EPA/ROD/R07-97/144
                                    1997
EPA Superfund
     Record of Decision:
     BEE CEE MANUFACTURING CO.
     EPA ID: MOD980860522
     OU01
     MALDEN, MO
     09/30/1997

-------

                   RECORD OF DECISION








              BEE  GEE MANUFACTURING SITE





                    MALDEN, MISSOURI
                      PREPARED BY:
    UNITED STATES ENVIRONMENTAL PROTECTION AGENCY





                       REGION VII





                  KANSAS  CITY,  KANSAS
                   SEPTEMBER 30,1997


-------
                    DECLARATION  FOR  THE  RECORD  OF DECISION

SITE  NAME AND  LOCATION

Bee Gee Manufacturing Site
Maiden, Dunklin County,  Missouri

STATEMENT OF BASIS  AND  PURPOSE

This decision document presents the remedial action selected  to  cleanup groundwater
contamination at the Bee Gee Manufacturing site  in Maiden, Missouri.   This remedial action
was chosen in accordance with the Comprehensive  Environmental Response, Compensation, and
Liability Act of 1980 (CERCLA), as amended by the  Superfund Amendments and Reauthorization
Act of 1986  (SARA)  and 40 C.F.R. Part 300,  the National  Contingency  Plan.  The decision is
based on the Administrative Record file for the  site.

The remedy selected is the same remedy that the  State  of Missouri presented in the Proposed
Plan.  The Proposed Plan was prepared by and approved  by the  state.  The remedy selected is
unchanged from that plan.

ASSESSMENT  OF  THE  SITE

Actual or threatened releases of hazardous substances  from the Bee Gee Manufacturing site, if
not addressed by implementing the response action  selected in this Record of Decision  (ROD),
may present an imminent and substantial endangerment to  public health, welfare, or the
environment.

DESCRIPTION OF  THE  SELECTED  REMEDY

The remedy selected to remediate contaminated groundwater  at  the Bee Gee Manufacturing site
is Natural Attenuation,  Groundwater Monitoring and Institutional Controls.  The preferred
remedy adeguately protects human health and the  environment from the risks posed by the site
because the contaminant plume is not likely to migrate off the Maiden  Industrial Park
property until the concentration of chromium in  the groundwater  is reduced below levels of
concern.  Additionally,  the area is served by Maiden's municipal water supply system.  This
eliminates any need for installing individual water supply wells at  or near the site.
Hexavalent chromium in the groundwater will attenuate  to concentrations below remediation
goals due to natural processes.  Institutional controls  will  be  reguired to prevent future
use of the groundwater in this part of the industrial  park and to warn potential purchasers
of the contamination.   Additional groundwater monitoring wells will  be installed to assess
the concentration and migration of the contaminant plume.

All federal and state applicable or relevant and appropriated regulations and reguirements
(ARARs) that will pertain to remedial action at  this site  will be complied with by this
alternative.

STATUTORY DETERMINATIONS

The selected remedy for the Bee Gee Manufacturing  site is  protective of human health and the
environment, complies with federal and state reguirements  that are legally applicable or
relevant and appropriate to the action for the site.   It is also cost-effective. This action
constitutes the final remedy for the site.   This remedy  utilizes permanent solutions and
alternative treatment technologies to the maximum  extent practicable for this site.  However,
because treatment of the principal threats of the  site was not found to be practicable, this
remedy does not satisfy the statutory preference for treatment as a  principal element.

-------
Eventually, there will be no hazardous substances above health-based levels remaining at the
site.  Within five years of installing the groundwater monitoring system,  EPA will conduct a
review to ensure that the remedy for the Bee Gee Manufacturing site is providing adequate
protection of human health and the environment.



-------
                           SEP 30 1997

MEMORANDUM

SUBJECT:  Record of Decision
          Bee Gee Manufacturing Site
          Maiden, Missouri

FROM:     Michael Sanderson
          Director, Superfund Division

TO:       Dennis Grams, P.E.
          Regional Administrator

     Attached for your signature is the Record of Decision  (ROD) for the Bee Gee
Manufacturing site located in Maiden, Missouri. The remedy presented in the ROD to address
groundwater contamination at the site includes natural attenuation, institutional controls,
and groundwater monitoring.

     The Bee Gee Manufacturing Company occupied the site from 1964 until 1983 and produced
aluminum moldings for storm windows and doors.  On-site disposal of process wastes resulted
in the contamination of soil and groundwater.  In 1992, the U.S. Environmental Protection
Agency  (EPA) conducted a removal action which included the removal of chromium-contaminated
soils and demolition of the building.

     This ROD selects natural attenuation, institutional controls, and groundwater monitoring
to address hexavalent chromium, the contaminant of concern in the groundwater.  The remedy
selected in the ROD is the same remedy presented by the State of Missouri in a Proposed Plan
issued during the public comment period conducted April 16, 1997, to May 16, 1997.


-------
MEMORANDUM

SUBJECT:    Record of Decision
            Bee Gee Manufacturing Site
            Maiden, Missouri

FROM:       Michael Sanderson
            Director, Superfund Division

TO:         Dennis Grams, P.E.
            Regional Administrator

     Attached for your signature is the Record of Decision  (ROD) for the Bee Gee
Manufacturing site located in Maiden, Missouri. The remedy presented in the ROD to address
groundwater contamination at the site includes natural attenuation, institutional controls,
and groundwater monitoring.

     The Bee Gee Manufacturing Company occupied the site from 1964 until 1983 and produced
aluminum moldings for storm windows and doors.  On-site disposal of process wastes resulted
in the contamination of soil and groundwater.  In 1992, the U.S. Environmental Protection
Agency  (EPA) conducted a removal action which included the removal of chromium-contaminated
soils and demolition of the building.

     This ROD selects natural attenuation, institutional controls, and groundwater monitoring
to address hexavalent chromium, the contaminant of concern in the groundwater.  The remedy
selected in the ROD is the same remedy presented by the State of Missouri in a Proposed Plan
issued during the public comment period conducted April 16, 1997, to May 16, 1997.

Attachment

SUPR:MCKS:Kovac:dulmer   Kinser Disk l-beecee.929 9/30/97
MOKS                          MOKS                SUPR
Kinser                        Kovac               Sanderson

-------
                               TABLE  OF  CONTENTS

Declaration of the Record of Decision

Decision Summary

Section                                                                 Page

1.0  SITE NAME, LOCATION, AND DESCRIPTION                                 1

2.0  SITE HISTORY                                                         2

3.0  PUBLIC PARTICIPATION IN THE REMEDY SELECTION                         5

4.0  SCOPE AND ROLE OF RESPONSE ACTION                                    5

5.0  SUMMARY OF SITE CONTAMINATION AND REMEDIAL ACTIVITIES                6

     5.1  REMEDIAL INVESTIGATION                                          6
     5.2  SOIL AND FACILITIES CONTAMINATION                               7
          5.2.1  REMOVAL ACTION                                           8
     5.3  GROUNDWATER CONTAMINATION                                       9
     5.4  SUMMARY AND RECOMMENDATIONS                                   10

6.0  SUMMARY OF SITE RISKS                                              10

     6.1  CONCLUSIONS                                                   13

7.0  REMEDIAL ACTION OBJECTIVES                                         14

8.0  DESCRIPTION OF ALTERNATIVES                                        14

     8.1  NO ACTION                                                     16
     8.2  NATURAL ATTENUATION                                           16
     8.3  ION EXCHANGE                                                  18
     8.4  REVERSE OSMOSIS                                               19
     8.5  ELECTROCHEMICAL PRECIPITATION                                 21
     8.6  CHEMICAL PRECIPITATION                                        22
     8.7  CONTAINMENT AND IN SITU REMEDIATION                           24

9.0  SUMMARY OF COMPARATIVE ANALYSIS OF ALTERNATIVES                    24

     9.1  OVERALL PROTECTION                                            25
     9.2  COMPLIANCE WITH ARARs                                         26
     9.3  LONG-TERM EFFECTIVENESS AND PERMANENCE                        26
     9.4  REDUCTION OF TOXICITY                                         27
     9.5  SHORT TERM EFFECTIVENESS                                      27
     9.6  IMPLEMENTABILITY                                              27
     9.7  COST                                                          28
     9.8  STATE ACCEPTANCE                                              28
     9.9  COMMUNITY ACCEPTANCE                                          28

10.0  SELECTED REMEDY                                                   28

-------
11.0  STATUTORY DETERMINATION                                             29

      11.1  PROTECTION OF HUMAN HEALTH  &  THE  ENVIRONMENT                 29
      11.2  COMPLIANCE WITH ARARs                                         29
            11.2.1  ACTION SPECIFIC ARARs                                29
            11.2.2  CHEMICAL SPECIFIC ARARs                               30
            11.2.3  LOCATION SPECIFIC ARARs                               30
            11.2.4  TO BE CONSIDERED                                      31
      11.3  COST EFFECTIVENESS                                            31
      11.4  UTILIZATION OF PERMANENT SOLUTIONS                            31
      11.5  PREFERENCE FOR TREATMENT                                      31

12.0  DOCUMENTATION OF SIGNIFICANT CHANGES                                32

FIGURE 1.  SITE LOCATION MAP                                              33

TABLE 1.  GROUNDWATER                                                     34

RESPONSIVENESS SUMMARY

-------
                                     RECORD  OF DECISION


                                       DECISION SUMMARY


1.0   SITE  NAME,  LOCATION,  AND  DESCRIPTION

1.1   SITE NAME AND  LOCATION

The Bee Gee Manufacturing facility is located in  the  town of Maiden, Dunklin County,
Missouri, in Township 23 North,  Range 10  East,  Section 28 (U.S.  Geological  Survey,  1978).
The site is located within the boundaries of the  Maiden  Municipal Airport and  Industrial
Park,  which was formerly a U.S.  Military  Base.

The site is located north of Harper Drive,  northeast  of  the former Bee Gee  Manufacturing
Company building (site facility) ,  and includes  an open field used by the Maiden Fire
Department as a training area.  A man-made ditch,  draining from west to east,  is  located
approximately 500 feet north of the site  facility.

This site covers approximately five acres and previously consisted of the metal plating
facility and a gravel-filled infiltration pit.  The foundation  of the manufacturing plant
remains onsite.  The gravel in the pit  has been removed  and the excavation  was backfilled
with clean soil.  Figure 1 shows the location of  the  site.

1.2   TOPOGRAPHY

Site elevations range from 290 feet above mean sea level (MSL)  to 293 feet  MSL.   The
topographic elevations of the site vary throughout, and  there does not appear  to  be one
particular surface drainage pathway.  The topographic relief is approximately  1.5 feet
(excluding the ditch north of the site).

The site is located physiographically in  the southeast Mississippi lowlands subdivision of
the Gulf Coastal Plain Province.   Most  of Dunklin County is a nearly level  part of  the
current Mississippi River Alluvial Plain.  The  surface soils in and around  Maiden consist of
generally loamy and sandy alluvium.  Levees constructed  along the major rivers and  a system
of flood control canals protect the county from flooding.  Some areas still experience
inundation during rainy seasons because of locally poor  drainage and level  topography.

Most of the regional surface-water drainage is  through a system of flood-control  canals. The
construction of these canals changed almost all of the Mississippi river delta area in
southeastern Missouri from a swamp to a major agricultural area by lowering groundwater
levels and providing surface drainage.  The drainage  system consists of a headwater diversion
canal, three detention basins in which  flood waters are  temporarily impounded, and  thousands
of miles of parallel,  lesser channels spaced at one mile intervals generally from west to
east.   This drainage system has reclaimed more  than 2,000,000 acres of southeast  Missouri
lowlands.

Regionally the surface-water drainage is  controlled by canals and tributaries  leading to the
Mississippi River.   The surface water generally drains from north to south  and then flows
east toward to the Mississippi River.  Surface  drainage  in the  immediate area  of  the site is
generally south to north, toward a drainage ditch on  the north  boundary of  the site.  Surface
water then flows under low gradient to  the east.

The alluvium is considered to be an aguifer (referred to in this report as  the "alluvial
aguifer"), and is approximately 100-150 feet in thickness in some areas.  It consists of
sand,  gravel,  silt and clay that were deposited by the Mississippi River and the  ancient Ohio
River and their tributaries.  The groundwater surface is generally about 10 feet  below the
ground surface.  Through the measurement  of groundwater  levels  in four of the  five  on-site

-------
monitoring wells, it was determined during field investigations that the upper-most alluvial
aguifer flow direction is toward the southeast.

1.3   ADJACENT LAND USES

The land within a guarter mile of the site is part of an industrial park.  While most of it
is vacant, some areas are used for small industrial plants and warehouse space.  The nearest
home is just over a guarter of a mile south of the site.  Maiden's municipal water supply
well No. 4 is located within one mile of the site.  Water from the site is not likely to
impact this well since it is side gradient from the site and is completed in an artesian
aguifer about 800 feet below ground surface.

