EPA/540/R-93/507
  SITE EMERGING TECHNOLOGIES PROJECT:
BABCOCK & WILCOX CYCLONE VITRIFICATION
                  by

  Jean M.  Czuctwa,  James J. Warchol,
 William  F.  Musiol. and  Hamid Farzan
     The Babcock  &  Wilcox Company
      Contract Research  Division
         Alliance, Ohio  44601
      Contract  No. CR-815800-02-0
           Project Officer:

           Laurel J.  Staley
Risk  Reduction Engineering  Laboratory
  Office of Research  and Development
 U.S.  Environmental Protection Agency
        Cincinnati,  Ohio  45268
RISK  REDUCTION ENGINEERING  LABORATORY
  OFFICE OF RESEARCH AND DEVELOPMENT
 U.S.  ENVIRONMENTAL PROTECTION  AGENCY
        CINCINNATI, OHIO 45268

-------
                                   DISCLAIMER


      The  information  in this  document  has been funded in part by the United
States Environmental Protection Agency  under Cooperative Agreement NO. CR-
815800-02-0 to Babcock & Wilcox Co.   The document has been subjected to the
Agency's administrative and peer review and has been approved for publication
as an EPA document.  Mention of trade names or  commercial  products does not
constitute  endorsement or recommendation for use.

-------
      The U.S. Environmental  Protection Agency (EPA) is charged by  congress
with protecting the  Nation's  land, air, and water  resources.  As the enforcer
of national environmental  laws,  the  EPA strives to  balance human activities
and the ability of natural systems to support  and  nurture life.  A key part of
the EPA's effort  is  its research into our  environmental  problems to find new
and innovative solutions.

      The Risk Reduction Engineering Laboratory (RREL)  is responsible for
planning, implementing, and managing research,  development, and demonstration
programs to provide  an authoritative,  defensible engineering basis in support
of the policies,  programs, and  regulations of the EPA with respect to drinking
water, wastewater, pesticides,  toxic substances,  solid and hazardous
wastes,and Super fund-related  activities.   This publication is one of the
products of that  research  and provides  a  vital communication  link between the
researcher and the user community.

      Now in its  eighth year, the Superfund Innovative Technology Evaluation
(SITE) Program is part of  EPA's research into cleanup methods for hazardous
waste sites around the nation.   Through  cooperative agreements with
developers, alternative or innovative technologies are refined at  the  bench-
and pilot-scale level and  then demonstrated at actual sites.  EPA collects and
evaluates extensive  performance data on each technology  to use in remediation
decision-making for  hazardous waste  sites.

      This report documents the results  of laboratory and pilot-scale field
testing of the vitrification  of soil contaminated with methods.

                              E.  Timothy Oppelt,  Director
                              Risk Reduction Engineering  Laboratory

-------
                                    ABSTRACT


      The Babcock & Wilcox cyclone  vitrification furnace appears well suited
to treating  high inorganic content hazardous wastes and contaminated soils,
which exist at many Super fund sites.   In a study performed under the U.S.  EPA
Superfund  Innovative  Technology Evaluatron (SITE) Emerging Technologies
Program, the Babcock  & Wilcox six million Btu/hr  pilot  cyclone furnace was
used to vitrify  an EPA Synthetic Soil  Matrix (SSM)  spiked with 7,000 ppm lead,
1,000 ppm  cadmium,  and 1,500 ppm  chromium.

      During  1990 to  1992, pilot-scale testing of the Babcock & Wilcox six
million  Btu/hr pilot  cyclone furnace for the vitrification  (immobilization) of
heavy metals from contaminated soil was  conducted.  The  tests  were conducted
on wet and dry contaminated soil  (synthetic  soil matrix) fed at several feed
rates ranging from  50 to 300 Ib/hr.  The soil  is captured and melted In the
molten slag  layer that  forms at the cyclone  furnace wall, exits the cyclone
furnace,  and  is  dropped into a  water-filled  slag  tank  where it solidifies.

      The cyclone vitrification process  successfully treated several tons  of
SSH. The vitrified  soil was non-teachable by the Toxicity Characteristic
Leaching  Procedure (TCLP).   The volume of the  vitrified soil was reduced by
approximately 25-35% when compared to  dry  SSM.

      This  report was  submitted in  fulfillment of Cooperative Agreement
CR-815800-02-0 by the  Babcock  & Wilcox Research  4 Development Division under
the partial  sponsorship of the U.S. Environmental  Protection Agency. This
report covers a  period from March,  1990,  to  February 28, 1992, and work was
completed as  of  February 28, 1992.

      Subsequent to the SITE Emerging  Technologies  project described here,  the
U.S. Environmental Protection Agency  conducted a SITE Demonstration  of the B&W
cyclone  vitrification process  in November,  1991. The results  of this
Demonstration are expected  to  be published by the U.S. EPA  in  1992.
                                       1v

-------
                               TABLE  OF CONTENTS
Foreword   ________________________________iii
Abstract 	   iV
Figures  and  Tables 	  vi
Abbreviations and  Symbols  _______________________    vii
Acknowledgments  ____________________________   viii

1     EXECUTIVE  SUMMARY  	    1
      A.      The  SITE  Emerging Technologies program   ___________     1
      B.      Summary Results 	    1
2     INTRODUCTION AND BACKGROUND  INFORMATION 	   3
3     PROCESS  DESCRIPTION  	    6
      A.      Phase  I (Dry Soil Processing) Configuration  _________     8
      B.    Configuration for Phase  II  (wet  Soil  Feed Processing)   _  _ _ _    11
      C.      Atomizer Design for  Phase II Tests   _____________    15
      D.      Furnace Continuous  Monitors  __________________   17
      E.      Applicable Wastes and Possible Technology
             Configurations  	  18
4     EXPERIMENTAL DESIGN 	  20
      A.      Decription of Phase  I  and Phase II Tests   	    20
      B.     Description of Phase  I  (Dry SSM Feed)  Tests _________    21
      C.    Description of  Phase II  (Wet SSM Feed)  Tests    	    23
      D.     Use of a  Fluxing Agent  to  Increase
             Metal  Retention in  the Slag  	  24
      E.     Synthetic  Soil  Matrix  (SSM)  	    25
      F.     Sampling  Methods  	   28
      G.      Analytical  Methods   	 30
5     RESULTS	31
      A.      Vitrification as  Measured by TCLP Test Results    _______   31
      B.      Volume  Reduction   _______________________ 36
      C.     Metals  Retention         	  38
      D.     Mass Flowrates  of the  Fly Ash and Slag Streams	41
      E.      Relative  Concentrations of Metals in the  Slage
             andFlyAsh	  41
      F.    OJperability/Emissions                                             48
6     QUALITY ASSURANCE 	,	  50
      A.      Systems Audits	     50
      B.     Performance  Audits  for  Critical  Measurements  	*......  51
      C.     Performance Audits  for  Non-Critical  Measurements   	  53
7     CONCLUSIONS AND  RECOMMENDATIONS	55
      A.      Conclusions	55
      B.      Recommendations  for  Future Work	.55
8     REFERENCES	58
9     APPENDIX	59

-------
Figure                                                            PU3H

 1         The Pilot Cyclone Test Facility.. ____________   7
 2         Schemation of Cyclone Vitrification Process	  9
 3         Phase 1 Cyclone Furnace Configuration- _________   10
 4         Phase II Cyclone Furnace Configuration ________   12
 5         Wet Soil Feed System ___________________   14
 6         Schemation of Wet Soil Atomizer.. ____________   16
 7         Sampling and  Analysis Location   	   29
 8         Vitrified Synthetic Soil Matrix-____________   32
 9         Toxicity Characteristic Leaching Procedure Results	_ _ _ _ _   33
10         Volume Reduction. _____________________   37
11         Heavy Metal sand Ash Mass Balance ____________   44
12         Heavy Metals Capture vs.FeedRate. ____________   46
13         Heavy Metals  Capture vs.Volatility Temperature. _ _ _   47
                             LIST OF TABLES
Table
 1        Phases and Specific Goals of the SITE
           Emerging Technologies Program.  	    5
 2         Typical Cyclone  Furnace Test Conditions 	    21
 3         Phase I Test Matrices  	    22
 4         Phase II Test Matrices	    23
 5         Typical SSM Characterization Results(DryBasis)  	    27
 6         Results of TCLP Tests for Untreated and Treated SSM ...   34
 ?         Percent of Leachable Metals  Before and After Treatment  . .   35
 8         Total Metals in  the Soil,Slag and
           Multiple Metals Train Particulates 	    42
 9         Average  Phase I   CO,C02,and NOx Levels(Spiked SSM)  	  48
10         QC Data  for TCLP Analyses  	    52
11         QC Data for Non-Critical Metals Determinations 	     54
                                 V i

-------
                       LIST OF ABBREVIATIONS AND  SYMBOLS
ABBREVIATIONS
          ASTM  --   American Society for Testing  of Materials
          Btu    --  British  thermal units
          B&W    --  Babcock & Wilcox
          Cd  - -    cadmium
          Cr    - -  chromium
          cu ft  --  cubic foot
          DRE    --  destruction  and removal  efficiency
          EPA    --  United  States Environmental  Protection Agency
          kg     --  kilogram
          L      --  liter
          Ib/hr  -- pounds per hour
          MBtu   --  Million British thermal  units
          mg     --  milligram
          MSW   --  municipal  solid  waste
          MW     - -  megawatt
          Pb     --  lead
          PSIG   --  pounds per square  inch  gage
          QA     --  quality assurance
          QAPP   --  quality assurance  project plan
          iPD    --  relative percent difference
          RREL  --  Risk Reduction Engfneering Laboratory  (EPA)
          SBS    --  small boiler simulator pilot  facility
          SITE  --   Superfund Innovative  Technology Evaluation
          SSH    --  synthetic soil  matrix
          TCLP   --  toxicity characteristic  leaching procedure
          u      --  microgram
                                      Vii

-------
                                ACKNOWLEDGMENTS

      This document was  prepared under Cooperative Agreement  No.
CR-815800-02-0 by the  Babcock & Wilcox Company Research and Development
Division, Alliance, Ohio.   Laurel Staley of the  Risk Reduction Engineering
Laboratory  (RREL)  was  the Project Officer responsible for the  preparation of
this  document and deserves  special  thanks for her helpful comments  and  advice.
SSM was  obtained from  the RREL Releases  Control  Branch (Edison, NJ).  TCLP
analyses were performed by Aquatec  (So.  Burlington,  VT). Technical assistance
was provided  by  B&K staff
R. Bailey,  S. Boyce,  L.  Breyley,  V.  Burgess,  J. Curtis, R.  Huskins,  J. Lyden,
K. Nevitt, R. Schreckengost,  E. Stoffer,  and  T. Wilson.
                                      Viii

-------
                             1. EXECUTIVE SUMMARY

The SITE Emerging Technologies Project
      During 1990 to  1992,  pilot-scale  testing of the Babcock I Wilcox six
million Btu/hr pilot  cyclone furnace  for  the  vitrification of soil and
immobilization  of heavy metals was conducted.   The tests were conducted on wet
and dry contaminated  soil  (synthetic  soil matrix)  fed at several different
feed rates.

Summary  Results
      The pilot cyclone  furnace was successfully used to vitrify an EPA
Synthetic Soil Matrix (SSM) spiked  with 7,000 ppm  lead,  1,000 ppm cadmium,  and
1,500 ppm chromium.    Tests  showed 95  to 97% of the  non-  combustible portion of
the input SSM was incorporated  within the slag. When  operated  at 50 to 150
Ib/hr of dry  SSM feed, and from 100-300 Ib/hr of wet  SSM feed,  the cyclone
technology was  able to  produce  a non-teachable product.  Average lead,
cadmium, and chromium TCLP  teachabilities in the untreated SSM  were 104,  54,
and 2.3 mg/L,  respectively.  Average  lead,  cadmium,  and chromium TCLP
teachabilities  in the treated SSM from  the 50 to 150  Ib/hr dry SSM tests were
0.20,  0.13, and 0.11  mg/L,  respectively, and for the  treated  SSM from the 100
to 300  Ib/hr  wet SSM  tests  were  0.20, 0.07, and 0.04  mg/L, respectively. All
of these TCLP results are close to  the  analytical detection limit and, hence,
the results for wet vs.  dry soil  are not likely significantly  different. All
of these treated SSM  TCLP results are well below the  TCLP  limits.

      Using natural gas  as the fuel,  the  CO and NO,  stack emissions gases from
the process averaged  19  and 352  ppm at  3% 02,  respectively.  Stack C02
averaged 11.5%.   These stack levels are within acceptable ranges.  The capture
of heavy metals in the vitrified slag from all  tests ranged from 8-17% for
cadmium, 24-35% for  lead,  and  80 95% for chromium. Addition of  10% of a Borax
flux did not significantly  improve  the  heavy  metals  capture in  the vitrified
slag despite  lower  cyclone temperatures  (=100°F).

-------
      The capture of heavy metals in the slag increased with increasing feed
rate, likely  due  to shorter cyclone furnace  residence  times.  The capture of
metals in the slag  increased with decreasing metal  volatility.  This suggests
the cyclone vitrification process would be well suited to treatment of low
volatility contaminants,  such as  many  radionuclides.

      The treatment of the synthetic soil  matrix resulted in a volume
reduction of  25-35% (dry basis).   The  vitrification  treatment results  in an
easily-crushed,  glassy product.
                                      -2-

-------
                  2.   INTRODUCTION AND  BACKGROUND  INFORMATION

      The Superfund Amendments  and Reauthorization Act of 1986 directed the
U.S. Environmental Protection Agency to establish an "Alternative or
Innovative  Treatment  Technology Research and Demonstration  Program".  In
response, the EPA Office of Solid  Waste and  Emergency Response and the Office
of Research and Development established a formal  program called the Superfund
Innovative  Technology Evaluation (SITE) Program to accelerate the development
and use of  innovative cleanup technologies at hazardous waste sites across the
country.

      This project was sponsored under  the SITE Emerging Technologies  Program.
Before a technology can be  accepted  into the Emerging Technologies Program,
sufficient  data must  be  available to validate  its  basic concepts. The
technology  is then subjected to  a  combination of  bench-  and  pilot-scale
testing in an attempt to apply the concept under  controlled  conditions.

      The Babcock & Wilcox  cyclone furnace is a well-established design (over
26,000 M installed electrical capacity) for the  combustion  of high inorganic
(ash) coal.   The combination of high heat  release rates  (450,000  Btu/cu ft for
coal) and high turbulence in cyclones assures the high temperatures required
for melting the high  ash fuels.  The inert ash  exits the cyclone furnace as a
vitrified slag.

      Taking advantage of the ability of the cyclone furnace to form a
vitrified slag from  waste  inorganics,  the cyclone furnace was used in  a
research and development project to  vitrify  municipal  solid  waste  (MSW)  ash
containing heavy  metals.   The cyclone furnace produced a vitrified MSW ash
which was below EPA  teachability  limits for all  eight RCRA  metals.  The
successful treatment  of MSW ash  suggested that  the  cyclone vitrification
technology would be applicable to  high  inorganic  content hazardous wastes and
contaminated soils that also contain organic constituents.  These  types  of
materials exist at many Superfund sites, as well as sites where  petrochemical
                                      -3-

-------
and chemical sludges  have been disposed.   Our approach for establishing the
suitability of the cyclone vitrification technology  relies  on the premise that
for acceptable performance  in  treating hazardous waste mixtures containing
organic and heavy metals constituents,  the cyclone furnace  must melt EPA's
synthetic soil matrix  (SSM)  while producing a non-teachable  slag and must
achieve the destruction and removal efficiencies  (DRE's,  currently 99.99%) for
organic contaminants normally  required for RCRA hazardous waste incinerators.
The high  temperature (>2,500 to 3,000°F), turbulence,  and residence  time  in
the cyclone and main furnace are  expected  to result  in high organics
destruction and  removal efficiencies  (DRE's).

      A SITE demonstration was performed on  the  pilot cyclone furnace in
November of 1991.  An  EPA-supplied synthetic soil matrix spiked with heavy
metals  (cadmium, chromium,and  lead), organics (anthracene  and  dimethyl
phthalate), and simulated radionuclides (cold strontium, bismuth, and
zirconium) was used.   Depending  on the results of the SITE demonstration, the
next step for product development would be conceptualization, design,
construction,  field testing, and  economic  analysis of a full-scale unit (e.g.,
80 tons per day).

      This report will present  the results of both the Phase  I(1990-1991) and
Phase  II (1991-1992) Emerging Technologies  efforts.  The two  Phases  had
specific goals as given in Table  1.   Roth  Phases  used an EPA synthetic soil
matrix spiked with  lead,  cadmium, and chromium.  The most  important  goal  for
both Phases was to produce  a vitrified soil  that passes the Toxicity
Characteristic Leaching Procedure (TCLP)  limits for  lead,  cadmium, and
chromium.   Because the most significant difference  between Phases I and  II is
the use of a  dry or wet soil  feed system, Phases I  and II nay also be referred
to in this report as "Dry Soil Feed System"  and  "Wet Soil Feed System,"
respectively.  The wet soil feed system was  used for the EPA Demonstration of
the technology and, thus, this report  will emphasize the results for this
final  system  configuration.
                                       -4-

-------
                                   TABLE  1
                     Phases  and  Specific Goals  of the
                   SITE  Emerging  Technologies Project
          Phase
                    Specific Goals
 Phase I  (1990-91)  -
 Dry Soil Feed System
 Phase  II  (1991-92)  -
 Wet Soil Feed System
• Determine synthetic soil matrix  (SSM)
  properties.
. Establish cyclone operability (e.g.,
 feeding,  melting behavior, operational
data).
. Determine slag  leachability and  volume
  reduction.
. Determine preliminary heavy metals mass
  balance  for cyclone treatment process.


. Design of wet soil feed system and atomizer.
. Establish cyclone operability (e.g.,   feeding,
  melting  behavior,  operational  data).
. Determine slag  leachability and  volume
  reduction.
. Optimize heavy  metals capture and  determine
  metals mass balance for  cyclone  treatment
  process.	
      Measurement of organics  destruction efficiencies, thought to  be  less of

a technical challenge compared with metals  capture,  was reserved  for a SITE

Demonstration performed  in November  1991. The remainder of  this  report

describes the cyclone furnace used in this  study,  the  tests  that  were

conducted, the results achieved and, finally,  conclusions  that can  be  drawn

about the usefulness of  the cyclone furnace  for  the  treatment  of  hazardous
waste.
                                      ,5.

-------
                              3.  PROCESS DESCRIPTION
      The Babcock  & Wilcox six million Btu/hr  cyclone furnace located in
Alliance, Ohio, was used to perform  all  pilot-scale vitrification tests
discussed in this  report.  The furnace is water-cooled and simulates the
geometry of B&H's front- wall  fired  cyclone coal-fired  boilers.  This cyclone
facility has been  proven to simulate typical full-scale cyclone units in regard
to furnace/convection gas  temperature  profiles  and  residence  times,  NOx levels,
cyclone slagging potential, ash retention in the slag, unburned carbon, and
flyash  particle size.

