Weekly
              Update
    or More Information:
       Russ Forba, EPA
         457-5042
      forba.russ@epa.qov
      Diana Hammer, EPA
         457-5040
     hammer.diana@epa.qov
     Keith Large, MT DEQ
          841-5039
        klarqe@mt.qov
     Doug Martin, MT NRDP
         444-0234
       dmartin@mt.gov
   Peter Nielsen, Missoula Co.
         258-4968
   Nielsen Pİ ho.missoula.mt.us


         Websites:
      http://www.epa.gov/
    reqionS/superfund/sites/
         mt/milltown

     http://www.cfrtac.org
Milltown   Reservoir
            Sediments
                                              Superfund  Site
                                                        Issue #47
                                                                                    k
                                                                                               February 14,2008
                      Only the head wall and the blue penstocks remain from the old Powerhouse, 2/12/08
      Milltown Reservoir1
      Community Office
    (315 Anaconda St., Milltown, MT)

      Winter Office Hours:
     Tuesdays  1:00-3:00  pm
  EPA and DEQ staff are available;
         Stop by to talk
           or say hi!
These weekly updates are intended
to provide you with the latest infor-
mation about remediation, restora-
tion and redevelopment activities at
     the Milltown Reservoir.
           US EPA Montana Office
           10 W. 15th St., Ste.3200
           Helena, Montana 59626
Status: Removal of the Milltown
Powerhouse is underway! Diversion
of the Clark  Fork River into the by-
pass channel  and breaching of the
Powerhouse coffer dam are set for
mid-late March 2008.  Project per-
sonnel have worked 128,146 hours
without time lost to injury.

Currently.
•   The brick walls of the Power-
    house have been removed; all
    that remains is the concrete
    "head" wall.
•   Workers  are installing sheet piling
    upstream of the Powerhouse
•   Removal of the right abutment
    wall of the Milltown Dam struc-
    ture will resume along with re-
    moval of the dam head wall (concrete wall in photo) when the Powerhouse coffer dam is com-
    plete. Demolition should take about 2 weeks and be complete in late February 2008.
•   Continue  loading 45 rail cars each  day with excavated sediment for transportation to the
    repository at the Anaconda Smelter Superfund Site.  449,876 tons (391,197 cubic yards) of
    sediment have been hauled to the Anaconda Smelter Superfund Site for disposal. Site stockpiles
    are nearly depleted; soon Envirocon  will resume excavation of contaminated sediments
•   Resumed  work on the bypass channel berm; recent warm weather sped up progress.  The berm
    is now complete from the west end to the rail bridge; the inlet area should be done in February.
•   Continue  to line the Bypass Channel with reno mattresses and TRM. The lining will protect
    the bypass channel from erosion.  Installation of the reno mattress is 89% complete; TRM is 74%
    complete. All the bypass channel liners should be in place by the end of this month.
•   Excavation of the Bypass Channel inlet is complete. Workers  will now install grade control
    structure, Reno Mattresses, and TRM. The inlet should be complete in the next two weeks.
•   Bypass Channel Outlet grade control structure and work pad are complete;  workers are now ty-
    ing bypass channel erosion control lining into the grade control  structure.
•   Trucks continue to haul rock per day to supply materials for  lining the bypass channel and rip
    rap for the upstream coffer dam. Rock is being hauled to the site from the east and west.
•   Twenty four dewatering wells are producing 2455 gallons per minute (gpm), of which, 2195 gpm
    are discharged into the Clark Fork River and 260 gpm are discharged to the Blackf oot River.
•   1-90 Bridge:  USACE is removing barges from the Blackfoot River. Of the 90 original barges,
    all but 12 have been removed. Each  day, six trucks carrying barges are guided by a pilot car out
    along Tamarack Road and onto Highway 210.  All barges should be out by Monday, 2/18/08.
•   Highway  200 Bridge:  MDT and its contractors continue to make good progress; workers are
    removing  the superstructure of the bridge. The new bridge should be in place this fall.
•   Pedestrian Bridge:  Missoula County continues to remove the old pedestrian bridge. The new
    "hybrid" bridge should be in place this fall.

-------
     Thurs.  February 21
     EPA and Montana Trout
     Unlimited are hosting
     an informational meet-
     ing for  Fly-fishing
     Guides, Outfitters, Fly
     Shop Owners, and
     other river users.
     6:30-8:30 pm in the
     Missoula City Council
     Chambers (140 W. Pine)
     Tuesday, February 26
     Milltown Redevelop-
     ment Working Group
     monthly meeting,
     6:30-9:00 pm at Our
     Savior's Lutheran
     Church  in Banner.
     Weds.  March 12
     EPA/DEQ Project
     Update Open House
     (5:30-6:30 pm) and
     Public Meeting (6:30-
     8:30 pm) in the Banner
     School Gym.   EPA will
     provide an update re:
     cleanup activities, di-
     version of the Clark
     Fork River; Breach of
     the coffer dam; Fish-
     eries impacts; Ground-
     water modeling; Well
     program; Restoration;
     and Redevelopment!
      Juestions/discussion.
              ty reasons, the PROJECT
              ncluding the nearby rivers,
            is CLOSED TO THE PUBLIC.
            A posted guard will allow
          ly authorized personnel  on site.
           To view on-going activities:
http://www.clarkfork.org/programs/milltown.html
   Made possible by donations from Envirocon, MRL, and Modern Machinery
  coming work:

  Continue bypass channel berm construction up-
  stream of the rail bridge
  Continue reno mattress and TRM installation
  Continue hauling rock for bypass channel liner
  Continue removal of the right abutment/head wall
  Install grade control structure at inlet
  Finish Powerhouse coffer dam
  Begin dewatering coffer dam
  USACE removing barges from the Blackfoot River
  MDT continues work on the Hwy 200 bridge
  County continues work on the Pedestrian bridge
  EPA continues its local well programs
                                                                                   PROJECT SCHEDUU
                                                                                 2008

2009
 Build coffer dam
MRL bridge mitigation
Powerhouse removal
Stage 2 drawdown
Sediment removal
Rail hauling sediment
Replace Hwy 200 bridge
Replace walking bridge
Spillway removal
Sediment removal
Raul hauling sediment
                                                  Oil
        Restor
        Redevelopment
        Restoration
        Redevelopment
        Restoration
        Redevelopment
Removing barges from the Blackfoot River, 2/12/08. The 90
barges created a work platform during 1-90 bridge mitigation.
             Installation of sheet piling as part of the coffer dam upstream
                     of the Milltown Powerhouse, 2/12/08.
                        2/12/08, Tying bypass channel liner into the grade control structure at the
                        bypass channel outlet. In a few weeks, the Clark Fork River will be diverted
                         into this channel, isolating the river from the contaminated sediments.

-------