EPA542-R-06-014
                                          June 2006
                                      www.epa.gov/tio
                               www.clu-in.org/optimization
REMEDIATION SYSTEM EVALUATION (RSE)
   AMERICAN CREOSOTE WORKS SITE
          PENSACOLA, FLORIDA
  Report of the Remediation System Evaluation

     Site Visit Conducted October 5, 2005
               Final Report
                June 2006

-------
                                       NOTICE
The U.S. Environmental Protection Agency (U.S. EPA) funded the work described herein and the
preparation of this document by GeoTrans, Inc. under EPA contract 68-C-02-092 to Dynamac
Corporation, Ada, Oklahoma. Mention of trade names or commercial products does not constitute
endorsement or recommendation for use.

-------
                               EXECUTIVE SUMMARY
A Remediation System Evaluation (RSE) involves a team of expert hydrogeologists and engineers,
independent of the site, conducting a third-party evaluation of site operations. It is a broad evaluation that
considers the goals of the remedy, site conceptual model, above-ground and subsurface performance, and
site exit strategy. The evaluation includes reviewing site documents, visiting the site for up to 1.5 days,
and compiling a report that includes recommendations to improve the system. Recommendations with
cost and cost savings estimates are provided in the following four categories:

    •    improvements in remedy effectiveness
    •    reductions in operation and maintenance costs
    •    technical improvements
        gaining site closeout

The recommendations are intended to help the site team (the responsible party and the regulators) identify
opportunities for improvements.  In many cases, further analysis of a recommendation, beyond that
provided in this report, may be needed prior to implementation of the recommendation. Note that the
recommendations are based on an independent evaluation by the RSE team, and represent the opinions of
the RSE team. These recommendations do not constitute requirements for future action, but rather are
provided for the consideration of all site stakeholders.

The American Creosote Works (ACW) site is located on 1800 Gimble Street on the abandoned American
Creosote Works wood preserving plant in Pensacola, Florida. The site is approximately 18  acres in area.
The site is about 600 yards north of Pensacola Bay and Bayou Chico. The site soil and ground water have
been impacted with volatile organic  compounds (VOCs) and semi-volatile organic compounds (SVOCs)
associated with wood treating. The soil remedy has largely been completed.

The ground water remedy, as of the time of the most recent operation, involved automated recovery of
dense non-aqueous phase liquid (DNAPL), with ground water extraction occurring only to enhance
DNAPL recovery. At the time of the RSE, the system had been down for over one year due to damage
from Hurricane Ivan in September 2004. The site team estimated that operation would resume by the end
of calendar year 2005. A remedy including ground water extraction is also planned for the site as a
second phase to the ground water remedy.  This RSE focuses on the ground water remedy as a whole,
including optimization of the current DNAPL recovery system and considerations for improved DNAPL
and ground water remediation.

The observations and recommendations contained in this report are not intended to imply a deficiency in
the work of either the system designers or operators but are offered as constructive suggestions in the best
interest of the EPA, the public, and the facility. These recommendations have the obvious benefit of
being formulated based upon operational data unavailable to the original designers. The RSE team has
the following  recommendations to improve the effectiveness of the current remedy.

    •    EPA is encouraged to continue revisiting the ground water and soil cleanup levels for the site
        because determination of these levels is fundamental to managing the remedy.

    •    Given relatively shallow ground water (e.g., 5 feet below ground surface) and benzene
        concentrations as high as 47 ug/L, the site team is encouraged to consider the potential for vapor
        intrusion in nearby buildings.  This consideration could include evaluation of the structures to
                                               11

-------
       determine if vapor intrusion is likely. Sampling would likely be appropriate only if this
       preliminary evaluation suggests the need.

       Since operation began in 1999 there have been four exceedances of the discharge criteria.  The
       RSE team has suggested new criteria for replacing the granular activated carbon on a regular
       basis.

    •   The site team should evaluate options to implement stronger institutional controls.

Implementation of these recommendations might require capital costs of $25,000 and an increase in
annual costs of $3,000 per year. However, these cost increases might be offset by the following
recommendations to reduce costs.

    •   The RSE team suggests proceeding with a semi-annual monitoring program in place of an
       anticipated quarterly monitoring program. Implementing this recommendation might save
       $40,000 per year.

       Once the pump and treat (P&T) system reaches steady state operation, the RSE team anticipates
       the annual labor costs can be reduced from $160,000 to $120,000 per year without reducing
       remedy protectiveness.  This could save an additional $40,000 per year, if implemented.

The RSE team also provides a recommendation for technical improvement, which involves repiping the
DNAPL line between the treatment shed and the DNAPL storage tank.  The majority of RSE team input,
however, is a recommended strategy for moving forward with the ground water remedy. This strategy
involves additional investigation and considerations  for addressing both DNAPL and contaminated
groundwater.

A table summarizing the recommendations, including estimated costs and/or savings associated with
those recommendations, is presented in Section 7.0 of this report.
                                              in

-------
                                       PREFACE
This report was prepared as part of a project conducted by the United States Environmental Protection
Agency Office of Superfund Remediation and Technology Innovation (U.S. EPA OSRTI) in support of
the "Action Plan for Ground Water Remedy Optimization" (OSWER 9283.1-25, August 25, 2004).  The
objective of this project is to conduct Remediation System Evaluations (RSEs) at selected pump and treat
(P&T) systems that are jointly funded by EPA and the associated State agency. The project contacts are
as follows:
           Organization
    Key Contact
       Contact Information
U.S. EPA Office of Superfund
Remediation and Technology
Innovation
(OSRTI)
Jennifer Hovis
1235 S. Clark Street, 12th floor
Arlington, VA 22202
Mail Code 5201G
phone: 703-603-8888
hovis.iennifer@epa.gov
Dynamac Corporation
(Contractor to U.S. EPA)
Daniel F. Pope
Dynamac Corporation
3601 Oakridge Boulevard
Ada, OK 74820
phone: 580-436-5740
fax: 580-436-6496
dpope@dvnamac.com
GeoTrans, Inc.
(Contractor to Dynamac)
Doug Sutton
GeoTrans, Inc.
2 Paragon Way
Freehold, NJ 07728
phone: 732-409-0344
fax: 732-409-3020
dsutton@geotransinc .com
                                            IV

-------
                           TABLE OF CONTENTS
NOTICE	I

EXECUTIVE SUMMARY	II

PREFACE	IV

TABLE OF CONTENTS	V

1.0 INTRODUCTION	1
       1.1    PURPOSE	1
       1.2    TEAM COMPOSITION	2
       1.3    DOCUMENTS REVIEWED	2
       1.4    PERSONS CONTACTED	2
       1.5    SITE LOCATION, HISTORY, AND CHARACTERISTICS	3
            1.5.1     LOCATION	3
            1.5.2     POTENTIAL SOURCES	3
            1.5.3     HYDROGEOLOGIC SETTING	3
            1.5.4     DESCRIPTION OF GROUND WATER CONTAMINATION	4

2.0 SYSTEM DESCRIPTION	5
      2.1    SYSTEM OVERVIEW	5
      2.2    EXTRACTION SYSTEM	5
      2.3    TREATMENT SYSTEM	5
      2.4    MONITORING PROGRAM	6

3.0 SUMMARY OF TREATMENT SYSTEM ACTIVITIES	7
      3.1    CURRENT SYSTEM OBJECTIVES AND CLOSURE CRITERIA	7
      3.2    TREATMENT PLANT OPERATION GOALS	8

