United States Region 4 Environmental Protection 345 Courtland Street, NE Agency Atlanta GA 30308 November 1980 904/9-80-062 &EPA Chemical Fire At Drexel Chemical Company Memphis, Tennessee ------- PREFACE This report reflects the activities of the Environ- mental Emergency Branch (EEB) Region IV, EPA, as it was concerned with the captioned event. The report outlines the key actions of the Federal On-Scene Coordinator, the Regional Response Team (RRT), and state, local, and Federal members of the RRT. It reflects the complexity of respond- ing to environmental emergencies and the need to coordinate and plan in advance for a major incident such as this event. This report is intended to satisfy the requirements of the National Oil and Hazardous Substances Pollution contin- gency Plan and to help others learn from our experiences. Environmental Emergency Branch library/region n r-kunonMWlFNTAL PROTECTION agency ------- TABLE OF CONTENTS SECTION PAGE 1. SUMMARY 1-1 2. THE SITUATION 2-1 3. PHOTOGRAPHS 3-1 4. SUPPORTING MATERIAL 4-1 ------- 1. SUMMARY At 9:15 a.m. on July 5, 1979, an explosion and fire occurred at the Drexel Chemical Company, Memphis, Tennessee, which resulted in the evacuation of numerous individuals along the path of the billowing smoke. The presence of Class B poisons created the possibility of significant public health and environmental impact. Local officials evacuated the threatened areas while fire officials utilized minimum amounts of water in an effort to contain the blaze to the production plant. Despite these efforts, large amounts of contaminated water ran from the plant site to a nearby drainage culvert, Mai lory Bayou, which flowed to Nonconnah Creek and into McKellar Lake. City officials acted quickly to dam the drainage at Horn Lake Road, thus containing the contaminated water. Local contacts indicated that no air monitor- ing took place during the initial fire. When EPA arrived on-scene the air pollution problem was essen- tially over, but several other situations had developed. Large amounts of vapor had precipitated out of the dense smoke and left large yellow droplets along its path. The plant itself was a complete loss and presented a special cleanup problem because of the Class B poisons. The contaminated water was contained at Horn Lake Road, but was already in large quantities. The containment area was a flood- plain for drainage from the South Memphis area, which made isolation of the contaminated water virtually impossible. 1-1 ------- A Regional Response Team (RRT) meeting was held and potential problem areas were discussed. Nearly every local agency was repre- sented along with selected state and federal agencies. Task assign- ments were made as follows: FDA - commercial products Health Department - residential areas Poison Control Center - human exposure EPA and State of Tennessee - plant site and contaminated water Human exposure and chemical fallout were found to be minimal. Plant site cleanup presented difficult solid waste questions concern- ing neutralization and ultimate disposal. Tennessee Solid Waste Control worked closely with the company to minimize disposal costs. During the initial operation, the company seriously considered bank- ruptcy versus committing to substantial cleanup costs that seemed open-ended at the time. This was outweighed by the company's desire to clean up their "mess" and continue in business. Disposal of contaminated water presented a special problem. Sam- ple analysis showed low levels of poisons but bioassay work indicated the water was very toxic to aquatic life. The volume and concentra- tion of the water made carbon filtration cost-prohibitive, but dis- charge to McKellar Lake was equally undesirable because surrounding communities used it for water sports and fishing. The solution was limited treatment through the Sewage Treatment Plant (STP) and subse- quent discharge into the Mississippi River. This proved to be an acceptable method and resulted in the disposal of an estimated 14 million gallons of contaminated water. Cleanup of the plant site lasted about three weeks using a com- mercial contractor, and company officials seemed pleased with the results. The company also entered into a cooperative effort with the Poison Control Center to investigate degree and effects of fallout on soil and vegetation. The work was funded by Drexel Chemical and conducted by the Poison Control Center and a local university. Chemical/Physical Characteristics ¦Drexel Chemical was predominantly a formulation plant for various pesticide and herbicide mixtures used in agricultural applications 1-2 ------- with very little chemical reaction. The company handled three Class B poisons: Methyl Parathion, EPN, and DNBP (Dinoseb). Other chemicals in inventory presented a reduced concern when compared to the poisons. Some surfactants, emulsifiers, etc., were present, which may have added significantly to the toxic effects on aquatic organisms but were not felt to be toxic in general. Documentation of Significant Events Initial concerns centered on the possible air pollution problems resulting from the heavy smoke at the plant site. The smoke traveled in a southwesterly direction, crossing the Mississippi River into Arkansas over open fields and residential and industrial areas. Evac- uation had minimized human exposure, but officials were faced with determining a safe time for people to return home. Jim Littell of EPA Air Monitoring checked the downwind