v>
U.S. Environmental Protection Agency
EVALUATION OF THE RESPONSE TO THE MAJOR OIL SPILL AT
THE ASHLAND TERMINAL, FLOREFFE, PENNSYLVANIA
BY THE INCIDENT-SPECIFIC REGIONAL RESPONSE TEAM

-------
EVALUATION OF THE RESPONSE TO THE MAJOR OIL SPILL AT
THE ASHLAND TERMINAL, FLOREFFE, PA
BY THE INCIDENT-SPECIFIC REGIONAL RESPONSE TEAM

-------
EVALUATION OF THE RESPONSE TO THE MAJOR OIL SPILL AT
THE ASHLAND TERMINAL, FLOREFFE, PA
BY THE INCIDENT-SPECIFIC REGIONAL RESPONSE TEAM
TABLE OF CONTENTS
Page
Introduction	i
Executive Summary	ii
Section I: Description of the Incident	1
Section II: Description of the Response	3
Section III: Findings and Recommendations	10
Section IV: Conclusion	18
List of Appendices
Water User Experience
Transcript of the NRC Report of the
Ashland Oil Spill, Floreffe,
Allegheny County, PA
Incident-Specific Regional Response Team
River Monitoring Work Group
Glossary of Abbreviations
Assessment of Monitoring Elements
Appendix A:
Appendix B:
Appendix C:
Appendix D:
Appendix E:
Appendix F:

-------
INTRODUCTION

-------
INTRODUCTION
A four-million gallon steel storage tank collapsed at the
Ashland Oil Company terminal in Floreffe, Pennsylvania, Saturday
Evening, January 2, 1988, creating one of the largest inland oil
spills in the United States. A wave of 3.9 million gallons of
diesel fuel crashed over the tank's containment dike and surged
in all directions. Initial estimates were that over 1,000,000
gallons escaped into the Monongahela River through storm sewers
located on an adjacent property. These estimates were later
revised to approximately 750,000.
This report provides the Incident-Specific Regional Response
Team's (RRT's) evaluation of the response to the Ashland Oil
Spill. Five work groups were established to assess the response
and their draft submissions are the basis of this report. The
five work groups assessed the initial response, water supply,
river monitoring, river cleanup, and communications. This report
provides relevant background information pertaining to the
incident and the response, as well as the RRT's findings and
recommendations for improving future responses.
Organization of the Report
Section I provides background information relating to the
January 2 release, as well as the natural and technological
factors affecting the emergency response.
Section II provides a description of the initial on-site
response, river monitoring, and river cleanup activities.
Section III presents the RRT's findings regarding the
emergency response activities and provides specific
recommendations to improve the efficiency and effectiveness of
future responses.
Section IV outlines the RRT's overall conclusions regarding
the response to the Ashland Oil Spill.
i

-------
EXECUTIVE SUMMARY

-------
EXECUTIVE SUMMARY
Description of the Incident
A total of 3,881,841 gallons of No. 2 diesel fuel were
released from a collapsing oil storage tank at the Ashland Oil
Company terminal in Floreffe, Pennsylvania on Saturday, January
2, 1988 at 5:10 p.m. The catastrophic release created a wavelike
surge of oil that passed over the banks of the facility's
containment berms and into a nearby storm drain. Current
estimates are that approximately 750,000 gallons of the diesel
fuel entered the Monongahela River.
Several factors made response efforts difficult. First, due
to the force of the release, most of the oil entered the river
within the first two hours of the tank rupture, leaving little
time to obtain equipment and personnel to stop the flow. Second,
the rupture occurred after dark, preventing first responders from
conducting a thorough assessment of the extent of the spill.
This problem was aggravated by the disconnection of power and
communication lines at the site and the evacuation of 250 nearby
residents in response to a report of a gasoline leak from an
adjacent tank. Third, extremely cold air and water temperatures
affected all aspects of the response, including monitoring and
cleanup activities.
Description of the Response
Ashland Oil Company employees provided prompt notification
of the tank rupture and spill to the National Response Center and
to local emergency response agencies. Local authorities were the
first on-scene responders. Early response efforts by these
authorities and Ashland's cleanup contractor were directed toward
preventing the spilled diesel fuel from entering the Monongahela
River by blocking off storm drains and by creating temporary
containment dikes.
The U.S. Coast Guard (USCG) acted as the first federal
official on scene and was joined at daybreak by the U.S.
Environmental Protection Agency's (EPA's) On-Scene Coordinator
(OSC). The OSC advised Ashland that EPA would direct and monitor
all phases of the cleanup operation. Ashland agreed to EPA's
direct control and also agreed to assume full responsibility for
all cleanup costs incurred.
The Incident-Specific Regional Response Team (RRT) was
formally activated on Monday, January 4. Prior to that time,
however, many of the RRT member agencies were already actively
involved in the initial response. RRT members acted as conduits
of information to and from their respsective agencies and made
recommendations for appropriate response actions.
ii

-------
State agencies primarily directed their efforts toward river
water quality monitoring and concerns regarding the provision of
safe drinking water supplies. To those ends, three types of river
monitoring took place: Monitoring at water utility intakes to
protect water supplies, monitoring spill effects on fish and
wildlife, and monitoring of the river to define the spill mass and
movement.
The USCG coordinated and oversaw the recovery of oil in both
the Monongahela and Ohio Rivers. The river cleanup operations
spanned 38 miles and were severely hampered by near arctic weather
conditions. In addition, as the oil passed through the series of
locks and dams along the rivers, the oil became dispersed
throughout the water column limiting boom containment to the oil
remaining on the water's surface.
Summary of Findings and Recommendations
Coordination
During the initial eighteen (18) hours of the response,
local, state, and federal agencies worked independently to
minimize the dangers and damage resulting from the spill, and no
single agency assumed an overall coordinating role. The RRT found
that with one exception, this limited response coordination did
not concern the agencies at the time since each had numerous
individual functions to perform. After the initial 18 hours,
coordination improved, but was still hampered in part by the
widely separate areas where response activities needed to occur.
The RRT concluded that either a single, large command post or
better liaison among multiple response sites would have enhanced
response coordination. The RRT recommends in the future that
earlier coordination and an assignment of responsibilities by the
OSC occur.
The Region III Contingency Plan states that "the RRT shall be
activated automatically in the event of a major or potentially
major discharge or release", but the RRT was not activated until
Monday, January 4. The RRT concludes that it could have provided
valuable assistance to the responding agencies had the RRT been
involved in the first 24 hours following the spill.
The RRT recommends that the team be activated as soon as
possible after a large spill occurs, and that a decision should be
made as to whether or not it would be necessary for RRT members to
be brought together on site. The RRT further recommends the
designation of an "RRT Coordinator" to assist the OSC by
facilitating communications among responding agencies.
iii

-------
The RRT finds that in the initial days of the spill, the
coordination and communications of river monitoring data suffered
because no lead agency was assigned to oversee these activities.
The RRT recommends for future responses the early establish-
ment of a single coordinating agency to focus the coordination
and communication of monitoring data so that relevant data is
efficiently collected, and to ensure a standardization of
analysis.
Communications
Communications problems were encountered during the Ashland
Oil Spill due to insufficient communications equipment at the
command post to support the large number of responding agencies.
The RRT recommends immediate installation of an adequate number
of phone lines to support these agencies at command posts in
addition to the use of cellular phones.
The RRT further recommends that an efficient means of
communications between the command post and RRT members be
developed by the RRT Communications Work Group.
Resources
The lack of immediately available containment and monitoring
equipment hindered the response. Delays were caused by the need
to locate and transport essential equipment. The RRT recommends
the preparation of inventories of locally available equipment to
assist emergency responders in quickly locating necessary
equipment.
The Ashland Oil Spill could have been far more devastating
had public water supplies been contaminated or water shortages
more severe. The RRT recommends that emergency planning agencies
and water suppliers work toward improving the availability of
contingency water supplies.
iv

-------
SECTION I
DESCRIPTION OF THE INCIDENT

-------
SECTION I
DESCRIPTION OF THE INCIDENT
On Saturday, January 2, 1988 at approximately 5:10 p.m.,
3,881,841 gallons of No. 2 diesel fuel were released from a
collapsing oil storage tank at the Ashland Oil Company terminal
in Floreffe, Pennsylvania. The Ashland terminal is a small (35-
tank) oil and tar tank farm located between State Highway 837 and
the Duquesne Power and Light Company, approximately 200 yards
from the Monongahela River. The catastrophic release created a
wavelike surge of oil that passed over the banks of the
facility's containment berms and into a nearby storm drain.
Initial estimates were that 1,000,000 gallons of the diesel fuel
entered the Monongahela River via a storm sewer running beneath
the Duquesne property. These estimates were later revised to
approximately 750,000 gallons.
Most of the 750,000 gallons of oil that entered the river
did so within the first two hours following the rupture of the
tank. Even under the most perfect conditions, it would have been
difficult to obtain the personnel and equipment necessary to
block off the drains and the outfall to the river in such a short
time. Several factors generally outside the control of federal,
state and local personnel contributed to making conditions at the
site less than ideal for responding to a major oil spill.
The rupture of the storage tank occurred at dusk. Darkness
prevented a thorough assessment at that time of the extent of the
spill, and that in turn delayed initial response actions. In
response to reports of a gasoline leak, all electrical and
telecommunication lines were disconnected at the Ashland terminal
to diminish the threat of fire and explosion. Approximately 250
nearby residents were evacuated. The resulting confusion made
site access difficult and impeded the efforts of first responders
to effectively contain the spill.
The Monongahela River current was initially estimated to be
moving at 2 mph; however, the actual rate was 1.1 mph, and the
flow rate continued to decrease as temperatures fell in the days
that followed. Predictions of plume movement were difficult to
make due to the changing river flow rate. The spill occurred in
the Lock and Dam No. 3 pool at river mile 25. The plume quickly
reached Lock and Dam No. 3 which is a little over one mile
downstream at river mile 23.8. Passing over this dam and the
series of navigational locks and dams on the Monongahela and Ohio
Rivers, the oil was emulsified and mixed until it was dispersed
throughout the water column. Once the oil was emulsified, it
largely escaped containment by booms. Cleanup crews could find
few suitable locations for oil collection downstream from the
spill site, and river access was impossible at many points.
1

