PRELIMINARY DRAFT A STUDY OF THE COST IMPACT OF THE RESOURCE CONSERVATION AND RECOVERY ACT (RCRA) ON THE DISPOSAL OF NONHAZARDOUS WASTES FROM MINING PEDCo ENVIRONMENTAL ------- z_ppt cut 7 (?/£>-L>-79-003 PRELIMINARY DRAFT 'A*'''StUDY~W"TllTTOSTTM^f^F-fHE RESOURCE CONSERVATION AND RECOVERY ACT (RCRA) ON THE DISPOSAL OF NONHAZARDOUS WASTES FROM MINING Prepared by PEDCo Environmental, Inc. 11499 Chester Road Cincinnati, Ohio 45246 Contract No. 68-03-2577 Work Directive No. 9 PN 3350-1 Prepared for EPA Technical Project Monitor S. Jackson Hubbard Resource Extraction and Handling Division IERL-Cincinnati Office of Research and Development In cooperation with Land Disposal and Hazardous Waste Management Divisions Office of Solid Waste Washington, D.C. March 1979 ------- A. A STUDY OF THE COST IMPACT OF THE RESOURCE CONSERVATION AND RECOVERY ACT ON THE DISPOSAL OF NONHAZARDOUS WASTES FROM MINING The main objective of this study is to present estimated total capital and annual operating costs of mining solid waste disposal technologies that will satisfy the criteria prescribed in Section 4004 of the Resource Conservation and Recovery Act (RCRA). The study focuses on the following 10 mining industries: copper, iron ore, molybdenum, gold, lead, zinc, phosphate, clay, stone, and sand and gravel. These 10 industries contribute about 91 percent of all the nonhazardous mining solid wastes (excluding coal mining wastes), as shown in Table 1. This table also shows what portion of the wastes from an industry is considered nonhazardous. All mine wastes (overburden and waste rock) from these industries are considered nonhazardous, with the exception of about 30 percent of the phosphate overburden generated in Florida, which is considered hazardous. Only three of the industries- clay, sand and gravel, and gold (placer mines only) generate nonhazardous tailings (beneficiation wastes). Nonhazardous waste from all other domestic mining industries are shown in various tables in this study as from "other industries." The costs are divided, for each criterion, into national baseline costs; national state- and other Federal-induced costs; and national RCRA (Criteria-induced) costs (Table 2). The baseline costs represent estimated costs of control methods already in use by the industry--tailings ponds, diversion ditches, closure practices—that satisfy or partially satisfy any of the six RCRA criteria. State-induced costs represent estimated costs of complying with state standards for the control of nonhazardous wastes; other Federal-induced costs represent those complying with Federal regulations other than RCRA. The Clean Water Act of 1977 covers surface waters and wetlands when an NPDES permit is denied; therefore, the costs of these controls are considered separate from the Criteria-induced costs. This report does not, 2 ------- TABLE 1 ESTIMATED MINING INDUSTRY PRODUCTION AND NONHAZARDOUS WASTE QUANTITIES (1,000 metric tons) Mining No. of Nonhazardous wastes industry mines Product Tailings Mine wastes Total Copper 61 244,700 627,900 627,900 Iron ore 68 216,900 234,800 234,800 Molybdenum 3 55 10,740 10,740 Gold 99 0.021 108 8,408 8,516 Lead/zinc 33/36 16,840 4,778 4,778 Phosphate 47 169,300 150,200S 150,200 Clay 1,249 39,770 2,275 33,760 36,035 Stone 5, 584 815,400 Negligible 66,160 66,160 Sand and gravel 7,007 718,000 35,900 Negligible 35,900 Coal 6,459 573,300 11 H Other 829,000 21,840+ 97,73O0 119,570 Total 60,123 1,234,476 1,294,599 'Represents tailings from gold placer mining. Other gold mining tailings are considered hazardous. +Fifty percent of tailings from other mining industries are considered to be nonhazardous. ^Thirty percent of all phosphate mine waste in Florida is considered hazardous and thus is not included in this number. SMCRA is responsible for coal mine wastes. a All mine wastes from other mining industries are con- sidered to be nonhazardous. 3 ------- TABLE 2 ESTIMATED NATIONAL BASELINE AND REGULATORY COSTS FOR NONHAZARDOUS MINING WASTE CONTROLS (1,000 dollars) Wetlands Costs Ground water Surface water NPDES NPDES permit permit granted denied Total Floodplains Closure NPDES permit granted NPDES permit denied National baseline Total capital Annual OtM Total annualized National state- and , other Federal-induced Total capital Annual OiH Total annualized National criteria- induced Total capital Annual OfcM Total annualized 2,166 111 411 295,900 32,400 96,000 61,500 6,800 19,900 440,800 22,410 98,530 110,500 5,500 34,800 30,300 1,000 • 3,700 26,900 2,700 8,900 250,100 292,000 336,500 54,500 34,500 49,500 208,300 10,400 66,400 206,400 10,300 66,500 1,837,300 159,300 505,700 497,466 57,021 148,441 645,000 49,300 200,900 2,132,100 179,100 601,000 864,800 340,300 533,700 2,105,200 176,400 592,100 *These costs do not include nonhazardous waste control costs for the coal mining industry. ------- however, include the costs of control methods for nonhazardous wastes from coal mining; these wastes are regulated by the Surface Mining Control and Reclamation Act of 1977 (SMCRA). Estimates of these costs are presented in the regulatory analysis report prepared to support the final SMCRA regulations (Federal Register, March 13, 1979). Criteria-induced costs, finally, are those costs of complying with RCRA that exceed the compliance costs for state and other Federal standards. The three cost categories are total capital, annual operation and maintenance, and total annualized costs. The last is the sum of annualized capital and annual operation and maintenance costs. Baseline costs for ground water are minimal when compared with the costs induced by state and Federal regulations. Baseline costs for surface water, however, are considerably greater because of the protection afforded by existing tailings ponds at mine sites. There are no baseline costs for floodplains and air quality because there are practically no controls specifically in use to satisfy these criteria. Some industries have measures that satisfy the RCRA closure criterion. The industries would have to incur an estimated additional capital cost of $1.84 billion to meet the RCRA closure criterion. National baseline capital costs of nonhazardous waste control for all mining industries are estimated at $497 million. The annualized baseline control costs are an estimated $148 million. National state- and other Federal-induced capital costs are estimated at $645 million if NPDES permits are granted for facilities located in wetlands, and $865 million if these permits are not granted. Respective annualized costs are $201 million and $534 million. The total RCRA or Criteria-induced costs are estimated at $2.13 billion (NPDES permits granted) and $2.11 billion (NPDES permits denied). Respective annualized costs are $601 million and $592 million. 