2.0   SITE HISTORY

Bee Gee Manufacturing occupied the site from 1964 until early 1983 and produced aluminum
moldings for storm windows and doors.  The window and door moldings were cleaned and etched
in preparation for application of a finishing coat of paint.  A series of five open vats were
used to hold cleaning, etching and rinsing fluids.  The aluminum moldings were dipped from
one tank to another during the manufacturing process.  The chemicals in the various vats were
identified under the trade names Alodine 4780 and Ridoline 72.

Waste liguid from the process was allowed to flow through a series of pipes directly onto the
surface soil immediately north of the east end of the facility.  Personnel from the Water
Pollution Control Unit of the Missouri Department of Natural Resources'  (MDNR) Southeast
Regional Office reported chromium wastes on the surface at the site during an investigation
conducted July 13, 1981.  In a letter from MDNR dated July 27, 1981, Bee Gee Manufacturing
was warned to cease the discharge of untreated process water.

Bee Gee Manufacturing declared bankruptcy in 1983, and the site was taken over by Missouri
Aluminum Products Company.  This company cut and assembled storm doors, but did not include
chemical cleaning of aluminum in the process as did Bee Gee Manufacturing.

Falcon Door and Window  (Falcon)  next occupied the site.  Falcon only assembled aluminum door
and window frames and did not generate any hazardous wastes from their process.  According to
a bill of sale dated April 15, 1985, Falcon Communications purchased certain assets from
Missouri Aluminum Products Company.  The vats were not purchased by Falcon.  However, Falcon
arranged to have the material that remained in the tanks removed.

The contents of the five vats was sampled and analyzed by William A. Green and Associates
(WAGA) of Maiden, Missouri, for pH, hexavalent, trivalent and total chromium, aluminum,
nickel, and lead to determine compliance with discharge reguirements to the local Publicly
Owned Treatment Works (POTW).  According to a Falcon letter to MDNR dated December 20,  1985,
the Maiden Board of Public Works authorized discharging the contents of vats one, two,  four,
and five, to the POTW provided that the pH was adjusted to between 6 and 9 prior to
discharge.

The sludge in the four vats was removed.  However, the vats were left in place.  A
recommendation was made for the chromic acid solution in vat three, to be removed by a
hazardous waste disposal company.  Falcon Door and Window reguested authorization from MDNR
for removal of the waste material contained in the tank.

According to a letter written by WAGA to Falcon on March 20, 1986, Mid-America Transport
Services, a licensed hazardous waste transporter, removed, and transported the chromic acid
solution.  According to the letter, the tank walls were rinsed; however, a small amount of
aluminum solution and less than one gallon of rinse water remained on the tank bottom.   The
chromic acid solution was transported to Chem Clear, Inc., in Chicago, Illinois, on March 20,
1986, as stated in a copy of the Uniform Hazardous Waste Manifest.

-------
During the time that the building was occupied by the various tenants, several sampling
events and evaluations of the groundwater  (from nearby wells),  soil, and "sludge" at the site
were conducted.  The MDNR Division of Environmental Quality Laboratory Services Program
collected samples from the following four sources:  (1) selected city wells;  (2)  liguid
discharge from a pipe extending out of and onto the north side of the building (from the area
of the building that contained the chemical cleaning process vats);  (3) discolored soil north
of the building; and (4) the five process vats.  Water samples were also collected by the
Missouri Department of Health (MDOH)  at several nearby residential, irrigation, and public
water supply wells from 1984 to 1991.  Southeast Missouri State University conducted a
test-pit survey at the site in 1986.

A report prepared by MDNR on June 27, 1984, indicated that the sludge north of the building
was sampled and analyzed according to the Toxicity Extraction Procedure (TEP).  The reported
chromium concentration was 2.5 milligrams per liter (mg/1).  According to the report, the
regulatory TEP Limit for chromium was 5.0 mg/1.  The discharge liguid from the building was
also analyzed and found to have a chromium concentration of 0.62 mg/1.  Several wells located
near the site were also sampled; however, only three metals  (aluminum, barium, and lead) were
detected at concentrations which were above their associated detection limit.  Aluminum and
chromium were each detected at concentrations above detection levels at a residential well
with concentrations at 1.0 and 0.032 mg/1, respectively.  Samples taken from the two wells at
the nearby golf course had concentrations of barium above the detection level.

Seven city wells were monitored from March 1984 to September 1991 by MDOH.  The groundwater
analytical data from samples taken from those wells indicated no concentrations of chromium
above the detection limit of 0.005 mg/1.

A preliminary removal assessment was conducted by the Environmental Protection Agency (EPA)
on February 12, 1992.  The Bee Gee Manufacturing building interior and exterior were
inspected for future removal procedures by representatives of EPA and MDNR.  The potential
source area for chromium contamination was the soil north of the east end of the metal
treating facility where chemical-process liguids were disposed. The soils in this area were
sampled in April 1992,  approximately 40 soil samples were collected for analysis.

The EPA approved an Action Memorandum For the Removal of Contaminated Surface Soil at the Bee
Gee Site on July 1, 1992.  The action level for the soil was set at 2000 milligrams per
kilogram (mg/kg) for total chromium and 180 mg/kg for hexavalent chromium.  The scope of the
removal included contaminated soil and the portion of the Bee Gee Manufacturing building that
contained five vats used for metal plating processes.

On July 27, 1992, EPA's on-scene coordinator (OSC) mobilized to the site.   Removal of the
contaminated soil and process tanks and portions of the building was completed on August 20,
1992.

Following listing of the site on the National Priorities List  (NPL) in 1991, a Remedial
investigation  (RI) of the site was conducted.  Parts of this investigation occurred
concurrently with the Removal Investigation and Removal Action.  Later, a Further
Investigation of Groundwater (FIG) was conducted.  Both investigations were conducted to
better define the contamination of the site.  Field activities for the RI were conducted from
April 13 through 24, and June 8 through 12, 1992.  Field activities for the FIG were
conducted from April 12 through April 17, 1993.

Based on conclusions and recommendations contained in the RI, FIG and Risk Assessment, a
Feasibility Study  (FS)  was ordered.  The FS was completed in October 1994.  Information from
the FS was used to select the most appropriate remedy for the remediation of the contaminated
groundwater at the Bee Gee site.  This selection was detailed in the Proposed Plan, which was
completed and released for public comment in April 1997.

-------
3.0   PUBLIC PARTICIPATION IN THE  REMEDY  SELECTION

The FS and Proposed Plan, which were included as part of the Administrative Record (AR),  were
made available to the public at the Maiden Public Library and at the offices of EPA in Kansas
City, Kansas, and at the MDNR in Jefferson City, Missouri.   The notice of availability for
the AR and the announcement of a public meeting held on May 1,  1997, was published in the
Maiden Democrat.  The public comment period was held from April 16,  1997, to May 16,  1997.
At the public meeting,  representatives from the MDNR and the EPA received public comments and
answered guestions about problems at the site and the remedial  alternatives under
consideration.  A response to the comments received during this period is included in the
Responsiveness Summary, which is part of this Record of Decision (ROD).

This decision document presents the selected remedial action for the Bee Gee Manufacturing
site in Maiden, Missouri.  This remedy was selected in accordance with the Comprehensive
Environmental Response, Compensation, and Liability (CERCLA) Law of 1980, as amended by the
Superfund Amendments and Reauthorization Act (SARA)  of 1986, and to the extent practicable,
the National Contingency Plan (NCP). This decision is based on  the Administrative Record  for
this site.

4.0   SCOPE  AND ROLE  OF  RESPONSE ACTION

The response action selected in this ROD will address the contamination at the site not
addressed during the prior removal action.   This response action involves monitoring and
attenuation of hexavalent chromium-contaminated groundwater.  It also involves enacting
institutional controls to restrict access to contaminated groundwater at the site. The
contaminant plume is estimated to be 400 feet long by 400 feet  wide, with a maximum depth of
25 feet.   The plume is estimated to have traveled 438 feet from the point of release.
Analytical results of groundwater samples from the site indicate the on-site presence of
total chromium at levels above current water guality standards. Hexavalent chromium has been
detected at levels that do not exceed current water guality standards;  however,  these
concentrations are in excess of the risk-based level calculated by the MDOH.  Analytical
results also indicate the presence of arsenic at concentrations above current groundwater
guality standards, but sampling results from the background well indicate these levels of
arsenic may represent naturally occurring concentrations.

5.0   SUMMARY  OF  SITE  CONTAMINATION  AND REMEDIAL ACTIVITIES

5.1   REMEDIAL INVESTIGATION

Following listing of the site on the National Priorities  List,  a RI of the site was
conducted.  Field activities for the RI at the Bee Gee site were conducted from April 13
through 24, and June 8 through 12, 1992.  Groundwater at  the site was evaluated during both
field investigation episodes.  Site field investigation activities included:

    •   Conducting soil sampling,  including x-ray fluorescence (XRF)  on-site screening of
       surface soil and "slam bar"  (sample driving method)  core sampling;

    •   Conducting a groundwater sampling cone penetrometer  (geoprobe)  survey to optimize  the
       location of the planned monitoring wells;

    •   Installation of groundwater monitoring wells to collect  groundwater samples for
       chemical analysis;

    •   Measuring groundwater elevations in all  monitoring wells within a 24-hour period;

    •   Conducting a pumping test to evaluate the hydraulic connection between the deep aguifer
       (city wells),  the shallow aguifer (deep monitoring well)  and the  upper-most alluvial
       aguifer (shallow monitoring wells);

-------
    •   Conducting three slug tests on three monitoring wells (MW-3,  MW-4 and MW-5)  to evaluate
       the hydraulic properties (hydraulic conductivity)  of the upper-most alluvial aguifer;

    •   Conducting a site survey to locate all monitoring wells, soil sample locations,  and
       sampling cone penetrometer locations, both horizontally and vertically,  and tying them
       into the Missouri State Plane Coordinate System;

    •   Air samples were also collected for seven days over a ten-day period; and

    •   In addition to the soil sampling,  sediment samples were collected from the ditch north
       of the site.

Additional field investigation activities  (Further Investigation of Groundwater  (FIG))  were
conducted from April 12 through 17, 1993.  Site field activities included:

    •   Conducting a groundwater geoprobe survey to evaluate the extent of groundwater
       contamination in the upper-most alluvial aguifer and evaluate whether or not the
       shallow aguifer has been impacted by chromium contamination emanating from the site;

    •   Installing five (5) temporary sand points (piezometers)  to collect groundwater samples
       for chemical analysis and evaluating the groundwater gradient and flow direction;

    •   Measuring groundwater elevations in all monitoring wells and the sand points within a
       24-hour period to evaluate the gradient and groundwater flow direction;

    •   Conducting a site topographic survey to locate all additional geoprobe and sand point
       locations, and tying them to the Missouri State Plane Coordinate System; and

    •   The collection of groundwater samples for chemical analysis from the five (5)
       monitoring wells which were installed during the initial field investigation.

5.2   SOIL AND FACILITIES  CONTAMINATION

The potential source area for chromium contamination was the soil north of the east end of
the metal treating facility where chemical-process liguids were disposed.  The soils in this
area were sampled in April 1992, and were evaluated by the collection of 40 soil samples at
depths of 0-3, 3-6, 6-9, 9-12, 12-18, 24-36, 36-48, and 48-54 inches below ground surface.
During the RI, the soils were tested for total metals, soil pH, cyanide, and hexavalent
chromium.  In addition, four samples were tested for toxicity characteristic leaching
procedure (TCLP) metals.  The hexavalent chromium was analyzed by SW 846 Method 7196 A
following TCLP extraction.

A visibly stained surface area adjacent to the building footprint that contained the process
tanks was considered the contamination zone.  Prior to the RI activities, EPA performed a
screening survey using an XRF spectrometer to study the areal and vertical extent of chromium
contamination at the facility.  A slam bar was used to retrieve samples at depths below the
ground surface.  Nine locations were analyzed at three-inch intervals with the XRF.  Chromium
contamination extended to 30 inches below the ground surface at some locations.  The XRF
study indicated a larger area of surface contamination than indicated by visible staining
(E&E, 1992).

The Technical Assistance Team  (TAT) of Ecology and Environment, Inc., was tasked by EPA to
provide technical support in conjunction with potential removal activities at the site.
TAT's technical support included screening the soil with an XRF Spectrometer, confirmation
soil sampling, analytical laboratory procurement, contractor monitoring, and site
documentation  (E&E/TAT, 1992).

A preliminary removal assessment was conducted by EPA on February 12, 1992.  The XRF chromium
model was developed by calibrating laboratory analyses of six samples from the February 12,

-------
1992, field investigations with XRF measurements.  The soil samples represented surface,
subsurface and residual waste from inside the Bee Gee Manufacturing building.  Total chromium
concentrations were measured in the range of 7.24 to 24,100 mg/kg in surficial soils (0 to 3
inches).