-------
The Pittsburgh area experienced extremely cold weather
during the first weeks of 1988. Very low air and water
temperatures affected all aspects of response, monitoring, and
cleanup activities. The frigid conditions on the river increased
the risk of hypothermia for cleanup crews which led to the
decision by the OSC to demobilize all personnel from the river on
the fourth day after the spill. For several days, the ice cover
on the Monongahela and Ohio Rivers was between 50 and 90 percent.
The ice, which contained a percentage of the oil, interfered with
the placement of booms and sorbent materials and complicated
estimations of the movement of the plume based on river velocity.
Cold temperatures may have stabilized the oil emulsion in the
river. The emulsion in turn, contributed to the difficulty of
oil recovery operations and increased the threat of contamination
to subsurface water utility intakes.
2

-------
SECTION II
DESCRIPTION OF THE RESPONSE

-------
SECTION II
DESCRIPTION OF THE RESPONSE
Notification of Government Agencies
Ashland employees provided prompt and thorough notification
of the tank rupture and spill to the National Response Center
(NRC) and to local emergency response agencies. In turn, the NRC
notified the U.S. Coast Guard (USCG) of the spill and at 1810
hours, the USCG notified U.S. EPA Region III. Initial evaluation
of the spill took place in darkness and as a result, early
reports of the spill greatly underestimated its magnitude.
Although all agencies received timely notification, important
information about the spill was not known as the agencies
prepared their initial response.
Initial On-site Response
Local authorities were the first on-scene responders and
immediately rerouted traffic away from the site and instituted
site safety measures. Local mutual aid agreements were exercised
and a temporary command post was established at the Floreffe Fire
Hall. Early efforts by local response agencies and Ashland's
cleanup contractor, O.H. Materials, Inc., were directed toward
preventing the spilled diesel fuel from entering the Monongahela
River by blocking off storm drains and by creating temporary
containment dikes. These efforts were hampered by darkness and
extreme cold. The response was further hampered because
communication and power lines at the Ashland terminal were shut
off as a precautionary measure at the time of the spill. Despite
the outstanding efforts of local responders, the plugging,
patching, booming, and building of dikes had minimal impact on
the flow of oil; there was simply too much moving too quickly.
The USCG acted as the first federal official on scene and
exercised control of river traffic and mobilized the National
Strike Force. After inspecting the site, the USCG provided
information to EPA. EPA advised the Coast Guard that the
position of Federal On-Scene Coordinator (OSC) would be assumed
by EPA and that the OSC would arrive on site at first light.
The EPA Region III Technical Assistance Team (TAT) was
immediately dispatched to the site.
Oversight of Ashland's Response Efforts
The USCG monitored Ashland's efforts throughout the initial
response phase and directed the river cleanup by providing advice
to Ashland. The Coast Guard made the initial determination that
Ashland's efforts were proper and thorough.
3

-------
At 0740 hours on January 3, 1988, the EPA OSC arrived on
site and delivered a verbal "Notice of Federal Interest to
Suspected Discharger" to Ashland officials. The OSC advised
Ashland that EPA would direct and monitor all phases of cleanup
operations. Ashland agreed to EPA's direct control and also
agreed to assume full responsibility for all cleanup costs
incurred.
The Incident-Specific Regional Response Team (RRT) was
formally activated Monday, January 4, 1988, although many of the
RRT member agencies were already actively involved in the initial
incident response. The following agencies participated in the
RRT activations during the incident:
U.S. Coast Guard, Second District, Fifth District, MSO
Pittsburgh, National Strike Force LANTAREA Strike Team
U.S. Environmental Protection Agency (Regions III, IV, V)
U.S. Army Corps of Engineers (Pittsburgh, Cincinnati,
Huntington, Louisville)
U.S. Department of Interior (Philadelphia, Chicago)
National Oceanic and Atmospheric Administration
(Rockville, Seattle)
Occupational Safety and Health Administration
Federal Emergency Management Agency
Pennsylvania Department of Environmental Resources
Pennsylvania Emergency Management Agency
West Virginia Department of Natural Resources
West Virginia Department of Health
Ohio Environmental Protection Agency
Ohio River Valley Water Sanitation Commission
Kentucky Department for Environmental Protection
The RRT was activated to provide advice and guidance to the
OSC. RRT members acted as conduits of information to and from
their respective agencies. During RRT teleconferences, the
political, programmatic, and statutory implications of the
actions of the responding agencies were discussed, and
recommendations for appropriate response actions were made.
4

-------
Delegation of Tasks
During the initial hours of the response, none of the
agencies on site assumed the role of "lead response agency."
Once on scene the following morning, the OSC assumed the lead
role. Specific tasks and responsibilities were assigned by the
OSC to the agency best qualified to perform them.
State authorities immediately directed their efforts toward
concerns over water quality, which by noon on January 3, 1988,
became a separate, significant response phase managed by State
and county authorities. In particular, the Pennsylvania Depart-
ment of Environmental Resources (PADER) and the Pennsylvania
Fish Commission (PFC) began assessing the impact on water
quality and downstream water intakes.
The USCG, with the recognition that Ashland and local
authorities were controlling the site response, focused
immediately on cleanup and recovery of oil in the river.
River Monitoring
Three types of monitoring took place during the event:
monitoring of the river to define the spill mass and track its
movements, monitoring the effects on fish and wildlife, and
monitoring at intakes to protect water supplies. Flow and
velocity forecasts by the National Weather Service were initially
utilized to predict progress of the oil plume. In addition, the
U.S. Army Corps of Engineers (USACOE) provided velocity
information on a daily basis.
Attempts at tracking the plume were initiated on January 4,
1988 and included the culmination of overflight observations and
taste and odor reports from treatment plant operators and lock
and dam workers. Flow and velocity data and weather forecasts
were obtained from appropriate agencies. On January 5, PADER and
the PFC began sampling on the Monongahela and Ohio Rivers at
three depths in the water column and sediment on the river banks.
Analyses performed were Oil and Grease (O&G) and Total Organic
Carbon (TOC). PADER, in cooperation with the Allegheny County
Health Department, also initiated sampling of surface and
groundwater intakes along the rivers in Pennsylvania, with
analyses for volatile organics, TOC, and fuel oil performed by
the PADER laboratory in Harrisburg.
A group at the Ashland command post consisting of represent-
atives of U.S. EPA, the National Oceanic and Atmospheric
Administration (NOAA), PADER, and the Ohio River Valley Water
Sanitation Commission (ORSANCO) set up a program of sampling
river water at the first eight water supply intakes downstream of
the spill site. The sampling was initially set up as three
samples per day at each intake, but had to be cut back to two per
5

-------
day due to logistical considerations. Analyses were first
performed at a local contract laboratory (NUS) until a field
laboratory could be set up by the cleanup contractor, O.H.
Materials, Inc. Analyses included volatile organics, base
neutrals, and No. 2 fuel oil.
On January 6, personnel from the U.S. EPA, West Virginia
Department of Natural Resources (WVDNR), and ORSANCO initiated an
effort to track the spill from tow boats. One boat equipped with
a fluorometer moved upstream from Wheeling, while a second boat
equipped with a TOC analyzer moved downstream from Wheeling.
After the first day, it became apparent that the fluorometer
provided useful results for characterizing the plume, while the
TOC analyzer did not. Thereafter, the effort continued utilizing
one tow boat and a fluorometer with personnel from Ohio EPA,
WVDNR, and ORSANCO. Samples were collected at the point where
the fluorometer indicated the leading edge and the peak
concentration of the spill and were shipped to the WVDNR's
Guthrie Laboratory for analysis of volatile organics, base
neutrals, and fuel oil. On January 6, 7 and 8, the USACOE,
Pittsburgh collected samples at several locations including the
New Cumberland, Montgomery, Emsworth, Elizabeth and Braddock
Dams.
Ohio EPA set up a monitoring system at eight sites on the
Ohio River and commenced sampling on January 7. Analyses
included TOC, O&G, and organics.
On January 13, personnel from the USACOE, Huntington
District took over the downstream tracking of the spill. They
continued to perform the tracking, utilizing their own boat and a
flow-through fluorometer, through January 23 when the spill left
the limits of their jurisdiction (Meldahl Dam, river mile 436) .
The effort was then taken over by the USACOE's Louisville
District, which followed the spill until February 2, at which
time the spill was no longer detectable by the boat-mounted
fluorometer.
From January 19 through 23, a tow boat was again employed to
assist in the tracking and to provide samples requested by down-
stream water users. Five-gallon samples were collected at the
indicated peak for use by the utilities performing treatability
studies.
On January 22, the spill reached Kentucky. Monitoring by
the Kentucky Division of Water consisted primarily of fluoro-
meters at water intakes. Fluorometers were successfully utilized
at Maysville and Louisville.
Fluorometers were moved downstream to provide monitoring at
water intakes in Evansville, Indiana and Cairo, Illinois. By
that time, the spill had dispersed to the point where results
were inconclusive. Monitoring at Cairo, just above the mouth of
the Ohio River, was concluded on February 12.
6

