EPA/ROD/R03-96/224
1996
EPA Superfund
Record of Decision:
BUTLER MINE TUNNEL
EPA ID: PAD980508451
OU01
PITTSTON TOWNSHIP, PA
07/15/1996
-------
Text:
RECORD OF DECISION
BUTLER MINE TUNNEL SITE
DECLARATION
SITE NAME AND LOCATION
Butler Mine Tunnel Site
City of Pittston
Luzerne County, Pennsylvania
STATEMENT OF BASIS AND PURPOSE
This decision document presents the remedial action for the Butler Mine Tunnel Site ("Site") in the City of
Pittston, Pennsylvania. The remedial action was chosen in accordance with the requirements of the
Comprehensive Environmental Response, Compensation, and Liability Act of 1980 ("CERCLA"), as amended by
the Superfund Amendments and Reauthorization Act of 1986 ("SARA"), 42 U.S.C. §§ 9601 et seq.; and to the
extent practicable, the National Oil and Hazardous Substances Pollution Continqency Plan ("NCP"), 40 C.F.R.
Part 300. This decision document explains the factual and leqal basis for relectinq the remedy for this
Site. The information supportinq this remedial action decision is contained in the administrative record for
this Site.
The Commonwealth of Pennsylvania concurs with the selected remedy.
ASSESSMENT OF THE SITE
Actual or threatened releases of hazardous substances from this Site, if not addressed by implementinq the
response action selected in this Record of Decision ("ROD"), may present an imminent and substantial
endanqerment to public health, welfare, or the environment.
DESCRIPTION OF THE SELECTED REMEDY
This remedy addresses the possible future releases of hazardous substances from the Butler Tunnel. There
were two prior releases of hazardous substances from the Site, one in 1979 and another in 1985. The remedy
includes institutional controls and preparations for a remedial response to address the threat posed by the
conditions at the Site. The remedy uses an Administrative Center to a) monitor rainfall, b) monitor flow
rate at the Tunnel discharqe location, c) measure water levels in monitorinq boreholes and d) collect water
samples for chemical analysis to attempt to predict when a discharqe of hazardous substances may occur. The
Administrative Center would be responsible for notifyinq the U.S. Environmental Protection Aqency ("EPA") and
the Pennsylvania Department of Environmental Protection ("PADEP") when a potential for a flushout exists and
when a flushout occurs. A flushout is defined as a sudden discharqe of oil
contaminated with hazardous substances from the mine workinqs into the Susquehanna River.
This remedy also includes preparation for future remedial response by constructinq access roads and anchors
alonq the river's edqe and pre-purchasinq containment and absorbent booms necessary for any such remedial
response. These materials will be stored near the site to allow for the quickest possible
response. The remedy includes desiqn and implementation of two future response actions to cleanup future
discharqes. Response personnel would use the absorbent booms and anchor them alonq the river's edqe to
collect any oil discharqe containinq hazardous substances.
DECLARATION OF STATUTORY DETERMINATIONS
The selected remedy is protective of human health and the environment, complies with Federal and State
requirements that are legally applicable or relevant and appropriate to the remedial action and is cost
effective.
This remedy prepares for the potential release of contaminants into the Susquehanna River. However, because
removal and treatment of the hazardous substances which pose a threat at the site was not found to be
practicable, this remedy does not satisfy the statutory preference for treatment as a principal element. No
distinct pool or pocket of the contaminated oil wastes was found that could be pumped out and removed. The
oil that is present has adhered to the rocks and qravel located in the collapsed mine workinqs beneath the
qround surface.
Because this remedy will result in hazardous substances remaininq onsite above health-based levels, a review
under Section 121(c) of CERCLA, 42 U.S.C. §9621(c) will be conducted within five years after the initiation
of the remedy to ensure that the selected remedy continues to provide adequate protection of human health and
-------
the environment.
Thomas C. Voltaggio, Director Date
Hazardous Waste Management Division
-------
TABLE OF CONTENTS
I. SITE NAME, LOCATION AND DESCRIPTION 1
II. SITE HISTORY 2
III. ENFORCEMENT HISTORY 4
IV. HIGHLIGHTS OF COMMUNITY PARTICIPATION 5
V. SCOPE AND ROLE OF REMEDY 6
VI. SUMMARY OF SITE INVESTIGATIONS AND WASTE VOLUMES 6
A. HAZARDOUS SUBSTANCES 6
B. HYDROGEOLOGIC INVESTIGATION 7
C. SURFACE WATER AND SEDIMENT INVESTIGATION 8
D. BIOTA INVESTIGATION 8
VII. SUMMARY OF SITE RISKS 10
VIII. SUMMARY OF REMEDIAL ALTERNATIVES 14
A. ALTERNATIVE 1: NO ACTION 14
B. ALTERNATIVE 2: INSTITUTIONAL 14
C. ALTERNATIVE 3: INSTITUTIONAL/REMEDIAL RESPONSE 16
D. ALTERNATIVE 4: INSTITUTIONAL/MULTI-PORT OUTLET 17
E. ALTERNATIVE 5: SURFACE RECLAMATION 18
IX. SUMMARY OF COMPARATIVE ANALYSIS OF ALTERNATIVES 19
A. OVERALL PROTECTION OF HUMAN HEALTH AND THE
ENVIRONMENT 20
B. COMPLIANCE WITH ARARS 21
C. LONG-TERM EFFECTIVENESS AND PERMANENCE 22
D. REDUCTION OF MOBILITY, TOXICITY OR VOLUME 22
E. SHORT-TERM EFFECTIVENESS 23
F. IMPLEMENTABILITY 24
G. COST 24
H. STATE ACCEPTANCE 25
I. COMMUNITY ACCEPTANCE 25
X. EPA'S SELECTED REMEDY: DESCRIPTION AND PERFORMANCE
STANDARDS FOR EACH COMPONENT OF THE REMEDY 26
A. GENERAL DESCRIPTION 26
B. ADMINISTRATIVE CENTER 26
C. REMEDIAL RESPONSE 29
D. ENGINEERING AND SITE PREPARATION REQUIREMENTS 30
E. COMMUNITY RELATIONS 31
F. BOREHOLE CLOSURE 31
G. FIVE-YEAR REVIEWS 31
H. WORKER SAFETY 31
I. DEED RESTRICTIONS 31
J. OPERATION AND MAAINTENANCE 32
XI. STATUTORY DETERMINATIONS 32
A. PROTECTION OF HUMAN HEALTH AND ENVIRONMENT 32
B. COMPLIANCE WITH AN ATTAINMENT OF APPLICABLE OR
RELEVANT AND APPROPRIATE REQUIREMENTS ("ARARS") 33
1. CONTAMINANT-SPECIFIC ARARS 33
a. WATER QUALITY CRITERIA 33
b. WASTEWATER TREATMENT REGULATIONS 34
2. LOCATION-SPECIFIC ARARS 34
a. DREDGING AND FILLING 34
b. DAM SAFETY WATERWAY MANAGEMENT 34
c. FLOOD PLAIN MANAGEMENT 34
d. FISH AND WILDLIFE CONSERVATION 35
e. ENDANGERED SPECIES PROTECTION 35
f. ABANDONDED BOREHOLE CLOSURE 35
g. PENNSYLVANIA STORM WATER MANAGEMENT ACT
OF 1978 ("ACT 167") 35
3. ACTION-SPECIFIC ARARS 35
a. GENERATION AND STORAGE OF HAZARDOUS
MATERIALS 35
b. MUNICIPAL WASTE MANAGEMENT 36
c. SPECIAL WATER POLLUTION REGULATION 36
d. NATIONAL POLLUTANT DISCHARGE
ELIMINATION SYSTEM ("NPDES") 36
e. OIL POLLUTION PREVENTION 36
f. RESIDUAL WASTE REGULATIONS 36
g. FUGITIVE EMISSIONS CONTROL 36
-------
h. BOREHOLE CLOSURE 36
i. EROSION CONTROL 37
j. STORM WATER DISCHARGE 37
C. COST EFFECTIVENESS 37
D. UTILIZATION OF PERMANENT SOLUTIONS AND ALTERNATIVE
TREATMENT (OR RESOURCE RECOVERY) TECHNOLOGIES
TO THE MAXIMUN EXTENT PRACTICABLE 37
E. PREFERENCE FOR TREATMENT AS A PRINCIPLE ELEMENT 38
XII. DOCUMENTATION OF SIGNIFICANT CHANGES 38
XIII. RESPONSIVENESS SUMMARY 39
-------
RECORD OF DECISION
BUTLER MINE TUNNEL SITE
DECISION SUMMARY
I. SITE NAME, LOCATION AND DESCRIPTION
SITE DESCRIPTION
The Butler Mine Tunnel Site ("Site") is located in Luzerne County, in northeastern Pennsylvania. The
tunnel discharge point is located on the east bank of the Susquehanna River, approximately 350 feet north of
the Fort Jenkins Bridge in the City of Pittston, Pennsylvania. A Site location map is provided
in Figure 1.
The Butler Tunnel ("Tunnel") was constructed prior to the 1930s as a drainage tunnel for underground
coal miles via a series of interconnecting drainage ditches. Flow from the Tunnel discharges directly into
the Susquehanna River. It was designed to drain only that portion of the Butler Mine workings which were
situated above an elevation of 595 feet above sea level. However, mining occurred in numerous seams to
elevations as low as 300 and 400 feet above sea level. The Tunnel drains an approximate five-square mile
area of underground mine caverns and waterways. The Tunnel still continues to drain the mine
workings. It routinely discharges water containing contaminants of acid mine drainage composed of sulfate,
iron, and magnesium into the Susquehanna River. During mining operations, boreholes were drilled into the
mines to serve as air vents for the mines. Many individuals and companies used the bore holes to dispose of
various wastes, including, residential and commercial wastes containing hazardous substances and waste oil.
One such borehole was in Pittston at a gas station and auto repair shop called the Hi-Way Auto Service
Station ("HWAS"), located over two miles from the Tunnel discharge point. This borehole is known as the HWAS
borehole. The waste oil accumulated in the underground mine workings. It is believed that any sudden influx
of substantial amounts of water (such as heavy rain) will cause the accumulated
substances to be flushed out and discharged from the Tunnel.
The migration of contaminants from this Site begins with a rainfall event over the surface area of the
entire mine workings including Pittston, Dupont and neighboring communities. The water from the rainfall
enters the mine by moving through open boreholes and from the natural seepage of rainfall through the earth.
As the water fills the underground mine workings, the water elevation rises within the mines with the oil
waste floating on the surface of the water. The flushout occurs when the oil spills into the interconnecting
underground drainage ditches and then to the Butler Tunnel's discharge location along the banks of the
Susquehanna River. Water in the mine workings is not used as a drinking water source for the area.
There are no known endangered species or critical habitats within the immediate vicinity of the Site.
II. SITE HISTORY
In late 1977, an oil recycling and reclamation company contracted with the owner of the Highway Auto
Service Station for the disposal of oil waste into the HWAS borehole on the service station property. It is
estimated that several million gallons of waste were disposed of into this borehole. In July 1979, this
disposal was discontinued because of a Pennsylvania State Police investigation.
At the end of July 1979, Pennsylvania authorities were notified of a strong odor emanating from the
Butler Tunnel outfall on the banks of the Susquehanna. Upon arriving at the scene, authorities discovered a
35-mile long oil sick on the Susquehanna River originating at the Butler Tunnel outfall. Both the U.S.
