR can effect the
proposed improvements through minor management or regulatory changes. It is
more difficult for Federal agencies to assume a larger role in this process.
6.2.2.3	Delays Due to Local Agency Involvement
DNR can designate and operate open water disposal sites only with the
consent of tne local government that issues the shoreline permit. Local
review, public notice, and decision-making procedures coupled with the WDOE
review and the SHB appeal process can result in extensive administrative
delays in designating a new site or renewing an existing one. Delays in
obtaining site approvals or renewals can be expensive for the private or
public concerns that must postpone dredging activities.
6.2.2.4	Complexity Due to Special Permit Conditions
In recent years, some localities have imposed additional restrictions on
site use through Conditional Use Permits. Examples of conditions include:
•	Time limits
•	Volume restrictions
•	Monitoring requirements
•	Separate approvals for individual dumping activities.
These special conditions are difficult to monitor and enforce, may decrease
site availability, and may Increase delays In obtaining approvals for Individ-
ual projects. If local involvement in site management increases because of
implementation of one of DNR's proposed management alternatives, this obstacle
will increase, too. On the other hand, localities can use this mechanism to
provide additional safeguards, if they perceive that Federal or State efforts
6-23

-------
are inadequate to protect their interests. Greater local participation will
ensure greater recognition of local concerns.
In addition to more stringent permit conditions, increasing local concern
over activities at these sites could lead to exclusively local dumping, if
local governments use their permit authority to systematically deny dredged
materials from other jurisdictions. Each jurisdiction denied access could
petition DNR for its own site, thus proliferating sites.
While this result is undesirable, it is also unlikely for two reasons.
First, the Interagency Committee was established to constrain dumping to a few
dedicated sites. Second, State law requires an "appearance of fairness" in
decision-making. If similar materials from different jurisdictions were not
allowed at the same site, WDOE or the Shorelines Hearing Board could intervene
in the process. The fact that this possibility exists, though, emphasizes the
need for active State involvement in regulating the type, quantity, and
location of open water dumping — not to deny local Involvement but to allay
local concerns.
6.2.3 Statutory/Regulatory Obstacles
The two issues discussed in this section are considered statutory or
regulatory because of the types of approaches that would be needed to modify
the existing situation.
6.2.3.1 Five-Year Permit Limits
The Shoreline Management Act Imposes a five-year limit on locally issued
permits. This necessitates frequent repetition of the entire decision-making
process. On the administrative side, this regulatory requirement may be seen
as causing duplication and delays. On the other hand, though, the Shoreline
Management Act is the only law that provides formal public input to the
decision-making process. Without this public access, there would probably be
a greater incidence of public controversy and legal challenge through the
courts. Consideration of public comments through this formal, mandated
process may ultimately save time. This regular review of the site designation
6-24

-------
decisions also provides local governments with an opportunity to evaluate new
information as it arises and to impose "five-year plans" through local permit
conditions, even if a concerted regulatory effort is lacking.
6.2.3.2 Shortage and High Cost of Upland Disposal Alternatives
The shortage of economical upland disposal sites for solid waste in the
Puget Sound area, especially in urban areas, combined with continued demand
for dredging to support economic growth create a substantial need for open
water disposal sites. Demand for adequate disposal sites is increasing at the
same time scrutiny of existing sites by regulators and the public is increas-
ing. When dredged materials are determined to be unfit for open water
disposal they may be only slightly contaminated but they still must be
disposed of in some way.
As an example of these limitations in urban areas, both the City of
Seattle and King County operate landfills through solid waste utilities.
Telephone contacts with these utilities revealed that solid waste is accepted
at a cost of $12.85 per ton at Seattle's landfill, and $26.50 per ton at King
County's regional landfill. As mentioned in Section 4, DNR charges $0.10 per
cubic yard of dredged material at open water disposal sites. Assuming that,
the weight and volume of water approximate those of dredged spoils, these
costs can be translated into comparable figures.
A cubic yard of water weighs .842 of a ton.* Using this conversion, it
would cost $10.82 per cubic yard to dispose of water at Seattle's landfill,
and $21.31 at King County's. Assuming dredged material is at least as heavy
as water, upland disposal would be over 100 times more expensive than open
water disposal.
*From the Water Measurement Manual, U.S. Department of Interior, Bureau of
Reclamation, 1967:
27 feet3 ^ 1 gal.
1 yard 3 .13368 feet
8.34 lbs. 1 ton
3 * 1 gal. X 2000 lbs.
¦ .842 ton
6-25

-------
Even if cost factors could be ignored, it is not clear that dredged
materials would be accepted at existing landfills. The Seattle/King County
Health Department regulates the quality of materials allowed at landfills
(Wally Swofford, Health Department personal communication). Both solid waste
utilities also regulate the quantity and type of materials accepted at their
landfills. The dredged materials being discussed here are contaminated at
levels far below that considered "hazardous." However, Health Department
rules or local prohibitions on wet or liquid materials may prevent their
disposal at landfills. Capacity is also a factor in that acceptance of new
types of wastes could decrease the expected usable life of the landfills.
Seattle projects that current use rates will fill all its landfill capacity in
three to five years (Jack Palmer, Seattle Solid Waste Utility, personal
communcation).
If disposal sites cannot be found locally, other options must be con-
sidered. Although there is a hazardous waste disposal site in Arlington,
Oregon, it is even more expensive to transport dredged sediments there. Also,
pollutant levels in most of the "contaminated" dredged sediments are not high
enough to be considered "hazardous wastes."
As the shortage of upland disposal sites becomes more severe, there will
be limited alternatives:
•	Stop dredging contaminated areas, where economic activity depends on
dredging
•	Dump more and more contaminated material into Fuget Sound, perhaps
capping the material with cleaner sediments
•	Find upland sites which are more costly.(66J)
In addition to the shortage of sites, DNR's currently low lease fee
favors open water dumping and discourages consideration of upland alter-
natives. DNR's management proposals, which could increase or decrease lease
fees, bear on this issue. Although DNR's proposals have not been refined to
the level of specific values for the new lease fees, several statements can be
made. Discontinuing lease fees seems inconsistent with the "public trust"
6-26

-------
concept, which states that "fair market values placed on these lands [managed
by DNR] will result in better land use decisions" (WAC 332-30-100). On the
other hand, raising lease fees could make open water disposal more realis-
tically priced in relation to upland alternatives. Further, raising lease
fees substantially could encourage consideration of some upland alternatives
that are prohibitively expensive at current lease fees.
Difficult decisions will have to be made within the next few years.
Although a regional approach to solid waste management has been proposed,
there has been little action toward developing a solution.
6.2.4 Public Input Considerations
Public comment and review may cause delays in the decision-making pro-
cess. Public perception may link one decision or activity to another and sup-
port or oppose both for uninformed reasons. Also, one segment of a community
may be more vocal because of proximity or perceived threat of an activity.
6.3 CONCLUSIONS
DNR's proposal to change the management structure of its open water site
designation and leasing program is a key idsue in future decision-making.
Currently, DNR allows the Corps, EPA, and WDOE to decide which materials are
acceptable for dumping, with no independent review. DNR also does virtually
no compliance or long-term monitoring of sites and requires none. Increasing
DNR's role would help in orchestrating monitoring activities. However, DNR's
involvement in acceptability determinations would likely add a layer of review
and delay without improving evaluation procedures or technical understanding
of unknowns. The options decreasing DNR's role would continue this situation
or make it worse.
The Interagency Committee has a major role In site designation, but there
is no formal product of its activity and historical events may influence
today's decisions. Decisions usually involve redesignation of sites that have
been in use longer than the regulatory programs meant to control them. Regu-
lators are not necessarily choosing the "best" open water disposal sites based
6-27

-------
on scientific evidence, but may be choosing to continue using existing sites
based on historical practice, lack of alternatives, lack of information and
desire not to contaminate other sites.
The local shoreline permit program provides for routine, public reevalua-
tion of site selection decisions and review of new information. Increasing
local involvement could lead to more stringent permit conditions, site use
restrictions, or proliferation of sites, making management more difficult.
This provides an incentive for active, responsible State management to allay
local concerns. The shoreline permit also provides a failsafe mechanism
whereby WDOE or local agencies can intervene if EPA, the Corps, or DNR do not
properly regulate and monitor open water disposal of dredged material in Puget
Sound.
Alternatives to open water disposal of dredged material are urgently
needed. Increased DNR lease fees may encourage consideration of upland sites
in individual cases. However, a regional approach, involving Federal, State,
and local governments, is needed to provide a long-term solution to the
continuing need for disposal of solid waste.
Research is needed to link disposal activities to effects on biota,
overall impacts of other pollutant sources, and long-term effects on Puget
Sound. DNR's lease fees could provide funds for continuing research by NOAA,
EPN, WDOE, and others. Also, the five-year shoreline permit provides a
mechanism for directing research at specific sites in step-wise increments. A
research effort implemented in this way by a central authority, DNR or WDOE,
could be well coordinated and managed. If Implemented by local governments
with incomplete perspectives and parochial concerns this type of research
effort would not solve existing problems.
6-28