-------
In general, cold weather hampered the river monitoring
efforts. Poor navigation conditions forced the monitoring crews
to use slow moving tug boats which slowed the provision of
monitoring information to water utilities.
Monitoring Effects on Wildlife
Dozens of individuals, under the guidance and direction of
the Audubon Society and the Pennsylvania Game Commission, worked
for days following the spill retrieving and cleaning oil-soaked
waterfowl from along the rivers. Efforts to save waterfowl were
hampered by low temperatures and by ice on the rivers which kept
rescue workers on the shore. Although many birds were saved,
estimates of waterfowl mortality range from 2,000 to 4,000 ducks,
loons, cormorants, and Canada geese, among others.
Biologists from the WVDNR conducted shoreline counts along
120 miles of the Ohio River to determine the number of fish
killed. In the week following the spill, several censuses of
dead and stressed fish were taken in the dam pools along the
river.
WVDNR aquatic toxicologists designed oil-impact studies on
species of mussels by taking censuses and samples from well-
established mussel beds on the Ohio before and after the arrival
of the oil slug. In separate studies, mussels and catfish were
placed in cages in the river downstream from the spill and were
collected after the plume had passed. The organisms will be
analyzed to determine the adverse effects of the diesel fuel.
Effects on Water Supplies
Appendix A outlines by individual water supplier the impacts
and actions taken with respect to water supply facilities. In
general, however, the provision of information by emergency
response agencies enabled downstream water suppliers to implement
treatment procedures and increase storage volume before the spill
affected their intakes. Public confidence in the water purveyors
and in the government agencies responding to the spill was
maintained because the quality of the water supplied never
deteriorated.
Coordination of raw and finished water quality testing and
reporting was critical because of the need to use that
information in making decisions with respect to water plant
operations. Use of private laboratories for quick turnaround
time of sample results was vital for determining the effective-
ness of carbon treatment and for verifying the quality of
drinking water during the incident.
7

-------
Where needed, emergency water stations were set up quickly
and refill operations were well organized in spite of cold
temperatures which necessitated the staging of water tankers
indoors. Special plumbing was rapidly installed so that multiple
faucets were available at each station. Dairies and breweries
provided bottled water and were given guidelines for protection
of the quality of the bottled water.
The Commonwealth of Pennsylvania issued a Water Conservation
Order for three counties during the incident. This order and the
cooperation of the public allowed three of the four affected
water suppliers in Pennsylvania to avoid water loss to their
customers.
River Cleanup
It is now known that virtually all the oil entered the river
via a single route; a 24" drainage pipe on the adjacent Duquesne
Power Company property that discharged into the river at
Duquesne's cooling water discharge. Once this route was
identified, the fire department installed an underflow dam in
front of the drain opening to prevent the oil from flowing into
the river. However, due to delays caused by darkness, loss of
power and communications, an an evacuation of the area, the dam
was not installed until 2100 hours on January 2, 1988. By that
time, most of the oil had already reached the river. This first
containment was replaced by an inflatable plug that failed early
the next morning. At that time, an additional 50,000 gallons of
oil were released into the river.
The oil spill from the Ashland facility quickly reached the
first in a series of locks and dams along the Monongahela and
Ohio Rivers. As the oil passed through the locks and dams, it
apparently became emulsified and dispersed throughout the water
column. As a result, the containment booms were only able to
retain a percentage of oil that was not emulsified.
Traffic in the Monongahela River was prohibited for 58 hours
following the Ashland spill and was restricted for seven days,
enabling cleanup crews to move about freely in the river. Daily
evaluation of the restrictions on river traffic were made by the
Marine Safety Office (MSO) in Pittsburgh.
Efforts to contain and recover oil at this enormous spill
included the utilization of over 150 people, eleven vacuum
trucks, three cranes, and 20,000 feet of river boom. The very
extreme weather conditions prevented extensive use of recovery
methods such as the application of sorbent materials because ice
cover prevented the sorbent materials from contacting the oil.
In addition, the ice cover and high risk of injury for the work
crews prevented the placing of booms in some otherwise strategic
locations. Recovery efforts were centered around diversion and
removal of the oil from natural or man-made pockets.
8

-------
River cleanup operations spanned 38 river miles, and were
conducted at times in extremely cold conditions. The USCG
provided personnel from both MSO Pittsburgh and National Strike
Force LANTAREA Strike Team to oversee cleanup operations by
contractors hired by Ashland. Cleanup monitoring consisted of
visits to the cleanup sites by survey teams, who reported cleanup
progress to the On-Scene Coordinator at the command post.
Providers of alternative oil recovery technology from all
over the world contacted the EPA during the emergency. The
following alternative technologies were proposed: biodegra-
dation, viscoelastomers, degreasers, demulsifiers, solvent
extractors, gelatinizing agents, water purifiers, boat-mounted
oil/water separators, robots, bird feathers, and placement of
pantyhose in the spillway.
All individuals and companies who contacted EPA concerning
the use of their products at the spill were referred to the
Ashland Oil Company.
At the request of Ashland, a field test of the effectiveness
of a viscoelastomeric product was performed on the Ohio River
during the cleanup. The product neither promoted nor inhibited
the rate of oil recovery from the river.
9

-------
SECTION III
FINDINGS AND RECOMMENDATIONS

-------
SECTION III
FINDINGS AND RECOMMENDATIONS
The findings and recommendations of the RRT can be generally
grouped into three major topics which are critical elements in
any emergency response operation: Coordination, Communications
and Resources.
COORDINATION
The initial 18 hours of response to the emergency can be
characterized as a loosely organized, but relatively effective
attempt, to minimize the dangers and damage from the spill. As
local, county, state, and federal agencies responded, each
exercised its own responsibilities independently as liaison was
established at the scene. At no time in the initial hours did
any agency deem it necessary to "take charge" of the entire
response effort and only the City of Pittsburgh HAZMAT team
expressed some concern about being able to identify the
individual in charge. By 8:00 a.m. on January 3, 1988, all
responding agencies were on scene and in liaison with the
others. A response organization then developed which, while not
without some temporary shortcomings, served as an effective
structure throughout the response period. This response organiza-
tion included the assignment by the OSC of specific areas of
responsibility, such as site cleanup, water monitoring, oil
recovery, and assistance to water suppliers, to appropriate
agencies.
Command Post
During the Ashland response, there appeared to be a constant
tradeoff between the need to have all response personnel in a
single command center for better coordination, and the need to
limit the number of people present in the command post to
minimize the confusion. A single, very large, command post would
have enhanced response effectiveness; however, no site for such a
center could be located in the first twelve hours, and the
locations of the multiple response activities (spill site
cleanup, river oil recovery, water supply protection) were widely
separated. In retrospect, perhaps an effective future arrange-
ment would be to establish a central command post staffed by
personnel responsible for each aspect of the response and separ-
rate operations centers for each aspect.
10

-------
Regional Response Team
The Region III Regional Contingency Plan states: "The RRT
shall be activated automatically in the event of a major or
potential major discharge or release," but the RRT was not
activated until Monday, January 4, 1988. The RRT could have
provided assistance to the responding agencies sooner, had it
become involved in the response during the first 24 hours
following the spill. It is recommended that the RRT become
active as soon as possible after future large spills occur. All
standing RRT members should be informed of the activation. At
the time of RRT activation, a decision should be made about
whether or not the effectiveness of the spill response will be
increased should RRT members be brought together on site.
The RRT should consider designating an "RRT Coordinator" to
facilitate communications among responding agencies, including
RRT members. During an emergency, such an individual could be in
charge of reporting back to the OSC all of the developments at
Emergency Operations Centers (EOCs), other than the command post,
such as those established during emergencies by the Red Cross and
the FEMA.
The Ashland response was profoundly affected by Ashland Oil
Company's decision to assume financial responsibility for the
cleanup. Considering the pivotal position of Ashland officials
for making decisions which affected all aspects of the response,
it may have been useful to include an Ashland representative in
RRT teleconferences. Their representation could have provided
the RRT directly with any factual details regarding their
activities and their ability to comply with RRT recommendations
to the OSC. This representative would not, however, have had any
authority to speak for the RRT.
Coordination of Water Monitoring Efforts
The coordination and communication of monitoring efforts in
the initial days suffered because no lead agency was assigned.
Following the initial emergency response lead by the USCG,
ORSANCO accepted the lead; ORSANCO sent its field operations
coordinator to the Wheeling interim command center and its
Cincinnati office served as the data clearinghouse. Because
there was no legal basis for ORSANCO's lead role, it was possible
only by an informal agreement of the agencies involved.
In the future, the early establishment of a single water
monitoring data coordinating agency can serve to improve the
focus on communications so that efficiency and data relevance are
optimized. Central command, financial and technical responsibi-
lity, and a source of up-to-date information can be established
so that field monitoring may be addressed at the onset of an
emergency. Furthermore, the lead agency can take steps to
determine the availability of resources and establish
standardization of analysis among the various agencies.
11