      The pilot cyclone furnace, shown in  Figure 1,  is fired  by a single,
scaled-down version of a cormnercial  coal combustion cyclone furnace.   The
furnace  geometry  is a horizontal  cylinder  (barrel).  A  summary of the process  is
illustrated in Figure 2.   Both the primary air and secondary air were heated to
approximately 820°F.   Primary air, secondary air,  and soil conveying air (150*F)
used to  transport  the soil into the  furnace accounted for  25%,  72%, and 3% of
the total air  input,  respectively.   For these tests,  natural gas and preheated
primary  combustion air  enter  tangentially into the cyclone burner.  In dry soil
processing, preheated secondary air,  the soil matrix, and a portion of the
natural gas enter  underneath  the secondary air and parallel to the cyclone
barrel axis.   For  wet soil processing, an atomizer  is used to spray the soil
paste directly into the  furnace.

      Upon  entering the  cyclone furnace, soil is captured and melted, and
organics  are destroyed in the  molten  slag layer that  is formed and retained on
the furnace barrel wall  by centrifugal action created by the tangentially fired
combustion  air.  The  soil  melts, exits the cyclone furnace from the tap at the
                                        -6-

-------
            STACK PARTICULATE
            SAMPLING LOCATION
      SSM FEED
      SYSTEM
      CONTINUOUS EMISSIONS
      MONITOR (CEM)
      SAMPLING LOCATION
SSM
SAMPUNG
LOCATION
 SLAG AND
 QUENCH
 WATER
 SAMPUNG
 LOCATION
                       ID FAN
                 SCRUBBER
                 (NOT IN
BAGHOUSE

 HEAT
 EXCHANGER
                                       SLAKER
                                       (NOT IN
                    COMBUSTION
                    AIR
         NATURAL GAS
         IIIJ-l I WIXJ-ll— V-^
         INJECTORS
                                                        FURNACE
                                                        STACK
               I   I   II
                FURNACE
            SLAG
            TRAP
                 NATURAL
                 GAS
               SOIL

               INJECTOR
       ^CYCLONE
SPOUT    BARREL
                        SLAG
                         QUENCHING
                         TANK

        FIGURE 1  Pilot Cyclone Test Facility

                             -7-

-------
cyclone throat, and is dropped  into  a water-filled slag tank where it
solidifies.   Operation of the cyclone at a load of 5 million Btu/hr produced the
best slag tapping  conditions.   Operation at both 6 and 4 million Btu/hr  load
conditions decreased slag tapping due to changes in cyclone flow patterns.

      A small  quantity of soil  also exits as flyash  with the flue gas from the
furnace and is collected in a baghouse.   This flyash can be recycled to the
furnace as indicated in Figure  2  to  increase the capture of metals and to
minimize the volume of the potentially hazardous fly ash waste stream.

      Flue gas passes  through a baghouse for purposes  of particulate control.
To maximize the capture of metals, a heat exchanger is used to cool the  stack
gases to  approximately 200°F before  entering the baghouse.  Although the cyclone
facility  is equipped with an acid gas scrubber, it was not used for these tests
because acid gas generation  (e.g.,  HC1) from the vitrification of the SSH was
expected to be low.

Phase I (Dry  Soil Processing) Configuration
      The furnace  configuration used in Phase  I  is-shown  in Figure 3. Natural
gas and preheated  primary combustion air enter tangentially into the  cyclone
burner.   Preheated secondary  air,  the soil matrix (fed into the furnace
pneumatically  by a screw feeder),  and natural gas enter parallel to the cyclone
axis  into the  cyclone furnace. The  soil is captured  and  melted  and  organics
destroyed in the molten  slag layer that  is  formed and retained on the furnace
wall by centrifugal action.   Most  of  the  soil  melts,  exits the cyclone furnace
from the tap at the cyclone throat,  and is dropped into a water-filled slag tank
where it solidifies.  A small  quantity of soil  exits  as flyash with the flue gas
from the furnace and is collected  in  a baghouse.
                                        -8-

-------
I

-------
o
I

                                                       AIB


                                                                                             AIB
                                                                                                    GAS
                                                                                          SOIL
                                                                                                AIH

                                                                                                  GAS
                                                                               •L

                 FIGURE 3   Cyclone furnace Configuration  for       1

-------
      Particulate control was achieved by way of a MikroPul, Inc.baghouse
containing twenty-three  10-ft.  Nomex bags and operated at  an  air-to-cloth ratio
of 2.8  at  150°F.   A single-pass,  water-cooled heat exchanger with seventy  1.5" x
8 ft  U-tubes is used to  cool the stackgases to approximately 200*F before
entering the baghouse.   Although the cyclone facility  is equipped with  an acid
gas scrubber, it was not  used  because  acid gas generation (e.g., HC1)  from the
vitrification of SSM was expected to be low.

Configuration  for Phase II (Wet Soil Feed Processing)
      The primary difference between the  cyclone  furnace configurations for
Phase I and Phase II is in  the  feed system.  While Phase I tests used  dry soil,
Phase II used soil  with  a high moisture content and  a muddy consistency.  It  is
generally thought that Superfund soils will range from very dry to wet  or muddy.
Because  feed system problems are often encountered at Superfund sites,  it was
important to demonstrate  that the cyclone  furnace  could operate with a wet soil
feed.   In addition,  it  was not known how well the vitrification process would
tolerate a high moisture feed  (e.g., possible heat losses  due to evaporation  or
entrainment of particulate by  the generated steam).  Thus, wet soil  feed system
design  and testing were  a major  goal  of the Phase II effort.

      The wet feed  system furnace  modifications  are  shown in Figure 4.  The
modifications were performed not only to add wet soil feeding capability,  but
also to improve the  distribution of soil to the soil- melting surfaces  of the
furnace  barrel.   Modifications made  on the  furnace  to  accomplish these  two goals
included:  (1) removal of the scroll so that no primary air or natural gas are
added at the furnace front location;  (2)  installation of natural gas jets at
                                       -11-

-------
              COMBUSTION
              AIR
NATURAL GAS
INJECTORS
                                           CYCLONE
                                           BARREL
                               SLAG
                               SPOUT
                     SLAG
                     QUENCHING
                     TANK
FIGURE 4    CYCLONE FURNACE FOR WET SOIL INPUT
                         -12-

-------
the secondary air  entrance.   These were used together with the gas  lighter; and
(3) installation of a soil atomizer using variable compressed air at the former
scroll burner location  (see  Section  C,  below).

      To  improve the feeding of wet soil to the cyclone furnace  a Moyno
progressing cavity pump with speed  controller  (Frame 2J3, Type CDR AM) was used
to feed the high viscosity  soil.   A maximum feed  rate  of 620 Ib/hr  is possible
with this pump model.   The  pump stator material  is natural rubber and the rotor
is chromium steel.   The speed controller is designed to maintain  a constant
motor speed and,  thus,  a constant  soil  feed rate to the cyclone furnace (200
Ib/hr  feed at  a pump speed of 631  rpm).

      The Phase  II feed system was installed and tested using clean, wet SSM to
which water was  added to produce a moisture content of 24%  (the  as-received  $SM
was approximately  20%  moisture).   A schematic of the system  is shown in Figure
5.

      The soil was added to the feed hopper as  follows:  Yater was added to each
drum of SSM.  After replacing the  drum  lid,  the soil was  mixed  using a drum
tumbler operated for 1 hour. The drum lid was replaced by a discharge  cone,  and
the drum  was  emptied into the feed hopper by way of two valves.    Particles
larger than 1/2* were screened  from  the  soil during transfer  to  the  feed hopper.
After loading the hopper, a two-blade mixer was turned on.  The  feed  system was
calibrated and SSM was fed  to the  cyclone furnace for initial combustion
optimization.   Several SSM moisture  contents were tested,  and the most effective
operation was found  at 26%  moisture.   Therefore,  the pump was recalibrated at
26% moisture  and  the  remaining Phase II experiments were conducted at this
moisture  level.
                                        -13.

-------
           SSM Feed System


   "\"".A Vr% LrY 1C
in



                 (TYP.)



TO


         W (? t :> o 11 Feed S v s t e m

-------
Atomizer Design  for Phase II Tests
      To optimize  the  distribution  of wet feed inside the cyclone furnace,
preliminary testing with simple nozzles was performed to determine the
atomization design for SSM.   An externally-mixed  atomizer appears to work  well
for  the  SSM.  High-velocity  air was used to  achieve atomization. The  objective
for  this project was  to evenly spray SSM to the cyclone furnace barrel walls
where combustion and  melting will take  place.  The droplet size must also  be
large enough  to avoid merely entraining the SSM in the combustion gases exiting
the  furnace,  but not  so large as to form deposits in the furnace.

      An atomizer  was designed, modified,  and tested during Phase II. For
successful vitrification of  the  soil  paste,  the atomizer has to meet the special
requirements  associated with  the soil material  and furnace geometry. Commercial
atomizers  or  nozzles  of the required flow capacities  have  flow passages  that are
too  small  to  pass  the soil paste or  the expected small pebbles in the soil.  The
specific parameters deemed important to the operation of the  atomizer  are as
follows:    (1) atomize a high soli(14  soil slurry  consisting of approximately  75%
to 80% solids;  (2) accommodate  flow rates up  to about 400  Ib/hr of slurry;  (3)
permit passage  of  pebbles or agglomerates up to about  3/8 inch in diameter; (4)
have a compressed  air consumption of about 200 Ib/hr or less (pilot-scale  only);
 (5)  minimize  flow  constrictions  that  would tend to plug; (6) provide a
directional spray  that could be pointed toward the hottest surfaces in the
 interior of the cyclone combustor;  and  (7) have an overall diameter of 1 to  1
 1/2  inches to accommodate installation through  existing ports in the cyclone
combustor.

      The  atomizer, shown in Figure 6, was-developed  to  inject and disperse the
soil paste  into the  cyclone combustor.   Photographs of the atomizer are  enclosed
 in the Appendix.   The atomizer consists of two concentric  tubes.  The inner tube
provides the  flow  passage for the soil  paste,  while compressed air is supplied
 in the annular  space  between the two  tubes.   At the outlet end of the atomizer,
 flow passages between the soil  tube  and the annulus  provide the high velocity
air  streams for atomization  of the  soil.  The outlet  end of the  soil paste tube
 is shaped  in  a rectangle and attached  to  a tungsten carbide insert.  This  insert
                                       -15-

-------
                                          of the
CTv
I
              N.
              /'

                      AIR
                       /„../_
                                                                                       SOIL
                                                                       AIR
                         JiC 6  Scheaiatk: fit ay ram of the Wc-t So' 1 At
-------
is  in the  form  of a billet with a machined slot.  The tungsten carbide insert
forms three of the  four  walls of the rectangular opening, while a flow
distributor plate forms  the  fourth wall.   Rectangular flow passages machined
into the flow distributor  plate  provide the high velocity air streams that
atomize the soil paste.

      The flow passages  are  inclined at different angles relative to the axis of
the atomizer in  order to distribute the soil particulate  over a large area.  The
tungsten carbide insert  is used  to minimize erosion due to the high velocity air
and soil particles  impacting the wall of the  tube opposite the air passages.

      This style of atomizer provides a "straight through" passage of the soil
paste into the  combustor to minimize pluggage problems  due to agglomerates or
pebbles.   Also, the flow of compressed air in the annulus  surrounding  the soil
paste tube provides cooling  which minimizes the  chance of the soil drying out in
the tube and plugging  the  atomizer.   The atomizer designs were  initially
cold-tested outside the  cyclone furnace by spraying clean SSM  into a 55-gallon
barrel to observe the SSM spray pattern and flow.

      In final  operation, atomizer air  flow rates of 90 to 130  Ib/hr,  and static
pressure of 15 to 100 PSI6 were used.   The soil  atomizer was inserted at two
locations; next to  the gas lighter or at the  middle of the cyclone using the
scroll burner initially  and  eventually replacing the scroll burner with a plate
(see picture in the Appendix).   The  latter configuration was  the most optimal.
The direction of the  dispersed soil  can be controlled by adjusting the atomizer
direction.   Soil atomizer  direction  was upward  for the best results; when
pointed downward slag  accumulation was  observed.

Furnace  Conditions Monitors
      To monitor the  operation of the cyclone furnace  during Phase  I  and Phase
II  tests,  the  following  operating parameters were monitored.  Carbon monoxide
and carbon dioxide  were  measured during both  phases  of cyclone testfng using
Beckman Model 864 Infrared Analyzers.   Oxygen was measured using Beckman Model
755 and  Bailey  Model  OC1530  Oxygen Analyzers. Nitrous  Oxides were measured
using a Beckman Model  951A NO/NOx Analyzer.
                                       ,11-

-------
      Calibration was performed  before and  after each day's  test with  SSM  spiked
with heavy  metals  using calibration gases  supplied  by Linde (Somerset, NJ).
Fluke digital  readout  and Type K thermocouples  were used for temperature
readings.   Air flow rates were measured using  ASTM orifices.  Rosemont pressure
transducers were used.   Data acquisition was by an  IBM PC using a  Keithley 570
system  and  LabTech software.

Applicable  Wastes  and  Soils and  Possible Technology Configurations
      An  advantage of vitrification over  other  thermal destruction processes  is
that in addition  to the  destruction of organic  constituents, the resulting
vitrified product  captures  and does not  leach heavy metals or  radionuclides.

      The cyclone  vitrification technology would be applicable to high inorganic
content hazardous  wastes,  sludges,  and  contaminated soils that contain heavy
metals  and  organic constituents.   These  types of materials exist at many
Superfund and  Department  of Energy  sites, as well as sites where petrochemical
and chemical sludges have been disposed.  These wastes may be  in the form  of
solids, a soil slurry (wet soil),  or  liquids.  To be treated in the cyclone
furnace, the ash  or solid matrix must melt and  flow at cyclone furnace
temperatures  (2800 to  3000°F).

      Because  of  the technology's ability to capture  heavy metals in the slag
and render  these  non-leachable,  an important application  of the technology  is
contaminated soils  which  contain non-volatile radionuclides  (e.g.,  strontium,
transuranics).

      The cyclone  furnace can be operated with  gas,  oil,  or coal as the
supplemental fuel  (the  likely  application for  coal-fired use is waste treatment
at an existing electrical generating  utility).    The waste itself may also  supply
a significant  portion of the required  heat input.  Heat recovery  is available,
but is  unlikely to be a priority for the final  design. Recycling of the small
volume  of baghouse  ash may be advantageous in field operation.
                                        -18-

-------
      Additional air  pollution control devices,  such as NOx reduction
technologies,  can  be  applied as needed.   An acid  gas scrubber would be required,
for example,  when chlorinated wastes  are treated.  The final process
configuration  will  determine the size of the  full-scale system.
                                       -19-

-------
                             4.  EXPERIMENTAL DESIGN

      The studies  discussed in this document occurred  in  two phases.  Both
phases will be described in more detail later in the report. For purposes of
describing the process,  Phase  I  concerned  feeding  dry soil to the cyclone and
Phase II concerned feeding wet soil to the cyclone. The process configuration
used for each phase will  be described  below.

Description of Phase I and  Phase II Tests
      The most important  goal  for both Phases was  to produce a vitrified soil
that passes the Toxicity Characteristic Leaching Procedure (TCLP) limits for
lead, cadmium, and  chromium.   Because  the  most significant difference between
Phases I and  II  is the use of a dry or wet soil feed system,  Phases  I and II may
also be referred to in this report  as  "Dry Soil  Feed System" and "Wet Soil Feed
System,"  respectively. The wet soil feed system was used  for the EPA
Demonstration of the technology.  Thus,  this  report will emphasize the  results
for this final system  configuration.  Both Phases used an EPA synthetic soil
matrix spiked with  lead,  cadmium, and  chromium.

      Typical run  conditions for the Phase  I  and Phase  II  tests are given in
Table 2,  below.
                                       -20-

-------
                                   TABLE 2
    	Typical  Cyclone  Furnace Tests  Conditions	
    	Condition	Typical Range of Values
     Heat Input (natural  gas fuel)                     5  million  Btu/hr
     SSM  Feed Rate                                     50 to 300  Ib/hr
     Excess Oxygen                                           1.0%
     Primary and  Secondary Air Temperature                  820°F
     Total Air Split -  Phase I
       Primary Air                                           25%
       Secondary Air                                         72%
       Feed Air                                               3%
     Total Air Split   Phase II
       Primary Air                                         not used
       Secondary Air                                        96.5%
       Soil Atomizer Air                                     3.5%
     Slag Temperature (in cyclone barrel)                2370-2460°F
     Gas  Temperature (cyclone exit)                      2800-3000°F
     Furnace Exit Temperature                            2100-2200°F
     Baghouse Temperature                                   200°F
     Flyash/Flyash + Slag Ratio   Phase I                     5%
     Flyash/Flyash + Slag Ratio  - Phase  II	3%	
      Measurement of organics destruction efficiencies,  thought  to  be  less  of a
technical challenge  compared with metals  capture,  was reserved for  a  SITE
Demonstration  performed  in November  1991
      A description of both Phase I  and Phase II will be  provided, below followed
by  a description of  the SSM used  in each-test.


Description  of Phase I  (Dry SSM Feed)  Tests
      Phase  I  tests ranged from 3-1/4 to 14 hours. The  cyclone  furnace was
first fired  on natural gas  (with gradual  addition of primary  and secondary  air)
for approximately 2-3  hours before adding  the SSM. After  the furnace  barrel was
heated,  SSM  feed  was started and soil melting  and tapping was observed through
observation ports.   Minor adjustments were made,  as  needed,  to maintain  soil
                                       -21-

-------
melting and  tapping.   Sensors,  emissions monitors,  and sampling were  initiated
after  conditions  stabilized.   The test  conditions  for the preliminary
vitrification tests are  given in Table 3

                                    TABLE 3
                            Phase  I Test Matrices



Test

Cyclone
Load
MBtu/hr
SSM
Feed
Rate,
Ib/hr

Stack %
Excess
Oxygen

Slag
leap.
*F


Flyash/
Slag
Primary &
Secondary
A1r Temp.
•F
    Preliminary  Vitrification  Tests  [Ory,  Clean  Soil]
10/25/90
10/26/90
10/26/90
10/26/90
4.8
4.6
4.9
4.7
50
100
150
200
1.1
0.8
0.5
0.7
2340
2430
2370
2380
                                                                       813
                                                         <5%*          821
                                                                       824
                                                                       823
    Heavy   Netils Tests  [Ory, Spikea  Soil]
11/01/90
11/15/90**
11/16/90**
11/19/90
4.S
4.7
4.8
4.6
100
46
141
94
0.7
0.5
0.7
0.9
2350
2400
2375
2390

7.5%***
5. n***
5.8%***

830
817
826
      *Amount of the  SSM leaving the  furnace as ash, preliminary
       estimate.
     **Tests used for TCLP  and  heavy  metals mass balance.
    ***Includes  estimate of amount of particulate  deposited in the
       convection pass.

      The purpose of  the preliminary  tests was  to  optimize cyclone conditions
for the  vitrification of the SSM.  Because the  purpose was to  establish run
conditions, clean (unspfked)  SSM was  used.   Furnace  optimization  included minor
adjustments in the  thermal load,  SSM  inlet location, primary air  temperature,
and damper settings to optimize soil  melting and throughput. The  SSM inlet
location was changed  from  the scroll  burner at the furnace  front to along the
secondary air inlet location on the furnace barrel side.

