Unied States                                             EPA420-S-04-007
                        Pro!ectton                                          October 2004
       Transportation Conformity Rule Amendments for the New 8-hour
         Ozone and PM2 5 National Ambient Air Quality Standards and
                   Miscellaneous Revisions for Existing Areas;
                 Transportation Conformity Rule Amendments:
           Response to Court Decision and Additional Rule Changes

               Summary  of the July 1, 2004, Published Final Rule


Note: This document provides a summary of the various rule revisions included in EPA's July 1,
2004, transportation conformity final rule (69 FR 40004). The July 1, 2004, rulemaking
addresses: 1) transportation conformity under the new 8-hour ozone and PM2 5 air quality
standards; and 2) the March 2, 1999, conformity court decision that affected several provisions
of the rule.  The summary descriptions correspond with the individual preamble sections
included in the final rule.
Section III: Conformity Grace Period and Revocation of the 1-hour Ozone Standard
As discussed in this section of the final rule, conformity applies one year after the effective date
of EPA's initial nonattainment designation for the 8-hour ozone and PM25 air quality standards.
The rule provides information on how the one-year conformity grace period should be
implemented in new 8-hour ozone and PM2 5 areas, including multi-jurisdictional metropolitan,
donut and isolated rural areas.

This section also discusses the conformity impacts of EPA's April 30, 2004, final rule (69 FR
23951) that revokes the 1-hour ozone standard one year after the effective date of 8-hour ozone
nonattainment designations. In accordance with EPA's April 30, 2004, final rule, conformity for
the 1-hour ozone standard will no longer apply in existing 1-hour nonattainment and
maintenance areas once that standard and corresponding designations are revoked.

This section also describes when conformity will apply, or not apply, in areas with an Early
Action Compact (EAC).  See the conformity final rule and April 30, 2004, final rule for more
details on this issue.

Finally, this section describes  only minor revisions to the transportation conformity rule, since it
primarily discusses issues that are already in statute, or are affected by other rulemakings or
guidance.

Section IV: General Changes in Interim Emissions Tests
As discussed in this section, the final rule:
»•     Changes the previous conformity rule's references for "emissions reductions tests" to be
      "interim emissions tests;"
»•     Establishes 2002 as the baseline year for the baseline year interim emissions tests for the
      8-hour ozone and PM2 5 standards (i.e., for the "no-greater-than-2002" and "less-than-
      2002" interim emissions tests);

-------
»•      Allows certain areas to utilize a "build-no-greater-than-no-build" test, and does not
       require regional emissions analyses in years where the transportation projects and
       assumptions in the build and no-build scenarios are the same; and
»•      Specifies that higher classified ozone and CO areas must continue to meet both the build-
       less-than-no-build and less-than-baseline year test during the time period before SIP
       budgets are available.

Section V:  Regional  Conformity Tests in 8-hour Ozone Areas That Do Not Have 1-hour Ozone
SIPs
This section discusses the following rule changes:
»•      Once an 8-hour ozone area has adequate or approved 8-hour SIP budgets in place, those
       budgets must be used to demonstrate conformity.
»•      Prior to adequate or approved budgets:
       •       marginal and subpart 1 ("basic") areas can do either the build-no-greater-than-
              no-build test or the no-greater-than-2002 test.
       •       higher classified ozone (moderate and above) and CO (moderate with design
              value greater that 12.7 ppm and serious) areas  must continue to meet both the
              build-less-than-no-build and less-than-baseline year test, as stated above in the
              summary for Section IV.
»•      The final rule extends the 1-hour ozone flexibility for  conformity determinations that
       meet clean data area requirements to 8-hour ozone areas. See the conformity final rule
       for further details.
»•      Prior to a SIP submission, interim emissions tests and  regional emissions analyses in 8-
       hour ozone nonattainment areas must address both ozone precursors, nitrogen oxides
       (NOx) and volatile organic compounds (VOCs), unless EPA issues a NOx waiver for the
       8-hour  ozone  standard.

Section VI: Regional Conformity Tests in 8-hour Ozone Areas That Have 1-hour Ozone SIPs

This section describes the following rule changes:
»•      Once an 8-hour ozone area has adequate or approved 8-hour SIP budgets in place, those
       budgets must be used to demonstrate conformity.
»•      Prior to adequate or approved 8-hour ozone SIP budgets, all 8-hour areas with adequate
       or approved 1-hour ozone SIPs must use their 1-hour budgets for 8-hour conformity,
       unless it is determined through the interagency consultation process that using the interim
       emissions tests is more appropriate for meeting Clean  Air Act requirements (limited
       cases only, as described in preamble).
»•      The final rule discusses four different area boundary scenarios and how the budget test
       using 1-hour ozone budgets should be used to demonstrate conformity for the 8-hour
       ozone standard.  Conformity for the four area boundary scenarios must be demonstrated
       as follows:

       Scenario 1 - Where 8-hour and 1-hour ozone boundaries are the same, conformity  must
       generally be demonstrated by using the 1-hour ozone SIP budgets.

