United States       Solid Waste and    EPA530-R-93-017
            Environmental Protection  Emergency Response  November 1993
            Agency          (5305)         www.epa.gov/osw
vvEPA    Solid Waste Disposal
            Facility Criteria
            Technical Manual

-------
                                   DISCLAIMER
The  information in this document has been funded wholly  or  in part by the United States
Environmental Protection Agency under Contract Number 68-WO-0025. Mention of trade names
or commercial products does not constitute endorsement or recommendation for use.
                                      NOTICE
The policies set out in this manual are not final Agency action, but are intended solely as guidance.
They are not intended, nor can they be relied upon, to create any rights enforceable by any party in
litigation with the United States.  EPA officials may decide to follow the guidance provided in this
memorandum, or to act at variance with the guidance, based on an analysis of specific site
circumstances.  The Agency also  reserves the right to change this guidance at any time without
public notice.

-------
                         TABLE OF CONTENTS

INTRODUCTION  	iv

CHAPTER 1. SUSP ART A	  1
     1.1  INTRODUCTION	  3
     1.2  PURPOSE. SCOPE. AND APPLICABILITY 40 CFR $258.1 (a)(b}	  4
     1.3  PURPOSE. SCOPE. AND APPLICABILITY (conO 40 CFR $258.1 (cWe^)	  5
     1.4  SMALL LANDFILL EXEMPTIONS 40 CFR $258.1 (T)	  7
     1.5  APPLICABILITY 40 CFR $258.1 (g)-(i)	  9
     1.6  DEFINITIONS 40 CFR $258.2 	  10
     1.7  CONSIDERATION OF OTHER FEDERAL LAWS 40 CFR $258.3	  14

CHAPTER 2. SUSP ARTS	  15
     2.1  INTRODUCTION	18
     2.2  AIRPORT SAFETY 40 CFR $258.10  	19
     2.3  FLOODPLAINS 40 CFR $258.11  	24
     2.4  WETLANDS 40 CFR $258.12	28
     2.5  FAULT AREAS 40 CFR $258.13  	37
     2.6  SEISMIC IMP ACT ZONES 40 CFR $25 8.14 	41
     2.7  UNSTABLE AREAS 40 CFR $258.15  	45
     2.8  CLOSURE OF EXISTING MUNICIPAL SOLID WASTE LANDFILL UNITS
           40 CFR $258.16  	61
     2.9  FURTHER INFORMATION	63

CHAPTERS. SUSP ART C	  73
     11    INTRODUCTION	76
     12    PROCEDURES FOR EXCLUDING THE RECEIPT OF HAZARDOUS
           WASTE 40 CFR $258.20  	77
     H    COVER MATERIAL REQUIREMENTS 40 CFR $258.21	84
     14    DISEASE VECTOR CONTROL 40 CFR $258.22  	85
     15    EXPLOSIVE GASES CONTROL 40 CFR $258.23  	87
     16    AIR CRITERIA 40 CFR $258.24 	101
     17    ACCESS REQUIREMENT 40 CFR $258.25  	103
     18    RUN-ON/RUN-OFF CONTROL SYSTEMS 40 CFR $258.26	104
     19    SURFACE WATER REQUIREMENTS 40 CFR $258.27	105
     3.10  LIQUIDS RESTRICTIONS 40 CFR $258.28 	107
     3.11   RECORDKEEPING REQUIREMENTS 40 CFR $258.29	110
     3.12  FURTHER INFORMATION	114
                                                     Revised April 13, 1998

-------
CHAPTER 4. SUSP ARID	  117
     4J,   INTRODUCTION	  121
     42   PERFORMANCE-BASED DESIGN 40 CFR $258.40  	  122
     43   COMPOSITE LINER AND LEACHATE COLLECTION SYSTEM 40 CFR
           $258.40	  149
     4,4   RELEVANT POINT OF COMPLIANCE 40 CFR §258.40(d) 	  188
     4,5   PETITION PROCESS 40 CFR S258.40(e^ 	  191
     16   FURTHER INFORMATION	  193

CHAPTERS. SUBPARTE	  205
     5J,   INTRODUCTION	  211
     12   APPLICABILITY 40 CFR $258.50 (a) & fb) 	  211
     13   COMPLIANCE SCHEDULE 40 CFR § 258.50 (c)	  214
     14   ALTERNATIVE COMPLIANCE SCHEDULES 40 CFR 258.50 (d)(e) & (g)
            	  215
     15   QUALIFICATIONS 40 CFR 258.50 (f) 	  217
     16   GROUND-WATER MONITORING SYSTEMS 40 CFR $258.51 (a)(b)(d)
            	  219
     17   GROUND-WATER   MONITORING   WELL   DESIGN   AND
           CONSTRUCTION 40 CFR $258.51 (c) 	  241
     18   GROUND-WATER SAMPLING AND ANALYSIS REQUIREMENTS 40
           CFR $258.53	  253
     19   STATISTICAL ANALYSIS 40 CFR $258.53 (gV(D 	  268
     5.10  DETECTION MONITORING PROGRAM 40 CFR $258.54 	  274
     5.11   ASSESSMENT MONITORING PROGRAM 40 CFR §258.55(a)-(f)	  281
     5.12  ASSESSMENT MONITORING PROGRAM 40 CFR §258.55(e)  	  286
     5.13   ASSESSMENT MONITORING PROGRAM 40 CFR §258.55(h)-(i)	  289
     5.14  ASSESSMENT OF CORRECTIVE MEASURES 40 CFR $258.56  	  291
     5.15   SELECTION OF REMEDY 40 CFR $258.57 (a)-fb) 	  298
     5.16  SELECTION OF REMEDY 40 CFR $258.57 (c) 	  299
     5.17  SELECTION OF REMEDY 40 CFR $258.57 (d)	  303
     5.18   SELECTION OF REMEDY 40 CFR $258.57 (e)-(f)	  305
     5.19  IMPLEMENTATION OF THE CORRECTIVE  ACTION PROGRAM 40
           CFR $258.58 (a) 	307
     5.20  IMPLEMENTATION OF THE CORRECTIVE  ACTION PROGRAM 40
           CFR $258.58 fb)-(d) 	309
     5.21   IMPLEMENTATION OF THE CORRECTIVE  ACTION PROGRAM 40
           CFR $258.58 (e)-(g) 	311
     5.22  FURTHER INFORMATION	313
Revised April 13, 1998

-------
CHAPTER 6. SUBPARTF 	  319
     6J,   INTRODUCTION	322
     £2   FINAL COVER DESIGN 40 CFR §258.60(a)	322
     63   ALTERNATIVE FINAL COVER DESIGN 40 CFR §258.60fb) 	332
     6A   CLOSURE PLAN 40 CFR §258.60(c)-(d)	338
     £5   CLOSURE CRITERIA 40 CFR §258.60(e)-(i) 	339
     £6   POST-CLOSURE CARE REQUIREMENTS 40 CFR $258.61	342
     6J_   POST-CLOSURE PLAN 40 CFR §258.61(c)-(e) 	345
     £8   FURTHER INFORMATION	348
                             APPENDICES

CHAPTER 2
APPENDIX I FAA Order 5200.5A 	69

CHAPTER 3
APPENDIX I - SPECIAL WASTE ACCEPTANCE AGREEMENT 	  115
iii                                                    Revised April 13, 1998

-------
                                    INTRODUCTION

      This manual was originally published in November, 1993 as a companion to the Criteria for
Municipal Solid Waste Landfills (MSWLF Criteria) that were promulgated on October 9, 1991 as
40 CFR Part 258. Since that time the MSWLF Criteria have been modified several times due to
statutory revisions and court decisions that are discussed below.  Most of the modifications delayed
the effective dates but all provisions are now effective.  All changes to the rule are included in the
text  of the manual.   The technical content of the manual did not require revision and only
typographical errors were corrected.

       The manual is now available in electronic format and can be accessed on the Environmental
Protection Agency's (EPA) web site .
Purpose of This Manual

       This technical manual has been developed to
assist owners/operators of MSWLFs in achieving
compliance with the revised MSWLF Criteria. This
manual is not a regulatory document, and does not
provide  mandatory  technical  guidance,  but does
provide assistance for coming into compliance with
the technical  aspects of the revised landfill Criteria.

Implementation of the Landfill Criteria

       The EPA fully intends that States and Tribes
maintain the lead role in implementing and enforcing
the revised Criteria. States will achieve this through
approved State permit programs.   Due to recent
decisions by the courts, Tribes will do so  using a
case-by-case review process.1  Whether in a  State or
in Indian Country, landfill owners/operators must
comply with the revised2 MSWLF Criteria.

State Process
Example of Technical and Performance
Standards in 40 CFR Part 258: Liners

Technical standard:
MSWLFs must be built with a composite
liner consisting of a 30 mil flexible mem-
brane liner over 2 feet compacted soil with a
hydraulic conductivity of no more than 1x10"
7 cm/sec.

Performance standard:
MSWLFs must be built in accordance with a
design  approved  by the  Director  of  an
approved State or as specified in 40 CFR
§ 258.40(e) for unapproved  States.  The
design must ensure  that the concentration
values listed in Table 1 of 40 CFR § 258.40
will not be exceeded in the uppermost aquifer
at  the relevant point  of compliance,  as
specified by the  Director of an approved
State under paragraph 40 CFR § 258.40(d).
       The Agency's role in the regulation of MSWLFs is to establish national minimum standards
that the states are to incorporate into their MSWLF permitting programs.  EPA evaluates state
   1 The Agency originally intended to extend to Indian Tribes the same opportunity to apply for permit program
approval as is available to States, but a court decision blocked this approach.  See the Tribal Process section
below for complete details.

   2EPA finalized several revisions to 40 CFR Part 258 on October 1, 1993 (58 FR 51536) and issued a correction
notice on October 14, 1993 (58 FR 53136). Questions regarding the final rule and requests for copies of the
Federal Register notices should be made to the RCRA/Superfund Hotline at 800 424-9346.
Revised April 13, 1998
                                      IV

-------
                                       Introduction
MSWLF permitting programs under the procedures set out in 40 CFR Part 239, "Requirements for
State Permit Program Determination of Adequacy," proposed on January 26, 1996 (61 FR 2584),
to determine whether programs are adequate to ensure that MSWLF owners/operators comply with
the federal standards.  As of early 1998, 40 States  and Territories had received full approval and
another seven had received partial approval.

       If their permitting programs have been approved by EPA, States can allow the use of flexible
performance standards established in 40 CFR Part 258 in addition to the self-implementing technical
standards for many of the Criteria.  Approved States can provide owners/operators flexibility in
satisfying the location restrictions, operating criteria, and requirements for liner design, ground-
water monitoring, corrective action,  closure and post-closure care, and financial assurance. This
flexibility allows for the consideration of site-specific  conditions in designing and operating a
MSWLF at the lowest cost possible while ensuring protection of human health and the environment.
In unapproved states, owners/operators must follow the self-implementing technical standards.

       EPA continues to work with States toward approval of their programs and recommends that
owners/operators stay informed of the approval status of the programs in their State.  States may be
in various stages of the program approval  process.  The majority of  states have received full
program approval and others have received "partial" program approval (i.e., only some portions of
the State  program are approved while the remainder of the program is pending approval).
Regardless of a State's program approval status, landfill owners/operators must comply with the
Criteria. States can grant flexibility to owners/operators only in the areas of their program that have
been approved.  For example,  a  state in which only the ground-water monitoring area of the
permitting program has been approved by EPA cannot  grant owners/operators flexibility to use
alternative liner designs.

       States are free to enact landfill regulations that are more stringent than the MSWLF Criteria.
Certain areas of flexibility provided by the Criteria (e.g., the small landfill exemption) may not be
reflected in a State program.  In such instances, the owner/operator must comply with the more
stringent provisions (e.g., no exemption).  These regulations would be enforced by the State
independently from the Criteria. NOTE:  The program requirements for approved States may
differ from those described in  this manual, which  are  based specifically  on the Federal
Criteria. Therefore, owners/operators are urged to work closely with their approved State in
order to ensure that they are fully in compliance with all  applicable requirements.

       State regulatory personnel  will  find this document helpful  when reviewing  permit
applications for landfills.  This manual presents technical information to be used in siting, designing,
operating, and closing landfills, but does not present a mandatory approach for  demonstrating
compliance with the Criteria.  This manual also outlines the types of information relevant to make
the demonstrations required by the Criteria, including demonstrations for restricted locations and
performance-based designs in approved States.

Tribal Process

       From the beginning of EPA's development of the permitting program approval process, the
Agency planned to offer permitting program approval to tribes as well as to states. In a 1996 court

v                                                                  Revised April 13, 1998

-------
                                       Introduction
decision3, however, the court ruled that EPA cannot approve tribal permitting programs.  The
Agency has therefore developed a site-specific rulemaking process to meet its goal of quickly and
efficiently providing owners/operators in Indian Country4 the same flexibility that is available to
landfill owners/operators in states with EPA-approved MSWLF permitting programs.  The process
is described in Site-Specific Flexibility Requests for Municipal Solid Waste Landfills in Indian
Country—Draft Guidance (EPA530-R-97-016).

       Under this process, an owner or operator can request to use certain alternative approaches
at a specific MSWLF site to meet the 40 CFR Part 258 performance standards. Unless the tribal
government is the owner/operator, the tribal government should review the request for consistency
with tribal law and policy and forward it to EPA with a recommendation. If EPA approves a
request, it will issue a site-specific rule allowing the use of the requested alternative approaches.
Owners/operators in Indian Country should therefore understand that when this manual refers to
areas of flexibility that can be granted by a "State Director," they would instead seek such flexibility
in the form of a site-specific rulemaking from EPA after tribal government review of their petition
for rulemaking. Although tribes will not issue permits as EPA-approved permitting entities under
the Criteria, they are free to enact separate tribal landfill regulations that are more stringent than the
Criteria.  Tribal regulations are enforced by the tribe independently of the Criteria.

       The  site-specific  process  encourages  active  dialogue  among   tribes,  MSWLF
owners/operators, EPA, and the public. The  guidance is designed so that the Agency works in
partnership with tribes.  Because EPA recognizes tribal sovereignty, EPA will respect tribal findings
concerning consistency of proposed approaches with tribal law and policy.

Revisions to Part 258

       Some important changes have been made to Part 258 since its original promulgation.  In
addition, other regulations that affect solid waste management have been implemented.

Ground-Water  Monitoring Exemption for Small,  Dry, and  Remote  Landfills  (40 CFR
§258.1(f)(l))

       The Land Disposal Program Flexibility Act (LDPFA) of 1996 reestablished an exemption
for ground-water monitoring for owners/operators  of certain small MSWLFs. EPA revised 40 CFR
§ 258.1(f)(l) on September 25, 1996 (61 FR 50409) to codify the LDPFA ground-water monitoring
exemption. To qualify for an exemption, owners/operators must accept less than 20 tons per day of
MSW (based on an annual average), have no evidence of ground-water contamination,  and  be
located in either a dry or remote location.  This exemption eases the burden on certain small
MSWLFs without compromising ground-water quality.5
   3 Backcountry Against Dumps v. EPA, 100 F.3d 147 (D.C. Cir. 1996).

   4 This manual uses the term "Indian Country" as defined in 40 CFR § 258.2.

   5 In the original 40 CFR Part 258 rulemaking, promulgated October 9, 1991, the Agency provided an
exemption from ground-water monitoring for small MSWLF units located in dry or remote locations. In 1993, the
U.S. Court of Appeals for the District of Columbia set aside this ground-water monitoring exemption. Sierra Club
v. EPA, 992 F.2d 337 (D.C. Cir. 1993).

Revised April  13, 1998                                                                  vi

-------
                                       Introduction
New Flexibility for Small Landfills (40 CFR §§ 258.21, 258.23, 258.60)

       In addition to reestablishing the ground-water  exemption for small,  dry,  and remote
MSWLFs, the LDPFA provided additional flexibility to approved states for any small landfill that
receives 20 tons or less of MSW per day. EPA revised 40 CFR Part 258 to allow approved states
to grant the  use of alternative frequencies  of daily cover,  alternative frequencies of methane
monitoring, and alternative infiltration layers for final cover (62 FR 40707 (July 29, 1997)).  The
LDPFA  also authorized flexibility to establish  alternative  means for demonstrating financial
assurance, and this flexibility was granted in another action.  The additional flexibility will allow
owners and operators of small MSWLFs the opportunity to reduce their costs of MSWLF operation
while still protecting human health and the environment.

Added Financial Assurance Options (40 CFR § 258.74)

       A revision to 40 CFR Part 258,  published November 27, 1996 (61 FR 60328), provided
additional options to the menu of financial assurance instruments that MSWLF  owners/operators
can use  to demonstrate that  adequate funds will be readily available for the  costs of closure,
post-closure care, and corrective action for known releases  associated with their facilities.  The
existing  regulations specify several mechanisms that owners and operators may use to make that
demonstration, such as trust funds and surety bonds.  The additional mechanisms are a financial test
for use by local government owners and operators, and a provision for local governments that wish
to guarantee the closure, post-closure, and corrective action costs for an owner or operator.  These
financial  assurance options allow local governments to use their financial strength to avoid incurring
the expenses  associated with the use of third-party financial instruments.  This action granted the
flexibility to all owners and operators  (including owners and operators of small facilities) to
establish alternative means for demonstrating financial assurance as envisioned in the LDPFA.

       Additionally, EPA promulgated a regulation allowing corporate financial tests and corporate
guarantees as  financial assurance mechanisms that private owners and operators of MSWLFs may
use to demonstrate financial assurance (63 FR  17706 (April 10, 1998)). This test extends to private
owners and operators the regulatory flexibility already provided to municipal owners or operators
of MSWLFs.  These regulations allow firms to demonstrate  financial assurance by passing a financial
test. For firms that qualify for the financial test, this mechanism will be less costly than the use of
a third party financial instrument such as a trust fund or a surety bond.

How to Use This Manual

       This document is subdivided into six chapters arranged to follow the order of the Criteria.
The first chapter addresses the general applicability of the Part 258 Criteria; the second covers
location  restrictions;  the third explains  the operating requirements;  the fourth discusses design
standards;  the fifth covers ground-water monitoring and corrective action;  and the sixth chapter
addresses closure and post-closure care. Each chapter contains an introduction to that section of the
Criteria.  This document does not include a  section  on the financial responsibility requirements;
vii                                                                  Revised April 13, 1998

-------
                                       Introduction
questions regarding these requirements may be addressed to EPA's RCRA/Superfund Hotline at 800
424-9346.

       Within each  chapter, the Criteria have been subdivided  into smaller segments.  The
Statement of Regulation section provides a verbatim recital of the regulatory language. The second
section, entitled Applicability, provides  a general explanation of the regulations and who must
comply with them.  Finally, for each segment of the regulation, a Technical Considerations section
identifies key technical issues that may need to be addressed to ensure compliance with a particular
requirement.   Each chapter ends with a section entitled Further Information, which provides
references, addresses, organizations, and other information that may be of use to the reader.

Limitations of This Manual

       The ability of this document to provide current guidance is limited by the technical literature
that was available at the time of preparation.  Technology and product development are advancing
rapidly, especially in the areas of geosynthetic materials and design concepts. As experience with
new waste management techniques expands in the engineering and science community, an increase
in published literature, research, and technical information will follow. The owners and  operators
of MSWLFs are encouraged to keep abreast of innovation through technical journals, professional
organizations, and technical information developed by EPA. Many of the Criteria contained in Part
258 are performance-based.  Future innovative technology may  provide additional means for
owners/operators to meet performance standards that previously  could not be met by a particular
facility due to site-specific conditions.

Deadlines and Effective Dates

       The original  effective date for the Criteria, October  9, 1993, was revised for several
categories of landfills, in response to concerns that a variety of circumstances was hampering some
communities' abilities to comply by that date. Therefore, the Agency provided additional time for
certain landfills to come into compliance, especially small units and those that accepted waste from
the 1993 Midwest floods.  As the accompanying table indicates, the extended general effective dates
for all MSWLF categories have passed, and all  units should now be in compliance.
Revised April 13, 1998                                                                 viii

-------
                           SUMMARY OF CHANGES TO THE EFFECTIVE DATES OF THE MSWLF CRITERIA

General effective date.1'2'3
This is the effective date for location,
operation, design, and closure/post-
closure.
Date by which to install final cover
if cease receipt of waste by the
general effective date.2 3
Effective date of ground-water
monitoring and corrective action.2 3
Effective date of financial
assurance requirements.3'4
MSWLF Units
Accepting Greater
than 100 TPD
October 9, 1993
October 9, 1994
Prior to receipt of waste
for new units; October
9, 1994 through October
9, 1996 for existing
units and lateral
expansions
April 9, 1997
MSWLF Units Accepting
100 TPD or Less; Are Not
on the NPL; and Are
Located in a State That
Has Submitted an
Application for Approval
by 10/9/93, or on Indian
Lands or Indian Country
April 9, 1994
October 9, 1994
October 9, 1993 for new
units; October 9, 1994
through October 9, 1996 for
existing units and lateral
expansions
April 9, 1997
MSWLF Units That
Meet the Small
Landfill Exemption in
40 CFR §258.1(f)
October 9, 1997; exempt
from the design
requirements
October 9, 1998
Exempt from the
ground-water
monitoring
requirements.5
October 9, 1997
MSWLF Units
Receiving Flood-
Related Waste
Up to October 9, 1994
as determined by State
Within one year of date
determined by State; no
later than October 9,
1995
October 9, 1993 for
new units; October 9,
1994 through October
9, 1996 for existing
units and lateral
expansions
April 9, 1997
1 If a MSWLF unit receives waste after this date, the unit must comply with all of Part 258.
2 See the final rule and preamble published on October 1, 1993 (58 FR 51536) for a full discussion of all changes and related conditions.
3 See the final rule and preamble published on October 6, 1995 (60 FR 52337) for a full discussion of all changes and related conditions.
4 See the final rule and preamble published on April 7, 1995 (60 FR 17649) for a discussion of this delay.
5 See the final rule and preamble published on September 25, 1990 (61 FR 50409) for a discussion of the ground-water monitoring exemption.

-------
CHAPTER 1

SUBPART A
 GENERAL

-------
                                   CHAPTER 1
                                   SUBPART A

                              TABLE OF CONTENTS
U,   INTRODUCTION	  3

L2   PURPOSE. SCOPE. AND APPLICABILITY 40 CFR §258.1 (a)(b)	  4
      1.2.1  Statement of Regulation	  4
      1.2.2  Applicability	  4
      1.2.3  Technical Considerations 	  4

H   PURPOSE. SCOPE. AND APPLICABILITY (cont.) 40 CFR §258.1 (c)-(e)	  5
      1.3.1  Statement of Regulation	  5
      1.3.2  Applicability	  5
      1.3.3  Technical Considerations 	  7

L4   SMALL LANDFILL EXEMPTIONS 40 CFR §258.1 (f)	  7
      1.4.1  Statement of Regulation	  7
      1.4.2  Applicability	  8
      1.4.3  Technical Considerations 	  8

L5   APPLICABILITY 40 CFR §258.1 (g)-(j)	  9
      1.5.1  Statement of Regulation	  9
      1.5.2  Applicability	  10
      1.5.3  Technical Considerations 	  10

L6   DEFINITIONS 40 CFR §258.2	  10
      1.6.1  Statement of Regulation	  10
      1.6.2  Applicability	  13
      1.6.3  Technical Considerations 	  13

L7   CONSIDERATION OF OTHER FEDERAL LAWS 40 CFR §258.3	  14
      1.7.1  Statement of Regulation	  14
      1.7.2  Applicability	  14
      1.7.3  Technical Considerations 	  14

-------
                                    CHAPTER 1
                                    SUBPART A
                                     GENERAL
1.1 INTRODUCTION

Under the authority of both the Resource Conservation and Recovery Act (RCRA), as amended by
the Hazardous and Solid Waste Amendments (HSWA) of 1984, and Section 405 of the Clean Water
Act, the EPA issued "Solid Waste Disposal Facility Criteria" (40 CFRPart 258) on October 9, 1991.
These  regulations revise the "Criteria for Classification of Solid Waste Disposal Facilities and
Practices," found in 40 CFR Part 257.  Part 258 was established to provide minimum national
criteria for all solid waste landfills that are not regulated under Subtitle C of RCRA, and that:

    •  Receive municipal solid waste; or
    •  Co-dispose sewage sludge with municipal solid waste; or
    •  Accept nonhazardous municipal waste combustion ash.

Part 257 remains in effect for all other non-hazardous solid waste facilities and practices.

Subpart A of the regulations defines the purpose, scope, and  applicability of Part 258 and provides
definitions necessary for proper interpretation of the requirements.  In summary, the applicability
of the  Criteria is dependent on the operational status of the MSWLF unit relative to the date of
publication of Part 258 and the effective date of the rule (October 9, 1993). An exemption from the
design  requirements is provided for small MSWLF units if specific operating, environmental, and
location conditions are present. [The final rule as promulgated on October 9, 1991 exempted the
owner/operators of small landfill units from both Subparts D and E. On May 7, 1993 the U.S. Court
of Appeals for the District of Columbia Circuit issued an opinion  that EPA did not have the
authority to exempt these small landfills from the ground-water monitoring requirements (Subpart
E), therefore, these small landfills can not be exempted from Subpart E. EPA is delaying the date
of compliance for these units until October 9,  1995 (58 FR 51536).   In addition, the Agency is
investigating alternative ground-water monitoring procedures for these units.]

Owners or operators of MSWLF units that do not meet the Part 258 Criteria will be considered to
be engaging in the practice of "open dumping" in violation  of Section 4005 of RCRA.  Similarly,
owners and operators of MSWLF units that receive sewage sludge and do not comply with these
Criteria will also be in violation of applicable sections of the Clean Water Act.

-------
                                      Subpart A
1.2 PURPOSE, SCOPE, AND
    APPLICABILITY
    40 CFR §258.1 (a)(b)

1.2.1 Statement of Regulation

    (a)    The purpose of this part is to
establish   minimum national   criteria
under the Resource Conservation and
Recovery Act  (RCRA  or  the  Act),  as
amended,  for all municipal solid waste
landfill (MSWLF)  units  and under the
Clean Water   Act,  as  amended,  for
municipal  solid waste landfills that are
used to dispose of sewage sludge. These
minimum  national  criteria ensure the
protection  of  human  health  and  the
environment.

    (b)    These Criteria  apply to owners
and  operators  of  new MSWLF units,
existing  MSWLF   units,  and lateral
expansions,    except    as   otherwise
specifically provided in  this part; all
other solid waste disposal facilities and
practices that  are  not  regulated under
Subtitle  C of RCRA are subject to the
criteria contained in Part 257.

1.2.2  Applicability

Owners and operators of MSWLF  units that
receive municipal solid waste or that receive
municipal waste combustion ash and are not
currently regulated under Subtitle  C  of
RCRA must comply with  the   Criteria.
Furthermore, MSWLF units that receive and
co-dispose sewage sludge must comply with
Part 258 to  be in compliance with Sections
309 and 405(e) of the Clean Water Act.
1.2.3  Technical Considerations

Criteria that define a solid waste disposal
facility are contained within Part  257 of
RCRA (Criteria for Classification of Solid
Waste Disposal  Facilities and Practices).
Definitions pertaining to the revised Criteria
are included in the definition section of Part
258.  A MSWLF unit is defined as a discrete
area of land or excavation that receives
household waste, and that is not considered
a   land    application   unit,    surface
impoundment, injection well, or waste pile
as those terms are defined under §257.2. An
existing unit is a  solid  waste disposal unit
that is receiving solid waste as of October 9,
1993.  A  lateral expansion is a horizontal
expansion of the waste boundaries of an
existing MSWLF unit.  A new unit is  a
MSWLF unit that has  not received waste
before October 9, 1993.

In addition to household waste, a MSWLF
unit may  receive commercial waste, non-
hazardous  solid  waste  from  industrial
facilities including non-hazardous sludges,
and   sewage  sludge  from wastewater
treatment  plants.   The terms commercial
solid waste, industrial waste and household
waste are  defined in §258.2 (Definitions).

The types of landfills regulated under Part
257 include those facilities that receive:

•   Construction  and  demolition   debris
    only;

•   Tires  only; and

•   Non-hazardous industrial waste only.

-------
                                       General
MSWLF  units  are  not  intended,  nor
allowed, to receive regulated quantities of
hazardous  wastes.    Should  a MSWLF
owner/operator discover that a shipment
contains regulated quantities of hazardous
waste while still  in the possession of the
transporter,  the  owner/operator  should
refuse  to  accept  the  waste  from the
transporter.    If  regulated  quantities of
hazardous  wastes  are  discovered  after
accepting the waste from the transporter, the
owner/operator must return the shipment or
manage  the  wastes in accordance with
RCRA Subtitle C requirements.

Subtitle C of RCRA establishes  procedures
for   making    a   hazardous    waste
determination.    These  procedures are
summarized in Chapter 3 and Appendix B of
this document.
1.3 PURPOSE, SCOPE,
    AND APPLICABILITY (cont.)
    40 CFR §258.1 (c)-(e)

1.3.1 Statement of Regulation*

*[NOTE: EPA finalized several revisions
to 40 CFR Part 258 on October 1, 1993
(58 FR 51536)  and issued a correction
notice on October 14,1993 (58 FR 53136).
These  revisions delay the effective date
for some categories of landfills.   More
detail  on the content  of the revisions is
included in the introduction.]

   (c)   These Criteria  do not apply  to
municipal solid waste landfill units that do
not receive waste after October 9,1991.

   (d)  MSWLF units that receive waste
after  October   9,   1991  but   stop
receiving waste before October 9, 1993
are exempt from all the requirements of
Part   258,  except   the  final   cover
requirement specified in Section 258.60(a).
The final cover must be installed within six
months of last receipt of wastes. Owners or
operators of MSWLF units described in
this paragraph that fail to complete cover
installation within this six month period
will be subject to all the requirements of
Part 258, unless otherwise specified.

    (e)    All MSWLF units that receive
waste  on or after October 9, 1993 must
comply with all requirements of Part 258
unless  otherwise specified.

1.3.2 Applicability

The applicability of Part 258, in its entirety or
with exemptions to specific requirements, is
based  upon the operational status  of the
MSWLF  unit  relative to  the  date  of
publication, October 9, 1991, or the effective
date of the rule, October 9,  1993 (see Figure
1-1).   Three  possible operational scenarios
exist:

    (1)    The MSWLF unit received its 1 ast
load of waste prior to October 9, 1991. These
facilities are exempt from all requirements of
the Criteria.

    (2)    The  last load  of waste  was
received  after October  9, 1991, but before
October 9,  1993. The owners and operators
must  comply only with  the  final cover
requirements of §258.60(a).  If the final cover
is  not installed within six (6) months of the
last  receipt  of  wastes,  the  owners  and
operators will be required to comply with all
requirements of Part 258.

-------
                                               Subpart A
               Date of
             Publication
           (Octob«ri, 1981)
C
o
S
                   YES
            Effective Date  -
           (October9, 1993)
 MSWLF Must
Comply with All
  of Part 256
                                                                      NO
                                                        Part 258 Does
                                                          Not Apply
                                                                                                Final Cover
                                                                                              Requirements of
                                                                                              §258.60(ai Apply
  Did MSWLF
 Recieve Cover
Within 6 Mos. of
 Firta! Reeetp
  of Waste
                                               Figure 1-1
                                        Applicability Flow Chart

-------
                                      General
    (3)    The MSWLF unit continues to
receive waste after October 9,  1993.  The
owners or operators must comply with all
requirements of Part 258, except  where
specified otherwise.

1.3.3 Technical Considerations

MSWLF units that receive the last load of
waste between October 9, 1991 and October
9, 1993, must complete closure within six
months of the last receipt of waste. Closure
requirements are  specified in  Subpart  F;
however,  these  MSWLF units  will be
subject only to the closure requirements of
§258.60(a) unless they fail to complete
closure within the six-month period.  The
alternative cover design is not an option for
MSWLF units in unapproved States.

The final cover system must be designed to
minimize infiltration and erosion. The final
cover must have a permeability that is less
than or equal  to  the permeability  of the
bottom liner system or the natural subsoils
present, or a permeability no greater than 1
x 10"5 cm/sec, whichever is less. The system
must be composed of an erosion layer that
consists of at least six inches of an earthen
material capable of sustaining native plant
growth  and an  infiltration  layer that is
composed of at least 18 inches of an earthen
material.  However, if a MSWLF  unit is
constructed with a synthetic membrane in
the liner system,  it is anticipated that the
final cover  also will require a synthetic
liner.   Currently, it is  not possible  to
construct   an  earthen  liner  with  a
permeability less than or equal to a synthetic
membrane.        Detailed    technical
considerations for the cover requirements
under §258.60(a) are provided in Chapter 6.
1.4 SMALL LANDFILL
    EXEMPTIONS
    40 CFR §258.1 (f)

1.4.1 Statement of Regulation

    (f)(l) Owners or operators of new
MSWLF units, existing MSWLF units,
and lateral expansions that dispose of less
than twenty (20)  tons of municipal solid
waste daily, based on an annual average,
are exempt  from  subparts D [and E]* of
this Part, so long as  there is no evidence
of existing ground-water contamination
from  the MSWLF unit and the MSWLF
unit serves:

    (i)    A community that experiences
    an  annual interruption of at least
    three consecutive months of surface
    transportation that prevents access to
    a   regional   waste   management
    facility, or

    (ii)   A  community  that  has  no
practicable     waste     management
alternative and the landfill unit is located
in an area that annually receives less than
or equal to 25 inches of precipitation.

    (2)   Owners or operators of new
MSWLF units, existing MSWLF units,
and  lateral expansions that  meet the
criteria in (f)(l)(i) or (f)(l)(ii) must place
in the operating  record  information
demonstrating this.

    (3)   If the  owner or operator of a
new MSWLF unit, existing MSWLF unit,
or lateral expansion has knowledge  of
ground-water  contamination  resulting
from  the  unit that has  asserted the
exemption in (f)(l)(i) or (ii), the owner or
operator    must    notify   the   State

-------
                                      Subpart A
Director  of such contamination  and,
thereafter, comply with Subparts D [mttt
E]* of this Part.

* [Note: On May 7, 1993 the U.S. Court of
Appeals for the District of Columbia Circuit
issued an opinion that EPA did not have the
authority  to exempt these small landfills
from    the   ground-water   monitoring
requirements (Subpart E), therefore,  these
small landfills can not be exempted from
Subpart E.  EPA  is delaying the date of
compliance for these units until October 9,
1995 (58 FR 51536; October 1,  1993).]

1.4.2 Applicability

The exemption from Subpart D (Design) is
applicable only to owners or operators of
landfill units that receive, on an annual
average, less than 20 tons of solid waste per
day.  The exemption is allowed so long as
there  is no evidence of existing ground-
water contamination from the MSWLF unit.
In addition, the MSWLF unit must serve a
community that meets one of the following
two conditions:

•   For at least three consecutive months of
    the year, the  community's municipal
    solid  waste  cannot  be transported by
    rail, truck, or  ship to a regional waste
    management facility; or

•   There is no practicable alternative for
    managing wastes, and the landfill unit
    is  located in an area that receives less
    than 25 inches of annual precipitation.

If either of the above two conditions is met,
and there is no evidence of existing ground-
water contamination, the landfill unit owner
or operator is eligible for the  exemption
from the design, ground-water monitoring,
and  corrective action requirements.  The
owner or operator must place information
documenting eligibility for the exemption in
the facility's operating  record.  Once an
owner or operator can no  longer demon-
strate compliance with any of the conditions
of the exemption, the MSWLF facility must
be in compliance with Subpart D.

1.4.3 Technical Considerations

The  weight criterion of 20 tons does not
have  to  be   based on  actual  weight
measurements but may be based on weight
or volume  estimates.  If the daily waste
receipt records, which include load weights,
are  not available for the  facility, waste
volumes  can  be   estimated  by  using
conversion factors of 1 ton = two to three
cubic yards per ton depending on the type of
compaction  used at the  MSWLF unit.
Waste weights may be determined  by
counting  the  number  of  trucks  and
estimating an average weight for each.

To determine the daily waste received, an
average may be used. If the facility is not
open on a daily basis, the average number
should reflect that fact.   For example, if a
facility is open four days  per week (208
days/year) and accepts  25  tons each day,
then the average  daily  amount of waste
received can be calculated as follows:


  Average Daily Waste Calculation
  4 days/week x 52 weeks/year = 208 days/year; and
  25 tons/day x 208 days/year = 5200 tons/year; then
  5200 tons/year •+• 365 days/year = 14.25 tons/day.
  The facility would meet the criteria for receiving less than
  20 tons per day.

-------
                                       General
Compliance with  the 20  tons per  day
criterion should be based  on all  waste
received, including household  waste  and
agricultural or industrial wastes. As defined
in the regulations, household waste includes
any solid waste (including  garbage, trash,
and sanitary waste in septic tanks) derived
from  households  (including  single  and
multiple residences,  hotels  and motels,
bunkhouses, ranger stations, crew quarters,
campgrounds,  picnic grounds, and day-use
recreation areas).

The exemption from Subpart D requires that
there be "no evidence  of existing ground-
water contamination"  as a condition for
eligibility.  Evidence of contamination may
include detected or known contamination of
nearby  drinking water wells,  or physical
evidence such  as stressed vegetation that is
attributable to  the landfill.

One of two other conditions must be present
for the  exemption to apply.  The first of
these conditions is an annual interruption in
transportation for at least three consecutive
months.  For example, some rural villages in
Alaska may be restricted from transporting
wastes to a regional facility due to extreme
winter climatic conditions.  These villages
would find it impossible to transport wastes
to a regional waste  facility for at least three
months  out of the year  due to snow and ice
accumulation.

The second condition is composed of two
requirements:  (1) the lack of a practicable
waste management alternative; and (2) a
location that receives  little rainfall.  The
exemption applies  only to those areas that
meet both  requirements.

The determination of a "practicable waste
management    alternative"    includes
consideration of technical,  economic, and
social factors.  For example,  some small
rural communities, especially in the western
part of the United States, are located great
distances    from    alternative    waste
management  units (other MSWLF units,
composting   facilities,  municipal  waste
combustors, transfer stations,  etc.) making
regionalization  of  waste   management
difficult.

Furthermore, many  rural communities are
located in arid areas that receive 25 inches
or less  of precipitation annually, which
reduces the  likelihood  of ground-water
contamination because of lessened leachate
generation and contaminant  migration.
Rainfall information can be obtained from
the National Weather Service, the National
Oceanographic     and    Atmospheric
Administration (NOAA), and the United
States  Geological Survey (USGS) Water
Atlases.
1.5 APPLICABILITY
    40 CFR §258.1 (g)-(j)

1.5.1 Statement of Regulation

    (g)  Municipal solid  waste landfill
units failing to satisfy these criteria are
considered open dumps for purposes of
State solid waste management planning
under RCRA.

    (h)  Municipal solid  waste landfill
units  failing  to  satisfy  these  criteria
constitute   open  dumps,  which  are
prohibited under Section 4005 of RCRA.

    (i) Municipal solid waste landfill units
containing  sewage  sludge  and  failing

-------
                                     Subpart A
to satisfy these Criteria violate sections
309 and 405(e) of the Clean Water Act.

    (j)  The effective date of this part is
October  9,  1993,  unless  otherwise
specified.*

*[NOTE:  EPA finalized several revisions
to 40 CFR Part 258 on October 1, 1993
(58 FR 51536) and issued a  correction
notice on October 14,1993 (58 FR 53136).
These revisions  delay the effective date
for some  categories of landfills.  More
detail on  the  content of the revisions is
included in the introduction.]

1.5.2  Applicability

All MSWLF facilities that receive waste on
or after the effective date must comply with
all of Part 258  except where  otherwise
noted. MSWLF facilities that fail to comply
with  the  Part 258  Criteria  will  be  in
violation of Section 4005 of RCRA and with
Sections 309 and 405(e) of the Clean Water
Act if the facility receives sewage sludge.

1.5.3 Technical Considerations

Failure to comply with the Part 258 Criteria
will   result  in  a  MSWLF  unit being
categorized as an open dump under Section
4005  of RCRA.  The practice of operating
an open dump is prohibited.

If a MSWLF unit co-disposes sewage sludge
with  municipal solid waste and  fails to
comply with Part 258, it also will be in
violation of Section 405(e) of the Clean
Water Act (CWA),  which requires  that
sewage sludge be disposed of in accordance
with  regulations  established   for  such
disposal. If found to be in violation, owners
or operators may be liable for both civil  and
criminal actions enforced under Section 309
of the Clean Water Act.
1.6 DEFINITIONS
    40 CFR §258.2

1.6.1 Statement of Regulation

Unless   otherwise  noted,  all  terms
contained in this part are defined by their
plain meaning.  This  section  contains
definitions   for   terms   that   appear
throughout   this    Part;    additional
definitions appear in the specific sections
to which they apply.

Active life means  the period of operation
beginning with the initial receipt of solid
waste and ending  at completion of closure
activities in accordance with §258.60 of
this Part.

Active  portion means  that  part of a
facility  or unit that  has received or is
receiving wastes  and that has not been
closed in accordance with §258.60 of this
Part.

Aquifer means a geological formation,
group of formations,  or  portion of a
formation capable of yielding significant
quantities of ground water to  wells  or
springs.

Commercial solid waste means  all types
of solid waste generated  by stores, offices,
restaurants, warehouses, and other non-
manufacturing   activities,   excluding
residential and industrial wastes.
                                         10

-------
                                     General
Director of an approved State means the
chief administrative officer of the State
agency responsible for implementing the
State  municipal  solid  waste  permit
program  or  other system   of  prior
approval that is deemed to be adequate
by  EPA under regulations  published
pursuant to section 4005 of RCRA.

Existing  MSWLF  unit   means  any
municipal solid waste landfill unit that is
receiving solid waste as of the effective
date of this  Part. Waste  placement in
existing units must be consistent  with
past operating  practices or  modified
practices to ensure good management.

Facility means  all contiguous land and
structures, other  appurtenances,  and
improvements on the land used for the
disposal of solid waste.

Ground water  means  water  below the
land surface in a zone of saturation.

Household waste means any solid waste
(including  garbage, trash, and sanitary
waste  in  septic  tanks)  derived from
households  (including single and multiple
residences,    hotels    and    motels,
bunkhouses,   ranger   stations,  crew
quarters, campgrounds, picnic grounds,
and day-use recreation  areas).

Industrial solid waste means solid waste
generated by manufacturing or industrial
processes that is not a  hazardous waste
regulated under Subtitle  C  of RCRA.
Such waste may include, but is not limit-
ed to, waste resulting from the following
manufacturing processes: Electric power
generation;     fertilizer/agricultural
chemicals; food and related products/by-
products; inorganic chemicals; iron and
steel manufacturing; leather and leather
products; nonferrous metals manufac-
turing/foundries;   organic  chemicals;
plastics and resins manufacturing; pulp
and paper industry; rubber and miscel-
laneous plastic products;  stone,  glass,
clay,  and concrete  products;  textile
manufacturing;      transportation
equipment; and water treatment.  This
term does not include mining waste or oil
and gas waste.

Lateral expansion means  a horizontal
expansion of the waste boundaries of an
existing MSWLF unit.

Leachate means a liquid that has passed
through or emerged from solid waste and
contains soluble, suspended, or miscible
materials removed from such waste.

Municipal solid waste landfill unit means
a discrete area  of land or an excavation
that receives household waste, and that is
not  a land  application unit,  surface
impoundment,  injection well, or  waste
pile, as those terms are defined under
§257.2. A MSWLF unit also may receive
other types of RCRA Subtitle D wastes,
such   as  commercial  solid   waste,
nonhazardous  sludge,   conditionally
exempt small quantity generator waste,
and industrial solid waste. Such a landfill
may be publicly or privately owned.  A
MSWLF unit may be a new MSWLF
unit, an existing MSWLF unit or a lateral
expansion.

New MSWLF unit means any municipal
solid  waste landfill unit  that  has not
received waste prior to the effective date
of this Part.
                                       11

-------
                                    Subpart A
Open burning means the combustion of
solid waste without:

    (1)    Control of combustion air to
maintain   adequate  temperature   for
efficient combustion,

    (2)    Containment      of     the
combustion reaction in an enclosed device
to provide sufficient residence time and
mixing for complete combustion, and

    (3)    Control of the emission of the
combustion products.

Operator means the person(s) responsible
for the overall operation of a facility or
part of a facility.

Owner means the person(s) who owns a
facility or part of a facility.

Run-off means any rainwater, leachate,
or other liquid that drains over land from
any part of a facility.

Run-on means any rainwater, leachate, or
other liquid that drains over land onto
any part of a facility.

Saturated zone means that part of  the
earth's crust in which all voids are filled
with water.

Sludge means any  solid, semi-solid, or
liquid waste generated from a municipal,
commercial,  or industrial  wastewater
treatment plant, water supply treatment
plant, or  air pollution control facility
exclusive of the treated effluent from a
wastewater treatment plant.
Solid waste means any garbage, or refuse,
sludge  from  a wastewater  treatment
plant, water supply treatment plant, or
air pollution control facility and other
discarded  material,   including  solid,
liquid, semi-solid, or contained gaseous
material  resulting  from   industrial,
commercial,  mining, and  agricultural
operations,   and  from   community
activities, but does not include solid or
dissolved materials in domestic sewage,
or  solid  or   dissolved   materials  in
irrigation return flows or  industrial
discharges that are point sources subject
to  permit  under 33  U.S.C.  1342,  or
source,  special nuclear,  or by-product
material as defined by the Atomic Energy
Act of 1954, as amended (68 Stat. 923).

State means any of the several States, the
District  of Columbia, the Commonwealth
of Puerto Rico, the Virgin Islands, Guam,
American Samoa,  and  the  Common-
wealth of the Northern  Mariana Islands.

State   Director   means   the   chief
administrative officer of the State agency
responsible for implementing the State
municipal solid waste permit program or
other system of prior approval.

Uppermost aquifer means the  geologic
formation nearest the natural ground
surface that is an aquifer, as well as lower
aquifers   that   are    hydraulically
interconnected with this aquifer within
the facility's property boundary.

Waste management unit boundary means
a   vertical   surface   located  at  the
hydraulically downgradient limit of the
unit. This vertical surface extends down
into the uppermost aquifer.
                                       12

-------
                                       General
1.6.2 Applicability

The definitions are applicable to all new,
existing, and lateral expansions of existing
MSWLF units regulated  under  40 CFR
§258.  Additional definitions are provided
within the body of the regulatory language
and will apply to those particular sections.
Definitions  in Subpart  A  apply  to  all
Sections of Part 25 8.

1.6.3 Technical Considerations

Selected definitions will be discussed in the
following brief narratives.

Approved State: Section 4005(c) of RCRA
requires that  each   State   adopt  and
implement a State permit program. EPA is
required to determine whether the State has
developed  an  adequate program.   States
have primary responsibility for implemen-
tation and enforcement of the Criteria. EPA
has the authority to enforce the Criteria  in
States where EPA has deemed the permit
program to be inadequate.   The Agency
intended to extend to Indian Tribes the same
opportunity to apply  for permit  program
approval as is available to States.  A federal
court  ruled,  however,  in   Backcountry
Against Dumps v. EPA,  100 F.3d 147 (D.C.
Cir. 1996),  that EPA cannot do  so.  The
Agency therefore developed  a site-specific
rulemaking  process to provide warranted
flexibility  to  owners  and  operators   of
MSWLFs in Indian Country.  Obtain the
draft  guidance   document   Site-Specific
Flexibility  Requests for  Municipal  Solid
Waste Landfills  in Indian Country (EPA
530-R-97-016) for further information.

Aquifer:  An aquifer is a formation  or
group  of formations capable of yielding a
significant amount of ground water to wells
or springs.  To be an aquifer, a formation
must yield enough water for ground-water
monitoring samples. An unconfmed aquifer
is one where the water table is exposed to
the  atmosphere through openings in the
overlying geologic formations.  A confined
aquifer is isolated from the atmosphere at
the   discharge  point   by  impermeable
geological units.   A confined  aquifer has
relatively impermeable beds  above  and
below.

Existing unit:  Any MSWLF  unit that is
receiving household waste as of October 9,
1993 must continue to operate the facility in
a manner that is consistent with both past
operating practices and modified practices
that  continue  or improve good  waste
management.     Changes  in  operating
practices  intended  to  circumvent  the
purpose,   intent,  or  applicability  of  any
portions of Part 258 will not be considered
in conformance with the Criteria. Facilities
spreading  a thin layer of waste over unused
new  areas will not  be exempt from the
design requirements for new units.  The
portion of a facility that is considered to be
an existing  unit  will  include the waste
management  area that has received waste
prior  to  the  effective  date of Part 258.
Existing   units may  expand  vertically.
However, vertical placement of waste over
a closed unit would cause the unit to be
considered a new unit and would subject the
unit to the design requirements  in Part 258.

Note: Not all units that have a valid State
permit are considered existing units. To be
an existing unit, the  land surface  must be
covered by waste by October 9, 1993.

Lateral   expansion:    Any  horizontal
expansion of the waste boundary of a unit is
a lateral expansion.  This  means that new
                                         13

-------
                                      Subpart A
land surface would be  covered by waste
after October 9, 1993.  Expansions to the
existing unit have to be consistent with past
operating procedures or operating practices
to ensure good management.

Spreading  wastes over a large area  to
increase the size of an existing unit, prior to
the effective date would not be consistent
with good management practices.  If a new
land surface adjacent to an existing unit first
receives waste after October  9, 1993, that
area is classified as a lateral expansion and
therefore, is  subject  to the new  design
standards.  However,  Part 258 regulations
provide the flexibility for approved States to
determine what would constitute a  lateral
expansion.

Municipal  solid  waste  landfill   unit:
Municipal solid waste landfill units are units
that receive household waste, such  as that
from single and multiple residences, hotels
and motels, bunkhouses,  ranger  stations,
crew quarters, campgrounds, picnic grounds
and day-use recreation  areas. Other Subtitle
D wastes, such as commercial solid  waste,
nonhazardous sludge, and  industrial solid
waste, may  be disposed of in a municipal
solid waste landfill.

New municipal  solid waste landfill unit:
A new MSWLF unit is any unit that has not
received  waste prior  to October  9,  1993.
Lateral  expansions are considered  new
MSWLF units for the purpose of location
restrictions  and design standards.   New
MSWLF   units   are   subject  to   all
requirements of Part 258.
1.7 CONSIDERATION OF
    OTHER FEDERAL LAWS
    40 CFR §258.3

1.7.1  Statement of Regulation

    The owner or operator of a municipal
solid waste landfill unit must comply with
any other applicable Federal rules, laws,
regulations, or other requirements.

1.7.2  Applicability

Owners and operators of MSWLF units
must comply with Federal regulations, laws,
rules or requirements that are in effect at the
time of publication of Part 258 or that may
become effective at a later date.

1.7.3 Technical Considerations

Specific sections  of Part 258  reference
major Federal regulations  that also may be
applicable to MSWLF units regulated under
Part 258.   These regulations include  the
Clean  Water  Act  (wetlands,  sludge  dis-
posal,  point  and  non-point source  dis-
charges), the Clean Air Act, other parts of
RCRA  (Subtitle C  if the MSWLF  unit
inadvertently receives regulated hazardous
waste),  and the Endangered  Species Act.
Furthermore, additional  Federal rules, laws,
or regulations may need to be considered.
The owner or operator of the MSWLF unit
is  responsible  for  deter-mining   the
conditions  present at the facility that may
require consideration of other Federal Acts,
rules, requirements, or regulations. Careful
review of the Part 258 Criteria will help to
identify most of the major Federal laws that
may be applicable to a particular MSWLF
unit.
                                          14

-------
    CHAPTER 2

    SUSPART B
LOCATION CRITERIA
        15

-------
                                    CHAPTER 2
                                    SUBPART B

                              TABLE OF CONTENTS
2.1  INTRODUCTION	  18

2.2  AIRPORT SAFETY 40 CFR $258.10  	  19
      2.2.1  Statement of Regulation	  19
      2.2.2  Applicability  	  20
      2.2.3  Technical Considerations	  20

2.3  FLOODPLAINS 40 CFR $258.11 	  24
      2.3.1  Statement of Regulation	  24
      2.3.2  Applicability  	  24
      2.3.3  Technical Considerations	  25
             Floodplain Identification  	  25
             Engineering Considerations	  27

2.4  WETLANDS 40 CFR $258.12	  28
      2.4.1  Statement of Regulation	  28
      2.4.2  Applicability  	  30
      2.4.3  Technical Considerations	  31

2.5  FAULT AREAS 40 CFR $258.13 	  37
      2.5.1  Statement of Regulation	  37
      2.5.2  Applicability  	  37
      2.5.3  Technical Considerations	  38

2.6  SEISMIC IMP ACT ZONES 40 CFR $25 8.14 	  41
      2.6.1  Statement of Regul ati on	  41
      2.6.2  Applicability  	  41
      2.6.3  Technical Considerations	  42
             Background on Seismic Activity 	  42
             Information Sources on Seismic Activity	  42
             Landfill Planning and Engineering in Areas of Seismic Activity  	  42
                                         16

-------
2.7 UNSTABLE AREAS 40 CFR §258.15  	  45
      2.7.1  Statement of Regulation	  45
      2.7.2  Applicability 	  46
      2.7.3  Technical Considerations	  47
             Types of Failures	  49
             Subsurface Exploration Programs  	  54
             Methods of Slope Stability Analysis	  54
             Design for Slope Stabilization  	  56
             Monitoring	  60
             Engineering Considerations for Karst Terrain  	  60

2.8 CLOSURE OF EXISTING MUNICIPAL SOLID WASTE LANDFILL UNITS 40
      CFRS258.16	  61
      2.8.1  Statement of Regulation	  61
      2.8.2  Applicability 	  62
      2.8.3  Technical Considerations	  62

2.9 FURTHER INFORMATION	  63
      2.9.1  References	  63
      2.9.2  Organizations	  65
      2.9.3  Models	  68

      APPENDIX I - FAA Order 5200.5A	  69
                                         17

-------
                                     CHAPTER 2
                                     SUBPART B
                            LOCATION RESTRICTIONS
2.1 INTRODUCTION

Part 258 includes location restrictions to address both the potential effects that a municipal solid
waste landfill (MSWLF) unit may have on the surrounding environment, and the effects that natural
and human-made conditions may have on the performance of the landfill unit.  These criteria pertain
to new and existing MSWLF units and lateral expansions of existing MSWLF units.  The location
criteria of Subpart B cover the following:

    •  Airport safety;

    •  Floodplains;

    •  Wetlands;

    •  Fault areas;

    •  Seismic impact zones; and

    •  Unstable  areas.

Floodplain, fault area, seismic impact zone, and unstable area restrictions address conditions that
may have adverse effects on landfill performance that could lead to releases to the environment or
disruptions of natural functions (e.g., floodplain flow restrictions).  Airport safety, floodplain, and
wetlands criteria are intended to restrict MSWLF units in areas where sensitive natural environments
and/or the public may be adversely affected.

Owners or operators must demonstrate that the location criteria have been met when Part 258 takes
effect. Components of such demonstrations are identified in this section. The owner or operator
of the landfill unit must also comply with all other applicable Federal and State regulations, such
as State wellhead protection programs, that are not specifically identified in the Criteria.  Owners
or operators should note that many States are now developing Comprehensive State Ground  Water
Protection Programs.  These programs are designed to coordinate and implement ground-water
programs in the States;  they may  include additional requirements.  Owners or operators should
check with State environmental agencies concerning Comprehensive State Ground Water Protection
Program requirements. Table 2-1 provides a quick reference to the location  standards required by
the Criteria.
                                           18

-------
                                      Location Criteria
                                      Table 2-1
                              Location Criteria Standards
Restricted
Location
Airport
Floodplains
Wetlands
Fault Areas
Seismic Impact
Zones
Unstable Areas
Applies to
Existing Units
Yes
Yes
No
No
No
Yes
Applies to
New Units
and Lateral
Expansions
Yes
Yes
Yes
Yes
Yes
Yes
Make
Demonstration to
"Director of an
Approved State"
OR
Retain
Demonstration in
Operating Record
Operating Record
Operating Record
Director
Director
Director
Operating Record
Existing
Units Must
Close if
Demonstra-
tion Cannot
be Made
Yes
Yes
N/A
N/A
N/A
Yes
2.2 AIRPORT SAFETY
   40 CFR §258.10

2.2.1  Statement of Regulation

    (a)  Owners  or  operators of  new
MSWLF units, existing MSWLF units, and
lateral expansions that are located within
10,000 feet (3,048 meters) of any airport
runway end used by turbojet aircraft or
within 5,000 feet (1,524 meters) of any
airport runway end used by only piston-
type aircraft must demonstrate that  the
units are designed and operated so that the
MSWLF unit does not pose a bird hazard
to aircraft.
    (b) Owners or operators proposing to
site  new  MSWLF  units  and  lateral
expansions within a five-mile radius of any
airport runway end used by turbojet
or piston-type  aircraft must  notify the
affected airport and the Federal Aviation
Administration (FAA).

    (c) The owner or operator must place
the demonstration in paragraph (a) in the
operating  record  and  notify  the  State
Director that it has been  placed in the
operating record.

    (d) For purposes of this section:
                                            19

-------
                                           Subpart B
    (1) Airport means public-use airport
open to the public without prior permission
and without restrictions within the physical
capacities of available facilities.

    (2) Bird hazard means an increase in
the likelihood of  bird/aircraft  collisions
that may cause damage to the aircraft or
injury to its occupants.

2.2.2  Applicability

Owners and operators of new MSWLF units,
existing MSWLF units, and lateral expansions
of existing units that are  located  near  an
airport, who cannot demonstrate that the
MSWLF unit does  not pose a bird hazard,
must close their units.

This  requirement  applies  to   owners and
operators of  MSWLF units located within
10,000 feet of any airport runway end used by
turbojet aircraft or within 5,000 feet of any
airport runway end  used only by piston-type
aircraft. This applies to airports open to the
public without prior permission for use, and
where  use  of  available facilities  is  not
restricted. If the above conditions are present,
the owner or operator must demonstrate that
the MSWLF unit does not pose a bird hazard
to aircraft and notify the State Director that
the demonstration  has been placed in the
operating record.  If the demonstration is not
made,  existing  units must be  closed  in
accordance with §258.16.

The regulation, based on Federal Aviation
Administration   (FAA)  Order  5200.5 A
(Appendix I), prohibits the disposal of solid
waste within the specified distances unless
the owner  or operator is able to make the
required demonstration showing that the
landfill is designed and operated so as not to
pose bird hazards to aircraft. The regulation
defines a   "danger  zone"  within  which
particular care must be taken to ensure that no
bird hazard arises.

Owners or operators proposing to site new
units or lateral units within five miles of any
airport  runway  end must notify  both the
affected  airport  and   the  FAA.    This
requirement is based on the FAA's position
that MSWLF units located within a five mile
radius of any airport runway end, and which
attract or sustain hazardous bird movements
across aircraft flight paths and runways, will
be considered inconsistent with safe  flight
operations.   Notification by  the  MSWLF
owner/operator to the  appropriate regional
FAA office will allow FAA review of the
proposal.

2.2.3  Technical Considerations

A demonstration that a MSWLF unit does not
pose a bird hazard to aircraft within specified
distances of an  airport runway end should
address at  least three   elements of  the
regulation:

•   Is the airport facility within the  regulated
    distance?;

•   Is  the  runway  part of  a  public-use
    airport?; and

•   Does or will the existence of the landfill
    increase the likelihood of bird/aircraft
    collisions that may cause damage  to the
    aircraft or injury to its occupants?

The first element can be addressed  using
existing maps showing the relationship of
existing runways  at  the  airport to  the
existing or proposed new  unit or lateral
                                              20

-------
                                        Location Criteria
expansion.  Topographic  maps (USGS 15-
minute  series) or State, regional, or  local
government agency maps providing similar or
better accuracy would allow direct scaling, or
measurement, of the closest distance from the
end of a runway to the nearest MSWLF unit.
The measurement can be made by drawing a
circle of appropriate radius (i.e., 5,000 ft.,
10,000 ft, or 5 miles, depending on the airport
type) from the centerline of each runway end.
The  measurement  only  should be  made
between the end of the runway and the nearest
MSWLF unit perimeter,  not between any
other boundaries.

To determine whether the runway is part of a
public use airport and to determine whether
all  applicable  public  airports  have  been
identified, the MSWLF unit owner/operator
should contact the airport administration or
the regional FAA office.  This rule does not
apply to private airfields.

The  MSWLF  unit  design  features and
operational practices can have  a significant
effect  on  the  likelihood  of  increased
bird/aircraft collisions. Birds may be attracted
to MSWLF units to satisfy a need for water,
food,  nesting, or roosting.  Scavenger birds
such as starlings, crows, blackbirds, and gulls
are most commonly associated with  active
landfill units.  Where bird/aircraft collisions
occur, these types of birds are often involved
due to their flocking, feeding, roosting, and
flight  behaviors.     Waste  management
techniques to reduce the supply of food to
these birds include:

    •  Frequent  covering of  wastes that
      provide a source of food;
    •  Shredding, milling,  or  baling  the
       waste-containing food sources; and

    •  Eliminating the acceptance of wastes
       at  the landfill unit that  represent a
       food source for birds (by alternative
       waste management techniques such as
       source separation and composting or
       waste minimization).

Frequent covering of wastes that represent a
food source for the birds effectively reduces
the availability of the food supply. Depending
on site conditions such as  volume and types
of wastes, waste delivery schedules, and size
of the working face, cover may need to  be
applied several  times a  day to keep  the
inactive portion of the working face small
relative to the area accessible to birds.  By
maintaining a small working face, spreading
and compaction equipment are concentrated
in  a  small  area  that  further  disrupts
scavenging by the birds.

Milling or shredding municipal  solid waste
breaks up food waste into smaller particle
sizes and distributes the particles throughout
non-food wastes, thereby diluting food wastes
to a level that frequently makes the mixture
no longer attractive as a food supply for birds.
Similarly,  baling municipal  solid   waste
reduces the surface area of waste that may be
available to scavenging birds.

The use of varying bird control techniques
may prevent the birds from adjusting to a
single  method.   Methods such as  visual
deterrents  or sound have been used with
mixed success in an attempt to discourage
birds  from  food  scavenging.    Visual
deterrents include realistic models (still or
animated)  of the bird's natural predators
                                               21

-------
                                            Subpart B
(e.g., humans, owls, hawks, falcons).  Sounds
that have had limited success  as deterrents
include  cannons,  distress  calls   of  the
scavenger birds,  and sounds of its natural
predators.  Use of physical  barriers such as
fine wires strung across or near the working
face have also been  successfully used (see
Figure 2-1).   Labor  intensive  efforts have
included falconry and firearms.   Many  of
these methods have limited long-term effects
on  controlling bird  populations  at landfill
units/facilities, as the  birds  adapt to  the
environment in which they find food.

Proper design and operation also can reduce
the attraction of birds to the  landfill unit
through eliminating  scavenger bird habitat.
For example, the use  of the landfill unit as a
source  of water can  be  controlled  by
encouraging   surface  drainage   and  by
preventing the ponding of water.

Birds also may be attracted to a landfill unit as
a nesting  area. Use of the  landfill  site as a
roosting or nesting area is usually limited to
ground-roosting birds  (e.g., gulls).  Operational
landfill units that do not operate continuously
often provide a unique roosting habitat due to
elevated ground temperatures (as  a  result of
waste decomposition within  the landfill) and
freedom from disturbance.  Nesting can  be
minimized, however, by examining the nesting
patterns and requirements of undesirable birds
and designing controls  accordingly.   For
example, nesting  by  certain species can  be
controlled   through    the   mowing   and
maintenance schedules at the landfill.

In  addition   to  design   features   and
operational   procedures  to  control  bird
populations,   the  demonstration  should
address the likelihood that the MSWLF unit
may increase bird/aircraft collisions.  One
approach to addressing this part of the airport
safety criterion is to evaluate the attraction of
birds to the MSWLF  unit  and determine
whether this increased population would be
expected to result in a discernible increase in
bird/aircraft collisions.   The evaluation of
bird  attraction   can  be  based  on  field
observations  at  existing  facilities  where
similar geographic location, design features,
and operational procedures are present.

All   observations,  measurements,   data,
calculations and  analyses, and  evaluations
should be documented  and included  in the
demonstration. The demonstration must be
placed in the operating  record and the State
Director must be notified that  it  has been
placed in the  operating record (see Section
3.11 in Chapter 3).

If an  owner  or  operator  of  an  existing
MSWLF unit cannot successfully demonstrate
compliance with  §258.10(a), then  the unit
must be closed in accordance with §258.60
and post-closure activities must be conducted
in accordance with §258.61  (see §258.16).
Closure must occur by October 9, 1996. The
Director of an approved State can extend the
period up to 2  years if it is demonstrated that
no  available  alternative  disposal  capacity
exists and the unit poses no immediate threat
to human health  and the environment (see
Section 2.8).

In accordance with FAA guidance,  if an
owner or operator is proposing to  locate a
new unit or lateral expansion of an existing
MSWLF unit  within 5 miles of the end of a
public-use airport runway, the affected airport
and the regional FAA office must be notified
to provide  an opportunity to  review and
comment on the site.  Identification of public
airports in a given area can be
                                               22

-------
                           Location Criteria
                          Monofilament
Rope or Wire
                               " Guyed to
                            Movable Anchors
                                                     Source: SCS Engineers
                         Figure 2-1.
                    Bird Control Device
                                 23

-------
                                         Subpart B
requested from the FAA.  Topographic maps
(e.g.,  USGS  15-minute  series)  or other
similarly  accurate   maps   showing  the
relationship  of the airport runway and the
MSWLF unit should provide a suitable basis
for determining whether the FAA should be
notified.
2.3 FLOODPLAINS
   40 CFR §258.11

2.3.1  Statement of Regulation

    (a) Owners or  operators  of new
MSWLF units, existing MSWLF units, and
lateral  expansions located  in  100-year
floodplains must demonstrate that the unit
will not restrict the flow of the 100-year
flood, reduce the temporary water storage
capacity of the floodplain,  or  result in
washout of solid waste so as to pose a
hazard  to  human   health  and  the
environment. The owner or operator must
place the demonstration in the operating
record and notify the State Director that it
has been placed in the operating record.

    (b) For purposes of this section:

    (1) Floodplain means the lowland and
relatively flat areas adjoining inland and
coastal waters, including flood-prone areas
of offshore islands, that are inundated by
the 100-year flood.

    (2) 100-year flood means a flood that
has  a 1-percent  or  greater chance  of
recurring in any given year or a flood of a
magnitude equaled or exceeded once in 100
years on the average  over a significantly
long period.
    (3) Washout means the carrying away
of solid waste by waters of the base flood.

2.3.2 Applicability

Owners/operators of new MSWLF units,
existing   MSWLF  units,   and  lateral
expansions of existing units  located in a
100-year  river  floodplain  who cannot
demonstrate that the units will not restrict
the flow of a 100-year flood nor reduce the
water storage capacity, and will not result
in a wash-out of solid waste, must close the
unit(s). A MSWLF unit can affect the flow
and  temporary  storage  capacity  of  a
floodplain. Higher flood levels and greater
flood   damage    both   upstream   and
downstream can be created and could cause
a potential hazard  to  human health and
safety.  The rule does not prohibit locating
a MSWLF unit in a 100-year floodplain; for
example, the owner or  operator is allowed
to demonstrate that the unit  will comply
with  the  flow   restriction,  temporary
storage,  and washout  provisions of the
regulation. If a demonstration  can be made
that the landfill unit will not pose threats,
the  demonstration  must be placed in the
operating record, and  the State Director
must be notified that the demonstration was
made and placed  in the  record.  If the
demonstration  cannot  be made for  an
existing MSWLF unit, then the MSWLF
unit must be closed in 5  years in accordance
with §258.60, and the  owner or operator
must  conduct  post-closure activities  in
accordance with §258.61 (see §258.16).
The closure  deadline may be extended for
up to  two years by the  Director of  an
approved State if the owner or  operator can
demonstrate that no available alternative
disposal   capacity  exists  and  there
                                            24

-------
                                       Location Criteria
is no immediate threat to human health and
the environment (see Section 2.8).

2.3.3 Technical Considerations

Compliance with  the  floodplain criterion
begins with a determination of whether the
MSWLF unit  is  located in the 100-year
floodplain.  If the MSWLF unit is located in
the  100-year floodplain, then the owner or
operator must demonstrate that the unit will
not  pose a  hazard to human health and the
environment due to:

•   Restricting the base flood flow;

•   Reducing the temporary water storage;
    and

•   Resulting in the washout of solid waste.

Guidance  for  identifying floodplains  and
demonstrating facility compliance is provided
below.

Floodplain Identification

River floodplains are readily identifiable as
the  flat areas adjacent to the river's normal
channel.    One hundred-year  floodplains
represent the sedimentary deposits formed by
floods  that have a one percent chance of
occurrence in  any  given year and that are
identified in the flood insurance rate maps
(FIRMs) and flood boundary and floodway
maps published by  the Federal Emergency
Management Agency  (FEMA)  (see Figure
2-2).   Areas classified as  "A"  zones are
subject to the floodplain location restriction.
Areas classified as  "B" or "C" zones are not
subject to the restriction, although care should
be  taken  to design  facilities  capable of
withstanding some potential flooding.
Guidance on using FIRMs is provided in
"How to Read a Flood Insurance Rate Map"
published by FEMA. FEMA also publishes
"The  National Flood  Insurance Program
Community   Status   Book"   that   lists
communities that may not be involved in the
National Flood Insurance Program but which
have FIRMs or Floodway maps  published.
Maps and other FEMA publications may be
obtained from the FEMA Distribution Center
(see Section 2.9.2 for the address). Areas not
covered by  the FIRMs  or Floodway maps
may be included in floodplain maps available
through the U.S. Army Corps of Engineers,
the U.S.  Geological Survey, the U.S. Soil
Conservation Service, the Bureau of Land
Management,   the    Tennessee   Valley
Authority,  and  State,  Tribal,  and local
agencies.

Many of the river channels covered by these
maps may have undergone modification for
hydropower or flood control  projects and,
therefore,   the   floodplain   boundaries
represented  may   not  be   accurate   or
representative.   It may be  necessary  to
compare the floodplain map series to recent
air photographs to identify  current river
channel   modifications  and   land   use
watersheds  that  could  affect  floodplain
designations.  If floodplain maps are  not
available, and the facility is located within a
floodplain, then a field study to delineate the
100-year floodplain may be  required.   A
floodplain delineation program can be based
primarily on  meteorological  records  and
physiographic  information such as existing
and    planned   watershed   land   use,
topography, soils  and  geologic mapping,
and    air    photo    interpretation    of
geomorphologic (land form) features.  The
United   States  Water   Resource  Council
(1977) provides information for determining
                                              25

-------
            Figure 2-2
Example Section of Flood Plain Map
                  26

-------
                                       Location Criteria
the potential for floods in a given location by
stream gauge records. Estimation of the peak
discharge also  allows an  estimation of the
probability of exceeding the 100-year flood.

Engineering Considerations

If the MSWLF unit is within the  100-year
floodplain, it must be located so that the
MSWLF unit does not significantly restrict
the base flood  flow  or significantly  reduce
temporary storage capacity of the floodplain.
The MSWLF unit must be designed to prevent
the washout of  solid  waste  during the
expected flood  event. The rule requires that
floodplain  storage  capacity,   and  flow
restrictions that occur  as  the  result of the
MSWLF unit, do not pose a hazard to human
health and the environment.

The demonstration that these considerations
are met relies  on  estimates  of the flow
velocity and volume of floodplain storage in
the vicinity of the MSWLF unit during the
base flood. The assessment should consider
the floodplain storage capacity and floodwater
velocities that would likely exist in absence of
the MSWLF unit.  The volume occupied by a
MSWLF   unit   in   a   floodplain  may
theoretically  alter   (reduce)   the   storage
capacity and restrict flow. Raising the base
flood level by more than one foot can be an
indication that the MSWLF unit may reduce
and restrict storage capacity flow.

The location of the MSWLF unit relative to
the velocity distribution of floodwaters will
greatly   influence  the  susceptibility  to
washout.   This  type  of assessment  will
require a conservative estimate of the shear
stress on the landfill components caused by
the  depth,  velocity,  and   duration  of
impinging river waters.  Depending on the
amount of inundation, the landfill unit may
act as a channel side slope or bank or it may
be isolated as an island within the overbank
river channel.  In both cases an estimate of
the river velocity would be part of a proper
assessment.

The  assessment  of  flood water  velocity
requires that the channel  cross  section be
known above, at, and below the landfill unit.
Friction factors on the overbank are deter-
mined from the surface conditions and vege-
tation present. River hydrologic models may
be used to simulate flow levels and estimate
velocities through these river cross sections.

The Army Corps of Engineers (COE, 1982)
has developed several numerical models to
aid in the prediction of flood hydrographs,
flow parameters, the effect of obstructions on
flow levels, the simulation of flood control
structures, and sediment transport.   These
methods may or may not be appropriate for a
site; however, the following models provide
well-tested analytical approaches:

HEC-1      Flood  Hydrograph  Package
    (watershed model  that  simulates the
    surface run-off response of a river basin
    to precipitation);

HEC-2  Water Surface Profiles (computes
    water   surface    profiles    due   to
    obstructions;    evaluates    floodway
    encroachment potential);

HEC-5   Simulation of Flood Control  and
    Conservation Systems (simulates the
    sequential  operation  of a  reservoir
    channel  system  with  a   branched
    network configuration; used to design
                                              27

-------
                                          Subpart B
    routing that will minimize downstream
    flooding); and

HEC-6   Scour  and Deposition in Rivers
    and Reservoirs (calculates water surface
    and sediment bed surface profiles).

The  HEC-2 model is  not appropriate for
simulation of sediment-laden braided stream
systems  or  other  intermittent/dry  stream
systems that are subject to flash flood events.
Standard run-off and peak flood hydrograph
methods would be more appropriate for such
conditions to predict the effects of severe
flooding.

There  are  many  possible  cost-effective
methods  to protect  the MSWLF unit from
flood damage including embankment designs
with rip-rap, geotextiles, or other materials.
Guidelines for designing with these materials
may be found in Maynard (1978) and SCS
(1983). Embankment design will require an
estimate of river flow velocities, flow profiles
(depth),  and wave  activity.   Figure  2-3
provides  a  design  example  for  dike
construction and  protection  of  the  landfill
surface from flood water. It addresses height
requirements to control the effects  of wave
activity.  The use of alternate erosion control
methods  such as gabions (cubic-shaped wire
structures filled with stone), paving bricks,
and mats may be considered.  It should be
noted, however, that the dike design in Figure
2-3 may further decrease the water storage
and flow capacities.
2.4 WETLANDS
   40 CFR §258.12

2.4.1  Statement of Regulation

    (a) New MSWLF units  and  lateral
expansions shall not be located  in wetlands,
unless the owner or operator can make the
following demonstrations to the Director of
an approved State:

    (1) Where applicable under section 404
of the Clean Water Act or applicable State
wetlands  laws, the presumption  that  a
practicable  alternative to the  proposed
landfill is available which does not involve
wetlands is clearly rebutted;

    (2) The construction and operation of
the MSWLF unit will not:

    (i) Cause or contribute to violations of
any  applicable  State  water  quality
standard,

    (ii)  Violate  any applicable  toxic
effluent  standard  or  prohibition  under
Section 307  of the  Clean Water Act,

    (iii) Jeopardize the continued existence
of endangered or threatened species or
result in  the  destruction   or adverse
modification of a critical habitat, protected
under the Endangered  Species Act of 1973,
and

    (iv) Violate any requirement under the
Marine Protection, Research,  and
Sanctuaries Act of 1972 for the protection
of a marine  sanctuary;
                                             28

-------
 ASSUMPTIONS:
 * FETCH = 2500 FT'
 * WIND SPEED = 50 MPH
 * AVE. WATER DEPTH ALONG FETCH = 5 FT
 * OVERBANK WATER VELOCITY = 0,25 FT/S
 DEFINITIONS
 Zs = Wave Setup (tilting of water surface upward at downwind end)
 Zw = Capillary Waves Height {developed by wind over water surface)
 Zr = Wave Run-up (water run-up along dike from wave impact)
                           WIND
                             i
 t
RIVER
LANDFILL
 EQUATIONS
                                          WIND
                                         Free Board
                              2500 F x>t Fetch
                                                              Dike
                                                            Landfill
                          Flood Plain
                                            Rood Plain

                                             Section A
                                       	Total Wave Height (Zt = Zs + Zw + Zr)
                                        \
                                                         .100 yr Flood Water
                                                          \  A
                           SECTION A
                                  SOLUTIONS
 where:
 Zr = Wave run-up along dike
 Zr/Zw = Relative run-up rafo from
 chart below
 A = Wavelength
 tw = Wave period
 Vw = wind speed (mph)
 F = fetch (mites)
      Zw= 0.034 V
where:
Zw = ave. height of heighest 1/3rd
of waves (ft)
F = fetch (miles)
              140CW
 where:
 Zs = rise above stiff water [eve! (ft)
 Vw = wind speed (mph)
 F = fetch (miles)
 d = water depth along fetch (ft)
                                 w=-
                                                KjH"
    1000(0.0167
                                                        -since)'
where:
W = Rip - Rap stone weight (tos)
d - Rip - Rap stone diameter
K = Coefficient (30)
Y = Stone Density (Ib/cf)
H = height of design wave (ft)
o = bank slope (degrees)
From the data provided in the assumptions
at the beginning of the example:
Zs = 0.18 n., Zw = 1.55 ft., Zr = 2.40 ft '
Zt Design Height = 4.13 ft
Base 100 yr flood level = 5 ft
for Factor of Safety of 1.5
Dike Height = (1.5) (4.13 + 5) =  13.7 ft
   For the Rip - Rap design given:
   K = 30, y= 120, H = 1.55 ft., a = 185
   For the protective stone on Dike
   d = 0.5ft, W = 12lbs7stone
                                                               \~.^_1'*~ , "°: .TiTT -i------• -H
            Wave run-up ratios vs. wave steepness and embankment slopes
  Re'e^ence 'or Equations: U.S. Department of Interior, Bureau of Land Reclamation (1974)
  Reference tor Wave Run-up Chart: L»nsiey and Franani (1972)
                                   Figure 2-3. Example Floodplain Protection Dike Design
                                                  29

-------
                                         Subpart B
    (3) The MSWLF unit will not cause or
contribute to significant degradation of
wetlands.  The owner or  operator must
demonstrate the integrity of the MSWLF
unit and  its ability to protect ecological
resources by  addressing  the  following
factors:

    (i)  Erosion, stability,  and migration
potential of native wetland soils, muds and
deposits used to support the MSWLF unit;

    (ii) Erosion, stability, and migration
potential of dredged and fill materials used
to support the MSWLF unit;

    (iii) The volume and chemical nature
of the waste managed in the MSWLF unit;

    (iv)   Impacts  on fish, wildlife,  and
other aquatic resources and their habitat
from release of the solid waste;

    (v)      The   potential   effects  of
catastrophic release of waste to  the wetland
and   the   resulting  impacts   on  the
environment; and

    (vi)    Any  additional  factors,  as
necessary, to demonstrate  that ecological
resources in the  wetland are sufficiently
protected.

    (4)   To the extent  required  under
Section 404  of the  Clean  Water Act or
applicable State wetland laws, steps have
been  taken  to  attempt to achieve no net
loss of wetlands (as defined  by acreage
and function) by first avoiding impacts to
wetlands   to  the  maximum   extent
practicable   as  required by  paragraph
(a)(l) of  this  section,  then  minimizing
unavoidable impacts  to the  maximum
extent practicable, and  finally offsetting
remaining unavoidable  wetland  impacts
through  all appropriate and practicable
compensatory  mitigation  actions  (e.g.,
restoration of existing  degraded wetlands
or creation of man-made wetlands); and

    (5) Sufficient information is available
to make  a reasonable determination with
respect to these demonstrations.

    (b)    For purposes  of  this  section,
"wetlands" means those areas that are
defined in 40 CFR §232.2(r).

2.4.2  Applicability

New MSWLF units and lateral  expansions in
wetlands  are prohibited, except in approved
States.    The wetland  restrictions  allow
existing MSWLF units located in wetlands to
continue  operations as  long as compliance
with the other requirements of Part 258 can
be maintained.

In addition to the regulations listed in 40 CFR
§258.12(a)(2), other Federal  requirements
may be applicable in siting a MSWLF unit in
a wetland. These include:

•   Sections 401, 402, and 404 of the CWA;
•   Rivers and Harbors Act of 1989;
•   National Environmental Policy Act;
•   Migratory Bird Conservation Act;
•   Fish  and Wildlife Coordination Act;
•   Coastal Zone Management Act;
•   Wild and Scenic Rivers Act; and the
•   National Historic Preservation Act.

As  authorized  by  the EPA,  the  use  of
wetlands  for location of a MSWLF facility
may require a permit from the U.S. Army
                                             30

-------
                                        Location Criteria
Corps of Engineers (COE).   The types of
wetlands present (e.g., headwater, isolated, or
adjacent), the extent of the wetland impact,
and  the  type of impact  proposed  will
determine the applicable category of COE
permit (individual or general) and the permit
application procedures.  The  COE District
Engineer should be contacted prior to permit
application   to  determine   the  available
categories of permits  for a particular site.
Wetland permitting or permit review  and
comment can include additional agencies at
the federal,  state, regional, and local level.
The requirements for wetland permits should
be reviewed by the owner/operator to ensure
compliance with all applicable regulations.

When  proposing to locate a new facility or
lateral expansion in a wetland,  owners or
operators  must be able to demonstrate that
alternative sites are not available and that the
impact to wetlands is unavoidable.

If it  is demonstrated  that  impacts  to  the
wetland are unavoidable, then all practicable
efforts must be made to minimize and, when
necessary, compensate for the impacts. The
impacts must be compensated for by restoring
degraded wetlands, enhancing or preserving
existing wetlands, or creating new wetlands.
It is  an  EPA objective  that  mitigation
activities result in the achievement of no net
loss of wetlands.

2.4.3  Technical Considerations

The term wetlands, referenced in §258.12(b),
is defined in §232.2(r).  The EPA currently is
studying the issues involved in defining  and
delineating wetlands.  Proposed changes to
the "Federal  Manual  for  Identifying  and
Delineating  Jurisdictional Wetlands," 1989,
are still being reviewed.  [These changes were
proposed in the Federal Register on August
14, 1991 (56 FR 40446) and on December 19,
1991  (56 FR 65964).]   Therefore,  as  of
January 1993, the method used for delineating
a wetland is based on  a previously existing
document,   "Army  Corps  of Engineers
Wetlands  Delineation  Manual," 1987.   A
Memorandum of Understanding  between
EPA and the Department of the Army, Corps
of Engineers, was amended on January 4,
1993, to state that both agencies would now
use the COE 1987 manual as guidance for
delineating  wetlands.    The  methodology
applied by an owner/operator to define and
delineate wetlands should be in keeping with
the federal guidance in place at the time of the
delineation.

Because of the unique nature of wetlands, the
owner/operator is required to demonstrate that
the landfill unit will not cause or contribute to
significant degradation of wetlands.   The
demonstration  must   be  reviewed  and
approved by the Director of an approved State
and placed in the facility operating record.
This provision effectively bans the siting of
new MSWLF units or  lateral expansions in
wetlands in unapproved States.

There are several key issues that need to be
addressed if an owner or operator proposes to
locate a lateral expansion or a new MSWLF
unit in a wetland. These issues include:  (1)
review  of  practicable  alternatives,   (2)
evaluation of wetland acreage and function, (3)
evaluation of impacts of MSWLF units  on
wetlands, and (4) offsetting impacts.  Although
EPA has an objective of no net loss of wetlands
in terms of acreage and function, it recognizes
that  regions of  the  country   exist  where
proportionally large areas  are dominated  by
wetlands.     In   these  regions,   sufficient
                                               31

-------
                                            Subpart B
 acreage and a suitable type of upland may not
be present to allow construction of a new
MSWLF unit or lateral expansion  without
wetland impacts. Wetlands evaluations may
become an integral part of the siting, design,
permitting,  and  environmental  monitoring
aspects of a landfill unit/facility (see Figure 2-
4).

Practicable Alternatives

EPA believes that locating new MSWLF units
or lateral expansions in wetlands should be
done only where there are no less damaging
alternatives available.   Due to the extent of
wetlands  that  may  be present in certain
regions, the banning of new MSWLF units or
lateral  expansions in wetlands  could  cause
serious capacity problems.  The flexibility of
the rule  allows owners  or  operators  to
demonstrate  that there are no  practicable
alternatives to locating or laterally expanding
MSWLF units in wetlands.

As  part  of  the evaluation of  practicable
alternatives,   the  owner/operator  should
consider the compliance of the location with
other regulations and the potential impacts of
the MSWLF unit on wetlands and related
resources.  Locating or laterally expanding
MSWLF   units  in   wetlands  requires
compliance  with   other   environmental
regulations.  The owner or operator must
show that the operation or construction  of the
landfill unit will not:

    •  Violate any  applicable  State  water
       quality standards;

    •  Cause or contribute to the violation of
       any applicable toxic effluent standard
       or prohibition;
    •  Cause  or contribute to violation of
       any requirement for the protection of
       a marine sanctuary; and

    •  Jeopardize the continued existence of
       endangered  or threatened species or
       critical habitats.

The MSWLF unit cannot cause or contribute
to  significant  degradation   of wetlands.
Therefore, the owner/operator must:

    •  Ensure the integrity of the MSWLF
       unit, including consideration  of the
       erosion,  stability,  and migration of
       native wetland soils and  dredged/fill
       materials;

    •  Minimize impacts on  fish, wildlife,
       and other aquatic resources and their
       habitat  from  the release of solid
       waste;

    •  Evaluate the effects of catastrophic
       release of wastes on the wetlands; and

    •  Assure that ecological resources in the
       wetlands  are  sufficiently protected,
       including consideration of the volume
       and   chemical  nature   of   waste
       managed in the MSWLF  unit.

These factors were partially  derived from
Section 404(b)(l) of the  Clean  Water  Act.
These guidelines address the protection of the
ecological resources of the wetland.

After consideration of  these  factors, if no
practicable alternative to locating the landfill
in wetlands is available, compensatory steps
must  be  taken  to  achieve no  net loss of
wetlands as defined by acreage and
                                               32

-------
Wetland Study
 Not Required
                                                                   Has a wet-
                                                                 land Delineation
                                                                   Study Been
                                                                   Performed?
   Is landfill
Site Adjacent to
of Impinging on
  a Wetland''
                                  Contact COE
                                  Regarding a
                                    Wetland
                                Delineation Study
                                                                   A Wetland
                                                                Delineation Study
                                                                   Should toe
                                                                   Performed
                                      Are
                                   Practicable
                                   Alternate
                                Disposal Optens
                                 or Landfill Sites
                                   Available'
                                   Alternate
                                 Disposal Study
                                   Required
Cannot Build in
   WeflarxJ
                                  A/e Alternate
                                Disposal Options
                                 or Landfill Sites
                                   Available7
                                Identify Affected Acreage
                                  and Functions ater
                                 Minimizing Impact and
                                 Arrange COE Site Visit
                                                               Contact State and COE to
                                                               Determine Wetland Offset
                                                                 Ratios and Functional
                                                                Rank of Offset Options
                                                                    File for Landfill
                                                                  Permit /404 Permit
                                                               1. Impact Minimization Plan
                                                               2, Rebuttal of Alternatives
                                                               3. Wettartd Offset Plan
                                                               4. Offset Monitoring Plan
                                    Figure 2-4
           Wetlands Decision Tree for Owners/Operators
                             in Approved States
                                         33

-------
                                            Subpart B
function.   The owner/operator must try  to
avoid  and/or  minimize  impacts  to the
wetlands  to  the greatest extent possible.
Where avoidance and minimization still result
in wetland impacts,  mitigation  to  offset
impacts is required. Mitigation plans must be
approved  by  the   appropriate  regulatory
agencies and must  achieve an agreed-upon
measure of success.  Examples of mitigation
include restoration of degraded wetlands  or
creation  of wetland acreage  from existing
uplands.

Part 258 presumes that practicable alternatives
are available  to locating landfill units  in
wetlands because landfilling is not a water-
dependent activity. In an approved State, the
owner or operator can rebut the presumption
that a practicable alternative to the proposed
landfill unit or lateral expansion is available.
The   term  "practicable"  pertains  to the
economic and social feasibility of alternatives
(e.g.,  collection of waste at transfer  stations
and trucking to an existing landfill facility  or
other possible landfill sites).  The feasibility
evaluation may entail  financial,  economic,
administrative,  and   public   acceptability
analyses    as    well    as   engineering
considerations.  Furthermore, the evaluations
generally  will  require  generation  and
assessment of land use, geologic, hydrologic,
geographic,  demographic,  zoning,  traffic
maps, and other related information.

To rebut the presumption that an  alternative
practicable site exists generally will require
that a site search for an alternative location
be  conducted.   There  are no standard
methods for conducting site searches due to
the variability of the number and hierarchy
of screening criteria that may be applied  in
a specific case.  Typical criteria may include:

    •  Distance  from   waste   generation
       sources;
    •  Minimum   landfill    facility   size
       requirements;
    •  Soil conditions;
    •  Proximity to ground-water users;
    •  Proximity of significant aquifers;
    •  Exclusions from  protected  natural
       areas;
    •  Degree  of difficulty  to  remediate
       features; and
    •  Setbacks   from   roadways   and
       residences.

Wetland Evaluations

The  term  "wetlands"   includes  swamps,
marshes,  bogs,  and any  areas that  are
inundated or saturated  by ground water or
surface water at a frequency and duration to
support, and that under normal  circumstances
do  support,  a prevalence  of  vegetation
adapted for life in saturated soil conditions.
As defined under current guidelines, wetlands
are identified based on the presence of hydric
soils, hydrophyte vegetation, and the wetland
hydrology. These characteristics also affect
the  functional value of a wetland in terms of
its  role in:   supporting fish  and wildlife
habitats;   providing  aesthetic, scenic,  and
recreational   value;  accommodating flood
storage; sustaining aquatic diversity; and its
relationships  to surrounding  natural areas
through nutrient retention and productivity
exportation   (e.g.,  releasing   nutrients  to
downstream  areas, providing transportable
food sources).

Often, a wetland assessment will need to be
conducted by a qualified and experienced
                                               34

-------
                                        Location Criteria
multi-disciplinary  team.   The  assessment
should identify:  (1) the limits of the wetland
boundary based on hydrology, soil types and
plant  types;  (2)   the  type  and  relative
abundance of vegetation, including trees; and
(3) rare,  endangered, or otherwise protected
species and their habitats (if any).

The   current  methods  used  to  delineate
wetlands are presented in "COE Wetlands
Delineation Manual," 1987.  In January 1993,
EPA and COE agreed to use the 1987 Manual
for purposes of delineation.  The Federal
Manual  for Identifying   and Delineating
Jurisdictional Wetlands (COE, 1989) contains
an  extensive  reference  list  of available
wetland  literature.   For  example,  lists of
references  for the identification of plant
species characteristic of wetlands throughout
the United States, hydric soils classifications,
and  related  wetland  topics  are  presented.
USGS topographic maps, National Wetland
Inventory (NWI)  maps, Soil Conservation
Service (SCS) soil maps, wetland inventory
maps, and aerial photographs prepared locally
also may provide useful information.

After  completion  of a wetland  study, the
impact of the MSWLF unit on wetlands and
its relationship to  adjacent wetlands can be
assessed  more  effectively.    During  the
permitting process, local, State, and federal
agencies with jurisdiction over wetlands will
need to be contacted to schedule a site visit.
It is usually advantageous to encourage this
collaboration as early as possible in the site
evaluation process, especially if the State
program  office  that  is  responsible  for
wetland  protection is  different from the
solid    waste     management     office.
Regulations will  vary significantly from
State to State with regard to the size and type
of  wetland  that  triggers  State  agency
involvement.   In  general, the COE will
require  notification and/or consultation  on
any   proposed  impact  on  any   wetland
regardless of the actual degree of the impact.
Other agencies such as the Fish and Wildlife
Service  and  the SCS  may  need to  be
contacted in some States.

Evaluation of ecological resource protection
may include assessment of the value of the
affected  wetland.   Various techniques are
available for this type of evaluation, and the
most appropriate technique for a specific site
should  be  selected  in  conjunction  with
applicable  regulatory  agencies.  Available
methods include analysis of functional value,
the Wetland Evaluation Technique (WET),
and the Habitat Evaluation Procedure (HEP).

The 1987 Manual does not address functional
value in the detail provided by the  1989
manual.  The methodology for conducting a
functional   value   assessment   should  be
reviewed  by  the  applicable regulatory
agencies.   It  is  important to  note that
functional  value  criteria  may become  a
standard part of wetland delineation following
revision  of the federal guidance manual(s).
The owner or operator should remain current
with the  accepted practices  at the time of the
delineation/assessment.

The  functional value  of a given wetland is
dependent  on its soil, plant, and hydrologic
characteristics,   particularly  the  diversity,
prevalence, and extent  of  wetland   plant
species.    The  relationship  between the
wetland and surrounding areas (nutrient  sinks
and sources) and the ability  of the wetland to
support animal habitats, or rare or endangered
species,  contributes to the  evaluation  of
functional value.
                                               35

-------
                                          Subpart B
Other  wetland   and  related  assessment
methodologies include WET and HEP. WET
allows comparison of the values and functions
of wetlands before and after construction of a
facility,  thereby  projecting the  impact a
facility may have on a wetland.  WET was
developed   by   the  Federal   Highway
Administration  and  revised by the  COE
(Adamus et a/., 1987).  HEP was developed
by the Fish and Wildlife Service to determine
the quality and quantity of available habitat
for selected species.  HEP and WET may be
used in conjunction with each other to provide
an integrated assessment.

Impact Evaluation

If the new unit or lateral  expansion is to be
located in a wetland, the  owner or operator
must demonstrate that the unit will not cause
or contribute to significant degradation of the
wetland.  Erosion potential and stability of
wetland soils and any dredged or fill material
used to support the MSWLF unit should be
identified as part of the wetlands evaluation.
Any adverse stability or erosion problems that
could affect  the  MSWLF or  contaminant
effects that could be caused by the MSWLF
unit should be resolved.

All  practicable  steps  are to  be  taken to
minimize potential impacts of the MSWLF
unit to wetlands.  A number  of  measures
that can aid in minimization of impacts are
available. Appropriate measures  are site-
specific and should be incorporated into the
design and operation of the MSWLF unit.
For  example, placement  of ground water
barriers may be required if soil and shallow
ground-water  conditions  would  cause
dewatering  of  the wetland  due  to the
existence of underdrain pipe systems at the
facility.   In many instances,  however,
wetlands are formed in response to perched
water tables over geologic  material of low
hydraulic   conductivity   and,   therefore,
significant drawdown impacts may not occur.

It is possible that the landfill  unit/facility will
not  directly  displace  wetlands,  but  that
adverse effects may be caused by leachate or
run-off Engineered containment systems for
both leachate and run-off should  mitigate the
potential for discharge to wetlands.

Additional  actions   and   considerations
relevant  to  mitigating  impacts   of fill
material  in  wetlands    that   may  be
appropriate for  MSWLF  facilities  are
provided in Subpart H (Actions to Minimize
Adverse  Effects)  of  40  CFR   §230
(Guidelines for  Specification of Disposal
Sites for Dredged or Fill Materials).

Wetland Offset

All unavoidable impacts must be "offset" or
compensated for to ensure that the facility has
not caused, to the extent practicable, any net
loss of wetland acreage.  This compensatory
mitigation may take the form of upgrading
existing marginal or lower-quality wetlands
or creating new  wetlands.  Wetland offset
studies require review and development on a
site-specific basis.

To identify potential sites  that  may be
proposed  for upgrade of existing wetlands
or  creation of new wetlands,  a cursory
assessment of surrounding wetlands  and
uplands   should   be   conducted.     The
assessment may include a study to  define
the  functional characteristics  and inter-
relationships  of these  potential  wetland
mitigation areas.  An upgrade of an existing
wetland   may  consist  of  transplanting
                                              36

-------
                                       Location Criteria
appropriate vegetation  and importing low-
permeability  soil materials that would  be
conducive   to   forming   saturated   soil
conditions. Excavation to form open water
bodies or gradual  restoration of salt water
marshes by culvert expansions to promote sea
water  influx  are  other  examples  of
compensatory mitigation.

Individual States may have offset ratios to
determine how  much  acreage  of  a given
functional value is required to  replace the
wetlands  that   were  lost  or  impacted.
Preservation  of lands,  such   as  through
perpetual  conservation  easements,  may  be
considered as a viable  offset option.  State
offset ratios may require that for wetlands of
an  equivalent  functional  value,  a  larger
acreage be created than was displaced.