area late in the evening of July 5, and determined that any remaining air pollution threat would exist only around the immediate area of the plant site. Protection of human health became the first priority in this incident. At the RRT meeting, an effort was made to determine all of the potential health hazards resulting from the fire. Task assign- ments were given to various groups and this information was distri- buted to the news media by means of a press conference directly after the RRT meeting. Agency names, functions, and phone numbers were distributed to enable citizens to contact them directly. Information about decontamination of household and outdoor items was also distri- buted to the press after being discussed by EPA, State, Health Depart- ment, and Poison Control Center officials. Drexel Chemical officials looked to EPA and state personnel for guidance on the necessary cleanup procedures. Initial speculation on disposal costs caused the company to seriously consider whether it should even begin cleanup operations if, in fact, they were going to "break" the company. Lawyers and insurance agents advised company officials against entering into an open-ended effort. The OSC worked with the company and state officials for one and one-half days to 1-3 ------- devise a cleanup plan that was environmentally sound yet within reason on cost. This effort allowed the company to clean up its problem instead of laying the burden on the taxpayer. Water decontamination posed one of the most serious problems. The water was in a floodplain and could not be isolated. Until signi- ficant cleanup occurred at the plant site, additional chemical runoff and large volumes of water would collect in the holding basin. Acti- vated carbon filtration was considered, but estimates indicated that it could run as high as $500,000 to filter what appeared to be low- concentration contaminated water. This did not seem reasonable if an alternative could be found. Neutralization was tried using caustic materials but it was not felt the water would be suitable for dis- charge to McKellar Lake afterward. Discharge to the lake was undesir- able because of its use for water sports and fishing, and also because limited flow through the lake would not permit dilution and disper- sion. These factors led to the decision to pump the waste through the STP for limited treatment and discharge into the Mississippi River where its toxic effects, if any, would be minimal. The logistics of pumping all of the liquid to the STP proved to be difficult because the plant was able to handle only a limited amount (l%-5%) by volume without affecting the bacteria. At these pump rates, it would have taken an estimated two weeks to empty the pond. Any rainfall would significantly extend that period of time. Finally, the decision was made by the 0SC and state to bypass the treatment at the STP and pump as much contaminated water as possible. This method posed a second problem: availability of large-volume pumps because most were tied up irrigating crops. The city of Memphis assisted by loaning a 10-inch pump from the STP. This proved invalu- able in eliminating the contaminated water and allowing the drainage canal to be reopened. 1-4 ------- 2. THE SITUATION Response and Observations: Chronological Events July 5, 1979 An explosion and fire occurred at the Drexel Chemical Company, Memphis, Tennessee, at 9:15 a.m. At 4:00 p.m., Jan Rogers, who had been designated On-Scene Coordinator, arrived and was briefed on the situation. The initial fire caused significant air pollution concerns. SSW winds blew the smoke across the Mississippi River and into Arkansas. The river was closed to vessel traffic until 3:00 p.m. Civil Defense had evacuated the area along the path of the smoke as a precaution. The U.S. Coast Guard (USCG) contacted Ergon, Inc., and requested that they put a boom across Nonconnah Creek to contain any floatable pollu- tant runoff from the plant site. The OSC, USCG, Civil Defense, and Ergon surveyed the plant site, drainage ditches, and Nonconnah Creek to McKellar Lake. There was still some fire in the building but the dense smoke had cleared. Firemen were using minimal water to contain and extinguish. There were large amounts of contaminated runoff from firefighting and broken water lines. An earthen dam was containing contaminated water at Horn Lake Road. The boom on Nonconnah Creek was not collecting any pollu- tant . 2-1 ------- At 6:00 p.m., the OSC met with Drexel Chemical Company President Robert Shockey and learned that the highly toxic chemicals involved were Methyl Parathion, EPN, and DNBP. It had been determined that an explosion in the "Hot Room," where the poisons were stored, had caused the fire. The cause of the explosion was not known. Most of the chemicals in the building were in liquid form. It had been recom- mended to Drexel that contaminated runoff be treated with caustic to neutralize the poisons. Chemical representatives believed that in a hot fire 95% of the chemicals would be destroyed. A dam had been installed by city per- sonnel at Horn Lake Road to contain the contaminated runoff. Shelby County Health Department officials were sampling Nonconnah Creek to determine the extent of pollution below the containment dam. By 6:00 p.m., evacuated residents had been allowed to return to their homes. The industrial area south-southwest of the plant was still evacuated. Mr. Shockey agreed to provide a list of the inventory