Weekly
            Update
  or More Information:
     Russ Forba, EPA
       457-5042
    forba.russ@epa.qov
    Diana Hammer, EPA
       457-5040
   hammer.diana@epa.qov
   Keith Large, MT DEQ
        841-5039
      klarqe@mt.qov
   Doug Martin, MT NRDP
       444-0234
    douqmartin@mt.qov
           Milltown   Reservoir
                       Sediments
                                              lUperfund  Site
                                                                  Issue #57
                                                                 May 14,2008
Status: The Milltown Project continues to go very well and is on schedule.
Project personnel have worked 1669,400 hours without time lost to injury.
 Peter Nielsen, Missoula (
        258-4968
 Nielsen P© ho.missoula.mt.us

       Websites:
    http://www.epa.gov/
  reqionS/superfund/sites/
       mt/milltown

   http://www.cfrtac.org

                                         Completed removal of the bridge over the spillway on Friday
                                         May 9,2008. Next up: removal of the spillway, radial gate,
                                              and divider black beginning later this month.
      Milltown Reservoir
      Community Office
    (315 Anaconda St., Milltown, MT)

         Office Hours:
    Tuesdays 1:00-3:00  pm
  kEPA and DEQ staff are available
        Stop by to talk
           or say hi!
These weekly updates are intended
  to provide you with the latest
  information about remediation,
       restoration and
  redevelopment activities at the
      Milltown Reservoir.
         US EPA Montana Office
         10 W. 15th St., Ste.3200
         Helena, Montana 59626
Currently.
•  Completed removal of the dam spillway bridge Friday.
•  Completed removal of overbank sediments along the confluence channel. EPA thanks Enviro-
   con for undertaking this Best Management Practice and relocating 43,000 cubic yards of clean
   material out of the floodplain. Preventing these sediments from eroding during high flow this
   spring helps reduce the impacts to aquatic life downstream.
 •  Completed the Clark Fork River outlet/diversion dike road, allowing access to the spillway
   and tunnel pond from the sediment accumulation area 1 (SAA-1) point.
 •  Sediment excavation continues from cells 2 and 5.
 •  Continue loading 45  rail cars each day.  To date, 870,199 tons (756,695 cubic yards) of
   sediment have been hauled to the Anaconda Smelter Superfund Site for use in site reclamation.
 •  Currently pumping 85 gallons per minute (gpm) from 2 wells. Will begin pumping water from
   Tunnel Pond later this week.
•  Re-grading soil stockpiles, sorting concrete stockpiles.
•  Began hauling approximately 15,000 cubic yards of landfill material to Tunnel  Pond for
   disposal. Should be complete this week.
•  This week, sending stockpiled steel to Missoula for recycling;  tires to landfill for disposal.
•  Remnants of an old train were found in Tunnel Pond on Friday; details to follow.
•  Work continues for replacement of State  Highway 200 bridge. Installation of the pier cais-
   sons has been slower than expected but the project is still on schedule overall.
•  Work continues on the Pedestrian Bridge.  The "hybrid" bridge truss has been constructed,
   combining two sections of one of the old trussed with a new middle section.  The re-newed
   bridge will span the Blackfoot River, allowing for  better fish and boat/floater passage.

-------
     Upcoming
        Events
    Tuesday, May 27
    Milltown Redevelopment
    Working Group monthly
    meeting 6:30-9:00 pm at
    Banner Lutheran Church.
Upcoming work:
•   Continue sediment excavation and hauling.
•   Completion of work plan for dam spillway
    removal; removal should begin around the end
    of May and take about 5 months to complete.
•   Work continues on Hwy 200 (MDT) bridge and
    Banner Pedestrian bridge (Missoula County).
•   EPA continues its local well programs.
      To view on-going activities, visit:
 http://www.clarkfork.org/ click on the webcam.
Milltown-Bonner Area  Drinking Water  Well Program
Since beginning its well identification and mitigation program last fall, EPA has re-
placed (or is in the process of replacing) 79 domestic water wells in the Milltown-
Bonner area.  In addition to the residential wells, EPA has also replaced 3 public water
supply wells, serving over a hundred families. These wells were identified through an
extensive survey and data collection effort conducted by Missoula County and the U
of M. All told, EPA is spending over $1,000,000 on well mitigation in the Bonner-
Milltown area. The ground water levels are coming up now with the higher spring
flows and it appears that the groundwater may have reached an equilibrium with the
historic, pre-dam groundwater levels and we may not see any more significant drops in
area groundwater levels.  However, if you have questions or concerns about your resi-
dential well, please call Deb Clevenger, EPA, 457-5004 or 1-866-457-2690 toll-free.
  PROJECT  SCHEDUU
2008  Sediment removal
       Rail hauling sediments
       Build coffer dams
       Powerhouse removal
       Stage 2 drawdown
       MRL bridge mitigation
       Replace  Hwy 200 bridge
       Replace  walking bridge
       Spillway removal
 2009 Sediment removal
                                                      Restoration
                                                      Redevelopment
                                               2010  Restoration
                                                      Redevelopment
                                               2011  Restoration
                                                      Redevelopment
       Looking downstream: Bypass channel (on right) and diversion dike road (on left), May 13, 2008
                         u__j«iHgr;-»
                      Tunnel Pond. Envirocon will begin
                      pumping water out later this week
                     Looking north across the dam spillway, j
                             May 13,2008.
                                                     Safety Reminder
                                                  DURING THE MILLTOWN CLEANUP,
                                                  THE CLARK FORK AND BLACKFOOT
                                                  RIVERS ARE CLOSED TO RIVER REC-
                                                  REATION ABOVE AND  BELOW THE
                                                          PROJECT AREA.

                                                  Clark Fork River users must exit
                                                  the river at Turah Fishing Access;
                                                  Blackf oot River users must exit at
                                                         Weigh Station.

                                                               VIOLATORS and
                                                                TRESPASSERS
                                                               WILL BE FINED.
                                                               For more informa-
                                                                tion, please call:
                                                      MT FWP at 542-5500.
     Please
     Watch
    out for
      Logs!
       When recreating on the
       Clark Fork River below the
       dam, please be aware
       that numerous logs will be
       moving downstream as flow
       increases. The logs should
       stop moving after high flow.
           Be careful, be safe!

-------