5 ------- 1. Development of Model Plants Costs attributable to RCRA and other state and Federal legislation were determined by using the concept of a model plant, because a detailed, site-by-site study was beyond the scope of this report. For each of the 10 major mineral industries, a model plant was developed that represented the production level and the quantities of tailings and mine wastes generated. Production levels were obtained from the Minerals Yearbook, and solid waste tonnages were obtained from available sources and contacts within the mining . . . . 1,2 industries. Figures 1 through 9 display the model plant sizes used in the study. The model plants include various steps within the process that generate significant quantities of solid wastes. They also reflect the control methods that are practiced to some extent within the industry. Each state was allocated a number of model plants based on the production levels for that industry within the state. The model plant size for the copper industry (Figure 1) was determined on the basis of the total solid wastes generated within the industry, and from the fact that 25 out of 61 mines produce 93 percent of the Nation's copper.The model plant, therefore, is a typical mine within the group of 25 major producing mines. The iron ore model plant size (Figure 2) was determined by the same 3 method, but with only 54 mines producing all of the Nation's iron ore. All of the primary molybdenum ore is produced at three mines, and three model plant sizes were thus developed from information on actual tonnages obtained from the respective mining companies. The tonnages represent a molybdenum mine that uses both surface and underground mining methods (Figure 3). 6 ------- CHEMICAL FLOTATION ADDITIVES Figure 1. Copper mining and beneficiating model plant. ------- CHEMICAL Figure 2. Iron ore mining and beneficiating model plant. ------- CHEMICAL FLOTATION Figure 3. Molybdenum mining and beneficiating model plant. ------- The gold ore model plant size (Figure 4) was based on the production figures for only those sites that mine gold as the principal ore: i.e., actual gold mines. The lead/zinc industry model plant size (Figure 5) was based on combined production levels for the two industries. It is an average of the model plant sizes for lead and zinc, as determined separately. The lead model plant size was based on 25 mines producing 99 percent of the Nation's lead, and the zinc model plant size was based on 25 mines producing 89 percent of 3 the Nation's zinc ore. The clay model plant size (Figure 7) was determined by two methods. Mine waste tonnage was calculated as the average of the total mine wastes produced at all clay mines. Tailings tonnage was calculated as the average from the production of kaolin and fuller's earth, because these are the only clay processes that generate significant quantities of tailings.^ The model plant sizes for the remaining industries—phosphate rock (Figure 6); crushed, broken, and dimension stone (Figure 8); sand and gravel (Figure 9)--were calculated as an average production size based on the total number of mine sites within the respective industries. 2. Baseline and Criteria-Induced Control Methods for Tailings and Mine Wastes at Model Plants Most mining industries are now using control methods that satisfy at least some portion of the Federal criteria. These baseline controls are indicated on the model plant block diagrams for each industry (Figures 1 through 9). The copper, iron ore, gold, lead/zinc, clay, and stone industries have minimal diversion ditching to prevent surface waters from interacting with overburden piles. These industries also have minimal closure practices for overburden, usually involving grading and revegetation. "Minimal" diversion ditching and closure means that 20 percent (for ditching) and 10 percent (for closure) of the individual facilities within the industry are using these practices. Diversion ditching and closure of overburden primarily protect surface water from pollution by suspended solids. 10 ------- PLACER MINING OPEN PIT/UNDERGROUND MINING REAGENTS HATER (CYANIDE) Figure 4. Gold mining and beneficiation model plant. ------- ALL VALUES IN DRY METRIC TONS PER YEAR. Figure 5. Lead/zinc mining and beneficiating model plant. ------- Figure 6. Phosphate mining and beneficiating model plant. ------- WATER Figure 7. Clay mining and beneficiating model plant. ------- Figure 8. Crushed, broken, and dimension stone mining model plant. ------- WATER Figure 9. Sand and gravel mining model plant. ------- The molybdenum industry makes extensive use of diversion ditches, which are present in about 80 percent of the industry. Both the molybdenum and phosphate industries commonly grade and revegetate their overburden. Phosphate mining companies in Florida reclaim all or nearly all of their overburden. Unlined ponds are the baseline controls used in the two major industries (clay, sand and gravel) that produce tailings classified as nonhazardous. In addition to the ponds, the clay industry practices minimal closure for tailings. The stone industry produces negligible quantities of tailings. Control methods have also been formulated in response to RCRA. (See Figures 10 through 15.) These various controls are discussed below in terms of the