4.0 FINDINGS AND OBSERVATIONS FROM THE RSE SITE VISIT	9
      4.1    FINDINGS	9
      4.2    SUBSURFACE PERFORMANCE AND RESPONSE	9
            4.2.1     WATER LEVELS	9
            4.2.2     CAPTURE ZONE	9
            4.2.3     DNAPL RECOVERY	10
      4.3    COMPONENT PERFORMANCE	10
            4.3.1     WELL PUMPS	10
            4.3.2     PIPELINES	10
            4.3.3     AIR COMPRESSORS	11
            4.3.4     OIL/WATER SEPARATOR	11
            4.3.5     BAG FILTER	11
            4.3.6     GRANULAR ACTIVATED CARBON UNITS	11
            4.3.7     PAH METER	11
            4.3.8     TREATED WATER DISCHARGE	12
            4.3.9     CONTROLS	12

-------
            4.3.10   OTHER MAINTENANCE ITEMS	12
      4.4    COMPONENTS OR PROCESSES THAT ACCOUNT FOR MAJORITY OF COSTS	12
            4.4.1    UTILITIES	12
            4.4.2    NON-UTILITY CONSUMABLES AND DISPOSAL COSTS	13
            4.4.3    LABOR	13
            4.4.4    CHEMICAL ANALYSIS	13
      4.5    RECURRING PROBLEMS OR ISSUES	13
      4.6    REGULATORY COMPLIANCE	13
      4.7    TREATMENT PROCESS EXCURSIONS AND UPSETS, ACCIDENTAL
            CONTAMINATION/REAGENT RELEASES	13
      4.8    SAFETY RECORD	14

5.0 EFFECTIVENESS OF THE SYSTEM TO PROTECT HUMAN HEALTH AND THE
    ENVIRONMENT	15
      5.1    GROUND WATER	15
      5.2    SURFACE WATER	15
      5.3    AIR	15
      5.4    SOILS	15
      5.5    WETLANDS	16

6.0 RECOMMENDATIONS	17
      6.1    RECOMMENDATIONS TO ENSURE EFFECTIVENESS	17
            6.1.1    CONTINUE REVISITING SOIL CLEANUP LEVELS AND ACLs	17
            6.1.2    CONSIDER POTENTIAL FOR VAPOR INTRUSION	17
            6.1.3    REVISE PROGRAM FOR DETERMINING GAC REPLACEMENT	17
            6.1.4    EVALUATE OPTIONS TO IMPLEMENT STRONGER INSTITUTIONAL CONTROLS	18
      6.2    RECOMMENDED CHANGES TO REDUCE COSTS	18
            6.2.1    REVISE THE GROUND WATER SAMPLING PROGRAM	18
            6.2.2    REVIEW LABOR COSTS ONCE SYSTEM OPERATION HAS STABILIZED	18
      6.3    MODIFICATIONS INTENDED FOR TECHNICAL IMPROVEMENT	19
            6.3.1    REPIPE DNAPL FROM TREATMENT SHED TO DNAPL STORAGE TANK	19
      6.4    MODIFICATIONS INTENDED TO GAIN SITE CLOSEOUT	19
7.0 SUMMARY	22


Figures
Figure 1-1.    Site Plan
Figure 1-2.    North-South Geologic Cross-Section
Figure 5-1.    Historical Soil Excavation and Results from the Sanders Beach Study
                                        VI

-------
                                l.-l   INTRODUCTION
1.1           PURPOSE

During fiscal years 2000 and 2001 Remediation System Evaluations (RSEs) were conducted at 20 Fund-
lead pump and treat (P&T) sites (i.e., those sites with pump and treat systems funded and managed by
Superfund and the States). Due to the opportunities for system optimization that arose from those RSEs,
EPA OSRTI has incorporated RSEs into a larger post-construction complete strategy for Fund-lead
remedies as documented in OSWER Directive No. 9283.1-25, Action Plan for Ground Water Remedy
Optimization. OSRTI has since commissioned RSEs at approximately 10 additional Fund-lead sites with
P&T systems. An independent EPA contractor is conducting these RSEs, and representatives from EPA
OSRTI are participating as observers.

The Remediation System Evaluation (RSE) process was developed by the U.S. Army Corps of Engineers
(USAGE) and is documented on the following website:

             http://www.environmental.usace.armv.mil/library/guide/rsechk/rsechk.html

RSEs involve a team of expert hydrogeologists and engineers, independent of the site, conducting a third-
party evaluation of site operations. They are broad evaluations that consider the goals of a remedy, site
conceptual model, above-ground and subsurface performance, and site exit strategy.  An RSE includes
reviewing  site documents, visiting the site for 1 to 1.5 days, and compiling a report that includes
recommendations to improve the system. Additional conference calls and/or email exchanges can be
used for further communication. RSE recommendations with cost and cost savings estimates are
provided in the following four categories:

   •   improvements in  remedy effectiveness
       reductions in operation and maintenance costs
   •   technical improvements
   •   gaining site closeout

The recommendations are intended to help the site team identify opportunities for improvements. In
many cases, further analysis of a recommendation, beyond that provided in this report, might be needed
prior to implementation of the recommendation. Note that the recommendations are based on an
independent evaluation by the RSE team, and represent the opinions of the RSE team. These
recommendations do not constitute requirements for future action, but rather are provided for the
consideration of all site stakeholders.

The American Creosote Works (ACW) Site was chosen based on the site complexity, remedy progress,
and forecasted expenditures. This report provides a brief background on the site and current operations, a
summary of the observations made during a site visit, and recommendations for changes and additional
studies.

-------
1.2          TEAM COMPOSITION

The team conducting the RSE consisted of the following individuals:

       Rob Greenwald, Hydrogeologist, GeoTrans, Inc.
       Anna Kekis, Civil/Environmental Engineer, GeoTrans, Inc.
       Doug Sutton, Water Resources Engineer, GeoTrans, Inc.
1.3
DOCUMENTS REVIEWED
Author
US EPA
US EPA
US EPA
US EPA
US Army Corps of
Engineers Mobile District
US EPA
BEM Environmental
Engineers and Scientists
US Army Corps of
Engineers Mobile District
Date
2/03/1994
May, 2001
August 1991
9/24/2001
October 2002
January, 2003
5/24/2004
June, 2005
Title/Description
Record of Decision, American Creosote Works, Inc.
OU2, Pensacola, FL
American Creosote Works Site, Pensacola, Florida,
Fact Sheet
Phase 3 Remedial Investigation Report, American
Creosote Works Site
5 Year Review, American Creosote Works
Superfund Site
SCAPS Investigation at American Creosote Works
Superfund Site
American Creosote Works Site, Pensacola, Florida,
Fact Sheet
Extraction Well and Recovery System Optimization
Desk Study Evaluation American Creosote Works
Superfund Site
Operation and Maintenance Report, April 1 1999 to
September 30, 2004 for OU2 Phase I DNAPL
Recovery and Recycling American Creosote Works
Superfund Site
1.4          PERSONS CONTACTED

The following individuals were present for the site visit:

   •   Jeff Day, BEM Systems
   •   Ed Herman, US Army Corps of Engineers Mobile District
   •   Shea Jones, Remedial Project Manager, EPA Region 4
   •   Richard Kinsella, US Army Corps of Engineers Mobile District
   •   Ross McCollum, US Army Corps of Engineers Mobile District
   •   Chuck Sands, US EPA Headquarters
   •   John Sykes III, State Regulator, Florida Department of Environmental Protection
   •   Kay Wischkaemper, EPA Region 4

-------
1.5            SITE LOCATION, HISTORY, AND CHARACTERISTICS

1.5.1          LOCATION

The ACW site is located on 1800 Gimble Street on the abandoned American Creosote Works wood
preserving plant in Pensacola, Florida. The site is approximately 18 acres in area. The site is bounded by
Gimble Street to the north, F Street to the east, Pine Street and an apartment condominium complex to the
South, and L Street to the west.  A lumber company, an auto body shop, a produce distributor, and an
appliance sales and repair shop lie to the north of the site, residential areas are to the south and east, and
the Pensacola Yacht Club (PYC) lies to the southwest of the site. The site is about 600 yards north of
Pensacola Bay and Bayou Chico. A site plan is included as Figure 1-1.