      During the  four days  of tests,  the  cyclone operation remained very stable.
Soil input was  increased from 46  to 141 Ib/hr  with test durations of  3  to 6
hours.   The slag  tapped  well,  and no buildup of deposits was observed in the
                                       -22-

-------
 furnace.   The surface  slag  temperature  was measured using a two-color optical
pyrometer and ranged from 2340 to 2430°F.   Measurements of the gas temperature
were not made during the  tests.   However, previous  work with HSM flyash
vitrification showed gas temperatures in the range  of 2840 to 2940°F at the
cyclone outlet.   The cyclone temperature was adequate to melt the soil, but  not
excessive,  which could  lead  to increased metals volatilization.
Description of  the Phase II  (Wet  SSM Feed)  Tests
      The Phase II test  conditions for  the preliminary vitrification tests and
heavy metals tests are given  in Table 4.

                                    TABLE  4
                            Phase   II Test Matrices
Test
Preliminary
8/20/91
8/21/91
8/27/91
8/27/91
8/28/91
8/28/91
8/29/91
9/03/91
VdW
9/09/91
9/10/91
9/10/91
9/11/91
Cyclone
Load
MBtu/hr
SSM
Feed Stack X
Rate, Excess
Ib/hr Oxygen
Vitrfficatfon Tests [Met,
5.1
5:3
5.0
4.9
4.9
4.9
4.9
5.1
100 0.77
100 0.76
100 0.62
150 0.56
200 0.58
300 0.53
300 0.56
300 0.47
Slag
Temp.
°F
Flyash/
Slag (X)
Primary &
Secondary
Air Temp.
'F
Clean SoilJ*
2455
2420
2370
2410
2410
2390
2405

Metals Jests [wet, Spiked Soil]*
4.8 200 1.2 2430
4.9
4.9
4.9
4 -^***
200 1.0
100 Ofi.
300 0.7
200 4.7
2420
2470
2400
2320
1.77
2.01
1.73
04
0.4
1.49
1.89
1.94
2.32
2.63


3.53
814
794
814
814
810
813
810
807
823
825
813
822
810
        *Atomizer  air 90 to 130 Ib/hr,  15 to  100 PSIG  static  pressure.
       **Atomizer air flow rates of 128  to  134  Ib/hr were used.
      • **10% Borax was added to the  SSM.
      For Phase II tests the cyclone was operated at  a  nominal   load  of 5 MBtu/hr
and 1% excess oxygen.  The  SSM input was varied  between 100 to  300 Ib/hr.  The
cyclone operating conditions were  relatively  smooth,  and the longest  continuous
operation was six hours  at  200 Ib/hr of SSM feed rate.
                                       -23-

-------
      The  preliminary tests were  mainly performed to observe the operational  *




condition  of  the  cyclone.   Cyclone temperature,  SSM  feed rate, and slag tapping




conditions of the SBS are the operational variables  that were monitored.   If too




much SSM is fed to the cyclone,  assuming the soil melts,  the  cyclone throat will



be flooded by the molten slag and slag  will  stay inside the cyclone and




adversely  impact  the  cyclone operation.    Larger  particles  in  the  SSM (3/8") will




stay in  the cyclone until  they melt,  but  if  they do  not melt,  then they should




leave the  cyclone encapsulated by the slag.   The slag/large particle removal



from the cyclone essentially  determines the maximum  load.  The cyclone  was




operated at a nominal load of 5 MBtu/hr  and  about 3 to  10%  excess  air.   The  SSM



feed was gradually Increased  from 100  Ib/hr to  the  maximum of 300  Ib/hr.  The




critical factors  were to observe whether  the SSM  indeed melts  down to slag and




if the cyclone taps freely.




     When  the soil  was evenly dispersed around the cyclone  barrel,  the slag




melted readily. Slag  accumulated inside the  cyclone  (approximately  1.5  to 2



inches)  until  the slag started tapping.    This behavior  may  be specific  to a




small water-cooled  cyclone.   Cyclone tapping was good until the feed rate




increased  to  400  Ib/hr.   The cyclone was  cold and slag  tapping stopped  or was




blocked.








Use of a Fluxing  Agent to Increase metal Retention in the Slag.




      Fluxing agents  that  cause  the soil  to  melt and tap at lower temperatures



may decrease  metals volatilization  and,  thus,  increase the capture  of  the metals




in the slag.    Borax was  reported as a fluxing agent  for MSW ash vitrification




[5].  For one  of the tests during Phase  II 10% by weight Borax (20  Ib/hr)




(B4Na20?/10H20)» was  mixed with SSM.   After Borax was  added,  the cyclone load




could easily  be  reduced to  4.1  MBtu/hr  without  any problem with  slagging. With




the added  Borax,  the  slag temperature was reduced from 2430°F (200  Ib/hr SSM



                                       -24-

-------
feed rate)  to 2320°F and NOx levels decreased from 318-337 ppm (200 Ib/hr feed
rate) to  260  ppm,  as shown in the Appendix figures.  The Borax appeared  to
facilitate  the movement  of slag out of the cyclone furnace barrel. When  Borax
was added,  the  flyash produced  increased  to 3.53% of the  input  SSM, presumably
due to vaporization of sodium from the  Borax.

Synthetic Soil  Matrix (SSM)
      The synthetic soil  matrix  formulated  by EPA was used for cyclone testing.
Both  clean and spiked synthetic soil matrix  (SSM) were  obtained from the  EPA
Risk Reduction Engineering Laboratory (RREL) Releases Control Branch  in  Edison,
NJ. SSM, used  by EPA for  treatment technology evaluations, has been well
characterized  in  previous studies [1].   The spiked SSM  used in this study
contained 7,000 ppm (0.7%)  lead,  1,000  ppm  cadmium,  and 1,500 ppm chromium.    For
each project  Phase, clean,  unspiked SSM (up to 3 tons) was used  for  preliminary
                                       -25-

-------
cyclone optimization,  and then heavy metal spiked  SSM  (up  to 2.5 tons) was used




for the heavy metals tests.




      The SSM moisture content  as-received was approximately 20%.  For Phase  !,




the small amount  of spiked SSM used was passively  dried  in plastic-lined  trays,



lumps crushed,  and screened to minus  1/4".   For  Phase  II,  the moisture content



of the SSM was increased  to  24-263  and a wet feed system was installed (see




below) to feed  the SSM in this configuration.








      Before Phases  I  and II,  analyses were made to  characterize SSM  to




determine combustion conditions, ash melting behavior and need,  if any,  for a



slag fluxing agent.  The results are  given in Table 5.  The Phase II  results are



for the spiked  rather  than clean SSM.   The soil  contained mainly inert




components,  low organic  carbon (most  carbon was present as  carbonate),  and a low



heat content  (41  Btu/lb  for  clean SSM) .   The  soil  was largely  composed of




silicates (50.3%).   A  significant  portion of the SSM consisted of small




particles; 21.4% of  the  particles were less than 149 microns  and 7.4% of the




particles were  less  than  44  microns.   Gravel of  up to  1/4" was also present in




the SSM.
                                        -26-

-------
                                   TABLE 5
            Typical SSM Characterization Results  (Dry Basis)
Parameter
Moisture
Volatile Hatter
Fixed Carbon
Ash
Heating Value, Btu/lb
Total Sulfur
Total C (corr. for C02)
Total Carbonate, % 0)3
Silicon as Si02*
Aluminum as AljOj*
Iron as Fe2Q,*
Titanium as T102*
Calcium as CaO*
Magnesium as MgO*
Sodium as Na,0*
Potassium as ICO*"
Sulfur as SO,*
Phosphorous as PjQj*
Slag Viscosity (in *F at
250 poise, red. atm.)
Ash Fusion Temp. , *F
Atmosphere
A (I.D.)
B (S.T., SP)
C (S.T., HSp)
D (F.T., 1/16")
E (F.T., Flat)
Phase I
(Dry, Unspiked SSM)
1.2%
18.9%
--
80.3%
41
0.004%
0.64%
15.3%
50.3%
9.2%
3.0%
0:35x
16.8%
3.8%
1.1%
1.3%
0.41%
1.3%
2319'F


red. 0X1 d.
2220 2240
2250 2250
2260 2280
2420 2520
2540 >2750
Phase II
(Wet, Spiked SSM)
20.4%
	

81.7%
878
	
._
15.4%
47.0%
8.9%
2.2%
0.35%
15 . 1%
4.4%
0.6%
1.1%
0.70%
0 . 35%
23SO°F


red. OXld.
2250 2240
2280 2270
2290 2300
2600
—
     * Ash analysis.
    -- Showed no further  physical change up to a maximum of 2750°F.
      The chemistry of the SSM resulted in a  low ash fusion temperature under
oxidizing and reducing conditions and  low slag (melted soil)  viscosity.  This is
essential for the soil to melt and flow during  furnace  operation and ensure
encapsulation of hazardous constituents and continuous, controlled removal of
the molten slag from the  cyclone furnace.  The  analysis results were similar for
the SSM used  for both  project Phases.   For example,  the slag viscosity (T,,
temperature at which the  material has a viscosity of 250 poise)  of the Phase  I
SSM was 2319°F and for the Phase II SSM was 2350eF. The slag viscosity of the
clean, dry SSM enabled  it  to be  treated in the  cyclone  furnace without the
addition  of fluxing agents (coals with  similar  slag viscosities are known to
                                      -27-

-------
readily melt  in  a cyclone furnace).   The  spiked  soil  gave slightly higher ash
fusion temperatures than  the  clean SSM.
      Before the Phase I  tests,  spiked SSH samples were  submitted wet
(as-received) and dry (oven-dried at -95oC) for TCLP testing  (EPA 1311)  for Pb,
Cd, and Cr  by Aquatec, Inc. (So. Burlington,  VT)  to verify that  the starting
soil failed the  TCLP.   The leachability of the lead  averaged 81  mg/L;  cadmium,
40 mg/L;  and  chromium,  2.8 mg/L.   With the exception  of chromium, the spiked
soil exceeded EPA limits for lead (5 mg/L) and  cadmium (1 mg/L). This
below-EPA-limit  (5 mg/L  limit)  result for chromium agrees with previous reports
for SSM  [I] .   The low chromium leachability may be caused  by the clay component
of SSM,  which may adsorb chromium.

                                                                                 >
Samp1i ng Methods
      Sampling and analysis  followed  guidelines in the U.S.  EPA  SW-846 Manual,
and the  Duality Assurance Project Plan (QAPP)  [2]  met RREL Category III
requirements.   Performance criteria  were set for  critical  measurements (TCLP)
and non-critical  measurements (heavy  metals mass  balance,  volume reduction).
Several  systems  conditions were monitored.
     Sampling  locations for the various  measurements and analyzers are shown in
Figure  7.   Duplicate  soil  and slag grab samples  were  obtained at approximately
one hour intervals during the heavy metals tests. The soil was  collected by way
of a sampling valve  in the soil feeder line  (Phase I)  and by sampling the feed
hopper using  a plastic ladle (Phase  II).   The  slag was  collected with a steel
shove1.
      Particulate  loading was measured  at a location  after  the convection pass
and before the  baghouse  using an  EPA Method  5 Train  [4]. Stack  metals were
measured using the EPA Multiple Metals Train  (BIF Method, see Reference 3) with
                                        -28-

-------
     CYCLONE TREATMENT OF CONTAMINATED SOIL
        SAMPLING LOCATIONS AND ANALYSERS
CD
                          BAB
SOIL

     	
      ASH
              1 5
      %
             TEMP
             0>
                AIR
      {•'EfcDiiATfc
                                             CO
                                             CCh
                                             ItMP
                                         I
                                       FLY ASH
                  WATER
                         SLAG
      F1 OKt. ^ S jjiiiJ 11 n 
-------
the exception  that the HN03  and KMn04 impingers were not used.  This exception
was made because  previous sampling with  the filter temperature held at  120 I
14*Cf as specified in the Multiple Metals  Train Method  [3],  showed no  more than
0.2% of the total  lead,  cadmium,  and chromium were present In the impingers.
Metals levels determined using this method should be considered  lower  estimates.
Post-furnace  CO,  C02,  and NOx levels were measured using continuous  emissions
monitors.
                                                                                 *
Analytical  Methods
      TCLP analyses  were performed  by Aquatec,   Inc.  (So.  Burlington,  VT)  using
EPA Method 1311.   The metals in the TCLP extracts were determined by  EPA  Hethod
6010. Total  metals  In  the SSM, slag, and particulates were determined using EPA
6000 and 7000 methods,  with  the exception that  the total  digestion  of the
samples was performed using a modified ASTH  E926-88 (the EPA digestion methods
do not completely  dissolve the  solid matrix).   Preparation of stack samples for
metals determination followed the Multiple Metals  Train method.  The accuracy of
all metals analyses  was  verified  using  check standards from EPA or  other
sources.   Analyses of the soil  for fuel  properties, major constituents,  and  bulk
density were  performed  using standard ASTH methods.  Particle size
determinations were  made by way of standard  U.S.  sieve numbers. Quality
assurance results  for the analytical  measurements  are given in Section 7.0.
                                       -30-

-------
                                   5.  RESULTS

      Four major  results were obtained from the Phase  I  and Phase IIstudies.
They are as follows.
1. The  Cyclone Furnace successfully vitrified  the SSM  feed and produced a
    leachate that  passed the TCLP test.

2. The  Cyclone Furnace achieved a volume reduction  of  25-35% when
    treating  SSM  during Phase I and Phase  II.

3. A majority of  the heavy metals in the SSM were retained in the slag
    during treatment in  Phase  II.

4. The  Cyclone Furnace operated well during treatment  of SSI and produced
    no  unusually  high  levels  of gaseous  emissions.

Each of these  results  is discussed in  more  detail  below.

Vitrification  as  Measured by TCLP Test Results.
      The pilot cyclone furnace was  successfully used to vitrify an EPA
Synthetic Soil  Matrix  (SSM)  spiked with 7,000 ppa  lead,  1,000 ppm cadmium,  and
1,500 ppm chromium.  A photograph of the vitrified SSM  is shown in Figure 8.
TCLP results  for  the Phase  I  and Phase II heavy metals  tests are shown in Figure
9, and  original analytical  reports are presented  in  the  Appendix.  Table 6
Summarizes  the  results  achieved.
                                       -31-

-------
FIGURE  8 Vitrified  Synthetic Soil Matrix
                                  -32-

-------
f<
J 1i
ci
£
1 I

S
fcfcf
» s
CO -:-
to O
< I
3 '
yj ,
5
...
x ;






0


0



§
0

§




„







—
:
„






































o
^
is

i
j




n
p
W-
y/K
W-

wx:






5551














^
§J SSM
p
Jw^ p.^*^^
M r^"™111""^ 	 -~^\



SSJU SSM


ibUKt a
Tox i c i ty Cha ractftr i s t i c Leach i ng Procedure-  {'!'Cl>')  kesu 11 s

-------
                                    Table 6
          Results of TCLP Tests for Untreated and Treated SSM

UNTREATED SSM
Cadmium
Chromium
Lead
TREATED SSM
Cadmium
Chromium
Lead
Phase I
mg/L

54.2 ¥ 3.6
2.3 I 1.3
104 ¥34

0.13 ¥ 0.05
0.11 ¥ 0.09
0.20 1 0.06
Phase II

34.2 * 2.9
0.48 ¥ 0.08
74 ¥ 0.0

0.07 ¥ 0.03
0.04 ¥ 0.08
0.20 ¥0.11
With Borax
Flux

30.3 ¥ 0.57
0.20 ¥ 0.11
50.6 ¥ 3.5

0.27
0.02
0.39
Regulatory
Levels ^g/L

1.0
5.0
5.0

1.0
5.0
5.0
        All of these treated SSM TCLP results are well below the TCLP  regulatory
limits set by EPA. The  results  show that the cyclone vitrification process
succeeded in producing a non-leachable slag.  All of these TCLP results are
close to the analytical detection  limit  and, hence,  the  results for both Phase I
and Phase II tests are  not  significantly different.
        The laboratory  blank submitted with these samples gave  lead, cadmium,
and chromium levels  below the detected levels.  For  two Phase I slag samples,
the measured chromium teachabilities were  not significantly different  from that
of the laboratory blank.
      The reduced TCLP results shown in Table 6  for  the  SSM from the Borax test
suggest a small amount  of stabilization  of lead in  the SSM  occurs  by the
addition of Borax.   These  differences still remain  when the dilution  of the
sample by Borax is taken into account.   This slight  trend would have to  be
verified by additional  sampling; nevertheless,  it did not  render the  SSI
non-hazardous.

      The vitrification treatment  results  in an easily-crushed,  glassy product
which minimizes the volume  required for  landfilling. The  slag from the tests
                                       -34-

-------
appeared to be a black,  glassy,  obsidian-like mass as shown in Figure 8.  Some
large,  white,  glass participates  are  readily visible in the slag  fragments.
When viewed under a low-magnification microscope,  both the slag (soil)  matrix
and the embedded white particles  appeared  to  have  completely  melted. Yhen
examined by a Scanning Electron Microscope-Energy Dispersive  Spectroscopy,  the
white particles are enriched in oxygen and silicon and,  thus,  may be composed of
silicon dioxide  (quartz).   The darker regions are enriched in  aluminum,  iron,
calcium,  and magnesium,  but  also contain  oxygen  and silicon.
      Did the Cyclone Furnace  immobilize metal contamination  in the vitreous
slag it produced, or did the high process temperatures volatilize all of the
metal  contamination?    This can be evaluated by calculating the  percent of each
heavy metal that was  teachable  for  the untreated and treated soil as given in
Table 7.
                                   TABLE 7
        Percent  of Leachable  Metals Before  and  After Treatment
                            (Phase  I and Phase  II)

Heavy
Metal
Lead
Cadmium
Chromium
Phase
% of Total
Metal Present
That Leached
Before
Treatment
(ssm
29
84
3.8
I
% of Total
Metal Present
That Leached
After
Treatment
(Vitr. SSM)
0.18
2
0.07
Phase
% of Total
Metal Present
That Leached
Before
Treatment
(SSM)
20
57
0.55
2
% of Total
Metal Present
That Leached
After
Treatment
(Vitr. SSM)
0.09
0.70
0.02
      The percentage of metals that leached  from  the  slag  was  less  than that for
the SSM feed for each metal tested and for both  phases of testing. These
                                      -35-

-------
results indicate that the vitrification process has  changed  the
physical/chemical form of the soil  in such a manner  as  to  render the heavy
metals much less leachable.

Volume  Reduction
      The treatment of the synthetic soil matrix resulted  in a volume reduction
of 25-35%  as calculated  on  a dry basis.   Figure 10 shows the volume  per ton of
SSM  or slag which must be sent for disposal.   The volume for SSM  (dry basis)  and
                                       -36-

-------
           SSM VOLUME REDUCTION
CO
«w
o 2
1
u
c
»- 2
OT
u>
0 1
X '
O
1 t
w
1
_j
O


1


1


.
1

1


•'


_


—



***"




—

















25%

3S%














































               SSM
SSM



I
SSM



i!
       FIGURE 10

-------
Phases I and II vitrified slag are  shown.   Approximately 35% and 25%  volume
reduction was  obtained by vitrification of  dry  SSM and  wet  SSM, respectively.
The volume reduction  is a combination of 22% mass reduction by calcination of
limestone component of SSM and the increased bulk density from 80 Ib/eu  ft for
SSM to 86-92 lb/GU ft for slag.   The resulting volume reduction  estimate
calculated on  a dry basis is conservative since the  as-received SSM contained
approximately 25% water,  which will be vaporized and contribute  further  to
volume reduction.
      Differences in  volume  reduction  calculated  for  Phase I and Phase II  may
simply reflect the  difficulty  in obtaining representative samples of  the wide
particle size ranges  in  the  slag.   Still,  the Phase  II (25%) volume reduction is
probably a more accurate measurement because special  care was taken to assure
that water was removed from the collected slag after  the test.