The EPA assisted with the RI by conducting soil screening with the XRF Spectrometer which had
been calibrated for total chromium during the initial field investigation in February 1992.
The results from the screening were used to identify the contaminated zones.  If the
concentration of total chromium egualed or exceeded 200 mg/kg in the surficial soil of an
area, it was designated as a contaminated zone.  A 10- by 10-foot grid pattern was used for
the initial testing.  Isoconcentration maps were created to delineate specific areas of
chromium contamination with sampling locations.  Field measurements showed that there was
contaminated surficial soil further to the east than was initially anticipated.  Therefore, a
20-foot extension was added to the eastern border of the grid.

Beginning June 9, 1992, sampling of the monitoring wells, slug tests, and a deep and alluvial
interconnectivity test were conducted.  At this time, the Bee Gee Manufacturing building
interior and exterior were inspected for future removal procedures by EPA and MDNR.

The EPA collected four additional soil samples that were analyzed for total chromium,
hexavalent chromium, and Toxicity Characteristic Leaching Procedure  (TCLP)  chromium analyses.
The results of the analyses indicated that, although high levels of total chromium were
detected in the soil, the levels of hexavalent chromium were guite low. The hexavalent
chromium ranged from <1.5 - 10.7 mg/kg and the total chromium ranged from 4,080 - 23,100
mg/kg (E&E, 1992).  The TCLP level did not exceed 5.0 mg/1 of total chromium, which is the
Resource Conservation and Recovery Act (RCRA) regulatory level for chromium-contaminated soil
to be classified as a hazardous waste.

5.2.1  REMOVAL ACTION

The EPA approved an Action Memorandum For the Removal of Contaminated Surface Soil at the Bee
Gee site on July 1, 1992.  The action level for the soil was set at 2000 mg/kg for total
chromium and 180 mg/kg for hexavalent chromium.  The scope of the removal included
contaminated soil and the portion of the Bee Gee Manufacturing building that contained five
vats used for metal plating processes.

On July 27, 1992 , EPA's on-scene coordinator  (OSC) mobilized to the site.   The building's
siding was sampled for asbestos content analysis.  Several containerized products remaining
in the building were put into an inventory.

The analytical results from the asbestos samples showed that the siding on the building
contained 40 percent chrysotile asbestos.  Therefore, it was necessary to complete an
asbestos abatement project as part of the removal.  Thirty-eight plastic bags  (approximately
3.26 cubic yards) of asbestos-containing material were removed from the exterior of the
building and disposed of as special waste.

On August 3, 1992, EPA began the removal of the vats inside the building.  Demolition of the
building began and was completed on August 5, 1992.  The EPA collected three soil samples
from underneath the concrete pad of the building.  The samples were submitted for total
chromium, hexavalent chromium, and TCLP chromium analyses. The soil used to backfill the
building excavation was obtained from an off-site location. It was analyzed for heavy metal
contamination before it was placed at the site.

On August 8, 1992, EPA completed the demolition of the various scrap metal parts and vats.
On August 10, 1992, a salvage operator removed two loads of scrap steel from the site.   A
total of 17 truckloads (62 tons) of debris from the building demolition was disposed of
offsite as special waste.

The contaminated surficial soil at the Bee Gee Manufacturing site was divided into fourteen
sections, ranging in area from 1,200-4,800 sguare feet (ft#),  which would be removed and

-------
sampled for verification.  The EPA excavated sections of soil with three to six-inch lifts,
followed by confirmation screening with the XRF.  RES began loading soil from Section 1
(south of the Bee Gee Manufacturing building) on August 12, 1992.  The soil was also
considered a special waste, transported by the same waste hauler, and deposited in the same
landfill as the building debris.

During the excavation of the soil, EPA uncovered a 14 foot x 27 foot x 6 foot gravel pit in
the contaminated zone.  The gravel appeared to have been used during Bee Gee's operation to
facilitate percolation of the wastewater discharge from the facility.  The gravel was
excavated and disposed of along with the soil.  A total of 26 truckloads (356 tons)  of soil
were removed.  Thirty seven (37) loads of backfill were delivered and placed at the site.

The backfilled area of the site was seeded and covered with straw.  A cement block wall was
constructed to enclose the east end of building.  Site restoration was completed on August
20, 1992.  All containerized materials were either shipped back to the manufacturer, land
filled, or recycled.

5.3   GROUNDWATER  CONTAMINATION

Based on slug tests conducted on monitoring wells completed in the upper-most alluvial
aguifer, a hydraulic conductivity range of 3 to 13 ft/year was calculated  (SvE, 1993b). The
observed hydraulic gradient across the site was approximately 0.001 ft/ft.   Based on these
values and an estimated effective porosity of 0.35, an average linear flow velocity of 0.009
to 0.04 ft/day can be calculated.

An approximation of the distance from the chromium plume to its outer edge can be calculated
by considering that the distance down gradient from the source to the leading edge or
chromium plume is egual to the average linear groundwater velocity multiplied by the
estimated time since chromium entered the groundwater, assuming the hydraulic properties of
the aguifer remain constant.

According to the March 5, 1981, MDNR report, Bee Gee Manufacturing occupied the building from
1964 to early 1983.  Assuming that discharges of chromium-containing solution began in 1964,
an estimated 30 years have elapsed since the first discharge. Using the maximum average
linear velocity for ground water at the site of 0.04 ft/day, an estimated travel distance of
438 feet can be calculated for the down gradient part of the chromium plume.  This value does
not take into consideration factors that would retard the movement of solute, such as
interaction with aguifer materials.

During the Further Investigation of Groundwater (FIG) field investigation,  groundwater
samples  (for laboratory analyses) were collected from 18 shallow and four deep cone
penetrometer borings; five sand points; and five monitoring wells.  The results of those
analyses indicated that each of the target analytes  (arsenic, beryllium, chromium, lead, zinc
and hexavalent chromium)  were detected above detection limits in at least one of the
groundwater sampling locations.

Five  (5) additional groundwater samples were collected from nearby residential and irrigation
wells completed in the upper-most alluvial aguifer.  Each of these samples were analyzed for
arsenic, beryllium, chromium,  lead, and zinc.  Hexavalent chromium was analyzed at one
location.  Zinc was detected at each location at concentrations ranging from 23.4 to 64.7
micrograms per liter  (Ig/1), which are below the associated Secondary Drinking Water Standard
of 5000 Ig/1.  Lead was detected at one location at a concentration of 4.0 Ig/1, which is
below the Action Level of 15 Ig/1.

5.4   SUMMARY AND  RECOMMENDATIONS

Risk-levels for hexavalent chromium and total chromium in groundwater were established in the
Risk Assessment by the MDOH for the Bee Gee site.   While detected levels of total chromium
were below the risk-level of 3,500 parts per billion  (ppb), the risk-level of 18 ppb for

-------
hexavalent chromium was exceeded.  The most recent analytical-results show the presence of
hexavalent chromium at concentrations up to 52 ppb.

Even though the source has been removed, concentrations of hexavalent chromium in groundwater
at the site exceed site-specific risk-based concentrations.  However, use of the site can be
controlled, and there are no known shallow groundwater users down gradient of the site.
Therefore, only monitoring and prohibiting the use of the contaminated groundwater plume are
considered necessary.  Active remediation of the groundwater at the Bee Gee site was found to
be unnecessary.

6.0   SUMMARY  OF  SITE  RISKS

This section explains the risk assessment process.  The risks to human health and the
environment at the Bee Gee Manufacturing site are described in the site-specific Risk
Assessment for Exposure to Contaminated Groundwater.  This document was prepared for MDNR by
the Missouri Department of Health using EPA guidance.  The Risk Assessment followed the
following four step process:  1)  identification of contaminants which are of significant
concern at the site; 2) an exposure assessment which identified exposure pathways and
calculated contaminant intake; 3) a toxicity assessment for chemicals of potential concern at
the site; and 4)  a risk characterization, which integrated the three earlier steps to
summarize the potential and current risks posed by hazardous substances at the site.  Risks
at the site do pose a threat to human health, but no environmental risk were identified.

Two risk assessments were prepared by MDOH to analyze the potential adverse health effects
from exposure to the contaminants at the site.  The initial Baseline Risk Assessment
evaluated adverse health effects to both current and future on-site populations resulting
from exposure to hazardous substances in surface soil and groundwater.  Airborne contaminants
were considered for risk analysis under an assumption that suggested that the increased level
of activity would result in an increased level of airborne particulates and would represent a
worst case scenario. However,  because nickel, total chromium, and hexavalent chromium were
not detected above their associated detection limits, the air pathway was excluded from the
Baseline Risk Assessment.

Following the August 1992, Removal Action to remove contaminated soils and other potential
sources from the site,  a second risk assessment was completed.  Since the removal was
considered successful,  soil was not considered as a medium of concern in the second risk
assessment.  Only data collected during the FIG were used in order to identify potential
health risks from exposure to groundwater.  The study focused on health risks posed by
ingestion of and bathing in site groundwater by a future on-site resident.  Since hexavalent
chromium is a metal and nonvolatile, risk of inhalation does not exist; therefore, the air
pathway was not considered.

The concept of the Reasonable Maximum Exposure (RME) is an important aspect of calculating
the risk for a site.  The RME is an estimate of the highest exposure that is reasonably
expected to occur at a site.  Residential exposure is the most conservative scenario and
tends to result in the highest risk estimates.  Even though the primary land use in the area
is industrial, the residential scenario was evaluated because the potential exists for future
land use to become residential.  It should be noted that the land for a considerable distance
around the site is part of the Maiden Industrial Park. While a residential scenario is
possible, this fact makes it improbable.

Two RMEs were evaluated in this risk assessment:   A 70 kg  (kilogram) adult living on the site
for 30 years  (RME3) and a 15 kg  (age 0 to 6) child living on the site for 7 years (RME4); The
adult ingests 2 L  (Liter) of contaminated groundwater a day and bathes with contaminated
groundwater 12 minutes each day over a 30-year period while living on the site.  The child
ingests 1 L of contaminated groundwater a day and bathes with contaminated groundwater 12
minutes a day over a 6-year period while living on the site.

-------
Noncarcinogenic and carcinogenic risks were evaluated using metal concentrations from the two
most contaminated groundwater samples.  Results of the initial Baseline Risk Assessment were
used to select the Contaminants of Concern  (COCs)  to be evaluated in the FIG Risk Assessment.
Metals retained as contaminants of concern included:

    •   Total Chromium
    •   Hexavalent Chromium
    •   Arsenic
    •   Lead
    •   Zinc

Beryllium was eliminated from the COG list because it was detected in only one monitoring
well (MW-1), which is the background  (up gradient) well for the site.

The analytical data from two monitoring wells  (MW-3 and MW-5), were used as the exposure
point concentrations for risk calculations.  These two wells exhibited the highest
concentrations of COCs during the FIG.  Only total chromium was detected at concentrations
that exceeded the Maximum Contaminant Levels (MCL) established in the Safe Drinking Water
Act.  Hexavalent chromium, the more toxic form, was detected at the MCL (100 Ig/L) and
substantially above a risked based level (18 Ig/L).

The risk of cancer from exposure to a chemical is described in terms of the probability that
an individual exposed for 30 years will develop cancer over a 70-year lifetime. Typically,
cancer risks of 1x10-6 (one in one million) or lower are considered to be so small that they
are of no practical concern.  Higher cancer risk levels may be cause for concern, and the EPA
typically requires site remediation if risks exceed 1x10-4  (one in ten thousand).  The major
contributor to carcinogenic risks at the site was determined to be arsenic; however, arsenic
has been determined to be a naturally occurring substance at the site.

The total excess lifetime cancer risk calculated for the adult resident for RME 3, based on
exposure to wells MW-3 and MW-5, were 2.2x10-4 and 2.9x10-4, respectively.  The total excess
lifetime cancer risk calculated for the child resident for RME 4, based on exposure to wells
MW-3 and MW-5, were 1.2x10-4 and 1.6x10-4,  respectively.  These total excess lifetime cancer
risks for the hypothetical adult and child resident, based on the analytical data for both
monitoring wells, exceed 1 in 10,000  (1.0 x 10-4).  The carcinogenic risk is based totally on
exposure to arsenic in groundwater.  It should be noted that although arsenic was detected in
three of the four monitoring wells onsite,  it was detected at levels significantly below the
Maximum Contaminant Level of 50 Ig/1. The available information on site history does not
indicate the use of arsenic-containing compounds in any of the former manufacturing
processes.  Naturally occurring or background concentrations of arsenic in the groundwater
cannot be ruled out. Previously completed sampling of the Maiden public wells did not include
arsenic as a parameter to be analyzed for;  however, arsenic was detected in the discharge
material from the Bee Gee Manufacturing building and several wells located near the site
during the MDNR Abandoned Hazardous Waste Site Sampling event on June 27,  1984.  The report
indicated that all the wells near the site had concentrations of arsenic less than the
detection level of 0.005 mg/1.  The discharge sample indicated that the arsenic value was
less than the detection level of 2.5 mg/1.

