US Army Corps
                                     of Engineers
                                     Galveston District
   MISSISSIPPI RIVER SOUTHWEST PASS , LOUISIANA
             SITE MANAGEMENT PLAN
         FOR THE MAINTENANCE DREDGING
      OCEAN DREDGED MATERIAL DISPOSAL SITE
                 AS REQUIRED BY
                SECTION 102 OF THE
MARINE PROTECTION, RESEARCH AND SANCTUARIES ACT

-------
                          SITE MANAGEMENT PLAN

          MISSISSIPPI RIVER, SOUTHWEST PASS, LOUISIANA
              OCEAN DREDGED MATERIAL DISPOSAL SITE

I.     General

      The Marine Protection, Research and Sanctuaries Act (MPRSA) of 1972 (33 U.S.C. Section
1401, et seq.) is the legislative authority regulating the disposal of dredged material into ocean
waters, including the territorial sea.  The transportation of dredged material for the purpose of
placement into ocean waters is permitted by the Corps of Engineers or, in the case of Federal
projects, authorized for disposal under MPRSA Section 103(e), applying environmental criteria
established by the Environmental Protection Agency in the Ocean Dumping Regulations (40 CFR
Parts 220-229).

      Section 102(c) of the MPRSA and 40 CFR  228.4(e)(l) authorize the  Environmental
Protection Agency  (EPA) to designate ocean dredged material disposal sites  (ODMDSs) in
accordance with requirements at 40 CFR 228.5 and 228.6. Section 103(b) of MPRSA requires that
the Corps of Engineers (USAGE) use dredged material sites designated by EPA to the maximum
extent feasible.  Where  use  of an EPA-designated site is not feasible, the USAGE may, with
concurrence of EPA, select an alternative site in accordance with MPRSA 103(b).

      Section 228.3 of the Ocean Dumping Regulations established disposal site management
responsibilities; however, the Water Resources Development Act of 1992 (WRDA 92; Public Law
102-580) included a number of amendments to the MPRSA specific to ODMDS management.
Section 102(c) of MPRSA as amended by Section 506 of WRDA 92 provides that:

      1.     Site management plans shall be developed for each ODMDS designated pursuant to
             Section 102(c) of MPRSA.

      2.     After January  1, 1995, no ODMDS  shall receive a final designation unless a  site
             management plan has been developed.

      3.     For ODMDSs that  received a final designation  prior  to January 1,  1995,  site
             management plans shall be developed as expeditiously as practicable, but no later
             than January 1, 1997, giving priority to sites with the greatest potential impact on the
             environment.

-------
ODMDS Management Plan                      Mississippi River Southwest Pass, Louisiana


       4.     Beginning on January  1, 1997, no permit or authorization for dumping shall be
             issued for a site unless it has received a final designation pursuant to Section 102(c)
             MPRSA or it is an alternate site selected by the USAGE under Section 103(b) of
             MPRSA.

       This Site Management Plan, for the Mississippi River, Southwest Pass, LA Ocean Dredged
Material Disposal Site, was developed jointly by the U.S. Environmental Protection Agency, Region
6 (EPA, Region 6) and the U.S. Army Corps of Engineers, Mississippi Valley Division, New
Orleans District (CEMVN). In accordance with Section 102(c)(3) of the MPRSA, as amended by
WRDA 92, the plan includes the following:

       1.     A baseline assessment of conditions at the site;

       2.     A program for monitoring the site;

              Special management conditions or practices to be implemented at the site that are
              necessary for protection of the environment;
       4.     Consideration of the quantity of dredged material to be discharged at the site, and the
             presence, nature, and bioavailability of the contaminants in the material;

       5.     Consideration of the anticipated use of the site over the long term, including the
             anticipated closure date for the site, if applicable, and any need for management of
             the site after the closure;

       6.     A schedule for review and revision of the plan.
II.     Site Management Objectives

       The purpose  of ODMDS management is to ensure that placement  activities do not
unreasonably degrade the marine  environment or interfere with other  beneficial  uses  (e.g.,
navigation) of the ocean.  The specific objectives of management of the Mississippi River Southwest
Pass Ocean Dredged Material Disposal Site for maintenance material are as follows:

       1.     Beneficial use of dredged material;

-------
ODMDS Management Plan                      Mississippi River Southwest Pass, Louisiana


       2.      Ocean discharge of only that dredged material that satisfies the criteria set forth in 40
              CPR Part 227 Subparts B, C, D, E, and G and Part 228.4(e) and  is suitable for
              unrestricted placement at the ODMDS;

       3.      Avoidance of excessive mounding either within the  site boundaries or in  areas
              adjacent to the site, as a direct result of placement operations.

