REMEDIATION SYSTEM EVALUATION


HELLERTOWN MANUFACTURING COMPANY SUPERFUND SITE

             HELLERTOWN, PENNSYLVANIA

          Report of the Remediation System Evaluation,


  Site Visit Conducted at the Hellertown Manufacturing Superfund Site

                      JuneS, 2001
           Final Report Submitted to Region 3

                  November 14, 2001
                  I
                  5
\
 LU
 o

-------
                                        NOTICE
Work described herein was performed by GeoTrans, Inc. (GeoTrans) and the United States Army Corps
of Engineers (USAGE) for the U.S. Environmental Protection Agency (U.S. EPA). Work conducted by
GeoTrans, including preparation of this report, was performed under Dynamac Contract No. 68-C-99-
256, Subcontract No. 91517.  Mention of trade names or commercial products does not constitute
endorsement or recommendation for use.

This document (EPA 542-R-02-0081) may be downloaded from EPA's Technology Innovation Office
website at www.epa.gov/tio or www.cluin.org/rse.

-------
                             EXECUTIVE SUMMARY
The Hellertown Manufacturing Superfund Site, located in Hellertown, Pennsylvania 1.5 miles south of
Bethlehem, Pennsylvania, is approximately 8.6 acres and addresses trichloroethylene (TCE)
contamination of the groundwater resulting from operations of a former spark-plug manufacturing
facility.  The initial Remedial Investigation found that the primary sources of contamination are onsite
lagoons once used for containing process water laden with chemicals including TCE. The Record of
Decision required placement of an asphalt cap covering the former lagoon area and a pump-and-treat
system to address the groundwater contamination.  Construction of the asphalt cap was completed in
1994 and operation of the pump-and-treat system began in February 1996.

Groundwater TCE concentrations as sampled during November 2000 are an order of magnitude
lower than they were during the Remedial investigation nearly 10 years earlier.  In November 2000
TCE concentrations downgradient of the lagoons were as high as 190 ug/L. TCE concentrations
upgradient of the lagoons as high as 140 ug/L were also detected in November 2000 suggesting a
potentially uncharacterized source on site.

In general, the RSE team found a well-operated system.  Recommendations to improve system
effectiveness include the following:

•       An additional monitoring well downgradient of the site should be installed and sampled to help
        delineate the plume.  Water level measurements from this well would also help in generating
        a more accurate potentiometric surface downgradient of the extraction well thereby
        elucidating the extent of the capture zone.

•       The groundwater extraction system consists of a single well that is currently operating at 110
        gpm rather than the designed rate of 160 gpm.  A steady decrease from 160 gpm has been
        noticed since February 2000. Given that this well is solely responsible for containing the
        plume and extracting contaminated groundwater, the well and pump should be evaluated and
        possibly replaced.

•       Institutional controls and deed restrictions  are required by the Record of Decision and were
        mentioned in the five-year review. However, these controls have not yet been implemented.
        Institutional controls and deed restrictions should be implemented.

•       TCE concentrations of 140 ug/L upgradient of the lagoons suggest the possibility of another
        source area (likely associated with the old equipment washing area or with the old
        groundwater treatment system, which is still in place). An initial investigation using a
        GeoProbe to collect soil gas and water samples should be  conducted to better delineate this
        contamination.

These recommendations might require approximately $75,000 in capital costs and might increase
annual costs by approximately $5,000 per year.

-------
Recommendations to reduce life-cycle costs include the following:

•       Groundwater is extracted at approximately 150 gallons per minute with an approximate
        concentration of 40 ug/L.  This translates to a approximately 30 pounds of TCE extracted and
        treated per year.  Current annual costs for the system total approximately $130,000 per year
        (excluding analytical costs).  With a capital investment of approximately than $125,000 this
        cost could likely be reduced to approximately $110,000 per year if extracted water is treated
        only with liquid phase carbon. Furthermore, with this recommendation the treatment system
        process monitoring could be reduced, potentially saving an additional $10,000 per year.  Thus,
        with a potential savings of $30,000 per year, the site managers should consider replacing the
        current treatment system with liquid phase carbon treatment. However, a pilot test should be
        conducted prior to implementation to ensure carbon usage is as projected.

•       Regardless of revamping the treatment system, the building heat should be reduced.  The
        building is kept at 60 to 65 degrees Fahrenheit but only needs to be as high as 35 or 40
        degrees Fahrenheit to protect against freezing. This would save approximately $1,000 per
        year in costs for natural gas.

Finally, cleanup limits for the site have yet to be determined.  The Record of Decision mentioned that
if background levels are lower than the maximum contaminant levels, then background contaminant
levels or the detection limit would be the cleanup level. Such cleanup levels would be stricter than
those set at the large majority of Superfund  sites. The RSE team recommends that the cleanup levels
be established so that an exit strategy can be developed.

A summary of recommendations, including  estimated costs and/or savings associated with those
recommendations, is presented in Section 7.0 of the report.

-------
                                     PREFACE
This report was prepared as part of a project conducted by the United States Environmental
Protection Agency (USEPA) Technology Innovation Office (TIO) and Office of Emergency and
Remedial Response (OERR).  The objective of this project is to conduct Remediation System
Evaluations (RSEs) of pump-and-treat systems at Superfund sites that are "Fund-lead" (i.e., financed
by USEPA). RSEs are to be conducted for up to two systems in each EPA Region with the
exception of Regions 4 and 5, which already had  similar evaluations in a pilot project.

The following organizations are implementing this project.
           Organization
   Key Contact
        Contact Information
 USEPA Technology Innovation
 Office
 (USEPA TIO)
Kathy Yager
11 Technology Drive (ECA/OEME)
North Chelmsford, MA 01863
617-918-8362
yager.kathleen@epa.gov
 USEPA Office of Emergency and
 Remedial Response
 (OERR)
Paul Nadeau
1200 Pennsylvania Avenue, NW
Washington, DC 20460
Mail Code 5201G
phone: 703-603-8794
fax: 703-603-9112
nadeau.paul@epa.gov
 GeoTrans, Inc.
 (Contractor to USEPA TIO)
Rob Greenwald
GeoTrans, Inc.
2 Paragon Way
Freehold, NJ 07728
(732) 409-0344
Fax: (732) 409-3020
rgreenwald@geotransinc. com
 Army Corp of Engineers:
 Hazardous, Toxic, and Radioactive
 Waste Center of Expertise
 (USAGE HTRW CX)
Dave Becker
12565 W. Center Road
Omaha, NE 68144-3869
(402) 697-2655
Fax: (402) 691-2673
dave.j.becker@nwd02.usace.army.mil
                                          111