-------
Standardization of Sampling and Analytical Data
While the degree of cooperation among the agencies was high,
they operated independently so that there was a lack of
standardization of analysis. Naturally, it would be optimal to
use identical measures and procedures among agencies for
comparison of analyses. The fluorometers, for example, provide
an illustration of potential problems. Tow boat and stationary
fluorometers employed discrete sample analysis and were
calibrated with a standard solution of naphthalene. (There is
some question about standard solution degradation during the
period of analysis.) The U.S. Corps of Engineers' fluorometer
employed a flow-through sample analysis and was not calibrated
with a standard solution of naphthalene. Because of these
inconsistencies, there was some difficulty in combining
measurements to gain a complete history of the plume.
As another example, some laboratories reported a nonspecific
"fuel oil" concentration which could be quantified in at least
two ways. One method measured a single constituent and estimates
total concentration based upon fractional composition; another
sums the concentrations of many similar components in a given
range of the GC spectrum.
The measurement techniques to be used for specific situa-
tions should be standardized. Analytical methods for determining
concentrations of contaminants should also be standardized. The
Organics Detection System (ODS) gas chromatographs were
invaluable in providing on-site analysis with minimal sample
turnaround time. GC/MS was used for verification of raw and
finished water quality and was required by some regulatory
agencies before approval was given to water plants to return to
operation. Consideration should be given to standardization of
portable GCs with subsequent GC/MS verification for incidents of
this type in the future.
COMMUNICATIONS
Communications during the initial stages of the incident
were very difficult, and the fact that the incident required a
shutdown of power and communications on site for a period
contributed to this problem. Regardless, the sheer number of
agencies involved in an incident of this magnitude would strain
any communications system.
eoiMnnn ications Resources
During the Ashland Oil Spill, there were some problems
encountered in attempting to contact RRT members during off-duty
hours. A list of 24-hour phone numbers for contacting RRT
members should be regularly updated and made available to all RRT
12

-------
members at all times. In addition, the 24-hour phone numbers for
various agencies and the numbers to newly installed or rented
portable phones need to be gathered and aggressively disseminated
to all responding groups.
Responders need large quantities of communications hard-
ware. Immediate installation of a large number of phone lines to
the command post is essential for adequate communications during
a response of this size. However, cellular phones are a
necessity for rapid, efficient response. Temporary rental of
these phones is possible through some car rental companies.
Mobile phones should be provided to field work crews so that they
can make regular updates to the command post. Cellular phone use
can become a problem if system capacity is exceeded due to
the tremendous number of phones employed in a major disaster.
Conventional phone service should be installed on scene as soon
as possible.
The numerous difficulties with both the EPA and USCG-NRC
teleconference systems were apparent to all who participated in
the RRT teleconferences. It is recommended that for future
activations, the RRT should, where time permits, utilize a
private telecommunications system (such as AT&T) until the
federal teleconference network can be improved.
EPA's and NOAA's electronic mail systems can be efficient
mechanisms for communication between RRT members. It is suggest-
ed that each RRT member be assigned an E-mail box under each
system and that for EPA-lead responses an RRT E-mail distribution
system be established at the Regional Response Center in
Philadelphia. Through such a distribution system, POLREPs and
Special Bulletins can be promptly delivered to all RRT members.
This would improve the quality of RRT teleconferences, as all
members would be in possession of the same information. The
Communications Work Group for the Standing RRT should attempt to
standardize the RRT E-Mail distribution system.
River monitoring data were distributed using ORSANCO's
electronic bulletin board and direct telephone. This system,
which had been established prior to the spill with water
utilities along the river, was widely used and worked well. Some
parties lacked the appropriate hardware (computer and modem) to
use the bulletin board and in some cases did not have knowledge
of the service. Procedures could be developed to utilize
ORSANCO's electronic bulletin board more effectively, or
alternately for RRT use, the data could be distributed via EPA or
NOAA E-Mail. Specific times of day should be established for
updating the bulletin board and two-way electronic communications
should be implemented. Water suppliers could then provide daily
updates on their operations via computer bulletins. A water user
telephone hotline could be used in a similar manner for plants
without computer equipment.
13

-------
Providing Information to the Public
At one point in the response, prior to receiving official
notice from the state, a local government agency suggested that
the need for water conservation was lessening. Criteria and
authority for lifting Water Conservation Orders should be made
clear to local governments and water purveyors by the party
establishing the order so there is basic agreement beforehand on
when conservation can be discontinued. Partial lifting of an
area-wide need for conservation could confuse the public and
result in prolonged water shortage in some areas.
For the water suppliers, public relations activities were a
high priority, essential for maintaining customer confidence in
their drinking water quality. While this was generally achieved
at Ashland, it is worth reiterating that information should be
given in future emergencies to the media consistently and on a
regular basis, preferably through one spokesperson at the
facility. It is also suggested that copies of press releases be
sent to other water users along the river.
Very special attention must be paid to ensure that the media
continually notify the public if the problem is one of quantity
and not of contamination. Water suppliers should be aware that
the use of interconnects, changes in water flow patterns, and
varying pressures may lead to taste and odor problems that the
public could misinterpret as contamination.
Communications Between Command Post and Water Suppliers
To the extent practicable, provisions were made so that
information on the extent of contamination of raw water sources
was provided to all parties involved with water supply decisions.
Furthermore, modeling was used to assist in determining when
contamination would reach a water intake and how long surface
intakes would be shut down. Such information was, of course,
vital for deciding whether or not sufficient water storage
existed and which areas required emergency supplies first.
More guidance is needed from state drinking water agencies
in developing treatment schemes. The best information was
generated with jar tests on contaminated river water samples, but
it was difficult for downstream water users to obtain these
samples. Consideration should be given to developing a means for
delivering such samples to downstream suppliers early in the
response.
More timely health effects data on the contamination is
needed along with assistance in interpreting its significance.
Water utilities were often questioned by the public and the media
about the safety of their drinking water and the toxicity of fuel
oil components. In the future, ATSDR, along with state health
departments, could be better utilized for this purpose on site.
14

-------
Coordination and Communication of River Monitoring Data
A greater understanding of river flow is necessary for
improved time-of-arrival and contaminant concentration estimates.
Currently, for the Ohio River Basin, these estimates can be based
only on river velocity measurements at discrete locations as
provided by the River Forecast Center of the National Weather
Service (NWS).
In the case where the contaminant is mixed throughout the
water column, as was the case with the Ashland spill, river
velocity equals plume velocity. As NWS river velocity data are
provided daily throughout the year for points along the Ohio
River and on major tributaries, it appears an ideal source of
timely and reliable information. Nevertheless, because the data
are provided at wide distance intervals (e.g., 62 miles between
Moundsville and Willow Island) and river velocities may change
significantly in a day, considerable uncertainty exists in time-
of-arrival estimates. The velocity gradient within pools is an
especially important factor at low flow, when the river may take
several days to travel between dams. These shortcomings were
apparent in the discrepancies noted between predicted and actual
times of arrival.
Downstream users were kept informed of the most recent
measured concentrations of contaminant and its expected treat-
ability. As discussed earlier, this information was initially
slow in coming because of difficulty in setting up GC analytical
capability. In the future, improvements should be sought in
laboratory setup procedures and by use of established water
quality models.
A final difficulty in the area of coordination and
communication was the selection of data that would be most useful
to downstream water utilities. The data first posted on the
electronic bulletin board were concentrations of organic
compounds, which were later supplemented by No. 2 fuel oil
results. Downstream utilities remarked that this data was not
meaningful to them in assessing treatability. The delivery of 5-
gallon samples that could be used for treatability tests was much
more useful to the water supply plants.
In the end, monitoring efforts have been successful in that
there was no (known) public health impact and no damage to water
treatment systems due to untimely notice.
RESOURCES
A lack of immediately available resources such as contain-
ment and monitoring equipment hindered the response to the
Ashland oil spill. Federal response equipment is housed in
widely separated locations and so was not easily accessible for
use. No current inventories of equipment and resources
15

-------
controlled by governmental or industrial entities existed.
Delays were caused by the need to locate and transport needed
equipment and by the necessity of diverting valuable personnel
from actual response and cleanup efforts to do so.
As an example, considerable difficulty was encountered in
obtaining fluorometers for spill monitoring. This tool was
identified within the first days of the emergency as a means of
tracking the spill, and by chance one was found with the proper
light wavelength filters for oil-in-water analysis.
Unfortunately, when it was decided to use the instruments in
multiple locations (mobile and stationary), no information was
available on other instrument suppliers. Eventually, several
more fluorometers were located with the aid of the manufacturer's
sales records, but by then several days' worth of data had not
been obtained.
A warehouse of available containment and monitoring
equipment in the Pittsburgh area would have been ideal. However,
the warehousing of equipment for emergency responses is not
mandated by any local, state, or federal agency; nor is it cost-
effective. Inventories of locally available equipment would have
assisted emergency responders in quickly locating essential
equipment. Such inventories could be developed through a
cooperative arrangement between local industries and government.
For the most part, in the initial days the regulatory
agencies involved in the response were not able to provide
the turnaround time for water analyses needed to make the
decisions facing them. This problem may have been due to the
heavy workloads or to the physical separation between the river
and the laboratory. In any case, it is not likely that the
analytical data could have been obtained any faster. Later, with
the availability of the mobile laboratory, this problem was
appreciably reduced in magnitude. Delays, of course, were
especially bothersome for water utilities in need of qualitative
and quantitative data to assess treatability. The ability to
provide this information either through private laboratory
contracts or through mobile analytical capabilities is very
important to the efficiency of the response.
Regulatory agencies should consider maintaining in state or
local contingency plans a list of local laboratories certified to
perform necessary testing in an emergency. Sampling and analysis
protocols should be pre-approved by the appropriate regulatory
agencies. Time estimates should be obtained from local
laboratories with respect to sample processing as a part of these
plans. Whenever possible, a contract with the local laboratory
should be drawn up that gives emergency analyses priority over
their routine work. Operating hours and number of samples that
can be handled by the local laboratory should be maintained in
this information package. Finally, the development of a mobile
laboratory capability by the responding agencies is significant
in ensuring an efficient response.
16

-------
This particular incident could have been far more
devastating had public water supplies been contaminated or water
shortages more severe. It is essential that emergency planning
agencies and water suppliers plan for the availability of
contingency water and equipment.
Emergency planning agencies should maintain a current list
of available bulk water haulers, facilities with tankers that can
be used in refill operations (i.e., fire companies and dairies),
and sources of plumbing expertise for distribution station
hookups.
Each water supplier should maintain a list of service and
equipment companies that can provide replacement pumps,
chlorination equipment, or chemical feed equipment in the event
of an emergency.
17