       These objectives will be achieved through the following measures:

       1.      Regulation and administration of ocean dumping permits;

       2.      Development and maintenance of a site monitoring program;

       3.      Evaluation of permit compliance and monitoring results.
       4.

III.    Roles and Responsibilities

       In accordance with Section 102 (c) of the MPRSA and with the Regional MOU between
CEMVN and  EPA, Region 6  on Management of ODMDSs signed March  15,  1988, EPA  is
responsible for designation of ODMDSs.  Where use of an EPA-designated site is not feasible, the
CEMVN may, with concurrence with EPA, Region 6 select an alternative site in accordance with
Section 103(b) of the MPRSA as amended by Section 506 of WRDA  1992.

       Development of site management plans for ODMDSs within the New Orleans District is the
joint responsibility of EPA, Region 6 and the CEMVN.  Both agencies are responsible for assuring
that all components of the site management plans are implementable, practical, and applicable to site
management decision-making.


IV.    Funding

       Physical, chemical, and biological effects-based testing shall be undertaken on sediments to
be deposited at the ODMDS. This testing will be conducted at least every five years, or as necessary
to address contaminant concerns due to unanticipated events, and will be funded by the permittee if
the proj ect is permitted or CEMVN for Federal proj ects. The permittee or CEMVN, as appropriate,
shall also be responsible for costs associated with placement site hydrographic monitoring. Should
monitoring indicate that additional studies and/or tests are needed at the ODMDS, the cost for such

-------
ODMDS Management Plan                      Mississippi River Southwest Pass, Louisiana
work would be shared by the permittee or CEMVN and EPA, Region 6.  Physical, chemical, and
biological effects-based testing at the ODMDS, or in the site environs after discharge, that is not
required as a result of hydrographic monitoring, shall be funded by EPA, Region 6. Federal funding
of all aspects of this Site Management Plan is contingent on availability of appropriated funds.
V.     Baseline Assessment

       A.    Site Characterization. The Mississippi River Southwest Pass Project ODMDS is
located west of and parallel to the Mississippi River, Southwest Pass bar channel (Figure 1.). The
site is  rectangular, with an area of approximately 3.44 square nautical miles and the northern
boundary  approximately  1.75 nautical  miles from the mouth of the Mississippi River, with
coordinates located at:

       28°54'12"N, 89°27'15"W;
       28°54'12"N, 89°26'00"W;
       28°51'00"N, 89°27'15"W;
       28°51'00"N, 89°26'00"W.

       Baseline conditions at the Mississippi River, Southwest Pass ODMDS were assessed during
the site designation process. Details of baseline conditions, including descriptions of the marine
environment in  the site vicinity  and the physical, chemical and biological characteristics  of the
sediments and the water column at the  site, are contained in the  "Final  Environmental Impact
Statement (EIS) for the Mississippi River, Southwest Pass Ocean Dredged Material Disposal Site
Designation" (EPA 1988).  In 1995, EPA collected and characterized sediment and biological
samples at the Mississippi River Southwest Pass ODMDS.  This information updates the EIS
baseline conditions at the disposal site.

       B.    Historical Use of the Site. The Rivers and Harbors Acts of 1946 and 1962, the
Supplemental Appropriations Act of 1985, and the Water Resources Development Act of 1986
provided for the construction of a -55-foot deep channel in the Mississippi River from the Gulf of
Mexico to Baton Rouge, LA., a distance of 257 miles. Construction of the -55-foot channel is not
complete. Currently a channel with the following dimensions is maintained:

     -45' deep x 500' wide Mile 232.4 to Mile 104.5
     -45'deep x 750'wide Mile 104.5 to Mile 18.0 Below Head of Passes
     -45' deep x 600' wide between Mile 18.0 Below Head of Passes and Mile 22 Below Head of

-------
ODMDS Management Plan                      Mississippi River Southwest Pass, Louisiana
Passes
      The present configuration of the site was established during the site designation process. The
existing site received interim designation for disposal of dredged material from Mississippi River,
Southwest Pass in 1977(42 FR 2461 et seq.). Interim status of the site was extended indefinitely in
January 1980. The Mississippi River, Southwest Pass ODMDS received final designation on May 1,
1989 (54 FR 61).