Environmental Protection Agency ("EPA") and the Pennsylvania Department of Environmental Resources (now known
as the Pennsylvania Department of Environmental Protection or "PADEP"), responded and performed an emergency
removal under the authority of §311 of the Clean Water Act ("CWA"). Section 311 of the CWA authorizes the
cleanup of any oil discharge into a navigable water. After further investigation by EPA, PADEP and other
authorities, the source of the substances was traced to the borehole at the Highway Auto Service Station.
Testing of the wastes found in the borehole matched the waste in the outfall. To provide conclusive proof, a
dye was placed in the HWAS borehole. The same dye was subsequently observed in the outfall discharge.
After this spill was cleaned up, EPA installed an emergency monitoring device at the outfall of the
Butler Tunnel. The Butler Emergency Response Program ("BERP") was designed to monitor the continuing
discharge of water from the Tunnel and trigger an alarm if hazardous substances were discharged. PADEP
was charged with the operation and maintenance of the BERP system. After several years without a toxic
discharge, the system was abandoned. Following the 1979 spill, the Butler Tunnel Site was evaluated and
proposed for inclusion on the National Priorities List ("NPL"). However, EPA made the determination that no
remedial activities were needed and the Site was removed from the proposed list.
-------
In September 1985, another sudden discharge from the Butler Tunnel occurred following heavy rains and
flooding associated with Hurricane Gloria, which swept through the area. Upon arriving at the scene, PADEP
found a 50-mile oil slick in the Susquehanna River emanating from the Butler outfall. EPA was
notified and, with the assistance of PADEP, began cleanup activities under § 311 of the Clean Water Act.
This response became an emergency removal under § 104 of CERCLA when chemical analysis confirmed the presence
of Bis(2-ethylhexyl) phthalate and dichlorobenzene, which are federally regulated hazardous
substances. EPA removed and disposed of 161,000 pouunds of oil/chemical-soaked debris and soil from the
site. After further testing and investigation, EPA determined that the 1985 discharge was linked to the
illegal dumping that caused the 1979 discharge. EPA spent over $735,000.00 on the 1985 removal action. On
May 20, 1986, the Butler Tunnel site was once again proposed for inclusion on the NPL and was finally listed
on July 1, 1987.
After both the 1979 and 1985 discharges, hydrogeologic studies were performed by EPA. These studies
concluded that a low probability of a future discharge exists under normal day to day conditions but another
discharge may occur anytime a large storm hits the area.
III. ENFORCEMENT HISTORY
On December 27, 1985, EPA sent information reguest letters to the Potentially Responsible Parties
("PRPs") associated with the haulers that sent waste to the Butler Tunnel Site. In May of 1986 EPA sent
notice letters to twenty-five partie inviting them to undertake the Remedial Investigation/Feasibility Study
("RI/FS"). Most of these parties were companies whose wastes were picked up by Russell Mahler. Seventeen of
these parties agreed to perform the RI/FS pursuant to a Consent Agreement and Order dated March 30, 1987.
The Butler Mine Tunnel Site Phase I Remedial Investigation Report, Phase II Remedial Investigation Report,
and the Feasibility Study Report are the products of the Consent Order. The responsible parties hired
Gannett Fleming, Inc. to conduct the investigations and to prepare these reports. These studies are included
in the Administrative Record for this Site.
On November 24, 1989 the United Stated filed a complaint against twenty defendants, all generators of
hazardous substances sent to the Site, to recover EPA's past response costs associated with the 1985 spill.
A Consent Decree was filed, concurrently with the complaint, in which 17 settling defendant agreed to pay
$600,00 towards EPA's past costs and the Department of Defense agreed to pay $28,500 towards past costs. The
Decree was entered on January 17, 1990, over the non-settlors objections.
On June 8, 1990, two of the three non-settling defendants (NEAPCO, Inc. and Chemical Management, Inc.)
entered into a second Consent Decree with the United States, agreeing to pay $200,000 towards EPA's past
costs, which the district court approved in July 25, 1990.
The United States then moved for summary judgment against Alcan, the remaining defendant, to collect
the balance of the removal costs (which totaled approximately $350,000). The district court granted the
United States' motion on May 8, 1991, holding that Alcan was jointly and severally liable for the removal
costs because Alcan's waste contained identifiable levels of hazardous substances and was present at the site
from which there was a release. Alcan filed an appeal with the United States Court of Appeals for the Third
Circuit on June 5, 1991. The district court's opinion was vacated and the case was remanded for further
proceedings. (See Section IV below for a discussion of the appeal.) The United States filed a summary
judgment motion in the district court and on June 8, 1995, District Judge Thomas I. Vanaskie of the United
States District Court for the Middle District of Pennsylvania entered a judgment in favor of the United
States in the amount of $471,790.18. U.S. v. Alcan Aluminum Corporation. (CN: 3:89-cv-01657, United States
District Court, Middle District of Pennsylvania, June 28, 1995).
IV. HIGHLIGHTS OF COMMUNITY PARTICIPATION
The RI/FS Report and the Proposed Plan for the Butler Mine Tunnel Site were released to the public for
comment on July 19, 1994 in accordance with Sections 113 (k) (2) (B) , 117 (a), and 121(f) (1)(G) of CERCLA,
42 U.S.C. §§ 9613(k)(2)(B) 9617(a), 9621(f) (1)(G). These documents were made available to the public in
both the administrative record and in an information repository maintained at the Luzerne County Court House
Emergency Management Center located on North River Street in Wilkes-Barre, Pennsylvania. The notice of
availability for the documents and the public meeting was published in the Wilkes Barre Times
Leader.
A public comment period on the documents was held from July 19, 1994 through September 22, 1994. In
addition, a public meeting was held on September 20, 1994. At this meeting, representatives from the EPA and
PADEP were present and answered guestions about the Site and the remedial alternatives under
consideration. A Fact Sheet containing Site related information was distributed at the Public Meeting.
EPA's response to all comments on the Proposed Plan and related documents received during the comment period
is included in the Responsiveness Summary in this ROD. A copy of the transcript of the public
meeting has been placed in the administrative record file and information repository.
-------
V. SCOPE AND ROLE OF REMEDY
This remedial action will address the principal threat posed by conditions at the Butler Tunnel Site,
that is, the potential for another discharge of the oily hydrocarbon materials containing hazardous
substances which remains in the underground mine workings. This remedial action will prepare for such a
release by establishing a monitoring system to predict such release, by planning for response action, and by
providing materials to expedite the response action. This is the only ROD planned for the Site.
The concentrations of some of the hazardous substances previously detected in the 1985 flushout exceed
the acceptable levels for both human health and continuous aquatic life as allowed by the Pennsylvania Water
Quality Standards.
VI. SUMMARY OF SITE INVESTIGATIONS AND WASTE VOLUMES
The Remedial Investigation ("RI") attempted to re-construct the operations of the oil recycling
contractor and the dispatching tanker trailers carrying waste materials to the HWAS borehole. Based on
reports from different refinery facilities and records, it is estimated that between 1,500,00 to 2,700,000
gallons of liguid wastes were disposed into the mine workings. The RI report further estimates the oil
content of the liguid to be between 330,000 to 490,000 gallons. In reviewing the two oil discharge events
from 1979 and 1985, PADEP and EPA have estimated that between 276,000 and 400,000 gallons were discharged
during these events. Therefore, there still could be 50,000 to 90,000 gallons of oil contained in the mine
workings.
A. Hazardous Substances
In 1985 the analysis of the oily hydrocarbon discharge from the Tunnel revealed hazardous substances
which triggered CERCLA expenses to address the discharge. The hazardous substances are listed in Table 1.
The oily waste containing these hazardous substances moved through the mine workings into the Tunnel
and discharged into the Susguehanna River. The Remedial Investigation also shows that some hazardous
substances and oily waste still remain in the mine workings and present a potential risk if another flushout
should occur. Therefore, EPA has evaluated two discharge conditions, a flushout condition and a day to day
condition, to describe the nature and extent of releases that could occur at the outfall of
the Tunnel. Table 2 shows the two conditions and the concentrations of the contaminants of concern that were
reported during: 1) the 1985 flushout of the oily liguid wastes, and 2) the day to day concentrations as
reported in the RI.
Table 1: 1985 Releases of Hazardous Substances
Benzene Dimethyl phthalate
Bis (2-ethylhexyl)phthalate Di-n-octyl phthatate
4-Bromophenylzphenyl ether Ethylbenzene
Carbon Tetrachloride Methylene chloride
Chloroform Naphthalene
Cyanide Phenol
Dichlorobenzene(s) Toluene
Diethyl phthalate Trichloroethylene
Xylene(s)
B. Hydrogeologic Investigation
As part of the RI, a geologic study and borehole monitoring and sampling were conducted to identify the
main contaminant migration pathway and the extent to which hazardous substances remain in the mine workings.
The RI also assessed the affects of precipitation on the monitoring and sampling conducted in the mine
workings to determine if rainfall did effect the concentration in the analytical results.
EPA hydrogeologic studies conducted in 1981 and 1987 demonstrated that contaminants injected into the
HWAS borehole migrated downward through the Red Ash mine workings and into the Bottom Red Ash workings. The
contaminants followed the structure contours of the Bottom Red Ash mine workings, entered an underground
east-west drainage ditch and then reached the tunnel discharge location on the eastern side of the
Susguehanna. During the investigation additional boreholes were drilled, some existing boreholes were
reopened, and the monitoring, sampling and analytic program was conducted. One of the goals was to
determine if any accumulation of contaminants was present underground.
Using 14 different boreholes, the RI detected some of the hazardous substances detected in the 1985
release in 10 of the boreholes. The highest concentrations were found in the HWAS borehole. The frequency
of detection and the concentrations decreased as the borehole locations followed the main contaminant
-------
migration pathway along the Bottom Red Ash workings toward the east-west drainage ditch.
The second part of the hydrogeologic investigation attempted to correlate rainfall events with an
increase in water flow into the east-west drainage ditch and ultimately to the tunnel discharge location. In
general each storm produced a different rainfall amount and occurred over a different time duration. The
size of a storm is assessed by comparing return periods. A storm's return period is the average number of
years with in which the storm's rainfall amount will be egualed or exceeded.
As an example, the September 1985 storm caused by Hurricane Gloria had a return period of 55 years and
can be described as a "55 year storm". It is estimated that flow from the Tunnel exceeded 42 million gallons
per day during that rainfall event. During the RI three storms did exceed the 1 year storm level, and these
storms did increase the volume of water exiting the tunnel. Therefore, the RI concludes that measurement of
storm rainfall can be used to predict the actual flow from the Tunnel.
C. Surface Water and Sediment Investigation
Surface water samples were collected at three different locations on the eastern side of the
Susguehanna River. The first location was north of the tunnel discharge location. The second was located at
the Bridge just south of the discharge location and the third was located at the next bridge further
south. The surface water analytical results did not show detectable concentrations of the hazardous
substances at any of the three locations.
Sediment samples were also collected and analyzed from the same three locations. Three of the
hazardous substances were detected, but they did not exceed sediment guality criteria based on PADEP Water
Quality Criteria for the protection of fresh water aguatic life. Generally volatile, semi-volatile and
petroleum compounds were detected in sediments at higher levels at the bridge just south of the tunnel
discharge. These detections could be attributed to the previous discharge incidents.
D. Biota Investigation
A macro invertebrate investigation was conducted as part of the RI and samples were collected near the
three locations where surface water and sediment samples were taken. Generally, the macro invertebrate
community improves as the distance from the Lackawanna River and the Susguehanna River confluence increases.
Total number of specimens was smallest at a location north of the Tunnel and greatest at the second bridge
south of the tunnel. There were no changes directly attributable to the Butler Tunnel discharges on a day to
day basis. The Lackawanna River guality is the factor that probably explains the results of the river biota
study.