      A specific  volume reduction for  the  Borax  test could not be calculated.
However, the total  volume reduction is  expected to decrease because  of: (1)  the
addition of Borax,  and  resulting ash,  to  the feed SSM; and (2) the lower bulk
density of the resulting slag (81  Ib/cu  ft)  compared with the non-Borax  slag
 (86-92  Ib/cu ft).

Metals Retention

      A mass balance for total  ash,  cadmium, chromium,  and  lead was  performed
for  the cyclone furnace treatment process.   A description of the way  in  which
metal mass balances are calculated as well as examples  of the  calculation tables
used for the Phase II mass balances are  attached  in  the Appendix. The purpose of
                                       -38-

-------
the mass balance was to determine the fate of the heavy metals during soil
treatment.   During the thermal vitrification process, heavy metals partition
between the vitrified  slag and the stack flyash.   It is desirable to maximize
the capture of the heavy metals in the non-hazardous vitrified slag.

      For the Phase I tests, the  overall mass balance achieved was 79 to  103%
output divided by input, and the  heavy  metals  mass  balance accounted for 65 to
77% of the input lead, 56  to 61%  of the cadmium,  and  141  to  145%  of  the
chromium.
      The lead and cadmium were below 100% consistently. Heavy metal deposits
on the wall and convection pass of  the  furnace were likely the most important
factor in lead and cadmium mass balances below 100%.

      In the case of chromium,  mass  balances in excess of 100% were calculated.
The most likely source of excess chromium was  a  newly installed refractory  which
contains 9.6% chromium oxide (Cr2Qj}( and "bake-out" or abrasion  of the material
elevated the stack chromium levels.

      Analytical accuracy  is also  a source of errors. As  a part of analytical
quality assurance, spike  samples,  containing  a known amount of  heavymetals,
were measured.  Cadmium  and lead  in the slag were  detected within  15%.

      An additional  source of error may have been in the  assumption that  no
vapor phase metals exist after the  Multiple Metals Train filter, operated at
120°C.

      For the Phase  II tests,  the  overall  and heavy metals mass balance were
                                       -39-

-------
closer  to 100%.  An  overall  balance achieved 102 to 107%  input,  and the heavy
metals mass balance  accounted for 74 to 87.5% of the lead Input,  50.5  to 71.5%
of the cadmium, and  78.9  to  96.8% of the chromium.   The use of chromium
refractory  was minimized to  prevent any  chromium contamination.

      Determining the  fate of heavy metals in the  cyclone furnace depends upon
determining the relative  amounts of SSM that leave the cyclone  furnace in the
slag and  fly  ash  and a determination of the concentration  of metals  in each of
those streams.  Since the exhaust gas  from  the  cyclone is  cooled to 120*F prior
to release to  the atmosphere,  all of the  metals that escape the cyclone furnace
should be captured in  one of these two solid streams.   None of the metals should
be present  In the exhaust gas in the gas  phase. A discussion of  the relative
mass flowrates of the  fly ash and slag streams and of  the relative metals
concentrations in each  is presented below.
                                       -40-

-------
Mass Flowrates  of the  Fly Ash and Slag Streams

      Tests  showed  95  to 97% of the non-  combustible portion of the  input  SSM
was incorporated within  the  slag.    The amount  of SSM leaving the  furnace as
flyash was approximately  5-7%.   Because the  generation of flyash will be partly
a function of fuel  particle size, and because  drying the SSM produced a finer
particulate,  this  5%-7°/o estimate  is higher than that found for a wet  feed
system.    A portion of the heavy  metals from the  SSM will condense on the flyash.
This flyash  residue may  be  treated by  another technology or  simply be recycled
to  the  cyclone  for  further  treatment.

      The Borax flux  added  during one of the Phase II tests, appeared to
facilitate the  movement  of  slag out of the cyclone furnace  barrel.  When Borax
was added, the flyash produced  increased  to 3.53% of the input SSM, presumably
due to  vaporization of sodium from the Borax.

Relative  Concentrations of Metals  in  the  Slag and Fly Ash

      During the Phase I and Phase II heavy metals tests, soil and slag samples
were collected,  composited,  and analyzed.   The  total  metals results,  averaged
and reported on a  dry basis,  are given in Table 8.
                                        -41-

-------
                               TABLE  8

    Total Metals  in Soil,  Slag,  and Multiple Metals Train
   	Particulates	
                                          Total Metals,  ppm  (rag/kg)
Sample
Phise 1
CoiiiDOSltt Soil (Orv SSM)
46 Ib/hr
141 Ib/hr
reagent blank
Cadmium
1316 1 40*
1223 ? 34
<0.05
Chromium
1391 ?86
1339 ? 93
<0.05
Lead
8007 ? 248
73901214
<0.05
Composite Slag
  46 Ib/hr
  141  Ib/hr
  reagent blank
HuUlole Heta1s_Tra1n Partlculates
  46  Ib/hr
  141  Ib/hr
  filter blank
Phase II

Composite Soil (SSM.
   100 Ib/hr
   200 Ib/hr
   300 Ib/hr
   200 Ib/hr + Borax
   reagent blank

Composite Slag
   100 Ib/hr
   200 Ib/hr
   300 Ib/hr
   200 Ib/hr + Borax
   reagent blank
Drv Basis)
                     101
                  134 T  3.2
                   <0.05


                   15146
                   14816
                      15
                     1227
                 1261?17
                    1329
                     1259
                    <0.5
                      113
                  190 ? 6.
                      179
                      284
                    <0.2
    1907
2169* 147
  <0.05


   12493
    9893
     108
    1527
1550 ? 14
    1594
    1565
    <0.5


    1455
1488 ?10
    1421
    1208
    <0.2
    1624
2432T221
   <0.05


   80414
   99880
     149
    7198
7708 ? 110
    7701
    7838
    <0.5


    2077
3592 T 56
    2552
    3834
    
-------
When compared with the  soils  metals levels,  the slag was relatively enriched in
chromium and depleted in  lead and  cadmium.    The capture of heavy metals in the
vitrified slag from  all tests ranged from 8-17% for cadmium, 24-35% for lead,
and 80-95% for chromium.
      Addition of 10% of  a Borax flux did not significantly improve the heavy
metals capture in the vitrified slag despite a decrease  in cyclone operating
temperature  of approximately 10§*F.
      Several  other  trends can be  seen  from  this data.  The capture of  heavy
metals in the slag increased  with  increasing feed rate,  likely due to shorter
cyclone furnace residence times.   As expected, less  volatile metals were more
readily captured in the slag.    The capture of metals in the slag increased with
decreasing metal volatility.  This  suggests the  cyclone  vitrification process
would be well suited to treatment  of  low volatility contaminants,  such as  many
radionuclides.
      Lower  cadmium,  chromium, and  lead levels  were observed in fly  ash from the
Borax tests.   More fly  ash was  generated  for the Borax tests, however.  Thus,
metals Missions rates were only slightly lower for the Borax test.
      Figure 11 shows the estimated overall  split  of heavy metals betweenflyash
and vitrified  slag.   For  the Phase  I  dry soil feed,  from 8 to  17% cadmium, 24  to
35% lead, and  80 to  95% of chromium were retained in the slag.   For the Phase II
wet soil feed  system, from 12  to 23% cadmium, 38  to 54% lead,  and  78 to 95%  of
chromium were  retained  in the slag.   The ranges were determined  using
non-normalized and  normalized  concentrations  of heavy metals as  determined by
mass balance (see Section 5.0,  D).
                                       -43-

-------
                       INPUT
                            SLAQ
                                       ASH
A. PHASE 1 (DRY SOIL, 141 LB/HR)
          Cd
                  8 to  16
                                                  24 tO 35
                         TO
                         m
             80 TOM

B. PHASE 2 (WET SOIL, 200 LB/HR)
              12 to 23
                  ASH
              CORY BASIS)
                                                   TO 54
          Cr
 S
TO
   ASH
(DRY BASIS)
                                                          3.3
            78 to 95                            96.7
  FIGURE  11 Heavy  Metals and Ash  Mass  Salance
                               -44-

-------
      Figure  12 shows that heavy  metals content in the  slag increases  with



 increasing SSH feed rate between 50 to 300  Ib/hr.  Since  fuel  (natural gas)  feed



was relatively  constant, this suggests that increasing SSM feed rate reduces the



 solid residence time (and/or slag temperature,  see Appendix figures)  in the



 cyclone furnace and,  consequently, reduces vaporization  of heavy metals into the



 flue gas.  This  increasing  capture  with feed rate shows some  promise  for further



 metals capture  optimization,  and is an encouraging trend for process scale-up.



      An attempt  was  also  made to correlate the different behavior of  the metals



 during cyclone  treatment with their volatility. The temperature at which the



 metal vapor pressure was 100 iw Mercury  was  chosen  as the volatility parameter.



 Figure 13 shows the heavy metals retained in the slag as a  function  of



 volatility  of  the metal.   A marked trend was obtained, and we  concluded that



 increasing volatility is the  dominant  factor over  the fate of  heavy  metals.



 Figure 13  shows the volatility of the metal is  inversely proportional  to the



 slag metal concentration.   These results suggest that  the  cyclone vitrification



 process may show very high capture for very low volatility  contaminants,  such as



 many radionuclides.   Conversely,  high volatility metals  are  likely to  be



 concentrated  in the flyash which  may then be suitable  for metals recovery.



 Intermediate  volatility species, such  as lead,  are captured to some  degree in



 the flyash  and may be recycled to the  furnace to increase the overall  capture of



 the metal  in  the  slag.



      Figures 11 and 13 suggest better capture  of the metals in the slag  for the



 Phase II wet  feed system compared with the Phase  I dry soil feed system.  The



 reason for the  improved  capture  may be a combination of  any  of the following:



 (1)  increased  feed rates, resulting  in lower slag  temperatures and,  thus,  less



 metals volatilization;  (2)  reduced soil residence time  in  the furnace  and, thus,



 less  metals  volatilization; or (3) larger particle size  distribution in the  wet
                                        -45-

-------
FEED RATE AND HEAVY METALS CAPTURE
  4.0
I-
Ifl
g 3d
  2.0
I
  0,2
 i

 i
      -O
              100    ISO


                SStt
250
   FiCtLWt 12 Heavy Me tils iip-Wre v^

-------
VOLATILITY & HEAVY METALS CAPTURE
  90
                         I AMD    II
w
m
1
s
z
  50
  30
  10
       D
       A
       O
                                       Cr
                                       O
                                       A
    I	 I	t	1	1	1	1	1	i	i	1	 t 	1	i	 t 	I.
                                       _t__j_
     §00   800
                             100 mm Mg
    'IGURt 13     Hetdls Captyre vs. Volatility Temperature

-------
SSM, thus reducing the  surface  exposed  for metals volatilization.
      With the possible exception of cadmium, the  addition  of a 10% Borax
fluxing agent did  not significantly  improve the  capture of the heavy metals.
For the Borax test; from 17.9 to  30.5%  cadmium, 37.8 to  54.7%  lead, and  62.8  to
91.7% of chromium  were  retained in the slag. The Borax  flux reduced the slag
temperature  from 2430°F to 2320°F by reducing the  natural gas load  from 5 to 4.1
MBtu/hr.  Only for the  most volatile metal,  cadmium,  does this temperature
difference  appear to affect volatilization.  This small improvement in  cadmium
capture Is offset  by  an increase in volume to be processed  (and,  thus,  decrease
in volume reduction for a given weight of SSM treated)  and  an  Increase in the
weight of potentially hazardous  flyash stream.  Still,  the  Borax  improved soil
melting and tapping from the furnace.   If a small amount of Borax can  improve
soil  melting,  the feed rate may be  increased for a given heat input rate.

Operab i1i ty/Em i ss i ons
      Stable cyclone operation was  achieved  during the  pilot  tests.
Post-furnace CO, C02,  and NOX levels were measured using continuous emissions
monitors,   Average levels measured during  the heavy metals tests are given  in
Table 9.
                                    TABLE 9
         Average  Phase I  CO,  C02,   and  NOx Levels (Spiked  SSM)

Measurements
Cyclone Stack CO, Stack Nox
Load Feed Rate , PIP at Stack 0)3 , ppm at 3%
Test MBtu/hr lb/ hr 3% 0, % Oz
11/15/90 4.7 46
11/16/90 4.8 141
18 11.4 365
19 11.5 319
                                       -48-

-------
       Although  the NOx  levels are relatively low,  the measured  NOx  levels can be
 further reduced,  if desired,  by application of NOx reduction technologies. This
 may be necessary for wastes  intrinsically high in nitrogen compounds which
 produce higher levels of NOx emissions.   Carbon monoxide (CO)  levels  were  very
 low,  indicating stable combustion.   The C02 levels measured  are  typical  for
 combustion of natural gas.
       The slag did  not  appear homogeneously melted;  larger particles appeared
 unmelted,  but after  viewing  under a microscope, the  particles  appeared
 completely melted.
       Average post-furnace NOx, C02, and  CO  levels  for the  five heavy metals
 tests  in  Phase  II were 322 ppm,  10.5%. and 27  ppm,  respectively  (see Appendix
 for specific measured values).   These  levels are similar to  those measured in
 Phase I.   The Appendix contains  graphs of NOx levels and slag  temperatures
 plotted against feed rates for the preliminary and heavy metals tests.  As
 expected,  the NOx  levels decrease with increasing SSM feed rates  (and, thus,
 cyclone temperatures).   The  slag temperature was sensitive to  the SSI feed rate;
 it decreased  from 2470 to 2400°F.when SSM  feed rate  increased from 100 to  300
 Ib/hr, respectively  (see  Appendix  figures).   The flyash (measured  at convection
 pass exit) remained  low,  at  approximately 2% of SSM  input (See Appendix  Dust
 Loading data).
      Some operability problems and feed rate will be improved  by full-scale
 design and operation.  For example,  the  surf ace-area-to- volume  ratio of the
 pilot unit is much larger than that expected  for a full-scale unit.  This  will
 decrease the heat input  required  to  melt  a given amount of soil.
      With the added  Borax, the slag temperature was reduced from  2430°F  (200
Ib/hr  SSM feed  rate)  to 2320°F  and NOx  levels decreased from  318-337  ppm (200
Ib/hr  feed  rate)  to 260 ppm, as  shown in the Appendix figures.
                                         49-

-------
                                6.  QUALITY ASSURANCE

      Quality assurance systems audits  and a performance evaluation audit were
conducted by the B&W Quality Assurance Unit.   The activities included an audit  of
the instruments and calibrations,  heavy metals  tests soling procedures, and an
audit of the Aquatec laboratory (Phase I).   Audit and  performance  results are
summarized below.

Systems Audits
      During Phase  I,  the  systems  audit of the  instrument calibration found  that
the transducer used  for the  indication  of secondary combustion air flow rate was
calibrated to an accuracy  specification of 0.4% of  span (0-5 volts).  The
manufacturer's  specification  for accuracy deviation  is  0.2%  of span and,  thus;  the
instrument was out  of  calibration.   Because  secondary air flow rate is not a
critical measurement,  this deviation had no  impact  on  the project. During Phase
I, the  sampling objective of  30-minute  intervals for sequential  soil (SSM) and
slag samples was not met because the sampling times  required to obtain a given
weight of soil from  the soil  sampling valve  were longer than anticipated (up to 35
minutes per sample).   Thr  impact of this deviation  from the  Quality Assurance
Project Plan  (QAPP)  was minimal because the  soil sampling was nearly continuous.
A second sampling deviation was the  use  of a metal   shovel to collect the slag from
the slag tank.   Ideally, metals collection devices  should be avoided for trace
metals sampling; however,  plastic  and glass  devices could not be used.  The effect
of metals introduced from the shovel,  if any,  would result in a more conservative
estimate of the metals  teachability.
      During  Phase II, the systems  audit  found,  for  two multiple  metals trains
(16:10  and 17:44 on  9/9/91), the pump was turned  off before removing the probe
from the stack, while  Method  5 specifies that the probe is removed before the pump
is shut off.  The  impact of this deviation is thought  to be  negligible.  The train
performed at  16:10  (200 Ib/hr test)  omitted the  0.1N  HNOs  probe rinse specified  in
the Multiple Metals Train procedure [3].   For the train  run at 17:44 (also 200
Ib/hr test),  the percentages of the total  cadmium, chromium,  and lead found in the
0.1N  HNOj rinse were 2.6,  4.9,  and  2.4%,  respectively.  This  can be compared  with
                                         -50-

-------
the relative percent difference  for the total  cadmium,  chromium,  and lead
collected by the  two trains which was 25, 4 and 2.5%.  respectively.  Thus,  for
chromium and lead, the differences in the total particulate metals found can be
completely explained, by  losses  due to omitting the 0.1N HNOj rinse (with an
overall  impact  of a few percent  difference).  The omission  of the 0.1N HNOj  rinse
explains only a small portion of the differences for cadmium. Thus, the  effect  of
omitting the  0.1M HNO| rinse  is  insignificant  for  cadmium. Bacause  the
particulate stream is a  small portion of the overall materials balance  for the
cyclone process,  the differences introduced by omitting the 0.1H HNOj rinse  are
not thought to  significantly  affect  the  mass balance results for  the project.
      The QAPP  specified  that ASTN Method E886 be used for  the digestion  of  soil
and slag samples  for total  metals.   However,  to achieve complete digestion of
these matrices, modifications to the ASTN method were required.  The Modified ASTM
E886 Method is attached in the Appendix.