     History of disposal of dredged material prior to 1976 is incomplete. Dredging records
dating back to 1960 indicate discontinuous reaches of the lower jetty and bar channel were
maintained with hopper dredges.

     Maintenance dredging of the Mississippi River, Southwest Pass  area is required on an
annual basis. Dredging is conducted approximately between Mile 6.5  Above Head of Passes and
Mile 22 Below Head of Passes. While deep draft hopper dredges are utilized for maintenance
along the entire channel length, cutterhead dredges are utilized between Mile 1 and Mile 18.8
Below Head of Passes. Material removed from the lower jetty (Mile 11 Below Head of Passes to
Mile 18.8 Below Head of Passes) by cutterhead dredges is deposited for bank nourishment or
wetlands development. Material removed from the lower jetty and bar channel (Mile 11 Below
Head of Passes to Mile 22 Below Head of Passes) by deep draft hopper dredges is deposited in
the ODMDS. Only dredged material from the navigation channel is placed in the ODMDS.

     The hopper dredges use two methods of dredging and disposal when working in the lower
jetty and bar channel reaches; dredge and haul; and dredge and haul with agitation. In the dredge
and haul mode; material is pumped into the hopper and hauled and deposited in the ODMDS.
Agitation dredging consists of filling a hopper dredge to capacity and  allowing it to continuously
overflow. The very fine suspended sediments are released and swept away by littoral currents
which generally flow westward. Dredged material that accumulates in the hopper and is not re-
suspended during agitation is hauled and deposited into the ODMDS.
       Dredging is conducted on non-continuous reaches beginning in the winter and continuing

-------
ODMDS Management Plan                      Mississippi River Southwest Pass, Louisiana

to the fall. Dredging is conducted in areas of high shoaling, often with multiple deep draft
hopper dredges together. Maintenance may be conducted within the lower jetty and bar channel
reaches at any time throughout the dredging season. When a deep draft hopper dredge is working
in the channel, dredging and disposal operations will occur 24 hours a day, 7 days a week until
the authorized channel dimensions are restored. Table 1. provides a summary of the dredged
quantities since 1976.

VI.    Quantity of Material and Presence of Contamination

       A.    Summary of information used to determine size of the site.  The rectangular
shaped Mississippi River, Southwest Pass ODMDS is 3.44 square nautical miles in size. The
ODMDS parallels and is west of the Mississippi River Southwest Pass bar channel. When EPA
designated it an interim ODMDS in 1977, the site had been used historically for disposal of dredged
material from the navigation  channel. The location and configuration of the site resulted from the
ease of disposal from the navigation channel. In January 1980 the interim status of the  site was
extended indefinitely.  On May  1, 1989, final designation of the ODMDS was completed. No
recommendations for changes in the size of the site were made as a result of the  site designation
studies.

     The location and configuration of the ODMDS involves only short transit of the hopper
dredge from the navigation channel to the ODMDS. This minimizes interference with other
activities such as fishing and navigation in the site environs during dredging and disposal
operations. The site also is easily accessible for surveillance of dredged material disposal
operations and monitoring.

     Like most ODMDSs in the Gulf of Mexico, the Mississippi River, Southwest Pass
ODMDS is a dispersive site.  The dredged material discharged into the site is reworked by wave
and littoral currents and moved out of the ODMDS.

Since 1976, the Mississippi River, Southwest Pass lower jetty and bar channel reaches have been
dredged annually; and dredged material has been placed in the ODMDS. Approximately 3.5

-------
ODMDS Management Plan
Mississippi River Southwest Pass, Louisiana
      Table 1. Summary of Dredged Quantities Deposited at the Mississippi River,
                   Southwest Pass ODMDS


CY76
01 Jan
CY77
01 Apr
CY78
01 Jan
CY79
01 Jan
CY80
02 Jan
CY81
12 Jun
CY82
15 Jul
CY83
23 Jan
CY84
14 Apr
CY85
03 Jan
01 Jan
CY86
01 Jan
CY87
11 Feb
Dredging


- 26

- 30

- 30

- 30

- 30

- 30

- 02

- 18

- 30

- 13
- 31

- 30

- 03


May

Apr

Jul

Sep

Jul

Jul

Aug

Jun

Dec

Dec
Dec

Apr

Nov
Interval


'76

'77

'78

-79

'80

'81

'82

'83

'84

'85
'85

'86

'87
Quantity of Dredged Material
(cubic yards)