Due to the experimental nature of creating or
enhancing wetlands, a monitoring program to
evaluate the progress of the effort should be
considered and may be required as a wetland
permit condition.    The  purpose  of the
monitoring program is to verify that the
created/upgraded  wetland  is  successfully
established and that the intended function of
the wetland  becomes  self-sustaining over
time.
2.5 FAULT AREAS
   40 CFR §258.13

2.5.1  Statement of Regulation

    (a) New MSWLF units  and  lateral
expansions shall not be located within 200
feet (60  meters) of a fault that has  had
displacement in Holocene time unless the
owner or  operator demonstrates  to the
Director of an approved State that an
alternative setback  distance of less than
200 feet (60 meters) will prevent damage to
the structural integrity of the MSWLF unit
and will be protective of human health and
the environment.

    (b) For the purposes of this section:

    (1) Fault means  a fracture or a zone of
fractures  in  any material along  which
strata on one side have been displaced with
respect to that on the other side.

    (2) Displacement means the relative
movement of any two  sides  of  a fault
measured in any direction.

    (3) Holocene means the most recent
epoch of the Quaternary period, extending
from the end of the Pleistocene Epoch to
the present.

2.5.2 Applicability

Except in approved States, the regulation bans
all new MSWLF units or lateral expansions of
existing units within 200 feet (60 meters) of
the outermost boundary of a fault that has
experienced   displacement   during   the
Holocene Epoch (within the last 10,000 to
12,000 years).  Existing MSWLF units are
neither required to close nor to retrofit if they
are located in fault areas.

A variance to  the  200-foot  setback is
provided  if the owner  or operator  can
demonstrate to the Director of an approved
State that a shorter  distance will prevent
damage to the structural integrity  of the
MSWLF unit and will  be protective of
human health  and the environment.  The
demonstration for a  new MSWLF unit or
lateral   expansion  requires  review   and
                                             37

-------
                                           Subpart B
approval by the Director of an approved State.
If the demonstration is approved, it must be
placed in the facility's operating record. The
option to have a setback of less than 200 feet
from  a Holocene fault is  not  available in
unapproved States.

2.5.3  Technical Considerations

Locating a landfill in the vicinity of an area
that has experienced faulting in recent time
has inherent dangers.  Faulting occurs in areas
where the geologic stresses exceed a geologic
material's ability to withstand those stresses.
Such   areas  also  tend  to  be  subject  to
earthquakes  and   ground  failures  (e.g.,
landslides, soil  liquefaction) associated with
seismic activity. A more detailed discussion
of seismic activity is presented in Section 2.6.

Proximity  to a  fault  can cause  damage
through:

•   Movement along the  fault which  can
    cause displacement of facility structures,

    Seismic activity associated with faulting
    which can  cause  damage to facility
    structures through vibratory action (see
    Figure 2-5), and

    Earth shaking which can cause ground
    failures such as slope failures.

Consequently, appropriate setbacks from fault
areas are required to minimize  the potential
for  damage.

To  determine if a proposed landfill unit is
located in  a  Holocene  fault  area,  U.S.
Geological Survey (USGS)  mapping can be
used.   A  series of  maps  known  as  the
"Preliminary    Young    Fault    Maps,
Miscellaneous Field Investigation (MF) 916"
was published  by  the USGS  in  1978.
Information about these maps can be obtained
from the USGS  by calling 1-800-USA-
MAPS, which reaches the USGS National
Center in Reston, Virginia, or by calling 303-
236-7477,  which reaches the USGS Map
Sales Center in Denver, Colorado.

For  locations where a fault zone has been
subject to movement since the USGS maps
were  published  in  1978,  a   geologic
reconnaissance  of the site and surrounding
areas may be required to map fault traces and
to   determine   the   faults   along  which
movement  has occurred  in Holocene time.
This reconnaissance also may be necessary to
support a demonstration for a setback of less
than 200 feet. Additional requirements may
need to be met before a  new unit or lateral
expansion may be approved.

A site fault characterization is necessary to
determine whether a site is within 200 feet of
a fault  that has had movement  during  the
Holocene epoch.  An investigation would
include  obtaining   information   on  any
lineaments (linear features) that suggest the
presence of faults within  a 3,000-foot radius
of the site.  The information could be based
on:
    A  review  of available  maps,  logs,
    reports, scientific literature, or insurance
    claim reports;

    An aerial  reconnaissance of  the  area
    within a  five-mile radius of the  site,
    including aerial photo analysis; or
                                               38

-------
                           Location Criteria
                           Figure 2-5

                    Potential Seismic Effects
        Deformed Leachate
        Collection Pipe
\
                                                  \Leachate
                                                    Collection Pipe
                                                Clay Liner
A schematic diagram of a landfill showing potential deformation of
the leachate collection and removal system by seismic stresses.


Source: US EPA, 1992
                                 39

-------
                                           Subpart B
    A field reconnaissance that includes
    walking portions of the area within 3,000
    feet of the unit.

If the site fault characterization indicates that
a fault or a set of faults is situated within
3,000 feet of the proposed unit, investigations
should  be  conducted  to  determine  the
presence or absence of any faults within 200
feet  of  the  site  that  have  experienced
movement during the Holocene period.  Such
investigations can include:

    Subsurface exploration, including drilling
    and trenching, to locate fault zones and
    evidence of faulting.

    Trenching perpendicular to any faults or
    lineaments within 200 feet of the unit.

    Determination  of  the  age of any
    displacements, for example by  examining
    displacement of surficial deposits such as
    glacial  or  older  deposits  (if Holocene
    deposits are absent).

•   Examination   of  seismic   epicenter
    information to look for indications  of
    recent  movement  or  activity   along
    structures in a given area.

    Review of high altitude, high resolution
    aerial  photographs with  stereo-vision
    coverage. The photographs are produced
    by  the National Aerial  Photographic
    Program (NAPP) and the National High
    Altitude Program (NHAP).  Information
    on these photos can be obtained from the
    USGS EROS Data Center in Sioux Falls,
    South Dakota at (605) 594-615
Based  on  this  information  as  well  as
supporting maps and analyses,  a  qualified
professional  should  prepare a  report that
delineates  the  location  of the Holocene
fault(s) and the associated 200-foot setback.

If  requesting   an  alternate    setback,   a
demonstration must be made to show that no
damage to the  landfill's  structural integrity
will result.    Examples  of  engineering
considerations and modifications that may be
included  in  such  demonstrations are  as
follows:

•   For zones with high probabilities of high
    accelerations  (horizontal)   within  the
    moderate range of 0. Ig to 0.75g, seismic
    designs should be developed.

    Seismic  stability  analysis  of landfill
    slopes should be performed  to  guide
    selection of materials and gradients for
    slopes.

    Where  in-situ  and laboratory   tests
    indicate  that a potential landfill site is
    susceptible  to   liquefaction,  ground
    improvement  measures like  grouting,
    dewatering,   heavy   tamping,   and
    excavation should be implemented.

•   Engineering options  include:

    —     Flexible pipes,

    —     Ground improvement measures
           (grouting,  dewatering,  heavy
           tamping, and  excavation), and/or

    —     Redundant      precautionary
           measures (secondary containment
           system).
                                               40

-------
                                       Location Criteria
In addition, use of such measures needs to be
demonstrated to be protective of human health
and  the  environment.     The  types  of
engineering controls  described  above are
similar to those that would be employed in
areas  that  are  likely   to   experience
earthquakes.
2.6 SEISMIC IMPACT ZONES
   40 CFR §258.14

2.6.1  Statement of Regulation

    (a) New MSWLF units and  lateral
expansions shall not be located in seismic
impact zones, unless the owner or operator
demonstrates   to   the Director  of  an
approved  State  that all  containment
structures,  including  liners,  leachate
collection  systems, and  surface  water
control systems, are designed to resist the
maximum  horizontal  acceleration  in
lithified earth  material for the site. The
owner  or  operator   must  place  the
demonstration in the operating record and
notify the State Director  that it has been
placed in the operating record.

    (b) For the purposes of this section:

    (1) Seismic impact  zone means an area
with a ten percent or  greater probability
that the maximum horizontal acceleration
in lithified earth material, expressed as a
percentage of the earth's gravitational pull
(g), will exceed O.lOg in 250 years.
in
    (2) Maximum horizontal acceleration
    lithified  earth  material means  the
maximum expected horizontal acceleration
depicted on a seismic hazard map, with a
90 percent or greater probability that the
acceleration will not be exceeded in  250
years, or the maximum expected horizontal
acceleration based on a site-specific seismic
risk assessment.

    (3) Lithified earth material means all
rock, including all naturally occurring  and
naturally formed aggregates or masses of
minerals or small particles of older rock
that formed by crystallization of magma or
by  induration of loose  sediments.  This
term does not include man-made materials,
such  as fill,  concrete,  and  asphalt, or
unconsolidated  earth materials,  soil, or
regolith lying at or near the earth  surface.

2.6.2  Applicability

New MSWLF units and lateral expansions in
seismic impact zones are prohibited, except in
approved States. A seismic impact zone is an
area that has  a  ten  percent  or  greater
probability  that  the  maximum  expected
horizontal  acceleration in  lithified earth
material, expressed as a  percentage  of the
earth's gravitational pull (g),  will exceed
O.lOg in 250 years.

The regulation prohibits locating new units or
lateral expansions in a seismic impact zone
unless the owner or operator can demonstrate
that the  structural components  of  the  unit
(e.g., liners, leachate collection systems, final
cover, and surface water control systems) are
designed to  resist the  maximum horizontal
acceleration in lithified earth material at the
site.  Existing units are not required to be
retrofitted. Owners or operators of new units
or lateral expansions must notify the  Director
of  an  approved  State  and  place  the
demonstration  of  compliance  with  the
conditions of the restriction in the operating
record.
                                              41

-------
                                          Subpart B
2.6.3  Technical Considerations

Background on Seismic Activity

To understand seismic activity, it is helpful to
know its origin. A brief introduction to the
geologic underpinnings of seismic activity is
presented below.

The earth's crust is not a static system. It
consists of an assemblage of earthen masses
that are in slow motion.  As new crust is
generated from within the earth, old edges of
crust  collide  with  one another,  thereby
causing stress.  The weaker edge is forced to
move beneath the stronger edge back into the
earth.

The dynamic conditions of the earth's crust
can be manifested as shaking ground (seismic
activity), fracturing (faulting), and volcanic
eruptions. Seismic activity also can result in
types of ground failure.  Landslides and mass
movements (e.g., slope failures) are common
on  slopes;  soil  compaction  or  ground
subsidence tends to occur in unconsolidated
valley  sediments; and  liquefaction of soils
tends to happen in areas where sandy or silty
soils that are saturated and loosely compacted
become in effect, liquefied (like quicksand)
due to  the  motion.    The latter types of
phenomena  are addressed  in Section  2.7,
Unstable Areas.

Information Sources on Seismic Activity

To  determine  the  maximum horizontal
acceleration of the lithified earth material
for the site (see Figure 2-6), owners or
operators  of MSWLF  units should  review
the seismic 250-year interval maps in U.S.
Geological  Survey  Miscellaneous  Field
Study Map MF-2120, entitled "Probabilistic
Earthquake Acceleration and Velocity Maps
for the  United States  and Puerto  Rico"
(Algermissen et al., 1991).   To  view the
original of the map that is shown in Figure 2-
6 (reduced in size), contact the USGS office
in your area. The original map (Horizontal
Acceleration - Base modified from U.S.G.S.
National  Atlas,  1970, Miscellaneous Field
Studies, Map MF 2120) shows county lines
within each State. For areas not covered by
the aforementioned map, USGS State seismic
maps may be used to estimate the maximum
horizontal   acceleration.     The  National
Earthquake Information Center, located at the
Colorado  School  of  Mines  in  Golden,
Colorado, can provide seismic maps of all 50
states.  The Center also maintains a database
of known earthquakes and fault zones.

Information on the location of earthquake
epicenters and intensities may be available
through  State  Geologic  Surveys  or the
Earthquake  Information   Center.     For
information    concerning      potential
earthquakes in specific areas, the Geologic
Risk Assessment Branch of USGS may be
of assistance.   Other  organizations  that
study  the  effects  of earthquakes  on
engineered structures include the National
Information   Service  for   Earthquake
Engineering, the Building Seismic Safety
Council, the National Institute of Science
and Technology, and the American Institute
of Architects.

Landfill  Planning  and  Engineering in
Areas of Seismic Activity

Studies indicate that during earthquakes,
superficial (shallow) slides and differential
displacement tend to be produced, rather
than massive slope failures  (U.S.  Navy
1983).   Stresses  created by  superficial
failures can affect the liner and final cover
                                              42

-------
     Principal Islands at
        Hawaii
      9:111 n.wxe
Explanation

       - Jlrti/unial inx
al a pcitunl nf gravity.
                                                                                                          Altort Equal AIM Projsdion
                                                                                                              H-.HI I '.W«M«">
                                          Figure 2-6. Seismic Impact Zones
(Areas with a 10% or greater probability that the maximum horizontal acceleration will exceed .10g in 250 years)

-------
                                            Subpart B
systems  as well  as  the  leachate  and  gas
collection and removal systems.  Tensional
stresses within the liner system can result in
fracturing of the soil  liner and/or tearing of
the flexible membrane liner.  Thus,  when
selecting suitable  sites from many potential
sites   during   the   siting   process,   the
owner/operator should try to avoid a site with:

    Holocene fault zones,
    Sites with potential ground motion, and
    Sites with liquefaction potential.

If one of the above types of sites is selected,
the owner/operator must consider the costs
associated with the development of the site.

If, due to a lack of suitable alternatives, a site
is chosen that is located in a seismic impact
zone, a demonstration must be made to the
Director of an approved State that the design
of  the unit's  structural components  (e.g.,
liners, leachate collection, final covers, run-on
and run-off systems) will resist the maximum
horizontal acceleration in lithified materials at
the site.   As part  of the  demonstration,
owner/operators must:

    Determine  the  expected peak  ground
    acceleration from a maximum strength
    earthquake that could occur in the area,

•   Determine  the   site-specific   seismic
    hazards such as soil settlement, and

    Design the  facility  to withstand  the
    expected peak ground acceleration.

The design of the slopes, leachate collection
system,  and  other  structural components
should have  built-in conservative  design
factors.         Additionally,    redundant
precautionary measures should be designed
and built into the various landfill systems.

For those units located in an area with an
estimated maximum horizontal acceleration
greater than O.lg, an evaluation  of seismic
effects should consider both foundation soil
stability  and waste  stability under  seismic
loading.  Conditions that may be  considered
for the evaluation include the construction
phase (maximum open excavation depth of
new cell adjacent to an existing unit), closure
activities  (prior to final consolidation of both
waste  and subsoil),  and  post-closure  care
(after final consolidation of both waste and
foundation soil). If the maximum horizontal
acceleration is less than or equal to O.lg, then
the design  of the unit will not  have to
incorporate an evaluation of seismic effects
unless  the facility will be situated in an area
with low strength foundation soils  or soils
with potential for liquefaction. The facility
should be assessed for the effects of seismic
activity even if the horizontal acceleration is
expected to be less than 0. Ig.

In determining the potential effects of seismic
activity  on  a  structure,  an  engineering
evaluation should examine soil behavior with
respect to  earthquake  intensity.    When
evaluating soil characteristics, it is necessary
to know  the  soil strength as well as  the
magnitude or intensity of the earthquake in
terms  of peak acceleration.   Other soil
characteristics,   including    degree   of
compaction, sorting (organization of the soil
particles), and degree of saturation, may need
to be considered because of their potential
influence on site conditions.  For example,
deposits  of loose  granular  soils  may be
compacted by the ground vibrations induced
by an earthquake.   Such volume reductions
could result in large uniform or differential
                                               44

-------
                                        Location Criteria
settlements of the ground surface (Winterkorn
and Fang, 1975).

Well-compacted cohesionless embankments
or reasonably  flat slopes in insensitive clay
are less likely to fail under moderate seismic
shocks (up to 0.15g and 0.20g acceleration).
Embankments made of insensitive cohesive
soils founded on cohesive soils  or rock may
withstand even greater seismic  shocks. For
earthen embankments in  seismic regions,
designs with  internal  drainage  and  core
material most resistant to fracturing should be
considered.   Slope materials vulnerable to
earthquake shocks are described below (U.S.
Navy, 1983):

•   Very steep slopes of weak, fractured and
    brittle rocks or  unsaturated loess are
    vulnerable to transient shocks caused by
    tensional faulting;

•   Loess   and saturated  sand  may be
    liquefied by seismic shocks causing the
    sudden  collapse of structures and flow
    slides;

    Similar effects  are possible in sensitive
    cohesive  soils  when natural  moisture
    exceeds the soil's liquid limit; and

•   Dry cohesionless material on a slope at
    an  angle of  repose will  respond  to
    seismic shock by shallow sloughing and
    slight flattening of the slope.

In general,  loess,  deltaic  soils, floodplain
soils, and loose fills are highly susceptible to
liquefaction   under   saturated  conditions
(USEPA, 1992).

Geotechnical    stability    investigations
frequently incorporate the  use  of computer
models to reduce the computational time of
well-established analytical methods.  Several
computer software packages are available that
approximate the anticipated dynamic forces
of the design earthquake by resolving  the
forces into a  static analysis  of loading on
design  cross  sections.   A  conservative
approach would incorporate both vertical and
horizontal   forces   caused   by   bedrock
acceleration if it can be shown that the types
of material of interest are susceptible to the
vertical force component.   Typically,  the
horizontal   force  caused   by   bedrock
acceleration  is  the  major  force  to  be
considered in the seismic stability analysis.
Examples of computer models include PC-
Slope by Geoslope Programming (1986), and
FLUSH by the University of California.

Design  modifications to accommodate an
earthquake may  include shallower waste
sideslopes, more conservative design of dikes
and   run-off  controls,  and    additional
contingencies for leachate collection should
primary systems be disrupted. Strengths of
the landfill components  should be  able to
withstand these additional forces with an
acceptable factor  of safety.   The  use of
professionals experienced in seismic analysis
is  strongly recommended for  design of
facilities located in areas of high seismic risk.
2.7 UNSTABLE AREAS
   40 CFR §258.15

2.7.1  Statement of Regulation

    (a)  Owners  or  operators  of new
MSWLF units, existing MSWLF units,
and lateral expansions  located  in  an
unstable area  must demonstrate that
engineering   measures    have    been
incorporated into  the MSWLF  unit's
                                              45

-------
                                         Subpart B
design to ensure that the integrity of the
structural components of the MSWLF unit
will  not  be disrupted.  The  owner  or
operator must place the demonstration in
the operating record and notify the  State
Director that it has  been placed in the
operating record.  The owner or operator
must consider the following  factors, at a
minimum, when determining whether an
area is unstable:

    (1) On-site or local soil conditions that
may  result  in  significant  differential
settling;

    (2)  On-site  or  local   geologic  or
geomorphologic features; and

    (3)  On-site  or  local human-made
features  or  events  (both  surface  and
subsurface).

    (b) For purposes of this section:

    (1) Unstable area means a location that
is susceptible to natural or human-induced
events or forces capable of impairing the
integrity of  some or  all of the  landfill
structural  components  responsible for
preventing   releases   from  a  landfill.
Unstable areas can include poor foundation
conditions,  areas  susceptible  to  mass
movements, and Karst terrains.

    (2)   Structural  components means
liners, leachate  collection systems,  final
covers,  run-on/run-off systems, and any
other component used in the  construction
and  operation of  the  MSWLF  that  is
necessary for protection of human health
and the environment.

    (3) Poor foundation conditions means
those areas  where features  exist which
indicate that a  natural or  man-induced
event may result in inadequate foundation
support for the structural components of a
MSWLF unit.
    (4)
Areas   susceptible   to   mass
movement means those areas of influence
(i.e., areas  characterized  as  having an
active  or  substantial possibility of mass
movement) where the movement of earth
material at, beneath, or adjacent to the
MSWLF unit, because of natural or man-
induced events, results in the downslope
transport of soil  and rock material by
means of gravitational influence. Areas of
mass  movement  include,  but are  not
limited to, landslides,  avalanches, debris
slides and flows, solifluction, block sliding,
and rock fall.

    (5) Karst terrains means areas where
karst topography, with its characteristic
surface and  subterranean  features, is
developed as the result of dissolution of
limestone, dolomite, or other soluble rock.
Characteristic   physiographic  features
present in karst terrains include, but are
not limited to, sinkholes, sinking streams,
caves, large springs, and blind valleys.

2.7.2 Applicability

Owners/operators of new MSWLF  units,
existing   MSWLF  units,   and   lateral
expansions of  units that  are located in
unstable   areas must  demonstrate  the
structural  integrity  of the unit.  Existing
units for which a successful demonstration
cannot be  made must be  closed.   The
regulation applies  to new units, existing
units, and lateral expansions that are located
on  sites  classified as  unstable   areas.
Unstable  areas  are  areas  susceptible to
                                            46

-------
                                        Location Criteria
natural  or human-induced  events or forces
that are capable of impairing or destroying the
integrity of some or  all of the structural
components.  Structural components consist
of liners, leachate collection systems,  final
cover systems, run-on  and run-off control
systems, and any other component necessary
for protection  of human  health   and the
environment.

MSWLF units can be located in  unstable
areas,  but the  owner  or operator   must
demonstrate that the structural integrity of the
MSWLF unit will not be disrupted.  The
demonstration must  show  that engineering
measures have been  incorporated  into the
design of the unit to ensure the integrity of the
structural  components.   Existing  MSWLF
units that do not meet the demonstration  must
be closed within 5 years in accordance with
§258.60, and owners and operators  must
undertake     post-closure   activities    in
accordance with §258.61. The Director  of an
approved State can grant a 2-year extension to
the closure requirement under two conditions:
(1) no disposal alternative is available, and (2)
no immediate threat is posed to human health
and the  environment.

2.7.3  Technical Considerations

Again,  for the purposes of this discussion,
natural unstable areas include those areas that
have  poor   soils   for  foundations,   are
susceptible to mass movement, or have  karst
features.

    Areas with  soils  that  make   poor
    foundations  have   soils  that   are
    expansive or settle suddenly.   Such
    areas may lose their ability to support a
    foundation when subjected to natural
(e.g., heavy rain) or man-made events
(e.g., explosions).

—     Expansive soils usually are clay-
       rich  soils  that,  because of their
       molecular structure, tend to swell
       and  shrink  by taking  up  and
       releasing  water and  thus  are
       sensitive to a variable hydrologic
       regime.   Such soils   include:
       smectite (montmorillonite group)
       and vermiculite clays; bentonite
       is  a  smectite-rich  clay.    In
       addition,  soils  rich in  "white
       alkali"    (sodium     sulfate),
       anhydrite  (calcium sulfate),  or
       pyrite  (iron  sulfide) also may
       exhibit swelling as water content
       increases.  Such soils tend to be
       found in the arid western states.

—     Soils  that are  subject  to rapid
       settlement (subsidence) include
       loess, unconsolidated clays, and
       wetland soils.  Loess,  which is
       found in the central states, is a
       wind-deposited  silt   that   is
       moisture-deficient  and  tends to
       compact      upon     wetting.
       Unconsolidated clays, which can
       be found in the  southwestern
       states, can undergo considerable
       compaction when fluids such as
       water  or   oil   are  removed.
       Similarly, wetland soils, which
       by their nature are water-bearing,
       also   tend  to  be   subject   to
       subsidence   when   water   is
       withdrawn.

Another type of unstable  area is  an
area  that   is  subject  to  mass
movement.  Such areas can be situated
                                               47

-------
                                           Subpart B
on steep or gradual slopes.  They tend to have
rock or soil conditions that are conducive to
downslope movement of soil, rock, and/or
debris (either alone or mixed with water)
under the influence of gravity. Examples of
mass    movements   include    avalanches,
landslides, debris slides and flows, and rock
slides.

    Karst terrains tend to be subject to
    extreme   incidents   of   differential
    settlement,  namely  complete ground
    collapse. Karst is a term used to describe
    areas  that  are  underlain  by soluble
    bedrock,  such  as  limestone, where
    solution of the  rock by water creates
    subterranean drainage systems that may
    include areas of rock collapse. These
    areas tend to be characterized  by large
    subterranean and  surficial  voids (e.g.,
    caverns and sinkholes) and unpredictable
    surface and ground-water  flow (e.g.,
    sinking streams and large springs).  Other
    rocks such as dolomite or gypsum also
    may be subject to solution effects.

Examples of human-induced unstable areas
are described below:

    The presence of cut and/or fill slopes
    during construction of the MSWLF unit
    may cause slippage of existing soil or
    rock.

    Excessive  drawdown of ground water
    increases the effective overburden on  the
    foundation soils underneath the MSWLF
    unit,   which  may  cause  excessive
    settlement or bearing capacity failure on
    the foundation soils.
    A closed landfill as the foundation for a
    new landfill ("piggy-backing") may be
    unstable unless the closed landfill has
    undergone complete  settlement of the
    underlying wastes.

As  part of their  demonstration to site  a
landfill in an unstable area, owners/operators
must assess the ability of the soils and/or rock
to serve as a foundation as well as the ability
of  the  site  embankments  and  slopes  to
maintain a stable condition.   Once these
factors  have  been evaluated,  a  MSWLF
design should be developed that will address
these types of concerns and prevent possible
associated  damage to  MSWLF structural
components.

In designing a new unit or lateral expansion
or re-evaluating an existing MSWLF unit, a
stability assessment should be conducted in
order to avoid or prevent a destabilizing event
from impairing the structural integrity of the
landfill component  systems.   A stability
assessment   involves   essentially   three
components:   an  evaluation of subsurface
conditions,  an analysis of slope stability, and
an examination of related  design needs.  An
evaluation of subsurface conditions requires:

    Assessing  the stability  of foundation
    soils, adjacent embankments, and slopes;

    Investigating  the   geotechnical   and
    geological characteristics of the site to
    establish   soil  strengths   and  other
    engineering properties  by  performing
    standard penetration  tests, field  vane
    shear tests, and laboratory tests; and
                                               48

-------
                                        Location Criteria
    Testing the soil properties such as water
    content,  shear  strength,  plasticity, and
    grain size distribution.

A  stability  assessment  should  consider
(USEPA,  1988):

    The  adequacy  of   the  subsurface
    exploration program;

    The  liquefaction  potential   of  the
    embankment,  slopes,  and  foundation
    soils;

    The   expected   behavior   of   the
    embankment, slopes, and foundation soils
    when  they  are  subjected  to seismic
    activity;
    The  potential
    failure; and
for  seepage-induced
    The potential for differential settlement.

In addition, a  qualified professional must
assess, at a minimum, natural conditions (e.g.,
soil, geology, geomorphology)  as  well  as
human-made  features   or   events  (both
subsurface  and  surface) that could  cause
differential settlement  of ground.   Natural
conditions  can be highly unpredictable and
destructive, especially if amplified by human-
induced changes to the environment.  Specific
examples   of  natural   or   human-induced
phenomena include:  debris flows resulting
from heavy rainfall in a small watershed; the
rapid formation  of a sinkhole as a result of
excessive  local  or regional  ground  water
withdrawal  in   a  limestone  region;  earth
displacement  by   faulting   activity;  and
rockfalls  along   a cliff  face   caused  by
vibrations resulting from the detonation of
explosives or sonic booms.
Information  on  natural  features  can be
obtained from:

    •  The  USGS  National  Atlas   map
       entitled   "Engineering  Aspects of
       Karst," published in 1984;

    •  Regional or local soil maps;

    •  Aerial  photographs  (especially in
       karst areas); and

    •  Site-specific investigations.

To examine an area for possible sources of
human-induced ground instability, the site
and surrounding area should be  examined
for   activities   related   to    extensive
withdrawal  of  oil,  gas,  or water  from
subsurface units as well as construction or
other operations that may result  in ground
motion (e.g., blasting).

Types of Failures

Failures occur  when  the  driving forces
imposed  on   the   soils  or  engineered
structures exceed the resisting forces of the
material. The ratio of the resisting force to
the driving force is considered the factor of
safety (FS).  At an FS value less than 1.0,
failure will occur by definition.  There is a
high  probability that,  due  to  natural
variability and  the degree  of  accuracy in
measurements, interpreted  soil conditions
will  not be precisely representative of the
actual soil conditions.   Therefore, failure
may  not occur exactly at the calculated
value, so factors of safety greater than 1.0
are required for the design.  For  plastic soils
such  as  clay,  movement or deformation
(creep) may occur  at  a higher  factor of
safety  prior   to   catastrophic   failure.
                                              49

-------
                                           Subpart B
Principal  modes  of failure in  soil or rock
include:

    Rotation (change of orientation) of an
    earthen mass on a curved slip  surface
    approximated by a circular arc;

•   Translation (change of position) of an
    earthen mass on a planar surface whose
    length is large compared to depth below
    ground;

•   Displacement of a  wedge-shaped  mass
    along one or  more planes of weakness;

•   Earth and mud flows in loose clayey and
    silty soils; and

    Debris flows in coarse-grained soils.

For the purposes of this discussion,  three
types  of failures can occur at a landfill unit:
settlement,  loss  of bearing strength,  and
sinkhole collapse.

•   If not properly engineered, a landfill in
    an unstable area may undergo extreme
    settlement, which can result in structural
    failure.   Differential  settlement  is  a
    particular mode of failure that generally
    occurs beneath a landfill in response to
    consolidation and  dewatering  of the
    foundation soils during and following
    waste loading.

    Settlement beneath a  landfill unit, both
    total and differential, should be assessed
    and compared to the elongation strength
    and flexure properties of the liner and
    leachate collection  pipe system.   Even
    small   amounts of   settlement   can
    seriously damage  leachate  collection
    piping  and sumps.  The analysis will
    provide  an   estimate  of  maximum
settlement, which can  be used  to  aid in
estimating differential settlement.

    Allowable   settlement   is   typically
    expressed  as   a  function   of  total
    settlement because differential  settlement
    is more difficult to predict.  However,
    differential settlement is a more  serious
    threat to  the integrity of the structure
    than  total  settlement.    Differential
    settlement also is discussed in Section
    6.3 of Chapter 6.

    Loss of bearing strength is a  failure
    mode that tends  to occur in  areas  that
    have soils that tend to expand,  rapidly
    settle, or liquefy, thereby causing failure
    or reducing performance of overlying
    MSWLF components.  Another example
    of  loss of  bearing strength involves
    failures that have occurred at operating
    sites  where  excavations  for landfill
    expansions adjacent to the filled areas
    reduced the mass  of the soil at the toe of
    the slope, thereby reducing the  overall
    strength   (resisting  force)   of   the
    foundation soil.

•   Catastrophic collapse in the form of
    sinkholes  is a type of failure that occurs
    in karst regions.  As water,  especially
    acidic   water,   percolates   through
    limestone   (calcium   carbonate),   the
    soluble carbonate  material  dissolves,
    forming cavities and  caverns.   Land
    overlying caverns can collapse suddenly,
    resulting in sinkhole features that can be
    100 feet or more in depth and 300 feet or
    more in width.

Tables  2-2  and 2-3  provide examples of
analytical considerations for mode of failure
assessments in  both natural and human-made
slopes.
                                               50

-------
                                            Location Criteria
         1. Slope in Coarse-Grained Soil with
                  Some Cohesion
   Low Groundwater
     Failure of thin
     wedge, position
     influenced by
     tension cracks
High Groundwater
Failure at relatively
shallow toe circles
With low groundwater, failure occurs on
shallow, straight, or slightly curved surface.
Presence of a tension crack at the top of the
slope influences failure location.  With high
groundwater, failure occurs on the relatively
shallow toe circle whose position is determined
primarily by ground elevation.

Analyze with effective stress using strengths C'
and 0' from CD tests. Pore pressure is
governed by seepage condition. Internal pore
pressures and external water pressures must be
included.
             2. Slope in Coarse-Grained,
                   Soil Cohesion
    Low Groundwater
    Stable slope angle
    = effective friction
    angle
High Groundwater
Stable slope angle
= !/2 effective
friction angle
Stability depends primarily on groundwater
conditions. With low groundwater, failures
occur as surface sloughing until slope angle
flattens to friction angle. With high
groundwater, stable slope is approximately 1/2
friction angle.

Analyze with effective stress using strengths C'
and 0' from CD tests. Slight cohesion
appearing in test envelope is ignored. Special
consideration must be given to possible flow
slides in loose, saturated fine sands.
         3. Slope in Normally Consolidated or
            Slightly Preconsolidated Clay

      Location of failure depends on variation of
              shear strength with depth.
   Strength constant
   «,ith depth
                              Strength constant
                              with depth
                          Failure occurs on circular arcs whose position
                          is governed by theory. Position of
                          groundwater table does not influence stability
                          unless its fluctuation changes strength of the
                          clay or acts in tension cracks.

                          Analyze with total stresses, zoning cross
                          section for different values of shear strengths.
                          Determine shear strength from unconfmed
                          compression test, unconsolidated undrained
                          triaxial test or vane shear.
               Suff or Hard Stratum
Source: Soil Mechanics, NAVFAC Design Manual 7.01

                       Table 2-2. Analysis of Stability of Natural Slopes
                                                    51

-------
                                                Subpart B
          4. Slope in Stratified Soil Profile

        Location of failure depends on relative
          strength and orientation of layers.
   Strata oflow
   strength
Location of failure plane is controlled by
relative strength and orientation of strata.
Failure surface is combination of active and
passive wedges with central sliding block
chosen to conform to stratification.

Analyze with effective stress using strengths C'
and 0' for fine-grained strata and 0' for
cohesionless material.
            5. Depth Creep Movements in
                  Old Slide Mass

      Bowl-shaped area of low slope (9 to 11%)
            bounded at top by old scarp.
Strength of old slide mass decreases with
magnitude of movement that has occurred
previously.  Most dangerous situation is in
stiff, over-consolidated clay which is softened,
fractured, or slickensided in the failure zone.
    Failure surface of
    low curvature which
    is a portion of an
    shear surface
Source: Soil Mechanics, NAVFAC Design Manual 7.01

                Table 2-2. Analysis of Stability of Natural Slopes (Continued)
                                                    52

-------
                                             Location Criteria
          1. Failure of Fill on Soft Cohesive
            Foundation with Sand Drains
     Location of failure depends on geometry and
              strength of cross section.
Usually, minimum stability occurs during
placing of fill.  If rate of construction is
controlled, allow for gain in strength with
consolidation from drainage.

Analyze with effective stress using strengths C'
and 0' from CU tests with pore pressure
measurement. Apply estimated pore pressures
or piezometric pressures. Analyze with total
stress for rapid construction without
observation of pore pressures, use shear
strength from unconfmed compression or
unconsolidated undrained triaxial.
         2. Failure of Stiff Compacted Fill on
              Soft Cohesive Foundation
   Failure surface may be rotation on circular arc or
      translation with active and passive wedges.
Usually, minimum stability obtained at end of
construction. Failure may be in the form of rotation
or
translation, and both should be considered.

For rapid construction ignore consolidation
from drainage and utilize  shear strengths
determined from U or UU tests or vane shear
in total stress analysis. If failure strain of fill
and foundation materials differ greatly, safety
factor should exceed one, ignoring shear
strength of fill. Analyze long-term stability
using C and 0 from CU tests with effective
stress analysis, applying pore pressures of
           3. Failure Following Cut in Stiff
                   Fissured Clay
    Original
    ground line
Release of horizontal stresses by excavation
causes expansion of clay and opening of
fissures, resulting in loss of cohesive strength.

Analyze for short-term stability using C' and 0'
with total stress analysis.  Analyze for long-
term stability with C'r and 0'm based on
residual strength measured in consolidated
drained tests.
                     Cut at toe
         Failure surface depends on pattern of
           fissures or depth of softening.
Source: Soil Mechanics, NAVFAC Design Manual 7.01
                       Table 2-3. Analysis of Stability of Cut and Fill Slopes,
                                  Conditions Varying With  Time
                                                    53

-------
                                            Subpart B
Subsurface Exploration Programs

Foundation soil stability assessments for non-
catastrophic failure require field investigations
to determine  soil strengths  and other soil
properties.  In  situ field  vane  shear tests
commonly  are  conducted in  addition  to
collection of piston samples for laboratory
testing of undrained shear  strengths (biaxial
and  triaxial).   Field vanes taken  at  depth
provide  a profile  of soil strength.   The
required field vane depth intervals vary, based
on soil strength and type, and the number of
borings required depends on the variability of
the  soils,  the  site  size,   and  landfill  unit
dimensions.  Borings and  field vane testing
should  consider  the anticipated design  to
identify segments of the facility where critical
cross sections are likely to occur.   Critical
sections  are where factors  of  safety  are
anticipated to be lowest.

Other tests that are conducted to characterize
a soil include determination of water content,
Atterberg  limits,  grain  size  distribution,
consolidation,   effective   porosity,   and
saturated  hydraulic conductivity.   The site
hydrogeologic conditions should be assessed
to  determine  if  soils  are   saturated   or
unsaturated.

Catastrophic  failures,  such   as  sinkhole
collapse in karst terrains or fault displacement
during an earthquake, are  more  difficult to
predict.  Subsurface karst structures may have
surface  topographic  expressions  such  as
circular depressions over subsiding solution
caverns.  Subsurface borings or geophysical
techniques may provide reliable means  of
identifying the occurrence,  depth, and size of
solution  cavities that have the potential for
catastrophic collapse.
Methods of Slope Stability Analysis

Slope  stability analyses are performed  for
both excavated side slopes and aboveground
embankments. The analyses are performed as
appropriate to verify the structural integrity of
a cut slope or dike. The design configuration
is evaluated for its stability under all potential
hydraulic and loading conditions, including
conditions that may exist during construction
of an expansion (e.g.,  excavation). Analyses
typically  performed  are  slope stability,
settlement, and liquefaction.  Factor of safety
rationale and selection  for different conditions
are described by Huang  (1983) and Terzaghi
and   Peck   (1967).      Table   2-4  lists
recommended  minimum factor of  safety
values for slopes. Many States may provide
their   own  minimum   factor   of  safety
requirements.

There   are  numerous  methods  currently
available  for  performing  slope  stability
analyses.  Method selection should be based
on the soil properties  and the  anticipated
mode  of failure.  Rationale for  selecting a
specific method should be provided.

The  majority  of these methods  may  be
categorized as "limit  equilibrium" methods
in which driving and resisting  forces  are
determined  and  compared.    The  basic
assumption  of  the  limit   equilibrium
approach is that the  failure criterion is
satisfied along an assumed failure surface.
This surface may be a straight line, circular
arc,  logarithmic spiral, or other irregular
plane. A free body diagram of the driving
forces acting on the slope is constructed
using  assumed  or known values  of  the
forces. Next, the soil's shear resistance as it
pertains  to  establishing  equilibrium   is
calculated. This calculated  shear resistance
                                               54

-------
                               Location Criteria
                               Table 2-4

       Recommended Minimum Values of Factor of Safety
                     for Slope Stability Analyses
                                      Uncertainty of Strength Measurements

Consequences of Slope Failure	Small,	Large,	

No imminent danger to human life or           1.25                1.5
major environmental impact if slope           (1.2)*              (1.3)
fails

Imminent danger to human life or              1.5           2.0 or greater
major environmental impact if slope            (1.3)           (1.7 or greater)
fails	


1   The uncertainty of the strength measurements is smallest when the soil
   conditions are uniform and high quality strength test data provide a consistent,
   complete, and logical picture of the strength characteristics.

2   The uncertainty of the strength measurements is greatest when the soil
   conditions are complex and when available strength data do not provide a
   consistent, complete, and logical  picture of the strength characteristics.

*  Numbers without parentheses apply for static conditions and those within
   parentheses apply to seismic conditions.
Source:   EPA Guide to Technical Resources for the Design of Land Disposal
          Facilities.
                                      55

-------
                                           Subpart B
then is compared to the estimated or available
shear strength of the soil to give an indication
of the factor of safety (Winterkorn and Fang,
1975).

Methods that  consider only the whole free
body  as  a  single unit include the Culmann
method  and  the  friction  circle  method.
Another approach is to divide the free body
into vertical  slices and to  consider  the
equilibrium of each slice.  Several versions of
the  slice method are available; the best known
are  the Swedish Circle method and the Bishop
method.   Discussions of these  and other
methods may be found in Winterkorn and
Fang  (1975), Lambe and Whitman (1969),
and U.S. Navy (1986).

A computer program that is  widely used for
slope stability analysis is PC STABL, a two-
dimensional   model  that  computes  the
minimum critical factors  of safety  between
layer interfaces. This model uses the method
of vertical  slices to analyze the slope and
calculate the factor of safety.  PC STABL can
account  for heterogeneous  soil  systems,
anisotropic  soil  strength  properties, excess
pore water pressure due to shear, static ground
water   and  surface   water,   pseudostatic
earthquake   loading,  surcharge  boundary
loading, and tieback loading.  The program is
written in FORTRAN IV and can be run on a
PC. Figure 2-7 presents a typical output from
the  model.

Design for Slope Stabilization

Methods for slope stabilization are presented
in Table 2-5 and are summarized below.

•    The first illustration shows that stability
    can  be increased by  changing the slope
    geometry through reduction of the slope
    height, flattening the slope angle, or
excavating a bench in the upper part of
the slope.

The   second  illustration  shows  how
compacted  earth or rock  fill  can  be
placed in the form  of a berm at and
beyond the slope's toe to  buttress the
slope. To prevent the development of
undesirable water pressure behind the
berm, a drainage system may be placed
behind the berm at the base of the slope.

The  third  illustration  presents several
types  of  retaining structures.   These
structures  generally  involve  drilling
and/or    excavation    followed    by
constructing cast-in-place concrete piles
and/or slabs.

—     The T-shaped  cantilever  wall
       design  enables  some  of  the
       retained soil to  contribute to the
       stability of the  structure and is
       advisable for use on slopes that
       have vertical cuts.

—     Closely-spaced   vertical  piles
       placed along the top of the slope
       area   provide    reinforcement
       against slope failure through a
       soil arching effect that is created
       between the piles.  This type of
       retaining system is advisable for
       use on steeply cut slopes.

—     Vertical   piles   also  may   be
       designed   with  a  tie  back
       component at an angle  to  the
       vertical  to  develop  a   high
       resistance to lateral forces.  This
       type of wall is recommended for
       use in areas
                                               56

-------
                             Location Criteria
                             Figure 2-7
               Sample Output from PC STABL Model
 CD Subgrade: Internal friction angle = 32 degrees
 © Refuse: Internal friction angle of waste = 25 degrees
 ® Refuse: Internal friction angle of waste = 25 degrees
 Sliding Block/Wedge
    Failure Surface
Factor of Safety = 1.374
                                                 Circular Failure Surface,
                                                 Factor of Safety = 1.723
                                    57

-------
             Scheme
    Applicable Methods
        Comments
 1. Changing Geometry
     Excavation
1.    Reduce slope height by
     excavation at top of slope

2.    Flatten the slope angle.

3.    Excavate a bench in
     upper part of slope.
   Area has to be accessible
   to construction
   equipment. Disposal site
   needed for excavated soil.
   Drainage sometimes
   incorporated in this
   method.
 2. Earth Berm Fill
     Compacted earth or rock
     berm placed at end
     beyond the toe. Drainage
     may be provided behind
     the berm.
   Sufficient width and
   thickness of berm
   required so failure will
   not occur below or
   through the berm.
 3. Retaining Structures
                   Retaining
                   S true cure
     Retaining wall: crib or
     cantilever type.

     Drilled, cast-in-place
     vertical piles and/or slabs
     founded well below
     bottom slide plane.
     Generally 18 to 36 inches
     in diameter and 4- to 8-
     foot spacing. Larger
     diameter piles  at closer
     spacing may be required
     in some cases with
     mitigate failures  of cuts
     in highly fissured clays.
1.  Usually expensive.
   Cantilever walls might
   have to be tied back.

2.  Spacing should be such
   that soil can arch between
   piles. Grade beam can be
   used to tie piles together.
   Very large diameter (6
   feett) piles have been
   used for deep slide.
Source: Soil Mechanics, NAVFAC Design Manual 7.01
                                           Table 2-5
                            Methods of Stabilizing Excavation Slopes

-------
             Scheme
    Applicable Methods
        Comments
                                    3.
    Retainine Structure'
                                    4.
    Retainine Structure
   Retaining
   Structure
               1
     Drilled, cast-in-place
     vertical piles tied back
     with battered piles or a
     deadman.  Piles founded
     well below slide plane.
     Generally, 12 to 30
     inches in diameter and at
     least 4- to  8-foot spacing.
     Earth and rock anchors
     and rock bolts.
                                         Reinforced earth.
3.  Space close enough so
   soil will arch between
   piles. Piles can be tied
   together with grade beam.
4.  Can be used for high
   slopes, and in very
   restricted areas.
   Conservative design
   should be used, especially
   for permanent support.
   Use may be essential for
   slopes in rocks where
   joints dip toward
   excavation, and such
   joints daylight in the
   slope.

5.  Usually expensive
 4. Other methods
See TABLE 7, NAVFAC DM-
7.2, Chapter 1
Source: Soil Mechanics, NAVFAC Design Manual 7.01
                                     Table 2-5 (continued)
                           Methods of Stabilizing Excavation Slopes

-------
                                          Subpart B
    with  steeply  cut  slopes where soil
    arching can be developed between the
    piles.

    —     The last retaining wall  shown
           uses  a cantilever  setup  along
           with   soil    that   has   been
           reinforced  with  geosynthetic
           material to provide a system that
           is highly resistant to vertical and
           lateral  motion.  This type  of
           system is best suited for use in
           situations where vertically  cut
           slopes   must   have   lateral
           movement strictly controlled.

Other potential procedures for stabilizing
natural and human-made slopes include the
use of geotextiles  and geogrids to provide
additional strength, the installation of wick
and  toe  drains  to relieve  excess pore
pressures,  grouting,   and  vacuum  and
wellpoint pumping to lower ground-water
levels. In addition, surface drainage may be
controlled to decrease infiltration, thereby
reducing the potential for mud and debris
slides in some areas. Lowering the ground-
water  table  also  may  have stabilizing
effects.  Walls or large-diameter piling can
be used to stabilize slides of relatively small
dimension or to retain steep toe slopes  so
that failure will not extend back into a larger
mass (U.S. Navy, 1986).  For more detailed
information regarding slope  stabilization
design,  refer to  Winterkorn and  Fang
(1975),  U.S.  Navy (1986),  and  Sowers
(1979).  Richardson and Koerner (1987) and
Koerner (1986) provide design guidance for
geosynthetics in both landfill and general
applications.
Monitoring

During  construction activities, it may be
appropriate  to  monitor  slope  stability
because of the additional stresses placed on
natural  and engineered soil  systems (e.g.,
slopes,  foundations, dikes)  as a result of
excavation and  filling  activities.   Post-
closure slope monitoring usually  is not
necessary.

Important monitoring  parameters may
include settlement,  lateral movement, and
pore water pressure.  Monitoring for pore
water pressure is usually accomplished with
piezometers screened in the sensitive strata.
Lateral  movements of structures may be
detected  on the  surface  by  surveying
horizontal  and    vertical   movements.
Subsurface movements may be detected by
use of slope inclinometers.  Settlement may
be monitored by surveying ground surface
elevations (on  several  occasions over a
period of  time) and  comparing them with
areas that are not likely to experience
changes in elevations (e.g.,  USGS  survey
monuments).

Engineering Considerations for  Karst
Terrains

The principal concern with karst terrains is
progressive and/or  catastrophic failure of
subsurface conditions due to the presence of
sinkholes,   solution   cavities,    and
subterranean  caverns.  The  unpredictable
and catastrophic nature of subsidence in
these areas makes them difficult to develop
as landfill  sites. Before situating a MSWLF
in a karst  region, the subject site should be
characterized thoroughly.
                                             60

-------
                                        Location Criteria
The first  stage  of  demonstration  is  to
characterize  the  subsurface.    Subsurface
drilling, sinkhole monitoring, and geophysical
testing are direct means that can be used to
characterize a site.  Geophysical techniques
include   tests    using   electromagnetic
conductivity,  seismic  refraction,   ground-
penetrating  radar,  gravity,  and electrical
resistivity. Interpretation and applicability of
different geophysical techniques should  be
reviewed by a qualified geophysicist.  Often
more than one technique should be employed
to  confirm  and  correlate  findings and
anomalies.       Subsurface   drilling   is
recommended highly for verifying the results
of geophysical investigations.

Additional  information on karst conditions
can come from remote sensing techniques,
such  as aerial  photograph  interpretation.
Surface mapping of karst features can help to
provide  an  understanding  of  structural
patterns and  relationships in karst terrains.
An understanding of local carbonate  geology
and stratigraphy can aid in the interpretation
of  both remote  sensing  and  geophysical
techniques.

A demonstration that engineering measures
have been incorporated into a unit located in
a karst terrain may  include both initial
design and site modifications. A relatively
simple engineering modification that can be
used to mitigate  karst terrain problems is
ground-water and surface water control and
conveyance.  Such water control measures are
used to minimize the rate of dissolution within
known near-surface limestone. This means
of controlling karst development may not be
applicable to all karst situations.  In areas
where  development of karst  topography
tends to be minor, loose soils overlying the
limestone    may   be    excavated    or
heavily compacted to achieve the needed
stability. Similarly, in areas where the karst
voids are relatively small and limited in
extent,  infilling  of the void  with slurry
cement grout or other material may be an
option.

In general,  due to  the  unpredictable and
catastrophic nature of ground failure in such
areas,  engineering  solutions   that try to
compensate for the weak geologic structures
by constructing manmade ground supports
tend to be complex and costly. For example,
reinforced raft (or mat) foundations could be
used  to  compensate for lack  of ground
strength in some karst areas. Raft foundations
are a type of "floating foundation" that consist
of a concrete footing that extends over a very
large area. Such foundations are used where
soils have a low bearing capacity or where
soil conditions are variable and erratic; these
foundations are able to reduce and distribute
loads.  However,  it should be noted that, in
some instances, raft foundations may not
necessarily be able to prevent  the extreme
type of collapse and settlement that can occur
in karst areas. In addition, the construction of
raft foundations can be very costly, depending
on the size of the area.
2.8 CLOSURE OF EXISTING
   MUNICIPAL SOLID WASTE
   LANDFILL UNITS
   40 CFR §258.16

2.8.1  Statement of Regulation

    (a)    Existing  MSWLF  units  that
cannot make the demonstration specified
in  §§258.10(a),  pertaining to  airports,
258.11(a), pertaining to floodplains,  and
258.15(a),  pertaining to unstable  areas,
                                              61

-------
                                           Subpart B
must  close   by  October  9,   1996,  in
accordance with §258.60 of this part and
conduct   post-closure    activities    in
accordance with §258.61 of this part.

    (b) The deadline for closure required
by  paragraph (a) of this  section may be
extended up to two years if the owner or
operator demonstrates to the Director of an
approved State that:

    (1) There is no available alternative
disposal capacity;

    (2) There is no immediate threat  to
human health and the environment.

2.8.2  Applicability

These  requirements  are applicable  to all
MSWLF  units  that receive waste  after
October 9, 1993 and cannot meet the airport
safety,   floodplain,   or   unstable   area
requirements.    The  owner or operator  is
required to demonstrate  that the facility: (1)
will not pose a bird hazard to aircraft under
§258.10(a); (2) is designed to prevent washout
of solid waste,  will not restrict floodplain
storage capacity, or increase floodwater flow
in a 100-year floodplain under §258.11 (a);
and  3) can withstand  damage  to  landfill
structural component systems (e.g.,  liners,
leachate collection,  and other  engineered
structures) as a result of unstable conditions
under   §258.15(a).      If  any   of  these
demonstrations cannot be made,  the landfill
must close by  October 9, 1996. In approved
States, the closure deadline  may be extended
up to two additional years if it can be shown
that alternative  disposal   capacity   is not
available and that the MSWLF unit does not
pose an immediate threat to human health and
the environment.
2.8.3  Technical Considerations

The engineering considerations that should be
addressed  for  airport  safety,  100-year
floodplain encroachment, and unstable areas
are discussed in Sections 2.2, 2.3, and 2.7 of
this chapter.   Information  and evaluations
necessary for these demonstrations also are
presented in  these  sections.  If applicable
demonstrations are not made by the owners or
operators, the landfill unit(s) must be closed
according to  the  requirements of  section
§258.60 by October 9, 1996.

For MSWLF units located in approved States,
this deadline may be extended if there is no
immediate threat to human health and the
environment and no waste disposal alternative
is  available.   The demonstration of no
disposal alternative should consider all waste
management  facilities,  including landfills,
municipal waste combustors, and recycling
facilities. The demonstration for the two-year
extension should consider  the  impacts on
human health and the environment  as  they
relate to airport safety, 100-year floodplains,
or unstable areas.

§§258.17-258.19  [Reserved].
                                              62

-------
                                      Location Criteria
2.9 FURTHER INFORMATION

2.9.1  References

General

  Linsley and Franzini, (1972).  "Water Resources Engineering"; McGraw-Hill; pp. 179-184.

  U.S. EPA, (1988). "Guide to Technical Resources for the Design of Land Disposal Facilities";
      EPA/625/6-88/018; USEPA; Risk  Reduction  Engineering Laboratory and Center for
      Environmental Research Information; Office of Research and Development; Cincinnati,
      Ohio 45268.

  USGS.  Books and Open File Section, Branch Distribution, Box 25046, Federal Center, Denver,
      CO 80225.

Floodplains

  COE, (1982). HEC-1, HEC-2, HEC-5, HEC-6 Computer Programs; Hydrologic Engineering
      Center (HEC); U.S. Army Corps of Engineers; Hydrologic Engineering Center; Davis
      California.

  Federal Emergency Management Agency, (1980). "How to Read a Flood Insurance Rate Map";
      April 1980.  Available from FEMA Regional Offices.

  Maynard, S.T., (1978).  "Practical Riprap Design"; Hydraulics Laboratory Miscellaneous Paper
      H-78-7; U.S. Army Engineers Waterways Experiment Station; Vicksburg, Mississippi. SCS,
      (1983).

  "Maryland Standards and Specifications for Soil Erosion and Sediment Control"; U.S. Soil
      Conservation Service; College Park, Maryland.

  U.S. Water Resources Council, (1977).  "Guidelines for Determining Flood Flow Frequency";
      Bulletin #17A of the Hydrology Committee; revised June 1977.

Wetlands

  COE, (1987).  "Corps of Engineers Wetlands Delineation Manual," Technical Report (Y-87-1),
      Waterways Experiment Station, Jan. 1987.
                                             63

-------
                                         Subpart B
  COE, (1989).  "Federal Manual for Identifying and Delineating Jurisdictional Wetlands,"
       Federal Interagency Committee for Wetland Delineation; U.S. Army Corps of Engineers,
       U.S. Environmental Protection Agency, U.S. Fish and Wildlife Service, and U.S.D.A.,
       Soil Conservation Service; Washington, D.C., Cooperative Technical Publication.  1989.

  Fault Areas, (1992). "Aspects of Landfill Design for Stability in Seismic Zones," Hilary I.
       Inyang, Ph.D.

Seismic Impact Zones

  Algermissen, S.T., et al., (1991). "Probabilistic Earthquake Acceleration and Velocity Maps
       for the United  States and Puerto Rico,"  USGS Miscellaneous Field Study Map MF-
       2120.

  Algermissen, S.T., et al., (1976).  "Probabilistic Estimates  of Maximum Acceleration and
       Velocity in Rock in the Contiguous United States"; Open File Report 82-1033; U.S.
       Geological Survey; Washington, D.C.

  U.S. EPA, (1992). "Aspects of Landfill Design for Stability in Seismic Zones", Hilary I.
       Inyang. Ph.D.

  U.S. Navy,  (1983).  "Design Manual-Soil Dynamics,  Deep  Stabilization, and Special
       Geotechnical Construction," NAVFAC DM-7.3; Department of the Navy; Washington,
       D.C.; April, 1983.

  Winterkorn, H.F. and Fang, H.Y., (1975).   "Foundation  Engineering  Handbook." Van
       Nostrand Reinhold. 1975.

Unstable Areas

  Geoslope Programming Ltd., (1986).  PC-SLOPE, Version 2.0 (May);  Calgary, Alberta,
       Canada.

  Huang, U.K., (1983). "Stability Analysis of Earth Slopes"; Van Nostrand Reinhold Co.; New
       York.

  Koerner, R.M., (1986).  "Designing with Geosynthetics"; Prentice-Hall Publishing Co.;
       Englewood Cliffs, New Jersey.

  Lambe, W.T. and R.V. Whitman, (1969). "Soil Mechanics"; John Wiley and Sons, Inc.; New
       York.
                                            64

-------
                                      Location Criteria
  Richardson, G.N. and R.M. Koerner, (1987).  "Geosynthetic Design Guidance for Hazardous
       Waste Landfill Cells and Surface Impoundments"; Hazardous Waste Engineering Research
       Laboratory; USEPA, Office of Research and Development; Cincinnati, Ohio; Contract No.
       68-07-3338.

  Sowers, G.F., (1979).  "Soil Mechanics and Foundations: Geotechnical Engineering,"  The
       MacMillan Company, New York.

  Terzaghi, K. and R.B. Peck, (1967). "Soil Mechanics in Engineering Practice", 2nd Edition; John
       Wiley and Sons, Inc.; New York.

  U.S. Navy, (1986).  "Design Manual-Soil Mechanics, Foundations and Earth Structures,"
       NAVFAC DM-7; Department of the Navy; Washington, D.C.; September 1986.

  Winterhorn, H.F. and Fang, H.Y., (1975).  "Foundation Engineering Handbook," Van Nostrand
       Reinhold, 1975.

2.9.2  Organizations

American Institute of Architects
Washington, D.C.
(202) 626-7300

Aviation Safety  Institute (ASI)
Box 304
Worthington, OH 43085
(614) 885-4242

American Society of Civil Engineers
345 East 47th St.
New York, NY  10017-2398
(212) 705-7496

Building Seismic Safety Council
201 L Street, Northwest Suite 400
Washington, D.C. 20005
(202) 289-7800

Bureau of Land  Management
1849C St. N.W.
Washington, D.C. 20240
(202) 343-7220  (Locator)
(202) 343-5717  (Information)
                                             65

-------
                                         Subpart B
Federal Emergency Management Agency
Flood Map Distribution Center
6930 (A-F) San Thomas Road
Baltimore, Maryland 21227-6227
1-800-358-9616

Federal Emergency Management Agency
(800) 638-6620 Continental U.S. only, except Maryland
(800) 492-6605 Maryland only
(800) 638-6831 Continental U.S., Hawaii, Alaska, Puerto Rico, Guam, and the Virgin Islands

Note: The toll free numbers may be used to obtain any of the numerous FEMA publications such
      as "The National Flood Insurance Program Community Status Book," which is published
      bimonthly.

          To obtain Flood Insurance Rate Maps and  other flood maps, the FEMA Flood Map
          Distribution Center should be contacted at 1-800-358-9616.

Federal Highway Administration
400 7th St. S.W.
Washington, D.C. 20590
(202) 366-4000 (Locator)
(202) 366-0660 (Information)

Hydrologic Engineering Center (HEC Models)
U.S. Army Corps of Engineers
609 Second St.
Davis, CA 95616
(916)756-1104

National Information Service for Earthquake Engineering (NISEE)
University of California, Berkeley
404A Davis Hall
Berkeley, CA 94720
(415)642-5113
(415) 643-5246 (FAX)

National Oceanic and Atmospheric Administration
Office of Legislative Affairs
1825 Connecticut Avenue Northwest
Room 627
Washington, DC 20235
(202) 208-5717
                                            66

-------
                                      Location Criteria
Tennessee Valley Authority
412 First Street Southeast, 3rd Floor
Washington, DC 20444
(202) 479-4412

U.S. Department of Agriculture
Soil Conservation Service
P.O. Box 2890
Washington, DC 20013-2890
(Physical Location: 14th and Independence Ave. N.W.)
(202)447-5157

U.S. Department of the Army
U.S. Army Corps of Engineers
Washington, DC 20314-1000
(202) 272-0660

U.S. Department of the Interior
Fish and Wildlife Service
1849 C Street Northwest
Washington, DC 20240
(202) 208-5634

U.S. Department of Transportation
Federal Aviation Administration
800 Independence Ave., S.W.
Washington, D.C. 20591
(202) 267-3085

U.S. Geological Survey
12201 Sunrise Valley Drive
Reston, Virginia 22092
(800) USA-MAPS

U.S. Geological Survey
Branch of Geologic Risk Assessment
Stop 966 Box 25046
Denver, Colorado 80225
(303) 236-1629

U.S. Geological Survey
EROS Data Center
Sioux Falls, South Dakota 57198
(605)594-6151
                                            67

-------
                                         Subpart B
U.S. Geological Survey
National Earthquake Information Center
Stop 967 Box 25046
Denver Federal Center
Denver, Colorado 80225
(303)236-1500
2.9.3  Models

  Adamus, P.R., et  al.,  (1987).   "Wetland  Evaluation  Technique  (WET);  Volume  II:
       Methodology"; Operational Draft Technical Report Y-87; U.S. Army Engineer Waterways
       Experiment Station; Vicksburg, MS.

  COE, (1982).  HEC-1, HEC-2, HEC-5, HEC-6 Computer Programs; Hydrologic Engineering
       Center (HEC); U.S. Army Corps  of Engineers; Hydrologic Engineering Center; Davis
       California.

  Geoslope Programming Ltd., (1986). PC-SLOPE, Version 2.0 (May); Calgary, Alberta, Canada.

  Lysemer, John, et al., (1979).  "FLUSH: A Computer Program for Approximate  3-D Analysis";
       University of California at Berkeley; March 1979.  (May be obtained through the National
       Information Service for Earthquake Engineering at the address provided in subsection 2.9.2
       of this document.)

  Purdue University, Civil Engineering Dept, (1988).  PC STABL, West Lafayette, IN 47907.

  United States Fish and Wildlife  Service, (1980).  "Habitat Evaluation Procedures".  ESM 102;
       U.S. Fish and Wildlife Service; Division of Ecological Services; Washington, D.C.
                                             68

-------
   APPENDIX I
FAA Order 5200.5A
       69

-------
                                            U.S. DEPARTMENT OF TRANSPORTATION
                                             FEDERAL AVIATION ADMINISTRATION
                                                                                                                              5200.5A
                                                                1/31/90
                                      SUBJ: WASTE DISPOSAL SITES ON OR NEAR AIRPORTS
1.         PURPOSE. This order provides guidance concerning the establishment, elimination or monitoring of landfills, open dumps, waste disposal
sites or similarly titled facilities on or in the vicinity of airports.

2.         DISTRIBUTION. This order is distributed to the division level in the Offices of Airport Planning and Programming Airport Safety and
Standards, Air Traffic Evaluations and Analysis Aviation Safety Oversight, Air Traffic Operations Service, and Flight Standards Service; to the
division level in the regional Airports, Air Traffic, and Flight Standards Divisions; to the director level at the Aeronautical Center and the FAA
Technical Center, and a limited distribution to all Airport District Offices, Flight Standards Field Offices, and Air Traffic Facilities.

3.         CANCELLATION. Order 5200.5, FAA Guidance Concerning Sanitary Landfills On Or Near Airports, dated October 16, 1974, is canceled.

4.         BACKGROUND. Landfills, garbage dumps, sewer or fish waste outfalls and other similarly licensed or titled facilities used for operations
to process, bury, store or otherwise dispose of waste, trash and refuse will attract rodents and birds. Where the dump is ignited and produces smoke,
an additional attractant is created. All of the above are undesirable and potential hazards to aviation since they erode the safety of the airport
environment. The FM neither approves nor disapproves locations  of the facilities above. Such action is the responsibility of the Environmental
Protection Agency and/or the appropriate state and local agencies. The role of the FAA is to ensure that airport owners and operators meet their
contractual obligations to the United States government regarding compatible land uses in the vicinity of the airport. While the chance  of an
unforeseeable, random bird strike in flight will always exist, it is nevertheless possible to define conditions within fairly narrow limits where the risk
is increased. Those high-risk conditions exist in the approach and departure patterns and landing areas on and in the vicinity of airports. The number
of bird strikes reported on aircraft is a matter of continuing concern to the FM and to airport management.  Various observations  support the conclusion
that waste disposal sites are artificial attractants to birds. Accordingly, disposal sites located in the vicinity of an airport are potentially incompatible
with safe flight operations. Those sites that are not compatible need to be eliminated. Airport owners need guidance in making those decisions and
the FM must be in a position to assist. Some airports are not under the jurisdiction of the community or local governing body having control of land
usage in the vicinity of the airport. In these areas, the airport owner should use its resources and exert its best efforts to close or control waste disposal
operations within the general vicinity of the airport.

5.         EXPLANATION OF CHANGES. The following list outlines the major changes to Order 5200.5:

          a. Recent developments and new techniques of waste disposal warranted updating and clarification of what  constitutes a sanitary landfill.
This listing of new titles for waste disposal was  outlined in paragraph 4.

          b. Due to a reorganization which placed the Animal Damage Control Branch of the U. S. Department of Interior Fish and Wildlife Service
under the jurisdiction of the U.S. Department of Agriculture an address addition was necessary

          c. A zone of notification was added to the criteria which should provide the appropriate FM Airports office an opportunity to comment
on the proposed disposal site  during the selection process.

6. ACTION.

   a. Waste disposal sites located or proposed to be located within the  areas established for an airport by the guidelines set  forth in paragraphs 7 a
b, and c of this order should  not be allowed to  operate. If a waste disposal site is incompatible with an airport in accordance with guidelines  of
paragraph 7 and cannot be  closed within a reasonable time, it should be operated in accordance with the criteria and instructions issued by Federal
agencies such as the Environmental Protection Agency and the Department of Health and Human Services, and other such regulatory bodies that may
have applicable requirements. The appropriate  FM airports office should advise airport owners, operators and waste disposal proponents against
locating, permitting or concurring in the location of a landfill or similar facility on or in the vicinity of airports.
                                                                  70

-------
          (1) Additionally, any operator proposing a new or expanded waste disposal site within 5 miles of a runway end should notify the airport
and the appropriate FM Airports office so as to provide an opportunity to review and comment on the site in accordance with the guidance contained
in this order. FM field offices may wish to contact the appropriate State director of the United States Department of Agriculture to assist in this review.
Also, any Air Traffic control tower manager or Flight Standards District Office manager and their staffs that become aware of a proposal to develop
or expand a disposal site should notify the appropriate FM Airports office.

          b. The operation of a disposal site located beyond the areas described in paragraph 7 must be properly supervised to ensure compatibility
with the airport.

          c. If at any time the disposal  site, by virtue of its location or operation, presents a potential hazard to aircraft operations the owner should
take action to correct the situation or terminate operation of the facility. If the owner of the airport also owns or controls the disposal facility and is
subject to Federal obligations to protect compatibility of land uses around the airport, failure to take corrective action could place the airport owner
in noncompliance with its commitments to the Federal government. The appropriate FM office should immediately evaluate the situation to determine
compliance with federal  agreements and take  such action as may be warranted under the guidelines as prescribed  in Order 5190.6, Airports
Compliance Requirements, current edition.

          (1) Airport owners should  be encouraged to make periodic inspections of current operations of existing disposal sites near a federally
obligated airport where  potential bird  hazard problems have been reported.

          d. This order is not intended to resolve all related problems but is specifically directed toward eliminating waste disposal sites, landfills
and similarly titled facilities  in the proximity of airports, thus providing a safer environment for aircraft operations.

          e. At airports certified under Federal Aviation Regulations, part  139, the airport certification manual/specifications should require disposal
site inspections at appropriate intervals for those operations meeting the criteria of paragraph 7 that cannot be closed. These inspections are necessary
to assure that bird populations are not increasing and that appropriate control procedures are being established and followed. The appropriate FAA
airport offices should develop working relationships with state aviation agencies and state agencies that have authority over waste disposal and
landfills to stay abreast of proposed developments and expansions and apprise them of the hazards to aviation that these present.

          f. When proposing a disposal site, operators should make their plans available to the appropriate state regulatory agencies. Many states
have criteria concerning siting requirements specific to their jurisdictions.

          g. Additional information on waste disposal, bird hazard and related problems may be obtained from the following agencies:

                               U.S. Department of Interior Fish and Wildlife Service
                                18th and C Streets, NW
                               Washington, DC 20240

                               U.S. Department of Agriculture
                               Animal Plant Health Inspection Service
                               P.O. Box 96464
                               Animal Damage Control Program
                               Room 1624 South Agriculture Building
                               Washington, DC 20090-6464

                               U.S. Environmental Protection Agency
                               401  M Street, SW
                               Washington, DC 20460

                               U.S. Department of Health and Human Services
                               200  Independence Avenue, SW
                               Washington, DC 20201

7.        CRITERIA. Disposal sites  will be considered as incompatible if located within areas established for the airport through the application
of the following criteria:

   a. Waste disposal sites located within 10,000 feet of any runway end used or planned to be used by turbine powered aircraft

   b. Waste disposal sites located within 5,000 feet of any runway end used only by piston powered aircraft.
                                                                  71

-------
          c. Any waste disposal site located within a 5-mile radius of a runway end that attracts or sustains hazardous bird movements from feeding,
water or roosting areas into, or across the runway and/or approach and departure patterns of aircraft.

Leonard E. Mudd
Director, Office of Airport Safety and Standards
                                                                 72

-------
    CHAPTER 3

    SUSPART C
OPERATING CRITERIA

-------
                                      CHAPTER 3
                                      SUBPART C

                                TABLE OF CONTENTS
3.1  INTRODUCTION 	  76

32     PROCEDURES FOR EXCLUDING THE RECEIPT OF HAZARDOUS WASTE 40 CFR
       §258.20	  77
       3.2.1  Statement of Regulation 	  77
       3.2.2  Applicability	  77
       3.2.3  Technical Considerations 	  77
             Inspections	  78
             Alternative Methods for Detection and Prevention	  81
             Recordkeeping	  82
             Training	  82
             Notification to Authorities and Proper Management of Wastes	  82

33.     COVER MATERIAL REQUIREMENTS 40 CFR §258.21  	  84
       3.3.1  Statement of Regulation 	  84
       3.3.2  Applicability	  84
       3.3.3  Technical Considerations 	  84

3A     DISEASE VECTOR CONTROL 40 CFR §258.22	  86
       3.4.1  Statement of Regulation 	  86
       3.4.2  Applicability	  86
       3.4.3  Technical Considerations 	  87

3J     EXPLOSIVE GASES  CONTROL 40  CFR §258.23	  87
       3.5.1  Statement of Regulation 	  87
       3.5.2  Applicability	  88
       3.5.3  Technical Considerations 	  89
             Gas Monitoring  	  90
             Landfill Gas Control Systems	  94
             Passive Systems	  96
             Active  Systems	  96

3_A     AIR CRITERIA 40  CFR §258.24	101
       3.6.1  Statement of Regulation 	101
       3.6.2  Applicability	101
       3.6.3  Technical Considerations 	101
                                          74

-------
3.7    ACCESS REQUIREMENT 40 CFR §258.25	103
       3.7.1 Statement of Regulation  	103
       3.7.2 Applicability	103
       3.7.3 Technical Considerations  	103

M    RUN-ON/RUN-OFF CONTROL SYSTEMS 40 CFR §258.26	104
       3.8.1 Statement of Regulation  	104
       3.8.2 Applicability	104
       3.8.3 Technical Considerations  	104

3_J)    SURFACE WATER REQUIREMENTS 40 CFR §258.27 	105
       3.9.1 Statement of Regulation  	105
       3.9.2 Applicability	106
       3.9.3 Technical Considerations  	106

3.10   LIQUIDS RESTRICTIONS 40 CFR §258.28	107
       3.10.1 Statement of Regulation  	107
       3.10.2 Applicability	107
       3.10.3 Technical Considerations  	108

3.11   RECORDKEEPING REQUIREMENTS 40 CFR §258.29 	110
       3.11.1 Statement of Regulation  	110
       3.11.2 Applicability	110
       3.11.3 Technical Considerations  	Ill

3.12 FURTHER INFORMATION	114
       3.12.1 References	114
       3.12.2 Addresses  	114
APPENDIX I - SPECIAL WASTE ACCEPTANCE AGREEMENT	  Following Page 114
                                           75

-------
                                    CHAPTER 3
                                    SUBPART C
                            OPERATING CRITERIA
3.1  INTRODUCTION

The Solid Waste Disposal Facility Criteria contain a series of operating requirements pertaining to
routine operation, management, and environmental monitoring at municipal solid waste landfill
units (MSWLF units).  The operating requirements pertain to new MSWLF units, existing MSWLF
units, and lateral expansions of existing MSWLF units.

The operating requirements have been developed to ensure the safe daily operation and management
at MSWLF units.  The operating requirements include:
  The exclusion of hazardous waste;
  Cover material;
  Disease vector control;
  Explosive gases control;
  Air monitoring;
Facility access;
Run-on/run-off control systems;
Surface water requirements;
Liquid restrictions; and
Recordkeeping requirements.
Any owner or operator of a MSWLF unit must comply with the operating requirements by October
9, 1993.

In specific cases, the operating requirements require compliance with other Federal laws.  For
example, surface water discharges from a MSWLF unit into the waters of the United States must
be in conformance with applicable  sections  of the Clean Water Act. In addition, burning of
municipal solid waste (MSW) is regulated under applicable sections of the Clean Air Act.
                                          76

-------
                                   Operating Criteria
3.2  PROCEDURES FOR EXCLUDING
     THE RECEIPT OF HAZARDOUS
     WASTE 40 CFR §258.20

3.2.1  Statement of Regulation

   (a) Owners or operators of all MSWLF
units must implement a program at the
facility for detecting and preventing the
disposal of regulated hazardous wastes as
defined  in  Part  261 of  this  title  and
polychlorinated biphenyls (PCB) wastes as
defined in Part 761 of this title.   This
program must include, at a minimum:

   (1)  Random  inspections  of incoming
loads unless the owner or  operator takes
other steps to ensure that incoming loads
do not contain regulated hazardous wastes
or PCB wastes;

   (2) Records of any inspections;

   (3)  Training of  facility personnel  to
recognize regulated  hazardous waste and
PCB wastes; and

   (4)  Notification of State Director  of
authorized States  under  Subtitle C  of
RCRA or the EPA Regional Administrator
if in an unauthorized State if a regulated
hazardous  waste   or  PCB  waste  is
discovered at the facility.

   (b)  For   purposes  of  this   section,
regulated hazardous waste means a solid
waste that is a hazardous waste, as defined
in 40 CFR 261.3, that is not excluded from
regulation as a hazardous waste under 40
CFR 261.4(b) or was not generated by a
conditionally   exempt  small   quantity
generator as defined in §261.5 of this title.
3.2.2  Applicability

This regulation applies to all MSWLF units
that receive wastes on or after October 9,
1993.

The owner or operator must develop  a
program  to detect and prevent disposal of
regulated hazardous wastes or PCB wastes at
the MSWLF facility. Hazardous wastes may
be gases, liquids,  solids, or  sludges that are
listed or exhibit the characteristics described
in 40 CFR Part 261. Household hazardous
wastes  are  excluded   from   Subtitle  C
regulation,   and   wastes  generated   by
conditionally    exempt   small   quantity
generators  (CESQGs)  are  not considered
regulated hazardous wastes  for purposes of
complying  with  §258.20; therefore,  these
wastes may be accepted for disposal  at  a
MSWLF unit.

The MSWLF hazardous waste exclusion
program  should be capable of detecting and
preventing  disposal of PCB wastes.  PCB
wastes may be liquids or non-liquids (sludges
or solids) and are defined at 40 CFR Section
761.60.   PCB wastes do not include  small
capacitors found in fluorescent light ballast,
white  goods   (e.g.,   washers,   dryers,
refrigerators)  or  other  consumer electrical
products (e.g., radio and television units).

The hazardous waste exclusion program is not
intended   to   identify  whether regulated
hazardous waste or PCB waste was received
at the MSWLF unit or facility prior to the
effective date of the Criteria.

3.2.3  Technical Considerations

A solid waste is a regulated hazardous waste
if it: (1) is listed in Subpart D of 40 CFR
                                          77

-------
                                        Subpart C
Part 261 (termed a "listed" waste); (2) exhibits
a  characteristic  of a  hazardous  waste  as
defined in Subpart C of 40 CFR Part 261; or
(3) is a mixture  of a listed hazardous waste
and    a    non-hazardous   solid   waste.
Characteristics of hazardous wastes  as defined
in Subpart C of 40 CFR Part 261 include
ignitability,   corrosivity,   reactivity,  and
toxicity.  The toxicity characteristic leaching
procedure (TCLP) is the test method used to
determine  the   mobility  of  organic  and
inorganic compounds present in liquid, solid,
and  multiphase  wastes.    The  TCLP  is
presented in Appendix II of Part 261.

The MSWLF Criteria exclude CESQG waste
(as defined in  40  CFR §261.5) from  the
definition of "regulated hazardous wastes."
CESQG  waste  includes  listed  hazardous
wastes or wastes that exhibit a characteristic
of a hazardous waste that  are generated in
quantities no greater than  100 kg/month, or
for acute  hazardous  waste,  1   kg/month.
Under 40 CFR §261.5(f)(3)(iv) and  (g)(3)(iv),
conditionally exempt small quantity generator
hazardous wastes may be disposed at facilities
permitted, licensed, or registered by a State to
manage municipal or industrial solid waste.

Other  solid wastes  are  excluded  from
regulation  as a  hazardous waste under 40
CFR  §261.4(b)  and may be  accepted  for
disposal  at  a  MSWLF  unit.   Refer  to
§261.4(b) for a listing of these wastes.

PCBs  are   regulated   under  the  Toxic
Substances Control Act (TSCA),  but PCB-
containing  wastes are considered  hazardous
wastes in some States. PCBs typically  are not
found  in  consumer  wastes  except  for
fluorescent ballast and small  capacitors in
white goods and  electrical appliances.
These sources are not regulated under 40 CFR
Part 761 and, therefore, are not part of the
detection  program required  by  §258.20.
Commercial  or industrial sources  of PCB
wastes  that  should be  addressed by  the
program include:

•   Mineral   oil   and   dielectric  fluids
    containing PCBs;

•   Contaminated  soil,  dredged  material,
    sewage sludge, rags, and other debris
    from a release of PCBs;

•   Transformers   and   other    electrical
    equipment containing dielectric fluids;
    and

•   Hydraulic machines.

The  owner  or  operator  is required  to
implement a program to detect and exclude
regulated hazardous wastes and PCBs from
disposal in the landfill unit(s). This program
must include elements for:

•   Random inspections of incoming loads or
    other prevention methods;

•   Maintenance of inspection records;

•   Facility personnel training; and

•   Notification to appropriate authorities if
    hazardous wastes or PCB  wastes  are
    detected.

Each of these program elements is discussed
separately on the following pages.

Inspections
An inspection is typically a visual observation
of the incoming waste loads by
                                           78

-------
                                    Operating Criteria
an  individual  who  is  trained  to identify
regulated hazardous or PCB wastes that would
not be acceptable for disposal at the MSWLF
unit. An inspection is considered satisfactory
if the  inspector  knows the nature of all
materials received in the load and is able to
discern whether the materials are potentially
regulated hazardous wastes or PCB wastes.

Ideally,  all  loads  should  be  screened;
however,  it  is generally  not  practical to
inspect in detail all incoming loads. Random
inspections, therefore, can be used to provide
a reasonable means to adequately control the
receipt  of  inappropriate wastes.  Random
inspections are simply inspections made on
less than every load.

The frequency of random inspections may be
based on the type  and  quantity  of wastes
received  daily,  and   the   accuracy   and
confidence desired in conclusions  drawn from
inspection observations.  Because statistical
parameters are not provided in the regulation,
a reasoned, knowledge-based approach may
be taken. A random inspection program may
take many forms such  as  inspecting every
incoming load one day out of every month or
inspecting   one  or   more  loads   from
transporters of wastes of unidentifiable nature
each day.  If these  inspections indicate that
unauthorized wastes are being brought to the
MSWLF site, then the  random inspection
program should be modified to increase the
frequency of inspections.

Inspection frequency also can vary depending
on the nature of the  waste.  For example,
wastes   received   predominantly    from
commercial or industrial sources may require
more  frequent  inspections  than  wastes
predominantly from households.
Inspection priority  also  can be  given to
haulers with unknown service areas, to loads
brought to the facility in vehicles not typically
used for disposal of municipal solid waste,
and to loads transported by previous would-be
offenders. For wastes of unidentifiable nature
received from sources other than households
(e.g.,      industrial      or     commercial
establishments), the inspector should question
the transporter about the  source/composition
of the materials.

Loads should be inspected  prior to  actual
disposal  of the  waste at the working face of
the landfill unit to provide the facility owner
or operator the opportunity to refuse or accept
the wastes. Inspections can be conducted on
a tipping floor of a transfer station before
transfer of the waste to the disposal facility.
Inspections also may occur at the tipping floor
located near the facility scale house, inside the
site entrance, or near, or adjacent  to, the
working  face  of the  landfill  unit.   An
inspection flow chart to  identify, accept, or
refuse  solid waste is provided as Figure 3-1.

Inspections of materials may be accomplished
by  discharging the vehicle load  in an  area
designed  to  contain  potentially  hazardous
wastes that may arrive at the facility.   The
waste  should  be  carefully  spread  for
observation using a front end loader or other
piece of equipment.   Personnel  should be
trained to identify suspicious wastes.  Some
indications of suspicious wastes are:

•   Hazardous  placards or marking;

    Liquids;

    Powders or dusts;
                                            79

-------
                                 Waste Inspected by
                                 Personnel Trained to
                                 Recognize Hazardous
                               Wastes Prior to Delivery at
                                    Working Face
Waste is Identified as
  Non-Hazardous
 Waste is Not Readily
     Identifiable
Waste is Identified as a
  Hazardous Waste
     Deliver to
   Working Face
  Isolate Wastes by
 Moving to Temporary
    Storage Area
      Record
     Inspection
    Refuse Waste
 Have Wastes Tested
Including Unidentified
Containerized Wastes
       Record
      Inspection
                     Waste Determined to
                      be Non-Hazardous
            Waste Determined to
               be Hazardous
                 Return to Working
                 Face and Dispose
                 Record Inspection
               Manifest and
            Transport Wastes to
             a Facility Permitted
               to Handle the
             Hazardous Waste
            (E.G., A Facility with
             a RCRA Permit or
               Interim Status)
                                              Record Inspection
                                               and Notify State
                                                   Director
                                   Figure 3-1
              Hazardous Waste Inspection Decision Tree
                    Inspection Prior to Working Face
                                        80

-------
                                    Operating Criteria
•  Sludges;

•  Bright or unusual colors;

•  Drums or commercial size containers; or

•  Chemical odors.

The  owner  or  operator  should  develop
specific  procedures to be  followed when
suspicious   wastes  are  discovered.    The
procedure  should  include   the  following
points:

•  Segregate the wastes;

•  Question the driver;

•  Review the manifest (if applicable);

•  Contact possible  source;

•  Call  the appropriate  State  or  Federal
   agencies;

•  Use appropriate protective equipment;

•  Contact laboratory support if required; and

•  Notify a response agency if necessary.

Containers with contents that are not easily
identifiable, such  as  unmarked 55-gallon
drums, should be opened only by properly
trained personnel. Because these drums could
contain hazardous  waste,  they  should be
refused whenever possible.  Upon verifying
that the solid waste is acceptable, it may then
be  transferred  to  the working  face  for
disposal.

Some facilities may consider it reasonable to
test unidentified waste, store it, and see that
it is disposed of properly.  Most facilities
would not consider this reasonable.

Testing typically would include The Toxicity
Characteristic Leaching  Procedure (TCLP)
and other tests for characteristics of hazardous
wastes including corrosivity, ignitability, and
reactivity. Wastes that are suspected of being
hazardous should be handled and stored as a
hazardous  waste until  a  determination is
made.

If the wastes temporarily stored at the site are
determined  to be hazardous,  the  owner or
operator is responsible for the management of
the waste. If the wastes are to be transported
from the facility, the waste must be: (1) stored
at the MSWLF  facility in accordance with
requirements of a hazardous waste generator,
(2) manifested, (3) transported by a licensed
transporter,  and  (4) sent to  a permitted
Treatment,  Storage,  or Disposal   (TSD)
facility for disposal.  These requirements are
discussed further in this section.

Alternative  Methods for  Detection  and
Prevention

While the  regulations  explicitly refer to
inspections  as  an  acceptable  means  of
detecting regulated hazardous wastes and PCB
wastes,  preventing  the  disposal  of these
wastes may be accomplished  through other
methods.    These   methods  may  include
receiving   only  household  wastes  and
processed (shredded or baled) wastes  that are
screened for the presence of the excluded
wastes prior to processing. A pre-acceptance
agreement between the owner or operator and
the waste hauler is another alternative method.
An example of a pre-acceptance agreement is
presented as Appendix  I.  The owner or
operator should
                                            81

-------
                                        Subpart C
keep any such agreements concerning these
alternatives in the operating record.

Recordkeeping

A record should be kept of each inspection
that is performed.  These records should be
included and maintained   in  the  facility
operating record.  Larger facilities that take
large amounts of industrial and commercial
wastes may use more detailed procedures than
smaller facilities  that  accept  household
wastes.  Inspection records may include the
following information:

•  The date and time wastes were received for
   inspection;

•  Source of the wastes;

•  Vehicle and driver identification; and

•  All observations made by the inspector.

The Director of an  approved  State  may
establish alternative recordkeeping locations
and requirements.

Training

Owners  or   operators  must  ensure  that
personnel  are trained  to identify  potential
regulated hazardous waste and PCB wastes.
These personnel could include supervisors,
designated inspectors, equipment operators,
and  weigh   station  attendants  who  may
encounter hazardous wastes.  Documentation
of training should be placed in the operating
record for the facility in accordance  with
§258.29.

The training  program  should  emphasize
methods to  identify containers  and labels
typical of hazardous waste and PCB waste.
Training also should address hazardous waste
handling procedures, safety precautions, and
recordkeeping    requirements.        This
information is provided in training courses
designed to comply with the  Occupational
Safety and Health Act (OSHA) under 29  CFR
§1910.120.   Information  covered in these
courses  includes  regulatory  requirements
under 40 CFR Parts 260 through 270, 29  CFR
Part 1910, and related guidance documents
that discuss such topics as:  general hazardous
waste   management;   identification    of
hazardous wastes; transportation of hazardous
wastes;   standards  for   hazardous  waste
treatment; storage and disposal facilities; and
hazardous waste  worker  health and safety
training and monitoring requirements.

Notification  to  Authorities  and  Proper
Management of Wastes

If regulated quantities of hazardous wastes or
PCB wastes are found at the landfill facility,
the owner or operator must notify the proper
authorities. Proper authorities are either the
Director  of a State  authorized to implement
the hazardous waste program under Subtitle C
of   RCRA,    or  the   EPA  Regional
Administrator, in an unauthorized State.

If the owner or operator discovers regulated
quantities of hazardous waste or PCB waste
while  it  is still  in the  possession  of the
transporter, the owner or operator can refuse
to accept the waste at the MSWLF facility,
and the waste will remain the responsibility of
the transporter. If the owner or operator is
unable to identify the transporter who brought
the hazardous waste, the owner or operator
must  ensure  that the waste is managed in
accordance
                                           82

-------
                                   Operating Criteria
with  all   applicable  Federal  and   State
regulations.

Operators of MSWLF facilities should be
prepared to handle hazardous wastes that are
inadvertently received at the MSWLF facility.
This may include having containers such as
5 5-gallon  drums   available   on-site  and
retaining a  list of  names  and telephone
numbers of the nearest haulers licensed to
transport hazardous waste.

Hazardous  waste  may  be  stored at the
MSWLF facility for 90 days, provided that
the following procedures required by 40 CFR
§262.34, or applicable State requirements, are
followed:

• The waste is placed in tanks or containers;

• The date of receipt of the waste is clearly
  marked and visible on each container;

• The  container or tank is marked clearly
  with the words "Hazardous Waste";

• An   employee  is  designated  as  the
  emergency coordinator who is responsible
  for coordinating  all  emergency  response
  measures; and

• The name and telephone  number  of the
  emergency coordinator and the number of
  the fire department is  posted next to the
  facility phone.

Extensions to store the waste beyond 90 days
may be approved pursuant to 40 CFR 262.34.

If the owner or operator transports the wastes
off-site, the owner or operator must comply
with 40  CFR Part 262 or the
analogous State/Tribal requirements.
owner or operator is required to:
The
•   Obtain an  EPA identification number
    (EPA form 8700-12  may  be used to
    apply for an EPA identification number;
    State or Regional personnel may be able
    to provide  a provisional identification
    number over the telephone);

•   Package  the waste in accordance with
    Department of  Transportation (DOT)
    regulations under 49 CFR Parts 173, 178,
    and 179 (The container must be labeled,
    marked,  and   display  a  placard  in
    accordance with DOT  regulations  on
    hazardous  wastes under 49 CFR Part
    172); and

•   Properly  manifest the waste designating
    a permitted facility to  treat,  store, or
    dispose of the hazardous waste.

If the owner or operator decides to treat, store
(for more than  90 days), or dispose of the
hazardous waste  on-site,  he or  she must
comply with the applicable State or Federal
requirements  for hazardous waste treatment,
storage, and  disposal facilities.  This may
require a permit.

PCB wastes detected at a MSWLF facility
must be stored and disposed  of according to
40 CFR Part  761.  The owner or operator is
required to:

•   Obtain  an  EPA  PCB  identification
    number;

•   Properly  store the PCB waste;

•   Mark containers or items with the words
    "Caution: contains PCBs"; and
                                          83

-------
                                       Subpart C
   Manifest the PCB waste for shipment to a
   permitted  incinerator,  chemical  waste
   landfill,   or   high  efficiency   boiler
   (depending  on the  nature of  the  PCB
   waste) for disposal.
3.3  COVER MATERIAL
     REQUIREMENTS
     40 CFR §258.21

3.3.1  Statement of Regulation

   (a) Except as provided in paragraph (b)
of this section, the owners or operators of
all MSWLF units must cover disposed solid
waste with six inches of earthen material at
the end of each operating day, or at more
frequent intervals if necessary, to control
disease vectors, fires, odors, blowing litter,
and scavenging.

   (b)     Alternative   materials  of  an
alternative thickness (other than at least six
inches  of  earthen  material)   may  be
approved by the Director of an approved
State   if   the   owner  or    operator
demonstrates that the alternative material
and thickness control disease vectors, fires,
odors,  blowing  litter,  and  scavenging
without  presenting a  threat  to human
health and the environment.

   (c)  The Director of an approved State
may grant a temporary waiver from the
requirement of paragraph (a) and  (b) of
this section if the owner  or  operator
demonstrates  that there  are  extreme
seasonal climatic conditions that  make
meeting such requirements impractical.
3.3.2  Applicability

The regulation applies to all MSWLF units
receiving waste after October 9, 1993.  The
regulation requires MSWLF unit owners and
operators to cover wastes with a 6-inch layer
of earthen material at the  end of  each
operating day. More frequent application of
soil may be required if the soil cover does not
control:

•   Disease vectors (e.g.,  birds,  flies and
    other insects, rodents);

•   Fires;

•   Odors;

•   Blowing litter; and

•   Scavenging.

The Director of an approved State may allow
an owner or operator to use alternative cover
material of an alternative thickness or grant a
temporary waiver of this requirement.  An
alternative material must not present a threat
to human  health and the environment, and
must continue to control disease vectors, fires,
odors, blowing litter, and scavenging.  The
only basis for a temporary waiver from the
requirement to cover at the end of  each
operating  day  would  be  where extreme
seasonal climatic conditions make compliance
impractical.

3.3.3  Technical Considerations

Owners and operators of new MSWLF units,
existing MSWLF units, and lateral expansions
are required to cover solid waste at the end of
each operating day with six inches of earthen
material. This cover
                                          84

-------
                                    Operating Criteria
material requirement is not related to the final
cover required under §258.60.

The placement of six inches of cover controls
disease vectors (birds, insects, or rodents that
represent the principal transmission pathway
of a human disease) by preventing egress
from the waste and by preventing access to
breeding  environments  or  food sources.
Covering    also   reduces   exposure   of
combustible materials to ignition sources and
may reduce the spread of fire if the disposed
waste burns.  Odors and blowing litter are
reduced by eliminating the direct contact of
wind   and  disposed  waste.     Similarly,
scavenging is reduced by removing the waste
from  observation.  Should these unwanted
effects of inadequate cover persist, the owner
or operator may increase the amount of soil
used or apply  it more frequently.  Any soil
type  can  meet  the  requirements of the
regulation when placed in a six-inch layer.

Approved States may allow demon-strations
of alternative daily cover materials. The rule
does  not  specify the time frame for the
demonstration; usually the State decides.  A
period of six months should be ample time for
the owner or operator to make the demonstra-
tion.  There are no numerical require-ments
for   the  alternative  cover;   rather,  the
alternative cover must control  disease vectors,
fires,  odors, blowing litter, and scavenging
without presenting a threat to human health
and the environment.

Demonstrations can be conducted in a variety
of ways.    Some suggested  methods for
demonstrating alternative covers are:
1)  Side  by  side  (six inches  of earthen
    materials and alternative cover) test pads;

2)  Full-scale demonstration; and

3)  Short-term full-scale tests.

Alternative daily cover materials may include
indigenous   materials  or   commercially-
available materials.  Indigenous materials are
those materials that would  be  disposed as
waste; therefore, using these materials is an
efficient use of landfill space. Examples of
indigenous materials include (USEPA, 1992):

    •   Ash   from    municipal   waste
        combustors and utility companies;

    •   Compost-based material;

    •   Foundry    sand     from     the
        manufacturing process of discarding
        used dies;

    •   Yard waste such as lawn clippings,
        leaves, and tree branches;

    •   Sludge-based materials (i.e., sludge
        treated with lime and mixed with ash
        or soil);

    •   Construction and demolition debris
        (which has been processed to form a
        slurry);

    •   Shredded automobile tires;
        Discarded carpets; and

        Grit  from  municipal   wastewater
        treatment plants.
                                           85

-------
                                       Subpart C
Commercially developed  alternatives have
been  on the market  since the mid-1980s.
Some of the commercial alternative materials
require   specially   designed  application
equipment,  while  others  use  equipment
generally available at most landfills.  Some of
the types of commercially  available daily
cover materials include (USEPA, 1992):

   •  Foam  that usually  is sprayed on  the
     working face at the end of the day;

   •  Geosynthetic products such as a tarp or
     fabric panel that is applied at the end of
     the working  day and removed at  the
     beginning  of the  following  working
     day; and

   •  Slurry  products (e.g.,  fibers  from
     recycled newspaper and wood chip
     slurry, clay slurry).

Other criteria to consider when selecting an
alternative  daily  cover   material   include
availability  and  suitability of the material,
equipment requirements, and cost.

The temporary climatic waiver of the cover
requirement is available  only  to owners or
operators in approved States.  The  State
Director may grant a waiver if the owner or
operator  demonstrates  that  meeting   the
requirements would  be  impractical due to
extreme   seasonal   climatic  conditions.
Activities that may be affected by extreme
seasonal climatic conditions include:

•  Obtaining cover soil from a borrow pit;

•  Transporting  cover soil to the  working
   face; or
•   Spreading and  compacting the soil to
    achieve the required functions.

Extremely cold conditions may prevent the
efficient excavation of soil from a borrow pit
or the spreading and compaction of the soil on
the  waste.  Extremely wet conditions (e.g.,
prolonged rainfall,  flooding)  may  prevent
transporting cover soil to the working face
and may make it impractical to excavate or
spread and compact.  The duration of waivers
may be as short as one day for unusual rain
storms, or as long as several months for
extreme seasonal climatic conditions.
3.4 DISEASE VECTOR CONTROL
    40 CFR §258.22

3.4.1  Statement of Regulation

    (a)   Owners or  operators  of  all
MSWLF units must prevent or control on-
site populations  of disease vectors using
techniques appropriate for the protection
of human health  and the environment.

    (b)   For  purposes  of this  section,
disease vectors means any rodents, flies,
mosquitoes,  or  other animals, including
insects, capable of transmitting disease to
humans.

3.4.2  Applicability

The regulation applies to existing MSWLF
units, lateral  expansions,  and new MSWLF
units.  The owner or operator is required to
prevent or control on-site  disease  vector
populations of rodents, flies, mosquitoes, or
other animals, including other insects.  The
techniques that may be used in fulfilling this
requirement  must be  appropriate for  the
                                           86

-------
                                    Operating Criteria
protection   of  human   health   and  the
environment.

3.4.3  Technical Considerations

Disease vectors such as rodents, birds, flies,
and mosquitoes typically  are  attracted  by
putrescent waste and standing water,  which
act as a food source  and breeding ground.
Putrescent waste is solid waste that contains
organic matter (such as food waste) capable of
being decomposed by  micro-organisms.  A
MSWLF facility typically accepts putrescent
wastes.