-------
7. REDESIGNATION OF THE FOURMILE ROCK OPEN WATER DISPOSAL SITE
"Fourmile Rock" is the name of a designated dredged material disposal
site located in deep water in the Central Basin of Puget Sound. As Figure 7-1
indicates, it is slightly north of the entrance to Elliott Bay and southwest
of Westpoint. The Washington Department of Natural Resources (DNR) manages
and leases use of the site, which serves dredging projects in Seattle and King
County.
As discussed in Section 6, the need for disposal sites is created by
dredging to support economic growth and lack of upland landfill capacity.
These factors are all accentuated in Seattle and King County, the economic
center of the State. All the government agencies involved agree on the need
for continued disposal of dredged materials at a site accessible to this urban
and industrial area.
The Fourmile Rock site is within the jurisdiction of the City of
Seattle's Shoreline Master Program. Seattle initially issued a five-year
shoreline permit to DNR for the Fourmile Rock site in 1978. In the summer of
1983, the City granted a one-time, one-year extension of the permit as allowed
by State law. At the end of this period the City will be faced with consid-
ering permit re-issuance for the disposal site.(661)
Recent studies indicate that the site is contaminated with heavy metals
and toxic organics. Although concentratons of pollutants in the water column
are localized and transient because of dilution, other sampling studies have
shown bioaccumulation in plankton and elevated levels of organic compounds in
sediments collected at the disposal site.(14,28,29) Also, actual disposal
operations at an open water disposal site can smother indigenous invertebrates
and influence other aquatic fauna at a distance from the site due to redistri-
bution of material by currents.(67) Furthermore, sediments dumped at the site
in the future are likely to be contaminated because many dredging projects
that use the site for disposal involve maintenance or improvement of naviga-
tion channels, port facilities, and industrialized shipping and berthing
7-1

-------
'ISLAND! m :
Lff**
EVERETT
«
I
T
o / SNOHOMISH
3m,$ft 4
Elliott
Bay
D0th«H
Lake
Washington
•Redmond
r • twltvue . . 		
SEATTL
tliiott
SEE »»U«*qu«h
INSET «
Rtnton
\ K I N G
Auburn
4acoma
INSET
1	r
PIERCE
SCALE IN MILES
DDI
FIGURE 7-1
MAP OF SEATTLE AREA SHOWING DUWAMISH RIVER, ELLIOT BAY AND FOURMILE
ROCK OPEN WATER DISPOSAL SITE
Source: Final Feasibility Report and EIA. East West Duwamish Waterways Navigation
Improvement Study. US.C.O.E., Seattle District, January,1983
7-2

-------
areas. The City of Seattle has formed a Study Task Force to get a better
understanding of these issues in preparation for the shoreline permit decision
which must be made in the summer of 1984.
Because of these environmental concerns and the demand for this site,
Fourmile Rock was selected as a specific example of the general designation
process discussed previously. In Section 6 of this report, the relevant
agencies are introduced and their responsibilities outlined. This section
describes the specific decisions and procedures that will be used by the
Interagency Committee, DNR, the City of Seattle, and other agencies in the
case of the Fourmile Rock Disposal Site permit re-issuance.
7.1 THE DECISION-MAKING PROCESS
The decision-making process for the Fourmile Rock site will follow the
general pattern described in Section 6. This section presents more specific
details and distinguishes decisions or processes that have occurred from those
still needed.
Because DNR's activities and decisions are intertwined with those of the
Interagency Committee, the two are discussed together in Section 7.1.1. The
City of Seattle is introduced as an important new decision-maker in 7.1.2.
The City is the local shoreline managment agency with jurisdiction over
Fourmile Rock. Although much of the material pertains to Seattle's decisions
and opinions, environmental review and the SEFA process are presented in
7.1.3. WDOE and SHB involvement are discussed in 7.1.4,
7.1.1 DNR and the Interagency Committee
It is difficult to determine whether DNR directs the Committee or acts as
a result of Committee discussions and suggestions. The Interagency Committee
has been considering Fourmile Rock redesignation issues for over a year.
Scientific and political advice has been requested from NOAA's Pacific Marine
Environmental Laboratory, Seattle's Task Force on the Fourmile Rock Disposal
Site in Puget Sound, and other agencies and concerned parties. The Committee
and DNR have expressed interest to the point of soliciting pre-application
7-3

-------
information about local requirements for shoreline permit application and
approval. A City representative presented Seattle's requirements for local
shoreline permit renewal and environmental review at the Committee meeting on
September 28, 1983. Furthermore, no alternative sites have been proposed
during this period of deliberation.
Although Seattle's permit and environmental review criteria may cause
reconsideration, these points seem to indicate that DNR plans to apply for a
local shoreline permit to reauthorize the Fourmile Rock site* An official
decision will become available when DNR begins the permit application process
by completing a shoreline permit application and environmental checklist.
Seattle's shoreline master program procedures, timing, and criteria are
discussed next.
7.1.2 City of Seattle
This section describes the City of Seattle's shoreline management program
and its permitting procedures. Public notice requirements are also discussed.
7.1.2.1 The Seattle Shoreline Master Program
The Seattle Shoreline Master Program (SSMP) is set forth in Chapter 24.60
of the Seattle Municipal Code.(44) It is also incorporated in Chapter 173-19
of the Washington Administrative Code because the SSMP Implements the State
Shoreline Management Act of 1971. Seattle has primary responsibility for
implementing the regulatory program of the SMA locally* As a part of the
State Code, the SSMP has significance beyond its role as a zoning code and its
purpose differs from the rest of Seattle's zoning code* That purpose is Co
implement the policy and provisions of the SMA by regulating shorelines to:
•	Preserve, enhance, and Increase views of and access to the water
•	Encourage water-dependent uses
•	Provide for maximum public use and enjoyment of the City's
shoreline.(20)
The City's Department of Construction and Land Use (DCLU) (see Figure 7-2)
implements and manages the SSMP through the "Master Use Permit" system*
7-4

-------
LAND USE
SPECIALIST
LAND USE
DIVISION DIRECTOR
SENIOR
LAND USE
SPECIALIST
LAND USE
REVIEW MANAGER
DIRECTOR
FIGURE 7-2
CITY OF SEATTLE
DEPARTMENT OF CONSTRUCTION AND LAND USE
.(only relevant units shown)
7-5

-------
The SSMP divides the shoreline area under its jurisdiction into seven
environment classifications designated as:
•	Conservancy-NaturaL
•	Conservancy-Management
•	Urban Residential
•	Urban Stable
•	Urban Stable-Lake Union
•	Urban Stable-Central Waterfront
•	Urban Development (SSMP 24.60.325).
These classifications are significant in that they establish the management
objective for each area.
The Fourmile Rock disposal site is located in a Conservancy-Natural area.
The SSMP also designates areas of Puget Sound that are seaward of the line of
extreme low tide as "shorelines of statewide significance" (SSMP 26.60.305).
Only certain activities and use designations are allowed by the SMA for shore-
lines of statewide significance. Fourmile Rock is an area of statewide signi-
ficance -by this definition.
The SSMP regulations are quoted here to explain the purpose of the
Conservancy-Natural (CN) environment:
A. Within a city as highly urbanized as the City of Seattle, natural
areas are very few, small, and extremely difficult to preserve; yet
if the quality of life for future generations is to be maintained, a
significant part of that quality will relate to the existence and use
of natural areas.
8. The emphasis in the CN shoreline environment is on preservation and
restoration of natural systems and resources; and on prevention or
regulation of uses or activities that would degrade the natural
environment. Any proposed activity that would change the existing
situation would be desirable only if it further enhances, restores or
preserves the natural character of the area so classified.
7-6