Table 2: Contaminant Concentration in Flushout Events
Chemical 1985 Flushout Day to Day
Maximum Report Tunnel Maximum Tunnel
Concentration (ug/1) Concentration (ug/1)
Benzene 26.8 ND
Carbon Tetrachloride 13.6 ND
Chloroform 7.0 ND
Ethylbenzene ND 9.0
Methylene Chloride 795.0 ND
Toluene 11.0 4.0
Trichloroethene ND ND
Total Xylenes ND 59.0
bis (2ethylhexyl) phthalate 36.0 8.0
4-Bromophenyl 166.0 ND
phenyl ether
1,2-Dichlorobenzene ND ND
1,3-Dichlorobenzene 26.5 ND
1,4-Dichlorobenzene ND ND
Diethyl phthalate 5.0 ND
Dimethyl phthalate 5.0 ND
Di-n-octyl phthalate 5.0 ND
Naphthalene ND ND
Phenol ND ND
Cyanide 1.0 ND
Oil NA 100.0
-------
ND = Non Detect NA = Not Analyzed
VII. SUMMARY OF SITE RISKS
The risk evaluation conducted under CERCLA to describe the risk posed by the Butler Mine Tunnel Site was
based on the presence of hazardous substances that were found in the oily hydrocarbon discharge that occurred
in 1985 and the same hazardous substances detected in the water discharged by the tunnel on a day to day
basis.
Table 2 indicates two conditions and respective concentrations of the contaminants of concern that were
reported during 1) the 1985 flushout of the oily liguid wastes and 2) the day to day concentrations as
reported in the Remedial Investigation.
As part of the RI/FS, am analysis was conducted to estimate human health and environmental problems that
could result at the Site. This analysis is referred to as a Risk Assessment ("RA"). The RA is used to
evaluate the need for remedial action. It also helps in determining the levels to which site related
contaminants have to be treated to ensure the protection of human health and the environment. The RA for the
Site characterizes the current and potential threats to human health and the environment based on reasonable
maximum exposures ( RMEs ) to contaminants if no remedial action were taken. The RA is used to evaluate the
need for remedial action. It also helps in determining the levels to which site related contaminants have to
be treated to ensure the protection of human health and the environment. The RA examined both
carcinogenic and non-carcinogenic risk at the Site for several exposure pathways that are the possible ways
that people or aguatic life could come into contact with the hazardous substances. The human health risk
assessment is based on the assumption that exposure to Site related contaminants can occur only if a complete
exposure pathway exists.
The exposure pathways are based on recreational use when people could be in the river at the discharge
location and include the following possibilities:
1. Accidental swallowing of surface water;
2. Accidental swallowing of river sediment;
3. Accidental swallowing of the oily hydrocarbon material
while in the river;
4. Breathing in volatile compounds from the oily
hydrocarbon material while in the river
5. Skin contact with surface water;
6. Skin contact with the oily hydrocarbon material;
7. Eating fish from the river.
The National Contingency Plan ("NCP") establishes acceptable levels of carcinogenic risk for Superfund
sites between 1 in 10,000 and 1 in 1,000,000 additional cancer cases Expressed as a scientific notation this
translates to an acceptable risk range between 10-4 and 10-6. In addition to carcinogenic risk, chemical
contaminants that are ingested (eaten), inhaled (breathed), or dermally absorbed (skin contact), may present
a non-carcinogenic health risk to humans. This kind of risk is expressed as a
Hazard Index ("HI"). An HI exceeding one (1) is considered an unacceptable risk.
Table 3 shows the risk to human health from various exposure pathways for the contaminant
concentrations detected in the day-to-day conditions and for a flushout condition. The calculation
indicates that the risks from the day-to-day discharge and from a flushout discharge for the hazardous
substances are within an acceptable risk range. This is based on the fact that the day-to-day water has only
a few of the hazardous substances and those are at low concentrations. The main factor for the calculation
of the flushout exposure is that the time of the exposure would be very short before an exposed person would
get out of the river.
The risk to the environment and aguatic life were evaluated a part of the RI/FS. When evaluating
protection of the environment and aguatic life, the RI/FS recognizes that day-to-day Tunnel discharge does
not show large amounts of the oily hydrocarbon material. However if another discharge or flushout
should occur, there would be a damaging effect on both river bank vegetation and aguatic life in the river.
The risk to the aguatic life is the potential for chronic toxicity which could include a decrease in number
of organisms, a decrease in reproductivity and in their mobility and viability.
Table 4 shows a comparison of the chemicals of concern for the flushout scenario to PADEP's Water
Quality Standards. It should be noted that several concentrations exceed the continuous aguatic life
criterion and the long term human health criteria.
In addition to the ecological risks identified with the hazardous substances contained in the oily
-------
hydrocarbon material, a potential risk for human exposure resulting from a release such as the 1985 flushout
is also possible.
Fuel oils are a complex mixture of aliphatic and aromatic hydrocarbons whose exposure potentials are
based on the fate of the individual components in the mixture. The more volatile components such as the low
molecular weight alkanes will evaporate and enter the atmosphere. The higher molecular weight aliphatic
components have very low water solubility and will remain in soil or in the water where they may be adsorbed
to particulate organic matter in water or soil and, in water, will settle to the sediment. At the Butler
Tunnel Site, the flushout of the oily hydrocarbon material also presents a risk for public
water intakes located on the Susguehanna River.
In conclusion, actual or threatened releases of hazardous substances from this Site, if not addressed by
implementing the response action selected in this ROD, may present an imminent and substantial endangerment
to public health, welfare, or the environment.
-------
TABLE 3 - SUMMARY OF INCREMENTAL BASELINE RISK
ASSESSMENT RESULTS
Incremental Hazard Index
Maximum
Average
Total (all pathways)
Flushout Water-Phase
Dermal contact with Flushout
surface water
Flushout
Inhalation of volatile at
Tunnel outlet(1)
Total (all pathways) Flushout
Hydrocarbon Accidental ingestion of Flushout
Material Phase a sheen(2)
Flushout
Inhalation of volatile Flushout
from a sheen(3)
Total (all pathways) Flushout
Water and Total for Possible Flushout
Hydrocarbon Flushout Conditions
Material Phases (all pathways)(4)
Exposure Concentration 70-Kg 35-F
Condition Media Exposure Pathway Level Adult Child
Water-Phase Accidental ingestion of Maximum
surface water Average
Dermal contact with
surface water
NC — Not Calculated. Risk values are not calculated because concentration data or exposure variables are not available,
(1) Based on 1985 sampling results at the Tunnel outlet.
(2) Exposure concentrations consider loss of volatile compounds.
(3) Based on modeling results for volatilization and a wind speed of 10.8 mph.
(4) Sum of water-phase and sheen values for flushout conditions.
-------
Table 4: 1985 Flushout Contaminant Concentration and Pennsylvania Water Quality Standards
Chemical
Benzene
Carbon Tetrachloride
Chloroform
Ethylbenzene
Methylene Chloride
Toluene
Tricholorethene
Total Xylenes
bis (2-Ethylhexyl)
phthalate
4-Bromophenyl ether
1,3-Dichlorobenzene
Diethyl phthalate
Dimethyl phthalate
Di-n-octyl phthalate
Naphthalene
Phenol
Cyanide (free)
1985 Flushout
Maximum Report
Tunnel
Concentration
(ug/1)
26.8
13.6
7.0
ND
795.0
11.0
ND
ND
36.0
166.0
26.5
5.0
5.0
5.0
ND
ND
1.0
Human Health
Criteria
(ug/1)
1
.3
6
3000
5
7000
3
300
2
N/A
400 (total DCB)
20,000
313,000
N/A
10
300
700
Continuous
Aquatic Life Criteria
(ug/1)
128
556
389
580
2368
330
450
211
909
54
69
800
495
N/A
43
20
5
ND = Non Detect NA = Not Analyzed / Insufficient Data to Develop Criteria
(1) PA Department of Environmental Protection. PA Water Quality Standards. PA Code Title 25, Chapter 16.
Water Quality Toxics Management Strategy - Statement of Policy as amended January 19, 1991.
-------
VIII. SUMMARY OF REMEDIAL ALTERNATIVES
The Feasibility Study ("FS") contains all the remedial alternatives considered for the Butler Mine Tunnel
Site. This section describes the alternatives detailed in the FS.
Table 5: Remedial Alternatives Examined
Alternative 1 No Action
Alternative 2 Institutional
Alternative 3 Institutional/Remedial Response
Alternative 4 Institutional/Multi-Port Outfall
Alternative 5 Surface Reclamation
A. Alternative 1 - No Action
Evaluation of a No Action Alternative is required by the NCP. This alternative does not include any
remedial action. It is expected that flushouts will continue to occur in the future during periods of
intense rainfalls and that this alternative would fail to protect against the flushouts. The flushouts
present a potential risk to human health and the environment.
B. Alternative 2 - Institutional
In this alternative, an Administrative Center could be established in order to perform ongoing
assessments of rainfall amounts and forecasts for more rainfall. The Center will be maintained for ten years
after its establishment. The Center would also monitor the volume of water flowing from the Tunnel
opening and monitor the water levels in the mines and the boreholes. The Center would evaluate the potential
for a flushout to occur and would advise PADEP when necessary. The Administrative Center would consist of an
office and storage facility. The Center would not have to be permanently staffed, but would have a
designated individual who would assess the weather conditions daily and would be responsible or the
monitoring of the Tunnel discharge. The FS proposes that the Center would be operated for a period of 10
years, which is the basis for the cost estimate.
Because of the extremely short lead time available to mobilize cleanup activities, it is critical to be
able to anticipate the conditions under which a flushout may occur. Therefore, long-range precipitation
forecasting would be used along with continuous monitoring at the Site. Long-range weather forecasts (three
to five days) may be obtained for the Pittston area on a continuing basis from a weather forecasting service.
This information would alert the Center to the potential for a significant rainfall event. The Site
hydrogeologic monitoring system would consist of a continuously recording precipitation
gauge linked by computer and telephone to the Center. It would be programmed to alert the Center when a
predetermined rainfall rate or precipitation volume is recorded. The precipitation gauge would be located
within the surface boundary of the Butler Mine. It would collect and record precipitation in the area
overlying the main contaminant migration pathway.
The Center would also conduct hydraulic monitoring of Tunnel flow. The Tunnel flow monitoring system
would consist of a continuously recording flow metering system linked by modem to the Center. The monitoring
system would be designed to operate over a predetermined range of possible river and Tunnel flow conditions,
and would be programmed to alert the Center at a predetermined flow rate.
Based on monitoring data, the Center would use a hydraulic model to estimate Tunnel flow rates from
forecasted and ongoing precipitation events. If projected peak flow rates exceed a predetermined critical
level, the Center would evaluate this projection, along with other available information and data to
determine if a potential flushout alert should be put in place. This would trigger Tunnel discharge chemical
monitoring, borehole water level monitoring, and water quality sampling. The Institutional Alternative's
preliminary cost estimates are listed in Table 6.
-------
Table 6: ALTERNATIVE 2 COST SUMMARY
ALTERNATIVE 2 COSTS*
Capital Costs $ 450,000
Annual Operation & Maintenance (O&M) Costs $ 150,000
Present-Worth Cost $ 1,300,000
Total Project $ 1,750,000
* ALL Costs are Estimated
C. Alternative 3 - Institutional/Remedial Response
The Institutional/Remedial Response alternative combines the institutional response actions described in
Alternative 2 with a remedial response effort. If a flushout were to occur, the discharge of hydrocarbon
materials would be a concern. This alternative, therefore, supplements Alternative 2 by including design and
implementation of two future response actions to clean up future discharges. The flushout remediation costs
included in this alternative would be sufficient to pay for containment of
hydrocarbon materials on the river and collection of materials that may accumulate along the shoreline
downstream of the Tunnel outlet.