3,926,500

31,400

2,698,900

5,401,200

6,315,100

1,769,500

330,300

8,383,100

2,282,000

1,170,600
3,132,500

3,100,000

8,556,000
Table 1. Continued

-------
ODMDS Management Plan
Mississippi River Southwest Pass, Louisiana
CY88
20 Jan -
CY89
01 Jan -
CY90
07 Feb -
CY91
08 Jan -
CY92
01 Dec -
CY93
03 Jan
CY94
01 Oct
CY95
09 Feb
CY96
CY97
CY98
CY99
CY2000
CY01
CY02
CY03
CY04
CY05
CY06
CY07
Totals

02

04

02

10

01

- 05

- 01

- 01














Jun

Aug

Aug

Jul

Aug

Oct

Aug

Sep














'88

'89

'90

'91

'92

'93

'94

'95














2,495,800

1,381,200

1,245,100

450,000

7,200,700

11,055,300

4,353,300

7,504,695
8,360,290
7,565,976
9,262,940
4,960,527
518,000
6,671,000
11,310,020
5,145,755
6,261,917
2,087,114
2,510,000
5,426,616
70,080,155
million cubic yards of dredged material are removed from the lower jetty and bar channel
reaches and placed in the ODMDS  annually. The dredged material generally can be

-------
ODMDS Management Plan                      Mississippi River Southwest Pass, Louisiana

characterized as mixture of sand, silt, and clay. The average percentages of sand, silt, and clay
sampled from 12 stations in the jetty and bar channel, located between Mile 11 and Mile 22.2
Below Head of Passes, were 24.9%, 50.1°%, and 24.9% respectively. It is anticipated that
annual maintenance of the Mississippi River, Southwest Pass lower jetty and bar channel
reaches, and disposal of dredged material into the ODMDS will continue in the future.
       B.    Summary of testing requirements per Regional Implementation Agreement
(RIA)  and summary of past dredged material evaluations.  In October  1992, a RIA was
executed between EPA Region  6, and the New Orleans District.  This RIA was updated on
September 30, 2003 (U.S. EPA and USAGE, 2003), and describes protocols for evaluating the
quality of the dredged material  and implementation of the "GREEN BOOK"  (U.S. EPA and
USAGE, 1991). These protocols describe chemical parameters to be analyzed, as well as required
detection limits. It also specifies how toxicity testing and bioaccumulation assessments are to be
conducted, as well as organisms to be utilized.  Since that time, all sediment evaluations have been
conducted in accordance with the RIA.  Since the mid-1970s, before development of the RIA,
dredged material from the Mississippi River Southwest Pass Project had been evaluated numerous
times to determine suitability for offshore  placement.  This testing was performed to determine
levels of metals and organic constituents,  as well as toxicity and bioaccumulation assessments.
Testing beyond Tier I has been performed for this project in April  1999 and July 2007 in the
navigation channel, the ODMDS,  and the reference site. The above testing indicated that the
material was suitable for offshore placement without special management conditions.

     Although dredged material from the Mississippi River, Southwest Pass lower jetty and bar
channel reaches has been placed in the ODMDS annually, sampling or analyses has not been
performed annually. Prior to each maintenance event, a Tier I evaluation has been conducted.
Comprehensive analyses of existing and readily available information on the proposed dredged
material, including spill reports from the U.S. Coast Guard, National Response Center, indicated
"no reason to believe" that the proposed discharges of dredged material were not suitable for
ocean disposal. The CEMVN and EPA, Region 6, will adhere to the RIA in deciding when new
chemical and biological data are needed.

-------
ODMDS Management Plan                      Mississippi River Southwest Pass, Louisiana
VII.   Anticipated Site Use

     Dredged material will be removed annually using deep draft hopper dredges and
discharged via agitation or dredge and haul into the ODMDS. The dredged material generally is
comprised of 24.9% sand, 50.1% silt, and 24.9%  clay.

     Dredging in the lower jetty and bar channel reaches normally begins in the winter and
continues into the fall. When a dredge is working in the bar channel, disposal operations will
occur 24 hours a day, 7 days a week until authorized channel dimensions are restored.

     It is anticipated that annual maintenance of the Mississippi River, Southwest Pass lower
jetty and bar channel reaches, and disposal of dredged material into the ODMDS will continue in
the future. During each maintenance event, approximately 3.5 million cubic yards of dredged
material will be discharged into the ODMDS.