of the building. Jim Littell and James Bricker of EPA Air Monitoring arrived at 6:30 p.m. and looked over the situation. EPA Emergency Response Team (ERT) and Region VI personnel arrived on-scene and met with the OSC and Mr. Littell and Mr. Bricker to discuss the incident. A Regional Response Team (RRT) meeting was scheduled for July 6. The OSC toured the plant, containment, and creek areas. The company sampled behind the containment dam. July 6, 1979 The Command Post was set up at the Drexel Chemical office. The OSC contacted Jack Stonebraker, EPA in Atlanta, and briefed him on the situation. The OSC requested that he contact EPA solid waste person- nel and relay the potential disposal problem. The OSC surveyed the drainage ditch and Nonconnah Creek. The dam was holding all contaminated runoff in the drainage ditch. Nonconnah Creek had very low flow and there was no visual indication of the chemical reaching the mouth of McKellar Lake. At the plant site, the fire department was hosing the building. Sample results indicated low levels of contaminants. The OSC obtained the inventory list from Mike Smith, the vice president of Drexel. 2-2 ------- The RRT meeting was held at 10:00 a.m. The OSC advised the group of sample results and the status of the situation. The fire depart- ment was preparing to bulldoze part of the building to permit fumes to escape and limit the amount of water needed for smoldering areas. The air pollution problem was discussed. Concern was expressed about fuming in the plant. It was decided to advise that the trucking com- pany keep personnel in the building and out of the section of the yard downwind of the fire. It was felt that the air dispersion problem downwind did not present a real danger. Contamination of cars, gardens, homes, lawns, etc., was dis- cussed. The Shelby County Health Department was given the assignment to check on private facilities and FDA would check commercial facili- ties. A statement was to be released that would advise on procedures for decontaminating household and outdoor items. Since some contaminated runoff may have reached McKellar Lake, the Health Department preferred to continue the restriction on water- contact use of McKellar Lake until further analysis could be done. The fire department was advised on how to decontaminate their hoses by washing with soda ash and rinsing with clean water. The Health Department would do sample analysis on the commercial list if the need arose. It was decided that each agency representative would discuss his agency's area of expertise with the press. The meeting with the press took place at 11:45 a.m. The OSC visited the plant site at 12:30 p.m. Contaminated water was still running from the plant site. The OSC instructed Mr. Shockey to block all drainage from the plant site and attempt to shut off all sources of water to the building. All fire was out. There was sub- stantial flow in the drainage ditch. The company would develop a plant sketch showing where material was stored. The OSC contacted Ergon to remove the boom from Nonconnah Creek. ' Jack Stonebraker relayed the information that the EPA pesticides lab in Bay St. Louis, Missouri, would do chemical analysis over the weekend if needed. An estimated 25-30,000 pounds of soda ash had been added to the runoff at various points to neutralize the chemicals. 2-3 ------- Ben White of the Health Department called to report that his people had not found any significant problems of chemical fallout or fly ash in their visual inspection of residential areas. Reports from the TVA power plant indicated that the cloud had traveled north and west of the facility. The OSC and John Gilbert, EPA ERT, visited the plant site and found that the company was starting to move undamaged drums from the plant and was spraying with caustic to decontaminate. Mr. Cherry of TVA called and reported that he had taken samples on July 5 and 6. July 7, 1979 At the plant, the city would reinforce the dam at Horn Lake with stone and asphalt at the state's request. The state estimated that there were two million gallons of contaminated water at the Horn Lake dam. The Horn Lake area is a floodplain and there was no way to con- trol continued water collection. It was not considered feasible for the treatment plan to stay ahead of water accumulation. The approach to be used at the pond was to aerate to oxidize chemicals, neutralize to pH 9, check for 1 ppm levels on Class B poisons, allow water to build to dilution-level, and discharge several batches or one large batch. An RRT meeting was held at 10:15 a.m. Health Department person- nel had found minor amounts of charred material or yellow spots on vegetation. Fallout was considered minimal. There were no reports of illness, but the contractor working around the levee reported that some of his personnel were sick. FDA checked the trucking companies and stated that sealed trucks or cars should not have been damaged. The state presented results from samples taken July 5. Samples were taken at the plant and at the Horn Lake Road dam and sent to Bay St. Louis. Mike Higgs of Tennessee Water Quality Control called with the results of bioassay work. He felt that toxicity tests looked bad and that caution should be used regarding the release of contaminated water. 