-------
C.	The purpose of the CN shoreline environment designation is to pre-
serve, regulate or restore an area to its natural state, as nearly as
possible without human influence. Within such areas, only activities
which further, preserve, enhance or restore the existing natural geo-
logical, biological or hydrological conditions will be permitted,
such as: feeding, habitat improvement, ecological observation and
study or research, or other closely related activities.
D.	Access by the public to land area in CN environments will be limited
to natural trails, observation points, or special activities in
limited locations related to the specific area and its unique qual-
ities. Recreational use of CN designated land areas is intended to
be passive and generally noninteractive with the environment. Active
recreation, navigation, or landing and take-off of seaplanes may be
prohibited in specific water areas in this environment. The CN en-
vironment will also be used to designate a particularly biologically
or geologically fragile aspect of a geography and will therefore in-
dicate a requirement of any prospective user to provide evidence of
minimal impact (including adequate exploration of alternative designs
and strategies) to both that area and to the environment in general
(SSMP 24.60.330).
In addition, under a SMP, the specific activity undertaken is signifi-
cant. Open water disposal sites are considered "developments" requiring a
substantial development permit. Under the Seattle SMP, open water disposal of
dredged material is also considered a "landfill," which means "sand, soil,
gravel, or other material deposited onto a.wetland area, or into the water
over a submerged area" (SSMP 24.60.086). The SSMP regulations (24.60.730)
also state that landfill for natural beach protection in the Conservancy-
Natural environment is permitted as a "special use." Landfill that reduces
the area of the water's surface is prohibited. All other landfill Including
dredge disposal is a "conditional use" in the CN environment. Solid waste
such as broken concrete, building debris, appliances, car bodies, vegetation,
flammable material, or water soluble and/or toxic waste are prohibited as fill
material on both wetlands and submerged lands.
7.1.2.2 SSMP Permit Procedures
An application for an open water disposal site represents a landfill
development in a Conservancy-Natural environment and a shoreline of statewide
signifance, and requires a substantial development and a conditional use
permit from Seattle's Department of Construction and Land Use. Only one
7-7

-------
"Master Use and Construction Permit Application" is needed for such a dual
permit.
DCLU encourages applicants to have a pre-application conference.
Consultation with a City land use specialist often results in streamlined
processing of applications.(10) Although not formally announced as such, a
pre-application conference on the Fourmile Rock site has occurred. On
September 28, 1983, a Senior Land Use Specialist from DCLU spoke at a meeting
of the Interagancy Committee and presented Seattle's requirements for permit
renewal at the site. The DCLU representative also discussed environmental
review requirements.
Upon receipt of the DNR's application, the Seattle DCLU would assign a
Senior Land Use Specialist to review it. The SEPA environmental review
process and the Master Use Permit application decision-making process occur
simultaneously. DCLU would use the general procedures and criteria described
in Section 6.1.3. The Senior Land Use Specialist would also use some criteria
specific to the SSMP in reviewing the application and accompanying documents.
A substantial development permit is issued only when the development proposed
is consistent with the Shoreline Master Program of the City, including shore-
line goals and policies, and the provisions of the SMA. The applicant has the
burden of proving that the proposed substantial development is consistent with
these criteria. Uses identified as shoreline conditional uses, may be autho-
rized in specific cases upon approval by WDOE if the request complies with
the criteria mentioned in Section 6.1.3.1. The following general criteria ex-
cerpted from the SSMP, some of which apply to developments in shorelines of
statewide significance, must also be met:
•	All proposed developments must conform to permit requirements of all
other agencies having shoreline jurisdiction or responsibility
•	All proposed developments must conform with applicable Federal, State,
and local regulations relating to air and water quality and noise
pollution
•	The proposed development must satisfy any substantive requirements of
the State Environmental Policy Act
7-8

-------
•	Uses are preferred in the following order:
-	Water-dependent
-	Water-related
-	Non-water-dependent or non-water-related with regulated public
access
-	Non-water-dependent or non-water-related without regulated public
access
•	Applications for permits on shorelines of statewide significance are
evaluated in accordance with the principles outlined below and the
guidelines in WAC 173-16-040(5):
Recognize and protect the statewide interest over local interest
-	Preserve the natural character of the shoreline
-	Result in long-term over short-term benefit
Protect the resources and ecology of shorelines
-	Increase public access to publicly owned areas of the shorelines
Increase recreational opportunities for the public on the
shorelines
•	Uses which cause or result in significant concentrations of harmful
pollutants and materials subject to blowing which may enter runoff
waters shall provide means to insure that such pollutants will not
enter the water or air.(SSMP 24.60.525)
DCLTJ may require the applicant to supply additional information or data
needed to evaluate the application, to prepare an environmental assessment, or
to make a determination on the application. An application can be cancelled
if the applicant has failed without justification to supply required informa-
tion or data within 90 days of a written request.
Procedures for environmental review are found in Section 7.1.3.
7.1.2.3 Public Notice Requirements
Upon receipt of the application, the Master Use Permit Ordinance, WAC
173-14, requires that the DCLU place four placards near the development site,
publish a notice in the Department's Land Use Information Bulletin, and
publish two notices a week apart in the local paper to notify the public of
the application. The applicant must also erect a large sign near the proposed
7-9

-------
development to advertise the environmental review process to the public.
Since a proposed deep water dredge disposal site is removed from the public,
the Seattle DCLU Director would decide an appropriate location for the sign.
The public, environmental regulatory agencies included, has 30 days from the
last newspaper notice to comment on the application.(34)
The Director mak.es a decision on the application within 60 days following
publication of the second required notice, or within 15 days after issuance of
a final environmental impact statement, if required. These time limits do not
apply when the Director has requested additional information from the appli-
cant, the applicant modifies the application, public hearing on the applica-
tion is held, or other land use approvals are included in the application
(SSMP).
As part of the review process a public hearing may be held, particularly
where:
•	The proposed development has broad public significance
•	Fifty or more interested persons file a written request for a hearing
during the 30 day comment period
•	The cost of the proposed development, exclusive of land, will exceed
$500,000
•	The proposed development will require a shoreline conditional use or
variance permit.(SSMP)
Twenty days prior to the hearing, notice must be given. Also, written notice
must be mailed to people who request it, at least seven days prior to the
hearing date. Seattle gives substantial consideration to public comments in
its final decision.
After all relevant reviews and hearings are completed, the Director of
DCLU makes a decision. This may take more than two months. If continuous use
of the Fourmile Rock site is desired after July of 1984, DCLU must receive
DNR's completed application at least by May to allow time for permit pro-
cessing. If a lapse in the site's availability is not a concern, this time
constraint is less important.(661)
7-10

-------
In a permit approval, the Director may attach conditions regarding the
location, character and other features of the proposed use, including pro-
vision of a performance bond for up to five years. In authorizing a shoreline
conditional use, the Director may also impose requirements and conditions with
respect to location, installation, construction, maintenance and operation,
and extent of open spaces to protect other properties in the shoreline envi-
ronment and the public's interest in the shoreline. A fee may be charged for
a substantial development permit.
Certain time requirements also apply to all substantial development
permits. If a project for which a permit has been granted has not been com-
pleted within five years after approval of the permit, the Director reviews
the permit, and upon a showing of good cause, either extends the permit for
one year, or terminates the permit as provided in WAC 173-14.060. Seattle
has already exercised this one-time extension authority for the current DNR
permit.
However, Seattle can also issue a permit for less than five years. Such
an "interim" permit would be considered if information that would allow a
better Informed decision is expected after July, 1984.
Any ruling on an application, whether approved or denied, must be trans-
mitted to the applicant, and filed with WDOE and the Attorney General. Any
person aggrieved by the grant or denial of a substantial development permit
may seek review by the Shorelines Hearing Board by filing a request within 30
days of receipt of the final order, and by concurrently filing copies of the
request with WDOE and the Attorney General as provided in the Shorelines
Management Act.
Since WDOE has this review authority, Seattle's decision is considered a
recommendation to the State.(661)
7-11

-------
7.1.3 Environmental Review
Designation of the Fourmile Rock site is an action subject to environ-
mental review under SEPA. SEPA guidelines (WAC 197-20) establish uniform
procedures to reduce duplication, integrate planning and licensing by govern-
ment agencies, encourage public involvement, and promote certainty about
requirements. This section explains environmental review and public notice
according to the Washington Administrative Code.
7.1.3.1	Lead Agency Status
The lead agency in the SEPA process is responsible for the threshold
determination of the need for an environmental impact statement (EIS), and, if
required, for the supervision or actual preparation of a draft or final EIS.
The State agency that initiates a proposal, DNR in the case of Fourmile Rock,
becomes the lead agency. However, any agency may assume lead agency status,
if all agencies with jurisdiction agree. Challenges to lead agency status are
discussed in Section 7.1.3.3.
7.1.3.2	Threshold Determination
During environmental review, the lead agency must make a decision as to
whether .an EIS is required. This is done using the environmental checklist
included as Appendix B. However, where there is agreement that an EIS is
required, the checklist is unnecessary. Such agreement by all concerned
agencies is not certain for the Fourmile Rock redesignation process.
To complete the checklist, DNR may need to request additional information
from other agencies. The checklist is reviewed in the context of the whole
proposal, including direct and indirect effects, to determine if there will be
a significant adverse impact on environmental quality. Factors not on the
checklist are not considered in the threshold determination. The questions on
the checklist are not weighted. Some "yes" answers do not necessarily imply
environmental significance. The nature of the existing environment, the
absolute quantitative effects of the proposal, and the cumulative effects of
marginal impacts are all important factors. Of course, it may be impossible
to forecast environmental impacts precisely. If sufficient information is not
7-12