       It is the policy of the New Orleans District to implement beneficial uses of dredged material,
wherever practicable. Although beneficial use of material removed by cutterhead dredges from the
Southwest Pass was employed during past maintenance operations, the current practice of utilizing
only hopper dredges to maintain the navigation channel precludes the immediate beneficial use of
material dredged from this channel. However, the CEMVN will continue to pursue beneficial use
disposal alternatives in partnership with the state  of Louisiana.
VIII.   Special Management Conditions or Practices

Special management conditions or practices applicable to the Mississippi River, Southwest Pass
ODMDS include the following:

     a. Options for beneficial use of dredged material taken from Mississippi River, Southwest
Pass lower jetty and bar channel were considered during development of the Mississippi River,
                                           10

-------
ODMDS Management Plan                      Mississippi River Southwest Pass, Louisiana

Southwest Pass Long Term Disposal Plan (LTDP) and in the EIS ODMDS designation process.
The alternatives reviewed included pump out of hopper dredges for wetlands creation or beach
nourishment, or concentrating material while bottom dumping to create berms. These
alternatives were determined to be infeasible due to the following: high costs; material
unsuitable for beach nourishment; and few environmental benefits. Additionally, during the
dredging season, hopper dredges must maintain high production in order to maintain project
depths. It was determined during the LTDP process that the time required to conduct pump out
operations ashore or at distant open water locations would result in the loss of project depths and
adversely impact navigation.

      Beneficial use is conducted with material removed from the jetty reach by cutterhead
dredge. This material is deposited beneficially for bank restoration or wetlands development.
Beneficial use of dredged material from the Mississippi River, Southwest Pass bar channel has
not been implemented because hydraulic  cutterhead pipeline dredges with trailing pipe,
traditionally used for beneficial use, are not used in the bar channel. Rough sea conditions, ship
traffic, and the need to maintain high production rates while being able to rapidly mobilize
equipment in the bar channel reach preclude use of this type of dredge. However, prior to the
start of each new fiscal year, beneficial use alternatives are investigated. Should technology and
or funding become available that would make beneficial use feasible, the CEMVN will
incorporate beneficial use into the disposal plan for the bar channel reach of the Mississippi
River, Southwest Pass to the maximum extent practicable.
IX.    Monitoring Program

       The primary purpose of the Site Monitoring Program is to evaluate the impact of the
placement of dredged material on the marine environment.  The evaluations will be used for making
decisions, preventing unacceptable adverse effects beyond the  site boundary, and  ensuring
regulatory compliance over the life of the ODMDS.  Emphasis will be placed on determining
physical impacts, since, to date, dredged material from the Mississippi River Southwest Pass Project
has been determined to be acceptable for ocean placement, without special conditions; however,

                                           11

-------
ODMDS Management Plan                       Mississippi River Southwest Pass, Louisiana

consideration of contaminants will also be included. Testing of dredged material is conducted based
on "Greenbook" and RIA procedures, however it is necessary to verify the decisions made regarding
the suitability of the dredged material are correct and that the material is not having an adverse
impact to the environment. In the event that the material persists in the ODMDS, there may be
potential for long-term contaminant effects on the benthos.

       The size and location of the Mississippi River Southwest Pass Project ODMDS were
determined pursuant to the General Criteria as listed in 40 CFR 228.5, and the Specific Criteria at 40
CFR 228.6(a). There are no significant environmental resources delineated within or immediately
outside of the designated ODMDS. Since this site is dispersive in nature, the primary concern of the
use of the site  is the potential short-term build up of dredged material, such that a  hazard to
navigation is presented. Another concern is whether there is significant short-term movement of the
dredged material beyond the ODMDS  boundaries; specifically, the benthic community can be
impacted if significant rapid movement of material off the site occurs, resulting in burial of benthic
populations outside the site.  Studies have shown that benthic organisms can burrow through 6-9
inches of dredged material without significant impacts on the community (EPA/USACE, 1996).

       The Site Monitoring Program is designed as a tiered program.  If initial tier results fail
predetermined limits, then a more complex set of tests is invoked at the next tier to determine the
extent of impact.  The tiers are used to facilitate rapid, accurate and economical  collection of
information for  use by the EPA, Region 6, and the CEMVN. The tiered testing for these factors is
described below.