2-4 ------- The OSC met with representatives of Drexel and OH Materials to discuss how to approach treatment. The OSC briefed A1 Smith, EPA Region IV Environmental Emergency Branch Chief. The OSC also talked with Waynon Johnson, Department of Interior, Fish and Wildlife Division, who felt that bioassay work would be beneficial because it would show how the contaminated water affected the ecosystem. July 8, 1979 Pond pH 9.4-9.5, Bioassay 1 a.m.-8 a.m. 10% and 5% dead. The OSC visited the plant and talked with OH Materials and the company. The company had committed OH Materials to handling the contaminated water problem. They were considering cleaning up the plant themselves. The OSC informed the company that this was their option within limits but that cleaning up contaminated rubble would involve far more exertion and danger than normal work in the plant and some employees would probably rather quit. The OSC talked to Waynon Johnson, who said that toxicity was probably due to surfactants, alcohols, emulsifiers, etc., since sample analysis had shown only small quantities of chemicals. At 12:50 p.m., George Sand of the Bay St. Louis lab reported a rough analysis: In the sample behind the dam: Methyl parathion Atrazine EPN DNBP 0.1 ppm 0.6 ppm Non-detected Non-detected Samples from the drainage culvert at the plant site: Methyl parathion Atrazine EPN DNBP Heavy Concentrations 2-5 ------- A meeting was held with the company. Terry Cothron of Tennessee Water Quality Control outlined four alternatives for moving the water as follows: Put it in holding pond and wait. This would buy time but do nothing. Leave material where it was and explore alternatives. Put material in sewer. Do nothing. At 5:45 p.m., George Sand reported the following: Dam Sample: Methyl parathion 0.07 ppm Atrazine 0.61 ppm EPN 0 ppm DNBP (Dinoseb) 0 ppm Ditch Sample: Methyl parathion 1.0 ppm Atrazine 101.5 ppm EPN 0.41 ppm DNBP 0 ppm The bioassay unit arrived on-scene and was moved to the Nonconnah pump station. The 0SC met with company officials. They had talked with OH Materials and were concerned with the costs. Lawyers and insurance personnel advised the company against committing to an open-ended cleanup; they would prefer to let the government clean up the site. The company wanted to stay in business and was concerned with its reputation. Company spokesmen said that they would like to clean up the site if it were economically feasible. Representatives from OH Materials stated that they would be ready to aerate the pond on July 9. The 0SC discussed with Drexel the approach to cleaning up the plant site. 2-6 ------- July 9, 1979 The OSC met with: Maynard Stiles - City of Memphis Public Works Dr. John Smith - City of Memphis Public Works Terry Cothron - Tennessee Water Quality Control Wayne Max - Tennessee Water Quality Control John Gilbert - EPA ERT Alternatives for moving the water and other factors involved in the cleanup were discussed. At the Horn Lake Road dam: OH Materials was moving pumps into place. OH Materials was clearing dirt from the top of the dam, which completely shut off the culvert and would prevent overflow in case of a flood. City personnel requested that it be left that way and they would break the dam if necessary. More vegetation appeared to be dying in the pond and along the edges. It was probably from the defoliants. Reporters were on-scene and interviewed the OSC. Harbor Patrol reported 30-40 fish dead at McKellar Lake. The OSC told Bob Shockey to make a commitment to OH Materials to start cleaning up the plant or he would take over and perform it as a federal project. Mr. Shockey expressed some reservations about cost but agreed to hire OH Materials. The OSC contacted EPA Region VI and briefed Dick Peckham on the possible use of the Sewage Treatment Plant (STP) to discharge contami- nated water to the Mississippi River. Mr. Peckham requested that he be notified before start-up. The OSC received sample results from Bay St. Louis: Pond (second look using acid extraction pH 2): DNBP - 0.67 ppm Ditch - 0 ppm 2-7 ------- At the dam site, OH Materials had two small pumps recirculating/ aerating water from the impoundment. A larger pump, 6 inches in diameter, was in place and would be started shortly. Recirculation was creating foaming, indicating the presence of surfactants, deter- gents, etc. OH Materials had additional equipment en route. The OSC talked with Bob Shockey and Mike Smith to discuss cleanup operations. Later, the company, state, and EPA met and discussed the following: By pumping into the sewer at 1% dilution, about 500,000 gallons would be pumped per day. Tests indicated this rate would not hurt the STP. Pumping into the sewer still looked to be the desirable method of disposal. The pumping would go on all night. The state would run a bioassay that night on circulated pond water and would run a new respiration rate on bacteria in the morning. Aerators were down at the STP. The pond was visited and found to be circulating well. Mr. Cothron discovered a small seepage under the dam but it was not posing a threat. OH Materials would pump all night. Two men would remain on-scene at the pond. The state would collect a bioassay sample at 8:30 p.m. and run it during the night. All three pumps were running. A line would be laid up the levee to the manhole the next day. Pumping was still causing foaming. OH Materials would begin cleanup of the plant site the next morning. At the plant, the company had diked off the plant along Pennsyl- vania Street and would flush out the ditch on the west side of the plant that night. 