Application  of cover  at the end  of each
operating day generally is sufficient to control
disease vectors; however, other vector control
alternatives   may   be  required.     These
alternatives could include:  reducing the size
of  the working  face;  other  operational
modifications   (e.g.,    increasing   cover
thickness,  changing  cover  type,  density,
placement frequency, and grading); repellents,
insecticides  or rodenticides;  composting or
processing of organic wastes prior to disposal;
and predatory  or  reproductive control  of
insect,  bird,  and  animal   populations.
Additional  methods to  control  birds  are
discussed in Chapter 2 (Airport Safety).

Mosquitoes,  for example,  are  attracted  by
standing water found at MSWLFs, which can
provide a potential breeding ground after only
three  days.   Water  generally  collects  in
surface depressions, open containers, exposed
tires,  ponds resulting from soil excavation,
leachate storage ponds, and siltation basins.
Landfill  operations that  minimize  standing
water and that use an insecticide  spraying
program ordinarily  are effective in controlling
mosquitoes.
Vectors may reach the landfill  facility not
only from areas adjacent to the landfill, but
through other modes conducive to harborage
and breeding of disease vectors. Such modes
may include residential and commercial route
collection  vehicles  and  transfer  stations.
These transport modes and areas also should
be  included in the  disease  vector control
program if disease  vectors  at the landfill
facility  become a problem.  Keeping the
collection  vehicles  and  transfer  stations
covered; emptying and cleaning the collection
vehicles and transfer stations; using repellents,
insecticides, or rodenticides; and reproductive
control are all measures available to reduce
disease vectors in these areas.
3.5 EXPLOSIVE GASES CONTROL
     40 CFR §258.23

3.5.1  Statement of Regulation

    (a) Owners or operators of all MSWLF
units must ensure that:

    (1) The concentration of methane gas
generated by the facility does not exceed 25
percent of the  lower explosive limit for
methane  in facility structures  (excluding
gas    control   or   recovery   system
components); and

    (2) The concentration of methane gas
does not exceed the LEL for methane at the
facility property boundary.

    (b) Owners or operators of all MSWLF
units must implement a routine methane
monitoring program to ensure that the
standards of paragraph (a) of this section
are met.
                                           87

-------
                                      Subpart C
   (1)   The   type   and   frequency   of
monitoring must be determined based on
the following factors:

        (i) Soil conditions;

        (ii) The hydrogeologic conditions
        surrounding the facility;

        (iii)  The  hydraulic  conditions
        surrounding the facility; and

        (iv)  The  location   of  facility
        structures      and     property
        boundaries.

   (2)   The   minimum   frequency   of
monitoring shall be quarterly.

   (c) If methane gas levels exceeding the
limits specified in  paragraph  (a) of this
section are detected, the owner or operator
must:

   (1) Immediately take all necessary steps
to ensure protection of human health and
notify the State Director;

   (2) Within seven days of detection, place
in the operating record the  methane gas
levels detected and a description  of the
steps taken to protect human health; and

   (3)  Within  60  days of  detection,
implement a  remediation plan for the
methane gas releases, place a copy of the
plan in the operating record, and notify the
State Director that  the  plan has been
implemented.  The plan shall describe the
nature and extent of the problem and the
proposed remedy.
    (4) The Director of an approved State
may  establish alternative schedules  for
demonstrating compliance with paragraphs
(2) and (3).

    (d) For purposes of this section, lower
explosive  limit (LEL) means  the  lowest
percent by volume of a mixture of explosive
gases in air that will propagate a flame at
25°C and atmospheric pressure.

3.5.2  Applicability

The regulation applies to existing MSWLF
units, lateral expansions, and new MSWLF
units.    The accumulation of methane  in
MSWLF structures can potentially result in
fire  and  explosions  that can  endanger
employees, users  of the disposal  site, and
occupants of  nearby  structures,  or  cause
damage to landfill  containment structures.
These  hazards  are preventable through
monitoring and  through  corrective  action
should methane gas levels exceed specified
limits in the facility structures (excluding gas
control or recovery system components), or at
the  facility property boundary.   MSWLF
facility owners and operators  must comply
with the following requirements:

•   Monitor at least quarterly;

•   Take immediate steps  to protect  human
    health in the event of methane gas levels
    exceeding 25% of the lower explosive
    limit (LEL) in facility structures, such as
    evacuating the building;

•   Notify the State  Director  if methane
    levels exceed 25% of the LEL in facility
    structures  or exceed  the  LEL  at  the
    facility property boundary;
                                          88

-------
                                    Operating Criteria
•  Within 7 days of detection, place in the
   operating   record   documentation  that
   methane gas concentrations exceeded the
   criteria,  along  with  a  description  of
   immediate actions taken to protect human
   health; and

•  Within 60 days of detection, implement a
   remediation plan for the  methane gas
   releases,  notify the State Director, and
   place a copy of the remediation plan in the
   operating record.

The compliance schedule for monitoring and
responding to methane levels that exceed the
criteria of this regulation can be changed by
the Director of an approved State.

3.5.3  Technical Considerations

To implement an appropriate routine methane
monitoring    program    to    demonstrate
compliance    with   allowable   methane
concentrations, the characteristics of landfill
gas production and migration at a site should
be understood. Landfill gases are the result of
microbial decomposition of  solid  waste.
Gases  produced  include methane  (CH4),
carbon dioxide (CO2), and lesser amounts of
other gases (e.g., hydrogen, volatile organic
compounds, and hydrogen sulfide).  Methane
gas, the principal component of natural gas, is
generally the primary concern in evaluating
landfill gas generation because it is odorless
and highly combustible. Typically,  hydrogen
gas is present at much lower concentra-tions.
Hydrogen forms as decomposition progresses
from  the  acid  production  phase  to the
methanogenic phase.   While  hydrogen is
explosive and is occasionally  detected in
landfill gas, it readily reacts to form methane
or hydrogen  sulfide.   Hydrogen  sulfide is
toxic and is
readily identified by its "rotten egg" smell at
a threshold concentration near 5 ppb.

Landfill  gas production rates vary  spatially
within a landfill unit as a result of pockets of
elevated microbial activity but, due to partial
pressure   gradients,  differences  in  gas
composition  are  reduced   as  the  gases
commingle within  and  outside  the landfill
unit. Although methane gas is lighter than air
and carbon dioxide is heavier, these gases are
concurrently produced at the microbial level
and  will  not  separate  by  their individual
density.  The gases will remain mixed and
will migrate according to the density gradients
between the landfill gas and the surrounding
gases (i.e., a mixture of methane and carbon
dioxide in a landfill unit or in  surrounding soil
will  not  separate  by  rising and  sinking
respectively, but will migrate as a mass  in
accordance with the density of the mixture
and other gradients such as  temperature and
partial pressure).

When   undergoing  vigorous   microbial
production, gas  pressures on  the order of 1 to
3 inches of water relative  to  atmospheric
pressure are common at landfill facilities, with
much higher pressures occasionally reported.
A barometric pressure change of 2 inches of
mercury is equivalent to 27.2 inches of water.
Relative  gauge pressures  at  a particular
landfill unit or  portion of a  landfill  unit, the
ability of site  conditions to contain landfill
gas, barometric pressure variations, and the
microbial  gas  production  rate   control
pressure-induced  landfill   gas   migration.
Negative   gas   pressures   are   commonly
observed and are believed to  occur as a result
of the delayed response within a landfill unit
to the passage of a  high pressure system
outside the landfill unit.  Barometric highs
will  tend to introduce atmospheric oxygen
into surface soils in
                                            89

-------
                                        Subpart C
shallow portions of the landfill unit, which
may  alter microbial  activity, particularly
methane production and gas composition.

Migration  of  landfill  gas  is  caused  by
concentration gradients, pressure gradients,
and density gradients. The direction in which
landfill gas will migrate is  controlled by the
driving gradients and gas permeability of the
porous material through which it is migrating.
Generally, landfill gas will migrate through
the path of least resistance.

Coarse, porous soils such as sand and gravel
will   allow greater  lateral  migration  or
transport  of gases than finer-grained soils.
Generally, resistance  to landfill gas  flow
increases  as moisture content increases and,
therefore,  an effective barrier to gas flow can
be created under saturated conditions.  Thus,
readily drained soil conditions, such as sands
and  gravels  above  the water  table,  may
provide a preferred flowpath, but unless finer-
grained soils are fully saturated, landfill gases
also can migrate in a "semi-saturated" zone.
Figure 3-2 illustrates the potential effects of
surrounding geology on gas migration.

While geomembranes  may  not eliminate
landfill gas migration, landfill gas in a closed
MSWLF unit will tend to migrate laterally if
the final cover contains a geomembrane and if
the side slopes of the landfill do not contain
an effective gas barrier.  Lateral gas migration
is  more common in older facilities that lack
appropriate gas control systems.  The degree
of lateral migration in older facilities also may
depend  on  the  type  of  natural   soils
surrounding the facility.
Stressed   vegetation   may  indicate   gas
migration.  Landfill gas present in the soil
atmosphere tends to make the soil anaerobic
by    displacing   the   oxygen,   thereby
asphyxiating the roots of plants. Generally,
the higher the concentration of combustible
gas and/or carbon dioxide and the lower the
amount of oxygen,  the greater the extent of
damage to vegetation (Flowers, et. al, 1982).

Gas Monitoring

The  owner  or  operator  of  a  MSWLF
unit/facility   must  implement  a  routine
methane monitoring program to comply with
the lower explosive limit (LEL) requirements
for methane.   Methane  is explosive when
present in the range of 5 to 15 percent by
volume  in  air.  When present in air at
concentrations  greater than 15 percent, the
mixture will not  explode.  This 15 percent
threshold is the  Upper Explosive  Limit
(UEL).    The  UEL  is  the  maximum
concentration of a gas or vapor above which
the substance will not explode when exposed
to a source of ignition. The explosive hazard
range is between the LEL and the UEL.  Note,
however, that methane concentrations above
the UEL remain  a  significant concern; fire
and asphyxiation  can still occur at these
levels. In addition, even a minor dilution of
the methane by increased ventilation can bring
the mixture back into the explosive range.

To    demonstrate     compliance,    the
owner/operator would  sample air  within
facility structures  where gas may accumulate
and in soil at the property boundary.  Other
monitoring  methods   may   include:  (1)
sampling gases from probes within the landfill
unit or from within the  leachate collection
system; or (2) sampling gases
                                           90

-------
     Clay or Synthetic Cap
      (Low Permeability)
Clay Soil, Frozen or
Saturated Soil, or Pavement
(Low Permeability)

                                             Sand and Gravel Soil
                                              (High Permeability)
                   EXTENSIVE LATERAL MIGRATION
      Clay or Synthetic Liner
     ~ (Low Permeability)
Daily Cover
(High Permeability)
                                             Clay Soil
                                             (Low PermeabMBy)
                   EXTENSIVE VERTICAL MIGRATION
Source:  Emcon, 1981.
                            Figure 3-2
                       Potential Effects of
           Surrounding Geology on Gas Migration
                                 91

-------
                                        Subpart C
from  monitoring  probes installed  in  soil
between the  landfill  unit  and  either the
property boundary or  structures  where gas
migration may pose a danger.  A typical gas
monitoring probe  installation is depicted in
Figure 3-3.

Although not required by the regulations,
collection of data such as water presence and
level,   gas   probe    pressure,    ambient
temperature, barometric pressure,  and the
occurrence of precipitation during sampling,
provides useful  information  in  assessing
monitoring  results.   For example, falling
barometric  pressure may  cause  increased
subsurface (gas) pressures and corresponding
increased methane content as gas more readily
migrates from  the landfill.   Gas  probe
pressure can be measured using  a portable
gauge capable of measuring both vacuum and
pressure in the range of zero to five inches of
water pressure (or other suitable  ranges for
pressure conditions); this pressure should be
measured prior to  methane measurement or
sample collection  in  the gas probe.   A
representative   sample    of   formation
(subsurface) gases can be collected directly
from  the probe.   Purging typically is not
necessary due to  the small volume of the
probe.  A water  trap  is recommended to
protect instrumentation  that  is  connected
directly to the gas probe.  After measurements
are obtained, the gas probe should be capped
to reduce the effects of venting or barometric
pressure variations on gas composition in the
vicinity of the probe.

The  frequency  of monitoring  should  be
sufficient to detect landfill  gas  migration
based on subsurface conditions and changing
landfill conditions such as partial or complete
capping, landfill  expansion,  gas migration
control  system    operation   or   failure,
construction of new or replacement
structures, and changes in landscaping or land
use  practices.   The rate of  landfill gas
migration as a  result of these anticipated
changes  and the  site-specific  conditions
provides the basis for establishing monitoring
frequency. Monitoring is to be  conducted at
least quarterly.

The number and location of gas probes is also
site-specific  and   highly  dependent  on
subsurface conditions, land use, and location
and design of facility structures.  Monitoring
for gas migration should be within the  more
permeable strata. Multiple or nested probes
are   useful   in   defining  the  vertical
configuration of  the  migration  pathway.
Structures with basements or crawl spaces are
more susceptible to landfill gas infiltration.
Elevated structures are typically not at risk.

Measurements are usually made in the field
with a portable methane meter, explosimeter,
or organic vapor analyzer.  Gas  samples also
may be collected in glass or metal containers
for laboratory analysis.   Instruments  with
scales of measure in "percent of LEL" can be
calibrated and used to detect the presence of
methane.     Instruments  of the hot-wire
Wheatstone  bridge  type  (i.e.,  catalytic
combustion) directly measure combustibility
of the gas mixture withdrawn from the probe.
The  thermal  conductivity  type  meter is
susceptible to interference as the relative gas
composition  and,   therefore,   the  thermal
conductivity,  changes.   Field   instruments
should be calibrated prior to measurements
and  should be rechecked  after each  day's
monitoring activity.
                                           92

-------
                  Operating Criteria
Source:  Warzyn Inc.
                                   PVC caps with
                                   petcocks

                                   Protective casing
                                   with lock
                                   Bentonite soil seal

                                   Bentonite seal

                                   1 inch PVC pipe

                                   1/2 inch PVC pipe
                                   1 inch perforated
                                   PVC pipe
                                   Gravel backfill
                                   Bentonite seal


                                   Sand and gravel
                                   Probe screen
                    Figure 3-3
         Typical Gas Monitoring Probe
                         93

-------
                                        Subpart C
Laboratory measurements with organic vapor
analyzers or gas chromatographs may be used
to confirm the identity and concentrations of
gas.

In addition  to  measuring gas composition,
other indications of gas migration may be
observed.   These include odor  (generally
described as either a "sweet"  or a rotten egg
(H2S) odor), vegetation damage, septic soil,
and  audible or  visual  venting  of  gases,
especially in standing water.   Exposure to
some gases can cause headaches and nausea.

If methane concentrations are in excess of 25
percent of the LEL in facility structures or
exceed the LEL at the property boundary, the
danger of explosion is imminent. Immediate
action must be taken to protect human health
from potentially explosive conditions.  All
personnel should be evacuated from the area
immediately. Venting the building upon exit
(e.g., leaving the door open) is desirable but
should not replace evacuation procedures.

Owners and operators in unapproved States
have 60 days after exceeding the methane
level to prepare and implement a remediation
plan. The remediation plan should describe
the nature and extent of the methane problem
as well as a proposed remedy.

To  comply  with this  60-day schedule,  an
investigation of subsurface conditions may be
needed in the vicinity of the monitoring probe
where  the  criterion  was  exceeded.   The
objectives of this investigation  should be to
describe the frequency and lateral and vertical
extent  of excessive  methane migration (that
which  exceeds the  criterion).    Such  an
investigation  also   may  yield  additional
characterization of unsaturated
soil  within  the  area  of concern.    The
investigation should consider possible causes
of the increase in gas concentrations such as
landfill  operational procedures,  gas control
system failure or upset, climatic conditions, or
closure  activity.  Based on the extent and
nature of the excessive methane migration, a
remedial action should be described,  if the
exceedance  is   persistent,  that   can  be
implemented within the prescribed schedule.
The sixty-day schedule does not address the
protection   of  human  health   and  the
environment.   The owner or operator still
must  take all  steps  necessary  to ensure
protection of human health, including interim
measures.

Landfill Gas Control Systems

Landfill gas  may  vent  naturally or  be
purposely  vented to  the atmosphere  by
vertical  and/or lateral  migration  controls.
Systems used  to control or prevent gas
migration are categorized as either passive or
active  systems.  Passive  systems provide
preferential flowpaths  by means of natural
pressure, concentration,  and density gradients.
Passive  systems  are primarily effective in
controlling convective flow and have limited
success  controlling diffusive flow.  Active
systems  are effective in controlling both types
of flow.   Active systems use  mechanical
equipment to direct or control landfill gas by
providing  negative  or  positive   pressure
gradients.  Suitability of the systems is based
on the design and age of the landfill unit, and
on the  soil,  hydrogeologic,  and hydraulic
conditions  of the facility  and surrounding
environment.  Because of these variables, both
systems  have had varying degrees of success.

Passive systems may be used in  conjunction
with active systems.  An example of this
                                           94

-------
                                    Operating Criteria
may be the use of a low-permeability passive
system for the closed portion of a landfill unit
(for remedial purposes) and the installation of
an active system in the active portion of the
landfill unit (for future use).

Selection of construction materials for either
type of gas control system should consider the
elevated  temperature conditions within  a
landfill unit as compared to the ambient air or
soil conditions in which gas  control system
components  are  constructed.     Because
ambient conditions are typically cooler, water
containing corrosive and  possibly toxic waste
constituents may be expected to condense.
This  condensate  should be  considered  in
selecting construction materials. Provisions
for managing  this  condensate should  be
incorporated  to prevent accumulation and
possible failure of the collection system. The
condensate can be returned to the landfill unit
if the landfill  is designed with a composite
liner  and  leachate  collection system  per
§258.40(a)(2).  See Chapter 4 for information
regarding  design.  See Section 3.10 of this
Chapter for information regarding liquids in
landfills.

Additional provisions (under the Clean Air
Act) were  proposed on May 30, 1991 (56 FR
24468), that  would require the  owners/
operators of certain landfill facilities to install
gas collection and control systems to reduce
the  emissions  of   nonmethane  organic
compounds (NMOCs).   The proposed rule
amends 40 CFR Parts 51, 52, and  60. For
new municipal solid waste landfill units (those
for which  construction was begun after May
30, 1991), and for those units that have a
design capacity greater than 111,000 tons, a
gas collection and control system  must  be
installed if emissions evaluations indicate that
the NMOC emissions rate is
150 megagrams per year (167 tons per year)
or greater. Allowable control systems include
open and enclosed flares, and on-site or off-
site  facilities  that  process  the   gas  for
subsequent sale or use.  EPA believes that,
depending on landfill design, active collection
systems  may  be more  cost-effective than
passive systems in ensuring that the system
effectively captures the gas that is generated
within the landfill unit.  The provisions for
new landfill units are self-implementing and
will be effective  upon promulgation  of the
rule.

In addition to the emissions standards for new
municipal  solid  waste  landfill units,  the
regulations  proposed  on  May  30,  1991
establish guidelines  for State programs for
reducing  NMOC emissions  from  certain
existing  municipal  landfill  units.    These
provisions apply  to landfill units for  which
construction was commenced before May 30,
1991,  and that have accepted waste since
November 8,  1987 or that  have remaining
capacity.  Essentially, the State must require
the same kinds  of  collection and control
systems for landfill units that meet the  size
criteria and  emissions levels outlined  above
for new landfill units.  The requirements for
existing facilities will be effective  after the
State  revises its  State  Implementation Plan
and receives approval from EPA.

The rule is scheduled to be promulgated in
late 1993; the cutoff numbers for landfill  size
and emission quantity may be revised in the
final  rule.   EPA expects  that  the new
regulations will affect less  than 9%  of the
municipal landfill facilities in the U.S.
                                           95

-------
                                        Subpart C
Passive Systems

Passive gas control systems rely on natural
pressure and convection mechanisms to vent
landfill gas  to  the atmosphere.   Passive
systems typically use "high-permeability" or
"low-permeability"    techniques,     either
singularly or in combination at a site.  High-
permeability systems use conduits such as
ditches, trenches, vent wells,  or perforated
vent pipes surrounded by coarse soil to vent
landfill gas to the surface and the atmosphere.
Low-permeability   systems  block  lateral
migration through barriers such as synthetic
membranes  and  high  moisture-containing
fine-grained soils.

Passive systems  may be incorporated  into a
landfill design or may be used for remedial or
corrective purposes  at both closed and  active
landfills.  They  may be installed within a
landfill unit along the perimeter, or between
the landfill and the disposal facility property
boundary.  A detailed discussion of passive
systems for remedial or corrective purposes
may be found in  U.S. EPA (1985).

A passive system may be incorporated into
the final cover system of a landfill closure
design  and  may consist of perforated  gas
collection pipes, high permeability soils, or
high transmissivity geosynthetics located just
below the low-permeability gas and  hydraulic
barrier  or infiltration  layer in the  cover
system. These systems may be connected to
vent pipes that vent gas through the  cover
system or that are connected to header pipes
located along the perimeter of the landfill
unit. Figure 3-4  illustrates a passive system.
The landfill gas collection system also may be
connected with the leachate collection system
to vent gases in the headspace of leachate
collection pipes.
Some problems have been  associated with
passive systems. For example, snow and dirt
may accumulate in vent pipes, preventing gas
from venting.  Vent pipes
at the surface are susceptible to clogging by
vandalism.  Biological clogging of the system
is also more common in passive systems.

Active Systems

Active gas control  systems  use mechanical
means to remove landfill gas and consist of
either positive pressure (air injection)  or
negative  pressure   (extraction)  systems.
Positive pressure systems induce a pressure
greater than the pressure of the migrating gas
and drive the gas out of the soil and/or back to
the landfill unit in a  controlled manner.
Negative pressure systems extract gas from a
landfill by  using a blower to pull gas out of
the landfill. Negative  pressure systems are
more commonly used because they are more
effective  and  offer  more  flexibility  in
controlling gas migration.  The gas may be
recovered for energy conversion, treated, or
combusted  in  a flare system.    Typical
components of a flare  system are shown in
Figure 3-5.  Negative pressure systems may
be  used as  either  perimeter  gas  control
systems or interior  gas collection/recovery
systems.  For  more information regarding
negative pressure gas control systems, refer to
U.S. EPA (1985).

An active gas extraction well is depicted in
Figure 3-6.  Gas extraction wells may be
installed within the landfill  waste  or,  as
depicted in Figure  3-7A and Figure 3-7B,
perimeter extraction trenches could be used.
One possible configuration of an interior gas
collection/recovery system is illustrated in
                                           96

-------
       Operating Criteria
           Gas Vent
         Figure 3-4
Passive Gas Control System
  (Venting to Atmosphere)
                                        Top Layer

                                        Low-Permeability Laye

                                        Vent Layer

                                        Waste
             97

-------
                           Subpart C
                                  77T—Waste Gas
                                      Inlet Valve
   Concrete Base
                                 Gas From
                                 Landfill
Source; E.G. Jordan Co., 1990.
        Figure 3-5. Example Schematic Diagram of a
              Ground-based Landfill Gas Flare
                              98

-------
             48" Corr. Steel Pipe
             w/ Hinged Lid

             Backfill, Compact by
             Hand in 6" Layers

             Exist Ground Elev
                                                                       Butterfly Valve

                                                                       Monitoring Port
Header with 3"
Dia. Branch Saddle

Kanaflex PVC Hose
Source CH,H Hill. 1992
                                                                                              3'-0"
4" Dia Sch 80 PVC
Solid Pipe
Soil Backfill	
                                                           *-
                                                                        T
                                                                          Varies
                                   Bentonite/Soil Seal
                                   4" Dia Sch 80 PVC
                                   Slotted Pipe
                                     Gravel Backfill
                                                                            2'-C'
                                                                             12"
                                                                                   Slotted Length
                                                                                       Varies
                                                                                     (2/3 Landfill
                                                                                       Depth)
                                     4" Sch 80 PVC Cap-
                                                                         Slotted Length
                                                                             Varies
                                                                         (1/2 Well Depth)
                                                                               !

                                                                               I
                                                           1  24" Dia
                                                           1—	M
                                                           i   Bore   i
                 Figure 3-6 Example of a Gas Extraction Well
                                              99

-------
                   - Geotextile
                                    Existing Cover
Existing Cover
                                        • Refuse
                                                Washed Gravel
                                               Oo
   Sourca: Swana. 1991

             Bottom of Trench Excavation
Figure 3-7A.  Perimeter Extraction Trench System
                                                     Quick Connect
                                                     Coupling
                     Flexible Hose
              Butterfly Valve
      Source: Swana, 1991
             Washed Gravel
                                                            Ground Surface
                                                         Clean Soil Backfill
                                                          HOPE Pipe
Figure 3-7B. Perimeter Extraction Trench System
                                     100

-------
                                    Operating Criteria
Figure  3-8.   The  performance  of active
systems is not as sensitive to freezing or
saturation of cover  soils as that of passive
systems.  Although active  gas  systems  are
more effective in withdrawing gas from  the
landfill, capital, operation, and maintenance
costs of such systems will be higher and these
costs can be expected to continue throughout
the post-closure period.  At some future time,
owners and operators may  wish to convert
active gas controls into passive systems when
gas production diminishes.  The conversion
option and its environmental effect (i.e., gas
release causing odors and health and safety
concerns) should be addressed in the original
design.

There are many benefits to recovering landfill
gas. Landfill gas recovery systems can reduce
landfill  gas odor and migration, can reduce
the danger of explosion and fire, and may be
used as a source of revenue that may help to
reduce the cost of closure.  Landfill gas can be
used with a minimal amount of treatment or
can  be  upgraded  to  pipeline  standards
(SWANA, 1992).  An upgraded gas is one
which has  had the carbon dioxide and other
noncombustible constituents removed.

Raw landfill gas may be used for heating
small facilities  and water, and may require
removal of only water and particulates for this
application. A slightly upgraded gas can be
used for both water and space heating as well
as    lighting,     electrical    generation,
cogeneration, and as a  fuel for  industrial
boilers-burners.   Landfill gas also  may be
processed to pipeline quality to be sold to
utility companies and may  even be used to
fuel  conventional vehicles. The amount of
upgrading and use of landfill  gas is  dependent
on the landfill size.
3.6 AIR CRITERIA
    40 CFR §258.24

3.6.1  Statement of Regulation

    (a)  Owners  or   operators  of  all
MSWLFs must ensure that the units do not
violate   any   applicable   requirements
developed under a State Implementation
Plan (SIP) approved or promulgated by the
Administrator pursuant to section 110 of
the Clean Air Act, as amended.

    (b) Open burning of solid waste, except
for the infrequent burning of agricultural
wastes, silvicultural wastes, land-clearing
debris,  diseased trees, or  debris   from
emergency    clean-up    operations,   is
prohibited at all MSWLF units.

3.6.2  Applicability

The regulation applies to existing MSWLF
units, lateral expansions to existing MSWLF
units, and new MSWLF units. Routine open
burning   of   municipal   solid  waste   is
prohibited. Infrequent burning of agricultural
and silvicultural wastes, diseased trees, or
debris from land clearing or emergency clean-
up operations is allowed when in compliance
with any applicable requirements developed
under a State Implementation Plan (SIP) of
the Clean Air Act.  Agricultural waste does
not include empty  pesticide containers or
waste pesticides.

3.6.3  Technical Considerations

Air  pollution  control   requirements  are
developed under a SIP, which is developed by
the  State and  approved  by  the  EPA
Administrator. The owner or operator of a
                                          101

-------
                                                          Gas
                                                          Treatment/Processing
                                                          Facility
Source: Emcon, 1981
                                      Figure 3-8

               Example of an Interior Gas Collection/Recovery System
                                          102

-------
                                    Operating Criteria
MSWLF unit should consult the State or local
agency responsible for air pollution control to
ascertain that the burning of wastes complies
with applicable requirements developed under
the SIP.  The  SIP may include variances,
permits,  or   exemptions   for   burning
agricultural wastes, silvicultural wastes, land-
clearing debris, diseased trees, or debris from
emergency  clean-up  operations.    Routine
burning of wastes is banned in all cases, and
the SIP may limit burning of waste such as
agricultural wastes to certain hours of the day;
days  of the year; designated burn  areas;
specific types of incinerators;  atmospheric
conditions; and distance from working face,
public   thoroughfares,   buildings,    and
residences.

Requirements under the SIP also may include
notifying applicable State or local agencies
whose permits may: (1) restrict times when
limited burning of waste may occur;  (2)
specify periods when sufficient fire protection
is deemed to be available; or (3) limit burning
to  certain areas.

Open burning is defined under §258.2 as the
combustion  of solid waste:   (1)  without
control  of  combustion  air to  maintain
adequate    temperature    for    efficient
combustion; (2) without containment of the
combustion reaction in an enclosed device to
provide sufficient residence time and mixing
for complete combustion; and (3) without the
control of the  emission of the combustion
products.   Trench  or  pit burners,  and air
curtain  destructors  are  considered open
burning   units  because   the  particulate
emissions are similar to particulate emissions
from open burning,
and these devices do not control the emission
of combustion products.
[Note: The Agency plans to issue regulations
under the Clean Air Act to control landfill gas
emissions from large MSWLF units in 1993.
These regulations are found at 40 CFR Parts
51, 52, and 60.]
3.7 ACCESS REQUIREMENT
    40 CFR §258.25

3.7.1  Statement of Regulation

Owners or operators of all MSWLF units
must control public access  and prevent
unauthorized vehicular traffic and illegal
dumping  of  wastes  by  using artificial
barriers,  natural  barriers,  or both,  as
appropriate to protect human health and
the environment.

3.7.2  Applicability

The regulation applies to existing MSWLF
units, lateral expansions, and new MSWLF
units.  The owner or operator is required to
prevent public access to the landfill facility,
except under  controlled conditions  during
hours when wastes are being received.

3.7.3  Technical Considerations

Owners and operators are required to control
public access to prevent illegal dumping,
public exposures to hazards at MSWLF units,
and   unauthorized   vehicular    traffic.
Frequently,   unauthorized   persons   are
unfamiliar with the hazards associated with
landfill facilities,   and  consequences  of
uncontrolled access may include injury and
even death.  Potential hazards are related to
inability  of equipment  operators   to  see
unauthorized individuals during operation of
equipment and haul vehicles; direct exposure
to waste (e.g., sharp objects and pathogens);
                                           103

-------
                                       Subpart C
inadvertent  or  deliberate  fires;  and earth-
moving activities.

Acceptable measures used to limit access of
unauthorized persons to the disposal facility
include gates and fences, trees, hedges, berms,
ditches,  and embankments.   Chain link,
barbed wire added to chain link, and open
farm-type fencing are examples  of fencing
that may be used. Access to facilities should
be controlled through gates that can be locked
when the site is unsupervised. Gates may be
the only additional measure needed at remote
facilities.
3.8  RUN-ON/RUN-OFF
   CONTROL SYSTEMS
   40 CFR §258.26

3.8.1  Statement of Regulation

   (a) Owners or operators of all MSWLF
units must design, construct, and maintain:

   (1) A run-on control system to prevent
flow onto the active portion of the landfill
during the peak discharge from a 25-year
storm;

   (2) A run-off control system  from the
active portion of the landfill to collect and
control at least the water volume resulting
from a 24-hour, 25-year storm.

   (b) Run-off from the active portion of
the  landfill unit  must  be  handled in
accordance with §258.27(a) of this Part.
3.8.2  Applicability

The regulation applies to existing MSWLF
units, lateral expansions, and new MSWLF
units.  The owner or operator is required to
prevent run-on onto the active portion of the
landfill units and to collect and control run-off
from the active portion for a 24-hour, 25-year
storm. Management of run-off must comply
with the point and non-point source discharge
requirements of the Clean Water Act.

3.8.3  Technical Considerations

If stormwater  enters  the landfill unit and
contacts waste (including water within daily
cover), the stormwater becomes leachate and
must be managed as leachate.  The purpose of
a run-on control system is to collect and
redirect  surface waters to minimize  the
amount of surface water entering the landfill
unit. Run-on control can be accomplished by
constructing berms and swales  above  the
filling area that will collect and redirect the
water to stormwater control structures.

As  stated above, stormwater that does enter
the landfill unit  should  be  managed  as
leachate.    Run-off  control  systems  are
designed to collect  and control this run-off
from  the active portion of  the  landfill,
including  run-off  from areas  that  have
received  daily  cover,  which may  have
contacted waste materials.  Run-off control
can be accomplished through stormwater
conveyance structures that  divert this run-
off/1 eachate to the leachate storage device.

After a landfill unit has been closed with a
final cover, stormwater run-off from this unit
can  be managed  as stormwater  and  not
leachate. Therefore, waters  running off the
final  cover system of closed areas may  not
                                          104

-------
                                   Operating Criteria
require  treatment and  generally  can  be
combined with run-on waters.  For landfills
with steep side slopes, a bench system may
provide the best solution for run-off control.
A bench creates a break in the slope where the
velocity of the stormwater run-off is expected
to become erosive.  The bench converts sheet
flow run-off into  channel  flow.   Benches
typically are spaced 30 to 50 feet apart up the
slope.  An alternative to benches is a system
of  downchutes   whereby   stormwater  is
collected  off  the  top  of the  landfill  and
conveyed down the slope through a pipe or
channel.   Caution should be  taken  not to
construct downchutes with heavy  material
because of possible subsidence. Corrugated
metal pipes or  plastic-lined  channels are
examples of lightweight materials that  can be
used for downchute construction.

Run-on and run-off must  be  managed in
accordance with the requirements of the Clean
Water Act including, but not limited  to, the
National Pollutant  Discharge Elimination
System (NPDES). [See Section  3.9  of this
chapter for further information on compliance
with the Clean Water Act.]

Run-on and run-off control  systems must be
designed based on a 24-hour, 25-year  storm.
Information on the 24-hour, 25-year recurring
storm can be obtained from Technical Paper
40 "Rainfall Frequency Atlas of the United
States for Durations from 30 Minutes to 24
Hours  and Return Periods from  1 to  100
Years", prepared by the Weather Bureau
under   the  Department   of  Commerce.
Alternatively,  local meteorological  data can
be analyzed to estimate the criterion  storm.
To  estimate  run-on,  the local  watershed
should  be  identified  and  evaluated  to
document the basis for run-on design flows.
The Soil Conservation Service (SCS) Method
and/or the Rational  Method  are  generally
adequate  for  estimating  storm  flows for
designing  run-on  and/or  run-off  control
systems.  The SCS method estimates run-off
volume from accumulated rainfall and then
applies the run-off volume to a simplified
triangular unit hydrograph for peak discharge
estimation and total run-off hydrograph. A
discussion of the development and use of this
method  is  available   from  the  U.  S.
Department of Agriculture, Soil Conservation
Service (1986).

The  Rational  Method  approximates  the
majority of surface water discharge supplied
by the watershed upstream from the facility.
The Rational Method generally is used for
areas of less than 200 acres. A discussion of
the Rational Method may be found  in U.S.
EPA (1988).

Run-on/run-off  control   structures,  both
temporary   and   permanent,   may   be
incorporated into the system design.  Other
structures  (not  mentioned  above)  most
frequently used for run-on/run-off control are
waterways, seepage ditches, seepage basins,
and sedimentation basins.  U.S. EPA (1985)
provides  an in-depth discussion for  each of
these structures.
3.9 SURFACE WATER
    REQUIREMENTS
    40 CFR §258.27

3.9.1  Statement of Regulation

MSWLF units shall not:

    (a) Cause a discharge of pollutants into
waters  of the United States, including
                                          105

-------
                                        Subpart C
wetlands, that violates any requirements of
the Clean Water Act, including, but not
limited to, the National Pollutant Discharge
Elimination      System     (NPDES)
requirements, pursuant to section 402.

   (b) Cause the discharge of a nonpoint
source of pollution to waters of the United
States, including wetlands, that violates
any requirement of an area-wide or State-
wide  water quality management plan that
has been approved under section 208 or
319 of the Clean Water Act, as amended.

3.9.2  Applicability

The regulation applies to existing MSWLF
units, lateral expansions, and new MSWLF
units.  The owner or operator is required to
comply with the Clean Water Act  for any
discharges to surface water or wetlands.

3.9.3  Technical Considerations

The owner or operator of a MSWLF facility
should  determine  if the  facility  is  in
conformance with applicable requirements of
water quality plans developed under Sections
208 and 319 of the Clean Water Act, and the
National Pollutant  Discharge  Elimination
System (NPDES) requirements under Section
402 of the Clean Water Act.  The EPA and
approved   States  have  jurisdiction   over
discharge of pollutants  (other than dredge and
fill materials) in waters of the United States
including   wetlands.      MSWLF    units
discharging pollutants or disposing  of fill
material  into  waters  of the United States
require a  Section  402  (NPDES)  permit.
Discharge  of  dredge  and fill material into
waters of  the United States is  under the
jurisdiction of the U.S. Army  Corps  of
Engineers.
A MSWLF unit(s) that has a point source
discharge must have a NPDES permit.  Point
source discharges for landfills include, but are
not limited to:   (1) the release of leachate
from a leachate collection or on-site treatment
system into the waters  of the United States;
(2) disposal of solid waste into waters of the
United States; or (3) release of surface water
(stormwater) run-off which is  directed by a
run-off control system into the waters  of the
United  States.   Leachate that is piped  or
trucked off-site to a treatment  facility is not
regarded as a point source discharge.

The  Clean Water Act  (CWA)  provides
clarifications of terms such as  point source,
waters of the United States, pollutants, and
discharge of pollutants.

Owners/operators also  should be aware that
there are regulations promulgated pursuant to
the CWA regarding stormwater discharges
from  landfill facilities.  These regulations
require    stormwater   discharge    permit
applications  to  be  submitted by  certain
landfills that accept or have accepted specific
types  of industrial waste.  See 40 CFR Section
122.26(a)-(c), which originally appeared in
the Federal Register on November 16, 1990
(55 FR 47990).

In addition, EPA codified several provisions
pursuant   to  the   Intermodal    Surface
Transportation Efficiency Act of 1991 into the
NPDES regulations.  These regulations only
affect the  deadlines for submitting  permit
applications for stormwater  discharges, and
they apply to both uncontrolled and controlled
sanitary landfills.   "Uncontrolled  sanitary
landfills"  are defined  as  landfills or open
dumps that do not meet the requirements for
run-on or run-off controls that are found in
the
                                           106

-------
                                   Operating Criteria
MSWLF    Criteria,    Section    258.25.
"Controlled sanitary landfills" are those that
do meet the run-on and run-off requirements.
The   NPDES  regulations   specify  that
uncontrolled  sanitary  landfills owned  or
operated by municipalities   of  less than
100,000 (population) must submit a NPDES
permit  application  for  their stormwater
discharge or obtain coverage under a general
permit.   For controlled sanitary landfills
owned or operated by  a municipality with a
population  less than  100,000, there  is no
requirement to submit a stormwater discharge
permit application (before October 1,  1992)
unless a permit is required  under Section
402(p)(2)(A) or (E) of the Clean Water Act.
Other deadlines are set for municipalities with
a population less than 250,000 that own or
operate a municipal landfill.  For further
information  contact the Stormwater Hotline
(703)  821-4823.   See the April 2, 1992
Federal Register (57 FR 11394), 40 CFR
122.26.
3.10 LIQUIDS RESTRICTIONS
     40 CFR §258.28

3.10.1  Statement of Regulation

   (a)  Bulk or noncontainerized  liquid
waste may not be placed in MSWLF units
unless:

   (1) The waste is household waste other
than septic waste; or

   (2)  The waste  is  leachate or  gas
condensate derived from the MSWLF unit
and the MSWLF unit, whether it is an
existing  or new unit,  is designed with a
composite liner and  leachate  collection
system as described in §258.40 (a)(2) of
this  part.  The owner  or operator must
place the demonstration in the operating
record and notify the State Director that it
has been placed in the operating record.

    (b) Containers holding liquid waste
may  not be placed  in  a MSWLF  unit
unless:

    (1) The  container is a small container
similar in size  to that normally found in
household waste;

    (2) The container is designed to hold
liquids for use other than storage; or

    (3) The waste is household waste.

    (c) For purposes of this section:

    (1) Liquid  waste means any waste
material  that  is determined to  contain
"free liquids" as defined by Method 9095
(Paint Filter Liquids Test), as described in
"Test  Methods for Evaluating  Solid
Wastes, Physical/Chemical Methods" (EPA
Pub. No. SW-846).

    (2) Gas condensate means the liquid
generated as a result  of gas recovery
process(es) at the MSWLF unit.

3.10.2 Applicability

The regulation applies to new MSWLF units,
existing MSWLF units,  and lateral expansions
of existing MSWLF units.   The owner or
operator  is prohibited  from placing bulk or
non-containerized   liquid   waste,   or
containerized liquid waste into the MSWLF
unit.  Liquids from households are exempt.
Tank trucks of wastes are not exempt.
                                         107

-------
                                        Subpart C
3.10.3 Technical Considerations

The restriction  of bulk  or  containerized
liquids is intended to control  a source of
liquids that may become a source of leachate.
Liquid waste refers to any waste material that
is  determined to contain free liquids as
defined by SW-846 (U.S. EPA, 1987) Method
9095  - Paint Filter Liquids Test.  The paint
filter  test is performed by placing a  100
milliliter sample of waste in a conical,  400
micron paint filter.  The waste is considered a
liquid waste if any  liquid from the waste
passes through the filter within five minutes.
The apparatus used for performing the paint
filter test is illustrated in Figure 3-9.

If the waste is considered  a  liquid waste,
absorbent materials may be added to render a
"solid" material (i.e., waste/absorbent mixture
that no longer fails  the paint filter liquids
test).  One common waste stream that may
contain a significant quantity  of liquid is
sludge.   Sludge is a  mixture  of water  and
solids that has been concentrated from,  and
produced  during, water   and  wastewater
treatment.   Sludges may  be produced as a
result of providing municipal services (e.g.,
potable water supply, sewage treatment, storm
drain   maintenance)   or   commercial   or
industrial  operations.   Sewage sludge is a
mixture of organic and inorganic solids and
water, removed from wastewater containing
domestic  sewage.     Sludge   disposal  is
acceptable provided the sludge passes the
paint filter test.

[NOTE:    Additional Federal  regulations
restricting the use and disposal of sewage
sludge were published on February 19, 1993
in the Federal Register (58 FR 9248). These
regulations,   however,  do not  establish
additional  treatment  standards  or  other
special management requirements for sewage
sludge that is codisposed with solid waste.]

Owners and operators of MSWLF units may
return leachate and gas condensate generated
from a gas recovery process to the MSWLF,
provided the MSWLF unit has been designed
and constructed with a  composite  liner and
leachate collection system in compliance with
40 CFR §258.40(a)(2). Approved States may
allow leachate  and landfill gas condensate
recirculation in MSWLF units with alternative
designs.

Recirculating   leachate  or   landfill   gas
concentrate  may require demonstrating  that
the added volume of liquid will not increase
the depth of leachate on the liner to more than
30cm.

Returning gas condensate to the landfill  unit
may represent a reasonable long-term solution
for relatively small volumes of condensate.
Gas   condensate   recirculation   can   be
accomplished by pumping the  condensate
through pump  stations  at the gas  recovery
system and into dedicated drain fields (buried
pipe) atop the landfill, or into other discharge
points (e.g.,  wells).
Because gas condensate may  be  odorous,
spray systems for recirculation are not used
unless  combined with leachate recirculation
systems.

Leachate recirculation to a MSWLF unit has
been used as a measure for managing leachate
or as a means of controlling  and managing
liquid   and  solid   waste   decomposition.
Leachate recirculation can be accomplished in
the same manner as recirculation of landfill
gas condensate.    Because  of the  larger
volume, however, discharge points may not
be as effective as drainfields.  In some cases,
discharge points
                                           108

-------
            Operating Criteria
                                        Paint Filter
      Ring Stand
                 Funnel
                                   •Graduated Cylinder
Figure 3-9. Paint Filter Test Apparatus
                   109

-------
                                      Subpart C
have been a source of odor.  In addition, a
discharge point may not allow for dissipation
of the leachate. (For additional information
regarding the effectiveness of using leachate
recirculation to enhance the rate of organic
degradation,  see  (Reinhart  and   Carson,
1993).)
3.11 RECORDKEEPING
     REQUIREMENTS
     40 CFR §258.29

3.11.1  Statement of Regulation

   (a)   The  owner  or operator  of  a
MSWLF unit must record and retain near
the facility in an operating record, or in an
alternative  location  approved  by  the
Director of an approved state, the following
information as it becomes available:

   (1)    Any     location    restriction
demonstration required under Subpart B
of this part;

   (2)   Inspection   records,   training
procedures, and  notification  procedures
required in §258.20 of this Part;

   (3)   Gas  monitoring  results   from
monitoring  and  any remediation plans
required by §258.23 of this  Part;

   (4)   Any   MSWLF    unit   design
documentation for placement of leachate or
gas  condensate  in  a MSWLF unit as
required under §258.28 (a)(2) of this Part;

   (5)  Any demonstration, certification,
finding, monitoring, testing, or analytical
data required by Subpart E of this Part;
    (6) Closure and post-closure care plans
and any monitoring, testing, or analytical
data as required by §§258.60 and 258.61 of
this Part; and

    (7)  Any  cost estimates  and financial
assurance  documentation  required  by
Subpart G of this Part.

    (8)  Any  information demonstrating
compliance   with   small    community
exemption  as required by §258.1(f)(2).

    (b)  The  owner/operator must notify
the State  Director when the documents
from  paragraph  (a) of this section have
been  placed  or added  to the operating
record, and all information contained in
the operating record must be furnished
upon  request to the State Director or be
made available at all reasonable times  for
inspection by the  State Director.

    (c)  The Director of an approved State
can  set   alternative    schedules    for
recordkeeping     and     notification
requirements  as specified in paragraphs (a)
and  (b),   except  for   the   notification
requirements    in    §258.10(b)   and
§258.55(g)(l)(iii).

3.11.2 Applicability

The regulation applies to existing  MSWLF
units, lateral expansions of existing MSWLF
units,   and  new  MSWLF  units.    The
recordkeeping  requirements are intended to be
self-implementing so that owners/ operators in
unapproved States can comply without State
or EPA involvement. The owner or operator
is  required   to   maintain    records   of
demonstrations,   inspections,   monitoring
results, design documents, plans, operational
                                         110

-------
                                    Operating Criteria
procedures,  notices,  cost  estimates,  and
financial assurance documentation.

3.11.3 Technical Considerations

The operating record should be maintained in
a single location.  The location may be at the
facility, at corporate headquarters, or at city
hall, but should be near the facility. Records
should be maintained throughout the life of
the facility,  including the post-closure care
period.   Upon placement of each required
document in the operating record, the State
Director should be notified.  The Director of
an approved State may  establish alternative
requirements for recordkeeping, including
using  the State permit file for recordkeeping.

Recordkeeping at the landfill facility should
include  the following:

   (a)   Location restriction demonstrations:
Demonstrations are required for any location
restrictions  under Subpart B. The location
restrictions apply to:

•  Airports;

•  Floodplains;

•  Wetla

•  Fault areas;

•  Seismic impact zones; and

•  Unstable  areas.

   (b)   Inspection     records.     training
procedures,  and  notification   procedures:
Inspection records should include:
•   Date and time wastes were received during
    the inspection;

•   Names of the transporter and the driver;

•   Source of the wastes;

•   Vehicle identification numbers; and

•   All observations made by the inspector.

Training  records should include procedures
used to train personnel on hazardous waste
and on PCB waste recognition.  Notification
to EPA, State, and local agencies should be
documented.

    (c)  Gas  monitoring  results  and  any
remediation plans:  If gas levels exceed 25
percent of the LEL for methane in any facility
structures or exceed the LEL for methane at
the facility boundary, the  owner or operator
must place in the operating record, within
seven days, the methane gas levels detected,
and a description of the steps taken to protect
human health.  Within 60 days  of detection,
the owner or operator  must place a copy of
the remediation plan used for gas releases in
the operating record.

    (d)    MSWLF      unit      design
documentation for placement of leachate or
gas condensate in a MSWLF unit: If leachate
and/or gas condensate are recirculated into the
MSWLF unit, documentation of a composite
liner and a leachate collection system capable
of maintaining a  maximum of 30 cm of
leachate head in the MSWLF unit must be
placed in the operating record.
                                           Ill

-------
                                        Subpart C
(e)     Demonstration.	certification.
monitoring, testing,  or analytical  Finding
required  by  the   ground-water  criteria:
Documents to  be placed  in  the  operating
record include:

•  Documentation  of  design,  installation,
   development, and decommission of any
   monitoring wells, piezometers,  and other
   measurement,  sampling,  and  analytical
   devices;

•  Certification by a qualified ground-water
   scientist of the  number,  spacing,  and
   depths of the monitoring systems;

•  Documentation of sampling and analysis
   programs and statistical procedures;

•  Notice of finding a statistically significant
   increase over background for one or more
   of the constituents listed in Appendix I of
   Part 258 (or alternative list in  approved
   States) at any monitoring well at the waste
   management unit boundary (States with
   inadequate program) or the relevant point
   of compliance (approved States);

•  Certification by a qualified ground-water
   scientist that an error in sampling, analysis,
   statistical evaluation, or natural variation in
   ground  water  caused an  increase (false
   positive) of Appendix I constituents, or
   that a source other than  the MSWLF unit
   caused the contamination (if appropriate);

•  A notice identifying any Appendix II (Part
   258) constituents that have been detected
   in ground water and their concentrations;
•   A  notice  identifying  the  Part  258
    Appendix  II  constituents  that  have
    exceeded the ground-water protection standard;

•   A certification by  a qualified ground-
    water scientist that a source other than
    the   MSWLF   unit    caused    the
    contamination  or an error in sampling,
    analysis, statistical evaluation, or natural
    ground-water   variation   caused   a
    statistically  significant increase (false
    positive)  in  Appendix  II (Part  258)
    constituents (if applicable);

•   The remedies  selected  to  remediate
    ground-water contamination; and

•   Certification of remediation completion.

    (f)  Closure and post-closure plans and
any monitoring,  testing, or analytical data
associated with  these  plans:   The landfill
facility owner or operator is required to place
a copy of the closure plan, post-closure plan,
and a notice of intent to close the facility in
the operating record. Monitoring, testing, or
analytical data associated with closure and
post-closure  information  generated  from
ground-water and  landfill  gas monitoring
must be placed in the operating  record.   A
copy  of the notation on  the deed to  the
MSWLF  facility  property,   as  required
following closure, along with certification and
verification   that  closure and post-closure
activities have been completed in accordance
with their  respective  plans,  also  must be
placed in the operating record.

    (g) Estimates  and financial assurance
documentation  required:    The following
documents must be placed in the operating
record:
                                           112

-------
                                     Operating Criteria
•  An estimate of the cost of hiring a third
   party to  close  the largest  area of  all
   MSWLF units that will require final cover;

•  Justification for the  reduction of  the
   closure  cost estimate and the amount of
   financial assurance (if appropriate);

•  A cost estimate  of hiring a third party to
   conduct post-closure care;

•  The justification for the reduction of the
   post-closure cost estimate and  financial
   assurance  (if appropriate);

•  An estimate and financial assurance for the
   cost of a third  party to conduct corrective
   action, if necessary; and

•  A  copy  of  the   financial  assurance
   mechanisms.
                                            113

-------
                                      Subpart C
3.12 FURTHER INFORMATION

3.12.1  References

Flower, et al., (1982). "Vegetation Kills in Landfill Environs"; Franklin B. Flower, Ida A. Leone,
   Edward F. Oilman and John J. Arthur; Cook College, Rutgers University; New Brunswick, New
   Jersey 08903.

Reinhart, D.R., and D. Carson, (1993). "Experiences with Full-Scale Application of Landfill
   Bioreactor Technology," Thirty-First Annual  Solid Waste Exposition of the Solid Waste
   Association of North America, August 2-5, 1993.

SWANA, (1992). "A Compilation of Landfill Gas Field Practices and Procedures"; Landfill Gas
   Division of the Solid Waste Association of North America (SWANA); March 1992.

U.S. Department of Agriculture Soil Conservation Service, (1986). "Urban Hydrology for Small
   Watersheds"; PB87-101580.

U.S. Department of Commerce, Weather Bureau, "Rainfall Frequency Atlas of the United States for
   Durations from 30 Minutes to 24 Hours and Return Periods from 1 to 100 Years."

U.S. EPA, (1985).  "Handbook - Remedial Action at Waste Disposal Sites"; EPA/625/6-85/006;
   U.S. EPA, Office of Research and Development; Cincinnati, Ohio 45268.

U.S. EPA, (1986).  "Test Methods for Evaluating Solid Wastes:  Physical/Chemical Methods";
   Third Edition as amended by Updates I and II. U.S. EPA SW-846; Office of Solid Waste and
   Emergency Response; Washington,  D.C.

U.S. EPA, (1988).  "Guide to Technical Resources for the Design of Land Disposal  Facilities";
   EPA/625/6-88/018; U.S. EPA; Risk  Reduction Engineering Laboratory and  Center for
   Environmental Research Information; Cincinnati, Ohio 45268.

U.S. EPA, (1992).  "Alternative Daily Cover Materials for Municipal Solid Waste Landfills;"
   U.S. EPA Region IX; San Francisco, California 94105.
3.12.2  Addresses

Solid Waste Association of North America (SWANA/GRCDA)
P.O.Box 7219
Silver Spring, MD 20910
(301)585-2898
                                         114

-------
          APPENDIX I
Special Waste Acceptance Agreement
               115

-------
                                                                     Code*
Generator Name:
Address:	
                        Special  Waste Acceptance Application
Originating Division:^
Disposal Facility	
Location:	
Telephone: (   )	
Generator Contact:	
General Material Description: _
Waste Quantities:,
                                                                                   Units: Cubic Ws.3  Tons 3
Frequency of Receipt:  Daily a  Weekly O  Monthly 3  One Time 3
Other	
Process Generating Waste:	
Physical Properties:   Physical State at 7(fF: Solida SemisolidU iiquida Density:,
                 Viscosity: low O Medium !3 High Q     Flash Point:
                 Water Content:	% by Weight  Paint Filter Test:  Passed 3 Failed1!
                 Reactive: No 3 YesO With
                    f/CY  Color:
                    Odor. YesD No 3
Waste pH:
Chemical Properties: (Concentrations in mg/l)
(TCLP) Arsenic
Barium
Benzene
Cadmium
Carbon Tetrach/oride
Chlordane
Chlorobenzene
Chloroform
Chromium
o-Cresol
Other (iist):

Other Information: Delivery Method: Bulk 3
Regulatory Agency Appro\
Infectious: Yes 3 No J
m-Cresol
p-Cresol
Cresol
2,4-D
1,4 Dichlorobemene
1,2 Dich/oroethane
1, 1-Dichloroethylene
2,4-Dinitrotoluene
Endrirt
Heptach/or


Other
tal Received: VesQ AtoO
Hexachiorobenzene
Hexach/orobutadiene
Hexach/oroethane
Lead
Lindane
Mercurv
Methoxvchlor
Methyl Ethyl Ketone
Nitrobenzene
Pentachlorophenol



Permit Number:
Pyridine
Selenium
Silver
Tetrachloroethv/ene
Toxaohene
Trichloroethvlene
2. 4. S-Trich/oroohenol
2.4.6-Trichlorophenol
2.4.5-TP (Silvexl
Vinvl Chloride




                Material Safety Data Sheet Provided: Yes 3
GENERA TOR CER TIFICA TION
To the best of my knowledge, the information
provided above is accurate anrj the material is
not classified as a hazardous waste in
accordance with current regulations-.
Authorised Representative
Signature	
Name	
Title	
Date	

|| FOR OFFICE USE ONLY ||
Conditions for Acceptance




1 Originating Division Manager
2 Disposal Facility Manager
3. District Manager
4 Regional Engineer
Date
Date
Date
Date
Recertification Frequency: HI Annual 3 Annual Q Semi Annual 3
   "age Ic Owner'Cperator Second Page to Customer, Third Page to Laboratory
        Appendix I.  Example Special Waste Acceptance Agreement
                                                  116

-------
   CHAPTER 4

   SUBPART D
DESIGN CRITERIA

-------
                                       CHAPTER 4
                                       SUBPART D

                                 TABLE OF CONTENTS

4J.    INTRODUCTION 	121

42.    PERFORMANCE-BASED DESIGN
       40 CFR §258.40	122
       4.2.1 Statement of Regulation 	122
              4.2.2 Applicability	123
       4.2.3 Technical Considerations  	123
              Demonstration Requirements	123
              Leachate Characterization	124
              Assessment of Leakage Through Liners	125
              Leachate Migration in the Subsurface	126
                     Physical Processes Controlling Contaminant Transport in the Subsurface  . . 126
                     Chemical Processes Controlling Contaminant Transport in the Subsurface
                             	128
                     Biological Processes Controlling Contaminant Transport in the Subsurface
                             	129
              Leachate Migration Models  	130
              Overview of the Modeling Process	130
              Model Selection	135
                     Analytical Versus Numerical Models	135
                     Spatial Characteristics of the System	136
                     Steady-State Versus Transient Models	136
                     Boundary and Initial Conditions  	137
                     Homogeneous Versus Heterogeneous Aquifer/Soil Properties  	137
                     Availability of Data	138
              Summary of Available Models	138
              The EPA Multimedia Exposure Assessment Model (MULTIMED)  	139
                     Overview of the Model  	147
              Application of MULTIMED to MSWLF Units	147
                                           118

-------
4.3    COMPOSITE LINER AND LEACHATE COLLECTION SYSTEM
       40 CFR §258.40	149
       4.3.1  Statement of Regulation 	149
       4.3.2  Applicability	150
       4.3.3 Technical  Considerations	150
              Standard Composite Liner Systems  	150
              Soil Liner	151
                      Thickness	151
                      Lift Thickness 	151
                      Bonding Between Lifts  	152
                      Placement of Soil Liners on Slopes  	152
                      Hydraulic Conductivity	152
                      Soil Properties	153
                      Amended Soils  	154
                      Testing	154
                      Soil Liner Construction	159
              Geomembranes	160
                      Material Types and Thicknesses	160
                      Chemical and Physical Stress Resistance	160
                      Installation	162
              Leachate Collection Systems  	165
                      Grading of Low-Permeability Base  	166
                      High-Permeability Drainage Layer	167
                      Soil Drainage Layers	167
                      Geosynthetic  Drainage Nets	168
              Leachate Collection Pipes	171
                      Protection of Leachate Collection Pipes	173
                      Protection of the  High-Permeability Drainage Layer 	178
                      Soil Filter Layers	178
                      Geotextile Filter  Layers	179
              Leachate Removal System  	181
                      Other Design Considerations	182
              Construction Quality Assurance and Quality Control	182
                      COA/COC Objectives	182
              Soil Liner Quality Assurance/Quality Control  	183
              Soil Liner Pilot Construction (Test Fill)	185
              Geomembrane Quality Assurance/Quality Control Testing	185
                      Destructive Testing  	185
                      Non-Destructive  Testing 	186
              Geomembrane Construction Quality Assurance Activities  	186
              Leachate Collection System Construction Quality Assurance	187
                                             119

-------
4.4    RELEVANT POINT OF COMPLIANCE 40 CFR §258.40(d) 	188
       4.4.1 Statement of Regulation  	188
       4.4.2 Applicability	189
       4.4.3 Technical Considerations  	189
              Site Hydrogeology	189
              Leachate Volume and Physical Characteristics	189
              Quality. Quantity and Direction of Ground-Water Flow	189
              Ground-Water Receptors  	190
              Alternative Drinking Water Supplies  	190
              Existing Ground-Water Quality  	190
              Public Health. Welfare. Safety	190
              Practicable Capability of the Owner or Operator	191

4_J    PETITION PROCESS 40 CFR §258.40(e^	191
       4.5.1 Statement of Regulation	191
       4.5.2 Applicability  	191

4A    FURTHER INFORMATION  	193
       4.6.1  REFERENCES (Specific to  Performance-Based Design Assessment and Solute
              Transport Modeling)	193
       4.6.2 REFERENCES (Specific to Design Criteria^	199
       4.6.3 Models 	202
                                            120

-------
                                     CHAPTER 4
                                     SUBPART D

                                DESIGN CRITERIA
4.1 INTRODUCTION

New MSWLF facilities and lateral expansions of existing units must comply with either a design
standard or a performance standard for landfill design.  The Federal Criteria do not require existing
units to be retrofitted with liners.  The design standard requires a composite liner composed of two
feet of soil with a hydraulic conductivity of no more than 1 x 10"7 cm/sec, overlain by a flexible
membrane liner (FML) and a leachate collection system.  A performance-based design must
demonstrate the capability of maintaining contaminant concentrations below maximum contaminant
levels (MCLs) at the unit's relevant point of compliance.   The performance standard has been
established to allow design innovation and consideration of site-specific conditions; approved States
may have adopted alternative design standards. Owners/operators are advised to work closely with
State permitting agencies to determine the applicable  design  standard.   Owners/operators in
unapproved States may  use the petition process (§258.40(c)) to  allow for use of a performance-
based design.  This process is discussed in Section 4.5.

The technical considerations discussed in this chapter are intended to identify the key design features
and system components  for the composite liner and leachate collection system standards, and for
the performance standard.  The technical considerations include  1) design concepts, 2)  design
calculations, 3) physical properties, and 4) construction methods for the following:

   1) Designs Based on  the Performance Standard

      • Leachate characterization and leakage assessment;

      • Leachate migration in the subsurface;

      • Leachate migration models; and

      • Relevant point of compliance assessment.

   2) Composite Liners  and Leachate Collection Systems

      • Soil  liner  component (soil properties lab testing, design,  construction,  and  quality
        assurance/quality control testing);

      • Flexible  membrane   liners   (FML  properties,  design  installation,  and   quality
        assurance/quality control testing);

      • Leachate collection systems (strength and compatibility, grading and drainage, clogging
        potential, and filtration);
                                           121

-------
                                       Subpart D
      • Leachate removal systems (pumps, sumps, and standpipes); and

      • Inspections (field observations and field and laboratory testing).

Designs based on the performance  standard are described in Section  4.2.  Requirements for
composite liners are discussed in Section 4.3. These  sections address the minimum regulatory
requirements that should be considered during the design, construction, and operation of MSWLF
units to ensure that they perform in  a manner protective of human health and the environment.
Additional features or procedures may  be used to demonstrate conformance with the regulations or
to control leachate release and subsequent effects.  For example, during construction of a new
MSWLF unit, or a lateral expansion of an  existing MSWLF unit, quality control and quality
assurance procedures and documentation may be used to  ensure that  material properties  and
construction methods meet the design specifications that are intended to achieve the expected level
of performance.  Section 4.4 presents  methods to assess ground-water quality at the relevant point
of compliance for performance-based designs.  Section 4.5 describes the applicability of the petition
process for States wishing to petition to use the performance standard.	
4.2  PERFORMANCE-BASED DESIGN
     40 CFR §258.40(a)(l)

4.2.1  Statement of Regulation

     (a) New MSWLF units and lateral
expansions shall be constructed:

     (1) In  accordance  with   a  design
approved by the Director of an approved
State or as specified  in §258.40(e) for
unapproved States. The design must ensure
that  the concentration values  listed in
Table  1  will  not  be  exceeded  in the
uppermost aquifer at the relevant point of
compliance as specified by the Director of
an approved State under paragraph (d) of
this section, or

     (2) (See Statement of Regulation in
Section  4.3.1 of this guidance document for
the regulatory language for composite liner
requirements).

     (b) (See Statement of Regulation in
Section  4.3.1 of this guidance document for
the regulatory language for  requirements
pertaining to composite liner  and leachate
collection systems).

     (c) When approving a design that
complies with  paragraph (a)(l)  of this
section, the Director of an approved State
shall consider at least the following factors:

     (1) The hydrogeologic characteristics
of the facility and surrounding land;
     (2) The climatic factors of the area;
and
     (3) The volume  and  physical  and
chemical characteristics of the leachate.

     (d) (See Statement of Regulation  in
Section 4.4.1 of this guidance document for a
discussion of the determination of the relevant
point of compliance.)
                                          122

-------
                                     Design Criteria
                TABLE 1
      (40 CFR 258.40; 56 FR 51022;
            October 9, 1991)
  Chemical
MCL(mg/l)
  Arsenic                     0.05
  Barium                     1.0
  Benzene                     0.005
  Cadmium                   0.01
  Carbon tetrachloride        0.005
  Chromium (hexavalent)      0.05
  2,4-Dichlorophenoxy
    acetic acid                 0.1
  1,4-Dichlorobenzene         0.075
  1,2-Dichloroethane          0.005
  1,1-Dichloroethylene         0.007
  Endrin                      0.0002
  Fluoride                     4.0
  Lindane                     0.004
  Lead                        0.05
  Mercury                     0.002
  Methoxychlor               0.1
  Nitrate                     10.0
  Selenium                    0.01
  Silver                       0.05
  Toxaphene                  0.005
  l,l?l-Trichloroethane        0.2
  Trichloroethylene            0.005
  2,4,5-Trichlorophenoxy
    acetic acid                 0.01
  Vinyl Chloride              0.002
4.2.2  Applicability

The Director  of an  approved  State may
approve a performance-based design for new
MSWLF units and  lateral  expansions of
existing units (see Section 4.3.2), if it meets
the requirements  specified  in  40  CFR
258.40(a)(l). A performance-based design is
an  alternative  to   the   design  standard
(composite liner with a leachate collection
system). The composite design is required in
unapproved States; however, if EPA does not
promulgate procedures for State approval by
October  9,  1993,  the  performance-based
design may be available through the petition
process (see Section 4.5).

4.2.3  Technical Considerations

Demonstration Requirements

For   approval   of   landfill  designs  not
conforming to the uniform design standard of
a composite liner  system and a  leachate
collection system (40 CFR §258.40(a)(2)), the
owner or operator of the proposed MSWLF
unit must demonstrate to the  Director of an
approved State that the design will not allow
the compounds listed in Table 1 of §258.40 to
exceed the  MCLs in ground water  at the
relevant   point   of  compliance.     The
demonstration should consider an assessment
of leachate quality and  quantity,  leachate
leakage to the subsurface, and subsurface
transport to the relevant point of compliance.
These  factors  are   governed  by  site
hydrogeology,  waste  characteristics,  and
climatic conditions.

The nature of the demonstration is essentially
an assessment of the potential  for leachate
production and leakage from  the landfill to
ground water, and the anticipated  fate and
transport of constituents listed in Table 1 to
the proposed relevant point of compliance at
the  facility.  Inherent in this approach is the
need  to evaluate whether  contaminants in
ground water  at   the  relevant  point of
compliance  will exceed  the  concentration
values listed in Table 1. If so, then the owner
or operator  needs to  obtain sufficient site-
specific data to  adequately characterize the
existing ground-
                                          123

-------
                                        Subpart D
water quality and the existing ground-water
flow regime (e.g., flow direction, horizontal
and vertical gradients, hydraulic conductivity,
stratigraphy, and aquifer thickness).

An assessment should be made of the effect
MSWLF facility  construction will have on
site hydrogeology.   The assessment should
focus on  the  reduced  infiltration  over the
landfill area and altered surface water run-off
patterns. Reduction of ground-water recharge
and  changes   in surface  water  patterns
resulting from landfill construction may affect
ground-water  gradients in some cases and
may  result  in  changes  in lateral   flow
directions.   One  example of a hypothetical
performance-based demonstration follows.

It is possible that a MSWLF unit located in an
arid climatic zone would not produce leachate
from  sources  of water (e.g., precipitation)
other than that existing within the waste at the
time of disposal.  In such an environment, an
owner or  operator  may demonstrate  that
significant quantities of leachate would not be
produced.   The  demonstration  should be
supported by evaluating historic precipitation
and evaporation data and the likelihood that
the unit could be flooded as the  result of
heavy rains, surface run-off,  or high water
tables.    It  may   be  possible,  through
operational controls, to avoid exposing waste
to  precipitation  or  infiltration  of water
through overlying materials.  If significant
leachate production would not be expected,
the regulatory  authority, when reviewing the
demonstration,   should    consider    the
hydrogeologic  characteristics  of the facility
and the surrounding area, in  addition to the
expected volume of leachate and climatic
factors.
Assuming   leachate   is   produced,   the
demonstration   should  evaluate  whether
constituents listed in Table 1 can be expected
to be present at concentrations greater than the
MCLs. If such a demonstration is possible, it
must address the hydrogeologic characteristics
of the facility  and the surrounding  land to
comply with  §258.40(d).   The  following
sections  describe the  various  parts of a
demonstration in greater detail.

Leachate Characterization

Leachate characterization should include an
assessment  and demonstration of the quantity
and composition of leachate anticipated at the
proposed   facility.     Discussion  of  this
assessment follows.

Estimates of volumetric production rates of
leachate are important in evaluating the fate
and transport  of the  constituents listed in
Table 1. Leachate production rates depend on
rainfall, run-on, run-off, evapotranspiration,
water table  elevation relative to the bottom of
the landfill unit, in-place moisture content of
waste, and the prevention of liquid disposal at
the site.  Run-on,  run-off,  and water table
factors can be managed traditionally through
design and operational controls. The MSWLF
Criteria prohibit bulk or containerized liquid
disposal.     Incident  precipitation  and
evapotranspiration  can be evaluated using
models (e.g.,  HELP) or  other  methods  of
estimating  site-specific leachate production
(e.g.,  local  historical meteorologic data).

If  leachate  composition  data  that  are
representative of the proposed facility  are not
available, then leachate data with a  similar
expected composition should be presented.
Landfill leachate composition is influenced
by:
                                            124

-------
                                     Design Criteria
(1)  The annual infiltration of precipitation
     and rate of leaching;

(2)  The type  and  relative amounts  of
     materials in the waste stream; and

(3)  The age and the biological  maturity of
     the landfill unit, which may affect the
     types of organic and inorganic acids
     generated, oxidation/reduction potential
     (Eh), and pH conditions.

An existing landfill unit in the same region,
with similar waste stream characteristics, may
provide information that will allow the owner
or operator to anticipate leachate composition
of the proposed landfill  unit. A review of
existing  literature also may be  required to
assess  anticipated  leachate composition if
actual  data are unavailable (see U.S. EPA,
1987b).    A  wide  range  of   leachate
concentrations are reported in the literature
with   higher  concentrations of  specific
constituents typically reported for the initial
leachate from laboratory or field experimental
test fills or test cells. These "batch" one-day
landfill tests do not account for the long-term
climatic and meteorological influences on a
full-scale landfill operation.  Such high initial
concentrations are not typical of  full-scale
operations (which are subject to  the dilution
effects  of incidental  rainfall   on  unused
portions of the unit).

Assessment of Leakage Through Liners

An assessment of leakage  (the  volumetric
release  of  leachate from  the  proposed
performance-based design) should be based
on   analytical  approaches  supported  by
empirical data from other existing operational
facilities of similar design, particularly those
that have leak detection monitoring systems
(see U.S. EPA,  1990b).
In lieu of the existence or availability of such
information,     conservative     analytical
assumptions  may  be   used   to   estimate
anticipated leakage rates.

The transport of fluids and waste constituents
through geomembranes differs in principle
from  transport  through  soil liner materials.
The  dominant  mode of leachate transport
through liner components  is  flow through
holes  and  penetrations of the geomembrane,
and Darcian flow through soil components.
Transport through geomembranes where tears,
punctures,  imperfections, or seam failures are
not involved  is  dominated by  molecular
diffusion.   Diffusion occurs in response to a
concentration gradient and  is governed  by
Pick's  first law.   Diffusion  rates  through
geomembranes are very low in comparison to
hydraulic  flow rates in soil liners, including
compacted clays.  For synthetic  liners, the
most  significant factor influencing  liner
performance  is penetration  of  the  liner,
including imperfect seams or pinholes caused
by construction defects in the geomembrane
(U.S.  EPA, 1989).

A relatively new product now being used in
liner  systems is the geosynthetic clay  liner
(GCL).   GCLs  consist of a  layer of pure
bentonite   clay  backed  by  one  or  two
geotextiles.  GCLs exhibit properties of both
soil  liners and geomembranes,  and  have
successfully   substituted   for   the  soil
component in composite liner designs. GCLs
are believed to transport  fluids primarily
through diffusion  according  to  their low
hydraulic conductivities (i.e., 1 x 10"9 cm/sec
reported by manufacturers).  Applications for
GCLs are discussed further in the sections that
follow.

Several researchers  have studied the flow of
fluids  through  imperfections   in  single
                                           125

-------
                                        Subpart D
geomembrane and composite liner systems.
Further discussion of liner leakage rates can
be  found  in  Section 4.3.3 below.    For
empirical  data and analytical methods the
reader is  referred to Jayawickrama  et  al.
(1988), Kastman (1984), Haxo (1983), Haxo
et al.  (1984), Radian (1987),  Giroud  and
Bonaparte (1989,  Parts I and II), and Giroud
et al. (1989). Leakage assessments also may
be conducted with the use of the HELP model
(U.S.  EPA,  1988). Version 3.0 of the model
is under revision and will include an updated
method to assess leakage that  is based  on
recent research and data compiled by Giroud
and Bonaparte.

Leachate  Migration in the Subsurface

Leachate that escapes from a landfill unit may
migrate through  the  unsaturated zone  and
eventually reach the uppermost aquifer.  In
some instances, however, the water table may
be located above the base of the  landfill unit,
so that only saturated flow and transport from
the landfill unit need to be considered.  Once
leachate reaches the water table, contaminants
may be transported through the saturated zone
to a point  of discharge (i.e., a pumping well,
a stream, a lake, etc.).

The migration of leachate in the subsurface
depends on factors such as the volume of the
liquid component of the waste, the chemical
and  physical  properties  of the   leachate
constituents, the loading rate, climate, and the
chemical  and  physical  properties of  the
subsurface (saturated and unsaturated zones).
A  number  of   physical,   chemical,   and
biological  processes also  may  influence
migration.   Complex interactions between
these   processes  may  result  in  specific
contaminants being transported through the
subsurface  at different  rates.    Certain
processes  result  in  the attenuation  and
degradation of contaminants.  The degree of
attenuation is dependent on the time that the
contaminant is in contact with the subsurface
material,   the   physical  and   chemical
characteristics of the subsurface material, the
distance that the contaminant has traveled,
and  the  volume and  characteristics of the
leachate. Some of the key processes affecting
leachate migration are  discussed briefly here.
The  information is based on  a summary in
Travers and Sharp-Hansen (1991), who in
turn  relied  largely on Aller  et al. (1987),
Keely (1987), Keely (1989), Lu et al. (1985),
and U.S. EPA(1988a).

Physical Processes Controlling
Contaminant Transport in the Subsurface

Physical processes that control the transport of
contaminants  in  the subsurface  include
advection, mixing and dilution as a result of
dispersion   and   diffusion,   mechanical
filtration, physical sorption, multi-phase fluid
flow, and fracture flow.  These processes, in
turn,   are  affected   by   hydrogeologic
characteristics, such as  hydraulic conductivity
and porosity, and by chemical processes.

Advection  is the process by  which  solute
contaminants are transported  by the overall
motion of flowing ground water.   A non-
reactive solute will be transported at the same
rate and in the same direction as ground water
flow (Freeze and Cherry,  1979). Advective
transport  is chiefly  a   function  of  the
subsurface hydraulic conductivity distribution,
porosity, and hydraulic gradients.

Hydrodynamic  dispersion is  a non-steady,
irreversible  mixing  process   by  which  a
contaminant plume spreads as it is transported
through the subsurface.   Dispersion results
from the effects of two
                                           126

-------
                                      Design Criteria
components  operating  at  the microscopic
level: mechanical  dispersion and molecular
diffusion.  Mechanical dispersion results from
variations in pore velocities within the soil or
aquifer and may  be more significant than
molecular diffusion in environments where
the  flow  rates  are  moderate  to  high.
Molecular  diffusion occurs  as a result  of
contaminant     concentration    gradients;
chemicals move from high concentrations to
low concentrations. At very slow ground-
water velocities, as occur in clays and silts,
diffusion  can  be  an   important  transport
mechanism.

Mechanical filtration removes from ground
water contaminants that are larger than  the
pore spaces of the soil.  Thus, the effects of
mechanical filtration increase with decreasing
pore size within a medium. Filtration occurs
over a  wide range of particle sizes.  The
retention of larger particles may effectively
reduce the permeability of the soil or aquifer.

Physical sorption  is a  function of Van  der
Waals forces,  and  the hydrodynamic and
electrokinetic  properties  of soil  particles.
Sorption is the process by which contaminants
are removed from  solution in ground water
and adhere or cling to a solid surface.  The
distribution  of a  contaminant between  the
solution  and  the  solid  phase  is  called
partitioning.

Multiphase fluid flow occurs because many
solvents and oils are highly insoluble in water
and may  migrate  in the  subsurface as a
separate liquid phase.   If the viscosity and
density of a fluid differ from that of water, the
fluid may flow at a different rate and direction
than the ground water.  If the  fluid is more
dense than water it may reach the bottom of
the aquifer (top of an aquitard)
and alter its flow direction to conform to the
shape and slope of the aquitard surface.

Hydraulic conductivity  is a measure of the
ability of geologic media to transmit fluids
(USGS, 1987).  It is a function of the size and
arrangement of water-transmitting openings
(pores and fractures) in  the media and of the
characteristics of the fluids (density, viscosity,
etc.).     Spatial   variations  in   hydraulic
conductivity are referred  to as heterogeneities.
A variation in hydraulic conductivity with the
direction  of measurement is  referred  to as
anisotropy.

Variable  hydraulic  conductivity   of  the
geologic formation may cause ground-water
flow velocities to vary spatially. Variations in
the rate of advection  may  result in non-
uniform plume spreading.  The changes in
aquifer properties that lead to this variability
in hydraulic  conductivity  may  be three-
dimensional.   If  the  geologic  medium is
relatively   homogeneous,   it   may   be
appropriate, in some instances, to assume that
the aquifer properties also are homogeneous.

Secondary porosity in rock may be caused by
the dissolution of rock  or by  regional
fracturing; in soils, secondary porosity may be
caused  by  desiccation  cracks or  fissures.
Fractures or macropores respond quickly to
rainfall events and other fluid inputs and  can
transmit water  rapidly along  unexpected
pathways.  Secondary porosity can result in
localized high concentrations of contaminants
at significant distances from the facility.  The
relative importance of secondary porosity to
hydraulic conductivity  of the  subsurface
depends on the ratio of fracture  hydraulic
conductivity  to   intergranular   hydraulic
conductivity (Kincaid  et al.,  1984a).   For
scenarios in which  fracture flow is dominant,
the relationships
                                            127

-------
                                        Subpart D
used to describe porous flow (Darcy's Law)
do not apply.

Chemical Processes Controlling
Contaminant Transport in the Subsurface

Chemical processes that are important in
controlling   subsurface  transport  include
precipitation/dissolution, chemical sorption,
redox reactions, hydrolysis, ion exchange, and
complexation.  In general, these processes,
except for hydrolysis, are reversible.   The
reversible processes tend to retard transport,
but do not permanently remove a contaminant
from the system.  Sorption and precipitation
are generally  the dominant  mechanisms
retarding   contaminant  transport  in  the
saturated zone.

Precipitation/dissolution reactions can control
contaminant   concentration  levels.     The
solubility of  a solid controls the equilibrium
state  of a  chemical.   When the  soluble
concentration of a contaminant in leachate is
higher than  that of the  equilibrium state,
precipitation  occurs.    When  the  soluble
concentration is lower than the equilibrium
value, the contaminant exists in solution.  The
precipitation of a dissolved substance may be
initiated by changes in pressure, temperature,
pH, concentration, or redox potential (Aller et
al., 1987).  Precipitation of contaminants in
the pore space of an  aquifer can decrease
aquifer porosity. Precipitation and dissolution
reactions are especially important processes
for trace metal migration in soils.

Chemical adsorption/desorption is the most
common mechanism  affecting  contaminant
migration in  soils. Solutes become attached
to the solid phase by  means of adsorption.
Like     precipitation/dissolution,
adsorption/desorption is a reversible process.
However, adsorption/desorption
generally occurs at a relatively rapid  rate
compared to precipitation reactions.

The dominant mechanism of organic sorption
is  the  hydrophobic  attraction  between  a
chemical and natural organic matter that exists
in some aquifers. The organic carbon content
of the porous medium, and the solubility of
the contaminant, are important factors for this
type of sorption.

There is a direct  relationship  between the
quantity of a substance sorbed  on a particle
surface  and the quantity of the  substance
suspended in solution. Predictions about the
sorption of contaminants often  make use of
sorption isotherms, which relate the amount of
contaminant  in  solution  to  the  amount
adsorbed  to  the  solids.    For  organic
contaminants,  these isotherms  are  usually
assumed to be linear  and  the reaction  is
assumed to be instantaneous  and reversible.
The  linear equilibrium approach to sorption
may not be adequate for all situations.

Oxidation  and reduction  (redox) reactions
involve the transfer of electrons and occur
when the  redox  potential  in  leachate  is
different from that of the  soil  or aquifer
environment. Redox reactions are important
processes  for  inorganic  compounds  and
metallic elements.   Together with pH, redox
reactions  affect the solubility,  complexing
capacity,   and   sorptive   behavior   of
constituents, and thus control the presence and
mobility  of  many  substances  in water.
Microorganisms are responsible for a large
proportion of redox reactions that occur in
ground water.  The redox state of an aquifer,
and the  identity and quantity of redox-active
reactants, are difficult to determine.
                                           128

-------
                                     Design Criteria
Hydrolysis is the chemical  breakdown of
carbon bonds in organic substances by water
and its ionic species H+ and OH".  Hydrolysis
is  dependent  on pH and Eh and  is most
significant at high temperatures, low pH, and
low redox potential. For many biodegradable
contaminants, hydrolysis is slow compared to
biodegradation.

Ion  exchange originates  primarily  from
exchange sites on layered silicate clays and
organic matter that have a permanent negative
charge.   Cation exchange balances negative
charges in order to maintain neutrality.  The
capacity of soils to exchange cations is called
the cation exchange capacity (CEC). CEC is
affected by the type and quantity  of clay
mineral present, the amount of organic matter
present,  and the pH of the soil. Major cations
in leachate (Ca, Mg, K, Na) usually dominate
the CEC sites, resulting in little attenuation in
soils of trace metals in the leachate.

A  smaller ion exchange effect for anions is
associated  with  hydrous  oxides.    Soils
typically have more negatively charged clay
particles than positively  charged  hydrous
oxides.  Therefore, the transport of cations is
attenuated more than the transport of anions.

Complexation involves reactions of metal ions
with inorganic anions  or organic ligands.  The
metal and the ligand bind together to form a
new  soluble  species  called a complex.
Complexation  can   either  increase  the
concentration of a constituent in solution by
forming soluble complex ions or decrease the
concentration  by  forming  a soluble  ion
complex with a solid. It is often difficult to
distinguish  among   sorption,   solid-liquid
Complexation, and ion exchange.
Therefore,   these   processes   are  usually
grouped together as one mechanism.

Biological Processes Controlling
Contaminant Transport in the Subsurface

Biodegradation of contaminants may result
from the enzyme-catalyzed transformation of
organic    compounds    by    microbes.
Contaminants can be degraded to harmless
byproducts or to  more mobile and/or toxic
products through  one or  more of several
biological processes.   Biodegradation of a
compound depends on environmental factors
such  as redox potential,  dissolved oxygen
concentration, pH, temperature, presence of
other compounds and nutrients, salinity, depth
below land  surface,  competition  among
different   types   of   organisms,    and
concentrations of compounds and organisms.
The transformations that occur in a subsurface
system are difficult to predict because of the
complexity of the chemical and  biological
reactions  that may  occur.    Quantitative
predictions of the fate of biologically reactive
substances  are subject to a high  degree of
uncertainty, in part, because little information
is available  on biodegradation rates in  soil
systems or ground water.  First-order decay
constants are often used instead.

The operation of Subtitle D  facilities  can
introduce  bacteria and   viruses  into  the
subsurface.  The fate and transport of bacteria
and viruses in the subsurface is an important
consideration in the evaluation of the effects
of MSWLF units on human health and the
environment.  A large number of biological,
chemical, and physical processes are known to
influence  virus and bacterial survival  and
transport in the subsurface. Unfortunately,
knowledge of the processes and the available
data are insufficient to develop models  that
can
                                           129

-------
                                        Subpart D
simulate a  wide  variety  of  site-specific
conditions.

Leachate Migration Models

After    reviewing   the    hydrogeologic
characteristics of the site, the nature of liner
leakage, and the leachate characteristics,  it
may be appropriate  to  use  a mathematical
model to simulate the expected  fate  and
transport of the constituents listed in Table 1
to the relevant point of compliance.  Solute
transport and ground-water modeling efforts
should be conducted by a qualified ground-
water  scientist  (see  Section 5.5).   It  is
necessary to consider several factors when
selecting and applying a model to a site.
Travers and Sharp-Hansen (1991) provide a
thorough review of these issues.  The text
provided below is a summary of their review.

Overview of the Modeling Process

A number of factors can influence leachate
migration  from  MSWLF  units.    These
include, but are  not  limited  to,  climatic
effects,  the  hydrogeologic  setting,  and the
nature of the disposed waste.  Each facility  is
different, and no one generic model will be
appropriate in all  situations.  To develop a
model for a site, the modeling needs and the
objectives of the study should be determined
first. Next, it will be necessary to collect data
to characterize  the hydrological, geological,
chemical, and  biological conditions of the
system.  These data are used to assist in the
development of a  conceptual model of the
system,  including  spatial   and  temporal
characteristics and boundary conditions. The
conceptual  model and data are then used to
select a mathematical model that accurately
represents the conceptual model. The model
selected should  have  been  tested   and
evaluated by qualified investigators, should
adequately simulate the significant processes
present in the actual system, and should be
consistent with the complexity of the study
area, amount of available data, and objectives
of the study.

First, an evaluation of the need for modeling
should be made (Figure 4-1).  When selecting
a model to evaluate the potential for soil and
ground-water contamination (Boutwell et al.,
1986), three basic determinations must be
made (Figure 4-2).  Not all studies require the
use of a mathematical model.  This decision
should be made at the beginning of the study,
since modeling  may require a substantial
amount of resources and effort.  Next, the
level  of model  complexity required for a
specific study should be  determined (Figure
4-3).  Boutwell et al. (1986) classify models
as Level I (simple/analytical) and Level II
(complex/numerical) models.  A flowchart for
determining the level  of model complexity
required is shown in Figure  4-3.  Finally, the
model  capabilities necessary to represent a
particular  system  should  be  considered
(Figure 4-4).  Several models may be equally
suitable for a particular study.  In some cases,
it may be necessary to link or couple two or
more computer models to accurately represent
the processes  at the site.  In the section that
follows,   specific   issues that  should  be
considered when developing a scenario and
selecting a model are described.

Models are a simplified representation of the
real  system,  and  as such,  cannot  fully
reproduce or predict all  site  characteristics.
Errors are  introduced as  a  result  of: 1)
simplifying assumptions; 2) a lack of data; 3)
uncertainty in  existing  data;  4)  a  poor
understanding of the processes influencing the
fate and transport of contaminants; and
                                           130

-------
                                         Model Selection is
                                           Not Required
                     Is Modeling
                     Necessary?
                     (See Figure
                        4.10)
                        What
                       Level of
                      Modeling is
                      Required?
                      (See Figure
                        4.10)
                                             Complex/Numerical
Complex/Numerical
                                              What are
                                            the Required
                                            Level II Model
                                            Capabilities?
                                             (See Figure
                                               4-12)
  What are
the Required
Level I Model
Capabilities?
 (See Figure
   4-12)
                      Figure 4-1
    Three Basic Decisions in Model Selection
               (Boutwell et. al., 1986)
                           131

-------
                             Develop Conceptual
                            Understanding of Site
                                   Can
                               Assumptions
                               be Confirmed
                               with Existing
                                  Data?
          Will
       Additional
      Data Improve
     Understanding?
                                    Do
                                 You Need
                                Quantitative
                                Estimates of
                                  Future
                                Conditions?
   Specify
  Sampling
Requirements
                              Determine Level
                                of Modeling
                                 Required
                       Figure 4-2
Flow Chart to Determine if Modeling is Required
                (Boutwell et. al., 1986)
                           132

-------



Level of Modeling Required 1

r i
Level 1: Analytical Models 1 Level II: Numerical Models 1
j j
Identification of Remedial 1 Model Selection Criteria 1
Action-Specific Models I I
\
|
1 1 1 1
• r^- • r.. 1 Time I Resources/ I
Processes I Dimensionality I c 1 Data 1

*
Model Selection 1 Model Selection 1

                      Figure 4-3
Flow Chart to Determine the Level of Modeling Required for
             Soil and Groundwater Systems
                 (Boutwell et. al., 1986)
                          133

-------
                                                                           Are
                                                                         OitJer of
                                                                         Magnitude
                                                                         Predictions
                                                                        Acceptable
Reassess Goals
and Data Needs
                                                                           is Ft
                                                                         Reasonable
                                                                        to Assume mat
                                                                       Media Properties
                                                                       are Uniform, and
                                                                         Do Not Vary
                                                                           is it
                                                                         Reasonable
                                                                        to Assume that
                                                                       tr>e Ro* Fiatg
                                                                       Uniform. Steady
                                                                        and Regular''
                                                                           IS it
                                                                         Reasonabto
                                                                        to Assume that
                                                                      the 5» Geometry
                                                                         is Regular
                                                                          Are (ne
                                                                          Selected
                                                                       Remed4aj Actions
                                                                      Reiatrveiy S«mpie in
                                                                        ConAgurason'
                                                                           Does
                                                                       me PoUutant Have
                                                                      ReBBvsty the Same
                                                                         Density as
                                                                          Water?
                                         Do You Have Sufficient
                                        Resources and Available
                                       Data tor Numerical Models?
                               Use Level!: Anarylical Model
                                                                 Use Level II: Numencal Model
                                               Figure 4-4
Flow  Chart for Required  Model Capabilities for Soil and Groundwater Systems
                                       (Boutwell  et. al., 1986)
                                                    134

-------
                                     Design Criteria
5) limitations of the model itself. Therefore,
model  results  should  be  interpreted  as
estimates   of   ground-water   flow  and
contaminant transport.  Bond  and Hwang
(1988) recommend that models be used for
comparing  various  scenarios,   since  all
scenarios  would  be  subject to  the same
limitations and simplifications.

The quality of model results can depend to a
large extent on the experience and judgement
of the modeler, and on the quality of the data
used to develop model input. The process of
applying  the  model may  highlight  data
deficiencies that may require additional data
collection.  The  model results should be
calibrated to obtain the best fit to the observed
data.  The accuracy of the results obtained
from  modeling  efforts  should  then be
validated.   Model validation, which is the
comparison    of   model   results    with
experimental data or environmental data, is a
critical  aspect of model application, and is
particularly   important  for   site-specific
evaluations.

Several  recent reports  present  detailed
discussions  of the issues  associated  with
model selection, application, and validation.
Donigian  and Rao (1990) address each  of
these  issues, and present several options for
developing a framework for model validation.
EPA's  Exposure  Assessment  Group has
developed suggested recommendations and
guidance on model validation (Versar Inc.,
1987).  A  recent  report by the  National
Research Council (1990) discusses the issues
related to  model application and validation,
and provides recommendations for the proper
use of ground-water models.  Weaver et al.
(1989) discuss options for selection and field
validation of mathematical models.
Model Selection

Ground-water  flow  and  solute  transport
models  range  from  simple,   analytical
calculations  to   sophisticated   computer
programs that use numerical solutions to solve
mathematical equations describing flow and
transport.   A sophisticated model may not
yield an exact estimate of water quality at the
relevant point of compliance for a given set of
site conditions, but it may allow an estimate
of  the  effects of complex physical  and
chemical  processes.   Depending  on  the
complexity   of site   conditions   and  the
appropriateness    of    the    simplifying
assumptions, a fairly sophisticated numerical
model may provide useful estimates of water
quality at the relevant point of compliance.

The following  considerations  should  be
addressed when selecting a model.

Analytical Versus Numerical Models

Mathematical models use either  analytical,
semi-analytical, or numerical solutions for
ground-water flow and transport  equations.
Each    technique   has   advantages   and
disadvantages.    Analytical  solutions  are
computationally more efficient than numerical
simulations   and   are  more  conducive  to
uncertainty   analysis   (i.e.,  Monte  Carlo
techniques).    Typically,  input   data  for
analytical models  are simple and do  not
require detailed familiarity with the computer
model   or  extensive  modeling experience.
Analytical solutions are typically used when
data necessary for characterization of the site
are sparse and  simplifying assumptions are
appropriate  (Javandel  et  al., 1984).   The
limited data available in most field situations
may not justify the use of a detailed numerical
model;  in some cases, results from simple
analytical  models  may  be  appropriate
                                           135

-------
                                       Subpart D
(Huyakorn et al., 1986).  Analytical models
require  simplifying assumptions  about  the
system.    Therefore,  complex  interactions
involving several fate and transport processes
cannot be  addressed  in detail.   Analytical
models generally require a limited number of
parameters that are  often assumed to  be
constant in space and time (van der Heijde
andBeljin, 1988).

Semi-analytical models approximate complex
analytical   solutions  using    numerical
techniques (van der Heijde and Beljin, 1988).
Semi-analytical  methods  allow  for  more
complex site conditions than those that can be
simulated with  a purely analytical solution.
Semi-analytical solution methods can consider
multiple    sources    or   recharging   and
discharging wells. However, they still require
simplifying   assumptions    about    the
dimensionality   and  homogeneity  of  the
system.

Numerical models are able to evaluate more
complex site conditions than either analytical
or semi-analytical models. Numerical models
provide the user with  a  large  amount  of
flexibility;  irregular boundaries and  spatial
and temporal variations in the system can be
considered.    Numerical  models  require
significantly  more   data  than   analytical
models,    and    are   typically    more
computationally  intensive.     Use  of   a
numerical  model  requires an experienced
modeler, and can involve a larger amount of
computer time   than  simulations using  an
analytical or semi-analytical method.

To  select  an   appropriate  model,   the
complexity of  the  site  hydrology and  the
availability of data should  be considered.  If
data are insufficient,  a highly sophisticated
and  complex model should not be used.  In
some situations, it is beneficial to use  an
analytical or semi-analytical  model  as  a
"screening level" model to define the range of
possible values, and to use a numerical model
when there are sufficient data.

A highly  complex hydrogeologic  system
cannot  be accurately  represented  with  a
simple analytical  model.  Heterogeneous or
anisotropic  aquifer  properties,   multiple
aquifers,   and    complicated   boundary
conditions can be simulated using numerical
models. In addition, sophisticated numerical
models  are  available  that  can  simulate
processes such as fracture flow. Because each
site is unique, the modeler should determine
which conditions and processes are important
at a specific site, and then select a  suitable
model.

Spatial Characteristics of the System

Although    actual   landfill    units   and
hydrogeologic systems are three-dimensional,
it is often desirable to reduce the number of
dimensions  simulated  in  a mathematical
model  to one  or two.    Two-  and three-
dimensional  models  are  generally  more
complex and computationally expensive than
one-dimensional   models,   and  therefore
require more data. In some instances, a one-
dimensional model may adequately represent
the system; the available data may not warrant
the  use  of  a  multi-dimensional  model.
However, modeling a truly three-dimensional
system using a two-dimensional model may
produce  results  without adequate  spatial
detail.   The  choice  of  the  number   of
dimensions in the model should be made for
a specific site, based on the complexity of the
site and the availability of data.

Steady-State Versus Transient Models

Models can simulate  either steady-state  or
transient flow conditions. It may be
                                           136

-------
                                     Design Criteria
appropriate to assume that some ground-water
flow  systems  have  reached  approximate
"steady-state" conditions, which implies that
the system has reached equilibrium  and  no
significant changes are occurring over time.
The assumption  of steady-state  conditions
generally   simplifies   the   mathematical
equations used to describe flow processes, and
reduces the amount of input data required.

However, assuming steady-state conditions in
a system that exhibits transient behavior may
produce inaccurate  results.  For example,
climatic variables, such as precipitation, vary
over  time and  may have strong seasonal
components. In such settings, the assumption
of  constant recharge of the  ground-water
system  would  be  incorrect.   Steady-state
models  also  may  not  be appropriate  for
evaluating the transport of chemicals which
sorb or transform significantly (Mulkey et  al.,
1989). The choice of simulating steady-state
or transient conditions should be based on  the
degree of temporal variability in the system.