If a flushout were to occur, the Wilkes Barre Regional office of PADEP would initiate the containment and
cleanup of the oil spill on the river. If the PADEP emergency response crew reguires assistance it would
notify EPA for additional emergency response personnel. The cleanup efforts would include the use of
containment and absorbent booms. The containment boom is a floatable, fence-like barrier and the absorbent
booms are used within the containment boom to soak up the floating oily material.
In preparation for a flushout, land-based, permanent anchors would be constructed upstream and downstream
of the discharge location by the Center. This would make it easier to deploy and secure the booms. In the
event high river currents or winds cause the containment boom to close on itself, the anchors would be
employed to attempt to reduce drift.
Booms, skimmers, clean-up materials and support eguipment, including a boat, would be purchased by the
Center. In addition, a response preparedness plan would be developed for storage and upkeep of the booms and
eguipment. The plan would cover response and deployment procedures; access to utilities; practice
deployment exercises; and the handling, transportation and disposal of hydrocarbon material removed from
within the boom system and from along the shoreline. In this alternative, the anchors would be constructed
as part of the remedy. The booms would be pre-purchased and stored near the site. These response measures
will help to expedite the PADEP and EPA containment and cleanup efforts. As noted above the flushout
remediation costs are also included in this alternative.
This alternative includes two other tasks as part of the capital costs. The six exploratory boreholes
outside the main contaminant migration pathways would be permanently closed. The Center would take on
additional responsibilities to implement a public information program about the risks of improper disposal
of household hazardous wastes. This program would attempt to inform citizens in the area regarding the
potential harmful environmental effects of improper waste disposal. Since many boreholes of various sizes
are located throughout the areas surrounding the Site, it is possible that some household wastes, such as
used motor oil, could be disposed into the mine pool. Additional contaminants could therefore continue to
reach the Susguehanna River. This program would be directed toward residents in the entire Wilkes-Barre,
Scranton area.
The Institutional/Remedial Response cost estimates include costs for Alternative 2 and the costs for
construction of the anchors, purchase of boom materials and a fund for flushout remediation.
Table 7: ALTERNATIVE 3 COST SUMMARY:
Capital Costs $ 800,000
Annual Operation & Maintenance. (O&M) Costs $ 170,000
Present-Worth Cost $ 1,500,000
Flushout Remediation $ 1,400,000
-------
Total Project $ 3,700,000
* All Costs are Estimated
D. Alternative 4 - Institutional/Multi-Port Outfall
This alternative combines the institutional response actions of Alternative 2 with a multi-port outfall
technology. A large pipe would be constructed to take water from the Tunnel discharge location to the bottom
of the river. The outfall pipe embedded in the river would disperse Tunnel flow via ports to achieve
immediate mixing with up to 50 percent of the river flow. The multi-port outfall system would be comprised
of a transition chamber and a 300 foot long outfall pipe with ports embedded in the river. The multi-port
outfall would not reduce the mass or concentration of contaminants in the Tunnel discharge. It would reduce
the concentrations of water-phase constituents in the river by diluting them with the river flow. Operation
and maintenance would be reguired for the transition chamber, outfall pipe, and the ports. As with
Alternative 2, PADEP would be advised if the potential for a flushout exists, and, if
necessary, would issue river-use advisories and implement other response actions.
The Institutional/Multi-Port Outfall alternative cost estimates include costs for Alternative 2 in
addition to the costs of constructing and installing the outfall pipe. The costs for Alternative 4 are
listed below:
Table 8: Alternative 4 Cost Summary
ALTERNATIVE 4 COSTS*
Capital Costs $ 1,850,000
Annual Operation & Maintenance (O&M) Costs $ 160,000
Present-Worth Cost $ 1,500,000
Flushout Remediation $ 1,400,000
Total Project $ 3,250,000
* All Costs are Estimated
E. Alternative 5 - Surface Reclamation
This alternative is intended to stop the rainfall water from entering the mine pool beneath the surface
of the entire Butler Mine Tunnel workings. The surface area would consist of 10 to 15 acres in the Pittston
Area. Surface areas would be regraded to reduce the volume of rainfall that enters the migration pathway,
thereby reducing the probability of a flushout.
Since the area is currently developed by residents and businesses, the amount of regrading and
reclamation needed for this alternative is limited. The remaining undeveloped area is insufficient to
accommodate for the necessary regrading project. It is estimated that only a 45 to 50 percent reduction of
the volume of water entering the mine pool in the migration pathway can be achieved. This alternative does
not include the institutional response actions described in Alternative 2 and does not include the cost of
obtaining access to the land.
Table 9: Alternative 5: Cost Summary
ALTERNTIVE 5 COSTS*
Capital Costs $ 2,250,000
Annual Operation & Maintenance (O&M) Costs $ 25,000
Present-Worth Cost $ 2,000,000
Total Project $ 2,450,000
* All Costs are Estimated
-------
IX. SUMMARY OF THE COMPARATIVE ANALYSIS OF ALTERNATIVES
This section compares the various remedial alternatives. Table 10 also has a comparison of the
alternatives
EPA evaluates each remedial alternative against the nine criteria specified in the National Contingency
Plan ("NCP"). The alternative selected must first satisfy the threshold criteria. Next the primary balancing
criteria are used to weigh the tradeoffs or advantages and disadvantages of each of the
alternatives. Finally, after public comment has been obtained the modifying criteria are considered.
Below is a summary of the nine criteria used to evaluate remedial alternatives.
Threshold Criteria:
Overall Protection of Human Health and the Environment: Whether the remedy provides adeguate protection and
how risks posed through each pathway are eliminated, reduced or controlled through treatment, engineering
controls, or institutional controls.
Compliance with ARARs:
Whether or not a remedy will meet all applicable or relevant and appropriate reguirements ("ARARs") of
Federal and State environmental statutes and/or whether there are grounds for invoking a waiver. Whether or
not the remedy complies with advisories, criteria and/or guidance that may be relevant.
Primary Balancing Criteria
Long-Term Effectiveness and Permanence:
The ability of the remedy to afford long term, effective and permanent protection to human health and the
environment along with the degree of certainty that the alternative will prove successful.
Reduction of Toxicity, Mobility or Volume: The extent to which the alternative will reduce the toxicity,
mobility, or volume of the contaminants causing the site risks.
Short Term Effectiveness:
The time until protection is achieved and the short term risk or impact to the community, on-site workers and
the environment that may be posed during the construction and implementation of the alternative.
Implementability:
The technical and administrative feasibility of a remedy, including the availability of materials and
services needed to implement that remedy.
Cost:
Includes estimated capital, operation and maintenance ("O&M"), and net present worth costs.
Modifying Criteria
State Acceptance:
Whether the State concurs with, opposes, or has no comment on the Selected Remedial Alternative.
Community Acceptance:
Whether the public agrees with the Selected Remedial Alternative.
A. Overall Protection of Human Health and the Environment
A primary reguirement of the Comprehensive Environmental Response, Compensation and Liability Act ("CERCLA"
is that the selected remedial action be protective of human health, welfare and the environment. A remedy is
protective if it eliminates, reduces, or controls current and potential risks posed through
each exposure pathway to acceptable levels through treatment, engineering controls, or institutional
controls.
Alternative 1, No Action, has no provisions to monitor the flow from the tunnel or even try to predict if
a discharge would occur. Any response would be initiated by local residents who would initially notify
proper authorities. The No Action alternative does not include treatment or controls, provides no reduction
in risk, provides no monitoring for the prediction of a flushout which could take hours to detect when the
hazardous substances may enter the Susguehanna River. The No Action Alternative is not protective of human
health and the environment, and it will not be considered further
Alternative 2, Institutional, has provisions to monitor the rainfall in the Pittston Area, monitor the
-------
volume of the flow at the discharge location and in the mine workings. This alternative provides for the
prediction of conditions that would indicate a possible mine discharge, and the notification of response
personnel.
Alternative 3, Institutional/Remedial Response combines the protectiveness of Alternative 2 with the
ability to provide the response personnel with the equipment and access needed to contain a discharge as
quickly as possible. This alternative provides the greatest protection because it minimizes the impact
by planning for a PADEP/EPA response action and it decreases the time it would take to initiate the
containment of a flushout.
Alternative 4, Institutional/Multi-Port Outfall combines the monitoring involved with Alternative 2 with
a mechanism to disperse the oily hydrocarbon material and dilute the concentration of hazardous substances
associated with the discharge. However the dispersion of the discharge would have a negative impact on the
ability of PADEP/EPA to respond and contain the flushout materials.
Alternative 5, Surface Reclamation, should decrease the number of pathways that the rainfall could use to
enter the mine workings. Alternative 5 does not include the monitoring of Alternative 2 and does not provide
for materials and the planned response of Alternative 3.
B. Compliance with ARARs
Each remedial action alterative evaluated in the FS or in this ROD addresses a response to a release Of
contaminants from the Butler Tunnel to prevent the flow of contaminants downstream in the Susquehanna River.
As such, we cannot rely on this remedy to achieve the requirements of the State General Water Quality
Criterion of 25 9A Code § 93.6 relating to impacts of oil on aquatic life, and thus, invoke the waiver to
this ARAR based on technical infeasibility. All alternatives will have the ability to comply with Aquatic
Water Criterion "AWQC" levels for toxic substances of concern at the Site. See 25 PA Code Chapter 16, Table
1 and Table 4 of this ROD.
In the event of a flushout, hydrocarbon material will be discharged to the river, however, the booms
described in Alternative 3, if deployed in a timely manner, will reduce the migration of hydrocarbon material
discharged from the Tunnel. Depending on the quantity of hydrocarbon material and river
turbulence, the multi-port outfall described in Alternative 4 may, or may not, achieve this objective.
Alternatives 2,3,4 and 5 would comply with the pertinent location- and action-specific ARARs indicated
in Section XI.B.2 and XI.B.3, respectively, of this ROD.
C. Long-Term Effectiveness and Permanence
None of the alternatives examined in the FS or this ROD remove all of the oily hydrocarbon material
from the mine workings or provide a permanent solution that would prevent the flushouts. Long term
effectiveness is based on the ability for PADEP/EPA to respond to any discharge events at the site.
While Alternative 2 provides for the monitoring to predict the potential for a discharge event, it does
not provide for long term effectiveness to mitigate such an occurrence.
Alternative 3 attempts to provide long term effectiveness by deployment of booms during river
conditions which could create a flushout. The boom system will reduce the migration of hydrocarbon material
discharged from the Tunnel during a flushout and thereby provide greater protection of water quality and
downstream riverbanks.
The effectiveness of Alternative 4 is largely dependent upon the quantity of hydrocarbon material
discharged during a flushout and turbulence of the river.
Alternative 5 is anticipated to be approximately 50% effective over the long term at reducing the
inflow of surface water into the main contaminant migration pathway, and hence reduce the probability of a
flushout. To the extent that municipal storm water drainage is discharged to the abandoned mine workings,
the effectiveness of this Alternative will be lessened. In conjunction with Alternative 5, an environmental
monitoring program may have to be adopted to identify and eliminate source infiltration.
D. Reduction of Mobility, Toxicity or Volume
None of the alternatives evaluated in the FS or this ROD would result in a permanent reduction in the
mobility, toxicity or volume of the hazardous substances or hydrocarbon material discharged to the river.