-------
The project team is grateful for the help provided by the following EPA Project Liaisons.
 Regionl   Darryl Luce and Larry Brill
 Region 2  Diana Curt
 Region 3  Kathy Davies
 Region 4  Kay Wischkaemper
 Region 5  Dion Novak
Region 6    Vincent Malott
Region 7    Mary Peterson
Region 8    Armando Saenz and Richard Muza
Region 9    Herb Levine
Region 10  Bernie Zavala
They were vital in selecting the Fund-lead P&T systems to be evaluated and facilitating
communication between the project team and the Remedial Project Managers (RPM's).
                                           IV

-------
                              TABLE OF CONTENTS
EXECUTIVE SUMMARY	 i

PREFACE	111

TABLE OF CONTENTS	 v

1.0 INTRODUCTION 	1
       1.1     PURPOSE  	1
       1.2     TEAM COMPOSITION	2
       1.3     DOCUMENTS REVIEWED	2
       1.4     PERSONS CONTACTED  	3
       1.5     SITE LOCATION, HISTORY, AND CHARACTERISTICS	3
              1.5.1   LOCATION 	3
              1.5.2   POTENTIAL SOURCES 	3
              1.5.3   HYDROGEOLOGIC SETTING	4
              1.5.4   DESCRIPTION OF GROUND WATER PLUME	4

2.0  SYSTEM DESCRIPTION	6
       2.1     SYSTEM OVERVIEW 	6
       2.2     EXTRACTION SYSTEM	6
       2.3     TREATMENT SYSTEM	6
       2.4     MONITORING SYSTEM  	7

3.0  SYSTEM OBJECTIVES, PERFORMANCE AND CLOSURE  CRITERIA  	8
       3.1     CURRENT  SYSTEM OBJECTIVES AND CLOSURE CRITERIA	8
       3.2     TREATMENT PLANT OPERATION GOALS	9
       3.3     ACTION LEVELS 	9

4.0  FINDINGS AND OBSERVATIONS FROM THE RSE SITE VISIT	10
       4.1     FINDINGS  	10
       4.2     SUBSURFACE PERFORMANCE AND RESPONSE	10
              4.2.1   WATER LEVELS	10
              4.2.2   CAPTURE ZONES	10
              4.2.3   CONTAMINANT LEVELS	11
       4.3     COMPONENT PERFORMANCE  	12
              4.3.1   EXTRACTION WELL AND PIPING 	12
              4.3.2   EQUALIZATION TANK	12
              4.3.3   PACKED TOWER 	12
              4.3.4   AIR COMPRESSORS/BLOWERS	12
              4.3.5   CARTRIDGE FILTERS	12
              4.3.6   EXTRACTION AND PROCESS PUMPS	12
              4.3.7   VAPOR PHASE GRANULAR ACTIVATED CARBON	13
              4.3.8   BUILDING AND UTILITIES  	13
              4.3.9   CONTROLS 	13
       4.4     COMPONENTS OR PROCESSES THAT ACCOUNT FOR MAJORITY OF MONTHLY COSTS	14
              4.4.1   UTILITIES  	14
              4.4.2   NON-UTILITY CONSUMABLES AND DISPOSAL COSTS	14
              4.4.3   LABOR 	14
              4.4.4   CHEMICAL ANALYSIS 	14
                                             v

-------
       4.5     RECURRING PROBLEMS OR ISSUES  	15
       4.6     REGULATORY COMPLIANCE	15
       4.7     TREATMENT PROCESS EXCURSIONS AND UPSETS, ACCIDENTAL CONTAMINANT/REAGENT
               RELEASES	15
       4.8     SAFETY RECORD	15

5.0  EFFECTIVENESS OF THE SYSTEM TO PROTECT HUMAN HEALTH AND THE ENVIRONMENT	16
       5.1     GROUND WATER	16
       5.2     SURFACE WATER	16
       5.3     AIR	16
       5.4     SOILS  	16
       5.5     WETLANDS AND SEDIMENTS 	16

6.0  RECOMMENDATIONS	17
       6.1     RECOMMENDED STUDIES TO ENSURE EFFECTIVENESS  	17
               6.1.1    ANALYZE CAPTURE ZONE FOR GROUND WATER EXTRACTION WELL 	17
               6.1.2    EVALUATE EXTRACTION WELL PRODUCTION  	17
               6.1.3    IMPLEMENT INSTITUTIONAL CONTROLS 	17
               6.1.4    EVALUATE OLD PRETREATMENT AREA	18
       6.2     RECOMMENDED CHANGES TO REDUCE COSTS 	18
               6.2.1    CONSIDER MODIFYING TREATMENT PROCESSES TO LIQUID-PHASE CARBON ONLY	18
               6.2.2    LOWER BUILDING TEMPERATURE TO LOWER UTILITY COSTS 	19
       6.3     MODIFICATIONS INTENDED FOR TECHNICAL IMPROVEMENT 	20
               6.3.1    STOP PERFORMING DATA VALIDATION	20
       6.4     MODIFICATIONS INTENDED TO GAIN SITE CLOSE-OUT  	20
               6.4.1    ESTABLISH CLEANUP GOALS FOR THE AQUIFER  	20
       6.5     UNUSED EQUIPMENT	20

7.0  SUMMARY	21
List of Tables

Table 3-1.       Maximum Contaminant Level for each Contaminant of Concern
Table 3-2.       Pennsylvania DEP Discharge Criteria for the Hellertown Site
Table 4-1.       TCE Concentrations
Table 7-1.       Cost Summary Table

List of Figures

Figure 1-1       Site layout showing the locations of the monitoring wells and the extraction well
Figure 1-2       Cross section of the geology underlying the Hellertown Manufacturing Superfund Site
                                              VI

-------
                                1.0 INTRODUCTION
1.1        PURPOSE

In the OSWER Directive No. 9200.0-33, Transmittal of Final FYOO - FY01 Superfund Reforms
Strategy, dated July 7,2000, the Office of Solid Waste and Emergency Response outlined a
commitment to optimize Fund-lead pump-and-treat systems. To fulfill this commitment, the US
Environmental Protection Agency (USEPA) Technology Innovation Office (TIO) and Office of
Emergency and Remedial Response (OERR), through a nationwide project, is assisting the ten EPA
Regions in evaluating their Fund-lead operating pump-and-treat systems. This nationwide project is a
continuation of a demonstration project in which the Fund-lead pump-and-treat systems in Regions 4
and 5 were screened and two sites from each of the two Regions were evaluated. It is also part of a
larger effort by TIO to provide USEPA Regions with various means for optimization, including
screening tools for identifying sites likely to benefit from optimization and computer modeling
optimization tools for pump and treat systems.

This nationwide project identifies all Fund-lead pump-and-treat systems in EPA Regions 1 through 3
and 6 through 10, collects and reports baseline cost and performance data, and evaluates up to two
sites per Region. The site evaluations are conducted by EPA-TIO contractors, GeoTrans, Inc. and
the United States Army Corps of Engineers (USAGE), using a process called a Remediation System
Evaluation (RSE), which was developed by USAGE. The RSE process is meant to evaluate
performance and effectiveness  (as required under the NCP, i.e., and "five-year" review), identify
cost savings through changes in operation and technology, assure clear and realistic remediation goals
and an exit strategy, and verify adequate maintenance of Government owned equipment.