1.5.2          POTENTIAL SOURCES

The ACW site has been impacted by creosote and pentachlorophenol (PCP) resulting from wood
preserving activities that took place from 1902 to 1981. The main sources of contamination to soil and
groundwater are three ponds (main, overflow, and holding), a natural drainage course to Bayou Chico and
Pensacola Bay leading from the ponds, and the railroad impoundment. Contamination also resulted from
overland flow of impacted water from the ponds during periods of heavy rain and hurricanes. During a
Category 3 hurricane, the water surge reaches the edge of the site, and during a Category 4 hurricane, the
surge extends to the current treatment shed at the northern end of the property. In late 1983, the ponds
were cleaned out, solidified, and capped. Current sources of groundwater contamination are the creosote
and PCP dense non-aqueous phase liquid (DNAPL) in the ground.  In 1994, EPA estimated that there
were 7.25 million gallons of DNAPL and 152 million gallons of contaminated groundwater. In
September 1998, a DNAPL recovery system was installed and operated until about September 2004,
when it was damaged during Hurricane Ivan.  The current groundwater and soil contaminants are VOCs,
phenols, PAHs, PCPs, and dioxins.

1.5.3          HYDROGEOLOGIC SETTING

Pensacola lies within the Coastal Lowlands, which consist mainly of sand and gravel. This aquifer is
exposed at the surface and deepens to as much as 1,100 feet below ground surface. The upper 25 feet of
the ACW site consists of fine to coarse sand.  From about 25 feet to 200 feet below ground surface there
is very dense sand, fine to medium grained, with interbedded silt and clay nodules and lenses. There is a
clay layer directly under the ACW ponds at about 100 feet below ground surface.  The Pensacola Clay
underlies the sand and gravel aquifer at approximately 200 feet below ground surface and is
approximately 250 to 300 feet thick, reportedly providing a hydraulic barrier to vertical contaminant
migration. Based on the characteristics of the sands, the water-bearing zone can be divided into two
distinct strata identified as the upper and lower sand. The upper sand extends to approximately 25 or 30
feet below ground surface.  Representative hydraulic properties for the upper sand include a horizontal
hydraulic conductivity of 10"3 cm/s (approximately 3 feet/day) and a hydraulic gradient magnitude of
0.003. South of the site, a clay layer up to 38 feet thick underlies the Pensacola Yacht Club property
beginning at a depth of about 20 feet.  This clay layer extends south toward Pensacola Bay.  The lower
sand extends from 30  feet below ground surface to 200 feet below ground surface. Representative
hydraulic conductivities for the lower sand from the Remedial Investigation range from 3.4xlO"4 cm/sec
to 4.6* 10"4 cm/sec.  A representative hydraulic gradient magnitude is 0.0016. Ground water flow
direction at the ACW  site in the lower sand zones  is to the southwest. In the upper sand, ground water
flow direction is to the southwest on the western part of the site and southeast on the eastern part of the
site.  A north-south geologic cross-section is included as Figure 1-2.

-------
1.5.4         DESCRIPTION OF GROUND WATER CONTAMINATION

DNAPL has been observed in the upper and lower sands underlying the ACW site.  DNAPL migration in
the upper sand seems to follow the outline of the former waste ponds and the drainage area. During the
RSE site visit this contamination in the upper sand was referred to as the "surface runoff plume". It is
estimated that in the upper sand, DNAPL migration extends 300 ft to the south of Cypress Street, below
the PYC property. Its greatest depth is 10 to 30 feet below ground surface, following the upper boundary
of the shallow clay layer in this area. DNAPL occurs in the upper sand as stratified layers from less than
1 inch to 7 feet thick. The actual lateral extent of DNAPL in the upper sand layer is not known at this
time.

DNAPL in the lower sand has been observed at depths 35 to 75 feet below ground, mostly near the former
main pond.  The actual lateral and downgradient extend of DNAPL in the lower sand layer is not known
at this time either.  It is possible that  DNAPL in the lower sand extends underneath Pensacola Bay.

DNAPL in the subsurface provides a continuing source of PCP, PAH, and dioxin/furan contamination to
the groundwater.  Ground water contamination reportedly extends to as deep as  192 feet. In 2004, VOCs
and SVOCs were detected in well MW-4 (screened from 182 to 192 feet below ground surface) just
southwest of the site.  Ground water  contamination extends as far as  1,000 feet south of the site. In 2004,
benzene was detected at concentrations ranging from 28 ug/L to 84 ug/L, and acenaphthene was detected
at concentrations ranging from 58 ug/L to 130 ug/L in wells 28-1 and 28-5, which are located along the
PYC drain.  It is possible that the contamination extends further south, perhaps discharging to Pensacola
Bay.

-------
                            2.0 SYSTEM DESCRIPTION
2.1           SYSTEM OVERVIEW

The pump and treat (P&T) system began operation in 1998 as part of the first phase of remediation of
operable unit (OU) 2 (DNAPL remediation). When operating, the system extracts both water and
DNAPL, but water is only extracted to enhance DNAPL recovery rather than to remediate or control
groundwater contamination. The system was damaged during Hurricane Ivan in September 2004 and has
not operated since that time. Repairs are ongoing, and the site team expects to resume operation by the
end of calendar year 2005.
2.2           EXTRACTION SYSTEM

The P&T extraction system has consisted of 13 extraction wells. Each extraction well has a stainless steel
casing and a riser.  Extraction wells are installed at depths ranging from 20 feet to 76.5 feet below ground
surface. Historically, each operating well was outfitted with two pneumatic pumps: one for extracting
DNAPL and one for extracting ground water.  The pumps in eight wells are controlled by a series of four
sensors (two for each ground water pump and two for each DNAPL pump) to minimize the amount of
DNAPL extracted by the ground water pump and to minimize the amount of ground water extracted by
the DNAPL pump.  At the remaining extraction wells, the sensors and controllers were not installed
because the wells were not removing enough DNAPL.

Before the P&T system was shut down due to damage from Hurricane Ivan, only four of the extraction
wells were effective (EW-3, EW-5, EW-7, and EW-12). These four wells will operate when system
operation is resumed. In addition, four other wells (EW-2, EW-6, EW-8, and EW-11) will also operate
when the system is resumed. These four other wells were not very productive prior to system shut down,
but the site team believes that this lack of production was likely due to drought conditions.  Now that
there are no longer drought conditions, the site team anticipates that productivity of these wells may
improve.  The other five extraction wells have not recovered a significant portion of DNAPL, presumably
because the well screens do not intercept the intervals impacted with DNAPL.
2.3           TREATMENT SYSTEM

The treatment system is designed to treat the relatively low flow of water that is extracted to enhance
DNAPL recovery. The system consists of the following:

    •   10,000-gallon DNAPL holding tank
    •   630-gallon oil/water separator
    •   One 25 micron bag filter
       Two 1,500-pound liquid phase GAC units arranged in series
    •   An automated Turner Designs PAH monitoring meter
       Infiltration gallery
    •   Programmable logic control (PLC)  system

-------
2.4           MONITORING PROGRAM

Process Monitoring

Process monitoring consists of quarterly sampling at three locations: prior to the GAC units, in between
the GAC units, and after the GAC units. Analysis is for VOCs, dioxins/furans, and BNAs. An existing
PAH meter for evaluating the effluent does not work reliably.