However, the continual drainage of water through the mine workings will reduce the toxicity and volume of
contaminants over time.
-------
Alternative 2 does not provide for a response action and does not reduce the mobility, toxicity or
volume of the contamination discharged.
In Alternative 3, booms, if deployed in a timely manner, could reduce the downriver migration of
hydrocarbon material discharged from the Tunnel during a flushout. Effectiveness, however, would be
dependent on the ability to achieve timely deployment during weather and river conditions that would make
deployment difficult.
If a flushout were to occur, Alternative 4, multi-port outfall, would have no effect on the guantity of
constituents or hydrocarbon material discharged into the river but concentrations of the hazardous substances
would be diluted by dispersion in the river.
Alternative 5, Surface Reclamation, has the potential to reduce the amount of water discharged in a
flushout and the probability of a flushout, but does not result in a permanent reduction in the mobility,
toxicity or volume of hazardous substances or hydrocarbon material discharged to the river.
E. Short-Term Effectiveness
Construction of the physical facilities comprising the various alternatives is not anticipated to have
any permanent adverse affect on the community, workers or the environment.
Certain temporary and limited community and environmental concerns (e.g., fugitive dirt and aguatic
habitat disturbance) may be realized with Alternatives 3, 4 and 5. In addition, in the case of Alternative
3, health and safety concerns for the remedial contractor's personnel, caused by the extreme weather and
hazardous river conditions anticipated at the time of a flushout, would need to be addressed in the remedial
contractor's health and safety plan.
The time reguired to plan and implement administrative and institutional controls and design and
construct physical facilities is estimated to range from one and one-half to two years for Alternatives 2, 3
and 4.
Alternative 5 would reguire EPA to execute a large number of agreements with the various property
owners who are located on estimated 10 to 15 acres needed for regrading. Depending on the difficulties
encountered in negotiating agreements with property owners, this time might take up to four to five years.
Alternative 5 has the least short term effectiveness because of the disruption to the area while the
regrading would be occurring. The other alternatives have basically eguivalent short term effectiveness.
F. Implementability
Implementation considers the time reguired to design and construct each of the alternatives.
Implementation of the administrative and institutional controls, and design and construction of the
physical facilities comprising the alternatives are considered feasible. Based on available information, no
major technical problems are anticipated with engineering-designs or construction, achieving compliance with
regulatory reguirements, or obtaining permits. The services and materials necessary for constructions for
Alternatives 3 and 4 are available.
For Alternative 3 in the event of a flushout, the ability to deploy booms in a timely manner may be
difficult. As previously noted, severe weather and hazardous river conditions anticipated at the time of a
flushout can be expected to cause significant concern for the safety of workers charged with the
responsibility for deploying booms.
The implementability of Alternative 4 is more difficult than for Alternative 3.
A potential major hindrance to the implementation of Alternative 5 will be obtaining of rights-of-way,
and land-use rights and restrictions necessary for design activities, construction of the surface reclamation
projects ard the protection of the projects when completed. Legal and land-use
rights and restriction costs may be very high, and the attempted resolution of these matters very
time-consuming. there is no assurance that agreements can be successfully negotiated at a reasonable cost.
If such is the case, implementation may not be achievable without the intervention of the federal government.
G. Cost
Evaluation of cost for each alternative includes calculation of the capital costs, O&M costs, and the
net present worth. Capital costs consist of direct items such as labor, materials, eguipment, and services.
Operation and Maintenance costs or annual costs, are the post-construction costs necessary to
-------
maintain the remedial action. O&M costs include such items as operating labor, maintenance, auxiliary
materials, and energy. The present worth is based on both the capital and O&M costs, and provides the means
of comparing the cost of different alternatives.
The total project cost are estimated as follows:
Alternative 1 - $ 0
Alternative 2 - $1,750,000
Alternative 3 - $3,700,000
Alternative 4 - $3,250,000
Alternative 5 - $2,450,000
The ultimate capital cost for Alternative 5 could substantially increase due to the costs of
rights-of-way and land-use rights and restrictions.
Included in the project costs above are the operating and maintenance costs. For all practical
purposes, the annual operating and maintenance cost estimates for Alternatives 2, 3, and 4 are egual
($150,000 to $170,000). In addition to the annual operating and maintenance cost estimate of $170,000,
Alternative 3 includes an additional $1,400,000 fund for remediation expenses in the event of a flushout.
H. State Acceptance
The Commonwealth of Pennsylvania has concurred with the selected remedy, but has stated its objection
to EPA not including the Pennsylvania Land Recycling and Environmental Remediation Standards Act, the Act of
May 19, 1995, P.L.4, No. 1995-2, 35 P.S. §6026.101 et seg. ("Act 2") as an ARAR in this
ROD.
I. Community Acceptance
The Proposed Plan for the Butler Tunnel Site were released for public comment on July 19, 1994. The
Proposed Plan identified Alternative 3 (Institutional/Remedial Response) as EPA's preferred alternative. EPA
reviewed all written and oral comments submitted during the public comment period. The comments from the
public did not seem supportive of the Preferred Alternative identified in EPA' s Proposed Plan. EPA
determined that no significant changes be made to the remedy, as it was originally identified in the Proposed
Plan.
After application of the Nine Criteria, and consideration of public comment, EPA's preferred
alternative presented in the Proposed Plan was selected by EPA to be the selected remedy at the Site. EPA
believes that the selected remedy represents the best balance of the remedial alternatives with respect to
the nine criteria, and it best satisfies the statutory reguirements of CERCLA, and Superfund guidance.
The selected remedy is protective of human health and the environment, complies with Federal and State
reguirements that are legally applicable or relevant and appropriate to the remedial action, and is
cost-effective. The selected remedy utilizes permanent solutions and alternative treatment or resource
recovery technologies, to the maximum extent practicable, and satisfies the statutory preference for remedies
that employ treatment that reduces toxicity, mobility, or volume as a principal element. Implementation of
the selected remedy will not involve extensive construction, excavation, or other
remedial action measures that would pose any appreciable short-term risks to the public or to the workers
during construction or implementation.
X. EPA'S SELECTED REMEDY: DESCRIPTION AND PERFORMANCE
STANDARD(S) FOR EACH COMPONENT OF THE REMEDY
A. General Description
EPA has reviewed the various alternatives presented in the FS for the Site and has selected Alternative
3, Institutional/Remedial Response, as the selected remedy. The selected remedy calls for the establishment
of an Administrative Center to: a) monitor rainfall, b) monitor flow rate at the Tunnel discharge location,
c) measure water levels in monitoring boreholes, and d) collect water samples for chemical analysis so as to
enable one to predict when a flushout may occur. The Administrative Center would be maintained for ten years
from its establishment. The Administrative Center would be responsible
for notifying PADEP when a potential for a flushout exists, as well as notifying PADEP when a flushout
occurs.
The selected remedy also includes preparation for future cleanup activities by constructing access
roads, placing anchors along the river's edge, and pre-purchasing containment and absorbent booms necessary
for the cleanup. The selected remedy includes an additional cost of $1.4 million to pay for the
-------
implementation of the cleanup of future discharges. The estimated costs are based on two cleanup efforts
Comparable to the 1985 flushout event. Costs could increase if more flushout events occur, or the volume of
flushout materials exceeds the previous releases.
B. Administrative Center
An Administrative Center will be established for a ten year period in order to perform ongoing
assessments of rainfall amounts and forecasts for more rainfall. The Center would also monitor the volume of
water flowing from the Tunnel opening and monitor the water levels in the mines and the boreholes. The
Center would evaluate the potential for a flushout to occur and would advise PADEP when necessary. The
Administrative Center would consist of an office and storage facility. The Center would not have to be
permanently staffed, but would have a designated individual who would assess the weather conditions daily and
would be responsible for the monitoring of the Tunnel discharge. The Center would be operated for a period
of 10 years, which is the basis for the cost estimate.
Because of the extremely short lead time needed to mobilize cleanup activities, it is critical to be
able to anticipate the conditions under which a flushout may occur. Therefore, long-range precipitation
forecasting would be used along with continuous monitoring at the Site. Long-range weather forecasts
(three to five days) would be obtained for the Pittston area on a continuous basis from a weather forecasting
service. This information would alert the Center to the potential for a significant rainfall event. The
Site hydrogeologic monitoring system would consist of a continuously recording precipitation
gauge linked by computer and telephone to the Center. It would be programmed to alert the Center when a
predetermined rainfall rate or precipitation volume is recorded. The precipitation gauge would be located
within the surface boundary of the Butler Mine.
-------
Alternative 1
Alternative 4
Alternative 5
Compliance with AlTARs
DEP/EPA will provide
protection
DEP/EPA will provide
protection
Administrative Center will
try to predict and will
monitor
DEP/EPA will provide
protection
Administrative Center will
try to predict and will
monitor
DEP/EPA will provide
protection
DEP/EPA will provide
protection
Long-Term
Effectiveness and
Permanence
DEP/EPA will respond as
needed
DEP/EPA will respond as
needed
DEP/EPA will respond as
needed
DEP/EPA will respond as
needed
DEP/EPA will respond as
needed
Reduction of Mobility,
Toxicity or Volume
Through Treatment
Implementability
DEP/EPA will provide
protection
Administrative Center will
try to predict and will
monitor
DEP/EPA will provide
protection
Administrative Center will
try to predict and will
monitor
DEP/EPA will provide
protection
Large guanity of
discharge to be disposed
within the river will make
boom deployment more
difficult
No prediction methods
used
DEP/EPA will provide
protection
Surface regrading of
limited areas will not
ensure decrease of
possibility of flush out
Cost (Estimated)
State Accpetence
Community Acceptance
-------
It would collect and record precipitation in the areas overlying the main contaminant migration pathway.
The Center would also conduct hydraulic monitoring of Tunnel discharge. The Tunnel flow monitoring
system would consist of a continuously recording flow metering system linked by modem to the Center. The
monitoring system would be designed to operate over a predetermined range of possible river and Tunnel flow
conditions, and would be programmed to alert the Center at a predetermined flow rate.
Based on monitoring data, the Center would use a hydraulic model to estimate Tunnel flow rates from
forecasted and ongoing precipitation events. If projected peak flow rates exceed a predetermined critical
level, the Center would evaluate this projection, along with other available information and data to
determine if a potential flushout alert should be out in place. The issuance of such a alert would trigger
Tunnel discharge monitoring, borehole water level monitoring, and chemical analysis in the mines and at the
discharge location. Chemical analysis for the Contaminants of Concern will be done in accordance with the
appropriate methods of analysis are set forth at 40 CFR Part 141.24(f) (16) (v) (Series 524.2 for organics).
The Quantitation Limits (QLs) for each method are specified in the Superfund Analytical Methods for Low
Concentration Water for Organic Analysis" 8/94 -OLC02.
The administrative center will alert PADEP, EPA, the National Response Center, Department of Interior,
Pennsylvania Fish and Boat Commission and Pennsylvania Game Commission when monitoring and water analysis
indicate that the release may be imminent.
C. Remedial Response
Two types of booms, namely containment and absorbent, would be utilized, as appropriate, in the event
of a flushout. The containment boom would be a floatable, fence-like barrier with a bottom draft designed to
reduce river velocity within the enclosure thus helping to contain floating hydrocarbon material. Absorbent
booms would be deployed within the containment boom enclosure to absorb the floating hydrocarbon material.
The containment boom would be deployed by the remedial contractor once the Center issues a potential flushout
alert. Absorbent booms would be deployed when Tunnel discharge chemical
monitoring, or visual observation, confirmed the presence of petroleum hydrocarbon in the Tunnel discharge.