The Hellertown Manufacturing Company Site was chosen based on initial screening of the pump-and-
treat systems managed by USEPA Region 3 as well as discussions with the EPA Remedial Project
Manager for the site and the Superfund Reform Initiative Project Liaison for that Region. This report
provides a brief background on the site and current operations, a summary of the observations made
during a site visit, and recommendations for changes and additional studies.  The cost impacts of the
recommendations are also discussed.

A report on the overall results from the RSEs conducted for this system and other Fund-lead P&T
systems throughout the nation will also be prepared and will identify lessons learned and typical costs
savings.

-------
1.2
TEAM COMPOSITION
The team conducting the RSE consisted of the following individuals:

      Frank Bales, Chemical Engineer, USAGE, Kansas City District
      Rob Greenwald, Hydrogeologist, GeoTrans, Inc.
      Lindsey Lien, Environmental Engineer, USAGE HTRW CX
      Doug Sutton, Water Resources Engineer, GeoTrans, Inc.
1.3
DOCUMENTS REVIEWED
Author
EPA Region III
Environmental Strategies
Corp.
Ecology and Environment,
Inc
Ecology and Environment,
Inc
CH2M Hill
Roy F. Weston, Inc
EPA Region III
EPA Region III
COM
CDM
CDM
Date
September 30, 1991
June 17, 1991
August 1994
June 1994
June 7, 1996
October 1998
January 27, 1999
August 1999
November 1999
April 2000 through
February 2001
March 23, 2001
Title/Description
Record of Decision
Draft Remedial Investigation Report
Hydrogeological Conditions Evaluation
Design Basis Report for Remedial Design
Activities
Construction Report
Design Review Results and
Recommendations
Scope of Work
Five Year Review
Draft Operation and Maintenance Plan
Monthly Discharge Monitoring Reports
Annual Operations and Maintenance
Report

-------
1.4       PERSONS CONTACTED

The following individuals were present for the site visit:

Frank Bales (USAGE) 816-983-3591 francis.e.bales@usace.army.mil
Kathy Davies (USEPAReg. 3) 215-814-3315 davies.kathy@epa.gov
Rob Greenwald (GeoTrans) 732-409-0344 rgreenwald@geotransinc.com
Cesar Lee (USEPA Reg.  3) 215-814-3205 lee.cesar@epa.gov
Lindsey Lien (USACE) 402-697-2580 lindsey.k.lien@usace.army.mil
Paul Nadeau (USEPA OERR) 703-603-8794 nadeau.paul@epa.gov
Bernice Pasquini (USEPA Reg. 3) 215-814-3326 pasquini.bernice@epa.gov
Jim Romig (CDM Federal) 610-293-0450 romigjm@cdm.com
Mindi Snoparsky (USEPAReg. 3)215-814-3316 snoparsky.mindi@epa.gov
Doug Sutton (GeoTrans) 732-409-0344 dsutton@geotransinc.com


1.5       SITE LOCATION, HISTORY, AND CHARACTERISTICS

1.5.1       LOCATION

The Hellertown Manufacturing Superfund Site is approximately 8.6 acres and is located on Main
Street (Route 412) in Hellertown, Borough, Northampton County, Pennsylvania. The remedy at the
site addresses contamination from the manufacturing of spark plugs which began at that location in
1918 and was discontinued in 1982.  The surrounding area is a combined residential and commercial
area approximately 1.5 miles south of Bethlehem, Pennsylvania. The site is bordered on the north by
Interstate 78, on the east by Main Street, on the south by private residences, and on the west by a
Conrail railyard. Saucon  Creek is located on the far west side of the railroad property approximately
600 feet from the western boundary  of the site.  The site layout is depicted in Figure  1-1.

The warehouse onsite was purchased by Paikes Enterprises, Inc. in 1988 and used as a warehouse.
The current property owner is Federal Mogul.

1.5.2       POTENTIAL SOURCES

During operations at the spark-plug plant from 1930 to 1976, five unlined discharge lagoons were
maintained to treat aqueous discharges.  Discharges consisted of various chemicals including sodium
and potassium nitrates and nitrites, alkaline wastes, cyanide, zinc, hexavalent chromium, and
trichloroethylene. In 1965 a wastewater treatment plant was added to the facility.  In 1971 this plant
was upgraded by installing sludge drying beds, and in 1976, the lagoons were backfilled.  A Remedial
Investigation was conducted from 1988 to 1991  to investigate the extent of contamination site. The
investigation did find soil  and groundwater contamination associated with the lagoons, especially
lagoon #4, but did not find significant contamination associated with underground storage tanks or an
equipment wash area also located at the site. The Remedial investigation was followed by a Record
of Decision  on September 30, 1991 specifying an asphalt cap, institutional controls, and a pump-and-
treat system. The asphalt cap covering the former lagoon area was completed in 1994. Elements of
the  wastewater treatment system and the sludge drying beds were left  in place.

-------
It is believed that contaminants including TCE infiltrated through the unlined lagoons into the aquifer.
The lagoons were dredged and backfilled, and soil samples indicated volatile organic compounds
(VOCs) at levels less than 1 mg/kg, with the highest concentrations found near lagoon 4 in the
northwest corner of the site.  The monitoring wells show that VOCs have been transported offsite in
groundwater toward Saucon Creek at levels that exceed MCLs.  In contrast to the findings of the
Remedial Investigation, it appears that the elements of the old wastewater treatment system or
equipment wash area may have been a potential source of TCE, because an overburden well
approximately 100 feet downgradient of those features (CSP-7)  had a TCE concentration of 140
ug/L in November 2000.  That well is located upgradient of the lagoons, which have historically been
interpreted as the primary source of groundwater impacts.

1.5.3      HYDROGEOLOGIC SETTING

Figure 1-2, taken from the Hydrogeological Conditions Evaluation, depicts the geologic units observed
at the site. This figure depicts a northwest-southeast cross section of the stratigraphic units and the
monitoring and extraction well locations. The site elevation ranges from approximately 320 feet
above mean sea level (MSL) in the east to approximately 280 feet MSL in the west. Beneath the
asphalt cap installed in 1994, the stratigraphy includes  10 feet of overburden and 30 feet of saprolite
and phyllitic schist overlaying fractured dolostone identified with the Tomstown formation.  A
sandstone layer 10 feet thick exists within the dolostone formation at a depth ranging from  80 to 100
feet below ground surface (bgs).