The risk of adverse noncarcinogenic effects from chemical exposure is expressed in terms of a
Hazard Quotient  (HQ).  The HQ is the ratio of the estimated daily intake of a chemical to the
Reference Dose (daily dose which may be ingested,  inhaled or absorbed without adverse health
effects occurring).  The Hazard Index (HI)  is the summation of all chemical-specific HQs
within an exposure pathway and the Total Hazard Index is the sum of all pathway-specific HI
values.  Any of these values  (HQ, HI, Total HI) exceeding 1.0 indicates the potential for
adverse health effects to occur in exposed individuals.

The Total Hazard Indices calculated for the adult resident for RME 1 were 1.8 and 2.1,
respectively.  The Total Hazard Indices calculated for the child resident for RME 2 were 4
and 4.8, respectively.  Those values greater than 1 indicate that unacceptable
noncarcinogenic health risks from exposure to groundwater may be present for future adult and

-------
child residents.  The data suggest that the noncarcinogenic risks from ingestion and dermal
exposure to groundwater is dominated by arsenic and hexavalent chromium.   Zinc and trivalent
chromium in groundwater contribute relatively minor amounts to the total  noncarcinogenic
risks.

Total Hazard Indices for both RMEs exceed 1.0.  Conseguently,  noncarcinogenic health risks
may be present for a future adult or child resident living on the site.

The Lead Integrated Uptake Biokinetic Model (IUBK)  was used to estimate human intake of lead
from groundwater at this site.  To ensure lead concentrations were not sufficient to pose a
health threat, the highest concentration of lead found in groundwater was used in the IUBK.
Predicted blood lead levels greater than 10 micrograms per deciliter (ug/dL)  in over 5
percent of the potentially exposed population are considered to present a health hazard.
Because predicted levels were well below 10 ug/dL,  a health hazard is not expected to be
caused by ingestion of lead in groundwater.

Preliminary Remediation Goals (PRGs)  for a site may be established by:   (1)  adoption of
standards or recommendations from regulations, such as Maximum Contaminant Levels (MCLs) or
water guality criteria; or (2) calculation of PRGs based on health-related criteria.  The
approach used in this plan was to develop PRGs from health-related criteria derived from the
risk assessment process.  The PRGs, as indicated in Table 1, represent contaminant
concentrations to be achieved to satisfy the remedial action objectives,  with considerations
for background concentrations near the site. Background concentrations are considered because
in some cases they may be higher than risk-based concentrations or MCLs that were established
when public health criteria was considered.

6.1   CONCLUSIONS

Hexavalent chromium in shallow groundwater at the site presents an unacceptable risk for
non-carcinogenic effects.  If the response action selected in this ROD is not implemented,
the hexavalent chromium contamination in the shallow groundwater at the site will present an
imminent and substantial endangerment to public health.

Calculations in the risk assessment show that the shallow groundwater at  and near the site
presents an unacceptable carcinogenic risk due to its arsenic content.   However,
concentrations of arsenic detected in groundwater from the site were lower than the
concentration detected in the background monitoring well.  Therefore, remediation of arsenic
is not appropriate for this site.

Zinc and trivalent chromium concentrations do not present unacceptable health risks according
to the calculations in the risk assessment.  There is no health risk at the site from
exposure to the soil.  This is because the contaminated soil was removed from the site in
July 1992.

7.0   REMEDIAL  ACTION  OBJECTIVES

Remedial Action Objectives (RAOs) define the allowable exposures to contaminants of concern
found at a Superfund site.  The primary contaminant of concern at the Bee Gee Manufacturing
site is hexavalent chromium.   In consideration of this fact, the following Remedial Action
Objective was developed for the site:

    •   Prevent ingestion of water containing hexavalent chromium in excess of MCLs or
       preliminary remediation goals  (PRGs).

PRGs are site-specific clean-up goals calculated for a specific contaminant by MDOH based
upon the risk assessment.  MCLs and PRGs identified for this site by MDOH are presented in
Table 1.

-------
The MDOH identified both carcinogenic and non-carcinogenic risks from exposure to hexavalent
chromium at the site; therefore, the RAO was developed to prevent such exposure.  MDOH also
identified carcinogenic risks from exposure to arsenic. However, the level of arsenic
detected in monitoring wells on the site was less than the concentrations found in the
background well.  Therefore, remediation of arsenic is not considered appropriate for this
site.

8.0   DESCRIPTION OF  ALTERNATIVES

The remedial alternatives evaluated in detail in the FS report are described in the following
subsections.  These descriptions identify engineering components, institutional controls,
implementation reguirements, estimated costs, and major Applicable or Relevant and
Appropriate Reguirements (ARARs) associated with each alternative.

Common Elements:  Alternatives three through six have a number of common elements.  These
include the construction of extraction wells, neutralization and reduction in the treatment
process, and groundwater monitoring as an institutional control on a temporary basis during
remediation.  A description of each common element is presented below.

A)  Neutralization and Reduction

   Alternatives three  through  six  involve neutralization  and  reduction.   In  these
   alternatives,  the extracted groundwater  is pumped  to an influent holding  tank  and
   discharged  to  a  chemical  reduction  tank.  Hexavalent chromium is reduced  to  the  trivalent
   form using  either electrochemical reduction  or chemical reduction. Trivalent chromium is a
   more stable substance than  hexavalent chromium. By reducing  chromium  from the  hexavalent
   form to  the trivalent form,  it  becomes less  reactive and therefore safer  and easier to
   manage.

   When using  chemical  reduction,  sulfuric  acid would be  added  to a reduction tank  to reduce
   the pH of the  groundwater.   Following pH reduction, a  chemical such as ferrous sulfate
   would be added to react with hexavalent  chromium and reduce  it to  trivalent  chromium.

   In Alternatives  six  and  seven,  sulfuric  acid would be  added  to regenerate the  resin.
   Regenerate  solution  exiting the exchangers would be routed to the  chemical reduction  tank
   where a  chemical  such as  ferrous sulfate would be  added, and the chromium in the
   regenerate  solution  would be reduced and precipitated  out  of solution.

B)  Groundwater Monitoring

   Groundwater monitoring would serve  to detect changes in the  migration of  contaminants  and
   to indicate the  effectiveness of any remedial actions. However, it would  not treat or
   reduce the  contamination.   Monitoring wells  would  be added to the  existing network of
   monitoring  wells  to  provide additional definition  of the contaminated plume.   In addition,
   a sampling  and chemical  analysis plan would  be implemented.   Costs would  be  dependent  on
   the number  and depth of wells added and  the  freguency  and  magnitude of sampling.

C)  Extraction Wells

   Groundwater extraction wells would  be installed in Alternatives three through  six. These
   wells would be constructed  similar  to domestic or  municipal  water  supply  wells.
   Groundwater would be drawn  up from  the aguifer underlying  the site and piped to  the
   on-site  treatment system.   The  exact size, location, and pumping capacity will be
   determined  through hydrogeological  analysis  during the remedial design phase.

D)  Discharge of Treated Groundwater

   The preferred  option for  discharge  of the treated  groundwater produced by alternatives
   three through  six is to  the Maiden  Industrial Park POTW.   This POTW is currently operating

-------
   near  full  capacity and frequently exceeds the design hydraulic loading rate.  This is
   especially true during wet weather when infiltration problems have caused the hydraulic
   loading  rate to be exceeded by 40 percent. Contribution of the site groundwater treatment
   facility to this problem can be averted by implementing one or both of the following
   options:   Utilizing a holding tank to store treated groundwater for discharge during
   non-peak hours; and/or Installing an alarm and shutdown system to halt groundwater
   treatment  and discharge during heavy rain events.  The treatment facility is currently
   meeting  its National Pollutant Discharge Elimination System (NPDES) Permit discharge
   limits and no problems are expected by increasing the flow rate by 20 gallons/minute from
   the discharge of the site groundwater treatment facility.

8.1   Alternative 1:   No Action

Development of the no-action alternative is  required by CERCIA.   It  serves  as  a baseline  for
comparison with active cleanup alternatives.   Under this alternative,  no  action would be
taken to remove the groundwater contaminants.   Since this alternative  does  not change the
contamination concentration or exposure,  the risk remaining at  the  site would  be equivalent
to the estimated risks based on the risk assessment results.  Consequently,  this alternative
is not protective of human health and the environment.   A five-year  review  of  the site would
be required under CERCLA.   Thus,  funds  would be expended to conduct  the review.

     Capital Costs:                                            $20,000
     Annual O&M (Operation and Maintenance)  Costs:             $      0
     Total PW  (Present Worth):                                 $20,000
     Time of Implementation:                                   30  years
     Set-Up Time:                                              six months

8.2   Alternative 2:   Natural Attenuation,  Groundwater Monitoring and Institutional
      Controls

Under this alternative,  no active restoration measurers would be  taken to correct the
existing groundwater contamination.   Because the source of contamination  has been removed,
natural attenuation will result in the  concentration of hexavalent  chromium in the plume  to
be reduced below the PRGs  for the site.   Natural attenuation is the  process whereby
contaminants of concern,  such as hexavalent  chromium are diluted  and\or degraded to
concentrations or substances that are considered non-hazardous. The  mechanisms for achieving
this are hydrologic forces,  chemical reactions and biological processes that are already
present and occurring.

This alternative does not  provide for control of on-site contaminated  groundwater;  therefore,
the contaminants present in the groundwater  would continue to migrate. Long-term monitoring
of groundwater conditions  would continue on  an annual basis to  track migration and hexavalent
chromium concentrations of the contaminant plume.  Additional monitoring wells  would be
installed at or near the leading edge of the plume.  Information from the  monitoring would be
used to identify potential concerns to  off-site groundwater users.   It should  be noted that
the area is served by a municipal water system and there are presently no known groundwater
users within a mile of the site.

Institutional controls in  the form of deed restrictions,  and zoning  ordinances would be used
to advise future owners of the potential health risks from exposure  to the  groundwater.
However,  because the source of contamination has been removed,  there would  be  minimal
exposure to the contaminants of concern,  provided that contact with  shallow groundwater at
the site is restricted.   It would not be necessary to construct a fence around the site.
Potential danger to site workers who may be  excavating or drilling  into the saturated zone
would remain.

As previously stated,  the  contaminant plume  will attenuate over time.  As part of the RI\FS,
computer-generated modeling was used to predict the behavior of the  plume of contaminated
ground water over the next 30 years.   This information is contained  in a  report entitled

-------
Simulation of Contaminant Migration at the Bee Gee Manufacturing site.  The report  suggests
that hexavalent chromium concentrations in the plume may still exceed the current  maximum
contaminant level of 100 ppb after 30 years.   It also indicates that migration of  the  plume
over the past 30 years has been relatively limited and will continue to be so.   While  the
boundaries of the plume currently exceed the  boundaries of the property on the Registry of
Confirmed Abandoned or Uncontrolled Hazardous Waste Disposal Sites in Missouri (the
Registry) , it is not likely that it will migrate off of the property controlled by the City
of Maiden as part of its Industrial Park.

Public health evaluations would be conducted  every five years and would allow MDNR to  assess
the ongoing risks to human health and the environment posed by the site.  Groundwater
monitoring would occur on an annual basis. As reguired by the National Contingency  Plan
(NCP),  a risk re-evaluation using groundwater analytical data would be conducted every five
years.   The evaluations would be based on the analytical data collected from the groundwater
monitoring activities.

There is a limited amount of construction related to the implementation of Alternative 2. The
on-site monitoring wells would be used for groundwater sampling and monitoring over  a  period
of 30 years.  Additional monitoring wells are proposed under this alternative.

The costs associated with Alternative 2 consist of groundwater monitoring eguipment,
installation of additional monitoring wells,  analysis of ground water samples and  preparation
of the deed restrictions.

     Capital Cost:                                            $ 63,000
     Operation and Maintenance (annual):                      $ 18,000
     Total Cost (present worth):                               $261,000
     Time of implementation:
          Set-up:                                              six months
          Groundwater Monitoring:                             30 years

8.3  Alternative  3:   Groundwater Extraction, Treatment Using  Ion Exchange,  and
     Discharge

Alternative 3 is a groundwater extraction and treatment alternative utilizing five extraction
(recovery) wells and an ion exchange treatment system,  with the effluent being monitored and
discharged to the Maiden City POTW.   The time period estimate for aguifer restoration under
this alternative is four years.  Groundwater  monitoring is assumed for a period of six years.

The recovery wells would be installed to address the chromium plume.  The potential  exists
for either the number or spacing of the recovery wells to change as more exact well  yield
data are collected during the design phase.   The wells would be constructed of six-inch
Polyvinylchloride (PVC) casing, stainless-steel screens, and the well heads protected  by
flush-mounted vaults and locked covers.  The  estimated discharge rate for each recovery well
is assumed to be four gallons per minute  (gpm)  or a total of 20 gpm for five extraction
wells.