TIER Ml

       Physical and chemical  evaluations of  the ODMDS material  shall be conducted to
characterize possible effects from the placement of dredged material occurring at the site. Physical
analyses of the  sediment can assist in assessing the impact of disposal practices on the benthic
environment at  the disposal site and determine if dredged material is migrating offsite.  Chemical
analyses of the sediment shall be conducted to establish whether contaminants of concern are
suspected to be  affecting the benthic environment at the disposal site.
                                           12

-------
ODMDS Management Plan                       Mississippi River Southwest Pass, Louisiana
Bathymetric Surveys

       The ODMDS is located outside of the safety fairway for large vessel traffic, therefore, the
mounding will be considered in regard to shallow-draft vessels, only. Considering the grain-size
characteristics of typical maintenance dredged material from this channel, significant mounding is
not expected subsequent to discharge operations.

       Since the site is dispersive, movement of material from the site is expected to occur after
disposal operations cease.  In  order to detect if short-term movement of the material out of the
designated ODMDS is occurring at a significant rate, hydrographic surveys of the ODMDS shall be
obtained before the start of disposal operations, and after completion of disposal operations. A post-
disposal  survey indicating  an accumulation of 2.0  feet above the predisposal  elevation of
sedimentation within the site or mounding greater than 1.0 feet above the pre-disposal elevation for
movement of material outside of the designated ODMDS will be considered the threshold levels of
acceptability.

       Hydrographic surveys  shall be conducted along transects within the ODMDS.  These
transects shall be oriented perpendicular to the channel in the direction of sediment transport (i.e.,
southwest). Transect intervals shall be every 1,000 feet extending 1,000 feet outside each boundary.
In addition, a depth profile shall be obtained along each boundary.

       Surveys shall be obtained using a USAGE, or contract survey vessel equipped with electronic
surveying capabilities.  The vessel must be equipped with positioning equipment with a horizontal
precision of one (1) foot. The fathometer, which  shall display real-time depth on real-time location,
must have a precision  of 0.5 feet.  All data shall be collected using methodology described in
Engineer Manual EM 1110-2-1003, dated January 1, 2002.

       Data Analysis
                                            13

-------
ODMDS Management Plan                      Mississippi River Southwest Pass, Louisiana

       *     If deposited dredged material  is not mounding to elevations greater than the
             threshold elevation above the existing bottom elevation, and there  is no short-term
             movement of material beyond the limits of the ODMDS, then the management
             objectives are met. No further post-disposal monitoring will be required.

       *     If mounding to elevations greater than the threshold elevation, and/or movement of
             material out of the ODMDS has occurred, as determined by the post-dredging
             survey, then the monitoring program shall proceed to Tier M2.

Sediment Chemistry

       Sediment chemistry analyses shall be conducted in conjunction with the dredged material
evaluations from samples collected in the navigation channel. Collecting samples from both the
navigation channel and ODMDS during the same sampling event has been determined to be the most
efficient use of resources.  Because most ODMDSs lie directly adjacent to the navigation channels,
there are relatively short distances between the two areas. As described in the RIA,  sediment testing
in the navigation channels generally occurs on a five-year cycle.  Sediment chemistry results from
the ODMDS should be compared to the results collected from the reference site and the navigation
channel.  Significantly elevated sediment concentrations are defined as concentrations above the
range of contaminant levels in dredged sediments that the Regional Administrator and the District
Engineer found to be suitable for disposal at the ODMDS.

       Data Analysis

       *     If contaminant concentrations are not significantly different than navigation channel
             concentrations then no further testing is needed.

       *     If significant increases in levels of contaminants are observed at the ODMDS,  then a
             determination will be made whether a bioassay/bioaccumulation study is warranted
                                           14

-------
ODMDS Management Plan                      Mississippi River Southwest Pass, Louisiana

              to determine effects on the benthic community. The studies are described below as
              Biological Testing under Tier M2.

TIERM2

Bathymetric Surveys

       If transport of material from the site is occurring, hydrographic surveys shall be expanded to
include the impacted area and shall be performed on a semi-annual basis to determine the changes in
dispersion of the material until the impacts are no longer observed.  An accumulation of more than
one (1) foot of sedimentation along the ODMDS boundary will be considered the threshold level for
significant movement of material outside of the designated ODMDS.