Two permanent zones of saturation are of concern at the site: an intermediate zone, existing 15 to 95
feet bgs occurring primarily in the weathered saprolite; and a deep zone, existing approximately 95 to
greater than 215 feet bgs occurring in the dolostone which is fractured and exhibits characteristics of
solution weathering and channelized flow. The saprolite acts as a semiconfining layer above the
deeper fractured and weathered zone. In both zones, water flows to the west-northwest toward
Saucon Creek although the Hydrogeological Conditions Evaluation suggests the presence of
significant vertical gradients responsible for transporting TCE to deeper elevations 295 feet bgs as
detected in CSP-24. Flow in the deep zone may continue beyond Saucon Creek before rising and
returning to discharge into the creek.

1.5.4      DESCRIPTION OF GROUND WATER PLUME

The plume consists primarily of TCE and cis-1,2 dicholorethylene, a degradation product of TCE.
The highest TCE concentration as measured during the November 2000 sampling event is  190 ug/L
and was measured in a sampled taken from monitoring well CSP-14, a shallow monitoring well
located immediately downgradient of the northwest corner of the site (specifically downgradient of
lagoon #4). Other shallow wells in the same area measured during the same sampling event have
concentrations of 150 ug/L, 80 ug/L, and 33 ug/L. A deep monitoring well located adjacent to these
wells but over 100 feet deeper had a concentration of 43 ug/L.  A single monitoring well screening the
overburden, CSP-7, which is located 100 feet downgradient of the old wastewater treatment plant
(upgradient of the lagoons), had a concentration of 140 ug/L in November 2000.  Another monitoring
well screening the shallow bedrock, CSP-10, also located upgradient of the lagoons, had a TCE
concentration of 27 ug/L and a DCE concentration of 42. The impacts at CSP-7 and  CSP-10 suggest
that at least a portion of the plume formed upgradient of the waste lagoons.

-------
TCE contamination in groundwater has migrated beyond the site boundary.  Unfortunately, there are
no monitoring wells between the wells near immediate site boundary and the wells near Saucon
Creek. Therefore, it is difficult to characterize the plume in that region, which is immediately
downgradient of the remediation well. Low concentrations in groundwater have historically been
found in the overburden along the eastern bank of Saucon Creek. For instance, CSP-16 has had
TCE as high as 6.3 ug/1 in 1999, although all other readings since 1996 have been below 5 ug/1 at that
well.  CSP-18, a shallow groundwater well near Saucon Creek, had TCE of approximately 50 ug/L in
1990 and 1993,  but all samples there have been "non-detect" since 1996. It should also be noted that
there are no wells near Saucon Creek immediately downgradient of well CSP-14, where highest
groundwater concentrations are observed. TCE has also been infrequently detected at very low
concentrations (2 ug/1 or less) in the deep groundwater zone, more than 1,000 feet to the west of
Saucon Creek (i.e., on the other side). It is not clear that those impacts are related to this site.

-------
                         2.0  SYSTEM DESCRIPTION
2.1        SYSTEM OVERVIEW

The remedy for the Hellertown Manufacturing Site specified in the ROD includes the following items:

•      placement of an impermeable cover over the entire former lagoon area;

•      surface water runoff controls;

•      groundwater extraction from one well located on-site, above-ground treatment (air stripping
       and cartridge filtration), and discharge to Saucon Creek;

•      long term groundwater monitoring; and

•      deed restrictions.

The site was covered with asphalt in December 1994, and construction completion of the
groundwater extraction well and treatment plant occurred in January 1996 with full time operation
beginning in February 1996. The plant was down for a period of 17 months while a new well was
installed to replace the original extraction well.


2.2        EXTRACTION SYSTEM

The extraction system consists  of one well, EW-1.  Originally installed in 1993 in the location of
former lagoon 4, EW-1 originally had a screened interval from 115.5 to 215.5 feet bgs (163 to 63 feet
MSL).  Although the well was  designed to pump 160 gallons per minute (gpm), it only yielded 90 gpm.
The well was replaced by a new well in 1998-1999, EW-1R, in the same approximate location with a
screened interval ranging from 84 to 219 feet bgs (199 to 63 feet MSL). The new well and pump are
designed to extract 160 gallons per minute (gpm), and although the well was  operated at
approximately 160 gpm for a while, in was observed in February 2000 to be cavitating at 160 gpm,
and flow rate has been periodically decreased in 10 gpm increments since then to the current rate of
approximately 110 gpm.


2.3        TREATMENT SYSTEM

According to the construction  report(CH2MHILL, 1996) the groundwater treatment system was
designed with a treatment capacity of 100 gpm, an influent concentration of 970 ug/L (or parts per
billion by mass), and an effluent concentration of 1 ug/L. However, it was stated many times during
the RSE site visit that the wells were designed to extract at 160 gpm, and the system is certainly sized
to handle at least that flow rate. The system consists of the following elements:

-------
       equalization tank,

       cartridge filters,

       air stripping tower,

       vapor phase granular activated carbon (GAC),

       and discharge piping to Saucon Creek.
The entire system is contained in a building heated by two boilers (which are also used to heat the
influent into the vapor phase GAC), and the interior piping for the water is insulated.  The system
allows remote operation. An operator/maintenance engineer visits the site twice each month, and an
auto dialer calls the plant engineer when the system shuts down.  The plant cannot be restarted
remotely.
2.4       MONITORING SYSTEM

The monitoring system consists of 30 groundwater monitoring wells, a portion of which are sampled
on a quarterly basis.  The November 2000 sampling event involved VOC analysis from four
overburden wells, 19 shallow wells, and four deep wells. In addition, semi-annually the surface water
and sediments from Saucon Creek are measured and the groundwater elevations from all 30
monitoring wells and the extraction well are measured.

Plant influent and effluent are measured twice per month and air influent and effluent for the air
stripper is sampled once every two months with a photo-ionization detector.

-------
   3.0  SYSTEM OBJECTIVES, PERFORMANCE AND CLOSURE
                                    CRITERIA
3.1
CURRENT SYSTEM OBJECTIVES AND CLOSURE CRITERIA
The goal as specified in the ROD is to restore the aquifer to either the maximum contaminant levels
(MCLs), which are listed in Table 3-1, or applicable State background concentrations, whichever is
more stringent. These State background levels were to be determined by sampling subsequent to the
ROD and before treatment began. If the contaminants of concern were not detected in background
samples, the detection limits are to be used as the cleanup levels.  The 5-year review authored in 1999
states that EPA has not yet determined background concentrations, and that "upon determining the
background concentrations...EPA, in accordance with the ROD, will determine the remediation goal
for this site".  These cleanup goals have not yet been formally stated in the site documents reviewed
by the RSE team.  Along with the MCLs, the detection limits for contaminants are provided in Table
3-1. The discharge criteria to Saucon Creek listed in Table 3-2.