Ground Water Monitoring

The four on-site monitoring wells (ACWMW-5 cluster and ACWMW-6 cluster) are sampled semi-
annually for VOCs, SVOCs, and dioxins/furans. Additional on-site monitoring wells ACW-4, ACW-5,
ACW-MW1, ACW-MW2,  ACW-MW3, off-site monitoring wells (OPYC-1 through OPYC-5), and 22
other off-site monitoring wells have been sampled for VOCs, SVOCs, and dioxins/furans quarterly since
April 2004. These 32 wells have been part of the interim long-term monitoring program. The sampling
events were April 2004, July 2004, October 2004, and January 2005. Long-term ground water
monitoring is expected to continue at the site.

-------
         3.-1   SUMMARY OF TREATMENT SYSTEM ACTIVITIES


3.1           CURRENT SYSTEM OBJECTIVES AND CLOSURE CRITERIA

The site has two operable units (OUs):

   •   OU1 deals with the remediation of contaminated soil, sludge, and sediment. The amended
       Record of Decision (ROD) for OU1 was written in 1999. The OU1 remedy was largely
       completed by January 2004 and is not a primary focus of this RSE.

       OU2 addresses remediation of DNAPL and contaminated groundwater. The OU2 remedy is
       divided into two phases:

              Phase 1 of the OU2 remedy focuses on DNAPL recovery.  The ROD specifies the
              following components for this phase of the remedy:

                    Enhanced DNAPL recovery using a combination of water, alkaline, surfactant,
                    and polymer flooding

                    DNAPL/water separation and ground water treatment

                    Off-site transport and recycling of recovered DNAPL and injection of treated
                    ground water

                    Periodic ground water monitoring to evaluated DNAPL recovery efficiency

                 0   Sampling, plugging and abandoning private wells for which owner consent is
                    granted

                 ฐ   Implementation of State-imposed well permit restrictions

              Phase 2 of the remedy focuses on residual ground water contamination after DNAPL
              recovery has ended.  The ROD specifies the following components for Phase 2:

                 0   Ground water removal by pumping extraction wells

                    On-site treatment of contaminated ground water

                    Nutrient and hydrogen peroxide addition to the treated water

                 0   Injection of the treated ground water, with nutrients, into the contaminated
                    portion of the aquifer to stimulate in-situ biological treatment activity

                 ฐ   Dewatering of waste sludge from the treatment process and disposal at an off-site
                    RCRA landfill

                 ฐ   Periodic ground water and surface water monitoring to evaluate treatment system
                    performance

-------
The OU2 ROD specifies points of compliance for meeting the ACLs established for ground water at this
site.  These ACLs were designed to insure that groundwater exceeding surface water standards would not
discharge to Pensacola Bay and the PYC ditch.  The remedy will be considered effective when
groundwater wells immediately upgradient of the surface water bodies meet surface water standards and
ACLs are met in ground water at the points of compliance.  These ACLs have been used in place of
MCLs for cleanup criteria because area residences and businesses use city water and potable use of the
aquifer has been restricted. ACLs are currently  being reviewed by the EPA.  The current ACLs are
provided in the following table for reference.
Compound
Remedial Goals, jig/L
Volatile Organics
Benzene
91
Semi-Volatile Organics
Acenaphthene
Fluoranthene
Naphthalene
Total cPAHs
Benzo(a)Anthracene
Benzo(a)Pyrene
Benzo(b&k)Fluoranthene
Chrysene
Anthracene
Fluorene
Phenanthrene
Pyrene
Dibenzofuran
Pentachlorophenol
9,000
1,5000
21,900
1,100








44
296,000
The current P&T system represents work associated with the first phase of OU2. Use of surfactants and
alkaline have not been employed. State restrictions for permitting wells have been implemented, but
there is a question as to the effectiveness of these restrictions at the local level.
3.2
TREATMENT PLANT OPERATION GOALS
When restarted, the DNAPL recovery system will run 24 hours a day 7 days a week.  Water discharge
standards are set to the ACLs. The current ACLs are provided in the above table for reference; however,
the ACLs are being reviewed by EPA.

-------
   4.-1   FINDINGS AND OBSERVATIONS FROM THE RSE SITE VISIT
4.1           FINDINGS

The observations provided below are not intended to imply a deficiency in the work of the system
designers, system operators, or site managers but are offered as constructive suggestions in the best
interest of the EPA and the public. These observations obviously have the benefit of being formulated
based upon operational data unavailable to the original designers. Furthermore, it is likely that site
conditions and general knowledge of ground water remediation have changed over time.
4.2           SUBSURFACE PERFORMANCE AND RESPONSE

4.2.1          WATER LEVELS

Water elevation measurements were not collected at the ACW site until a quarterly water level
measurement program was recommended by the 5-year review report in 2001. The water elevation
contour maps and bedrock potentiometric maps indicate groundwater flow direction to the south towards
Pensacola Bay. Water levels also confirm a significant downward gradient of 0.05 ft/ft based on water
level measurements from wells 400 and 440 in January 2005.


4.2.2          CAPTURE ZONE

The extraction of groundwater during the first phase of the OU2 remedy is to enhance DNAPL recovery
and not to provide capture of contaminated ground water. When the system is operating, the average
ground water extraction rate is 0.4 gpm. On the other hand, the flow of ground water through the site is
approximately 6 gpm based on the following equation.

                                         Q = Kibw

where the definitions and values for the above parameters are provided in the following table.
Parameter Definition
Parameter Value for This Site
Provided by Site Documents
K = the hydraulic conductivity
/ = hydraulic gradient
b = thickness of the aquifer where contamination is present
w = width of the ground water contamination
~ 3 feet/day
~ 0.003 ft/ft
~ 200 feet
~ 600 feet
Calculated
Q = the flow rate of ground water flowing through the
contaminated portion of the site
~6gpm
        Note: A conversion factor of 7.48 gallons pet' cubic foot is used in the calculation ofQ.

Assuming that an appropriate extraction rate for capture is double the amount of water flowing through
the site, the extraction rate needed for capture would be approximately 12 gpm.  Therefore, the historical

-------
average extraction rate of approximately 0.4 gpm, which is intended to aid in DNAPL recovery, would
likely not be sufficient for effective hydraulic capture.


4.2.3         DNAPL RECOVERY

DNAPL recovery decreased dramatically the last two years that the system operated. During the first four
years of the OU2 Phase 1 Remedy, 20,000 to 26,000 gallons of DNAPL were removed per year. During
the last two years of operation only about 11,000 gallons of DNAPL were removed per year. The
following table has DNAPL removal estimates from startup in September 1998 until the shutdown in
August-September 2004 due to Hurricane Ivan.
Time Period
September 1998 to August 1999
September 1999 to August 2000
September 2000 to August 2001
September 2001 to August 2002
September 2002 to August 2003
September 2003 to August 2004
Total
Approximate DNAPL Removal (gallons)
20,246
20,246
23,027
26,434
10,723
10,723
111,399
The site team does not believe this decrease is due to well fouling. Rather, they attribute it to reduced
precipitation and infiltration, which appears to correlate with DNAPL recovery. Precipitation has
increased recently, and the site team is expecting recovery rates to increase once the system is restarted.
4.3           COMPONENT PERFORMANCE

4.3.1         WELL PUMPS

Each extraction wellhead is protected by a 3 feet square 2 feet deep steel vault with poured concrete base
and a steel lid. The well pumps are maintained as follows:

    •  The check valves on pump controls are cleaned quarterly.