criterion to which they apply. a. Ground Water Control methods that would meet the RCRA ground-water criterion (Figure 10) include the construction of diversion ditches to direct water away from the overburden and waste rock disposal areas. This control reduces the leaching of materials from these areas and subsequent pollution of the ground water. Industries that generate nonhazardous tailings would first evaluate the water table to determine whether leachate from existing, unlined tailings ponds could adversely affect the quality of ground water. A high/low water table has been delineated for this purpose. In a particular industry, the degree to which the tailings ponds will have an adverse impact on the ground water depends on the region where the industry is located. This study assumes, for example, that in the southeastern section of the country 25 percent of the land has a low water table and 75 percent a high water table; and these percentages are assumed to be reversed in states in the Southwest. A national summary of these high/low water-table percentages was prepared for the Northwest, Southeast, Southwest, Northeast, and Midwest (Table 3). 17 ------- NONHAZARDOUS WASTES TAILINGS MINE WASTES - DIVERSION DITCHES GROUND WATER TABLE EVALUATION HIGH GROUND WATER TABLE / LOW GROUND WATER TABLE \ NOTHING ADDITIONAL TO SATISFY RCRA CRITERIA SITE EVALUATION INSIGNIFICANT IMPACT SIGNIFICANT IMPACT MONITORING WELLS UPGRADE WITH LEACHATE COLLEC- TION SYSTEMS - MONITORING WELLS Figure 10. Controls induced by RCRA ground-water criterion covering nonhazardous wastes from the mining industry. 18 ------- TABLE 3 REGIONAL PERCENTAGES OF LOW OR HIGH WATER TABLE USED IN ANALYSIS OF GROUND WATER CRITERION Region Low water table (%) High water table (%) Northeast 50 50 Southeast 25 75 Southwest 75 25 Northwest 75 25 Midwest 25 75 Nonhazardous tailings ponds located in areas with low water tables are assumed to need no additional controls to satisfy the ground-water criterion. Ponds in areas with high water tables could be subjected to a site evaluation (consisting of a hydrogeological survey, permeability tests, evaluation, and report) to determine the actual impact on the ground water. It is estimated that 80 percent of the site evaluations would show an insignificant impact, with the accompanying recommendation that monitoring wells should be installed and data collected quarterly at these sites. The remaining 20 percent of the evaluations would indicate significant ground-water impact, with the recommendation that these sites install further control measures. The controls would consist of collection wells for the leachate to prevent it from entering the ground water. In addition, monitoring wells would be installed in appropriate locations to perform quarterly checks of the leachate collection system. b. Surface Water Control methods to meet the RCRA surface water criterion are shown in Figure 11. Diversion ditches around mine waste piles would prevent surface runoff from interacting with the waste and carrying it, primarily as suspended solids, into surface waters. The tailings ponds is a baseline control method for nearly all mining industries; it contains the tailings and prevents surface water contamination. One exception to the use of tailings ponds is gold 19 ------- placer mining operations, which are primarily located in Alaska and California. Sluiced wastes (tailings) from these operations are the only nonhazardous tailings within the gold mining and beneficiating industry. In current practice, they are pumped directly to streams and rivers. Control of the tailings from gold sluicing operations could be accomplished by construction of tailings ponds. NONHAZARDOUS WASTES - DIVERSION DITCHES - DIVERSION DITCHES - COMPACTION OF DIKE - SOIL COVERAGE OF DIKE - REVEGETATION OF DIKE Figure 11. Controls induced by RCRA surface water criterion covering nonhazardous wastes from the mining industry. For industries having tailings ponds, further controls to meet the surface water criterion include diversion ditches and upgrading of the pond dikes by compaction, soil coverage, and revegetation. The diversion ditches would direct waters away from tailings ponds to prevent the dikes from being weakened or washed out; and to reduce the chances of pond overflow. Either condition could cause suspended solids to contaminate surface waters. c. Wetlands Control methods to meet the RCRA wetland criterion are shown in Figure 12. Two scenarios are considered for tailings and other mine wastes. One scenario assumes that NPDES permits will be granted to all mining industries located in wetlands, allowing solid wastes to be disposed of within the area. The second scenario assumes that no NPDES permits will be granted and that all 20 ------- NONHAZARDOUS WASTES TAILINGS MINE WASTES NPDES PERMIT APPLICATION DENIED / GRANTED \ NPDES PERMIT APPLICATION DENIED GRANTED / \ CLOSURE OF EXISTING TAILINGS POND [REQUIRES ADDITIONAL MEASURES (FIG. 16)] ACQUISITION OF LAND ANO CONSTRUCTION OF A NEW DISPOSAL FACILITY OUTSIDE WETLANDS AREA UPGRADE DIKE - ACQUISITION OF LANO ANO COMPACTION OF DIKE CONSTRUCTION OF A NEW SOIL COVERAGE OF DIKE DISPOSAL FACILITY OUT- REVEGETATION OF DIKE SIDE WETLAND AREA - MONITORING WELLS - TRANSPORTATION OF WASTES TO NEW DISPOSAL AREA TRANSPORTION OF WASTES TO NEW DISPOSAL AREA Figure 12. Controls induced by RCRA wetland crierion covering nonhazardous wastes from the mining industry. ------- mining wastes generated in wetlands will have to be transported out of the area. Control methods for the two scenarios are outlined in the following paragraphs: NPDES permits granted: Monitoring wells, checked on a quarterly basis, would be installed around mine waste piles as a precautionary measure. The dikes around tailings ponds would be upgraded into a 3:1 sloped structure (3 horizontal, 1 vertical). This control would also include dike compaction, soil coverage, and revegetation (similar to the controls for the surface water criterion). NPDES permits denied: This scenario would