        Table 3-1: Maximum Contaminant Level for each Contaminant of Concern
Contaminant
Benzene
Tetrachloroethylene
Trichloroethylene
Vinyl chloride
trans- 1,2 Dichloroethylene
cis-1,2 Dichloroethylene
MCL
(ug/L)
5
5
5
2
100
70
Detection
Limit
(ug/L)
0.20
0.03
0.12
0.18
0.10
0.12
Analytical Method
601/602
601/602
601/602
601/602
601/602
524.2

-------
         Table 3-2: Pennsylvania DEP Discharge Criteria for the Hellertown Site
Effluent Parameter
Benzene
Total BTEX*
Tetrachloroethylene
Trichloroethylene
Vinyl chloride
transl,2DCE
cisl,2DCE
Average
Monthly Cone.
(ug/L)
1
100
1
1
1
1
1
*all concentrations in microgram per liter (ug/
Average
Daily Cone.
(ug/L)
2
200
2
2
2
2
2
Instantaneous
Maximum
Concentration
(ug/L)
2.5
250
2.5
2.5
2.5
2.5
2.5
Measurement
Frequency
2/month
2/month
2/month
2/month
2/month
2/month
2/month
Sample
Type
Grab
Grab
Grab
Grab
Grab
Grab
Grab
)
3.2
TREATMENT PLANT OPERATION GOALS
The operational goal of the plant is to maintain effluent TCE concentrations below 1 ug/L, which
agrees with the design specifications of the plant and complies with the discharge permit for that
contaminant.
3.3
ACTION LEVELS
The action levels regarding plant discharge are noted above.  The five-year review states that
cleanup goals have not been established for this site.

-------
 4.0  FINDINGS AND OBSERVATIONS FROM THE RSE SITE VISIT
4.1        FINDINGS

The RSE team noted that the system is well maintained and not operated at an unusual cost. The
observations and recommendations given below are not intended to imply a deficiency in the work of
either the designers or operators, but are offered as constructive suggestions in the best interest of the
EPA and the public. These recommendations obviously have the benefit of the operational data
unavailable to the original designers.
4.2        SUBSURFACE PERFORMANCE AND RESPONSE

4.2.1      WATER LEVELS

The water levels in the monitoring wells are regularly monitored.  Water levels have been plotted by
CDM (e.g., CDM, 2000 Annual O&M Report) on line graphs to compare pre-pumping and post-
pumping water levels, to assess whether drawdown occurs due to pumping. The overburden wells
show little if any drawdown due to pumping. Many shallow bedrock wells show some drawdown due
to pumping, and those wells are typically near the extraction well (e.g., wells CSP-5A, CSP-5B, CSP-
6, CSP-12, CSP-13, CSP-14), while some are further away from the extraction well (CSP-11, CSP-
15, CSP-18). Shallow bedrock wells distant from the extraction well typically show little or no
drawdown associated with extraction, as expected. The three deep bedrock wells closest to the
extraction well also show drawdown due to pumping (CSP-5c, CSP-24, CSP-25). Deep bedrock
wells distant from the extraction well typically show little or no drawdown associated with extraction,
as expected.

Analysis of water level  data from October 1997 when pumping was not occurring reveals information
about vertical hydraulic gradients in the absence of pumping. Water levels from CSP-5A, CSP-5B,
and CSP-5C, which are located adjacent to each other and are vertically spaced 10 feet apart,
demonstrate an upward gradient in the absence of pumping. Likewise, CSP-6 and CSP-25, which are
also adjacent but separated vertically by 100 feet also suggest an upward gradient in the absence of
pumping.

4.2.2      CAPTURE ZONES

Although the water level analysis suggests that drawdown does occur due to pumping, that
observation does not define the capture zone of the extraction well. Capture zones are based on
hydraulic gradients, which are impacted not only by drawdown due to pumping, but also by
background hydraulic gradients.  A capture zone was interpreted from water level data collected
during the pumping test at the original extraction well (Ecology and Environment, 1994) that suggested
the capture zone would encompass the majority of the area associated with the former lagoons and
possibly the contamination associated with CSP-7. This former capture zone analysis did suggest that

                                           10

-------
contamination in the area of wells CSP-10 and CSP-11 likely would not be captured.  A more recent
interpretation of potentiometric surface was not evident in documents reviewed by the RSE team.

The November 2000 water levels provide sufficient information from the shallow bedrock wells to
suggest that groundwater in the shallow bedrock near wells CSP-12, CSP-13, CSP-14, and CSP-5A
is captured by the extraction well.  Data is too sparse to estimate groundwater directions and capture
in the overburden and the deep bedrock or in the shallow bedrock further from the extraction well.
Because no monitoring wells or water-level measurements exist for over 400 feet to the west
(downgradient) the extent of contamination and capture is unknown downgradient of CSP-12, CSP-
13, CSP-14, and CSP-5A.
4.2.3
CONTAMINANT LEVELS
Groundwater concentrations appear to be declining slightly at some wells, although TCE concentration
at many wells are still significantly higher than the MCL of 5 ug/1. It is significant to note that current
influent levels to the plant (30-40 ug/1) are significantly lower than the design influent concentration of
nearly 1,000 ug/1.

Table 4-1 presents TCE concentrations versus time at selected wells.

                               Table 4-1 TCE Concentrations
Date
1990
1993
Dec 1995
Dec 1996
Dec 1999
Nov2000
EW-1R
(extraction)
not
constructed
not
constructed
not available
not available
41.5 (avg)
26
CSP-14
(shallow)
420
220
199
180
192
190
CSP-25
(deep)
not
analyzed
310
152
94
60
43
CSP-6
(shallow)
310
350
226
120
59
80
CSP-13
(shallow)
700
150
184
170
220
150
CSP-12
(shallow)
390
110
149
200
45
33
CSP-7
(overburden)
180
240
141
90
99
140
Note that TCE impacts are observed in all three zones (overburden, shallow bedrock,and deep
bedrock).

As stated in Section 1.5.4, there are no monitoring wells between the wells near the immediate site
boundary and the wells near Saucon Creek.  Therefore, it is difficult to characterize the plume in that
region, which is immediately downgradient of the remediation well. It should also be noted that there
are no wells near Saucon Creek immediately downgradient of well CSP-14, where highest
groundwater concentrations are observed. Concentrations at well CSP-18, a shallow bedrock well
near Saucon Creek, had TCE at approximately 50 ug/1 in 1990 and 1993, but has been "non-detect"
since 1996.
                                             11

-------
4.3        COMPONENT PERFORMANCE

During the first two years of operation the plant had difficulties in meeting extraction flowrate and
discharge standards.  These items were addressed by Weston in 1998 by replacing the extraction well,
upgrading some system components (pumps, distributor plate in air stripping tower) and redoing control
logic for the plant.

4.3.1      EXTRACTION WELL AND PIPING

Since being replaced in 1998, the extraction well has performed well.  However, the flow rate has been
declining since February 2000, from 160 gpm to the current rate of approximately 110 gpm. The pump
is "hard-piped" with steel which requires heavy machinery to remove the pump. Therefore, it has not been
pulled to  check it with respect to deterioration.  The pump from the original well was available  for
inspection, and showed evidence of significant corrosion (pits, holes, slits, rust).