Boundary and Initial Conditions

The  solution   of  differential  equations
describing flow  and  transport  processes
requires that initial and boundary conditions
be specified.  The initial  conditions describe
the conditions  present in the  system at  the
beginning of the simulation.  In many ground-
water  flow  and  transport models, these
conditions are related to the initial hydraulic
conditions in  the  aquifer and  the  initial
concentration  of contaminants.   Boundary
conditions define the conditions present on  the
borders  of the system, which may be  steady-
state or temporally variable. The initial and
boundary conditions chosen to represent a site
can  significantly  affect  the  results  of  the
simulation.
One  of  the  most  significant  boundary
conditions in solute transport models is the
introduction of a contaminant to the system.
A source  of ground-water  contamination
should be described in terms of its  spatial,
chemical, and physical characteristics, and its
temporal behavior.  Spatially, a source may be
classified  as  a point  source, line source, a
distributed source  of limited areal or three-
dimensional extent, or as a non-point source
of unlimited extent (van der Hjeide  et al.,
1988). Typically, temporal descriptions of the
source term boundary conditions for models
with analytical solutions are constant, constant
pulse, and/or exponential decay (Mulkey et
al., 1989).  Numerical models typically handle
a much wider  range  of source boundary
conditions, allowing  for a wide range of
contaminant loading scenarios.
Homogeneous    Versus
Aquifer/Soil Properties
Heterogeneous
The extent of the spatial variability of the
properties of each aquifer will significantly
affect the selection of a mathematical model.
Many   models  assume  uniform   aquifer
properties,  which  simplifies the governing
equations  and   improves   computational
efficiency.  For example, a constant value of
hydraulic conductivity may be  assumed at
every point in  the aquifer.   However, this
assumption may ignore the heterogeneity in
the hydrogeologic system. Bond and Hwang
(1988)  present guidelines for determining
whether the assumption  of uniform aquifer
properties is justified at a particular site.
They state that the error associated with using
an average value versus a spatial distribution
is  site-specific and extremely  difficult  to
determine.

When  site-specific data are  limited,  it is
common  to  assume  homogeneous  and
                                           137

-------
                                        Subpart D
isotropic aquifer properties, and to develop a
"reasonable   worst-case"    scenario   for
contaminant  migration in the  subsurface.
However, as Auerbach (1984) points out, the
assumption of homogeneous  and isotropic
aquifers often will not provide a "worst-case"
scenario.  For example, a continuous zone of
higher hydraulic conductivity in the direction
of ground-water flow can  result in much
higher rates of contaminant movement than
would  be  predicted   in   a  completely
homogeneous aquifer.   To develop a  true
"worst-case"  model,  information  on  the
probable heterogeneity and anisotropy of the
site should be collected.

The number of aquifers in the hydrogeologic
system  also  will affect  the  selection of a
mathematical model.  Some systems include
only a single unconfmed or confined aquifer,
which is  hydraulically  isolated from  the
surrounding  layers.   Some  mathematical
models, and in particular those with analytical
solutions, can simulate only single layers. In
other cases,  the  upper aquifer  may  be
hydraulically   connected   to  underlying
aquifers.  The MSWLF Criteria specify  that
MCLs not be exceeded at the relevant point of
compliance within the uppermost aquifer.
The  uppermost aquifer includes not only the
aquifer that is nearest the  ground surface, but
also  all  lower aquifers that are hydraulically
connected to the uppermost aquifer within the
vicinity of the facility.

Availability of Data

Although computer  models can be used to
make predictions about leachate generation
and  migration,  these predictions are highly
dependent on the quantity and quality of the
available data.  One of the  most common
limitations to modeling is insufficient data.
Uncertainty in model predictions results from
the inability to characterize a site in terms of
the boundary conditions or the key parameters
describing the significant flow and transport
processes (National Research Council, 1990).
The application of a mathematical model to a
site typically requires a large amount of data.
Inexperienced modelers may attempt to apply
a model with insufficient data and, as a result,
produce model results that are inconclusive.

To obtain  accurate  model results,  it is
essential to  use data that are appropriate for
the particular site being modeled. Models that
include generic parameters,  based on average
values for similar sites, can be used to provide
initial guidance and general information about
the  behavior  of  a  system,  but  it is
inappropriate to apply generic parameters to a
specific hydrogeologic system. An excellent
summary of the  data required  to model
saturated and unsaturated flow, surface water
flow,  and solute transport is presented in
Mercer et al. (1983).  This report provides
definitions and possible ranges of values for
source terms, dependent variables, boundary
conditions, and initial conditions.

Summary of Available Models

Several detailed  reviews  of  ground-water
models are  available  in the literature.  A
number of ground-water models, including
saturated flow, solute transport, heat transport,
fracture flow,  and multiphase flow models,
are summarized  in van der Heijde  et al.
(1988).  A report by van der Heijde and Beljin
(1988) provides detailed descriptions of 64
ground-water  flow and  solute  transport
models  that  were selected  for  use  in
determining wellhead  protection areas.  A
review of ground-water flow and
                                           138

-------
                                     Design Criteria
transport models for the unsaturated zone is
presented in Oster (1982).  A large number of
ground-water flow and transport models are
summarized by Bond  and Hwang  (1988).
Finally, Travers and  Sharp-Hansen (1991)
summarize models that may be applicable to
problems of leachate generation and migration
from  MSWLF  units.    (See References
supplied in Section 4.6.)

Table 4-1 (adapted from Travers and Sharp-
Hansen  (1991))  provides  information  on
select leachate generation models.  Tables 4-
la, b,  and c list some of the available models
that  can  be  used  to  predict contaminant
transport. The factors used to select  these
models  include availability, documentation,
uniqueness,   and   the  size  of  the  user
community. These models are categorized by
the techniques used  to  solve  flow  and
transport  equations.    Table 4-la   lists
analytical and semi-analytical models, and
Tables 4-lb  and 4-lc  list numerical  models
that are solved by the finite-difference and the
finite-element method, respectively.

The types of models  that are available  for
application to the  evaluation of MSWLF
designs  include leachate generation  models
and saturated and  unsaturated zone flow and
transport models.  The level of sophistication
of each  of these types of models is based on
the complexity   of the  processes  being
modeled.    The  majority  of the  models
consider  flow and  transport  based  on
advection  dispersion  equations.    More
complex  models   consider   physical  and
chemical transformation processes, fracture
flow,  and multiphase fluid flow.

Leachate  generation  models  predict  the
quantity and characteristics of leachate that is
released from the bottom of a landfill. These
models are used to estimate
contaminant source terms and the releases of
contaminants to the subsurface.  Flow and
transport models simulate the transport of
contaminants released from the source to the
unsaturated     and    saturated     zones.
Geochemical  models  are  available  that
consider chemical processes that  may be
active in the subsurface such as adsorption,
precipitation,  oxidation/reduction,  aqueous
speciation, and kinetics.

Complex flow models have been developed to
simulate the effects of nearby pumping and
discharging wells, fracture flow, conduit flow
in karst terrane, and multiphase flow for fluids
that are  less  dense or more dense than water.
However, the  use  of the  more  complex
models  requires additional data based on a
thorough  investigation  of  the  subsurface
characteristics at a site as well as well-trained
users to apply the model correctly.

Most  of the ground-water flow  and solute
transport models are deterministic. However,
the use of stochastic models, which allow for
characterization of spatial  and  temporal
variability in systems, is increasing. A few of
the models include a Monte Carlo capability
for addressing the uncertainty inherent in the
input parameters.

The EPA Multimedia Exposure
Assessment Model (MULTIMED)

EPA has developed a modeling package to
meet  the needs of a  large percentage of
MSWLF unit owners and operators who will
require fate and transport modeling as part of
the performance-based design demonstration.
This  model,   the  Multimedia  Exposure
Assessment   Model   (MULTIMED),   is
intended for  use at   sites  where  certain
simplifying   assumptions can   be  made.
MULTIMED can be used in
                                          139

-------
Table 4-1. Models for Application to Leachate Generation Problems (adapted from Travers and Sharp-Hansen, 1991)
Model
Reference
Bonazountas
and Wagner
(1984);
SESOIL
Carsel et al.
(1984) PRZM
EPRI (1981)
UNSAT1D
Knisel et al.
(1989)
GLEAMS
Schroeder et
al. (1984)
HELP
Model Flow Aquifer
Dimensions Conditions Conditions
1D/FD Ss.Unsat L,Hom,Iso
9
1D/FD Usat.Ss.Tr L.Hom.Iso
1D/FD Sat.Usat, Het.Hom.L
Ss.Tr Iso
1D/FD Usat.Tr.Ss Hom.Iso.L
quasi-2D FD Tr.Sat.Usat L.Homo,
Iso
Model
Processes
Ppt.Inf,
RO.ET,
Adv.Dif,
Ads.Vol,
Dec
Adv.Dis,
Dif.Dec,
Rxn.ET,
Vol.Inf
Ppt.Inf,
RO.ET
Inf.Dec.R
O.ET.Ads
ET.Ppt.In
f.Dra.RO
Chemical Additional Information
Species
single Seasonal Soil Compartment Model. Simulates transport of
water, sediment, and contaminants in soils. Includes affects of
capillary rise, biological transformation, hydrolysis, cation
exchange, complexation chemistry (metals by organic ligands).
Hydrology based on generalized annual water balance
dynamics model.
1 ,2, or 3 Pesticide Root £one M_odel. Also includes plant uptake,
leaching, runoff, management practices, and foliar washoff.
Hydrologic flow solved by water routing scheme, chemical
transport solved by finite difference scheme. Requires
meteorological data. Water balance model.
flow only Solves one-dimensional Richard's equation. Accounts for
capillary and gravitational effects. Requires landfill design
data.
single Groundwater Loading Effects of Agricultural Systems model.
Developed by modifying CREAMS (Knisel, 1980) to add
capability to estimate groundwater loadings. Simulates
erosion. Water balance computations.
flow only A quasi-two-dimensional, deterministic water budget for
landfills. Requires landfill design data. Model may be applied
to open, partially open, and closed landfills. Requires
meteorological data.
   ID  = One-dimensional        Sat
   2D  = Two-dimensional       Usat
   3D  = Three-dimensional      Horn
   H   = Horizontal             Het
   V   = Vertical               Iso
   Ss  = Steady-State           An
   Tr  = Transient              C
Saturated             Uc
Unsaturated          Adv
Homogeneous         Dis
Heterogeneous        Dif
Isotropic             Dec
Anisotropic          Ads
Confined Aquifer      Ret
Unconfined aquifer      In
Advection             ET
Decay                Ppt
Diffusion             RO
Decay                Run
Adsorption            W
Retardation            L
Infiltration
Evapotranspiration
Precipitation
Runoff
Reaction
Discharge or pumping wells
Layers

-------
         Table 4-la.  Analytical and Semi-Analytical Models for Application to Leachate Migration Problems
                                      (adapted from Travers and Sharp-Hansen, 1991)
   Model        Model        Flow        Aquifer        Model       Chemical
 Reference    Dimensions   Conditions   Conditions     Processes      Species
                                                                    Additional Information
Bcljin (1983)  ID(H), 2D(H)  Ss, Sat
SOLUTE      or 3D
             C,  Horn, Iso    Adv, Dis, Ads, single
                            Dec
             A package of 8 analytical models for solute transport
             in groundwater.  Also includes a program lor unit
             conversion and error and function calculation.
Domcnicoand  IDadvection    Ss, Sal
Palciauakcs    2D dispcrsioh
(1982) VMS
             C, Horn, Iso    Adv, Dis
single
Model for Vertical and Horizontal Spreading.
Assumes infinite aquifer thickness.  EPA considers
VHS to he a conservative model since retardation,
sorptions, precipitation, aquifer recharge not
considered. Source is continuous constant strip source.
Domenico and  3D (transport)  Ss, Sat       C, Horn, Iso    Adv, Dis       single
Rohbms
(1985)
Huyaknm el   3D            Ss, Sal       C, Uc, Horn,    Adv, Dis, Ads,  single
;U. (1987)                                 Iso, An        Dec
                                                       Conlaminanl transport from a finite or continuous
                                                       source in a continuous flow regimen. Assumes infinilc
                                                       thickness.
                                                        Model allows for estimation of maximum
                                                        concentration distribution along center line of a
                                                        leachate plume. Gaussian vertical strip source.
Javandcl ct    2D(H)
al. (1984)
RESSQ

Lindstrom    1D(H)
and Bocrams
(1989)
CXPHPH
Ss, Sat       C, Horn, Iso    Adv, Ads       single
Ss, Sat       C, Horn,  Iso    Adv, Dis, Dec,  single
                            Ads, Rxn
             Calculate transport by advcclion and adsorption in a
             homogeneous, isotropic, uniform-thickness, confined
             aquifer. Uses semi-analytical solution methods.

             Analytical solutions of the general  one-dimensional
             transport equation for confined aquifers, will) several
             differenl initial and boundary conditions.
Nelson and    2D(H)
Schur(1983)
PATHS
Ss, Tr, Sat    C, Horn, Iso    Adv, Ads       single
             Groundwater How equations solved analytically,
             characteristic pathlines solved by Ruage-Kulls method.
Ostcndorf cl    ID(H.V)      Ss, Sat        Uc, Horn, Iso   Adv, Ads, Dec  single
al.  (1984)
                                                        Assumes transport of a simply reactive contaminant
                                                        through a landfill and initially pure, underlying,
                                                        shallow, aquifer with  plane, sloping bottom.
Prakash        ID, 2D or 3D   Ss, Sat        C, Horn, Iso    Adv, Dis, Ads,  single
(1984)                                                   I**
                                                        Source boundary condition:  instantaneous or finite-lime
                                                        release of contaminants from a point, line, plane, or
                                                        parallel piped source.

-------
         Table 4-la. Analytical and Semi-Analytical Models for Application to Leachate Migration Problems
                                (adapted from Travers and Sharp-Hansen, 1991) (continued)
   Model
  Reference
   Model
 Dimensions
Salhotrc el     lD(vadosc
al. (1990)     /one), 3D
MULTIMED  (transport in
              saturated /.one)
   Flow
Conditions

Ss, Sal, Usai
Unge cl al.
(1986);
Summers cl
al. (1989)
MYGRT
(Version 1.0,
2.0)
I,2(H,V)
Ss, Sat
   Aquifer
 Conditions

tic, Horn,  Iso,
I. (Usal)
 Model
Processes
Chemical
 Species
                                          Adv, Dis, Ads,  single
                                          Dec, Vol
tic, Horn, Iso   Adv, Dis, Rel,   single
               Dec
Additional Information
van           1D(H,V)       Ss, Sal
Gcnuchtcn
and Alvcs
(1982)
Yen (1981)    ID, 2D or 3D   Tr, Sal
AT123D
                            C, Horn, Iso    Adv, Dis, Dif,  single
                                           Ads
                            C, Uc,  Horn,    Adv, Dis, Dif,  single
                            Iso, An        Ads, Dec
                          Model simulates movement of contaminants in
                          saturated and unsaluraled groundwaler /.ones. In
                          surface water and emissions lo air.  Includes Monte
                          Carlo capability. Unsalurated zone transport solution
                          is analytical, saturated zone is semi-analytical.
                          Gaussian or palch source boundary condition.

                          Simulates migration of organic and inorganic solulcs.
                          Constant pulse source boundary condition.  Proprietary
                          code.
                                                        Three types of source boundary conditions are
                                                        considered: constant, exponential decay, and pulse step
                                                        function.
                                                        Analytical, semi-analytical, solution techniques based
                                                        on Green's function. Source boundary conditions
                                                        include: constant, instantaneous pulse, or finite-lime
                                                        release from a point, line, area, or volume source
 ID   =   One-dimensional       Sal
 2D   =   Two-dimensional      Usal
 3D   =   Three-dimensional     Horn
 II    =   Horizontal           Hel
 V    =   Vertical              Iso
 Ss    =   Steady-state          An
 Tr   =   Transient             C
                         Saturaled             Uc
                         Unsaluratcd          Adv
                         Homogeneous         Dis
                         Heterogeneous        Dif
                         Isolropic             Dec
                         Anisotropic          Ads
                         Confined aquifer      Ret
                                        Unconfincd aquifer    Inf
                                        Adveclion            ET
                                        Dispersion            Ppl
                                        Diffusion             RO
                                        Decay                Rxn
                                        Adsorption           W
                                        Retardation           L
                                                         Infiltration
                                                         Evapoiranspiralion
                                                         Precipitation
                                                         Run-off
                                                         Reaction
                                                         Discharge or pumping wells
                                                         layers

-------
Table 4-lb. Finite-Difference Models for Application to Leachate Migration Problems
                 (adapted from Travers and Sharp-Hansen, 1991)
	 	 --••
Model Model
Reference Dimensions
Ahriclc and ID
Pinder (19X3)
»
Dillion ct al. 3D
(1981; 1986)
SWIFT/
SWIFT II
Erdogcnand ID
Hcufcld
(1983)
GeoTrans 3D
(1985); Faust
el al. (1989)
SWAN-
FLOW
Kipp(1987) 3D
NST3D
Konikow and 2D (H,V)
Bradshocfl
(1985)
USGS-NOC
Flow Aquifer
Conditions (Conditions
Ss, Tr, Sat, Uc, Iso, Horn
Usal
Ss, Tr, Sat C, Horn, Het,
Iso, An
Tr, Sal Horn, Iso
Ss, Tr, Sat, Uc, Horn, Hot,
Usat Iso, An
Tr, Sat C, Uc, Horn,
Hcl, Iso, An
Ss, Tr, Sat C, Uc, Horn,
Hel, Iso, An
Model Chemical
Processes Species
Dis. Dif multiphase
Adv, Dis, Dif, single
Dec, Rxn, W
Adv, Dis, Ads, single
Ppt
multiphase
Adv, Dis, Dif, single
Ads, Dec, W
Adv, Dis, Dif, single
Ads, Dec, ET,
W
Additional Information
Multiphase model for modeling aquifer contamination
by organic compounds. Simulates simultaneous
transport of contaminant in a nonaqucous phase,
aqueous phase and as a mobile fraction of gas phase.
Effects of capillarity, interphase mass transfer,
diffusion, and dispersion considered.
Coupled groundwaler flow, and heal or solute
transport. Includes fracture flow, ion exchange, salt
dissolution, in confined aquifer. SWIFT-II includes
dual porosity for fractured media.
Model describes the desorption process using
intraparliclc and external file diffusion resistances as
rate controlling mechanism (considers fluid velocity
and particle si/e). Predicts Icachale concentration
profiles at the boundary of the landfill. Simulates
precipitation with interrupted flow condilions.
Faust (1989) extends SWANFLOW to include a
solution technique which lakes advantage of parallel
computer processing.
Simulates coupled density dependent groundwater flow
and heal or mass transport in an anisotropic,
heterogeneous aquifer.
Groundwater flow solved by finite difference, solute
transport by the melliod of characteristics.

-------
                Table 4-lb. Finite-Difference Models for Application to Leachate Migration Problems
                             (adapted from Travers and Sharp-Hansen, 1991) (continued)
Model
Reference
Harasiinhiin
cl al. (1986)
DYNAMIX
Prickctt cl al.
(19X1)
RANDOM
WALK or
TRANS
Ruachcl
(1985)
PORFLOW-
11 and III
Travis (1984)
TRACR3D
Walton
(1984) 35
Micro-
computer
Programs
Model
Dimensions
3D
ID or 2D(H)
2D(H,V) or
3D
3D
ID, 2D(H) or
3D (radial,
cyl)
Flow Aquifer
Conditions Conditions
Ss, Tr, Sal C, Uc, Horn,
Hcl, Iso, An
Ss, Tr, Sal C, Uc, Horn,
I lei, Iso, An,
L
Ss, Tr, Sal C, Uc, Horn,
Hct, Iso, An,
L.
Ss, Tr, Sat, C, Horn, Het,
Usat Iso, An
Ss, Tr, Sal C, Uc, Horn,
Hel, L
Model
Processes
Adv, Dis, Dif,
Dec
Adv, Dis, Ads,
Dec, ET, W
Adv, Dis, Dif,
Ads, Dec,
Rxn, W
Adv, Dis, Dif,
Ads, Dec
Adv, Dis, Rel
Chemical
Species
multiple
single
single
two-phase,
multiple
single
Additional Information
Model couples a chemical specification model
PHREEQE (Parkhursl cl al, 1980) with a modified
form of the transport code TRUMP (Edwards, 1969,
1972). Considers equilibrium reactions (see
gcochcinical codes).
Finite difference solution lo groundwatcr How,
random walk approach used lo simulate dispersion.
Simulates random movement. Aquifer properties vary
spatially and temporally.
Simulates density dependent How, heat and mass
transport. Aquifer and fluid properties may he
spatially and temporally variable. Integrated finite
difference solution. Includes phase change.
Simulates transient two-phase flow and multi-
component transport in deformablc, heterogeneous,
reactive, porous media.
A series of analytical and simple numerical programs
lo analyze flow and transport of solutes in aquifers
with simple geometry.
ID   =   One-dimensional      Sat
2D   =   Two-dimensional     Usat
3D   =   Three-dimensional    Horn
H    =   Horizontal          Hct
V    =   Vertical            Iso
Ss   =   Steady-slate         An
Tr   =   Transient            C
Saturated
Unsaturaled
Homogeneous
Heterogeneous
Isotropic
Anisotropic
Confined aquifer
Uc   =   Unconfined aquifer    Inf
Adv  =   Advection           ET
Dis   =   Dispersion           Ppt
Dif   =   Diffusion            RO
Dec   =   Decay               Rxn
Ads  =   Adsorption          W
Ret   =   Retardation          L
Infiltration
Evapotranspiration
Prccipilalion
Run-off
Reaction
Discharge or pumping wells
Layers

-------
Table 4-lc. Finite-Element Models for Application to Leachate Migration Problems
               (adapted from Travers and Sharp-Hansen, 1991)
Model
Reference
Ccdcrbcrg el
al. (1985)
TRANQL
(19X9)
RUSTIC
Gupla el al.
(1982)
CFEST
Gureghian el
al. (1980)
Guvanssen
(1986)
NOT IF
Haji-Djalari
and Wells
(1982)
GEOFLOW
Huyakorn et
al. (1984)
SEFTRAN
Huyakorn el
al. (1986)
TRAFRAP
Osbomc and
Sykes(1986)
WST1F
Model
Dimensions
1 D, radial
vadose /.one);
2DH.V, radial
(saturated
/one)
2D(H,V) or
3D
2D
ID, 2D, or 3D
3D
ID or
2D(H,V)
2D(H,V)
2D
Flow
Conditions
Ss, Sat
Ss Tr Usat
Sal
Ss, Tr, Sal
Ss, Sal
Ss, Tr, Sal,
Usat
Ss, Tr, Sal
Ss, Tr, Sal
Ss, Tr, Sat
Tr, Sat, Usat
Aquifer
Conditions
C, Uc, Horn
C Uc Horn
Hct, Iso, An,
L
C, Uc, Horn,
Hel, Iso, An,
L
C, Uc, Iso, An
C, Uc, Horn,
Hel, Iso, An
C, Uc, Horn,
Hel, Iso, An,
L
C, Uc, Horn,
Hel, Iso, An,
L
C, Uc, Horn,
Hel, Iso, An
Uc, Horn, Hel,
Iso, An, L
Model
1'rocesses
Adv, Dis, Dif,
Ads, Dec
Adv, Dis, Ads,
Dif, Dec, ET,
W, Ppt, RO,
Ret
Adv, Dis, Dif,
Ads, Dec, W
Adv, Dis, Ads,
Dec
Adv, Dis, Dif,
Ads, Dec
Adv, Dis, Dif,
Dec, Rxn, Rel,
W
Adv, Dis, Dif,
Ads, Dec, W
Adv, Dis, Dif,
Ads, Dec,
Rxn, W

Chemical
Species
multiple
1, 2, or 3

single
single
single
single
single
single
two- phase
Additional Information
Multicomponenl transport model which links chemical
equilibrium code MICROQL (Weslfall, 1976) and
transport axle ISOQUAD (Pinder, unpublished
manuscripl, 1976). Includes a complexation in aqueous
phase.
Simulates fate and transport of chemicals through three
linked modules: root, values, and saturated /one.
Includes PRZN (Carsel et al., 1984). RUSTIC is in
Beta-lcsling phase. Includes Monte Carlo capability
PRZN solution by finite difference.
Solves coupled groundwater How, solute and heat
transport equations. Fluid may be heterogeneous.
Source boundary condition: Gaussian distributed
source. Transport only.
Groundwaler How and solute transport in fractured
porous media.
Simulation of arcal configuration only. Proprietary
axle.
Proprietary axle.
Simulates groundwater Row and solute transport in
fractured porous media. Includes precipitalion.
Model sirnulales Iransporl of immiscible organics in
groundwater. Assumes no mass transport belween
phases.

-------
                 Table 4-lc. Finite-Element Models for Application to Leachate Migration Problems
                             (adapted from Travers and Sharp-Hansen, 1991) (continued)
Model Model
Reference Dimensions
Thcis ct al. ID
(14X2)
FIESTA


van 1D(V)
Gcnuchlen
(1978)
SUMATRA-
I
Voss (19X4) 2D(H,V)
SUTRA

Ychand 2D(H,V)
Ward (1981)
FEMWATER
FEM WASTE

Ych (1990) 2D/3D
LEWASTE,
3DLEWASTE



Flow
Conditions
Sal




Tr, Sat, Usat




Ss, Tr, Sat,
Usat

Ss, Tr, Sat,
Usat



Ss, Tr, Sat,
Usat




Aquifer
Conditions
Horn, Iso




C, Uc, Horn,
Hcl, Iso, L



C, Uc, Horn,
Hct, Iso, An

Uc, Horn, Hct,
Iso, An



Uc, C, Horn,
Hct, Iso, An




Model
Processes
Adv, Dis, Ads,
Dec



Adv, Dis, Ads,
Dec, Ret



Adv, Dis, Oil,
Ads, Dec,
Rxn, W
Adv, Dis, Ads,
Dec, Ppt, W



Adv, Dis, Ads,
Dec, W




Chemical
Species Additional Information
multiple Combinations of a component transport model, FEAP,
and the chemical equilibrium speciation model
NINEQL (Wcstfall el al. 1976). Simulates up to 6
chemical components, including all solution and sorhcd
phase complexes.
single Simulates simultaneous How of water and solutes in a
one-dimensional, vertical soil profile.



single Fluid may be heterogeneous (density-dependent
groundwaler flow).

single FEMWATER simulates groundwaler flow.
FEMWASTE simulales waste Iransporl through
saturated unsaturaled porous media. Simulates
capillarity, infiltration, and recharge/discharge -sources
(e.g., lakes, reservoirs, and streams).
single Transport codes based on (lie Lagrangian-Eulcrian
approach, can be applied to Pcciel Numbers from 0 lo
infinity. LEWASTE is intended to simulate 2D local
How systems. 3DLEWASTE can simulate regional or
local flow systems. The LEWASTE series replaces the
FEMWASTE models.
ID   =   One-dimensional      Sat  =
2D   =   Two-dimensional     Usat =
3D   =   Three-dimensional    Horn =
II    =   Horizontal          Hct  =
V    =   Vertical            Iso  =
Ss    =   Steady-slate         An  =
Tr   =   Transient            C •   =
Saturated            Uc
Unsaturaied         Adv
Homogeneous        Dis
Heterogeneous       Dif
Isolropic            Dec
Anisolropic         Ads
Confined aquifer      Re I
Unconfincd aquifer    Inf
Adveclion           ET
Dispersion           Ppl
Diffusion           RO
Decay              Rxn
Adsorption          W
Retardation          L
Infiltration
Evapolranspiralion
Precipilation
Run-off
Reaction
Discharge or pumping wells
Layers

-------
                                     Design Criteria
conjunction with a separate leachate source
model, such as HELP (Schroeder et al., 1984).
Output  from  HELP   is  then  used   in
MULTIMED to demonstrate  that either a
landfill design or the specific hydrogeologic
conditions  present at  a site  will  prevent
contaminant concentrations in  ground water
from exceeding the concentrations listed in
Table 1 of §258.40. (Refer to pp. 4-53 and 6-
8  for  further discussion of  HELP.)    A
description of  MULTIMED   follows with
guidance  for determining  if its  use  is
appropriate for a given site.

[NOTE: Version 3.0 of the HELP model will
be available  during the  fall of  1993.   To
obtain a copy, call EPA's Office of Research
and Development  (ORD) in  Cincinnati at
(513)569-7871.]

Overview of the Model

The MULTIMED model consists of modules
that estimate contaminant releases to air,  soil,
ground water, or  surface water.  General
information about the model and its theory is
provided   in   Salhotra   et   al.   (1990).
Additionally,    information   about    the
application of MULTIMED to MSWLF units
(developed  by Sharp-Hansen et al. [1990]) is
summarized here. In MULTIMED, a steady-
state,    one-dimensional,   semi-analytical
module simulates  flow in the unsaturated
zone.  The output from this module, which is
water saturation as a function of depth, is used
as input to the unsaturated zone transport
module.  The latter simulates transient, one-
dimensional  (vertical)   transport   in   the
unsaturated zone and includes  the effects of
dispersion,  linear adsorption, and first-order
decay.  Output from  the unsaturated zone
modules is used as input to the semi-analytical
saturated zone transport module.  The latter
considers three-dimensional flow
because  the  effects of lateral or  vertical
dispersion may significantly affect the model
results.

Therefore, reducing the dimensions to one in
this module would produce inaccurate results.
The saturated zone  transport  module  also
considers linear adsorption, first-order decay,
and  dilution  as  a  result  of ground-water
recharge.  In  addition, MULTIMED has the
capability to assess the impact of uncertainty
in the model inputs on the model  output
(contaminant concentration  at  a specified
point), using the  Monte  Carlo simulation
technique.

The simplifying  assumptions  required  to
obtain the  analytical  solutions  limit  the
complexity  of the  systems that  can be
evaluated with MULTIMED.  The model  does
not account for site-specific spatial variability
(e.g., aquifer heterogeneities), the shape of the
land disposal facility, site-specific boundary
conditions, or multiple aquifers and pumping
wells.    Nor can  MULTIMED  simulate
processes,  such as  flow  in fractures  and
chemical reactions between contaminants, that
may  have  a  significant   effect   on   the
concentration of contaminants at a site.  In
more complex systems, it may be beneficial to
use MULTIMED as a "screening level" model
to allow the user to obtain an understanding of
the system.   A more complex model could
then be used if there are sufficient data.

Application of MULTIMED to MSWLF
Units

Procedures have been  developed  for  the
application of MULTIMED to the design of
MSWLF units. They are explained in Sharp-
Hansen   et   al.   (1990)  and   are  briefly
summarized here. The procedures are:
                                          147

-------
                                       Subpart D
•    Collect site-specific hydrogeologic data,
     including amount of leachate generated
     (see Section 4.3.3);

•    Identify  the  contaminant(s)   to  be
     simulated and the point of compliance;

•    Propose a landfill design and determine
     the corresponding infiltration rate; then

•    Run MULTIMED  and  calculate  the
     dilution attenuation factor (DAF) (i.e.,
     the factor by which the concentration is
     expected  to  decrease   between  the
     landfill   unit    and   the   point   of
     compliance); and

•    Multiply   the   initial   contaminant
     concentration by the DAF and compare
     the resulting concentration to the MCLs
     to determine if the design will meet the
     standard.

At this time, only contaminant transport in the
unsaturated  and/or saturated  zones can be
modeled, because the other  options (i.e.,
surface  water,  air)  have  not  yet been
thoroughly tested. In addition, only steady-
state transport simulations are allowed.  No
decay  of the contaminant source term is
permitted; the concentration of contaminants
entering the aquifer system is assumed to be
constant over time.   The  receptor  (e.g.,  a
drinking water  well) is  located directly
downgradient of the facility and intercepts the
contaminant  plume;  also,  the contaminant
concentration is calculated at the top  of the
aquifer.

The  user  should   bear  in   mind  that
MULTIMED may  not be an  appropriate
model for some sites.  Some of the issues that
should be considered before modeling efforts
proceed are summarized in Table
4-2.  A "no" answer to any of the questions in
Table 4-2 may indicate that MULTIMED is
not the most appropriate model to use.  As
stated above, MULTIMED utilizes analytical
and  semi-analytical solution  techniques  to
solve the mathematical equations describing
flow  and  transport.    As   a result,  the
representation of a system simulated by the
model is simple, and  little or no spatial  or
temporal  variability  is  allowed  for  the
parameters in the system. Thus,  a  highly
complex hydrogeologic  system cannot be
accurately represented with MULTIMED.

The   spatial   characteristics   assumed  in
MULTIMED  should  be  considered  when
applying  MULTIMED  to  a  site.    The
assumption  of  vertical,  one-dimensional
unsaturated flow may be valid for facilities
that   receive   uniform   areal   recharge.
However, this assumption may not be valid
for facilities where surface soils (covers  or
daily backfill) or surface slopes result in an
increase  of  run-off in certain areas  of the
facility,  and ponding of  precipitation  in
others.  In addition, the simulation of one-
dimensional, horizontal flow in the saturated
zone    requires   several    simplifying
assumptions. The saturated zone is treated as
a  single,  horizontal  aquifer  with uniform
properties (e.g., hydraulic conductivity). The
effects of pumping or discharging wells on the
ground-water   flow   system   cannot  be
addressed with the MULTIMED model.

The MULTIMED model assumes steady-state
flow in all applications.  Some ground-water
flow systems are in an approximate "steady-
state," in which the amount of water entering
the flow system equals the amount of water
leaving  the system.   However,  assuming
steady-state  conditions in a system that
exhibits  transient  behavior  may  produce
inaccurate results.
                                           148

-------
                                   Design Criteria
              TABLE 4-2
      ISSUES TO BE CONSIDERED
    BEFORE APPLYING MULTIMED
      (from Sharp-Hansen et al., 1990)
Objectives of the Study

•  Is a "screening level" approach
   appropriate?
•  Is modeling a "worst-case scenario"
   acceptable?

Significant Processes Affecting Contaminant
Transport

•  Does MULTIMED simulate all the
   significant processes occurring at the site?
•  Is the contaminant soluble in water and of
   the same density as water?

Accuracy and Availability of the Data

•  Have sufficient data been collected to
   obtain reliable results?
•  What is the level of uncertainty associated
   with the data?
•  Would a Monte Carlo simulation be
   useful? If so, are the cumulative
   probability distributions for the parameters
   with uncertain values known?

Complexity of the Hydrogeologic System

•  Are the hydrogeologic properties of the
   system uniform?
•  Is the flow in the aquifer uniform and
   steady?
•  Is the site geometry regular?
•  Does the source boundary condition
   require a transient or steady-state solution?
MULTIMED  may  be  run  in  either  a
deterministic or a Monte Carlo mode.  The
Monte  Carlo method provides a means of
estimating the uncertainty in the results of a
model, if the uncertainty of the input variables
is known or  can be estimated.  However, it
may be difficult to determine the cumulative
probability distribution for a given parameter.
Assuming a parameter probability distribution
when the distribution is unknown does not
help reduce  uncertainty.  Furthermore, to
obtain a valid estimate of the uncertainty in
the output, the  model must be run numerous
times (typically several hundred times), which
can be time-consuming.  These issues should
be considered  before  utilizing  the  Monte
Carlo technique.
4.3  COMPOSITE LINER AND
     LEACHATE COLLECTION
     SYSTEM
     40 CFR §258.40

4.3.1 Statement of Regulation

     (a) New MSWLF  units  and lateral
expansions shall be constructed:

     (1)  See Statement  of Regulation  in
Section 4.2.1 of this guidance document for
performance-based design requirements.

     (2) With a composite liner, as defined
in  paragraph  (b)  of this  section  and  a
leachate collection system that is designed
and constructed to maintain less than a 30-
cm depth of leachate over the liner,

     (b)  For  purposes of this section,
composite liner means a system consisting
of two components; the upper component
must consist of a minimum 30-mil flexible
                                         149

-------
                                       Subpart D
membrane  liner (FML),  and the  lower
component must consist of at least a two-
foot  layer  of  compacted  soil  with  a
hydraulic conductivity of no more than 1 x
10~7 cm/sec. FML components consisting of
high density polyethylene (HDPE) shall be
at least 60-mil thick.  The FML component
must be installed in direct and uniform
contact   with   the   compacted    soil
component.

4.3.2  Applicability

New  MSWLF  units and  expansions  of
existing  MSWLF units in States without
approved programs must be constructed with
a composite liner and a leachate collection
system (LCS) that is  designed to maintain a
depth of leachate less than 30 cm (12 in.)
above the liner. A composite liner consists of
a flexible membrane liner (FML) installed on
top of, and in direct and uniform contact with,
two feet of compacted soil. The FML must be
at least 30-mil thick unless the FML is made
of FIDPE, which must be 60-mil thick. The
compacted soil liner must be at least two feet
thick and must have a hydraulic conductivity
of no more than 1 x 10"7 cm/sec.

Owners  and  operators  of MSWLF  units
located in approved States have the option of
proposing  a   performance-based  design
provided that certain  criteria can be met (see
Section  4.2.2).

4.3.3 Technical Considerations

This  section  provides  information on the
components  of composite  liner  systems
including soils, geomembranes, and leachate
collection systems.
Standard Composite Liner Systems

The  composite  liner system  is an effective
hydraulic  barrier  because it combines the
complementary properties of two different
materials into one system: 1) compacted soil
with a low hydraulic conductivity; and
2) a FML (FMLs  are also referred to as
geomembranes). Geomembranes may contain
defects including  tears, improperly bonded
seams, and pinholes.  In the absence of an
underlying low-permeability  soil liner, flow
through  a defect in  a geomembrane is
essentially unrestrained.   The presence of a
low-permeability soil liner beneath a defect in
the geomembrane reduces leakage by limiting
the flow rate through the defect.

Flow through the soil component of the liner
is controlled by the size of the defect in the
geomembrane, the available air space between
the two liners into which leachate can flow,
the  hydraulic  conductivity  of  the   soil
component, and the hydraulic head.  Fluid
flow through soil liners is calculated  by
Darcy's  Law,  where  discharge  (Q)  is
proportional to the head loss through the soil
(dh/dl) for a given cross-sectional flow area
(A) and hydraulic  conductivity (K) where:

     Q = KA(dh/dl)

Leakage  through  a geomembrane  without
defects is controlled by Pick's first law, which
describes  the process  of liquid  diffusion
through the membrane liner. The diffusion
process is similar to flow governed by Darcy's
law  for soil  liners except that diffusion is
driven  by  concentration gradients and not by
hydraulic  head. Although diffusion rates in
geomembranes   are  several   orders   of
magnitude lower than comparable hydraulic
flow rates in low-permeability  soil liners,
construction  of a completely impermeable
geomembrane is
                                          150

-------
                                     Design Criteria
difficult.   The  factor  that most strongly
influences geomembrane performance is the
presence of imperfections such as improperly
bonded seams, punctures and pinholes.  A
detailed  discussion  of  leakage through
geomembranes and composite liners  can be
found in Giroud and Bonaparte (1989 (Part I
and Part II)).  A geomembrane installed with
excellent control over defects may yield the
equivalent of a one-centimeter-diameter hole
per  acre  of  liner installed  (Giroud  and
Bonaparte, 1989 (Part I and Part II)).  If the
geomembrane were to be placed over sand,
this  size  imperfection  under one foot of
constant hydraulic head could be expected to
account for as much  as 3,300  gal/acre/day
(31,000 liters/hectare/ day) of leakage.  Based
upon measurements of actual leakage through
liners at facilities that have been built under
rigorous control, Bonaparte and Gross (1990)
have estimated an actual leakage rate, under
one   foot   of  constant  head,  of   200
liters/hectare/day or about 21 gallons/acre/day
for landfill units.

The  uniformity of the contact between the
geomembrane and the soil liner is extremely
important in controlling the  effective flow
area of leachate through the soil liner. Porous
material, such as drainage sand, filter fabric,
or other geofabric, should not be  placed
between the  geomembrane  and  the  low
permeability soil liner.  Porous materials will
create   a   layer   of   higher   hydraulic
conductivity, which will increase the amount
of leakage  below  an imperfection  in the
geomembrane. Construction practices during
the  installation   of   the  soil  and  the
geomembrane affect the uniformity  of the
geomembrane/soil   interface,  and strongly
influence the performance of the composite
liner system.
Soil Liner

The following subsections discuss soil liner
construction  practices including  thickness
requirements, lift placement, bonding of lifts,
test methods, prerequisite soil properties,
quality   control,  and   quality  assurance
activities.

Thickness

Two feet of soil is generally  considered the
minimum thickness needed to obtain adequate
compaction to meet the hydraulic conductivity
requirement.  This thickness  is considered
necessary to minimize the number of cracks
or  imperfections through  the  entire  liner
thickness that could allow leachate migration.
Both lateral and vertical  imperfections may
exist  in  a compacted soil.   The two-foot
minimum thickness is believed to be sufficient
to inhibit hydraulic short-circuiting of the
entire layer.

Lift Thickness

Soil liners should be constructed in a series of
compacted lifts. Determination of appropriate
lift thickness  is  dependent  on  the  soil
characteristics,    compaction   equipment,
firmness of the foundation materials, and the
anticipated  compactive  effort  needed  to
achieve   the   required   soil    hydraulic
conductivity.  Soil liner lifts  should be thin
enough to allow adequate compactive effort to
reach the lower portions of the lift.  Thinner
lifts also  provide  greater  assurance that
sufficient compaction  can be  achieved to
provide good, homogeneous bonding between
subsequent lifts. Adequate compaction of lift
thickness between  five  and  ten  inches is
possible  if appropriate equipment is  used
(USEPA,  1988).    Nine-inch   loose  lift
thicknesses that will yield a 6-
                                           151

-------
                                        Subpart D
inch soil layer also have been recommended
prior to compaction (USEPA, 1990a).

Soil liners usually are designed  to be of
uniform thickness with smooth slopes over the
entire  facility.    Thicker  areas  may  be
considered  wherever  recessed  areas  for
leachate collection pipes or collection sumps
are located.  Extra thickness and compactive
efforts  near edges  of the  side  slopes may
enhance bonding between the side slopes and
the bottom liner. In smaller facilities, a soil
liner may be designed for installation over the
entire   area,  but  in   larger or multi-cell
facilities, liners may be designed in segments.
If this is the case, the design should address
how the old and new liner segments will be
bonded together (U.S. EPA, 1988).

Bonding Between Lifts

It is not possible  to  construct soil liners
without some microscopic and/or macroscopic
zones   of higher  and  lower   hydraulic
conductivity.  Within individual lifts, these
preferential pathways for fluid migration are
truncated by the bonded zone  between the
lifts. If good bonding between the lifts is not
achieved  during construction,  the  vertical
pathways  may  become   connected   by
horizontal  pathways  at  the lift  interface,
thereby diminishing the performance of the
hydraulic barrier.

Two methods may be used to ensure proper
bonding between lifts.  Kneading or blending
a  thinner, new lift  with  the previously
compacted lift may be achieved by  using a
footed roller with long feet that  can fully
penetrate a loose  lift of soil.  If the protruding
rods  or feet of  a  sheepsfoot  roller are
sufficient in length to penetrate the top lift and
knead the previous lift, good bonding may be
achieved.  Another method
includes scarifying (roughening), and possibly
wetting,  the top  inch or so of the last lift
placed with a disc harrow or other  similar
equipment before placing the next lift.

Placement of Soil Liners on Slopes

The method used to place the soil liner on side
slopes depends on the angle and length of the
slope.  Gradual inclines from the toe of the
slope enable continuous placement of the lifts
up  the slopes  and provide better continuity
between the bottom and sidewalls of the soil
liner.  When steep slopes are  encountered,
however,  lifts may need to be placed and
compacted horizontally due to the difficulties
of operating heavy compaction equipment on
steeper slopes.

When sidewalls are compacted  horizontally,
it is important to tie  in the edges with the
bottom   of  the   soil  liner  to reduce the
probability of seepage planes (USEPA, 1988).
A significant amount of additional soil liner
material  will  be required to  construct the
horizontal lifts since the width of the lifts has
to  be  wide  enough  to accommodate the
compaction equipment. After the soil liner is
constructed  on the side  slopes  using this
method,  it  can  be trimmed  back  to the
required thickness.  The trimmed surface of
the soil liner should be sealed by a smooth-
drum roller.  The trimmed excess materials
can be reused provided that they meet the
specified moisture-density requirements.

Hydraulic Conductivity

Achieving the hydraulic conductivity standard
depends   on  the  degree  of  compaction,
compaction  method,  type  of  clay,  soil
moisture  content, and density of the soil
during liner construction. Hydraulic
                                           152

-------
                                     Design Criteria
conductivity is the key design parameter when
evaluating the acceptability of the constructed
soil liner. The hydraulic conductivity of a soil
depends, in part, on the viscosity and density
of the fluid flowing through it.  While water
and leachate  can cause different test results,
water is an acceptable fluid for testing the
compacted soil  liner and source materials.
The effective porosity of the soil is a function
of size, shape, and  area of the  conduits
through  which  the  liquid flows.   The
hydraulic conductivity of a partially saturated
soil is less than the hydraulic conductivity of
the same  soil   when  saturated.    Because
invading water  only  flows through water-
filled voids (and not  air-filled voids), the
dryness of a soil tends to lower permeability.
Hydraulic  conductivity  testing should  be
conducted on samples that are fully saturated
to attempt to measure the highest possible
hydraulic conductivity.

EPA   has  published  Method   9100  in
publication  SW-846  (Test Methods  for
Evaluating Solid  Wasted  to measure the
hydraulic conductivity of soil samples. Other
methods appear in the U.S. Army Corps of
Engineers Engineering Manual  1110-2-1906
(COE,  1970)   and  the  newly  published
"Measurement of Hydraulic Conductivity of
Saturated Porous Materials Using a Flexible
Wall Permeameter"  (ASTM D-5084).  To
verify full saturation of the sample, this latter
method may be performed with back pressure
saturation  and   electronic   pore   pressure
measurement.

Soil Properties

Soils typically  possess a range of physical
characteristics,   including   particle  size,
gradation,  and  plasticity,  that affect their
ability to achieve a hydraulic conductivity of
1 x  10"7 cm/sec.  Testing methods  used to
characterize  proposed  liner  soils  should
include grain size  distribution (ASTM  D-
422), Atterberg limits (ASTM D-4318), and
compaction curves  depicting  moisture and
density relationships using the standard or
modified Proctor (ASTM D-698 or ASTM D-
1557),  whichever  is  appropriate  for the
compaction equipment used and the degree of
firmness of the foundation materials.

Liner soils usually  have at least 30 percent
fines (fine  silt-  and clay-sized  particles).
Some  soils with  less than 30 percent fines
may   be   worked   to   obtain  hydraulic
conductivities below 1 x 10"7 cm/sec, but use
of these soils requires  greater control of
construction practices and conditions.

The  soil  plasticity index  (PI),  which is
determined from the  Atterberg limits (defined
by the liquid limit  minus the plastic limit),
should generally be greater than 10 percent.
However,  soils with very high PI,  (greater
than 30 percent), are cohesive and sticky and
become difficult to work with in the  field.
When  high  PI  soils  are too dry  during
placement, they tend to form hard clumps
(clods) that are difficult to break down during
compaction.  Preferential flow paths may be
created around the clods allowing leachate to
migrate at a relatively high rate.

Soil  particles or rock fragments  also can
create  preferential  flow  paths.   For this
reason, soil particles  or rock fragments should
be less than 3 inches in diameter so as not to
affect the overall hydraulic performance of
the soil liner (USEPA, 1989).

The  maximum  density  of a soil  will  be
achieved at the optimum water content, but
this point generally does not correspond to the
point at which minimum hydraulic
                                           153

-------
                                        Subpart D
conductivity is achieved. Wet soils, however,
have low shear strength and high potential for
desiccation  cracking.   Care  should be taken
not   to   compromise  other   engineering
properties such as shear strengths of the soil
liner  by excessively  wetting the soil liner.
Depending on the specific soil characteristics,
compaction equipment and compactive effort,
the hydraulic conductivity criterion  may be
achieved at  moisture values  of 1  to 7 percent
above the optimum moisture content.

Although the soil  may possess the required
properties for successful liner construction,
the soil  liner may not meet the  hydraulic
conductivity  criterion if the  construction
practices  used to install  the liner  are not
appropriate    and   carefully   controlled.
Construction  quality  control  and  quality
assurance will be discussed in a later section.

Amended Soils

If locally   available  soils  do  not  possess
properties to achieve the specified hydraulic
conductivity, soil additives can be used.  Soil
additives, such  as bentonite or other  clay
materials,   can   decrease  the   hydraulic
conductivity  of the  native soil  (USEPA,
1988b).

Bentonite may be obtained in a dry, powdered
form that is  relatively easy to blend with on-
site  soils.    Bentonite is  a  clay  mineral
(sodium-montmorillonite) that expands when
it comes into contact with water  (hydration),
by absorbing the water within  the  mineral
matrix.  This property allows relatively small
amounts of  bentonite (5 to 10 percent) to be
added to a noncohesive soil (sand) to make it
more cohesive (U.S. EPA, 1988b). Thorough
mixing of additives to cohesive soils  (clay)
is difficult and may lead to inconsistent results
with respect to complying with the hydraulic
conductivity criterion.

The  most common additive used  to amend
soils is sodium bentonite.  The disadvantage
of  using  sodium bentonite includes  its
vulnerability to  degradation as  a result of
contact with  chemicals and waste leachates
(U.S. EPA, 1989).

Calcium bentonite, although more permeable
than sodium bentonite, also is used as a soil
amendment.  Approximately twice as much
calcium  bentonite typically is  needed to
achieve a hydraulic conductivity  comparable
to that of sodium bentonite.

Soil/bentonite mixtures generally  require
central plant mixing by means of a pugmill,
cement  mixer, or other mixing  equipment
where water can be added during the process.
Water, bentonite content, and particle  size
distribution must be controlled during mixing
and   placement.      Spreading   of  the
soil/bentonite mixture may be accomplished
in the same manner as the spreading of natural
soil  liners,  by  using  scrapers,  graders,
bulldozers, or a continuous  asphalt paving
machine  (U.S. EPA, 1988).

Materials other than bentonite, including lime,
cement,  and other clay minerals such as
atapulgite, may be used as soil additives (U.S.
EPA,  1989).     For  more  information
concerning  soil  admixtures, the  reader  is
referred to the technical resource document on
the design and  construction of clay liners
(U.S. EPA, 1988).

Testing

Prior to  construction  of a  soil  liner, the
relationship between water content, density,
                                           154

-------
                                     Design Criteria
and hydraulic conductivity for a particular soil
should  be  established  in the  laboratory.
Figure 4-5 shows the influence  of molding
water content (moisture content of the soil at
the  time  of  compaction)  on   hydraulic
conductivity of the soil. The lower half of the
diagram is a compaction curve and shows the
relationship between dry unit weight, or dry
density of the soil, and water content of the
soil.  The optimum moisture content of the
soil is related to a peak value of dry  density
known as maximum dry density.  Maximum
dry  density  is  achieved at the  optimum
moisture content.

The  lowest  hydraulic  conductivity  of
compacted clay soil is achieved when  the soil
is  compacted at a moisture content  slightly
higher than the  optimum moisture content,
generally in the range of 1 to 7 percent (U.S.
EPA, 1989). When compacting clay, water
content and  compactive  effort are the two
factors that  should be controlled to meet the
maximum hydraulic conductivity criterion.

It  is impractical to specify and  construct a
clay liner to a specific moisture content and a
specific compaction  (e.g., 5 percent wet of
optimum  and 95 percent modified  Proctor
density).  Moisture content can be difficult to
control in  the  field during  construction;
therefore, it may  be more appropriate to
specify a range of moisture  contents  and
corresponding   soil   densities   (percent
compaction) that are considered appropriate to
achieve the  required hydraulic conductivity.
Benson and Daniel (U.S. EPA, 1990) propose
water  content and density criteria  for the
construction of clay liners  in  which the
moisture-density   criteria    ranges   are
established based on hydraulic conductivity
test  results.   This  type  of approach is
recommended because of the flexibility and
guidance it provides to the
construction contractor during soil placement.
Figure 4-6 presents compaction  data as a
function of dry unit weight and molding water
content for the construction  of clay liners.
The amount  of soil  testing  required  to
determine these construction parameters is
dependent on the degree of natural  variability
of the source material.

Quality assurance and quality control of soil
liner materials involve both laboratory and
field  testing.    Quality  control  tests are
performed   to    ascertain    compaction
requirements  and  the  moisture content  of
material delivered to the site.  Field tests for
quality assurance provide  an  opportunity to
check  representative areas of the liner for
conformance  to compaction  specifications,
including   density  and  moisture  content.
Quality assurance laboratory testing is usually
conducted on field samples for determination
of hydraulic conductivity of the in-place liner.
Laboratory testing allows full saturation of the
soil samples and simulates the effects of large
overburden stress on the soil, which cannot be
done conveniently  in the field (U.S. EPA,
1989).

Differences between laboratory  and  field
conditions (e.g.,  uniformity  of  material,
control of water content, compactive effort,
compaction equipment) may make it unlikely
that minimum hydraulic conductivity values
measured in the laboratory on  remolded, pre-
construction borrow source samples are the
same as  the values achieved during  actual
liner construction.   Laboratory testing  on
remolded soil specimens does not account for
operational  problems  that  may  result  in
desiccation, cracking, poor bonding of lifts,
and inconsistent degree  of compaction  on
sidewalls   (U.S.   EPA,    1988b).     The
relationship between field  and  laboratory
hydraulic   conductivity testing  has  been
investigated by the U.S. Environmental
                                           155

-------
    Hydraulic
 Conductivity
     Dry Unit
      Weight
                             Molding Water Content
Source: U.S. EPA, 1989.

  Note: The optimum moisture content occurs at the point at which maximum density is achieved.
  The lowest hydraulic conductivity generally occurs at water contents higher than optimum.
                                Figure 4-5
            Hydraulic Conductivity and Dry Unit Weight as a
                   Function of Molding Water Content
                                     156

-------
£
*s
     120
     110
     100
      90
         10
                                                     Acceptable
                                                     Zone
             15                  20

            Molding Water Content (%)
          An
          D
          OJ
Compactive Effort
                                                                     25
                Compaction Data for a Silty Clay (from Mitchell et al.. 1965).
                Solid symbols represent specimens with a hydraulic
                conductivity < 1 x 10'7 cm/s and open symbols represent
                specimens with hydraulic conductivity > 1 x 10'7 cm/s.
Source: CERI 90-50 (USEPA, 1990)
               Figure 4-6. Compaction Data for Silty Clay

                                   157

-------
                                        Subpart D
Protection  Agency using field case studies
(U.S. EPA, 1990c).

In situ, or field, hydraulic conductivity testing
operates on the assumption that by testing
larger masses of  soil  in the field, one can
obtain more realistic results.  Four types of in
situ hydraulic conductivity tests generally are
used:    borehole tests,  porous  probes,
infiltrometer tests, and underdrain tests.  A
borehole test is conducted by drilling a hole,
then  filling   the  hole with  water,  and
measuring  the rate at which water percolates
into the borehole.  In the borehole test, water
also can percolate through the sidewalls of the
borehole. As a result, the measured hydraulic
conductivity   is usually  higher  than  that
measured  by other one-dimensional  field
testings.

The  second type of test involves driving or
pushing a  porous probe into the soil and
pouring water through the probe into the soil.
With this method,  however, the advantage of
testing directly in the field is somewhat offset
by the limitations of  testing such  a small
volume of  soil.

A third method of testing involves a device
called  an  infiltrometer.    This  device  is
embedded  into the surface of the soil liner
such that the rate of flow of a liquid into the
liner can be measured.  The two types  of
infiltrometers most widely used are open and
sealed. Open rings  are less desirable because,
with a hydraulic conductivity of 10"7 cm/sec,
it  is  difficult to detect  a 0.002 inch  per day
drop  in water level   of  the  pond  from
evaporation and other losses.

With sealed rings,  very low rates of flow can
be  measured.      However,    single-ring
infiltrometers allow lateral flow beneath the
ring, which can complicate the interpretation
of test  results.    Single  rings are  also
susceptible  to  the effects  of temperature
variation; as the water temperature increases,
the entire system expands. As it cools down,
the system  contracts.  This  situation could
lead to erroneous measurements when the rate
of flow is small.

The  sealed  double-ring  infiltrometer  has
proven to be the most successful method and
is  the  one currently used.   The  outer ring
forces  infiltration from the inner ring to be
more or less one-dimensional.  Covering the
inner ring with water insulates it substantially
from temperature variation.

Underdrains, the fourth type of in situ test, are
the most accurate in situ permeability testing
device because they  measure exactly what
migrates  from  the bottom of  the  liner.
However, under-drains are slow to generate
data for low permeability liners, because of
the length  of time required to accumulate
measurable flow. Also, underdrains must be
installed  during  construction,  so  fewer
underdrains  are used than  other kinds of
testing devices.

Field hydraulic conductivity tests are not
usually performed  on the completed liner
because the tests may take several weeks to
complete (during which time the liner may be
damaged   by   desiccation   or   freezing
temperatures) and because large penetrations
must be  made into  the  liner.    If field
conductivity tests  are performed,  they are
usually conducted on a test pad.  The test pad
should be constructed using the materials and
methods to be used for the actual soil liner.
The width of a test pad is usually the width of
three to four construction vehicles, and the
length  is  one  to  two  times  the  width.
Thickness is usually two to three feet. Test
pads can be used as a means for verifying that
the proposed
                                            158

-------
                                     Design Criteria
materials  and construction procedures will
meet performance objectives. If a test pad is
constructed, if tests verify that performance
objectives have been met, and if the actual
soil liner is constructed to standards that equal
or exceed those used in building the test pad
(as verified through quality assurance), then
the actual soil  liner should  meet or exceed
performance objectives.

Other than the  four types of field hydraulic
conductivity tests described earlier, ASTM D
2937  "Standard Test Method for Density of
Soil in Place by the Drive-Cylinder Method"
may be used to  obtain  in-place hydraulic
conductivity  of the soil  liner.  This  test
method uses a U.S. Army Corps of Engineers
surface soil sampler to drive  a thin-walled
cylinder (typically 3-inch by 3-inch) into a
completed lift  of the soil  liner to  obtain
relatively undisturbed samples for laboratory
density and hydraulic conductivity testings.
This test  can provide useful correlation to
other  field  and  quality  assurance  testing
results (e.g, Atterberg limits, gradation, in-
place moisture and density of the soil liner) to
evaluate the in-place hydraulic conductivity of
the soil liner.

Soil Liner Construction

Standard compaction procedures are usually
employed  when constructing soil liners. The
following factors influence  the degree  and
quality of compaction:

•    Lift thickness;

•    Full  scale  or segmented lift placement;

•    Number of equipment passes;

•    Scarification between lifts;
•    Soil water content; and

•    The type of equipment and compactive
     effort.

The method used to compact the soil liner is
an important factor in achieving the required
minimum  hydraulic conductivity.   Higher
degrees  of compactive effort  increase soil
density  and  lower  the  soil   hydraulic
conductivity for a given water content.  The
results of laboratory compaction tests do not
necessarily  correlate directly with the amount
of compaction that can be achieved during
construction.

Heavy compaction equipment  (greater than
25,000 Ibs or 11,300 kg)  is typically used
when  building the soil  liner  to maximize
compactive effort (U.S.  EPA,  1989).   The
preferred field compaction equipment  is a
sheepsfoot roller  with long  feet that fully
penetrates  loose  lifts of soil  and  provides
higher compaction while kneading the  clay
particles together.  The shape and depth of the
feet are important; narrow, rod-like feet with
a minimum length of about seven inches
provide the best results. A progressive change
from the rod-like feet to a broader foot may
be  necessary  in  some  soils  after  initial
compaction, to allow the roller to walk out of
the compacted soil. The sheepsfoot feet also
aid in  breaking  up  dry  clods (see  Soil
Properties  in this section).  Mechanical road
reclaimers, which are typically  used to strip
and re-pave  asphalt,  can  be  extremely
effective in reducing soil clod  size prior to
compaction and in scarifying  soil  surfaces
between lifts. Other equipment  that has been
used to compact soil includes  discs  and
rototillers.

To  achieve adequate compaction,  the lift
thickness (usually five to nine inches) may be
decreased or the number of passes over
                                           159

-------
                                       Subpart D
the  lift  may  be increased.    Generally,
compaction equipment should pass over the
soil  liner five to  twenty times to attain the
compaction needed  to comply  with the
minimum  hydraulic  conductivity  criterion
(U.S. EPA, 1989).

Efforts  made  to  reduce clod  size during
excavation  and placement of the soil for the
liner should   improve the  chances for
achieving   low hydraulic   conductivity in
several ways.  Keeping clods in the soil liner
material small will facilitate a more uniform
water content.  Macropores  between  clod
remnants can result in unacceptably high field
hydraulic conductivity.

Opinions differ on acceptable clod sizes in the
uncompacted soil.  Some suggest a maximum
of one to three inches in diameter, or no larger
than one-half the lift thickness.  The  main
objective  is  to  remold  all  clods in the
compaction  process   to   keep  hydraulic
conductivity values consistent throughout the
soil liner (U.S. EPA,  1988).

Geomembranes

Geomembranes are relatively thin sheets of
flexible thermoplastic or thermoset polymeric
materials   that  are  manufactured   and
prefabricated at a factory and transported to
the  site.     Because  of  their  inherent
impermeability, use  of geomembranes in
landfill unit construction has increased.  The
design of  the  side  slope,  specifically the
friction    between   natural    soils   and
geosynthetics, is critical and requires careful
review.

Material Types and Thicknesses

Geomembranes are made  of one  or  more
polymers  along  with  a variety  of  other
ingredients such as carbon  black, pigments,
fillers,   plasticizers,    processing    aids,
crosslinking chemicals, anti-degradants, and
biocides. The polymers used to manufacture
geomembranes  include a  wide  range of
plastics and rubbers differing in properties
such  as  chemical resistance  and  basic
composition (U.S. EPA, 1983 and U.S. EPA,
1988e).  The polymeric  materials may be
categorized as follows:
     Thermoplastics  such
     chloride (PVC);
as  polyvinyl
•    Crystalline thermoplastics such as high
     density polyethylene (HDPE), very low
     density  polyethylene  (VLDPE),  and
     linear   low   density   polyethylene
     (LLDPE); and

•    Thermoplastic  elastomers   such  as
     chlorinated polyethylene (CPE)  and
     chlorosulfonated polyethylene (CSPE).

The polymeric materials used most frequently
as geomembranes are HDPE, PVC, CSPE,
and CPE. The thicknesses of geomembranes
range from 20 to 120 mil (1 mil = 0.001 inch)
(U.S. EPA, 1983 and U.S. EPA, 1988e).  The
recommended minimum  thickness  for  all
geomembranes is 30 mil, with the exception
of HDPE, which must be at least 60 mil to
allow  for  proper  seam  welding.    Some
geomembranes  can be manufactured by a
calendering process with fabric reinforcement,
called  scrim, to provide additional tensile
strength and dimensional stability.

Chemical and Physical Stress Resistance

The design of the landfill unit should consider
stresses imposed on the liner  by the design
configuration.  These stresses include the
following:
                                          160

-------
                                     Design Criteria
•    Differential  settlement in  foundation
     soils;

•    Strain requirements at the anchor trench;
     and

•    Strain requirements over long, steep side
     slopes.

An extensive  body of literature has been
developed by manufacturers and independent
researchers on the physical properties of
liners.   Geosynthetic  design equations  are
presented in several publications including
Kastman (1984), Koerner (1990), and U.S.
EPA(1988e).

The chemical resistance of a geomembrane to
leachate has traditionally been considered a
critical issue for Subtitle C (hazardous waste)
facilities where highly concentrated solvents
may be encountered.   Chemical resistance
testing of geomembranes may not be required
for MSWLF units containing only municipal
solid waste; EPA's data base has  shown that
leachate from MSWLF units is not aggressive
to these  types of  materials.  Testing  for
chemical  resistance   may  be   warranted
considering  the   waste  type,   volumes,
characteristics, and amounts of small quantity
generator waste or other industrial waste
present in the waste stream. The following
guidance is provided in the event such testing
is of interest to the owner or operator.

EPA's  Method  9090  in SW-846  is  the
established test procedure used to evaluate
degradation of geomembranes when exposed
to  hazardous   waste  leachate.     In   the
procedure, the geomembrane is immersed in
the site-specific chemical  environment for at
least 120 days  at two different temperatures.
Physical  and mechanical properties  of the
tested material are then compared to those
of the original material every thirty days.  A
software  system  entitled  Flexible  Liner
Evaluation Expert (FLEX), designed to assist
in the  hazardous waste permitting process,
may aid in interpreting EPA Method 9090 test
data (U.S. EPA, 1989). A detailed discussion
of both Method 9090 and FLEX is available
from EPA.

It is imperative that a  geomembrane liner
maintain its  integrity  during  exposure  to
short-term and long-term mechanical stresses.
Short-term  mechanical stresses include
equipment traffic during the installation of a
liner system, as well as thermal expansion and
shrinkage of the geomembrane during the
construction and operation  of  the MSWLF
unit.  Long-term mechanical stresses result
from the placement of waste on top  of the
liner system and from subsequent differential
settlement of the subgrade (U.S. EPA, 1988a).

Long-term success  of the liner requires
adequate friction between the components  of
a liner system, particularly the  soil subgrade
and   the   geomembrane,   and   between
geosynthetic components, so that slippage  or
sloughing does not occur on the slopes of the
unit. Specifically, the foundation slopes and
the subgrade materials must be  considered in
design equations to evaluate:

•    The  ability  of  a geomembrane  to
     support its own  weight  on the  side
     slopes;

     The  ability  of  a geomembrane  to
     withstand down-dragging during  and
     after waste placement;

•    The best anchorage configuration for the
     geomembrane;
                                          161

-------
                                       Subpart D
•    The stability of a soil cover on top of a
     geomembrane; and

•    The  stability  of  other  geosynthetic
     components such as geotextile or geonet
     on top of a geomembrane.

These requirements may affect the choice of
geomembrane material, including polymer
type,  fabric  reinforcement,  thickness,  and
texture (e.g.,  smooth or textured for HDPE)
(U.S. EPA, 1988). PVC also can be obtained
in a roughened or file finish to increase the
friction angle.

Design specifications should indicate the type
of raw polymer and manufactured sheet to be
used  as well as the  requirements for the
delivery, storage, installation, and sampling of
the geomembrane. Material properties can be
obtained  from the  manufacturer-supplied
average  physical property values, which are
published in the Geotechnical Fabrics Report's
Specifier's Guide and updated annually.  The
minimum    tensile    properties   of   the
geomembrane must be sufficient to satisfy the
stresses  anticipated during the service life of
the geomembrane. Specific raw polymer and
manufactured sheet specifications and  test
procedures include (U.S. EPA,  1988e,  and
Koerner, 1990):

Raw Polymer Specifications

     • Density (ASTMD-1505);

     • Melt index (ASTM D-1238);

     • Carbon black (ASTM D-1603); and

     • Thermogravimetric analysis (TGA)
       or differential scanning calorimetry
       (DSC).
Manufactured Sheet Specifications

     •  Thickness (ASTMD-1593);

     •  Tensile properties (ASTM D-638);

     •  Tear resistance (ASTM D-1004);

     •  Carbon black  content  (ASTM  D-
        1603);

     •  Carbon black dispersion (ASTM D-
        3015);

     •  Dimensional stability  (ASTM  D-
        1204); and

     •  Stress crack resistance  (ASTM  D-
        1693).

Geomembranes may have different physical
characteristics,  depending on the  type of
polymer and the manufacturing process used,
that can affect the design of a liner system.
When reviewing manufacturers'  literature, it
is  important  to   remember  that   each
manufacturer may use more than one polymer
or resin type for each grade of geomembrane
and that the material specifications may be
generalized  to represent several grades of
material.

Installation

Installation  specifications  should  address
installation  procedures  specific  to  the
properties  of  the  liner  installed.    The
coefficient  of  thermal expansion  of the
geomembrane sheet  can affect its installation
and   its   service   performance.      The
geomembrane   should  lie   flat   on  the
underlying soil.   However,  shrinkage  and
expansion of the sheeting, due to changes in
temperature during installation, may result in
excessive   wrinkling  or  tension  in  the
                                          162

-------
                                     Design Criteria
geomembrane.       Wrinkles    on    the
geomembrane  surface  will   affect   the
uniformity of the soil-geomembrane interface
and   may  result   in  leakage  through
imperfections.  Excessive  tautness of the
geomembrane may affect its ability to resist
rupture from localized  stresses on the seams
or at the toe of slopes where bridging over the
subgrade may occur during installation.  In
addition to thermal expansion and contraction
of the geomembrane, residual stresses from
manufacturing remain in some geomembranes
and can  cause  non-uniform expansion and
contraction  during  construction.    Some
flexibility is needed in  the specifications for
geomembrane  selection   to   allow   for
anticipated  dimensional  changes  resulting
from thermal expansion  and contraction (U.S.
EPA, 1988).

Technical specifications for geomembranes
also   should  include:     information  for
protection of the material during shipping,
storage  and   handling;  quality  control
certifications provided by the manufacturer or
fabricator (if panels are constructed); and
quality control testing by the  contractor,
installer, or  a construction quality assurance
(CQA)   agent.     Installation   procedures
addressed by the technical  specifications
include  a   geomembrane   layout   plan,
deployment  of  the  geomembrane at  the
construction site, seam  preparation, seaming
methods,  seaming temperature constraints,
detailed   procedures   for   repairing  and
documenting construction defects, and sealing
of the geomembrane to appurtenances, both
adjoining and penetrating  the  liner.   The
performance of inspection activities, including
both non-destructive and destructive quality
control field testing of  the sheets and seams
during installation  of the  geomembrane,
should   be   addressed  in  the   technical
specifications. Construction quality assurance
is addressed
in an  EPA guidance  document (USEPA,
1992).

The geomembrane sheeting is shipped in rolls
or panels from the supplier, manufacturer, or
fabricator to the construction site. Each roll
or panel may be  labeled according to  its
position on the geomembrane layout plan to
facilitate installation.   Upon  delivery,  the
geomembrane sheeting should be inspected to
check  for damage that may have  occurred
during shipping. (U.S. EPA,  1992).

Proper storage of the rolls or panels prior to
installation  is  essential   to  the   final
performance  of the  geomembrane.  Some
geomembrane   materials   are  sensitive  to
ultraviolet exposure and should not be stored
in direct sunlight prior to installation. Others,
such as  CSPE and  CPE, are  sensitive  to
moisture and heat and can partially crosslink
or block  (stick together) under improper
storage conditions.   Adhesives or welding
materials,  which   are   used   to   join
geomembrane  panels, also should be stored
appropriately (U.S. EPA,  1992).

Visual inspection and acceptance of the soil
liner subgrade should be  conducted prior to
installing the geomembrane.  The surface of
the    subgrade    should   meet   design
specifications   with  regard  to   lack   of
protruding  objects, grades,  and thickness.
Once these inspections  are  conducted and
complete, the geomembrane may be installed
on top of the soil liner.   If necessary,  other
means  should be employed to protect  the
subgrade from precipitation and erosion, and
to prevent desiccation,  moisture loss, and
erosion  from  the  soil  liner  prior   to
geomembrane placement.  Such methods may
include placing a plastic tarp  on top  of
completed portions of the soil liner
                                           163

-------
                                       Subpart D
(USEPA, 1992).  In addition, scheduling soil
liner  construction  slightly  ahead  of the
geomembrane and drainage layer placement
can reduce the exposure of the soil liner to the
elements.

Deployment,    or   placement,   of   the
geomembrane  panels or  rolls should  be
described  in the geomembrane layout plan.
Rolls of sheeting, such as  HDPE,  generally
can be deployed by placing a shaft through
the core of the roll, which is supported and
deployed using a front-end loader or a winch.
Panels composed of extremely flexible liner
material such as PVC are usually folded on
pallets, requiring workers to manually unfold
and place  the geomembrane.  Placement of
the geomembrane goes hand-in-hand with the
seaming process; no more than the amount of
sheeting that can be seamed during a shift or
work day should be deployed at any one time
(USEPA,  1988). Panels should be weighted
with sand bags if wind uplift of the membrane
or  excessive   movement   from  thermal
expansion is  a potential  problem.   Proper
stormwater control measurements should be
employed  during construction  to prevent
erosion of the  soil liner  underneath the
geomembrane and the washing away of the
geomembrane.

Once  deployment  of a   section  of the
geomembrane is complete and each  section
has been visually inspected for imperfections
and tested to ensure that it is the specified
thickness,  seaming of the geomembrane may
begin.  Quality  control/quality  assurance
monitoring of the seaming process should be
implemented   to detect  inferior  seams.
Seaming  can  be conducted  either  in the
factory  or in  the field.  Factory  seams are
made in a controlled environment and are
generally of high quality, but the entire seam
length (100 percent) still should be
tested non-destructively (U.S. EPA, 1988).
Destructive testing should be done at regular
intervals along the seam (see page 4-66).

Consistent quality in fabricating field seams is
critical to liner performance, and conditions
that may affect seaming should be monitored
and  controlled  during installation.   An
inspection should be conducted in accordance
with a construction quality assurance plan to
document the integrity of field seams.  Factors
affecting the seaming process include (U.S.
EPA, 1988):

•    Ambient temperature at which the seams
     are made;

•    Relative humidity;

•    Control of panel lift-up by wind;

•    The   effect   of   clouds   on   the
     geomembrane temperature;

•    Water content of the subsurface beneath
     the geomembrane;

•    The  supporting surface on  which the
     seaming is bonded;

•    The skill  of the seaming crew;

•    Quality and consistency of the chemical
     or welding material;

•    Proper preparation of the liner surfaces
     to be joined;

•    Moisture on the seam interface; and

•    Cleanliness of the seam interface (e.g.,
     the amount of airborne dust and debris
     present).
                                          164

-------
                                     Design Criteria
Depending on  the  type  of geomembrane,
several bonding systems are available for the
construction of both factory and field seams.
Bonding methods include solvents, heat seals,
heat  guns,  dielectric  seaming,  extrusion
welding, and  hot wedge techniques.  To
ensure  the  integrity  of  the  seams,  a
geomembrane should be  seamed using the
bonding   system  recommended   by  the
manufacturer (U.S.  EPA, 1988).  EPA has
developed  a  field seaming manual for all
types of geomembranes (U.S. EPA, 199la).

Thermal   methods   of  seaming   require
cleanliness of the bonding  surfaces,  heat,
pressure, and  dwell time to  produce high
quality seams. The requirements for adhesive
systems are the same as  those for thermal
systems,  except that the adhesive takes the
place of the heat.  Sealing the geomembrane
to appurtenances  and penetrating structures
should be  performed  in  accordance with
detailed drawings included  in the design plans
and approved specifications.

An anchor trench along the perimeter of the
cell   generally  is   used  to  secure  the
geomembrane during construction (to prevent
sloughing or slipping down the interior side
slopes). Run out calculations (Koerner, 1990)
are available to determine the depth of burial
at a trench necessary to hold a specified length
of membrane, or  combination of membrane
and geofabric or geotextile. If forces larger
than the tensile strength of the membrane are
inadvertently developed, then the membrane
could tear. For this reason, the geomembrane
should be allowed to  slip or give in the trench
after  construction to prevent such tearing.
However,   during    construction,   the
geomembrane should be anchored according
to the detailed drawings provided in the
design plans and specifications  (USEPA,
1988).

Geomembranes that are subject to damage
from exposure to weather and work activities
should be covered with a layer of soil as soon
as possible after quality assurance activities
associated  with geomembrane testing are
completed.  Soil  should be  placed without
driving construction vehicles directly  on the
geomembrane.    Light  ground   pressure
bulldozers may be used to push material out
in front over the liner, but the operator must
not attempt to push a large pile of soil forward
in a continuous manner over the membrane.
Such methods can cause localized wrinkles to
develop and overturn in  the  direction of
movement.  Overturned wrinkles create sharp
creases   and  localized  stresses  in  the
geomembrane that could lead  to premature
failure.     Instead,   the operator  should
continually place  smaller amounts of  soil or
drainage material  working outward over the
toe  of the  previously placed  material.
Alternatively, large backhoes can be used to
place soil over the geomembrane that can later
be  spread  with  a  bulldozer or  similar
equipment.   Although such methods may
sound tedious and slow, in the long run they
will be faster and more cost-effective than
placing too much material too fast and having
to remobilize the liner installer  to  repair
damaged sections  of the geomembrane.  The
QA activities conducted during construction
also   should   include  monitoring  the
contractor's activities on top of the liner to
avoid  damage  to installed and  accepted
geomembranes.

Leachate Collection Systems

Leachate refers to  liquid that has passed
through or emerged  from solid waste  and
contains dissolved, suspended, or immiscible
                                          165

-------
                                        Subpart D
materials removed from the solid waste.  At
MSWLF units, leachate is typically aqueous
with limited,  if any, immiscible  fluids or
dissolved solvents.  The primary function of
the leachate collection system is to collect and
convey leachate out of the landfill unit and to
control the depth of the leachate above the
liner. The leachate collection  system (LCS)
should be designed to  meet the regulatory
performance standard of maintaining less than
30  cm  (12 inches) depth  of leachate, or
"head,"  above  the liner.  The 30-cm head
allowance is a design standard and the Agency
recognizes that this design standard may be
exceeded for relatively short periods of time
during the active life of the unit.  Flow of
leachate through imperfections in the liner
system increases with an increase in leachate
head  above the liner.   Maintaining a  low
leachate level above the liner helps to improve
the performance of the composite liner.

Leachate  is  generally  collected  from  the
landfill   through  sand  drainage  layers,
synthetic drainage nets,  or granular drainage
layers with perforated plastic collection pipes,
and is then removed through sumps or gravity
drain carrier pipes.  LCS's should consist of
the following components (U.S. EPA, 1988):

•    A low-permeability base  (in this case a
     composite liner);

•    A  high-permeability  drainage layer,
     constructed of either natural granular
     materials (sand and gravel) or synthetic
     drainage material (e.g., geonet) placed
     directly on the FML, or on a protective
     bedding layer (e.g., geofabric) directly
     overlying the liner;

•    Perforated leachate   collection pipes
     within the high-permeability drainage
     layer to  collect leachate and carry  it
     rapidly to a sump or collection header
     pipe;

•    A protective filter layer over the high
     permeability  drainage  material,   if
     necessary, to prevent physical clogging
     of the material by fine-grained material;
     and

•    Leachate collection  sumps  or header
     pipe  system where leachate can  be
     removed.

The design, construction, and operation of the
LCS should maintain a maximum height of
leachate above the composite liner of 30 cm
(12 in). Design guidance for calculating the
maximum leachate depth over  a liner for
granular  drainage  systems  materials   is
provided in the reference U.S. EPA (1989).
The leachate head  in the layer is a function of
the liquid impingement rate, bottom  slope,
pipe spacing, and drainage  layer  hydraulic
conductivity.   The  impingement rate  is
estimated  using   a complex liquid routing
procedure.  If the maximum leachate depth
exceeds 30 cm for the system, except for
short-term occurrences, the design  should be
modified  to  improve  its   efficiency  by
increasing grade,  decreasing pipe spacing, or
increasing  the   hydraulic  conductivity
(transmissivity) of the drainage  layer (U.S.
EPA, 1988).

Grading of Low-Permeability Base

The typical bottom liner slope is a minimum
of two percent after allowances for settlement
at all points in   each  system.   A slope  is
necessary   for  effective  gravity  drainage
through the entire operating and post-closure
period.     Settlement  estimates  of  the
foundation soils should set this two-
                                           166

-------
                                      Design Criteria
percent grade  as  a post-settlement design
objective (U.S. EPA, 1991b).

High-Permeability Drainage Layer

The  high-permeability  drainage layer  is
placed directly over the liner or its protective
bedding layer at a slope of at least two percent
(the same slope necessary for the composite
liner).  Often  the  selection of a drainage
material is based on the on-site availability of
natural granular materials. In some regions of
the country, hauling costs may be very high
for sand and gravel, or appropriate materials
may be unavailable; therefore, the designer
may elect to use geosynthetic drainage nets
(geonets) or synthetic drainage materials as an
alternative.      Frequently,   geonets   are
substituted for granular materials on  steep
sidewalls  because maintaining sand on  the
slope during construction and operation of the
landfill unit is  more  difficult (U.S. EPA,
1988).

Soil Drainage Layers

If the drainage layer of the leachate collection
system  is  constructed  of granular  soil
materials  (e.g.,  sand  and gravel),  then it
should  be demonstrated  that this granular
drainage layer has sufficient bearing strength
to   support   expected   loads.      This
demonstration will be similar to that required
for the foundations and soil liner (U.S. EPA,
1988).

If the landfill unit is designed on moderate-to-
steep (15 percent)  grades, the landfill design
should include calculations demonstrating that
the selected granular drainage materials will
be  stable  on the most  critical slopes  (e.g.,
usually the steepest slope) in the design.  The
calculations  and  assumptions  should  be
shown, especially the
friction angle between the geomembrane and
soil, and if possible, supported by laboratory
and/or field testing (USEPA, 1988).

Generally,   gravel   soil   with   a   group
designation of GW or GP on the Unified Soils
Classification Chart can be expected to have
a hydraulic conductivity of greater than 0.01
cm/sec, while sands  identified as SW or SP
can  be expected to have  a coefficient of
permeability greater than 0.001  cm/sec.  The
sand or gravel drains leachate that enters the
drainage layer to prevent 30 cm (12 in) or
more accumulation on top of the liner during
the active life of the MSWLF unit LCS.  The
design of a LCS  frequently uses a drainage
material with a hydraulic conductivity of 1 x
10"2  cm/sec  or higher.  Drainage materials
with hydraulic conductivities in this order of
magnitude should be evaluated for biological
and  particulate  clogging (USEPA, 1988).
Alternatively, if a geonet is used, the design is
based on the transmissivity of the geonet.

If a filter layer (soil  or  geosynthetic) is
constructed  on top of a  drainage layer to
protect it from  clogging,  and the LCS is
designed  and  operated to  avoid  drastic
changes in the oxidation reduction potential of
the leachate (thereby avoiding  formation of
precipitates within the LCS), then there is no
conceptual    basis   to    anticipate    that
conductivity will decrease over time. Where
conductivity  is expected  to  decrease over
time, the change in  impingement rate  also
should be evaluated over the same time period
because the reduced impingement rate and
hydraulic conductivity may still comply with
the 30  cm criterion.

Unless alternative provisions are made to
control incident precipitation  and resulting
surface run-off, the impingement rate during
the operating period of the MSWLF unit is
                                           167

-------
                                        Subpart D
usually at least an order of magnitude greater
than the impingement rate after final closure.
The critical design condition for meeting the
30  cm  (12  in)  criterion can therefore  be
expected  during the operating life.  The
designer may evaluate  the sensitivity of a
design to meet the 30 cm (12  in) criterion as
a result of  changes in  impingement rates,
hydraulic  conductivity,   pipe  spacing, and
grades.  Such sensitivity analysis may indicate
which  element  of  the  design should  be
emphasized   during  construction   quality
monitoring  or whether the design  can  be
altered  to comply with the 30  cm  (12 in)
criterion in a more cost-effective manner.

The soil material used for the drainage layer
should be investigated at the borrow pit prior
to use  at  the landfill.   Typical borrow pit
characterization   testing   would    include
laboratory hydraulic conductivity and grain
size distribution.  If grain size  distribution
information    from   the   borrow   pit
characterization program can be correlated to
the hydraulic conductivity data, then the grain
size test, which can be conducted in a short
time in the field, may be a useful construction
quality  control parameter. Compliance with
this parameter would then be indicative that
the hydraulic conductivity design criterion
was achieved in the constructed  drainage
layer.  This information could be incorporated
into construction documents after the borrow
pit has  been characterized. If a correlation
cannot   be   made  between   hydraulic
conductivity and grain size distribution, then
construction documents may rely on direct
field   or   laboratory    measurements   to
demonstrate that the hydraulic  conductivity
design criterion was met in the  drainage layer.
Granular materials are generally placed using
conventional    earthmoving    equipment,
including  trucks, scrapers, bulldozers,  and
front-end  loaders.   Vehicles  should not be
driven  directly   over  the  geosynthetic
membrane when it is being covered.  (U.S.
EPA, 1988a).

Coarse  granular drainage materials, unlike
low-permeability soils, can be placed dry and
do  not need  to  be  heavily  compacted.
Compacting granular soils tends to grind the
soil  particles together, which increases the
fine   material  and   reduces   hydraulic
conductivity.    To  minimize   settlement
following material  placement, the granular
material may be compacted with a vibratory
roller.   The final thickness of the drainage
layer should be checked by  optical survey
measurements   or  by   direct   test   pit
measurements (U.S. EPA, 1988).

Geosynthetic Drainage Nets

Geosynthetic drainage nets (geonets) may be
substituted for the granular layers of the LCRs
on the bottom and sidewalls of the landfill
cells.   Geonets require less  space  than
perforated pipe or gravel  and also promote
rapid transmission of liquids.   They  do,
however, require geotextile filters  above them
and can experience problems  with creep and
intrusion.      Long-term  operating   and
performance experience of geonets is limited
because the material and its  application are
relatively  new (U.S. EPA, 1989).

If a  geonet is used in place of a granular
drainage layer, it must provide the same level
of performance (maintaining less than 30 cm
of leachate head  above the liner).   An
explanation of the calculation used to compute
the capacity of a geonet may be found in U.S.
EPA(1987a).  The
                                           168

-------
                                      Design Criteria
transmissivity of a geonet  can be reduced
significantly  by intrusion of the  soil or a
geotextile.  A protective geotextile between
the soil and  geonet will help alleviate this
concern. If laboratory transmissivity tests are
performed,  they  should be  done  under
conditions, loads,  and configurations  that
closely replicate the actual field conditions.  It
is important that the transmissivity value used
in the  leachate  collection   system design
calculations be  selected based  upon those
loaded conditions (U.S. EPA, 1988).  It is also
important to ensure that appropriate factors of
safety are used (Koerner, 1990).

The  flow  rate or transmissivity of geonets
may be evaluated by  ASTM D-4716.  This
flow rate may then be compared to design-by-
function equations  presented in U.S.  EPA
(1989). In the ASTM D-4716 flow test, the
proposed collector  cross section should be
modeled as closely as possible to actual field
conditions (U.S. EPA, 1989).

Figure 4-7 shows the flow rate "signatures" of
a geonet between two geomembranes (upper
curves) and the same geonet between a layer
of clay soil  and  a  geomembrane (lower
curves). The differences between the two sets
of   curves   represent   intrusion  of  the
geotextile/clay  into the  apertures  of the
geonet.  The curves are used to obtain a flow
rate for the particular geonet being designed
(U.S. EPA, 1989). Equations to determine the
design flow rate or transmissivity are  also
presented in U.S. EPA (1989), Giroud (1982),
Carroll (1987), Koerner (1990), and FHWA
(1987).

Generally, geonets perform well and result in
high factors of safety or performance design
ratios, unless creep (elongation under constant
stress)  becomes a problem  or  adjacent
materials intrude into apertures (U.S. EPA,
1989). For geonets, the most
critical specification is the ability to transmit
fluids under load.  The specifications  also
should  include  a minimum transmissivity
under expected landfill  operating (dynamic)
or   completion   (static)   loads.      The
specifications for thickness and  types of
material should be identified on the drawings
or   in   the  materials  section   of  the
specifications, and should be consistent with
the design calculations (U.S. EPA, 1988).

Geonets are often used on the sidewalls of
landfills because of their ease of installation.
They should be placed with the top ends in a
secure  anchor trench  with the  strongest
longitudinal  length extending down the slope.
The geonets  need not be seamed to each other
on the slopes, only tied at the edges, butted, or
overlapped.  They should be placed in a loose
condition,   not  stretched  or  placed in  a
configuration where they are bearing their
own weight in tension.  The construction
specifications should   contain  appropriate
installation requirements as described above
or   the  requirements   of  the   geonet
manufacturer.    All  geonets need  to  be
protected by a filter  layer or geotextile to
prevent clogging (U.S. EPA, 1988).

The  friction  factors  against  sliding  for
geotextiles, geonets, and geomembranes often
can be  estimated using manufacturers  data
because these materials do not exhibit the
range  of characteristics  as  seen in  soil
materials. However, it  is important that the
designer perform the  actual tests using site
materials  and that  the  sliding  stability
calculations accurately  represent the  actual
design configuration, site conditions, and the
specified material characteristics (U.S. EPA,
1988).
                                           169

-------
           c
           E

           "co
           •S
           d>
           75
           en

           o
           c
           E
           OJ
           75
           CE

           _o
           LL
                          5,000     10,000     15,000

                           Normal Stress (1lbs./sq. R)

                        (a) FML - Geonet - FML Composite
                                       20,000
                                                        20,000
         5,000     10,000     15,000

          Normal Stress (1lbs./sq. R)

(b) FML - Geonet - Geotextile - Clay Soil Composite
   Source: U.S. EPA. 1989.
Figure 4-1. Flow Rate Curves for Geonets in Two Composite Liner Configurations
                                       170

-------
                                    Design Criteria
Leachate Collection Pipes

All components of the leachate collection
system  must have sufficient strength  to
support the weight of the overlying waste,
cover system, and post-closure loadings, as
well  as  the  stresses  from  operating
equipment.  The component that  is most
vulnerable to compressive strength  failure is
the  drainage   layer  piping.    Leachate
collection  system  piping  can   fail  by
excessive deflection,  which  may  lead  to
buckling or collapse (USEPA, 1988). Pipe
strength  calculations   should   include
resistance to wall crushing, pipe deflection,
and  critical buckling pressure.   Design
equations and  information for most pipe
types can be obtained from the major pipe
manufacturers.    For more  information
regarding pipe  structural strength,  refer to
U.S. EPA (1988).

Perforated drainage pipes can provide good
long-term performance. These pipes have
been shown to transmit fluids rapidly and to
maintain good  service lives.  The depth of
the drainage layer around the pipe should be
deeper than  the diameter of the pipe.  The
pipes can be placed in trenches to  provide
the extra depth.   In  addition, the trench
serves as a sump (low point) for leachate
collection.  Pipes can be susceptible  to
particulate and  biological clogging similar
to the drainage  layer material.  Furthermore,
pipes also can be susceptible to deflection.
Proper  maintenance  and  design  of pipe
systems  can mitigate these  effects  and
provide  systems that function  properly.
Acceptable  pipe  deflections should  be
evaluated for the pipe material to  be used
(USEPA, 1989).

The  design  of  perforated collection pipes
should consider the following factors:
•    The   required  flow  using   known
     percolation impingement rates and pipe
     spacing;

•    Pipe  size using  required  flow and
     maximum slope; and

•    The structural strength of the pipe.

The pipe spacing may be determined by the
Mound Model. In the Mound Model (see
Figure 4-8), the maximum height of fluid
between  two  parallel  perforated drainage
pipes is equal to (U.S. EPA, 1989):
        _ L\fc r tan2a   _ tana
       s   2     c        c
     where c = q/k
        k = permeability
        q = inflow rate
        a = slope.

The two unknowns in the equation are:

  L = distance between the pipes; and
  c = amount of leachate.

Using a maximum allowable head, hmax, of 30
cm (12 in), the equation is usually solved for
"L" (U.S. EPA, 1989).

The amount of leachate, "c", can be estimated
in a variety of ways including the Water
Balance Method (U.S. EPA, 1989) and the
computer  model Hydrologic Evaluation  of
Landfill Performance (HELP). The HELP
Model is a quasi-two-dimensional hydrologic
model of  water movement  across,  into,
through, and out of landfills.  The model uses
climatologic, soil, and landfill design data and
incorporates  a  solution   technique  that
accounts for the effects of  surface  storage,
run-off, infiltration, percolation, soil-moisture
                                          171

-------
                              Subpart D
                                Inflow
Source: L'.5. £W. /9S9
          Figure 4-8. Definition of Terms for Mound Model
                       Flow Rate Calculations
                                 172

-------
                                     Design Criteria
storage,   evapotranspiration,  and  lateral
drainage.   The  program  estimates run-off
drainage and leachate that are expected to
result  from  a  wide variety of landfill
conditions, including open, partially open, and
closed landfill cells.  The model also may be
used to  estimate the depth of leachate above
the bottom liner of the landfill unit.  The
results may be used to compare designs or to
aid in  the  design  of leachate  collection
systems (U.S. EPA, 1988).

Once  the  percolation and pipe spacing are
known,  the design flow rate can be obtained
using the curve in Figure 4-9. The amount of
leachate percolation  at the particular site is
located on the x-axis.

The required flow rate is the point at which
this value intersects with the  pipe spacing
value determined  from the Mound Model.
Using this value of flow rate and the bottom
slope of the site, the required diameter for the
pipe can be determined (see  Figure 4-10).
Finally, the graphs in Figures 4-11  and 4-12
show  two ways to  determine whether the
strength of the pipe is adequate for the landfill
design.   In Figure  4-11,  the vertical  soil
pressure is located on the y-axis. The density
of the backfill material around the pipe is not
governed by strength, so it will  deform under
pressure rather than break.  Ten percent is the
absolute limiting deflection value for plastic
pipe. Using Figure 4-11, the applied pressure
on the pipe is located and traced to the trench
geometry, and then the pipe deflection value
is checked for its adequacy (U.S. EPA, 1989).

The LCS specifications should  include (U.S.
EPA,  1988):

•    Type of piping material;
•    Diameter and wall thickness;

•    Size  and  distribution  of  slots  and
     perforations;

•    Type of coatings (if any) used  in the
     pipe manufacturing; and

•    Type of pipe  bedding  material  and
     required compaction used to support the
     pipes.

The construction drawings and specifications
should clearly indicate the type of bedding to
be used under the pipes and the dimensions of
any trenches.   The  specifications  should
indicate how the pipe lengths are joined.  The
drawings  should show how the pipes are
placed with respect to the perforations. To
maintain the lowest possible leachate head,
there  should be perforations near the pipe
invert, but not directly at the invert.  The pipe
invert itself should  be solid  to allow for
efficient pipe flow at low volumes (U.S. EPA,
1988).

When drainage pipe systems are embedded in
filter and drainage layers, no unplugged ends
should be allowed.  The filter materials in
contact with the pipes should be appropriately
sized to prevent migration of the material into
the pipe.  The filter media, drainage layer, and
pipe network should be compatible and should
represent an integrated design.

Protection of Leachate Collection Pipes

The long-term  performance  of the  LCS
depends on the design used to protect pipes
from physical clogging (sedimentation) by the
granular drainage materials.  Use of a graded
material around the pipes is most effective if
accompanied  by  proper  sizing  of  pipe
perforations.  The Army Corps of
                                           173

-------
                            Subpart D

                    Percolation, in Inches per Month
          *Where b = width of area contributing to leachate collection pipe
           Source: U.S. EPA. 1989
Figure 4-9. Required Capacity of Leachate Collection Pipe
                               174

-------
   1000
o
o
    600
    300
    200
         1
        0.9
        0.8

        0.7

        0.6

        0.5

        0.4
                                                         \
                                                          A
                                                            V

                                                                    \
                                                                     \
                                                                                       \
    \
\    \
 \     \
  \     V

V
                                                                                                              \
                                                                                                                      \
                                                                                                                            \
                                                                                                                                 \
                                                                                                                                 \
                                                        •Sy"*-*^
U

 c
                                                               A3
                                                                                        K
                                                                                  «-:
                                                                                                    \---\
                                   ^s:

                                                                                                                 ^
                                                                           f^b
P
_c
&
ca
•s
VI
a
    100
                                                                      \^
                                                                        '"k
                                                                                                        "
                                                                                                         *

0.2
     50
        0.1
                                                 V
                                                                        \
                                                                           V*
                                                                                               Pipe Flowing Full
                                                                                      Based on Manning's Equation n=0.010
            0.1
                         0.2     0.3   0.4 0.5 0.6   0.8  1.0
                                                                  2.0     3.0   4.0  5.0 6.0  8.0  10
                                                                                                            10     20    30  40     60
           Source: U.S. EPA, 1989
                                                        Slope of Pipe in Feet per Thousand Feet
                                      Figure 4-10.  Leachate Collection Pipe Sizing Chart

-------
                                 Subpart D
   n
                    95% Soil
                     Density
         12.000
         10.000
          8.000
          6.000
          4.000
          2.000
                                Initial Effect of Ring Stiffness  i
                                                 i         i
85% Soil
 Density
                                                             90%
  75% Soil
  Density
                                                      75% Soil Density Plot of
                                                       Vertical Soil Strain £
               0       5       10       15       20       25

                 Ring Deflection, AY/D (%) = 6 Except as Noted

               Source: U.S. EPA. 1989
Figure 4-11.  Vertical Ring Deflection Versus Vertical Soil Pressure for
       18-inch Corrugated Polyethylene in High Pressure Soil Cell
                                    176

-------
                             Design Criteria
a
•
 B/D = 7.73
                                                         B/D = 7.5
                                                          B/D = 1.8

                                                          Vertical Soil Strain £
                                                         for Native Soil @
                                                          75% Density
                                                25
30
                      Ring Deflection, AY/D (%)
         Source: U.S. EPA, 1989
      Figure 4-12.  Example of the Effect of Trench Geometry
                 and Pipe Sizing on Ring Deflection
                                  177

-------
                                        Subpart D
Engineers  (GCA  Corporation,  1983)  has
established design criteria using graded filters
to prevent  physical  clogging of  leachate
drainage layers and piping by soil sediment
deposits.   When  installing  graded filters,
caution should be taken to prevent segregation
of the material (USEPA, 199la).