Performance Audits for Critical Measurements
      The quality assurance results for the critical measurements, TCLP  of  the  SSM
feed  material, and the vitrified  soil product are given in Table 10. The TCLP
analyses met Performance  Evaluation objectives based on results for EPA check
standards  of 97.2*91.5X,  compared with an acceptance criteria  of 90-110%.
Detection  limits surpassed  those specified in  the QAPP. matrix spikes ranged from
79-152%  recovery for Phase  I  and  25-118% for Phase II,  which exceeded the cadmium
and lead QA objectives,  but was within  expected performance for environmental
matrices.   Because the  measured values were orders of magnitude  above  or below
the TCLP limit, exceeding this criterion should not affect  conclusions  made
regarding whether a sample met or exceeded TCLP limits.
      For the TCLP leaching  analyses,  precision was  determined  by duplicate
determinations  of one slag and one soil during each heavy metals  test. The
precision for several of the measurements'exceeded the QA objective of 20%
relative percent  difference (%  RPD) .   Precision  objectives may  have  been  higher
than can reasonably be expected  of these samples (indeed,  50% is generally
considered  excellent precision for environmental samples).  The lack of precision
for certain soil  TCLP analyses may have been due to the heterogeneous nature of
the soil matrix.   The soil  contains a wide range  of particle sizes,
                                        -51-

-------
                                        TABLE  10
                              QA Data  for TCLP Analyses
Cadmium
Quality assurance
Parameter
Phase 1
Accuracy , %
Precision, %
soil*
slag*
TCLP Detection
Limit, n/l
Phase II

Objective

50-150

20
20

10


Found

100-138

2,2
6,43

9.1

Chromium

Objective

50-150

20
20

20


Found

79-107

4,98
41,91

10.6

Lead

Objective

50-150

20
20

5


Found

108-152

11,64
9,25

1.3

 Accuracy, %
 Precision, %
50-150
39.7
50-150
100-118
50-150
25-50
soil*
slag*
TCLP Detection
Limit, fiq/L**
20
20

10
5,3
29,6

10
20
20

20
3,1
62,26

10
20
20

5
'6,10
22,3

5
 • Data for two determinations  (one  for  each heavy metals test).
 **Data from  blank  determinations  used.

which stratify  in layers,  making representative  sampling more difficult. A relative
enrichment  in smaller particles relative to the  bulk sample would increase the detected
metals  (small particles contain higher amunts of the contaminants because of their
relatively  high  surf ace-to-volume  ratio).   Because the  soil samples  already exceeded the
TCLP limits for  lead and cadmium by 20-50 times,  the  higher-than-expected relative
percent difference has  no  impact on  the  project.   For example, for lead in one soil
sample, a relative percent  difference of  64% would still result in a soil which fails
the TCLP  by one order  of magnitude.
      The precision  for a  number of slag TCLP leaching analyses also did not meet  the  QA
objectives.    This was likely due to the very low levels of teachable metals in these
samples that  gave results  near the analytical  detection limits. As  measurements
approach the  detection  limit  for an analytical  method, the  relative percent differences
between duplicates is  expected  to  increase.   This was especially evident for the
chromium measurements  (up to  91% RPD).   For example, for the  three slag samples analyzed
from the Phase I  11/15 test, one  sample was measured to be at the detection  limit,  one
at  1.5  times  the  detection limit,  and one was at 4 times the detection limit.  Because
the slag  samples  were  below the TCLP limits  for lead, cadmium, and chromium by one to
                                            -52-

-------
two orders of magnitude, the higher-than-expected relative percent difference has no
impact on the project.

Performance Audits for Non-Critical  Measurments
       The quality assurance objectives and  results  for the non-critical measurements
(total metals analysis) are given in  Table 11.   The metals analysis met QA data quality
objectives for accuracy based on  recovery of check standards added to matrix spike
samples.   Precision,  determined  from duplicate (or more) analyses  of samples, exceeded
the QA objective of 20% relative  percent  difference,  with  the exception of cadmium in
the multiple natals train  in Phase II (the precision  appears  to be related to the
volatility of a given metal and may reflect  differences in combustion conditions rather
than  analytical differences).   Laboratory blank  levels were well below  the detected
levels  for the metals  determinations.   For  the multiple metals trains, the  acceptance
criterion  for percent isokinetic sampling was  90-110%.  For  Phase I and  Phase II tests,
percent  isokinetic sampling was 99-101%,  which exceeded  the acceptance criterion.
      The non-critical measurements included analyses of check standards during
continuing calibration.  Recalibration was performed  when  continuing  calibration
standards  failed to  meet  the 90-110%  acceptance  criterion stated  in theQA Project Plan
                                            -53-

-------
                  TABLE 11
QA Data for Non-Critical Metals  Determinations
       Cadmium
Chromium
Lead
Quality
Assurance
Parameter
Phase /
Accuracy, %
soil
slag
Precision, %
soil
slag
MMTS
Phase //
Accuracy, %
soil
slag
Precision, X
soil
slag
MMT*
*Multiple Metals

Objective

50-150
50-150

20
20
20

50-150
50-150

20
20
20
Train

Found

81
114

2.6-4.3
1.9-6.4
5.9

107
92.0

0.7-5.5
0.5-4.4
25


Objective

50-150
50-150

20
ao
20

50-150
50-150

20
20
20


Found

106
88

1.6-12
4-13
5.2

103
96.9

0.3-3.4
1.1-4.7
4


Objective

50-150
50-150

20
20
20

50-150
50-150

20
20
20


Found

77
110

3.8-5
1.7-17
10

96.8
95.6

0.3-5.0
0,08-2.1
2.5

                      -54-

-------
                       7.  CONCLUSIONS AND RECOMMENDATIONS


Conclusions
      The  following  conclusions  can be drawn about the  ability  of the cyclone

furnace to process  organic and heavy metal contaminated soil  based  upon the

results of the Phase I and Phase II tests.  These  conclusions are as  follows.


1.     The Babcock & Wilcox six million Btu/hr  pilot cyclone furnace was
      successfully used  to vitrify an EPA-Synthetic Soil Matrix  (SSM)  spiked
      with 7,000 ppm lead, 1,000  ppm cadmium, and 1,500 ppm chromium.  When
      operated at  50 to  150 Ib/hr  of  dry  SSM feed,  and  from  100-300 Ib/hr  of wet
      SSM feed,  the cyclone technology was able to produce a non-teachable
      product (well  below  TCLP limits).

2.     The cyclone vitrification process would be well suited to  treatment  of low
      volatility contaminants, such as many radionuclides. At least  95 to 97% of
      the  input  SSM was  incorporated within the slag.  During the thermal
      vitrification  process,  the heavy metals partition between  the vitrified
      slag and  the stack  flyash.   The capture of heavy  metals in  the slag was
      found to  increase  with  increasing  feed rate and with decreasing  metal
      volatility.

3.     Stable  cyclone operation was achieved  during the pilot tests.  Using
      natural gas as the fuel,  the CO and NOx, stack emissions  gases  from the
      process were  within  acceptable  ranges.

4.     The  treatment  of  the synthetic soil matrix resulted  in  a  volume reduction
      of 25-35%  (dry basis).   Vitrification results in an easily-  crushed,
      glassy product.


Recommendations  for Future Work

      The  cyclone furnace  may be best suited to the treatment of soils

contaminated by  organics and  either very  high- or  low-volatility

metals/radionuclides.   This statement can be  explained as  follows:

       (1)  the high  heat release rates and turbulence make the cyclone
      vitrification  process well suited  for organics destruction;

       (2)  vitrification of very high-volatility metals  or radionuclides  would
      tend to concentrate those elements in the relatively  small flyash stream,
      which may  then be suitable for recovery;

       (3)  vitrification of very low-volatility metals or  radionuclides would
      tend to concentrate those elements  in  a  non-teachable product  (the  slag)

                                       -55-

-------
      and  produce only low flyash  levels.   Such elements are  present  at
      Department  of Energy and Department of Defense contaminated soil  sites.
      Feasibility  for  these  elements  will  be verified in the  SITE Demonstration.
For  intermediate volatility  metals/radionuclides,  the best process option may be
to recycle the flyash to the furnace in order to maximize the capture of heavy
metals  in the non-leachable  slag  and minimize the size  of the flyash waste
stream.

      The flyash  recycling concept should be  demonstrated on a pilot- scale
process to verify feasibility and potential  advantages. The effect on the
percent capture of  metals  in  the slag and TCLP performance should be evaluated.
Even  if recycling  proves  undesirable,  the heavy metals are contained in a
relatively small flyash stream that may then be stabilized for disposal.  This
represents a much smaller  stream requiring  hazardous waste treatment and
disposal  (3-5% of the original contaminated soil).

      The heat  input  for  a given rate of soil feed for  the pilot-scale unit
should  be improved  in the field-scale design.  This  improvement  will comefrom
lower cooling surf ace-to-furnace-volume ratios which will result in  lower heat
losses  from  the unit.  The feed rates achieved during this project are  likely
minimum  values because of the limits imposed by working  with  a cyclone furnace
designed  for coal combustion rather  than waste vitrification.  Feed  rates will
be increased by  improved  gas  burner design and placement  for a vitrification
application.

      In  addition to the  Emerging Technologies effort,  a U.S. EPA SITE
Demonstration of the cyclone furnace was performed  in November of 1991. Heavy
                                       -56-

-------
metals, volatile and  non-volatile radionuclides,  and organic  hazardous
constituents were  spiked into the synthetic  soil  matrix. Measurements will  be
made to verify  previous TCLP leachabilities,  volume reduction, and  heavy metals
capture in the slag.   DRE's  for organic  contaminants  will be measured. The
immobilization of radionuclides  will be measured using American Nuclear Society
leaching procedures.   Conventional air pollutants will be  measured  to test
regulatory  compliance.   Potential technology applications  and  estimated process
economics will be  addressed.

      Based on the results of the SITE Demonstration,  BiW  will assess the
further  development/commercialization of the cyclone vitrification process.
Conceptualization  and  design  of a full-scale  system have not been performed. An
important next step is the design, fabrication,  and demonstration of  a
full-scale  vitrification furnace. The operation of a  full-scale  unit can be
used to obtain  accurate process economics.
                                       -57-

-------
                                  8.  REFERENCES


1.     P. Esposito, J. Hessling, B,  Locke, M.  Taylor, M.  Szabo, R. Trumau.  C.
      Rogers, R. Traver and E. Earth,  "Results of Treatment Evaluations of a
      Contaminated Synthetic Soil," JAPCA. 39:  294  (1989).

2.     RREL Quality Assurance Project Plan No.  P-309-B. submitted by  B&W to RREL
      July 2, 1990,  and Phase II modifications submitted by letter to RREL
      August 28, 1991.

3.     "Methodology for the Determination  of  Trace Metal  Emissions  in  Exhaust
      Gases From Stationary Source  Combustion  Processes," Subsection  3.1  of the
      Methods  Manual  for Compliance with  BIF Regulations  (EPA/530-SW-91-010,
      December  1990).

4.     40 CFR 60, Appendix A, July  1990, Method 5.

5.     J. Nowok  and S.  A.  Benson, University of  North Dakota, Gas Research
      Institute  Report  No.  GRI-89/0078.
                                       -58-

-------
                                   9.  APPENDIX

Calculation of Heavy Metals Mass  Balance
      A  mass  balance  for total ash, cadmium, chromium, and  lead was performed
for the  cyclone  furnace  treatment process.   The purpose of  the mass balance was
to determine  the fate of the  heavy metals during Phase I (at  46 and  141  Ib/hr)
and Phase II (200 Ib/hr and  Borax test).   Proximate and ultimate analysis was
performed  to  determine the volatile compounds (e.g., CO, from CaCOj) In the SSM.
Each day the  soil feeder was calibrated before and after the tests,  and an
average  feed rate was used.   Each day's slag  was  collected and  weighed.  The.
weight was  corrected  for water.   The particulate  loading of flyash  to the stack
was isokinetically  measured and  averaged.  Some flyash also deposits  in the
convection pass or  on  the furnace walls.   The  convection pass  flyash  deposit
could not  be  measured,  but was  estimated at 50% of  the  stack  flyash.  This was
based on the  amount of convection pass deposit that has been  measured previously
with Ohio #6  coal  flyash  (50% of stack flyash).

      To determine the mass balance, total heavy metals analysis was  performed
on the  feed SSM, vitrified slag, and  captured flyash. For each test,  duplicate
Hultiple Metals Trains were collected and heavy metals were determined (with the
exception  of the Borax  test,  where only  one  train was performed). Slag and feed
soil (SSM)  samples  were collected  at approximately one hour  intervals.   The
samples  collected were composited  and analyzed  for total heavy  metals in
duplicate  or  triplicate.   The volatile matter, slag,  and flyash  loading were
normalized to  100%  of dry,  C02-free SSM.   The  results consistently  showed that
flyash  loading was very small  (5% or less of the SSM  input).
                                       -59-

-------
A normalized  and non-normal!zed mass balance was  calculated as follows:
(1)   The amount of SSM,  flyash,  and slag was  measured for each test,
(2)   A  material balance  was  performed on the SSM  and combination of
     flyash,  slag,  SSM water, SSM  CO,  in the flue gas (achieved 79  to 103%
      input for  Phase I  and 102 to  107% input  for Phase II).
(3)   The flyash and slag streams were normalized to  100%,  assuming  the
     average of the SSM  feed  rate measured before  and after the test.
(4)   Using  the normalized ash  and slag  percentages,  performed a mass
     balance  on lead, cadmium, and  chromium  (mass times concentrations).
     This mass balance in Phase I accounted  for 65 to 77% of the input
      lead,  56 to  61% of the  cadmium,  and 141  to 145% of  the chromium
      (chromium result discussed in Section 6.0, H),  and  in Phase II
     accounted for 74 to 87.5% of the lead  input,  50.5 to 71.5% of  the
     cadmium, and 78.9 to  96.8% of the chromium.
(5)   The mass balance was normalized  to 100% (100% = amount of heavy
     metals measured  in  input SSM using the  SSM rate and the SSM metal
     concentrations   --  this  assumes  the SSM  input rate and concentrations
     were  the most accurately  measured  parameters).
(6)   The mass balance range reported was the percent mass balance for  the
     slag with the lower end of the  range  being  the_non-normal 1 zed,  data
     and the  upper limit being the normalized data to which  15% was added
     to account for analytical error.   The  mass balance range for the
      flyash  was calculated  from (100   the slag range).
                                  -60-

-------
Dust Loading Data

Date
Soil Moisture Content (%)
SiacTAsHj^Torivut
Stack Pressure,* Water
Dust Sample, (g)
Flue Gas Sampled, (CuFl)
Temperature, (F)
Sample Flue Gas Mass, (to)
Total Flue Gas, fto/hr)
Barometric, "Hg
Stack Abs Pressure, (psl)
Gas Mol WetQht

920-91
25
1.77
0.55
046
3047
101
2.14
2793
28.76
14.14
29.64
i^ffc. *"•**/•••
6-21-91
25
201
055
0.51
30.42
103
214
2874
2892
14.21
2984

6-27-91
25
173
055
031
2594
114
179
3416
29.01
14.26
2964
w~* r\&jr
8-2791
25
04
055
007
2527
118
1.73
3360
2900
14,26
2984

82891
25
191
055
050
2507
114
1.73
3386
2903
14.27
2985

82891
25
1 49
055
051
2463
120
169
3361
2902
1427
2985
Identification Number
Dale
Soil Moisture Content (X)
Stack Ash,(%) of Input
Slack Pressure," Water
Dust Sample, (g}
Flue Gas Sampled, (CuFQ
Temperature, (f\
Sample Flue Gas Basi^ J6J__
Total Ftue Gas, (t»mr)
Baromeiric, "Hg
Siach Abs P'essurejjfwll
Gas Mol Weight
007-A10
82991
25
189
055
1.02
25.71
112
, 1.79
3383
2904
14.28
2965
009 A1 2
9391
25
1.94
055
1.02
2571
112
1.79
3474
29.04
1428
2966


•













































*?



Identification Number
Date
Soil Moisture Content (%)
Stack Asn,(%) of Input
Stack Pressure,* Water
Dust Sample, (g)
Flue Gas Sanded, (CuFl)
Temperature, (F)
Sample Flue Gas Mast, (to)
Total Flue Gas, (IVhr)
BarometriCj, "HQ
Stack Abs Pressurej (psij
Gas Mol Wetght















































































-------
                                                   SBS DATA AVERAGES
ooT-Aca
              Cyclone
W
                                                                 OM
                  W"
                                                                             CO
T
                                                                                       NOB
                                                                                                                    "iii"
                !<}*
                  U
                                                MO
                                               ~m
      ~w
                                                             is
¥
"SRT
_f_
     adT-'tef
                 4 I
                                                       BO
                WTO

                                                                                                                     IB
                                                                                                                    isr
                                                       in
                                                                 a an
                                                                                         208
                                                                                                                     In
  	ggg;
                                                       111
Ps>

-------
                                        SBS
CTk

-------
                 II         Metals
Test


%
to 1
AO1
A02
A0S

201,90
186.15



2.32
2LK1
asa
68. n
«i 1 1

107^34
107.66
102.12
208
2.3S
3.42
61.02
60.75
57.12
•             CO2 dry      Hindi 10%

-------
  en
              SOIL
                HEAVY METALS
                TCLP      	
                ASH MELT PROPERTIES
                MAJOR CONSTITUENTS
                % MOISTURE
                BULK DENSITY
                FEED RATE
                            CYCLONE
                            FURNACE
                             TEMP
                             92
                             COMB. AIR
                                    SLAG QUENCH
                                       WATER
                                                      POST FURNACE
                                                       HEAVY METALS
                                                       PARTICULATE LOADING
                                                       (ASH/SLAG SPLIT)
                                                       MAJOR CONSTITUENTS
                                                       GAS VELOCITY
                                                                               FLUE GAS
                                                                                CO
                                                                            BAGHOUSE
                                                                                           TEMP
                                                                                   J
                                                                                   i
                                                                               FT.Y ASH
                                          SLAG
                                            HEAVY METALS
                                            TCLP
                                            BULK DENSITY
                                            MAJOR CONSTITUENTS
                                            SLAG TEMPERATURE
rt .
7.
Sampling  locations and analyses  for the Phase I and Phase II heavy metala  tests used for the  heavy
metals  mass balance, TCLP leachability, and volume reduction.

-------
                                    II             and                 for Soil,
                                   and Fly Ash
Test

Sol Slag
% d Input
Stag
put,

Lead
Cadmium

?S36
1281
1S44

18?