involve the purchase of land outside the wetlands to construct disposal facilities for tailings and mine wastes. The control system would include the transportation of these nonhazardous wastes to the new sites. With one exception, it is assumed that the wastes from all mining industries located in wetlands would have to be trucked a distance of 16 kilometers one way. The exception is the Florida phosphate industry, which is located in areas of extensive wetlands; the assumed trucking distance in this case is 32 kilometers. Because of the distances involved, pumping the tailings to the new facility is not considered feasible. The control method described here includes thickening the tailings slurry to a 70 percent solids sludge before it is transported by truck. Overflow from the centrifuge would be pumped to storage tanks as recycle water. In addition to trucking the newly generated tailings to new disposal facilities that meet RCRA criteria, the scenario includes closing the existing tailings ponds (pond free water pumped off, pond allowed to drain, 0.6 meters of soil uniformly graded over the pond, and revegetation). Closure measures for the relocated disposal facilities are described under the closure criterion. The percentages of the specific industries located in wetlands were calculated from the percentages presented in Table 13 (page 111-6) of the 22 ------- Draft EIS; and from knowledge of the relative locations of these wetlands and the minerals industry facilities when this information was available. For example, although 46 percent of Florida is wetlands, most of the Florida phosphate industry is located within that portion; so a value of 90 percent was assumed to represent this case. d. Floodplains Control methods to meet the RCRA floodplains criterion are shown in Figure 13. Diking is the principal method selected, for both tailings and mine wastes, to satisfy this criterion. For mine wastes, this entails construction, compaction, soil coverage, and revegetation of dikes 3 meters high at a 3:1 slope. The dikes would be built around accumulated plus newly generated mine waste. On a national average, three sides of the mine waste piles (assuming roughly rectangular shapes) would require diking. In actuality, some waste piles are located against a ridge or ridges bordering the floodplains; these piles may be protected from floods on one, two, or three sides. Conversely, some waste piles are located in the middle of floodplains, and dikes would have to be built around their entire periphery. For tailings ponds, the floodplain criterion would include upgrading the pond dikes to a 3:1 slope, compacting, covering with 0.6 meters of soil, and seeding and fertilizing to prevent erosion. I NONHAZARDOUS WASTES (TAILINGS AND MINE WASTES) - DIKE CONSTRUCTION - COMPACTION OF DIKE - SOIL COVERAGE OF DIKE - REVEGETATION OF DIKE Figure 13. Controls induced by RCRA floodplain criterion covering nonhazardous wastes from the mining industry. 23 ------- The percentages of industries located in floodplains were determined on a state-by-state basis. Most of the states were assigned a value of 5 percent, which is the estimated average percentage of land in the United States that is within floodplains. Air Quality Control methods to prevent adverse impacts on air quality are shown in Figure 14. Fugitive dust from mine waste piles would be controlled by revegetating the piles. This method is discussed under the closure section. NONHAZARDOUS WASTES TAILINGS MINE WASTES KEEPING FREE WATER ON THE ENTIRE PORTION OF THE TAILINGS POND NO CONTROLS NEEDED DURING ACTIVE DISPOSAL OF MINE WASTES. CLOSURE CRITERIA- INDUCED CONTROLS PROVIDE FOR LONG TERM PROTECTION OF AIR QUALITY Figure 14. Controls induced by RCRA air quality criterion covering nonhazardous wastes from the mining industry. Fugitive dust can also be generated by the action of the wind across dried areas of tailings ponds, particularly in arid regions of the West and Southwest. Tailings that are considered nonhazardous, such as those of the clay and sand and gravel industries, are contained in ponds that are smaller in size and are nearly all located in nonarid regions. As a result, the pond surfaces are wet most of the time (i.e., the addition of new tailings water and the precipitation rate exceed the evapotranspiration rate for these areas). Because the ponds do not dry out and create dust problems, no additional controls to protect air quality standards are considered necessary. 24 ------- f. Closure Control methods to meet the RCRA closure criterion are shown in Figure 15. The RCRA criterion requires that accumulated and newly generated, nonhazardous mine wastes be closed with 0.6 meters of soil cover, and that the soil be revegetated. With a few exceptions, such as Florida phosphate, most of the mineral industries have allowed mine wastes to accumulate in piles since the startup of the mines. The quantity of these wastes is considerable, depending on the type of industry and length of time the mines have been in operation; the copper model plant, for example, has an assumed life of 15 years. The control method for stabilizing these accumulated mine waste piles would involve regrading to provide adequately contoured slopes; compaction of this material; coverage with 0.6 meters of soil; soil amelioration; and seeding to revegetate. NONHAZARDOUS WASTES TAILINGS MINE WASTES DEWATERING SOIL COVERAGE RE VEGETATION - GRADING AND SURFACE COMPACTION - SOIL COVERAGE - REVEGETATION Fiaure 15 Controls induced by RCRA closure criterion covering nonhazardous wastes from the mining industry. The newly generated mine wastes would be spread out, compacted, covered with soil, and revegetated on a continual basis. These procedures are similar to the reclamation that is practiced in some industries. Closure would thus occur regularly, so that the wastes would be "closed" on a weekly, monthly, or even an annual basis rather than be allowed to accumulate through the remainder of the mine life. 25 ------- Procedures for closure of a tailings pond when it is full are also shown in Figure 15. Pond free water would be pumped to a pressurized filtering system to remove solids, and the clarified water would be discharged to a surface stream or river or used for operational purposes at the mine or mill. When the drained area was stable, 0.6 meter of soil would be used to cover the tailings, followed by compaction and revegetation. 