-------
available an EIS is required. If the checklist can be properly evaluated a
threshold determination should be available within 15 days.(13)
If DNR determines that Fourmile Rock redesignation does not require
preparation of an EIS, a proposed Declaration of Nonsignificance (DNS) is
prepared and distributed to other agencies with jurisdiction, which have 15
days to comment in writing. DNR also notifies the public at this time. After
this period and after considering comments the lead agency, DNR, may:
•	Adopt the proposed declaration as a final declaration
•	Determine that the proposal is significant
•	Gather additional information.
Seattle has stated that it will challenge DNR's lead agency status, as dis-
cussed in 7.1.3.3, if DNR issues a final DNS. If an affirmative threshold
determination is made, DNR circulates a Declaration of Significance and begins
preparing a draft EIS. No agency can repeat a threshold determination for the
same proposal.
7.1.3.3 Lead Agency Disputes
A lead agency challenge will occur in the Fourmile Rock case if Seattle,
or another agency, disagrees with a proposed DNS or believes that DNR is not
preparing a proper EIS.
Upon reviewing a proposed DNS, an agency, with jurisdiction may transmit a
"Notice of Assumption of Lead Agency Status" within the 15 day comment period.
This notice states that the consulted agency believes that an EIS is required
for the proposal and that the consulted agency assumes lead agency status from
the initial lead agency. The new lead agency then has the duty to prepare a
draft and final EIS.
Two or more agencies may agree to share responsibilities but one of them
must be the nominal lead agency. If the agencies cannot decide on a lead,
WDOE is petitioned to resolve the dispute.(13)
7-13

-------
7.1.3.4 Environmental Impact Statement
The purpose of the environmental impact statement (EIS) is to provide
environmental information for consideration by governmental decision-makers
before undertaking major actions. Time limits on the EIS process do not apply
when the proponent of the action is also the lead agency.
A draft EIS is used to inform public officials, project sponsors, and
interested citizens of a proposed governmental action and to inform the lead
agency of the public's concerns. It is focussed on assessment of adverse
impacts, consideration of alternatives, and analysis of measures to mitigate
impacts. A draft EIS must contain an introduction, table of contents, dis-
tribution list, and a description of the proposed action. The remaining sec-
tions may be varied but, in general, the following points must be considered:
•	Detailed, overly technical reports do not assist decision-makers
•	The scope should be sufficiently broad to be useful to other agencies
that must approve a proposal
•	The lead agency may limit the content and level of detail of some
sections to be proportionate with Che expected impacts
•	Other studies and data may be referenced, rather than explained in
detailed discussions
•	The relationship between short-term uses and long-term productivity is
important
•	Impacts that narrow the range of uses or pose long-term risks to human
health should be given special attention
•	A "reasonableness" test is intended to apply to the range of
alternatives considered.
A pre-draft consultation is usually held to discuss the contents of a draft
EIS. Agencies so consulted have 45 days to respond in writing.(13)
During its recent presentation to the Interagency Committee, Seattle
outlined its position on the reasons for and contents of an EIS for Fourmile
Rock.
7-14

-------
Seattle has two counterbalancing concerns about the Fourmile Rock site:
•	Concern over continued dumping of contaminated materials and potential
impacts
•	Constraints on the maritime industry and the need for continued
dredging to support economic growth.
Seattle believes an EIS is necessary to highlight consequences and
alternatives such as capping or moving the site and developing upland sites.
The City proposed that the following topics be addressed in a "limited issue"
EIS before next summer's shoreline permit decision:
•	Description of existing conditions using data collected by METRO,
NOAA, the Port of Seattle, and EPA, when it becomes available
•	Recommendations for a research program based on proposals by NOAA (28)
•	Consideration of upland disposal and regional planning approaches
•	Description of measures for mitigating the effects and consequences of
using the site
•	Exploration of alternative sites.(66 I)
The Corps of Engineers has suggested that such a study could cost more than
$100,000. SEPA guidelines neither authorize nor prohibit imposition of fees
to cover the costs of EIS preparation. However, consulted agencies may not
charge the lead agency for providing data or comments during the EIS pro-
cess. (13) Members of the Interagency Committee have agreed to investigate
funding options.
7.1.3.5 Public Notice Requirements
After a draft EIS is developed it is circulated for review for 35 days.
To accomplish notification, WD0E publishes a weekly listing of all DNSs, draft
EISs, and final EISs, known as the "SEPA Register." The SEPA regulations
establish a long list of Federal, State, and local agencies that must be
notified and an even longer list of agencies that may be consulted for their
7-15

-------
environmental expertise. If a consulted agency does not respond within the
allowed time, the lead agency may assume that it has no comments and bar the
agency from registering objections later in the process. Public hearing rules
are the same as those for SMA.
The lead agency should prepare a final EIS within 75 days of issuance of
the draft EIS unless it is unusually complex. The final EIS must contain a
summary of comments received, an explanation of changes to the text made in
response to comments, and a summary of critical comments with which it does
not agree. This document is circulated in the same manner as the draft EIS.
The lead agency may take no action for seven days after the final EIS is dis-
tributed. After that it can be used in decision-making by the lead agency and
other agencies with jurisdication.
7.1.4 Review by WDOE and SHB
WDOE's review of Seattle's recommended decision on the DNR permit would
likely not result in any new decisions. The Operations Management Division
represents WDOE on the Interagency Committee and the Shorelands Division re-
views local permit decisions. Presumably, these divisions would consult with
each other well before the Interagency Committee recommendation to pursue a
permit. If all of WDOE's concerns are addressed early in the process, WDOE
should have no objections to Seattle's final approval of the permit. However,
WDOE could impose additional conditions on the permit. If Seattle denies the
permit, WDOE considers the decision final.
The Shorelines Hearing Board .can review a final decision, if requested,
whether it is an approval or denial. In the case of approval, a variety of
citizen's groups may appeal for SHB review. Seattle residents, especially in
the Queen Anne and Magnolia communities on the Northside of Elliott Bay, per-
ceive a connection between the Fourmile Rock decision and continued growth
and development of the area.(661) The Duwamish Navigation Improvement Pro-
ject depends on the availability of economical disposal sites near the river.
Other related issues are the potential uses of Piers 90 and 91, which include
Naval facilities, filling and commercial/ industrial development. Individuals
7-16

-------
or groups opposed to either project, or growth in general, could appeal for
SHB review. In the case of denial, affected groups, like the Port of Seattle,
sponsor of the Duwamish Project, or the Corps of Engineers, a major dredger of
navigation channels, could appeal to SHB.
Since there are proponents of both sides of the issue, it is probable
that SHB will be involved in the decision on redesignation of the Fourmile
Rock Disposal site. The SHB will decide on the merits of the case.
7.2 OBSTACLES TO DECISION-MAKING
This section discusses technical and administrative obstacles to the
redesignation process. Funding problems are also described.
7.2.1 Technical Obstacles
The same problems of lack of information discussed previously apply
particularly to the Fourmile Rock site. Scientists and regulators are con-
cerned because studies show that sediments at the site are currently enriched
with heavy metals and toxic organic pollutants.(24) There are additional con-
cerns about dredged materials that may be dumped at Fourmile Rock in the fu-
ture. For example, dredging for navigation or docking occurs frequently in
the lower Duwamish River in Seattle. Fish and sediments containing elevated
concentrations of pesticides, polychlorinated benzenes and polycyclic aromatic
hydrocarbons, as well as diseased bottom fish, have been found there.(29)
However, there is not yet enough information to link observed contaminant
levels to effects on organisms. Nor are there numerical criteria for deter-
mining what contamination levels are acceptable at the site and in dredged
sediments. Without these criteria it is difficult to evaluate fully the im-
pact of current and planned disposal activities at Fourmile Rock.
Research projects are being conducted in the Sound by NOAA, EPA, WDOE,
METRO, and others. However, research agendas do not focus solely on the
Fourmile Rock site, since they are concerned with larger issues. These on-
going studies will eventually provide more clues as to the disposition of
Fourmile Rock and recommendations for managing it in an environmentally sound
7-17

-------
manner. Today, though, a thoroughly informed decision cannot be made. As a
condition of permit approval, the City of Seattle may request assurances that
this research would be done in a timely manner.(661)
7.2.2	Administrative Obstacles
The City of Seattle can place conditions on a permit for Fourmile Rock if
it is approved. This causes regulatory uncertainty because other environ-
mental and management agencies and developers cannot know what the conditions
will be. Examples of options that may be considered include:
•	Shortened Time Limit - A one-or-two-year "interim" permit could be
issued if, for example, the EIS takes a long time to complete
•	Monitoring Requirements - Monitoring could be required for the site
and/or the material dumped to develop better data for future decisions
•	Research Requirements - Approval could be conditioned on completion,
or initiation, of specific studies by specific agencies.
7.2.3	Funding Obstacles
A major question left unresolved at the last Interagency Committee
meeting was paying for the EIS. A Corps of, Engineers representative, who is
familiar with EISs, suggested that $100,000 or more might be needed for a
study of the type proposed by Seattle. DNR's lease fees for the site, about
$4,000 per year, barely cover administrative and management costs. WDOE is
investigating the possibility of using funds allocated for solid waste manage-
ment.
7.3 CONCLUSIONS
The City of Seattle has clearly stated its position regarding the EIS.
An EIS will need to be funded and initiated quickly to serve as an input to
Seattle's permit renewal decision. Even if the City issues an Interim per-
mit next year, a final EIS will be needed within a year or two. Seattle's
straightforward presentation of its permit requirements sets the framework for
interagency coordination, which has the potential to facilitate the permitting
process.
7-18