Hydrocarbon material discharged from the Tunnel to the river prior to boom deployment, or hydraulically
swept out of the boom system, would adsorb to debris, vegetation and soil along the river shoreline
downstream from the Tunnel outlet. The removal of this material would also be undertaken by the remedial
contractor. This material would be disposed according to the CERCLA Off-site Disposal Policy.
Land-based upstream and downstream permanent anchors would be provided to assist with the deployment
and securing of the booms. Two pile cap anchors, each with an imbedded structural steel column containing
eyelets, would be constructed along the river shoreline; one approximately 200 feet upstream and the
second approximately 100 feet downstream of the Tunnel outlet.
The Center would purchase all the material to respond to a flushout. This material would include booms
and support eguipment, including a boat. In addition, a response preparedness plan would be prepared
covering, among other things, storage and upkeep of the booms and eguipment; response and deployment
procedures; access to utilities; practice deployment exercises; and the handling, transportation and disposal
of hydrocarbon material removed from within the boom system and from along the shoreline. Since weather
(wind, visibility) and river (current, roughness, floating debris) conditions at the time of a possible
flushout would be adverse, the plan would also set forth safety guidelines to be considered prior to
dispatching workers onto the river to deploy or maintain booms. The facilities and
eguipment for the remedial response would be subject to EPA approval and much met EPA specifications for
responding to an oil spill.
D. Engineering and Site Preparation Reguirements
Engineering design activities, and the preparation of construction drawings and specifications would
have to be undertaken prior to construction of physical facilities.
Two pile cap anchors, each with an imbedded structural steel column containing eyelets, would be
constructed along the river shoreline; one approximately 200 feet upstream and the second approximately 100
feet downstream of the Tunnel outlet. These anchors would be used by the remedial contractor to deploy and
secure the booms. In addition, it will be necessary to clear and maintain a boat launching area and access
road. The access road will extend from the nearest road to the river.
In preparation for a flushout, facilities would be provided at the Site for the temporary storage of
booms and support eguipment, personal protective eguipment, and hydrocarbon material removed from the boom
system. Provisions would also be made for worker and eguipment decontamination and/or off-site disposal of
contaminated eguipment, apparel, and decontamination residues. Since limited land area is available in the
-------
vicinity of the Tunnel outlet, the staging area for the temporary storage of hydrocarbon material removed
from the boom system would be designed to accommodate its rapid removal to an appropriate off-
site disposal site.
The transport of hydrocarbon material, decontamination residues and contaminated debris removed from
the water by the boom system for off-site disposal would be reguired in the event of a flushout.
Arrangements would be made for the collection, transport and off-site disposal of the hydrocarbon material,
together with contaminant-coated eguipment, cleanup supplies and shoreline debris.
Material contained within the boom system during a flushout, along with contaminant-coated eguipment,
clean-up supplies and shoreline debris, would be disposed of off-site at an appropriate
facility taking into consideration the guantity and composition of such material.
E. Community Relations
Another task of the selected remedy would be the preparation of an community information program to be
presented to local municipal officials and residents. The program would, among other things, be designed to
discourage the continued use of boreholes for waste disposal.
F. Borehole Closure
Six of the boreholes used during the RI at the site would be closed in accordance with the procedures
described in PA Code Title 25 of the Pennsylvania, Chapter 88.
G. Five-Year Reviews
Five Year reviews shall be conducted after the remedy is implemented to assure that the remedy
continues to protect human health and the environment.
H. Worker Safety
During all Site work, Occupational Safety and Health Administration ("OSHA") standards set forth at 29
C.F.R. Parts 1910, 1926 and 1904 governing worker safety during hazardous waste operations, shall be complied
with.
I. Deed Restrictions
Deed restrictions shall be developed and submitted to EPA for approval. Once approved, these deed
restrictions shall be placed in the deed to the Site by filing said restrictions with the Recorder of Deeds
of the appropriate County.
The deed restrictions shall prohibit the excavation or disturbance of the Site, for as long as
contaminations remains above performance standards.
The deed restrictions shall be valid and binding in the Township and the Commonwealth in which the Site
is located. The continuing need for these restrictions shall be re-evaluated during the Five-year Site
reviews which are conducted under CERCLA Section 121 (c), 42 U.S.C. Section 9621(c) .
J. Operation and Maintenance
An operational and maintenance (O&M) plan for the selected remedy shall be reguired. The performance
of the Administrative Center's functions shall be carefully monitored or a regular
basis and the system may be modified, as warranted by the performance data collected during operation.
Samples of river water near the tunnel discharge point shall be collected periodically to ensure that
contaminants contained in the day-to-day tunnel discharge are not significantly increasing.
XI. STATUTORY DETERMINATIONS
CERCLA directs EPA to select remedial actions that are protective of human health and the environment.
Section 121 of CERCLA also reguires that the selected remedial action comply with ARARs, be cost effective,
and utilize permanent treatment technologies to the maximum extent practicable. The following sections
discuss how the selected remedy for the Butler Mine Tunnel Site meets these statutory reguirements.
A. Protection of Human Health and Environment
The selected remedy is protective of human health and the environment. The Administrative Center will
provide continuous oversight of the potential for any release of hazardous substances from the tunnel. By
-------
monitoring the rainfall, the volume of water exiting the tunnel and monitoring the water level
as well as the potential for oil flow in the mine workings, the Center will be able to predict if a release
is likely to occur. In the event of a likely release, the selected remedy provides the materials for
collection of hazardous substances discharges. Booms and absorbent materials will be stored at the site for
immediate access for agency response. The selected remedy protects human health and the environment from
contaminated tunnel discharge while providing an acceptable level of risk
No distinct pool or pocket of the contaminated oil wastes was found that could be pumped out and
removed from the Tunnel.
The oil that is present is adhering to the rocks and gravel located in the collapsed mine workings
beneath the ground surface.
Because this remedy will result in hazardous substances remaining on site, and the potential exists for
the substances to be present above health-based levels, a review will be conducted within five years after
commencement of remedial action to ensure that the remedy continues to provide adeguate protection of human
health and the environment.
B. Compliance With And Attainment of Applicable of Relevant and Appropriate Reguirements ("ARARs")
Section 121(d) (2)(A)(i) and (ii) of CERCLA reguires that remedial actions shall meet all federal and state
environmental reguirements that are applicable or relevant and appropriate.
ARARs fall into three categories, depending on the manner by which they are applied to a site. The
characterization of an ARAR may not be unigue, as some ARARs are combinations of the following three
categories:
Contaminant-Specific: Health- or risk-based numerical values or methodologies that establish clean-up levels
or discharge limits for particular contaminants. Examples of contaminant-specific ARARs include Safe
Drinking Water Act Maximum Contaminant Levels and the Clean Water Act ("CWA") Water Quality Criteria
("AWQC"). Contaminant-specific ARARs would be utilized in assessing the concentrations of hazardous
substances in any discharge to the Susguehanna River
Location-Specific: Restrictions based on the concentration of hazardous substances or the conduct of
activities at specific locations. These may limit or preclude certain remedial actions or may apply to
portions of a site. Examples of location-specific ARARs include Resource Conservation and Recovery Act
("RCRA") location and floodplain management reguirements. To the extent remedial alternatives include
construction within or along the shoreline of waterways, the reguirements of location-specific ARARs must be
met.
Action-Specific: Technology or activity-based controls or restrictions on activities related to the
management of hazardous waste. To the extent remedial alternatives include the handling and disposal of
solid wastes (including hazardous and residual wastes), or storm water-related construction activities, the
reguirements of action-specific ARARs must be met.
1. Contaminant-Specific ARARs:
a. Water Quality Criteria. Title 25 Chapter 93 of the Pennsylvania Code sets forth water guality
standards. These standards are based upon water uses that are to be protected. The AWQC are considered by
the state in its regulation of discharges. Relative to toxic substances, Chapter 93 references Chapter 16
under Title 25 of the Pennsylvania Code. Section 16.51 provides in-stream water concentrations for toxic
substances that are to be used in the development of effluent limits. State AWQC would be applicable to any
remedial alternative that affects surface water guality. State AWQC for hazardous substances of concern at
the Site are presented in Table 4 of this ROD. To the extent the state has not established
numerical AWQC, federal non-enforceable water guality guidelines established by EPA under the provisions of
Section 304 of the CWA may be relevant and appropriate. Please see page 21 of this ROD for a discussion of a
waiver for reasons of technical impracticability for impacts-of oil on aguatic life 25 PA Code § 93.6.
b. Wastewater Treatment Regulations. Under Title 25 of the Pennsylvania Code, Chapter 95 lists general
reguirements for wastewater treatment. For discharges to waters affected by abandoned mine drainage, Section
95.5 states that industrial waste shall achieve as treatment, Best Conventional Pollutant
Control Technology or Best Available Technology Economically Achievable, as appropriate, to prevent pollution
in downstream waters.
2. Location-Specific ARARs
a. Dedging and Filling. Regulations implementing Section 404 of the Clean Water Act, 33 U.S.C. § 1344,
-------
codified at 40 CFR Part 230, set forth requirements related to the discharge of dredged or fill materials
into waters of the United States, including wetlands. To the extent remedial action includes construction of
land based anchors within or along the shoreline of waterways, the requirements of 40 CFR Part 230 may be
applicable.
b. Dam Safety Waterway Management. Title 25 Chapter 105 of the Pennsylvania Code governs the construction
and maintenance of dams, encroachments, and water obstructions located in, along, across or projecting into
regulated waters, including wetlands. To the extent remedial action includes construction within or along the
shoreline of regulated waterways, the requirements of Chapter 105 may be applicable.
c. Flood Plain Management. Title 25 PA Code Chapter 106 sets forth permitting requirements relating to
certain obstruction located in floodplains. To the extent that the remedial action involves "obstruction" in
a floodplain as defined in Chapte 106, the substantive permit requirements of that Chapter may be
applicable.
d. Fish and Wildlife Conservation. The Fish and Wildlife Coordination Act, 16 U.S.C. 661-666c, addresses
the conservation and enhancement of fish and wildlife resources. The Act requires consultation with the Fish
and Wildlife Service when water-resource or land-use development or improvement projects are
planned. The provisions of the Act are applicable since the remedial action includes construction along the
shores of waterways, modification to stream flows, or land reclamation.
e. Endangered Species Protection. The Endangered Species Act, 16 U.S.C.§§ 1536 (a) (2)and 1537 a. (a),
require the Fish and Wildlife Service to determine if a water-resource or land-use plan may adversely affect
an endangered specie(s). To the extent that remedial activities include construction along the shores of
waterways or land reclamation, such activities would have to be planned and implemented in accordance with
the provisions of this Act.
f. Abandoned Borehole Closure. Title 25 Chapter 88 of the Pennsylvania Code requires that exploration
holes, other drill or boreholes, wells or other exposed openings be sealed, backfilled, or otherwise managed.
The provisions of Chapter 88 would have to be considered with the implementation of the selected remedy.
g. Pennsylvania Storm Water Management Act of 1978 ("Act 167"). Section 13 of this Act requires that any
person engaged in the alteration/development of land which may affect storm water runoff characteristics,
implement control measures consistent with the provisions of applicable existing county storm water
management plans. Compliance with an existing county storm water management plan will have to be considered
should remedial activities alter the land in such a way as to affect storm water runoff.