2-8 ------- July 10, 1979 At the dam site, water was being circulated. The OSC went to the bioassay unit and talked with state personnel. Samples had been taken the previous night at the dam, the middle of the pond, and at the culvert entrance to the pond. The midstream sample appeared more concentrated than the other two. Split samples went to the STP. The city would also run for pesticides. The state would take additional samples. At the plant site, work had been completed along the railroad track but there was still some discoloration in the ditch. There was very little flow in the ditch. The OSC talked to Terry Cothron: The weather would be good until Friday with the possibility of thundershowers. Pumping into the sewer would begin at a 1% dilution rate and bacteria would be monitored for effects. If none, it would be possible to increase the rate. Middle of the pond would be mixed with tailings due to a difference in concentration and toxicity. The STP would look at respiration rates every two hours to observe effect. The state, EPA, and the city gave approval for pumping into the STP. The state arranged to sample STP effluent while contaminated water was being pumped. Atrazine would be hydrolyzed by acid or base. Dr. Nunez of the mid-South Poison Control Center called and said that he was going to release a statement about the deaths of small animals in the immediate area of Drexel. He also asked if soil samples would be analyzed and was informed that there were no plans to do so at that time. LIBRARY/REGION IV U.S. ENVIRONMENTAL PROTECTION AGENCY 345 COURTLAND STREET, N.E. ATLAr!"'". ca 2-9 ------- At 10:30 a.m., John Gilbert told OH Materials to start pumping into the sewer at 380 gpm. There was a press conference at Maynard Stiles' office. The OSC, Terry Cothron, Mike Higgs, and Mr. Stiles participated. The press was briefed on the situation and informed of the decision to pump through the STP. Mr. Sand reported that the samples taken July 7 contained no chlorinated compounds. The pumping rate was increased to 400 gpm at 12:50 p.m. The state took an effluent sample at the STP. The OSC spoke with Larry Ledford of Tennessee Solid Waste Control and informed him that the company was ready to begin cleanup of the building and needed to establish a plan for each item based on his requirements for disposal. OH Materials shut down for the day at 5:30 p.m., except to finish the 6-inch pipe to the top of the levee. The company was going to clear an area that night so the contractor could begin decontamination operations in the morning. July 11, 1979 The OSC checked the dam area. The level was down approximately one inch. The OSC also checked the bioassay unit and found that 1% and 5% tests looked OK. The effluent leaving the STP was being di- luted 10 to 1 with TVA cooling water before entering the Mississippi River. At the plant site, the OSC, John Gilbert, Bob Shockey, and Larry Ledford discussed the disposal technique to be used on materials in- plant. OH Materials had started moving drums, tin, etc., but were progressing slowly. The fire department arson squad requested that the contractor work around the Hot Room while they inspected and sampled the area. Marlene Jones of the STP was reluctant to increase the flow, although 1% and 5% tests looked OK at the 8:00 p.m. test. She was requested to do tests up to 25% concentration to establish an upper limit that the plant might tolerate. Mike Higgs would discuss in- creasing the flow with Ms. Jones again. 2-10 ------- The state talked to the city about increasing the flow. They were being cautious and indicated that if the STP had to be bypassed, it would cut off the food supply to bacteria. Therefore, bypassing would have to be scheduled for a period of time, and then switched back to the STP for a few hours and continued in a cycle. At the pond area, the OSC told OH Materials to dike the Delta drainage ditch. Marlene Jones of the STP called and reported that higher forms of bacteria made up 15% of the mass. The plant would test every four hours starting at 6:00 p.m. when the 2% flow arrived at the plant. The lake would remain closed. Mr. Cothron would set up a schedule for possible STP bypass. In the evening, the OSC had OH Materials set the pumps and hoses to pump into the manhole on Horn Lake Road. The OSC also checked the Delta Refinery drainage to make sure the dam would have no adverse effects when the water backed up. It started to rain at 5:30 p.m. The city approved the plan to increase pumping without bypassing. Maximum volume, about 2,500 gpm, was being pumped into the sewer. Mike Smith asked what to do with concentrated water accumulation and was told to store it in tanks for the time being. Terry Cothron stated that it was not feasible to pump uncontami- nated water at the upper end of the pond over the levee. July 12, 1979 The rain stopped at 4:00 a.m. The level of the pond was up one foot. Nonconnah Creek water level was also up. The flow in the drainage ditch was about the same. State personnel arrived at 6:30 a.m. and stated that higher con- centrations should be pumped at the pump intake versus the upper end of the pond. The state would be running a bioassay on the water taken at the back of the pond. Bob Shockey told the contractor to move the Class B poisons. The OSC told Mike Smith to put additional contaminated water into a hold- ing tank. 2-11 ------- By 10:00 a.m., the pond level was approaching one inch below the zero-inch mark. At the STP, aeration was on, bacteria was showing minor effects, there