-------
Investigation of the disposal site should be accompanied by investigation
of upland disposal alternatives. Alternative sites must be available for
contaminated materials, if there are to be options other than disposal in
water or termination of dredging.
Both the SEFA process and the SMA permit process allow many public input
points. Public involvement is likely to be extensive in the Fourmile Rock
case because of related pollution and growth issues. The public perceives
discharges at Fourmile Rock as a way of spreading relatively stable sediments
from inside Elliott Bay out into the main basin of Puget Sound. The public
also connects the growth and development of port facilities in the lower
Duwamish and at Piers 90/91, unwanted by some, to the continued need for
dredging and disposal at Fourmile Rock.
Research is needed to fill known information gaps and others identified
by the EIS. The EIS has the potential for outlining new research efforts that
will need to be funded and implemented. For implementing research efforts,
the local permit allows Seattle to place conditions, such as monitoring or
fees, on the use of the site.
7-19

-------
APPENDICES

-------
APPENDIX A
PUGET SOUND WATER QUALITY DECISION-MAKING STUDY
QUESTIONNAIRE

-------

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
WASHINGTON. D.C. 20460
OFFICE OF
WATER
MEMORANDUM
SUBJECT: Puget Sound Water Quality Decision-Making Study
FROM: Bob Linett, Project Office
TO:
Recipients
A study of certain water quality decision-making processes affecting
Puget Sound Is being conducted by JRB Associates for EPA Headquarters, in
cooperation with EPA Region X. The general and specific decision-making
processes under evaluation are:
o	Clean Water Act Section 301(h) waivers
o	Clean Water Act Section 404 dredge and fill permits
o	Duwamish River deepening project
o	Designation of dredged spoil dumpsites
o	Redesignatlon of the Fourmlle Rock dredged spoil dumpslte.
Those of you receiving this memorandum and the attached questionnaire have
been selected on the basis of expertise in one or more of the areas listed
above*
The questionnaire is designed to elicit information necessary to evaluate
the decision-making processes under study. It is focused on such factors as
key participants in the decision process, timing and sequencing of the
process, and any obstacles to decision-making such as lack of technical data
and institutional or statutory constraints. Tour expertise on these issues is
essential to the study.
Please complete the questionnaire by September 23. In certain cases,
interviews with JRB analysts will be arranged during the week of September 26.
The questionnaire you receive will indicate whether it should be mailed
directly to JRB or held for discussion at an interview. If your expertise
includes more than one decision process under evaluation, please fill out a
separate questionnaire for each one.
Your cooperation in this study is greatly appreciated. If you have any
questions, please do not hesitate to call John Underwood (442-0966) or Tom
Wilson (442-1413) at Region X.

-------
Questionnaire for Puget Sound
Water Quality Decision-Making Study
Name		
Position .
Division 	
Agency	_
Phone 		
This questionnaire is part of an EPA study of regulatory decisions that
can affect the water quality of Puget Sound. Three general and two specific
decison-making processes are being Investigated:
~	CWA Section 301(h) waivers
~	CWA Section 404 dredge and fill permits
~	Duwamish River deepening project
~	Designation of dredged spoil dumpsites
~	Redesignation of the Fourraile Rock dumpsite.
Please complete the questionnaire only for the area in which you are
directly involved, indicating the appropriate box above.
If you have input to more than one of these decisions, please complete a
separate questionnaire for each.
Please complete this questionnaire by September 23 and bring it with you
to the interview scheduled with JRB analysts during the week of September 26.
1

-------
Background
1. How is the decision-making process initiated (i.e., by which agency and
in what way)?
2. How is your agency informed of its initiation?
3. What is the nature of your agency's involvement in the decision-making
process (e.g., review of information for ultimate decision or for
advisory opinion)?
4. (a) How many divisions and individuals within your agency are
responsible for input to the decision?
(b) List the divisions and their roles.
2

-------
(c) List the staff positions and their roles.
Information, Timing and Criteria
5. What group provides the information necessary to reach a decision?
6. How long does it take to acquire the necessary information?
7. Once all the necessary information is acquired, how long does the evalu-
ation take?
8. Is there a required time limit on your review?
3

-------
9. What evaluation criteria, such as regulations or guidelines, are used to
reach a decision?
10. To which agency or office 1s your decision transmitted?
Obstacles
11. What technical problems, such as lack of data-or conflicting Information,
are encountered in the decision-making process?
12. What administrative difficulties are encountered (e.g., lack of suffl
cient time or personnel, or incomplete applications)?
13. What statutory or regulatory problems, such as insufficient criteria, are
encountered?

-------
14. What other obstacles typically arise?
Coordination with Other Agencies
15. To your knowledge, what other federal, state or local agencies are
Involved in the decision-making process?
16. What are their roles in the process?
17. (a) Is their review simultaneous with yours?
(b) If not, in what order do the reviews occur?
5

-------
18. Are other agencies allotted the same amount of time for review as yours
is?
19. (a) Does your agency rely on input from another agency before a final
decision can be reached?
(b) If so, what agency supplies this information and what is the nature
of this input?
(c) Are there obstacles to this information flow?
20. (a) Must another agency receive your input before a final decision can
be reached? If so, which agency? .
6

-------
(b) Are there obstacles to this process?
21. (a) What agency coordinates Inputs to the decision-making process?
(b) How Is this accomplished?
22. How Is your review affected if another agency:
(a) denies the permit, approval or certification?
(b) objects to the proposed action?
(c) fails to approve, deny or comment within the allotted time?
7

-------
Environmental Impact Statement
23. (a) When and by what agency is an Environmental Impact Statement
required?
(b) At what point in the decision-making process is this determination
made?
24. (a) Which agencies review an Environmental Impact Statement?
(b) Which agency is responsible for the final decision on the Environ-
mental Impact Statement?
25. How does approval of an Environmental Impact Statement affect the grant
or denial of a permit or certification?
8

-------
Public Input
26. (a) Is public notice of the proposed action required?
(b) When, for how long, in what form, and by what agency must notice be
given?
27. (a) Is a public comment period required?
(b) How long is it?
28. What effect do negative public comments have on the decision-making
process?

-------
29. (a) Must public hearings be held?
(b) What triggers non-mandatory public hearings?
(c) At what point in the process does this occur?
(d) How does a public hearing affect the time frame for decision-making?
30. How and by whom are the results of a public hearing incorporated into the
decision?
31. What obstacles to informed public input are likely to arise?
10

-------
Please attach a copy of the following documents:
1.	An organizational chart of your agency and division.
2.	A flow chart of the decision-making process within your agency.
3.	A copy of the regulations or guidelines that serve as criteria for the
decision.
11

-------
APPENDIX B
STATE OF WASHINGTON ENVIRONMENTAL CHECKLIST FORM

-------
APPENDIX B
STATE OF WASHINGTON ENVIRONMENTAL CHECKLIST FORM
The State Environmental Policy Act of 1971, Chapter 43.21, Revised Code of
Washington, requires all state and local governmental agencies to consider
environmental values both for their own actions and when licensing private pro-
posals. The Act also requires that an Environmental Impact Statement (EIS) be
prepared for all major actions significantly affecting the quality of the
environment. The purpose of this checklist is to help the agencies involved
determine whether or not a proposal is such a major action.
Applicants must answer the following questions as completely as possible with
the information presently available. Where explanations of answers are
required, or where an explanation would be helpful to government decision
makers, include an explanation in the space provided, or use additional pages if
necessary. Include references to any reports or studies which are relevant to
the answers provided. Complete answers to these questions will help all agen-
cies involved with a proposal to undertake the required environmental review
without unnecessary delay.
The following questions apply to your total development proposal, not just to
the license for which an applicant is currently applying or the proposal for
which approval is sought. Answers should include the impacts which will be
caused by a proposal when it is completed, even though completion may not occur
until sometime in the future. This will allow all of the agencies which will be
involved to complete their environmental review now, without duplicating paper-
work in the future.
NOTE: This is a standard form being used by all state and local agencies in the
State of Washington for various types of proposals. Many of the questions may
not apply to your proposal. If a question does not apply, just answer it "no"
and continue on to the next question.
WL:nrd
IB5/209.16
- 16 -