Clogging of the pipes and drainage layers of
the  leachate collection  system can occur
through several other mechanisms, including
chemical  and biological  fouling (USEPA,
1988).  The LCS should be designed with a
cleanout access capable of reaching all parts
of the collection system with standard pipe
cleaning equipment.

Chemical clogging can occur when dissolved
species  in the leachate precipitate in the
piping.   Clogging can be  minimized  by
periodically flushing pipes or by providing a
sufficiently steep slope in the system to allow
for  high flow velocities for self-cleansing.
These  velocities  are  dependent  on  the
diameter of the precipitate particles and on
their specific gravity.  ASCE (1969) discusses
these relationships.  Generally, flow velocities
should be in the range of one or two feet per
second  to  allow for self-cleansing of the
piping (U.S. EPA,  1988).

Biological clogging due to algae and bacterial
growth can be a serious  problem in MSWLF
units. There are  no universally  effective
methods  of  preventing   such  biological
growth.   Since organic materials  will  be
present  in  the landfill unit, there will be a
potential for biological clogging.  The system
design should include features that allow for
pipe system cleanings.  The  components of
the  cleaning system  should include (U.S.
EPA, 1991b):

•    A  minimum of six-inch diameter pipes
     to  facilitate cleaning;
•    Access   located   at   major   pipe
     intersections or  bends  to  allow  for
     inspections and cleaning; and

•    Valves, ports, or other appurtenances to
     introduce  biocides   and/or   cleaning
     solutions.

In its discussion of drainage layer protection,
the  following   section  includes  further
information concerning protection of pipes
using filter layers.

Protection of the High-Permeability
Drainage Layer

The openings in drainage materials, whether
holes in pipes, voids in gravel, or apertures in
geonets, must be protected against clogging
by accumulation of fine (silt-sized)  materials.
An intermediate  material  that has  smaller
openings than those of the drainage material
can be used as a filter between the waste and
drainage layer.  Sand may be used as filter
material, but has the disadvantage of taking
up vertical space (USEPA, 1989). Geotextiles
do not use up air space and can be used as
filter materials.

Soil Filter Layers

There are three parts to an analysis of a sand
filter that is placed above drainage material.
The first determines whether or not the filter
allows adequate flow of liquids.  The second
evaluates whether the void spaces are small
enough to prevent solids from being lost from
the upstream materials. The third estimates
the long-term clogging behavior of the filter
(U.S. EPA, 1989).

The particle-size distribution of the drainage
system and the particle-size distribution of the
invading (or upstream) soils are required
                                           178

-------
                                     Design Criteria
in the design of granular  soil (sand filter)
materials. The filter material should have its
large and small size particles intermediate
between the  two extremes.  Equations for
adequate flow and retention are:

     •  Adequate Flow:
        d85f>  (3 to 5)d15ds

     •  Adequate Retention:
        d15f<  (3 to 5)d85wf

     Where  f = required filter soil;
           d.s. = drainage  stone; and
           w.f = water fines.

There are no quantitative methods to assess
soil  filter  clogging,   although   empirical
guidelines   are  found   in  geotechnical
engineering references.

The  specifications for granular filter layers
that surround perforated pipes and that protect
the drainage layer from clogging are based on
a well-defined particle size  distribution. The
orientation and configuration of filter layers
relative to other LCS components  should be
shown  on  all  drawings  and  should  be
described, with ranges of particle sizes, in the
materials section of the specifications (U.S.
EPA, 1988a).

Thickness is an important placement criterion
for granular filter material.  Generally, the
granular filter materials will  be placed around
perforated  pipes  by   hand,  forming  an
"envelope."  The dimensions of the envelope
should be clearly stated on the drawings or in
the specifications.   This envelope  can  be
placed  at the  same  time  as the granular
drainage layer, but it is important that the
filter envelope protect all areas of the pipe
where the clogging potential  exists.   The plans
and
specifications should indicate the extent of the
envelope.  The construction quality  control
program should document that the envelope
was  installed according to the  plans  and
specifications (U.S. EPA, 1988).

A granular  filter layer is  generally placed
using the same earthmoving equipment as the
granular drainage layer. The final thickness
should be checked by optical survey or by
direct test pit measurement (U.S. EPA, 1988).

This filter layer is the uppermost layer in the
leachate collection system.  A landfill design
option includes a buffer layer, 12 inches thick
(30 cm) or more, to protect the filter layer and
drainage layer from damage due to traffic.
This final layer can be general fill, as long as
it is  no finer than the  soil  used in the filter
layer (U.S.  EPA,  1988).   However,  if the
layer has a low permeability, it will affect
leachate recirculation attempts.

Geotextile Filter Layers

Geotextile filter fabrics are often used.  The
open spaces in the fabric  allow liquid flow
while simultaneously  preventing  upstream
fine  particles  from  fouling  the   drain.
Geotextiles  save vertical space, are easy to
install, and have  the added  advantage of
remaining stationary under load.  Geotextiles
also  can be used as  cushioning  materials
above   geomembranes  (USEPA,  1989).
Because  geotextile filters are susceptible to
biological   clogging,  their use  in  areas
inundated by leachate (e.g., sumps,  around
leachate collection pipes, and trenches) should
be avoided.

Geotextile filter design parallels  sand filter
design  with some modifications (U.S. EPA,
1989).     Adequate  flow  is  assessed  by
                                           179

-------
                                         Subpart D
comparing    the    material    (allowable)
permittivity   to   the   design   imposed
permittivity.  Permittivity is measured by the
ASTM  D-4491 test  method.   The  design
permittivity  utilizes  an  adapted  form  of
Darcy's law. The resulting comparison yields
a design ratio, or factor of safety, that is the
focus of the design (U.S. EPA, 1989):
DR = 0allow/0reqd
where:
        0aiiow = permittivity from ASTM
             D-4491
        0reqd= (q/a) (l/hmax)
          q/a = inflow rate per unit area
     h max = 12 inches

The second part of the geotextile filter design
is determining the opening size necessary for
retaining the upstream soil or particulates in
the leachate. It is well established that the 95
percent opening size is related to particles to
be  retained  in  the  following  type  of
relationship:

095 < fct. (d50, CU, DR)

where:
     O95 = 95% opening size of
          geotextile;
     d50 = 50% size of upstream particles;
      CU = Uniformity of the upstream
   particle size; and
      DR = Relative density of the
          upstream particles.

The O95 size of a geotextile in the equation is
the opening size at which 5 percent of a given
value  should be less than the particle size
characteristics of the invading materials.  In
the test for the  O95 size of the geotextile,  a
sieve with a very coarse mesh in the bottom is
used as a support. The geotextile is placed on
top of the mesh and is bonded
to the inside so that the glass beads used in the
test cannot escape around the edges of the
geotextile filter. The particle-size distribution
of retained glass beads is compared to the
allowable  value using any  of a  number of
existing formulas (U.S. EPA, 1989).

The third consideration in geotextile design is
long-term  clogging. A test method for this
problem that may be adopted by ASTM is
called the  Gradient Ratio Test.  In this test,
the hydraulic gradient of 1 inch of soil plus
the underlying geotextile is compared with the
hydraulic gradient of 2 inches of soil.  The
higher the gradient ratio, the more likely that
a clog will occur.  The final ASTM gradient
ratio  test will  include failure criteria.   An
alternative to this test method is a long-term
flow  test  that also  is  performed  in  a
laboratory.  The test models a soil-to-fabric
system at the anticipated hydraulic gradient.
The   flow  rate   through  the  system  is
monitored.   A long-term  flow rate  will
gradually decrease until  it  stops altogether
(U.S. EPA, 1989).

The  primary function of a geotextile is to
prevent  the  migration  of fines  into  the
leachate pipes while allowing the passage of
leachate.  The most important specifications
are those  for  hydraulic conductivity and
retention.  The hydraulic conductivity of the
geotextile  generally should be at least ten
times the soil it is retaining. An evaluation of
the retention ability for loose soils  is based on
the average particle size of the soil and the
apparent opening size (AOS) of the geotextile.
The   maximum   apparent   opening   size,
sometimes called equivalent opening size, is
determined by the size of the soil  that will be
retained; a geotextile is then selected to meet
that specification.  The material specifications
should contain a range of AOS values for the
geotextile,  and
                                            180

-------
                                    Design Criteria
these AOS values should match those used in
the design calculations (U.S. EPA, 1988).

One of the advantages of geotextiles is their
light weight and  ease  of  placement.  The
geotextiles are brought to the site, unrolled,
and held down with sandbags until they are
covered with a protective  layer.   They are
usually overlapped, not seamed; however, on
slopes or in other configurations, they may be
sewn (U.S. EPA, 1988).

As with granular filter layers, it is important
that the design drawings  be clear in their
designation of geotextile placement so that no
potential route  of pipe or  drainage  layer
clogging is left unprotected.  If geotextiles are
used on a slope, they should be secured in an
anchor   trench   similar  to   those  for
geomembranes or geonets (U.S. EPA,  1988).

Leachate Removal System

Sumps, located in a recess at the low point(s)
within the leachate collection drainage layer,
provide one method for leachate  removal
from  the MSWLF unit.   In the past, low
volume  sumps  have  been   constructed
successfully from reinforced concrete pipe on
a concrete footing, and supported above the
geomembrane on  a steel plate to  protect the
geomembrane  from  puncture.   Recently,
however,    prefabricated    polyethylene
structures have become available.   These
structures may be suitable for replacing the
concrete components of the  sump and have
the advantage of being lighter in weight.

These sumps typically house a submersible
pump, which is positioned  close to the sump
floor to pump the leachate  and to maintain a
30  cm  (12 in) maximum leachate  depth.
Low-volume sumps, however, can present
operational problems. Because they may run
dry  frequently,  there   is  an   increased
probability of the submersible pumps burning
out.  For this reason, some landfill operators
prefer to have sumps placed at depths between
1.0 and 1.5 meters.  While head levels of 30
cm or less are to be maintained on the liner,
higher   levels   are  acceptable  in  sumps.
Alternatively, the sump may be designed with
level controls and with  a backup pump to
control initiation and shut-off of the pumping
sequence  and  to  have  the capability  of
alternating between the two pumps.  The
second pump also may be used in conjunction
with the primary pump during periods of high
flow (e.g., following storm events) and as a
backup if the primary pump fails to function.
A visible  alarm warning light to indicate
pump failure to the operator also may  be
installed.

Pumps used to remove leachate  from the
sumps  should be sized to ensure removal of
leachate at the maximum rate of generation.
These  pumps also should have a  sufficient
operating  head to lift  the leachate to the
required height  from the sump to the access
port. Portable vacuum pumps can be used if
the required lift height is within the limit of
the pump.   They can be  moved in sequence
from one leachate sump to another.  The type
of pump  specified  and  the leachate sump
access pipes should be compatible and should
consider performance needs under operating
and closure conditions (U.S. EPA,  1988).

Alternative  methods of leachate removal
include  internal   standpipes   and  pipe
penetrations through the geomembrane, both
of which allow  leachate  removal by  gravity
flow to either a leachate pond or exterior
pump station. If a leachate removal  standpipe
is used, it should be extended through the
entire landfill from liner to
                                          181

-------
                                        Subpart D
cover and then through the cover itself.  If a
gravity   drainage   pipe   that   requires
geomembrane penetration  is used, a  high
degree of care should be exercised in both the
design and construction of the penetration.
The penetration  should be  designed  and
constructed   in   a  manner  that  allows
nondestructive quality control testing of 100
percent of the seal between the pipe and the
geomembrane.  If not properly constructed
and fabricated, geomembrane penetrations can
become a  source of leakage through the
geomembrane.

Other Design Considerations

The stability of the individual  leachate
collection system components  placed on
geomembrane-covered  slopes  should be
considered.   A method for calculating the
factor of safety (FS) against sliding for soils
placed on a  sloped geomembrane surface is
provided in  Koerner (1990).   This method
considers  the factors  affecting the system,
including the slope length, the slope angle,
and   the  friction   angle  between   the
geomembrane and its cover soil.  Generally,
the slope angle is known and is specified on
the design drawings.  A minimum FS is then
selected. From the slope angle and the FS, a
minimum  allowable   friction   angle  is
determined,  and the various components of
the liner system  are selected based on this
minimum friction  angle.   If the  design
evaluation results in an unacceptably low FS,
then either the sidewall slope or the materials
should be changed to produce an  adequate
design (U.S. EPA, 1988).  For short slopes in
a landfill unit, the FS can be as low as 1.1 to
1.2 if the slope will be unsupported (i.e., no
waste will be filled against it) for only a  short
time, and if any failures that do occur can be
repaired fairly easily.  Longer slopes  may
require  higher factors of safety  due to the
potential of
sliding  material to tear the  geomembrane
along the slope or near the toe of the slope.

Construction Quality Assurance and
Quality Control

The following section is excerpted from U.S.
EPA (1992).  This section discusses quality
assurance  and  quality  control  (QA/QC)
objectives. For a more detailed discussion on
QA/QC and specific considerations, refer to
U.S. EPA (1992).

CQA/CQC Objectives

Construction  quality   assurance  (CQA)
consists of a planned  series of observations
and tests to ensure that the final product meets
project   specifications.      CQA   plans,
specifications, observations, and tests are used
to provide quantitative criteria with which to
accept the final product.

On  routine  construction projects, CQA is
normally the  concern  of  the owner and is
obtained using an  independent third-party
testing firm.  The independence of the third-
party inspection firm is important, particularly
when the owner is a corporation or other  legal
entity that has under its corporate "umbrella"
the  capacity to perform the CQA activities.
Although "in-house" CQA personnel may be
registered professional engineers, a perception
of misrepresentation may exist if CQA is not
performed by an independent third party.

The CQA officer should fully disclose any
activities or relationships with the owner
that  may  impact   his  impartiality  or
objectivity.      If   such   activities   or
relationships exist, the CQA  officer should
describe actions that have been  or can  be
taken to avoid, mitigate,  or  neutralize the
possibility  they  might  affect  the  CQA
                                           182

-------
                                    Design Criteria
officer's    objectivity.        Regulatory
representatives can then evaluate whether
these mechanisms are sufficient to ensure an
acceptable CQA product.

Construction quality control  (CQC) is an
on-going   process  of  measuring  and
controlling the characteristics of the product
in order to meet manufacturer's or project
specifications.  CQC is a production tool
that is employed by the manufacturer of
materials and by the contractor installing the
materials at the site.  CQA, by contrast, is a
verification tool employed by the facility
owner or  regulatory agency to ensure that
the materials and installations meet project
specifications.      CQC   is   performed
independently  of  the  CQA Plan.   For
example,  while   a   geomembrane  liner
installer will perform CQC testing of field
seams, the  CQA   program  will  require
independent  CQA testing  of those same
seams by a third-party inspector.

The CQA/CQC plans  are  implemented
through inspection activities that  include
visual  observations,  field  testing  and
measurements,   laboratory   testing,  and
evaluation of the  test  data.   Inspection
activities typically  are concerned with four
separate functions:

•    Quality Control (QC) Inspection by
     the   Manufacturer  provides  an  in-
     process measure of the product quality
     and its conformance with the project
     plans and specifications.  Typically,
     the manufacturer will  QC test results
     to certify that the product conforms to
     project plans and specifications.

     Construction  Quality Control (CQC)
     Inspection by the Contractor provides
     an in-process  measure of construction
     quality  and  conformance  with the
     project   plans   and  specifications,
     thereby  allowing  the  contractor  to
     correct the construction process if the
     quality of the product is not meeting
     the specifications and plans.

     Construction   Quality    Assurance
     (CQA)   Testing   by  the   Owner
     (Acceptance Inspection) performed by
     the owner usually  through the third-
     party testing firm, provides a measure
     of the final product  quality  and its
     conformance with project plans and
     specifications.  Due to  the  size and
     costs  of a  typical  MSWLF  unit
     construction project, rejection of the
     project at completion would be costly
     to all parties. Acceptance Inspections
     as portions of the  project  become
     complete allow deficiencies to be
     found  and  corrected   before   they
     become too large and costly.

     Regulatory   Inspection  often   is
     performed by a regulatory agency  to
     ensure that the final product conforms
     with   all   applicable   codes   and
     regulations.   In  some  cases, the
     regulatory   agency  will  use  CQA
     documentation and the as-built plans
     or  "record drawings"  to   confirm
     compliance with the regulations.

Soil Liner  Quality Assurance/Quality
Control

Quality  control  testing  performed  on
materials used  in construction of the landfill
unit includes source testing and construction
testing.  Source testing defines  material
properties that govern material  placement.
Source testing  commonly includes moisture
content, soil density, Atterberg limits, grain
size, and laboratory hydraulic conductivity.
Construction testing ensures that landfill
                                         183

-------
                                      Subpart D
construction   has  been   performed  in
accordance with  the  plans  and technical
specifications.      Construction   testing
generally  includes  tests  of soil moisture
content,   density,  lift  thickness,   and
hydraulic conductivity.

The method of determining compliance with
the  maximum   hydraulic   conductivity
criterion should be specified in the QA/QC
plan.  Some methods have included the use
of the criterion as a maximum value that
never  should  be  exceeded, while  other
methods have used statistical techniques to
estimate the  true  mean.    The  sample
collection program should  be designed to
work   with  the  method  of  compliance
determination.     Selection  of  sample
collection  points  should  be made  on a
random basis.

Thin wall sampling tubes generally are used
to collect  compacted clay  samples for
laboratory hydraulic conductivity testing.  It
is important to minimize disturbance of the
sample being collected. Tubes pushed into
the soil by a backhoe may  yield disturbed
samples. A recommended procedure (when
a  backhoe  is available  during  sample
collection) is to use the backhoe bucket as a
stationary support and push the tube into the
clay with a jack positioned between the clay
and the tube.  The sample hole should be
filled  with bentonite  or  a bentonite  clay
mixture, and compacted using short lifts of
material.

If geophysical  methods  are used for
moisture and  density  measurements,  it is
recommended  that alternative methods be
used less frequently to verify the accuracy
of  the   faster   geophysical   methods.
Additional     information    on   testing
procedures can be found  in U.S.  EPA
(1988b) and U.S. EPA (1990a).
Quality assurance testing  for  soil liners
includes the same testing requirements as
specified   above  for   control   testing.
Generally,  the tests  are performed  less
frequently  and  are  performed  by  an
individual or an entity independent of the
contractor.  Activities of the construction
quality  assurance  (CQA)  officer  are
essential    to   document    quality   of
construction.       The   CQA   officer's
responsibilities and   those  of the CQA
officer's staff members may include:

•    Communicating with the contractor;

•    Interpreting   and clarifying  project
     drawings and specifications with the
     designer, owner, and contractor;

•    Recommending     acceptance    or
     rejection by the owner/operator of
     work completed  by  the construction
     contractor;

•    Submitting   blind   samples  (e.g.,
     duplicates and blanks) for analysis by
     the contractor's testing staff or one or
     more  independent  laboratories,  as
     applicable;

•    Notifying  owner   or  operator  of
     construction  quality  problems  not
     resolved on-site in a timely manner;

•    Observing   the  testing  equipment,
     personnel, and procedures used by the
     construction  contractor to  check for
     detrimentally significant changes over
     time;

•    Reviewing     the     construction
     contractor's quality control recording,
     maintenance,     summary,     and
     interpretations   of  test   data  for
     accuracy and appropriateness; and
                                         184

-------
                                    Design Criteria
•    Reporting to the owner/operator on
     monitoring results.

Soil Liner Pilot Construction (Test Fill)

A pilot construction or test fill is a small-
scale test pad that can be used to verify that
the  soil,  equipment,  and  construction
procedures can produce a liner that performs
according to the construction drawings and
specifications.  An owner or operator may
want to consider the option of constructing
a test fill prior to the construction of the
liner.   A test  pad is useful  not  only  in
teaching people how to build a soil liner, it
also can function as a construction quality
assurance tool.  If the variables used to build
a test pad that achieves  a IxlO"7 cm/sec
hydraulic conductivity are followed exactly,
then the completed  full-size liner  should
meet  the regulatory requirements  (U.S.
EPA,  1989).  A test fill  may be a cost-
effective  method  for the  contractor  to
evaluate  the  construction  methods and
borrow source.  Specific factors that can be
examined/tested during construction of a
test fill include (U.S. EPA, 1988b):

•    Preparation   and    compaction   of
     foundation material  to  the  required
     bearing strength;

•    Methods of controlling uniformity  of
     the soil material;

•    Compactive  effort  (e.g.,  type  of
     equipment,  number of  passes)  to
     achieve  required  soil  density and
     hydraulic conductivity;

•    Lift   thickness   and    placement
     procedures to achieve uniformity  of
     density  throughout  a  lift  and the
     absence of apparent boundary effects
     between lifts or between placements in
     the same lift;

•    Procedures  for  protecting  against
     desiccation cracking or other site- and
     season-specific failure mechanisms for
     the finished liner or intermediate lifts;

•    Measuring the hydraulic conductivity
     on  the test fill  in  the  field and
     collecting samples of field-compacted
     soil for laboratory testing;

•    Test procedures for  controlling the
     quality of construction;

•    Ability of different types  of soil to
     meet      hydraulic     conductivity
     requirements in the field; and

•    Skill   and   competence   of   the
     construction     team,     including
     equipment  operators  and  quality
     control specialists.

Geomembrane Quality Assurance/
Quality Control Testing

As with the construction  of soil liners,
installation of geomembrane  liners should
be   in   conformance  with   a  quality
assurance/quality  control  plan.    Tests
performed  to  evaluate  the  integrity  of
geomembrane   seams   are   generally
considered to  be either "destructive"  or
"non-destructive."

Destructive Testing

Quality control testing of geomembranes
generally includes peel and shear testing of
scrap   test  weld   sections   prior   to
commencing  seaming  activities  and  at
periodic intervals  throughout  the   day.
Additionally,  destructive peel and  shear
field
                                          185

-------
                                      Subpart D
tests are performed  on samples from  the
installed seams.

Quality assurance testing generally requires
that an independent laboratory perform  peel
and shear tests of samples from installed
seams.   The  samples  may  be collected
randomly  or in  areas  of  suspect  quality.
HDPE  seams  are  generally   tested   at
intervals equivalent to one sample per every
300  to 400 feet of installed  seam  for
extrusion  welds,  and every  500 feet  for
fusion-welded seams. Extrusion seams on
HDPE require grinding prior to welding,
which can greatly diminish parent material
strengths  if excessive grinding  occurs.
Detailed discussion of polyethylene welding
protocol can be found in U.S. EPA (1991a).
For dual hot wedge seams in HDPE, both
the inner and outer seam may be subjected
to destructive shear tests at the independent
laboratory. Destructive samples of installed
seam welds are generally  cut into several
pieces and distributed to:

•    The installer to perform construction
     quality control field testing;

•    The  owner/operator to retain and
     appropriately catalog or archive; and

•    An independent laboratory for peel
     and shear testing.

If the test results  for a seam  sample do  not
pass the acceptance/rejection criteria, then
samples are cut from the same field seam on
both sides of the  rejected  sample location.
Samples are collected and tested until  the
areal limits of the low quality seam  are
defined.  Corrective measures should be
undertaken to repair the length  of seam that
has not passed  the  acceptance/rejection
criteria.   In many  cases,  this  involves
seaming a cap over the length of the rejected
seam or reseaming the affected area (U.S.
EPA, 1988).  In situations where the seams
continually fail testing, the seaming crews
may have to be retrained.

Non-Destructive Testing

Non-destructive test methods are conducted
in the field on an in-place geomembrane.
These test methods determine the integrity
of the geomembrane field  seams.   Non-
destructive test methods include the probe
test,  air lance,  vacuum  box, ultrasonic
methods  (pulse   echo,   shadow   and
impedance plane),  electrical  spark  test,
pressurized dual seam, electrical resistivity,
and hydrostatic tests.  Detailed discussion of
these test methods may be found in U.S.
EPA  (199la).   Seam  sections  that fail
appropriate, non-destructive tests must  be
carefully delineated, patched or reseamed,
and retested.  Large patches or reseamed
areas should be subjected to destructive test
procedures for quality assurance purposes.
The specifications should clearly describe
the degree to which  non-destructive and
destructive test  methods will be used  in
evaluating failed portions of non-destructive
seam tests.

Geomembrane Construction  Quality
Assurance Activities

The  responsibilities  of  the construction
quality assurance (CQA) personnel for the
installation   of  the  geomembrane  are
generally the  same as the responsibilities  for
the construction  of a soil liner  with the
following additions:

•    Observation of liner storage area and
     liners in storage, and handling of the
     liner as the panels are positioned in  the
     cell;
                                         186

-------
                                    Design Criteria
•    Observation of seam overlap, seam
     preparation  prior  to  seaming,  and
     material underlying the liner;

•    Observation  of destructive testing
     conducted on scrap test welds prior to
     seaming;

•    Observation   of  destructive   seam
     sampling, submission of the samples
     to an independent testing laboratory,
     and review of results for conformance
     to specifications;

•    Observation of all seams and panels
     for  defects  due to  manufacturing
     and/or handling and placement;

•    Observation  of all  pipe penetration
     boots and welds in the liner;

•    Preparation   of reports  indicating
     sampling  conducted  and  sampling
     results,   locations   of  destructive
     samples,   locations   of   patches,
     locations of  seams  constructed, and
     any problems encountered; and,

•    Preparation of record drawings of the
     liner installation, in some cases.

The last responsibility is frequently assigned
to the contractor, the owner's representative,
or the engineer.

Leachate Collection System
Construction Quality Assurance

The purpose  of leachate  collection system
CQA  is  to  document  that the system
construction  is  in accordance  with  the
design specifications.  Prior to construction,
all materials should be inspected to confirm
that
they  meet  the  construction  plans  and
specifications.  These include (U.S. EPA,
1988):

•    Geonets;

•    Geotextiles;

•    Pipe size, materials, and perforations;

•    Granular   material  gradation  and
     prefabricated    structures   (sumps,
     manholes, etc.);

•    Mechanical, electrical, and monitoring
     equipment; and

•    Concrete forms and reinforcement.

The leachate collection  system foundation
(geomembrane  or low  permeability  soil
liner) should be inspected  and surveyed
upon  its completion to  ensure that it has
proper grading and  is free  of debris and
liquids (U.S. EPA, 1988).

During    construction,    the    following
activities,   as   appropriate,   should  be
observed  and  documented  (U.S. EPA,
1988):

•    Pipe bedding  placement  including
     quality, thickness, and areal coverage;

•    Granular   filter   layer   placement
     including    material   quality   and
     thickness;

•    Pipe installation including location,
     configuration,   grades, joints,  filter
     layer placement, and final flushing;

•    Granular  drainage layer placement
     including  protection of  underlying
     liners, thickness, overlap with filter
                                         187

-------
                                     Subpart D
     fabrics and geonets if applicable, and
     weather conditions;

•    Geonet placement  including layout,
     overlap, and protection from clogging
     by granular material carried by wind
     or run-off during construction;

•    Geotextile/geofabric     placement
     including coverage and overlap;

•    Sumps and structure installation; and

•    Mechanical and electrical equipment
     installation including testing.

In addition to field observations, actual field
and laboratory  testing may be performed to
document that the materials meet the design
specifications.  These activities should be
documented  and   should   include  the
following (U.S. EPA, 1988):

•    Geonet and geotextile sampling and
     testing;

•    Granular  drainage  and  filter  layer
     sampling  and testing for grain size
     distribution; and

•    Testing   of    pipes   for   leaks,
     obstructions, and alignments.

Upon  completion  of construction,  each
component should be inspected to identify
any damage that may have occurred during
its installation, or  during construction  of
another component (e.g., pipe  crushing
during  placement  of granular  drainage
layer). Any damage that does occur should
be repaired, and these corrective measures
should be documented in the CQA records
(U.S. EPA, 1988).
4.4  RELEVANT POINT OF
     COMPLIANCE
     40 CFR §258.40(d)

4.4.1  Statement of Regulation

     (a) (See Statement of Regulation in
Section 4.2.1 of this guidance document for
the regulatory language for performance-
based design requirements.)

     (b) (See Statement of Regulation in
Section 4.3.1 of this guidance document for
the regulatory language for requirements
pertaining to composite liner and leachate
collection systems.)

     (c) (See Statement of Regulation in
Section 4.2.1 of this guidance document for
the regulatory language for performance-
based design requirements.)

     (d) The relevant point of compliance
specified by the Director of an approved
State shall be no more than 150 meters
from   the  waste  management  unit
boundary and shall be located on land
owned by the owner  of the MSWLF unit.

In  determining  the relevant point  of
compliance,  the  State Director  shall
consider at least the following factors:
     (1)     The
characteristics  of
surrounding land;
  hydrogeologic
the  facility  and
     (2) The volume and physical and
chemical characteristics of the leachate;

     (3) The  quantity,  quality,  and
direction of flow of ground water;

     (4) The proximity and  withdrawal
rate of the ground-water users;
                                        188

-------
                                   Design Criteria
     (5)  The  availability of alternative
drinking water supplies;

     (6)  The  existing  quality  of  the
ground water, including other sources of
contamination  and   their  cumulative
impacts on the ground water and whether
the ground water  is  currently used or
reasonably  expected  to  be  used  for
drinking water;

     (7) Public health,  safety, and welfare
effects; and

     (8)  Practicable  capability of  the
owner or operator.

4.4.2  Applicability

In States with approved permit  programs,
owners/operators may have the opportunity
to employ an alternative liner design, as per
§258.40(a)(l).  In these  situations, some
flexibility  is   allowed   in  terms   of
establishing a relevant point of compliance.
The relevant point of compliance may be
located a maximum of 150 meters from the
waste management unit boundary; however,
the location must be on property owned by
the MSWLF unit owner or operator.

In unapproved States the  relevant point of
compliance is  set at the waste management
unit boundary. The waste management unit
boundary is defined as  the vertical surface
located at the hydraulically downgradient
limit  of  the  unit.   This vertical surface
extends down into and through the  entire
thickness of the uppermost aquifer.

4.4.3  Technical Considerations

At least eight factors should be considered
in establishing the relevant point of
compliance for any design under §258.40.
The factors provide information needed to
determine if the  alternative boundary is
sufficiently protective of human health and
the environment and if the relevant point of
compliance  is adequate  to measure  the
performance of the disposal unit.

Site Hydrogeology

The  first factor to  be  considered  when
determining   the    relevant   point   of
compliance  is site  hydrogeology.    Site
hydrogeologic characteristics  should  be
used  to  identify additional  information
required  to  set  the relevant point  of
compliance.    The  site  data  should  be
sufficient to determine the lateral  well-
spacing  required to  detect contaminant
releases   to  the   uppermost   aquifer.
Hydrogeologic information required to  fully
characterize a site is presented in greater
detail in Section 5.6.3.

Leachate Volume and Physical
Characteristics

Data on  leachate volume and  quality are
needed  to  make  a determination  of the
"detectability" of leakage from the facility
at the relevant point of compliance. The net
concentration at  any  given  point resulting
from the transport of contaminants from the
landfill is a  function  of contaminant type,
initial  contaminant   concentration,   and
leakage  rate.    Assessment  of leachate
volume is discussed in Sections 4.2 and  4.3.
The  assessment  of contaminant fate  and
transport was discussed in Section 4.3.

Quality,  Quantity  and  Direction  of
Ground-Water Flow

The  hydrogeologic data  collected  should
provide information to assess the ground-
water  flow  rate,   ground-water  flow
                                         189

-------
                                      Subpart D
direction, and the volume of ground-water
flow.  Background ground-water  quality
data should be used to establish baseline
concentrations    of    the    monitoring
constituents.    This  information will  be
required   as   input   to   determine   if
contaminants from the  landfill unit have
been released  and have migrated to the
relevant point of compliance.

Ground-Water Receptors

The goal of establishing the relevant point
of compliance is to ensure early detection of
contamination  of the uppermost aquifer.
The distance  to the  relevant  point  of
compliance should allow sufficient time for
corrective measures to be implemented prior
to the migration of contaminants  to private
or public water supply wells.

Existing users of ground water immediately
downgradient from the  facility should be
identified on a map.   Users located at a
downgradient point  where contaminants
might be expected to migrate during the
active life and  post-closure care  period of
the  facility should be identified.

Alternative Drinking Water Supplies

Consideration  should  be  given  to  the
availability  of alternate drinking  water
supplies  in the event  of a ground-water
contamination problem. If the uppermost
aquifer  is  the  sole water  supply  source
available, all reasonable efforts should be
made to locate  the  relevant  point  of
compliance as close as possible to the actual
waste management unit boundary.

Existing Ground-Water Quality

The existing ground-water quality,  both
upgradient  and  downgradient  of  the
MSWLF
unit,  should  be   determined  prior  to
establishing   the   relevant   point   of
compliance  (see  Section  5.6.3).   The
performance  standard for landfill design
requires that  landfill units be designed so
that the concentrations listed in Table 1 are
not  exceeded  at   a  relevant  point  of
compliance.  Issues for approved States to
consider are whether the ground water is
currently used or is reasonably expected to
be used as a drinking water source when
setting a relevant point of compliance.  If
the  ground  water is not  currently  or
reasonably expected to be used for drinking
water,  the State may allow the relevant
point of compliance to be set near the 150-
meter limit.

Public Health, Welfare, Safety

Consideration should  be  given  to  the
potential overall effect on public health,
welfare, and safety of the proposed relevant
point of compliance. Issues that should be
considered include:

•    Distance to the nearest ground-water
     user or  potentially  affected  surface
     water;

•    The  response time  (based  on  the
     distance to the proposed relevant point
     of compliance) required to identify
     and  remediate or otherwise  contain
     ground   water  that  may  become
     impacted   and  potentially   affect
     downgradient water supplies; and

•    The risk that detection monitoring data
     may not be representative of a worst
     case release of contaminants to ground
     water.
                                         190

-------
                                   Design Criteria
Practicable Capability of the Owner or
Operator

If the relevant point of compliance is placed
farther from the waste management  unit
boundary, the  volume of water requiring
treatment, should the ground water become
contaminated, will increase.  One or more of
the following  conditions  could affect the
owner's or operator's practicable capability
(technical  and  financial)  to remediate
contaminant releases:

•    Area of impact, remedial costs, scope
     of remedial investigation, and  site
     characterization;

•    Increased response time due to higher
     costs and  increased technical scope of
     selected remedial method;

•    A reduction of the removal efficiency
     of treatment technologies; and

•    Increased difficulty  in ground-water
     extraction or containment if these
     technologies are chosen.

The Director may require some indication of
financial  capability of the owner or operator
to maintain a longer  and  more  costly
remedial   program  due  to  the  longer
detection  time frame associated  with  a
relevant point  of compliance  located  at a
greater distance from the waste management
unit boundary. Additional information on
remedial   actions for  ground  water  is
provided  in this document in Chapter 5.
4.5  PETITION PROCESS
     40 CFR §258.40(e)

4.5.1 Statement of Regulation

  (a) - (d) (See Statement of Regulation
in Sections 4.2.1,  4.3.1,  and 4.4.1 of this
guidance   document   for  regulatory
language.)

     (e)  If EPA does not promulgate a
rule establishing the  procedures  and
requirements for State  compliance with
RCRA Section 4005(c)(l)(B) by October
9,  1993,  owners   and  operators  in
unapproved States may utilize a design
meeting the performance  standard in
§258.40(a)(l) if the following conditions
are met:

     (1) The State determines the design
meets  the  performance  standard  in
§258.40(a)(l);

     (2)  The  State  petitions  EPA to
review its determination; and

     (3)   EPA  approves   the   State
determination or does not disapprove the
determination within 30 days.

[Note to Subpart D:  40 CFR Part 239 is
reserved to establish the procedures and
requirements for State  compliance with
RCRA Section 4005(c)(l)(B).]

4.5.2 Applicability

If EPA does not promulgate procedures and
requirements for state approval by October
9, 1993,  owners and operators of MSWLF
units located in unapproved States may be
able to  use  an  alternative design  (in
compliance  with  §258.40(a)(l))  under
certain circumstances.
                                        191

-------
                                      Subpart D
Owners  or  operators  of MSWLF  units
should contact the municipal  solid waste
regulatory  department in their State to
determine if their State has been approved
by the U.S. EPA.
                                         192

-------
                                   Design Criteria
4.6 FURTHER INFORMATION


4.6.1  REFERENCES

(Specific to Performance-Based Design Assessment and Solute Transport Modeling)

Abriola, L.M., and G.F. Finder, (1985a). A Multiphase Approach to the Modeling of Porous
     Media Contamination by Organic Compounds 1. Equation Development. Water Resources
     Research 21(1):11-18.

Abriola, L.M., and G.F. Finder, (1985b). A Multiphase Approach to the Modeling of Porous
     Media Contamination by Organic Compounds 2. Numerical Simulation. Water Resources
     Research 21(1): 19-26.

Aller, L., T. Bennett, J.H. Lehr, R.J. Petty, and G. Hackett, (1987).  DRASTIC: A Standardized
     System for Evaluation Ground Water Pollution Potential Using Hydrogeologic Settings.
     EPA-600/2-87-035, Kerr Environmental Research Lab, U.S. Environmental Protection
     Agency, Ada, Oklahoma.  455 pp.

Auerbach, S.I., C. Andrews, D. Eyman, D.D. Huff, P.A. Palmer,  and W.R. Uhte, (1984).
     Report of the Panel on Land Disposal. In: Disposal of Industrial and Domestic Wastes:
     Land and Sea  Alternatives.  National Research Council.  National  Academy Press.
     Washington, DC. pp. 73-100.

Beljin, M.S., (1985).  A  Program Package  of Analytical Models for  Solute Transport in
     Groundwater "SOLUTE".  BASIS, International Groundwater Modeling Center, Holcomb
     Research Institute, Butler University,  Indianapolis, Indiana. 163 pp.

Bond, F., and S. Hwang, (1988).  Selection Criteria for Mathematical Models Used in Exposure
     Assessments: Groundwater Models. EPA/600/8-88/075, U.S. Environmental Protection
     Agency, Washington, DC.

Boutwell, S.H., S.M. Brown, B.R. Roberts, and D.F. Atwood, (1986).  Modeling Remedial
     Actions at Uncontrolled Hazardous Waste Sites.  EPA/540/2-85/001, U.S. Environmental
     Protection Agency, Athens, Georgia.

Cederberg, G.A., R.L. Street, and J.O. Leckie, (1985).  A Groundwater Mass Transport and
     Equilibrium Chemistry Model for Multicomponent Systems. Water Resources Research,
     21(8):1095-1104.

Dean, J.D., P.S. Huyakorn, A.S. Donigian, Jr., K.S. Voos, R.W. Schanz, YJ.Meeks, and R.F.
     Carsel, (1989).  Risk of Unsaturated/Saturated Transport and Transformation of Chemical
     Concentrations (RUSTIC). EPA/600/3-89/048a, U.S. EPA, Athens, Georgia.
                                        193

-------
                                     Subpart D
de Marsily, G., (1986).  Quantitative Hydrogeology:  Groundwater Hydrology for Engineers.
     Academic Press, San Diego, California. 440 pp.

Dillon,  R.T., R.M. Cranwell, R.B. Lantz, S.B. Pahwa,  and D.S. Ward,  (1978).   Risk
     Methodology for Geologic Disposal of Radioactive Waste: The Sandia Waste Isolation
     Flow and Transport (SWIFT) model.  Sand 78-1267/NUREG-CR-0424, Sandia national
     Laboratories, Albuquerque, New Mexico.

Domenico, P.A., and  V.V. Palciauskas, (1982).  Alternative Boundaries in  Solid Waste
     Management.  Ground Water, 20(3):303-311.

Domenico, P.A., and G.A. Robbins, (1985).  A New Method for Contaminant Plume Analysis.
     Ground Water, 23(4):476-485.

Donigian, A.S., and  P.S.C.  Rao, (1990).   Selection,  Application, and  Validation  of
     Environmental Models.  In: Proceedings of the International Symposium on Water Quality
     Modeling of Agricultural Non-Point Sources, Part 2. D.G. DeCoursey (ed.).  ARS-81,
     U.S. Department of Agriculture Agricultural Research Services, pp. 577-600.

Erdogen, H., and R.D. Heufeld, (1983).  Modeling Leachates at Landfill Boundaries. Journal
     of Environmental Engineering, 109(5): 1181-1194.

Faust, C.R., J.H. Guswa, and J.W. Mercer, (1989). Simulation of Three-Dimensional Flow of
     Immiscible Fluids Within and Below the Unsaturated Zone.  Water Resources Research,
     25(12):2449-2464.

Freeze, R.A., and J.A. Cherry, (1979). Ground Water. Prentice-Hall, Englewood Cliffs, New
     Jersey. 604 pp.

GeoTrans, Inc., (1985).  SWANFLOW: Simultaneous Water, Air and Non-Aqueous Phase
     Flow, Version 1.0-Code Documentation.  Herndon, Virginia. 97 pp.

Grove, D.B., and K.G.  Stollenwerk, (1987). Chemical Reactions Simulated by Groundwater
     Quality Models. Water Resources Bulletin, 23(4):601-615.

Gupta, S.K., C.R. Cole, C.T. Kincaid, and F.E. Kaszeta, (1982).  Description and Applications
     of the FE3DGW and CFEST Three-dimensional Finite Element Models, Battelle Pacific
     NW Laboratories, Richland, Washington.

Gupta,  S.K., C.T. Kincaid, P. Meyer, C. Newbill, and C.R.  Cole, (1982).   CFEST:
     Multidimensional Finite Element Code for the  Analysis of Coupled Fluid, Energy and
     Solute Transport. PNL-4260, Battelle Pacific NW Laboratories, Richland, Washington.
                                        194

-------
                                   Design Criteria
Gureghian, A.B., D.S. Ward, and R.W. Cleary, (1980).  A Finite Element Model for the
     Migration  of Leachate from a Sanitary Landfill in Long Island, New York - Part I:
     Theory.  Water Resources Bulletin, 16(5):900-906.

Guvanasen, V., (1984).  Development of A Finite Element Code  and Its Application to
     Geoscience Research. Proceedings 17th Information Meeting of the Nuclear Fuel Waste
     Management Program, Atomic Energy of Canada, Ltd. Technical Record TR-199.  pp.
     554-566.

Haji-Djafari, S., (1983). User's Manual GEOFLOW Groundwater Flow and Mass Transport
     Computer Program. D'Appolonia, Pittsburgh, Pennsylvania.

Huyakorn, P.S. et al., (1984).  Testing and Validation of Models for Simulating Solute
     Transport  in Groundwater: Development, Evaluation and Comparison of Benchmark
     Techniques.   GWMI 84-13,  International Groundwater Modeling  Center, Holcomb
     Research Institute, Indianapolis, Indiana.

Huyakorn, P.S., M.J. Ungs, L.A. Mulkey, and E.A. Sudicky, (1987).  A Three-Dimensional
     Analytical Method for Predicting Leachate Migration.  Ground Water, 25(5):588-598.

Huyakorn, P.S., H.O. White, Jr., V.M. Guvanasen, and B.H. Lester, (1986). TRAFRAP:  A
     Two-dimensional Finite  Element Code for Simulating Fluid Flow  and  Transport of
     Radionuclides in Fractured Porous Media. FOS-33, International Groundwater Modeling
     Center, Holcomb Research Institute, Butler University, Indianapolis, Indiana.

Javandel, I., C. Doughty,  and C.F. Tsang,  (1984).  Groundwater Transport: Handbook of
     Mathematical Models. Water Resources Monogram 10, American Geophysical Union,
     Washington, DC 228 pp.

Keely, J.F., (1987). The Use of Models in Managing Ground-Water Protection Programs. U.S.
     Environmental Protection Agency. EPA/600/8-87/003, Ada, Oklahoma. 72 pp.

Keely, J.F., (1989).  Performance Evaluations of Pump-and-Treat Remediations. EPA/540/4-
     89/005, U.S. Environmental Protection Agency, Ada, Oklahoma. 19 pp.

Kincaid, C.T., J.R. Morrey, and I.E. Rogers, (1984a). Geohydrochemical Models for Solute
     Migration- Volume 1: Process Description and Computer Code Selection.  EA-3417,
     Electric Power Research Institute, Palo Alto, California.

Kincaid,  C.T.,  J.R. Morrey, S.B.  Yabusaki,  A.R. Felmy,  and  I.E.  Rogers,  (1984b).
     Geohydrochemical Models for Solute Migration- Volume 2: Preliminary Evaluation of
     Selected Computer Codes.   EA-3417,  Electric Power Research Institute, Palo  Alto,
     California.
                                        195

-------
                                     Subpart D
Kipp, K.L., Jr., (1987).  HST3D: A Computer Code for Simulation of Heat and Solute Transport
     in  Three-Dimensional Groundwater Flow Systems.  WRI 86-4095, U.S. Geological
     Survey, Lakewood, Colorado.

Konikow, L.F., and J.D. Bredehoeft, (1985).  Method-of-Characteristics Model for Solute
     Transport (1985 revision). U.S. Geological Survey.

Lindstrom, F.T., and L. Boersma, (1989).  Analytical Solutions for Convective-Dispersive
     Transport in Confined Aquifers with Different Initial and Boundary Conditions. Water
     Resources Research, 25(2):241-256.

Lu, J.C.S., B.  Eichenberger, and R.J. Stearns, (1985). Leachate Migration from Municipal
     Landfills. Pollution Technology Review No.  19. Noyes Publications, Park Ridge, New
     Jersey.  453 pp.

Mercer, J.W., S.D. Thomas, and B.  Ross, (1983).  Parameters and Variables Appearing in
     Repository  Siting Models.  NUREG/CR-3066.  Prepared for U.S. Nuclear Regulatory
     Commission, Washington, DC.  244 pp.

Mulkey, L.A., A.S. Donigian,  Jr., T.L. Allison, and C.S. Raju, (1989).  Evaluation of Source
     Term Initial Conditions  for Modeling Leachate Migration from Landfills. U.S. EPA,
     Athens, Georgia.

Narasimhan, T.N., A.F. White, and T. Tokunaga. 1986. Groundwater Contamination From an
     Inactive Uranium Mill Tailings Pile 2. Application of a Dynamic Mixing Model.  Water
     Resources Research, 22(13): 1820-1834.

National Research Council,  (1990).  Ground Water Models:  Scientific and Regulatory
     Applications.  National Academy Press, Washington, DC. 320 pp.

Nelson, R.W.,  and J.A.  Schur,  (1980). PATHS Groundwater Hydrologic Model. PNL-3162,
     Battelle Pacific NW Laboratories, Richland, Washington.

Osborne, M., and J. Sykes, (1986). Numerical Modeling of Immiscible Organic Transport at
     the Hyde Park Landfill. Water Resources Research, 22(l):25-33.

Ostendorf, D.W., R.R. Noss, and D.O. Lederer, (1984). Landfill Leachate Migration through
     Shallow Unconfmed Aquifers, Water Resources Research, 20(2):291-296.

Oster, P. A. Review of Ground-Water Flow and Transport Models  in the Unsaturated Zone,
     (1982).   NUREG/CR-2917, PNL-4427.  Pacific Northwest Laboratory, Richland,
     Washington.

Prakash, A., (1984). Groundwater Contamination Due to Transient Sources of Pollution. J. of
     Hydraulic Engineering, 110(11): 1642-1658.
                                        196

-------
                                   Design Criteria
Prickett, T.A., T.G. Naymik, and C.G. Lonnquist, (1981). A Random-Walk Solute Transport
     Model for Selected Groundwater Quality Evaluations.  Bulletin 65, Illinois State Water
     Survey, Champaign, Illinois.

Runchal, A.K., (1985). PORFLOW: A General Purpose Model for Fluid Flow, Heat Transfer
     and Mass Transport in Anisotropic, Inhomogeneous, Equivalent Porous Media, Volume
     I: Theory, Volume II: User's Manual.   ACRI/TN-O11. Analytic and Computational
     Research, Inc. West Los Angeles,  California.

Runchal, A.K., (1985). Theory and Application of the PORFLOW Model for Analysis of
     Coupled  Flow,  Heat  and Radionuclide Transport in Porous  Media.  Proceedings,
     international Symposium on Coupled Processes Affecting the Performance of a Nuclear
     Waste Repository, Berkeley, California.

Salhotra, A.M., P. Mineart, S. Sharp-Hansen,  and T. Allison, (1990). Multimedia Exposure
     Assessment Model (MULTIMED) for Evaluating the Land Disposal of Wastes—Model
     Theory.  Prepared for U.S. Environmental Protection Agency, Environmental Research
     Laboratory, Athens, Georgia.

Schroeder, A.C., A.C.  Gibson, and M.D. Smolen, (1984).  The Hydrologic Evaluation of
     Landfill Performance  (HELP) Model,  Volumes  I and II.   EPA/530/SW-009 and
     EPA/530/SW-010, U.S. Environmental Protection Agency, Cincinnati, Ohio.

Sharp-Hansen, S., C. Travers, P. Hummel, and T. Allison,  (1990).  A Subtitle D Landfill
     Application Manual for the Multimedia Exposure Assessment Model (MULTIMED).
     Prepared for the U.S. EPA, Environmental Research Laboratory, Athens, Georgia.

Summers,  K.V., S.A.  Gherini, M.M. Lang, M.J. Ungs, and K.J. Wilkinson,  (1989). MYGRT
     Code Version 2.0: An IBM Code for Simulating Migration of Organic and Inorganic
     Chemicals in Groundwater.  EN-6531.   Electric Power Research Institute, Palo Alto,
     California.

Temple, Barker and  Sloane, Inc.,  (1988). Draft Regulatory Impact Analysis of Proposed
     Revisions to Subtitle D Criteria for Municipal Solid Waste Landfills. Prepared for Office
     of Solid Waste, U.S. Environmental Protection Agency.

Theis, T.L., D.J. Kirkner and A.A. Jennings, (1982).  Multi-Solute Subsurface Transport
     Modeling for Energy Solid Wastes.  Technical Progress Report for the Period September
     1,  1981-August  31, 1982, COO-10253-3, Prepared for Ecological Research Division,
     Office of Health and Environmental Research, U.S. Department of Energy.

Travers, C.L., and S. Sharp-Hansen, (1991). Leachate Generation and Migration at Subtitle D
     Facilities: A Summary and Review of Processes and Mathematical Models.  Prepared for
     U.S. EPA, Environmental Research Laboratory, Athens, Georgia.
                                        197

-------
                                     Subpart D
Travis, B., (1984).  TRACR3D: A Model of Flow and Transport in Porous/Fractured Media.
     LA-9667-MS. Los Alamos National Laboratory, Los Alamos, New Mexico.

Unge, M.J., K.V. Summers, and S.A. Gherini, (1986).  MYGRT: An IBM Personal Computer
     Code for Simulation Solute Migration in Groundwater, User's Manual. EA-4545-CCM.
     Electric Power Research Institute, Palo Alto, California.

U.S. EPA, (1988). Superfund Exposure Assessment Manual. EPA/540/1-88/001, Washington,
     DC. NTISNo. PB89-135859.  157pp.

U.S. EPA, (1993). Compilation of Ground-Water Models; PB93-209401; U.S. EPA; Office of
     Solid Waste; Washington, D.C.

van der Heijde, P.K., Y. Bachmat, J.  Bredehoeft, B.  Andrews, D. Holtz, and S.  Sebastian,
     (1985).   Groundwater  Management:  The  Use of Numerical Models.   American
     Geophysical Union, Washington, D.C.

van der Heijde, P.K., and M.S. Beljin,  (1988a).  Model Assessment for Delineating Wellhead
     Protection Areas. EPA-440/6-88-002, U.S. EPA, Washington, DC.

van der Heijde, P.K., El-Kadi, A.I., and S.A. Williams, (1988b). Groundwater Modeling: An
     Overview and Status Report. EPA/600/2-89/028, U.S. EPA, Ada, Oklahoma.

van Genuchten, M.T., (1978). Simulation Models and Their Application to Landfill Disposal
     Siting; A Review of Current Technology.  In Land Disposal of Hazardous Wastes. EPA-
     660/9-78-016, U.S.  EPA, Cincinnati, Ohio.

van Genuchten, M.T., and WJ. Alves, (1982).  Analytical Solutions of the One-Dimensional
     Convective-Dispersive Solute Transport Equation. USDA, Technique Bulletin No. 1661.
     U.S. Department of Agriculture, Washington, DC.

Versar, Inc., (1987). Current and Suggested Practices in the Validation of Exposure Assessment
     Models, Draft Report.  Prepared for U.S. EPA Office  of Health and Environmental
     Assessment, Exposure Assessment Group, Washington, DC.  EPA Contract No. 69-02-
     4254, Work Assignment No.  55.

Voss, C.I., (1984).  SUTRA:  A Finite Element Simulation Model for Saturated-Unsaturated
     Fluid Density-Dependent Groundwater Flow with Energy  Transport or Chemically
     Reactive Single Species  Solute Transport.  Water Resources Investigations 84-4369, U.S.
     Geological Survey.

Walton, W.C., (1984). 35 Basic Groundwater Model Programs for Desktop Microcomputers.
     GWMI 84-06/4,  International Groundwater Modeling Center, Holcomb Research Institute,
     Butler University, Indianapolis, Indiana.
                                        198

-------
                                   Design Criteria
Weaver, I, C.G. Enfield, S. Yates, D. Kreamer, and D. White, (1989). Predicting Subsurface
     Contaminant Transport and Transformation: Considerations for Model Selection and Field
     Validation. U.S. EPA, Ada, Oklahoma.

Yeh,  G.T., (1981).  AT123D:  Analytical, Transient, One-,  Two-, Three-Dimensional
     Simulation of Waste Transport in the Aquifer System.  Publication No. 1439. Oak Ridge
     National Laboratory, Oak Ridge, Tennessee.

Yeh, G.T., (1990). Users' Manual of a Three-Dimensional Hybrid Lagrangian-Eulerian Finite
     Element Model of WASTE Transport through Saturated-Unsaturated Media.  Pennsylvania
     State University, University Park, PA.

Yeh, G.T., and D.S. Ward, (1981). FEMWASTE:  A Finite-Element Model of Waste Transport
     through Saturated-Unsaturated Porous Media.   ORNL-5601.   Oak Ridge National
     Laboratory, Oak Ridge, Tennessee.

Yeh, G.T., and D.S. Ward, (1987).  FEMWATER:  A Finite-Element Model of Water Flow
     through Saturated-Unsaturated Porous Media.  ORNL-5567/R1.  Oak Ridge National
     Laboratory, Oak Ridge, Tennessee.
4.6.2  REFERENCES

                            (Specific to Design Criteria)

ASCE, (1969).  "Design and Construction of Sanitary and Storm Sewers"; ASCE Manual on
     Engineering Practice; No. 37.

Bear, Jacob and Arnold Veruijt, (1987).  "Modeling Groundwater Flow and Pollution"; D.
     Reidel Publishing Company; Dordracht, Holland.

Benson, Craig H. and David E. Daniel, (1990).  "Influence of Clods on Hydraulic Conductivity
     of Compacted Clay"; Journal of Geotechnical Engineering; Volume 116, No. 8; August,
     1990.

Bonaparte,  R. and Gross, B.A., (1990). "Field Behavior of Double-Liner Systems.  In Waste
     Containment Systems:   Construction,  Regulation, and  Performance, Edited by R.
     Bonaparte. Geotechnical Pub 1.26, ASCE.

Carroll, Jr., R.G., (1987).  "Hydraulic Properties of Geotextiles." Geotextile Testing and the
     Design Engineers,  ASTEM 952, American Society for Testing and Materials, Philadelphia,
     PA, pp 7-20.

COE, (1970). "Laboratory Soils Testing"; EMI 110-2-1906; Headquarters, Department of the
     Army; Office of the Chief of Engineers; Washington, DC  20314.
                                        199

-------
                                     Subpart D
FHWA, (1985).  "FHWA Geotextile Engineering Manual."  Contract No.l DTP H61-83-C-
     00150.

FHWA, (1990).   "Geotextile Design & Construction  Guidelines.   Contract  No. FHWA
     DTFH61-86-C-00102.

GCA Corporation, (1983).  "Draft Permit Writers'  Guidance Manual for Hazardous Waste
     Treatment, Storage, and Disposal Facility"; 1983.

Giroud, J.P., (1982). "Filter Criteria for Geotextiles," Proceeding 2nd International Conference
     on Geotextiles, Las Vegas, Nevada.

Giroud, J.P.  and  R.  Bonaparte,  (1989).   "Leakage  Through  Liners  Constructed with
     Geomembranes - Part I:  Geomembrane Liners"; Geotextiles and Geomembranes 8(2);
     0266-1144/89; pp. 27-67; Elsevier Science Publishers Ltd., England, Great Britain.

Giroud, J.P.  and  R.  Bonaparte,  (1989).   "Leakage  Through  Liners  Constructed with
     Geomembranes - Part II:  Composite Liners"; Geotextiles and Geomembranes 8(2); 0266-
     1144/89; pp. 71-111; Elsevier Science Publishers Ltd., England, Great Britain.

Giroud, J.P., A. Khatami and K. Badu-Tweneboah, (1989).  "Technical Note - Evaluation of the
     Rate  of Leakage Through Composite Liners"; Geotextiles and Geomembranes 8; 0266-
     1144/89; pp. 337-340; Elsevier Science Publishers Ltd., England, Great Britain.

Haxo, H.E., Jr., (1983). "Analysis and Fingerprinting of Unexposed and Exposed Polymeric
     Membrane Liners"; Proceedings of Ninth Annual Research Symposium: Land Disposal,
     Incineration,  and Treatment of Hazardous Waste; EPA/600/9-83/018; U.S. EPA;
     Cincinnati, Ohio.

Haxo, H.E., Jr., J.A. Miedema and H.A. Nelson,  (1984).  "Permeability of Polymeric Membrane
     Lining Materials"; Matrecon, Inc.;  Oakland, California; International Conference on
     Geomembranes; Denver, Colorado.

Industrial  Fabrics Association International (1990).  "1991 Specifiers Guide;" Geotechnical
     Fabrics Report, Volume 8, No. 7, 1990.

Javendale, I.,  C.  Doughty and C.F. Tsang, (1984).  "Groundwater Transport; Handbook of
     Mathematical Models"; American Geophysical Union; Washington, DC 20009.

Jayawickrama, P.W., K.W.  Brown, J.C. Thomas and R.L. Lytton, (1988).  "Leakage Rates
     Through Flaws in Membrane Liners"; Journal of Environmental Engineering; Vol.  114,
     No. 6; December, 1988.
                                        200

-------
                                  Design Criteria
Kastman, Kenneth A., (1984). "Hazardous Waste Landfill Geomembrane:  Design, Installation
     and Monitoring"; Woodward-Clyde Consultants,  Chicago,  Illinois;  International
     Conference on Geomembranes; Denver, Colorado.

Koerner, Robert M., (1990).  "Designing  with Geosynthetics"; 2nd Edition; Prentice Hall;
     Englewood-Cliffs, New Jersey 07632.
Radian Corporation, (1987).  "Technical Data Summary: Hydraulic Performance of Minimum
     Technology Double Liner Systems"; Radian Corporation; Austin, Texas 78766 for U.S.
     EPA; Contract No. 68-01-7310; Task 7-4.

U.S. EPA, (1982).  "Landfill and Surface Impoundment Performance Evaluation"; SW-869;
     Charles A. Moore; U.S. EPA. NTIS PB-81-166357.

U.S. EPA, (1983).  "Lining of Waste Impoundment and Disposal Facilities";  SW-870; U.S.
     EPA; Office of Solid Waste and Emergency Response; Washington, DC 20460. NTIS PB-
     81-166365 Revised: PB-86-192796.

U.S. EPA, (1987a). "Background Document on Bottom Liner Performance in Double-Lined
     Landfills and Surface Impoundments"; EPA/530/SW-87/013; U.S. EPA; Washington, DC.
     NTISPB-87-182291.

U.S. EPA, (1987b) " Characterization of MWC Ashes and Leachates from MSW Landfills,
     Monofills and Co-Disposal Sites: Volume VI of VII; Characterization of Leachates from
     Municipal Solid Waste Disposal Sites and Co-Disposal Sites"; EPA/530/SW-87/028F,
     Washington, D.C. NTIS PB-88-127998.

U.S. EPA, (1988).  "Guide to Technical Resources for the Design of Land Disposal Facilities";
     EPA/625/6-88/018; U.S. EPA; Risk Reduction Engineering Laboratory; Center for
     Environmental Research Information; Cincinnati, Ohio 45268.

U.S. EPA, (1988a). Superfund Exposure Assessment Manual. EPA/540/1-88/001, Washington,
     D.C., NTIS No. PB89-135.859, 157 pp.

U.S. EPA, (1988b).   "Design, Construction and Evaluation  of Clay  Liners  for Waste
     Management Facilities; EPA/530/SW-86/007F; U.S. EPA; Office of Solid Waste and
     Emergency Response; Washington, DC  20460.  NTIS PB-86-184496.

U.S. EPA, (1988c). "Groundwater Modeling: An Overview and Status Report";
     EPA/600/2-89/028; U.S. EPA; Environmental Research Laboratory; Ada,  Oklahoma
     74820.  NTIS PB-89-224497.
                                       201

-------
                                    Subpart D
U.S. EPA,  (1988d).  "Multimedia Exposure Assessment Model for Evaluating the Land
     Disposal of Hazardous Wastes, Volume I"; Woodward-Clyde Consultants, Oakland, CA
     94607-4014 for U.S. EPA; Environmental Research Laboratory; Office of Research and
     Development; Athens, Georgia  30613.

U.S. EPA,  (1988e).  "Lining of Waste Containment and Other Impoundment Facilities";
     EPA/600/2-88/052; U.S. EPA; Risk Reduction Engineering Laboratories; Cincinnati, Ohio
     45268. NTISPB-89-129670.

U.S. EPA, (1989).  "Seminar Publication - Requirements for Hazardous Waste Landfill Design,
     Construction and Closure"; EPA/625/4-89/022; U.S. EPA; Center for Environmental
     Research Information; Office of Research and Development; Cincinnati, Ohio 45268.

U.S. EPA, (1990a). "Seminars - Design and Construction of RCRA/CERCLA Final Covers",
     CERI 90-50; U.S. EPA; Office of Research and Development; Washington, DC  20460.

U.S. EPA, (1990b). "Draft - LDCRS Flow Data from Operating Units - Technical Support for
     Proposed Liner/Leak Detection System Rule"; Geoservices, Inc. Consulting Engineers;
     Norcross, Georgia 30093.

U.S.  EPA,  (1990c).   "Relationship of  Laboratory- and Field-Determined Hydraulic
     Conductivity in Compacted Clay Layer"; EPA/600/2-90/025; U.S. EPA; Risk Reduction
     Engineering Laboratory; Cincinnati, Ohio 45268. NTIS PB-90-257775.

U.S. EPA, (1991a).  "Technical Guidance Document: Inspection Techniques for the Fabrication
     of Geomembrane Field Seams"; EPA 530/SW-91/051, May 1991, Cincinnati, Ohio.

U.S. EPA, (1991b). "Landfill Leachate Clogging of Geotextiles (and Soil) Filters";
     EPA/600/2-91/025, August 1991; Risk Reduction Engineering Laboratory; Cincinnati,
     Ohio, 45268. NTIS PB-91-213660.

U.S. EPA, (1992). "Technical Guidance Document: Construction Quality Management for
     Remedial Action and Remedial Design Waste Containment Systems"; EPA/540/R-92/073,
     October 1992; Risk Reduction Engineering Laboratory, Cincinnati, Ohio  45268  and
     Technology Innovation Office, Washington, D.C. 20460.

4.6.3  Models

List of Contacts for Obtaining Leachate Generation and Leachate Migration Models

Center for Exposure Assessment Modeling (CEAM), U.S. EPA, Office of Research and
Development, Environmental Research Laboratory,  Athens, Georgia  30605-2720, Model
Distribution Coordinator (706) 546-3549, Electronic Bulletin Board System (706) 546-3402:
MULTIMED, PRZM, FEMWATER/FEMWASTE, LEWASTE/3DLEWASTE
                                       202

-------
                                  Design Criteria
Electric Power Research Institute, Palo Alto, California, (214) 655-8883: MYGRT,
FASTCHEM

Geo-Trans Inc., 46050 Manekin Plaza, Suite 100, Sterling, VA 20166, (703) 444-7000:
SWANFLOW, SWIFT, SWIFT II, SWIFT III, SWIFT/386.

Geraghty & Miller, Inc., Modeling Group, 10700 Parkridge Boulevard, Suite 600 Reston,
VA 22091: MODFLOW386, MODPATH386, MOC386, SUTRA386, Quickflow,

International Groundwater Modeling Center, Colorado School of Mines, Golden, Colorado
(303) 273-3103: SOLUTE, Walton35, SEFTRAN, TRAFRAP,

National Technical Information Services (NTIS), 5285 Port Royal Road, Springfield, VA
22161, (703) 487-4650: HELP

Dr. Zubair Saleem, U.S. EPA, 401 M Street SW, Washington, DC, 20460, (202) 260-4767:
EPACML, VHS

Scientific Software Group, P.O. Box 23041, Washington, DC 20026-3041 (703) 620-9214:
HST3D, MODFLOW, MOC, SUTRA, AQUA, SWIMEV.
                                       203

-------
        CHAPTER 5

        SUBPART E
GROUND-WATER MONITORING
  AND CORRECTIVE ACTION

-------
                                   CHAPTER 5
                                   SUBPART E

                              TABLE OF CONTENTS

5J,   INTRODUCTION	211

12   APPLICABILITY 40 CFR $258.50 (a) & fb) 	211
      5.2.1  Statement of Regulation	211
      5.2.2  Applicability  	212
      5.2.3  Technical Considerations	212

53.   COMPLIANCE SCHEDULE 40 CFR $ 258.50 (c)	214
      5.3.1  Statement of Regulation	214
      5.3.2  Applicability  	214
      5.3.3  Technical Considerations	214

14   ALTERNATIVE COMPLIANCE SCHEDULES 40 CFR 258.50 (d)(e) & (a)	215
      5.4.1  Statement of Regulation	215
      5.4.2  Applicability  	216
      5.4.3  Technical Considerations	217

15   QUALIFICATIONS 40 CFR 258.50 (f)  	217
      5.5.1  Statement of Regulation	217
      5.5.2  Applicability  	218
      5.5.3  Technical Considerations	218

16   GROUND-WATER MONITORING SYSTEMS 40 CFR $258.51 (a)fb)(d)	219
      5.6.1  Statement of Regulation	219
      5.6.2  Applicability  	220
      5.6.3  Technical Considerations	221
             Uppermost Aquifer  	221
             Determination of Background Ground-Water Quality 	221
             Multi-Unit Monitoring Systems	222
             Hydrogeological Characterization  	224
             Characterizing Site Geology	225
             Monitoring Well Placement	235
                                        206

-------
17   GROUND-WATER MONITORING WELL DESIGN AND CONSTRUCTION 40
      CFRS258.51 (c) 	241
      5.7.1  Statement of Regulation	241
      5.7.2  Applicability 	241
      5.7.3  Technical Considerations	241
             Monitoring Well Design	244
                   Well Casing  	244
                   Filter Pack Design 	248
                   Surface Completion 	250

18   GROUND-WATER SAMPLING AND ANALYSIS REQUIREMENTS
      40 CFR $258.53  	253
      5.8.1  Statement of Regulation	253
      5.8.2  Applicability 	254
      5.8.3  Technical Considerations	255
             Sample Collection  	255
                   Frequency	255
                   Water Level Measurements  	256
                   Well Purging  	256
                   Field Analyses 	258
                   Sample Withdrawal and Collection	258
             Sample Preservation and Handling	260
                   Sample Containers 	262
                   Sample Preservation	262
                   Sample Storage and Shipment 	262
             Chain-of-Custody Record	263
                   Sample Labels 	263
                   Sample Custody Seal  	264
                   Field Logbook 	264
                   Sample Analysis Request Sheet 	265
                   Laboratory Records 	265
             Analytical Procedures 	265
             Quality Assurance/Quality Control	266
                   Field Quality Assurance/Quality Control  	266
                   Validation	267
             Documentation	268
                                        207

-------
12    STATISTICAL ANALYSIS 40 CFR $258.53 (g)-(i)  	268
       5.9.1  Statement of Regulation	268
       5.9.2  Applicability  	270
       5.9.3   Technical Considerations	271
             Multiple Well Comparisons	272
             Tolerance and Prediction Intervals	273
             Individual Well Comparisons	274
             Intra-Well Comparisons	274
             Treatment of Non-Detects  	274

5.10   DETECTION MONITORING PROGRAM 40 CFR $258.54 	274
       5.10.1 Statement of Regulation	274
       5.10.2 Applicability  	276
       5.10.3 Technical Considerations	277
             Independent Sampling for Background 	277
             Alternative List/Removal of Parameters	279
             Alternative Frequency  	279
             Notification  	280
             Demonstrations of Other Reasons For Statistical Increase  	280
             Demonstrations of Other Sources of Error	281

5.11   ASSESSMENT MONITORING PROGRAM 40 CFR §258.55(a)-(f)	281
       5.11.1 Statement of Regulation	281
       5.11.2 Applicability  	283
       5.11.3 Technical Considerations	285
             Alternative List  	285
             Alternative Frequency  	285

5.12   ASSESSMENT MONITORING PROGRAM 40 CFR §258.55(e)  	286
       5.12.1 Statement of Regulation	286
       5.12.2 Applicability  	287
       5.12.3 Technical Considerations	287
             Release Investigation	288
             Property Boundary Monitoring Well  	288
             Notification of Adjoining Residents and Property Owners  	288
             Demonstrations of Other Sources of Error	288
             Return to Detection Monitoring	289

5.13   ASSESSMENT MONITORING PROGRAM 40 CFR §258.55(h)-(i)	289
       5.13.1 Statement of Regulation	289
       5.13.2 Applicability  	290
       5.13.3 Technical Considerations	290
                                        208

-------
5.14  ASSESSMENT OF CORRECTIVE MEASURES 40 CFR $258.56 	291
      5.14.1  Statement of Regulation	291
      5.14.2  Applicability 	291
      5.14.3  Technical Considerations	291
             Source Evaluation  	292
                   Plume Delineation  	292
             Ground-Water Assessment	294
             Corrective Measures Assessment	295
             Active Restoration	296
             Plume Containment	297
             Source Control	298
             Public Participation 	298

5.15  SELECTION OF REMEDY 40 CFR $258.57 (a)-fb) 	298
      5.15.1  Statement of Regulation	298
      5.15.2  Applicability 	299
      5.15.3  Technical Considerations	299

5.16  SELECTION OF REMEDY 40 CFR $258.57 (c)  	299
      5.16.1  Statement of Regulation	299
      5.16.2  Applicability 	300
      5.16.3  Technical Considerations	301
             Effectiveness of Corrective Action	301
             Effectiveness of Source Reduction	302
             Implementation of Remedial Action	302
                   Practical Capability  	302
             Community Concerns	303

5.17  SELECTION OF REMEDY 40 CFR $258.57 (d)	303
      5.17.1  Statement of Regulation	303
      5.17.2  Applicability 	304
      5.17.3  Technical Considerations	304

5.18  SELECTION OF REMEDY 40 CFR $258.57 (e)-(f)	305
      5.18.1  Statement of Regulation	305
      5.18.2  Applicability 	306
      5.18.3  Technical Considerations	306
                                        209

-------
5.19   IMPLEMENTATION OF THE CORRECTIVE ACTION PROGRAM
      40 CFR $258.58 (a)	307
      5.19.1 Statement of Regulation	307
      5.19.2 Applicability  	308
      5.19.3 Technical Considerations	308
            Monitoring Activities	308
            Interim Measures	308

5.20   IMPLEMENTATION OF THE CORRECTIVE ACTION PROGRAM
      40 CFR $258.58 fb)-(d)	309
      5.20.1 Statement of Regulation	309
      5.20.2 Applicability  	309
      5.20.3 Technical Considerations	310

5.21   IMPLEMENTATION OF THE CORRECTIVE ACTION PROGRAM
      40 CFR $258.58 (e)-(g)	311
      5.21.1 Statement of Regulation	311
      5.21.2 Applicability  	311
      5.21.3 Technical Considerations	312

5.22 FURTHER INFORMATION	313
      5.22.1 References	313
                                      210

-------
                                   CHAPTER 5
                                   SUBPART E
                      GROUND-WATER MONITORING
                         AND CORRECTIVE ACTION
5.1   INTRODUCTION

The Criteria establish ground-water monitoring and corrective action requirements for all existing
and new MSWLF units and lateral expansions of existing units except where the Director of an
approved State suspends the requirements because there is no potential for migration of leachate
constituents from the unit to the uppermost aquifer.  The Criteria include requirements for the
location, design, and installation of ground-water monitoring systems and set standards for ground-
water sampling and analysis.  They also provide specific statistical methods and decision criteria for
identifying a significant change in ground-water quality. If a significant change in ground-water
quality occurs, the Criteria require an assessment of the nature and extent of contamination followed
by an evaluation and implementation of remedial measures.

Portions of this chapter are based on a draft technical  document developed for EPA's hazardous
waste program. This document, "RCRA Ground-Water Monitoring: Draft Technical Guidance"
(EPA/530-R-93-001), is undergoing internal review, and may change.  EPA chose to incorporate
the information from the draft document into this chapter because the draft contained the most
recent information available.
5.2 APPLICABILITY
    40 CFR §258.50 (a) & (b)

5.2.1  Statement of Regulation

 (a) The requirements in this Part apply to
MSWLF  units, except  as  provided  in
paragraph (b) of this section.

 (b)     Ground-water     monitoring
requirements   under  §258.51  through
§258.55 of this Part may be suspended by
the Director of an approved State for  a
MSWLF unit if the owner or operator can
demonstrate that there is no potential for
migration of hazardous constituents from
that  MSWLF unit  to  the  uppermost
aquifer (as defined in §258.2) during the
active life of the unit and the post-closure
care period. This demonstration must be
certified  by  a  qualified  ground-water
scientist and approved by the Director of
an  approved State,  and must be based
upon:

 (1)    Site-specific    field    collected
measurements, sampling, and  analysis of
physical, chemical, and biological processes
affecting contaminant fate and transport,
and

 (2) Contaminant  fate   and   transport
predictions that maximize contaminant
migration and consider impacts on human
health and environment.
                                        211

-------
                                        Subpart E
5.2.2 Applicability

The ground-water monitoring requirements
apply to all existing MSWLF units, lateral
expansions  of  existing  units,  and  new
MSWLF  units  that  receive  waste  after
October 9,  1993.   The  requirements for
ground-water monitoring may be suspended if
the Director of an approved State finds that no
potential exists for migration of hazardous
constituents from the MSWLF unit to  the
uppermost aquifer during the active life of the
unit, including closure or post-closure care
periods.

The "no potential for migration" demonstra-
tion must be based upon site-specific informa-
tion relevant to the fate and transport of any
hazardous constituents that may be expected
to be released from the unit.  The predictions
of fate and transport must identify the max-
imum anticipated concentrations of constitu-
ents migrating to the uppermost aquifer so
that a protective assessment of the potential
effects to human health and the environment
can be made.  A  successful demonstration
could  exempt  the  MSWLF  unit  from
requirements of §§258.51  through 258.55,
which  include installation  of ground-water
monitoring  systems,  and   sampling   and
analysis for both detection  and assessment
monitoring  constituents.   Preparing No-
Migration  Demonstrations  for  Municipal
Solid Waste Disposal Facilities-Screening
Tool is a guidance  document  describing a
process owners/ operators can use to prepare
a   no-migration   demonstration  (NMD)
requesting  suspension of the ground-water
monitoring requirements.

5.2.3 Technical Considerations

All MSWLF units that receive waste after the
effective date of Part 258 must comply with
the ground-water monitoring requirements.
The Director of an  approved State  may
exempt an owner/operator from the ground-
water monitoring requirements at
§258.51  through §258.55 if the owner  or
operator   demonstrates  that there  is  no
potential for hazardous constituent migration
to the uppermost  aquifer throughout the
operating,  closure, and post-closure  care
periods of the unit. Owners and operators of
MSWLFs not located in approved States will
not be eligible for this  waiver  and will be
required  to comply with  all ground-water
monitoring requirements. The "no-migration"
demonstration must be certified by a qualified
ground-water scientist and approved by the
Director  of an approved State.   It must be
based on site-specific field measurements and
sampling  and  analyses  to  determine the
physical, chemical, and biological processes
affecting the fate and transport of hazardous
constituents.   The demonstration  must be
supported by site-specific data and predictions
of the maximum contaminant migration.
Site-specific information must include, at a
minimum,  the  information  necessary  to
evaluate   or  interpret  the  effects of the
following  properties   or  processes  on
contaminant fate and transport:

Physical Properties or Processes:

•  Aquifer    Characteristics.    including
   hydraulic conductivity, hydraulic gradient,
   effective porosity, aquifer thickness, de-
   gree of saturation, stratigraphy, degree of
   fracturing and secondary porosity of soils
   and   bedrock,   aquifer   heterogeneity,
   ground-water discharge,  and ground-water
   recharge areas;

•  Waste Characteristics, including quantity,
   type,   and  origin   (e.g.,  commercial,
   industrial, or small quantity generators of
   unregulated hazardous wastes);
                                           212

-------
                     Ground-Water Monitoring and Corrective Action
•  Climatic Conditions,  including annual
   precipitation,    leachate    generation
   estimates,  and  effects   on  leachate
   quality;

•  Leachate   Characteristics,   including
   leachate composition,  solubility, density,
   the presence of immiscible constituents,
   Eh, and pH; and

•  Engineered  Controls,  including liners,
   cover systems, and aquifer controls (e.g.,
   lowering the water table).  These should
   be evaluated under design and failure
   conditions  to  estimate their  long-term
   residual performance.

Chemical Properties or Processes:

•  Attenuation of  contaminants  in  the
   subsurface,    including    adsorption/
   desorption   reactions,  ion   exchange,
   organic content  of soil, soil water pH,
   and consideration  of possible reactions
   causing  chemical  transformation   or
   chelation.

Biological Processes:

•  Microbiological Degradation, which may
   attenuate target  compounds  or  cause
   transformations     of    compounds,
   potentially forming more toxic chemical
   species.

The alternative design section of Chapter
5.0 discusses these and other processes that
affect contaminant fate and solute transport.

When  owners or operators prepare  a  no-
migration  demonstration, they  must  use
predictions  that  are  based  on  maximum
contaminant  migration both from the unit
and  through  the  subsurface  media.
Assumptions  about  variables   affecting
transport should  be biased toward over-
estimating  transport and the anticipated
concentrations.   Assumptions  and  site
specific data that are used in the fate and
transport predictions should conform with
transport   principles    and   processes,
including adherence to  mass-balance and
chemical  equilibria  limitations.   Within
these    physicochemical     limitations,
assumptions  should be biased toward the
objective   of  assessing  the  maximum
potential impact on human health and the
environment.    The  evaluation  of  site-
specific data  and assumptions may include
some of the following approaches:

•  Use of the upper bound of known aquifer
   parameters  and  conditions  that will
   maximize contaminant transport (e.g.,
   hydraulic    conductivity,    effective
   porosity,   horizontal   and   vertical
   gradients), rather than average values

•  Use of the lower range of known aquifer
   conditions and parameters that tend to
   attenuate or retard contaminant transport
   (e.g., dispersivities, decay coefficients,
   cation   exchange  capacities, organic
   carbon    contents,     and   recharge
   conditions), rather than average values

•  Consideration of the  cumulative impacts
   on water quality, including both existing
   water quality data and cumulative health
   risks posed  by hazardous constituents
   likely to migrate from the MSWLF unit
   and other potential or known sources.

A discussion of mathematical approaches
for  evaluating  contaminant  or  solute
transport is provided in Chapter 5.
                                         213

-------
                                     Subpart E
5.3 COMPLIANCE SCHEDULE
    40 CFR § 258.50 (c)

5.3.1  Statement of Regulation*

*[NOTE:  EPA finalized several revisions
to 40 CFR Part 258 on October 1, 1993
(58 FR 51536), and these revisions delay
the effective date for some categories of
landfills.  More detail  on the content of
the   revisions  is   included  in   the
introduction.]

 (c) Owners  and operators of MSWLF
units must comply with the ground-water
monitoring  requirements  of  this part
according to the following schedule unless
an alternative schedule is specified under
paragraph (d):

 (1) Existing MSWLF units and lateral
expansions less than one mile from  a
drinking  water  intake  (surface   or
subsurface) must be in  compliance with
the    ground-water       monitoring
requirements  specified  in §§258.51  -
258.55 by October 9, 1994;

 (2) Existing MSWLF units and lateral
expansions greater than one mile but less
than  two miles from a drinking water
intake (surface or subsurface) must be in
compliance   with   the  ground-water
monitoring  requirements specified  in
§§258.51 - 258.55 by October 9, 1995;

 (3) Existing MSWLF units and lateral
expansions greater than two miles from a
drinking  water  intake  (surface   or
subsurface) must be in  compliance with
the    ground-water       monitoring
requirements  specified  in §§258.51  -
258.55 by October 9, 1996;
 (4) New  MSWLF units must be  in
compliance  with  the   ground-water
monitoring requirements specified  in
§§258.51 - 258.55 before waste can  be
placed in the unit.

5.3.2 Applicability

The rule establishes a  self-implementing
schedule for owners or operators in States
with programs that are deemed inadequate
or not  yet approved. As  indicated in the
Statement  of Regulation, this  schedule
depends on the distance of the MSWLF unit
from drinking water sources.  Approved
States may  specify an alternative schedule
under §258.50 (d), which is discussed in
Section 5.4.

Existing units and lateral  expansions less
than one mile from a drinking water intake
must be in compliance with the  ground-
water monitoring requirements by October
9,  1994. If the units are greater than one
mile but less than two miles from a drinking
water intake, they must be in compliance by
October 9, 1995. Those units located more
than two miles from a drinking water intake
must be in compliance by October 9, 1996
(see Table 5-1).

New MSWLF units, defined as units that
have not received waste prior to October 9,
1993, must be  in compliance with these
requirements   before   receiving  waste
regardless  of the  proximity to a water
supply  intake.

5.3.3 Technical Considerations

For most facilities, these requirements will
become applicable 3 to 5  years after the
promulgation date of the rule. This period
                                       214

-------
                    Ground-Water Monitoring and Corrective Action
      Table 5-1. Compliance Schedule for Existing Units and Lateral Expansions
                        in States with Unapproved Programs
Distance From Water Supply Intake
One mile or less
More than one mile but less than two
miles
More than two miles
Time to Comply
From October 9, 1991
3 Years
4 Years
5 Years
should provide sufficient time for the owner
or operator to conduct site investigation and
characterization studies to comply with the
requirements  of 40 CFR §258.51 through
§258.55.   For those facilities  closest  to
drinking water intakes, the period provides
2 to 3 years to assess seasonal variability in
ground-water quality.   A drinking water
intake includes water supplied to a  user
from either a surface water or ground-water
source.

5.4  ALTERNATIVE COMPLIANCE
    SCHEDULES
    40 CFR 258.50 (d)(e) & (g)

5.4.1  Statement of Regulation

 (d) The Director of an approved State
may specify an alternative schedule for
the  owners  or  operators  of existing
MSWLF units and lateral expansions to
comply    with    the    ground-water
monitoring  requirements  specified  in
§§258.51 - 258.55.  This schedule must
ensure that  50  percent  of all existing
MSWLF units  are in compliance by
October 9, 1994 and all existing MSWLF
units  are in
compliance by  October  9,  1996.   In
setting  the compliance  schedule,  the
Director of an approved  State  must
consider potential risks posed by the unit
to human health and the environment.
The   following  factors   should  be
considered in determining potential risk:

 (1) Proximity    of    human    and
environmental receptors;

 (2) Design of the MSWLF unit;

 (3) Age of the MSWLF unit;

 (4) The size of the MSWLF unit;

 (5) Types   and  quantities  of wastes
disposed, including sewage sludge; and

 (6) Resource  value of the  underlying
aquifer, including:

 (i)   Current and future uses;

 (ii)   Proximity and withdrawal rate of
users; and

 (iii)  Ground-water     quality    and
quantity.
                                       215

-------
                                      Subpart E
 (e)  Once  established  at a  MSWLF
unit, ground-water monitoring shall be
conducted throughout the active life and
post-closure care period of that MSWLF
unit as specified in §258.61.

 (f)  (See  Section  5.5  for   technical
guidance on  qualifications of a ground-
water scientist.)

 (g) The Director  of an approved State
may establish alternative schedules for
demonstrating     compliance     with
§258.51(d)(2), pertaining to notification
of placement of certification in  operating
record;  § 258.54(c)(l),  pertaining to
notification that statistically significant
increase  (SSI) notice  is in  operating
record; § 258.54(c)(2) and (3), pertaining
to an assessment monitoring program;
§ 258.55(b), pertaining to sampling and
analyzing  Appendix  II  constituents;
§258.55(d)(l), pertaining to placement of
notice (Appendix II constituents detected)
in record  and  notification of  notice in
record;  § 258.55(d)(2),  pertaining to
sampling  for  Appendix  I  and  II;
§  258.55(g),  pertaining  to  notification
(and placement of notice in record) of SSI
above ground-water protection standard;
§   258.55(g)(l)(iv)  and  §  258.56(a),
pertaining to assessment of corrective
measures; §   258.57(a),  pertaining to
selection of remedy and notification of
placement in  record;  §  258.58(c)(4),
pertaining to  notification of placement in
record   (alternative corrective  action
measures); and § 258.58(f), pertaining to
notification   of placement  in  record
(certification  of remedy completed).
5.4.2  Applicability

The Director of an  approved State may
establish   an   alternative  schedule  for
requiring owners/operators of existing units
and lateral expansions to comply with the
ground-water  monitoring  requirements.
The alternative schedule is to ensure that at
least fifty percent of all existing MSWLF
units within a given State are in compliance
by October 9, 1994 and that all units are in
compliance by October 9, 1996.

In establishing the alternative schedule, the
Director of an approved State may use site-
specific information to assess the relative
risks posed by different waste management
units  and will allow  priorities  to  be
developed at the State  level.  This site-
specific information (e.g.,  proximity  to
receptors, proximity and withdrawal rate of
ground-water users, waste quantity, type,
containment design and age) should enable
the Director to assess potential risk to the
uppermost aquifer.  The resource value of
the aquifer to be monitored (e.g.,  ground-
water quality  and quantity,  present and
future uses, and withdrawal rate of ground-
water users) also may be considered.

Once  ground-water monitoring has been
initiated, it must continue throughout the
active life, closure, and post-closure care
periods.  The post-closure period may last
up to  30 years or more after  the MSWLF
unit has received a final cover.

In addition to  establishing  alternative
schedules  for compliance with  ground-
water monitoring requirements, the Director
of  an  approved  State  may   establish
alternative schedules for certain
                                         216

-------
                     Ground-Water Monitoring and Corrective Action
sampling  and  analysis  requirements  of
§§258.54 and 258.55, as well as corrective
action requirements  of §§258.56, 258.57,
and 258.58. See Table 5-2 for a summary
of  notification  requirements  for which
approved States may establish alternative
schedules.

5.4.3  Technical Considerations

The rule allows approved States flexibility
in  establishing  alternate  ground-water
monitoring  compliance  schedules.    In
setting an  alternative schedule,  the  State
will consider potential impacts to human
health and the environment.   Approved
States have the option to address MSWLF
units  that  have environmental  problems
immediately.   In establishing alternative
schedules   for  installing   ground-water
monitoring systems
at existing MSWLF units, the Director of an
approved State may  consider information
including the  age  and design  of existing
facilities. Using this type of information, in
conjunction with a knowledge of the wastes
disposed, the  Director should be able to
qualitatively assess or rank facilities based
on  their   risk  to  local  ground-water
resources.
5.5  QUALIFICATIONS
     40 CFR 258.50 (f)

5.5.1 Statement of Regulation

 (f)  For the purposes of this Subpart, a
qualified ground-water scientist  is  a
scientist or  engineer who has received a
baccalaureate or post-graduate degree in
                  Table 5-2.  Summary of Notification Requirements
Section
§258.51(d)(2)
§258.54(c)(l)
§258.55(d)(l)
§258.57(a)
§258.58(c)(4)
§258.58(f)
Description
14 day notification period after well installation
certification by a qualified ground-water scientist (GWS)
14 day notification period after finding a statistical increase
over background for detection parameter(s)
14 day notification period after detection of Appendix II
constituents
14 day notification period after selection of corrective
measures
14 day notification period prior to implementing alternative
measures
14 day notification period after remedy has been completed
and certified by GWS
                                         217

-------
                                      Subpart E
the natural sciences  or engineering and
has sufficient training and experience in
ground-water  hydrology  and  related
fields as may be demonstrated by State
registration, professional certifications,
or completion of accredited university
programs that enable that individual to
make  sound  professional  judgements
regarding   ground-water   monitoring,
contaminant  fate  and  transport, and
corrective action.

5.5.2  Applicability

The   qualifications  of  a  ground-water
scientist  are   defined  to   ensure  that
professionals of appropriate capability and
judgement are consulted when required by
the Criteria.   The ground-water  scientist
must possess the fundamental education and
experience necessary  to evaluate ground-
water  flow,   ground-water  monitoring
systems,  and  ground-water  monitoring
techniques  and methods.   A ground-water
scientist  must understand and be able to
apply methods to solve  solute  transport
problems  and   evaluate   ground-water
remedial  technologies. His or her education
may  include  undergraduate  or  graduate
studies   in  hydrogeology,  ground-water
hydrology,  engineering  hydrology,  water
resource     engineering,     geotechnical
engineering,    geology,    ground-water
modeling/ground-water computer modeling,
and other aspects of the  natural  sciences.
The qualified ground-water scientist must
have  a college degree but need  not have
professional certification, unless required at
the  State   or  Tribal   level.     Some
States/Tribes   may   have   certification
programs  for ground-water  scientists;
however, there are no recognized Federal
certification programs.
5.5.3  Technical Considerations

A qualified ground-water  scientist must
certify work performed  pursuant  to  the
following provisions of the ground-water
monitoring    and   corrective    action
requirements:
   No     potential     for
   demonstration (§258.50(b))
migration
   Specifications  concerning the number,
   spacing, and depths of monitoring wells
   (§258.51(d))

   Determination  that contamination was
   caused by  another source or  that  a
   statistically  significant increase resulted
   from an error in sampling, analysis, or
   evaluation (§§258.54 (c)(3) and 258.55
•  Determination that compliance  with  a
   remedy  requirement is not technically
   practicable (§258. 58(c)(l))

•  Completion of remedy (§25 8.5 8(f)).

The owner or operator must determine that
the  professional  qualifications  of  the
ground-water specialist are in accordance
with the regulatory definition. In general, a
certification  is  a signed document that
transmits   some   finding   (e.g.,   that
monitoring wells were installed according
to acceptable practices  and standards at
locations and depths appropriate for a given
facility). The certification must be placed
in the operating record of the facility, and
the State Director must be notified that the
certification  has been  made.   Specific
details  of  these  certifications  will  be
                                         218

-------
                    Ground-Water Monitoring and Corrective Action
addressed in the order in which they appear
in this guidance document.

Many  State   environmental  regulatory
agencies have  ground-water scientists on
staff.  The owner or operator of a MSWLF
unit or facility is not necessarily required to
obtain certification from  an  independent
(e.g., consulting)  ground-water scientist and
may, if agreed to by the Director  in an
approved  State,  obtain approval by  the
Director  in lieu of  certification  by an
outside individual.
5.6 GROUND-WATER
    MONITORING SYSTEMS
    40 CFR §258.51 (a)(b)(d)

5.6.1  Statement of Regulation

 (a) A ground-water monitoring system
must  be  installed  that consists  of a
sufficient number of wells, installed at
appropriate locations and depths, to yield
ground-water samples from the upper-
most aquifer (as defined in  §258.2) that:

 (1) Represent the quality of background
ground water that has not been affected
by leakage from a unit.  A determination
of  background  quality  may  include
sampling   of   wells   that   are    not
hydraulically  upgradient of the waste
management area where:

 (i) Hydrogeologic conditions  do  not
allow the owner or operator to determine
what wells are hydraulically upgradient;
or

 (ii) Sampling at other wells will provide
an  indication  of background ground-
water quality that is as representative or
more
representative than that provided by the
upgradient wells; and

 (2) Represent the quality of ground
water  passing the  relevant  point of
compliance specified by the Director of
an approved State under §258.40(d) or at
the waste management unit boundary in
unapproved States. The downgradient
monitoring system must be installed at
the relevant point of compliance specified
by  the Director of an approved  State
under  §258.40(d)  or  at  the  waste
management    unit    boundary   in
unapproved States that ensures detection
of ground-water contamination in  the
uppermost  aquifer.   When  physical
obstacles preclude installation of ground-
water monitoring  wells at the  relevant
point of compliance at existing units, the
down-gradient monitoring system may be
installed  at  the   closest  practicable
distance  hydraulically down-gradient
from the relevant point of compliance or
specified by the Director of an approved
State   under   §258.40  that  ensures
detection of ground-water contamination
in the uppermost aquifer.

 (b) The Director  of an approved State
may approve a multi-unit ground-water
monitoring  system instead  of  separate
ground-water monitoring systems  for
each MSWLF unit when the facility has
several  units, provided the multi-unit
ground-water monitoring system meets
the requirement of §258.51(a) and will be
as protective of human health and the
environment  as  individual monitoring
systems for each MSWLF unit, based on
the following factors:

 (1) Number, spacing, and orientation of
the MSWLF units;
                                       219

-------
                                      Subpart E
 (2) Hydrogeologic setting;

 (3) Site history;

 (4) Engineering design of the MSWLF
units; and

 (5) Type  of waste  accepted  at the
MSWLF units.

 (c) (See  Section  5.7  for  technical
guidance on monitoring well design and
construction.)

 (d) The number, spacing, and depths of
monitoring systems shall be:

 (1) Determined based upon site-specific
technical information  that must include
thorough characterization of:

 (i) Aquifer  thickness,  ground-water
flow rate, ground-water flow direction
including   seasonal    and   temporal
fluctuations in ground-water flow; and

 (ii)     Saturated  and   unsaturated
geologic units and fill materials overlying
the   uppermost   aquifer,    materials
comprising the uppermost aquifer, and
materials comprising the confining unit
defining  the lower  boundary  of the
uppermost  aquifer; including, but not
limited  to:  thicknesses,  stratigraphy,
lithology,   hydraulic    conductivities,
porosities and effective porosities.

 (2) Certified by a  qualified  ground-
water   scientist  or approved  by the
Director of an approved State. Within 14
days of this certification, the owner  or
operator  must notify the State Director
that the certification has been placed in
the operating record.
5.6.2  Applicability

The requirements for establishing a ground-
water  monitoring  system  pursuant  to
§258.51 apply to all new units, existing
units, and lateral expansions of existing
units according to the schedules identified
in 40  CFR  §258.50.   A ground-water
monitoring   system   consists  of  both
background wells and wells located at the
point of compliance or waste management
unit  boundary (i.e., downgradient wells).
The ground-water monitoring network must
be capable of detecting a release from the
MSWLF unit.   A  sufficient number of
monitoring   wells   must   be   located
downgradient of the unit and be screened at
intervals in the uppermost aquifer to ensure
contaminant   detection.      Generally,
upgradient wells  are  used to  determine
background ground-water quality.

The downgradient wells must be located at
the relevant point of compliance specified
by the Director of an approved State, or at
the waste management  unit boundary in
States  that are not in  compliance with
regulations. If existing physical structures
obstruct well  placement, the downgradient
monitoring system should be placed as close
to the relevant  point  of  compliance as
possible. Wells located at the relevant point
of compliance must be capable of detecting
contaminant releases from the MSWLF unit
to the  uppermost aquifer.   As  discussed
earlier in the section  pertaining to the
designation   of   a  relevant   point  of
compliance  (Section 4.4), the point of
compliance must be no greater than 150
meters from the unit boundary.

The  Director of an approved State may
allow the use of a multi-unit ground-water
monitoring system. MSWLF units in
                                        220

-------
                     Ground-Water Monitoring and Corrective Action
States that are deemed not in compliance
with the regulations must have a monitoring
system for each unit.

A qualified ground-water scientist  must
certify that the number, spacing, and depths
of the monitoring wells are appropriate for
the MSWLF unit. This certification must be
placed in the operating records.  The State
Director must be notified within 14 days
that  the  certification was placed in  the
operating record.