    •  The plastic parts of pumps that are damaged by DNAPL are changed as needed (quarterly on
       average).

    •  The sensors in wells are cleaned approximately twice per year.

The sensors and pump controllers have been effective at reducing ground water extraction by the DNAPL
pumps and DNAPL extraction by the ground water pumps.


4.3.2         PIPELINES

Groundwater and DNAPL is conveyed from the extraction wells to the treatment system through above-
ground pipelines. The DNAPL line is then routed from the treatment shed to the DNAPL storage tank.
The pneumatic lines from the air compressor in the treatment shed to the pumps in the wells also run in
                                             10

-------
above-ground pipelines. All above-ground pipelines used to be PVC; but currently, the pipelines are
being upgraded as follows:

       Ground water pipelines will be 1.5 inch PVC

    •   DNAPL pipelines will be % inch kynar

    •   The containment piping around the groundwater and DNAPL pipelines will be 4" stainless steel

       High voltage electricity wires for solenoid control will be in galvanized steel pipelines

       Low voltage electricity wires for sensors will be in galvanized steel pipelines

The site team expects to finish the pipeline upgrade project around November 2005.


4.3.3         AIR COMPRESSORS

A 10 horsepower air compressor powers the pneumatic pumps. The site team did not report any
maintenance problems with the air compressor.


4.3.4         OIL/WATER SEPARATOR

The treatment system is equipped with a 630 gallon oil water separator. The accumulating DNAPL is
manually transferred into 55 gallon drums for storage until a tanker truck comes to pump out the drums.
If storage space in the drums is not adequate between pick-up events, the contents of the drums are
pumped into the DNAPL storage tank.


4.3.5         BAG FILTER

The treatment system has one  25 micron bag filter. The filter is changed weekly.


4.3.6         GRANULAR ACTIVATED CARBON UNITS

There are two 1,500-pound  GAC units piped in series with no ability to change the lead and lag units.
Since startup of the DNAPL extraction the carbon was changed out twice: on 8/17/01 and on 5/04/04.
This frequency of carbon change equates to about 3,000 pounds of carbon use over a 3-year period.
Therefore, the current system uses approximately 1,000 pounds of carbon every year. After removal,
spent carbon is brought to a regeneration facility.  There were a number of exceedances of the discharge
criteria during the past few years of operation, suggesting that GAC may have needed more frequent
replacement.


4.3.7         PAH METER

The PAH meter used to determine the presence of contaminants in the effluent has been recently
ineffective for the site because the process water flow rate is too slow for the meter to gather a reliable
reading. The site team relies on the quarterly process sampling to determine when GAC requires
replacement.
                                             11

-------
4.3.8          TREATED WATER DISCHARGE

The infiltration gallery is about 120 feet away from the treatment shed and is about 150 feet long. The
gallery runs parallel to the northern boundary of the site.  The site team has not reported any problems
associated with maintenance.


4.3.9          CONTROLS

Data from the treatment system is downloaded to the operator's laptop routinely. There are appropriate
controls to prevent releases.


4.3.10        OTHER MAINTENANCE ITEMS

The following maintenance activities are necessary for optimal treatment system operation:

    •   change absorbent pads around treatment plant weekly

    •   weekly general site check

    •   occasional service to floor float


4.4    COMPONENTS OR PROCESSES THAT ACCOUNT FOR MAJORITY OF COSTS

The USAGE estimates that approximately $380,000 per year is spent on operation, maintenance,
monitoring, and reporting of the current DNAPL extraction system at the ACW site. Part of the cost is
paying for subcontractors to do the groundwater sampling.  Detailed breakdown of these costs is included
in Table 4-2; a brief description is presented below.
Item Descriptions
O&M labor, PM, and reporting - (provided by USAGE)
Consumables/GAC - (switch out GAC and other consumables)**
DNAPL disposal - (estimate 20,000 gallons per year at $6 per gallon)
Electricity
Analytical - no cost to site (analyzed by the CLP program)
Sampling labor - (10 day event for 2 people, assume $2,000 per day, four
events per year)**
Other
Total
Estimated Cost
$160,000
$5,000
$120,000
$1,500
$0
$80,000
$13,500
$380,000
   * Estimated by RSE team based on other information provided by site team.
4.4.1          UTILITIES

Primary consumer of power is the air compressor and the transfer pump between the oil/water separator
and the bag filter. Electrical cost for the plant for one year is $1,500.
                                            12

-------
4.4.2         NON-UTILITY CONSUMABLES AND DISPOSAL COSTS

DNAPL disposal (off-site incineration) for one year, assuming 20,000 gallons of DNAPL, is
approximately $120,000.  GAC usage is approximately 1,000 pounds per year, but more frequent
changeouts may be needed to avoid future exceedances of the discharge criteria. The cost for GAC is
likely between $1,000 and $2,000 per year. The bag filter is replaced weekly and likely contributes a
minimal amount to annual costs. Total non-utility consumables and disposal cost for one year is
approximately $125,000.


4.4.3         LABOR

Labor costs for the treatment system include project management, reporting, and operation and
maintenance of the treatment system. Maintenance activities include weekly treatment system
maintenance (described in Section 4.3.9), quarterly and semiannual extraction well maintenance
(described in Section 4.3.1), and quarterly ground water sampling.

4.4.4         CHEMICAL ANALYSIS

The chemical analysis for the site is provided by the CLP program, and the costs are not charged to the
site.
4.5          RECURRING PROBLEMS OR ISSUES

Recurring problems for the DNAPL extraction system are as follows:

•      Electrical problems due to lightning at least twice a year
•      Clogging of the Kynar tubing between the treatment shed and the DNAPL storage tank
•      Occasional hurricanes that cause damage


4.6          REGULATORY COMPLIANCE

Discharge standards (which are the remedial goals or ACLs) have been met with the exception of four
occasions.  On April 2001, April 2002, October 2002, and June 2003 benzene in the treatment plant
effluent exceeded its ACL.
4.7  TREATMENT PROCESS EXCURSIONS AND UPSETS, ACCIDENTAL
     CONTAMINATION/REAGENT RELEASES

The site team did not report any treatment process excursions that would lead to a health and safety
hazard or additional site contamination.
                                          13

-------
4.8   SAFETY RECORD

The site has a trailer that has a telephone, health & safety equipment, and a bathroom. The site is not in a
remote location, and the operators have cell phones as well. No health and safety incidents were reported
to the RSE team.
                                            14

-------
     5.-1   EFFECTIVENESS OF THE SYSTEM TO PROTECT HUMAN
                         HEALTH AND THE ENVIRONMENT
5.1  GROUND WATER

Dissolved and freephase PCP and PAHs exist underneath the ACW site. The vertical and horizontal
extent of this contamination is not entirely known.

The existing P&T system is designed for DNAPL extraction and not containment of groundwater.
Groundwater is migrating offsite at concentrations well above MCLs but below the current ACLs for a
number of constituents (except for dibenzofuran which is routinely detected above the ACLs). It is noted,
however, that EPA is reviewing the ACLs.