-------
ENVIRONMENTAL CHECKLIST FORM
I. BACKGROUND
A. Name of Proponent:
B. Address and Phone Number of Proponent:
C. Date Checklist Submitted:
D. Agency Requiring Checklist:
E. Name of Proposal, if applicable:
F. Nature and Brief Description of the Proposal (including
but not limited to its size, general design elements,
and other factors that will give an accurate understanding
of its scope and nature):
G. Location of Proposal (describe the physical setting of the
proposal, as well as the extent of the land area affected by
any environmental impacts, including any other information
needed to give an accurate understanding of the environmental
setting of the proposal):
- 1 -

-------
H. Estimated Date of Completion of the Proposal:
I. List of all Permits, Licenses, or Government Approvals
Required for the Proposal (federal, state and local-
including rezones):
J. Do you have any plans for future additions, expansion, or
further activity related "to or connected with this proposal?
If yes, explain:
K. Do you know of any plans by others which may affect the property
covered by your proposal? If yes, explain:
L. Attach any other application form that has been completed
regarding the proposal; if none has been completed but is
expected to be filed at some future date, describe the
nature of such application form:

-------
II. ENVIRONMENTAL IMPACTS
(Explanations of all "yes" and "maybe" answers are required).
Yes Maybe No
A. Earth. Will the proposal result in:
1.	Unstable earth conditions or in
changes in geologic substructures?		 	 	
2.	Disruptions, displacements, com-
paction, or overcovering of the
soil?		 	 	
3.	Change in topography or ground
surface relief features?		 		
4.	The destruction, covering, or
modification of any unique
geologic or physical features?		 		
5.	Any increase in wind or water
erosion of soils, either on or
off the site?		 	 	
6.	Changes in. deposition or
erosion of beach sands, or
changes in siltation, deposi-
tion, or erosion which may
modify the channel of a river
or stream or the bed of the
ocean or any bay, inlet or
lake?		 	 	
Explanation:
B. Air. Will the proposal result in:
1.	Air emissions or deterioration
of ambient air quality?
2.	The creation of objectionable
odors?
- 3 -

-------
3. Alteration of air movement,
moisture or temperature, or any
change in climate, either
locally or regionally?
Explanation:
Water. Will the proposal result in:
1.	Changes in currents, or the
course of direction of water
movements, in either marine or
fresh water?
2.	Changes in absorption rates,
drainage patterns, or the
amount of surface water run-
off?
3.	Alterations to the course or
flow of flood waters?
4.	Change in the amount of surface
water in any water body?
5.	Discharge into surface waters,
or in any alteration of sur-
face water quality, including
but not limited to temperature,
dissolved oxygen, or turbidity?
6.	Alteration of the direction or
rate of flow of ground waters?
7.	Change in the quantity of
ground waters, either through
direct additions or withdrawals,
or through interception of an
aquifer by cuts or excavation?
8.	Deterioration in ground water
quality, either through direct
injection or through the seepage
of leachate, phosphates,
detergents, waterborne virus or
bacteria, or other substances
into the ground waters?

-------
9. Reduction in the amount of water
otherwise available for public
water supplies:
Explanation:
Flora. Will the proposal result in:
1.	Change in the diversity of species,
or numbers of any species of flora
(including trees, shrubs, grass,
crops, micro-flora and aquatic
plants)?
2.	Reduction of the numbers of
any unique, rare or endangered
species of flora?
3.	Introduction of new species of
flora into an area, or in a
barrier to the normal replen-
ishment of existing species?
4.	Reduction in acreage of any
agricultural crop?
Explanation:
Fauna. Will the proposal result in:
1.	Changes in the diversity of
species, or numbers of any
species of fauna (birds, land
animals including reptiles,
fish and shellfish, benthic
organisms, insects, or micro-
fauna)?
2.	Reduction of the numbers of
any unique, rare or endangered
species of fauna?
3.	Introduction of new species of
fauna into an area, or result in
a barrier to the migration or
movement of fauna?

-------
4. Deterioration of existing
wildlife habitat?
Explanation:
Noise; Will the proposal increase
existing noise levels?
Explanation:
Light and Glare. Will the proposal
produce new light or glare?
Explanation:
Land Use. Will the proposal result
in the alteration of the present or
planned land use of an area?
Explanation:
Natural Resources. Will the pro-
posal result in:
1.	Increase in the rate of use
of any natural resources?
2.	Depletion of any nonrenewable
natural resource?
Explanation:
Risk of Upset. Does the proposal
involve a risk of an explosion or
the release of hazardous substances
(including, but not limited to oil,
pesticides, chemicals or
radiation) in the event of an
accident or upset conditions?
Explanation:

-------
K. Population. Will the proposal
alter the location, distribution,
density, or growth rate of the
human population of an area?
Explanation:
k* Housing. Will the proposal affect
existing housing or create demand
for additional housing?
Yes Maybe No
Explanation:
M. Transportation/Circulation. Will
the proposal result in:
1.	Generation of additional
vehicular movement?
2.	Effects on existing parking
facilities, or demand for
new parking?
3.	Impact upon existing trans-
portation systems?
4.	Alterations to present
patterns of circulation or
movement of people and/or
goods?
$. Alterations to waterborne,
rail, or air traffic?
6. Increase in traffic hazards
to motor vehicles, bicyclists
or pedestrians?
Explanation:
- 7 -

-------
Public Services. Will the proposal
have an effect upon, or result in a
need for new or altered governmental
services in any of the following
areas:
1.	Fire protection?
2.	Police protection?
3.	Schools?
4.	Parks or other
recreational facilities?
5.	Maintenance of public facili-
ties, including roads?
6.	Other governmental services?
Explanation:
Energy. Will the proposal result in:
1.	Use of substantial amounts of
fuel or energy?
2.	Demand upon existing sources
of energy, or require the
development of new sources of
energy?
Explanation:
Utilities. Will the proposal result
in a need for new systems, or altera
tions to the following utilities:
1. Power or natural gas?

-------
2.	Communications systems?
3.	Water?
5. Seer or septic tanks?
5.	Storm water drainage?
6.	Solid waste and disposal?
Explanation:
Human Health. Will the proposal
result in the creation of any health
hazard or potential health hazard
(excluding mental health)?
Explanation:
Aesthetics. Will the proposal
result in the obstruction of any
scenic vista or view open to the
public, or will the proposal
result in the creation of an
aesthetically offensive site
open to public view?
Explanation:
Recreation. Will the proposal result
in an impact upon the quality or
quantity of existing recreational
opportunities?
Explanation:

-------
T. Archaeological/Historical. Will the
proposal result in an alteration of
a significant archaeological or
historical site, structure, object
or building?
Explanation:
II I, the undersigned, state that to the best of my knowledge the above
information is true and complete. It is understood that the lead
agency may withdraw any declaration of non-significance that it
might issue in reliance upon this checklist should there be any
willful misrepresentation or willful lack of full disclosure on my
part.
Proponent:
Date: 	
This checklist was reviewed by	
Environmental Specialist, Department of Construction and Land Use. Any
comments or changes made by the Department are entered in the body of the
checklist and contain the initials of the reviewer.
IB5/CK .LIST10
- 10 -

-------
APPENDIX C
BIBLIOGRAPHIES

-------
APPENDIX C
BIBLIOGRPAHY
1.	American Society of - Civil Engineers. 1983 Coastal Zone '83. Proceedings of
the Third Symposium on Coastal and Ocean Management. Orville J. Magoon and
Hugh Converse, ed. American Society of Civil Engineers, New York, New York.
Vol. I-III.
2.	Baker, E.J., 1982. Suspended Particulate Matter in Elliott Bay. U.S. Department
of Commerce. National Oceanic and Atmospheric Administration. NOAA Technical
Report ERL417-PMEL35. Environmental Research Laboratories. 44 pp.
3.	Bish, R.L., Warren, R., Weschler, L.F., Crutchfield, J.A., Harrison, P., Coastal
Resource Use - Decisions on Puget Sound. 1975. University of Washington Press.
206 pp.
4.	Bish, R.L. 1982. Governing Puget Sound. University of Washington Press.
Seattle, Washington. 137 pp.
5.	Booz, Allen and Hamilton, Inc. Resource Assessment of the Section 404 Dredge
and Fill Program Draft Final Report. 1980. Bethesda, Maryland.
6.	Cardvell, R.D., Olsen, S., Carr, M.I.,. Sanborn, E.W. 1979. Causes of Oyster
Larvae Mortality in South Puget Sound. NOAA Technical Memorandum, ERL MESA-39.
Environmental Research Laboratories. Boulder, Colorado. 73 pp.
7.	CED. Report to the Chairman, Committee on Merchant Marine and Fisheries House
of Representatives. 1980. Washington, D.C.
8.	Dames and Moore. 1981. Baseline Studies and Evaluations for Commencement Bay
Study/Environmental Impact Assessment. Vol. I: Summary and Synthesis. Prepared
for U.S. Army Corps of Engineers. Seattle, Washington. Contract No. DAC W67-80-
C-0101. 43 pp.
9.	Department of the Army, Office of the Chief of Engineers. 1979. Digest of
Water Resources Policies and Authorities. Washington, D.C. Pamphlet No.
1165-2-1.
10.	Department of Construction and Land Use, City of Seattle. September 1983. Infor-
mation Bulletin No. 209. 10 pp.
11.	Department of Construction and Land Use, City of Seattle. May 1981. Information
Bulletin No. 208. 10 pp.
12.	Department of Ecology, Office of Water Programs, Water Quality Management
Division. 1983. FY 1984 Water Quality Management Program. Olympia, Washington.
13.	Department of Ecology. 1978. Guidelines: State Environmental Policy Act.
Olympia, Washington.
14.	Dexter, R.N., Anderson, D.E., Quinlan, E.A., Goldstein, L.S., Strickland, R.M. ,
Pavlou, S.P., Clayton, J.R., Kocan, R.M., Landolt, M. 1981. A Summary of
Knowledge of Puget Sound Related to Chemical Contaminants. NOAA Technical
Memorandum OMPA-13. Office of Marine Pollution Assessment. Boulder, Colorado.
435 pp.