Extraction well pumps will deliver contaminated groundwater to an on-site treatment  facility
where the contaminants of concern are removed.   Ion exchange is a process in which wastewater
is passed through a bed of insoluble exchange material called resin. As wastewater is  passed
through the resin, chromium ions are exchanged on the surface with other negatively  charged
ions of less toxic elements.  As a result, chromium is removed from the wastewater and bound
up in the resin particles. Extracted groundwater would be pumped into an influent  holding
tank for flow egualization.  The influent would then be sent to an anion exchanger where
hexavalent chromium is removed by the ion exchange process.  Following hexavalent  chromium
removal, trivalent chromium would be removed  in a cation exchanger.

Periodically, the ion exchange resin will become saturated with chromium and reguire
regeneration.  Regeneration would be conducted onsite without removing the resin from  the

-------
exchangers.  To regenerate the ion exchange resin,  sulfuric acid and sodium hydroxide would
be passed through the anion exchanger,  and only sulfuric acid would be passed through the
cation exchanger.  Regenerate solution exiting the exchangers would be routed to the chemical
reduction/precipitation batch tank.  Sulfuric acid and ferrous sulfate would be added to
reduce and precipitate the chromium out of the regenerate solution as chromium hydroxide.
The resulting solution would be routed to the filter press and the sludge would be shipped
offsite for disposal.

As part of this alternative, monitoring wells would be sampled to verify the effectiveness of
the remediation effort and to track the contaminant plume's movement.  Four additional wells
for detection of the contaminant plume's movement at the site are proposed.   These wells
would allow down gradient monitoring of the contaminant plume.  Monitoring of the extraction
well's discharge would also be performed in order to evaluate the effectiveness of the
extraction system to contain and reduce the level of contaminants in the shallow groundwater.

By extracting and treating the contaminated groundwater, Alternative 3 provides a high level
of protection to human health and the environment.   Direct contact and ingestion of
contaminated groundwater is eliminated by this action.

The cost associated with Alternative 3 consists of groundwater monitoring eguipment and
analyses, plus treatment system eguipment and operation.

     Capital Cost:                                            $674,000
     Operation and Maintenance (annual):                      $ 92,000
     Total Cost  (present worth):                               $970,000
     Time of implementation:
          Set-up:                                             six months
          Groundwater Monitoring:                             six years
          Groundwater Extraction:                             four years

8.4   Alternative  4:   Extraction,  Treatment Using Reverse Osmosis, and Discharge

This alternative would use an extraction well system similar to the one described in
Alternative 3.  Following extraction, the groundwater would be pumped to a reverse osmosis
treatment system.

Reverse osmosis treatment is carried out by placing untreated water into a module and forcing
it between a pressurized tube and a stack of membranes.  From there the influent flows
through the various open channels across the surface of the membranes. When the membrane
process is operated on the cross-flow principle,  the solution to be treated is pumped under
pressure along a membrane and is divided by this means into two partial flows - a permeate or
filtrate which flows through the membrane and a concentrate or residual solution.  In the
latter, the contaminants in the water are held back by the membrane and are thus
concentrated.  The high pressure cross-flow method ensures that solutes are not deposited on
membrane surfaces even though their concentration increases along the flow path.  The short
feed water path across the membrane followed by a 180 degree flow reversal creates turbulence
and eliminates polarization concentration, thereby minimizing membrane fouling and scaling.
The permeate drains from the membrane's intermediate layer into a manifold for final
discharge into the city's POTW.

The treatment system would generate approximately 0.5 gallons/minute of waste concentrate.
This concentrate would be collected and processed through a filter press for dewatering and
final disposal.  It would be expected that this system would generate 15 cubic yards of
filter cake waste material during the life of the project.  This material would be classified
as a hazardous waste for disposal purposes.  The system is designed to operate continuously
and only shut down for maintenance and backwashing once every two weeks for two hours.  This
backwash cycle can be initiated manually or through a Programmic Logic Controller (PLC).  The
PLC monitors and controls the system through pressure differentials,  and tank levels will
automatically shut the system down if conditions outside the range of operating parameters

-------
are detected.  An alarm will then be activated to alert the operator of system difficulties.
An option for the PLC is to have the alarm notify appropriate authorities  in the  case  of  an
alarm condition through the use of a modem and telephone line during periods when an operator
is not onsite.

Minimal chemical usage is required for the backwash cycle,  and no chemicals  are required  for
the treatment process.  This is not an operator-dependent system,  and the  opportunity  for
operator error is very low.

This system would not require a full-time operator; however,  a daily check of the system
would be recommended for visual inspection of the treatment plant and extraction  wells along
with performing routine maintenance and filter press operations.  Based on  the influent
parameters and the stability of groundwater,  it is expected that  the membranes with the
reverse osmosis unit would last the entire duration of the project (four years) and would not
need to be replaced.

For purposes of cost estimation, it is assumed the system will operate continuously for a
four-year period.  Labor requirements are estimated at 10 hours/week.

Monitoring of the groundwater to ensure that the contaminant plume is controlled  under this
action would also be required.

     Capital Costs:                                           $721,000
     Annual O&M:                                              $ 41,000
     Total Present Worth:                                     $954,000
     Months to Implement:
          Set-up:                                             10  months
          Groundwater Monitoring:                             six years
          Groundwater Extraction:                             four years

8.5   Alternative  5:   Extraction,  Treatment Using Electrochemical  Precipitation and
      Discharge

This alternative would use a similar extraction well system as Alternatives  3 and 4.
Following extraction, the groundwater would be submitted to an electrochemical precipitation
treatment system.

The electrochemical precipitation process uses sacrificial electrodes to produce  an insoluble
ferrous ion, which adsorbs and coprecipitates heavy metals that are present  in the waste
stream.  The free ferrous ion released from the electrodes attracts contaminants  and makes
them part of the insoluble matrix formed as the ion comes out of  solution.   If there is any
hexavalent chromium present, the ferrous ion is oxidized to ferric ion while the  hexavalent
chromium is reduced to trivalent chromium and removed by adsorption onto the amorphous iron
oxyhydroxide that is formed.  The contaminant removal mechanisms  include new compound
formation, surface complexation and electrostatic attractions,  that can work in combination
to give needed removal efficiencies.

The precipitate is removed from the water by adjusting the pH,  adding coagulant aids and
utilizing an inclined plate clarifier.  Discharge from the incline plate clarifier will pass
through a multi-media filter system for final polishing of the effluent before discharge  into
the POTW.  The complete process increases the amount of sludge produced by adding
approximately four ppm metal hydroxide for every one ppm of contaminate treated.   Sludge  is
drawn off the bottom of the clarifier at the rate of 10 percent of the total flow rate (two
gpm) .   The sludge is then pumped into a holding tank and processed through a filter press for
dewatering and final disposal.   The filtrate which passes through the press  is returned to
the influent tank of the system.  The sludge generation rate is estimated  at 0.5  ft.3/day.
The sludge is not expected to contain hexavalent chromium,  and classification of  the waste
will be determined from TCLP metal analysis.

-------
The treatment system would not require a full-time operator.   However,  a daily check of the
system would be needed.  This would include visual inspection of the system and extraction
wells, replenishment of chemicals for pH adjustment and coagulant aid.  Cleaning of the filter
press is estimated to be done twice per week.

Initial start up of the precipitation option systems requires significant effort.  After start
up, maintenance of the system would not be as  operator dependent as the start up,  with the
exception of chemical handling,  routine maintenance and filter press operation.

A PLC monitors and controls the system and will automatically shut down the system in the
event parameters exceed the operating range.  An alarm will then be activated to alert the
operator of system difficulties.  An option for the PLC is to have the  alarm notify
appropriate authorities in the case of an alarm condition through the use of a modem and
telephone line during periods when an operator is not onsite.

For purposes of cost estimation, it is assumed the system will operate  continuously for a
four-year period.  Labor requirements are estimated at 20 hours/week.

Monitoring of the groundwater to ensure that the contaminant plume is controlled under this
action would also be required.  The cost associated with Alternative 5  consists of
groundwater monitoring equipment and analyses, plus treatment system equipment and operation.

     Capital Cost:                                            $444,000
     Operation and Maintenance  (annual):                      $ 87,000
     Total Cost  (present worth):                              $720,000
     Time of implementation:
          Set-up:                                             six months
          Groundwater Monitoring:                             six years
          Groundwater Extraction:                             four years

8.6   Alternative  6:   Extraction  and Treatment  Using Chemical Precipitation

A typical chemical precipitation process involves the precipitation of  heavy metals in an
alkaline solution.  This is accomplished as the metal ion combines with the hydroxide ion to
form an insoluble metal hydroxide solid.  This reaction is carried out  at a high pH. This
process is pH dependant and is reversible.  The lowest effluent concentrations achievable are
limited to the solubility of the metal hydroxides formed, under ideal conditions,  for each
individual metal.  Problems with treating a wastewater stream with multiple metals begin when
the metals have a different pH range for minimum solubility;  therefore, the operating pH
chosen is a compromise of all the metals involved.

The process described for this study is a modification of the typical chemical precipitation
process.  The following is a process of iron coprecipitation technology for heavy metals
removal.  This is more of a physical than chemical removal mechanism.

This process involves sparging air into a neutral pH wastewater stream  mixed with a ferrous
iron solution to form an insoluble dense iron matrix.

Discharge from the extraction wells is collected in an influent equalization tank.  A ferrous
iron solution is added to the stream as it is  transferred to the air sparging reactor.  The
heavy metals are naturally adsorbed to the surface of the iron solids.   In the reaction zone,
sodium hydroxide is added to control the pH to 7.8 and air is sparged to rapidly oxidize the
ferrous (Fe+2) iron to ferric (Fe+3)  iron.  Hexavalent chromium is reduced to trivalent
chromium as the ferrous iron is oxidized to the ferric state.  The ferric iron forms an
insoluble solid for precipitation.  The heavy metals are "occluded" into the dense iron
matrix, are insulated from the solution by the iron and are not allowed to resolubilize.
This phenomenon makes it possible to remove heavy metals from water to  concentrations below
their thermodynamic solubility limits.  After completion of this reaction,  the solids-laden
water is transferred to a clarifier where polymer is added to assist in gravity settling of

-------
the solids.  Effluent from the clarifier is at a neutral pH and will not need adjustment
before final discharge into the city's POTW.  Some of the sludge from the clarifier is
transferred back into the air sparged reactor to act as a catalyst for the oxidation of
ferrous to ferric iron.  The remainder of the sludge is processed through a filter press for
dewatering and final disposal.  Chemicals used during this process include sodium hydroxide,
polymer,  and ferrous chloride.

Chelating agents, if present, act exactly contrary to the intent of a wastewater treatment
system by keeping the metals in solution while water treatment processes are intended to
remove the metals from solution.  Because the removal mechanism of this process is more
physical than chemical, it is able to remove chelated metals from solution by enveloping the
metal and its associated chelator in iron and subseguently precipitating the iron solids.

This system would not reguire a full-time operator; however, a daily check of the system
would be recommended for visual inspection of the treatment plant and extraction wells,  along
with replenishing chemicals, performing routine maintenance, and filter press operations.

The sludge generation rate is estimated at 1.3 ft.3/day.  The sludge is not expected to
contain hexavalent chromium and classification of the waste will be determined from TCLP
metal analysis.

For purposes of cost estimation, it is assumed the system will operate continuously for a
four-year period.  Labor reguirements are estimated at 20 hours/week.

Monitoring of the groundwater to ensure that the contaminant plume is controlled under this
action would also be reguired.

The processes described in Alternatives 5 and 6 are similar processes in that they both use a
ferrous ion which is oxidized to a ferric ion to adsorb the contaminants followed by solids
precipitation.  The procedure of introducing the ferrous ion into the wastewater stream is
the main difference between these two processes.

The cost associated with Alternative 6 consists of groundwater monitoring eguipment and
analyses, plus treatment system eguipment and operation.

     Capital Cost:                                           $378,000
     Operation and Maintenance  (annual):                     $101,000
     Total Cost  (present worth):                             $710,000
     Time of implementation:
          Set-up:                                            six months
          Groundwater Monitoring:                            six years
          Groundwater Extraction:                            four years

8.7   Alternative  7:   Containment and In Situ Remediation

Under this alternative, a "funnel and gate" system for in situ treatment of the contaminated
groundwater would be used.  The system would consist of a low hydraulic conductivity cutoff
wall with a gap that contains a reactive porous media.  Cutoff walls (the funnel)  modify
groundwater flow patterns so that groundwater flows primarily through the porous reactor
(gate).  The University of Waterloo, Ontario, Canada has a patent pending on this relatively
new and innovative process.  Research is currently being conducted on development of a
reactor material specific for chromium.  Bench-scale studies have been conducted to assess
the ability of iron-bearing solids to remove dissolved hexavalent chromium from contaminated
groundwater.  Indications are that hexavalent chromium can be reduced and removed from
solution by forming insoluble trivalent chromium.  This process would therefore reduce the
toxicity of the groundwater by removing the chromium from solution.  No information on porous
reactor materials for removal of arsenic in groundwater is available at this time.