3. Costs and Cost Methodology This section presents and discusses baseline costs, state- and other Federal-induced costs, and Criteria-induced costs on a capital and an annualized basis. All the costs are given in 1978 dollars. The methodology used to determine these costs is also discussed. The two principal sources of cost data were Richardson and Means; other sources were used for certain unit costs.5*8 a. Baseline and Above-Baseline Costs For each of the 10 mining industries, costs have been calculated for the baseline case and for the control methods attributable to government regulations (Table 4). Baseline costs include all the criteria; costs above baseline are figured separately for each criterion. In the copper industry, for example, the 61 mines have a total baseline capital cost (for all criteria) of $94,000; annual operating and maintenance costs are $3,216,000; and total annualized costs are $3,227,000. Capital costs above baseline to meet the ground-water criterion are estimated at $185,000, and total annualized costs are estimated at $37,000. Within this industry, the sum of the costs above baseline to meet all criteria is estimated at $433 million, and total annualized costs at $114 million. b. Costs Per Unit of Waste and Product The control method costs have also been calculated per metric ton of waste and of product, based on the total annualized costs for each industry (Table 5). For the baseline case, these costs in the copper industry are 26 ------- TABLE 4 ESTIMATED TOTAL BASELINF AND GOVFRNMFNT-TNDUCFD COSTS BY INDUSTRY AND BY CRITERION (1,000 dollars) !\> -VI Costs attributable to government regulations (above baseline) Wet lands Mining industry Copper Total capital Annual OtM Total annualized iron ore Total capital Annual OfcK Total annualized Molybdenum Total capital Annual otM Total annualized Gold Total capital Annual OtM Total annualized Lead/zinc Total capital Annual OtH Total annualized Phosphate Total capital Annual OtM Total annualized Baseline costs Ground water Surface water NPDES permit granted Nl'DES permit denied Floodplains Closure NPDES permit granted Total NPDES permit denied 94 3,21* 3,227 134 2,408 2,424 1,960 1,100 1,340 6 91 91 26 99 104 59 9, 292 9,292 IBS 10 37 264 14 SO 1,947 208 628 52 4 13 119 7 28 185 10 37 264 14 50 5,286 265 1,042 52 4 13 119 7 28 120 19 35 13 4 4 26,700 15,800 19,200 30 30 35 1,219 112,900 174 238,400 390 258,000 ,500 224 823 1,044 54 110 419 22 95 2,828 141 650 433,000 50,540 114,000 430,000 43,000 100,700 11,600 580 2,000 13,770 1,400 3,420 8,742 1,313 2,863 63,700 9,600 20,800 433,370 50,560 114,074 435,148 461,728 43,271 59,052 101,658 120,823 11,606 582 2,002 22,047 1,927 5,200 9,278 1,347 2,988 9,295 1,373 3,019 67,985 179,666 9,929 240,155 29,896 279*506 Clay Total capital 46,800 9,109 4,003 22,720 16,320 Annual OtM 15,180 923 201 598 2,977 Total annualized 22,050 2,861 1,040 1,793 5,743 7,891 107,700 151,423 145,023 397 4,366 6,485 8,864 2,0*0 26,940 34,684 30,634 Stone Total capital 1,300 2,500 2,500 14,130 10,640 Annual OtM 2,693 125 125 1,063 5,000 Total annualized 2,027 650 650 4,909 7,200 16,350 180,000 215,480 212,190 822 34,000 36,935 40,072 4,250 72,000 82,459 84,750 Sand and gravel Total capital 401,900 310,800 87,970 13,860 60,590 Annual OtM 17,800 34,300 4,399 693 3,030 Total annualized 93,600 101,100 28,800 4,536 15,530 345,100 421,800 1,179,530 1,226,260 17,300 56,692 59,029 113,000 117,000 364,436 375,430 Other Total capital 45,200 32,500 10,040 5,206 22,740 Annual OtM 5,187 3,560 503 335 26,540 Total annualized 13,500 10,540 3,166 1,167 30,570 37,810 167,000 252,556 270,090 1,896 14,500 20,794 46,999 12,100 45,970 72,943 102,346 Total Total capital 497,479 357,479 110,422 57,268 250,120 Annual OtM 57,056 39,152 5,529 3,686 291,777 Total annualized 148,455 115,908 34,827 12,834 336,278 415,942 20,856 133,078 1,837,312 159,299 505,693 2,778,423 2,971,275 228,522 516,613 802,340 1,125,784 ------- TABLE 5 ESTIMATED BASELINE AND REGULATORY COSTS PER UNIT BASIS * Current product value (S/metric ton) Baseline costs Mining industry National annualized costs ($1000/yr) $/metric ton of waste $/metric ton of product Copper 1,325 3,227 0.005 0.013 Iron ore 24.70+ and 0.675 2,424 0.010 0.011 Molybdenum 10,990' 1,340 0.125 24.4 Gold 6,77O,OOO0 91 0.011 4,330 Lead/Zinc Lead, 747; Zinc, 681 104 0.022 0.006 Phosphate 17.40 9,292 0.062 0.055 Clay 2.20 to 220** 22,050 0.612 0.554 Stone 2.85++ 2,827 0.043 0.003 Sand and gravel 2.46 93,600 2.61 0.130 * 1978 dollars; 1979 Mineral Commodity Summaries, U.S. Bureau of Mines ^Natural ores, 51.5% Fe. I Pellets, per metric ton unit of Fe. 'per ton of molybdenum in concentrate. ^Based on average selling price of $192.50/oz. ** Price varies with type and quality of clay. 4.x Dimension stone at $89.80/metric ton accounts for 0.15% of stone production. (continued) ------- TABLE 5 (continued) State-and other Federal- State-and other Federal-induced costs induced costs (NPDES permit granted) (NPDES permit denied) National National Mining industry annualized costs (SlOOO/yr) $/metric ton of waste $/metric ton of product annualized costs <$1000/yr> $/metric ton of waste $/metr ic ton of product Copper 69 0.0001 0.0003 69 0.0001 0.0003 Iron ore 829 0.004 0.004 12,500 0.05 0.05 Molybdenum 1 0.0001 0.02 1 0.0001 0.02 Gold 1,745 0.21 83,100 1,723 0.20 83,320 Lead/Zinc 99 0.02 0.006 31 0.007 0.002 Phosphate 704 0.005 0.004 159,400 1.06 0.95 Clay 5,640 0.16 0.14 10,500 0.29 0.24 Stone 4,565 0.07 0.006 11,100 0.16 0.01 Sand and gravel 169,300 4.72 0.24 183,300 5.1 0.26 (continued) ------- TABLE 5 (continued) Criteria-induced costs Criteria-induced cost (HPDES permit granted) (NPDES permit denied) Mining industry National annualized costs ($1000/yr) $/metric ton of waste $/metrie ton of product National annualized costs ($1000/yr) $/metric ton of waste $/metric ton or product Copper 114,200 0.18 0.47 114,200 0.18 0.47 Iron ore 100,800 0.43 0.46 100,800 0.43 0.46 Molybdenum 2,000 0.19 36.3 2,000 0.19 36.3 Gold 3,574 0.42 170,200 3,574 0.42 170,200 Lead/Zinc 3,020 0.63 0.18 3,020 0.63 0.18 Phosphate 21,210 0.14 0.13 20,800 0.14 0.12 Clay 29,150 0.81 0.73 28, 200 0.71 0.71 Stone 77,710 1.18 o o 7 3,960 1.12 0.09 Sand and gravel 199,500 5.56 0. 