-------
15. Federal Register, November 26, 1982, p. 53677.
16.	Federal Register, July 22, 1982, p. 31821.
17.	Federal Register, December 24, 1980.
18.	Fox, N. , Heikkala, S., Dearborn, K., Hershman, M. , Sorenson, J. 1983. Shoreline
Master Program Study: Analysis Report. Prepared for the Washington State Depart-
ment of Ecology.
19.	Harper-Owes. .1983. Water Quality Assessment of the Duwamish Estuary, Washington.
Prepared for Municipality of Metropolitan Seattle. 193 pp.
20.	Hulsizer, E.J. Why We Need to Study the Seattle Shoreline Program. Seattle,
Washington. 1982. 8 pp.
21.	JRB Associates. 1983. Dynamics of Biological Impacts of Toxicants in the Main
Basin of Puget Sound and Lake Washington. Vol. Is Evaluation of Toxicant Distri-
bution, Transport and Fate. Draft Report. Prepared for Municipality of Metro-
politan Seattle. JRB Project No. 2-817-03-856-53. Seattle, Washington. 328
pp.
22.	JRB Associates. 1983. Assessment of Program Guidance Needs for Estuaries.
Draft Final Report. Prepared for U.S. Environmental Protection Agency, Office
of Water Regulations and Standards. Washington, D.C. EPA Contract No.
68-01-6348. 35 pp.
23.	JRB Associates. 1983. State Potential for Assuming a 404 Program: Region
X. Report submitted to U.S. Environmental Protection Agency, Office of Federal
Activities. Washington, D.C. EPA Contract No. 68-01-6087. 99 pp.
24.	JRB Associates. 1983. Dynamics and Biological Impacts of Toxicants in the
Main Basin of Puget Sound and Lake Washington - Volume III: Assessment of Puget
Sound Toxicant Problems and Implication to Metro's Water Pollution Control and
Environmental Planning. Draft Final Report. Prepared for the Municipality
of Metropolitan Seattle in partial fulfillment of the obligations under Metro
Resolution 3677. Bellevue, Washington. 63 pp.
25.	Jones and Stokes Associates, Inc. 1983. Water Quality Management Program for
Puget Sound. Draft Report Nos. 1 and 2. Prepared for U.S. Environmental Protec-
tion Agency, Region X.
26.	League of Women Voters of Washington. 1983. Public Perception of the Washington
Shoreline Management Act., Submitted to Washington State Department of Ecology.
27.	Lee, N. , Nichols, B. 1982. Environmental Quality Problems Associated With
Estuaries: A Pilot Study. Final Report. Prepared by JRB Associates, McLean,
Virginia for U.S. Environmental Protection Agency, Program Integration and Evalua-
tion Branch, Washington, D.C. EPA Contract No. 68-01-6348. 11 pp. and 9
indexes.

-------
28.	Long, E.R., A Multidisciplinary Approach to Assessing PolluCion in Coastal Waters.
Abstract. Reprinted from the Proceedings of the Third Symposium on Coastal
and Ocean Management ASCE/San Diego, California, June 1-4, 1983.
29.	Malins, D.C., McCain, B.B.-, Brown, D.W., Sparks, A.K., Hodgins, H.O. 1980.
Chemical Contaminants and Biological Abnormalties in Central and Southern Puget
Sound. NOAA Technical Memorandum 0MPA-2. Office of Marine Pollution Assessment.
Boulder, Colorado. 295 pp.
30.	Malins, D.C., Chan, S.L., McCain, B.B., Brown, D.W., Sparks, A.K.,
H.O. 1981. Puget Sound Pollution and Its Affects on Marine Biota.
Report submitted to Marine EcoSystems Analysis (MESA) Puget Sound
Seattle, Washington. 74 pp.
31.	Massath, G.J., Feely, R.A.,	Lamb, M.F. 1982. Elemental Composition	of Suspended
Particulate Matter in the	Lower Duwamish River and Elliott Bay,	Washington.
NOAA Technical Memorandum	0MPA-17. Office of Marine Pollution	Assessment.
Boulder, Colorado. 44 pp.
32.	METRO. 1983. Duwamish Clean Water Plan. Draft. Municipality of Metropolitan
Seattle. Seattle, Washington. 19 pp.
33.	NOAA. 1980. Data Catalog for the Marine Ecosystems Analysis Puget Sound Project.
Distribution and Summarization of Digital Data. U.S. Department of Commerce,
National Oceanic and Atmospheric Administration. Washington, D.C. 87 pp.
34.	NOAA. 1983. The Washington State Permit Process for Establishing Open Water
Dredge Disposal Sites. U.S. Department of Commerce, National Oceanic and Atmos-
pheric Administration. Washington, D.C. 24 pp.
35.	Pacific Marine Environmental Laboratory. 1982. FY 80-82 Final Report. Estuarine
and Coastal Pollutant Transport and Transformation. The Role of Particulates.
A project under the NOAA/OMPA Section 202 research program. Herbert C. Curl,
Jr., ed. U.S. Department of Commerce, National Oceanic and Atmospheric Admin-
istration. Environmental Research Laboratories. 228 pp.
36.	Puget Sound Air Control Agency. 1983. Attaining and Maintaining the Lead
Standard in Washington State. Proposed for inclusion in the Washington State
Air Quality Implementation Plan. Washingtpn State Department of Ecology, Olympia,
Washington. 46 pp.
37.	Puget Sound Council of Governments. 1980. Central Puget Sound Region Growth
Profiles. Seattle, Washington. 17 pp.
38.	Riley, R.G., Crecelius, E.A., O'Malley, M.L., Abel, K.H., Mann, D.C. 1981.
Organic Pollutants in Waterways Adjacent to Commencement Bay (Puget Sound).
NOAA Technical Memorandum OMPA-12. Office of Marine Pollution Assessment.
Boulder, Colorado. 90 pp.
Hodgins,
Progress
Project.

-------
39
40
41
42
43
44
45
46
47
48
49
50
51
52
Sakrison, R.G. 1982. Comparison of State and Local Management Activities and
Federal Requirements for Transfer and Operation of State 404 Program. Washington
Department of Ecology. Olympia, Washington.
Sakrison, R.G. Final Report. Feasibility Study of State Assumption of Section
404 Program (Discharge of Dredge and Fill Material). EPA Grant #808976-01-1,
Task V.
Schell, W.R., Collias, E.E., Nevissi, A., Ebbesmeyer, C.C., et al. 1976. Trace
Contaminants from Duwamish River Dredge Spoils Deposited Off Fourmile Rock in
Elliot Bay. Report prepared for Municipality of Metropolitan Seattle. Seattle,
Washington. 105 pp.
Seattle Department of Construction and Land Use, Pre-Application Checklists.
9/26/83. 3 pp.
Seattle Department	of Construction and Land Use, Master Use Permit Intake
Checklist. 5 pp.
Seattle Shoreline	Master Program, Chapter 24.60, Shoreline Master Program
Regulations. 1983.	61 pp.
Shapiro and Associates, Inc., 1983. Inventory of Wetland Resources and Evaluation
of Wetland Management in Western Washington. Prepared for Washington State
Department of Ecology. Seattle, Washington. 101 pp.
URS Company. 1983. Resource Use Conflicts in Puget Sound Solution Alternatives.
Draft Report. 58 pp.
U.S. Army Corps of Engineers. Permit Program, A Guide to Applicants. November
1, 1977." EP 1145-2-1. 20 pp.
U.S. COE. 1979. Digest of Water Resources, Policies and Authorities. Department
of the Army. Office of the Chief of Engineers. Washington, D.C. EP 1165-2-1.
U.S. DOI. 1982. East, West and Duwamish Waterways Navigation Improvement Study.
Fish and Wildlife Coordination Act Report. United States Department of the
Interior. Fish and Wildlife Service. Region I. Olympia, Washington. 54 pp.
U.S. EPA. 1979. Notice of Approved Action. Washington State Dairy Waste Water
Quality Management Plan. U.S. Environmental Protection Agency, Region X.
Seattle, Washington.
U.S. EPA. 1981. Wastewater Management Plan for the Lake Washington/Green River
Basins. Final Environmental Impact Statement. U.S. Environmental Protection
Agency. Region X. Seattle, Washington. EPA 910/9-80-077.
U.S. EPA. 1982. Commencement Bay Remedial Response Fact Sheet. U,S.
Envrionmental Protection Agency. Region X. Seattle, Washington. 41 pp.