       Data Analysis

       *      If deposited dredged material is mounding to elevations above the threshold value,
              but less than fifteen (15) feet above the existing bottom  elevation and there is no
              significant short-term transport  of material beyond the limits of the ODMDS, then
              semi-annual post-disposal monitoring shall occur as described.

       *      If at  six months after disposal, deposited dredged material remains mounded to
              elevations greater than half the  post-disposal elevations, then bathymetric surveys
              shall  be continued.

       *      If deposited dredged material is mounding to elevations greater than fifteen (15) feet,
              and/or significant movement of material out of the ODMDS has occurred, the New
              Orleans District together with EPA Region  6 will  consider various  management
              options to rectify the situation.  Such options could include, but are not limited to
              expansion of the ODMDS; or relocation of the ODMDS within the zone of siting
              feasibility described in the designation EIS.
                                           15

-------
ODMDS Management Plan                      Mississippi River Southwest Pass, Louisiana
Biological Testing

       If the results of the Tier Ml sediment chemistry evaluation suggest the need for additional
testing, then solid-phase bioassay and bioaccumulation testing shall be conducted in accordance with
the procedures described in the RIA. If the sediment can be attributable to recent dredging, funding
for testing under this Tier will be provided by CEMVN or the permittee, as appropriate; otherwise
funding will be provided by EPA, Region 6. Any such testing is contingent on availability of
appropriated funds.

Data Analysis

       *     If toxicity is not indicated, then no further testing is needed and disposal activities
             can continue at the ODMDS.

       *     If toxicity is indicated at the ODMDS, the New Orleans District together with EPA
             Region 6 will consider various management options to rectify the situation. Because
             the ODMDS  is a dispersive site,  potential sources of toxicity other than  dredged
             material must also be considered. If planned use of the ODMDS is imminent, a
             decision must also be made whether to allow continued use of this site.

X.     References

NMFS (National Marine Fisheries Service), 2007. Revision 2 to the November 19,2003 Biological
       Opinion concerning Dredging of Gulf of Mexico Navigation Channels and Sand Mining
       ("Borrow") Areas Using Hopper Dredges by COE Galveston, New Orleans,  Mobile, and
       Jacksonville Districts (Consultation Number F/SER/2000/01287).

U.S. EPA  and USAGE. 1991.  Evaluation of Dredged Material Proposed for Ocean Disposal -
       Testing Manual.  EPA-503/8-91/001.  U.S. Environmental Protection Agency and U.S.
       Army Corps of Engineers, Washington, D.C.

U.S. EPA  and USAGE. 2003. Regional Implementation Agreement for Testing and Reporting
                                          16

-------
ODMDS Management Plan                      Mississippi River Southwest Pass, Louisiana
       Requirements for Ocean Disposal of Dredged Material off the Louisiana and Texas Coasts
       Under Section 103 of The Marine Protection, Research  and Sanctuaries Act.   U.S.
       Environmental Protection Agency, Region 6 and U.S. Army Corps of Engineers, Galveston
       and New Orleans Districts.
XI.    Site Management Plan Review and Revision

       Pursuant  to  Section 102(c) of the MPRSA, as amended by  WRDA  1992, the  Site
Management Plan for the Mississippi River Southwest Pass ODMDS will be reviewed and revised,
if necessary, not less frequently than 10 years after adoption and every 10 years, thereafter.

       Modifications or updates to the Site Management Plan may be necessary, based on specific
needs identified for specific authorized projects. Modifications or updates to the Site Management
Plan may be proposed by either the CEMVN or EPA Region 6. Following a thirty (30) day review
period of the changes(s), the modifications may be incorporated into the plan by mutual consent of
both agencies.

       This Site Management Plan complies with Section  102(c)(3) of the Marine Protection,
Research and Sanctuaries Act of 1972 (33 U.S.C. Sections 1401, etseq.) as amended by Section 506
of the Water Resources Development Act of 1992 (WRDA 92; Public Law 102-580), and has been
approved by the following officials of Region 6 of the U.S. Environmental Protection Agency, and
New Orleans District of the U.S. Army Corps of Engineers. This plan goes into effect upon the date
of the last signature:
Richard E. Greene                                                         Date
Regional Administrator
Region 6
U.S. Environmental Protection Agency
Alvin B. Lee                                                       Date
Colonel, US Army
                                          17

-------
ODMDS Management Plan
Mississippi River Southwest Pass, Louisiana
District Commander
New Orleans District
U.S. Army Corps of Engineers
                                         18

-------