-------
In order to further evaluate the effectiveness of this system, treatability studies would be
required in order to determine the size and appropriate porous reactor material. Groundwater
modeling of the funnel and gate system would also be necessary.

Monitoring of the groundwater to ensure that the contaminant plume is controlled under this
action would also be required.

At this time, information on the cost of this alternative and the time necessary for
remediation are not available.

9.0  SUMMARY OF  COMPARATIVE ANALYSIS OF  ALTERNATIVES

Alternative remedial actions were developed to respond to the contamination at the Bee Gee
site.  The alternatives described in the preceding section were evaluated using criteria
related to the factors set forth in Section 121 of CERCLA and the NCP (National Oil and
Hazardous Substances Pollution Contingency Plan).   The nine criteria are described below.

Threshold Criteria:

Overall Protection of Human Health and the Environment.  This criterion addresses whether a
remedy provides adequate protection to human health and the environment and describes how
risks from each pathway are eliminated,  reduced, or controlled through treatment, engineering
controls, or institutional controls.

Compliance With ARARs.  This criterion addresses whether a remedy will comply with
chemical-specific, action-specific, and location-specific ARARs and with other criteria,
advisories and guidance such as To Be Considered  (TBCs), or provide grounds for a waiver.
TBCs are further discussed in Section 11.2.4.

Primary Balancing Criteria:

Long-Term Effectiveness and Permanence.   This criterion refers to the magnitude of residual
risk, including the ability of a remedy to maintain reliable protection of human health and
the environment over time once clean-up goals have been met, and the adequacy and reliability
of engineering and institutional controls.

Reduction in Toxicitv, Mobility, and Volume through Treatment.  This criterion assesses the
anticipated performance of the treatment technologies that may be employed in a remedy.

Short-Term Effectiveness.  This criterion refers to the period of time with which the
remedial response objectives are achieved, as well as the remedy's potential to have adverse
impacts on human health and the environment during the construction and implementation
periods.

Implementabilitv.  This criterion assesses the technical feasibility for constructing and
operating a remedy; the technical and administrative reliability of a remedy,  including the
availability of materials and services needed to implement the chosen remedy,  and the ease of
undertaking additional action, if necessary.

Cost.  This criterion includes the capital, operation and maintenance (O&M), and present
worth cost of a remedy.

Modifying Criteria:

State Acceptance.  This criterion assesses whether, based on its review of the FIG/FS and
Proposed Plan, the state agency concurs, opposes,  or declines to comment on the preferred
alternative.

-------
Community Acceptance.  This criterion assesses the degree of community acceptance of a
remedy.  The degree of community acceptance can generally be determined as a result of a
review of comments received during the public comment period.

9.1   OVERALL PROTECTION OF HUMAN HEALTH  AND THE  ENVIRONMENT

Of the six alternatives,  Alternatives 1 (No Action)  and 2 (Groundwater Monitoring and
Institutional Controls)  provide limited to no protection for human health and the environment
under a future use scenario where groundwater at the site is utilized.  However,  Alternative  2
does provide sufficient monitoring and controls to prevent access to and warn the public of
the potential health risks from exposure to the groundwater.  These controls are supplemented
by the fact that the area is served by Maiden's municipal water supply system.   In effect,
this eliminates the need for installation of individual water supply wells at or near the
site.  Alternative 2 is considered to be more protective than Alternative 1,  but less
protective in comparison with the extraction and treatment alternatives.   Because Alternative
1 would not be protective of human health and environment,  it was not considered as a viable
option for the site.

Alternatives 3, 4, 5 and 6 ranked essentially the same because they are all highly protective
of the environment.  Each of the groundwater extraction and treatment alternatives would
provide protection of human health and the environment by eliminating,  reducing,  or
controlling risk through treatment, engineering controls, or institutional controls at the
site.

The technology for containment and insitu remediation as discussed in Alternative 7 is
relatively new and sufficient information is not available to properly evaluate  it.

9.2   COMPLIANCE WITH ARARs

All treatment alternatives would comply with federal and state ARARs.  Disposal  of the sludge
and solid wastes generated at the site would need to be managed in accordance with the Solid
Waste Disposal Act, Department of Transportation (DOT)  Hazardous Materials Transportation
Act, Missouri Solid and Hazardous Waste Laws and Rules and the Resource Conservation and
Recovery Act.  Discharges of treated groundwater from the site would need to be  managed in
accordance with the Clean Water Act, Missouri Clean Water Law,  Missouri Water Quality
Standards, and Missouri Water Pollution Control Regulations.  All activities at  the site must
comply with the Occupational Safety and Health Act (OSHA).

9.3   LONG-TERM EFFECTIVENESS AND PERMANENCE

Residual risk at the site is not managed by Alternative 1.   Alternative 2 would  effectively
manage residual risk at the site on a permanent basis since access would be restricted.  The
reduction and management of residual risk would be effective in Alternatives 3,  4,  5,  and 6.
Each of those alternatives would remove the risk from the site and transfer it to a
controlled disposal facility.

All of the treatment alternatives would essentially eliminate the long-term risks associated
with the contaminated groundwater extracted and treated during remediation.

Based upon groundwater extraction predictions, each of these alternatives provide protection,
but risks would remain for approximately four years until groundwater clean-up goals are
achieved.

9.4   REDUCTION OF  TOXICITY, MOBILITY, OR VOLUME  THROUGH TREATMENT

Alternatives 1 and 2 do not utilize treatment.  Therefore,  they are not discussed here.

Four of the six alternatives  (3, 4, 5 and 6)  utilize extraction and treatment as a remedial
response for the groundwater.  All extraction and treatment alternatives are capable of

-------
restoring the contaminated groundwater to the PRG.   Each of the treatment processes provides
reduction in the mobility and volume of contaminants.   However,  only Alternatives 5 and 6
reduce the toxicity of hexavalent chromium,  which gives these two alternatives a higher
ranking with respect to this criteria.

9.5   SHORT-TERM EFFECTIVENESS

Alternatives 1 and 2 cause no community or site worker risks during implementation of the
remedy.  Community risk would be low during the installation of the extraction and monitoring
wells and the treatment facility.  There would be a greater risk to workers,  but compliance
with OSHA requirements and guidelines for hazardous waste site activities would minimize
these.  Analysis for air emissions would not be necessary because the contaminant is a heavy
metal and will not volatilize into the air pathway.

Environmental impacts resulting from the installation of the wells and treatment system would
include noise pollution and minimal fugitive dust emissions during construction. During
extraction and monitoring well construction, sedimentation and erosion controls would be
implemented to minimize contact with contaminated soil removed from the contaminated aguifer.

As with community risks, risks to workers and the environment would be similar in all
alternatives; however, in the active restoration alternatives (Alternatives 3,  4)  workers
and equipment would be removed from the site faster than under the containment solutions.
The time required for design and construction would be similar for all alternatives.

9.6   IMPLEMENTABILITY

Alternative 2 can be implemented easily.  Approval  from local governmental agencies for
establishing institutional controls will be necessary.

The technical feasibility of all other alternatives except Alternative 7 is similar because
process technologies employed in these alternatives are proven and reliable.   The ability to
construct and operate the elements of Alternatives  3 through 6 is high.  The materials and
services for implementing these alternatives are available on a regional if not local basis.
Because of the lack of information about alternative 7, its implementability is not known.

9.7   COST

The estimated total present worth cost of the selected remedy,  Alternative 2,  is $261,000.
Alternative 1 has the lowest total present worth cost  ($20,000).  The total present worth
cost of Alternatives 3, 4, 5, and 6 are $970,000; $1,280,000; $720,000; and $710,000
respectively.

9.8   STATE  ACCEPTANCE

The remedy selected here, Alternative 2, is the same as that proposed by the state in the
Proposed Plan.

9.9   COMMUNITY ACCEPTANCE

Community acceptance is specifically addressed in the attached Responsiveness Summary.  The
Responsiveness Summary provides a review of the significant public comments received on the
FS and Proposed Plan, and responses to the comments.  In general, the community agrees with
the remedy selected in this ROD.

10.0   SELECTED  REMEDY

Upon review of the alternatives in the FS, EPA has  selected Alternative 2, Natural
Attenuation,  Groundwater Monitoring and Institutional Controls,  as the remedy for the Bee Gee
site.  The selected remedy adequately protects human health and the environment from the

-------
risks posed by the site because the contaminant plume is not likely to migrate off the Maiden
Industrial Park property until the concentration of chromium in the groundwater is reduced
below levels of concern.  Additionally,  the area is served by Maiden's municipal water supply
system.  This eliminates any need for installing individual water supply wells at or near the
site.  Hexavalent chromium in the groundwater will attenuate to concentrations below
remediation goals due to natural processes.  Institutional controls will be reguired to
prevent future use of the groundwater in this part of the industrial park and to warn
potential purchasers of the contamination.  Additional groundwater monitoring wells will be
installed to assess the concentration and migration of the contaminant plume.

The capital costs for this alternative is $63,000 with an annual O&M cost of $18,000. The
Total Present Worth for Alternative 2 is $261,000 and is shown to be cost-effective.

11.0    STATUTORY  DETERMINATION

Under its legal authority, EPA's primary responsibility at Superfund sites is to undertake
remedial actions that achieve adeguate protection of human health and the environment.  In
addition, Section 121 of CERCLA establishes several other statutory reguirements.   These
specify that when complete, the selected remedial action for the site must comply with ARARs
unless a statutory waiver is justified.   The selected remedial action must also be
cost-effective and utilize permanent solutions and alternative treatment technologies or
resource recovery technologies to the maximum extent practicable.  Finally, the statute
includes a preference for remedies that employ treatments that permanently and significantly
reduce the volume, toxicity, or mobility of the hazardous waste as their principal element.
If the evaluation of two or more specific remedies is egual, or nearly so, remedies employing
treatment as a principle element should be selected.  However, when a non-treatment remedy is
clearly superior based on the evaluation of all the reguired criteria, selection of such a
remedy is indicated.

The following subsections discuss how the selected remedy for the Bee Gee Manufacturing site
meets these statutory reguirements of Section 121 of CERCLA, as amended by SARA, and to the
maximum extent possible, the NCP.

11.1  PROTECTION  OF HUMAN HEALTH AND THE ENVIRONMENT

The selected remedy protects human health and the environment by preventing human contact
with contaminated groundwater.  This is accomplished through zoning ordinances and deed
restrictions.  Monitoring the migration and attenuation of hazardous concentrations of
chromium in the groundwater plume will also be done. This will provide decision makers with
the information needed to ascertain that no further remedial actions are needed.

Implementation of the selected remedy will not pose any unacceptable short-term risks or
cross medial impacts to the site, workers, or the community.

11.2  COMPLIANCE WITH ARARs

The selected remedy will comply with all applicable, relevant, and appropriate reguirements.
No waiver of an ARAR is being sought or invoked for the selected remedy.  The ARARs of
concern include, but are not limited to, the following.

11.2.1  ACTION-SPECIFIC ARARs

Action-specific ARARs are technology or activity based reguirements. These reguirements are
triggered by the particular remedial activities selected to clean-up the site.
Action-specific ARARs include the following.

Health and Safety Standards 29 CFR Part 1926 and 29 CFR Part 1910:  Lists reguirements for
the protection of human health and safety at hazardous waste sites. These standards will
apply to the site because of the potential for on-site worker exposure to hazardous

-------
substances while performing remedial activities at the site.

Missouri State Well Construction Act RSMo 256.600 to 256.640:  Applies to well construction
onsite.  These rules are applicable because the remedial activity requires monitoring well
installation at the site.

Missouri State Well Construction Rules:  10 CSR 23-1.010 to 6.060:  Applies to well
construction onsite.  These rules are applicable because the remedial activity requires
monitoring well installation at the site.

11.2.2  CHEMICAL-SPECIFIC ARARs

Chemical-specific requirements are usually health- or risk-based numerical values or
methodologies that establish the acceptable amount or concentration of a chemical in the
ambient environment.  The ARARS listed below are standards set for drinking water supplies.
They are applicable at the Bee Gee Manufacturing site because the underlying aquifer may be
used as a drinking water supply.  The following are the chemical-specific requirements for
the Bee Gee site.

Safe Drinking Water Act  (42 U.S.C. 300f et seq.)  National Primary Drinking Water Standards
Maximum Contaminant Levels (MCLs) 40 CFR Part 141:  Maximum contaminant concentration allowed
in regulated public water supplies.  Based on chemical's toxicity, treatability, cost
effectiveness, and the analytical limits of detection.