11720
7874
38.0
ll.t
. 79.3 1
mo
i_ ms
14.21
74.0
50.5
83, S
SI .3
23.7^
84.8



                                                                                             _,_,,_,
I
m
— ]



?§SS
1246
1640
3S70
186


jfUfmr"* i
W sir ?r 1
LBad
Cadmium
Gtvanlunk
' ?838
125S
15611
3SS1
197
1461


we?
37-9
12.1
78.4
49 S
89.4
18.4
i?.sT
71.5
96.8
43,3
81.0

56.7
83.0


Lead



1261
1SSO
3K?
190
1466


64S1
37.6
12,3
ms
42.21
48.5
is. i
796
60.8
L 94.4
47.1
20.2
82.9
S2.9
79.8
17.1
ty| |^Q|
Tiaiwih
Lmml
GcvJbniuni
i»liyfiikjiri
&2i8
Id^l
t6l/
Joiii
2fW
1ZIU
/UWJV
V31O3


17.9
68,8
«i,5
1 j
16.0
79.3
67.S
78.9
47.6
28,5
79.7 :
S2.4
73.5
20,3

-------
CTl
~~l
I
       On
       (X,
       N— '


       1
         m
       O at
       2
                          Clean Soil Testing
                                    Soil
                             a
B3
                             Soil Feed Rate

-------
             MTO
                                  Clean Soil Testing
                                          Slag Jemof ratu res
CD
             I44t
         S
         w
             MM
             uw
                                              Soil Disperser Air Range: 9CM3Q (fb/hr)
                                              Total Load; 4J-5.3 (MBtu/hr)
                                      K)
                                                          ca
                                       Soil Feed Rite (LB/11R)

-------
   H»
                  Heavy Metals Testina
o
                                Mo                 |M
                                       12JB
*>  2f»

O
O
U
                               / \
                               /
                     4.14                     \
            Air: 134        '                      x,
                             lit

                      Soil feed

-------
         JU*
      E
      2
                    Spiked Synthetic Soil Matrix
                                               (ill)
                  No                        Ois     Air 128
                                     63
o
I
      WJ

      -2
      t/i
                                            .$Jr 134
         oat
                                     J*»
                              S<«1 Feed Rile
                                                                 .M*

-------
71-

-------
72

-------
                                    o
                              aquatec
                             KHVIHONHtHTAL ffUVfCffJ
                          75 Cron MountMi Dnvn, 5c. Buribifton, VT W403
                                  ret, ao2/4Si-io?4
   Babcock * Wilcox Company
   R&D Division,  Att:  A/P
   1562 Beeson  Street
   Alliance, OH 44601
   Attention
                                        Date        :  12/07/90
                                        ETR  Number:  24003
                                        Project No.:  90000
                                        No.   Samples:  24
                                        Arrived     :  11/16/90
                                        P.O. Number:  537-OA247838
       Jean Czuczwa
                                                 Page
     Itondortf tnolyM* tor* porforaod In accordrc* wtth Nothodt for Analysis of W««r and UMtM, M
    T««t H«Thod» for IvituBtinf Mitd UMt«, »-»**, or Stindvrd H»thod» for tit* iMMifwtion of y«t*r «rd
                         All rowlts *r«  in ••/( unlots oth«m
                               Comments/Notas
                                     73

-------
                                   o
                             aquatec
                            smmmmorrM, sutmxs
                         75 Crws Moan*** Ortm So. fceitngK*. VT
                                 TtL UZ/«a*. 10?4
   Babcock 4 Wilcox  Company
   RtD  Division,  Att:A/P
   1562 Beeson Street
   Alliance, OH 44601

   Attention  : Jean  Czuczwa
                                               Dat*        :
                                               ETR Numb«r:
                                               Project No.:
                                               NO. Saapl**:
                                               Arrived    :
                                                            12/07/90
                                                            24003
                                                            90000
                                                             24
                                                            11/16/90
                                               P.O. Nu*b«r: 537-OA247838
                                               Page
     Stindwd arw
            for
Lab  No./
     Method NO.
                         in •ccardrc* wit* Method* for Wly»l» »f Mt«r wri UMIM, IM-600/4/79-020,
                         UMta, w-t*4r or *tirdw4 M*tNxt» for t»i
                        All rMuiu ar* tn >«/l in I Ma •ttwrwiM not«d.
                 Sample Description/
                              p«ram«t«r
                                                             R«»ult
124383
125162
         Slag-Spik« 2,  1419:(TCLP Ext)
         6010                Cadmium, Total
         6010                Chromium,  Total
         7471                Lftad,  Total
         Slag-SpiKi
         6010
         6010
         7421
                     2,  1419:[MS](TCLP Ext)
                             Cadaiiuai,  Total
                             Chromium,  Total
                             Laad,  Total
124382DP Slag-Spike 2,  1419: [RZP] {TCLP Ext)
         6010                CadmiUB,  Total
         6010                Chromiua,  Total
         7411                L«ad,  Total
                                                                 170 a
                                                                  74 a
                                                                 155 a
                                                                 220 a
                                                                 166 a
                                                                 210 a
                                                                 110 a
                                                                 49 a
                                                                 121 a
124384    Slag-Spike 2,  1534-1543:(TCLP  Ext)
         6010                Cadmium,  Total
         6010                Chromium, Total
         7421                Laad,  Total

124386    Slag-Spike 2, 1730-1750:(TCLP  Ext)
         6010                Cadmium,  Total
         6010                Chromium,  Total
         7421                Lead,  Total
                                                                  53 a
                                                                 <20 a
                                                                 125 a
                                                                 166  a
                                                                  36  a
                                                                 132  a
                              ComB«nts/Not«s
a  * ug/1

   < Last Pag« >
                      Submitted By
                                   : //Jl.

Aquatec Ir.c
                                   -74-

-------
                                    o
                             aquatec
                             CMyiftOMMtMTAL S0IVICSS
                         75 Citwn Mount** Dm*, So, Bwriwftim. VT SS403
                                 TIL. HB/tM.1074
   Babcock & Wilcox  Company
   RiD Division, Att:  A/P
   1562 Beeson  Street
   Alliance,  OH  44601

   Attention :  Jean  Czuczwa
                                                Date        :
                                                ETR Number :
                                                Proj ect No.:
                                                No.  Samples:
                                                Arrived    :
                                                              12/07/90
                                                              24022
                                                              90000
                                                              22
                                                              11/16/90
                                                P.O. Nuaber: 537-OA247838
                                                Page
                          In ac««r«lv«« nith
            for IwMtwtinf Jolld UMfc, sy-S^A, or
                         All r«Kiitt ar* In i^/l
Lais No,/          Sa«3l« Description/
     Method   Ho.    "         Fmran*t*r
                                           fw»
                                               far t!M
                                                  not»d
                                                            of
124517    Soil-Spike 3,  1245-1310:(TCLP Ext)
         6010                Cadmium, Total
         6010                Chromium, Total
         6010                Lead, Total
124517MS Soil-Spike 3,
         6010
         6010
         6010
                        1245-1310:[MS]  (TCLP  Ext)
                             Cadmium, Total
                             Chromium, Total
                             Lead, Total
124517DP Soil-Spike  3,  1245-1310:[REP] TCLP  Ext)
         6010                Cadmium, Total
         6010                Chromium, Total
         6010                Lead, Total

124519    Soil-Spike  3,  1420-1433: (TCLP Fxt)
         6010                Cadmium, Total
         '6010                Chromium, Total
         6010                Lead, Total

124521    Soil-Spike  3,  1642-1648:(TCLP Ext)
         6010                Cadmium, Total
         6010                Chromium, Total
         6010                Lead, Total
                                                              Result
                                                                54000  a
                                                                  aao  a
                                                                73000  a
                                                                54000  a
                                                                 1670  a
                                                                81000  a
                                                                55000  a
                                                                  910  a
                                                                82000  a
                                                                46000  a
                                                                  890  a
                                                                55000  a
                                                                52000  a
                                                                 4400  a
                                                               132000  a
a   = ug/l

<  Cont.  Next  Page >
                              Comments/Notes
                                     -75

-------
                              aquatec
                             INYHIOHMIHTAL MHWOW
                         71 CfMn Mtmmmm Drw«, So- •uri«t(ton. VT C84BJ
                                  Til, «HliS§.tO?«
   Babcock 6 Wilcox Company
   R&D Division,  Att:  A/P
   1562 eeson  Street
   Alliance,   OH  44601

   Attention  : Jean Czuctva
                                                Date        :
                                                ETR  Number :
                                                Project  No. :
                                                No.  Samples:
                                                Arrived     :
                                                P.O.  Number:
                                        12/07/90
                                        24022
                                        90000
                                         22
                                        11/16/90
                                        537-OA247838
                                                 Page
     Iterator* mlyM* Mr* pM>f«r**4 In •cecrdvw* nit* *»thod§ for An«ly*U of Uotor
    Use NtttM* for Iv»lt«t1»j S«IU MMt«, W-144, «r Uaraterd
                         All rwuiU »r« <«t «g/l i*il
LabNo./           Sample  Description/
     Method *ff.               Parameter
                                                            UMtoo, tM-MO/i/7?-0»,
                                                             of Usttr «nd W*stwu«t*f .
                                                               Result
124523
         6010
         6010
         7421
                     3,  1230-1237: (TCLP  Ext)
                             Cadmium,  Total
                             Chromium, Total
                             L*ad,  Total
124523MS Slag-Spike  3, 1230-1237 : [HS]   (TCLP Ext)
         6010                Cadmium.  Total
         6010                Chromium,  Total
         7421                Lead,  Total
                                             137  a
                                             220  a
                                             250  a
                                                                  210 a
                                                                  320 a
                                                                  330 a
124523DP Slag-Spike  3, 1230-1237:[REP]  (TCLP Ext)
         6010                Cadmium,  Total
         6010                chromium,  Total
         7421                L«ad,  Total
                                                                   145  a
                                                                    81  a
                                                                   230  a
124525    Slag-Spike  3,  1418-1435:(TCLP  Ext)
         6010                 Cadmium,  Total
         6010                 Chromium,  Total
         7421                 Lead,  Total
                                                                    60  a
                                                                    28  a
                                                                  210  a
124527    Slag-spike  3,  1640-1649:(TCLP  Ext)
         6010                Cadmium,  Total
         6010                Chromium, Total
         7421                Lead,  Total
                                                                   107  a
                                                                   112  a
                                                                   250  a
                               Comments/Notes
i   - ug/1

   < Last Page  >
submitted  By J
                                                               Aquatec I n c
                                    -76-

-------
                                   o
                            aquatec
                                        some**
                             MowMaM Ditv*. So. ••utingian. VT M403
                                 TIL IB/*Si.l0?4
                 AftUlUrar* CA JL4R'E4frOlt Tn
  Babcock and Wilcox
         DMC 7 D«c«»b«r  1990
         fw»«»N« 90000
         ETTlNoe 24003  And 24022
                        16 Hov«mb«r  1990

T«t Mniwdi for EvmJmtun Sobd Wi
Kxorlaac* wi
•M.SW4440I
AJJrwuitt

^^^^11 1 III ^^^^^••111 IH ^^^^H
Cadmium
Chromium
L«Ad
 aad WMM. B>A-«00/4/7MaD,
r StuxUrt VUUxxfc for tit* ^^^^M a* WM« t*d WMtmucr.
































Lab Ho.
S*mpk Dcacripuoo
  112690A:  Method Blank for TCLP  Extract samples 124376,  124376DP, 125161,
           124378,  124380,   124382,  124382DP,   125162,  124384,  124386,  124517,
           124517DP, 124517MS,  124519, 124521,  124523, 124523DP and 124523MS.
           Res ults • are reported  in ug/L.
                       Summed Br
                                                                     Aquatec lo;
                                    -77-

-------
                                                                 aquatec
                          Spike Sample Recovery
                              Inorganic  Data


                              ETR No. 24003


Sample ID:  Soil-Spike 2, 1400-1412 (TM Ext)
Cd
Cr
Pb
Sample ID:
Parana tay
Cd
Cr
Pb
Spiked Staple
Result fuf/L)
53763.00
4147.90
145453.06
Slag-Spike 2, 1419
Spiked Saapl*
Result fug/Li
219.91
166.19
209.41
Saapl*
Results (uy/LV
55112.00
3161.84
146062.18
(TCLP Ext)
Sample
ReiulCi fuf/L)
169.64
73.88
155.24
Splk*
A4d««I fuf/ljl
NA
1000.0
N7\

Spike
Added fug/^
50.0
100.0
50.0
I ftlCOVMV
NA
98.6
NA

X Recovery
100.5
92.3
108.3
                                  78

-------

                                 »
                                 ETR No.  2'
Sample  ID:  Soil-Spike 3.  1245-1310  (TCLP Ext)
              Spiked Sample         Sample           spike
              R««ulc fug/O      R««ulti Cu«/L1
Cd
Cr
Pb
53518.
1665.
80592.
00
66
76
53857.
875.
72956.
00
01
19
NA
1000.0
NA
NA
79.1
NA
Sample  ID:  Slag-Spike  3,  1230-1237  (TCLP Ext)
              Spiked Sample          Sample              Spike
              tUault fu«/Ll
Cd
Cr
Pb
205.76
323.88
325.10
136.90
216.69
249.26
50.0
100.0
50.0
137.7
107.2
151.7
                                      -71,

-------
                  Duplicate Sample Recovery
                       Inorganic Data

                        ETR No. 24003
Sample ID:  Soil-Spike 2,  1400-1412  (TCLP Ext)


                                Duplic*t«
Sample  ID: Slag-Spike 2,  1419 (TCLP  Ext)
                                                              aquatet
Cd
Cr
Pb
55112.00
3161.84
146062.18
53971.00
1086.63
74810.21
n mam:
2.1
97.7
64.5
'uttitr
Cd
Cr
Pb
Sample
Raoule fu*/O
169.64
73.88
155.24
Duplicate
110.03
48.94
121.21
I R PD
42.6
40.6
24.6
                               -80-

-------
                                 R«cov*ry
                      Inorganic
                       ET& No, 26022
Sample ID: Soil-Spike  3,1245-1310  (TCLP Ext)
Sample  ID:  Slag-Spike  3,  1230-1237 (TCLP Ext)
               Sample           Duplicate
            Raiule  fu/LI      Ra«ilta ru/Ll
                             -il-
                                                            aquatec
•MM^|y
Cd
Cr
Pb
Sample
Hostile fuf/D
53857.00
875.01
72956.19
Duplicate
Rciule* fug/L)
54863.39
909.18
81766.37
1.9
3.8
11.4
^^^^MM^B
Cd
Cr
Pto
136.90
216.69
249.26
145.38
81.13
229.02
6.0
91.0
8.5

-------
                                                            aquatec
                          QC summary
                    ETR No. 24003 and  24022

                          Page 1 of 2
Gadaiua
Chromium
                  IPA
               Standarj
IVQCS





IVQCS





IVQCS


IVQCS





IVQCS















IVQCS




IVQCS
Found
f 11/11
483.63
485.34
491.92
474.83
495.72
495.60
497.21
493.07
499.36
503.59
513.71
484.18
491.18
477.14
482.30
495.00
488.83
488.96
480.54
478.31
500.78
511.8o
525.72
515.87
480.46
508.08
494.23
497.37
509.24
514.91
499.33
478.58
475.31
489.01
477.24
True
£.Uf/l)
500.0
500.0
500.0
500.0
500.0
500.0
500.0
500.0
500.0
500.0
500.0
500.0
500.0
500.0
500.0
500.0
500.0
500.0
500.0
500.0
500.0
500.0
500.0
500.0
500.0
500.0
500.0
500.0
500.0
500.0
500.0
500.0
500.0
500.0
500.0

X R*covnrv
96.7
97.1
98.4
95.0
99.1
99.1
99.4
98.6
99.9
100.7
102.7
96.8
98.2
95.4
96.5
99.2
97.8
97.8
96.1
93.7
100.2
102.4
105.1
103.2
96.1
101.6
98.8
99.5
101.6
103.0
99 . 9
95.7
95.1
97.8
95.4

-------
              QC Sunmry
      ETR No. 24003  and 24022

             Pag* 2 of  2


   EPA
IVQCS
IVQCS
378-5
378-5
 Found
 Cuf/Jl

 976.61
 929.70
1020.58
1019.33

 904.55
 981.35
1005.24

 975.77
 983.23
 907.34
1005.46

  35.00
  35.83
  36.65

  34.49
  35.00
  35.51
1000.0
1000.0
1000.0
1000.0

1000.0
1000.0
1000.0

1000.0
1000.0
1000.0
1000.0

  34.0
  34.0
  34.0

  34.0
  34.0
  34.0
                                                97.7
                                                93.0
                                               102.1
                                               101.9
                           90.
                                               100
                           97.6
                           98.3
                           90.7
                          100.5

                          102.9
                          105.4
                          107.8

                          101.4
                          102.9
                          104.4
378-5
34.08
34.08
32.34
32.58
                34.0
                34.0
                34.0
                34.0
               100.2
               100.2
                95.1
                95.8
                  -83-

-------

                  Method Detection Limit Study

                       ETR 24003 and 24022
                                                           HDL
                               	
6010       Cadmium       12-05-90       2.55       0.839       9.1
6010       Chromium      12-05-90       2.89       0.816      10.6
7421       Lead           11-29-90      0.40       0.912       1.3
6010       Lead         12-05-90      22.13       0.854    77.8
                         «&L - 3 x



HDL- Mtthod d«t«ccion  limit.

S|> - Standard  deviation of the  average noise level,

B   • Slop* of  cht calibration  line.
90000E07DEC90
                               84

-------
                                  o
                            aquatec
                       A JM*m6*r of tfM Jncftc^M tm^vnnmnM
                          M South Ptrfc Dnvt tekhttwr. Vtrmom «44*
                            m. lows-mo FAX
   Babcock * Wilcox  Company
   R&D Division,  Aft:  A/P
   1562  Beeson  Street
   Alliance,  OH  44601

   Attention i Jean  Czuczwa
                                               Date        :
                                               ETR  Number:
                                               Project No.:
                                               No. Samples:
                                               Arrived     :
                                               P.O. Number:*
                                               Page
 11/05/91
26202
 91000
 29
 09/13/91
                         tn
                                     tothedi for
                   Mr
       NcttMdt for lv»lu»tir< UHd WMtt, SW-MA, or ttwterd H*th«dB for th« UaairMtlon of U«t*r and UH
                         *U rMult* or* In >t/l unloss otlwrvlM netod.
Lab No./          Sampl* Description/
     Method NO.               Parani«t«r                       Result
143696
              Hopper 2001b/hr: (TCLPExt)
         6010                Cadmium,  Total
         6010                Chromium, Total
         6010                Lead, Total
143696MS F*«d Hopper  200lb/hr: [MS] (TCLPExt)
         6010                Cadmium, Total
         6010                Chromium, Total-
         6010                had,  Total

143696DP Feed Hopper  2001b/hr: [REP] (TCLPExt)
                             Cadmium, Total
          6010                Chromium,  Total
         6010                Lead, Total

143698   F*«4 Hopper  200lb/hr: (TCLPExt)
         6010                Cadmium, Total
         6010                Chromium,  Total
         6010                Lead, Total

143700   Feed Hopper  2 OOlb/hr: (TCLPExt)
         6010                Cadmium, Total
         6010                Chromium,  Total
         6010                Lead, Total

143702   Slag Tank 2001b/hr; (TCLPExt)
         6010                Cadmium, Total
         6010                Chromium,  Total
         7421                Lead, Total
                                                                  33
                                                                0.46
                                                                  78
                                                                  31
                                                                0.67
                                                                  66
                                                                  34
                                                                0.46
                                                                  70
                                                                  34
                                                                0.50
                                                                  88
                                                                  32
                                                                0.46
                                                                  65
                                                                0.11
                                                                0.02
                                                                0.19
< Cont. Next  Page >
                                  -85-

-------
                                   o
                             aquatec
                        M MwnlMT at ift* IneAeap* IrwfrwMMMiaf
                           99 Sou* P*rt Dnv». ColdtMMr, Vtmiom 9544*
                             TEL a02/«S5-12IX> f AX *»«S"S24i
                   ANA L-Y XIC-A L -«R E POR T
   Babcock 6 Wilcox Company
   R&D  Division, Att: A/P
    1562 Beeson Street
   Alliance,  OH 44601

   Attention : Jean Czuczwa
Dat*        :
ETR Nunb«r:
Project No. :
No.  Sanpl**:
Arrived     :
P.O. Number:
                                                              11/05/91
                                                              26202
                                                              91000
                                                               29
                                                              09/13/91
                                                 Pag*
    ?MI nttka* far
Lab No./
     M*thod  No.
                          In tccortM^ct nltti n*tiwdk far *n«ly«t» of ttotw w      ,   --
                      Solid UMt*t W-M*, or Stanctortf >»«th«J» far tlM iMBfnctlen of inter and UMf««ttr
                          All rttult* «r* in «t/l k*»t»»» «tlMtrMl«* r»t*d.
                  Saapl*  Description/
                               param«t*r                       R«»ult
143704
143706
143708
143710
143712
143714
         Slag Tank 2001b/hn (TCLPExt)
         6010                Cadmium,  Total
         6010                Chroaiua,  Total
         7421                Lead,  Total

         Slag Tank 200lb/hr:(TCLPlXt)
         6010                Cadmium, Total
         6010                Chromium, Total
         7421                L*ad,  Total