28 196,450 5.47 0.27 ------- estimated at $3.2 million; this figure equals $0,005 per metric ton of waste and $0,013 per metric ton of product. For state- and other Federal-induced annualized costs (NPDES permit granted), the estimate is $69,000; this figure equals $0.0001 per metric ton of waste and $0.0003 per metric ton of product. For Criteria-induced annualized costs (NPDES permit granted), the estimate is $114 million; this figure equals $0.18 per metric ton of waste and $0.47 per metric ton of product. c, Cost Methodology (1) Capital Costs National baseline and above-baseline capital costs for each mining industry were based on the size of the model plant and the control methods chosen to meet the RCRA criteria. Unit costs were determined for components of control methods that are current or baseline and those that are above baseline to provide compliance with RCRA. The baseline and above- baseline control method component costs were subsequently calculated for the model plants. The sum of the control costs to meet a criterion for a model Plant was then calculated, as applicable, for tailings and mine wastes. These costs were determined for each of the six criteria for each model plant. When one control strategy satisfied two criteria, such as surface water and ground water, the costs for the strategy were divided equally between them. In each industry, the baseline costs to meet all criteria were determined from the product of the number of model plants and the sum of the model plant control costs. The total baseline costs per criterion were determined from the product of the number of model plants in the industry and the model plant cost of meeting that criterion. The individual industry criterion costs were summed to get the total mining industry criterion costs. The criterion costs were used to develop the baseline and above-baseline costs by state. The number of model plants in each state by industry and 31 ------- by type of waste (tailings and mine wastes) were determined by proportioning total tailings and mine waste quantities among the states, based on industry production figures For each state, the cost increment was determined from the product of number of model plants per industry and the model plant control costs for a criterion. The sum of these incremental costs for all industries within a particular state is that state's total industry cost to meet one RCRA criterion. The sum of these costs for all states in the United States is the national mining industry's cost to meet a criterion; and the sum of these costs for all criteria is the national cost impact on the mining industry of meeting RCRA-level controls for nonhazardous wastes. A contingency factor of 20 percent is included with the capital costs shown in the tables. Costs of RCRA-level controls were calculated by state to determine the total state-induced costs. Control costs in each state having regulations equivalent to the RCRA criteria were added together, then deducted from the national total costs of RCRA-level controls. The matrix shown in another appendix (Economic Impact Analysis) to this document lists the states that have regulations equivalent to RCRA criteria. Other Federal-induced costs (in Table 2, and included in above-baseline costs In Tables 4 and 5) are those attributable to the Clean Water Act. They represent the controls installed to meet the surface water and wetlands criteria (NPDES permit denied) in the states that do not have equivalent regulations. State and other Federal-induced costs are combined and deducted from the costs of meeting RCRA-level controls to yield the actual Criteria-induced cost. (2) flnnuaTized Capital Costs and Trust Funds Annualized capital costs were determined for each industry by » *• ¦ 4.U ,.anitsl at 12 percent interest over the remaining life of the amortizing the capital at i<- model plant. The equation for determining the annuity or capital recovery factor is: LLP + i )nl , [(i + in - l] 32 ------- where i is the interest rate and n is the number of years. Annuity factors for the main industries considered in this study are shown in Table 6. TABLE 6 ANNUITY FACTORS FOR MAJOR MINING INDUSTRIES WITH NONHAZARDOUS WASTES Industry Assumed remaining life of model plant (years)* Annuity factor Copper, gold 15 0.1468 Iron ore 20 0.1339 Molybdenum 30 0.1241 Lead/zinc, phosphate 10 0.1770 Clay, stone 7.5 0.2096 Sand and gravel 5 0.2774 * These remaining lives are assumed to be half of the full lives. Another annualized capital cost is the establishment of trust funds to pay for the closure of tailings ponds at the end of a mining operation and the operation and maintenance of monitoring wells after closure. A closure period of 1 year was assumed for nonhazardous tailings ponds (dewatering, adding soil, and revegetating). The trust fund for the monitoring wells is based on the assumption that they will be operated and maintained for 5 years after closure. Equations were derived to determine the trust funds for closure and for the monitoring wells (Table 7). The equations take into account variations in remaining life among the model plants, and they include a 2 percent return (above inflation) on capital. In the equations, T is the capital cost of the trust fund; and S is the cost of closure and of well operation and maintenance for 1 year. 33 ------- TABLE 7 EQUATION FOR TRUST FUNDS Industry Tailings pond closure Monitoring well upkeep Iron ore T = 3.202 S