was some color, no odor, some foaming. Samples were taken and respiration rates had been checked every 30 minutes the previous night. At 3:00 p.m., the pump hoses were adjusted and the pumping volume was 3,000 gpm. At 4:50 p.m., there was a message from the STP that the bacteria were dying. It was decided to pump maximum volume and bypass the STP. At 6:00 p.m., the STP began bypass until midnight. The flow was cut back to 1,000 gpm. Two 4-inch pumps were being used. Although called bypassing, the water was going through contact tanks, clarifiers, chlorine contact tanks, and discharge; no aeration tanks. Paul Christman of the STP suggested getting a 10-inch pump and loading the sewer with maximum pumping for full bypass of the STP and running in cycles until all the water was gone. Mr. Christman offered the use of the STP1s 10-inch pump if none other was available. July 13, 1979 The pond level continued to decrease. Ben White called. The 0SC and Terry Cothron discussed opening the lake. It was agreed that danger was remote at this time. Ben White saw samples with very low ppb range in McKellar Lake. He de- cided to open the lake with the suggestion that water-contact sports be avoided. He could close the lake quickly if heavy rains washed out the pond. The maximum pumping/bypass cycle began at 12:15 with all hoses in use. The schedule was 12 hours maximun pumping and 6 hours reduced to 1,000 gpm. At 1:00 p.m., George Sand called with the final sample results: Pond: Methyl parathion Atrazine 0.07 ppm 8.3 ppm EPN DNBP PNP 8.9 ppm 1.7 ppm 0 ppm 2-12 ------- Ditch: Methyl parathion Atrazine 1.0 ppm 101.5 ppm EPN DNBP PNP 0.41 ppm 25.3 ppm 7.1 ppm At 3:15 p.m., the STP's 10-inch pump arrived at the pond site. The OSC talked to Bob Shockey about solid waste disposal problem. At 8:00 p.m., the 10-inch pump was started. The pumping rate was estimated to be 5,000 gallons. At 11:00 p.m., the 10-inch pump was shut down. July 14, 1979 At the pond site, the contractor pumps were running. The 10-inch pump started at 7:45 a.m. Sewers were OK, there was no backing up or overflowing. The pond was dropping rapidly. Mr. Shockey said that he thought OH Materials was doing a good job. It was decided to run the STP 10 hours (6:00 p.m. - 4:00 a.m.) to build up bacteria, and then start pumping again between 4:00 a.m. and 4:00 p.m. At 6:00 p.m. at the pond site, the 10-inch pump was reworked. The flow was shut back to 1,000 gpm. The backhoe opened up drainage from low areas of the pond as water returned to the confines of the concrete culvert. Plans were made with the state to pump down liquid on July 15 and flush with dammed water and pump out. It was also planned to close the floodgates at Nonconnah pump station on July 16, break the dam, regrade the earth, and remove dirt from the ditch. The pump would be returned to the STP, and Ben White would be consulted on sampling McKellar Lake. 2-13 ------- July 15, 1979 Pumping at the pond started at 4:00 a.m., except for the 10-inch pump because it wouldn't prime. The pool would continue to be pumped down as much as possible. A fire hydrant would be used to flush the culvert to the floodgates. The dam would be broken and water allowed to flow to the floodgates. A backhoe would be used to uncover an 18-inch storm drain. At 4:30 p.m., the OSC contacted Paul Christman of the STP to inform him that the flow had been cut back to 1,000 gpm at 4:00 p.m. It was believed that another bypass would not be needed. The OSC informed Mr. Shockey and Mr. Smith that the pond area should be nearly drained by the next morning and pumping would be completed then. A small pool area not draining to the ditch was of concern because of concentration. The ditch area was fairly diluted. It was thought that the intake hose on the smaller pump would have to be moved to remove this. July 16, 1979 The pond area looked good and it was decided to send the 10-inch pump back to the STP. The floodgates at the pump station were closed. This would cause some accumulation, dilution, and slow discharge to Nonconnah Creek. A backhoe would be on-site the next morning to dig out the dam. Cleanup of the building was going well. Mr. Shockey and Mr. Smith were satisfied with the progress of the cleanup. July 17-18, 1979 The dam was broken on July 17. Some sediment remained, which caused the overflow dam to bleed material to the pump station. Nonconnah Creek was septic again. No yellow color effect from contaminated water was noticeable. Progress slowed at the plant site because of work in the Hot Room. No rain had occurred. There were no problems at McKellar Lake. 2-14 ------- 3. PHOTOGRAPHS 3-1 ------- CHEMICAL PLANT AFTER FIRE ------- CONTAMINATION ALONG RAILROAD TRACKS 3-3 ------- STORAGE AREA AFTER FIRE ------- CONTAMINATED RUNOFF WATER ------- CONTAINMENT AREA FOR CONTAMINATED WATER RUNOFF ------- CONTAINMENT AREA AFTER MOST OF THE WATER HAD BEEN DISPOSED OF ------- PUMPS USED TO MOVE CONTAMINATED WATER ------- PORTABLE BIOASSAY UNIT ------- CREWS REMOVING CONTAMINATED METAL FROM SITE ------- CREWS REMOVING CONTAINERS FOR RE-DRUMMING ------- ------- STATIC BIO ASSAY TESTING ------- 4. SUPPORTING MATERIAL 4-1 ------- ------- 1 2 3. 4 5 6 7 8 9 10 11 12 13 DREXEL CHEMICAL COMPANY MEMPHIS, TENNESSEE INVENTORY DNBP - Formulated as A1kanolamine Salt - 3 lb DNBP/gal 1,290 gal - Formulated in Xylene Large Solvent - 5 lb DNBP/gal 8,760 gal Paraffinic Oil plus Emulsifier 18,795 gal Maleic Hydrazide - Technical 90-98% 21,602 lb - Formulated as DEA Salt - 3 lb MH/gal ) - Formulated as K-Salt - 1.5 lb MH/gal )... 