         F*«d Hopp*r lOOlb/hr:(TCLPExt)
         6010                Cadmium,  Total
         6010                Chroodua,  Total
         6010                L«ad,  Total

         slag Tank lOOlb/hr:(TCLPExt)
         6010                Cadmium,  Total
         6010                Chromium,  Total
         7421                Lead,  Total

         ?««d Boppcr 3001b/hr:(TCLPExt)
         6010                Cadmium,  Total
         6010                Chromium,  Total
         6010                Laad,  Total

         Slag Tank 300lb/hr:(TCLPExt)
         6010                Cadmium,  Total
         6010                Chromium, Total
         7421                Lead,  Total
                                                                  0.04
                                                                  0.02
                                                                  0.14
                                                                  0.07
                                                                  0.02
                                                                  0.20
                                                                    36
                                                                  0.42
                                                                    72
                                                                  0.03
                                                                <0.01
                                                                  0.06
                                                                    40
                                                                 0.42
                                                                    78
                                                                  0.07
                                                                 <0.01
                                                                  0.19
< Cont. Naxt Pag* >
                                    -86-

-------
                                   o
                             aquatec
                        M MMtter ot tfw /rtcrtcpp« £mrtroom«m*/ Oot/p
                           0 South P»rt Drtv*. Cokhnm Vrrmont 9544*
                             TIL,
                  ANALYTICAL A.EPO'RT-
   Babcock  6 Wilcox Company
   R&D  Division, Att:  A/P
   1562  Beeson Street
   Alliance,  OH 44601
   Attention
                Jean Czuczwa
                                                 Data        :  11/03/91
                                                 ETR Number  :  26202
                                                 Project No. :  91000
                                                 No.  Saapl««:  29
                                                 Arrived     :  09/13/91
                                                 P.O. Nuab«r:  •
                                                 Page
     ttmterd miy*** »tr« pwforMd In •ccofd«nc« with Ntthodt for AiwtytU »f Uattr and UMtM, »A-600/4/79-020,
    TMt H*thod» for IvalMtfn* tellrf UMta, W-M4, «r ttandtrd Hvtitodi for tfc* IwHiiraitien of Uitsr ind
                          AIL rwults ar« in n/l ml«u «ttMntlt« not«d.
Lab No./          Saapl*  Description/
     Mathod  No.               Parameter                        R«»ult
143716   Food  Hopper Borax:(TCLPExt)
         6010                 Cadmium, Total
         6010                 Chromium, Total
         6010                 Lead, Total

143718   Slag  Tank Borax:(TCLPExt)
         6010                 Cadmium, Total
         6010                 Chromium, Total
         7421                 Lead, Total

143720   Slag  Tank Borax:(TCLPExt)
         6010                 Cadmium, Total
         6010                 Chromium,  Total
         7421                 Lead, Total
                                                                    30
                                                                  0.13
                                                                    54
                                                                  0.27
                                                                  0.02
                                                                  0.43
                                                                  0.27
                                                                  0.01
                                                                  0.35
   < .Last  Page >
Submitted  By  :
                                     -87-
                                                                Aquatec Inc.

-------
                         aquatec
                    A      erf tl*#
                       •W ;>
                         TEi

Babcock & Wilcox Co.
Date: 02  October 1991
Project No: 91000
ETRNo:  28202
Sample(s) Received on 13 September
    I at 1
                                                                   1991
                    «»      «nt>      for     orf
         fc*                 or          few jj»»       irf    »*»
                       AH     *»» <•

Cadaiam

















Lab No. S*npie Description
Blank. TCLP extraction blank for samples labalad 143696, 143696DP, 143696MS,
     143698,  143700,  143702, 143704,  143706,  143708,  143710,  143712.
     143716,  143718 , and 143720.
                      143714,

                                  /!.


-------
                                 aquatec
                               S§ South fmk On**. CotehMMr, V««M>m 0544*
                                  TIL 801- AM-', 203 FAX KKMMM14I
        Babcock and Wile ox  Company
                                           Date: 05 November 1991
                                           Project No: 91000
                                           ETRNo:  28477
                                           SMpfa(i) RMM OK 13 S«pttmb«r  1991
                                           1** I el I
                                                          W.
       Mtytu wm p«rfocn»««J m acxxxduuKS wtti Mttliodt tat AaiJytM of	.	  	
ftm MHto* tat Bvmh«oiij SaM WMM, SW-MA. at Su«tanJ ItatexH te tta EnMnanrisa of w»ur u*d Wi
    Ptninctcf
 C«dmlu»
 Chromium
 Lead
              :Q.Ql

              =0.01
              :0.§§5
  UbNo.
                                 Staple Descriprioa
PBLK Prep blank for samples 143702MS, 143702DP, 143716MS, 143716DP, 143718MS
      and 143718DP.
                          S«tniutt«l By:
                                        -90-

-------
                                  o
                            aquatec
                                 ineliecp* tmttmnamtut Qnup
                          » Sen* Part Onm Cekhnmr. V««t*»«t 0944*
                             TEL KB/ftM-un
                  ANAJ-YTJCAL-stflEFOAT
   Babcock 6 Wilcox Company
   R&D  Division,  Att: A/p
   1562  Beeson Street
   Alliance,  OH 44601

   Attention  :  J«an Czuczwa
                                                Data
                                                ETR Number
                                                Project  No.
                                                No. Samples
                                                Arrived
                                                P.O.  Number
                                                Paga
                                        11/05/91
                                        28477
                                        91000
                                          6
                                        09/13/91
             tyMs wtrt
             for
Lab No./
     H*thod NO.
    In *cc0rdtnet »ftft Hortiod* for Araiytis of U*t*r and WMtn, IP*-600/4/79-020,
Solid UMt*. M-A44P of (tandtrtt »««thod» for th» I»«iin«tf«n of y«t«r tnd tf»«t«w«t«r.
          •*•• tn ••/! i»lM« othorvtM no tod.

                                         R«»ult
                  Sanpl« Description/
                               Paraa*t*r
143702MS Slag  Tank 2001b/hr:[MS](TCLPExt)
         6010                 Cadmium,  Total
         6010                 Chromium,  Total
         7421                 L«adr  Total

143702DP Slag Tank 2001b/hr:[REP](TCLPExt)
         6010                Cadaiua,  Total
         6010                 Chromium,  Total
         7421                 L«ad,  Total

143716MS F««d  Hopp«r Borax:[MS](TCLPExt)
         6010                 Cadmium,  Total
         6010                 Chromium,  Total
         6010                 l*ad,  Total

143716DP Feed  Hopper Borax:[RZP](TCLPExt)
         6010                 Cadmium,  Total
         6010                 Chromium,  Total
         6010                 L«ad,  Total

143718MS Slag Tank  Borax: [MS] (TCLPExt)
         6010                 Cadmium, Total
         6010                 Chromium,  Total
         7421                 L«ad,  Total

143718DP Slag  Tank Borax:[REP](TCLPExt)
         6010                 Cadmium,  Total
         6010                 Chromium,  Total
         7421                 Lead,  Total
                                                                 0.13
                                                                 0.23
                                                                 0.44
                                                                 0.08
                                                                 0.03
                                                                 0.24
                                                                   30
                                                                 0.33
                                                                   47
                                                                   31
                                                                 0.14
                                                                   51
                                                                 0.36
                                                                 0.25
                                                                 0.55
                                                                 0.25
                                                                 0.02
                                                                 0.41
   < Last Page >
                      Submitted  By
                                         Aquatec  In s

-------
                               QC
                               EYt
                                                                  aquatec
Cadmium       IVQCS


Chromium
Lead
IVQCS



 490.68
 491.74
 490.89
 487.69

 494.15
 500.04
 505.49
 504.66

 483.05
 493.38
 482.88
 489.70

 475.05
 408.73
 478.30

  15.74
  15.56
  16.18

 967.96
1030.30
1009.99
 984.88
 500.0
 500.0
 500.0
 500.0

 500.0
 500.0
 500.0
 500.0

 500.0
 500.0
 500.0
 500.0

 500.0
 500.0
 500.0

  15.0
  15.0
  15.0

1000.0
1000.0
1000.0
1000.0
                                                  98,
                                                  96.
                                                  98.
 97.5

 90.0
100.0
101.1
100.9

 96.6
 96.5
 96.6
 97. t

 95.0
 97.7
 9s.7

104.9
103.7
107.9

 96.8
103.0
100.6
 98.5
                                     -91-

-------
                               QC  Summary
                               ETR 26202
            EFA ...... S C
                            Pound (UC/L1
I R«eov
-------
 143702
 143702
 143702

 143716
 143716
 143716

 143718
 143718
 143718

 143696
 143696
143696
Cmdaims
Chtoaiua
Lead

Cadalua
threat am
Lead

Ca datum
ChroaiusR
Lead

C-a Anitas
Lend
                                       QC Summary
                                  ET1 NO. 28477/28202
                                   Results  in  ug/L
                                       Duplicate
  109.4740    81.8600
   15.0750    28.7660
  189.3980   237.1300

29929.4000 31408.4390
  132.3950   136.4310
54027.0160 51023.5780
  267.9530
   18.6640
  428.5714

32656.9372
  459.5020
77898.9380
  253.1760
   24.1630
  413.7400

33795.2173
  464.3000
70342.8830
              ail

             28.9
             62.5
             22.4

              4.8
              3.0
 5.7
25.7
 3.5

 3.4
 1.0
10.2
                                                                              aquatec
                                               Matrix
                                               Spike
                                           Sptkn
         128.9970   49.19   39.7
         234.2180  196.77  111.4
         435.4300  492.42   50.0
       30366.8320
         331.8620
       47450.1640
             49.73    NC
            198.93  100.3
            497.31    NC
  358.9100   49.47    NC
  253.6400  197.86  118.8
  551.3000  494.27   24.8
31437.8611
  665.8240
65792.0230
 49.98    NC
199.90  103.2
499.75    NC
 NC - Sample  result  is  greater than 4  times the splk«  added therefore % recovery is
      non-calculabi*.
                                            -93-

-------
 ACG-92-4191-07
 October 23, 1991
                              ANALYSTS BY ICP-AES
                                    DRY BASIS
Sample No. and Description..
M-48652
Soil, 100 Ib/hr Test, Composite
of 1025, 1115, 1245 hrs, 9/10/91

M-48653
Soil, 200 Ib/hr Test, Composite
of 1225, 1615, 1700, 1750 hrs,
M-486S4
Soil, 300 Ib/hr Test, Composite
of 1435, 1700, 1745 hrs, 9/10/91

M-48655
Soil with Borax, 200 Ib/hr Test,
Composite of 1030, 1250, 1350  hrs,
9/11/91
Cadmium,
     Cd_
  1,232
  1223
  1,281
  1,248
  1,255
                                        1,292
                                        1,366
                                        1,268
                                         1,251
Chromium,
   1,541
  1513
   1,544
   1,540
  1566
                     1,567
                     1,622
                     1,577
                      1553
                                                                            Lead,
                                                                               ft
                                                                            7,247
                                                                            7,150
                                                                            7,635
                                                                            7,655
                                                                            7836
                   7,509
                   7,894
                   8,208*
                   7,838
Acid Reagent	Blank
(Aqua Regia -HF- Boric Acid)
  <0.5
  <0.5
                                                                            <0.5
Note:  Replicate values were determined from  separate acid  digestions.

•     This value is probably too high - Pb calibration was difficult to maintain. ICP was
      recalibrated 3 times during this run because 5ppm Pb standards were too low or too high.
      See calibration data shown for 9/23/91.  The lead level measured in the Cr Spiked
      Sample was also  lower than 8208ppm.  See Spiked Sample Recovery data sheet in this
      report.
                                       -94-

-------
 ACG-92-4191-07
 October 23, 1991
                               ANALYSIS RY  1CP-ARS

Sample No . and PcsoiptJQQ

M-48656
Slag, 100 Ib/hr Test, Composite
of 1045, 1240, 1325 hrs,
9/10/91
M-48657
Slag, 200 Ib/hr Test, Composite
of 1245, 1615, 1730, 1820 hrs,
9/9/91
M-48658
Slag. 300 Ib/hr Test, Composite
of 1445, 1700, 1800 hrs, 9/10/91
M-48659
Slag with Borax, 200 Ib/hr Test,
Composite of 1215, 1300, 1408 hrs,
DRY RASIS
Cadmium,
Cd

116
111


187
186
197

178
180

279
289

Chromium,
Cr

1,489
1,421


1,500
1,484
1,481

1,440
1,403

1,219
1,197

Lead,
	 Pb

2,097
2,053


3,550
3,570
3,656

3,551
3,554

3,813
3,856
 9/11/91
        acnt Bla
<0.2
 (Aqua Regia -HF- Boric Acid)
<0.2
Note: Replicate values were determined from separate acid digestions.
<0.2
                                       -95-

-------
ACG-92-4191-07
October 23,  1991
                                         1Y.ICP.AES
       No.
M-48694
Filter & Combined Participates,
200 Ib/hr Test, 1610-1646 hrs,
9/9/91, 0.92  g Total particulates

M-48695
Filter & Combined Particulates,
2001b/hr Test, 1744-1820 hrs,
9/9/91, 0.69 g Total Particulates

0.1N HNO, Rinse for M-48695,
  0.08g solids

IUURRQR
Filter & Combined Particulates
with Borax, 200 Ib/hr Test,
1238-1314  hrs, 9/11/91, 1.23g
Total Particulates

0.1N HNO, Rinse for M-48696,
  O.llg solids

Acid Reagent Blank
  (Aqua Regia-HF-Boric Acid)

M-48697
Filter Blank

0. IN

Acetone
Cadmium,
     Cd..
  17,720
 25,625
  6,159
  13,103
Chromium,
«oom Cr
  7,874
  9,580
  4,259
  5,258

98,736
131.669
28,694
70,939

<0.5
<37
<0.2
<0.1
Sample Lost
<0.5
43
<0.2
<0.3

<0.5
< 37
<0.2
<0.1
                                        -96-

-------
 ACG-92-4191-07
 October 23, 1991
      ;

                              CONSTITUENTS BY ICP-AES*
                                    DRY BASIS
  M-486S3

Soil  Composite,
 200 Ih/hr Test,
1225, 1615, 1700,
1750 hrs, 9/10/91
   M-48655

Soil Composite
 with Borax,
   200 Ib/hr
  Test,  1030,
1250, 1350 hrs,
    9/11/91
                                                         M-48657
  M-48659
                                                     Slag Composite,       Slag Composite,
                                                     200 Ib/hr Test,        with Borax,
                                                     1245,  1615, 1730  200 Ib/hr
                                                     1820 hrs,
 Test, 1215,
1300,  1408 hrs,
    9/11/91
SiO,,*
AIA.%
FeA.o/0
HO,,*
CaO,%
MgO,o/0
80,,%
PaOs,o/o
NaA%
KjO,%
O 1*1 n/
47.35
46.80
9.07
8.83
2.28
2.22
0.35
0.34
15.26
14.99
4.45
4.33
0.67
0.72
0.39
0.31
0.59
1.12
47.27
44.93
9.15
8.96
2.23
2.18
0.41
0.32
13.20
13.20
3.99
3.96
0.69
0.61
0.34
0.33
1.93
1.93
1.13
1.13
ORQ
60.87
59.26
13.25
12.88
2.83
2.84
0.67
0.65
16.87
16.81
4.74
4.64
0.30
0.36
0.42
0.40
0.74
1.30
59.54
10.29
2.77
0.54
17.51
4.77
0.27
0.41
1.95
1.89
1.20
1.18
1 81
Note:  Replicate values were determined from separate acid digestions.

      Elements are reported as oxides for convenience and arc not necessarily present in that form.
      >T " ^ and K.20 were determined by flame photometry.
                                     -97-

-------
ACG-92-4191-07
October 23, 1991
                                       M-48653
Description;                          Soil Composite,
                                     200 Ib/hr Test,
                                    1225, 1615,  1700,
                                    1750 hrs, 9/10/91

Carbonate, % CO2                        15.44
                                       -98-

-------
ACG-92-4191-07
October 23,1991
                       -                                         % H7Q
                                                    (Before Compositing)


              Soil. 100 1b/hf Test.
                   9/10/91

                                                            25.02
                                                            26.32
                                                            24.32
                   M-48653
                      Jb/hr.TcsL
                                                            24.94

                                                            25.42

                                                            25.73

                   1750 H«                                 25.12



              Soil. 30Q Ib/ht
                   9/10/91

                   I43S Hrs                                 26.35

                   1700 H«                                 26.19

                   1745 Hrs                                 27.43



              with        200     Test.
                   9/11/91

                   1030 Hrs                                 28.89

                                                            28.44

                   13SO Hrs                                 29.30
                                     -99-

-------
ACG-92-4191-07
October 23, 1991
                                     AS
M-48656
Slag Composite, 100 Ib/hr Test,
 1045, 1240, 1325hrs,  9/10/91
Slag Composite, 200 Ib/hr Test,              85.47
1245,  1615, 1730, 1820, 9/9/91

M-48658
Slag Composite, 300 Ib/hr Test,             82.40
1445, 1700,  1800 hrs, 9/10/91


Slag Composite with Borax,                  81.45
200 Ib/hr Test, 1215,  1300, 1408 hrs,
9/11/91
   Values reported are average of 2 determinations  within 10% of each other.