Residences and businesses in the area are connected to the public water system, and the public water
supply wells are upgradient of the ACW site.  Therefore, the remedy should be protective of human
health with respect to ingesting ground water. However, the site team reports that the implemented
institutional control is a Florida Department of Environmental Protection rule. The site team reports,
however, that these institutional controls may not be effective since there are lots of exceptions to the
rules, such as allowing installation of wells for irrigation. There is a concern that these rules may not
provide adequate notification and that the Department of Health (which samples private wells) may not be
aware of the institutional controls and the potential for impacts to local wells.
5.2           SURFACE WATER

Site contamination extends downgradient from the site and likely reaches Pensacola Bay, Bayou Chico,
and/or the water in the PYC ditch. To date, contaminant concentrations in ground water are generally
below the ACLs; however, EPA is reviewing these ACLs.
5.3            AIR

Site contaminants include VOCs, such as benzene and naphthalene. In general, contaminant
concentrations are higher at 60 feet below ground surface than in shallow ground water.  However,
benzene concentrations as high as 47 ug/L have been detected in monitoring well 28-5, which screens an
interval from 5 to 10 feet below ground surface. Given the shallow depth to ground water, this benzene
concentration may be sufficiently high to cause a potential indoor air problem, if an overlying structure is
present that is not adequately isolated from soil vapor.
5.4           SOILS

On-site soil contamination from the three ponds has been addressed.  In late 1983, the contamination in
the ponds was removed, solidified, and capped. In addition, in 2003, contaminated surface soils from the
condominium area just south of the site, in the PYC area, and in the east and west residence areas were
excavated. Figure 5-1 illustrates areas where soil removal has been completed.
                                              15

-------
The residential areas downgradient of the site, shown on Figure 5-1, were investigated in 1997 during the
"Sanders Beach Study".  During this study, dioxin TEQ concentrations up to 1 ppb were identified. In
addition, the 1991 Phase III RI indicates TEQ concentrations as high as 1,500 ng/kg (i.e., 1.5 ppb) on
residential property immediately south of the site.  This surface soil contamination represents a potential
human exposure pathway.  For establishing cleanup criteria, the site team refers to the 1998 EPA
Directive titled Approach for Addressing Dioxin in Soil at CERCLA AND RCRA Sites (OSWER Directive
9200.4-26), which established a TEQ concentration of 1 ppb as a starting point for establishing dioxin
cleanup levels at CERCLA and RCRA sites.  According to this directive, a TEQ of 1 ppb represents an
increased cancer risk of 2.3 x 10"4. If these levels are revisited along with the ACLs for ground water, the
site team may find that remedial  action of these surface soils is merited.  The site team notes that a risk-
based corrective action approach consistent with new Florida Department of Environmental Protection
regulations may be appropriate for this soil contamination.  This regulation sets a default soil cleanup
target of 7 parts per trillion (ppt) for dioxin.

The site team is in the process of investigating possible surface soil contamination present along the
southeast ditch. The contamination might be due to the rail line or to overland flow from the site.
5.5           WETLANDS
Additional investigation is proposed for the PYC ditch, which may have been impacted from overland
flow of contamination and/or discharge of impacted ground water to the ditch.
                                               16

-------
                            6.-1   RECOMMENDATIONS
The recommendations provided in this section are based on a review of site documents and discussions
with the site team during the site visit. The recommendations in Sections 6.1 through 6.3 are intended to
be implemented immediately while the current system is operating.  The items in Section 6.4 are provided
to give the site team direction in modifying the overall OU2 remedy to be consistent with the ROD and
better achieve the goals stated in the ROD.

Cost estimates provided herein have levels of certainty comparable to those done for CERCLA
Feasibility Studies (-307+50%), and these cost estimates have been prepared in a manner consistent with
EPA 540-R-00-002, A Guide to Developing and Documenting Cost Estimates During the Feasibility
Study, July 2000.

6.1           RECOMMENDATIONS TO ENSURE EFFECTIVENESS
6.1.1         CONTINUE REVISITING SOIL CLEANUP LEVELS AND ACLs

EPA indicated that they are reviewing the ACLs that have been selected for the site to determine if they
are appropriate for ground water discharging to Pensacola Bay, Bayou Chico, and/or the PYC ditch.  The
RSE team encourages EPA to continue with this review because the determination of new ACLs will
significantly affect the implementation of the second phase of the OU2 remedy.

The RSE team also suggests that EPA revisit the soil cleanup standards for dioxin. The current level of 1
ppb represents an increased cancer risk of 2.3 x 10"4 and was meant to serve as a starting value for sites.
It is possible that a lower concentration is more appropriate as a cleanup level. The site team notes that
the Florida Department of Environmental Protection's new risk-based regulation establishes a default soil
cleanup target level of 7 ppt for dioxin.


6.1.2         CONSIDER POTENTIAL FOR VAPOR INTRUSION

Given the benzene concentration of 47 ug/L at monitoring well 28-5 and the relatively shallow depth to
water (5 to 10 feet), the site team may want to review residential and business structures in the area to see
if such concentrations in ground water could result in an adverse impact to indoor air. This
recommendation does not necessarily suggest that vapor sampling or indoor air sampling be implemented.
Such sampling would be contingent on the results from the review of building construction.  For example,
if the buildings are on stilts, it would be unlikely for there to be an indoor air problem caused by the
ground water plume.  The RSE team estimates that the cost for this evaluation is less than $5,000,
including documentation in a short technical memo to EPA.


6.1.3         REVISE PROGRAM FOR DETERMINING GAC REPLACEMENT

The treatment plant includes an automated sensor for detecting PAHs in the GAC effluent. If working
properly, this sensor can indicate to the site team when the GAC should be replaced. However, the sensor
has not been effective because the process water flow rate is too low. In its relatively short operating
                                             17

-------
history from June 1999 through September 2004, there were four instances of exceedances of discharge
criteria from the treatment plant effluent.  The site team collects samples from the GAC influent, mid-
point, and effluent on a quarterly basis, and the RSE team believes that this routine monitoring and
historical data is sufficient to determine when GAC replacement is necessary. Historical process
monitoring suggests that the two GAC units reach their chemical loading capacity every year, but GAC
has only been replaced twice since June 1999. The RSE team suggests that the site team replace the GAC
in twice the amount of time it takes for there to be a significant detection of benzene at the sampling point
between the two GAC units, or every year of operation, whichever is less. That is, during a period of
continuous operation, if there is no detection of benzene at the midpoint for six or nine months, the site
team should replace both GAC units after 12 months of operation. On the other hand, if there is a
significant detection of benzene after three months of operation, the site team should replace both GAC
units three months later (i.e., after 6 total months of operation or twice the amount of time it took for the
detection at the midpoint). This recommendation will likely increase the cost of GAC changeouts from
approximately $1,500 per year (e.g., two changeouts during five to six years of operation) to
approximately $4,500 per year (e.g., one changeout per year), but it should reduce the likelihood of the
treatment plant effluent exceeding the ACLs.


6.1.4         EVALUATE OPTIONS TO IMPLEMENT  STRONGER INSTITUTIONAL CONTROLS

As discussed in Section 5.1, there is some concern that local parties, including the Department of Health,
may not be aware of the current institutional controls. It is recommended that the EPA and State
regulators work with local officials to insure that the intent of the institutional controls is adequately
addressed. This might require approximately $20,000 of contractor support.
6.2           RECOMMENDED CHANGES TO REDUCE COSTS

6.2.1         REVISE THE GROUND WATER SAMPLING PROGRAM

The site team conducted four quarters of ground water monitoring between April 2004 and January 2005.
It is appropriate to conduct long-term ground water monitoring at this site, and the RSE team suggests
that an appropriate, cost-effective program would likely consist of semi-annual events that include
sampling of water quality, measuring water levels, and gaging DNAPL levels in monitoring wells.  Based
on information provided by the site team, the RSE team estimates that the monitoring costs (excluding
analysis)  are on the order of $20,000 per event. Therefore, continuing with quarterly sampling would
likely cost $80,000 per year and moving forward with semi-annual sampling would likely cost $40,000
per year.  The RSE team assumes that the site team would have eventually proceeded with a quarterly
sampling program in the absence of an RSE recommendation. Therefore, the RSE team estimates that
implementing this recommendation could save the site approximately $40,000 per year.