5.6.3 Technical Considerations

The obj ective of a ground-water monitoring
system is to intercept ground water that has
been contaminated by leachate from  the
MSWLF unit. Early contaminant detection
is important to  allow sufficient time  for
corrective measures to be developed and
implemented before sensitive receptors are
significantly affected.  To accomplish this
objective, the monitoring wells should be
located  to sample ground water from  the
uppermost aquifer at the closest practicable
distance from the waste  management unit
boundary.  An  alternative distance that is
protective  of   human   health  and   the
environment may be granted  by the Director
of an approved State. Since the monitoring
program is intended to operate through the
post-closure period, the  location,  design,
and installation of monitoring wells should
address   both   existing   conditions  and
anticipated facility development, as well as
expected changes in ground-water flow.

Uppermost Aquifer

Monitoring wells must be placed to provide
representative ground-water  samples from
the  uppermost  aquifer.   The  uppermost
aquifer is defined in §258.2 as "the geologic
formation nearest to the natural  ground
surface that is an aquifer, as well as lower
aquifers     that     are     hydraulically
interconnected with this aquifer within the
facility property boundary."  These lower
aquifers may be separated physically from
the uppermost  aquifer by less  permeable
strata   (having   a   lower   hydraulic
conductivity)   that   are   often   termed
aquitards. An aquitard is a less permeable
geologic unit or series of closely  layered
units (e.g., silt, clay, or shale) that in itself
will not yield significant quantities of water
but  will   transmit   water  through  its
thickness.  Aquitards may include  thicker
stratigraphic sequences of clays, shales, and
dense, unfractured crystalline rocks  (Freeze
and Cherry, 1979).

To be considered part  of the  uppermost
aquifer, a lower zone of saturation must be
hydraulically connected to the  uppermost
aquifer  within  the  facility  property
boundary.    Generally,   the  degree  of
communication   between  aquifers  is
evaluated by  ground-water pumping tests.
Methods have  been  devised  for  use in
analyzing aquifer test data. A summary is
presented in Handbook:  Ground  Water,
Vol. II (USEPA, 1991).   The following
discussions under this section (5.6.3) should
assist   the    owner   or   operator  in
characterizing the uppermost aquifer and
the hydrogeology of the site.

Determination of Background Ground-
Water Quality

The goal of monitoring-well placement is to
detect changes in the quality  of  ground
water  resulting from a release from the
MSWLF  unit.   The  natural  chemical
composition of ground water is controlled
                                         221

-------
                                      Subpart E
primarily by the mineral composition of the
geologic unit comprising the aquifer. As
ground water moves from one geologic unit
to another, its chemical composition may
change.   To  reduce  the  probability  of
detecting naturally occurring differences in
ground-water quality between background
and downgradient locations, only ground-
water samples  collected  from the  same
geologic unit should be compared.

Ground-water  quality in areas  where the
geology is  complex  can be difficult to
characterize. As a result, the rule allows the
owner or operator flexibility in determining
where to locate wells that will  be used to
establish background water quality.

If the facility is new, ground-water samples
collected   from   both   upgradient  and
downgradient  locations  prior  to  waste
disposal can be used to establish background
water quality.   The sampling  should  be
conducted to account for both seasonal and
spatial variability in ground-water quality.

Determining   background   ground-water
quality  by  sampling wells that  are not
hydraulically upgradient may be necessary
where hydrogeologic  conditions do not
allow the owner or operator to determine
which wells are hydraulically upgradient.
Additionally,  background  ground-water
quality  may be  determined by sampling
wells that provide ground-water samples as
representative or more representative than
those provided by upgradient wells.  These
conditions include the following:

•  The facility is located above an aquifer
   in which ground-water flow directions
   change seasonally.
•  The facility is located near production
   wells  that  influence  the direction of
   ground-water flow.

•  Upgradient  ground-water  quality is
   affected by a  source of contamination
   other than the MSWLF unit.

•  The   proposed   or  existing  landfill
   overlies a ground-water divide or local
   source of recharge.

•  Geologic units present at downgradient
   locations  are  absent  at  upgradient
   locations.

•  Karst terrain or fault zones modify flow.

•  Nearby surface water influences ground-
   water flow directions.

•  Waste management areas are located
   close  to a property boundary  that is
   upgradient of the facility.

Multi-Unit Monitoring Systems

A  multi-unit  ground-water  monitoring
system does not have wells at individual
MSWLF unit boundaries.   Instead,  an
imaginary line is drawn around all  of the
units at the facility. (See Figure 5-1 for a
comparison of single unit  and multi-unit
systems.) This line constitutes the relevant
point of  compliance.    The  option  to
establish a multi-unit monitoring system is
restricted to facilities  located in approved
States.   A multi-unit  system  must  be
approved by the Director of an approved
State after consideration has been given to
the:

•  Number, spacing, and orientation of the
   MSWLF units
                                         222

-------
Figure 5-1. Comparison of Single Unit and Multi-Unit Monitoring System
                              Single-Unit System
    Ground-Water
    Flow
                               Multi-Unit System
  V  G
  V
Ground-Water
Flow
                                   223

-------
                                      Subpart E
•  Hydrogeologic setting

•  Site history

•  Engineering design of the MSWLF units

•  Type of wastes accepted at the facility.

The purpose of a multi-unit  system is to
reduce the number of monitoring wells that
can provide the same information.    The
conceptual design of the multi-unit system
should consider the use and management of
the facility with respect to anticipated unit
locations.  In some cases, it may be possible
to justify a reduction in the number of wells
if the waste management units are aligned
along the same flow path in the ground-
water system.

The multi-unit  monitoring  system  must
provide a level of  protection  to human
health  and  the  environment  that   is
comparable to monitoring individual units.
The  multi-unit  system  should  allow
adequate   time   after    detection   of
contamination to develop and  implement
corrective   measures   before   sensitive
receptors are adversely affected.

Hydrogeological Characterization

Adequate    monitoring-well    placement
depends   on collecting  and  evaluating
hydrogeological information  that can be
used to form a conceptual model of the site.
The goal of a hydrogeological investigation
is to acquire site-specific  data concerning:

•  The  lateral  and  vertical extent of the
   uppermost aquifer

•  The  lateral  and  vertical extent of the
   upper and lower confining units/layers
•  The  geology at  the  owner's/operator's
   facility (e.g, stratigraphy, lithology, and
   structural setting)

•  The   chemical   properties   of  the
   uppermost  aquifer  and  its confining
   layers  relative  to local  ground-water
   chemistry and wastes managed  at the
   facility

• Ground-water flow, including:

   -  The vertical and horizontal directions
     of ground-water flow in the uppermost
     aquifer

   -  The    vertical    and    horizontal
     components of the  hydraulic gradient
     in the uppermost and any hydraulically
     connected aquifer

   -  The hydraulic conductivities of the
     materials that comprise the upper-most
     aquifer and its confining units/layers

   -  The average linear horizontal velocity
     of ground-water flow in the uppermost
     aquifer.

The  elements of a program to characterize
the hydrogeology of a  site are discussed
briefly in  the sections that follow and are
addressed in more detail in "RCRA Ground-
Water  Monitoring:    Draft  Technical
Guidance" (USEPA, 1992a).

Prior to initiating a field investigation, the
owner  or  operator  should  perform  a
preliminary investigation. The preliminary
investigation will  involve reviewing  all
available information about the site, which
may  consist of:
                                         224

-------
                     Ground-Water Monitoring and Corrective Action
   Information on the waste management
   history of the site, including:

   -  A chronological history  of the site,
     including   descriptions  of  wastes
     managed on-site

   -  A summary of documented releases

   -  Details on the structural  integrity of
     the MSWLF unit and physical  controls
     on waste migration

   A literature review, including:

   -  Reports of research performed in the
     area of the site

   -  Journal articles

   -  Studies and  reports available  from
     local, regional, and State offices (e.g.,
     geologic  surveys, water boards, and
     environmental agencies)

   -  Studies available from Federal  offices,
     such as USGS or USEPA
   Information
   including:
from    file    searches,
   -  Reports  of previous investigations at
     the site

   -  Geological    and    environmental
     assessment data from State and Federal
     reports.

The documentation itemized above is by no
means a complete  listing  of  information
available for a preliminary investigation.
Many  other  sources  of  hydrogeological
information may  be available  for review
during the preliminary investigation.
Characterizing Site Geology

After  the  preliminary  investigation  is
complete, the  owner/operator will  have
information that he/she can use to develop a
plan  to  characterize  site  hydrogeology
further.

Nearly all hydrogeological  investigations
include a subsurface boring program.  A
boring program is necessary to define  site
hydrogeology and the small-scale geology
of the area beneath the site. The program
usually requires more  than one iteration.
The objective of the initial boreholes is to
refine the conceptual  model  of the site
derived from the preliminary investigation.

The subsurface boring program  should be
designed as follows:

•  The initial number of boreholes and their
   spacing  is based on  the  information
   obtained   during   the    preliminary
   investigation.

•  Additional boreholes should be installed
   as needed to provide more  information
   about the site.

•  Samples  should  be  collected from the
   borings at changes in lithology.   For
   boreholes that will  be  completed  as
   monitoring wells, at least  one sample
   should be collected from the interval that
   will be the screened interval. Boreholes
   that will not be completed as monitoring
   wells must be properly decommissioned.

Geophysical techniques, cone penetrometer
surveys, mapping programs, and laboratory
analyses of borehole samples can be used to
plan and supplement the subsurface boring
program. Downhole geophysical techniques
                                         225

-------
                                      Subpart E
include electric, sonic, and nuclear logging.
Surface  geophysical  techniques include
seismic reflection and refraction, as well as
electromagnetic induction and resistivity.

The data obtained from the  subsurface
boring program should enable the owner or
operator to identify:

•  Lithology, soil types, and stratigraphy

•  Zones  of potentially  high  hydraulic
   conductivity

•  The presence of confining formations or
   layers

•  Unpredicted geologic features, such as
   fault zones, cross-cutting structures, and
   pinch-out zones

•  Continuity of petrographic features, such
   as sorting, grain size distribution, and
   cementation

•  The  potentiometric  surface  or  water
   table.
Characterizing
Beneath the Site
Ground-Water   Flow
In addition to characterizing site geology,
the owner/operator should characterize the
hydrology of the uppermost aquifer and its
confining layer(s) at the site. The owner or
operator  should  install  wells  and/or
piezometers to assist in characterizing site
hydrology.   The  owner/operator  should
determine and assess:

 •   The direct!on(s) and rate(s) of ground-
     water flow (including both horizontal
     and vertical components of flow)
 •   Seasonal/temporal,   natural,   and
     artificially  induced  (e.g.,   off-site
     production well-pumping, agricultural
     use)    short-term   and   long-term
     variations in ground-water elevations
     and flow patterns

 •   The hydraulic conductivities of the
     stratigraphic units at the site, including
     vertical hydraulic conductivity of the
     confining layer(s).

Determining   Ground-Water     Flow
Direction and Hydraulic Gradient

Installing monitoring wells that will provide
representative     background      and
downgradient water  samples requires  a
thorough understanding of how  ground
water flows beneath a site. Developing such
an   understanding   requires  obtaining
information regarding both ground-water
flow direction(s) and  hydraulic gradient.
Ground-water flow direction can be thought
of as the idealized path that ground-water
follows as it passes through the subsurface.
Hydraulic gradient (i) is the change in static
head  per  unit  of distance  in  a  given
direction.  The static head is defined as the
height above a standard datum of the surface
of a column of water (or other liquid) that
can be supported by the static pressure at a
given point (i.e., the sum of the elevation
head and pressure head).

To determine ground-water flow directions
and   hydraulic   gradient,   owners   and
operators should develop and implement a
water  level-monitoring  program.   This
program should be structured to provide
precise water level  measurements  in  a
sufficient number of piezometers or wells at
a  sufficient frequency to  gauge  both
seasonal  average  flow  directions  and
                                         226

-------
                     Ground-Water Monitoring and Corrective Action
temporal fluctuations in ground-water flow
directions.  Ground-water flow direction(s)
should be  determined from  water levels
measured in wells screened  in the  same
hydro-stratigraphic    position.       In
heterogeneous   geologic   settings  (i.e.,
settings    in    which   the    hydraulic
conductivities of the subsurface materials
vary with location in the subsurface), long
well  screens  can intercept  stratigraphic
horizons with different (e.g., contrasting)
ground-water flow directions  and different
heads. In this situation, the resulting  water
levels will not provide the depth-discrete
head  measurements required for accurate
determination of  the  ground-water flow
direction.

In addition to evaluating the component of
ground-water   flow  in   the  horizontal
direction, a program should be  undertaken
to assess the vertical component of ground-
water flow.  Vertical  ground-water flow
information should be based, at  least in part,
on field  data from wells and  piezometers,
such  as  multi-level  wells,   piezometer
clusters,  or multi-level sampling devices,
where appropriate. The following sections
provide acceptable methods for assessing
the vertical and horizontal  components of
flow at a site.

Ground-Water Level Measurements

To determine ground-water flow directions
and ground-water flow rates, accurate water
level measurements (measured to the  nearest
0.01 foot) should be obtained.  Section 5.8
delineates procedures for obtaining  water
level measurements.  At facilities where it is
known   or  plausible  that    immiscible
contaminants  (i.e.,  non-aqueous  phase
liquids (NAPLs)) occur (or are  determined
to be potentially present after considering
the waste types managed at the facility) in
the subsurface  at  the  facility,  both the
depth(s) to the immiscible layer(s) and the
thickness(es) of the immiscible layer(s) in
the well should be recorded.

For the purpose of measuring  total head,
piezometers and wells should have as short
a   screened    interval   as   possible.
Specifically, the screens in piezometers or
wells that are used to measure head should
generally be less  than 10 feet long.   In
circumstances including the following, well
screens  longer  than   10  feet  may  be
warranted:

 •  Natural  water   level  fluctuations
    necessitate a longer screen length.

 •  The interval  monitored  is  slightly
    greater than  the  appropriate  screen
    length (e.g., the interval monitored is
     12 feet thick).

 •  The aquifer monitored is homogeneous
    and extremely thick (e.g., greater than
    300 feet); thus, a longer screen (e.g., a
    20-foot screen)  represents  a  fairly
    discrete interval.

The head measured in a well with a long
screened interval is a function of all of the
different heads over the entire length of the
screened  interval.   Care should be  taken
when interpreting water  levels  collected
from wells  that have long screened intervals
(e.g., greater than 10 feet).

The water-level monitoring program should
be structured to provide precise water level
measurements in a sufficient  number  of
piezometers  or  wells  at  a   sufficient
frequency to gauge both seasonal  average
flow directions and temporal fluctuations in
                                         227

-------
                                      Subpart E
ground-water   flow   directions.    The
owner/operator should determine and assess
seasonal/temporal, natural,  and artificially
induced  (e.g.,  off-site  production well-
pumping, agricultural use)  short-term and
long-term  variations   in   ground-water
elevations, ground-water flow patterns, and
ground-water quality.

Establishing Horizontal Flow Direction
and  the  Horizontal   Component  of
Hydraulic Gradient

After the water level data and measurement
procedures are reviewed to determine that
they are  accurate, the data  should be used
to:

 •   Construct potentiometric surface maps
     and  water table maps based on the
     distribution of total head.  The  data
     used to  develop  water  table maps
     should be from  piezometers or wells
     screened  across the water table.  The
     data used to  develop  potentiometric
     surface   maps   should   be   from
     piezometers  or  wells  screened at
     approximately the  same elevation in
     the same hydrostratigraphic unit;

 •   Determine the horizontal  direction(s)
     of ground-water flow by drawing  flow
     lines on the potentiometric surface map
     or water  table map (i.e.,  construct a
     flow net);

 •   Calculate value(s)  for the horizontal
     and  vertical components of hydraulic
     gradient.

Methods   for constructing  potentiometric
surface and water table maps, constructing
flow nets, and determining the direction(s)
of  ground-water  flow  are provided by
USEPA  (1989c)  and Freeze and Cherry
(1979).  Methods for calculating hydraulic
gradient  are provided by Heath (1982) and
USEPA (1989c).

A potentiometric surface or water table map
will give an approximate idea of general
ground-water flow directions.  However, to
locate  monitoring wells properly, ground-
water  flow  direction(s)  and  hydraulic
gradient(s) should  be established in both the
horizontal and vertical directions and over
time at regular intervals (e.g., over a 1-year
period at 3-month intervals).

Establishing Vertical Flow Direction and
the  Vertical  Component of Hydraulic
Gradient

To  make an adequate determination of the
ground-water flow directions, the vertical
component of ground-water flow should be
evaluated directly. This generally requires
the installation of multiple piezometers or
wells in clusters or nests, or the installation
of multi-level wells or sampling devices. A
piezometer or well nest is  a closely spaced
group of piezometers or wells screened at
different depths, whereas a multi-level well
is a single device.  Both  piezometer/well
nests and multi-level wells allow for the
measurement  of vertical variations  in
hydraulic head.

When  reviewing  data   obtained  from
multiple placement of piezometers or wells
in single boreholes, the construction details
of the  well should be carefully evaluated.
Not only is it extremely  difficult to seal
several piezometers/wells at discrete depths
within a  single  borehole,  but  sealant
materials may migrate from the seal of one
piezometer/well to the screened interval of
another piezometer/well.  Therefore, the
                                         228

-------
                     Ground-Water Monitoring and Corrective Action
design of a piezometer/well nest should be
considered  carefully.     Placement  of
piezometers/wells   in   closely   spaced
boreholes,  where piezometers/wells have
been screened at different, discrete depth
intervals, is likely to produce more accurate
information. The primary concerns with the
installation of piezometers/wells in closely
spaced, separate boreholes are:   1)  the
disturbance of geologic and soil materials
that occurs when one piezometer is installed
may be reflected in the data obtained from
another piezometer located nearby, and 2)
the analysis of water levels  measured in
piezometers that are  closely  spaced,  but
separated   horizontally,   may   produce
imprecise information regarding the vertical
component of  ground-water  flow.   The
limitations    of   installing    multiple
piezometers either  in single  or separate
boreholes  may  be  overcome  by   the
installation of single multi-level monitoring
wells  or  sampling  devices  in  single
boreholes.       The    advantages   and
disadvantages of these types of devices are
discussed by USEPA (1989f).

The owner or operator should determine the
vertical direction(s) of ground-water flow
using the water  levels measured in multi-
level  wells or  piezometer/well  nests to
construct flow nets. Flow nets should depict
the piezometer/well depth and length of the
screened interval. It is important to portray
the screened interval accurately on the flow
net to  ensure  that  the piezometer/well is
actually    monitoring     the    desired
water-bearing unit.  A flow net  should be
developed from information obtained from
piezometer/ well clusters or nests screened
at different,  discrete  depths.    Detailed
guidance for the construction and evaluation
of flow nets in cross section (vertical flow
nets)  is provided  by  USEPA  (1989c).
Further information can be obtained from
Freeze and Cherry (1979).

Determining Hydraulic Conductivity

Hydraulic conductivity is a measure of a
material's   ability  to  transmit  water.
Generally, poorly  sorted silty or  clayey
materials have low hydraulic conductivities,
whereas well-sorted sands and gravels have
high hydraulic conductivities.  An  aquifer
may be classified as either homogeneous or
heterogeneous  and either  isotropic  or
anisotropic  according  to  the  way  its
hydraulic conductivity varies in space.  An
aquifer is  homogeneous if the hydraulic
conductivity  is  independent  of  location
within the aquifer; it is  heterogeneous if
hydraulic conductivities are dependent on
location within the aquifer. If the hydraulic
conductivity is independent of the  direction
of measurement at  a point in  a geologic
formation, the formation is isotropic at that
point.  If the hydraulic conductivity varies
with the  direction of measurement at a
point, the formation is anisotropic  at that
point.

Determining   Hydraulic   Conductivity
Using Field Methods

Sufficient  aquifer  testing  (i.e.,  field
methods) should be performed  to provide
representative   estimates  of   hydraulic
conductivity.   Acceptable field  methods
include conducting aquifer tests with single
wells, conducting aquifer tests with multiple
wells, and using flowmeters.   This section
provides brief overviews of these methods,
including  two  methods  for obtaining
vertically   discrete   measurements   of
hydraulic  conductivity.   The  identified
references provide detailed descriptions of
the methods summarized in this section.
                                         229

-------
                                       Subpart E
A commonly used  test for  determining
horizontal  hydraulic  conductivity with  a
single well is the slug test.  A slug test is
performed by suddenly adding, removing,
or displacing a known volume of water from
a well and observing the time that it takes
for the water level to recover to its original
level (Freeze and Cherry, 1979).  Similar
results can be achieved by pressurizing the
well casing, depressing the water level, and
suddenly releasing the pressure to simulate
the removal of water from the well.  In most
cases, EPA recommends that water not be
introduced into wells during aquifer tests to
avoid  altering  ground-water  chemistry.
Single-well tests are limited  in scope to the
area directly adjacent to the well screen.
The vertical extent  of the  well  screen
generally defines the  part of the geologic
formation that is being tested.

A modified version of the slug test, known
as the multilevel slug test,  is capable of
providing depth-discrete measurements of
hydraulic conductivity.  The drawback of
the multilevel slug test is that the test relies
on the ability of the investigator to isolate a
portion of  the  aquifer using a  packer.
Nevertheless, multilevel slug tests,  when
performed  properly,  can produce reliable
measurements of hydraulic conductivity.

Multiple-well tests involve withdrawing
water from,  or  injecting water into, one
well,    and   obtaining    water   level
measurements over  time in  observation
wells.    Multiple-well  tests  are  often
performed as pumping tests in which water
is pumped from  one well and drawdown is
observed in nearby wells. A step-drawdown
test should precede most pumping tests to
determine  an appropriate discharge  rate.
Aquifer tests conducted with wells screened
in the same water-bearing zone can be used
to provide hydraulic conductivity data for
that zone.  Multiple-well tests for hydraulic
conductivity    characterize   a   greater
proportion of the  subsurface than single-
well tests and, thus, provide average values
of hydraulic  conductivity.  Multiple-well
tests require  measurement of  parameters
similar  to those required  for  single-well
tests (e.g., time, drawdown).  When  using
aquifer  test  data  to determine  aquifer
parameters, it is important that the solution
assumptions  can  be   applied  to  site
conditions.   Aquifer  test  solutions  are
available   for   a   wide   variety   of
hydrogeologic settings, but are often applied
incorrectly by  inexperienced   persons.
Incorrect      assumptions      regarding
hydrogeology  (e.g., aquifer  boundaries,
aquifer  lithology,  and  aquifer thickness)
may translate into  incorrect estimations of
hydraulic  conductivity.  A qualified ground-
water scientist with experience in designing
and interpreting aquifer  tests  should  be
consulted to ensure  that aquifer test solution
methods  fit  the  hydrogeologic  setting.
Kruseman and deRidder (1989)  provide a
comprehensive discussion of aquifer tests.

Multiple-well tests conducted  with  wells
screened in different water-bearing  zones
furnish  information  concerning hydraulic
communication among  the zones.  Water
levels in these zones should be monitored
during the aquifer test to determine the type
of   aquifer   system   (e.g.,   confined,
unconfmed,    semi-confined,   or   semi-
unconfmed)  beneath the  site,  and  their
leakance  (coefficient   of leakage)  and
drainage factors (Kruseman and deRidder,
1989).  A multiple-well aquifer test should
be considered at every site as a method to
establish  the  vertical   extent  of  the
uppermost aquifer  and to evaluate hydraulic
connection between aquifers.
                                         230

-------
                     Ground-Water Monitoring and Corrective Action
Certain aquifer tests are inappropriate for
use in  karst terrains characterized  by a
well-developed conduit flow system, and
they also may be inappropriate in fractured
bedrock.  When a well located in a karst
conduit or a large fracture is pumped, the
water level in the conduit is lowered.  This
lowering produces a drawdown that is not
radial  (as  in  a granular aquifer) but is
instead a trough-like depression parallel to
the pumped conduit or fracture. Radial flow
equations do not apply  to drawdown data
collected  during  such a pump test.   This
means that a conventional semi-log plot of
drawdown versus time is inappropriate for
the purpose of determining  the  aquifer's
transmissivity and storativity. Aquifer tests
in karst aquifers can be useful, but valid
determinations  of hydraulic  conductivity,
storativity,  and  transmissivity   may be
impossible.  However, an aquifer test can
provide information on the presence  of
conduits, on storage characteristics, and on
the percentage of Darcian flow.   McGlew
and Thomas (1984) provide a more detailed
discussion of the appropriate use of aquifer
tests  in fractured  bedrock  and  on  the
suitable interpretation of test data.   Dye
tracing also is used to determine the rate and
direction  of  ground-water flow  in  karst
settings (Section 5.2.4).

Several  additional  factors  should  be
considered when planning an aquifer test:

 •  Owners and  operators should provide
    for the proper storage and disposal of
    potentially contaminated ground water
    pumped from the well system.

 •  Owners and operators should consider
    the potential effects of pumping on
    existing  plumes   of  contaminated
    ground water.
 •   In   designing  aquifer  tests   and
     interpreting    aquifer   test   data,
     owners/operators should account and
     correct for seasonal, temporal, and
     anthropogenic   effects    on   the
     potentiometric surface or water  table.
     This is usually done  by  installing
     piezometers outside the influence of
     the   stressed   aquifer.      These
     piezometers  should be  continuously
     monitored during the aquifer test.

 •   Owners and operators should be aware
     that,  in   a   very   high   hydraulic
     conductivity  aquifer, the screen size
     and/or filter pack used in the test well
     can  affect an  aquifer test.   If a very
     small screen size is used, and the pack
     is improperly graded,  the  test may
     reflect the characteristics of the filter
     pack, rather than the aquifer.

 •   EPA recommends  the use of a step-
     drawdown test to provide a basis for
     selecting  discharge rates  prior to
     conducting a full-scale pumping test.
     This will ensure that the pumping rate
     chosen for the subsequent pumping
     test(s)  can  be  sustained  without
     exceeding the available drawdown of
     the pumped wells. In addition, this test
     will produce a measurable drawdown
     in the observation wells.

Certain  flowmeters recently have  been
recognized  for their ability  to provide
accurate     and    vertically    discrete
measurements of  hydraulic conductivity.
One of these, the  impeller  flowmeter,  is
available commercially.  More  sensitive
types of flowmeters  (i.e., the  heat-pulse
flowmeter and electromagnetic flowmeter)
should be available in the near future. Use
of the impeller flowmeter requires running
                                         231

-------
                                      Subpart E
a caliper log to measure the uniformity of
the diameter of the well screen.  The well is
then pumped with a small pump operated at
a constant flow rate.  The flowmeter is
lowered into the well, and the discharge rate
is measured every few feet by  raising the
flowmeter  in  the  well.     Hydraulic
conductivity values can be calculated from
the recorded data using the  Cooper-Jacob
(1946) formula  for horizontal  flow  to a
well.   Use  of the  impeller flowmeter is
limited at sites where the presence of low
permeability   materials  does  not  allow
pumping of the wells at rates sufficient to
operate the flowmeter.  The  application of
flowmeters  in the  measure  of hydraulic
conductivity is described by Molz et al.
(1990) and Molz et al. (1989).

Determining  Hydraulic   Conductivity
Using Laboratory Methods

It  may be  beneficial  to use  laboratory
measurements of hydraulic conductivity to
augment the results of field tests. However,
field methods provide the best estimates of
hydraulic  conductivity   in   most  cases.
Because   of  the   limited   sample   size,
laboratory tests  can fail  to account for
secondary   porosity  features,   such as
fractures and joints, and hence,  can greatly
underestimate  overall  aquifer  hydraulic
conductivities.    Laboratory   tests   may
provide valuable  information  about the
vertical    component   of    hydraulic
conductivity of aquifer materials. However,
laboratory test results always  should be
confirmed by  field measurements,  which
sample a much larger portion of the aquifer.
In addition, laboratory test results can be
profoundly  affected by  the test method
selected and by  the manner in which the
tests are  carried out (e.g.,  the extent to
which  sample collection and preparation
have changed the in situ
hydraulic properties of the tested material).
Special  attention should be given to the
selection of the appropriate test method and
test  conditions and to quality  control of
laboratory results.  McWhorter and Sunada
(1977),  Freeze  and Cherry  (1979),  and
Sevee (1991) discuss determining hydraulic
conductivity in the laboratory. Laboratory
tests may  provide the  best  estimates of
hydraulic conductivity for materials in the
unsaturated zone, but they are likely to be
less  accurate  than  field  methods  for
materials in the saturated zone (Cantor et
al., 1987).

Determining Ground-Water Flow Rate

The calculation of the average ground-water
flow rate (average linear velocity of ground-
water  flow),   or   seepage   velocity, is
discussed in detail in USEPA (1989c), in
Freeze and  Cherry  (1979), and in Kruseman
and deRidder  (1989).  The average linear
velocity  of ground-water flow (v)  is   a
function  of hydraulic  conductivity (K),
hydraulic gradient (i), and effective porosity
(ne):

      v = - Ki
Methods for determining hydraulic gradient
and  hydraulic  conductivity  have  been
presented previously.  Effective porosity,
the percentage of the total volume of a given
mass of soil, unconsolidated material,  or
rock that consists of interconnected pores
through which water can  flow, should be
estimated  from laboratory tests or  from
values cited in the literature.  (Fetter (1980)
provides a  good discussion of effective
porosity. Barari and Hedges (1985) provide
default  values  for  effective  porosity.)
USEPA (1989c) provides methods for
                                         232

-------
                     Ground-Water Monitoring and Corrective Action
determining  flow rates  in  heterogeneous
and/or anisotropic systems  and should be
consulted prior to calculating flow rates.

Interpreting and Presenting Data

The following sections offer guidance on
interpreting and presenting  hydrogeologic
data    collected    during    the    site
characterization   process.      Graphical
representations  of  data,  such  as  cross
sections and maps, are typically extremely
helpful both when evaluating data and when
presenting data to interested individuals.

Interpreting Hydrogeologic Data

Once the site characterization data  have
been collected, the following tasks should
be undertaken to support and develop the
interpretation of these data:

 •   Review  borehole  and  well logs to
     identify  major  rock, unconsolidated
     material, and soil types and establish
     their horizontal  and vertical extent and
     distribution.

 •   From borehole  and  well  log  (and
     outcrop,   where   available)   data,
     construct representative cross-sections
     for  each MSWLF  unit,  one in the
     direction of ground-water flow and one
     orthogonal to ground-water flow.

 •   Identify  zones  of  suspected  high
     hydraulic conductivity, or structures
     likely   to  influence  contaminant
     migration through the unsaturated and
     saturated zones.

 •   Compare findings  with other studies
     and information collected during the
     preliminary investigation to verify the
     collected information.

 •   Determine  whether laboratory  and
     field   data   corroborate  and  are
     sufficient to define petrology, effective
     porosity,   hydraulic   conductivity,
     lateral   and   vertical    stratigraphic
     relationships, and ground-water flow
     directions and rates.

After the hydrogeologic data are interpreted,
the findings should be reviewed to:

 •   Identify information gaps

 •   Determine whether the collection of
     additional data or  reassessment  of
     existing data is required to fill in the
     gaps

 •   Identify  how information gaps are
     likely to affect the ability to design a
     RCRA monitoring system.

Generally, lithologic  data should correlate
with hydraulic properties (e.g., clean, well-
sorted, unconsolidated sands  should exhibit
high hydraulic conductivity).  Additional
boreholes should be drilled  and additional
samples should be collected to describe the
hydrogeology of the site if the investigator
is unable to 1) correlate stratigraphic units
between borings,  2)  identify  zones  of
potentially high hydraulic conductivity and
the thickness and lateral extent of these
zones,   or    3)   identify   confining
formations/layers  and the  thickness  and
lateral extent of these formation layers.

When  establishing the  locations of wells
that will be used to monitor ground water in
hydrogeologic  settings  characterized by
ground-water flow  in porous media, the
following should be  documented:
                                          233

-------
                                      Subpart E
 •   The ground-water flow rate should be
     based on accurate measurements of
     hydraulic conductivity and hydraulic
     gradient and accurate measurements or
     estimates of effective porosity

 •   The    horizontal    and    vertical
     components  of  flow   should  be
     accurately depicted  in flow nets and
     based on valid data

 •   Any seasonal or temporal variations in
     the  water  table  or  potentiometric
     surface,  and   in   vertical   flow
     components, should be determined.

Once an understanding of horizontal and
vertical  ground-water   flow  has   been
established, it is possible to estimate where
monitoring wells will most likely intercept
contaminant flow.

Presenting Hydrogeologic Data

Subsequent   to   the   generation   and
interpretation of site-specific geologic data,
the data should  be presented in geologic
cross-sections, topographic maps, geologic
maps, and soil maps.  The Agency suggests
that owners/operators obtain or prepare and
review topographic, geologic, and soil maps
of the facility, in addition to site maps of the
facility and MSWLF  units.  In cases where
suitable maps are not available, or where the
information contained on available maps is
not complete or accurate,  detailed mapping
of the site should be performed by qualified
and  experienced individuals.   An  aerial
photograph and  a topographic map  of the
site  should  be  included as  part of the
presentation of hydrogeologic data.  The
topographic  map  should be  constructed
under  the  supervision  of  a  qualified
surveyor and should  provide contours at a
maximum of 2-foot intervals.
Geologic and soil maps should be based on
rock,  unconsolidated material,  and  soil
identifications gathered from borings and
outcrops.  The maps should use colors or
symbols    to   represent    each   soil,
unconsolidated material, and rock type that
outcrops on the surface.  The  maps also
should show the locations of outcrops and
all   borings  placed  during   the   site
characterization.  Geologic and soil maps
are important because they  can provide
information describing how site geology fits
into the local and regional geologic setting.

Structure contour maps and isopach maps
should be prepared for each water-bearing
zone that comprises the uppermost aquifer
and for each significant confining  layer,
especially the one underlying the uppermost
aquifer.  A  structure contour map depicts
the configuration (i.e., elevations) of the
upper or lower surface or boundary of a
particular geologic or soil formation, unit,
or zone.    Structure contour  maps are
especially important in understanding dense
non-aqueous   phase   liquid   (DNAPL)
movement    because   DNAPLs   (e.g.,
tetrachloroethylene)  may  migrate in the
direction of the dip of lower permeability
units.   Separate  structure  contour maps
should be constructed for the upper and
lower surfaces (or contacts) of each zone of
interest.    Isopach  maps  should  depict
contours that indicate the thickness of each
zone.   These maps are generated  from
borings  and geologic  logs  and  from
geophysical measurements. In conjunction
with cross-sections, isopach maps may be
used to help determine  monitoring well
locations, depths, and screen lengths during
the design  of the  detection monitoring
system.
                                         234

-------
                     Ground-Water Monitoring and Corrective Action
A potent!ometric surface map or water table
map should be prepared for each water-
bearing zone that comprises the uppermost
aquifer. Potentiometric surface and water
table maps should show both the direction
and  rate  of ground-water flow  and the
locations  of all piezometers and wells on
which  they are based.   The water  level
measurements for all piezometers and wells
on which the potentiometric surface map or
water table map is based should be shown
on the potentiometric surface or water table
map.  If seasonal or temporal variations in
ground-water  flow occur  at  the  site,  a
sufficient number of potentiometric surface
or water table maps should be prepared to
show  these  variations.    Potentiometric
surface and water  table  maps  can  be
combined  with structure contour maps for a
particular  formation or unit.  An adequate
number of cross sections should be prepared
to  depict  significant  stratigraphic  and
structural trends and to reflect stratigraphic
and structural features in relation to local
and regional ground-water flow.

Hydrogeological Report

The hydrogeological report should contain,
at a minimum:

•  A description of field activities

•  Drilling and/or well construction logs

•  Analytical data

•  A discussion and interpretation of the
   data

•  Recommendations to address data gaps.

The final output of the site characterization
phase of the hydrogeological investigation
is
a conceptual model.   This  model is the
integrated  picture of  the  hydrogeologic
system and the waste management setting.
The final conceptual model must be a site-
specific description of the unsaturated zone,
the uppermost aquifer, and its  confining
units.  The model should  contain all of the
information necessary to  design a ground-
water monitoring system.

Monitoring Well Placement

This section separately addresses the lateral
placement   and   the   vertical   sampling
intervals  of point  of compliance wells.
However,  these  two aspects  of  well
placement should be  evaluated together in
the design of the monitoring system.  Site-
specific hydrogeologic  data obtained during
the site characterization should be used to
determine the lateral placement of detection
monitoring wells and to  select the length
and vertical position of monitoring  well
intakes. Potential pathways for contaminant
migration     are     three-dimensional.
Consequently, the design of a  detection
monitoring network  that intercepts these
potential      pathways     requires     a
three-dimensional approach.

Lateral    Placement    of  Point   of
Compliance Monitoring Wells

Point  of compliance  monitoring  wells
should be as close as physically possible to
the edge of the MSWLF unit(s) and should
be screened in all  transmissive zones that
may act as contaminant  transport pathways.
The lateral placement of  monitoring wells
should be based  on the number and spatial
distribution  of   potential   contaminant
migration pathways and on the depths and
thicknesses of stratigraphic  horizons that
can  serve  as   contaminant  migration
pathways.
                                         235

-------
                                      Subpart E
Point  of compliance  monitoring  wells
should  be  placed  laterally  along  the
downgradient edge of the MSWLF unit to
intercept    potential    pathways    for
contaminant migration.  The local ground-
water flow direction and  gradient are the
major  factors in determining  the lateral
placement of point of compliance wells. In
a homogeneous,  isotropic hydrogeologic
setting, well placement can  be based on
general   aquifer   characteristics   (e.g.,
direction and  rate of ground-water flow),
and potential contaminant fate and transport
characteristics (e.g., advection, dispersion).
More  commonly,  however,  geology  is
variable and preferential pathways exist that
control  the migration  of  contaminants.
These types of heterogeneous, anisotropic
geologic  settings  can have  numerous,
discrete zones within which  contaminants
may migrate.

Potential migration pathways include  zones
of   relatively  high   intrinsic   (matrix)
hydraulic conductivities, fractured/faulted
zones,  and  subsurface material that may
increase  in  hydraulic conductivity if the
material is exposed to waste(s) managed at
the  site  (e.g.,  a  limestone  layer  that
underlies an acidic waste).  In addition to
natural  hydrogeologic  features,  human-
made features may influence the ground-
water flow direction and,  thus, the lateral
placement of  point of compliance wells.
Such human-made features include ditches,
areas where fill material has been placed,
buried piping,  buildings, leachate collection
systems, and adjacent disposal units.  The
lateral   placement  of  monitoring  wells
should be based on the number and spatial
distribution   of   potential   contaminant
migration pathways and on the depths and
thicknesses  of stratigraphic horizons that
can  serve   as  contaminant   migration
pathways.
In some settings,  the ground-water flow
direction may reverse seasonally (depending
on precipitation), change as a result of tidal
influences   or  river  and  lake   stage
fluctuations,  or change  temporally as a
result of well-pumping or changing land use
patterns.  In other settings, ground water
may flow away from the waste management
area in all  directions. In such cases, EPA
recommends  that  monitoring   wells  be
installed on  all  sides  (or  in  a circular
pattern) around the waste management area
to allow for the detection of contamination.
In  these  cases,  certain  wells   may  be
downgradient only part of the time, but such
a configuration should ensure that releases
from the unit will be detected.

The lateral placement of monitoring wells
also   should  be based on  the  physical/
chemical characteristics of the contaminants
of concern. While the restriction of liquids
in MSWLFs may limit the introduction of
hazardous constituents into landfills, it is
important to consider the physical/chemical
characteristics  of  contaminants   when
designing   the  well  system.     These
characteristics include solubility, Henry's
Law constant, partition coefficients, specific
gravity, contaminant reaction or degradation
products, and the potential for contaminants
to degrade  confining layers. For example,
contaminants with low solubilities and high
specific gravities  that occur as  DNAPLs
may migrate in the subsurface in directions
different from the direction of ground-water
flow.   Therefore,  in situations where the
release of DNAPLs is a concern,  the lateral
placement  of compliance  point ground-
water   monitoring   wells   should  not
necessarily  only be along the downgradient
edge of the MSWLF unit. Considering both
contaminant     characteristics     and
hydrogeologic properties is important when
                                         236

-------
                     Ground-Water Monitoring and Corrective Action
determining  the  lateral  placement  of
monitoring wells.

Vertical Placement and Screen Lengths

Proper selection  of the vertical sampling
interval  is necessary  to  ensure that the
monitoring system is capable of detecting a
release from the MSWLF unit. The vertical
position  and lengths of well intakes are
functions of (1) hydro-geologic factors that
determine   the   distribution   of,    and
fluid/vapor phase transport within,  potential
pathways of contaminant migration to and
within the  uppermost aquifer, and (2) the
chemical and physical characteristics of
contaminants that control their transport and
distribution in the subsurface.  Well intake
length also is determined by  the  need to
obtain  vertically  discrete  ground-water
samples.   Owners and  operators  should
determine the probable location, size, and
geometry of potential contaminant plumes
when selecting well intake positions and
lengths.

Site-specific  hydrogeologic data obtained
during the  site characterization  should be
used  to  select  the  length  and  vertical
position  of monitoring well intakes.  The
vertical positions and lengths of monitoring
well intakes should be based on the number
and   spatial   distribution  of  potential
contaminant migration pathways and on the
depths  and  thicknesses  of stratigraphic
horizons that can serve as contaminant
migration pathways.  Figure 5-2 illustrates
examples  of complex  stratigraphy that
would require multiple vertical monitoring
intervals.

The depth and thickness  of a potential
contaminant  migration pathway  can  be
determined   from  soil,   unconsolidated
material, and rock samples collected during
the boring  program,  and from samples
collected while drilling the monitoring well.
Direct physical data can be supplemented by
geophysical data,  available regional/local
hydrogeological data,  and other data that
provide the vertical distribution of hydraulic
conductivity.  The vertical sampling interval
is not necessarily synonymous with aquifer
thickness.   Monitoring wells are  often
screened at intervals that represent a portion
of the thickness of  the aquifer.   When
monitoring an unconfined aquifer, the well
screen typically should be positioned so that
a  portion  of the  well  screen  is in  the
saturated  zone and a portion of the  well
screen is in the unsaturated zone (i.e., the
well  screen  straddles  the water table).
While the restriction of liquids in MSWLFs
may limit the  introduction of hazardous
constituents into landfills, it is important to
consider      the      physical/chemical
characteristics   of  contaminants  when
designing the well  system.

The  vertical  positions and  lengths  of
monitoring well intakes should be based on
the same physical/chemical characteristics
of  the  contaminants  of  concern  that
influence   the   lateral   placement   of
monitoring   wells.     Considering   both
contaminant     characteristics     and
hydrogeologic properties is important when
choosing the vertical  position and length of
the well intake.  Some contaminants may
migrate within very narrow  zones.   Of
course, for well placement at a new site, it is
unlikely that the owner or operator will be
able to assess contaminant characteristics.

Different   transport   processes   control
contaminant   migration  depending   on
whether the  contaminant dissolves  or is
immiscible   in   water.    Immiscible
                                         237

-------
                           Subpart E
Piezometric
Surface
    Down Gradient Zone
            Flow Path
                                                   69
                                                          65
                          Figure 5-2
                Upgradient and Downgradient
              Designations for Idealized MSWLF
                             238

-------
                     Ground-Water Monitoring and Corrective Action
contaminants  may  occur as  light  non
aqueous phase liquids (LNAPLs), which are
lighter than water, and DNAPLs, which are
denser than water.  LNAPLs migrate in the
capillary zone just above the water table.
Wells installed to monitor LNAPLs should
be screened at the water table/capillary zone
interface, and the screened interval should
intercept the water table at its minimum and
maximum elevation.  LNAPLs may become
trapped in residual form in the vadose zone
and become periodically remobilized and
contribute further to aquifer contamination,
either as free  phase or  dissolved  phase
contaminants, as the water table fluctuates
and precipitation infiltrates the subsurface.

The migration of free-phase DNAPLs may
be influenced primarily  by the geology,
rather than the hydrogeology, of the  site.
That  is,  DNAPLs  migrate   downward
through the saturated zone due to density
and then migrate  by  gravity  along  less
permeable geologic units  (e.g., the slope of
confining units, the slope of clay lenses in
more  permeable strata, bedrock troughs),
even in  aquifers with primarily horizontal
ground-water flow.  Consequently, if wastes
disposed at the site are anticipated to exist
in the subsurface as a DNAPL, the potential
DNAPL should be monitored:

 •  At the base of the aquifer (immediately
    above the confining layer)

 •  In structural depressions (e.g., bedrock
    troughs)    in    lower    hydraulic
    conductivity geologic units that act as
    confining layers

 •  Along lower  hydraulic  conductivity
    lenses and units within units of higher
    hydraulic conductivity
 •   "Down-the-dip"  of lower  hydraulic
     conductivity units that act as confining
     layers,    both    upgradient    and
     downgradient    of    the    waste
     management area.

Because of the nature of DNAPL migration
(i.e., along structural, rather than hydraulic,
gradients),  wells   installed  to  monitor
DNAPLs may  need to  be installed both
upgradient and downgradient of the waste
management area.  It may be  useful to
construct a structure contour map of lower
permeability strata and  identify  lower
permeability   lenses   upgradient   and
downgradient  of the  unit  along  which
DNAPLs may migrate. The wells can then
be located accordingly.

The lengths  of well  screens  used  in
ground-water   monitoring   wells   can
significantly affect their ability to intercept
releases of contaminants.  The complexity
of the hydrogeology of a site is an important
consideration when  selecting the lengths of
well screens. Most  hydrogeologic settings
are    complex    (heterogeneous    and
anisotropic)  to a certain degree.   Highly
heterogeneous  formations require shorter
well screens to allow sampling of discrete
portions of the  formation that can serve as
contaminant migration  pathways.   Well
screens that span  more than   a  single
saturated  zone or  a  single contaminant
migration  pathway  may  cause  cross-
contamination of transmissive units, thereby
increasing  the  extent of contamination.
Well intakes should be installed in a single
saturated zone.  Well intakes  (e.g., screens)
and  filter   pack  materials  should  not
interconnect, or  promote the interconnection
of, zones that are separated by a confining
layer.
                                         239

-------
                                      Subpart E
Even in hydrologically simple formations,
or within a single potential pathway  for
contaminant migration, the use of shorter
well screens may be necessary to detect
contaminants  concentrated  at particular
depths.  A contaminant may be concentrated
at  a  particular   depth  because  of  its
physical/chemical properties and/or because
of   hydrogeologic   properties.      In
homogeneous formations, a long well screen
can   permit   excessive    amounts   of
uncontaminated formation water to dilute
the contaminated ground water entering the
well.    At  best,  dilution  can  make
contaminant detection difficult; at worst,
contaminant detection is impossible if the
concentrations of contaminants are diluted
to levels below the detection limits for the
prescribed analytical methods.  The use of
shorter well screens allows for contaminant
detection  by reducing excessive dilution.
When   placed  at  depths  of  predicted
preferential  flow,  shorter well screens  are
effective in  monitoring the  aquifer or  the
portion of the aquifer of concern.

Generally, screen lengths should not exceed
10 feet.  However, certain hydrogeologic
settings may warrant or necessitate the use
of  longer  well   screens   for  adequate
detection monitoring. Unconfmed aquifers
with widely fluctuating water tables may
require longer screens to intercept the water
table surface  at  both its maximum  and
minimum  elevations and  to   provide
monitoring for the presence of contaminants
that  are less dense than water.  Saturated
zones that are slightly greater in thickness
than the appropriate screen length (e.g., 12
feet  thick) may warrant monitoring with
longer screen lengths.   Extremely thick
homogeneous  aquifers (e.g., greater than
300  feet) may be monitored with a longer
screen (e.g.,  a  20-foot screen) because a
slightly longer screen
would represent a fairly discrete interval in
a very thick formation.  Formations with
very low hydraulic conductivities also may
require  the use of longer well screens to
allow sufficient amounts of formation water
to enter the  well  for  sampling.   The
importance of accurately identifying such
conditions  highlights  the  need  for  a
complete hydrogeologic site  investigation
prior to  the  design  and placement  of
detection wells.

Multiple monitoring wells (well clusters or
multilevel  sampling  devices)  should  be
installed at a  single location when (1) a
single well cannot adequately  intercept and
monitor the vertical extent of a potential
pathway of contaminant migration, or  (2)
there is more than one potential pathway of
contaminant migration in the subsurface at
a single location, or (3) there is  a thick
saturated zone and immiscible  contaminants
are  present,   or  are  determined  to  be
potentially present after considering waste
types managed at the facility. Conversely, at
sites  where  ground  water  may  be
contaminated  by  a  single contaminant,
where there is a  thin saturated zone, and
where   the   site   is   hydrogeologically
homogeneous, the need for multiple wells at
each sampling location is  reduced.  The
number of wells that should be installed at
each sampling  location increases with site
complexity.

The following sources provided additional
information on monitoring well placement:
USEPA (1992a),  USEPA  (1990), USEPA
(1991), and USEPA (1986a).
                                         240

-------
                    Ground-Water Monitoring and Corrective Action
5.7 GROUND-WATER
    MONITORING WELL DESIGN
    AND  CONSTRUCTION
    40 CFR §258.51 (c)

5.7.1  Statement of Regulation

 (c) Monitoring wells must be cased in a
manner that maintains the integrity of
the monitoring well bore hole.   This
casing must be screened or  perforated
and packed with gravel or sand,  where
necessary, to enable collection of ground-
water samples.  The annular  space (i.e.,
the space between the bore hole and well
casing) above the sampling depth must be
sealed  to  prevent   contamination  of
samples and the ground water.

 (1) The owner or operator must notify
the  State  Director  that  the design,
installation,     development,     and
decommission of any monitoring wells,
piezometers  and  other  measurement,
sampling,    and   analytical  devices
documentation  has  been placed  in the
operating record;  and

 (2) The monitoring wells, piezometers,
and other measurement,  sampling, and
analytical devices must be operated and
maintained so that they perform to design
specifications throughout the life  of the
monitoring program.

§258.52 [Reserved].

5.7.2  Applicability

The  requirements for  monitoring well
design, installation, and maintenance are
applicable to all wells installed at existing
units, lateral expansions of units, and new
MSWLF units. The design, installation, and
decommissioning of any monitoring well
must be documented in the operating record
of the facility and certified by a qualified
ground-water scientist.   Documentation is
required for wells, piezometers, sampling
devices,  and  water level  measurement
instruments used in the monitoring program.

The  monitoring wells  must be cased  to
protect the integrity of the borehole.  The
design and construction  of the well directly
affects the quality and representativeness of
the samples collected. The well casing must
have a screened or perforated interval  to
allow the entrance of water into the well
casing. The annular space between the well
screen  and the  formation  wall  must be
packed  with   material  to  inhibit  the
migration of formation material into the
well. The well  screen must have openings
sized according to the packing material
used.  The annular space above the filter
pack must be sealed to provide a discrete
sampling interval.

All  monitoring  wells,   piezometers,  and
sampling and analytical  devices must be
maintained in a manner that ensures their
continued performance according to design
specifications over the life of the monitoring
program.

5.7.3 Technical Considerations

The design, installation, and maintenance of
monitoring wells will affect the consistency
and  accuracy of samples collected.  The
design  must be  based  on  site-specific
information.    The  formation  material
(lithology and grain size distribution) will
determine the selection of proper packing
and sealant materials, and the stratigraphy
will  determine  the screen length for the
interval to be monitored.  Installation
                                        241

-------
                                       Subpart E
practices should be specified and overseen
to  ensure  that the  monitoring well  is
installed as designed and will perform as
intended.   This section will discuss  the
factors  that  must be  considered  when
designing monitoring wells.  Each well  must
be  tailored to  suit the  hydrogeological
setting,  the contaminants to be monitored,
and other site-specific factors. Figure  5-3
depicts   the  components   of   a  typical
monitoring well installation.

The following  sections provide  a brief
overview of monitoring well design and
construction.      More   comprehensive
discussions are  provided in USEPA (1989f)
andUSEPA(1992a).

Selection of Drilling Method

The method chosen for drilling a monitoring
well  depends  largely  on  the  following
factors (USEPA, 1989f):

 •  Versatility of the drilling method

 •  Relative drilling cost

 •  Sample reliability (ground-water, soil,
    unconsolidated  material,  or  rock
    samples)

 •  Availability of drilling  equipment

 •  Accessibility  of the drilling  site

 •  Relative   time  required   for  well
    installation and development

 •  Ability of the drilling  technology to
    preserve natural conditions

 •  Ability to install  a  well of desired
    diameter and depth
 •   Relative ease of well completion and
     development, including the ability to
     install   the  well   in  the  given
     hydrogeologic setting.

In addition to these factors, USEPA (1989f)
includes matrices  to assist in selecting  an
appropriate drilling method. These matrices
list  the  most   commonly  used  drilling
techniques for monitoring well installation,
taking into consideration  hydrogeologic
settings and the objectives of the monitoring
program.

The following basic performance objectives
should  guide  the selection of  drilling
procedures for installing monitoring wells:

 •   Drilling should  be  performed in  a
     manner  that preserves the natural
     properties of the subsurface materials.

 •   Contamination     and/or     cross-
     contamination of ground  water and
     aquifer materials during drilling should
     be avoided.

 •   The drilling method should allow for
     the   collection   of   representative
     samples  of  rock,   unconsolidated
     materials, and soil.

 •   The drilling method should allow the
     owner/operator to determine when the
     appropriate location for the  screened
     interval has been encountered.

 •   The drilling method should allow for
     proper placement of the filter pack and
     annular sealants.  The borehole should
     be at least 4 inches larger in  diameter
     than the nominal diameter  of the well
     casing  and screen to allow adequate
                                         242

-------
                                      Protective Cover
                                      with Locking Cap
                   6 in (152mm)  	
                   Clearance for Sampler
                   Top of Riser 3 ft
                   (1.0m) Above Grade
2 ft (606mm) x 4" (101mm) Thic
Neat Concrete Pad
3 tt-5 ft (1.0-1.5m) Surface Seal of
Neat Cement Extended to at Least 1
ft below Frost Line  	
         Minimum 2" (50mm) ID Riser with
         Flush Threaded Connections
Well Identification Labeled Inside
and Outside the Cap

Vented Cap

Protective Casing

1/4" (6.3mm) Weep Hole at 6" Above Ground Level
3 ft-5 ft. (1.0 to'l.Sm) Protective Casing
Anchored Below Frost Line
                                                        Grout Length Varies
                   Borehole
                   Centralizer(s) As
                   Necessary
                               Plug
                                                        3 ft-5 ft (1.0m-1.5m) Bentonite Seal
 1 ft-2 ft (303mm-€06mm) Filter Pack
 Extended 2 ft (606mm) Above Slotted Well
 Screen
                                                        Well Screen Length Varies
 Sediment Sump (As Appropriate)
  Figure 5.3.  Example of a Monitoring Well Design-Single Cased Well
                                              243

-------
                                       Subpart E
     space for placement of the filter pack
     and annular sealants.

 •   The drilling method should allow for
     the collection of representative ground-
     water  samples.    Drilling  fluids
     (including air)  should be used only
     when  minimal   impact   to    the
     surrounding   formation  and  ground
     water can be ensured.

The following guidelines apply to the use of
drilling fluids, drilling fluid additives, and
lubricants  when  drilling  ground-water
monitoring wells:

 •   Drilling fluids, drilling fluid additives,
     or lubricants that affect the analysis of
     hazardous constituents in ground-water
     samples should not be used.

 •   The     owner/operator     should
     demonstrate  the inertness of drilling
     fluids,  drilling  fluid  additives,  and
     lubricants  by performing  analytical
     testing of drilling fluids, drilling fluid
     additives,  and  lubricants and/or by
     providing  information regarding  the
     composition of drilling fluids, drilling
     fluid additives, or lubricants obtained
     from the manufacturer.

 •   The  owner/operator should consider
     the potential impact of drilling fluids,
     drilling fluid additives, and lubricants
     on   the   physical  and  chemical
     characteristics of the subsurface and on
     ground-water quality.

 •   The volume of drilling fluids, drilling
     fluid additives,  and  lubricants  used
     during the drilling of a monitoring well
     should be recorded.
Monitoring Well Design

Well Casing

Well Casing and Screen Materials

A casing and well screen are installed in a
ground-water monitoring well for several
reasons: to provide access from the surface
of  the  ground  to  some  point  in  the
subsurface, to  prevent  borehole collapse,
and to  prevent hydraulic communication
between zones within  the subsurface.   In
some cases, State or local regulations may
specify  the casing and material that  the
owner  or  operator  should  use.     A
comprehensive discussion of well casing
and screen materials is provided in USEPA
(1989f)  and  in USEPA (1992a).    The
following discussion briefly  summarizes
information contained in these references.

Monitoring well casing and screen materials
may be  constructed of any of several types
of materials, but should meet the following
performance specifications:

 •  Monitoring  well  casing and screen
    materials   should   maintain   their
    structural  integrity and durability in
    the environment in which they are used
    over their operating life.

 •  Monitoring well casings and screens
    should be resistant to  chemical and
    microbiological    corrosion    and
    degradation  in  contaminated  and
    uncontaminated waters.

 •  Monitoring well casings and screens
    should  be  able   to  withstand  the
    physical  forces acting  upon them
    during and following their installation
    and during their use — including forces
                                         244

-------
                     Ground-Water Monitoring and Corrective Action
     due to suspension  in  the  borehole,
     grouting,    development,    purging,
     pumping,  and sampling and  forces
     exerted on them by the surrounding
     geologic materials.

 •   Monitoring well  casing and  screen
     materials should not chemically alter
     ground-water  samples, especially with
     respect to the  analytes of concern, as a
     result of their sorbing, desorbing,  or
     leaching  analytes.   For example,  if
     chromium is an analyte of interest, the
     well  casing  or  screen  should not
     increase or decrease the amount  of
     chromium in  the ground water. Any
     material leaching from the  casing  or
     screen should not be  an analyte  of
     interest or interfere in the analysis  of
     an analyte of interest.

In addition, monitoring  well casing and
screen materials should be relatively easy to
install into the borehole during construction
of the monitoring well.

The  selection  of  the most suitable well
casing and screen materials  should consider
site-specific factors, including:

 •   Depth to the water-bearing zone(s) to
     be monitored  and the anticipated well
     depth

 •   Geologic environment

 •   Geochemistry of soil, unconsolidated
     material,  and rock over the  entire
     interval in which the well is  to be cased

 •   Geochemistry of the ground water at
     the  site,  as determined  through   an
     initial analysis of samples from both
     background wells and downgradient
     wells and including:

     - Natural ground-water geochemistry

     - Nature   of  suspected  or  known
      contaminants

     - Concentration of suspected or known
      contaminants

 •   Design life of the monitoring well.

Casing materials widely available for use in
ground-water  monitoring  wells can  be
divided into three categories:

 1)  Fluoropolymer  materials,  including
     polytetrafluoroethylene     (PTFE),
     tetrafluoroethylene (TFE), fluorinated
     ethylene     propylene     (FEP),
     perfluoroalkoxy     (PFA),     and
     polyvinylidene fluoride (PVDF)

 2)  Metallic materials, including carbon
     steel,  low-carbon  steel, galvanized
     steel, and stainless steel (304 and 316)

 3)  Thermoplastic  materials,  including
     polyvinyl   chloride   (PVC)   and
     acrylonitrile butadiene styrene (ABS).

In addition to these three categories  of
materials,   fiberglass-reinforced  plastic
(FRP)  has been  used   for  monitoring
applications.  Because FRP has not yet been
used  in  general  application across  the
country, very little data are available on its
characteristics and performance. All well
construction     materials     possess
strength-related characteristics and chemical
resistance/chemical       interference
characteristics   that   influence   their
performance in site-specific hydrogeologic
                                         245

-------
                                       Subpart E
and    contaminant-related    monitoring
situations.

The  casing must be  made  of a material
strong enough to last for the life of the well.
Tensile strength is needed primarily during
well  installation when the casing is lowered
into  the hole.   The joint  strength  will
determine the maximum length of a  section
that can be  suspended  from the surface in an
air-filled borehole.

Collapse strength is  the capability of  a
casing to resist collapse by  any external
loads to which it is subjected both  during
and  after installation.  A casing is most
susceptible to collapse during installation
before placement of the filter  pack  or
annular seal materials around the casing.
Once a  casing is installed and supported,
collapse is seldom a concern.  Several steps
that  can be taken to avoid casing collapse
are:

 1)  Drilling a straight, clean borehole

 2)  Uniformly  distributing  filter  pack
     materials at a slow, even rate

 3)  Avoiding use of quick-setting (high
     temperature) cements for thermoplastic
     casings installation.

Compressive  strength of the casing  is  a
measure of the greatest compressive stress
that a casing can bear without deformation.
Casing failure due to a compressive  strength
limitation generally  is  not  an  important
factor in a properly installed well. This type
of failure  results from  soil friction on
unsupported casing.

Chemical      resistance/interference
characteristics  must be  evaluated  before
selecting   monitoring   well   materials.
Metallic casing materials are more subject
to corrosion,  while thermoplastic  casing
materials are more susceptible to chemical
degradation.   The geochemistry  of  the
formation water influences the  degree to
which  these processes occur. If ground-
water  chemistry  affects  the  structural
integrity of the casing, then the samples
collected from the well are likely  to be
affected.

Materials used for monitoring well casing
must not exhibit a tendency  to sorb or leach
chemical constituents from, or into,  water
sampled from the well.  If a casing material
sorbs constituents from ground water, those
constituents may  either not  be detected
during  monitoring or be detected  at a lower
concentration.  Chemical constituents also
can be  leached from the casing materials by
aggressive   aqueous  solutions.     These
constituents may be detected in samples
collected from the well.  The results may
indicate contamination that is due to the
casing rather than the formation  water.
Casing materials must be selected with care
to avoid degradation of the well and to
avoid erroneous results.

In certain situations it may be advantageous
to design  a  well using  more  than  one
material for well components.  For example,
where  stainless  steel  or  fluoropolymer
materials   are preferred   in  a specific
chemical environment, costs may be saved
by using PVC in non-critical portions of the
well.   These savings may be considerable,
especially  in  deep wells where only the
lower  portion of the well  is in a critical
chemical environment and where  tens of
feet of lower-cost PVC may be used in the
upper portion of the well.  In a composite
well design, dissimilar metallic
                                         246

-------
                     Ground-Water Monitoring and Corrective Action
components should not be used unless an
electrically isolating design is incorporated
(i.e., a dielectric coupling) (USEPA, 1986).

Coupling Procedures for Joining Casing

Only a  limited number  of  methods  are
available for joining lengths of casing or
casing and screen together.   The joining
method depends on the type of casing  and
type of casing joint.

There are generally two options available
for joining metallic well casings: welding
via application of heat, or threaded joints.
Threaded joints provide inexpensive, fast,
and convenient connections  and greatly
reduce potential  problems with chemical
resistance or interference (due to corrosion)
and explosion potential. Wrapping the male
threads with fluoropolymer tape prior to
joining sections improves the watertightness
of  the joint.   One  disadvantage to using
threaded joints  is that the tensile strength of
the   casing    string   is  reduced   to
approximately  70 percent of the  casing
strength.  This reduction in strength does
not usually pose a problem because strength
requirements for small  diameter wells (such
as  typical  monitoring wells) are  not as
critical and because metallic casing has a
high initial tensile strength.

Joints should create a uniform  inner  and
outer casing  diameter  in monitoring well
installations.      Solvent  cementing   of
thermoplastic pipe should never be used in
the construction of ground-water monitoring
wells. The cements used in solvent welding,
which are organic  chemicals, have been
shown to adversely affect the integrity of
ground-water samples for more than 2 years
after well installation;  only factory-
threaded  joints   should  be   used  on
thermoplastic well material.

Well Casing Diameter

Although the diameter of the casing for a
monitoring well depends on the purpose of
the well, the casing size is generally selected
to  accommodate  downhole  equipment.
Additional casing diameter selection criteria
include the 1) drilling or well installation
method used,  2)  anticipated  depth of the
well and associated strength requirements,
3) anticipated method of well development,
4) volume of water required to be purged
prior to sampling, 5) rate of recovery of the
well  after purging,  and  6)  anticipated
aquifer testing.

Casing Cleaning Requirements

Well casing and screen materials should be
cleaned prior to installation to remove any
coatings or manufacturing residues.  Prior to
use, all casing and screen materials should
be washed with  a  mild,  non-phosphate,
detergent/potable water solution and rinsed
with potable water. Hot pressurized water,
such as in steam cleaning, should be used to
remove organic solvents, oils, or lubricants
from  casing  and screens  composed  of
materials other than plastic.  At sites where
volatile  organic   contaminants  may  be
monitored, the cleaning of well casing and
screen materials should include a final rinse
with deionized water or potable water that
has not been chlorinated.  Once cleaned,
casings and screens should be stored in an
area that is free of potential contaminants.
Plastic  sheeting can generally be used to
cover the ground  in the  decontamination
area   to   provide   protection   from
contamination. USEPA  (1989f) describes
the procedures
                                         247

-------
                                       Subpart E
that should be used  to  clean  casing  and
screen materials.

Well Intake Design

The owner/operator  should  design  and
construct the intakes of monitoring wells to
(1) accurately sample the aquifer zone that
the well is intended to sample, (2) minimize
the  passage   of  formation  materials
(turbidity)  into  the well,  and (3)  ensure
sufficient structural integrity to prevent the
collapse of the intake structure.  The goal of
a properly completed monitoring well is to
provide  low  turbidity  water that  is
representative of ground-water quality in
the vicinity of the well.  Close  attention to
proper selection of packing materials and
well development  procedures  for  wells
installed in fine-grained formations (e.g.,
clays and silty glacial tills) is important to
minimize sample turbidity from suspended
and colloidal  solids.    There  may  be
instances where wells completed in rock do
not require screens or filter packs; the State
regulatory agency should be consulted prior
to completion of unscreened wells.

The selection  of  screen  length  usually
depends  on  the objective  of the well.
Piezometers and wells where only a discrete
flow path is monitored (such as thin gravel
interbedded  with  clays)   are generally
completed  using short screens (2 feet or
less).  To avoid dilution, the well screens
should  be  kept  to the  minimum  length
appropriate for intercepting a contaminant
plume, especially in a high-yielding aquifer.
The screen length should generally  not
exceed 10 feet.  If construction of a water
table well  is  the objective,   either for
defining gradient  or detecting floating
phases, then a longer screen is acceptable
because  the  owner/operator will  need to
provide  a  margin  of  safety  that will
guarantee that at least  a portion of the
screen always contacts  the  water table
regardless of its seasonal fluctuations. The
owner or operator should not employ well
intake designs that cut across hydraulically
separated geologic units.

Well  screen slot size should be selected to
retain from 90 percent to  100 percent of the
filter pack material (discussed  below) in
artificially filter packed wells. Well screens
should be factory-slotted. Manual slotting
of  screens  in the  field  should  not  be
performed under any circumstances.

Filter Pack Design

The primary filter pack material should be a
chemically inert material  and well rounded,
with a high coefficient of uniformity. The
best filter pack materials are made from
industrial grade glass (quartz) sand or beads.
The use  of other materials, such as local,
naturally  occurring   clean   sand,   is
discouraged unless it can be shown that the
material  is inert (e.g., low cation exchange
capacity), coarse-grained, permeable, and
uniform in grain size. The filter pack should
extend at least 2 feet above the screened
interval in the well.

Although design techniques for selecting
filter pack size vary, all use the  filter pack
ratio  to establish size differential between
formation   materials   and   filter  pack
materials.  Generally, this ratio refers to
either the  average (50  percent retained)
grain size of the formation material or to the
70  percent retained size  of the  formation
material.     Barcelona   et   al.   (1985b)
recommend using  a uniform filter pack
grain size that is three to five times the size
                                          248

-------
                     Ground-Water Monitoring and Corrective Action
of the  50 percent  retained size of  the
formation material (USEPA, 1990).

Filter pack material should be installed in a
manner that prevents bridging and particle-
size   segregation.    Filter  pack  material
installed  below the  water table should
generally be tremied into the annular space.
Allowing filter  pack material  to fall  by
gravity (free fall) into the annular space is
only appropriate when wells are relatively
shallow, when the filter pack has a uniform
grain size, and when the filter pack material
can be poured continuously into the well
without stopping.

At least  2 inches  of filter pack material
should be installed between the well screen
and  the  borehole  wall.  The filter  pack
should extend at least 2 feet above the top of
the well screen.  In deep wells, the filter
pack may not  compress  when initially
installed.  Consequently, when the annular
and  surface seals  are placed on the filter
pack, the filter pack compresses sufficiently
to allow grout into, or very  close to,  the
screen. Consequently, filter packs may  need
to be installed as high as 5 feet  above  the
screened interval in monitoring wells that
are deep (i.e., greater than 200 feet). The
precise volume of filter  pack  material
required should be calculated and recorded
before placement,  and the actual volume
used  should be  determined and  recorded
during well construction.  Any  significant
discrepancy between the calculated volume
and the actual volume should be explained.

Prior to installing  the annular seal, a 1- to
2-foot layer of chemically  inert fine sand
may  be placed over the filter pack to prevent
the intrusion of annular or surface sealants
into   the  filter  pack.   When   designing
monitoring wells, owners and
operators  should remember that the entire
length of the annular space filled with filter
pack material or  sand is effectively  the
monitored zone.   Moreover, if the  filter
pack/sand extends from the screened zone
into an  overlying zone, a  conduit  for
hydraulic connection is created between the
two zones.

Annular Sealants

Proper sealing of the annular space between
the well casing and the borehole wall is
required   to   prevent   contamination   of
samples and the ground water.  Adequate
sealing will prevent hydraulic  connection
within the  well annulus. The materials used
for annular sealants should be chemically
inert   with   the  highest    anticipated
concentration  of  chemical   constituents
expected in the ground water at the facility.
In general, the permeability of  the sealing
material  should be one to two orders  of
magnitude lower  than  the least permeable
part of the formation in contact with the
well.   The  precise  volume  of annular
sealants required should be calculated  and
recorded before placement, and the actual
volume used  should  be  determined and
recorded  during well  construction.  Any
significant   discrepancy   between    the
calculated volume and the actual volume
should be  explained.

When  the screened interval is  within  the
saturated  zone, a minimum  of 2  feet  of
sealant material, such as raw  (>10 percent
solids)  bentonite,  should  be   placed
immediately over the protective sand layer
overlying  the filter   pack.    Granular
bentonite, bentonite pellets, and bentonite
chips may be  placed around the casing by
means  of a  tremie pipe in deep  wells
(greater than approximately 30  feet deep),
                                         249

-------
                                      Subpart E
or by  dropping them directly down  the
annulus  in  shallow  wells  (less  than
approximately 30 feet deep). Dropping the
bentonite pellets down the annulus presents
a potential for bridging (from premature
hydration of the bentonite), leading to gaps
in the  seal below the bridge.  In shallow
monitoring wells, a tamping device should
be used to prevent bridging from occurring.

A neat cement or shrinkage-compensated
neat cement grout seal should be installed
on top of the bentonite seal  and extend
vertically up the  annular space between the
well casing and the borehole wall to within
a few feet of land surface.  Annular sealants
in slurry form (e.g.,  cement grout, bentonite
slurry) should be placed by the tremie/pump
(from the bottom up) method.  The bottom
of the  placement pipe should be equipped
with a side discharge deflector to prevent
the slurry from jetting a hole through  the
protective  sand  layer,  filter pack,  or
bentonite seal. The  bentonite seal should be
allowed to completely hydrate, set, or cure
in conformance with  the  manufacturer's
specifications prior to installing the  grout
seal in the annular space. The time required
for the bentonite seal to completely hydrate,
set,  or cure will differ with the materials
used   and    the    specific   conditions
encountered, but is generally a minimum of
4 to  24 hours. Allowing the bentonite seal
to hydrate, set, or cure prevents the invasion
of the more viscous and more chemically
reactive grout seal into the screened area.

When using bentonite as an annular sealant,
the appropriate clay should be selected on
the basis of the environment in which it is to
be used, such as the  ion-exchange potential
of the sediments,  sediment permeability,
and    compatibility    with    expected
contaminants. Sodium bentonite is usually
acceptable.
When the annular sealant must be installed
in the unsaturated zone,  neat cement or
shrinkage-compensated    neat    cement
mixtures should  be used for the annular
sealant.  Bentonite is not recommended as
an annular  sealant in the unsaturated zone
because   the   moisture    available   is
insufficient to fully hydrate bentonite.

Surface Completion

Monitoring wells  are  commonly  either
above-ground  completions  or  flush-to-
ground  completions.  The  design of both
types must  consider  the  prevention of
infiltration  of surface runoff into the well
annulus and the possibility of accidental
damage  or  vandalism.    Completing  a
monitoring  well  involves  installing the
following components:

•  Surface  seal

•  Protective casing

•  Ventilation hole

•  Drain hole

•  Cap and lock

•  Guard posts when wells are completed
   above grade.

A surface seal, installed on top of the grout
seal, extends vertically up the well annulus
to the land  surface.  To protect against frost
heave, the seal should extend at least 1 foot
below the frost line.  The composition of the
surface  seal should be  neat  cement or
concrete. In an above-ground completion,
the surface  seal should form at least a 2-foot
wide, 4-inch thick apron.
                                         250

-------
                     Ground-Water Monitoring and Corrective Action
A locking  protective casing  should be
installed around the well casing to prevent
damage  or  unauthorized  entry.    The
protective casing should be anchored below
the frost line (where applicable) into the
surface seal and extend at least 18 inches
above the surface of the ground.  A 1/4-inch
vent hole pipe is recommended to allow the
escape of any potentially explosive gases
that may accumulate within the well. In
addition, a drain hole should be installed in
the protective casing to prevent water from
accumulating  and,  in freezing climates,
freezing around the well casing.  The space
between the protective casing and the  well
casing may be filled with gravel to allow the
retrieval  of  tools and to prevent small
animal/insect entrance through the drain.  A
suitable cap should be placed on the well to
prevent tampering  or the  entry  of  any
foreign materials.    A  lock  should be
installed on the cap to provide security. To
prevent corrosion or jamming of the lock, a
protective  cover should  be  used.   Care
should be taken when using such lubricants
as graphite  or petroleum-based sprays to
lubricate  the  lock,  as  lubricants  may
introduce   a   potential   for   sample
contamination.

To guard against accidental damage to the
well from facility traffic, the owner/operator
should install  concrete  or steel bumper
guards around the  edge  of the  concrete
apron.  These should be located within 3 or
4 feet of the  well and should be painted
orange or fitted with reflectors to reduce the
possibility of vehicular damage.

The   use   of  flush-to-ground   surface
completions should be avoided because this
design increases the potential for surface
water infiltration into  the well.   In cases
where  flush-to-ground  completions   are
unavoidable, such as in active roadways, a
protective structure, such as a utility vault
or meter box, should be installed around the
well casing.  In addition, measures should
be taken to  prevent the accumulation of
surface water in the protective structure and
around the well intake.  These measures
should include outfitting the protective
structure with a steel lid  or manhole cover
that has a rubber seal or gasket and ensuring
that  the bond between  the cement surface
seal   and  the  protective   structure  is
watertight.

Well Surveying

The location of all wells should be surveyed
by  a licensed professional  surveyor (or
equivalent)  to  determine  their X-and-Y
coordinates as well as  their distances from
the   units  being   monitored  and  their
distances from each other. A State Plane
Coordinate System,  Universal  Transverse
Mercator  System,  or  Latitude/Longitude
should be used, as approved by the Regional
Administrator. The survey should also note
the    coordinates   of  any   temporary
benchmarks.  A surveyed reference  mark
should be  placed on  the top of the  well
casing, not on the protective  casing or the
well apron, for use as a measuring  point
because the well casing is  more stable than
the protective casing or well apron (both the
protective  casing and  the well  apron are
more  susceptible  to   frost  heave  and
spalling).    The  height  of  the  reference
survey datum, permanently marked on top
of  the  inner  well  casing,  should   be
determined within ±0.01  foot in relation to
mean sea level, which in turn is determined
by  reference to  an established  National
Geodetic Vertical Datum.  The reference
marked on top of inner well casings should
be re surveyed at least once every 5 years,
                                         251

-------
                                      Subpart E
unless  changes  in   ground-water  flow
patterns/direction,  or damage caused by
freeze/thaw  or  desiccation processes, are
noted.   In  such  cases,  the  Regional
Administrator may require that well casings
be resurveyed on a more frequent basis.

Well Development

All monitoring wells  should be developed to
create an effective filter pack around the
well  screen, to  rectify damage  to  the
formation caused by drilling, to remove fine
particles from  the  formation  near  the
borehole, and  to  assist in  restoring the
natural water quality of the aquifer in the
vicinity of the well. Development stresses
the formation around the screen, as well as
the filter pack,  so  that mobile fines,  silts,
and  clays are  pulled  into the  well and
removed. The process of developing a well
creates a graded filter pack around the well
screen. Development is also used to remove
any foreign materials (drilling water, muds,
etc.) that may have been introduced into the
well  borehole  during drilling  and  well
installation and to aid in the equilibration
that will occur between the filter pack, well
casing, and the formation water.

The  development  of a  well is extremely
important to ensuring  the  collection  of
representative ground-water samples.  If the
well  has been  properly completed,  then
adequate development should remove fines
that may enter the well either from the filter
pack  or the formation.  This improves the
yield, but more importantly  it  creates  a
monitoring  well   capable  of  producing
samples of acceptably low turbidity. Turbid
samples from an improperly constructed and
developed   well   may   interfere   with
subsequent analyses.
When development is initiated, a wide range
of grain sizes  of the natural  material is
drawn into the well, and the well typically
produces very turbid water. However, as
development continues  and  the natural
materials are drawn into the filter pack, an
effective filter will form through a sorting
process.   Inducing  movement of ground
water into the well  (i.e., in one direction)
generally results in bridging of the particles.
A means  of inducing  flow  reversal is
necessary  to  break  down bridges  and
produce a stable filter.

The   commonly  accepted  methods  for
developing wells  are described in USEPA
(1989f)  and Driscoll (1986) and include:

 •  Pumping and overpumping

 •  Surging with  a surge block

 •  Bailing.

USEPA   (1989f)  provides  a  detailed
overview of well  development and should
be  consulted   when  evaluating   well
development methods.

Documentation   of   Well     Design.
Construction, and Development

Information on the design,  construction, and
development  of  each  well  should  be
compiled.  Such information should include
(1) a boring log that documents well drilling
and associated formation sampling and (2)
a  well   construction  log   and   well
construction diagram ("as built").
                                        252

-------
                    Ground-Water Monitoring and Corrective Action
Decommissioning	Ground-Water
Monitoring Wells and Boreholes

Ground-water contamination resulting from
improperly  decommissioned  wells  and
boreholes  is a  serious  concern.   Any
borehole that will not be completed as a
monitoring  well  should  be   properly
decommissioned.  The USEPA (1975) and
the American  Water  Works  Association
(1985)  provide  the  following  reasons,
summarized by USEPA (1989f), as to why
improperly  constructed  or  unused wells
should be properly decommissioned:

 •  To eliminate physical hazards
    To     prevent
    contamination
ground-water
 •  To  conserve  aquifer  yield   and
    hydrostatic head

 •  To prevent intermixing of subsurface
    water.

Should  an  owner  or operator have  a
borehole or  an improperly constructed or
unused well at his or her facility, the well or
borehole should be decommissioned in
accordance   with   specific   guidelines.
USEPA (1989f) provides  comprehensive
guidance     on    performing    well
decommissioning that  can be  applied to
boreholes.   In addition, any State/Tribal
regulatory guidance should be consulted
prior to decommissioning monitoring wells,
piezometers,  or boreholes.    Lamb  and
Kinney (1989) also provide information on
decommissioning ground-water  monitoring
wells.

Many States  require that specific procedures
be followed and certain paperwork be filed
when decommissioning water supply wells.
                    In  some  States,  similar regulations may
                    apply to the decommissioning of monitoring
                    wells and boreholes.  The EPA and other
                    involved  regulatory  agencies, as well  as
                    experienced    geologists,    geotechnical
                    engineers, and drillers, should be consulted
                    prior to decommissioning a well or borehole
                    to   ensure  that  decommissioning   is
                    performed   properly   and  to   ensure
                    compliance with  State law. If a well to be
                    decommissioned  is contaminated, the safe
                    removal and proper disposal of the well
                    materials  should  be   ensured   by  the
                    owner/operator.   Appropriate   measures
                    should be taken to protect the health and
                    safety of individuals when decommissioning
                    a well or borehole.
                    5.8  GROUND-WATER SAMPLING
                        AND ANALYSIS
                        REQUIREMENTS
                        40 CFR §258.53

                    5.8.1 Statement of Regulation

                     (a) The   ground-water   monitoring
                    program   must    include   consistent
                    sampling and analysis procedures that
                    are designed to ensure monitoring results
                    that provide an accurate representation
                    of  ground-water   quality   at    the
                    background  and  downgradient  wells
                    installed in compliance with §258.51(a) of
                    this Part. The owner or operator must
                    notify  the  State  Director  that  the
                    sampling   and   analysis   program
                    documentation has been  placed in  the
                    operating record and the program must
                    include procedures and techniques for:

                     (1) Sample collection;

                     (2) Sample preservation and shipment;
                                        253

-------
                                    Subpart E
 (3) Analytical procedures;

 (4) Chain of custody control; and

 (5) Quality   assurance  and   quality
    control.

 (b) The   ground-water   monitoring
program  must  include  sampling  and
analytical methods that are appropriate
for ground-water  sampling and  that
accurately     measure     hazardous
constituents   and   other   monitoring
parameters in ground-water  samples.
Ground-water samples shall not be field-
filtered prior to laboratory analysis.

 (c) The   sampling  procedures   and
frequency must be protective of human
health and the environment.

 (d) Ground-water  elevations  must be
measured in each well immediately prior
to purging, each time ground  water is
sampled.  The owner or operator must
determine  the rate  and direction of
ground-water  flow each time ground
water   is  sampled.    Ground-water
elevations  in  wells which  monitor  the
same  waste management area  must be
measured within a period of time short
enough to  avoid temporal variations in
ground-water flow which could  preclude
accurate determination of ground-water
flow rate and direction.

 (e) The   owner  or   operator   must
establish   background   ground-water
quality in a hydraulically upgradient or
background  well(s)  for  each  of  the
monitoring parameters or constituents
required in the particular ground-water
monitoring program that applies to the
MSWLF  unit,  as   determined  under
§258.54(a), or
§258.55(a)  of this  Part.   Background
ground-water quality may be established
at wells that are not located hydraulically
upgradient from the MSWLF unit if it
meets the requirements of §258.51(a)(l).

 (f) The number of samples collected to
establish ground-water quality data must
be  consistent   with   the  appropriate
statistical    procedures    determined
pursuant to paragraph (g) of this section.
The sampling procedures shall be those
specified under §258.54(b) for detection
monitoring,  §258.55(b)  and  (d)  for
assessment monitoring, and §258.56(b) of
corrective action.

5.8.2 Applicability

The requirements for sampling and analysis
apply  to  all facilities required to conduct
ground-water  monitoring  throughout  the
active life, closure, and post-closure periods
of operation. Quality assurance and quality
control  measures  for  both  field  and
laboratory activities must be implemented.
The methods  and procedures constituting
the program must be placed in the operating
record of the facility.

For the sampling and analysis program to be
technically sound, the sampling procedures
and analytical methods used should provide
adequate accuracy, precision, and detection
limits for the analyte determinations. Prior
to  sampling,  the  static  ground-water
elevations in the wells must be measured to
allow determination of the direction of
ground-water  flow and estimates of rate of
flow.     The  time  interval  between
measurements at different wells must be
minimized  so that temporal changes in
ground-water  elevations do not cause an
                                       254

-------
                     Ground-Water Monitoring and Corrective Action
incorrect  determination  of  ground-water
flow direction.

Background ground-water quality must be
established at all upgradient or background
wells.  The background water quality may
be  determined from  wells  that are  not
upgradient of the MSWLF unit, provided
that the wells yield representative ground-
water samples.

The sampling program must be designed in
consideration of the anticipated  statistical
method applied by the owner or operator.
The data  objectives  of  the  monitoring
program, in terms of the number of samples
collected and the frequency  of collection,
should  be appropriate for the  statistical
method selected for data comparison.

5.8.3  Technical Considerations

The purpose of a ground-water sampling
and  analysis  program is to  establish a
protocol that can be followed throughout the
monitoring period of the site (operating,
closure, and post-closure). The protocol is
necessary  so  that data  acquired can  be
compared   over   time  and   accurately
represent  ground-water quality.  Sample
collection, preservation, shipment, storage,
and analyses should always be performed in
a consistent manner,  even as monitoring
staff change during the monitoring period.

The   owner's/operator's    ground-water
monitoring  program  must  include   a
description of procedures for the following:

•  Sample collection

•  Sample preservation and shipment

•  Analytical procedures
•  Chain of custody control

•  Quality assurance and quality control.

The ground-water monitoring program must
be documented in the operating record of
the facility.

The objectives of the monitoring program
should clearly define the quality of the data
required to  detect significant  changes in
ground-water chemistry due to the operation
of the solid waste disposal facility.  These
data quality objectives should address:

•  Accuracy and precision of methods used
   in  the analysis  of  samples, including
   field measurements

•  Quality  control  and quality assurance
   procedures used to ensure the validity of
   the results  (e.g.,  use of blank samples,
   record keeping, and  data validation)

•  Number of samples required to obtain a
   certain degree of statistical confidence
                          of  monitoring
•  Location  and number
   wells required.

Sample Collection

Frequency
The frequency of sample collection under
detection monitoring should be evaluated
for each site according to hydrogeologic
conditions and landfill design.  In States, the
minimum sampling frequency should be
semiannual.         The      background
characterization   should   include   four
independent samples  at each  monitoring
location during the first semi-annual event
(i.e.,   during  the  first  6   months  of
                                         255

-------
                                      Subpart E
monitoring).   (See the discussion  under
Section 5.10.3  on collecting independent
samples to determine background.)  More
frequent sampling may be selected.  For
example,   quarterly  sampling  may  be
conducted to evaluate  seasonal effects on
ground-water quality.

The frequency of sample collection during
assessment  monitoring   activities  will
depend  on  site-specific   hydrogeologic
conditions and contaminant properties. The
frequency of sampling is intended to obtain
a data set that is statistically independent of
the previous set. Guidance to estimate this
minimum  time  to  obtain  independent
samples is provided in "Statistical Analysis
of Ground-water Monitoring Data at RCRA
Facilities   -   Interim   Final  Guidance"
(USEPA, 1989).

Water Level Measurements

The ground-water monitoring program must
include provisions for measuring  static
water level elevations in each well prior to
purging    the    well    for   sampling.
Measurements of ground-water elevations
are used for determining horizontal  and
vertical hydraulic gradients for estimation
of flow rates and direction.

Field   measurements  may   include  the
following:

•  Depth to standing water  from a surveyed
   datum on the top of the  well riser (static
   water level)

•  Total depth of well  from the top of the
   riser (to verify condition of well)

•  Thickness  of  immiscible layers,   if
   present.
Measurements of the static water level and
the depth to the well bottom can be made
with a wetted steel tape.  Electronic water
level measuring devices may also be used.
Accepted standard operating procedures call
for the static water level to be accurately
measured  to within 0.01  foot  (USEPA,
1992a). Water level measurements should
be made at all  monitoring wells and well
clusters in a time frame that avoids changes
that may occur as a result of barometric
pressure changes, significant  infiltration
events, or aquifer  pumping.   To prevent
possible cross contamination of wells, water
level   measurement  devices  must   be
decontaminated prior to use at each well.

The ground-water  monitoring program
should include provisions for  detecting
immiscible  fluids   (i.e.,  LNAPLs   or
DNAPLs).      LNAPLs  are  relatively
immiscible liquids that are less  dense than
water and that spread across the water table
surface. DNAPLs are relatively immiscible
liquids that are more dense than the ground
water  and  tend  to  migrate  vertically
downward in aquifers. The  detection of an
immiscible layer may require specialized
equipment and should be performed before
the well is  evacuated  for conventional
sampling.  The ground-water monitoring
program should specify how DNAPLs and
LNAPLs will  be detected.   The program
also should include a  contingency  plan
describing  procedures  for  sampling  and
analyzing these liquids.   Guidance  for
detecting the presence of immiscible layers
can be  found in USEPA (1992a).

Well Purging

Because the water standing in a well prior to
sampling   may  not  represent  in-situ
ground-water quality, stagnant water should
                                         256

-------
                     Ground-Water Monitoring and Corrective Action
be purged from the well and filter pack prior
to sampling.   The QAPjP should include
detailed,  step-by-step   procedures  for
purging wells, including the parameters that
will be  monitored during purging and the
equipment  that  will be  used  for well
purging.

Purging  should   be  accomplished  by
removing ground water from the well at low
flow rates using a pump. The use of bailers
to purge monitoring wells generally should
be avoided.   Research has shown that the
"plunger" effect  created  by  continually
raising and lowering the bailer into the well
can result  in continual  development or
overdevelopment of the well. Moreover, the
velocities at which ground water enters a
bailer   can   actually   correspond   to
unacceptably high purging rates (Puls and
Powell, 1992; Barcelona et al.,  1990).

The rate at which ground water is removed
from the well during purging ideally should
be approximately 0.2 to 0.3  L/min or less
(Puls and Powell, 1992; Puls et al., 1991;
Puls and Barcelona, 1989a;  Barcelona, et
al., 1990). Wells should be purged at rates
below  those  used to develop the well to
prevent further development of the well, to
prevent damage to the well, and to avoid
disturbing   accumulated   corrosion   or
reaction products in the well (Kearl et al.,
1992; Puls et al.,  1990; Puls and Barcelona,
1989a;   Puls  and   Barcelona,   1989b;
Barcelona,  1985b).   Wells also should be
purged at or  below their recovery  rate so
that migration of water in the formation
above the well screen does not occur. A low
purge rate also will reduce the possibility of
stripping VOCs from the water, and will
reduce the likelihood of mobilizing colloids
in the subsurface that are immobile under
natural flow conditions. The owner/operator
should
ensure  that  purging   does  not  cause
formation water to cascade down the sides
of the well screen.  At no time should a well
be purged to dryness if recharge causes the
formation water to cascade down the sides
of  the  screen,  as  this  will  cause  an
accelerated loss of volatiles.  This problem
should  be anticipated;  water  should  be
purged from the well at a rate that does not
cause recharge water  to be excessively
agitated.   Laboratory  experiments  have
shown that unless cascading is prevented, up
to 70 percent of the volatiles present could
be lost before sampling.

To  eliminate the need to dispose of large
volumes of purge water, and to  reduce the
amount  of time required for purging, wells
may be purged with the pump  intake just
above or just within the screened interval.
This procedure eliminates the need to purge
the  column of stagnant water located above
the well screen (Barcelona et al.,  1985b;
Robin   and  Gillham,  1987;  Barcelona,
1985b; Kearl et al., 1992). Purging the well
at the top of the well screen should ensure
that fresh water from  the  aquifer moves
through the well screen and upward within
the  screened interval. Pumping rates below
the recharge capability of the aquifer must
be maintained  if purging is performed with
the pump placed  at the top of the well
screen,  below the  stagnant water column
above the top  of the well screen (Kearl  et
al., 1992).  The Agency suggests that a
packer be placed above the screened interval
to ensure that "stagnant" casing water is not
drawn into the pump. The packer should be
kept inflated in the well until after ground-
water samples are collected.

In  certain situations,  purging  must  be
performed with the pump placed  at,  or
immediately below, the air/water interface.
                                         257

-------
                                      Subpart E
If a bailer must be used to sample the well,
the well  should be purged by placing the
pump  intake  immediately  below   the
air/water interface. This will ensure that all
of the water in the casing and filter pack is
purged, and it will minimize the possibility
of mixing and/or sampling stagnant water
when the bailer is lowered  down into the
well and  subsequently retrieved (Keeley and
Boateng, 1987). Similarly, purging should
be performed at the  air/water interface if
sampling is not performed immediately after
the well  is purged without removing the
pump. Pumping at the air/water interface
will  prevent the mixing of stagnant and
fresh water when  the pump used to purge
the well is removed and then lowered back
down into the well for the purpose of
sampling.

In cases where an LNAPL has been detected
in the monitoring  well, special procedures
should be used to purge the well.  These
procedures  are  described   in   USEPA
(1992a).

For most wells, the  Agency recommends
that purging continue until measurements of
turbidity, redox potential,  and dissolved
oxygen in in-line or downhole analyses of
ground   water have  stabilized  within
approximately  10%  over  at least  two
measurements (Puls and Powell, 1992; Puls
and Eychaner, 1990; Puls et al., 1990; Puls
and Barcelona, 1989a; Puls and Barcelona,
1989b; USEPA,  1991;  Barcelona et  al.,
1988b).  If a well is purged to dryness or is
purged such that full  recovery exceeds two
hours, the well should be sampled as soon as
a sufficient volume  of ground water has
entered the well to enable the collection of
the necessary ground-water samples.

All purging equipment that has been or will
be in contact with  ground water should be
decontaminated prior to use.  If the purged
water  or  the decontamination  water  is
contaminated  (e.g.,  based on  analytical
results),  the  water should be stored  in
appropriate   containers   until  analytical
results are available, at which time proper
arrangements  for  disposal  or treatment
should be made (i.e., contaminated purge
water may be a hazardous waste).

Field Analyses

Several constituents  or  parameters  that
owners or operators may choose to include
in a ground-water monitoring program may
be physically or chemically unstable and
should be tested after well purging and
before  the   collection  of  samples  for
laboratory analysis. Examples of unstable
parameters include pH, redox (oxidation-
reduction)  potential,  dissolved  oxygen,
temperature, and specific conductance.

Field analyses should not be performed on
samples designated for laboratory analysis.
Any field monitoring equipment or field-
test  kits  should  be  calibrated at  the
beginning of each  use, according to  the
manufacturers' specifications and consistent
with methods in SW-846 (USEPA, 1986b).

Sample Withdrawal and Collection

The equipment used to withdraw a ground-
water sample from a well must be selected
based on consideration of the parameters to
be analyzed in the sample. To ensure the
sample is representative of ground water in
the  formation, it  is  important to keep
physical  or  chemical  alterations of  the
sample to a  minimum.  USEPA (1992a)
provides an overview of the issues involved
in   selecting   ground-water   sampling
equipment,   and  a  summary   of   the
                                        258

-------
                     Ground-Water Monitoring and Corrective Action
application  and  limitations  of  various
sampling mechanisms.  Sampling materials
and  equipment should  be  selected  to
preserve  sample  integrity.    Sampling
equipment  should be constructed  of inert
material.   Sample  collection equipment
should  not  alter analyte  concentrations,
cause loss of analytes via sorption, or cause
gain of analytes via desorption, degradation,
or corrosion. Sampling equipment should
be designed such that Viton®, Tygon®,
silicone, or neoprene components do not
come into  contact with the ground-water
sample.    These  materials  have  been
demonstrated to cause sorptive losses of
contaminants  (Barcelona  et  al.,  1983;
Barcelona et al., 1985b; Barcelona et al.,
1988b; Barcelona et al., 1990). Barcelona
(1988b) suggests that sorption of volatile
organic    compounds    on    silicone,
polyethylene, and PVC  tubing may result in
gross    errors    when     determining
concentrations of trace organics in ground-
water   samples.     Barcelona   (1985b)
discourages the use  of  PVC sampling
equipment  when  sampling  for  organic
contaminants.   Fluorocarbon resin (e.g.,
Teflon®) or stainless  steel  sampling devices
which  can  be  easily  disassembled for
thorough decontamination are  widely used.
Dedicating sampling equipment  to  each
monitoring well will help prevent cross-
contamination  problems that could  arise
from improper decontamination procedures.

Sampling equipment should cause minimal
sample agitation and  should be selected to
reduce/eliminate sample contact with the
atmosphere   during   sample   transfer.
Sampling  equipment  should not  allow
volatilization or aeration of samples to the
extent   that analyte  concentrations  are
altered.
Bladder pumps are generally recognized as
the best overall sampling device for both
organic and inorganic constituents, although
other types  of  pumps   (e.g.,  low-rate
submersible centrifugal pumps, helical rotor
electric  submersible  pumps)  have been
found   suitable   in   some  applications.
Bailers,  although inexpensive and simple to
use, have been found to cause volatilization
of samples, mobilization of particulates in
wells and  imprecise results  (USEPA,
1992a).

The  following recommendations apply to
the use  and  operation of ground-water
sampling equipment:

 •   Check valves should be designed  and
     inspected  to  ensure that  fouling
     problems  do  not  reduce delivery
     capabilities  or result  in aeration  of
     samples.

 •   Sampling equipment should never be
     dropped into the well,  as this will
     cause  degassing  of the  water upon
     impact.

 •   Contents of the sampling device should
     be transferred to sample containers  in
     a controlled manner that will minimize
     sample agitation and aeration.

 •   Decontaminated sampling equipment
     should not  be allowed to  come into
     contact  with the ground  or  other
     contaminated  surfaces    prior   to
     insertion into the  well.