16,179 gal - Formulated as K-Salt - 2.25 lb MH/gal ) Fatty Alcohols (Cg + C^q) P^us Emulsifier 6.06 lb Alcohol/gal 10,024 gal Sulfur - 98% Manufacturers Grade 67,500 lb - Formulated as 6 lb/gal - packaged 12,735 gal - Formulated as 6 lb/gal - bulk tanks 13,000 gal - (May not have been released) Sodium Chlorate - 3 lb/gal with 1.5 lb Urea/gal 29,810 gal Hydrazine Hydrate - 54.4% Solution 1,144 gal Hydrated Lime 33,750 lb Maleic Anhydride Less than 40,000 lb - (Truck was being unloaded) Atrazine - Technical 95-98% 14,650 lb - Formulated 4 lb/gal 1,110 gal EPN 93% Technical 39,600 lb Methyl Parathion 80% Technical 39,600 lb Various Surfactants & Emulsifiers 85,717 lb 4-3 ------- INVENTORY Size No. Containers Total Dynamite 3 5 gal 258 1,290 gal Dynamite 5 30 gal 291 8,730 gal Dynamite 5 5 gal 6 30 gal Peptoil 4 x 1 gal 3,065 12,260 gal Sucker Stuff 4 x 1 gal 765 3,060 gal Peptoil 5 gal 1,307 6,535 gal Super Sucker Stuff 4 x 1 gal 1,453 5,812 gal Super Sucker Stuff 4 x 1 gal 248 992 gal Sucker Plucker 4 x 1 gal 2,506 10,024 gal Riverside Sulfur. 5 gal 210 1,050 gal Barber Sulfur 5 gal 99 495 gal Drexel Suffa 5 gal 1,650 8,250 gal Surfac 820 4 x 1 gal 1,520 6,080 gal Helena Sulfur 5 gal 588 2,940 gal Defol 55 gal 542 29,810 gal S.S. Stuff 4 x 1 gal 1,980 7,920 gal Atlox 804 4,522 4,522 lb Anti Foam 3,279 3,279 lb Clay 50 lb 23 1,150 lb CR273C Acid 100 lb 14 1,400 lb DOWCIL 100 lb 13 1,300 lb Hydrazide Solution 440 lb 26 11,400 lb Kelzan 300 lb 21 6,300 lb LS-300 16,039 16,039 lb Lime 50 lb 675 33,700 lb Lomar 50 lb 240 12,000 lb LO 529 450 lb 34 15,300 lb Maleic Hydrazide 44 lb 320 14,080 lb PVP 30 100 lb 35 3,500 lb Maleic Anhydrazide 50 lb 50 2,500 lb Drexel H.H. Tech 7,522 7,522 lb Paraformaldehyde 50 lb 40 2,000 lb Petro-D-425 60 lb 71 4,260 lb PolyFon 0 50 lb 55 2,750 lb Sulfur 50 lb 1,350 67,500 lb Soda Ash 640 640 lb Urea 100 lb/bag 138,037 13,803,700 lb Unico Atrazine 100 lb 222 22,200 lb Super P-150 10,367 Super Sucker Stuff HC 10,656 EPN 93% Tech 550 lb/drum 72 39,600 lb Methyl Parathion Tech 00 o 550 lb/drum 72 39,600 lb Atrazine Tech 50 lb 293 14,650 lb 4-4 ------- Inventory - Pg. 2 The following containers were empty: Size No. Containers Super Sucker Stuff HC 4 X 1 804 Sucker Plucker 4 X 1 4,573 Super Sucker Stuff 4 X 1 389 Sucker Stuff 4 X 1 1,647 Peptoil 4 X 1 253 Surfac 820 4 X 1 2,232 Ansar 4 X 1 507 Unsleeved 4 X 1 1,671 Plain 2 X 2-1/2 1,944 5 Gal Pails (black) 1,214 5 Gal Plastic 126 5 Gal Open Head 7,533 5 Gal Old Open Head 798 5 Gal White Metal 59 New 55 Gal Drums 114 New 55 Gal Plastic 768 30 Gal Drums 469 Helena SMH 4 X 1 48 Plain 48 144 Black P/P Caps 14,200 2" Seals 4,396 PI ugs 9,000 2-1/2 Gal Caps 101,000 4x1 Gal Caps 254,380 Flex Spouts 15,665 4-5 ------- TELEGRAPHIC MESSAGE NAME Of AGENCY EPA, Region IV Atlanta, Georgia PRECEDENCE action* PRIORITY INFO: SECURITY CLASSIFICATION UNCLAS ACCOUNTNG CLASSIFICATION date prepared 07/09/79 TYPE OF MESSAGE 0 SINGLE ~ »OOK |~1 MULTIPLE-ADDRESS FOR INFORMATION CALL NAME John R. Moebes PHONE NUMBER (404)881-3973 THIS SPACE FOR USE OF COMMUNICATION UNIT MESSAGE TO 8E TRANSMITTED (Use doubU spacing and all capital Utters) TO: MAYNARD STILES, DIRECTOR DIVISION OF PUBLIC WORKS CITY OF MEMPHIS 125 NORTH MAIN MEMPHIS, TENNESSEE 38103 RE: MEMPHIS SOUTH WASTEWATER TREATMENT PLANT NPDES PERMIT NO. TN0020729 THE ON-SCENE COORDINATOR OF THE ENVIRONMENTAL EMERGENCY CAUSED BY THE FIRE AT THE DREXEL CHEMICAL COMPANY HAS REQUESTED THAT CONTAMINATED WATERS RESULTING FROM THAT FIRE BE PUMPED TO THE MEMPHIS SOUTH WASTEWATER TREATMENT PLANT. THE CITY HAS AGREED TO ACCEPT THAT CONTAMINATED WATER IF EPA AGREES NOT TO TAKE ACTION FOR VIOLATION OF THE SOUTH WASTEWATER TREATMENT PLANT NPDES PERMIT CAUSED BY THE CONTAMINATED WATER. EPA, IN CONSIDERATION OF THE EMERGENCY THAT EXISTS, AGREES NOT TO TAKE ACTION FOR ANY PERMIT VIOLATION CAUSED BY THE CONTAMINATED WATER BEING PUMPED TO THE SOUTH WASTEWATER TREATMENT PLANT. SANFORDyW. HARVEY,UR.V) DATE SIGNED: DIRECTOR, ENFORCEMENT DIVISION EPA, REGION IV PAGE NO. NO. OF PCS. SECURITY CLASSIFICATION UNCLAS {STANDARD FORM 14 tfVISCO AUGUST 1967 QSA PPia (41 CFR) 101-15.306 6U.S. OowrniMnt Prhitlne Offie*: 197ft— 2G1-447/344S 14-102 4-6 ------- UNITED STATES ENVIRONMENTAL PROTECTION AGENCY DATE. July 16, 1979 SUBJECT. FROM TO The Analysis of Water Samples Taken at the Drexel Chemical Co., Memphis, Tennessee After the Explosion and Fire George J. Sand Pesticides Monitoring NSTL Station, MS 39529 Mr. Jan Rogers, Enforcement Division Hazardous Materials Section, Region IV Federal On-scene Coordinator Thru: Dr. Han Tai 7^, The water samples that were taken at the Drexel Chemical Company on July 7, 1979, and delivered to our laboratory by the U.S. Coast Guard, have been analyzed for pesticides, herbicides, and toxic chemicals. The analytical results are listed as follows: Analytical Results of Water Samples Taken at Drexel Chemical Company, Memphis, Tennessee Lab Acc. No. 9-73-018 9-73-019 Sample Site Above Earthen dam Methyl Parathion (ppm) 0.07 Drainage ditch 1.0 below plant, between RR bridge Atrazine (ppm) 8.3 101.5 EPN (ppm) ND 0.41 Dinoseb (DNBP) (PPm) 8.9 25.3 p-nitrophenol (ppm) 1.7 7.1 Note: ND - None detected Minimum Detectable Level Organophos Toxic Chem Dinoseb Atrazine .05 ppb 10 ppb 10 ppb .10 ppb Sample extraction and analysis by: Gerald Gardner Milas Blaylock Ray Shaw If you should have any questions about the above