-------
 ACG-92-4191-07
 October 23,1991
                          SOIL BULK DENSITY*. POTINDS/FT3
                                       DRY BASIS
Soil, 100 Ib/hr Test,                        76.57
Partial Composite


Soil, 200 Ib/hr Test,                        81.90
Partial  Composite

M-48654
Soil, 300 Ib/hr Test,                        81.53
Partial Composite

M-48655
Soil with Borax,                            75.76
200 Ib/hr Test,
Partial Composite
   Values reported arc average of 2 determinations within 10% of each other. Samples were dried at
   ISO'F, and crushed with a jaw crusher (approximately 1/4").  Portions from 2 different hour tests
   were used to fill the box for each sample.
                                       -101-

-------
 ACG-92-4191-07
 October 23,1991
                                                %
                                         BYICP
M-4K6S7
Soil Composite, lOOlb/hr
Test, 1025,  1115, 1245 hrs,
9/10/91
                                         Cd
107.34 %R

 (1.565)
                                          Pit
(7.417)
Soil Composite, 300 Ib/hr
Test, 1435, 1700, 1745 hrs,
9/9/91

M-4865S
Soil Composite with Borax,
200 Ib/hr Test, 1030, 1250,
 1350 hrs, 9/1 1/91
 (1.315)
 (1,233)
 (1,613)
103.43 %R
96.86 %1
 (7,733)
M-48656
Slag Composite, 100 Ib/hr
Test, 1045,1240,1325 hrs,
9/10/91

M-48658
Slag Composite, 300 Ib/hr
Test, 1445,1700,1800 hrs,
9/10/91
92.03 %R
  (167)

96.91 %R'

 (3,425)
M-48659
Slag Composite with Borax,
200 Ib/hr  Test, 1215,  1300,
1408 hrs, 9/11/91
 099)
 (1,242)
 95.60 %R
Note:   Values shown in parentheses are ppm of the 2 elements not spiked in each sample.
                                       -102-

-------
ACG-92-4191-07
October 23, 1991
                          CALIBRATION VERIFICATION
Cadmium.
Initial
4.86
Continyjog
5.09
4.90
5.28

4.93
4.98
4.85

5.09
5.06

%R
97.2
%R
101.8
98.0
105.6

98.6
99.6
97.0

101.8
101.2
Chromium.... Sppm
Initial
4.97
%R
99.4
Continuing %B
5.13
5.00
5.19

4.90
4.81
4.84

5.13
5.04
102.6
100.0
103.8
(Recalibrated)
98.0
96.2
96.8
(Recalibrated)
102.6
100.8
Lead. Sppm
Initial
5.07
Continuing
5.11
5.16
5.41

5.03
4.73
4.56

5.28
5.54
%R
101.4
%R
102.2
103.2
108.2

100.6
94.6
91.2

105.6
110.8
                               CHECK STANDARD
Cadmium^ Q.S.ppm
Measure^     j%%
 0.57      114.0
 0.52      104.0
Chromium. Q.Spprn
0.56
0.51
          112.0
          102.0
Measured      %R
  0.42       84.0
  0.48       96.0
                                   -103-

-------
ACG-92-4191-07
October 23,  1991
                          CALIBRATION VERIFICATION
9/26/91
Ci4fflJMffli,
Initial
4.98
Continuing
4.83
4.87

%R
99.6
%R
96.6
97.4
, Chromium
Initial
4.95
Continuing
4.85
4.97
t 	 5pp.ro
%R
99.0
%R
97.0
99.4
LeMtJppiD
Initial
4.95
Continuing
5.25
5.21
x&
99.0
%R
105.0
104.2
CHECK STANDARDS
9/26/91
Cadmium.
Measured
JQrom
%R
Chromium.
Measured
j&Q&ni
%R
Lead. 50j
Measured
Wfl
J6R
49.96       99.9
                    49.44        98.9
                            50.69      101.4
 Cadmium. Q.Sppm
                    Chromium. Q.Sppm'
Measured
%R
Measured
%R
                                    -104-
  *  No  peak found.
  ** These values were not used in reporting results.
                              Lead* Q.2ppm
Measured    %R
0.53
0.46
Cadmium.
Measured

0.21
Cadmium.

19.59
19.50
106.0
92.0
JLZDom
%R

105.0
JStem
JR
98.0
97.5
0.63
0.32
Chromium.
Mssjirsd

0.20
Chromium
Measured
19.99
20.16
126.0
64.0

%R

100.0

11
100.0
100.8
0.53
0.52
LeaiL



Lad*.
Mea^ifed
19.60
19.65
106.0
104.0
Q.2ppm

*

2Qppm
1 M
98.0
98.3

-------
 ACG-92-4191-07
 October 23, 1991
                            CALIBRATION  VERIFICATION
                                        10/3/91
  Cadmium. Sppm
Initial

  4.99
 %R

 99.8
 Chromium. Sopm

Initial         %R

  5.04         100.8
                                                      Lead. Sppm
               Initial

                 5.06
            101.2
Continuing

  4.96
  4.96
  4.96
 99.2
 99.2
 99.2
C_ontinyjng

  4.99
  4.82
  4.92
99.8
96.4
98.4
Continuing

  4.98
  5.00
  5.09
            99.6
            100.0
            101.8
  Cadmium. IQpum
Measured
 %R
                                 CHECK STANDARDS
                                       10/3/91
                       Chromium. IQppm
Measured
                               Lead.  IQppm
              Measurai
             %g
10.25
9.85
9.46
102.5
98.5
94.6
10.00
9.92
9.64
100.0
99.2
96.4
10.19
9.43
9.67
101.9
94.3
96.7
 Cadmium, loom
Measured.

 0.98
 1.02
 %R

 98.0
102.0
                       ChromiumJppm
Measured

  0.94
  0.95
 %R

94.0
95.0
                                Lead, loom
Measure^

  0.95
  0.96
            %R

           95.0
           96.0
                                     -105-

-------
 ACG-92-4191-07
 October 23, 1991
                            CALIBRATION VERIFICATION
                                        10/4/91
 Cadmium. Sppni

Initial        %R

 4.96        99.2
                                   Chromium 5pprn
                               Lead. Sopm
Iniiial
5.09
%R
101.8
Initial
5.21
%R
104.2
Continuing

  4."77        95.4
Continuing     %R

  5.02        100.4
                                                              Continuing

                                                                4.84      96.8
                                CHECK STANDARDS
                                       10/4/91
 Cadmium. .2Qpgnj

Measured     %R

 19.81        99.1
 Chromium.

Measured      %R

 19.71         98.6
                                                               Lead. 20ppm

                                                             Measured.

                                                               19.23      96.2
        .. O.Sm
Measured     %R

 0.50       100.0
Measured      %R

  0.52        104.0
                                                               Lead. O.Sppm*

                                                             Measured     %R

                                                               0.70      140.0
  Lead value was outside ± 10% range but samples contained much higher lead levels. Calibration was
  within ± 10% at the higher levels.
                                    -106-

-------
ACG-92-4191-07
October 23, 1991
                                  CALIBRATION VERIFICATION


                      10/8/91                              10/13/91

                   Boron. 5oom                                5.
Initial
5.09
Continuing
5.13
5.07
5.12
5.17
%R
101.8
%R
102.6
101.4
102.4
103.4
Initial
5.04
Continuing
5.15
%R
100.8
%R
103.0
                                       STANDARDS


                      10/8/91                              10/13/91

                   Bo.ro.tL. Ippm                     Chromium Q.5ppm*

               Measured         %R                                 %R

                 1.00           100.0                0.42             84.0
                 0.97            97.0
                 0.98            98.0

                                                    CJirojpiyini
                                                                    %R

                                                   50.16            100.3
                                                   50.39            100.8
   Approaching detection limit in this matrix. These values are for indication of acid reagent
   blank levels.
                                       -107-

-------
ACG-92-4191-07
October 23, 1991
                         CALIBRATION VERIFICATION
                                    10/21/91
 Cadmium. 5opm
Initial

 4.61
 %R

 92.2
Chromium. 5ppm

Initial         %R

  4.93         98.6
                                                     Lead. SPPITI
                 4.79
%R

95.8
Continuing

 4.63        92.6
                      Continuing     %"R,

                        5.03        100.6
                             Continuing

                              4.71      94.2
                              CHECK
 Cadmium. Q.

Measured     %R

 0.46        92.0
                      ChromiumQ-

                      Measured      %R

                        0.50        100.0
                            Measured
                 0.64
                                        128.0
Cadmium. Q.2ppm
 %R

100.0
 90.0
 80.0
 0.20
 0.18
 0.16
 Chromium.,	Q,2pgiB

Measured      %R
110.0
100.0
100.0
                                                    Lead. 0.2ppm
                                                              Measured     %R
  0.20
  No peak found. The above low level values (0.2ppm) were used only to report < values for
  Cadmium and Chromium in the filter blank and acid reagent blanks.
                                     -108-

-------
ACG-92-4191-07
October 23,  1991
                          CALIBRATION VERIFICATION
                                      10/22/91
  Cadmium. Sppm
Initial

 4.86
 %R

97.2
5.08
Continuing
4.78
5.17
101.6
%R
95.6
103.4
Initial

  5.20
 %R

104.0
                                      (Recalibrated)

                                      5.26        105.2
                                    Continuin
                                                   %R
                                                                     Lead. Sm
                                                                  Initial
                                                                    4.77
95.4
                                                      4.94       98.8

                                                     Continuing   JIB.
4.85
5.13
97.0
102.6
4.81
4.80
96.2
96.0
                               CHECK STANDARDS
                                       10/22/91
 Cadmium. O.Sppm

Measured      %R

 0.48         96.0
                                              t Q.Sm
 0.49
 0.48
 0.47
             98.0
             96.0
             94.0
                      Measured       %R

                        0.54         108.0

                         (Recalibrated)

                        0.53         106.0
                        0.51         102.0
                        0.52         104.0
                                                      Lead. Q.5m*
                                                                 Measured
                                0.49
                                                                              98.0
                                0.80      160.0
                                0.65      130.0
                                0.50      100.0
  At low lead levels (0.5ppm) the lead intensities measured are close to background levels in
  the matrix.
                                        -109-

-------
ACG-92-4191-07
October 23,1991
                       CALIBRATION PROCEDURE FOR ICP
This instrument is calibrated using acid/matrix reagent blank (same matrix used in standards
preparation) as standard 1 and a matrix-matched standard (in this case 50ppm of each element)
as standard 2.   An analytical curve is drawn by the instrument using the data obtained from
standards 1 and 2.

Instrument calibration is verified using a  separate matrix-matched standard (or standards) in the
working range of the samples.  The calibntion standard(s) are checked throughout the analysis
and recalibration (using standards 1  and 2) is performed when the calibration verification
standard falls outside (or sometimes near) the 90 to 110% range.

An independent check standard can also be used for calibration verification if it is in the working
range of the samples.  An acid/matrix reagent blank which has been digested along with the
samples is also run as an unknown.
                                         -110-

-------
                                        Form VI
                            QC Report No.    ACG-92-4191-07
                                      DUPLICATES
Lab. Name
ARC - Analytical Chemistry
Date:    September 21 1991  / October 3. 1991
  Project  No.  4191-07
Sample No.     M-48652
   Units:      oom	
Compound
I.
2,
3, Lead




Sampte(S)
1,232
1,541
7,24?
(D)
1,223
1,513
7,150
;
RDP I
0.733 I
1 , 83-4 !
1.347 I
      N    -Out of Control
      RDP m [{S-D}]/[(S-i-D)/2)] x 100
      NC   -  Non calculable RDP due to value(s)less than CRDL
                                          -111-

-------
                                   *     Form VI
                             QC Report No.    ACG-92-4I91-Q7
                                       DUPLICATES
Lab. Name     ARC - Analytical Chemistry
Date:   September 23. IQQ1 /October 3. 1991
  Project No.  4191-07
Sample No.      M-48653
   Units:     t>pm	
Compound
1 ,
2.
3.








(D)
1,248
1,540
7,655
*
2.609
0,259
0,262
      •  First 2 replicate samples were used to calculate RDP values.

      N    - out of Control
      RDP= [{S-D}]/[(S+D)/2)]xlOO
      NC  -  Non calculable RDP due to value(s) less than CRDL
                                           -112-

-------
                                         Form VI
                            QC Report No.   AnO-92-4191-07
                                      DUPLICATES
Lab. Name
ARC - Analytical Chemistry
Date:    October 3. 1991
  Project  No.  4191-07
Sample No.     M-48655
   Units:     ppm	
Compound
1. Cadmium
2. Chromium
3. Lead
Control Limit



Sample(S)
1,268
1,577

Duplicate (D)
1,251
1,553

RDP
1.349
1.534

      N    - Out of Control
      RDP= [(S-D}]/[(S+D)/2)] x 100
      NC   -  Non calculable RDP due to value(s) less than CRDL
                                          -113-

-------
                                         Form VI
                             QC Report No.    ACG-92-4191-07
                                      DUPLICATES
Lab. Name     ARC - Analytical Chemistry
Date:  September 26. 1991 / October 3. 1991
  Project  No. 4191-07
Sample No.     M-48657
   Units:      ppm	
1
Compound
1. Cadmium
2, Chromium
3.
Control Limit



Sample(S)
187
1,500
3,550
Duplicate (D)
186
M84
3,570
|
.1
1
0,535 1
LOT4 1
	 i
0.562 1
      •  First 2 replicates were used to calculate RDP values.

      N    - out of Control
      RDP= [{S-DM(S+D)/2)]xlOO
      NC   -  Non calculable RDP due to value(s) less than CRDL
                                           -114-

-------
                                         Form VI
                             QC Report No.    ACG-92-4191-07
                                       DUPLICATES
Lab. Name     ARC -'Aftlvticai Chemistry	

Date:    September  23. 1991 / October 3. 1991
  Project No. 4191-07
Sample No.      M-48654
   Units:      ppm	
Compound
I.
2, Chromium
3,




Sampl«(S)
1,292
1,567
7,509
(D)
1,366
1,622
7,894
RDP !
!
3.
-------
                                           Form VI
                               QC Report No.    ACG-Q7-41Q1-07
                                         DUPLICATES
    Lab Name
ARC 'Analytical Chemistry
Date: September  26  1991 / October 3. 1991
  Project  No.  4191-07
Sample No.     M-48656
   Units:
                                               JDPCL
Compound
1. Cadmium
2, Chromium
3,
Control Limit



Sample(S)
116
1,489
2,09?
Duplicate (D)
111
1,421
RDP \
4.386 j
4«6?i I
| 2,120 |
         N    - out of Control
         RDP = [|S-D}]/[(S+D)/2)] x 100
         NC   -  Non calculable RDP due tovalue(s) less than CRDL
                                             -116-

-------
                                        Form V
                            QC Report No.    ACG-92-4191-07
                                      DUPLICATES
Lab. Name   ARC - Analytical Chemistry

Date:   September 26. 1991 /October 3. 1991
  Project No. 4191-07
Sample No.     M-48658
   Units:
Compound
1. Cadmium
2. Chromium
3. Lead
Control Limit



Sample(s)
178
1,440
3,551
Duplicate (D)
180
1,403
3,554
(
i
RDP I
1.117 1
2.607 [
0.084 ]
     N    -Out of Control
     RDP=  [{S-D}]/[(S+D)/2)J x 100
     NC   -  Non calculable RDP due to value(s) less than CRDL
                                        -117-

-------
                                        Form V
                            QC Report No.     ACG-92-4191-07
                                     DUPLICATES
Lab. Name   ARC • Analytical Chemistry
Date: September 26. 1991 /Octobers. 1991
  Project No.  4191-07
Sample No.    M-48659
   U&S:  _
pom
Compound
1.
2,
3. Lead




Sareple(s)
279
1,219
S :
(D) |
289 3.52! |
\
1 | LI:I j
      N    - Out of Control
      RDP-  [{S-D}3/[(S+D)/2)JxlOO
      NC   -  Non calculable RDP due to value(s) less than  CRDL
                                        -118-

-------
                                        Form IV
                            QC Report No._  ArG-Q7-41Q1-07
                               SPIKE SAMPLE RECOVERY
                                         SOILS
Lab. Name    ARC - Analytical Cherrjistry

Date:     October 3. 1991	
Project No.  4191-07
Units:     nnm
Mo.
i
!
I
Compound
1 .
2, Chromium
3. Lead
Control Limit
% R



(SR)
6,57?
11,855
12,476
Sample
1,223
1,513
7,894
Spike

-------
                                        Form IV
                            QC Report No.   ACG-92-4191-07
                               SPIKE SAMPLE RECOVERY
                                        SLAGS
Lab. Name    ARC  - Analytical  Chemistry
Date:     September 26 1991
Project No.  4191-07

 Units:    ppm	
Sample No,
; M-48656
M'4St-58
M-4S659 f
Ccnrpound
L Cadmium
2, Chromium
3, Lead
Control Limit 1 Spiked Sample
% R fSR)
9,263
11,063
| '
Sample
(SR)
116
1,440
3,813
Spike
(SA)
9,945
9,930
9,995
.j
% R 1
92,01 1
96,->l |
95 60 1
%R= [(SSR-SR/SA)] x 100
  N - out of control
NR- Not Required
                                          -120-

-------
                                            Form III
                                QC  Report No  Af.G-92-4191-07
                                            BLANKS
Lab.  Name    ARC-Analytical  Chemistry
Date:     September 23.  1991	
                          Project No.  4191-07

                           Units:     ppm
   . Cadmium
                                    Aqua-Regia-HF-Boric Acid
                            initial Calibration
                 Continuing Calibration
<0.5
<0.5
                                                                           Preparation  Blank
I
} Compound
Blank Value
Blank Value
*
Blank Value j
2. Chromium
3. Lead
<0.5
<0.5
<0.5
<0.5


                                              -121-

-------
                                             Form III
                                QC Report No.  Af!ri-92-4l9l-n7
                                            BLANKS
Lab. Name    ARC -Analytical Chemistry
Date:     September  26. 1991	
       Project No.  4191-07
       Units:      ppm	
                                    Aqua-Regia-HF-Boric Acid
                            Initial Calibration
Continuing Calibration
Preparation Blank
Compound
1. Cadmium
2. Chromium
3. Lead
Blank Value
<0.2
<0.2
<0.2
Blank Value
<0.2
<0.2
<0.2
Blank Value



                                              -122-

-------
                                              Form III
                                 QC Report No.  Ar.G-Q7.-4lQl-n7
                                             BLANKS
Lab. Name    ARC - Analytical Chemistry

Date:     October 4  1991	
                                                        Project  No.  4191-07

                                                         Units:     ppm	
Go;
;1 i.
                                     Aqua-Regia-HF-Boric  Acid
                             Initial  Calibration
                                                  Continuing  Calibration
Preparation Blank
                               Blank Value
                                  <0.5
2. Chromium
3, r.ead
<0.5
<0.5
<0.5
<0.5
I

                                               -123-

-------
                                            Form III
                                QC Report  No  Ar.rT-92-4191-n7
                                            BLANKS
Lab. Name  ARC  -   Analytical Chemistry_
Date:     O.tnher 4.1991	
Project  No. 4191-07
units:
              ppm
                                    Aqua-Regia-HF-Boric Acid
                            Initial Calibration


Compound
L
2,
3, Lead

<0,5
<0.5
<0,5

<0.S

-------
                                         Form III
                              QC Report No.   ACG-97-4191-07
                                         BLANKS
Lab. Name   ARC-Analytical  Chemistry
Date:  October  21.  1991	
   Project No.      4191-07
   Units:          oom	
                                  0. IN HNO, Rinse Blank
                          Initial Calibration
Continuing Calibration

Compound
1. Cadmium
2. Chromium
3. Lead
Blank Value
<0.2
<0.2
<0.2
Blank Value
<0.2
<0.2
<0.2
Blank Value \
\
	 - 	 — — -<]

                                       -125-

-------
                                          Form III
                              QC Report  No.   Ar.fi-92-4191-07
                                         BLANKS
Lab.  Name    ARC - Analytical Chemistry
Date:   Qp.tnbpr 21. 1991
Project No.  4191-07

  units:      rmm
                                     Acetone Rinse Blank



Comoound
1. Cadmium
2. Chromium
3. Lead
Blank Value
0.1
<0.3
0.1
Blank Value
<0.1
<0.3
0.1
Blank Value



                                         -126-

-------
                             aquatec
                         Utmtmr ol M»« IneHeap* £nv/n>nm«nta/ Group
                           *8 South P*rt Dnv*. Cokhe*t«r. Vermont 0544*
                              TEL- 802.S5S-1203 FAX 102 6SM2U
   Babcock 4 Wilcox  Company
   R&D  Division,  Att: A/P
   1562  Beeson  Street
   Alliance,  OH 44601
   Attention
Jean  Czuczwa
                                  Date        :
                                  ETR  Number :
                                  Project  No.:
                                  No. Samples:
                                  Arrived     ::
                                  P.O. Number:
                                                  Page
11/05/91
28477
91000
  6
09/13/91
     Standard mtlyiM wtr* ptrforMd In accordant* with N«thod» for Analytlt of Uattr and W«ttn, EPA-600/4/79-020,
     TMI Methods for Eyaluatlng Solid UHT«, SW-K6, or  St*nd«rd M*thod» for th« ExM
       Submitted By
 Aquatec  inc.
                                    -127-

-------