6.2.2         REVIEW LABOR COSTS ONCE SYSTEM OPERATION HAS STABILIZED

The current annual O&M cost for the system is $380,000. If recommendation to continue annual
sampling, but on a semi-annual basis, is implemented, the annual costs should decrease by approximately
$40,000 per year to $340,000. This is relatively cost-effective for a Fund-lead site of this nature,
especially since there is not much flexibility in DNAPL disposal costs. Once the system is operating on a
steady-state basis, the labor costs for project management, reporting, and plant operations could likely be
reduced to approximately $120,000 from $160,000.  This would leave $25,000 per year for project
                                             18

-------
management, $20,000 per year for annual reports, $50,000 for weekly operator visits, and $25,000 for
non-routine repairs. This should further reduce long-term O&M costs to approximately $300,000.
6.3           MODIFICATIONS INTENDED FOR TECHNICAL IMPROVEMENT

6.3.1         REPIPE DNAPL FROM TREATMENT SHED TO DNAPL STORAGE TANK

The kynar DNAPL line from the treatment plant to the DNAPL storage tank makes a series of right-angle
turns, including one turn from a vertical direction to a horizontal direction. At this particular turn, the
kynar tubing kinks.  During the past several winters when temperatures drop, the line clogs at this kink.
The kink and clog could likely be avoided by hard-piping this portion of the line with either galvanized or
painted steel. This effort should reduce the number of shutdowns and reduce the potential for DNAPL
leaks. The costs for this modification should be less than $1,000.


6.4           MODIFICATIONS INTENDED TO GAIN SITE CLOSEOUT

The items in this section are provided as a proposed strategy for a cost-effective means of implementing
the ROD. It should be noted that this strategy is, in many ways, consistent with the approach taken to
date and should not necessarily represent a large departure from activities that have been conducted to
date. However, the suggested strategy will involve implementation of Phases I and II of the OU2 ROD
simultaneously with the purpose of improving remedy protectiveness. The RSE team suggests the
following path forward (items 1 to 4 pertain to the upper sand only):

1.      Conduct a shallow SCAPS event to determine the DNAPL distribution and extent south of the
       site toward and onto the  PYC property, between the water table and the top of the shallow clay
       layer that begins at approximately -10 ft MSL.

2.      Based on the SCAPS results, install two monitoring wells (constructed so they could potentially
       be converted to extraction wells) near the downgradient edge of the DNAPL plume but within
       this offsite shallow DNAPL plume to determine how mobile the product is and the potential for
       recovering NAPL from this location. If the mobile DNAPL in the shallow sand extends all the
       way to the Bay, these wells would likely be located in an area where establishing a DNAPL
       cutoff is appropriate and where access is optimal.

3.      Based on the data from steps 1 and 2, determine the potential for DNAPL in the upper sand to
       continue migrating (based on recovery rates and DNAPL thickness in the new wells) and the need
       for actively containing this offsite DNAPL. Three options may exist for addressing this shallow
       DNAPL:

              No action - might be appropriate if the product plume is stable and not mobile

           •   Manual collection from wells or collection trench - might be appropriate if product is
              mobile but sufficiently limited to not merit a more aggressive containment approach.

           •   Recovery trench with automated collection - only appropriate if the other two other
              options are not sufficient, and DNAPL will almost certainly migrate into the PYC ditch
              or discharge directly to the bay.
                                             19

-------
4.      If the DNAPL is mobile and "no action" is not an option, discuss the potential with PYC to use
       their property for remediation of shallow DNAPL. Remedial options to be discussed with PYC
       might range from periodic manual collection to the installation and operation of a DNAPL
       recovery trench and an on-site AST system for collected DNAPL.

5.      Implement a comprehensive ground water remedy as follows:

           •    Increase shallow DNAPL recovery on-site to reduce mobile DNAPL mass.  This
               component of the remedy is important to reduce/minimize the amount of DNAPL that
               can continue to migrate downward or horizontally at depth. The on-site SCAPS data
               (already collected) should be used to locate wells in three different intervals: a shallow
               interval, an intermediate interval,  and a deep interval.  Each of the recovery wells should
               have a screened interval that covers the extent of the DNAPL zone it is intended to
               screen. According to the SCAPS  report the screen lengths would be 5 feet for the
               shallow zone, 20 feet for the intermediate zone, and 20+ feet for the deep zone. Effort
               should be taken to stay within these intervals so that the wells do not act as preferential
               pathways for further downward migration. Effort should also be taken to place the wells
               in areas with relatively high permeability so that DNAPL recovery is effective.  (Note
               that the previous SCAPS data concluded that the reason that some wells don't produce is
               that they might be screened in areas with relatively low permeability.) Estimate
               approximately four wells per interval for a total of approximately  12 new recovery wells.

               If the revised ACLs are lowered and the offsite dissolved plume has concentrations that
               exceed these new standards, ground water extraction wells should be installed to contain
               the dissolved contamination in both the upper sand and the lower sand.  Ground water
               extraction  should likely occur at multiple depth intervals at or near the downgradient
               edge of the ACW property. Extracted water should be pumped to  the on-site treatment
               system for treatment. Treated water should be discharged to the subsurface in an
               infiltration gallery that is located side-gradient of the capture zone, presumably on the
               eastern side of the property, so that the capture zone of the extraction wells is not
               negatively impacted.  By cutting off the primary source of dissolved contamination at this
               location, the concentrations at locations downgradient of the capture zone that are not in
               direct contact with DNAPL should begin to decrease.  Evaluating  concentration trends at
               the 400 monitoring well cluster will help evaluate the effectiveness of this effort to
               contain the dissolved plume (unless significant DNAPL is present in the vicinity, or if it
               is within the capture zone of the extraction wells).  Concentrations in other wells, such as
               well 760 and 28-1, should also begin to decrease. Groundwater modeling with a
               relatively simple software package, such as Quickflow™, should be used to help
               determine the appropriate pumping locations, infiltration gallery location, and pumping
               rates.

           •    The recovery from the DNAPL recovery wells and the ground water extraction wells (if
               installed) should be evaluated to determine if the existing treatment plant can handle the
               capacity. If a new treatment plant is needed, the plant should include the following:

                      Appropriately sized oil-water separator

                   ฐ   Appropriately sized organoclay vessel to remove emulsified product that may be
                      present in the oil-water separator effluent
                                               20

-------
                      Two appropriately-sized GAC vessels arranged in series with the capability to
                      swap lead and lag units

                      Sample ports to sample the influent, between the GAC vessels, and the effluent
                      (use of the automated BTEX/PAH sensor should not be needed)

                      Discharge to an infiltration gallery that is constructed side-gradient to the former
                      waste ponds so that it does not reduce the ability of the groundwater extraction
                      wells to provide containment.