Lead/zinc, phosphate T = 3.903 S Clay, stone T = 0.853 S T = 4.101 S Sand and gravel T = 0.897 S T = 4.309 S (3) Other Annual Costs In addition to annualized capital costs, the other annual costs include maintenance of the various control systems (assumed to be 5 percent of the applicable total capital costs); electricity to operate pumps, as during pond dewatering (assumed to cost 30 mills/kWh); labor to operate equipment, such as the front-end loader, is costed at $26.60 per man-hour, including supervision and overhead; trucking of tailings and mine wastes from wetlands when NPDES permits are denied (assumed to be done by a contractor); and annual costs of continuous overburden grading, soil spreading, and revegetating, (also assumed to be done by a contractor). d. Configuration and Costs of Control Methods The flow diagrams (Figures 1 through 9) and "tree" diagrams (Figures 10 through 15) in Sections 1 and 2 presented the different baseline controls and those that would meet RCRA criteria, respectively. This section discusses design parameters and components of the control methods. Unit costs are listed, where appropriate, in parentheses. (1) Tailings Pond The tailings pond is the principal method used to control mining beneficiation wastes. Most mines have tailings ponds; some, such as gold placer mines, discharge their waste sluicing water elsewhere. To 34 ------- determine the cost of constructing a tailings pond for nonhazardous beneficia- tion wastes, this study assumed the following design parameters: rectangular- shaped pond; depth of about 11 meters from the top of the dike to the bottom of the pond; dike around three sides of the pond (assuming a natural barrier on one side); and a slope of 2:1 (horizontal:vertical) except in floodplains or wetlands, where dikes are sloped 3:1. The dikes are constructed to have a 6-meter wide horizontal section along the top so that machinery can be driven and maneuvered there. Ponds are designed with a 1.5 meter freeboard above the water and an allowance of 1.2 meters of free water above the settled solids. Incoming slurry is assumed to be 30 percent solids, by weight; and settled tailings are assumed to be 65 percent solids, with an average specific gravity of 1.8. The excavated depth of a pond is based on the amount of material needed to construct the dike. The length to width ratio of the pond is 2:1. With the exception of the sand and gravel industry, it is assumed that one pond will accomodate the beneficiation (tailings) wastes from the other subject mineral industries over the entire life of each model plant. Sand and gravel operations typically construct a small settling pond at the start- up of a mine to receive beneficiation wastes during the initial two or three years of operation; with subsequent employment of one or more excavated areas from the mining operation for this purpose; consequently, baseline control costs for tailings from the sand and gravel industry are based on this configuration, i.e., construction of a 3-year settling pond and operation and maintenance of this pond and the ponds created by the mining operation over the life of the mine. In a case where a new pond must be built (e.g., gold placer mining) the cost is calculated for a capacity adequate to handle tailings for half the duration of a mine life; it is assumed that the mines are halfway through their useful lives. For both baseline case ponds and new ponds, assumptions about the annual quantities of tailings received were shown in Table 1. The capital cost of constructing a tailings pond includes the following components: land (rural undeveloped, $2,400 per hectare); land clearing ($1,300 per hectare); survey ($925 per hectare); excavation of pond area 35 ------- ($0.47 per cubic meter); hauling and dumping overburden at the dike area ($0.47 per cubic meter); dike formation and compaction ($1.88 per cubic meter); and fine grading ($0.69 per square meter). (2) Ground Mater Evaluation This evaluation is the determination of the water table level. The main costs are for drilling temporary test wells,; which in this study are assumed to be 6.35 centimeters in diameter. The cost of a 15-meter-deep well is $475, and each linear meter exceeding that depth is $25. (3) Site Evaluation A detailed site evaluation includes a hydrogeological survey to determine ground-water movement and flow nets ($5,000), and tests of borings to determine Teachability and permeability ($3,000). Capital costs of such an evaluation, including engineering appraisal and a report, is estimated at $15,000. (4) Leachate Collection System The system considered here is a group of collection wells spaced at a density of one per hectare. Each well is equipped with piping and a pump located above ground level. The wells collect the leachate and pump it back to the tailings pond. Cost of a well, with pump and piping, is estimated at $4,500. (5) Monitoring Wells The monitoring wells are costed according to depth. The wells include casing 10 centimeters in diameter, schedule 40 piping 3.8 centimeters in diameter, and pumps rated at 5,700 liters per hour. The installed cost of a 15-meter deep monitoring well is estimated at $3,000; and a 30-meter-deep well, at $4,000. 