-------
SECTION IV
CONCLUSION

-------
SECTION IV
CONCLUSION
In particular, the RRT notes that the willing cooperation
between all regional elements was the outstandng factor that
resulted in the successful protection of the public health and
the environment during the Ashland Oil Spill. All responding
agencies, groups, and individuals are to be commended for their
performance throughout the emergency. Despite the magnitude of
the spill, the rapid entry of oil into the river, and adverse
weather conditions, all public water suppliers were protected.
The RRT concludes that the overall response to the Ashland
Oil Spill was effective. Despite the magnitude and instantaneous
nature of the oil release and the various factors, including
weather conditions, that hampered containment and cleanup
efforts, the response achieved the following:
a)	The initial notification of the spill was timely;
b)	River monitoring efforts were successful in that
drinking water intakes were secured prior to any
contamination of water supply systems;
c)	Ashland Oil Company worked cooperatively under the
direction of the U.S. EPA and agreed to take full
responsibility for funding cleanup activities; and
d)	The spill site was safely secured with no injuries to
workers, emergency response personnel, or residents.
Although the response to the Ashland Oil Spill was
effective, the RRT's final conclusion is that implementation of
the recommendations presented herein will improve the efficiency
and effectiveness of future responses.
18

-------
APPENDIX A
WATER USER EXPERIENCE

-------
APPENDIX A
WATER USER EXPERIENCE
Water supply plants downstream from the Ashland terminal
were promptly notified of the January 2, 1988 spill; however, the
presence of oil throughout the water column and the corresponding
impact on water supplies was not recognized until the following
morning.
This Appendix summarizes the experiences of the major water
supply facilities that were affected by the Ashland Oil Spill.
West Penn Water Company (Becks Run^. PA fMononaahela River mile 4.5^
West Penn Water (WPW) was notified by the Allegheny County
Health Department (ACHD) about the spill at approximately 7:00
p.m., January 2. Little information was available on the spill
location, size, volume (estimates ranged from 30,000 to 3 million
gallons), or travel time to intake. The Hays Mine plant intake
was closed early January 3, and testing began immediately using
the ORSANCO-ODS gas chromatograph. Additional samples were sent
to a local lab for GC/MS verification. Samples were also taken
by EPA, PADER, and ACHD. Attempts were made to determine the
chemical composition of the fuel oil. The plant considered
blocking off the two upper water intakes and operating with the
lower intakes; however, oil was observed at depths greater than
15 feet.
On Monday, January 4, WPW pilot tested a carbon feed process
that proved successful in removing the oil. This process was
used by four of the five Pennsylvania water companies that used
the contaminated portions of the river as a raw water source.
The fifth water company, Sewickley Borough, switched over to
wells. On January 6, treatment and analysis schedules were
established and the Hays Mine plant started operating at 25
percent capacity.
Excellent public relations efforts helped to maintain public
confidence throughout the water emergency.
City of Pittsburgh Water Authority. PA (Allegheny River mile 7.41
The City of Pittsburgh draws its water from the Allegheny
River, which was uncontaminated by the spill. The excess
capacity of the Pittsburgh system provided 15 to 20 million
gallons per day (mgd) to West Penn and West View Water Companies.

-------
West View Water Authority. PA (Ohio River mile 4.5)
West View Water Authority was notified of the spill the
evening of January 2, and immediately implemented their emergency
contingency plan. This plan included increasing carbon feed
capacity, topping off reservoirs and tanks in the system,
activating wellfields, and establishing water line connections
with the City of Pittsburgh. Use of the developed wells was
delayed for a short time pending laboratory evaluation of the
quality of the raw water.
Regulatory agencies approved operation on January 10, at
which time the plant started to blend 25 percent river water with
well water. The primary factors that enabled West View to
provide water to its customers were the use of well water, the
connections with the City of Pittsburgh's system, and the
Pennsylvania Emergency Management Council's conservation order.
Robinson Township Authority. PA (Ohio River mile 8.6)
Robinson Township was the only water company that had
customers without water during the incident. Approximately
17,000 customers were without water for up to 48 hours. Two
thousand (2,000) customers were without water for up to 5 days,
and 200 customers were without water for an entire week.
The primary activity of the Authority during the incident
was the development of interconnections with other water supply
plants. The plant was able to open its river intakes 8 days
after the spill, on January 10, following conversion from a
potassium permanganate feed system to a carbon feed system.
Midland Water Authority. PA (Ohio River mile 36.2)
Midland Water Authority was advised on January 3 at
approximately 7:00 p.m. that the oil would reach the plant in 24
hours, and were advised to build reserves and cut consumption.
The river intake was shut down at 6:00 p.m. on January 4, with 4
million gallons of water in reserve. No interconnections with
other water supply plants were possible. A local industry, J&L
Products, which normally uses 2 MGD, was ordered by PADER to cut
consumption to a minimum. On January 7, divers completed the
installation of oil filter blanket material around the intakes,
and plant startup procedures began using 600-pound/million
gallons powdered activated charcoal for water treatment. Results
of tests of the finished water were acceptable and the plant went
back on line with the modified treatment process at 2:00 p.m. on
January 7, 1988.

-------
East Liverpool Water Treatment Plant. OH (Ohio River mile 41)
East Liverpool water treatment plant shut its intakes at
0300 hours on January 5, 1988 even though the plant had not yet
been affected by the spill. Officials of the plant determined
that they could not afford the risk of contaminating the
facility. In the interim, reserves and water conservation were
relied upon until river water treatment could commence. A creek
outflow aided in minimizing the spill's effects by diverting oil
from collecting near the facility's intake. By 1200 hours on
January 7, East Liverpool was back on line treating water with
activated carbon. Ashland's mobile laboratory was utilized to
test water samples on a 24-hour basis to ensure water quality.
Toronto Water Treatment Plant. OH (Ohio River mile 60)
At 2300 hours on January 5, 1988, Toronto, Ohio closed its
intakes. A large reservoir lessened the severity of the
situation. The reservoir, coupled with water conservation
efforts, provided sufficient water supplies until the plant
reopened its intakes and began treating river water at 2230 hours
on January 9, 1988.
Steubenville Water Treatment Plant. OH (Ohio River mile 65)
At the time of the spill, Steubenville's storage capacity
was at its fullest enabling an adequate supply of water to be
provided. Facility officials monitored the quality of water at
15 to 20-minute intervals. When odor became apparent on January
6, 1988, the water intake was closed for a period of 10 to 11
hours. After the contamination had passed, the intake was
reopened at 2225 hours.
Wheeling Water Treatment Plant. WV (Ohio River mile 86.8)
Useful information on treatment methods was developed by
water utilities upstream. The plant used a number of tests to
monitor for oil in water, such as the Hanby Test, fluorometric
analysis, threshhold odor, and gas chromatography. The GC was
used to confirm the presence or absence of low-level organics in
raw and finished water. Treatment schemes were evaluated using
jars of river water spiked with oil. Reliable concentration and
health effects data from upstream monitoring were not readily
available during the first week following the spill.
Alternate water sources were obtained from the communities
of Martins Ferry and Bridgeport and water barges brought in by
Ashland Oil. These barges were filled with water from Wheeling
Creek, a tributary of the Ohio River downstream of the Wheeling
water treatment plant. The plant went off Ohio River water the
evening of January 8 and reopened by blending with barge water on
January 10. Prior to reopening, an absorbent filter blanket was
placed over the intakes by divers.

-------
American Electric Power. WV (Ohio River mile 76.5. 111.1. lii.su
Power plants utilizing the river for cooling water are
vulnerable to high levels of oil. Since the period immediately
after the spill saw near record demands for electricity due to
heating needs, the threat of disruption of any of the power
plants was a grave concern. The fact that there was no disrup-
tion is noteworthy; however, plans for water treatment, if it
became necessary, were in place.
The Cardinal Plant, at mile 76.5, was the only plant that
observed oil at the 20 ppm level. A low dose of detergent was
added to the water there.
Sistersville Water Works. WV (Ohio River mile 1371
There was much concern regarding potential difficulties in
providing adequate water supplies at Sistersville because there
were no alternate supplies. During the crisis, Ashland provided
barged water to Sistersville while the plant's intakes were
closed from January 13 to January 21, 1988. USCG assistance was
not required. Residents also assisted by adhering to water
conservation requests.
E.I. DuPont. Parkersbura. WV (Ohio River mile 1901
The oil spill had no immediate impact on plant operations.
Huntington Water Treatment Plant. WV (Ohio River mile 3061
Huntington was hampered by a water hysteria in fear of a
water shortage prior to the arrival of the spill to the area.
Diesel pumps were installed in a nearby, unaffected stream as an
alternative water supply in anticipation of potential river
contamination. Intakes were closed on January 22 and water from
the Guyandotte and Ohio Rivers was blended for treatment until
100% Ohio River water treatment resumed on January 25, 1988.
Ashland Water Treatment Plant. KY (Ohio River mile 319.75)
Ashland, Kentucky shut its intakes at 0200 hours on January
22 and reopened them and began treating river water at 1200 hours
the following day. In the interim, reserves were utilized.
Mavsville Utility Commission. KY (Ohio River mile 408.5)
Barged water was provided to Maysville by Ashland Oil Company
during the period from 0715 hours on January 23 until 1630 hours
January 24, 1988 while the intakes were closed.