If the data in steps 1 through 4 clearly suggest the need for downgradient containment of shallow
DNAPL, consider construction of a shallow interceptor trench at a practical location to contain the
downgradient plume.  This location would preferably as close to the downgradient edge of the plume as
possible. The trench should be completed one to two feet into the shallow clay.  A horizontal perforated
pipe should be placed at the bottom of the trench with a sump, riser, and dedicated pump. The  trench
should be back filled with gravel such that the permeability of the fill is substantially greater than the
native sandy material.  The site team should also consider installing a geomembrane on the downgradient
edge of the lower half of the trench to further prevent DNAPL from migrating through the trench.
DNAPL migrating along the top of the clay or in stringers in the sand above the  clay should reach the
trench, migrate downward through the gravel, and collect at the bottom of the trench where it is gathered
in the perforated pipe and directed to the sump. Depending on the amount of DNAPL, recovery can occur
from regularly scheduled manual events or through automated pumping.  All attempts should be made to
avoid automated pumping due to the inconvenience of treating extracted water and storing extracted
DNAPL. If automated pumping is needed, DNAPL should be stored in a local AST to minimize potential
problems with conveying DNAPL over 1,000 feet back to the ACW site. There are two options for the
treated water:  treat the water near the point of extraction with a separate treatment system; or, pipe the
water back to the ACW treatment plant.  The most cost-effective solution is likely to pipe the water back
to the treatment system (over 1,000 feet through public right of ways).  Because the pipe will be buried
and difficult to replace, pipe that is resistant to naphthalene and other creosote compounds should be used,
such as 304 stainless steel.

Because of the open-ended nature of this recommendation, the RSE team has not provided a cost estimate
for implementation.
                                              21

-------
                                     7.-1   SUMMARY
The observations and recommendations contained in this report are not intended to imply a deficiency in
the work of either the system designers or operators, but are offered as constructive suggestions in the
best interest of the EPA and the public.  These recommendations have the obvious benefit of being
formulated based upon operational data unavailable to the original designers.

Recommendations are provided in all four categories: effectiveness, cost reduction, technical
improvement, and site closeout. Recommendations for effectiveness are primarily focused on reviewing
cleanup standards, considering the potential for vapor intrusion, revising the procedure for determining
the GAC replacement frequency, and evaluating options for stronger institutional controls.
Recommendations for cost reduction include revising the ground water monitoring program and reducing
overall labor once the system operation has stabilized. The technical improvement recommendations
include repiping the DNAPL line to avoid clogging. With respect to site closure, a strategy is provided
for improving the overall remedy.

Table 7-1 summarizes the costs and cost savings associated with each.  Both capital and annual costs are
presented.  Also presented is the expected change in life-cycle costs over a 30-year period for each
recommendation both with discounting (i.e., net present value) and without it.
                                               22

-------
                                Table 7-1.  Cost Summary Table
Recommendation
6.1.1 Continue Revisiting Soil
Cleanup Levels and ACLs
6.1.2 Consider Potential for Vapor
Intrusion
6.1.3 Revise Program for
Determining GAC Replacement
6.1.4 Evaluate Options to
Implement Stronger Institutional
Controls
6.2. 1 Revise the Ground Water
Sampling Program
6.2.2 Review Labor Costs Once
System Operation has Stabilized
6.3. 1 Repipe DNAPL Line from
Treatment Shed to DNAPL
Storage Tank
6.4 Modifications Intended to
Gain Site Closeout
Reason
Effectiveness
Effectiveness
Effectiveness
Effectiveness
Cost
Reduction
Cost
Reduction
Technical
Improvement
Site Closeout
Additional
Capital
Costs
($)
$0
$5,000
$0
$20,000
$0
$0
$1,000
Not quantified
Estimated
Change in
Annual
Costs
($/yr)
$0
$0
$3,000
$0,000
($40,000)
($40,000)
$0
Not quantified
Estimated
Change
in Life-cycle
Costs
($)*
$0
$5,000
$90,000
$20,000
($1,200,000)
($1,200,000)
$1,000
Not quantified
Estimated
Change
in Life-cycle
Costs
($)**
$0
$5,000
$48,400
$20,000
($645,600)
($645,600)
$1,000
Not quantified
Costs in parentheses imply cost reductions.
* assumes 30 years of operation with a discount rate of 0% (i.e., no discounting)
** assumes 30 years of operation with a discount rate of 5% and no discounting in the first year
                                                 23

-------
FIGURES
   24

-------
                                                                FIGURE 1-1. SITE PLAN.
                          TREATMENT   GIMBLE STREET
                            SHED       #3  AREA
                                                                         GIMBLE STREET
                                                                           #1  AREA
                                                                                                                                     -N-
                                                                                      GIMBLE STREET
                                                                                        #2  AREA
               GROUNDWATER
                EXTRACTION
                 SYSTEM
                                                               FORMER
                                                              RAILROAD
                                                            IMPOUNDMENT
LEGEND

AMERICAN CREOSOTE WORKS

MONITORING WELL  LOCATION

FENCE LINE

ROAD

VEGETATED AREA
                                                                                                                                           SOUTHEAST
                                                                                                                                             DITCH
           WEST
      RESIDENCE AREA
PYCDS-N     PENSACOLA
PYCDS-M    YACHT  CLUB
                            700
                            720^8i'<;i!,
PYCDS-S                      760
                               r  if i1

                                m
            PENSACOLA YACHT	if,','!,1 m
            CLUB DITCH          (( I1,'I', III
                              ? u i f j l! I
                              \ i];!!*i
                                                                                          SCALE IN FEET

                                                           (Note: Figure taken out of "Interim Long Term Monitoring Report", BEM, 2005)

-------
                                             FIGURE 1-2. NORTH SOUTH GEOLOGIC CROSS SECTION (BECHTEL, 1996)
    won in   ฃ/
    11-
    40-
   80--
   120-
   160
  200
                                                                                                                                        ^^^^^^1—f	ซ	g- y*f=a-VL-'g — -ป -yri
                    t  FORMER ACW WASTE PONDS  I
     LEGEND

       SAHO

Illllll  S1LTY SMiO

       CLAYEY SAND

   Tl  0-AY

  700   KLL MIM1ER

              IHICHVAt.
                  UPPER SMjjj
                        .
IJPPEH SAM), FIW

       SAM)
LOKH SAHO. I IM
in riv
                                      PERME ABILITY

                                 ^V.  VERTICAL
                                                                                    CD600
                                                                   TO 100'TD 100'        ซ
                                 3.    WATER LEVEL
                                      20 FT DEEP
                                      HELLS 2/81
                                                                                                                                                   WATER LEVEL
                                                                                                                                                   60 r DEEP
                                                                                                                                                   WELLS 2/81
          ID 200'
                                    	, — -7— -iflTOB
                                                                                          TO 200'
                                                           HORIZONTAL SCALE
                                                                IN FEET

                                                         0        200        400
                                                         I	1	1	1	1
                                                         0         40         80
                                                            VERTICAL SCALE
                                                                IN FEET
(Note: Figure originally generated by Bechtel, 1996, and extracted by the RSE team from the "SCAPS Investigation Report", USAGE, 2002.)

-------
                                  FIGURE 5-1. EXTENT OF SOIL EXCAVATION AND RESULTS OF SANDERS BEACH STUDY.
  MAP LEGEND
+  PROPOSED MW
 x.  PROPOSED SW
 ฎ  SAMPLE LOCATION
ACW EXTRACTION WELLS
ฎ  EXTRACTION WELL
 ฎ  MONITORING WELL

  ACW MW  LOGS
    DEPTH
ฉ  MW  <30 FT BGS
C  MW  30-70  FT BGS
Q  MW  >70 FT BGS
    DITCH
 A  NGS CONTROL
    PENSACOLA WOOD
    TREATING SITE
    DIOXIN LIMITS

    REMEDIAL
    PROPERTIES
                     (Note: This figure was provided to the RSE team by the Florida DEP.)

-------