 •   Ground-water  samples   should  be
     collected as soon as possible after the
     well  is   purged.   Water  that  has
     remained in the well  casing for more
     than  about  2 hours has had  the
                                        259

-------
                                 Subpart E
opportunity to exchange gases with the
atmosphere and  to interact with the
well casing material (USEPA, 1991b).

The rate at which a well is sampled
should not exceed the rate at which the
well was purged. Low sampling rates,
approximately   0.1    L/min,   are
suggested.  Low  sampling rates will
help  to  ensure  that  particulates,
immobile  in the  subsurface  under
ambient conditions, are not entrained
in  the  sample  and  that  volatile
compounds are not stripped from the
sample (Puls and Barcelona, 1989b;
Barcelona, et al.,  1990;  Puls  et al.,
1991; Kearl  et  al.,  1992; USEPA,
1991b). Pumps should be operated at
rates  less than  0.1  L/min  when
collecting  samples for volatile organics
analysis.

Pump lines should be cleared at a rate
of 0.1 L/min  or less before collecting
samples for volatiles analysis so that
the samples collected will not be from
the period of time when the pump was
operating more rapidly.

Pumps  should  be  operated   in  a
continuous manner so that they do not
produce samples that are aerated in the
return tube or upon discharge.

When  sampling  wells  that  contain
LNAPLs,  a stilling  tube should  be
inserted in the  well.  Ground-water
samples should be collected from the
screened interval of the well below the
base of the tube.

Ground-water samples collected for
analysis for  organic constituents  or
parameters should not be filtered in the
field.
Once appropriate sampling equipment has
been selected and  operating  procedures
established, samples should be collected and
containerized   in   the  order  of   the
volatilization sensitivity of the parameter.
The preferred collection order for some of
the more common ground-water analytes is
depicted on the flow chart shown in Figure
5-4.

The  ground-water  monitoring  program
documentation  should  include   explicit
procedures    for    disassembly    and
decontamination of sampling equipment
before     each   use.         Improperly
decontaminated  equipment  can  affect
samples in several  ways.   For example,
residual contamination  from the  previous
well may remain on equipment, or improper
decontamination may not remove all of the
detergents   or  solvents   used   during
decontamination.     Specific  guidance
regarding decontamination of the sampling
equipment is available (USEPA  1992a). To
keep  sample  cross-contamination  to  a
minimum, sampling  should proceed from
upgradient  or background  locations  to
downgradient locations that would contain
higher concentrations of contaminants.

Sample Preservation and Handling

The procedures for preserving and handling
samples are nearly as important for ensuring
the integrity of the samples as the collection
device   itself.   Detailed procedures  for
sample preservation must be provided in the
Quality  Assurance Project  Plan  (QAPjP)
that is included in the sampling and analysis
program description.
                                    260

-------
        STEP
        PROCEDURE
                                                                          ESSENTIAL ELEMENTS
   Well Inspection


   Well Purging
     Hydrotogic Measurements

              I
Removal or Isolation of Stagnant Water
                                                                            Water Level Measurements
Representative Water
      Access
   Sample Collection'
   Field
   Determinations*
                              Determination of Well-Purging Parameters
                                        (pH, Eh, -n, Q )*
                                      Volatile Organics, TOX
                                      Dissolved Gases, TOC
                                         Large Volume
                                          Samples for
                                       Organic Compound
                                         Determinations
                                                   Verification of
                                                Representative Water
                                                  Sample Access
                                                Sample Collection by
                                               Appropriate Mechanism

                                              Minimal Sample Handling

                                                   Head-Space
                                                   Free Samples

                                                   Head Space
                                                   Free Samples

                                                 Minimal Aeration or
                                                  Depressurization
                                         Metal Samples
                                           Cyanides
                                              Adequate Rinsing against
                                                   Contamination
    Preservation
    Field Blanks
    Standards
        Assorted Sensitive
        Inorganic Species
              Nm"; Fe(lt)
                                        Major Cations and
                                            Anions
    Storage Transport
                                       (as needed for good
                                            QA/QC)
                                                 Minimal Air Contact,
                                                    Preservation

                                               Minimal Loss of Sample
                                               Integrity Prior to Analysis
 Denotes analytical determinations which should be made in the field.
'This is a suggested order tor sampling, not all parameters are required by Part 258.
                                              Figure 5-4
                                  Generalized Flow Diagram of
                                Ground-Water Sampling Steps
                                                  261

-------
                                      Subpart E
Sample Containers

To  avoid  altering  sample  quality,  the
samples  should be transferred  from the
sampling equipment directly into a prepared
container.  Proper sample containers for
each constituent or group of constituents are
identified in  SW-846 (USEPA, 1986b).
Samples  should never be composited in a
common  container in the  field  and then
split.  Sample containers should be cleaned
in a  manner  that is  appropriate for the
constituents to be analyzed.   Cleaning
procedures  are  provided   by   USEPA
(1986b).  Sample containers that have been
cleaned according to these  procedures can
be procured commercially.

Most vendors will provide a certification of
cleanliness.

Sample Preservation

During  ground-water  sampling,   every
attempt  should  be   made  to  minimize
changes in the chemistry of the samples. To
assist in maintaining the natural chemistry
of the samples, it is necessary to preserve
the sample.  The owner or operator should
refer  to SW-846 (USEPA,  1986b) for the
specific preservation  method and holding
times for each constituent to  be  analyzed.
Methods   of  sample  preservation  are
relatively limited and are intended to retard
chemical  reactions,   such  as  oxidation,
retard, biodegradation, and to reduce the
effects of sorption.  Preservation methods
are   generally  limited   to  pH  control,
refrigeration, and  protection from light.

Sample Storage and Shipment

The storage and transport of ground-water
samples must be performed in a manner that
maintains sample quality.  Samples should
be cooled to 4°C as soon as possible after
they are collected. These conditions should
be maintained until the samples are received
at the  laboratory.    Sample  containers
generally are packed  in picnic coolers or
special containers for shipment.

Polystyrene foam, vermiculite, and "bubble
pack" are frequently used to pack sample
containers  to  prevent breakage.  Ice is
placed in sealed plastic bags and added to
the cooler.  All related paperwork is sealed
in a plastic bag and taped to the inside top of
the cooler. The cooler top is then taped
shut. Custody seals should be placed across
the hinges and latches on the outside of the
cooler.

Transportation    arrangements    should
maintain proper storage  conditions  and
provide for effective sample  pickup  and
delivery to the laboratory.  Sampling plans
should be coordinated with the laboratory so
that  appropriate  sample  receipt, storage,
analysis, and custody arrangements can be
provided.

Most analyses must be performed within a
specified period (holding time) from sample
collection. Holding time refers to the period
that begins when the sample is collected
from the well and ends with its extraction or
analysis. Data from samples  not analyzed
within  the recommended  holding times
should  be considered  suspect.   Some
holding times for Appendix I constituents
are as short  as  7 days.   To provide the
laboratory with  operational flexibility in
meeting these  holding   times,  samples
usually  are shipped via overnight courier.
Laboratory capacity or operating hours may
influence sampling schedules. Coordination
with laboratory staff during
                                         262

-------
                     Ground-Water Monitoring and Corrective Action
planning  and   sampling   activities  is
important  in   maintaining  sample  and
analysis quality.

The   documentation  that  accompanies
samples during shipment to the laboratory
usually includes chain-of-custody (including
a listing of all sample containers), requested
analyses, and full identification of the origin
of samples (including contact names, phone
numbers,  and  addresses).   Copies of all
documents shipped with the samples should
be retained by the sampler.

Chain-of-Custody Record

To document sample possession from the
time of collection, a chain-of-custody record
should be filled out to  accompany  every
sample  shipment.   The  record should
contain the following types of information:

•  Sample number

•  Signature of collector

• Date and time of collection

• Media sampled (e.g., ground water)

•  Sample type (e.g., grab)

• Identification of sampling location/well

• Number of containers

• Parameters requested  for analysis

•  Signatures of persons  involved in the
  chain of possession

• Inclusive dates of possession with time
  in 24-hour notation
•  Internal   temperature   of   shipping
   container when samples were sealed into
   the container for shipping

•  Internal temperature of container when
   opened at the laboratory

•  Any remarks regarding potential hazards
   or other information the laboratory may
   need.

An  adequate chain-of-custody  program
allows for  tracing  the  possession and
handling of individual samples from  the
time of collection through completion of
laboratory  analysis.   A chain-of-custody
program should include:
   Sample     labels     to
   misidentification of samples
prevent
•  Sample custody seals to preserve the
   integrity of the samples from the time
   they are collected until they are opened
   in the laboratory

•  Field notes to record information about
   each sample collected during the ground-
   water monitoring program

•  Chain-of-custody  record to document
   sample  possession  from the time  of
   collection to analysis

•  Laboratory storage and analysis records,
   which are maintained at the laboratory
   and which record pertinent information
   about the sample.

Sample Labels

Each   sample's  identification  should  be
marked clearly in waterproof ink on the
sample container.  To aid  in labeling, the
                                        263

-------
                                      Subpart E
information should  be written  on  each
container prior to filling with a sample.  The
labels  should  be sufficiently durable  to
remain legible even when wet and should
contain the following information:

•  Sample identification number

•  Name and signature of the sampler

•  Date and time of collection

•  Sample location

•  Analyses requested.

Sample Custody Seal

Sample custody  seals should be placed  on
the shipping container and/or individual
sample bottle in a manner that will break the
seal if the container or sample is tampered
with.

Field Logbook

To provide an  account  of all activities
involved in sample collection, all sampling
activities, measurements, and  observations
should  be  noted in  a field  log.   The
information   should   include   visual
appearance (e.g., color, turbidity, degassing,
surface film),  odor (type,  strength), and
field measurements and calibration results.
Ambient conditions (temperature, humidity,
wind, precipitation) and well  purging and
sampling activities should also be recorded
as an  aid  in evaluating sample  analysis
results.

The  field logbook  should document the
following:

 •  Well identification
Well depth

Static   water   level   depth   and
measurement technique

Presence and thickness of immiscible
layers and the detection method

Well yield (high or  low)  and well
recovery after purging (slow, fast)

Well purging procedure and equipment

Purge volume and pumping rate

Time well purged

Collection  method  for  immiscible
layers

Sample  withdrawal  procedure  and
equipment

Date and time of sample collection

Results of field analysis

Well sampling sequence

Types  of sample  bottles used  and
sample identification numbers

Preservatives used

Parameters requested for analysis

Field observations of sampling event

Name of collector

Weather  conditions,  including  air
temperature
                                        264

-------
                     Ground-Water Monitoring and Corrective Action
 •   Internal temperature  of  field  and
     shipping containers.

Sample Analysis Request Sheet

A  sample  analysis request sheet should
accompany the  sample(s) to the laboratory
and   clearly   identify  which   sample
containers  have been designated for each
requested parameter and the preservation
methods used.  The record  should include
the following types of information:

•  Name of person receiving the sample

•  Laboratory sample number (if different
   from field number)

•  Date of sample receipt

•  Analyses to be  performed  (including
   desired analytical method)

•  Information  that may be useful to the
   laboratory (e.g., type and quantity of
   preservatives added, unusual  conditions).

Laboratory Records

Once the sample has been  received in the
laboratory, the sample custodian and/or
laboratory   personnel   should   clearly
document the  processing  steps  that are
applied  to  the  sample.    All   sample
preparation    (e.g.,    extraction)    and
determinative steps  should be identified in
the laboratory  records.  Deviations  from
established methods or standard operating
procedures  (SOPs),  such  as the  use of
specific  reagents (e.g.,  solvents,  acids),
temperatures, reaction times, and instrument
settings, should be noted.  The results of the
analyses of all quality  control  samples
should  be identified for  each batch of
ground-water  samples  analyzed.    The
laboratory logbook should include the time,
date, and name of the person who performed
each processing step.

Analytical Procedures

The  requirements  of 40  CFR Part 258
include   detection    and    assessment
monitoring  activities.   Under detection
monitoring,  the  constituents  listed  in  40
CFR  Part 258, Appendix  I are to  be
analyzed for.  This  list includes volatile
organic compounds (VOCs)  and  selected
inorganic  constituents.     No   specific
analytical  methods   are   cited  in  the
regulations,  but there is a requirement (40
CFR  §258.53(h)(5))  that  any  practical
quantitation  limit (PQL) used in subsequent
statistical   analysis    "be    the   lowest
concentration  level that  can be  reliably
achieved within specified limits of precision
and  accuracy during routine laboratory
operating conditions that are available to the
facility." Suggested test methods are listed
in Appendix II of Part 258 for informational
purposes  only.     Method  8240   (gas
chromatography with packed column; mass
spectrometry) and  Method  8260  (gas
chromatography  with  capillary  column;
mass  spectrometry)  are typical  methods
used  for all  Appendix  I  VOCs.   The
inorganic analyses  can be performed using
inductively coupled plasma atomic emission
spectroscopy (ICP) Method 6010.  These
methods,  as  well  as  other  methods
appropriate to these analyses, are presented
in Tests  Methods for Evaluating  Solid
Waste,    Physical/Chemical   Methods,
SW-846 (USEPA, 1986), and are routinely
performed by numerous analytical testing
laboratories.   These methods  typically
provide PQLs in the 1 to 50 |ig/L range.
The  ground-water  monitoring plan  must
specify the analytical method to be used.
                                         265

-------
                                      Subpart E
Evaluation and documentation of analytical
performance  requires that quality  control
samples be collected and analyzed along
with the ground-water monitoring samples.
Chapter   One    of  SW-846   (Quality
Assurance) describes the types of quality
control samples  necessary, as well as the
frequency at which they must be collected
and  analyzed.   In  general,  these  quality
control samples  may include trip  blanks,
equipment rinsate samples, field duplicates,
method    blanks,   matrix   spikes   and
duplicates, and laboratory control samples.

Other  mechanisms,   including   sample
holding times, surrogate constituents, and
standard additions,  are also used to control
and   document   data  quality.      The
specification  of  and adherence to  sample
holding  times  minimizes  the   sample
degradation  that   occurs   over   time.
Evaluating  the   recovery   of   surrogate
constituents spiked into organic  samples
allows the analyst and data user to monitor
the efficiency of sample extraction and
analysis.  The method of standard additions
is  used to eliminate the effects of matrix
interferences  in inorganic analyses.

Quality Assurance/Quality  Control

One of the fundamental responsibilities of
the owner or operator is to  establish  a
continuing program to ensure the reliability
and   validity of  field  and  analytical
laboratory data  gathered  as part of the
overall ground-water monitoring program.
The  owner or  operator must explicitly
describe the QA/QC program that  will be
used in  the   laboratory.  Most  owners or
operators will use commercial laboratories
to   conduct  analyses  of  ground-water
samples.   In these cases, the owner or
operator is responsible for ensuring that the
laboratory  of  choice   is  exercising   an
appropriate QA/QC program.

The owner or operator should provide for
the use  of  standards, laboratory  blanks,
duplicates,   and   spiked   samples  for
calibration and identification of potential
matrix interferences,  especially for metal
determinants.   Refer to Chapter  One of
SW-846 for  guidance.   The  owner or
operator  should  use  adequate  statistical
procedures (e.g., QC charts) to monitor and
document performance and to implement an
effective  program  to  resolve   testing
problems (e.g., instrument maintenance,
operator training). Data from QC samples
(e.g., blanks, spiked samples) should be
used as a measure of performance or as an
indicator  of potential sources of cross-
contamination, but  should not be used by
the laboratory to alter or correct analytical
data.   All laboratory QC data should be
submitted with the ground-water monitoring
sample results.

Field Quality Assurance/Quality Control

To verify the precision of field  sampling
procedures, field QC samples, such as trip
blanks,  equipment blanks, and duplicates,
should be collected.  Additional volumes of
sample   also  should  be  collected  for
laboratory QC samples.

All field QC samples should be prepared
exactly  as regular  investigation  samples
with regard to sample volume, containers,
and preservation. The concentrations of any
contaminants found in blank samples should
not be  used  to correct the ground-water
data.  The contaminant  concentrations in
blanks should be documented, and if the
concentrations are more than an  order of
magnitude greater  than  the field sample
                                         266

-------
                     Ground-Water Monitoring and Corrective Action
results, the owner/operator should resample
the ground  water.   The owner/operator
should  prepare  the   QC   samples  as
recommended in Chapter One of SW-846
and  at  the  frequency  recommended  by
Chapter One of SW-846 and should analyze
them  for  all of the required monitoring
parameters.  Other QA/QC practices, such
as   sampling   equipment   calibration,
equipment decontamination procedures, and
chain-of-custody procedures, are discussed
in other sections of this chapter and should
be described in the owner/operator's QAPjP.

Validation

The analytical data report provided by the
laboratory will present all data measured by
the laboratory but will not adjust those data
for field  or  laboratory  quality  control
indicators.  This means  that just because
data have been  reported,  they are not
necessarily an accurate representation of the
quality of the ground water.  For example,
acetone and methylene  chloride are  often
used  in  laboratories   as   cleaning  and
extraction solvents and, consequently, are
often laboratory contaminants, transmitted
through  the  ambient  air  into  samples.
Method blanks are analyzed to evaluate the
extent   of   laboratory   contamination.
Constituents found as contaminants in the
method blanks are "flagged" in the sample
data.  The sample data are  not, however,
adjusted for the contaminant concentration.

Other kinds  of samples are  analyzed to
assess other data quality indicators.  Trip
blanks are used to assess contamination by
volatile organic constituents during sample
shipment and storage.  Matrix spike/matrix
spike duplicate  sample pairs  are used to
evaluate analytical bias and precision.
Equipment  rinsate samples  are  used to
assess the efficacy of sampling equipment
decontamination  procedures.   The  data
validation process uses the results from all
of these QC samples to determine if the
reported analytical data accurately describe
the samples.  All reported data  must be
evaluated — a reported value of "non-detect"
is a quantitative report just like a numerical
value and must be validated.

The  data validation process  must  also
consider the presence and quality of other
kinds of data used to ensure data quality
(e.g., calibration frequency and descriptors,
matrix specific detection limits). All of the
criteria for data quality are described in the
quality assurance project plan (QAPjP) or
sampling and analysis plan (SAP). These
documents may reference criteria from some
other source,  (e.g., the USEPA Contract
Laboratory  Program).  The performance
criteria must be correctly specified and must
be used for data validation. It is a waste of
time  and money  to  evaluate data against
standards other than those used to generate
them.  Several documents are available to
assist the reviewer in validation of data by
different criteria (i.e., Chapter One of Test
Methods for Evaluating  Solid Waste,
Physical/Chemical Methods, USEPA CLP
Functional   Guidelines  for  Evaluating
Organics Analyses, USEPA CLP Functional
Guidelines for Evaluating Pesticides/PCBs
Analyses, etc.).

In addition  to specific  data that describe
data quality,  the validator  may  consider
other information that may have an impact
on  the end-use   of the  data,  such as
background    concentrations   of   the
constituent  in the environment.   In any
event, the  QAPjP or  SAP also should
describe the validation procedures that will
be used. The result of
                                         267

-------
                                     Subpart E
this validation should be the classification
of data as acceptable or unacceptable for the
purposes of the project. In some cases, data
may be further qualified, based either on
insufficient data or marginal performance
(i.e.,  qualitative uses   only,  estimated
concentration, etc.).

Documentation

The  ground-water  monitoring  program
required by §258.50 through §258.55 relies
on    documentation   to    demonstrate
compliance.  The operating record of the
MSWLF  should  include   a  complete
description of the  program  as well   as
periodic implementation reports.

At a minimum, the following aspects of the
ground-water monitoring program should be
described  or  included in  the  operating
record:

•  The  Sampling and Analysis plan that
   details  sample  parameters,  sampling
   frequency,    sample     collection,
   preservation, and analytical methods to
   be used, shipping procedures, and chain-
   of-custody procedures;

•  The  Quality  Assurance  Project Plan
   (QAPjP) and Data Quality Objectives
   (DQOs);

•  The locations of monitoring wells;

•  The design, installation, development,
   and decommission of monitoring wells,
   piezometers,  and  other  measurement,
   sampling, and analytical devices;

•  Site hydrogeology;
   Statistical methods to be used to evaluate
   ground-water monitoring   data   and
   demonstrate  compliance   with   the
   performance standard;

   Approved demonstration that monitoring
   requirements    are    suspended    (if
   applicable);

   Boring logs;

   Piezometer and well construction logs
   for the ground-water monitoring system.
5.9 STATISTICAL ANALYSIS
    40 CFR §258.53 (g)-(i)

5.9.1 Statement of Regulation

 (g) The owner or operator must specify
in  the  operating  record  one  of the
following statistical methods to be used in
evaluating ground-water monitoring data
for each  hazardous constituent.   The
statistical test chosen shall be conducted
separately for each hazardous constituent
in each well.

 (1) A parametric analysis of variance
(ANOVA)   followed    by    multiple
comparisons  procedures  to   identify
statistically   significant   evidence  of
contamination. The method must include
estimation and testing of the  contrasts
between each compliance well's mean and
the background  mean levels  for  each
constituent.

 (2) An analysis  of variance (ANOVA)
based  on ranks  followed by  multiple
comparisons  procedures  to   identify
statistically   significant   evidence  of
contamination. The method must include
                                        268

-------
                    Ground-Water Monitoring and Corrective Action
estimation and testing of the contrasts
between each compliance well's median
and  the background  median levels for
each constituent.

 (3) A tolerance  or prediction interval
procedure in which an interval for each
constituent  is   established  from  the
distribution of the background data, and
the level  of each constituent  in each
compliance well is compared to the upper
tolerance or prediction limit.

 (4) A control chart approach that gives
control  limits   for   each  constituent.

 (5) Another statistical test method that
meets  the  performance  standards  of
§258.53(h).  The owner or operator must
place a justification for this alternative in
the operating record and notify the State
Director of the use of this alternative test.
The justification must demonstrate that
the  alternative   method   meets  the
performance standards  of §258.53(h).

 (h) Any statistical method chosen under
§258.53(g)  shall   comply   with  the
following  performance  standards,  as
appropriate:

 (1) The  statistical   method  used  to
evaluate ground-water monitoring data
shall be appropriate for the distribution
of chemical parameters or  hazardous
constituents. If the distribution  of the
chemical   parameters   or   hazardous
constituents is shown by the owner or
operator to be inappropriate for a normal
theory test, then the data  should  be
transformed or a distribution-free theory
test should be used. If the  distributions
for the constituents differ, more than one
statistical  method may be needed.
 (2) If an  individual well  comparison
procedure   is  used  to  compare  an
individual  compliance well constituent
concentration    with     background
constituent concentrations or a ground-
water protection standard, the test shall
be done at a Type I error level of no less
than 0.01 for each  testing period.  If a
multiple comparisons procedure is used,
the Type I experiment wise error  rate for
each testing period shall be no  less than
0.05; however, the Type I error of no less
than 0.01 for individual well comparisons
must be maintained.  This performance
standard does not apply  to  tolerance
intervals, prediction intervals, or control
charts.

 (3) If a control chart approach is used to
evaluate ground-water monitoring data,
the specific type of control chart and its
associated parameter values shall  be
protective  of human health and the
environment.  The  parameters shall be
determined after considering the number
of samples in the background data base,
the data distribution, and the range of the
concentration values for each constituent
of concern.

 (4) If  a   tolerance  interval   or  a
predictional interval is used to evaluate
ground-water monitoring data, the levels
of confidence and, for tolerance intervals,
the percentage of the population that the
interval must contain, shall be protective
of human health and the environment.
These parameters shall be  determined
after considering the number of samples
in the background data base, the data
distribution,   and  the  range  of the
concentration values for each constituent
of concern.
                                       269

-------
                                     Subpart E
 (5) The statistical method shall account
for data below the limit of detection with
one or more statistical procedures that
are protective of human  health and the
environment.  Any practical quantitation
limit (PQL) that is used in the statistical
method shall be the lowest concentration
level that can be reliably achieved within
specified limits of precision and accuracy
during   routine  laboratory  operating
conditions  that  are  available  to the
facility.

 (6) If necessary,  the  statistical method
shall include  procedures to  control or
correct  for   seasonal   and   spatial
variability as well  as temporal correlation
in the data.

 (i)  The   owner   or  operator   must
determine  whether or  not there is a
statistically  significant   increase  over
background values for each parameter or
constituent required  in  the  particular
ground-water monitoring program that
applies  to   the   MSWLF   unit,  as
determined   under   §§258.54(a)  or
258.55(a) of this part.

 (1) In     determining    whether   a
statistically  significant  increase  has
occurred,  the owner or  operator must
compare the  ground-water  quality of
each parameter or  constituent at each
monitoring well designated pursuant to
§258.51(a)(2) to the background value of
that  constituent,   according  to  the
statistical  procedures and performance
standards specified under paragraphs (g)
and (h) of this section.

 (2) Within a reasonable period of time
after completing sampling and analysis,
the  owner or operator must determine
whether  there has been a  statistically
significant increase over background at
each monitoring well.

5.9.2  Applicability

The  statistical  analysis requirements  are
applicable to all existing units, new units,
and lateral expansions of existing units for
which ground-water monitoring is required.
The use of statistical procedures to evaluate
monitoring  data  shall  be  used  for  the
duration  of the  monitoring  program,
including the post-closure care period.

The owner or operator must indicate in the
operating record the statistical method that
will be used in the analysis of ground-water
monitoring results. The data objectives of
the monitoring, in terms of the number of
samples collected  and  the frequency  of
collection,  must be  consistent with  the
statistical method selected.

Several options  for analysis  of ground-water
data  are provided in the criteria.  Other
methods may be used if they can be shown
to meet the  performance standards.  The
approved methods include both parametric
and nonparametric procedures, which differ
primarily  in constraints placed  by  the
statistical distribution of the data.  Control
chart,  tolerance interval,  and prediction
interval approaches also may be applied.

The owner or operator must conduct  the
statistical comparisons between upgradient
and downgradient wells after completion of
each sampling event and receipt of validated
data.    The  statistical procedure  must
conform to the  performance standard of a
Type I error level of no less than 0.01 for
inter-well  comparisons.   Control chart,
tolerance interval, and  prediction  interval
approaches must incorporate decision values
                                        270

-------
                     Ground-Water Monitoring and Corrective Action
that are protective of human health and the
environment.  Generally,  this is meant to
include a significance level of a least 0.05.
Procedures to treat data below analytical
method detection levels  and seasonality
effects  must  be part  of the statistical
analysis.

5.9.3  Technical Considerations

The  MSWLF rule requires  facilities  to
evaluate ground-water monitoring  data
using  a statistical  method  provided  in
§258.53(g)  that  meets the  performance
standard of §258.53(h).  Section 258.53(g)
contains a provision allowing for the use of
an alternative statistical method as long as
the performance  standards of §258.53(h) are
met.

The requirements of §258.53(g) specify that
one of five possible statistical methods be
used    for    evaluating    ground-water
monitoring data. One  method should be
specified for each constituent. Although
different methods may be selected for each
constituent at new facilities, use of a method
must be substantiated by demonstrating that
the distribution  of data  obtained on that
constituent is appropriate for  that method
(§258.53(h)).    Selection  of a  specific
method is described in Statistical Analysis
of Ground- Water Monitoring Data at RCRA
Facilities  -  Interim  Final  Guidance"
(USEPA, 1989)  and in Statistical Analysis
of Ground- Water Monitoring Data at RCRA
Facilities - Addendum to Interim Final
Guidance (USEPA,   1992b).   EPA  also
offers     software,     entitled     User
Documentation   of   the   Ground-Water
Information Tracking  System (GRITS) with
Statistical Analysis Capability, GRITSTAT
Version 4.2.   In addition to the statistical
guidance provided by EPA, the following
references may be
useful for selecting other methods (Dixon
and   Massey,   1969;   Gibbons,  1976;
Aitchison and Brown, 1969; and Gilbert,
1987). The statistical methods that may be
used in evaluating ground-water monitoring
data include the following:

•  Parametric   analysis   of   variance
   (ANOVA) with multiple comparisons

•  Rank-based  (nonparametric) ANOVA
   with multiple comparisons

•  Tolerance interval or prediction interval

•  Control chart

•  An alternative statistical method (e.g.,
   CABF t-test or confidence intervals).

If an alternative method is used, then the
State Director must be  notified,  and  a
justification for its use must be placed in the
operating record.

The statistical analysis methods chosen must
meet performance standards specified under
§258.53(h), which include the following:

1) The method must be appropriate  for the
   observed distribution of the data

2) Individual   well    comparisons   to
   background ground-water quality  or  a
   ground-water protection  standard shall
   be done at a Type I error level of no less
   than 0.01 or, if the multiple comparisons
   procedure is used, the experiment-wise
   error rate for each testing period shall be
   no less than 0.05

3) If a control chart is used, the type of
   chart and associated  parameter  values
                                         271

-------
                                      Subpart E
   shall be protective of human health and
   the environment

4) The level of confidence and percentage
   of the population contained in an interval
   shall be protective of human health and
   the environment

5) The method must account for data below
   the limit of detection (less than the PQL)
   in a manner that is protective of human
   health and the environment

6) The method must account for seasonal
   and  spatial  variability and  temporal
   correlation of the data, if necessary.

These statistical analysis methods shall be
used  to  determine whether a significant
increase   over  background   values  has
occurred.    Monitoring  data  must  be
statistically analyzed after validated results
from each sampling and analysis event are
received.

The   statistical   performance  standards
provide a means to limit the possibility of
making  false   conclusions  from   the
monitoring data.  The specified error level
of 0.01 for individual well  comparisons for
probability of Type I error (indication of
contamination when it is not present or false
positive) essentially means that the analysis
is predicting with  99-percent confidence
that no significant increase in contaminant
levels is evident when in fact no increase is
present. Non-detect results must be treated
in an appropriate manner or their influence
on the statistical method may invalidate the
statistical conclusion.  Non-detect results
are discussed in greater detail later in this
section.
Multiple Well Comparisons

If more than two wells  (background and
downgradient combined) are screened in the
same stratigraphic unit, then the appropriate
statistical comparison method is a multiple
well  comparison  using  the  ANOVA
procedure.     The   parametric  ANOVA
procedure assumes that the data from each
well group come from the same type (e.g.,
Normal)  of distribution  with  possibly
different  mean  concentrations.     The
ANOVA tests for a difference in means.  If
there are multiple background wells, one
should consider the possibility of trying to
pool these background data into one group.
Such an increase in sample size often allows
for more accurate statistical comparisons,
primarily  because better  information  is
known about the background concentrations
as a whole.  Downgradient wells should not
be  pooled,   as  stated  in  the regulations.
Ground-water  monitoring  data  tend to
follow a log normal  distribution (USEPA,
1989), and  usually need to be  transformed
prior to  applying a parametric ANOVA
procedure.      By   conducting   a   log
transformation, ground-water monitoring
data will generally be  converted to a normal
distribution. By applying a Shapiro-Wilk
test, probability plots, or other normality
tests on the residuals (errors) from  the
ANOVA procedure,  the normality of the
transformed data can be  determined.  In
addition, data variance for each well in the
comparison   must   be   approximately
equivalent;  this condition can be checked
using Levene's or Bartlett's test. These tests
are  provided  in  USEPA (1992b)  and
USEPA (1989).

If the transformed data do not conform to
the normality assumption, a nonparametric
ANOVA procedure  may be  used.   The
                                         272

-------
                     Ground-Water Monitoring and Corrective Action
nonparametric statistical procedures do not
depend  as  much  on the  mathematical
properties of a specified distribution.  The
nonparametric equivalent to the parametric
ANOVA is the Kruskal-Wallis test, which
analyzes variability of the average ranks of
the  data  instead  of the  measurements
themselves.

If the data display  seasonality (regular,
periodic, and time-dependent  increases or
decreases in parameter values), a two-way
ANOVA procedure should be  used. If the
seasonality can  be corrected,  a one-way
ANOVA procedure may still be appropriate.
Methods to treat seasonality are described in
USEPA(1989).

ANOVA procedures attempt to determine
whether different wells have significantly
different   average   concentrations    of
constituents.  If a difference is  indicated, the
ANOVA test is followed  by  a multiple
comparisons procedure to investigate which
specific wells are  different among those
tested.    The  overall  experiment-wise
significance level of the ANOVA must be
kept  to a  minimum of 0.05, while  the
minimum   significance  level  of  each
individual comparison must be set  at 0.01.
USEPA  (1992b)  provides   alternative
methods that can be used when the  number
of individual contrasts to be tested is very
high.

Tolerance and Prediction Intervals

Two types of statistical intervals are often
constructed from data: tolerance intervals
and prediction intervals. A comprehensive
discussion of these intervals is provided in
USEPA 1992b.  Though often confused, the
interpretations and uses of these intervals
are quite distinct.  A tolerance interval is
designed to contain a designated proportion
of the population (e.g., 95  percent of all
possible sample measurements).  Because
the interval is constructed from sample data,
it also is a random interval. And because of
sampling fluctuations, a tolerance interval
can contain the specified proportion of the
population only with  a certain  confidence
level.

Tolerance  intervals are  very  useful  for
ground-water data analysis because in many
situations one wants to ensure that at most a
small  fraction  of the compliance well
sample  measurements  exceed  a  specific
concentration level (chosen to be protective
of human health and the environment).

Prediction  intervals  are constructed  to
contain the next sample value(s) from  a
population or distribution with  a  specified
probability.   That is, after sampling  a
background  well  for some  time  and
measuring the concentration of an analyte,
the data can be used to construct an interval
that will contain the next analyte sample or
samples (assuming the distribution has not
changed).   Therefore, a prediction interval
will  contain  a future value or values with
specified probability.   Prediction intervals
can  also  be  constructed to contain  the
average of several future observations.

In summary, a tolerance interval contains a
proportion  of  the  population,  and   a
prediction  interval contains one or  more
future observations. Each has a probability
statement   or   "confidence  coefficient"
associated  with it.  It should be noted that
these intervals assume that the sample data
used to construct the intervals are normally
distributed.
                                         273

-------
                                     Subpart E
Individual Well Comparisons

When  only  two  wells  (e.g.,  a  single
background and a single compliance point
well) are  being   compared,  owners or
operators should not perform the parametric
or nonparametric  ANOVA.   Instead, a
parametric  t-test,  such   as   Cochran's
Approximation   to  the   Behrens-Fisher
Students'  t-test,  or a nonparametric test
should be performed.   When a  single
compliance well group is being compared to
background data and a nonparametric test is
needed, the Wilcoxin Rank-Sum test should
be performed. These tests are  discussed in
more detail in standard statistical references
andinUSEPA(1992b).

Intra-Well Comparisons

Intra-well comparisons, where data of one
well  are evaluated over time, are useful in
evaluating trends in individual wells and for
identifying seasonal effects in the data. The
intra-well comparison methods do  not
compare  background  data to compliance
data.  Where some existing facilities may
not have  valid background data, however,
intra-well comparisons may represent the
only valid comparison available.  In the
absence of a true background well, several
monitoring events  may  be  required to
determine trends and seasonal fluctuations
in ground-water quality.

Control charts may be used for intra-well
comparisons but are only  appropriate for
uncontaminated  wells.    If  a  well  is
intercepting a release, then it is  already in
an "out-of-control" state, which violates the
principal   assumption  underlying  control
chart procedures.  Time series  analysis (i.e.,
plotting  concentrations  over  time)  is
extremely useful for identifying trends in
monitoring data. Such data may be adjusted
for seasonal effects to aid in assessing the
degree of change over time.  Guidance for
and limitations of intra-well comparison
techniques are provided in USEPA (1989)
andUSEPA(1992b).

Treatment of Non-Detects

The treatment of data below the detection
limit of the analytical method (non-detects)
used depends on the number or percentage
of non-detects and the statistical method
employed. Guidance on how to treat non-
detects is provided in USEPA (1992b).

5.10  DETECTION MONITORING
      PROGRAM
      40 CFR §258.54

5.10.1  Statement of Regulation

 (a) Detection monitoring is required at
MSWLF  units   at   all   ground-water
monitoring    wells    defined   under
§§258.51(a)(l) and (a)(2) of this part. At
a  minimum, a  detection monitoring
program must include the monitoring for
the constituents listed in Appendix I  of
this part.

1) The Director  of an approved  State
   may delete any  of  the Appendix I
   monitoring parameters for a MSWLF
   unit if  it can  be shown  that the
   removed   constituents   are   not
   reasonably  expected  to  be in or
   derived  from the waste contained  in
   the  unit.

2) The Director  of an approved  State
   may establish an alternative list  of
   inorganic indicator parameters  for a
   MSWLF unit, in lieu of some or  all  of
                                        274

-------
                    Ground-Water Monitoring and Corrective Action
   the heavy metals (constituents 1-15 in
   Appendix   I),   if  the  alternative
   parameters   provide   a   reliable
   indication of inorganic releases from
   the MSWLF unit to the ground water.
   In     determining     alternative
   parameters,  the   Director   shall
   consider the following factors:

(i) The    types,     quantities,    and
   concentrations   of  constituents  in
   wastes managed at the MSWLF unit;

(ii) The   mobility,   stability,    and
    persistence of waste constituents or
    their  reaction  products  in  the
    unsaturated   zone   beneath  the
    MSWLF unit;

(iii) The  detectability   of   indicator
    parameters, waste constituents, and
    reaction  products  in the ground
    water; and

(iv) The concentration or  values  and
    coefficients    of   variation   of
    monitoring     parameters     or
    constituents   in  the  background
    ground-water.

 (b) The monitoring  frequency for all
constituents listed  in Appendix I, or the
alternative list approved in accordance
with paragraph (a)(2), shall be at least
semiannual during the active life of the
facility (including closure) and the post-
closure  period.  A minimum of four
independent  samples  from  each  well
(background and downgradient) must be
collected and analyzed for the Appendix
I  constituents, or  the  alternative list
approved in accordance with paragraph
(a)(2),   during  the  first  semiannual
sampling event. At least one sample from
each well(background and downgradient)
must  be collected  and analyzed during
subsequent semiannual sampling events.
The Director of an approved State may
specify   an   appropriate  alternative
frequency  for  repeated sampling and
analysis for Appendix I constituents, or
the   alternative   list   approved  in
accordance with paragraph (a)(2), during
the active life (including closure) and the
post-closure care period. The alternative
frequency   during   the   active  life
(including closure) shall be no less than
annual. The alternative frequency shall
be based on consideration of the following
factors:

1) Lithology   of   the   aquifer   and
   unsaturated zone;

2) Hydraulic conductivity of the aquifer
   and unsaturated zone;

3) Ground-water flow rates;

4) Minimum     distance     between
   upgradient edge of the MSWLF unit
   and  downgradient monitoring well
   screen (minimum distance of travel);
   and

5) Resource value  of the aquifer.

 (c) If the owner or operator determines,
pursuant to §258.53(g) of this part, that
there  is  a statistically significant increase
over background for one or more of the
constituents listed in Appendix I  or the
alternative list approved in accordance
with paragraph (a)(2), at any monitoring
well at the boundary specified  under
§258.51(a)(2), the owner or operator:

 (1) Must, within 14 days of this finding,
place a notice in  the operating record
indicating which constituents have shown
statistically significant changes from
                                       275

-------
                                      Subpart E
background levels, and notify the State
Director that this notice was placed in the
operating record; and

 (2) Must   establish   an   assessment
monitoring   program   meeting   the
requirements  of §258.55 of  this part
within 90 days, except as provided for in
paragraph (3) below.

 (3) The     owner/operator     may
demonstrate that a source other  than a
MSWLF unit  caused the contamination
or  that   the  statistically   significant
increase resulted from error in sampling,
analysis, statistical evaluation, or  natural
variation in ground-water  quality.   A
report documenting this  demonstration
must be certified by a qualified ground-
water   scientist  or  approved by  the
Director of an approved State and  be
placed  in  the  operating record.  If a
successful  demonstration is made and
documented, the owner or operator may
continue   detection   monitoring   as
specified in this section. If after 90 days,
a successful demonstration is not made,
the owner or  operator must initiate  an
assessment monitoring   program   as
required in §258.55.

5.10.2  Applicability

Except for the small landfill exemption and
the no migration demonstration, detection
monitoring is required at existing MSWLF
units, lateral expansions of units, and new
MSWLF units.  Monitoring must occur at
least semiannually at both background wells
and downgradient well locations.   The
Director of an approved State may  specify
an   alternative    sampling   frequency.
Monitoring  parameters must include  all
Appendix  I   constituents   unless   an
alternative
list has been established by the Director of
an approved State.

During  the  first semiannual  monitoring
event, the owner or operator must collect at
least   four   independent  ground-water
samples from each  well  and analyze the
samples for all constituents in the Appendix
I  or  alternative  list.  Each  subsequent
semiannual  event  must  include,  at  a
minimum, the collection and analysis of one
sample  from all  wells.  The  monitoring
requirement continues throughout the active
life of the landfill and the  post-closure care
period.

If an owner or operator determines that a
statistically   significant   increase   over
background has occurred for one or more
Appendix I constituents (or constituents on
an alternative list), a notice must be placed
in the facility operating record (see Table 5-
2). The owner or operator must notify the
State Director within 14 days of the finding.
Within 90 days, the owner or operator must
establish an assessment monitoring program
conforming to the requirements of §258.55.

If  evidence   exists that a  statistically
significant  increase  is  due  to  factors
unrelated to the unit, the owner or operator
may make a demonstration to this effect to
the Director of an approved State or place a
certified demonstration in the  operating
record.   The potential  reasons  for an
apparent statistical increase may include:

•  A  contaminant source other  than the
   landfill unit

•  A  natural  variation  in ground-water
   quality

•  An analytical  error
                                        276

-------
                     Ground-Water Monitoring and Corrective Action
•  A statistical error

•  A sampling error.

The demonstration that one of these reasons
is responsible for the statistically significant
increase over background must be certified
by a  qualified ground-water  scientist or
approved by the Director of an approved
State. If a successful demonstration is made
and documented, the owner or operator may
continue detection monitoring.

If a successful demonstration is not made
within 90 days, the owner or operator must
initiate an assessment monitoring program.
A flow chart  for  a detection monitoring
program in a State whose program has not
been approved by EPA is provided in Figure
5-5.

5.10.3 Technical Considerations

If there is a statistically significant increase
over   background    during    detection
monitoring  for one or more constituents
listed in Appendix I of Part 258 (or an
alternative list of parameters in an approved
State), the owner or operator is required to
begin   assessment  monitoring.     The
requirement   to   conduct   assessment
monitoring  will  not change, even  if the
Director of an approved State  allows the
monitoring  of geochemical  parameters in
lieu of some or all of the metals listed in
Appendix  I.  If  an owner or  operator
suspects that  a  statistically  significant
increase  in a geochemical  parameter is
caused by natural variation in ground-water
quality or a source other than a  MSWLF
unit, a demonstration to this  effect must be
documented in a report to avoid proceeding
to assessment monitoring.
Independent Sampling for Background

The ground-water monitoring requirements
specify  that four independent samples be
collected  from  each  well  to  establish
background during the  first  semiannual
monitoring event.  This is because almost all
statistical procedures  are  based  on the
assumption that samples are independent of
each other.  In other words, independent
samples more  accurately  reflect the true
range of natural variability  in the ground
water,  and  statistical  analyses based  on
independent samples  are more  accurate.
Replicate samples, whether field replicates
or   lab   splits,   are   not   statistically
independent measurements.

It  may  be   necessary  to   gather  the
independent samples over a range of time
sufficient  to   account   for   seasonal
differences.  If seasonal differences are not
taken into account,  the  chance  for false
positives  increases (monitoring   results
indicate a release, when a release has not
occurred).  The  sampling interval chosen
must ensure that sampling is being done on
different volumes of ground  water.  To
determine the appropriate interval between
sample  collection  events that will ensure
independence, the owner or operator can
determine  the site's  effective  porosity,
hydraulic  conductivity,  and  hydraulic
gradient  and  use this  information  to
calculate ground-water velocity  (USEPA,
1989).  Knowing the velocity of the ground
water should enable an owner/operator to
establish an interval that ensures the four
samples  are being collected from four
different volumes of water. For additional
information  on   establishing  sampling
interval,   see   Statistical  Analysis   of
Groundwater Monitoring Data at RCRA
                                         Til

-------
Semiannual Monitoring for all Appendix I

• First semiannual monitoring-
   Four independent samples from each well
   (background and downgradient)

• Subsequent semiannual monitoring-
   One sample from each well (background
   and downgradient)
         Subsequent significant
       increase over background
       for one or more Appendix
            1 constituents?
 Continue
semiannual
monitoring
            YES
 Within 14 days notify State director that
 notice placed in record

 Within 90 days establish assessment
 monitoring program

 May demonstrate other source responsible
 or an error in sampling/analysis/statistics
           Figure 5-5.  Detection Monitoring Program

                              278

-------
                     Ground-Water Monitoring and Corrective Action
Facilities  -  Interim  Final  Guidance,
(USEPA, 1989).

Alternative List/Removal of Parameters

An  alternative  list  of   Appendix  I
constituents may be allowed by the Director
of an approved State.  The alternative list
may use geochemical parameters, such as
pH and specific conductance, in  place of
some or all of the metals (Parameters 1
through  15)  in  Appendix  I.    These
alternative   parameters  must  provide  a
reliable indication  of inorganic  releases
from the MSWLF unit to ground water. The
option of establishing an alternative list
applies only to Parameters 1 through 15 of
Appendix  I.   The list of  ground-water
monitoring parameters must include all of
the volatile organic compounds (Appendix
I, Parameters 16 through 62).

A  potential  problem  in  substituting
geochemical parameters for metals on the
alternative   list   is  that  many  of  the
geochemical   parameters   are   naturally
occurring. However, these parameters have
been used to indicate releases from MSWLF
units.    Using  alternative   geochemical
parameters is  reasonable in  cases  where
natural  background levels are not high
enough to mask the detection of a release
from a MSWLF unit.  The decision to use
alternative parameters also should consider
natural  spatial and  temporal variability in
the geochemical parameters.

The types, quantities, and concentrations of
wastes managed at the MSWLF unit play an
important  role  in  determining  whether
removal of parameters from Appendix I is
appropriate.  If an  owner or  operator has
definite knowledge  of the nature of wastes
accepted at the  facility, then removal of
constituents  from Appendix  I may  be
acceptable.  Usually, a waste would have to
be homogeneous to allow for this kind of
determination. The owner or operator may
submit a demonstration that documents the
presence or absence of certain constituents
in the waste.  The owner or operator also
would have to demonstrate that constituents
proposed for deletion from Appendix I are
not degradation or  reaction  products  of
constituents potentially present in the waste.

Alternative Frequency

In approved  States, 40 CFR  §258.54(b)
allows the Director to specify an alternative
frequency  for  ground-water  monitoring.
The  alternative frequency is  applicable
during the active life, including the closure
and  the   post-closure   periods.    The
alternative  frequency can  be no less than
annual.

The need to vary monitoring frequency must
be evaluated on a site-specific basis. For
example, for MSWLF units located in areas
with low ground-water flow rates, it may be
acceptable to monitor  ground water less
frequently.  The sampling frequency chosen
must be sufficient to protect human  health
and the environment.  Depending  on the
ground-water flow rate and the resource
value  of   the   aquifer,   less  frequent
monitoring  may be  allowable  or  more
frequent monitoring may be necessary. An
approved State  may specify an alternative
frequency  for  repeated  sampling and
analysis of Appendix I constituents based on
the following factors:

1) Lithology  of   the  aquifer  and  the
   unsaturated zone
                                         279

-------
                                       Subpart E
2) Hydraulic conductivity of the aquifer
   and the unsaturated zone

3) Ground-water flow rates

4) Minimum   distance   between    the
   upgradient edge of the MSWLF unit and
   the downgradient well screen

5) The resource value of the aquifer.

Approved States also can set alternative
frequencies for monitoring during the post-
closure care period  based on  the  same
factors.

Notification

The notification requirement under 40 CFR
§258.54(c) requires an owner or operator to
1) place a notice in the operating record that
indicates which constituents have shown
statistically  significant  increases  and  2)
notify the State Director that the notice was
placed  in  the  operating record.   The
constituents can be from either Appendix I
or from an alternative list.

Demonstrations of Other Reasons
For Statistical Increase

An owner or operator is allowed 90 days to
demonstrate that the statistically significant
increase of a contaminant/constituent was
caused by statistical, sampling, or analytical
errors or by  a source other than the landfill
unit.    The  demonstration   allowed  in
§258.54(c)(3) may include:

1) A   demonstration  that  the  increase
   resulted   from  another  contaminant
   source
2) A  comprehensive audit of  sampling,
   laboratory,   and   data   evaluation
   procedures

3) Resampling and analysis to verify the
   presence  and  concentration  of  the
   constituents for which the increase was
   reported.

A  demonstration  that  the increase  in
constituent concentration is the result of a
source other than the MSWLF unit should
document that:

•  An alternative source exists.

•  Hydraulic connection exists between the
   alternative  source and the well with the
   significant increase.

•  Constituent(s) (or precursor constituents)
   are present at the alternative source or
   along the flow path from the alternative
   source prior to possible release from the
   MSWLF unit.

•  The    relative   concentration   and
   distribution of constituents in the zone of
   contamination are more strongly linked
   to  the alternative source than  to the
   MSWLF unit when the fate and transport
   characteristics of the constituents are
   considered.

•  The  concentration observed in ground
   water could not have resulted from the
   MSWLF   unit   given  the   waste
   constituents and concentrations in the
   MSWLF unit leachate and wastes, and
   site hydrogeologic conditions.

•  The    data   supporting  conclusions
   regarding   the  alternative  source  are
   historically     consistent     with
   hydrogeologic
                                         280

-------
                    Ground-Water Monitoring and Corrective Action
   conditions   and   findings  of   the
   monitoring program.

The  demonstration must be documented,
certified  by  a  qualified  ground-water
scientist, and placed in the operating record
of the facility.

Demonstrations of Other Sources of
Error

A  successful   demonstration  that  the
statistically significant change is the result
of an error in sampling, analysis,  or data
evaluation may include the following:

•  Clear indication of a transcription or
   calculation error

•  Clear indication of a systematic error in
   analysis or data reduction

•  Resampling, analysis, and evaluation of
   results

•  Corrective measures to prevent  the
   recurrence of the error and incorporation
   of these measures into the ground-water
   monitoring program.

If resampling is necessary, the sample(s)
taken must be independent of the previous
sample.  More  than one  sample  may be
required to substantiate the contention  that
the original sample was not representative
of the ground-water quality in the affected
well(s).
5.11  ASSESSMENT   MONITORING
      PROGRAM
      40 CFR §258.55(a)-(f)

5.11.1  Statement of Regulation

 (a) Assessment monitoring is required
whenever  a   statistically   significant
increase over  background   has  been
detected  for   one  or  more  of  the
constituents listed in Appendix I or in the
alternate  list  approved in  accordance
with § 258.54(a)(2).

 (b) Within 90 days  of  triggering an
assessment monitoring  program,  and
annually  thereafter,   the  owner  or
operator must sample  and analyze the
ground  water  for  all  constituents
identified in Appendix II of this part. A
minimum  of   one  sample  from  each
downgradient well must be collected and
analyzed during  each  sampling event.
For any new constituent detected in the
downgradient  wells as a result  of the
complete   Appendix   II  analysis,  a
minimum of four independent samples
from   each   well   (background   and
downgradient) must be  collected and
analyzed to establish background for the
new constituents.   The Director of an
approved  State    may   specify   an
appropriate subset of wells to be sampled
and   analyzed   for   Appendix   II
constituents      during    assessment
monitoring. The Director of an approved
State may delete any of the Appendix II
monitoring parameters for a MSWLF
unit if it can be shown that the removed
constituents are not reasonably  expected
to be contained in  or  derived from the
waste contained in the unit.
                                       281

-------
                                     Subpart E
 (c) The Director of an approved State
may specify an  appropriate alternate
frequency  for  repeated sampling and
analysis for the full set of Appendix II
constituents required  by §258.55(b)  of
this part, during the active life (including
closure) and post-closure care of the unit
considering the following factors:

 (1) Lithology   of  the   aquifer  and
unsaturated zone;

 (2) Hydraulic   conductivity  of  the
aquifer and unsaturated zone;

 (3) Ground-water flow rates;

 (4) Minimum     distance     between
upgradient edge of the MSWLF unit and
downgradient  monitoring well  screen
(minimum distance of travel);

 (5) Resource value of the aquifer; and

 (6) Nature (fate and  transport) of any
constituents detected in response to this
section.

 (d) After obtaining the results from the
initial  or subsequent sampling  events
required in paragraph (b) of this section,
the owner or operator  must:

 (1) Within 14 days, place a notice in the
operating   record    identifying  the
Appendix II constituents that have been
detected  and notify the State Director
that  this notice has been placed in the
operating record;

 (2) Within 90 days, and on at  least a
semiannual basis thereafter, resample all
wells specified by § 258.51(a), conduct
analyses for all constituents in Appendix
I to this Part or in the alternative list
approved    in    accordance     with
§258.54(a)(2), and for those constituents
in  Appendix  II  that  are detected  in
response to paragraph (b) of this section,
and record their  concentrations  in the
facility operating record.  At least  one
sample from each well  (background and
downgradient)  must be  collected  and
analyzed during these sampling events.
The Director of an approved State  may
specify  an   alternative    monitoring
frequency   during   the  active   life
(including  closure) and the post closure
period for the constituents referred  to in
this  paragraph.      The   alternative
frequency for Appendix I constituents or
the alternate list approved in  accordance
with §258.54(a)(2) during the  active life
(including closure) shall be no less  than
annual. The  alternative frequency shall
be based on consideration of the factors
specified in paragraph (c) of this section;

 (3) Establish background concentrations
for any constituents detected pursuant to
paragraphs (b) or (d)(2) of this section;
and

 (4) Establish ground-water  protection
standards for all  constituents detected
pursuant to paragraph (b) or (d)(2) of
this  section.      The   ground-water
protection standards shall be  established
in accordance with paragraphs (h) or (i)
of this section.

 (e) If the concentrations of all Appendix
II constituents are  shown to be at  or
below background  values,  using   the
statistical procedures in §258.53(g),  for
two consecutive sampling  events, the
owner or operator must notify the State
                                       282

-------
                     Ground-Water Monitoring and Corrective Action
Director of this finding and may return to
detection monitoring.

 (f)  If   the   concentrations   of   any
Appendix II  constituents  are  above
background values, but all concentrations
are  below the ground-water protection
standard established under paragraphs
(h)  or  (i)  of this  section, using  the
statistical procedures in  §258.53(g), the
owner   or   operator  must   continue
assessment  monitoring  in  accordance
with this section.

5.11.2 Applicability

Assessment monitoring is  required at all
existing units, lateral expansions, and new
facilities whenever any of the constituents
listed in  Appendix  I are detected  at a
concentration   that   is  a   statistically
significant increase over background values.
Figure 5-6 presents a flow chart pertaining
to applicability requirements.

Within 90 days of beginning assessment
monitoring, the owner or operator must
resample  all   downgradient  wells   and
analyze the samples  for all  Appendix  II
constituents.   If any new  constituents are
identified in this process, four independent
samples   must  be  collected   from   all
upgradient and downgradient  wells  and
analyzed  for  those  new  constituents to
establish background concentrations.  The
complete list of Appendix II constituents
must be monitored in each well annually for
the duration of the assessment monitoring
program.  In an approved State, the Director
may  reduce the number of  Appendix  II
constituents to be analyzed  if  it  can be
reasonably shown that those constituents are
not present in or derived from the wastes.
The Director of an approved State
may specify an appropriate subset of wells
to be included in the assessment monitoring
program. The Director of an approved State
also may specify an  alternative frequency
for  repeated  sampling  and analysis of
Appendix II constituents.  This frequency
may be decreased or increased based upon
consideration    of   the    factors   in
§258.55(c)(l)-(6).    These  options for
assessment   monitoring   programs  are
available only with  the  approval of the
Director of an approved State.

Within 14 days of receiving the results of
the  initial  sampling  for  Appendix II
constituents under assessment monitoring,
the owner or operator must place the results
in the operating record and notify the State
Director that this notice has been placed in
the operating record.

Within 90 days of receiving these initial
results, the owner or operator must resample
all  wells for all Appendix I and detected
Appendix II constituents. This  combined
list of constituents must be sampled at least
semiannually thereafter, and the list must be
updated  annually  to include any  newly
detected Appendix II constituents.

Within the  90-day period, the  owner or
operator must establish background values
and ground-water   protection   standards
(GWPSs) for all Appendix II constituents
detected. The requirements for determining
GWPSs are provided in §258.55(h). If the
concentrations   of   all  Appendix  II
constituents are at or below the background
values after two independent, consecutive
sampling events, the owner or operator may
return  to   detection  monitoring   after
notification has been  made  to  the  State
Director.  If, after these  two
                                         283

-------
                                          Figure 5-6
                           ASSESSMENT MONITORING
            YES
                                        Is There a
                                       Statistically
                                   Significant Increase
                                      in Appendix I
                                      Constituents?
                                                       YES
   Continue/Return to
  Detection Monitoring

iiiiiiiiiiiiiiiiiinnin	iiimiiiiiiiiiiiimllin
                 [null
                                              Assessment Monitoring (258.55)
                         • Sample for All Appendix II Constituents
                         • Set Ground-Water Protection Standard for Detected
                          Appendix II Constituents
                         • Resample for Detected Appendix II Constituents and All
                          Appendix I Constituents Semi-Annually
                         • Repeat Annual Monitoring for All Appendix II Constituents
                         • Characterize Nature and Extent of Release
                                                 Is There
                                               a Statistically
                                           Significant increase in
                                          Appendix II Constituents
                                            Over Ground-Water
                                                Protection
                                                Standard?
      Are all
    Appendix II
Constituents Below
   Background?
   Proceed to
Corrective Action
         Continue Assessment
              Monitoring
       »	IIIHIllllllllllHIIIIIIHIIlllllllllllllllllllllllL
                                               284

-------
                     Ground-Water Monitoring and Corrective Action
sampling events, any detected Appendix II
constituent is statistically above background
but below the  GWPSs,  the  assessment
monitoring program must be continued.

5.11.3 Technical Considerations

The purpose of assessment monitoring is to
evaluate  the  nature   and  extent  of
contamination.  The assessment monitoring
program is phased. The first phase assesses
the  presence  of  additional  assessment
monitoring constituents (Appendix II or a
revised list designated by an approved State)
in all downgradient wells or in a subset of
ground-water monitoring wells specified by
the Director of an  approved  State.  If
concentrations   of   all   Appendix  II
constituents  are at or below  background
values using the  statistical procedures in
§258.53(g) for two consecutive sampling
periods, then the  owner or operator can
return to detection monitoring.

Following notification of a  statistically
significant increase  of  any  Appendix I
constituent above background, the owner or
operator  has  90  days  to  develop  and
implement  the  assessment  monitoring
program.  Implementation of the program
involves sampling downgradient monitoring
wells for ground water passing the relevant
point of compliance for the unit (i.e., the
waste   management  unit   boundary  or
alternative boundary  specified  by  the
Director   of   an    approved   State).
Downgradient  wells  are   identified  in
§258.51(a)(2).   Initiation  of assessment
monitoring  does  not  stop  the  detection
monitoring program. Section 258.55(d)(2)
specifies that analyses must continue for all
Appendix I  constituents on  at least a
semiannual basis.  Within the 90-day period,
the owner or operator must collect at least
one sample from each downgradient well
and analyze the samples for the Appendix II
parameters.   If a  downgradient well has
detectable quantities of a new Appendix II
constituent, four independent samples must
be  collected from  all   background  and
downgradient wells to establish background
for the new constituent(s).  The date, well
locations,  parameters detected, and their
concentrations must be documented in the
operating  record  of the  facility,  and the
State Director must be notified within 14
days of the initial detection of Appendix II
parameters.    On  a  semiannual  basis
thereafter,     both     background     and
downgradient wells must be sampled for all
Appendix  II constituents.

Alternative List

In an approved State, the Director may
delete  Appendix II parameters  that the
owner or  operator can demonstrate would
not be  anticipated  at  the facility.   A
demonstration  would  be  based  on  a
characterization of the wastes contained in
the unit and an assessment of the  leachate
constituents. Additional information on the
alternative list  can be  found in  Section
5.10.3.

Alternative Frequency

The Director of an approved  State may
specify an  alternate sampling frequency for
the entire Appendix  II list for both the
active  and  post-closure  periods  of the
facility.   The   decision  to change the
monitoring frequency must consider:

1) Lithology of the aquifer and unsaturated
   zone;
                                         285

-------
                                      Subpart E
2) Hydraulic conductivity of the aquifer
   and unsaturated zone;

3) Ground-water flow rates;

4) Minimum distance of travel (between the
   MSWLF  unit edge  to downgradient
   monitoring wells); and

5) Nature  (fate  and  transport)  of  the
   detected constituents.

The Director of an approved State also may
allow  an alternate frequency,  other  than
semiannual, for the monitoring of Appendix
I and detected Appendix II constituents.

The   monitoring  frequency   must  be
sufficient  to  allow detection of ground-
water contamination.  If contamination is
detected early, the volume of ground water
contaminated  will  be  smaller  and  the
required  remedial  response  will  be less
burdensome.  Additional information on the
alternate frequency can be found in Section
5.10.3.

In an  approved State, the Director  may
specify a subset  of wells  that  can be
monitored for Appendix II constituents to
confirm a release and track the plume of
contamination     during      assessment
monitoring.  The owner or operator should
work closely with the State in developing a
monitoring plan that targets the  specific
areas  of concern, if possible.   This  may
represent  a   substantial  cost  savings,
especially at large facilities for which only
a very small  percentage of wells  showed
exceedances above background.  The use of
a subset of wells likely will be feasible only
in cases where the direction and rate of flow
are relatively constant.
5.12  ASSESSMENT  MONITORING
      PROGRAM
      40 CFR §258.55(g)

5.12.1  Statement of Regulation

 (g) If  one  or  more  Appendix   II
constituents are detected at statistically
significant levels above the ground-water
protection standard  established  under
paragraphs (h) or (i) of this section in any
sampling  event, the owner or operator
must, within 14 days of this finding, place
a   notice   in  the   operating  record
identifying the Appendix II constituents
that have exceeded  the ground-water
protection standard and, notify the State
Director  and   all   appropriate  local
government officials  that the notice has
been placed in the operating record. The
owner or operator also:

 (1) (i) Must characterize the nature and
extent  of  the  release  by  installing
additional monitoring wells as necessary;

 (ii) Must install at least one additional
monitoring well at the facility boundary
in the direction of contaminant migration
and sample this well in accordance with
§258.55(d)(2);

 (iii)  Must notify all persons who own
the land  or reside  on  the  land that
directly overlies any part of the plume of
contamination   if contaminants  have
migrated off-site if indicated by sampling
of wells in accordance with §258.55(g)(i);
and

 (iv)   Must initiate an  assessment  of
corrective  measures  as  required  by
§255.56 of this part within 90 days; or
                                        286

-------
                     Ground-Water Monitoring and Corrective Action
 (2)  May demonstrate that a  source
other than a MSWLF unit caused the
contamination,  or that the statistically
significant increase resulted from error in
sampling, analysis, statistical evaluation,
or  natural variation in  ground-water
quality.    A  report documenting this
demonstration must be  certified by a
qualified  ground-water   scientist   or
approved by the Director of an approved
State and placed in the operating record.
If a successful demonstration is made the
owner   or  operator  must  continue
monitoring  in   accordance  with  the
assessment monitoring program pursuant
to §258.55, and may return to detection
monitoring   if    the    Appendix   II
constituents  are below background as
specified in §258.55(e). Until a successful
demonstration is made, the owner  or
operator must comply with  §258.55(g)
including  initiating an  assessment  of
corrective measures.

5.12.2  Applicability

This requirement  applies to facilities in
assessment monitoring and is applicable
during the active life, closure, and post-
closure care periods.

5.12.3  Technical Considerations

If an Appendix II constituent(s) exceeds a
GWPS in any sampling event, the owner or
operator  must notify the  State Director
within 14 days and place a notice  of these
findings  in the  operating record  of the
MSWLF  facility. In addition, the owner or
operator  must:

1) Characterize  the  lateral and  vertical
   extent of  the  release  or plume by
   installing and sampling an appropriate
   number of additional monitoring wells

2) Install    at   least   one   additional
   downgradient  well   at   the  facility
   property  boundary in the direction of
   migration of the contaminant plume and
   sample that well for  all Appendix II
   compounds initially and  thereafter, in
   conformance  with   the   assessment
   monitoring program

3) Notify  all property owners whose land
   overlies the suspected plume,  if the
   sampling  of any property  boundary
   well(s)  indicates that contaminants have
   migrated offsite

4) Initiate  an  assessment  of corrective
   measures, as required by §258.56, within
   90 days.

In assessment monitoring,  the  owner or
operator may  demonstrate  that  a  source
other than the MSWLF  unit caused the
contamination  or   that  the statistically
significant increase was  the result of an
error in  sampling, analysis,  statistical
evaluation, or natural variation in ground-
water quality.  The demonstration must be
certified  by  a qualified   ground-water
scientist or approved by the Director of an
approved  State.    Until   a  successful
demonstration  is  made,  the  owner  or
operator must comply with §258.55(g) and
initiate assessment of corrective measures.
If the demonstration is successful, the owner
or  operator  must  return to assessment
monitoring and may return to the detection
program provided  that all  Appendix II
constituents are at or below background for
two consecutive sampling periods.
                                        287

-------
                                      Subpart E
Release Investigation

If the GWPS is exceeded, a series of actions
must be taken. These actions are described
in the next several paragraphs.  The owner
or operator must investigate the extent of
the   release  by  installing   additional
monitoring wells and obtaining additional
ground-water  samples.  The investigation
should  identify  plume geometry,  both
laterally and vertically.  Prior to such field
activities,  records of  site operation  and
maintenance activities should be reviewed
to identify possible release locations within
the landfill  and whether such  releases are
expected to be  transient (e.g., one time
release due to repaired liner) or long-term.
Due to the presence  of dissolved ionic
constituents,  such as  iron, magnesium,
calcium,   sodium,  potassium,  chloride,
sulfate, and carbonate, typically associated
with MSWLF unit leachates,  geophysical
techniques, including resistivity and terrain
conductivity, may be useful in defining the
plume.  Characterizing the nature  of the
release should include a description of the
rate and direction of contaminant migration
and    the     chemical    and    physical
characteristics of the contaminants.

Property Boundary Monitoring Well

At least one monitoring  well must be
installed  at the  facility boundary  in  the
direction   of   contaminant   migration.
Additional   wells may be  required  to
delineate the plume.  Monitoring wells at
the facility  boundary should be screened to
monitor all stratigraphic units that could be
preferential  pathways  for  contaminant
migration in the uppermost aquifer.    In
some cases, this may require installation of
nested wells or individual wells screened at
several discrete intervals. The well installed
at the facility boundary must  be sampled
semiannually or at an alternative frequency
determined by the Director of an approved
State. The initial sample must be analyzed
for all Appendix II constituents.

Notification of Adjoining Residents and
Property Owners

If ground-water  monitoring indicates that
contamination has  migrated  offsite,  the
owner or operator must notify  property
owners  or residents  whose  land surface
overlies any part of the contaminant release.
Although the requirement does not describe
the contents of the notice,  it is expected that
the notice  could include  the following
items:

•  Date of detected release

•  Chemical composition of release

•  Reference to the constituent(s), reported
   concentration(s), and the GWPS

•  Representatives of the MSWLF facility
   with  whom  to  discuss  the finding,
   including their telephone numbers

•  Plans and schedules for future activities

•  Interim recommendations or remedies to
   protect   human    health   and    the
   environment.

Demonstrations of Other Sources of
Error

The owner or operator may demonstrate that
the source of contamination was not  the
MSWLF  unit.   This   demonstration  is
discussed in Section 5.10.3.
                                         288

-------
                    Ground-Water Monitoring and Corrective Action
Return to Detection Monitoring

A facility conducting assessment monitoring
may return to detection monitoring if the
concentrations    of   all   Appendix   II
constituents  are  at or below background
levels for two consecutive sampling periods
using  the   statistical   procedures   in
§25 8.5 3 (g).      The   requirement  that
background   concentrations   must   be
maintained for two consecutive sampling
events will reduce the possibility that the
owner or  operator  will  fail  to  detect
contamination   or  an  increase  in   a
concentration of a hazardous constituent
when one actually exists.  The Director of
an  approved  State   can  establish   an
alternative time period (§258.54(b).
5.13  ASSESSMENT   MONITORING
      PROGRAM
      40 CFR §258.55(h)-(j)

5.13.1  Statement of Regulation

 (h) The  owner   or   operator  must
establish  a  ground-water  protection
standard   for   each   Appendix   II
constituent detected in the ground water.
The ground-water  protection standard
shall be:

 (1) For  constituents   for   which   a
maximum contaminant level (MCL) has
been promulgated under Section 1412 of
the Safe Drinking Water Act (codified)
under 40 CFR Part 141, the MCL for that
constituent;

 (2) For constituents for which MCLs
have   not   been   promulgated,   the
background   concentration   for   the
constituent  established  from  wells  in
accordance with §258.51(a)(l); or
 (3) For  constituents  for  which  the
background level is higher than the MCL
identified under subparagraph (1) above
or health based levels identified under
§258.55(i)(l),     the     background
concentration.

 (i) The Director of an approved State
may establish  an  alternative ground-
water    protection    standard    for
constituents for which MCLs have not
been established.   These ground-water
protection standards shall be appropriate
health  based  levels  that  satisfy  the
following criteria:

 (1) The level  is derived in a  manner
consistent  with Agency guidelines for
assessing    the    health    risks    of
environmental  pollutants (51 FR 33992,
34006, 34014, 34028);

 (2) The level is  based  on scientifically
valid  studies conducted in accordance
with the Toxic Substances  Control Act
Good Laboratory Practice Standards (40
CFR Part 792) or equivalent;

 (3) For carcinogens, the level represents
a concentration associated with an excess
lifetime  cancer   risk  level  (due  to
continuous lifetime exposure) with the 1
x 10"4 to 1 x 10"6 range; and

 (4) For systemic  toxicants,  the   level
represents a concentration to which the
human population (including sensitive
subgroups) could be exposed to on a daily
basis   that  is   likely  to   be   without
appreciable risk of deleterious effects
during a lifetime. For purposes of this
subpart, systemic toxicants include toxic
chemicals that  cause  effects other  than
cancer or mutation.
                                       289

-------
                                      Subpart E
 (j)  In    establishing    ground-water
protection standards under paragraph
(i), the Director of an approved State may
consider the following:

 (1) Multiple contaminants in the ground
water;

 (2) Exposure    threats   to   sensitive
environmental receptors; and

 (3) Other site-specific  exposure  or
potential exposure to ground water.

5.13.2 Applicability

The  criteria for establishing GWPSs are
applicable  to  all  facilities  conducting
assessment monitoring where  any Appendix
II  constituents  have been  detected.   The
owner or operator must establish a GWPS
for each Appendix II constituent detected.

If  the  constituent  has  a  promulgated
maximum  contaminant level  (MCL), then
the GWPS is the MCL. If no MCL has been
published  for   a  given  Appendix   II
constituent, the  background concentration of
the constituent becomes the GWPS.  In
cases where the background concentration is
higher than a promulgated MCL, the GWPS
is set at the background level.

In   approved  States,  the  Director  may
establish   an    alternative   GWPS  for
constituents for which MCLs have not been
established. Any alternative GWPS must be
health-based levels that satisfy the criteria in
§258.55(i). The Director may also consider
any of the criteria identified in §258.55(j).
In    cases   where   the    background
concentration is  higher  than the  health-
based  levels,  the GWPS  is set at the
background level.
5.13.3 Technical Considerations

For each Appendix II constituent detected,
a GWPS must be established.  The GWPS is
to be set at either the MCL or background.
Where  the  background  concentration  is
higher than the MCL, then  the GWPS is
established at background.

Directors of approved States have the option
of establishing  an  alternative  GWPS  for
constituents without MCLs. This alternative
GWPS must be an appropriate health-based
level, based  on specific  criteria.   These
levels must:

•  Be consistent  with EPA  health  risk
   assessment guidelines

•  Be based on scientifically valid studies

•  Be within a risk range of IxlO"4 to IxlO"6
   for carcinogens

•  For systemic toxicants (causing effects
   other than cancer or mutations),  be a
   concentration to  which   the  human
   population could be exposed on a daily
   basis  without  appreciable  risk   of
   deleterious effects during a lifetime.

The health-based GWPS may be established
considering the presence of more than one
constituent,    exposure    to   sensitive
environmental  receptors,  and  other site-
specific exposure to  ground water.   Risk
assessments to establish the GWPS must
consider cumulative  effects  of multiple
pathways  to  receptors and  cumulative
effects  on  exposure  risk  of  multiple
contaminants. Guidance and procedures for
establishing a health-based risk assessment
may  be found  in  Guidance on Remedial
Actions for
                                         290

-------
                    Ground-Water Monitoring and Corrective Action
Contaminated Groundwater at Superfund
Sites, (USEPA, 1988).
5.14  ASSESSMENT OF
      CORRECTIVE MEASURES
      40 CFR §258.56

5.14.1  Statement of Regulation

 (a) Within 90 days of finding that any of
the constituents  listed  in Appendix II
have  been  detected  at  a statistically
significant level exceeding the ground-
water protection standards defined under
§258.55(h) and (i) of this part, the owner
or operator must initiate an assessment of
corrective measures. Such an assessment
must be completed within a reasonable
period of time.

 (b) The  owner   or   operator  must
continue to monitor in  accordance with
the assessment monitoring program as
specified in §258.55.

 (c) The  assessment shall include an
analysis of the effectiveness of potential
corrective measures in meeting all of the
requirements and  objectives  of  the
remedy  as   described  under §258.57,
addressing at least the following:

 (1) The performance, reliability, ease of
implementation, and potential impacts of
appropriate potential remedies, including
safety impacts, cross-media impacts, and
control  of  exposure to  any residual
contamination;

 (2) The  time required  to  begin  and
complete the remedy;
 (3) The costs of remedy implementation;
and

 (4) The institutional requirements such
as State or local permit requirements or
other  environmental or  public health
requirements that  may  substantially
affect implementation of the remedy(s).

 (d) The owner or operator must discuss
the results  of the  corrective measures
assessment,  prior  to the selection  of
remedy,   in a   public  meeting   with
interested and affected parties.

5.14.2  Applicability

An assessment of corrective measures must
be  conducted whenever  any Appendix  II
constituents  are  detected  at  statistically
significant levels exceeding the GWPS.  The
assessment of corrective measures must be
initiated within  90  days of the finding.
During the initiation of  an  assessment of
corrective measures, assessment monitoring
must be  continued.   The  assessment of
corrective    measures   must    consider
performance (including potential impacts),
time, and cost aspects of the remedies.  If
implementation requires additional State or
local permits, such requirements should be
identified.   Finally,  the results  of the
corrective  measures  assessment must  be
discussed  in  a  public  meeting   with
interested and affected parties.

5.14.3  Technical Considerations

An assessment of corrective measures  is
site-specific  and  will vary  significantly
depending on the design and age  of the
facility, the  completeness of the facility's
historical   records,   the   nature    and
concentration of the contaminants found in
                                       291

-------
                                      Subpart E
the ground water, the complexity of the site
hydrogeology, and the facility's proximity
to sensitive receptors.  Corrective measures
are  generally  approached  from   two
directions: 1) identify and  remediate  the
source of contamination and 2) identify and
remediate   the   known   contamination.
Because each case will be site-specific, the
owner or  operator should be  prepared to
document that, to the best of his or  her
technical and financial abilities, a diligent
effort  has been  made  to  complete  the
assessment in the shortest time practicable.

The factors listed in §258.56(c)(l) must be
considered in assessing corrective measures.
These general factors are discussed below in
terms   of  source   evaluation,  plume
delineation, ground-water assessment, and
corrective measures assessment.

Source Evaluation

As part of the  assessment of corrective
measures,  the owner or operator will need to
identify the nature of the  source of  the
release. The first step in this identification
is a review of all available site information
regarding  facility design, wastes received,
and  onsite  management practices.   For
newer facilities, this  may be  a relatively
simple task.   However, at  some  older
facilities,  detailed records of the facility's
history may  not  be as well documented,
making source definition more difficult.
Design,  climatological,  and  waste-type
information should be used to  evaluate the
duration of the release, potential seasonal
effects  due  to  precipitation  (increased
infiltration and leachate generation), and
possible  constituent  concentrations.   If
source evaluation is   able  to identify a
repairable engineering condition that likely
contributed to the cause of contamination
(e.g., unlined leachate storage ponds, failed
cover system, leaky leachate transport pipes,
past conditions  of  contaminated  storm
overflow),  such  information  should be
considered  as part of the assessment  of
corrective measures.

Existing site  geology and hydrogeology
information,  ground-water   monitoring
results,   and  topographic  and  cultural
information must be documented clearly and
accurately.  This information may include
soil boring logs, test pit and monitoring well
logs, geophysical data, water level elevation
data, and other information collected during
facility   design   or  operation.     The
information  should  be  expressed in  a
manner that will aid interpretation of data.
Such data may include isopach maps of the
thickness of the upper aquifer and important
strata,     isoconcentration    maps     of
contaminants, flow nets, cross-sections, and
contour maps. Additional guidance on data
interpretation that may be useful in a source
evaluation is presented in RCRA Facility
Investigation  Guidance:    Volume  I  -
Development of an RFI  Work Plan and
General Considerations for RCRA Facility
Investigations,  (USEPA   1989a), RCRA
Facility Investigation Guidance:  Volume IV
- Case  Study Examples,  (USEPA 1989d),
and  Practical Guide For Assessing and
Remediating Contaminated Sites (USEPA
1989e).

Plume Delineation

To effectively assess corrective measures,
the  lateral   and   vertical   extent   of
contamination must be known.  When it is
determined that a GWPS is exceeded during
the assessment monitoring program, it may
be necessary to install additional wells  to
characterize the contaminant plume(s). At
                                         292

-------
                     Ground-Water Monitoring and Corrective Action
least one additional well must be added at
the property boundary in the direction of
contaminant  migration to  allow  timely
notification to potentially affected parties if
contamination migrates offsite.

The following circumstances may  require
additional monitoring wells:

•  Facilities that have  not determined the
   horizontal and  vertical  extent  of the
   contaminant plume

•  Locations  where  the   subsurface  is
   heterogeneous or where  ground-water
   flow patterns  are difficult to establish

•  Mounding  associated  with  MSWLF
   units.

Because the  requirements  for  additional
monitoring are site-specific, the regulation
does not specifically establish cases where
additional wells  are necessary or establish
the number of additional wells that must be
installed.

During the plume delineation process, the
owner or operator is  not  relieved  from
continuing  the   assessment  monitoring
program.

The rate of plume migration and the change
in contaminant  concentrations  with  time
must be monitored to allow prediction of the
extent and timing  of impact to sensitive
receptors.  The receptors may include users
of both ground-water  and surface water
bodies where contaminated  ground water
may be discharged.  In some cases, transfer
of volatile compounds from ground water to
the soil and  to  the air may provide  an
additional migration pathway. Information
regarding  the aquifer characteristics  (e.g.,
hydraulic conductivity, storage coefficients,
and effective porosity) should be developed
for  modeling  contaminant  transport  if
sufficient data are not available. Anisotropy
and  heterogeneity of the aquifer must be
evaluated,  as  well  as  magnitude  and
duration of source inputs, to  help explain
present and predicted plume configuration.

Currently,  most   treatment  options  for
ground-water  contamination  at MSWLF
units involve  pump and  treat or in-situ
biological technologies (bio-remediation).
The cost and duration of treatment depends
on  the  size of the  plume, the pumping
characteristics  of the aquifer, and  the
chemical  transport phenomena.   Source
control  and  ground-water flow control
measures to reduce the rate of contaminant
migration should be included in the costs of
any remedial activity undertaken. Ground-
water modeling  of the  plume may  be
initiated to establish the following:

•  The  locations  and pumping rates of
   withdrawal and/or injection wells

•  Predictions      of     contaminant
   concentrations at exposure  points

•  Locations of additional monitoring wells

•  The  effect  that source  control options
   may have on ground-water remediation

•  The effects of advection and dispersion,
   retardation,   adsorption,   and  other
   attenuation  processes  on  the  plume
   dimensions     and     contaminant
   concentrations.

Any modeling effort must  consider that
simulations of remedial response measures
and  contaminant  transport  are based  on
many necessary simplifying assumptions,
                                         293

-------
                                      Subpart E
which affect the accuracy of the model.
These  assumptions   include   boundary
conditions, the degree and spatial variability
of   anisotropy,  dispersivity,   effective
porosity, stratigraphy, and the  algorithms
used   to   solve  contaminant  transport
equations.    Model  selection  should be
appropriate for the amount of data available,
and the technical uncertainty of the model
results must be documented by a sensitivity
analysis  on  the input  parameters.    A
sensitivity analysis is generally done after
model calibration by  varying  one input
parameter at a  time  over a realistic range
and  then  evaluating  changes in  model
output.  For additional  information on
modeling, refer to the Further Information
Section of  Chapter  5.0  and  the  RCRA
Facility Investigation Guidance: Volume II
- Soil, Groundwater and Subsurface  Gas
Releases (USEPA, 1989b).

Ground-Water Assessment

To  assess  the  potential  effectiveness  of
corrective  measures  for  ground-water
contamination, the following information is
needed:

•  Plume  definition (includes  the types,
   concentration, and spatial distribution of
   the contaminants)

•  The amenability  of the contaminants to
   specific  treatment  and  potential   for
   contaminants   to    interfere    with
   treatability

•  Fate  of  the  contaminants  (whether
   chemical transformations  have, are,  or
   may be occurring, and the degree  to
   which  the species  are sorbed to  the
   geologic matrix)
•  Stratigraphy and hydraulic properties of
   the aquifer

•  Treatment   concentration  goals  and
   objectives.

The owner or operator should  consider
whether immediate measures to limit further
plume migration (e.g., containment options)
or   measures   to   minimize   further
introduction  of contaminants to  ground
water are necessary.

The process by which a remedial  action is
undertaken  will  generally  include   the
following activities:

•  Hydrogeologic investigation, which may
   include  additional  well  installations,
   detailed vertical and lateral sampling to
   characterize  the  plume,   and  core
   sampling  to determine the degree of
   sorption of constituents on the  geologic
   matrix

•  Risk assessment, to determine the impact
   on  sensitive receptors,  which  may
   include  identification  of the  need to
   develop  treatment  goals  other than
   GWPSs

•  Literature  and  technical  review  of
   treatment  technologies  considered  for
   further study or implementation

•  Evaluation of costs of different treatment
   options

•  Estimation of  the  time required  for
   completion  of  remediation under  the
   different treatment options
                                         294

-------
                     Ground-Water Monitoring and Corrective Action
•  Bench-scale    treatability     studies
   conducted    to    assess    potential
   effectiveness of options

•  Selection   of   technology(ies)   and
   proposal preparation for regulatory and
   public review and comment

•  Full-scale pilot study for verification of
   treatability   and  optimization  of  the
   selected technology

•  Initiation   of   full-scale    treatment
   technology    with   adjustments,   as
   necessary

•  Continuation of remedial action until
   treatment goals are achieved.

Corrective Measures Assessment

To compare  different treatment options,
substantial amounts of technical information
must  be assembled  and  assessed.   The
objective of this information-gathering task
is  to identify the following items for each
treatment technology:

•  The expected performance of individual
   approaches

•  The  time   frame   when   individual
   approaches   can   realistically   be
   implemented

•  The   technical   feasibility   of   the
   remediation,   including   new   and
   innovative  technologies,  performance,
   reliability and ease of implementation,
   safety and cross media impacts

•  The  anticipated   time  frame  when
   remediation should be complete
•  The anticipated cost of the remediation,
   including capital  expenditures,  design,
   ongoing engineering, and monitoring of
   results

•  Technical and financial capability of the
   owner  or   operator  to  successfully
   complete the remediation

•  Disposal requirements  for  treatment
   residuals

•  Other   regulatory    or   institutional
   requirements, including  State and local
   permits, prohibitions, or environmental
   restrictions   that   may   affect   the
   implementation of the proposed remedial
   activity.

The  performance  objectives   of   the
corrective measures should be considered in
terms of source reduction,  cleanup goals,
and cleanup time frame.  Source reduction
would include measures to reduce  or stop
further releases and may include the repair
of  existing  facility components  (liner
systems, leachate storage pond liners, piping
systems,   cover systems),  upgrading of
components (liners and  cover systems), or
premature closure in extreme cases.  The
technology proposed as  a cleanup measure
should be the  best available  technology,
given the practicable capability of the owner
or operator.

The  technologies  identified  should  be
reliable,    based   on   their   previous
performance;  however,  new  innovative
technologies are not discouraged if they can
be  shown, with  a reasonable degree of
confidence, to be reliable.

Because most treatment processes, including
biorestoration,     potentially    produce
byproducts  or   release   contaminants to
                                         295

-------
                                      Subpart E
different  media  (e.g.,  air  stripping  of
volatile compounds),  the impacts of such
potential  releases  must   be  evaluated.
Releases to air  may  constitute  a  worker
health and  safety concern and must  be
addressed  as part  of  the  alternatives
assessment  process.   Other cross  media
impacts, including transfer of contaminants
from soils to ground water,  surface water, or
air, should be assessed and addressed in the
assessment of corrective actions. Guidance
for addressing air and soil transport and
contamination  is provided  in  USEPA
(1989b) and USEPA (1989c).

Analyses should be conducted on treatment
options to determine whether or not they are
protective   of  human  health  and  the
environment. Environmental monitoring of
exposure  routes (air and  water)  may
necessitate health monitoring for personnel
involved   in  treatment   activities   if
unacceptable  levels   of   exposure  are
possible.     On  a   case-by-case   basis,
implementation  plans may  require both
forms of monitoring.

The  development    and    screening  of
individual corrective measures requires an
understanding  of  the  physio-chemical
relationships and interferences between the
constituents and  the sequence of treatment
measures that must be implemented. Proper
sequencing of treatment methods to produce
a  feasible  remedial  program  must  be
evaluated to avoid interference between the
presence  of some  constituents and the
effective removal of the targeted compound.
In addition, screening  and design parameters
of potential  treatment options should  be
evaluated in the early stages of conceptual
development and planning  to  eliminate
technically unsuitable treatment methods.
In  general,  selection  of   an appropriate
treatment   method   will    require  the
experience
of   a   qualified   professional  and  will
necessitate a literature review of the best
available treatment technologies.

Numerous case studies and published papers
from scientific and  engineering technical
journals exist  on treatability of specific
compounds  and   groups   of  related
compounds.      Development  of   new
technologies    and    refinements     of
technologies  have   been   rapid.      A
compendium of  available literature that
includes treatment technologies for organic
and inorganic  contaminants, technology
selection, and other sources of information
(e.g., literature search data bases pertinent
to ground-water extraction, treatment, and
responses) is included in Practical Guide
for    Assessing     and    Remediating
Contaminated Sites (USEPA, 1989e).

The  general   approach  to   remediation
typically includes active restoration, plume
containment,   and   source   control   as
discussed  below.    The selection  of  a
particular  approach  or  combination  of
approaches must be based on the corrective
action objectives.  These general approaches
are  outlined in Table 5-3.   It should  be
emphasized that the objective of a treatment
program should be to restore  ground water
to pre-existing conditions or to levels below
applicable     ground-water    protection
standards while simultaneously restricting
further  releases of contaminants to ground
water.  Once treatment objectives are met,
the chance of further contamination should
be mitigated to the extent practicable.

Active Restoration

Active   restoration   generally   includes
ground-water extraction, followed by  onsite
or  offsite wastewater treatment.  Offsite
                                         296

-------
                     Ground-Water Monitoring and Corrective Action
wastewater treatment may include sending
the contaminated water to a local publicly
owned treatment works (POTW) or to a
facility designed to treat the contaminants of
concern. Treated ground water may be re-
injected,  sent   to  a  local  POTW,  or
discharged to a local body of surface water,
depending on  local,  State,  and Federal
requirements.  Typical treatment practices
that  may   be   implemented   include
coagulation  and precipitation of metals,
chemical oxidation of a number of organic
compounds,  air stripping to remove volatile
organic   compounds,   and  biological
degradation  of other organics.

The rate  of contaminant  removal  from
ground  water will depend on the  rate of
ground-water removal, the cation exchange
capacity  of  the  soil,   and  partition
coefficients of the constituents sorbed to the
soil (USEPA, 1988).  As the concentration
of  contaminants in the ground  water is
reduced, the rate  at which constituents
become partitioned from  the soil to the
aqueous phase may also be reduced.  The
amount of flushing of the  aquifer material
required to remove the contaminants to an
acceptable level will  generally determine
the time frame required for restoration. This
time frame  is  site-specific and  may last
indefinitely.

In-situ  methods may be  appropriate for
some sites,  particularly where pump and
treat technologies  create  serious adverse
effects  or where  it  may  be financially
prohibitive.   In-situ methods may include
biological restoration requiring pH control,
addition of specific micro-organisms, and/or
addition of nutrients and  substrate to
augment and encourage  degradation  by
indigenous     microbial     populations.
Bioremediation    requires   laboratory
treatability studies and
pilot  field   studies  to  determine  the
feasibility and the reliability of full-scale
treatment. It must be demonstrated that the
treatment  techniques   will   not   cause
degradation of a target chemical to another
compound that has unacceptable health risks
and that is subject to further degradation.
Alternative in-situ methods may  also  be
designed to increase the effectiveness of
desorption or removal of contaminants from
the aquifer matrix.  Such methodologies
may include steam stripping, soil flushing,
vapor extraction, thermal desorption, and
solvent washing, and extraction for removal
of  strongly  sorbed  organic  compounds.
These  methods also  may   be used  in
unsaturated    zones    where   residual
contaminants may be sorbed to the geologic
matrix during periodic fluctuations of the
water table. Details of in-situ methods may
be found in several sources: USEPA (1988);
USEPA (1985); and Eckenfelder (1989).

Plume Containment

The purpose  of plume  containment  is to
limit  the spread  of  the  contaminants.
Methods  to  contain  plume  movement
include passive hydraulic barriers, such as
grout curtains and slurry walls, and active
gradient control systems involving pumping
wells  and french  drains.   The types  of
aquifer  characteristics  that  favor  plume
containment include:

•  Water  naturally  unsuited  for  human
   consumption

•  Contaminants    present    in     low
   concentration with low mobility

•  Low   potential  for   exposure   to
   contaminants and low risk  associated
   with exposure
                                         297

-------
                                      Subpart E
•  Low transmissivity and low future user
   demand.

Often, it may be advantageous for the owner
or  operator  to  consider  implementing
ground-water  controls to inhibit further
contamination   or   the    spread    of
contamination. If ground-water pumping is
considered for capturing the leading edge of
the contaminant plume, the  contaminated
water must  be managed in conformance
with  all  applicable  Federal  and  State
requirements.  Under most conditions, it is
necessary to consult  with the regulatory
agencies  prior to  initiating  an  interim
remedial action.

Source  Control

Source   control  measures   should   be
evaluated to limit  the  migration  of the
plume.  The regulation does not limit the
definition of source control to exclude any
specific type of remediation.   Remedies
must  control  the  source  to reduce  or
eliminate further releases by identifying and
locating the cause of the release (e.g., torn
geomembrane,  excessive  head  due  to
blocked leachate collection system, leaking
leachate collection well or pipe).  Source
control measures may include the following:

•  Modifying  the operational procedures
   (e.g.,  banning  specific   wastes   or
   lowering the head over the leachate
   collection system through more frequent
   leachate removal)

•  Undertaking   more   extensive   and
   effective maintenance  activities  (e.g.,
   excavate waste to repair a liner failure or
   a clogged leachate collection system)
•  Preventing     additional     leachate
   generation that may reach a liner failure
   (e.g., using a portable or temporary rain
   shelter during operations or capping
   landfill areas that contribute to leachate
   migrating from identified failure areas).

In extreme cases, excavation of deposited
wastes for treatment and/or off site disposal
may be considered.

Public Participation

The owner or operator is required to hold a
public meeting to discuss the results of the
corrective action assessment and to identify
proposed remedies.  Notifications, such as
contacting  local  public agencies,  town
governments, and State/Tribal governments,
posting  a   notice  in  prominent  local
newspapers,     and    making     radio
announcements are  effective.   The public
meeting   should   provide   a   detailed
discussion of how the owner or operator has
addressed the factors at §258.56(c)(l)-(4).
5.15  SELECTION OF REMEDY
      40 CFR §258.57 (a)-(b)

5.15.1  Statement of Regulation

 (a) Based on the results of the corrective
measure  assessment conducted  under
§258.56, the  owner or operator must
select a remedy that, at a  minimum,
meets the standards listed in paragraph
(b) below. The owner or operator must
notify the State Director, within 14 days
of  selecting  a  remedy,  that  a  report
describing the selected remedy has been
placed in the operating record and how it
meets the standards in paragraph (b) of
this section.
                                        298

-------
                     Ground-Water Monitoring and Corrective Action
 (b) Remedies must:

 (1) Be protective of human health and
the environment;

 (2) Attain the ground-water protection
standard   as  specified   pursuant   to
§§258.55(h) or (i);

 (3) Control the source(s) of releases so as
to reduce or eliminate, to the maximum
extent practicable,  further  releases  of
Appendix   II  constituents   into  the
environment that may pose a threat  to
human health or the environment; and

 (4) Comply   with    standards   for
management of wastes as specified  in
§258.58(d).

5.15.2 Applicability

These  provisions  apply to facilities that
have been required to  perform  corrective
measures.   The selection of a  remedy is
closely related to the assessment process and
cannot be accomplished unless a sufficiently
thorough evaluation of alternatives has been
completed.  The process of documenting the
rationale for  selecting  a remedy requires
that a report be  placed  in  the facility
operating record that clearly defines the
corrective    action     objectives    and
demonstrates why  the  selected  remedy is
anticipated to meet those objectives.  The
State Director must be notified within  14
days of the placement of the report in the
operating records of the facility.  The study
must  identify how the remedy will  be
protective  of  human  health   and  the
environment,  attain  the  GWPS  (either
background, MCLs, or,  in approved States,
health-based standards,  if applicable), attain
source control objectives,
and  comply  with  waste  management
standards.

5.15.3  Technical Considerations

The    final    method    selected    for
implementation must satisfy the criteria in
§258.57(b)(l)-(4). The report documenting
the capability of the  selected method to
meet these four criteria should include such
information as:

 •   Theoretical calculations

 •   Comparison  to existing  studies  and
     results   of similar  treatment  case
     histories

 •   Bench-scale or pilot-scale treatability
     test results

 •   Waste management practices.

The  demonstration presented in the report
must document  the  alternative  option
selection process.
5.16  SELECTION OF REMEDY
      40 CFR §258.57 (c)

5.16.1  Statement of Regulation

 (c) In selecting a remedy that meets the
standards  of §258.57(b), the  owner  or
operator  shall  consider the  following
evaluation factors:

 (1) The    long-    and    short-term
effectiveness and protectiveness  of the
potential   remedy(s),  along  with  the
degree of certainty that the remedy will
prove successful based on consideration
of the following:
                                        299

-------
                                     Subpart E
 (i) Magnitude of reduction of existing
risks;

 (ii)  Magnitude  of  residual  risks  in
terms of likelihood of further releases due
to    waste    remaining    following
implementation of a remedy;

 (iii)  The type and degree of long-term
management    required,    including
monitoring, operation, and maintenance;

 (iv)  Short-term  risks  that  might  be
posed to the community, workers, or the
environment during implementation of
such  a  remedy,   including  potential
threats   to   human  health  and   the
environment associated with excavation,
transportation,   and   redisposal    or
containment;
 (v) Time
achieved;
until   full  protection  is
 (vi)  Potential for exposure of humans
and    environmental    receptors    to
remaining   wastes,  considering   the
potential threat to human health and the
environment associated with excavation,
transportation,     redisposal,      or
containment;

 (vii) Long-term   reliability  of   the
engineering and  institutional controls;
and

 (viii) Potential need for replacement of
the remedy.

 (2) The effectiveness of the remedy in
controlling the source to reduce further
releases  based on consideration  of the
following factors:

 (i) The extent  to which  containment
practices will reduce further releases;
 (ii)  The  extent to which treatment
technologies may be used.

 (3) The   ease   or    difficulty    of
implementing a potential remedy(s) based
on consideration of the following types of
factors:

 (i) Degree of difficulty associated with
constructing the technology;

 (ii)  Expected operational reliability of
the technologies;

 (iii)  Need to coordinate with and obtain
necessary approvals and permits from
other agencies;

 (iv)  Availability     of    necessary
equipment and  specialists; and

 (v)  Available capacity  and location of
needed treatment, storage, and disposal
services.

 (4) Practicable capability of the owner
or operator, including a consideration of
the technical and economic capability.