-------
Cincinnati Water Works. OH (Ohio River mile 462.8)
The distance of Cincinnati from the spill site allowed more
time for implementation of contingency plans. Information about
the spill's concentration as it moved downriver was limited and
was not helpful in predicting treatment dosages of activated
carbon. Plant personnel traveled to Wheeling and Huntington to
collect samples of the oil for jar test analyses. Fluorometers
were used for analysis of samples and provided better estimates
of the oil concentration. GC/FID was the most sensitive tool
used for organics detection; however, the fluorometer was easier
to operate and provided a faster turnaround time on test results.
Threshhold odor was not an effective test at the low oil
contaminant levels observed at the Cincinnati Water Works.
The plant remained off the river water for 86 hours and
resumed operation with carbon treatment until no trace of oil
contamination was observed in the river.
Kenton County Water District No. 1. KY (Ohio River mile 463)
On January 21, the Kentucky Department of Natural Resources
held a meeting with water utility personnel and state emergency
teams to discuss response plans when the spill reached the
Kentucky border. Information on the spill's position and profile
was presented, monitoring procedures were established, and a
communications network set up.
The Kenton County plant was off the Ohio River for about 72
hours and no serious problems were encountered. Since 2 sources
were available, either the Ohio and the Licking Rivers, the plant
minimized the amount of water treated with activated carbon.
Louisville Water Company. KY (Ohio River mile 600.6)
The Louisville Water Company (LWC) found the upstream water
user information very helpful and relied on ORSANCO to provide
updates on spill movement and time of arrival estimates. As the
spill diluted and spread downriver, it became apparent that LWC
would be faced with low levels of oil contamination over a long
period of time. Therefore, the company focused on the develop-
ment of treatment strategies and on keeping the public informed
about the steps taken.
Threshhold odor, fluorometry, and gas chromatography were
among the tests used to monitor the oil contamination. Odor
tests were conducted using water spiked with No. 2 fuel oil.
Five (5) ppb appeared to be the minimum detection level for the
odor test. Various treatment schemes were evaluated with jar
tests using oil concentrations of 100 ppm to 10 ppb.

-------
The first oil contamination was observed in the raw water at
noon on January 27 and oil reached a maximum level of 67 ppb on
January 29. Activated carbon was added (between 200 and 400-
pound/million gallons) during this period and was gradually
decreased as the contamination dropped below 1 ppb 4 days later.
Evansville Water Works. IN (Ohio River mile 791.5)
Treatment information and concentration data obtained from
upstream water users was sufficient for contingency planning at
Evansville. River conditions changed drastically with heavy
rainfall the week of February 1. This reduced the time-of-
arrival estimates by 2 weeks. The spill's leading edge was no
longer distinct by the time the spill arrived and fluorometer
peak readings were inconsistent.
Fluorometry and gas chromatography were used to monitor raw
and finished water. The passage of the oil took approximately 20
hours, with a 10 ppb oil concentration at the peak. Carbon
treatment was applied for 5 days. Media coverage and public
communication required a substantial amount of time throughout
the month of January.
Paducah Water Works. KY (Ohio River mile 935.5)
Since the spill had diluted beyond detection by the time it
reached Paducah, no additional treatment measures were taken at
the plant. Media coverage, however, was intense and public
relations activities consumed a great deal of time. Monitoring
at water plant intakes had been planned by Kentucky as long as
the oil contamination was detectable. Paducah was not informed
when oil monitoring was discontinued by the state.

-------
APPENDIX B
TRANSCRIPT OF THE NRC REPORT OF THE ASHLAND OIL SPILL
FLOREFFE, ALLEGHENY COUNTY, PA

-------
TRANSCRIPT OF NATIONAL RESPONSE CENTER TAPE
REPORT OF THE ASHLAND MAJOR OIL SPILL
FLOREFFE, ALLEGHENY COUNTY, PENNSYLVANIA
It should be noted prior to reading this text that during the course of this
report, date and time were not given. It is known that the date of the
initial spill report was January 2, 1988; however, the exact time of these
events is not known.
Call #1 • NRC Incoming
NRC:	National Response Center.
Caller: Yes, sir. This is John Gajdosik at Floreffe, Pennsylvania. I have
an emergency. 1 have a diesel fuel tank that has collapsed.
NRC:	All right, sir, you know that as far as an emergency situation, all
I can do is take a report in a timely manner and call the federal
on-scene coordinator.
Caller: Okay, well, I'm going to be calling the Coast Guard, in a second.
You are the National Response Center, so 1 wanted to notify you.
NRC:	Well, let me get a report form started. Okay?
Caller: Okay.
NRC:	I've got a series of questions to ask you. Pause. Okay, your name
again, sir, is what?
Caller: John, that's G-a-j-d-o-s-i-k. Look, I'm going to have to go shut
off some . . . I'm going to have to go shut off some electricity.
NRC:	Let me, let me have your phone number right quick.
Caller:	Okay. That's area code 412, 462-5111.
NRC:	And you're in what city?
Caller:	Floreffe, Pennsylvania. That's south of Pittsburgh.
NRC:	Uhat county?
Caller:	A11egheny.
NRC:	And the location where you're at?
Caller:	Uh. You mean the, where do you mean where am I at?
NRC:	Where the tank's at.
Caller:	Uh. It's inside the terminal at Ashland Oil, Floreffe.

-------
NRC T rartscr i pt
Page 2
NRC:	Ashland Oil?
Caller:	Ashland Oil Company.
NRC:	And the street is . . .
Caller:	State Street, on Route 837.
NRC:	Okay, sir.
Caller:	Okay?
NRC:	All right.
Caller:	All right, bye.
NRC:	Bye.
Call #2 - NRC Outgoing
Answer: Hello.
NRC:	Hello. This is Petty Officer Mackey at the National Response
Center.
Answer: Yeah.
NRC:	I got a real sketchy report from--are you familiar with Ashland Oil
on State Street, Route 837 in, he called it Floral, PA? He said it
was just south of Pittsburgh?
Answer: Floreffe.
NRC:	Floreffe.
Answer: I know where it's at.
NRC:	Okay. He was out of breath when he called me, so all I got was that
and his phone number. He said he had a diesel tank that collapsed.
And he had to call the Coast Guard.
Answer: He had a diesel tank?
NRC:	A diesel tank that collapsed. And he told me he couldn't
document any more information, that he had to go close some
valves, so he was, um
Answer:
All right, what's his phone number there.

-------
NRC Transcript
Page 3
NRC:	Area code 412, 462-5111. And I'm going to give this NRC Report #3 2.
Answer:	Number 32?
NRC:	Uh-huh. His name was Gados i k, G-a-d-o-s-i-k.
Answer:	That's all right, I can get it.
NRC:	Okay, and I hope you'll call me back and I'll finish my report.
Answer:	I'll give you a call back.
NRC:	Okay.
Answer:	That'll make it easy.
NRC:	That's in Pittsburgh's area? I got . . .
Answer:	Yeah, it's mile, um--oh--25 on the Monongahela River.
NRC:	Okay.
Answer:	Give or take.
NRC:	Well, it sounds like you got a pretty . . .
Answer:	Big one
NRC :	Big one goi n' on.
Answer:	Did he say any of it was getting in the water, or what?
NRC:	Ah, he never mentioned that. He said that he was wanting to call
the Coast Guard. He said he wanted to notify the National Response
Center and then he wanted the Coast Guard to be notified right away.
So . . .
Answer: Evidently it was. Tank collapse. He didn't say if it was a.tank
barge or if it was . . .
NRC:	Uh-uh. He said a tank, so I think it's a storage tank. They have
any tank--a tank farm there?
Answer: Yeah.
NRC:	That's what I got the feeling that it is.
Answer:	They got a small tank farm there. Okay. Appreciate it.
NRC:	All right. Bye.
Answer:	Bye.

-------
NRC T ranscri pt
Page 4
Call #3 - NRC Incoming
NRC:	National Response Center.
Caller:	Yes. I'd like to report a spill, please.
NRC:	All right, just a moment, sir.
Pause
NRC:	Before you get started--] was talking with one guy--you're not
calling from Ashland Oil, are you?
Yes I am.
All right. Is this in Pennsylvania?
Right.
All right. So I can just reference the same report that--'cause I
got started . . .
Who were you talking to there?
Nagadosik?--or?
G a d o s i k ?
Yeah.
Okay.
That's the right way to spell his name-•G•a-d-o-s-i-k?
G-a-d-j-o-s-i-k'-yeah.
G-a-d-j .
G-a-j-d-o-s-i-k.
CaI ler:
NRC:
Caller:
NRC :
Caller:
NRC:
Ca I ler:
NRC:
Caller:
NRC:
Caller:
NRC:
Caller:
Long pause
NRC:
Caller:
NRC:
Okay, that report number's gonna
representing Ashland?
Ash I and Oil, right.
Are you representing-•you'
Well, I'm gonna put your name in place of h i s • - what was your name,
sir?
Caller: Morgan.

-------
NRC Transcript
Page 5
NRC:	Morgan?
Caller:	Yes. M-o-r-g-a-n.
NRC:	And your first name?
Ca11er:	George.
NRC:	And you're at 412-462-5111?
Caller:	They're out of service right now, but yes, that is our number.
NRC:	Uhat's another number?
CaI Ier:	Pardon?
NRC:	Is there another number?
Caller:	Right now we don't have one. I'm over at the neighboring factory
here. Ah, let's see, 384-3350.
NRC:	384?
Caller:	3350.
f
NRC:	And it is--the proper name of the company is Ashland Oil?
Caller:	Ashland, yes. Ashland Oil, Inc.
NRC:	The address is State Street and Route 837?
Caller:	Uh--204 Glass House Road.
NRC:,	And that's Floreffe, F-1•o-r•e-f-f-e, Pennsylvania?
Caller:	Right. 15025.
NRC:	15025.
Caller:	Right.
NRC:	And that's mile 25 on the Nongona--Nongahelia River.
Caller:	Honongahela River, right.
NRC:	Allegheny County.
Caller:	Right.