National Secondary Drinking Water Standards:  Secondary Maximum Contaminant Levels (SMCLs))
40 CFR Part 141:  Aesthetic criteria established for finished water supplies.

Missouri Safe Drinking Water Act 640.100-140 RSMo:  Defines MCLs and SMCLs for the State of
Missouri.

Missouri Public Drinking Water Regulations 10 CSR 60-4.010:  Defines MCLs and SMCLs for the
State of Missouri.

11.2.3  LOCATION-SPECIFIC ARARs

No location-specific ARARs apply to the Bee Gee Manufacturing site.  There is no evidence of
the occurrence of sensitive or native communities within a one-mile radius of the site.
Proposed activities will not adversely affect wetlands.  The site is not on an active flood
plain.

11.2.4  TO BE CONSIDERED

These policies and strategies are not promulgated regulations, therefore compliance with
their provisions cannot be mandated.  However, due to their relevance to protection of human
health and the environment, they were considered in the selection of the remedy.

Site specific risk based Preliminary Remediation Goals:  The PRG is a TBC.  A memorandum from
the MDOH provided PRGs for the Bee Gee Manufacturing site. The PRG for Hexavalent Chromium at
this site is 18 ppb.

U.S. EPA Groundwater Protection Strategy:

Corrective Action Cleanup Standards Policy for RCRA, UST, and CERCLA Sites.

11.3   COST-EFFECTIVENESS

The selected alternative is cost-effective because it has been determined to provide overall
effectiveness proportional to its cost, estimated at a present total worth of $261,000.  Of
the alternative evaluated, only Alternative 1:  No Action, has a lower cost than the selected

-------
alternative.  The lack of protectiveness  of human  health makes the No Action alternative
unsuitable.  Alternative 5 was the next lowest  cost  of  the  action alternatives.  This
alternative cost, nearly a half million dollars more, for modest gains in long-term
protection.  Therefore,  it was not considered as cost-effective as the selected remedy.

11.4   UTILIZATION OF  PERMANENT SOLUTIONS  AND ALTERNATIVE TREATMENT OR RESOURCE
       RECOVERY TECHNOLOGIES TO THE MAXIMUM EXTENT PRACTICABLE

The selected remedy represents the maximum extent  to which  permanent solutions and treatment
technologies can be utilized at the Bee Gee Manufacturing site to meet water guality
reguirements.   Of those  alternatives that are protective of human health and the environment
and comply with ARARs,  EPA has determined that  this  selected remedy provides the best balance
of tradeoffs,  in terms of long-term effectiveness  and permanence; reduction in toxicity,
mobility,  or volume achieved through treatment; short-term  effectiveness; implementability;
and cost.

11.5   PREFERENCE FOR  TREATMENT AS A  PRINCIPAL ELEMENT

The selected remedy does not satisfy the  statutory preference for treatment as a principal
element of the remedy.   However,  the principal  threat to human health is from ingestion or
dermal contact with contaminated groundwater.   Since contact with the groundwater is very
unlikely,  EPA does not believe treatment  is warranted in this instance.

12.0  DOCUMENTATION OF  SIGNIFICANT  CHANGES

The Proposed Plan for the Bee Gee site identified  Alternative 2 as the preferred remedy.  It
was released for public  comment on April  17,  1997.   No  written comments were received.  Oral
comments received during the public meeting held on  May 1,  1997, are addressed in the
attached Responsiveness  Summary.   Upon review of these  comments, it was determined that no
significant changes to the proposed remedy were necessary.



-------
                                   TABLE 1
                                 GROUNDWA.TER
    Concentration Ranges, Background Concentrations, MCL, MCLGs, Preliminary
                      Remedial Goals, and Detection Limits

                                Units:  mg/1
Chemical
Arsenic
Chromium VI
Chromium,
Total
Lead
Zinc
Concentration Background MCL MCLG SMCL Preliminary
Range Concentration Remediation
(RI/FIG Data) Goals (5)
0.001 - 0.013 0.0043/0.010* 0.05 NS — 0.0005
0.05 - 0.1 <0.05*/<0.05* NS NS — 0.018
0.003 - 2.95 0.024/0.0407 0.1 0.1 — 3.5
0.002 - 0.0826 0.050/0.0826 0-015 (1) 0.0
0.004 - 0.121 0.0706/0.119 NS NS (2) 5.0 1.0
* None Detected at the detection limit; therefore, a concentration less than the associated
  detection value could exist
(1) Action Level - Treatment Technology Level
(2) NS = None Specified
(4) Detection levels elevated in FIG as result of Matrix Interference
(5) As calculated in the Baseline Risk Assessment
MCL - Safe Drinking Water Act - Maximum Contaminant Level, May 1994
MCLG - Safe Drinking Water Act - Maximum Contaminant Level Goal, May 1994
SMCL - Safe Drinking Water Act - Secondary Maximum Contaminant Level, May 1994

-------
                                           BEE  GEE  SITE






                                    RESPONSIVENESS SUMMARY











                                TABLE OF CONTENTS





Community Relations Summary                                          1





Summary of Public Comments                                           2

-------
                            BEE GEE  SITE  RESPONSIVENESS SUMMARY

                                 Community Relations  Summary

Requirements of the Comprehensive Environmental Response Compensation and Liability Act of
1980 (CERCLA)  for public participation  in  selecting the remedy for a Superfund site include
releasing the Feasibility Study (FS)  and the Proposed Plan for review and comment by
interested individuals or groups.

The Missouri Department of Natural  Resources  (MDNR) met these requirements in April and May
of 1997 by placing both documents in  the Administrative Record for the site.  The
Administrative Record (AR) ,  including the  FS and the Proposed Plan was made available to the
public at the Maiden Public Library and at the offices of EPA in Kansas City, Kansas, and at
the MDNR in Jefferson City,  Missouri.

The notice of availability for the  AR and  the announcement of a public meeting held on May 1,
1997, was published in the Maiden Democrat, a newspaper of general circulation in the
vicinity of the site.  The public comment  period was held from April 16,  1997, to May 16,
1997.  The public meeting was  held  as scheduled at the Maiden City Hall.

At the public meeting, representatives  from the MDNR and the EPA received public comments and
answered questions about problems at  the site and the remedial alternatives under
consideration.  Summarized responses  to the comments received during this public meeting are
included in this document in the section entitled Summary of Public Comments.  No written
comments were received.

-------
                                            BEE  GEE  SITE


                                     RESPONSIVENESS  SUMMARY

Summary of  Public  Comments

A full copy of the transcript of this meeting is included in the Administrative  Record  for
the Bee Gee Site.

QUESTION:  How big a spot are we talking about out there?

RESPONSE:  According to the groundwater investigation,  the plume of contaminated groundwater
extends over an area about 400 feet by 400 feet.  The exact depth of the  contaminated water
is not known but we do not believe the contamination is deeper than 25  feet  into the ground.
At the time that the remedy is implemented there will be some checks made to be  sure that we
do know the actual area and depth of the contaminant plume.

QUESTION:  You also mentioned the dirt that was moved to a landfill.  Does that  put the
landfill in jeopardy, too?

RESPONSE:  Because of the characteristics of the waste it was handled as  special waste.  It
was done according to solid waste disposal regulations and laws at that time.  Future
liability depends on whether they improperly handled the removed waste  at the landfill.
However, according to the information available on the removal it was done properly.

QUESTION:  Is there any possibility of this spreading,  creeping out and moving on, making a
bigger area,  expanding more and more?

RESPONSE:  There is.  The plume will spread.  As it does,  there will be some natural
processes and dilution that will take place.  As it does,  the concentration  of the
contaminants will lessen.  This will actually reduce the risk or danger posed by the
groundwater at the site.

COMMENT:  I became involved in this thing fifteen years ago.   I was serving  as chairman of
the Airport Board when Bee Gee went defunct and 999 came along.  And I  was present when the
gentleman from the University of Missouri at Rolla came down and suggested that  the city put
down the wells to triangulate the site.  The one well,  the depth of the existing well at the
air base was an Artesian well, 800 feet.  It would have been several hundred thousand dollars
in expenditures, which nobody had.  At that point in time,  this gentlemen, whose name I don't
recall, indicated that the contamination extended probably no more than six  inches into the
dirt.  The possibility it would enter in the aguifer was certainly real.   It was chromium
dioxide.  Subseguent to that, there was a large article in the St.  Louis  Post Dispatch  with a
big arrow pointing to the Maiden Industrial Park as a Superfund site.   You know, we lived
with that hanging over us like Love Canal or Times Beach.   This is the  fourth meeting like
this I know that I have attended in the last fifteen years and nothing  has been  done.   I have
met with your counterparts before.  You all moved with glacial speed.   Either there is  a
problem or there is not a problem.  If there is a problem,  you need to  address it.  If  there
is not a problem, and you might have told me and I think there is a problem  with this heavy
metal poisoning and it is nothing to fool around with.

I had a conversation out there subseguent to the original one where I suggested  we get  a
front end loader and dig up the original contaminated soil and store it in 55 gallon drums
and you could decide where to put it.  One of your counterparts said there was no acceptable
landfill in this area.  This gentleman says the Lemmons Landfill at Dexter was an acceptable
landfill.  So I mean fifteen years now have gone by,  you have removed at  least the initial
contamination.  We still have a site that is contaminated.  What you are saying is you are
going to monitor this thing some more.

-------
You now talk about the plume that extends.  My point is,  you talk about the plume and this
thing is going to spread.  It seems to me if there was any sort of remedial action taken at
the time you wouldn't have the plume.

RESPONSE:  Before the soil was removed, contaminants had already leached into the
groundwater.  At the time the removal was done, a gravel filled pit was discovered in the
area where the discharge had occurred.  This pit was constructed by Bee Gee to facilitate
percolation of the discharged waste water into the surrounding soil.  This resulted in
accelerated migration of contaminants into the site groundwater.

QUESTION:  Why did it take ten years from the initial contamination to remove the soil?  If
this is a Superfund site (it should get)....  priority attention.

RESPONSE:  In general, it takes a number of years for a site to progress through the
Superfund evaluation process (a preliminary assessment, site inspection, removal site
evaluation).  Planning for a removal may also take considerable time.  While I do not know
all of the specific reasons that it took this long to complete the removal at Bee Gee, the
following information provides some insight.

The initial action in 1981 was taken under the federal Clean Water Act  (CWA) .  Enforcement of
the CWA was delegated by EPA to the state.  At the time of the initial MDNR response, the
problem at the site was only noted to be a discharge of contaminated water to the soil
surface.  A full-scale investigation was not done at that time.  Bee Gee ceased the discharge
of contaminated water after the CWA investigation.  Falcon's 1986 purchase of the Bee Gee
plant triggered the Superfund investigation.  When they took over the site, Falcon found
numerous products left on the site by the previous operators.  EPA and MDNR began
investigating the long term problems at the site after they worked with Falcon to eliminate
the immediate concerns.

COMMENTS:  Well, it really took from 1981.  1 haven't heard  (anything) here tonight that I
didn't hear in 1981.  "It is a contaminated site:  and "...  the primary contaminant was
chromium dioxide, a heavy metal".  "They ceased operation."  "The ground was contaminated".
"The water supply was probably contaminated."  "We should be drilling test wells."  All this
stuff.  Now that was sixteen years ago.  And as I say, I don't know where you folks stand in
the chain of command with Department of Natural Resources and EPA and all that.  Apparently
either we have not pursued this aggressively enough with the authorities or you guys in your
jobs have not pursued it aggressively enough. Either there is a problem or there isn't a
problem.  If it is a serious problem, you need to straighten it up and get us off the
Superfund site.

I don't know when the Superfund site designation came.  I know in '81 I talked to a gentleman
that went through the same scenario with me about what the contaminant was and what should be
done about it.

RESPONSE:  The site was listed on the Superfund National Priorities List in 1993.  If there
had been a house next door or any human exposure or there was any danger to anyone, it
probably would have received a higher priority.

COMMENT:  There was a house at that time just east of that site and the people who lived
there, I can't tell you their names.  They had pets of ducks, geese, rabbits and pens.  They
made some comments about that fact that he was there.  They had a shallow well they used for
lawn and gardening.  I don't think the house is there.  It has been torn down now.  It was to
the east of that site.  But my point is,  this has been dragging on for years.   I went to a
meeting in the old city hall in the  '80s with your counterparts.  There were five people
there as I recall.  We did this same thing.  I will apologize for the sarcasm, this dog and
pony show, and nothing happened.  Nothing happened.  Falcon, when they bought that site in
'86, they were good corporate citizens.  They made a real effort to do something about it and
to do something about it in the restrictions of the law.   I don't know what engendered this
meeting here tonight. Why are we here tonight?