results, please contact us. We will store these water samples for a short period of time in the event that you may have need for these samples or may request some additional analysis. cc: Sam Wastler EPA Form 1320-6 (Rev. 3-76) 4-7 ------- UNITED STATES ENVIRONMENTAL PROTECTION AGENCY CINCINNATI, OHIO 45268 DATE: August 13, 1979 SUBJECT: Drexel Chemical Company FROM: John M. Gilbert Environmental Response Team TO: J. Stephen Dorrler, Leader Environmental Response Team 1. Place Visited: Memphis, Tennessee 2. Dates: July 5, 1979 through July 13, 1979 3. Facility Involved: Drexel Chemical Company 2487 Pennsylvania Street Memphis, Tennessee 38109 (901) 774-4370 4. Type of Spill: Explosion and fire at a pesticide plant 5. Products Involved: Methyl Parathion, DNBP, EPN, and Atrazine 6. OSC: Jan Rogers, Region IV 7. Remarks: This memo will be a brief summary of the incident. Jan and I are collectively writing a complete report on the incident. E&E will assist in printing the report when completed. SUMMARY On July 5, 1979 an explosion and fire completely destroyed the Drexel Chemical Company's manufacturing facility at 2487 Pennsylvania Street. Drexel produced a wide range of pesticides and herbicides. The explosion occured in the "hot room" where two class B poisons were stored. The class B poisons handled at the facility were: 1. Methyl Parathion 2. EPN 3. DNBP (not stored in the hot room) Runoff from the fire fighting effort flowed through a drainage ditch into Nonconnah Creek. Nonconnah Creek empties into McKellar Lake. During the fire the drainage ditch was dammed by the City Public Works, however, some runoff reach Nonconnah Creek prior to construction of the dam. 4-8 ------- Ifre company added soda ash, NaOH and KOH to the runoff water in order to hydrolize the methyl parathion, EPN, and DNBP. Soda ash was also added to Nonconnah Creek. Literature and experience indicated both methyl parathion, and EPN will hydrolize readily. DNBP is slower to hydrolize. When I arrived, around 1900, the fire was out and the runoff water con- tained. Jan had arrived around 1600 hours and had already talked to the company. Clean up fell into the following: 1. Plant site - contaminated metal, drums (full & empty) and standing water. 2. Contaminated runoff water The company engaged OH Materials to do the clean up. Plant Clean Up Due to the configuration of the facility it was impossible to contain all standing water at the plant. To contain as much as possible, the OSC had the company plug all storm sewers and construct earthen dikes around the facility. The drainage ditch running from the plant to Nonconnah Creek could not be contained close to the plant because the ditch handled runoff from the surrounding neighborhood in addition to the plant. The material at the plant was handled in the following manner: 1. Metal was decontaminated with an acid wash and hauled off by a metal reclaimer. 2. Contaminated water was pumped into the company's storage tanks. 3. Containers with product remaining in thera were emptied into drums. 4. Debris was hauled to a local landfill - permission given by Tennessee Solid Waste. Contaminated Water The dike constructed by the city where the drainage ditch goes under Horn Lake Road stopped all additional flow into Nonconnah Creek. The OSC had the dam reinforced to contain additional runoff from rainfall. The dam contained a large volumn of contaminated water that had to be disposed of. After close coordination with EPA, Tennessee Water Quality and the city of Memphis, the contaminated water was pumped into the South Sewage Treat- ment Plant. The effleunt from the STP flows into the Mississippi River. Initially, the pumping rate was such that a 5% solution was entering the plant. When it became evident that this rate would require the pumping for many weeks, the rate was pushed to full pumping capacity. This caused problems at STP and the plant's entire flow had to be bypassed. To keep the STP alive, the bypass was not in one shot, but staggered. When the 4-9 ------- piant went back on line the pumping rate of contaminated water was rfeduced to a level (5%) that the plant could handle. After sufficient time to stabilize the plant, the flow as upped and the plant bypassed. This continued until the contaminated pond was dry. TASK FORCE To evaluate the entire situation, the OSC held a meeting with all interested organizations. As a result of the meetings, the following was agreed upon: 1. FDA would handle contamination of commercial products. 2. Health Department would check gardens, yards, and public fishing. 3. Poison Center would handle all complaints about human effects. 4. EPA and State would handle the clean up. SAMPLE ANALYSIS The following samples were analyzed: Drexel - initial runoff samples EPA(Bay St. Louis) - runoff water samples State - runoff, Nonconnah Creek, bioassay, STP effluent OH - metal City - STP bugs, STP effluent The bioassay test was the first indicator on how toxic the runoff was and proved to be invaluable by providing quick (4 hour) results. The decision not to discharge the contaminated water into the Nonconnah Creek and the initial pumping rate was based on the bioassay results. After Jan and I left, the company and the Poison Control Center began a cooperative effort to investigate fall-out on soil and vegetation.- The work is being done by the Poison Control Center, a local university is doing the analysis, and Drexel is paying the'bill. cc: Jan Rogers 4-10 ------- |