-------
NRC Transcript
Page 6
NRC:	Spill occurred at what time?
Caller: I was notified at 5:30, so I imagine sometime between 5 and 5:30.
NRC:	Because he called me at 17:22.
Caller: That's about it then, because he called me probably about the same
time.
NRC:	All right. Spilled diesel fuel. Do we have an amount?
Caller: Ah--an undetermined amount right now, but the tank ruptured, so it
hard to say.
NRC:	And it's a storage tank?
Caller:	Right.
MRC:	And it collapsed.
Caller:	Right.
NRC:	Is it going into the water?
Caller:	1 haven't down been on the river, but I've heard that it is, so I'
assuming that it is.
NRC:	And, what's being done? Do you have any idea?
Caller: Right now we have all the local fire departments; they got
everything cordoned off. They're bringing in some sand trucks and
some end loaders to put out on Route 837. And we're trying to
survey the situation right now over in the terminal to see what we
have got there exactly.
NRC:	Okay. What was the capacity of this tank?
Caller: Ah, 90,000 barrels.
NRC:	So it's potential that 90,000 barrels have spilled out.
Caller: I--the max I would say, if indeed it's true, would be about 80,000
If we've lost it all, I haven't been able to determine that yet.
NRC:	Have you notified any other agencies?
Caller: Ah, just our own emergency group and we'll be calling the Coast
Guard ...
NRC:	I've notified the Coast Guard in Pittsburgh, so . . .

-------
NRC Transcript
Page 7
Caller:	Okay.
NRC:	... a I ready.
Caller:	Okay, that'll take care of that, then.
NRC:	And, I was looking at any state agencies yet.
Caller:	Ah, no I haven't yet, that'll be the next one on the line then.
NRC:	That's the Pennsylvania DNR?
Caller:	Yeah.
NRC:	All right, so it looks like a pretty bad situation.
Caller:	1 would say right now it's a very bad situation.
NRC:	All right.
Caller:	Okay, could I have your name please?
NRC:	It's Petty Officer Mac key *•M-a•c•k-e-y.
Caller:	H-a-c-k-e-y. Thank you.
NRC:	Yes, sir.
Caller:	Bye.
Call #4 • NRC Incoming
NRC:	National Response Center.
Caller: Yes, sir. My name is James Smith. I'm the safety office, Hazardous
Materials Response Team from the PIeasantvi I I e Volunteer Fire
Company. Ue are currently at the scene of a diesel fuel storage
tank coll apse.
NRC:	Yes, s i r - • i n Floreffe, Pennsylvania.
Caller: Yes, sir. You've been made aware of that?
NRC:	Yes, sir. Do you have any details on how much has been spilled?

-------
NRC Transcript
Page 8
Caller: Yes, sir. Ah, the best details we can get at the moment are
approximately 100,000 gallons. Presently, the containment dike
surrounding the tank has contained most of it. Unknown as to how
much. We do have a spill across the highway and some towards the
river, however we are unable to ascertain exactly (faded). We have
contained it as best as possible. In the process of containing it
to the best of our ability. Local emergency management has been
notified, but we definitely do have approximately 100,000 gallons.
NRC:	All right. But not that much in the river.
Catler:No,sir.
NRC:	All right. Well, I've just talked with the owner and he said that
it's a 90,000-barrel capacity tank.
Ca I I e r : Okay.
NRC:	And he said at the most he suspect 80,000 barrels spilled. That's a
whole lot more than 100,000 gallons. And, ah--but the tank is
surrounded with a dike?
Caller:	Yes, sir.
NRC:	And the dike?--it's overflowing the dike?
Caller:	Yes, sir.
NRC:	All right.
Ca 11 er:	Okay?
NRC:	I'll put that into the report that I got from them.
Caller:	Okay, thank you, sir.
NRC:	Bye.

-------
APPENDIX C
INCIDENT-SPECIFIC REGIONAL RESPONSE TEAM

-------
APPENDIX C
INCIDENT-SPECIFIC REGIONAL RESPONSE TEAM
ASHLAND MAJOR OIL SPILL
THOMAS C. VOLTAGGIO, CO-CHAIRMAN
DENNIS CARNEY
ROBERT E. CARON
STEPHEN D. JARVELA
ALAN JACKSON
U.S. Environmental Protection Agency
Region III, Superfund Branch
841 Chestnut Building
Philadelphia, PA 19107
(215) 597-9893
FRED STROUD
U.S. Environmental Protection Agency
Region IV
345 Courtland Street, N.E.
Atlanta, GA 30365
(404) 347-3931
MICHAEL STRIMBU
U.S. Environmental Protection Agency
Region V
230 S. Dearborne Street
Chicago, IL 60604
(312) 353-2102
CMDR JAMES CLOW
U.S. Coast Guard, Fifth District (meps)
431 Crawford Street
Portsmouth, VA 23705
(804) 398-6638
CMDR ROBERT LUCHUN
U.S. Coast Guard, Second District (meps)
1430 Olive Street
St. Louis, MO 63103-2398
CMDR EUGENE A. MIKLAUCIC
U.S. Coast Guard, Marine Safety Office
Second District
Suite 700, Kossman Building
Forbes Avenue and Stanwix Street
Pittsburgh, PA 15222
(412) 644-5808

-------
ANITA MILLER
U.S. Department of Interior
U.S. Courthouse, Room 502
Second and Chestnut Streets
Philadelphia, PA 19106
(215) 597-5378
DR. JEAN SNIDER
U.S. Department of Commerce
National Oceanic and Atmospheric Administration
Hazardous Material Response Branch
11400 Rockville Pike
Rockville, MD 20852
(301) 443-8933
JOSEPH McCAREY
Federal Emergency Management Agency
105 South 7th Street
Philadelphia, PA 19106
(215) 931-5520
COL MATT MILLER
U.S. Army Corps of Engineers, Pittsburgh District
Hydrology and Hydraulics Branch
1928 Federal Building, 1000 Liberty Avenue
Pittsburgh, PA 15222
(412) 644-6831
JOHN BARRY
U.S. Department of Labor
Occupational Safety and Health Administration
Gateway Building, Suite 2100
3535 Market Street
Philadelphia, PA 19104
(215) 596-1201
PETER TENNANT
ORSANCO
49 East 4th Street
Suite 815
Cincinnati, OH 45202
(513) 421-1151
FRED OSMAN
Pennsylvania Department of Environmental Resources
P.O. Box 2063, Fulton Building
Harrisburg, PA 17120
(717) 787-2814, 5028
JOSEPH LaFLEUR
Pennsylvania Emergency Management Agency
P.O. Box 3321
Harrisburg, PA 17105
(717) 783-8016

-------
RON SANDY
West Virginia Department of Natural Resources
1201 Greenbrier Street
Charleston, WV 25311
(304) 348-3614
RUSS RADER
Assistant: Director, Environmental Engineering Division
West Virginia Department of Health
1800 Washington Street E., Room 550
Charleston, WV 25305
(304) 348-2981
WILLIAM BURGER
Kentucky Department for Environmental Protection
Division of Water
Environmental Response Team
18 Reilly Road
Frankfort, KY 40601
(502) 564-3410
ZACK CLAYTON
Ohio Environmental Protection Agency
1800 Watermark Drive
P.O. Box 1049
Columbus, OH 43266-0149
(614) 481-4300,

-------
APPENDIX D
RIVER MONITORING WORK GROUP

-------
APPENDIX D
RIVER MONITORING WORK GROUP
FEBRUARY 11, 1988
SEWICKLEY , PENNSYLVANIA
Participants in the Hork Group to conduct the critique of the initial
response at the Ashland Major Oil Spill was chaired by ORSANCO included
representatives of the agencies which were involved in the monitoring efforts
and included:
NAME
Scott Fennell
ORGANIZATION
ORSANCO
ADDRESS
49 E. 4th Street
Cincinnati, OH 45202
TELEPHONE NO.
(513) 421-1151
Russ Rader
John Youger
UV Health Dept
Ohio EPA
Charleston, UV 25311
1800 Uatermark Drive
Columbus, OH 43215
(304) 348-2981
(614) 481-7130
Chuck Taylor
Ohio EPA
1800 Uatermark Drive
Columbus, OH 43215
(614) 481-7025
Steve Steranchak PADER
121 S. Highland Ave.
Pittsburgh, PA 15206
(412) 645-7100
Patricia Miller	PADER
121 S. Highland Ave.
Pittsburgh, PA 15206
(412) 645-7100
Russ Stotzman
Tom Proch
Mike Havelka
Bob Moran
Peggy Uallace
PADER
PADER
EPA/Ueston TAT
Indiana DEM
CHMR
121 S. Highland Ave.
Pittsburgh, PA 15206
121 S. Highland Ave.
Pittsburgh, PA 15206
Suite 436, Hawley Bldg
Wheeling, UV 26003
5500 Bradbury
Indianapolis, IN 46241
320 Uilliam Pitt Uay
Pittsburgh, PA 15238
(412) 645-7100
(412) 645-7100
(304) 233-1610
(317) 342-5158
(412) 826-5320
Sarah Shockley
CHMR
UPARC
(412) 826-5320
Lythia Metzmeier KY Div. of Water	18 Reilly Road	(502) 564-3410
Frankfort, KY
Ron Sandy	WVDNR	1201 Greenbrier	(304) 348-3614
Charleston, WV