3. Action-Specific ARARs
The PADEP has identified the Pennsylvania Land Recycling and Environmental Remediation Standards Act, the Act
of May 19, 1995, P.L.4, No. 1995-2, 35 P.S. §6026.101 et seq. ("Act II") as an ARAR for this remedy. EPA has
determined that Act II does not, on the facts and circumstances of this remedy, impose any
requirements more stringent than the federal standard.
a. Generation and Storage of Hazardous Materials. If hazardous wastes are generated during remedial
activities, requirements relating to the generation of hazardous waste set forth in Title 25 Pennsylvania
Code, Chapters 260-270 and/or 40 CFR Parts 260 and 270, as appropriate, must be met. If hazardous
waste from equipment decontamination or debris, etc., are stored on-site pending off-site disposal, all
applicable storage requirements in Title 25 Pennsylvania Code Chapters 260-270 and/or 40 CFR Part 262.34 or
264 and/or 268 must be met.
b. Municipal Waste Management. Title 25 of the Pennsylvania Code, Chapters 271 to 285, regulate the
management of municipal waste. If remedial activities generate wastes, these requirements will be applicable
to on-site activities.
c. Special Water Pollution Regulations. Title 25 Chapter 101. of the Pennsylvania Code requires PADEP
notification of an accident or incident involving any toxic substance that would endanger downstream water
users, or result in a danger of pollution or damage to property. If remedial response activities
are necessary, the requirements of Chapter 101 would be applicable.
d. National Pollutant Discharge Elimination System ("NPDES"). Title 25, Chapter 92 of the Pennsylvania
Code sets forth discharge criteria that include effluent limitations, standards of performance, toxic
effluent standards and prohibitions for pollutants discharged to waters of the state. To the extent a
remedial response to a flushout creates a point source discharge of pollutants, NPDES discharge limits are
applicable, however because of the potential volume of tunnel flushout compliance with an effluent
limitations established by the NPDES requirement is technically impracticable from an engineering
perspective. EPA is waiving this ARAR in accordance with CERCLA § 121(d) (4) (C).
-------
e. Oil Pollution Prevention. Procedures and methods to prevent the discharge of oil from
non-transportation-related on-shore facilities into navigable waters are established under 40 CFR 112. The
reguirements for the development and implementation of a Spill Prevention Control and Countermeasure
Plan to minimize the potential for oil discharges to navigable waters must be met for remedial response
actions.
f. Residual Waste Regulations. Reguirements pertaining to the generation, handling and management of
residual wastes are set forth under Title 25 of the Pennsylvania Code, Chapters 287 to 299. These
regulations govern residual waste processing, disposal, transportation, collection and storage. If remedial
activities generate residual wastes, these reguirements are applicable.
g. Fugitive Emissions Control. Title 25, Chapter 123 of the Pennsylvania Code regulates standards for
contaminant emissions, including those from open burning and demolition activities. Construction activities
generating fugitive air emissions would have to be conducted in accordance with the applicable provisions of
this regulation.
h. Borehole Closure. Title 25 of the Pennsylvania Code, Chapter 88, describes procedures applicable to
closure of the six boreholes used during the RI at the Site.
i. Erosion Control. Title 25, Chapter 102, of the Pennsylvania Code, reguires that those undertaking
earth-moving activities which create accelerated erosion or a danger of accelerated erosion, implement
certain soil erosion control and conservation measures. Chapter 102 sets forth the specific erosion and
sedimentation measures reguired to minimize accelerated erosion and sedimentation. This provision will have
to be considered should remedial activities either accelerate or create a danger of acceleration of soil
erosion.
j. Storm Water Discharge. Storm water discharge permit reguirements for construction activity that would
include clearing, grading or excavation of five or more acres are set forth in 40.C.F.R. § 122.26. To the
extent that such construction is undertaken, these reguirements may be applicable or relevant and
appropriate.
C. Cost Effectiveness
The selected remedy is cost-effective in providing overall protection in proportion to cost, and meets all
other reguirements of CERCLA. The NCP, at 40 C.F.R. Section 300.430(f) (ii) (D), reguires that EPA evaluate
cost-effectiveness by comparing all the alternatives which meet the threshold criteria - overall protection
of human health and the environment and compliance with ARARs - against three additional balancing criteria:
long-term effectiveness and permanence; reduction of toxicity, mobility and volume through treatment; and
short-term effectiveness. The selected remedy meets these criteria and provides for overall effectiveness in
proportion to its cost. The estimated present worth cost for the selected remedy is: $3,700,000.
The cost effectiveness of the selected remedy is provided by the ongoing monitoring which has the capability
for round the clock supervision of the tunnel discharge, but is less expensive by
developing a program to provide predictability for when a discharge may occur and by providing materials and
easy access to the tunnel discharge location. The selected remedy also includes provisions for costs
associated with two additions flushouts which secures the ability for a remedial response when needed.
D. Utilization of Permanent Solutions and Alternative Treatment
(or Resource Recovery) Technologies to the Maximum Extent Practicable
EPA has determined that the selected remedy represents the maximum extent to which permanent solutions and
treatment balance among the other evaluation criteria. Of those alternatives evaluated that are protective
of human health and the environment and meet ARARs, the selected remedy provides the best balance of
tradeoffs in terms of long-term and short-term effectiveness and permanence, cost, implementability,
reduction in toxicity, mobility, or volume through treatment, State and community acceptance, and preference
for treatment as a principal element.
The selected remedy will reduce contaminant levels in surface water and reduce the risks associated with
direct contact and ingestion of the flushout to the maximum extent practicable, as well as provide long-term
effectiveness.
E. Preference for Treatment as a Principal Element
The selected remedy does not satisfy CERCLA's statutory preference for treatment as a principal element. The
selected remedy addresses the primary threat of future ingestion and direct contact of contaminants through
release potential preparedness.
-------
XII. DOCUMENTATION OF SIGNIFICANT CHANGES
The Proposed Plan for the Butler Mine Tunnel Site was released for public comment on July 19, 1994. The
Proposed Plan identified Alternative 3 as the preferred alternative. EPA reviewed all written and oral
comments submitted during the public comment period. It was determined that no significant changes be made
to the remedy as it was originally identified in the Proposed Plan.
XIII. RESPONSIVENESS SUMMARY
OVERVIEW
On July 19, 1994, EPA published a Proposed Remedial Action Plan ("Proposed Plan") setting forth its preferred
alternative for the Butler Mine Tunnel Superfund Site located in the City of Pittston, Luzerne County
Pennsylvania, and announced the public comment period for such Proposed Plan. EPA held a public meeting on
the Proposed Plan on September 20, 1994. At this meeting, representatives from the EPA and PADEP answered
guestions about the Site and the remedial alternatives under consideration. A Fact Sheet containing
Site-related information was distributed at the public meeting. Those in attendance at the meeting included
local area residents, State and local officials, representatives from EPA, PADEP, and the PRPs.
In addition, EPA established a site information repository at the Luzerne County Court House Emergency
Management Center located on North River Street, Wilkes-Barre, Pennsylvania. The repository contains the
Administrative Record for the Site, which includes the RI/FS report, the Proposed Plan, and other relevant
documents. Additionally, a copy of the Administrative Record is maintained at EPA Region Ill's
Administrative Record Reading Room, 841 Chestnut Building, Philadelphia, Pennsylvania.
EPA screened five possible remedial alternatives fear cleaning up the contamination associated with the Site.
During the selection process, and prior to reaching the final decision regarding the selected remedy, EPA
gave consideration to nine key evaluation criteria while carefully considering State and Community acceptance
of the remedy. EPA selected Alternative 3 as the selected remedy for the Site. Alternative 3 satisfies es
the key criteria for remedy selection and minimizes the need for long-term treatment and management.
COMMENTERS' MAJOR ISSUES AND CONCERNS AND EPA'S RESPONSES
A. Concerns and Issues Raised During the September 20, 1994
Public Meeting:
1. Public Meeting Comment #1:
a. Summary of Senator Raphael Musto's Comments to EPA
During The September 20, 1994 Public Meeting:
Senator Musto was disappointed by what he considered to be the lack of meaningful alternatives for the
cleanup of the Butler Tunnel Site. Instead of completely removing the contaminated Site, the Senator noted
that the contamination wil remain on-site and that the Butler Mine Tunnel will continue to be a
community burden, potentially dangerous to the residents' health and our natural resources.
Senator Musto also noted that while the Proposed Plan states that where is a "low probability" of a future
discharge, it also acknowledges that a flush-out can occur "any time a large storm hits the area." He
further noted that, according to the Plan, the contaminants remain in the Site so there is still a potential
risk and that in the case of another flush-out, "there would be a damaging effect." He further stated that,
by the EPA's own admission, a problem exists and that the possibilities instill fear in the citizens of
Greater Pittston.
The Senator also noted the threat to the river, stating that our rivers must be conserved for future
generations, and that such natural resources are not disposal systems for any kind of waste, especially not
toxic material.
b. Other Comments Made During the September 28, 1994
Public Meeting With Regard To The Risks Associated
With The Proposed Alternative
The comments continued to emphasize that the possibility of a future discharge is very real; that any funds
expended at the Butler Tunnel should provide for the cleanup of an existing problem, not pay for the cleaning
up of a future spill; under the current alternative, we are waiting for an accident to happen;
and that we should take more precautions to prevent a future discharge.
EPA Response to Comment #1:
-------
No distinct pool or pocket of the contaminated oil wastes was found that could be pumped out and removed.
The oil that is present is adhering to the rocks and gravel located in the collapsed mine workings beneath
the ground surface. Therefore, excavation and removal is not technically feasible because the only way to
excavate and remove the rocks and gravel in the mine workings would be to completely disrupt the current
residential and commercial use of the surface property. EPA would not select a remedy which would so
dramatically disrupt the lives of these property owners.
2. Public Meeting Comment #2 by Unidentified Citizen:
A member of the audience wanted to know whether EPA has a position on landowners who own land above this
underground site and what are the rights of the landowners in this situation. Specifically, this commenter
asked about property owners who have cooperated with EPA to allow boreholes to be drilled on their
land and when EPA will close the boreholes.
EPA Response to Comment #2:
The selected remedy does not provide for excavating any individual's property to find a pool of waste oil.
In terms of the existing boreholes, the remedial alternative selected here will reguire closure of boreholes
installed in the remedial investigation if they are not needed for future monitoring. EPA
would, however, have to maintain at least some borehole locations to implement the monitoring program for
water level measurement and possible sampling for water in the mine workings to determine if any of the oil
is rising up to the point where a discharge could occur.
The remedial action will be designed to enable property owners to have full use of their property. If a
particular borehole is necessary to monitor the mine workings and it will interfere with the owner's use of
the property, EPA will evaluate if it can be relocated.
3. Public Meeting Comment #3:
Congressman Kanjorski suggested that the Butler Mine Tunnel and the mine workings are widespread throughout
the Wilkes Barre Region and perhaps some of the contaminants may have reached other outfall locations of acid
mine drainage. This prompted some discussion of a second operable unit to sample at a location near the
Wyoming Valley Sanitary Authority.
EPA Response to Comment #3:
Based on a review of the complex subsurface geology and extensive mine workings between these widely
separated areas EPA feels that it is unlikely that contaminants from the HWAS borehole can travel
approximately ten miles to the Sanitation Authority. However, EPA will conduct further investigation on seeps
located in the areas adjacent the Wyoming Valley Sanitary Authority. The purpose will be to determine if any
of the organic chemicals identified as hazardous substances for Butler Tunnel are present
at the Wyoming Valley Sanitary Authority location.