36 ------- (6) Diversion Ditches Cost of construction of diversion ditches (1.8 meters deep by 0.6 meters wide at the top) with a trencher is approximately $2.10 per linear meter. (7) Dike Formation, Soil Coverage, Revegetation Dikes are the principal control method used in this study for protecting overburden in floodplains. They are also part of the construction of a tailings pond, when no natural barriers are available. In this study, tailings pond costs normally include dikes with 2:1 slopes (which are assumed to exist at all baseline case ponds). Costs of dikes for new ponds are attributable to RCRA, as are the costs of new dikes (3:1 slopes) around overburden in floodplains, and for modifying existing pond dikes in wetlands and floodplains to 3:1 slopes. Unit construction costs used for dike construction and compaction were: $1.26 per cubic meter of dike material to build a floodplain dike around mine wastes (3:1 slopes, 3 meters high, constructed of overburden); and $1.88 per cubic meter to build a tailings pond dike (2:1 slope). The unit cost of dike formation for tailings ponds is based on the baseline case, which includes the cost of fine grading the dike. Additional costs of $0.51 per cubic meter of dike material are needed to modify pond dikes in floodplains from a 2:1 to a 3:1 slope. These costs are for loading trucks and hauling overburden from the piles to the dike areas. Additional costs of $0.47 per cubic meter are needed for new tailings pond dikes not in floodplain areas. These costs are for hauling and dumping the excavated portion of the pond to the dike area. The revegetation costs for dikes or for closing tailings ponds and mine waste piles include the cost of fill soil, top soil, seeding, and fertilizing. It was assumed that all of the soil would have to be purchased. When mine wastes are revegetated as an ongoing procedure (e.g., in the Florida phosphate 37 ------- industry), it is assumed that usable soil material could be segregated during mining operations so that only 50 percent of the soil would need 'to be purchased. Unit costs of soils and revegetation used in this study are as follows: purchased fill soil (0.45 meters thick) is $3.40 per cubic meter delivered to dike areas, and $23,500 per hectare delivered to overburden piles and tailings ponds for closure; purchased top soil (0.15 meters thick) is $4.12 per cubic meter delivered to dike areas, and $8,800 per hectare delivered to the site for closure purposes. The surface areas used to determine costs, by industry, are shown in Table 8. Where only the outer slope and horizontal portion of the dike are covered with fill soil and top soil, costs of spreading and compacting the two soils are $1.26 and $1.53 per cubic meter, respectively. The costs increase by fifty percent if both slopes (as on floodplain dikes) are covered with soil. Fine grading of the soil on dikes is costed at $0.69 per square meter. Revegetating, including seed and fertilizer, is costed at $2,500 per hectare. This revegetation cost applies to dikes and the closure of tailings and mine wastes. (8) Waste Transportation If NPDES permits are not granted to mines in wetlands, costs must be included for transporting newly generated mining wastes out of those areas. Capital costs include purchasing a front-end loader to load the newly generated mine waste from the piles onto 30-ton trucks. If the front-end loader is used full time for 8 hours a day, 5 days a week, 50 weeks a year, the cost of the equipment per hour is estimated at $52. Trucking of the waste from the mine site to the disposal facility is assumed to be done by a contractor, which makes it an operating cost. The unit cost of trucking is $1.05 per metric ton of waste, including fuel and labor and based on a round trip of 32 kilometers. This distance was assumed for all mines in wetlands except the Florida phosphate industry, which is located in extensive wetlands 38 ------- TABLE 8 SURFACE AREAS OF NONHAZARDOUS MINING WASTES BY INDUSTRY MODEL PLANT Industry Full 1 i fe* Mine wastes (hectares) Tailings pond (hectares) Copper 716 NA+ Iron 355 NA Molybdenum 5.28 NA Gold 153 0.5§ Lead/zinc 7.73 NA Phosphate 171 NA Clay 1.67 2.3 Stone 1.42 Negligible Sand and Gravel Negligible 0.8 Urani urn NA NA * For model plant half life, values are half the number shown. + Not applicable; wastes are considered hazardous. § Only tailings wastes from mining of placer deposits. 39 ------- areas. A distance of 64 kilometers was assumed there, bringing the unit cost of trucking to an estimated $1.96 per metric ton of waste. Other operating costs include labor and fuel to operate the front-end loader. Direct labor plus overhead is estimated at $26.60 per man-hour, and fuel at $6.00 per hour per loader (38 liters of fuel per hour at $0.16 a liter). The capital costs of transporting tailings wastes include such major items as purchase of a centrifuge (to concentrate the slurry from 30 percent solids to 70 percent solids); a slurry feed pump plus spare; sludge conveying system/hopper; and recycle water tanks. The sum of these items for the clay industry model plant, for example, is about $205,000. (9) Dewatering Tailings Pond for Closure In this study, dewatering consists of pumping the free water off the tailings pond and allowing the retained surface water to drain until the ground is stable enough for machinery to work on it. The costs include pumping the water from the pond surface and purchase of a fine-mesh, backwash filter to remove suspended solids. The capital cost of the filtering unit, with pumps and piping, is $25,000. The main operating cost is for electricity (30 mills per kilowatthour) to run the centrifugal feed and backwash pumps. 40 ------- REFERENCES 1. U.S. Bureau of Mines. Minerals yearbook 7974. v. 1. Metals, minerals and fuels. U.S. Department of the Interior, 1976. ' 2. PEDCo Environmental, Inc. Study of adverse effects of solid wastes from all mining activities on the environment. U.S. Environmental Protection Agency. Contract Number 68-01-4700. Cincinnati, 1979. 303 p. 3. U.S. Bureau of Mines. Mineral commodity summaries 1978. U.S. Department of the Interior, 1978. 200 p. 4. U.S. Bureau of Mines. Mineral facts and problems. Bulletin 667. U.S. Department of the Interior, 1975. 1,266 p. 5. Richardson Engineering Services, Inc. The Richardson rapid system. 1978-79 ed. v. 1, 3, 4. Solano Beach, Calif., 1978. 6. Robert Snow Means Company, Inc. Building construction cost data, 1978. Duxbury, Mass., 1977. 7. U.S. Environmental Protection Agency. Assessment of industrial hazardous waste practices in the metal smelting and refining industry. SW-145c. 2. Washington, D.C., 1977. 8. Midwest Research Institute. A study of waste generation, treatment and disposal in the metals mining industry. PB-261052. Environmental Protection Agency, Washington, D.C., October 1976. 41 ------- |