4.3.2      EQUALIZATION TANK

The 3,000-gallon equalization tank provides capacity for only fifteen minutes of storage.  The flow rate
out of the tank is controlled by the pump that forces water to the top of the air stripper. The plant runs
continuously, not in batch mode.

4.3.3      PACKED TOWER

The packed tower is 35 feet high with a packed bed depth of 24 feet. The water is distributed evenly
across  the packing with a  distribution plate.  The packing is jaeger plastic two inch Tri-packs.   No
corrosion or scaling problems have been identified.

4.3.4      BLOWER

One blower is utilized to provide forced air to the stripping tower. This unit is 7.5 hp and provides process
air at approximately 1,000 cfm.

4.3.5      CARTRIDGE FILTERS

Two parallel cartridge filters remove solids prior to entering the air stripping tower.  The relatively clean
and soft water at the site does not foul these filters. The operators have changed these filters only once
since they took over operation in 1999 and noted that they showed little sign of being fouled.

4.3.6      EXTRACTION AND PROCESS PUMPS

The pumps include a well pump (15 hp) and a process pump (7.5 hp) inside the building.  Both pumps have
been upgraded since 1998 renovations were performed. The process pump has not  shown excessive
wear. The pumping rate of the well pump, however, has declined from 160 gpm at installation to 110 gpm
at the time of the RSE— a decrease of 10 gpm in the pumping rate occurs every 5 to 6 months. This is
due to oscillations in the pumping rate and shaking in the piping that the operator addresses by throttling
back a valve to decrease the extraction rate by 10 gpm.
                                            12

-------
4.3.7      VAPOR PHASE GRANULAR ACTIVATED CARBON

Two vapor GAC units are on site.  The process air from the air stripper is heated to lower the relative
humidity and therefore increase carbon capacity. The units each contain approximately 2,000 pounds
of activated carbon. Because influent concentrations to the plant are lower than originally designed,
carbon changeout should be very infrequent. A simple calculation is provided below:

          Calculate of pounds of TCE per year in extracted groundwater and assume
                               100% removal by air stripper.

     150 gallons  40 ug  3.785  liters  10'9 kg   2.2 Ibs   1440 minutes   365 days  26 Ibs
     	x	x	x	x	x	x	=	
       minute     liter     gallon      ug      kg         day         year     year
                     Calculate pounds of vapor phase carbon per year:
                 5 Ibs of carbon    26 Ibs of contaminant   130 Ibs of carbon
                                • x
                Ib of contaminant           year                 year
Due to the low organic loading to the plant the lead unit should not require new carbon for 10 to 15
years.

4.3.8      BUILDING AND UTILITIES

The building encases the entire process including the air stripping tower.  The temperature in the
winter is maintained at 60 to 65 degrees Fahrenheit. The heat for the building and for the preheater
(for vapors prior to GAC unit) are provided by two separate boilers.  The operators are going to begin
a long term maintenance contract for upkeep and tuning of these units.

4.3.9      CONTROLS

The extraction well and plant are shut down for alarms including but not limited to low levels in the
extraction well, leaking in the piping, high water levels in the air stripper reservoir, low air through the
air stripper, or a high level in the building sump. The controls also allow for partial shutdown.  The
extraction well is shutdown when a high level is detected in the equalization tank and the feed pump is
shutdown when a low level is detected in the equalization tank.  The blower for the air stripper shuts
down if either of these signals last for longer than 30 minutes. Each alarm triggers an autodialer that
contacts the project engineer.
4.4       COMPONENTS OR PROCESSES THAT ACCOUNT FOR MAJORITY OF
           MONTHLY COSTS

The total annual cost of operations is estimated at $132,500 excluding analytical costs.  The annual cost
breakdown included labor (including project management) at $93,000, travel costs of $6,500, direct
costs (utilities and materials for sampling) of $33,000.  Laboratory analyses and data validation are

                                            13

-------
performed under the Contract Laboratory Program (CLP), and costs are not directly assigned to the
site and therefore not included in the annual cost estimate provided above.

It should be noted that the during the information survey conducted prior to the RSE, the estimated
costs for this site were $350,000 per year.  That number is also referred to in the 5-year review.
Reportedly the estimate of $350,000 per year has been used for the purpose of insuring that adequate
budget is available as a  contingency because  of maintenance issues in past years that have required
significant expenditure.

4.4.1       UTILITIES

Of the $33,000 spent on direct costs, approximately $15,000  is spent on electricity for running the
pumps  and $5,000 is spent on natural gas for heating the building and the air entering the vapor GAC.

4.4.2       NON-UTILITY CONSUMABLES AND DISPOSAL COSTS

The remainder of the direct costs are primarily spent on materials needed for the process monitoring
and quarterly sampling events.  There are no  disposal costs  that occur on a regular basis.  A reserve of
filter cartridges is available onsite, and because these filters infrequently require replace, additional
filters will not need to be purchased for a number of years.

4.4.3       LABOR

Labor,  including project management, accounts for 70% of the system costs.  The system is
maintained on a regular schedule by a subcontracted operator who is present at the site once every
two months.  In addition, process influent and effluent are sampled twice per month by the O&M
contractor. An operations and maintenance inspection along with sampling of the plant influent and
effluent are conducted by the project manager twice per month, and aquifer sampling and water level
measurements are conducted quarterly.

4.4.4       CHEMICAL ANALYSIS

The chemical analyses (for VOC's) performed are in accordance with the surface water  discharge
requirements from the State. It  should be noted that this data is being validated which is not a standard
procedure for long term monitoring at pump and treat sites.  As stated earlier, analyses are performed
under the CLP program, and those costs are not directly assigned to the site.
4.5       RECURRING PROBLEMS OR ISSUES

The most notable recurring problem is the decreasing flow from the extraction well. No notable
process problems have occurred. Unscheduled shutdowns have all been weather related. The boilers
have required excessive maintenance; therefore, the site is going to enter a boiler maintenance
contract to relieve this problem.
                                             14

-------
4.6       REGULATORY COMPLIANCE

Compliance with discharge standards was a problem early during operation of the plant. Upon
completion of upgrading the extraction well pump, process controls, process pump and distribution
system in the tower, the treated groundwater has met all discharge criteria.
4.7       TREATMENT PROCESS EXCURSIONS AND UPSETS, ACCIDENTAL
          CONTAMINANT/REAGENT RELEASES

The system has been shut down on several occasions.  These shutdowns have almost exclusively been
caused by power outages rather than any process problems.