B. Comments Submitted on Behalf of Respondents to the Administrative Order:
Summary of General Comments
The Respondents were concerned that portions of EPA's description of the conditions at the Site are not
entirely correct and that the description of the remaining risks potentially posed by the Site are
exaggerated. Additionally, they claim that EPA's explanation of the role of the companies that funded the
studies has caused confusion. The PRPs also note that the waste oil that went into the Butler Tunnel was
placed there by an independent licensed oil recycling company; it was not placed there by any of the
companies that signed the Administrative Order or that funded Gannett Fleming's study of the Site. Finally,
the PRPs note that a number of clarifications are needed with respect to the tables accompanying EPA's
Proposed Remedial Action Plan.
Detailed Comments And Responses
1. Comment on Page 2 of the Proposed Plan:
According to the Respondents:
Paragraph 5, third and fourth lines, refer to a "flush
out" as a sudden discharge of the oily hydrocarbon
materials which have been disposed of "into the mine
pool." The phrase "into the mine pool" reflects a number
of misunderstandings. The misunderstandings carry forward
-------
into other portions of the report as well.
First, the waste was not disposed of "into the mine pool"
but rather into a borehole located at the site of the Hi-
Way Auto Service (HWAS) facility just off Route 81, near
Pittston. Second, the RI did not identify any "pool" or
"mother lode" of contamination. Rather, it disclosed low
levels of potential contamination in a number of abandoned
mine workings, including in the rubble and debris in the
abandoned Stark, Red Ash, and Bottom Red Ash mine
workings, and in a number of other locations.
The Respondents suggest that the phrase "mine pool" be deleted and the phrase "mine workings" should be
substituted.
EPA Response to Comment on Page 2 of the Proposed Plan:
This ROD reflects the comment and now refers to the waste oil as part of the mine workings.
2. Comment on Page 4 of Proposed Plan:
According to the Respondents, the Site Description needs to be rewritten to better conform to the evidence
developed during the RI and they proposed substitute language.
EPA Response to Comment on Page 4 of the Proposed Plan :
EPA has adopted the Respondents' language in the ROD.
3. Comment on Page 5 of the Proposed Plan:
According to the Respondents:
even though it is certainly true that there is at best a
"low probability" of a future discharge, it is not
"obvious" but in fact uncertain whether another discharge
can occur at all. The remedial investigation shows that
at least a 25-year storm and possibly more than a 50-year
storm would be necessary even to set up the hydraulic
potential for another flushout. In addition, sufficient
oily wastes would, at the same time, have to still be
present in the mines in order to create even the
possibility of a significant discharge into the
Susguehanna. In view of the discharges that have already
occurred, the natural attenuation over time, and the
absence of any located concentrations of oily wastes, the
combination of the hydraulic conditions and the necessary
concentrations, certainly describes a "low probability"
event.
EPA Response to Comment on Page 5 of the Proposed Plan:
The ROD maintains that a discharge could occur any time a large storm hits the area and that the monitoring
must be performed.
4. Comment on Page 5 of the Proposed Plan:
According to the Respondents:
the Proposed Plan does not correctly state the seguence of
events and confuses the "companies who were responsible
for the illegal dumping" (i.e., the oil recycling and
reclamation companies operated by Russell Mahler) with the
PRPs that signed the Administrative Order and funded the
RI/FS. They provided a rewritten paragraph and an
attachment of a chronology of significant events.
EPA Response to Comment on Page 5 of the Proposed Plan:
-------
Comments on the enforcement history of the Proposed Plan have been addressed in the ROD.
5. Comment on Page 6 of the Proposed Plan:
According to the Respondents:
the paragraph referring to "a potential risk" if another
flushout should occur is not supported by the risk
assessment contained in the FS. They suggested revised
language stating that there would be no unacceptable risks
to human health associated with these constituents.
EPA Response Comment on Page 6 of the Proposed Plan:
EPA still maintains that some constituents can pose an unacceptable risk to human health and the environment
if concentrations in the discharge are egual to or higher than the concentrations measured in the 1985
flushout.
6. Comment on Page 7 of the Proposed Plan:
According to the Respondents:
the heading of Column Two on Table 2 should be changed to
"1985 Flushout Maximum Tunnel Concentration (ug/L)". The
heading of Column Three should be changed to "Maximum Day
to Day Tunnel Concentration (ug/L)" to reflect that these
are not expected daily maximums, but instead the highest
day-to-day readings obtained throughout the study.
EPA Response to Comment on Page 7 of the Proposed Plan:
Table 2 reflects that the maximum concentrations of a flushout have been identified as the 1985 flushout and
that the day-to-day maximum concentrations are also reported.
7. Comment on Page 8 of the Proposed Plan:
According to the Respondents:
the Proposed Plan incorrectly states that is another
discharge or flushout should occur, there would be a
damaging effect on both river bank vegetation and aguatic
life in the river. They contend that any damage is not
supported by the Feasibility Study or by this experience of
past discharges at the site.
EPA Response to Comment on Page 8 of the Proposed Plan:
The suggested changes about the detrimental effect of any oily discharge on the river bank vegetation and the
aguatic life have not been incorporated. Even though the exposure of aguatic life to any such discharge is
likely to be short-term, the damage would still occur. The remedial action reguired by this ROD will
minimize any such damage.
8. Comment on Page 8 of the Proposed Plan:
According to the Respondents:
the language referring to Table 4 is potentially
misleading. Specifically, sentence states that: "[I]t
should be noted that several concentrations exceed the
continuous aguatic life criterion and the human health
criteria." Since these criteria are based on chronic
exposures, Respondents note that the analysis in Table 4
is an extremely conservative one.
EPA Response to Comment on Page 8 of the Proposed Plan:
-------
EPA recognizes that the statement reflects EPA's conservative position on the potential risks that could
occur.
9. Comment on Page 10 of the Proposed Plan:
According to the Respondents:
the heading of column two in Table 4 should be changed to
"1985 Flushout Reported Tunnel Concentration (ug/L)".
They also suggested that a footnote should be added to Table 4 indicating that the potential risks are
overstated.
EPA Response to Comment on Page 10 of the Proposed Plan:
The suggestion for a heading to Table 4 is accepted, but the footnote was not because the text of the risk
assessment discusses the transient or brief temporary exposure that could occur during a flushout and the
risk calculations included some dilution by the mixing in the river.
10. Comment on Page 12 of the Proposed Plan:
According to the Respondents:
the description of Alternative 3 which states that the
PADEP office would initiate contamination and cleanup of
the oil spill in the River is not necessarily correct.
EPA Response to Comment on Page 12 of the Proposed Plan:
PADEP's Wilkes Barre Region has an emergency response capability and it is fully expected that PADEP will be
the first agency to respond.
11. Comment on Page 13 of the proposed Plan:
According to the Respondents:
the summary of costs for Alternative 3 should contain a
line at the bottom showing the "Total Project Costs" as
$3,700,000.
EPA Response to Comment on Page 13 of the Proposed Plan:
This has been corrected.
12. Comment on Page 14 of Proposed Plan:
According to the Respondents:
in the description of Alternative 5, the references to the
costs not included in the estimate should note that land-
use costs were not included in the estimate.
EPA Response to Comment on Page 14 of Proposed Plan:
The costs for land-use in Alternative 5 have been included in the text of this ROD.
13. Comment on Page 15 of the Proposed Plan:
According to the Respondents:
the table showing the Analysis of Remedial Alternatives,
contains a typographical error. The phrase "on toxicity"
should be "in toxicity." They also noted a other
typographical error under the column for "Alterative 5."
EPA Response to Comment on Page 15 of the Proposed Plan:
-------
Both have been corrected.
C. Comments submitted by Federal and State Agencies
1. Comments Submitted by Department of Interior:
A comment raised by the Department of Interior in their review of the ROD concerns the requirement that the
Adminsitrative Center monitor the potential for a flushout for only a period of ten years. Several
questioned why the ROD would not require a thirty-year period.
EPA Response to Department of Interior Comment:
There are no regulations or guidance under CERCLA concerning the operation and maintenance period for a site
of this unique nature.
The initial flushout occurred in 1979. This ROD will have been signed in 1996 and the design phase of the
Superfund process will occur next. It is anticipated that the Administrative Center will be in place by 1998
and that the ten-year period will continue until 2008. This will result in thirty-three years of
monitoring for this Site.
In addition, the most recent storm and rainfall event in early 1996 did not produce the flushout discharge
and the necessary response that would have been provided for under this ROD. This Site will also require a
five-year review for site conditions and there remains a possibility that EPA could extend the operation
of the Administrative Center, if necessary.
2. Comment raised by PADEP:
When reviewing the draft ROD, PADEP noted that, "[h]istorically, PADEP has not been successful in trying to
predict the likelihood of a release. It should be noted that this type of monitoring may or may not prove
useful in predicting a release."
EPA Response to PADEP Comment:
EPA agrees with PADEP, but believes that this ROD reflects a realistic approach to provide some type of
predictive ability and to provide response capability for Federal and State agencies.
-------
Pennsylvania Department of Environmental Protection
Environmental Cleanup Program
Hazardous Sites Cleanup Section
Northeast Regional Office
2 Public Sguare
Wilkes-Barre, PA 18711-0790
(717) 826-2549
July 2, 1996
Mr. W. Michael McCade
Regional Administrator
USEPA Region III
841 Chestnut Building
Phildelphia, PA 19107
Re: Record of Decision Concurrence Letter
Butler Mine Tunnel NPL Site
City of Pittston, Luzerne County
Dear Mr. McCade:
The Record of Decision (ROD) received on May 31, 1996, for tbc Butler Mine Tunnel
Superfund Site located in the city of Pittston, Luzerne County, has been reviewed by the
Department.
The major components of the selected remedy include:
1. The establishment of an Administrative Center to a) monitor rainfall, b) monitor
flow rate at the Tunnel discharge location, c) measure water levels is in monitoring
boreholes, and d) collect water samples for chemical analysis to attempt to predict
when a charge of hazardous substances may occur.
2. The preparation for Future remedial responses by constructing access roads and
anchors along the river's edge, and prepurchasing containment and absorbent
booms necessary for any potential remedial response.
3. The design and implementation of two future response actions to clean up future
discharges.
4. The preparation of a Community Information Program to be presented to local
municipal officials and residents.
5. The closing of six (6) of the boreholes used during the Remedial Investigation.
6. Deed restrictions to prohibit excavation or disturbance of the site.
An Equal Opportunity/Affirmative Action Employer http://www.dep.state.pa.us Printed on
Recyled Paper ![]()
-------
Mr. W. Michael McCade July 2, 1996
I hereby concur with the EPA's proposed remedy with the following conditions and stipulations:
A. The Department vail be given the opportunity to review and comment on
documents and concure with decisions related to the design and implementation of
the remedial action. This would include the preparation of the Response
Preparedness Plan, engineering design activities, and construction
drawings and specifications.
B. EPA will ensure that the Department is provided an opportunity to fully participate
in any negotiations with responsible parties.
C. The Department will reserve our right and responsibility to take independent
enforcement actions pursuant to state law.
D. This concurrence with the selected remedial action is not intended to provide any
assurances pursuant to SARA Section 104(c) (3) .
E. The Department is taking the opportunity to assert that the Land Recycling and
Environmental Remediation Standards Act, the Act of May 19, 1995, P.L. 4, No.
1995-2, 35 P.S. § 6026.101 et. seg., is an ARAR for this site.
Although the Maximum Aguatic Life Criteria values were not included in Table 4 (page 13) in
the POD, they are a component of Pennsylvania's Water Quality Standard and therefore, are
ARAR's for this site.
Thank you for the opportunity to concur with this EPA Record of Decision. If you have any
guestions regarding this matter, please do not hesitate to contact me.
Sincerely,
William McDonnell
Regional Director
------- |