-------
RESPONSE:  EPA removed the soil.  After they removed the soil more testing was done and
chromium contamination was found in the groundwater.  Now we have to make a decision on the
groundwater.  Should we do something here?  We took a look at again and made the decision,
hey, there is something here.  Let's look at it again. That is kind of why were are here.
The groundwater issue, the soil has supposedly been removed and cleaned up and that media has
been handled.  We worry about the groundwater.  That is what we did.  We assessed the
groundwater.  You removed the soil and all that is taken care of.  We still have the
groundwater issue.  We look at it and see if it is going to be a health risk.  That is why we
examined it.  I note that these things do drag on.  It fells like nothing has been done.  The
soil is removed now.  So it is possible you can have a building on top of it and open it back
up for business and the land can be utilized again.  We were looking at future residential,
if you are able to put a well on this site.  Is there contaminated groundwater that will
travel to another well. This is what we say we need to look at.

We are not denying it is taking a long period of time.  The main reason we are here tonight
is because the state of Missouri and EPA have come to conclusions on what to do with the
site.  The purpose of this public meeting is to explain the remedy and get comments from the
public and to find out what they think about the plan before we decide what to do with the
site.

COMMENT:  One of the city's main water wells is probably less than a hundred yards from that
site.

COMMENT:  The guestion I would like to see answered on some sort of reasonable scale so we as
ordinary people can understand, what is the risk?  You said there is a Risk Assessment study.
I haven't read it and probably won't read it.

RESPONSE:  In simple terms what we do is we take a concentration that we know affects people.
If I give you chromium, let's say I used you as a test subject, and give you this much
chromium and I watch you.  There is no effect.  I give you a little higher dose and we
continue to do this until we get a dose that affects you.  That gives us the magic
concentration number.  What we do is to protect human health we divide that by ten hundred
thousand.  We take that single dose down and we say do not ever take more than this does.
Then we take that dose, compare it to what is out there in the water.  And what is out there
in the water is a little bit higher than that magic number. We have is a cushion there to
what we know will affect you and what we accept as acceptable for you to drink.  It is above
the acceptable limit.  We call that one.  We say one unit.  Don't take more than one of
these.  The numbers come out to four.  Four times the acceptable limit might have health
effects on you.  But with no one out there, there is no exposure.

I can't tell you, and I wish we could say this concentration you are going to develop a skin
rash in three days.  We just can't say that.  We don't know enough about the chemical's
habits.  There is not a lot of testing done.  This not an exact science.  We don't know.
That is not acceptable to us.  We are not going to take the chance.  So to us, that amount is
- I can't say nothing is going to happen.  I can't tell you what is going to happen.  I can
tell you that at that dose we have some effects in animals we study in the labs, which can
affect workers handling that.  So we say it is not acceptable risk. There is that risk at
this site.

But that risk is only if you drink the groundwater.  There is nothing on the surface. Walking
across it or if you play in the dirt or eat the dirt.  There is no risk there. We take an
adult and child and family.  And we do a family.  We say you are drinking two liters of water
a day.  You may drink two liters of water from your home.  A lot of people don't.  That is
what we are going to do.  We want to protect people so we are going to say you do.  Say you
wash your hands you are drinking and you bathe in this, 350 days out of the  (year).  You have
got it all over your head, face, (every) pore of you is soaking in it thirty minutes a day.
We figure out how much is getting into your body. And that is where we get the risk.  If you
are drinking two liters of water a day, wash your clothes, wash your body, wash your hands,
bathing for thirty minutes a day, there is going to be some risk to you.

-------
Some people say, you know, say that is unreasonable, that no one is going to do that. No one
bathes thirty minutes.  I have a daughter that can stay in the bathtub for an hour slide back
and forth.  That doesn't happen.  We want to make sure.  We just assume you are water lovers.
So we can look at that.  That is not happening out there.  There is no home out there.  There
is no well dug into it.  So there is no risk now because there is no one there to ingest that
chemical.  And that is what we say.  Is that understandable?

COMMENT:  So to answer Mr. Sante's guestions, putting it on a scale of zero to ten, right now
risk is zero.

COMMENT:  Zero risk to the people and citizens of Maiden.

QUESTION:  If you went to use the land, would there still be restrictions on any deed?

RESPONSE:  Yes, the Proposed Plan calls for deed restrictions on the property until the
contamination has attenuated.

QUESTION:  Is there a process to remove the restriction, get a dispensation?

RESPONSE:  When monitoring results show that the contaminated groundwater plume is
remediated, the restrictions can be removed.

QUESTIONS:  What would be considered acceptable if somebody went out there and built a house?
What would it will take for them to be able to do that?  At this point how much more clean up
would you have to do?

RESPONSE:  We have an  (MCL) number for groundwater.  That means you can drink it at the level
of chromium in the groundwater that is safe to drink.  We would like to see the numbers get
down to that level.

QUESTION:  How far are you from that number?

RESPONSE:  The preliminary remediating goals for the site is 18 parts per billion for
hexavalent chromium.  For total chromium the preliminary remediation goal is 3,500 parts per
billion.  The last analysis for total chromium showed between 100 and 150 parts per billion.
We are well within the limit on levels of total chromium.  The problem is the hexavalent
chromium.  The hexavalent chromium is running in the 20 to 30 parts per billion range.  We
need to see the concentration down to 18 parts per billion.

QUESTION:  What would it take to get that down?

RESPONSE:  Time and natural attenuation.

QUESTION:  What was the original test?

RESPONSE:  DNR person could not recall the exact concentrations in the original samples.
However, they were not significantly higher.

QUESTION:  What was the Risk Assessment on that?

RESPONSE:  The Risk Assessment was done to be conservative and protect, we take the samples
shoe everything from zero to whatever the highest number is.  We take the highest number and
we assume that it is contaminated everywhere.  Again, that is overprotective.  That is kind
of how we do it.  I can tell you for chromium the concentration was 100 parts per million.

QUESTION:  What was hexavalent?

RESPONSE:  100 parts per million.

QUESTION:  So it dropped from 100 down to 18 and 25?

-------
QUESTION:  In a period of time of fifteen years?

COMMENT:  Roughly fifteen years is correct.

QUESTION:  At this rate another four or five years it should be kind of down?

RESPONSE:  We hope that is what will happen.

QUESTION:  Is there anything that could be put on the ground to neutralize the groundwater?

RESPONSE:  I can address that.  I will get into discussing the alternatives.  I worked on the
feasibility study.

QUESTION:  When does the thirty-year clock start?  Does it start twenty-five years ago or
fourteen years ago when the test wells were put in?

RESPONSE:  Thirty years is an considered the longest that it will take for the contaminant
plume to attenuate to the preliminary remediation goals calculated for the site.  If the
preliminary remediation goals are achieved any time during that thirty years, we will stop
the monitoring and move forward with all the other things to get this site delisted.  To
determine when the time starts is probably less significant than when it ends?  The clock has
been running as far as the attenuation is occurring.  This is a process that naturally occurs
whether or not we have anything to do with it.  So, the guestion is not when we start
counting.  It is when will the process actually occur and when will the concentration of
hexavalent chromium get down to the calculated preliminary remediation goals.  The rate of
(attenuation) will probably be slowing down as the concentrations get closer and closer to
the remedial goals.

Technically, based on the Superfund contract, the thirty years starts in the near future when
we have implemented the proposed remedy.  I think we are going to hit, using common sense
here, we are going to get through that a lot faster than thirty years.  But that is just the
figures we have.  We hope it will take four or five or less.

QUESTION:  When it reaches that (the remedial goals) will the monitoring continue or will you
all stop?

RESPONSE:  Once we determined the concentrations are down to 18 parts per billion, we would
be monitoring for two more years.   The State would then notify EPA that the site is clean and
recommend moving forward with delisting the site.  If monitoring was done on a guarterly
basis, achievement of the remediation goals might be declared guicker than that.

QUESTION:  This monitoring, is it on a monthly basis or guarterly or yearly or what?

RESPONSE:  Monitoring would occur on an annual basis.  In fact, with the site at this stage
it is monitored annually by MDNR now.  We have five monitoring wells on the site.  A
specialist from the Environmental Services Program comes down once a year and collects
groundwater samples from each of the monitoring wells.  He takes them to our lab at Jefferson
City where they are analyzed to find out how much hexavalent they contain.  The samples are
also analyzed to find out what the concentration of all forms of chromium is.

QUESTION:  There are five  (wells)  on site now?

RESPONSE:  That is correct.  The proposed plan calls for four more wells.  That is an
approximate number.  It is possible we may need more or fewer monitoring wells. Please note
that we know that the contaminated plume has exceeded our monitoring well field.  It has
migrated outside of the area we have covered by monitoring wells. That is why we know we need
more wells.

QUESTION:  You need four more wells?

-------
RESPONSE:  We estimate that four more wells are needed.  Those wells would be placed at the
edge of the property more or less.

QUESTION:  These wells are six feet deep; is that correct?

RESPONSE:  State personnel were not certain of the exact depth of the monitoring wells.
Right now we believe the contamination is around 25 feet deep.  It will be somewhere 10 feet
and 60 feet.

QUESTION:  That  (60 feet) would be the maximum?

RESPONSE:  We believe that is the maximum depth.

QUESTION:  The size of it (of the plume)  will increase in all directions or is it moving like
in the south or to the north - is that a silly guestion?

RESPONSE:  That is an excellent guestion.  Looking at the big picture, the whole plume is
moving southeast.  If you take a small area, like you were looking at one little group of
about ten molecules, they are moving also moving southeast.  As they are moving, they are
also dispersing, so the plume is getting wider as it travels.  Also, the concentration at any
given point in the plume is reducing because of that dispersal.

The contractor that performed the Feasibility Study created a computer model of the behavior
of the plume.  The information from the groundwater model gives us a lot of encouragement
that the proposed remedy will work.  The model showed that the area of unacceptable
contamination will probably never get off the airport property.  By the time it reaches the
property limits it will have attenuated below the level of concern.

QUESTION:  If say that we were fortunate enough to get some big manufacturing company that
wanted to come to this area, could we build over that?

RESPONSE:  A manufacturing facility could probably be built on the site.  That is not a
definitive answer.

COMMENT:  That is better than saying absolutely no.

RESPONSE:  MDNR would reguire the developer to submit a change of use reguest for the site.
We would evaluate whether, through excavation or getting into the contaminated groundwater,
anyone would be at risk.  Even if they were going to get into the contamination during
construction, it is possible that special precautions could be taken to deal with that so
that the construction could go on.  It could be cost effective to do the construction and
just take special precautions.  People work on hazardous waste sites every day.  They can do
this without significant harm to themselves because they take special precautions to avoid
contact with contaminants, or to reduce the contamination before they get into it.

The fact that this area is served by a municipal water system makes the possibility of
building on the sight more acceptable.  The city's wells (according to a geologic study),
don't draw water from the aguifer where this contamination is.  We would probably not want
them to put in wells for the employees to drink or work in all day, or open up a car wash
using that water.

QUESTION:  Is this people from this general area that live around here or people from
Jefferson City or New York?

RESPONSE:  Comments would not be restricted to people from this area.  For instance, at the
Quality Plating Plant near Sikeston, there were a significant number of people from the Cape
Girardeau area, from Southeast Missouri State University that had comments and input on the
proposed plan for that site.  If any environmental organization wanted to comment, they would
be free to do so and their comments would be welcome.

-------
QUESTION:  What was the estimated cost on this project?

RESPONSE:  $261,000 on the remedy we proposed.

QUESTION:  Who pays for that?  Is the city of Maiden responsible for that?

RESPONSE:  The State has deferred that part of the project to EPA.  Under Superfund, the
normal process is to attempt to recover all expenditures on a Superfund site from those who
are liable for the site.  That is generally owners, operators, or others who have contributed
to the contamination.  In this case, the only viable owners and operators that we know of
that exist are the city of Maiden and the 999 Corporation.

EPA also realizes the realities of life and economics.  We know a community the size of
Maiden does not have the resources to finance the selected remedy.  I don't think the city
will write EPA a check for $261,000.  We look at the ability to pay.  We look at fairness and
reasonableness issues.  And in the instance where there is a shortfall, EPA will not elect to
try to recover costs.  There is no future in going after money where there is no money.  We
will not go ahead and pay more taxpayer's dollars  (in legal costs) to get dollars we already
spent and we know we are not going to get back.

That is not to say, we wouldn't seek some participation by the city and the formal
discussions will take place further down the road once we know where we can go and how we can
go about it.  But we understand the reality of life... that no community in this country is -
flush (with money) right now.  And it is unlikely that Maiden will be able, to or asked to
participate to the full amount that the law would allow us to do.  We want to be reasonable.

COMMENT:  That is good to hear.  As a taxpayer of Maiden, that is very good to hear.

COMMENT:  As the mayor of Maiden —

RESPONSE:  At this point we don't have anything solid and we are not beginning negotiations.
We don't do that at a proposed plan meeting anyway.  EPA will have discussions with the mayor
and a city council to let them know how the process goes. EPA has modified the process
somewhat, particularly for small communities, to try and find reasonable ways to fulfill the
reguirements of the law and at the same time be fair and eguitable with the communities.

-------