       Scenario 2 - Where the 8-hour ozone boundary is smaller than the 1-hour ozone
       boundary, conformity must generally be shown using one of the following versions of the
       budget  test:
       •       the budget test using the portion(s) of existing  adequate or approved 1-hour ozone
              SIP budgets that cover the 8-hour nonattainment area, where such portion(s) can
              be appropriately identified; or

-------
       •      the budget test using the existing adequate or approved 1-hour ozone SIP budgets
             for the entire 1-hour nonattainment area. Emission reductions must come from
             within the 8-hour ozone area.

       Scenario 3 - Where the 8-hour ozone boundary is larger than the 1-hour ozone boundary,
       conformity must generally be demonstrated using the budget test based on the 1-hour
       ozone SIP budgets for the 1-hour ozone area, plus the interim emissions test(s) for one of
       the following:
       •      the portion of the 8-hour ozone nonattainment area not covered by the 1-hour
             budgets;
       •      the entire 8-hour ozone nonattainment area; or
       •      the entire portion of the 8-hour ozone nonattainment area within an individual
             state, in the case where 1-hour SIP budgets are established for each state in a
             multi-state nonattainment area.

       Scenario 4 - Where portions of the 8-hour and 1-hour ozone boundaries overlap,
       conformity must generally be demonstrated using existing 1-hour budgets whenever
       feasible, plus the interim emissions test(s) for one of the following:
       •      the portion of the 8-hour ozone nonattainment area not covered by the 1-hour
             budgets;
       •      the entire 8-hour ozone nonattainment area; or
       •      the entire portion of the 8-hour ozone nonattainment area within an individual
             state, in the case where 1-hour SIP budgets are established for each state in a
             multi-state nonattainment area.
       If it is impossible to determine what part of a 1-hour ozone budget is  appropriate, a
       Scenario 4 area can use the interim reduction test(s) alone.

»•      For more information on the conformity test requirements in complex areas, see EPA's
       "Companion Guidance for the July 1, 2004, Final Transportation Conformity Rule:
       Conformity Implementation in Multi-jurisdictional Nonattainment and Maintenance
       Areas for Existing and New Air Quality Standards."  A copy of this guidance can be
       downloaded from EPA's transportation conformity website at,
       http://www.epa.gov/otaq/transp/conform/policy.htm

Section VII: Regional Conformity Tests in PM2; Areas
This section discusses the following rule changes:
»•      Once a PM2 5 area has adequate  or approved PM2 5 budgets in place, those budgets must
       be used to demonstrate conformity.
»•      Prior to adequate or approved budgets, PM2 5 areas can choose either the
       build-no-greater-than-no-build test or the no-greater-than-2002 test for direct PM2 5
       emissions and the relevant PM2 5 precursors that apply in a given area.

Section VIII: Consideration of Direct PM2; and PM2; Precursors in Regional Emissions
Analyses
As described in this section, the rule requires that directly emitted PM2 5  from motor vehicle
tailpipe, brake wear, and tire wear emissions must be considered in all conformity analyses.
This section also explains that EPA is not finalizing conformity requirements for PM2 5
precursors proposed in the November 5, 2003, rulemaking (68 FR 62690) in  this action. EPA
plans to finalize the requirements for PM2 5 precursors in a subsequent rulemaking before PM2 5
nonattainment designations are finalized.

-------
Section IX: Re-entrained Road Dust in PM2; Regional Emissions Analyses
This section discusses the following rule changes:
»•      Conformity analyses must include re-entrained road dust if a SIP establishes an adequate
       or approved PM2 5 budget that includes re-entrained road dust.
»•      Prior to adequate or approved budgets, re-entrained road dust must be included in
       conformity analyses only if EPA or the State air agency finds it to be significant.
»•      PM2 5 emissions may be adjusted to reflect the true impact of re-entrained road dust on
       regional air quality in accordance with EPA's future guidance on this issue.

Section X:  Construction-Related Fugitive Dust in PM2; Regional Emissions Analyses
This section discusses the following rule changes:
»•      Conformity must be demonstrated for construction-related fugitive dust if a SIP
       establishes an adequate or approved PM2 5 budget that includes construction-related
       fugitive dust.  Construction-related fugitive dust is not included in any PM2 5 conformity
       determinations before a SIP is submitted.
»•      PM2 5 emissions may be adjusted to reflect the true impact of construction-related fugitive
       dust on regional air quality in accordance with EPA's future guidance on this issue.

Section XI: Compliance With PM2; SIP Control Measures
As described in this section, FHWA and FTA projects in PM25 nonattainment and maintenance
areas are required to comply with the PM25 SIP's control measures, when such measures exist.
The final rule is similar to the current requirement for PM10 areas.

Section XII:  PM2; Hot-spot Analyses
This section explains that EPA is not finalizing any of the options for PM25 hot-spot analyses
proposed in the November 5, 2003, rulemaking (68 FR 62690) in this action. EPA plans to
request further public comment on these and other options for PM2 5 hot-spot analyses in a
subsequent rulemaking. EPA plans to finalize requirements for PM2 5 hot-spots before PM2 5
designations are finalized.