4.8       SAFETY RECORD

No safety issues were apparent and no safety problems or accidents were reported to have
occurred in the past. There is a broken fence that was reported in the ROD, and the fence was still
found to be broken during the RSE visit.
                                       15

-------
   5.0  EFFECTIVENESS OF THE  SYSTEM TO PROTECT HUMAN
                    HEALTH AND THE ENVIRONMENT
5.1       GROUND WATER

Several monitor wells and piezometers are located on site. Some wells have shown marked decline in
site contaminants while others have shown little to no decrease in concentrations. It is not clear that
the source of contamination near CSP-7 of CSP-10 (upgradient of the lagoons) has been
characterized.  The capture zone of the extraction well has not been documented since extraction
began, and while there are monitoring wells near Saucon Creek, there are no monitoring wells
immediately downgradient of the most contaminated well (CSP-14) all the way to Saucon Creek.
5.2       SURFACE WATER

Surface water in the creek is sampled upstream and downstream of the outfall twice per year.  No
significant impacts have been observed.  TCE was detected at a very small concentration (estimated
at 1 ppb) in one surface water sample in July 2000.
5.3       AIR

Air emissions from the GAC units are sampled two times per month using a PID.  The loading to the
carbon units is minimal, and not likely to be any problem.
5.4       SOILS

Soils exposure was remedied by the asphalt cover that now covers the former lagoons and serves as a
parking lot.
5.5       WETLANDS AND SEDIMENTS

The sediments in the creek are sampled at several points up and downstream of the outfall twice per
year. Reportedly, minor detections of VOC's in sediments of Saucon Creek have been detected both
upgradient and downgradient of the treatment plant outfall.
                                          16

-------
                           6.0  RECOMMENDATIONS
6.1        RECOMMENDED STUDIES TO ENSURE EFFECTIVENESS

6.1.1      ANALYZE CAPTURE ZONE FOR GROUNDWATER EXTRACTION WELL

As stated in the five year review, the capture zone (EW-1R) needs to be further evaluated to
determine if EW-1R is containing the entire plume as designed. This should include development of
potentiometric surface maps with water levels indicated and interpreted capture zone superimposed.
A one-time effort of $5,000 is appropriate, plus an additional $3,000 per year thereafter for continued
capture zone evaluation on the basis of potentiometric surface maps.

Ideally, one or more monitoring wells in the shallow bedrock should be added between CSP-14 and
Saucon Creek, to allow increased resolution for water level evaluation as well as water quality
evaluation.  The ability to add one or more wells in that area may be hampered by access issues, as
well  as limitations due to steep slopes immediately west of CSP-14. To add one well should cost
approximately $20,000 in capital costs, and additional sampling and analysis of that well will be less
than  $2,000 per year.

6.1.2      EVALUATE EXTRACTION WELL PRODUCTION

The decrease in flow from the extraction well is a concern because it could adversely impact the
ability to maintain hydraulic control. Therefore, the pump should be removed and the pump and well
should be evaluated (although removing the pump is a difficult operation, it will need to be done). It is
suspected that this pump and screen are failing as did the previous extraction well.  It may be
necessary to also evaluate the screen with a downhole camera while the pump is removed. Chemical
analysis of the water will help identify the potential agents for fouling or corrosion.  Sampling should be
conducted from the extraction well for iron,  manganese, sulfur minerals and complexes, pH,
conductivity, sand/silt content, carbon dioxide, carbonate, bicarbonate, and major ions including calcium
and magnesium. The cost for analyzing all of these constituents in a single sample should be
approximately $200 per sample.  Cost for these combined evaluations should be less than $10,000.
The RSE team has not estimated cost for a replacement pump and/or replacement well.

6.1.3      IMPLEMENT INSTITUTIONAL CONTROLS

As required by the ROD and noted in the five year review, institutional controls are to be implemented
to prohibit the use of site groundwater for a drinking water or a domestic well.  Currently, this has not
be performed. Estimated cost for this activity is $15,000.

6.1.4      EVALUATE OLD PRETREATMENT AREA

Contamination in CSP-7 and possibly in CSP-10 needs to be further evaluated. The original Remedial
Investigation analyzed soil contamination near the CSP-7 and these samples showed low
concentrations of total VOCs around 50 ug/kg. That investigation, however, did not thoroughly
                                            17

-------
evaluate groundwater contamination. Current measurements of VOCs in the soil gas and groundwater
will help to more thoroughly evaluate and delineate contamination in this area.  The soil gas evaluations
would also be useful for evaluating whether or not soil gas concentrations are elevated across the
southern site boundary, in the vicinity of the frame dwelling.  Because groundwater is present above
the bedrock, a GeoProbe could be used to obtain soil gas and groundwater grab samples in
approximately 15 locations primarily around the former equipment washing area and waste water
treatment facility.  This evaluation, including hiring out a GeoProbe for two or three days and
conducting the analytical work could be accomplished for approximately $15,000. Additional
investigation would be based on results of those studies.

Given the location of present monitoring wells, it will be very difficult to determine if CSP-7 and the
surrounding plume in that vicinity are captured by the current extraction well.  The importance  of that
uncertainty will be more meaningfully evaluated after the extent of contamination in the vicinity of
CSP-7 and the old water treatment area is better understood, as per the recommendation described
above.
6.2       RECOMMENDED CHANGES TO REDUCE COSTS

6.2.1      CONSIDER MODIFYING TREATMENT PROCESSES TO LIQUID-PHASE CARBON ONLY

As discussed in Section 4.3.7, based on a pumping rate of 150 gpm and influent concentration of 40
ug/1, there is less than 30 Ibs of TCE removed each year from the groundwater. The design influent
concentration was much higher (nearly 1,000 ug/1).  It could be argued that the water extracted from
EW-1R could simply be discharged directly to the creek through the existing outfall. By the time that
water discharged to the creek, most of the TCE would have volatilized, and certainly after discharge to
the  surface water the rest would volatilize. However, EPA and the Pennsylvania Department of
Environmental Protection generally prefer remedies that reduce mass rather than transfer mass into
the  atmosphere. Therefore, a more palatable option would be to replace the current filter/air
stripper/vapor carbon system with a filter/liquid-phase carbon system.  Given that the filters do not
appear to be removing significant amounts of solids, clogging of the filters or carbon should not be
significant a problem.

Using a conservative estimate of 300 Ibs of liquid phase carbon to one pound of contaminant the
remedy would require 9,000 Ibs of carbon per year. At $2/lb, this would equate to $18,000 per year of
carbon. Two GAC units each containing 10,000 Ibs of carbon and aligned in series would provide over
15 minutes of contact time in each vessel, and the lead vessel would have enough carbon treat the
water for a year.  Water could be sampled after the primary unit to help determine when it needs
replacement and after the secondary unit to determine if the effluent concentration is below the
discharge criteria.  Due to chemical loading and potential fouling, the lead unit may require
replacement once a year. During this replacement, the secondary unit would become the primary unit,
and the replacement vessel would become the secondary unit.

The air stripper and the current vapor phase carbon units could be removed and the new liquid phase
carbon units could be plumbed into the current system after the cartridge filters. To avoid the costs of
heating the entire treatment plant, a small insulated room with a small electric heater could be
constructed within the current treatment building to house the cartridge filters and the new carbon
                                             18

-------
units. The heater would keep the small room at 50 degrees Fahrenheit during the winter thereby
discontinuing the need for the boilers that are currently used.