-------
NAME
Sam Perris
Nark Anthony
Gerald L. Greiner
James Amnion
Patr i ck Neichter
George Kincaid
Michael Koryak
Bill Cremeans
Robert W. Schmitt
Jim Irwin
Michael Dalton
Gene M i kIauc i c
Jerry Schulte
Peter Tennant
ORGANIZATION
WVDNR
Corps of Engineers
PA Fish Commission
PA Fish Commission
Corps of Engineers
Corps of Engineers.
Corps of Engineers
Corps of Engineers
Corps of Engineers
Ohio EPA
Ohio EPA
U.S. Coast Guard
ORSANCO
ORSANCO
ADDRESS
1304 Goose River Rd.
Fairmont, WV
Cincinnati, OH
1520 Menk Road
New Kensington, PA
P.O. Box 31
U. Mifflin, PA
P.O. Box 59
Louisvi11e, KY 40201
Huntington, UV
Pittsburgh, PA
Huntington, WV
Pittsburgh, PA
Twinsburg, OH
1800 Watermark Drive
Columbus, OH 43215
Pittsburgh, PA
49 E . 4th St.
Cincinnati, OH 45202
49 E. 4th St.
Cincinnati, OH 45202
TELEPHONE NO.
(304)	366-5880
(513)	684-3070
(412)	339-1564
(412)	672-0740
(502)	582-6739
(304)	529-5694
(412)	644-6831
(304)	529-5338
(412)	644-6951
(216)	425-9171
(614)	481-4300
(412)	644-5808
(513)	421-1151
(513)	421-1151

-------
APPENDIX E
GLOSSARY OF ABBREVIATIONS

-------
APPENDIX E
GLOSSARY OF ABBREVIATIONS
ATSDR	Agency for Toxic Substances and Disease Registry
COE	United States Army Corps of Engineers
DOI	United States Department of Interior
EPA	United States Environmental Protection Agency
FEMA	Federal Emergency Management Agency
IDEM	Indiana Department of Environmental Management
KDW	Kentucky Division of Water
NOAA	National Oceanic and Atmospheric Administration
NRC	National Response Center
OEPA	Ohio Environmental Protection Agency
ORSANCO	Ohio River Valley Water Sanitation Commission
OSC	On-Scene Coordinator
PADER	Pennsylvania Department of Environmental Resources
PEMA	Pennsylvania Emergency Management Agency
PFC	Pennsylvania Fish Commission
RRT	EPA Regional Response Team
TATM	EPA Technical Assistance Team Member
USCG	United States Coast Guard
WVDNR	West Virginia Department of Natural Resources

-------
APPENDIX F
ASSESSMENT OF MONITORING ELEMENTS

-------
APPENDIX F
ASSESSMENT OF MONITORING ELEMENTS
For purposes of assessment, monitoring efforts in the after-
math of the spill have been divided into two categories based on
the types of analyses. The categories are analyses providing
qualitative data and those providing quantitative data.
Qualitative Data
Qualitative measures are those that provide a measure of
relative concentration. This type of measurement was found to
address the problem of tracking the spill in the most timely
fashion.
Fluorometrv
The fluorometer was found to be an exceptionally useful tool
in tracking the occurrence of the plume. Fluorometers relate the
visible light emitted by fluorescing compounds to units of
concentration.
Certain components of the diesel fuel (naphthalene and
benzene had been identified) made the fluorometer a viable
instrument in this case. Moreover, the instrument is rugged and
transportable, easy to operate and provides nearly instant
results. Figure 1 shows a concentration profile as measured with
the boat fluorometers. Figure 2 shows the apparent dilution of
the plume as it traveled downstream. The fluorometer performed
admirably in its intended use of tracking the spill.
Nevertheless, there are unanswered questions regarding further
interpretation of the results.
Ultimately, it may be possible to convert measures of fluor-
escence into diesel fuel concentration. This will require ident-
ification of diesel fuel components that fluoresce at 524 nm, and
the determination of their relative concentration in diesel fuel.
In addition, account must be taken of the relative degradation or
volatilization of the fluorescing versus non-fluorescing
components with time. Turbidity, which varied greatly over the
monitoring period, may affect fluorescence as well.
Two areas for exploring the use of fluorometry include: 1)
Its use in quantifying concentration; and 2) its utility for
other contaminants. The first area will become apparent to some
extent as analysis of data progresses. As indicated in the body
of the report, initial analyses indicate linear correlation
between fluorescence and concentration. A literature search may
reveal other studies addressing the issue. Secondly, manufac-
turers' literature may be helpful in identifying other compounds
detected by the fluorometer. This information, along with an

-------
inventory of materials commonly stored or shipped on the river,
would be useful for development of emergency response monitoring
programs.
Hanbv Test
The Hanby Test is a simple extraction/colorimetric test that
may be performed with a field kit in about 15 minutes. The
principal reactions involve an extraction reagent reacting with
aromatics in the contaminated sample. A catalyst is then added
to create color, the hue and intensity of which is compared to a
standard chart for the interpretation of concentration. While
the method has the desired characteristics of simplicity and
immediacy, there are apparent shortcomings.
Determination of concentration with the Hanby Test is a sub-
jective judgement, which may not be reproducible among several
field personnel. Moreover, because the reaction is subject to
photochemical oxidation (i.e., in sunlight), the sample must be
analyzed within minutes, and is thus unavailable for comparison
with subsequent samples. According to information in the manu-
facturer's brochure, the method appears to be effective up to 20
ppm of diesel fuel; analytical results from the Pittsburgh area
indicate the diesel fuel concentration to be on the order of 500
ppm (Robinson Township intake, EPA sample of January 6, 1988).
In light of these problems, the fluorometer was preferred over
the Hanby Test for continued field use. Meanwhile, the
manufacturer is pursuing improvements to the method, which may
make the test viable in the future.
Odor
Odor as a means of determining contamination remains a
standard practice at water utilities along the river, although it
was not pursued in the coordinated efforts. The method is very
simple and results quickly obtained. When heated, even dilute
concentrations of diesel fuel (less than 1 ppm) were apparent in
water-intake samples as a kerosene-like smell. For example, the
laboratory technician at the Portsmouth Water Plant success-
fully detected the leading edge and peak concentration arrivals
by odor as later confirmed by fluorometer data. The method was
not pursued in boat monitoring because a more definitive measure
was desired and because continuous odor sampling is hampered by
fatigue (as well as proximity to diesel engines on tow boats).
Quantitative Data
Quantitative measures have the advantage of providing real
concentration figures which may be more useful in decisions about
treatability, threats to wildlife and fisheries, etc. Unfortu-
nately, measurements take more time to obtain and uncertainty of
results remains a problem.

-------
Total Organic Carbon
Total organic carbon (TOC) is a measure of the total organic
content of a contaminated water sample, including the aromatic
and aliphatic compounds that make up diesel fuel. The required
analysis time is relatively short (approximately 1/2 hour), but
because the equipment is designed for the laboratory, it is
unsuitable for field measurements. Another shortcoming is the
uncertainty of the analysis. According to Standard Methods
(1985), the precision of Combustion-Infrared Method is 5 to 10
percent on unfiltered samples. But a bigger problem may be the
nonspecificity of the analysis. In the case of tracking a spill,
there is no assurance that increased TOC is due to the occurrence
of the contaminant plume versus unknown discharges. Indeed,
initial review of the data appears to affirm the decision not to
rely on TOC as the primary means of tracking the plume. The TOC
data showed no logical trend.
Oil and Grease
Oil and grease (O&G) is a nonspecific measurement of the
occurrence of similar compounds which dissolve in trichlorotri-
fluoroethane. It includes all materials extracted from the
acidified sample and not volatilized during the test, including
sulfur compounds and chlorophyll. A significant fraction of
diesel fuel may be left unextracted by the solvent or lost to
volatilization, depending largely on method (Standard Methods,
1985, p. 497). Like TOC, it may be unsuitable for tracking a
plume where interference from other contaminants complicates
interpretation of the data.
Gas Chromatography
For identification of contaminants and quantification of
concentration, gas chromatography (GC) is the preferred method.
Detection limits are typically about 10 ppb or less, sufficient
for purposes of addressing treatability. In an emergency, how-
ever, a drawback is the relatively long analysis time ranging
from one hour to one day. Also, the delicate nature of the
equipment precludes field use and necessitates employment of
analytical laboratories, which are costly in time and money.
The most common use of gas chromatography in the affected
area is for analysis of volatile organic compounds. Ten water
utilities along the Monongahela and Ohio Rivers are participants
in the ORSANCO Organics Detection System and collect daily
samples for volatile organics analysis. The diesel fuel spilled,
however, did not contain significant quantities of volatiles. GC
analysis for base neutrals was necessary to identify the signifi-
cant components of the material spilled. That type of analysis
is more time consuming as well as less widely available than that
for volatiles. At best, results were available 24 hours after
sample collection.

-------
For purposes of evaluating the recent monitoring efforts and
developing monitoring plans for future events, it is desirable to
combine or compare data obtained by different measurements. This
may include, for example, correlations of gas chromatography and
fluorometer data in order to improve the use of the latter.
Initial analyses performed by the Huntington District U.S. Corps
of Engineers indicate great potential of using fluorometry
(perhaps combined with turbidity measurementss) for the
determination of contaminant concentration in ppm. Similar
comparisons of odor detectability, Hanby Test, etc. may reveal
potential supplements to fluorometry for tracking and perhaps
quantifying contamination. Finally, a study of the actual plume
velocities versus NWS river velocities is also in order for the
eventual improvement of time-of-arrival prediction methodology.

-------
w
u
2?
UJ
y
D
3
u-
FIGURE 1
PLUME PROFILE OF 15,16 JAN
LEADING EDGE TO THE SPILL SITE
RIVER MILE

-------
4.5
4
3 J5
3
23
2
1B
1
0.5
0
AND BACKGROUND FLUORESCENCE
COMMON FLUORESCENCE UNITS

~
\
RAIN
•4f
T
100
300
500
RAIN
700
OHIO RIVER MILE
+ BACKGROUND VALUES

-------