Section XIII:  PM10 Hot-spot Analyses
EPA is also not finalizing any of the options for PM10 hot-spot analyses proposed in the
November 5, 2003, rulemaking (68 FR 62690). EPA plans to request further public comment on
these and other options  for PM10 hot-spot analyses in a subsequent rulemaking. Existing
conformity rule PM10 hot-spot requirements continue to remain in effect.

Section XIV:  Federal Projects
The final rule amends the conformity regulations in response to the March 2, 1999, conformity
court decision that affected the procedures for advancing highway and transit projects during a
conformity lapse.  Consistent with the court decision, transportation projects may advance
during a conformity lapse as long as they have received the appropriate federal approvals before
the lapse. This rule revision is consistent with existing EPA and the Department of
Transportation (DOT) guidance; guidance implementing the March 2, 1999, court decision can
be downloaded from EPA's conformity website at,
http://www.epa.gov/otaq/transp/conform/policy.htm

Section XV: Using Motor Vehicle Emissions Budgets from Submitted SIPs for Transportation
Conformity Determinations
The final rule requires EPA to find SIP budgets adequate before they can be used in a conformity
determination. This rule revision is consistent with the March 2, 1999, conformity court
decision and existing federal guidance on this issue.  The rule also establishes EPA's existing
administrative process for determining whether SIP budgets are adequate for conformity

-------
purposes.  It also describes the process for determining the adequacy of budgets through the SIP
approval process and for changing a previous finding of adequacy or inadequacy.

Section XVI: Non-federal Projects
As discussed in this section, regionally significant non-federal projects cannot be advanced
during a conformity lapse unless they have received all necessary state and local approvals prior
to the lapse. This rule revision is consistent with the March 2, 1999, conformity court decision
and existing federal guidance on this issue.

Section XVII: Conformity Consequences of Certain SIP Disapprovals
The final rule changes the point in time at which a conformity "freeze" occurs when EPA
disapproves a control strategy SIP without a protective finding (i.e., deletes the previous rule's
120-day grace period before a conformity freeze occurs).  Under this rule change, a conformity
freeze occurs immediately upon the effective  date of EPA's final disapproval of a control
strategy SIP and its budgets if a protective finding is not made. During a conformity freeze no
new plans, TIPs or plan/TIP amendments can be found to conform.  This rule change is
consistent with the March 2, 1999, conformity court decision and existing federal guidance on
this issue.

Section XVIII:  Safety Margins
The final rule deletes a provision of the conformity regulations that had allowed areas with SIPs
submitted prior to November 24,  1993, to use existing safety margins for conformity without
EPA approval.  This rule revision is consistent with the March 2,  1999, conformity court
decision and existing federal guidance on this issue.

Section XIX: Streamlining the Frequency of Conformity  Determinations
This section discusses several changes to the conformity frequency requirements.  Specifically,
the final rule:
»•      Eliminates the requirement to determine conformity of the TIP within 6 months when
       conformity has been demonstrated for the transportation plan;
»•      Eliminates the requirement to redetermine conformity within 18 months of November 24,
       1993, the publication date of the first conformity rule;
»•      Specifies that the 18-month SIP approval trigger begins on the effective date of EPA's
       approval action;
»•      Streamlines the 18-month SIP approval trigger by  requiring a conformity determination
       only when the budgets in an approved SIP have not previously been used in conformity;
»•      Eliminates the 18-month trigger for SIPs and federal implementation plans that add,
       delete, or change a TCM.

Section XX: Latest Planning Assumptions
The final rule changes the point in the conformity process when the latest planning assumptions
are determined. The final rule allows conformity determinations to be based on the latest
planning assumptions that are available at the time the conformity analysis begins, rather than at
the time of DOT's conformity determination for a transportation plan, TIP or project. This
section clarifies the "time the conformity analysis begins," and provides details on how the final
rule should be implemented.

Section XXI: Horizon Years for Hot-spot Analyses
This section describes a clarification to the rule that project-level hot-spot analyses in
metropolitan nonattainment and maintenance  areas must consider the full time frame of the
area's transportation plan when the analysis is conducted. EPA does not expect this clarification
to change significantly how project-level analyses are being conducted in practice.

-------
Section XXII: Relying on a Previous Regional Emissions Analysis
As discussed in this section, the final rule:
»•      Allows MPOs to rely on a previous regional emissions analysis for minor transportation
       plan revisions.
»•      Adds the existing policy interpretation into the rule that a conformity determination that
       relies on a previous analysis does not satisfy the three-year frequency requirement for
       plans and TIPs.
»•      Clarifies that a conformity determination that relies on a previous regional emissions
       analysis must be based on all adequate and approved SIP budgets that apply at the time
       that DOT makes its conformity determination.

Section XXIII: Miscellaneous Revisions
In this section, EPA describes changes to the rule that streamline and improve the existing
conformity regulations, such as:
»•      Adding and revising definitions;
»•      Including existing limited maintenance plan and insignificance policies into the
       regulatory text;
»•      Providing a grace period for new models;
»•      Clarifying budget test requirements;
»•      Clarifying requirements for non-federal projects in isolated rural areas.

-------