Under this scenario less labor and power would be required.  Although the electric heater would
require additional electricity; overall, the electricity would be  reduced because the 7.5 hp blower to the
air stripper could be removed. The boilers and the natural gas would be eliminated.  The visits by the
subcontracted operator once every two months could be eliminated and project management
associated with the subcontract and general maintenance issues could be reduced. In addition,
because of the simplicity of the system, someone locally could be hired to conduct site visits twice per
month and sampling of the process water.

It is estimated that these changes might require up to $125,000 to implement, but net savings in labor,
travel, and utilities costs  could be $22,000 per year or more.  Also, the proposed maintenance contract
for the boilers could be eliminated thus removing an expected additional cost.

With two  10,000-lb carbon units in series treating approximately 30 Ibs of contaminants  per year
(requiring a conservative estimate of 9,000 Ibs of carbon per year), it is reasonable to reduce the
frequency of site visits and  process monitoring.  Because the second carbon unit serves as a natural
backup to the first, a site visit that includes sampling of the process water once every month would
likely be sufficient.  If over time it is found that the carbon vessels are replaced  less frequently than
once per year, site visits and sampling of the process water could be reduced to once every two
months. If site visits and sampling of the process water is reduced to once per month, and these visits
are made by a local contractor, an additional savings of approximately $10,000 per year  could be
expected.

A comparison of the capital costs and the annual cost savings associated with this recommendation
suggests that life cycle savings would be realized after approximately 6 years of operation.  Therefore,
to realize substantial costs savings, this recommendation should only be implemented if system
operation  is expected to continue for 10 or more years.

Prior to  implementation,  a pilot test with 55 gallon drums of carbon could be conducted with a fraction
of the current extracted water (i.e., 11 gpm) to verify that actual carbon usage is similar to that
estimated  in this  recommendation.

6.2.2      LOWER BUILDING TEMPERATURE  TO LOWER  UTILITY COSTS

Under current operations, the building temperature is maintained at 60 to 65 degrees during the winter
months  even though the building is only manned a few days per month.  If the current treatment
process  is continued, the air stripping towers can operate at subfreezing temperatures. Therefore, it is
recommended that building  temperature be maintained around 35 to 40 degrees Fahrenheit.  This might
reduce heating costs by $1,000 year.
                                              19

-------
6.3       MODIFICATIONS INTENDED FOR TECHNICAL IMPROVEMENT

6.3.1      STOP PERFORMING DATA VALIDATION

The need to validate the monitoring data should be revisited as this step is typically only required for
site investigation and not for operation. This reduction in scope will save a nominal amount of money
(apparently these costs are not directly assigned to the site) and will allow quicker use of the collected
data.


6.4       MODIFICATIONS INTENDED TO GAIN SITE CLOSE-OUT

6.4.1      ESTABLISH CLEANUP GOALS FOR THE AQUIFER

The ROD states that cleanup goals will be the more stringent of the Federal MCLs or the background
concentration established by the State. These cleanup goals have not been formally established.
These goals should be established so that the closure criteria are clear and an appropriate exit strategy
can be developed.
6.5       UNUSED EQUIPMENT

No unused equipment was noticed at this site. If recommendations in Section 6.2.1 are implemented,
there may be some unused government equipment (filters, blower, pump, etc.).
                                        20

-------
                                    7.0  SUMMARY
In general, the RSE team found a smoothly running treatment system and a well-operated and
maintained site. The observations and recommendations mentioned are not intended to imply a
deficiency in the work of either the designers or operators but are offered as constructive suggestions
in the best interest of the EPA and the public.  These recommendations have the obvious benefit of the
operational data unavailable to the original designers.

Several recommendations are made to assure system effectiveness, reduce future operations and
maintenance costs, improve technical operation, and gain site close out. The recommendations to
improve effectiveness include investigations to help delineate the plume, and to evaluate the capture
zone of the current extraction well.  The recommendations for cost reduction include a potentially
simplified system consisting only of liquid-phase carbon.   Finally, clarification of cleanup goals is
recommended, since specific cleanup goals have not yet been established.

Recommendations, and estimated cost increases/decreases associated with those recommendations,
are presented in Table 7-1.
                                              21

-------
                                Table 7-1. Cost Summary Table
Recommendation
6.1.1 Delineate plume and
evaluate capture zone
6.1.2 Evaluate extraction
well and pump
6.1.3 Implement
institutional controls
6. 1 .4 Initial investigation
near CSP-7and old
treatment area
6.2.1
a) Switch to only
liquid-phase carbon
b) Further reduce process
monitoring
6.2.2 Reduce heating in
building (lower
temperature)
6.3. 1 Stop performing data
validation
6.4.1 Establish cleanup
levels
Reason
Effectiveness
Effectiveness
Effectiveness
Effectiveness
Cost
Reduction
Cost
Reduction
Technical
improvement
Site Close
Estimated Change in
Capital
Costs
$25,000
$10,000
$15,000
$25,000
$125,000
$0
$0
$0
Annual
Costs
$5,000
$0
$0
$0
($22,000)
($10,000)
($1,000)
$0
$0
Lifecycle
Costs*
$175,000
$10,000
$15,000
$25,000
($535,000)
($300,000)
($30,000)
$0
$0
Lifecycle
Costs**
$105,600
$10,000
$15,000
$25,000
($230,000)
($161,100)
($16,100)
$0
$0
Costs in parentheses imply cost reductions.
* assumes 30 years of operation with a discount rate of 0% (i.e., no discounting)
** assumes 30 years of operation with a discount rate of 5% and no discounting in the first year
                                               22

-------
FIGURES

-------
           FIGURE 1-1.  SITE LAYOUT SHOWING THE LOCATIONS OF THE MONITORING WELLS AND THE EXTRACTION WELL.
                 SCALE IN  FEET
(Note: This figure is adapted from Figure 2-1 from the Hellertown Manufacturing Company Site Hydrogeological Conditions Evaluation, Ecology and
Environment, August 1994.)

-------
          FIGURE 1-2. CROSS SECTION OF THE GEOLOGY UNDERLYING THE HELLERTOWN MANUFACTURING SUPERFUND SITE.


                                                                                            A'

                                                                OVERBURDEN -,
                                                                                                   POTENTIOMETRIC WATER  LEVEL
                                                                                                   FOR THE DEEP  AQUIFER  ZONE
(Note: This figure is taken from Figure 4-1 from the Hellertown Manufacturing Company Site Hydrogeological Conditions Evaluation, Ecology and
Environment, August 1994.)

-------

                                                             Solid Waste and
                                                             Emergency Response
                                                             (5102G)
542-R-02-008I
October 2002
vwwv.clu-in.org/rse
www.epa.gov/tio
U.S. EPA National Service Center
for Environmental Publications
P.O. Box 42419
Cincinnati, OH 45242-2419

-------