-------
53.	U.S. EPA. 1982. Harbor Island Work Sheets. Region X. Seattle, Washington.
54.	Washington Administrative Code: Chapter 332-30, Aquatic Land Management. 16
pp.
55.	Washington Administrative Code: Chapter 220-110, Hydraulic Code Rules. 23
pp.
56.	Washington Administrative Code: Chapter 173-201, Water Quality Standards for
Waters of the State of Washington. 11 pp.
57.	Washington Administrative Code: Chapter 173-14, Permits for Developments on
Shorelines of the State. 10 pp.
58.	Washington Coastal Currents. August 1983. Olympia, Washington. 8 pp.
59.	WDOE. 1976. Washington State Coastal Zone Management Program. Washington
Department of Ecology. Olympia, Washington. 153 pp.
60.	WDOE. 1979. Washington State Implementation Plan. Washington Department of
Ecology. Office of Air Programs. Olympia, Washington.
61.	WDOE. 1983. Commencement Bay/Nearshore Tideflats Cooperative Agreement
Remedial Investigation (CX810926-01-0). Office of Field Operations. Washington
Department of Ecology. Olympia, Washington.
62.	WDOE. 1983. FY 1984. Water Quality Management Program. Prepared by Water
Quality Managment Division, Office of Water Programs, Washington Department
of Ecology. Olympia, Washington. 69 pp.
63.	Washington Department of Fisheries. 1931. Significant Areas for Certain Species
of Food Fish and Shellfish in Puget Sound. Technical Report 59. Olympia,
Washington. 45 pp.
64.	Washington Department of Fisheries. 1983. Location, Harvest and Economic Values
of Salmon, Bailfish, Groundfish and Shellfish Resources, Summarized from the
WDF-Sponsored Testimony in the Northern Tier Pipeline Case (Proposed Cross-Sound
Route) With Updated Figures for 1979 and 1980. Technical Report No. 76. 136
pp.
65.	Personal Communications August 15-18, 1983. Seattle, Washington.
A.	Armstrong, John, Biologist, Ocean Programs Team, USEPA, Region X. Seattle,
Washington.
B.	Carroll, Florence, NPDES Data Systems, Water Permits and Compliance Branch.
USEPA, Region X. Seattle, Washington.
C.	Everts, Jim, Superfund Enforcement and Contracts Section, Toxic Substances
Control Branch. USEPA, Region X. Seattle, Washington.
D.	Findley, Charles, Deputy Director, Air and Waste Management Division USEPA,
Region X. Seattle, Washigton.
E.	Hurlburt, Eric, Fisheries Biologist, Washington Department of Fisheries.
Olympia, Washington.

-------
F.	Jamison, David, Director, Marine Research and Development, Department of
Natural Resources. Olympia, Washington.
G.	Kassebaum, Carl, Environmental Engineer, Water Resources Assessment Team.
Environmental Evaluation Branch. USEPA, Region X. Seattle, Washington.
H.	Kauzlovic, Phil, Regional Habitat Manager. Washington Department of
Fisheries. Olympia, Washington.
I.	Lagerloaf, Marcia, Ocean Programs Team, Water Permits and Compliance Branch.
USEPA, Region X. Seattle, Washington.
J. Malek, John, Environmental Planner, U.S. Army Corps of Engineers. Seattle,
Washington.
K. McNamee, Joan, Environmental Engineer. Superfund Managment Section. USEPA,
Region X. Seattle, Washington.
L. Merry, Ken, Chief, Office of Environmental Health Programs, Department of
Social and Health Services. Olympia, Washington.
M. Monn, Bob, Water Quality Planning and Managment Section Supervisor, Washington
Department of Ecology. Olympia, Washington.
N. Moore, Elbert, NPS Specialist, Water Planning Section. USEPA, Region X.
Seattle, Washington.
Q. O'Neal, Gary, Director, Environmental Sources Division. USEPA, Region V.
Seattle, Washington.
P. Nolan, James, Air Pollution Engineer. Puget Sound Air Pollution Control
Agency. Seattle, Washington.
Q. Petke, Dan, Environmental Engineer. 1PA. Redmond, Washington.
R. Phillips, Oceanographer, Environmental Resources Section. U.S. Army Corps
of Engineers. Seattle, Washington.
S. Robichaud, Robert, Acting Pretreatment Coordinator. Water Permits and
Compliance Branch. USEPA, Region X. Seattle, Washington.
T. Towle, James, Project Manager. U.S. Army Corps of Engineers.
Washington.
U. Underwood, John, Chief, Water Quality Branch. USEPA, Region X.
Washington.
V. White, Richard, Environmental Engineer, Air Program Development
Air Programs Branch. USEPA, Region X. Seattle, Washington.
W. Wilson, Thomas, Chief, Water Planning Section. USEPA, Region X.
Washington.
X. Wenman, Fred, Biologist, U.S. Army Corps of Engineers. Seattle, Washington.
Personal Communications September 26-31, 1983. Seattle and Olympia, Washington.
A.	Armstrong, John, Biologist, Ocean Programs Team, Water Permits and Compliance
Branch, Water Division, USEPA, Region X. Seattle, Washington.
B.	Arnold, Gail, Biologist, Environmental Resources Section, Planning Branch,
Engineering Division. U.S. Army Corps of Engineers, Seattle District.
Seattle, Washington.
C.	Baxter, Warren, Permit Section, Regulatory Functions Branch, Operations
Division. U.S. Army Corps of Engineers, Seattle District. Seattle,
Washington.
D.	Bodi, Laurie, Attorney, Office of General Counsel. National Marine Fisheries
Service, Seattle Branch. U.S. Department of Commerce. Seattle, Washington.
E.	Dahlgren, Curtis, Marine Habitat Manager, Environmental Planning and Permits
Branch, Habitat Management Division. Washington Department of Fisheries.
Olympia, Washington.
Seattle,
Seattle,
Section,
Seattle,

-------
F.	Fleskes, Carol, Sanitary Engineer, Water Quality Management and Planning
Section, Water Quality Management Division,- Office of Water Quality
Management. Washington Department of Ecology. Olympia, Washington.
G.	Groves, Al, Biologist, National Marine Fisheries Service, Seattle Branch.
U.S. Department of Commerce. Seattle, Washington.
H.	Hammersmith, Ed, Sanitary Engineer, Shorelands Management Section, Shorelands
Division, Office of Land and Water Resources. Washington Department of
Ecology. Olympia, Washington.
I.	Hulsizer, Elsie, Senior Land Use Specialist, Land Use Division, Seattle
Department of Conservation and Land Use. Seattle, Washington.
J. Kassebaum, Carl, Environmental Engineer, Water Resources Assessment Team,
Environmental Evaluation Branch, Water Division. USEPA, Region X. Seattle,
Washington.
K. Long, Edward, Marine Biologist, Ocean Assessment Division, National Oceanic
and Atmospheric Administration, U.S. Department of Commerce. Seattle,
Washington.
L. Martin, Stephen, Biologist, Environmental Resources Section, Planning Branch,
Engineering Division. U.S. Army Corps of Engineers, Seattle District.
Seattle, Washington.
M. Obert, William, Environmental Planner, Shorelands Planning Section, Shorelands
Division, Office of Land and Water Resources. Washington Department of
Ecology. Olympia, Washington.
N. Thomas, Joan, Division Supervisor, Water Quality Management Division, Office
of Water Quality Management. Washington Department of Ecology. Olympia,
Washington.
0. Thornton, Jim, Environmental Planner, Environmental Quality Section,
Operations Management Division, Office of Operations and Enforcement.
Washington Department of Ecology. Olympia, Washington.
P. Voerman, Gary, Life Scientist, Water Resources Assessment Team, Environmental
Evaluation Branch, Water Division. USEPA, Region X. Seattle, Washington.
Q. Weinmann, Fred, Biologist, Environmental Resources Section, Planning Branch,
Engineering Division. U.S. Army Corps of Engineers, Seattle District.
Seattle, Washington.
>7. U.S. COE, Seattle District, East, West and Duwamishi Waterways Navigation
Improvement Study. Final Feasibility Report and Final Environmental Impact
Statement. January 1983.

-------