 (5) The degree  to  which community
concerns are addressed  by a potential
remedy(s).

5.16.2 Applicability

These provisions apply to facilities that are
selecting a remedy for corrective  action.
The rule presents the considerations and
factors that the owner or operator must
evaluate  when  selecting  the  appropriate
corrective measure.
                                       300

-------
                     Ground-Water Monitoring and Corrective Action
5.16.3 Technical Considerations

The  owner  or  operator must consider
specific topics to satisfy the performance
criteria  under  selection  of  the  final
corrective measure.  These topics must be
addressed in the report  documenting the
selection of a particular corrective action.
The  general topic  areas  that  must  be
considered include the following:

•  The anticipated long- and  short-term
   effectiveness  of the corrective action

•  The anticipated effectiveness of source
   reduction efforts

•  The ease or difficulty of implementing
   the corrective measure

•  The technical and economic practicable
   capability of the owner or operator

•  The degree to  which the selected  remedy
   will address  concerns  raised  by the
   community.

Effectiveness of Corrective Action

In  selecting  the  remedial  action, the
anticipated   long-term   and   short-term
effectiveness should  be evaluated.  Long-
term  effectiveness  focuses  on  the  risks
remaining after  corrective measures have
been   taken.     Short-term  effectiveness
addresses the risks during construction and
implementation of the corrective measure.
Review  of  case  studies where  similar
technologies have been applied provide the
best   measures   to   judge   technical
uncertainty, especially when relatively new
technologies  are applied.  The  long-term,
post-cleanup  effectiveness may be judged
on  the ability of the proposed  remedy to
mitigate further
releases of contaminants to the environment,
as well as on the feasibility of the proposed
remedy to meet or exceed the GWPSs.  The
owner or operator must make a reasonable
effort to estimate and quantify risks, based
on  exposure pathways  and  estimates  of
exposure  levels  and durations.    These
estimates include risks  for both ground-
water and cross-media contamination.

The source  control  measures that will be
implemented,     including    excavation,
transportation,      re-disposal,      and
containment,  should be  evaluated  with
respect  to potential  exposure  and risk  to
human health and the environment.   The
source control measures should be viewed
as an integral component of the overall
corrective action.  Health considerations
must address monitoring risks to workers
and  the  general  public  and  provide
contingency plans should an unanticipated
exposure occur.  Potential exposure should
consider both long- and short-term cases
before, during, and after implementation  of
corrective actions.

The time to  complete the remedial activity
must be estimated,  because it will  have
direct  financial   impacts  on  the  project
management needs and financial capability
of  the  owner or  operator to meet the
remedial objectives.  The long-term costs  of
the remedial alternatives and the long-term
financial condition of the owner or operator
should  be   reviewed   carefully.     The
implementation  schedule  should  indicate
quality  control  measures  to  assess the
progress of the corrective measure.

The operational reliability of the corrective
measures should be considered.  In addition,
the institutional  controls and management
practices developed  to assess the reliability
should be identified.
                                         301

-------
                                      Subpart E
Effectiveness of Source Reduction

Source  control  measures  identified  in
previous sections should  be discussed  in
terms of their expected effectiveness.  If
source control consists of the removal and
re-disposal of wastes, the residual materials,
such as contaminated soils above the water
table,  should  be  quantified  and  their
potential to  cause further  contamination
evaluated.  Engineering controls intended to
upgrade or repair deficient conditions  in
landfill component systems,  including cover
systems, should be quantified in terms  of
anticipated   effectiveness   according   to
current  and   future   conditions.     This
assessment may indicate to what extent it is
technically and financially  practicable  to
make use  of existing  technologies.   The
decision against using a certain technology
may be based on health considerations and
the potential for unacceptable exposure(s) to
both workers and the public.

Implementation  of Remedial Action

The  ease  of implementing  the proposed
remedial action will affect the schedule and
startup success of the remedial action.  The
following key factors need to be assessed:

 •   The availability of technical expertise

                    of   equipment
Construction
technology
or
     The ability to properly manage and
     dispose   of  wastes  generated  by
     treatment

     The  likelihood  of  obtaining  local
     permits  and public  support  for the
     proposed project.
Technical  considerations,  including  pH
control, ground-water extraction feasibility,
or the ability to inject nutrients, may need to
be considered, depending on the proposed
treatment method. Potential impacts, such
as  potential  cross-media  contamination,
need to be reviewed as part of the overall
feasibility of the project.

The schedule of remedial activities should
identify the start and  end  points of the
following periods:

•  Permitting phase

•  Construction and startup period, during
   which  initial implementation  success
   will be evaluated,  including time  to
   correct any unexpected problems

•  Time when full-scale treatment will  be
   initiated and duration of treatment period

•  Implementation  and  completion   of
   source control measures, including the
   timeframe   for   solving   problems
   associated
   with interim management and disposal of
   waste materials or treatment residuals.

Items that require long lead times should be
identified early  in  the  process and those
tasks should be initiated early to ensure that
implementation  occurs  in  the   shortest
practicable period.

Practical Capability

The owner or operator must be technically
and financially capable of implementing the
chosen remedial  alternative and  ensuring
project completion, including provisions for
future changes  to the  remedial plan after
progress is reviewed.  If either technical or
financial  capability is inadequate  for  a
                                         302

-------
                    Ground-Water Monitoring and Corrective Action
particular alternative, then other alternatives
with similar levels of protectiveness should
be considered for implementation.

Community Concerns

The public meetings held during assessment
of alternative measures are intended to elicit
public comment and response. The owner
or operator  must,  by  means of meeting
minutes and  a record of written comments,
identify which public concerns have been
expressed  and  addressed  by  corrective
measure  options.   In  reality,  the  final
remedy  selected  and implemented will  be
one that the State  regulatory agency, the
public, and the owner or operator agree to.
5.17  SELECTION OF REMEDY
      40 CFR §258.57 (d)

5.17.1  Statement of Regulation

 (d) The owner or operator shall specify
as  part  of  the selected  remedy  a
schedule(s) for initiating and completing
remedial activities. Such a schedule must
require  the  initiation   of remedial
activities within a reasonable period of
time taking into consideration the factors
set forth  in paragraphs (d) (1-8). The
owner or operator  must  consider  the
following factors in  determining  the
schedule of remedial activities:

 (1) Extent and nature of contamination;

 (2) Practical  capabilities of remedial
technologies in achieving compliance with
ground-water    protection   standards
established under §§258.55(g) or (h) and
other objectives of the remedy;
 (3) Availability of treatment or disposal
capacity  for wastes  managed  during
implementation of the remedy;

 (4) Desirability of utilizing technologies
that are  not currently available,  but
which  may  offer significant advantages
over already available technologies  in
terms of effectiveness, reliability, safety,
or ability to achieve remedial objectives;

 (5) Potential risks to human health and
the  environment  from   exposure  to
contamination prior to completion of the
remedy;

 (6) Resource  value  of  the  aquifer
including:

 (i) Current and future uses;

 (ii)  Proximity and withdrawal rate of
users;
 (iii)  Ground-water
quality;
quantity   and
 (iv)  The potential damage to wildlife,
crops, vegetation, and physical structures
caused by exposure to waste constituent;

 (v) The hydrogeologic characteristic of
the facility and surrounding land;
 (vi)  Ground-water
treatment costs; and
removal   and
 (vii) The   cost   and  availability
alternative water supplies.
             of
 (7) Practicable capability of the owner
or operator.

 (8) Other relevant factors.
                                       303

-------
                                      Subpart E
5.17.2 Applicability

The requirements  of §258.57(d)  apply to
owners or  operators  of all  new units,
existing units, and  laterally expanded units
at  all facilities  required to  implement
corrective actions.  The requirements must
be  complied with prior  to  implementing
corrective measures.  The  owner or operator
must specify  the  schedule for  remedial
activities   based    on   the   following
considerations:

•  The size and nature of the contaminated
   area at the time  the corrective measure is
   to be implemented

•  The  practicable   capabilities   of the
   remedial technology selected

•  Available  treatment   and   disposal
   capacity

•  Potential  use of alternative innovative
   technologies not currently available

•  Potential risks to  human health and the
   environment existing prior to completion
   of the remedy

•  Resource value  of the aquifer

•  The   practicable   capability   of  the
   owner/operator

•  Other relevant factors.

5.17.3 Technical Considerations

The time schedule for implementing and
completing   the   remedial   activity   is
influenced by many factors that should be
considered by the  owner  or operator. The
most critical factor is the  nature and extent
of the contamination, which significantly
affects the ultimate treatment rate.  The size
of the treatment  facility and the ground-
water extraction and injection rates must be
balanced for system optimization, capital
resources,   and    remedial    timeframe
objectives. The nature of the contamination
will  influence  the  degree to  which the
aquifer must be flushed to remove adsorbed
species. These  factors, which in part define
the practicable  capability of the alternative
(treatment efficiency, treatment rate, and
replenishment of contaminants by natural
processes),  should  be  considered when
selecting the remedy.

In addition, the rate at which treatment may
occur may be restricted  by the availability
or capacity to handle treatment residues and
the  normal    flow   of  wastes  during
remediation. Alternative residue treatment
or disposal capacity must be identified as
part of the implementation plan schedule.

If contaminant migration is slow due to low
transport   properties   of   the  aquifer,
additional time  may be available to evaluate
the value  of  emerging  and  promising
innovative technologies. The use of such
technologies is not excluded as part of the
requirement to implement a remedial action
as  soon  as  practicable.     Delaying
implementation to increase the availability
of new technologies must be evaluated in
terms of achievable cleanup levels, ultimate
cost, additional environmental impact, and
potential  for increased risk to  sensitive
receptors.  If a new technology clearly is
superior  to existing options in  attaining
remediation   objectives,   it   may   be
appropriate to delay implementation. This
may require that existing risks be controlled
through interim measures.
                                         304

-------
                    Ground-Water Monitoring and Corrective Action
In setting the implementation schedule, the
owner or operator should assess the risk to
human health and the environment within
the   timeframe  of  reaching  treatment
objectives.   If the  risk is unacceptable,
considering  health-based  assessments  of
exposure paths and  exposure limits,  the
implementation  time schedule must be
accelerated or the selected remedy altered to
provide an acceptable risk level in a timely
manner.

Establishment  of the schedule also  may
include consideration of the resource value
of the aquifer, as it pertains to current and
future use, proximity to users, quality and
quantity of ground water, agricultural value
and uses (irrigation water source or impact
on  adjacent agricultural  lands), and  the
availability of alternative supplies of water
of similar quantity and quality.  Based on
these factors, a relative assessment of the
aquifer's resource  value  to the  local
community can be established. Impacts to
the  resource and the degree of financial or
health-related distress by users should be
considered.  The implementation timeframe
should attempt to minimize the loss of value
of the resource to users. The possibility that
alternative water supplies will have to be
developed as part of the remedial activities
may need to be considered.

Because owners or  operators may not be
knowledgeable  in  remediation  activities,
reliance on the owner or operator to devise
the   schedule  for   remediation  may be
impracticable.  In these instances, use of an
outside  firm to  coordinate  remediation
scheduling may be necessary.  Similarly,
development of a schedule for which the
owner or  operator cannot finance, when
other options exist that do allow for owner
or operator financing, should be prevented.
5.18  SELECTION OF REMEDY
      40 CFR §258.57 (e)-(f)

5.18.1  Statement of Regulation

 (e) The Director of an approved State
may determine that remediation of a
release of an Appendix II  constituent
from a MSWLF unit is not necessary if
the owner or operator demonstrates  to
the  satisfaction of the  Director  of an
approved State that:

 (1) The  ground water is  additionally
contaminated by substances that have
originated from a  source other than a
MSWLF  unit and those substances are
present  in  concentrations  such that
cleanup of the release from the MSWLF
unit  would  provide   no  significant
reduction  in risk to  actual or potential
receptors; or

 (2) The  constituent(s)  is  present   in
ground water that:

 (i)  Is  not  currently  or  reasonably
expected  to  be a  potential  source   of
drinking water; and

 (ii) Is not hydraulically connected with
waters    to   which    the   hazardous
constituents are migrating or are  likely to
migrate in a concentration(s) that would
exceed  the  ground-water  protection
standards  established under §258.55(h)
or (i); or

 (3) Remediation  of  the release(s)  is
technically impracticable; or

 (4) Remediation results in unacceptable
cross-media impacts.
                                        305

-------
                                      Subpart E
 (f) A determination by the Director of
an approved State pursuant to paragraph
(e) above shall not affect the authority of
the State to require the owner or operator
to undertake source control measures or
other measures that may be necessary to
eliminate or minimize further releases to
the ground water, to prevent exposure to
the ground water, or to remediate the
ground water to concentrations that are
technically  practicable and significantly
reduce threats to human  health or the
environment.

5.18.2 Applicability

The criteria under §258.57(e) and (f) apply
in approved  States only.  Remediation of the
release of an Appendix II constituent may
not be necessary if 1) a source other than the
MSWLF unit is partly responsible for the
ground-water contamination, 2) the resource
value  of the  aquifer is extremely limited, 3)
remediation  is not technically feasible, or 4)
remediation will  result  in  unacceptable
cross-media impacts.   The  Director may
determine that while total remediation is not
required, source control measures or partial
remediation   of   ground    water   to
concentrations   that   are    technically
practicable and significantly reduce risks is
required.

5.18.3 Technical Considerations

There are four situations where an approved
State may not require cleanup of hazardous
constituents released to ground water from
a MSWLF unit. If sufficient evidence exists
to document  that the  ground  water is
contaminated by a source other than the
MSWLF unit, the Director of an approved
State may grant a waiver
from  implementing  some  or all  of the
corrective  measure  requirements.    The
owner or operator must demonstrate that
cleanup of a release from its MSWLF unit
would provide no  significant reduction in
risk to receptors due to concentrations of
constituents from the other source.

A waiver from corrective measures also may
be granted if the contaminated ground water
is not a current  or reasonably  expected
potential future drinking water source, and
it is unlikely that the hazardous constituents
would  migrate  to  waters  causing  an
exceedance  of GWPS.   The  owner or
operator  must   demonstrate  that  the
uppermost  aquifer is  not  hydraulically
connected with a lower aquifer.  The owner
or operator may seek an exemption if it can
be    demonstrated   that   attenuation,
advection/dispersion  or   other   natural
processes  can  remove   the  threat  to
interconnected aquifers.  The  owner  or
operator may seek  the latter exemption if
the contaminated  zone is not a drinking
water resource.

The  Director of an approved  State may
waive cleanup requirements if remediation
is not technically feasible. In addition, the
Director  may  wave  requirements   if
remediation results in unacceptable cross-
media impacts.  A successful demonstration
that remediation is not technically feasible
must document specific facts that attribute
to  this  demonstration.      Technical
impracticabilities may be related to the
accessibility  of  the  ground  water  to
treatment, as well as the treatability of the
ground water using practicable treatment
technologies. If the owner or operator can
demonstrate that unacceptable cross-media
impacts are uncontrollable  under a given
remedial option
                                         306

-------
                    Ground-Water Monitoring and Corrective Action
(e.g.,  movement in response to  ground-
water  pumping  or  release  of  volatile
organics to the atmosphere) and that the no
action option is a less risky alternative, then
the Director  of an approved State  may
determine that remediation is not necessary.

A  waiver of remedial obligation does not
necessarily release the owner or operator
from the responsibility of conducting source
control measures or minimal ground-water
remediation.  The  State may require that
source control  be  implemented  to  the
maximum extent practicable to minimize
future risk of releases of  contaminants to
ground water or that ground water be treated
to  the extent technically feasible.
5.19  IMPLEMENTATION OF THE
      CORRECTIVE  ACTION
      PROGRAM
      40 CFR §258.58  (a)

5.19.1  Statement of Regulation

 (a) Based on the  schedule established
under   §258.57(d)  for  initiation  and
completion  of remedial  activities  the
owner/operator must:

 (1) Establish and implement a corrective
action ground-water monitoring program
that:

 (i) At   a   minimum,   meets   the
requirements   of    an   assessment
monitoring program under §258.55;

 (ii)  Indicates the effectiveness of the
corrective action remedy; and
 (iii)  Demonstrates  compliance  with
ground-water   protection   standard
pursuant to paragraph (e) of this section.

 (2) Implement  the  corrective  action
remedy selected under §258.57; and

 (3) Take any interim measures necessary
to ensure the protection of human health
and the environment. Interim measures
should, to the greatest extent practicable,
be consistent with the objectives of and
contribute to the performance of any
remedy that may be required pursuant to
§258.57. The following factors must  be
considered by an owner or operator in
determining whether interim measures
are necessary:
 (i) Time  required  to  develop
implement a final remedy;
and
 (ii)  Actual  or  potential exposure  of
nearby  populations  or  environmental
receptors to hazardous constituents;

 (iii)  Actual or potential contamination
of drinking water supplies or sensitive
ecosystems;

 (iv)  Further degradation of the ground
water that may occur if remedial action is
not initiated expeditiously;

 (v) Weather conditions that may cause
hazardous constituents to migrate or  be
released;

 (vi)  Risks  of fire  or  explosion,  or
potential  for  exposure  to  hazardous
constituents as a result of an accident or
failure of a container or handling system;
and
                                       307

-------
                                      Subpart E
 (vii)  Other  situations that may  pose
threats  to  human  health  and  the
environment.

5.19.2 Applicability

These provisions apply to facilities that are
required to initiate and complete corrective
actions.

The owner or  operator  is  required to
continue to implement its ground water
assessment monitoring program to evaluate
the effectiveness of remedial actions and to
demonstrate that the remedial objectives
have been attained at the  completion of
remedial activities.

Additionally, the owner or operator must
take any interim actions to protect human
health and the environment.  The interim
measures must  serve to  mitigate  actual
threats and prevent potential  threats from
being   realized   while   a   long-term
comprehensive response is being developed.

5.19.3 Technical Considerations

Implementation of the corrective measures
encompass all activities necessary to initiate
and continue remediation.  The  owner or
operator    must   continue   assessment
monitoring to anticipate whether interim
measures are necessary, and to determine
whether  the corrective  action is meeting
stated objectives.

Monitoring Activities

During the implementation period, ground-
water monitoring  must be conducted to
demonstrate  the  effectiveness  of  the
corrective action remedy.  If  the remedial
action is not effectively curtailing further
ground water degradation or the spread of
the contaminant plume, replacement of the
system with an  alternative measure may be
warranted.  The improvement rate of the
condition of the aquifer must be monitored
and compared to the cleanup objectives.  It
may be  necessary to  install  additional
monitoring wells to more clearly evaluate
remediation progress.  Also, if it becomes
apparent  that  the  GWPS  will  not  be
achievable technically, in a realistic time-
frame,  the performance objectives of the
corrective  measure must be reviewed and
amended as necessary.

Interim Measures

If unacceptable potential risks to human
health and the environment exist prior to or
during implementation  of the  corrective
action, the owner or operator is required to
take interim measures to protect receptors.
These interim measures are typically short-
term   solutions to   address  immediate
concerns and do not necessarily address
long-term remediation objectives.  Interim
measures may  include  activities such as
control of ground-water migration through
high-volume withdrawal of ground water or
response to equipment failures that occur
during  remediation (e.g., leaking drums).  If
contamination  migrates  offsite,  interim
measures  may  include  providing  an
alternative  water  supply  for   human,
livestock,  or  irrigation  needs.    Interim
measures also  pertain to source  control
activities that may be  implemented as part
of the overall corrective action.  This may
include activities such as excavation of the
source  material  or in-situ treatment of the
contaminated source.    Interim  measures
should be  developed with  consideration
given to maintaining  conformity with the
objectives of the final  corrective action.
                                         308

-------
                    Ground-Water Monitoring and Corrective Action
5.20  IMPLEMENTATION OF THE
      CORRECTIVE ACTION
      PROGRAM
      40 CFR §258.58 (b)-(d)

5.20.1  Statement of Regulation

 (b) An   owner   or   operator   may
determine,   based   on   information
developed after implementation of the
remedy has begun  or other information,
that compliance with  requirements of
§258.57(b)  are  not  being  achieved
through  the remedy selected.  In such
cases,  the  owner  or  operator   must
implement other methods or techniques
that could practicably achieve compliance
with the requirements, unless the owner
or  operator  makes  the determination
under §258.58(c).

 (c) If the owner or operator determines
that compliance with requirements under
§258.57(b) cannot be practically achieved
with any currently available methods, the
owner or operator  must:

 (1) Obtain  certification of a qualified
ground-water  specialist or approval by
the Director of an approved State that
compliance  with  requirements  under
§258.57(b) cannot be practically achieved
with any currently available methods;

 (2) Implement alternate  measures to
control  exposure  of  humans or the
environment to residual contamination,
as necessary to protect human health and
the environment; and

 (3) Implement alternate  measures for
control of the  sources of contamination,
or  for removal or decontamination of
equipment, units, devices, or structures
that are:

 (i) Technically practicable; and

 (ii)  Consistent  with   the   overall
objective of the remedy.

 (4) Notify the State Director within 14
days  that  a   report  justifying  the
alternative    measures    prior    to
implementing  the  alternative measures
has been placed in the operating record.

 (d) All solid wastes that are managed
pursuant  to a  remedy required  under
§258.57, or an interim measure required
under §258.58(a)(3), shall be managed in
a manner:

 (1) That  is protective of human health
and the environment; and

 (2) That complies with applicable RCRA
requirements.

5.20.2 Applicability

The requirements   of  the  alternative
measures are applicable when  it  becomes
apparent that the remedy selected will not
achieve the GWPSs or other significant
objectives  of the remedial program (e.g.,
protection  of  sensitive  receptors).   In
determining  that the selected corrective
action approach will  not achieve desired
results,  the  owner  or  operator  must
implement  alternate corrective measures to
achieve the GWPSs.  If it becomes evident
that the cleanup goals are not  technically
obtainable   by    existing    practicable
technology, the owner  or operator must
implement actions to control exposure of
humans or the environment from residual
                                       309

-------
                                      Subpart E
contamination and to control the sources of
contamination.   Prior  to  implementing
alternative measures, the owner or operator
must  notify the Director of an approved
State within 14  days that a report justifying
the alternative measures has been placed in
the operating record.

All wastes that are managed by the MSWLF
unit  during  corrective  action,  including
interim and alternative measures, must be
managed according to applicable  RCRA
requirements in a manner that is protective
of human health and the environment.

5.20.3 Technical Considerations

An owner or operator is required to continue
the assessment monitoring program during
the remedial  action.  Through monitoring,
the short  and  long term  success  of the
remedial action can  be gauged  against
expected progress.  During the remedial
action,  it  may be necessary  to  install
additional ground-water monitoring wells or
pumping or  injection wells to adjust to
conditions that vary from initial assessments
of the  ground-water  flow  system.   As
remediation  progresses  and  data  are
compiled,  it may become evident  that the
remediation  activities will  not  protect
human health and  the environment, meet
GWPSs, control sources of contamination,
or  comply  with   waste   management
standards.   The reasons  for unsatisfactory
results may include:

•  Refractory  compounds  that are  not
   amenable  to removal  or destruction
   (detoxification)

•  The  presence   of  compounds  that
   interfere  with   treatment   methods
   identified for target compounds
•  Inappropriately applied technology

•  Failure of source control  measures to
   achieve desired results

•  Failure of ground-water control systems
   to  achieve  adequate  containment  or
   removal of contaminated ground water

•  Residual  concentrations  above GWPSs
   that cannot be effectively reduced further
   because  treatment efficiencies are  too
   low

•  Transformation or degradation of target
   compounds to different  forms that are
   not amenable  to further treatment by
   present or alternative technologies.

The  owner  or  operator  should compare
treatment   assumptions  with   existing
conditions  to determine if  assumptions
adequately   depict  site  conditions.   If
implementation occurred as designed, the
owner or operator should attempt to modify
or upgrade existing remedial technology to
optimize performance  and  to  improve
treatment  effectiveness.  If  the  existing
technology  is found to be unable to meet
remediation    objectives,     alternative
approaches must  be evaluated that could
meet  these  objectives  while the present
remediation is continued. During this re-
evaluation period, the  owner or operator
may suspend treatment only if continuation
of remedial activities clearly increases the
threat to human health and the environment.
                                         110

-------
                    Ground-Water Monitoring and Corrective Action
5.21  IMPLEMENTATION OF THE
      CORRECTIVE ACTION
      PROGRAM
      40 CFR §258.58 (e)-(g)

5.21.1  Statement of Regulation

 (e) Remedies   selected   pursuant  to
§258.57  shall be  considered complete
when:

 (1) The owner or operator complies with
the ground-water protection standards
established under §§258.55(h) or (i) at all
points within the plume of contamination
that  lie   beyond  the   ground-water
monitoring well system established under
§258.51(a).

 (2) Compliance with the ground-water
protection  standards established under
§§258.55(h) or (i) has been achieved by
demonstrating that concentrations of
Appendix  II  constituents  have  not
exceeded the ground-water  protection
standard(s)  for  a  period   of  three
consecutive years using the  statistical
procedures and performance standards in
§258.53(g)  and (h). The Director of an
approved   State   may   specify   an
alternative length of time during which
the owner or operator must demonstrate
that concentrations  of  Appendix II
constituents  have  not  exceeded the
ground-water  protection   standard(s)
taking  into consideration:

 (i) Extent and concentration of the
release(s);

 (ii)  Behavior  characteristics  of the
hazardous  constituents  in the  ground
water;
 (iii)  Accuracy  of   monitoring   or
modeling   techniques,  including  any
seasonal,   meteorological,   or  other
environmental  variabilities  that may
affect the accuracy; and

 (iv)  Characteristics  of  the   ground
water.

 (3) All actions required to complete the
remedy have been satisfied.

 (f) Upon completion of the remedy, the
owner or operator must notify the State
Director  within   14  days   that   a
certification that the remedy has been
completed  in  compliance  with  the
requirements  of §258.58(e)  has  been
placed  in  the  operating  record.   The
certification must be signed by the owner
or operator and by a qualified ground-
water  specialist  or  approved  by the
Director of an approved State.

 (g) When,  upon  completion  of the
certification, the  owner  or  operator
determines  that  the  corrective  action
remedy has been completed in accordance
with the requirements under paragraph
(e) of this section, the owner or operator
shall be released from the requirements
for financial  assurance  for  corrective
action under §258.73.

§258.59 [Reserved].

5.21.2 Applicability

These criteria apply to facilities conducting
corrective action. Remedies are considered
complete when, after 3 consecutive years of
monitoring (or an alternative length of time
as identified by the Director), the results
show  significant statistical evidence that
                                       ill

-------
                                      Subpart E
Appendix II constituent concentrations are
below the GWPSs. Upon completion of all
remedial  actions, the  owner or  operator
must  certify to  such,  at which point the
owner or operator is released from financial
assurance requirements.

5.21.3  Technical Considerations

The regulatory period  of compliance is 3
consecutive years at all points within the
contaminant  plume  that lie beyond the
ground-water monitoring  system unless the
Director of an approved State specifies an
alternative length of time.  Compliance  is
achieved  when  the  concentrations  of
Appendix II constituents do not exceed the
GWPSs for a predetermined length of time.
Statistical procedures in  §258.53  must be
used to demonstrate compliance with the
GWPSs.
The   preferred   statistical
comparison is to construct a
                           method  for
                             99 percent
confidence interval around the mean of the
last 3 years of data and compare the upper
limit of the confidence  interval  to the
GWPS.  An upper limit less than the GWPS
is considered significant evidence that the
standard is no longer being exceeded.  The
confidence interval  must be based on the
appropriate   model   describing    the
distribution of the data.

Upon completion of the remedy, including
meeting the GWPS at all points within the
contaminant plume, the owner or operator
must notify  the  State  Director  within
fourteen days that a certification that the
remedy  has been completed has been placed
in the operating record. The certification
must be signed by the owner or operator and
a  qualified  ground-water   scientist  or
approved by  the Director  of an approved
State.  Upon completion  of the remedial
action, in accordance with §258.58(e), the
owner or operator is released  from the
financial assurance requirements pertaining
to corrective actions.

The  Director of an approved  State may
require an alternate time period (other than
3 years)  to  demonstrate compliance.  In
determining an alternate period the Director
must consider the following:

•  The extent  and concentration  of the
   release(s)

•  The behavior characteristics  (fate and
   transport) of the hazardous constituents
   in  the  ground  water  (e.g.,  mobility,
   persistence, toxicity, etc.)

•  Accuracy  of monitoring or  modeling
   techniques,  including   any   seasonal,
   meteorological  or  other environmental
   variabilities that may affect accuracy

•  The characteristics of the ground water
   (e.g., flow rate, pH, etc.).

Consideration of these factors may result in
an extension or shortening  of the time
required   to   show   compliance   with
remediation objectives.
                                         112

-------
                     Ground-Water Monitoring and Corrective Action
5.22 FURTHER INFORMATION
5.22.1  References

Aitchison, J., and J.A.C. Brown (1969).  "The Lognormal Distribution"; Cambridge University
Press; Cambridge.

American Water Works Association (1984).  "Abandonment of Test Holes, Partially Completed
Wells and Completed Wells."  Appendix I. American Water Works Association Standard for
Water Wells, American Water Works Association, Denver, CO, pp 45-47.

Barari, A., and L.S. Hedges (1985). "Movement of Water in Glacial Till."  Proceedings of the
17th International Congress of International Association of Hydrogeologists.

Barcelona,  M.J., J.A. Helfrich  and E.E. Garske, (1985).  "Sampling  Tube Effects on
Groundwater Samples"; Analytical Chemistry 47(2): 460-464.

Barcelona, M.J., J.P. Gibb, J.A. Helfrich, and E.E. Garske, (1985b).  "Practical Guide for
Ground-Water Sampling," USEPA,  Cooperative Agreement #CR-809966-01, EPA/600/2-
85/104, 169pp.

Barcelona, M.J., et al.  1990. Contamination  of Ground Water:  Prevention. Assessment.
Restoration.  Pollution Technology Review No. 184, Noyes Data Corporation, Park Ridge, NJ,
213 pp.

Cantor, L.W., R.C. Knox, and D.M. Fairchild (1987). Ground-Water Quality Protection. Lewis
Publishers, Inc.,  Chelsea, MI.

Cooper, H.H., Jr., and C.E. Jacob (1946). "A Generalized Graphical Method for Evaluating
Formation Constants and Summarizing Well-Field History." American Geophys. Union Trans.,
V. 27, No. 4.

Daniel, D.E., H.M. Liljestrand, G.P. Broderick, and J.J. Bounders, Jr. (1988).  "Interaction of
Earthen Linear Materials with Industrial Waste Leachate in Hazardous Waste and Hazardous
Materials," Vol.  5, No. 2.

Dixon, W.J. and F.J. Massey, Jr.  (1969).  "Introduction to Statistical Analysis"; 3rd Edition;
McGraw-Hill Book Co.; New York, New York.

Driscoll, F.G., (1986). "Groundwater and Wells"; Johnson and Johnson; St. Paul, Minnesota.

Eckenfelder, W.W.,  Jr., (1989). Industrial Water Pollution Control. McGraw-Hill, Inc., Second
Edition.

-------
                                     Subpart E
Fetter, C.W., Jr. (1980). Applied Hydrogeology. Charles E. Merrill Publishing Co., Columbus,
OH.

Freeze, R.A. and J.A. Cherry, (1979).  Groundwater: Prentice-Hall, Inc.; Englewood Cliffs,
New Jersey.

Gibbons, J.D., (1976). "Nonparametric Methods for Quantitative Analysis"; Holt, Rinehart, and
Winston Publishing Co.; New York, New York.

Gilbert, R.O.,  (1987).  Statistical Methods for Environmental Pollution  Monitoring: Van
Nostrand Reinhold Co.; New York, New York.

Heath, R.C. (1982). Basic Ground-Water Hydrology. U.S. Geological Survey Water Supply
Paper 2220, 84pp.

Hsieh, P.A., and  S.P. Neuman  (1985). "Field Determination of the Three  - Dimensional
Hydraulic Conductivity Teasor of Anisotropic Media." Water Resources Research, V. 21, No.
11.

Kearl, P.M., N.E. Korte, and T.A. Cronk. 1992. "Suggested Modifications to Ground Water
Sampling Procedures Based on Observations from the Colloidal Borescope."  Ground-Water
Monitoring Review, Spring, pp. 155-160.

Kruseman, G.P., and N. A. de Ridder (1989). "Analysis and Evaluation of Pumping Test Data,"
International Institute for Land Reclamation and Improvement/ILRI, Bulletin  II, 4th Edition.

Lamb, B. and T. Kinney (1989).  "Decommissioning Wells - Techniques and  Pitfalls."
Proceedings of the Third National Outdoor Action Conference on Aquifer Restoration, Ground-
Water Monitoring and Geophysical Methods, NWWA, May 22-25, 1989, pp 217-228.

McGlew, P.J. and J.E.  Thomas  (1984). "Determining  Contaminant Migration  Pathways in
Fractured Bedrock." Proceedings of the  Fifth National Conference on Management of
Uncontrolled Hazardous Waste Sites.

McWhorter, D.B., and O.K. Sunada (1977). Ground-Water Hydrology and Hydraulics. Water
Resources Publications, Fort Collins, CO.

Miller, J.C. and J.N. Miller, (1986).  Statistics for Analytical  Chemistry: John Wiley  and Sons;
New York, New York.

Molz, F.J.,  O.  Guven and J.G. Melville (1990). "A  New Approach and Methodologies for
Characterizing the Hydrogeologic Properties of Aquifers." EPA Project  Summary.  EPA
600/52-90/002.
                                        114

-------
                    Ground-Water Monitoring and Corrective Action
Molz, F.J., R.H. Norin, A.E. Hess, J.G. Melville, and O. Guven (1989) "The Impeller Meter for
Measuring Aquifer Permeability Variations: Evaluation and Comparison with Other Tests."
Water Resources Research, V 25, No. 7, pp 1677-1683.

Puls, R.W. and R.M. Powell.  1992.  "Acquisition of Representative Ground Water Quality
Samples for Metals." Ground-Water Monitoring Review, Summer, pp. 167-176.

Puls, R.W., R.M. Powell, D.A. Clark, and C.J. Paul.  1991.  "Facilitated Transport of Inorganic
Contaminants in Ground Water: Part II." Colloidal Transport, EPA/600/M-91/040, 12pp.

Puls, R.W., and MJ. Barcelona.  1989a.   "Filtration of Ground Water Samples for Metals
Analysis." Hazardous Waste and Hazardous Materials, v. 6, No. 4.

Puls, R.W., and MJ. Barcelona.  1989b.  "Ground Water Sampling for Metals Analysis."
USEPA Superfund Ground Water Issue, EPA/504/4-89/001, 6 pp.

Sevee, J. (1991). "Methods and Procedures for Defining Aquifer Parameters," in D.M. Nielsen,
ed., Practical Handbook of Ground-Water Monitoring. Lewis Publishers, Chelsea, MI.

USEPA (1975). Manual of Water Well Construction Practices. USEPA Office of Water Supply,
Report No. EPA-570/9-75-001, 156 pp.

USEPA, (1985). "Handbook: Remedial Action at Waste Disposal Sites"; EPA/540/G-88/003;
U.S. EPA; Office of Emergency and Remedial Response; Washington, D.C.

USEPA,  (1986a).   "RCRA Groundwater Monitoring Technical  Enforcement Guidance
Document"; Office of Solid Waste and Emergency Response - 9950.1.

USEPA, (1986b).  "Test Methods for Evaluating Solid Waste - Physical/Chemical Methods";
EPA SW-846, 3rd edition; PB88-239-233;  U.S. EPA; Office of Solid Waste and Emergency
Response; Washington, D.C.

USEPA, (1986c).  "Superfund Public Health Evaluation Manual";  PB87-183-125; U.S. EPA;
Office of Emergency and Remedial Response; Washington, D.C. 20460.

USEPA, (1986d).  "Superfund Risk Assessment Information Directory"; PB87-188-918; U.S.
EPA; Office of Emergency and Remedial Response; Washington, D.C. 20460.

USEPA, (1988). "Guidance on Remedial Actions for Contaminated Groundwater at Superfund
Sites"; PB89-184-618; U.S. EPA; Office of Emergency and Remedial Response; Washington,
D.C.20460.
                                        115

-------
                                     Subpart E
USEPA, (1989). "Statistical Analysis of Groundwater Monitoring Data at RCRA Facilities-
Interim Final Guidance"; EPA/530-SW-89-026; U.S. EPA; Office of Solid Waste; Washington,
D.C.

USEPA,  (1989a).  "RCRA Facility Investigation (RFI) Guidance; Interim Final; Vol. I
Development  of  an  RFI  Work Plan  and General Considerations  for  RCRA Facility
Investigations"; PB89-200-299; U.S. EPA; Office of Solid Waste; Washington, D.C.

USEPA, (1989b).  "RCRA Facility Investigation (RFI) Guidance; Interim Final; Vol. II - Soil,
Ground Water and Subsurface Gas Releases"; PB89-200-299; U.S. EPA; Office of Solid Waste;
Washington, D.C.

USEPA, (1989c).   "Criteria for Identifying Areas of Vulnerable Hydrogeology Under the
Resource Conservation and Recovery Act, Interim Final. Appendix B  -Ground-Water Flow
Net/Flow Line Construction and Analysis."

USEPA,  (1989d).   "RCRA Facility Investigation (RFI) Guidance; Vol  IV:  Case Study
Examples;" PB89-200-299; U.S. EPA; Office of Solid Waste; Washington, D.C.

USEPA, (1989e).  "Practical Guide for Assessing and Remediating Contaminated Sites - Draft";
U.S. EPA; Waste Management Division,  Office of Solid Waste, 401  M Street, S.W.;
Washington, D.C.  May 1989.

USEPA, (1989f). "Handbook of Suggested Practices for the Design and Installation of Ground-
Water Monitoring Wells"; PB90-159-807; U.S EPA; Office of Research and Development;
Washington, D.C.

USEPA, (1990). "Handbook: Groundwater Vol I;" EPA/625/6-90/016a; U.S. EPA; Office of
Research and Development; Cincinnati, Ohio.

USEPA, (1991). "Handbook: Groundwater Vol II"; EP A/625/6-90/016b; U.S. EPA; Office of
Research and Development; Cincinnati, Ohio.

USEPA, (1992a).  "RCRA Ground-Water Monitoring: Draft Technical  Guidance"; EPA/530-R-
93-001; U.S. EPA; Office of Solid Waste; Washington, D.C. PB93-139-350.

USEPA, (1992b).  "Statistical Training Course for Ground-Water Monitoring Data Analysis",
EPA/530-R-93-003; U.S. EPA; Office of Solid Waste; Washington, D.C.

USEPA, (1992c).  "User Documentation of the Ground-Water Information Tracking System
(GRITS) with Statistical Analysis Capability, GRITSTAT Version 4.2;" EPA/625/11-91/002;
USEPA Office of Research and Development, Center for Environmental Research, ORD
Publications.
                                        116

-------
                    Ground-Water Monitoring and Corrective Action
USGS, (1989).  "Chapter C2, Computer Model of Two-Dimensional Solute Transport and
Dispersion in Groundwater";  L.F. Konikow and J.D. Bredehoeft; Book 7; U.S. Geological
Survey; U.S. Department of Interior.

Way, S.C., and C.R. McKee (1982).  "In-Situ Determination of Three-Dimensional Aquifer
Permeabilities." Ground Water, V. 20, No. 5.
                                        117

-------
Subpart E
   118

-------
       CHAPTER 6

       SUBPART F
CLOSURE AND POST-CLOSURE

-------
                                  CHAPTER 6
                                  SUBPART F

                            TABLE OF CONTENTS

6.1  INTRODUCTION	  322

62.    FINAL COVER DESIGN 40 CFR §258.60(a)	  322
      6.2.1  Statement of Regulation  	  322
      6.2.2  Applicability	  323
      6.2.3  Technical Considerations  	  323
            Infiltration Layer 	  324
                  Geomembranes	  329
            Erosion Layer	  330

63.    ALTERNATIVE FINAL COVER DESIGN 40 CFR §258.60(b)	  332
            6.3.1  Statement of Regulation  	  332
            6.3.2  Applicability	  332
            6.3.3  Technical Considerations  	  333
            Other Considerations 	  333
                  Drainage Layer	  333
                  Gas Vent Layer	  335
                  Biotic Layer	  336
            Settlement and Subsidence	  336
            Sliding Instability	  337

6A    CLOSURE PLAN 40 CFR  §258.60(c)-(d)	  338
      6.4.1  Statement of Regul ati on  	  338
      6.4.2  Applicability	  338
      6.4.3  Technical Considerations  	  338

6J.    CLOSURE CRITERIA 40 CFR §258.60(e)-(j)  	  339
      6.5.1  Statement of Regulation  	  339
      6.5.2  Applicability	  340
      6.5.3  Technical Considerations  	  341

6J>    POST-CLOSURE CARE REQUIREMENTS 40 CFR $258.61 	  342
      6.6.1  Statement of Regulation  	  342
      6.6.2  Applicability	  343
      6.6.3  Technical Considerations  	  343
                                      320

-------
6.7   POST-CLOSURE PLAN 40 CFR §258.61(c)-(e)  	  345
      6.7.1  Statement of Regulation 	  345
      6.7.2  Applicability	  346
      6.7.3  Technical Considerations 	  346

6.8 FURTHER INFORMATION	  348
      6.8.1  References	  348
      6.8.2  Organizations	  349
      6.8.3  Models	  349
      6.8.4  Databases  	  349
                                       321

-------
                                  CHAPTER 6
                                  SUBPART F
                      CLOSURE AND POST-CLOSURE
6.1 INTRODUCTION

The criteria for landfill closure focus on two central themes: (1) the need to establish low-
maintenance  cover  systems and  (2) the  need to  design a final cover that minimizes the
infiltration of precipitation into the waste.  Landfill closure technology, design, and maintenance
procedures continue to evolve as new geosynthetic materials become available, as performance
requirements become more specific, and as limited performance history becomes available for
the relatively small number of landfills that have been closed using current procedures and
materials.  Critical technical issues that must be faced by the designer include the:

•   Degree and rate of post-closure settlement and stresses imposed on  soil liner components;
•   Long-term durability and survivability of cover system;
•   Long-term waste decomposition and management of landfill leachate and gases; and
•   Environmental performance of the combined bottom liner and final cover system.

Full closure and post-closure care requirements apply to all MSWLF units that receive wastes
on or after October 9, 1993. For MSWLF  units that stop receiving wastes prior to October 9,
1993, only the final cover requirements of §258.60(a) apply.

*[NOTE:  EPA finalized several  revisions to 40 CFR Part 258 on October 1, 1993 (58 FR
51536) and issued a correction notice on October 14, 1993 (58 FR 53136). Questions regarding
the final rule  and requests for copies of the Federal Register notices should be made to the
RCRA/Superfund Hotline at (800) 424-9346.  These revisions delay the effective date for some
categories of landfills.  More  detail on the  content  of the revisions  is included in the
introduction.
6.2 FINAL COVER DESIGN
    40 CFR §258.60(a)

6.2.1  Statement of Regulation

    (a)    Owners or operators  of  all
MSWLF units must install a final cover
system  that is  designed  to minimize
infiltration and erosion.  The final cover
system must be designed and constructed
to:
    (1)    Have permeability less than or
equal to the permeability of any bottom
liner system or natural subsoils present,
or a permeability no greater than 1 x 10 5
cm/sec, whichever is less, and

    (2)    Minimize infiltration through
the closed MSWLF unit by the use of an
infiltration   layer   that   contains   a
minimum  of 18-inches of an earthen
material, and
                                        322

-------
                                Closure and Post-Closure
    (3)    Minimize erosion of the final
cover by the use of an erosion layer that
contains a minimum 6-inches of earthen
material  that is  capable of sustaining
native plant growth.

6.2.2  Applicability

These final cover requirements apply to all
MSWLF  units  required   to  close  in
accordance  with  Part  258,  including
MSWLF units that received wastes  after
October 9, 1991  but stopped  receiving
wastes  prior to October 9,  1993.   Units
closing during this two-year period are
required to install a final cover.

The final cover system required to close a
MSWLF unit, whether the unit is an existing
unit, a new unit, or a lateral  expansion of an
existing unit,  must be  composed of an
infiltration layer that is a minimum of 18
inches thick, overlain by an  erosion layer
that is a minimum of 6 inches thick.

The final cover should minimize, over the
long term, liquid infiltration  into the waste.
The final  cover  must  have  a  hydraulic
conductivity less than or  equal  to any
bottom liner  system or natural  subsoils
present to prevent a "bathtub" effect.  In no
case can the final cover have a  hydraulic
conductivity greater than 1 x 10"5 cm/sec
regardless of the permeability of underlying
liners or natural  subsoils.   If a synthetic
membrane is in the bottom liner, there must
be a flexible membrane liner (FML) in the
final cover to achieve a permeability that is
less than or equal to the permeability of the
bottom liner. Currently, it is not possible to
construct   an   earthen   liner   with  a
permeability less than or equal to a synthetic
membrane.
In  approved  States,  an  alternate cover
system may be approved by the Director
(see Section 6.3).

6.2.3  Technical Considerations

Design  criteria for a final cover system
should be selected to:

•   Minimize infiltration of precipitation
    into the waste;

•   Promote good surface drainage;

•   Resist erosion;

•   Control landfill gas migration and/or
    enhance recovery;

•   Separate  waste  from vectors  (e.g.,
    animals and insects);

•   Improve aesthetics;

•   Minimize long-term maintenance;

•   Protect   human    health   and   the
    environment; and

•   Consider final use.

The first three points are directly related to
the regulatory requirements.   The  other
points typically are considered in designing
cover systems for landfills.

Reduction of infiltration in a well-designed
final cover system is achieved through good
surface drainage and run-off with minimal
erosion, transpiration of water by plants in
the vegetative cover  and root zone, and
restriction of  percolation through earthen
material.   The  cover  system should be
designed to provide the  desired level  of
                                         323

-------
                                       Subpart F
long-term  performance  with   minimal
maintenance. Surface water run-off should
be properly controlled to prevent excessive
erosion and soil loss.  Establishment of a
healthy vegetative layer is key to protecting
the  cover  from  erosion.     However,
consideration   also  must  be   given  to
selecting plant  species that are  not deeply
rooted because they  could damage  the
underlying infiltration layer. In addition,
the cover system should be geotechnically
stable  to prevent failure,  such  as  sliding,
that may  occur between  the erosion and
infiltration layers, within these  layers,  or
within the waste. Figure 6-1 illustrates the
minimum requirements for the final cover
system.

Infiltration Layer

The infiltration layer must  be at least  18
inches thick and consist of earthen material
that   has   a    hydraulic   conductivity
(coefficient of permeability) less  than  or
equal to the hydraulic  conductivity of any
bottom liner system  or natural subsoils.
MSWLF units  with poor or non-existent
bottom   liners   possessing   hydraulic
conductivities greater than 1 x 10"5 cm/sec
must have an infiltration layer that  meets the
1  x 10"5  cm/sec  minimum requirement.
Figure 6-2 presents an example of a final
cover  with a hydraulic conductivity less
than or equal to the hydraulic conductivity
of the bottom liner system.

For units that have a composite liner with a
FML, or naturally occurring soils with very
low permeability (e.g., 1 x  10"8 cm/sec), the
Agency anticipates that the infiltration layer
in the  final cover will include a synthetic
membrane as part of the final cover.  A final
cover  system  for a MSWLF unit with a
FML  combined  with  a  soil   liner and
leachate collection  system is presented in
Figure 6-3a.  Figure 6-3b  shows a final
cover system for a MSWLF  unit that has
both a double FML  and double leachate
collection system.

The earthen material used for the infiltration
layer should be free of rocks, clods, debris,
cobbles,   rubbish,  and  roots  that may
increase  the  hydraulic  conductivity  by
promoting preferential  flow  paths.   To
facilitate run-off while minimizing erosion,
the surface  of the compacted soil should
have a minimum slope of 3 percent and a
maximum slope of 5 percent after allowance
for settlement. It is critical that side slopes,
which are frequently greater than 5 percent,
be evaluated for erosion potential.

Membrane and clay layers should be placed
below  the   maximum  depth  of  frost
penetration  to  avoid freeze-thaw effects
(U.S. EPA,  1989b).   Freeze-thaw effects
may include  development of microfractures
or realignment of interstitial fines, which
can increase the hydraulic conductivity of
clays by more than an order of magnitude
(U.S. EPA,  1990). Infiltration layers may
be  subject  to desiccation,  depending on
climate and soil water retention in  the
erosion layer.  Fracturing and volumetric
shrinking  of the clay due to water loss may
increase the hydraulic conductivity of the
infiltration  layer.  Figure  6-4  shows  the
regional average depth of frost penetration;
however, these values should not be used to
find the maximum depth of frost penetration
for a  particular  area of concern  at  a
particular  site. Information regarding the
maximum depth of frost penetration for a
particular area can be obtained from the Soil
Conservation   Service,   local   utilities,
construction    companies,   and    local
universities.
                                         324

-------
                                Closure and Post-Closure
Erosion Layer:
 Min. 6" Soil
   • Infiltration Layer:
Min. 18" Compacted Soil (1 x
      10-5 cm/sec)
                                                    Existing Subgrade
                                     Figure 6-1
                Example of Minimum Final Cover Requirements
                                         325

-------
                                      Subpart F
Erosion Layer:           ^^^^^^^^^^^^^^^^            Infiltration Layer:
 Min. 6" Soil ^      '  ^^F^^^^""""^^"^^^^^^^^  -  Min-18" Compacted Soil (1 x 10-6
                                                                  cm / sec)
              =?/                                       . «=
                                                               2 Feet Compacted
                                                             Soil (1 x 10-6 cm/sec)
                                    Figure 6-2
      Example of Final Cover With Hydraulic Conductivity(K) < K of Liner
                                        326

-------
  Erosion Layer
To sustain vegetation
                                  FML
Infiltration Layer: Min. 18"
 compacted soil (1 x 10-5
      cm/sec)
                                                                         FML
                                                                    Feet Compacted Soil
                                                                     (1 x 10-7 cm/sec)
                                    Figure 6-3a
        Example of Final Cover Design for a MSWLF Unit With a FML
                         and Leachate Collection System
    Erosion Layer:
 To sustain vegetation
                  FML
                                   2 Feet Compacted
                                  Soil (1 x 10-7 cm/sec)
      Infiltration Layer: Min. 18"
         compacted soil (1 x
            10-5cm/sec)
                                                                              FML
                                                                    12" Compacted
                                                                  Soil (1 x 1.0-7 cm/sec)
                                    Figure 6-3b
 Example of Final Cover Design for a MSWLF Unit With a Double FML and
                           Leachate Collection System
                                        327

-------
                            Subpart F
Source: USEPA (1989)
                          Figure 6-4
         Regional Depth of Frost Penetration in Inches
                              328

-------
                                Closure and Post-Closure
The  infiltration  layer  is  designed  and
constructed in a manner similar to that used
for soil liners (U.S. EPA, 1988), with the
following differences:

•   Because  the cover  is generally  not
    subject to large overburden loads, the
    issue of compressive stresses  is  less
    critical unless post-closure land use will
    entail construction of objects that exert
    large amounts of stress.

•   The soil  cover is subject to loadings
    from  settlement   of   underlying
    materials.   The extent  of  settlement
    anticipated  should be evaluated and a
    closure and post-closure maintenance
    plan should be designed to compensate
    for the effects of settlement.

•   Direct   shear  tests  performed   on
    construction   materials  should   be
    conducted at lower shear stresses than
    those used for liner system designs.

The design of a final cover is site-specific
and the relative  performance of cover design
options may be  compared and evaluated by
the  HELP  (Hydrologic  Evaluation  of
Landfill Performance) model.  The HELP
model  was developed by the U.S.  Army
Corps of Engineers for the U.S. EPA and is
widely   used   for  evaluating   expected
hydraulic   performance   of   landfill
cover/liner systems (U.S. EPA, 1988).

The  HELP  program  calculates   daily,
average, and   peak estimates  of  water
movement across, into, through, and out of
landfills.  The   input parameters for the
model include soil properties, precipitation
and other climatological data, vegetation
type,   and  landfill  design information.
Default  climatologic and soil  data  are
available  but   should  be   verified  as
reasonable for the site modeled.  Outputs
from the model include precipitation, run-
off, percolation  through the base of each
cover layer subprofile, evapotranspiration,
and lateral drainage from each profile. The
model also calculates the maximum head on
the barrier soil layer of each subprofile and
the maximum and minimum soil moisture
content of the evaporative zone.  Data from
the model are presented in a tabular report
format and  include the input parameters
used  and a summary of the  simulation
results.   Results  are presented  in  several
tables of daily, monthly, and annual totals
for each year specified. A summary of the
outputs also is produced, including average
monthly totals,  average annual  totals, and
peak  daily values for several  simulation
variables (U.S. EPA, 1988).

The HELP model may be used to estimate
the hydraulic  performance of  the cover
system designed for a MSWLF unit.  Useful
information  provided by the HELP model
includes  surface run-off,  duration and
quantity of water storage within the erosion
layer, and net infiltration through the cover
system to evaluate  whether  leachate will
accumulate  within the landfill.  For the
model to be used properly, the HELP Model
User's Guide and documentation should be
consulted.

Geomembranes

If a geomembrane is used as an infiltration
layer, the geomembrane should  be  at least
20  mils (0.5 mm) in thickness, although
some geomembrane materials may  need to
be  a greater thickness (e.g.,  a minimum
thickness of 60 mils is recommended for
HOPE because of the difficulties in making
consistent field  seams in thinner material).
                                        329

-------
                                       Subpart F
Increased thickness  and tensile strengths
may be necessary to prevent failure under
stresses caused by construction and waste
settlement  during the  post-closure  care
period.  The strength, resistance to sliding,
hydraulic performance, and actual thickness
of  geomembranes   should   be  carefully
evaluated.  The quality and performance of
some textured  sheets may be difficult to
evaluate due to the variability  of  the
textured surface.

Erosion Layer

The thickness of  the  erosion  layer  is
influenced by depth of frost penetration and
erosion potential.  This layer is also used to
support vegetation.  The influence of frost
penetration was discussed previously on
page 6-3.

Erosion   can   adversely   affect    the
performance of the final cover of a MSWLF
unit  by   causing   rills   that   require
maintenance  and repair.   As  previously
stated, a healthy vegetative layer can protect
the cover from erosion;  conversely, severe
erosion can affect the vegetative  growth.
Extreme erosion may lead to the exposure of
the infiltration layer, initiate or contribute to
sliding  failures,  or  expose the waste.
Anticipated erosion  due to  surface water
run-off for given design  criteria  may be
approximated using  the USDA Universal
Soil Loss Equation (U.S. EPA, 1989a). By
evaluating  erosion loss,  the design may be
optimized to reduce maintenance  through
selection of the best available soil materials
or by initially adding excess soil to increase
the time required before maintenance is
needed. Parameters in the equation include
the following:
           X = RKLSCP

where      X = Soil loss (tons/acre/year)
           R = Rainfall erosion index
           K = Soil erodibility index
           L = Slope length factor
           S = Slope gradient factor
           C = Crop management factor
           P = Erosion control practice.

Values for the Universal Soil Loss Equation
parameters may be obtained from the U. S.
Soil Conservation Service (SCS) technical
guidance  document  entitled "Predicting
Rainfall Erosion  Losses, Guidebook 537"
(1978),  available at  local SCS offices
located throughout the United  States. State
or local SCS offices can provide factors to
be used in the soil loss equation that are
appropriate to a given area of the country.
Figure 6-5 can be used to find the soil loss
ratio due to the slope  of the site  as used in
the Universal  Soil Loss Equation.   Loss
from wind erosion can  be determined by the
following equation (U.S. EPA, 1989a):
           X = I'K'C'L'V
where
X =
r =
K' =
c =
L' =
V' =
Annual wind erosion
Field roughness factor
Soil erodibility index
Climate factor
Field length factor
Vegetative cover factor.
A vegetative cover not only improves the
appearance of the  site, but it also controls
erosion of the final cover; a vegetated cover
may require  only  minimal maintenance.
The vegetation component of the erosion
layer should have the following
                                         330

-------
                             Closure and Post-Closure
       0      100
200      300
400      500      600      700
                                                                            800
Source L'SEPA. 1989
                                   iOpe Length (Feet)
                                  Figure 6-5
                          Soil Erosion Due to Slope
                                       331

-------
                                       Subpart F
specifications
EPA, 1989b):
and  characteristics  (U.S.
•   Locally adapted perennial plants that
    are resistant to drought and temperature
    extremes;

•   Roots  that will not disrupt the low-
    permeability layer;

•   The ability to thrive in low-nutrient soil
    with minimum nutrient addition;

•   Sufficient  plant density to minimize
    cover soil erosion;

•   The ability to survive and function with
    little or no  maintenance (i.e., self-
    supportive); and

•   Sufficient  variety of plant species  to
    continue to achieve these characteristics
    and specifications over time.

The use of deep-rooted  shrubs and trees is
generally inappropriate  because  the root
systems may penetrate the infiltration layer
and   create   preferential   pathways   of
percolation.  Plant species with fibrous  or
branching root systems are suited for use at
landfills, and can include a large variety  of
grasses, herbs (i.e., legumes), and shallow-
rooted plants.  The suitable species in a
region will vary, dependent on climate and
site-specific factors such as soil type and
slope gradient  and aspect.   The timing  of
seeding (spring or fall in most climates) is
critical  to  successful   germination and
establishment of the vegetative cover (U.S.
EPA,  1989b).  Temporary  winter  covers
may be grown from fast-growing seed stock
such as winter rye.
Selection of the soil for the vegetative cover
(erosion layer) should include consideration
of soil type, nutrient and pH levels, climate,
species of the vegetation selected, mulching,
and  seeding  time.   Loamy  soils with  a
sufficient organic  content generally  are
preferred.  The balance  of clay,  silt, and
sand in loamy soils provides an environment
conducive  to  seed  germination and  root
growth (USEPA,  1988).

The Director of an approved State can allow
alternate  designs to address  vegetative
problems (e.g., the use of pavement or other
material) in areas that are not capable of
sustaining plant growth.
                                6.3 ALTERNATIVE FINAL COVER
                                   DESIGN
                                   40 CFR §258.60(b)

                                6.3.1  Statement of Regulation

                                   (b)    The Director of an approved
                                State may approve  an alternative final
                                cover design that includes:

                                   (1)    An  infiltration  layer  that
                                achieves  an  equivalent  reduction   in
                                infiltration  as  the  infiltration  layer
                                specified in paragraphs (a)(l) and (a)(2)
                                of this section, and

                                   (2)    An erosion layer that provides
                                equivalent protection  from  wind   and
                                water  erosion  as  the  erosion  layer
                                specified in (a)(3) of this section.

                                6.3.2 Applicability

                                The Director of an  approved State  may
                                approve alternative final cover systems that
                                can achieve equivalent performance as
                                         332

-------
                                Closure and Post-Closure
the   minimum   design   specified   in
§258.60(a).  This provides an opportunity to
incorporate   different  technologies   or
improvements into  cover designs, and to
address site-specific conditions.

6.3.3  Technical Considerations

An alternative material and/or an alternative
thickness  may be used for an infiltration
layer   as  long  as  the infiltration layer
requirements specified in §258.60(a)(l) and
(a)(2) are met.

For example, an armored surface (e.g., one
composed of cobble-rich soils or soils  rich
in weathered rock fragments) could be  used
as an  alternative to the six-inch  erosion
layer.   An armored surface, or hardened cap,
is generally used in arid regions or on steep
slopes  where   the  establishment   and
maintenance of vegetation may be hindered
by lack of soil or excessive run-off

The materials used for an armored surface
typically are (U.S. EPA, 1989b):

•   Capable  of protecting the underlying
    infiltration   layer   during   extreme
    weather events of rainfall and/or wind;

•   Capable of accommodating settlement
    of  the  underlying material without
    compromising the component;

•   Designed with a  surface slope that is
    approximately   the   same   as  the
    underlying soil  (at least  2  percent
    slope); and

•   Capable of controlling the rate of soil
    erosion.
The erosion layer may be made of asphalt or
concrete.  These materials promote run-off
with negligible erosion. However, asphalt
and concrete  deteriorate  due to thermal
expansion and due to deformation caused by
subsidence.  Crushed rock may be spread
over  the  landfill  cover  in  areas where
weather  conditions such  as  wind, heavy
rain, or temperature extremes commonly
cause  deterioration of vegetative covers
(U.S. EPA, 1989b).

Other Considerations

Additional Cover System Components

To reduce the generation of post-closure
leachate  to  the greatest  extent possible,
owners   and   operators  can  install  a
composite cover made of a geomembrane
and a  soil component  with low hydraulic
conductivity.   The hydraulic properties of
these components are discussed in Chapter
4 (Subpart D).

Other components that may be used in the
final cover system include a drainage layer,
a gas vent layer, and a biotic barrier layer.
These components are discussed in the
following sections and are shown in Figure
6-6.

Drainage Layer

A permeable drainage layer, constructed of
soil or geosynthetic drainage material, may
be  constructed between the erosion layer
and the underlying infiltration layer.  The
drainage  layer in a  final cover  system
removes   percolating   water  that   has
infiltrated through the erosion  layer after
surface  run-off  and  evapotranspiration
losses. By removing water in contact with
the low-permeability layer, the potential for
                                         333

-------
 20-mii FML—
     or
60-mi I HDPE
                 60 cm
                 30cm

                 30cm
60cm
                                                                          \ N N S \ -WS
                                                                          / f S /->-.••—
                                                                          N. \ \ S X^^S
}
                                                                     Vegetation/
                                                                     Soil Top Layer

                                                                     Filler Layer

                                                                     Biotic Barrier Layer

                                                                     Drainage Layer
                                                                         - Low-Permeability
                                                                          FML/Soil Layer

                                                                     Gas Venting Layer

                                                                     Waste
                                                 Figure 6-6
                                Example of an Alternative Final Cover Design

-------
                                 Closure and Post-Closure
leachate generation is diminished. Caution
should be taken when using a drainage layer
because this layer may prematurely draw
moisture from the  erosion  layer that is
needed to sustain vegetation.

If a drainage  layer is used,  owners  or
operators   should  consider  methods  to
minimize physical clogging of the drainage
layer by root systems or soil particles.  A
filter  layer,  composed of either  a low
nutrient soil or geosynthetic material, may
be placed between the drainage layer and
the cover soil to help minimize clogging.

If granular drainage layer  material is used,
the filter layer should be at least 12  in. (30
cm) thick with a hydraulic conductivity in
the range of 1 x  10"2  cm/sec to 1  x 10"3
cm/sec. The layer should be sloped at least
3 percent at the bottom of the layer.  Greater
thickness and/or slope may be necessary to
provide  sufficient  drainage   flow   as
determined by site-specific  modeling (U.S.
EPA, 1989b).  Granular drainage material
will vary from site to site depending on the
type of material that is locally available and
economical to use. Typically, the material
should be  no coarser than 3/8 inch (0.95
cm), classified according  to the Universal
Soil  Classification System (USCS) as type
SP, smooth and rounded, and free of debris
that    could   damage    an    underlying
geomembrane (U.S. EPA,  1989b).

Crushed stone generally is not appropriate
because of the sharpness of the particles.  If
the available drainage  material is of poor
quality, it may be necessary to increase the
thickness and/or slope of the drainage layer
to maintain adequate drainage.  The HELP
model can be used as an analytical  tool to
evaluate the relative expected performance
of alternative final cover designs.

If geosynthetic materials  are  used as  a
drainage layer, the fully saturated effective
transmissivity should be the equivalent of
12 inches of soil (30 cm) with a hydraulic
conductivity range of 1 x 10"2 cm/sec to 1 x
10"3   cm/sec.     Transmissivity  can  be
calculated  as  the hydraulic  conductivity
multiplied by the drainage layer thickness.
A filter layer (preferably  a non-woven
needle punch fabric) should be placed above
the  geosynthetic  material  to  minimize
intrusion and clogging by roots  or by soil
material from the top layer.

Gas Vent Layer

Landfill gas collection systems serve  to
inhibit gas migration.  The gas  collection
systems  typically  are  installed directly
beneath the infiltration layer.  The function
of a gas vent layer is to collect combustible
gases  (methane)  and  other  potentially
harmful gases (hydrogen sulfide) generated
by micro-organisms during biological decay
of organic wastes, and to divert these gases
via a pipe system through the infiltration
layer.     A   more   detailed  discussion
concerning landfill gas, including the use of
active and passive collection systems, is
provided in Chapter 3 (Subpart C).

The gas vent layer is usually 12 in. (30 cm)
thick and should be located between  the
infiltration  layer  and  the waste  layer.
Materials used in construction of the gas
vent layer should be medium to coarse-
grained porous materials such as those used
in  the drainage   layer.    Geosynthetic
materials may be  substituted for granular
materials  in the  vent  layer if equivalent
performance can be demonstrated. Venting
                                         335

-------
                                       Subpart F
to an  exterior  collection point  can be
provided by means such as horizontal pipes
patterned laterally throughout the gas vent
layer, which channel gases to vertical risers
or lateral headers.  If vertical risers are used,
their number should be minimized (as they
are frequently vandalized) and located at
high points in the cross-section (U.S. EPA,
1989b).  Condensates will form within the
gas collection pipes; therefore, the  design
should address drainage of condensate to
prevent blockage by its accumulation in low
points.

The  most obvious potential problem  with
gas collection systems is the possibility of
gas vent pipe penetrations through the cover
system. Settlement within the landfill may
cause   concentrated   stresses   at   the
penetrations,  which   could  result   in
infiltration  layer  or pipe failure.    If  a
geomembrane is used  in the  infiltration
layer, pipe sleeves, adequate flexibility and
slack material should be provided at these
connections     when     appropriate.
Alternatively, if  an active gas control
system  is planned,  penetrations may be
carried out through the sides of the cover
directly  above the liner  anchor trenches
where   effects  of  settlement   are  less
pronounced.  The gas collection system also
may be connected to the leachate collection
system, both to  vent gases that may form
inside the leachate  collection pipes and to
remove gas condensates that form within the
gas collection pipes. This method generally
is not preferred because if the leachate
collection pipe is full, gas will not be able to
move through the  system.   Landfill  gas
systems  are  also discussed in Chapter  3
(Subpart C).
Biotic Layer

Deep plant roots or burrowing animals
(collectively  called  biointruders)  may
disrupt the drainage and the low hydraulic
conductivity layers, thereby interfering with
the drainage capability of the layers. A 30-
cm  (12-inch) biotic  barrier  of cobbles
directly beneath the erosion layer may stop
the penetration of some deep-rooted plants
and  the invasion of  burrowing animals.
Most research  on  biotic barriers has been
done in, and  is applicable to arid areas.
Geosynthetic  products that  incorporate  a
time-released herbicide into the matrix or on
the surface of the polymer also may be used
to retard plant roots. The longevity of these
products requires  evaluation if  the  cover
system  is to serve for longer than 30 to 50
years (USEPA, 1991).

Settlement and Subsidence

Excessive settlement and subsidence, caused
by decomposition and consolidation of the
wastes,  can impair the integrity of the final
cover system.  Specifically, settlement can
contribute to:

•   Ponding of surface water on the cap;

•   Disruption of gas  collection  pipe
    systems;

•   Fracturing   of  low   permeability
    infiltration layers; and

•   Failure of geomembranes.

The degree and rate of waste settlement are
difficult  to   estimate.    Good  records
regarding the type, quantity, and location of
waste materials disposed will improve the
estimate.  Settlement due to consolidation
                                         336

-------
                                 Closure and Post-Closure
may be minimized by compacting the waste
during daily operation of the landfill unit or
by landfilling baled waste.  Organic wastes
will continue  to degrade  and  deteriorate
after closure of the landfill  unit.

Several models have  been developed  to
analyze   the   process   of  differential
settlement. Most models equate the layered
cover to  a  beam  or column undergoing
deflection due to various loading conditions.
While these models are useful to designers
in understanding the qualitative relationship
between  the  various  land disposal  unit
characteristics  and in  identifying   the
constraining factors, accurate quantitative
analytical methods have not been developed
(U.S.  EPA,  1988).

If the amount of total settlement can  be
estimated,  either   from   an   analytical
approach  or from empirical relationships
from data collected  during the operating life
of the facility, the designer should attempt
to estimate the potential strain imposed  on
the cover system components.  Due to the
uncertainties  inherent  in  the  settlement
analysis, a biaxial strain calculation should
be  sufficient to estimate the stresses that
may be imposed on the cover system.  The
amount of strain that a liner is capable of
enduring may  be as low as  several percent;
for geomembranes, it may be 5 to 12 percent
(U.S.  EPA,  1990).   Geomembrane testing
may  be  included as  part of the design
process to estimate  safety factors against
cover system failure.

The cover system may be designed with a
greater thickness and/or slope to compensate
for settlement  after closure. However, even
if settlement and subsidence are considered
in the design  of the final  cover, ponding
may still occur after closure and can be
corrected during post-closure maintenance.
The  cost   estimate   for  post-closure
maintenance   should  include  earthwork
required to regrade the final  cover due to
total and differential settlements. Based on
the  estimates  of total and differential
settlements  from  the  modeling  methods
described  earlier, it may be appropriate to
assume that a certain percentage of the total
area needs regrading and then incorporate
the  costs into  the  overall  post-closure
maintenance cost estimate.

Sliding Instability

The slope  angle, slope length, and overlying
soil load  limit the stability of component
interfaces   (geomembrane   with   soil,
geotextile, and geotextile/soil). Soil water
pore pressures developed along interfaces
also can dramatically reduce stability.  If the
design slope is steeper than  the  effective
friction angles between the material, sliding
instability generally will occur.   Sudden
sliding has the potential to cause tears in
geomembranes, which require  considerable
time and expense to repair.  Unstable slopes
may require remedial measures to improve
stability as a means  of offsetting  potential
long-term maintenance costs.

The friction angles between various media
are best determined by laboratory direct
shear tests that represent the design loading
conditions.  Methods to improve stability
include using designs  with flatter slopes,
using   textured   material,  constructing
benches in the cover system, or reinforcing
the cover soil  above the membrane  with
geogrid or  geotextile  to minimize  the
driving force  on the interface of concern.
Methods for applying these design features
can be found in (U.S. EPA  1989), (U.S.EPA
1991), and (Richardson and Koerner 1987).
                                         337

-------
                                      Subpart F
6.4 CLOSURE PLAN
    40 CFR §258.60(c)-(d)

6.4.1  Statement of Regulation

    (c)     The owner or operator must
prepare a  written  closure  plan  that
describes the steps necessary to close all
MSWLF units at any point during their
active life in accordance with the cover
design requirements in §258.60(a) or (b),
as applicable.   The  closure  plan,  at a
minimum, must include  the following
information:

    (1)     A  description  of  the final
cover,  designed  in  accordance with
§258.60(a)   and   the  methods  and
procedures to be used to install the cover;

    (2)     An estimate of the largest area
of the MSWLF unit ever requiring a final
cover as required under §258.60(a) at any
time during the active life;

    (3)     An estimate of the maximum
inventory of wastes ever on-site over the
active life of the landfill facility; and

    (4)     A schedule for completing all
activities necessary to satisfy the closure
criteria in §258.60.

    (d)    The owner or operator must
notify the  State Director that a closure
plan has been prepared and placed in the
operating  record  no  later  than   the
effective date of this part, or by the initial
receipt of waste, whichever is later.

6.4.2  Applicability

An owner or operator of any MSWLF unit
that receives wastes on or after October 9,
1993, must prepare a closure plan and place
the plan in the operating record.  The plan
must describe specific steps and activities
that will be followed to close the unit at any
time after it first receives waste through the
time it reaches its waste disposal capacity.

The closure plan must include at least the
following information:

•   A description of the final cover and the
    methods and procedures to be used to
    install the cover;

•   An estimate of the largest area that will
    have to be covered (typically this is the
    area  that will exist when the final full
    capacity is attained); and

•   A schedule for completing closure.

The  area  requiring  cover  should  be
estimated for the operating  period  from
initial receipt of waste through closure.

The closure  plan must be  prepared  and
placed in  the  operating  record  before
October 9, 1993 or by the initial receipt of
waste, whichever is  later.  The owner or
operator  must notify the  State Director
when the plan  has  been  completed  and
placed in the operating record.

6.4.3 Technical Considerations

The closure plan is a critical document that
describes the steps that an owner or operator
will  take to ensure that all  units will be
closed in a manner  that is protective of
human health and the environment.  Closure
plans provide the basis for cost estimates
that in turn establish the amount of financial
responsibility that must be demonstrated.
                                         338

-------
                                Closure and Post-Closure
The closure plan must describe all areas of
the MSWLF unit that are subject to Part 258
regulations  and  that  are  not closed  in
accordance with §258.60.  Portions of the
landfill unit that have not received a final
cover must be included in the estimate. The
area to be covered at any point during the
active life of the operating unit  can be
determined   by   examining  design  and
planned  operation  procedures  and  by
comparing the procedures with construction
records,  operation  records,   and  field
observations. Units are operated frequently
in phases, with some phases conducted on
top of previously deposited waste.  If the
owner or operator routinely closes landfill
cells  as they are filled, the plan should
indicate the greatest number of cells open at
one time.

The estimate  must account for the maximum
amount of waste on-site that may need to be
disposed in the MSWLF unit over the life of
the facility (this includes any waste on-site
yet to be disposed). The maximum volume
of waste ever on-site can be estimated from
the maximum capacity of each unit and any
operational procedures that may  involve
transfer of wastes to  off-site  facilities.
Where insufficient design, construction, and
operational records are  found, areas and
volumes may be estimated from topographic
maps  and/or aerial photographs.

Steps that may  be included in the closure
plan are as  follows:

•   Notifying State Director  of intent to
    initiate closure §258.60(e);

•   Determining  the area to receive final
    cover;

•   Developing the closure schedule;
•   Preparing    construction    contract
    documents and securing a contractor;

•   Hiring   an   independent  registered
    professional   engineer  to  observe
    closure   activities    and   provide
    certification;

•   Securing borrow material;

•   Constructing the cover system;

•   Obtaining signed certificate and placing
    it in operating record;

•   Notifying State Director that certificate
    was placed in operating record; and

•   Recording notation in  deed to land  or
    other similar instrument.

The  closure plan   should   include  a
description of the final cover system and the
methods and procedures that will be used to
install  the  cover.  The  description of the
methods, procedures, and  processes  may
include design  documents;  construction
specifications for  the final cover system,
including erosion control measures; quality
control   testing  procedures   for   the
construction   materials;    and   quality
assurance  procedures for construction.  A
general discussion of  the methods  and
procedures   for   cover  installation  is
presented in Section 6.3.3.
6.5 CLOSURE CRITERIA
    40 CFR §258.60(e)-(j)

6.5.1  Statement of Regulation

    (e)     Prior to beginning closure of
each  MSWLF  unit  as  specified   in
                                         339

-------
                                     Subpart F
§258.60(f), an owner or operator must
notify the State Director that a notice of
the intent to close  the unit  has been
placed in the operating record.

    (f)    The owner or operator must
begin closure activities of each MSWLF
unit no later than 30 days after the date
on which  the MSWLF unit receives  the
known final receipt  of wastes or, if  the
MSWLF unit has remaining capacity and
there is a reasonable likelihood that  the
MSWLF  unit  will  receive  additional
wastes, no later  than one year after  the
most recent  receipt of wastes. Extensions
beyond  the  one-year  deadline  for
beginning closure may be granted by  the
Director  of an  approved  State  if  the
owner or operator demonstrates that the
MSWLF unit has the capacity to receive
additional wastes and the  owner   or
operator has taken and will continue to
take all steps necessary to prevent threats
to human health and  the environment
from the unclosed MSWLF unit.

    (g)  The owner  or  operator  of  all
MSWLF  units  must complete closure
activities  of each  MSWLF  unit   in
accordance  with the  closure plan  within
180  days following the  beginning  of
closure as  specified in paragraph  (f).
Extensions of the closure period may be
granted by the Director of an approved
State  if   the  owner   or  operator
demonstrates that  closure  will,   of
necessity, take longer than 180 days and
he has taken and will continue to take all
steps to prevent threats to human health
and the environment from the unclosed
MSWLF unit.

   (h) Following closure of each MSWLF
unit, the owner or operator must
notify   the  State  Director  that  a
certification, signed by an independent
registered   professional  engineer  or
approved by Director of an  approved
State, verifying that closure  has been
completed in accordance with the closure
plan, has been placed in  the  operating
record.

    (i)(l) Following   closure   of  all
MSWLF units, the owner or operator
must record a notation on the deed to the
landfill  facility property, or some other
instrument that is normally  examined
during title search, and notify the  State
Director that  the notation  has been
recorded and a copy has been placed in
the operating record.

    (2)    The notation on the deed must
in  perpetuity  notify  any  potential
purchaser of the property  that:

    (i)     The  land has been  used as a
landfill facility; and

    (ii)    Its  use   is restricted  under
§258.61(c)(3).

    (j)   The  owner  or operator  may
request  permission from the Director of
an approved State to remove the notation
from the deed if all wastes are removed
from the facility.

6.5.2 Applicability

These closure requirements  are applicable to
all MSWLF units that receive wastes on or
after October  9,  1993.   The  owner or
operator is required to:

•   Notify the State Director of the intent
    to close;
                                       340

-------
                                Closure and Post-Closure
•  Begin closure within 30 days of the last
   receipt  of waste  (or 1 year if there is
   remaining capacity and it is likely that it
   will be used);

•  Complete  closure within  180  days
   following the beginning of closure (in
   approved States,  the period of time to
   begin  or complete closure  may  be
   extended by the Director);

•  Obtain a certification, by an independent
   registered professional engineer,  that
   closure was  completed in accordance
   with the closure plan;

•  Place the certificate in the operating
   record and notify the State Director; and

•  Note  on  a  deed  (or  some  other
   instrument) that the land was used as a
   landfill  and  that  its use  is restricted.
   Should all wastes be removed from the
   unit in an approved State, the owner or
   operator may request permission from
   the Director to remove the note on the
   deed.

6.5.3  Technical Considerations

Closure activities must begin within 30 days
of the last receipt of waste  and must be
completed within 180 days. Some MSWLF
units, such as those in seasonal population
areas, may have remaining capacity but will
not receive the  next load  of waste  for a
lengthy period  of time.   These MSWLF
units must receive waste within one year or
they must  close.  Extensions to  both  the
1-year and the 180-day requirements may be
available to owners or operators of MSWLF
units in approved States. An extension may
be granted if the owner or
operator can  demonstrate  that  there  is
remaining capacity or that additional time is
needed   to  complete   closure.    These
extensions  could  be  granted  to  allow
leachate  recirculation   or  to  allow  for
settlement.  The owner  or operator must
take,  and  continue  to take,  all  steps
necessary to prevent threats to human health
and the  environment from the unclosed
MSWLF unit.  In general, this requirement
should  be  established  for  a  unit  in
compliance with the requirements of Part
258.  The owner or operator may need to
demonstrate how access to the unclosed unit
will be controlled prior to closure or receipt
of waste and how the various environmental
control   and   monitoring  systems   (e.g.,
surface  run-off, surface run-on, leachate
collection, gas control system, and ground-
water and gas monitoring) will be operated
and  maintained while  the unit remains
unclosed.

Following closure of each MSWLF unit, the
owner or operator must have a certification,
signed  by  an  independent   registered
professional engineer, verifying closure. In
approved States, the Director can approve
the certification.  The  certificate  should
verify that closure  was  completed  in
accordance with the closure plan.   This
certification should be based on knowledge
of the  closure  plan, observations made
during  closure,  and  documentation  of
closure activities provided by the owner or
operator.  The signed certification must be
placed in the operating record and the State
Director  must  be  notified   that  the
certification was completed and placed in
the record.

After closure  of all units at a MSWLF
facility, the owner or operator must record
a  notation in the  deed,  or in records
                                         341

-------
                                     Subpart F
typically examined during a title search, that
the property was used as a MSWLF unit and
that  its use  is  restricted under 40  CFR
§258.61(c)(3).  Section 258.61(c)(3) states:

"...  Post-closure use of the property  shall
not disturb the integrity of the final cover,
liner(s), or any other components of the
containment systems or the function of the
monitoring systems  unless necessary to
comply with the  requirements  of  Part
258...and...  The Director of an  approved
State may  approve any other disturbance if
the  owner or operator demonstrates  that
disturbance of the final cover, liner, or other
component of  the  containment system,
including  any removal of waste, will not
increase the potential threat to human health
or the environment."

These restrictions are described further in
Section 6.7  (Post-Closure Plan)  of  this
document.

The  owner   or  operator   may   request
permission from the Director of an approved
State to remove the notation to a deed.  The
request should  document that all  wastes
have been  removed from the facility. Such
documentation may  include photographs,
ground-water and soil testing in the area
where wastes were deposited, and reports of
waste removal activity.
6.6 POST-CLOSURE CARE
    REQUIREMENTS
    40 CFR §258.61

6.6.1  Statement of Regulation

   (a) Following closure of each MSWLF
unit, the owner or operator must conduct
post-closure care. Post-closure
care  must be  conducted for 30 years,
except as provided under paragraph (b)
of this part, and consist of at least the
following:

    (1)   Maintaining the integrity and
effectiveness of any final cover, including
making repairs to the cover as necessary
to  correct  the  effects  of  settlement,
subsidence, erosion, or other  events, and
preventing  run-on  and run-off from
eroding or otherwise damaging the final
cover;

    (2)   Maintaining and operating the
leachate collection system in  accordance
with  the  requirements  in  §258.40, if
applicable. The Director  of an approved
State may allow the owner or  operator to
stop managing leachate  if the owner or
operator demonstrates that leachate no
longer poses a threat to human health
and the environment;

    (3)   Monitoring the ground water
in accordance with the requirements of
Subpart E and maintaining the ground-
water monitoring system, if  applicable;
and

    (4)   Maintaining and operating the
gas monitoring system in accordance with
the requirements of §258.23.

    (b)   The length of the post-closure
care period may be:

    (1)    Decreased by  the Director of
an  approved  State  if  the  owner  or
operator demonstrates that the reduced
period  is sufficient to  protect human
health and the  environment  and this
demonstration  is  approved  by   the
Director of an approved  State; or
                                       342

-------
                                Closure and Post-Closure
   (2)     Increased by the Director of an
approved  State if the Director  of  an
approved  State  determines  that  the
lengthened period is necessary to protect
human health and the environment.

6.6.2  Applicability

Post-closure  care  requirements  apply to
MSWLF units  that stop receiving  waste
after October 9, 1993.  They also apply to
units  that  stop  receiving waste  between
October 9,  1991, and October 9, 1993, and
fail to complete closure within six months
of the final receipt of waste.

Post-closure care requirements are focused
on operating and maintaining the proper
functions of four systems that prevent or
monitor releases from the MSWLF unit:

•  Cover system;

•  Leachate collection system;

•  Ground-water monitoring system; and

•  Gas monitoring system.

Owners or operators must comply  with these
requirements for a  period of  30  years
following closure. In approved States, the
post-closure care period may be shortened if
the owner or operator demonstrates to the
satisfaction of the Director  that human
health and  the environment are protected.
Conversely, the Director may determine that
a period longer than 30 years is necessary.
The requirement to operate and maintain the
leachate   collection   system  may   be
eliminated  by the Director of an approved
State if the  owner or operator demonstrates
that leachate
does not pose a threat to human health and
the environment.

6.6.3 Technical Considerations

When the final cover is installed, repairs
and maintenance may be necessary to keep
the  cover  in   good   working   order.
Maintenance  may  include  inspection,
testing,  and  cleaning of leachate collection
and removal system pipes, repairs  of final
cover, and repairs of gas and ground-water
monitoring networks.

Inspections  should be made on  a  routine
basis. A schedule should be developed to
check   that  routine  inspections  are
completed. Records of inspections detailing
observations should be kept in a log book so
that changes  in any of the MSWLF units can
be monitored; in addition, records should be
kept detailing changes in post-closure care
personnel to ensure that changing personnel
will not  affect post-closure care due to lack
of knowledge  of routine activities.  The
activities and frequency of inspections are
subject to State review to ensure that units
are monitored and maintained for as long as
is necessary  to protect human health and the
environment.

Inspection   of  the  final cover may  be
performed on the ground and through aerial
photography.    Inspections   should   be
conducted at appropriate intervals  and the
condition of the facility should be recorded
with notes, maps,  and photographs.  The
inspector  should  take  notice  of  eroded
banks, patches  of dead vegetation, animal
burrows, subsidence, and cracks along the
cover.  The  inspector also should note the
condition  of  concrete  structures  (e.g.,
manholes), leachate collection and removal
                                         343

-------
                                       Subpart F
pipes,   gas  monitoring   systems,   and
monitoring wells.

For   larger   facilities,   annual   aerial
photography  may  be a  useful  way  to
document the extent of vegetative stress and
settlement  if either  of these has  been
observed during routine inspections.  It is
important to coordinate  the photography
with  the  site  "walkover"   to   verify
interpretations    made    from    aerial
photographs.   Aerial  photography should
not be used in place of a site walkover but in
conjunction with the site walkover.  An
EPA document (U.S.  EPA  1987) provides
further   information   on   using   aerial
photography  for   inspecting  a   landfill
facility. (See the Reference section at the
end of this chapter.)

Topographic  surveys of the landfill unit(s)
may  be  used  to  determine  whether
settlement has occurred.  These should be
repeated every  few years until settlement
behavior is established. If settlement plates
are used,  they  should be permanent and
protected  from vandalism  and accidental
disturbance (U.S. EPA, 1987). Depressions
caused by settlement may lead to ponding
and should be filled with soil. Excessive
settlement may warrant reconstructing  or
adding to portions of the infiltration layer.
Damage caused  by  settlement  such  as
tension  cracks  and tears in the synthetic
membrane should be repaired.

Cover systems  that have areas where the
slope is greater  than 5  percent may be
susceptible to erosion. Large and small rills
(crevices) may form along the  cover where
water has eroded the cover.  This may lead
to exposure of the synthetic geomembrane
and, in severe cases, depending on the cover
system  installed, exposure  of the waste.
Erosion may lead to increased infiltration of
surface water  into  the  landfill.   Areas
showing signs of erosion should be repaired.

Certain types of vegetative cover (e.g., turf-
type grasses) may require mowing at least
two  times a year.   Mowing can  aid in
suppression of weed and brush growth, and
can  increase the vigor  of certain grass
species. Alternatively, certain cover types
(e.g., native prairie  grasses) require  less
frequent mowing (once every three years)
and may be suitable for certain climates and
facilities where a low-maintenance regime
is  preferable.  For  certain cover types,
fertilization  schedules may be necessary to
sustain  desirable   vegetative   growth.
Fertilization schedules should be based on
the cover type present. Annual or biennial
fertilization  may  be  necessary for certain
grasses,   while  legumes   and   native
vegetation may require little or no fertilizer
once established.  Insecticides may be used
to  eliminate insect  populations that  are
detrimental  to vegetation.   Insecticides
should be carefully  selected and  applied
with consideration for potential  effects on
surface water quality.

Some  leachate collection  and  removal
systems have been  designed to  allow  for
inspections in an  effort to ensure that they
are working properly.  Leachate  collection
and  removal pipes  may be flushed  and
pressure-cleaned on a regular schedule (e.g.,
annually)  to reduce the accumulation of
sediment and precipitation  and to  prevent
biological fouling.

Similarly,  gas collection systems should be
inspected  to ensure that they are working
properly.   Vents should be  checked to
ensure they  are not  clogged by foreign
matter such as rocks.  If not working
                                         344

-------
                               Closure and Post-Closure
properly, the gas collection systems should
be flushed and pressure-cleaned.

At   some  landfill  facilities,  leachate
concentrations eventually may become low
enough so as not to pose a threat to human
health or the environment. In an approved
State, the Director may allow an owner or
operator to cease managing leachate if the
owner or operator can demonstrate that the
leachate no longer poses a threat to human
health   and  the  environment.     The
demonstration   should   address   direct
exposures of leachate releases to ground
water,  surface water,  or seeps.  Indirect
effects,  such  as  accumulated  leachate
adversely affecting the chemical, physical,
and  structural containment systems  that
prevent leachate  release, also  should be
addressed in the demonstration.

The  threat posed  by direct exposures to
leachate released to ground water, to surface
waters, or through seeps  may be assessed
using health-based criteria.  These criteria
and  methods are  available through the
Integrated Risk Information System (IRIS)
(a database maintained by U.S. EPA), the
RCRA  Facility   Investigation   Guidance
(U.S. EPA, 1989c), the Risk Assessment
Guidance for Superfund (U.S. EPA, 1989d),
and certain U.S. EPA regulations, including
MCLs  established under the Safe Drinking
Water  Act and the ambient water quality
criteria under the Clean Water Act. These
criteria and  assessment procedures  are
described in Chapter 5 (Subpart E) of this
document.  Concentrations at the points of
exposure, rather than concentrations in the
leachate in the collection system,  may be
used when assessing threats.
6.7 POST-CLOSURE PLAN
    40CFR§258.61(c)-(e)

6.7.1  Statement of Regulation

    (c)    The owner or operator of all
MSWLF units must  prepare a written
post-closure  plan  that  includes,  at a
minimum, the following information:

    (1)    A     description    of   the
monitoring and  maintenance  activities
required in §258.61(a) for each MSWLF
unit,  and the frequency at which these
activities will be performed;

    (2)    Name, address, and telephone
number of the person  or office to contact
about the facility during the post-closure
period; and

    (3)    A  description of the planned
uses of the property during the post-
closure  period.  Post-closure use of the
property shall not disturb the integrity of
the final  cover,  liner(s), or any other
components of the containment system,
or the function of the  monitoring systems
unless necessary  to  comply  with  the
requirements in Part 258.  The Director
of an approved State may approve any
other  disturbance  if  the  owner  or
operator demonstrates that disturbance
of  the   final  cover,  liner  or  other
component of the  containment system,
including any removal of waste, will not
increase the  potential threat to  human
health or the  environment.

    (d)    The owner or operator must
notify the  State Director that a post-
closure  plan  has  been prepared  and
placed in the  operating record no later
                                        345

-------
                                      Subpart F
than  the  effective date  of this part,
October 9, 1993, or by the initial receipt
of waste, whichever is later.

   (e)     Following completion  of the
post-closure  care   period   for   each
MSWLF  unit,  the owner or  operator
must  notify the State Director  that  a
certification, signed  by an independent
registered  professional  engineer   or
approved by the Director of an approved
State, verifying  that post-closure care has
been  completed in accordance  with the
post-closure plan, has been placed in the
operating record.

6.7.2  Applicability

Owners and operators of existing units, new
units,  and  lateral  expansions  of existing
MSWLF units that stop receiving waste
after  October 9,  1993  are  required  to
provide a post-closure plan. MSWLF units
that  received  the  final  waste  shipment
between October 9, 1991 and October 9,
1993 but failed to complete installation of a
final cover system within six months of the
final receipt of waste also are required to
provide a post-closure plan.

The   post-closure  plan   describes  the
monitoring activities that will be conducted
throughout the 30-year period.  The plan
also establishes:

•  The schedule or frequency  at which
   these activities are conducted;

•  Name, address, and telephone number of
   a person to contact about the facility;

•  A description of a planned use that does
   not disturb the final cover; and
•   The procedure for verifying that post-
    closure   care   was   provided   in
    accordance with the plan.

In approved States only,  the  owner or
operator  may  request  the  Director to
approve a use that disturbs the final cover
based on a demonstration that the use  will
not increase the potential threat to human
health and the environment.

6.7.3 Technical Considerations

The State Director must be notified that a
post-closure    plan,    describing    the
maintenance activities required  for each
MSWLF  unit, has  been  placed  in  the
operating  record.   The  post-closure plan
should  provide  a  schedule for  routine
maintenance of the  MSWLF unit systems.
These  systems  include  the  final  cover
system, the leachate  collection and removal
system, and the landfill  gas and ground-
water monitoring systems.

The plan must include the name, address,
and telephone number of the person  or
office  to  contact  regarding  the facility
throughout   the   post-closure   period.
Additionally,  the   planned  uses of  the
property during the post-closure period must
be provided in the plan.  These uses may not
disturb  the integrity of the final  cover
system, the liner system,  and  any other
components   of  the  containment   or
monitoring  systems unless necessary to
comply with the requirements of Part 258.
Any other  disturbances  to  any of  the
MSWLF components must be approved by
the Director of an approved State.  An
example of an acceptable disturbance may
include  remedial   action  necessary  to
minimize the threat to human health and the
environment.
                                         346

-------
                                 Closure and Post-Closure
Following completion of the post-closure
care period, the State Director must be
notified  that an  independent  registered
professional  engineer  has  verified  and
certified that post-closure  care  has been
completed in accordance  with  the  post-
closure plan and that this certification has
been  placed in  the  operating  record.
Alternatively, the Director of an approved
State  may  approve  the  certification.
Certification of post-closure care should be
submitted for each MSWLF unit.
                                          347

-------
                                     Subpart F
6.8 FURTHER INFORMATION

6.8.1 References

Giroud, J.P., Bonaparte, R., Beech, J.F., and Gross, B.A., "Design of Soil Layer -Geosynthetic
    Systems Overlying Voids". Journal of Geotextiles and Geomembranes, Vol. 9, No. 1, 1990,
    pp. 11-50.

Richardson, G.N. and R.M. Koerner, (1987).  "Geosynthetic Design Guidance for Hazardous
    Waste Landfill Cells and Surface Impoundments"; Hazardous Waste Engineering Research
    Laboratory; USEPA, Office of Research and Development; Cincinnati, Ohio; Contract No.
    68-07-3338.

U.S. EPA, (1987). "Design, Construction and Maintenance of Cover Systems for Hazardous
    Waste: An Engineering Guidance Document"; PB87-19156; EPA/600/2-87/039; U.S.
    Department of Commerce, National Technical Information Service; U.S. Army Engineering
    Waterways Experiment Station; Vicksburg, Mississippi.

U.S. EPA, (1988).  "Guide to Technical Resources for the Design of Land Disposal Facilities";
    EPA/625/6-88/018; U.S. EPA; Risk Reduction Engineering Laboratory and Center for
    Environmental Research Information; Office of Research and Development;  Cincinnati,
    Ohio 45268.

U.S. EPA, (1989a).   "Seminar Publication  - Requirements for Hazardous Waste Landfill
    Design,   Construction and Closure";  EPA/625/4-89/022;  U.S.  EPA;  Center  for
    Environmental Research Information; Office of Research and Development;  Cincinnati,
    Ohio 45268.

U.S. EPA, (1989b).  "Technical Guidance Document: Final Covers on Hazardous Waste
    Landfills  and Surface Impoundments"; EPA/530-SW-89-047; U.S. EPA; Office of Solid
    Waste and Emergency Response; Washington, D.C. 20460.

U.S. EPA, (1989c).   "Interim  Final:  RCRA Facility Investigation (RFI) Guidance"; EPA
    530/SW-89-031; U.S. EPA; Waste Management Division; Office of Solid Waste; U.S.
    Environmental Protection Agency; Volumes I-IV; May 1989.

U.S. EPA, (1989d). "Interim Final:  Risk Assessment Guidance For Superfund; Human Health
    Evaluation Manual Part A"; OS-230; U.S. EPA;  Office of Solid Waste and Emergency
    Response; July 1989.

U.S. EPA, (1991).  "Seminar Publications - Design and Construction of RCRA/CERCLA Final
    Covers"; EPA/625/4-91/025; U.S. EPA, Office of Research and Development; Washington,
    D.C.20460.
                                       348

-------
                               Closure and Post-Closure
6.8.2  Organizations

U.S. Department of Agriculture
Soil Conservation Service (SCS)
P.O. Box 2890
Washington, D.C. 20013-2890
(Physical Location:  14th St. and Independence Ave. NW.)
(202)447-5157

Note:      This is the address of the SCS headquarters. To obtain the SCS technical guidance
          document concerning the Universal Soil Loss Equation (entitled "Predicting Rainfall
          Erosion  Loss, Guidebook 537," 1978),  contact  SCS  regional offices located
          throughout the United States.

6.8.3  Models

Schroeder, et  al., (1988).   "The Hydrologic Evaluation of Landfill Performance (HELP)
    Model"; U.S.EPA; U.S. Army Engineer Waterways Experiment Station; Vicksburg, MS
    39181-0631; October 1988.

Schroeder, P.R., A.C. Gibson, J.M. Morgan, T.M. Walski, (1984).  "The Hydrologic Evaluation
    of Landfill Performance (HELP) Model, Volume I - Users Guide for Version I (EPA/530-
    SW-84-009), and Volume II - Documentation for Version I (EPA/530-SW-84-010); U.S.
    Army Engineer Waterways Experiment Station, Vicksburg, MS, June 1984.

6.8.4  Databases

Integrated Risk Information System (IRIS), U.S. Environmental Protection Agency, Office of
Research and Development,  Cincinnati, Ohio.
                                        349

-------